Environmental Protection
Agency
Emergency and
Remedial Response
May 1984
Superfund
Record of Decision:
Outboard Marine Corp.
Site, IL

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing]
1. REPORT NO.
  EPA/ROD/R05-84/007
             3. RECIPIENT'S ACCESSION NO.
4. TITLE AND SUBTITLE
  SUPERFUND RECORD OF DECISION:
  Outboard Marine  Corp.  Site, IL
             5. REPORT DATE
                  05/15/84
             6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
                                                           8. PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
                                                           10. PROGRAM ELEMENT NO.
                                                           11. CONTRACT/GRANT NO.
12. SPONSORING AGENCY NAME AND ADDRESS
  U.S. Environmental  Protection Agency
  401 M Street,  S.W.
  Washington, D.C.    20460
             13. TYPE OF REPORT AND PERIOD COVERED
                Final ROD Report	
             14. SPONSORING AGENCY CODE

                 800/00
15. SUPPLEMENTARY NOTES
16. ABSTRACT
       The Outboard  Marine Corporation  (OMC)  site is located north of  Chicago on
  the shore of Lake  Michigan.  It is the location of an outboard motor manufacturing
  plant which used polychlorinated biphenyls  (PCBs)  in its die cast machines for
  about 20 years ending in the early 1970's..  Discharges from the facility resulted
  in highly contaminated sediment in Waukgan  Harbor and contaminated soil  in the
  parking lot north  of the plant and the "North Ditch," a tributary of Lake Michigan.

       The cost-effective option considered for this site was excavation and off-
  site disposal of PCB contaminated material.   This is the only option that meets
  the requirements of TSCA and guarantees  the halt of PCB migration.   The  cost of
  this option is more than $75 million.  Because of the high cost to implement this
  option it was necessary to Fund Balance.  Fund Balancing is appropriate  where the
  alternative that would fully satisfy the technical requirements of other environ-
  mental laws is extremely expensive, and  another alternative which approaches the
  same level of effectiveness can be implemented for a much lower cost.  The Fund
  Balanced alternative for this site provides for off-site disposal of PCB contaminated
  hot-spots and on-site containment of the moderately contaminated materials.   The
  cost of the Fund Balanced selected alternative is estimated to be $21.57 million.
  Key Words: On-Site Containment, PCBs, NEPA,  Dredging, Water Quality  Standards,Fund
 	Balancing	.	
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.lDENTIFIERS/OPEN ENDED TERMS  C. COSATI Field/Croup
  Record of Decision
  Outboard Marine Corp.  Site,  IL
  Contaminated media:  gw,  sw,  soil, river
   sediments, fish, air
  Key contaminants : PCBs'  hydraulic fluids,
   oils
18. DISTRIBUTION STATEMENT
19. SECURITY CLASS (This Report/
   	None	
21. NO. OF PAGES
     28.	
                                              20. SECURITY CLASS (This page)
                                                        None
                                                                         22. PRICE
EPA Form 2220-1 («•». 4-77)   PREVIOUS EDITION is OBSOLETE

-------
                          ROD ISSUES ABSTRACT


Site;  Outboard Marine Corporation, Waukegan, Illinois

Region;  V

AA, OSWER
Briefing Date;  May 7, 1984

                           SITE DESCRIPTION

    The Outboard Marine Corporation (OMC)  site is located north  of
Chicago on the shore of Lake Michigan.   It is the location of  an
outboard motor manufacturing plant which used polychlorinated  biphenyls
(PCBs) in its die cast machines for about  20 years ending in the early
1970's.  Discharges from the facility resulted in highly contaminated
sediment in Waukegan Harbor and contaminated soil in the parking lot
north of the plant and the "North  Ditch,"  a tributary of Lake  Michigan.

                         SELECTED  ALTERNATIVE

    The cost-effective option considered for this site was excavation
and off-site disposal of PCB contaminated  material.   This is the only
option that meets the requirements of TSCA and guarantees the  halt  of
PCB migration.  The cost of this option is more than $75 million.
Because of the high cost to implement this option it was necessary  to
Fund Balance.  Fund Balancing is appropriate where the alternative  that
would fully satisfy the technical  requirements of other environmental
laws is extremely expensive,  and another alternative which approaches
the same level of effectiveness can be implemented for a much  lower
cost.  The Fund Balanced alternative for this site provides for
off-site disposal of PCB contaminated hot-spots and on-site containment
of the moderately contaminated materials.   The cost of the Fund
Balanced selected alternative is estimated to be $21.57 million.
        ISSUES AND RESOLUTIONS

1.  Two options for on-site containment of the PCB
    contaminated harbor material were considered.
    These on-site options were (1) containment in
    Slip 13 and (2) containment on the Outboard
    Marine Corporation (OMC) parking lot.  Both
    alternatives are considered to be technically
    acceptable.  Although containment in the OMC
    parking lot was estimated to cost up to $1.9
    million more, this cost differential would be
    decreased by whatever costs would be incurred
    for land acquisition costs in the slip area.
    However, this cost differential was outweighed
    by added ease of monitoring and implementation
    for the parking lot site.
KEY WORDS

.  On-Site
  Containment
.  PCBs
                                  -1-

-------
Outboard Marine Corporation,  Waukegan,  Illinois
May 7, 1984
Continued
        ISSUES AND RESOLUTIONS                       KEY WORDS

    In the feasibility study/  remedies from          .  NEPA
    several operable units were combined into a
    limited number of "assembled alternatives."
    During the ROD process, EPA decided to
    reassemble the remedies for the operable
    units, in response to public comments.
    By reassembling the alternatives,  the issue
    of NEPA compliance was raised.   In the
    future, it is important to present all
    possible combinations of remedies  to the
    public as potential alternatives.   In this
    way, EPA ensures compliance with NEPA.

    The selected remedy involves dredging all        .   Dredging
    sediments with PCB contamination above 50 ppm.    .   PCBs
    A model supported selection of  50  ppm on the      .   Water Quality
    basis that it provided a margin of safety to         Standards
    assure that after implementation of the
    remedy the harbor water column  would meet
    ambient water quality standards, and fish
    would not accumulate PCB beyond the FDA
    standard.

    The Fund Balancing provisions in CERCLA and      .   Fund Balancing
    the NCP were used to select an  option that is
    significantly less expensive and only slight-
    ly less reliable than the cost  effective
    option.
                                  -2-

-------
                    Record of Decis.iori
               Remedial -Alternative Selection
SITE;  Outboard Marine Corporation (CMC),  Wauke-jan,  Illinois


DOCUMENTS REVIEWED;

I have reviewed the following documents describing the analysis
of cost-effectiveness of remedial alternatives. for the OMC bite:

- OMC Feasibility Study, CH2M-Hill, July 14, 1983

- OMC Technical Documentation (a staff summary of the information
  collected during sampling, modeling and  engineering studies
  conducted by Region V as part of tne litigation effort)

- Summary of the Remedial Action Alternative Selection

- Responsiveness summary addressing comments received fror: the
  public.


DESCRIPTION OF THE SELECTED ALTERNATIVE:
- The alternative selected for each segment of the site is shown
  on the attached Table 1.
DECLARATIONS:
Consistent with CERCLA and the NCP,  I have determined that the
source control remedy described in Table 1 is the appropriate
Fund-financed action for this site in accordance with section
300.68(j) and (k) of the NCP.  Although the selected remedy does
not meet all the requirements of regulations issued under TSCA
and is somewhat less protective than the cost-effective option
as defined by the NCP, the remedy is expected to be reasonably
effective in preventing the migration of PC3 from the site which
would threaten public health, welfare or the environment.  In
addition, this remedy is expected to be significantly less expensive
than any alternative which would be fully consistent with TSCA
regulations and protective of public health.  Therefore, I have
determined that the level of protection provided by the selected
remedy is appropriate considering the need for additional protection
at this site and the amount of money available in the Fund to
respond to other sites which present or may present a threat to
public health, welfare or.the environment.

-------
                             -2-
          •            •                             .
The State of Illinois has been consulted and agreesfevi th the
remedy.  The action will require future operation aid mainten-
ance activities to ensure the continued effectiveness of the
remedy.  These activities will be considered part of the approved
action and eligible for Trust Fund monies for a period of one year,
In accordance with section 104(c)(3),  the State is required to
ensure the continued operation and maintenance of the selected
remedy.

In addition, the offsite transport and secure disposition of the
highly contaminated material (see Table 1) is more cost effective
than other remedial action and is necessary to protect public-
health, welfare or the environment.
                                      '•"V—t—"
                   \
                          Lee M. Thomas
                     Assistant Administrator
           Office of Solid Waste and Emergency Response
                                '
                              Date

-------
        S i I o Soijmont

    Wnukegan Harbor
COMPONENTS OK TIIK  KlINI) HAI.ANCEI) AI.TKRNAT IVE

                       Remedy Recommended
    1.  H tTTrrTy^con tain i na ted material
           (hot  spots  -  >10,0000 ppm)

    2.  Moderately  contami nated
        material  (500  - 10,000 ppm)
    3.  Loss contaminated material
        CiO -  500  ppm)

B.  Oval l.acjoon/Crescont  Ditch

    1.  Highly contami nated ma tori a
        (>i0,000 ppm)

    2.  Less cont.imi n.il'.oil tn.itorial
C.  North Ditch

    1.  Material  above  storm sower


    2. .Material  below  storm sewer
              Fxcavation,  dewatering,  fixation and
              olf-site disposal in a PCR  landfill.

              Excavation,  downterimj in  laijoon,
              fixation to minimi/.e volatilization,
              an(J disposal on OMC i>arking  lot.

              Excavation,  IOIKJ term dowatorinq in
              layoon,  and  disposal on OMC  parking .lot.
              Excavation and off-site disposal  in a
              PCM  landfi11.

              Containment  on site.
                -  Slurry walls down to glacial till
                   Impermeable cap
              Excavate and contain in  the
              Ova 1 Laijoon.

              Capped  wi tli clean fill and clay  cap.
       Cost
$ 3.15 Mi Hi on
$10.00 Mi Hi on
$  .74 Million
                                                         S 4.21 Million
I).  Parking Lot
              Contained in place with contaminated
              ilri.-dcjo  spoil?; from Waukegan  Harbor.
                   Slurry walls down to glacial till
                -  1 mpormi'cib 1 o cap
$3.2  Mi llion
    TOTAL
                                                         $21.30 Million

-------
/v: :"">.                      UNITED STATES
                   ENVIRONMENTAL PROTECTION AGtNCY
       •                        REGION V


                          CHICAGO :;.. '.0!3 3C5C4
                                        •      •
  MEMORANDUM
.-•'Ay   4  884
  SUBJECT:  Recommendation for Remedial Implementation
            Alternative Selection - CMC Hazardous Waste Site,
            Waukegan, Illinois

  FROM:      Valdas V. Adamkus
            Regional Administrator

  TO:        Lee M. Thomas
            Assistant Administrator
            Office of Solid Waste and
              Emergency Response

       EPA has completed the following remedial CERCLA activities
  at  the Outboard Marine Corporation (OMC) Site located in
  Waukegan, Illinois.

       Activity                                      Date

  Final  Work Plan, Source Control Feasibility
    Study                                            3/28/83

  Source Control Feasibility Study Report            7/15/83

  Opening of First Public Comment Period             7/15/83

  Public Informational Meeting                       7/28/83

  Public Meeting                                     8/3/83

  Close  of First Public Comment Period               9/1/83

  Opening of Second Public Comment Period            3/6/84

  Public Informational Meeting                       3/14/84

  Close  of Second Public Comment Period              4/4/84

       Region V has reviewed the information in the  reports and
  has  given careful consideration to the comments received in  the
  public comment periods.  Pursuant to Section 104(c)(2) of
  CERCLA, we have consulted with the State of Illinois before
  determining the appropriate remedial action.  Based on our
  review, Region V recommends that the following actions at the

-------
                              -2-
OMC Site~effectively mitigate and minimise damage to and prv/i.-io
acceptable protection of public health, welfare, and tthe e-ivir ?'i-
nent.  The recommended action included some off-site transport
as such a'ction is nore cost-effective than other remectial
actions and is necessary to protect public health, werfare,  n~ 1
the environment from the potential risk which may be created  by
further exposure to the continued presence of PCBs at  the OMC
Site.  As discussed with your staff, the  following recommendation
includes fund balanced considerations.
      Action

Dredge, Dewater, Dispose, Cap
in Parking Lot
(Slip No.3 and the Upper Harbor)
                                  Estimated Cost
                                   S 9,940,000
Dredge, Remove, Fix and Dispose
5, "00 yd3 of PCB-contarninated
mater ia 1
Excava te
Crescent
Cap
North Ditch, Contain in
Ditch/Oval Lagoon and
Excavate and Dispose 5,500 yd-5 of
PCB-contaminated material
(Crescent Ditch/Oval Lagoon)

Contain and Cap
(Parking Lot)
                              TOTAL
S 3,150,000



S 4,210,000



S   740,000


S 3,210,000
521,250,000
    Operation and maintenance costs for the site are  estimated
to be 534,250 annually, or 5800,000 for 30 years on a present
worth basis of 10%.  The Illinois Environmental Drotection
Agency will be responsible for the operation and maintenance.

