-------
Although a broad list of compounds were found in soils the areas investigated in OUA. a subset of
these compounds were identified as .compounds of concern. based on their frequency of detection.
concentrations relative to background levels, and concentrations relative to risk-based and regulatory criteria.
The compounds of concern evaluated in the risk assessment include:
. .
. metals:
antimony, arsenic, chromium, copper, lead, and zinc;
. HPAHs:
total HPAHs and individual HPAHs including benzo{a)anthracene, chrysene,
benzo(b)f1uoroanthene, benzo(k)f1uoranthene, benzo (g ,h ,i)perylene,
dibenzo(a,h)antbracene, indeno(1,2,3-cd)pyrene; (benzo(a)pyrene was individually
evaluated;
. pentachlorophenol;
. bis(2-etbylhexyl)phtba1ate;
. PCBs, and;
. dioxins (2,3,7,8-TCDD; only for the Capacitor Testing Lab).
Compounds of concern were not found or found in low concentrations in ten of the waste units. In
these areas, nO action was required by the State or EPA. Compounds of concern that exceeded MTCA
cleanup standards were found in seven waste units. These were addressed by removal actions.
Various compounds of concern were found in laterally extensive areas in the three actionable waste
units: Wood Pole Storage Area East, Ross Substation and Capacitor Yard, aDd Capacitor Testing Lab. The
contaminants of concern identified in the Wood Pole Storage Area East are HPAHs and pentachlorophenol.
HPAHs and pentachlorophenol are considered to be carcinogenic. HPAHs are relatively insoluble in wa~,
have a high affinity for soils and therefore, are relatively immobile. Pentachlorophenol is relatively soluble
in water, tends to sorb to particulate matter and is readily biodegradable. Mobility of pentachlorophenol is
expected to be limited due to the presence of compacted soils containing low permeability rates in this area.
Contaminated soil in the OUA are not RCRA wastes since the material would not designate as a dangerous
waste based on WAC-173-303-070(3). It is also not a federal hazardous waste as defined in 40 CFR Part 261
because it is neither a listed waste nor is it characteristic. HPAHs were detected in soils throughout this waste
uait from 0 to 3 feet bgs, and pentachlorophenol was dete<:tM only in surface soils throughout the area. Trace
levels of HPAH «0.003 mgllcg) were detected at 7.5 feet bgs at select locations. Figures 3 and 4 show the
conccotration and distribution ofpentacb1oropbenol and HPAH in this area, respectively. Figure S shows the
estimated area of conmmiluatM soil and the estimated volume of CODmminlltM material is 3,6SS yd3. HP AHs
and pentachlorophenol fOUDd in soils in this area were from chemicals that dripped from the treated
transmission poles stored in this area.
_1,..-1"'"
2S
-------
o WPE-SB11A
o WPE - SB03A
o WPE - SB09A
<:> WPE - SB08A
"
o WPE-SB01A
~ WPE-SB02A
o WPE-SB04A
. WPE - SB06A
-$-WPE-SB07A
-$-WPE-SB10A
.............
-.....
"
Wood Pole Storage Area, East
.
L£C£NO
----
SPA ROil Co"'pl.. Boyndru y
fenCl
~.a ~..d
9uildin9
$ lOCOI;on 01 lomplc(.) hovin9 a dtl,ct,d onOlr" obove AAO. .
-$- lOCOliOn 01 ,o,"ple(.) f\o..;n, 0 d",eatd O"Olyl. b.lo- AAO
o locotiO" 01 lO""'Dlf(.) "OW;"9 "0 detected O"OI,lf
e::z:::ZJ
Job No. 06737-012-005
1
e,,,,,,,,,,'I,,,, " '."IIC"",..1\1"81 ."
'"8.''' 't-, I.,,,,. A,.. r..,
SI"'.Of D£'I" CONe. OJAl
---
1IPC-180'0 0 II
""[ -18010 0 ,. J
.-r "SIOIA 0 " J
.(-11074 0 " J
_(-SlIOA 0 '.8 "
Voh,.. "'" It. 1110 "IM
J .. Ihl ...8111'" ."'" " 'ft '''.'''01''
."."111,.
N
A
0 60 120
SCALE IN rEEf
o WPE-SBI2A
Figure 3
Distribution of Pentachlorophenol (PCP)
Wood Pole Storage Area, East
BPA Ross Complex
-------
-$- WPE-S811 A
-$- WPE - S803A
eWPE-S809A
o WPE - S80BA
-$-WPE-SBI2A
"
-$- WPE-SB01A
+WPE-SB02A
-$- WPE-SB04A
+ WPE - SBOSA
-$-WPE-SB07A
-$-WPE-SB10A
'"
---
........
-$- WPE - SB05A
Wood Pole Storage Area, Eest
.
.
e'''llAh,li.". .t ht,. t"C'''''''''''8 ""AM
'" '''' -... "," s.o,... A'.. hll
".., lOtI 0['1" co.c: av.,
- --
WP(-SIOIA 0 a -a.
...r -S80IA 0 "1 .
,~ 000'
"[-S80)' ) 0 001
,~ 000'
~[-seo"" ,. a 0.1
tlPr -SIOU. 0 )0 "
-r ...'.01& 0 II"
,. 0001
..( -no" 0 ...
""(-SlIOA 0 . .
,~ 0 00'
_[-111'4 ) .,
IIII'(-Slt,a ) 0 001)
YOlu.. "'0' I.' '" ,,....
J .. 1Ji1t "'lei,l,d .01"" 01 ."" ....-...
'1"...1,',
N
fA.
o
60
120
SCALE IN rEET
~
SPA Ron Comp'u 801.11""0"
,."co
Aoa Rood
e,,3~:t\9
.. LOCOlion of lampl'(') ho.nnQ 0 "e'C(18d 01\01)'1. otlO~ AAO.
~ Locotion 01 lampl.h) hOvinV 0 dltecled O"Olr" b.la- AAO.
G> local:O"l 01 .~""If(') hOvinO no CSllfcted anat)'lc.
Figure 4
Distribution of Total HPAH
Wood Pole storage Area, East
BPA R088 Complex
DAMES & MOORE
,
~
I
J
.
l!C!NO
-------
CJ
...) "'" ~ ~ ~
.............. -....---- '--- ~ -~
.' ..- ,,' ,~
----.............. -'. .
~~~ ~
~~ ~$ ~~ ~ ~
Total Cubic Y
ords = 3,655
Wood Pole St
. orage Area, East
~ W#ff#hI
J---- .
----
----
----
- -
, ---
, --
------
---------
---
----
------
------
--------
BPA ROil C
- f.nc. ompl,. Boundory
~ Rail Road
c::::::J e~ildin9
V////////A
Elt. C::ontomin
otcct AreOI
N
. fA.
o
.
160
.
SCALE IN rEET
80
Estlmat d
a Araas of C Figure 5
Wood Pole StOntamlnatad Solis
orage A
BPA rea, East'
Ross Complex
DAMES & MOORE
LEG£ND
Job No
. 06737-012-005
-------
..
PCBs were the compound of concern identified in soils in the Ross Substation and Capacitor Yard.
The Ross Substation and Capacitor Yard is a IO-acre fenced area that contains numerous capacitors and
transformers. Spills of PCB oils from faulty capacitors and leaking equipment have occasionally occurred
within the substation. Figure 6 shows the distribution of PCB contamination and Figure 7 shows estimated
area of contaminated soil,' a volume estimate of approximately (1,196 yd3), in the Ross Substation and
Capacitor Yard.
PCBs are the compounds of concern identified in the Capacitor Testing Lab area. PCBs were detected
in surface soils around the outside of the Capacitor Testing Lab. Figures 8 and 9 show the distribution of
PCB contamination and the estimated area of contaminated soil (volume estimate of approximately 68 yd3) in .
the Capacitor Testing Lab Area. PCB-containing oils were reportedly spiUed onto the concrete floor during
storage of the failed capacitors, as well as onto the soil and gravel beyond the garage door. Potential heating
of the PCB-containing oils with the capacitors may have produced dio~.
PCBs are considered to be carcinogenic, are relatively insoluble in watec and have a high affinity to
sorb to soils. It is unlikeJy that PCBs will be mobile in soils in either the Ross Substation and Capacitor Yard
or the Capacitor Testing Lab based on the physical conblminant cbaracteristics and because soils in these areas
are compacted and have low permeability characteristics. PCBs are regulated as a dangerous waste in
accordance with WAC-I73-303 and are also regulated under TSCA, 40 CFR Part 761.
7.0 SUMMARy OF SITE RISKS
CERCLA response actions for QUA at the BPA Ross Complex site as described in this Record of
Decision are intended to protect human health and the environment from curient and potential future exposure
to hazardous substances in soil at the site. To assess these risks at the site, human health and ecological risk
assessments were conducted as part of the remedial investigation to characterize the magnitude of rislcs
associated with exposure to conmmin~tM surface soils and to prioritize areas within QUA for remedial action.
Human receptors included a hypothetical on-site residential child and adult (potential future sceuario); on-site
worker (current iDdustrial scenario); and off-site residential (recreational) child and adult. Ecological indicator
species selected for this site included the American robin (T. migratorius), raccoon (P. lotor), and black-tailed
deer (0. hemionus columbianus). The results of the risk assessments were used to decide whether remedial
. action is necessary and then used in the feasibility study for selection of cleanup guidelines to protect human
health and the environment.
The approach followed for both the human health and ecological Baseline Risk Assessment consisted
of the following general steps: (I) identification of chemicals of potential concern, (2) exposure assessment,
(3) toxicity assessment, and (4) risk characterization.
_I/~I'"
-------
RSCY-SB05A
<:>
<:>
RSCY-Se04A
<:>
RSCY-SS28
l£C[HD
RSCY-SSJJ<:>
RSCY-SSJ5
<:>
. RSCY - SSeJ
~RSCY-SS62
RSCY-SS59+
<:>RSCY-SS45
~CY-SS55
RSCY-SeOBA
<:> RSCY-SS65
R088 Sub.I.llon .nd C.p.cllor V.,d
lRSCY-SS25
o
RSCY-SS2J
~ RSCY-SeOJA
. RSCY-SS70
<:> RSCY-SSI0
RSCY-SSOI <:>
<:> RSCY-SS08
RSCY-SS02<:>
RSCV-SS20<:> ---
~RSCY-SB02A
--
8PA ROil CO"'P11U Boundof'
FtF\CI
R.a R...
BuilClinQ
.. lOCO';O" 01 tomple(.) hovin9 0 detected onol)'ll obo"'l AAO.
... lOCCIlion 01 tamDI.(t) hO..lftiQ a det,cl'd onolyt. belo. RAO.
G) location 01 somallh) hovinC) no deluted onal,ll.
---
e:::z:zJ
Job No. 06737-012-005
~'
'I
C,,,,,,.,,,,,,,,, .1 h'" PCI. 11'1 I",
-u. 1",'.11111" 'fI' C.,nll" '1"''11
RSCY-SSI6
RSCY-SBOIA
II
ij
ij
S1AtiON
-sa--IUt
'$tV-UI'
-seT-Sse'
ISCT-llro
IK'f-lsrr
.scy-ssr)
.lcY-SlII
lseY-Sln
llsa-U8D
.ICY-Slor
IScY-SlU
aSCT-SSIS
D[Pf"
COC. OUAl
---
.
.
o
o
o
.
o
o
o
o
o
o
II J
on J
, SF I
0.'1 J
130 J
r I J
... J
112 J
d." .J
0.1t ,J
0.31 .I
0.1) J
VII".. U,1t 18d ." ,,....
J ... ,". ...oel"'d ....". I, ." .,11...,...
,,,'''111,.
o
N
A
60
120
'----' .
SCALE IN rEEf
Figure 6
Distribution of Total PCBs
Ross Substation, and Capacitor Yard
BPA ROBS Complex
DAMES & MOORE
-------
. .
Ross Substation and Capacitor Yard
o
o
.19 Cubic Yards
1196 Total Cubic Yards
598 Cubic Yards
N
fA.
50
.
o
100
.
SCALE .. F£ET
LEGEND
- - - - SPA Ross Complex Boundary
1\" Fence
Roil Road
I Building
. WZbJ
Est. Con lamina led Areas
FIGURE 7
ESTIMATED AREAS OF CONTAMINATED SOilS
ROSS SUBSTATION AND CAPACITOR YARD
BPA ROSS COMPLEX
DAMES & MOORE
-------
l£GtNO
-
B~A !!to.. eo ""pl.. Bo",u!lct.,
r."u
Ro~ Rood
8uildin9
e:z:zJ
Job No. 06737-012-005
~
CTL-SS13
CTL - S803
CTL-SS12
ELl
-$- local:on csl lomDlt(t) tlDVinO a delec1cCJ 01"101)'" oboyc RAO.
.. locotion 01 sOl"l'lple(.) 1\0"""9 a detecled onol,I. b,IO.. A'AO
<:> lacat;on 01 somD1e(,) hovin9 no tlelec'ed O"Olyt~
Capacitor Testing
Laboratory
o 0 CTL-SB01
~CTL-SS07
G>. ~CTL-SS19
-$- 9CTL-SS06
-rCTL-SS18
-$- LCTl-SS04
CTL-SS01 III
GI
..
<
o-
r 1
D
I
....
I/)
III
:a
"0
c
III
CI)
I
I
)
rZJ
Q
l'
---
---
-,
(."eel'll',,,,,,, .1 '.,.1 faCl. 'ft 'h'
C.,nlll' rut ..., h....)
StAflON
0(""
COoC. WAl
---
elL-ISOt
CIL-Stot
en-Ilo,
en-liD'
Cfl....SSO'
ell-Sill
D.n "
0." J
-------
. .
- -"..-'"
,------------- ------:..=----- - --
-~_. -"'"
-- - --
;:-:::.;:.;:-=-- - --- --------
...
'"
/
/
I
I
\
N
fA
Capacitor Testing
Laboratory
[J8 Cubic
Yards
---------------
r.------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
l} ) -~~~~
------------"" <.
"
---------------, "
\ \
FIGURE 9
ESTIMATED AREAS OF CONTAMINATED SOILS
CAPACITOR TEST LABORATORY
BPA ROSS COMPLEX
DAMES & MOORE
o ----/-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
CD
GJ
~
<
I
D
I
-
CD
CD
:c
~
c:
CD
(I)
so
,
o
100
,
[]
SCALE IN FEET
D
LEGEND
- - - - BPA Ross Complex Boundary
Fence
Roil Rood
I Building
II
II
Wt0J
Est. Contaminated Areas
-------
7.1 COMPOUNDS OF CONCERN AND USE OF DATA
Twelve compounds of concern were selected from a broader list of chemicals of potential concern
identified by the Washington Model Toxies Control Act (MTCA), and EPA regional and national guidance
(EPA 1988, EPA 1991) based on comparison with natural and area background soil concentrations,
prevalence, and toxicity. The compounds of concern selected for inclusion in the risk assessment are as
follows:
. .
.
Metals: antimony, arsenic, chromium, copper, lead, zinc.
Suspected carcinogenic high molecular weight polynuclear aromatic hydrocarbons (HPAH)
were evaluated as total HPAHs. The carcinogenic HPAHs considered in the total HPAH are
benzo(a)anthracene, chrysene, benzo(b)fluoranthene, . benzo(k)fluoranthene,
benzo(g,h,i)perylene, dibenzo(a,h)anthraceDe, fluoranthene, indeno( 1,2,3 )pyrene,and pyrene.
- (Benzo(a)pyrene, a carcinogenic HPAH, was considered separately);
Pentachlorophenol;
Bis(2-ethylbexyl)phthalate;
Total polychlorinated biphenyl compounds (PCBs); and
Dioxin (2,3,7,8-TCDD).
.
.
.
.
.
These compounds of concern were carried throughout the baseline risk assessment and wer'C
considered in the Feasibility Study. The metals evaluated in the risk assessment were elevated above
background levels. Metals including antimony, chromium, copper, lead, and zinc wer'C evaluated as non-
carcinogenic compounds. Arsenic, HPAHs, pentachlorophenol, bis(2-ethylbexylphthalate, PCBs, and dioxin
are evaluated as carcinogenic compounds.
