United States         Office of
Environmental Protection    Emergency and
Agency            Remedial Response
EPA/ROD/R09-90/052
September 1990
Superfund
Record of Decision
Intersil, CA

-------
50272-101
 REPORT DOCUMENTATION
        PAGE
1. REPORT NO.
     EPA/ROD/R09-90/052
                                                                     3. Recipient's Accession No.
 4. Title and Subtitle
   S'UPERFUND RECORD OF  DECISION
   Intersil,  CA
   First Remedial Action - Final
                                           5. Report Date
                                              .  09/27/90
 7. Auttior(s)
                                                                     8. Performing Organization RepL No.
 9. Performing Organization Name and Address
                                                                     10. Project/Task/Work Unit No.
                                                                     11. ContractfC) or Grant(G) No.

                                                                     (C)
 12. Sponsoring Organization Name and Address
   U.S.  Environmental  Protection  Agency
   401 M Street,  S.W.
   Washington,  D.C.   20460
                                           13. Type of Report & Period Covered

                                                800/000
 IS. Supplementary Notes
 16. Abstract (Limit: 200 words)

 The  12-acre Intersil site  contains two  industrial properties,  Intersil,  Inc.,  and
 Siemens Components,  Inc.,  in Cupertino,  California.   Since 1978,  Siemens  has
 manufactured  semiconductor products  for optoelectronic applications at the  site.  Former
 underground waste-handling facilities,  which have been removed,  included  five unvaulted
 waste solvent  tanks  and an unvaulted acid dilution basin.  Solvents are currently stored
 above-ground  and wastewater is treated  in an acid neutralization system.  From 1967 to
 1988,  Intersil operated as a semiconductor assembly  facility.   Two vaulted  and one
 unvaulted underground acid neutralization systems, now excavated,  were used in the
 operation.  Both facilities used various organic solvents and  commercial  mixtures.
 Contamination,  a result of releases  from the underground waste handling  facilities at
 both plants,  has been detected in soil  and ground water beneath the site.   A contaminant
 plume also has been  detected,  which  affects offsite  ground water.   In 1983,  Siemens
 began onsite  soil vapor extraction,  and subsequently in 1986,  began pumping and
 treatment of  onsite  ground water.  Intersil began onsite ground water treatment and soil
 vapor extraction in  1987.   This Record  of Decision  (ROD) outlines  the final remedy
 addressing onsite source areas, and  onsite and offsite contaminated ground  water.  The

 (See Attached Page)                               	
 17. Document Analysis a. Descriptor*
    Record  of Decision  -  Intersil,  CA
    First Remedial Action - Final
    Contaminated Media:   soil, gw
    Key Contaminants:   VOCs (PCE,  TCE,  toluene),  other organics (phenols)

   b. Identifiers/Open-Ended Terms
   c. COSAT1 Field/Group
 18. Availability Statement
                            19. Security Class (This Report)
                                   None
                                                      20. Security Class (This Page)
                                                     	None	
21. No. of Pages
     107
                                                                                22. Price
(See ANS4-Z39.18)
                                      See Instructions on Reverse
                                                      OPTIONAL FORM 272 (4-77)
                                                      (Formerly NTIS-35)
                                                      Department of Commerce

-------
EPA/ROD/R09-90/052
Intersil, CA
First Remedial Action - Final

Abstract (Continued)

primary contaminants of concern affecting the soil and ground water are VOCs including
PCE, TCE, and toluene; and other organics including phenols.

The selected remedial action for this site includes enhancement and/or expansion of
onsite and offsite ground water pumping and treatment systems,  which use air stripping,
and the soil vapor extraction systems,  which use carbon adsorption at the Siemens and
Intersil facilities;  excavating 40 cubic yards of soil contaminated with greater than
10 mg/kg semi-volatile organics at the Siemens facility,  followed by offsite disposal;
pumping and treatment of offsite ground water using air stripping; discharging all
treated ground water to onsite surface water; and monitoring soil vapor and ground
water.  The estimated present worth cost for this remedial action is $18,750,000.  O&M
costs were not provided.

PERFORMANCE STANDARDS OR GOALS:  Ground water cleanup standards were chosen as the more
stringent of Federal or State MCLs,  or State Recommended Drinking Water Action Levels
(RDWALs) .  Chemical-specific goals include PCE 5 ug/1 (State MCL), TCE 5 ug/1 (State
MCL), and toluene 100 ug/1 (RDWAL) .   Soil cleanup goals have been set at 1 mg/kg total
VOCs for vapor extraction, and 10 mg/kg total semi-volatile organics (including phenols)
for soil excavation and offsite disposal.

-------
• It !.'«.
           UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                              REGION 9
                        1235 MISSION STREET
                      SAN FRANCISCO, CA 94103

                          RECORD OF DECISION
                         DECLARATION STATEMENT
   SITE  NAME AND LOCATION

   Intersil/Siemens Superfund Site
   Cupertino,  California


   STATEMENT OF BASIS AND PURPOSE

   This  declaration document presents the selected remedial action
   for the Intersil/Siemens site located in Cupertino,  California,
   which was chosen in accordance with the Comprehensive Environmen-
   tal Response, Compensation and Liability Act of 1980, 42 U.S.C.
   Section 9601, .as amended by the Superfund Amendments and
   Reauthorization Act of 1986,  (CERCLA), and the National Oil and
   Hazardous Substances Pollution Contingency Plan,  40  C.F.R.  Part.
   300,  55 Fed. Reg.  8666 (NCP).  This decision is based on the ad-
   ministrative record for this site.

   The State of California concurs with the selected remedy.


   ASSESSMENT OF THE SITE

   Actual or threatened releases of hazardous substances from this
   site, if not addressed by implementing the response  action
   selected in this Record of Decision (ROD), may present an im-
   minent and substantial endangerment to public health, welfare,  or
   the environment.
   DESCRIPTION OF THE SELECTED REMEDY

   The selected remedy for the Intersil/Siemens site addresses the
   principal threats posed by the site,  ground water and soil con-
   tamination.  The primary chemicals of concern include
   1,1-dichloroethene (1,1-DCE);  trichloroethene (TCE);
   tetrachloroethene (PCE); 1,1,1-trichloroethane (1,1,1-TCA); freon
   113;  and toluene.

   Several interim response actions were performed at the site by
   Intersil and Siemens.   This action represents the final remedial
   action to remove contaminants  from ground water and soil.   The
   major components of the selected remedy are:

-------
  o  Excavation of an estimated 40 cu. yds. of soil from the
Siemens on-site area.  The soil will be disposed of in compliance
with RCRA land disposal restrictions.

  o  Operation of 23 soil vapor extraction wells (15 wells in the
Siemens on-site area and 8 in the Intersil on-site area) with
treatment by carbon adsoprtion.

  o  Operation of 20 ground water extraction wells (13 wells in
the Siemens on-site area and 7 wells in the Intersil on-site
area).   Extracted ground water will be treated by air stripping
and discharged to Calabazas Creek under an NPDES permit.

  o  Operation of three ground water extraction wells in the
off-site area.  Extracted ground water will be treated by air
stripping and discharged to Calabazas Creek under an NPDES per-
mit.

  o  Continued monitoring of ground water and soil to verify con-
tainment of the contaminated' ground water and attainment of
cleanup levels.

                                 . ,s,
STATUTORY DETERMINATIONS

Promulgated maximum contaminant level goals (MCLGs) serve as the
ground water cleanup standards for those chemicals of concern
with MCLGs greater than zero.  MCLGs are the ground water cleanup
standards for two chemicals of concern at Intersil/Siemens: 1,1-
DCE and 1,1,1-TCA.  In these two instances, the California Action
Level (AL) or federal or state maximum contaminant level (MCL)
that has been chosen as the cleanup standard is either equivalent
to or more stringent than the federal MCLG.

The selected remedy is protective of human health and the en-
vironment, complies with federal and State requirements that are
legally applicable or relevant and appropriate to the remedial
action,  and is cost-effective.  This remedy utilizes permanent
solutions and alternative treatment technologies or resource
recovery technologies to the maximum extent practicable for this
site, and satisfies the statutory preference for selecting
remedies that employ treatment that reduces the toxicity,
mobility, or volume of the hazardous substances.  A review of the
remedial action will be conducted every five years, after com-
mencement to ensure that the remedy continues to provide protec-
tion of human health and the environment.
         Date                        -, ^-Daniel W. McGovern
                                        Regional Administrator
                                            EPA Region IX

-------
                        Table of Contents
Declaration
Decision Summary
    I.  Site Description	  1
   II.  Site History and Enforcement Activities	  1
  III.  Community Participation Activities	  1
   IV.  Scope and Role of Response Action	  2
    V.  Summary of Site Characteristics	  2
   VI.  Summary of Site Risks	  3
  VII.  Summary of Alternatives	  3
 VIII.  Comparison of Alternatives	  4
   IX.  The Selected Remedy	  4
    X.  Statutory Determinations	  7
Responsiveness Summary
Appendices
    A.  RWQCB Site Cleanup Requirements
    B.  Correspondence
    C.  Maps
    D.  Administrative Record Index

-------
        UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                           REGION 9
                     1235 MISSION STREET
                   SAN FRANCISCO, CA 94103

                         DECISION SUMMARY

The U.S. Environmental Protection Agency  ("EPA") and the
California Regional Water Quality Control Board, San Francisco
Bay Region ("Regional Board"), have worked together to select the
remedy for the Intersil/Siemens site.  Consequently, portions of
the documents by which the Regional Board has embodied its
selection of the remedy under State law reflect the efforts of
both agencies to investigate the site, to assess the risks which
it poses, and to evaluate and compare possible remedial
alternatives.  Particularly, certain portions of Order No. 90-119
which was adopted by the Regional Board on August 15, 1990,
referred to hereafter as the "Order," accurately set forth the
views and rationale of EPA.  Consequently, this Decision Summary
will refer to portions of those documents (both are attached),
and by such reference they are thereby deemed to be incorporated
into this Decision Summary.

I.  SITE DESCRIPTION

Finding 1 of the Order describes the Intersil/Siemens site.
Regional and site maps are found in Appendix C of this Record of
Decision ("ROD").  Residential neighborhoods are within a few
hundred feet north and south of the site, and an orchard is
approximately 2000 feet to the east.  There are five active
monitoring wells within a one-mile radius of the site, three of
them downgradient.


II.  SITE HISTORY AND ENFORCEMENT ACTIVITIES

Findings 3, 4, 11 and 25 of the Order provide a history of site
activities and state and federal enforcement activities at the
Intersil/Siemens site.


III.  COMMUNITY PARTICIPATION ACTIVITIES

Finding 22 of the Order describes how the public participation
requirements of CERCLA Sections 113 and 117 were met in the
remedy selection process.  A response to comments received during
the public comment period is included in the Responsiveness
Summary, which is part of this Record of Decision ("ROD").

-------
IV.  SCOPE AND ROLE OF RESPONSE ACTION

The selected remedy addresses the principal threats posed by the
site, ground water and soil contamination for the Siemens on-site
area, the Intersil on-site area, and the off-site area.  Finding
11 of the Order describes interim remedial actions at the site
and evaluates their effectiveness in removing and treating
contaminated ground water and in reducing contaminant migration
to ground water by means of vapor extraction and treatment of
contaminated soils.  The selected remedy will address ground
water contamination in the A- and B- zones on-site and in the B-
and C-zones off-site.  Contaminants removed from both soil and
ground water will be captured and permanently destroyed,
significantly reducing the toxicity, mobility or volume of the
hazardous substances in both media.
VI.  SUMMARY OF SITE CHARACTERISTICS

Findings 5 through 10 of the Order describe site hydrogeological
conditions and the nature and extent of organic chemical
contamination in soil and ground water at the Intersil/Siemens
site.
VII.  SUMMARY OF SITE RISKS

EPA policy and guidance require that the potential risk to human
health and the environment be evaluated under a No-Action
scenario.  This scenario assumes unrestricted access to site
contaminants (including soils and ground water) and assumes that
all on-going treatment and/or mitigation measures are terminated
immediately.  The information provided by the baseline risk
assessment is then used to characterize the current and potential
threats posed by the site to human health and the environment.

No exposure pathways with an excess cancer risk number (ECRN)
greater than the 10~4 to 10~6 range or a non-carcinogenic hazard
index (HI) greater than 1 were identified under current site
conditions.  Table 1 presents on-site and off-site pathway
exposures under future use scenarios.

Finding 12 of the Order summarizes the results of the baseline
risk assessment.  This section also discusses the assumptions
used in the exposure assessment.

No critical habitats or endangered species were identified for
the Intersil/Siemens site.  The potential for migration of
contaminants via surface runoff to Calabazas Creek is minimal.
Treated ground water from the on-site treatment units is
discharged to the creek as regulated by NPDES permit.  The
potential for future ecological impacts at this site is
determined to be low.

-------
VII.  SUMMARY OF ALTERNATIVES

In accordance with CERCLA Section 121, the National Contingency
Plan ("NCP"),  and the Interim Guidance on the Superfund Selection
of Remedy, December 24, 1986 (OSWER Directive 9355.0-10), a range
of soil and ground water remediation options for the
Intersil/Siemens site was developed and initially screened on the
basis of effectiveness, implementability and relative cost.
Next, a detailed analysis of the remaining alternatives in
relation to nine evaluation criteria was conducted.  Finding 14
of the Order identifies the nine evaluation criteria and Finding
13 provides a description of the proposed alternatives.

Although the Intersil and Siemens facilities are listed as one
site on the National Priorities List, each company completed its
own RI/FS and jointly completed an off-site RI/FS.  For this
reason, a separate series of alternatives was developed for the
Siemens on-site, Intersil on-site, and off-site areas.  The
alternatives for each and their associated costs are as follows:

     Siemens On-Site Alternatives
     1)  No action                                  $2,880,000
     2)  Ground water extraction/treatment
          (9 wells) and soil vapor extraction/
         treatment (15 wells)                        4,870,000
     3)  Ground water extraction/treatment
          (13 wells) and soil vapor extraction/
         treatment (15 wells)                        5,030,000
     4)  Same as #3 with soil excavation and
         disposal of approximately 40 cu. yds.
         of soil                                     5,660,000
     5)  Same as #4 with 7 additional soil
         vapor extraction wells                      6,360,000

     Intersil On-Site Alternatives
     1)  No action                                 $ 4,000,000
     2)  Existing ground water extraction/
         treatment (5 wells) and soil vapor
         extraction/treatment (4 wells)              9,800,000
     3)  Ground water extraction/treatment
          (7 wells) and soil vapor extraction/
         treatment (12 wells)                       10,100,000
     4)  Same as #3 with on-site reinjection
         of treated ground water                    10,700,000
     5)  Same as #2 with the addition of on-site
         ground water reinjection, soil excavation
         and on-site aeration, and a slurry wall    37,300,000
     6)  Same as #3 with more stringent ground
         water cleanup to VOC background levels     10,600,000

-------
     Off-Site Alternatives
     1)  No action          	             $1,220,000
     2)  Ground water extraction/treatment from
         one B-zone well                       '      2,120,000
     3)  Ground water extraction/treatment from
         three B-zone extraction wells with
         contingency for one C-zone well             2,990,000
     4)  Ground water extraction/treatment from
         two B-zone and one C-zone wells             2,650,000
     5)  Ground water extraction/treatment from
         two B-zone and two C-zon^wellisfs^fe'iw-, .    2,810,000
     6)  Same as #5 with more stringent ground
         water cleanup to VOC background levels      2,960,000

All of the alternatives, except the no action alternatives,
include continuing shallow zone and deeper aquifer ground water
and soil monitoring.  For all of the treatment alternatives,
except the no action alternatives, ground water is treated by air
stripping with subsequent discharge to Calabazas Creek under
NPDES permit.  Soil vapor treatment is by carbon adsorption.


VIII.  COMPARISON OF ALTERNATIVES

This portion of the ROD presents a comparison of the alternatives
using the nine evaluation criteria:  protection of human health
and the environment; compliance with applicable or relevant and
appropriate requirements ("ARARs"); long-term effectiveness and
permanence; reduction of toxicity, mobility or volume through
treatment; short-term effectiveness; implementability; cost;
support agency acceptance; and community acceptance.

Although the proposed alternatives for each of the three areas
are presented separately, they are comparable in that they
represent variations of similar basic treatment elements.
However, because the RI/FS reports were prepared separately, the
alternatives have been evaluated separately.  Table 2 (Siemens
on-site), Table 3 (Intersil on-site) and Table 4 (Off-site)
summarize the results of the detailed analysis of alternatives.


IX.  THE SELECTED REMEDY

In general terns, the selected remedy for the entire
Intersil/Siemens on-site and off-site areas consists of:

     o  Soil vapor extraction and treatment for soil cleanup
        (with soil excavation and disposal at the Siemens on-site
        area)

     o  Ground water extraction and treatment for ground water
        cleanup

-------
     o  Shallow zone and deeper aquifer ground water monitoring
        and soil monitoring

Specifically, the selected remedy for each area at the site is as
follows:

Siemens On-Site Area:  The selected remedy for the Siemens
on-site area is Alternative 4, which consists of expanded ground
water extraction and treatment, soil vapor extraction and
treatment, and soil excavation.  There will be a total of ten
A-zone and three B-zone ground water extraction wells.  There
will be a total of 15 soil vapor extraction wells.  The selected
remedy also includes excavation of approximately 40 cu. yds. of
contaminated soil to a depth of approximately 40 feet in the
areas of former tanks 1 and 3 to remove soils containing
semi-volatile organic compounds (SOCs).  The soil will be
disposed of in compliance with RCRA Land Disposal Restrictions
(LDRs).  The estimated time to achieve ground water cleanup is
45 - 85 years; the estimated time to achieve soil cleanup is
approximately 11 years.

Intersil On-Site Area:  The selected remedy for the Intersil
on-site area is Alternative 3, which consists of expanded ground
water extraction and treatment in the A- and B-Zone and expanded
soil vapor extraction and treatment.  There will be a total of
ten A-zone and one B-zone ground water extraction wells and eight
soil vapor extraction wells.  The estimated time to achieve
ground water cleanup is 60 years; the estimated time to achieve
soil cleanup is five years.

Off-site Area:  The selected remedy for the Intersil/Siemens
off-site area is Alternative 3, which consists of ground water
extraction from three B-zone extraction wells and treatment.
C-zone ground water will be captured by pumping of the B-zone
wells.  If C-zone VOC concentrations do not show a reduction
during the first one-year period and/or sufficient C-zone capture
is not demonstrated, a C-zone monitoring well will be converted
into a C-zone extraction well.  The estimated time to achieve
ground water clean up is 20 - 45 years.

For the three areas, ground water treatment will be accomplished
by air stripping with subsequent discharge to Calabazas Creek
under NPDES permit.  For the Siemens on-site area and the
off-site area, there may be partial reuse and reclamation of
treated water.  Soil vapor treatment will be accomplished through
carbon adsorption.  Regular ground water and soil vapor
monitoring will be conducted.

The selected remedy for each area is described in more detail in
Finding 15.1 - 15.3 of the Order.

The goal of this remedial action is to restore ground water to
its beneficial use.  Based on the information obtained during the
remedial investigation and on a careful analysis of all remedial

-------
alternatives, EPA and the State of California believe that the
selected remedy will achieve this goal.  It may become apparent,
during implementation or operation of the ground water extraction
system and its modifications, that contaminant levels have ceased
to decline and are remaining constant at levels higher than the
remediation goal over some portion of the contaminated plume.  In
such a case, the system performance standards and/or the remedy
may be reevaluated.

The performance of the ground water extraction and treatment
system will be carefully monitored on a regular basis and
adjusted as warranted by the performance data collected during
operation.  Modifications may include:

     a)  at individual wells where cleanup standards have been
         attained, pumping may be discontinued;
     b)  alternative pumping at wells to eliminate stagnation
         points;
     c)  pulse pumping to allow aquifer equilibration and to
         allow adsorbed contaminants to partition into ground
         water; and
     d)  installation of additional extraction wells to
         facilitate or accelerate cleanup of the contaminant
       "" plume.

ARARs

Chemical-, location-, and action-specific ARARs identified for
the Intersil/Siemens site include:

Federal:  Safe Drinking Water Act, Clean Air Act, RCRA  (Land
Disposal Restrictions), Clean Water Act

State:  Porter Cologne Water Quality Act, Safe Drinking Water
Act, Clean Air Act, California Hazardous Waste Control Law, State
Board Resolution 68-16, State Board Resolution 88-63 as
incorporated in the Water Quality Control Plan for San Francisco
Basin Plan

Local:  Bay Air Air Quality Management District (BAAQMD)
Regulation 8, Rule 47 ("Air Stripper and Soil Vapor Extraction
Operations") and BAAQMD Regulation 8, Rule 40  ("Aeration of
Contaminated Soil and Removal of Underground Storage Tanks")

TBCs for the Intersil/Siemens site include OSWER Directive
9355.0-28 ("Control of Air Emissions from Superfund Air Strippers
at Superfund Groundwater Sites").

Cleanup Standards

Findings 15.1 - 15.3 and 18 of the Order include a discussion of
cleanup standards for each area.  For each, ground water cleanup
standards are federal or state Maximum Contaminant Levels  (MCLs)
or California Department of Health Services (DHS) Recommended

-------
Drinking Water Action Levels (RDWALs).   Specification B.4 of the
Order presents ground water cleanup standards for all chemicals
of concern at the Intersil/Siemens site.

Promulgated MCLGs serve as the ground water cleanup standards for
those chemicals of concern with MCLGs greater than zero.  MCLGs
are the ground water cleanup standards for two chemicals of
concern at the Intersil/Siemens site:  1,1-dichloroethene
(1,1-DCE) and 1,1,1-trichloroethane (1,1,1-TCA).  In these two
instances, the California RDWAL or federal or state MCL that has
been chosen as the cleanup standard is either equivalent to or
more stringent than the federal MCLG.   A conservative remediation
standard of 1 ppm total VOCs and 10 ppm total SOCs has been set
for soil contamination.
STATUTORY DETERMINATIONS

In accordance with CERCLA Section 121, the selected remedial
action for each area at the Intersil/Siemens site is protective
of human health and the environment, complies with ARARs, is cost
effective, and utilizes permanent solutions and alternative
treatment technologies or resource recovery technologies to the
maximum extent possible.  In addition, the selected remedies
satisfy the statutory preference for remedies employing treatment
that reduces toxicity, mobility or volume as a principal element.

Under each area's chosen remedy, future risks at the site fall
within the 10~4 to 10~6 carcinogenic risk range and the
less-than-one Hazard Index for all exposure pathways.  On-site
soil will be remediated to a level that will protect on-site and
off-site ground water from further contamination by chemicals
presently in the soils.  The selected remedies comply with
federal and state ARARs.  Both soil vapor extraction and air
stripper emissions will meet the requirements of the BAAQMD
Regulation 8, Rule 47 and OSWER Directive 9355.0-28.
Implementation of the remedies will cause no unacceptable
short-term risks or cross-media impacts.

Treatment is used as a principal element for the selected
remedies.  Soil vapor extraction and treatment and ground water
extraction and treatment are permanent solutions and
significantly reduce contaminant toxicity, mobility and volume at
the site.  The selected remedial actions are the most
cost-effective.  Although the selected remedies' times to reach
cleanup are not the shortest, they do avoid short-term risks
associated with the shorter cleanup time alternatives.

Finding 16 of the Order provides an explanation of how the
selected remedies satisfy each of the statutory requirements.
Finding 19 of the Order specifically addresses how the selected
remedies protect the public health.

-------
Land Disposal Restrictions

CERCLA response actions must comply with RCRA Land Disposal
Restrictions (LDRs)  when they are determined to be ARARs.
Current EPA guidance directs that LDRs are not relevant and
appropriate for soil and debris wastes at this time.  In order
for RCRA LDRs to be applicable to soil and debris wastes, the
CERCLA response action must constitute placement of a restricted
RCRA hazardous waste.

The selected remedy for the Siemens on-site area soil includes
excavation of a total of approximately 40 cu. yds. of soil from
two separate locations, the sites of former tanks 1 and 3.  The
remedial investigation identified two SOCs at concentrations
greater than 10 ppm  (1,2,4-trichlprobenzene (1,2,4-TCB) and
phenol) at the two former tank locations.  Although soil vapor
extraction with treatment by carbon adsorption will be performed
at these two locations, SOCs are not readily amenable to
treatment by this method.  Soil vapor extraction is expected to
reduce concentrations to the soil VOC cleanup standard of l ppm,
but is not expected to reduce SOC concentrations to the soil SOC
cleanup standard of 10 ppm.

Neither 1,2,4-TCB nor phenol are listed or characteristic RCRA
hazardous wastes.  However, the soil that will be excavated and
disposed contains spent solvents (e.g., xylenes), which are
restricted RCRA hazardous wastes.  As such, they would be subject
to LDRs and would have to meet treatment standards  (effective
date November 8, 1990) before the soil could be excavated and
disposed of off-site.  (Metals in the soil were also determined
to be neither listed nor characteristic RCRA hazardous wastes).

The soil VOC cleanup standard of 1 ppm will reduce concentrations
well below required LDR treatment standards.  If these VOC
cleanup standards cannot be met, it will be necessary to obtain a
Soil and Debris Treatability Variance in order to comply with
LDRs.

