United Slates
Environmental Protection
Agency
Office of
Emergency and
Remedial Response
EPA/ROD/R04-88/019
September 1988
Superfund
Record of Decision
  Coleman  Evans, FL

-------
                                   TECHNICAL REPORT DATA
                            /Pleat read Instrucnont on the rtvmt before completing/
 I. MPOHT MO.
 EPA/ROD/ROih-86/019
                                  3. RECIPIENT'S ACCESSION NO.
4. TITLE ANOSUSTITLC
 SUPERFUND RECORD OP  DECISION
 Coleman Evans, PL
                                 5. R6PO«T DATi
                                            September 25, 1986
                                 «. PERFORMING ORGANIZATION CODE
7. AUTHORS)
                                                           8. PERFORMING ORGANIZATION REPORT
 t. PERFORMING ORGANIZATION NAMf AND ADDRESS
                                  10. PROGRAM ELEMENT NO.
                                                           II CONTRACT/GRANT NO
12. SPONSORING AGENCY NAME ANO AOORESS
 U.S. Environmental  Protection Agency
 401 M Street, S.W.
 Washington, D.C.  20460
                                 i 13. TYP6 OF REPORT ANO PERIOD CO*. £
                                 ;	Final ROD Report
                                  14, SPONSORING AQ6NCV CODE

                                            800/00
19. SUPPUEMiNTARY NOTES
16. ABSTRACT
    The Coleman Evans Wood  Preserving Company site is an active  11-acre  wood preserving
 facility located  in the  town of whitehouse, Duval County, Florida.   The. site consists o
 two distinct areas:  the western portion, which comprises the wood  treating facility;
 and the eastern portion, which consists of a landfill area which  has been used for t*e
 disposal of wood  chip  and  other wastes.  Land use around the site is primarily
 residential and light  commercial/industrial.  Since 1954, Coleman Evans has produced
 wood products  impregnated  with PC?.   Wastes from the process were discharged into an
 onsite drainage ditch, and two unlined sludge disposal pits.  In  1980,  ground water
 underneath the site was  found to be  contaminated.  As a result, Coleman Evans
 constructed a closed-loop  treatment  system.  In 1985, an immediate  removal action was
 taken to remove the contents of the  two unlined pits.  Subsequent site  investigations
 confirm soil and  ground  water contamination, with PCP the primary contaminant of cor.ce:
    The selected remedial action for  this site includes:  all soils  and  sediments wiiu.
 PCP concentrations greater than LO mg/kg will be excavated, approximately 9,000 cur: r
 yards; excavated  soils will be incinerated in a temporary onsite  incineration unit.
 Decontamianted soils will  be backfilled onsite; ground water recovery will be conduc •.<»••:
 for dewatering to facilitate excavation and to treat ground water with  PCP
 concentrations greater than 1.01 mg/1.  Recovered ground water  will be  stored and
 (See Attached Sheet)                                	
                                <£Y WORDS ANO DOCUMENT ANAfS'S
                  DESCRIPTORS
                                                             SNOEO
                                                                           C3SAT;
 Record of Decision
 Coleman Evans, FL
 Contaminated Media:  gw,
 Key contaminants: PCP
soil, sediments
H. DISTRIBUTION STATEMENT
                     '9 SEC<-R|TV CLASS . Tins Rtpom
                               None
                                                                                     31
                                              20. SECURITY CLASS
                                                        None
                                      i paqti
                                                                         22 'RICE

-------
EPA/ROD/RO4-86/019
Coleman Evans, PL

16.  ABSTRACT (continued)
analyzed.  If the level of PCP exceeds 1 ug/1, the ground water will be
treated by an onsite carbon adsorption unit to a level below 1 ug/1 PCP in
accordance with Chapter 17-3.061.3(m) of the Florida Administrative Code
before discharge to the surface water environment via the onsite drainage
ditch.  Other incidental Hazardous Substance List compounds identified in
ground water during the implementation of this remedy will be cleaned up to
levels which comply with Drinking Water Standards.   Clean up compounds for
which no standards exist will be to non-detection levels.  The estimated
capital cost for the remedy is $3,000,000 - $3,800,000 with no O&M costs.

-------
                            RECORD OF DECISION
                        REMEDIAL ACTION SELECTION
SITE

Coleman Evans Wood Preserving Co.
Jacksonville, Duval County, Florida
DOCUMENTS REVIEWED

I am basing my decision primarily on the following docunents which describe
site specific conditions and the analysis of effectiveness and cost of
the remedial alternatives for the Coleman Evans Site:

     - Coleman Evans Wood Preserving Co. Site Remedial Investigation Report,
     - Coleman Evans Wood Preserving Co. Site Feasibility Study,
     - Coleman Evans Wood Preserving Co. Surmary of Remedial Alternative
       Selection,
     - Public Health Evaluation,
     - Agency for Toxic Substances and Disease Registry - Health
       Assessment,
     - Department of the Interior - Release from Claims for Damages
       to the Natural Resources Under DOI Trusteeship.
DESCRIPTION OF THE SELECTED REMEDY

- All soils and sediments with pentachlorophenol (PCP) concentrations
  greater than 10 mg/kg will be excavated; approximately 9000 cubic
  yards.

- Excavated soils will be incinerated in a temporary onsite incineration
  unit.  The soils will be decontaminated in a primary chamber where PCP
  and fuel oil will be driven off in a gaseous phase.  The PCP will be
  thermally destroyed in a secondary chamber.  Incineration will be
  undertaken in accordance with federal, state, and local laws.  A
  detailed Quality Assurance/Quality Control plan will be developed
  during the Remedial Design.

- Decontaminated soils will be backfilled onsite.

- Ground water recovery will be conducted for dewatering to facilitate
... excavation and to treat ground water with PCP concentrations greater
  than 1.01 mg/1.  Recovered ground water will be stored and analyzed.
  If the level of PCP exceeds 1 ug/1, the ground water will be treated by
  an onsite carbon adsorption unit to a level below 1 ug/1 PCP in accordance
  with Chapter 17-3.061.3(m) of the Florida Administrative Code before
  discharge to the surface water environment via the onsite drainage
  ditch.  If EPA promulgates further regulations in the future which are
  more stringent than those outlined in this ROD, the future regulations
  will be observed.

-------
- Other incidental Hazardous Substance List compounds identified in ground
  water during the implementation of this remedy will be cleaned up to
  levels which comply with Drinking Water Standards.  If the Drinking
  Water Standards do not address these compounds, clean up will be consistent
  with the human health criteria identified in the 1980 Water Quality
  Criteria.  Clean up of compounds for which no standards exist will be
  to non-detection levels.  In cases where standards promulgated by the
  State of Florida are more stringent, the State standards will have
  precedence.

- Due to the complete destruction of site specific contaminants by
  incineration, no post-remedial monitoring or operations and maintenance
  activity is required.

DECLARATIONS

Consistent with the Comprehensive Environmental Response,  Compensation,
and Liability Act of 1980 (CERCLA), and the National Contingency Plan (40
CFR, Part 300), I have determined that the above Description of Selected .
Remedy for the Coleman Evans Wood Preserving Co. Site is an effective
remedy and provides adequate protection of public health,  welfare,  and
the environment.  The State of Florida has been consulted and agrees with
the approved remedy.  These activities will be considered part of the
approved action and eligible for Trust Fund monies until remedial action
is complete.  The basic assumption is that EPA will undertake
implementation if the responsible parties fail to undertake the design
and implementation of the selected remedy.

I have also determined that the action being taken is appropriate when
balanced against the availability of Trust Fund monies for use at other
sites.  In addition, the selected remedy is more permanent than other
remedial actions,  and is necessary to protect public health, welfare or
the environment.

If additional remedial actions are determined to be necessary,  a Record
of Decision will be prepared for approval of the future remedial action.
     Date                              Jack E. Ravan/
                                       Regional Administrator

-------
                                SECTION I
                      SITE LOCATION AND DESCRIPTION
The Colenan Evans Wood Preserving Conpany (Coleman Evans) is located on
Celery Avenue in Whitehouse, Duval County, Florida (Figure 1).  The
site is an active 11-acre wood preserving facility which uses pentachloro-
phenol (PCP) as a wood preservative.

The Colenan Evans site is composed of two distinct areas.  The first area
comprises the wood treating facility and is located on the western portion
of the property.  The eastern portion is a landfill area which has been
used for disposal of wood chips and other facility wastes.

Site surface features include two unlined disposal pits, which were partially
removed in July 1985 under an EPA emergency response, and the active wood
treatment facilities.  The treatment system is composed of a large pressure
chamber, several tanks for storage of the preservative fluids, a sand
filter system, and several storage sheds.

The Colenan Evans site is relatively flat, with less than 10 feet of relief
over the entire site.  The site drains into a ditch which eventually enters
into a swampy area to the south, and then into McGirts Creek.

Within a 1-mile radius of the site, land use is primarily residential and
light commercial/industrial.  Outside the 1-mile radius, the area is
primarily undeveloped rural land.

Locally, there is no central water supply, thus approximately 1000
residents rely on ground water resources for their drinking water source.
Surface waters in Duval County are used exclusively for sport fishing and
recreation.  Agriculture near the site is limited to small gardens.  The
only natural resources are the surficial aquifer system and Floridan
aquifer.

-------
            ^  ,3
                               Colenan Evans
                              Wood Preserving
                                   Co.
                    ;     DDD        Q
                  L	L
                                                 a
                                                                  1
                                                               SCALE IN f
                                                                APPROXIUA'
                    CtNC««l AVCHUC
                                 a
                                    a
                                             <=3
              i 00
              ?1
a a
    a   i
             TO UcCiHTS CREEK
Figure 1.   Colenan Evans Wood Preserving Coipany Site Ixacation Map.
                              (2)

-------
                                .SECTION II
                               SITE HISTORY
OPERATIONAL HISTORY                                              :

Since 1954, Coleman Evans has produced preserved wood products which are
impregnated with PCP.  The treatment process includes steaming, drying,
and pressure soaking the wood, all within a single chamber.  The wood
products are impregnated with PCP dissolved in #2 diesel fuel.

Prior to 1970, the process effluent was precipitated with caustic soda
and aluminum sulfate, passed through a sand filter, and discharged into
the onsite drainage ditch.  The recovered sludge was deposited into two
unlined pits onsite.  The pits, located along the southern boundary, were
approximately 100 feet by 50 feet and extended to unknown depths.  In
1970, Coleman Evans began storing the sludge in storage tanks located
adjacent to the pits.  At this time, the company engaged an engineering
firm to design a waste water treatment system.  Treatment of the effluent
with chlorination and lime precipitation was adopted to produce a clear
waste water.

In September 1980, the City of Jacksonville Bio-Environmental Services
Division (BES) confirmed the presence of ground water contamination on site.
As a result, Coleman Evans incorporated an activated carbon filter system
into the treatment process in late 1980.  In 1981, the company completed the
construction of a closed-loop treatment system.
PEBMIT AND REGULATORY HISTORY

In June 1972, Coleman Evans received an Industrial Operation Permit from
the State of Florida Department of Air and Water Pollution Control.  The
permit was for design and operation of a 2500 gpd industrial waste
treatment system and for discharge of effluent to McGirts Creek via the
onsite drainage ditch.  A renewal permit was issued in September 1977 and
expired in August 1980.

A National Pollution Discharge Elimination System (NPDES) Permit was
issued to Coleman Evans in August 1975.  Upon institution of a closed-loop
system, the company allowed this permit to expire in August 1980.  EPA
formally inactivated the NPDES permit in June 1982.

In November 1980, Coleman Evans filed a Part A EPA Hazardous Waste Permit
Application as required under Section 3005 of RCRA.  In its application,
the company stated that with the closed-loop system there was a capacity
for storing 2000 gallons of waste.  The estimated annual quantity of
hazardous waste generated was 5000 gallons.

