4
                   Handbook for
      o
t*.
                   Reviewing Contractor
                   Property Control Systems
                   How to review written property control systems
      ^            and conduct compliance reviews
      (V
                   United States
                   Environmental Protection Agency

                   May 1990
       en
       2                 HEADQUARTERS LIBRARY
       -                 ENVIRONMENTAL PROTECTION AGENCY
       >?                 WASHINGTON, D.C. 20460

-------
                                                             t .-^
0.0 ,w..isi  ;:.-<•

-------
                           Contents
             <•  Introduction
                Purpose and scope of the handbook	vii
                Contents in brief	vii
                About the handbook	vii
Section one. Program criteria	
             *  Chapter!.Policies
                Approach		3
                Written property control systems	3
                Compliance reviews  	4
Section two. Written property control systems	
             <ģ  Chapter 2. Reviewing a written system
                Assessing contract data  	11
                Applying the criteria	12
                Notifying die contractor	13
Section three. Site compliance reviews	•
             *  Chapter 3. Preparing for a review
                Introduction	21
                Determine sites and dates	21
                Select the team	22
                Notify the contractor	22
                Finalize the dates	22
                Make travel arrangements  	25
                Plan the review	'	25
                Prepare for the sample invert ories	26
             *  Chapter 4. Conducting or  iew
                Introduction  	27
                                                                   Hi

-------
Contents
                 Entrance interview	, .  .27
                 Sample inventories	. .  .28
                     Acquisition	35
                     Receiving	36
                     Identification and records	37
                     Storage and movement	38
                     Property consumption	39
                     Utilization  	40
                     Maintenance and calibration  	41
                     Physical inventory	43
                     Subcontract administration  	44
                     Reporting	45
                     Disposal  	46
                     Contract completion or termination	47
                 Closing the review	50
                 Exit interview   	52
               * Chapter 5. Reporting the findings
                 Report features	53
                 Preparing and submitting the report	.54
               <ģ Chapter 6. Follow-up procedures
                 Approach	„	55
                 Informal telephone follow-up   	55
                 Scheduled written follow-up	55
                 Follow-on review	56
Section four. Desk reviews	
               <* Chapter 7. Conducting a desk review
                 Introduction   	59
                 Plan the review	59
                 Notify the contractor	59

-------
                Conduct the review  	60
                Document the findings	62
Appendix	
             * A. Random sampling
                Definition	65
                Application	65
                Selecting the sample items  	65
                Random Number Table 1  	70
                Random Number Table 2	71
             * B. Selected sampling
                Definition	72
                Application	72
                Selecting the items	72
             * C. Categories of property control
                Definitions  	74
             * D. Sensitive Hems list
                Dollar value from $300 to $999	76
             + E. Property administrator addresses
                Addresses	77

-------
Contents
   1
   2
   3
   4
   5
   6
   7
   8
	Figures	

 Sample Compliance Review Schedule   	8
 Summary of Compliance Review Steps	20
 Organizing the Review	23
 Overview: Conducting the Review   	29
 Physical Inventories	30
 Records to Review  	33
 Optional Records Review Form	34
 Inventory Analysis Form  	69
     CAP
     FAR
     GFP
     M&TE
     PCMD
     RTP
               Acronyms
         Contractor-acquired property
         Federal Acquisition Regulation
         Government-furnished property
         Measuring and test equipment
         Procurement and Contracts Management Division
         Research Triangle Park, NC
vi


-------
                          Introduction
Purpose and scope of the handbook
                This handbook was developed to standardize and detail the pro-
                cedures for reviewing contractors' written property control sys-
                tems and conducting compliance reviews. It establishes criteria
                for the compliance review program, defining policies and stand-
                ards. The handbook also serves as a hands-on guide that can be
                used as a training manual, reference document, or a workbook.

Contents in brief	

                The handbook is made up of four sections and an appendix. The
                sections consist of program criteria, written property control sys-
                tems, site compliance reviews, and desk reviews.

                In the appendix, you will find a description of random sampling
                and selected sampling procedures and a list of sensitive item
                categories. The addresses and telephone numbers of the con-
                tract property administration offices are also provided for quick
                reference as well as the definitions of the 12 categories of proper-
                ty control.

About the handbook

                If you have any comments about tins handbook, or if you want
                additional copies, please contact the Chief, Property Manage-
                ment Section (Security and Property Management Branch,
                Facilities Management and Services Division) at FTS-382-2144
                or by mail at PM-215, Headquarters.
                                                                      ou

-------


-------
                                                         Section one. Program criteria
                               Policies
                                  Chapter 1
Approach
                 The property control system review program has been estab-
                 lished to ensure that contractor-held government property is
                 being adequately cared for and controlled by EPA contractors.
                 The policies described in this handbook will be in effect begin-
                 ning in Fiscal Year 1991 for new contracts and existing con-
                 tracts with at least two years remaining under the contract
                 period (using the maximum expiration date).

                 All EPA contractors with government property under their
                 contracts, regardless of the dollar value of that properly, are
                 required to have property control systems in place (48 CFR
                 45.104). EPA is required to approve or disapprove all property
                 control systems. The approval of a contractor's property control
                 system is based on an evaluation of the contractor's written sys-
                 tem or the contractor's operating procedures.

Written property control systems	

                 A written property control system is required of each contractor,
                 unless the property administrator determines that maintaining
                 a written system is unnecessary. The property administrator
                 should consider the following factors to determine the need for a
                 written system:
                 •  Dollar value of property
                 •  Number of property items
                 •  Contractor's scope of work
                 •  Complexity of system required to control property
                 •  Anticipated future acquisitions
                 If a written system is deemed unnecessary, the property admin-
                 istrator must prepare a written justification for the file. All con-
                 tractors controlling property valued at $500,000 or more are
                 required to submit written property control systems.

-------
Chapter 1. Policies
                  Program administration
                  For each contractor possessing government property, the EPA
                  contract property administration office that administers the
                  highest dollar value of property for that contractor is designated
                  as the lead office. The lead office is responsible for reviewing
                  and approving the contractor's written system.

                  Before approving a contractor's system, the lead office should
                  notify the other offices (secondary offices) administering proper-
                  ty for that contractor. It is the responsibility of the secondary
                  offices to review the contractor's written system for unique
                  requirements dictated by their contracts and to submit com-
                  ments to the lead office before the system review date. The lead
                  office should send the secondary offices copies of all correspon-
                  dence concerning the contractor's property control system.

                  Property control system register. To facilitate coordination
                  among the offices, a central property control system register will
                  be maintained by the Headquarters Property Management Sec-
                  tion. At a minimum, the register will list all EPA contractors,
                  contract numbers, dollar value of property, number of property
                  items, approval status of the property control system, and the
                  responsible contract property administration office. The register
                  will be updated quarterly and distributed to the contract proper-
                  ty administration offices.

Compliance reviews	

                  Compliance reviews are required to verify that contractors are
                  complying with FAR and contract requirements, and are operat-
                  ing in accordance with their written property control systems
                  (when applicable). A compliance review may be a site review
                  (conducted at a contractor's facility/site) or a desk review
                  (records are reviewed at the reviewer's office and telephone
                  interviews of contractor staff may be conducted).

                  Authority
                  The authority for the compliance review program is established
                  in 48 CFR 45.511, stated below.
                     The Government may audit the contractor's property con-
                     trol system as frequently as conditions  warrant. These
                     audits may take place at any time during contract perfor-
4 Compliance reviews


-------
                                        Section one. Program criteria
   mance, upon contract completion or termination, or at any
   time thereafter during the period the contractor is required
   to retain such records. The contractor shall make all such
   records and related correspondence available to the
   auditors.

Scope
Compliance reviews must be conducted of all EPA contractors in
possession of government property authorized under an EPA
contract. The reviews will cover the following areas of property
control:

• Acquisition               • Maintenance and calibration
• Receiving                • Physical inventory
• Identification and records  • Subcontract administration
• Storage and movement    • Reporting
• Property consumption      • Disposal
• Utilization                • Contract completion/termination
This handbook presents the Tninim^m requirements for evaluat-
ing a contractor's operating procedures. A review need not be
limited to the points listed in each category of property control
(in chapter 4). The contractor's scope of work will determine
whether additional areas should be examined, such as motor
vehicle management, reporting of leased property, and installed
property.

Approach
It is the responsibility of the property administrator designated
in the contract to ensure that compliance reviews are conducted
in accordance with the policies and procedures described in this
handbook. To ensure consistent treatment by the Agency, it is
important that EPA property administrators approach com-
pliance reviews in the same manner. This handbook should be
used as the guide for establishing a compliance review program
and for conducting the reviews.

The process should be kept as simple as possible, adhering at all
times to the bottom line: are the contractor's operating proce-
dures adequate to ensure the proper care and control of govern-
ment property? Are they within the boundaries of the FAR,
contract requirements, and sound business practices?

-------
Chapter 1. Policies
                 The Government establishes the minimum requirements on
                 which contractors base their procedures. Determining how to
                 meet those requirements is the contractor's responsibility; in
                 other words, how they do it is their business, as long as they are
                 meeting the nrnniTrmm requirements.

                 Criteria
                 The criteria for conducting compliance reviews are described in
                 this section.

                 Contractors subject to review. Compliance reviews will be
                 conducted of all EPA contractors in possession of government
                 property, subject to the limitations outlined in this section of the
                 handbook. Reviews are required whether the Government or the
                 contractor maintains the official property records, and regard-
                 less of the approval status of the contractor's property control
                 system.

                 Frequency of reviews. Standards for the frequency of reviews
                 have been established based on the dollar value of property, as
                 outlined below.

                 High dollar value ($500,000 and greater). Annual compliance
                 reviews must be conducted of contractors in possession of
                 government property valued at $500,000 and greater. A site
                 review must be conducted once every two years, and a desk
                 review must be conducted every other year, (on the off year)
                 when a site review is not conducted. A site review may be con-
                 ducted more frequently than every other year if conditions war-
                 rant, at the property administrator's discretion.

                 Low dollar value (less than $500,000). For contractors with less
                 than $500,000 in government property, a site compliance review
                 or a desk review must be conducted once every three years. If
                 the contractor does not have an approved property control sys-
                 tem, the review must be conducted in the first year of the con-
                 tract. The property administrator should consider the following
                 factors when determining the frequency and type of review: dol-
                 lar value of property, number of property items, complexity of
                  system, risk to the Agency, and past performance such as
                  contractor's responsiveness to reporting requirements and infor-         ĢL | _
                  maticn requests.

