United States
Environmental Protection
Agency
Office of
Emergency and
Remedial Response
EPA/ROD/R05-83/005
June 1983
Superfund
Record of
New  Brighton Site,  MN
(Interim Water Treatment)

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
1. REPORT NO.
  EPA/ROD/R05-83/005
                              2.
             3. RECIPIENT'S ACCESSION NO.
4. TITLE AND SUBTITLE
  SUPERFUND RECORD OF DECISION:
  New Brighton  Site,  MN (Interim Water  Treatment)
             5. REPORT DATE
               06/24/83
             6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
                                                            8. PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
                                                            10. PROGRAM ELEMENT NO.
                                                            11. CONTRACT/GRANT NO.
12. SPONSORING AGENCY NAME AND ADDRESS
  U.S. Environmental Protection Agency
  401 M Street,  S.W.
  Washington, D.C.    20460
              13. TYPE OF REPORT AND PERIOD COVERED
               Final ROD Report
              14. SPONSORING AGENCY CODE
               800/00
15. SUPPLEMENTARY NOTES
16. ABSTRACT
       The municipal  drinking water wells  in the City of New Brighton/Arden Hills were
  found to be contaminated with volatile organic solvents in June 1981.  The City
  opened two new wells  in 1982 to reach a  lower non-contaminated water aquifer.  Sine'-
  discovery of the  contamination, the levels of hazardous substances have increased
  the remaining undeepened municipal wells.   The city is presently drilling two
  additional deeper wells.   However, these new wells will not be available until the
  end of the year.  Despite water restrictions, anticipated  summertime peak demands for
  water will not be met without drawing water from contaminated wells.

       The cost-effective initial remedial measure (IRM) selected for this site is
  treatment of the  New  Brighton/Arden Hills wells #5 and #6  with granular activated
  carbon to meet anticipated peak summertime demands.  The capital cost for this IRM
  is estimated to be  $150,400 and O&M costs are $30,526 for  four months.

      Key Words: Granular Activated Carbon  (GAC),  Potable Water  Supply, DOD,  Federal
                 Facilities,  Off-Base Contamination,  Fire Protection
 7.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.lDENTIFIERS/OPEN ENDED TERMS
                           c. COSATI Field/Group
  Record of Decision:
  New.Brighton Site, MN  (Interim Water
  Treatment)
  Contaminated media: gw
  Key  contaminants: VOCs, solvents,  TCE
18. DISTRIBUTION STATEMENT
19. SECURITY CLASS (This Report)
        None
21. NO. OF PAGES
     24
                                               20. SECURITY CLASS (This page/
                                                       None
                                                                          22. PRICE
EPA Form 2220-1 (R«». 4-77)   PREVIOUS EDITION is OBSOLETE

-------
                          ROD ISSUES ABSTRACT


Site;    New Brighton/Arden Hills, Minnesota

Region;  V

AA, OSWER
Briefing Datet  June 24, 1983


                            SITE DESCRIPTION

    The municipal drinking water wells in the City of New Brighton/
Arden Hills were found to be contaminated with volatile organic sol-
vents in June 1981.  The City opened two new wells in 1982 to reach a
lower non-contaminated water aquifer.  Since discovery of the contami-
nation, the levels of hazardous substances have increased in the re-
maining undeepened municipal wells.  The city is presently drilling two
additional deeper wells.  However, these new wells will not be avail-
able until the end of the year.  Despite water restrictions, antici-
pated summertime peak demands for water will not be met without drawing
water from contaminated wells.

                         SELECTED ALTERNATIVE

    The cost-effective initial remedial measure (IRM) selected for this
site is treatment of the New Brighton/Arden Hills wells #5 and #6 with
granular activated carbon to meet anticipated peak summertime demands.
The capital cost for this IRM is estimated to be $150,400 and O&M costs
are $30,526 for four months.


