JENTAL PFJOTSCTJOM AGS'MC'Y
Office of Air Proarams
4.11 W.' Chapel Hill Street, Durham, N.C. 27701
Office of Air Programs
Bureau of Stationary Sources Pollution Control
Division 'of Applied Technology
Emission Testing Branch
Combustion ฃ Incineration Section
Test No. 71-CI-01
Duke Power Company
Pelzer, S.C.
.February 2-4,1971
Author & Project Officer: Jerome J. Rom
John J,,* McGinnity, Acting Chief
Emission Testing Branch
Roger T. Shigehara, Chief
Combustion & Incineration Section
-------
TABLE OF CONTENTS
Page No.
"I. Introduction 2
Figure 1 - Schematic of Sampling Points 3
Table I - Summary of Results & Pollutants Sampled at
each point , 4
Table II - Average Boiler Operation During Tests 5
Table III - Ash Analysis 6
Table IV - Coal Analysis... -.;... 7
II. Summary of Results.... 8
III. Process Description ....... 8
IV. Location of .Sampling "Points". 7."..... - -10
V. "Process .Operatton'Tr. rr... . /. .*. 11
VI. ..Sampliftg^ami-'ATi'alytical Procedures -~:12~-.
A. Moisture Determination 12
B. Velocity Traverse "13
C. Particulate Sampling - APCO Train 14
D. Particulate Sampling - ASME Train 17
E. NO., Sampling 17
}\ ' .
F. Orsat Sampling... . 18
Appendix
A. Particulate Results & Calculations :. A 1-8
B. N0v Emission Data B 1-3
/\
C. Lab Results., C 1-2
p. Trip Report ' D 1-2
E. Duke Power Report...." ...-.- . E 1-4
-------
INTRODUCTION
A cooperative test program was conducted by Duke Power and the
Emission Testing Branch personnel at the Lee Steam Station, Duke
Power Company, located in Pelzer, S.C.. The tests were conducted
February 2-4, 1971. The purpose of the tests was to determine
emission levels from controlled power plants to assist in estab-
lishing new Federal Source Performance Standards. .
Measurements of total particu'Iates and NO were made at the outlet
A
of the hot side precip-itatbr-(See Figure 1) by Source Testing
Section personnel .-_us-ing-.APCO methods. Observations of visible
emissiฃHs--jiejre--a1s6 made~by a member of the Emission Testing Itean.ch.___
Total particulates were measured by Duke Power personnel using the
ASME Power Test Code 27 method at both the inlet and outlet of the
precipitator to determine the collection efficiency of the precipitator
and to compare the outlet results with those obtained by the APCO method.
Pertinent results are listed "in Tables I thru IV. Complete results
are listed in the Appendix of this report. -..-.
-------
e^lM-Ej-J^.-^g.- . "- lima***
1
Boiler
Inlet
Point
X.
Inlet
Point
Test
A
-i
ป
Fest
B
Hot Side
Precip.
Outlet Test
Point A
J,
/is.
Outlet Test
Point B
f
\
.Figure 1 - Schematic of "Sampling Points
and Pollutants Sampled at each Point :
Pollutant
Particulate
, ^_ ^----_-
Parti oil ate"""^77"-
NO..
.0
6
0
Outlet
6
6
14
Method
APCO
ASf1ฃ-
PDS
-3-
-------
TABLE 1
SUMMARY OF RESULTS
Run Number
'Date . .
' .Stack Flow Rate - SCFM'* 'dry
% Water Vapor - % Vol .
% C02 - Vol % dry
% 02 - Vol % dry
% Excess air @ sampling point
S00 Emissions - ppm dry
c.
NO Emissions - pprri dry
s\ . -~ "~. -" " ^"*
Pa rti cu ] n tes -~APCO~Tra i iff"
., Pro5efr..Cyjr!^"n.eT & Filter Catch
gr/SCF* dry
gr/CF @ Stack Conditions
Ibs./hr.
GR/SCF* dry - ASME Train
"GR/CF P Stack Conditions
Ibs./hr.
Total Catch"- APCO Train
gr /SCF *dry
gr /CF @ Stack Conditions
Ibs./hr.
1A
2/2/71
107607
6.70
15.4
3.5
19.37
278**
.1745
.0737
160.9 "
.0387
.0168
40.9
.2002
.0846
1_84.7
IB
2/2/71
106757
6.20
15.4
3.5
19.37
246**
.2556
.1114
233.8
.0771
.0335
67.4
.2819
.1228
257.9
2A
2/3/71
115729
5.92
15.3
3.2
17.32
'
251**
.1600
.0679
158.7
.0753
.0327
83.3
-
.2116
.0897
209.8
26'
2/3/71
107088
5.17
15.3
3.2
17.32
270**
^j-
.1740
.0758
159.7
.1192
.0516
108.2
.2352
.1024
21.5.9
3A
2/4/71
111477
6.49
15.3
3.3
17.98"
' 252**
.1441
.0610
137.7
.0535
.0231
53.9
.1639
.0594
156.6
3B
2/4/71
107824
4.97
15.3
3.3
17.9iT
!