6 Compliance reviews

-------
                                            Section one. Program criteria
     Follow-on reviews may be conducted when the Agency's assets
     are significantly at risk.

     Contractors with multiple contracts. If a contractor has
     more than one contract with EPA, the contractor's overall sys-
     tem is reviewed if that contractor has a centralized organiza-
     tion. If the contractor's organization is decentralized, however, a
     compliance review should he conducted for each contract. It is
     the property administrator's responsibility to determine the
     nature of the contractor's organizational structure.

     Contractors with multiple sites. When a contractor has more
     than one site under a contract, the property administrator must
     decide which locations to visit. (For example, some Superfund
     contractors have a central office, regional office, and multiple
     sites.) The property administrator should do what is simplest,
     most cost effective, and still ensures the control of government
     property. Considerations include the location and dollar value of
     the property, access to the site (some sites are at remote loca-
     tions), and the company's organizational set-up (where the
     property is located vs. where the contact person and tile records
     are located).

     Program administration. Each contract property administra-
     tion office should prepare a compliance  review schedule on a
     quarterly basis, projecting the schedule for the next six-month
     period. In other words, the current quarter's schedule is updated
     every quarter and the next quarter's projected schedule is
     added. Figure 1 on the next page provides a sample schedule.

     The lead office is responsible for conducting the required com-
     pliance reviews. Secondary offices should provide any comments
     or input before the review is conducted. Copies of all reports and
     correspondence with the contractor concerning the compliance
     review should be sent to the secondary offices.

     In both reviewing contractors' written property control systems
     and conducting compliance reviews, it is essential that the con-
     tract property administration offices communicate with each
     other to ensure the effective control of government property being
     held by contractors.
                                 Section two. Written property control systems
Reviewing a  written system
                    Chapter 2
    This chapter presents a set of criteria for the evaluation of a
    contractor's written property control system, as well as guidance
    for applying the criteria. The purpose is to provide standards
    that will allow the consistent evaluation of written systems by
    EPA property administrators.

-------
Figure 1
                 58
                II
      8
      1
                         I
                              CO
                       <  m   o   •<  m o <

                       S3  Ģ,   ^   S  8 8
                                        o
                                        X
5 5
                       ģ Ģ   a    5
                                   J
                                   I
                         8 S S

                                                  °
                                                    o
                                                    <.
            ca  O
            §
                   Q
                   o
               &5   o
            *••  it*   "Ģr
                                                         I
          8
                                      I
                           o co  Ģe   o o
                                                                    .1
3K
S

                             mil
                                                                                          * K Ģ
     Chapter 2. Reviewing o written system
                       If the property administrator determines ttiat a written system
                       is not required, a written justification must be prepared for the
                       file, outlining the reasons for the determination.
     Applying the criteria
                       The criteria are provided in checklist form on page 14 in this sec-
                       tion of the handbook. The checklist was designed to allow the
                       reviewer to check off items that are covered by the system, and
                       to reference the page number if desired.

-------
                                                          Section two. Written property control systems
                            • Does this meet the nniiitTn\iTn requirements that are outlined
                               intheFAR?

           Notifying the contractor	

                            EPA is required to notify the contractor in writing of the
                            approval of the property control system. After reviewing a
                            contractor's system, send a letter advising the contractor of the
                            following:
                            • Approval status, such as:
                               • Changes must be made before approving the system.
                               • Approval is contingent on specific conditions.
                               • System is approved (state the basis for the approval-
                                 review of written system and compliance review, for
                                 example).
                            • General and specific comments about the system.
                            • Due date for completion of revisions to the system. Remem-
                               ber to follow up with an approval letter after the revisions
                               are submitted and the system is approved.
                            Use the following general guidelines when commenting on a
                            contractor's system.
                            D Focus on substance. Limit your comments to the substance of
                               the system. Avoid editorial or grammatical comments such
                               as typo's, organizational problems, or wording (unless there
                               is an impact on the control of government property).
                            O Don't tell the contractor what to say. State the deficiency and
                               identify the requirement. Example: Don't simply tell the con-
                               tractor to add a phrase (such as, add "and resolve discrepan-
                               cies with the vendor.") Re-word the comment so that you are
                               stating the deficiency and identifying the requirement: "Your
                               system does not identify follow-up measures for discrepant
                               shipments. Your procedures must enable you to track and
                               resolve discrepancies with the vendor."
                            D If a contractor includes more detail in the system than is
                               required, you must comment on any erroneous information.
                               (Example: the contractor includes a glossary of terms, with
" I                             incorrect definitions of "sensitive item" and "accountable
                               property." Even though these definitions are not required by
                               our criteria, you must comment on the incorrect information.)
                                                                                     13

-------
Chapter 2. Reviewing o written system
          Criteria for reviewing written property control systems


                 Acquisition
    Pg.#	    O The acquisition of accountable property, whether purchased,
                    furnished, or leased for more than 60 days, is authorized.
    Pg. #	    Š Existing government equipment on-hand is screened before
                    submitting requisitions.

                 Receiving
    Pg.#	    O Property received is inspected for content accuracy and
                    condition.
    Pg.#	    Š Receiving report adequately describes property and is
                    prepared and distributed to appropriate offices.
    Pg.#	    Š If quantity, condition, or description differs from that shown
                    on the shipping document, the discrepancy is documented in
                    writing. Follow-up actions are documented and annotated on
                    receiving document.

                 Identification and records
[Hj  pg.#	    O Equipment received is promptly classified and labeled with
                    EPA property decal.
    Pg.#	    Š Auditable inventory control and financial records are estab-
                    lished and maintained for the property.
    Pg. #	    Š Basic information is contained in the records, as outlined in
                    the FAR (see Guide, pages 27 - 29).

                 Storage and movement
    Pg.#	    Š An adequate system to control movement and location of
                    property is maintained.
    Pg.#	    Š Property in storage is protected, preserved, and inspected to
                    prevent loss, damage, and deterioration.
    Pg #	    Š Adequate safeguards are provided for securing government
                    property.
         	     Š A first in/first out system is established for stored items sub-
                    ject to age deterioration and warranty expiration.
 14 Criteria

-------
                                                Section two. Written property control systems
                  Property consumption
O  Pg.# _    Ž  Property is consumed only under contract performance.
    pg.# _    @  Stock record system is maintained for consumable items.

                  Utilization
    pg.$ _    O  Methods are established to ensure that government property
                     is utilized only for purposes authorized by the contract.
    pg.# _    €>  Contractual authorization is obtained to use property for
                     other than its original authorized purpose.
    pg.# _    Š  A system is established to review and identify government
                     property for release when it is no longer required for contract
                     performance.
    pg.# _    O  Criteria are established and retention of idle equipment is
                     documented and justified by the program manager.

                  Maintenance and calibration
    pg.# _    O  A scheduled maintenance program is established, consisting
                     of a systematic written procedure for servicing and inspect-
                     ing equipment to  ensure safe, efficient, and economical opera-
                     tion of government equipment.
    pg.# _ __    €>  A calibration control system is designed for all measuring
                     and test equipment (M&TE) to provide control of the evalua-
                     tion, calibration, maintenance, repair, and use of M&TE.
    Pfl.# _    @  Records are kept of maintenance and calibration performed,
                     including cost and date.
                  O  Maintenance and caUbration are performed by technically
                     qualified personnel.
    pg_# _    0  System is capable of identifying high maintenance costs for
                     review; corrective action is taken by management and is
                     documented.
                  Physical Inventory
     pg.# _    O Physical inventories are conducted at the start of the con-
                     tract, annually on the anniversary of contract award, on a
                     special basis if directed by the Government, and upon con-
                     tract completion or termination.
     Pg.# _    Š Physical inventories are conducted using the floor-to-records
                     approach.
                                                                           15

-------
Chapter 2. Reviewing a written system
    Pg.#	    Š Physical inventory results are promptly reconciled with
                     properly records.
    pg.#	    Š Inventory results and discrepancies are promptly reported to
                     the property administrator.

                  Subcontract administration
    pg.#	    O Procedures and controls are established to assure that
                     government property in a subcontractor's possession is ade-
                     quately protected.
    Pg.#	    Š Subcontractor is aware of contractual property provisions.
    Pg.#	    Š Subcontractor will report property transactions to the prime
                     contractor for notification of die properly administrator.

                  Reporting
    Pg,#	    O Inventory reports are provided to the property administrator
                     on the anniversary date of contract award.
    Pg.#	    Š EPA Form 1730-1 is submitted for all accountable contractor-
                     acquired property to include purchased, leased (if leased for
                     more than 60 days), and installed property; receipt of
                     government-furnished property is reported to the properly
                     administrator when the property is received.
CU  pg.#	    Š Any loss of or damage to government property is immedi-
                     ately reported to the properly administrator.
    pg.#	    0 Government property excess to the contract requirements is
                     promptly reported to the properly administrator.
    pg.#	    Š Retention of government property with low utilization rate is
                     justified and annually documented in writing. Must be jus-
                     tified by the project officer.

                  Disposal
    pg.#	    Š Disposition instructions provided by the property admin-
                     istrator are carried out as  directed.
    pg.#	    Š In accordance with instructions, the disposal of property is
                     properly documented.
    Pg.#	    Š A decontamination certification is prepared for all properly
                     subject to disposal actions.
                                                                                       *. ~
 16 Criteria

-------
                                                            Section two. Written property control systems
            D  Pg.#.
           D  Pg.i
Contract completion or termination
O Residual property is reviewed for appropriate action (such as
   decontamination or repair) before transfer or disposal of
   property.
Š A full accounting is effected of all government property (to
   include nonexpendable property regardless of cost and
   expendable supply items and materiel not consumed during
   contract performance) in posession of the prime contractor
   and the subcontractor. The final inventory report is sub-
   mitted promptly so that disposal of the property may be
   carried out in an orderly fashion.
i ģ
                                                                                        17

-------
*  i

-------
                                                  Section three. Site compliance reviews
                  Preparing for a review
                                 Chapter 3
Introduction
                 Preparing for a compliance review is a process consisting of a
                 series of steps:
                     Determine sites and dates
                     Select the team
                     Notify the contractor
                     Finalize the dates
                     Make travel arrangements
                     Plan the review
                     Prepare for the sample inventories
Determine sites and dates
                 On a quarterly basis, the property administrator prepares a com-
                 pliance review schedule, projecting review dates and locations
                 for a six-month period. During the planning process, the prop-
                 erty administrator considers the following elements in selecting
                 the specific sites.
                   O Dollar value of properly
                   O Location of property and records
                   D Accessibility of site(s)
                 To set the review dates, consideration is given to the factors
                 listed below.
                   O Number of days needed to conduct the review (one or two
                      individuals should be able to conduct a review within
                      three days)
                   D Travel time
                   D Proximity to other review sites

                 To keep costs at a minimum, reviews are scheduled by location,
                 not by contractor. For example, assume ABC Company and XYZ
                 Associates each have offices in Chicago that must be reviewed.
                 ABC also has a site to review in Kansas City. To reduce costs,
                 the two Chicago offices would be reviewed in one week, while

-------
Chapters. Preparing for a review
                 the Kansas City trip might be scheduled for a week when .
                 another contractor is being reviewed in the Kansas City area.