In the risk assessment, the individual waste units iddressed in Operable Unit A were grouped into
seven larger categories or waste unit groups to evaluate conf1lminant exposure potential within relatively
homogeneous exposure areas. The waste units were organized into Waste Unit Groups (WUG) based on
location within the Site, predominant contaminants present, surface water drainage and topography, proximity
to biological habitat, and other exposure considerations. No surface soil samples wer'C collected in association
with the oil water separators, therefore, this unit was not included in a waste unit group. The waste units
within each group are listed as follows:
Waste Unit Group
Waste Unit
1
Van's Way Oils Storage
Wood Pole Storage Area East
2
UtilizatioD and Disposal Yard
Hazardous Waste Storage Building
Herbicide Storage Area
3
Capacitor Testing Lab
Paint Storage Facility
Plumbing Shop (8Paint Shop.)
PCB Storage Building
4
Sand Blast Area
_"-""1'-
-------
5
Laboratory Waste Storage Area
Untaoking Tower
6
Ross Substation and Capacitor Yard
.
7
008-1 and 008-2 Drainfields
Top Coat Test Area
DOB-l Drainline
Wood Pole Storage Area South
Ellen Davis Trail
Samples with chemicals reported as undetected were assumed to contain these constituents at 1/2 the
sample quantitation limit for the purpose of calculating averages, as recommended by EPA guidance (EPA.
1989a). The Baseline RA was conducted for all chemical data sets based on the 9S perceo.t upper confidence
limit (UCL) ot the avenge concentrations in soil. The 95t1i UCL is utilized at the reasonable maximum
exposure (RME) value used in the risk assessment. The RME is defined as the highest potential exposure
expected to occur at a site (EPA, 1989a).
7.2 HUMAN HEALm RISK ASSESSMENT
This section summarizes the exposure assessment, toxicity assessment and the risk characterization
~sociared with the indicator chemicals evaluated in the human health risk assessment.
7.2.1 Exoosure Assessment
The exposure assessment characterizes the general setting in which potential exposures could occur,
including the physical setting and accessibility to CODtaminSltecJ areas; defines potentially exposed
populations;identities exposure pathways; defines the approach for quantifying exposures. including selection
of numerical exposure factors; and estimation of chemical intake.
7.2.1.1 Site Setting
The exposure assessment emphasizes potential exposures associl,l~ with current land use activities,
comprising the baseline sceuario, both on and around the site. In addition, in compliance with EPA Region
10 guicleliDes (BPA, Region la, 1991), a hypothetical on-site residential sceuario, addressing potential
exposures of poteDtia1 future residents is included in the quantitative risk issessment. This sceuario is included
to consider all poteatia1 exposures but is not regarded as likc1y given the presumed continued land usc
designation of the BPA Ross Complex as a power distribution facility. .
The area sunounding the Site exhibits a variety of land uses. These include residential (south,
southwest, and southeast), light commercialfmdustrial (east and northeast), major highways and thoroughfares
(west (primarily), north, east (secondarily», and open space (north, southeast, west). Exposure scenarios are
consistent with this diversity of land usc.
The Complex is generally fenced. Open (i.e., accessible) areas exist primarily in the southern section
of the Complex. Site access by adjacent residents could occur near the southern (19th Avenue) entrance to
the Site, where no steep slopes, bushy vegetation, fences or other controls restrict access. These areas include
the EUen Davis Trail, and Wood Pole Storage-South, which are in W~ Unit Group ff1.
4iIc."--..-
-------
Workers are assumed to have unlimited access to the Site through work-related duties. Hypothetical
oD-site residents are also assumed to have unlimited access to the site. Off-site residents are presumed
exposed in areas where unrestricted access exists, which is primarily on the southern perimeter of the Site.
There is DO known human habitation OD the Complex except for transients which reportedly occupy the
northern portion of the Complex near the Cold Creek landfill. Potential exposures will be addressed as part
of the Operable Unit B Baseline risk assessment.
. .
7.2.1.2 Potentially Exposed Populations
The human receptor groups that were evaluated in the baseline risk assessment included on-site
workers, hypothetical on-site residents, and off-site residents using portions of the site recreationally. Table
3 provides a descriptioo and summary of the various human receptor groups (both o~- and off-site) considered
for the Baseline RA. Hypothetical on-sitc residential exposures to site-related contaminants could also occur
in several ~ on the Site from several different waste units. This hypothetical scenario assumes that at some
point in the future the Ross Complex would no longer be used as a power distribution facility, but that OD-site
contaminant levels would remain the same. Several potential pathways could be involved, based on surface
soils, surface Water, and air.
Two residential receptor -age-classcs- were evaluated. These included children aged 0 to 6 and
-adults- aged 6 to 75. This distinction is believed to most effectively address the different types ofpoteDtiai
exposures occurring within human receptor groups.
Exposures to on-site workers could oc:cur at several areas of the Site based 00 direct contact with Soils
(including dermal contact, incideota1 ingestion, and inha1ation). On-site workers were oot assumed to ingest
produce grown oo-site or fisblshe1lfish taIceu from adjoining creeks. Because oumerous activities occur 00
the Site near contaminated areas, exposure durations and other factors were evaluated based 00 conservative
RME exposure factors.
Off-site residential exposures to site-related contaminants evaluated in this risk assessment were
limited to recreational use of WUG 17. Some direct contact with Operable Unit A Soils is also possible at
the southern portion of the Site where site access is not restricted.
A 1arge portion of the southeastcm area is bordered by a greenbelt through which the eastern portion
of the Ellen Davis trail passes. Consideration of residents around the Site was limited becau~ of Interstate
1-5 and other major thorougbfaRs ~ed to compound and obscure potential impacts from the Ross
Complex. . In addition. the uea to the west (near the Ellen Davis trail) is generally open space with woodland,
vacant lots. and riparian areas. Potential exposures of residents living near the Site are quantitatively
addressed through evaluation of the hypothetical assumption that coDt"ming~ fish aDd shellfish me consumed
and incidental contact with creek waters represented by Cold Creek and Burnt Bridge Creek occurs.
Ucl/..-lUoc
-------
- .
Table 3
DescrIption and Selection of Complete PotentIal Human Exposure Pathways by Receptor
Operable Un" A
BPA Ross Complex RI
Poh~~~t,.~~.~~.~tor
Off~te Residents
. "':..~... ,..,"... ... ',..
Hypothetical On-Site Residents
Route, Medium, and
Point of Exposure
"'" ','.....:' ',t-.... .~ .. ~..._:.'" ..... " ".. "",'111',"""". ,..... .~,. "'" I 01 I: .
. 1.,'"',,,,,.,.,,,,,,",".,
Ba.l. 'or Selection
. . """'1....,',
. ,.... ~......'. ....", ,-,.......,:...,,;,....,. -~, . .,.....,.... ,. t.,- "~, ",I' ..". ,",', .".' , .
Incidental Ingestion of soIls
Dermal contact with soils
Ingestion of homegrown fruits and
vegetables '
Incidental Ingestion of surface water or
sediment from Burnt Bridge or Cold Creek
Dermal contact with surface wafer or
sediment from Burnt BrIdge or Cold Creek.
Ingestion of IIJh/shellfish
Inhalation of wnd-borne particulates from
exposed surface soils
Inhatatlon of vapor-phase chemicals
transported off.slte
. . '-I"",.!
Incldentallngesllon of soils
Dermal contact with soils
Ingestion of homegrown fruit. and
vegetables
Assumes that solis could be contamInated via oerlal deposition or surface
water runoff.
Assumes that soils could be contaminated via aerial deposlllon or surface
water runoff.
Assumes that plants moy be Irrigated with contaminated water. planted in
contaminated soli. or that wlndborne contaminants would be deposited on
plant surfaces.
Assumes that contaminants could be taken up by human receptors during
swimming activities.
Assumes that contaminants could be taken up by human receptors during
swimming activities.
Assumes that Ross'Complex contaminants could be taken up by aquatic
organisms and Ingested by human consumers.
Assumes that solJ.borne contamInants could be transported to off-site soils.
Considered highly unDkely .In pori because most of the site Is paved. but was
addressed as BaseDne RA pothway.
.." ,,- '. .1. ',', ~'11",. ~:i!'~I~~J.r' "'~;',.ntil.'?t~A~.:,~;t.",,,,,:t.-'I-;': '; '''',' ,:,,.q ".., .
Assumes Ingestion of on-site soils.
. !.' I :i,.,f.. . '~' .' ,"
Assumes dermal contact with on-slte soils.
Assumes that plant. may be IrrIgated with contaminated water. planted In
contaminated soli. or that wndborne contamInants would be deposited on
plant surfaces.
...". ... .,,,,-...__.,", - ......... ..'~" .~. ,~",,,,,,,,,,---'-"-"""'~" ",,,,,,,,''''''''''''''''''_4.....,.~......_.....,---.....................-.._........''H'''''''''''''''_~-,..,..,., ~,",.'",,,,,,~,,,,,,,,,,,,,,~,,,,-,,,,,,,,,,,,,,,,,,-,,,,,,,,,,,,,_'___U""-'---"'-""-"",-";:,,",,................-_..-r'--"".'~"'~"""""
Job No. 0673HI12-006
"nllA DOnI XlWlTB1.3 14/22/93 I eO
-------
Table 3
Description and Selection of Complete Potential Human Exposure Palhways by Receptor
Operable Un" A
BPA Ross Complex RI
P~~e~t,~.I,R~~.~!.~~._.. .
Roul., Medium, and
Point 0' Exposure
", :'~. , . ,. 'r I.""'I~ ,:,...,," ,..~, '-"""...".-"""""".;,;0;0,",,,,,,,-,,:,,,,,,,,,-, .;.. .'.', ""."'
.:."~ ." .. . .~: .,,-~ ....
Hvpothetlcal On-Site Res/dents
(cant .)
Incidental' Ingestion 0' surface water or
sediment from Burnt Bridge or Cold Creek
Dermal contact with surface water or
sediment from Bumt BrIdge or Cold Creek.
Ingestion of ftsh/shellflsh
Inhalation ofwlnd-borne particulates from
exposed surface soils
Inhalation of vapor-phase chemicals
emitted from site
"1'. ,'.
'.~ ,..'..' ',.,"' .' n(::!~.,,;::;.""'!:":~',,"
Incidental Ingestion of soIls during work
acllvttes
Ross Complex workers
Dermal contact with lolls during work
acllvltes
Inhalallon of wlnd-drlven particulates from
exposed soils
Inhalation of vapor.phase chemicals
emitted from site
Basis for Selection
. ' 1'1-'"' ,~~., ,..,'''''' ....,.", ;""."..... ."'~""'.'._~....,..'''''..J. ~,'I't'.",:'-"'~:o'ot't ,,,'--,,,,,,-,,.,,"'..~I ..."... ';'''':... I . .
. ",; '; .- ~'" "..- ."" -.. ,.
Assumes that contamInants could be token up bV human receptors during
swimming activities.
Assumes that contaminants could betoken up bV human receptors during
swimming activities.
Assumes thai Ross Complex contaminants could be taken up bV aquatic
organIsms and Ingested bV human consumers.
Assumes that soli-borne contaminants are transported Into the air onslte.
Considered highly unnkely.ln part because most of the site Is paved. but was
addressed os Bosenne RA pathway.
r ';'::=':~':';~:;"'!I!''''~ftM!t;:t!t:HII$~$~,~~IItS*t.:t~tM1I'''_(J''I;.,...;ItIIt:''I<'''''~ 1.,:t4~I'''''''I'iil'l !...~,i.;.~~~,
-------
7.2.1.3 Identification of Exposure Pathways
"
Exposure pathways selected for evaluation in the risk assessment were: 1) incidental ingestion of
contaminated soil and dust; 2) dermal contact with contaminated soil; 3) ingestion of contaminated produce;
4) incidental ingestion .of surface water; 5) dermal contact with sediments; 6) ingestion of contaminated
fish/shellfish; 7) inhalation of contaminated particles; and 8) inhalation of organic vapors. Surface soils were
the principle source of contamination evaluated in the baseline risk assessment for: Operable Unit A. Potential
pathways were based on the three receptor groups (off-site residents who use Waste Unit Group #1 for
recreational purposes, hypothetical on-site residents, and on-site workclS) discussed above and summarized
on Table 3.
Table 3 depicts the rationale for selection of the potential exposure pathways for each of the three
receptor groups (off-site residents. on-site workers. hypothetical on-site residents) including route, medium
and eJtposure point. and basis for selection. For on-site workers and hypothetical on-site residents, seven
pathways were evaluated and six were evaluated for off-site residents. Inhalation or other eJtposure to fugitive
dust was evaluated for the RI for both on-site and off-site receptors. Grain size analysis of on-site soils
indicates that these soils are not subject to wind erosion. therefore this pathway was not included in the
quantitative assessment. Guidance for numerical eJtposure factors was generally obtained from EPA (e.g..
EPA 1989a; 1989b; Region 10 1991, 1991c, 1991b) or the opeD literature.
7.2.2 Toxicitv Assessment
'Ibis section summarizes the toxicological basis for aU compound-specific toxicity criteria requiRd
to conduct the Baseline Risk Assessment. These criteria. based on available quantified dose-response toxicity
data, are developed and reviewed within various offices of EPA. Summaries of the basis from which
toxicological values were derived are presented below.
7.2.2.1 Non-Carcinogenic Effects
For noncarcinogeaic chemicals. the reference doses (RID) are ~ as beucbinarks for toxic eudpoints
of conc:em. The goal in developing a RID is to identify the highest n(M)bscrved-adverso-ef'fect level (NOAa)
or the lowest-observed-adverse-effect-Ievel (LOAEL) from wdl-designed human or animal studies.
Uncertainty factors from 1 to 1.000 are incorporated to adjust this level based on the following consideratious:
. I) the duration of the experimental exposure, 2) effecIs elicited (if any), 3) eJttrapolation of the data to other
species (such IS eJttrapo1ation from animals to humans), and 4) scositive subgroups. Additional modifying
factors varyiag between 1 and 10 may also be incorporated in the derivation of the RID if additional
consideratiODS are ~'Y. RID and slope factors for the BPA risk asses<;ment were taken from EPA's
computerized Integrated Risk Information System (IRIS); Health Effects Assessment Summary Tables
(HEAST); Drinking Wa= Health Advisories; or personal communication with EPA Region 10 Risk
Assessment saaff.
The toxicological cbamcterization of compounds of concern was generally confined to chronic (i.e.,
lifetime) rather than acute or subcbronic eJtposures. This cbamcterization is consisteDt with the contaminant
concentratioDS fouad OD-Site, EPA guidance (EPA. (989) and eJtp0sure5 like1y to occur on site.
7.2.2.2 Carcinogenic Effects
For carcinogenic chemicals, slope factors are estimated using a conservative mathematical model
which estimates the relalionship between eJtperimental eJtposure (i.e., doses) and the development of CUCCI'
_11.-..1'-
-------
(i.e., response) that is derived from human or animal studies. Since there is much uncertainty in the dose-
response values generated using this procedure, the upper 95 percent confidence limit of the slope of the dose-
response curve is normally used in deriving the slope factor.
7.2.3 Risk Characterization
. .
The exposure and toxicity assessments form the basis for the characterization of chemical risks posed
by the Site. Carcinogenic risk is estimated as the incremental probability of an individual developing cancel'
in excess of the normal background population incidence over a lifetime as a result of exposure to a chemical
eith~ known or suspected to cause cancec. To estimate cancec risk, slope factors are combined with site
exposure information to estimate the incremental cancer risk, which represents a probability of cOntracting
cancer, and which is usually expressed in scientific notation (e.g., lE-(4). An excess lifetime risk of lE~
indicates that, as a plausible upper bound, an individual has a one-in-ten-thousand chance of developing cancel'
in a lifetime as a result of site-related exposure to a carcinogen.
For known or suspected carcinogens, acceptable exposures arc generally concentration levels that
represent an excess upper bound lifetime cancec risk to an individual of between lE..()4 and lE-06, using
information on the relationship between dose and response (NCP 1990). '
For non-carcinogens, the measure used to describe the potential for toxicity in an individual is IIOt
expressed as a probability. The potential for noncarcinogenic effects is evaluated by comparing an exposure
level over a specific period (e.g., lifetime) with a reference dose derived for a similar exposure period. This
ratio of exposure to toxicity is called a Hazard Quotient. The Hazard Index (HI) is the sum of more than one
hazard quotient for multiple substances andlor multiple exposure pathways. Potential noncarcinogenic effects
may be of concern if the HI exceeds unity (i.e., HI> 1).