        ISSUES AND RESOLUTIONS                     KEY WORDS

1.  A fast-track RI/FS was conducted to assess     . Granular Activated
    alternatives to provide the City with pota-      Carbon (GAC)
    ble water to meet anticipated summertime       . Potable Water
    peak demands.  The FS recommended a hydrau-      Supply
    lie connection with a neighboring commu-
    nity's water system.  The City objected due to
    taste and odor problems with the nearby system
    and requested that granular activated carbon
    (GAC)  be used for treating the contaminated
    wells.  As a result the cost estimate for car-
    bon treatment was reevaluated.  Based on new
    information from the prospective suppliers of
    the treatment system, the revised costs were
    estimated to be essentially the same as a con-
    nection to the nearby water system.  There-
    fore,  the feasibility study was amended and
    carbon treatment was recommended.
                                  -1-

-------
New Brighton/Arden Hills, Minnesota
June 24, 1983
Continued
        ISSUES AND RESOLUTIONS                     KEY WORDS

    Fund-financed response actions are not autho-  . Federal Facilities
    rized for releases from Federal facilities.
    The Twin Cities Army Ammunition Plant, a Fed-
    eral facility, is one of several potential
    sources of contamination.  However, fund-
    financed response actions were authorized
    because it has not been determined that the
    problems addressed in the IRM originate from
    the Federal facility.
                                  -2-

-------
                          JUN 24
                       RECORD OF DECISION
                    Initial Remedial Measure
SITE:  New Brighton/Arden Hills Site
       New Brighton, Minnesota

ANALYSIS REVIEWED:

I have reviewed the following documents describing the analysis
of cost-effectiveness of remedial alternatives at the New
Brighton/Arden Hills Site:

          -  Remedial Action Master Plan, New Brighton, CH2M Hill,
             January 29, 1983.

          -  Focused Remedial Investigation/Feasibility Study,
             New Brighton, CHgM Hill, May 29, 1983.

          -  Resolution of the City Council  of New Brighton
             No.  83-69, May 24, 1983.

          -  Staff summaries and recommendations.

DESCRIPTION OF SCHEDULED OPTION:

          -  Interim Water treatment system for the City of
             New Brighton wells #5 and #6 for peak demand
             periods for the summer using granular activated
             carbon (project duration 4 months).

DECLARATIONS:

Consistent with the Comprehensive Environmental  Response,
Compensation and Liability Act of 1980 (CERCLA), and the National
Contingency Plan (40 CFR Part 300), I have consulted with the
State of Minnesota prior to determining the appropriate remedial
action.   I have determined that the granular activated carbon
treatment for the New Brighton Site is a feasible and cost-
effective remedial  action necessary to protect public health
and the environment.   I have also determined that the action
being taken is appropriate when balanced against the resources
available in the Trust Fund and the need to respond at other
sites.
                                        Lee M.Thomas
                               Acting Assistant Administrator
                         Office of Solid Waste & Emergency Response

-------
    ri
     I     UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
    f                 WASHINGTON, D.C. 20460
                         June  22,  1983
                                                         OFFICE OF
                                                      GENERAL. COUNSEL.
MEMORANDUM

SUBJECT:  New Brighton/Arden Hills Site
FROM:     Lisa K.
          Associate Generar Counsel
          Solid Waste St Emergency Response
            Division (LE-132S)

TO:       Lee M. Thomas
          Assistant Administrator for  Solid Waste
            and Emergency Response  (WH-562A)


     I concur in your decision  to undertake an  initial  remedial

action (IRM) at the New Brighton/Arden Hills  site  on the  follow-

ing condition:  that the Agency has not determined that the

problems to be addressed by the IRM result from a  release from

a Federally-owned facility.

-------
                  New Brighton/Arden Hills  Site
                         Remedial Action
                        Briefing Document
 Purpose of this briefing  is to obtain AA approval  for  the  initial
 remedial measure recommended by the Region and  the  State for  the
 New Brighton/Arden Hills  Site.  A  "Record of  Decision" has been
 prepared to document the  approval.

 The New Brighton/Arden Hills Site  is contaminated with volatile
 organic solvents found in drinking water.  The  plume has spread.
 over approximately 18 square miles potentially  contaminating
 the drinking water supplies of 48,000 residents.  Source(s) for
 the contamination have not been positively identified.

 This contamination was found in New Brighton 's  municipal drinking
 water wells in June 1981.  The City of New Brighton deepened  two
 city wells in 1982 to reach a lower noncontaminated water aquifer.
 Since discovery of the contamination, the levels of hazardous
 substances have increased in the undeepened municipal wells.
 The City of New Brighton  is presently drilling  two additional
 deeper wells.  Although this program is progressing as fast as
 possible, these new wells will not be available until late this
 year.

 Despite water restrictions, anticipated summertime peak demands
 for water will not be able to be met without drawing water from
 contaminated wells.  The New Brighton water system does not blend
 the water as it is pumped from the municipal wells; therefore,
 the contaminated ground water will not be diluted by blending
with uncontaminated water.