Select the team	

                 The property administrator selects the review team, which is
                 usually made up of two people, and designates a team leader.
                 Ideally, the team members are familiar with the contractor's
                 property control system, scope of work, and the status of prop-
                 erty under the contract.

Notify the contractor	

                 A letter from the property administrator to the contractor's
                 point of contact serves as formal notification of the compliance
                 review. The letter is sent six weeks before the scheduled review
                 and covers the information outlined below.
                 H Review dates.
                 H Brief explanation of the purpose of the review.
                 EI Scope of the review.
                 33 Description of the files and documentation that should be
                    available for review.
                 H Names and positions of the review team members.
                 EI Request for the name, telephone number, and location of a
                    contact point for the review.
                 H Request for a copy of the most recent inventory by location
                    (specify the due date for receipt of the inventory listing).
                 H Name and telephone number of EPA representative to con-
                    tact regarding the review.
                 Hotel and airline/train reservations may be made at this point.
                 Do not finalize the reservations, however, until the dates have
                 been confirmed.

Finalize the dotes	

                 The dates for the review may be finalized by calling the contrac-
                 tor for confirmation if a letter has not been received. Be sure the
                     Note: A contractor's failure to submit the inventory listing does not
                     result in the review's cancellation.
  U.S.
  HAIL
D
22 Finalize the dotes


-------
                                            Figure 3
         Organizing the Review
     vvvvvvv
               Determine sites
               and dates
                         Select review
                         team
    NEWS
                Notify contractor
                          Finalize review
                          dates
              Plan site
              visit
                             Review team
                             coordination
-• *
              416935 -I .
              638IS1 ,l\ -I
              749262
              •74926B •I
Prepare random
sample

-------
It   ._

-------
                                                   Section three. Site compliance reviews
                 contractor submits the requested inventory listing before the
                 review date.

Make travel arrangements	'

                 As soon as the review dates are confirmed, travel arrangements
                 are finalized. The team leader is responsible for ensuring that
                 travel arrangements are made in the most efficient, cost effec-
                 tive manner. Whenever possible, the review team travels on the
                 same flight and stays in the same hotel. Arrangements need to
                 be made for.
                 * Hotel
                 4- Airline or train reservations
                 •>• Rental car, if needed

Plan the review
                 Planning. The property administrator determines which
                 categories of the contractor's system to focus on, taking the fol-
                 lowing factors into consideration:
                 • Types and dollar value of property

                 • Complexity of contractor's written property control system

                 • Risk to the Government
                 • Past judgments of the adequacy of the system

                 Preparation. To prepare for the review, the team examines the
                 contract files and any related documents pertinent to the con-
                 tract under review. It is important to look over these materials
                 in order to determine what is required for the contractor to
                 protect and control government property under an EPA con-
                 tract. The review team examines the materials listed below.
                 • Written property control system
                 • Contract (property clauses and scope of work)

                 • Contract modifications

                 • Delivery orders

                 • Subcontracts
                 • Most recent inventory
                                                                          25

-------
Chopter 3. Preparing tor a review
                 • Pending property actions (such as contract modifications,
                    property justifications, and transfers)
                 • Correspondence with the contractor
                 Before the review, the property administrator ensures that the
                 following objectives are met.

                 • Each team member has access to background materials and
                    has received a copy of this handbook.
                 • Team members understand the purpose of conducting a com-
                    pliance review and understand their roles during the review
                    process.

                 • The inventory listing submitted by the contractor has been
                    reconciled with the PPAS records.
                 • The random sample (records-to-floor) inventory form is com-
                    pleted before the review.
                 • Travel plans are coordinated and confirmed.

Prepare for the sample inventories	

                 One of the methods for collecting information during the review
                 is a records-to-floor inventory of randomly selected accountable
                 property items. The inventory may be recorded on an inventory
                 analysis form which is completed before the review. You may
                 also conduct a selected sample inventory of other than account-
                 able items. The forms should be completed before the review.
                 Please turn to the appendix for instructions and an explanation
                 of these processes.
                 *•* Remember to take the completed records-to-floor inventory
                    analysis form with you on the review, as well as blank forms
                    for the floor-to-records inventory. A copy of the form is
                    provided in appendix A.
26 Prepare for the sample Inventories

-------
                                                 Section three. Site compliance reviews
                  Conducting  a review
                                Chapter 4
Introduction
                 This chapter provides a detailed description of the steps for con-
                 ducting a site compliance review. The chapter is organized in sec-
                 tions, presented in the basic sequence that should be followed
                 while conducting the review,

Entrance interview	

                 The team leader hosts the entrance interview with designated
                 contractor staff and review team members present. The agenda
                 for the meeting follows. (If this is a repeat review with the same
                 contractor staff, you may want to condense the entrance inter-
                 view, skipping over some of the agenda items.)
                 • Make introductions among contractor staff and review team.
                   If the review team is made up of government and contractor
                   personnel, include this information during the introductions.
                 • Cite authority for conducting the review:
                   • FAR requirement
                   • Designated representative of the contracting officer

                 • Explain purpose of review: to determine if the contractor is
                   meeting the mimiTnim requirements to control and care for
                   government property under the contract. Stress that you are
                   not there to tell the company how it should operate.

                 • Provide overview of what you will be doing:
                   • Sample inventories
                   • Records review (ask them to make records available)
                   • Exit interview
                 • Summarize the 12 categories of property control (see appen-
                   dix C. Contractor may refer to page 10 of the Contractor's
                   Guide for Control of Government Property for more informa-
                   tion.)
                 • Discuss logistics: who will accompany team during inven-
                   tories and when the inventories will be conducted.
                                                                       "27

-------
           Chapter 4. Conducting a review
                            •  Request tour of facilities following entrance interview. Also
                               ask for information about:
                               •  Number and locations of sites under the contract
                               •  Storage facilities
                               •  Subcontracts
                            •  Discuss any discrepancies found in the inventory listing
                               which the contractor submitted before the review.

                            •  Ask for work space during review.

                            •  Wrap-up:
                               •  Any questions?
                               •  Exit interview will be held at end of review to discuss the
                                 findings.

                            At the conclusion of the entrance interview, read the next section,
                            then conduct the sample inventories.
           Sample inventories
                            The first step in reviewing the contractor's operations is conduct-
                            ing the sample inventories. Two types of inventories are con-
                            ducted, described below.

                            Records-to-floor inventory. 'TJecords-to-floor" means you select
                            the inventory items from the records and verify the information
                            in the records by physically locating the items. The inventory
                            items were selected before tile review using the random sample
                            procedures described in appendix A and, if applicable, the
                            selected sample procedures described in appendix B.

                            Floor-to-records inventory. "Floor-to-records" means you select
                            items at random as you see them, and verify that the records
                            are accurate for the selected items. Items are visually selected
                            at random in a variety of locations.

                            Conducting the inventories
                            While conducting inventories, be on the look-out for idle govern-
                            ment property which is obviously not being used (for example:
                            monitors stacked in a corner or a typewriter on top of a five-foot
                            file cabinet). Make a note of any idle property you see and ask
                            tile contractor about it. (Use this information later to help
                            evaluate the utilization and reporting categories.)
           28 Sample Inventories
.

-------
       Figure 4
O
o

Q.
c
o
(Q
O
 a    <
 
-------
Figure 5
•8
o
o
QJ
Ģ
2
I
PŖ
ta

Inventory

t3
^5 fi
co &Q
l-H
fl ^**
5 -°
*3 co
1=1

cd
1
1
1
D
•S
>v
inventory anal;
form


1
,>*
i
n
•*
information wi


CO
•B
O
o
v
1


1
(D
N
!
D
2
inventory resu]



-------
                                  Section three, ate compliance reviews
The next section describes the procedures for conducting the
records-to-floor random sample inventory.

Records-to-floor Inventory
The records-to-floor random sample inventory is conducted by a
review team member accompanied by a contractor employee.
Using the completed inventory analysis form (be sure to circle
"Records-to-floor" on each form), follow the steps described
below to conduct the inventory. Use the same approach to con-
duct a selected sample inventory, if applicable.
• Tell the contractor which items you are looking for.
• When an item is located, ask the contractor to read out the
   information by looking at the item (description, decal num-
   ber, manufacturer, model number, and serial number). If an
   item is located at another facility or site, look at the locator
   or other records for documentation, and note this on the form.
• Verify what the contractor reads out with the information
   recorded on the form.
    ^ If there is a discrepancy, make a note of the correct infor-
      mation.
    ^ Look at the item and assess its condition, making a nota-
      tion on Hie form in the appropriate box.
While you are conducting the records-to-floor inventory, make a
note of any items you may want to select for the floor-to-records
inventory.

Floor-to-records Inventory
Conduct the floor-to-records inventory accompanied by a contrac-
tor employee. If possible, select the same number of items as
were selected for the records-to-floor inventory. Do not select
any items that were included in the records-to-floor inventory.
Randomly select the items, choosing a variety of locations and
types of property.
• As you select an item, point it out to the contractor, and ask
   the contractor to read out the information by looking at the
   item (description, decal number, manufacturer, model num-
   ber,  and serial number).
   Note: When recording the inventory results, be sure to write legibly
   so you can read your own writing later.
                                                         31

-------
Chapter 4. Conducting Q review
                     ^ Record the information on an inventory analysis form (be
                        sure to circle "Floor-to-records").
                     ^ Look at the item and assess its condition, making a nota-
                        tion on the form in the appropriate box.
                  •  Once the inventory is completed, verify the information
                     recorded on the form with the PPAS records.
                     ^ If there is a discrepancy, make a note of the correct infor-
                        mation.

                  Analyze the results
                  After completing the inventories, analyze the results. Turn to ap-
                  pendix A and consult the random sample chart to determine if
                  additional inventories are required.