1
j
247**
I
.1675
.0725 j
i
154.7 j
.1335 I
.0573
121.2
t
.1778
i
.0769
' . \
164.3
**AVerage of all samples taken during the run.
* 70"F-,29.92 '"Hg
-------
TABLE II
AVERAGE BOILER OPERATION DURING TESTS
Run No. 1 Run No. 2 Run No. 3
Unit Load - MH 108 . 108.5 108
Main Steam Temperature,ฐF 949 945 940
Main Steam Pressure, PSIG - 1272-- ' 1260 1265
Soot Blowing . -_^.--=^___.r- --None - - None As Normal
Energy Input"-- -T06~BTU7H[t. " HOI5.2 1019.9 1015,2
-------
TABLE III
ASH ANALYSIS
-------
TABLE IV
COAL ANALYSIS
-------
II. SUMMARY OF RESULTS . ...
Participate results ranged from 0.14 GR/SCF to 0.26 gr/SCF by the
APCO method considering the catch in the front portion of the train
only (from the nozzle up to and including the filter). ASME results
ranged from 0.04 GR/SCF to 0.13 GR/SCF.
NO emissions varied from an average of 246 ppm to 278 ppm.
A
Visible emissions did not exceed 10% opacity. Soot blowing had no
noticeable effect on"ttfe 'opacity of the plume. '. . - -
HI. PROCESS;QESCRi-PTtON" ~ ..',' " ,. \- ' . . ... --
The tests were conducted on the emissions from Unit #1 at the Lee Steam
Station. Unit ;^1 has a Combustion Engineering 750,000 lbs./hr., triple
drum, natural circulation, tangentially fired boiler. This boiler produces
the steam to drive a General Electric 90 MW hydrogen cooled turbine -
generator.
-------
IV. LOCATION OF SAMPLING POINTS.
The two 9' X 12' precipitator outlet ducts were divided into 45 equal
areas for velocity traverses and particulate sampling by the APCO method.
The south duct was Tabled "A" and the north duct (nearest the river)"B'.'
Each duct.had 5 equally spaced sampling ports along the 1Z' length. The
9' width was divided into 9 equal spaces thus forming the 45 equal areas
(Figure 3).
Top View of Ducts
9'
SSL
1 ,
A
:"-""' '"- ' ' ' ' '
B
C
D
E
F
G
H
I
fff - j^y
- -
- ~
n
LJ
'.. 12' .. _
V
n
LJ
Li
^i
-_
4 28 3/4 ->
n
LJ
14 3/8"
1
- 3
Figure 3
10
-------
The sampling ports were approximately 28 ft. from a bend in the duct.
The precipitator inlet ducts were divided into 10 equal areas for the
purposes of velocity traverses and participate sampling by the ASHE method,
Precipitator outlet ducts were divided into 15 equal areas (Figure 4)
for the ASME sampling.
9'
:&.
Precipitator Outlet Ducts
'** . - -., , j , -. , , , , 1^' , . r.. . ' V 1
Sปป " 1 c. '" Fi
A .,_
B
_1_. CT -
~- - T**^-.
--" - "
.-_ , -.__
n
_TT
_ ^n
^T"
-ป>-~ .
i*^*j "** * --
j f - if M M ]_
J ซ,J 1 J-J1 ta .1 -^-J l-ป*-i.
r^_ 28 3/4"4| .-...-
1 2 3 45
Figure 4 " ' ;:V"'. ' -'; -: '<-". '
All NO. samples were taken thru port #3 in both ducts except the samples
for run number 2 at duct B which were taken thru port #4.
V. PROCESS OPERATION . -.' , ' ' ' . ".' ''-''. v /.', .^-- ':'.'.
Pulverized coal is tangentially fired into a triple drum boiler to
f
producer steam. The steam produced is used to drive a 90 MW turbine- )
generator. Normally the unit is operated so as to produce about 110 MW
of electricity, burning approximately 40 tons of pulverized coal per hour.
. 11
-------
The gaseous emissions from the boiler are directed through a hot side
precipitator to control participate emissions. From the precipitator
the gases exit through a stack.
Soot is removed from the system by blowing steam when and where needed.
Process operation was as normal during Runs Number 1 and 2 except that
soot blowing was eliminated. Run- Number 3 incorporated soot blowing as
normal to see if any increase in emissions could be detected.