The City engineer of New Brighton estimates that an additional
 2 million gallons per day (mgd) capacity will be required to
 meet peak summer demands, although normal use should require
 only an average of 1 mgd.  Recognizing the need for expeditious
 remedial action, EPA conducted a fast-track RI/FS to assess
 available alternative actions.
CH2M Hill completed a RI/FS in May 1983,
were considered:
    Three alternatives
Hydrologic connection to a
Minneapolis water reservoir

Treatment of New Lrighton
municipal wells #5 and #6
with granular activated carbon

Treatment of New Brighton
municipal wells #5 and #6
with air stripping
$185,209
$180,926
$144,865
2-3 weeks for
implementation
2-3 weeks for
implementation

6-7 weeks for
implementation

-------
                               — 2—
The costs noted above include the present worth cost of both
capital and 0 & M costs for the project life which is four  (4)
months.

A public meeting was held in New Brighton, Minnesota on" May 23,
1983.  Approximately 40 people attended.  The State presented a
brief background .on what is known about the contamination problem.
The CH2M Hill Project Officer presented a summary of results and
the recommended initial remedial measure to those in attendance
for review and comment.  The recommended alternative was connection
to the Minneapolis water supply.  There was some concern among
those present regarding the pipeline connection to Minneapolis
due to perceived taste and odor problems with this water during
summer months.  U.S. EPA informed the public that additional
comments could be submitted during the two-week period following
the meeting.  Copies of the feasibility  study were made available
to the public on May 26, 1983.  The two-week public comment period
ended on June 9, 1983.  The only written comment received was a
resolution from the City Council of New Brighton (See Attachment  D)
The resolution requested treatment of the New Brighton wells with
granular activated carbon.

Based on consideration of public comments and review of the CH2M
Hill FS and addendum (copy attached), EPA has determined that
granular activated carbon (GAC) treatment of the municipal water
wells # 5 and # 6 is the appropriate initial remedial measure to
be implemented.  The Regional Office of Drinking Water, the
Minnesota Pollution Control Agency, the Minnesota Department of
Health and the City of New Brighton concur in this decision.

The installation of GAC constitutes one part of the IRM.  Private
drinking wells and the City of St. Anthony will be addressed
later in a separate Record of Decision.

This "Record of Decision" certifies that:

     The selected initial remedial measure is a cost-effective
     remedy for the site.

  -  The selected initial remedial measure will effectively
     protect the public health.

     Monies are available in the Fund to finance the remedy.

Presently there is no enforcement action on-going with this site.
Letters were sent to potential responsible parties on June 6,1983
notifying the parties of the recommended IRM and giving them
seven (7) days to inform U.S. EPA if they wish to perform this
IRM.

The following actions are required to move this IRM into constructi

     Approve recommended IRM                 AA, OSWER

-------
                          -3-,
Enforcement release                     U.S.  EPA  -  Region V
   Notification time (7 days) to
   potential responsible parties

Approve proposed cooperative agreement - Awarded  June  17, 1983

Design IRM                              U.S.  EPA  -  Region V
Construct IRM                           U.S.  EPA  -  Region V

-------
          Remedial Implementation Alternative Selection
                  New Brighton/Arden Hills Site
                     New Brighton, Minnesota
                           June 3, 1983
HISTORY
The New Brighton/Arden Hills Site is located immediately north of
Minneapolis/ St. Paul, Minnesota  (See Attachment A).   in June
1981, the Minnesota Pollution Control Agency (MPCA) and the
Minnesota Department of Health  (MDH) found solvent contamination
of the groundwater used for drinking water in the City of New
Brighton and surrounding communities.  More than 150 area wells
have been sampled by the State of Minnesota, the U.S.  EPA Field
Investigation Team (FIT), and Army contractors.  Fifteen volatile
organic priority pollutants were found.  Although the  major
contaminant is trichloroethylene  (TCE), each well contaminated
by TCE is typically also contaminated with other volatile organic
chemicals.   Contaminant concentrations occur at levels warranting
serious concern over potential adverse impacts upon public health.
MDH has ordered several municipal and private wells closed.
Retests,  although few in number, have indicated increasing
concentrations of some contaminants.  The U.S.  Army is a potential
source of contamination at the site.  However,  the RI/FS has not
been completed and it is not possible to determine that the
problems at New Brighton result from a release from a  federal
facility.