    Region V additionally recommends that EPA share in the
costs of operation and maintenance for a period of one year
following completion of the project.  This time frame is  needed
to allow for settling of the cells and to assure the  integrity
of the cells.
                                        Valdas  V.  Adamkus

-------
 Illinois Environmental Protection Agency  •  2200 Churchill Road. Springfield. IL 6^7
217/782-5544

Mr. Basil Ccrstantelos .
Director, Waste Management Division                          L .
United States Environmental Protection Agency,               T
Region V                                                     {
230 South Dearborn Street
Chicago, IL  60604

Re:  Source Control Feasibility Study
     CMC - Waukenan Harbor Site

Dear Mr. Constantelos:

On September 19, 1983, the Agency transmitted to your office a  letter
endorsing the alternatives set forth in Secticr. 7 of the Source Control
Feasibility Study for the CMC - Waukegan Harbor site dated July 14,  1983,
as being an approach which is technologically feasible in providing
adequate protection of public health, welfare and the environment.   The
Agency also concluded that the approach was cost-effective as long as
the control alternatives were implemented in a phased manner to allow
the flexibility to assess development of new technologies at the various
increments of the project.

On May 1, 1984, members of Region V staff presented to myself,  Agency •
staff rerbers, and a representative of the Illinois Attorney General's
Office a proposal which would replace Alternative 63 as set forth in
the July 14, 1983, feasibility study with Alternative 6D as set forth
in a letter, dated April 4, 1984, which was prepared in response to
a request from USEPA - Region V by the authors of the feasibility study.
The Agency does not object to substitution of alternative 6D as long
as alternative 6D and the remaining Section 7 alternatives are  imple-
mented in a phased manner which recognizes the fiscal constraints on
the State of Illinois in raising its matching share, and which  allows
the flexibility to assess the development of new technologies at the
various increments of the project.
Richardi J.J Carlson
Director

cc:  Jim Frank
     Roger Kanerva
     Gary King

RJC:GPK:kam

-------
                      Summary of  Remedial Alternative
                   Selection - CMC Hazardous Vfeste Site,
                             Waukegan,  Illinois
I.  Site Location and Description

    The Outboard Marine Corporation site (OMC)  is  located  near the  intersection
    of Grand Avenue and Sheridan Road  on the west  shore of Lake Michigan in
    Waukegan, Illinois, about 37 miles north of Chicago and 1Q miles south
    of the Wisconsin state border.   See diagram on next page.

    Waukegan Harbor is an irregularly  shaped harbor about  37 acres  in area.
    The two areas of concern are Slip  No.  3 and the Upper  Harbor.   PCB
    concentrations -in Slip No. 3 are greater than  500  parts per million
    (ppm).  In the Upper Harbor, PCB concentrations are between 50  and 500
    ppm.  Water depths in the harbor generally  vary from 14 to 25 feet with
    sane shallower depths in Slip No.  3.  The harbor sediments consist of  1
    to 7 feet of very soft organic silt (muck)  overlying typically  4 feet
    of medium dense, fine to coarse sand.  A very  stiff silt (glacial tilH
    that typically ranges from 50 to more than  100 feet thick underlies  the
    sand.  The entire harbor is bordered by 20- to 25-ft-long steel sheet
    piling, except at the Waukegan Port District boat  launching areas and
    at the retaining wall near the harbor mouth.  The  sheet piles generally
    extend into the sand layer above the glacial till.

    The North Ditch is a small tributary of Lake Michigan  that drains
    surface runoff from about 0.11 square miles of OMC and North Shore
    Sanitary District property.  The ditch also drains surface runoff from
    an area west of OMC property and the railroad  tracks.   The North Ditch
    includes the 600-ft-long, 20-ft-wide Crescent  Ditch; the 240-ft-long,
    10- to 20-ft-40-ft-wide Oval Lagoon; and a  2,000-ft-long, 10-to 20-ft-
    wide east-west portion of the North Ditch.   PCB concentrations  are
    between 50 and 5,000 ppm in the North Ditch/Crescent Ditch/Oval Lagoon
    area.  The U.S. Department of the  Interior  measured the mean daily
    discharge of the ditch between March and September 1979 as  1.8  cubic
    feet per second (cfs), with a maximum discharge of 5.3 cfs.  They
    calculated the 5-year storm event  to be 23  cfs.

    The Parking Lot area is located north of CMC's Plant No. 2 and  'is about
    9 acres in area.  PCB concentrations are between 50  to 5,000 ppm.
    There are three entrances to the lurking Lot area: two fenced entrances
    in the northwest corner of CMC's property  and  one fenced entrance
    southeast of CMC's new die-cast complex at  the intersection of  CMC's
    private road and Seahorse Drive.

-------
                                 -2-
 The generalized subsurface conditions in the North Ditch/Parking  Lot
 area consist of- typically 30 feet  of  cctrpact,  very fiiie  to  fir.e Si.-.d
 overlying a stiff too very stiff silt (glacial tilD.feThe  thickness of
'the glacial till typically ranges  fron 50 to more  thallOO  feet.

 The presence of high levels of  PCBs in soil  and harbor sediments  in the
 vicinLty of the CMC plant was discovered in  1976.   In Slip  No. 3,
 approximately 10,900 yd3  of material  are contaminated by PCBs (exceeding
 50 ppm).  Available data  indicates that approximately 305,200 Ib  of
 PCBs exist in the contaminated  slip.   Currently no barriers exist to
 retard migration of the materials  into the Upper Harbor  and potentially
 Lake Michigan.   This is exaserbated by continual boat traffic in  the
 harbor.   Approximately 35,700 yd3  of  muck in thc> Upper Harbor are
 contaminated by about 5,000 Ib  of  PCBs (exceeding  50 ppm).   See Exhibit
 C pq 1-6.  In the North Ditch/Parking Lot area, approximately 175,800
 yd^ of material are contaminated by PCBs (exceeding 50 ppm).   Currently
 available information indicates that  approximately 771,200  Ibs of PCBs
 exist in this contaminated area.  See Exhibit C pg 1-6.   Currently no
 barriers exist to retard  migration of the substances into the environment.

 It is currently estirrvated that  7 to 20 Ib of PCBs  are discharged  annually
 into Lake Michigan from the North Ditch.  The groundwater is within 3
 feet of the surface of the Parking Lot area, resulting in contamination
 of this water.   It is estimated that the slowly moving water will begin
 releasing some 8 Ib/day of PCBs into Lake Michigan in approximately f
 years.  Existing air contamination from the  North  Ditch  waters is
 estimated at 15 Ib/yr. Any additional movement of the soil, currently
 under the paved parking lot, could cause additional volitalization of
 PCBs.  See Exhibit C pg 6-16.  Approximately 98.4  percent of the  PCBs
 now found in the Slip/Harbor area  are located in Slip No. 3, 1.6  percent
 have migrated into the Upper Harbor.   See Exhibit  C, pg  8-9.

 Site History

 Discharges of process water cooling water, and water from floor drains,
 from CMC are the major source of PCB contamination to the area.   About
 9 million pounds of PCB's were  purchased from the  Monsanto  Company from
 the early 1950's to 1971.   These PCB's were  used as hydraulic fluids  in
 die casting machines and  related equipment.

 Because the hydraulic systems in which the hydraulic fluids were  used
 leaked routinely, the fluids containing PCB's escaped from  die-cast
 machinery onto the surrounding  floor area.   CMC has advised U.S.  EPA
 that 10 to 15 percent of  all PCB's purchased may have escaped through
 floor drains and an oil interceptor system.   The floor drains discharge
 to Waukegan Harbor and the North Ditch Drainage.  U.S. EPA  has estimated
 that the discharge could  have been as high as 20%.

-------
                                -3-
Release of PCB's from the sice is frccn Surface Vsater, feriatil 12.2 tier.,
Groundwater, and the Food Chain.   Possible receptors include the
biological community of the harbor, North Ditch, and Nearshore Lake
Michigan Area.  People are exposed or potentially exposed through fish.
consumption, potentially through the drinking water supply, and by
direct contact.

The official 1980 Census figure for the City of Waukegan is 67,653.
The Harbor area, however, is zoned for industrial use.  Fifteen businesses
are located in the irradiate Haroor area and provide jobs to approximately
3,500.  The local Port Harbor for primarily recreational use.  Long
term plans additionally include a development of the Upper Harbor.  See
Exhibit C pgs 6-12, 6-13.

The population is exposed to PCS through three medias; air, water, and
the food chain (pri.-rarily fish).   It is currently estimated t.-.at 22 Ib
of PCBs are released into Lake Michigan each year fron Waukegan Harbor
water (based on a steady state model).  Approximately 12 to 40 ID of
PCBs are released from the Harbor into the local airshed eacn year."
Existing air contamination from the North Ditch waters is esti.Tated at
15 Ib/yr.  See Exhibit C pgs 6-16 through 6-17.  Total PCB concentrations
vary fron 0.6 parts per billion (ppb) in Waukegan Harbor to less than
0.01 ppb in Lake Michigan directly offshore from Waukegan Haroor.
There is an emergency water supply intake for Waukegan near the mouth
of the harbor, although it is rarely utilized.  See Exhibit C pg 6-20.
In U.S. EPA studies on Lake Michigan fish, results ranged frcm
concentrations of 2.7 ppm to 187 ppm PCB in fatty tissue for all
species.

Enforcement

U.S. EPA filed suit against the CMC and Monsanto Companies in 1976.
The suit is still in effect, not being brought to trial.  The existing
suits may be dismissed and reinstated as a Superfund Cost Recovery
Action following implementation of the cleanup.  U.S. EPA has conducted
several years of negotiations with OMC to try and reach an agreement
regarding a cleanup plan.  Since no agreement could be reached over a
long period of time, Region V recommended to Headquarters that the Fund
be accessed for the cleanup.

Alternatives Evaluation

The feasibility study began with an evaluation of over 70 unit processes
or methods to determine their potential for contributing to PCB  removal.
The processes retained from preliminary screening were assembled  into
21 alternatives.  Finally 17 alternatives and two subalternatives were
selected for more detailed evaluation.  Final alternative selection was
based upon the Feasibility Study, input from the community relations
program, and input from various headquarter's offices.

-------
                                -4-
 Community  Relations                        .   '.
               •
 Prior to the  selection of  the  appropriate  remedial action at the CMC
 site  the-following actions were taken and  the documents identi&ed were
 reviewed by the Regional staff:                                T

      A.  On March 28, 1983, a  Final Work Plan, Source Control Feasibility
 Study, CMC site, Waukegan, Illinois was authorized.  U.S. EPA Work
 Authorization 13-5M28.0.

      B.  On July 14, 1983, a Source Control Feasibility Study, CMC
 Hazardous  Waste Site, Waukegan, Illinois (FS) was completed.

      C.  On July 15, 1983, a public comment period to evaluate and
 comment on the FS began.  A public informational meeting was held in
 Waukegan on July 28, 1983, to  respond to any questions by the public.
 On August  3,  1983, a public meeting was held in Waukegan to receive
 formal public comment on the FS.  Finally, on September 1, 1983, the
 extended public comment period was closed.

      D.  Twenty-five written comments in addition to the comments
 received during the public hearing were received and responded to by
 the Region.

      E.  On March 6, 1984, a second public comment period to evaluate
 and comment on two issues in addition to the FS began.  A public
 informational meeting was held in Waukegan on March 14, 1984, to respond
 to any questions by the public.  On April 4, 1984, the public comment
 period closed.

      F.  Over 250 public conments were received during the public
 comment period and responded to by the Region.

      G.  As affected Agencies, the Illinois Environmental Protection
 Agency and the U.S. Corp of Engineers were informed of and involved in
 the preparation of the FS.  Additionally, pursuant to 16 U.S.C. 662(a),
 the U.S. fish and Wildlife Service, Department of Interior was informed
 about the  FS.  No adverse comments were received by U.S. EPA fron these
Agencies.

Consistency with other Environmental Laws

U.S. EPA conducted the feasibility stu-y process in accordance with the
 National Contingency Plan, and to the greatest extent possible, in
compliance with the National Environmental Policy Act.  U.S. EPA
developed  a cost effective alternative which is consistent with other
environmental laws applicable to the site.  Since a Fund-Balanced
alternative is under review a Superfund waiver from TSCA requirements
may be needed.

-------

Recorrended 'Alternative                                    '.

In accordance with Part 300.68(J) U.S. EPA conducted a complete cost
effective analysis concerning a wide range of alternatives.' The
alternative presented below also contains fund balancing considerations.

Slip No. 3 and Upper Harbor:  Hot Spot Removal

PCB-ccntaminated sediment, sand and silt would be dredged from the
localized area near the former OMC outfall (drainage pipe).  This
material contains the greatest PCS concentrations in. the harbor and
represents 92 percent of all the PCBs now found in Slip No. 3 and the
Upper Harbor.  This alternative would remove, fix, and dispose of
offsite an estimated 5,700 yd3 of PCS contaminated material, containing
about 286,500 Ib of PCBs.  The material would be disposed of in an off-
site licensed chemical waste landfill.  The estimated cost for this
alternative is 53,150,000.

Slip a 3 and Upper Harbor;  Dredge, Dewater, and Dispose in Parking Let

A sediment dispersal control device would be installed at the southern
end of the Upper Haroor.  A clay-lined dewatering lagoon will be con-
structed an the OMC vacant foundary property.  Sediments in excess of
50 ppm PCS will be removed frcn the harbor by hydraulic dredging.  Sedi-
ment slurry will be pumped to the dewatering lagoon.  Supernatant would
be decanted, treated to 1 ppb PCB's and returned to the harbor.

Solids would be treated in two fashions

     1)  Highly contaminated material from slip:

              dredge 	>  initial dewatering 	>  fixation

     2)  Less contaminated material from the harbor:

              dredge 	>  initial dewatering 	>  mechanical dewatering

Solids will be periodically removed by dragline and hauled by truck  for
disposal in the parking lot.  This will be codisposed with the existing
contamination in the parking lot.

Approximately 46,600 yd^ of sediments containing about 24,700 Ibs of PCB's
would be removed from the harbor, dewatered, and disposed  in the parking
lot.  Contaminated lagoon material would also be brought to the parking
lot.  This alternative is estimated to cost 59,940,000.