VI. SAMPLING AND ANALYTICAL.PROCEDURES- ' '
A. flo-is-ture_Deterinination" . ~ซ~~- .
Per cent moisture in the stack gas was determined by pulling a
measured volume of stack gas through a heated probe and into a
preweighed midget impinger containing 15 mis. of water and sitting
in an ice bucket. The per cent moisture was calculated from the
gain in weight of the impinger due to the water collected, and the
volume of gas pulled through the impinger. A schematic of the
moisture train is shown in r-'igure 5.
12
-------
Heated Probe
:ice Bath :
Impfnger *
Rptcineter..
Figure 5 - Moisture Train
8. Velocity Traverse
Velocity pressure and temperature measurements were taken in the
center of each of the 45 areas shown fn Figure 3 by Source Test
Section personnel. The velocity pressure was measured using an
S-type pi tot tube and oil manometer, and the temperature determined
using a chromaJ.-alumel thermocouple connected to a potentiometer.
Velocity,;gressure and temperature measurements were made at_the
center of each of 10 equal, areas in each inlet duct and the center
of each of the 15 equal areas (Figure 4) in the outlet ducts by
Duke Power personnel.
Velocity pressures were measured using a standard pitot tube
connected to an oil manometer. Temperatures were measured using
a thermocouple connected to a potentiometer.
13
-------
C. Particulate Sampling -'APCO Train
The APCO participate sampling train (Figure 6) consists of a
stainless steel nozzle (l),an Incoloy 825-10' probe (2), a cyclone
(4), and a filter holder (5) in a heated section (6) of the sample
box. The filter holder contained a 2 1/4" glass fiber filter (MSA
1106 BH). Beyond the filter was a modified Greenburg-Smith impinger
(8) containing 100 ml. H^O, a second Greenburg-Smith impinger not
modified (9) containing 100 ml. H?0, a third impinger (10) of the
modified Greenburg-Smith design left dry, and a fourth modified
Greenburg-Smith imp-inger -(11 ) containing approximately 175 grams
of accurately we_ighed_Jndieating silica gel. The impingers are
. JDijied-by_glass connectors and are in the ice bath section^?) of
the sample box. , .. " .
The sample box is connected to the meter box by an umbilical cord (14),
The umbilical cord has a thermometer (12) and check valve (13) on the
sample box end. The thermometer indicates the temperature of the gas
leaving the last impinger, and the check valve prevents gas from
backing up in the impingers thus forcing water from the impingers into
the filter when the system is turned off. ..
The meter bo,* contains a vacuum gauge (15) to measure the pressure
"drop across the sampling train, an on-off valve (16) and a by-pass
valve (18) to adjust the gas flow rate through the train. Next is
14
-------
a leak!ess vacuum pump (17) to pull the gas through the train, a dry
gas meter (19) to measure the total amount of dry gas sampled, and
an orifice,(20) connected to an oil manometer (21) to indicate in-
stantaneous gas flow through the train. The dry gas meter contains
inlet and outlet thermometers (12) to measure meter temperatures.
An S-type pitot tube (22) is attached to the probe. This pitot
tube is connected across an oil manometer to continuously measure
velocity pressure while sampling.
A thermocouple was~~tape'd to th'e probe and connected to a potentio-
meter to ind-ica-te-stack temperature.
A velocity traverse was taken in each duct by positioning the pitot .
and thermocouple in the center of each of the equal areas shown in
Figure 3. The data from these traverses was used to determine the
nozzle size needed to sample isokinetically and at a rate of approxi-
mately 0.75 cfm. The center of each of these equal areas was sampled
isokinetically for 3 minutes for a total of 135 minutes per each test
run. Isokinetic flow was maintained using the nomograph described in
the test procedures. Any deviation from the standard procedures are
explained in the Appendix. Complete test procedures are available from
OAP upon request. ' .
15
-------
Figure 6 -APCO Participate Train
-------
D., Particulate Sampling -ASME Train
Velocity traverses were taken in both the precipitator inlet
and outlet ducts using a standard pitot tube, and thermocouple
and potentiometer. The traverse data was used to select a sampling
nozzle size which would permit isokinetic sampling at a rate of
about 1 cfm through the meter. The same data v/as used to determine
the isokinetic sampling rates used in each area.
The sampling train consisted of a nozzle, a thimble holder containing
a tared alundum thTmbleT probe, condenser, dry gas meter, and- ejector.
The temperaturerancr pressure at the meter were monitored so that the
f"*9aT'sampled could be calculated-to standard condrbiens
Ten equal areas were sampled in the precipitator inlet ducts and
15 equal areas (see Figure 4) were sampled in the precipitator out-
let ducts. . ..... .....
Procedures were followed as given in'Power Test Code 27.
E. NO Sampling
Samples were collected in an evacuated flask of known volume
coDtaining 25*ml. of a dilute solution of I-L02 and t-L SO,. The
-- ~ ~" * * ~~ ' t
pressure and temperature of the flask was measured before and after
sampling so that the sample volume could be adjusted to standard
17
-------
conditions.