The most probable source(s) of the groundwater contamination lies
within Ramsey County, northeast of the City of New Brighton, a
suburb of the Twin Cities.  The identified plume of contaminated
groundwater underlies approximately 18 square miles of Ramsey
and Hennepin Counties.  Several potential sites have been identified
so that each may be the primary and/or a contributing  source of
the contamination.

A draft Remedial Action Master Plan (RAMP) for this site was
prepared and submitted to U.S. EPA Region V in late 1982.  On
May 2, 1983, a feasibility study for a temporary water supply
for the cities of New Brighton and St.  Anthony and several
private homes on private wells was authorized by U.S.  EPA
Headquarters.  A preliminary site investigation by the feasibility
study contractor (CH2M Hill), MPCA,  and the regional U.S. EPA
Project Officer was conducted on May 9 to 11, 1983.  Discussions
with City officials and MPCA staff indicated that, of  the three
study areas, New Brighton had the most immediate need  for a
temporary,  drinking water source to augment existing supplies
over the peak (summertime) demand period.  Without temporary
augmentation in New Brighton starting in June,  either:  (1) severe
water pressure drops could occur in the City distribution system
due to inadequate supply, thereby creating a significant risk
in the event of a major fire, or (2) contaminated wells would
have to be  pumped, thereby violating an MDH ban on their use and
exposing the population to a contaminated water source.

-------
                               -2-
Because New Brighton's need is immediate compared to  the other
two study areas, the feasibility study addressed only New Brighton,
The other study areas will be addressed in  later feasibility

CURRENT STATUS

Prior to June 1981, New Brighton operated eight municipal wells,
designated Wells 2 through 9.  Contamination was detected in all
wells but in significantly varying degrees.  In response to a
MDH order, the City embarked on a program to provide  residents
with a noncontaminated water supply.  Following a comprehensive
study by the City, they concluded that the  best long-term solution
was to deepen existing wells into the noncontaminated Mt. Simon/
Hinckley aquifer where possible, and/or develop new wells into
this formation if necessary.  Wells 8 and 9 have already been
deepened.   Wells 2 and 7 have trace levels of contamination.
Wells 2, 7, 8, and 9 are currently in service and supply a total
capacity of 5.1 mgd.  However, during the summer peak-use period
(June 1 to October 1), maximum daily water demands run as high
as three times the average daily rate, or 7.5 mgd.  Consequently,
City engineers are projecting a summer peak period shortfall of
approximately 2.4 mgd.  The construction of Wells 10  and 11,
originally planned for startup in early 1983, has been delayed
due to unforeseen drilling problems.  It is believed  however
that these wells will be producing by late  1983.

In discussions with New Brighton City engineers, and  a review
of historical water demands, it has 'been agreed that  a temporary
summertime water augmentation of approximately 2.0 mgd will
provide the .City with enough capacity to meet their peak require-
ments and that an average quantity of 1 mgd will be required.
Further, if treatment and use of an existing well source is to
be considered, the only likely candidates are Wells 5 and 6 due
to their capacity (2.2 mgd total), location, and ability to
integrate a treatment system quickly.  Wei Is 5 and 6  are currently
used only for emergency standby since the contamination levels
in the wells exceed State standards.

The feasibility study and addedum published by Cl^MHill in May
1983, identified three alternatives as an initial remedial measure
for the New Brighton/Arden Hills Site as follows:

Hydrologic connection to a                      $185,209*
Minneapolis water reservoir

Treatment of New Brighton Municipal
Wells 15 & 6 with granular activated carbon     $180,926*

Treatment of New Brighton Municipal
Wells 15 & 6 with air stripping                 $144,865* +

* (Present worth cost for capital and O&M costs for life of
   the project - 4 months).
+ Implementation would take 6-7 weeks as compared to  2-3 weeks
  for the other alternatives.

-------
                               -3-*
Each of the alternatives summarized above would provide  adequate
protection of public health, welfare and the environment.

On May 23, 1983, at a public meeting in New Brighton, Minnesota
the findings 'and recommendations of the CH2M Hill report were
presented by the CH2M Hill Project Officer.  MPCA, MDH, and
U.S. EPA Region V were also at the meeting.  The residents in
attendance raised objections to the use of Minneapolis water due
to perceived taste and odor problems.  Members of the City Council
of New Brighton also share this concern.  The Minneapolis water
according to MPCA files does have trace amounts of contaminants
in it.

