DRAFT SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT
    Wastewater Treatment Facilities for the Columbus, Ohio Metropolitan Area
                                 Prepared by the
                 United States Environmental Protection  Agency
                                    Region V
                               Chicago, Illinois
Science Applications
International Corporation
McLean, Virginia
                                      and
With
Triad Engineering
Incorporated
Milwaukee, Wisconsin
                                 December 1987
                                                  Approved  by:
                                                 Valdas T7  Adamki
                                                 Regional Administrator

-------
        APPENDIX A

   BRIEFING PAPER NO. 1
WASTEWATER FLOWS AND LOADS

-------
BRIEFING PAPER NO. 1
WASTEWATER FLOWS AND LOADS
Supplemental Environmental Impact Statement
USEPA  Contract No.  68-04-5035, D.O.  No. 40
Columbus Ohio "Wastewater Treatment Facilities
Prepared By:

SCIENCE APPLICATIONS INTERNATIONAL CORPORATION

TRIAD ENGINEERING INCORPORATED

-------
                          WASFKWATKR FLOWS AND LOADS
 I.    TliRMS AND DEFINITIONS

 2.    AVAILABLE DATA

 3.    ANALYSIS OF AVAILABLE DATA

      3.1  General
      3.2  Dry Weather Flows
      3.3  Water Usage
      3 4  Wet Weather Flows

4.    EXISTING AND PROJECTED FLOWS AND LOADS

     4.1  Fxisting Wastewater Flows
          4.1.1  Existing Average Flows
                 4.1.1.1  Infiltration
                 4.1.1.2  Industrial and Commercial Flows
                 4.1.1.3  Domestic Flows
          4.1.2  Maximum Hourly Flows
          4.1.3  Peak Process Flow
          4.1.4  Wet Weather Flows
     4.2  Existing Wastewater Loads
     4.3  Projected Flows and Loads

5.    FACILITY PLAN METHODOLOGY

      5.1  Dry Weather Wastewater Flows
     5.2  Design Average Daily Flows
      5.3  Design Wastewater Loads
     5.4  Industrial Flows and Loads
     5.5  Projected Flows and Loads
          5.5.1  Design Flows
          5.5.2  Design Loads

6.   COMPARISON OF BRIEFING PAPER AND FACILITY PLAN FLOWS AND LOADS

-------
                                 INTRODUCTION

     Under the direction of USEPA, a series of briefing papers are being
prepared addressing key issues in the development of the Supplemental
Environmental Impact Statement for the Columbus,  Ohio,  Wastewater Treatment
Facilities.  The briefing  papers  form the basis of discussions between Triad
and USEPA to resolve important issues.  The following paragraphs present the
background of the facility planning process, a description of the briefing
papers, and the purpose of this paper on flows and  loads.

FACILITY PLANNING PROCESS
     At the time this paper was prepared (March-August  1987) the city of
Columbus was proceeding to implement improvements at the Jackson Pike and
Southerly Wastewater Treatment Plants to comply with more stringent effluent
standards which must be met by July I,  1988.    These improvements  were based
on the consolidation of wastewater treatment operations at the Southerly
plant.   This  one-plant  alternative  is  a  change  from  the two-plant operation
proposed by the city in the  1970's and  evaluated in the 1979 EIS.

     The development and documentation of wastewater treatment process and
sludge management alternatives for the Columbus metropolitan area has been an
extended and iterative  process.    The design and  construction of various
system components have progressed, because of the 1988  deadline,  while
planning issues continue  to be resolved. As  a  result,  numerous  documents have
been prepared which occasionally revise a previously established course of
direction.

     The concurrent  resolution of planning issues and implementation of
various project components has made preparation of  the  EIS  more difficult
because final facility  plan recommendations are not available in a single
document.
                                     A-l

-------
BRIEFING PAPERS
     To facilitate preparation of the EIS,  a series of briefing papers are
being developed.   The purpose of the briefing papers  is to  allow USEPA to
review the work of the EIS consultant and to identify supplemental  information
necessary for the preparation of the EIS.   Six briefing papers  are  being
prepared as follows:

     •  Flows and Loads
     •  Sludge Management
     •  CSO
     •  Process Selection
     •  One Plant vs. Two Plant (Alternative Analysis)
     •  O&M and Capital Costs

     The specific focus of each briefing paper will be different.   However,
the general scope  of  the  papers  will adhere  to the  following format:

     *  Existing conditions will be documented.
     •  Evaluations,  conclusions, and recommendations of the facilities
        planning process will be reviewed using available documentation.
     •  Where appropriate, an independent evaluation  of the future  situation
        and viable alternatives will be prepared.
     •  The facility  plan and EIS briefing  paper conclusions will be  compared.

     The briefing paper process is intended to:

     •  Prompt the resolution of any data deficiencies.
     •  Clearly establish and define existing and  future conditions.
     •  Identify the  final recommended  plan which  the city  desires  to  implement..
     •  Provide a data base of sufficient detail to allow preparation of the
        draft EIS.
                                    A-2

-------
WASTEWATER FLOWS AND LOADS
     This briefing paper presents an independent evaluation of wastewater
flows and loads which is based on an analysis of operating records from the
Jackson Pike and Southerly Wastewater Treatment Plants and the 1985 Revised
Facility Plan Update.  The determination of wastewater flows and loads is a
key factor in the sizing of facilities,  the evaluation of treatment alterna-
tives, and the evaluation of solids management scenarios.  Design flows and
loads are presented for the 20-year planning  period which ends in 2008.  This
document  is divided into six  sections.

     •  Terms and definitions
     *  Available data
     •  Analysis of available data
     •  Existing and projected flows and  loads
     •  Facility plan methodology
     •  Comparison of facility plan and  briefing paper flows and loads
                                     A-3

-------
                          1.  TERMS AND DEFINITIONS
 BOD  or Biochemical  Oxygen Demand.  An index of the amount of oxygen required
 for  the biological  and chemical oxidation of the organic matter in a liquid.

 Combined  Sewer:  A  sewer which transports both wastewater and storm or surface
 water  in  a single pipe.

 Commercial/Industrial  Flow.  Wastewater flows  from commercial businesses and
 industry.

 Design Average Flow;  The 24-hour average flow which the upgraded and expanded
 treatment facilities will be sized and designed to process.

 Diurnal Peaking Factor:  The factor  applied  to  the design average  flow to
 account for the maximum flow rate occurring  at  the wastewater treatment plant
 over a given 24-hour period.   The  peaking factor  is calculated as the maximum
 hourly flow rate divided by the average hourly flow rate.

 Domestic Flow:  Residential sewage flow.

 *Dry Weather/No Bypass Flow Condition*  Dry weather days when there were no
 reported raw or settled sewage bypasses at the Southerly WWTP and no recorded
 hours of operation at the Whittier Street Storm Tanks.

 *Dry Weather Flow Condition.  Any day when precipitation does not occur on a
 particular day or during the day immediately preceding it.

Effluent.   The flow  out of a process.

 High Groundwater Infiltration:   Infiltration to sewers  that  occurs  during
 periods of extended  wet weather when the level  of the groundwater is high.

 Infiltration;   Water other than wastewater that enters  a sewerage  system,
 including sewer service connections, from the  ground through such  sources as
defective pipes,  pipe joints,  connections, or  manholes.   Infiltration  does not
 include,  and is distinquished  from,  inflow.

 Inflow or Rain Induced Flow;  Water other than wastewater that enters  a
sewerage system, including sewer service connections, from sources  such as
 roof leaders,  cellar drains,  yard drains, area drains,  foundation drains,
manhole covers,  cross connections  between storm sewers  and sanitary sewers,
catch basins,  cooling towers, storm  waters,  surface  runoff,  street  wash
waters, or drainage.  Inflow does  not  include,  and  is distinguished  from,
infiltration.
                                     A-4

-------
Force Main;  A sewer conduit which is pressurized by pumping.

Influent;  Flow into a process.

Low Groundwa ter Inf111 ration;  Infiltration that occurs during periods of
extended dry weather when the level of the groundwater is low.

SanitarySewer;  A conduit intended to carry liquid and  water-carried wastes
from residences, commercial buildings, industrial plants, and institutions
together with minor quantities of ground, storm, and surface waters that are
not admitted  intentionally.

Storm Sewer;  A sewer designed to carry only storm waters, surface run-off,
street wash waters, and drainage.

*Wet Weather  Flow CondjU:ions;  Any day (or days) on which measurable precipi-
tation occurred and  the  single  day  following any day on  which precipitation
occurred.   The day following  any  day  on  which  precipitation occurred is
defined as wet weather due to  the lag  in  the peak rain-induced flow  which is
seen at the plants  as  a result of in-system travel  time.  Defining the
following day as wet weather also accounts for the  effect of in-line storage
following extended periods of wet weather.

*These definitions  were developed for the analysis  contained in this document.
 They are not standard definitions.
                                     A-5

-------
                              2.  AVAILABLE DATA

     The  1985 and 1986 operating records from Che Southerly and Jackson Pike
 WWTPs  were reviewed to determine existing  and projected design flows and
 loads.   The following plant records  were obtained  from the city of Columbus
 and Ohio  EPA.

     •  Monthly Operating  Reports for both plants from January 1985 through
        December 1986.
     •  Monthly Report of Operations for the Jackson Pike  WWTP from January
        1985 through December 1985.
     •'  Monthly Report of Operations for the Southerly WWTP from January 1985
        through September 1986.
     •  Hours of operation of the Whittier Street Storm Tanks from January
        1985 through December 1986.
     *  Hourly flow data for both plants for February and September 1985.
     »  1985 monthly water consumption records for the Columbus Area.
     •  1983 Industrial Pretreatment Report - Malcolm Pirnie.
     •  Sewer lengths and sizes for  the  Columbus Sewer System.

     The Monthly Operating Reports (MORs) are submitted to Ohio EPA in
accordance with the NPDES permits.   Influent  flow  and load data were obtained
from these reports.  However, these  reports did  not  contain precipitation
data.   This information was obtained from the  Monthly Report of Operations
which is submitted  to  the Ohio Department  of Health.

     The Southerly  MORs include data on  amounts  of raw sewage bypassed and
settled sewage bypassed as well as  treated flow.  The Southerly plant has  a
method of treatment termed Blending  of Flows.  When  incoming flows increase to
the point  where the biological portion of the plant  begins to show signs of
potential  washout,  the flow  to the biological part of the plant is fixed.   The
increase in flow above this  fixed flow,  but less than the capacity of the
primary tanks,  is bypassed  around  the biological portion and blended  with  the
final effluent,  thus,  receiving only primary treatment and chlorination.
                                     A-6

-------
These  flows  are  reported  on  the  MORs as  settled sewage bypassed.  If the
primary  treatment  facilities are operating at capacity, then all excess flows
are bypassed directly to  the Scioto  River through a 108-inch diameter pipe
originating  in the screen building.   These  flows are reported on the MORs as
raw sewage bypassed.  After  August of  1986, no blending of flows was recorded
in the MORs  for the Southerly WWTP,  however, bypassing  was  still  reported.

     The Jackson Pike MORs provide flow  monitoring  data for the plant.
Jackson Pike does not blend as Southerly does,  nor do they bypass raw sewage.
The major  diversion point for Jackson Pike flows occurs at the Whittier Street
Storm  Tanks  before the  flows even  reach  the plant.  The tanks are capable of
acting as  a holding system for the excess flows until the flow  in the
interceptor subsides and they can be  bled back  into  the system and carried to
the Jackson Pike plant.   If the flows exceed the capacity of the tanks,  they
overflow to  the  Scioto  River.  Flows can also be directly bypassed along side
the tanks,  through an emergency bypass,  to the  Scioto  River.

     Flow  monitoring did not take place at the  Whittier Street Storm Tanks
until November of  1986.   However, hours of operation of the storm tanks  were
recorded during 1985 and 1986 on the Monthly Report of Operations.  The fact
that hours of operation were reported does not  necessarily mean there was
bypassing  or overflowing occurring at the tanks.  It only means that the gates
were open  and flows were  being diverted  into the  tanks.  In November of 1986,
the city   began monitoring the overflow but not the bypass.  Therefore,  the
data is still incomplete with respect to determining the total volume of flow
entering the Scioto River at the  Whittier Street facility.

     Hourly flow data was obtained for February and September of 1985 for both
plants.  These months represent the periods of minimum and maximum water
consumption  respectively.   This hourly flow data was used to determine a
diurnal peaking factor which is calculated by dividing  the  peak hourly  flow by
the average hourly flow.  This  diurnal  peaking  factor is multiplied  by the
design average  flow to determine  a  peak hourly  flow  for use  in sizing the  wet
stream treatment facilities.
                                     A-7

-------
      Dry  weather flows were determined through an analysis of 1985 and 1986
 flow data.  However, only 1986 flow data was used to determine wet weather
 flows.  An analysis of  1985 MOKs showed  that data on raw and settled sewage
 bypasses  at Southerly  were  not complete.  Up until August of 1985, only a
 bypass  flow  rate (MGD)  was  reported with no duration specified.    These
 bypasses  did not  always occur 24 hours a day, therefore, these  rates could not
 be  converted to  the volume  bypassed during that day.  In August of 1985,
 monitoring of the duration of the bypasses began which  provided  a  more
 accurate  determination of the volume of  the bypasses.   Therefore, the 1986
 calendar year data were used to estimate wet weather flows.

 Wet weather total system flow can not be determined solely based on the volume
 of  flow arriving at the Jackson Pike and  Southerly WWTPs.   There are  numerous
 points of combined sewer overflow throughout the Columbus Sewer System.  The
 Jackson Pike service area has  several regulator  chambers and  overflow
 structures in addition to Che Whittier Street Storm Standby Tanks  discussed
 previously.   The Southerly  service  area includes an  overflow structure at
 Roads End and the Alum Creek Storm Standby Tank.  There is no comprehensive
 flow  monitoring  data available for the regulators, overflows, and storm  tanks.
 The city began monitoring the overflows dt the Whittier Street  facility in
 November  of 1986.  However,  they  did not  monitor the bypass line at the
 Whittier  Street  facility.   The city also began monitoring some  of the other
 points of combined sewer overflow,  but  according to  the  MORs, the  flow
 monitoring equipment malfunctioned frequently  which provided no data.  Thus,
 the only flow data included  in the wet  weather  analysis,  other than plant flow
data, was that which was reported for  the Whittier Street overflow during
November  and December.

     The Industrial Pretreatment Report prepared by  Malcolm Pirnie in 1983 was
used to estimate the industrial and commercial  flows.   This report quoted
 figures on industrial  and commercial flows based on  1980 water and sewage
 records.  Due  to the lack of more recent quantification of industrial and
commercial flows, these figures were updated for this document using 1985
 population figures.
                                     A-8

-------
                        3.  ANALYSIS OF AVAILABLE DATA
     The following sections present an analysis of the wastewater flow data.
This analysis was developed independently of that presented in the facility
plan as a check of the assumptions and methodologies.    It was prepared using
Monthly Operating Reports (MORs)  for the Jackson Pike and Southerly  WWTPs and
precipitation data and water usage records for the city of Columbus.   Using
these records, wet weather and dry weather flows were developed for each
plant.   Dry weather flows were compared to water consumption data to aid in
the interpretation of monthly flow variations.

3.1  GENERAL
     Jackson Pike and Southerly MORs and precipitation data for the 1985 and
1986 calendar years were used  to establish existing wastewater flows.   The
following sections will discuss existing wet weather and dry weather flows.

     In order to determine wet and dry weather flows,  each daily  record  was
categorized accordingly.   Wet  weather was defined as any day on which
measurable precipitation occurred and the  single  day  following the last  day on
which precipitation occurred.   The day following one on which precipitation
occurred is defined in this analysis  as  wet weather  due to the lag in  the peak
rain induced flow which is seen at the  plants.  This  lag is a result of  in-
line storage and in-system travel  time.  The  remainder of the daily  records
were categorized as dry weather.  Weather conditions for 1985 and 1986 are
summarized in Table 3-1 using  these classifications.   There  were  a total  of
144 days in 1985 and 130 days  in 1986 on which measurable precipitation
occurred.   Wet weather days totaled 212 for  1985 and  197 for 1986.   There were
153 dry weather days  for  1985 and 168 for 1986.
                                      A-9

-------
                   TABLE  3-1.   WEATHER CONDITION SUMMARY
Precipitation*
Month
1985
January
February
March
April
May
June
July
August
September
October
November
December
TOTAL
1986
January
February
March
April
May
June
July
August
September
October
November
December
(inches)

1.14
1.67
3.42
0.73
3.92
1.41
1.65
2.34
1.18
1.98
10.67
1.18
31.29

1.54
2.96
2.61
1.31
2.47
5.53
3.60
1.61
3.44
4.16
3.00
2.81
TOTAL
35.04
 Days of Measurable
Precipitation (Count)
                           16
                           12
                           17
                           11
                           12
                           12
                            5
                           10
                            4
                           11
                           21
                           13

                          144
                           12
                           16
                           11
                           13
                           13
                           11
                            8
                            6
                            8
                            9
                           11
                           12

                          130
                                                    Wet Weather   Dry Weather
                                                    Days (Count)  Days (Count)
                             21
                             17
                             24
                             17
                             17
                             20
                              7
                             16
                              6
                             18
                             28
                             21

                            212
                             16
                             22
                             17
                             21
                             19
                             17
                             13
                             11
                             13
                             13
                             18
                             17

                            197
                                                                      10
                                                                      11
                                                                       7
                                                                      13
                                                                      14
                                                                      10
                                                                      24
                                                                      15
                                                                      24
                                                                      13
                                                                       2
                                                                      10

                                                                     153
                                                                      15
                                                                       6
                                                                      14
                                                                       9
                                                                      12
                                                                      13
                                                                      18
                                                                      20
                                                                      17
                                                                      18
                                                                      12
                                                                      14

                                                                     168
Measured at Port Columbus Airport
                                    A-10

-------
3.2  DRY WEATHER FLOWS
     Construction Grants 1985, which is the USEPA guide for the preparation of
facility plans, recommends that design flows for treatment works be determined
based on existing base flow;  estimated future flows from residential,  com-
mercial,  institutional  and industrial  sources;  and nonexcessive I/I.
Traditionally, base flows are established using dry weather flow.

     Dry weather days were classified  as indicated in the previous section.
By definition, they include any day on which measurable precipitation does not
occur that day or during the day immediately preceding it.  In applying this
definition to plant data, it was found that bypasses occurred in the  system on
several days which would be categorized as  dry weather.   Bypasses  are
monitored at  the Southerly WWTP and reported in the records as settled sewage
bypassed and raw sewage bypassed.   The  Jackson  Pike WWTP does  not  bypass  at
the plant.  However, when flows increase beyond plant capacity, the gates are
opened at the Whittier Street Storm Tanks and flows are  diverted to the tanks
before they reach the Jackson Pike  WWTP.   When the gates are open at  the
Whittier Street facility, it is considered  to be in operation.   Flows  diverted
through the Whittier Street Storm Tanks were not monitored until November of
1986, but the hours of operation  of the storm tanks are  reported on the
Jackson Pike WWTP  records.  Days with reported hours  of  operation  were
considered as bypass days.

     Closer examination of  the days  with  reported bypassing and storm tank
hours showed  that the majority occurred after  an extended wet  weather period.
Those that did not  follow an extended wet  weather period were assumed  to be
related to operational problems at  the  plant.   Therefore,  in  establishing dry
weather flows, only dry  weather/no bypass days were considered.

     Using the classification of dry weather/no bypass, monthly  average flows
were determined for the  1985 and 1986 calendar year.   These  flows  are
presented in Table 3-2.   In evaluating  these  flows,  the  1985 and 1986  averages
for each plant were very close.  The maximum and minimum combined  values  both
                                     A-ll

-------
    TABLE 3-2.  DRY WEATHER/NO BYPASS MONTHLY AVERAGE FLOWS (MGD)
        Month
Count
Jackson Pike
Southerly    Combined
        1985
January
February
March
April
May
June
July
August
September
October
November
December
TOTAL
AVERAGE
1986
January
February
March
April
May
June
July
August
September
October
November
December
TOTAL
AVERAGE
7
5
2
3
8
9
19
11
24
11
0
5
104


10
0
1
a
11
10
13
20
17
10
2
8
UO

75.86
79.20
82.00
81.30
83.88
78.89
80.47
75.18
73.38
72.31
ND
81,62

77.27

78.53
ND
80.73
82.52
76.66
80.33
81.32
77.13
75.87
78.08
70.30
79.06

78.33
56.44
60.74
60.55
58.92
60.88
55.14
58.40
51.85
50.64
52.57
ND
61.54

55.40

56.23
ND
62.50
57.69
48.21
58.34
55.79
55.74
55.18
53.25
54.30
60.98

55.52
132.30
139.94
142.55
140.22
144.76
134.03
138.87
127.03
124.02
124.88
ND
143.16

132.67

134.76
ND
143.23
140.21
124.87
138.67
137.12
132.87
131.05
131.33
124.60
140.04

133.85
ND - No dry weather/no bypass days
                                      A-12

-------
occurred in 1985.   The dry weather combined maximum monthly average of 145 MGD
occurred in May of 1985,  and  the dry weather combined minimum monthly average
of 124 MGD occurred in September of 1985.

     The maximum  monthly average dry weather flow of 145 MGD which occurred in
May is considered to represent a high  groundwater condition due to the large
amount of precipitation and extended wet weather periods in this month.   It
had the second highest monthly precipitation for 1985 of 3.92 inches.   The
highest occurred in November, but there were no dry weather/no bypass days in
November.  May had eight  dry  weather/no bypass  days  which occurred  during  two
4-day  periods.

     The minimum  monthly average dry weather flow of 124 MGD which occurred in
September of 1985 is considered  to represent a  low groundwater condition  due
to the extended dry period  which occurred during that month.  September of
1985 had 24 dry weather/no  bypass days  which  occurred during one 22-day period
and one 2-day period.  This was the  highest  number of dry weather/no bypass
days recorded in one month  for the  24  month  (1985 and 1986)  data base  that  was
evaluated.

     The 1985 flows closely approximate the 1986 dry weather/no bypass maximum
monthly average of 143 MGD  and the minimum monthly average  of 125 MGD.

3.3  WATER USAGE
     Information on water usage for  the Columbus  area was obtained from the
Columbus Division of Water  -  1985 Annual Report.  These flows  were evaluated
to gain further insight  into  the groundwater condition.  The  total  amount  of
water pumped to residential,  commercial, and  industrial customers  in the
Columbus area during the  1985 calendar year  was 44 billion  gallons.  Using
the 1985 population figure  of 870,000  people, developed by Ohio  Data Users
Center, the water usage  figure was converted to 139 gallons per capita per day
(gpcd).
                                     A-13

-------
     The 1985 average dry weather/no bypass flow of 136 MGD from Table 3-2 can

be converted to 156 gpcd using the population figure for 1985  of 870,000

persons.  The per capita water pumpage (139 gpcd) value is 17  gpcd  or approxi-

mately  12 percent less than the wastewater (156 gpcd) value.   This  17 gpcd

difference may be the result of high infiltration in the sewer system, not all

the sewer customers being water customers, or a result of illegal connections

to the sewer system.


     Table 3-3 compares the monthly average  water pumped to the Columbus area

vs.  monthly average  dry weather/no bypass  wastewater flows.  The table shows a

higher wastewater flow than water  pumpage for the spring months. This could

be due to more sewer customers than water  customers as discussed in the

previous paragraph.   However,  it  could  also be  a  result  of a greater amount of

infiltration from a high groundwater condition.  September, on the  other hand,

which had 24 dry weather/no bypass days had  an  average water pumpage figure

17.72 MGD greater than the wastewater  figure.   The  high water  pumpage figure

could be attributed  to lawn sprinkling due to the extended dry period.  The

low wastewater flow  indicates that less infiltration is entering the system,

which is a result of a low groundwater condition.


              TABLE  3-3   1985  WATER PUMPAGE  VS. WASTEWATER FLOW
          Month

        January
        February
        March
        April
        May
        June
        July
        August
        September
        October
        November
        December
Average Water
Pumped (MGD)

   111.23
   108.32
   109.65
   115.60
   120.33
   128.53
   127.15
   130.66
   141.74
   124.88
   117.23
   116.46
Average Dry Weather/
No Bypass Flow

      132.30
      139.94
      142.55
      140.25
      144.75
      134.03
      138.87
      127.03
      124.02
      124.88
        ND
      143.16
                                     A-14

-------
3.4  WET WEATHER FLOWS
     A limited data base was reviewed with respect to wet weather flows.
Insufficient data was available to quantify the total wet weather  flow for  the
entire Columbus system.

     The only data evaluated in determining wet weather  flows  was  that which
was reported from monitoring flows arriving at the plants  from January through
December 1986 and data reported from  monitoring overflows  at the Whittier
Street Storm Tanks during November and  December of 1986.  The  flow data
collected at the Southerly and Jackson  Pike plants is the  only data  that was
collected for an entire year.   Flow data was  collected at the  overflow located
at the Whit tier Street Storm Tanks during November and December of 1986.
However, no flow data was gathered from the bypass at Whittier Street.  From
October through December of 1986,  flow  monitoring  was performed at various
other overflows and regulators  within the Columbus combined sewer  system.
However, it was never performed at all  the points  of  combined  sewer  overflow
during the same month, and according  to the MORs,  the flow monitoring
equipment malfunctioned frequently.

     Wet weather days  were  categorized as discussed  in Section 3.1.  Wet
weather being defined as any day on which measurable  precipitation occurs and
the single day immediately following  any day  on which measurable precipitation
occurs.

     A total flow was calculated  for each wet weather day during  1986.   This
total  flow includes the following:

     •  Southerly treated sewage.
     •  Southerly settled sewage  bypassed.
     •  Southerly raw sewage bypassed.
     •  Jackson Pike treated sewage.
     •  Whittier Street sewage overflow volumes (November and  December only).
                                     A-15

-------
     Table 3-4 shows Che average and  maximum daily wet weather flows for
January through December of 1986.  As shown in the table, the maximum  wet
weather flow of 309.52 MGD occurred in March.  The actual day was March 14,
1986.   On March 12, the reported precipitation was 0.71 inches and 0.51  inches
was reported for March 13.  It must  be  remembered that this flow only
includes the flow arriving at the plants.   It does not include any bypassing
that may have occurred at the numerous  points of  combined sewer overflow
throughout the system.

     Wet weather flows are discussed  in more  detail  in the  CSO briefing  paper.

                      TABLE 3-4.  WET WEATHER FLOW DATA
                         Wet Weather
Maximum
Month
January
February
March
April
May
June
July
August
September
October
November
December
Total
1986
Days (Count)
16
22
17
21
19
17
13
a
13
13
18
17
197

Daily Average (MGD)
165.31
298.62
309.52
155.02
160.98
227.60
184.29
158.61
165.23
266.00
223.73
294.24

309.52
Average (MGD)
147.73
183.01
181.62
143.68
137.46
152.45
154.75
137.00
147.27
161.47
149.80
178.64

156.24
                                    A-16

-------
                   4.   EXISTING  AND  PROJECTED  FLOWS AND LOADS

      This  chapter  describes Che development of average daily and peak hourly
 flow rates and daily loadings of  TSS  (total suspended solids) and BOD which
 are  used to evaluate facility planning recommendations. The following sections
 present  the existing flows and  loads developed for the Columbus WWTPs from an
 independent analysis of  the 1985  and  1986 plant data, as well as projected
 flows and  loads for the  2008  design year.

      An analysis of existing  conditions established  the current average day
 flows.  This current condition  is subsequently dissagregated into domestic,
 infiltration,  industrial, and commercial flows.  A diurnal peaking factor and
 a process  peaking  factor are  established to project peak flow rates which will
 be used in sizing some of the  WWTP unit processes.  Wet  weather flows are
 discussed  briefly  with a more detailed discussion  included  in  the  CSO packet.

      The analysis also includes  a review of existing influent 800 and TSS
 loads.   BOD and TSS loads are used to determine sizings for WWTP unit
 processes  and  to aid in the selection of the alternative treatment processes.

      Wastewater flows  and  loads are projected for  the design year  (2008) using
 existing per capita flows and loads and 2008 population projections.

4.1  EXISTING WASTEWATER FLOWS
     This  section presents the existing average flow, maximum hourly flow,
 peak process flow,  and  wet  weather flow as determined from analysis of
available  data.

4.1.1  Existing Average Flows
     According to USEPA guidelines,  WWTP design flows are determined based on
existing dry weather flows and  non-excessive  I/I.   As discussed in  Section
3.2,   dry weather flows were determined based on a dry  weather/no bypass
condition.  Therefore,  the existing average flow was  determined through  an
                                     A-17

-------
 analysis of dry weather/no bypass flows.   The  1985 and  1986 combined Jackson
 Pike and Southerly maximum monthly average dry weather/no bypass flow from
 Table 3-2  was selected.   This  combined  flow  of 144.76 MGD occurred in May of
 1985 and was based on 83.88 MGD  for  Jackson  Pike  and  60.88 MGD  for  Southerly.

      In  subsequent  paragraphs, this  flow of  145 MGD is  further broken down into
 infiltration,  industrial,  commercial,  and  domestic  flows.   In Section 4.3,
 population  projections are used  to increase  this  flow for  the design  year.

 4.1.1.1  Infiltration
      No  current  infiltration/inflow  report was available for the Columbus
 sewer system;  therefore, wastewater  flow,  water use,  and precipitation data
 were  evaluated  to  estimate infiltration.

      The maximum monthly  average dry weather/no bypass flow of 145 MGD
 occurred in May of  1985.  The data base consists  of  two 4-day periods of dry
 weather/no  bypass conditions.  This month, which  had  3.92 inches of
 precipitation,  had  the second  highest monthly  rainfall  recorded during  1985.
 Therefore, it is safe to assume that  May would  represent a  high groundwater
 condition resulting in increased infiltration.  November had the highest
 precipitation with  10.67  inches,  but  there  were no dry weather/no bypass days
during that month.

     September of 1985 had the lowest combined  monthly average dry weather/no
bypass flow of  124.02 MGD for the 1985 and 1986 calendar years;  and it had
24-dry weather/no bypass days which  occurred in one 2-day period and one
 22-day period.  Due to the extended dry  weather period,  it  is  assumed to
represent a low groundwater condition.  Water usage figures presented in
Section 3.3  reinforce May  and  September  as  representing  high and  low
groundwater conditions.  The difference of 20.74 MGD between the high
groundwater month (May) and the low groundwater month  (September) represents
that portion of the total  infiltration which is attributable to a high
groundwater condition. However,  this is only a portion  of  the total  amount of
                                     A-18

-------
 infiltration  occurring  since  there  is also some  infiltration occurring during
 low groundwater conditions.   Therefore, the amount of infiltration occurring
 during  low groundwater  conditions must be determined and added to the  20.74
 MGD in  order  to establish  a  total infiltration  rate.

      In the absence of  a current  infiltration/inflow report other methods of
 estimating infiltration must  be used.   A common method involves using monthly
 water records to establish the domestic, commercial, and industrial portion of
 the wastewater flow.  The remainder of the wastewater flow is then assumed to
 be  infiltration.

      Since  September  1985 has been established as a low groundwater month,
 water usage rates from  this month will be used.   As reported in Table 3-3, the
 September  1985 water  pumpage rate is  141.74 MGD.  Literature states that
 approximately 60 to 80 percent of water becomes  wastewater.   The 20 to 40
 percent which  is lost includes water consumed by commercial and manufacturing
 establishments and water used for street washing, lawn sprinkling, and
 extinguishing  fires.   It also includes water used by residences that  are not
 connected to the sewer system as  well  as some leakage  from water mains and
 service pipes.  If it  is assumed that  70 percent of the  water becomes
 wastewater, then the return flow  for September would be 99.22 MGD. Referring
 to Table 3-3,  the wastewater  flow for September  is  124.02 MGD.   The difference
 between the actual wastewater flow (124.02) and the expected wastewater  flow
 (99.22)  is  24.80 MGD.   This value  is assumed  to  represent the amount  of
 infiltration occurring during a low groundwater condition.   Thus,  the total
 infiltration occurring during high groundwater conditions is obtained by
adding 20.74 MGD to 24.80  MGD.  This total infiltration figure  of 45.54  MGD,
converts to 52 gpcd.

     It  must be remembered that 52 gpcd is only  a rough  estimate of
 infiltration.   It is not known if  all of the water customers are sewer
customers or if all the  sewer customers  are water customers.  Some sewer
customers may  have their own private wells.   In addition, the consumptive use
of the brewery and the other industries is unknown.
                                     A-19

-------
      It  is, however, considered to be a non-excessive infiltration rate when
 compared to infiltration rates in the USEPA document entitled Facility
 Planning - 1981 Construction Grants Programs.  This document states that 2000
 to 3000  gpd/inch-diameter mile is considered a non-excessive infiltration rate
 for  sewer systems with lengths greater than 100,000 feet.  The Columbus Sewer
 System has a.  total length of 9,975,000 feet which converts to an estimated
 32,930 inch-diameter miles.  Multiplying the inch-diameter miles by 2000
 gpd/inch-diameter mile results  in 66  MGD or 76 gpcd.  Therefore, 52 gpcd of
 infiltration  would be  considered non-excessive.

     The  Revised  Facility Plan Update uses a peak infiltration rate of 72
 gpcd.  Divided between the two plants, it is 82 gpcd for Jackson Pike and 58
 gpcd for Southerly.  Assuming more  detailed information was available to
 establish this number  for the facility plan and considering 72 gpcd is also a
 non-excessive infiltration rate according to the  USEPA  document,  it will be
 used in  this  briefing  paper as the existing infiltration rate.  It converts to
 22.1  MGD for Southerly and 40.1 MGD  for Jackson Pike,  totaling 62.2 MGD for
 the entire Columbus Sewer System.  This number will be held constant through-
 out  the  planning  period.

4.1.1.2  Industrial and Commercial  Flows
     Current information on industrial and  commercial wastewater flows was not
 available. Therefore,  estimates were  made by updating  those values presented
 in the Columbus Industrial Pretreatment Program Report as prepared by Burgess
and Niple.  The Burgess and  Niple values  were updated proportional to the
 increase in population from 1980 to 1985 since they were based on 1980 water
consumption records.   The  1985 Estimates  of industrial and commercial  flows
are presented in  Table 4-1.
                                      A-20

-------
            TABLE 4-1.  INDUSTRIAL AND COMMERCIAL FLOW ESTIMATES
Jackson Pike
Southerly
TOTAL
1980
Population
472,503
368,228
840,731
1980
Industrial
Flow (MGD)
8.7
6.7
15.4
1980
Commercial
Flow (MGD)
4.3
3.1
7.4
1985
Population
489,000
381,000
870,000
1985
Industrial
Flow (MGD)
9.0
6.9
15.9
1985
Commercial
Flow (MGD)
4.5
3.2
7.7
     The analysis of variations in the dry weather/no bypass flows between
weekdays and  weekends  gives  an indication of  the magnitude  of the industrial
and commercial  flows.  Table 4-2 presents a summary of the weekly flow
variations  for  the  two plants.

      TABLE 4-2.  1985 DRY WEATHER/NO BYPASS WEEKLY FLOW VARIATIONS (MGD)

                              Jackson Pike      Southerly      TOTAL
          Weekday                78.71            55.37       134.08
          Weekend                73.80            54.92       128.72
          Difference              4.91             0.45         5.36
          % Difference            6.2              0.8          4.0
            From Weekday

     Referring to Table 4-1,  it can be seen that the total commercial and
industrial flow for Jackson Pike in 1985  is 13.5 MGD.   Relating  this to the
4.91  MGD difference  in  flow between weekdays and the weekend, suggests that
approximately 35 percent of the flow from  commercial and industrial sources
in the Jackson Pike  service area is from sources which operate on a  weekday
schedule.   Southerly, on the  other hand,  with  10.1 MGD industrial and
commercial  flow,  appears  to  have only 4 percent of its industrial and
commercial contributing flow sources operating on a weekday schedule.
                                     A-21

-------
 4.1.1.3  Domestic  Flows
      Domestic flows were estimated simply by subtracting infiltration,
 industrial, and commercial flows from the maximum dry weather/no bypass flow
 of  145  MGD.   The Jackson Pike  domestic  flow is  30.4 MGD and Southerly  is 28.8
 MGD.  Table 4-3 presents the breakdown of the existing flow for each plant and
 the  two plants combined.                                                  >

                       TABLE 4-3.  1985 ESTIMATED FLOWS

                            Jackson Pike      Southerly
 Design Average                   84              61
 Flow  (MGD)
      •  Infiltration           40.1            22.1            62.2
      •  Industrial              9.0             6.9            15.9
      •  Commercial              4.5             3.2             7.7
      •  Domestic               30.4            28.8            59.2

      4.1.2  Maximum Hourly Flow
      Just as demand for water  fluctuates on an hourly  basis, so do  wastewater
 flow  rates.  Fluctuations observed  in wastewater flow  rates  tend  to follow  a
diurnal pattern.  (See Figure 4-1.)  Minimum flow usually  occurs  in the early
morning hours when water use is low.  The  flow rates start  to  increase  at
approximately 6 a.m. when people are  going to work, and they reach  a peak
value around 12 noon.   The flow rate usually drops off in  the  early afternoon,
and a second peak occurs  in the  early evening hours between 6 p.m.  and 9 p.m.
In general, where extraneous  flows  are excluded  from the sewer system,  the
wastewater flow-rate curves will closely follow water-use curves.  However,
the wastewater curves will be displaced  by a time period corresponding  to  the
travel time in the sewers.
                                     A-22

-------
 o
M
Ul
   6PM
                 TOTAL FLOW
                                                                 MAXIMUM
AVERAGE


MINIMUM
                    DOMESTIC
                      FLOW
                                                INFILTRATION
                                                                           NIGHT-TIME
                                                                         DOMESTIC FLOW
                                                                       INDUSTRIAL
   SOUHCr- flitting 5e»er Cvaluntlon imtl Hcdnlil 11 tntlon


        fublUheiJ by Ihc American Society of Civil engineers (ASCC) anil the Water Pollution Control rcJcrotlon (VPCO, \yt\3.
                                                                   FIGURE 4-1
                                                                   DIURNAL FLOW VARIATIONS

-------
      Diurnal curves are also affected  by  the  size of  the community.  Large
 communities with more industrial and commercial  flows tend  to have flatter
 curves due to industries that operate  on  a  24-hour schedule, stores and
 restaurants that  are open 24 hours a day, and  to the  expansiveness of the
 collection systems.   These 24-hour operating schedules also result in more
 people working second and third  shift,  thus altering  normal flow  patterns.
 Longer travel  times in the collection  system  dampen peak flows observed at the
 WWTP.

     An existing  average flow of 145 MGD was  determined in Section 4.1.1.
 This flow  was  determined from average  dry weather flows and it is generally
 used in the  design of wastewater facilities to determine quantities of
 chemicals  needed, O&M coses,  labor, and energy requirements.  However,  the
 peak hourly  flow  must be used for hydraulic sizing of pumps.  Therefore, a
 diurnal peaking factor must be determined and applied to the design average
 flow to provide a peak  hourly design flow.

     Figure 4-2 presents wastewater flow  rate curves for the Jackson Pike and
 Southerly  plants compiled  from September  1985 dry weather/no bypass days.  The
 diurnal peaking factor was determined for the  Jackson  Pike and Southerly  WWTPs
 through an analysis of hourly wastewater  flows for February and  September
 1985.   These two months represent minimum  and  maximum water consumption,
 respectively for 1985.  The 1985  months were chosen since the existing average
 flow occurred in May of  1985.  Diurnal  peaking factors were calculated  by
dividing the maximum hourly  flow by the average hourly flow for each dry
 weather/no bypass day during  February and September.  These  values are  listed
 in Tables 4-4  and 4-5.

     The maximum  diurnal peaking factor seen at Jackson Pike during this
period  was  1.40, and  at  Southerly it was  1.51.  Jackson Pike's value of 1.40
occurred several times  and was selected as the diurnal peaking factor for
Jackson Pike.  Southerly's  maximum value of 1.51, however, was considered to
be excessive.  It  occurred, only  once,  on  September  21 when  the  average hourly
flow was at a low of 45  MGD.   The next peaking factor in the series was 1.37
                                     A-24

-------
  o
  UJ
  t-
8 9
                                            HOURS
                           JACKSON PIKC
SOUTHCRLY
-x-
TOTAL AVC
                                                               FIGURE 4-2
                                                               DIURNAL FLOW VARIATIONS
                                                               FOR DRY WEATHER

-------
TABLE 4-4.  HOURLY FLOW DATA SOUTHERLY WWTP
Average Hourly Peak Hourly
Date
2/4/85
2/8/85
2/9/85
2/16/85
2/17/85
2/18/85
2/19/85
2/20/85
2/26/85
2/27/85
2/28/85
9/1/85
9/2/85
9/3/85
9/4/85
9/5/85
9/6/85
9/7/85
9/8/85
9/9/85
9/10/85
9/11/85
9/12/85
9/13/85
9/14/85
9/15/85
9/16/85
9/17/85
9/18/85
9/19/85
9/20/85
9/21/85
9/22/85
9/28/85
9/29/85
* Peaking
Flow (MGD)
56.2
55.8
54.6
69.5
67.6
69.0
71.2
75.0
87.1
81.3
82.5
48.8
49.4
53.1
52.2
52.5
50.4
51.3
49.0
50.7
53.2
53.9
51.9
40.1
54.0
49.8
52.0
51.2
52.2
51.8
49.9
45.0
51.3
51.3
50.3
Factor = Peak
Flow (MGD)
58.0
63.0
65.0
83.0
79.0
78.0
78.0
81.0
97.0
90.0
85.0
56.0
62.0
62.0
59.0
57.0
57.0
60.0
56.0
54.0
57.0
61.0
59.0
55.0
64.0
57.0
64.0
55.0
58.0
57.0
58.0
68.0
68.0
62.0
59.0
Hourly Flow
Peaking*
Factor
1.03
1.13
1.19
1.19
1.17
1.13
1. 10
1.08
1.11
1.11
1.03
1.14
1.26
1.17
1.13
1.09
1.13
1.17
1.14
1.07
1.07
1.13
1.14
1.37
1.19
1.14
1.23
1.07
1.11
1.10
1.16
1.51
1.33
1.21
1.17

Weather
Condition
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY

 Average Hourly Flow
               A-26

-------
                TABLE 4-5.  HOURLY FLOW DATA JACKSON  PIKE WWTP

Date
2/4/85
2/8/85
2/9/85
2/16/85
2/17/85
2/18/85
2/19/85
2/20/85
2/26/85
2/27/85
2/28/85
9/1/85
9/2/85
9/3/85
9/4/85
9/5/85
9/6/85
9/7/85
9/8/85
9/9/85
9/10/85
9/11/85
9/12/85
9/13/85
9/14/85
9/16/85
9/17/85
9/18/85
9/19/85
9/20/85
9/21/85
9/22/85
9/28/85
9/29/85
Average Hourly
Flow (MGD)
76.0
73.0
69.0
91.0
87.0
92.0
91.0
92.0
98.0
95.0
99.0
69.3
72.0
76.9
81.0
81.3
79.5
75.6
72.1
78.7
79.0
76.0
71.7
73.7
69.3
72.4
72.3
73.4
72.9
72.6
70.0
67.0
70.6
68.5
Peak Hourly
Flow (MGD)
94.0
96.0
89.0
102.0
106.0
102.0
98.0
103.0
106.0
104.0
102.0
86.0
89.0
104.0
96.0
95.0
94.0
94.0
92.0
96.0
92.0
90.0
85.0
86.9
96.8
88.0
96.0
92.0
88.8
89.0
90.0
94.0
99.0
83.0
Peaking*
Factor
1.24
1.32
1.29
1.12
1.22
1.11
1.08
1.12
1.08
1.09
1.03
1.24
1.24
1.35
1.19
1.17
1.18
1.24
1.28
1.22
1.16
1.18
1.19
1.18
1.40
1.22
1.33
1.25
1.22
1.23
1.29
1.40
1.40
1.21
Weather
Condition
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
DRY
* Peaking Factor »   Peak Hourly Flow
                   Average Hourly Flow
                                 A-27

-------
 which is more representative of the maximum diurnal  peaking factor seen at the
 Southerly plant.  Thus,  1.4 was chosen as a representative diurnal peaking
 factor  for both plants.

 4.1.3   Peak  Process Flow
     A  peak  process flow  must, be developed  for use in sizing the various wet
 stream  processes.  This flow establishes the maximum process capability of the
 wet  stream treatment facilities.  Flows  greater than the peak process flow
 will cause the  treatment  facilities to operate beyond their intended design
 criteria.  Sustained operation above  the  peak process  flow may result in a
 violation  of permit limits.

     The peak process flow  is most reliably  established through an analysis of
 existing flow.  This approach was not  possible in  the  Columbus  system due to
 the  nature of the flow record.  As discussed in Section 2, the  flow records
 for  the two Columbus plants provided limited information regarding the amount
 of sewage  bypassed.  As a result a reliable  record of  the  total flow arriving
 is not available.  Furthermore,  peak wastewater  flows  normally  include some
 combined sewage.  A combined sewage overflow study, which will define a CSO
 control strategy,  is currently being prepared by the  city.  The impact of the
 CSO  recommendation on the wastewater treatment facilities will be evaluated at
 the  conclusion  of that study.

     In the 1979 EIS,  the following empirical formula was utilized to develop
 a peak process  flow, due to the absence of a comprehensive flow record.

     Peak Process  Flow =1.95 (Average Daily Flow) °*95

     Lacking flow information which would substantiate a peak process flow,
 the  1979 EIS formula provides a reasonable method for developing a peak
 process flow.  Based on the  2008  average  design flow of 154  MGD,  the  formula
yields a peak process flow of 233 MGD.  This corresponds  to a process peaking
 factor of  1.5.
                                      A-28

-------
     The  1.5 process peaking factor was  evaluated  relative  to  the  1986
available  flow data to assess  the extent of its  range.  The 1986 flow record
includes  flows treated  at  Jackson Pike  and Southerly and also the flows which
are bypassed at Southerly.  The flow record does  not include flows which were
bypassed  at Whit tier Street or any other combined  sewer overflows.  The 1986
average flow of the two plants was 145 MGD.  Applying  the  1.5 process peaking
factor to  this  average  flow yields a  peak process  flow  of 218 MGD.  Comparing
this flow  with the  1986  record  indicated  that the daily flow rate of 218 MGD
was exceeded only nine  days during the year or approximately  2.5 percent of
the time.  In  light  of  these few  exceedances,  the  1.5 process peaking factor
established by  the  1979  EIS provides  a reasonable  approach  to establish a peak
process flow.

4.1.4  Wet Weather Flow
     The maximum monitored  wet weather flow as determined from 1986 records
and discussed in Section  3.4 is 309.52 MGD.   This flow  occurred on March  14.
It includes 95.57 MGD for the Jackson Pike WWTP  and 213.95  MGD for the
Southerly WWTP.  The Southerly flow can be broken down  into 78.05 MGD
receiving complete  treatment,  30.30 MGD receiving primary treatment and
chlorination,  and 105.60 being  bypassed directly  to the Scioto River.   Note
that this maximum wet  weather  flow only  includes flow  that  arrives at the
treatment plants.  Any flow being bypassed at the various points  of combined
sewer overflow  is not  included.

4.2  WASTEWATER LOADS
     Monthly average  influent  TSS (total  suspended solids) and BOD (biochemical
oxygen demand)  loads were determined  for  all weather conditions.   These loads
are presented in Tables  4-6 and 4-7.

     The sampling point at  Jackson Pike  for TSS  and BOD concentrations is
located at the  grit  chambers on the O.S.I.S.  Therefore,  the samples  do not
represent the flow  from the Big Run  Interceptor.  The O.S.I.S.  carries in
                                     A-29

-------
TABLE 4-6.  1985 AVERAGE BOD LOADS (Ib/day)
Month
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
ANNUAL
Jackson Pike
BOD
118,466
109,094
104,532
97,918
97,831
109,632
94,384
93,591
88,619
104,161
96,483
92,466
100,702
Southerly
BOD
91,187
82,506
82,819
87,777
89,108
85,513
84,649
86,073
98,992
105,446
76,140
76,992
87,258
Total
BOD
209,653
191,600
187,351
185,695
186,939
195,145
179,033
179,664
187,611
209,607
172,623
169,458
187,960
                     A-30

-------
       TABLE 4-7.   1985 and  1986 MONTHLY AVERAGE TSS  LOADS  (Ib/day)
             Jackson Pike
Month      1985 TSS  1986 TSS

Jan.       120,331   115,923

Feb.       121,223   120,583

Mar.       136,509   129,050

Apr.       110,170   124,532

May        136,038   133,613

Jun.       158,045   139,516

Jul.       153,317   113,282

Aug.       126,033   108,853

Sep.       114,192   129,688

Oct.       121,086   139,653

Nov.       148,916   112,099

Dec.       105,969   104,965

ANNUAL     129,347   122,665
    Southerly
1985 TSS  1986 TSS

 99,391    87,633

108,739    91,508

107,085    94,313

106,911    92,109

108,516    89,700

 99,145    95,078

105,571    93,421

 91,308   100,996

 95,424   101,437

 93,693   100,830

 99,165    88,952

 97,948    86,313

101,042    93,535
      Total
 1985 TSS   1986 TSS

 219,722    203,556

 229,962    212,091

 243,594    223,363

 217,081    216,641

 244,554    223,313

 257,190    234,594

 258,888    206,703

 217,341    209,849

 209,616    231,125

 214,779   240,483

 248,081    201,051

 203,917    191,278

230,389   216,200
                                   A-31

-------
 approximately 65 to 70 percent of the flow at Jackson Pike.  Plant  staff
 believe that the flow arriving  through  the O.S.I.S. contains the majority  of
 the industrial  flow in the Jackson Pike service area.   Samples  taken from  the
 O.S.I.S. have always  been  used  to establish  waste loads for the total flow  to
 Jackson Pike.  The Southerly flow is  sampled  between the screens and the grit
 chambers.  Thus, the samples are  representative of 100  percent of the flow
 entering  the Southerly plant.

     Only  1985 data  were  used  to determine existing BOD loads because there
 were insufficient data available for  1986.  There were  only 304 days of
 reported BOD values  for Jackson  Pike  in  1986.  There were  341 days  of data  for
 Jackson Pike in  1985.  Southerly  reported BOD values on 362 days in  1986 and
 364 days in  1985.

     The 1985 annual average BOD  load for Jackson Pike, as  presented in  Table
4-6, is 100,702 Ib/day.  The maximum  monthly  average load  is  118,466 Ib/day,
and  it occurred in January.  The ratio of maximum monthly  average to the
annual average results in a peaking factor of 1.2.

     The 1985 annual average BOD  load for Southerly, as shown in Table 4-6, is
87,258 Ib/day.  The  maximum monthly average load, which occurred  in October,
is  105,446 Ib/day.   The peaking factor, as determined by dividing  the maximum
monthly average  by  the annual  average,  is 1.2.

     1985 and 1986 data were used  to  establish TSS loads for Jackson Pike and
Southerly.   Jackson Pike  had 365 and 363 days of TSS data for 1985  and 1986,
respectively.  There were 364 days of TSS data reported for Southerly for both
years.

     The average TSS load was obtained by computing  the average of  the annual
averages for 1985 and  1986.  The Southerly 1985 and 1986 average is  97,289
Ib/day; and Jackson Pike  is 126,006 Ib/day.   Peaking factors were established
for each year in  the  same manner as was used for BOD loads.  The peaking
factors for Jackson Pike  are 1.2 and  l.l for 1985 and 1986, respectively.  The
                                    A-32

-------
higher  value  of  1.2 was  chosen  as  the  Jackson  Pike  TSS  peaking factor.   The
Southerly TSS peaking  factors are  1.1 for both 1985 and  1986.   Table  4-8

summarizes  the  1985  and  1986 average and peak BOD and TSS loads.


                 TABLE 4-8.  1985  AND  1986 BOD AND  TSS  LOADS
                                      Jackson Pike    Southerly
BOD LOADS
     •  Average (Ib/day)
                (Ib/capita day)

     •  Peak (Ib/day)

     •  Peaking Factor
100,702
  0.206

118,466

    1.2
 87,258
  0.229

105,446

    1.2
 Total



187,960
  0.216

223,912

    1.1
TSS LOADS
     •  Average (Ib/day)
                (Ib/capita day)

     *  Peak (Ib/day)

     •  Peaking Factor
126,006
  0.258

151,207

    1.2
 97,289
  0.255

107,018

    1.1
223,295
  0.257

251,925

    1.1
POPULATION
489,000
381,000
870,000
                                      A-33

-------
      A summary of Che 1985  population  figures and historic wastewater flows
 and loads is  presented in Table  4-9.   These quantities were used as a basis
 for projecting flows and loads to the design year.

                        TABLE  4-9.   1985  FLOWS AND LOADS

                                 Jackson  Pike      Southerly      TOTAL
      Total Flow
      Ave.  (MGD)
              •  Infiltration
              •  Industrial
              •  Commercial
              •  Domestic
      BOD Load  (Ib/day)
      TSS Load  (Ib/day)
      Population

4.3   PROJECTED FLOWS AND LOADS
      This next section presents flows  and loads projected to the 2008 design
year.

     Table 4-10  presents the flows of  Table 4-9 in per capita/connection
form.  These data further reinforce the  figures presented in Table 4-9 since
they  represent reasonable values in agreement with the literature.

     Holding infiltration and  industrial  flows constant and using the existing
per capita commercial  and domestic  flows (Table 4-10) and the population
projections for 1988 and 2008,  wastewater flows were projected for 1988 and
2008.
84
40.1
9.0
4.5
30.4
118,500
151,200
489,000
61
22.1
6.9
3.2
28.8
105,400
107,000
381,000
145
62.2
15.9
7.7
59.2
223,900
258,200
870,000
                                      A-34

-------
                  TABLE 4-10.  1985 PER CAPITA/CONNECTION FLOWS


                                    Jackson Pike      Southerly      TOTAL

Per Capita
Domestic Wastewater Flow (gpcd)         62.2             75.6         68.1

Per Capita
Commercial Wastewater Flow (gpcd)        9.2              8.4          8.9

Per Capita
Industrial Wastewater Flow (gpcd)       18.4             18.1         18.2

Per Capita
Industrial, Commercial, and
Domestic Wastewater Flow (gpcd)         89.8            102.1         95.2

Per Capita
Infiltration (gpcd)                       82               58           72

Per Connection
Commercial Wastewater Flows
(gal/connection day)                     ND               NO         816.7

Per Connection
Industrial Wastewater Flows
(gal/connection day)                     ND               ND        62,109
1985 Per Capita
Water Pumped
Industrial, Commercial, and
Domestic (gpcd)                          ND               ND         139.1

1985 (Industrial, Commercial, and
Domestic) Water Pumped to Wastewater
Discharge Factor                         ND               ND          .976


  SOURCE:  City of Columbus, Division of Sewerage and Drainage, December 1986
                                      A-35

-------
     There was  insufficient  information available to disaggregate  the existing
 industrial loads and the expected future industrial loads from  the total.
 Therefore, the existing total per capita BOD and TSS loads from Table 4-8 were
 multiplied by the population projections and the respective peaking factors to
 obtain the 1988 and 2008 projected loads.  In doing so, growth of  industrial
 contributions is proportional to residential growth.

     Table 4-11 presents the 1988 projected population, flows, and loads for
each plant;  and Table 4-12 presents  the projected design average flows and
 loads for the 2008 design  year.
                                     A-36

-------
TABLE 4-11.  1988 PROJECTIONS
   Jackson Pike
Southerly
TOTAL
Total Flow
Ave. (MGD)
• Infiltration
• Industrial
• Commercial
• Domestic
BOD Load ( Ib/day)
TSS Load (Ib/day)
Population
84.8
40.1
9.0
4.6
31.1
123,400
154,500
499,000
TABLE 4-12. 2008
Total Flow
Ave. (MGD)
• Infiltration
• Industrial
• Commercial
• Domestic
BOD Load (Ib/day)
TSS load (Ib/day)
Population
Jackson Pike
87.9
40.1
9.0
5.0
33.8
134,600
168,600
544,600
61.7
22.1
6.9
3.3
29.4
106,900
109,100
389 , 000
PROJECTIONS
Southerly
66.0
22.1
6.9
3.7
33.3
121,300
123,800
441,400
146.5
62.2
15.9
7.9
60.5
230,300
263,600
888,000

TOTAL
153.9
62.2
15.9
8.7
67.1
255,900
292,400
986,000
        A-37

-------
                         5.   FACILITY  PLAN METHODOLOGY

      The following sections summarize the design wastewater flows and loads
 proposed in  the  facility plan and  the methodology used  in their development.
 The  Revised  Facility Plan Update (RFPU) and  the General  Engineering Report and
 Basis of Design  (GERBOD)  were used to prepare this discussion.   The following
 sections include:

      •   Dry  Weather Wastewater Flows
      *   Design Average Daily Flows
      •   Design Loads
      •   Industrial Flows  and Loads
      •   Projected Design  Flows and Loads

      The  facility plan developed existing dry weather wastewater flows to
approximate  a low groundwater condition.  These flows were projected to the
2015  design  year.  Then average  daily flows were developed to approximate
average infiltration under a high groundwater condition  and  these  flows  were
projected to the 2015 design year.    The 2015 average daily  flows approxi-
mating average infiltration under a high groundwater condition  were selected
as the design average flows  for use in alternative development in the facility
plan.

     Existing waste loads were determined and projected to the 2015 design
year.  Two scenarios  were developed for  future additional  flows and  loads  from
undocumented industrial growth.   However, since neither of these scenarios was
included in the design  average flows  and loads,  it appears that a  decision was
made  not  to  plan for future undocumented industrial growth.   The last section
summarizes the facility plan's selected  design wastewater flows and loads.

5.1  DRY WEATHER WASTEWATER FLOWS
     The Revised Facility Plan Update developed dry  weather  flows to
approximate  low infiltration under low groundwater conditions.    Monthly
                                      A-38

-------
Operating Reports (MORs) were used to determine dry weather wastewater flows
through  three different  methods.