After BES confirmed the presence of ground water contamination, Coleman
Evans was served a Notice to'Comply for violation of ground water standards.
It was under this notice that Coleman Evans submitted plans for the existing
closed-loop system.  In an effort to remedy violations, the company

-------
submitted a plan and schedule  for construction of  the closed-loop system
in April 1981.  The Florida Department of Environmental Regulation  (FDER)
issued a construction permit in June  1981.

Also in 1981, an FDER Inspection found that Coleman Evans was in violation
of RCRA hazardous waste reporting, planning, and safety requirements.
FDER issued a Consent Order in November  1982 which required Coleman  Evans
to implement a plan for sampling, analysis, monitoring, and reporting.
The company hired a contractor to assist in meeting the terms of the
Consent Order.  Final reports were issued by August 1983.

A further Site Inspection was conducted by FDER in April 1983.  FDER
found that Coleman Evans was a generator and storer of hazardous wastes,
and was in violation of RCRA requirements.  As a result, FDER required
Colenan Evans to submit an application for a Temporary Operation Permit
by April 19, 1983.  No application was submitted.  In September 1984,
FDER filed a lawsuit against the company, seeking relief which would
require the company to conduct remedial activities at the site.  The suit
is still pending.

In October 1981, the Coleman Evans site was proposed for inclusion on
the National Priorities List (NPL) based on an Hazard Ranking Score
of 59.14.  The site was finalized on  the NPL in March 1983.

In September 1984, EPA obligated funds for an RI/FS.  By October 1984,
EPA had tasked Camp Dresser and McKee, the REM II contractor, to execute
the RI/FS.  The field investigation was delayed by Coleman Evans1 refusal
to allow EPA onsite to conduct the removal and remedial activities.  As a
result, EPA and DOJ filed a motion in Federal Court to obtain an order
granting site access.  By June 1985,  EPA and its agents were granted site
access and field operations were initiated.

In an Immediate Removal Action, EPA excavated the contents of the two
unlined pits, and the pit material was shipped to Ernelie, Alabama.  This
action was conducted in June and July 1985.  The pits were backfilled
with clean material and french drains were installed.

The Remedial Investigation Report was completed in April 1986 and the draft
Feasibility Study was ready for release to the public on July 21, 1986.

A public meeting to present the FS was held on August 7, 1986.  The public
meeting was the initiation of the public comment period which closed on
August 28, 1986.

Due to the fact that Coleman Evans is an active facility which periodically
continues to have releases of hazardous substances, EPA requested that
Region IV RCRA personnel perform a site inspection.  The EPA inspector
found several RCRA infractions; however, the infractions identified are
being addressed in the State of Florida's lawsuit.  EPA will continue to
monitor the RCRA aspects of this site.
                                    (4)

-------
PREVIOUS STUDIES

Several site investigations were conducted between 1980 and 1983.  Studies
of air, soil, ground water, surface water and sediments were conducted by
federal and state agencies, as well as two consultants to Coleman Evans.
During the period from August to December 1980, BBS, FDER, Ecology and
Environment, Inc. (E&E), and NUS Corp. conducted separate soil and
ground water studies.  In December 1980, Law Engineering & Testing Company
(LETCO) installed and sampled monitor wells, soil test borings, and
shallow soil auger holes.  In June 1982, EPA conducted an air investigation,
using a photo-ionization meter (PI) and an infrared spectrophotometer,
and in March 1983, Groundwater Technology, Inc. (GTI) conducted a well
installation and sampling program at the site.  In 1985, EPA subcontracted
with Haztech, Inc. to remove the contents of the onsite sludge pit.  The
results are summarized below.

0 Air Studies - Air investigations were conducted by EPA in 1982.  None
  of the measurements recorded WC levels above background.  The GTI
  investigation indicated that ambient air quality was within acceptable •
  levels (<5.0 ug/1) except in a single borehole which had VDC levels of
  14.0 ppm and in the area of the sludge pits where VDC levels were
  recorded to be 5.0 ug/1.

0 Soil Studies - In 1980 LETCO collected three soil borings on site,
  however,  analysis was conducted on only two of the samples.  These two
  samples indicated PCP concentrations of 320 and 430 mg/kg.  In 1983, GTI
  analyzed soil samples from eight locations.  PCP concentrations ranged
  from 11 mg/kg along the southern edge of the disposal pits to 1,490
  mg/kg along the northern edge of the disposal pits (refer to Figure 2
  and Table 1).  In addition to PCP, chromium and copper were found in 5
  locations in concentrations ranging from less than 1 to 15 mgAg
x (Table 2).

0 Ground Water Studies - PCP contamination in the ground water of the
  upper surficial aquifer was confirmed by the 1980 LETCO study, the 1980
  E&E study, and the 1983 GTI study (Figure 3 and Table 3).  Several
  other organic compounds were identified during the E&E and GTI
  investigations (Table 4).  Metals contamination was also identified
  during these investigations; however, only the E&E study found lead and
  chromium above the 1980 Water Quality Criteria.  Lead was found at a
  concentration of 105 ug/1 in monitoring well M-l and chromium was found
  at 300 ug/1 and 1960 ug/1 in wells M-l and M-2 respectively.

  In the E&E study for EPA and in the 1983 LETCO study, shallow auger holes
  were also sampled for ground water contamination.  These wells, which
  range in depth frcm 2 to 5 feet below the surface, revealed PCP concentrations
  in the ground water ranging frcm 12 ug/1 to 4,900 ug/1  (Table 5).

  Private wells were sampled in 1980 by E&E and by the Florida Department
  of Health and Rehabilitative Services (DHRS).  No contamination of private
  wells was found.  This is primarily due to the presence of a competent
  confining unit within the surficial aquifer, below which private wells
  receive water, and to the low solubility  level of PCP.
                                        (5)

-------

            IT
LEGEND
                                                                                        N
                                                                                        I
                                          IPH
                                       B-2
                                            M-6
                        LJ
     M-5®   »>M U.A     '     ;$
\rn PkM.,^v:^*s-5  '•
                                     t-^i.
                                      S3    M 8~S 4
                                  !•   i'i
                                        i.i     L
                               /
                                GINERAl  AVINIIt
• B-1    HAND AUGER  SAMPLE LOCATIONS (1980)

® M-5    MONITOR WELL LOCATIONS (1983)

• S'1    HAND AUGER  SAMPLE LOCATIONS (1983)
  P-1
  Figure  2.  Soil Sanple Locations Used  in Previous Investiq.il ions ol the Colimin I^vans Wood
            Preserviiic) Conpany Site.

-------
Table 1.  Results of Previous Soil Investigations  for PGP Contamination

Location
B-l
B-2
-• P-l
P-2
P-3

Depth
(ft)
3.5-5.0
3.5-5.0
0.0-3.0
0.0-3.0
0.0-3.0

Sartple By
LETCO
LETCO
GTI
GTI
GTI

Date
12/2-4/80
12/2-4/80
3/4-14/83
3/4-14/83
3/4-14/83
PCP
Concentrations
(mgAg)
320
430
<12.5
1,170
2,090
 M-5            0.0-3.0          GTI              3/4-14/83         1,490
 M-5            6.0-8.0          GTI              3/4-14/83           990
 M-6            3.0-6.0          GTI              3/4-14/83           616  •
 M-6            7.5-9.0          GTI              3/4-14/83           346
 M-7            0.0-3.0          GTI              3/4-14/83            11.0
 M-7            3.0-6.0          GTI              3/4-14/83            53.6
 M-8            0.0-3.0          GTI              3/4-14/83           787
 M-8            3.0-6.0          GTI              3/4-14/83           504
                                      (7)

-------
Table 2.  Results of Previous Soil Investigations for Metals Contamination
Location
S-l
S-2
S-3
S-4
S-5
Date
3/83
3/83
3/83
3/83
3/83
C o n c e
Chromium (mg/kg)
4.94
3.97
4.69
15.46
4.55
ntrations
Copper (mgAg)
4.01
1.42
1.56
12.55
<1.0
  Source:  LETCO, 1981
                                      (8)

-------
vo
i;-r-
LEGEN
9fSSi
3>M-1
• P-1
* A-1
'i
UJ
U
Z
Ul
5
>-
a
Ul
_j
UJ
o
D
i
^^S***£^^ j.
tt^""11^ ..,- • -4Vib~"~~ ";•"
	 . . < T , 1
f^=— --wi^cj mn ^ ' J
I AM~3 /
SC^L [ — i^"2 7 ^M-2
^ooooOP rnM^' 	 / i
J fe "• LI J * __- '« J
TP ' u * *""5^ ^l — 	 1 A-4'lf /' --
1 •• c^—j v -• 	 ( pl< **** 1 H' ^!A /t\
//v A- 2* _ ll D l""l Bp~3
I/* ^^ ~D 7 H 11 II
<\ is I — 1 F )• K5! n tCI!"! | ] r^j
U y P-6 / ^
GENERAL AVENUE ~
Ii 	 1 *
" rzi ^
i
EXISTING MONITOR WELLS
PRIVATE DRINKING WELLS
HAND AUGER SAMPLE LOCATIONS
                   c: 3.   Pontachlorophenol Grcuuid Water Sanqilinq Locations  Used in Previous  Invest iqat ions
                         ot tlie Colenvin LV.ins Wcxxl I'reservinc]  Coni}>any Site.

-------
  Table 3.  Results of Previous Ground Water Investigations for PGP
            Contamination.


Location
M-l
M-2
M-3
M-4
M-5
M-6
M-7
M-8
M-9
M-10
M-ll
M-l 2
M-l 3

Depth
(ft)
13
13
15
15
15
15
15
15
15
15
15
14.5
14.5


Sanple By
E&E
E&E
GTI
GTI
GTI
GTI
GTI
GTI
GTI
GTI
GTI
LETCO
LETCO


Date
12/16/80
12/16/80
3/4-14/83
3/4-14/83
3/4-14/83
3/4-14/83
3/4-14/83
3/4-14/83
3/4-14/83
3/4-14/83
3/4-14/83
12/2-4/80
12/2-4/80
PCP
Concentrations
(ug/1)
4,000
12,000
ND
1,480
332
1,370
525
714
560 '
ND
ND
2,000
3,200
ND - none detected

-------
   Table  4.  Results of Previous Ground Water Investigations for Contamination
             by Chemicals Other than PCP.


                                              Concentrations  iti  ug/1

                             M-l   M-2   M-3   M-4   M-5   M-6   M-7   M-8   M-9   M-10   M-ll


Naphthalene                  15    16

Bis(2-ethylhexyl)phthalate   16    75    —    —    —    58.3  15.7              —     —

Di-n-octylphthalate          —    —    —    —    —    —    55.3  —

Anthracene                   —    23    —    —    —    —    —    —    —
                                        i
Phenanthrene                 —    23
Phenol                       170   680   —    --    —    41.5  12.9  —

Toluene                      86    300   ~    —    —    —    —    14.3

Di-n-butyl phthalate         —    —    —    —    —    10.6  —    10.6

tluorene                     —    —    —    —    —    19.7  —

Isophorone                   —   . —    —    —    —    —    10.3  —




—  - none detected

Source:
Ecology and Environment, Inc., 1980  (MW-1 and MW-2)
Groundwater Technology,  Inc.,  1983 (Wells Other Than MW-1 and MW-2)
                                            (11)

-------
Table 5.  Results of Previous Auger Hole Ground Vfeter Investigations for
          PGP Contamination.
 Location
Depth
 (ft)
Sanpled By
 Date
      PCP
Concentration s
     (ug/1)
  A-l

  A-2

  A-3

  A-4

  A-5

  A-6

  A-7
 5.0

 3.0

 2.0

 3.0

 7.0

 5.0

 5.5
   BES

   BES

   BES

   BES

   BES

   LETCO

   LETCO
9/9/80

9/9/80

9/9/80

9/9/80

9/9/80

12/2-4/80

12/2-4/80
      537

    4,800

       12

    1,070

       12

    4,900

       20
                                     (12)

-------
  •f.
0 Surface Water Studies - The 1983 GTI investigation documents the
  existance of contaminated surface water runoff.  During a rainstorm on
  March 7, 1983, GTI collected two samples from the onsite drainage ditch
  (Figure 4).  The upgradient sample (SW-2) contained less than 10 ug/1 of
  PCP in background runoff.  The downgradient sample (SW-1) yielded 1,760
  ug/1 of PCP.
                                  (13)

-------
                   j
                                 ni
                                 II J
                          CJ
                                 r  .......     ..,
                           \r-TT  f      "' *"*       \
                                    i   KIM NO ruu
                                                       7
                                   *   I'l
                                                                          SW - 2
a
                                                               ''
                                7
                                  GENERAL  AVENUE
           /
                                                   a
                                                  N
                                                  I
LEGEND
  SW-1   SURFACE WATER SAMPLING LOCATION
     Figure  4.  Surface Water Sampling Locations Used in  the  T)83 C.roundwat er Technologies,  Inc
               Surface Water Investigation at the Colenvin  LVans Vvotx.1 Preserving Company  Site.

