United States
            Environmental Protection
            Agency
                Office of
                Emergency and
                Remedial Response
EPA/ROO/R09-90/048
September 1630
&EPA
Superfund
Record of Decision
            Stringfellow, CA

-------
50272 101
-                          
REPORT DOCUMENTA T10N I I. REPORT NO.     I ~   ~ ~8 Ac--'«In No.  
   PAGE      EPA/ROD/R09-90/048         
... TIlle end .....                I. ....... D*    
SUPERFUND RECORD OF DECISION          09/30/90  
Stringfellow, CA               ..      
Fourth Remedial Action                 
7. AdIor(8)                   .. Pwf""'*'8 Org8lUa1lon .... No.
8. I'8rIonnkIg 0rpIrWtI0n II8m8 end AdIIr-.            10. Proj8c1lT88IWork UnIt No.  
                     I I. c-8Ct(C) 01 GI8n1(Q) No.  
                     Ic)      
                     101      
I~ Span80ftng OrgeNzaton II8m8 end AdIIr-. .            I~ Type III"""" P8rIocI Co-.d 
U.S. Environmental Protection Agency        800/000  
401 M Street, S.w.                   
washington, D.C. 20460           I'"      
15. SuppIMwIt8Iy NotM                      
us. Ab81r8c1ILbN1: 2IID .0rd8)                      
The Stringfellow site is an inactive hazardous waste disposal facility in Riverside
County, California, approximately 50 miles east of Los Angeles.  The site is divided
into four zones:  the onsite/upper mid-canyon area, which includes a l7-acre, inactive
industrial. disposal area in the southern portion of the Jurupa Mountains (Zone 1); the
mid-canyon area (Zone 2); the lower canyon area (Zone 3); and the community of Glen Avon
(Zone 4). From 1956 to 1972, approximately 34 million gallons of industrial waste from
metal finishing, electroplating, and DDT production were dispos~d of in unlined 
evaporation ponds located throughout Zone 1. Some of the wastes from these ponds 
migrated into the ground water system and were transported 2 miles downgradient (under
Zones 2 and 3) to form a ground water plume beneath the Glen Avon community (Zone 4) .
Between 1975 and 1980, the State removed approximately 6.5 million gallons of  
unspecified liquid waste and DDT-contaminated material from the  site. In 1980, EPA
removed approximately 10 million gallons of contaminated water,  reinforced containment
barriers, and improved a truck loading area. Further removal actions included  
installing french drain system fences; removal of all remaining surface liquids; 
partially neutralizing and capping the wastes; installing a gravel drain network, 
(See Attached Page)                     
17. Doc\Im8nI An8IpIa L De8crIpt-                     
Record of Decisio~ - Stringfellow, CA             
Fourth Remedial Action                  
Contaminated Medium: gw                 
Key Contaminants: VO(:s (TCE)               
b.Id8nII~T-                     
c. COSATI R81cWroup                      
II. AV8l'8b1UIy SIII8mInt            , I. S8cwtty CI- ('nll8 Report,   21. No. III,.... 
                   None    40 
                 211. SecuJIty Cla8ITIU P8118'   22. PrIce  
                   None       
(See ANSI-ZU. '1'
SHIMIIuCfI- on~-
II'om8rIy NnS45)
O..M'" of CorNnIn::8

-------
EPA/ROD/R09-90/048
Stringfellow, CA
Fourth Remedial Action
Abstract (continued)
monitoring wells, and surface channels: and constructing a surface barrier and leachate
collection system downgradient from the original evaporation ponds. In 1983, the first
Record of Decision (ROD) provided an interim remedial measure and addressed additional
fencing of the site and implemented erosion control and offsite disposal of the extracted
leachate. In 1984, a second ROD addressed construction of an onsite pretreatment plant
for contaminated ground water, and the third ROD in 1987, specified installation of a
ground water extraction system in the lower canyon area (Zone 3), as well as surface
channels to direct surface water runoff. This fourth ROD addresses the contaminated
ground water in Zone 1 (an interim measure) and in Zone 4, and proposes treatability
studies to remediate the source material in Zone 1. A future ROD will specify the source
treatment methods as well as a remedy for any remaining ground water contamination in
Zone 1. The primary contaminants of concern affecting the ground water include VOCs such
as TCE.
The selected remedial action for this site includes dewatering the bedrock in the
original disposal area (Zone 1), followed by ground water treatment at the existing
pretreatment plant, and offsite discharge to a publicly owned treatment works (POTW)
facility: ground water pumping and treatment using air stripping or granular activated
carbon, and reverse osmosis in Zone 4, followed by onsite reinjection or disposal in an
industrial sewer; conducting field tests on reinjection of treated ground water into
Zones 2 and 3: and performing treatability tests on soil vapor extraction at Zone 1. The
estimated present worth cost of this remedial action is $115,000,000, which includes
unspecified O&M costs.
PERFORMANCE STANDARDS OR GOALS: No remediation goals have been determined in this ROD
for Zone 1 ground water contamination, because this is an interim measure.
Chemical-specific goals for ground water in Zone 4 include TCE 5.0 ug/l (SDWA MCLs).

-------
                 RECORD OF DECISION DECLARATION

SITE NAME AND LOCATION

Stringfellow Hazardous Waste Site
Riverside County, California

STATEMENT OF BASIS AND PURPOSE

     This decision document for the Stringfellow site in
Riverside County, California selects certain interim remedial
actions, which have been chosen in accordance with the
Comprehensive Environmental Response, Compensation, and Liability
Act  (CERCLA), 42 U.S.C. §§ 9601 e£. sea.. as amended by the
Superfund Amendments and Reauthorization Act of 1986 (SARA), and
the  National Contingency Plan, 40 C.F.R. Part 300.  The decisions
in this ROD  are  based upon the contents of the administrative
record for the Stringfellow site.

     The State of California, while given the opportunity to
concur upon  the  remedy selected in this Record of  Decision,
remains silent.

ASSESSMENT OF THE SITE

     Actual  or threatened releases of hazardous substances from
this site,  if not addressed by implementing the response actions
selected in  this ROD, may present an imminent and  substantial
endangerment to  public health, welfare  and the environment.

DESCRIPTION  OF THE  REMEDY

     This  is the fourth  interim action  ROD for the site.   The
first ROD  involved  initial abatement activities including
fencing, erosion control, interim source control,  and  off-site
hauling and  disposal  of  contaminated liquids.  The second  ROD
involved construction of an on-site  pretreatment  plant to  treat
contaminated groundwater.  The third ROD  involved  installation of
a groundwater barrier system  in the  lower canyon  and  installation
of  peripheral surface channels to direct  upgradient surface  water
runoff.  This fourth  interim  action  ROD addresses  the  groundwater
pathway  in Zone  1  (the original disposal  area)  and Zone 4  (the
Community)  by selecting  actions  that mitigate  further  degradation
of  groundwater at the disposal source  and downgradient.  The
major components of the  selected  remedies  include:

     —  Dewatering  of the original  disposal  area,  Zone i;  using  a
     system of extraction wells,  followed by treatment of the
     extracted water  at  the  existing mid-canyon pretreatment
     plant and disposal  to  a  POTW for  further treatment;  and

     —  Installation  of  a groundwater extraction system in the
     community  to  extract and treat contaminated groundwater that

-------
     has migrated downgradient to Zone 4,  followed by reinjectio^
     of the treated water.

     In addition, a field test of soil-vapor extraction will be
performed  to determine the technology's implementability,
effectiveness, and costs for removal of volatile organic
compounds (VOCs) from Zone 1 soils.  Field studies on reinjection
of treated groundwater into Zone 2 and 3 also will be pursued.


STATUTORY DETERMINATIONS

     The selected remedy is protective of human health and the
environment,  complies with federal or state requirements  that are
legally applicable or relevant and appropriate to the remedial
action, and is cost effective.  This remedy utilizes permanent
solutions and treatment technologies to the maximum extent
practicable and  satisfies the statutory preference for remedies
that employ treatment that reduces toxicity, mobility, or volume
as a principal element.
                 LO
DANIEL wv MCGOVERN     A^                    Date
Regional  Administrator

-------
                     1990 RECORD OF DECISION
                         DECISION SUMMARY
                STRINGFELLOW HAZARDOUS WASTE SITE
                  SITE LOCATION AND DESCRIPTION

     The Stringfellow Hazardous Waste Site (also referred to as
"site," "Stringfellow," or "Stringfellow site") is located in
Riverside County, California, approximately 50 miles east of Los
Angeles (Figure l).   The original disposal area is located at the
head of Pyrite Canyon in the southern portion of the Jurupa Moun-
tains.  The plume of contaminated groundwater, extending ap-
proximately 2 miles south of U.S. Highway 60 into the community
of Glen Avon, is located within the Glen Avon Basin aquifer,
which in the past served as a source of drinking and agricultural
water.  At present, the Glen Avon Basin aquifer does not serve as
a primary source of drinking water for local residents.

     The remedial actions selected in this Record of Decision
(ROD) address the pathway of primary concern to public health,
exposure to contaminated groundwater.  These measures offer an
opportunity to reduce site-related risk and prevent further
degradation of downgradient groundwater.

     For purposes of organizing remedial  investigation/feasiblity
study  (RI/FS) information, the site, including  its contaminated
plume of groundwater, has been divided into four geographic zones
(Figure 2).

     The term "on-site" used to describe  Zone  l is in  reference
to the zone as the orginal disposal area, and  not to the defini-
tion of "on-site" in the National Contingency  Plan  (NCP).  The
MCP defines on-site as the "areal extent  of contamination and all
suitable areas in very close proximity to the  contamination
necessary for implementation of  the response action."   40 C.F.R.
section 300.5; 55 Fed. Reg.  8817  (3/8/90).  Using the  NCP defini-
tion,  the entire plume of contamination,  and therefore all  zones,
is considered "on-site."  Pursuant to CERCLA section I21(e), no
federal, state or local permit  is  required  for any  remedial ac-
tion conducted entirely on-site  as long as  the actions are  taken
within the zone  and the substantive portions or the ARAR are ad-
dressed.

-------
Zone l:   Qn-site/Upper Mid-Canvon Area

     Zone l includes the original 17-acre disposal area in the
northern part of Pyrite Canyon,  southward to approximately 600
feet below the subsurface barrier.  There is no residential or
commercial population in this zone.   Zone 1 groundwater is con-
taminated with a large number of organic and inorganic con-
taminants, including heavy metals.

Zone 2;   Mid-Canvon Area

     Zone 2 encompasses the portion of Pyrite Canyon that extends
from the southern edge of Zone l to the existing mid-canyon ex-
traction wells.  Zone 2 has no residential population and limited
commercial use as a rock quarry.  Zone 2 groundwater is
moderately to heavily contaminated.  The contaminants of concern
are primarily soluble, volatile organics, and soluble inorganics.
Moving southward through Zone 2, the groundwater contains rapidly
decreasing to neglible amounts of heavy metals.