-------
                              -6-
North Ditch Area:  Hot Spot Removal

PCS contaminated soil would be excavated fron the localized areas in
the Cresent Ditch and Oval Lagoon.  This material contains aobut 89
percent of all the PCB's now found in the North Ditch area, 'and
about 57 percent of all the PCB's now found in the North Ditch
parking lot areas.^ This alternative would remove and dispose of an
estimated 5,500 yd3 of soil containing about 440,500 Ib of PCB's.
The soil would be disposed of in an offsite licensed chemical waste
landfill.  The estimated cost is 3740,000.

North Ditch Area: Install Bypass Sewer and Contain Onsite Contaminated
N.D. Material

PCB-contaminated soil would be ccr.tained and capped in the Cresent Ditch/
Oval Lagoon area.  The North Ditch would be partly excavated to install
a bypass drainage pipeline.  The PCB-contaminated soil fron the bypass
excavation would be placed in tr.e Cresent Ditch/Oval Lagoon area before .
cappinng the area.  This alternative would contain about 492,100 Ib of
PCB's in 51,400 yd3 of soil.  The estimated cost is $4,210,000.

Parking Lot:  Contain and Cap

Approximately 277,700 Ibs. of PCB's in 105,000 yd3 of soil occur in the
CMC parkling lot.  46,600 yd3 of dredge material fron the harbor will be
brought to the site, graded and compacted.

The total contamination will be contained with slurry walls andd capped
in place.  The elevation of the parking lot will increase 14 feet.  This
portion of the project is estimated to cost $3,210,000.

The total estimated cost to implement the above recommended cleanup action
i e- f\r\ ^en nnn
is «J^\f j t Jv | ^W.
      ion and Maintenance
According to our memo concerning predicted O&M requirements of the
proposed project, O&M will inv^i -e mo»ing of vegatative containment v
cell covers and sampling monitoring wells.  The design life of the
structures is 30 years.  Annual OiM costs are estimated to be 84,250.
This is also estimated to be $800,000 for 30 years on a present
worth basis at 10%.

The Illinois Environmental Protection Agency is identified as the
State Agency responsible for 0&M.

-------
                                   -7-
Schedule                                    Cate of Implementation

Key Milestones                              (after RCD signature)

Complete Enforcement Negotiations           30 days
Aware/AG for Design Coord.                  Corrpleted
Superfund State Contract                    45 days
Award IAG to initiate design                40 days
Start Design                                45 days
Complete Design                              6 months
Award Cooperative Agreement for              8 months
  Construction
Award Superfund State Contract for           8 months
  Construction

Start Construction                          10 months
Ccrplete Construction                       3.5 years

Future Actions

Following construction, U.S. EPA will be responsible for O&M for one
year.  At that point long term OiM will revert to State responsibility.

-------
                    CMC   Technical Documentation

                          TABLE OF CONTENTS
                                                                        fPage
                                                                     •

      .-,.  s^wv. ^-v... ...^v.iw..	  1
      B.  EPA work at the OMC site	2
      C.  Concentrations of PCB found in the soil/sediment	5
      D.  Mechanisms of PCB Release from OMC 	  6
          1.  Air	6
          2.  Water and Sediment	7
          3.  Ground Water	8
      E.  Impact of PCB on Use of Waukegan Harbor	•	9

II.   Toxicity of PCB	14

III.  Threats to Public Health and the Environment Posed
      by PCB f ran OMC

      A.  Threats to Public Health	16
          1.  Drinking Water	'.  . 16
          2.  Ingestion of Contaminated Fish	16
          3.  Dermal Exposure	17
          4.  Inhalation	18

      B.  Threats to the Environment	18

TV.   Evaluation of "No-Action" Alternative  	 22

V.    Feasibility Study

      A.  Extent of Remedy	23
      B.  Screening of Alternatives	-	24
      C.  Excavation and Off-site Disposal 	 25
      D.  Containment on-site  	 27

VI.   The Cost-Effective Remedy	30

VII.  Fund Balancing	32

VIII. The Fund - Balanced Alternative	34

      A.  Development Process  	 35
      B.  Waukegan Harbor	41
      C.  Oval Lagoon/Crescent Ditch	43
      D.  North Ditch	44
      E.  Parking Lot	46
      F.  Evaluation of Threat Under Fund Balanced
          Alternative	47

IX.   TSCA	48

-------
                    BRIEFING MATERIAL ON CMC REMEDIAL ACTION
                  •              •             •    '                 .

I.   BACKGROUND                                                   F


A.   Site Description

The Outboard Marine Corporation site (CMC) is located near the intersection of

Grand Avenue and Sheridan Road on the west shore of Lake Michigan in Waukegan,

Illinois, about 37 miles north of Chicago and 10 miles south of the Wisconsin

state border.  The site may be divided into three areas:  Waukegan Harbor, the

North Ditch and the OMC parking lot.  See Figure 1.


Waukegan Harbor is an irregularly shaped harbor about 37 acres in area.  The

two areas of the Harbor of concern to this project are Slip No. 3 ana the

Upper Harbor.  Water depths in the Harbor generally vary from 14 to 25 feet

with some shallower depths in Slip No.  3.  The Harbor sediments consist of 1

to 7 feet of very soft organic silt (muck) overlying 4 feet of medium dense,

fine to coarse sand.  A very stiff silt (glacial till) that typically ranges

from 50 to more than 100 feet thick underlies the sand.  The entire Harbor is

bordered by 2O- to 25-ft-long steel sheet piling, except at the Waukegan Port

District boat launching areas and at the retaining wall near the Harbor mouth.

The sheet piles generally extend into the sand layer above the glacial till.


The North Ditch is a small tributary of Lake Michigan that drains surface

runoff fron about 0.11 square miles of  OMC and North Shore Sanitary District

property. -The ditch also drains surface runoff from an area west of OMC

property and the railroad tracks.   The North Ditch includes the contain the

6OO-ft-long, 20-ft-wide Crescent Ditch; the 240-ft-long, 1O- to 40-ft-wide

Oval Lagoon; and a 2,000-ft-long,  lo-to 20-ft-wide east-west portion of the

North Ditch.  The U.S. Department of the Interior measured the mean daily

-------
     North Ditch Area
     /N
                    Parking Lot Area
                  Upper Waukegan
                  Harbor Area
PCB CONCENTRATIONS
OVER 500PPM

PCS CONCENTRATIONS BETWEEN
50 AND 500 PPM
Site Map
        r•au

-------
                                     - 2 -



discharge of the ditch between March and September 1979 as 1.8 cubic feet per

second  (cf.s), with a maximum discharge of 5.3 cf.s.  They calculated the 5-year
                •              •
storm event to be 23 cfs.                                        fc •


The Parking Lot area is located north of OMC's Plant No. 2 and is about '•)

acres in area.  There are three entrances to the Parking Lot area: two fenced

entrances in the northwest corner of OMC's property and one fenced entrance

southeast of OMC's new die-cast conplex at the intersection of OMC's private

road and Seahorse Drive.


The generalized subsurface conditions in the North Ditch/Parking Lot area

consist of typically 3O feet of compact, verv fine to fine sand overlying a

stiff to very stiff silt (glacial till).  The thickness of the glacial till

typically ranges from 5O to more than 10O feet.




B.   EPA Work at the CMC Site.

High levels of PCBs in soil and harbor sediments in the vicinity of the OMC

plant were discovered in 1976 and 'were found to have originated in the OMC

outfalls.  With this discovery, EPA and State of Illinois began a series of

attempts to force OMC to cease discharging PCB and remove the PC3 contaminated

sediments from Waukegan Harbor and the North Ditch area.  These attempts

culminated in a suit filed against OMC by EPA to force OMC to dispose of North

Ditch soils and dredge/dispose of contaminated Harbor sediments and a countersuit

by OMC against EPA.  As a result of these suits, EPA conducted a series of

studies to assess the nature and extent of environmental problems in air,

surface water, ground water, soils and sediments of Waukegan Harbor and North

Ditch areas and southern Lake Michigan.

-------
                                     - 3 -
These studies included sarrpling studies:

     An Engineering Studv for the Removal and Disposition of PCS Contamination
     in the Waukegan Harbor and North Ditch at Waukeqan Harbor, Addendum to
     Final Report.  Prepared for USEPA Region V, Chicago, Illinoiir.  Lexington,
     Kentucky:  Mason & Hanger—Silas Mason Co., Inc., May 1981. |

     Hydrogeologic Investigation, Outboard Marine Corporation, Waukegan, Illinois.
     Prepared for USEPA Region V and JRB and Associates.  Madison, Wisconsin:
     Warzyn Engineering, Inc., September 20, 1979.

     CMC Technical and Witnessing Case Support Hydrological Studv. of Ground
     Water, Final Report.  Prepared for USEPA Oftice of Water Enforcement,
     Washington, D.C.  McLean, Virginia:  JRB Associates, Inc. February 10, 1981.

     Sediment and Shore Sample Collection, Waukegan Harbor Slip #3.  Prepared
     for USEPA Region V, Chicago, Illinois, and Mason & Hanger—Silas Mason
     Co., Inc.  Madison, Wisconsin:  Warzyn Engineering, Inc., May 26, 1981.

     Kamauskas, Robert J. Subsurface Investigation, North Ditch Area Outboard
     Marine Corporation, Waukegan, Illinois.  Prepared for USEPA Region V,
     Chicago, Illinois.  Madison, Wisconsin:  Warzyn Engineering, Inc., July 29,
     1980.

     Outboard Marine Corporation, Waukegan Harbor Boring, Waukegan, Illinois—
     C 9791.  Prepared for Mason & Hanger—Silas Mason Company, Inc., and USEPA
     Region V, Chicago, Illinois.  Madison, Wisconsin:  Warzyn Engineering,
     August 5, 198O.

     Sand Sample Collection, Waukegan Harbor Slip No. 3, Waukegan, Illinois—C
     956O.  Prepared for Mason & Hanger-Silas Mason Company, Inc., and USEPA
     Region V, Chicago, Illinois.  Madison, Wisconsin:  Warzyn Engineering,
     Inc., January 6, 1981.

     Sediment and Shore Sample Collection, Waukegan Harbor Slip No. 3, Waukegan,
     Illinois—C 9729.  Prepared for Mason & Hanger—Silas Mason Company, Inc.,
     and USEPA Region V, Chicago, Illinois.  Madison, Wisconsin:  Warzyn
     Engineering, Inc., May 26, 1981.
Mathematical Modeling Studies;

     Thcmann, R.V., and M.T. Kontaxis.  Mathematical Modeling Estimate of
     Environmental Exposure Due to PCB-Contaminated Harbor Sediments of Waukegan
     Harbor and North Ditch.  Prepared for USEPA, Cincinnati, Ohio.  Mahwah,
     New Jersey:  HydroQual, Inc., February 1981.

     Thcmann, R.V., and M.T. Kontaxis.  Mathematical-Modeling Estimate of
     Environmental Exposure Due to PCB-Contaminated Harbor Sediments of Waukegan
     Harbor and North Ditch.  Prepared for USEPA, Cincinnati, Ohio, Mahwah,
     New Jersey:  HydroQual, Inc,, February 1981.

-------
                                     - 4 -
     An Estimate of Sediment Movement in North Ditch,  Waukegan,  Illinois.
     Prepared fos USEPA Region V, Chicago, Illinois.   Champaign,  Illinois:
     United States Department of the Interior, Geological Survey^ 1980.

     Roberts, S.A.  Waukegan Harbor Slip No.  3—PCS Loading RatesT  Prepared
     for USEPA Region V, Chicago, Illinois.  Vihite Plains, New York:  Maicol.T
     Pirnie.  July 21, 1982.

     Volatilization.  Prepared for USEPA Region V, Chicago, Illinois.  White
     Plains, New York:  Malcolm Pirnie., August 5, 19B2.
Biological Studies;

     Harris, Rosalind Mason.  Waukegan Harbor PCS Fish Levels.   Prepared
     for USEPA Region V, Chicago, Illinois.  White Plains, New York:
     Malcolm Pirnie, July 9, 1982.

     - Study titled, "Outboard Marine Corporation Biological Studies Report,
       "February, 1979, prepared bv USEPA, Region V, Central Regional Labora-
       tory.  (This report is not a public document).

     - Study titled, "Effects of PCB's on Plankton," September 8, 1981,  pre-
       pared by Donald C. McNaught.

     - Study titled, "Health Risks Posed to Consumers of Fish Contaminated
       with PCB's from Lake Michigan," February,  1981, prepared by Clement
       Associates.
Engineering Studies:

     An Engineering Study for the Removal and Disposition of PCS Contamination
     in the Waukegan Harbor and North Ditch at Waukegan,  Illinois, Final Report.
     Prepared for USEPA Region V, Chicago, Illinois.   Lexington, Kentucky:
     Mason & Hanger—Silas Mason Co., Inc., January 1981.

     An Engineering Studv for the Removal and Disposition of PCS Contamination
     in the Waukegan Harbor, and North Ditch at Waukegan, Illinois.  Prepared
     for USEPA Region V, Chicago, Illinois. Lexington, Kentucky:  Mason & Hanger--
     Silas Mason Co., Inc., January 1981.

     Volatilization of PCBs During Planned Waukegan Harbor Cleanup Operations,
     Literature Review.  Prepared for USEPA Region V,  Chicago, Illinois.
     Lexington, Kentucky:  Mason & Hanger—Silas Mason Co., Inc., May 1981.

     An Engineering Studv for the Removal and Disposition of PCS Contamination
     in the Waukeqan Harbor and North Ditch at Waukegan,  Illinois.  Prepared
     for USEAP Region V, Chicago, Illinois. Lexington, Kentucky:  Mason & Hanger-
     Silas Mason Co., Inc., January 1981.