To analyze for NO the solution was evaporated to dryness and treated
A
with phenoldisulfonic acid reagent and ammonium hydroxide and measured
colorimetrically. ' '
F. Orsat Sample .-'.'
Integrated samples for C02 and Op were collected in Tediar bags
over the whole test period and analyzed using an orsat.
All APCO pro-cedu-res- ar-e- available upon request.
13
-------
Appendix A
-------
RF.PUUT NO.
PAGE
PAGES
SOURCE TESTING CALCULATION FORMS
Test. No.____
Name of Fi rni__J)jjke__Ppj//er_ -_Efilz&t,JL.JL,.
Location of Plant__p_eLze_rx.^_._jQ.. _
Type of Plant Co
No, Runs___3
Control Equi prnent Hot Side Precipitators .
Sampl i ng Poi nt Locati ons Qa.t].at_.D.acฑs,_fcQ!!.L-ฃne.ca.pjฑ5tQrs^
Po11utants Sampled ' Particulate, SQg^ N0:<, Visible Emissions
Time of Participate Test': . ''
Run Mo.__ 1 Date 2/2/2J Be9in lj_3.0__Pjv
Run No. 2 . Datir__2;/^/-2.L_I Begin _liOJLM
R,u n No. 3 ...., r^=~0a4e; _-:^g/4/71; j:. Ceg i n ]j
PARTICULATE EMISSION DATA
Run No.
P barometric pressure, "iig Absolute
p orifice pressure drop, "H00
_. n? _.. .. .<-.
V, volume of dry gas sampled @ meter
conditions, ft.3
Tm Average Gas Meter Temperature, ฐF
V Volume of Dry Gas Sampled @ Standard
'std. 6'onditions, ft.3
V Total HJ3 collected, ml;, Impingers
w & Silica! Gel.
>tandard
JPS
1A J IB
29.74
2L23
99.28'
64
00.28
52.0
29.74
2,13
99.74
65
2A j 2B
i
29.78129.78
2,50
102. 5^
"ซ 1
' ' 1
100.53T05-.6
140.0
140. 0
2J7
3A
"^R !
! ~"!
29.58 29.58 !
2.33 2.15 i
99, 09 |l 00. 00. 99.97
,?
52
102.55
1.18.0
62
100.88
147.6
55
..
102.18
112.7
V61uv,:e of""l'.'atc'r" Vapor Collected
ft.3 (3 Standard Conditions*
7.20 6.64 '6.6.4
5.59 7.00. 5.34!
i j
* 70 F, 29.92" Hg.-
A-l
-------
PARTICULATil EMISSION DATA (cont'd)
Run No.
i" "I
XM - % Moisture in the stack gas by volume
M. - Hole fraction of dry gas
% co2
% Qy
- - , ....... ' . . . . .
% N2 '
M H , - Molecular weight. of dry stack gas
M W - Molecular weight of stack gas
. ... - ,
PS - Stack Pressure-; '"tig .-"Absolute "
V - Stack^ Velocity @ stack ^conditions, fpm
.._ ..,. _ */
A - Stack -Arear ]n,-
Q - Stack Gns Volume @
s Standard Conditions, SCFM dry
T - Net Time of Test, m1n.
L>
0 - Sampling Nozzle Diameter, in.
/ '
%I - Percent isokinetic
m* . - Participate - probe, cyclone
and filter, nig.
m - Parti cu late - total, nig.
C - Parti cul ate - probe s cyclone,
an and filter, gr/SCF
C - Parti cul ate -'"total, gr/SCF
ao . - -
j C , - Parti cul ate - probe, cyclone, & f i i tet
[ gr/cf @ stack conditions
1
1A
6 . 70
0.93
15.4
3.5 .
81.1
30.6
29.72
679
15.97
29.23
2357.0
1555-5
107607
135
.375
; 96.91
1136.0
1303.7
. .1745 '
,'.
^002
.0737
IB
6.20
0.94
15.4
3.5
....... ,B.1J.
30.6
29.84
656
15.33.
29.23
2266.8
15552
106757
135
.377
96 '. 88
1668.7
1840.3
.2556
.2891
.1114
2A
5.92
0.94
15.3
3.2
.81. .5
30.6
29.84
638
29.27
2524.3
~ -
"15552 j
1
115729
135
i
.375
94.89
1097.5
... .... , ,
1451.3
.1600 .
.2116
'.0679
A~2
-------
PARTICULATE EMISSION DATA (cont'd)
Run No.
%M - % Moisture in the stack gas by volume
M, - Mole fraction of dry gas
% co2
a n
* ?