Zone 3:   Lower Canvon Area

     Zone 3 extends from the mid-canyon extraction wells down to
the lower canyon extraction system, north of U.S. Highway 60.
There are no private  residences  in Zone  3, although two active  T
businesses are  located within the zone.  Zone  3 groundwater  is
low to moderately contaminated.  The contaminants of concern are
soluble, volatile organics, and  soluble  inorganics.

Zone 4;  Community  of Glen Avon  Area

     Zone 4  includes  the area south of Highway 60 to the  leading
edge of  the plume of  site-related contaminated groundwater,  ap-
proximately  12,000  feet  from Zone  1.  The  affected area  is popu-
lated with a number of  private  residences.   The contaminants  of
concern  in the  groundwater  in this  zone  are  relatively  low  levels
of  a small number of  soluble, volatile organics,  and  soluble  in-
organics.  At  present,  the Glen Avon  Basin aquifer  (within which
the Stringfellow plume  lies) does  not  serve  as a  primary source
of  drinking  water for local  residents.

              SITE HISTORY AND  ENFORCEMENT  ACTIVITIES

     The site  was operated  by  the Stringfellow Quarry company
from August  21,  1956, to November 19,  1972,  as a  state authorized
hazardous waste disposal facility.   Approximately 34  million gal-
lons of  industrial  wastes  (primarily from metal finishing,
                               - 2 -

-------
electroplating and DDT production)  were placed in unlined
evaporation ponds located throughout the 17-acre disposal area.
Some of these wastes migrated downward, entered the groundwater,
and moved various distances downgradient.   The site was volun-
tarily closed in 1972.

Removal Activities

     In 1975, after declaring the site a public nuisance, the
California Regional Water Quality Control Board (RWQCB) began
studies to evaluate alternatives for abatement of the risks posed
by the site.  Between 1975 and 1980, the RWQCB developed reports,
conducted a controlled release of contaminants to Pyrite Creek
after heavy rains, and removed approximately 6.5 million gallons
of liquid wastes and DDT contaminated material.

     In 1980, federal involvement was initiated at Stringfellow
after an inspection by the U.S. Environmental Protection Agency
(EPA) and the U.S. Coast Guard (USCG).  The EPA Regional Response
Team (RRT) and the USCG Strike Team, using EPA funds, assisted
the RWQCB in mitigating the threat of a catastrophic discharge of
contaminated water.  This response resulted in the removal of ap-
proximately 10 million gallons of contaminated water, reinforce-
ment of containment barriers, and improvements to the truck load-
ing area.  Other activities completed by the RRT and USCG after
1980 include installation of a french drain, spring box, sumps,
and fencing, and improvements to surface drainage.

     In 1980, the RWQCB adopted an  Interim Abatement Program
(IAP) to further address the site.  The IAP was designed to con-
tain the wastes and minimize the risk of further contaminant
migration.  The program included the removal of all surface li-
quids; partial neutralization and capping of the wastes; instal-
lation of a gravel drain network,  interceptor  wells, monitoring
veils, and surface channels; and construction  of a clay core  sub-
surface barrier and leachate collection system downgradient of
the original evaporation ponds.

     In 1981, the California Department of Health  Services  (DHS)
became the  lead state agency for Stringfellow-related  cleanup,
although the RWQCB continued its involvement  at  the  site.
The Stringfellow site was  placed on the Environmental  Protection
Agency's  (EPA) National Priorities  List  in 1983.

-------
Interim Remedial Measures

     On July 22, 1983,  EPA signed its first Record of Decision
(ROD) selecting certain interim remedial measures (IRM)  and al-
lowing the state to be  reimbursed for the earlier abatement ac-
tions taken by the RWQCB.  Among other actions,  the IRM included
additional fencing of the site, erosion control, and hauling and
off-site disposal of extracted leachate.  The IRM were undertaken
primarily by DHS using  EPA funding under a cooperative agreement.
DBS began receiving such funding in 1983.

Fast-Track Remedial Investigation/Feasibility Study

     EPA conducted a fast-track remedial
investigation/feasibility study (RI/FS) between September 1983
and May 1984.  Based primarily upon the fast-track RI/FS, a
second ROD was issued by EPA on July 18, 1984.  The ROD selected,
as an interim measure,  the construction and operation and main-
tenance of a mid-canyon extraction well system and pretreatment
plant to remove and treat contaminated groundwater.

     The pretreatment system consists of lime precipitation for
metals removal, followed by granular activated carbon treatment
for  removal of the organic contaminants.  Under a discharge per-
mit  from the Santa Ana Watershed Project Authority  (SAWPA), the
treated effluent  is currently trucked to a local  industrial sewer
line, the Santa Ana Regional Interceptor (SARI).  The effluent
then receives additional treatment at a publicly-owned treatment
works  (POTW) in Orange County.  Sludge generated  from the
pretreatment process is  dewatered and taken to  an EPA-approved
land disposal facility.

     Although DHS  holds  the discharge permit  from SAWPA, EPA  has
entered into an  interagency agreement with the  U.S.  Army Corps  of
Engineers  (the Corps)  for  field oversight of  the  pretreatment
plant.  The Corps,  in  turn, uses a contractor to  operate and
maintain the pretreatment  plant.

     The pretreatment  plant's  influent,  treatment process,  and
effluent are monitored extensively to  ensure  quality performance.
Since  start-up  operations, the  plant has consistently met  the
stringent  requirements of  SAWPA's discharge permit.   As  of Decem-
ber,  1989, over  30 million gallons of  contaminated groundwater
have been  treated at the plant,  and  approximately 15,000 pounds
of metals  and  135,000  pounds  of organics have been removed.
Pretreatment plant operations  are ongoing.
                               -  4 -

-------
Full-Scale Remedial Investigation/Feasibility Study (RI/FS)

     With funding provided by EPA under the cooperative agree-
ment, DHS procured a contractor to conduct a full-scale RI/FS for
the Stringfellow site.  The RI/FS was initiated in 1984 to
characterize the site and to identify and evaluate alternatives
for final site cleanup.  The FS assessed 86 potentially ap-
plicable technologies.  Certain of these technologies have been
combined into five remedial alternatives (RAs).  Detailed evalua-
tion of the five alternatives was performed, as were a number of
treatability studies.  Although a majority of the work on the
RI/FS has been completed, work is still ongoing, including addi-
tional soil treatability studies (see "Highlights of Community
Participation").

     The draft RI report was released to the public in June,
1987, followed by the draft FS report in June 1988.  Public meet-
ings on the draft FS  report were held in September 1988.

Alternate Water Supply

     Analysis of water samples taken during  site investigations
detected radiation.   In  response, DHS sampled private drinking
water supply wells  in the site area.  Although  the elevated
levels of radioactivity  were later determined to be naturally oc-
curing and not related to the contamination  at  the site,  in the
summer of 1984,  in  response primarily to continued concern with
drinking water quality,  DHS initiated an  interim program  to
provide bottled water to nearly  400 Glen Avon  residences.
Bottled water was  supplied to give anyone  in identified areas of
elevated groundwater  radioactivity an alternate supply of domes-
tic  water, and to  eliminate any  domestic dependence on
groundwater near the  potential  influence of  contamination from
the  Stringfellow site.   In October 1985, California Senate Bill
1063 provided  State funds  to hook up residences, which had been
receiving State  supplied bottled water,  to the  Jurupa  Community
Services District.   The  connections  began  in June  1986, and  were
completed in  1989.

Earlv Implementation Actions

     Based upon  the ongoing  remedial alternative  (RA)  evaluation
in the  full-scale  RI/FS, additional  interim remedial  activities
were selected  in a third ROD  issued  by EPA on June 24,  1987.
These additional actions included:  l)  the installation of a
•groundwater  extraction system  in the lower canyon area (Zone 3)
with treatment of  the extracted groundwater at the existing

-------
 pretreatment  plant;  2) the installation of surface channels
 around  the  north end of the original disposal area in Zone l; 3)
 the  southward extension of the existing eastern and western sur-
 face channels;  and  4)  the reconstruction of  the Pyrite Creek
 channel.

     Using  cooperative agreement  funding, DHS procured contrac-
 tors to design these actions, and to construct the surface chan-
 nels around the north  end of the  orginal disposal area and the
 southward extension of the existing surface  channels.  DHS' con-
 tractors completed  the design in  1988 and the construction of the
 channels in 1990.   A number of potentially responsible parties
 (PRPs), through an  Administrative Order on Consent  (AOC),  in-
 stalled the extraction system and reconstructed the Pyrite Creek
 channel (see  "Federal  Enforcement," below).

 Federal Enforcement

     In August and  October 1982,  EPA  issued  to over 200  poten-
 tially  responsible  parties (PRPs), General Notice and Demand  let-
 ters, combined with information  requests, under sections 104  and
 113  of  the  federal  Comprehensive  Environmental Response, Compen-
 sation, and Liability  Act  (CERCLA).   The governments' negotiators
 held an initial meeting with the  PRPs  in November  1982,  follower'
 by a number of settlement meetings.   An acceptable  settlement
 agreement was not  reached.

     On April 21,  1983, the United  States and  the  State  of
 California  filed  a  civil  suit  in  the  United  States  District  Court
 for the Central District  of California  (U.S. v. J.B.  Stringfel-
 low. Jr.. et. al..  Civil  Number  83-2501 JMI  (C.D.  Cal.)).
 Eighteen generators, four  transporters, and  nine  owner/operators
 were named  as defendants  in the  lawsuit.  On June  4,  1987, the
 District Court granted the government's motion for  partial sum-
 mary judgment against  fifteen  of  the  defendants  on the  issue of
 liability under section 107 of CERCLA.  A  sixteenth defendant
 recently has  been added to  the  judgment.   A  case  management  order
 divides the litigation into three phases:   1)  liability, 2)
0remedy/damages, and 3) cost allocation.   Litigation is  ongoing.

     To facilitate  legal  discussions  with  the governments, fol-
 lowing  suit initiation,  the defendants formed a steering com-
 mittee. A  technical subcommittee was also  formed and meets with
 EPA and DHS technical staff  approximately once every quarter to
 exchange  technical  information.   The community's technical ad-
 visor  is  invited to these meetings.   Local and other state
 government  representatives are also invited depending on the
                               - 6 -

-------
agenda covered by the technical discussions.