-------
                                     - 5 -






The numerous investigations conducted over the years allowed EPA to accurately



define the'site  i/i terms of the.extent and quantity of contamination.  The



studies show that the OMC site is the largest uncontrolled potentpi source of



PCB to Lake Michigan.  More than one million pounds of PCb are present on



site. The PCB is shown to be bioaccumulating in the fish in Waukegan Harbor



and Lake Michigan.  The modeling studies demonstrate that the PCB is leaving



the site through movement of the surface water and ground water, volatilization



to the air and transport of the sediment.






C.   Concentrations of PCB Found in the Sediment;



Sampling data from Slip #3 showed PCB in concentrations up to 520,000 parts



per Trillion (ppm).  It is estimated that more than 3OO,OOO pounds of PCB are  -



contaminating 1O,000 cubic yards of sediment in Slip #3.  Data fron the upper



harbor areas of Waukegan Harbor also shew PCB contamination.  It is estimated



that approximately 5,OOO Ibs of PCB are present in 35,700 cubic yards of sediment



in the upper harbor.  The concentrations found in these sediments are much



smaller than those found in the sediments of Slip 3; the highest concentration



is 5OO ppm PCB. _ Figure 2 shows the average concentration of PCB found in the



various segments of Slip #3 and Waukegan Harbor.





North of the OMC plant, the North Ditch area contains sediments with concen-



trations of PCB exceeding 35,000 ppm.  It is estimated that 495,000 pounds of



PCB are present in 7O,8OO cubic yards of sediment and soils in the North Ditch



area.   Finally, the area of the OMC parking lot contains approximately 277,700



pounds of PCB in 105,800 cubic yards of soil.  The concentrations found in



this soil range up to 5,COO ppm.  Figure 3 shews the areas north of the OMC



plant with concentrations of PCB greater than 50 ppm.

-------
                                     - 6 -






D.   Mechanisms for PCB Release from OMC:



The sampling and modeling studies showed that PCB's are being released from



the OMC si-te to the surrounding environment. Lake Michigan is thF ultimate



receptacle tor most of the PCbs. The mechanisms by which the PCBs are being



released include the air, through volatilization of the pollutant; the sur-



face water, through the flushing of Waukegan Harbor and runoff through the



North Ditch; the ground water, through the slow movement of the ground water



towards Lake Michigan; and sediment transport, through the movement of sediment



with surface and ground water. The rates of release of PCB through each of



these mechanisms were explored in the investigations conducted by EPA.






1.  Air






Although no air -nonitoring for the presence of PCB's was conducted at the



site, modeling was used to estimate rates of volatilization of PCB from UMC.



The concentration of PCB expected in solution at the sediment/water interface



was estimated by mixing contaminated sediment in water, decanting the mixture



and analyzing for the PCB concentration of the water.  This concentration was



used with transport rate equations to estimate the rate of volatilization from



the site.  A volatilization rate of 3.8 mg/m 2 / hr frcm a saturated solution



(based on experiments conducted by General Electric in New York) was assumed.



If volatilization is considered proportional to the concentration of PCB in



solution, calculations based on the volitilization rate and the area of the



site show that approximately 3.3 pounds of PCB per month are leaving the harbor



portion of the OMC site through the atmosphere.  Because that rate would vary



positively with temperature, EPA estimates a total of 12 to 40 pounds per year



of PCB are volatilizing from the harbor.  In addition, it is estimated that



the North Ditch contributes 15 pounds of PCB to the atmosphere per year.

-------
OVTTFALL
                                                    Average
                                                     oo PCS
                                        Total Ai-Ao  (Mucki
                                          31
                                          32
                                          33
                                          34
                                          35
            AVERAGE ?C3 CCNCENTSATION
            IN ^AUKESAN HARBOR 3Y SEGMENT.
133.2
132.1
 36. a
103.2
 30.3

-------
NOftYH
01YCH
                             NORTH SHORE SANITARY DISTRICT
                                            PARKINGL6tV
           FORMER  'CRESCENT
           OUIFALLS 0|TCM
                                     LAKE
                                     MICHIGAN
            SCALE;i">340*
                           OUTBOARD MARINE CORP
                           JOHNSON OUTBOARDS OIV
                                   PLANT NO. 2
                                        FIGURED

                                NORTH  DITCH AREA
                             LEGEND
                                                              OVER 5O PPMPCB
                         EXTENT
OF    PCB  CONTAMINATION
 OVER 5O PPM

-------
                                     - 7 -
 2.   Water  & Sediment:
                                                *

 A great deal of monitoring was conducted to determine the concentrations of
                 •
                                                                 •

 PCB found in the water column and sediments of both the harbor anfi .the North


                                                                1
 Ditch.  In Waukegan Harbor, concentrations in the water column rafcged fr~jm a



 mean of approximately 6 parts per billion (ppb) about 3GO feet from Slip 3 to



 a mean of .07 (ppb) at the mouth of the harbor.  The concentrations in the



 sediments of the harbor are discussed above and shown in Figure 2.  These



 water column concentrations were used with a mathematical model of the



 hydrodynamics of the Harbor to estimate the release of PCB to Lake Michigan



 resulting fron PCB's dissolved in the water column and the transport of PCB-



 contaminated sediment under steady state conditions.  The estimated rate of



 release is 22 Ibs per year.





Sampling in the North Ditch shows the water column concentration, both dissolved



and particulate, in that area to average 7 ppb.  Again, this concentration was



used with a mathematical model of the hydrology to estimate the PCB loading to



Lake Michigan through the North Ditch.  The rate of release from the North



Ditch due to both dissolved PCB's and PCB-contaminated sediment is estimated



to be about 7-20 Ibs. per year.  The results of the sampling of the soils



and sediment is discussed above and shown in Figure 3.




 In addition to monitored sediment data at the site itself, sampling of the



surficial sediments in Lake Michigan indicate the presence of a "plume" of



contaminated sediments moving from Waukegan.   The shape of the "plume" strongly



suggest that Waukegan is contributing to the contamination of Lake Michigan



sediments.  See Figure 4.

-------
                                                             JWUJU
                                      air
Figure 1-6.
Generalized discribucion of PC3 concancracions ia  the
surficial sediaen:s of the southern basin of Lake
ilichigan.  Derived from daca gathered bv Arrasrong
(1980).

-------
                                     - 8 -
 3.   Ground Water:



 Extensive ground water contamination was documented in t.vo comprehensive ground



 water monitoring projects conducted in 1979 and 1980.  The studiefc showed PCB



 in the ground water in concentrations up to 35,000 ug/1.  This studies showed



 the contaminated ground water is moving slowly toward Lake Michigan and «dll



 become a significant source to the Lake in 30 - 60 years.






 The annual rates of release through each media from both the harbor and the



 North Ditch areas is shown in Table 1.





 In addition to the annual release of PCB's from OMC due to normal transport



 mechanisms, the site represents a hazard to environment due of the possibi-



 lity of a large, catastrophic-type release due to extreme storms.  The modeling



 of steady PCB movements lakeward and the assumptions concerning summer season



 meteorological and hydrologic events do not take into account the potential of



 the violent Lake Michigan storms of late fall or winter which cannot, practically



 speaking, be measured and modeled.  The lakeward movement of PCBs out of the



 Harbor during the winter may be underestimated and hence the range of annual



 PCB flux presented should be viewed as conservative.





 In addition, the models cannot account for commercial navigation and recreational



boating have the potential to disturb and expose highly contaminated materials,



directly, through turbulence induced by propellers, These disturbances and



 the major storm events which generate turbulence in the Harbor may sustain the



 continued' exposure of highly contaminated bottom sediments to the water colummn



and hence will promote the surficial redistribution of PCBs throughout the



Harbor.

-------
                            Annual Rates of Release of PCB
                                       from OMC
                                    (Pounds/year)
                                                                     •
                         Ait-
                Surface Water
                     &
                  Sediment
                       Ground Water
Harbor
12-40
  22
   N/A
North Ditch
 15
. 7-20
   N/A
Parking Lot
N/A
  N/A
Future Release
of 8 Ibs/year
                                       Table 1

-------
                                     - 9 -






 E.    Impact" of the PCBs on the Use of Waukegan Harbor;



      1.  Generally



 The presence of high levels of PCBs has prevented the dredging of the harbor



 since 1969 when they were discovered.  Over the years, the harbor has continued



 to silt  in, and its uses have deteriorated.  Sailboat keels are hitting botton.



 The Cement Company has indicated that its ore boats must travel with a half



 load  in order to access the Harbor.  Without removal of the sediment the Harbor



 will continue to lose value to businesses which depend upon it.






 In contrast to the dim prognosis for the future, both the City of Waukegan and



 the Port Authority have massive development plans for the harbor area.  This



 includes condominiums, boat ramps, new streets and a total upgrading of the



 area.  Currently, the City is completing a new 750 slip marina.





 Conversations with the Port Authority have indicated that the issue of uncontrolled



 PCBs had had adverse impacts on economic development.  Implementation of a



 PC3 control will allow the development plan to proceed.





The Corps of Engineers, the Waukegan Port Authority and U.S.  EPA are interested



 in implementing individual projects, which together will result in a program



 that addresses all areas of the harbor and will offer a long term resolution




 to the problem.  The Corps of Engineers wants to establish a regular maintenance



dredging program for the harbor where open lake disposal of dredge spoils can



 be utilized in future years.   Unless the contamination is removed above their



project 'area, this goal cannot be realized because PCB contaminated sediments



will continue to migrate into the area that the Corps dredges.  The high levels



 of PCBs in the harbor is preventing the Corps of Engineers from implementing a



maintenance dredging project which is needed to bring the harbor back to its

-------
                                     - 9 -






E.   Impact- of the PCBs on the Use of Waukegan Harbor:



     1.  Generally



The presence of high levels of PCBs has prevented the dredging of the harbor



since 1969 when they were discovered.  Over the years, the harbor has continued



to silt in, and its uses have deteriorated.  Sailboat keels are hitting botton.



The Cement Company has indicated that its ore boats must travel with a half



load in order to access the Harbor.  Without removal of the sediment the Harbor



will continue to lose value to businesses which depend upon it.





In contrast to the dim prognosis for the future, both the City of Waukegan and



the Port Authority have massive development plans for the harbor area.  This



includes condominiums, boat ramps, new streets and a total upgrading of the



area.  Currently, the City is completing a new 750 slip marina.






Conversations with the Port Authority have indicated that the issue of uncontrolled



PCBs had had adverse impacts on economic development.  Implementation of a



PC3 control will allow the development plan to proceed.





The Corps of Engineers, the Waukegan Port Authority and U.S.  EPA are interested



in implementing individual projects, which together will result in a program



that addresses all areas of the harbor and will offer a long term resolution



to the problem.  The Corps of Engineers wants to establish a regular maintenance



dredging program for the harbor where open lake disposal of dredge spoils can



be utilized in future years.  Unless the contamination is removed above their



project area, this goal cannot be realized because PCB contaminated sediments



will continue to migrate into the area that the Corps dredges.  The high levels



of PCBs in the harbor is preventing the Corps of Engineers from implementing a



maintenance dredging project which is needed to bring the harbor back to its

-------
                                     - 10 -


 full use.  This is having an adverse effect upon", the welfare of the local
                •              -            •
 community.


 2. Socio-economic                                                |

 A cursory survey of the employers in the Harbor area indicates that much of

 the economic activity either is water-dependent or water-related.  The Outboard

 Marine Corporation (manufacture of non-electrical machinery), Larsen Marine

 (rarine sales and services), Falcon Marine (marine contractor), Waukegan Port

 District (transportaion services), the Waukegan Yacht Club (recreation)  and

 the Waukegan Water Filtration Plant (public water supply)  depend upon the

 Harbor and Lake Michigan for their operations.  Huron Cement, and Gold Bond,

 both of which are Divisions of National Gypsum; Larsen Marine;  Falcon Marine;

 the Waukegan Port district and the Waukegan Yacht Club depend upon  a working

 harbor for their operations.


The Waukegan Port District operates the Waukegan Harbor.   The Port  District's

gross revenues during 1980 totalled 5286,950.  The sources of there revenues

 are shown below:

        Gasoline                  $13,000
        Land leases                64,000
        Slip rental                78,000
        Dry moorings               35,000
        Wet moorings                8,200
        Slip hopping               14,000
        Parking lot fees           16,000
        Boat launching             31,000
        Charter Boat permits        6,500
        Temporary docks             7,800
        Interest                    7,500
        Miscellaneous               5,950
        TOTAL                    $286,950

During 1980 there were approximately 43 conmercial ship dockings at Waukegan

Harbor (By telephone Mr. Bruce Lawson,  Deputy Director, Waukegan Port District

-------
                                     - 11 -


and Ms. Susan Du Bois, Gold Bond to WAPORA, Inc."; 19 October 1981).  Shipping
                 •              -            *     '
activity in che Harbor varied widely fron 1969 to 193U.  The number of tons of

cargo hauled over the 11-year period ranged from 538,866 in 1971 po 282,500 in

1930 (US Army COE n.d. and Waukegan Port District 1981).  The decline in shipping

activity during 1980 reflects the nature of the Port shipping activity during

1980 reflects the nature of the Port District's commercial clients.


The Port District currently serves two commercial clients: Huron Cement and

Gold Bond.  Huron Cement is located on the northwest side of the Harbor between

Slip #3 and Slip #1.  'Gold Bond is located south of Slip #1 (Figure 1-2).

During 1930, 282,500 tons of bulk csment and gypsum rock were hauled into the

Harbor for these two clients, respectively.  Because Huron Cement and Gold

Bond both supply building materials for the construction industry in the Chicago

metropolitan area their need for raw materials is directly related to the

level of construction activity taking place.   During 1980 and 1981, construction

activity in the Chicago area was relatively slow, and shipping activity at

Waukegan Harbor likewise declined.  Huron Cement and Gold Bond both dock at

Slip #1 to unload cargo.  Depending upon the size of the ship, Gold Bond's

ships either back out of the Harbor or back around into Slip #3 to swing the

bow around.  Huron Cement's ships back around into Slip *3 and leave the Harbor

bow first.