% N? :
M H , - Molecular weight .of dry stack gas
M W - Molecular weight of stack gas
APs - Velocity Head of stack gas, In. HO
T - Stack Temperature, F
[ZD^~y460)~ _ -~- -- -- ;
^ PS - Stack Pressurer-'Hg-^Abstrlute -
V --.Stack -yelo-e-vty (3 stack conditions, fpm
^ '--._*.. ^
' A - Stack Area, in.- '.
Q - Stack Gas Volume @ *
Standard Conditions, SCFM
T. - Met Time of Test, m1n.
V
0 - Sampling Nozzle Diameter, in.
%! - Percent isokinetic
nu - - Particulate - probe, cyclone
and filter, mg.
m - Particulate - total, mg.
w
C - Particulate - probe, cyclone,
an and filter, gr/SCF . ' - .
| C -.Particulate - total ,' or/SCF
ao
1 C ,. - Particular - probe, cyclone, & filter
gr/cf @ stack conditions.
2B
_ 5.17
0.95
15.3
3.2
81.5
30.6
29.97
67(1
15.49
29.27
2275.0
15552
1070S8
135
.375
99 . 58
1159.0
1566.1
.l"740~----.
.2352 '
.0758
3A
6.49
0.94
15.3
- 3.3
_ai.4__
30.6
29.84
6R2
16.49
29.07
2435.5 ""
15552
111477
135
.375
94.10
944.0
1073.8
.. .1441-
.1639
.0610
3B
' 4.97
0,95
15.3
3.3
81.4.....
30.6
29.97
670
- 15.65
29.07
2306 r4 ,
15552 !
107824
135
.372 |
97.50
.
1111.7
1179.5'
.1675
.1778-
.0725
A-3
-------
rr-.x\ ILULM ; i:
Run No.
C, ( - Parti cu 1 ate,.. tota.L, gr/cf
a" 0 stack cond.
C - Particulate, probs, cyc!onef
c:W and filler, Ib/hr.
C - Participate - total, Ib/hr.
% EA - % Exccs5 air G>
saropl ing point
'70ฐF. 29.92" Kg.
1A
.084f
IB
2A
2B 3A
3B
d22^-^?^^2^ -0694 -075-
160.233.8 158.}
JMJL25.Z-.Sf
19.37
159.7 137.7
154.1\
A-4 -;
-------
PARTI GUIATE CALCULATIONS
1. Volume of c!ry gas sampled at standard conditions - 70ฐF, 29.92"
'
mstd a 17.7 X v?R -I- P
: . . . md B
/
(Tra * 460) '
2. Volume of water vapor at 70ฐF & 29.92" Hg, Ft.3
wgas- ซ 0.0474 X V = Ft.3
Vs
3. % moisture ih stack gas -- -.
*N ป 100 X V. " '. --^- -
;_....,..__._^
mstd wgas .
4. Mole fraction of dr,- gas
,'."' H ป 100 ".._?M .V':-r' . . >:
.; . d 100
' . . pf
5.. Avernna molecular v.'ilnht of dry stack gas
X fcV
A-5
-------
3, Molecular weight of stack gas
'r' -M.W.' ป M.U.j X Hd -5- 18 (1 - Md)
%"-' 7. Stack velocity @ s-tack conditions, fpm
' "
1/2 ซ
fpm
8. Stack gas volume @ standard conditions* SCFM
0.123XVsXAsXMdXPs
(T + 460)
. '9. Per cent isokinotie
%I .
= 1032 X (le + 460) X V,
rrt
II!
10. Pavtlculato - p?'c;J;e9 cyclona, S filter, gr/SCF
C.5n = 0.0154 X Mf = gr/SCF
ail
,', . '^.:;;-'^- .. m std., .
A-6
-------
11... Particulate total, gr/SCF
r
- - Cao = 0.0154 X l-\t = gr/SCF
m std.
12. Participate - probe, cyclone & filter,
gr/CF at stack conditions
r - 17.7 X C X P 'X M. ซ Gr/CF
Vt " '' a
(T + 460)
13. Participate - total, gr/CF @ stack conditions
Cau
14. Particulate - probe, cyclone, & filter, Ib/hr.
Caw = 0.00857 X Can X Qs = Ib/hr.
15. Particulato - total, Ib/hr.
XCaoX V=l b/hr.
A-7
-------
16.... % excess air at campling point
% EA
= '100 X
0.266 X % 11 - % 0 = %
' r' ^ ? * "^
-------
Appendix B
-------
NOV EMISSION DATA
A
Run No.
.Date
nig N0? '
Tc - Flask Temperature, ฐF
V.,- - Flask Volume, liters
P. - Initial Flask Vacuum, "Hg.
' X
P.- Final Flask Vacuum, "Hg.
ppm NO?
