United-States1
           Environmental Proteciton
           Agency.
Office of
Emergency and
Remedial Response
EPA/ROD/R 03-86/031
S«pl«mb«r 1986
4>EPA   Superfund
           Record of Decision:
              Delaware City PVC, DE

-------
                                   TECHNICAL REPORT DATA
                            iPleat read Instructions on iht rtvtnt before completing)
1. REPORT NO.
 EPA/ROD/R03-86/031
             3. RECIPIENT'S ACCESSION NO.
4. TITLE ANO
 SUPERFUND  RECORD OF DECISION
 Delaware City  PVC,  DE
             5. REPORT DATE
                        September 30, 1986
             I. PERFORMING ORGANIZATION CODE
7. AUTMORIS)
                                                            I. PERFORMING ORGANISATION REPORT %c
9. PERFORMING ORGANIZATION NAM6 ANO ADDRESS
                                                            10. PROGRAM ELEMENT NO.
12. SPONSORING AGENCY NAME AND ADDRESS
 U.S. Environmental  Protection Agency
 401 M Street,  S.W.
 Washington,  D.C.   20460
             J13. TYPE OF REPORT AND PERIOD COv£ae;
              	Final ROD Report
             14. SPONSORING AGENCY CODE
                        800/00
19. SUPPLEMENTARY NOTES
16. ABSTRACT                              "  ~~~~~~~'     '     "	~	~~     	
    The Delaware  City PVC site is located  two miles northwest of Delaware  City,  New
 Castle County, Delaware.  In 1966 stauffer  Chemical Company (SCO of Westport,
 Connecticut,  founded the Delaware City PVC  Plant,  which is used for the manufacturing o
 polyvinylchloride  resin (PVC),  polyvinyl  acetate  and other polymers.   From  1971  to 19~4
 off-grade PVC  resin, sludge from the wastewater treatment system and residue  fror? the
 stripping process  were disposed of in two onsite  pits.   These "buried  sludge  pits" were
 closed and covered in 1979.  Off-grade PVC  resin  was disposed of in a  third pit.   This
 material was  removed and the pits backfilled in 1974.   In May 1981 Formosa  acquired the
 PVC manufacturing  and processing facility and  has continued operations to present.  The
 two buried sludge  pits and the third disposal  pit were  retained by SCC as part  of its
 Carbon Disulfide Plant, located adjacent  to the PVC Plant property.  An EPA conducted
 inspection in  May  1982 indicated serious  contamination  of the shallow  ground  water.
 Currently, ground  water, surface water, and soils are  contaminated with ?vc,  benzyl
 chloride monomer (VCM), TCE, and 1,2-dichloroethane (EDO.
    The description of the selected remedial action for  each area of this  site  is
 provided below.  Off-Grade Batch Pits:  excavate  and remove existing PVC  sludge  and
 contaminated  soils;  install a double synthetic liner;  install monitoring  wells  and
 perform quarterly  sample analysis for TCE,  EDC, VCM.   The excavated material  will ne
 (See attached  sheet)                           	
                                KEY WORDS ANO DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.iOENTIBiERS.OPEN £N06O TERMS
                                                                            COSATi F;eid.Croup
 Superfund Record  of  Decision
 Delaware City  PVC, DE
 Contaminated Media:  gw,  sw, soil
 Key contaminants:TCE, PVC,  EDC, VCM
18. DISTRIBUTION STATEMENT
19 SECURITY CLASS / Tint Kfponi
          None
21 NO. Of PAGES
           57
                                              20. SECURITY CLASS . Tins page I
                                                                          22. PRICE
EPA t*m 2220-1 (*•». 4-77)   PREVIOUS eOi TION . i O»§OHTC

-------
EPA/ROD/R03-86/031
Delaware City PVC, DE

16.  ABSTRACT (continued)

processed  and recovered (estimated at 80-85%) as a saleable finished
product to the maximum extent possible.  Non-recoverable material will be
disposed of offsite at an approved RCRA facility.  Stormwater Reservoir:
The sane remedy as described for the above off-grade batch pits.   Unlined
Ditches:  excavate and remove PVC sludge and dispose of at an approved RCRA
facility; install a single synthetic liner.  Aerated Lagoons:  excavate and
remove PVC sludge; clean and repair lagoons as necessary; install a double
synthetic liner; install monitoring wells and perform quarterly sampling
analysis for TCE, EDC and VCM.  The excavated material will be recovered to
the maximum extent possible (estimated to be 80-85%) and non-recoverable
material will be disposed of offsite at an approved RCRA facility.   Closed
Buried Sludge Pits:  place a drainage layer on top of the existing synthetic
cap; cover with a second synthetic cap and topsoil and revegetate.   Former
PVC Storage Area:  cover and cap the entire area with a double synthetic
cap.  Ground Water:  install a line of six ground water recovery wells at
the northern edge of the contaminant plume, and another six wells at the
southern edge.  Reuse the collected ground water in Formosa's plant
operations.  During periods of low water demand in the plant, treat the
ground water in the existing waste water treatment plant.  Install two
monitoring wells at the southern edge of the plume.  Provide an alternate
water supply for existing contaminated wells.  Operation and Maintenance:
as a minimum, regular inspections and, as necessary, repairs to the liners
and caps.  The ground water recovery system will be routinely monitored to
assure that it is capturing the contaminated plume.  The estimated capital
cost for the remedy is $1,904,000 with annual O&M costs of $43,000.

-------
                               RECORD OF DECISION

                         REMEDIAL ALTERNATIVE SELECTION


Site;  Delaware City PVC Site, New Castle County, Delaware

Documents Reviewed:

       I am basing my decision principally on the following documents describing
the analysis of cost effectiveness and feasibility of remedial alternatives  for
the Delaware City PVC Site:

   v    - "Remedial Action Feasibility Study":  Delaware City  PVC  Site,  New Castle
         County (Malcolm Pirnie, Roux Associates, June 1986).

       - "Hydrogeology and Groundwater Conditions":  Delaware City  PVC  Site,
         New Castle County (Roux Associates, February 4,  1983).

       - "Interim Report, Groundwater Conditions":   Delaware  City PVC Site,
         New Castle County (Roux Associates, June  1982).

       _ "A Site Inspection  Report":  Delaware City  PVC Site, New Castle  County
         (Ecology & Environment, Inc., June  28,  1982).

       - "Hydrogeologic Review":  Delaware City  PVC  Site,  New Castle County
         (Ecology and Environment,  Inc., June 3,  1982).

       - Staff summaries and  Recommendations.

       - Recommendation by the Delaware Department of Natural Resources and
         Environmental Control.

Description of the  Selected  Remedy;

1.   Off-grade  Batch Pits - Excavate and remove existing polyvinyl chloride  (PVC)
sludge and contaminated soils Co the  levels  to be  determined  at  the design
stage; install a double synthetic liner, install monitoring wells and perform
quarterly sample analysis  for trichloroethylene  (TCE), 1,2, dichloroethane
(EDC)  and vinyl chloride monomer (VCM), the  contaminants  of concern at  the
site.  The excavated material will  be directly processed  and  recovered  (estimated
by the companies to be 80-85%) as a saleable finished product to the maximum
extent possible.   Non-recoverable material will  be disposed of  off-site at  an
approved RCRA  facility (est.  I year).

 2.  Stormwater Reservoir  (RV Pond)  -  The same  remedy as described for the above
 off-grade batch pits  (est.  1  year).

 3.  Unlined  Ditches - Excavate and  remove  PVC  sludge, install a single  synthetic
 liner.   The  excavated material  will  be disposed  of  off-site  at  an approved
 RCRA facility  (est. 8 months).

 4.  Aerated  Lagoons - Excavate and  remove  PVC  sludge, clean and repair  lagoons

-------
                                      -2-
as necessary, Install a double synthetic liner, install monitoring wells and
perform quarterly sampling analysis for TCE, EDC and VCM.  The excavated material
will be recovered to the maximum extent possible (estimated by the companies Co be
80-85%) and non-recoverable material will be disposed of off-site at an approved
RCRA facility (est. 18 months).

5.  Closed Buried Sludge Pits - Place a drainage layer on top of the existing
synthetic cap, and cover with a second synthetic cap (or comparable substitute in
compliance with the requirements of RCRA) and topsoil and then revegetate
(est. 1 year).

6.  Former PVC Storage Area - Cover and cap the entire area with a double syn-
thetic cap (or comparable substitute in compliance with the requirements of RCRA)
and then revegetate (est. 6 months).

7.  Groundwater - Install a line of six groundwater recovery wells at the
northern edge of the contaminant plume, and another six wells at the southern
edge.  Reuse the collected groundwater in Formosa's plant operations.  During
periods of low water demand in the plant, treat the groundwater in the existing
waste water treatment plant.  Install two monitoring wells at the southern edge of
the plume.  Provide an alternate water supply for existing contaminated wells.

8.  Operation and maintenance (O&M) for the remedy will include as a minimum
regular inspections and as necessary repairs to the liners and caps.  The
groundwater recovery system will be routinely monitored to assure that it is
capturing the contaminated plurae.

Declarations                                                    •
    Consistent with the Comprehensive Environmental Response, Compensation,
and Liability Act of  1980  (CERCLA)  (42 U.S.C. § 9601-9657) and the National
Contingency-Plan (40  CF R  Part 300), I have determined that the remedial
action described above, together with proper operation and maintenance consti-
tutes a cost-effective remedy which mitigates and minimizes damage to public
health, welfare, and  the environment.  The remedial action does not affect
or violate any floodplain  or wetland area.  The State of Delaware has been con-
sulted and agrees with the approved remedy.  In addition, the action will require
future operation and  maintenance activities to ensure the continued effectivenes?;
of the remedies.  These activities  will be considered part of the approved
action and eligible for Trust Fund  monies for a period of six months following
completion of construction.

