United States
                Environmental Protection
                Agency
Air and Energy Engineering
Research Laboratory
Research Triangle Park NC 27711
                Research and Development
EPA/600/S7-90/021  Mar. 1991
EPA       Project Summary
                 Retrofit  Costs  for  SO2 and  NOX
                 Control  Options at 200
                 Coal-Fired  Plants
                Thomas E. Emmel and Mehdi Maibodi
                  This report documents the results of
                a study to significantly improve engi-
                neering cost estimates currently being
                used to evaluate the economic effects
                of applying sulfur dioxide (SO2) and ni-
                trogen oxides (NO,) controls at 200
                large SO2-  emitting  coal-fired  utility
                plants. To accomplish  the  objective,
                procedures  were developed  and used
                that account for site-specific retrofit
                factors. The site-specific Information
                was obtained from aerial photographs,
                generally available data bases, and in-
                put from utility companies. Cost esti-
                mates are presented for six control
                technologies: lime/limestone  flue gas
                desulfurlzation, lime spray drying, coal
                switching and cleaning, furnace  and
                duct sorbent Injection,  low NO, com-
                bustion or natural gas reburn, a'nd se-
                lective catalytic reduction. Although the
                cost estimates provide useful site-spe-
                cific cost information on retrofitting acid
                gas controls, the costs are estimated
                for a specific time  period and do not
                reflect future changes in boiler and coal
                characteristics (e.g.,  capacity factors
                and fuel prices) or significant changes
                in control technology cost and perfor-
                mance.
                  This Project Summary was developed
                by EPA's  Air and Energy Engineering
                Research Laboratory,  Research  Tri-
                angle Park,  NC, to announce key find-
                ings of the research project that is fully
                documented in a separate report of the
                same title (see Project Report ordering
                information at back).
Introduction
   The National Acid  Precipitation As-
sessment  Program  (NAPAP) is respon-
sible for developing cost and performance
information on various methods for reduc-
ing the emissions of acid rain precursors.
Coal-fired  utility boilers are major emitters
of sulfur dioxide (SO,,) and nitrogen oxides
(NOJ. However, estimating the cost and
performance of SO2 and NO controls for
coal-fired  power plants  is difficult due  to
differences in plant layout and boiler de-
sign.
  The objective of this study was to sig-
nificantly improve the accuracy  of engi-
neering cost estimates  used to evaluate
the economic effects of applying SO. and
NO  controls  at 200 large SO2-emitting
coal-fired  utility  plants.  This project was
conducted in four phases  as shown  in
Figure 1. In Phase I, detailed, site-specific
procedures were developed with input from
the technical advisory committee. In Phase
II, these procedures were used to evalu-
ate  retrofit costs at 12 plants based on
data collected from site visits. Based on
the results of this effort, simplified proce-
dures were developed  to estimate  site-
specific costs without conducting site vis-
its. In Phase III, the simplified procedures
were verified or modified based on utility
input by visiting 6 of the 50 plants. The
modified procedures  were then  used  to
estimate  retrofit costs at the remaining
138 plants. In Phase IV, utility comments
were incorporated into the final 200-plant
study report.


-------
           Phase I
        Develop Detailed
          Procedures
            Phase II
       Select 12 Plants and
          Develop Cost/
      Performance Estimates

      Revise Procedures and
        Cost Estimates and
        Develop Simplified
           Procedures
           Phase ///
       Evaluate 50 Plants

         Very Simplified
    Procedures with Visits to
          Six Plants

     Modify Procedures and
    Evaluate Remaining 138
            Plants
            Phase IV
        Finalize 200-Plant
          Study Report
Figure 1.  200-Plant study technical approach.
  This report presents the cost estimates
developed for 631 out of 662 boilers  in
200 plants using the simplified procedures.
Costs were  not developed for 31 boilers
because either they were burning  fuels
other than coal or they were new boilers
with  S(X  and NO, controls already in-
stalled. The commercial and developmen-
tal SO2 and  NOH control  technologies
evaluated  in the  study are listed  in Table
1. The detailed cost estimates developed
for 55 boilers in the  12 plants evaluated
using the detailed procedures are  pre-
sented in another report. The cost results
for all the  boilers evaluated  in this report
            Technical Advisory
               Committee