                  After completing the sample inventories, use the remainder of
                  this chapter as a guide for conducting the review. ^Please read
                  the following information before beginning the records review:
                  D  For organizational purposes, the procedures described in the
                     next section are grouped by property control element, begin-
                     ning with acquisition and ending with contract comple-
                     tion/termination. While conducting the review, procedures in
                     the categories will overlap. For example, when you review
                     the maintenance records, you are looking at the areas of
                     maintenance and calibration, utilization, and possibly dis-
                     posal (looking for cannibalization) at the same time. Figure 6
                     on the next page lists the records to be reviewed and the cor-
                     responding element of properly control.
                  O  Records are reviewed in detail for the sample items from the
                     records-to-floor inventory. You may use the form presented
                     in Figure 7 to keep track of the results of the records review.
                  D  "Characteristics of an effective system" outlines the mini-
                     mum requirements for a property control system. Some of
                     these characteristics may not apply to every contract. Use
                     your knowledge of the contractor's scope of work and your
                     common sense to decide which characteristics apply.
                  O  "What to look for" provides tips for checking the contractor's
                     compliance with the TTIITIITTIIUTI requirements. It is not an all-
                     inclusive list of what to do.
32 Sample Inventories

-------
o
2.
a
s.
                     m
                     5
                                                CO
                                                S
                                                S-
                                                                               8
                                                                                               §.'
                                                                                                                     I
                                                                                                                        u
                                                                                                                        i

-------
rigure /
     |
       i

     p

-------
                                                   Section three. Site compliance reviews
Acquisition
                 Definition: the process of acquiring government property either
                 through requisition or transfer from government sources, or
                 through purchase or lease, including those made from contrac-
                 tor stores.

                 Scope: covers the process of acquiring property; does not include
                 reporting acquisitions to EPA (that is part of the reporting
                 category). Do not address the competitive bid process or the
                 requirement for a lease vs. purchase analysis. These areas are
                 part of the contractor's procurement system and are covered in
                 depth during procurement system reviews performed by
                 Procurement and Contracts Management Division (PCMD).

                 Characteristics of an effective system
                 • The acquisition of accountable property, whether purchased,
                    furnished, or leased for more than 60 days, is authorized by
                    the contract or a modification.
                 • Existing government equipment on-hand is screened before
                    submitting requisitions.
                 • Requesting documents and purchase orders are prepared
                    and processed.

                 Records to review
                 To review the acquisition category, you need the following
                 documentation (when applicable):
                 • Procurement requests (requesting documents for CAP)
                 • Purchase orders (ordering documents for CAP)
                 • Contract modifications
                 • Propertyjustifications
                 • Transfer documents for GFP
                 • Original GFP listing in contract

                 What to look for
                 • If an item is not authorized, check for pending property jus-
                    tifications.
                 • Adequate paper trail from initiation of the request to comple-
                    tion of the purchase order.
                 • On purchase orders, make sure only EPA items are charged
                    to EPA.
                 • A means of identifying items listed on purchase orders (it.,
                    they must match up with the actual items).
                                                                         35

-------
Chapter 4. Conducting a review
                 Review the files and documentation to determine if the
                 contractor's operating procedures meet the minimum require-
                 ments outlined in "Characteristics of an effective system." Keep
                 track of the findings by writing down the facts about discrepan-
                 cies or problem areas; make a note of good characteristics as well.

Receiving	j	__	

                 Definition: the process of government property initially entering
                 into a contractor's custody.

                 Scope: covers the contractor's system for receiving property;
                 does not include decaling procedures (decaling is part of the
                 identification and records category) or the addition of tax and
                 freight charges to the acquisition cost of the item (this is an iden-
                 tification and records function).

                 Characteristics of an effective system
                 •  Receiving process includes inspection for content accuracy
                     and condition.
                 •  Receiving document adequately describes property and is
                     prepared and distributed to appropriate offices. The docu-
                     ment is signed and dated.
                 •  If quantity, condition, or description differs from that shown
                     on the shipping document, the discrepancy is documented in
                     writing. Follow-up actions are documented and annotated on
                     receiving document (e.g., completion of a partial shipment).
                 •  Misdirected or incorrect shipments are segregated and ade-
                     quately controlled, pending resolution of discrepancy.

                 Records to review
                 To review the receiving category, you need the following
                 documentation, when applicable:
                 •  Receiving documents (to include packing slips, shipping docu-
                     ments, and receiving reports)
                 •  Transfer documents (EPA Form 1700-7 for GFP)

                 What to look for
                 •  Consistent system for signing, dating, and annotating receiv-
                     ing slips.
                 •  Documentation that what was ordered was received and
                     accepted.
                 •  Adequate system for inspecting incoming shipments and con-
                     trolling partial deliveries.
36 Receiving

-------
                                                     Section three. Site compliance reviews
                  Compare the purchase documents with the receiving slips. .
                  Review the documentation to determine if the contractor's operat-
                  ing procedures meet the minimum requirements outlined in
                  "Characteristics of an effective system." Keep track of the findings
                  by writing down the facts about discrepancies or problem areas;
                  make a note of good characteristics as well.

Identification and records	

                  Definition: the identification of government property and the
                  official accounting and inventory control records maintained by
                  a contractor to show property status and to control government
                  property.

                  Scope: includes decaling government property and the accuracy
                  and completeness of documentation kept by the contractor. Does
                  not include submitting the information to the Agency.

                  Characteristics of an effective system
                  • Property received is promptly classified and labeled with
                     EPA property decal.
                  • Auditable inventory control and financial records are estab-
                     lished and maintained for government property.
                  • The records contain the basic information outlined in the
                     FAR (see Guide, pages 27 - 29).

                  Records to review
                  To review the identification and records category, you need the
                  following documentation (when applicable):
                  • Inventory control records (to include stock records for expend-
                     able items)
                  • Vehicle records

                  What to look for
                  • System for decaling components, to ensure consistency (e.g.,
                     components are always decaled or only the main unit is de-
                     caled).
                     Note: Look for consistency in nomenclature. For example, HNU
                     (manufacturer) photoionization detectors are sometimes catted
                     HNUs rather than photoionization detectors (actual item descrip-
                     tion). Referring to them as HNUs is acceptable as long as the use
                     is consistent in the records.
                                                                            37

-------
Chapter 4. Conducting o review
                 • Unit cost of property items includes tax, shipping, and instal-
                    lation. Look for a basis for determining the acquisition cost
                    (i.e., basis for apportioning costs when multiple items are
                    listed on one invoice).
                 • All items listed on invoices and charged to EPA contract are
                    listed on the contractor's inventory.
                 • Records must be auditable; in other words, you must be able
                    to track an item through the records to the actual item.
                 • Appropriate records are maintained for vehicles (mainte-
                    nance logs, sign-out sheets).

                 Review the files and documentation to determine if the
                 contractor's operating procedures meet the minimum require-
                 ments outlined in "Characteristics of an effective system." Keep
                 track of the findings by writing down the facts about discrepan-
                 cies or problem areas; make a note of good characteristics as well.

Storage and movement	

                 Definition: the process of storing and moving all types of govern-
                 ment property, including protection during storage and move-
                 ment.
                 Scope: Covers the internal movement of property necessary to
                 carry out the scope of work (e.g,, from the main office to a site or
                 from one site to another). It does not include movement result-
                 ing from the transfer of accountability to another entity, such as
                 the return of property to the program office (that's part of the
                 disposal category). Nor does it cover movement from one con-
                 tract to another even for the same contractor (that's a transfer
                 which must be coordinated with the property administrator and
                 approved by both contracting officers).

                 Characteristics of an effective system
                 • An adequate system to control movement and location of
                    property is maintained.
                 • Property in storage is protected, preserved, and inspected to
                    prevent loss, damage, and deterioration,
                 • Adequate safeguards are provided for securing government
                    property.
                 • A first in/first out system is established for stored items sub-
                    ject to age deterioration and warranty expiration.
                 • Government property is segregated from contractor property.
38 Storage and movement


-------
                                                    Section three. Site compliance reviews
                 Records to review
                 You will need the following documentation (when applicable):
                 • Movement orders (internal forms used by the company to
                    document the movement of property under the contract)
                 • Locator system files

                 What to look for
                 • A system that permits the contractor to locate equipment
                    within two days (e.g., logs by day, site or equipment). Note:
                    the two-day period applies to the system's ability to locate
                    property during contract performance (see Guide, page 9).
                 • Documentation of the movement of properly (e.g., logs, hand
                    receipts, movement orders).
                 • The contractor's procedures for physically moving property
                    (property is transported in the back of a pick-up truck or by a
                    moving company). Determine whether property is adequate-
                    ly protected during movement.
                 • Government property items in storage are properly pro-
                    tected, secured, and segregated from contractor property.

                 Review the contractor's storage facilities, observing security
                 measures for the storage area. Ask questions about the security
                 procedures for other areas where government property is located
                 (e.g., offices locked at night, restricted access). Examine the files
                 to help determine if the contractor's operating procedures meet
                 the minimum requirements outlined in "Characteristics of an
                 effective system," Keep track of the findings by writing down the
                 facts about discrepancies or problem areas; make a note of good
                 characteristics as well.

Property consumption	

                 Definition: the process of incorporating property into an end
                 item or otherwise consuming it in performance of a contract.

                 Scope: the property consumption category primarily covers the
                 use of supplies and materials acquired under the contract.

                 Characteristics of an effective system
                 •  Property is consumed only under contract performance.
                 •  Stock record system is maintained for consumable items.
                                                                           39

-------
Chapter 4. Conducting a review
                    Excesses are promptly returned to stores and returns are
                    recorded.
                 • Quantities consumed are reasonable.

                 Records to review
                 To review the property consumption category, you need the fol-
                 lowing documentation:
                 • Stock records

                 What to took for
                 • Supply levels seem reasonable.

                 Ask the contractor about re-order points for supplies and general
                 rates of consumption. Ask about access to supplies. Review the
                 stock records to help determine if the contractor's operating proce-
                 dures meet the minimum requirements outlined in "Charac-
                 teristics of an effective system." Keep track of the findings by
                 writing down the facts about discrepancies or problem areas;
                 make a note of good characteristics as well.

Utilization

                 Definition: tile process of using equipment and materials for
                 their authorized purpose.

                 Characteristics of an effective system
                 • Methods are established to ensure that government property
                    is utilized only for purposes authorized by the contract.
                 • Contractual authorization is obtained to use property for
                    other than its original authorized purpose.
                 • A system is established to review and identify government
                    property for release when it is no longer required for contract
                    performance.
                 • Criteria are established and retention of idle equipment is
                    documented and justified by the project officer.