-------
                                SECTION III
                            CURRENT SITE STATUS
 Soils   '                                                          :

 Soil samples were collected from seven well defined areas as shown in
 Figure 5.  The collection areas were based on operation sites.  Samples
 were analyzed by an onsite laboratory, a local laboratory, and a Contract
 Laboratory Program facility in a three-tiered quality control program.

 The areal extent of PCP contamination at a one foot depth, as shown in
.. Figure 6, includes the landfill area in the eastern portion of the
 site, a broad area east of the treatment cylinder, a broad east^west
 trending area comprising the waste pits and storage tanks, and the north-
 south drainage ditch which is south of the Coleman Evans property.
 Although the pattern of PCP occurrences is similar for both of the depth
 intervals sampled, the 3-foot interval (Figure 7) was found to contain
 the highest concentration.  This is reasonable, because the PCP-laden oil-
 was observed to float on the water table,  which typically fluctuates from
 two to five feet below the surface.

 The vertical extent of contamination was identified from soil samples
 collected at 5-foot intervals from 12 boreholes (Figure 8).  Cnly
 trace levels of PCP were found in boreholes located along the northern
 portions of the site; however, boreholes 38, 40, 41, 44, and 49 encountered
 PCP concentrations above background levels (Table 6).  Generally, PCP
 contamination was limited to the upper 10 feet of the soils, except in
 two boreholes which showed PCP contamination to a depth of approximately
 35 feet; however, contamination found at depth did not exceed action
 levels.

 Several metals such as arsenic,  cyanide,  mercury,  thallium, and vanadium,
 were also identified in onsite soil samples; however, the Public Health
 Evaluation (Appendix A, FS) states that the metals occur at levels below
 or within the normal ranges found in typical soils of the southeastern
 United States,  Therefore, metals are not of concern at this site.

 CLP data confirmed the presence of onsite PCP contamination.  The only
 other chlorinated phenol detected in onsite soil was at sample location
 D-50, which contained tetrachlorophenol at an estimated concentration of
 4,000 ug/kg.  Additional organic contaminants detected include, but are
 not limited to, a variety of napthalenes,  alkanes, and xylenes, which
 are thought to be associated with the fuel oil.  Also found was Aroclor
 1254, a polychlorinated biphenyl (PCB), which was found at sample F-29 at
 a concentration of 30,000 ug/1.

 Several samples contained compounds that have been identified as possible
 laboratory contaminants.  These include acetone, methyl ethyl ketone,
 methylene chloride, and bis (2-ethylhexyl) phthalate.

-------
AREA 0
                                 GENERAL  AVENUE
                                                                 L-J
  LEGEND
AREA A - TREATED WOOD STORAGE
AREA B - TREATED WOOD STORAGE
AREA C - LANDFILL AREA
AREA D - CHEMICAL TREATMENT AREA


Fiquir ').  Ons.it r So.i 1 Soii^l IIKJ Arras (A
          Fit>M St inly .
                                          AREA E - WASTE DISPOSAL PIT AREA
                                          AREA F - DRAINAGE AREA
                                          AREA Q - REMAINDER  OF SITE
                                                                                           r>
                                                                                           5
                                                                                  LTD
                                                G) llstnl Dm in<)  thr I'.I'A K.'in •(! 1.11  Invi-.l i'|.il \«\\

-------
Figure 6.  Pentachloroph^nol Concentrations in Soils at a Depfth of. One Foot.   Iwxjrads Outline
           Areas with Pentachlorophenol Concentrations Greater tlv«n  1 mq/k().

-------
                                                                                                                         1 1

                                                                                                                      BH4O
                                                                                                         i »MOI it i »m

                                                                                          SOUTH PHOPtHIV IINE
                                                                                          'CP.«P«.8P.HM,ll,0«
                                                                                          " f001 OII>IN>
                                                                                     .-   ...«
                                                                                     00   *ttO« OdiCIION tlltll
                                                                                     •"! -  rcP COMClMm*lKM LOMIOUM
                                                                                     A   I€M»OH»»l> •OMHOK
                                                                                     O   «fO««Cl lAIWf
                                                                                                                                        00
b. «l 1 IN I t 1 I
                                                            GENERAL AVENUE
n  r
           Figure  7.   Pentachlorophenol Concentrations  in Soil  at  a I)c|>th ot Tin ex.- lv<-t.
                        Outline Areas with  Pentachlorophenol Concentrations C,i (\itci  th.ni  I

-------
                               GENERAL  AVtMUE
                                             a
                                                 a
                                    izn
  LEGEND
  AREA A - TREATED WOOD STORAGE
  AREA B - TREATED WOOD STORAGE
  AREA C - LANDFILL AREA
  AREA D - CHEMICAL TREATMENT AREA
AREA E - WASTE DISPOSAL PIT AREA
AREA F - DRAINAGE AREA
AREA Q - REMAINDER  OF SITE
Fiyure 8.  Location Map of Boreholes Used for Soil Samples During the EPA Remedial Investiqation.

-------
Table 6.  Results cf PCP Analyses of Soil Samples Collected from
          Boreholes Durino the IPA Remedial Investigation.
Sanple
Code
CES-
BH-35-1
BH-35-2
BH-35-3
Btt-35-4
BH-35-5
B»-35-6
BH-36-1
BH-36-2
BH-36-3
BH-36-4
Btt-36-5
BH-36-6
BH-37-1
BH-37-2
BH-37-3
BH-37-4
BH-37-5
BH-38-1
BH-3S-2
BH-3&-3
BH-38-4
BH-38-5
BH-38-6
BH-38-7
BH-3S-8
BH-36-9
BH-38-10
BH-40-1
BH-4G-2
BH-40-3
OMO-4
BH-40-5
BH-40-6
Depth
(ft bis)
5
10
15
20
25
30
5
10
15
20
25
30
5
10
15
20
25
5
10
15
20
25
30
35
40
45
50
5
10
15
20
25
30
PCP in Soil (mqAg)
Cnsite Dup. Onsite Local Dup. Local
Lab Lab Lab Lab
M)
ft)
M)
tt>
M)
M)
[*>
tr
MD 0.04
to
tr 0.06
ID
MD
ND
ND
ro
M) ND
1,025 585
37
205
2.3
0.09
tr
tr 0.3
M)
tr
tr
10
.45
tr
tr
tr
tr

CL?



M)

It)



ND

rc
ND



ND





ND


ND

ND




ND
                                (20)

-------
• z.
Table 6 (cont.).
                   Results of PCP Analyses of Soil Samples Collected from
                   Boreholes During the EPA Remedial Investigation.
Sample
Code
CES-
BH-41-1
BH-41-2
BH-41-3
BH-41-4
BH-41-5
BH-41-6
BH-42-1
BH-42-2
Bft-42-3
BH-42-4
BH-42-5
BH-43-1
BH-43-2
BH-43-3
BH-43-4
BH-43-5
BH-43-6
BH-44-1
BB-44-2
BH-44-3
mAA— A
BH-44-5
BH-44-6
Btt-44-7
BH-46-1
BH-46-2
BH-46-3
HH dfi 4
BH-46-5
BH-46-6
BH-49-1
BH-49-2
BH-49-3
RH dl A
BH-4^-5
Depth
(ft bis)

5
10
15
20
25
30
5
10
15
20
25
5
10
15
20
25
30
5
10
15
20
£w
25
30
35
5
10
15
20
«u
25
30
5
10
15
5f)
£w
25
PCP in Soil (mqAq)
Qnsite Dup. Cnsite Local Oup. Local
Lab Lab Lab Lab

0.6
tr
tr
M)
tr
K>
M)
M>
BH
MD
M> {O
tr
(0
to
tt>
(C
ft} MD
2.1
15.1
0.9 <1.6
jsT)
im^
7.0
1.25
M}
M>
M>
MD
MQ
V^J
ND
M> M)
tr 0.1
1.1
0.45 <1.6
^
tr 0.3

CLP

MD




M>
M)



M)
ND




ND



1.6

2.7

ND




ND


0.54

ND
                                     (21)

-------
    Table 6  (cont.) .
                       Results of  PCP Analyses of Soil  Samples Collected  frorr.
                       Boreholes During the EPA Remedial  Investigation.
Sample
Code
Depth
(ft bis)
                           PCP  in  Soil   (aq/k
Cnsite
 Lab
                             Dup.
Cnsite
  Lab
                                                  Lab
Dup.  Local
       Lab
                                                                         CLP
CES-
BH-50-1
BH-50-2
BH-50-3
BH-50-4
BH-50-5
BH-50-6
BH-50-7
              5
             10
             15
             20
             25
             30
             35
              tr
              M)

              NO
              M>
              M)
              ND
                                     tr
M>   Not Detected Above Detection Limit
tr   trace «0.45 mg/kg)
                                       (22)

-------
Surface Water and Sediments

Surface water and sediment samples were collected at the locations shown
in Figure 9.  The background sediment sample, SD-15, taken upgradient
along McGirts Creek, was found to contain a suite of metals, which included
antimony (69 mg/1), lead (11 mg/kg)» mercury (0.13 mg/kg), and nickel  (31
nxj/kg).  The surface water sample (SW-15) collected at this location, was
estimated to contain 9 ug/1 chromium.  Neither sample contained organic
compounds above the laboratory detection limits (Table 7).

Analyses of stream and stream sediment samples revealed the presence of
PCP in the water and sediments of the drainageway leading from the site
to McGirts Creek.  Surface water concentrations near the site exceed the
surface water criteria established in Chapter 17-3061.3 (M) FAC, but
attenuate to below these criteria prior to reaching General Avenue.  The
mechanism for this attenuation is probably a combination of dilution in
water and adsorption to soils.  Sediment samples were found to contain
low levels of PCP south of General Avenue, and no indication of PCP at
McGirts Creek.

HYDROGEOLOGY

Groundwater Characteristics

At the Coleman Evans site groundwater contaminants were identified in the
upper portion of the water table zone of the Surficial Aquifer System.
The Surficial Aquifer System is comprised of three units:  the water table
zone, the semi-confining unit, and the limestone unit.  In the site area
private groundwater supplies are obtained from the limestone unit which
is locally well-protected by the semi-confining unit.  Groundwater flows
to the south and south west of the site.

Groundwater Contaminants

Groundwater samples were collected from 12 new monitoring wells (Figure
10) and 13 private wells (Figure 11).  The well samples were analyzed
under, the CLP program, and no contaminants except for methylene chloride
were found, but it was identified as a laboratory contaminant.