-------
              TABLE   1

 SUMMARY OF POTENTIAL HEALTH RISKS
INTERSIL/SIEMENS, CUPERTINO, CALIFORNIA
POTENTIAL UPPERBOUND
HAZARD INDEX
EXCESS LIFETIME


SCENARIO
PRESENT-USE SCENARIOS
Ingestion of groundwater
Municipal Well No. 24
Inhalation of VOCs-
Municipal Well No. 24
Inhalation of chemicals volatilized
from on-site sofls - Siemens:
Intersil:
FUTURE-USE SCENARIOS
Direct contact with on-site soils
- children
Direct contact with on-site soils
- adults gardening
Ingestion of groundwater
- A-Zone
Inhalation of VOCs - A-Zone
groundwater
Ingestion of groundwater
- B-Zone
Inhalation of VOCs - B-Zone
groundwater
Ingestion of groundwater
- C-Zone
Inhalation of VOCs -
C-Zone groundwater
Ingestion of groundwater
- Deeper Zones
Inhalation of VOCs
- Deeper Zones
Inhalation of chemicals votatSzed
from on-site soils - Siemens:
Intersil:
CANCER
AVERAGE



--

-

2 x Iff"
1 x 10'"
-

3 x 10*

2 x Iff7

1 x ^a4

2 x 1CT*

8 x 10'5

9x Iff5

9x Iff5

2 x 10"*

4 x 10"*

7x Iff6

4 x Iff"
2 x Iff70
RISKS
PLAUSIBLE
MAXIMUM


-

-

1 x Iff70
7 x 1ff'°


4 x Iff5

8X 10*

4 X ID'2

8 X 10'2

1 x 10'3

1 X 10'3

3 x 10~*

6 x 10"*

1 x 10'5

3 x 10'5

2 x Iff10
9 x Iff70

AVERAGE PLAUSIBLE
MAXIMUM


<1 <1

<1 <1

<1 <1
<1 <1


<1 1

<1 <1

>1 >1

<1 1

1 >1

<1 <1

<1 <1

<1 <1

<1 <1

<1 <1

<1 <1
<1 <1

-------
                                                                                 TABLE  2
                                                                      ALTERNATIVES ANALYSIS SUMMARY
                                                                       OF RECOMMENDED ALTERNATIVES
                                                                                  LF 1218
Short- tens
Alternatives Effectiveness
Alternative 1 Mo increased
- No Action exposure risk;
w/ Monitoring potential risks
for future use
scenarios; very
long time to
reach goals
Long- tens Reduction of
Effectiveness Toxicity. Mobility
and Permanence and Voluse Implemei
Mo Migration of VOCs are diluted, sorbed Implemeni
adverse environmental and degraded over time
effects; possible decreasing toxicity, but
Migration of chemicals voluse and affected area
to drinking water- are Increased
aquifers

Overall Protection
Coapl lance with of Human Health and
liability Cost (dollars)* ARARs ft TBCs the Environment
table Capital: Wouldn't achieve goals VOCs exceeding goals
0 for very long time, remain In potential
Annual OM: If ever drinking water source
152.160
Present Worth:
2,880,000

Alternative 2            No Increased      Thenasl regeneration
- Contain VOC Migration  exposure risk     of VES carbon offers
  Extract ft Treat Ground fras VES; ailnlMl permanent VOC
  Water

  Phased Soil Vapor
  Removal
risks fro*
stripper
CMlssions.  VES
ft ground water
extraction reduce
tie* to reach
remedial goals
over Alt. 1
                                           destruction
VOCs are diluted, sorbed Implementable.    Capital:       Would achieve goals    Protective;  treated
and degraded over tl«e   subject to permitt       365,873 sooner than Alt.  1;    effluent  disposal  to
decreasing toxlcity;                       Annual DIM:    would not address      Calabazas Creek will
chemical input to ground                          258,205 non-volatile chemicals not deplete  ground
water fro» soils reduced;                  Present Worth:                        water due to
ground water Migration                          4,870,000                        recharge; residual
controled; carbon            .                                                    risks extremely low
regeneration reduces
voluae of VOCs
Alternative 3            Sams as Alt. 2;
- Contain VOC Migration  Ves ft ground
- Accelerate VOC Reaoval water extraction
  Extract ft Treat Ground reduce tie* to
  Water                  reach remedial
                         goals over Alts.
- Phased Soil Vapor      1 t 2
  Removal
                  Thenasl regeneration
                  VES carbon offers
                  permanent VOC
                  destruction
Same as Alt. 2
Implementable,    Capital:       Would achieve goals    Protective; treated
subject to per*,lt>       431,955 sooner than Alt.  2;    effluent disposal to
                  Annual OM:     would not address      Calabazas Creek will
                         264,325 non-volatile chemicals not  deplete ground
                  Present Worth:                        water due to
                       5,030,000       .                 recharge; residual
                                                        risk extremely low
onasses.ukq
                                                           Page 1
                                                                                                                                                                   15-Jun-90

-------
                                                                      ALTERNATIVES ANALYSIS SUMMARY
                                                                       OF RECOMMENDED ALTERNATIVES
                                                                                  LF 1218
Alternatives
Short-term
Effectiveness
Long-term
Effectiveness
and Permanence
Reduction of
Toxic Ity. Mobility
and Volume
Implement ability Cost (dollars)*
Compliance with
ARARs ft TBCs
Overall Protection
of Human Health and
the Environment
Alternative 4
- Soil Excavation
  Areas 1 ft 3
                  as Alt. 3; less
             residual seal-vola-
             tile* than Alts. 1.
             2. ft 3; soil Incinera-
             tion permanently
                         Excavation poses
                         greatest human
                         expoaura risk;
                         no increseed
- Contain VOC Migration  exposure risk
- Accelerate VOC Removal fro* VES; minimal destroys VOC* ft sesil
  Extract ft Treat Ground risks fro* air    volatile*
  Water                  stripper emissions

- Phased Soil Vapor
  Removal
     as Alt. 2; soil
incineration reduces
volume of chemicals
Not easy to Impta-Capltal:       Would achieve goals
went; safety             852,67* sooner than Alt. 2;
concerns; space   Annual OtN:    Mould remove seml-
lImitations; nould       270.554 volatlles from sits
disrupt business  Present Worth:
                       5.660,000
Will achieve remedial
goala for site. Mould
Increase health risk
through short-term
exposure during
construction;
residual risk
extremely tow
Alternative 5
- Soil Excavation
  Areas 1 ft 3

- Contain VOC Migration
- Accelerate VOC Removal
  Extract ft Treat Ground
  Water
as Alt. 4
                                                   Alt. 4
     as Alt. 2; soil
Incineration reduces
voluM of chemical a
Same as Alt. 4.   Capital:       Would achieve goala
even more dlsrup-        966,648 sooner than Alt. 2;
tion to facility  Annual OftM:    Mould remove seml-
                         306.633 volatiles from site
                  Present Worth:
                       6.360.000
Will achieve remedial
goala for site. Mould
increase health risk
through short-term
exposure during
construction;
residual risk
extremely low
  Phased Soil Vapor
  Removal
onasses.u
                                                                                                                                                                    15-Jun-90

-------
                                                                      ALTERNATIVES ANALYSIS  SUMMARY
                                                                       OF RECOMMENDED  ALTERNATIVES
                                                                                  LF  1218
mmmmmmmmmmmmmm
Alternat
•«••••
Ives
!•••••••••••••••••••••••«
Short -tens
Effectiveness
Long- tens
Effectiveness
and Penaanence
Reduction of
Toxlcity, Mobility
and Voluae
Compliance with
iMpleacntablllty Cost (dollars)* ARARs ft TBCs
Overall Protection
of Hum Health and
the Environment
Alternative 6            SaM as Alt. 4;   toll Incarceration ft
- Soil Excavation        also will take a  thenaal VE8 carbon
  Areaa IAS            very long tla» to regeneration offers
                         reach "background paraanent cheaical
- Contain VOC Migration  levels" In ground destruction; less
- Accelerate VOC Reaoval water             residual seat-volatlies
  Extract t Treat Ground                   than Alts. 1. 2.  13;
  Water                                    less residual VOCs In
                                           ground Meter than all
- Phased Soil Vapor                        other alternatives
  •eauval
     as Alt. 2; soil
Incineration reduces
volume of cheaicals
     as Alt. 4;   Capital:       It would take a very   Protective;  less
also lapleaenta-         852,674 long tla* to reach      residual risk than
bit I ty for the    Annual OM:    "background levels"     other Alternatives
estimated 450 year       270,534
project life Is   Present Worth:                                    '
uncertain              5.660,000

                  Overall project
                  costs Mould be
                  •uch higher due
                  to long-tens
                  ground-Mater
                  extraction
                                                              m*nmmmmmmmmmmmmmmm
Notes:  1)  Evaluation of support agency and CoMunlty acceptance Mill be Included after appropriate rev leu process.
        2)  Costs are divided Into capital coats for lapleaientatlon of aystea*,  first year annual  operation and ealntenence
            costs, and a 10-year present worth cost.  The 1-year period Mas chosen as representative;  for  other tie* periods
            ranging fro* 1 to 30 years,  see detailed alternative present worth tables.
masses, wkq
                  Page 3
                                                                                                                                                                   15-Jun-90

-------
          TABLE 3
COMPARISON OF ALTERNATIVES
Alternative
1
No Action

II
Existing
Remedial
Action



IU
Expanded
Remedial
Action
IV
Expanded
Remedial
•Action
with
Reinfection

y
Minimal
Long-Term
Management
VI
VI
Exceeds
^ARARs
Protection Of
Human Health
and Environment

Not protective
/
>
Protective




Protective
Protective


Protective

Protective
Compliance
with ARARs
/N.
//n
/ / /
>^ ^s s
^^i»8^
i
<(


Yes
Yes


Yes

Exceeds
ARARs
Long-term
Effectiveness

Not effective
..
/ ^«.
^Bf£live\
/N?\fc-<' )
) \
J )
(/
Effecliv*^
Effective


Effective

Effective
Reduction Of
ToxicHy, Mobility
or volume
No reduction of
T.M.orV


Reduction of T, M.
andV


^s\^
jTsj /
Reduc/ion of T, M,
Increase in M,
reduction in T,
potential increase
inV


Increase in M,
reduction ol T
andV

Reduction of T,
M.andV
Short-term
Effectiveness

Not effective
Minimal impact
during
implementation
and operation,
longest time to
achieve ARARs
Some impact
during
implementation,
minimal impact
/during operation,
less time to
/achieve ARARs
V|han Alternative II
s. Some impact
x^ during \v\
implementation*
potential impact
during operation,/
potentially less'
time to achieve
ARARs than
Alternative III
Major impacts
during
implementation,
shortest time to
achieve ARARs

Requires longest
time to complete
Implementablllty

Implementable


Implemented




Implementable
sLess implementable
than Alternative III
"because of technical
and administrative
feasibility of
reinjection wells


Most difficult to
implement
May be technically
inleasible to achieve
background
concentrations
Cost
(Net present
value)

$4.0 million


$9.8 million




$10.1 million
$10.7 million


$37 million
-
Over
$10.7 million

-------
                                                                             TABLE  4
                                                                   ALTERNATIVES EVALUATION SUMMARY
                                                                               LF 158*
Alternative*
Alternative 1
-No Action
w/ Monitoring
Short-term
Effectiveness
Time to reach remedial
goal la very long;
does not satisfy RAO
of environmental
protection
••••••••••••••••••••••••••i
Long-term
Effectiveness
and Permanence
No mitigation of
adverse environmental
effect*
Reduction of
Toxicity. Mobility
and Volume Implemented I Ity
VOC* are diluted, sorbed Implementable
and degraded over time
decreasing toxicity. but
volume is Increased
Cost (dollar*)'
Capital: 0
Annual OlM:
79.160
Present Worth:
1. 216.883
Compliance with
' ARARs t TBCS
Would not achieve
remedial goals
for a long time
Overall Protection
of Human Health and
the Environment
Doe* not address
loss' of potential
resource, nor
potential exposures
from use of shallow
ground water
Alternative 2.1.A
-Extract fro*
 well LO-2B
-Air Stripping
 Treatment
-Discharge Treated
 Effluent to
 Calabazas Creek
No increased expoaure
risk; time to reach
goal* less than for
Alt. 1; air •tripping
effective for Indicator
chemical*
                                           VOCa removed fro*
                                           subsurface
VOC concentration in
ground water decreased
by extraction; mobility
reduced by new gradient
Treatment lowers toxi-
city and volume of VOC-
effected ground water
                                                                                          Implementable:
                                                                                          permits required for
                                                                                          extraction system
                                                                                          construction, air
                                                                                          emissions and NPDES
                                                                                          discharge
Capital:       Remedial goals         Will  probably achieve
       281,463 will be achieved by    remedial  goals,
Annual OlM:    extraction system;      protect humamvu*>
       133,960 BAAQMD and NPOES regs  health t  environment
Present Worth: limit VOC emissions and
     2.116,354 discharge
Alternative 2.2.A
-Extract fro*
 well LO-2B
-Air Stripping/
 GAC Treatment
-Discharge Treated
 Effluent to
 Calabaia* Creek
                    No Increased exposure
                    risk; time to reach
                    goal* le*a than for
                    Alt. 1; air stripping
                    effective for site
                    VOC*; GAC breakthrough
                    t spent GAC handling
                    require proper oper-
                    ation and haz. waste
                    management
                                           VOC* removed from
                                           aubeurfac*
                                             Same a* above; VOCa
                                             permanently destroyed
                                             In GAC regeneration
                                             process
                         Implementable;
                         permits required for
                         extraction' system
                         construction, air
                         emissions and NPOES
                         discharge
Capital:       Remedial  goals
       386.981 will be achieved by
Annual OlM:    extraction system
       138.852 BAAQMD i NPOES~reg*
Present Worth: limit VOC emissions t
     2.297,104 discharge; ARARs apply to
               spent carbon disposal
                                                                                                                                   Same as above
Alternative 2.3.A
-Extract from well
 LQ-2B
-UV/OX Treatment
-Discharge Treated
 Effluent to
 Calabazas Creek
                    No Increased exposure
                    risk If proper opera-
                    tion*; time to reach
                    goal* less than for
                    Alternative 1
                       VOC* removed from
                       subsurface
               VOCs
premanently destroyed
In UV/OX process
                                                                                          Impl ementable;permi t
                                                                                          required for extrac-
                                                                                          tion system construc-
                                                                                          tion, air emissions
                                                                                          and NPDES discharge;
                                                                                          treatment process
                                                                                          pilot testing required
Capital:       Remedial goals         Same as above
       658.835 will be achieved by
Annual OlM:    extraction system
       162.141 BAAQMD I NPDES regs
Present Worth: limit VOC emissions t
     2,927.027 discharge; ARARs apply to
               spent carbon disposal
Alternative 3.1.A
-Extract from
 wells LQ-1B,
 Id 29. S-2B
-Air Stripping
 Treatment
-Discharge Treated
 Effluent to
 Calabazas Creek
                    No Increased exposure
                    risk; time to reach
                    goal* less than for
                    Alts. 1 t 2; air
                    stripping effective
                    for site VOCs; less
                    B- to C-zone migration
                    than Alts. 1 I 2; C-zone
                    capture
                       VOC* removed from
                       subsurface
VOC concentration In
ground water decreased
by extraction; mobility
reduced over Alts 1 t 2;
Treatment lowers toxi-
city and volume of VOC-
affeeted ground water
                                                                                          Implementable;
                                                                                          permits required for
                                                                                          extraction system
                                                                                          construction, air
                                                                                          emissions and NPDES
                                                                                          discharge
Capital:       Remedial goals         Same as above
       459,291 will be achieved by
Annual OtM:    extraction system
       160,588 BAAQMD t NPDES regs
Present Worth: limit VOC emissions t
     2.993,823 discharge; ARARs apply to
               spent carbon disposal
1584/OFrSUM.wkq/T4-1
                                                                                   Page 1
                                                                                                                                                                  18-Jun 90

-------
                                                                              TABLE 4
                                                                   ALTERNATIVES EVALUATION SUMMARY
                                                                               Lf 1584
••1
Alternative*
Short -tens
Effectiveness
Long- tern
Effectiveness
end PenMnence
Reduction of
Toxlclty. Nobility
and VoluM
laplea
entebillty
Cost (dollars)*
Compliance with
ARARs ft TBCs
Overall Protection
of Hunan Health and
the Environment
Alternative 3.2.A
•Extract fro»
 wells LO-2B.
 LO-li. S-2B
-Air Strlpplng/GAC
 Treataent
-Discharge Treated
 Effluent to
 Caiabaias Creek
No Increased exposure
risk; tie* to reach
goals less than for
Alt. 1; air stripping
effective for site
VOCs; GAC breakthrough
ft spent GAC handling
require proper oper-
ation and hazardous
waste aanageaent; less
I- to C- tone Migration
than Alts. 1 ft 2;
C-tone capture
VOCs removed froa
subsurface
     as above; VOCs
permanently destroyed
In GAC regeneration
process
lapleaentable;
penslts required for
extraction systea
construction, air
eaiisslons and NPOES
discharge
Capital:       Reaadlal goals         Saaa aa above
       721,940 will be achieved by
Annual OIM:    extraction systea
       201,082 BAAQMD ft WOES regs
Present Worth: limit VOC eaisslons ft
     3,571,554 discharge; ARARa apply to
               spent carbon disposal
Alternative 3.3.A
-Extract from
wells LO-li,
10-28, S-2B
-UV/OK Treataent
-Discharge Treated
Effluent to
Calabazas Creek
No Increased exposure VOCs riao»sd froa
risk If proper opera* subsurface
tion; tiae to reach
goals less than for
Alt. 1;less 8- to C-
zone leakage than
Alta. 1 ft 2; C-zone
capture
Saae as above; VOCs
permanently destroyed
In UV/OX process
lapleaentable; peralts
required for extrac-
tion systea construc-
tion, air ealssions
and NPDES discharge;
treatment process
pilot testing required
Capital:
1,174.849
Annual OIM:
244.335
Present Worth:
4.689,430
Reaedial goals Ssae
will be achieved by
extraction systea
BAAOND ft NPDES regs
Halt VOC emissions ft
discharge; ARARs apply to
spent carbon disposal
as above
Alternative 4.1.A   No increased exposure
-Extract froa Nells risk; tiae to reach
 LQ-2B. S-2B, RK-2C goals less than for
-Air Stripping      Alts. 1. and 2; air
 Treataent          atripping effective
-Discharge Treated  for site VOCs
 Effluent to
 Calabazas Creek
                       VOCs reaoved froa
                       subsurface
                      Voluat ft Nobility
                      decreased over Alts
                      1. 2 ft 3;
                      Treetaent lowers toxl-
                      clty and voluM of VOC-
                      affected ground water;
lapleaentable; peralts
required for extrac-
tion systea construc-
tion, air eaisslons
and NPDES discharge;
•ore trenching in
City streets than
Alts. 1, 2 ft 3
                                                Capital:       Reaedial  goals
                                                       463,356 will  be achieved by
                                                Annual OM:    extraction systea
                                                       157,289 gAAQND ft  NPOES regs
                                                Present Worth: liait VOC eaisslons ft
                                                     2,647.078 discharge; ARARa apply
                                                               to spent  carbon
                                                               disposal
                                      Will  achieve reaediel
                                      goals,  protect  hunn
                                      health  ft environment;
                                      Tiae  to reach goals
                                      will  be less than
                                      for Alts 1  ft 2
Alternative 4.2.A   Seas as above;
-Extract froa wells GAC breakthrough
 IQ-2B.S-2B. RK-2C  ft spent GAC handling
-Air Stripping/GAC  require proper oper-
 Treataent          •tion and hazardous
-Discharge Treated  Maste i
 Effluent to
 Calabazas Creek
                       VOCs reaoved froa
                       subsurface
                           as above; VOCs
                      permanently destroyed
                      in GAC regeneration
                      process;
Saae as above          Capital:       Reaedial goals
                              662.922 will be achieved by
                       Annual OIM:    extraction systea
                              170,918 BAAOMD regs liait VOC
                       Present Worth: ealssions; ARARs apply
                            3,056,191 to spent carbon
                                      disposal
                                                                                      Saae as  above
1584/Or      ikq/U-1
                                                                                                                                                                  18-Jun-W

-------
                                                                              TABLE 4
                                                                   ALTERNATIVES EVALUATION
                                                                               LF 1584
                                                                                           SUMMARY
    Alternative*
                          Short-tens
                         Effectiveness
      Long-term
    Effectiveness
    end PenMnence
      Reduction of
   Toxlclty. Nobility
       •nd Volume
                                                  lapleaentebllity    Cost (dollar*)*
                  Compliance ulth
                    ARARs t liCs
Overall Protection
of Huamn Health and
the Environment
Alternative 4.3.A   No Increased exposure
-Extract.fro» Malls risk if proper opera*
 LQ-2B.S-2B, RK-2C  tlon; time to reach
-UV/OX Treatment    goals less than for
-Discharge Treated  Alts. 1 and 2
 Effluent to
 Calabazas Creek
VOCs removed froa     Same as above; VOCs
subsurface; VOCs      permanently destroyed
permanently destroyed In UV/OX process
In UV/OX process
                                                                                          Same as  above;
                                                                                          treatment process
                                                                                          pilot testing
                                                                                          required
                                                                      Capital:       Remedial goals
                                                                           1.046,123 will be achieved by
                                                                      Annual OM:    extraction systeai;
                                                                            205.307 BAAQMD regs  llailt
                                                                      Present Worth: VOC eatssions
                                                                           3,969.325
                                                                                      Seme as above
Alternative 5.1.A
-Extract fro* four
 •- ft C-sone nails
-Air Stripping
 Treatment
-Discharge Treated
 Effluent to
 CaIabates Creek
                    No Increased exposure
                    risk; tia* to reach
                    goals less than for
                    Alts. 1.2 ft 3; air
                    stripping effective
                    for site VOCs
VOCs reamed tram
subsurface
VOC cone, ft •ability
decreased over Alts
1. 2. 3 i 4;
Treatment loners toxl-
clty and voluae of VOC-
affected ground water;
                                               Implementabte; penilts Capital:
                                               required for extrac-
                                               tion systsai construc-
                                               tion, sir Missions
                                               and WOES discharge;
                                               •ore trenching in
                                               City streets than
                                               Alts. 1, 2. t 3
                    ial goals
       508.248 Hill be achieved by
Annual OM:    extraction system;
       165,063 BAAQND regs Halt
Present Worth: VOC esitssions
     2,811,476
Will achieve remedial
goals, protect humsn
health t environment;
Time to reach goals
Mill-be less than
for Alts 1.2(3
Alternative 5.2.A
-Extract frosi four
 •- ft C-tona Mails
-Air Strlpping/GAC
 Treatment
-Discharge Treated
 Effluent to
 Calabaias Creek
                                           VOCs removed fro*
                    GAC breakthrough
                    ft spent GAC handling
                    require proper oper-
                    ation and haiardous
                    Masts
                           as above; VOCs
                      permanently destroyed
                      In GAC regeneration
                      process;
                                                Capital:       Remedial  goals
                                                       730,754 Mill  be achieved by
                                                Annual OM:    extraction system
                                                       181,189 BAAQND regs Halt VOC
                                                Present Worth: emitsIons; ARARs apply
                                                     3.281,904 to spent  carbon
                                                               disposal
Alternative 5.3.A   No Increased exposure
-Extract froa four  risk If proper opera-
 B- t C-ione Mails  tlon; tlas to reach
-UV/OX Treatment    ARARS less than for
-Discharge Treated  Alts. 1, 2. 3 t 4
 Effluent to
 Calabazas Creek
                                           VOCs removed from
                                           subsurface
                                     VOCs
                      permanently destroyed
                      in UV/OX process
                         Seas es above;
                         treatment process
                         pilot testing
                         required
                                                                      Capital:       Reaedlal goals
                                                                           1.155.250 Mill be achieved by
                                                                      Annual  OM:    extraction system;
                                                                             218.852 BAAOND regs  Halt
                                                                      Present Worth: VOC emissions
                                                                           4,285.437
                                                                                                           Seas as above
1584/OFFSUH.Mkq/T4-1
                                                                                   Page 3
                                                                                                                                                                  18-Jun-90

-------
                                                                             TABLE *
                                                                  ALTERNATIVES EVALUATION SUMMARY
                                                                              LF  1584
    Alternatives
           Short-term
          Effectiveness
                                                 long-term
                                               Effectiveness
                                                   Reduction of
                                                ToxicIty.  Nobility
                                                    and VoluM
                                                                                             Implemented 11 ty   Cost  (dollar*)*
                                                                                                               Compliance with
                                                                                                                 ARARe t TIC*
                                                             Overall Protection
                                                             of  Human  Health and
                                                             the Environment
Alternative 6.1.A
-Extract from wells
 LO-2S, S-28, RK-2C
-Air Stripping
 Treatment
-Discharge Treated
 Effluent to
 Catabazas Creek
No Increased exposure)  VOCa famovirt from
riak; air stripping    subsurface; leaa
affective for aita
VOCa; Mill take a
vary long time to
reach "background
levels"
                                           residuals In aub-
                                           aurface than other
                                           Alternative*
                                                  VOC cone,  i Mobility
                                                  decreaaed over Alta
                                                  1.  2,  3 I 4;
                                                  Treatment  lower* toxi-
                                                  clty and voluao of  VOC-
                                                  affeeted ground water;
Technically
leplementeble; permits
required for extrac-
tion system construc-
tion, air emissions
and NPOES discharge;
more trenching In
City streets than
Alta. 1. 2, i 3;
long-term Impie-
mentabillty la un-
certain
Capital:       Remedial goala
       463,356 Mill be achieved by
Annual OM:    extraction system;
       157.289 8AAOND rega limit
Present Worth: VOC emissions
     2,959.686
Overall project
coata Mould be
much higher due
to long-term
ground-water
extraction
                                                                                                                                  Ulll achieve remedial
                                                                                                                                  goala, protect huaan
                                                                                                                                  health I environment
Alternative 6.2.A
-Extract from walla
 LQ-28. S-28, RK-2C
-Air Strlpptng/GAC
 Treatment
-Discharge Treeted
 Effluent to
 Calabazaa Creek
GAC breakthrough
I spent GAC handling
require proper oper-
ation and hazardous
waste management; Mill
take • vary long time to
reach "background
levele"
                                                                 Same aa above;  VOCa
                                                                 permanently destroyed
                                                                 In GAC regeneration
                                                                 process;
                                                                                                  Capital:       Remedial goala
                                                                                                         558,553 Mill be achieved by
                                                                                                  Annual  OM:    extraction system
                                                                                                         170.918 BAAQMD rega  limit VOC
                                                                                                  Present Worth: emissions; ARARs apply
                                                                                                       3.264,431 to apent carbon
                                                                                                  Overall projactdlapoaal
                                                                                                  costs would  be
                                                                                                  much higher  due
                                                                                                  to long-term
                                                                                                  ground-water
                                                                                                  extraction
                                                                                                                                  Saae aa above
Alternative 6.3.A   No Increased exposure  VOCa removed from     Same aa above;  VOCa
-Extract from Malta rlak If proper opera-  subsurface; VOCa      permanently destroyed
 IQ-28. S-2R, RK-2C tlon; Mill take a      permanently destroyed In UV/OX process
-UV/OX Treatment    very long time to      In UV/OX process; leas
-Dlacharge Treated  reach "background      residuals In sub-
 Effluent to        levels"                surface than other
 Calabazaa Creek                           Alternatives
                                                                           treatment process
                                                                           pilot testing
                                                                           required
                                                                                             Capital:       Remedial goala
                                                                                                  1.046,123 Mill be achieved by
                                                                                             Annual  OM:    extraction system;
                                                                                                    205.387 BAAOMD regs  limit
                                                                                             Present Worth: VOC emissions
                                                                                                  4.281.933
                                                                                             Overall project
                                                                                             coets Mould  be
                                                                                             auch higher  due
                                                                                             to long-term
                                                                                             ground-water
                                                                                             extraction
                                                                                                                                            aa above
NOTES:
Evaluation of State and comaunity acceptance Milt be Included efter appropriate review process.

Costs are divided into implementation, capital coats, first year annual  operation and maintenance  costs, and a
30-year present worth cost.  Overall project cost depends upon the time  required to reach remedial goals (Table 4-2).

Costs do not include legal, land use or closure/abandonment costs.
1584/OFrT
I/T4-1
                                                                                                                                                                   8-JUT 90

-------
                           REVISED RESPONSIVENESS SUMMARY
                         for Comments and Questions Received During
                                   June 13 - August 6, 1990
                                           on the
                                 Final Remedial Action Plan
                                           for the
                           Intersil / Siemens Proposed Superfund Site
                                Cupertino, Santa Clara County
Introduction
This revised responsiveness summary reviews comments and questions received through August 6,
1990 regarding the proposed remedial action plan (RAP) for the Intersil / Siemens proposed
Superfund site.  The RAP consists of expanded soil vapor extraction and treatment expanded
groundwater extraction and treatment, and limited soil excavation.  The RAP is formally presented in
the Remedial Investigation / Feasibility Study (RI/FS) reports, the proposed plan fact sheet (dated
June 1990) and the proposed final Site Cleanup Order (SCO) for the site.  The public comment
period on the RI/FS, the proposed plan fact sheet and the SCO was from June 13, 1990 to July 13,
1990.  The Board held a public hearing on the RAP and SCO during its June 20, 1990 meeting.
Intersil and Siemens have commented in writing twice on the SCO. AMI, the Department of Health
Services:  Office of Drinking Water (ODW), the City of Santa Clara and the Santa Clara  Valley Water
District (SCVWD) also commented on the SCO.  One nearby homeowner asked similar questions
covered in the public meetings, the letter and response letter are attached. One nearby homeowner
submitted a  letter (attached) suggesting that Intersil and Siemens should post a bond large enough to
cover the costs of cleanup. This is discussed in the Regulatory Oversight section.  No other written
comments were received during the comment period, nor was there any requests for a time
extension. Four letters of comment and/or question were received after the close of the period. The
four letters of comments include further explanation by ODW oh their earlier comments; letters with
similar comments as ODW's from the City of Santa Clara and  the SCVWD;  and a response from
Intersil to the July 11 ODW comments.  All comments, including the last four letters of comment are
responded to in this Revised Responsiveness Summary.

During the community meeting that took place in  Santa Clara  on June 21, 1990, community members
orally asked  numerous questions regarding the site history and effects as well as details on the RI/FS
and RAP. The audience had two significant comments/questions on the RAP concerning (1) the
length of time to achieve cleanup of 45 to 85 years was too long and that methods to shorten the
time to cleanup should be  reevaluated, and (2) who was going to provide regulatory oversight for
tine lengthy cleanup.

The summary of the significant comments and response to those comments are summarized below.
A recent  EPA memo established a two part approach to responsiveness summaries.  This document is
presented in one part  because Regional Board staff believe at this time  that  tine issues and responses
are succinct  enough that a two part approach is not warranted.

The Administrative Record for the site is available at the Sunnyvale Public Library and at the
Regional  Board Offices.

Community Relations Activities
The major community relations activities are listed below:
July 1989             Fact Sheet No. 1
September 1989       Community Meeting No. 1
January 1990         Fact Sheet No. 2, Answers  to Questions from Public
June 1990            Fact Sheet No. 3, Community Meeting No. 2
*<«<•<«. mo
Page 1 of 5

-------
 Local Community Comments

 Significant Issues and Concerns:

 General:
 Numerous questions were asked during the community meeting regarding the site history, site
 investigation, extent of soil and groundwater pollution, baseline public health evaluation,
 performance of interim remedial actions and the proposed RAP. These questions were all answered
 at the community meeting, in Fact Sheet No. 2, Answers to Questions from Public, and in the
 proposed plan Fact Sheet No. 3. A survey of the people attending the June 21, 1990 community
 meeting showed that only three people in attendance had also attended the September 1989
 community meeting.  Most of the questions asked during the June community meeting were similar
 to questions asked during the September community meeting.   Answers to these questions were
 provided at the June  community meeting and were documented in Fact Sheet No. 2.  One letter was
 received from a nearby homeowner with questions similar to those at the community meeting
 regarding the site investigation  and cleanup and these questions were answered by letter.  This
 comment letter and staff response letter back are included as an attachment

 Time to Achieve Cleanup Levels:

 The most significant question /  concern that arose during die public meeting was why does it take
 so long to achieve cleanup and is there any additional work that could be done to shorten the time
 necessary for cleanup.