2A
2/2/71
0.925
.60
2.043
25
0
279.0
3A
2/2/71
1.065
60
2.061
25
0
318.5
4A
2/2/71
0.785
60
2.046
25
0
236.5
._ ,
2/2/71
0.810
55
,
2.095
25
b
236.0
2.8
2/2/71
0.915
55
2.096
... ., u...
26"
0-
256.2
.
... . ,.. ,_. _ j
. .-
(iy-M60)
\
ppm N0"
Vf X (P. - Pf)
B-l
-------
NOV EMISSION DATA
A
-: - - - -
Run Mo.
.Date
mg N0?
I* - Flask Temperature', ฐF
Vf - Flask Volume, liters
Pi - Initial Flask Vacuum, "Hg.
Pf- Final Flask Vacuum, "Hg.
ppซi NC^ .
5A_
2/3/71
0.940
50
2.095
25
0
271. 2_j
. 6A
2/3/71
0 900
50
2.059
25
0
_2&L2_
7A
2/3/71
0 750
50
2.079
25
0
_mj_
__3B____
2/3/71
L
__
48
2/3/71
0.865
50.
2.097
25
0
-,-, - , -
._Z4.9^3
--. rL ,. .. j
J_B_____
2/3/71
0 990
50
2.061
25
0
.zaa_4__
"X (T^ + 460)
ppm NO9=
Vf X (P.
Pf)
B-2
-------
)v EMISSION DATA
A -
Run No.
.
.Date
mg NQ?
Tr - Flask Temperature, F
V,: - Flask Volume, liters
P. - Initial Flask Vacuum, "Hg.
Pf- Final Flask Vacuum, "Hg.
ppm HO,
8A
2/4/71
0.900
45
2.073
25
0
9W.Q
9A
2/4/71
"
0.840
45
2.065
25
0
?/n q
10A
2/4/71
_
68
2/4/71
0.865
45
2.071
25
0
u
?5n n
7B
2/4/71
0.865
40
2.103
25
0
i.
?A? R
T
X' (T.-+ 460)
'
. ..ppm
Vf X (P. (- Pf)
B-3
-------
Appendix C
-------
9 3
''"*"" ฃ$
^.,
_33Y,A.
, I
(
T
iฃ. ,f*iซ7
/
- ป
-'i ^MJ^I, 4..,.
__.^
(1,9.^
s-/
0,
-------
/
-:.
r
C-2
-------
Appendix D
-------
f _ , _.
j >
s February 23^ 1971
ENVIRGIIMEN7AL PROTCCTlOiJ AGENCY
Air Pollution Control Office
Reply to -
Atin o-i3? ' Source Testing SaGt1onป DA, BAG
Subject: -Soyrca Testing of Duke- Pc-.Jsr Plant, GraenvWe, SปC,
Tos John L. McG1nn1ty0 Chief, Engr. Br.,DAB BAG
THROUGH: James 0, Dealyc Chief,, Source Testing Section
1. Source test personnel visited the lea Steam Station0 Duko '
Power Company 8 February 1 through 4 to tsst unit- no, 1. The?
following goverruTant personnel wora Involved?
Hark Hooper Ray Hob ley
M1ke SlavlnsJcy Allan Riley
Jerry Rom - Stan Blacker DAQEO
Bill GHmley Jawes Ko'ily
Ed McCarlcy ' '
Gone Riley _
Bob Martin -- - - ^
2. Duke Povfl&r-sflf,ip1ed-3irriu1t:dneous1y with Af>CO using tho AS"ฃ
i Personnel Involved in testing from Duks Power aro listed
wr -*"'" ... ^~_-- ._
Bob Carpenter -:
Jim Snyder , . .'..... . _.-
T\A ^ v> -? r- ,-\ p. ,r> V * ป.-,-J- #ป
Evsrctta Yelton . .
Jim Hards on ' ,
Mlltcn K-j-Itilit . .'
David Martin
CoO. Hu.-nphrios
Bill Kino
V . . p . i * 5 ; r ! i :ซ
38 The tosts worn obsnrva-J by ths foil :;., -Ing visitors 2/2
Earl Povmrs ป Se C, Pollution Contract
Otto Pearson - S. Co Pollution Contract . ' '
Ed Galloway - C1nti. Gas and Electric
Dick Thorsel'S - EEI .
0-1
-------
Pago 2 - John U McSinnity
Yh3 tests-wars ofosarvod by the following visitors 2/3.
Alex Covo'll - Ccrft'iStlcn gr^ln-:
Ch;;ck Bldkosel't ป C''.,bust1on En
4, Sampjes v;-:rc obtained for particul;itc-s, N0._:9 and vlcrlh'Ia
crslsslcns using APCO n;jtlinc!3 specified in the Krocedyrea for
Porfononnco Tooting of Fual-burrslng ({qulpmc-nts. Second Draftsซ
Tha following oxeoptions v/ora mada to thts test procedure.
a0 Tha duct was divided Into 45 equal areas for tasting.
