United States .
           Environmental Protection
           Agency
Office of
Emergency and
Remedial Response
EPA/ROD/R09-89/039
September 1989
4>EPA  Superfund
          Record of Decision:
          Firestone Tire (Salinas Plant), GA

-------
50272-101
 REPORT DOCUMENTATION
        PAGE
1. REPORT NO.  .
   .  EPA/ROD/R09-89/039
                                                                    3. Recipient's AcceMlon No.
 4. Title and Subtitle
   SUPERFUND  RECORD OF DECISION
   Firestone  Tire (Salinas  Plant), CA
   First Remedial Action -  Final
                                           5. Report Date
                                              9/13/89
   Authors)
                                           8. Performing Organization RepL No.
 9. Performing Organization Name and Address
                                                                    10. Project/Task/Work Unit No.
                                                                    11. Contract(C) or Grant(G) No.

                                                                    (C)

                                                                    (G)
 12. Sponsoring Organization Name and Address
   U.S. Environmental Protection Agency
   401 M Street,  S.W.           ,
   Washington,  D.C.  20460
                                           13. Type of Report & Period Covered

                                               800/000
                                                                    14.
 15. Supplementary Note*
 16. Abstract (Limit: 200 words)
  The 256-acre Firestone Tire  (Salinas Plant)  site is in an agricultural area  in Salinas,
  California.  The facility was  operated as a  tire manufacturing plant from  1963 to 1980,
  in  which a variety of chemicals and chemical formulations were used including solvents
  and surfactants.  In 1983, as  part of the requirements for  the closure of  a
  RCRA-regulated storage area  at the facility,  Firestone conducted an environmental
  Investigation  and determined that some chemicals had been released to the  soil and
  round water.   Sampling indicated that a plume of VOC-contamination extends  about 2 1/2
  ailes northwest of the former  facility.  Consequently, onsite  and offsite  ground water
  pumping and treatment was initiated to further reduce chemical migration.  Furthermore,
  evaluation of  potential sources of contamination resulted in cleaning and  removing
  storage tanks  and above-ground facilities, as well as excavating 5,300 cubic yards of
  inorganic-'and organic-contaminated soil for final disposition offsite.  This final
  remedy provides for additional cleanup of ground water under the site and  as much as 2
  1/2 miles  from the site.  Soil analytical data indicated that  the residual risk from
  soil contamination after remedial measures had been implemented warranted  no further
  soil remediation.   The primary contaminants  of concern affecting the ground  water are
  VOCs including 1,1-DCA, 1,1-DCE,  1,1,1-TCA,  TCE, PCE, benzene,  toluene, and  xylenes.
  (Continued on  next page)
 17. Document Analysis a. Descriptors
    Record of  Decision - Firestone Tire  (Salinas  Plant), CA
    First Remedial Action - Final                                              '
    Contaminated  Media: gw
    Key Contaminants:  VOCs  (1,1-DCA,  1,1-DCE, :i,l,l-TCA, TCE,  PCE,  benzene,  toluene,
    xylenes)
   b. fdentifiers/Open-Ended Terms                  .-.'•'•
   c. COSATI Field/Group
4. Availability Statement
19. Security Class (This Report) '
None
20. Security Class (This Page)
None
21. No. of Pages
327
22. Price
(See ANSI-Z39.18)
                                      See Instructions on Revone
                                                     OPTIONAL FORM 272 (4-77)
                                                     (Formerly NTIS-35)
                                                     Department of Commerce

-------
                   DO NOT PRINT THESE INSTRUCTIONS AS A PAGE IN A REPORT


                                                     INSTRUCTIONS
 Optional Form 272, Report Documentation Page is based on Guidelines for Format and Production of Scientific and Technical Reports,
 ANSI Z39.18-1974 available from American National Standards Institute, 1430 Broadway, New York, New York 10018. Each separately
 bound report—for example, each volume bi a muhlvolume set—shall have its unique Report Documentation Page.

  1.   Report Number. Each Individually bound report shall carry a unique alphanumeric designation assigned by the performing orga-
      nization or provided by the sponsoring organization In accordance with American National Standard ANSI Z39.23-1974, Technical
      Report Number (STRN). For registration of report code, contact NTIS Report Number Clearinghouse, Springfield, VA 22161. Use
      uppercase letters, Arabic numerals, slashes, and hyphens only, as In the following examples: FASEB/NS-75/87 and FAA/
      RD-75/09.
  2.   Leave blank.

...3..  Recipients Accession Number^ Jaaarved for use by each report recipient    		_
  4.  TWe and Subtitle. TWe should indicate clearly and briefly the subject coverage of the report, subordinate subtitle to the main
     tine. When a report to prepared hi more than one volume, repeat the primary title, add volume number and Include subtitle for
     the specific volume.      	__..

  5.  Report Date. Each report shaD carry a date indicating at least month and year. Indicate the basis on which it was selected (e.g.,
     date of issue, date of approval, date of preparation, date published).

  6.  Sponsoring Agency Code. Leave blank.

  7.  Authors). Give name(s) In conventional order (e.g^, John R. Doe, or J. Robert Doe). List author's affiliation if it differs from
     the performing organization.

  8.  Performing organization Report Number. Insert if performing organizaton wishes to assign this number.

  9.  Performing Organization Name and Uaffing Address. Give name, street, dty, state, and ZIP code. Ust no more than two levels of
     an organizational hlerachy. Display the name of the organization exactly as it should appear in Government indexes such as
     Government Reports Announcements ft Index (GRA 41).

 10.  Project/Task/Work Unit Number.  Use the project, task and work unit numbers under which the report was prepared.

 11.  Contract/Grant Number. Insert contract or grant number under which report was prepared.

 12.  Sponsoring Agency Name and Mailing Address. Include ZIP code. Cite main sponsors.

 13.  Type of Report and Period Covered. State Interim, final, etc., and, H applicable, Inclusive dates.

 14.  Performing Organization Code. Leave blank.

 15.  Supplementary Notes.  Enter Information not Included elsewhere but useful, such as: Prepared In cooperation with... Translation
     of... Presented at conference of... To be published in...  When a report is revised, Include a statement whether the new
     report supersedes or. supplements the older report.
                                                                     V
 16.  Abstract Include a brief (200 words or less) factual summary of the most significant Information contained In the report If the
     report contains a significant bibliography or literature survey, mention It here.

 17.  Document Analysis, (a). Descriptors. Select from the Thesaurus of Engineering and Scientific Terms the proper authorized terms
     that identify the major concept of the research and are sufficiently specific and precise to be used as Index entries for cataloging.

     (b). Identifiers and Open-Ended Terms. Use Identifiers for protect names, code names, equipment designators, etc.  Use open-
     ended terms written In descriptor form for those subjects for which no descriptor exists.

      (c). COSATI Field/Group.  Field and Group assignments aro to be taken form the 1964 COSAT1 Subject Category Ust Since the
      majority of documents aro rnumdiscipllnary in nature, the primary Field/Group assignments) will be the specific discipline.
      area of human endeavor, or type of physical object The appUcatton(s) will be cross-referenced with secondary Reid/Group
      assignments that wOl follow the primary posting(s).

 18.  Distribution Statement Denote public reteasabiDty, for example "Release unlimited", or limitation for reasons other than
     security. Cite any availability to the public, with address, order number and price, If known.

 19. & 20.  Security Classification. Enter US. Security Classification in accordance with U. S. Security Regulations (i.e., UNCLASSIFIED).

 21.  Number of pages. Insert the total number of pages, Including Introductory pages, but excluding distribution list If sny.

 22.  Price. Enter price in paper copy (PC) and/or microfiche (MF) H known.

    GPO:   19830-381-526(8393)                                                                      OPTIONAL FORM 272 BACK
                                                                                                   (4-77)

-------
EPA/ROD/R09-89/039
Firestone Tire (Salinas Plant), CA

16.  Abstract (Continued)

 le selected remedial action for the site includes pumping and treatment of ground water
at the existing treatment facility using carbon adsorption and air stripping, with
offsite discharging of treated ground water to surface water; ground water monitoring to
ensure that the ground water plume is declining; crop testing to ensure that there is no
plant uptake of the contaminants; and developing a contingency plan for water in the deep
aquifer in case of contamination.  The estimated present worth cost for this remedial
action is $1,742,000, which includes an estimated O&M cost of $1,517,000 for 3 1/2 years.

-------
                              RECORD OF DECISION
                                   DECLARATION                     »

                     Firestone Tire and Rubber Company, Inc. Site
                                 Salinas, California

Statement of Basis and Purpose

       The Firestone Tire and Rubber Company Site ("Firestone Site"), located in Salinas,
California,  was added to the National Priorities List in 1987, and is subject to the require-
ments put forth in the Comprehensive Environmental Response, Compensation and
Liability Act. The California Department of  Health Services ("DHS") approved the
remedial action for the Firestone Site in accordance with California Health and Safety
Code at 25300 et. sea.. CERCLA, the National Contingency Plan, and applicable or relevant
and appropriate requirements for the site. This document serves as  EPA's selection of
remedy which fully supports the decision made by DHS. The DHS is serving as the lead
agency for Superfund activities at the Firestone Salinas Site.

       EPA's selection of the remedy chosen by DHS is based upon the Remedial Action
Order, Remedial Investigation, Risk Assessment, Feasibility Study, the Remedial  Action
Plan ("RAP"), the Response Summary, and the Administrative Record for this site. The
administrative record index is attached to this document, and the administrative  record
file is closed with the signing of this document.

Description of Remedial Action

       Firestone Tire and Rubber Company has been performing an RI/FS at  the site since
1986. A RCRA closure was completed in 1984 which addressed soil  contamination at the
site before the facility closed down. Firestone has been pumping and treating groundwater
at the facility since 1984 at an on-site groundwater treatment plant.  Since that time,
groundwater contaminant concentrations have significantly declined.

      The final remedy provides for cleanup and cleanup requirements for groundwater
under the site and extending to a distance of over 2 miles from the site.  The major com-
ponents of the final selected remedy include:

0     Pumping of groundwater from the shallow 60-80 foot hydrogeological zone for
      treatment;

0     Pumping of groundwater from the intermediate 120-180 foot  hydrogeological zone
      for treatment;

0     Treatment of extracted water by carbon adsorption and air stripping under a permit
      by the Monterey Air District;

0     Discharge of treated water to the Salinas River under an NPDES permit issued by
      the Regional Water Quality Control Board, San Louis Obispo  Region;

0     Regular monitoring  to ensure that the size of the groundwater plume is declining
      and to allow for adjustments to the system;

°     Crop  testing to ensure there is no uptake of contaminants by  plants;

-------
t"J. J INTERNATIONAL
I M m TECHNOLOGY                                         Prniort Mn 1Qr,Ofi7
CJLJ CORPORATION                                         Project NO. 13 00 6 7
               	-  	.	     August 1989
            TT:                                               FfRai
Feasibility  Study/
Remedial Action  Plan
Former Firestone Facility
Salinas, California
The Firestone Tire &  Rubber Company
Akron. Ohio
Volume I  - Text
           RESPONSIVE TO THE NEEDS OF ENVIRONMENTAL MANAGEMENT

-------
                                      -  2  -
      A contingency plan for currently uncontaminated water in  the deep aquifer which
      becomes contaminated and is found not to be effectively remedied.
Declaration

       EPA, under CERCLA, has selected this remedy for the Firestone Site. The remedy
is protective-of human health and the environment, attains Federal and State requirements
that are applicable or relevant and appropriate to the remedial action, and is cost- and
time-effective. This remedy satisfies Federal statutory preferences for remedies that
reduce toxicity* mobility, or volume of contaminants as a principal element It also utilizes
permanent solutions to the maximum extent practicable. The remedy also addresses and
provides for the 5-year review provision at CERCLA Section 121(c).  If this selected
remedial action does not meet the goals and cleanup objectives identified in the remedy, or
is not sufficiently protective of human health and the environment, then EPA may, under
the authorities of CERCLA, require additional response action from Firestone.
Date                      John Wise
                          Deputy Regional Administrator

-------
             Concurrences for Firestone Salinas  Superfund  Site ROD
I  concur with the remedy selected by the State of California and recommend that the Deputy Regional
Administrator sign the  Concurrence Record of Decision.
                               Hazardous Waste Management Division
 j yi
 Jeffrey A. Dhont
 Remedial Project Manager
 Enforcement Programs Section
                      / V
Alexis Strauss. Chief
Superfund Enforcement  Branch
                                                                Jeff Ze|jkson, Director
 Jeff Iftosenbloom, Chief
 Enforcement Programs Section    Assistant Director for Superfund
   Office of Regional Counsel
Steven Moores
Assistant Regional Counsel
     Cooper
 Acting  Regional Counsel
                                                   David Howekamp, Director  .
                                                      Water Management Division
                                                  Harry Seraydarian,  Director

-------
FEASIBILITY STUDY/REMEDIAL ACTION PLAN
      FORMER  FIRESTONE  FACILITY
         SALINAS,  CALIFORNIA

          Project No. 190067
             PREPARED FOR

 The  Firestone Tire  & Rubber  Company
        1200 Firestone Parkway
          Akron, Ohio  44301
              PREPARED  BY

            IT Corporation
              August  1989

            Final Revision

-------
                                                                Date:  8/22/89
                                                                Final Revision^
                              TABLE OF CONTENTS

                                                                       PAGE

LIST OF TABLES	   vi
LIST OF FIGURES.	  v11
EXECUTIVE SUMMARY	  ES-1
1.0  INTRODUCTION	  1-1
     1.1  PURPOSE OF REPORT	  1-1
     1.2  REGULATORY BASIS	  1-1
     1.3  ORGANIZATION OF REPORT	  1-3
     1.4  BACKGROUND INFORMATION	...	 . 1-4
          1.4.1  SUe Description	  1-4
          1.4.2  Site History	:	  1-5
          1.4.3  Environmental Fate of Chemicals at the Site	  1-6
          1.4.4  Residual Risk from Soil  Contaminants	  1-8
                 1.4.4.1  Introduction 	  1-8
                 1.4.4.2  Description of Soil Removal Activities
                          and Analytical  Data	  1-9
                 1.4.4.3  Residual Soil  Levels and Their Hazards	  1-14
     1.5  NONBINOING PRELIMINARY ALLOCATION OF RESPONSIBILITY	  1-19
2.0  IDENTIFYING AND SCREENING OF TECHNOLOGIES...	  2-1
     2.1  INTRODUCTION	  2-1
     2.2  REMEDIAL ACTION OBJECTIVES	  2-1
          2.2.1  Contaminants of Interest	  2-1
          2.2.2  Allowable Concentrations Based on Risk Assessment ...  2-2
          2.2.3  Review of Applicable or Relevant and Appropriate
                 Requirements (ARARs) and To-Be-Considered Materials
                 (TBCs)	  2-3
          2.2.4  Summary of Allowable Concentrations	  2-6
          2.2.5  Development of Remedial  Action Objectives	  2-6
     2.3  GENERAL RESPONSE ACTIONS	  2-7
     2.4  TECHNOLOGY TYPES AND PROCESS OPTIONS	  2-9
          2.4.1  Physical Treatment Methods	  2-9

-------
                                                               Date:  8/22/89
                                                               Final  Revision
                              TABLE OF CONTENTS
                                 (Continued)

                                                                       PAGE
                2.4.1.1  Coagulation/Flocculation ....................   2-9
                2.4.1.2   Oil-Water Separation .......................   2-10
                2.4.1.3   Flotation .................. ................   2-10
                2.4.1.4   Media Filtration ...........................   2-11
                2.4.1.5   Absorption/Adsorption ......................   2-12
                2.4.1.6   Gas-Phase Stripping ........................   2-16
                2.4.1.7   Reverse  Osmosis ............................   2-18
                2.4.1.8   Dialysis ............. . .................... .   2-19
                2.4.1.9   Electrodialysis ................ ... ..........   2-20
                2.4.1.10  Ultrafiltration ............................   2-20
                2.4.1.11  Freeze Processing ..........................   2-21
                2.4.1.12  Distillation.. .............................   2-24
                2.4.1.13  Extraction .................................   2-24
                2.4.1.14  Mechanical  Separation/Treatment ............   2-28
                2.4.1.15  Magnetic Separation ........................   2-33
                2.4.1.16  Evaporation/Crystal! ization/Drying .........   2-35
          2.4.2  Chemical Treatment Methods ...........................   2-37
                2.4.2.1   Neutralization .............................   2-37
                2.4.2.2   Precipitation. ...... .......................   2-38
                2.4.2.3   Ion Exchange ...............................   2-39
                2.4.2.4   Oxidation ..................................   2-40
                2.4.2.5   Reduction ..... . ............................   2-45
                2.4.2.6   Photolysis .................................   2-48
                2.4.2.7   Irradiation ................................   2-49
                2.4.2.8   Stabilization ..............................   2-50
          2.4.3  Biological  Treatment.. ..... . ---- ........ . ............   2-52
                2.4.3.1   Aerobic  Degradation ........................   2-52
                2.4.3.2   Anaerobic Digestion ........................   2-56
                2.4.3.3   Enzymatic Conversion ................ .......   2-57
                2.4.3.4    In Situ  Biological Remediation .............   2-53
FIR:0067-R3toc

-------
                                                                Date:  8/22/89
                                                                Final Revision
                              TABLE OF COKTEMTS
                                  (Continued)

                                                                        PAGE
                 2.4.3.5   Controlled Bacterial Applications	  2-59
                 2.4.3,6.   Composting	  2-62
                 2.4.3.7   Aquaculture	  2-63
          2.4.4  Thermal Treatment.....	...	  2-64
                 2.4.4.1   Thermal Oxidation (Incineration)	  2-64
                 2.4.4.2   Thermal Degradation (Calcination)	  2-65
                 2.4.4.3   Vitrification	  2-65
                 2.4.4.4   Plasma Pyrblysis	  2-66
                 2.4.4.5   Nuclear Destruction...	  2-66
          2.4.5  Dispersed Treatment	  2-67
          2.4.6  Centralized Treatment	  2-68
3.0  DEVELOPING REMEDIATION ALTERNATIVES	  3-1
     3.1  RELEVANT SITE CHARACTERISTICS	  3-1
     3.2  EXTRACTION ALTERNATIVES	  3-4
     3.3  TREATMENT ALTERNATIVES	  3-5
          3.3.1  Activated Carbon Treatment	  3-6
          3.3.2  Air Stripping		  3-6
          3.3.3  Natural Degradation/Dilution.	  3-7
          3.3.4  Combined/Additional  Strategies		  3-3
          3.3.5  Agricultural Spraying	  3-8
     3.4  DETAILED ANALYSIS OF DISPOSAL  ALTERNATIVES	  3-9
          3.4.1  Alternative S - Stream  Disposal	  3-9
          3.4.2  Alternative T - Injection	  3-10
          3.4.3  Alternative U - Holding Ponds, Lagoons, or Basins....  3-11
          3.4.4  Summary of Discharge Alternatives	  3-12
     3.5  SITE-SPECIFIC REMEDIAL ACTION  ALTERNATIVES	  3-14
          3.5.1  Approach	  3-14
          3.5.2  Developed Alternatives	  3-17
FIR:0067-R8toc                         11J

-------
                                                                Date:  8/22/89
                                                                Final Revision
                              TABLE OF CONTENTS
                                  (Continued)

                                                                        PAGE
4.0  DETAILED ANALYSIS OF REMEDIATION ALTERNATIVES	  4-1
     4.1  DETAILED ALTERNATIVE ANALYSES CRITERIA	  4-1
     4.2  ALTERNATIVE DESCRIPTION	,	  4-8
          4.2.1  Alternative A	,	  4-8
          4.2.2  Alternative 8	  4-10
          4.2.3  Alternative C	  4-11
          4.2.4  Alternative D	  4-13
                 4.2.4.1  Zone of Capture, Shallow Aquifer	  4-14
                 4.2.4.2  Zone of Capture, Intermediate Aquifer	...  4-15
                 4.2.4.3  Computer Simulations.	  4-17
                 4.2.4.4  Summary of Costs	  4-19
          4.2.5  Alternative E	  4-19
     4.3  DETAILED ANALYSIS	  4-21
          4.3.1  Short-Term Effectiveness	  4-22
          4.3.2  Long-Term Effectiveness and Permanence	  4-24
          4.3.3  Reduction of Toxicity, Mobility, and-Volume	  4-25
          4.3.4  Implementibility	  4-26
                 4.3.4.1   Technical Feasibility	  4-26
                 4.3.4.2   Administrative Feasibility	  4-23
                 4.3.4.3   Availability of Services and Materials	  4-29
          4.3.5  Cost	  4-30
          4.3.6  Compliance with ARARs	  4-32"
          4.3.7  Overall Protection of Human Health and
                 the Environment	  4-33
          4.3.8  State Acceptance	  4-34
          4.3.9  Community Acceptance	  4-34
     4.4  SUMMARY OF DETAILED ANALYSES	  4-34
 5.0  RECOMMENDED REMEDIAL ACTION	  5-1
 6.0  RESPONSIVENESS SUMMARY	  6-1
FIR:0067-R8toc                         iv

-------
                                                                Date:  8/22/89
                                                                Flna.l Revision
                              TABLE OF  CONTENTS
                                  (Continued)
REFERENCES
TABLES
FIGURES
APPENDIX A - REMEDIAL ACTION ORDER AND OPERATING PERMITS
APPENDIX B - PROJECT CHRONOLOGY
APPENDIX C - DATA BASE FOR CHEMICAL CONCENTRATIONS IN GROUND WATER
APPENDIX D - BASIC CONCEPTS OF ADSORPTION ON ACTIVATED CARBON
APPENDIX E - SUMMARY OF CARBON ADSORPTION CAPACITIES
APPENDIX F - AQUIFER CHARACTERISTICS
APPENDIX G - PHYSICAL AND CHEMICAL CHARACTERISTICS OF CHEMICALS
APPENDIX H - LIST OF ABBREVIATIONS AND ACRONYMS
APPENDIX I - GEOMETRIC MEAN CONCENTRATION CALCULATION METHODOLOGY
APPENDIX J - CONTAMINANT TRANSPORT SIMULATION
FIR:0067-R8toc

-------
                                                                Date:  8/22/89
                                                                Final Revision
                                LIST OF TABLES

TABLE NO.                            TITLE
    2-1            Potential Federal Applicable or Relevant and Appropriate
                   Requirements (ARARs)
    2-2            Potential State and Local Applicable or Relevant and
                   Appropriate Requirements (ARARs)
    2-3            Potential Other Federal Criteria, Advisories, and Guidance
                   to be Considered (TBC)
    2-4            Potential Other State and Local Criteria, Advisories, and
                   Guidance to be Considered (TBC)
    2-5            Organic Constituents - Water Quality Goals-Human Health and
                   Welfare
    3-1            Flowrates for Extraction Alternatives, Intermediate
                   Aquifer, Former Firestone Facility
    4-1            Examination of Alternatives Versus Potentially Applicable
                   or Relevant and Appropriate Requirements (ARARs)
    4-2            Summary of Detailed Analysis of Remediation Alternatives
                                                                  *
    4-3            Cost Comparison of Assembled Alternatives
    4-4            Cost Summary - Alternative A
    4-5            Cost Summary - Alternative B
    4-6            Cost Summary - Alternative C
    4-7            Cost Summary - Alternative 0
    4-8            Cost Summary - Alternative E
FIR:0067-R8toc                         vi

-------
                                                                Date:  8/22/89
                                                                Final Revision

                               LIST OF FIGURES

FIGURE NO.                             TITLE
    1-1            Vicinity Map
    1-2            Site Plan
    1^3            Well Location Map~1n Shallow Aquifer
    1-4            Well Location Map in Intermediate Zone
    1-5            Well Location Map for Monitoring Wells 1n Deep Aquifer
    1-6            Well Location Map for Agricultural, Domestic, Industrial
                   and Municipal  Wells in Deep Aquifer
    1-7            Area 1 - Fuel  Oil  Storage Area,  Soil Sample Locations and
                   Chemical Concentrations
    1-8            Area 2 - Hazardous Waste Storage Area, Soil Sample
                   Locations and Chemical Concentrations
    1-9            Area 3 - Raw Materials Storage Area, Soil Sample Locations
                   and Chemical Concentrations
    1-10           Area 4 - Three Sludge Drying Beds, Soil Sample Locations
                   and Chemical Concentrations
    1-11           Area 5 - Holding Ponds, Soil  Sample Locations and Chemical
                   Concentrations
    1-12           Area 6 - Seepage Ponds, Soil  Sample Locations and Chemical
                   Concentrations
    1-13           Area 7 - Transformer Yard and Waste Oil Tanks, Soil Sample
                   Locations and Chemical Concentrations
    1-14           Area 8 - Evaporation Beds, Soil  Sample Locations and
                   Chemical Concentrations
    2-1            Technology Screening Summary - Physical Treatment Methods
    2-2            Technology Screening Summary - Chemical, Biological, and
                   Thermal Treatment Methods
    2-3            Technology Screening Summary - Technology Process Options
FIR:0067-R8toc                         vii

-------
                                                                Date:  8/22/89
                                                                Final Revision

                               LIST OF FIGURES
                                 (Continued)

FIGURE NO.                             TITLE
    3-1            Potentiometric Surface, Shallow Aquifer, March 1989
    3-2            Generalized Geologic Cross Section Along Contaminant
                   Migration Pathways
    3-3            Approximate Plume Area, Shallow Aquifer, 1,1-OCE Maximum
                   Concentrations,  4-88 to 3-89
    3-4            Approximate Plume Area, Shallow Aquifer, 1,1,1-TCA Maximum
                   Concentrations,  4-88 to 3-89
    3-5            Approximate Plume Area, Intermediate Aquifer, 1,1-OCE
                   Maximum Concentrations, 4-88 to 3-89
    3-6            Approximate Plume Area, Intermediate Aquifer, 1,1-TCA
                   Maximum Concentrations, 4-88 to 3-89
    3-7            Approximate Plume Area, Deep Aquifer, 1,1-OCE Maximum
                   Concentrations,  4-89 to 3-89
    3-8   .         Approximate Plume Area, Deep Aquifer, 1,1-TCA Maximum
                   Concentrations,  4-88 to 3-89
    3-9            Extraction Well  Locations for Pumping Alternatives
    3-9a           Extraction Well  Locations, Pumping Alternative 1
    3-9b           Extraction Well  Locations, Pumping Alternative 2
    3-9c           Extraction Well  Locations, Pumping Alternative 3
    3-9d           Extraction Well  Locations, Pumping Alternative 4
    3-9e           Extraction Well  Locations, Pumping Alternative 5
    3-9f           Extraction Well  Locations, Pumping Alternative 6
    3-10           Extraction Well  Locations, Alternative B
    3-11           Extraction Well  Locations, Alternative C
    3-12           Extraction Well  Locations, Alternative 0
    3-13           Extraction Well  Locations, Alternative E
FIR:0067-R8toc                         viii

-------
                                                                Date:   8/22/89
                                                                Final  Revision
                               LIST OF FIGURES
                                 (Continued)
    3-14           Schematic  Flow Diagram, Ground-Water  Treatment
    4-1            Model  Areas
    4-1A           Alternative A, Plume Migration, Shallow Aquifer
    4-IB-           Alternative A, Plume Migration, Intermediate  Aquifer
    4-2A           Alternative B, Plume Migration, Shallow Aquifer
    4-28           Alternative B, Plume Migration, Intermediate  Aquifer
    4-3A           Alternative C, Plume Migration, Shallow Aquifer
    4-3B           Alternative C, Plume Migration, Intermediate  Aquifer
    4-4            Capture  Zone, Shallow Aquifer
    4-5A           Equipotential Lines, 650-GPM Capture  Zone,  Intermediate
                   Aquifer
    4-5B           Flowlines, 650-GPM  Capture  Zone,  Intermediate Aquifer
    4-5C           Flowlines, 400-GPM  Capture  Zone,  Intermediate Aquifer
    4-6A           Alternative 0, Plume Migration, Shallow Aquifer
    4-6B           Alternative D, Plume Migration, Intermediate  Aquifer
    4-6C           Alternative D',  Plume Migration,  Intermediate Aquifer
    4-6D           Alternative D, Plume Migration, 400 gpm,  Intermediate
                   Aquifer
    4-7A           Alternative E, Plume Migration, Shallow Aquifer
    4-7B           Alternative E, Plume Migration, Intermediate  Aquifer
    4-8            Harden 12  Ag Well 1,1-DCE Concentrations
FIR:Q067-R8toc                          ix

-------
                                                                Data:  8/22/89
                                                                Final Revision
                              EXECUTIVE SUKWARY

Firestone Tire & Rubber Company operated  a  tire-manufacturing  plant from 1963
to  1980  at  340  El Camino  Real  South,  about 6  miles southeast  of downtown
Salinas, California.  During operation, the  plant used a variety of chemicals
and  chemical  formulations  to  make  tires.   Firestone  began  environmental
Investigations  in  March  1983  as  part of  the requirements  for  closing  the
Resource Conservation  and  Recovery Act (RCRA) storage area at  the facility.
Firestone subsequently determined that some chemicals had been released to the
soil and ground water.  The nature and extent of  these chemicals in the ground
water  were   thoroughly  assessed  and   were  documented  in  'the  Remedial
Investigation report  issued to  the Department of  Health  Services  in December
1988.

As reported  in the  Remedial Investigation,  two groups of chemicals were found
in the ground  water both on and off  site:  chlorinated aliphatic hydrocarbons
and  volatile aromatic hydrocarbons.   The chlorinated  compounds  included  the
following:
         1,1-Dichloroethane (1,1-OCA)
         1,2-Dichloroethane (1,2-OCA)
         1,1-Oichloroethene (1,1-OCE)
         1,1,1-Trichloroethane (1,1,1-TCA)
         Trichloroethene (TCE)
         Tetrachloroethene (PCE).
The aromatics included the following compounds:
      •  Benzene
      •  Toluene
      •  Ethyl benzene
      •  Xylene (3  isomers).

In  general,  the chemicals'most commonly found  in  the  ground water  in  the
vicinity of  the facility are  1,1-DCA;  1,1-OCE; and 1,1,1-TCA.   Concentrations
are  found  in the  micrograms  per liter (parts per billion) range  in  on-  and
off-site ground  water.  The seven other chemicals are  found  either in lower
concentrations or  not at all in most wells.
        t
FIR:0067-R8ES                           ES-1

-------
                                                                Date:  8/22/89
                                                                Final Revision
The  ground-water  aquifer  system  at  the  facility  is  comprised  of  three
interconnected zones that are designated shallow, intermediate, and deep.  The
shallow  aquifer  extends  from about  30  feet below the  surface to a  depth of
about 90 feet.  The intermediate zone is generally between depths of about 100
and  140  feet  below the  surface.   The deep aquifer  system locally  has  up to
four zones at approximately 200-,,300-,  400-,  and 500-foot depths.

Analyses of  samples from monitoring, agricultural, domestic,  industrial, and
municipal water  wells indicate that the chemical plume extends  about  2-1/2
miles northwest  of  the  former Firestone facility.  The plume  of chemicals in
the ground water can be described as follows,  starting at the facility:
      •  A narrow ellipse 3,000 feet long and  1,000  feet wide, in the shallow
         aquifer, flowing almost due west
      •  A second,  narrow ellipse 4,000  feet  long  and 1,000 feet wide, in the
         intermediate zone, flowing northwest
      •  A third ellipse 7,000  feet long  and  1,500 feet  wide,  in  the  deep
         aquifer flowing northwest.

The concentrations of chemicals in the ground  water have been decreasing since
monitoring began in  1983.    The range  of  concentrations  in micrograms  per
liter, ug/i,  from April  1988 to March 1989 was as follows:
     Zone
     first ellipse
     second ellipse
     third ellipse

Interim  remedial  action  to  clean the ground water began as soon as Firestone
was  aware of  the problem.   Initially, extraction wells were  drilled into the
shallow  aquifer  on  site,  in a line  just northwest of the  plant  buildings.  A
ground-water treatment system was  installed after  Firestone received approval
from  State  and  county  regulatory  agencies.   Subsequently, extraction  wells
have  been  drilled  off-site  to  the northwest,  again   penetrating   into  the
shallow aquifer.
FIR:0067-R8ES                           ES-2
Depth (feet)
<90
100 to 140
>200
1,1-OCE
2 to 90
NO to 52
NO to 23
1,1-DCA
2 to 36
NO to 8
NO to 11
1,1,1-TCA
1 to 38
NO to 27
NO to 16

-------
                                                                Date:  8/22/89
                                                                Final Revision
IT prepared  a preliminary risk  assessment relative  to ground-water  use for
this project  in October  1988.   The risk values presented  in  that report were
updated  in  the Remedial  Investigation  (RI)  report  issued in  December 1988.
The risks have continued to decrease as the concentrations of chemicals 1n the
ground water are reduced by the treatment system.

Four ground-water  ingestion  scenarios were analyzed  in the December  1988 RI
report to evaluate potential  risk to humans:
      °  Current use of affected ground water (an existing well)
      •  Hypothetical well in shallow aquifer (90 feet)
      •  Hypothetical well in intermediate zone (120 feet)
      •  Hypothetical well in deep aquifer (220 feet).

In each  scenario,  risks  from  carcinogens  and noncarcinogens  were calculated
separately.  For carcinogens, the nonsignificant risk level was set at 1 xlO~°
(one in  one million)  additional  risk  due to  lifetime consumption of contamin-
ated ground  water from  the well.    For noncarcinogens,  a  health  index was
calculated, comparing  the allowable  drinking  water standard  with the actual
concentration  in the affected ground water.   The comparison  is  the ratio of-
actual  concentration  to  the  allowable concentration.   An  index value of less
than one means that the exposure level is less than the allowable human intake
level.   The  following  table  summarizes the  health  risk assessment  results
presented in the December 1988 RI report:

     HELL SCENARIO                 CARCINOGEN RISK          HEALTH INDEX
  Existing Shallow Aquifer         less than 1 x 10'6           0.02
  Hypothetical Shallow Aquifer     1.6 x 10"b                   1.4
  Hypothetical Intermediate Zone   less than 1 x 10~£           0.87
  Hypothetical Deep Aquifer        less than 1 x 10~°           0.2.

Based on this risk  assessment,  the  only scenario that  shows  risks  above the
acceptable levels is use of a hypothetical  domestic well placed in the maximum
contamination  point of the shallow aquifer.   This is the portion of the plume
FIR:0067-R8ES                           ES-3

-------
                                                                Date:   8/22/89
                                                                Final  Revision
with  ground  water currently  being  extracted  and  treated  to  reduce  the
contaminant  levels.    The  effect  of  continuing  treatment  in  reducing  the
concentrations was not included in  the risk  assessment results  given above.

In  addition  to presenting  carcinogenic risks  and health  indices, the  risk
assessment also establishes concentrations  that will protect" public  health.
Preliminary  health-protective  tap-water  concentrations were  calculated  for
both carcinogens and noncarcinogens.   The results are  as follows:
      •  Carcinogens
         - 1,2-OCA                                     0.5  wgA
         - TCE                                         3.2  ugA
         - PCE                                         0.7  ugA
         - Benzene                                     0.8  ugA
      «  Noncarcinogens       •  Unfactored           •  Factored
         - 1,1-OCE               290 ugA             5.8  ugA
         - 1,1-OCA               230 ugA            46   ugA
         - 1,1,1-TCA             340 ugA            68   ug/i
         - Toluene               120 ugA            24   ugA
         - Ethylbenzene            58 ugA            11.6  ugA
         - Xylene                 340 ugA            68   ugA

Based on the  results  of this site-specific  risk assessment, these  concentra-
tions would  be acceptable for a lifetime of daily use of the ground  water.
The  unfactored values  for  noncarcinogens  are   total  exposure values.    The
factored values incorporate a  standard  20 percent  factor for the  contribution
from drinking  water  plus, in  the  case  of 1,1-OCE, an  additional  uncertainty
factor of  10.   These  values were  rounded off   for presentation in the  Risk
Assessment report.  These health-protective  values  are based  on the  cumulative
health effects of noncarcinogens  with  common target  organs.   The  numerical
values  are based  on   the  respective contributions of each compound  to  the
health  index  at  the  time  the  risk  assessment  was prepared.    However,  the
contribution to the health index  for  the chlorinated compounds  is  dominated  by
1,1-OCE  (93  percent)   and  for  the  aromatics  by xylene  (97  percent),  so  the
relative contributions are not  expected  to change significantly.
FIR:0067-R8ES                           ES-4

-------
                                                                Date:  8/22/89
                                                                Final Revision
This FS/RAP establishes cleanup criteria as follows:
      ,•  Cleanup levels must result in  a cumulative health  index of less than
         1 considering the noncarcinogens with common target organs.
      •  Cleanup levels must  result in a  carcinogenic risk of  less  than 1 x
         10"° for each carcinogen.
      •  Cleanup levels must comply with each compound-specific applicable or
         relevant and appropriate requirement.
                                                                 s
For  purposes  of this  FS/RAP  and the  trade-off comparisons  between  alterna-
tives, the health-protective  levels given  above were  used  with the compound-
specific applicable  or relevant and appropriate requirements  to estimate the
cleanup levels.  However,  the actual  concentrations of  each  compound will be
used with\the above criteria to assess when remediation is complete.

The residual risks associated with  the  chemicals  in the soil  above the ground
water near the plant have also been assessed.

Eleven areas  were  identified  in  1983  as potential  sources of contamination.
Three  of  these were  inside the plant, and  eight  were outdoors.   The indoor
areas  were judged  not to  be  potential  sources  of  contamination following
cleaning and inspection for areas of leakage.  In the eight outdoor areas, the
storage  tanks  and  above-ground  facilities  were  cleaned and  removed.   The
exposed soils were tested for inorganic and organic chemicals.  As  a result of
this  testing  and  visual  inspections,  contaminated soils were  excavated and
disposed of at an  off-site, hazardous-waste  landfill.   These removals ranged
from  removal of  visibly stained soil  to an excavation of 5,300 cubic yards of
soil.  The soil cleanup levels established in 1983  and 1984 for this work were
based  on STLC  and  TTLC values.   This  FS/RAP assesses the residual  risk of the
chemicals remaining  in the soil after cleanup.

The   chemicals   remaining   in  the  soil  after   the   1983-34  cleanup  were
predominantly  oil  and grease, phthalates, and metals  (predominantly  zinc, as
zinc  oxide,  lead,  and nickel).   Testing  showed that  the oil  and  grease were
FIR:0067-R8ES                           ES-5

-------
                                                                Date:  8/22/89
                                                                Final Revision
not water  extractable.   A  risk assessment  considering 1ngest1on  and dermal
contact with  the oil and  grease shows  an acceptable  risk.   The  metals are
typically  at  below  background  levels.    The  phthalates  are   at very  low
levels.  Considering  these factors with  the low potential  for  migration and
the fact  that the  areas are  covered  with  heavy-duty  truck pavement  in the
middle of  an Industrial park,  the residual  risk from soil  contamination  is
judged acceptable.

A  variety  of  physical, chemical,  biological,  and  thermal  treatments  were
considered  to remediate  the low  concentrations  of chlorinated hydrocarbons  in
the ground  water at the site.   The technology screening step in the FS process
resulted in identifying carbon adsorption and air stripping as viable remedia-
tion  technologies.    These  technologies were  evaluated for  both centralized
and dispersed  treatment.  The  screening  indicated  that  continuation  of the
centralized combination  of the  carbon adsorption  and air  stripping  is the
preferable  technology for  remediation.  These  are the two  technologies  that
have been used for the interim remedial measures at the site to date.

The remediation  alternatives  developed  for consideration  were   based  on the
relevant site characteristics.   These  included the presence  of  the chemicals
in both the shallow and  intermediate aquifers  at  concentrations  above health-
protective  cleanup  levels.    In  addition  there  is a  small  area  in  the  deep
aquifer where  this occurs.   Computer  simulation  indicated that  the  shallow
aquifer  remediation  should  continue.    In  addition,  remediation  should   be
initiated in the intermediate  aquifer.

Six  alternative  pumping  scenarios   were  considered   for  remediating   the
intermediate aquifer.   These  consisted  of various  numbers and  locations   of
extraction  wells  and  pumping  rates.   The  optimum alterative was a series  of
five extraction wells aligned  along the axis of the intermediate  aquifer plume
pumping from  100 to  150 gpm.   In  addition to these  pumping  scenarios, three
disposal  alternatives  were   considered.     These  included  river  discharge,
surface discharge,  and  injection into the shallow aquifer.   Continuation   of
the current river discharge was indicated as the preferable alternative.

FIR:0067-R8ES                           ES-6

-------
                                                                Date:  8/22/89
                                                                Final Revision
Five alternatives to remediate both the shallow and intermediate aquifers were
analyzed in  detail.   These consisted  of a  no-action alternative,  and four
combinations of  pumping  from different sets  of wells in the  shallow and the
intermediate aquifers.   Computer  simulations  were made  of each of  the five
final  remedial  alternatives  to assess  the relative  effectiveness  and time
required to achieve cleanup for each alternative.

The  no-action  alternative  consists   of  stopping  the  current  pumping  and
treating.    This alternative  is  presented  as  a  baseline  alternative  for
comparison with  the other alternatives.    For  this  alternative the shallow
aquifer  plume  migrates toward  the  northwest,  following the  regional ground-
water  gradient.   Eventually this  plume merges with the  intermediate aquifer
and  continues  flowing  with  the  regional  gradient.    Some  dilution .and
dispersion occurs  naturally with  this  alternative.   The  computer  simulation
indicates that,  for this  no-action alternative,  both the  shallow  and  inter-
mediate aquifers will reach the cleanup concentrations in about 5 to  10 years.
This was  used as  a relative cleanup  period  of  1.0  for comparison  with the
other alternatives.

The  second remedial  alternative consists  of continuing to  pump and treat the
ground water from the shallow aquifer.  No pumping and treating is done  in the
intermediate  aquifer.   Compared with  the no-action alternative,  the shallow
aquifer  reaches  cleanup levels  in half  the  time;  however,  the  intermediate
aquifer  takes  the  same  time  since  no remediation is done  directly  in the
intermediate aquifer.  The reduction  in mass  loading  from the shallow aquifer
to the intermediate aquifer has little effect on the time to reach the cleanup
levels in the intermediate aquifer.

The  third  remedial  alternative consists  of  continuing to  pump and  treat the
ground water from the shallow aquifer.  In addition, five new extraction wells
are  installed in  the  intermediate aquifer.   These new  wells are  pumped  at
rates  from 100 to 150 gpm  concurrently with the ongoing pumping from  the wells
in the shallow  aquifer.    Thus, the combined  pumping  rate  exceeds the current


FIR:0067-R8ES                           ES-7

-------
                                                                Date:  8/22/89
                                                                Final Revision
treatment  plant  capacity   and   the  current  NPOES   permitted  flow  rate.
Therefore, a new 500 gpm air stripper is added to the treatment plant for this
alternative.  This also requires  a new air discharge permit.  This alternative
involves potential  delays  in obtaining the  new permits as well  as  delays in
obtaining access to the new well  locations and  for a new segment of pipeline.
However, assuming these new  wells can be Installed  and operating by the fall
of 1989, the shallow aquifer will reach the cleanup levels In half the time of
the no-action alternative.   The intermediate aquifer is projected to reach the
cleanup levels in 30% of the time required for the no-action alternative.

The fourth remedial  alternative  consists  of continuing  to  pump and treat the
ground water from the shallow aquifer.  In addition, five new extraction wells
are  installed  in  the intermediate  aquifer, as  for  the  third  alternative.
However, for this alternative the combined flow rates for both the shallow and
intermediate  aquifer wells  will be  maintained  below  650  gpm,  the  current
treatment plant capacity.   Thus,  no new permits, with the associated potential
delays, would be required.  There are still  the delays required to obtain the
access  agreements  for the new well   locations  and the  new pipeline segment.
However, assuming these new  wells are installed  and operating by the fall of
1989, a computer  simulation  indicates the pumping rates can  be adjusted such
that both the  shallow and  intermediate aquifers  can reach  the cleanup levels
in 60% of the time required for the no-action alternative.

The fifth remedial  alternative consists  of  continuing  to  pump  and  treat the
ground water from the  shallow aquifer.   In  addition, two new extraction wells
are installed in the  intermediate aquifer.   These new  wells will be pumped at
150 gpm,  and the combined  flow  rate  from  both the shallow  and intermediate
aquifers will be  less than 650 gpm.   Thus,  the  treatment plant does not need
to be expanded, and  no new permits are needed.   Access agreements for the new
well locations  and  the new pipeline  segment are required.    Assuming  the new
wells and pipeline  are installed and operating by  the fall of 1989, computer
simulation  indicates  that  pumping rates  can be  adjusted  such  that  both the
FIR:0067-R8ES                           ES-8

-------
                                                                Date:  8/22/89
                                                                Final Revision
shallow and intermediate aquifers  can  reach the cleanup  levels  in 95% of the
time required  for the no-action alternative.

The  recommended  remedial  alternative  is  the fourth  alternative  described
above.  This  alternative achieves  the  cleanup levels in  only  60% of the time
required for either of the first two alternatives  and 63* of the time for the
fifth  alternative.    The  fourth  alternative  Is  projected  to  take  slightly
longer than the third alternative (60%  compared to  50% of the no-action alter-
native time),  assuming there are no delays in permitting.  However, the fourth
alternative avoids the potential delays  in permitting at  a small Incremental
increase 1n time to achieve the  cleanup  levels.  Thus,  the fourth alternative
was  selected  for implementation.   Each  of the alternatives  is  comparable to
the  others  in terms  of short-term  effectiveness;  long-term effectiveness and
permanence; reduction of  toxicity, mobility,  and volume;  implementibility;
administrative feasibility; and availability of services and materials.  Thus,
the relative time to  achieve the clean up levels  is the primary discriminator
used to distinguish among  the alternatives.
FIR:0067-R8ES                           ES-9

-------
1.0

-------
                                                                Date:  8/22/89
                                                                Final Revision
                               1.0   INTRODUCTION
1.1  PURPOSE OF REPORT
The  overall  purpose  of this  Feasibility  Study/Remedial  Action  Plan  is  to
provide the  Information necessary  to  develop a  feasible and  practical con-
ceptual plan  for  completing  the remediation  of ground  water at  the  former
Firestone facility.   Interim ground-water remediation had  been ongoing since
February  1986,  as required by  the  California Department of  Health Services'
(DHS)  Remedial  Action  Order  HSA  85/86-002  (Appendix A).    This  Feasibility
Study/Remedial  Action Plan  1s to  ensure  that environmental,  technical,  and
cost-effective objectives are met.

The  environmental  objective 1s  to  perform the  remediation  in a  manner that
will preserve and maintain the beneficial uses of regional ground water  (i.e.,
domestic  and  agricultural  uses).   This objective  will  be met by addressing
both  the  quality and  availability of ground  water.    Appropriate  quality
standards are  applied to  protect ground water.   Remediation  strategies  are
considered with respect to minimizing the net use of ground water.

The  technical  objective is to  develop  a remediation plan  that (1) meets the
environmental,  performance,  and safety requirements  throughout the projected
remediation;  (2)  includes  technologies  with demonstrated reliability; and (3)
is  practical  for the site-specific  conditions as documented  in  the  Remedial
Investigation (RI) report prepared in December 1988 (IT, 1988a).

The  cost-effective   objective  is   to   optimize  the  cost  associated  with
completion  of  the  remediation,  considering  both  initial  capital  costs  and
operating costs for the duration of remediation.

1.2  REGULATORY BASIS
The  Remedial  Investigation  and Feasibility  Study/Remedial  Action  Plan have
been   submitted   in   two  reports.    The  initial  report  was  the   Remedial
Investigation (RI) submitted in December 1988.  The RI defined  the  lateral and

FIR:0067-R8S1                           1-1

-------
                                                                Date:  8/22/89
                                                                Final Revision
vertical extent of chemicals in the subsurface, both on site and off site, and
characterized the health and environmental risks associated with them.  The RI
provided the  basis  for the subsequent Feasibility  Study/Remedial  Action Plan
(FS/RAP) presented by  this  report.   The  FS/RAP  evaluates  various remediation
technologies  and screens  a  variety of  alternatives.   It  also presents  a
preliminary conceptual design of the-selected  remedial  action together with a
schedule for implementation.
The FS/RAP  was  prepared to meet  the specific requirements of the California
Department of Health Services' Remedial Action Order,  as well as the applica-
ble requirements,  orders,  and guidance  of the  U.S.  Environmental  Protection
Agency  (EPA),  Department  of  Health  Services (DHS),  Regional  Water  Quality
Control  Board  (RWQC8), Monterey  Say Unified  Air Pollution  Control  District
(MBUAPCD), and Monterey County Health Department.  Specific references include
the following:
      •  DHS Remedial Action Order HSA 85/86-002
      •  California Health  and Safety Code Sections 25356.1 and 25358.7
      •  The Comprehensive Environmental  Response,  Compensation and Liability
         Act of  1980,  (CERCLA)  42 USC Section 9601 et seq as amended by the
         Superfund Amendments  and Reauthorization Act of 1986
      •  The National Oil  and  Hazardous Substances Pollution Contingency Plan,
         40 CFR 300, November 20, 1985
      •  RWQCB Monitoring  and  Reporting Program No. 85-24
      •  RWQCB National Pollutant  Discharge Elimination System  Permit No.  CA
         0048950
      •  EPA  Guidance  Document  for  Conducting   Remedial  Investigations  ind
         Feasibility Studies (EPA 1988)
      •  DHS Site Mitigation Decision Tree
      •  Monterey County Health  Department,  Division of Environmental  Health,
         Permit for Construction, Repair, or Destruction of Water Wells
FIR:0067-R8S1                          1-2

-------
                                                                Date:  8/22/89
                                                                Final Revision
      •  Monterey Bay Unified Air Pollution Control District Permit to Operate
         No.  3168A  and  other  permits   to   operate   associated  with  well
         development.


1.3  ORGANIZATION OF REPORT

It is not possible to conform exactly to the report format and guidance speci-

fied by each of the multiple agencies involved with this project.  This report

1s Intended to  satisfy  the policies and guidance  with  respect to feasibility
studies and ground-water  remediation of the  involved agencies,  primarily the

DHS, EPA, and RWQCB.


This FS/RAP is organized as follows:

      •  Executive Summary

         -  Summarizes  the key  elements  of  this  Feasibility Study/Remedial
            Action Plan

      •  Section 1 - Introduction (this section)

         -  Summarizes the  background  for this  study  and the purpose  of the
            FS/RAP report

      •  Section 2 - Identifying and Screening of Technologies

         -  Identifies the types of technologies and process options that were
            screened for this study in terms of satisfying the remedial action
            objectives and general response actions

      •  Section 3 - Developing Remediation Alternatives

         -  Describes the  rationale for selecting  the  alternatives that were
            chosen  for  detailed  analyses  with  respect  to  evaluation  for
            effectiveness, implementibility, and cost

      •  Section 4 - Detailed Analysis of Remediation Alternatives

         -  Assesses  the  selected  alternatives  in terms of  short- and long-
            term  effectiveness;  permanence; reduction  of mobility, toxicity,
            and  volume;  implementibility;  cost;  compliance with  applicable or
            relevant and appropriate requirements  (ARARs); overall protection;
            state acceptance; and community acceptance
FIR:0067-R8S1                          1-3

-------
                                                                Date:  8/22/89
                                                                Final Revision
      •  Section 5 - Recommended Remedial Action
         -  Summarizes the  key findings 'and  conclusions from  the  FS/RAP and
            presents a conceptual  plan of the recommended remedial action
      •  Section 6 - Responsiveness Summary
         -  Summarizes  the  comments  received   following  the  public  review
            period after the draft of  this  report  1s  Issued.   This section Is
            not Included 1n the draft FS/RAP; 1t will  be*Incorporated Into the
            final FS/RAP.

1.4  BACKGROUND INFORMATION
                                                                   •
1.4.1.  Site Description
The  former Firestone  facility Is  located  at  340 El   Camino  Real  South In
Salinas, California, and covers  256 acres  1n the  Salinas  Valley, the largest
intermountain valley  in  the Central Range.   The  valley trends northwest for
about 90 miles  from Bradley to Monterey Bay  and is from 5 to  10 miles wide.
The Gabllan and Diablo Mountains border  the valley to the  east, and the Santa
Lucia Mountains  border the  valley  to the  west.   Alluvial fans  and  terraces
extend  from the  bordering  mountains  to  the  valley floor,  where  they  are
dissected by the  Salinas  River,  which meanders  in a  relatively narrow flood-
plain through the  valley.   Elevations of the valley  floor are generally  less
than 400 feet above mean sea  level  (msl).   The  area near the former Firestone
facility ranges from about 60 to 70 feet in elevation.

The  agricultural  lands  adjacent to  the  former  Firestone  facility  are  plowed
and  leveled on a  regular basis.  This  flat  plain is generally broken into two
areas.  The area  to the  south-southwest  of  the  facility is a floodplain at an
elevation of 45 feet, about 25 feet lower than the former plant.  This area is
bounded on the north by  an  erosional  bank.   At  the top of  this bank is a dirt
farm  road,  locally referred to  as  "Scarp  Road."   The   second  area where the
higher plain is broken is along Alisal  Slough.  The slough  is a narrow channel
FIR:0067-R8S1                          1-4

-------
                                                                Date:  8/22/89
                                                                Final Revision
that runs northwesterly from about  3/4  mile  west of the plant to Harris Road,

where it has been filled.


1.4.2.  Site History
Between  1963  and  1980,  Firestone Tire  &  Rubber Company  operated  a tire-

manufacturing  facility  located at  340  El  Camino Real  South,  approximately 6

miles  southeast  of  downtown  Salinas,  California  (Figures 1-1  and  1-2).

Firestone's  tire-manufacturing  operation  used  a  variety  of chemicals  and

chemical formulations.  The following major categories of chemicals were used:

         Carbon black
         Styrene-butadiene rubber
         Processing oils
         Zinc oxide
         Clay
         Surfactants
         Solvents
         Antioxidants
         Steel wire
         Natural rubber
         Petroleum distillate  fuels.


In  March 1983,  Firestone  began investigations  at  its  Salinas  facility  to

comply  with closure  requirements  of  the facility'-s  Interim Status Document,

under  the  Resource   Conservation  and  Recovery  Act,  and  of  the  California

Department  of Health Services and the  Central  Coast  Regional  Water  Quality

Control  Board.   Based on findings  from the  closure investigations, Firestone

began  on-site  investigations  in  July  1983  to  characterize  the  nature  and

extent of chemicals in both soil and ground water  (Appendix  B).


The  findings  of  the  early remedial  investigations prompted  the undertaking  of

interim  remedial  measures  for  both  soil  and  ground-water cleanuo.   These

interim  remedial measures have included source control  and  migration  control.

Source  control  measures consisted  of  removing underground  and  aboveground

tanks and excavating  and  disposing  of contaminated  soil in an off-site Class I

landfill.    At  present,  both on-site  and   off-site  ground  water  is being



FIR:0067-R8S1                           1-5

-------
                                                                Date:  8/22/89
                                                                Final Revision
extracted  and  treated to  control further  chemical migration  and  to reduce
concentrations.  The  remedial  activities performed  up to December  1988 were
described in detail in the Remedial Investigation Report submitted in December
1988  (IT,  1988a).   The  operating permits  for these remedial  activities are
included in Appendix A.

The locations of wells in the shallow aquifer and 1n the Intermediate zone are
shown on Figures 1-3 and 1-4, respectively.   Figure 1-5 shows the location of
monitoring  wells  in   the   deep   aquifer.    The  locations  of  agricultural,
domestic.  Industrial,  and  municipal wells  in the  deep aquifer  are shown on
Figure 1-6.  Soil  sample locations and  chemical  concentrations  are shown in
Figures 1-7 through 1-14.

1.4.3.  Environmental  Fate of Chemicals at the Site
The Risk  Assessment (IT,  19885)  and the  Remedial  Investigation  (IT, 1988a)
reports have  both  discussed the  environmental fate of the  chemicals at the
site.   The key question  addressed  in those  reports  1s  "why has vinyl chloride
not been  detected  in the  soils  or  ground water  at   the  Firestone  site in
Salinas?"  This  section  summarizes and  expands  on the  explanations given in
the earlier reports.

There  are  two  classes  of  chlorinated  solvents  that  were  commonly  used in
industry during the period the plant operated (1960s to 1980s).   These are the
chlorinated ethenes, particularly perchlorethylene (tetrachloroethene, or PCE)
and trichloroethylene  (trichloroethene,  or  TCE);  and the chlorinated ethanes,
of which  1,1,1 trichloroethane (methyl  chloroform,  or TCA)   is  the  only sig-
nificant representative.   The  former Firestone tire facility at Salinas used
TCA as the chlorinated solvent of choice.

As  described  in  the  earlier  reports,   sanitary  landfills  that  apparently
received no  vinyl  chloride  (chloroethene,  or VC)  have shown  significant VC
concentrations in  landfill  gas  and in liquid  leachate.   In  some cases,  VC is
not detected  until several  years after  the  landfill  had been  closed.   Much
FIR:0067-R8S1                          1-6

-------
                                                                Date:  8/22/89
                                                                Final Revision
research has  demonstrated  that these  landfills  indeed did not  receive waste

VC,  as  such.    Instead,  the  VC  is  produced  by  bacterial  degradation  of

chlorinated ethenes,  by a  step-wise  process.   The  earlier  reports  provide

details, but the major features are as follows:


      •  Stepwlse degradation of  PCE to  TCE,  TCE to 1,2-DCE (dlchloroethene),

         and 1,2-DCE to VC


      •  The process requires a mildly acidic environment, such as is found in

         the leachate of sanitary landfills.


      •  No production of 1,1-OCE (The compound found in highest concentration

         at the Firestone site) occurs under such conditions.


Thus,  vinyl  chloride  can  result  from biodegradation  of  PCE or  TCE  in  the

environment.  However, 1,1-OCE does not result from such a process.


The reports also  discuss the degradation of  1,1,1-TCA,  a chlorinated ethane,
in the environment.  The major features are as follows:

      •  TCA degrades by chemical action to acetic acid and hydrochloric acid,
         and also produces some  1,1-DCE  in  the process.  The  1,1-DCE yield is
         about 20 percent of the total TCA degraded.

      •  Biodegradation  processes  producing 1,1-OCE from  1,1,1-TCA  have also
         been  reported.   The  by-product of  these  is hydrochloric  acid.   In
         addition,  1,2-OCA  (dichloroethane)   is  reportedly  produced   in  TCA
         biodegradation.   It  is also known to  be  a contaminant  of commercial
         grade TCA.  Some 1,2-OCA is found in ground water at  the site.

      •  These processes operate in an alkaline environment.   Hence, the vinyl
         chloride  degradation process  described for  chloroethenes will  not
         operate (since  it requires an acidic environment).
                           i
      •  Any acetic acid and hydrochloric acid produced will be neutralized by
         the generally alkaline medium of  the site  ground water.  The quanti-
         ties of these acids  produced  are  exceptionally small  (in the tens to
         hundreds  of  ppb  range),  and so  the residual  anions  would  not  be
         detectable against background.  Further, other bacteria probably will
         decompose acetate to C02 and H20.

FIR:0067-R8S1                          1-7

-------
                                                                Date:  8/22/89
                                                                Final Revision
In summary, compounds  such  as PCE and TCE can  be  degraded 1n the environment
to vinyl  chloride.   The process  requires an acidic  environment  and operates
via  anaerobic  bacteria.   These  conditions,  while found  In municipal  solid
waste and sanitary waste landfills, do not exist at the former Firestone site
In  Salinas.   Further,  the  solvent  that  was used,  lsl»l=trichloroethane,
degrades  to  I,l-d1chloroethene  by  processes  that  operate 1n  an  aerobic,
alkaline environment.  These  are  the environmental  conditions In  the soil and
ground water  at  the site.   Therefore, vinyl chloride  1s  not expected  to be
found In ground water at the former Firestone facility 1n Salinas.

1.4.4.  Residual  Risk from Soil Contaminants

1.4.4.1.  Introduction
In  1983-84,  Woodward-Clyde  Consultants  (WCC)  carried  out an  intensive soil
Investigation  and  removal   action  in   9   areas   of  the  Firestone-Salinas
facility.   Interim cleanup criteria were  developed by OHS  and/or  by WCC.  The
soil cleanup  levels were  based on the soluble  threshold  limit  concentrations
(STLC)  and  total  threshold  limit concentrations  (TTLC),  which  are  values
proposed  by  the  State  to  determine 1f  wastes  containing  bioaccumulative or
persistent (B/P)  toxic substances are hazardous.

The  parameters  used to  establish the  1983   cleanup  levels at the Firestone
facility  were  determined  after considering  that over  50  individual  elements
and  compounds  were  found in  the  soil, but only  11 were  found in  measurable
concentrations in  near-surface ground  water.   The concentrations  in  ground
water were at levels 100 times less than the  concentrations in the soil.  This
indicates that the rate and  extent of  leaching  into the ground  water has been
very low for most of the soil contaminants.

WCC proposed at that time to establish  the following soil  cleanup  levels:
      •  Organics:  Soil concentration  twice  STLC
FIR:0067-R8S1                          1-8

-------
                                                                Date:  8/22/89
                                                                Final Revision
      •  Metals:  Soil concentration equal to 50 percent of the TTLC.


The proposed  soil  cleanup level  for metals was  based  on a  DHS  request that

lead (Pb) in soil at another site being investigated by WCC be reduced through

soil removal to 500 mg/Kg (50 percent of TTLC).


Initial soil and ground-water analyses were conducted for priority pollutants,

metals,  oil  and  grease,  total   organic  carbons,  total  organic  halogens,

phthalates,  and polynuclear  aromatic  hydrocarbons.    The primary  chemicals

identified in the soils were (Woodward-Clyde Consultants, 1984a):

         1,1-dichloroethene (1,1-OCE)            •  benzene
         1,1-dichloroethane (1,1-OCA)            •  ethylbenzene
         1,2-dichloroethane (1,2-DCA)            •  toluene
         1,1,1-trichloroethane (1,1,1-TCA)       •  xylene
         trichloroethene  (TCE)                   •  oil and grease
         tetrachloroethene (PCE).


Table  3-1  of the  Remedial  Investigation  report  (IT,  1988a)  lists  STLCs and

TTLCs for all the additional chemicals found in the soil.


Based  on.  the  analytical  results  from  the  Initial   studies, the  following

chemicals were  identified for  future testing  and  have  been the basis for risk

assessment and the ongoing ground-water monitoring program (IT, 1988a):


         1,1-OCE                       ,             1,1,1-TCA
         1,1-OCA                      v             benzene
         1,2-OCA                                    toluene
         TCE                                        xylene
         PCE                                        ethylbenzene


1.4.4.2.  Description of  Soil Removal Activities and Analytical Data

The  following  11  areas  at  the Firestone site were investigated  in  1983 and
1984, during the initial  phase of  the project:
FIR:0067-R8S1                          1-9

-------
                                                                Date:  8/22/89
                                                                Final Revision
      OUTDOOR AREAS                                 INDOOR AREAS
      Fuel Storage Area, Area 1                  Banbury Pits
      Courtyard, Area 2                          Curing Room
      Raw Materials Storage and                  Utility Trenches and
       Rallcar Unloading, Area 3                  Outdoor Corridor
      Sludge-Drying Beds, Area 4
      Holding Ponds, Area 5
      Seepage Beds, Area 6
      Waste Oil Storage and
       Transfer Yard, Area 7
      Evaporation Ponds, Area 8
                                             --  .                •
Each area was  evaluated against the interim cleanup  levels  for each chemical
and/or material.   Where  necessary,  mitigation activities were  undertaken to
meet the interim soil clean-up levels.

Chemicals detected  in  the  indoor  areas  were found  in sludges  and residues
remaining after the  plant shutdown.  After the  residuals  were removed, these
indoor areas were  cleaned.    The  floors were inspected for  signs of possible
leakage,  such  as cracked,  broken,  or  deteriorated  concrete.    No  cracks or
other signs of  leakage were found and, thus, the areas were judged  not to be
potential sources of ground-water contamination.

The  following  is  a  summary,  by area,  of the  type  of contamination found at
each of the outdoor  areas,  and  of the  type  of remedial activities undertaken.
Details of the  analytical results before and after mitigation activities are
presented in Woodward-Clyde's 1984 report.  Also, for areas 3, 4 and 7, native
soil  excavation  work  was required.   Analytical results  are given  for  soil
samples taken after completion of this  remedial work.
FIR:0067-R8S1                          1-10

-------
                                                                Date:  8/22/89
                                                                Final Revision
Fuel Oil Storage - Area 1
This area contained  eight underground fuel oil storage  tanks.   No detectable
levels of fuel  components or PCB  contaminants were found.   Oil  samples from
the tanks were found to contain  3  to  4 ppm of Aroclor 1260, a polychlorinated
biphenyl (PCB) compound.   After  removal of the tanks, no  PCB soil or ground-
water  contamination  above  the   detection  limits of  0.5  ug/z  for  soil,  and
0.1 ug/i for  water,  was  found.    No  remediation  was  done in this  area,  and
after tank removal", this area was considered to be properly closed.

Courtyard - Area 2
During  the  plant  operation  the courtyard  was a  multipurpose area  used  for
maintenance and  storage  with  a cooling  pond and  a hazardous waste storage
area.

The  surface  soils  in  the  hazardous  waste  storage  part  of  the  courtyard
contained  low  levels  of several  organic  compounds  (phthalate esters  and
polynuclear aromatics).   Metals  in the 100 to 200 ppm range were found in the
east-west ditch and the cooling tower ditch. Soil  from the ditches and an area
outside of  the  door to the  main building was  removed to a depth of  6 to 18
inches and disposed  of at a  Class  I hazardous waste disposal facility.  After
removal of  this  soil,  remaining  levels of organics  and  inorganics were found
to be  at background  levels and below  the  cleanup  levels prescribed in the OHS
Remedial  Action  Order,   and  in  the   February  29,  1984  letter  from  DHS  to
Firestone.

The area does not  constitute a threat to  public health or ground water and no
further  remedial   action  was required.   This area  was  accepted  as properly
closed.

Raw Materials Storage - Area 3
Raw materials used at  the plant  were  transported  to Area 3 by train and truck
and stored in 11 underground steel  storage tanks,  with capacities ranging from

FIR:0067-R8S1                           1-11

-------
                                                                Date:  8/22/89
                                                                Final Revision
5,000  to  14,000 gallons.   Materials that were  stored 1n the  tanks Included
gasoline, kerosene, acetone, hexane, wax, pine tar, naphtha, aromatic oil, and
various antioxidants.   The  area formerly contained a  silo  for storing carbon
black.  Numerous soil and ground-water samples were collected in this area and
analyzed for priority pollutants, metals, oil  and  grease  (O&G), total organic
carbon (TOC), and  total  organic halogens (TOX).   Various  chemical  substances
were  found  In greater  numbers  and  at higher  concentrations 1n the  soil and
ground water  in this area  than  in  any other area sampled during  the Initial
investigation (Woodward-Clyde Consultants, 1984a).

An extensive  cleanup of this area  was carried out, including  removal  of all
underground storage tanks, removal of soil in two phases (Phases A and 8), and
treatment of ground  water.   Phase A involved  removal  of  all plant equipment,
piping and tanks,  and  removal  of the contaminated soil to  a depth of  3  to 6
feet.  Samples  taken from  the  upper 18  inches  of soil at  the  bottom of the
excavation showed  no VOCs,  with the exception of  3.4  ppm of ethyl  benzene in
one  sample.   Oil  and grease  was still  present  (2,800 ppm) and  chromium and
zinc were detected at levels of 53 and 73 ppm.

In phase B,  the area of highest contamination was excavated to a  depth of 40
feet,  and  5,300 cubic  yards  of  soil  were removed.   After  backfilling  with
clean soil  an 8-inch asphalt cap was put in place.   Subsequently, concrete has
been  placed  over some of this  area as  well.   During the  Phase B excavation
work,  a  soil sampling  and  testing  program was  carried out on  the  excavated
soils.   Inorganics were below background levels.   Individual  organic species
were detected only in parts-per-billion concentrations.  Oil  and grease, found
at  levels  of  about  5,000  ppm,  did  not contain water  extractable  organic
constituents.