          —EPRI
          —EPA
          —DOE
          —Utility Air Regulatory Group
          —TVA
          —Natural Resource
            Defense Council
          —Vendors
              Utility Companies

           —Ohio Edison
           —American Electric Power
           —Ohio Electric Utility
             Institute
           —TVA
           —Kentucky Utilities
           —Union Electric
           —Cincinnati Gas S Electric
                  200 Plant
              Utility Companies
are presented in a database file for further
study and evaluation.
Methodology
  For  each plant,  a boiler  profile  was
completed  using sources of public  infor-
mation, the primary source  being the En-
ergy Information Administration (EIA) Form
767. Additionally, boiler design data were
obtained from  generally available data
bases, and aerial photographs  were ob-
tained  from state and federal  agencies.
The  plant and boiler profile information is
used  to  develop the input data for  ''
performance and cost models. The pc
mance and cost results incorporate .
ommendations from utility companies and
a technical advisory group. The advisory
group  included  utility  industry,  flue gas
desulfurization  (FGD)  vendor,  and gov-
ernment  agency representatives.
  All  of  the cost estimates were devel-
oped  using the Integrated Air  Pollution
Control System (IAPCS) cost model. The
IAPCS model was upgraded to include all
of the technologies being evaluated in this
program. All of the cost estimates were
developed  using the integrated technolo-
gies evaluated in this program. Evaluated
qualitatively without cost estimates were
life  extensions using fluidized bed com-
bustion and coal  gasification combined
cycle.
  Figure 2 presents the methodology used
to develop  IAPCS inputs to estimate site-
specific costs  of retrofitting SO,  and NOx
controls. The  site-specific  information
sources  were used  to develop  process
area retrofit multipliers, scope adder costs,
and boiler  and coal  parameters.  This in-
formation was  input to the IAPCS cost
model that  generated the capital, operat-
ing and maintenance (O&M), and levelized
annual costs of control  and the emission
reductions. The process area retrofit
culty  multipliers and  scope adder c
used to adjust generic cost model outpu..
to reflect site-specific  retrofit situations
were derived from an Electric Power Re-
search Institute (EPRI) report.
  Table  2  summarizes  the economic
bases used to develop the cost estimates.

Summary of Cost Results
  This section summarizes the  she-spe-
cific control cost estimates developed for
each  boiler evaluated.  The number of
boilers varied for each control technology
for reasons discussed under each control
technology summary.  For example,  low
NOt burners were not  evaluated  on  cy-
clone-fired  boilers because this technol-
ogy is not being developed for  cyclone
boilers (slagging combustors were not  ad-
dressed  under this  study). For  cyclone
boilers  and other  wet bottom  boilers,
natural gas reburning (NGR) was evalu-
ated for NOM control.
  For each control technology, the follow-
ing  three figures are presented: Capital
costs  (dollars/kilowatt),  levelized  annual
costs  (mills/kilowatt  hour), and  cost  per
ton of acid gas removed (dollarsAon), each
plotted versus the sum of megawatts. The
x-axis (sum of megawatts) is the cumu'a-
tive sum of the boiler size sorted in r
from the lowest to  the highest  cxx

-------
   '»1.  Emission Control Technologies Selected
                                                                                          Development Status
                                                  Species Controlled
                                               SO,             NO,
                                  Commercial
          Limited
        Commercial
        Experience
 Ongoing or
    Near
 Commercial
Demonstration
Lima/Limestone (L/LS) flue gas
 desulfurization (FGD)

Additive enhanced L/LS FGD

Lima spray drying (LSD) FGD •

Physical coal cleaning (PCC)

Coa! switching and blending (CS/B)

Low-No^ combustion (LNC)

Furnace sorbent injection (FSI) with
 humidification

Duct spray drying (DSD)

Natural gas rebuming (NGR)"

Selective catalytic reduction (SCR)