Following the public meeting, the feasibility study was made
available to the public for a comment period of two weeks.  The
feasibility study was sent to U.S. EPA Headquarters for review
prior to release. Regional Counsel and the Regional Response
Branch also reviewed the feasibility study.  The City of New
Brighton and MPCA also reviewed and commented on the feasibility
study prior to public release.  Based on review of all available
data, findings, recommendations of current and past technical
studies, and public comments, the Region (in concurrence with
the Regional Office of Drinking Water Quality) recommend approval
of treating wells No. 5 and 6 using granular activated carbon.
The system would utilize 80,000 pounds of virgin activated carbon
approved for potable water service.  The system would provide 13
minutes contact time at a total design flow rate of 1500 gpm.
The length of the project is 4 months.  Total capital costs and
O&M costs are shown in Attachment B.  Testing of the water for
water quality will be done by the City of New Brighton.

RECOMMENDED ALTERNATIVE

Section 300.68(e)(l) of the National Oil and Hazardous Substances
Contingency Plan (NCP) states that initial  remedial measures
should be taken when they are determined to be feasible, cost-
effective, and necessary to limit exposure to a significant
health hazard.  Based on our evaluation of the cost-effectiveness
of each of the proposed alternatives, the comments received from
the public and the City Council of New Brighton, information
from the State (MPCA and MDH) and from the Regional Office of
Drinking Water, we have determined that the IRM utilizing granular
activated carbon meets the NCP criteria.

-------
                                -4-.
PROPOSED ACTION

We request your approval of this IRM  for granular  activated  carbon
for treatment of municipal water wells  5 and  6  in  New  Brighton,
Minnesota.  Attachments B-D -provide additional  information to
support the documentation for this decision.

TENTATIVE SCHEDULE

Advise and receive bids             U.S. EPA  (CI^M Hill) Completed

Design and construction of          Following bid  receipt,
selected IRM                        tabulation, and recommendation
                                    of  award

If you have any questions please call Karen Waldvogel  at
(312) 886-7573.

Attachments as noted

-------
?fli §!?
      *WWM ^fO^fMVf
      prc^m •^r'r'SSwps^t
      &ff#u i....-^\ -yf ^\ 'l^s^XO^^T'v^oJ
- ' .'-•. /• I  J .:--V>>
-r^jVt i..:-^

*«-*«>u'""'i L
      *ai^:«Km\N
      r'^niM^ir^f t  . l-so/ X-R i \\ \
                         .^J "••.; .X M ^ ''VV\'" '
                         •fe^-hjdb^y
                         •- ^.^^V^rO^
                                      	_ ,1.;~-»_. '-'.'.
    0
                     f^-^M-.^ ,.-r< ^*iAO/U:^-.?N
                     i' P .\/•--*• tofM^v
                     ...;? , ::--iz:.-—-\    ^ *fc.\tJ;:'A
                     :'".' I :i	^    VA \V" \\'-. '•:•-
                     Siilf i ari'-^vVk      W-V{.>
                     ;.•,'•' -••'! .:-—'.v->      ••-,>» '>•
                     i I'-.. . :':"~~" -,, Lak' ^.»««»4  \ • I
                         4-
                               Anion Hilts'
      i '



-------
1
                                    ADDENDUM NUMBER 1
                                           TO
                                 DRAFT FEASIBILITY STUDY
                                 TEMPORARY WATER SUPPLY
                                    NEW BRIGHTON, MN
                                      MAY 27, 1983


              As indicated in a footnote in Section 9, page 9-1, of the
              subject Feasibility Study, it was anticipated that the acti-
              vated carbon system supplier, whose equipment and costs were
              used in the study, would submit a revised proposal.  This
              proposal was received and evaluated and is the subject of
              this addendum.

              The purpose of any Feasibility Study is to evaluate alterna-
              tives and recommend the most cost-effective solution to the
              problem consistent with sound engineering principles and
              judgement.  VJith this in mind, the referenced Feasibility
              Study recommended that a temporary pipeline be installed
              from Minneapolis' Hilltop Reservoir to New Brighton's dis-
              tribution and storage system at an evaluated cost of
              $1.76/1,000 gallons of water used.  The activated carbon
              alternative was.evaluated at §1.98/1,000 gallons  (See
              Table 8-1).

              The carbon system supplier's revised proposal contained
              several significant addition's, at no additional cost, which
              had the effect of eliminating the previously applied cost
              contingency of $27,200  (Table 6-1) and reducing their evalu-
              ated cost to $1.72/1,000 gallons.  The table below summarizes
              the revised carbon system costs.  Refer to Tables 6-1, 6-2 and
              8-1 for previous cost figures.