     In Ma'y 1988, sixteen of the defendants agreed, in an Ad-
ministrative Order on Consent (AOC),  to construct certain of the
interim actions that were selected in the third ROD issued by EPA
on June 24, 1987.  The AOC did not include the design and opera-
tion and maintenance of the groundwater extraction system, the
installation of the northern channels or the southward extension
of the existing channels.  Rather, using cooperative agreement
funding, DHS' contractors completed the design and constructed
the channels.  Operation and maintenance of the pretreatment
plant resides with EPA.

Proposed Remediation Plans

Community Groundwater Proposed Plan

     In June 1988, EPA and DHS released a Proposed Plan to ad-
dress site-related groundwater contamination in the community of
Glen Avon  (Community Groundwater  Proposed Plan).  The Plan
proposed to extract, treat  (through air stripping and reverse
osmosis), and reinject the treated groundwater.  The public had
an opportunity to comment on the  Community Groundwater Proposed
Plan from June to November  1988.  Two public meetings addressing
the Plan were held in September  1988.

Overall Proposed Plan

     At one of the public meetings in September  1988, Riverside
Representative George Brown  held an open congressional hearing on
the Stringfellow site.   At  the hearing, the Agencies' agreed  to
conduct additional soil  treatability studies before maJcing  a
decision on the  final  remedy for Zone  1.  Testimony by members of
the community and the  U.S.  Office of Technology  Assessment
reflected  the belief that certain soil  treatment  technologies
should be  further evaluated because of  possible  technical
developments  since the  issuance  of the  draft  FS  report.

     In response to  the  hearing  and  to  public  input,  EPA and DHS
developed  a  new  remedial alternative,  RA6.  consequently in
February  1989, the Agencies released  for  public  comment  a second
plan  (Overall Proposed  Plan) proposing  to  implement  RA6.   EPA and
DHS also  released a  fact sheet in April 1989  reflecting  recalcu-
lated  estimated  groundwater flow in  the community area  (Zone 4).
The April  fact sheet described the revised estimated cost com-
parisons  and cleanup times  for the Community  Groundwater Proposed
Plan,  and  for  the RAs  considered in  the draft FS report.

-------
     The., proposed remedy,  RA6 ,  of the Overall Proposed Plan in-
cluded, for Zones 2-4, the long-term continuation of
downgradient plume management activities.   For Zone 1, the Plan
proposed to dewater the area, use soil-gas extraction
(hereinafter referred to as "soil-vapor extraction," or "SVE")
for removal of volatile organic compounds  (VOCs) if tests proved
favorable, complete additional soil treatability studies, and in
stall an improved cap.

              HIGHLIGHTS OF COMMUNITY PARTICIPATION

     The community of Glen Avon has been kept actively informed
of the cleanup progress and actions taken at the Stringfellow
site.  One of the primary means of keeping the public informed
has been through the DHS publication of the "Stringfellow
Update."  Updates have been published approximately every other
month since late 1984, and are mailed to. over 3,000 Glen Avon
residents and interested parties.  The Community Groundwater
Proposed Plan was released through the June/July 1988
"Stringfellow Update," and the Overall Proposed Plan through the
February/March 1989 "Stringfellow Update."

     C Comment Periods
     EPA and DHS sought public comment on the draft RI/FS repor,.
and on the two proposed plans.  The comment period for the draft
RI report began in June etnd ended in October 1987.  The public
had an opportunity to comment on the draft FS report and Com-
munity Groundwater Proposed Plan from June through November  1988
The comment periods  for the Overall Proposed Plan and the April
fact sheet began in  March 1989, and April 1989,  respectively.
The comment period for both documents closed in  June 1989.

     c Meetings
     Public meetings and workshops have been held  in  and  near
Glen Avon  to  present cleanup  information  and to  receive  input
from the public.   Public meetings on the  draft FS  report  and Com-
munity Groundwater Proposed Plan were held  in Riverside  and
Orange Counties  in September  1988.  A public meeting  on  the Over-
all Proposed  Plan  was held in Riverside County in  March  1989.

     In addition to public meetings, the  Stringfellow Advisory
Committee  (SAC) --- an amalgum  of community,  government, and
private interests --- meets once a month to discuss  cleanup
progress at the site, and the remedial activities  being  pursued
by EPA and DHS.  The SAC is comprised of  a  community  leader,


                               - 8  -

-------
elected representatives,  local officials,  and EPA and DHS staff
and management.   SAC meetings are open to  the public.

community Input:  ROD

     Public comment, in various forums, indicated the community's
strong belief that the final remedial decision for Zone 1 should
be deferred until after the completion of  additional soil
treatability studies.  Nevertheless, pending the studies, the
community supported the issuance of a separate ROD to address
the cleanup of the groundwater underlying the Glen Avon area
(Zone 4), and the dewatering and soil-vapor extraction actions in
Zone l .

     The Agencies agreed with the suggestions provided by the
community, and have adopted its strategy as reflected in this ROD
(see "Scope and Role of Response Actions of This ROD").  The
final remedial decisions on the long-term plume management, and
the final response actions for Zone 1, will be addressed in a
subsequent ROD, following completion of the RI/FS, including the
additional soil treatability studies.

Community Input;  Significant/Episodic Storm and Seismic Events

     In response to community concerns regarding flooding and
possible exposure to contaminants via the surface water pathway,
EPA and DHS are evaluating the potential effect
significant/episodic storm or seismic events may have on the
site's engineered structures and downgradient community.  After  a
conceptual plan for the analysis was presented to the public for
comment in March 1990, the Agencies' proposed a detailed analyti-
cal approach and again sought public comment.  EPA and DHS will
share their written analyses  for discussion with the SAC.

Communit  Input:  Additional  Soil Treat    ii.v Studies
     Following  the Agencies'  agreement  ~o  conduct  additional  soil
 treatability  studies  for  Zone 1,  EPA and DHS  prepared discussion
 papers on the purpose and objectives of the studies.   EPA's Of-
 fice of Research  and  Development  (ORD)  is  providing technical ex-
 pertise and analysis  to assist the. Agencies in determining the
 implementability , costs,  long-term and  short-term  effectiveness,
 and reduction in  contaminant  toxicity,  mobility, and volume  (TMV)
 of the soil technologies  being considered.  The information
 gained from these treatability studies, along with the alterna-
 tives currently in the draft  FS report, will  be evaluated by  EPA
 and DHS  (using  the nine superfund criteria described under
                               - 9 -

-------
"Summary of Comparative Analysis")  in making the final remedial
decision for the Zone 1 area.   The treatability studies process
is currently under discussion between EPA,  DHS, and the com-
munity.

Information Repositories

     Documents issued for public comment, such as the draft RI/FS
reports, proposed plans, and other information relevant to the
Stringfellow site remediation and decision-making process are
routinely transmitted to and made available for inspection at a
number of information repositories located in Riverside and
Orange Counties.  The Administrative Record for this ROD will be
located at EPA's offices in San Francisco,  DHS' offices in
Sacramento, and the Glen Avon Branch Library.

Responsiveness Summary

     During public comment periods and associated public meet-
ings,  residents, elected officials, community organizations, the
community technical advisor, and the PRPs submitted comments on
the draft RI report, draft FS report, and two proposed plans.
The attached responsiveness summary responds to those comments
relevant to the remedial decisions selected  in this ROD.

          SCOPE AND ROLE OF RESPONSE ACTIONS IN THIS ROD

     The primary pathway of concern  for  the  response  actions
selected in this ROD  is groundwater.  As described  in  the Com-
munity Groundwater Proposed Plan,  the ROD  incorporates the  deci-
sion to remediate the  site-related contaminated plume  of
groundwater in  the community area  (Zone  4).   In addition, the  ROD
selects two source control measures  for  Zone 1  identified  in the
Overall Proposed  Plan:   l) dewatering, and  2)  field testing of
soil-vapor extraction (SVE).  These  interim response  actions are
limited in scope, and after the RI/FS and  additional  soil
treatability  studies  are completed,  will be followed by  selection
of  the final  site  remedy.   Accordingly, while the  Agencies have
identified certain contaminant-specific  remediation goals  in  this
ROD, cleanup  levels  for the  site as  a whole cannot  be finalized
until  the  long-term  plume  management of  the zones  is decided.
The response  actions  selected  for  Zone  4 in this  ROD are,  there-
fore,  interim decisions,  although the Agencies do  not envision
any additional  selection of  cleanup technologies  for this  zone.
                               -  10  -

-------
                 SUMMARY OF SITE CHARACTERISTICS

     This section summarizes information in the draft RI report
that is relevant to the remedial actions considered in this ROD.

     During operation of the Stringfellow site, liquid wastes
were placed in unlined ponds located throughout the 17-acre dis-
posal area.  Some of the wastes migrated downward, entered the
groundwater, mixed with clean groundwater,  and moved various dis-
tances dovmgradient, depending upon the chemical and physical in-
teractions with the geologic units.

     Groundwater contamination extends from Zone 1 into the com-
munity of Glen Avon, Zone 4, as shown in Figure 3.  The leading
edge of the contaminant plume is defined by the presence of
trichloroethylene  (TCE) in groundwater, and is approximately
11,000 to 12,000 feet south-southwest of Zone  l at the intersec-
tion of Agate Street and Jurupa Road in Glen Avon.  The plume
width in the Glen Avon area is up to 900 feet.

Zone l

     The soil/fill  material in Zone 1 is contaminated with a
variety of chemicals, including chlorinated solvents, pesticides,
PCBs, heavy metals, acidic materials, and volatile and semi-
volatile organic pollutants.  The predominant  organic contaminant
identified  in Zone  1 soils  is para-chlorobenzene sulfonic acid
(p-CBSA), a by-product of DDT manufacturing.   Volatile organics
(e.g., TCE and chloroform) constitute less than l percent of the
soil contaminant mass.  Metals such as  nickel, chromium, and cad-
mium are present.   Sulfates are also found in  high concentra-
tions.

     The inorganic  and organic contaminants which have migrated
from the soils  into the groundwater in  this zone, and which  con-
stitute the greatest percentage of the  contamination, are  the
sulfates and p-CBSA, respectively.  Eased on  available  informa-
tion and studies,  p-CBSA  is not considered to  be  toxic  to  human
health.  Sulfates  can be  harmful  in high concentrations.   Metals,
such as cadmium, chromium,  and nickel,  and VOCs,  such as
chlorobenzene,  chloroform,  and trichloroethylene  are  also  found
in  the Zone l groundwater.  The VOCs constitute  less  than  1  per-
cent of the dissolved organic carbon  in the groundwater, but many
individual  components exceed  federal/state drinking  water  levels.
Mean concentrations of  at least  eight  inorganic constituents and
nine organic constituents exceed  federal maximum  contaminant
levels  (MCLs),  secondary  maximum  contaminant  levels  (SMCLs),
                              - 11 -

-------
maximum contaminant level goals (MCLGs),  or adjusted ambient
water quality criteria (AWQC):   cadmium,  chromium, copper,
fluoride, iron, manganese, nitrate, zinc, chlorobenzene,
chloroform, l ,2-dichlorobenzene,  l,4-dichlorobenzene,  1,2-
dichloroethylene, l,1,2,2-trichloroethane,  tetrachloroethylene,
trichloroethylene,  and xylene.