     In addition, the  off-site disposal of contaminated soil to a secure hazardous
waste facility is necessary to protect public health, welfare and the environment

     I have determined that the action being taken is appropriate when balanced
against  the  availability of Trust Fund monies for use at other sites.
                                            r\
                                             .._
                                             "*• f.  •	ij'"  . *•  *~*i
                                              //  James M. -Self  •)
                                                 REGIONAL  ADMINISTRATOR

-------
                SUMMARY OF REMEDIAL ALTERNATIVE SELECTION

                     DELAWARE CITY PVC SUPERFUND SITE


SITE DESCRIPTION

     The Delaware City PVC Site is located approximately 2 miles northwest of
Delaware City at latitude 39°35'16"N and longitude 75°38'50"W in New Castle
County, Delaware.  The site is situated on State Route 13 just west of the
Getty Refining and Marketing Company between Red Lion Creek to the north, and
Dragon Creek to the south.  The area of the study site is approximately 260
acres. (See Figure #1)

  -f  The Delaware City PVC Site consists of a Polyvinyl Chloride (PVC) manu-
facturing facility owned and operated by Formosa Plastics Corporation (Formosa).
From 1966 until May, 1981, Stauffer Chemical Company (Stauffer) manufactured
PVC resin and processed vinyl chloride monomer at the facility.  In May 1981,
Formosa acquired the PVC manufacturing and processing facility and has continued
operations to present.  Stauffer has retained ownership of an existing carbon
disulfide plant adjacent to Formosa's property.  In April, 1982, one of the
domestic supply wells on Stauffer's property became contaminated with 1,2
dichloroethane (EDC), vinylchloride monomer (VCM) and trichloroethylene (TCE).
This occurence prompted Formosa and Stauffer to perform a hydrogeologic
investigation, conducted by Roux Associates, which identified the sources of
ground water contamination (See Figure #2).  The following sources were identified
at the site:

     1.  Off-grade Batch Pits - unlined earthen lagoons which receive waste-
         water from the S-l and S-2 production areas, when the wastewater
         sumps in these areas overflow.  These lagoons also serve as surge
         reservoirs during periods when the wastewater effluent cannot be
         discharged to the Delaware River.  PVC solids contaminated with EDC,
         VCM and TCE are also deposited in these lagoons.  This sludge-like
         material must be periodically excavated and disposed of off-site.

     2.  Stormwater Reservoir (RV Pond) - an unlined earthern basin used pri-
         marily for storm water collection.  This pond occasionally receives
         process wastewater and PVC solids from the production area (E-2) when
         the wastewater sump overflows.

     3.  Unlined Ditches - these ditches conduct stormwater runoff from the
         plant site to the off-grade batch pits and the RV pond.  Process
         wastewater is also discharged to these ditches when the production
         area sumps overflow.  PVC solids have been deposited at several
         locations in the ditches.

-------
                                    -2-


      4.   Aerated lagoons - concrete lined lagoons which receive wastewater
          and  PVC solids for treatment.  The potential for leakage  from the
          aerated lagoons exists through cracks  in the concrete liner.

      5.   Closed  Buried Sludge Pits (Burial Pits) - unlined pits which  were
          used to dispose of PVC solids and sludge from the aeration lagoon.
          In 1979, Stauffer closed out the pits  with a synthetic cap made from
          PVC  and designed to prevent  percolation.  The cap was then covered
          with soil and revegetated.

      6.   Former  PVC Resin Storage Area - A former PVC resin storage area was
          excavated and regraded in 1974 by Stauffer.   Recent sampling  has
  -f       indicated the presence of resin residue with EDC, VCM and  TCE
          concentrations at levels of  concern.

      The  Closed  Buried Sludge Pits and the Former PVC Resin Storage Area are
 located on  the Carbon Bisulfide Plant property  owned  by Stauffer Chemical
 Company and are  no longer in use.  The remaining sources are part of the active
 manufacturing process at the Formosa  Plastics Plant.

      The  hydrogeologic investigation  identified a plume of contamination consisting
 of EDC, VCM and  TCE in the lower portion of Columbia  aquifer.   High concentrations
 of EDC, VCM and  TCE arc present in the ground water in an area adjacent  to,
 and  west  of the  PVC plant.  The Roux  report recommended evaluating  remedial
 actions to  eliminate the major sources of EDC,  VCM and TCE on the  property and
 eliminating the  ground water pollution.

 SITE GEOLOGY

      The  site is located within the Atlantic Coastal  Plan Geologic  Province
 and  is  underlain by southeasterly dipping, unconsolidated sedimentary  strata
 of Cretaceous age.

      The  Cretaceous deposits mantle the irregular surface of the crystalline
 bedrock and have been locally divided into three formations.  The  oldest or
 deepest deposits are called the Potomac Formation.  The Potomac consists of
 silt and  clay beds with sandy layers  or lenses  that serve locally  as aquifers.
'The  sand  lenses  encountered between clay layers are generally thinner  than the
 clays.  The sand layers divide the Potomac Formation into three zones, the
 Upper,  Middle, and Lower.  The Potomac Formation is an important municipal
 and  industrial water supply source in the area. (See  Figure #3)

      Stratigraphically overlying the  Potomac Formation within a portion of the
 area of investigation, is a layer of  white, "sugery", fine-grained sand known
 as  the  Magothy formation.

      Above  the Potomac and Magothy formations in the  study area, is the
 Merchantville Formation which belongs to the Matawan Group of Upper Cretaceous
 Age.

-------
                                      -3-
     The Merchantville Formation consists of greenish-grey clayey silt with
clay, which is locally abundant as the in filling of burrows of benthic organisms.
The Merchantville Formation has a low permeability and thus serves as an
aquitard which hydraulically seoarates the sand of the Magothy and Potomac
Formations from the overlying Columbia aquifer.  Where the Merchantville is
absent, clays of the Upper Potomac are present directly below the Columbia and
serve the same purpose.  All evidence from this investigation indicates that
the Columbia is continuously underlain by an aquitard.

     Overlying the irregular topography of the Merchantville is the Columbia
Formation which is Pleistocene in age.  The Columbia Formation in Northern
Delaware consists of quart & sand with minor interbeds and lenses of gravel,
sj.lt and clay.  The Columbia aquifer is a water supply source for many residents
o'f this area.

HYDROGEOLOGY OF COLUMBIA AQUIFER

     The drilling and sampling program performed during the RI has concentrated
on the Columbia Formation, because this is the aquifer that was found to contain
EDC, VCM and TCE.  The resistivity survey that was also performed during the
investigation has helped to confirm the continuity of the Merchantville and/or
Potomac clay under the entire study area.  It has also demonstrated that the
Potomac clay layer is continuous under the Magothy sand layer which is present
in the western portion of the site.  Due to the presence of the Potomac clay
present in the area it can be concluded that the Potomac formation is not
threatened by contamination at the present time.
                                              •

     Water table maps prepared during the RI report show indications of a
"mound" in the water table under the western portion of the PVC plant property.
The highest water level in this mound was recorded at Observation Well
OW-11, east of the identified sources.  This mound is probably caused by
water losses at the plant (fire water ponds, cooling water towers) upgradient
of the identified source area.  Ground water flows from the area of this
mound under the sources to the northwest, west and southwest toward U.S.
Route 13.  Ground water to the west of Route 13 flows east to converge with
the flow from the plant.  Thus, ground water flowing to the northwest, toward
OW-5, turns in a northerly direction (roughly parallel to Route 13) and
flows toward Red Lion Creek.  Ground water flowing from the PVC plant toward
OW-16 turns in a southerly direction and flows to Dragon Run.  (See Fig. 4)

     Within the Columbia aquifer on the Stauffer property, there is a downward
component of groundwater flow typical of a recharge area.  The underlying
Merchantville formation will restrict further movement of ground water into
the deeper aquifer.  This explains why EDC, VCM and TCE can be found in only
the lower portions of the Columbia Aquifer.

Site History

     In 1966  Stauffer Chemical Company of Westport, Connecticut, founded the

-------
                                   -4-
Delaware City PVC Plant, which is used for the manufacturing of polyvinyl-
chloride resin (PVC), polyvinyl acetate and other polymers.  From 1971 to
1974 off-grade PVC resin, sludge from the wastewater treatment system and
residue from the stripping process were disposed of in two on-site pits.
These "buried sludge pits" were closed and covered in 1979.  Off-grade PVC
resin was disposed of in a third pit.  This material was removed and the
pits backfilled in 1974.  These three pits constitute the areas onsite
where disposal of waste occurred.

     In May 1981, Stauffer Chemical Company sold the PVC Plant to Formosa
Plastics Corporation, who currently operates the facility.  The sale did
not include the property on which the two buried sludge pits are located and
on which the third disposal pit, now backfilled, was also located.  This property
was retained as part of the Stauffer Chemical Company Carbon Disulfide Plant,
which is located adjacent to the PVC Plant property.

     On March 9 and 10, 1982, EPA conducted an inspection and sampling of the
Delaware City PVC Plant.  A total of 20 samples were obtained, including 8
surface water, 9 monitoring well, 2 industrial well, 2 residential well, 3
soil, and 1 waste sample.  Sample results from this inspection have indicated
that serious contamination of the shallow groundwater in the Columbia Formation
exists under the site.  In particular, high levels of VCM, TCE, and EDC were
found in ground water samples from monitoring wells located in the vicinity of
the lagoons and buried sludge pits.

     Subsequent to this inspection, Stauffer Chemical Company and EPA conducted
sampling of the residential wells located northwest of the sources in the
shallow (Columbia) aquifer.  The results showed significant contamination of
the wells with EDC and VCM.  The impacted domestic wells (3 wells) were immediately
replaced with an alternative water supply (tank truck and bottled water).