Sludge-Drying Beds - Area 4
This area contained three ponds that served as drying beds for sludge from the
industrial  wastewater  treatment  plant.   No  volatile  organic  compounds  were

FIR:0067-R8S1                          1-12

-------
                                                                Date:  8/22/89
                                                                Final Revision
detected in the six soil samples  taken  in  these beds,  one each at the surface
and at  a  depth of 4.5  feet in each  pond.   Phthalates were  found  at concen-
trations up  to 4.6 ppm.   Metal  concentrations were generally  at  background
levels.

Oil and grease  concentrations  as  high as 63,000 ppm were detected  in all the
deeper  (to  36 feet)  soil  samples,   teachability  tests with water  showed no
detectable oil  and grease  1n the water.  The  only remedial  work performed in
this area was removing  12-18 inches  of  contaminated top soil and replacing it
with clean backfill.

Holding Ponds - Area 5
The two ponds in Area 5 were used to hold storm-water runoff that exceeded the
capacity of the industrial wastewater treatment plant.   No volatile compounds
were found  in  the six soil samples taken at depths up  to 14 feet,  or the two
ground-water samples, taken  at depths of 25 feet  to 35 feet.   No orgam'cs or
metals  were found in  the  ground  water;   no  soil remediation  was  required,
based  on  observed soil  concentrations.   This  area  was  considered  properly
closed.

Seepage Beds - Area 6
Area  6 contained two  seepage ponds  that  received  treated  water  from two
sources -  the  sewage  treatment plant and the  industrial  wastewater treatment
plant.   The  results  of the  analyses showed  the  presence of  phthalates and
hexane  in  soil  at the 1 ppm  level  and  xylene at  0.1 ppm.   The values of the
metals, with the  exception of  zinc,  lead,  and nickel  were below STLC and TTLC
values.   The observed values  for lead,  zinc, and  nickel  were  well  below the
recommended  interim  cleanup levels developed  by Woodward-Clyde.   No remedial
action  for  these  areas  was recommended  based on the lack of potential impacts
on public health  or the environment.
FIR:0067-R8S1                          1-13

-------
                                                                Date:  8/22/89
                                                                Final Revision
Waste-011 Storage and Transformer Yard - Area 7
Area  7  contained  three  tanks used  for  the  storage  of various  processing
materials.  An above ground tank  in  the southern part of the yard was used to
store caustic soda/rubber  latex.   A burled tank  and  the above ground tank in
the northern part of the yard were used for the storage of waste oils.

An approximately I0-foot-d1ameter discolored area 1n  the southeastern portion
of the yard was  also Investigated.   Two soil  samples were collected from the
excavated area after the tanks were  removed.   No volatiles were detected, but
low levels of  phthalates were found.   Metal concentrations were below back-
ground, and no further remedial work was performed 1n this area.

Since no contaminants were detected  at  the site,  after removing the tanks and
any visually stained  surflclal soils,  no  remedial program was  necessary for
the transformer yard.  This area was considered to be clean.

Evaporation Ponds - Area 8
Area  8  contained three  ponds  that  were used  for storing excess  storm water
runoff  before  the  Industrial  wastewater  treatment  plant  was built.    No
detectable volatile  compounds  were  found  in the  three surface  soil  samples
analyzed;  low  phthalate concentrations were  detected.   Metal concentrations
were  below background  levels and lead  and nickel were  far  below the interim
cleanup levels.

This  area did  not  appear to  represent   a  threat to public  health or the
environment.    As a  result, it  was recommended  that  this  area not  receive
further investigation and be considered as properly closed.

1.4.4.3.  Residual  Soil Levels and Their Hazards
The investigations of  the  various source areas, Areas  1 through 8, conducted
in  1983  and  1984  showed that inorganic  chemical  concentrations in  soils in
Areas 1, 2, 5, 6, 8 were at or below background levels; thus,  these areas did
not  require  remedial  measures.   "Background"  means  the  average range  of


FIR:0067-R8S1                          1-14

-------
                                                                Date:  8/22/89
                                                                Final Revision
inorganics found in the earth's crust (EPA-OSWERSW-874, April 1983).  Remedial
measures  were  required and  subsequently implemented   at Areas  3, 4  and 7,
where the  soils  left  in place contained low  levels  of some  volatile or semi-
volatile  organic  compounds.    In  many cases,  significant levels of  "oil  and
grease" were detected  (concentrations  in the 1,000  to 50,000  ppm range).   In
each  case, the oil  and grease was  extracted with  deionized  water,  and  the
extracts  tested  for oil and grease.   In all such extracts, no  organics were
detected.  The soil analytical data  from the initial investigations indicated
that  no further  soil  remediation was  required.   Therefore,  all  subsequent
interim remediation activities were directed solely toward ground water.

The soil cap and asphalt or concrete covers also prevent downward infiltration
of rainwater.   Human  access  to, and direct  exposure to the  remaining soil is
not probable.  The shallow aquifer has dropped several feet below the level in
the  original  areas  (1 through 8)  of chemical  contamination.   Migration to
ground  water  is thus  unlikely.   Regional flow  in the  shallow  aquifer moves
from  south of  the site to the northwest.  An extensive array  of ground-water
monitoring and extraction wells covers possible flow paths away from the plant
area.   Ground-water monitoring results since  1985 demonstrate  that no organic
compounds  are entering on-site  ground  water  from  these yard  areas.   The
existing  on-site  monitoring  and  extraction wells  have not   detected  any
remaining  source  of  soil  contaminants,  entering the  ground  water  from  the
zones  that have been  remediated  (Zones  3,  4 and 7)  and from  all  the other
zones (Zones 1, 2, 5,  6, and 8).

Specifically,  for the  soils  remaining   in the  eight  areas  investigated,  the
potential  residual  risks to  human health and  the  environment  are described
below:

Area  3  -  Raw Material  Storage
After   the excavation  in  Phase  A  and  Phase   B   and   the  removal  of  the
contaminated soil, the  residual soil left at the bottom of the excavated areas
had the following highest observed concentrations: (in mg/kg).


FIR:0067-R8Sl                          1-15

-------
                                                                Date:  8/22/89
                                                                Final Revision
      Oil and Grease
      Ethylbenzene
      Chromium
      Zinc
      Benzene
      Xylenes
      Methyl Cyclohexane
Phase A
  2800
   3.4
    53
    73
    NO
    NO
    NO
Phase B
 4100
0.026
   NO
   NO
0.033
 0.11
 0.22
Drainage Ditch
     470
      NO
      38
      53
      NO
      NO
      NO
The  BTX plume  (Benzene,  Toluene,  Xylene)  appeared  to  be  confined  to  the
section of  Area 3 adjacent to  the  cement house.   This plume  appeared to be
somewhat limited  due to  the  retardation properties  of the  thick  clay layer
underlying  this section.   The  mobility of  the  volatile organic  compounds
(benzene, toluene, xylene  and  ethylbenzene)  in soil  is controlled  by several
geochemical factors,  such as the following:

      •  Sorption; by natural  soil organic matter and by oil and grease

      •  Biodegradation;  in near surface aerobic  zones and  also underground
         under anaerobic conditions

      •  Two-phase Flow;  because of  variations in  density  in  the  different
         media.

To conclude,  the potential existence  of some  VOC's under the  building near
area 3  appears  to have been limited by  the  low migrating  capabilities of the
organic components in question.   If a  significant  amount  of VOC had been left
under  the  building  it  should  have  been  detected  by  the  active ground-water
monitoring wells.  But none has been observed in over five years.
FIR:0067-R8S1
       1-16

-------
                                                                Date:  8/22/89
                                                                Final Revision
The oil  and  grease observed  in  the residual soil  left at the  bottom of the
excavation has  a very  low potential impact on  health and environment.   The
same  factors  affecting the  mobility of VOC's affect  in a larger  manner the
mobility or migratory tendencies of the  larger  molecules of  oil  and grease.
The only possible  exposure to these contaminants  is by dermal contact and/or
by soil  ingestion.   The toxicity of oil  and grease 1s very low, with a TDLo
(Tumor  Dose-Low)  1n  the  gm/kg  range  (grams  of  substance   per  kg  of  body
weight).

According  to  the California Site Mitigation Decision  Tree Manual  (1985) the
Department of Health  Services  (DHS) developed  Applied Action  Levels (AALs)
criteria to evaluate and, if necessary, to mitigate the impact of uncontrolled
hazardous waste  sites on the public health and  the environment.  When soil is
the  medium  of  exposure,   two   routes,   ingestion and  dermal  contact,  are
addressed  in  developing AALs.   A reasonable and  conservative  estimate of the
average  daily soil ingestion  is 0.15 g/day, and  an estimate  of  the average
daily soil exposure by dermal contact is 0.45g/day (Sedman, 1989).

The TDLo values  for heavy  oils  (RTECS  1983) range from 1 to 10 g/Kg, or  70 to
700 grams  per day  for an adult.   At an average daily exposure  (ingestion plus
contact) to 0.6  grams of soil, and  a maximum of  6500  ppm oil  and grease, the
daily dose would be:
      Dose =  65000 ug/g x 0.6 g/day = 39 mg/day.
      This dose  is l/2000th  to 1/20,000th of the reported TDLo.
Another  insight  into  the  relatively  low  hazard  of oil  and grease  comes from
the  measured  soil  concentrations   of  polynuclear  aromatics  (PNA)  at the
facility.   Generally,  each  sample showed  two  or  three PNAs,  at  most,  in
concentrations of  10  to 20 ppb.  Ratioing these with the maximum 65000 ppm oil
and grease level  found, this is about  equal to 1  ppm total PNA in the oil and
grease.  This corresponds  to 1  ug per gram of oil and grease.  With the  39 mg
daily dose calculated above, the average daily exposure to PNAs would be:
      PNA  dose = 1 ug/g x  .039 g/day = 0.04  ug
 FIR:0067-R8S1                          1-17

-------
                                                                Date:  8/22/89
                                                                Final Revision
A daily dose of 0.04 wg benzo(a) pyrene equivalent represents an insignificant
risk to human health.  This  is  particularly true because there is no credible
scenario whereby  an individual  could  receive  a 70 year  exposure  to material
burled under clean soil in the middle of an industrial park.

The inorganic level in the residual  soil  1s at nominal soil background levels
with the exception of zinc  (Zn).   This metal  1s  present only  as zinc oxide
(ZhO) which  is  harmless.   It is 1n  fact  used  in medicinal  preparations (zinc
oxide ointment) and is classified by the  Food  and  Drug Administration as GRAS
(Generally Regarded as Safe).

Area 4 - Sludge Drying Beds
The residual soil  left 1n the top layer removal of Area  4  show the following
level of contamination (in mg/kg):

      Oil and Grease                             63,000
      Cr                                             42
      Pb                                              6
      N1                                             55
      Zn                                            110
      Phthalates (3)                              0.112
      Phenanthrene & Naphthalene                  0.011
      BEHP (a phthalate ester)                      4.6

The same considerations given to the  impact of  oil and grease  for Area 3 are
applicable to this area.

The metals, except zinc,  are at background level.  Again,  zinc is found in the
harmless zinc oxide form.

The  phthalates  measured  in  the  samples  do  not  appear  to  result  from
Firestone's activities.   The manufacture  of tires did  not  include the use of

FIR:0067-R8S1                          1-18

-------
                                                                Date:  8/22/89
                                                                Final Revision
these compounds.  Phthalates are used mostly as plastidzers In the production
of polyvlnyl chloride  (PVC)  film.   Soil samples were  collected  and placed 1n
plastic  baggies (made  of PVC)  and most  probably were  contaminated by  the
phthalates 1n the bags.

The oil  and  grease  at Area 4, burled under one to two feet of fill, does not
pose a significant threat to human health or the environment, as discussed for
Area 3.

Area 7 - Waste 011 Storage/Transformer Yard
After  removal  of  the  two  storage  tanks  and  of  the  soil   that  showed
discoloration, no further action was required.  The  residual soil  left in the
area has only low concentration of  metals  and  phthalates.   Again,  there 1s no
apparent risk to health.

1.5  NONBINDING PRELIMINARY ALLOCATION OF RESPONSIBILITY
Upon consideration  of  all  the evidence,  the  Department  of  Health Services
concludes   that  the   preliminary   non-binding  allocation   of   financial
responsibility 1n this RAP 1s as follows:
         Firestone Tire & Rubber Company         100%
FIR:0067-R8S1                          1-19

-------
2.0

-------
                                                                Date:  8/22/89
                                                                Final Revision
                2.0  IDENTIFYING AND SCREENING OF TECHNOLOGIES
2.1  INTRODUCTION
The  California  Site  Mitigation  Decision  Tree  Manual  (DHS,  1986)  and  the
National Oil and Hazardous  Substances  Pollution  Contingency Plan (EPA, 1985a)
each require a stepped  approach to identifying  and  screening technologies to
be used for remedial action at contaminated sites.  Following characterization
of specific  site problems  and  contaminant  pathways, the  procedures  in these
documents require identification of general response actions that can meet the
remedial  response  objectives.   In general,  these  objectives  can be  met by
implementing any of a variety of  actions.  This  section presents a discussion
of the remedial response objectives, general response actions to satisfy these
objectives, and  potential technologies  that can  be used in implementing these
actions.

2.2  REMEDIAL ACTION OBJECTIVES

2.2.1  Contaminants of Interest
As discussed  in Section 3  of  the  RI  report,  six chlorinated hydrocarbons and
four aromatics  have  been Identified in  the monitoring  program for this site.
These chemicals are as follows:
            CHLORINATED HYDROCARBONS            AROMATICS
          1,1-Dichchloroethane  (1,1-DCA)        Benzene
          1,2-Oichchloroethane  (1,2-QCA)        Toluene
          1,1-Dichloroethene  (1,1-DCE)          Ethylbenzene
          1,1,1-Trichloroethane (1,1,1-TCA)     Xylene  (3  isomers)
          Trichloroethene (TCE)
          Tetrachlorothene  (PCE)

However,  an  examination of  the geochemical monitoring database  for  the  five
affected • agricultural  wells,  the  one  affected  domestic  well,  and  the  one
affected  inactive  well  shows that  the  actual  chemicals of interest are fewer
than  this.   (Affected well is used here to  indicate  a  well  where chemicals

FIR.-0067-R8S2                         2-1

-------
                                                                Date:  8/22/89
                                                                Final Revision

have  been  detected  on  a repeatable  basis  since  the  monitoring  began.)
1,2-OCA; PCE;  and  the aromatics  have  not been repeatedly detected  in any of
these wells.   Further TCE  has  not  been  detected  in these wells,  except for
Harris B, since  September 1986.  Thus, the  primary chemicals of Interest are
1,1-DCA; 1,1-DCE; and 1,1,1-TCA.

2.2.2  Allowable Concentrations Based on Risk Assessment
A key finding of the  risk  assessment  prepared  for this project (IT, 1988b) is
establishing ground-water  concentrations  that protect  public  health  and the
environment.    These  health-protective  levels  were  established  by  back-
calculating  from  a  carcinogenic risk  criterion  of  a  one  in one  million
(1 x 10" ) hazard,  or a noncarcinogenic index  criterion  of one, to a chemical
concentration at a  domestic-use tap.   These health-protective  levels  and the
maximum contaminant levels (MCL) respective values in ug/i are as follows:

                               Health-Protective
       •  Carcinogens               Levels                  MCLs

          - 1,2-OCA                  0.5                    0.5
          - TCE                      3.2                    5
          - PCE                      0.7                    5
          - Benzene                  0.8                    1

                               Health-Protective Levels
       •  Noncarcinogens        Unfactored     Factored      MCLs

          - 1,1-DCE                 290           6             6
          - 1,1-DCA                 230          50             5
          - 1,1,1-TCA               340          70           200
          - Toluene                 120          20
          - Ethyl benzene             58          10           680
          - Xylenes (3 isomers)     340          70         1,750
FIR:0067-R8S2                         2-2

-------
                                                                Date:  8/22/89
                                                                Final Revision

Based on the  results  of this site-specific risk  assessment,  these concentra-
tions would  be acceptable for  a lifetime of  daily  use of the  ground water.
The  unfactored values  for  noncarcinogens  are  total  exposure  values.   The
factored values incorporate  a standard  20 percent factor for the contribution
from drinking  water plus, in the  case of  1,1-OCE,  an additional uncertainty
factor of 10.  These values have been rounded off.

2.2.3  Review of Applicable or Relevant and Appropriate Requirements (ARARs)
       and To-Be-Considered Materials (TBCs)
CERCLA Section 121 requires  selection of  a remedial  action that is protective
of human  health  and the  environment.   EPA's  approach to determining protec-
tiveness involves  a risk assessment, considering  both applicable or relevant
and  appropriate  requirements   (ARAR)  and  To-Be-Considered  (TBC)  materials.
CERCLA  remedial  actions  that  leave any  hazardous  substance,  pollutant,  or
contaminant on site must meet, upon completion of the  remedial action, a level
or standard of control  that  at  least attains standards, requirements, limita-
tions, or criteria  that are applicable or  relevant  and appropriate under any
Federal environmental  law and  State environmental or  siting  law that is more
stringent  than  Federal  requirements.    Furthermore,  many  State  laws  give
enforcement authority  to agencies.  These  local  agencies develop regulations
that codify State requirements.  As a result, some local regulations can also
be ARARs.

The  EPA Office of  Solid Waste  and  Emergency Response  (OSWER) issued Directive
9234.0-05 on  July  9,   1987  and published  an essentially  identical  document
entitled  "Interim  Guidance  on  Compliance  with Applicable  or  Relevant  and
Appropriate  Requirements  (ARARs)"  (EPA,  1987).    These  guidance  documents
address  Comprehensive  Environmental  Response,   Compensation,   Liability  Act
(CERCLA) requirements  that remedial actions comply with  ARARs  of Federal  and
more  stringent promulgated  State  laws.    OSWER Directive  9234.1-01  "CERCLA
Compliance  with Other  Laws, Manual,  Draft  Guidance"   (EPA,  19886)  issued
August 8,  1988,  and  40  CFR  Part  300,  "The   National   Oil   and  Hazardous
FIR:0067-R8S2                         2-3

-------
                                                                 Date:   8/22/89
                                                                 Final  Revision


 Substances  Pollution Contingency  Plan, Proposed  Rule"  (EPA,  1988c)  provided

 additional   information  on  ARAR  Identification  and  compliance  as  well  as

 defining to-be-considered  (TBC)  material.


 ARARs  are defined  in the interim guidance  document (EPA,  1987)  as  follows:

       Applicable   requirements  means  those cleanup  standards,  standards  of
       control,  and  other  substantive  environmental  protection requirements,
       criteria,  or  limitations  promulgated under federal or  state law  that
	   specifically  address  a  hazardous  substance,   pollutant,  contaminant,
       remedial action,  location, or  other  circumstance at  a CERCLA site.

       Relevant  and  appropriate  requirements  means those cleanup  standards,
       standards  of  control, and  other substantive  environmental  protection
       requirements,   criteria,  or  limitations  promulgated  under  federal  or
       state   law   that,  while  not  "applicable"  to  a   hazardous  substance,
       pollutant, contaminant, remedial  action,  location, or other  circumstance
       at a CERCLA  site, address  problems or situations sufficiently  similar  to
       those  encountered at  the  CERCLA site that  their  use  is well suited  to
       the particular site.


 A  requirement may be either one of these  categories  but  not both.   There  is

 more discretion in the  determination of relevant and appropriate requirements;

 it  is. possible for  only  part of a  requirement to be considered  relevant and

 appropriate  in a  given case.   When the  analysis  results in  a determination
 that  a requirement  is both  relevant and  appropriate,  such a requirement  must

 be  complied  with to  the same degree  as  if  it were  applicable.


 In  addition, the  draft  guidance  manual (EPA, 1988b) and the  proposed  NCR  rule
 revisions (EPA, 1988c)  define To-Be-Considered  materials as follows:


       To-Be-Considered  Materials   (TBCs)   are   nonpromulgated   advisories   or
       guidance  issued  by  federal  or  state government  that are  not  legally
       binding and  do not have the status of potential ARARs.  However,  in  many
       circumstances  TBCs  will be considered along with ARARs  as  part of the
       site risk assessment and  may be used  in  determining the  necessary level
       of cleanup for protection  of health  or the environment.

       ARARs  will  define the cleanup goals  when they  set an acceptable level
       with   respect   to  site-specific  factors.    Cleanup  goals  for   some


 FIR:0067-R8S2                         2-4

-------
                                                                Date:  8/22/89
                                                                Final Revision


      substances  may  have  to  be   based   on  nonpromulgated  criteria  and
      advisories  [for example,  health  advisories  such  as  reference  doses
      (RFD)j  rather  than  on  ARARs  because  ARARs  do  not  exist   for  those
      substances or because an ARAR alone would not be sufficiently protective
      in the  given circumstance,  e.g., where additive effects  from several
      chemicals are involved.  In  these situations,  the cleanup requirements,
      in order to meet the cleanup goals, will not be based on ARARs alone but
      also on TBCs.


ARARs (and TBCs to  some extent)  may  be classified into categories as follows,

although not all ARARs will fall  neatly into this classification system:


      Ambient or  chemical-specific requirements  are usually  health- or risk-
      based  numerical  values  or methodologies which,  when  applied  to site-
      specific  conditions,  result in  the  establishment of numerical values.
      These  values establish  the  acceptable  amount  or  concentration of  a
      chemical  that  may   be   found  in,  or discharged   to,  the  ambient
      environment.

      Performance,  design,  or  other  action-specific requirements are usually
      technology-  or  activity-based  requirements or  limitations  on actions
      taken with respect to hazardous wastes.

      Location-specific requirements are restrictions placed on the concentra-
      tions  of  hazardous  substances  or the conductance of activities solely
      because they occur in special locations.


The initial step for identifying ARARs and TBCs involved reviewing appropriate
lists of  potential ARARs  and  TBCs and  comparing them to  the  site condition

and/or  potential  remedial  activities.   The  NCP  proposed  rule  (EPA,  1988c)

lists examples of potential Federal and State  ARARs and TBCs  in 53 FR 51447 to

53 FR 51450  in the preamble section to the proposed rule.   Potential ARARs and
TBCs  are  presented and  discussed  in  "CERCLA  Compliance  with  Other  Laws,

Manual, Draft Guidance" (EPA,  1988b).  Additionally, a copy of all Federal and
State ARARs  currently identified by the DHS  was  provided  (DHS, 1989).  These

sources of  information were  reviewed  and compiled with site-specific informa-

tion  to  generate  Tables  2-1  to  2-4.  . Table  2-1  presents  Federal  ARARs;

Table 2-2 presents  State and local ARARs; Table 2-3 presents Federal TBCs; and
Table 2-4 presents  State and local TBCs.


FIR:0067-R8S2                         2-5

-------
                                                                Date:  8/22/89
                                                                Final Revision

Contaminant-specific  ARARs  and  TBCs  were  developed  for  the  ground-water
contaminants of interest observed at  or near the facility as part of the Risk
Assessment (IT, 1988b).  Possible requirements, standards and criteria related
to water  quality goals  for organic  constituents  to  provide  protection  for
human health and welfare were summarized in Table 4-2 of the Risk Assessment.

However, since  that report was  issued  DHS revised  the  drinking-water action
levels and  the maximum contaminant levels.   The revised values  (as of April
1989) are shown in Table 2-5.

Examples of location-specific ARARs Include floodplain and wetland regulations
for  modification  or  installation  of  discharge  lines.   National  Pollutant
Discharge Elimination System (NPOES)  permits and  the Monterey  Say Unified Air
Pollution Control District (MBUAPCD)  permit to operate  are  somewhat location
oriented in  that  use-attainability studies for  surface  waters  and attainment
status of regional air quality have an impact on permit limitations.

Action-specific ARARs are discussed  in  detail  in  relation   to  alternative
screening and detailed analyses in Sections 3.0 and 4.0.

2.2.4  Summary of Allowable Concentrations
The  ground-water  cleanup  levels  used  in  this  FS/RAP  are  the lower  of  the
concentrations based on the health-risk assessment, considering the cumulative
health  risks,  and  the concentrations  based  on  the ARARs  discussed  in  the
previous two  sections.   In  general,  the concentrations  based  on the health-
risk assessment are the lower concentrations; however, for benzene and 1,1-DCA
the  State  drinking water  action level  ARARs  are  lower.   Thus,  the cleanup
levels in ug/z, are as follows:
FIR:0067-R8S2                         2-6

-------
                                                                Date:   8/22/89
                                                                Final  Revision

       •   Carcinogens             Clean-up Levels

          - 1,2-DCA                     0.5
          - TCE                         3.2  .                     ,
          - PCE                         0.7
          - Benzene                     0.7

       •   Noncarcinogens
                                                                .. -            *

          - 1,1-DCE                      6
          - 1,1-OCA                      5
          -1,1,1-TCA                    70
          - Toluene                      20
          - Ethyl benzene                 10
          - Xylene                       70

2.2.5  Development of Remedial Action Objectives
The remedial action objectives for the former Firestone facility operable unit
are  based  on  the  current knowledge  of the site  and on  the results  of the
preliminary risk assessment.  The current  knowledge  of the site is summarized
in the Remedial Investigation (IT, 1988a) as updated in the latest geochemical
database, Appendix C.  The Preliminary Risk Assessment (IT, 1988b) was updated
in the RI.  Key response objectives are as follows:
       •  To control migration of chemicals  from  the shallow aquifer into the
          intermediate  and  deep aquifers  where the water  is being  used for
          agricultural and some domestic purposes
       •  To maintain  the  quality of ground water downgradient  of  the former
          Firestone facility suitable for agricultural and domestic use.
Related objectives include the following:
       •  To restore the quality of the shallow aquifer 'to meet State drinking
          water action levels
FIR:0067-R8S2                         2-7

-------
                                                                Date:  8/22/89
                                                                Final Revision


       •  To provide actions that will minimize" adverse impact on the current
          use of the ground water in the area

       •  To provide  actions  that are consistent  with the  intent  of current
          operating permits for the existing treatment plant

       •  To  provide  actions  that  protect the health  of  the  workers  and
          residents in the vicinity of the site.


2.3  GENERAL RESPONSE ACTIONS

The feasibility  study procedures  followed by both California  and EPA specify

identifying  general  response  actions (DHS,  1986;  EPA,  1988a;  EPA,  1985b).

From the inception of the studies at the Firestone site, the following general

response action categories have been identified:

          Air pollution controls
          Surface-water controls
          Ground-water controls
          Gas migration control
          Waste removal
          Contaminated soil excavation
          Land disposal
          Temporary storage
          Control of Abeloe well contamination.


The air  pollution  controls apply to  the airstripper  at  the treatment plant.

These will continue throughout  the use of the  airstripper.   The surface-water

controls currently  apply to the  discharge  from the  treatment  plant into the

Salinas  River. .  These  controls  will   continue throughout  the  use of  the
treatment plan.  Ground-water  controls  are a  significant part of the ongoing

interim  remediation.    Currently, these  controls include  source  control  by

limiting the  ground-water flow containing chemicals  from the  shallow aquifer

into the intermediate zone.  In addition, these controls include hydrogeologic
containment of flow in the shallow aquifer.


Gas migration  control  was exercised  when the  soil-gas extraction  system was

operating.    Currently,  this  is not an  operable  general  response  action.

Likewise, waste  removal  was performed  when the plant was  closed  but  is not


FIR:0067-R8S2                         2-8

-------
                                                                Date:  8/22/89
                                                                Final Revision

operable currently.    Therefore,  waste  removal  is  not  an operable  general
response action.

Contaminated soil was  excavated during the  early remediation efforts  at the
site, as discussed  in  the remedial  Investigation report.   This contaminated
soil  was  disposed   of  at  a   licensed  Class  I  hazardous  waste  landfill.
Currently,  there  is  no  soil  excavation or  land  disposal  from  the Firestone
site so these are not operable general response actions.  Temporary storage of
chemicals occurred when the facility was being closed.   Currently, there  is no
temporary storage at the site  associated with the Firestone operations.

The  water  quality in  the  Abeloe well  initially  exceeded  the  State drinking
water  action level   for 1,1-OCE.    However,  the State and EPA subsequently
reevaluated the toxicity of 1,1-OCE  and raised  their allowable limits.   Thus,
control of this water is not currently a general response action.

The  current  general  response  actions and those foreseeable in the future are
used in conjunction  with site-specific problems and viable pathways to  focus
subsequent remedial   alternative evaluation.   They  also must  be used  in con-
junction with the remedial  action objectives and the allowable exposures  based
on  the  risk  assessment  and the ARARs discussed  above  to develop  a range of
treatment and containment alternatives that satisfy these criteria.

General response actions applicable to the Firestone site are as follows:
          No action
          Pumping on site
          Pumping off site
          Partial removal
          On-site (centralized) treatment
          Off-site (dispersed) treatment
          Off-site disposal.
                          /
In  accordance  with  the  September  24,  1987,  letter   from  Firestone  to DHS
(Firestone  Tire &  Rubber  Company,  1987),  this  feasibility  study is  to be

FIR:0067-R8S2                         2-9

-------
                                                                Date:  8/22/89
                                                                Final Revision

focused on the chemicals in the ground water.   Also, the no action alternative
becomes a shutdown of the existing system  rather  than a "do nothing" scenario
because there has already been substantial  remediation.

2.4  TECHNOLOGY TYPES AND PROCESS OPTIONS
This  section   briefly   describes  technology  types   and   process  options.
Physical, chemical, biological, and thermal treatment methods are summarized.
Figure 2-1  presents  the physical treatment methods,  and Figure  2-2 presents
the  chemical,  biological,  and thermal  treatment  methods  discussed  in  this
section.    An overview  of  technology  process  options is presented  in Figure
2-3.

2.4.1  Physical Treatment Methods

2.4.1.1 Coaqulation/Flocculation
The application  of  coagulatlon/flocculation involves  the  controlled addition
of  chemical  agents such  as  alum  or  polymers.   The  action of  these agents
serves to  create a  second phase  by  transforming  a  suspension  of ultrafine
particles into coagulated material or floes of larger particles (Berkowitz et
al,  1978,  page  503).   The  floes may  then be easily separated  by gravity,
thickening,  skimming,   filtration,  or  centrifugation.   This  technology  is
suitable  for treatment of waste streams containing suspended solids.

Coagulation/flocculation would  not  be an  effective treatment  method  for the
low  concentrations  of  organic constituents  found in  the  Firestone  Salinas
ground water.  Thus, no further  consideration  will  be given to this treatment
method for implementation at the Firestone  Salinas site.

2.4.1.2  Oil-Water Separation
Oil-water separation  technology  combines chemical  addition,  temperature con-
trol, and  a variety of engineered vessel  designs  to  enhance oil-water sepa-
ration.    Separator  vessel   designs  may  be   a  series  of  baffled  chambers
                                                                              i

FIR:0067-R8S2                         2-10

-------
                                                                Date:  8/22/89
                                                                Final Revision

(American Petroleum  Institute-type),  or  a  single vessel  that is  heated and
mildly agitated.  Coalescers are vessels with plates or packing to enhance the
collection and recovery of ultrafine oil  particles.   Chemical  addition and pH
adjustment are  frequently used  in addition  to aid  in separation,  to speed
coalescing action,  or to  aid  in  breaking  down of  emulsions  that  may form.
Heating may  be performed  to  reduce viscosity  and enhance the  separation of
emulsions.

Free oil  product  may be  removed from the separator  by manual  skimming with a
pump or  vacuum truck.  Wicking  ropes  or belts are often  used for continuous
skimming  of  surface  oil   from  separator tanks  or basins.    Simply allowing
gravity overflow  of  accumulated  oil may be the most  convenient way to remove
the free  product  from a  separator.   Oil-water separation technology is only
effective  for  separation  and  removal   of  free  organic  product,  emulsified
product, or dissolved product when concentrations are at or near saturation.

Oil-water separation  would not be  effective  for treating  the low concentra-
tions  of synthetic  organics found  in  the Firestone  Salinas ground  water.
Thus,  no further consideration  will' be given to  this treatment  method for
implementation at the Firestone Salinas site.

2.4.1.3  Flotation
Flotation is a technology that has been developed primarily for the separation
and concentration of mineral ores  (Berkowitz et al., 1978, pp.  535-536).  This
technology involves  the  controlled dispersion of a  fine air  stream through a
slurry.   The air bubbles  attach  themselves to suspended  solid particles (in
the case of mining, preferentially to ore particles).  The bubbles rise to the
surface  where  a  floe  forms.    A raking  device skims  the  surface  of the
flotation tank, removing the accumulated floe.  The floe is then collected for
further  processing  or disposal.    The aqueous  phase  is decanted,  disposed, or
recycled.  The process usually operates  in a continuous  mode.   Waste treatment
applications  have   included  cardboard  fiber  reclaiming,  municipal  sludge

FIR:0067-R8S2                         2-11

-------
                                                                Date:  8/22/89
                                                                Final Revision

thickening, and water  clarification.   This  technology is only  applicable to
the separation of  slurries (two phases).

Flotation would not  be effective in  treating the low  concentrations of dis-
solved synthetic  organics in  the  Firestone Salinas  ground  water.   Thus, no
further consideration will be  given to this treatment  method  for implementa-
tion at the Firestone Salinas site.

2.4.'l.4  Media Filtration
This technology involves  passing  a  contaminated waste  stream  through a fixed
(stationary) matrix (such as sand,  dolomite,  or fabric),  which provides rela-
tively uniform pores for physical  trapping or retention of a portion  (particu-
late  phase)  of the  waste stream.   Media filtration,  as referenced  in this
section,  applies to matrices  providing pore diameters greater than one micron.
Media filtration does  not include media  that have adsorpti've  capability such
as  activated  carbon,  zeolites, ion exchange resins, or  oil-adsorbing media.
Chemically active  or reactive media, such as stationary catalyst beds or fixed
stationary enzymes, are  also  excluded since their primary function is not to
provide a  barrier but  to perform  a  chemical  transformation.   Membrane-type
treatment technologies,  such  as reverse  osmosis, are also not included under
Media Filtration.    These methods are  referenced in  other sections (refer to
Section 2.4.1.7, Reverse  Osmosis; Section  2.4.1.8,  Dialysis;  Section 2.4.1.9,
Electrodialysis; Section 2.4.1.10,  Ultrafiltration).     Media  filtration is
only capable of removing contaminants greater than one micron in size.  This
technology is not  effective in removing Tiolecular contaminants such as synthe-
tic organics.

Media filtration would  be ineffective for treatment  or removal  of the chemi-
cals  found  in the  Firestone  Salinas  ground  water.   However,  the technology
could be appropriate  for pretreatment to remove  suspended solids, silts, and
clays that  may be  in  the ground water  pumped to the  surface.   No further
consideration will  be given  to  this  method  for implementation  as  a primary

FIR:0067-R8S2                         2-12

-------
                                                                Date:  8/22/89
                                                                Final Revision

treatment method  at  the Firestone  Salinas site.   Pretreatment  of Firestone
Salinas ground water  has not been required to date.  All extraction wells have
been thoroughly developed to minimize intrusion from suspended solids.

2.4.1.5  Absorption/Adsorption
The two  categories  of  absorption/adsorption  (Northwestern Carbon,  1988)  are
physical adsorption and chemlsorption.  These  two  processes will  be discussed
separately.
     *

These two processes will be discussed separately.

Physical Adsorption
Physical  adsorption  is  a   surface  phenomenon  involving  weak  van  der  Waals
forces, differing from  absorption,  which  by definition is penetration of one
substance into  the bulk of another  (Weist,  1975).   The forces  involved in
physical adsorption are similar to.  those  responsible for surface  tension in
liquids.   Physical  adsorption  as   referenced   in  this  section  takes  place
between a solid  adsorbent  and a liquid or  gas  containing, adsorbable species.
(Liquid-liquid  absorption   is  discussed   in  Section  2.4.1.13.)    Adsorbents
possess  a very   high  internal  surface  area  which  prov'des  the   sites  for
adsorption to take place (at the molecular level).   Adsorption is a reversible
process because of the  weak  van  der  Waals forces involved.  Adsorbents can be
regenerated  using solvents, steam,  heat,  or other methods  depending  on the
species that  is adsorbed.   There are many different useful adsorbents used in
chemical  processing  and  waste  treatment;  these  include acid-treated  clay,
activated alumina,  alumino  silicates,  bone char,   Fullers earth,  iron oxide,
magnesia, -silica gel, and carbon (Mark et al., 1985).  Clays are most commonly
used as  oil  adsorbents.  They are particularly  effective against free oil or
micro  emulsions,  for  which  activated  carbon would  be.  ineffective,  rapidly
depleted, or uneconomical.   Often clays are used as a pretreatment of the feed
to  a  carbon  system.    The  other adsorbents  listed  have  limited  use in waste
treatment applications, except  for  iron oxide.   The application of  iron oxide

FIR:0067-R8S2                         2-13

-------
                                                                Date.-  8/22/89
                                                                Final Revision

in  waste  treatment  is  discussed  in  more  detail  in-  Section* 2.4.2^5  under
Electrolytic Oxidation/Reduction.

Activated  carbon adsorption  is  the primary adsorbent used  in  waste treatment
today.  The following technologies  use activated carbon:
       •  Granular Activated Carbon Treatment (GAC)
       •  Powdered Activated  Carbon Treatment  PACT" (PACT"  1s  a  registered
          trademark of Zimpro Corporation).

These methods will be discussed individually.

Granular Activated Carbon Treatment
Carbonaceous, material such as coal, wood, coconut shells, or petroleum pitch,
when  subjected  to controlled  oxidation  (in  a kiln) under a  reducing  atmo-
sphere, can  be  "activated,"  producing a  high quality,  effective  adsorbent.
The  activation  process  serves  to  burn out  some of  the carbon, creating an
intricate  internal structure within the carbon matrix.  The internal structure
is characterized by  a very high internal  surface area.   High  grade activated
carbons have over  1,000  square meters of  Internal surface  area per gram.   An
in-depth discussion  of  the  concepts  of  activated  carbon  adsorption may be
found in Appendix D.

Granular  activated  carbon  treatment  is   one  of the  preferred  methods  for
economical removal of  low concentrations of  a  wide  variety of  small to medium
size  organic  molecules.    Larger molecules  (such as  oil) are  not  as  readily
adsorbed because  these molecules do not  fit well into  the  internal  pores of
the  activated  carbon (the pore  sites  being  where adsorption  occurs).   Small
molecules, however,  diffuse  readily  into  the pores and  are  held  by the weak,
attractive  van  der  Waals  forces.   Different  compounds  are adsorbed  more
readily than  others.   This  scale  depends on  a variety  of  factors including
molecular size,  structure,  the  carbon type  and  pore size,  and  the  heat  (or
energy) of adsorption.   The  heat of  adsorption is generally equivalent to.the

FIR:0067-R8S2                         2-14

-------
                                                                Date:  8/22/89
                                                                Final Revision

heat of  condensation (gas to  liquid phase  change)  of the  adsorbed species.
Experimentally measured adsorption capacities have been determined for various
compounds.  A  summary of the  test procedures to  determine  carbon adsorption
capacities and  a summary  of carbon  adsorption capacities  for a  variety of
chemicals are provided 1n Appendix E.

Granular  activated   carbon  treatment  1s  most  economical   for removing  low
concentrations of organics.  The  higher  the  Influent waste  concentration, the
more  quickly  the  carbon  is  exhausted.    Waste  streams  containing  organic
concentrations  up  to  100 ppm  can  be  economically  treated using  activated
carbon.  Streams up to 10,000 ppm can be economically treated, provided regen-
eration  of  the  carbon  in place  is possible.   Vapor-phase  solvent recovery
using activated  carbon  is  one  application where activated carbon  is used for
treatment of high concentrations of organics.  The activated carbon is usually
steam  regenerated  and  the solvent  recovered by  decanting  or distillation.
Vapor-phase organic  adsorption  on activated carbon  has to be carefully moni-
tored to prevent bed fires resulting from the heat evolved by adsorption.

Activated carbon treatment is  technically  appropriate for treating the ground
water  at the Firestone  Salinas site.    Carbon is especially well  suited for
removing  the very  low concentrations of chlorinated  organics  and  producing a
very  high purity effluent stream.   Further evaluation will be  performed on
this method in combination with other options in Section 3.0.

PACT*
Powdered  activated  carbon treatment is  a  process that uses  pulverized acti-
vated  carbon  in conjunction with biological  treatment  to produce  very  high
reductions of biological oxygen demand  (BOO) (99*) and chemical oxygen demand
(COD)  (9056).  PACT" reduces odor and toxicity and  improves effluent color  over
                           /
conventional  waste-treatment  processes  (Zlmpro,   1984).   PACT™ is  a process
licensed  to Zimpro Inc.
FIR:0067-R8S2                         2-15

-------
                                                                Date:  8/22/89
                                                                Final Revision

PACT™  treatment  involves addition  of powdered  carbon to  the effluent  of a
primary clarifier in  a  waste treatment plant.  The mix  is  sent to an aerated
basin where further biological action takes place and toxics are adsorbed onto
the carbon.  The effluent from  the  basin  flows to a secondary clarifier where
the  carbon  and sludge  are  settled  out  and  removed from  the bottom  of the
clarifier.   The  carbon  is  recovered,   regenerated,  and  sent  back to  the
clarifier.  Sludges are separated and  further treated  or disposed.  The over-
flow from the secondary clarifier 1s ready for discharge or may be filtered to
remove any trace carryover solids.  Carbon recovery is in the 80 to 90 percent
range.  The process is  effective  in  removing  low levels of industrial organic
wastes and solvents that find their  way  into  municipal  waste streams (Zimpro,
1984).

The process is  somewhat capital  intensive and is generally intended for large-
scale  waste-treatment  operations treating greater  than 1 million gallons of
wastewater per  day.

PACT"  technology  would  not  be  appropriate  for treatment  of the  Firestone
Salinas ground  water.   Since granular activated  carbon treatment  alone has
proved to be adequate, the capital cost for the additional combined biological
treatment capability provided by  PACT" would  not be justified (since biologi-
cal  treatment is only marginally  effective against  chlorinated organic hydro-
carbons).   Thus,  no  further consideration  will be  given to  this  treatment
method for implementation at the Firestone Salinas site.

Chemisorption
————	                     .                     5
Chemisorption is primarily an absorption process using chemicals,  solvents, or
chemically treated media to absorb materials from a waste stream.  The process
relies on solvation or  chemical  reaction  and  the formation of strong chemical
bonds  as  compared  to the weak  forces driving  physical  adsorption processes.
Chemisorption processes may  proceed by  adsorption  at the  surface   interface
then  absorbed  as  reactions  and  diffusion  into the  bulk  mass  takes  place.

FIR:0067-R8S2                         2-16

-------
                                                                Date:  8/22/89
                                                                Final Revision

Chemisorption processes  are  not as  easily reversed  as  physical  adsorption
processes, especially if the  bonds  formed are extremely  strong.   Examples of
Chemisorption in waste treatment are the  use of  limestone or sodium carbonate
to remove sulfur dioxide from stack  gases.  Anhydrous materials such as copper
sulfate or  concentrated  sulfuric acid are  used  as chemical  agents to remove
water  from  gas  streams.   In refinery  processing, alkanolamines are  used in
sour  gas  scrubbing  towers  to remove  carbon dioxide,  hydrogen  sulfide,  and
carbon disulfide from sour refinery  gas (Dow Chemical Company, 1980).

Chemisorption would be ineffective  in treatment  or removal of the chlorinated
organics  in  the  Firestone  ground water.  Chlorinated  organics are relatively
inert  and nonreactive.   Thus, no further consideration  will  be given to this
treatment method for implementation  at the Firestone Salinas site.

2.4.1.6  Gas-Phase Stripping
The  three  gas-phase  stripping   processes  that  have   application  to  waste
treatment are as follows:
       •  Air stripping
       •  Steam stripping
       •  Alternate gas stripping.

These  three processes are discussed  in the following subsections.

Air Stripping
Air stripping is a  commonly  used method  for removal of volatile organics from
water.   Air stripping,  similar  to  distillation,  is a  mass  transfer process
that  depends on  the  favorable   equilibrium  for  the  transfer  of  dissolved
volatile  components  from the  liquid into  the  gas phase.  A variety of differ-
ent methods can be  used  to  enhance the  mass  transfer rate  such as spraying
(spray ponds), aeration towers (with plates), or packed stripper columns.  The
purpose  of  spraying,   plates,   or  packing  is   to  enhance  mass transfer  by
providing  intimate  contact  between  the  air  and  liquid  (the  same function
FIR:0067-R8S2                         2-17

-------
                                                                Date:  8/22/89
                                                                Final Revision

plates  perform  in  a distillation  tower).   The  volatile  components  in  the
liquid will transfer to the gas phase, providing a continuous supply of fresh,
uncontaminated air is kept in contact with the liquid (Kavanaughy, 1980).

Packed  stripper  columns  have advantages  over  other  enhanced  air  stripping
methods.  Packed columns provide multiple  equilibrium  stages giving the high-
est mass  transfer  efficiency.  Forced  air draft 1n a stripper  column  can be
adjusted to  provide  the optimum a1r-liqu1d  ratios for removal  of particular
volatile chemical  species.   Packed  columns  can also be used  to perform pre-
treatment before another operation such as activated carbon adsorption.

The advantages of air stripping in waste treatment are the low treatment cost,
high efficiency  for  volatile organic removal,  simple  operation, and compact-
ness for treatment of large volumes.  Air strippers for ground-water treatment
                                                                     •
are most economical  in  locations  where direct  discharge  to' the atmosphere is
allowable.

Air stripping is  a treatment method that has been proven  efficient and cost
effective  in  removing  volatile organic contamination  in  ground water (Shukla
and Hicks, 1984).  The  removal of the chlorinated  organic  hydrocarbons in the
Firestone  Salinas  ground water by  air stripping  has  been  demonstrated  as a
very effective treatment method.   Air  stripping will  be  evaluated further in
Section 3.0 as a suitable treatment method for implementation of the Firestone
Salinas site.

Steam Stripping
Steam stripping is a waste  treatment method  using  saturated steam injected in
a liquid stream to remove volatile components.  The same general mass transfer
principles apply to steam stripping as for air stripping.

Steam  stripping  is confined  within closed  tanks  or columns  to control  heat
transfer losses.   A  closed tank with a steam sparger  will  serve as a sincle-

FIR:0067-R8S2                         2-18

-------
                                                                Date:  8/22/89
                                                                Final Revision

staged steam stripper.  Columns with  plates  or packing provide multiple equi-
librium stages greatly increasing efficiency.   The  primary advantage of steam
stripping  is  the operation  at higher  temperature  (of  the  saturated  steam)
increases  the  vapor pressure of  volatile organic contaminants  and decreases
the  solubility of  dissolved gases  in  the  liquid  phase.   In  addition,  pH
adjustment may be used  to further decrease  the  solubility of certain acid or
basic  gases  such   as  ammonia  or hydrogen  sulfide.    This  method  provides
extremely  high removal  efficiencies  for many organlcs,  Including  many which
are not easily removed by simple air stripping.

The  major  disadvantage of  steam  stripping  1s energy consumption.   The feed
must  be  preheated  to near the  temperature of the saturated  steam.   The high
heat  capacity of  aqueous solutions  becomes  a major  economic  concern  when
comparing energy and capital costs of competitive treatment processes.

Steam  stripping  would be effective  in  removing the  organic  contamination in
the  Firestone  Salinas ground water.   However,  1t  has  been demonstrated that
air stripping  is an effective treatment method.  The added cost of using steam
would  provide  no additional  benefit.  Thus,  no further consideration will be
given  to this treatment  method for  implementation  at  the  Firestone Salinas
site.

Alternate Gas  Stripping
Alternate  gas stripping  is  gas  phase  stripping of  waste-containing liquids
using  a  supplied gas other than  air  or  steam.  Gases used may include carbon
dioxide  or nitrogen.  This  method  of stripping might  be  used  when air would
form  flammable or  explosive mixtures with the waste material (thus requiring
an  inert atmosphere for  safety).   Use of an alternate gas for stripping might
also  be  appropriate when  the energy economics  of using steam  stripping prevent
its  use  as an inerting  agent  (steam is  an effective  oxygen  stripper).   An
inert  gas  may also  be  required when the  materials  involved  require inerting
but  are heat  or water  sensitive  (eliminating the  option  of  using steam).

FIR:0067-R8S2                         2-19

-------
                                                                Date:  8/22/89
                                                                Final Revision

Alternate gas  stripping  might be used  economically when  a  chemical reaction
with the gas aids stripping efficiency,  such  as using carbon dioxide to strip
and acidify a waste stream.

Alternate gas stripping would be effective  in removal of the organic contami-
nants in the Firestone Salinas ground water.   However, there is no additional
benefit to offset the added cost of  supplying an inert alternate gas.  Simple
air  stripping  has  proven safe  and effective for  removing the  chlorinated
organic  hydrocarbon  contamination.    Thus, no  further consideration  will  be
given to  this  treatment  method  for implementation  at the  Firestone Salinas
site.

2.4.1.7  Reverse Osmosis
Reverse osmosis  technology employs  a semipermeable membrane  to achieve ionic
size separations.  The membrane is maintained under a sizable pressure gradi-
ent  to   achieve  concentration  of  dissolved  organic  and inorganic species.
Influent is  pumped  to the reverse osmosis  unit at a  pressure  of  between 300
and 600 psi.  Flow is maintained tangential to the membrane surface by using a
tubular  configuration  to  support  the membrane.   As a result  of continuous
flushing (due  to tangential  flow),  the membrane  does not  become plugged  as
does a media filter (which has flow normal to the media).

Reverse  osmosis  treatment  generates  two  streams,   a  clean permeant and  a
concentrated reject  stream.   Reverse  osmosis  treatment  does  not  destroy  or
eliminate contaminants but concentrates them in the reject stream.   The reject
stream must then be further treated or disposed.  The generation of the reject
stream may be a drawback of implementing this treatment method.   Concentration
of the waste stream up to 75  percent is possible in one pass.  Multiple units
in series are able to further concentrate the waste stream; however, there are
limits  that affect  the  performance and   integrity  of  the reverse  osmosis
membrane.  Reverse osmosis can be used for producing very concentrated streams
when  combined  with  other technologies  such  as distillation.    The  reverse

FIR.-0067-R8S2                         2-20

-------
                                                                Date:  8/22/89
                                                                Final Revision

osmosis process  cannot tolerate  suspended  solids, requiring  pretreatment to
prevent  membrane  fouling  or  damage.    Membranes are   also  susceptible  to
chemical attack, fouling, and damage from other species including oil, grease,
iron  and  manganese  salts,  particulates,  and  bioorganics  (such   as  algae)
(Berkowitz  et al.,  1978,  page  834).  Volatile organics  may cause membrane
swelling and permanent damage to the reverse osmosis membranes.

Capital costs  are  high for large capacity  systems, the  major cost item being
the membranes  themselves.   Energy consumption  is  low  to moderate.   The major
energy requirement is  to drive the high  pressure  feed pump.   Reverse osmosis
is  more  economical  for concentrating  dilute  streams   than evaporation  or
distillation.

Reverse osmosis  is an unsuitable  treatment method for  the Firestone Salinas
ground water due to the potential membrane damage that may occur from treating
chlorinated synthetic  organics.   Thus,  no further  consideration  will be given
to this treatment method for implementation at the Firestone Salinas site.

2.4.1.8  Dialysis
Dialysis  is  another  membrane  separation  technology.   The  membranes used are
semipermeable, which  allow salts  and  small organic molecules to  pass freely
through  while higher  molecular  weight  species are  retained (concentrated).
The process relies on  simple  diffusion with the concentration gradient across
the membrane as  the driving force.

Dialysis  is  best suited for use  in  treatment  of concentrated solutions (5 to
20  percent).    Also,  the membranes  can  be  sensitive  to  solvents,  which may
cause  them to  swell  or degrade.   The best applications of  this method are for
purification  of caustic or  nonoxidizing acid  solutions  containing  low mole-
                           i
cular  weight  organics.   The  production rate  of  dialysis is  relatively low
compared  to other methods (Berkowitz et al., 1978, pp. 347  and 349).  Dialysis
generates  a concentrated reject  stream  that may require  further  handling or

FIR:0067-R8S2                         2-21

-------
                                                                Date:  8/22/89
                                                                Final Revision

Dialysis would be ineffective for treatment or removing the low concentrations
of organics in the  Firestone Salinas ground water.   Thus,  no further consid-
eration will  be  given  to  this treatment  method for  implementation at  the
Firestone Salinas site.

2.4.1.9  Electrodialysis
Electrodialysis uses  ion-exchange-type membranes  to separate  Ion-containing
solutions into dilute and concentrated streams by application of a dc electric
current across a selectively permeable membrane.   The membranes are permeable
to only one type of ion charge  (anions or  cations).   Application of a current
causes Ions to migrate toward the respective anode or cathode.  Blocked by the
selectively permeable membrane,  ionic  species concentrate on one  side  of the
membrane or the  other.   The  method  is totally ineffective  for nonionized or
noncharged species.   Also the most effective and productive operating range is
for  solutions  whose  ionic  concentration  is  between  200  and  5,000  ppm
(Berkowitz et  al., 1978, pp. 406-407).

Electrodialysis would  be  ineffective for  treating the low  concentrations of
organics in the  Firestone Salinas  ground water.   Thus,  no further considera-
tion will  be  given  to  this  treatment method for  Implementation  at the  Fire-
stone Salinas  site.

2.4.1.10  Ultrafiltration
This technology employs a porous membrane  that  behaves  similar to a fixed- or
stationary-media filter.  A pressure gradient of  10  to  100  psi is maintained
across  the membrane,  producing  a  concentrated  reject  and dilute  permeate
stream.   The  pore  sizes  of Ultrafiltration  membranes  are much  smaller than
typical  media-type   filters.    Ultrafiltration  membranes will  retain  large
molecules  (greater   than  1,000  molecular  weight),   colloids,  and  suspended
solids while  allowing  water molecules,  ions,  and small  organic  molecules to
FIR:0067-R8S2                         2-22

-------
                                                                Date:  8/22/89
                                                                Final Revision

pass through.  Membranes can be tailored to specific applications (pore sizes)
such as  removal  of viruses or  higher  molecular weight organics  in  the 10 to
1,000  Angstrom  range  (Berkowitz  et  al.,  1978,  page  899).    This  method
generates a concentrated waste  stream  that may  require additional handling or
treatment  (typical  of all membrane  separation  technologies).   The  membranes
are  generally not  restrictive  to  low  molecular  weight  organics, and  the
membranes may  be sensitive to  chlorinated synthetic  organic  solvents  (which
may cause swelling or degradation).

Ultrafiltration  would be  ineffective  for  treatment  or  removal  of the  low
levels of chlorinated organics  in  the  Firestone  Salinas  ground  water.   Thus,
no further consideration will be^given to  this  treatment  method for implemen-
tation at the Firestone Salinas site.

2.4.1.11  Freeze Processing
The  following methods  of freeze  processing may have  application  to waste
treatment:
       •  Freeze crystallization
       •  Freeze crying
       •  Suspension freezing
       •  Zone refining.

Each of these is discussed in the following subsections.

Freeze Crystallization
This  treatment  method relies  on  the  phase  change that  occurs  when mixtures
containing dissolved  solids are frozen.   The  crystals  that first  form  as a
solution  is  cooled are  pure relative  to  the  remaining  liquid.  These  pure
crystals  may  then be  removed  mechanically,  washed, and  recovered.   The
remaining  solution  is now  concentrated  with the undesired  impurities.   The
method  is  most  effective  for treating  solutions  containing a 1  to  10  percent
concentration of  dissolved  species.   The only  commercial  application  of this
technology is for producing fresh water from salt water.

FIR:0067-R8S2                         2-23

-------
                                                                Date:  8/22/89
                                                                Final Revision

The disadvantages of  this method are high  energy  consumption (as a result of
requiring refrigeration),  removing,  washing,  and handling the frozen product,
and the  high  concentration range required  to  be effective (Berkowitz et al.,
1978, pp. 552-553).

Freeze crystallization would be Ineffective for treating the low^level organic
contamination  in  the  Firestone  Salinas  ground  water.   Thus,  no  further
consideration will be given to this treatment method for implementation at the
Firestone Salinas site*

Freeze Drying
Freeze  drying is  a  process  for removing  water  and  volatiles  from aqueous
mixtures containing solids or dissolved solids.  The process involves freezing
the mixture,  then pulling a high vacuum to sublime the water  and remove any
volatiles.  The remaining  solid material  is essentially dry without having to
be subjected to any heat.  This method may have value in dewatering chemically
sensitive materials.    This  process  is  used  commercially to  produce  freeze
dried coffee and other  dried foodstuffs.   Avoiding the use of heat to recover
food products prevents  thermal  degradation and  preserves  flavor.   The freeze
drying process might  be applied to  the  dewatering sludges; however, the added
cost of  providing  the  necessary refrigeration  usually  prevents  its  use  in
favor of other more economical  methods.

Freeze drying would not be a cost-effective treatment method for the Firestone
Salinas  ground  water.  Thus,  no  further consideration will  be  given to this
treatment method for  the implementation at the Firestone Salinas site.

Suspension Freezing
It has  been  observed  that the freezing  and thawing  of  some sludges and gela-
tinous  materials  aid  in  the  agglomeration  and separation  of  solids.   The
freezing  causes  suspended solids to  floe,  and when thawing  occurs,  the floe
separates from  the solution.   The  effect  is believed  to be as  a  result  of

FIR:0067-R8S2                         2-24

-------
                                                                Date:  8/22/89
                                                                Final Revision

pressure exerted on  sludge  particles by the formation  of ice crystals.  This
treatment has been  found  to be effective on all  types  of municipal treatment
plant  sludges.    However,  this process  has  only been  demonstrated  in  the
laboratory.    The  requirement  for  refrigeration  would  probably  make  it
competitive  only  in  climates  where  winter  temperatures  provide  natural
refrigeration.

Suspension freezing would not..be an  effective  method  for treatment or removal
of dissolved organlcs  1n  the  Firestone  Salinas ground water.   The process has
only  been  demonstrated effective  for  the  separation  of sludges.   Thus,  no
further consideration  will  be given to this treatment  method for implementa-
tion at the Firestone Salinas site.

Zone Refining
Zone  refining  is  a melt/refreeze method  used  to produce ultrapure metals,
inorganics,  and  organic  materials.    It  is  costly  and  only  suitable  for
treatment  of  small batches  of material.   The principal of  zone refining  .is
phase equilibrium,  similar  to  freeze  crystallization  or distillation.  When a
melted mixture cools, the crystals that form have a composition different from
the  original  mixture.   The  solid  phase is enriched with the  less volatile
components, opposite  of distillation where  the  vapor  phase  is  enriched with
the more volatile  components.   The process  is  usually applied to  already pure
materials.   A rod  of  material  is passed through  a  heater (usually  inductive
heating for metals).  The heater melts a small portion or zone in  the rod.  As
the  rod  is moved  forward through  the heater,  the molten zone moves down the
length  of  the rod.   The impurities  tend to  stay in  and  be carried  by the
molten  zone.   Repeating the process  a  number  of times  results in the produc-
tion  of  an ultrapure rod.  This technique  has use in the high technology and
semiconductor  industries  where ultrapure materials are required  and the cost
is  justified.   There are no  viable  applications for  waste or hazardous waste
treatment due to the economics  (Berkowitz et al.,  1978, pp. 910-916).
FIR:0067-R8S2                         2-25

-------
                                                                Date:  8/22/89
                                                                Final Revision

Zone refining  is  not  applicable to  waste  treatment  or ground-water  treat-
ment.   Thus,  no  further consideration  will  be  given  to  this method  for
implementation at the Firestone Salinas site.

2.4.1.12  Distillation
Distillation is a well known technology for separating mixtures of pure liqu.id
components.   The  method  relies on  the  difference  1n  volatilities of  the
components  of  a mixture  and  the  equilibrium  those  components reach  in  the
vapor phase at varying  temperatures.   Heating a mixture enriches  the  vapor
phase with  the more volatile component.   Condensing this  vapor phase produces
a volatile-rich liquid.   Repeating this process 1n a multlstaged distillation
column  allows  for  separation  of  components  that  may  have  only  slight
differences  in  boiling  point  (although  this  may  require  a large  number of
equilibrium  stages).   Distillation is best  suited when concentration  of  the
feed to a nominal purity is acceptable.  Production of ultrapure distillate or
highly  concentrated  bottom material may  require  several  hundred equilibrium
stages, high reflux rates  and large columns.   This results in  high capital
cost and  high energy  consumption when  large  feed volumes must  be handled.
Also, distillation of aqueous  solutions 1s especially  energy intensive due to
the high heat capacity of water.

Distillation would be  effective but  uneconomical  for treatment  of  the  low
concentrations of  organics in the Firestone Salinas ground water.   Thus, no
further consideration will  be  given  to this treatment  method  for implementa-
tion at the  Firestone Salinas Site.

2.4.1.13  Extraction
The  following  five  types of  extraction  methods  have  application  to  waste
treatment:
        •  Liquid-liquid extraction (referred to as  solvent extraction)
        •  Liquid-solid extraction (referred to  as leaching)
FIR:0067-R8S2                         2-26

-------
                                                                Date:  8/22/89
                                                                Final Revision

       •  Liquified gas extraction
       •  Supercritical fluid  extraction  (referred to  as  supercritical fluid
          oxidation)
       •  Gas-11quid extraction (referred to as stripping).

The first  three of  these methods are  discussed  1n  more  detail below.   The
latter  two of  these  methods  are discussed  In  Sections  2.4.1.6,  Gas-Phase
Stripping, and,2.4.2.4, Oxidation.

Liquid-L1qu1d/Solvent Extraction
Solvent  extraction technology uses  an  immiscible  solvent in contact  with a
second  .olvent  containing a dissolved  species  (solute) that  is  to  be recov-
ered.   An immiscible  solvent  is  selected that  has a great  affinity  for the
solute.    Intimate  contact  induced  by  vigorous  agitation or in  a  designed,
staged contactor allows for the transfer of the solute from one solvent to the
other  based  on  favorable  equilibrium.    After  contact,  the two   immiscible
solvent phases  separate,  allowing  for recovery  of the solute and either reuse
or  disposal  of  both  solvents.   The  major  advantage  of this  method is that,
with  the  proper  choice  of an extraction solvent,  only  a  relatively small
volume  of  extraction  solvent  is  required to  recover the solute  from a very
large  volume of  influent.    This process can  be significantly  more energy
efficient  than  direct recovery  by  methods  such as  distillation.   Proper
application of  solvent extraction technology concentrates  the  solute, often by
orders of  magnitude, with very low energy expenditure.

The major  inherent problem  with this  technology for environmental applications
is  finding an extraction  solvent  that is not in  itself environmentally sensi-
tive.   Organic  solvents  that  are  immiscible with water are all slightly water
soluble  to some degree.   TJus contamination may make return of treated ground
water   or   wastewater  to  the   environment   impossible  without   additional
treatment.
FIR:0067-R8S2                         2-27

-------
                                                                Date:  8/22/89
                                                                Final Revision

The potential*  environmental  concerns  associated with liquid-liquid extraction
and the availability  of much more acceptable  and  effective technologies make
this method unsuitable to treat the low levels of organic contamination in the
Firestone Salinas ground water.   Thus,  no further consideration will be given
to this treatment method for Implementation at the Firestone Salinas site.

Liquid-Solid Extraction/Leaching                            .
The two  types  of  leaching  mechanisms  are  so1vat1on  and  chemical  reaction.
Since  these two  methods  are  applied  identically,  they  will  be  discussed
together.

The following are the four types of leaching processes:
       •  Batch
       •  Continuous
       •  Heap or pile
       •  In situ (solution mining).

All these processes involve contacting a liquid with a solid,  resulting in the
selective removal of  a portion of the  solid  material,  either by solvation or
chemical reaction.

To differentiate between solvation  leaching  and chemical  leaching, an example
of each is  given.   The leaching of coffee with water is an example of solvent
leaching.   Certain coffee  solids  and  oils  are  solvated  (dissolved)  by the
water, producing the  extracted  cup  of coffee.   Alternatively, the leaching of
gold  from  ore  using  mercury  metal  is  an  example  of chemical  leaching.   The
mercury chemically  reacts  with the pure gold  particles  in  the ore to form an
amalgam.

There are many  different arrangements of  batch and continuous leaching equip-
ment, processes,  and  vessels.   Leaching may  be'performed  in  a single tank or
vessel with an  agitator to  mix the solids and leaching liquids.  A continuous
multi-staged extraction system may be used to  increase efficiency and yield by

FIR:0067-R8S2                         2-28

-------
                                                                Date:  8/22/89
                                                                Final Revision

providing  multiple  recovery  stages,   reflex  of  leachate  liquid,  filters,
settlers,  etc.    Extraction,  being  an  equilibrium  process,  is governed  by
fundamental  mass-transfer  principles,  the  same  as  distillation  and  air
stripping.

Heap  leaching  is a  common method used  in mining.   Large mounds of  ore are
placed  on an impervious  surface such  as  clay, a  concrete slab, or  plastic
lining.   Leaching liquid  sprayed on  the  mound percolates through  the solid
mass.   The  enriched leachate  is recovered at  the bottom  of the  mound and
processed to recover the desirable material.  This method 1s sometimes used in
waste  treatment  to  treat  contaminated soils.  An  example of  heap leaching is
the  treatment  of cyanide-leached ore  piles  (formerly  leached  for gold and
silver) which  have  been left  with  residual cyanide.   Solutions of oxidizing
agents  are sprayed  on  the  contaminated mound, chemically  leaching  out the
cyanide  as cyanate  or  allowing  the reaction  to go to completion,  producing
carbon dioxide.

In  situ  leaching is  generally  referred  to  as solution  mining.    Leaching
liquids  are pumped  underground  into  an  ore  body.   The  desirable material
dissolves or reacts with the liquid.  A  second recovery well allows the leach-
ing  liquid  to  return to the surface where it  can  be processed to recover the
leached material.

The  advantage  of solution mining is  avoiding  the cost  and  hazards involved
with  underground mining.    The disadvantages are  environmental  concerns over
injecting  liquids into  the ground water and insoluble  contaminants  in the ore
body,  which  may  decrease  the yield of  the leaching  process.   These insoluble
contaminants  can become  a  significant barrier  to  mass  transfer  when  they
accumulate.  Potential  waste treatment applications  might involve the removal
of  ,metals  or  organics from  sludges  or   soil  using  an  appropriate  liquid
extractant.
FIR:0067-R8S2                         2-29

-------
                                                                Date:  8/22/89
                                                                Final Revision

Liquid-solid extraction  would  not be effective  for treating or  removing the
dissolved organic contamination in the  Firestone  Salinas  ground water.   Thus,
no  future  consideration will  be  given  to  this  treatment  technology  for
implementation at the Firestone Salinas site.

Liquified Gas Extraction
Liquified gas extraction (LGE) is a  process  that  can  be effective 1n removing
organics  from  liquid waste  streams.   The  principles are similar  to liquid-
liquid  extraction except  the  solvent  is  a  gas  liquified  under  pressure.
Liquified gases such as carbon dioxide and propane have the ability to extract
many  organics.    Liquified  gas extraction  1s usually  carried  out  in  multi-
staged columns  providing high  extraction efficiencies.   The  process operates
based on  the equilibrium between  the solute  and  liquified gas solvent.   It is
controlled by mass-transfer principles similar to distillation,  air stripping,
and liquid-liquid extraction.  Extraction using a liquified  gas generates two
waste streams,  an organic  fraction  (dissolved in  the liquified gas)  and an
inorganic fraction usually consisting of  solids,  salts,  and  water.   These two
streams  are  immiscible.   The  organic  dissolved  by the liquified  gas  can be
recovered by  separating  the phases,  then  relieving the  pressure on the gas.'
The  liquified  gas,  usually having  a  substantial  vapor  pressure  difference
compared to the dissolved organics,  flashes off,  leaving the extracted organic
contaminants  behind.    The   gas  can  be collected,  recompressed,   and  reused
(Hazardous Material Control, 1988).