     Groundwater contamination is prevalent in all three
groundwater strata (alluvium, decomposed granite, and bedrock) in
Zone 1.

Zone 4

       The draft RI report found that in Zone 4, the only site-
related organic groundwater contaminant that exceeds federal max-
imum contaminant levels  (MCLs) for drinking water is TCE.  The
federal MCL is 5 ug/1.  TCE, as measured in 1985 and 1986 and
reported in the draft RI  report, reached as high as 436 ug/1  in
this zone.  At the plume's leading edge  (Agate and Jurupa
Streets) TCE was detected at less  than the MCL.

     Chloroform  is also  found  in excess of health-based levels.
In the absence of a federal MCL specific to chloroform, the
Agencies are looking to  the concentration, 6.0 ug/1, associated
with an excess cancer risk of  10~6 as the  level  that is protec-
tive of human health.  This concentration  coincides with  the
State of California's Action Level.  Chloroform  concentrations as
measured in 1985 and 1986 and  reported in  the draft RI report,
reached as high  as 32 ug/1 in  the  Zone 4 plume.

     Other dissolved organic contaminants  measured  above  back-
ground in  Zone  4 include chlorobenzene,  l,2-dichlorobenzene,  and
p-CBSA.  With  respect to the first two contaminants, the  levels
found  in the groundwater are lower than  proposed federal  MCLs
(the proposed MCL  for chlorobenzene  is  .1  mg/1  and  for 1,2
dichlorobenze  is  .6 mg/1).  There  are no standards  or guidelines
for p-CBSA, but  as discussed earlier, p-C3SA  has not been deter-
mined  to be toxic  to human health.

     With  respect  to  inorganic compounds,  the findings of the RI
indicate that  there  is  no heavy  metal contamination in  Zone 4
groundwater.   As pH  increases, heavy metals  in  the  groundwater
precipitate  from solution or  react with  aquifer materials ap-
proximately  1,000  feet  downgradient  of  the subsurface  barrier in
Zone  1.  The  inorganic  contaminants  found  in  the downgradient
zones  are  sulfates and  nitrates.   Within the  plume  of  con-
taminated  groundwater,  concentrations of these  contaminants are
                              - 12 -

-------
as much as 4 to 5 times higher than within the surrounding
aquifer.    Plume concentrations of nitrates and sulfates exceed
the federal MCL and proposed MCL, respectively,  with respect to
nitrates, currently available data indicate that anthropogenic
background levels in the community area also are elevated and
exceed the federal MCL.

     The contaminants in Zone 4 are predominantly confined to the
alluvium (uppermost) groundwater stratum.  Groundwater contamina-
tion underlying the community can be described three dimen-
sionally as a relatively narrow plume, increasing from ap-
proximately 300 to as much as 900 feet wide, and extending to as
deep as 100 feet below the surface.  TCE contamination has
migrated 11,000 to 12,000 feet southwest of Zone 1, and is
migrating at an approximate effective rate of  250 feet per year
(assuming that groundwater and its dissolved TCE are moving at
the same rate).

     Zone 4 is highly populated, and contains  private residences
with operable water wells.  Few private wells  have been found to
be contaminated, and none are presently used for drinking water.

                      SUMMARY OF SITE RISKS

     The baseline risk assessment conducted as part of the RI ex-
amined human  ingestion of contaminated groundwater and surface
water, ingestion of contaminated soil, and  inhalation of airborne
contaminated  soil particles and volatile compounds.  Because  this
ROD focuses on remedial actions affecting the  groundwater path-
way, the risk assessment  findings 'for this  pathway alone are  sum-
marized.

Groundwater Pathway

     The findings of the  RI  risk assessment  indicate that the ex-
posure pathway of primary concern  is  the potential human exposure
to contaminated  groundwater.   As discussed  earlier,  the
groundwater beneath  Zone  1  is  contaminated  with  a  large number  of
soluble organic  and  inorganic  contaminants,  including heavy  met-
als.  Moving  southward along  the  plume to  Zone 2,  the groundwater
is moderately to heavily  contaminated with  soluble,  volatile or-
ganics and  soluble  inorganics.   In this  zone,  the  heavy metals
begin to rapidly decrease and become  neglible  before entering
Zone 3.  The  Zone  3  groundwater  is minimally to  moderately con-
taminated with soluble, volatile organics,  principally  TCE and
chloroform, and  soluble,  inorganics,  principally nitrates  and
sulfates.   At the downgradient end of the  plume  in Zone  4, the
                              - 13. -

-------
concentrations of the carcinogenic compounds (principally TCE and
chloroform),  and of the inorganic compounds (principally nitrates
and sulfates) have significantly decreased from Zone 1.

Contaminants of Concern

     TCE and chloroform were selected as the basis for the public
health evaluation of the groundwater exposure pathway because
they are the only carcinogenic chemicals found above federal MCLs
or health-based levels in the community plume, and thus presented
the greatest human exposure risk.

Exposure Assessment

     The Stringfellow plume of contaminated groundwater lies
within the Glen Avon Basin aquifer.  The aquifer is not currently
used as a drinking water supply for local residents.  However, it
is considered to a be a potential source of drinking water and is
located within a groundwater subbasin  (Chino III) with Class I
characteristics.

Toxicity Assessment and Health Effects

     TCE has a relatively low acute toxicity, but exposure to
high doses can cause central nervous system depression, long-ter^
neurological effects, dermatitis, and  peripheral neuropathy.  TCE
is a probable human carcinogen and a proven animal carcinogen.
Chloroform can cause nausea, dizziness, and acute central nervous
system depression, as well as chronic  liver and  kidney damage.
This substance has been listed as a probable human carcinogen by
EPA.

     Cancer  potency  factors have been  developed  by EPA's Car-
cinogenic Assessment Group for estimating  the excess  lifetime
cancer risks associated with exposure  to potentially  carcinogenic
chemicals.   The  cancer potency factor,  expressed in units of
(mg/kg/day)   ,  is  multiplied by  the average  intake of a potential
carcinogen to provide an estimate of the upper bound  lifetime ex-
cess cancer  risk associated with exposure  at  that  intake  level.
The term  "upper  bound" reflects  the conservative nature of  the
risks calculated from the cancer potency  factor, which  are  un-
likely to  underestimate the actual cancer  risk.   The  cancer
potency factors  are  derived  from the results  of  human
epidemiological  studies or chronic animal  bioassays  to  which un-
certainty  factors have been added.  The cancer potency  factor  for
TCE is l.l x 10~2 (mg/kg/day)   .   The  cancer  potency  factor for
chloroform is  8.1 x  10~z  (mg/kg/day)   .
                              - 14 -

-------
     The toxicity of nitrate in humans is due to the body's
reduction of nitrate to nitrite.   This reaction takes place in
saliva of humans at all ages and in the gastrointestinal tract of
infants during the first three months of life.  The toxicity of
nitrite is demonstrated by vasodilatory/cardiovascular effects at
high dose levels and methemoglobinemia at lower dose levels.
Methemoglobinemia is an effect in which hemoglobin is oxidized to
methemoglobin resulting in asphyxia.  Infants up to 3 months of
age are the most susceptible subpopulation with regard to
nitrate.  50 Fed. Reg. 46973 (November 13, 1985).

     There is no evidence of adverse chronic health effects in
animals or humans from exposure to sulfate in drinking water, 50
Fed. Reg. 46979  (November 13, 1985).  The only adverse effects
noted from exposure to high levels of sulfate are diarrhea and
dehydration.  Infants appear to be more sensitive to sulfate than
adults.  There are  limited data on the acute effects of sulfate.
Information compiled  from questionnaires indicated that at con-
centrations of sulfate above 1,000 mg/1, the majority of respon-
dents noted a laxative effect.  Animal studies suggest that sul-
fate is not mutagenic, carcinogenic or teratogenic in mammals.
55 Fed. Reg. 30382  (July 25, 1990).

Risk Characterization

     The risk characterization quantifies potential  risks  to
human health in  the event that the contaminated plume of
groundwater is used as a residential  source  of drinking water.
The site-specific  risk values are estimated  by  incorporating  in-
formation from the  exposure assessment and the toxicity assess-
ment for the identified contaminants  of  concern.   Excess lifetime
cancer  risks are determined by multiplying the  intake or exposure
level by the cancer potency factor.

     Although no one  is currently using  the  contaminated plume  of
groundwater as a domestic water supply,  ingestion  of  the
groundwater currently underlying  the  community  zone  'Zone  4)  is
associated with  an excess cancer  risk of approximately  10" .
This risk increases by two  orders of  magnitude  to  approximately
10   moving upgradient  from Zone  4  to Zone  1.

     The exposure  assumptions  of  the  risk assessment	that an
individual weighing 70  kilograms  will drink  2 liters of water per
day  for 70 years	were used  to calculate the risks  associated
with use of this water  in the  community by  current and  future
residents.  In  addition,  the  risk calculation incorporated a
range of concentrations representing  the maximum and minimum
                              - 15 -

-------
measured levels for TCE and chloroform.

     Another indication of risks associated with human use of the
contaminated plume of groundwater is comparison to health-based
ARARs,  such as MCLs,  MCL goals, and State action levels.  Plume
concentrations are greater than ARARs for TCE, chloroform,
nitrates, and sulfates.

Zone 1  Risk Reduction

     The principal threat from Zone 1 derives from the presence
of a large mass of water-soluble contaminants that can migrate
and contaminate downgradient groundwater.  Water-soluble con-
taminants above health-based levels which have migrated the far-
thest are the volatile organic compounds (VOCs), principally TCE
and chloroform, and two inorganic compounds, nitrates and sul-
fates.   Although VOCs  represent less than one per cent of the
mass of contaminants present in Zone 1, they are significant be-
cause of their relative mobililty, and because they are the major
toxic organic contaminants found in the downgradient groundwater
plume.

Zone 4 Risk Reduction

     Response action in the community area  is necessary to reduc
the human health  risk  from contaminants  in  the plume of
groundwater to levels  that are protective of human health.
Response action  is also expected to prevent the  further migration
of the contaminated groundwater plume.   Without  remediation, con-
tinued plume migration could further contaminate  the Glen Avon
aquifer, as well  as parts of the larger  Chino III subbasin.  Ad-
ditional risks exist from exposure to contaminated groundwater
through  ingestion and, to a  lesser extent,  through dermal contact
and  inhalation of volatilized  chemicals.