     The residential well contamination prompted Stauffer to conduct a hydrogeologic
investigation.  This detailed hydrogeologic investigation included: the installation
of 32 monitoring wells, a sensitivity survey, and well sampling.  The results
are described in the Roux Associates, Inc.  report dated February 4, 1983.
The findings and conclusions from the Roux report are outlined below:

     1.  "The shallow geology in the area of investigation, from the land
         surface downward, includes: layers of sand (Columbia Formation); a
         clayey silt aquitard (Merchantville Formation); a sand layer (Magothy
         Formation); and a thick clay layer of the Potomac Formation.

     2.  The Merchantville Formation and upper clay layer of the Potomac Formation
         are apparently continuous beneath the site and hydraulically separate
         the Columbia aquifer from deeper Potomac aquifers.

-------
                              -5-
3T~  High concentrations of EDC and VCM are present in ground water in the
    Columbia aquifer in the area adjacent to, and west of, the PVC plant.

4.   The extent of EDC and VCM in the Columbia aquifer has been deter-
    mined to be limited to an area of the Stauffer and Formosa properties
    west of the PVC plant and possibly a small portion of Getty property
    west of Route 13.  Also, EDC and VCM is limited to the lower portion
    of this aquifer.

5.   Ground water flow in the Columbia aquifer from the western portion of
    the PVC plant property is apparently in all directions.  Observation
    wells in the Columbia aquifer to the north, south, and east of the
    plant do-.-not contain detectable concentrations of EDC or VCM.  Observation
    wells to the west of the plant do contain these compounds.  Therefore,
    based on the distribution of EDC and VCM in the Columbia, the flow of
    ground water containing these compounds is to the west.

6.   Based on the observed ground water flow directions and the concen-
    trations of EDC and VCM in ground water samples from observation
    wells, it appears that the source(s) of EDC and VCM are the surface
    impoundments in the western portion of the PVC plant property.  Based
    on the construction of these impoundments, it is logical to assume
    that the off-grade batch pits, which are unlined, are the principal
    source.

7.   Flow of ground water in Che Columbia aquifer to the west of the PVC
    plant is apparently controlled by the slope of the upper surface of
    the Merchantville, the presence of more permeable sediment in the
    deeper portion of the Columbia, and a ground water mound in the western
    portion of the PVC plant property.

8.   The rate of ground water flow in the Columbia aquifer is estimated to
    range between 0.3 and 1 foot per day (approximately 100 to 300 feet
    per year).

9.   The total volume of ground water flowing past the boundary of Stauffer's
    property to the west (beneath Route 13) is estimated to be 100,000
    gallons per day (70 gallons per minute).  Only the deeper portion of
    this flow contains EDC and VCM.

-------
                                   -6- -
    10.,  -The Columbia aquifer is used locally for individual domestic supplv.
         The deep Potomac aquifer is used locally by Getty for industrial
         water supply.

    11.  No water supply well within the area of investigation, domestic or
         industrial, (except for one on-site Stauffer residence) contains
         detectable concentrations of EDC or VCM.  The one exception (in addition
         to the Stauffer domestic well) is a single finding in 1982 of 6.1 ppb
         EDC in a supply well for an Stapleford Chevrolet Dealer on Route 13,
         south of Wrangle Hill Road.  However, this value was questioned in
         the Roux Report since the concentration was near the detection limit.

    12.  Discharge from the Columbia aquifer appears to be to local streams, '
         primarily Dragon Run.

    13.  None of the stream samples collected in the study area contained
         detectable concentrations of EDC or VCM."

     In May 1984, EPA and the Department of Natural Resources and Environmental
Control (DNREC) entered into a Consent Order with Stauffer and Formosa to per-
form a Feasibility Study (FS) for the site and to implement an approved remed-
ial action.  The final FS was submitted to EPA in June 1986 and was released for
public comment on July 25, 1986.

CURRENT SITE STATUS

     After the submittal of the Roux Associates report, Stauffer and Formosa
continued ground water monitoring in order to track the migration of the ground
water plume.  During one of these sampling efforts in 1983, EDC and VCM were de-
tected in the Foraker Getty Service Station and Stapleford Chevrolet dealer
wells south of the previously mapped plume area.  Stauffer provided an alternate
water supply (tank truck and bottled water) to the owners of these two wells.
This sampling confirmed the contamination of the auto dealer's well questioned
by Roux in 1983.

In August 1985, Stauffer provided city water from their plant to the three
residences on their property.  In 1986, the telephone company relay station
well located south of the Foraker Getty and Stapleford Chevrolet wells, also
became contaminated with EDC, VCM and TCE.  The owner of the well was also
provided with a temporary water supply by Stauffer and Formosa.

-------
                                    -7-
      A  permanent  solution  for  the  Foraker  Getty,  Stapleford  Chevrolet  and
 telephone  company relay  station  wells  will be  specifically addressed during
 the  recommended remedial action.

 ADDITIONAL REMEDIAL  INVESTIGATION  ACTIVITIES

      In accordance with  the  Consent  Agreement,  Stauffer  and  Formosa performed  an
 additional remedial  investigation  (RI)  at  the  site.    This additional  RI work  in-
 cluded  the installation  of monitoring  wells ,  pump testing,  and  soil testing.
 With regard to monitoring, four  (4)  additional  monitoring  wells  were installed to
 identify the extent  of the plume migration. Two  monitoring  wells  OW-30 and  OW-31
 were installed to define the southern  limit of  the plume and two monitoring  wells
-OW-32 and  OW-33 were installed to  determine the northern limit of  the  plume.   These
 monitoring wells, including  other  selected wells,  were sampled during  the  August
 and  December 1984 sampling efforts (see Tables  1  and  2).

      The results  of  the  August and December 1984  sampling  were compared with the
 limits  of  the plume  identified in  the  Roux Associates report dated February  4,
 1983.   A comparison  of the previous  sampling results  and the later results indi-
 cated:

      1.   The ground-water  sample collected in  August  1984  from OW-30 shows
          levels of 1,100 ppb EDC and 50 ppb VCM (Table 1).  This finding is
          consistent  with the ground-water  flow directions  mapped for the area
          and more significantly, this  well showed  no  EDC or  VCM  the first  time
          it was sampled.

      2.   It appears  that the plume has  stabilized  in  the northerly direction.
          Despite  findings  of EDC and VCM in OW-5  from the  inception of the
          project, OW-33, and OW-32 have never  shown EDC  or VCM.  This  situation
          is the result of  this area  of  the Columbia aquifer  being  significantly
          less permeable  with a lower gradient  than those to  the  south.

      3.   Neither  EDC or  VCM  were detected  in the  wells west  of Route 13 (OW-33,
          OW-29, OW-28).

      A  pump test  program was conducted to  determine the  aquifer  hydraulic  para-
 meters  necessary  for the design  of a potential  groundwater intercept system.   It
 was  determined that  recovery wells could be pumped between 10 and  15 gallons
 per  minute (gpm)  over an extended  period of time.

      A  total of ten  test pits  in the former PVC resin storage area
 (TP  9-18)  were excavated on  October  23, 1984 under the supervision of  a
 geologist .from Roux  Associates.  The purpose of excavating these pits  was  to
 investigate this  potential source  area and to  determine  its  significance with
 regard  to local groundwater  contamination.  Samples were collected, logged,

-------
                                   -8-


and delivered to Stauffer's Eastern Research Center for VCM, EDC, and
TCE analysis.  A minimum of two samples were collected from each test
pit, with at least one sample normally being collected from natural
sediments underlying any fill or resin.  The locations of the test
pits are shown on Figure 5 and analysis results are given in Tables 3 & 4.
Four additional test pits (TP19-22) were excavated on November 29, 1984.
The purpose of these pits was to further define the extent of the PVC
resin.  Analytical results for these resin/soil samples are given in
Table 2.  Overall the concentrations of EDC in the soil ranged from
non-detectable (ND) to 120 parts per million (ppm) and the concentrations
of TCE ranged from ND-210 ppm.  Note: the detection limit in soil is 4
ppm.

EflDANGERMENT ASSESSMENT

     The Feasibility Study performed by Malcolm Pirnie provided an analysis
of the potential environmental and health-related impacts represented by the
contaminants VCM, EDC, and TCE.  The analysis used available physiochemical,
toxicological and fate assessment data, relative to the above contaminants, in
order to screen and evaluate potential pathways of exposure, receptors and
associated health and environmental risks.

     For any of the above mentioned compounds to represent a potential threat
to environmental or human receptors, an exposure pathway from these source
areas to the receptors must exist.  The significance of air, surface water,
soil and ground water as potential exposure pathways was considered and
evaluated:

     Air - The small amount of volatilization of EDC, VCM and TCE from the
unlined ditches, batch pits, RV pond and aeration lagoons is the primary
release mechanism to air from the identified sources.  It is estimated that
total VCM emissions from the unlined ditches, batch pits, RV pond and aera-
tion lagoons amount to 0.33 Ib/day.  Relative to releases controlled under
the Clean Air Act from the active operation ,the release of VCM, EDC, and TCE
represents an insignificant exposure pathway.

     Soil - Two types of exposure pathways, direct and indirect dermal con-
tact, are considered in the evaluation of on-site soils.  The most signifi-
cant pathway is direct dermal contact with PVC sludges containing VCM,
EDC or TCE, during their removal or by unauthorized persons entering the

-------
                                   -9-
site.  Direct dermal contact is highly unlikely.  During periods of exca-
vation and removal, specific worker protective controls will be employed
and, in addition, plant security measures are more than sufficient to
ensure that unauthorized site access will not occur.

     The second pathway is indirect contact and involves the contamina-
tion of ground water through leaching of the VCM, EDC and TCE from overlying
PVC sludges.  The Remedial Investigation Study concluded that ground water
contamination by indirect contact with on-site PVC sludges constitutes the
greatest environmental and human health threat.  The proposed remedial
alternative measures will eliminate contaminated PVC sludges as an indirect
exposure pathway to environmental and human receptors.