This process may have energy advantages over nonpressurized solvent extraction
processes.   The energy required  to  recompress the gas  may  be  less  than the
energy necessary to distill  off solvent,  as  might be  required by conventional
liquid-liquid extraction processes to recover the extracted organic.  However,
this  economic advantage  may be offset  due to  the added  capital  cost of pres-
surized vessels and a compressor.
FIR-.0067-R8S2                         2-30

-------
                                                                 Date:   8/22/89
                                                                 Final  Revision

 Liquified  gas extraction could  probably be  effective  in  treating the Firestone
 Salinas  ground  water.    However,  this  method  would be  capital intensive  to
 implement   as a  treatment  method  for removing  the  organic  contamination.
 Development  and  testing would  be  required  to  verify  the  suitability of  a
 liquified  gas extraction  solvent and  determine  proper operating  conditions.
 Also,  gas, liquid  extraction  (air  stripping)  has   been  demonstrated  as  an
 effective   and  economical  treatment  method.    The developmental  expense  and
 greater  capital  costs in Liquified Gas Extraction are not  justified.  Thus,  no
 further    consideration   will   be  given  to   this   treatment  method   for
 implementation at the Firestone Salinas site.

 2.4.1.14  Mechanical  Separation/Treatment
 Mechanical separation  is  the  separation  of  materials  using  mechanical-type
 equipment.   The  following  are  the most common mechanical units  used  in waste
 treatment:
        •  Centrifuges
        •  Belt filter presses
        •  Air classifiers
        •  Vibrating screens
        •  Shredders/grinders
        •  HydrocTones.

 Each of  these is discussed  in the following subsections.

 Centrifuges
•The settling out  of  solids in  a tank.or basin due to gravity .is a  well knc^n
 occurrence.   Often settling occurs in  chemical  processing, and agitation  is
 required to  keep solids  in  suspension  or a mixture  homogeneous.  The opposite
 situation  can also be  a problem when  suspended  solids are  so  fine  or. emulsi-
 fied that  normal gravitational  force has no effect on settling them out.

 Mechanical centrifuges can  increase the apparent  force  on  solids in suspension
 up  to 300,000  times  normal  gravitational  force  (g)  depending on  the  type  of


 FIR:0067-R8S2      •                   2-31

-------
                                                                Date:  8/22/89
                                                                Final Revision

centrifuge.  Centrifuges may operate  in  batch  or continuous mode depending on
the design.  The  centrifuges that produce the  highest  g  forces (greater than
about 15,000g) are  generally batch type and only  suited  for pilot or labora-
tory operations.

The most widely used centrifuge  in waste treatment is. the continuous decanter
centrifuge operating in  the  range of 2,000 to  5,000g  (Moir,  1988).   The unit
has a rotating outer  bowl  with an inner backdrive scroll  (similar to a screw
feeder).   The  slurry  is  fed up the hollow shaft  of the scroll, which rotates
at  a  faster speed  than  the bowl.   The feed moves through the ports  on  the
shaft into .the bowl,  where the solids form a layer.  The  liquid depth in  the
bowl is controlled  by  adjustment of ports at  the  liquid  discharge (centrate)
end of  the unit.    Solids  are  conveyed  away from the  liquid end  of  the cen-
trifuge by the scroll  (hence  the name  backdrive).   They are  drawn  into  the
conical  end  of the bowl and discharged  at  the opposite end  from  the liquid.
Polymers are frequently  added  to enhance separation and  produce a drier caKe
(Moir,  1988).   Continuous  centrifuges  are  only suitable  for  treating wastes
containing contaminants greater than one micron in size.

A centrifuge would  not be  effective for  the treatment  or  removal  of the low-
level organic  contamination  in the Firestone Salinas ground  water.   Thus, no
future consideration will be given to this treatment method for imp lamentation
at the Firestone Salinas site.

Belt Filter Press
The belt  filter  press is  a  mechanical  unit which.uses two continuous porous
belts to dewater  fibrous organic solids  in the  1- to  2-percent solids ringe.
The two belts  run. in  a  continuous loop  over  a series of  rollers.   The waste
liquid  is   introduced  onto  one  belt,  which  allows  free  water  to  drain  by
gravity.  The waste then travels on the top belt to a point where the'top belt
meets the  bottom  belt  at a  point  called the  wedge zone.    The  two belts move
together in a wedge-shape configuration, applying greater and greater presses

FIR:0067-R8S2                         2-32

-------
                                                                Date:  8/22/89
                                                                Final Revision

to the waste  solid  (removing more and more  water)  trapped between the belts.
The  two  belts  then  move  to  the pressure  zone over  and  around  a  series of
hydraulic rollers  where the  pressure on the waste  between the  two  belts is
highest (up to  100 psi).   After the  pressure zone, the two belts  separate and
the dry solids  drop  by  gravity  into  a bin or onto a conveyor belt for loading
or disposal.

Applications  of a  belt  filter press  to  waste  treatment include dewatering of
municipal waste  sludge  and  reclaiming of waste  cardboard fiber.   Polymers are
often added to  coagulate the  waste,  improve removal  efficiency, and produce a
drier cake.   This treatment  method  is  effective  for  removing  solids greater
than 500 microns (Deutsch,  1987).

A belt filter press  would  be ineffective  in treatment or  removal of the  low-
level  synthetic organics  in  the  Firestone Salinas ground  water.   Thus, nc
further   consideration   will   be   given    to   this   treatment   method   for
implementation  at the Firestone Salinas  site.

Air Classifiers
Air  classifiers are  devices  that  separate  solid materials based  on  size. -A.
number of forces act on particles carried  by  an air stream,  such as gravity,
drag,  and  centrifugal  force  (if  the air stream  and  particles  are rotating).
The  simplest  form of  an  air classifier is a  cyclone  separator  that simply
removes  particulates from gas  streams.    The particulate-laden  gas  stream
enters the  cyclone  chamber.  The  chamber  is a  cylindrical vessel with a  cone
bottom.  The  gas stream is directed  tangentally along the cylindrical surface
causing the gas to  spin around  the cylinder.   The particles are moved outward
as a result of  centrifugal  force.   Particulates begin to  fall  as  gravity  acts
upon them.  When they fall  near the  bottom,  they enter the cone portion of the
                           i
chamber.   The  decreasing   diameter  of  the  cone accelerates the  air stream,
increasing the  centrifugal  force  on  particulates and increasing the air pres-
sure in  the  bottom of  the  cone.   The particulates  fall  out the bottom of the

FIR:0067-R8S2                          2-33

-------
                                                                Date:  8/22/39
                                                                Final Revision

cyclone (carried by a small  amount  of  gas).   The cleaned gas exits the top of
the cyclone  through  a  large center exhaust nozzle  (due  to lower air pressure
at the top  of  the  cyclone).  This process is  limited  to  removal  of medium to
large particulates.  Small particulates are entrained in the gas phase and are
carried out the top of the cyclone.

Air-classifiers make use  of drag on a particle  in  a gas  stream as a function
of surface area, volume,  density, and  gravity  to separate (classify) particu-
lates and solids by size.   There are numerous  commercial  air classifying units
available varying  in design  and  configuration  (Klumpar  et al.,  1986).   Air
classifiers are useful for  grading  solid  feeds or products by size, which may
be critical  to the efficiency of a chemical  process or  the  sale  of manufac-
tured materials.  The details of the many available commercial air classifica-
tion units  will not be  discussed  further  for the  purpose of brevity.   The
primary  application-  of  this  technology  to  waste  treatment  is  dust  or
particulate removal from process gas streams or stack emissions.

Air classification would  not  be effective  for  the treatment or removal of the
dissolved organic  contamination  in  the Firestone Salinas  ground  water.  Thus,
no further consideration  will be  given to  this method  for treatment of ground
water at Firestone Salinas.

Vibrating Screens'
This method  is  used  to classify  dry solids by  size or separate water frcm wet
solids using gravity.  A  descending  order  series of large surface area screen
trays, each with a different size opening, are fed a dry solid stream or a wei
slurry.    The   stream  cascades  down  through  the  series  of  screens,  being
rejected off  a side opening  in  the screen tray  if the  particle  size is tec
large  to pass further.    Sorted  reject  particles are  collected  by  screen
size.   Each size  collected  actually  is  representative  of  a range  of  sizes
based  on  the  individual  screen  characteristics, ranges,  and openings.   The
screens are energetically vibrated to keep the particles in motion and prevent
plugging.
FIR:0067-R8S2                         2-34

-------
                                                                Date:  8/22/89
                                                                Final Revision

Vibrating screens are only  effective  for  participate removal,  classification,
or  recovery.   A  vibrating screen  would  not  be effective  for  treatment  or
removal of  dissolved  organic  contaminants as  found in the  Firestone  Salinas
ground water.  Thus, no  further  consideration  will  be given to this treatment
method for implementation at the Firestone Salinas site.

Shredders/Gri nders
Shredders, grinders, mazorators, choppers, and  a  host of  other units are used
to  precondition   waste  streams  to enhance  treatment  or  simplify  disposal.
Large solids are a problem for many processes.   Plugging of pipelines,  agglom-
eration, and overloading  or jamming equipment  are  all  problems  associated  by
oversized or  poorly conditioned feed.   Sanitary treatment  plants  frequently
grind all influent feed to prevent line plugging and enhance biological degra-
dation of solids  by maximizing surface area.   Wood, brush,  leaves,  and trash
are often chipped or shredded  at  sanitary landfills to enhance compaction and
biological degradation of waste- materials.   Trash or tires are often shredded
prior  to  burning in  incinerators  so  a uniform feed  is  provided  and  process
control problems  are  minimized.   Coal is pulverized to a uniform fine powder
for feed  to  power plant boilers.   Automobiles,  appliances,  and other  objects
are often  shredded  at  reclaim sites  to  aid the magnetic  separation  of iron
from other materials.

Shredders or grinders would not provide any benefit  toward the conditioning cf
contaminated ground water  at  Firestone  Salinas  for treatment or  removal  cf
dissolved organic contamination.  Thus, no further consideration will be a-1 ve-
to  this pretreatment method for implementation at the Firestone Salinas site.

Hydroclones               •
Hydroclones  are   liquid-phase  versions  of   cyclone  separators.   The  vessel
design  and  configuration  is  very  similar  and  the 'functional mechanics  and
process  are  the  same.   A liquid feed containing suspended  solids  enters the
hydroclone.  As in  a cyclone, the feed is directed tangentially to the outsice

FIR:0067-R8S2                         2-35

-------
                                                                Date:  8/22/89
                                                                Final Revision

of the hydroclone cylinder wall.  The spinning of the liquid around the hydro-
clone causes  solids  to move outward  as a result  of centrifugal  force.   The
solids drop downward  as  a result of gravity.   Solids  concentrate in the cone
bottom,  and  are discharged out  the  bottom as  a  slurry.   Clear  liquid  exits
overhead.    The disadvantage of hydroclone treatment  is  due  to  entrainment.
Only medium  to large particles  are  rerroved.   Also, the  collected solids are
still very wet and require further drying before disposal.  The primary advan-
tage  is cost.   It is a.very cheap  separation method, requiring  only energy
from pumping the fluid through  the unit.   Variations on hydroclones allow for
size classification of the solids, similar to gas-phase air classifiers.

Hydroclones are suitable  for particulate phase removal only.   The technology
would not  be  effective  in treatment  or removal  of  the dissolved  organic
contamination  found  in the  Firestone Salinas ground water.   Thus, no further
consideration will be given to  this treatment method for implementation at the
Firestone  Salinas site.

2.4.1.15  Magnetic Separation
This  treatment method is suitable  for separation of  paramagnetic materials.
The  two magnetic  processes having  potential  applications in  waste treatment
are  magnetic  conditioning  and  high gradient  magnetic separation.    Each  of
these is discussed in the following subsections.

Magnetic Conditioning            .                                         :
This  method  is primarily used  for gross  removal  of  tramp  iron  from a wice
variety of  processes.    It  has  application  to  mining,  metal  reclaiming,
chemical processing,  and  other  process where  free iron needs  to  be removed.
Magnetic conditioning is used to protect conveyor belts or sorting areas  where
materials   pass  by.    Powerful magnets  are suspended to attract  any free iron
contaminants or  objects  such as tools, nails, steel  objects, etc.   This  is
usually done  to  reclaim  the   objects or  prevent  damage further down  the
processing line to other units  (such as rock  crushers).

FIR:0067-R8S2              -          2-36

-------
                                                                Date:  8/22/89
                                                                Final Revision
Large electromagnetic cranes  are used  in  salvage  yards to  scavage  free iron
from other shredded materials such as plastic or rubber.

Magnetic conditioning would be totally ineffective  in removing or treating the
dissolved organic contaminants  in  the Firestone Salinas ground  water.   Thus,
no further consideration will be given  to  this  treatment  method for implemen-
tation at the Firestone Salinas site.

High-Gradient Magnetic Separation
This  treatment  method  uses  very  high  intensity  magnetic  fields  to  affect
separations based on ferromagnetic, paramagnetic, or diamagnetic properties of
the component elements.  All  but  16  elements  exhibit one  of these three prop-
erties.   The high-grade magnetic  separation process  (HGMS) requires  a high
energy  electromagnetic  source  and  a  ferromagnetic  filament,  which  may  be
felted  or woven  steel-wool  expanded  metal,  or  some  similar  type of  iron
material providing a high  void  space.   Magnetic fields  up to 20,000 Gauss are
necessary for treatment to be effective.  The  waste  stream is passed through
the ferromagnetic filament  filter.   Under  applied  magnetic fields, impurities
are  collected  in  the  filter  due  to magnetic  attraction.   When the  filter
becomes  loaded,   the magnetic  field  is  turned  off  and  the  filter  fabric
decontaminated.    HGMS  is   effective in removing  particles  as  small  as  one
micron.

Various  configurations  are  possible  to  allow  for  cyclic  or  continuous
operation.   Superconductivity magnets  show  promise by providing  even  higre-
magnetic  fields.   There  are many potential applications  for this technology,
but most  are in  the  developmental  stage.   Iron ore  concentration using HGMS
technology has  been commercially  demonstrated.   Other possible applications
include water treatment and  other  types of pollution control.  The method can
be effective in removing nonmagnetic species, providing they can be trasoec in
an iron matrix such as iron oxide (Klumpar et al.,  1986).
FIR:0067-R8S2                         2-37

-------
                                                                Date:  8/22/89
                                                                Final Revision1

High-gradient magnetic  separation,  being relatively undemonstrated  for waste
treatment, may not  be  appropriate  for removal or  treatment  of the contamina-
tion in the ground water at Firestone Salinas.  Thus, no further consideration
will be  given to  this  treatment method  for implementation at  the  Firestone
Salinas site.

2.4.1.16  Evaporation/Crystal!ization/Drying
Evaporation, crystallization, and drying operations will each be considered in
this section.  These operations  involve  the  controlled  application of heat to
drive  off  volatile  materials.     For   the purposes   of   this  discussion,
evaporation,  crystallization,  and  drying do not  involve  chemical  reaction
(other than phase  changes)  or thermal degradation of the materials  involved.
Thermal degradation  processes for  waste materials  are discussed  in  Section
2.4.4 under "Thermal Treatment."   Evaporation, crystallization, and drying are
similar operations except for the extent  to  which  the  heating  is carried out.
Evaporation, crystallization, and  drying are equilibrium processes  operating
based  on  mass-transfer  principles  and the different volatilities  of chemical
species.

Evaporation is applying heat for the purpose of  concentrating liquids that may
be pure,  solutions,  suspensions,  or emulsions.   Evaporation may also be used
to remove  a particular volatile component  in a liquid  (Wiegard,  1973).   The
applications and variations of evaporator design are quite  numerous, and will
net be  discussed  in  detail.   Evaporation is  used  in many chemical processing
operations,  for   solvent  recovery,   food  processing,  and  water  purification
(from  brine).  Evaporation may be  induced by direct  or  indirect heating or by
the  sun  (solar evaporation  which  is usually carried  out  in  outdoor  shallow
ponds with large surface areas).

Crystallization  is  an  evaporation-type  process;  however,  the  goal  is  to
recover dissolved  solids  instead of a concentrated  liquid.   By continuing tc
apply  heat, evaporating the  solvent  until the saturation point of the solvent

FIR:0067-R8S2                         2-38

-------
                                                                Date:   8/22/89
                                                                Final  Revision
is reached, precipitation of dissolved  solids  will  occur.   Careful  control of
this process yields crystals of the dissolved product, which can be recovered.
These crystals may be dry or slightly  wet,  or even slurried, depending on the
design of the crystallization process.

Drying is  a  process  which  produces solvent-free crystals  from  either a satu-
rated solution or  a  feed stream of moist or slurried crystals.   Dryers apply
sufficient heat to drive off all free solvent.

For  brevity,  the  discussion  of the  many  designs  for  evaporators,  crystal -
lizers, and  driers will  be  omitted.   Further  information  is given  in the 6th
edition of Chemical Engineers Handbook.

Evaporation, crystallization,  and  drying  are suitable processes for treating,
concentrating, or  removing  a wide  variety  of contaminants  in  waste  streams.
These  include  heavy  metals, radioactive materials,  inorganic  salts,  and many
types of  organics  (including  halogenated organics).   The  wastes may  be aque-
ous, nonaqueous, liquid, slurries, sludges, tars, or  solids  (Berkowitz et al.,
1978, pp. 466-467). The economics are usually  limited by energy consumption.

Evaporation, crystallization,  and  drying would  not be cost-effective methods
for  removal  of  the  low levels  of organic  contamination  in  the  Firestone
Salinas  ground  water  due  to  high energy consumption.    Thus,  no  further
consideration will be given to this treatment  method  for implementation at the
Firestone Salinas site.

2.4.2  Chemical Treatment Methods

2.4.2.1  Neutralization
This treatment method is generally applied  to  the treatment  of acidic or basic
solutions  of  gases,  salts,  buffers, or organics.   The method uses controlled
addition of  an  acid  or  base to a solution  to  either  raise or lower pH to meet

FIR:0067-R8S2                •          2-39

-------
                                                                Date:  8/22/89
                                                                Final Revis.ion

a particular requirement  (e.g., permit  limit),  or to achieve the formation of
a precipitate  such  as  an oxide or hydroxide  (see precipitation).   Gases such
as sulfur dioxide, carbon dioxide, or  ammonia can be used as sources of acids
or bases  (once in solution).   Also  solids  such  as lime,  sodium hydroxide, or
sodium bisulfite  are a convenient form of  neutralizing agent.   Organic acids
or bases  may  be used  but are  not usually economical on  an  industrial  scale.
This treatment method is most appropriate for acid waste or basic waste in the
pH range of 0 to 14 and for removal of certain metal ions  (see precipitation).
Treatment of highly concentrated acids or bases (outside the 0 to 14 pH range)
can be acccomplished by neutralization, but requires large amounts of chemical
agents and  a  means to  remove  the excess heat generated.   Neutralization (pH
adjustment) will  also   aid  in  the separation of  some  concentrated oil-water
mixtures  (at  or  near  saturation) and  breaking  of emulsions  (see oil-water
separation).  Control of chemical  addition is essential  to prevent the genera-
tion of undesirable species (such  as nitrogen trichloride)  and overshooting a
neutralization point.   Possible chemical  side  reactions  have  to  be reviewed
before implementing  a   neutralization  process to  avoid producing undesirable
side products. -Approximately 15 to 20 minutes residence time is necessary for
neutralization  reactions to  reach  complete  equilibrium.   This  often makes
precise control  of addition rates  difficult, especially when  adjusting near
neutral pH.

Neutralization- would   not  be  effective  in  the  treatment or  removal  of  low
concentrations  of  dissolved synthetic  chlorinated  organics  as found  in  the
Firestone  Salinas  ground  water.     However,  neutralization  is  used  at  the
Firestone  Salinas  site  to  adjust the pH  of  the  treatment  plant  effluent to
comply with the NPDES discharge requirements.

2.4.2.2  Precipitation
The  two  types  of  precipitation  discussed  in  this section  are  liquid-solid
precipitation, and electrostatic precipitation.  Each of these  is discussed in
the following  subsections.  .

FIR:0067-R8S2    '                    2-40

-------
                                                                Date:  8/22/89
                                                                Final Revision
Liquid-Solid Precipitation
This technology removes a contaminant by creating a second phase that can then
be removed or recovered.   Several  methods  can be used to induce precipitation
in a solution.  Addition of a chemical that will react with a species in solu-
tion to  form  an insoluble product is  an effective  way to force precipitation
to occur.  Materials such as hydrogen sulfide or sodium sulfide, when added to
solutions  containing  heavy metals,  will  cause precipitates  in  the  form  of
insoluble metal sulfides  to drop  out of the solution.  The solubility of most
metal sulfides  (in water) is  extremely low.   Precipitating  heavy metals and
removing the  precipitate  by media filtration methods reduce the environmental
toxicity of  the remaining  solution.   Chemical  addition  may also  be  used  to
cause a  shift in  the equilibrium, resulting  in precipitation or coalescence.
This often occurs as a result of simple pH adjustment.

Temperature change  is  also used  to achieve precipitation.  Cooling a solution
lowers  the solubility  of a  dissolved  species, ultimately  to the  point  of
saturation and  precipitation.   Heating a  solvent  containing dissolved compo-
nents will result  in evaporation of  the solvent.   (Refer to Section 2.4.1.16
Evaporation/Crystal!ization/Drying.)   Once the saturation point is reached in
the  remaining solvent, precipitation of  the  solute will occur.   This tech-
nology  is  best suited for  high  concentrations  in  solution  and more particu-
larly for  inorganic species and metal  ions.

Precipitation  would not  be  effective  for  treatment or  removal  of dissolved
organics  found  in the  Firestone  Salinas ground  water.   Thus,  no  further
consideration will  be given to this  treatment method  for  implementation at the
Firestone  Salinas  site.

Electrostatic Precipitation
This  treatment method  is  an  electrolytic  treatment method  for  removal  of
particulates  from  gas  streams.  Gas  from  a combustion or chemical process is
passed  between  two plates energized with  ac  electric  current.   Particulates

FIR:0067-R8S2                          2-41

-------
                                                                Date-:  3/22/89
                                                                Final Revision

through  the  field  become  charged  and  migrate  to  one  plate  or  the  other
depending on  the  charge  of the particle  (electrical  attraction).   The plates
eventually  become  loaded;  and periodically  the  current is  shut  off,  and the
plates are cleaned by mechanical means, such as compressed air blasting.  This
treatment method  is  used commercially for  cleanup of  stack  gases from power
plants.

This method would be ineffective for treatment of the Firestone Salinas ground
water.   Thus,  no further  consideration will  be  given  to  this  method  for
implementation at the Firestone Salinas site.
                                .*

2.4.2.3  Ion Exchange
Ion exchange treatment technology uses natural or synthetic inorganic crystals
(zeolites),  stationary-phase  synthetic   ion  exchange  resins,  or  dispersed
chelating agents to remove or bind ions contained in a solution.   Ion exchange
is generally  limited to  removal of metal  ions or charged  organic  species such
as  cyanide.    Stationary-phase synthetic  ion  exchange resins  consist  of  a
polymeric backbone with various active salt-forming organic groups attached to
the  end  of  the  polymer chains.   Potential  active  groups  may  be sulfonic,
carboxylic, phenolic, and various amine groups.  The ion exchange  process Is a
reversible exchange  between  the insoluble solid salt  (the  ion exchanger) and
an  ion-containing solution.    The  driving  force  for  the  exchange  of  ions
between  the  exchange  agent  and  solution  is a function  of  the  equilibrium
determined by  the  relative  insolubilities of the  salts that can form 5y iors
present and  the  exchange agent.  Adjusting  concentrations  or shifting the pH
changes  the  relative  solubilities,  thus  making  the  process  reversible.
Reversibility allows for recovering  the  species  removed from the  solution and
essentially  endless  regeneration/reuse of the resin  (Berkowitz  et a!., 1973,
pp. 633-636).

Chelating  agerts  are  structurally  similar  to  synthetic  ion  exchange resins
except  that  the  polymer  backbone,  which  makes  resins  fixed phase,  is  nc*

FIR:0067-R8S2      .                   2-42

-------
                                                                Date:  8/22/89
                                                                Final Revision

present.   The  active agent  is  free  to move throughout a  solution.   Chelants
are used  most  frequently to  bind  metal  ions in  solution,  usually  to prevent
them  from  interfering  with  polymerization  or  other. chemical  reactions.
Stationary-phase resins  are  usually best suited  for  waste treatment applica-
tions  because  the  contaminants  are  actually  removed, not  just bound  in  an
unavailable form.

In actual operation, the  ion  exchange resin in  the form of polymeric beads is
loaded  into a  column.   The solution  to  be  treated is usually passed downward
(concurrent) through the  resin  column.   Ions from the resin are exchanged for
ions  in  solution.    Either cations and anions can  be exchanged,  depending on
the resin type.  Various resin forms are available such as sodium-ion exchange
resins  or  hydrogen-ion  exchange resins.   These resins (sodium  and hydrogen)
cm be  regenerated  with  strong  salt  solutions  or acid solutions respectively,
when exhausted (a reversal of the equilibrium).  There are also various column
configurations   that  allow   for  cocurrent,  countercurrent,  or  continuous
operation.

Ion  exchange  technology  is  best  suited  for removal  of  ionic species.   Ion
exchange  would  be   ineffective  for  removal or  treatment  of the  dissolved
organics  found  in   the  Firestone  Salinas   ground  water.    Thus,  no  further
consideration will  be given to this treatment method  for implementation at the
Firestone Salinas site.

2.4.2.4  Oxidation
The  six  oxidation  technologies  that  have  potential   in  waste  treatment
applications are as  follows:
        •  Chemical  oxidation
        •  Wet air oxidation
        •  Supercritical fluid oxidation
        •  Electrolytic oxidation
        •  Thermal oxidation
        •  Bioloaical oxidation.
FIR-.0067-R8S2                         2-43

-------
                                                                Date:  8/22/89
                                                                Final Revision

The  first  three  of  these  technologies  are each  discussed in  the  following
subsections.   The, last  three  technologies,  electrolytic  oxidation,  thermal
oxidation,   and  biological  oxidation,  are  discussed  in  Section  2.4.2.5  -
Reduction,  Section  2.4.4  - Thermal Treatment,  and  Section 2.4.3 -  Biological
Treatment.

Chemical Oxidation
Chemical oxidation treatment  is  the  controlled  addition of chemical  oxidizing
agents to  a  waste stream  to cause chemical  transformation (via oxidation) of
the waste  to simpler or  less  toxic  components.  Sources  of  oxidants include
air, oxygen,  ozone,  hydrogen peroxide, chlorine,  chlorates,  chlorites,  hypo-
chlorites,   perchlorates,  permanganates, or  strong  oxidizing  acids  (such as
nitric acid).   The ideal  products of chemical  oxidation reactions  are simple
nonhazardous components such  as carbon dioxide or  water.   Often species  such
as HC1, N02» or $03 are generated that may require additional  treatment before
ultimate  disposal.    These  reactions  are  termed   "redox  reactions"  since
oxidation  (of  the water)  and reduction (of  the oxidizing  agent) occur at the
same time.

Oxidation  of  some  species may  also  produce   insoluble  precipitates.    This
occurs when solutions of metal ions are oxidized to produce metallic oxides cr
hydroxides.   Precipitates  may then be removed  by  media filtration  or centri-
fugation,  leaving a less environmentally toxic  solution.  The effectiveness of
the oxidation  process  depends on  the  chemistry and  reactions  involved.   The
usual  limitations  are  removal  of evolved heat  (oxidations  are  generally  exo-
thermic),  control  of side reactions that may  generate unwanted intermediates
(and consume  the  active  oxidant), reactivity of the  waste species,  and  toxi-
city of the  oxidation  products.   Chemical  oxidation is a method primarily for
treatment  of  organic-containing  wastes  of   moderate  to  high  reactivity.
Moderate to high reactivity organics include alcohols,,ketones,  organic acids,
alkyl  and   nitro-substituted  aromatics,  unsaturated  alky!  grouos,  carbohy-
drates,  phenols,  aldehydes,  amines,   and   various  sulfur  compounds.    The

FIR:0067-R3S2                         2-44

-------
                                                                Date:  8/22/89
                                                                Final Revision

selection of an  oxidant  is made based on a  number  of  factors including cost,
availability, side reactions, oxidant strength, and toxicity.

Low  reactivity  compounds  include  halogenated hydrocarbons,  saturated  alpha-
tics,  and  benzene.    These types of  compounds are particularly  resistant to
chemical oxidation.   Chemical  oxidation of these low  reactivity  organics may
be difficult, expensive,  slow, or  impossible to accomplish  only  by chemical
means.  Chemical oxidation in conjunction with UV light (photolysis) is effec-
tive  for some of these species (see  photolysis  -  Section 2.4.2.6).  Further,
some  organics such  as polyethylene or polypropylene have  very  low reactivity
toward  chemical  oxidants  and  are  classified  as  refractory  organics.   These
materials  can  be  oxidized  only  by  using  other methods  such   as  thermal
oxidation.

Chemical oxidation  would  be effective  in treating the  dissolved chlorinated
organics in  the Firestone Salinas  ground  water.   However,  the  probable slow
reactivity  of  these  organics  with  chemical oxidants  would require  longer
retention  times and  large holding  volumes  to  achieve  complete  destruction.
Ultraviolet   (UV)   radiation  treatment  with   chemical   oxidants  has  been
demonstrated as  effective; however, the capital cost,  potential  adverse side
reactions  (which may  produce  HC1  or short-chain  chlorinated organics), and
byproducts of this type of treatment make it  potentially unsuitable.  Thus, no
further consideration will be given to this treatment technology for implemen-
tation  at the Firestone Salinas site.

Wet-Air Oxidation
Wet-air oxidation is  a process technology  that uses oxygen (usually using air
as the source)  and water  under h-igh temperature and  pressure  (but under the
critical point  of  water)  to  oxidize  organics and certain metal  ions.   The
technology   is  'primarily  applicable  for  treatment  and  detoxification  of
municipal sludges and moderate concentrations of most organics.
FIR:0067-R8S2                         2-45

-------
                                                                Date:  8/22/89
                                                                Final Revision

The  process  begins by  preheating the  feed  and pumping  it into  the  wet-air
oxidation tower (reactor).  The pressure and temperature required for destruc-
tion is  specific  for  each waste type depending on  how resistant the waste is
to oxidation  and  the  BOD/COO  requirement.   Essentially a  wet-air  oxidation
reactor, is  a BOD/COD  reducer.   The primary  limitations on capacity  are  the
residence time,  blower capacity  (oxygen  source),  heat  transfer,  and  organic
concentration in the waste stream.

The  organic  concentration  and  composition of  feed  wastes  is the  primary
economic factor influencing  the applicability  of this  method.   Although wet-
air  oxidation  can  be  used  to  treat most organic waste  streams,  dilute or
highly  concentrated  wastes are  more  costly to  treat.  The  process requires
heat,  usually  derived  from  the  reacting  feed, to  maintain  temperature  and
pressure.   Low  concentrations of  organics in  the feed  do  not provide enougn
heat  value  to   self   sustain  the  process.    Dilute   waste   streams  require
additional  fuel,  usually  added  to the  feed  in  the  form  of diesel  fuel or
kerosene.   High  concentrations of organics  in the feed produce excess heat,
requiring high water  consumption to remove  the excess  heat  from the reactor
(in the  form of steam)  and making control  more difficult.   Economic operation
and control depend on a consistent feed concentration.

In actual operation of  a  wet-air  oxidation reactor,  water  and waste (and fuel
if necessary) are  premixed  and balanced,  then  fed  to  the  reactor to maintain
near-constant temperature and  pressure.   Water  must   be  present to  provide
steam for pressure  and  a  media  for the  (wet phase)  oxidation reaction to take
place.   A   consistent  feed  is  essential  to  prevent  drastic  pressure  and
temperature  shifts and   possible  incomplete  treatment.    Catalysts  such  as
nitric acid are sometimes used  to  speed  up the reaction or allow operation at
lower  temperatures.    Wet-air  oxidation   is particularly  effective  to  treat
refractory organics  such  as  polyethylene, chlorinated  organics,  pesticides,
and other otherwise untreatable wastes.   Treatment  of  halogenated soecies  and
other types of organics may produce aggressive by-products  that require exotic

FIR:0067-R8S2                         2-46

-------
                                                                Date:  8/22/89
                                                                Final Revision

metallurgy.  Reactors  are  usually  constructed  of high-grade stainless, nickel
alloys, or titanium.

Wet-air  oxidation  has  only  been  pilot  demonstrated  (10  gpm)  for  hazardous
waste treatment  (Zimpro, Series  300).   This technology requires sophisticated
process  control  and  peripheral  equipment  such as  high-pressure  pumps  and
compressors, and exotic alloy  heat exchangers.   Some of  the  other problems
associated with  operation  of a wet-air oxidation reactor  include  disposal of
salts  in  the  treated  effluent  and  control  of  fugitive emissions.    The
technology  is  very  well   suited   for the treatment  of  municipal  sludge.
Numerous  full-scale wet-air  oxidation  installations are in operation at POTWs
throughout the country.

Wet-air,  oxidation  technology  is not  considered economical  for dilute wastes
due  to  potential high  energy  cost and consumption.   Wet-air  oxidation would
not  be economical for  treating the low concentrations of chlorinated organics
in  the  Firestone Salinas  ground water.    Also,  the capital cost  to meet the
capacity  (ground water  volume) requirement would make this technology prohibi-
tively expensive to implement.  Thus, no  further  consideration will be given
to this treatment method for implementation at the  Firestone Salinas site.

Supercritical Fluid Oxidation
This  technology  is  similar  to  wet-air  oxidation  except  that  the  operating
conditions  are  above   the  critical  temperature  of  water.     Under  these
conditions  of  high  temperature and  pressure,   salts  precipitate  and  can be
recovered.  Organics are completely oxidized or  can be extracted and recovered
depending  on  the   supercritical  fluid medium   (i.e.  water,  carbon dioxide,"
etc.).    This  process  is  being discussed as  an   oxidation technology  sines
recovery  of  toxic  organics in waste treatment  is  usually  less important  than
destruction, especially for dilute  solutions.  In waste treatment,  the primary
application  of  the   technology   is   to   oxidize   organics  to  the  simplest
constituents and recover metal salts  (usually  in the form of  oxides).  Often

FIR:0067-R8S2                          2-47

-------
                                                                Date:  8/22/89
                                                                Final Revision

this  technology  is  referenced   in  the   literature  as  supercritical  fluid
extraction.   The  technology  may fit  in  either  category  depending on  the
operating  conditions.    In  this  section,  the technology  is considered  as  a
high-pressure supercritical  variation on wet-air oxidation treatment.

Control and metallurgy problems are magnified in supercritical fluid oxidation
processing because of higher operating temperatures and pressures and the more
aggressive operating  environment.   Pumps,  heat  exchangers, and  other  peri-
pheral equipment must  be constructed of exotic materials.   Equipment becomes
expensive to meet  the  demand of rigorous  operating conditions.   However, one
advantage of supercritical  operation is that the  reactor volume  and required
residence time  in  the  reactor to achieve  complete oxidation are  much-smaller
(than  for  wet-air  oxidation).    This  results in  downsizing of  much of  the
equipment.  Despite this  advantage,  however,  the  technology  does  not have any
commercial demonstrations reported to date for waste or hazardous waste treat-
ment.  Extensive laboratory work and testing have been performed, resulting in
the  issue  of several  patents for the use  of supercritical  fluid  oxidation in
hazardous  waste  treatment.    Other  applications  of supercritical  fluid  tech-
nology have  been commercialized,  including a supercritical  fluid extraction
process to remove caffeine from coffee.

Supercritical  fluid oxidation  technology  has  not  been commercially  demon-
strated or piloted.   Supercritical  fluid  oxidation  has not  been  proven  as  a
suitable  method  for  the  treatment of   ground   water.    Thus,  no  further
consideration will be given to this treatment method for implementation at the
Firestone Salinas site.

2.4.2.5  Reduction
Reduction  technology  for chemical separation or t/ansformation  is. well  known
in  the  production  of pure  reactive  metals, in refinery  processes,  and  waste
treatment.  The  following three  types of  reduction processes are discussed in
this section:

FIR:0067-RSS2                         2-48

-------
                                                                Date:  8/22/89
                                                                Final Revision
       •  Electrolytic oxidation/reduction
       •  Chemical reduction
       •  Direct hydrogenation.

Each of these methods is discussed individually in the following subsections.

Electrolytic Oxidation/Reduction
Electrolytic reduction  involves  application of dc electric  current  across an
electrolytic cell.   Control of  voltage  and amperage can  affect  many separa-
tions that  are  impossible  using other methods.   Electrolysis  of  molten salts
is  a  technique used  to produce  materials, such  as sodium metal,  aluminum,
magnesium, fluorine, and other very reactive materials.   Electrolysis of salt
solutions is the  major  process for  producing chemicals  sucn  as sodium hydrox-
ide and chlorine.   In an electrolytic cell, oxidation and reduction take place
simultaneously  at the  anode  and cathode  respectively.    Reduction  reactions
often produce pure metals or hydrogen (from reduction of hydrogen ions present
in  solution  or  reduction of water).   Reactive metals when  electrolyzed from
solutions further react with the  solution  to form other species.   This occurs
when  sodium chloride  solutions  are  electrolyzed.   The  final.'  products  are
chlorine, hydrogen, and sodium hydroxide.   The intermediate  product  of sodium
metal is  electrolyzed from  the  solution  but immediately  reacts with  the water
present  to  form sodium  hydroxide and hydrogen.   Electrolytic  cells  have been
developed and improved  for  various  waste treatment applications.   The primary
use of  this  technology  is  for  treatment  of waste streams containing dissolved
metals or ionized organics.

Over 200  commercial electrolytic  treatment  systems are  in use  for heavy metal
treatment.   This  technology  has been extended  to  treatment  of  ground water
containing  heavy  metal  contamination.  Variations on the electrochemical cell
have proven  effective for the treatment of fluorides and non-ionized organics.
The electrolytic  process is effective  for  treatment  of  such  a wide variety of
waste  because  it  provides  four  treatment  operations in  one unit.   Oxidation
and reduction occur  at  the  anode and  cathode.   Electrolysis  of water produces

FIR:0067-R8S2                         2-49

-------
                                                                Date:  8/22/89
                                                                Final Revision

hydroxide, which  helps  adjust the  pH  and precipitate metals.   A sacrificial
iron anode  is  oxidized to. produce  iron  hydroxide in solution.   This  form of
iron (as  reported  in  Section 2.4.1.5, under Physical Adsorption),  acts as an
adsorbent.  In solution both ionized and non-ionized species (organics) may be
trapped in the  iron  hydroxide matrix and coprecipitated.   Further evaluation
of this treatment  method  is  ongoing for  treatment  of organics.   Ground-water
treatment where both inorganic and organic contamination are involved might be
easily  and  more economically  treated  with a  single^electrochemical  unit as
compared  to  other multiple  treatment operations  addressing  each  waste  type
(Berkowitz et a!., 1978).

Electrochemical treatment  is an  emerging and relatively  untested  technology
for removal  of  chlorinated  organic  hydrocarbons.   The  technology  may not be
totally effective for treatment of  the  Firestone  Salinas  ground  water.  Thus,
no  further  consideration  will  be  given  to   this   treatment  method  for
implementation at the Firestone Salinas site.

Chemical Reduction
Chemical reduction uses chemically  induced reduction  reactions to cause a net
reduction in  the  oxidation  state of  a chemical  species.   Waste treatment is
performed by  selecting  reducing  agents  that are  powerful enough  to  convert
(reduce) a hazardous species  to  less  hazardous or nontoxic species of a lowe"
oxidation state.  A good example of this technology applied to waste treatment
is the  reduction  of  Chrome  VI to Chrome  III using  sodium sulfite,  bisulfite,
metabisulfite,  or  sulfur  dioxide  as  the source  of  the  reducing agent.   The
reaction proceeds under acidic conditions by converting  the sulfite source to
free sulfurous  acid.    The   sulfurous  acid is  oxidized   by  the  Chrome  VI to
sulfate.  Chrome VI is  alternatively  reduced to  Chrome  III.  The chemistry is
fairly  complex, as  is  the case for most  chemical  reduction reactions.  These
reactions are  termed  Redox  reactions  since  oxidation and  reduction  occur at
the same time.
FIR:0067-R8S2                         2-50

-------
                                                                Date:  8/22/89
                                                                Final Revision
Chemical reduction of metals dissolved in solution is a common waste treatment
operation.  Reduction technology also extends to the treatment of organics but
is limited.  Reagents such  as  borohydride,  lithium  aluminum hydride, aluminum
hydride,  reactive  metals such  as sodium,  potassium,  or  lithium,  hydrazine,
diborane,  and  a host of other agents  can  be  used  to reduce organics.   The
reactivity of these reagents limits  their usefulness  in  waste treatment since
many  are  also  very  water  reactive.    Reducing agents  are  often  added  to
chemical manufacturing processes to scavenge for impurities.

Chemical  reduction  technology is  primarily  effective   for treating  wastes
containing metals.  The  limited applications  of this  treatment technology for
organics  makes  this method  impractical to  treat  the  low-level  concentrations
of synthetic organics in the Firestone Salinas ground water.  Thus, no further
consideration will be given to this treatment method for implementation at the
Firestone Salinas site.

Direct Hydrogenation
Under pressure  and usually with  the  aid of a  catalyst,  many organic species
can  be  directly  hydrogenated and   subsequently   reduced.    The  technology
involves  direct  addition of hydrogen to a  wide variety  of organic functional
groups.   The conditions  required  may be mild,  as  is the  case  with aromatic
amines  and  aromatic  nitro compounds  (that  can be  hydrogenated  at 3  to  4
atmospheres  using  a nickel  catalyst).  Benzene  can be hydrogenated to cyclo-
hexane  but requires  hydrogen at several  hundred atmospheres and high temoera-
ture  (House, 1972).  Direct hydrogenation requires careful process control and
safety  measures  for handling  the  hydrogen  gas.   The  technology  has  wide
application  in  synthetic organic and  petrochemical  manufacture  but limited
application  to  waste  treatment  due to the  safety concerns, capital costs, and
rigorous  operating conditions.

Direct  hydrogenation would  be unsuitable as a treatment technology for the low
levels  of  synthetic  organics  In the  Firestone Salinas ground water.  T.nus, no

FIR-.0067-R8S2                         2-51

-------
                                                                Date:  8/22/89
                                                                Final Revision

further consideration will  be  given to this treatment method  for implementa-
tion at the Firestone Salinas site.

2.4.2.6  Photolysis
Photolysis,  as  applied  to waste  treatment,  is  the  inducement of  chemical
transformations using light.   Light, for  the purposes  of  this  section, refers
to radiation within the ultraviolet  (UV),  visible, or  infrared (IR)  radiation
spectrum.   Other  frequency ranges  are  discussed  in Section  2.4.2.7  under
Irradiation.   Breaking  of  bonds  using light  is  well  known in  organic  chem-
istry.  Light of the appropriate frequency and  intensity  cleaves many types of
chemical bonds, according to the principles of  quantum mechanics.  The mechan-
isms are complex and the applications specific, but the technology has useful-
ness,  especially  in the  treatment of  difficult-to-handle compounds  such as
pesticides  and  dioxin.   Light  sources  may  be the  sun;  low, medium,  or high
pressure mercury-arc lamps;  fluorescent  lamps; or  lasers.  The  selection of
the  light   source  depends  on   the  required intensity  and  frequency of  the
radiation necessary to  accomplish the desired chemical  transformation.  Photo-
lysis  is often  applied  in conjunction with  other  technologies  such  as UV and
ozone treatment, UV and chlorine treatment, or  UV and peroxide  treatment.  The
major  advantage of  this  technology is that  specific bonds can  be targeted by
selection of the appropriate frequency and intensity of the light source.

UV light  is frequently  used as  a  sterilizing  agent.   A  number  of  comrne-cial
applications have been developed  as well  as demonstrated  in pilot  plants for
treatment  of  dioxins and  PGBs.    Rearrangement,  side  reactions, and  the by-
products produced may limit the application of  this technology.  The treatment
may  produce species which  are  as  hazardous  or  difficult to  remove as  the
original  contaminants.    The  residence  time   required   to achieve  complete
destruction may limit processing capacity  or require a prohibitive increase in
the  size  of the photolysis  reactor.   Also, depending on  the  light  intensity
required, energy consumption could be extremely high.
FIR:0067-R8S2                         2-52

-------
                                                                Date:  8/22/89
                                                                Final Revision
Technical limitations would  make photolysis impractical for  treatment  of the
dissolved organics  in  the Firestone Salinas  ground  water.   Thus,  no further
consideration will be given to this treatment method  for implementation at the
Firestone Salinas site.

2.4.2.7  Irradiation
Irradiation using  high-energy gamma rays, x-rays, or  microwaves  is currently
an experimental  method  for hazardous waste treatment.   Microwave irradiation
of metal-containing  organics with  oxygen in the  plasma phase is  an experi-
mental method to  remove  metals by depositing the metals  in  the form of metal
oxide  films.   This  technique would  have limited commercial value  in waste
treatment due to  cost;  however,  it might be  developed for production of high
technology ultrapure materials.

Gamma irradiation treatment' is an experimental method that has been applied to
the  treatment  of pesticides.   Gamma irradiation of  labile food stuffs  is a
highly controversial method  for sterilizing, preserving,  or prolonging shelf
life.

Irradiation treatment using sources such as radio waves would not be effective
in waste  treatment  applications.  Radio-wave frequencies  and bandwidths have
the  wrong  magnitude or  are  the  wrong  frequency to  break chemical  bonds  cr
cause chemical transformations.

The drawbacks of irradiation use in waste treatment are limited applicability,
safety, and energy consumption.  High-energy gamma ray sources, x-ray sources,
and high-energy microwave generators require extensive shielding and isolation
to protect  operating personnel.   Gamma  ray  sources  are  often  expensive and
require  careful   handling  and  licensing  as  a  nuclear  material.    X-ray  and
microwave  generators become  expensive  as they  become  larger  for  commercial
applications.   Also, energy  (electrical) consumption becomes a  cost  factor
with  larger commercial  x-ray  and microwave units.

FIR:0067-R8S2                         2-53

-------
                                                                Date:   8/22/89
                                 -  •    .    •                     Final Revision

 Irradiation   is  currently  an  experimental  method  for  treatment  of   very
 difficult-to-treat  or  extremely hazardous wastes.   Sterilization by irradia-
 tion  is a potential commercial application but has drawbacks.

 The limited demonstrated waste treatment applications and safety concerns  make
 this  method  inappropriate  for removal or treatment  of  the  dissolved organics
 in the Firestone Salinas ground water.  Thus, no further consideration  will  be
 given  to  this  treatment  method for  implementation  at the  Firestone  Salinas
 site.

 2.4.2.8   Stabilization
.Stabilization  is  a treatment  process  for   immobilizing  waste  materials  to
 prevent them  from  entering  the  environment  or food chain.  Stabilization  does
 not destroy the  waste  but  alters  it chemically or physically to prevent mobi-
 lization  (leaching).   Other  terms that  describe  this process  are fixation,
 encapsulation, or cementation (Parmele et al., 1986)

 The four stabilization processes are as follows:
       •  Inorganic microencapsulation/fixation  (incorporate  the waste into  a
          silicate-based mix such  as cement or kiln dust).
          Inorganic  vitrification  (melt  or  fuse  the  waste,   discussed  in
          Section 2.4.4 under thermal treatment).
       •  Organic microencapsulation  (incorporate  the waste  into a polymer  or
          asphalt matrix).
       •  Organic encapsulation (surround a waste volume in a polymer shell).

 These  will  be  discussed  separately  as  inorganic and  organic  stabilization
 methods.

 Inorganic Stabilization
 Inorganic stabilization may involve the following chemical reactions:
 FIR:0067-R8S2                         2-54

-------
                                                                Date:  8/22/89
                                                                Final Revision

       •  Neutralization (acid/base)
       •  Precipitation (insolubilization)
       •  Hydration
       •  Addition
       •  Substitution
       •  Complexation
       •  Ion Exchange
       •  Adsorption.

The process  involves the  interaction  between the  waste  (soluble)  and  sili-
cates, alkali, water,  salts,  and  the ions 'present.  The  result  is the micro-
encapsulation of  insoluble waste particles  and  solidification of  the liquid
waste fraction.  The reactions are termed  cementation  reactions  or pozzolanic
reactions.   The  difference between  cement and  pozzolanic  materials  is  that
pozzolanic compounds require lime to form  a  cement  (materials  such as fly ash
or  volcanic  ash),  whereas materials  like calcium  silicate do  not.   Waste
materials, cement material, water, and  stabilizers are  balanced and mixed in a
pug mill  or  other  solids blending unit.   Once the  cementation reaction takes
place, the waste  material is encapsulated and should not be  leachable.

Stabilization  is  a  useful  method for  treatment of metal-containing wastes.
Metal-containing  waste  must  be either  recycled  or  stabilized since  they are
not  destroyed  by  conventional  treatment  methods.   The  cementation reaction
does  take  some  time to  go  to  completion.   The  reaction  also  requires water.
Totally "dry  solids  must be wetted  in  order  to stabilize  them.   Likewise,
extremely wet or diluted materials become  extremely expensive  to treat due to
the large amount of  cement material  required  to  form the  mix.   Some materials
such  as  acids may  require neutralization or  pretreatment  to prevent inter-
ference with the  cementation reaction.

Inorganic stabilization  would  be  uneconomical for  treatment of  the low-level
organic contamination in the Firestone  Salinas ground water.   Thus, no further
consideration will be given to this treatment method for implementation at the
Firestone Salinas site.
FIR-.0067-R8S2                         2-55

-------
                                                                Date:  3/22/89
                                                                Final Revision

Organic Stabilization
Organic  stabilization  uses  polymers,  asphalt,  polyolefins,  or plastics  to
encapsulate or  isolate  (microencapsulate)  waste materials.   Encapsulation is
the sealing of  a  large  waste mass with the stabilization  agent (i.e.  a vault
around  the  waste  mass).    Microencapsulation  involves  the  blending   of  the
stabilizing agent through the waste,  forming an aggregate that hardens, isola-
ting  individual  waste  particles  from  each  other and  from  the  environment.
This  process  usually  requires  heating  or  in  situ  catalysis  of   a  monomer
(resulting  in  formation of  the polymer).   When  the encapsulating material
cools, 1t hardens  into a stable  refractory  organic,  inert  to all but the most
aggressive attack.  This method is more expensive than_inorganic treatment and
would not be appropriate for dilute aqueous  wastes.

Organic stabilization would not  be an  appropriate  or  cost-effective treatment
method for the dissolved.organic contamination in the Firestone Salinas ground
water.  Thus, no  further consideration will.be  given  to  this treatment method
for implementation at the Firestone Salinas  site.

2.4.3  Biological  Treatment
The following seven biological  waste  treatment methods will be discussed:
       •  Aerobic degradation
       •  Anaerobic digestion
       •  Enzymatic conversion
       •  In situ biological remediation
       •  Controlled bacterial  applications
       •  Composting
       •  Aquaculture.

Variations on each  technology  will  be  discussed where appropriate  within tne
individual sections.

2.4.3.1   Aerobic Degradation
Aerobic  degradation is  a  biological   treatment  process   that user.  nat'j-z"
bacteria  to  convert  (oxidize  or   hydrolyze)  waste  organics  by  enzymatic

FIR:0067-R8S2       .                  2-56

-------
                                                                Date:  8/22/89
                                                                Final Revision

action.  Aerobic degradation requires oxygen  by  definition and function.  The
following  aerobic  processes are  the most  commonly  used  in  waste  treatment
today (Other less common methods function by similar biological mechanisms and
will not be discussed individually for the purpose of brevity):
       •  Activated sludge treatment
       •  Aerated ponds or lagoons
       •  Trickling filters
       •  PACT™ (powdered activated carbon treatment).

These  are  discussed individually.   PACT™  (a  registered  trademark  of Zimpro
Inc.) is discussed separately in Section 2.4.1.5.

Activated Sludge Treatment
Activated sludge treatment  is a biological  process  that relies on the genera-
tion,  maintenance,  and  continuous  recycling  of  biomass  (living  bacteria"!
culture) to decompose  organic  matter.    The  biological decomposition  of the
waste  is the  result of enzymatic conversion  of  organic matter as part of the
life functions of the bacteria.

Activated sludge treatment is applicable to waste streams  containing less than
1 percent  solids  and moderate concentrations  of organics.   Very low organic
concentrations do  not provide enough  "food"  to sustain the activated sludge
biomass.   Very  high concentrations may  require additional  dissolved oxygen
added  as  air or pure  oxygen  under pressure.  Activated  sludge processes are
sensitive to heavy metal contaminants.  Although the  biomass can  be  acclimated
to  tolerate metals, it  is  best  to pretreat the. influent  with lime to remove
them.  The  biomass acts as a BOD/COD reducer, able to digest a wide  variety of
organic contaminants.   However, not  all  species  are degraded, such  as certain
refractory  organics and  species  including  polychlorinated  biphenyls.   Some
halogenated  organics can' be  degraded  but  at slower rates  compared to other
organics.   Activated sludge processes are very sensitive to  drastic  changes in
feed  concentration.    The  biomass must  be  acclimated  slowly;  otherwise, the
bacterial culture may die.

FIR:0067-R8S2                         2-57

-------
                                                                Date:  8/22/89
                                                                Final Revision

The  activated  sludge process  requires two  steps.   In  the  first  step,  the
incoming waste  feed  is  mixed  with recycled  biomass  (from the  clarifier),
aerated, and allowed to react  in the aeration  basin.   In the second step, the
mix flows to a clarifier, where the activated  sludge  is allowed to settle.  A
portion of the sludge  is  recycled  to the aeration tank  and  a portion is sent
for disposal.  The;effluent  (overflow) from  the  clarifier decants and is sent
for further treatment or disposal.  Pretreatment  of., the feed may be necessary
to remove metals  or adjust the pH.   Often a large equalization tank is used to
stabilize possible shifts  in waste feed  composition.    Nutrients  may also be
added to enhance  and  optimize bacterial  growth  and function.

Activated sludge.treatment would not be cost  effective to treat the low levels
of contamination  in the Firestone Salinas ground  water.   There  are not enough
organics in  the  ground  water  to sustain  an  activated  sludge biomass.   Also,
the  retention  times  required would  make implementation  of this  technology
prohibitively expensive due  to massive  holding basins  and clarifiers.   Thus,
no further consideration will  be  given to this technology  for  implementation
at the Firestone  Salinas  site.

Aeration Ponds  or Lagoons
A  common  and  effective  aerobic  treatment  method  is  an  aeration pond  cr
lagoon.  Aerobic  bacterial  action  is  most  effectively  used  for  treatment cf
dissolved  organic  species.    A  relatively  shallow   pond  when  mechanically
aerated  becomes  an efficient  aerobic  waste  treatment  reactor.    Although ar
aerated pond is not as efficient as an activated sludge process, net treatment
cost is cheaper due to lower initial materials  and construction cost (assuming
land is relatively inexpensive and  available.)   Aeration ponds are best suited
for  treating waste  streams  with   loadings,  of  less  than  1 percent  solids.
Higher  solids  loading  may  fill  up  the.  pond quickly, requiring  expensive
dredging to restore operation.  Aeration  ponds  require longer retention times
than activated sludge  treatment.    Depending on the pond  depth,  both aerobic
and  anaerobic  activity  may  take  place.    Aeration  ponds  are  sensitive  to

FIR:0067-R8S2                         2-58

-------
                                                                Date:  8/22/89
                                                                Final Revision

changes in ambient temperature.  Biological  activity  drops  off below 30°C and
may cease near freezing.

Aeration ponds  may not  be  totally effective  for treatment of  the dissolved
chlorinated organics  in the Firestone Salinas  ground water.  Also, the slow
rate  at which  aerobic  bacteria  breakdown  chlorinated organic  hydrocarbons
would require a very  large  pond to  provide  adequate residence  time.  The cost
of construction and procurement of  land make this method unsuitable.  Thus, no
further   consideration,  will   be   given   to   this   treatment  method  for
implementation at the Firestone Salinas site.

Trickling Filters
A trickling filter is a simple application of aerobic biological  treatment.  A
packed  bed  of stones  or synthetic media provides  a surface  for  a bacterial
slime to grow and develop.  As the  waste flows through the filter bed, contam-
inants  are  removed  and digested by  the bacterial  cell mass (slime).   The
advantage of  a  trickling filter is that  it  provides  a  large surface area for
the  bacterial  slime  to grow,  a  large  area  for  intimate contact  of the waste
stream  with   the  bacterial   mass,  and  a means  to aerate  the  waste  stream,
providing  good  conditions  for biological  activity.   Anaerobic  bacteria may
also  grow  underneath the  aerobic  bacterial  slime,  if the  slime  layer grows
thick enough. Thus,  both  anaerobic  and  aerobic reactions may occur  within the
same unit.  Trickling filters decompose a wide range of organics similar to an
activated sludge process.  However, since the residence time within  the  trick-
ling  filter  is  less  than for  an activated  sludge treatment unit, the effici-
ency  is not  as  high.   Reflux of  a  portion  of  the  filter  effluent  is one
technique that helps  improve efficiency.  Trickling filters have the advantage
over  activated sludge  treatment of  being  more tolerant  of  shock loading.
Also,  trickling  filters tend to produce  a  more  uniform effluent quality when
influent quality varies.   Shock  loading  should be avoided  as much as possible
as  it may cause  overgrowth of the  bacterial  and sloughing of  the bacterial
slime mass from the filter packing.  Shock loading as a rule should  be avoideo
with  all biological treatment processes (Berkowitz et al.,  1973, pp. 253-259).
FIR-.0067-R8S2                         2-59

-------
                                                                Date:  8/22/89
                                                                Final Revision

A trickling  biological  filter would be  inefficient for treatment  of the low
concentration of organics in  the Firestone Salinas  ground  water.   There would
not be an adequate amount of  organics  present  to sustain sufficient bacterial
mass.  Thus,  no  further consideration will be  given  to this treatment method
for implementation at.the Firestone Salinas site.

2.4.3.2  Anaerobic Digestion
Anaerobic digestion is  a  bacterial  treatment process that  takes  place in the
absence of  air  (oxygen).   Two  types  of bacteria work  in  conjunction (symbi-
osis) with  each  other.   Acid-forming  bacteria hydrolyze complex  organics to
organic  acids,  alcohols,  carbon dioxide,  and  hydrogen.    Methane-producing
bacteria utilize  the  end  products of  the acid-forming  bacteria  to produce
methane and  cell  mass.    The process  produces a low  amount of  waste sludge
because  a  high  portion of  the organics  are  converted to  methane  and CC^
instead of cell  mass.   The process  can tolerate a higher percentage of solids,
up to  15 percent.   Conventional digesters are  closed tanks with  no agitation
and  provide  a retention  time  of  30  to 60  days.   High rate  digesters  have
provisions  for  mixing,  reducing the  retention  time  to an average  of  14 to
16 days.  Sludge volume can be reduced 40 to 60 percent  by anaerobic digestion
compared to aerobic digestion (Berkowitz et a!., 1978, p. 218).

Control of  an anaerobic treatment  process  is  essential.   Anaerobic bacteria
reproduce slowly, thus controlling  upsets  is critical to performance.  Upsets
occur when acid-forming  bacteria increase in number  relative to their methane-
forming counterparts.   This produces an excess  of acid,  reducing the number of
methane-forming  bacteria.    Methane-forming bacteria  are  sensitive  to  acid
build up.   Should  an  acid imbalance occur, pH  adjustment  or shut down of the
feed  may  be  necessary  to  prevent   totally  killing  all   the methane-producing
bacteria.   This would  result  in  digester failure  that  is very  odorous and
messy to clean  out..   Anaerobic bacteria are also sensitive to  certain metaU
and  various  organics  depending  on  the concentration.   The  technology is most
appropriate for waste streams containing volatile solids  and a  good supply of
digestible organics (Berkowitz et al., 1978).
FIR:0067-R8S2                         2-60

-------
                                                                Date:  8/22/89
                                                                Final Revision

Anaerobic digestion  would  not  be  suitable for  treating  the  low  levels  of
synthetic organics in the Firestone Salinas ground  water.   Inadequate organic
feed to sustain bacterial  and long residence time requirements would eliminate
this method  on the  basis  of operating  and capital  cost.   Thus,  no further
consideration will be given to this treatment  method for implementation at the
Firestone Salinas site.

2.4.3.3  Enzymatic Conversion
Enzymes  are  natural  biochemical  catalysts  manufactured by  living  cells  that
allow specific life  function chemical reactions  to  occur under mild temperate
conditions  (around  30°C).   Enzymes typically  are  polypeptide  chains (amino
acids) of molecular weights in the range of 1  x 10  mass units (Mark,  1985).

There are four categories of enzyme activity.   Absolute enzymes catalyze only
one specific reaction.  Stereospecific  enzymes  catalyze reactions of one type
of optical isomer but not the other, but may also cause reactions in a similar
class of the  same optical  configuration.   Hydrolyzing enzymes  react with a
specific organic  group,  such as  alcohols,  esters,  or  organic  acids.   Point-
specific enzymes  react  at  specific  sites  on  a particular  molecule,  such as
cleaving of a specific bond (Mark, 1985).

The  structure  and order  of amino  acids making up the enzyme  determine  its
reactivity and  function.   The  primary  enzyme structure  is determined by  the
linear  configuration or  order  of  the  amino acid  units.    Further structure
results  as the chain twists and folds on itself, giving it  a highly  intricate,
three-dimensional  structure  and  spacial  arrangement.   The  intricate enzyme
structure results  in the  creation of very  specific sites  on the enzyme mole-
cule.   These catalytic  sites  allow very specific reactions to occur  (Morrison
et al.,  1973).  Enzymes are temperature sensitive,  being deactivated at 50= to
70°C.   This is a  result  of higher temperatures distorting the enzyme struc-
ture.   Weak  hydrogen bonds  may  be stretched or broken  at higher temperatures,
disorienting or destroying the specific catalytic site  on the enzyme me-'ecu"e.

FIR:0067-R8S2                         2-61

-------
                                                                Date:  8/22/89
                                                                Final Revision

Enzymes  are produced  as  part  of  the  continuing  life  function  of  cells,
governed by instructions  in the cell's DMA.   Specific enzymes may be recovered
from various sources including plants, animal  organs, and cell cultures (Mark,
1985).
                                              *
Enzymes simply  added to solution may lose their  catalytic activity rapidly due
to  agitation,  pH, metals  in the  solution,  temperature,  and other  organics
present.  Various methods  have  been developed to  immobilize  enzymes on fixed
substrates.    Immobilization allows  use of  the enzyme  similar  to  catalysts
packed   in a fixed bed reactor.   Fixed or soluble enzymes may  be  introduced
into a  stirred  tank  reactor, accelerating a desired conversion.  Enzymes might
then be recovered for reuse or removed if catalytic activity is lost.  Commer-
cial applications of enzyme conversion include the  production of high fructose
corn syrup,  production of antibiotics, and fermentation.

Waste treatment is generally performed using  the bacteria,  which produces the
enzyme  rather than recovering a specific enzyme  and using that to break down a
particular toxic component.  There are enzymes  that  perform conversions, such
as converting urea to carbon dioxide.  The literature surveyed did not report
specific enzymes for treatment of chlorinated organic hydrocarbons.   However,
various types of aerobic  bacteria are known to break down chlorinated organics
slowly.  Few examples of  the isolation and commercial availability of specific
enzymes  that  might   be  used  in  ground water  treatment  are  reported  in  the
literature.

Enzymatic conversion  is  inappropriate for treatment  of  the Firestone Salinas
ground  water due to  the unavailability of suitable enzymes.  Thus,  no further
consideration will be given to this  treatment method for  implementation at the
Firestone Salinas site.

2.4.3.4  In Situ Biological Remediation
This technology is a method  used  to  enhance  the natural  breakdown of contami-
nants  that  have  been  released  into  ground  water or soil.   The  technology
FIR:0067-R8S2                         2-62

-------
                                                                Date:  8/22/89
                                                                Final Revision

involves injecting nutrients and available oxygen-enhancing chemicals (such as
hydrogen peroxide)  into  an underground  contaminated aquifer.   Nutrients and
increased oxygen  levels  stimulate  natural bacterial  growth.   The increased
numbers of bacteria break down the contaminants present at an accelerated rate
as  a  result of  the artificially  enhanced optimized  growth conditions.   In
addition,  the  bacterial  action  accelerates  the  release  of  contaminants
adsorbed on  soil   particles.    When  the  remediation is  completed, bacterial
levels return to  normal,  leaving no hazardous residuals.   In situ biological
remediation,  when   technically  appropriate  to   implement,   may  cut  the
remediation time  for a site by 90 percent  over  pump-and-treat methods alone.
In  situ  biological remediation  works  best when dissolved  organic concentra-
tions  are  high.    Usually  pump-and-treat  methods are  combined with  in situ
biological  remediation to  control  the  flow of nutrients.   Nutrient solutions
can  be directed   within  a  contamination  plume  by  injecting upgradient  of a
pump-and-treat extraction well.  In situ biological treatment can be effective
for vadose  zone  contamination, provided  a suitable  delivery method  (such as
percolation) can  be devised to deliver nutrient solutions.

Cultured natural  bacteria (selected to consume specific contaminants) may also
be  injected in addition to the nutrient solutions.  Release of certain geneti-
cally  engineered  bacteria  into  the  environment  is  still controversial but may
have some application in  the future.  Genetic engineering may allow the devel-
opment  of  bacteria that  will  treat  difficult or  slow  degrading contaminants
such as  DDT or PCBs.  Chlorinated hydrocarbons pose  a particular problem as
they are slow to degrade  biologically.

In  situ  biological  remediation  would  be  difficult   to   implement  at  the
Firestone Salinas  site due to the size  and depth  of the plume, high recharge
rate  of the  aquifer,  and  low  concentrations  of organic  compoundss  in the
ground  water.   The benefits  are limited due to  slow  biological breakdown of
chlorinated organics.  The  additional  cost is not considered to be justified.
Thus,  no further  consideration will  be  given  to  this  treatment  rneinod for
implementation at the Firestone Salinas site.
FIR:0067-R8S2                         2-63

-------
                                                                Date:  8/22/89
                                                                Final Revision"

2.4.3.5  Controlled Bacterial Applications
Engineered bacterial applications fall into the following two categories:
       •  Naturally selected
       •  Genetically engineered.

Each of these .applications is discussed in the following subsections.

Naturally Selected Bacteria
Since early  civilization,  bacteria and yeast  have been used  to  produce w.ine
and cheese through  fermentation.   As more was  learned  about these processes,
the specific  natural bacteria that  cause  these  transformations were isolated.
Recent progress has  allowed  culturing, drying,  and preserving  a  wide variety
of  natural  bacterial strains  to  perform  many chemical  synthesis  and  waste
treatment operations.

Dried bacterial cultures are available to decompose oil, gasoline, grease, and
various organics.   Normal mutation that occurs in the bacterial population has
led to  isolating  and  culturing  tolerant mutant strains  of  bacteria that will
break down normally difficult to treat or slow degrading wastes such as pesti-
cides, chlorinated organics,  phenols, and dioxins.

Addition of  selected bacteria  to  treatment units  (such as  activated  sludge
systems  or  anaerobic  digesters)  in  sanitary  plants   greatly  improves  the
efficiency and  ability  of these plants  to handle  industrial-type  wastes  ard
remain within permit limits.

Selected bacteria have potential applicability  for  in  situ  treatment of mate-
rials released to the environment.   The cleanup of oil  spills on coastal areas
is  dramatically enhanced by  application of  oil-digesting  bacteria.   In situ
biological   remediation   combined  with  pump-and-treat   methods  can  also  be
enhanced  by   the  addition  of  selected  bacterial   strains   specific  to  the
selected waste  type (PolyBac Corporation,  1989).   The limitations -en  using
naturally selected  bacteria  are those  imposed  by the methods  of application
(i.e., trickling filter, in situ treatment, activated sludge, etc.).

FIR:0067-R8S2                         2-64

-------
                                                                Date:  8/22/89
                                                                Final Revision

Naturally selected  bacteria  would have limited effectiveness  in  treatment of
the low concentrations of chlorinated organics in the Firestone Salinas ground
water.  As  stated  in other sections,  bacteria  are  slow in degrading chlorin-
ated  organics.   Furthermore, the  aquifers  at the  Firestone  Salinas site are
not  idaally suited  for  in  situ  biological  treatment  due  to high recharge
rates.  It  would not  be  economical  to consider surface biotreatment of pumped
ground water due to residence time and large holding volume.  Thus,  no further
consideration will  be given to this treatment method for implementation at the
Firestone Salinas site.