     •   An average daily flow  was derived  for  the  1984 dry months  (July and
         August).
     •   A 50th percentile flow was determined  from 40 randomly selected dry
         weather days  between 1982 and 1984.
     •   An average daily flow  was derived  for  the dry months of 1979
         through 1984.

     The GERBOD states that flows of  74 MGD  for Jackson Pike and 53 MGD for
Southerly were determined from the first method listed above using 1984 dry
months.  The report states that the flows developed by the other two methods
closely approximate these flows,  but  a direct  comparison  is not provided.

     The 1983 population for each WWTP service area was selected as the
population value to be used for calculation of gallons per capita per day
(gpcd)  flow factors.   The 1983  Southerly  population was determined to be
356,901 and the  Jackson Pike population was determined to  be 470,979.
Calculated gpcd flow factors are  149  gpcd for Southerly and 157 gpcd for
Jackson Pike  which results  in  a  system-wide average of 153 gpcd.   By
comparison, a system-wide average of  152 gpcd was calculated in the Original
Facility Plan based upon 1975  flow data.

     Utilizing population projections developed in  the Revised  Facility Plan
Update  (presented  in Table  5-1) and the gpcd  flow factors  discussed above,  dry
weather  flows were  projected for  each plant  for the years  1988, 2000, and
2015.   Table 5-2 presents these flows.
                                      A-39

-------
               TABLE 5-1.  FACILITY PLAN POPULATION PROJECTIONS

           Service Area

           Jackson Pike
           Southerly
           TOTAL
           SOURCE:  Revised Facility Plan Update - URS Dalton 1985

                TABLE 5-2.  PROJECTED DRY WEATHER FLOWS (HGD)

           Service Area                        Year
Year
1988
487,644
382,783
870,427
2000
531,366
420,495
951,861
2015
573,052
459,992
1,033,044
1988
77
58
135
2000
83
63
146
2015
90
69
159
           Jackson Pike
           Southerly
           TOTAL
           SOURCE.  Revised Facility Plan Update - URS Dalton 1985
5.2  DESIGN AVERAGE DAILY FLOWS
     The Revised Facility Plan Update developed design average daily flows to
approximate average infiltration under high  groundwater conditions.    Flow
values were obtained from Monthly  Operating Reports (MOR).  Forty-five days
were randomly selected from the years 1982 through 1985 based  on  the following
criteria.

     •  Weekdays only
     •  No significant rainfall on the sample  day
     •  No significant rainfall for 24 hours prior to  the sample  day
     »  No reported bypassing

     The 50th percentile flow values were derived from probability plots
for eacn WWTP.   The Jackson Pike  flow was determined to be 84  KGD,  and the
Southerly flow was determined  to be 59 MGD.
                                     A-

-------
     The WWTP service area population figures for 1984 of 475,909 for Jackson

Pike and 363,097 for Southerly were used to convert the above flows  to gpcd
flow  factors.  Jackson Pike  was  calculated  at 177 gpcd and Southerly was
calculated at 162 gpcd.   Table 5-3 shows the breakdown of the flow factors as

presented in  the RFPU.


                 TABLE 5-3.   DESIGN AVERAGE FLOW  FACTORS  (gpcd)


                      Jackson Pike         Southerly             Total
Flow Component.        Service Area        Service Area        Service Area

Domestic                  80                  80                  80
Industrial                15                  24                  19
Infiltration              82                  58                  T2

Total                    177                  162                 171

Source:  Revised Facility Plan Update - URS Dalton 1985

     Using population projections (Table 5-1) and total gpcd flow factors

developed for each WWTP, design flows were projected  for  the years 1988, 2000,

and 2015.  These flows are shown  in Table 5-4.


                    TABLE 5-4.  DESIGN AVERAGE FLOWS (MGD)
                                               Year
                 Service Area        1988      2000      2015

                 Jackson Pike          86        94       101
                 Southerly             63        68        75
                 TOTAL                149       162       176

                 SOURCE:  Revised Facility Plan Update - URS Dalton 1985
5.3  DESIGN LOADS

     Existing wasteloads were determined by randomly selecting 80 days from

MORs for each WWTP based on the following criteria:


     •  40 days during the low infiltration season - July, August, September
                                     A-41

-------
      •  40  days during  the  low  temperature  season - December, January,
        February
      *  Years  1982,  1983, 1984
      •  No  significant  rainfall on the selected day.
      •  No  significant  rain for 24 hours prior to the selected day
      •  No  bypassing
      •  Weekdays only

      The parameters  selected  for analysis were BODe, TKN, phosphorus,
suspended solids, and flow.

      Probability plots were constructed from  these calculated loads for both
the low infiltration season and  the low temperature season.  The 80th
percentile  loads were chosen  from  the  low infiltration plots.  These loads
were  used in calculating projected loads for  1988, 2000, and 2015.
Adjustments were made for the Anheuser-Busch Brewery.  It was assumed that the
existing loads and  flow from the brewery are the following:

     •  BOD  = 35,260 Ib/day
     •  SS     13,400 Ib/day
     •  Flow =3.13 MGD

     For future projections it was assumed that  the  brewery would increase
to its maximum monthly  average  BOD^  limit of  45,000 Ib/day.

     Table 5-5 presents the Revised Facility Plan Update's  design wasteloads
for the Jackson Pike and Southerly WWTP.
                                     A-42

-------
                   TABLE 5-5.  DESIGN WASTELOADS (Ib/day)
Jackson Pike
Southerly
Design
Year
1988
2000
2015
1988
2000
2015
BOD5
127,150
137,060
148,620
117,060
123,730
131,740
Suspended
Solids
145,780
157,130
170,390
180,020
116,450
126,550
TKN
16,700
18,000
19,520
14,570
15,760
17,260
Total
Phosphorus
5,459
5,884
6,380
4,595
4,991
5,467
SOURCE:  Revised Facility Plan Update - URS Dalton 1985

5.4  INDUSTRIAL FLOWS AND LOADS
     The Revised Facility Plan Update presented tables which included
additional flow and loading allowances for future,  undocumented industrial
growth.  This growth was only assumed to affect the Southerly plant.  No
reason was provided for this assumption.   Flow projections for both dry
weather and design average flow were  increased by 2 MGD and 4 MGD after 1988
to account for the  possibility  of  undocumented growth in the industrial
sector.  Table 5-6  presents dry weather flow projections with the additional
flow allowances of 2.0 MGD and 4.0 MGD for undocumented industrial growth.
Table 5-7 presents  design average  flow projections  with the  same  flow
allowances.
 TABLE  5-6.   DRY WEATHER FLOW PROJECTIONS FOR UNDOCUMENTED INDUSTRIAL GROWTH
                        (2 MGD/4 MGD FLOW ALLOWANCES)
                Service Area
                Jackson Pike
                Southerly
                TOTAL
                SOURCE:   Revised Facility Plan Update - URS Dalton 1985
Year
1988
77/77
58/58
135/135
2000
83/83
65/67
148/150
2015
90/90
71/73
161/163
                                     A-43

-------
TABLE 5-7.  DESIGN AVERAGE FLOW PROJECTIONS FOR UNDOCUMENTED INDUSTRIAL GROWTH
                        (2 MGD/4 MGD FLOW ALLOWANCES)
                                              Year
                Service Area        1988      2000      2015

                Jackson Pike       86/86     94/94    101/101
                Southerly          63/63     70/72     77/79
                TOTAL             149/149   164/166   178/180

                SOURCE:  Revised Facility Plan Update - URS Dalton 1985


     The increase in industrial flow could also increase the wasteload

projection.   Therefore, the facility planners  also revised their wasteload

projections to reflect the 2/4 MGD flow  increases.  Since the industrial flow

increase was only added to the Southerly  WWTP,  the increase in wasteloada will

only affect the Southerly plant.  Table 5-8 presents these revised wasteload

projections for Southerly.


              TABLE 5-8.  DESIGN WASTELOAD PROJECTIONS (ib/day)
                 ADJUSTED FOR UNDOCUMENTED INDUSTRIAL GROWTH
                                SOUTHERLY WWTP
Design
Year
2 MGD Allowance
1988
2000
2015
4 MGD Allowance 1988
2000
2015
BOD5
117,060
138,730
146,740
117,060
163,730
171,740
Suspended
Solids
108,820
122,170
132,230
108,020
131,610
141,710
TKN
14,510
16,510
18,010
14,510
17,760
19,260
Total
Phosphorus
4,595
5,066
5,542
4,595
5,191
5,667
SOURCE;  Revised Facility Plan Update - URS Dalton 1985


     The flows and loads which included an allowance for undocumented

industrial growth were  not used as a basis for alternative development,  which

assumes no industrial growth during the planning period.
                                     A-44

-------
5.5  PROJECTED DESIGN FLOWS AND LOADS
     This section summarizes  the  facility  plan's projected design flows and
loads.

5.5.1  Design Flows
     The Jackson Pike and Southerly projected 2015 design average daily flows
of 101 MGD and 75 MGD,  respectively,  were chosen by the facility plan as the
basis for development.  These  flows  were presented in Section 5.2.

     Since the Revised Facility Plan Update chose the one-plant alternative,
the design flows for Jackson Pike and Southerly were combined  resulting in an
average daily design flow of 176 MGD  to  be  treated at Southerly.  Peak process
design was then  calculated as 300 MGD by multiplying the design average flow
by a peaking factor of 1.7.  The peak  process  flow  of 300 MGD is used to size
the wet stream treatment  facilities.  There is no supportable information in
the facility plan on how the peaking  factor was derived.  There is reference
to the fact that anything greater than 1.7  would adversely affect process
efficiency under average flow conditions.  In subsequent correspondence and a
clarifying telephone conversation with the city's  consultant,  it was
determined that 1.7  was based  on a hydraulic constriction between the existing
primary clarifiers and aeration basins at the Southerly WWTP.  The consultant
indicated that each existing train is  limited  to an average to peak flow ratio
of 44 MGD to 75 MGD.  The 44 MGD average flow is based on mass loading to the
aeration basins,  and the  75  MGD peak  flow is based on the hydraulic capacity
of the existing conduits between the primary clarifiers and the aeration
tanks.   In light  of the fact that  the  CSO study  is  incomplete and that
analyses of wet weather data was  limited,  the 1.7 peaking factor was
considered appropriate by the city and their consultant*

     An additional 130 MGD for CSO control is added on to the peak process
flow of 300 MGD and this total  flow of 430  MGD is considered as the peak
hydraulic flow.   There are  conflicting statements in the facility plan
regarding which treatment processes will be sized for 430 MGD.  In Chapter 2,
                                      A-45

-------
it is seated that flows between 300 MGD and 430 HGD will be processed through
primary  settling and chlonnation.  In Chapter 12, it appears that only the
influent pumps and bar racks and screens are being sized for 430 MGD.

5.5.2  Design Loads
     Section 5.3 presented design loads determined in the facility plan
through analysis of Jackson Pike and Southerly plant records.  In addition to
these loads, the facility plan presents loads contributed by the additional
flows conveyed to the plant during peak hydraulic flow conditions.  These
additional flows are considered to be diverted from Whittier Street.
Table 5-9 presents the design loadings for the year 2015 including the loads
from Whittier Street flows.

                    TABLE 5-9.   DESIGN LOADINGS (Ib/day)

    Parameter     Southerly     Jackson Pike     Whittier St.      Total
                                                    10,000        290,360
                                                    20,000        316,940
                                                     1,300         38,080
                                                       400         12,247
    SOURCE:  Revised Facility Plan Update - URS Dalton 1985

     Since the Revised Facility Plan Update chose the one-plant alternative,
the loads listed in the Total column in the previous table were used as the
basis for development of alternatives.
BODr
TSS
TKN
P
131,740
126,550
17,260
5,467
148,620
170,390
19,520
6,380
                                      A-46

-------
      6.  COMPARISON OF BRIEFING PAPER AND FACILITY PLAN FLOWS AND LOADS

     This section summarizes Che design flows and loads developed in Che
facility plan and those developed by this briefing paper.  Table 6-1 provides
a comparison between the two.

               TABLE 6-1.  COMPARISON OF DESIGN FLOWS AND LOADS

                                          Facility Plan      Briefing Paper
  1988 Projected Average Flow (MGD)              149              147
  Design Year                                   2015             2008
  Design Average Flow (MGD)                      176              154
  Process Peaking Factor                         1.7              1.5
  Peak Process Flow (MGD)                        300              231
  Design BOD Load (Ib/day)                   290,360          255,900
  Design TSS Load (Ib/day)                   316,940          292,400

     The 1988 projected average flows are very close, being 149 MGD in the
facility plan and 147 for this briefing paper.   The projected design average
flows of 176 MGD  for the facility  plan  and 154 MGD for this briefing paper
vary by 22 MGD (14 percent) due to different  design years that result in a
difference in population projections.  The facility plan flows are based on
the year 2015 and the briefing paper flows are based on a 2008 design year.
For purposes of comparison, the facility plan design, average flow was brought
back to the year 2008.   Using the 2008 population projections developed for
the EIS and the gpcd flow figures used  in the facility plan, the facility plan
flows for 2008, presented in Table 6-2,  are 96  MGD for Jackson Pike and 72 MGD
for Southerly.  This  total  flow of 168 MGD for both plants is 14 MGD (9
percent) higher than the briefing paper flow of 154 MGD.
                                       A-47

-------
          TABLE 6-2.  FACILITY PLAN POPULATION AND FLOW PROJECTIONS
Flow Values (gpcd)

1988
     • Population
     • Flow (MGD)
2000
     • Population
     • Flow (MGD)
2008
     • Population*
     • Flow (MGD)**
2015
     * Population
     • Flow (MGD)
                         Jackson Pike
    177
487,644
     86
531,366
     94
544,600
     96
573,052
    101
Southerly

    162
382,783
     63
420,495
     68
441,400
     72
459,992
     75
                                 TOTAL
      171
  870,427
      149
  951,861
      162
  986,000
      168
1,033,044
      176
Source:  Revised Facility Plan Update - 1985

 *EIS population projections.
**Developed for comparison with briefing paper 2008 design flow.


     Thus,  even if the design years are the same and the population projec-

tions are the same, the design flows still differ slightly.  This difference

is because the flow projections made in the briefing paper were developed by

holding the infiltration and industrial portions of the flow constant and

increasing only the commercial and domestic flows proportional to the popula-

tion increase, whereas the flows  in the facility plan were developed by

increasing all of the flow, including infiltration and industrial,

proportional to the population increase.   Projected increases in infiltration

do not appear justified if the population  increase  is located within the

existing service area. The  facility plan  does  not document why an increase in

infiltration should be planned for.  Projected industrial increases should be

based on documented industrial growth by existing industries and/or policy
                                     A-48

-------
decisions by the municipality  to  plan  for  future undocumented  growth.
Furthermore, such industrial growth should be an identifiable  part of the
total design loads since capital cost  recovery for the added capacity must be
addressed.

     The projected peak process flows  are  231 MGD  and 300 MGD  for the briefing
paper and facility plan, respectively.   These flows differ significantly due
to differences in design average flows and different peaking factors.  The
reasons for the different design average  flows were discussed  in the previous
paragraphs.   The peaking factor is  1.5 for the briefing  paper  and 1.7 for the
facility plan.   The 1.5  peaking factor  for  the briefing  papers  is consistent
with the peaking  factor used  in the original  EIS.  The  facility  plan's peaking
factor of 1.7 is based on  the  maximum hydraulic capability of  the conduits
between the primary clarifiers  and aeration basins in the existing trains at
the Southerly WWTP.

     A breakdown of the briefing paper and facility plan projected BOD and TSS
loads is presented in Table 6-3.  The  differences  in  loads are  partially due
to differences in design years and also due to the inclusion of loads from
Whittier Street.  For  comparison purposes,  Table 6-4  presents the facility
plan loads brought back to 2008 without the Whittier Street  loads.  These
loads were decreased to the year 2008 using EIS population projections and
load factors developed in Section 4.2 of  this  document.   In comparing the
briefing paper loads to the 2008 facility plan loads,  it was found that the
loads are within 5 percent of each other.   Therefore,  the 2008  facility plan
loads will be used as the basis for further EIS evaluations.
                                      A-49

-------
   TABLE 6-3.  COMPARISON OF FACILITY PLAN AND BRIEFING PAPER DESIGN LOADS
Design Year

Jackson Pike
     •  BOD (Ib/day)
     •  TSS (Ib/day)

Southerly
     *  BOD (Ib/day)
     •  TSS (Ib/day)

Whittier Street
     •  BOD (Ib/day)
     •  TSS (Ib/day)
TOTAL
     •  BOD (Ib/day)
     *  TSS (Ib/day)
                Facility Plan
                     2015
                   148,620
                   170,390
                   131,740
                   126,550
                    10,000
                    20,000
                   290,360
                   319,940
                 Briefing Paper
                      2008
                    134,600
                    168,600
                    121,300
                    123,800
                    255,900
                    292,400
                       TABLE 6-4.  2008 PROJECTED LOADS
Jackson Pike
     •  BOD (Ib/day)
     •  TSS (Ib/day)

Southerly
     •  BOD (Ib/day)
     •  TSS (Ib/day)
Total
     •  BOD (Ib/day)
     •  TSS (Ib/day)
                       Facility Plan
141,600
161,600
126,600
121,300
268,200
282,900
                             Percent Difference
                  EIS        From Facility Plan
134,600             -4.9
168,600             +4.3
121,300             -4.2
123,800             +2.1
255,900             -4.5
292,400             +3.2
                                      A-50

-------
Summary

     Table 6-5 summarizes  the 2008  flows and loads which will be used as a
basis for further EIS analysis.   The 2008 average flows developed in this
briefing paper will be utilized.  They were developed based on 1985 and 1986
plant records, industrial flow data from the 1983 Industrial Pretreatment
Report, and the facility plan infiltration values.  A process peaking factor
of 1.5 is  applied  to this average flow to obtain the peak process flow.   The
facility plan BOD and TSS loads brought back to 2008, without the Whittier
Street loads,  will be utilized as the design loads.  Further documentation is
required and has been requested to verify the industrial flows and
infiltration value.
                TABLE 6-5.  2008 PROPOSED EIS FLOWS AND LOADS
                          Jacksoni__P ike         Southerly
Average Flow (MGD)               88                  66
Peak Process Flow (MGD)         132                  99
BOD Load (Ib/day)           141,600             126,600
TSS Load (Ib/day)           161,600             121,300
                                      A-51

-------

-------
         APPENDIX B

    BRIEFING PAPER NO. 2
SOLIDS HANDLING ALTERNATIVES

-------
BRIEFING PAPER NO. 2
SOLIDS HANDLING ALTERNATIVES
Supplemental Environmental Impact Statement
USEPA Contract No.  68-04-5035, D.O.  No. 40
Columbus Ohio Wastewater Treatment Facilities
Prepared By.

SCIENCE APPLICATIONS INTERNATIONAL CORPORATION

TRIAD ENGINEERING INCORPORATED

-------
                         SOLIDS HANDLING ALTERNATIVES
I.   EXISTING SLUDGE MANAGEMENT SYSTEMS
     l.l  Jackson Pike
     1.2  Southerly

2.   DEVELOPMENT OF SLUDGE MANAGEMENT ALTERNATIVES
     2.1  Jackson Pike Sludge Management Alternatives (Two-Plant Scenario)
          2.1.1  Jackson Pike Sludge Management Alternative JP-A
  ,        2.1.2  Jackson Pike Sludge Management Alternative JP-B
          2.1.3  Jackson Pike Sludge Management Alternative JP-C

     2.2  Southerly Sludge Management Alternatives (Two-Plant Scenario)
          2.2.1  Southerly Sludge Management Alternative SO-A
          2.2.2  Southerly Sludge Management Alternative SO-B
          2.2.3  Southerly Sludge Management Alternative SO-C
          2.2.4  Southerly Sludge Management Alternative SO-D
          2.2.5  Southerly Sludge Management Alternative SO-E
          2.2.6  Southerly Sludge Management Alternative SO-F

     2.3  Southerly Sludge Management Alternatives (One-Plant Scenario)

3.   EVALUATION OF SLUDGE MANAGEMENT ALTERNATIVES
     3.1  Cost Effectiveness of Sludge Management Alternatives
     3.2  Sludge Dewaterrng
     3.3  Planned System Redundancy
     3.4  Ultimate Disposal Plan
          3.4.1  Distribution and Marketing of Composted Sludge
          3.4.2  Land Application of Digested, Dewatered Sludge
          3.4.3  Landfilling of Incinerated Dewatered Sludge

-------
                                 INTRODUCTION

     Under the direction of USEPA,  a series of briefing papers are being
prepared addressing key issues in the development of the Supplemental
Environmental Impact Statement for the Columbus,  Ohio, Wastewater  Treatment
Facilities.  The  briefing  papers  form the  basis  of  discussions  between Triad
Engineering and USEPA to resolve these key issues.   The  following  paragraphs
present the background of the facility planning  process, a description of the
briefing papers,  and the purpose of this paper on solids handling  alterna-
tives.

FACILITY PLANNING PROCESS
     At the time this paper was prepared (March-August  1987) the city  of
Columbus was proceeding to implement improvements at the Jackson Pike  and
Southerly Wastewater Treatment Plants to comply with more stringent effluent
standards which must be met by July 1,  1988.   These improvements  were based
on the consolidation of wastewater treatment operations at the Southerly
plant.  This  one-plant alternative  is  a  change from the  two-plant  operation
proposed by the city in the  1970's and evaluated in the 1979 EIS.

     The development and documentation of  a wastewater treatment process and
sludge management alternatives for the Columbus metropolitan area  has  been an
extended and iterative process.    The design and construction  of various
system components have progressed, because of the 1988 deadline, while
planning issues continue to be resolved.   As  a result, numerous  documents have
been prepared which occasionally revise a previously established course of
direction.

     The concurrent resolution of planning issues and  implementation of
various project components has made preparation  of  the  EIS more difficult
because final facility plan recommendations are not available in a single
document.
                                      B-l

-------
BRIEFING PAPERS
     To facilitate preparation of the EIS,  a series of briefing papers  are
being developed.   The purpose of the  briefing papers is to  allow USEPA  to
review the work of the EIS consultant and to identify supplemental  information
necessary for the preparation of the  EIS.    Six briefing papers are being
prepared as follows:

     •  Flows and Loads
     •  Sludge Management
     •  CSO
     *  Process Selection
     •  One Plant vs. Two Plant (Alternative Analysis)
     •  O&M and Capital Costs

     The specific focus of each briefing paper will be different.   However,
the general scope  of  the  papers  will  adhere  to the  following format:

     •  Existing conditions will be documented.
     »  Evaluations,  conclusions, and  recommendations of the facilities
        planning process will be reviewed using available documentation.
     •  Where appropriate, an independent evaluation of the future  situation
        and viable alternatives will be prepared.
     •  The facility  plan and EIS briefing paper conclusions will be compared.

     The briefing paper process is intended to:

     •  Prompt the resolution of any  data deficiencies.
     •  Clearly establish and define  existing and  future conditions.
     •  Identify the  final recommended plan which  the city  desires  to implement.
     •  Provide a data base of sufficient detail to allow preparation of the
        draft EIS.
                                     B-2

-------
SLUDGE MANAGEMENT ALTERNATIVES
     This briefing paper reviews  the  facilities planning process and
subsequent efforts by the city relative to the development and adoption of a
sludge management  alternative.  The briefing paper is divided into four
sections as follows:

Section 1 - Existing Sludge Management System.
     Section 1 defines the current sludge processing and disposal practices of
     the Jackson Pike and Southerly plants.   It establishes a foundation from
     which potentially viable sludge management alternatives can be
     identified.

Section 2 - Development of Sludge Management Alternatives
     In Section 2 potentially viable sludge  management alternatives are
     identified and developed sufficiently to allow a comparative evaluation.

Section 3 - Evaluation of Sludge Management Alternatives
     Section 3 evaluates the sludge management alternatives that were
     developed.  The alternatives are evaluated with respect to the analysis
     of the briefing paper and in light of the recommendations of the
     facilities planning process and subsequent planning and preliminary
     design documents.

Section 4 - Planning Issues to be Resolved
     In Section 4 the issues that developed through this analysis are
     highlighted to facilitate discussion and  resolution.

The primary sources of information utilized in preparing this briefing paper
included:

     •  Revised Facilities Plan Update, September 30, 1985
     •  General Engineering Report and Basis of Design,  January 1,  1986
     •  Preliminary Design Evaluation of Sludge Dewatering, December 12, 1986
                                      B-3

-------
                   1.   EXISTING SLUDGE MANAGEMENT SYSTEMS

 1.1  JACKSON PIKE

     Figure 1 presents the sludge processing and disposal schematic currently
 in operation at Jackson Pike.  The sludge processing operations include:

     •  Primary sludge (PS) thickening in primary clanfiers
     •  Centrifuge thickening of waste activated sludge (WAS)
     •  Thickened sludge storage and blending (i.e. PS and WAS)
     •  Stabilization by anaerobic digestion or thermal conditioning
     •  Centrifuge dewatering

Dewatered sludge is disposed of in one of the following ways:

     •  Dewatered sludge is incinerated and  the ash product is ultimately
        landfilled.
     *  Dewatered sludge is land applied in an agricultural reuse program.

     The Jackson Pike facility currently produces 230-250 wet tons per day of
dewatered sludge at a cake solids concentration of about 17 percent.  On a dry
weight basis approximately 50 dry tons per day (dtpd) of dewatered solids are
produced for ultimate disposal.  Based on recent operating records,  approxi-
mately 50 percent of the dewatered sludge is incinerated and 50 percent is
land applied.

     Table 1 identifies and describes the existing sludge management
facilities at Jackson Pike.   The facility has  provisions for short-terra
storage of both PS and WAS outside of the main liquid processing stream.  The
centrifuges for thickening  of  WAS were originally installed in 1975-76 and are
estimated to have a remaining useful  life of approximately 10 years.
Thickened sludge storage and blending is accomplished using a secondary
digester.   The anaerobic digestion facilities  consist of eight primary
digesters constructed in 1937, and eight secondary digesters constructed in
                                      B-4

-------
PRELIMINARY
  PRIMARY
AEREATIDN
SECONDARY
RAW m
INFLUENT

L.M » nc.

IN i t*unr

vir i^n

I 1UI^»



uunr

^ir iurt

I 1UIN
EFFLUENT

                               PRIMARY
                               SLUDGE
                               HOLDING
     INCINERATION
CENTRIFUGE
DEWATERING
                                       DIGESTED
                                    SLUDGE HOLDING
                                          THICKENED  RAV SLUDGE
                                          TO DEVATERING
          ANAEROBIC
          DIGESTION
                                                      THERMAL
                                                    CONDITIONING
         TO
      LANDFILL
  TO LAND
APPLICATION
                                                                      WAS
                                                                      HOLDING
                                                CENTRIFUGE
                                                THICKENING
                                                WAS

                                                THICKENED
                                                SLUDGE
                                                BLEND/STORAGE
                                                              FIG.  1
                                                              JACKSON  PIKE
                                                              EXISTING  SLUDGE
                                                              MANAGEMENT SCHEMATIC

-------
                                       TABLE 1.  EXISTING SLUDGE MANAGMENT FACILITIES
                                               JACKSON PIKE WWTP; COLUMBUS, OH
ta
      Process

      Waste Activated  Sludge Holding


      Primary  Sludge Holding

      Centrifuge  Thickening (WAS)
Anaerobic Digestion




Digested Sludge Holding

Thermal Conditioning


Centrifuge Dewatering



Incineration


Ash Lagoon


Landfill

Land Application

     Sludge Transport and
     Application


     Application Sites
                                    Facilities/Condition

                                    One 78-foot x 14-foot x 8-foot deep basin
                                    (two)  standby units

                                    One 85-foot dia.,  25.25-foot SWD

                                    Two solid bowl centrifuges
Eight primary digesters:
70-foot dia., 27.5-foot SWD
Six secondary digesters:
85-foot dia., 23.5-foot SWD

One 85-foot dia., 25.5-foot SWD

Two reactors installed 1972,
Expanded 1978 to 4 reactors

Six solid bowl centrifuges
Installed 1976
                                         Two multiple-hearth  incinerators
                                         7-hearths, 22.25-foot diameter

                                         Two lagoons
                                         City-owned  landfill
                                         Contract operation
                                         Required acreage     2000 Ac/yr
                                         Available acreage   LOOOO Ac
Capacity

0.065 MG of storage


1 KG of storage

550 gpra/unit, 400 HP/unit
Feed solids 1%
Thickened WAS 4%

Volume:  1.6 x 106 CF total
          6.3 MG primary
          6.0 MG secondary


1.0 MG of storage

200 gpm/unit
100 gpra/unit, 100 HP/unit
Feed solids 3%
Dewatered cake 16-18%

170 wet tons/day
Feed Solids 16-18%

Total storage capacity 48,000 cyj
Cleaned as needed

Ash landfilled on an as-needed
basis through contract operation
                                             Transport 130-150 tons/day
                                             Application 70-200 tons/day
                                             Approximate unit cost of $1I/wet ton

                                             Application 260 days/yr
                                             Seasonal peaks dependent
                                             on weather and cropping patterns

-------
 1950.  Current practice utilizes two of the secondary digesters as short-term
 sludge holding facilities.  One digester is used as a mixing and blend tank as
 identified previously, the second provides for storage of digested sludge
 prior to dewatering.  Based on information furnished by the city, the
 structural integrity of the digesters is adequate; however, the mechanical
 components have  reached their useful  life.  The thermal conditioning units
 have performed better  than those at Southerly and have been maintained in good
 operating condition) however, some process piping and mechanical
 rehabilitation of the system is warranted.  The centrifuge dewatering
 equipment is less than 10 years old and has been rated as adequate for future
 use.  The multiple hearth incinerators were rebuilt in 1978-79.  The units are
 estimated to have 15-20 years of remaining useful service.

     The existing land application program is accomplished through contract
 operations.   A local contractor is responsible for transport and spreading of
 the sludge.   The  application  program is operated approximately 260 days per
 year, 5-6 days per week,  applying 70 to 200 wet tons per day,  17 percent
 solids,  of dewatered cake depending on seasonal demand.  In 1985, approxi-
 mately 5800 dry tons of sludge  were land applied,  in 1986  approximately 6800
 dry tons of sludge were applied.  Dewatered sludge is  normally removed from
 the Jackson Pike  site on a uniform basis to either land application under
 favorable weather conditions or to storage sites located near the application
 sites.   The  city  also has  utilized the Jackson Pike  ash lagoons for temporary
 short-term storage of dewatered cake.  The city is pleased with the
 performance of the application program.  They believe land application has
been satisfactorily received by the community and that continuation of the
 program should be included as part of any future planning.  Adequate
application acreage appears available within a reasonable haul distance from
 the treatment facility. Short-term storage of dewatered sludge has recently
been difficult and the city should address this problem if land application is
 part of the future sludge management  alternative.

Currently, incinerator ash is slurried and pumped to ash lagoons.  The lagoons
are periodically dredged with the ash taken to a landfill.  Plant staff have
                                     B-7

-------
 indicated  that  private  landfill  operators  have declined  to accept  the ash.
 Consequently! the only repository for the ash has been the city-owned
 landfill.

 1.2  SOUTHERLY
     Figure 2 presents the sludge processing and disposal schematic currently
 in operation at Southerly.  The sludge processing operations include:

     •  Primary sludge (PS) thickening in primary clanfiers
     •  Centrifuge thickening of waste activated sludge
     •  Thickened sludge blending (i.e., PS and WAS)
     •  Centrifuge dewatering

     Dewatered sludge is disposed of in one of the following ways:

     •  Dewatered sludge is incinerated and the  ash product  is  ultimately
        landfilled.
     •  Dewatered sludge is hauled to the composting facility and distributed
        as a soil conditioner.

     The Southerly facility currently produces 350-400 wet tons per day of
dewatered  sludge at a cake solids concentration of about 17 percent.  On a dry
weight basis, approximately 64 dry tons per day (dtpd) of dewatered solids are
produced for ultimate disposal.  Based on recent operating records,
approximately 70 percent of the dewatered  sludge is incinerated and the
remaining 30 percent is composted.

     Table 2 identifies and describes the existing sludge management
facilities at Southerly.   Primary sludge is thickened to approximately 4.5
percent in the primary clarifiers.  The thickening of WAS by solid bowl
centrifuges was installed and operating in the latter part of 1986.  The PS
and WAS is directed to separate tanks in a Sludge Control Building where it is
mixed prior to being pumped to the dewatering centrifuges.
                                      B-8

-------
            PRELIMINARY
               PRIMARY
            AERATION
SECONDARY
RAW m
INFLUENT

en i HC.IN i ui_Hrur xun







IJUJIN




uv-nr

sir iu«

1
nun
EFFLUENT

w
VO
CENTRIFUGE
DEVATERING
                                                                          CENTRIFUGE
                                                                          THICKENING
                                                                             WAS
                                                                   DISSOLVED AIR
                                                                    FLOTATION
                                                                    THICKENING
                                                                    (ABANDONED)
ANAEROBIC
DIGESTION
(UNDER REHABILITATION)
                                                                                          THERMAL
                                                                                        CONDITIONING
                                                                                         (ABANDONED)
                                           DEVATERED
                                           SLUDGE
                                           STORAGE
                     INCINERATION
                                                    I
                 TO
              LANDFILL
                               TO
                            COMPOSTING
                               FIG.  2
                               SOUTHERLY
                               EXISTING  SLUDGE
                               MANAGEMENT SCHEMATIC

-------
                                   TABLE  2.   EXISTING SLUDGE MANAGMENT FACILITIES
                                             SOUTHERLY WWTP; COLUMBUS, OH
 I
I—'
o
Process

Dissolved Air Flotation
Thickening (WAS)
Centrifuge Thickening (WAS)
Anaerobic Digestion
Thermal Conditioning


Centrifuge Dewatering



Dewatered Sludge Storage

Transport to Composting


Composting


Compost Disposal


Incineration



Ash Lagoon


Landfill
Facilities/Condition

Four units (? 1900 SF/unit
(Abandoned 1978 used as
WAS concentration tanks)

Four solid bowl centrifuges
Pre-Project 88, Contract #19
Not yet fully operational

Four primary digesters:
85-foot dia., 25.25-foot SWD
Two secondary digesters;
85-foot dia., 25.25-foot SWD
Construction date 1965

Three reactors
Installed 1974, abandoned 1980

Six solid bowl centrifuges
Operational approx. 7 years
One storage bin.

4-8 trucks @ 25 wet tons
Hrs of operation 56 hrs/wk

Extended aerated static pile system
Product removed by truck


Two existing multiple hearth units;
Two new multiple hearth units
New units in start-up

Two lagoons
City-owned landfill
Capacity
200 gpra/unit
Feed solids 1%
Thickened WAS 5%

Volume of 972,000 CF total
          4.8 MG primary
          2.4 MG secondary
200 gpra/unit


100 gpm/unit
Feed solids 3.5%
Dewatered cake 16-18%

Volume of 400 cy/300 wet tons

Haul distance of 7 miles roundtrip
120-200 wet tons/day
dependent on sludge and weather

Disposal through bulk sales to
public and private consumers

150 wet tons/day existing
260 wet tons/day new
Total storage capacity 76,000 cy;
Cleaned as needed

Ash landfilled on an as-needed
basis through contract operations

-------
     The anaerobic digestion facilties have not been operational since 1978,
but are currently undergoing rehabilitation.   The  anaerobic digestion system
at Southerly consists of four primary and two secondary digesters.  The
thermal conditioning units have not operated at Southerly for almost  10 years.
Chloride stress corrosion which led to equipment deterioration and continuous
mechanical problems caused the abandonment of the thermal conditioning units.

     The existing sludge dewatering facility at the Southerly plants consists
of six centrifuges which produce a final cake solids of 16-20 percent.
Dewatered sludge  is disposed through incineration or composting.  There are
two eight-hearth incinerators at Southerly which are each capable of burning
150 wet tons per day at 20-percent solids.  Two new incinerators are in the
final stages of construction and start-up.  The  new  incinerators will each
have a disposal capacity of 260 wet tons per day based on approximately 20
percent solids in the dewatered cake.

     Dewatered sludge which is not incinerated is  hauled by city-owned
vehicles to the composting facility where it is mixed, dried, screened, and
cured as a soil conditioner.  The composting  facility  can normally accept  30
percent of the volume of solids  produced  by  the  Southerly  plant with peak
capacity of 50 percent under ideal  conditions.   These  ideal conditions relate
to dry weather and cake solids concentration.

Currently, the ash is placed in on-site ash lagoons.   These ash lagoons are
periodically cleaned  with the ash being removed to the city-owned landfill.
                                     B-ll

-------
              2.  DEVELOPMENT OF SLUDGE MANAGEMENT ALTERNATIVES

     Preliminary evaluations necessary to establish a foundation for the
preparation of the EIS required that alternative  sludge  management schemes be
identified and developed.   The  sludge management  alternatives were formulated
in light of several goals and objectives.  These  goals and objectives included
the following:

     •  The sludge management alternatives must consist of processing and
        disposal options that will provide  for environmentally  sound
        processing and ultimate disposal of sludge.
     •  The alternative must provide a  reliable means for future processing
        and disposal.
     •  The alternatives should offer some flexibility allowing the city to
        modify the processing and  disposal  methods to relieve pressures
        created by equipment failures or temporary loss of the  ultimate
        disposal methods.

     The alternatives developed should consider,  to the extent  possible,
optimizing the reuse of the existing facilities thus minimizing  implementation
costs.

     This preliminary evaluation identified alternatives for the two-plant
scenario, where Jackson Pike and Southerly would  be operated independently,
and for the one-plant scenario, where Southerly is expanded to  handle the
projected flows and loads and the Jackson Pike facility in abandoned.  Under
the two-plant scenario, three alternative sludge management schemes were
identified for Jackson Pike,  and six sludge management alternatives were
identified for Southerly.  For the one-plant  scenario  (i.e., the consolidation
of wastewater treatment at Southerly)  the sludge  management alternatives which
were identified for the Southerly two-plant scenario were considered appropri-
ate to evaluate.

     The alternatives which were identified were first subjectively screened
to eliminate those alternatives which did not  adequately address future goals
                                     B-12

-------
and objectives.   Alternatives  which advanced from the subjective evaluation
were then developed in greater detail through performance of a solids balance,
identification of required facilities and appropriate facilities sizes,  and
development of a cost estimate for each alternative.  Sizing criteria used
were consistent  with current  engineering practice.  The cost estimates
prepared during the facilities planning process for  required facilities  were
reviewed in detail.  For the most part, these estimates were considered
reasonable and reflective of facilities planning work.  The  cost  estimates
developed in this briefing paper, revised and modified the facilities planning
estimates as appropriate to account for the difference between the
alternatives developed herein and the facilities plan alternatives.   In  areas
where the facilities planning estimate was not adequately supported, this
evaluation adjusted the estimates appropriately.

2.1  JACKSON PIKE SLUDGE MANAGEMENT ALTERNATES (TWO-PLANT SCENARIO)
     Three potential sludge management alternatives were identified for  the
Jackson Pike WWTP.   Each alternative is discussed separately in the  following
paragraphs.

2.1.1  Jackson Pike Sludge Management Alternative JP-A
     Figure 3 presents  the sludge managment schematic for alternative JP-A.
The alternative would involve the following sludge processes:

     •  Gravity thickening of PS
     •  Centrifuge  thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Centrifuge  dewatering

     Dewatered digested sludge would be land applied in an agricultural  reuse
program.
                                      B-13

-------
PRELIMINARY
PRIMARY
AERATION
  SECONDARY
CLARIFICATION
INFLUENT











EFFLUENT
	 i- 	 	 Sr—

                              GRAVITY
                              THICKENING
                              PS
                                              CENTRIFUGE
                                              THICKENING
                                              WAS


                                              THICKENED
                                              SLUDGE
                                              BLEND/STDRAGE
                      CENTRIFUGE
                      DEWATERING
               DIGESTED
            SLUDGE HOLDING
          ANAEROBIC
          DIGESTION
                          I
                        TO LAND
                      APPLICATION
                                     FIG. 3
                                     JACKSON PIKE
                                     ALTERNATIVE JP-A SLUDGE
                                     MANAGEMENT SnHF.MATIC

-------
     Based on the subjective review of this management alternative, it was
eliminated from  further  consideration.  Relying strictly on  land application,
for ultimate disposal of the projected sludge quantities, lacks the
flexibility critical to maintaining a successful disposal program.  This lack
of flexibility would require an increased degree of conservatism in design and
implementation to ensure plant performance during an interruption of the
disposal process.  Furthermore, the seasonal nature of the agricultural
application program would  require  substantial sludge storage facilities.
Normally, such storage facilities experience community relation difficulties
associated with  aesthetics and odors.

2.1.2  Jackson Pike Sludge Management Alternative JP-B
     Figure 4 presents  the  sludge management schematic for alternative JP-B.
This alternative would  consist of the following sludge processes.

     *  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Centrifuge dewatering
     •  Incineration

     Dewatered sludge would be disposed of as follows:

     •  50 percent of the dewatered sludge would be incinerated and the ash
        product landfilled.
     *  50 percent of the dewatered sludge would be land  applied.

     The 50:50  ratio  is approximately consistent with current Jackson Pike
disposal practices.   In  this  brief  analysis,  a comprehensive  review of alter-
nate ratios to  determine an optimum was not performed.   Since land application
is not a limiting factor and the incinerators at Jackson Pike require some
rehabilitation,  a split equal to current practices appears appropriate.
                                      B-15

-------
PRELIMINARY
  PRIMARY
              AERATION
         SECONDARY
RAW
INFLUENT

C.M 1 PIC.

11 i i/unr

(ir IUM

1 iUIN



Ul_fth

ur iuft

HUN
EFFLUENT

                              GRAVITY
                              THICKENING
                              PS
                                               CENTRIFUGE
                                               THICKENING
                                               WAS


                                               THICKENED
                                               SLUDGE
                                               BLEND/STDRAGE
    INCINERATION
CENTRIFUGE
DEVATERING
JGE   I
ING   I    ]
L^J SLU1
                                      DIGESTED
                                   SLUDGE HOLDING
ANAEROBIC
DIGESTION
         t
    t
         TO
      LANDFILL
  TO LAND
APPLICATION
                                                            FIG. 4
                                                            JACKSON  PIKE
                                                            ALTERNATIVE JP-B SLUDGE
                                                            MANAGEMENT SCHEMATIC

-------
     Subjective screening of JP-B indicated that the alternative adequately
addressed the goals and objectives.   Therefore,  it  was  developed for a more
detailed evaluation.  Table 3 describes the facilities required and presents
the estimated costs to implement  JP-B.

2.1.3  Jackson Pike Sludge Management Alternative JP-C
     Figure 5 presents the sludge management schematic  for alternative JP-C.
This alternative would consist of the following sludge processes.

     *  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Stabilization by thermal conditioning
     •  Centrifuge dewatering
     •  Incineration

     Dewatered sludge would be disposed of as follows:

     •  50 percent of the dewatered  sludge would be incinerated and the ash
        product landfilled.
     •  50 percent of the dewatered  sludge would be land applied.

     As previously discussed,  the 50:50  disposal ratio  is  consistent with
current practice.   The stabilization processes  would each handle 50 percent of
the thickened sludges produced under normal operating conditions.  The
dewatered, thermally conditioned sludge would be incinerated  while the
dewatered, digested sludge would be  land  applied.

     Sludge management alternative JP-C was also determined by the subjective
screening to merit more detailed consideration.  Table  4 describes the
facilities required and presents the estimated  costs to implement JP-C.
                                     B-17

-------
                                   TABLE 3
                  JACKSON PIKE SLUDGE MANAGEMENT ALTERNATIVE
                          JP-B (Two-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping              $6,070,000
     Three (3) new; 65-foot dia. x 10-foot SWD

Centrifuge Thickening WAS                                      $4,500,000
     Two (2) existing; 500 gpm
     One (I) new; 500 gpra

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                            $9,170,000
     Six (6) existing; 85-foot dia. x 23.5-foot SWD
     Four (4) existing, 70-foot dia. x 27.5-foot SWD

Centrifuge Dewatering                                          $  490,000
     Six (6) existing; 1200 Ib/hr

Incineration
     Two (2) existing, 7 hearth, 200 wet ton/day @ 20% solids  $3,600,000

Landfill
     Contract operations included with O&M

Land Application
     Contract operations included with O&M                         —

                         Capital Cost                         $23,830,000

                         Annual Operation and                 $ 3,070,000
                           Maintenance Cost

                         Present Worth (JP-B Two-Plant)       $45,930,000
                                      B-18

-------
            PRELIMINARY
  PRIMARY
AERATION
SECONDARY
RAW
INFLUENT

c.rt i nc.

IN i wL-rnr

tir luri

I IUI1



«-unr

iiir jiwn

lALin
EFFLUENT

                                           GRAVITY
                                           THICKENING
                                           PS
f
c-1
\0
                 INCINERATION
CENTRIFUGE
DEWATERING
                                                   DIGESTED
                                                SLUDGE HOLDING
                                                      THICKENED RAV SLUDGE
                                                      TO DEWATERING
                     I
                                                CENTRIFUGE
                                                THICKENING
                                                WAS


                                                THICKENED
                                                SLUDGE
                                                BLEND/STDRAGE
          ANAEROBIC
          DIGESTION
                               THERMAL
                             CONDITIONING
                     TO
                  LANDFILL
  TO  LAND
APPLICATION
                                                                         FIG. 5
                                                                         JACKSON PIKE
                                                                         ALTERNATIVE JP-C SLUDGE
                                                                         MANAGEMENT SCHEMATIC

-------
                                   TABLE 4
                  JACKSON PIKE SLUDGE MANAGEMENT ALTERNATIVE
                          JP-C (Two-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping               $6,070,000
     Three (3) new; 65-foot dia. x 10-foot SWD

Centrifuge Thickening WAS                                      $4,500,000
     Two (2) existing; 500 gpm
     One (1) new; 500 gpm

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                            $7,750,000
     Six (6) existing, 85-foot dia. x 23.5-foot SWD
     Two (2) existing; 70-foot dia. x 27.5-foot SWD

Thermal Conditioning
     Two (2) existing; 200 gpm                                 $3,000,000

Centrifuge Dewatering
     Six (6) existing; 1200 ib/hr                              $  490,000

Incineration
     Two (2) existing; 7 hearth, 200 wet ton/day @ 20% solids  $3,600,000

Landfill
     Contract operations included with O&M                         —

Land Application
     Contract operations included with O&M                         —

                         Capital Cost                         $25,410,000

                         Annual Operations and                $ 3,770,000
                           Maintenance Cost

                         Present Worth (JP-C Two-Plant)       $52,700,000
                                      B-20

-------
2.2  SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVES (TWO-PLANT SCENARIO)
     Six potential sludge management alternatives were identified for the
Southerly WWTP.  Each alternative  is discussed separately in the following
paragraphs.

2.2.1  Southerly  Sludge  Management Alternative SO-A
     Southerly sludge management alternative SO-A is graphically depicted by
the schematic presented  in Figure  6.  Alternative SO-A would utilize the
following sludge processes:

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Centrifuge dewatering
     •  Incineration

     Dewatered digested sludge would be incinerated and landfilled.

     Alternative SO-A was eliminated from further consideration for  two basic
reasons.   First,  the alternative proposes  to abandon the  existing compost
operations.   Such a  move would forfeit the substantial investment the city has
placed in the relatively new  facilities and would substitute disposal of all
of the sludge product by landfilling in lieu of  the current  practice which
reuses a portion of the sludge as soil conditioner.   Second,  alternative SO-A
lacks the flexibility needed  to  allow the  city to modify  disposal operations
subject to equipment failures or external pressures such as public dissatis-
faction or regulatory requirements.

2.2.2   Southerly Sludge Management Alternative SO-B
     Figure 7 presents the sludge management schematic for alternative  SO-B.
The alternative would feature the following sludge processes:
                                     B-21

-------
            PRELIMINARY
PRIMARY
AERATION
 SECONDARY
CLARIFICATION
INFLUENT











EFFLUENT

CO

K>
N»
                     INCINERATION
                 TO
              LANDFILL
                                           GRAVITY
                                           THICKENING
                                           PS



__—
"^•r^™ •" 	
CENTRIFUGE
DEWATERING


                                           THICKENED
                                           SLUDGE
                                           BLEND/STOTAGE
       ANAERDBIC
       DIGESTION
       (UNDER REHABILITATION)
                                      CENTRIFUGE
                                      THICKENING
                                         WAS
                                           DEVATERED
                                           SLUDGE
                                           STORAGE
                                      FIG.  6
                                      SOUTHERLY
                                      ALTERNATIVE  SO-A SLUDGE
                                      MANAGEMENT SCHEMATIC

-------
            PRELIMINARY
               PRIMARY
            AERATION
SECONDARY
RAW '*
INFLUENT

i^n i nc.

IN i ounr

Mr ion


i lUl^t



i>i_rtr

1.1 r j.wt

I iUIN
EFFLUENT

to

NJ
U)
CENTRIFUGE
DEVATERING
                                          GRAVITY
                                          THICKENING
                                          PS
                                          THICKENED
                                          SLUDGE
                                          BLEND/STOTAGE
ANAEROBIC
DIGESTION
(UNDER  REHABILITATION)
                                                    CENTRIFUGE
                                                    THICKENING
                                                       WAS
                                          DEWATERED
                                          SLUDGE
                                          STORAGE
                                                   I
                                                   TO
                                                COMPOSTING
                                                    FIG.  7
                                                    SOUTHERLY
                                                    ALTERNATIVE  SO-B SLUDGE
                                                    MANAGEMENT SCHEMATIC

-------
     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Centrifuge dewatering
     •  Composting

     Ultimate sludge disposal would be accomplished through the marketing and
distribution of compost as a soil conditioner.

     The subjective evaluation eliminated alternative SO-8 from further
consideration.   Flexibility to alter disposal operations  was the critical
factor in the evaluation.   Composting the entire volume of dewatered sludge
would mean a 2-3 fold increase in compost product over current conditions.  If
Southerly were operated in a one-plant scenario, 5-6 times the current compost
product would be produced.   An  aggressive  and successful  marketing program
would be mandatory to  locate and maintain sufficient receptors for the
compost.  The long-term reliability of an alternative which relies solely on
distribution of compost was not considered adequate to merit more detailed
development and evaluation.
                       >
2.2.3  Southerly Sludge Management Alternative SQ-C
     The sludge management schematic for alternative SO-C is presented in
Figure 8.   Southerly  sludge management alternative SO-C would consist of the
following sludge processes:

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Centrifuge dewatering
     •  Composting
     •  Incineration
                                      B-24

-------
            PRELIMINARY
PRIMARY
AERATION
SECONDARY
RAW IR
INFLUENT

L.M \ TIC.

IN i ui_«r

u,r ion

i iun



uunr

t±r J.UH

1 1UIN
EFFLUENT

Ul
                    INCINERATION
                                          GRAVITY
                                          THICKENING
                                          PS




CENTRIFUGE
DEVATERING


                                          THICKENED
                                          SLUDGE
                                          BLEND/STOTAGE
       ANAEROBIC
       DIGESTION
       (UNDER REHABILITATION)
                                      CENTRIFUGE
                                      THICKENING
                                         WAS
                                          DEVATERED
                                          SLUDGE
                                          STORAGE
                TO
             LANDFILL
                TO
            COMPOSTING
                  FIG. 8
                  SOUTHERLY
                  ALTERNATIVE SO-C SLUDGE
                  MANAGEMENT SCHEMATIC

-------
     Dewatered sludge would be disposed of as follows:
     •  75 percent of the dewatered sludge would be incinerated,  and the ash
        product would be  landfilled.
     *  25 percent of the dewatered sludge would be composted and the compost
        would be distributed as a soil conditioner.
     The 75:25 ratio is approximately consistent with current Southerly
disposal practices.   The digestion facilities would be sized to process that
portion of the sludge that would be incinerated.  The portion of the sludge
that would be composted would not receive stabilization prior to dewatering.

     Alternative SO-C represents current practice at Southerly when the
digestion facilities are operational.   Therefore, subjective screening
concluded that the alternative merits more detailed development and
evaluation.   Table 5 describes the facilities required and presents the
estimated costs to implement  SO-C.

2.2.4  Southerly Sludge Management Alternative SO-D
     Southerly sludge management alternative  SO-D is graphically depicted by
the schematic presented in Figure 9.  Alternative SO-D would utilize the
following sludge processes.

     *  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Centrifuge dewatering
     •  Composting
     •  Incineration

     Ultimate disposal of the sludge would be accomplished through one of the
following disposal options.
                                      B-26

-------
                                  TABLE 5
                   SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVE
                          SO-C (Two-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping               $2,520,000
     Four (4) existing; 45-foot dia. x 17-foot SWD

Centrifuge Thickening WAS                                      $2,000,000
     Four (4) existing; 250 gpm, 1250 Ib/hr
     One (1) new; 250 gpm, 1250 Ib/hr

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                            $4,280,000
     Six (6) existing, 85-foot dia. x 25.25-foot SWD

Centrifuge Dewatering                                          $5,120,000
     Six (6) existing; 1000 Ib/hr
     Two (2) new; 1000 Ib/hr

Dewatered Sludge Storage                                       $1,300,000
     One (I) new; 400 cy plus material handling

Composting
     Existing Facilities; 120 wet ton/day @ 20% solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids

Landfill
     Contract operations included with O&M

                         Capital Cost                        $15,220,000

                         Annual Operation and                $ 3,260,000
                           Maintenance Cost

                         Present Worth (SO-C Two-Plant)      $39,080,000
                                     B-27

-------
PRELIMINARY
PRIMARY
                                                       AERATION
                          SECONDARY
RAW
INFLUENT

c.n i rib.

M i L/L,nr

^AT iwrt

1 AUI1



uurtr

nr ion

i iurt
EFFLUENT

w

oo
         CENTRIFUGE
         DEVATERING
         INCINERATION
    TO
  LANDFILL
                               GRAVITY
                               THICKENING
                               PS
                               THICKENED
                               SLUDGE
                               BLEND/STOTAGE
       ANAEROBIC
       DIGESTION
       (UNDER REHABILITATION)
                                      CENTRIFUGE
                                      THICKENING
                                         VAS
                               DEVAJERED
                               SLUDGE
                               STORAGE

   TO
  LA'NB
                                        I
    TO
CDKPuST
                       APPLICATION
                                                                          FIG.  9
                                                                          SOUTHERLY
                                                                          ALTERNATIVE SO-D SLUDGE
                                                                          MANAGEMENT SCHEMATIC

-------
     •  25 percent of the sludge would be dewatered, composted, and distri-
        buted as a soil  conditioner.
     •  25 percent of the sludge would be digested, dewatered, and land
        applied.
     •  50 percent of the sludge would be digested, dewatered, incinerated,
        and landfilled.
     Alternative SO-D meets the goals and objectives of the subjective
screening.   The alternative offers continuation of the  existing incineration
and composting processes at Southerly and introduces land application as a
disposal process.   The city has indicated there is adequate acreage suitable
for land application within an economically feasible distance of the plant.
Alternative SO-D was advanced for further development and evaluation.  Table 6
describes the required facilities and presents the estimated costs to
implement SO-D.

2.2.5  Southerly Sludge Management Alternative SO-E
     Figure 10 presents the sludge management schematic for Alternative SO-E.
Southerly sludge management alternative SO-E would consist of the  following
sludge processes:

     •  Gravity thickening PS
     •  Centrifuge thickening of WAS
     •  Thickened  sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Centrifuge dewatering
     •  Composting

     Dewatered sludge would be disposed of as follows:

     •  50 percent would be composted and distributed as a soil conditioner.
        Sludge sent to compost would not go through the digestion  process.
     *  50 percent would be land applied as a fertilizer to agricultural
        acreage within a reasonable distance from the plant.
                                     B-29

-------
                                  TABLE 6
                   SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVE
                          SO-D (Two-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping              $2,520,000
     Four (4) existing; 45-foot dia. x 17-foot SWD

Centrifuge Thickening WAS                                     $2,000,000
     Four (4) existing; 250 gpra, 1250 Ib/hr
     One (1) new; 250 gpra, 1250 Ib/hr

Thickened Sludge Storage/Blend                                    —
     Existing Facilities Reused

Anaerobic Digestion                                           $4,280,000
     Six (6) existing; 85-foot dia. x 25.25-foot SWD

Centrifuge Dewatering                                         $5,120,000
     Six (6) existing; 1000 Ib/hr
     Two (2) new} 1000 Ib/hr

Dewatered Sludge Storage                                      $1,300,000
     One (1) new; 400 cy plus material handling

Composting
     Existing Facilities, 120 wet ton/day @ 20Z solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids

Landfill
     Contract operations included with O&M

Land Application
     Contract operations included with O&M                        —

                         Capital Cost                        $15,220,000

                         Annual Operation and                $ 3,340,000
                           Maintenance Cost

                         Present Worth (SO-D Two-Plant)      $39,680,000
                                     B-30

-------
            PRELIMINARY
PRIMARY
AERATION
SECONDARY
RAW '*
INFLUENT

C.M i nc.

IN i uunr

\ir iv*n

i lun



uuttr

ur lun

IIUIN
EFFLUENT

w

LO
                                          GRAVITY
                                          THICKENING
                                          PS

1

CENTRIFUGE
DEWATERING


                                          THICKENED
                                          SLUDGE
                                          BLEND/STOTAGE
       ANAEROBIC
       DIGESTION
       (UNDER REHABILITATION)
                                     CENTRIFUGE
                                     THICKENING
                                         VAS
                                          DEVATERED
                                          SLUDGE
                                          STORAGE
                                      I
                                      TO
                                     LAND
                                  APPLICATION
                TO
            COMPOSTING
                  FIG. 10
                  SOUTHERLY
                  ALTERNATIVE SO-E SLUDGE
                  MANAGEMENT SCHEMATIC

-------
     Based on Che subjective evaluation alternative SO-E was eliminated from
further consideration.  The reliability of utilizing only compost distribution
and land application  as ultimate  disposal options  did not appear reasonable.
The plant currently practices incineration and relies heavily on incineration
and landfill to dispose of sludge.  Furthermore,  it is critical that the plant
have a disposal method that is completely within their  control,  i.e.,  not
influenced by sludge quality,  weather, market demand, public perception or
other external  pressures.

