PB95-963132 EPA/ESD/R10-94/104 March 1995 EPA Superfund Explanation of Significant Difference for the Record of Decision: Bangor Naval Submarine Base, Site F, Bangor, WA 7/18/1994 ------- EXPLANATION OF SIGNIFICANT DIFFERENCES (ESD) FOR THE INTERIM REMEDIAL ACTION SITEF SUBASE, BANGOR BANGOR, WASHINGTON Introduction Site F at the Naval Submarine Base, Bangor (SUBASE, Bangor) is located in the south-central portion of the SUBASE. SUBASE, Bangor is located on Hood Canal in Kitsap County, Washington, approximately 10 miles north of Bremerton. The lead agency for this National Priorities List (NPL) site is the U.S. Navy. The U.S. Environmental Protection Agency (EPA) and the Washington State Department of Ecology (Ecology) have provided support and oversight on the preliminary studies, site investigations, remedial alternative selection, and design and construction of the Interim Remedial Action (IRA) at Site F. This ESD is prepared in accordance with Section 117(c) of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and Section 300.435(c)(2)(i) of the National Oil and Hazardous Substances Pollution Contingency Plan (NCP). It addresses the change from ultraviolet/oxidation (UV/Ox) technology to granular activated carbon (GAC) technology for treatment of groundwater extracted under the Site F IRA. A reevaluation of these alternative technologies concluded that GAC treatment of the extracted groundwater is equally implementable, equally effective, and substantially less expensive than UV/Ox treatment. Public notice of this ESD will be published in a major local newspaper. The ESD will be available for review in the information repositories located at the following Kitsap regional libraries: Central Kitsap Library (206) 377-7601 1301 Sylvan Way Bremerton, Washington 98310 Bangor Branch (206) 779-9724 Naval Submarine Base, Bangor Silverdale, Washington 98315-5000 The ESD will also become part of the Administrative Record File in accordance with NCP 300.825(a)(2). The Administrative Record for Site F is available between the hours of 0800 and 1600 at: Page 1 ------- Engineering Field Activity, Northwest Naval Facilities Engineering Command 1040 Hostmark Street Poulsbo, WA 98370 (206) 396-5984 Summary of Site History, Contamination Problems, and Selected IRA The Bangor Naval complex served as a munitions handling, storage, and processing site from the early 1940s until 1971. Site F, which consists of a former unlined lagoon and overflow ditch, was used between approximately 1960 and 1971 for the disposal of wastewater produced during the demilitarization of ordnance items in an adjacent Segregation Facility. Demil activities conducted in the Segregation Facility included initial separation of solid ordnance from the projectile casings, followed by steam cleaning of the casings. Condensate and ordnance residual from this process were collected in a holding tank. Holding tank effluent was treated in skimming and settling chambers to remove solids prior to discharge to the lagoon. The wastewater discharged to the unlined lagoon contained relatively high residual concentrations of trinitrotoluene (TNT) and hexahydro-1,3,5- trinitro-l,3,5-triazine (RDX), and lower concentrations of other ordnance compounds. Much of the wastewater apparently infiltrated through the bottom of the lagoon. During periods of heavy discharge, however, wastewater overflowed the lagoon into a narrow depression (ditch) to the south. Periodically, the lagoon was allowed to drain, and waste materials at the surface of the lagoon were "burned off" in place or transported off site for burning and disposal. No records were kept on the quantity of wastewater disposed of to the lagoon. In 1972-73, the lagoon was taken out of service, and process wastewater was subsequently collected in drums and delivered to the SUBASE, Bangor liquid-waste incinerator. The rate of wastewater delivery to the incinerator was estimated at 240 gallons per day. In 1980, demil operations were terminated and the former lagoon area was filled in and covered with asphalt. The Segregation Buildings were subsequently decontaminated and converted to storage. In 1978, evaluation of SUBASE, Bangor waste disposal sites (including Site F) began under the Navy Assessment and Control of Installation Pollutants (NACIP) program. Work at Site F continued in 1981 as part of an Initial Assessment Study (IAS) and in 1986 as part of a Characterization Study, both under the NACIP program. With the enactment of the Page 2 ------- Superfund Amendments and Reauthorization Act (SARA) in 1986, the Navy suspended further NACIP program activities and phaSed into the EP A Remedial Investigation/Feasibility Study (RIlFS) program. In August 1990, SUBASE, Bangor (including Site F) was officially listed on the National Priorities List (NPL) of Hazardous Waste Sites. The RIIFS investigation fQr the final remedial action at Site F is ~urrently ongoing. The disposal of ordnance wastewater at Site F resulted in contamination of soil and groundwater. Roughly 75 percent of the estimated total mass of ordnance at Site F is present within unsaturated soils beneath the fonner wastewater