     Surface Water - Ground water containing VCM, EDC and TCE is migrating
northerly toward Red Lion Creek and southerly toward Dragon Run.  Serving
as a discharge point for the contaminated ground water plume, these surface
waters represent a potential exposure pathway for aquatic biota and humans.
Available data from the literature, however, indicates that the rapid
volatilization rates for VCM, EDC and TCE under the turbulent stream
conditions found in typical surface waters will significantly reduce
these contaminant levels.  Red Lion Creek and Dragon Run may not be
turbulent to the point of producing volatilzation rates comparable to
the literature.  Nevertheless, the potential impacts of the contaminants
reaching the surface water must be addressed.

     Ground Water- A detailed hydrogeologic investigation has confirmed the
presence of the contaminants VCM, EDC and TCE In the Columbia aquifer.  This
aquifer serves as a drinking water supply for residents in the surrounding
area and, therefore, represents a significant potential threat for direct human
exposure via ingestion, inhalation and dermal contact.  Consumption of con-
taminated ground water by local residents represents the most significant
site-related exposure pathway and health risk threat.

     Potential human and environmental receptors at this site are described
below:

     Human Receptors - As discussed earlier, the most significant potential
exposure pathway is via the ground water.  A concern exists that residents
could potentially be exposed to the contaminants via ingestion of the ground
water or via inhalation of vapors or dermal contact during cooking, bathing,
and other domestic uses.  Samples collected from monitoring wells as part
of the Remedial Investigation Study indicate the presence of VCM, EDC, and
TCE.  The use of the three wells on Stauffer property serving residences has
been discontinued due to contamination in one well by VCM and EDC.

-------
                                   -10-


     Rydrogeologic investigations indicate that the ground water plume is
moving away from the site  in a northerly direction, towards Red Lion Creek,
and in a southerly direction towards Dragon Run.  An estimated 25-30 resi-
dences that utilize ground water are located downgradient of the northerly
and southerly paths of the plume.  These residences are located along Route 13
north of its intersection with Route 7, in the vicinity of the intersection
of Route 13 and Wrangle Hill Road, and further to the south along Route 13.
Only one of these residential wells may be tapping deeper, protected aquifers.

     A hydraulic connection, between the ground water and Red Lion Creek
and Dragon Run, represents a potential exposure pathway via surface
water, since these creeks are used for recreational or drinking water
purposes.

     Off-site exposure of humans to VCM, EDC, and TCE via air or soil is
not likely since the release of contaminants from source areas to air is
insignificant and soil dermal contact is virtually non-existent.

     Environmental Receptors - Future potential environmental receptors of
the contaminants VCM, EDC and TCE include the aquatic and terrestrial biota
of the surrounding area, however, there is very little information on the actual
biotic communities present.  The area is largely rural with some commercial/
industrial development.  The primary pathway for exposure of biota is through
surface waters potentially contaminated by groundwater.  The persistence
of these contaminants in surface waters would be limited, as discussed
previously.  In addition, data on VCM, EDC and TCE in the literature indicates
that none of these three substances has a high potential for bioaccumulation
or biomagnification in aquatic or terrestrial biota.

ALTERNATIVE EVALUATION

     The major objectives  for the remedial action to be taken at the
Delaware City PVC site are to abate the sources of contamination and to
mitigate the existing plume of contaminated ground water.  This would
involve preventing and/or  reducing: a) infiltration through the sources;
b) further migration of the existing contaminated shallow ground water;
c) direct contact of the soil with the PVC resin; d) future contamination
of the Potomac Formation,  and e) the degradation of surface waters.  The
requirements of CERCLA Section 104, EPA's mandate to protect the public
health and welfare and the environment, determine the goals and level
of response for the site.

     In an effort to determine remedial alternatives for the subject site,
feasible technologies were identified.  These technologies were then
screened to eliminate all  but the most practicable and implementable ones.
This screening considered: technical, public health, environmental,
institutional, and cost considerations.  Those technologies that passed
the technology screening process were used to form remedial alternatives.

-------
                                     -11-


The remedial alternatives were developed using best engineering judgement
to select a technology or group of technologies that best addresses the
problems existing at the site to protect public health, welfare, and the
environment.  In an effort to provide a degree of flexibility in the final
selection of a remedial action, alternatives covering a range of remedial
action categories have been developed.

     These categories are described below:

     a)  No action

     b)  Alternatives for treatment or disposal in an off-site facility.

     c)  Alternatives which attain public health and environmental standards
         as defined by CERCLA.

     d)   Alternatives which exceed public health and environmental standards
          as defined by CERCLA .

     e)  Alternatives which do not attain public health or environmental
         standards but will reduce the likelihood of present or future
         threat.

     In order to establish a means of evaluating the developed remedial
alternatives, Section 300.68(h) of the National Contingency Plan (NCP) was
reviewed.  In accordance with the NCP, criteria were selected by Malcolm Pirnie
to evaluate the developed alternatives.  With the exception of public acceptance,
the selected criteria presented below are consistent with the EPA Final Draft
Guidance Document for the preparation of Remedial Action Feasibility Studies
under CERCLA dated October 18, 1984 (Draft Guidance Document) and are defined
as follows:

Criterion              Definition

Environmental          Environmental effectiveness is defined as the ability
Effectiveness          of a particular remedial alternative to provide miti-
                       gation of future ground water and surface water contami-
                       nation.
                        o
Reliability            Reliability is defined as the level and difficulty of
                       operation and maintenance (O&M) requirements for a demon-
                       strated technology to reach and maintain the desired per-
                       formance.

-------
                                   -12-
Public
Acceptance
Constructlbility
Time Frame
Safety
Public acceptance is defined as the reaction most likely
to be expressed by the neighboring communities to the
potential health effects of a particular remedial alter-
native.  Community opposition can prevent viable plans
from being implemented.

Constructibility is defined as the labor effort and degree
of construction difficulty necessary to implement a parti-
cular remedial alternative considering the physical charac-
teristics of the site and external factors such as construc-
tion equipment and materials availability.

Time frame is defined as the length of time it takes to
complete the construction of a particular remedial alter-
native.

Safety is defined as the amount of precaution necessary to
prevent accidental exposure from occurring to either on-site
workers or nearby residents during the actual implementation
of a particular remedial alternative or for disposal off site,
     The developed remedial alternatives were ranked (using the matrix approach as
described in Chapter 3 of the Draft Guidance Document) with the six criteria defined
above.  Weighing factors for each criterion, which vary from 0.5 to 1.2, were also
developed and used in the evaluation process.  The weighing factors used by Malcolm
Pirnie were based on prior Remedial Investigation/Feasibility Study (RI/FS) documents
and attempt to reflect the relative importance of the individual criteria.

     A rank ordering technique was used as an effective method to eliminate inappro-
priate alternatives from further detailed consideration.
ANALYSIS OF REMEDIAL ALTERNATIVES

Note:.  Tables 5 & 6 contain costs for all alternatives.

Elements common to alternatives below:

   o Offsite Disposal - The FS prepared by Malcolm Pirnie discusses three
     options for the excavation and disposal of the PVC sludge from the
     impoundments.  These  options are: excavation and disposal of the PVC
     sludge in a municipal landfill, excavation and disposal of the PVC sludge
     in a RCRA Hazardous Waste Management Facility (HWMF) and the recovery of
     the PVC sludge to the maximum extent possible as a saleable finished
 ~   product and disposal  of  the non-recoverable soil/PVC mixture in a RCRA
     HWMF.

-------
                              -13-
fhe disposal of the PVC sludges in the municipal landfill does not comply
with the Agency's policy regarding the off-site disposal of Superfund
waste.  The Off-Site Disposal Policy requires all of the waste from a
Superfund site to be taken to a RCRA HWMF.  Therefore, this alternative
was determined to be unacceptable by EPA.

   The disposal of the PVC sludge at a RCRA HWMF while complying with
the Agency's Off-Site Policy is an expensive alternative (approximately
2-3 times cost of disposal at a municipal facility) and does not
necessarily provide a .permanent remedy.  The recovery of the sludge and
disposal of the excess waste in a RCRA facility is cost effective and
environmentally effective, because it reduces the amount of waste to be
taken off-site, provides a permanent remedy for a significant percentage
of the existing PVC sludge, is less expensive than disposal of all the
PVC sludge in a RCRA facility and is comparable in cost to the disposal
of all the PVC sludge in the municipal landfill.  It also attains all
environmental and public health standards under CERCLA.

     The recovery of the PVC sludges to the maximum extent possible
(estimated by the companies to be 80-85%) as a saleable finished product
and disposal of the non-recoverable soil/PVC mixture in a RCRA Hazardous
Waste Management Facility (HWMF) will be -used in the source control
alternatives.

Use of RCRA controls - Most of the alternatives listed below include the
installation of some type of liner or cap to prevent or minimize the
continuing leaching of contaminants into the groundwater at the site.  The
Malcolm Pirnie study discusses the use of clay, single synthetic and double
synthetic liners, concrete lining for the trenches and single and double
synthetic caps.

   The National Contingency Plan ( Section 300.68(j), 47 Fed. Reg., 31180
[July 16, 1982]) states that the remedial alternative selected will be the
one the Agency determines is cost effective (i.e. the lowest cost alternative
that is technically feasible, reliable, and which will effectively mitigate
or minimize damage to human health, welfare and the environment.)  In
addition, in selecting a remedial action for this site, the EPA must also
consider all other applicable environmental laws including RCRA.

   Vinyl chloride is a RCRA listed waste in pure form, but when mixed with
byproducts of manufacturing, the waste mixture is exempt.  EPA examined
the technical alternatives presented and available to minimize migration
of contaminants.  The relevant standards for caps and liners, outlined in
RCRA for control of migration of hazardous wastes, were seen to provide
the control that is required.  Therefore, the alternatives were evaluated
in this light to insure that they meet the requirements of CERCLA and the
NCP and are essentially those that would be required under RCRA.

The design requirements for multi-media or multiple caps and liners
outlined in RCRA are suitable for storage areas and treatment units because
they allow better environmental protection than single liners and enable
monitoring of the upper cap or liner to identify failures before
serious leakage results.