Fluktized bed combustion (FBC) or coal
 gasification (CG) retrofitc
      x

      x

      X
                       X


                       X
'Commercial on low-sulfur coals, demonstrated at pilot scale on high-sulfur coals.
Tnr wet bottom boilers and other boilers where LNC is not applicable.
    'uated qualitatively as combined life extension and SO2 / NOM control option. No costs were developed.
...- 25. 50, and 75 sum of megawatt per-
cent points for the boilers included in the
figure. Each point on the curve represents
a specific boiler cost result. The first point
represents  the boiler that had the lowest
capital cost and unit cost.  The last point
represents  the boiler that had the highest
cost. The curves turn up sharply because
each  curve was developed starting  with
the boiler having the lowest control  cost
and ending  with the  boiler having the
highest  control cost. The cost results do
not represent the average or cumulative
cost of control.
   Each utility section  in this  report  was
sent to  the appropriate utility for review
concerning plant information. Costs devel-
oped  in this report may not  represent a
particular  utility company's economic
guidelines. The cost results are static (not
dynamic) and represent a  single year in
the 1986-1989 period  with regard to ca-
pacity factor, coal sulfur,  and  pollution
control characteristics.

FGD Cost Estimates
    Figures  3 through 5 summarize the
cost estimates developed for wet lime/
limestone (L/LS) FGD with adipic acid ad-
      for 449 boilers. Two FGD configura-
     were evaluated: a conventional New
        Performance  Standard  (NSPS)
design having a single system for each
boiler, small absorber size, and one spare
absorber; and a low-cost design that has
combined boiler systems (when feasible),
but not a spare absorber. The target SO2
removal efficiency was 90%.
   Cost  estimates for FGD were  devel-
oped for only 449 of 631 boilers because
46 boilers were already equipped with FGD
systems,  130 boilers were burning low
sulfur coals (many are 1971 NSPS units),
and  6 boilers were too small or already
retired.  The  percent  increase  in capital
cost for retrofitting an FGD system over a
typical new plant installation ranged from
19 to over 100%, with the average being
45%. The levelized annual cost of control
(mills/kilowatt hour)  is also  strongly influ-
enced by system size and design  (e.g.,
percent  reduction required or conventional
versus low-cost configuration design), and
operation (capacity  factor  and  sorbent/
waste disposal costs).
  Figures 6 through 8 summarize the cost
estimates for lime spray drying  (LSD) for
all the boilers for which costs  were devel-
oped. Two control options were consid-
ered for the  retrofit of  this  technology:
reuse of the existing electrostatic precipi-
tator (ESP) or installation of a new fabric
filter (FF). Reuse of the existing ESP was
not considered:
• when the specific collection area (SCA)
  of the existing  ESP was  small <43.3
  m2/actual m3-sec or 220 ft!/1000 acfm,
  and
• when the addition  of  new  plate area
  was  impractical (e.g., roof-mounted
  ESPs).

In such cases, a  new FF was  used for
paniculate control with the  spray drying
system. However,  if a unit is burning  high
sulfur coal,  use of a new  FF  was  not
considered.  Based on the cited criteria,
168 boilers were considered with a  new
FF option, and 195 boilers were consid-
ered with reuse of the existing ESPs. The
cost of retrofitting new FFs results  in a
high retrofit difficulty  factor and a  high
cost of control.

Coal Switching and Cleaning
   For coal switching  (CS), two fuel price
differentials  (FPDs) were evaluated: $5
and $15Aon. The $5 to $15Aon FPD was
assumed to represent an estimated range
for switching to a low  sulfur coal.
  Figures 9 through  11   summarize  the
costs for 329 boilers in the 200 plants for
which costs were developed for CS. The
cost estimates for CS are based on $5
and $15/ton FPD. CS  was not considered

-------
                                                 Site Specific Information Sources
                  Aerial
               Photographs
               Retrofit Factors
             Access/Congestion
             Soil and Underground
             Flue Gas Ducting
             General Facilities
             Regional Cost Factors
Energy Information Administration Form 767
       Boiler/Coal Characteristics
            Scope Adder Costs
         Wet to Dry Ash System
         Chimney or Liner
         Paniculate  Manor Controls
                               NT
                                 Multiplier
        Utility Comments and
        Other Data Sources
         Boiler/Coal Parameters
         Boiler Characteristics
         Coal Characteristics
         Capacity Factor
         PM Control Type/Size
         Rue  Gas Temperature
                  Dollars
Direct Inputs
                                                         Cost Model Inputs
                                                Integrated Air Pollution Control System
                                                        Cost Model Outputs
                                  Capital Costs   O&M Costs     Annualized Costs    Emission Reduction
Figure 2.  Site-specific cost estimation methodology.
                        7»W« 2.  Economic Bases Used to Develop the Cost Estimates