7.2.3.1 Evaluation of On-Site Risks
R.esUlts of the Baseline RA indicated that the sum of lifetime cancec risk estimates for all chemicals
of concern for on-site worlcers and hypothetical on-site residential child and adult in each Waste Unit Group
2,4,5, and 7 ranged from 6.3E-06 to 6.7E-5 (Table 4). The highest risk was associated with WUG 14 and
was principally related to arsenic. All hazard quotients were below 1 except for antimony (1.45) in Waste
Unit Group #4. The estimated HQ for antimony found in Waste Unit Group 4 (Sand Blast Area) was for the
hypothetical oo-site residential child. Risks, associated with the contaminants present in the Sandblast AJea
have been removed since this area underwent a removal action.
For Waste Unit Groups, 1,3, and 6, total cancer risk estimates ranged from 4.4&05 to 2.1&04.
Waste Unit Group #1 is located in the northeast comer of the site and consists of two individual waste units
(Van's Way Oil Storage Area and Wood Pole Storage Area East). Total cancec risk estimates for all three
receptors, on-site worker and hypothetical on-site child and adult, ranged from 8.9E-OS to 2.1E-04. Total
HPAHs accounted for approximately 91 ~ to 95~ of the projected risk for each on-site receptor. The
occUrrence ofHPAHs were generally laterally extensive in the Wood Pole Storage Area East and only at spot
locations in Van's Way Oil Storage Area. Hazard Quotient estimates for Don-c:arciDogeoic compounds in
Waste Unit Group 1 were below the Hazard Jnd~ of 1; therefore, adverse health effects associated with the
non-carcinogenic compounds evaluated are not expected to occur,~' this area of the Site.
Waste Unit Group 3 is located in the central industrial core of the Site and consists of four individual
waste units, Capacitor Testing Lab, Paint Storage Facility, Plumbing Shop and PCB Storage Area. Total
cancer risk estimates for the on-site receptors ranged from 4.4E-OS to 1.2E-04.
&e1/.....1.-
-------
Table 4 .
Estimated Hazard Quotients and Ufetime Cancer Risk, Hypothetical On-Site Residential
and Occupational Receptors .
Operable Unit A
BPA Ross Complex RI
.
.
Hypothetical
On-Site Residential
Adult
Based on UCL1
HypoIheHcaI
On-Site ResIdential
CttIIc:I
On-Site
Worker
Compound
~_....~, ~ _.~ _..,~'" - .'~ ~.__.- ,,,"""'''.~.~ "-"""''''''''
.. . '" . .-:-...~~.,~........:~"......'"!O..~:;;;" ~'i""'.'" .. .'..r:"':....,.~~!:.,.!j'n !:r1'~': ~j'~.:;,,+...j...,.. ...<..~.'.. ..~-':.'~ ... . ~..~
--~...._-~...' "'"
Waste untt Group .1
~o~~t~~~!'!r"'!~"~;~'''~1;1''~",:' "
Ovomk.m
Copper
lead
Zinc
Conhlbulion from lead "
Total HPAHs
Benzo(a)pyr8n9
Penta:hlo/OPhenEll
Bis (2-ethy\h8XYt) phthdate
Total PCBs
sun of cancer lisle . "
PeIcent Itsk attIIbutabIe to total HPAHs.
pentac:hlorq)her1O and Iotal PC8s..
Waste Unit GrOUP .2
.. ...'.' 1':","". ........'~~.7!1)}.:::'..~:.+'~-:i."I~"T.,,="... ~
Wn7nrd QuotIent
0vtx'rWm
Copper
lead
Zinc
ContribUtion from lead ..
Total HPAHs
Benzg(a)pyr8n9
Pentad'1IoIopheIlOI
Bis~phthalate
Total PCBs
sun of cancer IIsk . ..
PeIcent dIk aftII)utabIe to total HPAHs.
pentachIorophen and Iotal PCBs ..
Waste Unit Group .3
...:. '':;',':: ."!~I~.W:'''';Ii.:..:~,t:'It':':;:::'lt: "'-':"".:
Wn7nrd Quatient
CtvarrUn
Ccpper
Lead
Zinc
ConI1tIutIon from lead .
Total HPAHs
Benzg(~
Pen~1OI
BIs~~ phthaIat8
. Total PC8I
Total COO/CDF
lUI'I'Iof cancer IIsk I ..
PeIcent Itsk aItrbItaI:IIe to total tf'AHs.
pel1II.d 1IoIq)h8I1OI. en:! total PC8a .
:j.'-'.:... ~''''': ':~A...-.;t... .
-JDoWII~';' .
0.04 0.10
0.04 0.19
0.04 0.16
0.01 0.01
8.1E-05 ~
4.1E-05 9.7E-05
3.3E-06 9~
3.1 E-
-------
Table 4
Estimated Hazard Quotients and lifetime Cancer Risk, Hypothetical On-Site Residential
and Occupational Receptors
Operable Unit A
BPA Ross Complex RI
Compound
Hypothetical
0~51te Residential
Adult
Based on UCl1
Hypotheti~1
On-5l1e Residential
ChIld
- .
On-5l1e
Worker
.~ ",,,,,',,'" ,""," """"';'. .' ..... '.'
'. ..._.,.,............~.,."".~"".,~ '."
:,,,,,"""~--"""'"
..............._~_.........;",.".,.,
,.-.-J--.
~~~.~~~-!~'..'.i'"''''"''<'''
Hmnrd Quotient
AntimDnV
0vcrnUn
Copper
Lead
Zinc
,,,!:':,;~~~,':~;';" "rt'~:.' v~;:j'i'~ i'."~::.!:-' ;...-~;.~::;::,'~ :" :::. ;;';',:;~..::1J!.:-'..":'~'
. '. ;. '!"'~: :,:-':,;:,~,!,:":""''','': ,:::.11'.;;!.i~" .!.::,~:o~;o;:o:IOIiO 'L~.h"JItO"~
0.89
0.19
O.oe
Q.32
0.07
us
0.29
Q.22
1.17
0.11
0.02
<0.01
<0.01
0.04
<0.01
ContributIon from lead ..
IUr1I 01 cancer risk I ..
I'eIc&1t lisle attribUtable to totaIWAHs.
pentachlolophenol. and total PCBs ..
6.OE-OS
3.5E-06
1.5E.()6
~7
1~
1~
6.7E-05
2.1~
5.1~
1.1~
1.8E.Q6
9itHJ7
2.~
3~
1&.06
~
2.5E-07
e.8E-07
1.88)7
1.0E-06
5.6&06
AnenIc
Total HPAHs
8enzD(a)pyI8ne
PentachlcxcphenOl
BG (24thyh1xy1) phthalate
Total PCBs
~
~
69.oI!'J.
Waste Unil Group '5
~.&~ft,;,,~~!~~~~""
Qvomium
Copper
Lead
zn:
",.,~ ,..r, ...~;oI;!:' ":"~ :t.~i ~-''''.'~':' "::!....",,j;"~~..;;.~.;;'(,~!-.,;,;;.:..
"~"". ""t', "
. ~",."'" ".~,"""', ,
, !<...-,;::.~~~ ~':iI ~:ioi.;"::~;:~~~~>
o.os
0.11
0.07
0.01
0.11
0.39
0.28
0.02
<0.01
0.01
0.01
<0.01
ContrtbuIian from lead ..
sum of cancer lisle I =
PeIcent lisle attrIJutabIe to totalWAHs.
pentc:x:l\lolOphellOl. and total.PCSs.
9J1Eo«1
5.1~
U~7
3.1~
1.1~
~
1.AE.05
5.8E..()6
~
7.1~7
2.~
4.6E~
6.3E-06
2.4£.()6
1~
<1.0E-07
1.~.
1~
Total HPAHs
8enzD(~
Pentac:hlolophenol
Bis (24thyh1xy1) phthalate
Toto! PCBs .
87 ..tIa
98A~
1~
,~~-=~~~.iI!I:.~~:;o;'1:~;..;~,.;;,~~:t!!'4i7,,;:.;.~~';!~;-oiIi~....:KP.I"„~"'''''':...o.:;~:::.:....~,;.",io:-<'-:.,::;.:...-,L' ~,.:,~::.::;:(, . ..'..:..~:;;...
IoImnorf 0. ....tIAnt
Antinony
Chromium
Copper
Lead
Zinc
"."."
, ::=:.:;.;.;.:;..,i...:~;:t;Ii.:..\:i.!.~~~~~,:' ..~~;W!I,N$Ol:'
0.24
0.07
0.07
0.44
0.01
us
0.12
0.17
1.67
0.02
Q.CX)
<0.01
<0.01
O.os
< 0.01
ContrbutIon from lead ..
amd cancer IIIk I.
Percent lisle attIINIabIe to totatWAHs.
penlachIofopheIlOl. and Iotal PCBs.
2.1~
1 JIE.06
6.4E-G7
1.2£.(16
7~
8JE.(I5
1.~
2.QE.06
1J1Eo«1
6.7£47
2JE.04
2JE.04
3JIE.07
6.~
~7
<1~
7.2E0C5
7.3E.(15
Total HPAHs
Ben2Io(a)pyr8n8
JIbj~1OI
BII (24thyhexyO phthalate
Total PC8I
98.4A
99.6~
1~
, . ~.'. ",~,~,'-", .'.....,..... -~ ,~
.,.,.,~-_....,._..,....,~-,,~......~, ", '...'~~ ....~- "".,~ ..~... "". ..............,.".,.~. .,,..~..._...'
~
. n.- C8IauI8I8d bb8nzaC8I..,.- illIGI indIId8d in... _01- .--. 8C8IP iI--- it............AM -.......
Jcb No. 0673NI1241iS
(!OU'..ROOI.ICI.WlTa-4 I 4172193 I 81)
-------
Tobie 4
Estimated Hazard Quotients and Ufetime Cancer Risk, Hypothetical On-Site Residential
and Occupational Receptors .
Operable Unit A
BPA Ross Complex RI
. . .,...-.".~~..'.~'
Compound
Hypothetical
On-Site Residential
Adult
Based on UClI
. Hypolhelic:al
On-SIte Resldenllal
ChIld
On-SIte
WOfIcer
-
.
. ~ ",,, ",.., ..'~ .,,~~ .
......."'~~.. .' ___r,.'"
Waste Unit Group .7
''>;0;_;'...- -X~ ~'''''''':;'~-:::O.'~'"'''''..:<.'I!M:'':''''
1.QE.()7
3.1E-06
4.9E-06
S.QE.()S
Allene
Total"'AHs
Benzc(a)pvnIne -
Pbo ,loQc/'b"opheIlOI
BIs ~phthclate
Total PCBs
20.~
. -..... ...._......~_...__......_..__...,...~.....-_. .........--~._....-......'''' '''''-''''. . '.-.
.....," ''''''. .....~ .....--~..... ,.'-......... .'"''''''
~
. 1118 riIk.........., tar b8nZ0(8j.".. illIIII incW8d n'" - ell - riIk wIuo. IIC8IP .--.ltar it .........Nt riIk......
Jab No. D6137~124QIS
~1JC1.Wl1a04 I ~ I eO
-------
Tbe estimated total cancer risk of 4.4xlO.s was found for the on-site worker. Total PCBs accounted for
approximately 91 % of the projected risk for the on-site worker in Waste Unit Group 3 and were
predominantly found in the Capacitor Testing Lab. Total PCBs occurrences were present in a localized area
in the Capacitor Testing Lab and at spot locations in the Paint Storage Facility, Plumbing Shop and PCB
Storage Area. Hazard Quotient estimates for non-carcinogenic compounds in Waste Unit Group 3 were below
the Hazard Index of 1; therefore, adverse health effects associated with the non-carcinogenic compounds
evaluated are not expected to occur in this area of the Site.
'.
waSte Unit Group #6 consists of one waste unit, the Ross Substation and Capacitor Yard, which is
enclosed by a fence with restricted access. The sum of cancer risk estimates for all three receptors, on-site
worker and hypothetical on-site child and adult, ranged from 8.0E-05 to 2.0E-04. The occurrences of total
PCBs in this Waste Unit Group is comprised of spot locations. Total PCBs accounted for approximately 95%
to 100% of the projected risk for each on-site receptor in this area.
Altl:rough lead was found in Waste Unit Group #6 above background, modeling results from the EPA
Uptake/Biokinetic Model (conducted for children, the most scnsitive indicator) suggested no evidence of
elevated hazard at reported soilleve1s for WUG #6. .
7.2.3.2 Evaluation of Off-Site Risks
The risk to off-sitc residents including adult and child as potential receptors was focused on Waste
Unit Group 7 (Wood Pole Storage A«:a East). This area is located on the southern Site perimeter and is the
only waste unit group that has unrestricted access to off-site residents. The risk was assessed through
exposure by potential recreational use since other routes have not been found to be significant. The lifetime
. cancer risk estimates for both off-site and recreation receptors related to Waste Unit Group 7 range from 1.2E-
06 to < 1.0£-07 which is below EPA's acceptable cancer risk range (fable 5).
Hazard Quotient estimates for non-carcinogcaic compounds in the evaluation of off-site receptors were
below the Hazard Index. of I; therefore, adverse health effects are not expected off-site.
7.2.4 Uncertainty
Major components of the assessment which decreased the certainty of other results were 1) the toxicity
reference values used, and the lack of values for several chemicals; 2) limitations in contaminant concentration
data for soils, ground water, and surface water; 3) the inclusion of concentrations at a level one-half the
detection limit for many chemicals; and 4) the use of a Dumber of assumptions to establish exposure
parameters in computing chemical intakes.
Due to uncertainty in these and other areas, conservative assumptions were made in order to ensure
protection of human health. Cancer and non-canccr risk estimates must be carefully interpreted, particularly
when evaluating noncarcinogenic effects where uncertainty factors of tWo to three orders of magnitude are
used in dose.-response assessments.
Although most parameters addressed and included in the Baseline RA are inexact, all are designed
to be conservative and therefore, are protective of all receptors considered.
_11--1""
-------
Table 5
Estimated Hazard Quotients and Ufetime Cancer Risk, Off-site Recreational Receptors
Operable Unit A
BPA Ross Complex RI
"
Compound
Based on 95"1. UCl for WUG f7
Adult Child
.'. . --.---........--.-.,.... .-,' .....~-.,' .'..
. ~~ ~_......,-_._..__....~. ,~~,--"~"~~-,,,,,,"""''''-' 0. ".~..'.. ."
Hn7nrd Quntient
Ovomium
Copper
lead
Zinc
0.02
0.05
0.05
-------
7.3 ECOLOGICAL RISK ASSESSMENT
The Baseline Ecological Risk Assessment was an evaluation of the potential threats to the environment
from the Site in the absence of any remedial action. It identified potential on or off-site exposures of
environmental receptors iobabiting the area to chemicals of concern, characterizes the toxicological properties
of "indicator" chemicals, and quantifies the extent to which exposures may contribute to ecological risk or
degradation under the conditions defined for the Site.
. .
The terrestrial components of the ecological risk assessment included: (1) identifying "indicator"
chemicals (previously discussed); (2) identifying potential exposure pathways; and (3) identifying biological
habitat and potentially exposed wildlife (or other) receptors. .
The overall approach to both the human health and ecological portions of the baseline risk assessment
are similar, especially in utilizing a Reasonable Maximum Exposure (RME) approach to addressing potential
ecological expOsures. Key differences include: (1) the ecological risk assessment addresses chronic toxicity
(based on available dose-response data, rather than considering carcinogenicity as an endpoint); and (2) several
wildlife iDificator species are ideotified to represem all potentially susceptible receptors. The May 1992
Operable Unit A RI report discusses the physical setting in which pOtential ecological exposures could take
place, including characterization of biological habitat and identification of indicator species and potentially
exposed populations.
For the ecological risk assessment. three key "indicator" species were ideotified, including the
American robin, Raccoon, and Black-tailed deer. These species were selected based 00 criteria intended to
ensure that DO other species are liIce1y to be more exposed than the indicator species, and that they are
representative of the potentially most sensitive species or organisms present at the Site. These criteria include:
sensitivity to cootaminants of concern; habitatioo within C1arlc couoty and potentially the vicinity of the Site;
valued or protected species (e.g., rare or endangered, game species, etc.), to ensure that protected organiSJ;DS
are considered; a mixture of aviaDlm..mnu.li8n species designed to address a variety of life histories and
feeding habits; representativeness of the potential for CODt..minant bioaccumulatioo (addressing predatioo as
a primary feeding habit); and representativeness of local biological communities. No threatened or endangered
species were observed at the Site or adjacent to the site.