-------
                                   -14-
ANALYSIS OF REMEDIAL ALTERNATIVES (cont)
A.   Off-grade Batch Pits and RV Pond Remedial Alternatives

     These two sources have been considered together since the same remedial
actions apply to both.  In developing remedial alternatives, it was determined
that Formosa would continue to keep both the offgrade batch pits and the RV
Pond in service due to their importance in the continued operation of the
Plant.  Hence, any alternatives in which these impoundments are taken out of
service were initially screened out.
Alternative No. 1 -  No Action

     This alternative involves no remedial action and leaves the sources
in their existing state.  Both off-grade batch pits and RV pond are of
earthen construction which  is not suitable for retaining wastewater.  At the
present time, the PVC sludges placed in these basins are in direct contact
with the soil and cause groundwater contamination through leaching of the
VCM, EDO, and TCE.  The groundwater contamination through direct contact
with on-site PVC sludges constitutes the greatest environmental and human
health threat.  A no action alternative would provide no additional protection
to the public health or environment and the contamination of soil and
groundwater would continue.
Alternative No. 2 - Recovery  of  the PVC Sludges and Installation of a
Clay Liner
     This alternative  includes excavation of the PVC sludges and co'ntaminated
soil to levels to be determined  at the design stage and recovery of PVC to
the maximum extent possible.  Disposal of non-recoverable material will be at
an off-site RCRA HWMF.  This  alternative also includes installation of a
three foot clay liner  compacted  to a permeability of 10-^ cm/sec.

     Since this alternative involves excavation and recovery of contaminated
sludges, the  risk of further  groundwater contamination from these sludges
will be eliminated.  The  clay liner will prevent the leaching of VCM, EDC,
and TCE into  the groundwater. The clay liner, however, may not be completely
reliable due  to the potential for cracking, thus jeopardizing the integrity
of the liner.  This alternative  does not attain public health and environmental
standards as  defined by CERCLA.

-------
                                   -15-
Alternative No. 3 - Recovery of the PVC Sludges and Installation of
a Single Synthetic Liner

     This alternative includes excavation of the PVC sludges and
contaminated soil to levels to be determined at the design stage, and
recovery of PVC to the maximum extent possible.  Disposal of non-recoverable
material will be at an off-site RCRA HWMF.  This alternative also includes
installation of a single synthetic liner.  .Prior to installation of a
synthetic liner, the site will be carefully graded to remove rocks and
other materials that may puncture the liner and a layer of clay or geotextile
material may be placed as a sub-base.  A one foot thick layer of clay will
be placed on top of the synthetic liner to protect against weathering.
Three downgradient monitoring wells will be installed to monitor any
potential contaminant migration from the pits and the pond.  The wells
will be initially sampled on a quarterly basis for PH, TOC, TOX, conductivity,
VCM, TCE and EDC.  If sampling results from two consecutive quarters are
found to be consistent and acceptable, further sampling may be extended to
semi-annually.  In addition, a Hazardous Substance List (HSL) analysis
will be conducted once a year.

     Since this alternative involves recovery of contaminated sludges, the
risk of ground water contamination from these sludges will be eliminated.
The single synthetic liner is more environmentally effective than a clay
liner, but single liners do not attain public health and environmental
standards as defined by CERCLA.
                                              «
Alternative No. 4 - Recovery of the PVC Sludges and Installation of
a Double Synthetic Liner

     Under this alternative, the contaminated sludges and soil will be
excavated to levels to be determined at the design stage and will be
recovered to the maximum extent possible.  Non-recoverable material will
be disposed of off-site in a RCRA HWMF.  The risk of groundwater
contamination from direct contact of these sludges with the soil will be
eliminated.  This alternative also includes installation of a double
synthetic liner.  Prior to installation of the lower (secondary) liner,
the site will be carefully graded to remove rocks and other materials that
may puncture the liner.  Then a layer of clay will be placed as a sub-base
on the graded site.  After the secondary liner is placed, a loose fill
material (sand/gravel) will be installed on top.  This fill material will
provide drainage to a leak detection system which will also be installed
at that time.  The leak detection system is generally a slotted pipe that
is pitched to a sump located outside of the impoundment.  Due to the slope
of the pits and the RV pond, a loose fill would not remain on the side
slopes.  A geotextile fabric will, therefore, be placed between the
synthetic liners along the side slopes.  Above the drainage layer an upper
synthetic liner will be installed and a one-foot thick clay layer will be
placed on top of the upper synthetic liner to protect it against weathering
and erosion.  The liner and geotextile fabric will be tied into the berm
around the impoundment with the top clay cover extended to cover the tie-in.
The monitoring requirements for this alternative would be the same as for
the single liner alternative described earlier.

-------
                                    -16-
     Th e double liner alternative will provide the most protection against
groundVate'r contamination.  Any wastewater that possibly penetrates through
the first liner should be retained by the second and detected by the detection
system.  Hence, the environmental effectiveness of the double liner is considered
to be excellent.

     Reliability of the double liner is judged to be excellent due to low
operation and maintenance requirements once the system is installed.  In addition,
double synthetic liner systems with leak detection systems have demonstrated
their reliability and applicability at similar sites.  In particular, the
double liner is more reliable in preventing leakage than the clay or single
synthetic liner over time and represents a small increase in cost.

     The double liner alternative meets all public health and environmental
standards as defined by CERCLA.

B.  Unlined Ditches Remedial Alternatives

     In developing remedial alternatives for the unlined ditches it was deter-
mined that Formosa would continue to operate the ditches as part of their
wastewater treatment plant.  It was also determined that the PVC sludges with-
in the unlined ditches cannot be recovered due to contamination with soil in
the ditches and, therefore, approximately 100 cubic yards (cy) of solids will
be removed and disposed of in a RCRA HWMF.  The amount of solid material to be
removed is based on a one foot deep excavation along an estimated twenty five
percent of the total length of the unlined ditches.  The actual areas which
require excavation were visually noted during a 1985 site visit, based on
the presence of the white PVC residue.

Alternative No. 1 - No Action
     This alternative involves no remedial action and leavas the source in
its existing state.  The unlined ditches are of earthen construction and do
not prevent leaching of VCM, TCE, and EDC from the PVC solids into the
groundwater.  The groundwater contamination through contact with on-site
PVC sludges constitutes the greatest environmental and human health threat.
A no action alternative would provide no additional protection to the public
health and the environment and the contamination of soil and groundwater. would
be expected to continue.

Alternative No. 2 - Installation of Concrete Trench

     In this alternative no contamination would be removed and a pre-cast 4-inch
thick concrete liner would be placed in the ditches (see Fig. 7).  The concrete
trench would be susceptible to erosion and cracking during its operation.  If
cracking does occur, it could cause further ground water contamination due to
leaching of the VCM, EDC, and TCE from the PVC sludges that are left in the
ditches.  Thi.s alternative does not attain public health and environmental
standards as defined by CERCLA.

-------
                                      -17-


Alt'ernative No. 3 - PVC Sludge Excavation and Installation of Single
Synthetic Liner

     In this alternative, contaminated sludges will be removed and disposed of
off-site in a RCRA HWMF.  The risk of groundwater contamination due to direct
contact of the sludges with the soil will be eliminated.  This alternative
also involves installation of a single synthetic liner (see Fig. 7). These
ditches convey waste to storage areas and are not storage areas themselves.
Single liners are believed to provide an adequate barrier and effective protection
of the groundwater.  Prior to installation of the synthetic liner, the site
will be carefully graded to remove rocks and other materials that may puncture
the liner.  A geotextile fabric will be used as the sub-base material to protect
the liner from puncturing.  The geotextile fabric will also help to
keep the side slopes from eroding.

     The PVC sludge excavation and lining of the ditches with an impermeable
synthetic liner will significantly reduce the potential for leakage into the
groundwater.  The environmental effectiveness of the synthetic liner was judged
to be excellent compared to that of a concrete trench.  There are concerns
regarding the stability of the synthetic liner with the eroding side slopes,
however, the geotextile fabric will be helpful in controlling this factor.

     This alternative attains public health and environmental standards as
defined by CERCLA.

Alternative No. A - PVC Sludge Excavation and Installation of Concrete Trench

     In this alternative, contaminated sludges will be removed and disposed of
off-site in a RCRA HWMF.  The risk of groundwater contamination due to direct
contact of sludges with the soil will be eliminated.  This alternative also
includes installation of a pre-cast 4-inch thick concrete liner.  The concrete
trench will be susceptible to erosion and cracking during its operation.  If
cracking does occur, it could cause further groundwater contamination due to
leaching of the VCM, EDC, and TCE from the PVC sludges that are contained in
the ditches due to the active operations.   This alternative does not attain
public health and environmental standards as defined by CERCLA.

C.  Aerated Lagoons - Remedial Alternatives

     In developing remedial actions/alternatives for the aerated lagoons it was
determined that Formosa would continue to operate the lagoons as part of their
wastewater treatment plant.  Therefore, any alternatives in which these impound-
ments are taken out of service have not been considered.  Additionally, the
recovery of the PVC sludges to the maximum extent possible as a saleable finished
product and disposal of the non-recoverable soil/PVC mixture in a RCRA HWMF will
be used in all of the source control alternatives.

Alternative No. 1 - No Action

     This alternative involves no remedial action and leaves the source in its
existing state.  The lagoons are constructed with a reinforced concrete liner,
which has eroded in different areas.  At the present time, these lagoons are
not effective  in retaining wastewater.  The VCM, TCE and EDC found in the PVC

-------
                                   -18-
sludges, move through cracks in the concrete liner and cause groundwater
contamination.  The groundwater contamination at the site constitutes a
great environmental and human health threat.  A no action alternative would
provide no additional protection to the public health or environment and the
contamination of soil and groundwater could be expected to continue.