                               Item                                          January 1985 Value
Operating labor
Water
Lime
Limestone
Land
Waste disposal
Electric power
Catalyst cost
19.7
0.60
65
15
6.500
9.25
0.05
20,290
$/person labor
$/1000gaJ.'
$/ton*
$/ton
$/acre •
$/ton
$/kWh
$/ton
                            Levelization factors

                             Operating and maintenance
                             Carrying charges
                          Current dollars"

                               1.75
                              17.5%
  Constant dollars'

        1.0
       10.5%
                        'For readers more familiar with metric units: 1 gal. = 3.8L, 1 ton = 907kg, and 1 acre = 4047m*
                        "Book life—30 years: tax life—20years; depreciation method—straight line; and discount rate—12.5%
                         based on a 6% escalation for inflation.

-------
                                                                              Figures.   Summary of capital cost results for
                                                                                        lime/limestone flue gas desulfurization.
                 20,000    40,000    60,000    80,000    700,000    »20,000
                                    Sum ofMW
                                                          100

                                                           90-

                                                           80-
 Figure 4.  Summary of annual cost results for
          lime/limestone flue gas desulfurization.
                                         I
                                         S
60



40

30
                                                    • WetFGD-NSPS
                                                    A low Cost FGD
                                                    (No spare absorbers, but
                                                     combined boilers.)
                                                     1988 Constant Dollars
                                                                                                75% of Total MW
                                                                                  50% of Total MW'
                                                                 25% of Total MW      yx
           20,000    40,000
                                                                                          £0,000    80,000
                                                                                          Sum ofMW
                                                                                                  100,000   120,000
    9,000
    8,000-
    7,000 -
o
2  5,000
o
|  4,000

|  3,000
• WetFGD-NSPS
A Low Cost FGD
(No spare absorbers, but
 combined boilers.)
1988 Constant Dollars
                                                                   Figure 5.  Summary of cost per ton ofSO2 removed
                                                                            results for lime/limestone flue gas desulfurization.
                  20,000    40,000    60,000    80,000     100,000    120,000
                                      Sum ofMW

-------
     400
     350
     300
     250
200
|
8
•5    '50
I
<3
     700
                                                                              Figure 6.  Summary of capital cost results for lime
                                                                                       spray dry ing.
              20.000
                               40,000      60.000
                                   Sum ofMW
                                                      80,000      700,000
   Figure 7.  Summary of annual cost results for lime
             spray drying.
                                                   1
                                              I
                                              3
                                                         35

                                                         30

                                                         25

                                                         20

                                                         15

                                                         10

                                                          5
                                                              1988 Constant Dollars
                                                                                               7596 of Total MW
                                                  I
                                                                                 50% of: Total MW
                                                               25% of Total MW        v
                                                                      20,000
                                                                             40,000      60,000
                                                                                  SumofMW
                                                                                                          80,000
                                                    100,000
   5,000
            25%ofTotalMW  50%ofTotalMW
                                                                                Figure 8.  Summary of cost per ton ofSO2 removed
                                                                                         results for lime spray drying.
                   20,000
                          40,000      60,000
                              Sum ofMW
                                                       80,000

-------
 8
70


60


50


40

30


20


10


 0
             •  $15 Fuel Price Differential
             A  $5 Fuel Price Differential
               1988 Constant Dollars
                                            75% of Total MW

             25% of Total MW - 50% of Total MW   \ \_
                         Figure 9.  Summary of capital cost results for coal
                                   switching and blending.
                     20,000       40,000        60,000

                                       Sum ofMW
                                                       80,000
                   100,000
                                                        17
Figure 10.  Summary of annual cost results for
           coal switching and blending.
                                                 s
                                          I
                                           re
                                           a
                                           c
15 -