7.3.1 Risk Characterization
Results shOWD on Table 6 indicate the total exposure and contribution by individual pathway for the
Baseline Ecological RA. Results are based 00 the 95" uppec confideoce limits (UCL values) by Waste Unit
Group, by teccesb:ia1 ecological receptor, and by "indicator" contamiruant. Similar to the ooo-carcinogenic
analysis of the human health component, when the HQ value is less than one, DO chronic toxicity associated
with Site contaminants is expected. It is conservatively assumed for the purposes of the analysis that all three
indicator species (robin, necooo, deer) could be present at any of the seven Waste Unit Groups of Operable
Unit A.
The results of the exposure assessmeot indicate that the five metals for which HQ values exceeded
one included antimony (Waste Unit Groups 4 and 6), arseaic (Waste Unit Group 4), chromium (Waste Unit
Groups 4 and 7), COppel' (Waste Unit Group 5), and lead (Waste Unit Groups 4, 6, and 7). No threshold
values were exceeded for the blaclc-tailed deer; potential chronic effects could be expected for the robin 001;
for antimony and chromium. while potential chronic effects could be expected for the raccoon oo1y for
arsenic. COpper'. and lead.
6oc1l""'1Aac:
-------
Table 6
Ecological Hazard Quotients by Contaminant, Terrestrial Receptors
Operable Unit A
BPA Ross Complex RI
t.
compou~ ,
Waste Unit Group' 1
~"~;. ,,~~,,:)iN!!!"I!I:!:.!");<;"i'" -"'~r,~'~~~:a;r.I:~""-'-'
Arsenic
Copper
Lead
~
Total HPAHs
Benzo (0) pyrena
Bis (2-EH) phthalate
Pentac:hloroph~
Total PCBs
waste Unit Graup 12
. ~1It""N' :....--.:......,.......:...,~ . ,
Arseric
Copper
Lead
~
Total HPAHs
B;enzo (a) pyrena
Bis (2-EH) phthalate
Pentachlorophenol
Total PCBs
~~~:,~~!.!.~'o.~,!.~",., "
Hsenc
Copper
Lead
me
Total HPAHs
Benzo (a) pyrena
Bis (2-EH) phthalate
Pentachlorophenol
Total PCBs
Total [)ic))cR
waste Unit Group 14
.. '";',,-:,~~''''''''''I,;.~',......;.~\;o,oo.'W'.1 .
Antmonv
Arseric
OYomhn1
Copper
Lead
~
Total HPAHs
Benzo (a) pyrene
Bis (2-EH) phthalate
Pentachlorophenol
Total PCBs
~.... ,............- ."
Jab No. 06737-C1124C1i5
(IOU'-_ROOIJCLw)11L1\ I 4I72J93 I eO
American Robin
." ~:~~~~~~.--
Raccoon
(1'. Iolor)
Black tailed Deer
CO. columblonus)
-...".."" -..,...........-.........,...-.,'
..-........- -.""-' ........-..,.--... ...,
. .'~~:.,~+.. ..~..,~..',~r;:jl!l'.~..I'J:=~II.OI"':'f.'::o.~\0I!~t;-'~1o!....~...,-,(~'~:ot~_",.11,1i.f'I..I~!;ll'#'~:'~' '.~.~,~.~;"""l:!'I:'itri"o~'" ,... ,
0.03
0.02
"""'.";".,' """
0.43
0.33
0.07
0.06
0.01
0.02
<0.01
-------
Table 6
Ecological Hazard Quotients by Contaminant, Terrestrial Receptors
Operable Unit A
BPA Ross Complex RI
. t:orripoU~d
v.:~~,2~:~~..'5,
Arsenic
Copper
lead
anc
Total HPAHs
Benzo (a) PVl'ene
Bis (2~ phthalate
Pentachlorophenol
Total PCBs
American Robin
.f!~ mlgrat"-~'!!'-'H'" .
".: '.:~. ~. ,
0.02
0.07
0.01
0.10
0.02
0.01
0.01
0.05
0.20
wast. Unit Gloup '6
.~iI!,.----~~:;!!:;!t-o"o"r"'''.':''; ';.,
Antinony
Arsenic
Copper
lead
Zinc
Total HPAHs
Benzo (0) PVl'en8
Bis (2-EH) phthalate
Pentachlorophenol
Total PC&
",:,,"'!,":"!<,',.", -.". ,...,
3.02
0.03
0.02
0.08
0.13
0.01
<0.01
0.01
0.05
1.81
waste Unit Gfoup '7
.~ ~ +'!.i'\!I'!':'r".',',
Atseric
CtYomiun
Copper
lead
Zinc .
Total HPAHs
Benzo (a) PVl'en8
Bis (2-&0 phthalate
Pentachlorophenol
Total PC&
:. ""-'"~""'<~0.c5".:.,..:".... ..:.,,::..:.:
40.04
0.01
0.03
0.08
0.01
<0.01
<0.01
0.01
0.11
'~~"'....,..,-,.....,.....__..._,.,-_--."... .'~' ,.,oc.'" ,..'
".,-...,',,,.,"',,""., "...."."
Jab No. 06737~12-4D15
«(OUt.JlaoIJCLW)1a.. I 4fl2I'13 I eI)
Raccoon
(P. Iota"
Black tailed Deer
(0. coIumbIanus)
.._.-. _.'''''",'.....'~
.'. ""'~".-..."-~.__......' ........
':";;.,'
.... 'i ":";:::"'~;;';':'~.;;;;:,.,:~.."",!:"';;'!,~. v",,','
..;:.,."-.--::!:n;",:;".:;;':i\:;-~~.'~',,,,::,
'. .
0.25
1.23
0.29
0.11
<0.01
<0.01
<0.01
<0.01
0.04
0.06
0.11
0.05
0.01
<0.01
<0.01
<0.01
<0.01
<0.01
"".;.~",,".;"'!";!~~~"'f!l!IlIi'r.~il:L~,.........'i::.. :..Z'.:.. """":\.J~ ,.
"', ~""."",~','~')..,' ,J'Io,,:,:., ~ "...;
om
0.44
0.26
2.84
0.13
<0.01
<0.01
<0.01
<0.01
0.34
0.01
0.10
0.02
0.44
0.02
<0.01
<0.01
<0.01
<0.01
<0.01
',~..-r.:;<:!<.4:~o~::::a..~ ~ "::'"~""";":"''''''';';;;'~~~:.O:151oi11''''':::(;o-)': <:P:
QI7 0.04
0.22 0.02
1.11 0.17
0.08 0.01
<0.01 <0.01
<0.01 <0.01
<1J.oI <1J.ol
<1J.ol <0.01
om <1J.ol
-------
The sole organic contaminant which exceeded one for the ecological RA was total PCBs in Waste Unit
Groups 3 and 6. No threshold values were exceeded for the black-tailed deer or raccoon; potential chronic
effects could be associated with exposures to the robin only. It should be noted that there are currently few
or no undisturbed surface soils in these waste unit groups which could provide suitable habitat for robins.
,-
In summary, ecological risk calculations for surface soil metals indicate the potential for chronic
toxicity to indicator species in Waste Unit Group 4 (Sandblast Area). Independent removal actions in
accordance with State of Washington Model Toxies Control Act cleanup criteria were conducted in this area
as well as in Waste Unit Groups 3, 5, and 7 which eliminate the potential ecological risk identified in these
waste unit groups or as in the case of Waste Unit Group 6, provide no suitable habitat now or in the planned
future for these species.
An independent removal action was not conducted in the Top Coat Test Area (a component of Waste
Unit Group #7); however, potential ecological risks associated with surface soils in this Waste Unit are
considered negligible because this area is covered by asphalt pavement and does not provide a suitable habitat
for these species now or in the foreseeable future.
8.0 REMEDIATION GOALS
The results of the baseline risk assessment indicate that no further remedial action is necessary under
CERCLA in 18 waste units in Operable Unit A and the Ellen Davis Trail.
Three waste units, the Wood Pole Storage Area East, the Ross Substation and Capacitor Yard, and
the Capacitor Testing Lab have been identified as requiring further action under CERCLA.
For the Wood Pole Storage Area East, the contaminants of concern are high molecular weight
polynuclear aromatic hydrocarbons (HPAHs) and pentachlorophenol. PCBs are the compounds of concern
in soils in the Ross Substation & Capacitor Yard and at the Capacitor Testing Lab. Based on consideration
of ARARs for this site, the remedial action objectives (RAO or clean up levels) for the compounds of concern
are:
Compounds of Concern RAO Source Soil Clean up Residential Risk
. Level (ppm) at Cleanup Level
Total HPAHs MTCAMethodA I 6.9 X l
-------
under MTCA since unrestricted access exists and they are not located within a recognized industrial area.
Therefore, the residential soil cleanup standards apply to these areas. The Ross Substation and Capacitor Yard
is considered industrial under MTCA since it is a secured area within the borders of a recognized industrial
area. The industrial soil cleanup standard for PCBs is applicable to this area.
-
,
The primary exposure pathway of concern in Operable Unit A is direct dermal contact. Both
residential and industrial soil cleanup standards are protective for this pathway, are within EPA's acceptable
risk range, and are protective of other media.
Actual or threatened releases of hazardous substances for this site, if not addressed by implementing
the response action selected in this ROD, may present an imminent and substantial endangerment to public
health, welfare, or the environment.
9.0 DESCRIPTION OF ALTERNATIVES
Nine alternatives were evaluated for soil remediation at the Capacitor Testing Lab, Wood Pole Storage
Area East and the Ross Substation 8£ Capacitor Yard. The general response actions initially considered for
soil remediation alternatives for Operable Unit A included:
.
Alternative A - No Action,
.
Alternative B -Institutional Controls,
8
Alternative C - Excavation with Off-Site Disposal,
.
Alternative D - Asphalt Capping with Institutional Controls,
.
Alternative F - KPEG Dechlorination
.
Alternative G - Soil Washing
.8
Alternative H - BES'P Extraction
.
Alternative I - Ex-Situ Solid-Phase Bioremediation, and
.
Alternative 1 - Thermal Treatment with Off-Site Disposal of Residuals.
Each-alternative is described briefly in the following sections.
9.1 ALTERNATIVE A: NO ACI10N
The No Action altemative is required by the National ContiDgeDcy Plan (NCP) and serves as a
baseline agaiDst which other soil remedial alternatives can be compared. Under this altemative, no remedial
activities would take place. This alternative docs DOt protect the public health or mitigate uoaccertable
environmeDtal risks associated with the contall'lination.
_11--'1.-
-------
9.2 ALTERNATIVE B: INSTITIITIONAL CONTROLS
.
.
This alternative includes the measures to limit or prohibit activities that may interfere with or disturb
contaminated areas and includes long-term monitoring of soils. Measures employed as institutional controls
would include access restrictions, deed restrictions, and land use restrictions. Access restrictions are designed
to prevent unauthorized access to areas where contamination is present and would consist of fencing, signs,
and roadway modifications. Deed restrictions would limit future land use. Land use restrictions would
prohibit disturbance of soil and nearby buildings.
9.3 ALTERNATIVE C: EXCAVATION WITH OFF-SITE DISPOSAL
This alternative involves the excavation of contaminated soils for disposal at an approved landfill.
The excavation would be bacIdi1led with clean earthen fill and compacted.
9.4 ALTERNATIVE D: ASPHALT CAPPING WITH INSTITUTIONAL CONTROLS
'Ibis aftcmative involves the application of a sealed asphalt cap over the contaminatl'Jd area to reduce
potential exposure of humans or the environment to the .contaminAnts. The cap would minimize the leaching
of soil contaminants. The asphalt layer would be of sufficient thiclcness to permit use of the waste unit for
multipurpose storage and would have an impermeability rating as required for landfiU covers. Tbe asphalt
would be sealed to further reduce its permeability and would be appropriately contoured to promote drainage
of non-c:oDtJlmi"At""" storm water to the storm SCWe£. Due to the continued presence of contamiDants,
institutional controls would be implemented. A long-term inspection program would include regularly
scheduled visual examination of the cap surface by qualified persoooe1. Subsidence, buclcling, or craclcing
would trigger maintenance measures. The results of the risk assessment indicated that contamination migration
to air was insignificant. Capping would eliminat... dermal contact. .
9.S ALTERNATIVE F: KPEG (POTASSIUM POLYETHYLENE GLYCn.) DECHLORINATION
The KPEG (potassium polyethyleae glycol) dechlorination process utilizes potassium or other aIJcaIi
metal polyethylene glycolates to degrade cblorioated organics. Excavated contaminated soil is mixed with the
KPEG solution in a heated reactor. When the reaction is complete, the KPEG solution and water is decanted
and the soil is washed with water. Tbe KPEG solution and water are recycled back into the process. KPEG
dechlorination reduces the toxicity of chlorinated contaminants and results in a nontoxic byproduct (EPA,
1989).
After treatment, the soil can be used as clean fill on site. Other .treatment residuals will be handled
properly as hazardous waste, as needed. Tbese residuals will be disposed of according to the specific
requirements for each waste stream.
_I'-'adl.'"
-------
9.6 ALTERNATIVE G: SOIL WASlflNG
This alternative involves the use of a washing process to remove contaminants from the soil.
Excavated soil is sorted to remove large debris. The soil is then rinsed with the wash solution as the soil is
passed over a series of screens. Contaminants are removed in the wash solution or are concentrated in the
soil fines. Following washing, the treated soil can be used as earthen fill for on-site grading. The
contaminant residual, which may include clays and fines, is sent off site for disposal at an approved RCRA
landfill.
.
.
9.7 ALTERNATIVE H: BES'J'8 EXTRACTION
Basic Extractive Sludge Treatment (BES'P) is a patented process that uses triethylamine to remove
contaminants from the soil. Excavated soil is mixed with the triethylamine, which removes contamin3.nts and
watec from the soil. The triethylamine is separated from the water and cont~minants; it is recycled for reuse
in the extractiOIt process. A small amount of concentrated contaminant residual would remain after treatment,
requiring disposal off site at an approved RCRA landfill. Treated soil can be used as clean earthen fill on site.
9.8 ALTERNATIVE I: EX-SITU SOLID PHASE BIOREMEDIATION
Contaminated soil is excavated and placed in a treatment cell constructed on site. The treatment ceU
would contain a lined enclosure equipped with a leachate collection and retum system, and adding nutrients.
water. supplemental micro-organisms. and oxygen as needed. Treated .soil can be used as earthen fill for
ping on site.
9.9 ALTERNATIVE J: THERMAL TREATMENT WITH OFF-SITE DISPOSAL
Contamiaated soil is excavated and incinerated in a mobile rotary kiln incinerator or fluidized bed
incinerator. Residual ash would be tested and if necessary disposed off-site. It is possible. based on. the
results of the testing. that disposal of residual ash could be OD. site.
9.10 ALTERNATIVES RETAINED FOR DETAILED EVALUATION
Tbe following alternatives were retained for detailed analysis based on the results of the initial
screening.
Wood Pole Storage A1U Btut
.
Alternative A - No Action,
.
Alternative B - Institutional Controls,
.
Alternative C - Excavation with Off-Site Disposal,
.
Alternative D - Asphalt Carping with Institutional Controls.
.
Alternative I - Ex-Situ Solid-Phase Bioremediation.
_1/--'1.'"
-------
Ross SubstaJion & C4paciJor Yard
.
Alternative A - No Action,
.
AJtemative B - Institutiooal Controls,
"
.
AJtemative C - Excavation with Off-Site Disposal,
.
AJtemative F - KPEG Dechlorination,
.
AJtemative G - Soil WashiDg,
.
AJternative H - B~ Extraction,
.
AJternative J - Thermal Treatment with Off-Site Disposal.
CapadJor Testing lAb
.
AJtemative A - No Action,
.
AJternative B - Institutiooal Controls,
.
Altemative C - Excavation with Off-Sitc Disposal,
.
Altemative F - KPEG DechloriDation,
.
Altemative G - Son Washing,
.
Altemative H - BF..S'P Extraction,
.
Alteroative J - Thermal Treatment with Off-Sitc Disposal.
10.0 COMPARATIVE ANALYSIS OF ALTERNATIVES
The remedial alternatives for each waste unit wete compared according to nine criteria as defined and
required by the NCP. The nine criteria are subdivided into three categories: (1) threshold criteria which relate
directly to statutory findings and must be satisfied by each chosen alternative; (2) primary balancing criteria,
which include technical factors; and (3) modifying criteria, which are measures of the acceptability of the
alternative to state agencies and the community.