2.2.6  Southerly Sludge Management Alternative SO-F
     Figure 11 presents the sludge management schematic  for  Alternative  SO-F.
Ths sludge management system would consist of the following processes:

     •  Gravity thickening PS
     •  Centrifuge thickening WAS
     •  Thickened sludge storage and blending
     •  Centrifuge dewatering
     •  Composting
     *  Incineration

     Ultimate disposal of  the sludge would be accomplished through one of the
following disposal options.

     •  SO percent would be composted and distributed as a soil conditioner.

     •  50 percent would be incinerated and landfilled.

     Alternative SO-F is similar  to alternative SO-C with the exception that
digestion is not provided.   The evaluation of  alternative SO-F  was  prompted
due to the fact that digestion prior to incineration has normally not proven
to be cost-effective.   Although digestion diminishes the amount of solids to
be handled in subsequent processes, the heat content of  digested sludge is
significantly reduced.  Furthermore,  digested sludge tends to be more
                                     B-32

-------
PRE
RAW "^
INFLUENT

:LIMINARY PRIMARY AERATION SECONDARY
EATMENT CLARIFICATION CLARIFICATION










EFFLUENT

w

to
U>
                                          GRAVITY
                                          THICKENING
                                          PS
                                          THICKENED
                                          SLUDGE
                                          BLEND/STOTAGE
                                                    CENTRIFUGE
                                                    THICKENING
                                                       WAS
CENTRIFUGE
DEVATERING
                                          DEVATERED
                                          SLUDGE
                                          STORAGE
                     INCINERATION
                TO
              LANDFILL
                              TO
                           COMPOSTING
FIG.  11
SOUTHERLY
ALTERNATIVE SO-F  SLUDGE
MANAGEMENT  SCHEMATIC

-------
difficult Co dewater  Chan combined  raw sludges.  These factors cause digested
sludge to be more difficult, and consequently more expensive on a unit basis
(i.e.  dollars  per dry ton),  than raw sludges to incinerate.  Since the
Southerly plant has a portion of the required digestion facilities and
adequate incineration facilities in place, the cost effectiveness of digestion
prior to incineration is less dependent on capital cost than an evaluation
where these facilities  are  not  in place.

     Table 7 describes the required  facilities and presents the estimated
costs to implement SO-F.

2.3  SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVES (ONE-PLANT SCENARIO)
     The three sludge management alternatives that were advanced from the
subjective screening phase for the Southerly two-plant scenario are considered
viable for Southerly one-plant scenario.  These three alternatives were
previously identified as SO-C, SO-D, and SO-F.   The remaining three
alternatives,  which were identified for the two plant scenario, are not
considered viable for the one-plant scenario for the same reasons previously
discussed.

     The sludge management  schematics  for  alternatives SO-C, SO-D, and SO-F
have been presented in Figures 8, 9, and 11 respectively.   Table 8 identifies
the required facilities and presents the estimated cost to implement sludge
management alternative  SO-C under a one-plant  scenario.  Table 9  presents the
facilities and estimated costs  to implement  SO-D  under a  one-plant scenario.
Table 10 presents the facilities and estimated  costs  to implement SO-F under a
one-plant scenario.
                                     B-34

-------
                                  TABLE 7
                   SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVE
                          SO-F  (Two-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping             $2,520,000
     Four (4) existing; 45-foot dia. x 17-foot SWD

Centrifuge Thickening WAS                                    $2,000,000
     Four (4) existing; 250 gpro, 1250 Ib/hr
     One (1) new; 250 gpra, 1250 Ib/hr

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Centrifuge Dewatering                                        $8,750,000
     Six (6) existing; 1000 Ib/hr
     Four (4) new; 1000 Ib/hr

Dewatered Sludge Storage                                     $1,300,000
     One (1) new; 400 cy plus material handling

Composting
     Existing Facilities; 120 wet ton/day @ 20% solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids

Landfill
     Contract operations included with O&M

                         Capital Cost                       $14,570,000

                         Annual Operation and               $ 3,940,000
                           Maintenance Cost

                         Present Worth (SO-C Two-Plant)     $42,770,000
                                     B-35

-------
                                  TABLE 8
                   SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVE
                          SO-C (One-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping              $5,070,000
     Four (4) existing; 45-foot dia. x 17-foot SWD
     Two (2) new; 85-foot dia. x 10-foot SWD

Centrifuge Thickening WAS                                     $5,600,000
     Four (4) existing; 250 gpra, 1250 Ib/hr
     Four (4) new; 250 gpm, 1250 Ib/hr

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                          $11,460,000
     Six (6) existing; 85-foot dia. x 25.25-foot SWD
     Four (4) new; 85-foot dia. x 25.25-foot SWD

Centrifuge Dewatering                                        $21,040,000
     Six (6) existing; 1000 Ib/hr
     Nine (9) new; 1000 Ib/hr

Dewatered Sludge Storage
     One (I) new; 400 cy plus material handling               $1,300,000

Composting
     Existing Facilities; 120 wet ton/day @ 20% solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids
     Rehabilitate existing                                    $1,300,000

Landfill
     Contract operations included with O&M

                         Capital Cost                        $45,770,000

                         Annual Operation and                $ 6,080,000
                           Maintenance Cost

                         Present Worth (SO-C One-Plant)      $89,590,000
                                     B-36

-------
                                  TABLE 9
                   SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVE
                          SO-D (One-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping              $5,070,000
     Four (4) existing; 45-foot dia. x 17-foot SWD
     Two (2) new; 85-foot dia. x 10-foot SWD

Centrifuge Thickening WAS                                     $5,600,000
     Four (4) existing; 250 gpra, 1250 Ib/hr
     Four (4) new; 250 gpm, 1250 Ib/hr

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                          $11,460,000
     Six (6) existing; 85-foot dia. x 25.25 foot SWD
     Four (4) new; 85-foot dia. x 25.25 foot SWD

Centrifuge Dewatering                                        $21,040,000
     Six (6) existing; 1000 Ib/hr
     Nine (9) new; 1000 Ib/hr

Dewatered Sludge Storage
     One (1) new; 400 cy plus material handling               $1,300,000

Composting
     Existing Facilities; 120 wet ton/day @ 20Z solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids
     Rehabilitate existing                                    $1,300,000

Landfill
     Contract operations included with O&M                        —

Land Application
     Contract operations included with O&M                        —

                         Capital Cost                        $45,770,000

                         Annual Operation and                $ 6,230,000
                           Maintenance Cost

                         Present Worth (SO-D One-Plant)      $90,710,000
                                     B-37

-------
                                  TABLE 10
                   SOUTHERLY SLUDGE MANAGEMENT ALTERNATIVE
                          SO-F (One-Plant Scenario)
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping              $5,070,000
     Four (4) existing; 45-foot dia. x 17-foot SWD
     Two (2) new; 85-foot dia. x 10-foot SWD

Centrifuge Thickening WAS                                     $5,600,000
     Four (4) existing; 250 gpra, 1250 Ib/hr
     Four (4) new; 250 gpra, 1250 Ib/hr

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Centrifuge Dewatering                                        $27,430,000
     Six (6) existing; 1000 Ib/hr
     Fourteen (14) new; 1000 Ib/hr

Dewatered Sludge Storage
     One (1) new; 400 cy plus material handling               $1,300,000

Composting
     Existing Facilities; 120 wet ton/day @ 20% solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids
     Rehabilitate existing                                    $1,300,000

Landfill
     Contract operations included with O&M

                         Capital Cost                        $40,700,000

                         Annual Operation and                $ 7,110,000
                           Maintenance Cost

                         Present Worth (SO-F One-Plant)      $92,440,000
                                     B-38

-------
               3.  EVALUATION OF SLUDGE MANAGEMENT ALTERNATIVES

     Sludge management alternatives were evaluated based on cost-
effectiveness, dewatering, system  redundancy, and ultimate  disposal.  Facility
planning information  is  included for each of  the criteria.  The results of the
evaluation are discussed in  the following sections.

3.1  COST EFFECTIVENESS  OF SLUDGE MANAGEMENT ALTERNATIVES
     Table 11 presents the potential sludge management alternatives and the
associated present worth of  each.   These alternatives and the present worth
costs will be utilized in a  subsequent briefing paper to assess the cost
effectiveness of the one-plant and two-plant  scenarios.

     Alternative JP-fi, which provides for digestion, dewatering, and a 50:50
split of the sludge to land application and incineration and landfill,  is the
cost-effective sludge management scheme  at  Jackson Pike.  This alternative is
approximately 15 percent  less costly than JP-C which proposes to retain the
thermal conditioning units for processing a portion of the sludge.

     The lowest present worth of the Southerly two-plant alternatives is
exhibited by SO-C.  Practically speaking,  however,  present worth of SO-D is
considered equal to that of SO-C.   At this level of planning analysis the  1.5
percent present worth difference is not a significant factor in selection of
an alternative.   In light of  this  fact, SO-D is  the recommended sludge
management alternative for the Southerly two-plant scenario.  Alternative SO-D
offers more flexibility  in that three disposal  methods are utilized (i.e.,
marketing of a compost product, land application of dewatered, digested
sludge, and landfilling of incinerator ash.)   SO-C on  the other hand utilizes
only two of the disposal  options,  not providing for land application.

     Alternative SO-F was developed to evaluate the cost effectiveness  of
digestion prior to incineration.   SO-F proposes  dewatering of raw sludge with
approximately 50 percent  of  the dewatered cake  incinerated.  Alternative SO-F
                                     B-39

-------
              TABLE 11
     PRESENT WORTH COMPARISON
OF SLUDGE MANAGEMENT ALTERNATIVES
SCENARIO
TWO-PLANT



ONE-PLANT

ALTERNATIVE
JP-B
JP-C
SO-C
SO-D
SO-F
SO-C
SO-D
SO-F
PRESENT WORTH
$ 45,930,000
$ 52,700,000
$ 39,080,000
$ 39,680,000
$ 42,777,000
$ 89,590,000
$ 90,710,000
$ 92,440,000
RECOMMENDED
ALTERNATIVES


JP-B + SO-D
$ 85,610,000


SO-D
$ 90,710,000
 ALTERNATIVE PROCESS / DISPOSAL INDEX

DIGESTION
THERMAL CONDITIONING
DEVATERING
INCINERATION
COMPOST
LAND APPLICATION
LANDFILL
REFERENCE
JP-B
•

•
•

•
•
FIG. 4
JP-C
•
•
•
•

•
•
FIG, 5
SO-C
•

•
•
•

•
FIG. 8
SO-D
•

•
•
•
•
•
FIG. 9
SO-F


•
•
•

•
FIG. 11
              B-40

-------
differs from  SO-C only  in  that  the  digestion  provided  in  SO-C  is not included
in SO-F.  From Table  11 it can  be seen that alternative SO-F  (i.e., incinera-
tion without  digestion) exhibits a  present worth approximately 9 percent
higher  than alternative SO-C.

     Digestion prior  to incineration has proven to be cost effective in this
case primarily due  to the  sunken  capital invested in the  Southerly  facilities.
Southerly has six existing anaerobic digesters and four multiple hearth
incinerators  in place (i.e., two existing and  two in startup).   The  new
incinerators are equipped with a waste heat recovery system which reclaims
waste heat from the incinerators to meet digestion and building heat require-
ments.  The waste heat  recovery system allows for the digester gas produced to
be used as a  fuel for the  incinerators, thus substantially reducing the
supplemental  fuel requirements  of the  incinerators.

     The existing digestion, incineration,  and waste heat recovery facilities
conservatively represent 20-25 million dollars of sunken capital.  If these
facilities were not in place,  the  required  additional capital costs  would be
sufficient to show  incineration of  raw sludge  to be more cost  effective than
digestion prior to  incineration.

     Under the one-plant scenario,  sludge management alternatives SO-C and
SO-D represent the lowest  present worth options.  Again digestion prior to
incineration (SO-C)  is a lower cost alternative than digestion  of raw sludge
(SO-F).  However,  the  difference between SO-C  and  SO-F  has been diminished to
approximately 3 percent.  This smaller difference is due to the fact that four
new digesters are required in the one-plant scenario.  The cost of the four
new digesters weakens the  impact  of the sunken capital  in the cost effective-
ness analysis and thus lowers the present worth difference.

     As with  the Southerly two-plant scenario, alternative SO-D is recommended
as the preferrable Southerly one-plant  sludge  management scheme.   For the
reasons previously discussed,  SO-D provides  the city with three reliable
disposal paths and adequate flexibility.
                                      B-41

-------
 3.2  SLUDGE DEWATERING
     The RFPU evaluated the sludge dewatering component of the various
 alternatives in light of the existing centrifuge equipment currently in
 service at Southerly.  The design criteria  for  the  dewatering centrifuges  was
 revised a number of  times  over  the course  of the planning and design.
 Facilities planning documents indicate the centrifuges will be rated at
 120 gpra with a  feed  solids of 5  percent, or approximately 3000 Ibs/hr.
 Subsequently, the GERBOD revised the design criteria for the centrifuges to
 1000 Ibs/hr.   Based on a feed  solids  of 4 percent,  the GERBOD assumed a
 dewatered cake of 20-21 percent could be produced.   The GERBOD further
 indicated that the successful,  efficient  operation  of the  dewatering process
 is critical to the overall cost of sludge processing and disposal.   The GERBOD
 noted that increasing the  solids content  of the dewatered cake reduces
 incinerator fuel consumption and subsequent handling costs,  and increases  the
 efficiency of downstream processes.   The  GERBOD concluded  recommending that
 alternative dewatering equipment (specifically belt presses  and diaphragm
 plate and frame (DPF) presses) be  fully evaluated to  optimize the  sludge
 processing scheme.

     As a result of the GERBOD's  recommendations,  pilot scale testing of
 dewatering equipment was conducted.   The pilot  testing and subsequent
dewatering evaluations were documented in the Preliminary Design Evaluation of
 Sludge Dewatering,  December 12,  1986.  The  evaluation acknowledges  that the
 tests were carried out under less than optimum conditions.  Tests were
 performed on unthickened,  undigested  sludge of  indeterminate composition.   The
 proportions of primary and waste activated sludge fed to the dewatering
devices could only be approximated.

     The dewatering evaluation selected the diaphragm plate and frame press as
 the optimum dewatering alternative.   The  evaluation recommended installation
of four DPF presses in Project  88 and the future installation of  an additional
 five DPF presses—to provide a  total  of nine presses.  The six (6)  existing
                                     B-42

-------
dewatering  centrifuges  will  become standby units after the Project 88 improve-
ments and will eventually be abandoned as the treatment plant project proceeds
and  the  remaining DPF presses  are  installed.

     The dewatering evaluation also recommended that the diaphragm plate and
frame presses be  located in  the existing thermal conditioning building with
appropriate modifications to that structure.  The estimated  cost for  implemen-
ting the DPF recommendation, presented in the dewatering evaluation,  was
approximately $22,000,000   The cost estimate previously presented in the
facilities plan and utilized in the cost-effective  evaluation for implementing
the centrifuge dewatering alternative was  approximately  $12,000,000.   Both of
these estimates are based on the one-plant  scenario.

     In the evaluation of dewatering alternatives the capacity of the
centrifuges was again revised.   Based on the interpretation of pilot  test
results, the capacity of the centrifuges was established at 700-750 ib/hr.  As
a result, 17 centrifuges (i.e.,  14  operating,  3  standby)  were needed  to
dewater approximately 240,000 Ibs/day of sludge.

     Following the pilot testing, one of the existing centrifuges was  modified
and upgraded to allow a full-scale test.  The feed  sludges  used  were  still not
representative of the future anaerobically digested sludge.   Review of the
data from this full-scale demonstration indicates that  the  modified centrifuge
could process in excess of 1000  Ibs/hr  (i.e.,  1300-1700 Ibs/hr)  on various
blend ratios of the existing sludge.

     Due to the sunken investment in the six existing centrifuges, the
established design capacity of modified  units is  important  to the selection of
the optimum dewatering alternative.
                                     B-43

-------
      Based on  the data contained in the Preliminary Design Evaluation of
 Sludge  Dewatering, use of less than 1000 Ibs/hr as the rated capacity of the
 modified  centrifuge  seemed  unusually  conservative.  Consequently, an
 independent cost-effective evaluation of dewatering was performed using
 1000  Ibs/hr as the design capacity.  This independent  analysis  was performed
 based on  the Southerly one-plant scenario.   The results of this analysis are
 summarized  in  Table  12.  Since the effectiveness of the dewatering devices
 impact  downstream processing units, the operational costs of incineration and
 ash disposal have been included in the cost-effective analysis.  The
 centrifuge dewatering option at $40,800,000 exhibits  a 7 percent  lower present
 worth than  the DPF option at a present  worth of $43,600,000.

     As a result of the higher rated capacity of the centrifuges, fewer units
 would be  required.   Fifteen  units,  12  operating and 3  standby would be
 adequate.   Assuming the thermal conditioning building  was the logical location
 for the dewatering facility, a smaller expansion of that structure would be
 necessary.  Fewer  centrifuges  and  associated equipment and less  building
 expansion result in the estimated cost of centrifuge dewatering approximately
 equal to  that  of the OFF press option (i.e., $22,000,000).

     The operation and maintenance costs associated with the  two  dewatering
 alternatives are  reasonably  consistent with those  developed in  the Preliminary
 Design Evaluation of Sludge  Dewatering.   The DPF presses are  approximately
45 percent more expensive to operate and  maintain  primarily due to higher
 labor costs and higher chemical costs.

     The centrifuges  will provide a 20 percent cake solids concentration,
 whereas the DPF presses will provide  a 25 percent cake solids concentration.
Consequently,  the operating  cost  of incineration is approximately 80 percent
higher for the centrifuge dewatered sludge.  The supplemental fuel required to
burn off the additional water is  the major  reason for this difference.   From
Table 12,  it can be seen that  operational costs for the incineration process
are $500,000 higher  under the  centrifuge dewatering alternative.    The
Preliminary Design Evalution of  Sludge Dewatering identified a $750,000
                                     B-44

-------
                        TABLE 12
             PRESENT WORTH COMPARISON
             OF  DEWATERING ALTERNATIVES
PROCESS
DEVATERING
INCINERATION
ASH DISPOSAL
TOTAL
PRESENT
WORTH
CENTRIFUGE
ALTERNATIVE
CAPITAL
$ 21,040,000
$ 0
$ 0
$ 21,040,000
D & M
$ 1,300,000
$ 1,100,000
$ 330,000
$ 2,730,000
$ 40,800,000
DPF PRESS .
ALTERNATIVE
CAPITAL
$ 21,920,000
$ 0
$ 0
$ 21,920,000
0 & M
$ 1,910,000
$ 600,000
$ 490,000
$ 3,000,000
$ 43,600,000
BASED DN 15  CENTRIFUGES <13 OPERATING AND 3 STANDBY), RATED
CAPACITY DF  1,000 LBS / HR / UNIT, PRODUCING CAKE SDLIDS
CONCENTRATION OF 80-PERCENT.
BASED DN 9 DPF PRESSES (7 OPERATING AND 2 STANDBY), RATED
CAPACITY OF 35,000 LBS  / DAY / UNIT EXCLUDING PRECDAT SOLIDS,
PRODUCING CAKE SOLIDS CONCENTRATION DF  35-PERCENT.
                       B-45

-------
difference in incinerator operating costs, also with the centrifuge dewatering
alternative being higher.

     The facilities planning documents and the Preliminary Design Evaluation
of Sludge Dewatering do not address the ultimate  disposal of  incinerator ash.
As described in Section 1 of this briefing paper, currently ash is stored in
on-site ash lagoons and periodically removed to a landfill site.  Due to the
fact that a substantial quantity of inert solids are added to the sludge under
the DFF press alternative, a larger quantity of ash is produced.  Consequently,
the costs associated with ash disposal will be higher  for the DPF press
alternative.   For purposes of this analysis,  an ash disposal cost of $15 per
cubic yard was utilized.  Based on this unit cost and the projected ash
quantities,  ash disposal under the DPF press alternative will be $160,000
(i.e.| approximately 50  percent)  more  costly than ash disposal for the
centrifuge dewatering alternative.

     The briefing paper analysis of dewatering alternatives reached a
different conclusion than the  Preliminary Design Evaluation of Sludge
Dewatering for several reasons.  These reasons are briefly discussed below.

     •  Use  of the higher capacity rating for the centrifuges in the briefing
        paper analysis,  resulted  in lower capital costs for the centrifuge
        alternative.
     •  Although the Preliminary Design Evaluation of Sludge Dewtering
        projected higher operating costs for the DPF presses than the
        centrifuges (i.e., approximately  15  percent  higher),  this difference
        was  increased to 45 percent in the briefing paper analysis.
     •  The  supplemental fuel required by the incineration process was higher
        for  both alternatives  in the briefing paper analysis.   This is due to
        the  fact that heat value of digested sludge was taken as 8000 BTU/lb
        of volatile solids.   In the Preliminary Design Evaluation the heat
        value of digested sludge was taken as 10,000 BTU/lb of volatile
        solids.   This  difference  in sludge heat value necessitated that
        supplemental fuel be added to the DPF press alternative in the
        briefing paper analysis,  whereas in  the Preliminary Design Evaluation
        the  DPF press dewatered solids required no supplemental  fuel.
        The  two analyses also  utilized different  unit costs  for supplemental
        fuel  (No.  2 fuel oil).  The Preliminary Design Evaluation used  $1.05
                                     B-46

-------
        per gallon.  The  briefing  paper  analysis used $0.85 per gallon based
        on telephone conversations with  fuel  suppliers.  Reviewing the 1985
        Operating Report  for the Division of  Sewerage and Drainage indicated
        that Southerly was  purchasing  fuel oil at  a  cost  of $0.66 per gallon.
        The net  impact  of both of these differences (i.e., heat value of
        digested sludge and cost of fuel oil) was  that the briefing paper
        analysis estimated  less of an  economic advantage  for  the DPF press
        alternative in the  incineration  process.
        Lastly,  the briefing paper analysis included  a cost for ash disposal,
        whereas  the preliminary design evaluation did not.  Since more ash is
        produced with the DPF  presses, this slightly favored the centrifuge
        alternative in this cost-effective analysis.
     From the above analyses it is evident that the selection of a dewatering
alternative is sensitive to the capacity criteria established for the devices
being evaluated and the final sludge cake solids concentrations these units
can produce.  In light of this sensitivity,  it appears reasonable to conduct
testing programs on sludges similar to that which will be processed in the
future (i.e., in  this  case  anaerobically  digested)  to  provide a representative
picture of probable equipment performance.  If such testing is not possible
for whatever reason, selection of conservative design criteria appears
justified for the initial project phase.   However,  the six existing modified
centrifuges should be evaluated with anaerobically digested sludge prior to
abandoning these units and implementing  the final project phases.

3.3  PLANNED SYSTEM REDUNDANCY
     The facilities planning documents recommended a sludge  management
alternative which provided redundancy in accordance with Table 13.  The table
is based on a Southerly one-plant scenario.

     The recommended alternative calls for 22  percent  of  the dewatered sludge
to be composted under normal conditions.  The compost facility has a capacity
to handle as much as 55 percent of the sludge under ideal conditions.  Ideal
conditions relate to total solids content of dewatered sludge, favorable
weather conditions for composting, and adequate demand for the compost
                                     B-47

-------
                TABLE 13.  SLUDGE MANAGEMENT SYSTEM REDUNDANCY
                      FOR FACILITIES PLAN RECOMMENDATION
     Process/Disposal
Average
Annual
Maximum
Capacity
                                              Values as a percentage of
                                              annual sludge production
     Compost/Sales & Distribution

     Digest/Land Apply

     Digest/Incinerate/Landfill

     Lime Stabilization/Land Apply
  22

  19a

  59a
   55

   67

   80h
a  Digestion to handle total of  sludge  incinerated and land applied, i.e.,
   approximately 80 percent of average annual  sludge  production.

   Incineration to provide complete redundancy for either composting or land
   application processes.

c  Lime stabilization is proposed by the facilities plan as a backup process,
   however, the sizing criteria and the need for these facilities are not
   clear.
                                     B-48

-------
product.  The compose facility is planned to operate in a range of 120 wet ton
per day on the low side,  up to more than 240 wet ton per day at maximum.

     Approximately 20 percent  of  the average annual sludge production would be
digested, dewatered, and land applied.   The current appplication program has
been successful, and the city anticipates that the demand for the dewatered
sludge product will remain.   The extent to which  land application can
function as a disposal option is subject to several factors including weather
conditions and cropping patterns.   Consequently,  the  amount of sludge which
will be  land  applied  is expected  to vary substantially  throughout  the year.
The program will operate from virtually no land application when factors
preclude application to a maximum of 60-70  percent of the average annual
sludge production (on a daily basis) being  land applied  during favorable
application circumstances.

     Approximately 60 percent of  the annual sludge production would be
incinerated.   The planning documents indicate the  incineration facility,
however, would be sized to handle a maximum of as  much  as 80 percent of the
sludge production.   This  additional 20-percent  would function as a valuable
backup for either the composting or the land application disposal option.   In
the event either of these options are  unable to process  and dispose of their
planned portion of the average annual  sludge production, incineration and
landfilling would be available to alleviate the problem.  The incineration/
landfill option would be expected to routinely backup the land appplication
option for reasons previously discussed.  The composting option  would be
expected to perform more consistently than  land application.  If incineration
were needed as a backup to composting,  it should be on a scheduled basis at a
time when  land application could  reasonably be expected to provide disposal
for a minimum of 20 percent  of the sludge production.

     In addition to the three processing and disposal options discussed above,
the facilities plan recommends that lime stabilization and land application be
provided as a backup to other ultimate disposal options.  Figure 5.3 of the
RFPU indicates that  the lime  facilities  would be sized only to backup the
                                      B-49

-------
compost  process, however,  the  details are not adequate to determine what is
proposed.  Furthermore, the need for this additional redundancy has not been
justified.  Recent correspondence with  the  city (i.e.,  May 29, 1987, URS
Dalton Responses to May 12, 1987 Comments) indicates the  recommendation of
lime  facilities has not been finalized completely and  is being reevaluated due
to the cost of  these  facilities.

     In this briefing paper analysis the redundancy issue was considered
relative to the existing and new incineration facilities at Southerly.  The
two new  incinerators  at Southerly will be capable of incinerating approximate-
ly 525 wet tons per day of dewatered cake at 20  percent  solids.  If a
dewatered cake solids of 25 percent can be realized, these two units would be
capable of incinerating approximately 560 wet tons per day.   The  two existing
incinerators,  which according  to the planning documents will be rehabilitated
under a one-plant option,  are capable of incinerating 320 wet tons per day at
20 percent solids.   Again,  if a 25 percent cake solids concentration can be
obtained, these units  would be capable of 350 wet ton  per day.  For purposes
of comparison, the total dewatered sludge cake  production of Southerly under a
one-plant scenario assuming all sludge  was directed  to incineration would be
approximately 510 wet  tons per day at 20 percent solids and 410 wet tons per
day at 25 percent solids.    With one new (larger) incinerator out of service,
the remaining three incinerators can handle 15 percent more sludge at 20
percent solids than the one-plant option can produce.   With  a dewatered cake
concentration of 25 percent solids,  these three incinerators could process
more than 50 percent more  sludge than the one-plant option can generate.

     Based on the above analysis, the incineration process offers sufficient
redundancy to allow processing and  disposal  of  all sludge produced even when
the composting and land application options are inoperative and one of the
larger incinerators is out of service.   In light of  the redundancy inherent in
the incineration process,  the need for greater redundancy does not appear
justified.
                                     B-50

-------
3.4  ULTIMATE DISPOSAL PLAN
     The facilities plan proposes three basic methods for ultimate
use/disposal of the wastewater sludges.  They are:

     •  Distribution and Marketing of Composted Sludge
     •  Land Application of Digested, Dewatered Sludge
     •  Landfilling of Incinerated, Dewatered Sludge

     The plan, however, does not offer many details relating to the operation,
costs, and planned reliability associated with these options.   The following
paragraphs briefly present the current understanding of the use/disposal
options.

3.4.1  Distribution and Marketing of Composted Sludge
     Dewatered, undigested sludge is transported by the city in trucks to the
composting facility.  The city operates and maintains the compost facility
which most recently has been processing approximately 120 wet  tons/day of
dewatered sludge from Southerly.  Conversations with city personnel have
indicated that the composting  facility costs approximately $1,200,000 per year
to operate.   The 1985  Operating Report  published by the  Division  of Sewerage
and Drainage shows the 1985 operating budget  for the compost facility to be
$2,000,000.   Based  on  these costs and the total  production of  the composting
facility, a unit cost  of  $26-40 per wet ton of sludge composted is estimated.

Currently compost is disposed of through mine reclamation projects, bulk and
residential package sales,  and nursery and institution use.  The  city has an
active marketing program and anticipates that future demand will be adequate
to dispose of the compost  produced.

     The composting facility has been cited as a source of odors  by the
community.  The city believes that most of  the odor problems can  be attributed
to the moisture content in the raw sludge and problems with the composting
equipment.   The city anticipates that future  operations  will increase
                                      B-51

-------
dewatered  solids  concentration and  reduce the potential for odors from the
facility.

3.4.2  Land Application of Digested, Dewatered Sludge
     The current land application program originates from the Jackson Pike
plant.  Currently land application is conducted on a contract basis and it is
expected that this practice will continue in the future.  Based on
conversations with city personnel, the current cost of land appplication is
approximately $12 per wet  ton of sludge  applied.  The contractor is
responsible for transport and spreading the sludge and for remote sludge
storage if necessary.

     Based on the earlier EIS (1979), adequate suitable acreage for sludge
application is available within a reasonable distance of the plant site.  The
current program is subject to substantial variation in peak and off peak
application rates due to weather and crop constraints.  Recent discussions
have indicated that remote sludge storage has become limited as farmers have
decided to accept the sludge only if it is spread immediately.  The ash
lagoons at Jackson Pike have been utilized to provide temporary storage and
relieve the pressure this situation  has  created.

     The future land application program should be planned and administered by
the city in such a way as to ensure the reliability of the agricultural use of
sludge.  Such planning and administration should include:

     •  Promotion of the use of sludge for agricultural purposes.
     •  Strict supervision of the contractor's performance.
     •  Maintenance of detailed program monitoring records.

     The city may have such a program  in place for the current land
appplication operations.   If so,  a description of current  and planned future
program administration would be valuable in preparation of the EIS.
                                      B-52

-------
3.4.3  Land fill i tig of Incinerated De watered Sludge
     At both Jackson Pike and Southerly, incinerator ash is temporarily stored
in on-siCe ash lagoons.   The lagoons are cleaned on an as-needed basis with
the ash being transported and deposited in a landfill by a contractor.  The
cost of ultimate disposal of ash has not been identified.  These costs vary
significantly depending on local availability of landfills, transport
distances, and composition of the ash.  Deposit charges alone can range
between $5-20 per cubic yard and may be substantially higher depending on
local conditions and ash quality.

     Conversations with the city have indicated that only the city-owned
landfill is accepting the incinerator ash.   Details relating to the projected
useful life of this landfill are not contained in the facilities plan.  For
the EIS to review the reliability of the landfill disposal option, the city
must furnish planning information documenting the steps being taken to ensure
a suitable disposal site will be available.
                                     B-53

-------
         APPENDIX C

    BRIEFING PAPER NO. 3
BIOLOGICAL PROCESS SELECTION

-------
BRIEFING PAPER NO.  3
BIOLOGICAL PROCESS SELECTION
Supplemental Environmental Impact Statement
USEPA Contract No. 68-04-5035, D.O.  No. 40
Columbus Ohio Wastewater Treatment Facilities
Prepared By:

SCIENCE APPLICATIONS INTERNATIONAL CORPORATION

TRIAD ENGINEERING INCORPORATED

-------
                         BIOLOGICAL PROCESS SELECTION
1.   TERMS AND DEFINITIONS


2.   BRIEFING PAPER ASSUMPTIONS


3.   PROCESS EVALUATION

     3.1  Process Description
          3.1.1  Design Criteria
                 3.1.1.1  Aeration Basins
                 3.1.1.2  Trickling Filters
                 3.1.1.3  Clanfiers
          3.1.2  Recommended Sizing
                 3.1.2.1  Southerly Two-Plant Semi-Aerobic
                 3.1.2.2  Southerly Two-Plant Trickling Filter/Activated Sludge
                 3.1.2.3  Jackson Pike Two-Plant Semi-Aerobic
                 3.1.2.4  Jackson Pike Two-Plant Trickling Filter/Activated Sludge
                 3.1.2.5  Southerly One-Plant Semi-Aerobic
                 3.1.2.6  Southerly One-Plant Trickling Filter/Activated Sludge

     3.2  Technical Evaluation
          3.2.1  Reliability
          3.2.2  Flexibility

     3.3  Environmental Evaluation

     3.4  Cost Evaluation


4.   COMPARISON OF BRIEFING PAPER AND FACILITY PLAN CONCLUSIONS

     4.1  Process Selection

     4.2  Clarifier Utilization

     4.3  One-Plant versus Two-Plants

-------
                                 INTRODUCTION

     Under the direction of USEPA,  a series of briefing papers are being
prepared addressing key issues in Che development of the Supplemental
Environmental Impact Statement for the Columbus,  Ohio, Wastewacer Treatment
Facilities.  The  briefing  papers  form the basis of discussions between USEPA
and their consultants to resolve these key issues.  The  following paragraphs
present the background of the facility planning process, a description of the
briefing papers,  and the purpose of this paper on biological process
selection.

FACILITY PLANNING PROCESS
     At the time this paper was prepared (March-July 1987) the city of
Columbus was proceeding to implement improvements at the Jackson Pike and
Southerly Wastewater Treatment Plants to comply with more stringent effluent
standards which must be met by July 1,  1988.    These improvements  were based
on the consolidation of wastewater treatment operations at the Southerly
plant.  This  one-plant alternative  is a  change  from  the  two-plant  operation
proposed by the city in the  1970's and evaluated  in the 1979 EIS.

     The development and documentation of wastewater treatment process and
sludge management alternatives for the Columbus metropolitan area has been an
extended and iterative process.    The design  and  construction  of various
system components have progressed, because of the 1988 deadline, while
planning issues continue to be resolved.  As  a  result, numerous  documents have
been prepared which occasionally revise a previously established course of
direction.

     The concurrent resolution of planning issues and implementation  of
various project components has made preparation of the EIS  more difficult
because final facility plan recommendations are not available in a single
document.
                                     C-l

-------
BRIEFING PAPERS
     To facilitate preparation of the EIS,  a series of briefing papers  are
being developed.   The purpose of the briefing  papers  is  to  allow USEPA  to
review the work of the EIS consultant and to identify supplemental information
necessary for the preparation of the EIS.    Six briefing papers are  being
prepared as follows:

     •  Flows and Loads
     •  Sludge Management
     •  Process Selection
     •  CSO
     *  One Plant vs. Two Plant (Alternative Analysis)
     •  O&M and Capital Costs

     The specific focus of each briefing paper will be different.  However,
the general scope  of  the  papers  will adhere  to the  following format:

     •  Existing conditions will be documented.
     »  Evaluations^  conclusions* and recommendations of the facilities
        planning process will be reviewed using available documentation.
     •  Where appropriate, an independent  evaluation  of  the future situation
        and viable alternatives will be prepared.
     •  The facility  plan and EIS briefing  paper conclusions will be compared.

     The briefing paper process is intended to:

     •  Prompt the resolution of any data  deficiencies.
     •  Clearly establish and define existing  and  future conditions.
     •  Identify the  final  recommended  plan  which  the city  desires to implement.
                                     C-2

-------
     •  Provide a data base of sufficient detail to allow preparation of the
        draft EIS.
BIOLOGICAL PROCESS SELECTION
     This Briefing Paper presents an evaluation of three different biological
processes selected by the city of Columbus, for use at the Jackson Pike and
Southerly Wastewater Treatment  Plants  (WWTP).  The scope of this report is to
review data made  available by the city's consultant,  identify issues and data
gaps, aid USEPA in the decision making process, and focus on future data needs
so that a complete and thorough  Environmental  Impact  Statement may be
prepared.

     The biological processes to be  evaluated  include the semi-aerobic process
(SA),  conventional activated  sludge  process (AS),  and trickling filters
followed by activated  sludge (TF/AS).  Data provided by the city's consultant
was evaluated against Ten State Standards, USEPA Design Criteria Documents,
and established literature values for critical design conditions for each of
the selected processes.  The  process evaluation includes a  process descrip-
tion, a review of the technical criteria from each of the process trains
including reliability,  flexibility,  performance,  expandability and turndown,
and environmental impacts.  Capital  costs are  also evaluated based on the
selection of system sizing and components necessary to  meet Ohio EPA effluent
discharge standards.   The final  section of the report deals with conclusions
and recommendations based on data available to date.
                                     C-3

-------
                          1.  TERMS AND DEFINITIONS


     An evaluation of municipal biological  treatment processes  requires  a

fundamental knowledge of  terminology used by design engineers.   The  following

key words used in this briefing paper are defined to assist the reader in

understanding the key issues raised during process evaluation.


Semi-Aerobic  The semi-aerobic process is a modified activated  sludge  system
which contains an initial anaerobic/anoxic conditioning stage consisting of a
mixture of aerobic return activated sludge and raw primary  effluent  followed
by aerobic treatment.  This process uses an anaerobic selector  zone  to control
bulking sludge followed by an aerated zone to convert soluble BOD to biomass.

Anaerobic - A biological treatment process that occurs in the absence of
oxygen.   This process contains bacteria that can survive  only in the absence
of any dissolved oxygen.   These bacteria are known as obligate  anaerobes.   The
anaerobic section of the  semi-aerobic  process is critical in providing a
selector mechanism  against those bacteria which cause bulking in a municipal
waste treatment  plant.

Anoxic - A condition of low dissolved  oxygen (less than 0.3 mg/1) or a
condition in which the only source  of oxygen is  mineral  bound oxygen such  as
nitrates.   Anoxic denitrification is a  process by which  nitric  oxygen is
converted biologically into nitrogen gas in the  absence  of dissolved oxygen.
In the semi-aerobic process, the anoxic zone may change  from anaerobic to
anoxic depending on the level  and concentration  of nitrates in  the wastewater.

Biological Phosphorus Removal - (Also  called Bio-P Removal) A process  by which
phosphorus associated with biological cells,  is  precipitated  from the
wastewater and contributes to the sludge of a biological treatment  system.
The semi-aerobic process results in biological phosphorus removal.   The city's
consultant estimates that excess phosphorus  removal results in  approximately
4.5 milligrams additional  sludge  per milligram of phosphorus  removed from  the
mixed liquor suspended solids.   The mechanism which triggers removal is  not
well understood;  however,  in plants where a phosphorus effluent  limitation is
in effect, biological phosphorus removal is an additional benefit. Where
biological phosphorus removal  cannot be triggered,  physical-chemical
phosphorus removal must be employed.  In all cases, the  removal of phosphorus
from the wastewater increases the sludge yield from the biological treatment
train.

Bulking Sludge/Rising Sludge - A bulking sludge  is one which shows poor
settleability as  measured by the sludge volume index (SVI Test).  The  cause of
a bulking sludge  is  generally  filamentous algae  or bacteria.  The microbe
responsible for bulking at  the Southerly wastewater treatment plant  has  been
identified as the cyanobacterium Schizothrax calcicola (Phormidium).  Because
                                     C-4

-------
of its poor seeding characteristics a bulking sludge will cause BOD and total
suspended solids violations due to the loss of particulates over the weirs of
the secondary clarifier.  High SVI numbers  are  indicative  of a  bulking sludge.

A rising sludge is one in which the sludge blanket of the secondary clarifiers
floats to the surface, once again causing TSS and BOO violations.   Rising
sludges are frequently caused by biological activity in the clarifier
resulting in the release of micro gas bubbles which attach to the sludge
particles.   One of the most frequent causes of a rising sludge  is  denitnfica-
tion in the secondary clarifiers.   The denitrification process  releases
nitrogen gas and carbon dioxide which causes the sludge to float.   No degree
of increased clarifier sizing or decreasing the clarifier surface  overflow
rate will compensate  for a  rising sludge.  The cause of the denitrif ication in
the secondary clarifiers must be eliminated for the  wastewater  treatment  plant
to meet standards.

Carbonaceous BOD Removal - This is the biological conversion of carbonaceous
organic matter in wastewater  to cell  tissue and various gases and by products.
In the conversion it is assumed that nitrogen present in the various compounds
is converted to ammonia.  High carbonaceous BOD values will result in effluent
violations.

Denitrification - The biological process by which nitrate is converted into
nitrogen and other gaseous end products.   When denitrification  occurs in  the
secondary clarifiers the result is a  rising sludge and effluent violations.

F/M Ratio - The food to mass  ratio.  This is a ratio of food substrate (BOD)
to biological mass (MLSS) which is used as a control parameter  for determining
the organic loading rate to  a  biological  treatment system.   A high F/M ratio
means that oxygen uptake rates will be high, biological  metabolic  rates will
be high,  and in the absence of excess  oxygen,  obligate aerobic bacteria will
be removed.  A low F/M  ratio  generally results in high dissolved oxygen
concentrations and may result in the selection of bulking bacteria in a
municipal wastewater treatment system.   In the semi-aerobic process  high  F/M
ratios are  intentionally maintained in the first bay of the aeration tank in
order to keep the system anaerobic and drive the biological processes
necessary for nitrification and denitrification.

Mixed Liquor Suspended Solids - (MLSS) The mixed liquor suspended solids  or
mixed liquor volatile suspended solids are a measure of the amount of biomass
present in the aeration system. For most conventional activated sludge
systems,  this concentration is approximately 1,200 to  3,000 milligrams  per
liter (mg/1).  For  the semi-aerobic system at  the Southerly WWTP,  this
concentration is 3,500  milligrams  per liter.  The reason for the very high
concentration of biomass held in the aeration basin  is the  low nitrification
rates experienced at Southerly.  At  the  Jackson  Pike  plant  where nitrification
rates are  considerably higher the  mixed liquor suspended solids  will be held
at 2,500 mg/1.
                                     C-5

-------
Nitrification - The two-stage biological process by which ammonia or total
kjeldahl (TKN) nitrogen is first converted to nitrite then  to nitrate.
Nitrification is the necessary first step in the nitrification/denitrification
cycle.  The goal is  to  convert  ammonia into nitrates and ultimately into
gaseous end products.   When the nitrification bacteria are inhibited due to
toxicity and nitrogen overloads,  the result  is  a violation of the  ammonia
standards for the Southerly or Jackson Pike Wastewater Treatment  Plants.

Over-pumping - This is the process by which the sludge inventory in the
secondary clarifiers is held to a minimim in order to place  the bulk of the
biomass back in the aeration system.  Over-pumping of the clarifier sludge is
necessary when  there is the potential for denitrification to occur in the
secondary clarifiers or where mixed liquor suspended solids in the aeration
basins must be held at a high concentration.  A well-designed clarifier will
permit over-pumping on a routine basis by eliminating rat-holing,  the
phenomenon by which water channels  through  the  sludge blanket leaving behind
the solids.   Channeling is  minimized by providing slow agitation and hydraulic
scouring devices in the sludge pumping system.  These devices are used in
circular clarifiers.   Rectangular clarifiers generally use a chain and flight
mechanism which drags  the  sludge down to a sludge sump located at the
discharge end of the rectangular clarifier.   The chain and flight  sludge
mechanism is generally  inefficient  where over-pumping is  required.

Surface Overflow Rate - (SOR)  The surface overflow rate is one of the critical
design parameters for sizing a clarifier.  The  dimensions for the surface
overflow rate parameter are gallons per day square  foot (gpd/d.  ft ) of
clarifier surface.   High surface  overflow rates generally result in loss of
solids from the secondary clarifiers.   Ten States Standards cites a surface
overflow rate of 1,200 gallons per day per square foot of clarifier surface
area as a good design  maximum for conventional  activated  sludge processes.
However, due to the fact that sludges produced from nitrification processes
are generally poor  settling,  Ten States recommends a surface overflow rate of
800 gallons per day per square foot of surface  area  for nitrifying sludges.
For this briefing paper the general range of 700 to 1000 gallons per day per
square foot was selected as a conservative design criteria.

Sludge Volume Index - (SVI) The sludge volume index is expressed as  the  volume
in mils per gram of waste  activated sludge after the mixed liquor has been
allowed to settle for  30 minutes  under quiescent conditions.   A  low SVI is
indicative of a well-flocculated, poor-settling sludge.   A high  SVI is
indicative of a bulking,  dispersed poor-settling sludge.   Sludges  with SVIs in
the range of 50 to 100 exibit excellent settling characteristics.   Sludges
with SVIs in the range  of  100  to  150 are  generally transitional  sludges  with
fair to good settling  characteristics.   Sludges  with SVIs in the range of 150
to 200 are characterized as bulking sludges as  indicated by the  poor settling
characteristics in the secondary clarifier and  poor dewatering characteristics
in the sludge handling process.
                                      C-6

-------
                        2.  BRIEFING PAPER ASSUMPTIONS

     The analysis contained in this briefing paper is based on two key
factors.  These include wastewater flows and loads and NPDES permit limits for
the Southerly and Jackson Pike Wastewater Treatment Plants.  Alternative
process trains were conservatively selected to meet applicable 1988 7-day and
30-day discharge  limits.

     A separate briefing paper, prepared for the EIS,  documents the
development of wastewater  flows  and  loads.  Table 2-1 presents the EIS  flows
and loads.

     The average design flow  for Jackson Pike will be held at 80 MGD,  and the
peak design flow will held at 100 MGD.   This results  in an additional 8 MGD at
average flow and 32 MGD at peak  flow being  diverted to Southerly.  Section
3.1.2.3 discusses the reasons  for limiting  the  flows  at Jackson Pike.
Table 2-2 presents the actual flows and loadings which would be processed by
each plant.  These flows  and  loadings are used  to determine facility sizes in
Section 3.1.2.

     Tables 2-3 and 2-4 provide a summary of the permit limitations for the
Jackson Pike and Southerly WWTPs.  These were taken from Ohio EPA Permit No,
4PFOOOOO*GD (Jackson Pike) and 4PF00001*HD (Southerly).  As  noted on the
attached tables, the effluent characteristics are segregated by time of year
as well as by 30-day and 7-day limits.  In addition to the concentration
limits, a mass loading limit based on an effluent loading  of  60 MGD from
Jackson Pike and 120 MGD from Southerly are included.  Table 2-5 is an
estimate of the one-plant permit limitations.   These  are based on the
assumption that the water quality impacts to the Scioto River will be  the
limiting factor in the event  the  Southerly wastewater treatment plant  is
expanded.   Therefore,  the concentration  limitations were derived  from  those
assigned to the Southerly  treatment plant.  Mass  loading limits were derived
by adding the flows of the Jackson Pike and Southerly plant together and
converting them to a mass basis.
                                     07

-------
     TABLE 2-1.  2008 PROJECTED FLOWS LOADS
Tributary to Jackson Pike

        BOD (Ib/day)                    141,600
        TSS (Ib/day)                    161,600
        TKN (Ib/day)                     18,532
        TP  (Ib/day)                      6,057
        Average Flow (MGD)                   88
        Peak Flow (MGD)                     132
Tributary to Southerly

        BOD (Ib/day)                    126,600
        TSS (Ib/day)                    121,300
        TKN (Ib/day)                     16,570
        TP  (Ib/day)                      5,248
        Average Flow (MGD)                   66
        Peak Flow (MGD)                      99
Total From Planning Area

        BOD (Ib/day)                    268,200
        TSS  (Ib/day)                    282,900
        TKN (Ib/day)                     35,102
        TP  (Ib/day)                     11,305
        Average Flow (MGD)                  154
        Peak Flow (MGD)                     231
                       C-8

-------
      TABLE 2-2.  ACTUAL FLOWS AND LOADS TO BE TREATED AT EACH FACILITY
                       Jackson Pike         Southerly          Southerly
                       (Two-Plant)         (Two-Plant)        (One-Plant)

Flow (MGD)
     Average                  80                  74                154
     Peak                    100                 131                231

BOD Load (Ib/day)
     Average             128,700             139,500            268,200
     Peak                107,300             160,900            268,200

TSS Load (Ib/day)
     Average             146,900             136,000            282,900
     Peak                122,400             160,500            282,900
                                     C-9

-------
               TABLE 2-3.  PERMIT LIMITATIONS - JACKSON PIKE
Effluent Characteristics

     C-BODr
          (June-Oct)
          (Nov-Apr)
          (May)

     Suspended Solids
          (June-Oct)
          (Nov-Apr)
          (May)

     Ammonia (N)
          (June-Oct)
          (Nov-Apr)
          (May)
 Concentration
     (mg/l)
 30-day  7-day
 8.0
20.0
13.0
16.0
30.0
26.0
  .0
   0
 2.5
12.0
30.0
19.5
24.0
45.0
39.0
 1.5
 7.5
 3.75
               Mass Loading
                  (Ibs/d)
              30-day    7-d*
 3,995
 9,988
 6,492
 7,990
14,980
12,984
  499
2,497
1,247
         5,993
        14,980
         9,737
        11,986
        22,471
        19,474
            748
          3,744
          1,872
  Mass limits based on 60 MGD effluent loading
                                      C-10

-------
                TABLE 2-4.  PERMIT LIMITATIONS - SOUTHERLY
                                Concentration         Mass Loading
                                    (mg/1)                (Ibs/d)
Effluent Characteristics        30-day  7-day

     C-BOD5
          (June-Oct)             8.0    12.0           7,990   11,985
          (Nov-Apr)             25.0    40.0          24,968   39,950
          (May)                 13.0    19.5          12,984   19,474

     Suspended Solids
          (June-Oct)            16.0    24.0           15,979  23,969
          (Nov-Apr)             30.0    45.0           29,962  44,942
          (May)                 26.0    39.0           25,967  38,951

     Ammonia (N)
          (June-Oct)             1.0     1.5             999    1,498
          (Nov-Apr)              5.0     7.5           4,994    7,491
          (May)                  2.0     3.0           1,998    2,996
  Mass limits based on 120 MGD effluent loading
                                      C-ll

-------
            TABLE 2-5.  ESTIMATED ONE PLANT PERMIT LIMITATIONS


                                Concentration           Mass Loading
                                    (mg/1)                 (Ibs/d)
Effluent Characteristics        30-day  7-day          30-day    7-day

     C-BOD5
          Uune-Oct)             8.0    12.0           12,010   18,014
          (Nov-Apr)             25.0    40.0           37,530   60,048
          (May)                 13.0    19.5           19,516   29,273

     Suspended Solids
          (Juoe-Oct)            16.0    24.0           24,019   36,028
          (Nov-Apr)             30.0    45.0           45,036   67,554
          (May)                 26.0    39.0           39,031   58,547

     Ammonia (N)
          (June-Oct)             1.0     1.5           1,501    2,252
          (Nov-Apr)              5.0     7.5           7,506   11,259
          (May)                  2.0     3.0           3,002    4,507


* Mass limits based on 180 MGD effluent loading

1.   No one-plant permit presently exists.  Mass loadings were derived from
     180 MGD flow and Southerly concentration limits.
                                      C-12

-------
     For the purposes of this briefing paper,  it  will be  assumed that  a
treatment train would be deficient if it  would be unable  to meet either  the
30-day or 7-day concentration limit or the 30-day or 7-day mass loading  limit.
It is understood that mass  limits  can be  modified if  the  new  loading does not
negatively impact receiving water quality.  Temperature considerations as they
impact such variables as nitrification rates were evaluated based on the most
stringent occurrence of those temperatures.  For example,  the lower nitrifica-
tion rates at Southerly (12°C) were evaluated against  the  November to  April
ammonia standards.
                                     C-13

-------
                            3.  PROCESS EVALUATION
     This section describes and evaluates the biological process alternatives
proposed in the facility plan.  The alternatives are evaluated based on
technical criteria, environmental criteria,  and system  costs.

3.1  PROCESS DESCRIPTION
     The semi-aerobic  (SA) and the trickling filter/activated  sludge (TF/AS)
biological processes were evaluated for these alternatives:

     •  Southerly Two-Plant
     •  Jackson Pike Two-Plant
     *  Southerly One-Plant

     The semi-aerobic process is a modified  form of the activated sludge
process.  The  process consists of a non-aerated reaction zone ahead an  aerated
activated sludge zone.   The non-aerated zone may be anoxic (nitrates are
present),  anaerobic (no nitrates  or oxygen present),  or  a combination of both.
The purpose of the anaerobic zone is  to function as a selector  mechanism
providing an environment which discourages proliferation of filamentous
organisms and thereby controls bulking sludge.  The anaerobic zone  may  change
to anoxic depending on the level and  concentration of nitrates in the
wastewater.  Denitrification occurs in the anoxic zone.   Denitrification is a
process by which nitrates are converted into nitrogen gas.

     The only  physical  differences between the semi-aerobic process and the
conventional activated  sludge  process  is  the  addition of an internal mixed
liquor recycle loop and two baffles in the first bay of the aeration tanks.
The internal recycle loop is used to  bring nitrates back to the anoxic  zone
and thus cause denitrification to take place.  The baffles are incorporated
into the design  to  prevent backmixing  from the aerated zone to the  anaerobic
zone.
                                     C-U

-------
     In reviewing full-scale operational data from the Southerly plant as well
as an evaluation of nitrification rates at both Southerly and Jackson Pike,  it
is evident that the semi-aerobic process proposed by the city is in effect
similar to the conventional activated sludge  process  with the exception of the
internal mixed liquor recycle loop and the addition of two baffles in the
first bay of the aeration tanks.   Given these exceptions,  a conventional
activated sludge system can be operated as a  semi-aerobic process simply by
reducing the amount of aeration provided in the first bay of the system.  If
one takes this reasoning one step further and adds an internal recycle pumping
system (estimated cost $10,000 per aeration tank),  the  result xs  a semi-
aerobic process minus two  23x15 foot concrete baffles.   For this reason, it
was assumed that the semi-aerobic process and the  activated sludge process
were in effect identical and would be  evaluated on that basis.

     The trickling filter/activated  sludge  process  is comprised of roughing
trickling filters followed by aeration tanks.  The trickling filters are
designed to remove 40 percent  of  the  BODr.  They function  in  the  same  manner
as the anaerobic/anoxic zone of the semi-aerobic process in that they select
for non-filamentous bacteria.   The aeration tanks  that  follow the filter
remove the remaining BODc  and provide  the  required nitrification.  An internal
recycle loop can be provided back to the trickling filters to initiate
denitrification there.

     Slightly reduced aeration tank capacity  and aeration energy is required
since the trickling filter  has  the ability  to dampen  peak biological loads and
thus minimize the amount of aeration time needed to achieve complete
biological oxidation.

     The following sections present design criteria and  recommended process
sizing for each alternative.
                                     C-15

-------
3.1.1  Design Criteria
     The biological process design criteria are listed in Table 3-1.   These
criteria were derived from pilot  data  provided by  the city's consultant,  the
Ten States Standards (Recommended Standards for Sewage Works, 1978 Edition,
Health Education Service Incorporated,  Albany, New York 12224),  and USEPA
criteria (innovative and Alternative Technology Manual,  EPA-430/9-78-009,
1978).   The range of acceptable operating conditions  given in Table 3-1
defines the critical regions for the aeration, trickling filter,  and final
clarification processes.  In the absence of more extensive full-scale piloting
data, it is assumed that violation of  these criteria would result in
inadequate treatment of the wastewater received at Jackson Pike or Southerly
which would result  in effluent  violations.

3.1.1.1  Aeration Basins
     The aeration process listing in Table 3-1 includes  evaluation criteria
for the hydraulic retention time in the aeration basin,  F/M ratios in the
first bay as well as the overall F/M ratio of the aeration basin,  design  mixed
liquor suspended solids  concentrations,  nitrification rates  for both  summer
and winter months,  and  a recommended ratio of oxygen uptake rates to dissolved
oxygen (OUR/DO).

     A minimum  hydraulic retention  time in the  aeration basin of  4.5 hours is
limited to the final 7 bays of  the  plug flow  reactor  for the semi-aerobic
process.   This datum was taken  from the Southerly SBR Nitrification Study
conducted by the city's  consultant (January 1987).  The  hydraulic  residence
time in the Project 20 full-scale semi-aerobic pilot study conducted at the
Southerly waste treatment plant typically ranged from 5 to 8 hours.  The  use
of a shorter residence  time in  the aeration basin for the trickling filter
process is based on the  fact that  a roughing  filter has  the  ability to  dampen
or attenuate peak biological loads,  thus minimizing the  amount of aeration
time required to achieve complete biological oxidation.
                                     C-16

-------
               TABLE 3-1.  BIOLOGICAL PROCESS DESIGN CRITERIA
Process
Aeration
Roughing Trickling
Filter
Clariflers
Parameter

Hydraulic Retention Time
(HRT, hrs) Minimum

F/M First Bay
Overall

MLSS Southerly
     Jackson Pike

Nitrification Rates
(mg NH^/gm VSS.hr)
Southerly summer
Southerly winter
JP summer
JP winter

OUR/D.O.
Hydraulic Loading Rate
(gpd/ft2)
Organic Loading Rate
(Ib BOD/d.1000 ft3)
Surface Overflow Rates
(gpd/ft2)
Solids Loading Rates
(Ib/d. ft2)
Ranee
4.75-SA, AS
3-TF
                                                0.13-0.17

                                                3500
                                                2500
                                                1.5-1.6
                                                0.9
                                                4.8
                                                3.0

                                                250-500
1400-4600

100-500


400-1000

20-50
Source
SBR Report1
               SBR Report
Control of Bulking
Sludge2

USEPA3*4

USEPA3
USEPAJ
                                                               USEPA-
^Southerly SBR Nitrification Study, Orris Albertson,  URS Dalton,  January 1987
2"The Control of Bulking Sludges", JWPCF, April 1987
^"Innovative and Alternative Technology Manual",  EPA  430/9-78-009,  1978
*"Wastewater Treatment Plant Design", WPCF,  1977
 No MLSS are provided for the combined plant option because the nitrification
 studies have not been run for that wastewater blend.
                                      C-17

-------
     The selection of an F/M ratio of 5 in Che first bay of the semi-aerobic
system is based on correspondence with Mr. Orris E. Albertson,  Process
Consultant to the city's consultant.   Mr.  Albertson also stated in an article
published in the April 1987 Journal  of the Water Pollution Control Federation
that the maintenance of a high F/M ratio  in the initial contact basin of a
semi-aerobic system was required to maintain the anaerobic and anoxic
conditions necessary to select against bulking bacteria.   This  high F/M ratio
would be realized in both the semi-aerobic and activated sludge options.  It
is assumed that the trickling filter option would greatly reduce this F/M
ratio due to the attenuating effect the upstream  roughing  filter would have on
carbonaceous BOD loadings.  An overall aeration basin F/M value of 0.13 to
0.17  would be consistent for a  well  operated nitrifying activated sludge
system.