                   DESCRIPTION OF ALTERNATIVES

     The following sections  discuss  the  alternatives considered
for  response actions  in  Zones  1  and  4.   The description of  the
alternatives,  as  well  as  the summaries of  the  comparative
•analysis,  reflect the  interim  and  limited  nature of  the Agencies'
response action  decisions  in this ROD.

Zone l

Dewatering
                              -  16  -

-------
     Active dewatering of the Zone 1 area is expected to reduce
the threat of further contamination of groundwater,  and to remove
substantial amounts of VOCs and other water-soluble, mobile con-
taminants currently in the groundwater.  Lowering the water table
in Zone 1 is also expected to reduce the long-term health risks
by decreasing the volume and mobility of VOCs and other soluble
contaminants.  Dewatering will serve to prepare the subsurface
for soil-vapor extraction (SVE) and/or other treatment tech-
nologies that may, as a result of currently ongoing treatability
studies, be selected in the final ROD.

Dewatering:  No Action Alternative

     The "no action" alternative involves no further effort to
control the source or the migration of site-related groundwater
contamination underlying Zone 1.  Inaction with respect to Zone 1
groundwater will  lengthen the time to achieve cleanup in all
downgradient zones.

Dewatering:  Gallery Drainage Tunnel  (Adit) System

     As described  in the draft FS report, one way to dewater Zone
1 is through a gallery drainage tunnel, or adit.  The oval-shaped
tunnel would be routed around Zone 1  and be constructed in com-
petent bedrock.   The gallery would include two sets of drain
holes drilled laterally, one set to drain contaminated
groundwater  from  beneath the site, and one set to redirect uncon-
taminated groundwater away from the site.  The drained water
would be piped to  the existing mid-canyon pretreatment plant for
removal of metals  and organic compounds.  The treated effluent
would then be transported to the Santa Ana Regional  Interceptor
(SARI) where it would be piped to a POTW for further treatment.

     Using the gallery system,  initial dewatering to bedrock is
anticipated  to take  one year,  and to  remove over  50% of the
soluble organics  and inorganics estimated to be present in  the
Zone 1 groundwater.   Depending upon  "he Agencies'  final remedial
decision for Zone 1,  maintaining the  lowered water  table  level
could be required in perpetuity.  The estimated costs  from  Appen-
dix A to the draft FS  report,  are presented, below.


     Capital cost:                          S  27,000,000
     Operations/Maintenance  (first  year):        500,000
                              - 17 -

-------
Dewaterir.    Surface Extraction Wells

     Anot: ^r way to dewater Zone 1 is through a series of
groundwater extraction wells.   Depending upon the cumulative ex-
traction rates of these wells  and drawdown characteristics, wells
would iteratively be added to  the dewatering matrix.   Installa-
tion, followed by a review of  effectiveness, would guide the
location and placement of subsequent wells.  Based upon the es-
timates of well yields and spacings required by the rock struc-
ture and the continuity of the fracture system, the draft FS
report conceptualized a total  of 18 to 36 wells.  The actual num-
ber of wells, however, may not be confirmed until most or all of
the wells have been installed and the system has been tested.
The extracted groundwater would be treated at the existing mid-
canyon pretreatment plant, transported to the SARI line, and, ul-
timately, to a POTW for further treatment.

     As with the gallery system, initial dewatering to bedrock is
anticipated to take one year,  and to remove over 50% of the
soluble organics and  inorganics estimated to be present in the
Zone 1 groundwater.   Depending on the outcome of the Agencies'
final remedial decision for Zone 1, maintaining the lowered water
table level could be  required in perpetuity.  The revised  es-
timated costs, including costs associated with maintaining the
dewatering system in  perpetuity, are presented, below.

     Capital cost:                          S 4,000,000
     Present Worth  (7% discount rate):      47,000,000

Zone 4

     Cleanup of  the site-related contaminated groundwater  in  the
community area  (Zone  4)  is a component  of  all  remedial  alterna-
tives  (RAs) evaluated in the FS report,  except  for the  "no ac-
tion" alternative.

Zone 4 Groundwater  Cleanup:  Mo action

     This alternative involves no  further  action  to clean  up the
site-related contaminated  groundwater  in the community  area,  or
to prevent the  further migration  of  the contaminant plume.

Zone 4 Groundwater  Cleanup:  Extraction,  No Treatment,  Disposal
                             to SARI
                              - 18 -

-------
     This alternative involves extracting contaminated water from
wells placed in the Zone 4 plume.   As the contaminated water is
extracted, uncontaminated groundwater from the surrounding
aquifer will naturally flush the plume clean over time.
The extracted groundwater would be discharged to the SARI in-
dustrial sewer line via an anticipated 15-mile pipeline, extend-
ing from Zone 4 to the sewer drop point.   The chemical quality of
the extracted water would be expected to be within the present
quality limits of the industrial sewer discharge permit for the
mid-canyon pretreatment plant, and therefore should not require
further treatment.  If the extracted water exceeds the water
quality limits of the discharge permit, or if discharge to the
industrial sewer is not permitted without treating the VOCs, the
VOCs would be removed prior to disposal.   For purposes of es-
timating costs, air stripping was assumed to be the treatment
technology for removing VOCs.

     Currently, under the SAWPA permit a maximum volume of
187,000 gallons per day can be discharged to the SARI  line.  The
discharge permit would likely have to be modified to allow  for
the much  larger volume expected to be generated by implementing
this alternative.

     Based upon a revised flow rate of 160 gpm, this alternative
is estimated to reduce TCE to the  federal MCL of 5 ug/1  in  ap-
proximately 75 years.  The estimated costs are shown,  below.

     Capital costs
      (pipeline extension, no  treatment):   S  11,000,000
     Present Worth  (7% discount rate):        48,000,000

     Capital costs
      (pipeline extension, air stripping):  S  12,000,000
     Present Worth  (7% discount rate):        52,000,000

Zone 4 Groundwater  Cleanup:   Extraction,  Treatment,  Reinjection

     As with the  previous alternative, this  alternative involves
extracting contaminated  groundwater  along the Zone  4 plume.   Un-
like the  previous  alternative,  this  alternative  involves replace-
ment of the extracted and treated  groundwater by  reinjection
along the periphery of  the  contaminant plume.   The  extraction and
reinjection wells  would  be  located and operated  in  a way to keep
the existing contaminated groundwater  plume  hydraulically con-
tained.   A closed system would  be  sought in  which contaminated
                              - 19 -

-------
groundwater flow is from less contaminated toward more con-
taminated groundwater.

     Pending confirmation by design studies, this alternative is
envisioned to involve the following processes:

o   Extraction of contaminated groundwater.

o   Treatment to remove volatile organic contaminants (air
    stripping).

o   Treatment to remove inorganic contaminants prior to
    reinjection (reverse osmosis (RO)).

o   Reinjection of treated water along the periphery of the
    plume.

o   Disposal of RO concentrate to the SARI line.

     Reinjection of the treated water is expected to hasten clean
up of the Zone 4 plume by a  factor of three.  The SAWPA permit
may need to be modified to allow for an increased volume that
could be generated by implementing this alternative.  Based on g
revised flow rate of 430 gpm, the estimated costs of this alter
native are provided, below.

     Capital costs
     (air stripping, RO, pipeline extension):   S  19,000,000
     Present Worth  (7% discount rate):          S  68,000,000
                   DESCRIPTION OF ALTERNATIVES:
               COMPLIANCE WITH OTHER LAWS AND ARARs

     Under Section  121(d) of  the  Comprehensive  Environmental
Response, Compensation,  and Liability Act  (CERCLA),  as  amended,
42 U.S.C. section  121(d), remedial  actions must  attain  a  degree
of cleanup that  assures  protection  of human  health and  the  en-
vironment.  Additionally, remedial  actions that  leave any hazard-
ous substance, pollutant, or  contaminant on-site must meet  a
cleanup  level or standard of  control that  at least attains
federal  and more stringent state  standards,  requirements,
criteria, or  limitations that are "applicable or relevant and ap-
propriate" under the  circumstances  of the  release.   These re-
quirements, known  as  "ARARs", may be waived  in  certain  instances.
CERCLA section I21(d)(4).  TO be  considered  as  ARAR, a  require-
ment must be  promulgated, 40  C.F.R.section 300.400(g)(4) ; be  sub-
                              - 20 -

-------
stantive rather than administrative,  55 Fed.  Reg.  8756-57 (March
8, 1990); and be a requirement of an  "environmental"  law as
provided in CERCLA section 121(d)(2)(A)(i).

     "Applicable" or "relevant and appropriate" requirements are
defined fully in the revised National Contingency Plan (NCP),  55
Fed. Reg. 8666-8865 (March 8, 1990),  40 C.F.R.  Part 300.  In sum,
"applicable" requirements are those standards,  criteria, or
limitations promulgated under federal or state environmental law
that specifically address a hazardous substance, pollutant, con-
taminant, remedial action, location,  or other circumstance at a
CERCLA site.  Where a promulgated standard,  criteria, or limita-
tion is not directly applicable, it may be "relevant and ap-
propriate"  if, in the exercise of the Agencies' discretion, it
addresses problems or situations sufficiently similar to those
encountered to be well-suited to the particular site.

     ARARs may be (a) "chemical-specific," which are generally
health- or  risk-based numerical values or methodologies that set
limits upon concentrations of specific contaminants in the en-
vironment;  (b) "location-specific," which are generally restric-
tions upon  certain types of activities because of existing site
characteristics  (e.g. wetland,  floodplain, historic site); or  (c)
"action-specific" , which are technology or activity based
restrictions triggered by the type of  remedial action under con-
sideration.  In  addition to ARARs, EPA or the State may, as ap-
propriate,  identify other advisories,  criteria, or guidance,
whether or  not promulgated, to  be considered for a particular
site.  While not mandatory, the Agencies may identify and  rely
upon TBCs,  as  they are known, to assist  in determining  what
cleanup  level  is protective or  to otherwise assist the  design of
Superfund remedies.