                 Records to review
                 To review the utilization category, you need the following
                 documentation (when applicable):
                 • Maintenance logs/records
                 • Equipment logs
                 • Calibration records
                 • Sign-out logs
40 Utilization

-------
                                                   Section three. Site compliance reviews
                 What to look for
                 • Turn-around time for newly acquired items: for how long are
                    they held in the receiving department or stored before being
                  * put to use?
                 • Methods that may help you determine if property is being
                    properly utilized:.
                    • Check maintenance, equipment, calibration, and sign-out
                      records for usage.
                    • Check the DOS directory in a personal computer to see the
                      last time it was used. You may briefly review the file
                      names to identify personal use.
                    • Look for items that are obviously not being used such as
                      monitors stacked in a corner, terminals in a closet, sealed
                      boxes of items, or property in storage. Remember: if there
                      is authorization to have these items stored in the closet,
                      etc., there is no "inadequate" finding.

                 Use the methods described above and consult the sample inven-
                 tory results to help determine if the contractor's operating proce-
                 dures meet the minimum requirements. Keep track of the
                 findings by writing down the facts about problem areas; make a
                 note of good characteristics as well.

Maintenance and calibration	

                 Definition: the process of providing the care necessary to obtain
                 a high quality of production and the most useful life of govern-
                 ment property.

                 Scope: this category focuses on the contractor's system for main-
                 taining and calibrating government property as needed. Even if
                 the contractor's equipment has not required maintenance, there
                 must be a plan for how maintenance will be handled. The
                 contractor's plan may be to call a vendor for service in the event
                 of equipment malfunctions; written service agreements are not
                 required. The key is that the contractor select the most efficient,
                 cost effective method to care for government property.

                 Characteristics of an effective system
                 • Government property is maintained in a safe, efficient, and
                    economical manner.
                 • A scheduled maintenance program is established, consisting
                                                                          41

-------
Chapter 4. Conducting a review
                    of a systematic written procedure for servicing and inspect-
                    ing equipment.
                 • A calibration control system is designed for all measuring
                    and test equipment (M&TE) to control the evaluation,
                    calibration, maintenance, repair, and use of M&TE.
                 • Records are kept of maintenance and calibration performed,
                    including cost and date.
                 • Maintenance and calibration are performed by technically
                    qualified personnel.
                 • System is capable of identifying high maintenance costs for
                    review; corrective action is taken by management and is
                    documented.

                 Records to review
                 To review the maintenance and calibration category, you need
                 the following documentation (when applicable):
                 • Maintenance logs
                 • Calibration logs
                 • Vehicle maintenance records
                 • Maintenance plan (for new contracts with no history of main-
                    tenance)

                 What to took for
                 • Condition of government property, including vehicles. For
                    vehicles, check the tires, oil level (you may ask the contractor
                    to show you the oil level on the dip stick), appearance of the
                    vehicle's interior. For other than vehicles, notice the overall
                    appearance of government property.
                 • Maintenance and calibration should be performed in accord-
                    ance with the manufacturer's suggested procedures.
                 • For health and safety equipment and for vehicles, there
                    might be separate maintenance plans. You may want to look
                    at these manuals.
                 • Look at the maintenance history records; are there high-
                    maintenance items that might need to be replaced?

                 If the government program office keeps the maintenance
                 records, contact that office to review the contractor's records. If
                 you find that the Government is not keeping adequate main-
                 tenance records for the contractor, you may require the contrac-
                 tor to keep the records (a required action in the report of
                 findings).
42 Maintenance and calibration

-------
                                                    Section three. Site compliance reviews
                  Consult the sample inventory results and look at the condition of
                  government equipment as you walk through the contractor's
                  facilities. Review the files and ask questions to help determine if
                  the contractor's operating procedures meet the minimum require-
                  ments. Keep track of the findings by writing down the facts about
                  problem areas; make a note of good characteristics as well.

Physical inventory	

                  Definition: the process of physically locating and counting
                  government property, recording the results and comparing the
                  findings to the records. The process includes posting findings
                  and adjustments.

                  Scope: covers the process of taking the inventory, recording the
                  results and reconciling them; does not include reporting the
                  inventory results to EPA (that's part of the reporting category).
                  Focus on how the contractor conducts the inventory (who does
                  it, approach, procedures) and how the results are reconciled.

                  Characteristics of an effective system
                  • Physical inventories are conducted at contract start-up,
                    annually on the anniversary of contract award, on a special
                    basis if directed by the property administrator, and upon con-
                    tract completion or termination.
                  • Inventories are conducted by personnel other than those
                    having custody of the property or control of the records.
                  • Inventories are conducted using the floor-to-records
                    approach.
                  • Physical inventory results are promptly reconciled with
                    property records.

                  Records to review
                  To review the physical inventory category, you need the follow-
                  ing documentation:
                  • Inventory control records (could be copies of EPA Forms
                     1700-7 and 1730-1, locator system records, computerized
                    inventory listing).
                  • Inventory work sheets, if available. If work sheets are not
                    available, interview the person who conducted the inventory.

                  What to look for
                  •  Physical inventory procedures that comply with the above
                     standards and ensure accurate results.
                                                                           43

-------
Chapter 4. Conducting o review
                 Review the files, reading over the inventory work sheets if avail-
                 able, and ask questions to determine if the contractor's inventory
                 procedures meet the minimum requirements outlined in "Charac-
                 teristics of an effective system." Keep track of the findings by writ-
                 ing down the /acts about discrepancies or problem areas; make a
                 note of good characteristics as well.

Subcontract administration	

                 Definition: the contractor's system to ensure a subcontractor's
                 compliance with the requirements for the control and care of
                 government property.

                 Scope: the prime contractor must submit consolidated reports
                 for all government property under the contract, to include sub-
                 contractor property. The prime communicates with the sub-
                 contractor and is the property administrator's only contact for
                 government property.

                 Characteristics of an effective system
                 • Procedures and controls are established to assure that
                    government property in a subcontractor's possession is ade-
                    quately protected.
                 • Subcontractor is aware of contractual property provisions.
                 • Subcontractor will report government property transactions
                    to the prime contractor for notification to the property ad-
                    ministrator.
(I)
                  Records to review
                  To review the subcontract administration category, you need the
                  following documentation (when applicable):
                  • Inventory control records (could be copies of EPA Forms
                    1700-7 and 1730-1, locator system records, computerized in-
                    ventory listing)

                  What to took tor
                  • Evidence that the prime contractor keeps track of subcontrac-
                    tor property (subcontractor property is included in prime's
                    inventory records, subcontractor property reports are sub-
                    mitted to prime, reports of missing or damaged subcontrac-
                    tor property)
44 Subcontract administration

-------
                                                   Section three. Site compliance reviews
                 Review the files and documentation to determine if the
                 contractor's operating procedures meet the minimum require-
                 ments in "Characteristics of an effective system." Keep track of
                 the findings by writing down the facts about discrepancies or
                 problem areas; make a note of good characteristics as well.

Reporting	

                 Definition; the preparation and submission of reports showing
                 the status of government property as required by the FAR and
                 the contract.

                 Scope: this category covers the accuracy, completeness, and
                 timeliness of reports the contractor is required to submit to the
                 property administrator. The contractor's rating in this category
                 is based upon knowledge of the requirements and performance
                 in submitting reports.

    „	„      Characteristics of an effective system
                 • Inventory reports are provided to the property administrator
                    at the start of the contract, annually on the anniversary date
                    of contract award, on a special basis as requested, and upon
                    contract completion or termination.
                 • EPA Form 1730-1 is submitted for all accountable CAP and
                    accountable property leased for more than 60 days; receipt of
                    GFP is reported to the property administrator when the
                    property is received.
                 • Any loss or damage to government properly is immediately
                    reported to the property administrator (details are provided
                    in the Guide).
                 • Government property no longer required for the performance
                    of the contract is promptly reported to the property admin-
                    istrator.
                 • Retention of government property with low utilization rate is
                    justified and annually documented in writing. Must be jus-
                    tified by the project officer.
                 Records to review
                 You will need the following documentation (when applicable):
                 • Copies of EPA Forms 1730-1 and 1700-7
                 • Inventory records
                 • Missing, stolen, or damaged property reports
                 • Reports of excess property
                 • Vouchers
                                                                         45

-------
Chapter 4. Conducting a review
                 What to took for
                 • Lag time between the receipt of property and reporting it on
                    EPA Form 1730-1 and 1700-7 (if used to report receipt of
                    GFP).
                 V* Compare the findings from your sample inventories with the
                    contractor's inventory records.
                 • Contractor's reporting history (e.g., annual inventories al-
                    ways late, incomplete data submitted for acquisitions,
                    reports submitted on time with complete information).
                 • Both CAP and GFP are reported as part of contractor's inven-
                    tory.
                 • Review the vouchers and supporting documentation; look for
                    equipment that may be included in "Other Direct Costs" sub-
                    listings and in "Subcontracts."
                 • Evidence that idle property is identified and promptly
                    reported to property administrator.

                 Review the files, documentation and the contractor's reporting
                 history to determine if the contractor is meeting the minimum
                 reporting requirements outlined in "Characteristics of an effec-
                 tive system." Keep track of the findings by writing down the facts
                 about discrepancies or problem areas; make a note of good char-
                 acteristics as well.
Disposal
                 Definition: the process of requesting and receiving disposition in-
                 structions and effecting the disposal of government property as
                 directed by the property administrator.

                 Characteristics of an effective system
                 • The quantity, condition code, and location are reported accu-
                    rately for property items requiring disposition.
                 • Disposition instructions provided by the property admin-
                    istrator are carried out as directed.
                 • In accordance with instructions, the disposal of property is
                    properly documented.
                 • A decontamination certification is included in the final inven-
                    tory report at the conclusion of the contract.
                 • Property is cannibalized only after receipt of the contracting
                    officer's approval and written instructions from the property
                    administrator.
46 Disposal

-------
                                                    Section three. Site compliance reviews
                  Records to review
                  To review the disposal category, you need the following
                  documentation (when applicable):
                  • Copies of disposition instructions
                  • Documentation of disposal actions

                  What to look for
                  • Documentation should include the signature of the individ-
                    ual who receives the property after it leaves the contractor's
                    possession.
                  • There is authorization on file for every disposal action.
                  • Disposal actions are taken within a reasonable time period
                    after receiving disposition instructions.
                  • When appropriate, proceeds are credited to the Government.
                  • To check for cannibalization, look through maintenance
                    records for entries describing the removal or installation of
                    parts. Look at property as you walk through the facility, espe-
                    cially in the storage area; ask to see the area where excess
                    property is stored. For example, if you see a three-legged
                    chair, ask where the other leg is. It may have been used to
                    repair another chair. Be sure the contractor has obtained
                    authorization to cannibalize government property.