All alternatives must meet the threshold criteria of overall protection of human health and the
environment and compliance with AltARs. The chart illustrated iD Figure 10 shows the relationship between
the screeoing criteria, the aiDe evaluation criteria, and the role of the criteria during remedy selection.. The
foUowiDg sections .preseat the comparison of alternatives.
.,.
_I,-,""Uoc
-------
Screening CriterIa
NIne EvaluatIon CrIterIa
~.,rat;}>~ ..,-{" ";.rf7~' r_~ ~," ~:"\,-\,.",,,'.' '. ,'..' ;..;..:
-:,?(2}(){~IJrf~'~j udJt~J.\;~lll: l~I~"J.!I,l ,',,: !
:;':",..!=,U~JUi,:(~I'J~~I~l}it0if':i\~hli' ,"," ,",
,~;if!~: ',,(~id't;i~j i G. [i L.o \','In;l~~;/~~ :,J:, ,:,/i., ':'j
- . . .
; "'..", : """. ',' .. .. .'
~:i:,~~tlt.Ji0:11:Jji',d3it),~lIkUiU:..tj@~J ':", !
',;"',::~ j:tJ;"J~r'OiH)' , ::,:"j
1''''-'.' ,,'"""::. . ,.'. . . -." "
~: "liJ~l~l~L8jiJ Ik 1(~tj~J~' ;tM~1~UL~~)" .' I
v:" ~;'G.I \',(~,n!I"Uil;l{~I!IiJ\\\ru:~III'iDiH , '\
" ; ,', :' .. " , , ,,: ' ' " " I
, '
. . . . .' j
" \,.'ji0u-i(;1""ljiUdIJ:),:1','U..!-:5' " .I
:".' ." I
J". ..: .. ." .:
.~,:!..:... \o~~::"b11...~,-~'.'ri- '~'rL. -...:~
~'"r,-til . ""J'':';''''~~'''''r. :"""":'~::
,,'\', ' '.0 "r',- . """I ; "-,
.!':,' .'. "u'd~l~'~IL~/~,."
t',.11~,,,;&:)~;i::;~: j':.>.;,/.i ;":.,,~':'~
." .' ..' .
: : ",' , , ' '," , ""', i
J':o(" <([,~,!~jUi,Ud!~~lIi~'l " " ,I
.~J} :.: : . " . ~ '" ': :. . "'. .. :; -' - --. j
':'>",~"'.';."!.,~~ '~fr"~!f~7}; '.( ~~Ji ~\~~:~', :\,.;;;,;'!/ ;;t.'~:
':<;:;" ". ' ,<,',' , ' !
"tf>;>"~~ll0I!t"dJ"~009 .. . .... :.1
. . . .
h01~~:".:-;' f~::'; S.\~.' '. '. ~', ," :~'~..' .:. " ~. ~:< ':":"{
\~~,~)~Jl'~'}!J,jI~'li~0":.!:J\~laB)"., 1
{"';"~~-; .\.' ',:. .~ - .'. . -~'-. .~', " . !
Role of Criteria During
Remedy Selection
"Threshold" Factors
"Primary Balancing" Factors
"Modifying" Considerations
Figure 10
Relationship of Screening Criteria
-------
10.1 .COMPARATIVE ANALYSIS FOR WQOD POLE STORAGE AREA EAST
Target Contaminants: HPAHs. PCP
10.1.1 Threshold Criteria
,-
10.1.1.1 Overall Protection of Human Health and the Environment
This criterion measures how the alternative, as a whole, achieves and maintains protection of human
health and the environment.
Alternative A, No Action, does not provide protection to human health or the environment and does
not prevent the migration of contaminants since no remedial activities would take place to reduce exposures
to contaminants.
AI~ve B, Institutional Controls, offers a slightly greater level of protection than Alternative A
through site restrictions designed to prevent exposure to contaminated material.
Alternative C, Excavation with Off-8ite Disposal, offers a higher level of overall protection than
Alternatives A or B, through the eliminAtion removal of CODtamin..~ materials from the Site. ConlBmin..t....t
materials would be transported to an approved landfill for disposal.
Alternative D, Asphalt Capping with Institutional Controls, offers a level of overall protection slightly
higher than Alternative B but lower than AltcnJative C. Alternative D would not remove risks associated with
contamination at the site, but would control risks by preventing exposure to the contaminants, inhibiting future
contaminant migration, and providing long-term monitoring.
Alternative I, Ex-Situ Solid-Phase Bioremediation, offers a level of overall protection comparable to
Altcruative C, but in addition, destroys contaminants to meet regulatory action levels.
10.1.1.2 Compliance with ARARs
Compliance with ARARs is a consideration of bow the alternatives comply with other regulations
explicitly applicable to the site and with those sufficiently relevant and appropriate to warrant inclusion.
There are no ARARs associated with Alternative A since no remedial actions would be taken, ARARs
would not be met. Alternative B wiD comply with MTCA requirements to prevent contact; however, it does
not meet the chemical specific ARARs identified for the site.
AJl contaminated material would be properly transported and disposed under Alternative C; therefore,
ARARs associated with transportation for off-site disposal would be complied with. Alternative D would
comply with MTCA requirements for preventing contact and Alternative I would comply with MTCA cleanup
requirements for residential land use.
Altanatives C, D, and I would comply with the Southwest Air Pollution Control Agency's
(SW APCA) gcaeral standards for maximum air emissions.
Altematives C, D, and I would comply with ARARs. Alternative A does not satisfy the threshold
criteria .because "DO actioo" would not be proteCtive. and therefore, will not be further evaluated.
_I/GanIIII...
-------
10.1.2 Primary Balancinl!: Criteria
10.1.2.1 Long-Term Effectiveness and Permanence
This criterion evaluates the long-term effectiveness aDd pennanance of alternatives in maintaining
protection of human health and the environment after remedial action objectives have been met.
"
Alternative B, Institutioaal Controls, controls long-term risks by minimizing the potential for
disturbance of contaminated materials. Residual risks to the on-site worlcer will not represent an unacceptable
cancer risk.
Alternative C, Excavation with Off-Site Disposal, has a high degree of long-term effectiveness and
permanence. This alternative minimizes the risks associated with contJllminllltM soils by their removal from
the Site. Residual risk to the on-site worker will Dot represent an unacceptable cancer risk.
Alternative D, Asphalt Capping with IDStitutioaal Controls, would be slightly more effective than
Alternative B but less effective than Alternative C. Under this alteroative, CODtRmiMlnts would be left in place
and a cap would be installed over them. This cap would preveat exposure to the CODtJllmination. The
permanence of Alternative D would depend on the effectiveness of iDstitutional controls and on long-term
maintenance of the cap. Residual risk to the OD-site worlcer will not represent an uDIi'~ble cancer risk.
Alternative I, Ex-Situ Solid-Phase BioremediatioD, offers long-term effectiveness and pcrmaDence
comparable to Alternative C. CoDtaminants would be degraded through treatment. Residual risks would be
compared to Alternative C. .
10.1.2.2 Reduction of Toxicity, Mobility, or Volume through Treatment
Alternatives were also evaluated according to their ability to reduce, through treatment, the toxicity,
mobility, or volume of contaminants.
There is no treatment associated with Alternatives B, C, or D.
Only Alternative I, Ex-Situ Solid-Phase BioremediatioD, provides reduction in contaminant mobility,
toxicity, and volume through treatment since contamioaots are destroy~.
I 0.1.2.3 Short-Term Effectiveness
This criterion 8ddresses the effects of the alternative during the COnstructiOD and implementation phase
until remedial action objectives are met. .
Alternative B, Institutional Controls, would not present additioaal short-term risk because
contRm;ntlt~ materials would not be disturbed. Site restrictions would be implemented in about two weeks
and the deed restrictions and other laud use restrictions would take approximately three months to implCIDCIlt.
Alternative C, Excavation witli Off-Site Disposal, prescats more potential for increased short-term
risk to the community. worlcers, and the environment due to the poteDtial exposure to dust geocratcd during
excavation as compared to Alternatives A or B. These risks can be effectively cootrolled using standard dust
suppression mcdlods, personnel protective equipment and through the implementation of a health and safety
_1/--..11.-
-------
plan. These risks will be eliminated after the implementation of the alternative which is expected to require
eight weeks. This time frame is longer than Alternative A, but less than Alternative B. Measures to control
the risks will be implemented prior to excavation.
"
Alternative D, Asphalt Capping with Institutional Controls, would present a lower short-term risk
than Alternative C. Tbe potential risk would be present only during the spreading of base course materials
over the contaminated surface which may generate a potential exposure to dust; however, this risk can be
effectively controlled. Time to implement this alternative is similar to Alternative B. It will take
approximately two weeks to lay the initial base course thus eliminating the short-term risks. Measures to
control the risk will be implemented before commencing the activities associated with laying the base course.
Alternative I, Ex-Situ Solid-Phase Bioremediation, presents a higher level of potential short~term risk
to the community, workers and the environment associated with exposure to dust from handling soil during
treatment over time as compared to Alternative C. Potential short-term risks can. be effectively controlled.
With treatment time of approximately one year, the time to complete remediation and reduce short term risks
is considerably longer than the other alternatives. Measures ~o control these risks will be implemented prior
to excavating Contaminated soil.
10.1.2.4 Implementability
This criterion addresses the technical and administration feasibility of constnlcting, operating, and
maintaining a remedial action alternative. .
. Alternative B is slightly difficult to implement due to the need for deed restrictions and land-use
restrictions .
Alternative C, Excavation with Off-Site Disposal is more difficult to implement that Alternative B
because approval for landfill disposal will be required.
Alternative D, Asphalt Capping and Institutional Controls, is more difficult than Alternative B but
similar to Alternative C. Labor and equipment for installation of the cap are readily available.
Alternative I, Ex-Situ Solid-Phase Bioremediation, is more difficult to implement than the other
alternatives considered. Treatability studies would be necessary to confirm degradation levels. The labor and
equipment to perform bioremediation is readily available.
10.1.2.5 Cost
Cost is another criterion by which candidate alternatives are compared. Costs in this case are
measured as direct capital costs. The direct capital costs for the remedial alternatives at the Wood Pole
Storage Area East for 3,700 cubic yards of contaminated material is as follows:
_1/.........s1.""
-------
Alternative
Direct Capital
Cost
Alternative B -
Institutional Controls
$20,520 .
",
Alternative C - Excavation with Off-5ite Disposal'
$513.660
Alternative D - . Asphalt Capping with Institutional
Controls
$396.340
Alternative H - Ex-5itu Solid-Phase Bioremedi«tion
Tier 1: EabaDc:ed Bioremediation
Tier 2: EabaDc:ed Bioremediation.
Gravel Cap. Institutional Controls
Tier 3: -EabaDc:ed Bioremediation,
Asphalt Cap. Institutional Controls
$450.000
$482,120-$586,520
$5 10,520-$870.520
Altemative D. Asphalt Capping with Institutional Controls. is more costly than Altemative B, but
significantly less costly than Alteraative C.
Altemative I. Ex-5itu Solid-Phase Bioremediation. costs more than the Institutional Controls alternative and
costs less than Alternative D.
10.1.3 Modifvin2 Criteria
Modifying criteria are used in the final evaluation of the remedial alternatives. and include comment from
Ecology and from the public.
10.1.3.1 State Acceptance
The State ofWasbington concurs with the selected remedy and comments received from Ecology bave been
incorporated into this Record of Decision.
10.1.3.2 Community Ac:c:eptanc:e
Based on the COJDJDel1ts received during the public review period and at the public meeting. the public
accepts the prefened altemative.
10.2 ROSS SUBSTATION AND CAPACITOR YARD
Target CoIUD1tlinant: PCBs
10.2.1 Threshold Criteria
10.2.1.1 Overall ProtectioD of Human Health aad the Eoviroameat
Altemative A. No ActioD. does not provide protectiOD to human health or the cDvironmeat since nv
'Off-sitc incincralion is elimiaaIed &om coasidentioa bccauIe die eoaI8miaaled IOiI - dcIcnIIiDcd DOt 10 be . RCRA WuIC.
4iIc""""',-
-------
remedial activities would take place.
Alternative B, Institutional Controls, offers greater levels of protection as compared to Alternative
A, through site restrictions designed to prevent exposure to contaminants.
..
Alternative C, Excavation and Off-Site Disposal, offers a higher level of protection as compared to
A and B because contaminants are removed from the site. The contaminated soil would be treated to meet
applicable land disposal requirements.
Alternative F, KPEG Dechlorination, offers a high level of overall protection of human health and
the environment, comparable to Alternative C. The KPEG process permanently degrades PCBs and leaves
a treatment residual in the soil, but this residual, polyethylene glycol bipheynyl ether is considered to be non-
toxic. '
Alternative G, Soil Washing, provides a lower level of protection of human health and the
environment th!n Alternatives C and F because Alternative G is not expected to achieve comparable redUctiOD
in contamiuant levels.
Alternative H, BEST, offers a level of ovc:tall protection comparable'to Alternatives C and F.
Altemative J, Thermal Treatment with Off-Sitc Disposal of Residuals, offers the same level of overall
protection as Alternative C. The process geocrates an ash that would be sent to a RCRA landfill for cfisposaI.
10.2.1.2 Compliance with ARARs
There are DO ARARs associated with Alternative A. Since DO remedial action would be taken,
ARARs would not be met. Alteroalive B will comply with MTCA teql1irements to prevent contact; however,
it does not meet the chemical specific ARARs identified for the site.
All dangerous wastes and treatment residuals that are dangerous wastes would be properly transported
and disposed under Alternatives C, F, G, Hand J; therefore, ARARs associated with transportation and
disposal would be complied with. Alternatives C, F, G, H and J would comply with MTCA clean up
requiremcnts for industrial land use.
Alternatives C, F, G, H, and J would meet requirements for disposal of PCBs at chemical waste
landfills.
Alternatives C, F. G, Hand J would comply with the Southwest Air PoUution Control Agency's
(SW AJ'C,A) general standards for maximum air emissions.
Alternatives F and G would comply with thc state waste discharge program, since waste watcr
discharges would meet all effluent guidelines.
In summary, Alternative A would not meet ARARs and cannot be selected as the remedial alternative.
Altenlatives C, D, F, G, H, and J would comply with ARARs. Since Alternative A does not satisfy the
threshold criteria of protectivencss,it will not be further evaluated.
UocIl--IAoe
-------
10.2.2 Primary Balancin!~ Criteria
10.2.2. I Long-tenn Effectiveness
Alternative B, Institutional Controls, is more effective than the No Action alternative. Site restrictions
would minimize the potential for disturbance of contaminated soils and long-term monitoring would provide
information relating to changes in contaminant concentratioDS. This alternative will not represent aD
unacceptable cancer risk to the on-site worker.
. .
Alternative C, Excavation with Off-Site Disposal, has a high degree of long-term effectiveness and
permanence. This alternative eliminates the rislcs associated with contaminated soils by excav~ting and
transporting soils off site to a TSCA landfill. Residual rislcs to the on-site worker will not represent an
unacceptable cancer risk.
Alternative F, KPEG Dechlorination, has a comparable level of long-term effectiveness and
permanence to Alternative C. The riskS associated with contaminants are reduced by permanent degradation.
Residual risks to the on-site worker will not represent an unacceptable cancer risk.
Alternative G, Soil Wasbiilg, provides a lower level of long-term effectiveness and permanence than
Alternatives C and F. Alternative G requires the addition of institutional controls to manage the residual risks.
This is required because soil washing is not expected to reduce the COD~minant levels below industrial soil
clean up levels. Residual risks to the on-site worker will not represent an unacceptable cancer risk.
Alternative H, BES'fG, would provide long-term effectiveness and permanence comparable to
Alternatives C and F. Alternative H minimizes the rislcs associated with on-site con~mination through
removal and treatment of con~minSited soils. Residual risks to the on-site worker will not represent an
unacceptable cancer risk.
The long-term effectiveaess and permaneuce of Alternative J, Thermal Treatment with Off-Site
Disposal of Residuals, would be similar to that of Altematives C, F and H. Alternative 1 would minimize
the risks associated with contaminated soils through removal and incineration of contaminated material. If
necessary, the residual from the incinerator would be placed in a TSCA-approved landfill.
10.2.2.2 Reduction of Toxicity, Mobility, or Volume through Treatment
AItemative B, Institutioaal Controls, and Alternative C, .Excavation with Off-Site Disposal, would
not involve treatment of the coD18miDated materials, so DO reduction in mobility, toxicity, or volume would
be achieved using these alternatives.