     The response actions considered and selected  in this  ROD  are
interim measures designed to mitigate  site-related risks to human
health and  the environment and  prevent further groundwater
degradation.   Accordingly, the  ARARs discussion below  focuses
primarily upon compliance with  those ARARs and  environmental  re-
quirements  specific  to the interim actions selected.  At the  time
the Agencies  finalize remedial  action  decisions  for  the site,
compliance  with  ARARs and  final selection of cleanup  levels will
be  fully addressed.
                                 :i -

-------
Zone 1:   Compliance With Other Laws and ARARs

ARARs

     For the action of dewatering, the federal Clean Water Act's
pretreatment standards, authorized under section 307(b), 33
U.S.C. section 1317(b), and 40 C.F.R.  Part 403; and the National
Pollutant Discharge Elimination System (NPDES) standards, under
section 311, 33 U.S.C. section 1317, are applicable to the off-
site discharge of treated water to the SARI sewer line.  Those
standards applicable are currently set forth  in the SAWPA permit
governing effluent discharges from the existing mid-canyon
pretreatment plant.  Disposal of the extracted water from the
dewatering system will be in compliance with  the existing permit
standards and any relevant modifications.  There are no
location-specific applicable or relevant and  appropriate require-
ments pertinent to the interim actions considered for zone l be-
cause it is not within 200 feet of a fault nor within a  100-year
floodplain.

     Recently EPA promulgated land disposal  restrictions,  includ-
ing treatment standards for the Third Third  scheduled wastes un-
der the Resource Conservation and Recovery Act, 42  U.S.C.  sectic
6924  (m) and 40 C.F.R. Part 148 (55 Fed. Reg.  22520-720  (June  1,
1990)).  The Agencies  are currently evaluating these standards
and are aware that they may be applicable to  the disposal  of the
treatment sludge at the pretreatment plant.   While  compliance
with the Third Third,  if necessary, may  increase the costs of
disposal associated with the dewatering  alternative, the
Agencies' preliminary  analysis indicates there will be  no  effect
upon the decision  to  dewater  Zone  1.

      Identification and selection  of  final cleanup  levels  for
the chemical contaminants  in  the  soil  and groundwater  in Zone  1
will  be made at  the time final remedial  actions are selected  for
the Zone.   Dewatering  Zone  1  neither  precludes  achieving,  nor  is
inconsistent with  meeting,  any chemical-specific cleanup levels
that may be chosen for site-related contaminants  in Zone 1.

Zone  4:  Compliance With Other Laws and  ARARs

ARARS

      No  location-specific  ARARs have  been  identified  for the  ac-
tion  alternatives  considered  for  Zone 4  groundwater cleanup.
                              - 22 -

-------
     For the first alternative (extraction, no treatment,  dis-
posal to the SARI), the Clean Water Act pretreatment and NPDES
standards, as discussed above under the dewatering alternative,
are applicable to the disposal of the extracted water to the
SARI.  These standards, as currently set forth in the existing
SAWPA permit, are likely to require modification because of the
expected increase in discharge volume associated with this alter-
native.  This alternative, if implemented, will comply with ap-
plicable permit standards, including any necessary modifications.

     For the second alternative (extraction, treatment,
reinjection), the Agencies have identified potential ARARs for
both treatment and reinjection.  With respect to air stripping,
the extracted water win be treated at the mid-canyon pretreat-
ment plant to meet the federal drinking water MCL for TCE  (5.0
ug/l) and the 10~6 risk level for chloroform  (6.0 ug/1).   In ad-
dition, the South Coast Air Quality Management District's
(SCAQMD) Regulation XIII, federally enforceable under the Clean
Air Act section 110, 42 U.S.C. section 7410,  is applicable to
emissions of VOCs  from new sources.  The SCAQMD recently promul-
gated a more stringent version of Regulation XIII that  is  ap-
plicable.  Regulation XIII requires best available control tech-
nology  (BACT) when incremental emissions of various air pol-
lutants, including volatile organic compounds, exceed a certain
threshold.

     An additional guideline  to be considered  (TBC) for air is
the  SCAQMD's Rule  1167.  Because a recent  court ruling  stayed en-
forcement of the Rule,  it  is  not considered ARAR.  Nevertheless,
the  purpose  of the Rule is to control  emissions of VOCs as
precursors to ozone  formation in the South Coast  Basin, where the
Stringfellow site  lies.  The  Rule  requires that all air stripping
facilities treating  contaminated groundwater  that emit  more than
one  pound per day  of total VOC emissions  install  controls  capable
of reducing  air emissions  by  90 percent.   Consideration of Rule
1167 in addition to  the SCAQMD's Regulation XIII  VOC  emissions
standards  is warranted  by, and consistent  with, EPA OSWER  Direc-
tive 9355.0-28,  "Control  of Air Emissions  From Superfund Air
Stripers  at  Superfund  Groundwater  Sites."   In nonattainment areas
like the  South Coast Air  Basin, which  is  acknowledged to have the
worst  ambient air  quality  in  the nation,  the  Directive seeks  to
incorporate  the use  of  controls  for  air  strippers,  consequently,
the  air stripping  treatment  system will  employ activated carbon
adsorption  at the  air-stripper off-gas to meet ARARS  and control
VOC  air emissions.
                              - 23 -

-------
     For the action of reinjection,  the Underground Injection
Control (UIC) program with respect to Class V Wells, pursuant to
the Safe Drinking Water Act and 40 C.F.R.  Part 144, Subpart B,
and the California Regional Water Quality control Board's "Water
Quality Control Plan, Santa Ana River Basin" (Basin Plan) provide
the interim action ARARs for TCE, nitrates, and sulfates.  The
UIC program requires that reinjection into Class V Wells, such as
those at the site, may not cause a violation of an existing
drinking water standard (MCL) under the SDWA, in this case 5 ug/1
for TCE and 10 mg/1 as N for nitrates.  With respect to nitrates,
the California Basin Plan's water quality objective of 11 mg/1 as
N is the State standard directly applicable to the reinjection of
nitrates.  Nitrate concentrations in the receiving formation are
believed to exceed the drinking water standard, and thus reinjec-
tion of treated water should not cause a violation of the SDWA
requirements under the UIC program.  Nevertheless, the UIC stan-
dards are relevant to potential underground sources of drinking
water and appropriate action ARARs under the circumstances where
the effectiveness of the technology considered for removal of
nitrates is anticipated to produce injectate that meets or ex-
ceeds either the UIC level of 10 mg/1, or the applicable Basin
Plan objective of 11 mg/1.  Consequently, both TCE and nitrates
will be reinjected at the UIC program levels  (5 ug/1 and 10 mg/1
as N, respectively).

     In the absence of a federal standard for sulfates the
California Basin Plan's water quality objective of  110 mg/l  is
directly applicable to the action of  reinjection.  Treated water
from the Zone  4 extraction system will be reinjected at  the  Basin
Plan objective.

Remediation Goals

     The Zone  4 response action  decisions made  in  this ROD are
considered  interim  for the reasons noted below.  Nevertheless,
the Agencies do not expect to select  further  Zone  4  response ac-
tions beyond those  chosen  in this ROD.  The  Agencies are,  there-
fore, identifying remediation goals  for the  contaminants found  in
the Zone 4 groundwater.  The remediation goals,  although being
set here for Zone 4 plume  cleanup, will not  be  finalized until
the decision for  long-term management of  the contaminated
groundwater  in all  downgradient  zones is made.

     Identification of  remediation goals  in this ROD for the com-
munity  area  (Zone  4)  is  based upon CERCLA's  objective  of restor-
ing and protecting  usable  groundwater to  the extent possible.
The Stringfellow  plume  is  located  within  the Chino III subbasin,


                              -  24 -

-------
which is a Class I aquifer having the potential for, and desig-
nated use as, a potential source of drinking water.   Under these
circumstances, the NCP indicates that the Agencies should look to
the maximum contaminant levels (MCLs) and maximum contaminant
level goals (MCLGs) under the Safe Drinking Water Act (SDWA), 42
U.S.C. section 300f, as potential cleanup levels.   While these
standards are not directly applicable because the community resi-
dents are not currently relying upon the groundwater as a drink-
ing water source, they are relevant and appropriate health-based
standards.  In the absence of a federal standard, the Agencies
looked to more stringent state standards or, if unavailable,  a
concentration based upon a 10~6 carcinogenic risk level.

     The only site related organic contaminants  in  Zone 4 that
were found in excess of health-based levels are TCE and
chloroform.  For TCE, the federal MCL and state promulgated stan-
dard are the same, at 5.0 ug/1.  Although the MCLG  for TCE is
zero, EPA has determined that a zero-based MCLG  is  not ap-
propriate as a remediation goal.  Therefore, the Agencies have
identified the remediation goal for TCE in Zone  4 as 5.0 ug/1.

     While there  is neither an MCL nor an MCLG specific to
chloroform, there  is a federal MCL of 100 ug/1 for  total
trihalomethanes, which includes chloroform.  The standard,
however,  is based  on an analysis evaluating the  health benefits
of chlorinating public drinking water supplies against the
detrimental effects of the production of trihalomethanes as a
result of chlorinating those supplies.  The Agencies, therefore,
determined that the MCL  for trihalomethane  is not an ARAR for  a
nonchlorinated source such as the  Stringfellow contaminant plume.
Since no other ARAR was available, the concentration, 6.0 ug/1,
associated with an excess cancer risk of 10 6 was identified  as
the cleanup goal  for chloroform.   This concentration coincides
with  the  State of  California Action  Level.  In  identifying the
goal, the Agencies have concluded  that a chloroform concentration
in the plume  of 6.0 ug/1  is appropriate  for the  circumstances  of
the Stringfellow  site, and will be protective  of numan  health.

      Based on available  data,  the  Agencies  believe  that  the
remediation goals  for TCE and chloroform can be  achieved.  The
Agencies  do  recognize, however,  that  recent studies by  EPA sug-
gest  that groundwater extraction and treatment  are  not,  in all
cases, completely successful  in  reducing contaminants  to  health-
based levels.   If  it becomes  apparent during operation  of  the
system,  that  contaminant  levels  have ceased to decline  or  are
declining at  a much slower rate  than anticipated, and  are  remain-
ing at  levels higher than the  remediation  goal,  such goal  and/or


                              - 25 -

-------
the selected remedy may be reevaluated at the discretion of the
Agencies.

     Both nitrates and sulfates are present in the Zone 4 con-
taminant plume.  The federal MCL (10 mg/1 as N) for nitrates has
been identified as a potentially "relevant and appropriate" Zone
4 remediation goal.  In the course of reviewing and evaluating
the public comments on the Community Groundwater Proposed Plan
and draft FS report, the Agencies have determined that setting
such a cleanup goal presents a problem.  While existing data in-
dicate that nitrate levels within the plume exceed the federal
MCL, the data also suggest that, in many locations, the back-
ground concentration of nitrates also exceed this standard.  The
situation raises questions as to the technical practicability of
achieving a cleanup goal which is lower than background condi-
tions.  Based upon present knowledge, the Agencies are consider-
ing invoking an ARAR waiver to allow the remediation goal for
nitrates to be set at background concentrations rather than at
the federal MCL.  Because the issue has not been the subject of
focused discussion and public comment, the Agencies will defer
finalizing the remediation goal for nitrates until after an op-
portunity for public input.