                  Review the files and documentation to determine if the contrac-
                  tor's operating procedures meet the minimum reporting require-
                  ments outlined in "Characteristics of an effective system." Keep
                  track of the findings by writing down the facts about discrepan-
                  cies or problem areas; make a note of good characteristics as well.

Contract completion or termination	

                  Definition: procedures to be followed by the contractor upon can-
                  tract completion or termination.

                  Scope: When you review contract completion, in some cases you
                  will review contracts that have been completed, and in other
                  instances you will be reviewing the contractor's plans for future
                  dose-out.

                  Characteristics of an effective system
                  • Residual property is/will be reviewed for appropriate action
                    (such as decontamination or repair) before transfer or dis-
                    posal of property.
                                                                           47

-------
Chapter 4. Conducting o review
                 • A full accounting is/will be effected of all government proper-
                    ty (to include nonexpendable property regardless of cost, and
                    expendable supply items and materiel not consumed during
                    contract performance) in possession of the prime contractor
                    and the subcontractor. The final inventory report is/will be
                    submitted promptly.
                 • Pending issues are/will be resolved, such as inventory adjust-
                    ments and determinations of liability, before contract closure.
                 • The property administrator is/will be notified when all pend-
                    ing actions on property-related issues are completed.

                 Records to review
                 To review the contract completion/termination category, you
                 need the following documentation (when applicable):
                 • Final inventory records
                 • Disposition instructions
                 • Documentation of disposal actions
                 • Written procedures for close-out, if applicable

                 What to took for
                 • Disposition of government property has been/will be properly
                    carried  out and documented.
                 • Adjustment documents, including request for relief from
                    responsibility, have been/will be processed.
                 • Proceeds from disposals or other properly transactions, in-
                    cluding adjustments and purchase credits, have been/will be
                    credited to the contract or paid to the Government as
                    directed by the contracting officer.
                 • All questions about title to property fabricated or acquired
                    under the contract have been/will be resolved and docu-
                    mented.

                 Review the files and documentation to determine if the contrac-
                 tor's operating procedures meet the minimum reporting require-
                 ments outlined in "Characteristics of an effective system." If the
                 contract has not closed out, talk to the contractor about close-out
                 to determine if the contractor understands the basic require-
                 ments. Keep track of the findings by writing down the facts about
                 discrepancies or problem areas; make a note of good charac-
                 teristics as well
48 Contract completion or termination

-------
                                 Section three. Site compliance reviews
Did you review all of the applicable categories of properly
control?

• Acquisition
• Receiving
• Identification, and records
• Storage and movement
• Properly consumption
• Utilization
• Maintenance and calibration
• Physical inventory
• Subcontract administration
• Reporting
• Disposal
• Contract completion or termination
                                                        49

-------
Chapter 4. Conducting a review
Closing the review
                 When the review procedures have been completed, the team
                 leader should hold a meeting with the review team to discuss
                 the findings. The next section provides general guidance for
                 evaluating the findings.

                 Evaluation guidelines
                 The evaluation of the adequacy of a contractor's operating proce-
                 dures is based on the facts that were established during the
                 review. The findings establish the facts on which conclusions
                 are founded. When you evaluate the adequacy of the contrac-
                 tor's system, use the following questions as your guide:
                 • Are the contractor's operating procedures adequate to ensure
                    the proper care and control of government property?
                 • Do the procedures meet the minimum requirements?
                 • Do the operating procedures conform with the contractor's
                    written property control system?
                 Adequate or inadequate? To determine whether the contractor's
                 operations in each area are adequate or inadequate, measure
                 the findings against the standards. The standards consist of
                 "Characteristics of an effective system" in each section, contract
                 and FAR requirements, as well as general principles of good
                 business practice. Consider the contractor's scope of work (for
                 example, sign-out logs are essential for contractors with multi-
                 ple sites, but not for a contractor whose government equipment
                 consists of computers located at one permanent site). Use your
                 judgment to determine whether a deficiency represents an aber-
                 ration or whether the deficiency points to a flaw in the system.

                 Look at the big picture. Be sure to look at the big picture. For
                 example, if a monitor is found in a closet, consider all the factors
                 before rating the utilization category. If the contractor has never
                 reported excess property and a monitor is found in a closet, you
                 would probably rate that category as inadequate. On the other
                 hand, if the contractor has consistently reported items that are
                 no longer needed, you might include a recommended action
                 about reporting excess property, but rate the category as ade-
                 quate. Ultimately, the adequate vs. inadequate decision is a
                    Note: Avoid "double jeopardy."Don't write up the same deficiency
                     in more than one category.
 50 Closing the review

-------
                                   Section three. Site compliance reviews
judgment call which must be based on the review team's evalua-
tion of the facts.

Exercise caution when reviewing a "problem" contractor. Be
sure to stick to the facts that were established during the
review. Don't turn the findings into proof of pre-conceived ideas.

Team meeting
The purpose of the team meeting is to evaluate each category
and organize the information gathered during the review for
presentation to contractor staff during the exit interview. The
level of detail for the discussion depends on how much time is
available. (Note: if you have access to a laptop computer, you
may be able to prepare the final report and deliver it to the con-
tractor during the exit interview.) The agenda for the meeting
follows.
• Summary of findings for each category: discuss the findings
   for each category reviewed. Be sure to include positive
   aspects of the contractor's operating procedures. Determine
   whether the contractor's operations for each category are
   adequate or inadequate. Review the notes you made in your
   handbook as well as the inventory analysis forms. Use the
   guidelines outlined in this section to help in the
   decision-making process.

• Summary of the contractor's overall system: you must rate
   the overall system as either adequate or inadequate. If all of
   the categories  reviewed were adequate, then the overall
   system will be rated as adequate. If any of the categories
   were found to be inadequate, however, then the overall
   system must be rated as inadequate (even one inadequate
   category means there is a deficiency in the operation of the
   property control system).
• Required actions: determine what actions are necessary for
   the contractor's operating procedures to meet the minimum
   requirements. Remember: you may identify deficiencies, but
   you may not tell the contractor how to operate. (Example:
   let's say the storage and movement category was found to be
   Note: Be careful about recommending actions because of the pos-
   sibility of additional cost to the Government. Remember that you
   can't require the contractor to do something just because it will
   make your life easier (e.g., marking the decal number on all the
   back-up documentation).
                                                          51

-------
Chapter 4. Conducting a review
                    inadequate because the contractor could not specify the
                    location of equipment being used in the field. Identify the
                    deficiency and state that a locator system is required, but do
                    not tell the contractor to set up a specific type of log system.)
                 • Determine whether a milestone schedule for completing the
                    actions will be needed. Will the contractor need to report the
                    status of required actions on a scheduled basis?

                 • Recommended actions: you may recommend actions that
                    would improve the contractor's operations, but that are not
                    necessary for the system's compliance with the minimum
                    requirements.
                 When the information has been assembled, the exit interview
                 may be conducted.

Exit interview	

                 The review team leader should conduct the meeting with the
                 review team and key contractor staff in attendance. The sug-
                 gested agenda for the exit interview follows.
                 • Thank the contractor staff for their cooperation and support.
                 • Briefly describe how the review was conducted.
                 • Explain the structure you are using to present the findings:
                    general summary of findings, findings in each category,
                    recommended actions, and required actions.

                 • Using the notes taken during the team meeting, present the
                    findings.
                 • Explain the next step in the review process: final report will
                    be submitted in approximately one month.
                 • Discuss the schedule for implementing the required actions:
                    advise the contractor that it is the contractor's responsibility
                    to implement all required actions, once they are finalized.

                 • Discuss the schedule for the contractor to report the status of
                    corrective actions (if applicable).
                 • Close the meeting.
                     Note: When making suggestions to the contractor about how to do
                     something, don't give away  confidential information about
                     another contractor's operations.
52 Exit Interview

-------
                                                  Section mree. Site compliance reviews
                  Reporting the findings
                                 Chapters
Report features
                 The report presents the review findings, recommended actions,
                 and required actions. The suggested format of the report follows.

                 Introduction
                 Identify the following information in an opening paragraph.
                    O  Name of contractor
                    n  Location of review
                    D  Dates of review
                    D  Compliance review team: names and titles
                    D  Contractor staff involved in review: names and titles
                    D  Brief statement about the contractor's scope of work

                 Summary of findings
                 State whether the contractor's working property control system
                 is adequate or inadequate. If any of the twelve categories were
                 found to be inadequate, then the overall system must be rated
                 as inadequate. In this case, explain the rating; avoid presenting
                 the review findings in a totally negative light. You might sum-
                 marize the number of categories reviewed: # adequate, # inade-
                 quate, # not applicable.

                 Methodology
                 Describe the procedures that were used to conduct the review.
                 Example: records-to-floor and floor-to-records inventories were
                 conducted using random sampling techniques; records were ex-
                 amined to determine compliance with the contractor's property
                 control system, the contract, and applicable federal regulations.

                 Findings
                 Briefly describe the findings in each category. Remember that
                 the findings are limited to the facts. Example: (in the utilization
                 category) The equipment sampled in the records-to-floor inven-
                    Note: Don't say "the overall review ofXYZ was inadequate." Ŗ:?y
                    "the review found XYZ's overall property control system tc   ?
                    inadequate" or "the overall system of control is inadequate to...
                                                                         53

-------
Chapter S. Reporting the findings
                 tory is being utilized for the intended purpose of the contract.
                 However, the floor-to-records sample revealed the following: one
                 monitor not being utilized, one monitor with a Supernind decal
                 not being used for Superfund work, and three PC shadow ter-
                 minals not being used."

                 When you describe the findings in a category that was rated in-
                 adequate, such as the example just cited, be sure to distinguish
                 the good characteristics from the bad. The language in the pre-
                 vious example makes it clear that the first statement is a "good"
                 characteristic, while the latter findings are "bad."

                 Required actions
                 Last the required actions which were determined at the close of
                 the review. Required actions are the actions necessary for the
                 contractor's operating procedures to meet the minimum require-
                 ments. Keep in mind that in terms of specific techniques or sys-
                 tems to use, you may not tell the contractor how to operate.