13

11

 9

 7

 5

 3

 1
                                                                115 Fuel Price Differential
                                                               • $5 Fuel Price Differential
                                                               1988 Constant Dollars _|
                                                                                       75% of Total MW
                                                                        50% of Total MW
                                                       25% of Total MW     .   \
    9,000
              20,000       40,000        60,000
                               Sum of MW
                                                                                                               80,000
                                                                                                                     100,000
    8,000 -
      •  % 15 Fuel Price Differential
      ^  J5 Fuel Price Differential
       1988 Constant Dollars
                                                                                   Figure 11.  Summary of cost per ton ofSO2 removed
                                                                                              results for coal switching and blending.
                     20,000
                            40,000        60,000
                                Sum ofMW
      80,000

-------
already burn a low sulfur  coal or have
wet-bottom boilers that can burn only coals
with special ash  fusion  properties. The
CS cost estimates are highly dependent
upon the FPD. The impacts of particulate
control  upgrades  and coal handling  up-
grades  are generally  small  by  compari-
son.
  Figures 12 through  14 summarize the
plant cost of physical coal cleaning (PCC).
Of 631 boilers, only 32 were evaluated for
PCC because either the coal already is
extensively cleaned or  the  plant is  not
located at a mine  mouth.

Sorbent Injection Cost and
Performance Estimates
  Two  sorbent injection technologies in
active  research  and development were
evaluated in this study:  furnace sorbent
injection (FSI) with humidification and duct
spray drying  (DSD).  Figures 15 through
20  summarize the cost  estimates devel-
oped for these technologies. Some boil-
ers were not considered good candidates
for these technologies because:

•  FSI  and DSD  were  not  considered
  practical  for boilers having an   ESP
  SCA < 220 ft2/1000 acfm, and
•  DSD  was not  considered  if  the  duct
  residence time from the injection point
  after the air heater to the ESP inlet was
  less   than 2 sec (<100 ft—30.5 m—of
  duct length).

Only 321 boilers were considered appro-
priate for DSD, and 289 were considered
for  FSI applications. The costs presented
for  FSI assume 50 and  70% SO2 control
with humidification.

Low NOX Combustion
  Figures 21 through 23 summarize cost
estimates for application of low NOi burner
(LNB) on dry-bottom wall-fired boilers (20-
55% NOx reduction), overfire air (OFA) on
tangential-fired boilers (10-35% NOx re-
duction), and natural gas reburn (NGR)
on  cyclone boilers (60% NO reduction).
The unit costs of  LNB and OFA are low
(<$300Aon of NO  removed). However, for
boilers where  NGR is applied, the unit
costs are much higher ($400-$1100/ton of
NO, removed).  This  is  due to  the  high
cost of natural  gas relative  to coal (as-
sumed to be a $2 /10e Btu* fuel  price dif-
ferential in  1988 dollars). For this study,
228 boilers were candidates for LNB, 214
boilers for OFA, and 81  boilers for NGR.
Some of the boilers were not considered
Tor readers more familiar with metric units, 1  Btu ••
 1.054KJ.
for low  NOx  combustion  technologies
(LNC) because of the reservations of plant
personnel regarding applicability of these
technologies.

Selective Catalytic Reduction
(SCR) Cost Estimates
   Figures 24 through 26 summarize the
cost estimates for application of SCR. For
most of the units, cold-side, tail-end sys-
tems were assumed (the  reactor down-
stream of particulate control or scrubbers).
In some instances, due to space availabil-
ity limitations or the  unit's being equipped
with a hot-side ESP, a hot-side, high-dust
system configuration was used (the reac-
tor between the economizer and the air
heater). Use of the  tail-end system mini-
mizes unit downtime,  which reduces the
uncertainty of estimating the  cost of re-
placement power,  and maximizes  the
catalyst life. However, a significant energy
penalty is associated with flue gas reheat-
ing compared  to that for a high-dust sys-
tem  (equivalent to  a 120°F—49°C—re-
heat). This cost was not considered in this
study because the current version of the
IAPCS model is unable to estimate it.
However, the cold-side SCR requires 60%
of the hot-side catalyst volume. Based on
a 1 -year catalyst life, the reheat and extra
catalyst volume  costs offset each other.
For this study, 624 boilers were evaluated
for SCR retrofit.