 The time to achieve cleanup levels for the proposed alternatives is presented in the following table.

                           Time to Achieve Geanup Levels (Years)

                     Siemens On-Site       Intersil On-Site         Off-Site

 Soil                         11                  5                       N/A

 Groundwater                45-85                60                      20-45


 Soil cleanup times are relatively short when compared to groundwater cleanup times.  Volatile
 organic compounds (VOCs) such as trichloroethene (TCE), the  main chemical of concern at the sites,
 are extracted much quicker when they exist in soil in a vapor state rather than when the VOCs  are
dissolved in groundwater. When VOCs are dissolved in groundwater, the VOCs adsorb or attach to
the soil particles where the groundwater is present and become trapped inside openings or crevices
on the soil particles, and it becomes very difficult to remove the adsorbed VOCs.  As groundwater is
pumped from a contaminated aquifer, VOCs slowly desorb or detach from the soil particles and are
extracted with the groundwater. Within limits this process may be speeded  up by pumping at a
higher flow rate, however, due  to the limiting factors of desorption, a point of decreasing VOC
removal will be reached so that any additional pumping rate increases will  not shorten the cleanup
time.

On-Site Areas
The shallowest groundwater zone beneath Intersil and Siemens, the A-zone,  has a very low
permeability (ability to transmit  water)  so that the A-zone will dewater or dry up if exposed to high
groundwater pumping rates. For this reason, the cleanup time from the A-zone groundwater is
limited by the amount of water that may be pumped from the A-zone.  Modeling has shown that if
the A-zone is pumped at any greater rate than is currently proposed 2.7 gallons per minute (gpm) at

                                        Page 2 of 5

-------
Intersil and 7 gpm at Siemens, it will dewater and groundwater extraction will no longer be effective
except for the ongoing soil vapor extraction.

Intersil's on-site alternative No. 4 considered reinjection of groundwater at the site to increase  the
pumping rate from 2.7 gpm to 3.3  gpm.  This decreased the cleanup time from 60 years to 45  years.
However,  this alternative was not selected due to  the difficulties in  controlling the reinjected water
and concerns that the reinjection could spread tine contamination.  Intersil's on-site alternative  No. 5
increased the rate of reinjection so that the groundwater pumping rate could be increased from 3.3
gpm to 73 gpm.  This increased flow rate decreased the cleanup time from 45 years to 20 years.
This alternative was also not selected due to the difficulties with reinjection.

Off-Site Area
For the off-site area proposed cleanup alternative No. 3, the B-zone groundwater is currently
proposed to be pumped  at 105 gpm.  The B-zone  is able to be pumped at a much higher rate than
the A-zone due to the greater permeability and  size of the B-zone.  The B-zone is proposed to be
pumped at this relatively high rate in order to capture and cleanup C-zone groundwater also. Off-
site alternative No. 4, which was not recommended, proposed to pump the B-zone at 45 gpm.  By
increasing the pumping  rate in the B-zone from 45 gpm  to 105 gpm, the cleanup time in  the B-zone
decreases from a range of 20 - 50 years to a range of 20 - 45 years.  By doubling the pumping rate
in the B-zone, only 5 years is reduced from the upper range  of predicted cleanup times.   This is
again due to the difficulty in extracting the VOCs from the clay soils.  Soil gas extraction is not
feasible off-site.

Groundwater conservation is also considered in  selecting the  proposed RAP. The relatively high
pumping rate in the B-zone has to be balanced  against groundwater conservation and the concern of
limiting withdrawals from the groundwater resources during  drought periods.

In conclusion, the Regional Board staff believe the proposed alternatives combine the best of
effectiveness, implementability, groundwater conservation, and time  to cleanup.  Progress reviews will
be completed to review progress and achievability and will consider changes available that can speed
cleanup.

Regulatory Oversight  Adoption of the SCO requires periodic reporting by Intersil and Siemens  on
their activities to achieve cleanup.  These reports are public record and will also be sent to the Cities
of Santa Clara, Cupertino, and Sunnyvale.  Additionally, until the site is cleaned up to the
requirements of the  SCO, the  Regional Board and/or EPA will provide regulatory oversight
Superfund requires a formal review of the progress every 5 years until cleanup.  If the Regional
Board is still the lead agency this review will be noticed at least by publication and distribution of
the agenda for the meeting where  the Board reviews the cleanup progress, where the status report
and recommendations can be obtained for review, and how the  public can comment on any
proposed Board actions in writing  or at a public hearing. If  the Board amends the cleanup
requirements, this would also be done with public notice at a public hearing.  It is expected that
EPA, if they are die lead regulatory agency, would offer the  public the same opportunities during
reviews and/or changes.

One comment letter suggested the  companies should post a bond large enough to cover die cost  of
cleanup.  The Board has not made this a practice  in the past, instead relying on its enforcement
authority to require  completion of cleanups.  Intersil and Siemens have completed all necessary
cleanup work required up until this time and there is no reason to believe they will  not continue to
do so.  Intersil and Siemens are part of two of the biggest companies in the world and have given
all appearances that they are dedicated to completing the cleanup.
                                         Page 3 of 5

-------
Intersil / Siemens Comments

Intersil and Siemens have commented twice on the SCO. The comments are mainly wording
changes to the SCO for clarification that do not change the intent of the SCO.  Most of their
comments have been incorporated into the SCO and the companies do not plan to contest the SCO.

AMI Comments

AMI stated that one finding in the SCO that referenced the AMI off-site groundwater plume was
unwarranted based on the available data.  Staff believe  the available data is adequate to make the
finding and this finding was not changed.

ODW, SCVWD and City of Santa Clara Comments

The ODW does not agree with the EPA Superfund final cleanup level  risk range for carcinogens of
10* to 10*.  They also do not agree with the use of MCLs as cleanup levels when more than one
chemical  is present at a site.  ODW recommends the use of a carcinogenic hazard index (CHI) of
one or a  10* carcinogenic risk level as cleanup levels whenever this level of protection can be
accomplished with reasonable and cost effective operational measures.  SCVWD and the City of
Santa Clara have recommended using a 10* carcinogenic risk level as a cleanup standard for
currently used  drinking water zones.  The SCVWD and City of Santa Clara recommendations are
apparently based on their concern that DHS will be promulgating Recommended Public Health
Levels (RPHL)  for chemicals in drinking water that will be set at the 104 risk level for each chemical.


Staff disagrees  with  ODW's use of the CHI and the 10* carcinogenic risk level as cleanup standards
because both are inconsistent with EPA standards contained in tine National Oil and Hazardous
Substances Pollution Contingency Plan (NCP), 40 CFR Part 300, March 8, 1990, the  Superfund Public
Health Evaluation Manual (SPHEM), (EPA, 1986), the Risk Assessment Guidance for Superfund,
Human Health Evaluation Manual (RAGS), (EPA, 1989),  and the Guidance for Conducting Remedial
Investigations and Feasibility Studies Under CERCLA, (EPA, 1988).

By using ODW's CHI with maximum contaminant levels (MCLs) in the denominator, a different risk
level for cleanup is obtained with each different suite of chemicals.  By using ODW's CHI of one,
staff would be  advocating cleanup at the  different Superfund  sites to variable risk levels with no
technical  or economic basis for these decisions.  Staff believes this is poor risk management and  risk
communication.

ODW cites the technical and  economic analysis that went into promulgation of MCLs as one basis
for using MCLs in the denominator of their CHL However, these technical and  economic
evaluations used for promulgating MCLs are completely different than  the technical and economic
evaluations made in remediating volatile organic compounds (VOCs) from sand and day aquifers.
For the Intersil / Siemens Site, the time necessary to achieve cleanup at this site is currently modeled
at 45  to 85 years and the 30-year present  worth cost is $19 million. Superfund requires that an
independent risk-based analysis of cleanup levels be completed for each Superfund site.  No mention
of a CHI is made in either EPA Superfund guidelines, and these guidelines do contain  procedures
that address the additive effects of multiple chemicals and multiple exposure pathways which appear
to be  ODW's main concerns.

In regards to the RPHLs, they are currently not promulgated and therefore may not be used as
cleanup standards.  The law establishing RPHLs also did not set a specific risk level (e.g. 104)-, these
levels will be set in  regulations by DHS by mid-1991.  Upon promulgation of RPHLs, they will be
evaluated for use as Applicable or Relevant and Appropriate Requirements (ARARs) for cleanup

                                         Pag* 4 of 5

-------
standards.                                     -   .

Because of the inconsistencies and differences between the EPA and ODW procedures, staff believes
EPA recommended risk management and risk communication techniques should be followed for all
Regional Board lead cleanup sites.

The SCO also contains tasks to reevaluate cleanup levels based  on new technical or health
information.  If ODW's recommendations should become codified  in law or regulations, then the
SCO could be modified to include the new  standards.

Notwithstanding  staffs' recommendation to follow all.EPA recommended risk assessment and
management procedures, the ODW CHI would be one for the C-zone, ODW's primary zone of
interest since it is apparently used as a drinking water source in the Valley. The CHI would be one
because there is only one ODW recognized carcinogen, TCE, in the C-zone.  Also, depending on the
methods used to  predict cleanup and risk (Siemens and Intersil  used slightly different methods),
ODW's, SCVWD's and the City of Santa Clara's goal of a 10* risk level may also be met at this  site
under the current cleanup plan. Which of  the methods for  predicting cleanup is more accurate will
not be known for many years, based on predicted and actual performances. Finally, the differences
in cleanup levels between what the SCO calls for and  ODW recommends are in the order of 5 ppb
vs.  2 ppb. These differences are difficult to measure, let alone achieve, with current technology.

Groundwater Pumping from the C-Zone

Alternatives 4 and 5 in the off-site FS and in the SCO included a groundwater extraction  well(s)
screened in the C-zone.  These alternatives  were not selected because of the adverse community
impacts involved in the installation of an additional groundwater  pipeline on Redwing Ave. and
because of pump tests and modelling that showed that the C-zone would be remediated through
pumping in the B-zone.  Remediation of the C-zone  is as high a priority of the RAP as remediation
of the A- and B-zones, If a reduction in C-zone concentrations is not demonstrated after one year,
the plan contains a contingency for the installation of C-zone extraction well(s).  The time to achieve
cleanup and the  cost for alternatives 4 and  5 were similar to that of the selected alternative,
alternative 3.

No changes are recommended to the RAP or the SCO in response to DHS, SCVWD or City of Santa
Clara comments.

Attachment
                                        Page 5 of 5

-------
 Mr. John Wolfenden

Case Manager
Regional Water Quality Control  Bdg.
1800 Harrison Street, Suite 700
Oakland, Ca  94612

Dear Mr. Wolfenden:

Will you please answer a few questions relating to the Siemen/s
Intersil cleanup of their contaminants in soil  in the Quail/
Inverness area:

1.  I live across Home'stead from Siemen's.  My  son owns a
    rental property on Homestead even closer to Siemen's.
    Will the soil contamination under my house  cause me
    or my family health problems 1n the future?

2.  What happened to all the contaminated soil  removed by
    Trumpp Bros, during their months of ditch digging to
    install certain pipes?  I will  not bring up the incon-
    venience that noise caused to those of us fronting
    onto the work.

3.  Your June 1990 pamphlet suggested that there are
    several treatment areas.  Aside from Siemen's or the
    Intersil  former location on Tantau, where are the
    other treatment systems located?

4.  If the ground is contaminated down to 300 feet, what
    about us eating fruits and vegetables grown in that
    soil?

Will try to attend your June 21st meeting at Laurel wood but
please do reply to the questions asked above.  Who is paying
the cost of all this cleanup and treatment?
Cordially yours,
VIVIAN KRODEL
1696 Quail Avenue
Sunnyvale, Ca 94087

-------
                        o
STATE OF CALIFORNIA
                  GEORGE DEUKMEJIAN, Oovtrnor
CALIFORNIA REGIONAL WATER QUALITY CONTROL BOARD

SAN FRANCISCO BAY REGION
1800 HARRISON STREET, SUITE 700
OAKLAND. CA 94612
                                  June 28,
                                  .2189.81
    1990
8124
'818T}
      Mrs.  Vivian Krodel
      1696  Quail Avenue
      Sunnyvale, CA 94087

      Dear,Mrs.  Krodel:

      Thank you  for attending the Intersil/Siemens community meeting on
      June  21.   I hope that we were able to  answer some of your questions
      and concerns.  As you requested, I will try to respond specifically
      to the questions raised in your letter.

           1.  Will  the soil  contamination  under my house cause me or my
              family health problems in the future?

              Soil contamination from Intersil and Siemens has extended
              off-site to an area between  Homestead Road and Lome Way.
              However, the levels in  the  soil north  of the facilities
              is low, less than  3 parts per million  TCE,  and is found
              at depths of 40 feet  or more.  Further,  a public health
              evaluation was conducted to evaluate current and potential
              future health risks posed by the site.   The evaluation
              concluded that the  carcinogenic risk for direct contact
              with on-site soils for children and adults is 3 potential
              excess cancer cases in  1 million and 2 potential excess
              cancer cases  in  10 million, respectively, and  the non-
              carcinogenic  hazard  index   is  less  than  one.    The
              carcinogenic risk from inhalation of chemicals volatilized
              from on-site soils is  1 potential  excess cancer risk in
              100 billion and the hazard  index for inhalation of VOCs
              volatilized from on-site soils is less than one.  On-site
              soils are contaminated with VOCs at much higher levels and
              at much shallower  depths than  the off-site  areas.   EPA
              considers carcinogenic risk  ranges  of 1 potential excess
              cancer risk in 10 thousand  to 1 in 1 million and hazard
              indexes of  up to 1 to be protective of public health.
              Therefore,  we do  not  believe  that the off-site  soil
              contamination poses a  threat to public  health.

-------
      2.   What happened to all the contaminated soil removed by '
          Trvunpp  Bros, during  their months  of ditch  digging  to
          install  certain pipes?

          The  pipeline was  installed along  Quail Avenue to convey
          groundwater  from the off-site  extraction wells  to the
          treatment  system at the  Siemens  facility..  The  soil
          removed  was  not contaminated with VOCs from Intersil and
          Siemens  and  was used to back-fill the ditches.

      3.   Aside from Siemen's or the Intersil former location on
          Tantau,  where are the other treatment systems located?

          All  of the treatment systems are located at the Intersil
          and   Siemens   facilities.      The   selected   remedial
          alternatives will expand the existing on-site soil vapor
          extraction and  treatment and  groundwater extraction and
          treatment systems.  Groundwater  extracted from wells off-
          site will continue to be treated at  the Siemens facility.
          The extracted groundwater will continue to be transported
          to the facility via the underground pipeline along Quail
          Avenue.   The  pipeline  is double-contained  to  prevent
        •  leaks.

     4.  If the ground is contaminated down to 300  feet, what about
          us eating fruits and vegetables grown in that soil?

          Soil contamination is limited to the facilties, to an area
          approximately 200 feet east  and west of the facilities, and
          to the north between Homestead Road and Lome Way.  Near
          Homestead Road, the soil contamination is deeper than 40
          feet.  The contamination is not found in a concentration
          or at a  depth that should have any impact on fruits or
          vegetables.  Also, polluted groundwater is found off-site
          at depths of greater than  100 feet, below the root zone
          of fruit trees or vegetable crops.

The Intersil and Siemens companies have paid for the investigations
and cleanups to date  and are expected to continue to do so.  As a
proposed Superfund site,  the federal Superfund Trust Fund will step
in and continue the cleanups should Intersil and Siemens fail their
responsibilities.  The $8.5 billion Trust Fund  is primarily funded
by a tax  on the chemical and petroleum industries.

I hope I was able to answer your  questions.   Please let me know if
you have  any other questions or concerns.
                             Sincerely
                                  "
                             John D. Wolfenden
                             Case Manager

-------
1696 Quail Avenue        .          '                  ----,..
Sunnyvale, Ca 94087   -               '                  -:  -.. „  !
August 4, 1990

California Regional Water Quality Control  Bd.               ^'^ 0 '/ ;~
1800 Harrison Street,  Suite 700                     ,.,. .
 Oakland, Ca   94612                                 t--- Uf/ Cjl:,i: ,L ,

Subject:  Inters 11 /Siemens soil  contamination

Gentlemen:

I was not able to attend the public  hearing  at the Laurel wood
School on June 21, 1990, but I  have  learned  what  was  discussed
at that meeting and would like  to make an  earnest request:

That both companies put up a heavy bond to  make sure they will  pay
for this cleanup In years to come.  I have learned that it may
take 45 years or more to get this mess cleaned up.  I own  a
property directly across the street  from Siemen's and another
on the southwest corner of Quail and Homestead.  This contamina-
tion will affect the  salablUty of  these  properties  for all
those 45 years.

We should not have to spend our tax  dollars  for this  cleanup!
The suggestion was made that this work 1s  eligible for Federal
cleanup funds.  If I were an executive on  either of those  two
firms involved so far, I would  have  made a specific note of
of that information.  Let's make SURE Intersil and Siemens
post a high enough bond to make them fully responsible for the
cleanup of their mess... for as long as It takes.

We have tolerated the noisy equipment needed to tear up our
streets and the Installation of pipes and  electrical  systems
underground (with all the notes associated with their Installa-
tion);  we have put up with steel plates banging day and night
as carshit them;  we have bitten our nails over the slow pace
of getting this cleanup started — but we  should not have  to
put up with taxpayers paying for spills caused by these two
major companies.
Cordially yours,
PS:  It 1s my understanding that there will be a Public Hearing
     in Oakland 1n August and I would like this made a part of
     those, proceedings.

                                      G.M.K.

-------
APPENDIX A

-------
                CALIFORNIA REGIONAL WATER QUALITY CONTROL BOARD
                              SAN FRANCISCO BAY REGION


ORDER NO. 90-119

SITE CLEANUP REQUIREMENTS FOR:

SIEMENS COMPONENTS, INC             INTERSIL, INC
19000 HOMESTEAD ROAD                 10900 NORTH TANTAU AYR
CUPERTINO                              CUPERTINO
SANTA CLARA COUNTY                   SANTA CLARA COUNTY

VALLCO PARK, LTD.
CUPERTINO
SANTA CLARA COUNTY

The California Regional Water Quality Control Board, .San Francisco Bay Region (hereinafter called
the Board) finds that

L      Site Location and Description  This Order presents the selected final remedial action plan  for
       the Intersil / Siemens proposed Superfund site.  The Siemens Components, Inc. (Siemens)
       facility is located at 19000 Homestead Road, Cupertino, and the former Intersil, Inc. (Intersil)
       facility is located at 10900 North  Tantau Ave., Cupertino (Figure 1).  Siemens and Intersil
       lease their respective properties from the piopeity owner, Vallco Park, Ltd.

       The properties are  located on approximately 12 acres at the southeast comer of North Tantau
       Ave. and Homestead Rd. in Cupertino near the borders of the City of Sunnyvale and the
       City of  Santa Clara. The two properties are adjacent to each other, separated by Forge Drive
       (Figure  1). The surrounding terrain gently slopes northeast towards San Francisco Bay,
       which lies approximately 75 miles  north of the Site.  Calabazas Creek lies approximately 0.2
       miles east of the Site and flows to  the northeast

2.      Description of the Selected Remedy The selected remedy for the rites consists of:

       o      Soil vapor extraction and treatment and soil excavation for soil cleanup

       o      Groundwater extraction and treatment for groundwater cleanup

       o      Shallow zone and deeper aquifer groundwater monitoring and soil monitoring

       There are currently seven soil vapor extraction wells and nine groundwater  extraction wells
       operating at the Site. The final remedial action plan will  include the installation of 16
       additional soil vapor extraction wells and 10 additional groundwater extractions wells.  Vapor
       phase carbon adsorption will  be  used for the soil vapor treatment and air stripping will be
       used for groundwater treatment

3.      Administrative Orders The following administrative orders have been adopted for Siemens
       and Intersil:

       Siemens
       o      June 1986 - Order No. 86-48, Waste Discharge Requirements (Site Cleanup
              Requirements)

                                            1

-------
o      May 1987 - Order No. 87-045, NPDES No. CA0029190
o      September 1987 - Cleanup and Abatement Order No. 87-133
o      March 1989 - Order No. 89-038, Site Cleanup Requirements

Intersil
o      April 1986 - Administrative Civil Liability
o      June 1986 - Order No. 86-49, Waste Discharge Requirements  (Site Cleanup
       Requirements)
o      September 1987 - Cleanup and Abatement Order No. 87-133
o      October 1987 - Order No. 87-133, NPDES No. CA0029262
o      March 1989 - Order No. 89-133, Site Cleanup Requirements

Site History Siemens produces a variety of light emitting diode (LED) semiconductor
products used as  components in optoelectronic products.  Until approximately 1988, the
manufacturing process consisted of LED ingot growing (where a gallium arsenide ingot was
produced), and currently consists of wafer fabrication.  Intersil formerly assembled
semiconductor devices, including low power complimentary metal oxide semiconductors, and
linear and discrete semiconductors, for use in various electronic components.  Processes
included wafer masking, etching and diffusion.

The underground waste handling facilities formerly used at Siemens included five unvaulted
waste solvent tanks and an unvaulted acid dilution basin.  The five waste solvent tanks and
the acid dilution basin have been excavated  Siemens currently treats wastewater using an
acid neutralization system and stores waste solvents above ground  Mark Systems, Inc.
initially occupied  the property in 1968. Litxonix, Inc. occupied the facility from 1971 to 1978.
Litronix was purchased by Siemens during the period of 1977 to 1978 and the facility has
been operated by Siemens since that time.

The underground waste handling facilities formerly used at Intersil included two vaulted and
one unvaulted acid neutralization systems, two unvaulted scrubber sumps and a vaulted
waste solvent tank.  All  the underground facilities have been  excavated The Intersil facility
was in operation  from 1967  to 1988.

The Siemens semiconductor manufacturing operations have used various organic  solvents
including trichloroethene (TCE), 1,1,1-trichloroethane (TCA), methanol, isopropanol (IPA),
n-butyl acetate, acetone, xylene, Freon, and commercial mixtures apparently containing
trichlorobenzene (TCB), phenols and toluene. The Intersil semiconductor fabrication
operations have used various organic solvents including TCE, TCA, Freon, xylenes, IPA,
n-butyl acetate, acetone, ethyl benzene, and commercial mixtures apparently containing
phenols and toluene.

In 1982, Intersil and Siemens submitted Facility Questionnaires to Regional Board staff
describing their underground neutralization systems, sumps, and tanks. Based on these
submittals, staff required the initiation of the remedial investigation (Rl) at Siemens and
Intersil in 1982.  The RJ has been ongoing for the last eight years. Interim remedial actions
began at Siemens in  1983 with the startup  of a soil vapor extraction system.  Groundwater
extraction and treatment began at Siemens in 1986. Interim remedial actions began at Intersil
in 1986 when the inactive neutralization system was removed, and continued in 1987 with
the startup of a groundwater extraction and soil  vapor extraction system.  The feasibility
study (FS) evaluates the interim remedial actions that have been ongoing for the last seven
years and evaluates alternatives for the final remedial action.  Intersil and Siemens have
submitted Remedial Investigation / Feasibility Study (RI/PS) reports for the on-site and off-site
areas.  The on-site area  for each company is the area within the respective property

-------
       boundaries.  The RI/FS reports summarize the last eight years of the RI and the last seven
       years of the interim remedial actions.

5.     SoD Investigation  Releases of chemicals have occurred from both the Siemens and Intersil
       underground waste handling facilities. Initial subsurface investigations at the Siemens
       property have shown solvent concentrations in the soil as high as 21,000 parts per million
       (ppm) n-butyl acetate immediately beneath former tank 1A and 11,000 ppm TCA, 17 ppm
       TCE and 15,200 ppm trichlorobenzenes immediately beneath former tank 3.  Investigations at
       the Siemens property show solvent concentrations in  the soil as high as 36 ppm TCA at a
       depth of 46 feet and 70 ppm TCE at a depth of 30 feet Siemens has installed 62 soil borings
       to define the extent of the soil pollution.  The extent of soil pollution has been defined to 1
       ppm TCE  or nondetect levels of TCE towards the west at the Siemens property boundary,
       towards the east 200 feet east of the Siemens hazardous material storage area, and on the
       north between Homestead Road and Lome Way.  At the northern border of the Siemens
      ' property on the south side of Homestead Road, TCE  was detected in a soil boring at 40, 50,
       80, and 100 feet deep at concentrations of 1.4, 1.8, 2.7, and 2.5 ppm, respectively. The
       southerly extent of the Siemens  soil pollution blends  together with  the northerly extent of
       the Intersil soil pollution.

       TCE concentrations at Intersil have been found as high as 33 ppm in two soil borings at
       depths of  26 and 41 feet in a soil boring near  the former inactive east acid neutralization
       system and up to 10 ppm at a depth of 595 feet in a soil boring near the north scrubber
       sump.  Intersil has installed 64 soil borings and analyzed 529 soil samples to define  the
       extent of the soil pollution. The extent of soil pollution has been defined to 1 ppm  TCE or
       nondetect  levels of TCE towards the west at 200 feet west of the western property boundary,
       to the south near the southern edge of the Intersil building, and to the east  within the
       eastern property boundary.  The northerly extent of die Intersil soil pollution blends together
       with the southerly extent of the Siemens soil pollution.

6.     Hydrogeology The subsurface geology beneath the Site consists of a series  of interbedded
       coarse-grained sand and gravel and fine-grained silt and day sediment units, representing
       alluvial stream channel deposits and associated overbank deposits.  The first saturated
       materials,  a locally perched water zone, occurs at approximately 50 to 60 feet below  the
       surface at some locations.  The first laterally extensive saturated hydrogeologk unit,  termed
       *e A-zone, occurs between 105  and 120 feet below the ground surface.  The next deeper
       permeable zone, the B-zone, occurs between approximately 130 and 150 feet below the
       ground surface.  The next deeper relatively permeable zone, the C-zone, occurs between
       approximately 180 and 210 feet below the ground surface.  Groundwater in the A-zone, B-
       zone and  C-zone flows generally to  the north, although local variations have been observed.
       A downward vertical gradient exists between the hydrogeologic zones.  Deep aquifers exist
       beneath the Site at depths of approximately 300 to 500 feet below the ground surface,
       separated from the C-zone by an approximately 75 foot thick regional aquitard.

7.     Groundwater Investigation Groundwater investigations at the Siemens and Intersil properties
       have shown the on-site and off-site A-, B-, and C-zones to be polluted with various  organic
       solvents. 97 monitoring wells have been installed to define the extent of groundwater
       pollution.  A-zone  monitoring wells on the Siemens property have detected TCE
       concentrations as high  as 26,000 parts per billion (ppb). A-zone monitoring wells on the
       Intersil property have detected TCE concentrations as high as 33/100 ppb. B-zone monitoring
       wells on die Siemens property have detected TCE concentrations as high  as 5080 ppb and
       1,1,1-TCA  concentrations as high as 1030 ppb.  B-zone monitoring wells on die Intersil
       pioperty have detected TCE concentrations as high as 950 ppb.  C-zone monitoring wells on
       die Siemens property have detected less dun 40 ppb organic solvents.

-------
       The groundwater pollution plumes from Siemens and Intersil have commingled in the A-zone
       and have migrated to the B-zone and C-zone.  The off-site groundwater pollution plume
       extends off-site approximately 1600 feet down gradient from the properties at concentrations
       greater than MCLs.  The off-site A-zone groundwater plume extends north from the Site to
       Lome Way.  The off-site groundwater plume in the B- and C-zones extends north from the
       Site to several hundred feet north of Inverness Way.  The off-site groundwater plumes
       appear to be defined  Monitoring well VM-1B at the far north eastern extent of the
       monitoring well network detected 10 ppb TCE  It appears that this may be part of the AMI
       groundwater plume.

8.     Adjacent Facility Gould AMI Semiconductors (AMI) formerly manufactured electronic
       components at a site located at 3800 Homestead Road, Santa Clara.  This site is immediately
       east of and adjacent to the Siemens and Intersil Site.  The underground waste handling
       facilities formerly used by AMI included an acid neutralization system, a concrete sump and
       a steel storage tank. TCE has been detected in the A-zone at the AMI facility, north of the
       AMI facility, and beneath the Marchese property east of AMI, at concentrations up to 300
       ppb.  TCE has been detected off-site at concentrations up to 168 ppb. Additional
       investigation is required to define the extent of the off-site AMI TCE groundwater plume.
       AMI has proposed an interim remedial action system.