Alternative No. 2 - PVC Sludge Recovery and Repair of a Concrete Liner

     This alternative includes excavation of the PVC sludges and recovery of
PVC to the maximum extent possible.  Disposal of non-recoverable material will
be in an off-site RCRA HWMF.  The risk of groundwater contamination due to
leaching of the VCM, EDC and TCE through cracks in the existing concrete
liner will be eliminated.  This alternative also includes the repair of the
existing concrete liner.  After the liner is repaired, it will still be sensitive
to'erosion and cracking during its operation.  If cracking does occur, it
could cause further groundwater contamination due to leaching of the VCM, EDC
and TCE from the PVC sludges.  This alternative does not attain all public
health and environmental standards as defined by CERCLA.

Alternative No. 3 - PVC Sludge Recovery and Installation of a Single
Synthetic Liner

     This alternative includes excavation of the PVC sludges and recovery of
PVC to the maximum extent possible.  Disposal of non-recoverable material would
be in an off-site RCRA HWMF.

     This alternative also includes repair of the existing concrete liner and
installation of a single synthetic liner over the existing liner.  The risk of
groundwater contamination due to leaching of the VCM, EDC and TCE through the
cracks in the existing concrete liner would be eliminated.

     After excavation of the accumulated PVC solids and crack repair,
geotextile fabric will be placed over the existing concrete to protect the
synthetic liner from wear and puncture.  Monitoring wells will be installed
and sampled to verify the containment (as described for the offgrade batch pits
and RV pond).  The single liner system placed over the cleaned and repaired
existing liner would provide more protection against leakage of the contaminants
to groundwater than the repaired concrete liner.  However, a single synthetic
liner system does not attain all public health and environmental standards as
defined by CERCLA.

Alternative No. 4 - PVC Recovery and Installation of a Double Synthetic Liner

     Under this alternative, the contaminated sludges will be recovered to the
maximum extent possible and non-recoverable material will be disposed of off-site
in a RCRA HWMF.  The risk of groundwater contamination due to leaching of the
VCM, EDC and TCE through the cracks in the existing concrete liner will be
eliminated.

-------
                                      -19-
     This -alternative also includes repair of the existing concrete liner and
installation of a double synthetic liner over the existing liner.  The double
liner system has been described previously:  clay sub-base, secondary synthetic
liner, leak detection system, geotextile fabric, primary synthetic liner, and
clay cover.  Monitoring wells will be installed and sampled to verify
containment (as described for offgrade batch pits and RV pond).

     The double liner alternative will provide the greatest protection against
groundwater contamination.  Any wastewater that could possibly penetrate through
the first liner should be retained by the second and detected by the leak
detection system.  Hence, the environmental effectiveness of the double liner
is considered to be excellent.

     Reliability of the double liner is judged to be excellent due to low
operation and maintenance requirements once the system is installed.  In
addition, double synthetic liner systems with leak detection systems have
demonstrated their availability and applicability at similar sites.

     The double liner is more reliable in preventing leakage than the concrete
or single synthetic liner over time and represents a small increase in cost.

     The double liner alternative meets all public health and environmental
standards as defined by CERCLA.

D.  Closed Buried Sludge Pits - Remedial Alternatives

     The unlined closed buried sludge pits (approximately 30,000 ft^ in
area) were used to dispose of PVC solids and sludge from aeration lagoons.  In
1979, these pits were closed out with a single 20 mil PVC cap, covered with
topsoil and revegetated.  The capped area was graded to promote stormwater
runoff to a collection ditch which runs along the perimeter of the area.  The
synthetic cap is tied into the ground beyond the extent of the contaminated
sludges and soils.  It should be noted that direct contact of the buried sludges
with the underlying groundwater is not anticipated to be a problem, since the
water table lies below the deepest area of contamination.

Alternative No. 1 - No Action

     In this alternative the existing cap would be periodically inspected for
signs of erosion, puncture, infiltration and repaired as necessary.  An inspection
of the PVC liner conducted in July 1985 by Stauffer, indicated minimal to no
reduction of integrity of the cap system.  The topsoil was uncovered at two
locations to sample the integrity of the PVC cap.  These samples exhibited no
cracks, tears or perforations caused during six years of service.

     The existing synthetic cap appears to prevent percolation of stormwater
since it promotes stormwater runoff to a collection ditch running along
the perimeter of the pits.  However, if the cap is not maintained properly,
there is a potential for cracks, tears or perforations to occur which would

-------
                                      -20-
contrib.ute-.to groundwater contamination through leaching of the VCM, EDC and
TCE.  This alternative does not attain public health and environmental standards
as defined by CERCLA.

Alternative No. 2 - Recapping

     This alternative involves placing 18" - 24" of loose material (sand/gravel)
to serve as a drainage layer on top of the existing synthetic liner and providing
an additional synthetic cap over the drainage layer.  This new liner would
then be covered with topsoil and revegetated.  The new liner would extend 10
feet beyond existing liner.

     This double cap alternative will provide more protection against groundwater
contamination than a single synthetic cap.  Any percolation that could possibly
penetrate through the first liner should be retained by the drainage system
and the second liner.  The double cap is more reliable in preventing leakage than
the single cap over time and represents a small increase in cost.  This alternative
meets all public health and environmental standards as defined by CERCLA.

Alternative No. 3 - Excavation and Removal

     This alternative involves excavation and removal of all contaminated
material and disposal in a RCRA HWMF.  Removing the contaminated soil and
sludges would entail excavating approximately 25,000 cubic yards.  The area
would be regraded upon the removal of the contaminated material.

     This alternative would eliminate the source of contamination and therefore
protect the groundwater from further contamination.

     This alternative meets all public health and environmental standards as
defined by CERCLA.

E.  Former PVC Resin Storage Area - Remedial Alternatives

     The former PVC storage area (approximately 12,000 ft^ in area) had been
excavated and regraded in 1974 by Stauffer.  During the performance of the FS,
fourteen test pits were excavated under the supervision of a geologist from
Roux Associates in order to determine the extent of contamination in this
source area.  The concentrations of EDC in the soil ranged from ND to 120 ppm
and the concentrations of TCE ranged .from ND to 210 ppm.  ND indicated con-
centrations less than the 4 ppm detection limit.

     The remedial actions for the former PVC resin storage area involve preventing
the stormwater from contacting the PVC resin and contaminated soil that are
present on-site.  The remedial alternatives, therefore, involve either removal
of all the contaminated material or capping to prevent storrawater percolation.
Direct contact of the contaminated material with the underlying groundwater is
not anticipated to be a problem since the water table lies below the area of
contamination.

-------
                                      -21-
Alternative No. I - No Action

     This alternative involves no remedial action and leaves the source in its
existing state.  At the present time, the stormwater percolates through the
PVC resin and the contaminated soils and contaminates the groundwater through
leaching of the VCM, EDC and TCE.  The groundwater contamination through storm-
water percolation constitutes an environmental and human health threat.  The
no action alternative would provide no additional protection to the public
health and environment and the contamination of groundwater would be expected
to continue.

Alternative No. 2 - Excavation and Removal               i

     Under this alternative, the areas of highest contamination will be excavated
arid disposed of in a RCRA HWMF.  Based on the analytical results from test pit
excavation and sampling, it was determined by Malcolm Pirnie, that test pit (TP)
12 and TP-14 should he excavated.  TP-12 contained 210 ppm of TCE at a depth of 24'
and TP-14 contained 120 ppm of EDC and 50 ppm of TCE at a depth of 42".  The
total amount of material removed will be 615 cubic yards.  The highest
concentration of any contaminant to remain in the soil would be 27 ppra of EDC
located at a depth of 5"5" in TP-9.

     This alternative would not provide protection against groundwater contami-
nation, because the leachate generated from the soil left on-site would cause
concentrations of contaminants in groundwater greater than the 10~6 Unit Cancer
Risk (UCR).  This alternative does not meet all public health and environmental
standards as defined by CERCLA.
                                              •
Alternative No. 3 - CappingtheAreas of Highest Contamination with Single
Synthetic Liner

     Under this alternative the material would be left in place and the areas
of highest contamination will be capped with a synthetic cap.  The cap would
be installed over a 2,700 square foot area around both TP-12 and TP-14.  Prior
to cap installation, additional tests would be performed around TP-12 and TP-14
to confirm that significant levels of PVC sludges exist and warrant capping.

     This alternative would not provide protection against ground water contami-
nation, because the leachate generated from the soil left uncovered would cause
concentrations of contaminants in the groundwater greater than the 10~6 UCR.
Also, the areas that will be capped may develop cracks, tears or perforations
if they are not properly maintained.  This could contribute to groundwater
contamination through leaching of the VCM, EDC and TCE.

     This alternative does not attain public health and environmental standards
as defined -by CERCLA.

Alternative No. 4 - Capping the Entire Area with a Single Synthetic Cap

     This alternative involves installation of a synthetic cap over the entire

-------
                                      -22-
area.  The installation of the synthetic membrane would involve sub-base grading,
placement of a sand layer, installation of a membrane, topsoil placement and
vegetation of topsoil.  The synthetic liner would also extend approximately 10
feet beyond the area of contamination.

This alternative does not attain public health and environmental standards as
defined by CERCLA.

Alternative No. 5 - Capping the Entire Area with a Double Synthetic Cap

     This alternative involves installation of a double synthetic cap over the
entire area.  The installation of a double synthetic liner would involve grading
the site, placement of  a sand layer, installation of a lower membrane, installa-
tion of a drainage layer, placement of an upper membrane, topsoil placement
and vegetation of topsoil.

     The double cap alternative will provide more protection against groundwater
contamination than a single synthetic cap.  Any percolation that could possibly
penetrate through the first cap would be retained by the drainage layer and
the second cap.

     The double cap alternative is more reliable in preventing leakage than a
single cap and represents a small increase in cost.

     The double cap alternative meets all public health and environmental
standards as defined by CERCLA.