Conclusion
   For each SO2 and NOx control tech-
nology evaluated in this study, different
factors affected  control  cost and perfor-
mance estimates for retrofit applications
at coal-fired boilers.  Table 3  identifies
factors found to have the most significant
effects.  For the  L/LS-FGD technologies,
site access/congestion and flue gas duct-
ing distances were major factors. For LSD-
FGD, the need  to  add new  particulate
control was also a major consideration.
  For CS and  PCC, the major retrofit fac-
tors, excluding FPD, were particulate con-
trol upgrade costs and boiler performance
impacts.  CS for wet-bottom boilers and
switching from a bituminous to a subbitu-
minous coal were not evaluated because
boiler performance  impacts are  likely to
be significant.
   For the sorbent injection technologies,
FSI and DSD,  paniculate control upgrade
costs would have the greatest impact. Ad-
ditionally,  sufficient  duct residence  time
must be  available for  DSD to  guarantee
good droplet drying.
  For the  LNC  and NGR  technologies,
boiler type and  configuration  are impor-
tant. LNB was applied  only to dry-bottom,
wall-fired boilers. OFA was  applied only to

                   8
tangential-fired units. NGR was applied '
wet-bottom  boilers and  other  misc
neous boiler types.  Boiler heat relt
rates and residence times in different fur-
nace zones would have significant effects
on  NOK removal  efficiency for  LNC and
NGR technologies.
    SCR costs would  be  greatly affected
by  access  and  congestion near the
economizer area for hot-side applications.
For cold-side applications,  access and
congestion near  the  chimney area and
flue gas  ducting  distances greatly affect
costs. For cold-side systems, the energy
penalty for flue gas reheat is balanced by
increased catalyst life and reduced  cata-
lyst costs. For hot-side  systems, boiler
downtime costs and catalyst life would be
significant cost and performance factors.
  The cost and performance information
presented is a realistic guide  regarding
the degree  of retrofit  difficulty  for  each
control option evaluated.  However,  as
noted in Table 1,  the technologies evalu-
ated in this study  are at various  stages of
commercial development. There is a higher
degree of uncertainty  regarding the  cost/
performance  for those technologies that
do  not have extensive commercial appli-
cation in  the U.S. Therefore, no attempt
has been  made in this study to  identify a
best option for each plant/boiler.
  Additionally, a utility company's dec
concerning which retrofit control to app,
to a given boiler is very complex. Consid-
erations used in making such a decision
include:
• system  reduction target and degree of
  flexibility regarding means  to achieve
  the target,
• current and future toad pattern for each
  boiler with or without controls,
• cost of  purchased power and planned
  new capacity,
• cost of capital and current/future finan-
  cial strength, and
• public utility  commission and state/re-
  gional regulatory agency attitudes.

The  data contained in this report can be
used to facilitate selection of least-cost
control  options for specific plants/boilers
for planning scenarios that address the
above decision criteria.
  The cost results for all the technologies
presented in  this report  are available in
three DBase III+ files and can be obtained
through the National Technical Informa-
tion  Service (NTIS). Disks 1  and  2 *">
high  density diskettes which contain:  '
name, technology, boiler number,  ca,

-------
       90

       80

       70

       60

       50

       40

       30

       20

       10

         0
       1988 Constant Dollars
                                                                           Figure 12.  Summary of capital cost results for
                                                                                     physical coal cleaning.
                          50% of Total MW
                                             75% of Total MW
         .25% of Total MW
                 2,000     4.000    6,000    8,000
                                       Sum ofMW
                                               10,000   12,000   14,000


                                                       5
       Figure 13.  Summary of annual cost results for
                 physical coal cleaning.
                                                      I
                                                      3
                                                                             50% of Total MW
                                                               25% of Total MW
     1,200
9  1,000
                                                               0      2.000    4.000    6.000    8,000    10,000   12,000   14,000
                                                                                           Sum ofMW

o
c
u
,^
      800
600
      400
      200
            1988 Constant Dollars
                                               75% of Total MW
                        50% of Total MW
              25% of Total MW
Figure 14.  Summary of cost per ton ofSO2 removed
           results for physical coal cleaning.
                 2,000    4,000    6,000     8,000    10.000   12,000   14,000