                                       TOTAL COSTS
                              CARBON ALTERNATIVE  (REVISED)

              Carbon System Lease                          $136,000
              Power & Pipe Connections                        5,000
                   Subtotal, Facilities                     141,000
              Engineering, CM                                 9,400
              Contingency                                    .	0_
                   Project Capital Estimate                . 150,400
              O&M Costs                       •               30,526
                   Total .Project Cost                      $180,926

              Water Rate, $/l,000 gallons                     $1.72
                 (At 105 days and 105 MG)
                                                                       •£- U

-------

Further, in an attempt to offset the potential risks with
the carbon system described in Sections 6 and 8 (pages 6-3,
8-1 and 8-3), the carbon system supplier has proposed to
1) provide an equipment or operational performance bond
equal to their proposal price ($136,000) at no additional
cost, and 2) provide up to an additional 80,000 Ibs of virgin
carbon if                premature break through of contamina-
tion occurs before the 105 day performance period ends.

All of the above considerations, coupled with the New Brighton
water department and city council's expressed desire for an
activated carbon system over the pipeline alternative, have
necessitated a concerted and critical reevaluation of the
previous pipeline system recommendation.  "At this time,
based on the available information, the most cost-effective
choice now appears to be the carbon system.  Further, it is
believed that any accompanying risks with this acknowledged
novel system design can be offset by the proposed performance
bond.  Consequently, the recommendation of this feasibility
study should be changed from the pipeline alternative to the
carbon alternative, subject to negotiation of contract terms
with the carbon system supplier.

-------


        '    ^


•„	-9-
 j f-> a . , . p . . ^
           . - -- u _>

-------
     ew
     Q
13
•
N
righton
XI
2
2
CC
CD
2
2
UJ
O
CO
g
cc
en
01
CJ
June 1,  1983

Ms.  Karen Waldvogel
U.S. EPA
Region  V
230  South Dearborn Street
Chicago, Illinois  60604

TEMPORARY WATER SUPPLY
CITY OF  NEW BRIGHTON, MINNESOTA
Karen, enclosed is a resolution adopted by the  New  Brighton  City
Council  on May 24, 1983 requesting the U.S.  Environmental
Protection Agency to provide a temporary water  supply  to  meet
Summer water needs and stating a strong preference  for the  carbon
adsorption option discussed in the May 26, 1983  draft  feasibility
study prepared by CH2M Hill.

Thank you for this opportunity to provide City  input.

Sincerely,
                      / ^
Leslie J. Proper, P.E.
Director of Public Works

mh

End osure

cc:  Steve Lee, MPCA
                                                             /O,
                                                                   J ,
                                                              •v\_-2 r\ J^ j

-------
                       RESOLUTION TlO  83-69
                        STATE OF MINNESOTA
                         COUNTY OF RAMSEY
                       CITY OF NEW BRIGHTON

  RESOLUTION -REQUESTING U.S.- ENVIRONMENTAL PROTECTION  AGENCY  TO
  PROVIDE TEMPORARY WATER SUPPLY AND STATING PREFERENCE  FOR CARBON
  ADSORPTION OPTION

       WHEREAS, the City of New Brighton has had several  of its
  water supply wells contaminated with volatile organic  hydro-
  carbons ;  and

j:     ' WHEREAS, in order to comely with a directive from  the
jj Minnesota Department of Health to provide non-contaminated  water
|; to its residents, the City will need a temporary water  supply
  to meet Summer water peak needs in 1983; and

       WHEREAS, the U.S. Environmental Protection Agency  has  funded
  a  feasibility study to determine alternative methods of providing
  the needed temporary water supply.

       NOW  THEREFORE BE IT HEREBY RESOLVED by the City Council of
  the City  of New Brighton that the City hereby requests  that the
  U.S. Environmental Protection Agency provide a temporary water
  supply to meet the City's 1983 Summer water needs; and

       BE IT FURTHER RESOLVED that the City strongly prefers  the
  carbon adsorption option outlined in the May 26, 1983  draft
  feasibility study prepared by CH2M Hill.
  Adopted this  24th  day of
May
1983
                                     fa         /ft s?£r
                                    X^g^<^^< "J  /P*^^
                                    Gregoj/y B.^ftarcus, Mayor
  ATTEST:
                                       fes F. Winkels, Acting City Manager ;
                	
   Margaret^A. Egan, City Clerk

  (SEAL)

-------