     With respect to sulfates, the EPA has recently issued a
proposed rule under SDWA which now identifies  sulfate drinking
water concentrations that pose a threat to human health.  Prior
to this proposal, sulfate concentrations were  set as a non-
enforceable secondary MCL for the aesthetic value of drinking
water.  The proposed rule is a potential ARAR, which will be con-
sidered  in setting the  final remediation goal  for sulfates in  the
contaminant plume.

                  SUMMARY OF COMPARATIVE ANALYSIS

     As  noted  previously, the  remedial actions described in  this
ROD are  interim measures.  Accordingly, the comparative  analysis
between  the  interim measures considered here  is  limited  to ensur-
ing that the chosen alternatives  are  consistent  with  any poten-
tial  final remedy and  the Superfund  criteria  relevant  to the in-
terim measure  being considered.   The  draft  FS report  provides  ad-
ditional detailed analysis  of  remedial alternatives.   To
facilitate the interim analysis  here,  the  nine criteria  are  iden-
tified,  below.
                              - 26 -

-------
                     Nine Superfund Criteria

1.   Overall protection of human health and the environment.
2.   Compliance with ARARs.
3.   Long-term effectiveness.
4.   Reduction of toxicity,  mobility, and volume (TMV).
5.   Short-term effectiveness.
6.   Implementability.
7.   COSt.
8.   State acceptance.
9.   Community acceptance.

Zone l

Dewatering:  No Action

     The "no action" alternative fails to meet criteria 1, 2, 3,
4,  5, 8, or 9.  This alternative can be implemented, by inaction,
at no cost.

Dewatering:  Gallery versus Surface Extraction Wells

     Both alternatives would meet ARARs, and the relevant techni-
cal criteria	reduction of TMV, short-term effectiveness, long-
term effectiveness, and  implementability.  While the standards in
the SAWPA permit must be met for dewatering, such standards are
being consistently met by treatment of extracted water at the
mid-canyon pretreatment  plant.  Continued compliance should not
be affected by dewatering.  Both alternatives would result in the
removal of a significant volume of  the soluble, mobile con-
taminants  from the plume, including those of primary concern,
VOCs.  Dewatering will physically  isolate remaining contaminants
by eliminating the potential for groundwater transport.  The ex-
tracted water would be treated at  the existing pretreatment plant
to remove metals and organics.  Both dewatering alternatives can
be implemented.  Any necessary precautions  to ensure short-term
protectiveness would be  taken during construction and  implementa-
tion.

     The capital costs associated  with  the  gallery  system are
higher than those  for the surface  extraction wells.    The com-
munity and State of California  favor selection of dewatering
through use of surface extraction  wells.
                              - 27 -

-------
Zone 4

Community Groundwater Cleanup:   No Action

     The "no action" alternative fails to meet Superfund criteria
l, 2, 3, 4, 5, 8, or 9.   This alternative can be implemented, by
inaction, at no cost.

Community Groundwater Cleanup:   1.  Extraction, No Treatment,
                                    Disposal to SARI
                                2.  Extraction, Treatment,
                                    Reinjection

     Both alternatives meet the first six superfund criteria.
Through continous extraction and treatment of contaminated
groundwater from Zone 4, reductions in contaminant concentrations
to the cleanup levels identified by the Agencies will be suffi-
ciently protective of human health and the environment.  Im-
plementation c^each alternative will meet action-specific ARARs
and TBCs regarolng use of air strippers.  Contaminant volumes un-
der either alternative will decrease without  further degrading
the surrounding aquifer.

     Contaminant removal combined with treatment will provide
long-term effectiveness and ensure short-term protection from aa
adverse  impacts on human health and the environment during con-
struction and  implementation.  Consideration of implementability
and cost shift the balance in favor of the second alternative.
If a major modification of the SAWPA permit  is not granted to in-
crease allowable discharge of treated water,  it may not be pos-
sible to implement the  first alternative.  With respect to costs,
the first alternative appears to  be less  costly.  If modeling in-
dications of cleanup time are correct, the first alternative
could take three times  as long as the second  alternative to
achieve  the remediation goals identified  for  Zone 4.   Selection
of the second  alternative is favored by the  State and  the com-
munity.

                        THE SELECTED REMEDY

Zone  1

     As  an  interim  response  action  in  Zone  l,  the Agencies have
selected dewatering  using a  matrix  of  surface extraction  wells
that would  be  iteratively  installed throughout the  Zone 1  area.

      Initial  dewatering to bedrock  is  anticipated to  take one


                              - 28 -

-------
year, and to remove over 50% of the soluble organics and inor-
ganics estimated to be present in the Zone 1 groundwater.
Depending on the outcome of the Agencies' final remedial decision
for Zone 1, maintaining the lowered water table level could be
required in perpetuity.

     At this time, there are no remediation goals being set
through this ROD for Zone 1.  Implementation of this alternative
would include compliance with all identified ARARs.

Zone 4

     The Agencies also have selected as an interim response
measure cleanup of the community groundwater through extraction,
treatment, and reinjection.

     Under the selected alternative, a number of wells would be
installed along the center line of the plume south of U.S. Highway
60 to extract contaminated groundwater.   Additonal wells in-
stalled at the sides of the plume would reinject treated water to
accelerate plume cleanup.  An estimated extraction rate between
200 and 600 gallons per minute is expected.  This  rate and the
feasibility of reinjection will be confirmed by field studies
prior to  final design  and implementation.

     If reinjection is  feasible, the extracted water would be
temporarily stored and piped to an air stripping unit, where TCE
and chloroform in the  water would be removed to meet concentra-
tions of  5.0 ug/l and  6.0 ug/1, respectively.  The treated water
would then be put through reverse osmosis  to reduce  the nitrates
and sulfates to acceptable  levels  (10 mg/1  as N and  110 mg/1,
respectively) prior to being reinjected.

     The  decision whether to use air stripping, as opposed to
granular  activated carbon,  to  remove VOCs  is considered a design
decision  that will be  confirmed through  design studies.
Similarly, use of  reverse osmosis  as opposed to another technol-
ogy  is  subject to design studies.   In  lieu of  reverse  osmosis,
the Agencies are  also  considering  an offset through  use of a
Chino III  subbasin desalter to  remove  nitrates and sulfates.

      If  reinjection  is not feasible,  the  Agencies may pursue
disposing of the  extracted  water  (after  treatment  to reduce VOCs,
and nitrates and  sulfates,  if  necessary)  through  a sanitary or
industrial sewer.
                              - 29 -

-------
Field Tests and studies

Soil-Vapor Extraction in Zone. 1

     This ROD includes a commitment to conduct a field test of
soil-vapor extraction (SVE).   Full-scale implementation of the
technology will be pursued if the following conditions are met:
1) the results of the field test indicate that the technology can
be successfully implemented at the site in a cost-effective man-
ner; and 2) implementation of the technology win not be incon-
sistent with nor preclude the final response action taken in Zone
1.  These determinations cannot be made at this time, but will be
made by the Agencies during the development and implementation of
the field test, and upon completion of the additional soil
treatability studies.  The decision whether to implement a full-
scale SVE system will be documented at a later date.

     If successful, soil-vapor extraction could further reduce
the future migration of VOCs into the groundwater by removing
them from the unsaturated soil above the water table.  Such
removal is anticipated to reduce the long-term health risks by
decreasing the volume of VOCs in the soil, and thus the future
volume of VOCs that could potentially migrate into the
groundwater and be transported towards the downgradient com-
munity.  SVE is anticipated to reduce the short-term health risk
from emissions of VOCs during implementation of ex-situ soil
treatment technologies, if chosen as part of the  final remedy,
and to hasten the remediation of Zone 1.  Although VOCs represent
less than one per cent of the mass of contaminants present in
Zone 1, they are significant contaminants because of their rela-
tive mobililty and toxicity, and because they are the major or-
ganic contaminants found  in the downgradient groundwater plume.

     In-situ SVE involves a patented process whereby a vaccuum  is
placed upon wells  in  the  ground above the  lowered water table,
forcing air to flow  through the pore spaces of  unsaturated con-
taminated  soil.  The  above-ground  support  equipment  vould  include
blowers, water/gas separators,  and vapor-phase  activated carbon
adsorption equipment.  The extracted air would  contain both
volatile organics  and moisture  (water vapor),  so  a  water/gas
separator  would  be required  to  separate  the moisture from  the
air.  The  small  volume of water  separated  out  of  the water/gas
separator  would  be conveyed  to  the. existing mid-canyon pretreat-
ment-plant.  The volatile .contaminants  in  the  vapor  phase  would
be  adsorbed onto the activated carbon,  which would  be
regenerated.         -   "~       .5==* »--•-•-•     :  -
                              - 30 r

-------
     The costs of a full-scale SVE system based on revised FS es-
timates are presented, below.

     Capital costs:                    S 15,000,000
     Present Worth (7% discount rate):    24,000,000

     In pursuing a field test of SVE, ARARs will be met.  For the
SVE field test, the existing SAWPA permit, embodying the ap-
plicable standards under the Clean Water Act's federal pretreat-
ment regulations, 40 C.F.R. Part 403, and its NPDES requirements,
33 U.S.C. section 1311, govern the off-site discharge of treated
water to the SARI.  The manifest requirements under the Resource
Conservation and Recovery Act, 40 C.F.R. Part 262, are applicable
to the off-site disposal of spent carbon to an approved regenera-
tion facility.  Finally, the VOC emissions standards under
Regulation XIII, as federally enforceable under the Clean Air
Act, and as enforceable by the State of California under it
revised regulation, are applicable to the SVE field tests.
Regulation XIII requires best available  control technology
(BACT) when incremental emissions of various air pollutants, in-
cluding volatile organic compounds, exceed a certain threshold.
Rule 1167 of the SCAQMD and EPA's OSWER Directive 9355.0-28
relating to the control of air emissions at Superfund groundwater
sites will be considered to the extent they are suitable to VOC
air emissions from the SVE process.

Reinjection of Treated Groundwater in Zones 2 and 3

     Also included in this ROD is a commitment to conduct field
studies on the  reinjection of treated groundwater into  Zones 2
and 3.  The type of information expected to be gained from such
studies  include estimated costs,  implementability,  long-term ef-
fectiveness, short-term effectiveness, and reduction  in con-
taminant toxicity, mobility,  and  volume  (TMV).  This  information,
along with  information on community  and  state acceptance, protec-
tion of public  health and the environment, and compliance with
ARARs will be used by the Agencies in determining whether to
implement reinjection  in Zones 2  and 3.  The decision to  imple-
ment a  reinjection system will be documented at a  later date.
                              - 31 -

-------
                    STATUTORY DETERMINATIONS

Zone I

Dewatering

     Dewatering of Zone 1 is an interim measure that offers an
opportunity to reduce risk and prevent further degradation of
dovmgradient groundwater.  It does not preclude nor is it incon-
sistent with potential future remedial actions.  During initial
dewatering, all action-specific ARARs will be met.   No location-
specific ARARs have been identified.   Remediation goals for Zone
l are not being addressed by this ROD.