New monitoring well sample results are presented in table 8.  The only
metals identified with concentrations above existing standards were
beryllium and magnesium, but based on the soils data, this occurrance is
believed to be natural.  Several compounds were identified in background
wells and in blank water samples and cannot be attributed to the site.
These compounds are bis (2-ethylhexyl) phthalate, hexahydroxepinone,
acetone, and toluene.

Several compounds were identified downgradient from the site, but not
onsite, carbon disulfide, 1,1,1-dichloroethane, and 3,3-dichlorobenzene.
Finally, PCP was identified in four onsite boreholes, but only BH-40
contained levels above the 1980 Water Quality Criteria of 1.01 mg/1.
                                       (23)

-------

                                                         COLEMAN EVANS
                                                         WOOD  PRESERVING
                            ^—-v-
'io«i«» L  \
            BASE MAP IS A PORTION OF THE
            U.S.G.S. MARIETTA. FLORIDA
            QUADRANGLE 7.5 MINUTE SERIES
            (PHOTO REVISED 1970)

     Figure 9a. Locations at which Surface Water and Sediment Sanples were
                Collected During  the EPA Remedial Investigation.

-------
to
m
                                     GENERAL AVENUE
                                   "\SW-20
                                      SD-20
             LEGEND
             SW-17 • WATER SAMPLE

             SD-17   SEDIMENT SAMPLE
         Piquio  <>\>.  Locations at which Surface Water and Sedi/nent Sairples were CoJ looted Durinq the

                    i:i'A Ktmxlial  Investiqation.

-------
    Table 7.  Analytical Results of  Surface Water  Sarrples  Collected  during the
              Remedial  Investigation.  Concentration Presented  in Micrograms
              per Liter (ug/1).


Pentachloro-
Phenol
C-ll Alkene
Total Xylenes
Sanple Location Nuirber
SW-15



SW-16



SW-17



r SW-18
4700x

7.1x
SW-19
77x
30x*

SW-20
360x


SW-21



SW-D1
3100x

7.7x
Aluminum
Antimony
Arsenic
870x


790x

6.5
640x


240x


570x
61x

600x


41 Ox
58x

200x
55x


Cadmium
Chromium
Cobalt

9x


9x





Iron
Lead
Magnesium
880x

1400x
760x

1600x
960x

5800x




360x

2800x
7x

llx

lOOOx

5700x



•~






HOOx
2.8x
6000x
1200x
2.2x
4900x
43Dx

2800>

Manganese
Potassium
Silver
29x


27x


21x


48x
1200x
7x
28x


33x


25x
1200x

62x
l20Cb
6x
Sodium
Tin
Zinc
6900x

26x
4800x


20,000x

15x
7000x
31x

22,000x

18x
21,000x

21x
23,000x
42x
44x
83(X)>


x = estimated value
* = tennatively identified carpound
                                   (26)

-------
      MW-610 BMW-52
MW-60
 •""•'WSP
                         /

                                                 Q
                          GENERAL AVLNUC
                MW-59
                                        a
                                                  «... ««
                                            n
                                            1~J
                                   MW-61
              LEGEND
LOCATION OF SHALLOW MONITOR WELL

LOCATION OF DEEP MONITOR WELL

LOCATION OF INTERMEDIATE

MONITOR WELL
                                                                         - N

                                                                         T
                                                              MW-57
                                                 czi
                                                      CLUSTER WELL

   Figure 10.  Location Map of New Monitoring Wells Installed cind Sampled Durincj the EPA

             Remedial Investigation.

-------
                       •PW-1
• PW-2
             T
             I
               4i     -
            [•
                                          (
                                          '
                                                       V
                                                           AREA
         PW-3
                          n\GJ__uuus-
                   n
                   Li
                                       1™f • Ml HfH
        II
3—i
                                       -PW-6
                                  OCHCRAL AVO4UC
                       •PW-14
                                                 /
                                                /
                                                      y

                                                     /
                                                             Q
                                                             ^

                                                          pw-12

                                                                              a
                                                                                                      00
                                                                                                      (N
                                                          LEGEND
                                                          PW-1» PRIVATE WELL SAMPLE LOCATIONS
1'i'juif  II.  I/ K-.it KM> Kip of I'rivato Wt;lls Son|)lo(l Durinq tln> Kl'A
                                                                            Invest iqat ion.

-------
   Table 8.  Analytical Results of Ground Water Samples Collected from
             New Monitoring Wells Installed During the Remedial
             Investigation.  Concentration Presented in Micrograms per
             Liter (ug/1).                                      :


3,3-Dichloro-
benzidine
Carbon
Disulfide
1 , 1-Dichloro-
ethane
Well Identification Number
MW-51



MW-52



MW-53



MW-54



MW-55

11

MW-56



Aluminum
Beryllium
Cadmium
3100


410


880


380


1800

6.0
380



Calcium
Chromium
Copper

18

60,000
24

8900


71,000
30

11,000


110,000


Iron
Lead
Magnesium
790
7.2x

470
21x
2300
2500
7.8x
2300
270

3200
2000


470
5.9x
3400
Manganese
Potassium
Selenium
20
4600x
5.5x
22
53,000x

58
6000x

21
24,000x

37
2800x

41
17,000x

Sodium
Zinc
22,000

26,000
85x
89,000
23x
18,000

40,000

19,000
30x
x = estimated value
                                   (29)

-------
   liable 8 (cont.
Analytical Results of Ground Water Samples Collected
from New Monitoring Wells Installed During the
Remedial Investigation.  Concentration Presented in
Micrograms per Liter (ug/1).


3 , 3-DJ chloro-
benzidine
Carbon
Disulfide
1,1-Dichloro-
ethane
Well Identification Number
MW-57

8.1x

MW-58

4.3x
4.3x
MW-59



r MW-60
200
6.2x

MW-61



MW-62

8.6x

Aluminum
Beryllium
Cadmium
810


440
7. Ox

550


860


1200


1400



Calcium
Chromium
Copper
3800
11

3400


1 3600



11

3100



13
46
Iron
Lead
Magnesium
4200


3600
6. Ox

2700

2500
2800
6.7x

4200
5.7x
2800
1300
9.4x

Manganese
Potassium
Selenium
61
3100x

69
4800x

28
2800x

20
4200x

33
2700x


6000x
7.4x
Sodium
Zinc
14, 000
39x
33,000
21x
24,000
41x
22,000
102x
24,000
89x
36,000
26x
x = estimated value
                                    (30)

-------
                                SECTION IV
                           ENFORCEMENT ANALYSIS
As noted  in Section  II of this document, the Coleman Evans Wood Preserving
Company has been  involved in  litigation with both the State of Florida
and U.S EPA.   In  Septeniber  1984, Florida filed suit against Coleman Evans
seeking relief which would  require the company to perform both short-term
and long-term  remedial actions at the site.  That suit is ongoing and
has recently been amended to  include charges of violation of RCRA
requirements.  In October 1984, EPA issued an administrative order pursuant
.to Section 106 of CERCLA, requiring Coleman Evans to conduct sampling
and perform immediate removal activities.  Coleman Evans refused to comply
with the  order, and  denied  EPA access to the site to perform the response
activities.  Therefore, in  March 1985, EPA filed a motion in Federal
Court, seeking an order which would permit EPA to enter the site and
conduct response  activities.  That motion was granted and EPA conducted
an immediate removal action in June 1985.

During the public comment period which followed the release of the RI/FS,
Coleman Evans  submitted a proposal for remedial action at the site.  That
proposal  suggested treatment of the contamination by biodegradation.  As
noted in  Section  V,  that alternative has been rejected due to concern
over the  extensive time period required and the possibility of incomplete
digestion of PCP  leaving a  dioxin residue.

Upon finalization of the Record of Decision, the Agency intends to formally
notify the company of the remedy which has been selected, and initiate
negotiations with them for  the conduct of the remedy.  If the company
does not  formally commit to perform the remedy, and provide assurances
that adequate  funding is available to complete the remedy in a timely
manner, EPA will  proceed with a Fund-financed Remedial Design/Remedial
Action.

It is important to note that implementation of the remedy recommended in
this jSunmary of Remedial Alternative Selection may temporarily disrupt
operations at  the Coleman Evans Wood Preserving Company during the
implementation of the Remedial Action.  The extent of the disruption,
if any, will be determined  during design of the selected remedy.

-------
                                SECTION V
                         ALTERNATIVES EVALUATION
PUBLIC HEALTH AND ENVIRONMENTAL OBJECTIVES

Public Health.  The public health threat posed by the Coleman Evans Site,
as identified in Public Health Evaluation (Appendix A, FS), is minimal.
Several exposure pathways are complete including   physical contact with
the contaminated soils, sawdust, and surface waters, inhalation of airborne
particulates, and the potential for ingestion of contaminated ground
water.  The Public Health Evaluation found that the site currently appears
to pose significant health threat based on the levels of contamination
which were identified in the Remedial Investigation, but potential exposures
are a risk.

Environmental Concerns.  The surface water levels of PCP identified in
the remedial investigation indicated that the site poses a threat to
aquatic species.  Unless the PCP runoff into the drainage ditch and
ultimately into McGirts Creek is prevented,  there is significant
potential for adverse environmental impact.

Alternatives Considered

Several alternatives were considered for remediating the Coleman Evans
site.  The alternatives were presented in groups targeted at remediating
a single aspect of the site.  Table 9 shows the technologies identified
for remediation of the ground water contamination (Group A alternatives),
and technologies considered for remediation of soil contamination (Group
B alternatives).

Several confcinations of group A and group B alternatives will provide
remedial actions which ccnply with applicable environmental laws.  One
example is a combination of ground water recovery and treatment (Group
A), and containment/encapsulation (Group B).  Ground water recovery and
treatment will respond to issues raised under the Clean Water Act (CWA),
the Toxic Substances Control Act (TSCA), and the Resource Conservation
and Recovery Act (RCRA).  These same laws are also addressed by containment
encapsulation of the landfill material.

Screening of Technologies

Potential remedial alternatives identified for the Coleman Evans site
were initially screened on the basis of technical feasibility and level of
protection provided to public health.  For example,  biological degradation
of PCP was eliminated during the initial screening phase because of the
protracted time frame necessary to accomplish cleanup and because incomplete
degradation can lead to a residue of dioxin in the soils.  Similarly,
thermal treatment was eliminated because this technology does not provide
any additional effectiveness compared to incineration of soils and it is
not cost effective compared to incineration.

-------
Table 9.  Technologies Considered for Remediation of the Coleman Evans Site.


 A.  Ground Water Technologies (Group A Alternatives)

     1.  Treatment Technologies
         a.  Flocculation, Sedimentation, and Filtration
         b.  Activated Carbon Adsorption

     2.  Recovery and Disposal Technologies
         a.  Recovery
         b.  Surface Water Discharge
         c.  Ground Water Recharge *

 B.  Soils Technologies (Group B Alternatives)

     1.  Treatment Technologies
         a.  Off Site Disposal
         b.  Solidification and Stabilization
         c.  Incineration
         d.  Solvent Extraction
         e.  Thermal Treatment *           '     .
         f.  Land Treatment *
         g.  Insitu Bicdegradation *
         h.  Containment and Encapsulation
         j.  Surface Capping

     2.  Recovery  Transport
         a.  Excavation
         b.  Transportation
 (*) = Denotes technologies vrtiich were eliminated during the
      preliminary screening phase.
                                   (33)

-------
The next phase of alternatives  screening was based on a detailed review
of each remedial alternative based on site specific criteria.  The second
phase review considered technical feasibility, the level of public health
and environmental protection provided, and on a relative cost-estimate
basis.  The alternatives eliminated during this phase are listed in
Table 10.

The alternatives Which were retained after screening were then described
in detail with regard to engineering considerations, equipment needs,
operation and maintenance needs, monitoring requirements, health and
safety, permitting requirements, scheduling projections, and cost estimates.


Technologies Eliminated

Several alternatives were eliminated in the preliminary screening phase
and in the detailed screening.  The following is a list of remedial
options which were eliminated during the screening phases and the reasons
for elimination.