9.     Deep Aquifer Investigation  The former Marchese Well No. 2, a private, deep irrigation well
       located approximately one-half mile down gradient from  Siemens and Intersil, was found to
       contain low levels (less than 30 ppb) of TCE, 1,1,1-TCA and Freon-113. In December 1986,
       this well was camera logged and sealed by the Santa Clara Valley Water District to prevent
       the further spread of pollutants through the well  Camera logging showed that the well was
       screened at three different intervals between 300 and  500 feet deep.

       Siemens and Intersil have installed four deep aquifer  monitoring wells to attempt to identify
       which of the deeper aquifers screened by the former Marchese Well  No. 2 contained VOCs.
       Since 1987, TCE has been sporadically detected in  two deep aquifer monitoring wells at
       concentrations up to 1  ppb.   TCE has not been detected in the deep aquifer wells for the last
       three quarters. TCA has been detected in the deep aquifer monitoring wells at
       concentrations up to 5 ppb.   TCA has not been detected  in the deep aquifer monitoring  wells
       for the last two quarters.  Toluene has been detected  at concentrations up to 42 ppb.
       Toluene was detected at 20 ppb in one deep aquifer well during the last quarter.  Any
       requirement for additional deep aquifer monitoring wells will  be based on the results of
       future quarterly monitoring  of the existing four deep  aquifer monitoring wells.

10.     Municipal Water Supply There are five active municipal wells within a one mile radius of
       the Siemens and Intersil properties.  Three of these wells are located in apparent down
       gradient directions. All five wells are being monitored for volatile organic chemicals (VOCs)
       by the Cities of Santa dan and Sunnyvale, dry of Santa Clara well No. 24, down gradient
       approximately 3700 feet northeast of the site, has consistently shown 1 to 43 ppb Freon-113
       and up to 16 ppb 1,1,1-TCA. No other pollutants have been detected in any of these wells
       to date.

11.     Interim Remedial Actions  Siemens has been performing soil and groundwater interim
       remedial actions at its property.  A sou"  vacuum extraction system to remove volatile organics
       from tile vadose zone has been in operation since November 1983, and is estimated to have
       removed approximately 13,200 pounds of VOC*. Siemens installed an A-zone groundwater
       extraction and treatment system in 1986.  A combined A-zone and B-zone groundwater
       extraction and treatment system has been operating since 1987. Siemens' groundwater
       extraction systems have removed approximately 590 pounds of VOCs. Intersil has also been

-------
       performing soil and groundwater interim remedial actions at its site.  A soil vacuum
       extraction system has been in operation since 1988, and is estimated to have removed
       approximately 2,300 pounds of TCE  An A-zone groundwater extraction and treatment
       system has been in operation since 1987, and is estimated to have removed approximately 43
       pounds of TCE.

12.     Baseline Public Health Evaluation A Baseline Public Health Evaluation (BPHE) was
       conducted for the site to evaluate current and potential future health risks posed by the site.
       Current risks are based on exposures that are presently occurring.  Potential future health
       risks are  based on  exposures that could potentially occur in the future if residential
       development occurred on the Site or if untreated shallow zone groundwater was used for
       human consumption. To ensure  that human health is protected,  tine BPHE incorporated
       conservative assumptions.  Therefore, it is very unlikely that the actual risks posed by the
       Site would be greater than estimated.  Average case and plausible maximum case scenarios
       are presented in the BPHE.  This finding refers to the average case scenarios using a nine
       year duration exposure.  Current exposures include ingestion of water from City of Santa
  x    Clara Well No. 24, inhalation of VOCs from the use of water from City of Santa Clara Well
       No. 24, and inhalation of chemicals volatilized from on-site  soils.   Freon 113 and TCA have
       been detected  in Well No. 24 at average concentrations of 1.7 ppb and 1.0 ppb, respectively.
       These concentrations correspond to a noncarcinogen hazard index of 10*.  This is 10,000
       times less than tine maximum acceptable hazard index of one.  The carcinogenic risk from
       inhalation of chemicals volatilized from on-site soils is ID11.   This is. 100,000  times less than
       the maximum  acceptable carcinogenic risk range of 10* to 104.  The hazard  index for
       inhalation of VOCs volatilized from  on-site soils is less than one.  The BPHE concluded that
       with respect to current  exposure  scenarios, risks were well below acceptable levels.

       Potential  future use exposures include  direct contact with on-site  soils, ingestion of shallow
       and deeper zone groundwater, inhalation of VOCs from use of shallow or deeper  zone
       groundwater, and inhalation of chemicals volatilized from on-site soils.  The carcinogenic risk
       for direct contact with on-site soils for children and adults is 3 x  10* and 2 x 107,
       respectively, and the noncartinogenic hazard index is less than one.  The carcinogenic risk
       from ingestion of shallow and deeper zone groundwater ranges from 1 x 10* to 4  x 10*.   The
       noncarcinogenic hazard index for ingestion of A-zone groundwater was greater than one.
       The carcinogenic risk from inhalation of VOCs from the use of shallow or deeper  zone
       groundwater ranges from 2 x 104 to 7  x I04 and tine noncarcinogenic hazard index is less
       than one. The carcinogenic  risk  from inhalation of chemicals volatilized from on-site soils is
       10".  The hazard index for inhalation  of VOCs volatilized from on-site soils is less than  one.

13.     Description of Alternatives  Siemens and Intersil evaluated several alternatives for tine final
       Remedial Action Plan in the FS.  In  the PS, a wide range of technologies were initially
       screened  based on  effectiveness, implementability, and relative cost  The technologies that
       passed this initial screening were then assembled into the range of treatment alternatives that
       are described below.

       The Siemens and Intersil properties are proposed as one site on the National Priorities List
       (NPL). However, each  company  completed its own on-site  RI/FS and together, they
       completed a joint off-site RI/FS.   For this reason, a separate series of alternatives was
       developed for  Siemens on-site, Intersil on-site and tine off-site area. The on-dte areas are tine
       areas within tine leased property  boundaries.

-------
13.1    .Siemens On-Site Alternatives

13.1.1  Alternative No. 1 is the "no action* alternative.  All existing interim remedial actions are
       discontinued and no further remedial actions are implemented.  Geanup levels would not be
       achieved for an estimated 750 to 1250 years when chemical concentrations might be reduced
       by natural attenuation.

13.1.2  Alternative No. 2 includes groundwater extraction and treatment and soil vapor extraction
       and treatment  Groundwater treatment is accomplished by air stripping with subsequent
       discharge to Calabazas Creek and possible partial on-site reuse.  Soil vapor treatment is
       accomplished through carbon adsorption. The existing groundwater extraction system of
       extraction wells HXA, H2A,  3-DD, 3-XA, 1-1D, H-3B, H-5B, and  3EB would be expanded to
       include LF-6A for a total of 9 groundwater extraction wells, 6 A-zone extraction wells and 3
       B-zone extraction wells.  However, 4 A-zone wells are currently dry due to the lowering
       water table, so there would only be a  total of 5 operating groundwater extraction wells.  The
       other 4 wells would be operated if regional groundwater levels rise. The estimated
       groundwater pumping rate is 25 gallons per minute (gpm).  Groundwater cleanup levels are
       federal or state MCLs or action levels.  The estimated time to achieve cleanup is
       approximately 55 to 95 years.

       The existing soil vapor extraction system of extraction wells ID, 3A, and 3C would be
       expanded to include 12 additional soil vapor extraction wells; 2EP, 2EPa, 2B, 4BP, HMSA1,
       HMSA2, SW-5, SW-6, SW-7, 3E, II, and 1M; for  a total of  15 soil vapor extraction wells. The
       estimated soil vapor vacuum rate is 400 cubic feet per minute (cfm). The  soil cleanup level is
       1 ppm  total VOCs and 10 ppm total SOCs.  The time to achieve soil cleanup is
       approximately 15 years.  The 30 year present worth cost for this alternative is $4.87 million.
       Regular groundwater and soil vapor monitoring will be completed

13.1.3  Alternative No. 3 includes accelerated groundwater extraction and treatment and soil vapor
       extraction and treatment  Alternative No. 3 is the same as alternative No. 2 with the
       addition of 4 A-zone extraction wells; W21A, LF-4A, LF-9A, and 2-1D-, for a total of 13
       groundwater extraction wells: 10 A-zone and 3 B-zone groundwater extraction wells.  4 A-
       zone wells  are currently dry so there would be  6 operating A-zone extraction wells.  The
       additional extraction weDs would add about 3 gpm for a total system pumping rate of  28
       gpm.  The time to achieve groundwater cleanup is approximately 45 to 85 years.  The 30
       year present worth cost for this alternative is $5.03 million.

13.1.4  Alternative No. 4 includes accelerated groundwater extraction and treatment; soil vapor
       extraction and treatment and sofl excavation.  Alternative No. 4 is the same as alternative
       No. 3 with the addition of soil excavation down to about  40 feet deep in the areas of former
       tanks 1 and 3 to remove sous containing semi-volatile organic compounds (SOCs) above the
       cleanup level of 10 ppm total SOCs.  Trichlorobenzene and Phenol were detected in former
       tank areas 1 and 3.  These compounds are not readily amenable to treatment by soil vapor
       extraction so these areas will be excavated.  Two areas of 9 square feet by 40 feet deep or an
       estimated 20 cubic yards of soil wfll be excavated at each  location.  The soil would be
       disposed of in accordance with law, possibly at  a Class I landfill or off-site treatment facility.
       The estimated time to achieve son cleanup is 10 yean.  The 30 year present cost for this
       alternative is $5.66 million.

13.15  Alternative No. 5 includes accelerated groundwater extraction and treatment, accelerated soil
       vapor extraction and treatment and soil excavation. Alternative No. 5 is the same as
       alternative No. 4 with the addition of 7 soil vapor extraction wells beyond the system
       proposed for alternatives 2, 3, and 4. There would be a total of 22 soil  vapor extraction

-------
       wells.  The additional soil vapor extraction wells are 2C, SW-I, SW-2, 1H, IG, 1J, and HMSA-
       3.  The estimated soil vapor vacuum rate is 800 cubic feet per minute (cfm).  The time to
       achieve soil cleanup is approximately 10 years.  The 30 year present worth cost of this
       alternative is $636 million.    : '• :'

13.1.6  Alternative No. 6 is the same as alternative No. 4 with a more stringent groundwater cleanup
       level of cleanup to background levels for VOCs. The  estimated time to achieve groundwater
       cleanup is approximately 450 years.

13.2    Intersil On-Site Alternatives

13.2.1  Alternative No. 1 is the "no  action" alternative.  All existing interim remedial actions are
       discontinued and no further remedial actions are implemented. Site  monitoring would be
       continued.  The 30 year present worth cost of this alternative is $4.0 million.  Geanup levels
       would not be achieved

13.2.2  Alternative No. 2 consists of the existing groundwater extraction and treatment and soil
       vapor extraction and treatment  Groundwater treatment is accomplished by air stripping with
       subsequent discharge to Calabazas Creek.  Soil vapor treatment is accomplished through
       carbon adsorption.  The existing groundwater extraction system consists of extraction wells
       W4A, W5A, W10A, W12A, and W17A,  The groundwater pumping rate is 1.75 gallons per
       minute (gpm).  Groundwater cleanup levels are federal or state MCLs or action levels.  The
       estimated time to achieve groundwater cleanup  is approximately 135  years.

       The existing soil vapor extraction system consists of extraction wells VE1, VE2, VE3, and VE4.
       The estimated soil vapor vacuum rate is 60 cubic feet per minute (cfm). The soil cleanup
       level is 1 ppm total VOCs.  The time to achieve soil cleanup is 7 years. The 30 year present
       worth cost for this alternative is $ 9.8 million. Regular groundwater and soil vapor
       monitoring will be conducted.

13.23  Alternative No. 3 includes expanded groundwater extraction and treatment and expanded soil
       vapor extraction and treatment  Alternative No. 3 is similar to alternative No. 2 with the
       addition of 1) new groundwater extraction pumps having lower pump  intakes installed in A-
       zone extraction wells W5A, W10A, WI2A, and VV17A; 2} conversion of A-zone monitoring
       well W9A into an A-zone extraction well and conversion of B-zone monitoring well W18B
       into a B-zone extraction well; 3) four new  vapor extraction wells and four new vent wells;
       and 4) capping six existing and two new vent wells along Forge Drive. Two new vapor
       extraction wells would be installed near the center of the site and perched-zone groundwater
       extraction well W4A would be converted to a dual soil vapor / groundwater extraction well
       and the dry groundwater monitoring well W4AA would be converted to a soil vapor
       extraction well The groundwater extraction  flow rate for this alternative is approximately 85
       gpm.  The time to achieve groundwater cleanup is 60 years.  The soil vapor extraction flow
       rate is 140 cfm. The time to achieve soQ cleanup is 5 years.  The 30 year present worth cost
       of this alternative is $10.1 million.

112.4  Alternative No. 4 includes expanded groundwater extraction and treatment and expanded soil
       vapor extraction and treatment and on-tite reinjection  of treated groundwater.  Alternative
       No. 4 is the same as alternative No. 3 with the addition of two A-zone groundwater injection
       wells and two new piezometers to monitor the effect of reinjection.  The time to achieve
       groundwater cleanup is 45 years. The 30 year present worth cost of this alternative is $10.7
       million.

-------
13.15  Alternative No. 5 includes expanded groundwater extraction and treatment, expanded soil
       vapor extraction and treatment, extensive soil excavation, groundwater reinjection, and
       installation of a slurry wall around the property down to the A/B  aquitard.  Alternative No. 5
       is the same as alternative No. 4 with the addition of 1) the excavation and on-site aeration of
       up to 170,000 cubic yards of soil; 2) installation of a slurry wall around the property and
       completed within Ac A/B aquitard to physically aid in containing  perched and A-zone
       groundwater beneath the property. Alternative No. 5 maintains the existing soil vapor
       extraction system and does not modify the soil vapor extraction system as in alternative nos.
       3 and 4.  The time to achieve groundwater cleanup is 20 years. The  time to achieve soil
       cleanup (largely through excavation) is  1 year.  The 30 year present worth cost of this
       alternative is $373 million.

13.2.6  Alternative No. 6 is the same as alternative No. 3 with a more stringent groundwater cleanup
       level of cleanup to background levels for VOCs. The estimated time  to achieve groundwater
       cleanup is several hundred years.  The  30 year present worth cost of  this alternative is $10.6
       million.

13.3    Intersil and Siemens Off-Site Area

133.1  Alternative No. 1 is the 'no action* alternative All  existing interim remedial actions are
       discontinued and no further remedial actions are implemented. Site monitoring would be
       continued. The 30 year present worth cost of this alternative is $122 million.  Geanup levels
       would not be achieved except through natural attenuation which would take an estimated
       750 to 1250 years.

133.2  Alternative No. 2 consists of groundwater extraction from B-zone extraction well LQ-2B and
       treatment Groundwater would be pumped from LQ-2B on Lanark Ct south on Quail Ave.
       to the Siemens property. Groundwater treatment is accomplished by  on-site air stripping
       with  subsequent discharge to Calabazas Creek and possible partial on-site reuse.  The
       estimated groundwater pumping rate is 40 gallons per minute (gpm).  Groundwater cleanup
       levels are federal or state MCLs or action levels. The estimated time  to achieve cleanup is
       approximately 20 to 50 years. The 30 year present worth cost for this alternative is $2.12
       million. Regular groundwater monitoring will be conducted

1333  Alternative No. 3 consists of groundwater extraction from three B-zone extraction wells and
       groundwater treatment and a contingency for one C-zone extraction well  Alternative No. 3
       is the same as alternative No. 2 with the addition of groundwater extraction from wells LQ-
       1B and S-2B.  Groundwater modeling has shown that pumping from  the B-zone will capture
       a portion of the C-zone groundwater at concentrations greater  than MCLs. C-zone capture
       area and water chemistry will be evaluated after 1 year of operation to determine the
       effectiveness of this alternative.  If adequate C-zone capture and a reduction in C-zone TCE
       concentrations are not demonstrated, then a C-zone extraction well will be installed. The
       estimated groundwater pumping rate is 105 gpm. The estimated time to achieve cleanup
       levels is 20 to 45 years.  The 30 year present worth cost for this alternative is  $2.99 million.

133.4  Alternative No. 4 consists of groundwater extraction from two B-zone and one C-zone
       extraction well and groundwater treatment Alternative No. 4 is the same as alternative No.
       3 with the addition of groundwater extraction from C-zone weU RK-2C For the C-zone
       extraction well, groundwater would be  pumped by underground pipeline from RK-2C on
       Kerry Ave., south along Redwing Ave. and then west along Lome Way to Quail Ave. and
       then  to the Siemens facility. The  estimated groundwater pumping rate is 65 gpm.  The
       estimated time to achieve deanup levels is 20 to 50 years.  The 30 year present worth cost for
       this alternative is $165 million.

                                             8

-------
 1S.S.5 Alternative No. 5 consists of ground water extraction from two B-zone and two C-zone
       extraction wells and ground water treatment Alternative No. 5 is the same as alternative No. 4
       with the addition of groundwater extraction from C-zone well LR-SC. The estimated
       groundwater pumping rate is 90 gpm.  The estimated time to achieve cleanup levels is 20 to 50
       years.  The SO year present worth cost for this alternative is $2.81 million.

 13.3.6 Alternative No. 6 is the same  as alternative No. 4 with a more stringent groundwater cleanup
       level to background levels for VOCs. The estimated time to achieve cleanup levels is 1 50 to
       300 years.  The 30 year present worth  cost for this alternative is $2.96 million.

 14.    Summary of Evaluation Criteria This section summarizes the nine evaluation criteria
       developed by EPA and used to compare the alternatives in the RI/FS.  The alternatives were
       evaluated in detail with respect to the nine criteria in the RI/FS report  Each alternative was
       also evaluated with respect to the six state law criteria set forth in Section 25356.1 of the
       California Health and Safety Code. A comparative analysis was completed in the RI/FS.

 14.1   Overall protection of human health and the environment This criterion addresses whether a .
       remedy provides adequate protection of human health and the environment

 14.2   Compliance with applicable or relevant and appropriate requirements (ARARs) This criterion
       addresses whether a remedy will meet all of the ARARs or other Federal and State
       environmental laws enumerated in the RI/FS.

 14 .3   Long-term effectiveness and permanence This criterion refers to expected residual risk and
       residual chemical concentrations after cleanup goals have been met and the ability of a remedy
.;      to maintain reliable protection of human health and the environment over time.

 14.4   Reduction of toxicity. mobility or volume This criterion refers to the anticipated  performance
       of the treatment technologies  a remedy may employ.

 14.5   Short-term effectiveness This criterion addresses the period of time needed to achieve cleanup
       and any adverse impacts on human health and the environment that may be posed during the
       construction and implementation period, until cleanup goals are achieved.

 14.6   Implementability This criterion refers  to the technical and administrative feasibility of a
       remedy.

 14.7   Cost Tub criterion includes estimated capital and operation and maintenance, usually
       presented in a SO year present worth format

14.8   Support Agency Acceptance This criterion addresses EPA's acceptance of the selected remedy
       and any other EPA comments.

14.9   Community Acceptance This criterion  summarizes the public's general response  to the
       alternatives.
15.    The Selected Remedy fffaal ttgm^*fia| Action pfa"^
15.1    Intersil On-Site Area  The selected remedy for the Intersil on-site area is Alternative No. 3.
       Alternative No. S includes expanded groundwater extraction and treatment and expanded soil
       vapor extraction and treatment. The existing sofl vapor extraction system consisting of
       extraction wells VE1, VE2, VES, and VE4 will be expanded to include four new vapor
       extraction wells and four new vent wells. Six existing and two new vent wells along Forge

                                             9

-------
       Drive will be capped  The existing groundwater extraction system consisting of extraction
       wells W4A, W5A, WlOA, W12A, «nd W17A will be upgraded to include, new groundwater
       extraction pumps having lower pump intakes installed in A-zone extraction wells W5A,
       WlOA. W12A, and W17A, and A-zone monitoring well W9A will be converted to an
       extraction well.  B-zone groundwater extraction will be accomplished through conversion of
       B-zone monitoring weD W18B into a B-zone extraction well

       Groundwater cleanup levels are federal or state MCLs (adopted or proposed) or California
       Department of Health Services (DHS) Recommended Drinking Water Action Levels
       (RDWALs). The soil cleanup level is 1  ppm total VOCs.  The final cleanup levels for the
       suite of chemicals detected in the A-zone equate to a future use scenario risk level for
       groundwater ingestion and inhalation of VOCs of 1.7 x 10*.  Groundwater treatment will be
       accomplished by air stripping with subsequent discharge to Calabazas Creek.  Soil vapor
       treatment is accomplished through carbon adsorption.  Regular groundwater and soil vapor
       monitoring will  be conducted The time to achieve groundwater cleanup is 60 years,  the
       time to achieve  soil cleanup is 5  years.

152    Siemens On-Site Area  The selected remedy for the Siemens on-site area is Alternative No. 4.
       Alternative No. 4 includes accelerated groundwater extraction and treatment, soil vapor
       extraction and treatment, and soil excavation.  The existing groundwater extraction system of
       extraction wells  HXA, H2A, 3-DD, 3-XA, MD, H-3B, H-5B, and 3EB would be expanded to
       include LF-6A, LF-4A, LF-9A, W21A,  and MD; for a total of 10 A-zone groundwater
       extraction wells  and 3 B-zone extraction wells.  However, 4 A-zone wells are currently dry
       due to the lowering water table,  so there would only be a total of 6 operating A-zone
       groundwater extraction wells under current conditions.

       The existing soil vapor extraction system of extraction wells  ID, 3A, and 3C would be
       expanded to include 12 additional soil vapor extraction  wells; 2EP, 2EPa, 2B, 4BP, HMSA1,
       HMSA2, SW-5, SW-6, SW-7, 3E, H and  1H for a total of 15 soil vapor extraction wells.
       Alternative No. 4 also includes soil excavation down to about 40 feet deep in the areas of
       former tanks 1 and 3 to remove soils containing semi-volatile organic compounds (SCO).
       The soil would be disposed of in accordance with applicable laws, possibly at a Class I
       landfill or off-site treatment facility.  The 30 year present cost for this alternative is $5.66
       million.

       Groundwater cleanup levels are federal or state MCLs (proposed or adopted) or RDWALs.
       The final cleanup levels for the suite of chemicals detected in the A-zone equate to a future
       use scenario risk level for groundwater ingestion and inhalation of VOCs  of 1 x 104.
       Groundwater treatment will be accomplished by air stripping with subsequent discharge to
       Calabazas Creek and possible partial reuse and reclamation on-site. Soil vapor treatment may
       be accomplished through carbon  adsorption.  Regular groundwater and soil vapor monitoring
       will be completed  The soO cleanup level is 1 ppm total VOCs and 10 ppm total SOCs.  The
       estimated time to achieve groundwater cleanup is 45 to 85 years.  The time to achieve soil
       cleanup is approximately 11 yean. Regular groundwater and soil vapor monitoring will be
       conducted.

153    Siemens / Intersil Off-Site Area The selected remedy for the Siemens / Intersil off-site area is
       Alternative No. 3. Alternative No. 3 consists of groundwater extraction from three B-zone
       extraction wells  and groundwater treatment  Groundwater would be pumped from wells LQ-
       1B, LQ-2B and S-2B. C-zone groundwater would be captured by pumping LQ-1B and LQ-
       2B. If C-zone groundwater concentrations do not show a reduction during the  first one year
       period, and if sufficient C-zone capture is not demonstrated, RK-2C will be converted into a
       C-zone extraction weJL

                                            10

-------
       Groundwater cleanup levels are federal or state MCLs (proposed or adopted) or RDWALs.
       The final cleanup levels for the suite of chemicals detected in the B-zone. equate to a future
       use scenario risk level for groundwater ingestion  and inhalation of VOCs of 1 x 1CH.
       Groundwater treatment will be accomplished by air- stripping with subsequent discharge to
       Calabazas Creek and  possible partial reuse and reclamation on-site.  Regular groundwater
       monitoring will  be completed  The  estimated time to achieve groundwater  cleanup is 20  to
       45 years.

15.4.   Uncertainty in Achieving Geanup Goals  The goal of this remedial  action is to restore
       groundwater to  its beneficial uses  Based on information obtained during the RI and on a
       careful analysis  of all remedial alternatives, the Board believes that the selected remedy will
       achieve this goal  However, studies suggest that  groundwater extraction and treatment will
       not be, in all cases, completely successful  in reducing contaminants  to health-based levels in
       the aquifer zones.  The Board recognizes  that operation of the selected extraction and
       treatment system may indicate the technical impracticability of reaching health-based
       groundwater quality standards using this  approach.  If it becomes apparent, during
       implementation  or operation of the system, that contaminant levels have ceased to decline
       and are remaining constant at levels higher than the remediation goal, that goal and the
       remedy may be  reevaluated.

       The selected remedy will include groundwater extraction for a period of 45 to 85 years,
       during which tine system's performance will be carefully monitored  on a regular basis and
       adjusted as  warranted by  the performance data collected during operation.  Modifications
       may include:

              a) discontinuing operation of extraction wells in areas where cleanup standards have
              been attained;

              b) alternating pumping at wells to eliminate stagnation points; and

              c) pulse  pumping  to allow aquifer equilibration and encourage adsorbed
              contaminants  to partition into groundwater.

155.   Change to the RI/FSs The RVFSs state that State Board Resolution 68-16, 'Statement of Policy
       with Respect to  Maintaining High Quality Waters in California/ is a To Be Considered"
       requirement The RI/FSs are hereby changed to state that Resolution 68-16 is an ARAR.

16.     Remedy Selection Rationale and Statutory Determinations The selected remedies are
       protective of human health and the environment  Groundwater contamination is treated so
       that the remaining potential future risks fall within the 10* to 10* carcinogenic risk range for
       acceptable cleanup levels.  The remedies comply with ARARs by achieving cleanup to at least
       Federal  and State MCLs (proposed or adopted) or RDWALs.  Soil is remediated to a level
       that wfll protect groundwater from future solvent contamination.

       The selected remedies are cost effective in achieving the required cleanup levels.  Siemens'
       on-site alternative No, 5 and Intersil's on-site alternatives No. 4 and 5 are more costly and
       these alternatives could have potentially spread the soil pollution further through
       groundwater injection or sofl vapor extraction at the periphery of the soil pollution.  The
       potentially shorter deanup times of these  more costiy alternatives does not justify their
       selection based on the potential problems associated with these alternatives. Intersil's on-site
       alternative No. 5 is too costiy to justify the additional slurry wall control and the large scale
       sofl excavation.  Off-site alternatives No. 4 and No. 5 are more costiy than off-site alternative
       No. 3. Off-site alternatives No. 4 and 5 may potentially draw groundwater deeper from  the

                                              11

-------
       •B-zone to the C-zone due to C-zone pumping and would also be more disruptive to the  >
       neighborhood due to additional trenching and construction activities.  Alternative No. 3 has
       been modeled to capture the off-site B-zone plume and a significant portion of groundwater
       containing concentrations greater than MCLs. For these reasons, alternative No.  3 was
       selected  The alternatives for cleanup to background concentrations were not selected
       because of the increased time and  cost necessary to achieve background concentrations and
       because of the need to minimize groundwater pumping and conserve groundwater supplies.

       The selected remedies are effective in the short-term with cleanup times for soil of 5 years to
       11 years and in groundwater from 45 years to 85 years.  The selected remedies are effective
       in the long-term by virtue of the fact that ARARs are achieved  Soil vapor extraction and
       treatment and groundwater  extraction  and treatment are permanent solutions and
       significantly reduce pollutant toxicity, mobility and volume at the site.  The selected off-site
       alternative. No.  3, will not require  the approximately 1000 feet of street trenching and piping
       that would be required by alternative No. 4.  All of the alternatives are implementable,  EPA
       has preliminarily approved the selected remedy.

       Treatment is used as  a principal element for the remedies.  Emissions from soil vapor
       extraction  will be treated by vapor phase carbon adsorption with the carbon canisters being
       regenerated off-site.  Emissions from air stripping towers will meet local air district
       requirements, which are anticipated to be less than a 10* risk level, or will be required to
       implement vapor phase carbon treatment

17.     NFDES Discharge  The extracted groundwater is treated by air stripping and then discharged
       to a storm sewer system tributary to Calabazas Creek. Currently, approximately  35,000
       gallons per day (gpd) of groundwater is discharged by Siemens  under NPDES Permit
       #CA0029190 and 2,000 gpd is discharged by Intersil  under NPDES Permit * CA0029261
       Calabazas Creek is tributary to South San Francisco Bay.  Intersil's permit expires on
       October 21, 1991  Siemens'  permit expires on April 1, 1991 The dischargers must file a
       Report of Waste Discharge in accordance with Title 23, Code of California Regulations, not
       later than  180 days in advance of the expiration date as application for issuance  of new
       waste discharge requirements.