F.  Groundwater - Remedial Alternatives

     At the present time, groundwater containing EDC, VCM nd TCE is flowing
west from the area of the identified sources.  Groundwater flowing to the
northwest toward OW-5 turns in a northerly direction (roughly parallel to Route
13) and flows towards Red Lion Creek.  Groundwater flowing toward OW-16 turns
in a southerly direction and  flows towards Dragon Run.  The alternatives to be
discussed below involve either plume remediation or plume management.  For the
alternatives that involve plume remediation, the recovered water will be used
in Formosa's PVC plant operations.  During any low water demand period at the
plant, the recovered water will be discharged to Formosa's wastewater treatment
plant.  The discharge of the  treated groundwater will be in compliance with NPDES
standards.

     Alternative technologies considered for groundwater remediation included
biological-; physical and chemical treatment.  Due to low concentrations of
contaminants in the groundwater, most alternatives were eliminated on both a
technical and cost basis.  Air stripping remained after initial screening but
was not chosen because reuse  of the water in the plant was more cost-effective..

-------
                                       -23-
Alternative No.  1  - No Action

     This alternative involves no  remedial  action  and  leaves  the  site  in  its
existing state.  A detailed hydrogeologic .investigation  has confirmed  the
presence of the  contaminants VCM,  EDC  and TCE  in  the  Columbia aquifer.  The
aquifer serves as  a drinking water supply to residents in  the surrounding
area.  Without groundwater controls, the contaminant  plume will continue  to
migrate in the northerly and southerly directions  and  will impact  the  residential
wells located downgradient.  At  the present, an estimated  25-30 residences
are  located downgradient of the  northerly  and southerly paths of  plume.  The
migration of the contaminated  plume represents a  significant  potential  threat  to
those citizens who are currently using the  aquifer through direct  exposure via
ingestion, inhalation and  dermal contact.

     The contaminated groundwater, if  not recovered,  will  eventually discharge
into Red Lion Creek and Dragon Run. Additionally, is  has  been calculated that
EDC  and VCM will be present in the groundwater at  the  discharge point  in
concentrations greater than allowed by EPA  Water  Quality Criteria.  Aquatic
and  terrestrial  biota may  be impacted  due to the  presence  of  these  contaminants
in the surface waters.  Also,  there is a potential threat  to  the  population
utilizing these  creeks for recreational or  drinking purposes.

     A no action  alternative would  provide no additional  protection  to  the public
health or environment and  the  contamination of the groundwater and  surface
waters would be  expected to continue.

Alternative No.  2  - Downgradient Pumping to Collect Groundwater at  the
Edge of the Existing Plume in  the  Buried Valley

     This alternative involves installation of two lines of pumping wells, one
across the buried" valley at the  northern edge  of  the  plume and one  across the
valley at the southern edge in order to collect  the EDC, VCM  and  TCE contaminated
groundwater.  (see Fig. 8)

     EDC and VCM have been detected in monitoring  well OW-5  (at  1,6000  and 310
parts per billion(ppb), respectively during August 1984  sampling).  Well  OW-32,
300  feet downgradient of OW-5, has not shown these compounds. Likewise,  OW-22,
further downgradient, has  never  shown  EDC or VCM.   Therefore, the  edge  of the
plume is somewhere between OW-5  and OW-32.

     Through August  1984,  OW-3 had consistently shown traces  of EDC
(less than  5ppb) but no VCM.   In the December  1984 sampling,  EDC  and VCM  were
detected.  The northern line would consist  of  six  wells  each  pumping  1015gpm.
OW-5 could be incorporated into  this line of pumping  wells.   Any  EDC/VCM/TCE
that may have migrated past OW-5 towards OW-2, will be drawn  back toward  and
.withdrawn by the northern  line of  pumping wells.

     Six piezometers would be  installed both upgradient  and  downgradient  of
this line of wells.  Water levels  will be  taken on a  quarterly basis  for  the
duration ol  the  pumping to demonstrate that the  system is  effectively  inter-
cepting all  EDC, VCM, and  TCE  contamination in the identified plume area.

-------
     The southern line of punning wells would trend northeast from Route 13
through OW-16.  Through the action of these wells, all EDC, VCM and TCE flowing
to the south from the existing plume area can be intercepted.  OW-30 showed
EDC (1,100 ppb) and VCM (50 ppb) for the first time during August 1984 sampling.
EDC/VCM/TCE in the vicinity of OW-30 will be drawn back .to the proposed line
of pumping wells.  Six piezometers would be installed both upgradient and
downgradient of this line of wells, so that accurate water level data can be
collected.  In this way it can be shown that all EDC/VCM/TCE from the identified
plume is being intercepted.  Similar to the northern line, six pumping wells
would be required.  Existing monitoring well OW-16 could be incorporated as
one of the pumping wells.  Each pumping well in the northern and southern
lines would consist of six-inch diameter casing and ten feet of screen.  Well
depths would range from 50 to 70 feet below the surface and each well would be
pulped at  10 to  15 gpm.  The piezometers would consist of two-inch diameter
casing and screen and be screened at the same hydrogeologic setting as the
pumping wells.  The lower portion of the Columbia aquifer has been shown to be
contaminated with EDC, VCM and TCE in the February 4, 1983, hydrogeology report.

     These two lines of wells are designed to intercept and collect water from
the deeper portion of the aquifer that contains the EDC, VCM and TCE.  The
exact number, location and pumping rates will be adjusted, if necessary, during
the final design phase of the remedial program to ensure complete capture of
the groundwater plume.

     The recovery wells will be operated until the concentrations of VCM, EDC
and TCE in these wells reach 1 ppb, 0.94 ppb, and 2.7 ppb respectively for. two
consecutive sample analysis.

     This alternative also includes replacement of the Getty Gas Station,
Stapleford Chevrolet and Telephone Company Relay station wells.  A pilot hole
to 300 feet below land surface will be drilled and sediment cores will be
logged at regular intervals.  A suitable water-bearing unit in either the
Magothy or Upper Potomac aquifers will then be selected as an alternative source
of water to these businesses.

     Two monitoring wells will be installed at the southern edge of the plume to
monitor the movement of the contaminated plume.  These wells will be sampled
semi-annually for VCM, EDC and TCE.  Downgradient residents using well water
will be provided a permanent potable water supply, if EPA/DNREC determine at
any time,  that contamination of the residential wells is imminent.

This alternative provides  for plume control, groundwater remediation and
alternate water  supplies.

-------
                                    -25-
Alternative No. 3 - Downgradient and Within Plume Pumpage to Collect All
Contaminated Groundvater

     This alternative involves the two lines of pumping wells described in
Alternative No. 2.  In addition, a third line of wells would be set up within
the existing plume area.  Use of the three lines of wells would speed up the
clean-up time, because more water would be collected, (see Fig. 8)

     The third line of wells would consist of eight new pumping wells spaced
approximately 125 feet apart.  The line would extend from the vicinity of
existing monitoring well OW-17 towards monitoring Well OW-1.  Both four-inch
diameter monitoring Wells OW-17 and OW-1 could be used as part of this system.
The total of ten wells in this line would be pumped at 10 gpra each which would
adds an extra lOOgpm of pumpage to this alternative.

     The third line of new wells within the existing plume area would effectively
intercept contaminated groundwater flowing from the identified sources.  The
two lines in the buried valley would effectively intercept groundwater containing
EDC, VCM and TCE from the edge of the existing plume.

     Each well in the third line of wells would consist of a six-inch diameter
casing with five feet of screen.  These wells would be shallower than their
buried valley equivalents due to the higher elevation of the underlying aquitard.
It is estimated that these wells will be 50 feet deep.  The exact number,
location and pumping rates will be adjusted, if necessary, during the final
design phase of the remedial program to ensure complete capture of the groundwater
plume.

     It is recommended that ten 2-inch diameter piezometers be installed both
upgradient and downgradient of this third line to effectively measure the
extent of the radius of influence of this line to the west.

     This system of three lines of pumping wells has one major advantage.  One
volume (from the sources to the intercept wells) of the identified plume can
be removed in half the time that an equal volume of contaminated  water would
be captured through implementation of Alternative I.  The third line is located
downgradient of a lower permeability area where groundwater flow rates are
significantly slower than in the buried valley.  Thus the cleanup of the
plume could be completed in less time.  A potential disadvantage of this expanded
system is that the larger volume of water removed (280 gpm total) may limit
choices for disposition of water.

     The recovery wells would be shut off when the concentrations of VCM,
EDC and TCE in the recovery wells reach 1 ppb, 0.04 ppb, and 2.7 ppb respectively
for two consecutive sample analyses.

     This alternative includes replacement of the Getty Gas Station,
Stapleford Chevrolet and Telephone Company Relay Station Wells as described

-------
                                       -26-
 in  Alternative No.  2.
       ^..

      Two monitoring wells will be  installed  at  the southern  edge  of  the  plume
 to  monitor movement of the contaminated  plume.   These  wells  will  be  sampled
 semi-annually for  VCM, EDC and TCE.   The three  lines of  wells  are designed to
 intercept and collect  water from the deeper  portion of the aquifer that  contains
 the  EDC,  VCM and TCE.   The exact number, location and  pumping  rates  of these
 wells will be adjusted, if necessary,  during the final design  phase  of the
 remedial  program to ensure complete  capture  of  the groundwater plume.

 Alternative No. 4  - Plume Management

      The  fourth alternative is plume management.   Plume  management involves
 implementation of  a monitoring network to track the movement of the  plume to
 re-Ceptors.  Under  natural conditions,  groundwater in the buried valley flows
 either to the north or south to discharge into  Red Lion  Creek  or  Dragon  Run
 respectively (Figure 8).   The rate of  movement  of the  existing plume to  the north
 appears  to be slower than movement to  the south because  sediments to the north
 are  significantly  less permeable than  those  to  the south (based on pump  test
 results).  (see Fig. 9)

      A number of items must be addressed in  implementing any plume management
 alternative.   These are:

      1.   The  projected path(s) of  the  plume  must  be verified.

      2.   The  identified sources must be  abated  so the  plume  is allowed to
          flush itself  naturally.

      3.   An adequate monitoring system must  be  set up  over the lifetime  of the
          existing  plume.

      4.   Domestic  wells in the path  of the plume, particularly at the same
          horizon in the aquifer, must  be identified so alternative supplies of
          water can  be  provided, if necessary.