Ground Water Technologies.

Ground Water Recharge.  Dae to  the locally high water table, ground water
recharge of recovered ground water would likely flood the surface
environment.  This alternative  was eliminated in favor of discharge to
surface waters.

Flocculation, Sedimentation, and Filtration.  This technology is feasible
and the risks to worker safety  and the environment are short-term.
However, carbon adsorption was  found to be equally feasible and had none
of the short-term risks.  Therefore, this remedy was screened out in
favor of carbon adsorption.
Soil Technologies.

Thermal Treatment.  Thermal treatment was eliminated because the effective-
ness of this technology is equivalent to incineration, but incineration
is significantly more cost effective.

Land Treatment.  This technology requires a large land area, extensive
material transport and handling, and extensive monitoring.  Other
technologies identified have fewer implementation constraints and are
equally effective.

In Situ Biological Destruction.  Incomplete digestion of PCP could leave
dioxin by-products.Biological treatment requires extensive pilot testing
and the time involved in execution of this technology is protracted.
                                  (34)

-------
Table 10.  Technologies Eliminated During the Coleman Evans Wood Preserving
           Ccnpany Feasibility Study Screening Process,
TECHNOLOGIES ELIMINATED
REASON
Ground Water Technologies

Flocculation, Sedimentation,
  and Filtration

Ground Water Pecharge
Carbon adsorption is equally
effective and less expensive

Recharge rates are too slow
for effective implementation
Soils Technologies

Thermal Treatment


Land Treatment



In Situ Biodegradation
Incineration is equally
effective and less expensive

Requires large areas of
land and long term (30
years) monitoring

Requires extensive testing,
long implementation period,
and may leave dioxin
residuals
                                   (35)

-------
ALTERNATIVES RETAINED

Several technologies were retained  for  final consideration as alternatives
for remediating the site.  Those alternatives retained are listed in
Table 11.  With the exception of the No Action Alternative and surface
capping, all technologies inherently include ground water recovery and
treatment due to the fact that these technologies require dewatering for
excavation.

Each of the remaining alternatives was  evaluated based on technical
feasibility, environmental impact, and  public health concerns (Table 12).
The present worth and operations and maintenance costs are presented in
Table 13.  Technologies which were  found to be feasible for the Coleman
Evans site are described below.

Ground Water Technologies

Alternative 1.  Well Point Ground Water Recovery, Carbon Adsorption, and
Surface Water Discharge.  This technology involves a mobile well point
configuration for recovery of contaminated ground water and for dewatering
of excavation areas.  Recovered ground water would be analyzed,  and treated
if contamination is found.  Treatment will involve passing contaminated
ground water through a carbon adsorption unit.  This technology is well
proven and can have removal efficincies up to 99%.  Discharge would
be to the surface water environmemt.  The contaminant concentration in
effluent must be less than 1 ug/1 in order to comply with State surface
water standards for PCP.

All excavation technologies inherently will require use of this recovery/
treatment/disposal option.  Therefore,  this technology has been included in
all excavation options, and carbon adsorption has not been cost evaluated
as a single item.

Soil Technologies

Alternative 1 - Surface Capping.  This option involves leaving contaminated
soils in place and constructing a RCRA-approved cap over identified areas
of PCP soil contamination.  A cap will prevent runoff of PCP into the
surface water environment, reduce air emissions,  and prevent further
migration of PCP into the soils.

Alternative 2 - Containment and Encapsulation.  This technology consists of
constructing an impermeable barrier,excavating the contaminated soils and
placing the soils within the impermeable barrier, and capping the soils
to provide full encapsulation onsite.  Ultimately, the contaminated soils
would be removed from contact with the environment.

Alternative 3 - Solidification and Stabilization.  This technology would
require excavation of contaminated soils and solidification by using a
mixture of soils with either a cement - based process or other pozziline
process, and on-site storage to solidify the contaminated soils.  Although
pilot testing would be required, this technology will reduce the solubility
or mobility of the wastes or may detoxify the contaminants.
                                     (36)

-------
 TABLE 11.  Remedial Technologies Retained for Detailed Evaluation.
        1.   Surface Capping
        2.   Containment/Encapsulation*
        3.   Solidification and Stabilization*
        4.   Off Site Disposal*
            a.   Etnelle,  Alabama
            b.   Pinewood,  South Carolina
        5.   Incineration *
        6.   Solvent Extraction *
        7.   No Action
(*)  = Denotes technologies that inherently require groundwater
      recovery operations to facilitate excavation activities.
                              (37)

-------
                Table  12.   Surrmary of Evaluation of Remedial  Alternatives.
                 Alienist I ve
              I .  Surface
                 Capping
              Cost  Conf Hence
              OnTI  Co a I ~flange*
              17.85 to 4VM
                                    Technical  feasibility
                   Conventional  equivalent
                   t> procedure*  are  uaed
                   (or capp 1 ng .
    Kuv 11 01 t-.ent a 1  l*»t>ac I


Hr it urea air eat as 1 ona,  nur-
face runoff f I den* a I con-
Inrt . (.round water re-tain*
cont ami itnt ed .
                                                                                                 Public Health Concern*
                               Potential  risks of people
                               drinking contaminated water
                               or  Ingesting vegetable*
                               having accumulated PCPa.
                                                                                                                 InatItutlonal  Requlremenla
                                                             Requirement* for 4OCKK I'nrta
                                                             760 through 264 for  closure
                                                             plana applicable to  aurface
                                                             capping.  I)KR permit.
U)
CD
              2.  Sol Idl ( leal Ion  Conventlonal  equipment
                                 & procedurea  uaed for aoll
                                 excavation  &  aol Idl f Icat Ion .
                                 Cleanup effeel Ivenea* must
Coal Conf Idence
Unit Cost Range*
87.81 to 99. /I
                                 be  verified  with leach
                                 teat a .
SolIdlIIcatIon of contami-
nated aolla will minimize
possible adverae environ-
mental Impact a.
                              Rlak  exposure of workera
                              during excavation la high.
                              After colIdlfIcatIon. rtak
                              of  exposure to contaminated
                              aolla la low. The rlaka of
                              ground water contamination
                              wl11  be algnlfleant ly
                              reduced.
                                                             Local permits  may  be required
                                                             for alte  activities. Slate I>KR
                                                             permit  RCRA  permit  required  for
                                                             discharging  treated water to
                                                             NcClrta Creek. Requirement of
                                                             of 40CPR  Parts 760 through 264.
                                                             170 » 124  are  applicable for
                                                             solldlflcallon/alahlllzallon.
              1. Containment &
                 KncapaulatIon

              Cost  ConfIdence
              Unit  CoHt Range*
              ^8. IS to  76.71
                    Conventions!  equipment
                    and  procedures used lor
                    aol I  exi aval I mi &
                    Conl a I iiMent .  Vi a I tied
                    pelHOlliiel  ncf-tt*d tor liner
n.ltt «ellioo«alble fiivl ruiiMcnl a I  1«^
|.A< t n .  '.i» Ht *•(  envl i uii«rn-
lal  rlak than Allcruntlve.1
I  i '2.  .Lie l.i |>oa»lbLe  tm\\
ti i c »f  ( he I I lie r .
                               • laka aaaoclated with process Requirements  for 40 CKH Part a
                               Include worker*' exposure to  760 through  2h4  RCRA specifics
                               contaminated aoll* i duat     tlona for TSO (acllltli-s.
                               particle* during excavation.
                               The long-term Incremental re-
                               duction In rlak Include* elim-
                               ination of air, surface i
                               ground water pathway*.
              4 .  So 1 vent
                 KxlractIon

              C.nn t Con f I dence
              Unit Coil Range*
               lit).(10-440. I/
                    Speclsllzed e<|til|*ment ft pe r -
                    ftoiine I  needed f»i  solvent
                    extraction. Common equipment
                    &  |>roce.|uir use I tor
                    eHt avni I on .
fCP tout ami nat ed soils  are
rxliHtled & potential ad-
veine env I i oiiment M I  Impact
IK all Igsl ed .
                               Same  concerna regarding ex-   Same as All c^rnat I ve  I,  |>lun Ixil
                               ravbal Ion a*  Alternative I.   permits for  I r annpor I al I	>l
                               llalng a  non-toxic aolvenl      o( com ent r ill i-d  extisitr.l
                               will  achieve  an overall risk  fluids containing  l'( P« .  M'A
                               ir.liullon from PCP contaml-   msnlfenl  .loi  ument nt I on
                               nat I on .                        requ I r eif.

-------
         Table  12  (cont.).   Sunrnary of  Evaluation of Remedial  Alternatives.
U)
VO
             Alternat tve
   Technical Feasibility
          •>. lucliierat Ion
          Cost Confidence
          Unit Cost Range*
          I88.U2-2U6.94
    Environmental  Impact
                                                                                          Public Health Concerns
                               Institutional Requirements
Common equlpaienl  ft proce-
dure* used for sol 1  excava-
tlon. Specialized equipment
ft expert technical personnel
required. Incineration has
•echanlcal component a sub-
ject to breakdown 4 costly
delays.
Sliort-terai potential  for
releases of tonic eislaslona
& residues Into environment.
Effective engineering ft man-
aKesient of air pollution con-
trol ft quenching system will
mitigate passible environmental
risk.
High potential  for risk
reduction or organic PCP
contaminants.
This option may  demand air
quality 'pentta  from UK.H .
          6. Off site
             Disposal

          Cost Confidence
          Unit Cost Range*
          188.36-224.89
Common equipment ft proce-
dures uaed for aoll excava-
tion • offalte trucking.
Possibility of spill during
transportation of soils.
This alternative will have    This  alternative will have    State a Federal IX>T permits
additional (low) envlronmen-  Incremental  public health     required for transportation of
tal rlaks due to possibility  rlaka reduction because PCPs  contaminated soils. H'A maul-
of spills during transports-  are  removed  4  tranaported.    fest documentation required.
t Ion.
          7. No Action       No additional equipment  or
                             facilities required.
                              High possibility  of  wast*
                              migration via suit see  runoff
                              ft ground water.  Possible
                              Impact  on receiving  walera.
                              Possible  rlaks of  Ingest Ion,
                              dermal  contact a  Inhalation
                              of  PCPs at  levels  considered
                              tonic  to  humans.
                                                                                                                      None
          • Unit costs are expressed In dollars per ton.

-------
Table 13.  Cost Estimates of Retained Remedial Technologies
Technologies
Surface Capping
Containment /Encap-
sulation *
Solidification *
Offsite Disposal *
Pinevood, SC
Emelle, AL
Incineration *
Solvent Extraction
Present Worth
Construction
Cost Dollars
447 , 950
992,000
1,4%, 000

3,606,000
5,088,000
3,703,000
5,767,400
Present Worth Total Present
O&M Cost, Dollars Worth Cost
334,000 781,950
334,000 1,326,200
218,000 1,714,900

0 3,606,600
0 5,088,000
0 3,703,000
41,700 5,809,100
(1)
Ratio
1
1.70
2.19

4.61
6-51
4.74
7.43
          (1) = Ratio of technology costs over the cost of the technology with the
               lowest present worth cost.

            * = Costs include ground water recovery and treatment operations.
                                           (40)

-------
 ' '£..
Alternative 4 - Offsite Disposal.  This technology involves excavation of
contaminated soils and transport to an offsite RCRA-approved facility for
treatment, storage, or disposal.  Approved facilities exist in Bnelle,
Alabama and Pinewood, South Carolina.

Alternative 5 - Cnsite Incineration.  This option would involve the use of
a temporary incineration facility to destroy PCP in contaminated soils
excavated from the site.  Contaminated soils would pass through a primary
chamber to "flash" the PCP from the soils and PCP destruction would occur
in a secondary chamber with higher temperatures.  The soil residue would be
used to backfill excavation trenches after analysis had demonstrated that
the PCP had been efficently removed.