18.     Cleanup Standards The groundwater cleanup standards for the site are Environmental
       Protection Agency (EPA) MCLs (proposed or adopted), California Department of Health
       Services (DHS) MCLs (proposed or adopted), DHS RDWALs. The soil cleanup standards  are
       1 ppm  total VOCs and 10 ppm  total SOCs.  These cleanup standards are defined in
       Specification B.4.

       Groundwater extraction will continue until drinking water quality is achieved, if feasible. If
       these standards  are determined to be infeasible, groundwater extraction shall continue as
       long as significant quantities of chemicals are being removed through groundwater extraction.
       Achieving drinking water quality is an ARAR for this site.  If drinking water quality cannot
       be achieved, the dischargers must demonstrate to the satisfaction of the Regional Board that
       the conditions for waiving an ARAR are  met (e.g., that meeting  the ARAR is technically
       impracticable from an engineering  perspective) and that the alternative proposed will be
       protective of human health and the environment  The Order will then need to be modified
       by the  Regional Board and approved by EPA to allow a less stringent groundwater cleanup
       level

19.     Risk Associated  With Cleanup Standards   The selected remedy is protective of human health
       and the environment - as required by Section 121 of CERCLA - in that pollution in
       groundwater is  treated to at least maximum contaminant levels (MCLs) and falls within

                                             12

-------
       EPA's acceptable carcinogenic risk range and sttncarcinogenic hazard index range.  EPA
       considers a carcinogenic risk range of I04 to 10* as an acceptable cleanup level  If the
       noncarcinogenic hazard index is less than one. EPA considers the combined intake of
       chemicals unlikely to pose a health risk.

       The carcinogenic risk at the cleanup  levels associated with the potential future me scenario
       of groundwater ingestion and inhalation of VOCs from grbundwater ranges fro» 1 x 104 to
       17 x 10* for the on-ote and off-site areas,  in cleaning up TCE to the 5 ppb cleanup
       standard, it is quite likely that the concentrations of other VOCs will be reduced to levels in
       the 5 ppb range. These risks were calculated using a potential future use scenario with a 30
       year duration exposure.
                                                         '                 •  *
       In the Ozone, there has been no PCE detected; 1,1-dlchJoroethene (1,1-DCE) was detected at
       1 ppb, and TCE was detected at 17 ppb as of the  May 11,1990 sampling event  Using the
       cleanup level of 5 ppb TCE and assuming that 1,1-DCE will be reduced to the detection limit
       of 0.5 ppb, the concentrations of 5 ppb TCE and 05 ppb 1,1-DCE equate to a carcinogenic
       risk of 13 x 10* using  the ingestion and inhalation pathways. This is 0.13 times less than
       the 10* risk level and 13 times greater than the 104 risk level
                                                  , fs.
       The noncancer hazard  indices associated with the  cleanup levels range from 0.0 to 0.4 for the
       on-site and off-site areas.  The method and assumptions used to obtain the Carcinogenic  Risk
       and the Hazard Index  associated with the deanup standards are contained in the RI/FS and
       the BPHE. The deanup standards for the site are protective of human health, have a
       carcinogenic risk that falls within a range of 10* to 10*, and a hazard index of less than  one.

20.     future Changes to Cleanup Standards  If new information indicates cleanup standards cannot
       be attained or can be surpassed, the  Board and EPA will  decide if further final deanup
       actions, beyond those completed, shall be implemented at this Site. If changes in health
       criteria, administrative  requirements, site conditions, or remediation efficiency occur, the
       discharger will submit  an evaluation of the effects of these changes on deanup standards as
       defined in Specification B.4.
         4
       The Regional Board recognizes that the discharger has already performed extensive
       investigative and remedial work onsite and that the discharger is being ordered hereby to
       perform additional remedial tasks.  It is in the public interest to have the  discharger
       undertake such remedial actions promptly and without prolonged litigation or the
       expenditure of public funds. The Regional Board recognizes (hat an important element in
       encouraging the discharger to Invest  substantial resources in undertaking such remedial
       actions is to provide the discharger with reasonable assurances that the remedial actions
       called for in this Order will be  the final remedial  actions required to be undertaken by the
       discharger. On the other hand, the Regional  Board also recognizes its responsibility to
       protect water quality, public health, and the environment and that future  developments could
       indicate that some additional remedial actions may be necessary.

       The Regional Board has considered and balanced these important considerations, and has
       determined that the remedial actions  ordered herein represent the Regional Board's best,
       current judgement of the remedial actions to be required of the discharger. The Regional
       Board will not require  the discharger to undertake additional remedial actions with respect to
       the matters previously  described herein unless: (1) conditions on the site, previously
       unknown to the Regional Board, are discovered after adoption of this Order, or (2) new
       information is received by the Regional Board, in  whole or  in part after the date of this
       Order, and these previously unknown conditions or this new information indkates that the
       remedial  actions required in this Order may not be protective of public health and the

                                              13

-------
        environment  The Regional Board will also consider technical practical^, cost effectiveness,
        State Board Resolution No. 68-16 and other factors evaluated by the Re£bnal Bovd in
        issuing this Order in determining whether such additional remedial actions are appropriate
        and necessary.

21.     Groundwater Conseivan'on Siemens and Intersil have considered the fusibility of
        reclamation, reuse, or discharge to a publicly owned treatment works (fOTW) of treated,
        extracted groundwater, as specified in  Board Resolution No. 88-160.  Ike Cry of Cupertino
        will not accept the discharge of treated groundwater for remediation pvposes n*> their
        sanitary sewer system.  Regarding on-tite process water reuse, the Inteofl facility is no longer
        operating and the Siemens facility process would  consume a small percentage of the extracted
        groundwater.  Both properties are mostly paved and use small amounts of irrigsf on water.
        Groundwater reinjection was evaluated but was determined to have the potential  to spread
        VOCs in the vadose zone, that fouling or dogging of the injection well may occur and was
        costly to implement  Capital costs for  reinjection  were $286/100 versus $11,000 for discharge
        to Calabazas Creek.  Irrigation or reuse is presently being further evaluated.

        Calabazas Creek is generally a dry creek bed in the area of the treated effluent dbcharge.  It
        appears that all the groundwater discharge is currently being naturally recharged through
        Calabazas Creek.  The  companies are currently completing a recharge study of Calabazas
        Creek which will be submitted on October 30, 1990.  This report will ako evaluate off-site
        irrigation and  reuse.

22.     Community Involvement  An aggressive Community Relations program has beea ongoing  for
        ail Santa Clara Valley Superfund sites, including the Intersil/Siemens site. The Board
        published a notice in the San Jose Mercury News, the Santa Clara Weekly and tie Valley
        journal on June 13, 1990, announcing the proposed final RAP and opportunity far public
        comment at the Regional Board Public Hearing of June 20, 1990 in Oakland. A presentation
        of the final cleanup plan was made at the June Board Hearing.  The 30 day cement period
        was from June 13, 1990 to July 13, 1990.  The June 13, 1990 notice also announced an
        evening public meeting held at the Laurelwood Elementary School in Ac Cry of Santa Clara
        on 'June 21, 1990.  A presentation  on the final cleanup plan was  also s*ade at the June 21,
        1990 public meeting. Public comment  did not generate any significant changes to the
        proposed plan.

        Fact Sheets were mailed to interested residents, local government officials, and stedia
        representatives. Fact Sheet 1, mailed in July 1989, summarized the pollution problem, the
        results of investigations to date, and the  interim remedial actions. Fact sheet 2, mailed in
       January 1990, provided written answers to questions from the public asked at the September
        27,  1989 community meeting.  Fact Sheet 3, mailed on June 7, 1990,  described the cleanup
        alternatives evaluated, explained the proposed final RAP, announced opportunities for public
        comment at the Regional Board Hearing of June 20, 1990 in Oakland and the Public Meeting
        of June 21, 1990 in Santa Can, and described the availability of further information at the
        Information Repository at the Sunnyvale Public Library.

       Fact Sheet 4, to be mailed in October 1990, will explain the final  adopted cleans? plan
        contained in this Order.
23.     Stare Board Resolution 68-16. "Statement of Policy with Respect to Mftjnftipjf g High Quality
       Waters in California*  On October 28, 1968, the State Water Resources Control Board adopted
       Resolution No. 68-16, "Statement of Policy with Respect to Maintaining High Quality Waters
       in California*. This policy calls for maintaining the existing high quality of Sttr waters
     •  unless it is demonstrated that any change would be consistent with the maxinun public

                                             14

-------
       benefit and not unreasonably affect beneficial uses,  the origBsJ discharge of waste to the
       groundwater at this Site was in violation of this policy, therefcse, the groundw*rr quality
       needs to be restored to its original quality to the extent reasceafele. For the purpose of
       establishing cleanup objectives, the shallow groundwater at the site is designated a potential
       source of drinking water.  The FS included alternatives that eashuted cleanup to background
       or non-detect levels.  These alternatives greatly increased the fce required to reach cleanup
       levels. For example, the Siemens on-site groundwater cleanup toe increased fmn
       approximately 85 yean to 450 yean.  Cleanup of groundwater to below the MCL for TCE
       may be unachievable due to the  difficulties in restoring aquifcss to concentratkm below 5
       ppb for any VOC  This is due to tile slow desorption of VOCs adsorbed  to the inner pore
       spaces of soil partides which make up the aquifer and VOCs adsorbed to clays and organic
       matter in the aquitard For this  reason, the MCLs were accepted as concejttraliDns that meet
       the intent of Resolution 68-16.

24.    Data Validation Development of the Board's final Remedial Action Plan was based on the
       Board's evaluation of eight yean of water and  soil quality data.  Random samples have been
       collected and analyzed by the Board to confirm the validity of data generated by the
       dischargers.  Data has been validated using EPA validation gvdance.  The Board finds that
       there is sufficient acceptable data to make cleanup decisions.

25.    Lead Agency  Pursuant to the South Bay Multi-Site Cooperative Agreement and the South
       Bay Ground Water Contamination Enforcement Agreement, estered into on May 2, 1985 (as
       subsequently amended) by the Regional Board, EPA and DHS. the Regional Board has been
       acting as  the lead agency. EPA is expected to  agree with the selected remedy and. issue  a
       Record of Decision following adoption by the Regional Board of the remedial action plan.
       The Regional Board will continue to regulate the dischargers' remediation and administer
       enforcement actions inaccordance with CERCLA as amended by SARA, the Caifomia Water
       Code, Health and Safety Code, and regulations adopted there under.

26.    Administrative Record The Administrative Record has been prepared in accordance with EPA
       Guidance, has been made available for public and PRP review, and provides the backup
       documentation  for the recommendations of staff and decisions by the Board

27.    Siemens and Intersil  are responsible parties under the federal Superfund (CERCLA/SARA).
       The Siemens and Intersil properties are jointly proposed as a  Superfund site  c* the National
       Priorities List

28.    This Order is written as a joint Order for Siemens and Inters!] because the groundwater
       pollution  plumes from both Companies have commingled in the A-zone and because tine two
       properties are proposed as one site on the National  Priorities  List  Siemens aad Intersil are
       encouraged to submit joint reports.  If joint reports are not coordinated and  admitted, each
       company  is still individually responsible for die joint tasks in this Order.

29.    Siemens Components, Inc. (hereinafter referred  to as a discharger) is a discharger because of
       the releases of chemicals that have resulted from its waste handling facilities. Intersil
       (hereinafter referred to as a discharger) is a  discharger because of the releases of chemicals
       that have resulted from its waste handling facilities.  Vallco Park, Ltd (hereinafter referred to
       as a discharger) is a  discharger because it is the current owner of the property where these
       releases have occurred

30.    The selected remedial action plan for the Siemens and Intersil Site was choseat in accordance
       with the Health and Safety Code Section 25356.1, the Comprehensive Environmental
       Response, Compensation, and Liability Act (CERCLA), as amended by the Superfund

                                             15

-------
        Amendments and Reauthorization Act (SARA), the National Oil and Hazardous Substances
        Pollution Contingency (NCP), and pursuant to the Multi-Site Cooperative Agreement This
        decision is based on the administrative record for the site.

31.     The Board adopted a revised Water Quality Control Plan for the San Francisco Bay Basin
        (Basin Plan) on December 17, 1986.  The Basin Plan contains water quality objectives and
        beneficial uses for South San Francisco Bay and contiguous surface and groundwaters.

32.     The existing and potential beneficial uses of the groundwater underlying and adjacent to the
        facilities include:

        a.      Industrial process water supply
        b.      Industrial service water supply
        c      Municipal and Domestic water supply
        d      Agricultural water supply

33.     The dischargers have caused or permitted, and threaten to cause or permit waste to be
        discharged or  deposited where it is  or probably will be discharged to waters of the State and
        creates or threatens to create a condition of pollution  or nuisance.

34.     This action is  an order to enforce the laws and regulations administered by the Board   This
        action is categorically exempt from  the provisions of the CEQA pursuant to Section 15321 of
        the Resources  Agency Guidelines.
                                                                              i
35.     This Order supersedes and rescinds the Intersil, Siemens and Vallco Park, Ltd. Order No. 89-
        038.

36.     On-site  and off-site containment and cleanup measures need to be implemented to alleviate
        the threat to the environment posed by the continued migration of the groundwater plume
        of organic solvents.

37.     The Board has notified the dischargers and interested agencies and persons of its intent
        under California Water Code Section 13304 to prescribe Site Qeanup Requirements for the
        discharge and  has provided them with the opportunity for a public hearing and an
        opportunity to submit their written views and recommendations.

38.     The Board, in  a public meeting, heard and considered all  comments pertaining to the
        discharge.

IT IS HEREBY ORDERED, pursuant to Section 13304 of the California Water Code and Section
25356.1  of the California Health and Safety  Code, that Siemens Components, Inc. and Intersil, Inc.
and Vallco Park, Ltd. shall cleanup and abate the effects described in the above findings as follows:

A,      PROHIBITIONS

        1.     The discharge of wastes or hazardous materials in a manner which wffl degrade
              water quality or adversely affect the beneficial uses of the waters of the State is pro-
              hibited.

        2.     Further significant migration of pollutants through subsurface transport to waters of
              the State is prohibited

        3.     Activities associated with the subsurface investigation and cleanup which will cause

                                              16

-------
               significant advene migration of pollutants are prohibited.

B.      SPECIFICATIONS

        1.      The storage, handling, treatment or disposal of toil or groundwater containing
               pollutants shall not create a nuisance as defined in Section 13060(m) of the California
               Water Code.

        2.      The dischargers shall  conduct monitoring activities as determined by the Executive
               Officer to define the current local hydrogeologic conditions, and the lateral and
               vertical extent of soil and groundwater pollution. Should monitoring results  show
               evidence of plume migration, additional characterization of the pollutant plume may
               be required.

       3.      All Siemens and Intersil wells shall be used to determine if cleanup standards have
               been met

       4.      Final cleanup standards for all onsite and off-site wells shall not be greater than the
               levels as provided in Finding 18.  The numerical final cleanup standards, therefore,
               shall not exceed the following in any well as set forth in the Self-Monitoring Plan:
Chemical
Groundwater Cleanup Standard
Basis
1989-90 Location
Max.(4)
POTENTIAL CARCINOGENS

1,1-Dichloroethylene (1,1-DCE)
Trichloroethylene (TCE)
Tetrachlorpethylene (PCE)
                     6
                     5
                     5
              59
              4700
              5
       LF-4A
       LF-6A
       W21A
NONCARCINOGENS

1,2-dichloroethylene (1,2-DCE)
       cis
       trans
1,1,1-trichloroethane (1,1,1-TCA)
Freon 113
Toluene
                     6
                     10
                     200
                     1,200
                     100-
1
1
1
1
2
3000   G-1A
NA(5)
700    3-DD
73     W19B
93     KB-1B
              1 -    California State Maximum Contaminant Level (MCL) for Drinking Water
                     (proposed or adopted).
              2 -    California State Recommended Drinking Water Action Level.
              3 -    California State Proposed MCL
              4 -    1989-90 Maximum Concentration Levels (ug/I).
              5 -    Not Analyzed
                     If Ac State of California proposes or adopts a MCL for toluene, the MCL
                     shall at that time become the cleanup standard to toluene at this  Site.
                                             17

-------
4.1    The soil cleanup standards are 1 ppm total VOCs and 10 ppm total SOCs.

5.     The discharger shall implement the final cleanup plan described in Finding 15.

6.     Final chemical concentrations shall not be found to exceed the appropriate cleanup
       level based on quarterly analytical results.

PROVISIONS

1.     Siemens and Intersil shall submit to the Board acceptable monitoring program reports
       containing results of work performed according to  a the attached •elf-monitoring
       program prescribed by the Board's Executive Officer.

2.     This Order supersedes and rescinds the Intersil, Siemens and Vallco Park, Ltd. Order
       No. 89-038.

3.     Siemens and Intersil shall comply with Prohibitions A.I., A3. and A3., Specifications
       B.I. and B.2. and Provisions Cl and C2 above immediately, except as modified in
       accordance with the time schedule and tasks below.  Within 60 days of the Executive
       Officer's determination and actual notice to Vallco  Park, Ltd. that Siemens and/or
       Intersil have failed to comply with Prohibitions A.1, A2 and A3, Specifications B.I
       and B.2 and Provisions Cl and C2 of this order, Vallco Park, Ltd., as landowner,
       shall comply with these paragraphs and with the tasks below.

COMPLETION DATE/TASK

SIEMENS VADOSE ZONE AND A-ZONE ON-SITE AREAS

Siemens is responsible for the following tasks a. through f.

a. /    COMPLETION DATE October 30, 1990

       TASK: GROUNDWATER REUSE AND RECLAMATION: Submit a technical report
       acceptable to the Executive Officer containing the groundwater reuse and reclamation
       plan for the treated groundwater.  The report shall include documentation of efforts
       to reuse the water, efforts to secure users for the water, and reasons why potential
       users would not accept the water and discuss the technical feasibility and cost-
       effectiveness of other water reuse options.  The report shall also include an
       evaluation of the recharge capacity of Calabazas Creek.

b.     COMPLETION DATE: May 31, 1991

       TASK: START UP OF EXPANDED REMEDIAL ACTION PLAN: Submit a technical
       report acceptable to the Executive Officer containing the start  up report for the final
       remedial action plan. This report shall contain the final construction schedule for the
       time period from adoption of this order through submittal of the startup  report, as-
       built construction drawings of the system, and the first two weeks of monitoring
       data.

c     CURTAILING SOIL VAPOR OR GROUNDWATER EXTRACTION

1)     COMPLETION DATE: 90 days prior to proposed curtailment of any soil vapor or

                                     18

-------
       groundwater extraction well or treatment system

       TASK- ONSITE WELL PUMPING CURTAILMENT CRITERIA AND PROPOSAL
       Submit a technical report acceptable to the Executive Officer containing a proposal
       for curtailing pumping from any onsite groundwater or vapor extraction well(s) and
       the criteria used to justify such curtailment  This report shall include data to show
       that groundwater or soil cleanup standards for all VOCs have been achieved and
       pollutant levels have stabilized or ire stabilizing, and that the potential for pollutant
       levels rising above cleanup standards is minimal.

       If the discharger daims that it is not feasible to achieve cleanup standards, the report
       shall evaluate the alternate standards that can be achieved

2)     COMPLETION DATE; 60 days after the Board approves onsite curtailment

       TASK:  IMPLEMENTATION OF ONSITE CURTAILMENT:  Submit a technical report
       acceptable to the Executive Officer documenting completion of the necessary tasks
       identified in the technical  report submitted for Task cl). Tasks cl) and c2) may be
       incorporated in the quarterly reports specified in Provision  C9 of this Order.

d.     COMPLETION DATE: July 31, 1995

       TASK: FIVE-YEAR STATUS REPORT AND EFFECTIVENESS EVALUATION.  Submit
       a technical report acceptable to the Executive Officer containing die results of any
       additional investigation; an evaluation of the effectiveness of installed final cleanup
       measures and cleanup costs; additional recommended measures  to achieve final
       cleanup objectives and standards, if necessary;  a comparison of previous expected
       costs with the costs incurred and projected costs necessary  to achieve cleanup
       objectives and standards*, and the tasks and time schedule necessary to implement
       any additional final cleanup measures. This report shall also describe the reuse  of
       extracted  groundwater and evaluate and document the cleanup of polluted soil and
       groundwater.  If safe  drinking water levels have not been achieved onsite and are
       not expected to be achieved through continued groundwater extraction and/or soil
       remediation, this report shall also contain  an evaluation addressing whether it is
       technically feasible to achieve drinking-water quality, and if so, a proposal for
       procedures to do so.

e.      COMPLETION DATE: 90 days after  request  made by the Executive Officer

       TASK: EVALUATION OF NEW HEALTH  CRITERIA. Submit a technical  report
       acceptable to the Executive Officer which  contains an evaluation of how the final
       plan and cleanup standards would be affected, if the concentrations as listed in
       Specification B.4. change as a result of promulgation of drinking water standards,
       maximum contaminant levels or action levels or other health based criteria.

f.      COMPLETION DATE: 90 days after request made by the Executive Officer

       TASK: EVALUATION OF NEW TECHNICAL INFORMATION.  Submit a technical
       report acceptable to the Executive Officer which contains an evaluation of new
       technical and economic information which indicates that cleanup standards or
       cleanup technologies in some areas may be considered for  revision. Such technical
       reports shall not be required unless the Executive Officer or the Board determines
       that such new information indicates  a reasonable possibility that the Order may need

                                     19

-------
             to be changed under the criteria described in Finding 20.

5.      INTERSIL VADOSE ZONE AND A-ZONE ON-SITE AREAS

       Intersil is responsible for the following tasks a. through f.

       a.     COMPLETION DATE: October 30, 1990

             TASK: GROUNDWATER REUSE AND RECLAMATION: Submit a»ehnaal report
             acceptable to the Executive Officer containing the groundwater raar *a* reclamation
             plan for the treated  groundwater. The report shall include doaaaatatiBR 
-------
       measures and cleanup costs; additional recommended measures to achieve final
       cleanup objectives and standards, if necessary; a comparison of previous expected
       costs with the costs incurred and projected costs necessary to achieve cleanup
       objectives and standards; and the tasks and time schedule necessary to •tplement
       any additional final cleanup measures. This report shall also describe the reuse of
       extracted groundwater and evaluate and  document the cleanup of polluted soil and
       groundwater. If safe drinking water levels have not been achieved onsite and are  not
       expected to be achieved  through continued groundwater extraction andAor soil
       remediation, this report shall also contain an evaluation addressing whether it is
       technically feasible to achieve drinking-water quality, and if so, a  propocal for
       procedures to do so.
                                                               •  *
e.     COMPLETION DATE: 90 days after request made by the Executive Officer

       TASK: EVALUATION OF NEW HEALTH CRITERIA. Submit a technical report
       acceptable to the Executive Officer which contains an evaluation of how the final
       plan and cleanup standards would be affected, if the concentrations as fsted in
       Specification B.4. change as a result of promulgation  of drinking water standards,
       maximum contaminant levels or action levels or other health  based criteria.

f.     COMPLETION DATE: 90 days after request made by the Executive Officer

       TASK 15: EVALUATION OF NEW TECHNICAL INFORMATION.  Submit a technical
       report acceptable to the Executive Officer which contains an evaluation of new
       technical and economic information which indicates  that cleanup standards or
       cleanup technologies in some areas may  be considered for revision.  Such technical
       reports shall not be required unless the Executive Officer or the Board determines
       that such new information indicates a reasonable possibility that the Order may need
       to be changed under the criteria described in Finding 20.

SIEMENS B-ZONE AND DEEPER ZONES ON-SITE AREAS  AND B-ZONE AND DEEPER
ZONES OFF-SITE DOWN GRADIENT AREAS
INTERSIL B-ZONE  AND DEEPER ZONES ON-SITE AREAS AND B-ZONE AND DEEPER
ZONES OFF-SITE DOWN GRADIENT AREAS
INTERSIL AND SIEMENS  OFF-SITE A-ZONE

Siemens and Intersil are responsible for the following  tasks a. through f.

a.     COMPLETION DATE: October 30,1990

       TASK: GROUNDWATER REUSE AND RECLAMATION: Submit a technical report
       acceptable to the Executive Officer containing  the groundwater reuse and reclamation
       plan for the treated groundwater.  The report  shall include documentation of efforts
       to reuse the water, efforts to secure users for the water, and  reasons why potential
       users would not accept the water and discuss  the technical feasibility and cost-
       effectiveness of other water reuse options.  The report shall also include an
       evaluation of the recharge capacity of Calabazas Creek.

b.     COMPLETION DATE May 31,1991

       TASK: START UP OF EXPANDED REMEDIAL ACTION PLAN: Submit a technical
       report acceptable to the Executive Officer containing  the start up  report for the final
       remedial action plan. This report shall contain the final construction schedule for the

                                     21

-------
        time period from adoption of this order through submittal 6f the startup report, as-
        built construction drawings of the system, and the first two months of monitoring
        data.

 c      COMPLETION DATE; March SI, 1992

        TASK:  EVALUATE C-ZONE GROUNDWATER EXTRACTION: Submit a technical
        report  acceptable to the  Executive Officer containing an evaluation of the
        effectiveness of the C-zone extraction system including determination of fee C-zone
        capture area based on field data and presentation of C-zone water chemistry data.
        Propose a construction schedule for a C-zone extraction well and piping, if necessary.

 d.      CURTAILING SOIL VAPOR OR GROUNDWATER EXTRACTION "

 1)      COMPLETION DATE: 90 days prior to proposed curtailment of any soil vapor or
        groundwater extraction well  or treatment system

        TASK:  WELL PUMPING CURTAILMENT CRITERIA AND PROPOSAL  Submit a
        technical  report acceptable to the Executive Officer containing a proposal for
        curtailing pumping from the extraction well(s) and the criteria used to justify such
        curtailment  This report shall include data to show that groundwater or soil cleanup
        standards for all VOCs have been achieved and pollutant levels have stabilized or are
        stabilizing, and that the potential for pollutant levels rising above cleanup standards
        is minimal

        If the discharger claims  that it is not feasible to achieve cleanup standards, the report
        shall evaluate the alternate standards that can be achieved.

2)      COMPLETION DATE; 60 days after the Board approves onsite curtailment

   -     TASK-  IMPLEMENTATION  OF CURTAILMENT:  Submit a  technical report
  ,      acceptable to the Executive Officer documenting completion of the necessary tasks
        identified in  the technical report submitted for Task dl).  Tasks d.1) and d.2) may be
       incorporated  in the quarterly reports specified in Provision C9 of this Order.

e.     COMPLETION DATE: July 31,1995

        TASK  FIVE-YEAR STATUS REPORT AND EFFECTIVENESS EVALUATION. Submit
       a technical report acceptable to the Executive Officer containing the results of  any
        additional investigation;  an evaluation of the effectiveness of installed final cleanup
       measures and cleanup costs; additional recommended measures to achieve final
       cleanup objectives and standards, if necessary; a comparison of previous expected
        costs with the costs incurred and projected costs necessary to achieve cleanup
       objectives and standards; and the tasks and time schedule necessary to implement
       any additional final cleanup measures. This report shall also describe the reuse of
       extracted  groundwater and evaluate  and document the cleanup of polluted soil and
       groundwater. If safe drinking water  levels have not been achieved onshe and  are not
       expected to be achieved  through continued groundwater extraction and/or soil
       remediation, this report shall also contain an evaluation addressing whefter it is
       technically feasible to  achieve drinking-water quality, and if  so, a  proposal for
       procedures to do so.
                                     22

-------
       f.      COMPLETION DATE: 90 days, after request made by the Executive Officer

              TASK: EVALUATION OF NEW HEALTH CRITERIA, Submit a technical report
              acceptable to the Executive Officer which contains an evaluation of how the final
              plan and cleanup standards would be affected, if the concentrations as listed in
              Specification 6.4. change as a result of promulgation of drinking water standards,
              maximum contaminant levels or action levels or other health based criteria.

       g.     COMPLETION DATE: 90 days after request made by the Executive Officer

              TASK: EVALUATION OF NEW TECHNICAL INFORMATION.  Submit a technical
              report acceptable to the Executive Officer which contains an evaluation of new
              technical and economic information which indicates that cleanup standards or
              cleanup technologies in come areas may be considered for revision. Such technical
              reports shall not be required unless the Executive Officer or the Board determines
              that such new information  indicates a reasonable possibility that the Order may need
              to be  changed under the criteria described in Finding 20.

7.      The submittal  of technical reports evaluating immediate, interim and final  remedial measures
       will include a projection of the cost effectiveness, benefits, and impact on public health,
       welfare, and environment of each alternative measure.  The remedial investigation and
       feasibility study shall be consistent with the guidance provided by Subpart F of the National
       Oil and Hazardous Substances Pollution Contingency Plan (40 CFR Part 300>, Section 25356.1
       (c) of the California Health and Safety Code, CERGLA guidance documents with reference to
       Remedial Investigation, Feasibility Studies, and Removal Actions-, and the State Water
       Resources Control Board's Resolution No. 68-16,  'Statement of Policy with  Respect to
       Maintaining High Quality of Waters in California".