     The mixed  liquor suspended solid concentrations of 3,500 (mg/1) for
the Southerly plant and 2,500  (mg/1) for the Jackson Pike plant  were
derived from SBR studies conducted by the city's  consultant.  It is assumed
that mixed liquor concentrations of the same magnitude  would be required for a
conventional activated sludge  system.   The primary reason for the higher mixed
liquor suspended solids  in the  Southerly aeration basin is  the  low nitrifica-
tion rates observed at that plant.  The Jackson Pike WWTP  experiences
nitrification rates well within the  range  of most sewage treatment facilities
(3-5 mg  NH4-N/g vss.hr).

     The cause of lower nitrification rates at the  Southerly plant is most
likely due to toxicity of  some  non-conventional  pollutants  present in the
Southerly raw wastewater.   The Southerly winter nitrification rate cited in
Table 3-1 was derived from  the full-scale project 20 pilot study.  The SBR
study indicated winter nitrification rates of 1.2 mg NH^/g vss.hr.  The  lower
nitrification rate was used in  this evaluation to provide a  more conservative
estimate of nitrification during winter conditions. Nitrification rates cited
for the Jackson  Pike wastewater treatment  system are well  within the range of
nitrification rates realised in North  American municipal treatment facilities.
                                      C-18

-------
     The significance of the oxygen uptake rate to dissolved oxygen ratio
(OUR/DO) has  been cited by  Mr.  Orris Albertson as  necessary for the control of
bulking sludge organisms in municipal  treatment facilities.  In his paper, Mr.
Albertson indicates that "The best control of bulking sludges is  provided by
both reactor compartmentalization and  by  DO  control  in each of the
compartments.  Often in practice, either will provide the necessary SVI
control; but the maximum control  will  be available when both a high F/M
gradient is present and DO  control as a function of time  for  each  compartment
is provided."  Mr.  Albertson further states that "Regardless  of whether the
initial contact zone is aerated or unaerated a sufficiently high  OUR/DO ratio
will ensure  both SVI control and  enhance phosphorus  removal.  The suggested
minimum OUR/DO ratio is greater than 250 to 1 and  preferably as high as 500 to
1."  Under  conditions of high  F/M ratios,  Mr. Albertson contends  that  the
biological cell will uptake organic material and release soluble  phosphates
given that the DO gradiant across the slime layer of the cell is less than
0.5  rag per liter.   Under endogenous conditions,  such  as  occur in  the final
zones of the aeration basin, soluble phosphate uptake occurs  as well as the
release of endogenous decay products  resulting in  a well-flocculated mixed
liquor  leaving the aeration basin.  It should be noted that these conditions
can be achieved in a conventional activated sludge aeration basin by the use
of compartmentalization and reducing the blower capacity in the initial stages
of the aeration tanks.   This condition is  further  enhanced  by increasing the
mixed liquor suspended solids and providing for an internal mixed liquor
recycle loop.

3.1.1.2  Trickling Filters
     The design criteria for roughing trickling filters  which are followed by
activated sludge systems is considerably higher than  those  for  trickling
filters followed by clarification. Hydraulic loading  rates  ranging from 1,400
to 4,600 gallons per day per square foot of surface area  are  considered good
design criteria.  Organic loading rates in the range  of  100 to  500 pounds of
BOD per day per 1,000 cubic  feet volume would also provide  adequate capacity
for a roughing trickling filter.   The  trickling filters,  when operated in this
                                      C-19

-------
condition, act as the initial zone or anaerobic/anoxia zone of the aeration
basin under the semi-aerobic or  activated  sludge options.  The roughing
trickling filters would reduce the volume  of aeration basin required and
effectively assist in control of sludge  bulking.

3.1.1.3  Clarifiers
     Given the fact that the three previously selected biological treatment
processes (semi-aerobic, conventional activated sludge, and trickling filter
followed by activated sludge) all can act  as effective selectors against
bulking organisms, it was assumed that SVIs would generally be in the range of
70 to 150.   Given this  SVI  range, there  are two critical  design factors which
must be considered when selecting and sizing  final clarifiers.  These are
surface overflow  rates (gallons  per day  per square foot surface area) and
solids or floor loading rates (pounds of suspended  solids per day per square
foot).   The city's consultant has selected very conservative surface overflow
rates for their final clarifiers.  These are generally in the range of 470 for
average flows and 800 for sustained peak flows.  Mr. Richard Brenner, USEPA
Cincinnati,  indicated that  conservative  design criteria for average flow rates
would be in the range of 500 to 550 with peak sustained surface overflow
loading rates set at 900 to 950.   For the purposes  of this evaluation,  a range
of 400 for average flow and 1,000 for sustained peak flow will be used.

     The city's consultant has also  selected  relatively conservative solids or
floor loading rates  for their clarifiers.  Generally, these have been in the
range of 18 to 23 pounds  per day  per square foot for  average flows and 29 to
36 pounds per day per square foot for peak flows.  A solids loading criteria of
20 to 50 pounds per day per square foot  as cited in the USEPA Innovative and
Alternative Technology Manual will be used in this briefing paper.
Rectangular clarifiers  should generally  be sized on the lower end of this
solids loading rate.   Circular clarifiers with hydraulically assisted sludge
removal devices can easily  accommodate the higher solids  loading  rates  without
causing sludge channeling or solids entrainment.
                                      C-20

-------
3.1.2  Recommended Sizing
     Based on the previously stated process design criteria and the 2008
projected flows and loads given in Table 2-1 of this briefing paper,  two
biological treatment trains  (i.e.  semi-aerobic and trickling filter/activated
sludge} were evaluated for the following alternatives-

     •  Southerly Two-plant
     •  Jackson Pike Two-plant
     •  Southerly One-plant

     A critical assumption in this evaluation is that the projected flows and
loads given in Table 2-1 in concert with a peaking factor of 1.5 will  permit
the plants to treat all anticipated dry weather flows plus some additional
inflow and infiltration during wet weather events to a peak design  flow of 100
MGD for Jackson Pike, 131 MGD for Southerly two-plant, and 231 MGD for a
Southerly one-plant alternative.

     BOD and total suspended solids loadings developed for this briefing paper
were similar  to  those presented in the  facility plan.  Total kjeldahl  nitrogen
and total phosphorus loadings presented in the facility plan were used in this
process evaluation (Table 1.1).  It was  further assumed  that  the  increase in
flow due to the application of a 1.5  peaking factor  would have little  or no
effect on the mass daily loading of BOD, total suspended solids,  or nitrogen.

     Tables 3-2 through 3-7 document the results of this briefing paper
analysis relative to the sizing  and  performance of the various biological
treatment processes for Southerly and Jackson Pike.   All previously stated
design and loading criteria were used to derive the  data presented  in  these
tables.
                                      C-21

-------
3.1.2.1  Southerly Two-Plant Semi-Aerobic
     Table 3-2 is a summary of the Southerly two-plant  semi-aerobic or
activated sludge options.   The existing six aeration basins  in  the  west  train
would be utilized with the addition of an internal  recirculation  pump and
baffles for the semi-aerobic option.  Four of the existing center train
aeration basins would be used with the addition  of  two  new 26 foot by 900  foot
by 15 foot sidewall depth aeration basins.  Given these conditions,  average
and peak aeration times fall well within the design parameters  cited in  Table
3-1.   In terms of final clarification, the existing clarifiers  would be
replaced with six new 190-foot diameter circular clarifiers  fitted  with
hydraulic sludge removal devices, flocculation chambers, and associated  piping
and an internal mixed liquor recycle system.  The addition of these six  190-
foot diameter units place the clarifiers well within the critically designed
surface overflow rates of 400 to 800 gallons per day per square foot of
surface area established by  the  city's consultant.   The solids  loading rates
based on a mixed liquor suspended solids  of  3500  tag per  liter fall well  within
process evaluation criteria.  Under peak hydraulic  loading conditions the
solids loading rates would exceed design criteria established in  the facility
plan.   Given the fact that circular clarifiers will be  used  in  this applica-
tion,  it is unlikely that a peak loading of 38 pounds per day per square foot
would overload  the  proposed  clarifiers.

3.1.2.2  Southerly Two-Plant Trickling Filter
     The critical design data for the Southerly  two-plant trickling filter
option is presented in Table 3-3.  Any evaluation of trickling  filters at  the
Southerly plant requires an understanding of the existing plant layout and
related logistical problems.  There is inadequate space  between the existing
primary clarifiers and aeration basins to install the proposed  110-foot
diameter trickling filters.   Due  to  this  limitation it was assumed that  the
trickling filters would be located in an area remote to those processes  and
that primary effluent would be pumped to the trickling  filter and discharged
from the trickling filter to the influent end of the aeration basin by gravity
conduits.   These logistical  problems  while not insurmountable were taken into
                                      C-22

-------
  TABLE 3-2.  SOUTHERLY PROCESS DESCRIPTION - TWO PLANT SEMI-AEROBIC, AS
Flow (Design)

Average (MGD)
Peak (MGD)

Aeration
  Tankage
    New
    Existing

  HRT (hrs)
    Average
    Peak
                     West Train
        37
        65.5
6
-------
         TABLE 3-3.  SOUTHERLY PROCESS DESCRIPTION - TWO PLANT TF/AS
Flow (Design)
     Average (MGD)
     Peak (MGD)
West Train

    40
    71
Center Train

    34
    60
Total

  74
 131
Trickling Filters

  Filters           2
-------
consideration when evaluating  the overall effect  of  the  trickling filter
process as discussed in Section 4 of  this briefing  paper.

     As indicated in Table 3-3, four 110-foot diameter by 22-foot high high-
rate roughing trickling filters were  sized  for  the Southerly two-plant option.
Two trickling filters would  service each of the existing treatment trains.
Hydraulic loading rates of 3,740 and 3,160 gallons per day per  square foot of
trickling filter surface area are well within the design criteria limit of
4,600 gallons per day per square foot.  The  organic loading rates of  121  and
148 pounds BOO per day per 1,000 cubic feet  of trickling filter volume are
well within  the  100  to 500 range.  Following the  trickling  filters, five  of
the six existing aeration basins in the west train and four existing basins in
the center train would be used  for  aeration capacity.  Although the hydraulic
retention times are considerably less than  thoses cited for the semi-aerobic
or activated sludge systems,  it is  considered adequate for aeration following
roughing trickling filters.

     Final clarification consists of six 190-foot diameter clarifiers with
resulting surface overflow rates in the range of 430 gallons per day  per
square foot under average conditions and 770 gallons per day per square foot
under peak conditions.   Solids  loading rates range from 22 pounds per day per
square foot at average flow to 38 pounds per day pen square foot at peak  flow.

3.1.2.3  Jackson Pike Two-Plant Semi-Aerobic
     Table 3-4 summarizes the design  criteria for the Jackson Pike semi-
aerobic and activated sludge  process  trains.  For  the semi-aerobic process the
A treatment train could handle an average of 48 MGD with a peak loading up to
60 HGD.  The  B treatment  train  was  restricted  to 32 MGD average and 40 MGD
under peak conditions.

     The assumption used throughout this briefing paper is that the Jackson
Pike plant  is hydraulically limited  to 100 MGD.  This  assumption is based on
information from the city and their consultant.  The  average flow to  Jackson
                                      C-25

-------
      TABLE 3-4.  JACKSON PIKE PROCESS DESCRIPTION - SEMI -AEROBIC, AS
Flow (Design)
     Average (MGD)
     Peak (MGD)
Aeration

  Tankage
     New
     Existing

  HRT (hrs)
     Average
     Peak

Clarification

  Tankage
     New
     Existing
                     A-Train
                       48
                       60
                        7.88
                        6.30
                                            B-Train
                                              32
                                              40
                                                                   Total
                                                                     80
                                                                    100
                                         4(326' x900'xl5'SWD
                                                 7.88
                                                 6.30
                                                                     10
              8@153'x60'xl2.5'SWD
Surface Overflow Rate
   (gpd/ft2)
   Average            650
   Peak               820
Solids Loading Rate
   (Ibs/d. ft2)
   Average
   Peak
                       23
                       29
                                      2
-------
Pike was  limited  to 80 MGD based  on Che capacity of the existing preaeration
and primary settling tanks.  Average flows in excess of  80 MGD and  peak flows
in excess of 100 MGD will be diverted to the Southerly WWTP.

     The semi-aerobic system would utilize 6 existing  aeration basins in the A
train.  In the B  train the 4 existing aeration basins  would be utilized.
Under both conditions,  hydraulic retention times are well within  the  limits
established in the evaluation criteria.  These criteria  were established
during the SBR and piloting studies utilizing Jackson  Pike  primary effluent.
As previously stated,  the nitrification rates in the Jackson Pike studies have
been approximately 300 percent higher than those reported for Southerly.
Given these conditions, the hydraulic retention time cited  in Table 2-4 is
considered adequate to  meet 1938 discharge limits  in terms  of ammonia.

     In evaluating final clarification for Jackson Pike, the selected option
includes rehabilitating the existing 12  clarifier  units  and  adding  2  new
rectangular clarifiers (153-foot by 60-foot by 12.5-foot sidewall depth) to
the B-train.  The  addition  of 2  new rectangular clarifiers would  provide
Jackson Pike with a combined  surface overflow area of 128,000 square feet.
The facility plan  recommended demolishing the existing clarifiers and
installing four new 200-foot diameter circular clarifiers.   This  would provide
the facility with 126,000 square feet of final clarifier surface area.
Surface overflow rates and solids  loading rates would  be essentially identical
for the rectangular clarifiers versus the  new circular clarifiers.   A
discussion of final clarifier utilization  for both Southerly and  Jackson Pike
is presented in Section 4.2 of this briefing  paper.

3.1.2.4  Jackson Pike  Two-Plant  Trickling  Filter/Activated Sludge
     The trickling filter/activated sludge option  design criteria for the
Jackson Pike WWTP is summarized in Table  3-5.  The design criteria for
aeration and final clarification are essentially the same as those  described
under the Jackson Pike  semi-aerobic and activated  sludge options.   Two  new
110-foot diameter by 22-foot high  and two  new 90-foot diameter by 22-foot high
                                     C-27

-------
             TABLE 3-5.  JACKSON PIKE PROCESS DESCRIPTION - TF/AS
Flow (Design)

     Average (MGD)
     Peak (MGD)

Trickling Filters
                        A-Train
48
60
  Filters            2@110l0x22'ht.
  Hydraulic Loading
  Rate (gpd/ft2)
     Average           2530
     Peak              3160

  Organic Loading Rate
  (Ib. BOD/d.1000 ft3)
     Average            129
     Peak               108

Aeration

  Tankage
     New
     Existing             6

  HRT (hrs)
     Average              7.88
     Peak                 6.30

Clarification

  Tankage
     New
     Existing   8@153'x60'xl2.5'SWD

  Surface Overflow Rate
     (gpd/ft2)
     Average            650
     Peak               820
                      B-Train
32
40
                  2(§90'0x22lht,
                      2520
                      3140
                       129
                       107
                         7.88
                         6.30
  Solids Loading Rate
     (Ib/d. ft2)
     Average
     Peak
23
29
              2
-------
trickling filters would be added to the process treatment  trains.  Critical
design conditions in terms of hydraulic loading and organic loading are  well
within criteria cited in Table 2-1.  One limitation which impacts the
selection of trickling filters for Jackson Pike is space. While the evaluation
of critical design criteria indicate that four units would be adequate,
limited available area would make  siting  difficult.

3.1.2.5  Southerly One-Plant Semi-Aerobic
     The critical design criteria for a one-plant  semi-aerobic option are
presented in Table 3-6.   Under the one-plant option,  the existing center and
west train would handle an average flow of 88 MGD with a peak flow of 132  MGD.
With the increased hydraulic loading, it will be necessary to construct  a new
east train capable of handling  an average  of 66  MGD with peak sustained loads
of 99 MGD,  This would include use of ten existing aeration basins at the
center and west trains with the construction of  two new 26-foot by 900-foot by
15-foot sidewall depth basins on the center train.  The new east train would
contain nine 26-foot by 900-foot by 15-foot sidewall depth aeration basins.

     Final clarification would include six new 200-foot diameter circular
clarifiers for the center  and west  train and four  new 205-foot diameter
circular clarifiers for the east train for a combined facility clarifier
surface area of 320,360 square  feet.   Given the  amount of clarifier capacity,
both the surface overflow rates and solids  loading rates are within design
criteria.

3.1.2.6  Southerly One-Plant Trickling Filter/Activated Sludge
     The trickling filter/activated sludge option for a Southerly one-plant
operation is presented in Table 3-7.   The  trickling  filters  would consist  of
four 115-foot diameter units for the  center  and  west  trains and two 115-foot
diameter units  for the east  train.  Under sustained peak hydraulic loading,
the hydraulic loading criteria is within the 4,600 gallons per day per square
foot of surface area for all trains.   Organic  loadings  are  within the range of
100 Co 500 pounds of BOD per day per thousand cubic feet of reactor volume.
                                      C-29

-------
 TABLE 3-6.  SOUTHERLY PROCESS DESCRIPTION - ONE-PLANT SEMI-AEROBIC AND AS
                  Center and West Train    East Train (New)
Flow (Design!

     Average(MGD)
     Peak(MGD)
          88
         132
           66
           99
                                                   Total
154
231
Aeration

  Tankage
     New
     Existing

  HRT (hr)
     Average
     Peak

Clarification

  Tankage
     New
     Existing
  2@26'x90o'xi5'swD
 10(§26'x900'xl5'SWD
           8.59
           5.73
   9@26'x900'xl5'SWD
            8.58
            5.72
6@200'0xl5'SWD
4@205'0x15'SWD
  Surface Overflow Rate
  (gpd/ft2)
     Average             470
     Peak                700
  Solids Loading Rate
  (pounds/d.ft2)
     Average
     Peak
          23
          35
                               500
                               750
           25
           37
 11
 10
 10
                                     C-30

-------
         TABLE 3-7.  SOUTHERLY PROCESS DESCRIPTION - ONE-PLANT TF/AS
Flow (Design)

     Average (MGD)
     Peak (MGD)

Trickling Filter
                        West Train
    50
    75
  Filters (New)       2@115'0x22'ht.
  Hydraulic Loading
  Rate (gpd/ft2)
     Average             2410
     Peak                3610
  Organic
  (Ib.BOD/d.lOOOft3)
     Average
     Peak
   112
   112
                    Center Train
 42
 63
                        2020
                        3030
134
134
              East Train
 62
 93
                   2@115'0x22'ht.    2@ll5'0x22'ht.
                2990
                4480
166
166
                 Total
154
231
Aeration

  Tankage
     New
     Existing

  HRT (hrs)
     Average
     Peak
5
-------
All other aeration and clarification criteria fall within the critical design
criteria for the one-plant  option.

     Final clarification would include six new 200-foot diameter clarifiers
for the west and center trains and four new 200-foot  diameter units for the
east train.

3.2  TECHNICAL EVALUATION
     The previously described treatment options were evaluated in terms of
their reliability and flexibility.  Reliability  is  measured  in terms of
potential loss of treatment system components as well as the impact of
toxicity on the biological treatment process.  System flexibility is discussed
in terms of response to mass  loadings  as well as upsets within the system.

3.2.1  Reliability
     A summary of system  reliability for the biological process options is
presented in Table 3-8.  The semi-aerobic and activated sludge processes are
evaluated with respect to aeration basin hydraulic retention time.  Trickling
filters are evaluated with respect to organic and hydraulic loading rates.
Final clarification is evaluated with respect to surface overflow rates and
solids loading criteria.

     The analysis of system reliability considered that one of the system
components was out of service. The  components remaining in-service would be
required to process the influent flow.   Table 3-8  presents  the impact  on the
process design  criteria  of processing average and peak  flow  through the  system
with one unit out of service.   Under conditions where system components  were
separated into  two parallel  treatment  trains,  or in the case of Southerly one-
plant where there are three parallel treatment trains,  the worst case  scenario
was represented by the loss  of one essential  component  in each of the  parallel
trains.   The  reliability evaluation  may also  be  interpreted  as a surge in
hydraulic or mass loadings,  where all  units are operative,  due to brief
intervals of raw wastewater flows or loads above  those projected  in Table 2-1.
                                     C-32

-------
                       TABLE 3-8.   SYSTEM  RELIABILITY
                          Jackson  Pike
                            (2-Plant)
PARAMETER

Aeration

Hydraulic Retention
  Time (hrs)
    Average
    Peak

Trickling Filter

Hydraulic Loading
  Rate (gpd/ft2)
    Average
    Peak

Organic Loading
  Rate (Ib BOD/d/1000ft3)
    Average
    Peak

Clarification
SA
TF/AS
 Southerly
 (2-Plant)
SA     TF/AS
5.91
4.75
5.91
4.75
8.50
4.80
5.56
3.15
       3600
       4500
        184
        154
                 2600
                 4590
                  156
                  180
                                   Southerly
                                   (1-Plant)
          SA
7.15
4.76
       TF/AS
4.50
3.00
                        2970
                        4450
                         235
                         235
Surface Overflow
  Rate (gpd/ft2)
    Average
    Peak

Solids Loading
  Rate (lb/d/ft2)
    Average
    Peak
 750
 930
  26
  33
 750
 930
  26
  33
 520
 920
  26
  46
 520
 920
  26
  46
 670
1000
  33
  50
 660
 990
  33
  49
NOTE:  This table assumes one component (aeration basin, trickling filter,
       or clarifier) is removed from service for repair or maintenance.  The
       resulting impact on the process design criteria is identified.
                                      C-33

-------
     The system  reliability data  for  the Jackson Pike semi-aerobic and
 trickling filter/activated sludge alternatives is contained in the first  two
 columns of Table 3-8.  For the aeration basin capacity,  it  was assumed that
 one of the four aeration basins in the B  train was  removed  from service for an
 extended period  of time  leaving three  functional basins in the B train; and
 one of the six basins in the  A train was removed leaving five basins available
 in the A train.  The efficiency of either train should not  be affected since
 the hydraulic retention times are still within design criteria listed in Table
 3-1.

     The impact  of removing one of the 110-foot diameter trickling filters  from
 service would cause  the  hydraulic  loading rate to increase to 4,500 gallons
 per day per square foot  of surface area.   This does not exceed the design
 criteria of 1,400 to 4,600.  The organic  loading  rate  would increase to 1S4
 pounds of BOD per day per 1000 cubic feet of filter.   This  is still within  the
 design range of  100  to  500.

     The removal of  one  of the clarifiers in each train would not have a
 significant impact on the solids overflow or  solids loading design criteria.

     Columns three and four of Table 3-8 show the impact of a loss of process
 components at Southerly under a two-plant option.   Removal  of one of the  six
 aeration basins  in either the west train or the center train would not cause
 the hydraulic retention time to be exceeded.  Removal  of one of the four
 trickling filters would not violate either  the established maximum hydraulic
 or organic loading rates.

     Removal of  one of the six circular clarifiers would not result in a
violation of the established design criteria.  The  solids loading rates would
                   «
be high (46  Ib/d/ft ); however,  this  should  not be  a problem for circular
clarifiers.
                                      C-34

-------
     Columns 5 and 6 in Table 3-8 presents the system reliability evaluation
for the Southerly one-plant option.   One of the aeration basins  in each  of  the
three trains would be removed from service due to maintenance or mechanical
failure.   For the semi-aerobic and TF/AS options,  this  would result in
hydraulic retention times in the aeration basins within specified design
criteria.  Removal of one of the six trickling filters  would not result  in
violations of the established maximum hydraulic  or organic  loading rates.

     In terms of clarifier capacity it was assumed that one  of the circular
clarifiers would be removed from the west and center section and one  from the
east section.  Under  these conditions, the  surface overflow  rate  as well as
the solids loading rate under peak hydraulic loadings  would  approach  the
critical limits of the design criteria,  however, they  would  not violate  them.
Once again, this should not be a problem for circular  clarifiers.

     In summary, all of the components under each alternative  would be capable
of operating within the specified design criteria in the event that a unit  was
removed  from operation.

     The second measure of system reliability is its ability to respond  to
system upsets or toxicity problems.   The semi-aerobic  process  provides
excellent capabilities to adjust to  high ammonia loadings.  Ammonia
concentrations will be monitored in the  number 6 bay in each of  the aeration
basins.   Once ammonia concentrations above 2 mg/1 are  found, an  internal
recycle pump will begin recirculating mixed liquor suspended solids back to
bay 1-A of the system to improve nitrification capacity.  The  internal recycle
system also allows the waste treatment plant operators  the ability to
compensate for periodic increases in primary effluent  ammonia overloads.

     The roughing trickling filter acts  as an anaerobic/anoxic aeration  bay in
the semi-aerobic process.  The filter reduces BOD loadings to the aeration
basins and effectively aids in the control of sludge bulking.  Effluent
recycling from the aeration basins back to the trickling filters acts in much
the same way as the internal recycle of  the semi-aerobic process.  Aeration
                                     C-35

-------
basin effluent recycling would also cause denitrification to occur within the
trickling filters.  Denitrification is vital during the summer months to
prevent a rising sludge in the final clarifiers.   One significant  limitation
of the trickling filter in cold climates is the tendency to ice.   Under these
conditions, loss of bio-mass as well as reduced process efficiency reduce the
effectiveness of the  trickling filters.

     Toxic effects will have a similar impact on the semi-aerobic and
trickling filter processes due  to  the common bacterial organisms  used in
nitrification and denitrification.  One source of toxicity to a nitrification
system can be slug loads of ammonia or  TKN.  Table 3-9 is a  summary of Project
20 operating data for the month of February 1987.   Project 20 is  not being run
in a manner exactly similar to that proposed for the semi-aerobic process.
Nevertheless,  its performance is indicative of the ability of the  semi-aerobic
process to nitrify under winter conditions.   The data in Table 3-9 includes
primary effluent ammonia concentrations for the west and center treatment
trains, final  effluent ammonia concentrations for aeration basins  1 and 2
which represent the semi-aerobic  process,  and  ammonia concentration from the
remaining aeration basins which were operated in a conventional activated
sludge mode with reduced aeration  in the initial bays of each basin.

     The data  indicate that both  the  semi-aerobic  and activated sludge process
can meet 7-day and 30-day ammonia  limits under cold weather conditions.
However, it should be noted that periodic peak loadings of ammonia such as
occurred on February 4,  February  22,  and February  24,  resulted in  bleedthrough
of high ammonia concentrations to  the final effluent.  Generally,  it appears
that ammonia concentrations in the primary effluent in excess of 25  rag/1  would
result in violations of the 7-day and 30-day permit if they were sustained.
It is apparent from the Project 20 data that slug  loads of ammonia will cause
effluent violations for both the  semi-aerobic and activated sludge processes.
The trickling  filter/activated  sludge option would respond in a similar
fashion allowing bleedthrough of high influent ammonia loads.   The source of
the high nitrogen load is most  likely one  or more  industries within the
service area.  As a  result  it is recommended that  the sources of the high
                                     C-36

-------
               TABLE 3-9.  AMMONIA BREAK-THROUGH - SOUTHERLY
                            (Ammonia as N, mgl)
     Date
     February

         1
         2
         3
         4
         5
         8
         9
         10
         11
         12
         15
         16
         17
         19
         22
         23
         24
         25
Primary Effluent
                  Final Effluent
 West
Center
   1 & 2
(Semi-Aerobic)
17
17
18
24
20
17
18
15
15
—
17
16
21
20
30
19
24
15


15
14
16
24
19
15
17
15
14
—
—
14
21
20
30
18
25
15


1.1
0.7
0.9
5.3
1.3
0.1
0.1
0.1
0.2
0.1
0.1
0.6
1.2
4.6
7.3
8.7
1.8
0.4
30-day 1.9
7-day 3.5
all others
   (AS)

    2.5
    2.5
    3.7
    7.4
    3.4
    3.1
    2.8
     1.4
     0.7
     O.I

     1.6
     1.5
     5.6
     8.7
    10.5
     7.1
     2.6
     3.6
     5.4
SOURCE:  Contract 20 Operational Data
                                     C-37

-------
ammonia loads  be  identified  and  be  limited  in the amount of TKN they are
allowed to discharge.  Without such control,  it  would be impossible to
consistently meet the  1988 effluent limits for ammonia.

     The data in Table 3-LO  summarizes reported pollutant concentrations in
the Jackson Pike and Southerly influent and presents inhibition levels of
these pollutants for various biological processes.   Influent concentrations of
copper and zinc at the Columbus  plants may be found at levels which can
inhibit the nitrification process.  Copper and  zinc could act as inhibitory
pollutants if the influent concentrations shown in Table 3-10 are carried
through the primary effluent and  enter the biological treatment process.  The
city of Columbus must  consider controlling  the level of inhibitory industrial
pollutants to prevent system upsets.   An  aggresive  and  well-monitored
industrial pretreatment program  would be necessary to ensure the nitrification
process is protected from inhibitory and/or toxic effects of industrial
discharges.

3.2.2  Flexibility
     System flexibility is defined as the ability of the system to expand or to
turn-down (respond to reduced flows or loads) its biological processes.   It
will be necessary for  the city of Columbus to control slug loads of ammonia
and TKN no matter which biological option or treatment plant option is
selected.  Impacts can also  be manifested in terms of loss of load.   At the
present time, it is  estimated that 35 to  45 percent of the BOO loading to
the Southerly plant  originates with the Anheuser-Busch Brewery.  The  impacts
of losing this  BOD loading are most directly felt in the first bay of the
semi-aerobic system.  Mr. Albertson has indicated that in order for the
nitrification and denitrification process to proceed in this first bay,  an
OUR/DO ratio of at least 250-1 must be maintained.   Under current  design
conditions, the OUR/DO ratio is approximately 500-1.   Given the loss  of all
brewery waste  for a sustained period, it can be assumed that a critical OUR/DO
                                     C-38

-------
                 TABUS 3-10 SUMMARY OF PCLUTttRT INHIBITION UEVELS FOR BIOUDGICAL PROCESSES
                                       Jackson Pike
                                           Southerly
Activated Sludge,  Nitrification,  Anaerobic,
Priority Pollutant
1 Acenapthene
23 Chloroform
30 1,2-Trans Dichloroethylene
38 Ethylbenzene
44 Hethylene Chloride
55 Napthalene
65 Phenols

66 BIS(2-Ethylhexyl)Phthalate
67 Butyl Benzyl Phthalate
85 TeCrachloroethylene
86 Toluene
87 Trtchloroethylene
118 Cadmunu


119 Chramun


120 Copper


121 Cyanide


122 Lead
123 Mercury

124 Nickel


128 Zinc

Influent, ug/1 Effluent, ug/1
^•^ ^^v
12* —
— —
4*-ll* —
45* —
— —
50* 13*

17* —
50* —
44* —
2Q*-24* —
150* —
4.6-15.0 1.0-1.6


34.0-280.0 17.0-28.0


64.0-210.0 9.9-14.0


90* 23*


35.0-165.0 5.4-7.3
7* —

34.0-215.0 41.049.0


205.0-670.0 99.0-190.9

Influent ug/1
^^^
3.3*-10*
19*
5.3*-13*
44*
—
50*

20*
—
—
12*
190*
1.2-7.0


1.7-210.0


31.0-100.0


30*


14.0-69.0
0.56

14.0-60.0


25.0434.0

Effluent ug/1
3.7*-10.0*
—
—
—
4.3*-11.0*
47*-53*
3*-10*

—
—
—
—
—
0.3-1.4


9.4-12.0


9.8-10.0


43*


2.2-7.2
0.30

19.0-26.0


36.042.0

ug/1
_
—
—
—
—
—
I 200,000
U 300,000
—
—
1400
—
__
I 10,000-50,000
U 60,000
T 1,000
B 5.0-50
T 1,000
I 7,000
B5-50
I 1,000
U 3,600
T 100
I 200
U 200,000
I 200
T 100-1,000
U 200,000
T 1,000-2,500
I 2,000-25,000
U 25,000
T800
I 1,000
ug/1
_
I 10,000
—
—
—
—
14,000

—
—
—
—
_
I 7,000


I 250
U 1,000

T50
U 260

I 240
U 21,000

I 700
I 2,000

T 250-500
I 500-3,000

T 80-500

ug/1
^^^
—
—
—
—
—
—

—
_
—
—
—
I 20


I 1,000-10,000


I 1,000-10,000


14,000


_
I 1,365,000

—


I 5,000-20,000

*Frora Priority Pollutant Scan
 B - Beneficial
 T - Threshold for inhibiting
 I - Inhibiting
 U -Upsets
effects
                Source:  Table 8.3, Colunbus Industrial  Pretreatment  Program, Vol.  2, January 1987
                *Anaerobic from EPA 430/9-76-Ol7a

-------
ratio can be maintained.  If the brewery wastes are the primary source of the
historical bulking problems at Southerly,  the plant could operate  in a semi-
aerobic or conventional activated sludge mode with little or no problems.

     The second advantage of the  semi-aerobic process  in terms of  responding
to periodic upsets is what Mr. Albertson has described as sludge memory.   Most
activated sludge systems which have biological phosphorus removal  capabilities
are able to respond in a linear fashion to organic loading upsets  based on
sludge age.   Assume the sludge age is maintained at 9 days for a 2-day period
and the primary source of organic loading is removed from the system.  The
impact on the effluent would be comparable to the ratio of 2-9 or
approximately 22 percent loss of system efficiency.  Under these conditions,
the system would recover rapidly once the source of organic loading is placed
back into the system.  The disadvantage of this type of activated  sludge
(i.e., one which demonstrates biological phosphorus  removal),  is  that the
sludge yield in terms of pounds of sludge produced per pound of BOD destroyed
is quite high.   This is due  to  the fact  that the  elemental phosphorus
percipitated from the system contributes to  the total sludge volume.  In all
instances,  it is apparent that the nitrification process and the biological
phosphorus  process are closely related.   Attempts by the city's consultant to
separate nitrification from phosphorus removal have not been successful.

3.3  ECTVIRONMENTAL CRITERIA
     One purpose for evaluating treatment alternatives and options is
ultimately to ensure that the  treatment  plants meet their environmental
limits.   Meeting these limits is predicated on a combination of conservative
design criteria,  projection of hydraulic and pollutant loading rates, and
pilot testing to demonstrate system strengths and  weaknesses under real-world
conditions.   To  date,  pilot  testing  in  Columbus  has  utilized a sequencing
batch reactor (SBR),  and most testing has been at the  Southerly plant.  In
reviewing the work done to date,  additional  information needs to be gathered
on the impacts of blending Jackson Pike and Southerly primary effluent to
determine if nitrification rates can be sustained.
                                     C-AO

-------
     Ic will also be necessary to limit the mass loading of TKN to the
Southerly waste treatment plant in order for the nitrification process  to  be
effective.   Periodic high loadings of TKN have resulted in the bleedthrough of
ammonia from the primary effluent during the Project 20 pilot demonstration.
Unless these loads of TKN are controlled,  all  three  biological  processes would
be subject  to ammonia bleedthrough resulting in violation  of  the permit
ammonia concentration and mass-loading limits.

     Meeting total suspended solids  and BOD  limits is primarily a  function of
clarifier efficiency.  Soluble BOD is rapidly removed in the aeration basin.
That portion of the  BOD associated with the  particulates in the wastewater as
well as the suspended solids which escape from the clarifier,  would cause  BOD
or suspended solids violations.   Controlling suspended  solids  violations is
based on controlling the  SVI of both Jackson Pike and Southerly biological
treatment systems.

     All three  processes  have the ability to select  against filamentous
organisms which cause bulking.   The  semi-aerobic and activated sludge systems,
as demonstrated by Project 20 data,  could reduce SVIs and keep ammonia
concentrations  well within permit limits given the absence of slug  primary
effluent ammonia loadings.  Operating data for the Southerly waste  treatment
plant from 1983 through 1986, indicate SVIs  in the range of 75 to  181 are
possible.   In all  instances,  the  peak  SVI  loadings occurred during  the summer
months and did not reach the critical SVI limit of 200.

     Denitrification is  equally important during the summer months.
Denitrification will prevent the formation of a rising  sludge  in the  final
clarxfiers.  No amount of clarifier  upsizing or clarifier  configuration
modification can prevent a violation during episodes of rising sludges.  It
is, therefore,  necessary  that the denitrifiers complete the chemical reaction,
converting the  nitrates  into nitrogen and carbon dioxide,  in  the aeration
                                   •x
basin.  This is accomplished by overpumping the secondary  clarifiers,
maintaining a  minimum sludge blanket  in those clarifiers,  and holding the
                                     C-41

-------
mixed  liquor suspended solids in the aeration basin to 3500 mg/1 (Southerly
plant).  Denitnfication  also has  the  side benefit  of  eliminating nitrites  and
nitrates from  the  plant  effluent.

     At the present time there is no nitrate or nitrite standard in the Ohio
EPA permit limitations written for  the Jackson Pike and Southerly plants.
However, removing  these pollutants from the effluent wastewater would result
in the removal of pollutants from the  receiving  waters and subsequently any
groundwaters which are recharged from the  surface waters.  Denitrification is
considered a benefit,  not only in terms of  removing  unwanted  pollutants from
the surface waters and the groundwaters of the state,  but also in terms of
limiting the occurrence of rising sludges  in the secondary clarifiers.

     Another secondary benefit from the semi-aerobic process would be that it
is a biological phosphorus  removal system.  Research has indicated that
denitrification, nitrification,  and  phosphorus removal are closely related
biological reactions.  Although phosphorus  removal  increases  the  volume of
sludge to be treated by both Southerly and Jackson  Pike,  it also  results in
the removal of a nutrient pollutant  from the surface water and groundwater.

     A negative environmental impact of odor and pests in the form of flies is
associated with the trickling filter/activated sludge option.  Trickling
filters have been cited  in  odor  complaints particularly under conditions of
high organic loadings  such as  will be employed in the  roughing filters
proposed for Jackson Pike and Southerly.   In  addition,  fly larvae and flies
have been known to breed  on  these  filter media resulting in nuisance
complaints.  Attempts to  control  odors  and flies  by covering  the  trickling
filters results in the installation of a drafting system  to allow adequate  air
to pass through the filter  media.  This  would add cost to the system  and may
result in reduced  efficiency during  the summer months.
                                     C-42

-------
3.4  COSTS
     The biological treatment train cost components (shown  in Table 3-11)
include trickling filters, aeration basins,  aeration system  blowers,  blower
housing, diffusers, (and internal recycle loops in the case  of serai-aerobic
systems), and clarification processes.  Table 3-11 provides  a comparison
between the costs from  the Revised Facility  Plan  Update and the briefing paper
costs.

     In general, costs developed for  this briefing paper  are lower than those
presented in the facility plan due to lower  projected average and peak flows.
In general, the higher facility  plan  costs at Southerly for  the  two-plant
alternative are due to the fact  that  a new east train  was required.   The  lower
projected flows used  in the briefing paper analysis did not require a new east
train for the two-plant option.

     Under the combined plant option, the lower costs  associated with the
briefing paper estimates are  due to the  requirement for fewer treatment
facilities based on lower flows.

     In most cases, the semi-aerobic option  was less costly than the  trickling
filter/activated sludge option.   This is due to the fact  that a  significant
portion of the required aeration capacity already exists.

     The briefing paper analysis also reviewed the clarifier evaluation
prepared during the facility planning process.  In this clarifier evaluation,
it was assumed that the Southerly One-Plant  Alternative would be implemented.
Three clarifier configurations were developed.  These  included:

     •  Alternative 1:  Construction  of  12  new 200-foot diameter clarifiers,
     •  Alternative 2:  Constructing  6 new 200-foot diameter clarifiers for the
        east train,  using all existing clarifiers  for  the center train,  and
        constructing three 200-foot diameter clarifiers for the west train.
                                     C-43

-------
                                      TABLE 3-11  COMPARISON OF CAPITAL COSTS
                                         SEMI-AEROBIC VS.  TRICKLING FILTER

                                          (Costs in millions of dollars)
                                             SOUTHERLY
                                JACKSON PIKE
COMBINED
    Cost Component
    Trickling Filters
i    Aeration
    Clarification
    TOTAL
Facility Briefing Facility
Plan Paper Plan
SA
—
34.7
33.8
TF/AS SA TF/AS SA TF/AS
23.7 — 11.0 — 11.0
21.9 12.3 7.2 23.8 23.8
26.3 20.5 20.5 9.8 9.8
Briefing Facility Briefing
Paper Plan Paper
SA TF/AS SA TF/AS SA TF/AS
9.9 — 29.9 — 21.5
22.5 22.5 63.6 47.8 46.5 30.5
8.7 8.7 41.8 41.8 35.5 35.5
68.5  71.9  32.8   38.7   33.6  44.6    31.2  41.1  105.4  119.5  82.0  87.5
    Note:   Briefing Paper costs are consistently lower than Facility Plan costs due to lower projected flows.

-------
     •  Alternative 3:   Constructing 6 new 200-foot diameter clarifiers for
        the east train;  using existing rectangular clarifiers  and  adding 2  new
        175-foot diameter clarifiers for the center train; and using the
        existing rectangular clarifiers and adding 2 new 175-foot  diameter
        clarifiers to the west train.
     Alternative 3 was discarded as being unworkable in terms of hydraulic
limitations.  Alternatives 1 and 2 were evaluated with a cost of $43,194,000
for Alternative 1, and $40,126,000 for Alternative 2.   The RFPU study
concluded that the two alternatives exhibit similar present worth costs.
Consequently,  due to the  advantages of circular clarifiers, it was recommended
that the existing clarifiers be  demolished and  new 200-foot clarifiers  be
installed.   These advantages include:

     •  Easier flow splitting and control of flow to each clarifier.
     •  Reduction in the number of telescoping  sludge valves to be controlled.
     •  Ability to provide flocculation within the clarifier.
     •  Less potential risk for shortcircuiting.
     •  Automatic scum removal for the entire surface.
     *  Less complicated  construction phasing.

     In addition to these advantages the capability to  rapidly  return sludge
to the aeration basin is  a distinct advantage of circular clarifiers.   Due to
the low nitrification rates at Southerly, the briefing  paper  evaluation
concurs with the advantages of circular clarifiers and recommends their
installation at Southerly.
                                     C-45

-------
       4.   COMPARISON OF BRIEFING PAPER AND FACILITY PLAN CONCLUSIONS
4.1  PROCESS SELECTION
     The briefing paper analysis concurs with Che facility plan in its
selection of Che semi-aerobic process as the preferred biological process.
The process is superior to the trickling filter/activated sludge process  due
to its ability to provide nutrient removal and the flexibility of process
control it affords operators. As previously stated,  the  semi-aerobic system
is essentially the same as the conventional  activated sludge  system and could
easily be operated in the conventional activated sludge mode if necessary.
Although the trickling filter/activated sludge option is  considered reliable,
it does exhibit the disadvantages of producing nuisance odors and pests,  and
requires additional space to implement.

     Process selection is also predicated on the assumption that  Columbus will
implement and enforce a rigid industrial preteatment  program  which will limit
the concentration of toxic pollutants and slug loads  of ammonia.  Pilot data
have indicated that slug loads of ammonia  or TKN will pass  through the  primary
clarifiers and may result in ammonia  bleedthrough from the aeration basins.
These influent conditions must be controlled to ensure that any biological
process will perform effectively and meet  permit limitations.

4.2  CLARIFIER UTILIZATION
     The briefing paper evaluation agreed  with the facility plan
recommendation to demolish the existing rectangular clarifiers  at Southerly
and replace them with new circular clarifiers.  Due to the  lower flows  and
loads utilized in the briefing paper analysis,  less facilities are recommended
in the briefing paper for both the Southerly one-plant and  Southerly two-plant
alternatives.

     Contrary to the RFPU, the briefing paper recommends  retaining the
existing retangular clarifiers at Jackson  Pike.   The  arguments  for the
selection of circular clarifiers at Southerly,  primarily  high mixed liquor
                                     C-46

-------
suspended solids, the  need for overpumping,  and  low nitrification rates do not
apply to the Jackson Pike waste treatment facility.  The 12 existing
rectangular ciarifiers at Jackson Pike should be rehabilitated,  and 2 addi-
tional rectangular ciarifiers should be constructed to provide adequate final
effluent clarification capacity.

4.3  ONE-PLANT VS. TWO-PLANT
     The decision to utilize a combined one-plant option versus a two-plant
option must be based on process reliability as well as cost factors.  The  data
presented in this briefing paper shows the biological treatment process for
the two-plant option is less costly.  The  unknown factor at this point is  the
effect of nitrification rates on blending  Jackson Pike and Southerly primary
effluent.  In the absence  of this  data,  it is  speculative  to recommend a one-
plant versus two-plant option based on process considerations alone.
                                      C-47

-------

-------
      APPENDIX D

 BRIEFING PAPER NO. 4
O&M AND CAPITAL COSTS

-------
BRIEFING PAPER NO.  4
0 & M AND CAPITAL COSTS
Supplemental Environmental Impact Statement
USEPA Contract No. 68-04-5035, D.O.  No. 40
Columbus Ohio Waste water Treatment Facilities
Prepared By:

SCIENCE APPLICATIONS INTERNATIONAL CORPORATION

TRIAD ENGINEERING INCORPORATED

-------
                            CAPITAL AND O&M COSTS
1.   DEVELOPMENT OF BRIEFING PAPER COSTS

     l.l  CAPITAL COSTS
     1.2  O&M COSTS
2.   FACILITY PLAN COSTS


3.   COMPARISON OF BRIEFING PAPER AND FACILITY PLAN COSTS

-------
                                 INTRODUCTION

     Under the direction of USEPA,  a series of briefing papers are being
prepared addressing key issues in the development of the Supplemental
Environmental Impact Statement for the Columbus,  Ohio,  Wastewater Treatment
Facilities.  The briefing  papers  form the basis of discussions between Triad
Engineering  and USEPA to resolve important issues.  The following paragraphs
present the background of the facility planning process, a description of the
briefing papers, and the purpose of this paper on costs.

FACILITY PLANNING PROCESS
     At the time this paper was  prepared (March-July 1987) the city of
Columbus was proceeding to implement improvements at the Jackson Pike and
Southerly Wastewater Treatment Plants to comply with more stringent effluent
standards which must be met by July 1, 1988.    These improvements were based
on the consolidation of wastewater treatment operations at the Southerly
plant.  This  one-plant  alternative  is a  change  from  the two-plant operation
proposed by  the city in the  1970's and evaluated in the 1979 EIS.

     The development and documentation of wastewater treatment process and
sludge management alternatives for the Columbus metropolitan area has been  an
extended and iterative process.   The design  and  construction  of various
system components have progressed,  because of the 1988  deadline,  while
planning issues continue  to be resolved.  As  a  result,  numerous  documents have
been prepared which occasionally revise a previously established course of
direction.

     The concurrent resolution of planning  issues  and implementation of
various project components has made preparation of the  EIS more  difficult
because final facility plan recommendations are not available in a single
document.
                                       D-l

-------
BRIEFING PAPERS
     To facilitate preparation of the EIS,  a series  of briefing papers  are
being developed.   The purpose  of the  briefing  papers  is  to allow USEPA  to
review the work of the EIS consultant and to identify supplemental  information
necessary for the preparation  of the  EIS.   Six briefing papers  are  being
prepared as follows:

     •  Flows and Loads
     •  Sludge Management
     •  CSO
     •  Process Selection
     •  One Plant vs. Two Plant (Alternative Analysis)
     •  O&H and Capital Costs

     The specific focus of each briefing  paper will  be different.   However,
the general scope of  the  papers  will  adhere  to the following  format:

     »  Existing conditions will be documented.
     •  Evaluatxonsi  conclusions, and recommendations of the  facilities
        planning process will  be reviewed using available documentation.
     *  Where appropriate, an  independent  evaluation of the future  situation
        and viable  alternatives will  be prepared.
     *  The facility  plan and  EIS briefing  paper conclusions  will be  compared.

     The briefing paper process is  intended to:

     •  Prompt the  resolution  of any  data deficiencies.
     •  Clearly establish and  define  existing  and future conditions.
     •  Identify the  final  recommended  plan which the city desires  to implement.
     •  Provide a data base of sufficient detail to  allow preparation of the
        draft EIS.
                                      D-2

-------
O&M AND CAPITAL COSTS
     This briefing paper presents capital and operation and maintenance costs
associated with the Southerly One-Plant and Jackson Pike and Southerly Two-
Plant alternatives.  Topics addressed include:

     •  Development of briefing paper capital and O&M costs
     •  Facility plan capital and O&M costs
     •  Comparison of briefing paper and facility plan costs

     The briefing paper cost analysis is based on the 2008 design flows and
loads which were presented in the Wastewater Flows and Loads Briefing Paper.
The facility plan costs are taken from  the  1985 Revised Facility Plan Update.
These costs were developed for a 30-year planning period ending in 2015.
                                      D-3

-------
                    1.  DEVELOPMENT OF BRIEFING PAPER COSTS
     This section presents briefing paper capital and O&M costs for the
Southerly One-Plant, Southerly Two-Plant, and Jackson Pike Two-Plant
alternatives.  Due to the differences in design flows between the facility
plan and the briefing papers, an independent cost analysis was prepared based
on the 2008 flows and loads developed in the  Wastewater Flows and Loads
Briefing Paper.  Table 1-1 presents the flows and loads which were used as a
basis for developing these costs.  The Process Selection Briefing Paper
recommended  the  semi-aerobic process.  Therefore, O&M and capital costs were
developed assuming semi-aerobic as the biological process being employed.
Solids handling costs are consistent with facilities recommended in the Solids
Handling Briefing Paper.

                TABLE 1-1.  BRIEFING PAPER FLOWS AND LOADS
                             Jackson Pike      Southerly      Total
Average Flow (MGD)                  80               74           154
Peak Process Flow (MGD)            100              131           231
BOD Load (Ib/day)              128,700          139,500       268,200
TSS Load (Ib/day)              146,900          136,000       282,900
NOTE:  Average flows in excess of 80 MGD and peak process flows in excess of
       100 MGD at Jackson Pike will be diverted to Southerly under  the  two-
       plant alternative.
1.1  CAPITAL COSTS
     Detailed cost estimates prepared during the facilities planning process
by the Turner Construction Company  were utilized in preparing the construction
costs for this briefing paper.   These cost  estimates were reviewed in detail
and adjusted as appropriate to account for  differences in the briefing paper
design flows and unit process sizing.  Table 1-2 presents the construction
costs for the Southerly One-Plant,  Southerly Two-Plant,  and  Jackson Pike  Two-
Plant alternatives.
                                     D-4

-------
                   TABLE 1-2.  BRIEFING PAPER CAPITAL COSTS


                               Southerly         Southerly        Jackson Pike
Cost Component                (One-Plant)       (Two-Plant)       (Two-Plan^)

Site Work                    $ 22,932,000      $ 11,448,000      $  7,251,000
Miscellaneous Buildings         5,232,000         4,857,000         1,857,000
Plumbing/HVAC                   5,875,000         5,875,000         4,337,000
Hoa/tunr-ita                      lA.inn.nnn            —             « -)7i nnn
Headworks
Preaeration
Primary Settling
Chlorination                    4,000,000         2,500,000
Effluent Pumping
Outfall Line
Gravity Thickening
Digestion
           Thickening
                                 J,0/_>,UUU         3,O/3,UUU         4,JJ/,UUU
                                14,300,000            —             8,271,000
                                 5,905,000         1,533,000         3,750,000
primary settling                13,590,000         4,717,000         7,372,000
Aeration                        46,533,000        12,284,000        22,502,000
Final Settling                  35,462,000        20,521,000         8,691,000
'•M—* — -'-•*                     4,000,000         2,500,000         2,000,000
                                 6,270,000            --             4,340,000
                                 3,000,000            —               700,000
                                 5,070,000         2,520,000         6,070,000
                                11,460,000         4,280,000         9,170,000
oenLmuge inicitening            5,600,000         2,000,000         4,500,000
Centrifuge Dewatering           21,040,000         5,120,000           490,000
Dewatered Sludge Storage         1,300,000         1,300,000
Incineration                     1,300,000             —            3,600,000
Sludge Conveyor System              —                —            5,000,000
Instrumentation & Control       10,070,000         4,799,000         6,995,000
Electrical Distribution          1,896,000         1,896,000           607,000
Jackson Pike Rehabilitation     13,564,000
Interconnector South            4,982,000
Interconnector North            5,048,000      	—             5,048,000

TOTAL CONSTRUCTION COSTS     $244,429,000      $ 85,650,000      $112,551,000

Contingency (15%)               36,664,000        12,848,000        16,883,000
Land                              200,000           200,000
Salvage Value (PW)           -12.582,000      -  4,644.000      -  5.628.000

CAPITAL PRESENT WORTH        $268,711,000      $ 94,054,000      $123,806,000
                                     D-5

-------
 1.2   O&M COSTS
      Operation and maintenance  costs  were developed  for each plant alter-
 native.   The costs are presented in Table 1-3.  The basis of these costs are
 described in  the  following paragraphs.

               TABLE 1-3.  BRIEFING PAPER ANNUAL O&M COSTS ($)
Southerly
U-Plant)
4,050,000
4,446,000
1,197,000
4,800,000
712,000
1,314,000
330,000
Southerly
(2-Plant)
2,850,000
2,250,000
580,000
2,425,000
342,000
1,314,000
60,000
Jackson Pike
(2-Plant)
2,880,000
2,412,000
658,000
2,425,000
712,000
—
170,000
Labor
Material & Supply
Chemicals
Energy
Land Application
Composting
Ash Disposal
TOTAL                  16,849,000       9,821,000        9,257,000
NOTE:  These costs are based on 2008 design flows and loads.

     Labor costs for operation and maintenance were determined by evaluating
information on the number of employees currently employed at the treatment
facilities and their respective salaries.  An average annual salary (including
benefits) of $30,000  per  employee  was established for future cost projections.
The projected number of workers for each alternative is 135 for the Southerly
One-Plant, 95 for the Southerly Two-Plant,  and 96 for the  Jackson Pike Two-
Plant.

     Typically, annual material and supply costs are estimated as a percentage
of total construction costs.   However,  in this situation,  with a portion of
the facilities already in place, doing so may underestimate the actual cost.
Therefore, cost curves  were used to determine the construction costs for each
plant alternative as a new facility.  One percent of this  cost was estimated
as the annual material and supply  cost.
                                      D-6

-------
     Chemical  costs  were determined for three  processes:  chlorination,
centrifuge thickening, and centrifuge dewatering.  A current chlorine cost of
$200 per ton and a polymer cost of  $1 per pound  were used for  these estimates.

     Costs for electrical energy were estimated based on costs  documented in
the 1985 Operating Report prepared by the City of Columbus Division of
Sewerage and Drainage.  These costs were adjusted to account for the
following:

     •  An increase  in power costs from $0.04 to $0.05 per kilowatt-hour
     •  An increase  in average flow from 145 MGD to 154 MGD
     •  Additional oxygen requirements for nitrification

     Fuel cost estimates were determined based on the assumption that the
future solids handling scheme would include digestion and dewatering to a
minimum cake solids  content of 22 percent.   Under this  assumption,  enough
sewage gas is produced to meet  the  fuel requirements of the incinerators and
the digesters.   Additional  fuel  cost estimates  for heating and  service  were
based on costs documented in the 1985 Operating Report prepared by the City of
Columbus Division of Sewerage and Drainage.  Fuel costs for heating and
service were estimated as $200)000 per year for each plant under the two-plant
alternative and $350,000 per  year for the Southerly One-Plant Alternative.
The total energy cost for the Jackson Pike  WWTP and the Southerly WWTP in 1985
was $4.5  million.   In comparing this cost to the 2008 projected cost of $4.7
million,  it must be remembered that the following factors differ between the
two costs.

     •  In 1985 the Southerly digesters were not operating.
     •  Dewatered cake solids at both plants averaged only 17 percent  in 1985.
     •  Power costs in 1985 were $0.04 per  kilowatt-hour.
     •  There is a 6 percent  increase in average flow from 1985 to  2008.
                                      D-7

-------
     Land  application  is  a  contract operation.  Based on past contract costs
 from the city,  it has  a unit cost of $15 per wet ton.

     Operation and maintenance costs for the compost facility were estimated
 based on historical O&M costs.  A unit cost of $30 per wet ton was used.  This
 cost includes materials,  supplies, energy, and labor.

     Ash disposal, which  includes hauling and landfilling,  was estimated at a
 cost of $15 per cubic  yard.

     The total present worth O&M  cost  for  Che combined Jackson Pike and
 Southerly Two-Plant option  is $189,940,000.  This  cost is  13  percent higher
 than the Southerly One-Plant  cost of  $168,200,000.

     Table 1-4 presents the present  worth of the O&M costs for each plant
alternative.