Falcon Marine is located on the east side of the Harbor adjacent to the Waukegan

Water Filtration Plant.  Falcon Marine docks between four and eight barges

along the seawall.  The barges are between 30 and 42 feet wide and 100 to 120

feet long.

-------
                                     - 12 -






Many  types of  recreation facilities and opportunities are available in the



Waukegan Harbor "area; the foremost of these is fishing.  The Illinois
of Conservation, Division of Fisheries and Wildlife has estimate* that Waukegan



Harbor and offshore areas experience the heaviest fishing pressure of any area



along the Illinois coastline of Lake Michigan.  Although the majority of the



recreational uses of the Harbor are related to fishing, a substantial amount



of pleasure boating, sailing, picnicing, and other water-related activities



also take place.






The 10 public boat launching ramps at the Harbor are open for use on April 1



each year and the 117 slips and 41 mooring cans are open by 1 May.  There also



are 75 dry parking spaces for boats.  Demand for the boat moorings is quite



high, and the current waiting listed contains more than 600 applications.





A considerable amount of boat-launching activity occurs at the Harbor.  During



the period April 1931 through 31 July 1981, 5,755 boat launching tickets were



sold (a S3 fee is charged).   This does not account, however, for the approximately



450 season-pass holders who have unlimited boat launching privileges.





Larsen Marine Service, Inc. , is located adjacent to Slip *3 at the north end



of Waukegan Harbor and is the largest lakefront yacht dealer in the Chicago



metropolitan area.  Because Waukegan Harbor is the only protected public harbor




along the northern Illinois shoreline, a large amount of recreational boating



activity is concentrated there.  Larsen Marine is the only marine sales and



services' company located directly on Waukegan Harbor.  The company provides



yacht brockerage for new and used power boats and sailboats and offers complete



marine repair services.  A crane operated . boat hoist is also available for



removal and storage of all size. classes of boats.  These services are of

-------
                                     - 13 -






considerable importance to recreational boaters -in the  region  because  there



are no similar commercial facilities on the'northern Illinois  coastline.
                                                              nuroer
Currently, the Illinois Department of Conservation limits the nurter of charter



boats which operate out of Waukegan Harbor to 35.  Of this total, 27 are members



of the Waukegan Charter Boat Association;  members include eight 4-passenger



boats and nineteen 6-passenger boats.  The Charter Boat Association estimates



that its 27 boats have between 12,000 to 15,000 paying clients.





This boating activity results in substantial fishing pressure.  There are 14



public boat access points along the Illinois shoreline to serve the entire



metropolitan region.  Although Waukegan is 40 miles north of Chicago, the



major population center of the region, the Waukegan area experienced the greatest



fishing pressure along the entire Illinois shoreline of Lake Michigan.  This




estimation is based on a 1979 sport fishing creel survey conducted along the



Illinois portion of Lake Michigan by the Illinois Department of Conservation.






The results of the creel survey indicated that the heaviest pier/breakwater



fishing pressure was experienced at the Waukegan Harbor and that the heaviest



boat fishing pressure.was experienced offshore from the Waukegan Harbor.  The



survey personnel estimated that a total of 222,918 angler hours were expended



for pier/breakwater fishing along the Ilinois shoreline.  At the Waukegan



Harbor, the 1979 estimate of angler hours was 45,974, or 21% of the total.



However, the average number of fish caught per hour at the Waukegan Harbor was



the second lowest rate of the 14 sites listed.





The estimates for the trolling fishery also indicated that more angler hours



were expended in the Waukegan Harbor area than at any of the other locations.



Of the total 601,426 estimated angler hours spent trolling, 184,554 (31%) were

-------
                                     - 14 -



                                                 •

 allocated to Waukegan Harbor.  As for the pier/breakwater fishery, the number
                  •               -            •


 of  fish caught per hour was relatively low.  The majority of the iish caught



 by  both pier/breakwater and trolling fishing *>ere coho salmon.  Hilf of all



 the coho caught from the pier/breakwater fishery were from Waukegan Harbor.



 The Waukegan Harbor trolling fishery accounted for 34% of all the coho salmon



 caught along the Illinois shoreline in 1979.





 Although significant fishing activity took place on the Waukegan breakwater



 and from boats in 1979, relatively little shore fishing occurred at the Waukegan



 Harbor.  Of the 285,374 angler hours estimated for the 1979 shore fisher/,



 only 1,179 (0.4%) were  allocated to the Waukegan Harbor.






 II.  TOXICITY OF PCBS



 The toxicity of PCBs to humans was demonstrated graphically and tragically in



 1963 when rice oil in Yosho, Japan, was accidentally contaminated with PCBs.



 Since then, extensive information has been collected concerning the toxicity



 of  the different types of PCB compounds in varying concentrations.  The compounds



 have been found to be toxic and uniquely persistant in the environment and the



 human body.





The best summary of the information available on the toxicity of PCB was compiled



 in August 1982 by the Health and Environmental Review Division within the



Office of Toxic Substances for the TSCA rulemaking on PCB.  This summary of



health information concludes that PCBs are linked to a myriad of health and



 environmental problems, including the following:




   o  carcinogenic effects in rodents - especially liver cancers.



   o  immunosuppressive activity.

-------
                                  - 15 -
o  Tremendous bioaccumulation of PCB occurs in the food chain Fish flesh
   often contains several thousand times the concentration of PCB found in
   the a*nbient water.

o  ambient exposure impairing reproduction potential of coimierqhal fisheries
   and mink.                                                  |

o  high PCB levels found in birds, especially in gulls and other carnivorous
   birds.

o  chloroacne - a painful, scarring disease that is frequently accompanied
                by other problems including deformity of bones and teeth,
                headaches, dizziness, fatigue, abdominal pain and vomiting.

o  adverse affects on the menstrual cycle of rhesus monkeys.

o  changes in menstruation in humans.

o  reduction in rate of conception, reduction in implantations, difficulty
   in carrying offspring to term.

o  PCBs are inducers of hepatic microsomal enzymes (role of producing sex
   steriods).

o  increase production of androgen and testosterone in rats.

o  increased liver to body weight ratios in rabbits.

o  the uteri of 1,254 rabbits were about 1/2 the size of the control group
   after exposure to PCBs.

o  Reproduction in mink appears to be extremely sensitive to PCBs; reproduction
   was totally inhibited at an exposure of 5 ppm for 10 months.

o  PCBs have been shown to cause adverse effects to test animals in all
   four areas of tertogenicity, which includes 1) death to the developing
   organism, 2) structural abnormalities, 3) growth retardation and 4)
   development of functional deficiencies.

o  PCBs have been found in mothers milk. Infants PCB concentrations increase
   with exposure time and may cause morphological alterations of the
   liver at the ultracelluar levels and increased susceptability to viral
   infections because of increased innnunosupressive activities of PCBs.

o  Infant monkeys have died prior to weaning when exposed to PCBs because
   of rudimentary thymuses, small spleens and lyrtph nodes.

o  excess liver cancer deaths observed in workers exposed to PCBs at high
   concentrations.

o  PCBs induced lesions in the digestive tract which may be precursors to
   carcinomas.

-------
                                     - 16 -
III.  THREATS TO PUBLIC HEALTH AND THE ENVIRONMENT POSED BY PCBS  AT THE OMC
      SITE
                                                                i.
A.   Threats to Public Health;

A toxic ccrpound or chemical poses a threat to public health only^to the extent

that the public is exposed to the compound or chemical.  Risk is always a

function of toxicity and exposure.  PCBs have been shown to be toxic.  There

are several routes by which the public is exposed to this toxic compound at

the OMC site and by which is released to Lake Michigan.  These routes of public

exposure are discussed below.


I.   Drinking Water

The City of Waukegan maintains an emergency drinking water intake in Waukegan

Harbor.  Although this intake is rarely used and has been used only six times

in the last fifteen years, it is an integral component of the Waukegan Water

Supply.  Should the City need to utilize the emergency intake, PCB contaminated

sediment and water may be introduced into the drinking water system.  The City

has its main drinking water intake about 1 mile off shore in Lake Michigan.

At the request pf the Lake County Health Department, USEPA conducted a survey

of the water supply for PCB's.  USEPA sampled the raw water, finished water,

and drinking water sludges.  Low concentrations of PCB's were found in the

drinking water sludge samples.  This indicates that PCB's are getting into the

system, but are being adequately removed by the treatment system.


2.   Ingestion of Contaminated Fish

The waters of Lake Michigan are heavily fished for both commercial sale and

sport.   The near shore area adjacent to the OMC site is often fished.  A 1979

sport fishing creel survey by the Illinois Department of Conservation indicates

that the Waukegan Harbor area accounts for 21% of the angler hours expended in

-------
                                      - 17 -






 Illinois for pier/breakwater fishing (45,000  hoars).   Even Waukegan Harbor



 itself,  although""No Fishing" signs are displayed,  has occasionally been  used



 for fishing".  All fishing near the site,  both in Waukegan Harborffind Lake



 Michigan presents a potential public exposure to PCB  oecause PCBs are bio-



 accumulated by fish from the water in which they live and from the insects and



 plants they ingest.  It has been demonstrated that  fish bioaccumulate PCBs by



. 100,000  or more ti;nes the ambient water concentrations.





 In USEPA studies on Lake Michigan fish,  results ranged from concentrations of



 2.7 ppm  to 187 ppm PCB in fatty tissue for all species.   Although it is  impossible



 to determine the exact source of these PCB's,  clearly PCB in Lake Michigan



 fish is  a problem and clearly the CMC site is a source of PCB to the Lake.





 It is very difficult to calculate the extent  of human exposure to PCBs through




 the consumptions of contaminated fish because the levels of PCBs in fish  differ



 significantly as does the amount of fish consumed by  different persons.   Based



 on a study conducted by the Michigan Department of  Public Health (Cordle, et.



 al., 1978),  it is considered likely that persons who  consume large amounts of



 contaminated Lake Michigan fish are exceeding the recommended daily limit.



 Based on the Clements Associates study on the "Health Risks Posed to Consumers



 of Fish  Contaminated with PCB's from Lake Michigan" (1981), heavy consumers of



 Lake Michigan fish contaminated with PCB may  be exposed to a one in one  thousand



 excess risk of developing cancer with a lifetime of exposure.  Obviously,



 those who consume fish from the highly contaminated Waukegan Harbor area  are



 also likely to be exceeding the recommended daily limit  for PCB consumption.





 3.   Dermal Exposure



 Another  route of public exposure to the PCBs  at the OMC site is related  to the



 recreational and commercial activities conducted around the site.  Pleasure

-------
                                     - 18 -





 boats moored,  launched and then removed from Waukegan Harbor are coated with
                •               -            "


 contaminated harbor muds and silts.  Boat owners and workers areiexposed to



 PCBs when they work on the boats.  Boats may be removed from theEiarbor, brought



 to the owner's home and washed, spreading PCB contaminated material to the



 owner's property.





 In addition, the North Ditch discharges to a beach area, meandering across the



 sand until it reached Lake Michigan.  The public has access to this beach for



 walking or playing.





 Because of the level of public activity in and around the OMC site, public



 exposure to PCBs through the skin is likely.





 4.   Inhalation



 As was discussed above, PCBs are volatilizing from the OMC site in significant



 quantities.  These volatile PCBs present yet another route of public exposure.



 Twelve percent of Waukegan's work force is employed adjacent to the harbor.



 In addition, many people utilize the harbor for recreational boating about



 eight months per year, with numbers peaking in the hot summer months when



 volatilization is highest.  A recreational beach is located due east of harbor.



The prevailing winds blow east and thus beach users are likely to be exposed



 to PCB contamination.





B.   Threats to the Environment:



 In addition to the threats to public health posed by the site, the PCB's at



 the OMC site present a significant threat to the environment of Waukegan Harbor



and Lake Michigan.  As described above, water samples taken from Waukegan



Harbor and the North Ditch have mean concentrations of PCB of 0.6 ppb and 7.0



ppb, respectively.  The USEPA Ambient Water Quality Criteria for the protection

-------
                                     - 19 -






 of  fresh water aquatic life from chronic toxicitydue to PCB is 0.014 ppb.



 Water column concentrations at the site far exceed the ambient watir quality



 criteria,  the concentrations found in water samples taken in Lake Michigan



 offshore frcm Waukegan Harbor showed PCB concentrations at 0.01 ppb, slightly



 less  than the water quality criteria.





 Research has shown that small amounts of dissolved PCB's, such as those found



 in  Lake Michigan, can inhibit phytoplankton photosynthesis (McNaught et al.



 1981).  Because phytoplankton are at the base of the Lake Michigan food chain,



 inhibition of phytoplankton photosynthesis will limit the poundage of sport



 fish  that can be produced in the Lake.  In one experimental study, PCB concen-



 trations of 5 ng/1 inhibited nanoplankton photosynthesis by 5.7% (McNaught



 et  al. 1981).  Concentrations of 100 ng/1 and 500 ng/1 inhibited nanoplankton



photosynthesis by .8.9% and 18.9%, respectively (McNaught et al.  1981).  PCB



 concentrations of 5 ng/1 are comparable to the levels found in the open waters



 of  Lake Michigan, and concentrations of 500 ng/1 are corparable to present



 levels in Waukegan Harbor.





     The PCB's in-Waukegan Harbor present a special danger to immature fish.