8.      If the dischargers are delayed, interrupted or prevented from meeting one or more of the
       completion dates specified in this Order, the dischargers shall promptly notify the Executive
       Officer and the Board may consider revision to this Order.
          4
9.      Technical reports on compliance with the Prohibitions, Specifications, and  Provisions of this
       Order shall be submitted monthly to the Board commencing on October 15, 1990 and
       covering the previous month.  On a monthly basis thereafter, these reports shall consist of a
       letter report that, (1) summarizes work completed since submittal of the previous report, and
       work projected to be completed by the time of the next report, (2) identifies any obstacles
       which may threaten compliance with the schedule of this Order and what actions are being
       taken to overcome these obstacles, and (3) includes, in  the event of non-compliance with
       Provision G3.  or any other Specification or Provision of this Order, written notification which
       clarifies the reasons for non-compliance and which proposes specific measures and a schedule
       to achieve compliance.  This written notification shall identify work not completed that was
       projected for completion, and shall  identify the impact  of non-compliance on achieving
       compliance with the remaining requirements of this Order.  The monthly  reports shall be
       submitted until the expanded remedial action plan startup report is submitted.

       On a  quarterly basis, quarterly reports shall include, but need not be limited to, updated
       water table and piezometric surface maps for til affected water bearing zones, soil and
       groundwater capture area maps, and appropriately scaled and detailed base maps showing
       the location of all monitoring wells and extraction wells, and identifying adjacent facilities
       and structures.  Water level measurements are not required for wells where the configuration
       of the pumping equipment does not permit the measurement to be taken.  When appropriate,
       due to new data, and upon request by the Executive Officer, new geologic data shall be

                                            23

-------
        incorporated in cross-sectional geological maps describing the hydrogeological setting of the >
        site.  Quarterly reports shall be due on the 30th day of the following month after the
        reporting period

 10.     All hydrogeological plans, specifications, reports, and documents shall be signed by or
        stamped with the seal of a registered geologist, engineering geologist or professional
        engineer.

 11.     All samples shall be analyzed by State certified laboratories or laboratories accepted  by the
        Board using approved EPA methods, where available, for the type of analysis to be
        performed.  All laboratories shall maintain quality assurance/quality control records for Board
        review.

 12.     The dischargers shall maintain in good working order, and operate, as efficiently as possible,
        any facility or control system installed to achieve compliance with the requirements  of this
        Order.

 13.     Copies of all correspondence, reports, and documents pertaining to compliance with the
        Prohibitions, Specifications, and Provisions of this Order, shall be provided to the following
        agencies:

        a.   Santa Clara Valley Water District
        b.   City of Cupertino and City of Sunnyvale
        c   U. S. Environmental Protection Agency, Region DC (H-6-3)

        The Executive Officer may additionally require copies of correspondence, reports and
        documents pertaining to compliance with the Prohibitions, Specifications, and Provisions of
        this Order to be provided to a local repository for public use.

14.     Within 60 days of the Executive Officer's determination and actual notice to Vallco Park, Ltd.
        that Siemens and/or Intersil have failed to comply with any portion of Provisions 1 through
        10, of this Order, Vallco Park. Ltd., as landowner, shall comply with these  Provisions.

15.     Siemens, Intersil and Vallco Park, Ltd. shall permit the Board or its authorized representative,
        in accordance with Section 13267(c) of the California Water Code:

         a.    Entry upon premises in which any pollution sources exist consistent with the site
              Health and Safety Plan, or may potentially exist, or in which any required  records
              are kept, which are relevant to this Order.

         b.    Access to copy any records required to be  kept under the terms and conditions of
              this Order.

         c    Inspection of any monitoring equipment or methodology implemented in response to
              this Order.

         d    Sampling of any groundwater or soil which is accessible, or may become accessible,
              as part of any investigation or remedial action program undertaken by the  discharger.


16.     Vallco Park, Ltd shall file a report on any changes in site occupancy and ownership
        associated with the facilities described in this Order.
                                              24

-------
 17.     If any hazardous substance, as defined pursuant to Section 25140 of the California Health
        and Safety Code, is discharged in or on any waters of the state, or discharged and deposited
        where it is, or probably will be discharged in or on any waters of the state, the discharger
        shall report such discharge to this Board,  at (415) 464-1255 on  weekdays during office hours
        from 8 a.m. to 5 p.m., and to the Office of Emergency Services at (800) 852-7550 during non-
        -business hours.  A written report shall be filed with  the Regional Board within five (5)
        working days and shall contain information relative to:  the nature of waste or pollutant,
        quantity involved, duration of incident, cause of spill, Spill Prevention, Control, and
        Countermeasure Plan (SPCQ in effect, if any, estimated  size of affected area, nature  of effect,
        corrective measures that have been  taken  or planned, and a schedule of these activities, and
        persons/agencies notified.

18.     The Board will review this Order periodically and may revise the requirements when
        necessary.
I, Steven R. Ritchie, Executive Officer, do hereby certify that the foregoing is a full, true and correct
copy of an Order adopted by the California Regional Water Quality Control Board, San Francisco
Bay Region, on August 15, 1990.         /- /
                                      Steven R. Ritchie
                                      Executive Officer
Attachments:
       Self-Monitoring Program
       Site Map
                                               25

-------

-------
CALIFORNIA REGIONAL WATER QUALITY CONTROL BOARD
             SAN FRANCISCO BAY REGION

             SELF-MONITORING PROGRAM

                        FOR

                Siemens Components, Inc
                 19000 Homestead Road
              Cupertino, Santa Clara County

                     Intersil, Inc
                10900 North Tantau Road
              Cupertino, Santa Clara County

                    Vallco Park, Ltd
                    P. O. Drawer V
              Cupertino, Santa Clara County


                 ORDER NO. 90 - 119

                    CONSISTS OF

                 PART A, December 1988
              As Modified by SBTD, 1/23/89
                 With Appendices A-E

                        and

             PART B, adopted August 15,  1990

-------
                                          PARTB

Siemens Components, Inc                         Intersil, Inc
19000 Homestead Road                            10900 North Tantau Ave.
Cupertino, Santa Clara County                     Cupertino,  Santa Clara County

Vallco Park, Ltd.
P. O. Drawer V
Cupertino, Santa Clara County

1   DESCRIPTION OF SAMPLING STATIONS
                                                                        • •
       All existing and future perched, A-. B-, C- and deeper rone monitoring and extraction wells
       as appropriate.  See Table 2 (attached) for list of monitoring wells.

D,  MISCELLANEOUS REPORTING.  None.

Dl SCHEDULE OF SAMPLING AND ANALYSIS

       The schedule of sampling and analysis shall be that given in  Table 1 (attached).

IV.  MODIFICATIONS TO PART A.
                                                                            i
       A.     Delete Sections B, D, E,  F.2, F3, G.1, G-4-b, G.4.e,  and G.4.g.

       6.     In Section G.2, delete the first sentence of the third paragraph:

              In addition, the waste discharger shall promptly accelerate his monitoring program to
              analyze the discharge at least once every day (Section DJLh.).

       C '   The first paragraph of Section G.4 shall be changed to read as follows:
         4
              Written reports shall be  filed with the Regional Board regularly for each calendar
              quarter (unless otherwise specified) and filed no later than the thirtieth day of the
              following month.  The reports shall be compromised of the following:

       D.     Section G.4.a.l.) shall be changed to read as follows:

              1)     Identification of  all violations of the site cleanup order and self-monitoring
                     program found during the reporting period.

       E     Insert section C4.a3) to read as follows:

              Time periods during which the soil vapor extraction system or groundwater treatment
              system was not operating for greater than one week.   Time periods during which the
              individual groundwater extraction wells were not  operating for greater than one
              week.

       F.     The first paragraph of Section G.4.4. should be changed to read as follows:

              Tabulations of the results from each required analysis specified in  Part B by date,
              type of sample and detection limit and station.  The report format will be prepared
              using the examples shown in APPENDIX B.

-------
       C.      Section C.4.d4) shall be changed to read as follows:

               4)      Lab results shall be signed by the laboratory director, copied, and submitted
                      as an appendix to the regular report

       H.      Insert Section G.4.d5) to read as follows:

               The EPA Method 8240 analyses shall include tentative identification and
               semi-quantified concentrations of non-priority pollutant substances of greatest
               apparent concentration, to be followed by identification and confirmation of peaks of
               greatest concentration.

       L       Insert a new section G.4.g. to read as follows:

               For each individual vapor extraction well, the total soil vapor extraction system and
               the groundwater extraction system: a quarterly tabulation showing the  average air
               and groundwater flow rate, the average influent air and groundwater concentration
               and; on an annual basis, estimates of the average chemical mass removal rate from
               soil and groundwater and the cumulative mass of chemicals removed from soil and
               groundwater since startup. Include the above tabulations from startup, where
               available, through the current reporting period  Include concentration and mass data
               for TCE, TCA, any other individual main constituents, and total volatile organic
               compounds. When the existing vapor extraction system design does not permit the
               measurement of air flow from an individual vapor extraction well, a suitable down
               stream sampling point may be used to estimate  air flow  for that well.

       J.       The third sentence of Section G.5 shall be changed to read as follows.

               In addition, the report shall contain a comprehensive discussion of the compliance
               record and all corrective action taken or planned which may be needed to bring the
               discharger into full compliance with the site cleanup Order and self-monitoring
               requirements.

I Steven R. Ritchie, Executive Officer, hereby certify that the foregoing Self-Monitoring Program:

       1.      Has been developed in accordance with  the procedure set forth in this Regional
               Board's Resolution No. 73-16 in order to obtain data and document compliance with
               site cleanup requirements established in Regional Board Order No. 90-119.

       2.      May be reviewed at any time subsequent to the effective date  upon written notice
               from the Executive Officer or request  from the  discharger, and revisions will be
               ordered by the Executive Officer or Regional Board

       3.      Was adopted by the Board on August 15, 1990.
       DATE                              Steven R. Ritchie
                                           Executive Officer
Attachments:   Table I
              Table D

-------
                            TABLE 1
           SCHEDULE FOR SAMPLING, MEASUREMENTS,  AND ANALYSIS
! SAMPLING STATION »»
1
I
1
1 	 . 	
j TYPE OF SAMPLE
JEPA 8010/8020 or 8010
forcpurgeable priority
pollutants
|ln addition to:
Freon 113
j Priority Pollutant
Metals
JGC/MS (EPA 8240)
Open S"can
All existing and future perched, A-,
B-, C- and deeper zone monitoring
and extraction wells as listed in
Table 2.
---.-_-.__ i
G
Q, 2/Y,
1/Y
1/Y*









 LEGEND FOR TABLE 1
 G * grab sample
 Q • quarterly
 1/Y - once per year
 2/Y » twice per year
 *  EPA  8010/8020 not  required for  quarters  when EPA  8240 is
performed.
Sampling and analysis shall be consistent with an approved QAPP.

-------
                                         TABLE 2

MONITOR ING WELLS TO BE SAMPLED AS  REQUIRED IN TABLE 1

 INTERSIL. INC.

Quarterly
W4A, W5A, W10A, W12A. E17A,

Semi-annual

W2A, W3A, W6B, W7A, W8B, W9A, WllB, W13A, W14A, W14B, WI8B

 SIEMENS COMPONENTS. INC.

Semi-annual
LF-2A, MD(P), 2-1D, 2EP, 3-DD, 3-XA, 4BP. F-1A, G-1A.  H-1A, H-2A, H-XA. LF-4A(P), LF^A. LF-9A,
T-2A*. W21A, W22A, 3-EB, H-3B, H-5B, LF-1B, LF-5B, LF^z), W19B, W20B, H-4C*

Quarterly
T-1A, LF-3B'(z)

INTERST17SIEMENS OFF-SITE STUDY AREA

Quarterly                                                                               ,
S-1A, LF-8A, RK-1B, S-3B*. S-5B, KP-1B, LS-2B, PC-IB, LH-IC*. LR-3C'. RK-2C
          4
Semi-annual
LS-1A, QH-1A, T-3A*, W15A*, W16A», PUB, S-2B, IQ-1B, IP-1B, KB-1B», KB-2B, KR-1B.LQ-2B, PH-1B,
PL-2C, S-4C, S-6C, BK-r. BK-2*. BK-3*. BK-4»

Annual
KL-1B

Note
Additional wells shall be included in Table 2 as installed

• • Only wells listed with a * shall be sampled by EPA  Method 8020.
(P) • Wells 1-1D and LF-4A shall be analyzed annually for priority pollutant metals.
(z) - Wells LF-3B and LF-7B shall be analyzed annually for zinc

Due to drought conditions, some wells have insufficient water levels and slow recovery rates.  Wells will
not be sampled if water levels are inadequate, but shall be re-incorporated into the monitoring program
if water levels recover sufficiently to permit accurate sampling.

-------
APPENDIX B

-------
SIF
•^ B Kmm
                                                     ' l   .

 July  13,  1990                                .... ^.   ' "  '••'.' , ^^^)
 By Messenger

 Mr. John Wolfenden
 California Regional Water Quality Control  Board
 San Francisco Bay Region
 1800 Harrison Street, Suite  700
 Oakland/ California  94612

 Re:  Siemens Comments on Tentative Order
      for the Intersil/Siemens  Site	

 Dear John:

 Enclosed are comments of Siemens Components,  Inc.  ("Siemens")
 on the tentative site cleanup  order  for the Intersil/Siemens
 site.  For your convenience, we have handwritten suggested
 changes on the attached copy of the  tentative order.

 Siemens has worked closely with Intersil,  Inc. in  preparation
 of these comments.  Therefore, most  comments  are joint
 suggestions of both companies.

 Please feel free to call me  if you have any questions.

 Sincerely,
 R^John Wys*, Jr.  ,
 Business and Legal Affairs Manager

 Enclosure

 cc:  Edward Firestone, Esq.
      Robert L. Bines, Esq.
Siemens Components, Inc.

Oraoeteoronics Division  19000 Homestead Road  Cupertino. California 95014  (408)257-7910

-------
 John Wolfenden
 July 13,  1990
 Page 2
     •    Intersil and Siemens have jointly revised Table 2 to
          Appendix B to more accurately reflect Intersil, Siemens
          and AMI's respective responsibilities concerning the
          sampling of designated monitoring wells.  This has
          resulted in the elimination from Table 2 of veils AMI-
          1A, AMI-2A, VM-1B, BM-1B, HS-1B and KB -IB.

     If you have any questions concerning Intersil's comments,
please do not hesitate to call me.  Thank you.
                                   Very truly yours,
                                   Edward A. Firestone
Enclosure

cc:  Steven Ritchie - RWQCB (v/o end.)
     Steve Morse - RWQCB (v/o encl.)
     Marie Lacey - EPA
     Tom Iwamura - SCVWD (w/o encl.)
     Burt Viskovich - City of Cupertino (v/o encl.)
     J.P. Mailie - city of Sunnyvale (v/o encl.)
     James Bruen - Landels, Ripley & Diamond
     Nancy Bice - Geomatrix
     John Wyss - Siemens Components, Inc.
     Karen Nardi - McCutchen,  Doyle, Brown & Enersen
     Jeff Hennier - Levine-Fricke
     Joel Nobrega - Vallco Park (v/o encl.)

-------
                            July 13, 1990
 VIA MESSENGER                                      ,
                                                     ^ ':<;,•£-
 John Wolfenden                               n."A«i-^
 Regional Water Quality Control Board         ^'•••-. / CC'.'."^>^. r.^
 San Francisco Bay Region                              	~- --^icD
 1800 Harrison Street, 7th Floor
 Oakland,  California  94612

       Re:   Intersil, Inc.'s Comments on Tentative Order No.  90-
            	, Site Cleanup Requirements for:  Siemens, Intersil
            and Vallco Park	

 Dear John:

       Enclosed is an annotated version of the captioned Tentative
 Order setting forth Intersil's comments.  These comments have
 been prepared in coordination with representatives of Siemens
 Components,  Inc. ("Siemens").  As a result, Intersil's comments
 and  suggested changes are nearly identical to those submitted by
 Siemens  (e.g..  differences may exist between the two companies'
 submissions  with respect to those portions of the Order that deal
 solely with  Intersil or solely with Siemens).
                                   (
       With  respect to Intersil's comments, we wish to highlight
 the  following points:

       •     The bullet item concerning administrative civil
            liability should be deleted (see Finding No. 3,  page
            2).

       •     The discussion regarding Intersil's acid
            neutralization systems should be deleted (SSS. Finding
            No.  4, page 2).

       •     Also with respect to the discussion of Site History,
            the Order should reflect that Intersil began interim
            remedial actions in 1986 when the inactive
            neutralization system was removed fsee Finding No. 4,
            page 2).

       •     Intersil requests that the RWQCB staff delete Finding
            15.4  from the Order for the reasons set forth in the
            May  16,  1990 letter froa Landels, Ripley & Diamond to
            Steve Morse (attached as Appendix A to Intersil's June
            1990  Feasibility Study Report), and also for the
            reasons set forth in the July 13, 1990 letter from
            John  wyss to John Wolfenden.
Intersil, ire. • Err£ar:adero Center West • 275 Battery Street 23rd Floor • S*n Francisco. CA 94111 • 41S-986-14S6 • FAX 415-986-3958

-------
State of California


Memorandum
                            x_. /•_./.'" j """ *• ^-'l  .... _
                                 "' ...... '--4.  . ._ _._


                                -Ul- •  i  ttl
                                                          Deportment of Health
10
from
Steven Ritchie, Executive Officer ~~
Regional Water Quality Control Board
1800 Harrison St., Suite 700
Oakland, CA  94612
      office of Drinking Water
      2151 Berkeley Way, Rm 458
      Berkeley, CA  94704
      8-571-2160
                                                 dc1e :  July 11,  1990

                                                 Subject:  Tentative Order
                                                    Site Clean-up
                                                    Requirements-
                                                    Intersil/ Siemens-
                                                    Proposed Superfund
                                                    Site-Santa Clara Cy
      The  subject  document  has been  reviewed  by  the Department  of
      Health  Services,   Office  of  Drinking  Water.    We  offer  the
      following comments:
           The primary  goal  in  remediation of  hazardous  waste
           sites   is  the  protection  of  public  health  and  the
           environment.    The  Office  of  Drinking  Water has  the
           responsibility  to ensure that the quality of California
           drinking water  is pure, wholesome and  potable,  that it
           meets    all   applicable   regulatory   mandates,   and
           concentrations  of foreign  toxic substances  present in
           these  drinking water  supplies do not  pose significant
           or unacceptable  health  risks to  human  health.    The
           existing  and   potential   beneficial   uses  of   the
           groundwater    underlying    and   adjacent   to    the
           Intersil/Siemens   facilities   include   municipal   and
           domestic water  supply.  Within a one mile radius of the
           site,  there  are  currently  5 active  municipal  wells
           operated by the  Cities of  Santa Clara  and  Sunnyvale.
           Our review  of  the  proposed  cleanup  operation is  to
           assure the potential  hazards associated with the  site
           will   not  jeopardize  the  integrity  of  the  affected
           groundwater  aquifers as domestic water supply sources.

           The proposed cleanup  operation includes  3 groundwater
           aquifers;  A-  ,  B-   ,  and  the  C-Zones.   The  C-Zone
           aquifer at  depths  between  180  to 210  feet,  is  an
           existing and potential domestic water supply source for
           small  water  systems  in the Santa Clara Valley.   The C-
           Zone aquifer is also  an intermediate  link between the
           shallow aquifers  in  A- and B-  Zones  to the  deeper
           aquifers from which most existing  municipal wells in
           Santa  Clara  Valley  currently draw for domestic supply
           uses .

-------
                                             Santo Clara Valley Water District
                                             5750 AIMAOEN EXPRESSWAY
                                             SAN JOSE, CALIFORNIA 95118
                                             TELEPHONE   (408) 265-5600
                                             FACSIMILE    (4081266-0271

                                             AN Af FIRMATIV! ACTON EMPIOTH
                      o
JUL  1  ~ ;::£:>
                                                                                         -^
                                                                                         •'   \
 July 13, 1990
 Mr. John Wolfenden
 Regional Water Quality Control Board
 1800 Harrison Street, Suite 700
 Oakland, CA  94612

 Dear Mr. Wolfenden:

 Subject:       Comments on Final Clean Up Proposal, Intersil/Siemens site, Cupertino, California

 This letter presents our comments on the above subject site.

 We are in general concurrence with the clean up proposal and water conservation practices proposed for
 this site.  However, we do have concerns regarding proposed clean up goals for existing or potential
 drinking water aquifers. Consistent with our Board of Director's position on clean up goals for similar
 sites, we urge you to consider setting clean up goals for carcinogenic contaminants using die Carcinogenic
 Hazard Index   Approach.  As a  dean up goal, this provides a more conservative approach when a
 multiple carcinogenic chemicals are present

We fully understand that further remediation requirements would be evaluated based on feasibility and
risk assessment evaluation.

Please call Tom Iwamura or myself at (408) 927-0710 should you have any questions.

Sincerely,
Division
Ground

-------
                                                     3>  GOULD
Gould AMI Semiconductors
2300 Buckskin Road, Pocatello. Idaho 83201
Telephone (208) 233-4690                                         l    Semiconductors
                              July 12, 1990       JUL ' 3 13£3

                                             A,i«M».rv
   Steve I. Morse'
   California Regional water Quality Control Board
   1800 Harrison Street, Suite 700
   Oakland, California  94612

   Dear Mr. Morse:

        Thank you for providing the opportunity for public comment on
   the Board's Tentative Site Cleanup Order for Siemens Components,
   Inc., Intersil,  Inc., and Vallco Park,  Ltd.   The following few
   comments are made on behalf of Gould AMI Semiconductors ("AMI").

        Item 5 refers to the extent of soil pollution east of the
   Siemens/Intersil plume.   As you know, we are completing
   investigation and undertaking interim remedial measures on our
   former site.  Our consultants advise us that complex
   hydrogeological  migration patterns exist in this area, and
   conclusiveness with respect to the results of source investigation
   may not be possible.  Nonetheless, we intend to quickly remediate
   identified elevated VOCs on our former  site.

        Item 7 refers to groundwater investigation, concluding that
   off-site plumes  appear to be defined.  We have the same concerns
   expressed above  regarding the eastern and northeastern borders of
   the Siemens/Intersil plume.  This section refers to monitoring well
   VM-lB at the far eastern extent of the  plume network, which has
   detected 10 parts per billion TCE.  This well also has detected 4
   parts per billion TCA.  Our consultants advise us that the
   combination and  levels of these VOCs appear to be attributable to
   the Siemens/Intersil plume.  Thus, we believe the order's comment
   that the elevated TCE detected at VM-lB "may be part of the AMI
   groundwater plume" is unwarranted by the data.

        Item 8 refers specifically to the  former AMI facility.  The
   source of the elevated off-site levels  discussed in this item has
   not been established, and we believe conclusiveness with respect to
   the results of source investigation may not be possible.
   Nonetheless, we  intend to quickly remediate identified elevated
   VOCs on our former site in accordance with the interim remedial
   action system referred to in this item  of the order.

-------
Steve I. Morse
July 12, 1990
Page 2
     Thank you once again for allowing us the opportunity to review
the Tentative Order and provide comment.
                              Very truly yours,
                              Dan Schroeder
                              Vice President - Fab Operations
                              and Development

-------
Steven Ritchie
Page 2
July 11, 1990
     The proposed cleanup levels for the shallow groundwater
     aquifers, designated  as  A- and  B- Zones,  to  drinking
     water  standards,  are appropriate  for  the potential
     future  use  which  will  not  include  domestic  supply
     sources.   We  also  concur  with the  proposed  cleanup
     levels  for  non-carcinogens  at  non-carcinogen  hazard
     index 1.0 for  the 3  aquifers.   However, the   proposed
     cleanup levels for carcinogens in  conjunction  with  the
     potential beneficial  use of  the C-Zone aquifer as  a
     .source of drinking water  supply  are of concern  to  the
     Department.

     The proposed remediation  levels for carcinogens for  the
     C-Zone aquifer are:
          EPA's "applicable or relevant and appropriate
          requirements  (ARARs),  which, in this  case,
          are the same as the California Drinking Water
          Standards,  and

          EPA's  10~4  to 10~6  Carcinogenic Risk  Range
          (CRR)  for carcinogens prescribed in  the "Risk
          Assessment   Guidance  For  Superfund,   Human
          Health  Risk Assessment:  US  EPA Region  IX
          Recommendations",  (EPA,  1989).


     The Department does  not support EPA's CRR of 10~4  to
     10~6 as acceptable health risk levels for  carcinogens
     in drinking  water;  instead,  we use  the  10~6  as  the
     terminus risk level whenever this level  of  protection
     can be accomplished with reasonable and  cost effective
     operation measures.    We further do not concur with the
     use of drinking water  standards as the  target  cleanup
     levels  for  contaminated  groundwaters  designated  as
     domestic   water   supply   sources,   particularly   in
     contaminated  sites   involving   multiple   chemicals.
     Multiple  chemicals-contamination  sites  present   an
     additional  dimension  of health risks because  of  the
     additive and/or  synergistic  effects  of  the  different
     component toxicants in  the  chemical  mixtures.    These
     effects are not well understood or reasonably defined.
    The   Department   fully   recognizes  that   there   are
    contaminated  groundwaters in  California  which need  to
    be  cleaned up  and where the resulting  product water
    represents  a  significant  resource  which,  in   some

-------
Steven Ritchie
Page 3
July 11, 1990
     situations,  must  be  used  for  domestic  consumption
     purposes.   For  this  reason,   in  the  remediation  of
     contaminated sites, the Department strongly recommends
     that  cleanup  should  be   at  levels  well   below  the
     drinking  water  standards,   to  the   extent  possible,
     within reasonable economic and technical  limits.   This
     recommendation is reflected in  the Department's  "Policy
     Guidance  for  Direct   Domestic  Use  of   Groundwater
     Contaminated with Toxic Substances".   Attached for your
     reference is a copy of  the Department's policy.

     We also  recommend  the  approach of  carcinogen hazard
     index (CHI)  at unity (1.0)  in setting cleanup goals for
     aquifers  used  for  domestic  water   supply  purposes,
     particularly in contamination sites  involving chemical
     mixtures.   When    chemical  mixtures  of carcinogenic
     nature are present for  which there is insufficient data
     to evaluate  the  health  effects  associated  with  the
     potential interaction among the component toxicants,  it
     is the practice of the  Department to  consider toxicants
     to be additive in action.   This additive  action may  be
     expressed as the  CHI and is  calculated as follows:


          CHI  - C!/(AAL,  AL  or  MCL)! * C2/(AAL, AL or MCL)2
                + .... + Cn/ (AAL, AL or MCL) n
     In  this equation, Cn  is the concentration  of the nth
     toxicant,  and (AAL,  AL or MCL)n  is the Applied Action
     Level,  Action Level,  or Maximum Contaminant  Level of
     the nth toxicant.

     The 1.0 CHI approach provides an additional measure of
     protection for the   surrounding environment and reduces
     the   possibility   of   chemical   contamination   of
     neighboring areas,  including the deeper aquifers which
     can  be affected  by  downward  vertical  movements of
     toxicants  from the contaminated zones. This approach is
     in keeping with the goal of the Department's Drinking
     Water Program, which is to assure that all Californians
     are provided a  reliable  supply  of safe drinking vater,
     and the California Site Mitigation  Decision Tree Manual
     (DHS, 1986), which  was  the subject of  public comment
     and scientific  peer review.  The  Decision Tree Manual
     is also consistent  with the Federal  Superfund Public
     Health  Evaluation Manual (EPA, 1986).

     In  addition,  the   groundwater  contamination  at  the
     Intersil/Siemens  site  involves high  concentrations of

-------
 Steven Ritchie
 Page 4
 July 11,  1990
      PCE,  TCE and 1,1-DCE,  among several other chemicals, in
      the  shallow aquifers.    We are  concerned  about  the
      potential migration  of these  chemicals  laterally and
      vertically throughout the surrounding deeper aquifers.
      Furthermore,  the  biotransformation  of  PCE,  TCE  in
      groundwaters to other more toxic compounds such as DCE
      and  vinyl  chloride,   which poses  additional  health
      hazards to  the  future  users of the affected aquifers,
      must  also be considered.   In the calculation  of CRR for
      Intersil/Siemens using the  ARARs  selected for  this
      site, these two issues of  potential health hazards were
      not considered.