                   TABLE  1-4.   BRIEFING PAPER O&M COSTS ($)
Annual O&M
1988-1992
1993-1997
1998-2002
2003-2007
Total
Southerly
[1-Plant]
16,047,000
16,247,500
16,448,000
16,648,500

Southerly
12-Plant]
8,848,000
9,091,000
9,334,000
9,577,000

Jackson Pik
[2-Plant]
9,257,000
9,257,000
9,257,000
9,257,000

Present Worth
(1988)
168,200,000
94,140,000
95,800,000
                                      D-8

-------
                           2.  FACILITY PLAN COSTS
     Costs were  presented  in  the  Revised Facility Plan  Update  (RFPU)
for the Southerly One-Plant, Southerly Two-Plant, and Jackson Pike Two-Plant
alternatives.  These costs  are for facilities which were sized based on the
flows  and  loads  presented  in  Table 2-1.

                  TABLE 2-1.  FACILITY PLAN FLOWS AND LOADS

                     Jackson Pike    .Southerly    Whittier Street    Total
Average Flow (MGD)         101             75             —             176
Peak Process Flow (MGD)    172            128             —             300
CSO (MGD)                   -              -              130            130
BOD Load (Ib/day)      148,620        131,740          10,000        290,360
TSS Load (Ib/day)      170,390        126,550          20,000        316,940
NOTE:  Flows at Jackson Pike  in excess of 100 MGD will be diverted to
       Southerly under the two-plant alternative.  The additional flow of 130
       MGD of CSO will be transported to Southerly under either alternative.
     These flows and loads differ  from  those used in  the briefing paper.
Table 2-2 presents the Revised Facility Plan Update capital costs associated
with these flows and Table 2-3 presents the RFPU O&M costs for the one-plant
and two-plant alternatives.  The O&M costs  associated  with wet stream
treatment and solids handling were increased throughout the planning period to
account for increases in flows and loads.   The  O&M costs for head works,
administration, Whittier Street facilities, and the Jackson Pike diversion
chamber were held constant throughout  the planning period.

     The RFPU O&M costs also include an amount allocated to "Other Capital
Costs".  These  costs  were originally estimated with capital costs.   The costs
are for rehabilitation or replacement of existing equipment.  Table 2-4 shows a
breakdown of these costs.
                                      D-9

-------
Headworks
Storm Bypass
Stormwater Tanks
Preaeration
Primary Settling
                   TABLE 2-2.  FACILITY PLAN CAPITAL COSTS
                                Southerly          Southerly       Jackson Pike
 Cost  Component                 (One-Plant)        (Two-Plant)        (Two-Plant)

 Site  Work                     $  24,817,490       $  21,120,060      $   8,056,750
 Miscellaneous Buildings          6,314,840         5,856,230          3,514,900
 Plumbing/HVAC                      100,000            100,000          3,071,870
 uA.^u»*b..                       26,278,310         19,536,520         10,163,620
                                 2,316,950         2,316,950

                                 8,802,450         6,516,490          4,148,080
 rrimary aeccung                15,734,910         13,020,930          5,819,100
 Aeration                        63,605,700         34,661,730         23,856,500
 Final Settling                  41,812,710         33,848,295          9,832,890
 Effluent Filters                50,066,830         29,682,210         25,060,510
 "U1~- -•- — •—                     6,489,190         4,367,810          3,218,280
                                 9,221,730            122,340          7,321,300
                                 2,491,210            --                796,280
                                 5,866,755         4,781,660          7,272,140
                                 9,833,400         5,913,650          9,377,250
                                 7,766,720         5,120,895          6,917,630
 ifiernmj. ^UIIUALiumiig               —                ——              3,030,260
 Centrifuge Dewatering           11,943,104         6,721,880            517,580
 Incineration/Ash Lagoon          2,546,770         2,546,770          3,975,830
 Lime Stabilization               1,200,000         1,200,000
 Instrumentation & Control       11,439,090         8,697,710
 Electrical Distribution          2,097,610         2,097,610
 Jackson Pike Rehabilitation     15,000,000
 Whittier Storm Tanks             7,465,180         7,465,180
 Whittier to Jackson Pipe         3,782,300         3,782,300
 Grit to Flow Diversion Pipe     4,738,940         4,738,940
 Interconnector North             5,727,010         6,279,510
 Interconnector South    ,         5,509,780         5,509,780
Miscellaneous                	—          	IZ____          5,000,000

 TOTAL CONSTRUCTION COSTS     $358,475,369      $241,511,840      $149,889,580

 Engineering Fees               42,592,748         26,629,941         15,962,812
Land Acquistion                   200,000           200,000
 Process License Fees            8,000,000         4,000,000          4,000,000
 Salvage Value                  -5.431.000         -3.774.000         -2.059.000

CAPITAL PRESENT WORTH        $403,837,117      $268,567,781      $167,793,000
Chlorination
Effluent Pumping
Outfall Line
Gravity Thickening
Digestion
Centrifuge Thickening
Thermal Conditioning
                                                                    8,331,650
                                                                      607,160
                                      D-10

-------
                  TABLE 2-3,  FACILITY PLAN O&M COSTS  ($/YR)
WETS IDE
1988-1990
1991-1995
1996-2000
2001-2005
2006-2010
2011-2015
SOLIDS
1988-1989
1990-1999
2000-2015
WHITTIER STREET
2-PLANT
SOUTHERLY
4,642,259
5,694,560
6,078,667
6,466,235
7,030,124
7,694,711
6,109,400
6,380,500
6,511,500

2-PLANT
JACKSON PIKE
3,455,820
4,225,624
4,589,694
4,976,569 -
5,625,354
6,416,125
4,887,200
5,090,000
5,192,400

2-PLANT
TOTAL
8,098,079
9,920,184
10,668,361
11,442,804
12,655,478
14,110,836
10,996,600
11,470,500
11,703,900

1-PLANT
SOUTHERLY
6,478,414
7,953,897
8,408,234
8,929,529
9,581,484
10,451,592
8,100,200
8,426,500
8,956,400

1995-2015

JP DIVERSION CHAMBER

1988-2015

HEADWORKS

1988-1089
1990-2015            687,400

ADMINISTRATIVE

1988-2015            400,000

OTHER CAPITAL

1986-2000            915,995

TOTAL
                     47,900
                    136,000
                  1,074,660
                  1,074,660
                    400,000
                    366,066
                     47,900
                    136,000
                  1,074,660
                  1,762,060
                    800,000
                  1,282,061
Present Worth
   (1985)
127,734,009
104,785,539     232,519,548
     47,900
    136,000
  1,219,500
    500,000
  1,141,329
176,166,114
                                      D-ll

-------
                TABLE  2-4.  FACILITY PLAN OTHER CAPITAL COSTS


                                                         COST ($)
 SOUTHERLY  (ONE-PLANT)
  Preaeration
       Replace Diffusers                                  193,000
       Replace Flushing Equipment                          26,000
       Replace Blowers                                     88,000
       Replace Cross Collectors                           111,000
  Pr mary Settling
       Replace Flights, Chains, and Cross Collectors    1,800,000
       Replace Skimming Equipment                          90,000
       Weir Replacement                                   100,000
  Digester Renovation                                   3,600,000
  Centrifuges - Automatic Backdnves                      300,000
  HVAC Renovation                                       8,747,500
  Jackson Pike Sewer Maintenance Yard                     975,440
  Incineration                                          1,300,000

TOTAL                                                  17,330,940

SOUTHERLY (TWO-PLANT)
  Preaeration
    •  Replace Diffusers                                  193,000
    *  Replace Flushing Equipment                          26,000
    *  Replace Blowers                                     88,000
    *  Replace Cross Collectors                           111,000
  Digester Renovation                                   3,600,000
  HVAC Renovation                                       8,747,500
  Jackson Pike Sewer Maintenance Yard                     975,440

TOTAL                                                  13,740,940

JACKSON PIKE (TWO-PLANT)
  Miscellaneous Building Renovation                       257,000
  Primary Building Renovation                             168,000
  Primary Tanks
       Not Filling Tanks                                  230,000
       Replace Flights, Chains, and Cross-Collectors      991,000
       Replace Skimming Equipment                         133,000
       Replace Weirs                                      214,000
       Replace Sluice Gates                               266,000
  Ae ation
       Replace Sluice Gates                               932,000
       Renovate Control Building                          612,000
  HVAC Renovation                                       1.918.000

TOTAL                                                   5,721,000
                                      D-12

-------
           3.  COMPARISON OF BRIEFING PAPER AND FACILITY PLAN COSTS
     Tables 3-1 and 3-2 present cost  comparisons  between the one- and two-plant
alternatives for the briefing paper and facility plan, respectively.  The
facility plan shows the two-plant alternative being 15 percent more costly than
the one-plant.   However, the briefing paper shows the one-plant as 7 percent
more costly than the two-plant.  This difference  between the facility plan and
the briefing paper is primarily a result of differences in design flows.  At
the briefing paper's lower  flows,  a new east train,  headworks, and expanded
Interconnector Sewer are not required under a two-plant alternative.  At the
facility plan flows, these  facilities are required under either alternative.
However, they vary in  size  being  larger for the one-plant.

     A direct cost comparison between the briefing paper and facility plan
costs is not possible for several reasons.   There is a difference in design
flows, costing methods, equipment (the facility plan's  recommended CSO
facilities), and planning periods.

     The difference in flows between  the facility plan is 22 MGD for average
flow and 69 MGD for peak flow.  This  difference affects the costs for the
two-plant alternative more  than the one-plant alternative.

     The method used in the facility  plan  for  O&H costs also caused
differences in the capital costs between Che briefing paper and the facility
plan.   As discussed  in  Section 2,  the facility plan  shifted some
rehabilitation costs from capital to  O&H.   The following processes were
affected by this shift:

     •  HVAC renovation
     •  Preaeration
     •  Primary Settling
     •  Aeration
     •  Centrifuge Dewatering
     *  Incineration
     •  Digestion
                                      D-13

-------
      TABLE 3-1.  PRESENT WORTH OF BRIEFING PAPER CAPITAL AND O&M COSTS


                                Capital            O&M             Total

One-Plant [Southerly]         268,711,000      168,200,000      436,911,000

Two-Plant [So. and JPj        217,860,000      189,940,000      407,800,000

Difference From One-Plant     -50,851,000      +21,740,000      -29,111,000

Percent Difference                -23              +13               -7
NOTE:  These costs are based on a 2008 average flow of 154 MGD and a peak flow
       of 231 MGD.  Present  worth costs are in 1988 dollars.
                                     D-14

-------
     A portion of Che costs were  for routine maintenance costs such as
 painting and roof repairs.  These costs are covered under annual  maintenance
 expenditures.  However,  some of the costs were for major equipment  renovation.
 For example, the $6 million renovation of the existing digesters,  which have
 not operated since 1980, was placed under the O&M costs as "Other Capital
 Costs".   It was felt that these costs should remain in the capital costs.  The
 city has indicated that  the digesters  are  currently undergoing renovation.
 Therefore,  the briefing  paper capital costs include these costs.   The cost of
 renovating the HVAC and  plumbing  systems was placed under O&M costs in the
 facility plan because the systems will be replaced as they become inoperable.
The briefing paper included this cost as capital expenditures in the future
brought back to a present worth amount.

     An additional factor in the cost difference between the briefing paper
and the facility plan costs is the recommended CSO facilities.  Triad has not
 included costs for facilities to control CSO as the city has.  Triad recom-
 mends that a CSO study be completed prior to any recommmendations on CSO
 facilities.  The following facilities are included in the facility plan costs
for CSO:

     *  Storm bypass
     •  Stormwater tanks at Southerly
     •  Whittier storm tanks
     •  OSIS Relief Sewer from Whitter Street to the flow diversion chamber.

     The costs  for the CSO facilities are common to both  a  one and  two-plant
alternative.  Therefore,  they  do not have a significant  impact on the
comparison  between the costs of one-plant vs.  two-plants.

     Effluent filters are no longer needed at either plant  due to changes in
the permit  limits.  Therefore,  they were not included  in the briefing paper
costs.
                                      D-16

-------
     The final factor which causes a difference between the briefing paper and
facility plan costs is the planning period.  The faciltiy plan has a 30-year
planning period beginning in 1985 and ending in 2015.  The briefing paper
planning period extends 20 years, from 1988 to 2008.  This affects the flow
projections, which in turn affect the capital costs.  But more importantly, it
affects O&M costs.  The facility plan has 30 years of annual O&M  costs.  These
costs are presented in 1985 dollars.   The briefing paper only has 20 years of
O&M costs presented in 1988 dollars.
                                     D-17

-------
       APPENDIX E

  BRIEFING PAPER NO. 5
COMBINED SEWER OVERFLOWS

-------
BRIEFING PAPER NO.  5
COMBINED SEWER OVERFLOWS
Supplemental Environmental Impact Statement
USEPA Contract No. 68-04-5035, D.O.  No. 40
Columbus Ohio Waste"water Treatment Facilities
Prepared By:

SCIENCE APPLICATIONS INTERNATIONAL CORPORATION

TRIAD ENGINEERING INCORPORATED

-------
                           COMBINED SEWER OVERFLOW
1.   TERMS AND CONDITIONS
2.   AVAILABLE DATA
3.   CSO ANALYSIS
     3.1  Traditional Approach
     3.2  RFPU Approach:  Review and Critique
     3.3  Briefing Paper Analysis

-------
                                 INTRODUCTION

     Under the direction of USEPA,  a series of briefing papers are being
prepared addressing key issues in the development of the Supplemental
Environmental Impact Statement for the Columbus,  Ohio, Wastewater  Treatment
Facilities.  The  briefing  papers  form the  basis  of discussions  between Triad
Engineering and USEPA to resolve important issues.  The  following  paragraphs
present the background of the facility planning  process,  a description of  the
briefing papers,  and the purpose  of this paper on Combined Sewer Overflow
(CSO).

FACILITY PLANNING PROCESS
     At the time this paper was  prepared (June-August 1987)  the city of
Columbus was proceeding to implement improvements at the Jackson Pike and
Southerly Wastewater Treatment Plants to comply with more stringent effluent
standards which must be met by July 1,  1988.  These improvements were based on
the consolidation of wastewater  treatment  operations at  the Southerly plant.
This one-plant alternative is  a change  from the  two-plant operation proposed
by the city in the  1970's and evaluated in the 1979 EIS.

     The development and documentation of wastewater treatment process and
sludge management alternatives for the Columbus metropolitan area  has been an
extended and iterative process.   The  design and  construction of various  system
components have progressed, because of the  1988  deadline,  while planning
issues continue to be resolved.   As a result, numerous documents have been
prepared which occasionally revise a previously  established course of
direction.

     The concurrent resolution of planning  issues and implementation of
various project components has made preparation  of the EIS more difficult
because final facility plan recommendations are not available in a single
document.
                                     E-l

-------
BRIEFING PAPERS
     To facilitate preparation of the EIS,  a series of briefing papers are
being developed.   The purpose of the briefing papers is  to  allow USEPA to
review the work of the EIS consultant and to identify supplemental  information
necessary for the preparation of the EIS.   Six briefing  papers are  being
prepared as follows:

     •  Flows and Loads
     •  Sludge Management
     *  Process Selection
     *  O&M and Capital Costs
     •  CSO (Combined Sewer Overflows)
     •  One Plant vs. Two Plant (Alternative Analysis)

     The specific focus of each briefing paper will be different.  However,
the general scope of  the papers will adhere to the following format:

     •  Existing conditions will be documented.
     •  Evaluations,  conclusions, and  recommendations of the facilities
        planning process will be reviewed using available documentation.
     •  Where appropriate, an independent evaluation of  the future  situation
        and viable alternatives will be prepared.
     •  The facility  plan and EIS briefing paper conclusions will be  compared.

     The briefing paper process is  intended to:

     •  Prompt the resolution of any data deficiencies.
     •  Clearly establish and define existing and  future conditions.
     •  Identify the  final recommended plan which the city desires  to
        implement.
     •  Provide a data base of sufficient detail to allow preparation of the
        draft EIS.
                                     E-2

-------
COMBINED SEWER OVERFLOWS
     This briefing paper presents an independent evaluation of the status of
the Combined Sewer Overflow (CSO) problem in the city of Columbus.  The
Supplemental Environmental Impact Statement being prepared will address only
Phases 1 and 2 of the city's  facility  planning  process.   The  city  has  advised
USEPA that these two phases do not contain provisions for CSO.  Normal
facility planning processes incorporate CSO into the plan prior to developing
design flows for wastewater treatment  facilities.  However, the city of
Columbus intends to conduct a detailed CSO  analysis  after a majority of the
wastewater treatment  facilities  are in place.

     The  purpose of this briefing paper is to  describe  the traditional
approach to the problem of CSO analysis and in this light, review and  critique
the approach used in the 1985 Revised  Facility  Plan Update (RFPU).   While the
lack of data does not allow a comprehensive analysis of  the CSO problem,  some
general calculations are provided in comparison to those in the RFPU.
                                     E-3

-------
                           I.  TERMS AND DEFINITIONS

     The following terras and definitions are contained in Appendix A of the

current USEPA Region V NFDES Permit Strategy for Combined Sewer Systems.  This

list is reprinted in its entirety and thus, not all of the terras are referred

to  in this briefing paper.  These terms are used throughout the discussions in
this briefing  paper.


Best Management  Practices  (BMPS); - means schedules of activities,
prohibitions of practices,  maintenance procedures,  and other  management
practices to prevent or reduce  the  pollution of  "waters  of the  United  States."
BMPS also includes treatment requirements, operating procedures, and practices
to  control plant site runoff, spillage or leaks,  sludge or waste disposal, or
drainage from  raw  material storage.  (40 CFR 122.2).

Bypass;  - the intentional  diversion of waste streams from any portion of a
treatment facility.  (40 CFR 122.41(m)(4)).  "Treatment Facility"  means
"Treatment Works" as defined below.

Combined Sewer: - a sewer  that  is designed as a sanitary sewer and a storm
sewer.   (40 CFR 35.2005(b)(ll)).   (This  is  distinguished from a  sanitary  sewer
to which inflow  sources prohibited  by the sewer use ordinance have been
connected).

CompleteWaste Treatment System: -  a complete waste treatment system consists
of all  the treatment  works necessary to  meet the  requirements of title HI of
the Act, involving:   (i) the transport of wastewater from individual homes or
buildings to a plant  or facility where treatment  of the wastewater is
accomplished; (11)  the  treatment of the  wastewater to  remove pollutants;  and
(111) the  ultimate  diposal, including recycling or reuse, of  the treated
wastewater and residues which result from the treatment  process (40 CFR
35.2005(b)(12)).   (the catch basins  and overflow points are part of the
complete waste treatment system in a combined  sewer system.  Also see No. 17,
below.)

Dry Weather Flow; - flows  that  are not attributable to rainfall  or snowmelt,
and include  infiltration.

Excessive Infiltration: -  the quantity of  infiltration which  can be
economically eliminated from a sewer system as  determined in a cost-
effectiveness analysis  that compares the costs for correction of the
infiltration conditions to  the  total costs  for  transportation and  treatment of
the infiltration.  (40 CFR 35.2005(b)(16)).

Excessive Inflow; - the quantity of  inflow  which  can be economically
eliminated from a sewer system  as determined by a cost effectiveness analysis
that compares the costs for correcting the  inflow conditions  to  the total
costs for transportation  and treatment of the inflow (normally determined in
                                     E-4

-------
conjunction with the determination  of excessive  infiltration).  (40 CFR
35.2005(b)(16)).

Infiltration; - water other than wastewater that enters a  sewer system
(including sewer service connections and foundation drains)  from the ground
through such means as defective pipes,  pipe joints, connections, or manholes.
Infiltration does not include, and is distinguished from,  inflow.  (40 CFR
35.2005(b)(20)).

Inflow; - water other than wastewater that enters a sewer system (including
sewer service connections) from sources such as, but not limited to, roof
leaders, cellar drains, yard drains, area  drains,  drains from springs and
swampy  areas, manhole covers, cross  connections  between storm sewers and
sanitary sewers, catch basins, cooling towers,  storm waters,• surface runoff,
street wash waters, or drainage.   Inflow does  not include, and is
distinguished from,  infiltration (40  CFR 35.2005(b)(21)).

Nonexcessive Infiltration! - The  quantity  of flow  which is less than 120
gallons per capita per day (domestic base  flow and infiltration) or the
quantity of infiltration which cannot be economically and  effectively
eliminated from a sewer system as determined  in a  cost effectiveness analysis.
(40 CFR 35.2005(b)(28)).

Nonexcessive Inflow; - The maximum total flow rate during  storm events which
does not result  in  chronic operational  problems  related to hydraulic
overloading of the  treatment works or which does not result  in a total flow of
more than 275 gallons  per capita  per day (domestic  base  flow plus infiltration
plus inflow).   Chronic  operational problems may  include surcharging, backups,
bypasses,  and  overflows.  (40 CFR 35.2005(b)(29)).

Operational Flan;  - The objective of the operational plan  is to reduce the
total loading of  pollutants  entering  the receiving stream from  the  complete
waste treatment system.  This plan,  tailored to  the local  government's
complete waste treatment system, will include mechanisms and specific
procedures to ensure:

     a.  the collection and  treatment systems  are  operated to maximize
         treatment;
     b.  all dry weather flows are treated to the level specified in their
         permit;
     c.  storm water entry into the  sewerage system is  regulated;
     d.  the sewerage system hydraulic  and storage capacity  is identified and
         fully utilized during wet weather with  eventual treatment of stored
         flows;
     e.  the greatest  quantity of wet weather  flows receive  maximum possible
         treatment;
     f.  the sewerage system is adequately maintained to ensure optimum
         operational capability.

Overflow; - the uncontrolled diversion of  waste  streams  from a  combined sewer
system which occurs during wet weather when flows exceed conveyance capacity.
                                     E-5

-------
Sanitary Sewer; - a conduit intended to carry liquid  and  water-carried  wastes
from residences, commercial buildings, industrial plants, and institutions
together with minor quantities of ground, storm, and  surface waters that are
not admitted intentionally.  (40 CFR 35.2005(b)(37)).

Sewer Use Ordinance; - that ordinance or other legally binding document
enacted to prohibit any new connections  from inflow sources  into  the  sewer
system and require that new sanitary sewers and connections thereto are
properly designed and constructed.   Such ordinance shall  further  require that
all wastewater  introduced  into the sewer system does not contain toxics or
other pollutants in amount or concentration that endanger public  safety and
physical integrity of the  sewer  system,  pump stations,  or wastewater  treatment
facilities,  cause violation of effluent  limitations or water quality
standards,  or preclude the selection of  the most cost-effective alternate for
wastewater treatment  and  sludge disposal.   (40  CFR 35.2130).

Storm Sewer: - A sewer designed  to carry only storm waters, surface run-off,
street wash  waters,  and drainage.   (40 CFR 35.2005(b)(47)).

Treatment Works; - Any devices and systems for the storage,  treatment,
recycling,  and reclamation of  municipal  sewage,  domestic  sewage,  or liquid
industrial wastes used to implement  section  201 of the Act,  or necessary Co
recycle or  reuse water at  the  most  economical cost over the  design life of the
works.   These include  intercepting  sewers,  outfall sewers, sewage collection
systems, individual systems, pumping, power,  and other equipment  and
alterations thereof;  elements  essential  to  provide a  reliable recycled  supply
such as standby treatment  and  clear water facilities;  and any works,  including
acquisition of the land that will be an integral part of the treatment  process
or is used  for ultimate disposal  of  residues  resulting  from  such  treatment
(including  land for composting sludge, temporary storage  of  such  compost, and
land used for the storage of treated wastewater  in land treatment  systems
before land application);  or any other methods or  system for preventing,
abating, reducing,  storing,  treating, separating,  or  disposing  of  municipal
waste or industrial waste, including waste  in combined storm water and
sanitary sewer systems.  (40 CFR 35.2005(b)(48)).
                                     E-6

-------
                              2.  AVAILABLE DATA
     The operating records for both the Jackson Pike and Southerly Wastewater
Treatment Plants include information regarding the major overflows for each
sewerage system, specifically,  the Whittier Street Storm Tanks for the Jackson
Pike sewerage system  and  the  bypass at the plant for the Southerly sewage
system.  Additional reports which were reviewed for this analysis include the
following:

     •  Revised Facilities Plan Update (RFPU)  prepared  by URS Dalton  September
        30, 1985.
     •  General Engineering Report and Basis of Design  (GERBOD) prepared by
        URS Dalton January 31, 1986.
     •  Combined Sewer Overflow Monitoring Report prepared by Malcolm Pirnie,
        Inc. January 2, 1979.
     •  CSO Progress Report prepared by Malcolm Pirnie, Inc.  July 28, 1983.
     •  Central Scioto River Mainstem Comprehensive Water Quality Report
        prepared by Ohio EPA September 30, 1986.
     •  Use of Combined Sewer Overflow Analysis in the  September 30,  1985,
        Revised Facilities Plan Update prepared by the  city of Columbus  March
        23, 1987.
     While the RFPU contains one page of conclusions reached in the CSO
analysis, there is no information provided describing the analysis itself.
The GSRBOD provides greater detail on the analysis performed,  which references
data provided in the CSO Montioring Report and the CSO Progress Report.  The
final report cited was issued in response to questions by USEPA - Region V in
regard to the CSO analysis referenced in the RFPU.
                                     E-7

-------
                               3.  CSO ANALYSIS

3.1  TRADITIONAL APPROACH
     The traditional approach to a combined sewer system analysis used in this
briefing paper is outlined in a recent USEPA -  Region V document  entitled
"Technical Guidance for Use in the Development  of a Combined Sewer System
Operational Plan" published in September 1986.  The recommended tasks  in the
development of a stormwater management program are:

     •  Establishment of objectives
     •  Development of a data base
     •  Understanding the operation and response  of  the  combined  sewer system
     •  Identification of drainage areas
     •  Hydraulic analysis
     •  Review of meteorological data
     •  Monitoring of flows and collection of samples
     *  Selection of mathematical models
     *  Discussion of CSO control alternatives

     The following paragraphs discuss these aspects  in greater detail.

     The establishment of objectives is a project specific task which  leads
directly into the development of a data base.

     The development of a data base allows a municipality to become
knowledgeable about its combined sewer system,  including operation,
maintenance, and response to different meteorological conditions. Data is
obtained through detailed interviews with sewer,  public  works, and engineering
personnel.   The data required for such a data base includes, but  is  not
limited to:  geographical, geological, topographical,  and hydrologic data;
known physical condition of the sewer system, manholes,  and all appurtenances;
age, length, materials, sizes, slopes,  and depths of sewers; maintenance
practices; problems and system failures; treatment plant flow  records  and
                                     E-8

-------
charts; pumping station flow records, location of overflows and associated
operating experience and records;  identification of sewer system problem
areas; available combined sewer system maps; groundwater levels for all
seasons, with correlation to rainfall;  quality of  local  receiving waters and
required effluent or water quality standards; and  existing  ordinances
governing inflow connections to sewers  and enforcement  programs and policies,
as well as estimates of the extent and  significance of  such inflow
connections.

     Detailed maps of the municipalities sewerage system should be  up  to date
and the combined,  sanitary and  storm sewer systems should be clearly defined.
The maps should show sewer sizes,  slopes,  direction of flow, manhole
locations, and other major sewer system elements  such as regulating or control
structures and overflows.   This information will  allow  a general understanding
of the operation and response of the  sewerage  system.  These maps and data
will also allow the identification of drainage areas  within the  sewerage
system and thus establish  key hydraulic  locations where  flows can be monitored
and gaged.

     The hydraulic analysis proceeds from the collection of data in regard  to
the sewerage system itself.  This  analyis allows the  determination  of the
hydraulic capacities of the sewers.   The portion of  the  sewer system capacity
available for carrying  stormwater runoff is a function of the total hydraulic
capacity of the sewerage system as determined by:   the  pipe size, slope  and
material of construction,  the quantitiy  of  flows; and the level  to  which a
particular sewer can surcharge  without  causing an  overflow, basement flooding,
or other damage.   The most important  parameter which  may be determined in the
hydraulic analysis is that of  the  time  of concentration, which  is used in the
computation of the peak stormwater runoff rate.  Since most rainfall events
are of short duration,  the peak rate of runoff is of primary importance,   with
the total volume secondary.

     The monitoring of flows and collection of samples  should proceed only
after the hydraulic analysis and data collection efforts previously described
                                     E-9

-------
have been completed.  At key locations in the sewerage system and at  the major
overflow points, as previously determined,  flows should be  monitored  along
with collection of rainfall data.  Further,  it  is  desirable that  samples be
collected at the overflows at short time intervals during an overflow in order
to associate pollutant concentrations with the overflow. The rain gauges
should be located throughout the  sewer system service area  in order to
characterize the rainfall in terras of duration, intensity,  and volume. Thus,
in the knowledge provided by the data base  and hydraulic analysis that all
flows are accounted for, the volume of overflow and mass loading of pollutants
discharged to the receiving waters may be computed.  Then the intensity
duration relationships of the observed rainfalls may be compared to historical
records to relate the observed overflows to a recurrence interval.  Thus,
statistical relationships may be developed  which will relate rainfall to
overflow volumes and quality.

     The CSQ analysis may then be taken a step further in complexity  with the
use of a mathematical  model.  Mathematical  stormwater models are capable of
predicting the volume of stormwater  discharge  and  its constituent pollutants.
These models typically consist of two elements - a runoff element that
simulates the washoff of pollutants by rainfall on the watershed, and a
transport element that simulates the movement of those pollutants in  the sewer
system and their eventual discharge from it.   Data from flow monitoring and
sampling efforts may be used to calibrate such  a model after  which the model
is an invaluable tool in evaluating the effectiveness of various  control
alternatives and to identify optimum solutions.

3.2  FACILITIES PLAN APPROACH:   REVIEW AND  CRITIQUE
     Very little of the  data necessary  for  a  traditional CSO analysis  was
presented in the RFPU.   Existing  monitoring data was utilized from two support
documents:  The Combined Sewer Overflow Report of January 1979,  and the CSO
Progress Report of 1983.
                                     E-10

-------
     While  the quality of the monitoring data used is unknown, its value is
of some question due to the poorly developed data base regarding  the sewerage
system.  No maps of  the sewerage system were presented or developed, thus, the
drainage areas for each overflow or each system  (combined, sanitary, or storm)
were not clearly defined.  While  the CSO Progress Report (1983) did include a
discussion of computer modeling of the sewerage system with reference to the
Whittier Street Storm Tanks using the SWMM model, the input data  was not
presented and the results were not discussed or presented.   The Combined
Sewer Overflow Report (1979) includes a one year record of  overflow monitoring
data for nineteen overflow sites,  but the  completeness of this record is
subject to some question.  Further,  due to  the  lack of data in regard to how
the sewerage system  responds to wet weather conditions,  whether or not all
major overflows are  accounted for with the monitoring data is unknown.  The
fact that both support  documents and the RFPU overlooked  the Renick Run
overflow supports this contention.

     The discussion of the Combined Sewer Overflow analysis in the RFPU makes
four points:

     1. The CSO analysis consisted of ten  rainfall (overflow)  events  from 1979
        and 1982.
     2. The statistical analysis performed on these ten events showed that the
        80th percentile storm could be controlled at  a cost of $42 million.
     3. The environmental impacts of the existing combined  sewer  overflows
        were shown to be insignificant according  to documentation in the Draft
        OEPA Central Scioto River Water Quality Report and  the city river
        sampling results as reported in the monthly operating reports (MORs).
     4. The city would  meet its  NPDES permit requirements regarding the sewer
        system overflows and would continue to closely observe the Scioto
        River, the Olentangy  River, and Alum Creek in  order  to mitigate any
        adverse environmental impacts due  to overflows.
     There is no other  detail provided on  the  CSO analysis  in the RFPU other
than to make these four  points.   It was  not  until  four months  later that the
analytical  methodology for the CSO analysis was presented in the  GERBOO
(January 31,  1986) and  later  in  the report  titled  "Use of Combined  Sewer
                                     E-ll

-------
Overflow Analysis" in the September 30, 1985,  Revised Facilities Plan Update
(RFPU) which was submitted to USEPA - Region V March 23,  1987,  by the city.

     While it was  stated  in  the RFPU that the environmental impacts of the
existing combined sewer overflows were shown to be insignificant according to
documentation in the draft OEPA Central Scioto River Water Quality Report
(CWQR),  a review of this report did not substantiate this statement.  In fact,
information in the CWQR suggests that the environmental impacts of the
existing CSOs are significant.   On page 195  the CWQR states that "combined
sewer overflows, and as previously discussed,  plant bypasses also contributed
significant loadings of BOO^, NH^-N,  TSS,  and  other substances  to the Central
Scioto River Mainstera".  Further, page 317 states, "Reductions  in the
magnitude and frequency of combined sewer overflow discharges is needed to
improve aquatic community  function, alleviate aesthetic problems, and reduce
risks to human body contact recreation  in  the segment between Greenlawn Dam
and the Jackson Pike WWTP".

     The combined sewer overflow analysis presented in the RFPU considered
only Whittier Street overflows and neglected all others including the bypass
flows at Southerly.  The city analyzed  ten events  which were selected from a
larger data set of twenty-six events.   The ten  events  selected  were those that
had both quality and quantity data.   Data  for  the  events  not selected was not
presented.  Thus, due to  the  manner in  which the ten events were selected,
whether or not they can be considered representative of flows at the Whittier
Street facility is questionable, and  whether or not they  can be considered to
be representative of combined sewer overflows  from the entire sewerage system
is more questionable.

     The statistical analysis performed for the RFPU consisted  of plotting the
ten events  on probability paper  using a simple  Weibull plotting position
calculation.   Using this method, m is the rank of  the event  [highest (1) to
lowest (10)]  and n is the number of events (10).   The  plotting  position thus
calculated  refers to the probability or return period that is associated with
each of the observed events.   The use of  this  method is illustrated in Table
                                     E-12

-------
1, where the calculated plotting positions and associated return period for
each of the ten events analyzed are shown.  Thus, for event number 1 of
10/8/77, a  plotting  position of 0.364 is calculated.   This number refers to
the fact that 36.4 percent of  the  observed overflow volumes are less than that
of event number 1, while  63.6 percent of the observed overflow volumes are
greater that that of event number  1.  Thus, if the data set is established and
representative, projections may be made on the overflow volumes.  This method
further defines the recurrence interval (in years)  as the inverse  of the
calculated plotting position.   Thus,  the recurrence interval for event number
1 with a volume of 44.1 would be 1/0.364 or 2.75  years.   Thus  an overflow of
this magnitude could be expected to occur  every  2.75 years.   Note,  however,
that the data base from which  this  projection is  made consists of ten hand
picked events from a period of time of  about one year.  While the objective of
this method is to make such projections with a limited amount of data, the
questions still remain as to how representative  these ten events are and what
about the other overflows  in the system?  The calculated probabilities of the
ten events may have easily been checked using the rainfall data for each event
and associating a  recurrence interval  with the rainfall  intensity  which
induced the overflows based on a histrocial  record of rainfall  for the area.
However, this check was not performed.

     Thus,  the 80th percentile overflow was  shown  to be  50 million gallons.
In addition, the 80th percentile overflow  at  Renick Run was estimated at  12  MG
by taking a simple proportion of the 80th percentile flow to the hydraulic
capacity of the pipes converging at each overflow.   Thus, a  total  volume of 62
million gallons was recommended in the  RFPU for storage or treatment and the
cost associated with control at  this  level was estimated at $42 million.

3.3  BRIEFING PAPER ANALYSIS
     Lack of flow data does not allow an independent  comprehensive
analysis of the CSO problem.  Therefore, the following analysis is presented
only to provide data for comparison with  the  figures in  the RFPU.   The
combined sewer overflow volumes may be estimated using a procedure outlined in
                                     E-13

-------
        TABLE 1


Total CSO
Event Date Volume (MG)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
10/8/77
10/26/77
8/6/78
8/19/78
8/29/78
8/30/78
9/16/78
8/4/82
8/25/82
9/14/82
44.1
3.1
26.1
10.4
6.1
73.3
16.2
44.9
51.9
12.8
    Rank (m)
Highest to lowest

       4
      10
       5
       8
       9
       1
       6
       3
       2
       7
                   Plotting Position  (P)
0.364
0.909
0.455
0.727
0.818
0.091
0.545
0.273
0.182
0.636
                  Recurrence
                  Interval (yr)
                      (1/P)
  ,75
  ,10
  ,20
  ,38
  ,22
10.99
 1.83
 3.66
 5.49
 1.57
           E-14

-------
reference 1.  This method first estimates the percent imperviousness of the
area by the following equation:

    Percent Imperviousness = I - 9.6 PD(0-573 " °*0391 Io8 PD>
    Where PD = Population Density (Persons Per Acre)
     The population density for the combined sewer  area for the city of
Columbus was  cited  as 15.78 persons per acre in reference 2.   While the
                                                                   o
combined sewer  service area is known  to have decreased from 18.4 mi   to the
                           n
present estimate of 11.1  mi  (as  per city officials),  the population density
for this area may be assumed to have remained about the same.   Therefore,  16
persons per acre will be assumed,  thus:

                     I = 9.6 (16)(0*573 ~ °-0391 log 16)
                       = 41.3%
     Next the runoff coefficient  (CR)  weighted  between pervious and impervious
areas is estimated as follows:

                           CR = 0.15 + 0.75  (1/100)
                              " 0.15 + 0.75  (41.3/100) -  0.460
     The area weighted depression storage (DS)  is  then estimated assuming
0.0625 inches for impervious areas and 0.25  inch for pervious  areas.

                          DS - 0.25 - 0.1875 (1/100)
                             =  0.25 - 0.1875 (41.3/100) - 0.327 in.
     Finally,  the annual  runoff (AR) is  estimated  for  the  CSO  area  in  terms of
inches per year over the  given  area.

                         AR = (CR) P-5.234 (DS)0'5957
     Where P - Annual precipitation, in/yr = 37.01 in/yr
               AR = (0.46X37.01  in. )-(5.234X0.327  in.0'5951)
                  « 14.33 inches  per year
                                     E-15

-------
     Since Che existing combined sewer service area is known to be 11.1 mi ,
the estimated annual volume of runoff from this area  may be calculated  as
f o1 lows:

11.1 mi2 x 14.33 in. x 1 ft. x 52802 ft.2 x 7.481 Gal = 2,760  x 106  gallons  per ye.ir
                      12 in.     1 ml21 ft.
     A summary of  the 1985  and 1986  precipitation record for the city of
Columbus is provided in  Table 2.  This table shows the  number of days in which
precipitation was recorded  for each year broken down by depth.   In order to
relate the previously calculated  annual volume of  runoff  from the  combined
sewer area to a rainfall day basis, an average value  for 1985  and  1986  of 58
significant days of rainfall may be assumed.  A "significant" rainfall  may be
defined as all days  when greater than 0.15 inches of rainfall were recorded.
This number is reasonable  since the depression storage  for  the  combined sewer
area was previously  calculated at  0.327 inches.  Thus on a per-significant-
rainfall-day basis, a daily  volume  of runoff from  the combined  sewer  area may
be calculated as follows:

             2,760 x 106 GalIons  _•_ 58 Significant Rainfall Days
                          Year    '             Year
                        -  48 x 106 Gallons
                                   Signficant  Rainfall Day
     In addition to this flow, however,  is inflow from the separate sewer area
which must be estimated.  Since  the extent of  the inflow problem in  the
separate sewer area is unknown,  it will be assumed to be at the point of being
nonexcessive (refer to Section 1:  Terms and Definitions).   The  construction
grants program defines a nonexcessive inflow value of 275 gallons  per capita
per day (gpcd) as  the maximum allowable total  daily flow during a storm.
Thus, knowing  that the  average dry weather flow  is  167 gpcd (ref. Briefing
Paper No.  1),  a maximum allowable  inflow volume of 108 gpcd can be assumed for
this area.  The population for the  separate sewer  area  may be estimated by
subtracting the product  of the assumed combined sewer  population density (16
persons/acre) by the combined sewer area (11.1  mi  =  7104 acres) from the
total service area population (870,000 persons).   Thus  the population served
                                     E-16

-------
inflow from  the combined  sewer service area that only 3.6 percent of the total
significant rainfall would have to be accounted for as inflow.   It  must also
be noted that this simple volumetric analysis only considers average
conditions, i.e. 0.51 inches of  rainfall  per significant  rainfall  day.   Note
from the precipitation record of Table 2 that an average of 20 days each year
were recorded with precipitation greater  than this  amount with a maximum daily
total of 1.41 inches for 1985 and  1.69 inches for 1986.   It  must also be
recognized that this analysis  is only volumetric and does not account for the
maximum  rate of runoff or rain-induced inflow.   This  maximum rate would be of
primary importance in the selection of control  alternatives  or design of
facilities.  This  parameter,  however, can only be determined through a
detailed hydraulic analysis of the sewerage system.
           P
           R
           E
           C
           I
           P
           I
           T
           A
           T
           I
           0
           N

           D
           E
           P
           T
           H

           R
           A
           N
                          TABLE 2.  PRECIPITATION
1985

(Inches)
0.00 to 0.05
0.05 to 0,10
0.10 to 0.15
0.15 to 0.20
0.20 to 0.25
0.25 to 0.30
0.30 to 0.35
0.35 to 0.40
0.40 to 0.45
0.45 to 0.50
0.50 to 0.55
0.55 to 0.60
0.60 to 0.65
0.65 to 0.70
0.70 to 0.75
0.75 to 0.80
0.80 to 0.85
0.85 to 0.90
0.90 to 0.95
0.95 to 1.00
1.00 to 1.05
1.05 to 1.10
1.10 to 1.15
i i «; t-~ i ->n

Days
43
27
18
8
7
5
4
3
7
1
2
2
0
5
2
2
0
0
4
0
0
1
0
n
Total
Depth
(In.)
0.95
1.82
2.21
1.33
1.48
1.34
1.28
1.13
2.93
0.47
1.02
1.13

3.33
1.42
1.53


3.69


1.07


1986

Days
40
19
10
9
9
6
7
3
2
2
3
0
1
1
4
3
1
0
3
2
0
0
0
n
Total
Depth
(In.)
0.83
1.24
1.17
1.48
1.93
1.65
2.24
1.1
0.86
0.95
1.55

0.63
0.7
2.89
2.32
0.82

2.75
1.93





-------
                                  REFERENCES
1.   Heaney, J. P.,  et. al. Storm Water Management  Model:   Level 1 -
     Preliminary Screening Procedures.  USEPA Report No. EPA-600/2-76-275.
     NTIS No. PB 259 916.  October 1976.

2.   Heaney, J. P., et. al. Nationwide Evaluation of Combined Sewer  Overflows
     and Urban Stormwater Discharges, Volume II:  Cost Assessment and Impacts.
     USEPA Report No. EPA-600/2-77-064.   NTIS No.  PB 266 005.   March 1977.
                                     E-20

-------
       APPENDIX F

  BRIEFING PAPER NO.  6
ONE-PLANT VS. TWO-PLANT

-------

-------
BRIEFING PAPER NO.  6
ONE-PLANT VERSUS TWO-PLANTS
Supplemental  Environmental Impact Statement
USEPA Contract No. 68-04-5035, D.O. No. 40
Columbus Ohio Waste"water Treatment Facilities
Prepared By:

SCIENCE APPLICATIONS INTERNATIONAL CORPORATION

TRIAD ENGINEERING  INCORPORATED

-------
                          ONE-PLANT VERSUS TWO-PLANTS
1.   EXISTING FACILITIES
     1.1  Jackson Pike Wastewater Treatment Plant
          1.1.1  Major Interceptors
          1.1.2  Preliminary Treatment (O.S.I.S. Flow)
          1.1.3  Major Treatment Processes

     1.2  Southerly Wastewater Treatment Plant
          1.2.1  Major Interceptors
          1.2.2  Interconnector Pump Station
          1.2.3  Major Treatment Processes
2.   IDENTIFICATION OF SYSTEM ALTERNATIVES
     2.1  No Action Alternative
     2.2  Upgrade the Existing Facilities
     2.3  Eliminate Jackson Pike, Upgrade and Expand Southerly
3.   DEVELOPMENT AND EVALUATION OF SYSTEM ALTERNATIVE COMPONENTS
     3.1  Interconnector/Headwortcs
          3.1.1  One-Plant System Alternative
          3.1.2  Two-Plant System Alternative

     3.2  Wet Stream Treatment
          3.2.1  One-Plant System Alternative
                 3.2.1.1  Primary Treatment
                 3.2.1.2  Secondary Treatment
                 3.2.1.3  Post Treatment
          3.2.2  Two-Plant System Alternative
                 3.2.2.1  Primary Treatment
                 3.2.2.2  Secondary Treatment
                 3.2.2.3  Post Treatment
     3.3  Solids Handling and Disposal
          3.3.1  One-Plant System Alternative
          3.3.2  Two-Plant System Alternative
4.   EVALUATION OF SYSTEM ALTERNATIVES

-------
                                 INTRODUCTION

     Under Che direction of USEPA, a series of briefing papers are being
prepared addressing key issues in the development of the Supplemental
Environmental Impact Statement for the Columbus,  Ohio,  Wastewater Treatment
Facilities.  The briefing  papers  form the basis  of discussions between USEPA
and their consultant to resolve important issues.  The  following paragraphs
present the background of the facility planning process, a description of the
briefing papers, and the purpose of this paper on one-plant versus two-plants.

FACILITY PLANNING PROCESS
     At the time this paper was prepared (July-August 1987) the city of
Columbus was proceeding to implement improvements at the Jackson Pike and
Southerly Wastewater Treatment Plants to comply with more stringent effluent
standards which must be met by July 1,  1988.   These improvements  were based
on the consolidation of wastewater treatment operations at the Southerly
plant.   This  one-plant alternative  is a  change from  the two-plant  operation
proposed by the city in the  1970's and evaluated in the 1979 EIS.

     The development and documentation of wastewater treatment process and
sludge management alternatives for the Columbus metropolitan area has been an
extended and iterative process.    The design  and  construction  of various
system components have progressed, because of the 1988  deadline, while
planning issues continue to be resolved.  As  a result,  numerous  documents have
been prepared which occasionally revise a previously established course of
direction.

     The concurrent resolution of planning issues and implementation of
various project components has made preparation of  the  EIS  more difficult
because final facility plan recommendations are not available in a single
document.
                                     F-l

-------
BRIEFING PAPERS
     To facilitate preparation of the EIS,  a series of briefing papers  are
being developed.   The purpose of the  briefing papers  is  to  allow USEPA  to
review the work of the EIS consultant and to identify supplemental  information
necessary for the preparation of the  EIS.   Six briefing  papers  are  being
prepared as follows:

     •  Flows and Loads
     •  Sludge Management
     •  CSO
     •  Process Selection
     •  One Plant vs. Two Plant (Alternative Analysis)
     •  O&M and Capital Costs

     The specific focus of each briefing paper will be different.   However,
the general scope  of  the  papers  will  adhere to the  following format:

     •  Existing conditions will be documented.
     *  Evaluations,  conclusions, and  recommendations of the facilities
        planning process will be reviewed using available documentation.
     •  Where appropriate, an independent evaluation of  the future  situation
        and viable alternatives will be prepared.
     •  The facility  plan and EIS briefing paper conclusions will be compared.

     The briefing paper process is intended to:

     •  Prompt the resolution of any  data deficiencies.
     •  Clearly establish and define  existing and future conditions.
     •  Identify the  final recommended plan which the city desires  to implement.
     •  Provide a data base of sufficient detail to allow preparation of the
        draft EIS.
                                     F-2

-------
ONE-PLANT VS. TWO-PLANTS
     This briefing paper evaluates the comprehensive wastewater management
alternatives in light of previous biological process, solids handling, and
cost analyses.  The briefing paper is divided into four sections as follows:

Section 1 - Existing Facilities
     This section discusses the facilities which existed at the Jackson Pike
and Southerly WWTPs prior to implementing construction for Project 88.

Section 2 - System Alternatives
     Section 2 provides a description of the one-plant and two-plant
alternatives.

Section 3 - Development and Evaluation of System Alternative Components
     Section 3 summarizes the facilities required for each process under the
one-plant and two-plant alternatives.  Costs are included for  all facilities.

Section 4 - Evaluation of System Alternatives
     This section provides a technical evaluation of the  one-plant and two-
plant alternatives based on present worth cost,  reliability, flexibility,
implementability,  and operational ease.
                                     F-3

-------
                           I.   EXISTING FACILITIES

     This section describes the Jackson Pike  and  Southerly  Wastewater
Treatment Plants (WWTP).  Figure 1-1 shows the locations of the  two treatment
plants and the Southwesterly Compost Facility within the planning area.

1.1  JACKSON PIKE WASTEWATER TREATMENT PLANT
     The Jackson Pike WWTP began operation in 1937.  The  plant was  modernized
and expanded in capacity  in  the raid-fifties.  Currently  (prior to Project 88)
there are two parallel flow trains for wet stream treatment consisting of
preaeration, primary settling, aeration, and final clarification.  The
original train is called Plant A and the newer train is called Plant B.  The
two trains operate relatively independently of each other during liquid
processing but share sludge  handling  facilities.

1.1.1  Major Interceptors
     Wastewater arrives at the Jackson Pike plant via the 108-inch  diameter
Olentangy-Scioto Interceptor Sewer  (O.S.I.S.)  and the 72-inch Big Run
Interceptor Sewer.   The maximum hydraulic  capability of  the plant is 100 MGD.
Current average day flows are approximately 84 MGD.  The plant  accepts all the
flow from  the  Big  Run Interceptor but limits its  acceptance of  the  O.S.I.S.
flow so the hydraulic capability of  the plant will not  be exceeded.   The major
diversion point for the O.S.I.S. flows  is  at  the  Whittier Street  Storm Standby
Tanks.

     Seven miles of 150-inch and 156-inch diameter gravity sewer currently
exists between the Jackson Pike and Southerly treatment  plants.   It begins
3,000 feet  from the Jackson Pike WWTP and connects with a pump station on the
west side of the Scioto River near the Southerly WWTP.   In September of 1986,
USEPA provided funding for construction of the remaining 3000 feet of the
sewer (Figure 1-2).  This will complete  the Interconnector  Sewer  between the
two plants.  Included in the  north end construction will be a diversion
chamber which  will connect the  Interconnector Sewer with the O.S.I.S. north of
                                      F-4

-------
JACKSON PIKE WWTP

SOUTHERLY WWTP
APPROXIMATE SCALE.  1 INCH = 4.12 MILES
SOUTHWESTERLY COMPOST FACILITY
PLANNING AREA BOUNDARY  p_5
                          FIGURE 1-1
                          PLANNING  AREA

-------
      8  I
                                       -H-
                                         O'
                                                     I   I
                                                    I    )
PROPOSED
DIVERSION -^
CHAMBER \
/
X r . -. " \
f j aa
nr~ir"i r —
i i iu3UQ
]

DDDD I
§ \ * \
/^ ^ o t
/ O : ^4 .
/^ \ o \
//* TO
/ 10 I 5 \
A \ i
3 l i
\ \
~^\ } '
J '
r-,n v
(^ N



                         JACKSON PIKE WASTEWATCR TREATMENT PLANT
                          PROPOSED 150"
                          INTERCONNECTOR  EXTENSION
                          & 8" SLUDGE LINE EXTENSION
SOURCE:  REVISED FACILITY PLAN UPDATE
                              F-6
FIGURE 1-2
NORTH END INTER CONNECT OR

-------
Jackson Pike.   These improvements will allow the flow to Jackson Pike to be
controlled by diverting excess flows to Southerly.

1.1.2  Preliminary Treatment (O.S.I.S.  Flow)
     Preliminary treatment is provided  for flows entering Jackson Pike through
the O.S.I.S.  at a facility called the Sewer  Maintenance  Yard  which is located
approximately one mile north of Jackson Pike.  These  preliminary  treatment
facilities were  constructed in 1948.  They  are  rated at a  capacity  of 160 MGD
and provide preliminary screening and  grit  removal  for  flows in  the  O.S.I.S.
prior to their arrival at Jackson Pike.

1.1.3  Major Treatment Processes
     The Jackson Pike WWTP consists  of  the following  major  treatment
processes:

     •  Preliminary Treatment
     •  Primary Treatment
     •  Secondary Treatment
     •  Disinfection
     •  Solids Handling
     •  Solids Disposal

     Figure 1-3 shows a flow schematic of the Jackson Pike  WWTP.   Table 1-1
presents the equipment sizes and the capacities for each unit process.

1.2  SOUTHERLY WASTEWATER TREATMENT PLANT
     The Southerly WWTP began operation in  1967 with a  single train.  In the
early seventies,  an additional  wet  stream train was  added.  The original train
is termed the Center Section.  The  newer train is called the  West Section.
                                      F-7

-------
                                                     PLANT
                                     PRIMARY
                                  CLARIFICATION
                     AERATION
               PUMPING
INFLUENT





     SCREENING
                         PREAERATIDN
                                     PRIMARY
                                  CLARIFICATION
                   PLANT 'B*
                          PREAERATIDN
00
                                            PRIMARY
                                            SLUDGE
                                            HOLDING
                  INCINERATION
CENTRIFUGE
DEVATERING
                    SECONDARY
                  CLARIFICATION
                                                                                CHLORINATION
                      AERATION     SECONDARY
                      AcRATIUN    CLARIFICATIQN
                                                                                          EFFLUENT
                                                                                     VAS
                                                                                     HOLDING
                                                  CENTRIFUGE
                                                  THICKENING
                                                  WAS


                                                  THICKENED
                                                  SLUDGE
                                                  BLEND/STORAGE
   DIGESTED      ANAEROBIC
SLUDGE HOLDING   DIGESTION
                                                        THICKENED RAW SLUDGE
                                                        TO DEVATERING
                      •rn

                   LANDFILL
  TG LAND
APPLICATION
                  THERMAL
                CONDITIONING
FIGURE i-3
JACKSON PIKE WTP
FLO₯ SCHEMATIC

-------
                                          TABLE  1-1.   JACKSON PIKE EXISTING FACILITIES
\o
      Process
      Screening
      Pumping
      Preaeration
      Blowers for Preaeration and
        Aeration
      Primary Clarification
      Aeration
      Secondary Clarification
      Chlorination

      Waste Activated Sludge
      Holding
Facilities/Condition

Two mechanically cleaned bar screens
with 1.5-inch openings, west screen
replaced in 1983

Two variable speed at 55 MGD (32 ft TDK)
Two constant speed at 27.5 MGD (27.5 ft TDK)
One constant speed at 60 MGD (30 ft TDK)

Plant A - 2 tanks at 180 ft x 26 ft x 15 ft SWD
Plant B - 2 tanks at 113 ft x 26 ft x 15 ft SWD

4 at 21,000 cfm
2 at 15,000 cfm
2 at  3,000 cfm
3 at 12,500 cfm

Plant A - 4 tanks at 150 ft x 80 ft x 10 ft SWD
Plant B - 4 tanks at 150 ft x 80 ft x 10 ft SWD
Twelve sludge pumps at 250 gpm each

Plant A - 8 tanks at 900 ft x 26 ft x 15 ft SWD
Plant B - 4 tanks at 900 ft x 26 ft x 15 ft SWD

Plant A - 8 tanks at 153 ft x 60 ft x 12.5 ft SWD
Plant B - 4 tanks at 153 ft x 60 ft x 12.5 ft SWD
six return sludge pumps; one at 6,944 gpm,
one at 5,555 gpm, one at 5,902 gpm, one at
3,889 gpm, and two at 3,472 gpm each

By direct injection into discharge pipeline

One 78-foot x 14-foot x 8-foot deep basin
(two) standby units
165 MGD
1.05 MG total volume
0.66 MG total volume
48,000 SF total surface area
48,000 SF total surface area
21.0 MG total volume
10.5 MG total volume

73,440 SF total surface area
36,720 SF total surface area
0.065 MG of storage

-------
                                TABLE 1-1.  JACKSON PIKE EXISTING FACILITIES (cent.)
Process
Facilities/Conditions

One 85-foot dia., 25.25-foot SWD
I
*-*
o
Primary Sludge Holding

Centrifuge Thickening (WAS)   Two solid bowl centrifuges
Anaerobic Digestion




Digested Sludge Holding

Thermal Conditioning


Centrifuge Dewatering



Incineration


Ash Lagoon


Landfill

Land Application

     Sludge Transport and
     Application



     Application Sites
Eight primary digesters:
70-foot dia., 27.5-foot SWD
Six secondary digesters:
85-foot dia., 23.5-foot SWD

One 85-foot dia., 25.5-foot SWD

Two reactors installed 1972,
Expanded 1978 to 4 reactors

Six solid bowl centrifuges
Installed 1976
Two multiple-hearth incinerators
7-hearths, 22.25-foot diameter

Two lagoons
City-owned landfill
Contract operation
Required acreage    2000 Ac/yr
Available acreage  10000 Ac
                                                                                          1 MG of  storage

                                                                                          550 gpm/unit, 400 HP/unit
                                                                                          Feed Solids  1%
                                                                                          Thickened WAS 4%

                                                                                          Volume:  1.6 x 106 CF Total
                                                                                                  6.3 MG Primary
                                                                                                  6.0 MG Secondary
                                                                                         1.0 MG of storage

                                                                                         200 gpm/unit
                                                                                         100 gpm/unit,  100 HP/unit
                                                                                         Feed solids 3%
                                                                                         Dewatered cake 16-18%

                                                                                         170 wet tons/day
                                                                                         Feed solids 16-18%

                                                                                         Total storage  capacity 48,000 cy;
                                                                                         Cleaned as needed

                                                                                         Ash Landftlied on an as-needed
                                                                                         basis through  contract operation
                                                                                         Transport 130-150 tons/day
                                                                                         Application 70-200 tons/day
                                                                                         Approximate Unit Cost of
                                                                                         $ll/wet ton

                                                                                         Application 260 days/yr
                                                                                         Seasonal peaks dependent
                                                                                         on weather and cropping patterns

-------
1.2.1  Major Interceptors

     Southerly receives approximately 50 to 60 MGD via the Big Walnut Sanitary
Outfall Sewer which serves  the northeast, east, and southeast portions of
Columbus and Franklin County.  An additional 5 MGO of flow is carried to
Southerly by the Interconnector Sewer which serves  a  portion  of western
Columbus.  The Southerly WWTP only accepts the amount of flow that it can
successfully treat and bypasses the  remaining  flow.    Plant records  show that
bypassing occurs when treated flows  are as low as 54 MGD.  At other  times
treated flows can be as high as 90 MGD and no bypassing  is reported.  Excess
flow can be diverted to the Scioto River through a 108-inch diameter bypass
sewer at the plant's influent regulator chamber.