Alternative F, KPEG Dechlorination, offers a level of reduction of mobility, toxicity, and volume
through treatment of on-site contaminaats. Since the contaminants are degraded to non-toxic compounds, this
alternative provides a higher level of mobility, toxicity, and volume reduction overall on site.
Alternative G, Soil Washing, offers a lower level of reduction of mobility, toxicity, and volume
through treatment than F. This alternative is DOt expected to achieve the cleanup standards, therefore
institutional controls must be implemented.
Alternative H, BEST, offers a level of mobility, toxicity, and volume reduction comparable to
Altematives C and F. The process generates a concentrated liquid containing the contaminants removed from
4ioc:.,.....Uoc
-------
the soil, which would be sent off site for incineration.
..
Alternative J, Thermal Treatment with Off-Site Disposal of Residuals, offers the same level of
mobility, toxicity, and volume reduction as Alternatives C, F and H. The contaminated soil is incinerated,
thus destroying the contaminants. The ash generated by thermal treatment would be SeDt to a RCRA landfill
for disposal.
10.2.2.3 Short-Term Effectiveness
Alternative B, Institutional Controls, is comparable to Alternative A and would not result in added
short-term risk. It would take approximately one week for installation of site restrictions and about three
months to implement deed restrictions and land-use restrictions.
Alternative C, Excavation with Off-Site Disposal, may involve short-term risk to on-site workers, the
community, and the environment from exposure to dust generated during the excavation of soil as compared
to Alternatives A and B. These risks can be effectively controlled using standard dust suppression methods,
personnel protective equipment and through the implementation of a health and safety plan. These risks will
be eliminated after the implementation of the alternative which is dependent on scheduling shutdowns of the
Ross Substation & Capacitor Yard. Each shutdown would last one week with four shutdowns required to
complete the excavation. This altcmative would take longer to implement than alternative A or B. Measures
to control risks would be in place prior to excavation. .
Altemative F, KPEG DechloriDation, presents a slighdy higher level of potential short-term risk than
Alternative C. due to banding of conUlm;..,.t"'" soil for treatment. Short-term risks can be effectively
minimized by the use of appropriate controls. but would be present until the full implementation of the
alternative. This alternative would take approximately 12 weeks longer than Alternative C. Measures to
control risks would be in place prior to excavation.
Altemative G, Soil Washing. presents a sligbdy higher level of potential risk as compared. to
Altemative F. Potential risk may be increased from exposure to dust during handling of soil
after treatment. Short-term risks can be effectively controlled. Short-term risk will be prescot until the
alternative is fully implemented. which will take 12 weeks longer than Alternative C. Measures to control
risks would be in place prior to excavation.
Altemative H, BESP Extraction. is comparable to Alternative F in short-term effectiveness.
Although there would be potential increased risks to the community, workers, and the environment during
excavation and treatment due to exposure to dust, these could be effectively controlled. Like KPEG, this
altemative takes approximately 12 weeks to complete soil treatment after excavation. Short-term risks will
be eliminated after complete implementation of the alternative. Measures to control risks would be in place
prior to excavation.
The sbort-term effectiveness of Alternative J, Thermal Treatment with Off-8ite Residual Disposal,
would be similar to that of Alternatives F and H. Potential increased risks to the community. workers, and
the environment during excavation and handling can be effectively controlled by using appropriate measures.
Risk associated with the treatment process would be minimal because incineration offers high destructioD rates
and is subject to stringent emission control standards. This alternative would take 18 weeks longer than
Alternative C to implement. Short-term risks would be completely removed after implementation. Measures
to control risks would be in place prior to the start of excavation.
_1/--1.'"
-------
10.2.2.4 Implementability
Alternative B is slightly difficult to implement due to the need for deed and land-use restrictions.
Alternative C is more difficult to implement than Alternative B. This waste unit is actively used for
power distribution and therefore, scheduling activities within this area is limited due to operational constraints.
BPA has excavated and disposed of contaminated soils from a number of similar sites. BPA has a trained
worle force, standardized procedures and the necessary equipment, readily available to implement this
alternative.
Alternative F is more difficult to implement than Alternative B. This alternative has 'the same
limitations as Alternative C, plus there is the nced for treatability studies.
Alternative G may be more difficult than Alternative F due to the nced for long-term institutional
controls. TheSe institutional controls are required to ~ the long-term risks, since this alternative is not
expected to achieve the cleanup standards.
Alternative H is comparable to Alternative F. Treatability studies would be necessary and advance
scheduling would be required to mobilize the BES'P proCessing equipment.
Alternative J, Thermal Treatment with Off-Site Disposal of Residuals, is more difficult to implemeDt
than Alternatives F and H. Advance scheduling of incineration equipment would be necessary and a test bum
mUst be conducted. Off-gas from the incinerator would require treatment or monitoring to ensure compliance
with air poUution standards.
10.2.2.5 Cost
The estimated cost of each soil cleanup alternative, based on the direct capital costs for remediating
1,196 cubic yards of contaminated material in the Ross Substation and Capacitor Yard fonows:
Alternative
Direct Capital
Cost
AltcrDative B - Iastitutional Controls
$0
AltcrDative C - Excavation with Off-Site Disposal
$447,380
Altcmative G - Soil Washing
SSS9,030
$48S ,580
AltcrDative F - KPEG Dechlorination
Altemative H - BEST Extraction
$650,180
Alternative J - Thermal Treatment with Off-Site
Disposal of Residuals
$812.630
Alternative B bas the lowest cost of all the other alternatives exclusive of the No Action alternative.
060c1/--1..-
-------
Costs for Alternatives C, F, G and Hare Comparable. Alternatives C and H includes long-term
institutional controls required for remediation to industrial cleanup levels.
Alternative J, Thennal Treatment with Off-Site Disposal of Residuals, has the highest overall cost.
.
10.2.3 Modifvinl!: Criteria
10.2.3.1 State Acceptance
The State concurs with the selected remedy and comments received from Ecology bave been
incorporated into this Record of Decision.
10.2.3.2 Community Acceptance
Based on the comments received during the public review period and at the public meeting, the public
accepts the proposed alternative.
10.3
CAPACITOR TESTING LAB
Target Contaminant: PCBs
10.3.1 Threshold Criteria
10.3.1.1 OveraU Protection of Human Health and the Environment
Alternative A, No Action, does not provide protection to human health or the environment since no
remedial activities would take place.
AIteruativc B, Institutional Controls, offers greater levels of protection as compared to Alternative
A. through site restrictiODS designed to prevent exposure to contaminants.
Alternative C, Excavation and Off-Site Disposal, offers a higher level of protection as compared to
A and B because contaminants are removed from the site.
Alternative F, KPEG DecbloriDation, offers a high level of overall protection of human health and
the environment, comparable to AItcmative C. The KPEG process permanently degrades PCBs and leaves
a treatment residual in the soil, but this residual, polyethylene glycol bipheynyl ether is considered to be Don-
toxic~
Alternative 0, Soil Washing, provides a lower level of protection of human health and the
environment than Alternatives C and F because Alternative G is not expected to achieve comparable reduction
in contaminant levels.
Alternative H, BEST, offers a level of overall protection comparable to Alternatives C and F.
Alternative J, Thermal Treatment with Off-Site Disposal of Residuals, offers the same level of overall
protection as Alternative C, F. and H. The process generates an ash that would be sent to a RCRA landfill
for disposal.
UcIl.-.lIAoc:
-------
10.3.1.2 Compliance with ARARs
There are no ARARs associated with Alternative A since no remedial action would be taken. ARARs
would not be met. Alternative B will comply with MTCA requirements to prevent contact; bowever, it does
not meet the cbemical specific ARARs identified for the site.
-.
All dangerous wastes and treatment residuals that are dangerous wastes would be properly
transported and disposed under Alternatives C, F, G, Hand J; therefore, ARARs associated with
transportation and disposal would be complied with. Alternatives C, F, G, Hand J would comply with
MTCA clean up requirements for residential land use.
Alternatives C, F, G. H, and J would meet requirements for disposal of PCBs at cbemical waste
landfills. Alternative J would meet requirements for PCB incineration units.
AltematiYes C, F, G. Hand J would comply with the Southwest Air Pollution Control Agency's
(SW APCA) general standards for maximum air emissions.
Alt.ematives F and G would comply with the state waste discharge .program, since waste water
discharges would meet all effluent guide1iDes.
Alternatives C, F, G, H, and J would comply with ARARs. Since Alternative A does not satisfy the
threshold criteria of protectiveness it will not be further evaluated.
10.3.2 Primarv Balancin2 Criteria
10.3.2.1 Long-term Effectiveness
Alternative B. Institutional Controls, is more effective than the No Action alternative. Site restrictionS
would minimi7.e the potential for disturbance of CODf1Iminllted soils and long-term monitoring would provide
information relating to changes in contaminant concentrations. Residual risks to the oD-site worker would not
represent an uoacceptable cancer risk.
Alternative C, Excavation with Off-Site Disposal. bas a high degree of long-term effectiveness and
permanence. 'Ibis altemative ~iminlltes the risks associated with contaQlinllted soils by excavating and
transporting soils off site to a TSCA landfill. . Residual risks to the on-site . worker would not represent an
uoacceptable cancer risk.
Alternativc F. KPEG DechloriDation, bas a comparable level of long-term effectiveness and
permanence to Alternative C. Residual risks to the oo-sit.e worker would not represent an unacceptable cancer
risk.
Alternative G, Soil Washing, provides a lower level of long-term effectiveness and permanence tban
Alternatives C and F. Alternative G requires the additiOD of institutional controls to manage the residual rislcs.
'Ibis is required because soil washing is Dot expected to reduce the contaminant levels below residential soil
clean up levels. Residual risks to the on-sit.e worker would not represent an unacceptable cancer risk.
Alternative H. BES"P, would provide long-term effectiveness and permanence comparable to
Alternatives C and F. Alternative H minimizes the risks associated with on-site contamination through
removal and treatment of contaminated soils. Residual risks to tbe on-sit.e worker would not represent an
Ucll--'t.-
-------
unacceptable cancer risk.
The long-term effectiveness and permanence of Alternative J, Thermal Treatment with Off-Site
Disposal of Residuals, would be similar to that of Alternatives C, F aod H. Alternative J would minimize
the risks associated with contaminated soils through removal and incineration of contaminated material. If
necessary,the residual from the incinerator would be placed in a TSCA-approved landfill.
10.3.2.2 Reduction of Toxicity, Mobility, or Volume through Treatment
Alternative B, Institutional Controls, and Alternative C, Excavation, would not involve treatment of
the contaminated materials, so no reduction in mobility, toxicity. or volume would be achieved using theSe
alternatives. .
Alternative F, KPEG Dechlorination, offers a level of reduction of mobility, toxicity. and volume
through treatment of on-site contaminants. Since the contaminants are degraded to nOD-toxic compounds, this
alternative provides a higher level of mobility, toxicity. and volume reduction overall on site.
Alternative G. Soil Washing, offers a lower level of reduction of mobility, toxicity, and volume
through treatment than F. This alternative is not eJtpccted to achieve the residential cleanup standards,
therefore institutional controls must be implemented.
Alternative H, BEST, offers a level of mobility, toxicity. and volume reduction comparable to
Alternatives C and F. The process generates a concentrated liquid containing the contaminants removed from
the soil. which would be sent off site for incineration.
Alternative J, Thermal Treatment with Off-Site Disposal of Residuals, offers the same level of
mobility. toxicity, and volume reduction as Alternatives C, F and H. The contaminated soil is incinerated,
thus destroying the contaminants. The ash generated by thermal treatmczt would be sent to a RCRA landfill
for~. .
10.3.2.3 Short-Term Effectiveness
Alternative B, Institutional Controls would not result in ad~ short-term risk. It would take
approximately one wcelc: for installation of site restrictions and about three months to implement deed
restrictions and laud-use restrictions.
Alternative C, Excavation with Off-Site Disposal. may invol~short-term risk to on-site workers. the
community. and the environment from eJtposure to dust generated during the eJtcavation of soil as compared
to Alternatives A and B. These risks can be effectively controlled using standard dust suppression methods.
personnel protective equipment and through the implementation of a healtb and safety plan. These risks will
be elimilUlltM after the implemcztation of the alternative. This altemative would take longer to implement than
alternative A or B. Measures to control risks would be in place prior to eJtcavation.
Alternative F. KPEG Dechlorination. presents a slightly higher level of potential short-term risk than
Alternative C, due to banding of COPplin.tM soil for treatment. Short-term risks can be effectively
minimized by tbe use of appropriate controls. but would be present until the fuU implementation of the
alternative. This alternative would take approximately 12 weeks longer than Alternative C. Measures to
control risks would be in place prior to eJtC8vation.
4ioc1l--'1...
-------
Alternative G, Soil Washing, presents a slightly higher level of potential risk as compared to
Alternative F. Potential risk may be increased during from exposure to dust during handling of soil
after treatment. Short-term risks can be effectively controlled. Short-term risk will be present until the
alternative is fully implemented, which will take 12 weeks longer than Alternative C. Measures to control
risks would be in place prior to excavation.
..
Alternative H, BES'P Extraction, is comparable to Alternative F in short-term effectiveness.
Although there would be potential increased risks to the community, worlc:ers, and the environment during,
excavation and treatment due to exposure to dust, these could be effectively controlled. Like KPEG, this
alternative takes approximately 12 weeks to complete soil treatment after excavation. Short-term risks will
be eliminated after complete implementation of the alternative. Measures to control risks would be in place
prior to excavation. '
The short-term effectiveness of Altenaative J, Thermal Treatment with Off-Site Residual Disposal,
would be similar to that of Alternatives F and H. Potential increased risks to the community, worlc:ers, and
the environment during excavation and handling can be effectively controlled by using appropriate measures.
Risk associated with the treatment process would be minimal because incineration offers high destruction rates
and is subject to stringent emission control standards. This alternative would take 18 weeks longer than
Alternative C to implement. Short-term risks would be completely removed after implementation. Measures
to control risks would be in place prior to the start of excavation.
10.3.2.4 Implemeotability
Alternative B would be not be difficult to implement.
Alternative C is more difficult to implement than Alternative B. This waste unit is actively used for
pnwer distribution and therefore, scheduling activities within this area is limited due to operational constraints.
BPA has excavated and disposed of coutJaminat..n soils from a number of similar sites. BPA bas a trained
work force, standardized procedures and the necessary equipment readily available to implement this
alternative.
Alternative F is more difficult to implement than Alternative B. This alternative has th'e same
, limitations as Alternative C, plus there is the need for treatability studies.
Alternative G may be more difficult than Alternative F due to the need for long-term institutional
controls. These institutional controls are required to manage the long-term risks, since this alternative is not
expected to achieve the resideotial cleanup standards.
Alternative H is comparable to Alternative F. Treatability studies would be necessary and advance
scheduliDg would be required to mobilize the B~ processing equipment. '
Alternative J, Thermal Treatment with Off-Site Disposal of Residuals, is more difficult to implement
than Alternatives F and H. Advaaec schedu1ing of incineration equipment would be necessary and a test bum
must be conducted. Off-gas from the incinerator would require treatment or monitoring to ensure compliance
with air pollution standards.
10.3.2.5 Cost
The estimated cost of each soil cleanup alternative, based on the present worth of the initial capital
"''--''1-- '
-------
cost and the long-tenn operating and maintenance. costs for remediating 68 cubic yards of contaminated
material in the Capacitor Testing Lab follows:
Alternative
Direct
Capital Cost
$2,800
$35,560
$108,050
$70,120
$95,900
$100,300
Alternative B - Institutional Controls
Alternative C - Excavation with Off-Site Disposal
Alternative F - KPEG Dechlorination
Alternative G - Soil Washing
Alternative H - BEST Extraction
Alternative J - Thermal Treatment with Off-Site
Disposal of Residuals
Alternative B has the lowest cost of all the other alternatives.
. Costs for Alternatives C, F, G and H are comparable. Alternatives C and H includes long-term
institutional controls required for remediation to industrial cleanup levels.
Alternative J, Thermal Treatment with Off-Site DispoSal of Residuals, has the highest overall cost.
10.3.3 ModifyinS! Criteria
10.3.3.1 State Acceptance
The State concurs with the selected remedy and comments received from Ecology bave been
incorporated into this Record of Decision.