Alternative 6 - Solvent Extraction.  "Soil Washing" would consist of using
some type of solvent such as methanol to remove toxic substances (PCP) from
the soil.  Treatability studies conducted during the Remedial Investigation
demonstrated that this technology is feasible for this site on a bench
scale.  However, full scale testing will be required.

Alternative 7 - No Action.  This option would preclude further EPA involvement
with the Coleman Evans site and no further expenditures of Superfund money.
Institution of the no action alternative may not immediately impact public
health or welfare, but it would allow PCP contaminated site runoff to
continue to enter the surface water regime, thus contributing to the
deterioration of the environment.
                                  (41)

-------
                                 SECTION VI
                       COMMUNITY RELATIONS ACTIVITIES


Carmunity relations efforts for the Coleman Evans site were initiated in
November 1984 when EPA personnel visited the site along with personnel from
the REM II community relations contractor, ICF, Inc.  Attempts were made
to contact area residents; however, neighborhood response ranged from dis-
interest to strongly negative sentiment.  Only two area residents agreed to
discuss the site: Mr. H.G. Moore,  10917 General Avenue, and Mrs. Mamie Norman,
10904 General Avenue.

An information repository was established at the Whitehouse Elementary
School near the site, and all finalized documents were placed on file to
provide local public access.

Curing the RI/FS process, EPA was never contacted by concerned citizens with
regard to the Coleman Evans site; although sporadic press interest was
generated.

At the completion of the RI/FS process, EPA published and mailed a fact
sheet to interested parties as identified in the March 1985 Community
Relations Plan.  On August 7, 1986, a public meeting was held to discuss the
findings of the RI/FS.  Attendance was light  and the question and answer
session was not extensive.  The public meeting served to initiate a 3 week
public comment period which closed on August 28, 1986.  The only written comment
received during this period was a proposal for a remedial action submitted by
Coleman Evans contractors.  The responsiveness summary was completed on
September 16, 1986, and placed into the information repository.  A copy of
the responsiveness summary is presented in Appendix A.

-------
                                SECTION VII
    z-            CONSISTENCY WITH OTHER ENVIRONMENTAL LAWS
Environmental Laws which may be applicable or relevant to the remedial
activity are:                                                     _._

      —  Safe Drinking Water Act  (SDWA)
      —  Resource Conservation and Recovery Act (RCRA)
      —  State of Florida Administrative Code Chapter 17-3.061.3(m)
            - Surface Waters:  General Criteria
      —  Federal Water Quality Criteria (WQC)
      —  Clean Air Act (CAA)
Locally private wells obtain water from the limestone unit of the surficial
aquifer system, which is protected by a high integrity confining unit.
During the RI field study, numerous private wells were sampled and analyzed.
The results indicated that the private wells have not been impacted by the
site.  Therefore, the residents currently have a safe drinking water supply,
as specified under the SCWA.

The no-action alternative would not comply with the Hazardous Waste
Regulations identified in Subtitle C of RCRA.  However, all other
alternatives being considered are in accordance with RCRA Subtitle C.  The
selected alternative, as outlined in Sectin VIII, includes excavation of
contaminated soils.  In order to implement soil excavation, the upper
portion of the aquifer will require dewatering.  Contaminated ground water
must be treated until the PCP concentration is less than 1 ug/1 in order to
comply with the surface water discharge levels set forth in Chapter 17-3
061.3 (m) FAC.  This level was established by the State of Florida to
protect aquatic species.  The Federal Water Quality criteria has not
established a standard for PCP to protect aquatic species; however, a
human health criteria of 30 ug/1 was established to prevent organoleptic
effects.  A soil cleanup level of 10 mgAg was based on risks identified in
the Public Health Evaluation (FS, Appendix A).

Incineration activites would be conducted in accordance with the applicable
permitting standards and operations protocols established in the Clean Air
Act.  A quality assurance program would be developed under the remedial
design phase.

The National Resource Damage Assessment conducted by the Fish & Wildlife
Servive concluded that the Coleman Evans Site has not impacted any federal
trustee resources (Appendix B).  There are currently no threatened
wetlands and the site is above the 500-year flood plain (Figure 12).

-------
Figure 12.  500-Year Flood Potential Map for the Area Surrounding
            the Coleman EVans Wood Preserving Company.  Zones
            Designated with the Prefix "A" Indicate Areas of 100-
            Year Flood levels  (Dark Areas) and 500-Year Flood Zones
            are Designated with the Prefix "B".  National  Flood
            Insurance Program  Insurance  Rate Map  #12007-0500-0.
                           (44)

-------
                                SECTION VIII
                          RECOMMENDED ALTERNATIVE
'SELECTED REMEDY

The recommended alternative for the Coleman Evans site consists of excavating
all soils which have PCP contamination in excess of 10 mgAg/ and destruction
of the contaminants through onsite incineration.  In order to excavate the
contaminated soils, dewatering will be necessary.

A mobile incinerator will be used onsite to destroy the PCP found in soils.
The process will involve use of primary and secondary incineration chambers.
PCP and diesel fuel will be converted to gaseous phases in the primary
chamber and thermal destruction will occur in the secondary chamber.
Decontaminated soils will retain virtually their initial volume and can be
used to backfill excavation areas.  The total volume of soils to be treated
is estimated to be 9,000 cubic yards.

Ground water recovery will involve localized use of well points, which are.
sufficient for the shallow excavation depths (less than 20 feet) necessary
at this site.  Areas in which ground water contamination was identified
coincide with areas of soil contamination, thus there is little risk of
allowing contaminated ground water to escape; however, all ground water with
PCP concentrations greater than 1 mg/1 will be recovered.  The recovered
ground water will be analyzed and treated by activated carbon adsorption if
PCP concentrations exceed 1 ug/1.  Treated effluent will be discharged to
an on site drainage ditch.  The spent carbon will be thermally regenerated,
which will destroy the remaining PCP contamination.  The volume of ground
water containing PCP in excess of existing standards is conservatively
estimated to be 900,000 gallons.

Other incidental Hazardous Substance List compounds identified in the ground
water during implementation of this remedy will be cleaned up to levels
which comply with Drinking Water Standards.  If the Drinking Water Standards
do not address these compounds, cleanup levels will be consistant with the
human health criteria identified in the 1980 Water Quality Criteria.  Clean
up of"compounds for which no standards exist will be to non-detection levels.
In cases where standards promulgated by the State of Florida are more
stringent, the state standards will have precedence.  Also, should EPA
promulgate standards which are more stringent than existing standards or
criteria, the newer standard will be implemented.

Since this alternative provides total destruction of the wastes, long term
monitoring is not required, nor will there be any operation and maintenance
costs associated with this remedy.  Nor will land use restrictions be
imposed.
COST-EFFECTIVENESS

This remedy selected for the Coleman Evans site is the most effective
alternative, and is considered to be the most permanent remedy of choice
which resolves the threats posed by the site.  The environmental benefits

-------
gained outweigh the financial advantages gained by selecting a more
cost-effective solution.  A summary of feasible alternatives and rejection
criteria are presented in Table 14.

The selected remedy is estimated to cost between $3.0 and $3.8 mrilion
dollars.  The State of Florida has instituted a program for addressing the
problems posed by uncontrolled hazardous waste sites.  This program is
designed on the CERCLA model and is operated similarly to Superfund
through the Florida Department of Environmental Regulation.  The State of
Florida has agreed to fund 10% of the cost for implementing the selected
remedial action (Appendix C).  The City of Jacksonville Bio-Environmental
Services Division has also concurred with the selected remedy (Appendix D).
                                  (46)

-------
      Table  14.   Sutmary Table of  Feasible  Alternatives  and  Cost-Effectiveness
                  Comparison.  Costs  Presented  in  Millions  of Dollars^
 Remedial  Alternative
    Reason for Non-Selection
Estimated
Cost Range
 1.  Surface Capping
Implementation would not deal permanently
with the site contamination although
it provides a high degree of protection
to surface water and air.  Groundwater
contamination would remain.  Restricts
site use.
                                                                                0.5 to 0.9
.2.  Solidification and
     Stabilization
This is a viable alternative, but
contaminants would remain on-site
and long-term monitoring would be
required.  Land use limitations
 1.4 to 1.9
 3. Containment  and
      Encapsulation
This is a cost-effective option, but
contaminants would remain untreated.
Greater environmental risk arises from
the potential for liner failure.  Long
term monitoring and O&M will be required,
 0/7 to 1.5
 4.   Solvent  Extraction
This option is fully effective for
migration of all threats, but incineration
is equally effective with a lower cots.
 4.5 to 9.6
 5.  On-Slte  Incineration
                                              3.0 to  3.8
 6.   Off-Site  Disposal
Does not remediate wastes, only involves
transport to a RCRA-approved facility.
 2.9 to 4.2
 7.   No Action Alternative
No remediation of site specific conditions
potential health and environmental risks.
    0.0
                                        (47)

-------
                                 SECTION IX
                         OPERATION AND MAINTENANCE
No operation and maintenance will be required for the selected remedy since
all existing contamination will be thermally destroyed.

-------
                                 SECTION X
                               FUTURE ACTIONS
Successful implementation of the selected remedy will ultimately remove the
Colemari Evans Wood Preserving Conpany site from under the jurisdiction of
the Comprehensive Environmental Response, Compensation and Liability Act
once it has been deleted from the NPL.  Future site actions will be limited
to applicable aspects of the Resource Conservation Recovery Act (RCRA), for
the duration of the facility's existance.

-------
                                  SECTION XI
                               PROJECT SCHEDULE
The schedule for the RD/RI phases of the Coleman Evans Wood Preserving Corrpany
remediation are dependent on the success of enforcement negotiations.  If the
PRPs agree to undertake RD/RA, the schedule will be negotiated to acconrnodate
EPA, FDER, and the PRPs.

If, however, negotiations with the PRP are unsuccessful, EPA will follow
the schedule outlined below:
Schedule Landmark
1. Finalization of the ROD
2. Complete Enforcement Negotiations
3. Award Super fund State Contract (and
IAG) for Design
4. Initiate Design
5. Complete Design
6. Award/Amend Superfund State Contract
(and IAG) for Construction
7. Initiate Construction
8,. Complete Construction
Date for
Impl ementaion
9/30/86
12/31/86
2/31/87
4/1/87
10/1/87
10/30/87
12/1/87
12/1/89

-------
      APPENDIX A

 RESPONSIVENESS SUMMARY

     Coleman Evans
Wood Preserving Company

-------
            REGION IV

COLEMAN EVANS WOOD PRESERVING CO.
     RESPONSIVENESS SUMMARY

       September 16,  1986

-------
 .                          RESPONSIVENESS SUMMARY
                 COLEMAN EVANS WOOD PRESERVING COMPANY SITE

                   U. S. ENVIRONMENTAL PROTECTION AGENCY
                                 REGION IV
This is the Responsiveness Summary for the Coleman Evans Wood Preserving
Company site in Whitehouse, Duval County, Florida.  Since the EPA received
written comments from only one source during the Feasibility Study public
comment period, this document consists of a summary of the community
relations activities conducted at this site, a response to the one written
response received, the Feasibility Study fact sheet, and the transcripts
from the public meeting.

Following the Work Plan phase of the study from September 1984 to April  .
1985, the Remedial Investigation/Feasibility Study (RI/FS) for the site was
conducted from June 1985 to June 1986.  EPA received no telephone calls or
letters from the public concerning the site during that time.  A community
relations plan describing community concerns and recommending community
relations activities was prepared in March 1985.  In accordance with the EPA
National Contingency Plan and suggestions made in the Community Relations
Plan, EPA established an information repository at the Whitehouse Elementary
School.  The repository contained public documents on the site, including
the RI/FS work plan and the RI/FS report.