lagoon and overflow ditch. The remaining 25 percent is present in the Shallow Aquifer, an unconfined aquifer located at a depth of approximately 50 feet beneath the site. Water quality data indicate that. RDX has been transported in the Shallow Aquifer up to approximately 3,000 feet downgradient (west-northwest) of the fonner lagoon. Other ordnance compounds, such as lNT and DNT, have migrated less than 1,500 feet downgradient, and remain well within the extent of elevated RDX concentrations in the aquifer. The Record of Decision (ROD) for the Site F IRA was signed in . September 1991. It addresses the threat posed by the site by providing . groundwater containment and on-site treatment with penn anent reduction in the mobility, toxicity, and volume of contamination. The elements of the Site F IRA as set forth in the ROD. include: ~ Extraction of groundwater from the Shallow Aquifer to contain the contamination and thereby confine further contaminant movement in the aquifer; . ~ Treatment of the extracted groundwater using UV lOx technologies to meet applicable regulations prior to disposal; . ~ Disposal of the treated groundwater on base by recharge or injection into the Shallow Aquifer; and ~ Monitoring the effectiveness of the groundwater containment and groundwater treatment processes. . Description of the SignifICant Differences and the Basis for Those Differences UV lOx and GAC were evaluated in the ROD for the Site F IRA as. alternative technologies for treatment of extracted groundwater. It was determined that both technologies were capable of meeting the threshold criteria (protective of human health and the environment, and compliance with ARARs). The estimates prepared at that time al~o showed Page 3 ------- , . , . comparable costs for these technologies. UV lOx was selected for the following reasons: .. UV/Ox was considered to be more "implementable". due to limited availability of facilities capable of regenerating or disposing of spent GAC; .. UV lOx provides on-site destruction of contaminants; and .. UV lOx is an innovative technology. Based on current infonnation, the implementability of GAC is no longer a problem. The carbon manufacturerlsupplier selected by the Navy's Remedial Action Contractor (RAC) is now capable and willing to accept ordnance-laden GAC at their carbon regeneration facility. Their previous reluctance to handle the spent GAC, which was based on carbon regenerability considerations, can now be effectively addressed by limiting ordnance loading on the GAC. Accordingly, GAC is now considered equally as implementable as UV lOx technology. Since adsorbed ordnance compounds are thennally destroyed in the regeneration process, this treatment technology also satisfies the statutory preference for penn anent treatment to reduce toxicity, mobility, and vglume. . Table 1 presents current cost estimates for the Site F IRA using UV lOx versus GAC for groundwater treatment. Treatment by UV lOx is estimated to cost $800,000 more than treatment by GAC, based on two years of IRA operation. This is primarily due to the large difference in treatment" technology capital costs. A treatment plant. using either technology would require many common items, such as process pumps, holding tanks, filters for suspended solids removal, and interconnecting piping. The only. significant "unique" equipment required for GAC treatment are process vessels to hold the activated carbon itself. "The GAC cost estimate assumes that a Calgon Model 10 Dual Adsorption Unit is purchased for this purpose at a cost of approximately $190,000. " Equipment requirements and costs for UV lOx treatment are based on the findings of the UV lOx Treatability Study perfonned for Site F. In addition to the UV/Ox reactor itself, UV/Ox treatment w01Jld require facilities for . ozone generation, acid and base storagelinjection (for water pH . adjustment), gas recompressionlrecycling, and destruction of residual ozone in the offgas. The capital cost of equipment unique to UV lOx treatment is estimated at $800,000. The equipment cost differential between treatment technologies is therefore estimated at $610,000. Applying a contingency factor of 15 percent (to account for unforeseen additional costs) results in the capital cost differential of $700,000 as shown in rable 1. Page 4 ------- t . .. The corresponding cost estimates provided in the Site F IRA ROD are also shown in Table I for comparison. Estimates of total costs for both technologies have dropped since the ROD evaluation. This is due to the much lower costs now estimated for system operation and maintenance (O&M) in both cases. Lower O&M costs partly result from the lower ordnance concentrations, that are now anticipated in the extracted groundwater. This concentration reduction has a greater impact on GAC O&M costs, since they are more concentration-dependent than are UV lOx O&M costs. Another reason why GAC O&M costs have declined is that, as noted above, spent carbon can now be regenerated for reuse. The UV lOx Treatability Study, on the other hand, demonstrated that substantial reductions in UV lOx O&M costs were also justified. The net result