                 Recommended actions
                 This section permits you to recommend actions that would im-
                 prove the contractor's operations, but that are not necessary for
                 compliance with the minimum requirements. This section is use-
                 ful for recommending actions to contractors with an adequate
                 property control system.
       ing and submitting the report
                 It is the team leader's responsibility to see that a draft report of
                 findings is prepared within one week after completing the
                 review. All team members should review the draft. The final
                 report should be ready for the property administrator's approval
                 within one week of the review's completion. Additional levels of
                 approval may be required, depending on your organization's in-
                 ternal operating procedures.

                 Submit a copy of the report accompanied by a cover letter to the
                 contractor no later than one month after the review's comple-
                 tion. Forward copies of the report to the contracting officer and
                 project officer.
54 Preparing and submitting ihe report

-------
                                                  Section three, ate compliance reviews
                  Follow-up procedures
                                 Chapter 6
Approach
                 The purpose of establishing follow-up procedures is to ensure
                 that action is taken by the contractor to correct the deficiencies
                 identified during a compliance review. It is the contractor's
                 responsibility to implement required actions following a review.

                 Follow-up actions should be consistent with the nature of the
                 review findings. For contractors with minor problems, only mini-
                 mal follow-up will be necessary. Formal follow-up procedures
                 should be developed, however, for contractors with significant or
                 extensive weaknesses.

Informal telephone follow-up	

                 For contractors with minor problems, make a follow-up tele-
                 phone call four to six weeks after the report has been finalized.
                 The purpose of the call is to inquire about the status of imple-
                 menting the required actions.
Scheduled written follow-up
                 An option for following up required actions with contractors that
                 have major deficiencies is through formal written follow-up.
                 Depending on the nature of the problem and whether Hie con-
                 tractor has reported the follow-up actions, you may want to
                 schedule a date to send a follow-up letter (establish a tickler sys-
                 tem for this).

                 In the initial letter, reference the review and the required
                 actions, and request a written response from the contractor
                 reporting the status of implementing the required actions.
                 Specify a deadline for the response (two to four weeks after
                 receipt of letter).

                 If no response is received, send a second letter. If a third letter
                 is needed, it should be elevated to a higher level of manage-
                 ment. The property administrator may want to discuss the issue
                 with the contracting officer and the project officer.
                                                                       -55

-------
Chapter 6. Follow-up procedures
Follow-on review
                  A follow-on review may be conducted when the Government's
                  assets are significantly at risk. In this instance, a follow-on
                  review should be scheduled as soon as the contractor has imple-
                  mented required actions. The purpose of a follow-on review is to
                  ensure that corrective actions have been taken to safeguard the
                  Government's assets. The guidelines for conducting the review
                  and reporting the findings should be followed.
56 Follow-on review

-------
                                                          Section four. Desk reviews
             Conducting a  desk review
                                 Chapter?
Introduction
                 This chapter provides guidance for conducting desk reviews of
                 contractor property control systems. A desk review is defined as
                 a compliance review that is conducted at the reviewer's desk.
               .  The purpose of a desk review is to ensure that the contractor is
                 making only authorized purchases or leases, that purchases or
                 leases are reported as required, and that government property
                 is being properly cared for, controlled, and utilized.

                 The methods used to conduct a desk review will vary, depending
                 on factors specific to the contract/contractor being reviewed. The
                 property administrator must exercise judgment to determine
                 the procedures to follow, considering the following factors: value
                 of properly, number and type of property items, complexity of
                 system, risk to Hie Agency, and past performance. The review
                 should focus on known or suspected areas of vulnerability.

Plan the review	

                 To plan the review, you must determine the areas on which to
                 focus. Examine past review findings to pinpoint areas of vul-
                 nerability. If this is the first review being conducted, examine
                 your files to obtain information about the contractor's reporting
                 history. Select review methods that will focus on vulnerable
                 areas.

Notify the contractor	

                 A letter from the property administrator to the contractor's
                 point of contact serves as notification of the desk review. The let-
                 ter should cover the following information:
                 a Brief explanation of the purpose of the review
                 ta Scope  of the review
                 H Bequest for copies of documentation required
                 H Statement that the contractor will be notified of the findings
                                                                        59

-------
Chapter 7. Conducting a desk review
Conduct the review
                 Outlined below are procedures which may be used to conduct a
                 desk review. The property administrator may use these proce-
                 dures, or other appropriate methods that focus on vulnerable
                 areas. The review will cover records for the time period since the
                 date of the most recent review.

                 Examine documentation
                 You may examine any of the records described in the following
                 section.

                 Contract file in your office. Examine your contract files:
                 • Are annual inventory reports submitted promptly?
                 • Is EPA Form 1730-1 submitted for accountable CAP?
                 • Is receipt of GFP reported?
                 • Is loss of or damage to government property reported?
                 • Is government property excess to contract requirements
                    reported?

                 Call the contractor's point of contact for more information or to
                 ask  questions. A list of sample questions is provided later in this
                 section.

                 Contractor's records. When deciding which records to request
                 from tile contractor, select only those records required for the
                 review. Do not place an unreasonable burden on the contractor
                 (i.e., don't require the contractor to make copies of 1,000 pages
                 of logs).

                 You may focus on one particular area only, for instance, you
                 may examine all movement records for the last one-year period.
                 Or you may take a different approach and select several items of
                 accountable property and request copies of all records pertain-
                 ing to those items, verifying that an audit trail exists.

                 Copies of the following types of documents may be requested.

                 • Movement logs
                 • Sign-out logs
                 • Maintenance logs
                 • Calibration logs
                 • Procurement requests
60 Conduct the review

-------
                                         Section four. Desk reviews
• Purchase orders
• Payment vouchers

When you review payment vouchers, select representative
vouchers and look for reimbursement requests for property
items that have not been reported on EPA Form 1730-1. You
may need to request back-up documentation from the contractor
to identify costs. Look at several categories: equipment, miscel-
laneous under other direct costs, subcontracts, and sub-listings
under equipment such as repair, rentals, supplies, and shipping.
You might request copies of rental agreements to look for
renewals and credits.

Interview contractor
You may call the contractor's point of contact to gather informa-
tion concerning the contractor's property control procedures.
Use the following questions as a starting point. Be sure to ask
open-ended questions that require explanations rather than
"yes/no" questions.
D What steps are taken when government property is needed?
D Under what circumstances do you report leased property?
D What is your receiving process for government property?
O What are your procedures for decaling property?
O What records do you maintain for government property,
   including vehicles?
D How is government property stored?
D How is the movement of government property documented?
O How do you ensure that government property is utilized fully
   and only for purposes authorized by the contract?
D How do you identify government property that is no longer
   required for contract performance? What do you do if you no
   longer need an item of government property?
D What are your maintenance procedures for government
   property? What records do you keep?
D How do you conduct a physical inventory? Who conducts the
   inventory?
D What property transactions do you report to EPA?
D What do you do when an item is missing?
                                                        61

-------
Chopter 7. Conducting a desk review
                 D What do you do when you are ready to dispose of government
                    property?

Document the findings	

                 After completing the review, notify the contractor in writing of
                 the findings. The letter should cover the following information:
                 H Method used (e.g., a review of movement documentation or a
                    telephone conversation with [person's name]).
                 H Findings: contractor's procedures are adequate or inade-
                    quate. If inadequate, state the specific deficiencies.

                 H Required actions: if appropriate, identify required actions.
                 If the findings indicate that the Government's assets may be at
                 risk, the property administrator has the discretion to conduct a
                 site review.
62 Document the findings

-------
                                                                   Appendix
                     Random  sampling
                                Appendix A
Definition
                 Random sampling is a statistical measure used to analyze large
                 groups of objects or persons by examining a portion of the group
                 and generating results that are viewed as a reliable repre-
                 sentation of the group as a whole.

Application

                 Random sampling will be used to select accountable property
                 items for a records-to-floor inventory which will provide the in-
                 formation needed to assess some of the categories of property
                 control. (For inventories of other than accountable property, see
                 Appendix B.) The inventory analysis form for the records-to-
                 floor inventory will be completed at the home office before begin-
                 ning the compliance review. To randomly select the property
                 items that will be included in the inventory, you will need the
                 following.
                     D Contractor's inventory listing
                     D Random sample chart, located in this appendix
                     D Random number table
                     D Inventory analysis form (copy in this appendix)

Selecting the sample Items

                 Selecting the items for the sample records-to-floor inventory con-
                 sists of a three-step process, listed below. These steps are com-
                 pleted at the home office before conducting the review.

                 O Determine the sample size (if you are reviewing more  than
                    one contract, the sac.pie will consist of the combined
                    inventories of accountable property for all contracts being
                    reviewed).
                    Note: If the contractor fails to submit the requested inventory
                    listing, use the most current inventory available (if the contractor
                    does not fax or express-mail the listing to you.)
                                                                        65

-------
Appendix A. Random sampling
                 @ Choose the column and number patterns for the sample
                    selection.

                 Š Record the selected items on the inventory analysis forms.

                 O Determine the sample size
                 Use the inventory listing submitted by the contractor. If the con-
                 tractor did not submit an inventory as requested, use the most
                 recent inventory listing on file.

                 Using a copy of the inventory listing, number each accountable
                 property item consecutively, beginning with "1." Look at the
                 random sample chart on page 68 and locate the range that corre-
                 sponds to the total number of items in the contractor's inventory.

                 EXAMPLE: There are 92 items of accountable property in the
                 contractor's inventory. Based on the range of numbers in the ran-
                 dom sample chart, 25 items will be sampled (how: 92 falls be-
                 tween 91 -150 items, thus, the sample inventory will consist of
                 25 items).

                 @ Choose the column and number patterns
                 The random number tables that appear on pages 70 and 71 con-
                 sist of eight columns and 30 lines of six-digit number sequences.
                 These numbers have been randomly generated using a com-
                 puter. (If you have access to a computer program which
                 generates random numbers, you may use that instead.)

                 Select a column or a pattern of sequences (e.g., every third se-
                 quence or every sequence), then decide which digits from each
                 sequence you will use to select the item numbers. You may
                 choose the first, middle, or last digits in the sequence. Each
                 sequence you select will correspond with a numbered item on
                 the contractor's inventory listing. (If you use the random num-
                 ber tables in this appendix, vary your column and sequence pat-
                 terns for each review to ensure a random sample.)