     The dewatering process includes treatment at the existing
pretreatment plant of the water-soluble contaminants in Zone l,
such as VOCs, other organics, and metals.  Dewatering will reduce
the risk of human exposure to contaminated groundwater in Zone 1
by extracting and treating most of the contaminated groundwater
beneath the zone.  Minimizing contact between the source con-
taminants and uncontaminated groundwater infiltrating into the
area will greatly reduce the quantity of contaminants that could
migrate downgradient from Zone 1.  This  is an  important aspect r*
any final remedial decision for the site.

     During construction and implementation of the dewatering
system, there may be short-term potential for minimal increase of
VOC air emissions from well vents, relief valves in force mains,
or interim storage tank vents.  Based on an analysis of potential
air contamination health risks associated with the  implementation
duration, the excess lifetime carcinogenic risk  from inhalation
exposure in the community is approximately 2 x 10  8, and  in
Pyrite Canyon approximately 2 x 10~  .  These are within the  al-
lowable range for excess cancer risk.

     Dewatering using surface extraction wells is  cost effective
in that it provides substantive reduction in  the volume and  sub-
sequent mobility of the  soluble,  mobile  contaminants  in Zone l at
a cost reasonable to the level of protectiveness.   The draft FS
report estimates that over  50% of the aqueous-phase contaminant
mass  in Zone  1 will be removed during the initial  period  of
dewatering.

     There does  not appear  to be  any threat  to natural resources
or any impact on the  100-year  floodplain that  would result  from
dewatering.   According to a map  included in  the  Riverside County
Comprehensive General  Plan,  there are no unique  plant  communities


                              - 32 -

-------
in the Glen Avon area.   Nor are there endangered,  rare,  or
threatened animal species near the Stringfellow site.   Although
several birds, mammals,  reptiles, and amphibians have  been seen
in the vicinity of Pyrite Canyon, no significant,  rare or unique
permanent habitat in the vicinity of Highway 60 has been ob-
served.

Zone 4

Community Groundwater Cleanup

     During system operation, action-specific ARARs and TBCs will
be met.  There are no forseen unacceptable short-term risks or
cross-media impacts that could be caused by its implementation.

     The selected remedy is not estimated to be the least expen-
sive alternative for cleaning up the community groundwater, but
in light of the confidence levels associated with the cost es-
timates, the actual costs may not be significantly different than
the alternative which involved extraction, no treatment, and dis-
posal to the SARI.  Because the Agencies anticipate the selected
alternative will hasten the cleanup of Zone 4, the Agencies have
determined that the selected response action is the more cost-
effective of the alternatives considered.

     The selected remedy will reduce the toxicity, mobility, and
volume of Stringfellow-related contaminants in the affected com-
munity south of Highway 60.  The remedy is the most appropriate
solution as it also represents the maximum extent to which per-
manent solutions and treatment can be practically utilized in  a
cost-effective manner.

     Under CERCLA's amended provisions, the statutory preference
for treatment is satisfied by the selected remedy.  The ap-
proaches taken for sidestream and residual management, to be con-
firmed by design studies prior to final design and implementa-
tion, will comply with all requirements.

     During construction and  implementation of the system, there
may be short-term potential  for  minimal increase of VOC emissions
into the air  from well vents,  relief valves  in  force mains, or
interim storage tank vents.   Based on an analysis of potential
air contamination health risks associated with the implementation
duration, the excess lifetime  carcinogenic risk from  inhalation
exposure in the community  is  approximately 2 x  10", and  in
Pyrite Canyon approximately   2 x 10".  These  are within  the ac-
ceptable range for excess  cancer risk.


                              - 33 -

-------
     According to a map included in the Riverside county Com-
prehensive General Plan, there are no unique plant communities in
the Glen Avon area.  Nor are there endangered, rare, or
threatened animal species near the Stringfellow site.  Although
several birds, mammals, reptiles, and amphibians have been seen
in the vicinity of Pyrite Canyon, no significant, rare or unique
permanent habitat in the vicinity of Highway 60 has been ob-
served.

     All of the actions in this ROD are supported by the State
and the community.
                         CHANGES  FROM AND
               CLARIFICATIONS  TO  THE PROPOSED  PLANS

     None of the changes and clarifications discussed below war-
rant public notice and comment, nor affect the remedies selected.

     In response to comments on the draft FS report and the Com-
munity Groundwater Proposed Plan, estimated extraction rates in
Zone 4 were recalculated and now appear to be significantly lower
than previously believed.  The lowered extraction rates affected
the estimated cleanup times and costs for the alternatives beim
considered, and thus were recalculated.  The revised estimates
are reflected in the April 1989, "Stringfellow Update" newsletter
and reference documents.  Predicting the groundwater cleanup time
is difficult and existing methods are inexact.  Actual extraction
rate and yield need to be confirmed through further collection
and evaluation of field data.

     The new estimated times  for cleanup of the Zone 4 con-
taminant plume presented in this ROD are two to three times
longer than those reflected in the Proposed Plan.  However, the
recalculations still show that the alternative chosen is  an-
ticipated to hasten cleanup in Zone 4.  With  respect to estimated
costs, the new figures  indicate  that the alternative chosen is
more costly.  Cost figures were  calculated using both 7 percent
and 10 percent discount  rates.

     The Community Groundwater Proposed Plan  did not mention the
necessary first phase of the  remedial design, which will  involve
collection and evaluation of  field data  in the contaminant plume.
This task will enatole a  more  accurate design  of the remedial sys-
tem.  Installing prototype extraction wells  in selected areas  of
the community  plume, and performing short-term and  long-term
pumping tests, will provide valuable  information on aquifer


                              -  34 -

-------
characteristics and water quantity and quality to be extracted
and treated.  Based on this information,  it may become necessary
to maJce changes to the treatment and disposal process currently
envisioned.  The modifications will be made during detailed
remedial design, and if warranted, will be documented at a later
date.

     The Community Groundwater Proposed Plan assumed that no
treatment would be needed for the extracted water to be dis-
charged to an industrial sewer, such as the SARI.  This was based
on the assumption that the chemical quality of the extracted
water would be within the present quality limits of the SAWPA
discharge permit.  In case the extracted water is found to exceed
the discharge permit water quality limit, or if discharge to the
industrial sewer is not permitted without reducing VOC concentra-
tions in the extracted water, the water would be treated for VOC
removal prior to discharge.  Thus the alternative with disposal
to the SARI line has been evaluated in two different ways:  (1)
without using air stripping  (no treatment), and  (2) using air
stripping before discharge to an  industrial sewer.  For both
these subalternatives, cleanup time is still estimated to be ap-
proximately three times longer than the alternative selected.
Therefore, addition of this  subalternative did not alter the
selection of the remedy.

     The Community Groundwater Proposed Plan indicated that the
State Action Level for chloroform (4.3 ug/1) would be set as the
remediation goal.  As discussed in this ROD, the remediation goal
for  chloroform  has been identified as 6.0 ug/1.  The concentra-
tion coincides  with the new  state Action Level,  as well as EPA's
10~6 carcinogenic risk level.

     With  respect to  nitrates and sulfates,  the  Community
Groundwater Proposed  Plan  implied a number of  things which subse-
quently have been clarified  through this ROD.  First, the
response action in Zone  4  is on-site.  Therefore,  a  permit  from
the  Regional Water Quality Control Board  is  not  required, al-
though the  substantive portions of the Basin Plan  applicable  to
the  response action win need to  be met.   Secondly,  the Proposed
Plan indicated  that the cleanup  (remediation)  goal  for nitrates
vould be the federal  MCL.  As discussed  earlier,  the Agencies  are
considering setting the goal at background by  invoking a  waiver
based on the technical  impractacability  of meeting  a cleanup
standard which  is  lower  than anthropogenic background conditions
which currently are believed to exceed the  federal  MCL.   Thirdly,
with respect to sulfates,  the Proposed Plan  implied that  the
remediation goal would be  set at  the  water quality objective


                              - 35 -

-------
specified in the RWQCB's Basin Plan.   Rather, in setting the
remediation goal, the Agencies will consider the proposed EPA MCL
for sulfates.   If the rule is promulgated, the MCL will become
ARAR.

     The Overall Proposed Plan stated that soil-vapor extraction
(SVE) would be implemented if a field test proved favorable.  The
ROD offers further explanation by clarifying that the Agencies
are committed to full-scale implementation of SVE if the field
test indicates that SVE could be successfully used at the site in
a cost-effective manner, and that implementation of SVE would not
preclude nor be inconsistent with the final remedial decision for
Zone l.  These determinations cannot be made at this time, but
win be made by the Agencies during the development and implemen-
tation of the test and upon completion of the additional soil
treataJbility studies.  The decision whether to  implement SVE will
documented at a later date.

     The Overall Proposed Plan also implied that a ROD covering
RA6  in its entirety would be  issued by the Agencies.  In response
to community comment, and through issuance of this ROD, the
Agencies have agreed to first pursue the  dewatering and SVE
aspects of RA6, and to combine these with the decision to
remediate the groundwater plume in the community area.  Long-te^
continuation of downgradient  plume management activities will bt
addressed in the final ROD.
                              -  36 -

-------
                            GLEN   STRINGFELLOW
                            AVON *SITE
    012345678
Figure 1

-------
Stringfellow Site Plan
"GINO
.--.--- -.
,....,.t I)' '''.''10''01 "nl''''
IIe'I.'UN' 0' ""0-.'."'''''''0
.:.OtINORA" lit
. IiII8CMIII'O"t"'~ "",. """At..O
.,....." .n '" ''''''I''C'' "I'MII
. .".'''.CltOfit"..,.
. 18' MOH"O.....r. "It t'
. .,,,,"'''OIIUfiIIIC''''' [II""'"
o co-otu.." " .'80"""''''' "",1
- - - Cu....,.., f'I"",f"'U" "....".e'
ru...... I'
"""'fJA
I
PONt 41
I
(I .. .,...
............-..
""",''',,,,
riqurr.
2
\
,
S.'.~flP' AI ,
(' A II' PAIHI""
"All
t'''''''''
I +f'll I .I'\I"IW
~. ,,,,.rMIN' \ lioiVi
" "AN' \.." ~ .
~ ~
\\ \
,\
,\ .
\\ 8""' .."'",'"
~, !ioNi jl
--_.
fIVl''''Hflf",
,,""~'" AlitA
if

-------