-------
!
o
I
a:
6"
I
1
                                                                                Figure 15.  Summary of capital cost results for
                                                                                          duct spray drying.
                     20,000
                                  40,000        60,000
                                     SumofMW
                                                        80,000
100,000
     Figure 16.  Summary of annual cost results for    3
                duct spray drying.                   ^—
                                                 s

                                                        20


                                                        76


                                                        72
                                                             1988 Constant Dollars
                                                                           50% of Total MW
                                                                                              75% oi Total MW
                                                                                                     \
                                                              25% of Total MW
                                                                      20.000
    3,800


    3,400


    3,000


    2,600
7,800


7,400


7,000


 600
            1988 Constant Dollars
                                            75% Of Total MW
                             50%ofTotalMW
             25% offofa/MtV
                                       >y
                                                                                   40,000       60,000
                                                                                     Sum ofMW
                                                                                                         80,000
                                                 100,000
                                                                                 Figure 17.  Summary ofcostperton of SO? removed
                                                                                           results for duct spray drying.
                     20,000       40,000        60,000
                                    Sum ofMW
                                                             80,000
                                                                     100,000

-------
1 IV -
700-
o/i -
Hn -
5
^J 70-
I 60-
3 6a-
2 so -
O 40 —
30-
?fl-
70-
7988 Constant Dollars

i
75% of Total MW v-*

5096 of Total MW ^^^
2596 of Total MW *^ 	 >~^
^_^^
^
I
Figure 18. Summary of capital cost results for
furnace sorbent injection.
0 20,000 40,000 £0,000 80,000 700,000
Sum ofMW
•M -.--


17 -

^ is -
Figure 19. Summary of annual cost results for ^

2.400 -
2.200 -
2,000 -

* 7,600
o
I '

3 ovu
O
3 400-
n -
luriidie juruem injection. EI • •
— O -

^
S -
3 .
; .
1988 Constant Dollars





7596 of Total MW f

25% of Total MW \. ^^ , -~~^
^ _^— --^^"
^-^ 	 ^*
0 20,000
• 5096 Removal
19SS Constant Dollars 1


I
I
I
\
//
7596 of Total MW f* 1
!>096oflotalMW ^\ J* \
2S96 of Total MW v\ \X -^ -/

_^— N>— 	 ^J^A 	 — *
^— 	 * 	

40.000 60,000 80,000 100.000
Sum ofMW
Figure 20. Summary of cost per ton ofSO2 removed
results for furnace sorbent injection.
20,000       40,000       60,000
               Sum of AM
00,000
700,000

-------
§
       45

       40 -

       35-

       30

       25

       20

       15

       10

        5

        0
            A  LNB
            X  OFA
            m  NGR
            1988 Constant Dollars
                                  75% of Total MW
           50% of Total MW
25% of Total MW
                         20,000
                                            40,000
                                    Sum ofMW
     Figure 22.  Summary of annual cost results for
               low NO, combustion.
!
I
|
'£
                         20,000            40,000

                                   Sum ofMW
                                                              Figure 21.  Summary of capital cost results for
                                                                        low NO, combustion.
                                                60,000
                                                             A  LNB
                                                             X  OFA
                                                             •  NGR
                                                             1988 Constant Dollars \
                                                                                    75% of Total MW
                                                                                          \	
                                                                        50% of Total MW
                                                                           20,000
                                                                                             40,000
                                                                                      Sum ofMW
                                                                                                 60,000
           A  LNB
           XOFA
           m  NGR
           1988 Constant Dollars
                                 75% of Total MW
                        50% of Total MW
         ' ~25% of Total MW
                                                                             Figure 23.  Summary of cost per ton of NO, removed
                                                                                       results for low NO, combustion.
                                                             60,000