Genetically Engineered Bacteria
A  new frontier has  developed  as a  result  of advances  in molecular biology.
Recombinant  DMA  techniques  have  allowed the  joining  of  DNA  fragments  from
different organisms.   Inserting  these new ONA  fragments  into a bacteria give
the cells new genetic information.  The new instructions can cause the cell to
produce chemical materials or perform conversions  that were not normally part
of  its  former  life function.    Although  this  technology  is  in  its infancy,
great benefits have  already  been  derived  from its  application.  The synthesis
of human  insulin and  other hormones,  and  the production of vaccines and vita-
mins  are' just a few of the commercial applications.

The major  drawback with  this  technology  is the potential danger and contro-
versy  associated  with  the  creation  of these new  life 'forms.    Synthesis
reactions  involving  genetically  engineered  bacteria are carried out in closed
vessels.   The bacteria  are  "sterilized" or  removed before  the  products are
recovered  to prevent  environmental  release.   The  application of genetically
manipulated  bacteria to  waste  or in  situ  treatment  is  currently  restricted
until  the controversy  and  safety issues are  resolved.   Only one  commercial
application  of  environmentally released, genetically  engineered  bacteria has
been  allowed to date.    This  was a  test  involving a  bacteria engineerec to
prevent frost damage  to  strawberries.  Until the controversy and safety issues
are  resolved,  further development for  waste  treatment applications are  at  a
standstill.
FIR:0067-R3S2                         2-65

-------
                                                                Date:  8/22/89
                                                                Fina-1 Revision

Genetically engineered bacteria are unavailable for the treatment of the types
of  dissolved  chlorinated  organics  in  the  Firestone  Salinas ground  water.
Thus,  no  further consideration  will  be given to  this treatment  method  for
implementation at the Firestone Salinas site.

2.4.3.6  Composting
Composting is an aerobic treatment method  used  to treat primarily high solids
sludges or solid waste.  The  method  involves simply piling organic-containing
waste  and  allowing  natural  aerobic  bacteria to grow and  decompose the solid
waste  material.   Refinery  sludges  and  municipal  sludges may  be effectively
treated this way.   Often this method  is referred to  as landfarming.  Turning
over piles (tilling) enhances bacterial action and growth and serves to aerate
the soil.  Adding lime helps condition the soil  and balance the pH.  Nutrients
may be added  to  encourage  optimum bacterial growth  and waste breakdown.   The
products are  gases,  usually carbon  dioxide  and  steam,  and  a liquid leachate
which  may  contain  partially oxidized  organics  or heavy metals  (Berkowitz et
al.,  1978).   If  the waste  contains  primarily  organic  constituents,  sludge
disposal  from the  compost bed will  not be  necessary.   The  organics  will be
either completely oxidized  and be removed as gases or  left  in the leachate.
Compost  piles  must  be  slightly  wet for  the  bacteria to  begin  functioning.
Usually enough water  is  produced  by  the decomposition to sustain the bacteria
until  the  composting   is   completed.     Composting  will  also  proceed
anaerobically, as  demonstrated  in  municipal  landfills.   The products   from
anaerobic  composting are  methane,   some carbon  dioxide,  traces  of volatile
organics,  and  water.    On  a  large  scale,  methane  is  usually  extracted by
installing wells  in the landfill.   The gas is then  recovered,  purified,  and
sold  as  a medium  to high  BTU gas  product.  The  primary costs  involved in
composting are  transportation  to the  composting  site,  labor and  equipment
costs  to move and till  waste  material,  collection and disposal (or treatment)
of  leachate,  and the cost  of a  land  parcel and any  necessary improvements.
Improvements   may  include  a  concrete  slab  or  liner  to  assist  leachate
collection and prevent ground-water contamination.
FIR:0067-RSS2                         2-66

-------
                                                                Date:  8/22/89
                                                                Final Revision

Composting would  not  be applicable  to  treatment of  the  Firestone  Salinas
ground water  since  it  is only  a  treatment method  suitable for  solid  waste
material.   Thus,   no further consideration  will.be  given  to  this treatment
method for implementation at the Firestone Salinas site.

2.4.3.7  Aquaculture
A  novel  treatment  method for  treating  relatively dilute  aqueous  wastes  is
aquaculture treatment.  Several  species of aquatic plants are well adapted for
absorbing  waste  materials  from waste  streams;  in  particular,  those  wastes
containing  nutrients  such   as  available  nitrogen  and  phosphorous.    Water
hyacinths  are  a  menace  when  they clog  navigation  channels.    However,  the
characteristics that make them  a  menace in open waters make  them ideal  for
waste treatment.  These  plants  are  rapid  growing.  They have long,  fine fila.-
mented roots that  hang down as deep as 4 feet  from  the floating plant on the
surface.  Allowing these plants to grow over a large treatment  lagoon provides
an efficient way to detoxify large volumes of waste water.   The root filaments
trap  or  consolidate fine  particulates  which  settle  to the  bottom of  the
basin.   The  plants absorb soluble pollutants  and incorporate them  into plant
mass.   BOD,  suspended  solids,  and metals  can  be reduced by hyacinth treat-
ment.  Not all pollutants are destroyed,  some  being concentrated in the plant
tissues.   Also,  periodic harvesting of  the plants is  necessary.   The plants
are  much  easier  to  handle  and  dewater than conventional  sewage sludges.  The
plants are non-odorous  and  can  be  transported  in dump trucks.  . They are self-
dewatered when placed in a  landfarm and  biodegrade  aerobically.  The applica-
tion  of  aquaculture  is  competitive with  other processes.   The technology is
not  as  suitable  for  cold climates.   Lower temperatures  slow down the growth
rate  of  the  plants.   Also, prolonged  freezing  temperatures  will  kill  off
unprotected plants.   The  simplicity and added.benefits of this  technology make
it  attractive.   However,  aquaculture  is still  an emerging treatment method
(Hesby,  1983).   There is limited data  available  on  the ability of the plants
to remove synthetic  organic  hydrocarbons.
FIR:0067-R8S2                         2-67

-------
                                                                Date:  8/22/89
                                                                Final Revision"

Aquaculture treatment would not be  appropriate  for treatment of the Firestone
Salinas ground water.   The large land area  required  for treatment ponds, the
low concentrations  of  nutrients in the ground  water,  and unconfirmed ability
of  the  cultivated  plants  to treat or remove  chlorinated organics  make the
method unsuitable  and  uneconomical.   Thus,  no  further  consideration  will  be
given to  this treatment method for  implementation  at  the  Firestone Salinas
site.
                      *
2.4.4  Thermal Treatment
Thermal treatment is destruction of hazardous waste materials (solid, liquids,
gases, sludges, tars, etc.)  by  high-temperature heating.   There  are a number
of  different  thermal  treatment  technologies.   These  can  be  grouped into the
following five categories:

       •  Thermal oxidation (incineration)
       •  Thermal degradation (calcination)
       •  Vitrification (glass encapsulation)
       •  Plasma pyrolysis  (complete atomic disassociation)
       •  Nuclear  destruction  (fission,  fusion,   or  high  energy  bombardment
          reactions causing sub-atomic disassociation).

Thermal treatment would not be  economical  for treatment of the dilute concen-
trations of  chlorinated organic hydrocarbons in the  Firestone  Salinas ground
water.    However,  for  information  purposes,  brief discussions  .of  each of the
methods are presented.

2.4.4.1  Thermal Oxidation (Incineration)
Thermal oxidation  is the  reaction  of waste  material  with oxygen  in  the gas
phase.  This is a common treatment method  for.liquids such as solvents, fuels,
oils, etc.   It is also appropriate for combustible gases and solids (such as
municipal  trash  or rubber  scrap).   Treatment is  performed  in  units designed
with good air  flow  and  adequate residence time  to  allow for complete destruc-
tion.   Units  may  have  additional  fuel sources to maintain  temperature  when
treating  low  BTU  waste material.    Thermal  oxidation  units  include  liquid
injection  incinerators,  industrial  boilers,  and  kilns  (for  some  wastes),

FIR:0067-RSS2                         2-68

-------
                                                                Date:  8/22/89
                                                                Final Revision

rotary  kiln  incinerators,  fluidized  bed  incinerators  (relatively  new  tech-
nology),  fixed  or  multiple  hearth  incinerators   (used  for  incineration  of
municipal waste) and flare  stacks.  Operating  temperatures are usually in the
range of 1,600 to 2,400°F.

2.4.4.2  Thermal Degradation (Calcination)
Thermal degradation or calcination  is  a  process that degrades waste materials
by  thermally induced  chemical  transformations other  than  oxidation.    The
process  is best  suited  for solid waste  treatment.   During calcination,  water
and organics are driven  off,  and  the  organics  are  thermally destroyed.  Reac-
tion gases may also be driven off, such as hydrogen sulfide or carbon dioxide.
The inorganic waste  material  remaining after  treatment  is in a more suitable
form for  disposal.   The process  is suitable  for treating contaminated soils,
certain concentrated liquids,  sludges, and  tars.  The process has also proven
effective  for  the  concentration  and  solidification   of radioactive  waste
liquids and solids.  The process  is used commercially in smelting of some ores
and manufacture of  cement products.   Unit  configurations  include rotary kiln
furnaces,  fluidized  beds  units,  open   and   multiple   hearth  furnaces,  and
refinery  coker  units.    Operating temperatures  are  in  the range  of 1,200 to
2,500'F  (Berkowitz et al.,  1978).

2.4.4.3  Vitrification
Vitrification  is  a  combination  thermal  treatment  process  and  encapsulation
process.   Waste materials  are mixed  with  appropriate  inorganic  refractories
(silica,  alumina,  etc.)  or simply  heated (depending on  the  waste  material).
The  material  is heated  hot enough to melt or  fuse  the inorganic  components
into a glass.  The waste material is either micro encapsulated by the glass or
reacts to help form the  glass.  Organic components  in the  waste are  driven off
and thermally destroyed. < The waste after treatment is stable and suitable ^or
land burial.  -Units for  vitrification treatment include rotary  kilns, molten
salt units,  and  molten glass furnaces.   Operating  temperatures  depend on the
materials to be treated  but are usually high.
FIR:0067-R8S2                         2-69

-------
                                                                Date:  8/22/89
                                                                Final Revision'

An  alternate  version  of This  process  is  in  situ vitrification.    In  this
process  electrodes  are  inserted  into  the  ground  with  a graphite  linkage
between  the  electrodes.    A  current  is  applied  that  heats  the  graphite.
Eventually the graphite is hot enough  to melt  and fuse the inorganics to form
a molten*vitrified  glass.   Once  molten, the  glass acts  as  the conductor and
the graphite  burns  off.  .Organics may  be destroyed  or driven  off.  teachable
inorganics are either fused or encapsulated.   Melts as large as 800 tons have
been performed.   Treatment  of soil to  depths  of  50 feet is being considered.
The economics are competitive with alternative treatments.

The glass may  take  as  long as a  year  to cool  and  there  are some other tech-
nical  considerations.   The  process  is a promising  method for  treatment  of
radioactive wastes  and  waste  sites  where digging .up  of soils would  be  haz-
ardous  or impractical.   The  process  can  generate  in soil temperatures,  in
excess of 3,600°F (Buelt et al, 1982).

2.4.4.4  Plasma Pyrolysis
Plasma  pyrolysis  is an  emerging  treatment  method  that  destroys a  waste  by
passing  it  through  a plasma  gas  stream.   An  electrode assembly  is  used  to
energize  a  gas  stream.   The  gas  reaches  temperatures  between  5,000°  and
15,000°C.  Liquid waste heated by the  plasma  is completely disassociated.  It
then reforms,  into gases,  such as carbon monoxide,  nitrogen,  carbon dioxide,
hydrogen,  etc.    The  gases  are  scrubbed,  then  flared  to the  atmosphere.
Destruction efficiency is extremely high.  Currently the technology is limited
to pumpable liquids at treatment  rates  of  about 3 gpm.  Energy consumption is
high (Cheremisinoff, 1988).

2.4.4.5  Nuclear Destruction
Uncontrolled thermonuclear reactions produce temperatures exceeding 20 million
degrees  centigrade.   There  is  no doubt that  complete destruction  of  waste
materials would occur at these temperatures.   Although an uncontrolled nuclear
reaction  is  absurd for  use  as  a  waste  treatment  method,   development  of
controlled fusion technology may  provide an answer to  conventional and radio-
FIR:0067-R8S2                         2-70

-------
                                                                Date:  8/22/89
                                                                Final Revision
active waste problems in the future.  Nuclear reactors and high energy physics
units may be used to convert  some  dangerous,  long lived isotopes into shorter
lived, less  hazardous  species.  Currently  this is  not  economical  for large-
scale treatment.

This  method  is also presented to  show  the progression of  thermal  treatment
destruction  mechanisms  depending   on   the  temperature  and  energy  level.
Destruction  reactions   at  lower  (energy)   temperatures  proceed  by  molecular
rearrangement  and breaking  molecular bonds.   Higher temperatures (increasing
energy  level)  break materials down  into   atomic  components (as is  found in
plasma  processing).    At  still  higher  energy  (nuclear)   and  temperatures,
reactions occur at the subatomic level.

No further consideration will  be given to any of the thermal treatment methods
for implementation at the Firestone Salinas site.

2.4.5  Dispersed Treatment
The dispersed  treatment  option would locate treatment systems at remote loca-
tions  near  extraction  wells.    Each   system  would  operate   independently,
although  transmission  of operations  performance parameters  may be  sent  to  a
central  location  or recorded  remotely.   Each  treatment  system would process
ground water  independently.    It may  be  cost  effective to combine some of the
discharges  from remote  units  into  pipeline  headers and  send to  single or
multiple  remote locations for  discharge  (i.e.,  the Salinas River).  The number
of  treatment units would  be  determined  by optimum,  pumping requirements and
well  locations.

There  are several  disadvantages  to  dispersed  treatment.   Multiple treatment
units  would  require  added  sampling to  verify  performance of  each  system.
Maintenance  and labor  costs  would  be increased  in order to  attend to multiple
pieces  of equipment  (performing  the same  function).   Security  at nultiole
remote   locations  would  be  more   difficult   to  maintain.    The  large   lane
requirements  may  make  it difficult  to obtain  permission from property owners
to utilize larger areas  of their property.
                                                              »
FIR:0067-RSS2                         2-71

-------
                                                                Date:  8/22/89
                                                                Final Revision'

Although additional costs may be incurred to install piping to a central loca-
tion, these costs would  be  somewhat  offset  by  the economics and greater effi-
ciency with a  single,  larger treatment system.   Installation  of utilities at
multiple  locations  to  support operations  would  be more  expensive  than  if
utility services are provided to a single location.

Dispersed  treatment  would  not  be efficient  or  economical  for  treatment  of
Firestone Salinas ground water.   Thus,  no  further consideration will be given
to the dispersed treatment  option  for  implementation at the Firestone Salinas
site.

2.4.6  Centralized Treatment
The  existing  centralized  treatment  system  has  demonstrated  that  a central
treatment system is secure  and  efficient.'  The existing centralized treatment
system located within the Firestone Business Park has a proven performance and
safety record.   The location  provides  a high  degree  of security  due to the
presence of security at  the Business Park  entrance and operating personnel on
a 7-days-per-week basis.  The existing treatment system is attended during off
hours by a telephone paging system tied into  operations'  monitors.  Personnel
are available at all times during off hours to respond.  The operations record
of this  installation  demonstrates performance that  would  likely be unmatched
by multiple remote units.

A  centralized  treatment  system  is  the only  type  of  installed  remediation
equipment  considered  further for  treatment of ground water at  the Firestone
Salinas site.  Further evaluation  is included  in Sections 3.0 and 4.0.
FIR-.0067-RSS2                       .  2-72

-------
3.0

-------
                                                                Date:  8/22/89
                                                                Final Revision
                   3.0  DEVELOPING REMEDIATION ALTERNATIVES

3.1  RELEVANT SITE CHARACTERISTICS
The site  characteristics  relevant to the  remediation of  the  affected ground
water at  the  Salinas  site include the aquifer  system,  the site hydrogeology,
and the  geochemical  nature  of  the ground  water.   These  characteristics are
discussed in the following paragraphs.  Appendix F provides additional data on
aquifer characteristics.

The ground-water  aquifer  system  in the immediate vicinity of  the facility is
within three  interconnected  zones that are  designated  shallow, intermediate,
and deep.   The shallow aquifer extends from the surface  to a  depth.of about
90 feet.   The  intermediate  zone  is  about  40  feet  thick  and  is   generally
located  from  100  to  140 feet  below the  surface.    The  deep  aquifer system
locally has four distinct zones at 200-, 300-, 400-, and 500-foot depths.  The
various  water-bearing  zones  are  separated from one  another by  clay or silt
layers  (aquitards)  that have varying thicknesses and  are locally discontin-
uous.  Where  the aquitards  are thin  or discontinuous,  flow can occur between
the aquifers  above and below the  aquitard.   The shallow  aquifer has limited
use because  of its limited  capacity  during drought  years.   The intermediate
zone has  limited  use because it  is not  thick and, therefore, does not yield a
large  quantity of water.   The deep  zone  is extensively  developed  for agri-
cultural  and some domestic use.

Ground water  in the  aquifer  system around  the  Firestone site flows  generally
northwesterly.   In the  shallow aquifer  (Figure  3-1),  the local flow  direction
from the  former Firestone facility is westerly.  At a distance of about 3,000
feet to the west, the flow direction resumes the regional northwesterly trend.
On  the  basis  of  the  hydrogeologic work done for the remedial investigation,
the pathways  of chemical  movement  (Figure  3-2)  appear to be limited  laterally
to  local  ground-water channels.  The edges of these channels are of much lower
permeability  and  act  as  an  impediment  to the  lateral  spread  of chemicals in
the ground water  near  the site.   Within the layered vertical structure of the


FIR:0067-RSS3                         3-1

-------
                                                                Date:  8/22/89
                                                                Final Revision
aquifers there  are  vertical components  to the flowpaths  as well.   When the
agricultural wells are pumping, they create a  downward  flow component between
aquifers.

At the  site itself  and for  a  distance of about  3,000 feet to  the  west, the
aquHard under the shallow aquifer prevents downward flow.   However,  the aqui-
tard is  discontinuous  to  the west,  where  there is a downward  diffusion from
the surface aquifer  into the underlying intermediate zone.   The result is that
dissolved chemicals  in the surface aquifer are  mixed  and  diluted as  they dif-
fuse downward to and through the intermediate  zone.

Still farther  to the  northwest,  about 6,000  to  7,000  feet from the  former
Firestone facility,  the aquitard under the intermediate zone thins and  allows
further diffusion downward  into  the  uppermost, or 200-foot, unit  of the deep
aquifer.   The  subsequent  zone of  dilution in the deep aquifer  extends about
1,500 to 2,000  feet  to  the northwest.   Again,  regional  ground-water  flow
further  dilutes  the dissolved chemicals migrating downward from  the shallow
and intermediate units.

Finally, there  is a vertical  flow component between  the 200-foot  unit  to the
deeper units when the  agricultural wells  are  pumping.   Clay  aquitard  layers
between the  200-, 300-, 400-foot,  and  deeper water-bearing  units  are locally
discontinuous,  allowing additional  downward diffusion and  subsequent  dilution.
This zone of diffusion begins about  2  miles northwest of  the former  Firestone
facility.

Ground water has been sampled extensively  throughout  the  area  surrounding the
site.  Each of the agricultural  and domestic wells within 4 miles downgradient
(northwest)  of  the  site was located,  verified, and  sampled where access was
obtained.  On-site and  off-site monitoring  wells were also installed  to  assess
the horizontal  and  vertical  extent of  chemicals  in the ground  water and the
horizontal   and  vertical  flowpaths.   As a  result of these  samples,  combined
with each of the other  investigations done, the nature and  extent of  chemicals
in the ground water  have been defined.

FIR:0067-R8S3                         3-2

-------
                                                                Date:  8/22/89
                                                                Final Revision
Chemical  analyses  of  the wells  in the vicinity  have provided a  good under-
standing  of  the  concentrations  of  each  specific  chemical  in  the  list  of
chlorinated aliphatic  hydrocarbons and  volatile  aromatic  hydrocarbons  given
previously.  Since  the  analyses  have been repeated  over  time,  a  good history
of the concentration  changes in any given well  exists.  This  history can be
related,  in some cases,  to the performance of the  shallow aquifer ground-water
extraction   wells   and  treatment  plant.   Finally,   the  concentration  data,
combined  with  the  hydrogeologic investigations, have  determined  the vertical
and  horizontal extent  of  chemicals  associated   with the former  Firestone
facility  in the ground water.

Of  the  ten  indicator  chemicals  (Appendix  G)  defined   by  the  California
Department  of  Health Services  (DHS) for  study  at  the beginning of Firestone's
cleanup activities, three have been detected most  frequently in limited areas
of  the  ground  water:   1,1-DCA,  1,1-OCE, and  1,1,1-TCA  (Appendix  H).   The
latter two are  the most  reliable  indicators  of the presence  of  chemicals
because  they  are  found  in  more  wells  than  is the 1,1-DCA.   Samples  taken
during the  beginning  of the  extraction  well  field  and water  treatment plant
operations   show,  at  worst,   no  increase  in  concentrations and,  at  best,  a
decrease  in  concentrations   for  each  of  these  chemicals  (Appendix  I).   This
suggests  that  the extraction  wells have  stabilized the plume of contamination
and  are  reducing  the  concentration levels in  some  areas.   The largest reduc-
tions  have been  made  in the  on-site  locations  with  the highest  original
concentrations.

Samples from monitoring wells and from agricultural, domestic,  industrial, and
municipal  wells show that  the  chemical  plume ends about  2% miles  from the
former  Firestone  facility.    The  plume  of  chemicals  in  the ground  water
(chemicals  detected above the  method  detection  limits)  can be  described as
follows,  starting at the former Firestone facility:
      •  A narrow ellipse 3,000  feet  long and  1,000  feet  wide, in the shallow
         aquifer, flowing almost due west
      •  A  second  narrow  ellipse  4,000-feet-long  and  1,000-feet-wide, in the

FIR:0067-R8S3                         3-3

-------
                                                                Dates  8/22/89
                                                                Final Revision-
         intermediate zone,  flowing northwest
      • 'A third  ellipse 7,000  feet  long and  1,500 feet  wide,  in  the  deep
         aquifer,  flowing northwest.


Plumes of 1,1-OCE  and  1,1,1-TCA  in the various  aquifers  are  shown  in Figures

3-3 through  3-8.   The data upon which  these plumes are based were collected in
the:first quarter of 1989.  As shown  in  these figures,  the plume is laterally

confined to  alluvial  channels.   This  is  discussed in detail  in  the Remedial

Investigation  report  (IT,  1988a).    These  plumes  and  the extensive  hydro-

geological  studies  reported  earlier  are   the  basis  for 'location  of  the

extraction wells  as discussed  in  Section  3.2.


Concentrations of  1,1-OCE and 1,1,1-TCA  are used  throughout  this  report as

indicators of  remedial  trends for  all the  chemicals  found at the  site.   The

reasoning behind  this is:

      •  Continual  observations  in the we-lls  monitored  suggest  that concen-
         trations  of all  chemicals will  drop  below their  action  levels,  and
         often the detection  limits as well, before  1,1-OCE  levels reach the
         6 ppb California DHS Action Level,  the  cleanup  level  chosen for this
         compound.

      •  Monitoring and  reporting  of  1,1,1-TCA  levels  is done  because  that
         compound  is the precursor to  1,1-OCE actually found.   The degradation
         of  1,1,1-TCA to 1,1,-OCE is discussed in Section 1.4.3 of this FS/RAP
         report.


3.2  EXTRACTION ALTERNATIVES

Review  of  the plume maps  (Figures 3-3  and  3-4)  shows  that the currently

operating,  shallow  aquifer   extraction  wells,  S-7,  S-8, S-10,   S-ll,  M-l,

IT-SE2,  IT  SE3,  IT-SE4, and  IT-SE5 are  located  in  the  areas of the shallow

aquifer plume  with  the  highest  concentrations.    (Extraction well  S-9 is very

shallow and   is not currently  operating.)   Thus,  no modifications of locations
were needed  for the shallow aquifer remediation.


The plume maps for the  120-foot  aquifer  (Figures 3-5  and 3-6)  show some wells

above the cleanup  levels  presented on page  2-6.   Thus,  a series  of potential

locations for extraction wells  was  considered  to  be   installed  into  the


FIR:0067-R8S3                         3-4

-------
                                                                Date:  8/22/89
                                                                Final Revision
intermediate (120-foot) aquifer.  The potential well  locations  considered are
shown as  wells  IT-IE-1  through IT-IE-10  in Figure  3-9.   These wells  were
located  on the basis of the following criteria:
      •   Relatively high concentrations  of chemicals in the ground water
      •   Anticipated high-permeability geological flow channels (this will be
         confirmed during installation of the wells)
      •   Relative ease of access, where  possible,  for complete coverage of the
         plume.

From  these  potential   locations,  six  combinations  of  well   locations  were
analyzed.  These combinations are listed  in  Table 3-1, and the well  locations
and  flowrates  are  shown  in  Figures  3-9a through  3-9f.    These  combinations
include  configurations  aligned  along  the axis of the  chemical  plume, perpen-
dicular  to  the axis, a diamond  pattern  over the  plume,  and  a  cross  with the
long leg along the axis of the plume and the short leg across the axis.

Computer  simulations were  made for  each of  these  combinations.    The  most
efficient remedial  alternative  was  Alternative  6,  listed  in  Table  3-1.  This
alternative  consists  of five extraction  wells  aligned along the  axis of the
plume in the 120-foot aquifer.

This  extraction  alternative  was used to  develop  the  site-specific  remedial
action alternatives  discussed in Section  3-5.   Figures 3-10 through  3-13 show
the extraction well  locations for each remedial  action alternative.  The other
extraction   alternatives   in   Table   3-1   were   screened   from   additional
consideration.

3.3  TREATMENT ALTERNATIVES
The  five  treatment  alternatives  that  have  been   identified  as.  possible
strategies  to  be evaluated  for  implementation  at the  Firestone  Salinas  site
are as follows:
      •   Activated carbon treatment
     . •   Air stripping

FIR:0067-R8S3                         3-5

-------
                                                                Date:  8/22/89
                                                                Final Re vis-ion
      «  Natural or enhanced dilution/degradation
      •  Combined strategies
      •  Agricultural spraying.

These will be  discussed  individually in this section  and  evaluated in detail
as these alternatives  are  part of the  site-specific remedial  action alterna-
tives." in Section 4.0.

3..3.1  Activated Carbon Treatment
As part of interim remediation measures,  Firestone  installed two 20,000-pound
capacity activated carbon adsorbers.  These  two  units  are  piped to operate in
series  and have a continuous  treatment capacity of 500 gpm.    The  units are
charged with  virgin  activated carbon.   Currently,  a  majority  of  the ground
water pumped  from  the extraction wells,  is  routed through  the carbon units,
and  returned  to  the  Salinas   River   through   a  14-inch  diameter  outfall.
Monitoring of the concentrations of  organic contaminants  in  the  influent,
between the  beds,  and effluent  is  used to determine  the  frequency of carbon
replacement.     Carbon  replacement  is   a  simple  operation  requiring  minimal
downtime.  Spent carbon  is sent  for regeneration back to the  supplier.   The
existing carbon unit has demonstrated high efficiency  and  reliability for the
Firestone  Salinas  ground  water.    Thus,   activated  carbon  treatment  is
appropriate,  should continued treatment be required.

3.3.2  Air Stripping
An air  stripper  column was  installed at the  Firestone  Salinas  site as part of
the interim remediation measures that were implemented.  The intent of the air
stripper originally  was  for  pretreatment of  ground  water  before  processing
through the  carbon unit.   The existing air  stripper  has  performed exception-
ally well and  has  demonstrated that air stripping  treatment -alone is capable
of removing the volatile organic contamination in the Firestone Salinas ground
water below  the NPOES permit  levels for discharge of water into  the Salinas
River.    The  Firestone  Salinas air   stripper  has   features  that  optimize
performance  and  economy.    These include a  redistributor  within  the column,
high efficiency tower parking, and a variable speed blower.  Air stripping has

FIR:0067-R8S3                         3-6

-------
                                                                Date:  8/22/89
                                                                Final Revision
demonstrated greater  economy  over carbon treatment.   The  local  air district
allows  direct  discharge  of  the  stripper  exhaust  to  the  atmosphere  within
permitted limits.-

The permitted limit and hydraulic capacity  are  the  current limitations on the
existing air  stripper.    The  treatment capacity  of  the air  stripper is cur-
rently  limited to  180 gpm.    The performance  of  the  existing air stripper has
demonstrated that air stripping  is  appropriate,  should continued treatment be
requ i red.

3.3.3  Natural Biological  Degradation/Dilution
Natural biological  degradation of most chlorinated  synthetic organics occurs
very  slowly  in  the environment.   The problem  is two-fold.   First  there are
limited  bacterial  species  that  can  perform  this type of  conversion..   Some
chlorinated organic  compounds are not degraded  to  any  significant  degree in.
the environment because they are not usable by the available natural  bacteria.
Enhancing  bacterial   action  by  supplying  a  specific  strain  is  limited  to
finding suitable strains of bacteria that will perform the conversion.

The  second problem  is the deficiency of  nutrients  to  stimulate   bacterial
growth.  Chlorinated  organics are usually found  in  very dilute concentrations
when  released  into  the  environment.   Without  additional  nutrients, natural
bacteria grow and  reproduce very slowly.    The  limited numbers of cells would
degrade  chlorinated  organic materials at  a very slow  rate.   Aromatic hydro-
carbons  also  occur  in  very  dilute  concentrations  in  a limited area  of the
site.   They can be degraded,  but they are not widespread throughout  the plume.
They occur primarily near the  southwest corner of the building.

Due to  these  two  limiting factors,  relying  only on natural degradation of the
chlorinated organics  in the Firestone Salinas ground water would require many
years for  concentrations  in the ground water  to  return  to acceptable  levels.
FIR:Q067-RSS3                         3-7

-------
                                                                Date:  8/22/89
                                                                Final Revision
The aquifers  beneath  the  Firestone site are  high  quality and possess reason-
able  permeability.    Natural  dilution, removal,  and  recharge  will  be  the
primary  means for  lowering  organic concentrations  in the  various aquifers.
Even without operation of extraction wells, tremendous quantities of water are
removed  from  beneath the  site by  agricultural  water wells.   Some  of  these
wells  draw from both  shallow  and  deep   aquifers.    Additionally,  natural
recharge  of  the aquifer  from the  Salinas  River and  from the surrounding
mountains  dilutes  ground  water  significantly.    Although  the  process  may
require  several   years,  natural  and  induced dilution  and  flushing  of  the
aquifer would eventually bring organic contamination levels down to acceptable
levels.

3.3.4  Combined/Additional  Strategies
Under  the  interim  remediation strategy,  an  air  stripper  and  an activated
carbon  unit  were  installed   to  be  operated   in  series   (Figure  3-14).   Two
processing units were proposed for  economy  and environmental  protection.  Air
stripper  treatment  before  carbon  treatment of a process  stream  would extend
the life  of the  carbon significantly.   Since operation  began,  it  was demon-
strated  that  air stripping  or carbon  treatment  alone are both  effective in
removing  the  volatile  contamination  in  extracted  ground-water  streams.
Balancing  of  flows  by  directing   streams  with high  concentrations preferen-
tially  to the air  stripper  has maximized  plant treatment capacity and mini-
mized  carbon  changeout  cost.   The  current   plant  capacity is  650  gpm  and
requires   carbon   changeouts   only   twice   per  year,   with   the   current
concentrations.

Air stripping is more economical   and  equally effective  as  carbon  treatment.
In  hindsight,  the carbon  unit would not be  necessary providing an  air permit
were obtainable  to  discharge  all  pollutant  exhaust from  a larger air stripper
to  the atmosphere.   However,  to meet  treatment  capacity requirements,  the
economics does not  justify replacement  of  the existing carbon unit  with a new
air stripper  this late in the project (based on projected cleanup scenarios).
FIR:0067-R8S3                         3-8

-------
                                                                Date:  8/22/89
                                                                Final Revision
Other possible combined treatment  alternatives,  although effective, would not
be economical when  compared  against the inherent value  and operating cost of
the existing treatment system.

3.3.5  Agricultural  Spraying or Flooding
Aeration by  agricultural  spraying  or flooding is a "simple means to remediate
the ground water. This is currently being  done defacto from the deep aquifers
on an intermittent basis.   There are, however, several restrictions that limit
the usefulness of this alternative as a continuous process.

Agricultural  consumption  of water  will  not  coincide  with the  water supply,
thus requiring storage of  water or  shutdown  of  wells.   Agricultural spraying
is only  performed on  young  crops.   Furrow irrigation is the preferred method
of  irrigation for.  most  of  the  growing  season.    Agricultural  spraying or
flooding is a good way to utilize extracted ground water, but again the demand
is not always constant.

The  hydrogeology  of  the  area  shows that  the Salinas  River  as well  as  the
surrounding  mountains recharge  the  underground aquifers.    Pumping  treated
water to the river  simply returns  the ground  water  to  be used as required by
agricultural consumers upon demand.   Simply pumping  to the river is more  cost
effective  and minimizes  any  adverse public  reaction  to  other  water  uses.
Agricultural  spraying  is  considered  further  in  Section  4.0,  with  respect to
the deep aquifer.

3.4  DETAILED ANALYSIS OF DISPOSAL ALTERNATIVES
This  section briefly  describes  and analyzes disposal   alternatives  for  the
treated ground water  at the  former Firestone facility.   These disposal alter-
natives are  as follows:
      •  Alternative S:  Stream disposal - Section 3.4.1
      •  Alternative T:  Injection  -  Section 3.4.2
      •  Alternative U:  Holding ponds., lagoons, or basins  - Section 3.4.3
FIR:0067-R8S3                         3-9

-------
                                                                Date:  8/22/89
                                                                Final Revision
The  discussion  for  each  disposal  alternative  includes  identification  and
summary of  the alternative,  advantages and disadvantages  of  the alternative,
and the procedure for monitoring treatment plant affluent concentrations.

3.4.1  Alternative S - Stream Disposal
Alternative S  is the discharge of  treated ground water to the  Salinas River
channel.   This  is  the alternative  implemented  during  the  interim  remedial
measures started in February 1986 and continuing to the present (1989).

This  alternative consists  of pumping  the treatment  plant  effluent  into  a
pipeline, approximately 1  mile long, which runs from the treatment facility at
the former  Firestone  facility to  a discharge  point at  the Salinas  River.   An
NPDES  permit  was obtained  for a  maximum discharge  of 1000 gpm and startup
flows  not  to  exceed 250 gpm.   The Salinas River generally has  limited flow.
During the high water seasons, the river flows directly into the Monterey Bay;
however, the majority  of  the time the river  is  intermittent  and water infil-
trates into the ground before it reaches the bay.

Discharging into stream channels has been used for many years  for the disposal
of various treated waste water.  There  are several advantages  of this disposal
alternative.  The treated  wastewater at the former Firestone facility consists
of clean water and  is  returned  for  future use.  That is, there is no consump-
tive use of the water, except for a very small loss in the air stripper and in
the effluent  tank  (14 gallons out  of  775,000 gallons treated daily).   Clean
water  returned  to the  aquifer does not  place limitations on the  water use,
which  is  an important  advantage  of this  alternative.   Another  advantage of
this disposal  alternative  is that the  NPDES  permit required  for disposal  has
already been issued.  It will only require renewal.

A  disadvantage  of this alternative  is that  there is  a small  loss  of water
through evaporation and evapotranspiration after  the  water is discharged into
the Salinas River and before it infiltrates into the river bed.
FIR:0067-R8S3                         3-10

-------
                                                                Date:  8/22/89
                                                                Final Revision
For  this  alternative,  the  discharge water  is  monitored  at  the  treatment
facility and  at the  river  outfall,  and discharge  into  the  river would  be
discontinued  immediately,  if  effluent  concentrations  were  found  to  exceed
limits listed in the NPDES permit.

3.4.2  Alternative T - Injection
Alternative T consists of  injection of the treatment plant  effluent into the
aquifer from which  it was withdrawn.   The  injection of  liquid wastes, in this
case treated ground water, has  been widely  adopted as a common waste disposal
practice in the United States.  The most common type of injection well is that
used to return brine  extracted  during oil  and  gas field pumping.  The purpose
of the procedure is to iso.late  the  substance  from the biosphere.  In the case
of injection wells  at the former Firestone facility, the  purpose would be to
return clean usable water to the aquifer for downgradient uses.

The  advantages  of  injection  are that there is  no evaporation  of the water,
clean water  returned  to  the aquifer  does not  place limitations on water use,
and discharge pipelines can be avoided.

However, there  are  several   drawbacks  in the  use  of  injection  wells for dis-
posal.  Well  plugging is very  common  and requires that  the  well be taken out
of service  and  treated  before  it can  be returned  to  use.   An example of this
type  of  problem occurred at  the Ashworth  Brothers Metal  Plating Co. located
approximately 3 miles upgradient of the  former Firestone facility.  Addition-
ally,  if  water  with different chemical  characteristics  is  returned  to  an
aquifer,  the result  can be the dissolution  of  unwanted minerals  that can
degrade the quality  of  the  ground water,  possibly affecting  its  use.   This
alternative would require a  new NPDES permit and,  consequently, preparation of
the  associated  application   documents,  public  hearings,   meetings,  and  the
required time for regulatory review.

For  this alternative, the water being discharged into the  injection  well would
be monitored  at the  treatment  facility, and  discharge  would  be  discontinued
                                                                              »

FIR.-0067-R8S3                         3-11

-------
                                                                Date:  8/22/89
                                                                Final Revision
immediately, if effluent concentrations were found  to  exceed limits listed in
the NPDES permit.

3.4.3  Alternative U - Holding Ponds, Lagoons,  or Basins
Alternative U consists of discharging the  treatment plant  effluent into hold-
ing ponds,  lagoons,  or basins, which allow the water  to  infiltrate  into the
ground and to evaporate.  This type  of  operation has been a common waste dis-
posal practice for many years.  The  liquid waste,  in this case treated ground
water, is  placed  in unlined  ponds,  lagoons,  or basins and  allowed to infil-
trate into the ground  or  to evaporate,  either  directly or by evapotranspira-
tion.  The reason for using this  method  at the former Firestone facility would
be to return clean, usable water  to the  aquifer for downgradient uses.

Ponds, lagoons, and  basins  have  been used  for  many years  for the disposal of
various treated waste  water.   The following are some  of  the advantages.   The
treated waste  water, which consists of clean  water at the  former Firestone
facility,  is  returned for  future  use.   Clean  water returned  to  the aquifer
does not place limitations on water use, and extensive discharge.pipelines can
be avoided.

The major drawback  in  the use  of  this alternative  for waste water disposal at
the former Firestone facility  is the potential  flooding of some of the nearby
farmland, which  is at a  lower elevation  than  the  holding  pond.s,  lagoons, or
basins.  Crops with critical water needs are grown near the facility/ and could
be harmed  by  excessive water.  Additionally, during  harvest times, saturated
ground would  make  the  use  of farm  equipment  difficult.   A  further concern
would be  the  plugging of  the  bottom of the ponds,  lagoons,  or basins.   This
would require  that the operation  be stopped until  the problem was corrected.
Also,-, the  chemical characteristics  of  the water can  change  as it percolates
downward.  The result can  be the  dissolution of unwanted natural minerals that
can  degrade  the  quality  of  the  ground  water, thereby  making  it unusable.
Also, water can be  lost for reuse  by evaporation or evapotranspiration.  This
alternative would  require  a  new  NPDES permit, with  the  concomitant  public
FIR:0067-R8S3                         3-12

-------
                                                                Date:  8/22/89
                                                                Final Revision
hearings, meetings, and  time  required  for regulatory review,  (minimum of 180
days).

For this alternative,  the  water being discharged  into  the  ponds, lagoons, or
basins would  be  monitored  at the  treatment facility and at  the outfall with
discharge being discontinued  immediately  if effluent concentrations are found
to exceed limits listed in  the NPDES permit.

3.4.4  Summary of Discharge Alternatives
Alternative  S,  discharge  of  treated ground  water  to  the  Salinas  River, is
considered the most appropriate and  the most  time and cost-effective disposal
alternative for the Firestone site, based on IT's analysis of the three  alter-
natives.   Alternative  S  is protective of  the environment,  returns  a natural
resource for  future use, and does not have the  potential environmental proo-
lems associated with Alternatives T  and U.   Alternative S returns clean water
to the  aquifer,  and the NPDES  permit required  for  this disposal alternative
has already  been  issued.  The  discharge water  is monitored  at the treatment
facility and  at the river outfall, and  discharge into the  river  is discon-
tinued  immediately if  effluent  concentrations   are found  to  exceed  limits
established in the NPDES permit.

Alternative T consists  of  injection of the  treatment plant effluent into the
aquifer  from which  it  was  withdrawn.   Although Alternative  T returns water to
the  aquifer,  there are  a  number  of  potential  problems  associated  with  this
alternative, including the following:
      -  Well plugging is  very common.
         Injection  of  water  with different  chemical  characteristics into the
         aquifer can  result  in dissolution of unwanted minerals and degrada-
         tion of ground-water quality.

Alternative  T  would   require   a   new   NPDES  permit  (minimum  of   180  day
processing).    Potential   well  plugging  would  increase down  time  for  the
treatment plant.
FIR:0067-R8S3                         3-13

-------
                                                                Date:  8/22/89
                                                                Final Revision
Alternative V consists of discharging the  treatment  plant  effluent into hold-
ing ponds,  lagoons,  or basins, which allow the water to  infiltrate  into the
ground or  to evaporate.   This  alternative would  also return  water  to  the
aquifer,  but potential environmental  drawbacks  include the following:
      °  Potential flooding"of nearby farmland
      °  Potential adverse  effects  of excessive  water,  including  effects on
         crops;wi'th specific water requirements"and difficulties in the use of
         farm equipment on saturated  ground
      •  Potential for plugging of the bottom of the ponds, lagoons, or basins
      •  Potential for  dissolution of  unwanted minerals  and degradation of
         ground-water quality.

This alternative  would also  require  a new  NPDES permit,  with the concomitant
public hearings, meetings, and time required for regulatory review (minimum of
180 days).

3.5  SITE-SPECIFIC REMEDIAL ACTION ALTERNATIVES
As discussed  in the  previous  sections,  the treatment alternatives have been
screened  to carbon adsorption, air stripping,  or a combination of these.  The
disposal   options  were  screened   to  discharge   into  the Salinas  River.   The
extraction  alternatives  consist  of combinations  of  pumping  from  the shallow
and intermediate  aquifers,  and different .schedules  to initiate  pumping from
each aquifer.

The experience gained from operating  the interim remedial  measures since early
1986  demonstrates that  the  recovery can  be  optimized  by allowing  the site
manager  a  large  degree  of  flexibility  in adjusting  the  flowrates  in  the
individual  wells  on  the  basis of  the monitoring data.  The  general  criteria
used by the site manager are as follows:
      •  Maximize the flowrate from  affected wells up to  a  comoined  flowrate
         equal tc the treatment plant capacity
      •  Cycle the pumping rate,  if this proves to be efficient in remediation
FIR:0067-R8S3                         3-14

-------
                                                                Date:  8/22/89
                                                                Final Revision
      •  Pump the highest flow from the wells  with  the highest concentrations
         of chemicals

      •  Discontinue pumping as  the  concentrations  in a well  decrease to the
         cleanup  levels,  and  possibly  sooner  if  there  is  an  adjacent  or
         downgradient well  that will  capture the chemicals faster

      •  Direct  the  flowstream  with  the  highest   concentrations  to  the
         airstripper and the lowest flowstream to the carbon adsorption unit.


These procedures allow maximizing the recovery from the aquifer.


3.5.1  Approach

The  primary  objective  of  the feasibility  study remedial  action plan  is  to

ensure that appropriate remedial  alternatives are developed and evaluated that

protect  human  health and the  environment  and  are  appropriate to  the site's
problem.   The  EPA Draft Guidance  for Conducting Remedial  Investigations and

Feasibility Studies  Under CERCLA (March 1988, hereinafter  referred  to as EPA

RI/FS  guidance  document)  provides guidance for development  of alternatives.

Although the  risk  assessment  (IT, 1988b)  has shown  there  is no unacceptable

health or environmental risk, this guidance document was followed.


Alternatives  for  remediation  are  developed  by assembling   combinations  of

technologies into alternatives.  This  process  of six  general  steps  is briefly
discussed below:

      STEP 1 -  Develop  remedial  action objectives  specifying the contaminants
      and  media of  interest,  exposure pathways,  and remediation  goals  that
      permit  a range  of   treatment   and   containment   alternatives  to  be
      developed.   The objectives developed  are  based on contaminant-specific
      ARARs, when available, and risk-related factors.

      STEP 2  - Develop general  response  actions for  each  medium of  interest
      defining  containment,  treatment,  excavation,  pumping, or other  actions,
       singly  or in  combination,  that  may  be  taken  to  satisfy  the  remedial
       action objectives for the site.

       STEP 3  - Identify volumes  or  areas of media to which  general  response
       actions  might  be applied,  taking  into   account  the  requirements for
       protectiveness  as  identified in the  remedial action  objectives and the
       chemical  and physical characterization of  the site.
FIR:0067-R8S3                         3-15

-------
                                                                Date:  8/22/89
                                                                Final Revis.ion
      STEP 4 - Identify and screen the technologies applicable to each general
      response  action   to  eliminate  those   that  cannot   be  implemented
      technically at  the  site.    The general  response  actions ' are  further
      defined to specify remedial  technology types (e.g., the general response
      action  of  treatment  can be further  defined  to  include chemical  or
      biological  technology types).

      STEP 5  -  Identify and evaluate  technology  process options to select a
      representative   process   for   each   technology    type    retained   for
      consideration.  Although  specific processes  are selected for alternative
      development and  evaluation, these  processes  are   intended to  represent
      the broader range of process options within  a general  technology type.

      STEP  6  -  Assemble  the   selected  representative  technologies  into
      alternatives  representing   a  range   of   treatment  and  containment
      combinations,  as appropriate.


Step  1   has  been performed  in  the  RI.   The  other  steps   are   discussed  in

Section 2.0 of  this FS/RAP.   The remaining  activity required  in  developing

alternatives  is  combining  and assembling  representative  technology  process

options to specific alternatives.   At a  minimum,  EPA guidance states that at
least one  representative  process  option  from  each technology  identified  as

potentially applicable should  be developed.


The  "Site  Mitigation  Decision: Tree"  and  the current  NCP  rule state  that
developed alternatives should  include the following:

      •  .A no-action alternative

      •  Alternatives  involving off-site treatment or disposal

      •  Alternatives   that attain  applicable or relevant  public   health  or
         environmental standards

      •  Alternatives   that exceed  applicable or relevant  public   health  or
         environmental standards

      •  Alternatives  that do  not  attain  applicable  or  relevant  public health
         or  environmental   standards  but  which  meet  CERCLA's  objective  of
         adequately  protecting  public health, welfare, and the environment.


The proposed rule and  draft guidance do not specify that alternatives identify

different  levels  of ARAR attainment, but rather  concern themselves  with the
FIR:0067-R8S3                         3-16

-------
                                                                Date:  8/22/89
                                                                Final Revision
time required to reach remediation goals.  The proposed rule was considered in
this FS/RAP because it indicates current regulatory direction.

This  FS/RAP  study is  limited  to  the  remediation   of  contaminated  ground
water.  As such, the remediation effort can be considered to be a ground water
response action.  The draft EPA RI/FS guidance document states that:
      For ground water response  actions,  alternatives  should address not only
      cleanup  levels  but  also  the time  frame  within  which  the  alternatives
      might  be achieved.    Depending .on specific  site  conditions and  the
      aquifer  characteristics,  alternatives  should be developed  that achieve
      ARARs  or other  risk-based  levels  determined to  be  protective  within
      varying  time  frames  using  different  methodologies.    For  aquifers
      currently being used as a  drinking  water  source, alternatives should be
      configured that would  achieve  ARARs or risk-based  levels  as  rapidly as
      possible.

The NCP  proposed  rule states that a limited number of  remedial  alternatives
utilizing  one  or  more  technologies  that  attain site-specific  remediation
levels within  different time frames  should  be developed.   Also, the no-action
alternative  should.be  developed.  If there  is  reason  to believe that innova-
tive  technologies  may provide  superior performance compared  to demonstrated
technologies,  these should also  be developed.   No innovative technologies are
known to  exist for which  an  alternative should  be developed  for the Salinas
site.

3.5.2  Developed Alternatives
For the  site-specific remedial   action  alternatives developed  in this FS/RAP,
we  propose  that the  site manager  continue  to  apply  the criteria  listed in
Section  3.5  to optimize the aquifer restoration.  The  screened alternatives
from  this  FS/RAP  are discussed  in  detail   in  Section  4.0.    The following
paragraphs outline the alternatives.

Alternative  A  is  the  no action  alternative.   This alternative is required by
regulatory  guidelines and  is   considered as  a  baseline  alternative.    This
alternative  consists  of discontinuing  the current extraction and   treatment.
The monitoring wells  would continue  to be monitored  until  2  years after the

FIR:0067-R8S3                         3-17

-------
                                                                 Date:   8/22/89
                                                                 Final  Revision
 ground-water  cleanup  levels are achieved  by  natural  dilution,  degradation,  and
 diffusion.

 Alternative  B consists of  continuing to extract  and  treat ground water  from
 the shallow  aquifer.  No extraction will  be  done in the  intermediate  aquifer.
 The pumping  will stop when the shallow aquifer extraction wells  show concen-
 trations  have remained  below  the  ground-water cleanup levels.  Treatment  will
 consist  of  combined air stripping and  carbon adsorption when the flowrate is
 over 180 gpm  and air stripping only when the  flowrate  is less than  180  gpm.
 In each  of  these  cases, the  effluent  is discharged  into the Salinas  River.
 Monitoring will  continue in  the  shallow and  intermediate aquifers until  the
 concentrations have  remained  below  the  ground-water cleanup  levels  for  two
 uninterrupted years.

 Alternative  C consists of  continuing to extract  and  treat ground water  from
 the shallow  aquifer and simultaneously pumping and treating ground water  from
 the intermediate aquifer.   Each well  in this alternative.will  be  pumped  at its
 maximum  capacity.   This will  result in  a combined  flowrate that  exceeds  the
 current  treatment plant capacity of 650 gpm. Thus,  a  new 500  gpm air  stripper
 will  be  installed.   Extraction  will  continue in  each  well   at the  maximum
 flowrate  until  the  ground-water  cleanup   levels are achieved   in  both  the
 shallow  and  intermediate aquifers.   Treatment will consist of combined  carbon
 adsorption and air  stripping  with the existing air stripper as well as  with a
 new air  stripper.   The effluent will  be discharged  into the Salinas  River.
 Monitoring will  continue in  the  shallow and  intermediate aquifers until  the
 concentrations have  remained  below  the  ground-water cleanup  levels  for  two
 uninterrupted years.

.Alternative  D consists of  continuing to extract  and  treat ground water  from
 the shallow  aquifer and simultaneously pumping and treating ground water  from
 the intermediate aquifer,   as  in  Alternative C.   However, for Alternative D,
 all the  wells will  not  be  pumped  at their  maximum flowrate.   Rather,  the
 combined  flowrate will  be  maintained at or  below the  capacity of the  existing
 FIR:0067-R8S3       .           .        3-18

-------
                                                                Date:  8/22/89
                                                                Final Revision
treatment plant of 650 gpm.  Thus, no modification of the treatment plant will
be needed.

Extraction will continue until the ground-water cleanup levels are achieved in
both the  shallow and intermediate  aquifers.   Treatment will  consist of com-
bined carbon  adsorption  and air stripping with the  existing treatment plant.
The  effluent  will  be discharged  into  the  Salinas  River.    Monitoring _wi 11
continue  in  the  shallow and  intermediate  aquifers  until  the concentrations
have  remained  below the  ground-water  cleanup   level  for  two  uninterrupted
years.

Alternative E  consists  of  continuing  to extract  and  treat  ground water from
the shallow aquifer  and  simultaneously pumping  and  treating ground water from
the  intermediate  aquifer,   like Alternatives  C  and D.   However,  only two new
extraction wells  will be  installed in  the  intermediate aquifer.   This will
result  in  a   combined  flowrate  of  less  than  the  current  treatment  plant
capacity  of  650 gpm.   Extraction will  continue  in  each well at  the maximum
flowrate  until  the  ground  water cleanup levels are  achieved.   Treatment will
consist of combined  carbon  adsorption  and  air stripping with the  existing air
stripper  as long as  the flowrate exceeds 180 gpm.  At flowrates below  180 gpm,
only the  airstripper will  be used.   The effluent will  be discharged  into the
Salinas  River.   Monitoring  will  continue  in  the  shallow  and   intermediate
aquifers  until the concentrations have remained below the ground-water cleanup
levels for two uninterrupted years.
FIR:0067-R8S3                          3-19

-------
8



$
                                                                4.O

-------
                                                                Date:  8/22/89
                                                                Final Revision
              4.0  DETAILED ANALYSIS OF REMEDIATION ALTERNATIVES

This section  presents  a detailed analysis  of the alternatives  assembled and
described in Section 3.0, Developing Remediation Alternatives.  These alterna-
tives  are  analyzed for  their effect  on  the mitigation  of chemicals  in the
ground water.   The scope of treatment alternatives for  this  FS  is limited to
the use  of  air stripping and carbon filters  based  on  the treatment screening
presented  in  Section  2.0.    The various  pumping  alternatives  developed  in
Section 2.0  have  been  combined  with  treatment  alternatives  to develop  a
limited  number  of  remediation  alternatives   for   aquifer   restoration  in
Section 3.0.   As  a result,  the alternatives  developed  in   Section 3.0 are
limited to five based on the initial screening.

The purpose of the detailed analyses of alternatives is to analyze and present
relevant  information   to  allow comparison  of  alternatives,  selection  of  an
appropriate  remedy,  and  demonstration  of  satisfaction  of  the  statutory
requirements in the ARARs.

The criteria  utilized  to evaluate  alternatives  are presented in Section 4.1.
The current  NCR rule  states that  refinement  and specification  in  detail  of
alternatives  which remain  after the  alternative  screening  steps  have been
performed are required as part of the detailed analysis of alternatives.  Each
alternative is further developed in Section 4.2.  An evaluation and comparison
of  alternatives  for each  criteria are  presented in Section 4.3.   A summary of
the detailed analyses  is presented  in Section 4.4.

4.1  DETAILED ALTERNATIVE ANALYSES  CRITERIA
The  following current  and  proposed regulations  and  guidance documents have
been reviewed  to determine  appropriate criteria  to be  utilized  in performing
the detailed analysis  of -alternatives:
       •  California Department  of   Health Services, 1986,  the California Sits
         Mitigation Decision  Tree  Manual, Toxic  Substances Control Division,
         Alternative Technology and Policy Development Section, May.
FIR:0067-RSS4                         4-1

-------
                                                                Date:  8/22/89
                                                                Final Revision
      •  EPA,  1982,   The  National  Oil  and  Hazardous  Substances  Pollution
         Contingency  Plan under CERCLA,  as  amended, 47 FR 31203, July 16.

      •  EPA,   1985b,   "Guidance  on   Feasibility  Studies   Under   CERCLA,"
         EPA/540/G-85/003, June.

      •  EPA,  1988a,  "Draft Guidance for  Conducting Remedial  Investigations
         and  Feasibility  Studies  under CERCLA,"  OSWER Directive  9335.3-01,
         March.

      •  EPA,  1988c,  The National  Oil and  Hazardous  Substances  Pollution
         Contingency  Plan, proposed,.rule, 53 FR  51394, December 21.


The current  NCP  rule  states  that the detailed  analysis  of  alternatives shall

include the following components:

      •  Detailed cost estimation, including operation  and  maintenance costs,
         and distribution of.costs over  time

      •  Evaluation in terms  of engineering implementation,  reliability,  and
         constructibility

      •  An assessment of  the  extent  to which  the  alternative  is  expected to
         effectively  prevent,  mitigate, or minimize  threats to,  and  provide
         adequate protection  of public  health  and  welfare and the  environ-
         ment.   This  shall include an  evaluation  of the extent to  which  the
         alternative  attains or exceeds  applicable  or relevant and  appropriate
         federal  public   health  and  environmental  requirements.   Where  the
         analysis  determines   that  federal  public  health  and  environmental
         requirements are not  applicable   or  relevant  and appropriate,  the
         analysis shall,  as appropriate,  evaluate the  risks  of  the  various
         exposure levels  projected or  remaining  after  implementation  of  the
         alternative  under consideration.

      •  An  analysis of  whether  recycle/reuse,  waste  minimization,  waste
         biodegradation,   or  destruction  or  other  advanced,  innovative,  or
         alternative  technologies  is appropriate to  reliably  minimize  present
         or future threats to public  health or welfare or the environment

      •  An  analysis  of  any  adverse  environmental  impacts, methods  for miti-
         gating these impacts,  and costs of mitigation.


The DHS Decision  Tree states  that five criteria are  utilized  in the detailed

analysis of  alternatives.  The  criteria  are technical,  institutional,  cost,

public health,  and environmental  impact analysis.   The  criteria presented in

the Decision  Tree were  based  primarily on two  EPA  publications available at


FIR:0067-R8S4                         4-2

-------
                                                                Date:  8/22/89
                                                                Final Revision
the  time.    These  two documents  are  "Draft  Methodology  for Screening  and
Evaluation of Remedial Responses"  (prepared by JRB  Associates, McLean, VA for
EPA  Municipal  Environmental  Research  Laboratory,  Cincinnati,  Ohio;  and  EPA
Office of  Emergency and  Remedial Response, Washington,  D.C.,  March 16, 1984)
and "Guidance on Feasibility Studies under CERCLA" (EPA, 19855).

Although the  proposed  NCP rule  revision  at 53 FR 51394 has  not  been promul-
gated  and  the March 1988  RI/FS  guidance document  has  only been  issued  as a
draft  document,  these  documents  provide information on  the current direction
of  EPA  regulations  and  guidance.   DHS  recommended  that  these  recent  EPA
guidance  and  rules  be   followed   preferentially  over  the   California  Site
Mitigation  Decision Tree  Manual  when  the  two documents  conflicted  (William
Owen DHS, personal communication, March 15, 1989).

The  preamble to  the  proposed  NCP  rule  revision  states  "the RI/FS  process
proposed  today  incorporates  statutory  requirements,   reflects   the  program
management principles  of  the bias  for  action, streamlining,  and  site manage-
ment planning, and  builds  on the engineering  and  analytical steps established
in the current NCP."  The proposed rule includes criteria presented  in the DHS
Decision Tree  and  the  current  NCP  rule  in  a.  revised  format based on  previous
experience.    The  proposed  rule   criteria  are  utilized  for  the   detailed
evaluation of alternatives for this FS/RAP.

The  NCP  proposed  rule defines  nine criteria for  alternative evaluation  as
follows:

       (A)   Overall  protection of  human  health  and the environment.   Alter-
       natives  shall be  assessed as  to whether  they  can  adequately  protect
       human  health  and   the environment  from  unacceptable  risks posed  by
       hazardous substances,  pollutants, or contaminants present at the site by
       eliminating,  reducing, or controlling  exposures  to  levels established
       during  development  of  remediation goals.   This  is a threshold  require-
       ment and the  primary objective of the remedial program.
FIR:0067-RSS4                         4-3

-------
                                                                Date:  8/22/89
                                                                Final Revision
      (B)   Compliance  with ARARs.   The  alternatives shall be  assessed  as to
      whether they attain  applicable or  relevant  and appropriate requirements
      (ARARs) of other Federal and State environmental  and  public health Taws
      or provide  grounds  for invoking  one of  the waivers  included in  the
      proposed rule.   Compliance  with  ARARs is a threshold requirement.  All
      alternatives remaining in the final analysis  shall meet ARARs  or obtain
      ARAR  waivers.

      (C)   Long-term  effectiveness  and  permanence.   Alternatives   shall  be
      assessed for  the  long-term  effectiveness and  permanence  they afford,
      along  with  the  degree  of  certainty  that  the  alternative will  prove
      successful.    Factors that  shall  be considered,  as appropriate, include
      the following:

         (1)  Nature  and  magnitude  of  total  residual  risks   in   terms  of
              amounts;   potential   for  exposure  of  human  and  environmental
              receptors; concentrations  of  hazardous  substances,  pollutants,
              or contaminants  remaining following  implementation of a remedial
              alternative,   considering  the  persistence,  toxicity,  mobility,
              and  propensity  to  bioaccumulate  such hazardous  substances  and
              their  constituents

         (2)  The  type, degree, and adequacy of  long-term  management required
              for  untreated  substances  and  treatment  residuals,  including
              engineering   controls   (such   as   containment   technologies),
              institutional   controls,   monitoring    and   operating,    and
              maintenance

         (3)  Long-term  reliability   of   the   engineering   and   institutional
              controls, including uncertainties associated  with land disposal
              of untreated  hazardous  substances,  pollutants, and contaminants,
              and  treatment residuals
FIR.-0067-R8S4                         4-4

-------
                                                                Date:   8/22/89
                                                                Final  Revision
         (4)   Potential  need for  replacement of  the  remedy,  as  well as  the
              continuing  need for repairs  to maintain the performance of  the
              remedy.

      (D)   Reduction  of  toxicity, mobility, or  volume.   The  degree  to  which
      alternatives  employ treatment  that  reduces  toxicity,  mobility,  or volume
      shall  be assessed.   Alternatives which, at a minimum,  address  the  prin-
      cipal  threats posed by the site through treatment  shall  also  be identi-
      fied.    Factors  that shall  be considered,  as  appropriate,  include  the
      following:

         (1)   The  treatment  processes  the  alternatives  employ and  materials
              they  will treat

         (2)   The  amount  of  hazardous substances, pollutants,  or  contaminants
              that  will be destroyed or treated

         (3)   The   degree of  expected  reduction in  toxicity,  mobility,  or
              volume,  including how the principal threat  is  addressed through
              treatment

         (4)   The  degree  to which  the treatment is  irreversible

         (5)   The  residuals that will remain following treatment,  considering
              the   persistence,   toxicity,   mobility,    and   propensity   to
              bioaccumulate such hazardous  substances  and their constituents.

      (E)   Short-term effectiveness.   The short-term impacts  of 'alternatives
      shall  be assessed considering  the following:

         (1)   Short-term   risks, that might  be  posed  to  the community  during
              implementation of an alternative
FIR:0067-R8S4                         4-5

-------
                                                                Date:  8/22/89
                                                                Final Revision"
         (2)   Potential   impacts  on  workers during  remedial  action  and  the
              effectiveness and  reliability of  protective measures

         (3)   Potential  environmental impacts  of  the remedial  action  and the
              effectiveness  and  reliability   of  mitigative  measures  during
              implementation

         (4)   Time until  protection is achieved.

      (F)    Implementability.   The  ease  or  difficulty  of  implementing  the
      alternatives shall  be assessed  by  considering  the following types  of
      factors, as appropriate:

         (1)   Degree  of  difficulty  or uncertainty  associated with construction
              and operation of  the  technology

         (2)   Expected operational  reliability of the  technologies the alter-
              natives utilize and the ability  to  undertake additional  action,
              if required

         (3)   Ability and time required  to  obtain any  necessary approvals and
              permits from other  agencies

         (4)   Availability of necessary  equipment  and specialists

         (5)   Available  capacity  and location of  needed  treatment,  storage,
              and disposal services

         (6)   Timing  of  the  availability of prospective  technologies that may
              be under consideration.

      (G)    Cost.   The  types  of  costs that  shall  be  assessed  include 'the
      following:
FIR:0067-R8S4                         4-6

-------
                                                                Date:   8/22/89
                                                                Final  Revision
         (1)   Capital  costs,  including  contingency  and  engineering fees

         (2)  -Operation  and maintenance costs

         (3)   Net present  value  of  capital  and  O&M  costs.

      (H)   State  and/or support  agency acceptance.  Assessment  of  State con-
      cerns may not be completed until comments on the  RI/FS  are received and
      may  be discussed, to  the  extent possible,  in  the proposed plan issued
      for  public comment.   The  State  concerns  that shall  be  assessed include
      the  following:

         (1)   The  State's  and/or  support  agency  position and  key  concerns
              related  to the  preferred  alternative  and  other alternatives

         (2)   State and/or support  agency  comments on  ARARs  or  the  proposed
              use of waivers.

      (I)   Community  acceptance.   This assessment includes determining which
      components  of   the  alternatives  interested persons in  the  community
      support,  have reservations about, or  oppose.  This assessment  may not be
      completed until  comments on the  proposed  plan are received.

The EPA RI/FS  guidance  document presents  these  nine  criteria and  expands on
them.    The first  two criteria, overall protection  of  human health  and  the
environment,  and compliance with ARARs, are termed threshold  criteria in that
these  items  are evaluated as to whether,  and  how,  the  criteria are  met as
opposed  to  the  next  five criteria  for which  they  are  evaluated  on  a con-
tinuum.   In particular,  alternatives that  do not protect  human  health and the
environment,  or do not comply with ARARs (or justify a  waiver),  will  not meet
statutory   requirements  for  selection  of  remedy   in  the  Record of  Decision
(ROD).  The  final two criteria  for  State  (and/or support agency)  acceptance
and community acceptance are only preliminarily analyzed  in the  RI/FS.  These


FIR:0067-R8S4                         4-7

-------
                                                                Date:  8/22/89
                                                                Final Revision
criteria are formally addressed after the  completion  of  the FS and the formal
public hearing/comment period.

4.2  ALTERNATIVE DESCRIPTION
The five alternatives presented in Section 3.0  are  developed and described in
further detail  in  this section.   Table 4-1 presents  the  alternatives versus
potentially applicable or relevant'and appropriate requirements, and Table 4-2
summarizes the detailed analysis of remediation alternatives.  A cost compari-
son of the assembled remediation alternatives is presented in Figure 4-3.

4.2.1  Alternative A
Alternative A is the  "No-Action" alternative.   This is required by regulation
and is considered  as  a baseline alternative.   The  "no-action" alternative is
                                                                 •
defined as  being  the  current   site  conditions,  absent  the  ongoing  remedial
measures.   The ongoing remedial measures that started in February 1986 consist
of  pumping  and  treating  the   ground  water with  carbon  adsorption  and  air
stripping, and  discharging the treated water  to the Salinas  River  under an
NPDES permit.

This alternative consists of stopping the  pumping and treating that Is taking
place now.  Monitoring will continue under this alternative until the chemical
concentrations in each of the wells decrease to below the ground-water cleanup
levels.  Then, monitoring will  continue for  an  additional  two years to assure
that  no  concentrations  above   the  cleanup  levels  occur  (see  Section  5-2).
However, this  alternative  does include  maintaining the  treatment  plant  in a
standby mode for  two  years, ready to be placed back  in  service if necessary.
After two uninterrupted years with no concentrations above the cleanup levels,
all or  portions of the  treatment  plant may be dismantled and  s.alvaged.   At
this  point,  some  of   the  monitoring and  extraction  wells  may be abandoned
according to state  and  local requirements.   Sufficient wells will  be retained
to provide data for the 5-year  review required by CERCLA Section 121(c).

For this alternative,  the treatment plant will  not be operated.
FIR:0067-R8S4                         4-3

-------
                                                                Date:  8/22/89
                                                                Final Revision
This discussion  of  Alternative A  is  not meant  to  imply that  no-action will
clean up the aquifer, rather that  after some time, the observed concentrations
of chemicals  in  the aquifer will  decrease  to below  the  ground-water cleanup
levels due to natural attenuation,  degradation, and  diffusion.