10.3.3.2 Community Accc:ptaDce
Based on the comments received during the public review period and at the public meeting, the public
accepts the proposed alternative.
11.0 SELECTED REMEDY
11.1 KEY ELEMENTS OF SELECTED REMEDY FOR WOOD POLE STORAGE AREA EAST
Based upon consideration of the requirements of CERCLA, the detailed analysis of the alternatives
using the Dine criteria, and public comments, the most appropriate remedy for the Wood Pole Storage Area
East is AIteruative I, Ex-Situ Solid-Phase Bioremcdiation with cohancements. The contAminants of concern
in the Wood Pole Storage Area East arc HPAHs and ~.bloropheool. Tbe soil cleanup levels for these
compounds are 1 ppm and 8 ppm, respectively. The estimated volume of contamination is 3,700 cubic yards.
This alternative is preferred because it best achieves the goals of the evaluation criteria in comparison
to other alternatives. This alternative was selected because it employs an innovative technology. It provides
..11.-...1.-
-------
on-site t: :Zlent with permanent reduction in the toxicity, mobility and volume ~f the soil contamination and
reduces contaminants to levels that are protective of human health and the environment.
""1'''''1--
The selected remedy would be implemented as follows:
.,
A treatability study would be performed on samples of contaminated soil to design the
treatment regimen and refine treatment time estimates. The treatability study needs to
determine the treatment cell size, depth, microbes and oxygen concentrations. Area required
will depend on the DUmber of lifts of treatment which is directly related to the time required
to complete remediation as determined by the treatability studies.
.
Contaminated soil is excavated and placed in an aboveground treatment cell.
.
If a biotreatment cell is coDSttUcted. it would consist of an earthen benned area lined with
- polyethylene and layered with six inches of sand. Runon controls will consist of berms to
divert water around rather than through the treatment cell. Runoff controls will consist of
berms to divert water to one or more sumps. Water is collected in these sumps and pumped
to a nearby storage taDk. Water in the tank will be reapplied to the soil treatment area as
required to maintain soil moisture content within prescribed limits. . It may be treated and
discharged to the sanitary sewer, pending permits.
.
Soils which exceed the residential soil clean up standard for total carcinogenic HPAH of 1.0
mg/kg (MTCA Method A) or for pentachlorophenol of 8 mglkg (MTCA Method B) will be
excavated and treated.
.
The soil is treated with nutrients, and any necessary additives as determined by the
treatability studies. A leachate system is used to irrigate the soil in the treatment cell.
Oxygen required to maintain aerobic conditions can be supplied by adding hydrogen
peroxide to the irrigation water, through forced air piping, or by tilling the soil. To further
ensure that the contamiDants arc reduced to the lowest possible levels, an etbanoUwatcr
solution will be used to enhance bioremediation of organic compounds in the soil. The
ethanol solution is used to eusu1'e the release of organic chemical from the soil to provide a
nutrient source for the microorganisms. In addition to this enhancement, ultraviolet lights
will be used to aid in the degradation of the organic compounds of concern. Wave lengths
have been chosen to provide the maximum degradation potential for the chemicals.
.
Soil samples arc collected from the treatment cell for chemical and biological monitoring of
soil conditions in accordance with the treatmeot and monitoring schedule.
.
Confirmatory soil sampling of the excavation is performed to ensure that all soil which
exceeds resideotial soil clean up levels has been removed.
.
After the remediation is complete the treatment cell will be dismantled and scrapped. If aftcc
treatment the chemical residual levels in the soil exceed the primary cleanup goal of 1 ppm
(HPAHs) and 8 ppm (pentacblorophenol), the soil will be returned to the storage yard and
a determination will be made as to which type of cap should be implemented to contain the
remaining contNDinatioD as shown in Table 7.
-------
.
Table 7
Preferred Altemative Tier
Wood Pole Storage Area East
Operable Unit A ROD
8PA Ross Complex
PrImary Cleanup Goal ,
Prefetred Alternative tier Capital Cost
HPAH PCP
fief 1: Enhanced Bioremec:liotion 1ppm 8ppm S45Q.ooJ
TIer 2: Enchanced Bioremediotion with
nstalation of Gravel Barrier on Soil 1-23ppm 8-126ppm $482.120 to S586.5202
and nstitlltional Controls
fief 3: Enc:hanCed Bioremediation with
CAP lnstaGation on Soil and > 23 ppm > 126ppm $S 10.520 to S870.520 a
nstitutional Controls
'- The dearAJP level for HPAHs. 1 ppm. is the remedial action objective and 23 ppm is the Ix10-4ris1c
level for the Gn-$ite worker. The dean up level for PCP. 8 ppm. is the remedial action objective
and 126 ppm represents a 1 x 10-4ris1c level for the on-Ste worker.
2 - Cast range is based on a six inch gravel cap covemg 1ar. to 100'1. of the Wood Pole Storage Alea and $20.520
for instiMional controls.
a - Cast range is based on a foU' nch asphalt cop covering ;ar. to 100'1. of the Woad Pole Storage Alea and
$20.520 for institutional controls.
Jet> No. 06737.oi2415
-------
Laboratory testing will be undertaken throughout the course of the bioremediation project to monitor
contaminant levels in the treated soils. Progress of enhanced bio"remediation toward the targeted remediation
goals will be assessed at the end of the first summer session (approximately four months). If after four
months, contaminant concentrations are continuing to exhibit a reduction in concentration, bioremediation will
continue. However, if contaminant concentrations over time represent static conditions which suggest a
treatability limitation, a determination will be made to select a tiered preferred alternative as shOWD in Table
10. The tiered alternatives are based on the technical ability of bioremediation to achieve the soil cleanup
levels of I ppm for HPAH and 8 ppm for PCP. The rationale for the tiered approach allows for flexibility
in using an innovative treatment technology succeeded by optional altcmatives to achieve the soil cleanup
standards that will be protective of human health and the environment and be cost-effective. If the Tier I
cleanup levels can not be achieved using enhanced bioremediation, then either Tier 2 or Tier 3 will ~ selected
as the optional preferred alternative. The selection of either Tier 2 or 3 will be based on the achievable soil
cleanup levels for HPAHs and PCBs. Tier 2 involves the installation of a gravel barrier on the soil with
institutional controls. Tier 3 involves the installation of an asphalt cap with institutional controls. Table 10
presents the capital costs related to eacb tier.
11.2 KEY ELEMENTS OF SELECTED REMEDY FOR ROSS SUBSTATION & CAPACITOR YARD
Based upon consideration of the reqUirements of CERCLA, the detailed analysis of the aIterDatives
using the nine criteria, and public comments, the selected remedy for the Ross Substation & Capacitor Yard
is Alternative C, Excavation with Off-Site Disposal. The compound of concern iIi. the Ross Substation and
Capacitor Yard soils is PCBs and the industrial soil clean up level is 10 ppm. The estimated volume of
contamination is 1,196 cubic yards.
This alternative is preferred because it best meets the evaluation criteria as compared to the other
alternatives. It can be readily implemented and is protective of bum an health and the environment. The risks
posed by the contaminated soil would be addressed by removal of the soil from the Site.
The selected remedy would be implemented as follows:
.
The Ross Substation & Capacitor Yard is scheduled for sequenced shutdowns in sections, to
facilitate ongoing power distribution.
.
Contaminated soil is excavated, tested and hauled to a TSCA-approved landfill.
.
Soil sampling and testing is performed in each excavation to confirm that the cleanup
standards have been achieved. Clean fill will then be placed in the excavation.
.
Because the area is fenced and isolated from any nearby residential areas and likely to remain
an industrial site, cleanup will be to industrial standards. In accordance with MTCA Method
A requirements for industrial areas, fencing and deed restrictiODS will be maintained after
cleanup.
11.3 KEY ELEMENTS OF .SELECTED REMEDY FOR THE CAPACITOR TESTING LAB
Based upon consideration of the requirements of CERCLA, the detailed analysis "f the alternatives
using the nine criteria and public comments, the selected remedy for the Capacitor Testing Lab is Alternative
C, Excavation with Off-Site Disposal. The compound of concern in the Capacitor Testing Lab is PCBs and
the soil cleanup level is I ppm. The estimated volume of contaminated soil is 68 cubic yards.
_"""'" .4oc
-------
This alternative is preferred because it best'meets the evaluation criteria as compared to the other
alternatives. (t can be readily implemented and is protective of human health and tbe environment. The risks
posed by the contaminated soil would be addressed by removal of the soil from the Site.
The selected remedy would be implemented as follows:
.
Contaminated soil is excavated, tested and hauled to a TSGA-approved landfill. Tbe
estimated volume of soil to be removed was 68 cubic yards.
.
Soil sampling and testing is performed in each excavation to confirm that the cleanup
standards have been achieved. Clean fill will then be placed in the excavation.
.
Cleanup of PCB contaminated soils will be to residential standards.
12.0 STATUTORY DETERMINATION
BPA and EPA's primary rcspoosibility under CERCLA. is to eosure that the selected remedy will
protect human bealth and the eovUoament. Additiooally, Section 121 of CERCLA, as ameoded by SARA,
establishes several other stalUtory requirements and preferences. These specify that, whco complete, the
selected remedy must comply with applicable and relevant or appropriate covironmcotal standards established
under federal and state eoviroamentallaws unless a waiver is justified.
The selected remedy must also be cost-effective and utilize permanent solutions and alternative
treatment tecboologies or resource recovery technologies to the maximum extent practicable. Tbe remedy
should reprcscnt the best balance oftradeoffs among the alternatives with respect to pertinent criteria. Fmally,
the statute includes a prefetcoce for remedies that employ treatment that permanently and significantly reduce
the volume, toxicity, or mobility of hazardous wastes as their principal elemenL
The selected remedies for the contaminated soil at the Wood Pole Storage kea East and the Ross
Substation and Capacitor Yard and the Capacitor Testing Lab meet the statutory requirements.
12.1 PROTECTION OF HUMAN HEALTIi AND THE ENVIRONMENT
The selected remedy will. protect hUIDaD health and the environmcot through removing contaminants
from the site and destroying CODhlnift"ftt~ until the remaioiog levels aie protcc:tive of human health and the
enviroamcot. PCBs in soils Will be removed from the Ross Substation and Capacitor Yard and disposed off-
site. Contaminants, HPAHs and peotacblorophenol. in the Wood Pole Storage Area East will be degraded
through a bioremediationprocess. Engineering controls will be utiliz.cd during excavation and bioremediation
to eliminate the potcotial for exposure to dust. Sampling and analysis win be conducted foUowiDg excavation
and duriDg the bioremediation process to eosure that contaminant levels arc either removed or are below levels
that are protedive of human health ud the environment. There win be no adv~ effects on buman bealth
and the environmcot caused by coostruction and implementation of the selected remedies.
12.2 COMPUANCE wrm ARARs
The selected remedy of excavation and off-site disposal in the Ross Substatioo and Capacitor Yard
and the Capacitor Testing Lab and bioremediation in the Wood Pole Storage Area East will comply with the
4ioc1l"""""
-------
ARARs presented in the following list.
.
Requirements of Washington Model Toxies Control Act (Initiative 97) for clean up of hazardous waste
sites, Chapter 70.105 RCW, as codific:d in Chapter 173-340 WAC.
.
General emission standards under WAC 173-«X>-040 for visible emissions, fugitive emissions and
emissions of air contaminants which are detrimental to persons or property;
-.
.
Ambient source impact levels established under WAC 173-460-070 for new sources of toxic air
pollutants, including sites subject to the Model Toxics Control Act;
.
Performance requirements under WAC 173-460-040, WAC 173-460-060 and Section 400-100 of the
General Regulations for Air Pollution Sources of the Southwest Air Pollution Control Authority.
.
Federal bazardous waste transportation regulations, Title 49 CFR Parts 171 and 172.
12.2.4 Other Criteria Advisories or Guidance To-Be-Considered
BC
PCB cleanup levels are consistent with 40 CFR Part 761, Subpart G. Spill Cleanup Policy Rule. In
addition, off-site disposal of contaminated soil will be at a chemical waste landfill operating in accordance with
40 CFR Part 761 Subpart D (which is not an ARAR because it is oot ol1-site)~ and in accordance with the
revised Procedures for Planning and Implementing Off-Site Response Actions. OSWER Directive 9834.11.
November' 13, 1987,9834.118, January 4. 1988. No other criteria, advisory, o.r guidance are considered
necessary for implerDeotation of the selected remedy.
12.3 cosr EFFECTIVENESS
The selected remedies are the most cost effective alternative because they protect human health. and
the eovironment, attain ARARs, aud meet the objectives established for the remcdia1 action in a way that is
proportional to their costs.
The selected remedy for the Woodpole Storage Area East was in the same cost range as the other
alternatives evaluated; however, the remedy selected is the .most compatible alternative with BPA's future land
use of this area and the innovative treatment technology is expected to be implcmeotable.
The remedy for the Ross Substation and Capacitor Yard and the Capacitor Testing lAb is readily
implcmeotable at a lowei' cost than any other options and provides protection to human health and the
environmCl1t.
12.4 UTILiZATION OF pERMANENT SOLtmONS AND ALTERNATIVE TREATMENT
TECHNOLOGIES
The selected remedy rcpreseots the maximum extent to which permanent solutions and treatment
tA:d1oologies can be utilized in a cost-effective man.nec at the BPA Ross Complex. The selected remedy
provides the best \)!aIAIIN! of tradeoffs in tenDS of long-term effectiveness and permancoce, reduction in
toxicity, mobility. volume achieved through treatment, short-term effcctiveoess, , and cost. The remedy in
the Wood Pole Storage Area East employs an alternative treatment technology that will result in a permanent
remedy.
_II"""'''''
-------
12.5 PREFERENCE FOR TREATMENT AS PRINCIPAL ELEMENT
..
The Ex-Situ Solid Phase Bioremediation satisfies the statutory preference for treatment that
pennanently and significantly reduces the toxicity, mobility, and volume of hazardous substances.
Contaminants will be destroyed to the maximum extent practicable.
13.0 DOCUMENTATION OF SIGNIFICANT CHANGES
There are three significant changes pertaining to OUA since the Proposed Plan was released, for public
comment in August, 1992:
(1) Tbe Proposed Plan identified the need for remedial action under CERCLA at the Wood Pole
Storage Area East and at the Ross Substation and Capacitor Yard. However, it was clearly stated that the
Washington Bepartment of Ecology disagreed with EPA's position and supported the need for remedial action
at the Capacitor Testing Lab as well. It was also stated that BPA had agreed to pursue soil cleanup as a
removal action at the Capacitor Testing Lab as described in the Feasibility Study.
Since the release of the Proposed plan, EPA has reevaluated the data and the risk assessment for the
Capacitor Testing Lab. EPA has concluded that there is not a sufficient difference between the risks at the
Ross Substation and Capacitor Yard and the Capacitor Testing Lab to warrant action at one area and not the
other. Therefore, EPA has agreed to include the Capacitor Testing Lab for remedial action under CERCLA
as part of the OUA ROD.
Although the alternatives for remedial action at the Capacitor Testing Lab were not presented in the
Proposed Plan, the Capacitor Testing Lab was evaluated as part of the Feasibility Study. Thus, the detailed
analysis of altematives and cost comparisons have been available for public review and are a part of the
Administrative Record. The contaminant of concern, cleanup standards and remedial action for this area are
identical to the Ross Substation and Capacitor Yard. The Capacitor Testing Lab has been part of the RllFS
process and selection of a remedial action for this waste area is considered a logical outgrowth of the
information already available to the public. Therefore, EP A determined that the Proposed Plan did not have
to be amended because it is consistent with the type of remediation that has been presented for public
comment.
(2) The Proposed Plan specified bioremediation as the preferred treatment aItemative for the Wood
Pole Storage Area East. BPA has determined that 8eobal1Cl!'.ld bioremediation8 which utilizes geochemical
enhancements (UV light and chemical oxidizer's) in addition to conventional microbial activity would have a
greater' assurance of achieving the cleanup standards. In addition, the overall estimated cost of the enhanced
bioremediation is less than balf the cost that was estimated in the Proposed Plan. The selected remedy
includes a contingency that provides for alternative clean up levels if the clean up standards cannot be
achieved. If that is the case, after treatmcnt is completed, the remedy includes on-site disposal with capping.
Depending on the level of contamination remaining in soils, one of the two types of caps specified in Section
10 will be implemented.
(3) The Proposed Plan specified the volumc of conbamination in the Ross Substation and Capacitor
Yard as 4,900 cubic yards. This volumc was overestimated and the correct volume is 1,196 cubic yards.