1.2.2   Interconnector Pump Station
     The purpose of the Interconnector Pump Station is to pump flows from the
Interconnector across the Scioto  River to the  Southerly WWTP.  The Intercon-
nector Pump Station is located on the south end of the Interconnector near
Southerly (Figure 1-4).  Flows from  the  156-inch Interconnector Sewer enter a
58-foot wide by 25-foot long by 16-foot deep chamber to be distributed to
three channels containing coarse  bar racks  and  mechanically-cleaned  bar
screens.   Each channel is  6  feet  wide by 30 feet long by 33 feet high.   Flows
from the screening channels  enter a  20-foot wide by 66-foot  long by  23-foot
high wet well and are pumped by two 20 MGD and two 30 MGD extended shaft
centrifugal pumps through one 36-inch and one  48-inch force main to  the
Southerly headworks.

1.2.3   Major Treatment Processes
     The Southerly WWTP consists  of  the  following major treatment processes:

     •  Preliminary Treatment
     •  Primary Treatment
     •  Secondary Treatment
     *  Disinfection
                                     F-ll

-------
     •  Solids Handling
     •  Solids Disposal

     Figure 1-5 shows a flow schematic of Che Southerly WWTP.   Table  1-2
provides sizings and capacities of individual unit  treatment processes.
                                     F-12

-------
                                       CENTER TRAIN
       SCREENING
                       PREAERATIDN
PUMPING
RAW
INFLUENT
 I
 I—"
 U)
              GRIT REMOVAL
                       PREAERATIDN
                      CENTRIFUGE
                      DEVATERING
                           PRIMARY
                        CLARIFICATION
                                                                 AERATION
                                                            SECONDARY
                                                           CLARIFICATION
                           PRIMARY
                        CLARIFICATION
                CHLORINATION
                      EFFLUENT
               VEST  TRAIN
                                                                     SECONDARY
                                                                   CLARIFICATION
                     ANAEROBIC
                     DIGESTION
                     
-------
                                    TABLE 1-2.  SOUTHERLY WWTP EXISTING FACILITIES
t
(-•
4>
Process
Screening
Grit Removal
Pumping
Preaeration
Primary Clarification
Aeration
Secondary Clarification
Disinfection
Dissolved Air Flotation
Thickening  (WAS)
Facilities/Condition
Four bar racks with 5.5-inch openings
Four mechanical bar screens with 1-inch openings

Two aerated grit tanks at 44.5 ft x 20 ft x 13.5 ft SWD
Two aerated grit tanks at 51.2 ft x 20 ft x 13.5 ft SWD
Two variable speed blowers at 960 cfm each

Three variable speed pumps at 35 MGD (38 feet TDK)
Two variable speed pumps at 65 MGD (42 feet TDH)
One constant speed pump at 35 MGD (38 feet TDH)

Center Train - 4 tanks at 112.7 ft x 26 ft x 15.5 ft SWD
West Train - 4 tanks at 112.7 ft x 26 ft x 15.5 ft SWD
Three constant speed blowers at 3,400 cfm each

Center Train - 4 tanks at 80 ft x 165 ft x 10 ft SWD
West Train - 4 tanks at 100 ft x 170 ft x 10 ft SWD
Twelve sludge pumps at 150 gpra each

Center Train - 4 tanks at 26 ft x 900 ft x 15 ft SWD
West Train - 6 tanks at 26 ft x 900 ft x 15 ft SWD
Nine blowers at 20,000 cfm each

Center Train - 4 tanks at 89 ft x 170 ft x 12.5 ft SWD
West Train - 4 tanks at 104 ft x 180 ft x 10.5 ft SWD
Return sludge pumps - 4 at 7,000 gpm each,
4 at 10,500 gpm each, 4 at 8,100 gpm each,
4 at 12,000 gpm each
Waste-activated sludge pumps - 8 at 200 gpm each

Six 2,000 Ib/day chlorinators
Six 8,000 Ib/day evaporators
One chlorine contact basin at 260 ft x 260 ft x 7 ft SWD

Four units {? 1,900 SF/unit
(Abandoned 1978 used as
WAS concentration tanks)
0.39 MG total volume
170 MGD
1.36 MG total volume
1.36 MG total volume
52,800 SF total surface area
68,000 SF total surface area
10.5 MG total volume
15.8 MG total volume
60,520 SF total surface area
74,880 SF total surface area

-------
                                   TABLE 1-2.   SOUTHERLY WWTP EXISTING FACILITIES (cont.)
Process

Centrifuge Thickening
(WAS)
Anaerobic Digestion
Thermal Conditioning
Centrifuge Dewatenng
Dewatered Sludge
Storage

Transport to Composting
Composting


Compost Disposal


Incineration



Ash Lagoon


Landfill
Facilities/Condition

Four solid bowl centrifuges
Pre-Project 88, Contract #19
Not yet fully operational

Four primary digesters;
85-foot dia., 25.25-foot SWD
Two secondary digesters;
85-foot dia., 25.25-foot SWD
Construction date 1965

Three reactors
Installed 1974, abandoned 1980

Six solid bowl centrifuges
Operational approx. 7 years
One storage bin.
4-8 trucks @ 25 wet tons
Hrs of operation 56 hrs/wk

Extended aerated static pile system
Product removed by truck
Two existing multiple hearth units;
Two new multiple hearth units
under construction

Two lagoons
City-owned landfill
200 gpra/unit
Feed solids 1%
Thickened WAS 5£

Volume of 972,000 CF total
          4.8 MG primary
          2.4 MG secondary
200 gpm/unit
100 gpm/unit
Feed solids 3.5Z
Dewatered cake 16-18%

Volume of 400 cy/300 wet tons
Haul distance of 7 miles
roundtrip

120-200 wet tons/day
dependent on sludge and weather

Disposal through bulk sales to
public and private consumers

150 wet tons/day existing
260 wet tons/day new
Total storage capacity of
76,000 cy; Cleaned as needed

Ash landfilled on an as-needed
basis by contract operations

-------
                  2.   IDENTIFICATION OF SYSTEM ALTERNATIVES

     The current wastewater treatment facilities for the Columbus  metropolitan
area are the Jackson Pike and Southerly Wastewater Treatment Plants (WWTP)
(See Figure 1-1.)  Upgrading and expansion of one  or  both  of these facilities
is required to meet federal effluent limitations.  Thus, the following three
wastewater system alternatives have been selected to be evaluated  for
preferred  treatment.

     •  No action.
     •  Upgrade the existing facilities.
     •  Eliminate Jackson Pike,  upgrade and  expand Southerly.

     The following sections discuss these three alternatives.

2.1  NO ACTION ALTERNATIVE
     The development of a no action alternative xs consistent with EPA
guidelines for preparing an EIS.   A no-action alternative  cannot be  eliminated
during a preliminary screening.   It must be  included in a  detailed evaluation
of alternatives.  This  is  because  it serves as a baseline  when comparing  and
evaluating action alternatives.

     The no action alternative would involve normal maintenance  but no
improvement to the existing facilities.  Failure to rehabilitate and upgrade
the existing facilities will result in permit  violations.  This may result
in violations  of  water  quality standards for receiving  waters and  possible
                    i
public health  problems in the Columbus metropolitan area.

     New NPDES permit  limits have been established for  the Columbus  wastewater
treatment  plants which they must  be in compliance with by July 1,  of 1988.  The
plants are currently operating under interim limits.  The Columbus wastewater
treatment  plants, without improvements, cannot meet the new  NPDES  permit    ""
limits.  The new permits are more stringent  with respect  to  CBODc,  TSS, and
                                     F-16

-------
fecal coliform  limits.  The permits also include a limit for ammonia and a
minimum requirement for dissolved oxygen.  An inability to meet permit
requirements may  result in sanctions  by OEPA  and USEPA that could have adverse
social and economic  impacts in the facilities planning area.

2.2  UPGRADE THE EXISTING FACILITIES
     This alternative, which is consistent with current operation,  was
evaluated by the city in the facility plan.  This  alternative will be referred
to as the two-plant  alternative.  In this  alternative,  the existing treatment
plant sites will be maintained.  Each plant will be rehabilitated and expanded
as necessary to provide advanced wastewater treatment on  site  for wastewater
flows expected  through  the  year 2008.  Due  to site  limitations and existing
hydraulic constraints at Jackson Pike, the city maintains that the  wet stream
treatment capacity cannot be expanded.  However, the existing facilities can
be upgraded to provide necessary treatment to meet proposed effluent require-
ments.   Average flows in excess of 80 MGD  and peak flows in excess of 100  MGD
at Jackson Pike would be diverted  to Southerly via the Interconnector Sewer.
Figure 3-1 provides a flow schematic for the  two-plant alternative.

2.3  ELIMINATE JACKSON PIKE, UPGRADE AND EXPAND SOUTHERLY
     This alternative was evaluated and recommended by the City in the
facility plan.   Under this alternative, also called the one-plant alternative,
Jackson Pike would be phased out and all flows would be diverted to Southerly
via the Interconnector Sewer.  Expansion and rehabilitation of the  existing
facilities at Southerly would be required.   Figure  3-2  provides a flow
schematic for the one-plant alternative.
                                     F-17

-------
            SOUTHERLY SERVICE AREA
             AVG, FLOW » 66 MGD
             PEAK FLOW = 99 MGD
•=3
i
                                        JACKSON PIKE SERVICE  AREA
                                            AVG. FLOW = 88 MGD
                                           PEAK FLOW = 132 MGD
                                         INTERCONNECTOR
                                        AVG. FLOW = 8 MGD
                                       PEAK FLOW  =  32 MGD
               SOUTHERLY VVTP
             AVG.  FLOW = 74  MGD
             PEAK  FLOW « 131 MGD
         r
                                            JACKSON PIKE VWTP
                                            AVG. FLOW = 80  MGD
                                            PEAK FLOW = 100 MGD
     WEST  TRAIN
  AVG. FLOW - 37 MGD
 PEAK FLOW  -  65.5 MGD
    CENTER TRAIN
 AVG. FLOW =  37 MGD
PEAK FLOW = 65.5 MGD
                                        r
     PLANT 'A'
AVG. FLOW = 48 MGD
PEAK FLOW s 60 MGD
     PLANT 'B'
AVG. FLOW = 32 MGD
PEAK FLOW = 40 MGD
                                                                           FIGURE 2-1
                                                                           TWO-PLANT ALTERNATIVE
                                                                           FLOW

-------
SOUTHERLY SERVICE AREA
  AVG. FLOW - 66 MGD
  PEAK FLOW « 99 MGD
                        JACKSON PIKE SERVICE AREA
                           AVG. FLOW = 88 MGD
                          PEAK FLOW - 132 MGD
                             INTERCONNECTOR
                           AVG. FLOW
                          PEAK FLOW
           88 MGD
           133 MGD
                              SOUTHERLY VVTP
                            AVG. FLDV - 154 MGD
                            PEAK FLOW = 831 MGD
         VEST TRAIN
     AVG. FLOW • 44 MGD
     PEAK FLOW = 66 MGD
   CENTER TRAIN
AVG. FLOW = 44 MGD
PEAK FLDV = 66 MGD
    EAST TRAIN
AVG. FLOV e 66 MGD
PEAK FLOV » 99 MGD
                                                                FIGURE 2-2
                                                                DNE-PLANT  ALTERNATIVE
                                                                FLDV SCHEMATIC

-------
       3.  DEVELOPMENT AND EVALUATION OP SYSTEM ALTERNATIVE COMPONENTS

     This section presents the recommended process components and the
facilities required to implement the one-plant and two-plant system
alternatives.  The components which will be discussed include the following:

     •  Interconnector/Headworks
     •  Wet Stream Treatment
     •  Solids Handling and Disposal

     The Interconnector component involves options for conveyance between the
two WWTPs.  Included in the headworks are the coarse  bar  racks,  mechanically
cleaned bar screens, aerated grit chambers and pumps.   Net  stream treatment
includes primary, secondary, and post treatment.   Solids  components include
thickening,  processing, disposal, and reuse  processes.

     Secondary treatment and solids handling and disposal have been evaluated
in previous briefing papers.  Therefore,  this  briefing paper will  summarize
the recommendations of those  papers.

     The Interconnector,  headworks,  primary treatment, and post treatment are
presented for the first time in this briefing paper.   An evaluation of
available options is contained herein.    They will be discussed in greater
detail than secondary treatment and solids handling and disposal.

     Recommended  facility  sizings in this paper are based on the flows and
loads developed in Briefing Paper No.  1.   Costs are consistent with those
costs presented in Briefing Paper No. 4.

3.1  INTERCONNECTOR/HEADWORKS
     The Interconnector and headworks alternatives are being discussed
together since they directly affect one another.
                                      F-20

-------
     The 150-inch to 156-inch Interconnected Sewer  runs  in a north-south
direction between Jackson Pike and Southerly along the west side of the Scioto
River.  The south end connects to the Interconnector Pump Station.  The
Interconnector Pump Station, with a firm capacity of 60 MGD, pumps the flow
across the Scioto River to Southerly through a 48-inch force main and a
36-inch force main.

     The north end of the Interconnector Sewer is incomplete.  However,
funding has been provided  for its  completion.  The remaining segment will be
constructed along the west  and  north  side  of Jackson  Pike (Figure 1-2).  A
diversion chamber will be built connecting the  Interconnector with the
O.S.I.S.   This will allow  regulation  of flows to Jackson Pike and diversion of
flows to Southerly.

     The existing Southerly headworks are  rated at a capacity of 170 MGD.  The
headworks consist of coarse and fine screening, pumping, and aerated grit
removal.  The Jackson Pike headworks are rated at a capacity of 165 MGD.  They
consist of fine screening  and pumping.   Preliminary  treatment is provided for
flows entering Jackson Pike  through  the O.S.I.S.  at  the  Sewer Maintenance
Yard. These  preliminary  treatment facilities are rated at a capacity of
160 MGD and  provide  screening and grit removal for flows in the O.S.I.S. prior
to their arrival at Jackson  Pike.

3.1.1  One-Plant System Alternative
     Under the one-plant system alternative, the Jackson Pike plant would be
phased out  of service and  all flows tributary to  Jackson Pike would be
conveyed to Southerly via the Interconnector Sewer.   In order to convey the
Jackson Pike flows to Southerly, the south end  of the  Interconnector and the
Southerly headworks capacity must be expanded.
                                     F-21

-------
      The Interconnector  currently  conveys approximately 5 MGD  to Southerly
 from a connection at Grove City.   Under the one-plant system alternative, it
 would be required to convey an additional 132 MGD from Jackson Pike
 (Figure  2-2).  This total flow exceeds the 60 HGD capacity of  the existing
 pump station and force mains.   Alternatives for expansion which were evaluated
 by  the city  include  the  following:

      o   Option A - additional  pumping facilities and force mains
      o   Option B  - extension of the 156-inch gravity Interconnector to
         Southerly
      Option A consists of  increasing the current 60 MGD capacity to ISO MGD by
 construction of a new pumping  facility on the south side of the existing pump
 station, and by  constructing one new 48-inch and one new 36-inch force main
 parallel to the existing force mains to the  Southerly headworks.   The pump
 station expansion will include the addition of three, 30 MGD submersible
 centrifugal pumps and motors,  three mechanical bar screens, and a screenings
 conveyor system.

      Option B consists of extending the 156-inch Interconnector Sewer to the
 Southerly WWTP.  Pour 78-inch pipes would be used for the Scioto River
 crossing to avoid the construction of a low head dam.

     Under the one-plant alternative,  the  existing Southerly  headworks  would
not be able to handle the combined peak flow of 231 MGD (i.e. 99 MGD from
Southerly and 132 MGD from  Jackson Pike).

     The headworks options  are affected by the Interconnector  option selected.
The potential options available are:

     *  Option A-l - Expand existing headworks.
     •  Option B-l - Construct separate headworks  for the  Interconnector flows.
     »  Option B-2 - Construct new headworks for all flow.
                                     F-22

-------
      If Interconnected Alternative A is  selected, the flows from the Big
 Walnut Interceptor and the Interconnector would arrive at the plant at the
 same  elevation.  Therefore, the existing headworks could be expanded to handle
 all of the flow.  Expansion would include additional pumps, screens, and grit
 chambers.  This option will be known as  Option A-l.

      If Interconnector Option B is selected,  the  gravity  sewer will enter the
 Southerly headworks approximately eight  feet lower than the Big Walnut
 Interceptor.  This results in the need  for separate headworks (Option B-l) for
 the gravity Interconnector or completely new headworks (Option B-2) to handle
 the flows from both sewers.

     Option B-l consists of utilizing the existing 170 MGD headworks at
 Southerly for handling the flows  from the Big Walnut Interceptor and
 constructing new 150 MCD  headworks for handling the Interconnector flows.  The
 new Interconnector headworks will be located adjacent to  the existing
 headworks.  They will include coarse bar  racks, raw pumping,  followed by
 mechanical screening and aerated grit removal; all designed for 150 MCD.
 Mixing of the Interconnector and  Big  Walnut flows would follow aerated grit
 removal.

     Option B-2 involves  constructing completely  new headworks which include  a
 mixing chamber, coarse bar racks,  pumping,  and  aerated grit  chambers.   The
 flows from the Big Walnut Interceptor and the Interconnector would  combine in
 a mixing chamber and be conveyed  through  manually cleaned bar racks.   The
combined flow will then enter a wet well to be  pumped to  mechanical bar
screens followed by aerated grit chambers.  The new headworks  will  be  designed
 for a peak process flow of 231 MGD.  The combined costs for  the
 Interconnector/headworks alternatives are presented in Table 3-1.
                                     F-23

-------
                TABLE 3-1.   INTERCONNECTOR/HEADWORKS  ALTERNATIVE
                                   PRESENT WORTH COSTS
 Interconnector
 Headworks
 TOTAL
Option A/A-1
$14,058,000
$17,006,000
$31,064,000
Option B/B-1
 $4,432,000
$25,847,000
$30,279,000
Option B/B-2
 $4,432,000
$30,496,000
$34,928,000
      Option B/B-1  exhibits  the  lowest present worth cost.  However, practically
 speaking the present  worth  of A/A-1 is equal  to B/B-1.  Reliability, implemen-
 tability,  and ease of operation must also  be  considered  when selecting the best
 alternative.

      The gravity sewer options  (B/B-1  and  B/B-2) are more reliable than the
 force main option  (A/A-1) because there is less chance that the gravity sewer
 will rupture.  Also,  gravity  failure normally results in infiltration  to the
 conduit;  while force  mains  exfiltrate  to the  environment.  In addition, the
 gravity  sewer does not rely on  the  operation  of a  pumping facility to  function
 properly.  Therefore,  it would  be easier to operate and maintain.  However,
 separate headworks are needed for option B/B-1  which would require additional
 operation and  maintenance'time.

      The force mains,  on the  other  hand, may not require as deep of an
 excavation as  the  gravity sewer; and therefore, they would be easier to
 implement.

      Based on  the  cost and  reliability of  Option B/B-1 (gravity), it is the
 recommended  Interconnector/headworks  option for the one-plant alternative.

 3.1.2 Two-Plant System Alternative
      The two-plant alternative  does not require any expansion of the
 Interconnector or any additional headworks  at  the Southerly  WWTP.  New
 headworks  are  required at the Jackson  Pike WWTP.   The total present worth cost
of the headworks  is $14,170,000.
                                      F-24

-------
3.2  WET STREAM TREATMENT
     Briefing Paper No. 3 - Process Selection presented a detailed evaluation
of secondary treatment alternatives and provided recommendations for secondary
treatment  facilities  under each  system alternative.  In light of these
recommendations,  this section will summarize  the  facilities required under
each system alternative for the  following processes:

     •  Primary treatment
     •  Secondary treatment
     •  Post treatment

     Secondary treatment recommendations will be consistent with the
conclusion of the process selection breifing paper.   Primary treatment and
post treatment are being presented here for the first time.

3.2.1  One-Plant System Alternative
     The one-plant alternative requires upgrading and expansion of the
Southerly plant to handle  all  flows from the Jackson Pike and Southerly
service areas.   It was concluded in the process selection briefing paper that
in addition to  the two existing  trains,  one additional wet  stream  treatment
train would be required at the Southerly WWTP.  Figure  2-2  shows how the flow
will be distributed between the three trains.

3.2.1.1  Primary Treatment
     The Southerly WWTP currently has primary treatment consisting of
preaeration and primary settling.  Preaeration of wastewater prior  to primary
settling is done for odor control,  to prevent  septicity,  and to improve
subsequent settling.   Little  or  no  BOD reduction occurs  in  the preaeration
tanks.   However,  preaeration does increase  the  removal  of BOD and  suspended
solids in the primary tanks.  Primary settling  should remove 25 to 40 percent
of the influent BOD and 50 to 70 percent of the suspended solids.
                                     F-25

-------
      The Southerly WWTP currently has four preaeration tanks  in each of the
 Center and West Trains.   These  preaeration  tanks are adequate for providing
 treatment for the flows in these two trains under the one-plant alternative.
 However, an additional East Train is required  under  the  one-plant alternative.
 As  presented in Figure  2-2,  this  new East Train will provide treatment for an
 average  flow of 66 MGD and a peak process flow of 99 MGD.  Assuming a
 detention time of 30  minutes at average  flow,  four additional preaeration
 tanks  are  required in the new East Train.   These  new tanks are the  same size
 as  the tanks in the existing trains.

     The Southerly WWTP has four primary settling  tanks  in each of the
 existing Center  and West  Trains.  These tanks have adequate primary settling
 capacity for  the average  and peak flows  allocated to these trains under the
 one-plant  alternative.  However, additional tanks  are required for the new
 East Train.  Assuming a surface loading rate of 1000 gallons per day per
 square foot at average flow as recommended  by Ten States Standards,  66,000
 square feet  of  surface area  is  required.   This surface area can be provided by
 adding four new  150-foot  diameter circular  clarifiers.

 3.2.1,2  Secondary Treatment
     The form of secondary treatment currently provided at  the Southerly WWTP
 is conventional single-stage activated sludge.   This  process  includes
 rectangular aeration tanks followed by rectangular secondary clarifiers.   The
 plant was designed based on NPDES permit  limits of 30 rag/1 for CBOO^ and TSS.
The CBODc and TSS limits have become more stringent and an ammonia standard
has been added to both permits.  As a result of these changes, the plants  are
not capable of treating design flows to the more stringent permit limits.

     Through the course of the facilities planning  process  for the Columbus
wastewater treatment  facilities,  other alternatives to the conventional
activated sludge process have been proposed. The 1979 EIS recommended a
trickling filter process followed by activated sludge for the Jackson Pike
plant.   The Facilities Plan Update (FPU)  and Revised  Facilities Plan Update
                                     F-26

-------
 recommended a semi-aerobic treatment process.  The Process Selection Briefing
 Paper  evaluated  the  semi-aerobic,  trickling  filter/activated  sludge,  and
 single-stage  activated  sludge  processes and recommended  utilizing  the semi-
 aerobic  process  at both plants.

     The semi-aerobic process  is  a modified  form of the  activated  sludge
 process.  The process consists of  a non-aerated  reaction zone ahead of an
 aerated  activated sludge zone.  The non-aerated  zone may be anoxic (nitrates
 are  present), anaerobic  (no oxygen or nitrates present),  or a  combination of
 both.  The  purpose of the anaerobic zone  is  to control bulking sludge.  The
 anaerobic zone may change to anoxic depending on the level and concentration
 of nitrates in the wastewater.   In the  anoxic zone denitrification occurs.
 Denitrification  is a process by which nitrates are converted into  nitrogen
 gas.

     The  only physical differences between the serai-aerobic process and the
 conventional activated sludge process is an internal mixed liquor  recycle loop
 and  the  addition of baffles to compartmentalize  the  aeration  tanks.  The
 baffles are incorporated into the  design to prevent back-mixing from the
 aerated  zone  to  the anaerobic zone.  The internal recycle loop is used to
 bring nitrates back to the anoxic zone and thus cause denitrification to
 occur.

     Under  the one-plant  scenario, the Southerly WWTP would be upgraded to
 handle all flows from the Columbus service area.   The Southerly WWTP currently
 has a West  Train and a Center Train.  The West Train has six aeration  tanks
 which are capable of treating an average design flow of 44 MGD.   The Center
 Train has four aeration  tanks which are capable  of treating an average design
 flow of 29 MGD.   These flows are based on  the design  parameters of  the semi-
 aerobic  process.

     The 2008 average design flow for the one-plant alternative is 154 MGD.
This will require an additional aeration basin capacity of SI  MGD.   This can
                                     F-27

-------
 be provided by adding two tanks to the  existing  Center Train  and by construct-
 ing a new East Train  consisting of nine aeration basins.   Figure 2-2 shows how
 the flow is allocated to each train.

      The existing aeration basins will require some modifications to allow
 them to be  operated in the semi-aerobic mode.  Two baffles must be installed
 in the first bay of each  of  the ten existing tanks and an internal mixed
 liquor recycle loop must  also be added to each tank.

      The existing rectangular clarifiers will be replaced by six new circular
 clarifiers.  New circular clarifiers were recommended for the Southerly WWTP
 due  to the  high mixed  liquor concentration which must be maintained for
 nitrification  and the difficulty associated with settling a nitrified  sludge.

      In addition to the six new secondary clarifiers for the existing Center
 and West Trains, four new circular clarifiers are required for secondary
 settling in the new East Train.

 3.2.1.3   Post  Treatment
     The  current post treatment provided at the Southerly WWTP is
 chlorination.  The  Southerly  WWTP has  an earthen contact  basin with internal
 baffles.  This  basin  was designed  as a temporary structure until a decision on
 tertiary  treatment could  be finalized.  Since new regulations require
disinfection,  Southerly needs permanent facilities.

     Southerly would*require  two new chlorine contact tanks sized at 81 feet
by 200  feet by  10 feet side water depth.   Post  aeration will take place in the
 final pass of  the tanks to maintain a dissolved oxygen in the effluent of 7.0
rag/1.

     Table 3-4 summarizes the wet stream facilities required under the one-
plant alternative and the associated costs.
                                     F-28

-------
                                  TABLE 3-4
                             WET  STREAM TREATMENT
                             (Southerly One-Plant)
                        Facilities and Estimated Costs
PREAERATION                                                       $ 5,905,000
     Eight existing tanks;  112.7  ft x 26  ft x  15.5  ft SWD
     Four new tanks;  112.7  ft x 25.5 ft x 15.5  ft SWD
PRIMARY SETTLING                                                   13,590,000
     Four existing tanksj 80 ft x 165 ft x 10 ft SWD
     Four existing tanks; 100 ft x 170 ft x 10 ft SWD
     Four existing tanks; 150 ft dia. x 15 ft SWD


AERATION                                                          46,533,000
    IP JU Vll
     Ten existing tanks; 26 ft x 900 ft x 15 ft SWD
     Eleven new tanks; 26 ft x 900 ft x 15 ft SWD
FINAL SETTLING                                                    35,462,000
     Demolish existing tanks
     Ten new tanks; 200 ft dia. x 15 ft SWD


CHLORINATION/POST AERATION                                         3,000,000
     Two new tanks; 81 ft x 200 ft x 10 ft SWD
     including mixers, chlorinators, and evaporators.
     Post Aeration takes place in the final pass of
     the chlorine contact tanks.
                                           TOTAL CAPITAL COSTS  $104,490,000

                                           ANNUAL O&M COSTS        5,224,000

                                           TOTAL PRESENT WORTH  $144,504,000
                                      F-29

-------
 3.2.2   Two-Plant  System Alternative
     The  two plant alternative  requires upgrading of both plants and minor
 expansion of  the  Southerly plant.  No additional  wet stream treatment trains
 are  required  at either plant.  Flows are distributed to each of the plants as
 shown  in  Figure 2-1.

 3.2.2.1   Primary  Treatment
     Under the two-plant alternative, the Southerly WWTP has adequate primary
 settling  and  preaeration capacity.  However, upgrading of the existing
 facilities is required.

     The Jackson  Pike WWTP currently has two preaeration tanks in each of the
 two  trains, Plant A and Plant B.  The two tanks in Plant A provide 1.05  MG of
 total  volume.  The  two tanks  in Plant B provide 0.66 MG of total volume.
These  tanks are capable of treating an average flow of 80 MGD.  The projected
2008 average  flow for Jackson Pike is 88 MGD.  Therefore, due to  limited
preaeration capacity,  8 MGD will be sent to Southerly for treatment.

     The Jackson Pike WWTP has  four primary  settling tanks in each existing
train,  Plant A and Plant  B.   These  tanks are  also  limited to  an average  flow
capacity of 80 MGD.

3.2.2.2  Secondary Treatment
     The semi-aerobic process is recommended at both plants under the
two-plant alternative.
     Under the two-plant option the Southerly WWTP will be required to treat
an average flow of 74 MGD and a  peak  process  flow of  131  MGD.   These  flows
include 8 MGD under average conditions and 32 MGD under peak conditions being
diverted from Jackson Pike.   The Jackson Pike WWTP is limited to an average
flow of 80 MGD and a  peak process flow of 100 MGD.
                                     F-30

-------
      In accordance  with Che  evaluation presented  in  the  Process Selection
 Briefing Paper, only two additional aeration basins are  required in the Center
 Train at Southerly  under the  two-plant alternative.  Then each train would
 have  six basins and could treat an average flow of 37 MGD and a peak process
 flow  of 65.5  MGD (see Figure 2-1).

      The existing rectangular clarifiers should be demolished and replaced
 with  six new  circular clarifiers.

      The Jackson Pike WWTP  is hydraulic ally limited  to a peak process flow of
 100 MGD.  Any peak flows in excess of  this  flow would be diverted to the
 Southerly WWTP  under  a  two-plant  alternative.  An average flow of 88 MGD was
 projected for the 2008 design year.  However,  in evaluating the existing
 facilities, the preaeration and primary settling facilities were found to be
 limited to 80 MGD average flow.

     At an average  flow of 80 MGD and  a peak process flow of 100 MGD, the
existing aeration facilties at Jackson Pike have adequate capacity.   However,
extensive rehabilitation and the addition of baffles and an internal mixed
 liquor recycle system would be required to operate in the semi-aerobic mode.

     The final clarifiers,  on the other hand,  are not sufficient to treat a peak
process flow of 100 MGD.  Two additional rectangular clarifiers would be necessary.

3.2.2.3  Post Treatment
     Under the two-plant alternative,   the Jackson Pike and Southerly WWTPs
would require new chlorine contact tanks.  As  discussed in the previous
section,  Southerly has a temporary contact basin.   Jackson Pike  performs
disinfection by injection of  chlorine into the discharge pipeline.   Under the
two-plant alternative, Southerly would need two new  tanks sized at 150 feet by
64 feet by  10  feet  side  water  depth.  Jackson Pike would  need  two new tanks
sized at 100 feet by 70 feet by 10 feet side water depth.  Post  aeration would
take place  in the final pass of the tanks.
                                     F-31

-------
     Tables 3-5 and 3-6 present a summary of the required wet stream treatment
 facilities and the associated costs for the Southerly WWTP and the Jackson
 Pike WWTP,  respectively.

 3.3  SOLIDS HANDLING AND DISPOSAL
     This section summarizes the recommended solids handling and disposal
 components for the one-plant system alternative and the two-plant system
 alternative.  These recommendations were  identified  in the solids handling
 briefing paper after a thorough evaluation of solids  management options for
 each plant.

 3.3.1  One-Plant System Alternative
     The solids handling and disposal scheme identified for Southerly under
 the one-plant system alternative is shown  in Figure 3-1.  This handling and
disposal scheme includes the following sludge processes:

     •  Gravity thickening of primary sludge
     *  Centrifuge thickening of waste-activated sludge
     •  Thickened  sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Centrifuge dewatering
     •  Composting
     •  Incineration
     •  Land Application

     Dewatered sludge would be  disposed of as follows:

     •  25  percent would be composted and distributed as a soil conditioner.
        Sludge sent to compost  would not  go through the digestion process.
     •  25  percent would be land applied  as a fertilizer to  agricultural
        acreage within a reasonable distance from the plant.
     •   50  percent would be incinerated,  and the ash product would be landfilled.
                                     F-32

-------
                                  TABLE 3-5
                             WET STREAM TREATMENT
                            (Southerly Two-Plant)
                        Facilities and Estimated Costs
PREAERAT10N                                                      $  1,533,000
     Eight existing tanks; 112.7 ft x 26 ft x 15.5 ft SWD


PRIMARY SETTLING                                                   4,717,000
     Four existing tanks; 80 ft x 165 ft x 10 ft SWD
     Four existing tanks; 100 ft x 170 ft x 10 ft SWD


AERATION                                                          12,284,000
     Ten existing tanks; 26 ft x 900 ft x 15 ft SWD
     Two new tanks; 26 ft x 900 ft x 15 ft SWD


FINAL SETTLING                                                    20,521,000
     Demolish existing tanks
     Six new tanks; 190 ft dia. x 15 ft SWD


CHLORINATION/POST AERATION                                         1,800,000
     Two new tanks; 150 ft x 64 ft x 10 ft SWD
     including mixers, chlorinators, and evaporators.
     Post aeration takes place in the final pass
     of the chlorine contact tanks.


                                           TOTAL CAPITAL COSTS   $40,855,000

                                           ANNUAL O&M COSTS        2,382,000

                                           TOTAL PRESENT WORTH   $61,562,000
                                     F-33

-------
                                   TABLE  3-6
                              WET STREAM  TREATMENT
                            (Jackson  Pike Two-Plane)
                         Facilities and Estimated  Costs
PREAERATION                                                       $  3,750,000
     Two existing  tanks;  180  ft x  26  ft x  15  ft  SWD
     Two existing  tanks;  113  ft x  26  ft x  15  ft  SWD
     Building renovation
PRIMARY SETTLING                                                    7,372,000
     Eight existing tanks;  150 ft x 80  ft x  10  ft SWD
     Control building renovation
AERATION                                                           22,502,000
     Twelve existing tanks; 900 ft x 26 ft x 15 ft SWD
     Control building renovation
FINAL SETTLING                                                     8,691,000
     Twelve existing tanks; 153 ft x 60 ft x 12.5 ft SWD
     Two new tanks; 153 ft x 60 ft x 12.5 ft SWD


CHLORINATION/POST AERATION                                         1,300,000
     Two new tanks; 100 ft x 70 ft x 10 ft SWD
     including mixers, chlorinators, and evaporators.
     Post aeration takes place in the final pass of
     the chlorine contact tanks.
                                           TOTAL CAPITAL COSTS   $43,615,000

                                           ANNUAL O&M COSTS        2,648,000

                                           TOTAL PRESENT WORTH   $66,722,000
                                      F-34

-------
PRELIMINARY
PRIMARY
AERATION
SECONDARY
RAW '"
INFLUENT

c-Hinc.

n i uunr

ur iv,H

1 1LJ1N



uv_«p

cir iOft

HUN
EFFLUENT

                              GRAVITY
                              THICKENING
                              PS
                               THICKENED
                               SLUDGE
                               BLEND/STORAGE




CENTRIFUGE
DEVATERING


ANAEROBIC
DIGESTION
                                      CENTRIFUGE
                                      THICKENING
                                         WAS
         INCINERATION
                               DEVATERED
                               SLUDGE
                               STORAGE
     TO
  LANDFILL
                        TO
                        LAND
                        APPLICATION
                TO
             COMPOSTING
                      FIGURE 3-1
                      SOUTHERLY
                      PROPOSED  SLUDGE
                      MANAGEMENT SCHEMATIC

-------
     This alternative provides a  great deal of flexibility for disposal.  It
offers continuation of the existing incineration and composting processes at
Southerly and  introduces  land application as a disposal process.  Table 3-7
presents the required sizing and  associated  costs of the sludge management
facilities  for  the one-plant system alternative.

3.3.2  Two Plant System Alternative
     The recommended solids handling and disposal scheme for Southerly under a
two-plant system alternative is the1 same as that for a one-plant system
alternative.  This  scheme was previously described  in Figure 3-1.  Table 3-8
presents the sizing and  costs of  the required  sludge management facilities for
Southerly under a two-plant system alternative.

     The recommended solids handling and disposal scheme for Jackson Pike
under a two-plant alternative is  presented  in Figure 3-2.  This alternative
includes the following sludge processes:

     *  Gravity thickening of primary  sludge
     •  Centrifuge  thickening of  waste-activated sludge
     •  Thickened sludge storage  and blending
     •  Stabilization by anaerobic digestion
     *  Centrifuge  dewatering
     •  Incineration
     •  Land Application

     Dewatered sludge would be  disposed of  as  follows:

     •  50 percent  would be incinerated and  the ash product landfilled
     •  SO percent  would be land  appplied as a fertilizer to agricultural
        acreage within a reasonable distance from the plant.
                                     F-36

-------
                                  TABLE  3-7
                    SOUTHERLY SLUDGE MANAGEMENT COMPONENTS
                         One-Plant System Alternative
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water  Pumping             $5,070,000
     Four (4) existing; 45-foot dia. x  17-foot SWD
     Two (2) new; 85-foot dia. x 10-foot SWD

Centrifuge Thickening WAS                                      5,600,000
     Four (4) existing; 250 gpra, 1250 Ib/hr
     Four (4) new; 250 gpra, 1250 Ib/hr

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                           11,460,000
     Six (6) existing; 85-foot dia. x 25.25-foot SWD
     Four (4) new; 85-foot dia. x 25.25-foot SWD

Centrifuge Dewatering                                         21,040,000
     Six (6) existing; 1000 Ib/hr
     Nine (9) new; 1000 Ib/hr

Dewatered Sludge Storage
     One (1) new; 400 cy plus material handling                1,300,000

Composting
     Existing Facilities; 120 wet ton/day @ 20% solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids
     Rehabilitate existing                                     1,300,000

Landfill
     Contract operations included with O&M
                    \
Land Application
     Contract operations included with O&M

                         Capital Cost                        $45,770,000

                         Annual Operation and                  6,230,000
                           Maintenance Cost

                         Present Worth (One-Plant)           $90,710,000
                                     F-37

-------
                                  TABLE 3-8
                     SOUTHERLY  SLUDGE MANAGEMENT COMPONENTS
                         Two-Plant System Alternative
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water  Pumping              $2,520,000
     Four (4) existing; 45-foot dia. x  17-foot SWD

Centrifuge Thickening WAS                                       2,000,000
     Four (4) existing; 250 gpm, 1250 Ib/hr
     One (1) new; 250 gpm, 1250 Ib/hr

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                             4,280,000
     Six (6) existing; 85-foot dia. x 25.25-foot SWD

Centrifuge Dewatering                                           5,120,000
     Six (6) existing; 1000 Ib/hr
     Two (2) new; 1000 Ib/hr

Dewatered Sludge Storage                                        1,300,000
     One (1) new; 400 cy plus material handling

Composting
     Existing Facilities; 120 wet ton/day @ 20% solids

Incineration
     Two (2) new; 8 hearth, 260 wet ton/day @ 20% solids

Landfill
     Contract operations included with O&M

Land Application                                                  —
     Contract operations included with O&M
                    \
                         Capital Cost                        $15,220,000

                         Annual Operation and                  3,340,000
                           Maintenance Cost

                         Present Worth (Two-Plant)           $39,680,000
                                      F-38

-------
            PRELIMINARY
 PRIMARY
AERATION
SECONDARY
RAW '*
INFLUENT

C.M i ric.

n ^ ov.nr

^ir *WM

1 iUlt



v*-nr

^.j.r ion

1 1UI1
EFFLUENT

                                           GRAVITY
                                           THICKENING
                                           PS
                                               CENTRIFUGE
                                               THICKENING
                                               WAS


                                               THICKENED
                                               SLUDGE
                                               BLEND/STDRAGE
7
                 INCINERATION
CENTRIFUGE
DEVATERING
                                                   DIGESTED
                                                SLUDGE HOLDING
          ANAEROBIC
          DIGESTION
                      I

                      TO
                   LANDFILL
  TO LAND
APPLICATION
                     FIGURE 3-8
                     JACKSON PIKE
                     PROPOSED SLUDGE
                     MANAGEMENT  SCHEMATIC

-------
     The difference between this alternative and the alternative recommended
for Southerly is that the Jackson Pike alternative does not include
composting.  The recommended 50:50 disposal ratio between land application and
incineration is approximately consistent with current Jackson Pike disposal
practices.   Table 3-9 provides a list of the required facilities  for Jackson
Pike and their associated costs.
                                     F-40

-------
                                  TABLE 3-9
                   JACKSON PIKE SLUDGE MANAGEMENT COMPONENTS
                         Two-Plant System Alternative
                        Facilities and Estimated Costs
Gravity Thickening PS plus Dilution Water Pumping              $6,070,000
     Three  (3) new; 65-foot dia. x 10-foot SWD

Centrifuge  Thickening WAS                                       4,500,000
     Two (2) existing; 500 gpm
     One (1) new; 500 gpm

Thickened Sludge Storage/Blend
     Existing Facilities Reused

Anaerobic Digestion                                             9,170,000
     Six (6) existing; 85-foot dia. x 23.5-foot SWD
     Four (4) existing; 70-foot dia. x 27.5-foot SWD

Centrifuge  Dewatering                                             490,000
     Six (6) existing; 1200 Ib/hr

Incineration
     Two (2) existing, 7 hearth, 200 wet ton/day @ 20% solids   3,600,000

Landfill
     Contract operations included with O&M

Land Application
     Contract operations included with O&M                         —

                         Capital Cost                         $23,830,000

                         Annual Operation and                   3,070,000
                           Maintenance Cost

                         Present Worth (Two-Plant)            $49,930,000
                                      F-41

-------
                     4.    EVALUATION OF  SYSTEM ALTERNATIVES

      This  section evaluates the one-plant and two-plant system alternatives
 based on cost,  reliability, fexibility, implementability, and operational
 ease.

      Table 4-1  presents  the capital, annual O&M, and total present worth costs
 for  the  one-plant and two-plant system  alternatives.

                     TABLE 4-1.  SYSTEM ALTERNATIVE COSTS
                                                                 Total
                                   Capital       Annual O&M   Present Worth
One-Plant  [Southerly]              268,711,000   16,849,000   436,911,000
Two-Plant  {So.  and Jackson Pike]   217,860,000   19,078,000   407,800,000
Difference from One-Plant          -50,851,000   +2,229,000   -29,111,000
Percent  Difference                 -23           +13          -7

     Details on the development of the  costs in Table 4-1 are presented in
Briefing Paper  No. 4 - Capital and O&M Costs.

     The two-plant system alternative exhibits a total present worth cost
approximately 7 percent lower than the one-plant alternative.

     Both the one-plant and two-plant alternatives are equal with respect to
their reliability in meeting final  effluent  limits.  However,  the  two-plant
would be more reliable with respect to  shock loads.  Under the one-plant
alternative,  a plant upset at  Southerly could result in a significant loss of
biological treatment capacity and may cause  a serious water quality problem.
However, if the shock and/or toxic load can only reach one of the  two plants,
the impact may not be as severe.

     The two-plant alternative is judged more flexible than the one-plant
alternative.   With both  facilities  operational,  the  city  would have  more
flexibility to adapt to increased future flow,  to meet more stringent effluent
                                     F-42

-------
 limits,  and  to address combined sewer overflows.  The two-plant alternative
 would  leave  more  land available at Southerly for expansion.  The two-plant
 alternative  would improve and  upgrade Jackson  Pike  to provide a solid 100 MGD
 treatment capacity.  The two-plant alternative  would allow for future
 expansion of the  Interconnector system to divert more flow to Southerly while
 optimizing the use of the Jakcson Pike facility.

     The two-plant alternative would be easier  to implement since the majority
 of the facilities already exist.   Most  of the construction would consist of
 rehabilitation of existing facilities.   No expansion of  the conveyance system
 between the  plants is required under this alternative.

     The one-plant alternative would be easier  to operate and maintain since
 all facilities would be consolidated at one location.

     A recommendation on  a system alternative cannot be made based solely on
 this technical evaluation.  Environmental  impacts  must  be considered  prior to
making a recommendation.
                                     F-43

-------
         APPENDIX G

   GRAPHS OF STORE! DATA
  FOR DO, BOD, AND AMMONIA
   FROM 1971-1986 AT SIX
STATIONS ON THE SCIOTO RIVER
 BETWEEN JACKSON PIKE WWTP
   AND CIRCLKVILLE, OHIO

-------
39 55 «*.» 993 M 3S.t  a
SCIOTO R. AT COUffVUS - FRAHC RD,
39949 OHIO            FRAMCUN
OHIO RIUER              951091
SCIOTO RIUER
Z10HIO   •S060M1
                  DEPTH    t
 INDEX 1081500 M77M  13190
 HILES  953.M 624 93 1Z7.74
                                                                                           STQRET
         (RR U7.74)
                   899
PARAflETEB
 PO      PROBE
RC/L
NOIS
7H4
AUE
9.4
 WAX
16.4
HIM
9 3
BEG-DATE
71/Cl/M
                                                                                                     END-DATE
                   Slops of B»gr»»*lon  lin« »
                        > 67  UniU p«r V»»r.
            ie
                  1971        1973        1975        1977        1979        1981        1983        1985


                        1972        1974        1976        1979        1980        1988        1984        1986


                                                          1971-1986
                                                                                                            Station 600870
                                                                                                               RM 127.74

-------
             39 55 99.9 983 M 35.8  S
             SCIOTO R. AT CQLUMUS -  FRANC  RD.
             39949 OHIO            FRANKLIN
             OHIO RIVER               051991
             SCIOTO RIVER
             210HIO   95969991
                                DEPTH    •
              INDEX 1931SM  997789  13199
              KIIS.S  953.89  684.93 187.74
                                                                                                         5TORCT
               (Rfl 127.741
              /TVPft/AT!IMT/STREAR
                                 319
      PARAMETER
      UD      5 WV
NO/L
NOBS
596
AVE
4.7
 I1AX
24.9
DIN
e 6
BEG-DATE
71/91/94
END-DATE
85/97/19
Slop* of R>gr«»»ion Una
                                                              -9 IS
O
 i
                         19
                                1971         1973         1975         1977         1979         1981         1983         1985


                                      1978         1974         1976         1078         1989         1988         1984


                                                                        1971-1985
                                                                                                                          Station 600870
                                                                                                                             RM 127 74

-------
            39 55 M.t K3 •• 3S.0  8
            SCIOTO R. AT COlimUS - FRANK  RD.
            39049 OHIO             FRANKLIN
            OHIO RIUER               «S1«91
            SCIOTO RIVER
            ElOhIO   •GiCtMl
                               DEPTH    •
             INDEX l«aiS««  M772*  13: M
             MILES  953.M  684.93 ie?.74
                                                                                                        STORET Sy*i«M
 (RN 137.74)
/TVPfl/ftftBNT/STREflfl
                                      PARAHETER
                                61* HK3+HH4-  N TOTAL
            nc/L
hOK
£05
  AUE
B.4B3
  BftX
3 8M
IEG-DATE
7i/ei/e<
Offi-DATE
BS/tS/27
O
 i
                              1B7I        1973        1975        1977        1979         1981        1983        1985


                                    1978        1974        1976        1978        198»       1982        1984        1986


                                                                       1971-1986
                                                                                                                          Station 600870
                                                                                                                             RM 127.74

-------
n
 i
             39 58 51.9 9*3 91 97.9  E
             SCIOTO R. AT couumus - 1-279 s.
             39049 OHIO             FRANKLIN
             OHIO  RIVER               951991
             SCIOTO R1WER
             210MIO   95969991
                               DEPTH    9
              IMDEX l»ai5M  M77E»  13199
              HILCS  953. N  63-4.93 124.49
                                                                                                        STORTT
        (Rfl 124.49)
        /TVPA/Bf19HT/STREflfl
                                299
PARMCTER
 DO      PROBE
BC/L
NOBS
78S
AWE
8.4
17.2
BIN  BEG-DATE   END-DATE
9.3  7l/ei/94   86/95/S7
                         29
                                Slop* of R»ar»»ito> li»a  •     9 15  Unit* per V»«r.
                         15
                         19
                               1971        1973        1975        1977        1979        1981         1983         198S


                                     1972        1974        197(        1978        1989        1982         1984        1986


                                                                       1971-1986
                                                                                                                         Station 600880
                                                                                                                            RM  124  4

-------
              39 Si 51. • M3 tl t7.t  2
              SCIOTO R. AT COLUHJUS - 1-Z79 S.
                                                                                                        STORCT Sy*t«a
39*49 OHIO
OHIO RIWER
SCIOTO RIUER
aiomo
INDEX
BILES
        9S3.8e
                                    FRANKLIN
                                      9S1091
                                PO»TH    t
                             M?78«  1319*
                             624.93 1£4.4«
                                 (Rfl 124.4t)
                                               /TVPA/AK1NT/STSEW1
                                 31*
                         PARAMETER
                         100      S DAV
                                            Bfi/t
HOBS
683
6.7
 rwx
39.e
ICG-DATE
71/01/04
END-DATE
85/«7/19
                                 Slop* of R»gr«»»ien Lln« «    -9 33  Unit» p»r V»«r.
C5
 I
                          ie
                                       1972         1974         1976         1978        1989         1982        1984


                                                                        1971-198S
                                                                                                                          Station  600880
                                                                                                                             RM 124.4

-------
39 52 51.t 993 91 97.9  8
SCIOTO R. AT COLUnUJS - I-270 S.
39049 OHIO             FRAHKLIN
OHIO RIVCR               05)091
SCIOTO 8IUER
at OHIO   0s0t00ei
                   DEPTH    0
 INDEX 1021500  007720  13190
 RILES  953.80  £24.93 124.40
                                                                                            STORTT SysU*
(Rfl 124.40)
                          PARIMETER
                    610  NH3>NH4-  H TOTAL     DC/l
                        NOBS
                        718
  AUE
2 481
£3 500
  diH  BEC-DATE   END-DATE
0.000  71/01/04   86/05/27
            30
                                                 -C.31  Ui>ii» p«r V«»r
            20
            10
                  1971        1973        197S        1977        1979        1981        1983        1985


                        1972        1974        1976        1978        1980        1982        1984        1986


                                                           1971-1986
                                                                                                              Station  600880
                                                                                                                  RM

-------
39 49 57.* 013 M 3*.«  I
SC10TO R. AT SHADEUIUE - S.fi. 665
39*49 OHIO            FRAHKUM
OHIO RIUER              951091
SCIOTO RIUER
Z10HIO   »5e6*Ml
                   DEPTH    •
 INDEX 1W1SM  M7720  1319*
 MILES  953 8»  6S4.93 119.9*
                                                IRK 119.9*)
                                      PMARETER
                                       DO     PKOK
                                                         NOBS
                                                         773
7.7
 PIAX
16 6
                                                                                                   STORET
                   e e
BEG-DATE
71/«1/64
                                   END-DATE
                                Slop* ef R»flr««»loiL tl«« *
                                                 8.13  UnlU p»r
                         IS
o
 I
                                                                                                                             I
                                      1978
                                                                                                    1982
                                                                                                    1984
                                                                                                                        Station  600810
                                                                                                                           RM 119.9

-------
39 49 57.t 083 00 30.0 2
SCIOTO R. AT SHMEWILU -  S.R. £fi5
                                                                                                   STORET
3»»49 OHIO
OHIO RIVER
SCIOTO RIUER
210HIO
 INDEX 10Z1SM
 H1LES  953 B0
                                   FRANKLIN
                                     051091
                               DEPTH    6
                            00772*  13! 90
                            624.93 119 90
                                                (Rfl 119.90)
                                310
                         PMM1CTER
                         BOO      5 DAV
BC/L
             NOBS
             70S
6.6
 ri«x
3S 0
I1IN  BEC-DATE
1.0  71/01/04
EN&-DATE
85/07/19
O
 t
00
                         40
                                Slop* of  R«gr«»«to» Li»« •    -0.40  limit* p»r V«»r
                         30
                         19
                                     1972
                                                                                  1981         1983


                                                                            1980        1983         1984
                                                                                                                       1985
                                                                                                                          Station  600810
                                                                                                                              RM 119.9

-------
39 49 57.9 983 09 39.9  S
SCIOTO R. AT SHADCVILIE - S.R. 665  (RR 119.99)
39949 OHIO            FRAWrUN
OHIO RIUCR              951091
SCIOTO RIVER
eiOHIO   05960001
                  DEPTH    0
 INDEX 1921500 907729  13199
 RILES  953.89 G24.93 119.99

                         PARARETER
                   619 NH3+NH4-  N TOTAL
                                                                                                   STORET
                                                                     NOIS
                                                                     687
           AUE
         2.293
21 079
  HIM
0.ee»
KC-OATE
71/91/94
END-tMTE
85/11/97
                        39
                               Slop* of R«gr«»»on I in* •
Unit* p»r  V»ir
O
 l
                        19
                                                                                                                         Station 600810
                                                                                                                            RM  119.9

-------
           39 46 87.• «S3 M 27.9  2
           SCIOTO R. Mt COMMERCIAL POINT - S.ft. ?62
           39189 OHIO            PICKAUAV
           OHIO RIVER              051*91

           flOHlO "eSWWei                 /TVPA/WttNT/STREAB
            INDEX jeaiso «»T?e«  i3is»
            nats  953.8* 6Z4.n us.si
31*   tOl
5 5AV
                                                       nc/i
                                                                   NOBS
7 a
                                         HftX
                                        35.4
                                                                                                    STORET Sy»U*
BIN  BEC-DATE   EMD-DftTE
14"
                              5Up« of R*cr«»iioi> U»« •    -t 48  UniU gar  V»»r.
i
t-1
O
                                                                                                                     Station  600900
                                                                                                                        Rn  115.31

-------
o
 I
           39 4€ e?.t *83 M87.9  8
           SCIOTO R. MR COfflCRCIAl POINT  - S.R. 768
                                                                                                      STORTT
39129 OHIO
OHIO RIVER
SCIOTO RIWER
 INDEX
        9S3.8t
                                  PICKAUftY
                                    tsiesi
                              DEPTH    •
                           «er7e<  1319*
                           624.83 115.31
                                            /TYPA/ANWT /STREAM
                               299
                         PftRAflETER
                          DO      PROBE
MC/L
NOBS
795
? 5
 RAX
IS.8
IN  BEG-DATE   END-DATE
 4  71/01/04   8fi/e5/27
                               Stop*  of R*ar»»»l»n tt»» *
                                                 0.13  UniU 9*r V««r.
                       IS
                       II
                             1971
                                   1972
                                          1975


                                    1974        1976
                    1979        1981        1983        1985


               1970        1988        IS82        1984        1986


              1971-1986
                                                                                                                       Station 600900
                                                                                                                          RM  115.31

-------
39 46 27.« 0*3 M 27.»  Z
SC10TO R. HR COBtERCIAl  POINT - S R. 768
39129 OHIO            PICKAUAV
OHIO RIVER              051*91
SCIOTO RIDER
21 OHIO   0S060M1
                   DEPTH   •
 INDEX 102150*  09772*  131 90
 RILES  953.80  £84.93 115.31
                                                                                           STORET
              /TVPA/ARIKT/STREAfl
      PARAMETER
61ft NH3**M-  N TOTAt
                                             HC/l
NOBS
716
  AUE
1.993
   PMX
1S.47«
                                                                                       flIN  KG-DATE
END-DATE
86/K/S7
            IS
                              1S73        197S        197?        1979        1981        1983        1985


                        1978        1974        :97E        1978        1980        1982        1984        1SB6



                                                           1971-1986
                                                                                                            Station 600900

-------
             39 43  10.9 983 M 45.9  2
             6CIOTO ft. NR SOUTH IIOOBHELD - S.R.
             39129  OHIO             PICKAUAV
             OHIO RIVER               051891
             SC10TO RIWER
             aiOHio  9S960001
                               DEPTH    •
              INDEX 1B2I5M  007729  13191
              RILES 953.89  £34.93 199.37
                                                                                                       STORET
           316
        /TVPA/AniNT/STREWI
                                899
PAAAflETER
 DO      PROIE
HG/L
NOBS
894
AUE
7 e
                                                                                        17 4
BEG-DATE
73/91/94
END-DATE
86/95/99
                         29
                                Stop* ef  R«qr»»»len lint «	9.21   Unit* ?mr V«»r.
                         15
O
                                                                                                                         Station 600910
                                                                                                                            RM  109.37

-------
            38 37 Sl.t M8 57 45.• Z
            SCIOTO R. UPST CIRCIEVILLC  - FLORENCE CHAPEL RD.
            38189 OHIO            PtCKAtMV
            OHIO RIVER              OSltte
            SCIOTO RIVER
            eiOHIO   »S46M*1                /TVPA/WIBNT/STHEAH
                    78M1*     DEPTH    I
             INDEX leeiSM  M772* 1319t
             HUES  953.M  624.93 1*8.14
                                                                                                   STORET
                                299
PARAMETER
 00      PftOlE
HG/L
HO»S
140
AUE
7.3
 MX
13 1
HIM  BEC-DATE   END-DATE
e.7  ?3/«e'a8
                         IS
                                Slop*  of B»gr»»»lo» ltn» *
                        9.19  Unit* p»r Ve»r.
o
I
                        ie
                                                                                                                           Station  600340
                                                                                                                              DM

-------
             39 37 St.* M8 57 45.•  2
             SCJOTO R. UPST CIRCIEUIILE - FLORENCE CMAPEt RD.
             39129 OHIO             PICKMMV
             OHIO RIVER               e$l»M
             KIOTO RIUCR
             210HIO   f5«6»Ml
                    7te51«     DO>TH    t
              INDCX 1621$««  M7780  1319*
              MILES  953.S*  624.93 U8.14
                                                                                                   STORCT
319   BOD
                                               5  MV
                         NC/L
NOIS
135
AUE
4.S
35.•
KIN  BEG-MTC
e.9  73/06/28
                                                                                                                   86/98/44
                         49
                         38
O
 I
Slop* »f R«flrf»*l»n . l.tite •
                                                             -9.31  1/niU p«r  V««r.
                                1973          197S         1977          1979         1981          1983          1985


                                      1974          1976         1978          1989          1982          1984          1986


                                                                       1973-1986
                                                                                                                         Station  600340
                                                                                                                             RH  102.14

-------
39 37 $8.t 182 57 45.*  9
SCIOTO R. UPST CIRCUVIUE -  FLORENCE CHAPEL RD.
39129 OHIO             PICCAUAV
OHIO RIVER               051M«
SCIOTO RJUER
EIOHIO   «S«6»M1                /TVPA'AMNT/STREAft
        78*21•     DEPTH   e
 INDEX 1921SM  M778I  13199
 KILES  853.W  K4 93 1M. H

                          PARAMETER
                    61t NH3HM4-  M TOTAL
                                                                                                    STORE! Sy»t*«
                                                                      NOIS
                                                                      146
  AUE
e.733
  RAX
5.168
            P11N
»EC-CATE
73/efi/as
END-DATE
00
                                                                                                                           Station 600340

-------
         APPENDIX  H
TABLES OF ENDANGERED SPECIES

-------
                                  APPENDIX H
                         TABLES OF ENDANGERED SPECIES
          TABLE H-l.  ENDANGERED FAUNA SPECIES KNOWN TO OCCUR IN THE
                   COLUMBUS FACILITIES PLANNING AREA, OHIO*
         Species
   State     Federally
Endangered  Endangered
Remarks
 Indiana  bat
 (Myotis  sodalis)

 Peregrin falcon
 (Falco peregrinus)

 Bald eagle (Haliaeetus
 leucocephalus)

 Kirtland's varbler
 (Dendroica kirtlandii)

 Upland sandpiper
 (Bartramia longicauda)
Common tern (Sterna
Hirondo)

Four-toed salamander
(Hemidactyliumd scutatum)
Northern brook lamprey
(Icthyomyzon fossor)
Paddlefish (Polyodon
spathula)
Blacknose shiner
(Notropis heterolepis)
River redhorse
(Hoxostoma carinatum)
                         Habitat requirements are
                         not fully known.