Computer simulations have  been  made  for Alternative  A.   The program used for
these simulations and  the  input parameters  are discussed  in Appendix J.  The
model areas are shown  in Figure 4-1.   The migration of the chemical plume for
Alternative  A,  as  depicted by  the  cleanup  concentration  line  is  shown in
Figure 4-1A  for  the shallow aquifer  and in Figure 4-18  for the  intermediate
aquifer.   Under  this  alternative,  with  no  additional   pumping,   the  plume
migrates toward the west-in  the shallow aquifer  and toward tne west-northwest
in the  intermediate  aquifer.   Figures 4-1A and  4-1B  were prepared assuming a
hydraulic  conductivity of  200  feet/day.    The  rate of  plume  migration is
directly proportional  to the hydraulic conductivity.   Thus,  if the hydraulic
conductivity were 100  ft/day instead  of the 200  ft/day  used, the plume would
migrate half as fast.   For  a conservative cost estimate, the time required to
reach the cleanup level was  taken  consistent  with a hydraulic conductivity of
100 ft/day rather than 200  ft/day.

As the  plume reaches the left  side of the  model in  Figure  4-1A, the snallpw
aquifer merges with the intermediate  aquifer  as discussed  in  the  RI.   Thus,
when  the  plume reaches the  left  side of the  model,  the  shallow aquifer has
reached .the cleanup  level.   This takes . 5 years  as shown in  Figure  4-1.-.
However,  for a conservative  cost  estimate, we  assumed   a  10-year monitoring
period  for  this  alternative  because  the hydraulic conductivity  could  easily
vary by a factor of 2.
                         i
The net present worth of the-cost for  implementing Alternative A  is $1,525,0.00
at  a  discount rate  of  3 percent,  $1,387,000  at  5  percent,  and SI,116,000 at
10 percent, as summarized in Table 4-3.  The cost summary for Alternative  A is
presented  in Table  4-4.    There  are  no capital costs  for  this alternative
because  no  additional  pumping  or  treating  is  involved.     Monitoring  and


FIR:0067-R8S4                          4-9

-------
                                                                Date:  8/22/89
                                                                Final Revision
reporting costs have been included at $14,QOO/month  for  120 months.  A period
of 120 months was used for comparison purposes.   As discussed earlier the com-
puter simulations indicate the cleanup period is  directly  proportional  to the
hydraulic  conductivity.    The  cleanup  period  is  projected  at   60  to  120
months.  This analysis includes  a cost of $4,000/month for 24 months for main-
taining the existing treatment plant  in  an operational mode in the event that
the concentrations of chemicals  in the ground water increase and it is decided
to restart the plant.  No salvage value  for the  treatment plant is included in
the analysis.

4.2.2 . Alternative B
Alternative B consists of a continuation of  the  existing pumping and treating
of ground water  from the shallow aquifer only,  on-  and  off-site.   Currently,
there are 15  on-site extraction  wells and 5 off-site extraction wells  in the
shallow aquifer.   The site manager  adjusts the  flowrate  from  each  of  these
extraction wells to accommodate  changes  in the concentrations indicated.by the
monitoring data.  This pumping and treating will  continue until the monitoring
data  indicate  that  the  chemical concentrations  in  the  ground water  in the
shallow aquifer are less  than  the ground-water cleanup levels.

This  alternative  includes  maintaining the treatment  plant in  a  standby mode
for two years,  ready to be placed  back in  service  ,if necessary.   After two
uninterrupted  years  with  no  concentrations above  the  cleanup  levels  (see
Section 5-2),  all or  portions  of the treatment  plant may be  dismantled ana
salvaged.   At  this  point,  some  of the monitoring  and extraction wells  may be
abandoned according to state  and local requirements.   Monitoring will continue
in  the  120-foot  aquifer  until   two  years after  the  chemical  concentrations
reach the ground-water cleanup levels.   Then, the 120-foot aquifer, monitoring
wells  may  be  abandoned.   At  this   point,  the  remedial  action will be com-
plete.   Sufficient  wells  will   be  retained to  provide  data  for  the  5-year
review required by CERCLA Section 121(c).
FIR:0067-RSS4                         4-10

-------
                                                                Date:  8/22/89
                                                                Final Revision
For this alternative, the  treatment  plant will continue  to  operate with both
the air stripper and the carbon beds  as it is presently operating.

Computer simulations have been made  for Alternative  B,  similar to Alternative
A.   The areas  of  the  shallow  and intermediate aquifers  with concentrations
above the cleanup  levels  in this alternative  are  depicted in Figure 4-2A and
B.  In contrast to  Alternative A,  Figure  4-2A shows  that the extraction wells
arrest the westward  flow  of the plume in the  shallow  aquifer.   In fact, this
figure shows the cleanup level contour closing around both the on-site and the
offsite extraction  well fields.   Figure 4-2A  shows  that  Alternative B cleans
up the shallow aquifer in 2 years as  opposed to 5 years for Alternative A (for
a hydraulic conductivity of 200  ft/yr)  as  shown in Figure 4-1A.  -Thus, Alter-
native B is  expected to achieve the cleanup  levels  in  the shallow aquifer in
about 40% of the time required by Alternative A.

The cleanup  in the  intermediate aquifer proceeds at  the same  rate  for both
Alternative A and Alternative B  because  there is  no  pumping from this aquifer
in  either  alternatives.   The effect  of  reducing the  mass  loading  into the
intermediate aquifer compared to Alternative A is small.

The net present worth of the cost for implementing Alternative B is $3,186,000
at  a  discount rate  of  3  percent,  $2,990,000 at 5 percent,  and $2,588,000 at
10 percent, as summarized in Table 4-3.  The cost summary for Alternative 3 is
presented in Table 4-5.   There are no additional capital costs for this alter-
native  because  no  additional  pumping  or  treating capacity  is  involved.   For
purposes of  this cost  comparison,  monitoring  and  reporting costs  have been
included at $18,000/month for 33 months (while the treatment plant was assumed
to be operating) and $14,000/month for 120 months.  A period of 120 months was
used  for comparison purposes.   As discussed  earlier  the  computer simulations
indicate  the  cleanup  period   is  directly  proportional  to  the  hydraulic
conductivity.   The  cleanup  period is  projected  at  60  to 120 .months.   This
analysis  includes   a  cost  of  $35,200/month  for  33  months for  operating the
existing  treatment  plant.    No  salvage  value for  the  treatment plant  is
included in the analysis.

FIR:0067-R8S4                         4-11

-------
                                                                Date:  8/22/89
                                                                Final Revision
It  is  recognized  that  the  results of  computer models have  limitations, and
therefore, the  best  available predictions of  ability and  time  to meet ARARs
may  not  be  accurate.    Therefore, this  remedial  alternative  would  include
evaluation, of  system  operations   and  effectiveness  on  a  semi-annual  basis,
based on monitoring data.  In the  event remedial goals cannot be achieved, the
RAP/ROD may  be  amended accordingly by  invoking.the  appropriate ARAR waiver.
Any such RAP/ROD amendment would include appropriate public participation.

4.2.3  Alternative C
Alternative C was  defined  to pump and  treat the  affected  ground water in the
120-foot  aquifer  as  well as  the  ground water  in  the shallow  aquifer.   This
alternative.consists of installing and developing five new extraction-wells  in
the .120-foot  aquifer and  starting to pump and  treat ground  water from this
aquifer concurrently with the pumping  from the shallow aquifer.

For Alternative C, the pumping and treating of ground water from the 20 exist-
ing extraction wells  in the shallow aquifer wilj  continue.  The site manager
will adjust  the flow from each well based on  the  monitoring  data.  After the
concentrations  in the  shallow aquifer  decline  to  the ground-water cleanup
levels, pumping from the shallow  aquifer  will be stopped,  but monitoring  in
the shallow aquifer will continue  for  an additional two years.

In addition to this  shallow  aquifer remediation,  Alternative  C  includes pump-
ing and treating ground water from the 120-foot aquifer.  The five new extrac-
tion wells in the 120-foot aquifer will be located in a line along the axis  of
the chemical  plume.  The  actual locations  will vary  somewhat depending on the
time that the wells  are installed because the  plume  is  continuing to migrate
toward the northwest.   Thus,  the  longer it takes  to obtain the  access permits
and  agency  approvals and  the longer  the  installation  may be  delayed  due  to
planting cycles or weather,  the farther  to the northwest  is the optimum  loca-
tion of the new extraction wells.
FIR:0067-R8S4                         4-12

-------
                                                                Date:  8/22/89
                                                                Final Revision
The pumping  and  treating of  ground  water from  the  120-foot aquifer  will  be
started as  soon  as  the new wells can  be  installed and developed.   The flow-
rates from  both  the  120-foot  and the  shallow aquifer  will  be  adjusted by the
site manager  based  on the monitoring  data.   For Alternative C,  the combined
flowrate will exceed  650  gpm,  and the minimum flowrate from the  new wells in
the  intermediate wells  will  be  400  gpm.    Thus,  the  treatment  plant  will
require modification  and,  because the flowrate  exceeds  1,000 gpm,  the NPDES
permit will  have to be modified.   (For the  purposes  of  this report,  it has
been  assumed  that a  new air  stripper with  a  capacity  of 500  gpm  will  be
installed,  based on   a  comparison  of costs  with  a new   carbon  adsorption
system).  This pumping and treating  of ground  water  from  the 120-foot aquifer
will  continue until  the concentrations  are below  the ground-water  cleanua
levels.

Monitoring  in  all  aquifers will  continue  for two years after this to assure
that  no concentrations  above  the  cleanup  levels  occur.   This  alternative
includes maintaining  the treatment  plant in  a  standby  mode  for  two years,
ready  to  be  placed  back in  service  if necessary.    After  two  uninterrupted
years with  no  concentrations  above  the cleanup  levels (see Section 5-2), all
or  portions  of  the  treatment plant  may  be dismantled and  salvaged.   At this
point, some of the monitoring and extraction wells  may be abandoned according
to  state and local requirements.  Sufficient wells will be.retained to provide
data for the 5-year review required by CERCLA Section  121(c).

Results of the computer simulations for Alternative C  are presented in Figures
4-3A  and  B  for  the  shallow and intermediate  aquifers,  respectively.   The
cleanup  in  the  shallow  aquifer  for  Alternative C  proceeds  as   it  did for
Alternative B, (Figure 4-2A)  because the pumping  is the same.  However, as can
be  seen  in  Figure 4-3A,  continuing  pumping  from both the  onsite  and offsite
shallow  aquifer  wells  results   in  developing  a null point between  the two
extraction  well  fields where the gradient  is relatively small.   As shown in
Figure 4-3A, the shallow aquifer  is cleaned up in 2 years.
FIR:0067-R8S4   .                      4-13

-------
                                                                Date:  8/22/89
                                                                Final Revision
The cleanup  of the  intermediate aquifer  is  depicted  in  Figure 4-3B.   This
shows  that cleanup is achieved in 1 1/2 years.

The net present worth of the cost for implementing Alternative C is $5,905,000
at a  discount  rate of 3 percent,  $5,722,000  at 5 percent,., and  $5,308,000 at
10 percent, as summarized in Table 4-3.  The cost summary for Alternative C is
presented  in Table 4-6.   The  capital  costs for this  alternative  include the
cost  for  a new air  stripper  and the cost for  installing  five new extraction
wells  and a new segment of pipeline.  Monitoring and reporting costs have been
included  at  $18,000/month  for  33  months.  This  analysis  includes  a  cost of
$4,000/month for 24 months for  maintaining  the  existing treatment  plant in an
operational mode  in  the  event  that  the concentrations  of chemicals  in the
ground  water  increase  and  it  is  decided  to  restart the  plant  beyond  the
planned  operational  period.    No  salvage  value  for  the  treatment  plant is
included in the analysis.

A  primary  objective  of this  remedial  effort  will be  to establish  a  zone of
capture for chemicals  above the cleanup  levels in  the intermediate aquifer.
Accordingly, once the new extraction wells are installed, they will be sampled
for contaminants to determine the  concentrations  at  the wells.  If necessary,
one or  more additional  wells  will  be  installed farther  downgradient and/or
pumping rates adjusted to ensure that  the capture zone intercepts  any portion
of the  plume with  contaminant concentrations  above  the cleanup  level for any
contaminant.

Once pumping has commenced,  aquifer tests will be performed to verify the zone
of capture for the wells.  If necessary, another well may be installed furrhe-
downgradient.and pumping rates adjusted accordingly so  that any portion of the
plume containing concentrations above the cleanup Iev2ls for any contamination
is intercepted.

It  is recognized  that  the  results  of  computer models have  limitations,  and
therefore,  the  best  available  predictions  of ability  and  time  to meet ARARs
FIR:0067-RSS4                         4-14

-------
                                                                Date:  8/22/89
                                                                Final Revision
may  not  be  accurate.    Therefore,  this  remedial  alternative would  include
evaluation  of  system  operations   and  effectiveness  on  a  semi-annual  basis,
based on monitoring data.  In the event remedial goals cannot be achieved, the
RAP/ROD may  be  amended accordingly  by  invoking the  appropriate  ARAR waiver.
Any such RAP/ROD amendment would include appropriate public participation.

4.2.4  Alternative D
Alternative D, like Alternative C, was  defined  to pump and treat the affected
ground water in the 120-foot  aquifer as well  as the ground water in the shal-
low aquifer.  This alternative  consists of  installing and developing five new
extraction wells in the 120-foot aquifer and pumping and treating ground water
from this aquifer concurrently with the pumping from the shallow aquifer.  The
minimum flowrate from  the new wells  installed  in  the intermediate aquifer is
400  gpm.    Capture  zone  analyses  were done  for  Alternative  D for  both the
shallow and intermediate aquifers because this is the recommended alternative.

4.2.4.1  Zone of Capture, Shallow Aquifer
For Alternative D,  the pumping and  treating  of  ground water from some of the
20  existing extraction  wells  in the  shallow  aquifer will  continue.   The
purpose of  determining the  zone of capture  is to provide  information support-
ing  the  development  of a  feasible and practical  plan  for remediation of the
ground water  in the  shallow aquifer.   Additionally, the  analysis  must show
that  the  scenario  is  feasible,   timely,  cost   effective,   and  technically
acceptable.  One  of  the standard  methods for determining the zone of capture
is to use  the Theis non-equilibrium, equation developed in 1935 and determine
the  drawdown or  that portion  of  the  aquifer  dewatered  resulting  from the
pumping  of wells.   There  are  many  methods  for  determining  the  drawdown In
wells, and  they range from mathematical calculations plotted on graph paper to
plots on graphs developed for this purpose.

Since pumping has been going on for  several years  in the shallow aquifer and  a
shrinking of the plume has  been shown in the  field-collected data, no calcula-
tions are  performed  for the shallow  aquifer.   A comparison of the plume s-izs
to the measured potentiometric  levels will be used for this analysis.

FIR:0067-R3S4                         4-15

-------
                                                                Date:  8/22/89
                                                                Final Revision
The  following pumping  rates  apply  to  the  wells  pumping  from  the  shallow
aquifer for this analysis:
              On-site Wells
                     well IT-S7  -  70 gpm
                     Well IT-S8  -  10 gpm
                     Well IT-SI1 -  25 gpm
                     Well IT-MI  - 155 gpm
                     Total       - 260 gpm
              Off-site Wells
                     Well IT-SE2 -  70 gpm
                     Well IT-SE3 -  35 gpm
                     Well IT-SE4 -  70 gpm
                     Well IT-SE5 -  60 gpm
                     Total       - 235 gpm

These  pumping  rates will  be reduced when  the five  new  intermediate aquifer
extraction wells are installed  and  become  operational.   The combined flowrate
will not exceed 650 gpm.

The 4 wells located  on  site  are located  more or less in a northeast-southwest
line along the property  line of the facility.  The off-site wells are located
in an "L" shape in an area approximately 800 feet west of the facility (Figure
3-12).  The configuration  of wells  on-site appears  to be the optimum arrange-
ment for the interception of any contaminant migrating from the facility.  The
configuration  of   the  off-site  wells is  an  attempt to  intercept  and also
compress the plume as it moved from the facility.

Figure  4-4  shows  the capture  zone  for  the shallow aquifer.   A comparison cf
the  January  1988  and  1989  contours indicates  that the  drawdown  from the
shallow wells is adequate to intercept the plume.  The plume has decreased the
size and  concentration  levels 'in a reasonable  time  frame  and  it appears that
the  wells will continue to  intercept  the  plume  for  the  duration  of   their
pumping.
FIR:0067-R8S4                         4-16

-------
                                                                Date:  8/22/39
                                                                Final Revision
The site manager will  adjust the flow from each  well  based on the monitoring
data.   After the concentrations  in  the  shallow aquifer decline to the ground-
water cleanup  levels,  monitoring in the shallow  aquifer  will  continue for an
additional  two years.   Monitoring will  continue  under  this alternative until
the chemical  concentrations in each of the wells decrease to below the ground-
water cleanup  levels.   Then, monitoring  will  continue for an additional two
years to  assure that  no  unusual  increases in  the concentrations  above the
cleanup levels occur (see Section 5.2).

4.2.4.2  Zone of Capture, Intermediate Aquifer
In addition to this  shallow  aquifer remediation,  Alternative D includes pump-
ing and treating ground water from the  120-foot  (intermediate)  aquifer.  The
purpose of determining  the zone  of  capture is  to provide information support-
ing the development of a  feasible  and  practical plan  for  remediation of the
ground water  in the  120-foot aquifer.    Additionally, the calculations must
show  that  the  scenario is feasible,  timely,  cost  effective,  and technically
acceptable.  One of the standard methods  for  determining the zone of capture
is to use  the  Theis non-equilibrium equation  developed in  1935 and determine
the  drawdown   or  that  portion  of  the  aquifer  dewatered  resulting  from the
pumping of wells.    There are  many methods for  determining  the  drawdown in
wells and  they range  from  mathematical  calculations plotted on graph paper to
plots on  graphs  developed for  this purpose.    The  method  to  be  used in this
section will  be a computer generated result and is described as follows.

The zone of  capture is defined  using the  Prickett  solution of the Theis non-
equilibrium equation  (Figure 4-5A).  The  program RESSQ was used to calculate
flow  patterns  (Figures  4-5B  and  C).  Appendix  J of this  report explains these
models, the  effectiveness, the  limitations, and  the  assumptions required for
their operation.

The following  constants were  used to determine drawdown.
               Transmissivity  - 74,800 gpd/ft or 10,000  ft2/d
               Storage Coefficient - 0.001
               Pumping Rate -  650 gpm for Figures  4-5A and B
                           -  400 gpm for Figure 4-5C

F[R:0067-R8S4                         4-17

-------
                                                                Date:  8/22/89
                                                                Final Revision
The 5 wells  are  located in a line as  shown  in  Figure 3-12, with wells IT-IE2
through 5  separated by  about  300 feet  and  wells  IT-IE1 and  2 separated by
about 880  feet.    This  configuration of  wells  is the  optimum arrangement as
demonstrated in this document.

Figure 4-5A shows  the capture-zone for the 120-foot aquifer.  Note that after
30 days of pumping the cone of depression (zone of capture) reaches beyond the
January 1989  target cleanup area.   This indicates that  the  drawdown is ade-
quate to intercept  the  plume within  a  reasonable time frame and will continue
to intercept the plume for the duration of the pumping.

The five  new  extraction  wells  in the 120-foot  aquifer  will  have  a- minimum
pumping rate  of  400 gpm and will be  located in a line along  the axis of the
chemical plume.  The actual locations will vary somewhat depending on the time
that the wells are  installed because the plume is continuing to migrate toward
the northwest.    Thus.,  as  in  Alternative C,  the  longer it  takes  to obtain
access  permits  and agency  approvals  and  the  longer the  installation  may be
delayed due to planting cycles or weather, the farther to the  northwest is the
optimum location of the new extraction wells.

The pumping and treating of ground water from the the 120-foot aquifer will be
started as  soon  as the new wells can  be installed, and developed.   The flow-
rates from both the shallow aquifer  and  the  120-foot aquifer  extraction wells
will be adjusted  by the site manager  based  on  the  monitoring data.  However,
the combined  flowrate  will be  less  than 650 gpm so  the  treatment  plant will
not require  modification  and new operating permits  are  not  required.   This
pumping and  treating  of ground  water  from the  120-foot aquifer will continue
until the  chemical concentrations are below the  ground-water cleanup levels.
Then, pumping  will be  stopped,  but monitoring  in the 120-foot aquifer will
continue for  an  additional two  years.   At this  point,  some of the monitoring
and extraction  wells  may  be abandoned according to  state  and local require-
.ments.   Sufficient wells  will   be  retained to  provide  data for  the  5-year
review required by CERCLA  section 121(c).
FIR:0067-R8S4                         4-18

-------
                                                                 Date:   8/22/89
                                                                 Final  Revision
4.2.4.3  Computer Simulations
Results of the computer simulations for Alternative  D  are  presented  in  Figures
4-6A  and B  for  the shallow  and intermediate  aquifers,  respectively.    The
pumping  scenario  described below  is  for modeling purposes only.   For  actual
conditions, pumping  rates will be  based on  the monitoring  well  design,  and  the
results  of  aquifer  testing and  monitoring.   Both  shallow and  intermediate
aquifer wells  can  be pumped at the same time.   However,  the pumping rates  for
all  intermediate  aquifer wells  combined  will be  a  minimum  of  400  gpm.   The
cleanup  in the.shallow  aquifer proceeds as shown in Figure 4-6A.  This  figure
shows that the plume migration in  the  shallow aquifer  is  initially arrested by
.the current pumping.  To  break the null point discussed  in Alternative  C,  the
on-site,  shallow  aquifer  pumping  has  been simulated  as  being terminated  in
August  1989.   Off-site,  shallow  aquifer pumping is  continued at  200 gpm until
October  1989  for  this simulation.  This  allows the remaining  shallow  aquifer
plume to migrate under the  regional gradient  toward  the merging  of the  shallow
and  intermediate  aquifers.   Figure  4-6A shows  that by  February  1991 only an
area  about  800 feet long  is  covered with the target cleanup  plume,  and by
February 1992  the  shallow  aquifer  is  practically all below the  cleanup  levels.

The  cleanup of  the intermediate  aquifer  is depicted in  Figure  4-6B.    This
shows  that  cleanup  is  achieved  under  this simulation in  1 1/2 years.   This
alternative.also  avoids developing a  null point  between the shallow  and  inter-
mediate  aquifers  by terminating the  shallow aquifer pumping earlier than  the
intermediate aquifer pumping.

Two  additional variations  of Alternative  D  have been simulated.  These  are
labeled  as  Alternative D'  (650  gpm)   and Alternative  0'  (400 gpm).   The  pur-
poses  of these additional  simulations were to assess  the  effect  of  a delay in
beginning pumping  from  the intermediate aquifer  and  the effect  of pumping at a
flowrate of only  400 gpm.

As discussed  in Section 3, if there  are  delays  in obtaining access  agreements
or agency  approvals,  it  may  not be  possible  to install  the new  extraction
 FIR:0067-R8S4                         4-19

-------
                                                                Date:  8/22/89
                                                                Final Revision
wells  and  new pipeline  segment by  the fall  of 1989. .  If this  occurs,  the
installation will  have to  be delayed  until  the spring  of 1989  because  the
drill rigs and construction equipment may  not be allowed to damage the fields
and roads  during  the winter  rainy  season.   Thus, a  simulation  was made with
the-intermediate aquifer pumping starting  in  April  1990.   The results of this
simulation  (Figure  4-6C)  show  that the  proposed well  locations  are  not  as
effective  as  they are  if  the pumping  is  started in  the  fall of  1989.   The
we,lIs should be relocated  farther to the west, as discussed in Section 3.

The fourth simulation used the  fall  of  1989 as the start date of pumping from
the intermediate aquifer.   However,  in  contrast  to  the simulation  depicted in
Figure 4-6B where the pumping rate  was  650 gpm,  the pumping rate used for the
simulation was only 400 gpm.  The results of this simulation are summarized in
Figure  4-6D.    This* figure   shows  that a  pumping  rate  of  400 gpm  is only
minimally  effective  in  containing  the   intermediate aquifer plume.   Thus, for
the recommended alternative a minimum pumping rate of 400 gpm  is specified.

4.2.4.4  Summary of Costs
The net present worth of the  cost for implementing Alternative D is $1,829,000
at a  discount  rate of  3 percent,  $1,792,000 at 5 percent,  and  $1,708,000 at
10 percent, as summarized  in  Table 4-3.   The cost summary for  Alternative 0 is
presented  in Table 4-7.  Capital  costs  for this  alternative include the costs
for installing the five new wells  and a new segment of pipeline; there are no
new  capital  costs for  the  treatment plant.   Monitoring  and  reporting costs
have been  included at $18,000/month  for 12 months and at $14,000/month for 24
months.  This analysis includes a cost of $4,000/month for 24  months for main-
taining the existing treatment  plant in an operational mode in the event that
the concentrations of chemicals in the ground water increase and it is decided
to restart the plant.  No  salvage value  for the treatment plant  is  included in
the analysis.
FIR:0067-R8S4                         4-20

-------
                                                                Date:  8/22/89
                                                                Final Revision
4.2.4.5  Remedial Action Goals
A primary  objective of this  remedial  effort will 'be  to establish  a zone of
capture for  chemicals  above the  cleanup  levels in  the  intermediate aquifer.
Accordingly, once the new extraction wells are installed, they will be sampled
for contaminants to determine  the concentrations  at  the  wells.  If necessary,
one or  more additional wells  will  be  installed further  downgradient and/or
pumping rates adjusted to ensure  that  the capture zone intercepts any portion
of the  plume with  contaminant concentrations above  the  cleanup level for any
contaminant.

Once pumping has commenced, aquifer tests will be performed to verify the true
zone of  capture for the wells.   If necessary, another  well  may be  installed
further  downgradient  and   pumping   rates  adjusted  accordingly  so  that  any
portion of  the  plume containing  concentrations  above the  cleanup  levels for
any contamination is intercepted.

It  is  recognized that  the  results  of  computer models  have  limitations, and
therefore,  the  best available predictions  of ability and  time to meet ARARs
may  not be  accurate.    Therefore,  this  remedial  alternative  would include
evaluation  of   system  operations  and  effectiveness  on  a  semi-annual  basis,
based on monitoring data.   In  the event remedial goals cannot be achieved, the
RAP/ROD may  be  amended accordingly  by  invoking .the  appropriate ARAR waiver.
Any such RAP/ROD amendment would  include  appropriate public participation.

4.2.5  Alternative  E
Alternative  E,  like Alternatives C  and  D,  was defined  to  pump and treat the
affected ground water  in  the  120-foot aquifer  as  well  as the ground water in
the shallow  aquifer.   This alternative consists  of  installing and developing
two  new extraction  wells   in  the 120-foot  aquifer  and  pumping  and treating
ground  water from  this  aquifer  concurrently with  pumping from  the shallow
aquifer.
FIR:0067,RSS4                         4-21

-------
                                                                Date:  8/22/89
                                                                Final Revision
For Alternative E,  the  pumping and treating of  ground  water from some of the
20 existing extraction  wells  in the shallow aquifer  will  continue.   The site
manager will  adjust the  flow from  each  well  based  on the  monitoring data.
After  the  chemical  concentrations  in the  shallow  aquifer  decline  to  the
ground-water cleanup  levels,  monitoring in the  shallow aquifer will continue
for an additional  two years.

In addition to  this shallow  remediation,  Alternative  E  includes pumping and
treating ground water from the 120-foot aquifer.   The two new extraction wells
in the 120-foot aquifer will be located in a line along the axis of the chemi-
cal plume.   The actual locations will vary somewhat depending on  the time that
the wells are installed because the  plume  is  continuing to migrate toward the
northwest.    Thus,  the  longer it  takes to obtain  access permits  and agency
approvals,  and  the  longer  the installation  may be  delayed due  to planting
cycles or weather, the farther to the northwest  is the  optimum  location of the
new extraction wells.

The pumping  and treating  of  ground water  from  the  120-foot  aquifer will  be
started as soon as the new wells  can  be installed and developed.   The flow-
rates from both the  shallow aquifer  and the 120-foot aquifer extraction wells
will  be adjusted  by the site manager  based on  the  monitoring data.   However,
the combined flowrate will  be less  than 650 gpm, and the treatment plant will
not require modification.   This pumping and treating  of ground water from the
120-foot aquifer will continue until the chemical concentrations  are below the
ground-water cleanup  levels.   Then pumping will  be  stopped  and monitoring in
the  120-foot  aquifer  will  continue  for  an  additional  two  years.    If  no
concentrations  above  the  cleanup  levels occur (see Section  5-2), some of the
monitoring and  extraction wells in  the 120-foot  aquifer may be abandoned, and
the treatment plant may be disassembled and salvaged.   Sufficient wells will
be retained to  provide  data  for the 5-year  review  required  by CERCLA Section
FIR:0067-R8S4                         4-22

-------
                                                                Date:  8/22/89
                                                                Final Revision
Results of the computer .simulations for Alternative E are presented in Figures
4-7A  and  B  for  the  shallow  and  intermediate  aquifers,  respectively.   The
cleanup in the  shallow  aquifer proceeds  as shown in Figure 4-7A.  This figure
shows that the  plume  migration is initially  arrested  by the current pumping.
To  break  the null  point discussed  in Alternative  C,  the onsite  pumping is
terminated in 6 months.  Off-site, shallow aquifer pumping is continued at 200
gpm  for 9  months.   This --allows  the remaining plume  to migrate  under  the
regional gradient toward the merging of the shallow and intermediate aquifers.
Figure 4-7A shows  that  only  an area  about 1,000 feet long is covered with the
target  cleanup  plume  at that  time,  and  by  the  Spring  of  1992  the shallow
aquifer is practically all below the cleanup  level.

The  cleanup  of  the  intermediate  aquifer  is  depicted  in  Figure 4-7B.   This
shows  that  cleanup  is  achieved  in  5 years.   This alternative  also  avoids
developing  a null  point  between  the  shallow  and  intermediate  aquifers by
terminating the  shallow  aquifer pumping  earlier than the intermediate aquifer
pumping.

The net present worth of the cost  for  implementing Alternative E is $3,444,000
at  a  discount rate of  3 percent,  $3,311,000 at  5  percent,  and $3,017,000 at
10 percent, as  summarized in Table 4-3. . The  cost  summary  for Alternative  E is
presented in  Table 4-8.   Capital  costs for this alternative  include the costs
for  installing  two new extraction wells  and  a new segment of pipeline; there
are no  capital  costs  for the treatment plant.  Monitoring and reporting costs
have  been included  at  $18,000/month  for  36  months and  at  $14,000/month for
12 months.   A period  of 120 months was used  for comparison purposes.  As  dis-
cussed  earlier  the  computer  simulations  indicate  the   cleanup   period is
directly  proportional  to the  hydraulic  conductivity.    The  cleanup period is
projected at  60 to 120 months.  This analysis  includes  a  cost of $4,000/month
for  24  months for maintaining  the existing  treatment  plant  in an  operational
mode  in the  event that the  concentrations  of chemicals  in  the ground water
increase  and it  is  decided  to restart  the  plant.  No  salvage  value for the
treatment plant  is included  in the analysis.
 FIR:0067-R8S4                          4-23

-------
                                                                Date:  8/22/89
                                                                Final Revision
A primary  objective  of this  remedial  effort will  be  to establish  a  zone of
capture for  chemicals  above the cleanup  levels in the  intermediate aquifer.
Accordingly, once the new extraction wells are installed, they will be sampled
for contaminants to determine the  concentrations  at the  wells.  If necessary,
one or  more additional wells  will be  installed further  downgradient and/or
pumping rates adjusted to ensure that  the  capture zone intercepts any portion
of the  plume with  contaminant concentrations above the  cleanup  level  for any
contaminant.

Once pumping has commenced,  aquifer tests will be performed to verify the zone
of capture for the wells.   If necessary, another well may be installed further
downgradient and pumping rates adjusted accordingly so that any portion of the
plume containing concentrations above the cleanup levels for any contamination
is intercepted.

It  is  recognized that  the  results of  computer models  have  limitations, and
therefore, the  best  available predictions of ability and  time  to meet ARARs
may  not be  accurate.    Therefore,  this  remedial  alternative  would  include
evaluation  of  system  operations   and  effectiveness  on  a  semi-annual  basis,
based on monitoring data.   In the event remedial goals cannot be achieved, the
RAP/ROD may  be  amended accordingly  by  invoking the  appropriate ARAR  waiver.
Any such RAP/ROD amendment would include appropriate public participation.

4.3  DETAILED ANALYSIS
A  detailed  analysis  has  been  performed  on  each  alternative  using  the
previously presented evaluation criteria.  The primary remediation goal is the
control of the  migration  and  removal  of  contaminants  in the  ground  water
resulting from the operation of the  Firestone facility in .the Salinas Valley,
California.  This wiTi  be accomplished  by  determining the best pumping alter-
native  that  will  provide  the  highest  level  of  contaminants  for treatment at
the most cost-effective level.
FIR:0067-R8S4                         4-24

-------
                                                                Date:  8/22/89
                                                                Final Revision
This analysis  includes an  evaluation of each  alternative by  criteria  and a
comparison of the  relative  performance  among alternatives.  The effectiveness
of  the  alternatives  in  meeting contaminant-specific,  location-specific,  and
action-specific  ARARs  are  discussed  separately.    The  detailed  analysis
presented  in  this  section  is  not  intended  to  be  cqmplete and  final,  but is
intended to present  sufficient information about each  alternative  to allow a
comparative evaluation.
    «
4.3.1  Short-Term Effectiveness
The primary remedial  response  objective to  be achieved by the remedial action
is  attainment of  ground  water quality  at  the cleanup levels for chemicals in
the site ground  water.  Alternatives C  and  D would most likely achieve these
objectives the earliest.   There  is  only a marginal difference in time between
the two alternatives.  Alternative  C and .Alternate D well field layout in the
intermediate  aquifer  appears  to be  well  suited  to the  site  geology.   The
limited  number  of  wells  installed under  Alternative E  may  not  provide an
efficient  field  for  capture of chemicals.   Additionally,  full utilization of
the existing  treatment plant  after the shallow zone  is fully remediated may
not  be  achievable,  pumping  from   only  two   wells  in the  intermediate  zone,
during the later stages  of Alternative  E.   In any event,  the  time  required to
remediate  under  Alternative E would  exceed   that required  for Alternatives C
and D.

Alternative B  does not  provide  active  remediation  of  the intermediate zone.
Alternative A  provides  no  further  active   remediation.    Implementation of
either   of  these  alternatives  could  contaminate  downgradient   aquifers.
Remediation of the intermediate  zone  (Alternatives C, 0, and E)  is  expected to
remove  contaminated   ground  water   significantly  and reduce the potential of
significant contamination of the deeper  aquifers.

The risk  to  the community  is  highest  under  the No-Action Alternative A.  The
potential  for contaminant  exposure  is highest,  if. contaminants  are allowed to
migrate  to  the  deeper  aquifers.     Passive  remediation  utilizing natural


FIR.-0067-R8S4                         4-25

-------
                                                                Date:  8/22/89
                                                                Final Revision
attenuation mechanisms  and agricultural  well  use allows a  greater potential
for further contamination  of  wells.   Alternative C may  result  in atmospheric
discharges of contaminants from the new air stripper at levels approaching the
current  discharge  criteria  (potentially  limiting  operation  or  requiring
further monitoring).  Alternatives 8, D,  and  E present the lowest risk to the
                                          •
community during  remediation.   Incremental  differences between these alterna-
tives may not be significant.

The  risk   to  workers,  although   still   small,  will  be   greatest  under
Alternative C.   Construction-related risk varies with  level  of improvements.
Alternative C  includes  constructing  a  new  air  stripper  and five  new wells,
Alternative 0  includes  five  new wells, Alternative  E includes  two  new wells
only.    The  increase   in  emissions  under  Alternative C  would  lead  to  an
increased  hypothetical   risk   to  the   worst-case worker exposure  scenario.
Alternatives A, B, and E have the lowest potential for worker risk.

Short-term environmental  impacts  are greatest under Alternative A followed by
Alternative B  due  to  the potential  for further migration  of  the contaminant
plume.  The  high flowrate of ground water  withdrawal  under Alternative C may
have a minor  impact on  ground  water  recharge  and lead to entrainment of rela-
tively noncontaminated ground water.   Alternatives D and  E will have the least
impacts  on the  environment  during  construction and  implementation  'of  the
remedial alternative.   Environmental disturbances due to construction  activi-
ties under Alternatives C, D,  and E correspond with their respective levels of
construction.

Summary of Short-Term Effectiveness
Based  on  the  above  discussions,  the  alternatives with  intermediate  aquifer
extraction  are rated  approximately  equal.   Alternative  B  is  less short-term
effective due  primarily  to lack of  intermediate  zone  treatment,  and Alterna-
tive A is least short-term effective due to total reliance on passive remedia-
tion techniques.
FIR:0067-R8S4                         4-26

-------
                                                                Date:  8/22/89
                                                                Final Revision
4.3.2  Long-Term Effectiveness and Permanence
The magnitude of residual  risk  is  highest  for Alternative A due to the higher
potential for  contamination of domestic and  agricultural  wells from reliance
on natural mechanisms  for remediation of the  shallow  and intermediate zones.
Shallow  aquifer active   remediation  under  Alternative B  produces  long-term
residual risk less than Alternative A, but greater than Alternatives C, D, and
E.   Alternatives C, D,  and E  all  remediate the  intermediate  zone,  although
Alternatives C  and  D  are  most  likely  to  remove  more  contaminants  than
Alternative E due to capture efficiency of the larger well field.

Monitoring and  relying on  natural  mechanisms for remediation  of  shallow and
intermediate zone aquifers  in Alternative A and the intermediate zone aquifers
in Alternative  B are  deemed marginal to control  further  spread of contamina-
tion.   Long-term monitoring  and maintenance  of  plant  for restart  would  be
required.   Contamination  could spread  to  a  point  where  remediation  was  no
longer feasible.   Installing  a new air stripper as presented in Alternative C
could  require  significant  downtime  to allow for  construction  and debugging.
The  existing  system has  been  proven and is  currently  operating smoothly and
reliably.  Alternatives D  and E  are the most reliable alternatives.

The  plume maps  for  the deep aquifer (Figures 3.7 and 3.8)  show  that the  plume
is  lenticular  in  shape  and, although  26  deep aquifer  monitoring  wells were
installed, only a  limited number .of  these  wells detected any  chemicals.   A
model  simulation of the deep aquifer  was  studied to assess the effectiveness
of pumping from the agricultural wells  in  remediating  the deep aquifer.  The
results  indicate that  the agricultural wells strongly influence the direction
of  ground-water flow  and  additional  extraction  wells would  have difficulty
matching  the withdrawal  rate and  influence.   Therefore,  data from the Harden
12 AG  well was used to determine the trends of concentrations of chemicals in
the  deep aquifer.   Figure 4.8 shows  the  downward  trend of  1,1-DCE  in the
Harden  12 AG well over the past  3 years.  Although two deep aquifer monitoring
wells,  ITM17A  and  ITM13A, have 1,1-OCE levels above drinking water standards,
a  downward  trend  is  expected,  similar to  the  Harden  12 AG  well.   Because
 FIR-.0067-R8S4                          4-27

-------
                                                                 Date:   8/22/89
                                                                 Final  Revision
agricultural  use  of  the water has generally decreased the concentrations  to  a
relatively  low  level   of  chemicals  in  the  aquifer  or has  prevented  large
increases  of  concentrations  of  chemicals,  and,  this  can  be  expected to
continue  in  the future, no alternatives requiring additional extraction  wells
are planned for the  deep zone.

Summary of Lonq-Term Effectiveness and  Permanence
Based  on  the  potential  inadequacy of natural mechanisms .to fully  or  partially
remediate  shallow or intermediate aquifers  as  required for implementation of
Alternatives  A  and  B,  capture efficiencies of various intermediate zone  reme-
.diation alternatives,  and  proven efficiency of  the existing plant, the alter-
natives are ranked from the most  to  least  long-term effective and  permanent as
follows:  D,  C, E, B, A.

4.3.3  Reduction  of  Toxicity, Mobility,  and Volume
Under  the No-Action alternative,  no  active  treatment process  .is  employed.
Treatment  processes  for all the  other  alternatives  utilize air stripping  and
carbon adsorption technology as appropriate treatment processes,  as  discussed
in  Section 2.0.   Alternative C  would  necessitate increased  treatment  plant
capacity  most likely in the form of an additional  air stripper.  The  current
air  stripper and  carbon  adsorption system are  flow limited  at  130 gpm  and
500 gpm,  respectively.

The  existing combined  treatment  system  meets  NPDES  and  MBUAPCD  air pe-mit
requirements.   Permit modifications  would  be required  for Alternative  C.

Alternative C has the highest potential  to treat the greatest amount  of ground
water, although the  removal efficiencies  may suffer due  to dilution of  contam-
inants  by  entrainment of noncontaminated  ground water.    Alternative  0 is
expected  to  remove  only slightly less contaminants than Alternative  C, but in
doing  so, will  extract a  much  lesser  volume  of water.   Of  the  intermediate
zone  extraction  methods,   Alternative  E  will   potentially  extract  the  least
amount of contaminants  due to the reduction in contaminant capture efficiency


FIR:0067-R8S4                        4-28

-------
                                                                Date:  8/22/89
                                                                Final Revision
caused  by  using only  two wells  in  the intermediate  aquifer.   Alternative 8
will  not  address   active remediation  of  contaminants  in the  intermediate
aquifer.  Alternative A will  not  address  active remediation of the shallow or
the intermediate aquifers.

The treatment  processes  involved  are primarily irreversible removal processes
where little destruction  takes place directly.   Contaminants  adsorbed by the
carbon unit are  later  removed from the  carbon by a recycling firm.  The spent
carbon may be considered  a treatment residual.  Volatiles removed from the air
stripper are emitted to the air and may undergo photochemical reactions in the
atmosphere.   Alternatives 0  and  E would  generate  more carbon  than Alterna-
tive C  due  to  the  reliance  on the  carbon  units  for  a  greater  percentage of
waste stream treatment and  longer treatment period.   Similarly,  greater local
air emissions would be encountered under Alternative C.

Summary of Reduction of Toxicity. Mobility, and Volume
Alternative C  may  provide slightly  greater removal of  contaminants from the
ground  water,   although   local  discharges  to  surface  water  and  air  may be
higher.   Alternative 0 appears to  provide the best match  of  removal, due to
the fact' that  highly  contaminated areas will  be preferentially treated first.
Capture efficiency  may suffer for Alternative I due to too few wells, whereas
Alternatives A and  B do not thoroughly  address  each of the  chemical plumes.

4.3.4   Implementabi1ity

4.3.4.1  Technical  Feasibility
Alternatives  A  and B require no  new  construction,  and   can  be   implemented
immediately.   Alternatives C, 0,  and  E require  installation  of  new off-site
extraction wells.   In addition,  Alternative  C  would  require expansion of the
existing  treatment  plant.   Construction  of new  off-site  wells  would require
permits  and easements  from property  owners.
 FIR:0067-R8S4                          4-29

-------
                                                                Date:  8/22/89
                                                                Final Revision
Installation  of new  wells  would  have  to  be  done  during  the dry  season.
Previous experience  has  shown damage  to  fields may be caused  if drilling is
attempted during  wet weather.   This  restriction  may cause  some unscheduled
delays.

The least reliable  alternative  is A.  Natural  degradation  or dilution of the
plume  is dependent  on  many changing factors.    Contaminant  concentrations
within the,plume may decrease slower than  predicted extending the remediation
time even further.   The plume during that time may migrate  farther into the
aquifers.  However, should this trend be observed, counteractive measures such
as resuming ground water extraction could be implemented.

The water-treatment technologies of carbon treatment and air stripping used in
Alternatives B, C, 0, and E are well demonstrated and very efficient.  Ground-
water  extraction  has  been  demonstrated as  an  effective  way to  control  the
movement of the contamination plume.

The technologies recommended by the proposed alternatives would be expected to
develop schedule delay as a result of technical failure.  However, Alternative
A is the most likely alternative to  be  slower than expected.  Alternatives C
and D  would  take  longer  to implement due  to  new well construction but this
delay is accounted for in the schedule.

None of  the  alternatives  would  hinder  or  prevent  the taking  of   additional
remedial action.    The only  delays that  may  be  incurred  are  obtaining  any
required permits and the time to implement additional strategies.

Under  interim  remediation  status,  numerous monitoring  wells.were installed at
the  site and  existing water wells  identified near the  vicinity.    The site
geology  is complex.   However, it  is  not anticipated  that  any of the alterna-
tives,  if  implemented,   would   require  additional  monitoring   wells   to  be
installed.   There are monitoring wells between the contamination  plume  and
existing downgradient drinking water wells.
FIR:0067-R8S4                         4-30

-------
                                                                Date:  8/22/89
                                                                Final Revision
Summary of Implementability
Alternatives C  and D  are  most likely  to  be technically  successful  and meet
predicted schedule dates.  Alternative  A  is least likely to decrease contami-
nation levels to desired levels by the scheduled dates.

4.3.4.2  Administrative Feasibility
Currently,  the  air permit  for the  air stripper  limits  flow to  180 gpm and
various contaminant-specific emissions.   It is  anticipated that flowrates may
be modified, if a new air stripper were installed, but total facility emission
increases  would  not  be  allowed  to  increase.    Increases  in  emission upon
installation  of  an  air stripper  per  Alternative C may  approach  or   exceed
emission  standards or  the  75 percent  threshold  requiring  additional  moni-
toring.

The  NPOES  permit  currently  limits  discharges  to  the  Salinas  River  to
1,000 gpm.   High  flowrate  limits may be  exceeded  under  Alternative C.   Addi-
tionally,  some  debugging  may  be  needed   upon  installation  of  the  new air
stripper,  with  potential  upset  conditions  which  may cause  additional  moni-
toring.  Copies of the air permit and NPDES permit are found in Appendix A.

Alternatives  C, 0, and  E  all  require obtaining  leases, easements,  or pur-
chasing property  to allow  for installation  of  additional  extraction wells in
the  intermediate  aquifer.    Obtaining access  and  necessary  permits  would be
easier under Alternative E due to  the  fact that  only two wells (compared tc
five wells for  Alternatives D and E) would  be required.

Summary of Administrative Feasibility
Alternative  C would  be the most administratively  difficult  to achieve  due to
potential needs for air permit and/or NPDES modifications.  Alternatives C and
D wou.ld require more intermediate zone well  field  development than Alternative
E and much  less than Alternatives A and B,  which require no new well fields or
treatment systems.
FIR:0067-R8S4                         4-31

-------
                                                                Date:  8/22/89
                                                                Final Revisoon
4.3.4.3  Availability of Services and Materials
All  the  technologies  required  by  Alternatives  A  through  E  are  available,
demonstrated, and do  not  require licensing.  The treatment  methods of carbon
adsorption and air  stripping  have been well demonstrated  by the operation of
the existing treatment plant.

Ground-water extraction is  a  widely used method for  aquifer cleanup.   Alter-
native A  (No-Action Alternative)  is  the option  with  the  highest degree  of
technical risk.   Although  natural  degradation and  dilution will  occur,  the
specific  rate  at which  this  occurs  is dependent  on each  site's  character-
istics.  The effectiveness of a controlled ground-water extraction plan can be
predicted with greater certainty over simple, natural degradation and dilution
processes.

None  of  the technologies  used by  Alternatives A  to E would  require  further
development.  Predictive modeling will continue throughout the progress of the
cleanup to verify previous assumptions and assist in making any adjustments to
improve performance.  There is no limit to the scale which the technologies in
Alternatives B through  E  could be  implemented.   The  existing treatment plant
is  limited  to  a treatment  capacity of 650 gpm.  Alternative C would  require
installation of  additional  treatment capacity.  This  would  delay implementa-
tion due to the time required for design, procurement, delivery, and installa-
tion of the equipment.

Alternatives C, 0,  and E  require installation  of  new wells.   This will result
in  a  certain delay time  while permits and releases  from  landowners  could be
obtained.   Wells must be- installed during  the dry season.   Damage to fields
may occur if installation is performed during wet weather.  There is no reason
to expect qualified drilling contractors would be unavailable.  Implementation
of Alternatives C, D, and E would also be delayed while design, services, well
casing, .pumps, utilities, and pipe  are procured and installed.
FIR:0067-R8S4            •             4-32

-------
                                                                Date:  8/22/39
                                                                Final Revision
Alternatives B,  C,  0, and  E  would require operation of  the  carbon treatment
unit.   It is  estimated  that single-bed carbon  change  outs will  be required
about every three months  for the existing unit.   This  change  out period will
lengthen as remediation continues.  There is no reason to expect a shortage of
carbon  availability,  or  contractor  services  to remove  and dispose  of spent
carbon.

Summary of Availability of Services and Materials
Alternative A  would  be  the simplest  alternative  to implement,  requiring no
services or materials other  than  monitoring.   The  monitoring  period is longer
than  for  the  other  alternatives;  however,  the  operating cost  is   lowest.
Alternative C  has  the  highest risk  of disruption  due  to lack  of services.
However, based on historical operating data, this risk is very low.

4.3.5 Cost
This  section  summarizes  short-  and  long-term  costs   associated  with  the
implementation of Alternatives A through E.

The  estimates  were prepared  based on  current  operational cost  data  for the
existing  treatment  plant, quotes  obtained  from vendors,  and  historical  cost
data  extrapolated  to  current day  value.   The  accuracy  of  the  estimate is
+35 percent to  -20  percent.   No  inflationary  rate factors are assumed in the
cost  analysis.   No  contingencies  are  included because  the  costs  are  well
established from current operations.   There  should be  no  significant scope
changes once an  alternative  is selected for implementation.

Any  costs associated with  the  remediation  after the end  dates  stated in the
cost  summary tables are not  included  in the analysis.  These costs may  include
legal  fees,  mandatory site  improvements,  demolition of  the  treatment plant,
removing  or closure  of wells, and any long-term site monitoring  (SARA  Section
121  (c)).   No salvage value  was  awarded  for  the existing interim remediation
equipment  and  no capital  cost is  incurred by alternatives that  make use of
existing  equipment.


FIR:0067-R8S4                          4-33

-------
                                                                Date:  8/22/89
                                                                Final Revision
Table  4-3  summarizes the detailed cost  analysis  of Alternatives A through  E.
As  expected,  Alternative A  (no  action)  is the  least expensive to implement.
However,  it  does  have the highest risk  for not achieving the desired cleanup
levels  within  the  scheduled  time  period.   Alternative A  has  the highest
potential  for^ an overrun of  budget  due to an  extended  schedule but is  least
likely to overrun due to unforeseen  inflation or economic changes.

Alternative  B  does not require any  additional  construction.   However, Alter-
native B  ends  up being more  expensive  to  implement due to the  long  duration,
monitoring, and operating costs.

Alternative C has the highest cost of all the alternatives due to  installation
of  new wells,  and the requirements  to  expand  the treatment plant.   Economic-
ally,  Alternative C  has  no advantage over Alternative D which  is a similar
'remedial  action  plan but does  not require expansion  of the treatment plant.
Alternative  C  is  also predicted to  require longer to implement than Alterna-
tive 0 due to modification of permits.

Alternative E is  higher in cost than Alternative D  due to the predicted longer
duration required for completion and associated monitoring expense.

Potential Future  Cost
SARA requires an  evaluation of the potential for future  remediation.  Alterna-
tive A has  the highest potential  for  requiring additional  remedial  measures.
Alternatives  C  and  D   have  the  least  potential  for  requiring  additional
remediation.

The  greatest  probable additional  measures  for  Alternatives  C  and 0 which may
be  required  is  a longer pumping duration  than  estimated.  Alternatives A,  B,
and  E  are slow  and  have a higher  potential  to be  less effective.   The most
probable  additional  measures  necessary would  be  to implement  the  remedial
strategy  of  Alternative D.    However,  the  greatest  potential  future  cost
associated with  options  A,  B, and  E would  be  caused by the extended time for
 FIR:0067-R8S4                         4-34

-------
                                                                Date:  8/22/89
                                                                Final Revision
cleanup.  This delay may  allow  contamination  to spread to deeper aquifers and
expand the required cleanup efforts.

Summary of Cost
Alternative A  (the no  action  alternative)  would be the most economical option
to implement but carries  the  highest  degree of technical  risk.  Alternative D
is the  most  economical of the  action  alternatives.   Alternative D costs only
slightly more  than Alternative  A  and  achieves the desired objectives in about
one-third the time of Alternative A with lower technical risk.

4.3.6  Compliance with ARARs
A  summary of  examination  of  alternatives versus potentially  applicable  or
relevant and appropriate  requirements  is presented in Table 4-1.  Alternative
A  may not meet  ARARs for  either the  shallow or intermediate  aquifers,  and
alternative B may not meet ARARs for the intermediate aquifer.   In both cases,
the  alternatives  do not  involve  remedial  action, and an  indeterminate time
period  would  be  required for reaching cleanup  levels.   Reliance on passive,
natural  attenuation mechanisms for  attainment of  cleanup levels  for these
aquifers is required.  Alternative C will need to  obtain modifications of both
the NPOES' and MBUAPCD  permits to meet ARARs.

Most  of the ARARs and  other guidance criteria  to be considered are so specific
for this site  and actually define numerical remediation goals for chemicals cf
concern.  Agency experience  has shown that remediation goals may not be tech-
nically feasible to  achieve  in  the  modeled timeframes.  The remedial alterna-
tive^)  include evaluation  of system  operations and effectiveness at periodic
intervals.   In the event  remedial goals cannot be  achieved, the  RAP/ROD may be
amended  by  invoking the  appropriate ARAR  waiver.   Any such RAP/ROD amendment
would include  appropriate public participation.

4.3.7  Overall Protection of  Human Health  and  the  Environment
The  potential  risk  to  human  health and the  environment  is highest  under the
No-Action  Alternative  A, followed by Alternative  B, the  remediate   shallow


FIR:0067-R8S4                          4-35

-------
                                                                Date:  8/22/89
                                                                Final Revision
aquifer  only   alternative.      Both   these  alternatives   present   risk  of
contaminating  the  deep  aquifers utilized  for  irrigation and  drinking water
purposes by  relying  on only  natural  mechanisms and  irrigation  practices for
dispersion of contaminants.

Under Alternative C, the amount of contaminant capture is expected to be high,
but mass  balance releases  to the  environment  may be  increased in  terms of
quantity and  rate.    The entrainment of  lesser contaminated waters  into the
treatment system may result in lower percent contaminant removal.

Alternative D  appears to present the  best match of  protection  in  all  media.
Ground  water  will  be  selectively withdrawn  to  remove the  most contaminated
water sources first and affect maximum percent removal.  Alternative E appears
to be limited  by the  number  of wells  installed  into the intermediate zone and
may not adequately capture contaminants migrating  to  the  deeper aquifers, and
hence, be less protective than Alternatives C and D.

Summary of Overall  Protection
Alternative  D  provides  the  best compromise between  allowable  air  emissions,
contaminant capture, treatment efficiency, and respondent protection of health
andt the environment.    Alternative C  may  extract  the  greatest amounts cf
contaminants,  but  removal from  the treatment  stream  and  high  air  emission
levels  in  reference  to  the  air permits  may  occur..   Alternative  E  may net
adequately capture contaminants migrating to the deeper aquifers, Alternatives
A  and  B most  likely  will  not protect the  deeper  aquifers  from contamination
and potential human health and environmental risk.

4.3.8  State Acceptance
The state concurs with the remedy proposed.

4.3.9  Community Acceptance
There  is  no  community  opposition  to  the proposed  rerr.eay.    All  comments
received  have  been  addressed  in  the  "Response  Summary"   prepared   by  the
California Department of Health Services (Section 6 of this report).

FIR:0067-R8S4                         4-36

-------
                                                                Date:  8/22/89
                                                                Final Revision
4.4  SUMMARY OF DETAILED ANALYSIS
Table 4-2 provides a comparative summary of detailed analysis of the developed
remediation alternatives.   Synoptic  summary for each criteria  is  provided in
Section 4.3.   Alternatives A and  B  do not adequately respond  to  the ground-
water contamination problem  and  rely on passive mechanisms  to  assure ground-
water remediation.    Both  Alternatives A  and  B  have a  high  probability of
introducing additional contaminants to the deep aquifer.   Alternatives A and B
are potentially  low cost and easily implementable.   The  uncertainties in the
effectiveness of  these alternatives,  ability  to  reduce  risks  due  to further
ground-water  migration/degradation,  and compliance  with  ARAR's  render  these
alternatives unattractive.

Alternatives C, D, and E include installation of ground-water extraction wells
into the  intermediate aquifer  for remediation of contaminated ground water.
Alternatives C and D  include  installation  of  five  wells  into the intermediate
zone;  Alternative  E   includes  installation  of two  wells  only.     As  such,
Alternatives  C  and  0   are  expected to allow  greater  contaminant capture than
Alternative E.

Although  the  treatment  plant  is  upgraded  under  Alternative C, modeling  has
shown that high  flowrates  envisioned  under this alternative  may entrain large
quantities of uncontaminated ground  water.   Alternative  C  may  also require
modification  of  NPDES  and  MBUAPCD  air   permits.    Significant  de.lays  in
.installing the new air stripper under  Alternative  C  may  occur.   Alternative 0
appears  to  be  the   alternative   best  matched  to  the  site   conditions,  as
supported by  this detailed analysis.
FIR:0067-R8S4                         4-37

-------
5.©

-------
                                                                Date:  8/22/89
                                                                Final Revision
                       5.0  RECOMMENDED REMEDIAL ACTION


5.1  SUMMARY OF REMEDIAL ACTION

Alternative D  is  the recommended remedial  action  alternative,  based on the

detailed analysis presented in this FS/RAP (Section 4.0).  This alternative  is

summarized as follows:

      °  Installation and development of  five  (5)  new extraction wells in the
         120-foot aquifer.

      e  Disposal Alternative S, which is discharge of treated ground-water  to
         the Salinas River.

      •  A new,  approximately 1-mile-long pipeline segment  is  needed to con-
         nect the new extraction wells to the treatment plant.

      •  Treatment consisting  of  combined carbon adsorption and air  stripping
         with the existing treatment plant.

      •  Pumping and  treating ground-water from  the  120-foot aquifer concur-
         rently with the pumping from the shallow aquifer.

      •  Combined flowrate maintained at or below the capacity of the  existing
         treatment plant  of  650  gpm;  the wells  will  not be pumped  at their
         maximum flowrates.

      • 'Minimum flowrate of 400 gpm from the intermediate aquifer.

      •  Pump testing of each new extraction well.

      •  Well  field  configuration  in  the intermediate aquifer  appears  to  be
         well suited to the site geology.

      •  Effective  short-term,  with  low impact  on  the  environment during
         construction and implementation.

      •  Monitoring to continue in the shallow and intermediate aquifers until
         the  concentrations  have  remained   below the   ground-water . cleanup
         levels for two uninterrupted years..


5.2  ANALYSIS OF GROUND WATER SAMPLES  ,

Ground  water  samples from monitoring, extraction, and  agricultural  wells are

to  be  compared with  established  cleanup  levels for  each  of the ten  chenrica:

compounds  found  at the site.   Once the  remedial  pumping process has reduced
FIR:0067-R8S5                         5-1

-------
                                                                Date:  8/22/89
                                                                Final Revision
all concentrations  below cleanup  levels,  it  is planned  that  the  treatment
system will be shut down and placed on  standby.   Monitoring will continue for
two years, at a frequency to be determined in consultation with the regulatory
agencies.

If a sample from a well  that had  previously been below the cleanup levels for
any compound  shows  an  increase  to a value  that exceeds that  cleanup level,
immediate well resampling will  take place.   A  group  of four replicate samples
(not a  four-way split)  will be  taken.   Statistical  analysis  of  the results
will then  be  used to  decide if the initial  exceedance was  statistically sig-
nificant.  The  statistical  confidence  level to  be used  is  99 percent, with a
1 percent  chance  of  a  false negative,  that the mean  of the  four replicates
exceeds  the  cleanup  level.   A positive  result is a finding  from  the statis-
tical  analysis that the observed  exceedance of  a cleanup  level is statistic-
ally significant.   Subject to  revision  and  final  determinations during  the
detailed  design  of  the  selected  remedial action  system,  Student's  "t"  test
will be  used  in  the  statistical  analysis.   Other approaches  to be considered
during  final  design  include control chart  methods,  tolerance  intervals,  and
prediction intervals.    These  are all  accepted EPA methods  for  analysis  of
ground water data at  RCRA sites.

Under this procedure,'a positive  result  (i.e.,  a conclusion  that the ground
water concentration  has risen above  the cleanup  level)  would  mean  that  the
treatment  plant  would  be reactivated,  and  wells would be sampled  more  fre-
quently.  The increased sampling  frequency would continue until three consecu-
tive  period  samples   show  concentrations  below   cleanup   levels   for  all
contaminants.

5.3  DEEP AQUIFER CONTINGENCY PLAN
It  is  expected that pumping  in  the  intermediate aquifer will  intercept  the
plume of  contaminants from  the site and  that pumping in the deep aquifer will
not be necessary.  Levels cf contaminants in the deep aquifer, which  are (with
few excursions) below the cleanup  levels, are  expected to  decrease.   However,
FIR:0067-R8S5                         5-2

-------
                                                                Date:  8/22/89
                                                                Final Revision
there is the possibility  that  the cleanup system will not  be  as effective as

expected, and that more contamination  will  reach the deep  aquifer.   The fol-

lowing is a contingency for this situation.

      •  The deep aquifer  will  be monitored  on a quarterly basis, or as deter-
         mined by the regulatory agencies.  This will  include analyses for all
         of the  ten  standard contaminants which have been  found at the site.
         Cleanup  levels  have  been  established  for these  chemicals  in  this
         FS/RAP.    Deep   monitoring  wells  and  agricultural  wells  will  be
         monitored.

      •  Monitoring  Information will be used  to  evaluate  the effectiveness of
         the pumping from the  intermediate  aquifer.    If deep  aquifer wells
         show a rise in concentrations, adjustments  will  be made, if possible,
         to the intermediate pumping system  to halt  the  spread of contaminants
      ._  to the deep zone.

      •  If the concentration of any contaminant in  any  deep well is found and
         confirmed to be above  the cleanup  levels established  by this FS/RAP,
         the frequency of  sampling for  that  well and the immediately surround-
         ing  wells  will  be  increased to  monthly.   This  frequency  may  be
         adjusted  by the  regulatory agencies.   Sampling  will  continue  on  a
         monthly  (or as-specified)  basis  for any such  well until  three  con-
         secutive  periodic  samples  show  concentrations  below  cleanup levels
         for  all  contaminants.   Sampling  frequency will  then  revert  to  a
         quarterly  basis.    As  remediation  nears  completion,  Firestone  may
         petition DHS to further reduce the  sampling frequency of such wells.

      8  If the concentration for any contaminant in a deep well remains above
         the cleanup  level for  more than  one  year,  starting from the time the
         intermediate aquifer pumping begins, or if  any  concentration is found
         at any time which exceeds ten  times the cleanup level, then:

         1)  Firestone will  provide, for  any domestic or  drinking  water we"!
             with  concentrations  above cleanup   levels,    a  wellhead treatment
             system,  bottled  water,  or  other   interim  means   of  effectively
             protecting public  health  which  is approved  by   the  regulatory
             agencies.

         2)  For  agricultural  wells with  concentrations  above  cleanup  levels,
             Firestone  will   implement crop  uptake  testing  and   report  the
             results  to  the regulatory agencies, who will  then determine if
             further action is necessary.

         3)  Firestone  will   submit   to  DHS,   within  . ninety  days  and  in
             accordance with the requirements of the involved agencies, a plan
             for  remediating the deep aquifer.
FIR:0067-R8S5                         5-3

-------
                                                                Date:  8/22/89
                                                                Final Revision
         Firestone will  provide  the wellhead  treatment,  bottled  water,  or
         other approved protection on a shorter time frame  than  that  outlined
         above  if the  regulatory  agencies  determine,   due  to  changing  or
         unforeseen conditions,  that there  is  an  imminent threat to  public
         health or the environment from  deep aquifer contamination.

         If the concentration for any contaminant  in a  deep  well  remains above
         the cleanup  level for  more  than  eighteen months,  or above  ten times
         the cleanup level for more than three months, starting  from  the time
         that the Intermediate zone pumping  begins,  then  Firestone will  imple-
         ment the modified remedy according to the plan mentioned in  item 3
         above, as approved  by  the regulatory agencies.   The public will  be
         fully informed of any changes to the treatment  system at the time of
         implementation.    If any  changes  require  a  full  RAP/ROD  amendment,
         then the public will be fully involved as  required by  law before any
         such plan is  implemented.

         If data  from  deep  aquifer monitoring wells  indicate  that the down-
         gradient extent  of  contamination  in  the deep  aquifer  is no  longer
         known, then  Firestone will  monitor  wells  located further downgradient
         until the extent of- the plume is  again  known.   It is  possible that
         there are  other local  sources,  of chemicals  in  the  deep  aquifer,
         particularly  at  the  northwesterly end  of  the plume.
FIR:0067-R8S5                         5-4

-------
A

-------
STATE Of CAllfOBNIA— HEAITH AND WELFARE AGENCY                                  GEORGE DEUKME1IAM, Coemor
DEPARTMENT OF HEALTH SERVICES
TOXIC SUBSTANCES CONTROL DIVISION
•M51 BERKELEY WAY. ANNEX 7
  RKELEY, CA 94704
                              6.0  RESPONSIVENESS  SUMMARY
                       FORMER FIRESTONE TIRE AND RUBBER SITE

                            Analysis of Public Comments
                               Received on Draft RAP

                                  August 14, 1989

         I.    Introduction

              On July  13,  1989,  the  California  Department   of  Health
              Services held  a public  meeting  on the  proposed  remedial
              action plan for the former  Firestone Tire and Rubber  site,
              located  in  Salinas,  Monterey  County,  California.     The
              purpose of  the  meeting  was to  provide  the  public  with
              information  regarding  the  remedial  action  plan  and  to
              solicit public comments  on the  adequacy of  the  plan.    In
              addition,  comments  on  the   remedial  action  plan   were
              submitted to the Department during the public comment period
              which extended from June 27, 1989 to July 26, 1989.

              The verbal and written  comments which were received  during
              the public  meeting and  comment period  have been  compiled
              according to the agency, individual or meeting.  The purpose
             .of this document  is to  present a written  response by  the
              Department to these comments.

              A copy of the transcript of  the public meeting and all  the
              written comments received are available for review at:

              Toxic Substances Control      John Steinbeck Library
              Division                      110 West San Luis Street
              Region 2                      Salinas, Ca 93901
              5850 Shellmound, Suite 100
              Emeryville, CA  94608
              By Appointment Only
              (415) 540-3401

         II.   Comments and Responses

              The verbal  and written  comments which  were received  have
              been compiled  and categorized  by the  following   agencies,
              individuals or meetings:

              A.   Environmental Protection Agency
              B.   Public Water Supply Branch
              C.   Office of Planning and Research
              D.   Roy W. Fowler, Jr.
              E.   July 13, 1989 Public Meeting


                                        6-1

-------
                                                  8/22/89
                                                  Final
                        RESPONSE SUMMARY
A.   DBS RESPONSE TO  EPA ADDENDUM ON FEASIBILITY  STUDY/REMEDIAL
ACTION PLAN FOR FIRESTONE, SALINAS

Note: Underlined text indicates language proposed by EPA.

la.  EPA Comment:
     Page 3-4,  Section 3-2,  Paragraph  2: "above  the  drinking
     water  action  level."   What   action  level?   For   which
     compound?  This should be  revised to reference the  cleanup
     levels.  If DCE is referred to, a rationale as to why it  is
     a valid indicator parameter should be provided in the FS.

     DHS Response;
     DHS is in agreement with EPA that this statement needs to be
     clarified.  The phrase "drinking water action level" will be
     changed to state that  the plume maps  show areas above  the
     cleanup levels shown on page 2-6.

     1,1-DCE is referred to in section 2.2 and on page 3-4.
     Rational for using 1,1,1-TCA  and 1,1-DCE concentrations  as
     indicator  chemicals  has  been  expanded.   This   includes
     referencing earlier observations that  showed a decrease  in
     other chemical concentrations  as the  concentration of  DCE
     declined.