The areas warฎ V2]< X 20.8", slightly larger than tha
maximum specified ratio of 2/1.
bป Tfirsa i!9, san^plai; v/-ara takon during each run from tha
center of th$ duct cnly and not fro/n two points as specified*
c. The moisture do Gemination was made using 2 bubblov^s In
the train Instoad of tha specified bubbler.
do Par cant 1so?dr.c-t^e _v?as calculated using tha "aquation
from SourC'3"Tc3t1n?j"calculation forsns for Incinerators and
not th'ty'-ctiluifJcn spoc-ifjod In the Procedures.
' eป J^P.^^'ป SQR'P12S wซ?"^ obtained.
"?f:Two nrns v-.'Qfa c-oruiuctad Incorporating no soot bTovrlng. --
Ons> run was conducted o'yring scot blowing.
g* . CiJai C.i'^a tcucuiiicJ fvt1?;] 'cii;: piant wi'll ba ur>x?d in
calculating excess a1rป The bag sample dcita obtained was
. Inconsistent and appeared to be lev;.
50 Duks Pov/e?* peruonra'! sampled 15 equal areas 1n each duct
using the ASME insthod* Thay also sampled the 1n'!ot to the prs
c1p1t.5tor as '=;::]] as tho c'itlet. '
.'
6. D^ta Cf>t:vij";^d by both test groups K-U copied and ojcchancjad.
Ccr^ploto rtfsuKn will b.i axchangod c.i ;;con as the analytical
report Is rovlos-d and t!:n ncccssav"' d.ifcn calcu'!atad0
Source Tsiit Tecini
s~ .
eet Mark Hooper
Mike Slavlnsky Mle: 71 OAK
D-2
-------
Appendix
-------
DUKE PovniTf; COMPANY
i ,
Pcfrn'.a BOII.PIMO
433 SOUTH CHUKCH ST.T;E;:T, G:u,.-u.oTTi!, N. C.
A. C Trnao p O- Sox si TO
v>cs Putoiotirt no:!o>
February 26, 1971 .. . ...
Mr. Mark H. Hooper
APCO EPA ' .
411 West Chapel Hill Street
Durham, North Carolina 27701
Subject: Lee Steam Station
Unit No. 1
Electrostatic Precipitator
Joint Emission Test
Duke Power - 'APCO
February 1-5, 1971 .
Dear Mr. Hooper: ----- ..;.~ ._ . --
Enclosed you will find two cop ieja. of our tabulation of data and reaulta
from the subject test. At your earliest convenience, would you please
send us copi'eff" oฃ^our~re3ults."~ This is in accordance with the agreements
which we made ptto-y-tb the teat. . _^,_
After we receive your results, we will send you a copy of our teat report
which will include a coupariaion of your results and ours..
We call your attention particularly to Item 12 , "Coal Analysis, As Fired,"
in our tabulation. This was requested by your Mr. James Kelly. When he
was at Lee on February 5, 1971, we gave him coal samples from the test,
but he indicated that he did not have the equipment to. check the samples
for BTU , aah? moisture, and sulfur. . .
One unusual aad unexpected condition that we had during the test van <:ao
sulfur content of the coal. .It ran from 1.90 to 2.092. This uaa an
abnormal condition because our sulfur generally runs frota about .0.5 to
1.5%. V7e do not believe that this had any effect on' the performance of
this hot precipitator because ash conductivity varies 30 slightly with
sulfur in the 700ฐ F range.
)' truly yours,
A. C. Thies, Vice President
Production and Operation
RRC:vr -
Enclosures E-l
-------
LF '-STEAK STATION, USIT HO. 1
JO'^T "EMISSION TEST
DUKE POWER AND APCO
TABULATION 0? DATA AND RESULTS
(BY DUKE POWER COMPANY)
n
i
ro
I.
2.
3.
4.
5.
.6'.
' 1.
8.
9,
10.
11,
12.
V
13.
1.4,
Date
Run
Unit Load
Steam Flow
Main Stearu Teraperauure
Main Steaa Pressure
Reheat S tears Temperature
C02 . :'
C'2
'Condenser ABP
Baroraeter
Coal Ane.lyais, As l-'isred
BTU
Ash
Moisture '.