      Under   Table   1:    ARARs   and   TBC   Criteria   for
      Intersil/Siemens in Fact  Sheet 3  dated  June 1990, the
      concentrations   for  the  following organic   chemicals:
      cis 1,2-DCE, trans  1,2-DCE, and Freon 113,   are listed
      as  "proposed MCLs".   Please be advised that  the listed
      concentrations  for  these chemicals have been  adopted as
      MCLs   effective  July  1,   1990.    Attached  for  your
      reference is a copy of all  MCLs  for organic chemicals
      currently in effect  in our Drinking Water Program.

We  appreciate  the opportunity  to provide technical  review and
evaluation  relating  to  the   water   supply  issues   of  the
Intersil/Siemens   Cleanup  Program.     We  understand  that  our
recommendation of approach on  cleanup goals differs from that as
proposed in  the  Tentative  Order.   As  discussed with  Mr. John
Wolfenden  and Mr. Steve  Morse  of your Board on several occasions
on the phone during  the past two  weeks, we do firmly believe that
the 1.0  CHI approach will provide an acceptable margin of  safety
in  the  cleanup   of  contaminated groundwaters   as  well  as  a
reasonable assurance that future  potential water  users will not
be  exposed  to  undue  public  health  risks.   If  you  have  any
questions  or would  like  to meet again to  discuss further about
this  matter,  please  do not  hesitate to contact me.
                                   Catherine S. Ling, P.E.
                                   District Engineer
                                   Monterey District
Attachments

cc: See next page,

-------
Steven Ritchie
Page 5
July 11, 1990
cc:  Santa Clara County Health Department
     Santa Clara Valley Water District
     Santa Clara County Water Retailers
          CWS-Los Altos
          City of Cupertino
          City of Gilroy
          City of Milpitas
          City of Morgan Hill
          City of Mountain View
          City of Palo Alto
          City of San Jose
          City of Santa Clara
          City of Sunnyvale
          Great Oaks Water Company
          San Jose Water Company
          Stanford University

-------
                                             September 22, 1988
         POLICY GUIDANCE FOR DIRECT DOMESTIC USE  OF
       GROUNDWATER CONTAMINATED WITH TOXIC SUBSTANCES
A.   Purpose of Guidelines

     Most  plans  for cleaning  up groundwaters contaminated with
     toxic  substances  involve  extraction  of  the  contaminated
     groundwater and  treatment to remove or reduce  the  contami-
     nants.  The treated groundwater then must "either be  disposed
     of  or reused.  In water  short areas,  this treated  ground-
     water  is  often considered  to  be a valuable  resource  which
     should not be discarded.  In a growing number of situations,
     there  is  an  interest in utilizing this water directly in  a
     domestic  water  supply distribution system.  The purpose  of
     this guidance document  is  to set forth the position  and  the
     basic tenets by which the Public Water Supply Branch (PWSB)
     would consider such a proposal.

     It  is recognized  that the circumstances   surrounding  each
     situation may be different.  Proposals,  therefore,  must  be
     considered  on  a"  case-by-case  basis.   This  document   is
     intended  to  set forth basic public health principles  which
     should be used by the PWSB  staff in evaluating proposals  and
     in establishing appropriate permit conditions for any direct
     use.

B.   General Philosophy

     The primary  goal" of the  PWSB drinking water program  is  to
     assure that  all Calif ornians  are,  to the  extent  possible,
     provided  a  reliable  supply of  safe drinking water at  all
     times.  In furtherance  of this goal,  the  PWSB  continues  to
     subscribe to the basic  principle that  only the  best quality
     sources  of  water  reasonably available  to a water  utility
     should  be used  for  drinking.   When  feasible  choices  are
     available, the  sources  presenting the least  risk to public
     health  should  be  utilized.   Furthermore,  these  sources
     should   be   protected   against   contamination.    Whenever
     possible, lower quality  source waters  should  be used  for
     nonconsumptive  uses  where  there  are lower  health  risks
     (i.e., irrigation/ -recreation, groundwater replenishment, or
     industrial uses) .

     Water utilities should be encouraged to minimize the concen-
     tration   of  toxic  substances  in drinking water   (maximum
     contaminant level  [MCL] notwithstanding)  whenever  this  can
     be accomplished with reasonable and cost effective operation
     measures.
     Where  reasonable alternatives .are available,  high
     drinking water should not be allowed to  be degraded by
     planned addition of contaminants.  In other words, the MCLS

-------
                               -2-



     should  not  be  used  to  condone  contamination up  to those
     levels  where the  addition  of those  contaminants  can  be
     reasonably avoided.

     Drinking  water  quality   and  public  health  considerations
     shall be given a greater weight than costs or cost  savings.  .

     The  PWSB recognizes  that  there  are  contaminated  ground-
     waters  in California which  need  to  be cleaned up  and where
     the  resulting   product   water  represents   a   significant
     resource which  should  not  be  wasted.   In  some  situations,
     it may  be  reasonable to  consider the  use of these  treated
     contaminated groundwaters  for  domestic use.  Some communi-
     ties nay not have any  choice.  In  such  cases,  the public
     health principles set forth in the  following section should
     be used to guide the evaluation of such situations.

C.   Principles          '

     1.   Alternative sources of drinking water reasonably
          available to a water utility should be evaluated as
          to comparative risk  (assuming MCLs are, or can be,
          met).  These risks  should be compared  to cost benefit
          and a judgement made as to the best source to  be  usea
          within reasonable cost factors.

     2.   In evaluating the relative risk comparison of
          alternative  sources/  additive   effects of   multiple
          contaminants    are     an    important    consideration.
          Generally,  consideration  of allowing  direct  reuse  of
          contaminated  groundwater  should  be  limited  to single
          toxic  contaminants   or a  limited  number  of  similar
          chemicals which can be reliably treated with the  same
          process.

     3.   Blending may be considered acceptable in lieu  of
          treatment for relatively low levels (i.e., less than
          ten times the MCL)  of contaminants which have  lower
          levels  of  associated  risk  as  long  as the  blending
          process is fully reliable and  takes  place prior to  any
          entry into the distribution system.

D.   Principles  Governing  Use   of  Significantly  Contaminated
     Groundwaters

     1.   Groundwater containing multiple  contaminants,  ground-
          waters which are likely to contain unknown contaminants
          (such as  groundwater subject  to  contamination  from
         " hazardous waste disposal site), or highly contaminate^
          groundwater should  not be considered  for direct human
          consumption where alternatives  are available.

-------
                     -3-
Where alternative sources present greater overall  risks
or  are  not  available,  and the  groundwater  contains
high   concentrations   of   contaminants   or   multiple
contaminants, the treatment process  used to treat  the
contaminated  groundwater prior to  direct usage; in  a
domestic water distribution system must be commensurate.
with the degree of risk associated  with the  contami-
nants.   As a  minimum,  treatment for relatively high
risk sources  shall  include  use  of  the best  available
treatment  technology  defined  for that contaminant  by
the Environmental Protection Agency.   Furthermore,  the
treatment processes must have full reliability features
consistent with the type  and  degree  of  contamination
in the groundwater.

The treatment process used  must be capable of reliably
producing  water meeting MCLs  in the discharge  line
from  the final  treatment process at all times.   Any
water from other sources that is available for blending
prior- to entry into the distribution system  should be
used to provide an additional safety factor.

Facilities  for treating   water containing  specific
contaminants,  for  which the  MCL is  higher  than  the
maximum  contaminant level  goal   (MCLG)  and where  the
water  is  intentionally  added   to   the  distribution
system,  should be  designed and  operated to  meet  the
MCLG where this can be accomplished in a cost effective
manner.

Projects proposing  to use  highly contaminated ground-
water as a source of  domestic water  supply  should be
subjected to  a  public hearing or meeting prior  to  the
issuance of a domestic water supply  permit,  regardless
of compliance with MCLs.

-------
64444.-5.  Maximum Contaminant Levels.

     The maximum contaminant levels  for the primary  drinking
water-constituents shown in Table  5 shall not be exceeded  in
the water supplied to the public.
                            Table 5
                  Maximum Contaminant Levels
                       Organic Chemicals
Constituent
Maximum Contami-
nant Level, mg/1
(a)  Chlorinated Hydrocarbons
     Endrin	            0.0002
     Lindane	            0.004
     Methbxychlor	.;	            0.1
     Toxaphene	            0. 005
(b)  Chlorophenoxys
     2, 4-D	            0.1
     2, 4, 5-TP Silvex	            0.01
(c)  Synthetics
     Atrazine	    0.003 •
     Bcntazon	    0.018
     Benzene	    0.001
     Carbon Tetrachlpride	    0.0005
     Carbofuran	    0.018
     Chlordane..	    0.0001
     1,2-Dibromo-3-chloropropane	    0.0002
     1, 4-Dichlorobenzene	    0.005
     1,1-Dichloroethane	    0.005
     1,,2-Dichloroethane	    0.0005
     cis-l,2-Dichloroethylene	    0.006
     trans-l,2-Dichloroethylene	    0.0.1
     1,1-Dichloroethylene	    0.006
     1,2-Dichloropropane	    0.005
     1, 3-Dichloropropene	    0.0005
     Di(2-ethylhexyl)phthalate	    0.004
     Ethylbenzene	    0.680
     Ethylene Dibromide	    0. 00002
     Glyphosate	    0.7
     Heptachlor	    o.ooooi
     Heptachlor Epoxide.	    0.00001
     Molinate	    0.02
     Monochlorobenzene	    0.030
     Simazine	    0.01
     1,1,2,2-Tetrachloroethane	    0.001
     Tetrachloroethylene	    0.005
     Thiobencarb	    0.07
     1,1,1-Trichloroethane	    0.200
     1,1,2-Trichloroethane	'	...    0.032
     Trichloroethylene	:..    0.005
    . Trichlorof luoromethane..*.	'..    0.15
     l.l^-Trichloro-l^^-Trifluoroethane....    1.2
     Vinyl Chloride	    0.0005
   .  Xyler.es.....	    1.750*

-i-iCL  is for either single isomer or the sum of  the isomers,

-------
                          Appendix B.2
(Comments/Correspondence Received after 30-day comment period - June 13 to July 13, 1990)

-------
 Jul  31,90  10:03
                                                                                            P.02
                  THE
                             *.y  ----^ Tia  II
                             isSrsssr^ftS liUilJ
AtfCARA
                                            30 July 1990
                            W«Tf • OCPT.
                            CITY
                         i aoo
                        5AKTA CWA«A. CA 65OSO
                           («06l 964-11 «S
 Mr. StevenR. Ritchie
 Executive Officer
 California Regional Water Quality Control Board
 1600 Harrison Street, Suite 700
 Oakland. CA 94612

 SUBJECT: CLEANUP ALTERNATIVES FOR INTERSIL/SIEMENS SUPERFUNO SITE

 Dear Mr, Ritchie,

 This is in response to the proposed remediation plan recommended by the Regional Water Quality Control Board staff
 _nd outlined in Fact Sheet 3 issued in June. I am sorry to have been delayed in my response. I received Fact Sheet
 3 on 21 June, but was unable to complete my review of your plan before the public comment deadline; I needed some
 additional information which was only recently received.

 In my opinion the Regional Board staff has done an overall outstanding job In its handling of this case. Your staff is
 to be c ommended for the manner in which they have assembled the necessary data, conducted public meetings and
 developed the remediation goals and alternatives. There are, however, several substantive Issues which concern
 the City of Santa Clara, and I would like to bring these to your attention at this time for the record,

 The City of Santa Clara provides drinking water to a population of over 90,000 persons. Approximately 65% of the
 water served by the City is obtained from the deep groundwater aquifers lying beneath it. The remainder is treated
 surface water purchased from other agencies.  It is very likely that groundwater will always form the backbone of the
 City's water supply, and for that reason the City is extremely concerned about the long-term quality of that resource.
 The deep aquifers from which Santa  Clara pumps Us water are within the confined (pressure) zone, i.e., overlaid by
 a regional aquhard. This aqultard, consisting of clay layers up to hundreds of feet thick, has long been thought to
 protect the confined (deep) aquifers from contamination percolating down from the surface or from the shallow
 aquifers which are exposed to such percolation. Beginning in 1984, routine groundwater testing In compliance with
 A3-1603 has detected very small concentrations of two volatile organic contaminants (VOCs) in City of Santa Clara
 Wetl Number 24, which is approximately 1,100 meters down-gradient from the Intersil/Siemens site. Your office has
 been kept aware of these findings from the beginning. While there is no proof these contaminants emanated from the
 Intersil/Siemens s'rte, the same species were detected there and In the Marchese well: 1,1,1 -trichloroethane (TCA)
 and 1,1,2-trichloro-1,2,2-trifluoroethane (Freon 113).

 1. K Is unequivocal that VOCs exist in significant concentrations in all throt shallow aquifers, both on- and off-site.
 One of City's concerns is that your recommended remediation alternatives do not adequately address removal of
 contaminants from ad three shallow aquifers with equal efficiency. H would seem prudent that extraction of polluted
i ground-water from the C-zone be a priority, rather than the 'contingency* stated In your remediation plan. Whereas
 groundwater modeling by Regional Board staff may indicate there would be an upflow between the C-zone and the
 B-zone from whence the polluted water would be extracted, characterization of the contaminants Indicates they are
 generally insoluble in water and of higher specific gravity. Effective removal from the C-zone by pumping the B-zone
 may be problematical.  Failure to adequately contain and remove the contaminants from the C-zone aquifers may
 result in their eventual transport into the deep aquifers.
                                                                  f
                            : try to inks

-------
Jul  31,90  10:04
P.03
 projected in your plan may meet current water quality standards (ARARs), the City of Santa Clara may leter be faced
 with having to treat that groundwater in order to meet hearth-baaed standards mandated by the EPA and the tttte for
 the very tame set ofcontamlMntsfor even having to take one or more of our wells out of service—aa was suggested
 at one time by a member of your staff). I point to the advent of Recommended Public Health Levels (RPHLs) for
 drinking water which will be promulgated in early 1991. It la my understanding that RPHLs tor carcinogens will be
 based on a 10 uppcrbound cancer risk. In view of the proposed RPHLs, remediation to a 10'  risk, level seems
 dichotomcus. The City of Santa Clara would hope to see a remediation plan which will achieve the 10 ri&K level for
 carcinogens, with non-carcinogens not exceeding a Hazard index of unity.

 Thank you for taking the time to hear of our concerns. I know that you and your staff will do your very best on behalf
 of the citizens of Santa Clara and the region at the upcoming Beard Hearing on the remediation plan.
Very truly youre,
Richard H. Hathorrv'
Oit ector of Water & Sewer Utilities

RHHrlbm  C\WP51 \FILES\INT5IEM.RWQ

cc: John Wolfenden, RWQC8
  Jim Thompson, RWQCB
  Roger James, SCVWD
  City Manager
  RWQCB file
  CERCLAWe

-------
  "NT BY:                 ; 8. ,.90 .  18;02  .


Staff ef California
•

Memorandum


TO  « Steven Ritchie, Executive Officer
      Regional Water (Quality Control Board
      1800 Harrison St., Suit* 700
      Oakland, CA  94612
      Office of Drinking Water
      2131 Berkeley Way, to 45$
      Berkeley, CA  94704
      8-571-2160
SAN RAD LAB-»      SAN FRAN BAYJf 2

          Department ef Health Servkei
                     »




  Dot* • JUly 11, 1990

       Tentative Ordere
    Site Clean-up
    Requirements-
    Intersil/ Siemens
    i Solvent Service*-
    Proposed Superfund
    Sites-SantaClara Cy
      On July  24,   1990 Mr.  Steve  Morse  of  your  Board  requested
      clarifications and additional  comments  from  the Department  of
      Health Services  (OOHS)  - Office of  Drinking Water (ODW) on  the
      Cleanup Requirements  of Superfund sites  in Santa Clara  County.
      These comments are supplemental to those previously submitted to
      the Board in  a  nemo  dated  July  11, 1990.  We  have  recently
      completed review  for  2 cleanup sites:   Intersil/Siemens   (X/S)
      and Solvent  Services  Inc.  (S8Z)•      Inasmuch  at  our  general
      guidance  on   cleanup   goal*  for  cleanup   ef  contaminated
      groundwaters involving domestic water issues is the same,  we have
      combined the two sites in our response memos.   Tor case-specific
      comments on the  discussions of cleanup alternatives,  Carcinogen
      Hazard index  (CHI),  and risk  calculations for the  I/s and  SSI
      sites,   please refer to Appendices A and B, respectively,

      DOHS-OOW - CLEANUP GOALS

      As stated in our  July 11,  1990 memo, for the purpose  of  setting
      cleanup  goal*  for   contaminated  groundwaters   designated   as
      domestic water supply  source, the following are  the  guiding
      principles used by the Office of Drinking Watert

          1*    The  total cancer risk level does not exceed  10**,  or

          2.    Carcinogenic Hatard Index  does not exceed 1.0,  and

          3.    Ho contaminants exceed MCL or AL,  where applicable.

     The   above  criteria   should   be   followed  whenever   it   is
      technologically and economically feasible  in the  remediation  of
      contaminated groundwater  aquifers for  the protection of  their
     beneficial uses involving domestic consumption.

-------
SENT BY:                 ; |- 1-80 ; 16^02  ?       SAN RAO LAB*      SAN FRAN BAY18 3


     Steven Ritchie
     Pago ?
     July 91,
     REGIONAL BOARD (RB)  • PROPOSED CLEANUP LEVELS

     We acknowledge the method and procedural used by the Board etaff
     for deriving cleanup levele for Super fund eitee.  The procedural
     are detailed  in  the "Guidance  Document for the  Development of
     Health-Based Remedial Clean-up  Levels  for the  South  Bay Multi-
     site cooperative  Superfund Program1*  (RWQCB,  June 20, 1990).  The
     basis for this guidance  document stems from the  EPA'e Kational
     Oil and  Hazardous Substances Pollution Contingency Plan,  1990,
     and the Risk Assessment Guidance For Superfund, Human Health RisX
     Assessments  EPA Region XX Recommendations, 1989  (Interim Final) .

     We also acknowledge that the method used  by the Board etaff vas
     developed primarily to handle  cleanup  of Superfund sites.   The
     method does  not  adequately address  specific  concerns on  the
     protection of  affected  groundwatera  ae  domestic  water supply
     sources.

     We must aleo add  that in  the development of the  Board's "Guidance
     Document", the Department wae not informed about it or made part
     of its peer  review prior  to f inalization.

     Consequently,  the cleanup levels prescribed for both the 1/8 and
     SSI sites proposed in the Tentative Orders involve a much higher
     total cancer risk than the Department •• recommended 10*° level.
     in addition, using  the  Carcinogen Hazard  Index approach,  these
     contaminated sites after  remediation ordered by the Board,  will
     still have hatard indices many times higher than 1.0.

     We are opposed to these  cleanup level*   as they are excessively
     high and do not  adequately protect  the groundwater'e beneficial
     uses  as  domestic supply  sources.

     CLEANUP FEASIBILITY

     On the issue of cleanup feasibility. Board staff indicated during
     the July 24  meeting thati pursuant to the Board's Resolution No.
     68-16,  the Non-degradation  Policy,  the RI/FS  conducted by both
     1/8  and  S8Z  included  the  evaluation  of  cleanup  to  "non-
     detectable"  or "background" levele.   The  Board then  made the
     determination that  this  alternative would be  economically and
     technically  in feasible.   He agree that it would be impractical to
     clean up  to  non-detectable level*.   We  also request the Board to
     re-examine the  feasibility  of  a  cleanup  alternative and to
     reconsider the setting  of cleanup requirements to e more health
     protective level  from the standpoint of  protection of domestic
     water quality.

-------
-NT BY'
e- i-
SAN RAO LAB-*
SAN FRAN BAY!8 4
     Steven Ritchie
     Page 3
     July 31, 1990
     CALIFORNIA  SAFE DRINKIKO  WATER  ACT-RECOMMENDED PUBLIC  HEALTH
     LEVELS (RPHLS)

     In  addition,  we  draw your  attention  to section  4023 of  the
     California Safe Drinking Water  Act on Recommended Public Health
     Level*  (RFHLs).   A  copy  of  the  Act  is   enclosed   for  your
     reference.  The  Department  ie  currently  in  the  process  of
     promulgating the RPKLe mandated by  our Drinking Water Program.
     RPHLs are  health-based goals set to further reduce contaminant*
     in domestic water  supplies  to below the  MCL.   For carcinogenic
     compounds, the RPHLs will be  set  at the 10"° cancer risk level.
     These RPHLs will  be  applied  to all  domestic  water sources.
     Water suppliers serving 10,000  service  connections  or more will
     be required to submit, a Water Quality Improvement Plan  (WQIP) to
     the  Department  demonstrating  the  feasibility  of   providing
     additional treatment as well  as monitoring control  in order to
     rceet the  RPHLs  in both  their existing  as  well as  new  water
     sources.

     In essence,  the WQIP can be viewed as a parallel  document as the
     Remedial  Investigation /Feasibility Study  (Rl/rs)  retired of the
     responsible party(ies)  by  the  Board*  The  water  suppliers will be
     charged with the responsibilities  in meeting  more conservative
     and  health  protective  water  quality  standards   than  these
     required   of   responsible  parties   in  the   cleanup  of  the
     groundwater.   We  hereby  advise   the    Board  of this serious
     potential  shortcoming  in  imposing  less than acceptable  or health
     protective  remediation  levels   in  the  affected  groundwater
     aquifers used for domestic supply  source.

     We would also like  to point out  that in  accordance with the EPA'a
     National  contingency  Plan,  the RPHLe,  when promulgated,  will
     become the ARARs.   The RPHLs ars  currently  in  development.   We
     will keep  the Board informed of  all adopted RPHLs in the future.

     Thank you  for your  consideration on this important issue relating
     water supply quality.   We  are  hopeful that we can work  jointly to
     resolve this problem.   We will be  available  to  further discuss
     this issue  at  your request  or you may  have  questions we can
     answsr by phone.  Please do not hesitate  to  contact me at  (415)
     540-2160.
    Atttchaants
    cct See next page
                                            Catherine 8. Ling,
                                            District Engineer
                                            Monterey District

-------
SENT BY:
                        ; e- 1-80 ; lew ;       SAN RAD LAB-      SAN FRAN BAYII 5
     Steven Ritchie
     Pft^e 4'
     July 3i« 1990
     cc:  Santa  Clara County Health Department
          santa  Clara Valley Water District
          Santa  Clara County Hater Retailers
               CKS-LOS AltOC
               City of Cupertino
               City of Cilroy
               City of Nilpitas
               city of Morgan Rill
               City of Mountain Viaw
               City of Palo Alto
               City of San Jos*
               City of Santa Clara
               City of Sunnyvale
               Great OaXi Water Company
               San Joae Water Company
               Stanford Univereity

-------
BY:
e- 1-90 ;
SAN RAO LAB"
                                                         SAN FRAN BAY;« e
  Steven Ritchie
  Page 5
  July 51,  1990
  APPENDIX At  INTERSIL/SIEMENS SUPERTUND SITf

  A.    Cleanup levels

  The proposed cleanup levels prescribed for the I/a site contained
  in the Tentative Order are the ARARs(- MCL) for all the chemicals
  in all of  the A* , B- and C- zone aquifers*

  AS presented by Mr. Wolfenden  using the risk  calculations,  the
  cleanup  of PCS and  TCB to MCL  in the A- .and B»  zone aquifers
  would result in a total risk of  3.8 x 10~*.  This  is  3.8 times
  higher  than  the  10~*  level recommended  by  the Department  of
  Health Services.  Using  the DOHS  CHI approach for  3 carcinogens
  at MCL,  it would have an index  of 2.0,  twice that recommended by
  DORS.   However, ae  stated in our  July 11 nemo,  the A-  and B-
  Zcnes are  considered non-domestic supply zone.  Our cleanup goals
  would not  be  applicable  in this case.

  In the C*  Zone aquifer,  Mr.  Wolfenden pointed out  that the VOCs
  currently  detected  include 19 ppb  of TCE  and 1 ppb Of 1,1-DCE.
  Since DOB is considered  as  a  non-carcinogen,  only  TCS  is  of
  concern  in this particular  aquifer*   The  proposed cleanup  to
  drinking  water standard  for  TCS  would  be acceptable  from  a
  domestic  supply standpoint  because  only  a  aingia  carcinogenic
  chemical is involved in  this case.  Also, as discussed during the
  July  24, 1990 meeting,  the proposed cleanup to MCL  for TCE at a
  much higher concentration than that of OCE would at the same time
  bring  the OCX to  very low  or  non-detectable level,  assuming
  comparable removability  of both  TCE and DCE in the  aquifer.   We
  agree with this.  In this case,  we sugguest that it would be more
  appropriate  for the Board  to  communicate  the  "actual"  total
  cancer risk  expected from the  remediation rather than the risk
 calculated with the  assumption  that all of the chemicals are at
 MCL or ARARs levels.

 B.   Cleanup alternatives

 The  feasibility of cleanup  to  drinking  water  standards  for
 chemicals  in all  of the three  shallow aquifers A-,  B-  and  C*
 Zones is based on  the   proposed  remediation plan of  extracting
 contaminated  water  only from the A- and B-  Cone aquifers.   No
 groundwater extraction or  remediation is currently  proposed  for
 the C-  Zone  aquifer.  The groundwater  model used  by  the Board
 predicts  an  upward  flow  of contaminated water from C-  Zone
 aquifer to the upper A- and B- Zone  aquifers.     The  model  for
 this  cleanup alternative also projects to a 45-year  period  of
 remediation.    This appears to be  an extremely long  and energy
 intensive; task.

-------
SENT BY:
; e- 1-90 ; ie:os
SAN RAO LAB-
SAN FRAN BAYJt 7
     Steven Ritchie
     Page 6
     July 31, 1990
     We  question the  validity  of the  cleanup plan  which  does not
     include a direct remediation plan for C- Zone aquifer, tinea this
     is  the  moat  vulnerable con*  with  reepect  to  domestic water
     supply.    As  discussed previously,  the  C- Zone aquifer it an
     existing  domestic water supply source  for snail system wells,
     and is also the immediate link to  the  deeper aquifers, which is
     the primary source for most of large water systems.

     The Board should  examine the  feasibility of  direct extraction
     from the  c aquifer.   This could   be a more cost-effective and
     time* efficient alternative for  the overall  cleanup program at
     I/S.

-------
JYT
J 8- 1-80 ; 16:05
SAN RAO LAB*
SAN FRAN BAY;s e
    Steven Ritchie
    Page 7
    July 31, 1990
    APPENDIX BS  SOLVENT SERVICES INC.  SUPERFUND SITE
    A.   Background

         The  8SX  eite   involve*   multiple  chemicals  which   have
         contaminated the A,  B/C, and D/E aquifers,  both on- and off-
         site*  The greatest extent of contaaination ie  in  the  upper
         A and B/C aquifers.   The D/E aquifer ie an  existing domestic
         water supply source.  Within one Bile radius froa  the  site,
         there are  2 existing  domestic water  supply  wells  drawing
         from the D/I aquifer.

         The  carcinogenic  chemicala of  concern are  (8)s    Arsenic,
         Benzene, Vinyl  Chloride,  1,1-DCA,  Kethylene Chloride,  PCE,
         TCS,  Chlorofora.

         The  non-carcinogenic  chemicals  of   concern  are   (14)s
         Acetone, 2-Butanona, 1,2-DCB,  Cis-l,2-DC8, 1,1-DCS, Trans-
         1,2-DCE, Ethylbenrene,  Freon-113,  4-Meth-2-Fent.,  Nickel,
         Phenol,  1,1,1-TCA, Toluene, Xylene.

    B.   Cleanup levels

         KCHI • 0.96 for noncarcinogens.

         Total Cancer HisX including Arssnio • 4.98  x 10"4

         As shown, the cleanup levele proposed in the Tentative  Order
         by the  Board for the  S8X site involve  e  much higher (498
         tines)  cancer  risk  than  10~5.   in  addition,   applying  the
         DOKS CHI approach results  in a Kaiard Index of  7.1.

         As stated in our July 11  memo,  the interactive effects of
         the different  component toxicants in  the  mixtures are  not
         well defined and understood.  He are greatly concerned  about
         the  additional  health risks and  hazards  associated  with
         mixtures of  chemicals.  We again  request  the  Board to  re-
         examine the  feasibility of additional remediation measures
         and to  reconsider lowering  the cleanup  levels to s  more
         health protective level.

-------
SENT BY:
; e- 1-80 ; ie:oe  ;
                                              SAN RAO LAB-
SAN FRAN BAY;« 8
     Steven RitehU
     Page ft
     July 31, 1990
     C.   Cleanup alternative

          The extent of  the contamination and the characterization of
          the   plum*  off-site  were   not clear  from  the Tentative
          Order.   However,  it ie  clear that there will be no direct
          remediation  measure taken.    Instead,  the  remediation of
          contamination  off-site ie  proposed  as a "contingency* plan.
          It depends solely  on the on-cite containment process.  This
          process involves  the  operation of 3  extraction trenches to
          "pull bade*  and recover, contaminants from the groundvatar
          off-site.    The  Order,  on the other  hand,   specifically
          states that  the  effectiveness  of such proposed contingency
          plan has  not been demonstrated by  current data*   It there
          another contingency plan in  wait  in ease  the proposed one
          fails?