Ib.  EPA Comment;
     Page 3-17  implies that  No-action  cleans up  the  aquifer.
     This implication should be  removed.  No-action would  imply
     an escaping groundwate,r  plume at  concentrations above  the
     action levels.   While  it is  possible  that after  a  long
     period of time concentrations  would reach action levels  by-
     dispersion, it is  not within  common parlants  to refer  tc
     dispersion and dilution as "cleanup".

     DHS Response;
     In order  to clarify  any  misunderstanding caused  by  this
     paragraph, the following statement  (which is also found  in
     section 4.2.1) is included:

     Alternative A,  the No-action  alternative, is  required  by
     regulatory  guidelines  and  is  considered  as  a  baseline
     alternative.

2.   EPA Comment;
     Page 4-9, 4-10.  for Alternative  A state or  imply that  the
     alternative "cleans up" the  aquifer.   This language  should
     be removed or qualified clearly (see comment [Ib]).
                               6-2

-------
                                                  8/22/89
                                                  Final
3.
4.
     DHS Response:
     DHS does not believe that any implication is made that would
     suggest  that  Alternative  A  is  a  feasible  alternative;
     however, the  following language  is  added to  clarify  the
     definition of "cleanup" :

     This discussion under  Alternative A is  not meant to  imply
     that No-action will cleanup  the aquifer, rather that  after
     some time, the observed  concentrations of chemicals in  the
     aquifer will  decrease to  below  the groundwater  clean  up
     levels  due   to   natural  attenuation,   degradation   and
     diffusion.
     EPA Comment:
                Paragraph 2:   "Although  the proposed  NCP  rule
                         51394 has not  been promulgated and  the
                                has only been  issued as a  draft
                                provide ?&X&ywit/$i#$//?L$$i!0$?Z&-t2
                                ."   The  stricken  language   is
                                                            ARARs
     Page 4-3,
     revisions at 53 FR
     March 1988 RI/FS guidance
     document, these documents
               information  on
     inappropriate given the parallel it invokes.

     DHS Response:
     DHS feels that the  language may be  mistaken to mean
     and therefore concurs with EPA's change.
     EPA Comment:
     Page 4-4,  Paragraph (b).    Add as last sentence:  Compliance
     with ARARs  is a  threshold requirement.   All  alternatives
     remaining  in  the final analysis shall meet ARARs or have  an
     approved ARAR waiver.   It was not clear from the report that
     Firestone  understands  that meeting ARARs is not an  optional
     exercise (although it  is  stated fairly clearly in  Paragraph
     1,   page  4-8).    By   statute,  ARARs   must  be  met   and
     alternatives  which do  not meet ARARs cannot be retained  for
     analysis.

     DHS Response;
     While  the   last  paragraph   on  page   4.7  states   that
     alternatives  that do  not comply  with ARARs  will not  meet
     statutory  requirements for selection  of remedy in the  ROD,
     EPA's suggested  language is  added to  page 4-4,  paragraph
     (B).  With the following  change:  "...have  approved  ARAR
     waivers" to "...obtain ARAR waivers".
5.    EPA Comment:
     Page 4-8,   Section 4.2.1,
                                Sentence 3.
                   The  "no-action"  alternative  is  defined  as
     being  the  current  site  conditions,   absent  the  ongoing
                               6-3

-------
                                                  8/22/89
                                                  Final
     remedial measures.  The ongoing remedial measures consist of
     pumping and treating the qroundwater with carbon  adsorption
     and air stripping, and discharging the treated water to  the
     Salinas River.   Continued  groundwater  monitoring  is  not
     considered a remedial measure.

     DHS Response;
     The text has been changed to reflect EPA's concerns with the
     exception  of  the  last  sentence.   DHS  feels  that  this
     statement would  be redundant  given the  fact that  it  has
     already been stated that Alternative  A is not considered  a
     remedial measure  and  a  definition  of  cleanup  has  been
     provided.

6.   EPA Comment;
     Page 4-10, Section 4.2.2,  paragraph 2: "...That no  yftfyfs'^a'J
     {{see below}}  increases  occur  in  the  concentrations  of
     chemicals  in  the  ground   water.   After  two  years   of
     monitoring  with  no  ytyyi&YlftX  {{see  below}}  increase   in
     concentrations, all or  portions..."  The  word "unusual  is
     undefined and unclear.  What  is an "unusual" increase?   Is
     "unusual" based on statistical significance?  What numerical
     criteria shall be used to define significance?  These should
     be added.   Also,  it  is not  clear  from  this  discussion
     whether the  two  years  will  start  over  if  there  is  a
     significant increase.

     This same comment  applies to  the word  "unusual" on  Paaes
     4-12, 4-13, 4-18 and 4-20.

     Connected to  this issue  is the  fact that  CERCLA  Section
     121(c), 42 U.S.C. 9621(c), requires  that there be a  reviev
     of hazardous  waste  cleanups,  where  hazardous  substances
     remain on-site, at least every five years to ensure that the
     remedy  remains   protective  of   human  health   and   the
     environment.  The five years are counted from initiation  of
     the remedy.  If the remedy  does not remain protective,  EPA
     is instructed to use its  cleanup authorities once again  to
     address the problem.

     Thus, Firestone  could technically  dismantle its  treatment
     plant after  two  years with  concentrations  below  cleanup
     levels.  It  would merely  be necessary  to maintain  enough
     monitoring wells to review  the cleanup effectiveness  after
     five years.  However,  if levels increased  for any  reason,
     Firestone would be taking  a great risk  that an EFA  CERCLA
     Section  106  Order  would  be  issued  requiring  them   to
     reassemble the  treatment plant.   As is  clear to  Agencies
     now, there are many  instances where pump-and-treat  systems
     are shut down and the resulting change in equilibrium causes
     a desorption  of  contaminants  and  an  attendant  rise  in
     contaminant concentrations.

                               6-4

-------
                                             8/22/39
                                             Final
In order to  minimize Firestone's  risk as  well as  protect
public health, EPA therefore recommends that two  conditions
be  met  before  the  plant  is  dismantled:  two  years  of
monitoring, with treatment operating, in which no well  show
levels  above  the  cleanup  criteria;  and  two  years   of
monitoring with  the  pumps  shut  off  entirely,  in  which
contaminant levels do not rise above cleanup levels for  any
contaminant.  A review of the effectiveness can then be made
at the five-year point, and also at the end of the  process,
if the  end comes  at  a time  later  than five  years  from
initiation of the remedial action.

In order  to address  the vagueness  of "unusual",  and  the
five-year review  issue, the  referred wording  to be  added
under each remedial alternative (except A) is as follows:

The  shallow  and  intermediate  aquifer  extraction  system
(including extraction wells)  shall not  be abandoned  until
there has been;

1) with  treatment  operating,  an  uninterrupted  two  year
period  with   no  statistically-significant   increase   in
concentrations for any chemical, nor any concentration above
the cleanup levels established by this RAP;

2) with treatment shut down completely, an uninterrupted two
year period with no concentration for any chemical above the
cleanup levels established by this RAP.

The above two conditions shall apply over the entire aquifer
system as  a  whole;  not  for  one  aquifer  or  the  other
separately.

Effectiveness reviews shall be  performed by DHS and/or  EPA
after five full  years from  the initiation  of the  cleanup
action, and again before  the dismantling of the  extraction
system, if dismantling occurs after five years of initiation
of the cleanup action.

As cleanup  progresses,  certain  monitoring  wells  may  be
properly abandoned  by Firestone.   such abandonments  shall
require the prior  approval of  DHS and/or  EPA in  writing.
After  the   extraction   system  is   dismantled,   certain
monitoring  wells  shall  remain  available  for   sampling;
Firestone shall  apply to  DHS  and/or EPA  at the  tine  of
dismantling to  identify  the  wells  which  are  to  rer.air.
available.

A numerical criterion for "statistical significance"  should
be included.

DHS Response:

                          6-5

-------
                                                  8/22/89
                                                  F.inal
     The term "unusual" has been  deleted from the text.  In  its
     place, the text under each alternative states that Firestone
     is  currently  required  to  monitor  the  intermediate  and
     shallow aquifers  and will  continue to  do so  in order  to
     verify that  no  concentrations of  chemicals  exceed  their
     cleanup levels as established by this RAP.  If any  chemical
     in any monitoring well sample is detected above its  cleanup
     level, and the  analysis is confirmed,  the treatment  plant
     will be started up again.

     The monitoring period  for groundwater will  continue for  5
     years from the start of  the initiation of the final  remedy
     or for  a two  year period  after reaching  cleanup  levels,
     whichever occurs later.  Chemical concentrations must remain
     below cleanup levels for an uninterrupted two year period or
     the two year monitoring period will begin again.

7 .    EPA Comment;
     It is  indicated  on  Page 4-18  that  the  shallow  aquifer
     extraction wells will be shut down as early as August  1989.
     The wording of this alternative  should be expanded to  make
     it clear  that remedial  design will  determine the  pumping
     rates used from  all the  wells.  While it  should still  be
     noted that the wells may be shut down, it is still  possible
     that the wells will be  pumped for some time.  for  example:
     Shallow wells = 100  gpra, Intermediate wells  = 550 gpm,  is
     possible.

     DHS Response:
     The following wording will be added after the first sentence
     of section 4.2.4.3:

     The  pumping  scenario  described  below  is  for   modeling
     purposes only.  For actual conditions, pumping rates will be
     based on  the  monitoring well  design  and the  results  of
     aquifer  testing   and   monitoring.    Both   shallow   and
     intermediate aquifer wells can be  pumped at the same  time.
     However, the  pumping  rates for  all  intermediate  aquifer
     wells combined will have a minimum of 400 gpm.

8.    EPA Comment;
     The "Compliance With  ARARs" section  has several  problems.
     The greatest  of these  is that  it is  not clear  from  the
     report that the list of ARARs in the Tables will actually be
     complied with under the RAP.  Also of concern is that  ARARs
     are   referenced   summarily   as   "ARARs"   rather    than
     specifically.  Rather  that (sic)  explain each  problem  in
     detail,  we  have provided  our recommended  text changes  to
     solve these problems in as expeditious a manner as possible.
     The text here is from Section 4.3.6.  Stricken text is  shown
                Additions are shown  in italics (for purposes  of
                               6-6

-------
                                             8/22/89
                                             Final
this summary, they are shown underlined) .   Comments in
are in double brackets { {  } } .  This issue is critical.
                                                        text
"A summary of alternatives versus potentially applicable  or
relevant and appropriate requirements is presented in  Table
4-1. 'Alternative A may not meet #&#&& {{give specific ARARs
it may  not  meet  and  why)}  for  either  the  shallow  or
intermediate aquifers.  Alternative B  may not {{why  not?})
meet #£#££  ({give  specific ARARs}}  for' the  intermediate
aquifer.    Reliance   on   passive,   natural   attenuation
mechanisms  for  attainment  of  cleanup  levels  for  these
aquifers will occur.  W{J«Y Alternative C will meet ARARs if
permit modifications of  both NPDES and  MBUAPCD permits  %$
                         are obtained.
                   Most  of the  ARARs  and  other  guidance
criteria to be considered are z"0 specific for this site  and
actually define numerical remediation goals for chemicals of
concern.  Agency experience has shown that remediation goals
may not be  technically feasible to  achieve in the  modeled
timeframes.  The remedial alternative(s) include  evaluation
of  system   operations   and  effectiveness   at   periodic
intervals.  Should the ability  to obtain remediation  coals
become doubtful, the RAP will be amended accordingly  and/or
the appropriate ARAR waiver invoked.   Any such RAP and  ROD
amendment would include public participation in amending the
decision.
£. . . { {strike to end of paragraph.  Compliance with ARARs  is
a threshold criterion.  If any of the alternatives A-E  does
not meet ARARs  (i.e. those without  available waivers),  it
should  not  be  in  the  running  for  the  final  detailed
analysis. } }
"4.3.7  Overall  Protectiveness  of
Environment
                                     Human  Health  and  the
"The potential  risk to  human health  and the  environment,
#}WWti$/ttm//?#ty/Wy),  is  highest under  the  No-Action'
Alternative A,  followed  by Alternative  B,  the  remediate
shallow aquifer only  alternative.  Both these  alternatives
present risk of contaminating the deep aquifers utilized for
irrigation and drinking  water purposes by  relying on  only
natural attenuation mechanisms and irrigation practices  for

                          6-7

-------
                                              8/22/89
                                              Final
dispersion of  contaminants.
                                                ( {The   proper
place for such statements is in the summary  of  site risks  or
in the RI ,. not here . } >
"under Alternative C, the  amount of contaminant  capture   is
expected to  be  high,  but mass  balance  releases   to   the
environment may be increased in terms of quantity and rate.
                                            {{This  should   be
discussed  under  Implementability. } }   The  entrainment   of
lesser contaminated  waters into  the treatment  system   may
result in lower percent contaminant  removal .

"Alternative  D  appears  to  present  the  best   match    of
protection in all media.
                                      {{This  is an  artificial
constraint as far as the  Agency is concerned; therefore   it
is  not  a  consideration.   It  may  be  included  in    the
Implementability Section, however. }}..."

"Summary of Overall Protection

"Alternative  D   provides  the   best  compromise  between
jLJLJLW&M//fjL]t//£jlijLM]Lfi1lt  contaminant  capture,   treatment
efficiency, and  respondent  protection of   health  and   the
environment.  Alternative C may extract the  greatest amounts
of contaminants ,
        but result in lower removal efficiency.  ..."

...Skip to page 4-35, Paragraph 2, last sentence:

"As such, Alternatives C and D are expected to allow greater
contaminant  capture  than  Alternative   E,
                                            {(This is not  a
consideration here.)}  ..."

DHS Response;                     .
Section 4.3.6:   The text  has been  revised to  state  that
Alternatives A and B do not include remedial action and that
an indeterminate time  period would be involved for  reaching
clean up  levels  in  the  aquifers.   All  other  suggested
changes have been incorporated into the text.

Summary of ARAR  Compliance:  This is  an editorial  comment
that would not  change the  conclusion of  the FS/RAP.   The
"Summary of ARAR Compliance"  section does not  specifically

                          6-8

-------
                                                  8/22/89
                                                  Final
     state which ARARs will be  violated nor which waivers  would
     need to be  invoked; however, with  the additional  language
     requested for  Section 4.3.6.,  this  summary is  no  longer
     necessary and has been deleted.

     Section 4.3.7.:  All recommended deletions have been made,

     "Summary  of  Overall  Protection";   DHS  feels  that   the
     statement "... allowable air emissions..." should remain  in
     the text.   Air emissions  from  the treatment  plant  could
     present  a  health  risk  if  allowable  concentrations  are
     exceeded, and therefore should  be considered under  overall
     protection.

     The remaining deletions  and additions  indicated have  been
     incorporated into the text.

9.   EPA Comment:
     The wording which was added in the ARARs section,  regarding
     the contingency if  ARARs are  not met, should  be added  to
     each (accept for  Alternative A) of  the final  alternatives
     discussed:

     It is recognized  that the results  of computer models  have
     limitations, and therefore the best available predictions of
     ability and time to meet ARARs may not be accurate.  This is
     not  expected;  however,  this  remedial  alternative  would
     include evaluation of system operations and effectiveness at
     periodic intervals.   {{specify  as  closely  as  possible}}
     Should  the  ability  to  obtain  remediation  goals  become
     doubtful, the  RAP will  be amended  accordingly and/or  the
     appropriate ARAR  waiver  invoked.   Any such  RAP  and  ROD
     amendment would include public participation in amending the
     decision.

     DHS Response;
     This statement with some  minor modifications will be  added
     at the end of each alternative discussion (except for A):

     It is recognized  that the results  of computer models  have
     limitations, and therefore,  the best available  predictions
     of ability  and time  to  meet ARARs  may not  be  accurate.
     Therefore,   this   remedial   alternative   would  . include
     evaluation of  system  operations  and  effectiveness  on  a
     semi-annual basis based  on monitoring data.   In the  event
     remedial goals  cannot  be  achieved,  the  RAP/ROD  nay  te
     amended accordingly by invoking the appropriate ARAR waiver.
     Any such RAP/ROD amendment would include appropriate  public
     participation.

10.  EPA Comment:
                               6-9

-------
                                                  8/22/89
                                                  Final
     Page 4-29  does not  mention the  permit limits  on the  air
     stripper, nor  for  the  NPDES  permit.   This  is  critical
     information to  the FS  as  it is  a  primary ARAR  for  the
     preferred alternative.  The discharge limits, for mass  rate
     and  contaminant  loading,   where  applicable,  should   be
     provided in full and be easily accessible.

     DHS Response;
     The maximum  flow  rates  for the  air  stripper  and  NPDES
     permits are  given on  page 4-28.   In addition,  copies  of
     these permits are included in Appendix A for reference.  For
     clarity, the  text  was  revised  to  refer  the  reader  to
     Appendix A.

11.  EPA Comment;
     The plume diagrams shown in the simulations show a piece  of
     the intermediate zone plume moving off downgradient.   While
     the capture  zone figures  seem to  show that  the plume  is
     captured,  there  is  uncertainty.   This  is  an  extremely
     critical issue.   The  RAP  should be  explicit  as  to  the
     testing to be performed and as to how extraction wells shall
     be sited in order to ensure that the plume is captured.  The
     following suggested language is provided to be added to  all
     alternatives at  the point  that well  siting is  discussed.
     This pertains .to Alternatives C, 0,  and E:

     A primary  objective  of the  remedial  effort shall  be  to
     ensure that the  plume of contaminants  in the  intermediate
     aquifer is completely contained.  Accordingly, once the  nev
     extraction wells are  installed, they  shall be  immediately
     sampled   for   contaminants	to   determine   the	real
     concentrations at  the well  points.   If  necessary, one  or
     more additional wells will be installed further downgradient.
     and/or pumping  rates adjusted  to ensure  that the  capture
     zone is completely containing any portion of the plume  with
     contaminant concentrations above the  cleanup level for  anv
     contaminant.

     Once pumping has commenced, aquifer  tests shall be performed
     to verify  the  true zone  of  capture for   the  wells.   If
     necessary,  another   well   will   be   installed   further
     downqradient and pumping rates adjusted accordingly so  that
     any portion of the plume containing  concentrations above the
     cleanup  levels  for  any  contaminant  is   contained.   The
     results of  this assessment  shall be  reported to  DKS  and
     copied to EPA.

     DHS Response:
     The concerns raised in this comment  are mainly the result of
     the limitations of the computer models used.   However, these
     limitations are not spelled out, and therefore the  diagrams
     could easily be  misinterpreted by  the uninitiated  reader.

                              6-10

-------
                                                  8/22/89
                                                  Final
     In order to  mitigate this potential  problem, the text  has
     been revised  to  state that  a  primary objective  of  this
     remedial effort shall be to establish a zone of capture  for
     the chemicals  above  cleanup  levels  in  the  intermediate
     aquifer.   New  extraction   wells  will   be  sampled   for
     contaminants.  If  necessary,   additional  wells  will   be
     installed further downgradient and/or pumping rates adjusted
     to ensure that  the capture zone  intercepts any portion  of
     the plume with contaminant concentrations above the  cleanup
     level.                           .                          .

     The inclusion of  the following statement,  "The results  of
     this assessment shall be reported to DHS and copied to  EPA"
     is not necessary in  this report as it  will be included  in
     the Remedial Design.

12.   EPA Comment:
     Given that there is contamination in the deep aquifer (below
     the 120-foot zone) there should be a contingency in the  RAP
     for the  possibility  that  the  deep  zone  comes  to  have
     contaminants above the cleanup  levels.  Such a  contingency
     could likely be carried out by adding more wells in the deep
     zone and modifying the  treatment plan (including the  NPDES
     and air  permit) to  increase  plant capacity.   This  would
     probably require a public notice  but would not represent  a
     fundamental change to the remedy and thus would not  require
     a RAP or ROD amendment  nor a second public comment  period.
     The probable schedule  for implementing  such a  contingency
     system, along with the  general design parameter, should  be
     included.

     In order  to plan  for  this contingency,   Firestone  should
     submit  requests  for  "contingent"  NPDES  and  air  permit
     modifications  to  the  appropriate  agencies   immediately.
     These would request approval for flow rate increases in  the
     event,  and only in  the event, that  deep aquifer levels  go
     above the  cleanup  levels.    This approach  has  been  used
     effectively on other sites.   This   would allow action to  be
     taken  quickly  if  pumping  in  the  deep  aquifer  becomes
     necessary.

     It is recommended  that a contingency  plan,  including  such
     permit requests, be spelled out  in the RAP to address  this
     possibility.  This should indicate  that public notice,   via
     local newspapers, would be given if such changes are carried
     out.

     DHS Response;
     Modifications to the existing NPDES permit is not an  option
     available to  Firestone at  this time.    DHS discussed  this
     contingency with the  Regional Water  Quality Control  Board
     and was told that  the the Board  will  not issue  contingent

                              6-11

-------
                                                  8/22/89
                                                  Final
     NPDES permits.  In addition, it is DHS' opinion that cleanup
     of the deep aquifer by  EPA's proposed method would  require
   •  major modifications  to  the existing  treatment  plant  and
     significant increases in groundwater extraction rates.  Such
     changes would  require amendments  to the  State's RAP,  and
     also an additional public comment period.

     As a contingency in the event that the intermediate  aquifer
     extraction  system  is   not  found  to   be  effective   in
     maintaining chemical  concentrations  in  the  deep  aquifer
     below  the  established   cleanup  levels,  the   regulatory
     agencies will  re-evaluate the  extraction system  and  deep
     aquifer, and take the appropriate actions.

     A contingency for the deep aquifer has been added to section
     5 which will include monitoring  of the deep aquifer and  an
     evaluation of the intermediate zone extraction well  system«
     If any  chemical concentration  is found  above its  cleanup
     level, monitoring of  that well will  be increased.  If  the
     concentration of  any chemical  in a   domestic or  drinking
     water well in  the deep  aquifer•remains  above its  cleanup
     level within one year  of the initiation  of pumping in  the
     intermediate aquifer or if any concentration is found at any
     time to exceed ten times its cleanup level, then a well head
     treatment system shall  be established for  that well or  an
     alternate drinking water source  shall be provided.  If  the
     same conditions are found  for the deep aquifer  agriculture
     wells, the crop  testing program specified  in the  Remedial
     Action Order will be instituted.

     If after eighteen months of the initiation of pumping in the
     intermediate aquifer  the concentration  of contaminants  in
     the deep aquifer remains above  cleanup levels or above  ten
     times the cleanup  levels for more  than three months,   then
     Firestone  will  submit  to  DHS  within  90  days,  and  ir.
     accordance with the requirements of the involved agencies,  a
     proposal for modifying  the remedial system  to include  the
     deep aquifer.

     In addition, if data from the deep.aquifer monitoring  wells
     indicate that the  downgradient extent  of contamination  of
     the deep aquifer  is. no  longer known,   then Firestone  will
     install additional monitoring  well(s)  until  the extent  of
     the plume is known again.

13.  EFA Comment:
     Figures 3-2 through 3-8, 4-1,  4-2,  4-3,  etc. show  contours
     without  labels.    These  should   be  labeled   with   the
     appropriate level and  units.  If these  are 6 ppb  contours
     for DCE, it should be shown  or discussed in the text as  to
     why DCE is a  valid indicator for  plume extent.   Are  there'
     instances where  DCE is  below 6  but other  parameters  are

                              6-12

-------
B,

I.
                                                  8/22/89
                                                  Final
     above their  cleanup  level?   Where  might  this  be  true?
     Indicate in the text.

     DHS Response:
     Contours in figures 3-2 through 3-8, 4-1, 4-2, etc. have all
     been appropriately labeled.  Monitoring well data shows that
     DCE or TCA is the dominant chemical found in the wells.   In
     addition, the rational for using DCE is included in Sections
     2 and 3 as stated earlier.
DHS Responses to Public Water Supply Branch (PWSB)

PWSB Comment:
Section  2.2.2   Allowable  Concentrations  Based  on   Risk
Assessment

The maximum  contaminant levels  (MCL) for  several  organic
chemicals  listed  on  page  2-2  need  to  be  revised  and
incorporated  into  the  list.   The  chemicals,  MCLs,  and
effective dates are as follows:
     Chemical
                    MCL (uq/1)
Effective Date
     Carcinogens:
     1,2-DCA             0 . 5
     PCE                   5
     Benzene               1

     Noncarcinogens:
     1,1-DCE               6
     Ethylbenzene        680
     Xylenes (*)        1750
                                       April 5, 1989
                                       May 5, 1989
                                       February 25,1989
                                       February 25, 1989
                                       February 25, 19.29
                                       February 25, 1939
     (*) For a single isomer or sum of isomers


                       2-2 have been  revised to incorporate
DHS Response;
The MCLs on page
list provided.
     PWSB Comment:
     Section 4.0  Detailed Analysis of Remediation Alternatives

     The Public Water Supply Branch concurs that Alternative D is
     the most feasible, timely,  cost effective, and  technically
     acceptable alternative  available  to  decrease  contaminant
     levels in the intermediate  aquifer.  However, the PWSB  has
     concerns with respect to remediation of the deep aquifer.

     In reviewing the various alternatives, there is no provision
     to continue  to  monitor  the deep  aquifer  wells,  for  an
     assessment of the data, and  for a determination to be  made
                              6-13

-------
                                              8/22/89
                                              Final
if remediation of  the deep aquifer  is needed.   It   appears
that  final  remediation  will   only  be  limited  to  ' the
intermediate aquifer.   In Fact  Sheet  #9, June  28,   1989,
there is  no  indication  that  contamination  of  the  deep
aquifer has occurred.

Data from the Harden 12 AG  well has been used to  determine
the  trend  of  concentrations  of  chemicals  in  the  deep
aquifer.  This source  shows a decreasing  trend of   1,1-DCE
over a three year period.   Based on this trend, the  report
has indicated  that a  downward trend  is also  expected  of
Wells ITM17A  and ITM18A,  which have  1,1-DCE levels   above
drinking water standards.

In addition, the report indicates that "Because agricultural
use of the. water has generally decreased the  concentrations
to a relatively low level of chemicals in the aquifer or has
prevented large  increases  of concentrations  of  chemical,
and, this  can be  expected to  continue in  the future,  no
alternative  requiring  additional   extraction  wells   are
planned for the deep aquifer."

A  review   of  data   from   other  deep   aquifer   wells,
specifically, California Water  Service company Station  21,
Well ITM117A, and Well ITM18A, shows an increasing trend  of
1,1-DCE over a one to three year period.  Based on the  trend
of these wells, the proposal  of no need for remediation  of
the deep aquifer seems premature.

The  PWSB  recommends  that:  (1)  the  deep  aquifer   wells
continue  to  be   monitored  during   remediation  of   the
intermediate aquifer, (2) water  quality data from the  deep
aquifer wells  be  reviewed  to  determine  if  contaminants
present  are  at  an  acceptable  level  for  public  health
protection, and (3) the need for further remediation of  the
deep aquifer be based  on water quality  data from the  deep
aquifer wells, not the intermediate aquifer wells.

DHS Response:
DHS is in agreement with  the PWSB.  Firestone is  currently
required to monitor the deep aquifer and will continue  to be
required to  monitor  the  shallow,  intermediate  and  deep
aquifers in order to verify that no chemical . concentrations
occur above the cleanup levels established by this RAP.    If
any chemical in any  monitoring well sample  is found to  be
above its cleanup level,  and the analysis is confirmed,   the
treatment plant will be started up again.

The monitoring period  for groundwater will  continue for  5
years from the start of  the initiation of the final  remedy
or for  a two  year period  after reaching  cleanup  levels,
whichever occurs later.  Chemical concentrations must remain

                         6-14

-------
                                                  8/22/89
                                                  Final
     below cleanup levels for an uninterrupted two year period or
     the two year monitoring period will begin again.

     As a contingency in the event that the intermediate  aquifer
     extraction  system  is   not  found  to   be  effective   in
     maintaining chemical  concentrations  in  the  deep  aquifer
     below  the  established   cleanup  levels,  the   regulatory
     agencies will  re-evaluate the  extraction system  and  deep
     aquifer, and take the appropriate actions.

     Please refer to EPA comment  number 12 for a description  of
     the contingency.

3.   PWSB Comment:
     Table 2-5, Organic Constituents, Water Quality Goals - Human
     Health and Welfare

     The  State  adopted  MCLs  for  tetrachloroethylene   (PCE),
     1,1,1-Trichloroethane (TCA) and Trichoroethylene (TCE)  need
     to be added  under the  heading of "State  and EPA  Drinking
     Water Standards, MCLs, State".   The MCL and effective  date
     of the chemicals are as follows:

     Chemical	MCL (uq/1)	Effective Date

     PCE                       5            May 5, 1989
     TCA                     200            February 25, 1989
     TCE      .                 5            February 25, 1989

     DHS Response:
     The MCLs for PCE, TCA and TCE have been added to Table 2-5.


C.   Comment from Office of Planning and Research:
The State Clearinghouse submitted  the above named  environmental
document [Firestone  Tire and  Rubber Co.,   Remedial Action  Plan
SCH# 89062710] to selected state agencies for review.  The  state
agency review period is now closed and none of the state agencies
have comments.

DHS Response:
None required.

D.   Comment by Roy W. Fowler,  Jr.:

At our meeting on April 19, 1989 at Spreckles, representatives of
Firestone Tire and Rubber Company reviewed salient aspects of the
Remedial Action Program and the proposed Negative Declaration for
the above captioned project.

Since I have not heard anything  further as to the schedules  for
public comments, I am forwarding a  letter to you that I sent  to

                              6-15

-------
                                                  8/22/89
                                                  Final
Firestone which,  in  part,  describes the  general  area  of  my
concern, i.e., well abandonment and recharge.

Please place this letter into the file as my interim comments and
please send me your most recent schedule for public comment time.

DHS Response;
OHS acknowledges that there  is a proposal  to reuse the  treated
water from  Firestone's  treatment  plant  and  to  install  more
production wells.  Any new proposals of this nature would have to
consider the impact on the migration of the groundwater plume  as
well as its impact on the  recharge of local groundwater flow  by
addressing the issue in an Environmental Impact Report.

E.   July 13, 1989 Public Meeting:

Comments and responses may  be found in the  copy of the  meeting
transcript which is included in this summary as appendix A.
                              6-16

-------
                                                    APPENDIX A
 2

 3                            PUBLIC  MEETING
                         FORMER  FIRESTONE FACILITY
 4                           SALINAS,  CALIFORNIA

 5

 6

 7                     SALINAS HIGH  SCHOOL AUDITORIUM
                              JULY  13,  1989
 8                               7:00  P.M.
 9

10

11

12

13

14

15
16         DEPARTMENT OF  HEALTH  SERVICES
           Ms. Shirley  Buford
17         Mr. Ric Notini

18
           FIRESTONE:
19         Dr. Alan Altenau

20
           IT _C_0 RPORATION:
2.1         Mr. Chan Weisel
           Dr. P.. Nichols Hazel wood
22         Mr. R. Leonard Allen
23

24

25

26
             SUSAN D. KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1                    HEARING COMMENCED AT 7:20 P.M.




 2              SHIRLEY BUFORD.:.,  Good evening, ladles and




 3         gentlemen.  I'd like to welcome you tonight to the




 4         Remedial Action Plan and the negative dec and the




 5    "     proposed alternatives meeting for the Firestone site




 6         facility here in Salinas.




 7              My name is Shirley Buford.  I am with the




 8         Department of Health Services, community relations




 9         coordinator, and I will be your moderator tonight and




10         also will present to you the speakers from the




11         Department of Health, Firestone, the IT Corporation,




12         and also there are members here from the Environmental




13         Protection Agency and the Water Control Board -




14         Central Coast of San Luis Obispo.




15              I would like to talk with you just a little bit




16         about the purpose of this meeting tonight.  It is to




17         involve you, the public, in the decision that will te




18  .       ir.ade on the final cleanup plan for the Firestone




19         facility.




20              Community relations is mandated by both federal




21         and state laws and it usually involves us getting




22         involved and getting into the community at the very




23         beginning of discovering a site with hazardous




24         wastes.  During the process of the cleanup we held




25         public meetings, provide fact sheets and other




26         information for the public, including making a place






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1




 2




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




.24




25




26
for documents to be placed for the public to corr.e arc?




look at; that's called an information repository.   In




this case the information repository is locatec at  the




John Steinbeck Library.  And in that library you will




find the nine fact sheets distributed by Firestone,




information on the meetings that were held during the




process of the cleanup, and various documents related




to the cleanup at the site.




     We also mandate that Firestone develop a mailing




list and inform the community around the facility of




the investigation and the cleanup work taking place




there.




     Tonight you all have picked up an agenda, I hope,




from the front.  We'd like to go through, for your




information, the people who will be speaking to you




tonight will be Mr. Ric Notini from the Department  of




Health Services.  Ric Notini is the chief of the site




mitigation unit.




     We have Doctor Alan Altenau.  Doctor Alter.au is




the director of technology for Firestone.  He is




responsible for all environmental work and research




and de-velopment, including quality assurance ar.c




industrial hygiene.




     Next on our agenda is Mr. Chan Weisel who is the




general manager for IT Corporation for Northern




California.  He is the project director for the
             SUSAN D. KUCHER, CERTIFIED SHORTHAND  REPORTERS

-------
 1         Firestone Salinas works.




 2              Doctor Nick Hazelwood is the senior, technical




 3         specialist and route manager for the IT Corporation,




 4         and he is in charge of preparing Firestone risk




 5         assessment.




 6              And finally on our agenda we have Mr. Leonard




 7         Alien who is the senior project manager and




 8         geotechnical engineer in charge of the Remedial




 9         Investigation and Feasibility Study for the Firestone




10         facility.




11              After the.presentations, we will put together a




12         question and answer panel.  And there is some other




13         agency people I will introduce to you later who will




14         be available to answer questions on the site, on the




15         Remedial Action Plan draft, and the proposed plan for




16         cleanup.




17   .           At this time I'd like to introduce Mr. Ric Notini




18         from the Department of Health Services.




19              RIC NOTINI:   Thank you, Shirley.




20              What I would like to do over the next few minutes




21         is briefly describe the process of cleaning up a




22         hazardous waste site in California.




23              The State Department of Health Services is




24         responsible for investigating and remediating




25         hazardous waste sites in California.   We are presently




26         involved in the investigation and cleanup of over 300






             SUSAN D. KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1




 7.




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
sites across the state,  and Firestone is one of those




sites.




     The topic that I am supposed to talk about is the




state process.  What that really refers to is a




process that we have established to help insure that




these sites are cleaned  up to a satisfactory degree.




Every site that we're actively working on is describee!




in a report called Expenditure Plan for the Hazardous




Substance Cleanup Bond Act of 1984.  It was a law that




was passed in 1984 that  provided us funding to oversee




the investigation and cleanup of the sites.  So




Firestone is one of the  300 sites that's discussed in




this report.  And this report also describes in a let




more detail the process  that I am going to briefly go




over.




     I want to first mention that the process of




investigating and cleaning up a hazardous waste site




involves a lot of different agencies and requires a




lot of coordination.  And I just want to acknowledge




the assistance and help that we have gotten from a




number of other agencies including the Monterey County-




Health Department, the Regional Water Quality Control




Board, and the Federal Environmental Protection




Agency.  We do have representatives from those




agencies here, so if you come up with a question




specific to that agency, we'll ask them to help us
             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         out.




 2              I have.a co.uple of: overheads;. I want to show  and  I




 3         am going to have to step away from the mike, so I will




 4         try to speak up a little louder.




 5              This overhead shows the two laws that we use to




 6         investigate cleanup sites.  There is the Federal




 7         Superfund Law, which is also — the long name is




 8         actually called the Comprehensive Environmental




 9         Response Compensation and Liability Act, commonly




10         referred to as Federal Superfund.  And the State




11         Superfund Law has the Hazardous Substance Cleanup Bond




12         Act.  These are the two laws that provide us the




13         authority to investigate and cleanup these sites.




14              Now this Firestone site is actually considered




15         both a State Superfund site and a Federal Superfund




16         site.   Back in 1987 the Firestone site was proposed cr




17         actually added on to the Federal Superfund list, which




IB         is known as the National Priorities List.  So the




19         cleanup is going to have to satisfy not only State




20         requirements,  but Federal requirements as well.




21              If I could show the next overhead.   This gets




22         into the cleanup process, and I will move through this




23         rather quickly.  The first step involves discovering




24         the site.  And the first thing we do when we receive




25         either a complaint from a citizen or a report from a  t




26         company or perhaps another agency refers some






             SUSAN*D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1

 2-

 3

 4

 5

 6

 7

 8

 9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26
 information to us  indicating that  there  has  been  a

 leak  or  spill of a hazardous substance,  we conduct  a

 preliminary site assessment.  We try and determine  if

 there has, in fact, been a spill or leak, whether or

 not that spill or leak presents an actual or  potential

 threat  to public health or the environment.
      •

      Based on that, if we decide it it looks  like a

 significant enough of a problem, we move to  the next

 step, which is the Remedial Investigation.   What  that

 really  means is defining the problem, finding  out what

 is the  nature and extent of the contamination, and

 what  kind of a threat does it pose to public  health or

 the environment.  That study involves going  out and

 collecting samples of soil, air and groundwater,  very

 often,  and typically takes several years to  complete.

      Now during that time if there are some  things

 that  we  can do right away to begin to address  the

 problem, we call those interremedial measures.  Anc,

 in fact, at the Firestone site back in  '84 and  '85,

.they  actually excavated contaminated soil and

 installed some wells and began extracting some of the
         i
 contaminated groundwater.

      Once the Remedial Investigation is  completed the

 next  study we perform is a Feasibility Study,  which

 really  means trying to determine what's  the  best  way

 to complete the cleanup, looking at various
             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1




 2



 7





 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
alternatives.  And that is what v/as recently completed




by Firestone.




     In addition to that, the next step involves




preparing a Remedial Action Plan.  And the Remedial




Action Flan summarizes the results of the Remedial




Investigation and Feasibility Study and discusses the




cleanup alternative that is being proposed.




     In addition to that we are required to hold a




public meeting and provide for a 30-day public comment




period.  And we review and solicit comments from you




and review those comments, prepare a written response




to those comments before approving of a final Remedial




Action Plan.




     So Shirley mentioned that we have a public




comment period now which ends, I believe, the 27th of




July.  You have until then to provide us with your




comments.  We will review those and then try and




approve of a Remedial Action Plan based on the




comments we have received.




     Following the Remedial Action Plan, Firestone




will be required to prepare a remedial design, which




involves all the engineering design necessary to




install the systems that they propose.  Then they are




required to implement it and operate and maintain it




for as long as necessary.  I might mention that all of




this work up to now has been done by Firestone and
             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1        . paid by Firestone under oversight of the Department of




 .2         Health Services.




 3              The last thing I wanted to discuss is the




 4         California Environmental Quality Act.   As part of the




 5         process of investigating cleaning up the site, we must




 6         also make sure that we are complying with other state




 7         laws.  The California Environmental Quality Act is one




 8         of those laws that, is applicable.




 9              We have prepared a document known as an Initial




10         Study.  And based on that study we-have determined




11         that the proposed cleanup will not have any




12         significant environmental impacts; therefore, we have




13         filed a proposed negative declaration and do not plan




14         on performing an environmental impact report.  That is




15         also an item we are interested in receiving your




16         comments on.  So we have proposed a negative




17         declaration for this site.




18              That is all I have to say.  The speakers




19         following me will specifically discuss the Firestone




20         site and I will be available for additional questions




21         you might have.  Thank you.




22         .     SHIRLEY BUFORD:   Thank you, Ric.




23              The next speaker is Doctor Alan Altenau from




24         Firestone, and he is the director of technology for




25         Firestone.




26              Doctor Altenau?






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1              ALAN ALTENAU:   Thank you very much and good




 2         evening.




 3              I would like to briefly discuss some of the




 4         background of the site and a brief overview of the




 5         work and progress that has gone on since environmental




 6         investigations have begun back in 1983.




 7              Firestone manufactured tires at the Salinas plant




 8         from 1963 to 1980.  The plant was closed in 1980, and




 9         during the closure of the plant,  equipment removal and




10        . so forth, environmental investigations were begun.




11         These investigations were begun in cooperation with




12         the Department of Health Services of California.




13         During these investigations we noted there was some




14         soil contamination and some contamination of the




15         groundwater.




16              In 1984, proceeding along with our




17         investigations,  we moved to the off-site area as. we




18         were beginning to learn more about the on-site




19         contamination that existed.  Also in 1984,  as a result




20         of the 1983 investigations which  indicated some soil




21         contamination, we removed over 5,000 cubic yards of




22         contaminated soil and disposed of that soil properly.




23         That really begun an approach that we followed




24         throughout this  investigation and study as where we




25     .    found contamination, we immediately took remedial




26         action to correct that problem rather than waiting for






             SUSAN D. KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         all the investigations to be finished.  So this was




 2         the first piece of remedial action that we have




 3         carried out by removing all the soil.  We also removed




 4         underground storage tanks and any contaminated soil




 5         that might be associated with the removal of these




 6         tanks.




 7              In 1985, again as a result of some of the initial




 8         investigation showing contaminated groundwater




 9         on-site, we began construction of an on-site




10         groundwater extraction system and treatment plant.  So.




11         as the water would start moving from on- tc off-site,




12         we could capture that contamination before it would




13         leave the site.  So that construction was begun in




14         1985.




15              Now the chemicals that we showed as contaminants




16         in the soil and groundwater were several chlorinated




17         type of chemicals.  These chemicals typically were




18         used — some of these chemicals were used in the




19         cleaning of equipment.  So during that, small amounts




20         of spillage in the cleaning of equipment, some of




21         these chemicals got in the soil, went through the




22         soil, finally into some of the groundwater.  Arc scir.e




23         of the chemicals really resulted from degradation,




24    -     natural degradation of these chemicals in the soil to




25         other chemicals.  So it wasn't chemicals used in the




26         manufacturing process, but small amounts of chemicals






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1




 2,




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
used to clean equipment, things like that.



     In November of 1985 an extensive amount of crop



testing began.  Various crops were tested to determine




whether there was any takeup of any of this



contamination during the irrigation process.  The




results showed there was no chemical contamination in



any of these crops.  The same kind of investigation



continued off and on over a period of time and further



verified there was no contamination present in these




crops.




     In 1986, start of the treatment plant began,




again capturing contamination in the groundwater




before it would go off-site.  This contamination that




we're extracting is what we call in the shallow




aquifer down to about 90 feet.  When we use the term




"aquifer," that means different bodies of water in the




groundwater, and sometimes they are separated by clay




layers.  And in the site here we have different




aquifer levels, maybe 100, 200, 300, 400 and so




forth.  So we have investigated over time these




different aquifer levels, which are bodies of water




separated by impermeable clay layers.  So this



extraction plan was extracting and cleaning water up




from the shallow aquifer, roughly 90 foot aquifer,



before it leaves the site.




     In August of 1986 the Department of Health
             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         Services approved an off-site deep g.roundwater

 2         investigation plan.  This was a plan designed to very

 3         thoroughly investigate the off-site area — very far

 4         off-site actually — to determine the extent of

 5         contamination and to better define where the

 6         contamination is.  The results of this investigation

 7         indicated that the contamination off-site is a rather

 8         narrow band of contamination which we would call a

 9         plume, but it's just an area where the contamination

10         exists.  But it was not wide-spread, it was somewhat

11        . narrow.  And the plan also indicated why it stayed

12         narrow due to the geological formations around the

13         area.

14              In 1987 we continued routine well sampling and

15         that showed no additional agricultural or municipal

16         wells with contamination.  We continually monitor

17         various.wells.  And this is just a note that 1987, at

18         that point since the investigations began in 1983, we

19         found no additional well contamination in the

20         agricultural or municipal wells.  And I think part of

21 •        that is the quick remedial action we have taken at the
                    i
22         beginning in removing quite a bit of all the

23         contaminated soil as well as putting an on-site

24         extraction treatment plant functioning to reduce the

25         possibility of further contamination of going

26         off-site.


             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1              In April of 1987 DHS approved well locations for


 2'        the
-------
 1




 2




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
contamination at this site.



     In December of 1988 we issued a very extensive




Remedial Investigation report,  which is really a




compilation of all the analysis, results and




conclusions that took place over these years during




our investigations.




     In June of this year the Department of Health



Services approved this Remedial Investigation report.




During the time they were reviewing this report we




were preparing a document called a draft feasibility




study.  And this was a document really which follows




from the Remedial Investigation report, which by




looking at the results of this Remedial Investigation,




what would be appropriate alternatives for further




additional remedial action.  And a number of




alternatives were listed and considered.  And from




these potential alternatives for future remedial




action, a document, the Remedial Action Plan, would




follow which would be the selection of the most




appropriate alternative listed  in the draft




feasibility report.  .And tonight later on we will be




discussing the proposed Remedial Action Plan for




further action at this site.




     In June of 1989 DHS announces a proposed final




cleanup plan which followed from the Feasibility Study




and is now part of the Remedial Action Plan, and that
             SUSAN D. KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
  1          was  discussed  in  fact  sheet  number nine.



  2               As  mentioned previously, DBS proposed  a negative




  3          declaration  for the  Remedial Action Plan which  says




  4          that DBS does  not see  any environmental problems  from




  5          carrying out this Remedial Action Plan that is




  6          proposed.




  7              _June  27th, published notices for public meeting




  8          and  a comment  period,  which  is one month.  We're




  9          having a public meeting today and the comment period




 10          ends July  27th.




 11               So  that's a  very  brief  overview of the work  and




 12          progress that  has gone on over these last number  of




 13          years.




 14               WALTER  WONGs    Doctor Altenau, I know  this is the




 15          wrong time,  but I think it's important while you're




.16          there and  before  people leave to watch the Bill Cosby




 17          Show at  8:00 o'clock,  there  is a question you need to




 18          answer at  this time  because  I have received quite a




 19          few  calls  about it.  Because apparently in the medias




 20          it was reported that you found new contamination  at a




 21          deeper aquifer, and  I wasn't aware of this because I




 22          am of  the  understanding that levels have always been




 23          below  action levels.  Can you clarify that now while




 24          everybody  is here?




 25               ALAN  ALTENAU:   Would you put a couple of slides




 26          back  up, please?






             SUSAN  D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1              We put an off-site extraction system in in



 2         September of 1987 — this is again about a third of a




 3         mile off-site in the 90-foot aquifer, shallow




 4         aquifer.  We put this extraction system in to stop




 5         further contamination from going from that level to a




 6         lower aquifer, namely the 120-foot aquifer.   We knew




 7         some had taken place.  But we wanted to first put this




 8         extraction system in to remove most of the




 9         contamination in this level before putting extraction




10         wells in the 120-foot aquifer so we wouldn't draw down




11         the contamination in the 90-foot aquifer.  We wanted




12         to do a substantial amount of cleanup and then install




13         extraction wells in the 120-foot aquifer, which is the




14         proposed plan.  The amount of contamination in the




15         deep aquifers — 200, 300, 400, and 500 — have never




16         exceeded the state action level during all these




17         investigations.  So due to the Remedial Action Plan




18         that we have had early on as well as continuing




19         throughout, the deep aquifers always had action levels




20         below the state action limit.




21              WALTER WONG:   So it is not a problem?




22              ALAN ALTENAU:   It is not a problem in the deep




23         aquifers and we continually monitor the deep aquifer.




24         If anything, we continually see it decline in values




25         in the deep aquifer, which one would expect because




26         the remedial action has taken place.






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1              WALTER WONG:   Okay.  Fine.




 2              SHIRLEY BUFORD:;   Thank you. Doc-tor Altenau.




 3              And with  that  I would like  to introduce  the




 4         person, the gentleman who asked  the question, Doctor




 5         Walter Wong, who is representing you from the Monterey




 6         County Health  Department, and obviously he is very




 7         concerned about this site.  And.I would just like to




 8         let you know who that was asking the question.  Thank




 9         you.




10              Next on our agenda is Chan Weisel, general




11         manager for the IT Corporation.  And he will  talk




12        . about the progress that's been made in the cleanup so




13         far.




14              CHAN WEISEL:   Thank you, Shirley.  And also,




15         welcome to our meeting this evening.




16              What I would like to do is  simply give a little




17         more information on the progress that has been made/




18         the actual cleanup or  remediation progress over the




19         last several years.




20              As Ric mentioned, we have been involved in what




21         is called interremedial measures, IRM's, which is




22         actual cleanup work done before all the investigation




23         is complete and before the final cleanup plans are




24         set.




25              Literally most of the cleanup has been




26         completed.   As mentioned earlier, soil -- contaminated






             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         soils and underground tanks have been removed, all




 2         disposed at licensed hazardous waste facilities.




 3              Doctor Altenau mentioned the various activities




 4         giving the dates and all.  What this figure will show




 5         you is — well, it will simply put it in perspective




 6         as to where things are.




 7              This is the large building, the former Firestone




 8         facility.  And you see at the south end the treatment




 9         plant which was installed in 1985 and operational in




10         early 1986.  In that same time frame was the




11         installation of 15 water extraction wells, groundwater




12         extraction wells on-site.  And they are along this




13         line.- They are piped all to the treatment plant, the




14         water is treated and then discharged to the Salinas




15         River.




16              The off-site extraction wells referred to earlier




17         are about a third of a mile away from the plant or the




18         property line.  And there are five of them and these




19'         were installed in 1987 and operational just about two




20         years ago.  The water from these wells is pumped




21         through a pipeline along the farm roads to the




22         treatment plant.




23              The groundwater plume referred to is a narrow




24         band of contamination starting essentially in the




25         middle of these on-site of this on-site well area or




26         at least that's where the highest concentrations exist






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1          and moving  in this direction, and this is in the




 2          shallow aquifer, the uppermost aquife-r about 90 feet.



 3          down.  So it's this narrow band of contamination




 4          moving in the shallow aquifer that all of our work,




 5          all of our  groundwater work has been intended to




 6          remove — remove the contaminants from.




 7              Later  you will see slides which will show the




 8          next and we believe final phase of work which will be




 9          extraction  in the 120-foot layer.  And again as Doctor




10          Altenau mentioned,  there is no significant




11          contamination in the deeper aquifers and therefore no




12          remediation plan.




13              What I would like to show you now are three




14          contamination concentration curves which I think




15         dramatically shows the progress and the




16          accomplishments of the cleanup to date.  I showed you




17          the line of 15 on-site extraction wells.  This first




18         curve is an average of the extremes of that line, the




19         uppermost wells and the lowermost wells.  And as you




20         can see,  three years ago concentration average was




21         about three parts per billion.  Most recently we're




22         down to .under one part per billion.   The action level




23         — drinking water action level is six parts per




24         billion so we're well below that.  So that is,  we




25 ,        feel,  a real accomplishment.   These concentrations by




26         the way are for DCE,  one of the chemical contaminants






             SUSAN D. KUCHER,  CERTIFIED  SHORTHAND REPORTERS

-------
                                                                     1
 1




 2



 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
and the main one that we have tracked.




     Same kind of curve here, but for the center of




the plume or where the center of the on-site




extraction wells are.  And here, instead of starting




at 30 parts per billion, we were over 400 parts per




billion and have brought that down to five.  So that's




essentially a hundred fold decrease.  You can see why




I am saying that the bulk of the cleanup has been




completed.  Again the action level is six, so we're




below the action level in the on-site area.




     Last concentration curve for the off-site




extraction wells which were started up in 1987, the




average concentration at that time was about 65 parts




per billion, currently running about 16.  So we're




still slightly above the action level, but coming down




nicely.




     I think this final slide on the accomplishments




summarizes well.  It shows the actual area of the




contaminant plume in the groundwater at different




periods of time.




     Again here is the former Firestone facility, the




line of on-site extraction wells along here and the




off-site extraction wells shown here.  This is the




plume area at six parts per billion or the action




level for each of the years 1986, '87, '88, and '89.




     And as you can see in 1986 the area was quite
             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1




 2-




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
large covering all of the area- of the on-sl-te



extraction' wells*  One-year, later after- the treatment*



plan had operated for a year, major reduction in plume




area.  The next year 1988, even a greater reduction.




In 1989 so far, this is the area.  That's about an  85




percent reduction in plume area during  that three-year




period.-  So we feel that a lot of the remediation




again has been completed and we're well on the way.




You can see here I talked about the narrow plume.   You




can see how narrow that is at this time.




     Thank you, Shirley.




     SHIRLEY BUFORD:   Thank you.




     Next on our agenda, we'll present Doctor Nick




Hazelwood, senior technical specialist  and group




manager for IT Corporation and he will  talk to you




about risk assessment at the Firestone  facility.




     NICK HAZELWOOD:   Thank you very much, Shirley.




I hope you can all hear me.  If you can't put your




hands up.




     When we talk about risk assessment there are two




things you have to keep in mind.  First of all, the




only tim-? you have a risk is when there is both a




hazard,  the presence of a hazardous material or a




hazardous situation and  someone is exposed to it.   If




you have  a hazardous material and no one is exposed to




it, there is no risk until that exposure happens.   So
             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         when we analyze risk assessment, we both analyze for



 2         hazards and for possible exposures.




 3              In identifying the hazards at this facility we




 4         looked for the types of chemicals that are present in




 5         the soil and the groundwater and looked at the effects




 6         or potential effects on human health and/or the




 7         environment.



 8              These are the chemicals that are the indicator




 9         chemicals that were found at the site, and we talked




10         about chlorinated solvents and aromatic solvents that




11         were used.  1,1 DCE, which is this one here, 1,1




12         dichloroethene, also known as vanilladene chloride as




13         a compound, is actually a degradation product of 1,1,1




14         trichloroethane, which is the principal solvent that




15         was used.  When this material gets in the soil and




16         water it is broken down frorc natural processes to this




17         compound.  This is the compound that is present in the




18         highest concentration and is what we use as our




19         indicator.  That's why all of our graphs are shewing




20         1,1 DCE.  The other compounds are there, they are




21         there in lower concentrations.  So this is the easiest




22         one to track and this is the one we're working on to




23         reduce to accepted levels.  Next slide, please.




24              When we look at exposures, we look both at the




25         media that could be delivering the substance -- air,




26         drinking water, irrigation water and soil on the one






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         hand — and the routes of exposure — inhalation,

 2r        ingestion or skin contact.
                                                                      j
 3              Out of all those possible combinations of 12 or       i

 4         so, these were the three that we isolated as being the     j
                                                                     • i
 5         possible routes or pathways that could lead to risk.       j

 6         Obviously drinking the drinking water contaminated         j
                                                                      t

 7         with the substances that were found.                       j

 8              Second, air emissions from the treatment plant,       i

 9         because there is an air stripper in there, or from         j
                                                                      i
                                                                      !
10         water used for irrigation and evaporation of these         |

11         chemicals from the irrigation water.  Analysis cf this

12         showed that the concentrations in air were well below      ;

13         the accepted levels as set by regulatory agencies for
                                                                      i
14         air emissions from both DHS and the Monterey Unified       :

15         Air Pollution Control District requirements.               ;

16              Crop uptake,  as Doctor Altenau told you, has beer.

17         studied extensively.  There is no data to show that

18         there is any uptake by these chemicals by the crops

19         grown in the crops in the field using the irrigation

20         water.  So we can basically "X" out these two.  They

21         are potential,  but not actual pathways.   So our

22         analysis and risk  assessment has focused on the

23         dr.inking water  issue.  Next slide,  please.

24              The risk criteria that are laid down for our

25         cleanup is that substances that are carcinogens that

26         could cause cancer,  that the amount in the drinking        :



             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         water must be small enough so that the lifetime

 2         additional risk from drinking that water for 70 years

 3         would be less than one in a million additional

 4         possibility of getting cancer.

 5              Similarly for non-carcinogens, we calculate

 6         something called a health index.  Now the health index

 7         takes the state action level, which as several people

 8         have mentioned for DCE is six parts per billion and

 9         says you divide the actual concentration by the number

10         that is the action level and that number must be less

11         than one.  The action level, in other words, tells you

12         what is the permissible concentration in drinking

13         water that you could ingest without harm for

14         non-carcinogens.  And the sum of all of those things

15         must be less than one.  In other words, the

16         concentration of all the non-carcinogens must be small

17         enough so that there is no long-term adverse health

18         effect from this water.  Next slide, please.

19              We looked at different possibilities for drinking

20         water.  There is only one well in this area that is

21         used for domestic purposes.  So we said •— let us take
                  i
22         some worse case situations.  We will take a

23         hypothetical well in the shallow aquifer,  similarly

24         one in the intermediate zone and one in the deep zone,

25         and take the average concentration in each one of

26         those and is there a potential health risk.


             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1              And this next slide summarizes the findings of




 2         the risk assessment.  There is.no potential health:




 3         risk in the existing well if someone were to put a




 4         well in the shallow aquifer.  And as Walter Wong will




 5         tell you, the County does not allow that kind of thing




 6         for a lot of reasons.  But if it were done there would




 7         be a slight risk, which is of course one of the




 8         reasons*why we're going and cleaning it up.  Similarly




 9         the hypothetical intermediate and deep zone wells,




10         again with the average concentrations, there is no




11         potential health risk.  Go ahead.




12              So the risk assessment conclusions, and this is




13         quoted from the risk assessment, there is no present




14         or future threat to public health.  There is no




15         present threat because our analysis shows no one is




16         exposed.  There is no future threat because there is a




17         cleanup plan which is going to be discussed by




18         subsequent speakers that will remove the last residue




19         of the hazardous material so that there will be no




20         future threat to public health.




21       .       SHIRLEY BUFORD:   Thank you. Doctor Hazel wood.




22              Our last speaker on the agenda is Le.onard Allen




23         and he will speak to you about the proposed Remedial




24         Action Plan.




25              Mr. Allen?




26              LEONARD ALLEN:   Good evening, ladies and






             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         gentlemen.



 2              My purpose this evening is to present the




 3         Department of Health Services proposed plan for you so




 4         you can see what the next stage will be so that you




 5         will have your opportunity to comment on that, get




 6         your input into the State.




 7              The first speaker this evening, Ric Notini,




 8         covered the State procedures for evaluating a site




 9         such as the Firestone site and getting to the stage of




10         having the proposed plan and actually implementing




11         that through cleanup.



12              We can have the first view graph there,  George.




13              The proposed plan that I will be covering tonight




14         comes out of that portion of the process that Ric




15         covered called the Feasibility Study.  The Feasibility




16         Study is really a very detailed engineering study that




17         considers a wide variety of alternatives aimed toward




18         cleaning up the contamination that has been found.




19         And out of that Feasibility Study we select the best




20         remediation alternative.




21              The proposed plan is based, to a large degree, on




22         the Remedial Investigation report that was prepared in



23    •     December of '88.  That report has, as Doctor  Altenau




24         has mentioned, combined all the previous studies of




25         the site, defined this plume or where the chemicals




26         occurred in the groundwater.  We have got this narrow






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         region that looks like a cigar on one of the earlier



 2         slides.  It's not spread out laterally quite a bit;



 3         it's fairly confined in there.  Once we've got that



 4         area defined, then we can look at the remediation plan



 5         to cleanup that zone of chemicals in the groundwater.



 6         Earlier also we have discussed that the soils on the



 7         site that were contaminated were removed.  So the



 8         proposed plan that we're discussing this evening is



 9      .   focused just on the cleanup of the grcundwater which



10         is left.



11              The Feasibility Study that was done for this site
            «                    •


12         followed the very formalized, detailed Department of



13         Health Services guidelines as well as the



14         Environmental Protection Agency guidelines.  The large



15         variety of remediation schemes that were considered



16         for the treatment, included a number of chemical,

  •

17         physical and biological processes.



18              We have also looked at other types of treatments



19         such as a containment,  if there is some way to contain



20         the contamination where it was, concluded that pumping



21         the groundwater out and treating it was the best



22         alternative.



23              We can see the next view graph then.  Once we



24         have gotten to the point where we have selected 3 PLLT.O



25         and treat alternative,  then we have to look at the



26         locations of the extraction wells.  What wells are we





             SUSAN D.  KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1




 2




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
going to pump from?  Both horizontally, where are we



going to locate the wells .and what depths are we going




to be pumping from?




     It has been mentioned that there are 15 existing




extraction wells on-site and there are five existing




extraction wells off-site, all of those located in a




zone shallower than 90 feet.




     In addition, during the Feasibility Study we




considered ten new well locations that would install




wells down to the zone 120 feet deep.  With those




wells, all the existing and the proposed — or the ten




new wells that w.ere evaluated, then we have the




alternatives of adjusting the pumping rates to come up




with the combined flow rate from the groundwater




that's being extracted.




     If that goes back to our treatment plant, then we




have a variety of treatment alternatives.  As we




mentioned, we considered a large number of physical,




chemical and biological treatment options for the lew




concentrations; that is concentrations in the parts




per billion range that we're dealing with here at




Firestone and the chlorinated hydrocarbons and




aromatic hydrocarbons that are present at these low




concentrations.




     The Feasibility Study and the cleaning process




leads us to the viable treatment options of being
             SUSAN D. KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 3




 4




 5




 6




 7




 8




 9




10




11




1.2




13




14




15




16




17




18




19




20




21




22




23




24




25




26
carbon absorption*, the air stripping, and the other



one being a combination of those two.  Tfiat is what's




been going on at the treatment plant for the last




several years.




     The other options that were considered were the




options for how we discharged the treated water; that




is, once the groundwater has been extracted and has




gone through the treatment plant, what do we do with




the water after it has been cleaned?  We did consider




three alternatives here.  One was continuing the




discharge into the Salinas River about a mile south of




the treatment plant.   This has gone on for the last




three years.  We considered injection of the treated




water through wells located on-site.  And we also




considered disposal of the treated water into surface




ponds just south of the plant area.  The screening




process that we went through led us to stay with the




discharge to the Salinas River.




     Looking at the combinations of the well locations




and the pumping rates with these treatment options and




the discharge options led us to define five




alternatives that were studied then in greater




detail.




     The first alternative is called a "no action




alternative."  And for the Firestone site that would




involve  stopping what is going on right now,  taking no
             SUSAN D. KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         further -treatment action.  That is — that's required

 2         by regulations and is more to establish a baseline

 3         case for comparison with the other alternatives.

 4              For alternative B, we looked at continuing the

 5         existing pumping and treating system; that is, pumping

 6         from the existing wells at a combined flow rate up to

 7         650 gallons a minute.  That's only pumping from the

 8         shallow aquifer.

 9              In fact, we have two limitations on the flow rate

10         that we can treat under the current conditions.  The

11         650-gallon-a-minute treatment of the water is limited

12         by the current capacity of the treatment plant.

13         Actually with the pumping from the contaminated wells

14         that we're doing right now and the declining

15         groundwater table in this area, we can only pump about

16         450 gallons a minute from the existing wells.

17              The third alternative that we looked at showed

18         that we would — if we put in five new wells in the

19         intermediate aquifer a little farther northwest of the

20         plant from the five off-site wells that exist now and

21         we pump those in combination with the current pujrpir.c
                  /
22         from the shallower wells, we could pump at a combined

23         rate of about 1150 gallons a minute.  This does

24         involve the five new wells to be constructed in the

25         intermediate aquifer, it would also include an
                                  4
26         expansion of the existing treatment plant.
                                                               •8

             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         '     However,  recognizing that is using almost double


 2          the pumping rate  that we have been using in the past;


 3          when you use  that much additional water we looked at


 4          the fourth alternative, which is similar to the third


 5          except that we adjust the flow rate so that the


 6          combined flow  rate from all the wells, including the


 7          five new wells, does hot exceed the 650 gallons per


 8          minute.  That, in fact, is the alternative that has


 9          been selected by DHS for the proposed plan.


10              The fifth alternative, similar to the fourth,


11          only that two additional wells would be installed in


12          the intermediate aquifer, was that we would have fewer


13          wells.  We have recognized that by looking at a lower


14          combined treatment flow of 600 gallons per minute for


15          that.


16              Okay.   These five alternatives were analyzed in


17         detail and  discussed in the feasibility study.  There


18          are nine evaluation criteria that are included in the


19          EPA guidelines and used by Department of Health


20          Services also.


21              We have broken up the evaluation criteria into


22          four that we call the key criteria and five other


23         criteria.  Now these are not listed in terms of


24         priority.  Certainly if we were including priority,


25         the overall protection of the human health and the
                         t

26         environment would be high on the list rather than down



             SUSAN D.  KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         under the other criteria.




 2              The differentiation'between the key criteria and



 3         the other are that the key criteria are the ones that




 4         help us differentiate more among the five alternatives




 5         that were studied in detail.




 6              The first criteria,  short-term effectiveness,




 7         lets us evaluate how effective the proposed




 8         alternative would be in a relatively short period of




 9         time.




10              Long-term effectiveness,  on the other hand, is




11         other than given enough time,  how effective would the




12         remediation be for each of the five alternatives?




13              The third key criteria was the one that US EPA




14         calls a reduction of toxicity, mobility and volume.




15         That's getting into the question of the permanence,




16         how permanent is the proposed  remediation?




17              The fourth key criteria is whether the proposed




18         alternative complies with all  the regulatory




19         guidelines involved.




20              The other items, just to  run through them briefly




21         here since they don't help us  differentiate greatly




22         between the alternatives,  are  the impiementability;




23         that is, is there sufficient technology?  Is there




24         equipment?  Is there manpower  to actually implement




25         the proposed remediation?




26              The sixth criteria would  be the cost






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         effectiveness of the remediation.




 2              The seventh, the overall protection of human



 3         health and the environment, would be either State




 4         acceptance and/or EPA concurrence with the plan.




 5              And finally, the community acceptance, that's one




 6         of the purposes of the meeting this evening is to




 7         present the plan to the community and get the feedback




 8         from the community on how acceptable that plan is.




 9         When we apply these nine evaluation criteria to the




10         five alternatives, we came up with the matrix that




11         shows how these work.




12              If we look in terms of the first criteria, the




13         short-term benefits, the first two — no action and




14         continuing the current operations — do not do




15         anything to remediate the chemicals in the groundwater




16         in the 120-foot level.  So they really don't achieve




17         the short-term effectiveness.  So we put "no".on




18         there.




19              If we put in the five new wells, in the case of




20         alternative C and D, pumping either 1150 gallons a




21         minute or 650 gallons a minute, we have put "yes" in




22         here.   We do achieve the short-term effectiveness.




23              If we cut back to only two new wells,  as in




24         alternative E, we again have "no" for the short-terrr,




25         benefit.   It takes us longer to achieve the cleanup




26         levels with those.






             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS •

-------
 1              So looking just in terms of the short-term

 2         benefit criteria, there are only alternative C and D

 3         that satisfy that criteria.  The shaded zone D there,

 4         of course, is the proposed plan that is being

 5         presented to you this evening.
                                                            •
 6              In terms of long-term benefits, the no action

 7         alternative would take a long time because there is no
                  *
 8         active remediation undertaken for that alternative.

 9         Given enough time — that is, the long-term benefits

10         — all the other options do eventually achieve a

11         long-term benefit.

12              Looking in terms of the reduction of toxicity,

13         mobility and volume, we achieve it with the last three

14         on the list here.  We achieve it only in the shallow

15         aquifer for alternative G and we do not achieve it in

16         the terms of the no action alternative or alternative

17         A.

18              Under the regulatory compliance evaluation

19         criteria we did not comply with the regulations in

20         case of the no action alternative,  we do in the case

21         of the other four; although in the case of C there

22      .   would be some permit chang.es required to implement

23         that.

24              So looking at the comparison of these

25         alternatives we see that alternative D,  the proposed

26         plan, is the only one that satisfies each of these


             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         four key criteria as we go along here.  Again, only

 2         alternative C and D on here achieve the short-term^


 3         benefits.

 4              So if we look at the differences now between C


 5         and D on here, we see that actually — even though we


 6         pump almost twice as much, in the case of C we're


 7         pumping 1150 gallons a minute compared to 650 gallons
         «
 8         a minute.


 9              The time for the cleanup is really not that much


10         different.  We're controlled more by the cleanup in

11         the 120-foot level than we are by the cleanup in the


12         90-foot level.  And the time,for the cleanup in the


13         120-foot level is essentially the same for alternative


14         C and D.  So we have the same time, the cost obviously


15         is higher with the alternative C because it would


16         involve expansion of the treatment plants, some


17         additional capital costs,  also time involved to


18         achieve the new permits that would be required.


19              One of the other major differences between


20         alternative C and D is that alternative C, which was


21         not selected, would take twice the amount of pumping.