Once the draft FS was completed, a fact sheet (Attachment A) was prepared to
describe the remedial technologies that EPA was considering for the site,
the proposed clean-up goals, and the details of the public meeting and the
public comment period.  The fact sheet was mailed to individuals on the
Coleman Evans site mailing list and placed in the information repository.
Announcements for the public meeting and the public comment period were
placed in local papers.  EPA held the public meeting on August 7, 1986 and
the public comment period covered the period from August 7 to August 28,
1986.  Approximately 10 to 15 concerned citizens attended the public meeting.
The~transcripts of the public meeting are presented in Attachment B.

The only written response received was from Ground Water Technology, Inc.
(GTI), a consultant for the Coleman Evans Wood Preserving Company.  The GTI
proposal is summarized below, and the full document is presented in
Attachment C.
Cctnnent Summary

GTI submitted a response to the Feasibility Study.  The document which was
submitted was a "Response to Feasibility Study" in which GTI outlined a
proposal to undertake photo/biodegradation of the contaminated waters and
soils at the site and to recovery and recycle the free-floating pentachloro-
phenol/diesel fuel mixture from the surficial aquifer.  The proposal included
site history, a work plan, a monitoring program, a cost evaluation, and a
photo/biodegradation process summary.

-------
Response

EPA reviewed the potential application of biodegradation for the Coleman
Evans site during the Feasibility Study and has reviewed the proposal
submitted by GTI.  This technology was eliminated during the earl%r phases
of the Feasiblity Study because of technical problems associated with
biodegradation.  First, the feasibility of this process would have to be
determined during a long term pilot testing program, especially since there
have been limited previous studies which evaluate biodegradation of
pentachlorophenol.  Second, the volume of contaminated soils (estimated to
be 9,000 cubic yards) would require a long period of time for complete
digestion of the contaminants, especially at the greater depths of
contamination identified during the Remedial Investigation.  Third, the
contaminants which are at depth may exist under anaerobic conditions.  In
order to evaluate biodegradation as a feasible option, a very wide range of
conditions would have to be implemented during the testing process.  Finally,
there is a potential for the creation of unacceptable by-products during
the biodegradation process; specifically dioxins.  Generation of dioxins
vsould further increase the risk to the public health and welfare, and to
the environment than is currently posed by pentachlorophenol, the main
contaminant of concern.
Although the financial aspects of biodegradation are attractive, the
potential for greater health and environmental risk and the long periods of
time required for testing and implementation are unacceptable to EPA.  For
these reasons- EPA eliminated biodegradation technologies during the Coleman
Evans Feasibility Study process.  EPA has determined that biodegradation is
not sufficiently proven to be an acceptable option for remediation of the
conditions at the Coleman Evans Wood Preserving Company site.

-------
      APPENDIX B

   Natural Resource
   Damage Assessment

     Coleman Evans
Wood Preserving Company

-------
              United States Department of the Interior

                           OFFICF  OF THE SECRETARY
                                   -liTON, D.C.  20240
                                                           JUN 2 I  '335
  ER84/1518
  Mr. Gene Lucero, Director
  Office of Waste Programs Enforcement
  Environmental Protection Agency
  401 M Street, SW (Room S362N) WH 527
  Washington, D.C. 20460

  Dear Mr. Lucero:

  The Department of the Interior has conducted a preliminary natural resources survey of
  the Coleman/Evans Wood Preserving Company at Whitehouse, Duval County, Florida, to
  determine whether  the  Secretary of  the  Interior's  trust responsibilities for natural
  resources have been affected.

  Our survey indicates that there are no lands under the trusteeship of the DOI near the
  Coleman/Evans  site.  However, the  Ortega River system nearby  can  be inhabited by
  various trust resources, including  anadromous fish, migratory birds, and endangered and
  threatened species  of  wildlife. The manatee, an endangered marine mammal, can be
  found in the Ortega River system.

  Site visits and review of various reports and studies show that soils and surface waters
  have not been seriously  contaminated  very far off  site.  There  is no documentable
  evidence that our  trust  resources have been  affected  by  materials from  this site.
  However, we  believe the site should be cleaned up quickly so that  contaminants do not
  move off site.

  Accordingly, we would grant a release  from claims  for damages  to natural  resources
  under our trusteeship from the  Coleman/Evans  site, provided that timely  remedial
  action consistent with the NCP is  taken to clean up the site.

                                        Sincerely,
                                             Blanchard, -Director
                                       Office of Environmental Project Review
  cc:
£_Steve Klein/EPA

-------
      APPENDIX C

   State of Florida
 Letter of Concurrence
        for the
    Selected Remedy

     Coleman Evans
Wood Preserving Company

-------
                             STATE OF FLORIDA
           DEPARTMENT OF ENVIRONMENTAL REGULATION
TWIN TOWERS OFFICE BUILDING
2600 BLAIR STONE ROAD
TALLAHASSEE, FLORI DA 32301-824 1
              BOB GRAHAM
          ?T     GOVERNOR

        VICTORIA J. TSCHINKEL
               SECRETARY
                                  September 24, 1986
   Mr. Jack Ravan
   Regional Administrator
   United States Environmental
     Protection Agency
   Region IV
   345 Courtland Street, N.E.
   Atlanta, Georgia  30365

   Dear Jack:
    - a p ?/ -L-  •
  v 1^2 /T, r~: ;•; r->" ' •?' ™ ,~
L';
    SEP 25 1985
   The Florida Department of Environmental Regulation agrees with
   the selection of Alternative #5 as described in the final
   feasibility study for the Coleman Evans Wood Preserving Superfund
   Site in Whitehouse, Duval County, Florida.

   This alternative includes the excavation and on-site incineration
   of soils and sediments, and the on-site treatment of contaminated
   ground water.  This alternative will effectively destroy contam-
   inated soils and sediments and treat ground water.

   The cost estimate for Alternative #5 ranges from $3.0 - $3.8 mil-
   lion for the use of a temporary on-site incineration facility,
   and groundwater treatment unit.  Due to the complete destruction
   of site specific contaminants by incineration, no post-remedial
   monitoring or operation and maintenance activity is required.
   The state will provide ten percent of the total cost, or about
   $300,000 - $380,000 from the State Water Quality Assurance Trust
   Fund.

   We look forward to participating with the U. S. Environmental
   Protection Agency during implementation of  remedial activities
   at the Coleman Evans .Wood Preserving site.

                                  Sincerely,
                                  Victoria J. Tschinkel
                                  Secretary
   VJT/ps
                      Protecting Florida and Your Quality of Life

-------
      APPENDIX D

 City of Jacksonville
 Letter of Concurrance
        for the
    Selected Remedy

     Coleman Evans
Wood Preserving Company

-------
DEPARTMENT OF HEALTH, WELFARE
& BIO-ENVIRONMENTAL SERVICES
Bio-Environmental Services Division
         May 21, 1986
 Ms. Kristina Teepen
 Remedial Project Manager
 U. S. Environmental Protection Agency - Region IV
 345 Courtland Street
 Atlanta, GA  30365	

     RE: Coleman Evans Wood Preserving Company                        ;-
         Draft Feasibility Study

 Dear Ms. Teepen:

 The  Bio-Environmental Services Division  (BESD) has briefly reviewed  EPA's  Draft
 Feasibility Study of Coleman Evans Wood Preserving Company, dated May 2, 1986.

 The  BESD  would support the option of incineration, over the  other  options  for
 remedial  actions,  as presented.  Incineration provides  the  following  benefits
 which BESD feels are noteworthy.

     I.  Destruction of the organics

    II.  Usability of the site after contamination disposal

   III.  No requirement for continual monitoring

 Incineration,  of  course,  as  an option needs to  be  better  defined  prior  to
 implementation.  Specifically such items as retention times, in situ   monitoring,
 etc. must be detailed.  Further, in order for incineration to be viable, just from
 a  permitting  standpoint, a great deal of public awareness and education  on  the
 benefits—of the program shall be necessary.  Otherwise a permit may be delayed  as
 a result of public concerns requesting Administrative Hearings.

 If BESD can be of further assistance, please advise.

                                                 Very truly yours,
                                                  obert Steven Pace, P.E.,
                                                 Bio-Environmental Engineer
 cc: Mr. Ernest E. Frey, P.E.
     John K. Flowe, P.E.
     Khurshid K. Mehta, P.E.

 RSP/ns
DER
        AREA CODE / 904 / 633-3318 / 515 WEST 6TH STREET / JACKSONVILLE, FLORIDA 32206-4397

-------
      APPENDIX E
PUBLIC HEALTH EVALUATION
       Submitted
          by
       CDC/ATSDR
     Coleman Evans
Wood Preserving Company

-------
  _. ttiviri, ^
 •;*'    '"J

(4
  •<"..<,£<•
   Date
   From
   Subject
   To
DEPARTMENT OF HEALTH & HUMAN SERVICES
June 26,  1986
Public Health  Advisor
ATSDR-EPA  Liaison
                                                      Public Health Service
                                                      Agency for Toxic Substances
                                                       and Disease Registry
                                                               Memorandum"
Coleman-Evans
Duval County,
               NPL Site;
               Florida
          Kris Teepen,  RPM
          EPA ERRB RAS
                                                        A7L..STA,
          As requested,  I  have reviewed  the  Draft Feasibility  Study,
          dated May  2,  1986,  for the referenced  site.  Given my  long
          term involvement with this site,  and  in the interest of  time
          for your program management purposes,  I have elected not to
          refer this  document to the ATSDR  for  a more indepth  review
          and comment.   I  trust you will  find  the following useful.

          Historical  EPA and  ATSDR review and  other site documents on
          file have  sufficiently identified  the  actual and potential
          public health  issues of concern for  this site, especially  the
          factors that  must be present in order  for a public health  threat
          to exist.   The 1984 EPA emergency  response action  (excavation
          of lagoon  sludges)  appears to  have helped reduce the predominant
          public health  threat posed by  the  site (i.e. potential  for
          percolation and  migration of contaminants to adjacent  private
          wells).

          The qualitative  risk assessment that  is described in the FS
          assesses on both technically and  epidemiologically sound bases,
          the potential  health concerns  existing at the site with  current
          (p. 1-1) and  future use (p. A-32)  exposure scenarios.   As  such,
          any, or a  combination of the three preferred remedial  alternatives
          (surface capping w/closure; solidification; incineration)  appear
          adequate to protect public health  and  to reduce the  potential for
          future exposures to occur that  may  increase the threat  of  exposure'
          to site contaminants at levels  that  would be of health  concern.
          However,  if  a  "No Action" alternative is selected,  it  appears
          prudent that a  monitoring program  of  private wells  at  the
          residences adjacent to the site  be considered.  Contingency plan:
          should also  be  developed if  such monitoring identifies that site
          contaminants at levels exceeding primary drinking water standard:
          are found at those wells in  use  for potable purposes.

          If I can  assist further with  the remaining remedial  phases of th
          site, ple_ase let me know.

         QL?
          Chuck
     L
       P ietrosewicr
          cc:  file
              ATSDR/Buynoski

-------
            REGION IV

COLEMAN EVANS WOOD PRESERVING CO.
     RESPONSIVENESS SUMMARY

       September 16,  1986

-------
                           RESPONSIVENESS SUMMARY
                 COLEMAN EVANS WOOD PRESERVING COMPANY SITE

                   U. S. ENVIRONMENTAL PROTECTION AGENCY
                                 REGION IV
This is the Responsiveness Summary for the Coleman Evans Wood Preserving
Company site in Whitehousa, Duval County, Florida.  Since the EPA received
written comments from only one source during the Feasibility Study public
cement period, this document consists of a summary of the ccrmunity
relations activities conducted at this site, a response to the one written
response received, the Feasibility Study fact sheet, and the transcripts
from the public meeting.