-------
                                                                       1
 August 2, 1990
                                               AUG tt2

                                          QUALITY CW'fllQL BOARD
 John Wolfcndei
 Regional Water Quality Control Board
 San Francisco Bay Region
 1800 Harrison Street, 7th Floor
 Oakland, California  94612

      Re:  Intersil, Inc.'s Response to Comments by DOHS, Office
           of Drinking Water, Concerning Intersil/Siemens Site
           Tentative Order

 Dear John:

      This letter presents Intersil's position regarding comments
 submitted to the Regional Board by the Department of Health
 Services, Office of Drinking Water ("ODW") dated July 11, 1990,
 concerning ODW's review of the Tentative Order for the
 Intersil/Siemens proposed Superfund site.  At the outset, we wish
 to express our complete agreement with Regional Board staff
 statements that ODW's suggested use of a carcinogenic hazard
 index ("CHI1*) of one or a 10*6 carcinogenic risk level as cleanup
 standards are inappropriate and should be rejected.1  Intersil's
 comments encompass many of the points raised by Regional Board
 staff in the Responsiveness Summary (Appendix C to the Tentative
      1    Intersil also notes that no branch or office of the
 Department of Health Services commented on Intersil or Siemens' /
 On-Site and Off-Site RI/FS Reports, or on the Baseline Public
 Health Evaluation prepared by Clement Associates under contract
 to the RWQCB.  In fact, in a letter dated January 22, 1990  from
 David Wang, Chief, Site Mitigation Unit, Toxics Division,
 Region 2 to John Wyss of Siemens Components, inc., the
 Department specifically asked to be removed from the mailing list
 for this Site.
tnwnril tor
»75 B*nir,f rtTi.ii, mi
                                     Pin Franste*, SAJH111 - ,m..?w i UC •

-------
John .Wolfenden
August 2, 1990
Page 2


O^der), and are intended to supplement that summary.  Our
comments are as follows:

     A. x  The Regional Board Should Reiect ODW's Suggested
          "Terminus Risk Level" of 10**, ODW's "Policy Guidance
          for Direct Domestic Use of Groundwater Contaminated
          with Toxic Substances", and ODW's Suggested Use of a
          Carcinogenic Hazard Index of One, Because They are not
          ARARs.	-

     In its comments to the Regional Board, ODW stated that the
proposed cleanup levels for the A- and B- zones are appropriate
given the potential future use of these aquifers.  With respect
to proposed cleanup levels in the C-zone however, ODW indicated
some concern.2

     The Tentative Order has established C-zone cleanup levels
Consistent with the Regional Board's determination that
"(ajchieving drinking water quality is an ARAR for this site."
Tentative Order, Finding No. 18, p. 12.  That is, groundwater
cleanup standards for the site are EPA Maximum Contaminant Levels
("MCLs"), California Department of Health Services  ("DOHS") MCLs,
and DOHS Recommended Drinking Water Action levels ("RDWALs").
Id.  These cleanup standards are derived from federal and state
standards, requirements, criteria and limitations, and therefore
constitute ARARs within the meaning of Section 121(d)(2) of
CERCLA, as amended by SARA, 42 U.S.C. S 9621(d)(2).  In contrast,
ODW's recommended use of a CHI of one and 10"* carcinogenic risk
level are not ARARs and should not be used to establish cleanup
levels.
     2    As a factual mater, ODW's contention that the C-zone
should have lower cleanup levels is incorrect.  First, data
collected to date by Intersil and Siemens' consultants indicates
that the A-, B-, and C-zones in the vicinity of the
Intersil/Siemens Site are part of a shallow water bearing zone
that is separated from the Deeper Aquifers by a 75-foot-thick
regional aquitard.  Seef e.g.. Tentative Order, Finding No. 6,
p. 3.  There is evidence suggesting that the B- and C-zones are
hydraulically connected in the Site region; but there is no
evidence of any hydraulic connection between these two zones and
the Deeper Aquifers.  Second, no evidence has been found to
support ODW's statement that the C-zone is an existing domestic
water supply source in the vicinity of the Site.  Instead,
available information indicates that the municipal supply wells
in the region draw water from the Deeper Aquifers.

-------
John Wolfenden
August 2, 1990
Page 3


%   In order for ODW's recommended use of a CHI of one,  a
carcinogenic risk level of 10"*, or the "Policy Guidance for
Direct Domestic Use of Groundwater Contaminated with Toxic
Substances" to rise to the level of an ARAR, they must,  among
other things, be "promulgated.1*  42 U.S.C. S 9621 (d) (2) (A) (ii) .
To be "promulgated," ODW's suggested approach must be "generally
applicable" and "legally enforceable."  40 C.F.R.
S 300.400(g)(4).  The approaches suggested by ODW to establish
cleanup levels meet neither of these criteria.

     First, standards that are inconsistently applied are not
"generally applicable" standards.  See, e.g.. 42 U.S.C.
S 9621(d)(4)(E).3  RWQCB staff communications with DOHS
representatives, and a review of actions taken at certain DOHS-
lead Superfund sites, indicate that ODW's recommended procedures
are not consistently applied within DOHS.

     RWQCB staff discussions with Jeff Wong of DOHS' Toxics
Biar.ch (Sacramento), reveal that the Toxics Branch was "unaware
of any [DOHS] requirement that the CHI using MCLs in the
denominator was required to be less than one for cleanup levels."
Responsiveness Summary, p. 3.  In addition, DOHS recently
approved cleanup levels that exceeded a 10* * risk level at a
State Superfund site in Palo Alto.  See DOHS Fact Sheet No. 4 for
Stage 1 FS, Aydin Energy State Superfund Site, Palo Alto,
California (June 1990).  These examples demonstrate that the
approach espoused by ODW in its comments has not been
consistently (if at all) applied and therefore is not "generally
applicable" so as to qualify as an ARAR under Section 121(d)(2)
of CERCLA, or under 40 C.F.R. S 300.400(d)(4).

     Second, ODW's proposed methods and policies must be
"legally enforceable" to be an ARAR.  In order to be legally
enforceable, ODW's recommended methods and policies must
constitute a "substantive rule"  (i.e.f one enacted by an
administrative agency pursuant to statutory delegation).  In this
case, ODW's use of a CHI of one and a 10'* carcinogenic risk
level is at best a general statement of policy, the application
     3    In addition, for a cleanup standard to be generally
applicable, it must be appropriate for use as a cleanup standard
for all sites.  55 Fed. Reg. 8746.  The "Policy Guidance for
Direct Domestic Use of Groundwater. . ." involves guidelines
whereby the Public Water Supply Branch of DOHS would consider the
later use of treated groundwater in a domestic water supply
distribution system.  Thus, the policy does not appear to apply
in the context of establishing cleanup levels for aquifers such
as the A-, B- and C-zones beneath the Intersil/Siemens Site.

-------
John Wolfenden
August 2, 1990
Page 4


6^ which is apparently inconsistent even within the different
offices and branches of DOHS.  Because ODW's policies are not
legally enforceable, they are not ARARs.4

     B. x The CHI Equation Used by ODW is Technically Flawed
          with Regard to Maintaining a Specific Incremental
          Cancer Risk Goal, and Therefore Should not be Used to
          Develop Cleanup Standards at the Site.	

     In its comments, OOH sets forth its equation to calculate
the CHI.  Intersil's analysis of that equation reveals that the
equation is inconsistent with ODW's stated goal of an incremental
cancer risk of 10* *.  The CHI equation used by ODW appears to be
derived from calculations in the California Site Mitigation
Decision Tree Manual (the "Manual").  The Manual bases its risk
calculations on DOHS Applied Action Levels (AALs).  For
carcinogens, AALs are based on a maximum exposure level ("MEL")
that produces one adverse effect in a population of one million
exposed receptors,  or an incremental carcinogenic risk of 10*6.
The MELs are derived from toxicity studies such as
epidemiological research or long-term animal bioassays.  AALs are
based entirely on health effects and do not consider the
limitations of technology, whereas Action Levels (ALs) and
Maximum Contaminant Levels (MCLs), are health-based values
modified as necessary to consider cost and technical limitations.
AALs are specific to the chemical, the receptor, and the medium
of exposure.  The procedures in the Manual call for summing the
ratios of the chemical concentration to the AAL over the
chemicals and the exposure route.  If this sum is greater than
one for carcinogens, the total incremental carcinogenic risk to a
receptor is greater than 10* *.

     The CHI equation used by ODW is similar in form to the
equation used in the Manual with the following significant
difference:  ODW's equation allows for the use of AALs, ALs, or
     4    Lead and support agencies may consider other
advisories, criteria, or guidance in establishing cleanup
standards.  55 Fed. Reg. 8746.  "To be considered" factors
("TBCs") may be considered in developing cleanup levels and the
like, but unlike ARARs, they are not binding cleanup standards
that must be achieved.  At this Site, the RWQCB actually
considered the various points raised in ODW's comments in the
context of the remedial alternatives that evaluated cleanup to
background.  See Tentative Order, Finding Nos. 13.1.6, 13.2.6,
and 13.3.6, pp. 7-9.  The RWQCB rejected these alternatives
because of considerations based on time to cleanup, cost and
groundwater conservation.  ISL., Finding No. 16, p. 12.

-------
iVT BY:
; e- 1-fiO ; 16=05  ;
SAN RAO LAB"
SAN FRAN BAY:8 8
    Steven Ritchie
    Pago  7
    July  31, 1990
   APPENDIX Bt  SOLVENT SERVICES INC. SUPERTUND 8ZT1
   A*   Background

        The   ssz   site  involves  multiple   cheaioals   which  have
        contaminated the A, B/C, and D/E aquifers, both on- and off-
        site.  The  greatest  extent of contaaination ie in the upper
        A and B/c aquifers.  The D/E aquifer ie an exieting domestic
        water supply source.  Within  one Bile radiue from the site,
        there  are 2  existing domestic  water supply veil*, drawing
        from the D/l aquifer*

        The  carcinogenic chemicals of concern  are (8)t   Arsenic,
        Benzene, Vinyl Chloride,   1,1-OCA, Kethylene Chloride,  PCS,
        TCS, Chiorofora.

        The   non-carcinogenic  chemicals  of  concern   are  (14)t
        Acetone,  2-Butanone,  1,2-DCB, Cis-l,2-DC£,  1,1-DCE, Trans-
        1,2-DCE,  Ethylbencene,  Freon«113,  4-Meth-2-P«nt,,  Nickel,
        Phenol, 1,1,1-TCA, Toluene, xylene.

   B.   Cleanup level*

        KCRZ « 0.96 for noncarcinogan*.

        Total Cancer Risk including Arsenic • 4.98 x 10*4

        As shown, the cleanup levels proposed in the Tentative Order
        by the  Board for the SSZ site  involve e auch  higher (498
        tiaec) cancer  risk than  10~tt.   In addition,  applying  the
        DOHS CHI approach results  in a Hazard index  of 7.1.

        As stated  in our July  11 aeao,  the  interactive effects of
        the different  component toxicants in the mixtures  are  not
        veil defined and understood.  He are greatly concerned about
        the  additional health  risks  and hazards  associated  with
        cixtures of  chemicals.   We again request the Board to  re-
        exaaine the  feasibility of additional  reaediation aeasures
        end to  reconsider  lowering the  cleanup  levels to  a  aore
        health protective level.

-------
SENT BY:
J 8- 1-80 ; 18206  i
                                              SAN RAO LAB-*
SAN FRAN BAY;8 9
      Steven Pitch!*
      Page 8
      July 31, 1990
     C.   Cleanup alternative*

          Tha extant of  tha eontanination and the characterieatlon of
          the   plum*  off-site  wera   not clear  from  tha Tentative
          Order.   However,  it la  claar that there will ba no direct
          remediation  measure taken.    Instead,  tha  remediation of
          contamination  off-site is  proposed  as a "contingency* plan.
          It depends solely on tha on-site containment process.   This
          process involves  tha  opsration of  3  extraction tranches to
          "pull bade"  and  raoovar. contaminants from tha  groundvatar
          off-site.    Tha  Order,  on  the other  hand,   specifically
          states that  tha  effectiveness  of such proposed  continganoy
          plan has  not baan demonstrated by  currant data.   Is there
          another contingency plan in  wait  in ease  the proposed one
          fails?

-------
                                                  KCKW. Vf«B
August 2, 1990
                                              AUG fi 2

                                         QUALITY CON TOOL BOARD
John Wolfendei
Regional Water Quality Control Board
San Francisco Bay Region
1800 Harrison Street, 7th Floor
Oakland, California  94612

     Re:  Intersil, Inc.'s Response to Comments by DOHS, Office
          of Drinking Water, Concerning Intersil/Siemens Site
          Tentative Order	

Dear John:

     This letter presents Intersil's position regarding comments
submitted to the Regional Board by the Department of Health
Services, Office of Drinking Water (NODWN) dated July 11, 1990,
concerning ODW's review of the Tentative Order for the
Intersil/Siemens proposed Superfund site.  At the outset, we wish
to express our complete agreement with Regional Board staff
statements that ODW's suggested use of a carcinogenic hazard
index ("CHI") of one or a 10"6 carcinogenic risk level as cleanup
standards are inappropriate and should be rejected.1  Intersil's
comments encompass many of the points raised by Regional Board
staff in the Responsiveness Summary (Appendix C to the Tentative
     1    Intersil also notes that no branch or office of the
Department of Health Services commented on Intersil or Siemens' /
On-Site and Off-Site RI/FS Reports, or on the Baseline Public
Health Evaluation prepared by Clement Associates under contract
to the RWQCB.  In fact, in a letter dated January 22, 1990 from
David Wang, Chief, Site Mitigation Unit, Toxics Division,
Region 2 to John Wyss of Siemens Components, inc., the
Department specifically asked to be removed from the mailing list
for this Site.
                < W;:-,! <-- 37F B'(It:-;? P«

-------
John .Wolfenden
August 2, 1990
Page 2


O^dcr), and are intended to supplement that summary.  Our
comments are as follows:

     A. v  The Regional Board Should Reiect ODW's Suggested
          "Terminus Risk Level?1 of 10* *, ODW's "Policy Guidance
          for Direct Domestic Use of Groundwater Contaminated
          with Toxic Substances", and ODW's Suggested Use of a
          Carcinogenic Hazard Index of One, Because They are not
          ARARs.	

     In its comments to the Regional Board, ODW stated that the
proposed cleanup levels for the A- and B- zones are appropriate
given the potential future use of these aquifers.  With respect
to proposed cleanup levels in the C-zone however, ODW indicated
some concern.2

     The Tentative Order has established C-zone cleanup levels
Consistent with the Regional Board's determination that
H[a]chieving drinking water quality is an ARAR for this site."
Tentative Order, Finding No. 18, p. 12.  That is, groundwater
cleanup standards for the site are EPA Maximum Contaminant Levels
("MCLs"), California Department of Health Services  ("DOHS") MCLs,
and DOHS Recommended Drinking Water Action levels ("RDWALs").
Id.  These cleanup standards are derived from federal and state
standards, requirements, criteria and limitations, and therefore
constitute ARARs within the meaning of Section 121(d)(2) of
CERCLA, as amended by SARA, 42 U.S.C. S 9621(d)(2).  In contrast,
ODW's recommended use of a CHI of one and 10*6 carcinogenic risk
level are not ARARs and should not be used to establish cleanup
levels.
     2    As a factual mater, ODW's contention that the C-zone
should have lower cleanup levels is incorrect.  First, data
collected to date by Intersil and Siemens' consultants indicates
that the A-, B-, and C-zones in the vicinity of the
Intersil/Siemens Site are part of a shallow water bearing zone
that is separated from the Deeper Aquifers by a 75-foot-thick
regional aquitard.  See, e.g.. Tentative Order, Finding No. 6,
p. 3.  There is evidence suggesting that the B- and C-zones are
hydraulically connected in the Site region; but there is no
evidence of any hydraulic connection between these two zones and
the Deeper Aquifers.  Second, no evidence has been found to
support ODWs statement that the C-zone la an existing domestic
water supply source in the vicinity of the Site.  Instead,
available information indicates that the municipal supply wells
in the region draw water from the Deeper Aquifers.

-------
John Wolfenden
August 2, 1990
Page 3


%   In order for ODW's recommended use of a CHI of one, a
carcinogenic risk level of 10'*, or the "Policy Guidance for
Direct Domestic Use of Groundwater Contaminated with Toxic
Substances" to rise to the level of an ARAR, they must, among
other things, be "promulgated."  42 U.S.C. S 9621(d)(2)(A)(ii).
To be "promulgated," ODW's suggested approach must be "generally
applicable" and "legally enforceable."  40 C.F.R.
S 300.400(g)(4).  The approaches suggested by ODW to establish
cleanup levels meet neither of these criteria.

     First, standards that are inconsistently applied are not
"generally applicable" standards.  See, e.g.. 42 U.S.C.
S 9621(d)(4)(E).3  RWQCB staff communications with DOHS
representatives, and a review of actions taken at certain DOHS-
lead Superfund sites, indicate that ODW's recommended procedures
are not consistently applied within DOHS.

     RWQCB staff discussions with Jeff Wong of DOHS' Toxics
Eiar.ch (Sacramento), reveal that the Toxics Branch was "unaware
of any [DOHS] requirement that the CHI using MCLs in the
denominator was required to be less than one for cleanup levels."
Responsiveness Summary, p. 3.  In addition, DOHS recently
approved cleanup levels that exceeded a 10* * risk level at a
State Superfund site in Palo Alto.  See DOHS Fact Sheet No. 4 for
Stage 1 FS, Aydin Energy State Superfund Site, Palo Alto,
California (June 1990).  These examples demonstrate that the
approach espoused by ODW in its comments has not been
consistently (if at ail) applied and therefore is not "generally
applicable" so as to qualify as an ARAR under Section 121(d)(2)
of CERCLA, or under 40 C.F.R. S 300.400(d)(4).

     Second, ODW's proposed methods and policies must be
"legally enforceable" to be an ARAR.  In order to be legally
enforceable, ODW's recommended methods and policies must
constitute a "substantive rule" (i.e.. one enacted by an
administrative agency pursuant to statutory delegation).  In this
case, ODW's use of a CHI of one and a 10*6 carcinogenic risk
level is at best a general statement of policy, the application
     3    In addition, for a cleanup standard to be generally
applicable, it must be appropriate for use as a cleanup standard
for all sites.  55 Fed. Reg. 8746.  The "Policy Guidance for
Direct Domestic Use of Groundwater. . ." involves guidelines
whereby the Public Water Supply Branch of DOHS would consider the
later use of treated groundwater in a domestic water supply
distribution system.  Thus, the policy does not appear to apply
in the context of establishing cleanup levels for aquifers such
as the A-, B- and C-zones beneath the Intersil/Siemens Site.

-------
John Wolfenden
August 2, 1990
Page 4


6^ which is apparently inconsistent even within the different
offices and branches of OOHS.  Because ODH's policies are not
legally enforceable, they are not ARARs.4

     B. x The CHI Equation Used by ODW is Technically Flawed
          with Regard to Maintaining a Specific Incremental
          Cancer Risk Goal, and Therefore Should not be Used to
          Develop Cleanup Standards at the Site.	

     In its comments, ODW sets forth its equation to calculate
the CHI.  Intersil's analysis of that equation reveals that the
equation is inconsistent with ODW's stated goal of an incremental
cancer risk of 10* *.  The CHI equation used by ODW appears to be
derived from calculations in the California Site Mitigation
Decision Tree Manual (the "Manual11).  The Manual bases its risk
calculations on DOHS Applied Action Levels (AALs).  For
carcinogens, AALs are based on a maximum exposure level ("MEL")
that produces one adverse effect in a population of one million
exposed receptors,  or an incremental carcinogenic risk of 10*6.
The MELs are derived from toxicity studies such as
epidemiological research or long-term animal bioassays.  .AALs are
based entirely on health effects and do not consider the
limitations of technology, whereas Action Levels (ALs) and
Maximum Contaminant Levels (MCLs), are health-based values
modified as necessary to consider cost and technical limitations.
AALs are specific to the chemical, the receptor, and the medium
of exposure.  The procedures in the Manual call for summing the
ratios of the chemical concentration to the AAL over the
chemicals and the exposure route.  If this sum is greater than
one for carcinogens, the total incremental carcinogenic risk to a
receptor is greater than 10**.

     The CHI equation used by ODW is similar in form to the
equation used in the Manual with the following significant
difference:  ODW's equation allows for the use of AALs, ALs, or
     4    Lead and support agencies nay consider other
advisories, criteria, or guidance in establishing cleanup
standards.  55 Fed. Reg. 8746.  "To be considered" factors
("TBCs") may be considered in developing cleanup levels and the
like, but unlike ARARs, they are not binding cleanup standards
that must be achieved.  At this Site, the RWQCB actually
considered the various points raised in ODW's comments in the
context of the remedial alternatives that evaluated cleanup to
background.  See Tentative Order, Finding Nos. 13.1.6, 13.2.6,
and 13.3.6, pp. 7-9.  The RWQCB rejected these alternatives
because of considerations based on time to cleanup, cost and
groundwater conservation.  ldx» Finding No. 16, p. 12.

-------
John Wolfenden
August 2, 1990
Page 5
     in calculating the CHI.  If AALs are used in the CHI
equation, a CHI of one indicates a total incremental carcinogenic
risk of 10' *.  If ALs or MCLs are used in the CHI equation
however ,v a CHI of one nay not indicate a total incremental
carcinogenic risk of 10'*, because ALs and MCLs consider
technical limitations.  In ODW's comments, 10' 6 is specified "as
the terminus risk level whenever this level of protection  can be
accomplished with reasonable and cost effective operation
measures," and ODW then recommends using the CHI equation  to
develop groundwater cleanup goals.  However, because the CHI
equation allows the use of ALs and MCLs in calculating the CHI,
the CHI equation may be inconsistent with ODW's stated goal of
developing cleanup levels that result in a total incremental
carcinogenic risk of 10' *.  Use of ODW's CHI of one would  likely
result in the development of "random risk levels" at different
RWQCB-lead Super fund sites, with the decisions regarding cleanup
levels lacking technical or economic support.  See Responsiveness
Summary, p.  3.

     In addition to the problems identified above, ODW's approach
for calculating the CHI fails to consider site-specific factors,
as required by the formula in the Decision Tree Manual. The
final equation, on which the CHI equation appears to be based,
should therefore not be taken straight from the Manual and
applied without first considering the proceeding calculations and
considering various site-specific issues.  For instance, the risk
assessment in Intersil's On-Site Report was a site-specific risk
assessment,  performed in accordance with EPA guidance.
Characteristics of the Site and vicinity were incorporated into
the risk assessment to determine the risks presented at the Site
after remediation.  Site-specific exposure scenarios and
federally-approved health effects criteria developed from
toxicity studies were used to determine the risk to receptors
after remediation was complete.  The additive and/or synergistic
effects of exposure to multiple chemicals via multiple exposure
routes was also considered in the risk assessment by totaling
the risk due to each chemical from each exposure route.  The
total incremental carcinogenic risks calculated were between the
range of 10"* and 10**, the range of risks considered protective
by EPA.

     Intersil's conclusion that ODW's method of calculating the
CHI is flawed is consistent with the statements of RWQCB staff
set forth at pages 3 to 4 of the Responsiveness Summary.  Based
on Intersil and RWQCB staff criticisms, the RWQCB should reject
the techniques advanced by ODW to determine cleanup levels.

-------
John Wolfenden
August 2, 1990
Page 6


*>   C.   The Cleanup Levels Contained in the Tentative Order are
          Fully Protective of Hunan Health and Domestic Supplies;
          ODW's Suggested Risk Levels and Cleanup Standards
       - v Should Therefore be Rejected.	

     As pointed out by Regional Board staff in the Responsiveness
Summary, ODW's suggested use of the CHI and the 10" * carcinogenic
risk level as cleanup standards is inconsistent with among other
things, the National Contingency Plan, 40 C.F.R. Part 300 ("NCP")
that was promulgated on March 8, 1990.  See also Safe Drinking
Water Act, 42 U.S.C. $ 300f et seq.  In accordance with the Site
Cleanup Requirements Order No. 89-038 issued by the Regional
Board, and consistent with the fact that the Intersil/Siemens
Site was proposed for listing on the National Priorities List,
Intersil performed the RI/FS in accordance with EPA guidance.
EPA guidance used to conduct the RI/FS included:  the NCP, the
Superfund Health Evaluation Manual (SPHEM) (EPA 1986), the Risk
Assessment Guidance for Superfund, Human Health Evaluation Manual
(RAGS) (EPA 1989), and the Guidance for Conducting Remedial
Investigations and Feasibility Studies Under CERCLA  (EPA 1988).

     As discussed in the previous section, the RI/FS process at
the Intersil/Siemens Site included conducting a site-specific
risk assessment and calculating site-specific carcinogenic risk
levels.  ODW's carcinogenic risk level is inconsistent with those
determined by EPA to be protective of drinking water.  The NCP
states that "for known or suspected carcinogens, acceptable
exposure levels are generally concentrations that represent an
excess upper bound lifetime cancer risk to an individual of
between 10'* and 10"*."  40 C.F.R. S 300.430(e)(2).  EPA's risk
level recently has been judged acceptable by the RWQCB for
cleanup to MCLs at several sites in Santa Clara County, including
the Applied Materials and Intel, Santa Clara 3 sites.  RWQCB
Site Cleanup Requirements Order Nos. 89-167 and 90-	,
respectively.

     D.   Conclusion

     The policies underlying ODW's comments are not ARARs, and
should therefore be rejected by the Regional Board.  In addition,
ODW's formula for calculating the CHI appears flawed and
inconsistent with DOHS' goal of maintaining a specific
incremental cancer risk.  Finally, the cleanup  levels established
in the Tentative Order for the Site are fully protective of
current and future domestic water supplies.

     The methods and recommendations discussed  in ODW's comments
should be considered in the context of the newly revised NCP.
There, after literally years of technical input and review, EPA

-------
John wolfenden
August 2, 1990
Page 7


nqted that setting remediation goals within the range of 10' * to
10'6 "allows a pragmatic and flexible evaluation of potential
remedies at a site while still protecting human health and the
environment."  55 Fed. Reg. 8717.  The RWQCB's method of
establishing cleanup levels therefore represents the proper
approach.

     Please call if you have any questions.  Thank you.

                                   Sincerely,
                                    wLto*JJiir\
                                   Edward A. Firestone
cc:  R. John Wyss, Siemens Components, Inc.

-------
               00'03'«0 171*1
                                             400  2««  0271  S.C.UALLEV yflTER
                                                                              02
                                           Santo OOTQ NfeEsy Ufatef DfeMd
                                            5750 ALMADEN EXPRESSWAY
                                            SAN JOSE, CALIFOINIA 9508
                                            TELEPHONE   (406) J6M600
                                            PACSIMIIE    (408) 266 0271

                                            AN AffltMATIVf ACTON IMflOYH
 August 3.1990
 Mr. Steve Morie
 Regional Water Quality Control Board
 1800 Harrison Street, Room 700
 Oakland, CA  94612
 Dear Mr. Morse:
 Subject:
Comments on Intersil/Siemens and Solvent Services Clean Up Plans
In nrevlmx comment! transmitted to your staff by letters dated July 13,1990, and July 20,1990, for the
Intersil/Siemens and Solvent Services sites respectively, we have suggested that the Regional Board apply
the Carcinogenic Hazard Index approach for setting clean up level.

In response to discussions with you at a meeting on July 24,1990, and subsequent discussions with the
Department of Health Services, I agree that your methodology for computing clean up levels may be
appropriate. The District remains concerned, however, with the recommended goals resulting in 10* risk
levels for carcinogenic compounds. It is my understanding that forthcoming Recommended Public Health
Levels (RPHL's) will be based on a 104 cancer risk. As a result, the recommended goal could adversely
impact the future use of that portion of the groundwater basin.

Therefore, we urge you to require a remediation plan which will achieve a total cancer risk level of 104
in order to assure uninhibited use of the groundwater basin
Division Engineer
Groundwater Protection Division

-------
APPENDIX C

-------
                                      '        ••~               ^
                          Figure 1-1: REGIONAL MAP
Project No. 1218
LEVINE^FRICKE
CTXHULTIMO fMOMUHS «MO MTOOOOCOlOOfTI
JHH34JAN«Omp«

-------
    Figure  to  :
MONITORING WELL LOCATOMS

        LEVINE'FRICKE

-------