22         So if there is an impact on the agricultural use of


23         the water,  it would be greater with C,  which again


24         leads us to alternative D as the selection.

25              D was selected as the final proposed cleanup plan


26         because it achieves the rapid cost-effective cleanup



             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         and requires less groundwater to be pumped than

 2         alternative C, which is the only other alternative

 3         that achieves the short-term benefits criteria.  We

 4         have a map here that shows the proposed five new

 5         wells.

 6              As I mentioned earlier, we actually considered a

 7         total of ten different locations in the off-site area

 8         for wells in the intermediate aquifer.  These are the

 9         five that we have selected and are included in the

10         proposed plan — three of them are located along

11         Alisal Slough and two of them are located on existing

12         farm roads.  We have done this to minimize any impact

13         on the agricultural activities out in that area.

14              Those five pipelines — the five new proposed

15         wells would be connected by a pipeline that would run

16         along Alisal Slough and along Scarp Road and tie into

17         the existing pipeline back about a third of a mile

18         away from the existing treatment plant;

19              To summarize the proposed plan, we would plan to

20         continue pumping from the existing shallow aquifer

21         wells, although the pumping rates from the various
                 i
22         wells would be adjusted depending on how the

23         monitoring data came in.  In addition, the five new

24         wells would be Installed in the intermediate aquifer.

25         The plan right now would be to have those wells

26         installed this fall.  We would pump at a combined flow


             SUSAN D. KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         r'ate up to 650 gallons a minute: from all the wells,




 2         both the shallow and-the intermediate aquifer wells.



 3              What we're accomplishing by this is that we will




 4         — we lose the contamination in the intermediate




 5         aquifer and continue to reduce the contamination in




 6         the shallow aquifer as we have been for the last three




 7         years-or so.  We are also cutting off any migration of




 8         the chemicals from the 120-foot aquifer into the




 9         deeper aquifers.  The treatment plant would continue




10         operating as it has been for the last several years;




11         that is, we would still be using the carbon absorption




12         and air stripping units on the site.  The discharge




13         would continue to go into the Salinas River as it has




14         been going.




15              By putting in the five new wells in the




16         intermediate aquifer,  our computer simulations project




17         that we will significantly reduce the remaining




18         cleanup time.  We're projecting that the cleanup time




19        .will be about a year to a year and a half from the




20         time that the wells and the 120-foot aquifer are




21         installed.   We have run over a hundred  computer




22         simulations in various combinations of  well locations,




23         pumping rates,  projected the cleanup times.




24              Some of the alternatives,  basically the five that




25         we have discussed in detail here,  are shown on the




26         plots across the wall,  if you would care to take a






             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND  REPORTERS

-------
 1




 2




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25




26
look at those during the break here prior to the




question and answer period.



     In addition,  we do have several other maps, if




you would like to take a look at those, those will be




spread out on the table up in the front during the




break period here.




     Shirley?




     SHIRLEY BUFORD:   Thank you, Mr. Allen.




     Okay.  I think that's a lot of information to




digest.  We would like to take a few minutes to break




so you can look at the other information .and be ready




for the question and answer period.  So we'll take ten




minutes and get into the question and answers.




     (Break taken from 8:22 to 8:33 p.m.)




     SHIRLEY BUFORD:   Thank you very much.  We'd like




to get started on the second part of the program,- the




question and answer session.




     We have got a number of agency representatives




here, other than those who were making presentations




tonight.  And I have already introduced Walter Wong.




Doctor Wong is sitting in the front.  He represents




the County Health Department — Monterey County Health




Department.  Also we have got Bob Baldridge who




represents the Water Quality Control Board - Central




Coast.  That is Mr. Baldridge.  And Jeff Dhont from




the Environmental  Protection Agency.  Jeff is up at
             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         the table.  And you have met the other presenters, so



 2         we'd like to get started.



 3              I would like to ask you to stand if you have a




 4         question and give your name, identify yourself.  And




 5         if you want to ask a question of a specific person,




 6.        please indicate that, otherwise we will get the answer




 7         for you.



 8              So I would like to open the process now.  Are




 9         there any questions?




10              ED FISHKIN:   I have a question.  There seems to




11         be a very well thought out —




12              SHIRLEY BUFORD:   Okay.  Give us your name, sir.




13         Please state your name.




14              ED FISHKIN:   Ed Fishkin.




15              It seems to be a very well thought out mediation




16         plan.   Assuming that the computer projections are




17         correct, in a year and a half from now all of the




18         contamination levels are below  the action level.  How




19         much longer would you continue  to pump and how much




20         longer would you continue to sample to make sure that




21         the water is indeed clean?




22              SHIRLEY BUFORD:   Thank you.




23              Mr. Allen, would you like  to answer that?




24              LEONARD ALLEN:   At the point where the




25         concentrations in the groundwater have reached the




26         cleanup levels, we would stop the pumping at that






             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1         stage.  The monitoring beyond that to see that there




 2         is no unusual buildup in the concentrations past that,




 3         we're anticipating now would take place for at least




 4         an additional two years.



 5              ED FISHKIN:   Thank you.




 6              SHIRLEY BUFORD:   Thank you.




 7              Okay.  The gentleman in the red.  Would you like




 8         to stand and tell us who you are?




 9              JIM LAND:   My name is Jim Land from Carmel




10         Valley.  I was wondering, it seems to be apparent that




11         the flow rate is something of a concern because of




12         somewhat of a depletion of the aquifers.  I was




13         wondering why the water isn't injected back into the




14         aquifer rather than dumped into the Salinas River.




15              And I have a second question too.




16-              SHIRLEY BUFORD:   Okay.  Mr. Allen, will answer




17         your first question.




18              LEONARD ALLEN:   That's a very good question.  In




19         effect, we are recharging the water with the discharge




20         to the Salinas River.  The river bed is porous enough




21         that the water that we're discharging does permeate




22         back into the shallow aquifer system.  In fact, the




23         flow monitoring system that the Federal Government




24         monitors downstream from us shows a lower flow rate




25         than we're actually pumping into the river at the




26         discharge.






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1               So we are doing  it,, we 're/ achiev ing; the  injection



 2          into  the shallow aquifer system without  the problems



 3          that  inherent in injecting it  through wells on-site.



 4          With  wells on-site you have problems with siltation,



 5          you are not able to maintain the pumping into those

                                                                      i
                                                                      i

 6          injection wells.                                           I

                                                                      i

 7               SHIRLEY BUFORD:   And you had a second part to        j



 8          your  question, sir?



 9               JIM LAND:   Yeah.  With all the available



10          technologies of water cleanup possible, why was carbon



11          absorption the chosen method here?



12               LEONARD ALLEN:   The carbon absorption and the



13          air stripping do turn out to be the most effective.



14         You are limited with a lot of the other technologies



15         because of the very low concentrations that we have in



16          the waters to start with.



17               We're down in the parts per billion range.  A lot



18          of the technologies would not be effective in there.



19          I'm not sure what other alternatives you are




20         considering here,  but there are other limitations with




21          the other ones if you are looking at soire biological



22      •'•   treatments you have problems treating the chlorinateds



23         at this low level.   In fact with the biological




24         treatments you have to have enough of the nutrients to



25,         keep the bugs alive,  and  we just don't have those high



26         concentrations here.






             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
 1              We did look at probably 30 or 40 different




 2         alternatives.  But for the chlorinated hydrocarbons




 3         and the aromatic carbons and activated carbon and the




 4         air stripping are the most efficient way to go.




 5              JIM LAND:   Thank you.




 6              JOHN GOODRICH:   Back to the original question.




 7         Any idea of what the re-absorption is of the water you




 8         pump out?  You're saying it gets re-absorbed back into




 9         the aquifer; any idea what percentage?




10              LEONARD ALLEN:   Well, it depends on how far




11         downstream it goes.  Eventually all of it is.  The




12         Salinas River is recharging the shallow aquifer in




13         this area, so it's getting back in there.  Quite a




14         high percentage of it is getting back in.




15              SHIRLEY BUFORD:   Can I get your name, sir?




16              JOHN GOODRICH:  John Goodrich.




17              SHIRLEY BUFORD:   Pardon me?




18              JOHN GOODRICH:  John Goodrich.




19              SHIRLEY BUFORD:   Goodrich.  Thank you.




20              Anymore questions?




21              JIM ABELOE:   Yes.  My name is Jim Abeloe.  I am




22         interested in the 120-foot aquifer and the extent of




23         contamination in the aquifer and the amount of the




24         degree of contamination.  The upper aquifer plume has




25         been well-identified both in concentration and extent,




26         and I would like to have that same information for the






             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
 1         120-foot aquifer.



 2              SHIRLEY BUFORD:   For the 120-foot aquifer you




 3         would like to know the contamination plan?




 4              JIM ABELOE:   Yeah.  Whether you contemplate




 5         putting the plan in or something like that.




 6              SHIRLEY BUFORD:   Okay.  Mr. Allen?




 7              LEONARD ALLEN:   Yes.  There is a map in the"




 8         feasibility study, which we-have a copy of here if you




 9         would like to take a look at it.  It shows the plume




10         in the intermediate aquifer.  That is similar to the




11         shallow aquifer in that it's confined laterally.




12         These are old alluvial sand and., gravel channels that




13         are filled in that the chemicals are going down




14         basically.  It's approximately the sarce width as the




15         plume that we have in the shallow aquifer.  The




16         concentrations of DCE, as I recall,  are about 15 tc 20




17         on an average in that area —




18              NICK HAZELWOOD:   Maximum.




19              LEONARD ALLEN:  — maximum values for those.  The




20         plume starts out just west of where  the off-site




21         extraction wells are now and extends out to where the




22         120-foot aquifer emerges with the 200-foot aquifer.




23         It was about 250 feet, as I recall,  something like




24         that out.




25              SHIRLEY BUFORD:   Thank you.  Does that answer




26         your question,  sir?






             SUSAN D.  KUCHER,  CERTIFIED SHORTHAND REPORTERS

-------
  1




  2




  3




  4




  5




  6




  7




  8




  9




10




11




12




13




14




15




16




17




IS




19




20




21




22




23




24




25




•26
     JIM ABELOE:   Yes, sir.



     SHIRLEY BUFORD:   Thank you.




     Are there any any additional questions?




     As Mr. Allen just stated, he's got a copy of the




Feasibility Study and other reports here tonight, but




they are also located at the information repository at



the John Steinbeck Library, including the other




community relations materials that have been




generated, nine fact sheets and other information that




was generated on the Firestone facility.  You are




welcome to review that material there.




     And again, please call us.  Any of the presenters




that you heard tonight from the Department of Health




Services, Firestone, IT, Doctor Wong, the Water




Quality Control Board/ we're all here to help you and




to give information to you about the site.




     I would like to thank you for coning out tonight




and sitting through the presentations.  And please




feel free to come and talk to any of the people here.




If you have no more questions, we will adjourn the



meeting.  Thank you.




     (Hearing concluded at 8:42 p.m.)
             SUSAN D. KUCHER, CERTIFIED SHORTHAND REPORTERS

-------
TABLES

-------
TABLES

-------
                                                                        TABLE 2-1

                                       POTENTIAL FUJERAI  APPLICABLE OR RELEVANT AN) APPROPRIATE NEqUIREKXTS (ARMS)
                RtgUIHLKNTS
TYPt1
SWWRV
ADMINISTERING
    AGEfO
Resource Conservation  and Recovery Act
(RCRA) as aieuled by Ibiardous and Solid
Uaste AimJitnls (I6W/U
(42 USCA 7401-7642)
(40 CfK 260-2UI)

   Ground Water Protect ion
   (40 CM 264.90) and monitoring
   (40 CFR 264.97)
Safe Drinking Hater Act  (STNA)
[42 USC 300(f)]
   Haxinun Contaminant Levels  (HCLs)
   400* 141.11-141.16

   underground Injection Control Relations
   (40 CFR Parts 144, 145. 146. aivl 147)
          ROM-related regulations are generally action specific.                   EPA office of
          However, RCRA provides Haxiiiun Concentration Limits (RCRA M3Ls)            solid waste.
          as part of ground-water protection  standards (40 CFR 264.94).
          ROM His are given for fewer chemicals than the SDUA. although
          the SIM* Mils are the basis for RCRA HCLs when regulated.

          Hazardous constituents entering ground water oust not exceed              EPA office of
          concentration limits in the aquifer underlying the waste management        solid waste.
          area.  The ground-water nun it or ing  program mist provide a reliable
          indication of ground-water quality  be lew the waste management  area.

          Establishes drinking water standards for all sources                      OHS
          of public drinking water.  California Department of Health Services
          (W6)  is the primary agency for airiinistration of the STJWA in  the state.
          See state section. Table 2.

          Applicable HCLs are based on Haxinun Contaminant Level Goals (Mate).      DHS in California
          best available technology, best treatment techniques, and cost.

          Potentially applicable for alternatives utilizing a ground-               016 in California.
          water  injection option.
FIR:0067-Rr
                                                                                                                                         DATE: 8/22/89
                                                                                                                                         PIMM

-------
                                                                      TABLE 2-1
                                      POTENTIAL FEDERAL APPLICAOI OR RELEVANT AM) APPROPRIATE REqUlRDCNTS (ARABS)
                                                                      (Contirued)
               HtqUIRMNTS
TYPE
SUHWY
AEN1N1STERING
    AfiENCY
Occupational  Sdfety and Health Act
(19 OK 1910)
Executive Order  11988 related to
floodplain management 40 CFR 264 an*
Executive Order  11990 related to
Protection of wetlands. 40 CfR Part 6.
         A
          Establishes general safety procedures in the work  place.  Installed       CAL-OSIIA
          c^iipntKTt (lakes  it necessary for workers to be engaged in routine
          activities at  the site.  Markers may be exposed to dilute organic
          coritdninants fran air stripper off gas.  OS!(A Markers exposure
          levels and general construction safety standards should be considered.
          OSm Pennissable Exposure Level (PEL) requiranents under 19 CFR 1910.120
          are applicable to worker exposures during response actions at CERCLA sites,
          except in states that enforce equivalent or more stringent requirements.
          California has reinstated a program for nongovemient employee work place
          exposures with equivalent or more stringent requirements.  See discussion
          in state section.
          The current WOES permitted discharge structure is located in the flood-
          plain and wetlands of the Salinas River.  This discharge structure and
          potential future  new structures should avoid adverse effects, minimize
          potential harm, and preserve resource values in floodplain and wetlands.
                                               RUTXB in California
  Type  of ARAK:   C-contamtnanl specific.  I-location specific,  A-action specific.
GOV.006/-HT
                                                                                                                                     DATE: 8/22/t
                                                                                                                                     FINAI  REVISION

-------
                                                                        TABLE 2-1
                                       POTENTIAL FEDERAL APPLICABLE OR RELEVANT wo APPHCPRIATE REquuocHrs (ARMS)
                                                                       (Continued)
                REOUIkEKNTS
TYPE
ADMINISTERING
    ACENCV
Clean Water Act (CWA)  33 USCA lftl-1376
40 CFR 1GO-H9
   National Pollutant Discharge Elimination
   Systan (HUES) (40 CFR 122-125)
   Water Quality Standards fCWA US (a)(l)]
Clean Air Act (CAA)  (42 USCA 7401-7642)          A
(40 OH 50-49)
   National Emission Standard for                A
   lla/aruous Air Pollutants (40 CfR 50-69)
           Ihe Clean Water Act retires permitting of effluent discharges            RlflCB  in California
           under  the WOES permit program and seeks  to protect the existing and
           attainable uses of waters of the U.S.

           Ml)fS  permits contain applicable standards, monitoring requirenents,      RUEjCB  in California
           and standard and special conditions for water discharges.  Both co-site
           and off-site discharges from CERCLA sites to surface waters are required
           to meet the substantive CUA requirements, including discharge limitations,
           monitoring requirements, and best managanent practices.  Oily off-site
           CEKCLA discharge oust be permitted.  The  facility possesses an NPDES
           pennit for discharge to the Salinas River.

           Effluent limitations are required to achieve all appropriate State water  Administered by EPA
           quality standards.  EPA "Policy for the Development of Mater Quality-     Office of Water.
           Based  Pennit Limitations for Toxic Pollutants"  (49 FR 9016, March 9g 1984)
           states that toxic pollutants contained in direct discharges may be con-
           trolled beyond Best Control Technology/Best Available Technology (BCT/BAT)
           equivalents to meet applicable State water quality standards.

           The Clean Air Act (CAA) is implemented through  State programs             CARS and M3UAPCD
           of the California Air Resources Board (CARB).   CARB gives enforxanent     See state section.
           authority to local air quality managanent districts.  The Monterey Bay
           Unified Air Pollution Control District (MBUAPCO) enforces air quality for
           facilities in this area.  Activities resulting  in emission require a'
           pennit to operate with corresponding effluent requiranents as for the
           existing air stripper.

           national Emission Standards for Hazardous Air Pollutants (NESJWP)         CARB and rCUAPCD
           are process and industry specific and were praajlgated to protect
           people and the enviroment.  NESIIAP standards are currently limited
           to very few chemicals (40 CFR 61).  Benzene is  discussed under NESlMPs;
           luwver. no anission standards are described (40 CFR 61.110-112).
    -fin*. ;_p i
                                                                                                                                        DATE: 8/22/89
                                                                                                                                        FINAL, REVISION

-------
                                                                      lAfflf 2-2
                                       POTENTIAL STATE APPLICABLE 0) RELEVANT AH) APPROPRIATE REqUIREMXIS (ARARS)
                                                                      (Continual)
               KKjUIRLRNTS
TYPl
SWWfl
ABMNISTERING
    AGEtCY
California  Environnental Quality Act
Public Resources Code. Division 13
Occupational li'dllh and Safety Act,
Labor Code, Sectim 6JUO el seq.~
Chapter 6.6 Safe Drinking U.
-------
                                                                        TABLE 2-*
                                        POTENTIAL STATE APPLICABLE OR RELEVANT AM) APPROPRIATE Snj/IROtKTS (/WARS)
                                                                       (Contirued)
               REgUIRQCNTS
TYll
SIMWY
ADMINISTERING
    AGENCY
   Regulation XII  - New Source Review
   Ptup Test  Permit
State Drifting Wrter Act (SDWA).
Health and Safety Code. Division 7.
Part 1, Chapter 7, Section 4010 et seq.
California Code of Reflations,
Title 22,  Division 4, Chapter 15,
Dunestic Udter Quality aid Hmitoriny
Porter-Coloyne teter Quality Act
Water CuJe,  Division 7, Section 1XII)
et seq., CCH litle 23, Chapter 3,
SutKhdpter 9 ani Subchapter 15. K60-2836
           This  reflation sets forth preconstruction review requirements for new           M3UAPCD
           or modified stationary sources, to ensure that  the operation of such
           stationary sources does not interfere with progress  in attafrment of the
           national ambient air quality standards, without unnecessarily restricting
           the  future economic growth .within the district.  NAAQS guidelines and total
           anissions limits are on a case-by-case basis.

           Required for withdrawal and discharge of volatile contaminated ground water      M3UAPCD
                atmospheric release of contaminants is possible.
           SDWA establishes drinking water standards for sources of public
           drinking water.  Federal MCLs are incorporated intd  State regula-
           tions regulations, and in sane cases the State may proiulgate more
           stringent State MCLs.  The DIB has promulgated His  for 12 organics
           and 2 inorganics in drinking water.  Several  of the  proposed KLs
           are the sane as or more stringent than the current nonprcnulgatad
           DtIS ALs.  Under SUM, as amended by "AB 1803," sanpling and analysis
           of drinking water sources are required.  upon review of the results
           of initial sampling, a monitoring program is  established by OHS.
           In the event of violation of DIG action levels for drinking water,
           public notification may be required.

           Similar to the Federal CUA, the Act and its associated  regulations
           apply to protection of waters of the State.   An MTJES permit is
           required for off-site discharges, whereas, only substantive
           requirements are required for on-site discharges.  Porter-Cologne
           delegates standard setting authority to the RUQCBs.  RUQCB will not
           dictate specific treatment alternatives but will require that the
           alternative meet mininun action levels and perform at a level near
           the Rest Available Technology (BAT) for the chosen alternative.
           The WJXb is responsible for establishing WOtS substantive and
           administrative requirsnents for permitting at levels sufficiently
           protective of the waters of the State.  RtJJCB emission  standards
           are set on a case-by-case basis and apply to  treated wastewater.
           storm water runoff, etc.  Waste dischShje reports  and requirements
           are also specified.
                                                 DHS is responsi-
                                                 ble for adninistering
                                                 the State SUM, which
                                                 includes the  "Afl  1803"
                                                 monitoring program.
                                                 RWQCB
OOV:006/-RF
                                                                                                                                       DATE: 8/22/89
                                                                                                                                                 RFVISION

-------
                                                                        f/ttLE 2-2
                                       POTENTIAL STATE APPLICABLE OR RELEVANT MO APPROPRIATE RETJJ1RLHENTS (MURS)
                                                                       (Continued)
               KEqulKERHTS
TYPE
SuWWY
ADMINISTERING
    AGENCY
     Rule 40?  - tiiisance (including odors)
     Rule 410  - Fugitive Dust
   Regulation  IX  - Standards of Performance      A
   for ffcw Stationary Sources
   Regulation X - National Emission  Standards   A. C
   for Hazardous Air Pollutants
   Rule 1167  - Air Stripping Operations          A
   (Reyulalion XI - Source-Specific Standards)
           Prohibits the discharge of any material  (including odorous conpcunds)      M3UAPCD
           that may cause injury, detriment, nuisance, or annoyance to the
           public, businesses, or property, or endanger human health, canfort,
           repose, or safety.  This rule would be used for enforcement in odor
           prublsn situations.
                                                            i
           Limits cm-site activities so that the concentrations of fugitive          tOlAPCD
           dust at the property line shall not be visible and the downwind
           particular concentration shall not be more than  100 micrograns per
           cubic meter, averaged over 5 hours, above the upwind particulate
           concentration.  The rule also requires taking every reasonable
           precaution to minimize fugitive dust. Hay be applicable for
           construction activities.

           Implements the provisions of Part 60, Chapter I;  Title 40 of the .         tOMPCD
           Code of Federal Regulations (CFR) under  the supervision of fCUAPCD
           Executive Officer.

           Implements the provisions of Part 61, Chapter I,  Title 40, of the         WtWCD
           Cale of Federal Regulations (CFR) under  the supervision of WUAPCO
           Executive Officer, if contaminants identified at  site are listed.

           The rule is designed to reduce volatile  organic compound (VOC)            MBUAPCD
           emissions from new and existing air stripping equipment used
           for the treatment of contaminated water.  The rule requires that al I
           exhaust gases from air stripping equipment shall  be vented through a
           control device or process that will reduce the total VOC emissions to a
           level that is at least 90 percent of the previous emissions on a mass
           basis.  Ibwever, the rule exaipts fran this specific requirement air
           stripping equipment that have total VOC  emissions of 1 pound per day.
           or less.  Recordkeeping of water and air stream analysis of VOC
           concentration is required for all facilities.  These requirements are
           reflectal in the conditions of the existing air pennit.
GOV:006/-KT
                                                                                                                                       DATE: 8/22/89
                                                                                                                                       PIMAI  RFVIRION

-------
                                                                        TASf 2-2
                                        POTENTIAL STATE APRICABLE OR RELEVANT AM) APPROPRIATE RflJUIROOfTS (ARABS)
                                                                       (Continued)
                KtgUIHOtNTS
TYPl
                        SLWWY
  ADMINISTERING
      AGENCY
   Closure an] Postclosure of Interim
   Status and Permitted Facilities
   (Title 22; 67210-67220)
   Closure and Postclosure of  Interim
   Status and Permitted Facilities (continued)
   (Title 22, 67210-6/220)
   Hazardous Uaste Mauler Registration
   (Title 22. 66420-66465) and Reijiire-
   ments for Transporters of lla/ardous
   Uaste (Title 22. 66530-66664)

Hulford-Carre)I Air Resources  Act.
Health and Safety Code.  Division 26,
Section 30000 et seq.   17 CAT.  Part III.
Chapter I. Section 60000 et seq.
A. C
Monterey Bay unified Air Pollution
Control District (HJttlAPCI))  Rules
arid Reflations

   Rtijuldtion IV - Prutiiditioriary R
           The facility shall be closed in a manner that minimizes the need           OB
           for further maintenance (6721 l[a]) and controls, minimizes, or
           eliminates postclosure escape of hazardous waste, leachate.
           contdiiinatod rainfall, or waste decomposition products to the
           gru«) or surface waters or the aunosphere (6721 l[b]).

           Contanination at the Firestone Site was identified during closure          HIS
           activities of a permitted facility.   Thus. CMS is the lead agency
           for this  FS/RAP, although the site and adjacent contaminated ground
           water are currently being raradiated  and the facility has been  for-
           DBlly closed and the contamination source removal.  Postclosure monitor-
           ing requirements nust still be int.

           Ih/dntous waste must be transported by a hauler registered                06
           by the state.
The State counterpart to the Federal CAA. Mulford-Carrel I
establishes the California Air Resources Board  (CARB) and
local Air Quality Management Districts (A^ds).  The CARB and
AfJOs are given responsibility for protection of air quality
in the state.   They oust also develop control measures for
reducing missions  of the CARB-identified toxic air contaminants.
Permitting authority Is delegated in this act.  The Firestone
facility and associated ranediation activities are subject to
permit, ru|uirenents issued under this authority.  Al location of
allowable emissions are on an air basin specific basis.

The following  sections and regulations fran KIUAPCOmay apply             HDUAPCD
to a water-treaunent system, should air stripping be usod as a
techno) njv.-
CARB and (MBUAPCO)
COV:006/-RI
                                                                                                                                       DATE: 8/22/89
                                                                                                                                       FINAL REVISION

-------
                                                                       TAfa.  _-2
                                       POTENTIAL STATE ATTI ICAW1 OR ROfWWT MO AffWFHIATE RHJUIKOfNTS (ARAftS)
               REQUIRfKNTS
rm:'
SIWWY
ADMINISTERING
    AGENCY
Hazardous Waste Control Act (Health and
Safety Code.  Section 25100-25396)  as
administered  by the Department of  Health
Services (DIIS) under tie California Code of
Relations.  Title 22, Chapter 30; Hininun
Standards for Huui/nent. of Hazardous and
Extrunely Hd^dnius wastes.
          IUCA has may elenents that are intenled to control  hazardous
          wastes firm their point of generation through accuiulatfon,
          transportation, treatment, storage,  and ultimate disposal.
          It is inplanented largely through regulations under CCR.
          Title 22. Division 4. Chapter 30. Section 66300 of  Chapter 30
          provides no ROW-type exsiption for  CERCLA sites.
   Criteria for Identifying Hazardous Uastes
   (Title 22. 66693-66/46)
   Reqjirunents  for Generators of Hazardous
   Uaste
   (Title 22. 66470-66515)
          Tests for identifying hazardous characteristics are described  In           OHS
          Title 22, Article 11. Sections 66693-66746.  If a waste is
          either listed or tested and found hazardous, then mnaganent nust
          caiply with the hazardous waste neqjiranents under Title 22.  tttile
          these standards are not treatment or disposal limits, the resulting
          classification as hazardous waste results  in efforts to meet the
          standard, thereby nuking hazardous designation methods a form of
          treatment standard.

          An oner or operator who initiates a shipment of hazardous waste           D6
          fran a Transport, Storage, or Disposal  (TSD) facility shall coiply
          with the generator standards established under Article 6 (66470-66515).
          Title 22 of CAT (66470[d]).  These standards include keeping of
          manifests (66481). submission of manifest  to DIE within 30 days of
          shipirot (66484[fj). preparation of a biennial report (66493[a]).
          and a nvwiuun 90-day accuiulation tine  (66508[a]).
GOV:0067-RT
                                                                                                                                    DATE:  B/22/8&
                                                                                                                                    FINAL  RFVISION

-------
                                                                       WBlf ?-3
                                     POTENTIAL ana nasw. CRITERIA. ADVISORIES. MO GUIDANCE ro HF OMSIDEVD (TBC)
               REQUIRE* KTS
TYPE1
SIMWY
AB«INISTERING
    AGEICY
Federal  Criteria. Advisories,  and Procedures

   Health Effects Assessments  (IIEAs) and         C
   Proposed l£As ("Health Effects Assessnent
   for [Specific Chanical]").  ECAO. USEPA. 1985

   Reference  Duse (RflJs). ("Verified Reference   C
   Uuses of USEPA." ECAO^IN-475, January 1986)

   Carcinogen Potency Factors  (CPFs). (Table 11. C
   "Ibalth Assessnent Uacuitnt for letrachloro-
   ethylene (Perchloroethylene)." USff'A. QEA/
              , July 198b)
   Pesticide and food additive tolerances and    C
   action levels.  Nute:  Germane portions of
   tolerances art! action levels nay be pertinent
   anJ therefore are to be considered in certain
   situations

   Federal  sole source aquifer requiranents      A
   (52 FR 6873. Mirch 5. 1987)

   EPA's GrourJ Uiter Protection Strate
-------
               KtqUIRtKKTS
                                                                        TABLE 2-3
                                      POTENTIAL ana HUM  OUTEKIA. ADVISORIES AND OJIMNCE ID BE OMSUOED (ib
                                                                       (Continued)
lYPt1
                                                                          ADMINISTERING
                                                                              AGENCY
   Guidance on Rtiiulial Actions for Contamin-     A
   died GruinJ Wdter at Suierfund sites (Draft.
   Octcter 191)6)  establishes criteria for the
   use of  background concent rat ions did ACLs

   Superfund Pub)ic Health Evaluation fenual     C

   EPA Health Advisories for Drinking Uater      C
   Sift* Maxiiiim Ctfitaninant Level Coals (MCLG)   C
USEPA ROW Guidance Ducuients

   Interim Final  Alternate Concentration
   Limits.  Guidance Part I:  ACL Policy and
   Information Ra^iraitnts  (vluly 1967)
   Technical Resujrce OocirMits (TRDs).
   RCRA Grounl-Uater Hnitorimj Technical
   Enforcaient Guidance
USEPA Office of Witer (kiiddnce uocifiuits

   Water -Relatal f/iviruniuital Fate of 129
   Priority Pollutants  (19/9)
Provides guidance on key decisions in the development, evaluation.
diil selection  of ground-Mater ranedial  actions.
Outlines health-based risk assessment.

These advisories are nonpronul gated concentrations of drinking
water contaninanls  for organic and inorganic chsnicals.  The
advisories are levels at tiiich adverse health effects would not
be anticipated to occur over specific exposure durations.  For non-
carcino
-------
                                      POTENTIAL Onifl FEUJML CRITERIA. AJV1SOUES AN) GUUWCE TO BE OMSIOERFD (IK)
                                                                       (Continued)
                RLguiROCNTS
TYPE
5LMWW
ADMINISTERING
    AGENCY
   Quality Criteria for Uiter 1986
   Clean Uater Act  Udter Quality Criteria for
   Protection of llnian Health and Fresh Uiter
   Aguatic Life  bl FR 43666
             Support Daamant for Uater Quality
   Based Toxics Control
          Uater quality Criteria (UQC) established under Section 304 of             RUQGB
          CWA (51 FR 43665). are based on effects of human health aid aquatic
          life that do not reflect  technological or economic considerations.
          QA UQCs are applicable to water discharges to surface or ground water.
          These substantive criteria would apply to uastewater discharges to  .
          the Salinas River.

          Elaborates on water-quality-based toxics control.                        RUQCB
   Developing Requirements  for Direct and        A
   Indirect Discharges of C£RCIA Uastewater
   (1987)

   WOES Guidance Docunants -                    A

   IfUES Best Kmaijonent Practices Guidance      A
   Kanual (Jurt 1'JHI)

   Ground WiterAJIC Guidance Oocunuits -         A
   Corrective Action Keqjirenunts
   Ground Uiter Protection Strategy (August 19U4)

   Clean Uater Act Guidance Ibcunents            A

£PA IRIS Cancer KisJt InfuniHtion                 C
Guidance for Corxlu.ting Won-didl Investigations  A
aid feasibility Stulies lt«Vf CIWIA (Draft)
          Explains development of  vestewater discharges.



          Presents guidance relative to ffUCS procedures.

          Presents guidance on WOES GM>.


          Presents yiidance relative to ground-water protection.



          Presents guidance relative to CWA.

          EPA  IKIS cancer risk infomul ion represents the most  current.
          peer-reviewed ctanicdl concentrations in water producing risk
          levels.  The 10   risk  level was used for the risk  assessment
          in this FS.  The IRIS values are more current than  the Clean
          Water (Uiun Health Criteria for Drinking Uater.

          Presents CfKCIA procedures.
                                                RWQC8




                                                RUQCB



                                                RU)CB

                                                EPA
                                                EPA
                                                                                                                                           DATE: 8/22/89
                                                                                                                                            FINAI  RFVIBION

-------
                                                                   TABli 2-3
                                   POTENTIAL ODIH FEDERAL CRI TIN I A. ADVISORIES MO OJ1DANCE ID BE OMSIOEDED (TBC)
                                                                  (Continued)
               RtQUIRtMN'5
FYPl
SLHWV
ADMINISTERING
    AGENCY
Guidance on Preparing Siperfurri Decision
OocuiHit:  Ihe Prxoosed I'I an and Recorx) of
Decision (Draft)

StaniJard C|>erating Safrty Unities
          Presents ifiidance on preparing ROD.
          Presents safety procedures for operations.
                                             EPA
                                             Cal-OSIM
  Type of  IBC:   C-conlaciinant snecific,  l.-lix.aliun specific, A-action specific.
                                                                                                                                   DATE: 8/22
                                                                                                                                   FINAL  REVISION

-------
                                           onnt STATE AM) LOCAL CRITERIA, AOVISCRIES. AW GUIDANCE  ID BE CONSIDERED (TBC)
                REQUlklKMTS
Department of Health Services Decision
Tree. Revised Oecaibcr 1906

Water Quality Control  Plans at the State
Water Resources Control  Board and the
Regional UaU-r Quality Control Board
  WE1
SIMWRY
ADMINISTERING
    AGEfCY
  A. C       Provides guidance on development of site-specific  cleanup levels and       DJIS
            evaluation of ranodial action alternatives.

   L        Water Quality and Basin Plans.  Use attainability  studies and the          State Water
            current water quality of  surface waters are used in determining            Resources Control
            allowable discharges to surface water bodies under WOES penults.          Board; RvflCB
RtfJCfl Water Quality Control Plan
Effluent Limitations
016 Drinking Udter Action Levels (ALs)
L, A. C     The Clean Water Act and Porter-Cologne Water Quality Act  require
            regional water quality control boards to develop water quality
            control plans.  Effluent  limitations are specified in River
            Basin Water Quality Control Plan.  These limitations are  not
            praiulgated. but are considered when peniritting wastewater
            discharges to surface water bodies.

   C        046 action levels are specified for some of the organic contaminants
            that have been identified in ground water.  These levels  in sane
            cases are available for contaminants that do not have HCLs.  046
            action levels are reconnended drinking water levels and are not
            praiulgated, but could be used as policy or guidance. Water purveyors
            in California will generally take action if the 016 notifies than of
            contaminants exceeding ALs.  ALs are not proiulgated, but are used as
            016 policy.  These are drinking water standards developed by the
            UK and in practice nust  be met to comply with 016 requirements.
                                                RHP
                                                OHS.  ALs are also
                                                used by other
                                                agencies as the
                                                basis for effluent
                                                and disposal
                                                limitations.
GOV:006/-RI
                                                                                                                                      DATE: 8/22/89
                                                                                                                                      FINAL  REVISION

-------
               HEQUIRLKNTS
                                                                     T/ttf 2-4
                                          onin STATC /N> IITAI CHITDUA. ADVISORIES. MO GUHWCE ID BE OKIKHD (TBC)
                                                                     (Continued)
iri'E1
DI6 Applial Auiun Levels  (AALs)
Central  Valley tU£B Designated Level
Methudoloijy  for Waste Classification
and Cleans  Level Detenni nation
(October 1*6)
                                                                        ABMNISIIRING
                                                                          •  Af£NCV
       action levels are exposure limits that are pollutant-
    n-ceptor-specific and used as a starting point for establish-
ing cleantf) levels.  If the AALs are exceeded, then actions should
be takun to clean tf> contaminants dowi to these levels.  In sore
cast-,, cleanup may be allowed by the 016 to be greater than the
Mis.   However, justification oust be given for doing so, and the
0(6 oust approve the modified cleanup levels.  Mater treatment values
should neet AAL standards for water discharges an! human receptors
(i.e., drinking water).  Also, AALs are available for the air to human
pathway.  Applied action levels are not proiulgated, but could be used
as policy or guidance.

This guidance docunent  is in the tentative stage of development for use
in the classification and subsequent disposal method of both hazardous
and non-hazardous wastes.  The method is still site specific but
generic; conservative classification levels can be approximated.  The
Designated Levels are to be considered criteria.
                                                                                Applied by 06
                                                                                on a site-specific
                                                                                basis.
                                                                                RUQCB
 'lype of  IliU:   C-cuntaminant specific, L-location  specific, A-action specific.
1,0V: 0067-Kl
                                                                                                                                   DATE: 8/22/8'
                                                                                                                                   FINAL  REVISION

-------
                                                                                                                                                                                                               Date:  8/22/89
                                                                                                                                                                                                               Final Revision
                                                                                                                     I ABIE 2-4
                                                                                                               ORGANIC CONSTITUENTS
                                                                                                 UAIEI QUALII1 GOALS -  HUNAN HEALTH AND UEUARE
(1)
     UKuAKIl
 1.1-Ulcnloroethylene
 I,)-Otchloroethane
 |,2rDUhlorpethane
~ (tn/ene
 (thylbeniene
 tetracnloroetiiylene
 Toluene
 1,1,1-lrlcnloroeihaiM)
 IrUhloroethylene
 lylene(t)



NONCANCER
HEALTH
ADVISORIES OR
SIAIL ANU LPA UHUMW. VATLN SIANlUKlft
MAllMUN CONTAMINANT LEVELS (MClS)
PRIORI »CL~~MCL r,fiAir?p» 'syATt
o^TT ua/i jggilT
? ; 6

4 Zero O.b
S Zero 1
' / 1 \ i -i\
JUO1 J )OUl ' BHO
S13' Zero'1' S
/ 1 1 Ml
2.0UQ1 ' 2,cno' '
2»0 200 2UO
S Zero S
lo.noo'3' • lo.opo'3' i./so
UHS
UMIW1NG BAHH
ACTION LEVELS
TOIiqU TASTE 4 ODOR
iig/T uj/T

S


• ?9
6
• 100



IMS
APPLIED ...
ACTION LJVELS'"
HAW
Mj/T



O.I
680

100
200

620
SUGGESTED
NO-ADVtRS{.R(SPDNSE
LEVELS
CPU
JJJJZI
JO(4>

MO'4'
'0
680* 4)
19.400*4'
12,000'4I
200<4>
n
440<4>
(SNARLt)
•fcAS

100





340
1,800






ONE IN ONE MILLION INCREMENTAL
CANCER RISK LEVEL
EPA •- NATIONAL
AMBIENT HATER
quALITV CRITERIA
tali


0.94
0.66

0.8


?.»

f P» HIALTH OR
HATER OUALITV
ADVISORIES^
HJ/t ,


0.9S
0.68

0.6?


4.S


' NATIONAL
ACAOEN* OF
SCIENCES (HAS)
UgH


O.M '


1.6

,,(S)
l.S«S>

EPA -- NATIONAL AMBIENT
HATER QUALITY CRITERIA
BASED ON NONCANCER
PUBLIC HEALTH
al£T




1,41)0

14.300
18.400


            Iro.n CalltornU Heyfondl Water guallty Conlrol Uujrd. Ctnlral Valley Region, !•)«/. Append 11 III, *lhe Designated Levtl Methodology (or Wattt CUtf Ulcitlon ind Cleanup Level Oeternlnat Ion.'
    prepared by Jon. B. Marshack. revised September 14, I9U/. eicept for AAL'l (see Note 6).
 '?IUHS, TSCD. Uecemlier 2. I9B7. human receptors; AAl »iter Is SIB Ac (Ion Level.                                     •
 '''proposed, updated as of Kd> ?2. 1989 Federal Register, pi). 22064.                                                '
 (4)Drjft/lentatlve.                                                     .                              '....'
          on llolted evidence.
 F|«:OU6;-I4-2re>

-------
                                                                Date:   8/22/89
                                                                Final  Revision
                                  TABLE 3-1                                         >
                    FLOHRATES FOR EXTRAaiON ALTERNATIVES
                             INTERMEDIATE  AQUIFER
                          FORMER FIRESTONE FACILITY
                            EXTRACTION  ALTERNATIVE

               WELL
                                                                                    si
                                                                                    OLL
IT-IE1
IT-IE2
IT-IE3
IT-IE4
IT-IE5
IT-IE6
IT-IE?
IT-IE8
I.T-IE9
IT-IE10

150
150
150
100
_
_
150
_..
_

_
_
150
_
_
_
150
150
150

150
-
150
_
_
_
=
150
150

—
.
100
-
150
150
-
150
150
150
150
.
150
_
_
_
150
_
_
150
150
150
150
100
_
_
-
_
_
              NOTE:   Flowrates  given  in  gpm.
                     Flowrates  shown  were  used  in  the  tradeoff  studies
                     between  various  extraction alternatives.   Actual
                     flowrates  to  be  used  in  remediation  will be
                     established by the  Site  Manager based  on the
                     monitoring data  for the  recommended  remedial
                     alternative,  Alternative D, the combined flowrates
                     will  not exceed  650 gpm, the  current treatment
                     plant capacity.
FIR:0067-R8T31

-------
          nis
                                               IWIf <-i
IIAMINMION If AI IIUMIIVU WOOUS HHlMUAliir AiHICAUU Ot NUJUM AM) AflUHUAIl IO}J!I««MTS (AKMts)

                                                       AI IIHNAIIVf C - KIHIIIAR       Al ItKtMlltf 0  - HfMUIAd
                                                       SIM I (W AMI INII m III AH              SIMIUU  AMI
                                                       Atjmrxs. iiioi HIM RAif.        iHniMoiArr  Aguiruts.
                                                       tt AW IXTAKSIIIN. fin  Mtt       UlSllfT. nJM, FlVt KU
                                                                     IN  UILS        INIUMDIAIl tCH. tfUS
                                   AUIKNAIIVC  A -  H> tiltCH
                                          HIM 1)1 All
                                     JJ WJJW
                                                     (M »
                                                                                                                                                     AIIIIINAIIU I  - KIMIIIAIl
                                                                                                                                                            SIIAIIOUAM)
                                                                                                                                                       INIUMIHAII AIJUIUHS.
                                                                                                                                                      LIISIIMi HJH\.  Ml ffW
                                                                                                                                                                   ifo uus
-siieuf i£
 Driniing I
 -U3TH Safe Urinting Utter A}
 .Huiuun Canldflidiiit Ltvels
 -C06 Stdte Driitiny kfeter Ait
  Drintiny Udtir Vlicn levels
 -IWPA Artjitrt Ujti.f Quality
 -U-iCA IL>dlUi IT  killer
Hesiduil  risk  of Uunicdls in sail dfter soil raiuvdl is duaued
                                                                        for dll dltenutives.
Allowing only iu(ur<)l
Ui uL«t varioiA clMniLjl-s)iinest in the shallow art!
                                  01 interest in tit snalliM     120-fuut  intenmlidte tune ai^jifers.  lui-ther ccntdninatiu> <4 the deqi ttftifen  is  nut cx|iei:t»l
                                  aifiiftr will te net.  Die      An to the clean^i of Uie gruund water in Die cuntributiny inlmnertiate anil shallow /ones.
                                  puteiitial dr contdfliiidtiun
                                  o( I)ULI> difjlfiTS due to lai:k
                                  of nnnJul itn in the inter-
                                  inuliale /ine is high.
 -IHFM
                    AU, fbtiaul  H)l 4>plicdt)le
  Discharge (luniiutiui System
  tnt Udter (Judlity  Stdnlanis
  -OWjCB. fOrter-ColLyi- Uiler
  Quality Act. MltS *d Uiter
  Qiallty Stvirknls
      A. Cle<« Air Ait
  -OWJ. HjllooKirn-ll Air
  Rt-uuraes Ait
         ). Kules «
                                 Nut
                                  Uili/atitn of the oisling
                                  tredUiut plant will  not
                                  result in any violations of
                                  the existing permit rajuire-
                                  auits with regard to dis-
                                  ihjn>- i|ud(itity or
                                   lit existini uenoit  to ojier-
                                   ate oruvides limitation on
                                   the ra(e of treatment  tw tie
                                   air itriuper. total  hydiu-
                                   carUn umssiuns and anis-
                                   siai  I imitating for spe-
                                   cific tmtjnindnls.  (iiera-
                                   t ion of the systai will be
                                   ptrfoniul in cuipl iano? with
                                   the existing (Mniit  limita-
                                   tiue> din)
                                                                            hiyh flax rates
                                                                 over 1,1100 yun envisionol
                                                                 unler this alternative uvy
                                                                 reiuine inalif icatiui of the
                                                                 I, (ID gin flow limitations
                                                                 conlainuJ in  the exist inu
                                                                 M11ES uEfwit.  Mater Quality
                                                                                                               an? not expect ««
                                                                                                   to be enceakd, althouji
                                                                                                   stdrt-ii> anl (Jctuyyiny of a
                                                                                                   new air stripper nay
                                                                                                   SUM id) water handling
                                                                                                               tu assui«
                                                                                                           treaUient.
                                                                 Installation of a nan air
                                                                 stripper wuild mfjire nulli-
                                                                 fication at  the existing flow
                                                                 rate I imitations,  the
                                                                 NIMfCDny  limit overall
                                                                 onissions Iran both strippers
                                                                 to the existing spurific con-
                                                                 tdiiinant lyiantlties.  Koni-
                                                                 toriny both  units separately
                                                                 may be reiplru), as well as
                                                                 detailud start 71(1 monitoring
                                                                 for the new units,  lotal
                                                                 auissions iny  exceed 7b per-
                                                                 ctnt of Uie permitted aicunt,
                                                                                                                     utili/alion of the existing
                                                                                                                     treatment plant will  nut
                                                                                                                     result  in any violations  of
                                                                                                                     the existing penait rei^iire-
                                                                                                                     umts with reganl to discharge
                                                                                                                     tfjantity or
                                                                                                                     The existing |«raiit hi oiierate
                                                                                                                     provides  Imitation on the rate
                                                                                                                     of  treaUiut by the air strip-
                                                                                                                     per, total hyaWarUn unis-
                                                                                                                     sions, an! uniss-ioji limitations
                                                                                                                     for specilic omtaniinants.
                                                                                                                     (Deration of the systoii will be
                                                                                                                     pertained in uii|iliance with
                                                                                                                     Uc existini pemiit liinit-
                                                                                                                     atiais and ai|iiruiuits.
                                                                                                                    Uili/ation of the existing
                                                                                                                    t realms* plant will not result
                                                                                                                    in any violations of the
                                                                                                                    existing penult reifjinnunts
                                                                                                                    with reuard to discharge
                                                                                                                    qjantity or quality.
                                                                                                                    Ihe existing penmt to out-rate
                                                                                                                    provides  limitation ui tli- rate
                                                                                                                    of  tredbient by the air strip-
                                                                                                                    per, total hydrocarUjn aiiis-
                                                                                                                    sions anJ emission limitations
                                                                                                                    for specific contaminants.
                                                                                                                    Operation of the systoii will lie
                                                                                                                    perloniul in onpliance with
                                                                                                                    the existiiij permit limit-
                                                                                                                    ations ami
HA:f IK  10/9-14
                                                                                                                                                             DATE: 8/22/89
                                                                                                                                                             FINAL  REVISION

-------
                                                                                            IJttli  48
                                              IXAXIHAIUM U * HMftllVtS 1/IJWfi POnNIMlV AMICM1 (It HUUAMI HO MWHUAIl ffqjINDflflS (AKAHs)
                                                                                                         *'                                        ,;
      AMI IflIS fAt.ll«S
                                    AllIKftAIIVJ A - N) ALllUN
                                                                         Al IIKUAIM H
                                                                            HI Mill All
                                                                                      INY
 -IIS1PA. Clean Air  Avt
 -OKB. Act  Hjlluru-Ortll Air
  ttesuurtes
 -HllAKi). Hula  dnd H»*>ildUin
 (cuilirual)
                                AinW4AI|W  t  - MHDIAIL
                                siMitu ANI  INIIIMIIIAII
                                Al Jill I US. IIIUI IIIURAIF.
                                HANI  IXPANSIin. 11VI MU
                                  IHI1 Will All  KH t4IIS
                              (••tent idlly nifjiriinj mm?
                                       nuuluriuj.   |uh-
                                     ^hiiviny
                              ttv ai^jiiiiiuits  (uild uccir
                              if dir district tas  in(le«-
                              ible r
  /HIMNAIIM: »- MMIHAII
        SllAlllU ANI
   INIItMUIAR AlJIIIIHS,
  UISIIM. PI ANI. iltf  NfW
  INIIKMDIAII AM 14US
                                               Al IIW4AIIH I  - WK1IIAII
                                                      SIMIIU AM)
                                                 INIIKHIHAII AIIUMHS.
                                                UISIIM; I'lANI. IUIMU
                                                INIIKHIHAII  /Ot tlllS
        ). Sldftlanfc of IVrfunu-
  £ (Of few jtdtlLIl.1l>
  SuuA.es. Itw Suurui
                                  Nut
Ml  d(»)li(d(ilc
 -HlWU/. Knp l»l
 -U-JIA «d Cdl-OSlA Uaief dl
     re«>ild-
        fur
imldlldtlun
(U dpplic<4>li.'
                                                                                                                                                                  Ht
 -OSIIA an) UI-09IA
           levels
                                                                 Salisfact ion uf
                                                                 tuns wuuld U>
                                                                 dL'velupiut a
                                                                 of d new dir
                                                                 Incluks pntuislrticl ion rv-
                                                                 view nxfjiruiHils prior lo
                                                                 issiune of d permit lo coii-
                                                                 Slrutl.  fotenlidlly hl«Ji
                                                                 expwsv  dnl l*j tine ivfdlivo
                                                                 lo the prujcil scojie tor cuo-
                                                                 plldllU!.

HJ( d(4>li(.dl>le                      Ml d|tilitdl>le                 A puip lest permit Muld be rtifiiruj for lesluy of DM wells wttie disclunj.* of vuldtlle <
                                                                 irktltxl uruj«I wdler with putentidl for dUusuheric rtleuse would u'cur. suth ds. in ML'11 (kw.-lop-
                                                                 uut. tonih.mfe prU)luu> dn? nut dnlicipdted.  ds tie levels of (onlduiiruliun div IOM  dilvrut U> for all conslruclion did duiolilion drlivilies  u»k.itdkui ftr lit site IkMllli do) Safety Plan.


                                   lull ciiifillance with these stalues will  be pni<  i il per the existiny site health and safety plan.  Uurter safety is assesswl
                                   in lit risk  dSSeisoMl by lew levels of  worku 11 Ji.

                                                                 HMWthelical wurker risk will
                                                                 fae saivwhat hnjnr  in this
                                                                 scenario Ate lo  iiKrivisixl
                                                                 auissiuns, bit shuilil lie
                                                                 wilhin Die 111 levels.
HA.f
                                                                                                                                                                 DATE. 8/2^   i9
                                                                                                                                                                 FINAL  RE VISION

-------
                                                                                                                                  MU 4-2
                                                                                                            SUMRT OF (TTAIUD ANiniS OF OKDIAIUM A.IOMUUCS
    AUVrSIS fAdORS
Short-let* effectiveness
           pnutectiun is achieved
                                      JM nHHAtm A - M) /trim
All! WWII VI n -
HINDI AH
VKU ajMIHH ffll»
AlirRMAIIVl C - RnCIIIAH
SIM 1 (If AM) INIDMDIAIE
A(|llf[RS. IIIGHFIMAII.
HAM liPAKSKM. FIVE MM
IHTIRHDIAIL «H KUS
AinRNftllVT D • KHDIAK
9W.Uk AM)
IMIDHUIArt AQJIfFJIS.
[IISIIIC FLAM. (IV MU
IMITHKDIArt flH tfUS
AHOVMIIVC E - RINVIAIE
SIMKM AM)
IMIDMUIAIE AtKUFIfiS.
CXISIIIC Fl/NI. IU) NTU
IfflllHOIAR KH UJUS
        dnJ inlcnrMlule /une
*»jiler% ojiettaJ to rudi clean-
ill levels by Uinter
                                    ProlecticTi conslsU of 1*1 of
                                    sensitive rwn>lori and checking by
                                    nnitoring to detemiw plwe oove-
                                    niU anJ dispersion.  Hininptline
                                    (T'-jjiral for nnitorinq is b years.
          iilif is expected to be
          hy Uinter 1991/9?.
                                   frotection for  intenrediate lone
                                   consists of  lack of sensitive
                                   reiffitors and assurance by •cnitor-
                                   inj to detemine pluv mfMOfit and
                                   dispersion.  Hininm tin1 for roni-
                                   torinj Is S >rMrs.
Ranaliation of the shallow and
intenodiale /one au^iifers is
expo, led to he con|)leted by Uinter
1991/9?.

RamJiatlon of the shallow and
inteimediate /one au>iifers is
expected to protect the deep
         fro* future dnjratlat Ion.
Ranfiatlon of the shallow and
intemediate /one aquifers is
expected to be onpleted by fall
1990.

Same as Alternative C.
Damnation of the shallow and
intenadiate /one aquifers is
expected to be cmiileted by Uinter
1993/94.

Sane as Alternative C.
(VoUction of cumuiity
ranwlial  acduis.
                                    Neliance on natural mechanlsvB and
                                    aeration throu/i spray irrigation
                                    will retain? a lurej ti«e lo rair-
                                    diate the shallow and intemixlUte
                                    tin- Haulers aid «qy result in
                                               of the ifeep ai|iifer.
                                   Hpliance on natural nechanisms and
                                   aeratiin thru«|i spray Irri9atian
                                   will reifiire a  Ion) ttaie lo me-
                                   diate thi- intemediate /one apjjifer
                                   anl nuy result  in dujradat ion of the
Ramlial  actions infer Ihrse alter-
ndtives iwy nut If lonsiikTed
cuiplete  until nnilorinu, assum
prutrclion.   II urutettian (km not
utuf. tlic (rtmlMl for antdniiiid-
tiin uf the <»M> »>ii(rr. usa) f
-------
                                                                                                          SHORT or OCTAILED AM.KIS IF KMDIATMN * monies
                                                                                                                                (Continued)
AlltRNAIItt B -
HtHUIAE
AfttVSIS (AdORS AlllHNAIIW A - M) KHUN SIWHU AQJIHR (MY
Protection of xrters difing M>t «n>li«*le to site worters - Site wrier exposures are considered
ruirdul actions direct rundiation Mill Le negligible considering the arission
teminaleit. rates, ccnfainatlon of factors
rujjirul for exposure, and duration
oi expected mediation activities.
Caplidnce with standard operating
prut«kire and tfJIA regulations will
prolnt'Mixrliers during reiedial
attivities.
AinUNAUVl C - SSMDIArt
SIN (WAN) INHIHOIAn
AfjuiRRs. mniiirwwn,
HAM IKPAHSIfM. DM NW
IMnNHUIAII AM UlLS
Same as Alternative B.
AlITfiNMNE D-RMDIAIt
SHN.LQI AN)
INHIMUIAn AQJirOtS.
(iisiiic rum. ritf m
INHRKDIAIE AM tf US
Sane as Alternative B.
ALITIMMIVl C - RMUIAR
SIMtlOJ AM)
(xisiiic njwi. rut mi
INIDMVIAH AM If US
Sane as Alternative
B.
                                    Ayricullural wxter exposiinp will
                                    potntully he hufvr lr<*ise ol the
                                                     lrhn«/i (he RiU
                                               untlutnl this rib' MBS
                                    mininul.
Duration of enposure is  less Uun
           A.
Duration of etposure is only
sli
-------
                                                                                                              SMfWT OF DETAILED AMUTSIS ff NDfDlATKM AITEHMTIMS
                                                                                                                                    (Continued)
ANAUSIS FACIGRS
ALtTRNMIVE 6 -
W Mill All
AlRRNAH* A - H) ACIIOH SIWKW MfllfCR (HV
ftTERNMIVE C - REMHIATE
SIWUW AN) INIUMDIAIE
AOJIfWS. HIGHRnWHl.
PLANT EXPANSION. FIVE MM
imrmDiArt KH. OILS
ALTERNATIVE 0 - 1OWIAIE
9N.UU AN)
IHTEHWTOATE AOWERS.
EUSTIIG PLANT. Fltf NEW
INTERMUIATE WC tfLLS
AHEDNMIVE E - (CWJ)IArt
9W.UUMO
iNTtncDiATE AOIIFERS.
EXISIIIC PLANT. IW) WW
INTETMDIATE SH. ICLLS
t-lenn Effectiveness  anil
                                      relative n-sidwl  risk,         Hilerale residual risk,  lack of     Low residudl risk - ranedlation of
                                      «/i risk dsses9 aifiifers.
                                                                                                                                                Same as Alternative C.
                                                                                                                                                                                    Srtnc as Alternative C.
     anl reliability of           Icnj-lenmnjnilorini) will be         long-tern mm i lor ing will be         Honttorlng of ground-water wells     Sane as Alternative C.
                                 nti|ii(nl U> monitor  natural attenua- reifiired to man it or  that nigratlon   will contlne throughout remediation
                                 lion of tunt animation  and nuinte-    ol water (run the intermediate /one  and for two years following achieve-
                                      uf ground wattr  i|iialily.       will nt affect deeper ground water, ncnt of the cleanup levels.  Treat-
                                                                                                        ment plant monitoring will continue
                                                                                                        during operation.
                                                                                                                                                                                    Same as Alternative C.
                                    Hi treaUmt  pi art m'raticns for
                                    Altrmal ive A.
                                                                    I he existing treatment system has     Installation of a new air stripper   Hie existing treatment  system has    Same as Alternative 0.
                                                                    bun operate) reliably since Spring  will retire a period of startup and beat operated reliably  since Spring
                                                                    lift ami is experiert  to operate      additional controls.                 1986 and is expected to operate
                                                                    reliably during the ronedial action.                                     reliably during the  remedial action.
                                                                    No pndilons are expected  in meeting                                      No problems are expected  in neeting
                                                                                      s.                                                     permit
F IR.006/M9I4
                                                                                                                                                                        DATE:  8/22/89

-------
                                                                                                                                     Table 4-2

                                                                                                              SMMY OF DETAILED AM.VSIS IF (BOUTHM JDONOIKS
                                                                                                                                    (Continued)
ANALYSIS (ACTORS
Al TERNATIVT. B -
WMDIAIt
MflflNAIIVE A - MD ACTION SIWIOU AOIIFEU OLV
ALTERNATIVE c - RTHDIATE
SIM LOf AN) INTTRrtUIATE
AQUIFERS. MIGHflonATE.
PLANT EXPANSION. FIVE NTH
INTEKrCDIAIE «K ItLLS
ALTERNATIVE 0 - REKDIATE
SWLWAIO
INTERKDIATE XQJIFERS.
tUSTItC PLANT. FIVE NtW
IWERrClHATE 20C UtLLS
ALTERNATIVE E - HEHPIATt
SHAIKH AM)
INTBKDJATE AQUIFERS.
ExisTiic PLANT, no tcu
INTDHDIATE W WHS
Reduction of To«icity. KJbility. or   loxicity  is reduced by
VOllTE
Treatnirt process and raicdy
-Annum of hazardous material
 destroyed
-Reduction in toxicily, mtiility,
 and volune
-Irreversibility of treatment
-type and Quantity of  treabnent
 residual
attenualion.  (Ability is not
affected,   volune of affected area
is increased allhaK/) at a reduced
concentration.
Air stripping and/or carbon adsorp-   Air stripping and carbon adsorption     Same as Alternative C.
                                                                                                                                                                                          Sane  as Alternative C.
lion raluoe  Uuicity. nobility,  and
volune of chanicals in affected
uruul water.
                                    reduce Uwicity, (utility, and
                                    volun? of  chanicals  in affected
                                    gronJ water.
                                    Source, vadose zone,  and grxuid-
                                    water ai|iifers will not be actively
                                    treated.  Aeration and natural
                                    mechanisms will be relied  on to
                                    reduce toxicity.  The contaminants
                                    will bo dispersed  irreversibly
                                    thn««/«)Ul the grant-water plure.
Contaminants In  the shallow tone
ground water are actively reme-
diated.  Source, vadose tone, and
intermediate and deep aquifer con-
tamination will  not be actively
treated.  Tor raicdlatlon of the
deep ami intenrodiate aquifers.
aeration thnugti irrigation and
natural ncchdnisms will be relied on
In reduce tcu icily.  The contami-
nants will be disiwrsed irreversibly
thra«>uit the yrunil water pluie.
                                                                        Contaninants  In the shallow and
                                                                        Intermediate  zone ground water
                                                                        agplfers are  addressed.  Atjiifer
                                                                        remediation of the shallow and
                                                                        Intermediate  zone ninimi/e the
                                                                        potential for further contamination
                                                                        of the deep aojjlfers.  Source.
                                                                        vadose zone,  and deep atjiifer
                                                                        contdmlnatlon will not be treated
                                                                        other than by the agricultural well
                                                                        pipping.

                                                                        Contaminants  removed by the air
                                                                        stripper will be emitted to the
                                                                        atmosphere.   Contaminants removed by
                                                                        the cartxn unit will be sent to a
                                                                        recycler for  regeneration.  Small
                                                                        amounts of chanicals may he dis-
                                                                                lo the Salinas Rivi-r.
                                                                                                                                                   Sane as Alternative C.
                                                                                                                 Same as Alternative C.
                                                                                                                                                    Sane as Mltematlvs C.
                                                                                                                 Sane as Alternative C.
f ID 006/K'H4
                                                                                                                                                                         DATE: 8/22/1
                                                                                                                                                                         FINAL  REVISIOM

-------
                                                                                                                             TABU 4-?

                                                                                                        SfHW OF OFTMUD /NtfSIS JX obtain easanents on private property
and connect than to the existing
systan.
ALTERNATIVE 0 - REKDIATE
SHALLOW AN)
INTETKDIATE AfJJIFERS.
EXISTirC PLANT. FIVE NBI
INTENrCDIATE 70C ICLLS
Sane as Alternative C.
ALTEHMTIVE E - RDCDIATE
SHULOI AND
INTEFHOIATE /QJIFERS.
EXISTING PLANT. TV) WU
INTERHDIATE XH UUS
Same as Alternative C.
-Reliability of lechnolmy
Del iance on natural mechanisms and
irrigation far ranErjiaticn is slow.
The existing treatment systan has    Sane as Alternative B.
h«n derated since Spring 1986 with
a hl^h degree of reliability.
Technical problem with the existing
systan are not expected.
Sane e Alternative B.
                                                                                                                                         Same as Alternative B.
-Fase of undertaking additional
 raieclial ajrtion,  if necessary.
Prior to dismantling the treatjnent
syslejn, maintaining the treabmit
plant in standby node for 2 years
will allnj
-------
                                                                                                         SMWIV OF P£TAJL£D MN.YS1S OF KKDIATUM JUBBWIWES
                                                                                                                              (Continual)
    WWYSIS FACTORS
                                     AUKNAIIVI A- tOACMCN
                                                                              WKDIATE
                                                                         StIAtJ OW AqJIFEH OtY
                                      M.HMMIIVE C - REMEDIATE
                                      SIW.UW MO INTrRHHIATE
                                      AQJIFERS. mai ficvRAii.
                                     PLANT  EXPANSION. FIVE MM
                                      IKIENKUIATE MC tCLLS
                                                                                                                                              ALTERNATIVE 0 - REKDIATE
                                                                                                                                                    9W.UM AW
                                                                                                                                               IKIWCDIATl AQUIFOS.
                                                                                                                                              EXISIIIC PIANT. FIVE NEU
                                                                                                                                              IHTDHDIArE ffl»€ tfIIS
                                                                                                                                                                                ALIERNMI* E - IDCDIAIE
                                      IKIWCDIAIE JKJJIFFJG.
                                      Eiisritc PUWI.  no m
                                      IHIWCDIArt «M If US
-Honitwing considerations
                                   tustinq monitoring network of
                                   grunt-water wplls will be usorl.
Existing rmnitoring network of
grand-water wells and treatment
plant vnpling points will be used.
                                                                                                       In addition to existing systan,
                                                                                                       monitoring will be <*Hnl at new
                                                                                                       wells and at new air stripper.
.In addition to existing system,
nnitoring will be added at new
wells.
Sane as Alternative 0.
Aitninistrdtine feasibility

-Coordination with other agencies    Ho pe> .rits rei|iired,
                                                                    tto no* permits  rwjjired.
                                   ffttS anl miWCO permit mortlftc*-    rto new permits  retired.
                                   tiorB would be retired for instal-
                                   lation of a new air stripper.
                                                                                                                                                                             (to new permits required.
Availability of Services and         It) ntv services, materials or per-   S*n- as Alternative A.
Materials                           smiel  are nxuirul.
                                                                                                       The availability of resources to
                                                                                                       develop nat wells into the inter-
                                                                                                       mediate rare is only expected to be
                                                                                                       limited by the availability of land.
                                                                                                       easanonls, ami right of ways, etc..
                                                                                                       not by services or materials.
                                                                                                                                          Same as Alternative C.
                                                                                                        Sane as Alternative C.
Cost, rtet ('resent  Uprth. $1 ,«B

-1 percent discount  rale

-S percent discount  rate

-10 percent discount  rate
                                                                    3.1*
                                   I,M/

                                   I, I Id
                                   5.905

                                   5.??2

                                   5,«fl
                                                                                                                                          1.829

                                                                                                                                          1.7V

                                                                                                                                          1,7(8
                                   3.444

                                   3,111

                                   3.0U
 10:006/1(914
                                                                                                                                                                DATE: 8/22/89-
                                                                                                                                                                FINAL REVISION

-------
                                                                                                                                  UBU4-2
                                                                                                            SLHNK OF CHARD) MUSIS v xmiuauN
                                                                                                                                 (Cant liued)
AW.rSIS 'ACTORS
AimtNAIIVE B -
WMWAIT.
Ai UHNATIVl A - ND AUIGN SlWIfU AQIIFER plidnce with action-specific
                                   tfct
Conplies with action-specific ARM.
Ihrun/i existing WJtS permit md
Hi WO) permit.
Overall Protecticn of tUivan
and
-Rpun hedlth and emirorrrtntal
 protectitn throu/i risk elimina-
 tion ratictim or toilful
                                   Risk assessment shows current ri-i
                                   is at acceptable level,  this
                                   alternative has UIKJ ikjralion ot
Sane as Alternative A, except that
duration of ejqwsure in shallow
        is  less.
                                                                                                          Treatment plant «x)i float Ions to
                                                                                                          acconmiate hio]i flow rate will
                                                                                                          retire NKS permit rodif (catlore
                                                                                                          of allowable flew rates and
                                                                                                          permit to operate.
                                   Conplles with action-specific ARARs
                                   through existing NVES pemrit and
                                          i permit.
                                                                                                                                                                                Sane as Alternative 0.
Risk assess/rait shows current rlst   Provides the best nix of protection  SoneWut lower potential for risk
is at acceptable level.  This alter- of all  envlronnjital madia  and runan reduction than Alternatives C and
                                   health by concentrating on  areas of  due to lower contaminant capture ,
                                   hig)i contamination first.           capabilities of a  be well Inter-
                                                                      nal late tone extraction system
                                                                      (conjured to five  well systems).
                                                                                                          native has short duration of
                                                                                                          exposure.
                                                                                                          Honed i at I on of contaminated grand
                                                                                                          water In the shallow ard  Interme-
                                                                                                          diate zone aifjlfers will  protect the
                                                                                                          deq> aojjlfers fron further contami-
                                                                                                          nation  and reduce luiun health and
                                                                                                          envirunmmtar risk.
                                                                                                                                             Sane as Alternative C.
                                                                                                                                                                                     as Alternative C.
I IH
                                                                                                                                                                   DATE: 8/22/89
                                                                                                                                                                   FINAL  REVISION

-------
May 25, 1989
Alternative
                    Table  4-3
       COST COMPARISON OF ASSEMBLED  ALTERNATIVES
                     FIRESTONE
                    (11,000's)
                  Increiental             Net Present Worth
Short-ten        Long-ten*              at Discount Rate
Capital Cost      DIN  Cost       3 Percent   S Percent   10 Percent
z
o
A:
8:
C:
D:
E:
Pulping rate : 0 gpi
No Action. 10 years
Puip Increientally 500 gpi to 0
12.83 years
Puip Incrementally 1150 gpa to 0
Expand plant * five nells. 4.67
Puip Incrementally 650 gpi to 0
Add five wells, 3.42 years
Puip Increnentally 500 gpi to 0
Add two Nells. 6.67 years
Varies
Varies
510 Varies
275 . Varies
200 Varies
1,525
3,186
5,905
1,829
3,444
1,387
2,990
5,722
1,792
3,311
1,116
2,588
5,308
1,708
3,017

-------
         25-Hay-89                            Table  4-4
                                           COST SUMMARY OF ALTERNATIVE  A
                                           NO ACTION -  PUMPING RATE  :  0                      -                               tr
                                           10 Years (April  '89  to  April  '00)
                                              FIRESTONE
                                                                              Annual
                                                                             Estmted
         Cost Iteis                                                           Costs
Construction Costs
   All capital costs are 'sunk* and not a part  of  this  evaluation.