                         Occurs as an uncommon
                         migrant.

                         Occurs as an uncommon
                         migrant.

                         Occurs as an uncommon
                         migrant.

                         Hay occur in suitable,
                         grassy habitat anywhere in
                         the country.   Recent
                         records exist for Bolton
                         Field and Rickenbacker  Air
                         Base.

                         Occurs as an uncommon
                         migrant.

                         Requires a bog-like
                         habitat.  A recent record
                         exists for the northeastern
                         corner of the country.

                         Rare occurrence in Big
                         Valnut Creek and Big Run
                         (tributary of Olentangy
                         River).

                         One specimen observed in
                         Scioto River below
                         Greenlawn Dam in 1976.

                         Population in Rocky Fork
                         Creek (tributary of Big
                         Valnut Creek,  northeast
                         Franklin County).

                         Known population in Scioto
                         River and tributaries.
                                     H-l

-------
          TABLE H-l.  ENDANGERED FAUNA SPECIES KNOW TO OCCUR IN THE
             COLUMBUS FACILITIES PLANNING AREA, OHIO* (Continued)
        Species
                             State     Federally
                          Endangered  Endangered
Remarks
Slenderhead darter
(Percina phoxocephala)
Spotted darter
(fitheostoma Maculatum)
Lake Chubsucker
(Erimyzon succtta)

Shortnose gar
(Lepisosteus platostomius)

Mooneye
(Hiodon tergisus)c

Tippecanoe darter
(Ethestpma tippecanoe)d

Scioto madtorn
(Noturus trautmani) ' *
                                                   Known population in Big
                                                   Walnut and Big Darby
                                                   Creeks.

                                                   Small population in
                                                   Olentangy River and Big
                                                   Valnut Creeks.
                                                   Collected just downstream
                                                   of FPA at Circleville.

                                                   Found only in Big Darby
"Source:  Ohio Department of Natural Resources 1986, unless otherwise noted.

bSource:  OEPA 1986a.

cSource:  Yoder 1987; Ohio Department of Natural Resources 1986.

dSource:  Cavender 1986.

'Source:  Multerer 1986.
                                     H-2

-------
   TABLE H-2.  LIST OF STATE AND FEDERALLY ENDANGERED PLANT SPECIES IN OHIO
Selaginella rupestris, Rock Spikemoss
Isoetes engelmannii, Appalachian Quillwort
Botrychium lanceolatum, Triangle Grape-fern
Ophioglossum engelmannii, Limestone Adder's-tongue
Trichomanes boschianum~Appalachian Filmy Fern
Polypodium pplypodioides, Little Gray Polypody
DryopterTs clintoniana,(D. cristata yar. cllntoniana) Clinton's Wood Fern
Sparganium androcladum, Keeled Bur-reeH
Sparganium chlprpcarpum, Small Bur-reed
Potamogetonfiliformis, Filiform Pondveed
Potamogeton gramineus, Grass-like Pondveed
Potamogeton Killii, Hill's Pondweed
Potamogeton praelongus, White-stem Pondveed
Potamogeton robbinsii, Robbin's Pondveed
Potamogeton tennesseensis, Tennessee Pondveed
Scheuchzeria palustris, Scheuchzeria
Sagittaria graminea, Grass-leaf Arrovhead
Cinna laTIfolia, Northern Vood-reed
Danthonia compressa, Flattened Wild Oat Grass
Digitaria filiformls, Slender Finger-grass
Glyceria~acutiflprat Sharp-glumed Manna-grass
Koeleria macrantha~(K. cristata), Junegrass
Helica nitens, Three-flovered Meli c
Huhlenbergia cuspidata, Plains Muhlenbergia
Oryzopsis asperifolia, Large-leaved Mountain-rice
PanicumlSicknelin, Bicknell's Panic-grass
Pan i cum boreale, Nor them Panic-grass
Panicurn leibergii, Leiberg's Panic-grass
Panicum villpslssimum, Villous Panic-grass
Panicum yadkinense, Spotted Panic-grass
Poa volfii., Wolf's Bluegrass
Schizacnne purpurascens, False Melic
Carex aquatilis, LeafyTussock Sedge
Carex arctata, Drooping Wood Sedge
Carex argyrantha, Silvery Sedge
Carex atnerodes, Wheat Sedge
Carex bebbii, B'ebb's Sedge
Carex cryptplepis (C. flaya yar. fertilis), Little Yellov Sedge
Carex debilis yar. Hebilis, Weak Sedge
Carex decpmposita, Cypress-knee Sedge
Carex folliculata, Long Sedge
Carex garberi, Garber's Sedge
Carex gravida, Heavy Sedge
Carex naydenix, Hayden's Sedge
Carex Ipuisianica, Louisiana Sedge
Carex nigromarginata, Black-margined Sedge
Carex ormpstachya, Stiff Broad-leaved Sedge
Carex pallescens, Pale Sedge
Carex sprengelll, Sprengel's Sedge
Carex striatulaT Lined Sedge
Cyperus acuminatus,  Pale Umbrella-sedge
                                     H-3

-------
   TABLE H-2.   LIST  OF  STATE AND  FEDERALLY ENDANGERED PLANT SPECIES IN OHIO
                                  (Continued)


   perus dipsacifprmis,  Teasel-sedge
 Rhynchospora globularis,  Grass-like Beak-rush
 Scirpus expansus,  Woodland  Bulrush
 Scirpus smithii,' Smith's  Bulrush
 Scirpus subterminalis,  Swaying Rush
 Wolffiella floridanaT Wollfiella
 Juncus  interior,  Inland Rush
 Cltntonia borealis,  Bluehead-lily
 Li Hum  pHiladelphicum,  Wood-lily
 Melanthium virginicum,  Bunchflower
 Nothoscorchiin bivalve, False Garlic
 Smilax  pulverulenta,  Downy  Carrion-flower
 Streptopus roseus, Rose Twisted-stalk
 Iris  brevTcaulis,  Leafy Blue Flag
 Iris  verna,  Dwarf  Iris
 Sisyrinchium atlanticum,  Atlantic Blue-Eyed-grass
 Sisyrinchium montanum,  Northern Blue-eyed-grass
 Arethusa bulbosa,  Dragonfs-mouth
 Coeloglossum viride  (Habenaria viridis), Long-braeted Orchid
 Corallorhiza trifida, Early Coral-root
 Corallorhiza wisteriana,  Spring Coral-root
 Cypripedium  calceolus var.  parviflorum, Small Yellow Lady's-slipper
 Cypripedium  candidum7 White Lady's-slipper
 Hexalectris  spicata7 Crested Coral-root
 PlatantheTa  blephariglottis (Habenaria blephariglottis), White Fringed Orchid
 Spiranthes romanzoffiana, Hooded  Ladies'-tresses
 Populus Ttelsamifera, Balsam Poplar
 Populus  heterophylla, Swamp Cottonwood
 Salix caroliniana, Carolina Willow
 Salix pedicellaris, Bog Willow
 Myrica pensy1vanTca, Bayberry
 Ulmus tnomasii, Rock Elm
 Urtlca~chamaedryoides,  Spring  Nettle
 Polygonum  cilinode, Mountain Bindweed
 Pplygonum  ramosissimum, Bushy  Knotweed
 Chenopodium  leptophyllum  (sensu Fernald 1950), Slender Goosefoot
 Froelichia flpridana, Cottonweed
Arenaria~patula, Spreading  Sandwort
 Silene caroliniana var. wherryi,  Wherry's Catchfly
Nuphar variegaturn, Bullhead Lily
Aconitum noveboracense, Northern  Monkshood
Aconiturn uncinatum, Southern Monkshood
Actaea rubra, Red Baneberry
Ranunculus pusillus, Low  spearwort
Trollius~Iaxus, Spreading Globe-flower
Magnolia macrophylla, Bigleaf  Magnolia
Hagnplia tripetala, Umbrella Magnolia
Arabis dfivaricarpa, Limestone  Rock-cress
                                     H-4

-------
   TABLE H-2.   LIST OF STATE AND FEDERALLY ENDANGERED PLANT SPECIES IN OHIO
                                  (Continued)


Arabis drummondii, Drummond's Rock-cress
Arabis gatens, Spreading Rock-cress
Draba brachycarpa, Little Vhitlow-grass
Draba cuneifolia, Wedge-leaf Whitlow-grass
Draba reptans, Carolina Whitlow-grass
Erysimum arkansanum (E. capitaturn), Western Wall-flower
Drpsera intermedia, Spathulate-leaved Sundew
Ribes missouriense, Missouri Gooseberry
Ribes rotundifolium, Appalachian Gooseberry
Ribes triste, Swamp Red Currant
Amelanchier sanguinea, Rock Serviceberry
Dalibarda repens, Robin-run-away
Potentilia arguta, Tall Cinquefoil
Prunus nigra, Canada Plum
Pyrus decora (Sorbus decora), Western Mountain-ash
Rubus setosus, Small Bristleberry
Astragalus neglectus, Cooper's Milk-vetch
Baptisia~australis, Blue False Indigo
Desmodiumillinoense, Prairie Tick-trefoil
Desmbdium sessilifolium, Sessile Tick-trefoil
GalactiiTvolubilis, Milk-pea
Lathyrus venosus, Wild Pea
Oxalis^montana (0. acetosella), White Wood-sorrel
Geranium bicknellii, Bicknell's Crane's-bill
Polygala cruciata~Cross-leaved Milkwort
Polygala curtissli, Curtiss' Milkwort
Euphorbia serpens, Roundleaf Spurge
PnyllantHus caroliniensis, Carolina Leaf-flower
Paxistima canbyi, Cliff-green
Acer pensyIvanicum, Striped Maple
CaenotFus herbaceus (C. ovatus), Prairie Redroot
Hypericum deriticulatum, Coppery St. John's-wort
Hudsonia tomentosa, Beach-heather
Viola missouriensis, Missouri Violet
Viola nephrpphylla, Northern Bog Violet
Viola primulifolia, Primrose-leaved Violet
Viola tripartita var. glaberrima (forma glaberrima), Wedge-leaf Violet
Viola walteri, WaTter's Violet
Arlia hispida, Bristly Sarsaparilla
Hydroegty_le umbe 1 lata, Navelwort
Ledum grognlandicum, Labrador-tea
Rh6dpdenJr6rT caTendulaceum, Flame Azalea
Vaccinium myrtilloides, Velvet-leaf Blueberry
Vaccinium oxycoccos, Small Cranberry
Hottonia~in£lata, Featherfoil
Halesia Carolina, Silverbell
Styrax americanus, Snowbell
Gentiana puberulenta (G. puberula), Prairie Gentian
Gentiana saponaria, Soapwort Gentian
Cuscuta compacta, Sessile Dodder
Cynoglossum virginianum var. boreale (C. boreale), Northern Wild Comfrey
                                     H-5

-------
   TABLE H-2.  LIST OF STATE AND FEDERALLY ENDANGERED PLANT SPECIES IN OHIO
                                  (Continued)


Collinsonia verticillata (Hicheliella verticillata), Early Stoneroot
Honarda punctata, DotttiH Horsemint
Trichostema dichotomum var. lineare (T  setaceum), Narrow- leaved Bluecurls
Agalinis auriculata (Gerardia auriculata; Toman thera auriculata) , Ear-leaf
  Foxglove
Agalinis purpurea var. parvi flora (A. paupercula var. pauperula and var.
  borealis; Gerardia paupercula var. paupercula and var. borealis), Small
  Purple Foxglove
Agalinis skinneriana (Gerardia skinner i ana), Skinner's Foxglove
Aureolaria pedicularia var. ambigens (Gerardia pedicularia var. ambigens),
  Prairie Fern-leaf False Foxglove
Orobanche ludoviciana, Louisiana Broom-rape
Utricular'ia cornuta, Horned Bladderwort
Plantagp cordata, Heart-leaf Plantain
Galium I'abradoricum, Bog Bedstrav
Gal i urn palust re /Harsh Bedstrav
Symphoricarpps "albus var. albus, Snovberry
Cirsium carolinianum, Carolina Thistle
Eupa t ori um hyssop i folium, Hyssop Thoroughwort
Heterotheca gramini folia' (Chrysppsis gramini folia), Silkgrass
Hieracium canadense, Canada Havkveed
Hieragium longipilum, Long-bearded Havkveed
Hymenoxys acaulis ( Ac t inea herbacea), Lakeside Daisy
      tn
Prenantnes aspera, Rough Ra 1 1 lesnake-roo t
S i Iph i um"Tac i n i a t um , Compass-pl
Solidago odora, Sweet Goldenrod
S i Iph i um"Tac i n i a t um , Compass-plant
   idag
Ver besi ria occ i den tal i s , Yellow Crovnbeard

-------
          TABLE H-3.  ENDANGERED UNIONID MOLLUSCS KNOWN TO
               HAVE INHABITED THE SCIOTO RIVER SYSTEM
Scientific Name
Common Name
Simpsonaias ambigua
Quadrula cylindrica
Quadrula metaneura
Quadrula nodulata
Fusconaia maculata
Plethobasus cyphyus
Pleurobema clava
Pleurobema cordatum
Cyprogenia stegaria
Potamilus laevissimus
Lampsilis teres
Lampsilis orbiculata
Lampsilis ovata
Simpson's Shell
Cob Shell
Knobbed Rock Shell
Winged Pimpleback
Long-solid
Common Bullhead
Club Shell
Ohio Pigtoe
Ohio Fan Shell
Fragile Heel-Splitter
Yellow Sand Shell
Pink Mucket Pearly Mussel
Ridged Pocketbook

-------
    Table H-4     Rare or  endangered  fish  species  collected  during  the  1979-1981
                     sampling  period  and/or  listed   as   occurring   in   the  central
                     Scioto   River  mainstem  study  area   by  the  Ohio  Department   of
                     Natural    Resources,   Heritage   Program      (Source-     Ohio   EPA
                     1986a).
Species
Ltle chubsucker
Bluebreilt darter
Goldeye
ODHR StatW
Endangered
Threatened
Undetermined
OONR Location*, Tear
Ctrclevllle Canil pff ltd 100 (1974. 1981)
1} Setoto
2} Seloto
3) Scioto
1) Setoto
2) Scioto
it south of Deer Cr. (1961)
near ClrcletlUe (19(2)
. beloH Big Oarby confluence (1963)
. it GrcenliMi Ate. (1959)
. dit. Bio Dirby Cr.
Ohio EM collection!, dat«»
Hot collected
Hot collected
DM 74.1 (1981)
Silver Itaprcy


Shertnott gtr


River redhorte
Endangered


Endtngered


Endtngered
Shortheid  redhorse
raddleftsh
Undetemlned
Endangered
    confluence (1962)

Scioto * it Chintcotht (19M)


Seloto R. dit. Chilli tothe 1973
1) Scioto R. u*t. Big Darby Cr. (1962)
2) Setoto R..dtt. Dublin Rd  VTP dt« (1979)
1) M. brfvlceps - Scloto R. it
                                          n, brfvlceps - Sclo
                                          "ChllticotKe (19M)
Not collected
(only belo* Chilltcothe. 1979)

KM 118.8 (1981)
                                                                                RN 70.7
                                                                                RN 78.1
                                                                                RH 102.0
                                                                                KM 102.0
         1980
         1979
         1979
         1981
Scioto R. dst. CreenliMi d*a (1976)
                                                                                RH 104.8 (1979
                                                                                MM 134.8 (1981!
                                                                                RH 138.6 (198t
RN 138.6-70.7 (72 fUhi
  1979-1981)
Olentingy R. (1980)
Big Walnut Cr. (1980,1981)

Not collected
                                               H-8

-------
       APPENDIX   I
 SITES AND  STRUCTURES  IN
THE COLUMBUS AREA LISTED
ON THE NATIONAL REGISTER
   OF HISTORIC PLACES

-------
                                  APPENDIX I


     The following sites/structures are listed on the National Register of

Historic Places.
Delaware County

Ashley, Building at 500 East High Street
   (Eastlake Houses of Ashley Thematic
   Resources)  (11-25-80)

Building at 505 East High Street
   (Eastlake Houses of Ashley Thematic
   Resources)  (11-25-80)

Building at 101 North Franklin Street
   (Eastlake Houses of Ashley Thematic
   Resources)  (11-25-80)

Building at 223 Vest High Street
   (Eastlake Houses of Ashley Thematic
   Resources)  (11-25-80)

Ashley vicinity, Sharp, Samuel, House
   (Sharp's Run), 7436 Horseshoe Rd.
   (07-29-82)

Delaware.  Delaware County Courthouse.
   N. Sandusky St. and Central Ave.
   (5-22-73) PH0034681

Delaware Public Library, 100 N. Sandusky
   St. (01-11-83)

Elliott Hall, Sturges Library, and
   Merrick Hall.  Ohio Vesleyan
   University Campus (4-23-73) PH0094480

Monnett Hall, Ohio Wesleyan University
  Campus at Elizabeth and Vinter Sts.
   (6-23-75).

Sandusky Street Historic District.
  44 S. to 92 N. Sandusky, 47 E. to
   31 W.

St. Mary's Church and Rectory, 82 E.
  William St. (5-23-80)

Van Deman, Henry, House, 6 Darlington
  Rd. (05-31-84)
Delaware vicinity.  Greenwood Farms.
  S. of Delaware off U.S. 42 (4-17-79);
  79/07/23 079 0001773

Limestone Vale, 3490 Olentangy River Rd.
  (10-2-78)

Ufferman Site, N. of Delaware (7-24-74)
  PH0034711

Varren Tavern Complex.  U.S. 36
  (08/30/83)

Galena vicinity.  Curtiss, Marcus, Inn
  E. of Galena at 3860 Sunbury Rd.
  (12-12-76)

Keeler, Diadatus.  House, SB of Galena
  at 4567 Red Bank Rd. (2-2-79)
  80/01/10079 0006789

Spruce Run Earthworks.  About 3 mi. S.
  of Galena, (7-16-73) PH0034703

Harlem vicinity.  Cook, John, Farm, E.
  of Harlem at Miller Paul Rd. and
  Gorsuch Rd. (4-11-77)

Olive Green vicinity.  Chambers Road
  Covered Bridge, 1.5 mi. NE of Olive
  Green (11-21-74) PH0085049

Sunbury Tavern (Hopkins House), NW
  corner OH 37 and Galena Rd. (2-24-75)

Sunbury Township Hall, Town Sq.
  (2-20-75)

Sunbury vicinity, Center Inn, SE of
  Sunbury on OH 37 (01/11/83)

Westerville vicinity, Sharp, Stephen,
  House, N. of Westerville on Africa Rd.
  (09/30/82)

-------
Winter, and 9 E.  to 17 W. William
   (12-17-82)
Medill, William, House, 319 N. High St.
  (3-30-78)
Vorthington vicinity.  Highbank Park
  Works.  E. bank of Olentangy River
  (2-15-74) PH0112895
Fairfield County

Amanda, Barr House, 350 W. Main St.
  (11-26-80)

Amanda vicinity.  Allen, Lyman, House
  and Barn, NW of Amanda on OH 188
  (11-18-76)

Baltimore vicinity. Bright, John,
  Covered Bridge, 2.5 mi. SW of
  Baltimore over Poplar Creek (5-28-75)

Miller Farm, S of Baltimore on
  Pleasantville Rd. (5-22-75)

Musser, Henry, House, SE of Baltimore at
  7079 Millersport Rd. (5-5-78)

Pugh-Kittle House, 2140 Bickel Church
  Rd. (06-16-83)

Canal Winchester.  Loucks Covered
  Bridge, SB of Canal Winchester on SR
  207 (Diley Rd.) (10-8-76)

Carroll vicinity. Ety Enclosure, NE of
  Carroll (7-12-74) PH0034801

Ety Habitation Site, NE of Carroll
  (7_24-74) PH0034819

Carroll vicinity.  John Bright, No. 1
  Iron Bridge, 2 mi. (3.2 km) NE of
  Carroll on Havensport Rd. (9-20-78)

Lancaster.  Bush, Samuel, House, 1934
  Cold Spring Dr. (10-1-74) PH0034762

Lancaster Historic District, Roughly
  bounded by 5th Ave., Penn Central

Lancaster West Main Street Historic
  District, W. Main St. from Columbus to
  Broad St. (2-2-79)j 80/01/10079
  0006790
Sherman, John, Birthplace, 137 E. Main
  St. (10-15-66) PH0034845 NHL.

Square 13 Historic District, Roughly
  area along Broad and High Sts. between
  Mulberry and Chestnut Sts. (7-24-72)
  PH0034851 HABS;G

St. Peter's Evangelical Lutheran Church,
  Broad and Mulberry Sts. (4-16-79)j
  79/07/23 079 0001775

Lancaster, Tallmadge-Mithoff House, 720
  Lincoln Ave. (5-6-76)

Lancaster vicinity. Chestnut Ridge Farrc,
  3375 Cincinnati-Zanesville Rd., SW.
  (7-24-72) PH0034771

Concord Hall, 1445 Cincinnati-Zanesville
  Rd., SW. (U.S. 22) (10-25-72)
  PH0034789

Reber, Valentine, House, W. of Lancaster
  at 8325 Lancaster-Circleville Rd.
  (OH 188) (7-30-75)

Willow Lane Farm (Nathaniel Wilson
  House), SW of Lancaster on U.S. 22
  (10-26-72) PH0034878

Lithopolis vicinity.  Old Maid's Orchard
  Mound, E. of Lithopolis (7-15-74)
  PH0034843

Lockville.  Lockville Canal Locks, Off
  Pickerington-Lockville Rd. (9-10-74)
  PH0085006

Pickerington vicinity, Dovel, J.H.,
  Farm, 660 N. Hill Rd. (03-15-82)

Hizey Covered Bridge, E. of Pickeringtou
  on SR 235 (10-8-76)

Stemen Road Covered Bridge, NE of
  Pickerington over Sycamore Creek,
  (4-20-79); 79/07/23 079 0001776

RR tracks, OH 33 and Tennant St.
  (08-11-83)
                                     1-2

-------
Rushville, Rushville Historic District,
  Bremen Ave., Main and Market Sts.
  (11-24-80)

Rushville vicinity.  Vinegar drier
  Village (7-30-74) PH0034886

Rock Mill. Rock Mill Covered Bridge,
  SR 41 (4-26-76)

Royalton.  Royalton House, Amanda
  Northern Rd. (7-30-75)

Sugar Grove vicinity.  Crawfis
  Institute, Crawfis and Old Sugar Grove
  Rds. (ll-29-79)j 80/01/10079 0006402

Vest Rushville, Ijams, Joseph, House,
  Broad and Main Sts. (06/16/83)

Franklin County

Bexley, Duncan, Robert P., House, 333 N.
  Parkview Ave. (08-23-84)

Jeffrey, Malcomn, House 358 N. Parkview
  (05-08-83)

Canal Vinchester, Canal Winchester
  Methodist Church, S. Columbus and High
  Sts. (03-15-82)

Canal Winchester vicinity.  Bergstresser
  Covered Bridge, W. of OH 674 over
  Walnut Creek (5-3-74) PH0070181

Central College Multiple Resource Area.
  This area includes:  Westerville
  vicinity, Central College Presbyterian
  Church, Sunbury Rd.; Fairchild
  Building.

Central College vicinity.  Squire's Glen
  Farm, 6770 Sunbury Rd. (8-13-74)
  PH0070432

Columbus, American Insurance Union
  Citadel, 50 W.  Broad St. (3-21-75)

Camp Chase Site,  2900 Sullivant Ave.
  (4-11-73) PH0112909

Broad Street United Methodist Church,
  501 E.  Broad St.  (11-26-80)
Columbia Building, 161-167 N. High St.,
  (08-12-83)

Capital University Historic District,
  E. Main St. and College Ave.
  (12-17-82)

Columbus Country Club Mound, 4831 E.
  Broad St., (2-15-74) PH0070211

Columbus Near East Side District,
  Roughly bounded by Parsons Ave., Broad
  and Main Sts., and the railroad
  tracks (5-19-78)

Columbus Savings and Trust Building
  (Atlat Building), 8 E. Long St.
  (9-15-77)

Columbus Transfer Company Warehouse,
  55 Nationwide Blvd. (02-24-83)

Drake, Elam, House, 2738 Ole Country
  Lane (4-6-78)

East Town Street Historic District,
  Roughly bounded by Grant and Franklin
  Aves., Lester Dr. and E. Rich St.
  (7-30-76)

Pelton School, Leonard Ave. and N.
  Monroe St. (05-31-84)

Fort Hayes, Cleveland Ave. and 1-71
  (1-26-70) PH0070238

Franklin Park Conservatory, 1547 E.
  Broad St. (1-18-74) PH0070246

Franklinton Post Office (David Deardurf
  House), 72 S. Gift St. (3-20-73)
  PH0070254

German Village, Roughly bounded by
  Livingston Ave., Pear Alley, Nursery
  Lane, Blackberry Alley, and Lathrop
  St. (12-30-74) PH0044148

Great Southern Hotel and Theatre,
  S. High and E. Main Sts. (12-02-82)

Hamilton Park Historic District, Broad
  and Long Sts. (07-28-83)
                                     1-3

-------
Hanna House,  1021 E. Broad  St.
   (4-19-79);  79/07/23 079 0001778
Ohio State Arsenal, 139 V. Main St.
  (7-18-74) PH0070378
Harrison, Gen. William Henry,
  Headquarters (Jacob Oberdier House),
  570 W. Broad St.  (12-15-72) PH0070271

Hayes and Orton Halls, Ohio  State
  University, The Oval (7-16-70)

Higgins, H.A., Building  (Flatiron
  Building), 129 E. Naghten  St.
  (8-27-79)? 79-11-30 079 0005031

Holy Cross Church,  Rectory and School,
  212 S. 5th St. (4-26-79) 79/07/23 079
  001779

Huntington, Franz,  House, 81 N. Drexel
  Ave. (5-29-80)

Indianola Junior High School, 420 E.
  19th Ave. (6-30-80)

Jaeger Machine Company Office Building,
  550 tf. Spring St. (06-16-83)

Jefferson Avenue Historic District,
  Roughly bounded by 1-71, E. Broad,
  llth, and Long Sts. (12-02-82)

Jones, V.H., Mansion, 731 E. Broad St.
  (10-2-78)

Krumm House, 975-979 S.  High St.
  (09-30-82)

Long and Third Commercial Building,
  103-113 E. Long St. (07-01-82)

Near Northside Historic  District, Off OH
  315 (6-4-80)

North Market Historic District, Roughly
  bounded by W. Goodale, Park, High,
  Front, and Vine Sts. (12-30-82)

Ohio Asylum for the Blind, 240 Parsons
  Ave. (7-26-73) PH0070351

Ohio National Bank, 167  S. High St.
  (11-26-80)

Ohio Stadium,  404 W. 17th Ave. (3-22-74)
  PH0070360
Ohio Statehouse, SE corner of High and
  Broad Sts. (7-31-72) PH0070386 G.
  Ogers, Isaiah Saiah Rogers.

Ohio Theatre, 39 E. State St. (4-11-73)
  PH0070394 NHL; G.

Old Governor's Mansion (Ohio Archives
  Building, Charles H. Lindenberg
  House), 1234 E. Broad St. (6-5-72)
  PH0070408

Old Ohio Union, 154 V. 12th Ave.
  (4-20-79); 79/07/23 079 0001780

Old Port Columbus Airport Control Tower,
  420 E. 5th Ave. (7-26-79); 79-11-13
  079 0004392

Orton Memorial Laboratory, 1445 Summit
  St. (11-25-83)

Pierce, Elijah, Properties, 435 E. Long
  St. and 142-44 N. Everett Alley
  (08-03-83)

Pythian Temple and James Pythian
  Theater, 861-867 Mt. Vernon Ave.
  (11-25-83)

Rankin Building, 22 V. Gay St.
  (03-10-82)

Rickenbacker, Capt. Edward V., House,
  1334 E. Livingston Ave. (5-11-76) NHL.

Schlee-Kemmler Building, 328 S. High St,
  (12-02-82)

Second Presbyterian Church, 132 S. Third
  St. (01-11-83)

Seneca Hotel, 361 E. Broad St.
  (12-29-83)

Sessions Village, Both sides of Sessions
  Dr. (2/20/75)

Smith, Benjamin, House, 181 E. Broad
  St. (6/4/73) PH0070424
                                      1-4

-------
South High Street Commercial Grouping,
  Bounded by Pearl, Mound, Main, and
  High Sts. (12/29/83)

Sullivant, Lucas, Building, 714 V. Gay
  St. (3/20/73) PH0070441

Thurber, James, House, 77 Jefferson Ave.
  (11/8/79); 80/01/10079 0006403

Toledo and Ohio Central Railroad
  Station, 379 W. Broad St. (6/18/73)
  PH0070475 HAERj G.

Trinity Episcopal Church, 125 E. Broad
  St. (11/13/76)

U.S. Post Office and Courthouse (Old,
  Old Post Office), 121 E. State St.
  (4/11/73)

Valley Dale Ballroom, 1590 Sunbury Rd.
  (12/17/82)

Welsh Presbyterian Church, 315 E. Long
  St. (11/24/80)

Vyandotte Building, 21 V. Broad St.
  (2/23/72) PH0070491 HABS

York Lodge No. 583, 1276 N. High St.
  (07/19/84)

Columbus Vicinity

Agler-la Follette House, 2621 Sunbury
  Rd. (12/14/78)

Davis, Samuel, House, 4264 Dublin Rd.
  (2/15/74) PH0070220

Hartman Stock Farm Historic District,
  S. of Columbus on U.S. 23 (10/9/74)
  PH084999

Jackson Fort (12/10/74) PH0085251

McDannald Homestead, NE of Columbus at
  5847 Sunbury Rd. (2/17/78)

Noble, Jonathan, House, 5030 Vesterville
  Rd. (SR 3) (12/3/75)

Dublin vicinity.  Davis, Anson, House,
  4900 Hayden Run Rd. (7/7/75)
Holder-Wright Works (2/15/74) PH0070319

Sells, Benjamin, House, S. of Dublin at
  4586 Hayden Run Rd.  (7/30/75)

Gahanna, Shepard Street School (Gahanna
  Nursing Home), 106 Short St.
  (11/29/79); 80/01/10079 0006404

Grove City, Gantz Homestead, 2233 Gantz
  Rd. (6/20/79); (10/23/79) 079 0002507

Groveport, Groveport Log Houses, Wirt
  Rd. (5/6/76)

Groveport Town Hall Historic Group, 628,
  632 Main and Main and Front Sts.
  (7/31/78)

Hilliard vicinity.  Wesley Chapel, SE of
  Billiard at 3299 Dublin Rd. (2/27/79);
  79/07/13 079 0000620

Lockbourne vicinity, Herr, Christian S.,
  House, N. of Lockbourne at 1451
  Rathmell Rd. (03/05/82)

Marble Cliff, Miller, J.F., House, 1600
  Roxbury Rd. (05/31/84)

Riverlea, Russell, Mark, House 5805 N.
  High St. (12/12/76)

Sunbury Rd.; Presbyterian Parsonage,
  6972 Sunbury Rd.; Washburn, Rev.
  Ebenezer, House, 7121 Sunbury Rd.
  (11/25/80)

Washington Township.  Washington
  Township Multiple Resource Area.  This
  area includes various properties at
  various locations.  Details available
  upon request. (4/11/79); 79/07/16 079
  0001090

Westerville, Alkire House, 269 N. State
  St. (3/30/78)

Hanby, Benjamin,  House, 160 W. Main St.
  (11/10/70) PH0094501

Hart, Gideon, Rouse, 7328 Hempstead Rd.
  (8/14/73) PH0070289
                                     1-5

-------
Otterbein Mausoleum, V. Walnut St.
  (11/29/79); 80/01/10079 0006405

Towers Hall, Otterbein College, Main and
  Grove Sts., Otterbein College campus
  (3/4/71) PH0070459

Westerville High School, Vine Street
  School, 44 N. Vine St. (5/29/75)

Westerville vicinity.  Everal, John W.,
  Farm Buildings, 7610 Cleveland Ave.
  (9/18/75)

Osborn, Charles S., 5785 Cooper Rd.
  (3/28/77)

Worthington, Johnson, Orange, House,
  956 High St. (4/3/73) PH0070335

New England Lodge, 634 N. High St.
  (3/20/73) PH0070343

Snow, John, House, 41 V. New England
  Ave. (7/26/73) PH0071251

Worthington Manufacturing Company
  Boardinghouse, 25 Fox Lane (6/19/73)
  PH0112917

Worthington Multiple Resource Area.
  This area includes:  Adams, Demas,
  House, 721 High St.; Bishop-Noble
  House, 48 tf. South St.; Brown, Sidney,
  House, 12 E. Strafford Ave.; Fay,
  Cyrus, House, 64 W. Granville Rd.;
  Gardner House, 80 W. Granville Rd.;
  Johnson, Orange, House, 956 High St.
  (previously listed in the National
  Register 4-3-73); Kilbourne House,
  679-681 High St.; Ladd-Mattoon House,
  73 E. North St.; New England Lodge,
  634 High St. (previously listed in the
  National Register 3-20-73); Old
  Worthington Inn, Nev England and High
  Sts.; President's House, 38 Short St.;
  Ripley House, 623 High St.; St. John's
  Episcopal Church, 700 High St.; Scott,
  Travis,  House, 72 E. Granville Rd.;
  Sharon Township Town Hall, Granville
  Rd. and Hartford St.; Skeele, Capt.
  J.S., House, 700 Hartford St.; Snow,
  John, House, 41 W. New England Ave.
  (previously listed in the National
  Register 7-26-73); Topping, J.R.,
  House, 92 E. Granville Rd.; Park,
  Jonathan, House, 91 E. Granville Rd.'
  Wilcox, Hiram, House 196 E. Granvill«
  Rd.; Worthington Historical Society
  Museum, 50 W. New England Ave.;
  Worthington Manufacturing Company
  Boarding House, 25 Fox Lane
  (previously listed in the National
  Register 6-19-73); Worthington United
  Presbyterian Church, High St. and W.
  Granville Rd.; Worthington Village
  Green, Village Green; Wright, Horace,,
  House, 137 E. Granville Rd.; Wright,
  Potter, House, 174 E. New England Avo.
  (4/17/80)

Licking County

Brownsville vicinity.  Flint Ridge
  (11/10/70) PH0070904

Croton vicinity.  Belle Hall Covered
  Bridge, E. of Croton on Dutch Cross
  Rd. (10/22/76)

Granville, Avery-Hunter House, 221 E.
  Broadway (12/27/79)

Buxton Inn, 313 E. Broadway (12/26/72)
  PH0070874

Granville Multiple Resource Area
  (Partial Inventory).  This area
  includes:  Granville, Granville
  Historic District, OH 37; Bancroft,
  A.A., House, N. Pearl St. and
  Washington Dr.; Carpenter, Wallace W.,
  House (The Castle) 323 Summit St.;
  Dustin Cabin, 597 N. Pearl St.; Rogers
  House, 304 N. Pearl St.; Rose, Capt.
  Levi, House 631 N. Pearl St.
  (11/28/80)

St.  Lukes Episcopal Church, 111 E.
  Broadway St. (4/26/76)

Granville vicinity, Bryn Mawr (Fassett's
  Folly), 3758 Lancaster Rd., SW
  (03/29/83)

McClune's Villa, 537 Jones Rd.
  (04/22/82)
                                     1-6

-------
Stanbery, Edwin, Office, 1 mi (1.6 km)
  E. of Granville (11/30/78)

Heath, Ohio Canal Groundbreaking Site,
  OH 79 (5/24/73) PH0070963

Johnstown, Monroe Township Hall-Opera
  House, 1 S. Main St. (7/6/81)

Johnstown vicinity.  Lynnwood Farm, S.
  of Johnstown at 4986 Caswell Rd.
  (6/22/79); (10/23/79) 079 0002509

Newark.  Chapel Hill Cemetery Buildings,
  Cedar St., Chapel Hill Cemetery
  (4/13/77)

Courthouse Center, 35-37 S. Park Pi. and
  jet. of S. Park and S. 2nd St.
  (11/29/79); 80/01/10079 0006411

Home Building Association Bank, 6 V.
  Main St. (7/2/73) PH0070912

Hull Place, 686 W. Main St. (12/21/79)

Licking County Courthouse, Courthouse
  Sq. (3/20/73) PH0070921

McNamar-McLure-Miller, Residence, 124 V.
  Main St. (06/17/82)

Newark Earthworks, Mound Builders State
  Memorial (10/15/66) PH0070955 NHL.

Oakwood, 64-70 Penney Ave. (5/29/80)

Pennsylvania Railway Station, 25 E.
  Walnut St. (11/29/79); 80/01/10079
  0006412

Rhoads, Peter F., House, 74 Granville
  St. (11/28/80)

Sherwood-Davidson and Buckingham Houses,
  W. Main and 6th Sts. (11/10/77)

Shield's Block, 23-29 S. Park Pi.
  (11/29/78)

Upham-Vright House, 342 Granville St.
  (6/22/79); (10/23/79) 079 0002510

West Side Planning Mill, 197 Maholm St.
  (01/21/83)
Williams, Ellas, House (Bolton House),
  565 Granville St. (4/16/79); 79/07/23
  079 0001786

Newark vicinity.  Upland Farm, N. of
  Newark off OH 657, (12/1/78)

Pataskala, Bethel Baptist Church
  (Pataskala MRA), Vine and Cedar Sts.
  (09/22/83)

Casterton House (Pataskata MRA), 105
  Broadway (09/22/83)

Elliot House (Pataskala MRA), 301 S.
  Main St. (11/14/83)

Kauber, Warren F., Funeral Home
  (Pataskala MRA), 289 S. Main St.
  (09/22/83)

Mead House (Wind Flower House)
  (Pataskala MRA), 245 S. Main St.
  (09/22/83)

Pataskala Banking Company (Pataskala
  MRA), 354 S. Main St. (09/22/83)

Pataskala Elementary School (Pataskala
  MRA), 396 S. High St. (09/22/83)

Pataskala Jail (Pataskala MRA), Main St.
  (09/22/83)

Pataskala Presbyterian Church (Pataskala
  MRA), Atkinson and Main Sts.
  (11/14/83)

Pataskala Town Hall (Pataskala MRA), 430
  Main St. (09/22/83)

Pataskala United Methodist Church
  (Pataskala MRA), 458 S. Main St.
  (09/22/83)

Madison County

Lafayette.  Red Brick Tavern, 1700
  Cumberland Rd. (9/5/75)

London.  Madison County Courthouse,
  Public Sq.  (3/14/73) PH0094552

Swetland Rouse, 147 E. High St.
  (01/11/83)
                                     1-7

-------
Mount Sterling.  Mount Sterling Historic
  District, Both sides of London St.
  (10/1/74) PH0060801

Plain City vicinity.  Gary Village Site,
  SB of Plain City (5/13/75)

Somerford vicinity   Wilson, Valentine,
  House, About 1 mi. N. or Somerford off
  1-70 (5/22/73) PH0060828

Pickaway County

Ashville, Ashville Depot, Madison and
  Cromley Sts. (2/25/80)

Circleville.  Anderson, William
  Marshall, House, 131 W. Union St.
  (11/29/79); 80/01/10079 0006419

Circleville Historic District, Main and
  Court Sts. (5/16/78)

Memorial Hall, 165 B. Main St.
  (11/21/80)

Morris House, 149 W. Union St. (8/3/79);
  79-11-13 079 0004400

Circleville vicinity, Horsey-Barthelmas
  Farm, W. of Circleville on OH 104
  (7-24-80)

Lavndale Farm Complex, 26476 Gay
  Dreisbach Rd. (04/19/84)

Mount Oval (Tolbert House), Off U.S. 23
  (7/25/74) PH0071293

Peters, Stevenson, House, OH 188
  (02/09/84)

Redlands, 1960 N. Court St. (05/14/82)

Kingston vicinity.  Bellevue, N. of
  Kingston on OH 159 (3/17/76)

Marcy vicinity.  Fridley-Oman Farm,
  W. of Marcy in Slate Run Metropolitan
  Park (12/6/75)

South Bloomfield vicinity, Renick Farm,
  N. of Bloomfield on U.S. 23 (03/05/82)
Williatnsport vicinity.  Bazore Mill,
  S. of Williamsport on OH 138 at Deer
  Creek (12/19/78)

Williamsport vicinity.  Shack, The, NW
  of Williamsport (5/23/74) PH0071307

The following properties have been
  determined to be eligible for
  inclusion in the National Register.

Fairfield County

Lancaster, U.S. Post Office—Lancaster
  (10/28/83)

Richland, R.F., Baker Bridge, Thornville
  Rd. and Little Rush Creek; 78/11/13
  078 0055084

Franklin County

Columbus, Barber Shop, 82-86 E. Town
  St. (1204.3)

Beggs Building, 21 E. State St.

Bldg. at 736-40 East Long Street
  (02/17/84)

Central National Bank Building, 152-166
  S. High St. (1204.3)

Hartman Theater Building, 73-87 E. State
  St. (1204.3)

LaSalle Wine Store, 242-244 S. High St.
  (1204.3)

Oven, Jim, Real Estate, 232 S. High St.
  (1204.3)

Trailvays, 246-254 S. High St. (1204.3)

1000-02 S. High Street (63.3)

17-19 E. Stewart Avenue (63.3)

21-33 E. Stewart Avenue (63.3)

99 S. High Street (63.3)
                                     1-8

-------
Licking County

Health.  Digiondomenico Site (Ohio LIC
  343-0.00).; 78/11/15 078 0050632

Pickayay County

Darby township, Orient Bridge, OH 762
  over Big Darby Creek (63.3)

The following sites/structures are
  pending inclusion to the National
  Register.

FranklinCounty

Broad Street Apartments, East Broad
  Street MRA, 880—886 E. Broad St.,
  86003404 11/04/86

Broad Street Christian Church, East
  Broad Street MRA, 1051 E. Broad St.,
  86003448, 11/04/86

Cambridge Arms, East Broad Street MRA,
  926 E. Broad St., 86003412, 11/04/86

Central Assurance Company, East Broad
  Street MRA, 741 E. Broad St. 86003421,
  11/04/86

East Broad Street Commercial Building,
  East Broad Street MRA, 747, 749, 751
  E. Broad St., 86003424, 11/04/86

East Broad Street Historic District,
  East Broad Street MRA, Along E. Broad
  St.  between Monypenny and Ohio Aves.
  86003393, 11/04/86

East Broad Street Presbyterian Church,
  East Broad Street MRA, 760 E. Broad
  St., 86003397, 11/04/86

Garfield—Broad Apartments, East Broad
  Street MRA, 775 E. Broad St.,
  86003427, 11/04/86

Heyne—Zimmerman House, East Broad
  Street MRA, 973 E. Broad St.,
  86003450, 11/04/86

Hickok, Frank,  House,  East Broad Street
  MRA, 955 & 957 E. Broad St., 86003444,
  11/04/86
House at 753 East Broad Street, East
  Broad Street MRA,, 753 E. Broad
  Street, 86003425, 11/04/86

Jacobs, Felix A., House, 1421 Hamlet
  St., 86003434, 11/04/86

Johnson—Campbell House, East Broad
  Street MRA, 1203 E. Broad St.,
  86003414, 11/04/86

Joseph—Cherrington House, East Broad
  Street MRA, 785 E. Broad St.,
  86003429, 11/04/86

Kauffman, Linus E., House, East Broad
  Street MRA, 906 E. Broad St.,
  86003410, 11/04/86

Kaufman, Frank J., House, East Broad
  Street MRA, 1231 E. Broad St.,
  86003420, 11/04/86

Levy, Soloman, House, East Broad Street
  MRA, 929 E. Broad St., 86003427,
  11/04/86

Lovejoy, Carrie, House, East Broad
  Street MRA, 807 E. Broad St.,
  86003435, 11/04/86

Morris, C.F., House, East Broad Street
  MRA, 875 E. Broad St., 86003398,
  11/04/86

Frentiss, Frank, House, East Broad
  Street MRA, 706 E. Broad St.,
  86003396, 11/04/86

Prentiss—Tulford House, East Broad
  Street MRA, 1074 E. Broad St.,
  8603413, 11/04/86

Saint Paul's Episcopal Church, East
  Broad Street MRA, 787 E. Broad St.,
  86003430, 11/04/86

Schueller, Erwin V., House, East Broad
  Street MRA, 904 E. Broad St.,
  86003406, 11/04/86

Scofield—Saner House, East Broad Street
  MRA, 1031 E. Broad St., 86003447,
  11/04/86
                                     1-9

-------
Sharp—Page House, East Broad Street
  MRA, 935 E. Broad St.

86003445

86003449

ARCHAEOLOGICAL SITES

Delaware County

Powell vicinity.  Highbanks Metropolitan
  Park Mounds I and II, E. of Powell on
  U.S. 23 (3/19/75)

Fairfield County

Canal Winchester vicinity.  Schaer,
  Theodore B., Mound, SE of Canal
  Winchester (6/20/75)

Carroll vicinity, Coon Hunters Mound
  (5/2/74) PH0034797

Pinkerington vicinity.  Fortner Mounds
  I, II.  NE of Pinkerington (7/12/74)
  PH0034827

Tarlton vicinity.  Tarlton Cross Mound,
  N. of Tarlton (11/10/70) PH0034860

Franklin County

Columbus.  Campbell Mound (11/10/70)
  PH0094498

COE Mound, W. of High St. (7/18/74)
  PH0070203

Columbus vicinity.  Hartley Mound, N. of
  Columbus (7/15/74) PH0070297

Galloway vicinity.  Galbreath, John
  Mound, W. of Galloway (7/15/74)
  PH0070262

Georgesville vicinity.  Cannon, Tom,
  Mound (5/2/74) PH0070190

Worthington vicinity.  Jeffers, H.P.,
  Mound (5/2/74) PH0070327
Licking County

Granville vicinity.  Alligator Effigy
  Mound (11/5/71) PH0070891

Homer.  Dixon Mound (Williams Mound)
  (6/4/73) PH0070882

Reynoldsburg vicinity.  ETNA Township
  Mounds I and II, E. of Reynoldsburg
  off 1-70 (9/5/75)

Utica vicinity.  McDaniel Mound (5/2/7O
  PH0070939

Melick Mound, S. of North Fork of
  Licking River (3/27/74) PH0070947

Madison County

West Jefferson vicinity.  Skunk Hill
  Mounds (7/30/74) PH0060810

Pickaway County

Circleville vicinity.  Arledge Mounds I
  and II (7/30/74) PH0071285

Luthor List Mound (10/16/74) PH0034291

Fox vicinity.  Clemmons, W.C., Mound
  (5/2/74) PH0071315

Tarlton vicinity.  Horn Mound (8/7/74)
  PH0034304

Williamsport vicinity.  Tick Ridge Mound
  District, NW of Williamsport (6/11/75)
                                     I-10

-------
      APPENDIX  J
ARCHAEOLOGIC BACKGROUND

-------
                                  APPENDIX J
                            ARCHAEOLOGIC BACKGROUND

     The earliest evidence of human culture vithin the Scioto Drainage system
is evidenced by the Fluted Point Complex of the Palaeo-Indian Tradition, which
has been dated to between 18,000 and 10,000 years B.C.  This component,  the
Fluted Point Complex, is represented primarily by the surface recovery of
isolated Fluted Points (projectile points) and other characteristic artifacts
of this manifestation.

     The Fluted Point Complex is followed by the Piano Complex of  the Palaeo-
Indian Tradition, dating between 10,000 and 6,000 years B.C.  The  Piano
Complex is documented in the Scioto Valley by a series of isolated surface
finds of characteristic projectile point types including Lanceolate Points,
Sawmill Stemmed Lanceolate Points, and Stringtown Spurred-Stemmed  Lanceolate
Points.

     The known distribution of Piano Complex workshop sites centers in
Coshocton County in proximity to the outcrops of Upper Mercer Flint with a
secondary center in Licking County adjacent to the heavily utilized Flint
Ridge Flint.  These raw materials were used in the manufacture of  the vast
majority of Lanceolate-style projectile points.  The distribution  of excavated
sites and surface finds in this region would be along major stream valleys.

     The Archaic Developmental Stage spans the time interval from  ca. 8,000 to
1,500 years B.C.  In part, the Piano Complex and the earliest manifestations
of the Archaic stage overlap in time.

     The Archaic Development Stage is evidenced by two cultural traditions
throughout the Scioto Drainage system:  the Appalachian Archaic Tradition
(8,000 to 3,500 years B.C.) and the Laurentian Archaic Tradition (3,500 to
1,500 years B.C.).

     The Kirk Phase of the Appalachian Archaic Tradition has been dated to
between 8,000 and 7,000 years B C., while the St. Albans Phase dates to
between 7,000 and 6,100 years B.C.  The majority of sites are situated within
the low terraces of the major stream valleys—in environmental zones that have
been reconstructed as bottomland hardwood forests.
                                     J-l

-------
     The distribution of Kirk and St. Albans Phase components is rather veil
known for the Scioto Drainage south of Circleville.  Stray surface finds of
Kirk Corner-Notched and St. Albans Bifurcated-Base projectile points were
recovered along both the east and vest banks of the Scioto River in southern
Franklin County.  However, it was not possible to define either clusters of
artifact occurrence or to define sites on the basis of this analysis.  The
only evidence for Archaic Stage (6,000 and 3,500 years B.C.) occupation of the
Scioto Drainage has come from the surface recovery of several well-defined
projectile point types, either as isolated surface occurrences or from
occurrences in raulticomponent surface manifestations.

     The Laurentian Tradition represents the most recent of the Archaic
Development Stage manifestations within Ohio.  The various components of the
tradition have been radiocarbon dated to between ca. 3,500 years B.C. and
prior to 1,500 years B.C.  In this region, one phase of the tradition has been
defined:  the Dunlap Phase of the Laurentian Tradition within the central and
lower Scioto Valley.  Sites occur as both open sites and within rock shelters
in the eastern portion of Ohio.  The majority of open sites are situated in
close proximity to the then-contemporary shorelines of water sources (lakes,
bogs, swamps, and streams).

     The Glacial Kame Manifestation represents a poorly understood series of
archaeological remains that are contemporaneous with the terminal portion of
the Laurentian Tradition.  The manifestation is known primarily from the
discovery of human burials that occur deep within shaft graves excavated into
glacial kames, usually elevated over adj'acent stream valleys.  Sites of the
Glacial Kame Manifestation do occur in both Pickaway and Franklin Counties.

     The Scioto Tradition spans the time interval from 1,500 years B.C. to ca.
900 years A.D.  Three phases of the Scioto Tradition have been defined.  The
three major manifestations include the following:

     a.   Adena Phase (Early Woodlands),  dating from 1,500 years B.C. to 1
         A.D./B.C.
         This phase represents the earliest manifestation of the Scioto
         Tradition within the Scioto Drainage.   The majority of manifestations
         have been dated to between 1,500 years B.C. and 1 A.D./B.C., although
                                     J-2

-------
    components predating 1,500 years B.C. are known from both the Hocking
    River and Ohio River Valleys.  Only four Adena Phase burial mounds
    are known from Franklin and Pickaway Counties.

    The Adena Phase mortuary ceremonial manifestation is evidenced by one
    site occurring within a 10-kilometer radius of the Southerly tftfTP.
    Typical burial mounds of the Adena Phase represent small structures
    covering less than 20 inhumations located on high terraces and/or
    bluffs overlooking major stream valleys.  The settlement pattern of
    the Adena Phase, known for limited information, consists of small
    villages or hamlets (2 to 10 structures) scattered along the low
    terraces and flood plain of the stream valleys.  One large habitation
    site—the Dominion Land Company Site in Franklin County—has been
    reported.

b.  Hopewell!an Phase (Middle Voodland), dating from ISO years B.C. to
    650 years A.D.

    This phase of the Scioto Tradition has been dated to between 150 B.C.
    and 650 A.D.  The greatest concentration of sites occurs in the
    Scioto River Valley between Circleville and Portsmouth.  The concen-
    tration of Hopewellian earthworks occurs in the Scioto Valley and its
    tributaries south of Columbus.

    Within the central and lower Scioto Valley, Hopewellian hamlets
    appear to be composed of two to four structures (houses) situated on
    rises of the flood plain and first terrace of the Scioto River and
    the major tributary stream.

    Four Hopewellian Phase sites are known to be in the vicinity of the
    Southerly VWTP project area.

c.  Chesser Phase, Peters Phase, Cole Complex (Late Voodland), dating
    from 650 to between 900 and 1,000 years A.D.

    The subsequent portion of the Scioto Tradition consists of a series
    of regionally defined phases:  the Peters Phase in the Hocking
    Valley, the Chesser Phase in the lower Scioto Valley, the Cole
    Complex in the upper Scioto Valley, and the Licklighter Phase in the
    Miami Valley.  These various Late Voodland phases occupy a time
    interval that has been radiocarbon dated to between 650 and 950 to
    1,000 years A.D.

    The Cole Phase (also known as Cole Complex) has been defined by Baby,
    Potter, and their co-workers for the upper portion of the Scioto
    Valley (Circleville to Columbus) and for the Darby Creek, Upper
    Scioto, and Olentangy Drainages.

    The terminal portion of the pre-European culture history of the
    Scioto Drainage is dominated by the Fort Ancient or Mississippian
    Tradition.
                                J-3

-------
Fort Ancient Tradition settlement patterns consist of large nucleated
villagest frequently oriented around vacant plazas or areas con-
taining platform or "temple" mounds and frequently defined by
palisades.  Villages are most frequently located in close proximity
to major streams and on rises within the flood plain, or on first
terraces of the stream valleys; frequently in close proximity to the
richest of the available soils.

A total of seven Late Voodland Mississippian manifestations are known
to occur in the vicinity of the Columbus Southerly project area.
Nearly all adjacent manifestations are knovn only from the results of
the phase II survey.

The terminal portion of the prehistoric sequence within the Scioto
Valley—the time interval from 1650 to 1680 until Anglo-European
settlement during the 1780s and 1790s—is poorly known from both the
archaeological and historical literature.  Only one site has been
excavated from this time interval—the Morrison Site from the Scioto
Valley south of Chillicothe.

In summary, the Scioto Drainage system has been used by a succession
of prehistoric cultures and prehistoric populations for over 18,000
years.  Many of these cultural manifestations are well represented
within the region.

A phase I and phase II survey of the Southerly WWTP in 1985 revealed
four prehistoric sites.

-------
            APPENDIX K
POPULATION PROJECTIONS AND METHODS

-------
                                  APPENDIX K
                      POPULATION  PROJECTIONS AND METHODS

 Introduction
      This  appendix presents  past  population  trends  of  the overall  planning
 area  as  well as  the proposed interceptor  areas.  The overall  service area
 covers most  of Franklin County,  including all  of the City of  Columbus as well
 as  small portions  of Delaware, Fairfield, and  Licking  Counties.  This review
 outlines baseline  data  used  in evaluating population projections and for
 estimating the relative attractiveness  for development of various  communities
 within the planning area.

      Most  of the available population projections have not been prepared for
 small areas  and  the detailed information  required for  accurate small area
 projections  is not  available.  The  1980 census provides the baseline for the
 trend analysis used to  prepare all  of the regional  population projections.
 Because  growth between  1970  and  1980 was  less  than  expected and the  growth
 between  1980 and 1985 was greater than  expected, the Ohio Department of
 Economic Development, which  prepares the  State population estimates  at the
 Ohio  Data  Users  Center  (ODUC), has  revised its official estimates  three times
 since the  1980 U.S.  Census.  The  most recent estimate  was published  and
 verified in  September of 1985.  Both the Mid-Ohio Regional Planning  Commission
 (MORPC)  and  Ohio Environmental Protection Agency (OEPA) prepare population
 estimates  for small areas; that is  counties, cities, and  unincorporated areas.
 These two  agencies  have not  revised their population estimates to  reflect  the
 most  recent  ODUC projections.  Therefore, these small  area projections do  not
 reflect  the  most recent State-approved  projections.  The  Revised Facility  Plan
 Update (RFPU) considers these revisions, but does not  reflect the  region's
 most  recent  growth  trends.