-------
8
1
280

240

200

160


120

 80


 40-

  0
            1988 Constant Dollars
             ' 25% of Total MW
                                                75% of Total MW
                              50% of Total MW         \.
                                                           3 Year Catalyst Life
               Figure 24.  Summary of capital cost results for
                          selective catalytic reduction.
                20,000      60,000       100,000
                                      Sum ofMW
                                                 140,000
180.000
     Figure 25.  Summary of annual cost results for
               selective catalytic reduction.
                                                                                    50% of Total MW
                                                                  25% of Total MW         \
                                                               0   20,000
             60,000
                                                                                       /00,000
140,000
180.000
I
5*
;
                                                                                  Figure 26.  Summary of cost per ton of NO, removed
                                                                                            results for selective catalytic reduction.
    2,000 •
     J,000
                      40,000       80,000        120,000

                                       Sum ofMW
                                                        160,000
       200,000

-------
Table 3.  Retrofit Factors Affecting Cost/Performance
     Control
    Technology
  Access and
  Congestion
Ducting
Distance
Additional
Partticulate
  Control
Boiler
Type
   Boiler
Configuration
   Lime/Limestone Flue Gas Desulfurization

   Lime Spray Drying

   Coal Switching/Blending

   Physical Coal Cleaning

   Furnace Sorbent Injection

   Duct Spray Drying

   Low NO, Combustion

   Natural Gas Rebuming

   Selective Catalytic Reduction
                                                        x

                                                        x
                                                         x

                                                         x

                                                         x
                                                     x

                                                     x
SO2 and NO removed per year, SO2 and
NO  removal efficiencies, capital cost in
dollars,  annual cost in dollars, dollars per
kilowatt,   mills  per kilowatt hour,  dollars
per ton  of SO2 removed,  and dollars per
ton of NO. removed.  Disk 1  is in current
1988 dollars,  disk 2 is in constant 1988
dollars, and disk 3 contains a third DBase
file (200.DBF) with general plant, boiler,
and  company information based on  De-
partment of Energy Form 767 data. Disk 3
also contains an ASCII file  (README.
                       ASC) listing abbreviations used in all three
                       database files. The  cost  result database
                       can be used to estimate total costs  and
                       emissions for individual or combined con-
                       trol technologies for the 200 plants pre-
                       sented in this report.

-------
T. Emmel and M. Maibodi are with Radian Corporation, Research Triangle Park, NC
   27709.
Norman Kaplan is the EPA Project Officer (see below).
Tha complete report, consists of five volumes and diskettes entitled "Retrofit Costs for
   SO and NOt Control Options at 200 Coal-Fired Plants,"  (Set Order No. PB 91-133
   314/AS; Cost $181.50, subject to change).
         "Volume I. Introduction and Methodology" (Order No. PB 91-133 322/AS;
         Cost: $17.00, subject to change).
         "Volume II. Site-Specific Studies forAL, DE, FL, GA, IL" (Order No. PB 91-
         133 330/AS; Cost: $45.00, subject to change).
         "Volume III. Site Specific Studies for IN, KY, MA. MD, Ml, MN" (Order No.
         PB 91-133 348/AS; Cost: $45.00, subject to change).
         "Volume IV. Site Specific Studies for MO. MS, NC, NH, NJ, NY, OH" (Order
         No. PB 91-133 355/AS;  Cost: $53.00, subject to change).
         "Volume V. Site Specific Studies for PA, SC, TN, VA, Wl, WV (Order No. PB
         91-133 363/AS; Cost: $53.00, subject to change).
         Related set of three diskettes (Order No. PB 91-506 295/AS; Cost $80.00
         subject to change).
The above items will be available only from:
        National Technical Information Service
        5285 Port Royal Road
        Springfield, VA 22161
        Telephone: 703-487-4650
The EPA Project Officer can be contacted at:
        Air and Energy Engineering Research Laboratory
        U.S. Environmental Protection Agency
        Research Triangle Park, NC 27711
United States
Environmental Protection
Agency
                                   Center for Environmental Resea:
                                   Information
                                   Cincinnati, OH 45268         ;
Official Business
Penalty for Private Use $300

EPA/600/S7-90/021
000047147    PS
US  j£P A
LIBRARY  SERVICES
RES  TRI  PARK

-------