Monitoring (0 I M)
      10 Years Monitoring                                  314,000  /MO.  :      $168,000
Total Plant Operation (0 4 fl)
       2 Years Standby Only                                 $4,000  /MO.  :        $43,000
ANNUALIZEO COST 0 4 M

NET PRESENT WORTH OF ANNUALIZED 0 4  H  COST
   (Unifori Series Present  north for        10  Yrs.)
       3\             8.530 factor     .                                     $1,433,074
       5\             7.722 factor                                          $1,297,251
      10*             6.145 factor                                          $1,032,287

   (Unifori Series Present  north for         2  Yrs.)
      •n             1.913 factor                                             191,847
       5\             1.859 factor                                             $89,252
      10*             1.736 factor                                             $83,306

TOTAL  PRESENT  HORTH Of  ANNUALIIED 0  I  M COST ALTERNATIVE A
   At  3 percent                                                              $1,524,921
   At  5 percent                                                             $1,386,503
  .At  10 percent                                                             $1,115,593

-------
          25-Hay-89                                 Table   4-5                                                             ^O
                                            COST  SUMMARY OF ALTERNATIVE 8                                                  ® 55
                                      '  PUMP  INCREMENTALLY  - PUMPING RATE  : SOOgpl to 0                                    £J>
                                         12.83 Years  (April '89 to Jan. '02)   .                                            •- £
                                              FIRESTONE                                                           *•_,
                                                                               Annual                                     £i<
                                                                             Estimated                                    <-
          Cost  Iteis                                                            Costs
 April  '89  to  Jan  '92"        Puiping  rate 9 SOOgpi
     2.75 Years  Duration      End puip 4  treatient Jan  '92

   Construction  Costs
    All capital  costs are 'sunk* and not a part of this evaluation.

   Monitoring  (0 4 M)                                       118,000 /MO.

   Total Plant Operation (0 4 N)                   .         $35,200 /HO.
    Includes air stripper 4 carbon treatient            	
                                                           $53,200 /MO. :      $638,400

NET PRESENT WORTH OF ANNUALIZED 0 4 M COST
    (Unifori Series Present Worth for     2.75 Yrs.)
       3*             2.602 factor                                           $1,661,344
       5*             2.511 factor                                           SI,603,165
      10*             2.306 factor.                                          11,471,948

January '92 to  January '02  Puiping rate 0 0 gpi
      10 Years Duration

  Monitoring (0 4 H)                                       $14,000 /HO. =      1168,000

  Total Plant Operation (0 4 H)      On standby             $4,000 /HO. =       $48,000
       For  txo years

NET PRESENT WORTH OF ANNUALIZED 0  4 H COS!                            '
   (Unifori Series Present Worth for        2 Yrs.)
       3*             1.913 factor                                              $91,847
       5*             1.859 factor                                              $89,252
      10*             1.736 factor                                              $83,306

NET PRESENT WORTH OF ANNUALI2ED 0  4 H COST
   (Unifori Series Present Worth for       10 Yrs.)
       31             8.530 factor                                           $1,433,074
       5*           '   7.722 factor                                        .   $1,297,251
      10*              6.145 factor                                           $1.032,237
TOTAL PRESENT WORTH  OF  ANNUALIZED  0 4  H  COST  ALTERNATIVE  B
   At 3 percent                                                               $3.!S6,:s4
   At 5 percent                                    .                           $2.989.6s3
   At 10 percent                                                              $2,587,541

-------
          25-Hay-89
          Cost  Iteis
                     Table  4-6
        COST SUMMARY OF ALTERNATIVE C
PUMP INCREMENTALLY,  EXPAND PLAHT;  AOO FIVE HELLS -  PUMPING RATE :  1150 gpi to 0
           4.67 Years (April '89 to January '94)
                FIRESTONE
                                                 Annual
                                               Estiiated
                                                 Costs
April  '89  to  January  '92    Pimping rate « 500 gpt
     2.75 years Duration     End puap S treat 01/92

  Construction Costs
   All capital costs are 'sunk* and not a part of this evaluation.
  Monitoring (0 & M)

  Total Plant Operation (0 4 n)
NET PRESENT WORTH OF ANNUALIZEO 0 4 M COST
   (Unifon Series Present north for     2.75 Yrs.j
       J*             2.602 factor
       5*             2.511 factor
      10\             2.306 factor
                             $18,000 /HO.

                             $35,200'/MO.

                             $53,200 /HO.
                                                                             $1,755,600
                                              $4,568,696
                                              $4,408,704
                                              $4,047,856
                                                         0)0
                                                         • V)
                                                         ™>
                                                         N UJ
                                                                                                                         Ou.
Noveiber '89 to October '90          Putping rate * 650 gpi
       1 year Duration      Puip and treat 120'  Mils
  Monitoring (0 & M)

  Total Plant Operation (0 4 n)
      (included above)

      (induces above)
NET PRESENT HORTH OF ANNUALIZED 0 4 H COST
   (Unifori Series Present Morth for        1  Yrs.i
       l\             0.971 factor
       5*   .          0.952 factor
      10*             0.909 factor
JO /MO.

JO /C.O.

JO /KO.
                                                                                     JO
                                                      JO
                                                      JO-
                                                      JO

-------
                                                                                                                          ,r
          25-May-89                                 Table  4-6 (cont.)                                                     2
                                      COST SUMMARY (CONTINUED) OF ALTERNATIVE C                                         - S2
                              PUMP INCREMENTALLY, EXPAND PLANT; ADO FIVE NELLS - PUHPING RATE : 1150 gp« to 0           SJ 2
                                         4.67 Years (April '89 to January '94)                                          ^cc
                                              FIRESTONE                                .                         QJ J
                                                                               Annual                                   K-Z
                                                                             Estiiated                                  oil
          Cost Iteis                                                            Costs
January  '92 to January  '94  Pulping rate 0 gpi
       2 years Duration     Treatient plant on standby

  Monitoring (0 t N)                                       $14,000 /HO.

  Total Plant Operation (0 I II)      (on standby)           $4,000 /HO.

                                                           $18,000 /HO.   :     $432,000

NET PRESENT NORTH OF ANHUALIZEO 0 i H COST
   (Unifori Series Present North for        2 Yrs.)
       3t             1.913 factor                                             $826,619
       5*             1.859 factor             •                                $803,265
      101             1.736 factor                                             $749,752
June '89 to October '89     Expand plant,  add five nex wells and pipline
  Construction Cost         Nells and pipeline                                 $275,000
                            Plant expansion                                    $235,000
                            Total  Construction  Cost                             $510,000
TOTAL PRESENT NORTH OF ANNUALIZED 0  i  N  AND  CAPITAL  COSTS  ALTERNATIVE  C

         At  3 percent                                                         15,905,314
         At  5 percent    .                                                     $5,721,970
         At  10 percent                                                       $5,307,603

-------
         25-May-89
         Cost I teas
                       Table  4-7
          COST SUMMARY OF ALTERNATIVE  0
  PUMP INCREMENTALLY,  ADD FIVE WELLS  - PUMPINS  RATE  :  650  gpi  to 0
             3.42 Years (April '89  to  Septeiber   '92)
                  FIRESTONE
                                                  Annual
                                                 Estiaated
                                                  Costs
April  '89 to July '89
    0.2S years Duration
Puaping rate 500 gpj
Puip and treat Onsite  nells
  Monitoring (0 4 M)

  Total Plant Operation (0 t H)
NET PRESENT NORTH OF ANNUAL1ZEO 0 i M COST
   (Unifon Series Present Worth for     0.25 Irs.)
       3*             0.245 factor
       5*             0.242 factor
      10*             0.235 factor
                               $18,000 /MO.

                               $35,200 /HO.

                               $53,200 /MO.
                                                                               $159,600
                                                   839,163
                                                   $38,698
                                                   $37,579
                                                                                                                            2
                                                                                                                            C
                                                                                                                         si
July '89 to Noveaber '89    Puaping  rate  500  gpi
    0.33 years Duration     Puap  and treat  Qffsite  Nells

  Monitoring (0 I M)

  Total Plant Operation (0 4 Mj
NET PRESENT WORTH  OF  ANNUALIZED  0  i  H  COST
   (Unifon Series Present  worth for     0.33  Yrs.)
       3*             0.324 factor
       5*             0.319 factor
      M             0.310 factor
                              $18,000 /MO.

                              $35,200 /MO.

                              $53,200 /MO.  :
                                                                              $210,67:
                                                   $68,166
                                                   $67.296
                                                   $65,230

-------
          25-May-89        •                         Table  4-7  (cont.)
                                       COST SUMMARY  (CONTINUED)  OF  ALTERNATIVE  0
                               PUMP INCREMENTALLY, AOO  FIVE HELLS -  PUMPING  RATE  :  650  gpl  to  0
                                          3.42 Years (April '89  to  September   '92)
                                               FIRESTONE
                                                                               Annual
                                                                             Estimated
          Cost Iteis                                                           Costs
 Noveiber '89 to October  '90  Pushing  rate  650  gpt
        1 /ear Duration      Puip  and treat  120' wells
                             End puip &  treat  October  '90
   Monitoring (0 4  M)                                       $18,000 /MO.

   Total  Plant Operation  (0 I M)                            $35,200 /MO.

                                                           $53,200 /MO.  :     $638,400

 NET  PRESENT  WORTH  OF ANNUALUED 0 i  H COST
    (Unifori  Series Present Worth  for        1 Yrs.)               -
       3\              0.971 factor                                             $619,806
       51              0.952 factor              .         .                      $608,000
       10*              0.909 factor                                             $580,364.


 October  '90  to  October '92    Pulping rate 0 gpi
       2 years  Duration     Treatment plant on standby

  Monitoring  (0 4 H)                                       $14,000 /MO.

  Total Plant Operation (0 4 fl)      (on standby)            $4,000 /HO.

                                                           $18,000 /NO.  :    '  $432,000

NET PRESENT NORTH OF ANNUALIZED 0 4 M COST
   (Unifori Series Present North for         2  Yrs.)
       3*              1.913 factor                                             $826,619
       5\              1.859 factor                                             $803,265
      10*              1.736 factor                                             $749,752


June '89 to October '89     Install  f^ive ne» nells and pipline

  Construction Cost                                                            $275,000
TOTAL PRESENT  NORTH OF  ANNUALHEO  0  4  H  AND  CAPIIAL  COSTS  ALTERNATIVE  0

         At  3  percent                                                         $1,828,759
         At  5  percent                                                         $1,792,260
         At  10 percent                          .                         •     $1,707,925

-------
                                                                                                                            r'
          25-May-89                                 Table  4-8                                                            «2
                                           COST SUMMARY OF ALTERNATIVE E                                                 ^j-
                               PUMP  INCREMENTALLY, AOO TWO NELLS - PUMPING RATE : SQOgpt to 0                             c>4 J2
                                         6.67 Years (April '89 to Jan. '96)                                              w^
                                              FIRESTONE                                                          £•£
                                                                               Annual                                    JjZ
                                                                             Estiiated                                   oil
          Cost  Iteis                                                            Costs
 April  '89  to  July  '89        Putping rate 8 SOOgpi      Onsite Nells
     0.2S Years  Duration      Puip 4 treat on and offsite Nells

   Construction  Costs
    All  capital  costs are  'sunk* and not a part of this evaluation.

   Monitoring  (0 4  H)                                       $18,000 /MO.

   Total Plant Operation (0 4 M)    .                 •       US,200 /MO.

                                                           $53,200 /HO. :      $638,400

 NET  PRESENT' NORTH  OF ANNUAUZED 0 4 M COST
    (Unifori Series Present North for     0.25 Yrs.)
       3*             0.245 factor                                             $156,673
       51             0.242 factor                                             $154,792
      10*             0.23S factor                                             1150,317

 July '89 to Noveiber '89  Puiping rate 8 500 gpi       Offsite Hells
     0.33 Years  Duration

   Monitoring-(0 4 M)                                       J18.000 /HO.
   Total Plant Operation (0 4 ,1)                            $35,200 /MO.
                                                           $53,200 /MO.   :     $638,400

NET PRESENT NORTH OF ANNUftLHEO 0 4 H COS1
   (Unifori Series Present Worth for     0.33 Yrs.)
       l\             0.324 factor                                             $206,565
       51             0.319 factor      .                                       $203,928
      10*             0.310 factor                                             $197,667

Noveiber '89 to January '94 Puiping rale « 500 gpi     120'  depth
    4.17 Years Duration     Puip and treat

  Monitoring (0 4 N)                                       $18,000 /MO.
  Total  Plant Operation (0 4 M)                            $35,200 /MO.
                                                           $53,200. /MQ.   :      $638,400

NET PRESENT WORTH OF  ANHUALIZEO 0 4 N COST
   (Unifori Series Present  Worth for      4.17  Yrs.)
    .   3\       .      3.866 factor                                            $2,467,765
       5\             3.682 factor                                            $2,350,500
      10*   .          3.280 factor                                            $2,093,';3

-------
          25-Hiy-89                                 Table  4-8  (cant.)                                                     ^
                                       COST SUMMARY  (CONTINUED)  OF  ALTERNATIVE  E                                           ^£
                               PUMP INCREMENTALLY, AOO  TWO  HELLS -  PUMPING  RATE :  500gp«  to  0                              eg uj
                                          6.67  Years (April  '89  to  Jan.  '96)                                               «°"
                                               FIRESTONE                                                          uJ<
                                                                               Annual                                     < 5
                                                                             Estiiated                                    ou>
          Cost  Iteis                                                            Costs
 January  '94  thru  January  '96          Puiping rate 8-0 gpi^         Monitor only, plant on standby.
        2 Tears  Duration     Puip  S  treat ends 01/94

   Construction  Costs
    All capital  costs are  "sunk* and not a part of this evaluation.

   Monitoring  (0 t n)                                       114,000 /no.

   Total  Plant Operation (0 4 .1)       (on'standby)           $4,000 /NO.

                                                           $18,000 /HO. :      $216,000

NET PRESENT NORTH OF ANNUALHED 0 t 1 COST
   (Unifon Series Present north for        2 rrs.)
       l\             1.913 factor                                             $413,309
       51             1.859 factor                                             $401,633
      101             1.736 factor                                             $374,876
Construction Costs
   TNO new (120') veils and pioeline                                  '         $200,000
TOTAL PRESENT WORTH Of ALTERNATIVE E

   At 3 percent                                                              13,444,312
   At 5 cercent                                                              $3,310,854
   At 10 percent                                                              $3,016,583

-------
FIGURES

-------
(O
o
o
li
(ED
QZ
 iCO
C
      •f?»«*?s:;

              liillll
                                              :.*«<
                                                        FORMER
                                                        FIRESTONE
                                                          FACILITY
                                                               ASHWORTH
                                                               BROTHERS
                                                               SITE
     LEGEND =
     {   |  SALINAS URBAN AREA
   SITE
                             SCALE
                                           2 MILES
                                                                   FIGURE  I-!


                                                                 VICINITY  MAP
                                                              FORMER FIRESTONE FACILITY
                                                                SALINAS, CALIFC"';: A
                                                                   PREPARED
   REFERENCED
    7.5MIN. U.S.G.S. TOPOGRAPHIC MAP OF CHULAR,
    NATIVIDAD, SALINAS 8 SPRECKEL5 .CALIFORNIA
    QUADRANGLES, DATED 1947, PHOTOREVISED 1968,
    1984,1973,1984 RESPECTIVELY. SCALE' I-24,COO

   ' 1984 IT CORPORATION
    ALL COPYRIGHTS RESERVED
                                                        FIRESTONE  TIRE 8 RUBBER CO.
                                                                  AKRON, OHIO
                                                               .. Creating a Saier Tomorrow
     Do Not Scale Thu Drawing

-------
                                            SAWN i TRS  I  CHECKED 9* \tt*/ \'t-'t-te [DRAWING
                                            8"   I9-I9-9B I  APPROVES 9Y I Jt*  l^//f/»» |NUMB£»
                     190067-89
AREA I
AREA 2
AREA 3
AREA 4
AREA 5
AREA 6
AREA 7
AREA 8
                                   PROPERTY
                                   BOUNDARY
                                IOOOFEET
                                                                      FUEL STORAGE
                                                                      COURT YARD
                                                                      RAILCAR  UNLOADING
                                                                      SLUDGE  BEDS
                                                                      HOLDING  PONDS
                                                                      SEEPAGE  PONDS
                                                                      WASTE OIL TANKS
                                                                      EVAPORATION PONDS
                                                            REFERENCE -
                                                            EXHIBIT B OF RAO HSA 85/86-002
ALL CQPraiGMTS RESERVED
                                                                        F.IGURE 1-2
                                                                        SITE PLAN
                                                                    FORMER FIHESTOIVE fiCILI'T
                                                                      SALINAS, CALIFORNIA
      FIRESTONE TIRE a RUBBER CO.
             AKRON, OHIO
                                                                     ... Ci»r?tlBfT a Sel«r Tomorrow

-------
   WELL LOCATION MAP
   IN SHALLOW AQUIFER
  FORMER  FIRESTONE FACILITY
     SALINAS. CALIFORNIA
         PREPARED FOB
FIRESTONE TIRE 8 RUBBER CO
       AKRON. OHIO
      Cr*atln0 a Safer Tomotrow

-------

-------
     WELL  LOCATION  MAP  FOR
MONITORING  WELLS IN DEEP AOUIfEH
     FONUCK pifttSToMC rjtcnrTr

-------
 *tLL LOCATION MAP FOR AGRICULTURAL
DOMESTIC. INDUSTRIAL 8 MUNICIPAL WELLS
           IN DEEP  AQUIFER

-------
 *
 m
 evj
 N
  40 FEET
                          FUEL, N.D.
                          PC8,  N.D.
tu

-------
3
cvj
<
X
to
o
o
C5

RAWINI
UMBER
Q
*m
4)

ALL COPYRIGHTS RESERVED KJLJ . - • Ci9oung a saioi Tomorrow
Do Not Scale Tnu Drawing

-------
cvj
(0
o
o
O)
11
c 3
02
Is
PHASE B AREAS
                                           •EDGE OF LOADING DOCK
        470ppm,0a<*
            15         APPROXIMATE
           
-------
 to
 CVJ
 CM
 
< 2
(E3
02
515
a «
                 DRYING BED
               SURFACE TO 36 FEET
               GROUND WATER«47 FEET
  DRYING BED
               63,400ppm 08G
               5.2ppm Nl
               2.9ppm Pb
 SURFACE TO 36 FEET
GROUND WATER ® 45 FEET
 43,400 ppraOSG
 17ppm Ni
 2.8ppm Pb
  DRYING  BED
SURFACE TO 36 FEET
GROUND WATER648 FEET
44,900ppm OSG
55ppm Ni
6ppm Pb
            NOTES
      I.   FOR PLAN LOCATION OF
         AREA 4, SEE FIGURE  l~2


            LEGEND
     ®   SOIL SAMPLE LOCATION

   086  OIL AND GREASE
   REFERENCE*
   WOODWARD-CLYDE
   CONSULTANTS, I984o
    1984 IT CORPORATION
    ALL COPYRIGHTS RESERVED
                                        100 FEET
                         FIGURE 1-10

               AREA 4-THREE SLUDGE DRYING BEDS
                  SOIL  SAMPLE  LOCATIONS
                AND CHEMICAL CONCENTRATIONS
                    FORMER FIRESTONE FACILITY
                      SALINAS, CALIFORNIA
                         PREPARED FOR
                  FIRESTONE TIRE 6  RUBBER CO.
                         AKRON, OHIO
                       . Creating a Safer Tomorrow
     Do Not Seal* Thu O'awmg-

-------
 r-
 
0~Z
sS

li
OC 3
QZ
^Tt
Mi
ffi

to
 
-------
i=
_ UJ

II
CC 3
QZ
rani
CD
O
  00
Z
3>

Q.
o
o:
Q.
                                   SEEPAGE POND
                                              GROUND WATER^ 24 FEET

                                              4.2ppb Pb

                                              21 ppm  Ni

                                              53ppm  Zn
                                           SEEPAGE POND
                                                                          ui
                                                                          z
                                                                      tr
                                                                      ui
                                                                      Q.
                                                                      o
               NOTES
          FOR PLAN  LOCATION  OF

          AREA 6, SEE FIGURE  I-2
               LEGEND
        ®SOIL SAMPLE  LOCATION
    REFERENCE'-

    WOODWARD-CLYDE

    CONSULTANTS, 1984 Q



1984 IT CORPORATION

ALL COPYRIGHTS RESERVED
                                   50
                                  100 FEET
                                                             FIGURE  1-12
                                           AREA 6  -  SEEPAGE  PONDS

                                            SOIL SAMPLE  LOCATIONS

                                         AND CHEMICAL CONCENTRATIONS
                                              FORMER FIRESTONE FACILITY
                                                SALINAS, CALIFORNIA

                                                    PREPARED  FOR

                                           FIRESTONE T»RE & RUBBER CO.

                                                  AKRON, OHIO
                                                            Creating a saxer Tomorrow
     Do Not Scale This Drawing

-------
<
CC3
O Z
CD
O

-------
 CD
 CNJ
 OJ

!'.
II
tr 3
QZ
 g^M
 d
 s D'awmq

-------
               CENTRALIZED OR
            DISPERSED  TREATMENT
               FIGURE  2-1

TECHNOI OGY SCREENING SUMMARY
   PHYSICAL  TREATMENT METHODS
FIRESTONE  TIRf   ft  RUSHER  COMPANY
                   INTKKNATIONAI.
                   TECHNOLOGY
                   CORPORATION
 PHYSICAL
TREATMENT
COAGULATION/aOCCULATION
                                                                                           -H:
                                                                                                  OIL-WATER SEPARATION
                                                                                                       FLOTATION
                                                                                                    MEDIA FILTRATION
                                                                                                 ABSORPTION/ADSORPTION
                                                                                                        -»- PHYSICAL ADSORPTION
                                                                                                        -•- CHEMISORPTION
                                                                                                  CAS-PHASE STRIPPING
                                                                                                             AIR STRIPPING
                                                                                                             STEAM STRIPPING
                                                                                                             ALTERNATE GAS STRIPPING
                                                                                                    REVERSE OSMOSIS
                                                                                                        DIALYSIS
                                                                                                    ELECTRODIALYSIS
                                                                                                     ULTRAFILTRATION
                                       FREEZE PROCESSING
                                                                                                          ~- FREEZE CRYSTALLIZATION
                                                                                                          •- FREEZE DRYING
                                                                                                       —»- SUSPENSION FREEZING
                                                                                                          »- ZONE REFINING
                                                                                                      DISTILLATION
                                                                                                      EXTRACTION
                                              »- SOLVENT EXTRACTION
                                            —•- LEACHING
                                            —*- LIQUIFIED GAS EXTRACTION
                                            —•-  SUPERCRITICAL  FLUID OXIDATION
                                              »- STRIPPING
                                    MECHANICAL SEPARATION/TREATMENT!
                                            --*- CENTRIFUGES
                                            --*- BELT FILTER PRESSES
                                            -•- AIR  CLASSIFIERS
                                            -•- VIBRATING SCREENS
                                            —•- SHREDDLRS/GRINDERS
                                            1—^- HYDROCYCLONES
                                                                                                  MAGNETIC SEPARATION
                                                                                                        -»— MAGNETIC CONDITIONING
                                                                                                        -^- HIGH GRADIENT MAGNETIC SEPARATION
                                     EVAPOSA IION/CKYSIAl' IZAilO.M/DRYING
                                                HII  (Hlli/A4

-------
                         CENTRALIZED OR
                      DISPERSED TREATMENT
               FIGURE  2-2

TECHNOLOGY  SCREENING SUMMARY
     CHEMICAL. BIOLOGICAL.  AND
    THERMAL  IREATMENT METHODS
                I'REPARID FOM

               FIRESTONE
       IIRE & RUBBER  COMPANY
                   INTKRNATIONAI,
                  TKCHNOI,O(;Y
                  CORPORATION
    JICAL
TREATMENT
                                                                                                     -H:
                                                                     BIOLOGICAL
                                                                     TREATMENT
                                         NEUTRALIZATION
PRECIPITATION
                                                                                                                      LIQUID/SOLID PRECIPITATION
                                                                                                                      ELECTROSTATIC PRECIPITATION
                                                                                                               ION EXCHANGE
                                                                                                                OXIDATION
                                                                                                                      CHEMICAL
                                                                                                                      WET AIR
                                                                                                                      SUPERCRITICAL FLUID
                                                                                                                      ELECTROLYTIC
                                                                                                                      THERMAL
                                                                                                                      BIOLOGICAL
                                                                                                                REDUCTION
                                                                                                                      ELECTROLYTIC OXIDATION/REDUCTION
                                                                                                                      CHEMICAL REDUCTION
                                                                                                                      DIRECT HYDROGENATION
                                                                                                                PHOTOLYSIS
                                                                                                                IRRADIATION
                                                                                                               STABILIZATION
                                                                                                                      INORGANIC MICROENCAPSULATION/FIXATION
                                                                                                                      INORGANIC VITRIFICATION
                                                                                                                      ORGANIC MICROENCAPSULATION
                                                                                                                      ORGANIC ENCAPSULATION
                                      AEROBIC DEGRADATION
                                                                                                                      ACTIVATED SLUDGE TREATMENT
                                                                                                                      AERATED PONDS OR LAGOONS
                                                                                                                      TRICKLING FILTERS
                                                                                                                      POWDERED ACTIVATED CARBON TREATMENT
                                                                                                            ANAEROBIC DIGESTION
                                                                                                           ENZYMATIC CONVERSION
                                     IN SITU BIOLOGICAL. REMEDIATION
                                   CON TROLLED BACTERIAL APPLICATIONS
                                                 NATURALLY SELECTED
                                                 GENETICALLY ENGINEERED
                                          COMPOSTING
                                          AQUACULTURE
                                                                       THERMAL
                                                                     TREATMENT
                                                          I'l P  (i<)6 /A5 OJH9
                                          INCINERATION
                                                                                                                CALCINATION
                                          VITRIFICATION
                                                                                                             PLASMA P1ROLVSIS
                                                                                                           NUCLEAR DESTRUCTION

-------
GE.NI.R.    LSI'ONSE  AC 11011
urniAi  ii.cumu COY
IECHNOIOGY PROCESS OPTION


SHUT DOWN
EXISTING SVSTF'M

PUMP
ON SITE
WELLS

PUMP
OFFSITE
WELLS

PARTIAL
REMOVAL

OFFSITE
DISPOSAL

NONE

GROUND-WATER
ex FRACTION

GROUND-WATFR
EXTRACTION

• GROUND-WATER
EXTRACTION









NONE

GROUND -WATER
EXTRACTION
WELLS

GROUND-WATER
EXTRACTION
WELLS

GROUND- WATER
EXTRACTION
WELLS

                                      SURFACE DISCHARGE
                                     FOR  AQUIFER RECHARGE
                                        WELL INJECTED
                                     FOR AQUIFER RECHARGE
                                            WATER
                                             USE
                                         NONE
                                 GROUND-WATER INJECTION WELLS
                                      PRETREATMENT
                                                                            POST-TREATMENT
                                                                                NONE
                                                                                                    FIGURE  2-3
        INTERNATIONAL
        TKCHNOI-OCY
        COHI'ORATIDN
 KM  (Wlli/AI  ll.^H'J
                   TECHNOLOGY SCREENING SUMMARY
                    TECHNOLOGY PROCESS OPTIONS
                               PREPARED FOR

                               FIRESTONE
                            TIRE &  RUBBER
                               COMPANY

-------
     FORMER
     FIRESTONE
     FACILITY
  POTENTIOMETRIC  SURFACE
    SHALIOW AQUIFER
       MARCH 1969
        FIRCSTOC FACIUTY
     SALINAS. CALIFORNIA
FIRESTONE TIRE 8 RUBBER CO.
       AKRON, OHIO
     . Creating a SafM

-------

r
                                                                                                                                                        -
                                                                                                                                                                            r-   -::ri
-H    ^!::f>      Jl
  ]f»     ,-  •   v';.  <:'.  ...  -  :
 ff     n        •;;r    •••*
  1                            "
                                                                                                                                                                f
                                                                                            8ENERAU7M BtOLOCH;  CROSS SECTION

                                                                                               i
                                                                                               !  '
         J
                                                                                                                                                               tNEHAi •.'[ _  I "Ji 0
-------
                                                           ...H.-
                                                  >mik/»ri
                                                  • AAH.
                                                                                      1	\"  >^
                                                                                              \
                                                                                                                    **"„
                                                                                       ! •;;:	
                                                                                       A'-'"
                                                                                           • • 'I.
                                                                                         UW» f*/«
                                                                                        NOClO/MNI
                                                                                       AS.,?
                                                                               '""•  ••I*.''''''
                                                                                 NOM?A«("«'M
                                                                                        » » -A* ?•(
                                                                                        «T^">A7»1
                                                                                    '•'••«
                                                                                     SiO
                                                                                    >r«S
                                                                                        ""*i',V,


                                                                                        A«u"110
                                                                            S 5(«/H»^Wu.L,iAjll .^H/t
                                                                               filU
                                                                                           ..-»
.w». i% . olH
    CHWO.L  lA»i .in/I

    *«*"V *3Si
    ^- A»U«  %VT
                                                                                OH»(7/B7I
                                                                                     A
                                                                                        A SI 5  •«)•!•
                                                                                          f»    DHY ( T/tr I
          IOlS/88)
          ir    TT1
          •*»•?    ._!	L^i_
                                                                                            • N'Jl V»#l
                                                                                            9«3N
                                        NOIIl/88)
                                          • AM9U
• «*B4B
                                                                                                                       ^
                                                             ^
                                                                                »
' CONCENTRATIONS IN PP8

1 NO INOICATfs VALUES WEME SILO*
 METHOD DETECTION LIMITS
                                         _utai>._o_._
              I
                       Hi.URF  3-3

                APPROXIMATE  PLUME  «REA
                   SHAl [ 0*  flQUlFE =?
            ',1-DCE  MAXIMUM  . ?NCENTRATIONS
                     4/88 TO 3/89
                 fOBMEB ' BE STOUT FACIIIT-
                    SALINAS. C4LIFOBNI*
                        p»ifpARfo FOR
              FIRESTONE  TIRE 8 RUBBER CO
                      AKRON, OHIO
                                                                                                   Creating a Sa!»r Tomcuiow
                                                                                                                                .A

-------
                                      FORMER
                                      FIRESTONE
                                      FACILITY
LIMITS OF DETECTION
                                 APPROXIMATE  PI UME  AREA
                                     SHAi LOW  AQUIFER
                              I l-l'Ca MAXIMUM '  ''NrENIRATIONS
                                      4/88  I'"  3.89
                                  i  iRMFfc  > Kf S'JfJf  fi'IlL '  •
                                             iL I' ' RNI A
                                FIRESTONE  TIRE  8 RUBBER CO
                                       AKRON. OHIO
1 HO INOICATFS  .tLufS »F •(  flint
 Mf THOD OF Tt l.tlON I IMItS
                                      Civatlna a Sal»r Tomonow

-------
                                                     NDII/III         LIMIT OF
                                                      ~*"""          DETECTION
                                                                                                            FIGURE  3-5

                                                                                                     APPROXIMATE  PI UME AREA
                                                                                                      INTF.RMEDIAIE  AOUIFER
                                                                                                  1,1-DCE MAXIMUM CONCENTRATIONS
                                                                                                          4/88 TO 3/89
                                                                                                       FlRCSTONt TlBf  a RUBMR CO

                                                                                                                AKflON. OHIO
'. HO MOI
  •ITHOO DETECriOH

-------
\
                                                                                                                                                 \
           FIGURE  *  6

    APPROXIMATE  PLUME  AREA
     INTERMEDIATE AQUIKFR
I I.I-TCA MAXIMUM CONCENTRATIONS
         4/88  TO 3. 89
                    2 NO INDICATES VALUES WEHE BCL0W
                                                                                                                        FIRESTONE TIRE  S RUBBER CO

                                                                                                                                AKMON. OHIO

                                                                                                                       FTi
                                                                                                                                                     &

-------
                                                                                               Lou/ol  .                         noi
                                                                                              J—                            • •—
                                                                                                         APPROXIMATE  PLUME  AREA
                                                                                                          INTERMEDIATE  AQUIFER
                                                                                                     1,1,1-TCA MAXIMUM CONCENTRATIONS
                                                                                                              4/88 T 03 78 9
                                                                                                           MUfSTONt TIMC a  mjHCR CO

                                                                                                                    AKRON. OHIO
2 NO INDICATCf V*LUCf WCMC BtUOW
  • ITHOD OCTICTIOK LIHITI

-------
     LIMIT OF

     DETECTION
                                                                                                     APPROXIMATE PIUME
                                                                                                          DEEP  AQUIFER
                                                                                                 I.IDCE MAXIMUM CONCENTRATIONS
                                                                                                          4/88 TO 3/89
                                                                                                      FIRESTONE TIRE 8 RUBBER CO

                                                                                                                    OHIO
S MO INDICATES  VALUE* WCHf BELO* MCTHOP
  OETfCTION LI

-------
    APPROXIMATE PLUME  AREA
        DEEP  AOUIFER
1,1,1-TCA MAXIMUM CONCENTRATIONS
        4/88  TO 3/89
       'OffMf* '  "ft
          SALINAS

-------
    FORMER
    FIRESTONE
    FACILITY
         FIGURE 3-9
EXTRACTION  WELL LOCATIONS
 FOR 1'iif.lPiNG ALTERNATIVES
IRESTONE TIME 8 RUBBER CO
      AKRON, OHIO
     CnottDO a Sate TOOWROW

-------
                                                                                                                FORMER
                                                                                                                FIRESTONE
                                                                                                                FACILITY
ISOgpm  IT-IE3 \     HT-UZ
                                                                                                                    FIGURE
                                                                                                            EXTRACTION WELL LOCATIONS
                                                                                                              PUMPING ALTERNATIVE  i
                                                                                                           FIRESTONE TIRE 8 RUBBER CO
                                                                                                                 AKRON, OHIO
                                                                                                                 Craatlno a Safm Tomanow

-------
      FORMER
      FIRESTONE
      FACILITY
          FIGUHE n Jb

 tXTPACTION AELL _'.)C6TIONS
   PUMPIfJG Al FERNA1IVE ?
FIRESTONE TIRE 8 RUBBER CO
       AKRON. OHIO
      Ci*ating a SotOT Tomonow

-------
     FORMER
     FIRESTONE
     FACILITY
          FIGURE ' 9c
 EXTRACTION WELL LOCATIONS
   PUMI IN'i .'.LrERN/UIVE 3
FIRESTONE  HRE 8 RUBBER CO
       AKRON. OHIO
      Creating a Saisr Tomorrow

-------
     FORMER
     FIRESTONE
     FACILITY
         FIGURE 3-9(1
 EXTRACTION WELL LOCATIONS
   PUMPING ALTERNATIVE
FIRESTONE TIRE 8 RUBBER CO
      AKRON, OHIO
      Qtullofl a ScilAi Tomonow

-------
                                                                                            FORMER
                                                                                            FIRESTONE
                                                                                            FACILITY
IT-IE2   IT-IEI
ISOgpm
                                                                                                FIGURE 3-9e

                                                                                        EXTRACTION WELL LOCATIONS
                                                                                          PUMPING ALTERNATIVE 5
                                                                                       FIRESTONE  TIRE 8 RUBBER CO
                                                                                             AKRON, OHIO

-------
     FORMER
     FIRESTONE
     FACILITY
         FIGURE 3 91
 EXTRACTION WELL LOCATIONS
   PUMPING ALTERNAIIVE 6
FIRESTONE TIRE B RUBBER CO
      AKRON, OHIO
      Cnotlng a Sai«t Tomorrow

-------
     FORMER
     FIRESTONE
     FACILITY
 EXTRACTION  WELL LOCATIONS
      ALTERNATIVE B
FIRESTONE TIRE 6 RUBBER CO
      AKRON, OHIO
      emoting a Sal«i Tomorrow

-------
0S-IO
         FORMER
         FIRESTONE
         FACILITY
             FIGURE 3 II
    EXTRACTION WELL  LOCATIONS
          ALTERNATIVE C
   FIRESTONE  TIRE 8 RUBBER CO
          AKRON, OHIO
         Creating a Sal*r Tomottow

-------
    FORMER
    FIRESTONE
    FACILITY
        FIGURE 3-12
EXTRACTION WELL  LOCATIONS
IRESTONE TIRE 8 RUBBER CQ
      AKRON, OHIO

-------
     FORMER
     FIRE.STONE
     FACILITY
         FIGURE ? l3
 EXTRACTION WELL LOCATIONS
      ALTERNATIVE E
FIRESTONE TIRE 8 RUBBER CO.
      AKRON, OHIO
      Creating a Salci Tomanow

-------
                                      SHALLOW
                                        MODEL AREA
AQUIFER
DIATE A
 EL ARE
                                                       FIRESTONE TIRE B RUBBER CO
                                                          AKRON, OHIO

-------
01
I
o
a>
2/89
                                                            ALTERNATIVE  A
                                                                                    2/90
                                                                                                           IJ-
                       2/91
                                                          FIRESK
                                                          FACILIJ
                       2/93
                                                         13IU.
                                                          FIRESn
                                                          FAC/LII
                                                                                    2/92
                                                                                   TIRES J<
                                                                                   FACILI;
                                                                                   ij.
                                                            C:
                                                                                    2/94
                                                                                  FIRESTl
                                                                                  tACILI I
                                                           PLUME MIGRATION
                                                           SHALLOW AQUIFER
NOTE:
FOR PLAN LOCATION OF  MODEL
AHEA SHE FIGURE 4  1

OUTLINED AREA ENCOMPASSES
CLEANUP LEVELS FOR EACH
CONSTITUENT
                                                                                                            FIGURE 4-1A

                                                                                                         ALTERNATIVE A
                                                                                                        PLUME MIGRATION
                                                                                                        SHALLOW AQUIFER

                                                                                                          PREPARED FOR

                                                                                                    FIRESTONE TIRE & RUBBER CO
                                                                                                          AKRON, OHIO

                                                                                                            INTERNATIONAL
                                                                                                            TECHNOLOGY
                                                                                                            CORPORATION

-------
P)
ffl
                        1/89
                                                             ALTERNATIVE A
                                                                                                             1/90
0?
                        1/91
                                                                                                            1/92
                        1/93
                                                                                                            1/94


                                                                                                           -I  '

                                                                                                           O
                                                            PLUME MIGRATION
                                                         INTERMEDIATE AQUIFER
NOTE
FOR PI AN LOCATION OF  MODEL
AREA SEE FIGURE 4 -1

OUTLINED AREA ENCOMPASSES
CLEANUP LEVELS FOR EACH
CONSTITUENT
         FIGURE 4-18

      ALTERNATIVE A
     PLUME MIGRATION
   INTERMEDIATE AQUIFER
       PREPARED FOR

 FIRESTONE TIRE & RUBBER CO.
       AKRON. OHIO

         INTERNATIONAL
         TECHNOLOGY
         CORPORATION

-------
 <0
 o
 o
 2
                                     ALTERNATIVE B
2/89

                                                                                     6/09
                                                                                                              Cl
                         10/89
Id
                                                           FIRESTi
                                                           f ACILIJ
                         2/91
                                                                                     2/90
                                                                                    FIREST
                                                                                    FACILI
                                                                                                             8/91
                                                                                                            FIREST.
                                                                                                            FACILI)
                                                            PLUME MIGRATION

                                                            SHALLOW AQUIFER

                                                                   9CAIE

                                                               0    SOO    1000 FT
                                                                                                     NOTE:

                                                                                                     FOR PLAN LOCATION OF MODEL
                                                                                                     AREA StE FIGURE « '

                                                                                                     OUTLINED AREA ENCOMPASSES
                                                                                                     CLEANUP LEVELS FOR EACH
                                                                                                     CONSTITUENT
                                                                                                              FIGURE 4-2A

                                                                                                           ALTERNATIVE B
                                                                                                          PLUME MIGRATION
                                                                                                         SHALLOW AQUIFER

                                                                                                            PREPARED FOR

                                                                                                     FIRESTONE TIRE &  RUBBER CO.
                                                                                                            AKRON, OHIO

                                                                                                              INTERNATIONAL
                                                                                                              TECHNOLOGY
                                                                                                              CORPORATION

-------
 CM
 rt
 O
 o
 I
Si
                                                               ALTERNATIVE  B
1/89
                                                                                      1/90
                         1/91
                                                                                                               1/92
L'
..«
                         1/93
                                                                                                               1/94
                                                                           \
                                                             PLUME MIGRATION

                                                           INTERMiOlATE AQUIFER
                                                                                                     FOR PLM4 LOCATION OF MODEL

                                                                                                     AREA  SEE FIGURE 4-1

                                                                                                     OUTLINED AREA ENCOMPASSES
                                                                                                     CLEANUP LEVELS FOR EACH
                                                                                                     CONSTITUENT
                                                                                                              FIGURE 4-2B


                                                                                                           ALTERNATIVE B

                                                                                                          PLUME MIGRATION
                                                                                                        INTERMEDIATE AQUIFER

                                                                                                             PREPARED FOR

                                                                                                      FIRESTONE TIRE & RUBBER CO.
                                                                                                             AKRON. OHIO


                                                                                                              INTERNATIONAL
                                                                                                             I TECHNOLOGY
                                                                                                              CORPORATION

-------
0)
CM
 ID
 O
ill
                                                              ALTERNATIVE C
                        2/89
 6/89
i iRf sn
incnir
                                                                                                              Cl
                         10/89
                         2/91
                                                            FIRESfl
                                                            FACILII
                                                          mj...
                                                             PLUME MIGRATION
                                                             SHALLOW AQUIFER
                                                                    SCALE
                                                               0     500    1000 FT
 2/90
FIRES T<
FACILII
  8/91
FIRESn
FACILH
                                                                                                               Lj
NOTE:
FOR PL
-------
o
o
m
                                                            ALTERNATIVE C
1/89
                                                                                  10/89
                       1/90
                                                                                                          4/90
                       7/90
                                                                                             0
                                                           PLUME MIGRATION
                                                        INTERMEDIATE AQUIFER
                                                                                  10/90
    PLAN LOCATION OF MODEL

AREA SEE FIGURE 4-1

OUTLINED AREA ENCOMPASSES
CLEANUP LEVELS FOR  EACH
CONSTITUENT
                                                                                                            FIGURE 4-3B


                                                                                                         ALTERNATIVE C
                                                                                                        PLUME MIGRATION
                                                                                                     INTERMEDIATE AQUIFER

                                                                                                          PREPARED FOR

                                                                                                   FIRESTONE TIRE & RUBBER CO.

                                                                                                          AKRON. OHIO


                                                                                                           , INTERNATIONAL
                                                                                                            TECHNOLOGY
                                                                                                           I CORPORATION

-------
                                                         0= '
                                                         0S"
                                                         OX l
                                                                  FORMER
                                                                  FIRESTONE
                                                                  FACILITY
                                                               n
                                                                    FIGURE

                                                                EQUIPOTENTIAL LINES
                                                              850-GPM CAPTURE ZONE
                                                               INTERMEDIATE  AQUIFER
*'ID»f »•*•»
                                                             FIRESTONE TIRE 8 RUBBER CO
                                                                   AKRON, OHIO
                                                                   Civatlng a Sa)«t Tomorrow

-------
                                                                                                                                      FLOWUNES
                                                                                                                              850-CPM CAPTURE ZONE
                                                                                                                               INTERMEDIATE AQUIFER
                                                                                                                               ronnfR  FIHE3TONE FACILITY
                                                                                                                                 SALINAS. CALIFORNIA
TARGET CLEANUP AHCA
JANUAMT III!
                                                                                                                               FIRESTONE TIRE 8 RUBBER CO

                                                                                                                                       4KRON. OHIO
FLOW DIRECTION

-------
                                                                                                                                  FLOWLINES
                                                                                                                           400-GPM CAPTURE ZONE
                                                                                                                            INTERMEDIATE AQUIFER
                                                                                                                           FORMER FIRESTONE FACILITY
                                                                                                                              SALINAS. CALIFORNIA
TARGET CLEANUP AREA
JANUARY 1>lt
                                                                                                                           FIRESTONE  TIRE 8 RUBBER CO
                                                                                                                                   AKRON OHIO
FLOW 01 DECT I ON

-------
y\
fv
                         2/89
                                                                ALTERNATIVE D
                                                             urtfsii
                                                             FACILII
                                                           U£U,
   6/09
     SI(
  f ACII ir
IJjJ.  .
                         10/89
                         2/91
                                                             FIHESTi
                                                             FACILII
                                                              t
                                                           (4£U
                                                            FIRESrt
                                                            FACILIT
                                                              Cl
                                                              PLUME MIGRATION
                                                              SHALLOW AQUIFER
   2/90

 FACILIJ




   tl
   2/92
 FiaesT'
 FtCILIl
   t
NOTE:

FOR PLAN LOCATION OF MODEL
AREA  SEE FIGURE •» -1

OUTLINED AREA ENCOMPASSES
CLEANUP LEVELS FOR EACH
CONSTITUENT
         FIGURE -I 6A

      ALTERNATIVE D
     PLUME MIGRATION
     SHALLOW AQUIFER

        PREPARED FOR

 FIRESTONE TIRE &  RUBBER CO.
        AKRON. OHIO

        I INTERNATIONAL
         TECHNOLOGY
         CORPORATION

-------
                                                               ALTERNATIVE  D
                         1/89
10/tS'i
                         1/90
 4/90
> i
III I
Co
                         7/90
10/90

                                                                           <•>•
                                                                           \
                                                                                                  0
                                                              PLUME MIGRATION
                                                           INTERMEDIATE AQUIFER
                                                                    SCALE
                                                                                                                             NOTES:
OUTLINED AREA ENCOMPASSES
CLEANUP LEVELS FOR EACH
CONSTITUENT

FOH PLAN LOCATION OF MODEL

AREA  SEE FIGUF1E 4 1

PUMPING RATE 650 qprn

STAHT OF PUMPING
OCTOBER t989
                        ALTERNATIVE  D

                       PLUME MIGRATION
                    INTERMEDIATE AQUIFER

                         PREFAHED FOH

                  FIRESTONE TIRE £ niJEBEfJ CO.
                         AKRON. OHIO


                           INTERNATIONAL
                           TECHNOLOGY
                           CORPORATION

-------
CD
 I
1^
10
o
o
ALTERNATIVE D'
                         1/89
                                                4/00
                         7/90
                                                                                                              10/90
2
Sv
                         1/91
                                           . o
                                                                                                               10/91
                                                             PLUME  MIGRATION
                                                           INTERMEDIATE AQUIFER
                                                                                                                           NQLES:
                                                                    500    1000 FT
                                                                OUTLINED AREA ENCOMPASSES
                                                                CLEANUP LEVELS FOR EACH
                                                                CONSTITUENT

                                                                FOR PLAN LOCATION OF MODEL

                                                                AREA SEE FIGUHE  -1-1


                                                                PUMPING RATE t.50 ypm  •


                                                                STA'tT OF PUMPING
                                                                APHIL 1990
                                                                         FIGURE 4 -6C


                                                                      ALTERNATIVE  D'

                                                                     PLUME MIGRATION
                                                                  INTERMEDIATE AQUIFER

                                                                       PREPARES COR

                                                                FIRESTONE TIRE 8, RUBBER CO.
                                                                       AKRON, OHIO


                                                                         INTERNATIONAL
                                                                         TECHNOLOGY
                                                                         CORPORATION

-------
to
I
K
10
o
o
0>
1/89
                                ALTERNAHVE D (400 gpm)
                                                                                  10/09
                          1/90
                                                                                                             7/90
                          1/91
                                                                                   1/92
                                                                          \
                                                             PLUME MIGRATION

                                                           INTERMEDIATE AQUIFER
                                                                                                                           NOTES
OUTLINED AREA ENCOMPASSES

CLEANUP LEVELS FOR EACH

CONSTITUENT


FOH PLAN LOCATION OF MODEL

AREA SEE FIGURE -4 1


START OF PUMPING

OCTOBER  1989
                                                                                                              FIGURE 4 6D


                                                                                                       ALTERNATIVE D 1400 gpml

                                                                                                         PLUME MIGRATION

                                                                                                       INTERMEDIATE AQUIFER


                                                                                                            PBEPAHED FOR


                                                                                                     FIRESTONE TIRE & RUBBEH CO.

                                                                                                            AKRON. OHIO


                                                                                                              INTERNATIONAL
                                                                                                              TECHNOLOGY
                                                                                                              CORPORATION

-------
 n
 to
 i
 N
 1C
 O
 O
                         2/89
ALTERNATIVE E
                                                             i mi :. / c
                                                             t At.ll I I
                                                 6/fl'J

                                                / IHI  !
                                                I ti.n 11
                         10/89
                                                                                                                 2/90
£7
I 0>
                          2/91
                                                               C:
                                                               PLUME MIGRATION

                                                               SHALLOW AQUIFER
                                                 2/92
                                                 IR? s n
                                                 Acn n
                                                                      500     1000 FT
NQl L:.:

FOn  I'LAN LOCATION OF MODEL

AREA SEE FIGURE  I -1

OUTLINED AHEA ENCOMPASSES
CLEANUP LEVELS FOR EACH
CONSTITUENT
                                                                           FIGUME J -7A


                                                                       ALTERNATIVE  E

                                                                      PLUME MIGRATION
                                                                      SHALLOW AQUIFER

                                                                         PREPARED FOB

                                                                  FIRESTONE TIRE S RUBBER CO.

                                                                         AKRON. OHIO


                                                                           INTERNATIONAL
                                                                           TECHNOLOGY
                                                                           CORPORATION

-------
ID
O
to
I

10
o
O
                        1/89
                                                              ALTERNATIVE E
                                                                                                               1/90
                        1/91
                                                                                                               1/92
r
                        1/93
                        fc>5>
                                                -1


                                                                                                                              OUTLINED AREA ENCOMPASSES

                                                                                                                              CLEANUP LEVELS FOR  EACH
                                                                                                                              CONSTITUENT
                                                                                                                                        FIGURE -I 7B


                                                                                                                                     ALTERNATIVE  E

                                                                                                                                   PLUME MIGRATION

                                                                                                                                 INTERMEDIATE AQUIFER

                                                                                                                                      PREPARED FOR


                                                                                                                               FIRCSTQNE TIRE 3. RUBBER CO.

                                                                                                                                      AKRON, OHIO


                                                                                                                                        INTERNATIONAL
                                                                                                                                        TECHNOLOGY
                                                                                                                                        CORPORATION

-------
             UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                                 REGION IX
                             215 Fremont Street
                           San Francisco. Ca. 94105
MEMORANDUM
SUBJECT:



TO:

THRUT

FROM:


DATE:
Adjustment of Risk Values and
Recommendation for
Groundwater Cleanup Levels
at Firestone Salinas

Alexis Strauss, Chief
Superfund Enforcement Branch

Betsy Qjfnow, Chief
Enforcement Programs Section
Jeff Dhont  . ^
Remedial Proje€t'Manager
Firestone Salinas Site
June 20, 1989
Purpose

    The purpose of this memorandum is. to
explain certain  adjustments  which were
made in risk calculations for the Firestone
Salinas Site, and  to provide a rationale for
selection of groundwater cleanup levels at
the Site.
Recommendation

   This memorandum will recommend
that the cleanup levels  established  in the
draft RAP  be accepted as protective and in
accordance with ARARs, provided that the
cleanup level for 1,1-DCA  is lowered from
20 ppb to 5 ppb.
                      Introduction to Background and Issues

                       Firestone submitted a final draft FS/RAP
                      to  DHS on June 5,  1989.   The RAP sets
                      cleanup  levels for the groundwater
                      remediation  effort  at the  Site,  based  on
                      both risk  and ARARs.  To be able to ad-
                      dress these proposed  cleanup levels, EPA
                      has had to perform three tasks:

                       1) Make  adjustments and correct certain
                       errors in the manner in  which risk cal-
                       culations were made for the Site;

                       2) Address the  issue of whether 1,1-DCE
                       is to be treated as a  carcinogen  in the
                       quantitative risk assessment;

                       3)  Firestone  used a rather unusual
                       method for arriving at the cleanup levels.
                       EPA must compare the results  of
                       Firestone's  method with  the results that
                       would be obtained  by EPA's method and

-------
                                       - 2 •-
    decide whether  the  proposed cleanup
    levels are  acceptable  from  the  EPA
    standpoint.

    Note that the computation of cleanup
levels is a related  yet somewhat separate
issue from the calculation  of risk actually
posed by the site.  A quantitative risk as-
sessment was performed  to determine, un-
der a probable worst-case, scenario,  what
the risk would be from  the site.  This as-
sumed  that  the concentration that people
would be  drinking for a seventy-year
lifetime is a geometric  mean of the con-
centrations found in affected wells.

    With regard to cleanup levels, however,
we are calculating  the risks which would
exist if concentrations were brought to the
cleanup levels themselves.  Rather than as-
sessing exposure based on a geometric mean
over affected  wells,  it is assumed  that
people  are exposed to water at the cleanup
levels themselves.  In other words, it is as-
sumed that each well constitutes a point of
compliance and  must meet the cleanup
level requirement.

    Each of the above three issues will now
be discussed in turn.
Adjustments in Calculations

    The  following adjustments and  recal-
culations were  required in order to assess
the appropriateness  of the proposed
cleanup levels:

    1. Certain  values for cancer  potency
      factors had  been updated  without
      Firestone's knowledge.   Recalcula-
      tion  was required using  the new
      CPF values.

    2. Noncarcinogenic effects  of car-
      cinogens had  not been included in
      the calculation of  the  original site
      risk.  When these were included and
      a  new hazard index  computed for
      the  site,   the HI  was  still  insig-
    nificant (< 0.01), and so it became ap-
    parent that the cancer risk would drive
    the cleanup level selection.

 3. 1,1-DCA had not been treated by Fires-
    tone as a carcinogen.   Recalculations
    were required which incorporated  1,1-
    DCA in the cancer assessment.

 4. Firestone  had  not considered  inhala-
    tion exposure in  its risk  calculations.
    Primarily at issue here was the inhala-
    tion  of volatile organics  by  persons
    while in  the shower.  A  standard es-
    timation  was  used,   which  has  been
    used by EPA while awaiting the results
    of indoor  shower inhalation  studies.
    This is that the exposure  to chemicals
    by inhalation, i.e. the dose, is equal to
    the exposure from ingestion of drink-
    ing water.   Making this assumption
    does not  merely  double the  risk be-
    cause cancer  potency  factors  for in-
    halation may vary from those for in-
    gestion.   Thus,  a separate inhalation
    risk calculation must be made and
    added  to  the ingestion risk  to obtain
    the total risk.
1,1-Dichloroethylene as a Carcinogen

  1,1-Dichloroethylene (1,1-DCE) is cur-
rently  the  primary contaminant  at Fires-
tone.  In all likelihood, if its concentration
were reduced by remediation to the Action
Level  of 6 ppb,  all  other contaminants
would  be  non-detectable.   At issue is
whether it  is appropriate to treat 1,1-DCE
in a quantitative risk assessment, or to base
its cleanup on ARARs.  Upon review with
Regional Toxicologist Gerald Hiatt and
discussion with DHS toxicologists, the fol-
lowing  points  and  recommendation  have
emerged with regard to this issue.

  1,1-DCE is a Class C Agent, "Possible Car-
cinogen" (as distinguished  from chemicals
classified  as  Class A,  "Known Human
Carcinogens", or Class B, "Probable  Human
Carcinogens").  EPA's practice with respect
to risk assessment and  setting cleanup

-------
                                       -  3 -
levels is to treat Class C Agents on a case-
by-case basis, using either a modified-RfD
approach or a quantitative risk assessment.
The  modified-RfD approach  is similar  to
the RfD calculation normally used for
non-carcinogens;  additional safety factors
are introduced to take into account the car-
cinogenic  potential of  Class C agents and
the possibility  of multiple routes of ex-
posure to  the chemical.  This approach  is
often used by  EPA's Office  of Drinking
Water  (ODW) in setting  MCLGs;  accord-
ingly,  when used  it generally results  in
cleanup numbers based on ARARs.   The
use of  the approach  is  particularly ap-
propriate  for those Class C agents  where
the evidence for  carcinogenicity is  espe-
cially weak. In such cases, the use of quan-
titative cancer risk assessment can produce
less useful or even misleading results.

    For 1,1-DCE in groundwater, the avail-
able  data support the use of the  modified-
RfD approach to  setting cleanup  levels.
The  number of negative cancer studies on
1,1-DCE  is  notable.    Five  oral car-
cinogenicity studies have been  conducted
on 1,1-DCE,  including a lifetime  joint
study by the National Cancer Institute and
the National Toxicology Program.  All of
these oral  cancer  studies were negative.
Eleven  studies  on 1,1-DCE evaluated car-
cinogenic potential via inhalation; ten were
negative.   One  study,  by Maltoni,  did
produce evidence of carcinogenic potential
in mice,  although  this  interpretation  is
blurred somewhat by lack of a clear dose-
response relationship.  A similar study by
the same  group  of investigators did not
produce cancer in rats, even though  doses
of up to six-fold higher were administered.
Thus,  the evidence supporting  classifica-
tion  of  1,1-DCE as a "carcinogen" are espe-
cially weak.

    At Firestone, if 1,1-DCE is treated as a
carcinogen in  a  quantitative  risk assess-
ment, rather  than using  the modified-RfD
approach,  then at the DHS Action Level of
6 ppb  it will single-handedly put the risk
for the site at greater than 3.5E-4. In  order
to bring the risk below l.OE-4, the cleanup
level for 1,1-DCE would have to be set at 1
ppb or less.

  After reviewing this  issue and consulting
with Gerald  Hiatt, I recommend that 1,1-
DCE  be removed from  the quantitative
cancer risk calculation, and that  its DHS
Action Level of  6 ppb (the EPA MCL  is
7 ppb) be considered protective. This is in
accordance with  ODWs  decision  to use
qualitative rather than quantitative risk as-
sessment in  setting the MCLG  (MCL and
MCLG are equal for  1,1-DCE) for  this
chemical.

  In the risk calculations which follow, it is
assumed  that  all  wells at  Firestone  will
meet the DHS  Action  Level of 6 ppb for
1,1-DCE, and that this will  be  considered
protective. Accordingly, 1,1-DCE is not in-
cluded in the risk calculations.
Firestone's Method  of  Cleanup  Level
Derivation

Protectiveness of Proposed Cleanup Levels

 In  determining  the proposed cleanup
levels, Firestone determined the l.OE-6 can-
cer risk  level  or  each carcinogen as if it
were alone.  In other words,  sum risk  was
not calculated.  Then, where the  lowest
ARAR for any chemical was lower than
the  l.OE-6 risk for  that compound,   the
ARAR replaced the l.OE-6  level  as   the
proposed cleanup level.      Of course,  in
doing this, Firestone had not made any  of
the necessary adjustments discussed  above,
such  as  incorporation  of  inhalation   ex-
posure.

 Firestone's  method bears several dis-
crepancies with standard EPA risk  assess-
ment guidelines. However, EPA will  accept
risk in the 10   to 10   range when compar-
ing risks against ARARs.    Even  though
Firestone did  not calculate  a cumulative
risk in its cleanup level calculation,  it did
use a 10   point of departure on each com-
pound. It was therefore possible, regardless

-------
                                       - 4  -
of the nature of Firestone's method, that
the resulting cleanup levels were acceptable
anyway.  This potential was assessed and
the results can be seen in the accompanying
Tables.

    The Tables show cumulative  risks, in-
cluding inhalation  exposure and treating
1,1-DCA as  a carcinogen.  The first Table
computes  the  excess cancer risk  assuming
that all chemicals are present at Firestone's
proposed cleanup levels.  The second Table
computes  the  excess cancer risk  assuming
that all the chemicals are present at the
lowest ARAR for each chemical.

    PLEASE NOTE that  in the first Table,
the proposed cleanup level (PCL) for 1,1-
DCA has  been entered  as 5 ppb, instead of
Firestone's actual proposed level of 20 ppb.
This  is because: 1) DHS  has  an  Action
Level of 5 ppb,  and may propose an MCL
of the same in the near future,  and  2) if
the level of 1,1-DCA is left at  20 ppb, the
total risk will exceed l.OE-4. It  is  therefore
assumed that the level for this compound
will  be  lowered to 5 ppb.   From an en-
gineering  standpoint,  this  will  make little
difference in  remediation,  because when
1,1-DCE is  reduced to its  action level  of
6 ppb,  1,1-DCA will remain at levels far
below 5 ppb,   barring  very unusual cir-
cumstances.

    It can be seen from the first Table that
the proposed cleanup levels provide for a
total risk  not  exceeding  3.3E-S (assuming,
of course, that 5 ppb is  used for 1,1-DCA
instead of 20ppb).

    In the second Table, it can be  seen that
the cleanup  levels (except  for  20 ppb for
1,1-DCA) are all equal to or lower than the
lowest ARAR  for the  compound.  It caj
also  be  seen that, even if  all  the cleanup
levels were  raised to the ARARs, the risk
would still be  acceptable at 4.1E-4.  Thus,
with the exception of 20 ppb for  1,1-DCA,
Firestone's proposed cleanup levels (PCLs)
are protective  from a risk  standpoint and
meet applicable ARARs.  This is true even
though the method, of deriving the cleanup
levels may not have completely conformed
to EPA's method for such computations.
Conclusion

 The following is recommended:

1.   1,1-DCE  be removed  from the quan-
 titative (cleanup level)  risk  assessment
 and a level of 6 ppb be considered protec-
 tive;

2.   the cleanup level for  1,1-DCA be
 lowered from 20 ppb to 5 ppb;

3.   the cleanup levels proposed  by Fires-
 tone (except for  1,1-DCA) be considered
 protective and in accordance with ARARs
 and  therefore that EPA concur with their
 adoption;

4.   the RAP declare that these levels shall
 be met in each and every monitoring well
 before cleanup can be considered at-
 tained.

 If the above is adopted,  the risks at the
site from groundwater will be acceptable
even though  the method Firestone used to
calculate the  cleanup levels did not exactly
conform to our method.

-------
                                        FIRESTONE  SALINAS  SUPERFUND  PROJECT
Assessment of Excess Cancer Risk at Prooosed Groundwater Cleanup Levels
CHEMICAL ORAL CPF IHHAL CPF
[CAS NO.]
1 , 2-0 I CHLOROETHANE 9.1E-2 9.1E-2
(1,2-DCA)
(107-06-2J
TRICHLOROETHYLENE 1.1E-2 1.3E-2
(TCE) [79-01-6]
TETRA-
CHLOROETHYLENE 5.1E-2 3.3E-3
(PCE) 1127-18-4]
BENZENE 2.9E-2 2.9E-2
[71-43-2]
1,1-D1CHLOROETHANE 9.1E-2 9.1E-2
(1,1-DCA) [75-34-3]
PROP. DOSE AT D.U. RISK INHAL RISK TOTAL RISK
CLEANUP PCL AT PCL AT PCL AT PCL
LEVEL (mg/kg/day)
(ug/O t*1)
0.5 1.4E-5 1.3E-6 1.3E-6 2.6E-6
3.2 9.1E-5 1.0E-6 1.2E-6 2.2E-6
0.7 2.0E-5 1.0E-6 6.6E-8 1.1E-6
0.7 2.0E-5 5.8E-7 5.8E-7 1.2E-6
5 <*2> 1.4E-* 1.3E-5 1.3E-5 2.6E-5
1 1
TOTAL RISKS AT PROPOSED CLEANUP LEVELS ore====> 1 . 7E - 5 1.6E-5 | 3.3E-S |

I I
CPF = Cancer Potency Factor   PCL = Proposed Cleanup Level   D.U. = Drinkfng Water   INHAL » Inhalation

NOTE;  Calculation assumes 70-kg body weight, and ingestion of 2 liters of water per day.  over • 70-year lifetime.

       <*1>:  The dose acquired through ingestion is assumed, for estimation, to be equal  to the dose acquired by
              inhalation.  This has been a standard EPA assumption while indoor inhalation studies are being
              performed and confirmed.
                                                                                                               I
       C*2>:  VERY IMPORTANT -- Firestone did not propose 5 ug/l in their FS RAP.   The proposed value was 20 ug/l.
              This Table assumes that the PCL Will be dropped to 5 ug/l.  DHS has  an action level  of  5, and may
              issue an MCL at this level.  Also. If the level for 1.1-DCA is left  at 20 ug/l.  the  total risk will
              exceed 1 .0E - 4 .

-------
                                        FIRESTONE  SALINAS  SUPERFUMO  PROJECT
Assessment of Excess Cancer Risk at Lowest Groundwater Standards (ARARs)
CHEMICAL ORAL CPF INHAL CPF
[CAS MO.)


»
1 ,2-DICHLOROETHANE 9.1E-2 9.1E-2
(1 ,2 -OCA)
[107-06-21
TRICHLOROETKTLENE 1.1E-2 1.3E-2
(TCE) [79-01-61
TETRA-
CHLOROETHYLENE 5.1E-2 3.3E-3
(PCE) [127-18-41
BENZENE 2.9E-2 2.9E-2
[71-43-21
1 ,1-DICMLOROETHANE 9.1E-2 9.1E-2
| LOU LOU CLASS
IARAR ARAR OF
|ug/l NANE CARC.
I











0.5 CANCL 82


5 NCL B2


5 NCL B2

1 CANCL A

5C*2> A.L. C
DOSE AT D.U. RISK INHAL RISK TOTAL RISI
LOU ARAR AT ARAR AT ARAR AT ARAR
(ug/kg/day)
C*2>
1.4E-5 1.3E-6 1.3E-6 2.6E-6


1.4E-4 1.5E-6 1.8E-6 3.3E-6


1.4E-4 7o1E-6 4.6E-7 7.6E-6
<
2.9E-5 8.4E-7 8.4E-7 L7E-6
'
1.4E-4 1.3E-5 1.3E-5 2.6E-5 '
(1,1-OCA) [75-34-31 j
1
TnYAI'BICVCAYinLfC6TADADC«««a«H9* 9 £ C • C 1TB.C I A { C • C
TU^IALKISKSnlLUWcSIAKAKS •**"***> . . c • * C 9 1 • r t > | H • 1 t 3
I 	
CPF " Cancer Potency Factor   PCL * Proposed Cleanup Level   D.U. • Drinking Uater   INHAL » Inhalation

NOTE;  Calculation assumes 70-kg body weight, and Ingestion of 2 liters of Mater per day, over a 70-y.ear lifetime.
""^^"^                                                                                   - ^        . ..r"'*'      '

       {*1>:  The dose acquired through Ingestion is assumed, for estimation, to be equal to the dose acquired by
              inhalation.  This has been a standard EPA assumption while indoor inhalation studies are being
              performed nnd confirmed.

       {•2>:  DHS action level of S ug/l.  Expected NCL of 5 ug/l.                                             •

-------