Sulphur
Precipitate.: Efficiency
' A Side
, 3 Side
Average
Precipitator Gas Flow-
A. At Duct Conditions
A__Sj.dc_
Inlet
Outlet '
Average
.v B Side
Inlet '
.Outlet
Average
A & B Total
B. At Contract Conditions
A Side
Inlet
Outlet;
Average
2-2-71
' '' 1
; KM ' 108
M-Lbซs/Hr ' 795
V| ft , ..949
^s;ic 1272
l|?iT : 951
'!'.? . 15.3
1 '% . , '3,50
"kg ! '. ' 0.78
- "Kg j| ' 29.72
' *
BTU/Lb: ' ! 11605
% j , ; 16.22 -
% 1. 5.36
% ;;.f -1.93
%
,
: . 99.21
' ' 98.52
98.37
2-3-71
2
108.5 ,
793
945
1260
940
15.3
'3.50
0.68
29.80
11979
15,65
. 4.84
1.90
98.48
97.53
98.00
2-4-71
3
103
790
940
1256
935
15.3
3.50
0,68
29.55
11690
15.10
6.75
2.09
98 . 88
97.44
98.16
Average
108.2
'- 792.7
. 944,6
i 1266
! ' 942
' 15.3
3.50
0.71
; 29.69
t
I
i 11758
15,65
5.65
, 1.97
93.86
97.83
98.35
AFGi
271,771
239,047
230,409
241,963
236,481
239,222
519,631
277,703
297-,798
287,751
257,386
299,032
278,209
243,454
242,741
243,098
522,307
262,924
308,099
285,508
253,809
273,100
263,455
242,352
242,806
242,579
506,034
260,104
282,506
271,305
260,989
287,060
274,024
242,590
240,675
<*}-, C."i*>
ฃ -4 J. 3 O .^ J '
515,651
266,910
296,134
281,521
-------
TABULATION OF DATA AND RESULTS (cont'd)
n
i
Co
\\ T
Oj,
In. E?0
Inlet
Outlet
i ' Average
' ' A & S Total
15. Duct Temperature
; A Inlet
'; B Inlet - '
i Average
. A Outlet
B Outlet .. .. '
Average
16. Temperature Drop
Across Precipitator
.17. Duct Pressure
A Inlet . ' '
B Inlet . '
, Average
A Outlet
B Outlet
Average
13. Duct Loadings (Not for Efficiency Cal.)
At Duct Conditions . . GRAINS/ACF
A. Leaving Stack
.'' A Side
B Side
Average
B, At Precipitator Outlet
A Side
3 Side
Average
At Precipitator Inlet
A Side
B Side
Average
\
248,005
244,134
"' 246,070
533,321
. 679.3
'i 676.2
;| 677.3
, j 669. 2
'' '667.7
J663.5
249,151
250,056
249,604
531,112
630.0
677.9
673.9
. 663.4
669.3
668.8
249,720
252,178 -.
250,949 i '
522,254
676.0 ;
669.9 .
672.9
' 664.3
660,6
662,5 -
248,959
248,739
248,374
530,395
673,4
674.7
676.6
667.3
665.9
666.6
9.3
0.0245
0.0478
0.0362
0.0168
0.0335
0..0252
2.0840
2.1203
2.1022
10,1
0,0475
0,0750
0.0613
0.0327
0.0516
0.0422
2,1518
2.1060
2.1289
10.4
0.0332
0.0322
0.0577
0.0231
0.0573
0.0402
2.0121
2.2261
2.1191'
10.0
-6.72
-6.47
-6.60
-6. S3
-6.70 '
-6,79
-6,48
-6,47
- ' -6.43
-6.33
-6.61 '
" '-6.72
-6.67
' -6.62
, -6.65
-7.01
-6. S3
'-6.92
-6.62
-6.52
-6.58
- -6.91
-6.71
-6. 31
0.0351
0,0633
0.0517
0.0242
0.0475
0.0358
2.0826
2.1508
2.1167
-------
20,
21.
22,
Dust Loadings (For -Efficiency Caic.)
; ac 32ฐ? and 29.92 "Kg
A. 'At Prccipitator Outlet
iA1 Side :
;5 Side
Average
B. .At Precipitator Inlet
A Side
' B Bide
Average
Energy Input , -
Emission Rate
Outside Ambient Tarnoerature
I"
K ' "
'y "
;T:..
ATION 0? DATA AND RESULTS (cont'd) -
GRAINS /,CF
; . ; * .
VJ 4
1 ! 1
' ' i '
: i j
1C6 BTU/Hr.
Lbs/10ฐ BTU<
"ฐF- '
0.0418 0.0813
0.0832 ' ' 0.1286
0.0625 . '. 0.1050 -
;5:j2S80 5.3439
J5J6253 5.2035
I5J4567 5.2737
l6l5. 2 1019.9
i '* ป
). 11056 - 0.18524
: 35 30 - -
0.0577
0.1440
0.1009
5.1567 '
5.6296
5.3918
1015.2
0.17175
32
. N. T . '
V . T
<-
i
0.0669
.0.1186
0.0395
5.2629
5.4852
5.3741
1016.8
0.155S5
32.3
i *
2/22/71
RRC/vr
\
------- |