_11.-..1-
-------
.
.
ATTACHMENT I
-------
.
RESPONSIVENESS SUMMARY
OPERABLE UNIT A
BONNEVILLE POWER ADMINISTRATION
ROSS COMPLEX
,"
This responsiveness summary addresses the questions and comments received by the Bonneville Power
Administration concerning the Proposed Plan related to soil remediation for Operable Unit A at the Ross
Complex located in Vaocouvcc, Washington. The Site was listed on the National Priorities List (NPL) in
November 198? based on the presence ofvolatiJe organics compounds in groundwater and the Site's proximity
to the City of Vancouver's drinking water supply. As a results of the listing BPA, pursuant to a Fedcca1
Facility Agreement signed by BPA, EPA, and the Washington Department of Ecology (Ecology) on May I,
1990, BPA conducted a Remedial InvestigationlFeasibility Study (RI/FS) to determine the nature and extent
of contamination at the site and to evaluate alternatives for the clean up of con~min"ted areas.
On May I, 1991, a community relations plan (CRP) was prepared by BPA's Community Relations
Group in accordance with CERCLA, as amended by SARA. The CRP included establishing information
repositories and communication pathways to disseminate information, Information repositories are located
at both the Ross Complex and in the Vancouver Regional Library, 1007 East Mill Plane Boulevard,
Vancouver, Washington 98663.
An administrative record was established to provide the basis for selection of the remedial action in
accordance with section 113 of CERCLA. The administrative record is available for public review at the Ross
Complex or the Vancouver Regional Library. During the RIfFS, BPA issued a press release and five
additional fact sheets. The chronology of the community relations is listed below.
. May 22, 1990
. July 1990
. March 1991
. May 1991
. August 1991
. May 1992
A scoping meeting was held to provide information to the public and hear concerns
about environmental conditions at the site.
Fact sheet No.4 described the results of the May scoping meeting.
Fact sheet No.5 described chronology of events and the work plan for the RIIFS.
Fact sheet No.6 described the RI and FS programs and current site work.
Fact sheet No.7 described status of the RI field work,
Fact sheet No.8 defined Opemble Units A and B, discussed OUA Rl and risk
assessment findings, and activities planned for the summer of 1992.
-------
The public was given the opportunity to participate in the remedy selection process in accordance with
sections 117 and 1 I 3 (1<) (2) (B) of CERCLA. The proposed plan for Operable Unit A, which summarized the
alternatives evaluated and presented the preferred alternative, was mailed to approximately 800 interested
parties on August 14, 1992. BPA provided public notice through a display ad in the Columbian and
Oregonian on August 24, 1992 to explain the proposed plan, list the public comment period, and announce
the public m~ng. Press coverage was also provided in the local news media which resulted in a news article
of August 20, 1992.
.
,
A 30-day public comment period was held from August 14 to September 14, 1992. Approximately
20 people attended a public meeting, which was held on September 2,1992 at the Ross Complex, DOB
Auditorium. The public comment period was held from August 14 through Septemger' 14, 1992. BPA held
a public meeting on Wednesday, September 2, 1992 to explain the recommended cleanup plan and solicit
public commoots. Four written comments were received during the comment period. Copies of the
transcripts for the public meetings and comment letters received are provided in the Administrative Record.
A summary of the comments received followed by BPA's respoose follows.
Groundwater concerns that were expressed during the public comment period on the Proposed Plan
for the cleanup of contaminated soils at the site will be addressed in the separate Record of Decision that
documents the cleanup decision for the contaminated groundwater at the site. A Proposed Plan for Operable
Unit B, which describes Site groundwater concerns, will be available for public review in June 1993 and the
Record of Decision is scheduled for release in August 1993.
1.
It is imperative that the public know what goes on at the facility and that the remedies select~
will be safe and Will be implemented in a timely manner.
Response:
Since 1985 BPA bas endeavored to keep the public informed about events related to the
hazardous waste investigation at Ross. We have done this by working with the media and
through a series of written notices, information sheets, and public meetings. We will
continue to look for ways to improve communication with our public.
As stated at the public meeting, we have not been able to identify any off-site risks due to
contaminant migration. The remedies now being proposed are directed at on-site risks. These
actions are designed to ensure that there will be nO off-site rislcs in the future and that even
on-site risks win be eliminated. Bonneville recognizes that it needs to deliberate in
undetta1ciilg these actions while moving ahead without undue delay.
The implementation of the remedy in the Ross Substation and Capacitor Yard is scheduled
for fiscal year 1995. At this time, PCB equipment will be replaced and the PCB
contamioated soil will be removed. The remedy for the Capacitor Testing Lab will be
conducted concurrently with the remedy in the Ross Substation and Capacitor Yard.
Planning for implementation of the remedy in the Wood Pole Storage Area East is currently
_11--1.'"
-------
.
.'"
2.
Response:
3.
Response:
4.
Response:
_1'--11.-
underway. The length of time to complete bioremediation is dependent on biological
reactions. It cannot be accurately predicted although a treatment period of one to two years
is anticipated.
The public want to ensure that the clean-up process is not a temporary solution and that the
problem is really resolved.
As outlined in the proposed plan, in selecting a specific cleanup tccImology, we are required
to consider a number of criteria. Among other things, we must evaluate the short-term
effectiveness, long-term effectiveness, as weD as overall reduction in mobility, toxicity, and
volume of waste through treatment. Long-term effectiveness was a critical component in the
evaluation for the selection of a remedy. The alternatives selected ~ intended to ensure that
the solutions applied provide a penD8DCIJt remedy.
Institutional Controls appears to be the logical choice for containment. It does not disturb the
soil and cause it to be air-bome, the cost is reasonable, and it is unlikely the land be open to a
great deal of public use.
Institutional Controls includes measures to limit or prohibit activities that may interfere with
or disturb contaminated areas. We recognize that the cost for institutional control is
reasonable; however, the use of this alternative W9uld not allow BPA to have unrestricted
access for incorporation of these areas into the long term planning and development process
for the Ross Complex. Therefore, Alternatives I and C, were selected for the Wood Pole
Storage Area East, Ross Substation and Capacitor Yard and Capacitor Testing Lab based on
best the balance of trade offs resUlting from the comparative analysis of alternatives and
when implemented will allow BPA unrestricted use of these areas.
The contaminants do not appear to be a problem. The foUowing alternatives are preferred: 1)
no action 2) institutional control, and 3) certainly nothing more costly than the Table 3 preferred
altematives.
The preferred alternatives for the Wood Pole Storage Area and the Ross Substation and
Capacitor Yard and associated costs presented in Table 3 were selected based on the best
balance oftradeoffs among the alternatives evaluated including costs. The remedies selected
accommodates regulatory treatment preferences and includes the eval~tions of criteria such
as effectiveness, implementability, and cost. The cost estimates have been refined since
issuances of the Proposed Piau and they are significantly lower. BPA, therefore believes it
makes sense to remove these known levels of contamination.
-------
5.
A concern related to all contaminants at Ross and many other areas of our community exists.
Removal of all contaminants from the site is advocated.
.
Response:
BPA, in worlcing with EPA and the state, has utilized a risk-based clean up approach. Whee
warranted this approach requires the removal of contaminants. In other situations,
contaminants may be contained for the prevention of further migration. Tbe interaction of
these two approaches achieves the clean up requirements of EP A and the state which are
protective ofhumao health and the environment. Historical contamination is being addressed
by the selected remedies. Tbese remediations coupled with changes in the handling and
storage practices which caused the contamination, discontinuing the use of certain hazardous
compounds, and the development of new waste handling facility, ~II when taken together,
represent the best way of reducing the potential for future contamination issues.
.
. .
_"--1.-
-------
,
.'"
A TIACHMENT II
ADMINISTRATIVE RECORD LISTING
-------
ATTACHMENT II
Administrative Record List
TitletT . Dote Po es Author lOr nization
,'.,',',',",'.'.',',',',',",',',",',','.','.',','.',",'.',',',',',',',',',',',',',",', ',',',','.,',',",',',', -,',','.-.','.',',',',-,-,','.'.','.'.'.-,','.'.'.'.",'.'.','.'.',','.','.',','.',',',',',','
SITE IDENTIFICATION
.. Background (Suspect Contamination) 7/1/89 15 USEPA
NFL Listing/Site Inspection 9/14/88 21 US EPA
.d Preliminary Assessment Report 4/1/86 50 BPA
Site Investigation (SI) Report 7/1/88 VI/II/III Pacific NW Lab. Richland
REMEDIAL INVESTIGATION (RI)
Work Plan (RIfFS Study) VOl I 6/1/91 Domes & Moore
Work Plan (RI/FS Study) VOl II 6/1/91 Domes &. Moore
RI Work Plan Modification 8/1/91 7 Anthony Morrell. BPA
RI Operable Unit A Vol 1 5/15/92 Dames & Moore
RI Operable Unit A Vol 2 5/15/92 Dames & Moore
RI (Unit A) Appendices Volume 1 5/15/92 Domes & Moore
RI (Unit A) Appendices Volume 2 5/15/92 Domes & Moore
RI (Unit A) Appendices Volume 3 5/15/92 Domes & Moore
RI (Unit A) Appendices Volume 4 5/15/92 . Domes & Moore
RI (Unit A) Appendices Volume 5 5/15/92 Dames & Moore
RI (Unit A) Appendices Volume 6 5/15/92 Dames & Moore
RI (Unit A) Appendices Volume 7 5/15/92 Dames & Moore
RI (Unit A) Appendices Volume 8 5115/92 Dames & Moore
FEASI81UTY STUDY
Feasibility Study Operable Unit A 7122/92 200 Dames & Moore
Proposed Plan 8/11/92 13 BPA. EPA. Ecology
Ltr proposing enhanced bioremed. I 2/12/93 4 Anthony Morrell. BPA
ltr agree to enhanced bioremed. 2/19193 2 Nancy Hamey. U.s. EPA
ltr agree to enhanced bioremed. 2122/93 2 Chris Poindexter. Ecology
RECORD OF DECISION
REMEDIATION I
Removal Action Closure Report 8124/92 Dames & Moore
COORDINATION
Federal Faci6ties Agreement 3/1 /90 60 BPA. EPA. Ecology
Transmit Site Inspection Report 8/8/89 1 Gloria Lenz. SPA
EPA's position re fieldwork act 6/15/90 1 Nancy Harney. U.s. EPA
BPA Commence Fteldwork 5/2/91 1 Nancy Homey. U.s. EPA
Transmits RI Report Operable Unit A 5/15/92 1 Anthony Morrell. BPA
EPA's Comments on Anal RI 6/9/92 5 Nancy Homey. U.s. EPA
EPA's Accept RI Operable Unit A 6/23/92 1 Nancy Homey. U.s. EPA
Transmit Pre6minay Assessment 7/11/86 1 Stephen Sander. SPA
Transmit SIte Inspection Report 8/8/89 1 Gloria lenz. SPA
Accepts RI/FS Work Plan 8/21/91 1 Chris Poindexter. Ecology
Request to Revise schedute 11/1/91 4 Anthony Morrell. SPA
Response to Concerned Citizen 2/3192 2 Chris Poindexter. Ecology
Transmits RI Report Operable Unit A 5/15/92 1 Anthony Morrell. BPA .
FFA Resolution of Disputes Alternate 611/92 1 Chris Poindexter. Ecology
Extension for Draft ROD 7/24/92 1 Chris Poindexter. Ecology
-------
ATTACHMENT II
Administrative Record list
title IT e Dote Po es Author lOr onization
.. ,",",,'.,",".',. .'.",".','.'.'.'.'.",".",',"."," ,'."."."."..".,'.".',".'.' ,".'.".".".".'.'.".",-.-,",',-.-.'.'.-.".'.-.".-.".'.'.".'.'.',".'.'.".'.'.'.'.".",'.".'.",",".".','.",",',' "
HEALTH ASSESSMENTS
ATSDR Ltr enc lAG. schedule visit 2/28/92 33 Luther DeWeese ATSDR
,".
PUBLIC PARTICIPATION
MemolCommunity Relations Plan 9130/88 7 Asst to Adm. Environment
Community Relations Plan 5/1/90 8 BPA
Ross Community Contact list 11/30/89 5 BPA
Notice of 5/22/90 meeting 4/27190 2 George Gwinnutt. Area M!
Ross Community Contact list 5/12/92 3 BPA
Official Comment Log Close 5/31/90 5/31/90 11 Comments 1-6
Ltr enclosing 5/22/90 question respons 7/12/90 1 John Straub. BPA
Ltr re Superfund Site infonnation 11/16/90 1 John Straub. BPA
Ltr re Superfund Site Activities 3/27191 1 John Straub. BPA
Ltr re Superfund Site Activities Update 5/21/91 1 John Straub. BPA
Ross Complex Dev Guide Info 3/1192 2 BPA
Lte re waste handlinglsite cleanup 4/13/92 2 Dave Dunahay. BPA
Ltr review proposed plan & public mtg 8/11/92 1 Dave Dunahay. BPA
Public Comment Log 9/14/92 5 Interested Neighbors
SPA Notice of Intent (RIfFS) 4/27190 2 Federal Registrar eelS)
Ross Complex Cleanup 5/17/90 1 The Columbian
Ross Complex Looks to Future Jan-92 3 BPA
SPA Announces AR Avail Ubrary , 6/1/92 1 The Oregonian
SPA Announces AR Avail Ubrary 6/1/92 1 The Columbian
SPA Announces AR Avail Ubrary 6/15/92 1 The Columbian
SPA Announces AR Avail Ubrary 6115/92 1 The Oregonian
SPA's Superfund Proposal 8/24/92 1 The Columbian
SPA's Superfund Proposal 8/24/92 1 The Oregonian
Wlthc::' :;wal of NOI to Prepare EIS I 12/4/92 1 Federal Registrar (8S)
EPA Releases BPA Superfund Shedule 7/8/90 1 EPA
SPA Site to be tested for hazards 9/30/84 1 The Columbian
Toxic contamination suspect BPA Sub 7/8/86 1 The Oregonian
Chemical tests to begin on BPA Site 719186 1 The Oregonian
Ross tests trigger S 1.5 million study 1019188 . 1 The Oregonian
EPA stresses three sites for cleanup I 7/14/89 1 Seattle PI
EPA plans to track pollutants 7/14/89 1 The Columbian
Seattle firm to test Bonneville pollution 10122/89 1 The Oregonian
EPA adds BPA site to waste list 11/16/89 1 The Oregonian
Ross contamination still unclear 5/23/90 1 The Columbian
BPA plan will affect site near Hazel Dell 4/19/90 1 The Oregonian
BPA seeles comment on cleanup 8/20/92 1 The Oregonian
Ross Complex takes next step 8/20/92 1 The Columbian
Fact Sheet-Ross Needs a Cleanup 4/1/90 2 BPA
Fact Sheet-CERCLA Process 5/1/90 2 BPA
Fact Shet-Inspection Summary 5/1/90 4 BPA
Fact Sheet-May 22 Meet Q&A 7/1/90 4 BPA
Fact Sheet-What's Happening 3/1191 1 BPA
Fact Sheet-Studies Begin 5/1191 2 BPA
FactShee~UpdCrte 8/1/91 1 BPA
Fact Sheet-What's Happening May-92 2 BPA
-------
ATTACHMENT II
Administrative Pecord List
II.
Title/T e
.,.",-"."-.,.,...-.."",...,.,.,..-.,.,,,...,...-.""".,',"""""'0"""""""""""""'"
TECHNICAL SOURCES
Summary of CERCLA
History & Statute
EPA Final Rule (Fed Register)
Technical Assistance Grant Update
EPA Guidance for RIIFS Baseline
CERCLA Requirements
...
Dote Po es Author lOr onizotion
"""".",."",.",.-.",,-,',- ,',',',',',',',", """,-.,.."",.".,.-.",,',",',"','.'.'.',',.,.,',',',
1986
11/28/86
318/90
211190
2121190
10/6/89
..-".".,-.""".,..,...,.,....,.-.-......,..-.-,'.'...-.".""",."-"".",."".,.,,,."..'.'.'.',',','.',',',',',','
.
p...~ AOREa«IOJCLSJ
"-3
,",'.'.'.','.'.',',".'
30
70
55
1
25
1
(Index and CERCLA Act)
EPA Region X
Nancy Horney. U.S. EPA
U.S. Dept. of Energy
-------