Following the Work Plan phase of the study from September 1984 to April
1985, the Remedial Investigation/Feasibility Study (RI/FS) for the site was
conducted from June 1985 to June 1986.  EPA received no telephone calls or
letters from the public concerning the site during that time.  A community
relations plan describing ccrmunity concerns and recommending community
relations activities was prepared in March 1985.  In accordance with the EPA
National Contingency Plan and suggestions made in the Community Relations
Plan, EPA established an information repository at the Whitehouse Elementary
School.  The repository contained public documents on the site, including
the RI/FS work plan anci the RI/FS report.

Once the draft FS was completed, a fact sheet (Attachment A) was prepared to
describe the remedial technologies that EPA was considering for the site,
the proposed clean-up goals, and the details of the public meeting and the
public comment period.  The fact sheet was mailed to individuals on the
Coleman Evans site mailing list and placed in the information repository.
Announcements for the public meeting and the public comment period were
placed in local papers.  EPA held the public meeting on August 7, 1936 and
the public comment period covered the period from August 7 to August 28,
1986.  Approximately 10 to 15 concerned citizens attended the public meeting.
The-'transcripts of the public meeting are presented in Attachment B.

The only written response received was from Ground Water Technology, Inc.
(GTI), a consultant for the Coleman Evans Wood Preserving Company.  The GTI
proposal is summarize"! 'rvlow, and the full document is presented in
Attachment C.
Garment Summary

GTI submitted a resper-- -3 the Feasibility Study.  The document which was
submitted was a "Res^-.--: to Feasibility Study" in which GTI outlined a
proposal to undertake ph?tO''biodegradation of the contaminated waters and
soils at the site and to recovery ar1 rer/rle the free-floating pentachloro-
phenol/diesel fuel mixture from, the sur':icial aquifer.  The proposal includes
site history, a work plan, a monitoring program, a cost evaluation, and a
photo/biodegradation process summary.

-------
Pfesponse

EPA reviewed the potential application of biodegradation for the Coleman
Evans site during the Feasibility Study and has reviewed the proposal
submitted by GTI.  This technology was eliminated during the early phases
of the Feasiblity Study because of technical problems associated with
biodegradation.  First, the feasibility of this process would have to be
determined during a long term pilot testing program, especially since there
have been limited previous studies which evaluate biodegradation of
pentachlorophenol.  Second, the volume of contaminated soils (estimated to
be 9,OOC cubic yards) would require a long period of tijne for complete
digestion of the contaminants, especially at the greater depths of
contamination identified during the Remedial Investigation.  Third, the
contaminants which are at depth may exist under anaerobic conditions.  In
order to evaluate biodegradation as a feasible option, a very wide range of
conditions would have to be implemented during the testing process.  Finally,
there is a potential for the creation of unacceptable by-products during
the biodegradation process; specifically dioxins.  Generation of dioxins
would further increase the risk to the public health and welfare, and to
the environment than is currently posed by pentachlorophenol, the main
contaminant of concern.
Although the financial aspects of biodegradation are attractive, the
potential for greater health and environmental risk and the long periods of
time required for testing and implementation are unacceptable to EPA.  For
these reasons. EPA eliminated biodegradation technologies during the Colenan
Evans Feasibility Study process.  EPA has determined that biodegradation is
not sufficiently proven to be an acceptable option for remediation of the
conditions at the Coleman Evans Wood Preserving Company site.

-------
      APPENDIX B

   Natural Resource
   Damage Assessment

     Coleman Evans
Wood Preserving Company

-------
              United States Department of the Interior
                           OFFICF OF THE SECRETARY
                            \\ASH:--JTON, D.C.  20240
                                                           JUN 2 I

  ER84/1318


  Mr. Gene Lucero, Director
  Office of Waste Programs Enforcement
  Environmental Protection Agency
  401 M Street, SW (Room S362N) WH 527
  Washington, D.C. 20460

  Dear Mr. Lucero:

  The  Department of the Interior has conducted a preliminary natural resources survey of
  the Coleman/Evans Wood Preserving Company at Whitehouse, Duval County, Florida, to
  determine  whether the  Secretary of the Interior's trust  responsibilities for natural
  resources have been affected.

  Our  survey indicates that there are no lands under the trusteeship of the DO1 near the
  Coleman/Evans site.  However, the Ortega  River system nearby can be inhabited by
  various trust resources,  including anadromous fish, migratory birds, and endangered and
  threatened species  of wildlife.  The manatee, an endangered marine  mammal, can be
  found in the Ortega River system.

  Site visits and review of various reports and  studies show that soils and surface waters
  have not been seriously contaminated very far off site.   There is no documentable
  evidence that  our  trust resources have been affected by  materials from this  site.
  However, we believe the site should be cleaned up quickly so that contaminants do not
  move off site.

  Accordingly, we would grant a release from  claims for damages to natural resources
  under our  trusteeship from the Coleman/Evans site, provided that  timely  remedial
  action consistent with the NCP is taken to clean up the site.

                                       Sincerely,
                                             Blanchard, -Director
                                       Office of Environmental Project Review
  CC:
/__Steve Klein/EPA

-------
      APPENDIX C

   State of Florida
 Letter of Concurrance
        for the
    Selected Remedy

     Coleman Evans
Wood Preserving Company

-------
                            STATE OF FLORIDA

           DEPARTMENT OF ENVIRONMENTAL REGULATION
TWIN TOWERS OFFICE BUILDING
2600 BLAIR STONE ROAD
TALLAHASSEE. FLORI DA 32301-8241
               BOB GRAHAM
           f;     GOVERNOR

         VICTORIA J. TSCHINKEL
                SECRETARY
                                  September 24, 1986
   Mr. Jack Ravan
   Regional Administrator
   United States Environmental
     Protection Agency
   Region IV
   345 Courtland Street, N.E.
   Atlanta, Georgia  30365

   Dear Jack:

   The Florida Department of Environmental Regulation agrees with
   the selection of Alternative #5 as described in the final
   feasibility study for the Coleman Evans Wood Preserving Superfund
   Site in Whitehouse, Duval County, Florida.

   This alternative includes the excavation and on-site incineration
   of soils and sediments, and the on-site treatment of contaminated
   ground water.  This alternative will effectively destroy contam-
   inated soils and sediments and treat ground water.

   The cost estimate for Alternative #5 ranges from $3.0 - $3.8 mil-
   lion for the use of a temporary on-site incineration facility,
   and groundwater treatment unit.  Due to the complete destruction
   of site specific contaminants by incineration, no post-remedial
   monitoring or operation and maintenance activity is required.
   The state will provide ten percent of the total cost, or about
   $300,000 - $380,000 from the State Water Quality Assurance Trust
   Fund.
   We look 'forward to participating with the U
   Protection Agency ccring implementation of
   at the Coleman Evans v.'ocd Preserving site.

                                  Sincerely,
 S. Environmental
remedial activities
                                  Victoria J. Tschinkel
                                  Secretary
   VJT/ps
                       Protecting Florida and Your Quality of. Life

-------
      APPENDIX D

 City of Jacksonville
 Letter of Concurrance
        for the
    Selected Remedy

     Coleman Evans
Wood Preserving Company

-------
DEPARTMENT OF HEALTH, WELFARE
& BIO-ENVIRONMENTAL SERVICES
Bio-Environmental Services Division
                                      May 21, 1986
                                                                         .
                                                                    ">r>v ,. J !'JC J  ; 1
                                                                    .""n
Ms. Kristina Teepen
Remedial Project Manager
U. S. Environmental Protection Agency - Region IV
3f5 Courtland Street
'Atlanta, GA  30365                                               _.	

    RE: Coleman Evans Wood Preserving Company                         •
        Draft Feasibility Study

Dear Ms. Teepen:

The  Bio-Environmental Services Division (BESD) has briefly reviewed  EPA's  Draft
Feasibility Study of Coleman Evans Wood Preserving Company, dated May 2, 1986.

The  BESD  would support the option of incineration, over the  other  options  for
remedial  actions,  as presented.  Incineration provides  the  following  benefits
which BESD feels are noteworthy.

    I.  Destruction of the organics

   II.  Usability of the site after contamination disposal
  III.  No requirement for continual monitoring

Incineration,  of  course,  as  an option needs to  be  better  defined  prior  to
implementation.  Specifically such items as retention times, in situ   monitoring,
etc. must be detailed.  Further, in order for incineration to be viable, just fron
a  permitting  standpoint, a great deal of public awareness and education  on  the
benefits--of the program shall be necessary.  Otherwise a permit may be delayed  as
a result of public concerns requesting Administrative Hearings.

If BESD can be of further assistance, please advise.

                                                Very truly yours,
                                                  obert Steven Pace, P.E.,
                                                 Bio-Environmental  Engineer
  cc:  Mr.  Ernest  E.  Frey,  P.E.  DER
      John K.  Flowe,  P.E.
      Khurshid K.  Mehta,  P.E.

  RSP/ns
        AREA CODE / 904 / 633-3318 / 515 WEST 6TH STREET / JACKSONVILLE, FLORIDA 32206-4397

-------
      APPENDIX E

PUBLIC HEALTH EVALUATION

       Submitted
          by
       CDC/ATSDR

     Coleman Evans
Wood Preserving Company

-------
-•""""'••                                                        Public Health Service
 •   "'..
(4-
  ••-.~Z£
        DEPARTMENT OF HEALTH & HUMAN SERVICES                      Agency for Toxic Substances
                                                             and Disease Registry

                                                     -;       Memorandum

 Date    June 26, 1986

                                                          _*.?-!?„/ R,5^,	
 From    Public Health Advisor                          i ~ vi.^!^.'.^-';'---'-
        ATSDR-EPA Liaison                              :'  f
                                                     •  jr<  J!j?:2fi  >S3
 Subject  Coleman-Evans NPL Site;                        !!  j_ 	  	
        Duval County, Florida                          j;  f!" "01 .-•)• i  ; i i?
                                                       Ll  ^ !—' >— '«•— ^ *-'
                                                             :•>".•. - ;;;•:• i ;•:; ;v
 To     Kris Teepen, RPM                                      A7-.'..vr.*. JA.
  .,,•    EPA ERRB RAS
                                                     i
        As requested, I have reviewed the Draft  Feasibility Study,
        dated Hay 2, 1986,  for the referenced  site.  Given  my long
        term involvement with this site, and in  the  interest  of time
        for your program management purposes,  I  have elected  not  to
        refer this document to the ATSDR for a more  indepth review
        and comment.  I trust you will  find the  following useful.

        Historical EPA and ATSDR review and other  site documents  on
        file have sufficiently identified the  actual and  potential
        public health issues of concern for this  site, especially the
        factors that must be present in order  for  a  public  health threat
        to exist.  The 1984 EPA emergency response action (excavation
        of lagoon sludges)  appears to have helped  reduce  the  predominant
        public health threat posed by the site  (i.e. potential  for
        percolation and migration of contaminants  to adjacent private
        wells) .

        The qualitative risk assessment that is  described in  the  FS
        assesses on both technically and epidemiologically  sound  bases,
        the potential health concerns existing at  the  site  with current
        (p. 1-1) and future use (p. A-32) exposure scenarios.   As such,
        any, or a combination of the three preferred remedial alternatives
        (surface capping w/closure,- solidification;  incineration) appear
        adequate to protect public health and  to  reduce  the potential for
      .  future exposures to occur that  may increase  the  threat  of expos-re
        to site contaminants at levels  that would  be of  health  concer-  .

        However, if a "No Action" alternative  is  selected,  it appears
        prudent that a monitoring program of private wells  at the
        residences adjacent to the site be considered.   Contingency, plans
        should also be developed if such monitoring  identifies  that site
        contaminants at levels exceeding primary  drinking water standards
        are found at those wells in use for potable  purposes.

        If I can assist further with the remaining remedial phases  of  this
        site, please let me know.
                         *
        Chuck Pietrosewicr

        cc:  f ile
            ATSDR/Buynosk i

-------