To ensure a self-sustaining community of fish, a certain critical percentage



must survive from the larval stage to maturity.  If the critical percentage



 that must reach maturity is not attained, fish population will decline and a



stocking program will be required to maintain the population.  If the cause of



 the decline is not corrected, a continual stocking program is required.  Wilford



 (1980) found a direct correlation between fish fry mortality rates in Lake



Michigan lake trout and PCB and DDE levels in the water column.

-------
                                     - 20 -


     Concentrations of PC3s in Waukegan Harbor are not evenly represented by
                                                                 •
 the water column  levels.  PCBs tend to concentrate at levels abovfe .those found

 in the water column in two sections:  the surf icial bottom sedim^t and the

 air/water interface.  Increased concentrations in these sectors result from

 the tendency of PCBs to partition into organic compounds by adsorption.  The

 organic fraction  can move PCBs downward with settling particulate matter or

 upward into the plankton, oil, and foam at the air/water interface, and held

 there by what is  generally referred to as "the surface film effect."   Bottcm

 sediments are used as a food source for bottom feeding fish and are ccmmonly

 the depository for developing eggs and larvae when used as a spawning ground.

 In addition, the  surface film is a rich food source to many types of young

 fish (Wangersky 1976).  Although documentation does not yet exist, it is

 speculated that an increased biological hazard exists for fish feeding on

 bottcm dwelling organisms of Waukegan Harbor and outlying water, or using the

Waukegan area sediments as a spawning ground.


 In the central Waukegan Harbor area, fish would encounter PCB concentrations

 in the surficial sediments that range from 8 to 3,600 ppm (Armstrong 1980) and

which are more than 20,000 times more concentrated than the levels typically

 found in the Waukegan Harbor water column.  Although no PCB concentration data

are available for the surface film sector of the Harbor, the known affinity of

PCBs to become adsorbed into organic compounds and the increased presence of

such ccnpounds at the air/water interface suggests that PCBs may have an

 increased adverse impact on the biota through this sector.


Only twenty-nine  fishes (9 total species,  6 game species) have been captured

 in Waukegan Harbor for the purpose of determining bioconcentration factors

 for PCBs.  The relative scarcity of sane fish in the Waukegan vicinity as

-------
                                     - 21 -




evidenced by the low number of species captured may be related to the high
                 •

levels of PCBs and other pollutants found in the area.           i




In an effort to show the environmental inpact of the OMC site of take Michigan,


the movement of PCB's from the project area to the Lake was compared for the


input of PCB's to the Lake from other sources.  The vast size of the lake


makes this sort of analysis misleading;  Lake Michigan is so large even 55 Ibs


or so per year from a single source does not appear significant.  A nearshore


sector with a 10 kilometer radius was selected as an area of localized impact


outside Waukegan Harbor.




Although the 10-kilometer radius area was selected arbitrarily, it represents


a reasonable-sized area that excludes possible influences from other sources.


such as the City of Chicago to the south.  The area of the Lake within this


radius also coincides roughly with the eastward extent of the unstratified,


nearshore zone of Lake Michigan.  The long-term average PCB mass load from the


combined Waukegan Harbor/North Ditch system to Lake Michigan may be conservatively


estimated to be 22 to 44 pounds per year (modeling of water and sediment only).


If it is assumed that the dry deposition load of PCBs to the entire Lake is


approximately 550 to 1,100 Ib/yr and that rainfall and dry deposition are


uniform over the Lake (USEPA 1981), then the 22 to 44 Ib/yr PCB load from the


Waukegan Harbor/North Ditch area could represent frcm 49% to 80% of the total.


load to the near-shore (10 km) sector.  See Figure 5.

-------
 INPUT
INP'J'
                          •.:-••
                      ,'.; .  • -.' •:.../»•??:».\.  ,
The rar.gs  asd di s t rib u t
the searshors 3«ctar c:
•aukegaa '-arior ('iycrc^
                                     er  c:  the tctai  ?C3 leads  :

-------
                                     - 22 -

 IV.   EVALUATION OF THE  "NO ACTION" ALTERNATIVE   ";
                  •                                                *
 Studies conducted by EPA have shown that high concentrations of P(3 'exist in
 all segments of the CMC site (Waukegan Harbor, North Ditch, and the OMC parking
 lot).  In addition, sampling and modeling studies have shown that the PCB's
 are leaving the site through the flushing of water from the Harbor and the
 North Ditch, the movement of ground water toward lake Michigan, the transport

 of sediment into Lake Michigan ana the volatilization of PCB's to the atmosphere.

Under the NCP, source remedial actions are appropriate if a substantial con-
centration of hazardous substances remain at or near the area where they were
originally located and inadequate barriers exist to retard migration of sub-
stances into the environment.

A source control action is appropriate at the OMC site because the investigations
 regarding the human health and environmental impacts of exposure to PCB's have
shown that PCB's are both toxic and uniquely persistant.  The release of PCS
from the site was evaluated and it was determined that the release is resulting
 in a public exposure to PCB.  These evaluations showed that the public is
being exposed or potentially exposed to the PCB's released frcm OMC though the
drinking water supply, consumption of contaminated fish, skin contact with
contaminated material, and inhalation of volatilized PCB's.

In addition, the PCB's being released frcm OMC are having a negative impact on
the environment of Waukegan Harbor and the nearshore area of Lake Michigan.
Finally, a no action alternative may result in indefinite postponement of the
dredging of the navigation channel.  If routine channel dredging were precluded,
deep draft shipping activity would eventually cease as a result of sedimentation
at the Harbor mouth.

-------
                                      - 23  -





 Although the economic contribution  of the  Harbor  industries  that are dependent



 on a working harbor for their operations to  the overall economy of jthe area



 has not been-quantified, the  impacts  associated with a further curtailment in



 use of Harbor would be substantial.   Such  a  curtailment would be expected if



 no action was taken to abate  PCS contamination in the Harbor because of the



 potential hazards associated  with Harbor maintenance activities.





 Because of the known and potential  threats to public health, welfare and the



 environment  specified  above and associated with the release  of of PCB's from



 the QMC site, remedial action has been determined to be necessary to provent



 and mitigate the migration of PCB's from the site and the spread of PCBJs to



 Lake Michigan and the  food chain.





 Under CERCLA, the remedial action taken to control the PCB's must be determined



 to  be cost effective based on engineering, environmental and economic criteria.



 EPA conducted a feasibility study to evaluated the potential remedies for the



 site.





V.   FEASIBILITY STUDY





     A.  Extent of Remedyt



Before assessing the various options, it is  necessary to consider the quantity



of contaminated soil or sediment to be controlled.  The quantity is dependent



on  the concentrations of PCB which must controlled to protect the public health



and environment.  EPA has determined that all soil and sediment contaminated



 to  50 ppm or greater must be  controlled.  This limit was based upon modeling



of  the Harbor done by Hydroqual (1980).  Using a hydrodynamic model of water



and sediment transport, Hydroqual estimated the flux of PCB to Lake Michio--

-------
                                     - 24 -




 if sediments in the Upper Harbor and Slip No. 3 are contaminated with 500,
                                                *

 100, 50, 10 and 1 ppm PCB.  The modeling studies-showed that if all sediments


 contaminated to greater than 100 ppm are contained or removed frcji the Harbor


 and steady state conditions ar-a assumed, the flux of ?CB to Lake flichi^an will


 approach zero, the water column concentrations in the Harbor itself will be


 reduced to less than 0.02 ug/1, the ambient water quality standard, and fish


 residing in the Harbor will not accumulate PCB to greater than 5 ppm, the FDA


 standard.




These modeling studies did not address the turbulence introduced into the


Harbor by boat traffic and heavy storms, however, and this turbulence may


 introduce as much as 2 pounds per year of PCB would be released to Lake Michigan


 if the sediments are contaminated to 100 ppm.  To lower the estimated release


of PCB from the Harbor and provide some margin of safety for the fish in the


Harbor, it is necessary to dredge so that the sediments remaining will have


concentrations of PCB less than 50 ppm.  Although there is no modeling available


 for the area north of the CMC plant, considerations similar to those regarding


 the Harbor area suggest that 50 ppm is an appropriate level of cleanup for the


whole site.  In addition, such a level of cleanup would ensure that the material


excavated as part of construction of the slurry walls would not require off-site


disposal at a chemical landfill.  Finally, a 50 ppm level of cleanup provides


a consistant objective for the cleanup of the entire site.






     B.  Screening of Alternatives




To determine the most effective way to clean up the sediments contaminated to


greater than 50 ppm PCB.  EPA evaluated more than fifty treatment alternatives


and technologies.  These alternatives included in place destruction of the PCB


with UV/ozonalysis, biodegradation and oxidation; in-place fixation with

-------
                                     - 25 -
 sorbents and seals;  in-place separation of the PCB and removal; removal of the
                 •
 contaminated =oils and sediment; alternatives to bypass the contaminated material;

 water treatnent technologies; onsite storage and offsite disposalFor storage/

 disposal.


 Although there is a  lot of research on innovative methods of destroying or

 fixing PC3's and several alternatives are potentially promising, there are

 relatively few technologies that have been proven to be effective on PCB

 contaminated soil and sediment.  In reality, the only proven feasible technologies

 approaches available are the traditional alternatives of (1) excavation and

 offsite disposal or  incineration and 2) containment of the material on site.

 The offsite option of incineration was screened out because it was judged to

 be an order of magnitude more expensive than land disposal.  Thus, the two .

 options evaluated in detail were offsite disposal in a landfill, and onsite

 containment.  The variations on these primary alternatives were evalutated in

 detail to determine  the best way of accomplishing each option.  The combination

 of treatment technologies considered most appropriate for each of the two

 generic alternatives is described below.


     C.    Excavation and Offsite Disposal;


 If implemented in Waukegan Harbor, an offsite disposal option would require

several steps.  A sediment dispersal control device would be installed across

 the south end of the upper Harbor to ensure that sediment disturbed during

dredging does not escape to Lake Michigan.  Sediments contaminated with PCBs

 would be removed with a hydraulic dredge (a suction line) and the sediment

 slurry pumped through a pipeline to an initial solids dewatering lagoon.

-------
                                     - 26 -






Because the hydraulic dredge cannot penetrate the area of deep contaminated



sand and silt near the OMC outfall, a mechanical dredge inside a single shee



pile cofferdam would be used to remove this material.





The dredged solids would be dewatered, fixed and transported to a disposal



site meeting TSCA standards for PCB's.  All removed water and process water



would be routed to a water treatment plant for suspended solids and PC3 removal



(to 1 ppb PCBs, an effluent standard based on Best Available technology from  .



the Mason and Hanger analysis), then discharged to the harbor or to a sanitary



sewer.  During excavation and dewatering, volatiliation of PCB's is likely to



increase because the highly contaminated sediments will be exposed.  This



volatilization will be temporary and will be minimized by using best management



practises.






In the areas north of the OMC plant, the excavation and off-site disposal



would be somewhat simpler because underwater dredging would not be necessary.



A bypass would be constructed to divert surface water flow around the highly



contaminated areas of the Crescent Ditch and Oval Lagoon directly to Lake



Michigan.   The soils would be dewatered in place using well points and pumps,



excavated with a backhoe or front end loader, fixed with portland cement or



another fixing agent, cured and transported to a disposal site meeting TSCA



standards.  Well water would be routed to an onsite water treatment plant for



suspended solids and PCB removal (to 1 ppb PCBs), then discharged to the lake



or to a sanitary sewer.  Because the material in the Parking Lot area is not



expected to be flowable, the intermediate step of hydrating the soil with a



fixing agent is considered unnecessary.  During excavation, the volatilization



of PCB's is likely to increase beause the highly contaminated soils will be



exposed.  This volatilization will be temporary and will be minimized by



using best management practises.

-------
                                  - 27 -




 The  excavation  and  offsite disposal options are the most reliable remedial
                 •

 alternatives  for the OMC site.  The CMC site is located immediately adjacent

                                                                 L
 to Lake Michigan.   The Waukegan Harbor portion of the site is hycffologicaliy


 connected to  Lake Michigan and the northern are^s of tne site have ground


 water only three feet below the surface.  Sediment and soil from the area is


 continuously  transported to the Lake.  By excavating and removing the PCS


 contaminated  material from the site, the transport of PCS to the Lake, and the


 accompanying  threat to public health and the environment is stopped.  There


 will no longer  be high concentrations of PCB adjacent to the lake so all of


 the  threats described earlier are eliminated.  Under this alternative, the PCB


 contaminated  material would be disposed of in a chemical landfill as defined


 under the PCB regulations (40 CFR 761).  This type of landfill is designed


 specifically  to contain hazardous material and is located so that the physical


 environment will not act to deteriorate the containment cells.  The EPA, by


 promulgating  the PCB regulations, has established that chemical landfills as


 defined in the PCB  regualtions are safe, reliable receptacles for PCB contaminated


 material.




     D.  Containment On-Site




The other generic type of alternative available for dealing with the PCB


contaminated  material involves containing the material on-site in such a way


 that the release of PCB's to Lake Michigan is prevented.  There are two basic


ways to contain the material onsite; a lined landfill meeting the requirements


of TSCA onsite or a containment cell using the existing glacial till as a


bottom.




Upon analysis of the TSCA landfill option it became apparent that it is impossibl


 to build a disposal facility meeting all of the TSCA requirements and it is

-------
                                     - 28 -






complicated and expensive to build one approximating those requirements.  It



is  impossible to"build a TSCA landfill because such a facility must be placed



"above the-historical high ground water table." In addition, "fl
-------
                                     - 29 -



inpermeable clay cap.   Ground water monitoring"-welIs would be installed around
                •               -
the site for detection of any future PCB migration.
                                                        fpass would b
 In the area north of the OMC plant, a gravity pipeline bypass would be con-sir-cte-

 to divert surface water flow around the highly contaminated areas, the Crescent

 Ditch and Oval Lagoon.  This bypass would collect drainage from the storm.

 drain (that flows north at  the west edge of CMC's property), from OMC plant

 roof drains, and from regraded areas north and south of the Crescent Ditch and

 discharge it to Lake Michigan.