based on these analyses and present technology, however, is that GAC is now estimated to be significantly less expensive than UV lOx from both a capital and an O&M cost perspective. GAC treatment still requires off-site tra.I:1sport of contaminants prior to their ultimate destruction. However, current estimates indicate that, for a 225 gpm treatment rate, only about two 20,OOO-pound truckloads of spent carbon per year will require transport to a regeneration facility. The distinction of UV/Ox as an innovative technology still applies as well. However, the greater cost-effectiveness of GAC treatment outweighs the UV lOx advantages of on-site contaminant destruction and innovative technology. Based on the data now available, GAC is proposed for use in place of UV lOx to treat extracted groundwater under the Site F IRA. Regulations which apply to transporting GAC to and from Site F will be included as ARARs for the remedial action. Transport of this material will be conducted in accordance with all applicable local, state, and federal transportation regulations. Fresh GAC transported onto the site will not be a hazardous waste and standard shipping regulations will apply. Spent GAC will be managed as a K045 hazardous waste. (K045 is the hazardous waste number assigned under the Resource Conservation and Recovery Act [RCRA] for spent carbon from the treatment of wastewater containing explosives.) A limit of ten percent by weight explosives loading on the GAC to be sent off site is set in order to ensure that the GAC will not be a characteristic RCRA hazardous waste for reactivity. In addition, spent GAC will be evaluated to determine if it exhibits the toxicity hazardous waste characteristic (e.g., due to 2,4-DNT content). This evaluation will include testing if necessary. Spent GAC will be manifested and transported in accordance with all applicable regulatio,ns. Page 5 ------- . . . . In order to ensure that the off-site thennal treatment-does not contribute to present or future environmental problems, the selection of a 'thermal treatment facility' will follow the procedures presented in Procedures for Planning and Implementing Off-Site Response Actions, 58 FR 49200, September 22, 1993. Backup Technologies UV/Ox will be the back-up technology for groundwater treatment, to be used in the unlikely event that thennal destruction of ordnance compounds adsorbed onto GAC proves impracticable. If a specific batch of spent GAC is not accepted for thermal regeneration (due, for example, to an unacceptably high ordnance loading), it will either be used as a supplemental fuel in a cement kiln or, as a last resort, incinerated. ' Affirmation of the Statutory Determinations Considering the new information that has been developed for the Site F IRA, the lead agency believes that the remedy as changed is protective of human health and the environment, complies with federal and state requirements that were identified in the ROD as applicable or relevant and appropriate to this remedial action at the time the original ROD was signed, and is cost-effective.' The revised remedy utilizes permanent solutions. GAC was considered as an alternative treatment technology during development and selection of the original remedy. It is now considered to be equivalent to UV lOx in tenns of effectiveness and implementability. Public Participation Activities Public notice of this ESD will be published in a major local newspaper. Notice has been issued previously that the contents of the Administrative Record File are available for public review and comment. The GAC treatment technology has been discussed and presented to the public at previous meetings conducted to explain the alternatives and selected remedy for the Site F IRA. A fact sheet will be issued explaining this' ESD. 14632S\ESDSITEF.DOC Attachment: Table 1 - Site F Interim Remedial Action Cost Estimates Page 6 ------- . . . . . . . Table 1 - Site F Interim Remedial Action Cost Estimates Cost in Thousands of Dollars Current Estimatesl IRA ROD Estimates2 Groundwater Treatment Technology UV IOx3 GA<:4 UV/Ox GAC Capital 2,000 1,300 1 ,200 900 Operation & Maintenance (O&M) 300 200 1,300 1,600 (Based on 2 years of operation) Total Estimated Cost 2,300 1,500 2,500 2,500 Current capital estimates are based on a 300 gpm design flow rate, with 15 percent contingency. Current O&M estimates assume a typical operating flow rate of 225 gpm. 2 The IRA ROD cost estimates assume a flow rate of 200 gpm (both design and actual operation) with no contingency. 3 Current UV lOx treatment cost estimates are based on quotes provided by Solarchem during the UV/Oxidation Treatability Study performed for Site F. 4 Current GAC treatment cost estimates are based on quotes provided by Calgon Carbon Corporation. 14632S\ESDSITEF.DOC Page 7 ------- . .' .. ~ . - site Name: INITIAL NAME DATE INITIAL NAME EXPLANATION OF SIGNIFICANT DIFFERENCES Concurrence Bangor, site F !A {' : Rodin 1 : C-.20 -9if 1 C,.j : ~: : ~ /.."'): : Clarke : :SJ!lL: I I 1 I I I. I I I I . I 1 : pierre 1 Oesterle I Hofer I~.I I I' I 1 :O~11i)q1 : 6-~-4¥: 71-1<11 DATE : !-~ 1 . Smith I~I : 7 /' t; . : I' I I ------- |