                 EXAMPLE: You have decided to use the first two digits in the se-
                 quences from column 4 on random number table 1, beginning at
                 the bottom of the column, to select items for your sample. You
                 must choose two digits from each sequence because there are 92
                 items (a two-place number) in the contractor's inventory.
 66 Selecting ttie sample Items

-------
                                                    Appendix
€> Record the selected item numbers
Now that you have selected the sequence pattern you will be
using, you are ready to select the items for the random sample
and record the selections on the inventory analysis form (circle
"Records-to-floor" on the top of each form you use). The steps are
described below, continuing with our example.

Ž Select the first sequence from the column you have chosen to
use. (You have decided to use the first two digits in each sequence
in column 4, beginning with the last sequence. Look at random
number table 1: the last sequence in column 4 is 529028.)


-------
Appendix A. Random sampling
                                            Random Sample Chart
Number
of items'
1-18
19-50
51-90
91-150
151-400
401
-10,000
10,001
-35,000
35,001
-100,000
100.000
and more

Sample
size!
All
18
21
25
32
34
40
46
52
Sample 1
Acceptable
error range
0
0
0-1
0-2
0-3
0-3
0-4
0-5
0-6
Sample 2
Unacceptable
error range**
1 +
1 +
2+
3 +
4 +
4 +
5 +
6 +
7 +
Sample
size 2
^_
—
21
25
32
34
40
46
52
Acceptable
error range
^^
—
1
0-2
0-3
0-3
0-4
0-5
0-6
Unacceptable
error range
_--
—
2
3
4
4
5
6
7
                                 ThU chart wu excoptad from the Armtd Soviets Procunmtia KttulatiaHt.

                       *ff you are reviewing more than one contract, this number will consist of the combined num-
                       ber of accountable items under all contracts being reviewed.

                       "If the records-to-floor inventory results are in the unacceptable error range, continue with
                       Sample 2 if time permits.
 68  Random sample chart

-------
i
  I
 if
  I
        Figure 8








        III
        o
        v^


        I

                W

                Tl

-------
1 Appendix A, Random sampling
1 Random Number Table O
1 146868
1 991964
1 068575
1 024985
1 420183
1 471908
1 367201
1 135449
1 083932
1 795869
1 690966
1 148464
1 192683
1 741070
1 414750
1 911564
1 941624
1 725358
1 054053
1 912907
1 666572
1 807204
1 265006
1 281279
1 843967
1 685704
1 844360
1 786088
1 090875
1 700581
008690
600999
594659
906437
035928
368285
289453
113907
324883
627114
312064
435662
808537
798752
947038
394530
122998
007587
682045
216462
607501
081136
207883
830536
804403
550037
418471
868955
459188
648054
132396
969990
863824
585059
527965
036092
790941
263138
226102
332221
751522
872843
067504
515481
094077
329091
408496
258603
682742
562425
121024
249941
897277
519011
592663
193473
633070
160641
726611
808806
807333
711555
889357
248368
169179
198699
056022
950778
213997
241467
749593
343760
399186
254286
716530
880805
260267
229710
781418
593528
410889
738419
846967
091673
542823
929215
894012
563104
425968
529028
146135
434268
298374
424365
712570
057028
687291
072719
389272
548815
790909
837109
607762
501305
236057
254522
690183
896796
540192
252572
849303
108213
111395
149495
188515
899107
248372
654154
701839
423653
802307
963060
194752
171629
200566
680051
371673
484101
569570
232870
652824
916275
164570
552547
020016
875744
193939
023238
408186
223225
819176
482222
705396
272563
154905
219905
052832
790724
268875
979817
970189
031092
817621
766251
841841
645050
582263
098014
969903
666022
764876
437804
993901
487440
387797
311865
818986
268363
738990
012070
615935
933473
372045
595911
821149
173076
106175
886510
136654
443107
W
676440
027128 -
561594
559933 ~
582819
071116
257984
393489
281715
130369
712894
843079
162164
238453
979424 A
356333 ~
441330
757066
938799
709008
164502
376024
300369
004986
205091
113274 .
601612
676275
264636
314884 ^
70 Random numbers

-------
Appendix
Random Number Table Š
729493
837369
164985
832181
998409
485781
964613
701475
869735
422607
528700
570061
702724
979758
368116
340160
997255
129767
809137
554619
393829
485794
306493
396909
673576
301622
130318
691128
758248
471661
410855
667044
520465
312079
485206
263257
139965
182125
144821
399171
672549
601331
096120
519487
076200
615964
248649
772033
912025
975411
715080
007761
344259
132189
811206
780748
140259
241936
055951
348196
301129
464733
941691
831167
828091
424328
172351
011412
656217
048093
868664
116020
743392
360320
996329
927096
563128
400927
036669
242369
104559
225455
986632
875194
872447
905071
358791
654550
887177
526568
981512
773812
908346
842912
246553
067915
916103
754044
904345
367653
453513
723729
248223
173393
602974
791396
649646
563625
525006
574598
558200
194966
458259
269014
501595
302157
719504
648447
085665
698065
140454
866036
273918
226649
867597
275252
680021
243521
400382
762542
586040
800318
600016
599266
548495
613716
218328
447413
014529
791014
897776
359593
321911
830137
171440
779046
699034
619635
463027
539633
034480
997801
181961
958614
228752
567013
868160
806075
105235
624700
254598
625107
627940
750333
221523
971738
403679
976503
602310
855126
992388
788928
183456
737549
907128
126450
704587
534413
614087
381039
026219
472612
530103
965123
482641
708587
234770
726305
091530
714429
749559
479463
734599
375760
838994
743027
559188
343823
533227
801057
978260
035490
128035
703235
670404
633256
184820
264868
579835
085239
208126
483005
872801
655048
313639
513433
387373
136087
939999
183943
994266
088443
937183
239039
707517
170687
983292
751354
369290
369514
584551
121646
649872
999741
075310
078795
047678
704314
618046
679809
       71

-------
Appendix B. Selected sampling
                    Selected sampling
                               Appendix B
Definition
                Selected sampling is defined as a nonsrientific method of choos-
                ing other than accountable property items for inventory, based
                on the Government's degree of exposure to risk.

Application

                The property administrator must exercise judgment to deter-
                mine when a selected sample inventory is needed; selected
                sampling will not be required in all cases. The following factors
                are considerations:
                    D Government's susceptibility to loss or exposure to risk.
                    a Number of property items.
                    a Dollar value of property items.
                    D Adequacy/completeness of contractor's procedures
                      described in written property control system.

Selecting the items

                Use your judgment to decide which items to include in the inven-
                tory. Considering the Government's susceptibility to loss, select
                a variety of items (including sensitive items). The number of
                items you select is discretionary. Remember: the time you spend
                on the inventory should be proportionate to the dollar value of
                the property and the Government's vulnerability to loss.

                One suggestion for deciding how many items to inventory is to
                select half the number of items that were included in the ran-
                dom sample records-to-floor inventory. Another suggestion is to
                count the number of nonaccountable items, consult the random
                sample chart on page 68 for the sample size, and inventory half
                the sample size shown. Example: the sample size for an inven-
                tory of 325 items is 32; you would include 16 items in your
                inventory (half of 32).
72 Selecting the Items

-------
                                                      Appendix
Record the appropriate information on an inventory analysis
form. During the review, follow the instructions described in
chapter 4 for conducting a records-to-floor inventory.
                                                           73

-------
Appendix C. Categories of property control
          Categories of property control
                                Appendix C
                 Acquisition
                 The process of acquiring government property either through
                 requisition or transfer from government sources, or through pur-
                 chase or lease, including those made from contractor stores,
                 Covers the process of acquiring property; does not include report-
                 ing acquisitions to EPA (part of the reporting category).

                 Receiving
                 The process of government property initially entering into a
                 contractor's custody. Covers the contractor's system for receiv-
                 ing property, does not include decaling procedures or the
                 addition of tax and freight charges to the acquisition cost of the
                 item (part of the identification and records category).

                 Identification and records
                 The identification of government property and the official ac-
                 counting and inventory control records maintained by a
                 contractor to show property status and to control government
                 property. Includes the decaling of government properly and the
                 accuracy and completeness of the documentation kept by the
                 contractor. Does not include submitting the information to the
                 Agency.

                 Storage and movement
                 The process of storing and moving all types of government
                 property, including protection during storage and movement.
                 Movement covers the internal movement of property necessary
                 to carry out the scope of work (e.g., from the main office to a site
                 or from one site to another). It does not include the movement of
                 government property resulting from the transfer of account-
                 ability to another entity, such as the return of property to the
                 program office or a transfer to another contract (that's part of
                 disposal).

                 Property consumption
                 The process of incorporating property into an end item or other-
                 wise consuming it in performance of a contract.
74 Definitions

-------
                                                   Appendix
Utilization
The process of using equipment and materials for the
authorized purpose.

Maintenance and calibration
The process of providing the care necessary to obtain a high
quality of production and the most useful life of government
property.

Physical Inventory
The process of physically locating and counting government
property, recording the results and comparing the findings to
the records. The process includes posting findings and adjust-
ments; does not include reporting the inventory results to EPA.

Subcontract administration
The contractor's system to ensure a subcontractor's compliance
with the requirements for the control and care of government
property.

Reporting
The preparation and submission of reports showing the status of
government property as required by the FAR and the contract.

Disposal
The process of requesting and receiving disposition instructions
and effecting the disposal of government property as directed by
the property administrator.

Contract completion or termination
Procedures to be followed by the contractor upon contract com-
pletion or termination.
                                                        75

-------
Appendix D. Sensitive Items list
                  Sensitive items list
                           Appendix D
Dollar value from $300 to $999
Group #
10
51
58
58
58
58
59
67
70
74
74
77
Class
All
All
05
20
35
36
65
All
All
20
50
30
Description
Weapons
Hand tools
Telephones/telephone equipment
Cameras, TV/radio equipment
Tape players, etc.
Video equipment
Microphones and speakers
Photographic equipment
ADP and support equipment
Calculators
Dictating/recording machines
Phonographs, radios and televisions
            Nate: No ADP software or supplies will be entered into PPAS
76 Sanative Items

-------
                                                      Appendix
Property administrator addresses
                      Appendix E
        Property Administrator
        EPA Office of Administration and
          Resources Management
        26 W. Martin Luther King Drive
        Room #293
        Cincinnati, Ohio 45268
        FTS-684-7262

        Property Administrator
        EPA Office of Administration and
          Resource Management
        MD-36
        Research Triangle Park, North Carolina 27711
        BTS-629-4352

        Property Administrator
        Property Management Section
        401M Street, S.W.
        PM-215
        Washington, D.C. 20460
        FTS-475-7712             _  _   	
                                                          -77

-------
J

-------