 It would be constructed south of the sheet piling just north of the east-west

 portion of the North Ditch.  The Parking Lot area would be regraded to divert

 surface water flow to catch basins.


 Containment will -effectively control the major mechanisms for the release of

 PCB from the OMC site.  The volatilization of PCB will be prevented because

 the containment cells will be capped with several •" ^t of impervious material.

 The transport of contaminated sediment will be eliminated because the sediment

 will contain behind impermeable slurry walls.  Finally, the contamination of

 surface water with PCB will be eliminated because the water will no longer be

 in contact with PCB contaminated sediment.


Because no slurry wall is completely impermeable, the containment cells will

 release very small quantities of PCB very slowly to the ground water.  Based

on an overall permeability of 10"^ on/sec, migration of PCB's through 2 ft

 slurry, walls around the containment cells will disperse about 0.003 Ibs of PCB

per year.  Assuming the same permeability for the glacial till, migration

 through a one foot layer of glacial under all the containment areas will disperse

 about .03 Ibs per year.  If cracks occur in the slurry wall or if pockets of

-------
                                     - 30 -






perrreable material are present in the glacial till, this dispersion will occur



faster.  These rates of dispersion, however, are much less than tfte 55 - 1'j'j



Ibs per year EPA models shows are being released under present conditions.








VI.  THE COST EFFECTIVE REMEDY





Because of the problems of reliability of containment cells built in proximity



to Lake Michigan, containment is considered less effective than offsite transport



and disposal of the PCB contaminated material at a chemical landfill as defined



by the PCB regulations.





The Environmental Protection Agency has consistently held that the public



health risks associated with PCB's, particularly high concentrations of PCB's,



are such that the release of PCB's into the environment must be strictly



controlled.  Because it is impossible to build a TSCA landfill on a site adjacent



to and in Lake Michigan, containment on site is not consistent with the Agency's



basic regulatory position regarding PCB's or EPA's definition of cost-effective-



ness in the National Contingency Plan.  Thus, the excavation and offsite



disposal option is considered the only remedial action for the OMC site which



effectively mitigates and minimizes risk to public health and the environment.





In defining the most cost-effective technique for accomplishing excavation



and offsite disposal, several options were evaluated.  These options involved



alternative methods of dewatering the material dredged and excavated from



Waukegan Harbor and the area north of the site.  The options available for the



dredged sediments in the Harbor are:





1.  Dredge - Dewater in Lagoon - Fix - Dispose



2.  Dredge - Dewater in Barges - Fix - Dispose



3.  Dredge - Dewater in Lagoon - Dispose

-------
                                      - 31 -


 Option 2, which requires dewatering of the sediments in barges is not a feasible

 option for' the extremely large quantities of material which will oe dredyed

 from the Ugper Harbor area.  The minimal savings in dewatering thL dredged

 sediments from Slip 3  in barges would be offset because the simplicity of one

 technique and economies of scale attained by treating the sediments in the

 Slip and the Upper Harbor in the same fashion would be lost.


. Option 3, would depend upon evaporation to dewater the dredged sediments.

 Although this is technically feasible, the evaporation would result in

 significant quantities of PCB being volitilized from the highly contaminated

 sediments.  It is estimated that as much as 63 pounds/day PCB would volitilize

 during dewatering.  The public health and environmental impacts of this remedy

 are too significant to consider it any further.


 The most cost-effctive remedy for the excavation and disposal of material  from

 the Waukegan Harbor is to Dredge -Dewater in Lagoons - Fix and Dispose.


 For the contaminated material north of the site, there are options for excavating

 and dewatering the material.  These options are:

                          Excavate - Dispose
                          Excavate - Fix - Dispose

 The fixation step is necessary to ensure that the material is not flovable,

 that is,  that it will not spill as a liquid.   The materials to be removed  from

 the Oval Lagoon/Crescent Ditch area are expected to be as wet a dredge spoils

 and, as such, the material will need to be dewatered or "fixed" before it  is

 safe to transport it in trucks, etc.


 On the other hand, the material in the parking lot expected to be dry after

 the ground water is drawn down with pumping wells and it will not spill as a

-------
                                     - 32 -


 liquid, even without fixation.  Therefdre for material in the parking lot the

 fixation st3|.--  is not considered necessary. '


 Based on the above analysis, the cost-effective remedy for the 01C site is:

     Dredge - Oewater  in Lagoons-Fix-Dispose for
                Waukegan Harbor                $35,500,000

     North Ditch Area
        Excavate - Fix - Dispose               $26,820,000

     Parking Lot
        Excavate - Dispose                     $12,570,000
        Total               '                   $74,890,000



     This remedy would have no adverse impacts on the future use of the land

because all contaminated material will be removed from the site.  All areas

would be filled with clean material and graded to preproject elevations.



VII.  FUND BALANCING


     Under section 300.68(k) of the National Contingency Plan, EPA is required

to balance the need for protection of public health, welfare, or the environment

against the amount of money available in the Hazardous Substance Response

Trust Fund (Fund) in selecting a remedy.  EPA must preserve its ability to

respond to other sites which present or may present a threat to public health

or welfare or the environment, taking into account the need for immediate

action. -In evaluating the appropriate extent of remedy for OMC, EPA must

consider the need to respond to other releases with Fund monies.


Because the estimated cost to implement the cost-effective remedy for the

CMC site identified above exceeds $70 million, EPA has conducted an analysis

-------
                                     - 33 -






of  Fund  assets  in which expected .Fund receipts'are. compared with expected



future needs- for remedial actions at sites curr-jntly listed on the Rational



Priority List.   In addition, we have considered the expected experxlit'jres for



immediate and planned  removals and other program neaJs.  These analyses have



shown that  implementation of the cost-effective remedy at the CMC site will



have serious impacts on EPA's ability to respond at other hazardous waste



sites.
EPA's Superfund budget prepared for FY 84 allocated $3.4 million for remedial



construction at the OMC site.  The difference between this allocation and the



$75 million necessary to fund the cost-effective remedy is $72 million or



more than one half of the $ 130 million FY 84 budget for remedial investigation,



feasibility studies and construction.  EPA's analysis shows that it" all material



contaminated to more than 50 ppm is disposed offsite, approximately 1UO other



projects currently underway or planned for FY 34 would have to be cancelled.





The situation is not expected to improve in FY 85.  The FY 85 budget for the



entire Superfund program including immediate and planned removals, expected to



be approximately $510 million.  EPA's analysis show that this FY 85 budget



will essentially consume all of the monies left in the Trust Fund.  Of that




$510 million, an estimated $300 million will be available for remedial actions.



The cost-effective remedy for OMC would require 10% of the entire program



budget and 22% of the dollars planned for remedial action.  The program has



identified'more than 60 remedial construction projects which will be ready for



implementation in FY 85.  The total costs of those construction projects will



exceed the $300 million expected to be available.  Thus, if the cost-effective



remedy of OMC is implemented, approximately 8 other construction projects must



be cancelled, assuming an average cost of $6 to $8 million for each project.

-------
                                     - 34 -   .     -.
                                                                   •
In light of the high cost of ths remedy for the OMC site, both in tS^rms of
                                                                   r
dollars and other actions which would have to be foregone, the Agency has
decided to consider other remedial actions for the OMC site.   If the PCB
contaminated material at the site can be controlled to the extent that the
annual release of PCB from the site approaches zero with some reliability and
the relative risk of public exposure to PCB is minimal, then Fund balancing
may be appropriate.  In evaluating other remedial alternatives, the Agency's
objective was to find the least cost alternative which controls the PCB
contaminated material on-site such that the release of PCB's from the site
will approach zero.

VIII.  FUND BALANCED ALTERNATIVE - RECOMMENDED FOR IMPLEMENTATION

In evaluating remedial options for Fund-balancing at the OMC site, on-site was
considered.  As stated above, there are problems associated with the reliability
of onsite containment.  It is impossible to build =» containment cell at the
OMC site that is equivalent to PCB landfills defined in the PCB regulations.
In looking at options for Fund balancing, therefore, the Agency tried to
developed a balanced combination of options that takes into account the lesser
reliability of the onsite containment cell yet minimizes the very expensive
offsite transport and disposal.  Accordingly, the option recommended for
implementation includes both offsite disposal and onsite containment components.
In addition, the recommended option includes extensive post closure monitoring
of the containment cells to ensure their continued integrity.  The multistage
process for developing the fund balanced alternative is described below.

-------
                                     - 35 -






     A.    Development Process



 1.   First Public'Garment Period



 In July 1983, EPA proposed five cleanup actions for the three PCifc contaminated



 areas of  the O1C site.  The actions included both offsite disposal and on-site



 containment components.  Actions 1 and 2 concern Slip No. 3 and the Upper



 Harbor.





 Action 1:
In conjunction with Action 2, below, PCB-ontaminated sediment, sand and silt



would be dredged from the localized area near the former OMC outfall in Slip



No. 3.  An estimated 5,700 yd3 of PCB contaminated material, containing



about 286,500 Ib of PCBs would be removed, fixed and disposed offsite in a



licensed chemical landfill.  The estimated cost is $3,150,000.





Action 2:
A containment wall would be constructed around the perimeter of the western



portionof Slip No. 3, part of the Upper Harbor sediments would be dredged into



the contained area; the con- inment area would be capped.  Approximately 306,900



Ib or PCBs in 21,100 yd3 of sediments would be contained.  The estimated



cost is $6,100,000.






Actions 3 and 4 concern the North Ditch Area.






Action 3:



PCB-contaminated soil would be contained and capped in the Crescent Ditch/Oval



Lagoon area.  The North ditch would be partly excavated to install a bypass



drainage pipe.  The PCB-contaminated soil from the bypass excavation would be



placed in the Cresent Ditch/Oval Lagoon area before capping the area.

-------
                                     - 36 -






Approximately 492,100 Ib of PC3s in 51,400 yd3 of soil would be contained.



The estimated cost is §4,210,000.





The total estimated cost or the five actions is 517,410,000.     |





2.   Second Public Comment Period



Upon further review of the proposed remedial alternative and the comments



 vnerated djring the first public comment period, EPA decided to reexamine



the Slip *3/Upper Harbor portion of the five cleanup actions.  The initially



proposed action provided for containment of all Sediment contaminated to 150



ppm in the Upper Harbor.





The Agency decided consider an alternative which would contain all sediments.



contaminated to 50 ppm remaining in the Upper Harbor.  With the addition of



this material, approximately 310,OOU Ibs of PCBs in 46,600 yd3 of sediments



would be contained in a larger containment cell.  The larger cell would esentialiy



eliminate the water frontage portion of Larsen Marina.  The estimated cost of



Action 2 described above with the increased control to 50 ppm is $9,300,00.



This increased the total cost for the five actions to $20,610,000.  The change



to Action 2 resulted in all of the five cleanup actions providing for containment



or off-site removal of all materials contaminated to 50 ppm.  At the same tine



the Agency decided to consider the possibility of building a containment cell



in the Slip/Harbor area without constructing a replacement slip.





Previously, all of the alternatives in the Feasibility Study regarding the



construction of a containment cell in the Slip/Harbor area included the



construction of a replacement slip.





In March 1984, EPA again opened a public conmsnt period regarding the Feasibility



Study soliciting comment on all of the alternatives.  In addition public comment

-------
                                     - 37 -



 was solicited  regarding  increasing the scope of -the Slip/Harbor containment


 cell  to contain PCB contaminated sediments to 5U ppm and not building a rep
                                                                 •

 slip.   •   -                                                     £ •



 3.    Final Selection Process



After the close of the second comment period in April of 1984, EPA re-examined


 the feasibility study and public comments in order to determine the best approach  "


 for a Fund-balanced remedy for the OMC site.  This examination focused on the


contaminated material in slip 43 and the Upper Harbor.



 During this re-examination the Agency again reviewed all costs and all possible


 technologies available in the matrix of cleanup actions addressed in the feasibility


study.  It became apparent that EPA would assume a risk of greater than expected


costs for contament in slip *3 and that a different combination of alternatives


regarding the Slip #3/Upper Harbor area and the Parking Lot might provide


substantially equivalent environmental benefit at approximately the same cost.





4.   Review of Alternatives



The feasibility study included an alternative to dredge, dewater in lagoons


and remove offsite all sediments with concentration of PCB greater than 50


ppm.   The cost of the alternative is estimated at 321,300,000 and would result


in returning the Slip #3/Upper Harbor area to its original use upon completion


of the action.  There are two primary concerns regarding this alternative; the


cost of the option and the volatilization rate from the sediments during the


two year dewatering period.  Variations in this alternative to provide essentially


equivalent environmental protection at approximately the same cost as the


alternative previously recomended are described belcw.

-------
                                     - 38 -






 Similar Cost:



 The major difference  is cost between containment  in slip *3 and the alternative



 to  dredge~dewat-=r  in  lagoons and dispose ot't'site  resulted from thdTthir-1 corporent;



 the offsite disposal  of the material.  It the material could be disposed onsite,



 the cost  of the  two alternatives is similar.  If, in addition, EPA considers



 the potential risks of costs associated with aquiring access to Slip «3 and



 the Upper Harbor to build a containment cell, the costs of the two are essentially



 the same.





Two possible locations for the final disposal of  the solids could be the Parking



Lot area  and the North Ditch area of the CMC site.  Soth of these areas contain



PCB contaminated sediments and a number of alternatives had been developed



which contemplate  the construction of containment cells in these areas.  The



addition  of material to either of the cells will  not substantially increase



the cost  to build  the containment cell.  As the Parking Lot containment cell



proposed  during  the public comment period is larger than the North Ditch area



cell, the Parking  Lot area is considered more suitable for containment of the



dredged solids from the Slip and Harbor.   Instead of containing 100,000 cubic



yards of  material  and being 5 feet above grade, as it was proposed, this cell



would contain 140,000 cubic yards and be 14 feet above grade, if the material



from the  Harbor  is added.