Revised  Facilities  Plan Update Projections
      Population  levels were  forecast for the year 2015  in  the RFPU.   Besides
 the year 2015 population, used for planning purposes,   the  population  in 1988
also was evaluated  by this RFPU because the Clean Water Act Amendments mandate
compliance by all wastewater treatment  facilities with NPDES permit  limits by
                                     K-l

-------
 July 1,  1988.   The following  sources  of population data and existing projec-
 tions were   reviewed  prior  to development of RFPU projections?

      o  Environmental Impact  Statement (EIS) for Wastewater Treatment
         Facilities for the  Columbus Metropolitan Area  (US EPA 1979);
      o  Design  Finalization Overview  Team Report (AWARE 1984);
      o  Facilities Plan Update Report (Malcolm Pirnie  1984);
      o  Growth  Potential Report  (City of Columbus 1984);
      o  Ohio Department of  Development, Data Users Center, State and County
         Projections (June 1982);
      o  Ohio Department of  Development, Data Users Center, Draft Final
         Population Projections (August 1985);
      o  Traffic Zone  Projections - 1980 and 2010 (Mid-Ohio Regional Planning
         Commission 1983);
      o  Franklin County projections developed by the Design Parameters Team as
         a check against other projections;
      o  Miscellaneous  Facilities Plan and Facilities Plan Segment documents
         pertaining to  sewer service areas;
      o  Ohio Environmental  Protection Agency, Office of the Planning
         Coordinator, Water  Quality Management Plan Projections  (1977, 1982).

As the preceding list  indicates, numerous sources using various methodologies
were  used to make  population  projections in the RFPU and the Consolidated
Environmental Information Document (BID).  For the purpose of this EIS,  the
population projections prepared by the Ohio Data Users Center (a division of
the Ohio Department of Development) and the OEPA were  reviewed and adjusted to
reflect  the overall service area for 1988, 2000, and 2008.

Ohio  Data Users Center Projections
     The ODUC prepares the official population projections for the State of
Ohio.  ODUC bases  its  recent  projections on the 1980 U.S. Census, and historic
trends for migration, births,   and deaths.  The projections reviewed in this
EIS were revised in September  1985.  These projections were prepared on  the
county and state level, for the years 1980 through 2010   A preliminary
accuracy check recently was conducted by ODUC for their Franklin County
                                     K-2

-------
forecasts.  During  this  check,  the  population  estimates  were well within the
accepted statistical  confidence level  with  an  error  rate of  less than 2
percent.

     Table K-l shows  ODUC's  population projections for the State of  Ohio and
the  four counties in  the service area  for 1980 through 2010.   This table shows
that the State of Ohio will  decrease over the  30-year period while the
population in Franklin County as well  as the other counties  in the service
area will increase.

     ODUC is responsible for certifying population projections prepared within
the State.  In 1982,  after several  public hearings,  ODUC certified OEPA's
Planning and Engineering Data Management System for  Ohio (PEMSO)  population
projections.  The OEPA prepared its projections for  selected service areas on
the  township, village, and county levels    These projections were prepared
before  the 1980 U.S.  Census  was released, and  therefore  are  based on the 1970
U.S. Census and the growth trends exhibited in the area  prior to  1980.
Although the methodology employed to make these projections  is sound,  the
growth  between 1970 and  1980 was less  than  expected.  And the growth between
1980 and 1984 was larger than expected.
           TABLE K-l.  POPULATION PROJECTIONS FOR THE STATE OF OHIO
                 AND THE  COUNTIES IN THE COLUMBUS SERVICE AREA

Ohio
Delaware
Fairfield
Franklin
Licking
1980
10,797,630
53,840
93,678
869,132
120,981
1990
10,681,863
61,709
98,655
924,592
127,390
2000
10,583,083
71,381
104,033
975,013
132,154
2010
10,398,338
81,164
107,577
1,026,008
136,765
Source:  (ODUC, 1985).
                                     K-3

-------
     Table K-2  lists  the  service area population by county as a percent of  the
 total  county  population for  the same time period.  This  table indicates that
 most of  Franklin County's population (over 99%) will be  located in  the service
 area.  Less than I  percent of Fairfield's population and an average of 3
 percent  of Delaware and Licking Counties will be included in the service area.

 Ohio Environmental  Protection Agency Projections
     Table K-3  compares OEPA's projections with ODUC's by county for  1980,
 1985,  and 2000.  This  table  indicates that ODUC currently assumes a slightly
 higher growth rate  for Franklin County  than OEPA used in its earlier
 forecasts.  ODUC'S  projections are based on the 1980 U.S. Census and  show a
 higher 1980 population in  Franklin County than OEPA.  In fact, OEPA's earlier
 forecasts underestimate the  1980 Franklin County population by 56,000 persons.
 OEPA uses higher growth rates for Fairfield, Delaware, and Licking  Counties
 than ODUC.  This results  in  higher overall population estimates by  OEPA for
 these counties.

     OEPA acknowledges that  its 1982 PEMSO estimates may not reflect  an
 accurate picture of the service area population and has  attempted to  modify or
 revise these estimates.  However, since the 1982 estimates are the  only
 numbers  that have been certified by the State, OEPA cannot release  the revised
 version of these estimates.  The growth rates used for Franklin County are
 similar for both OEPA  and  ODUC; this analysis will assume that if OEPA's 1980
 population is adjusted to  reflect the 1980 U.S. Census,  then the two
 projections will be more closely aligned.  This adjustment, referred  to
hereafter as OEPA (adj.),   is reflected in Table K-2 as part of the  comparison
 for Franklin County.   Since  Fairfield,  Delaware, and Licking Counties combined
comprise 1 percent of  the  total service area population  in 1980 and 2 percent
of the total service area  population in 2015,  no adjustments were made for
 these counties.
                                     K-4

-------
           TABLE K-2.  OHIO EPA-PEMSO PROJECTIONS FOR THE COLUMBUS SERVICE AREAS
Service Area
by County
Columbus
Franklin
Delaware
Licking
Subarea Total
Baseline 1980
1970/77 Projected
787,062
1,149
845
789,056
789,089
1,616
1,020
791,725
1985
802,857
1,928
1,120
805,905
1990
820,946
2,276
1,218
824,440
1995
834,634
2,663
1,305
838,602
2000
869,006
3,131
1,375
873,512

Canal Winchester
Franklin
Fairf leld
Subarea Total
OEPA notes that the
Franklin
Backlick Creek
Franklin
Fairfield
Licking
Subarea Total
Service Area Total
3,420
9
3,429
1980 population
12,137
526
1,643
14,306
794,128
4,016
8
4,024
for Canal
17,246
587
2,233
20,066
815,815
4,801
8
4,809
Winchester was
19,210
634
2,602
22,446
833,160
5,898
8
5,906
37 in Fairfield
22,891
684
3,007
26,582
856,928
7,353
8
7,361
and 2,712
23,746
735
3,421
27,902
873,865
8,384
8
8,392
in
25,426
786
3,831
30,043
911,947
Source:  Ohio Environmental Protection Agency Computer Print Out 1982
PEMSO-  Planning & Engineering Data Management System for OHIO

-------
             TABLE K-3.  COMPARISON OF POPULATION PROJECTIONS BY
                      COUNTY FOR THE COLUMBUS, OHIO AREA
County
Source
Franklin
ODUC
OEPA
OEPA (adj.)**
Fairfield
ODUC
OEPA
Delaware
ODUC
OEPA
Licking
ODUC
OEPA
1980
869,132
812,670
869,132
93,678
82,401
53,840
54,779
120,981
125,943
1985
898,345
829,523
887,400
96,120
87,972
57,693
62,320
124,394
137,648
2000
975,013
906,903
971,700
104,033
106,180
71,381
87,810
132,154
162,791
2015*
1,048,000
974,900
1,044,600
109,000
128,500
86,500
123,500
138,000
187,000
 *This estimate is a simple extrapolation of OEPA and ODUC projections based
  on previous growth rates and rounded to 500.
**OEPA figures were increased to reflect the 1980
  complete explana11on).
U.S. Census (see text for
Comparisons
     Using the proportions shown in Table K-4 ODUC's county-wide population
estimates were adjusted to reflect the OEPA estimate of the service area
populations.  Table K-5 compares OEPA's PEMSO estimate with ODUC's estimates
adjusted to reflect the service area boundaries, and with the OEPA (adjusted)
estimates.  A straightline extrapolation was used to estimate the 1988 and
2008 populations.  When this table is compared with Table K-6 RFPU population
projections, it shows that ODUC and OEPA (adjusted) estimates are higher than
the RFPU.  The difference between the two projections is less than 2 percent
                                     K-6

-------
which is within an acceptable range for statistical error.  This sets the
service area population at a high of 1,020,000 and a lov of 950,400 in 2008.
This figure is at most 23,000 individuals greater than the revised service
area projections shown in Table K-6.  These population figures will serve as a
baseline for estimating the growth that would be likely to occur without the
construction of the interceptors.

Revision of RFPU Projections
     The RFPU used the Mid-Ohio Regional Planning Commission's (MORPC) traffic
zone population projections as the initial data base for developing the
overall and subservice area population projections.  MORPC's traffic zone
system is based on a network of roadway intersections developed in the 1960's
and was updated between 1974 and 1980.  This network is based on land use and
traffic patterns and is able to predict population projections, changes in
land use and transportation needs.  These projections are a disaggregation of
the ODUC projections for Franklin County.  As a result of ODUC's 1985
revisions, MORPC is revising its projections.  MORPC will increase its 2010
population projection from 941,341 to 1,027,341 (1,026,000 is the ODUC
estimate) for Franklin County.   This increases the forecast population in
Franklin County by 86,000 individuals by 2010.
                                     K-7

-------
               TABLE K-4.   POPULATION DISTRIBUTION BY COUNTY FOR
                           THE COLUMBUS SERVICE AREA
County/Service Area               1980            1985            2000
Franklin
Total Population
Service Area Population
% of total
Fairfield
Total Population
Service Area Population
% of Total
Delaware
Total Population
Service Area Population
X of Total
Licking
Total Population
Service Area Population
% of Total

812,670
810,351
99.7*

82,401
595
.7%

54,779
1,616
3.0*

125,943
3,253
2.6*

829,523
826,868
99.7*

87,972
642
.7*

62,320
1,928
3.1*

137,648
3,722
2.7*

906,903
902,816
99.5*

106,180
796
.7*

87,810
3,131
3.6*

162,791
5,206
3.2*
Source:  OEPA, PEMSO Projections, February 1982.
                                     K-B

-------
          TABLE K-5.  COMPARISON OP POPULATION PROJECTIONS BY COUNTY
                        FOR THE  COLUMBUS SERVICE AREA
                                                                  Increase
                                                                  Between
    Source                1988          2000         2008         2000-2008
     ODUC                925,900        982,600    1,018,000      35,400
     OEPA                848,600        911,947      950,347      38,400
     OEPA (adj.)         902,200        976,130    1,052,900      41,000
Source:  Interpolation of Tables K-l, K-2, K-3, K-4.
                                     K-9

-------
         TABLE K-6.   REVISED FACILITY PLAN UPDATE  POPULATION FORECASTS
Service Area
   1980
Service Population
1988      2000
2015
Jackson Pike (1980 Bdry.)
Southerly (1980 Bdry.)
West Scioto (a)
Big Run
Darby Creek
Grove City
Minerva Park
Sunbury-Galena
Big Walnut
Black lick
Groveport
Rickenbacker AFB
Rocky Fork
467,153
324,336
(b)
(b)
(b)
15,941
(b)
(c)
(b)
(b)
(b)
(b)
(b)
487,644
336,633
(b)
(b)
(b)
16,601
2,063
(c)
(b)
21,904
3,436
2,146
(b)
500,294
360,834
31,072
(b)
(b)
17,490
2,187
(c)
(b)
31,034
3,499
2,146
3,305
511,035
372,344
42,564
(b)
(b)
22,571
2,265
(c)
(b)
35,091
3,542
2,146
3,601
TOTAL
807,430    870,427   951,861   995,159
NOTES:

(a)  A significant portion of the Upper Scioto West Interceptor presently is
     served by temporary pump stations and force mains that discharge to the
     Upper Scioto East Interceptor.  This service area population is included
     in the 1980 and 1988 service population of Jackson Pike.  By the year
     2000, this service population is deducted from the Jackson Pike service
     area and allocated to the West Scioto service area, reflecting
     construction of the Upper Scioto West Interceptor Sever.

(b)  Area not served during projection period.

(c)  Area excluded from analysis.  No service planned.

Source:  URS Dalton 1986.
                                    K-10

-------
                APPENDIX  L
                   DRAFT
                CRITIQUE OF
       WATER QUALITY MODELING ISSUES
          FOR THE COLUMBUS, OHIO
SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT

-------
                        Draft


                    Critique of
         Water Quality Modeling Issues
             for the Columbus, Ohio
Supplemental Environmental Impact Statement
                   August 31,1987
                     Submitted To:
        U S Environmental Protection Agency, Region V
                230 South Dearborn Street
                 Chicago, Illinois 60604
                     Submitted By
         Science Applications International Corporation
                  8400 Westpark Drive
                 McLean, Virginia 22102
           EPA Contract No 68-04-5035, D.O. #040
             SAIC Project No 2-813-06-193-40
                         L-1

-------
                                     1. Introduction

   The Columbus Supplemental EIS (SEIS) is being prepared to evaluate the current facilities
planning information for the City of Columbus Key provisions of the current facilities plan for
Columbus include*
      o  Upgrading and expansion of the Southerly wastewater treatment plant (WWTP)
      o  Phase-out and ultimate abandonment of the Jackson Pike WWTP, and
      o  Re-routing of Jackson Pike flows to the Southerly WWTP

Future facilities planning activities will address the issue of CSO control at the Whittier Street
storm tanks overflow The two wastewater treatment plants operated by the City of Columbus
(Jackson Pike and Southerly) are projected to discharge almosHSO mgd of treated effluent to
the Scioto River by the year 2008

   A simplified graphic of the locations of point source discharges and  riverine features in the
Columbus area is provided below
                                                                       y
                                       River Mile 132
                            Whittier Street Pumping Station
                                           River Mil* 129
                                      Jackson Pike POTV
                                            River Mil* 127

                                          Southerly POTW
                                             River Mile 118

                                             River Mile 117
                                            L-2

-------
   Facilities planning activities for the City of Columbus, including future (but as yet
unspecified) modifications for CSO control at Whittier Street, involve decisions which will
directly impact water quality in the Scioto River  These decisions include

      o  Locations of effluent discharge outfalls
      o  Quantity of treated effluent released from each outfall, and
      o  Extent of wastewater treatment prior to discharge

Due to the Federal government's participation in the proposed project (through the USEPA §201
grant), and the potential for the proposed project to result in significant impacts on the
environment, an environmental review is required  This review is necessitated in the USEPA
procedures for implementation of NEPA

   Results of current and future facilities planning activities will directly affect the three
major point sources (Whittier Street, Jackson Pike and Southerly) which presently influence
water quality in a 30 mile stretch of the Scioto River, in the Columbus area Because of this
direct relationship between facilities planning decisions and the quality of the aquatic
environment, it is essential that these aspects of project impacts be carefully considered in the
SEIS.

   The most common approach to evaluating the water quality impacts related to a WWTP
effluent discharge is through application of a water quality model  The USEPA relies on models
to determine the need for upgrading wastewater treatment plants beyond secondary, and whether
Federal grant monies may be used for such purposes  As an evaluative tool, the model provides a
mathematical simulation of the naturally-occurmg physical/chemical processes which
biodegrade, or assimilate, wastes in the receiving water  Through such mathematical
representations, models assist managers in determining whether proposed improvements in
wastewater treatment processes will provide significant benefits to the water quality of the
receiving waters

   Typically, initial model development is followed by a process of model calibration and
verification, with site specific field data, to ensure that the model is faithfully characterizing
and reflecting natural conditions  At this point, individual variables (such as effluent quantity,
quality or total wasteload) can be selectively modified to predict and evaluate the impacts
(positive or negative) on water quality in the receiving water Permitted effluent limits can
then be established for the discharger Such limits reflect a quantification  of the total excess
wasteload assimilative capacity of the receiving water which is allocated to the subject
discharger (generally, the total available assimilative capacity is not allocated to  a single
discharger).

   As an aid to the establishment of wasteload allocations (WLA) and related permit discharge
limits, a water quality model was initially developed for the Scioto River, in the Columbus
vicinity, by the Ohio EPA (OEPA), using QUAL2 (a commonly used, reliable framework) Based
on this model, the OEPA proposed permit limits for the Jackson Pike and Southerly POTWs, in
the Comprehensive Water Quality Report (CWQR).

   The original QUAL2 model was later updated, by a consultant to the City (URS Dalton), and


                                             L-3

-------
transformed to a QUAL2E format, which is operable with PC hardware The updated model was
then used to derive alternate wasteload allocations and discharge limits, which were proposed by
the City to OEPA  These alternate allocations and limits were accepted by OEPA and sent to USEPA
in an amended CWQR.  To date, the amended CWQR has not been approved by the USEPA, however
the discharge limits have been approved The discharge limits in the amended CWQR are the
basis for the current facilities planning efforts and a key component in the SEIS evaluations

   Therefore, in order to determine if the proposed project will significantly impact the quality
of the natural environment, it is necessary to determine the accuracy of the wasteload
allocations and resultant discharge limits. This determination is made through examination of
the reasonableness of variables and assumptions on which the model was constructed, and
through assessment of the reliability of these variables and assumptions to represent natural
conditions

   Preliminary evaluations conducted as part  of the SEIS have questioned a variety of the
variables and assumptions used in the QUAL2E model and resultant discharge limits. Although
these questions are currently unresolved, they include technical input variables to which the
model is especially sensitive  Collectively, these questions seriously undermine the reliability
of the current model

   In the following sections, the questioned model input variables and assumptions are identified
and discussed
                                            L-4

-------
                                  2.  Technical Issues

   This section includes an identification of specific model input variables and assumptions
whose reliability is considered questionable, as a result of preliminary SEIS review efforts

21   Existing Modeling

   Two attempts were made at developing a water quality model for the Scioto River near
Columbus, Ohio  The first model was developed by the OEPA using the computer program QUAL2
(SEMCOG)  This model was calibrated with water quality data collected during a July, 1982
"intensive survey", and verified with similar data collected in August, 1981  The second
modeling effort was conducted by the City of Columbus and its consultant, URS-Dalton  An
updated version of QUAL2, QUAL2E (enhanced), was used in the second effort

   The major difference between the two efforts, other than the computer program employed,
was that URS incorporated a term to account for the production of oxygen by the benthic
(attached) algae that staff members observed growing in the river during a field reconnaisance
survey in September, 1985. The OEPA had not included the effects of benthic algae or
phytoplankton  in its earlier (QUAL2) model of the Scioto

   Two major problems are associated with the existing water quality modeling  The first
problem is that steady state modeling frameworks (le, QUAL2  and QUAL2E) were applied to
stream conditions that were essentially not at steady state  The second major problem stems
from the use of a benthic photosynthesis oxygen production term  In constructing both models,
rate constants were derived through analysis of field data on physical/chemical parameters in
the river However, comparison of the field data and the resulting calibration and verification
plots has indicated that acceptable fits to DO data were not obtained in either study

   Other problems include inappropriate or incomplete consideration of ammonia data, other
nitrogen species, phytoplankton, and cross-sectional profiles

2 2   Steady State Modeling Framework.

   Modeling frameworks such as QUAL2 and QUAL2E are normally applied to situations in which
none of the state variables (the concentrations of DO and other water quality constituents) or
"forcing functions" (effluent and boundary BOD. nitrogen loadings, etc) vary at any given
location with respect to time, i e, when the system is at "steady state" However, it is often
acceptable to apply steady state models to certain  non-steady  state situations  For example,
steady state models are often used to model estuaries  However, the model is constructed with
data gathered at high or low slack tides, and is therefore tidally-averaged  In this way, any
error introduced by using a steady state framework to model a dynamic, periodically varying
estuary is reduced.

   Similarly, in streams, when a state variable such as DO varies at specific locations due to
such dynamic processes as photosynthesis, error is introduced into the output of a steady state
model.  If such time variation in the inputs or state variables occurs, and steady state models are
the only practical tools available, care must be taken to consider the effects of any time variable

                                            L-5

-------
factors in order to minimize the model error resulting from the use of the steady state
framework As in the preceding estuarine example, error minimization is usually accomplished
by time-averaging the data over the period of concern (e g., periods of darkness, periods of
light)

   Non-steady state conditions occurred in the Scioto River near Columbus during the July,
1982 intensive survey  Streamflows were observed to decline steadily during this survey,
reflecting the effects of a moderate rainfall event which had occurred just prior to the start of
sampling. Therefore, background BOD and NOD loadings, and velocities and depths throughout the
system, were also declining  More significantly, a diurnal DO variation of greater than 2 mg/L
was measured at several of the sampling stations (as indicated in Figure 6-7 of the Central
Scioto River Mamstem CWQR) At several of the most downstream stations sampled,
supersaturated DO conditions occurred during the early evening hours  Thus, true steady state
conditions were not realized in the Scioto during the July intensive survey

   Steady state model error due to non-steady state effects, such as variable waste loading, can
be reduced by considering individual "plugs", or parcels, of water  In plug flow sampling,
unique parcels of water are followed and sampled as they move downstream, at intervals
according to the expected time of travel (determined from dye studies conducted concurrently, or
at similar streamflow)  Each plug is then treated as a separate water quality sampling run,
from which a predicted profile can be generated using the corresponding inputs However, no
data have been collected from the Scioto River from which such a plug flow model can be
developed

   No steady state model, no matter how carefully developed, will allow an accurate prediction of
the DO time series as impacted by photosynthesis  QUAL2E may be run in the dynamic mode,
which will allow the development of a model to predict the time-variable effects of
phytoplankton (but not penphyton algae) on the in stream DO and nutrient profiles  While
inputs and forcing functions (i e effluent and background Streamflows, BOD and NOD loadings,
and DO concentrations) must remain constant, the variation m stream DO concentrations due to
diurnal variation in algal photosynthesis can be simulated  However, QUAL2E does not have the
capability to properly simulate benthic photosynthesis which, apparently, may be quite
significant in the Scioto River  To successfully accomplish the simulation of benthic or
planktonic algae over time, detailed knowledge of the algae nutrient uptake kinetics and
light-growth relationships are required This knowledge is preferably gained from
site-specific studies which, in the present case, are lacking for the intensive survey periods  In
an attempt to compensate for these deficiencies, literature information would have to be used as
initial values for most of the parameters

   In both existing versions of the model, all of the observed DO data points for the four-day
survey were used in calibrating the model  However, these DO values were taken from samples
collected in both the morning and afternoon hours  Simultaneously calibrating to both morning
and afternoon DO observations resulted in the underprediction of the afternoon, and
overprediction of the morning, DO profiles  Only 11  of 50 observations were from the morning,
and none were from before 9 30 am  Since most of the DO values used for calibration were from
the afternoon hours, when DO will be at its highest level of the day, the resulting predicted DO
profile was skewed towards a higher level than it probably should have been. This procedure


                                            L-6

-------
disregards the night and early morning hours, when DO is usually at its lowest level. (Note that
the DO concentration measured at river mile 118 5 at 9-30 am on July 21.1982 was 3 9 mg/l,
which was the lowest value observed during the entire  survey)  In the URS model (QUAL2E),
inclusion of the benthic photosynthesis term resulted in an even higher mean DO profile than the
OEPA model (QUAL2), based on the same sampling data

   As an alternative, it might be appropriate to segregate the water quality data with respect to
the date and time sampled, i e to "time-average" the data The use of a steady state model could
then be better justified, perhaps by calibrating separately to morning (low DO) and afternoon
(high DO) observations, or by assigning weights to each observation so that a more realistic
picture of daily average water quality values could be obtained   Actual mean parameter values
(e g , Kd, Kn, etc.) could be better estimated in this way, and more accurate predicted profiles
could subsequently be generated

2 3   Benthic Photosythesis Term in QUAL2E.

   The QUAL2E model is an improvement over the earlier QUAL2 model in that it recognizes the
need to include the effects of algal pertphyton on DO in the Scioto River  It is apparent from the
URS data that, at times, these attached algae can significantly impact the observed DO profile  in
the river  However, the URS model incorporates a negative sediment oxygen demand (le; benthic
oxygen production)  There are numerous pitfalls associated with the use of a negative sediment
oxygen demand (SOD) term in the URS model

   URS' experiment was conducted over a two day period beginning September 25,1985
During this period, it was generally sunny, but periods of clouds and rain occurred on the 26th
During the penods of cloud cover on the 26th, a net consumption of oxygen was measured in the
DO chambers, which would be expected.  During the sunny periods, a net production of oxygen
was observed By plotting the change in DO in the chambers and bottles over time, URS derived
slopes, in mg/L/min, of the oxygen depletion curves  It is not stated whether these slopes
represent averages over the entire experimental period, or instantaneous maxima.  However,
only the results of the experiments on September 25, when a net production of oxygen was
occurring, were used to calculate the "overall" net 24 hour SOD of -1.74 g/m2/day (the
negative sign implies a net production of oxygen)

   The applicability of this SOD rate to a model calibrated with data collected three years prior
to these experiments must also be questioned Stream conditions,  such as substrate composition
and   nutrient availability to adequately support benthic algae growth, can change in three
years, especially in a relatively small, waslewater-dommated stream such as the Scioto Also,
the sunlight conditions that greatly influence the rate of oxygen production were much different
during the July 1982 study period  URS reports that sky cover ranged from 0% to 100%
during the survey period  However their SOD rate was derived from an experiment conducted
only during bright sunshine.  In addition, the experiments were conducted at only one station,
located between the Jackson Pike and Southerly discharges This rate was applied to all of
reaches in the model, except in those reaches where the predicted DO greatly exceeded
observed values  In those cases, the SOD term was arbitrarily removed in order to "fit" the
observed DO data
                                            L-7

-------
   Finally, there is also the difficulty in determining a "design condition14 SOD rate for use in a
WLA model No precedent or EPA guidance exists in applying a ne1 benthlc oxygen production
term for use in a WLA model.  Before using a term in the model which has little or no literature
justification, and which appears to have been used mainly to better fit the data representing
higher DO concentrations, additional data collection should be required to support its use

2 4   Other Significant Problems

   In addition to the major technical problems discussed in the preceding sections, several
additional problems are noted  These additional problems are discussed in the following.

2 4.1    Phytoplankton Influence on DO Profile

   Neither model accounted for the influence of phytoplankton on the DO profile of the river
This is especially apparent m the lower reaches of the Scioto (below river mile 109) where
significant populations of phytoplankton apparently caused supersaturated DO conditions In
addition, elevated ultimate CBOD values were also observed beginning at river mite (RM) 109
Chlorophyll a samples taken in September, 1982 during a diurnal DO study conducted by OEPA
indicate that this section of the river is probably impacted  by an active phytoplankton
population   (In bottle BOD tests, the presence of algae in the samples can increase the measured
ultimate BOD considerably over that which is traceable directly to wastewaters) However, the
OEPA CWQR  mentions that "algal simulations were not performed.  With the information
available, the QUAL-II model could not be accurately calibrated to the Scioto River."

   URS attempted to incorporate the effects of phytoplankton in their WLA analysis, and a
sensitivity analysis of the effects of phytoplankton on the DO profile under design wasteflow
conditions was conducted  The analysis showed that an increase in DO of only 014 mg/L would
be expected if  the phytoplankton population were to increase from 0 to 100 ug/L This
contradicts the July and September, 1982 data presented by OEPA, where significant increases
in afternoon DO were observed at the most downstream stations, correlated with high
chlorophyll a levels  URS provides no information in the report concerning values for algal
kinetics or cell  stotchiometry parameters used in the sensitivity analysis.

242    Nitrogen Species.

   The QUAL2E model does not appear to be successfully calibrated for NH3-N and NO2+NO3-N,
and organic N  was not modeled Figures 6-5 and 6-6 of the CWQR appear to indicate an
erroneous value for the nitrification rate coefficient  Observations for both ammonia and
nitrite-nitrate nitrogen are generally underpredicted  This  carries over, although to a
somewhat lesser extent, to the verification profiles for these variables given in Figures 6-9 and
6-10 of the CWQR. This could stem from not accounting  for  the effects of algal uptake on
nutrients in the model

   Organic nitrogen was not considered in either model  Organic N can hydrolyze to produce
ammonia, which can then be taken up by algae or oxidized by nitrifying bacteria  Inclusion of all
of the nitrogen  species, as well as the effect of algal uptake, may result in a closer
correspondence between observed and predicted values


                                            L-8

-------
2 4.3    Cross Sectional Profiles

   Cross sectional profiles provided by the OEPA do not indicate significant variation in cross
sectional area or depth  OEPA established 25 reaches based on times-of-travel, river cross
sections and flows observed during studies conducted in 1980-1981  Each of these reaches is
characterized by a unique power function for flow vs velocity and flow vs depth. However, none
of the information required to assess the flow-velocity or flow-depth power equations presented
in Table 6-2 (flows, times-of-travel, depths for each reach) is given in the report

   Flow vs velocity and flow vs depth relationships affect the model's internal calculation of
reaeration, and the rate of transport of pollutants through the system Therefore, it is critical to
properly define these relationships to correctly predict the DO response to changes in flow,
especially when determining the WLA However, predicted stream depths developed in the
QUAL2E model do not appear to correlate with actual field data  For example, if a flow of 150 cfs
is used, the depth equations for reaches 2 and 4 yield depths of 2 8 and 1 8 feet, while the
equation for reach 3 yields 0 7 feet  In contrast, based on observation of the profiles submitted
by OEPA, there do not appear to be any locations that were sampled that have a mean depth of less
than two feet.

   Since the shapes of the cross sectional profiles appear to be relatively uniform, it may be
more appropriate to divide the study area into fewer physical reaches, so that less variation in
depths is obtained. It is accepted modeling practice not to divide a stream system into any more
reaches than is necessary, especially if a general physical uniformity throughout the stream is
observed.
                                             L-9

-------
                       3. Conclusions and Recommendations.

   Based on the reviews conducted to date, it does not appear that an accurate and reliable
predictive model for use in assessing current and future environmental conditions has been
developed  This is most likely due to limitations in the available data, and to the inability of
QUAL2E to simulate diurnal 00 variations in the steady state mode  Specific conclusions and
recommendations concerning the existing water quality models are listed below

3.1   Algal Effects on DO

   The contribution of dissolved oxygen by algae to the stream DO balance is not usually
accounted for in determining assimilative capacity However, an attempt should be made to
factor the effects of algae on DO into the modeling for the Scioto River, using the September,
1982 diurnal DO data  Any assumptions on daytime oxygen production by algae must be balanced
against the catastrophic effects that nighttime respiration of these cells can have on DO, and
subsequently on stream biota

   A diurnat DO study was conducted in September, 1982  Some extremely (ow DO values were
observed, and most values recorded were below the 5 mg/L DO standard  However, the number
of samples and their times of collection were not reported in the Draft CWQR  The appropriate
data for developing an accurate and reliable model of algae in the Scioto for the July, 1982
survey are apparently not available Thus, it may be difficult to improve on either modeling
effort for that period, given the existing data set  However, it may be possible to use the diurnal
data collected during September, 1982 to formulate a model of the river which includes the
effects of algae on DO This data set should be analyzed for its potential use in model development.

3 2   Benthic Algae/SOD

   The effects of benthic algae on SOD should not be incorporated into the WLA model until a
more complete set of data is available  More studies similar to the URS SOD study should be
conducted before a term describing the benthic production of oxygen is incorporated into the
model. Due to the existence of the  Whittier Si CSO and periodic bypasses of the Southerly
WWTP, organic solids introduced into the river during storm events may settle out in the study
area and result, at times, in a benthic oxygen demand that exceeds the production of oxygen by
benthic algae. This needs to be considered in establishing a steady state net SOD term for use in
the model

3 3   Non-steady State Modeling

   The feasibility of using a non-steady slate modeling framework should be explored  USEPA
has developed WASP, a multi-purpose dynamic modeling framework that can be used to simulate
the effects of phytoplankton on nutrients and DO in streams as well as other types of water
bodies. The available body of data  should be examined carefully  to determine whether WASP, or
any other similar framework, may be a more appropriate tool for modeling the Scioto River
than QUAL2E

   Although WASP is more flexible  than QUAL2E, it is also more complicated and, therefore,


                                            L-10

-------
more costly to develop and utilize

3 4   Additional Data

   The feasibility of collecting an additional set of data should be examined  The shortcomings of
the available data upon which to build a valid water quality model for the Sctoto River have been
described by the OEPA and URS  The basic problem is that water quality samples were collected
without regard to plug flow in the system  Due to the time variability of DO in the Scioto during
low flows, the assumption of steady state (which is crucial to the successful utilization of
QUAL2E as the modeling framework) is invalidated

    Also, the depth and velocity vs flow relationships were developed for flows that may be
exceeded as a result of plant expansion in the future  New information collected at higher flows
in the Scioto would decrease the uncertainty in the results produced by these equations

3 5   Evaluation of Alternatives

   Because the existing models were developed under a two-discharge scenario, these models
should not be used to evaluate the one-plant alternative without further data collection and
modeling analysis  It is likely that, under a one-plant scenario, the water quality impacts of the
Southerly plant will extend even farther downstream during 7Q10 flow events than presently
occurs

   The existing  models extend downstream only to RM 103, near Circleville.  Beyond RM 103,
there is no information - physical, hydrologic or chemical - on which to base model
development  Furthermore, there are other large industrial discharges below RM 100 whose
effluent limits may be impaired by the downstream relocation of the DO sag likely to occur due to
the combination of flows in a one-plant scenario  This data deficiency needs to be corrected
before a reliable model of this section of the river can be constructed
                                             L-1 1

-------
             APPENDIX  M
U S  ENVIRONMENTAL PROTECTION AGENCY,
  WATER QUALITY  BRANCH, MEMORANDUM
   ON COLUMBUS WATER QUALITY MODEL

-------
  FROM

                  UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                                       REGION V
   DATE  SEP 30 1987

SUBJECT   Columbus,  Ohio Water Quality  Modeling
          Kenneth A.  Fenn,
          Water Quality

          Todd A. Caye/, Chief
          Municipal  Facilities Branch
          In response  to your memorandum  of September 9, 1987, regarding the
          water quality modeling  for Columbus. Ohio, my staff has reviewed the
          EIS consultant's  (SAIC) critique of the modeling work performed by
          OEPA and  later work completed by URS-Dalton for the City of Columbus,

          As you may know,  the  original OEPA two-plant modeling analysis for
          Jackson Pike and  Southerly was  reviewed by the Eastern District
          Office, the  Planning  and  Standards Section and our Permits Section.
          These offices found the original QUAL II analysis to be sound.

          OEPA effort  resulted  in the  following limits-

          Plant          River Mile       Flow       CBODt;

          Jackson Pike       127          110 MGD     5.2 mg/1

          Southerly          118          85 MGD     5.0 mg/1

          Subsequently, the City of Columbus employed URS-Dalton to model the
          Scioto River as a means of confinning the State's analysis and for
          exploring a one-plant alternative.  URS-Dalton employed lower flow
          discharge projections, and concluded that the following limits would
          achieve dissolved oxygen  and ammonia water quality standards:
          Plant

          Jarkson  Pike

          Southerly

          Jackson  Pike

          Southerly
   Time

 Pre-1992

 Pre-1992

1992-

1992-2015
  Flow

 60 MGD

 90 MGD
 CBODfi

8.0 mg/1

8.0 mg/1
   Decommissioned

156 MGD     8.0 mg/1      1.0 mg/1
          As you can see, the results are comparable, with a decrease in
          ammonia  that  allows slightly higher CBODs values.  We would also
          point out that these  limits approach those achievable with available
          technology.

                                       M-l
            3-78)

-------
                                -2-
 In terms of the critique by SAIC, we agree that model  calibration
 and verification would be improved with further work on stream
 hydraulics and algal kinetics.  However, we can make this same
 statement regarding virtually any other water quality model  in
 Region V and perhaps the rest of the Country.  Furthermore, it does
 not always follow that a better calibration of existing conditions
 would necessarily improve the prediction of future conditions.
 This is because future conditions wi 11 be dramatically different
 due largely to changes in hydraulics and the control of both point
 and nonpoint sources of pollution.  For these reasons, professional
 judgment is an overriding factor in developing and applying a water
 quality model.  The current model may have an error margin of
 +1.0 mg/1 of dissolved oxygen.  Given the complexity of the Scioto
 River in this area, we are not convinced that future modeling work
will either significantly reduce this error or significantly revise
the current effluent limitations.

We agree with the Environmental  Review Branch that further modeling
 of the one-plant vs. two-plant alternative seems counterproductive.
This is because reasonable estimates of the one vs. two-plant
approach are available to your staff.   We have endorsed the two-plant
analysis developed by URS-Dalton which is the basis for the current
 permit limits at each facility.

We also agree that OEPA may be able to provide additional professional
judgment if that is deemed necessary for the purpose of the EIS.
                           M-2

-------
            APPENDIX  N
THE INFRASTRUCTURE PROJECT 1985-1986
  FINAL REPORT   EXECUTIVE SUMMARY

-------
  DEVELOPMENT COMMITTEE FOR GREATER COLUMBUS
THE INFRASTRUCTURE PROJECT
          1985-1986
     FINALREPORT
         5DECEMBER 1986
              N-l

-------
                  "While the space directly beneath a
                support Us structure, the area under the


                surface of the streets and sidewalks is filled

                with the systems essential to support its

                occupants. The basic systems, which we


                caMflfes, include water, sewage removal


                and drainage, electricity, steam, gas, and

               telephone communication "

                              The quotation above  ft the
                            cover Illustration are from
                            UNDERGROUND  by David
                            Macaulay. Copyright  © 1976
                            by David Macaulay. Uted  by
                            permission of Houghton Mlfflln
                            Company.



                  "The nation's infrastructure  The physical


               framework that supports & sustains virtually


               all economic activity "
                              Definition by the National
                            Council on  Public  Works
                            Improvement
N-2

-------
                       CONTENTS
Extracts from the "GREATER COLUMBUS INFRASTRUCTURE INVESTMENT
REQUIREMENTS AND FINANCING STRATEGY:  THE NEXT FIVE YEARS"
(the Final Report of the DCGC 1985-1986 Infrastructure Project)
            EXECUTIVE SUMMARY
            Section VI. NEXT STEPS:
            IMPLEMENTATION             104 - 107
INFRASTRUCTURE MAPPING & INFORMATION SYSTEM
NOTE:  The Final Report of the DCGC 1985-1986 Infrastructure
Project will be distributed to all agencies which were
participants in the Project.
                               N-3

-------
                            EXECUTIVE SUMMARY
     The Development Committee for Greater Columbus undertook a major
study to assess the area's Infrastructure condition and to develop
strategies for keeping its capital facilities well managed and
maintained.  This report represents the final product of two earlier
reports written by The Urban Institute in February and September 1986.
The first report, Greater Columbus Infrastructure Investment
Requirements (Feb. 1986), evaluates capital facility performance and
determines capital investment requirements and funding availability over
the next five years for area roads, bridges, water, and sewer systems*
The second report, Financing Greater Columbus"3 Infrastructure (Sep.
1986), provides a detailed analysis of the area's options for financing
its capital program.  The present report represents a final statement of
this Greater Columbus Investment Strategy*

GREATER COLDMBDS'S CAPITAL PLANT

     o   Two indicators of performance — a street maintenance
         effectiveness index and resurfacing cycles — suggest that
         several jurisdictions are falling behind in road repair.  The
         City of Columbus, in particular, falls below a sample of other
         large cities In road performance, reflecting a fluctuating
         program of maintenance and repair.

     o   Jurisdictions with high ratings generally show short
         resurfacing cycles and more systematic programs of street
         resurfacing.

     o   Based on several performance measures, bridges in the county
         are generally In good condition.  Only 6 percent are
         structurally deficient, the potentially most serious bridge
         problem.  The older structures that fall largely under county
         responsibility, are in the poorest condition.

     o   Area water supply is adequate to the year 2000, provided
         additional sources are identified beginning in 1991v

     o   Area water distribution systems show low main breaks relative
         to other cities*  The level of unaccounted-for-water, at 20
         percent, is higher than average, but It is not out of line with
         older cities*

     o   The major performance problem facing the Greater Columbus area
         in sanitary sewers is the need to upgrade the City of Columbus'
         sewage treatment plants to meet EPA requirements.
                                  N-4

-------
     o   Condition of area collection systems appears  to be adequate.
         The City of Columbus and its suburbs fare well relative to
         other cities with respect to the number of main breaks  and
         sewer line back-ups.

     o   As a relatively new area of infrastructure concern,  information
         is not readily available on the performance of area stor* sewer
         facilities.

GREATER COLUMBUS'S CAPITAL INVESTMENT PATTERNS

     o   The majority of area improvements are slated  for expansion  (46
         percent) and upgrading (43 percent) of capital facilities.
         Only 11 percent of total Investment dollars are targeted for
         rehabilitation of existing facilities.  The City of Columbus,
         in particular, should consider a more balanced division of
         resources to insure that existing facilities  will be kept in
         good repair.

     o   Approximately half of projected investment requirements over
         the next five years can be met from available federal,  state,
         and local resources.

     o   The City of Columbus is responsible for nearly half of  the
         funding shortfall, not surprising in view of  the city's major
         role as provider of area highway services, water supply, and
         sewage treatment.  Nearly two-thirds of suburban investment
         projects, however, are also unfunded.

     o   The area shows large projected Investments of $454 million  over
         the next five years for roads, but only 18 percent Is slated
         for rehabilitation.

     o   Planned investment requirements for bridges over the next five
         years are small relative to other infrastructure areas.  The
         majority are for rehabilitation and upgrading.

     o   The City of Columbus system accounts for 90 percent of  total
         planned water Investments.  The majority of city investments
         are for supply improvements and system upgrading.  The  majority
         of suburban needs are for rehabilitation and  upgrading.

     o   Planned sanitary sewer Investments over the next five years
         represent the second largest spending area.  The majority of
         improvements are for upgrading, to meet Environmental
         Protection Agency requirements, and for expansion.  Only a
         small fraction of planned spending is for rehabilitation.

     o   Planned storm sewer investments over the next five years are
         the smallest of all of the Infrastructure areas.  However,
         since several studies are only now underway that could  lead to
         a  higher needs estimate.


                                 N-5

-------
 THE COST OF RKKKWIHG GREATER COLUMBDS'S CAPITAL FACILITIES:  REASSESSING
 THE AREA'S NEEDS

     The Development Committee for Greater Columbus (DCGC) and the Mid'
 Ohio Regional Planning Commission (MORPC) with guidance and Input from
 local area officials prioritized an initial list of capital projects
 according to several criteria such as funding availability, health and
 safety standards, and impact on the local community.  The effort
 produced a list of priority projects and an estimate of the funding
 shortfall expected for 1987-1991.

     o   Investment requirements across all infrastructure areas and
         Jurisdictions were reduced from $1.05 billion (1986-1990) to
         $946 million (1987-91).  The funding shortfall declined by 9
         percent, from $500 million to $457 million.

     o   Funding shortfall as a percentage of total planned capital
         investment is 48 percent.

     o   Sanitary sewer projects represent 39 percent of the total
         investment; storm sewers 2 percent.  Capital spending for water
         systems are 8 percent of the total.  Road and bridge
         improvement expenditures comprise 47 percent and 5 percent of *
         total investments, respectively.

     o   Sanitary sewers comprise about 35 percent of the total
         shortfall.  Road funding shortfalls account for 54 percent.

         Funding shortfalls in the water area amount to 2 percent;
         bridges 7 percent of the total shortfall.

     o   The shortfall as a percent of total investment requirements in
         each infrastructure area is greatest in bridges, at 67%,
         followed by: roads, 56%; sanitary sewers, 44%; storm sewers,
         31%; and water, at 11%.

     o   The City of Columbus comprises the bulk of total area
         shortfalls in roads, bridges, and sanitary sewers.  The growth
         suburbs account for most of area shortfalls in water systems
         and storm sewers*

FINANCING CAPITAL REQUIREMENTS

     o   Proposed financing mechanisms to support infrastructure
         requirements should be consistent with accepted public finance
         practice:  large scale investments should be debt-financed;
         debt issuance should be by jurisdictions with the greatest
         overall responsibility for area infrastructure; improvements
         should be paid for by those who directly benefit from the
         improvements.
                                  N-6

-------
The bulk of area road and bridge requirements could be
supported with modest increases in user charges: $10 increases
In license tag fees; a 2c per gallon local fuel tax; an
extension of the county sales tax to gasoline.

Other road and bridge funds required could be raised through
developer contributions, so that the increased capacity needed
to service growth is supported by those who create added
demand.

The Columbus area appears to have a strong claim on Increased
ODOT discretionary funds, which historically represent a
smaller share than total road mileage responsibility.

Most jurisdictions with water and sewer funding shortfalls
could support the required investment with increases over
current rates.  The remaining jurisdictions likely will have to
partially support Investment requirements through general fund
support.

The creation of a storm-water management district represents
the best avenue for handling the area's flood and drainage
investment requirements.

Institution of a comprehensive, automated, Infrastructure
mapping and Information system, including inventory, condition,
and Investment data across jurisdictions and sectors, would
encourage better infrastructure management, and ensure reduced
long-range capital requirements through improved maintainance
programming for existing infrastructure.
                       N-7

-------
                     VI.  NEXT STEPS:  IMFLEMKMTATIOH








      The  development of a comprehensive analysis of Greater Columbus*s



 infrastructure and financing opportunities represents the first step in



 a capital stock investment and management strategy.  The main objective



 lies  ahead: translating this strategy into concrete action.  This will



 require a coordinated effort to educate the public as to its Importance,



 secure authorization from the General Assembly for key steps in the



 financing plan, cement local cooperation regarding the choice and



 financing of capital priorities, and ensure the collection and automated



 storage of the information needed to wisely choose among capital



 projects, and between capital and maintenance expenditures.





 Taxpayer/Voter Approval



     The  financing plan contemplated in this report places on local



 highway and utility service users the responsibility for financing



 improvements to these same services*  In the area of roads and bridges,



 Increased fees and charges can support general obligation borrowing  by



 the County to support area-wide Investment.  This requires authorization



 of general obligation bond Issues by the Franklin County Commissioners,



 and approval by county voters.



     The  rate increases required to fund utility system Investments  do



not require general voter approval.  However, city  councils will have to



 support increases of the needed magnitudes to cover borrowing



 requirements, or authorize the expenditure of general  fund revenues to



 meet extraordinary Investment costs.  In contrast to the multi-



 jurlsdlctlonal approach needed to address area road and bridge



                                  N-8

-------
 Investment,  Increased funding for water and sewer investment is a
 decision for each system*  in each community.

 State Legislative Change
      The first  action required of the state is to modify the current
 limitation on the county vehicle license fee.  Instead of the current $5
 ceiling,  counties should be  allowed  to increase the license fee, either
 by a designated amount or  according  to locally perceived needs.
      State action also will  be required to permit local imposition of
 fuel taxes.   Since the 2c  Increase in the gasoline tax is the major
 source of planned new revenues to support road and bridge investment,
 this approach should  have  a  local priority.  In addition, the decline in
 fuel prices offers a  window  of opportunity to Impose an acMitional fee
 at  a time when  the impact  on consumers will be minimal.  Similarly,
 State approval  will be required to permit extension of the county sales
 tax to gasoline.   As  this  would not  represent an increase in the tax,
 but  an increase in the taxing base,  resistance to this approach should
 be somewhat muted.

Local Government  Cooperation
     Area governments  already have demonstrated willingness to cooperate
in a coordinated  infrastructure renewal effort by participating  in the
DCGC's Greater  Columbus  Community Capital Investment Strategy effort.
However, many specific project priorities remain to be negotiated, a
process requiring  continuing good will and cooperation among all
governments in  the  County*
                               N-9

-------
      A cooperative agreement will have to be negotiated between the City
 of Columbus and Franklin County  to determine the specific road and
 bridge projects to be  financed from a County bond issue, and the
 sequencing of repair work.  In addition, suburban jurisdictions will
 have to reach their own accomodation with the County In slating local
 road projects for renewal.  The  DCGC has a vital role to play in
 sustaining the areawide cooperation that has developed during this first
 project effort.
      The creation of a storm-water management district represents the
 best way to finance areawide flood and drainage improvements*  The
 structure  of  such a district remains to be worked out among the
 prospective participants, for example, the rights and terms of entry and
 withdrawal,  the  allocation of investment, and the type and level of
 service charges.   Though difficult, this process will result  in a secure
 mechanism  for storm-water funding.
Improved Coordination and Hanageaenc of Capital ««H Maintenance Spending/
     The overall Community Capital  Investment  Strategy  effort till now
has focused primarily on capital investment  needs  and funding
requirements.  The immediate  thrust of this  effort is to remedy any
investment backlogs, and ensure that the  facilities needed  to accooodate
new population and economic growth  are in place.   However,  the Columbus
area faces a unique opportunity to  reduce long-run capital  Investment
requirements.  The complex Interrelationship between ongoing maintenance
spending and capital improvements requirements is  long-recognized but
not always considered as a basis for action.   By acting now to improve
local infrastructure management, area jurisdictions can ensure that the
                                 N-10

-------
 existing,  and planned, capital stock is adequately maintained, thus



 forestalling more  costly  future  investments in Infrastructure renewal.



 The creation of a  comprehensive, multi-jurisdietional, automated



 geographic information and mapping system would be an important, indeed



 critical,  step in  Improved capital planning.



     Such  a system would  store and display Inventory and condition



 information, and combine  water and sewer distribution system



 information, street and bridge information, Including traffic data,



 zoning and land use data, demographic and economic information, and



 virtually  any other information  to allow an assessment of service demand



 for any infrastructure link.  With the addition of maintenance and



 repair history data, area infrastructure managers can plan for cost-.



 effective  maintenance investment, to ensure the longest useful life of



 any capital asset.  In addition, capital Investments across sectors can



 be coordinated to ensure  cost-effective repair and minimal disruption;



 for example, through the  sequencing of street repairs and water line



 replacement*



     The cost recovery period of an Investment in infrastructure



management system* can be quite  short.  The City of San Jose estimated



their system investment at $3.3  million, with annual operating  costs  of



$705,000.  The annual benefits expected were $995,000 for avoidance of



higher future replacement costs; $1,020,000 for increased maintenance



productivity; and $75,000 for reduced costs of tore settlements and



insurance*  The initial capital  investment would be repaid in 2.5  years.
                                N-ll

-------
            INFRASTRUCTURE MAPPING & INFORMATION SYSTEM
      A timely recommendation by the Urban Institute is for the
 "institution of a comprehensive, automated infrastructure mapping
 and  information system..."  The recommendation is considered
 timely due  to a great amount of interest locally and activity
 nationally  in such systems.  Variously known as a "Geographic
 Information System"  (CIS in Chattanooga, Tennessee), a "Mapping
 and  Geographic Infrastructure System" (IMAGIS in Indianapolis),
 "Mapping Oriented Information System" (MOIS at American Electric
 Power), "Automated Mapping/Facilities Management" (AM/FM for the
 U.S.  Air Force, Consolidated Gas Transmission Corporation of
 Clarksburg, West Virginia,...and others), or some combination,
 such  as AM/FM-GIS, in Seattle, the systems are basically similar.
 For  sake of simplicity, here and until a better acronym is
 devised - we will refer to the system as AM/FM.

     An important part of  the DCGC Infrastructure Project has
 been  gathering information concerning AM/FM.  We have found a
 wealth of experiences available for reference as the Greater
 Columbus community investigates developing an AM/FM system.

     Many agencies admit to having come to a realization that
 they are having difficulties and high costs in their mapping and
 information systems.

     These were well summarized by Peoples Natural Gas Company
of Pittsburgh as due to:

          "redundancy of data due to decentralized divisions!
     update delays to complete a record; difficulties in
     researching data due  to the independent maintenance of
     varying documents-, inadequacies for special applications
     such as network analysis; and expensive maintenance
     costs  since the effort was very labor intensive."

     They continue by stating:

          "The Peoples Natural Gas Company feels that a
     corporate Facilities  Information Management System
     with computer graphics has enormous potential.   Consi-
     dering the changing needs of the gas industry  for
     extensive record keeping, mapping and design, we must
     pursue means to improve the effort."

     Statements repeated often by utility companies and metro-
politan areas are that the high costs of AM/FM systems can be
made acceptable by forming coalitions and thereby sharing the
system and  costs.  Repeatedly, the experienced voices in  this
new industry of AM/FM urge adequate planning and project
definition  as being crucial to the success of an AM/FM project.

                              N-12

-------
     Some experiences have been of starting over, or regrouping,
as  stated in the following concerning Seattle:

          "The City of Seattle Joint Automated Mapping Project
     began as individual efforts by four separate City agencies.
     The City's Budget Office, recognizing their commonality,
     initiated this joint project.  The City is currently con-
     ducting a unique pilot project intended to develop cost
     estimates of conversion of the City's land and utility
     facilities data base and to provide a better understanding
     of AM/FM-GIS system capabilities and related implementation
     procedures and processes.  The pilot project was developed
     by the City participating agencies jointly following an
     evolutionary process.  The process of development of a
     request for proposal for a consultant to complete the pilot
     began with an agreement on goals and objectives, included
     identification of candidate applications and development of
     a pilot project approach, and concluded with a memo of
     agreement, or charter, between the agencies assuring
     commitment of adequate resources (dollar and personnel) to
     the pilot.  Key to the success of this process and to the
     success of the project itself, is the ability of project
     management to (1) maintain management commitment to the
     project, (2) continue an open communicative, synergistic
     decision process, and (3) assure sufficient resources in
     the leadership role.  With these factors, the cooperative,
     i.e., joint, nature of the project can be maintained through
     the pilot and into an implementation decision process.
     In summary, management commitment, an open process, and
     leadership support have forged a team effort from the
     initial set of individual agency, or turf, interests."

     In conclusion, we will report a statement from the Coachella
Valley Water District (California) Deputy Chief Engineer:

          "CAD is here to stay - AM/FM is on the way I

          When?  How soon?  No one has the answer today.  The
     only statement that can be made to a certainty is that
     AM/FM is as inevitable to the District and to all similar
     public agencies as data processing was 15 or 20 years ago."
                              N-13

-------
        APPENDIX 0

SEIS DISTRIBUTION LIST TO
PUBLIC GROUPS AND OFFICES

-------
Federal Agencies

U.S. Department of Agriculture
U.S. Department of Commerce
U.S. Department of Defense,
  Army Corps of Engineers
U.S. Department of Housing and Urban Development
U.S. Department of Health and Human Services,
  Public Health Service
U.S. Department of the Interior,
  Fish and Wildlife Service
  National Park Service
U.S. Department of Labor
U.S. Department of Transportation,
  Coast Guard
  Federal Highway Administration
Ohio Congressional Delegation,
  U.S. Senators
  U.S. Representatives

State of Ohio

Building Industry Association of Ohio
Office of the Governor
Ohio Office of Management and Budget
State Clearinghouse
Ohio Environmental Protection Agency
Ohio Department of Natural Resources
Ohio Department of Public Health
Ohio Department of Transportation
Ohio Department of Justice
Ohio Department of Economic and Commercial Development
Ohio Department of Energy
Ohio Water Development Authority
Ohio Department of Agriculture
Ohio Federation of Soil and Water Conservation Districts
Ohio Historic Preservation Office
Ohio Attorney General
Ohio Department of Parks and Recreation
Ohio Utilities Company
                                      0-1

-------
Local

Capital Square Commission
City of Bexley
City of Gahanna
City of Grandview
City of Grove City
City of Milliard
City of Reynoldsburg
City of Upper Arlington
City of Worthington
Clinton Area Commission
Columbus Dispatch
Columbus Health Department
Columbus Industrial Association
Delaware County Regional Planning Commission
Fairfield County Regional Planning Commission
Franklin County Farm Bureau
German Village Commission
Greater Hilltop Area Commission
Hamilton Township
Italian Village Commission
Logan-Union-Champaign Regional Planning Commission
Madison County Regional Planning Commission
Mid-Ohio Health Planning Federation
Mid-Ohio Regional Planning Commission
Near East Area Commission
Northeast Area Commission
Pickaway County Regional Planning Commission
Public Library of Columbus and Franklin County
Rickenbacher Air Force Base
South Linden Area Commission
University Area Commission
Village of Brice
Village of Canal Winchester
Village of Dublin
Village of Galena
Village of Harrisburg
Village of Johnstown
Village of New Albany
Village of New Rome
Village of Obetz
Village of Orient
Village of Pataskala
Village of Plain City
Village of Riverlea
Village of Urbanerest
Village of Valleyview
Village of West Jefferson
                                     0-2

-------
Public  Interest Groups

American Association  of University Women Great  Lakes  Basin
  Task  Force
Archaeological Society  of Ohio
Audubon Society of Ohio
Citizens for  a Better Environment
Citizens Advisory  Council
Citizens for  Good  Planning
Columbus Board of  Realtors
Environmental Clearinghouse,  Inc.
Environmental Defense Fund
Franklin County Health  Department
F.U.T.U.R.E.
Future  Farmers of  America
Greater Cleveland  Growth Association
Izaak Walton  League
League  of  Ohio Sportsmen
League  of  Women Voters  of Ohio
Natural Wildlife Federation
Nature  Conservancy of Ohio
Ohio Academy  of Sciences
Ohio Air Quality Development  Authority
Ohio Biological Survey
Ohio Chamber  of Commerce
Ohio Conservation  Foundation
Ohio Conservation  Fund
Ohio Electric Utility Institute
Ohio Environmental Council
Ohio Environmental Health Association
Ohio League of Conservation Voters
Ohio Natural  Areas Council
Ohio State University
Ohio Natural  Heritage Program
Ohio Sierra Club
Ohio Soil  and Water Conservation  Commission
Ohio Water Pollution  Control  Conference
Ohio Water Resources  Center
Sciota  Bass Anglers
Water Pollution Control  Federation
Water Resources Council
Wildlife Legislative  Fund

Interested Citizens

Complete list available  upon  request.
                                       0-3
• US GOVERNMENT PRINTING OFFICE 1987 542 876

-------