The present worth  of this option if the material  is disposed on site is



approximately $10,000,000.  Although this is significantly less than the cost



of  this alternative if the material is disposed offsite, it is still more than



the cost  of containing the material in Slip 3.  EPA previously estimated the



cost of containment of all harbor wastes above 50 ppm in Slip 3 at S9.3 mi1



including SI.2 million for construction of a slip to replace Slip 3.

-------
                                     - 39 -




construction without these replacement costs .would be $8.1 million, or SI.9
                 •               -            "

million  less than  the parking lot.  However, if EPA did not build such a slip,
                                                                 •

it might be required to compensate Larser Marine and the other sMp owner f'^r


the property interest needed to build a containment cell in the slip.  For a


varietty of reasons, including  the fact that the exact size of the coantainnent


cell cannot be determined prior to final design, EPA has been unable to obtain


any accurate assessment of the  cost of acquiring the necessary property interest.


However, based on  a review of all the data in the record the Agency has believes


that the costs of  acquiring these rights may be substantial and may, therefore,


significantly reduce the apparent SI.9 million difference between the parking


lot and slip options.




Environmental Factors:




An option to dredge, dewater-in-lagoons and contain on the parking lot presented


the same environmental concerns during the dewatering phase as the option


presented when the material was to be disposed offsite.  The dewatering in


lagoons will depend on evaporation to dewater the sediments and will take two


years.  During this dewatering, a great deal of PCB could volatilize from the


sediment.  To minimize the risks of PCB volatilization from the dewatering


lagoons, the more highly contaminated sediments from Slip 3 (1,000 ppm - 10,000


ppm) would be dewatered and fixed in a much faster process.  This will lower


the concentration of PCB in the dewatering lagoons to below 1,000 ppm and


lower the estimated volatilization from the ponds to less than 1.4 Ibs per


day.  -(The hot spots in Slip 3, with concentration of 10,000 ppm - 300,000


ppm, would be disposed offsite as described in Action 1.  This discussion


relates only to the sediment handled as part of Action 2.)  The step of "fixing"


the higher concentration of PCB contaminated reduces the risk of environmental


harm from volatilization.

-------
                                     - 4U -




 In addition to the environmental effects of the.dewatering of the sediments,


 EPA considered the effects of using the parking lot containment cell to contain
                          *                                       •

 the Harbor"-sedi.Tents.  One effect is an increase in size of the cfcntairjtient cell


 on the CMC parking lot.  The volume of tnis cell will oe expanded*by raising



 the top an additional 10 feet above grade.  The impacts of the expansion of


 the cell were judged to be minor.  The sell was already proposed to be 5 feet


 above grade, the additional 10 feet presented no additional conplications.




Another example of the type of effects considered was a longer construction


 time for the parking lot containment cell which could not be conpleted until


 the sediments are dewatered (up to two years).  This effect was considered to


 have a minimal impact, too.




 Finally, because the parking lot containment cell for the Harbor materials-is



 above grade, any leakage of materials and the integrity of the cell itself could


 be more easily monitored.  Based on analysis of the environmental impacts,



dewatering the Harbor sediments and containing them in a cell on the CMC parking


 lot presents similar environmental benefits to containment of the sediments in



 Slip #3.




 Selection of Containment Site




 Based on the analysis of the cost presented above, the difference in costs is



 less than SI.9 million, possibly substantially less.  However, the parking lot



option may result in some environmental benefit due to ease of monitoring.  In



 addition, the parking lot option has advantages in terms of ease of implemen-


 tation.

-------
                                     - 41 -
A  containment cell .Tuat be built under the OMC parking lot to contain the



contaminated souls in that area.  Long term access to that property it necessary



for  that cell regardless of where the Harbor material is contained.  Jf a



containment cell  is built in Slip 3, long term access to property owned by



Larsen and EJ & J Railroad is also necessary.





Containment of the Harbor material in the containment cell on the parking is



easier for EPA to implement because it will require long term access to only



one parcel of property instead of three parcels.  On this basis, EPA has



concluded that the potential cost difference is outweighed by potential monitoring



advantages and reduction of implementation advantages of containing these



wastes in the parking lot area.








     B.  Waukegan Harbor



         1.  Hot Soots



In some portions of the site, the concentrations of PCB are so high that off-



site disposal is considered to be the minimally acceptable protection of the



public health.  This is the case for those highly contaminated sediment



identified in Slip No. 3.  The extremely high concentrations of PCB's in a



relatively small volume of material mandates that this material be handled



with great care and placed in a highly reliable a chemical landfill, which is



designed to protect public health to the greatest extent possible.





As identified in the feasibility study and previous work prepared by Mason and



Hangar Company, the presence of extreme high concentrations of PCB's exerts

-------
                                  - 42 -
an  unacceptable diffusionary pressure on underlying sediment or towardfany



slurry wall which would be built to contain such material.  Removal offtrie



most highly contaminated material for offsite disposal is necessary to control



the driving force that is causing the PCB's to spread into the underlying



clay.  This is demonstrated by the core data from the slip which shows that in



areas of highest contamination, PBC's have moved downward into the clay and in



areas of lesser contamination the PCB's have not penetrated the underlying



clay.  Thus, if the material is not removed, the containment cell would be



much more prone to leakage.





In  addition, the feasibility study demonstrates that after two years the



containment cells will begin to leak a small quantity of water, based on a



permeability coefficient of 10"7 centiineters/minute.  if the highly contaminated



 •aterial is not removed, the leachate will considerably more contaminated and



thus present a larger threat to public health and the environment.



There is no alternative less costly than the cost-effective remedy that approaches



the effectiveness of off-site disposal.  The costs of off-site disposal of



•these sediments is $3,150,000.





         2.  Less Contaminated Portions of Slip 3 and



             Upper Harbor



The less contaminated sediments in Slip No. 3 and Upper Waukegan Harbor may be
1


Contained onsite.  Because the sediments in this area are contaminated with



'CB's in lower concentrations, the glacial till which is beneath the OMC site



 ill act as an effective seal.  No PCB's have been found in the till under



 oderately contaminated sediments and soils.  Therefore, adequate containment

-------
                                     - 43 -
onsite  is possib-le for these moderately contaminated materials.





This containment will effectively control the major mechanisms for the release



of PC3  from the CMC site.  The volatilization of PCB will be prevented because



the containment cells will be capped with several feet of impervious material.



The transport of contaminated sediment will be eliminated because the sediment



will contain behind impermeable slurry walls.  Finally, the contamination of



surface water with PCB will be eliminated because the water will no longer be



in contact with PCB contaminated sediment.





EPA evaluated two ways to contain this material onsite; dredging the Upper



Harbor to contain the contaminated material in Slip 3 and dredging both the



Upper Harbor and Slip 3, dewatering the material and containing it on CMC



property.  Based on the analyses presented in the discussion in Section A, the



latter option is recommended.





Upon completion of this project the harbor, Slip 3, and the vacant property



can be returned to its existing use.








     C.  Oval Lagoon and Crescent Ditch






Some of the sediments in the Crescent Ditch/Oval Lagoon area of the site are



as highly contaminated as those in Slip #3.  Fund balancing is not appropriate



for these sediments for the same reasons as it was inappropriate for the Slip



#3 sediments; containment does not provide adequate protection of public health



and the environment because the glacial till has been shown to be unable to



adequately prevent migration of that material.

-------
                                      - 44 -
                       •

 Off-site removal and disposal in an landfill as defined in the PCS regulations

 is necessary to ensure the reliability of the containment cell bottcn^and

 sidewalls and to prevent the leachate from the cell from becoming more concen-

 trated due to the highly contaminated material within the cell.


 .Contaminated material remaining after hotspot removal will be contained in

"place through the use of slurry walls and a clay cap.  In addition, the material

 generated as a result of sewer installation will be contained on site.


 This containment structure is necessary to bring annual rates of release rate

 to zero from this portion of the site.  Surface water and ground water flows

 will be removed from contact with the contaminated material.  The containment

 ~°11 will be more reliable because the most highly contaminated material will

  .- removed for off site disposal.  The mechanisms of release of the PCB's will

 be essentially halted by implementation of this alternative.


           a.   Some increased volatilization will take place while the
               construction is underway, but once the clay cap is in place,
               volatilization will be reduced to zero.

           b.   Ground water flows will be diverted around the containment site
               by the slurry walls.

           c.   The underlying till will prevent the release of PCB contaminated
               sediment because of its thickness and impermeability.
i
           d.   Surface water will be diverted around the cell by the impermeable
               clay cap.  Contaminated material will no longer be in contact
               with surface water and surface water dispersion of PBC's will be
              'halted.

          e.   Sediment transport will be stopped because the material will be
               contained in a cell.


      D.  North Ditch

  .ider this alternative, the North Ditch will be partially excavated in order

-------
                             - 46 -
<3S
                               e h        ^

                                          a
 Contaminated soil in the                f°r 'Jeali^ with
                   ^ the parking iot  ,.

APProxi,7iatelv •>-,-, ,n                   Evolves  in  Place .

         Cel^ 27?,70U pounds of PCS-, -                  lncaPSulation.
                                                               of
                                                                C





      to the


-------
                                           - 46 -
c.
                                                                            *
               as  sufficient* to protect public  health,  but  less effective    t •
               than the cost  effective remedy which would require complete   F

              sediment removal and backfilling prior to sewer construction.
              Volatilization - This will  be significantly reduced
              because  the  entire area will  be capped.

             :.  Parking Lot


    The  recommended fund-balanced  approach  for  dealing  with the large  volume of

   contaminated soil in the parking lot involves in place  incapsulation.
1


„  Approximately 277,700 pounds of PCB's  in 105,000 yd3 of  soil would  be contained

  and capped  in the parking  lot area.  Slurry  walls would  be constructed around

  the perimeter of the major contamination and tied into the underlying glacial

  till.   The  underlying till  would be relied upon  to contain  the  downward movement.

 A clay cap would seal the top preventing surface water percolation into the

 cell.   Riprap would protect  the east edge of  the  cell  from wave  or other errosion

   .ions.  Encapsulation was  chosen as the  fundbalanced alternative over excavation

;nd removal,  the costeffective alternative, because it  provide a  high  degree

f protection  of public health and the environment  for  substantially less

>ney.  The PCB's in the parking lot have been shown to be moving slowly toward

iKe Michigan.   The fund-balanced alternative will  further slow or contain

at  release of PCB's to the lake environment.   The fund-balanced alternative

itrols the mechanisms  which were causing the PCB's to leave the site.


     1.  Ground Water - Ground water movements are the main driving
         force here,  causing  the PCB enclaves  in soil  to move slowly
         toward Lake Michigan.  Surrounding the contamination mass
         with slurry walls will divert  the ground  water flows away.

     2.   Surface Water - Surface water currently percolates through
         the surface and sand  exerting pressures on the PCB masses to
        move down  gradient.  The surface water route will be eliminated
        because of the cap.

-------
                                     - 47 -
        3.  Volatilization - Currently, volatilization is rather smalfe
            because of soil cover and the site  is partially paved.   |
            However, the cap will aid in further reducing ulitization
.r
Technical components and costs of the remedial alternative recommended for

implementation of, given Fund Balancing considerations are summarized in

Table 2.


     F.   Evaluation of Threat Under Fund Balanced Alternative;

In sections I and III of this documentation it was shown that the uncontrolled

PCB's at the CMC site were being released from that site in significant

quantities and were posing a threat to public health and the environment

as a result of that release.  The alternative described above will sucessfully

control the PCB's at the site and bring the release of PC3s to almost

zero. In doing so the threat to public health and environment posed by

the site will be mitigated so long as the containment cells function as

they are designed.  Because the cells would not comply with TSCA requirements

of PCB landfills and the Agency has concerns about the long term reliability

of the cells, off site transport and disposal is considered the minimum adequate

alternative and the cost-effective alternative.


The fund balanced alternative which includes both off site disposal and on

site contamination is only slightly less than fully adequate, however.  The

very highly contaminated material is removed frcm the site and the threat

posed by the moderately contaminated material is mitigated because material is

contained with a relatively high degree of reliability.


The threat posed to public health and the environment by the site after

this option is implemented will be small.  Because this alternative provides

-------
                                     - 48 -



almost as much protection for significantly less cost than the cost  •
                                                                     7C '
effective option, Fund balancing is considered appropriate at this site.




IX.  TSCA

As the recommended fund-balanced alternative includes the construction of two

on-site containment structures for the disposal of PCS dredge material and

soils, the Region evaluated this action in light of the Toxic Substances Control

Act (TSCA) regulations (40 CFR Part 761).



Pursuant to 40 CFH Part 761.60(5), all dredged materials that contain PCBs

must be disposed of in one of three ways:  I. in an incinerator which complies

with 40 CFR Part 761.65; or  2. in a chemical waste landfill which complies


with 40 CFR Part 761.65; or  3. upon application, using a disposal method to

be approved by the Regional Administrator in the Region where the PCBs are

located.



The Regional Superfund Office applied to the Regional Administrator for the

approval of an alternate disposal method.  The Regional Administrator denied

the application.  The decision was based upon the failure of the proposed

landfill to meet a number of technical requirements traditionally required for

approval of an alternate disposal method.  The denial cited the following

issues as its basis:  the lack of a synthetic membrane liner for the containment

cells; the fact that the landfill was not 50 feet from the historic high water

table; the .lack of an internal leachate collection system; and the lack of a 6

foot woven mesh fence surrounding the landfill.

-------