      5.   The  future use of lands above the plume must  be determined  so as to
          prevent supply wells from inadvertently being installed  into the
          plume.

      6.   The  effects (if  any) of plume discharge  into  receptors must be  determined,

 This alternative allows continuing contamination of the  aquifer and  demands
 extensive monitoring and  institutional controls.   EPA  has determined that this
 does not  meet all  public health and  environmental standards  as defined by CERCLA.

 Alternative No. 5  - Delaware DNREC - Remedial Alternative
w
      The  State of  Delaware proposed  an additional alternative  to  the four
 described above.   In the  State's proposal an industrial  water  supply wellfield
 would be developed along either the  east or  west  side  of Route 13.   The  resulting
 water supply could be  used by Stauffer/Formosa  for one or more purposes  in
 ongoing operations. The  State assumed that  the groundwater  would have a maximum

-------
                                       -27-
concentjation of EDC and/or VCM of  1000 ppb.  The  actual  detections  provide  an
average concentration of 7,000 ppb  EDC, 400 ppb VCM, and  lOppb  TCE  for  groundwater
collected by the recovery wells.  Groundwater flow paths  were projected from
the identified sources to each of the potential recovery  wells.   The  highest
levels of VCM, EDC and TCE recorded at each monitoring well within a  flow  path
were averaged.  Each of these numbers was  then averaged.   These  calculations
take into account 25% dilution by uncontaminated water withdrawn along  with
the plume water.

     Such a wellfield would accomplish the major goals described in  the State's
proposal.  The major goals of the State's  proposed alternative  are to provide
water from a wellfield while ensuring protection of the deeper  aquifer  system.
An ancillary benefit is the removal of water containing EDC, VCM and  TCE.
The State also proposed to construct a waterline for the  residences  along
the' discharge path as part of the cleanup.  However, Malcolm Pirnie  determined
that this alternative would not effectively remove all .EDC, VCM  and  TCE from
the identified plume.  In particular, the  DNREC's  alternative would  be  unable
to capture all of the plume unless wells are installed along the entire width
of the plume, parallel to the buried valley and in poor waterbearing  areas.

CONSISTENCY WITH OTHER ENVIRONMENTAL LAWS
     Alternatives were examined in light of applicable  Federal,  State  and  local
environmental program requirements and  in  light  of  all  CERCLA  requirements.

     The remedial actions proposed will be coordinated  with  the  State  to  insure
that the water and air quality will meet all  applicable standards.
                                                •
RECOMMENDED ALTERNATIVE  (see Table 6)

     Section 300.68(j) of the National  Contingency  Plan (NCP)  states that  the
appropriate extent of remedy shall be determined by the lead agency's  selection
of a remedial alternative which the agency determines is  cost-effective  (i.e.,
the lowest cost alternative that  is technically  feasible  and reliable  and
which effectively mitigates and minimizes damage to and provides adequate
protection of public health, welfare and the  environment).   In selecting  a
remedial alternative, EPA must consider all environmental  laws that are  applicable
Based on the evaluation  of the cost effectiveness of each proposed alternative,
,the analysis contained above and  the comments received  from  the  public and
information from the Delaware Department of Natural Resources  and Environmental
Control (DNREC), we recommend the following remedial alternative for the
six-identified sources and the groundwater:

     1.  Off-grade Batch Pits - Excavate and  Remove PVC sludges  and contaminated
soils to the levels to be determined at the design  stage;  install a double
synthetic  (or RCRA conforming equivalent)  liner, install  monitoring wells  and
perform quarterly sample analysis for TCE, EDC and  VCM.  The excavated material

-------
                                       -28-
 will be directly processed and recovered  (estimated by the companies  to  be  80-85%)
 as  a saleable finished product to the  maximum extent possible.   Non-recoverable
 material will be disposed  of off-site  at  an  approved RCRA facility.   Since
 this alternative involves  recovery of  contaminated  sludges,  the  risk  of  groundwater
 contamination from these sludges  will  be  eliminated.

      The double  liner will provide the most  protection against  leakage of the
 contaminants.

      2.   RV Pond - The same remedy as  described  above for the off-grade  batch
 pits.

      3.   Unlined Ditches - Excavate and remove PVC  sludge, intall  a single
 synthetic liner.  The excavated material  will be disposed of off-site at an
 approved RCRA facility.   Excavation and removal  of  PVC sludges will eliminate
 the risk of groundwater contamination  from these sludges.  The  single synthetic
 liner will provide protection against  leakage of the contaminants  into the
 groundwater.

      4.   Aerated Lagoons - Excavate and remove PVC  sludge, clean and  repair
 lagoons, install a double  synthetic (or RCRA conforming equivalent) liner and
 monitoring wells.   The excavated  material will be recovered  (estimated by the
 companies to  be  80-85%)  and the non-recoverable material will be disposed of
 off-site at an approved  RCRA facility. The  recovery of contaminated  sludges
 will eliminate the risk of groundwater contamination from these  sludges.
 Cleaning and  repair of the concrete liner and installation of a  double liner
 on  top will provide the most protection against  leakage of the  contaminants
 into the groundwater.

      5.   Closed  Buried Sludge Pits - Place a drainage layer  on  top of the
 original liner.   Then cover with  a second synthetic liner (or comparable sub-
 stitute in compliance with the requirements  of RCRA), topsoil and  revegetate.
 The double synthetic cover will provide protection  against stormwater percolation
 and groundwater  contamination.

      6.   Former  PVC Storage Area  - Cover  and cap the entire  area with a  double
 synthetic (or comparable substitute in compliance with the requirements  of  RCRA)
 cap and revegetate.  The cap will protect the groundwater from  the leaching of
.the contaminants.

      7.   Groundwater - Install one line of six groundwater recovery wells at
 the northern edge of the plume, and another six  wells at the southern edge.
 Reuse the collected groundwater in Formosa's plant  and during the  low water
 demand at the plant dispose of the groundwater at the wastewater treatment
 plant.  Install  two monitoring wells at the  southern edge of the plume.  The
. recommended-recovery system will  collect  the contaminants and prevent the plume
 from'migrating further.

-------
                                      -29-
OPERATION AND MAINTENANCE

     Periodic inspection and maintenance will be required for all the liners
and the caps to assure that they are functioning properly.  Periodic inspection
and maintenance will also be necessary during operation of the recovery system.
The operator of the recovery system should have experience with a municipal
wellfield or contaminated groundwater pumping system or have demonstrated
experience in a groundwater related field.

     Proper maintenance of the groundwater treatment system will be required to
ensure compliance with the NPDES and the Clean Air Act.

     The groundwater monitoring program for the sources and recovery well
system will commence after installation of the liners, caps and the recovery
wells (est. 12 months).  Periodic analysis will evaluate the effectiveness of
the selected remedy.

EVALUATION OF ALTERNATIVES NOT SELECTED

     OFF-GRADE BATCH PITS AND RV POND

     The alternative that involved installation of a clay liner was not chosen,
because it may not be completely reliable due to the potential for cracking.

     The alternative that involved installation of a single synthetic liner
was not chosen, because it was less reliable than the double synthetic liner.
If the wastewater penetrates the single synthetic liner it would cause ground-
water contamination.  Overall, both the clay and single synthetic liners are
less reliable and environmentally effective than the double synthetic liner.

     The double liner is more reliable in preventing leakage than the clay or
single liner over time and represents a small increase in cost ($500,000 vs.
$460,000 and $450,000 for off-grade batch pits and $250,000 vs. $232,000 and
$227,000 for RV Pond).

     Both clay and single synthetic liners do not meet all public
health and environmental standards as defined by CERCLA.

UNLINED DITCHES
     The single synthetic liner was chosen over the concrete liner alternative.
The concrete liner was less environmentally effective than synthetic liner due
to the possibility of cracking.  The concrete liner was also more expensive than
the synthetic liner (5115,000 vs. $65,000).

The single synthetic liner meets all public health and environmental standards
as defined by CERCLA.

-------
AERAtEI)^ LAGOONS

     The alternative that involved cleaning and repair of the existing concrete
liner was not chosen, because it would still be sensitive to cracking and
erosion during its operation.  If the cracking occurs, it could cause further
groundwater contamination.

     The alternative that considered installation of a single synthetic liner
was not chosen because it was less reliable and environmentally less affective
than the double synthetic liner.

     The double synthetic liner is more reliable in preventing leakage than
single synthetic liner or concrete liner over time and represents a small
increase in cost ($425,000 vs. $343,000 and $278,000).

     Both the concrete and single synthetic liners do not meet all public
health and environmental standards as defined by CERCLA.

CLOSED BURIED SLUDGE PITS

     The alternative that involved keeping the existing cap was not chosen
because it was less environmentally effective than the double synthetic cap.
It did not meet all public health and environmental standards as defined by
CERCLA.

     Total excavation and removal of contaminated sludges was rejected, because
it offered comparable protection to the double synthetic cap, but was considerably
more expensive ($5,946,000 vs. $155,000).

FORMER PVC RESIN STORAGE AREA

     The alternative that involved excavation and removal of highest contamination
areas was not chosen, because the concentrations of contaminants left on-site
would cause- further degradation of the groundwater through leaching of the
contaminants.

     The alternative that involved capping the highest contamination areas
with synthetic liner was not chosen because the uncovered areas would also
cause further degradation of the groundwater.

     Capping the entire area with single synthetic liner was rejected because
it was less environmentally effective than the double synthetic cap.

     The double cap is more reliable than the single cap over time and represents
a small increase in cost  ($295,000 vs. $180,000).
       t.
     Furthermore, all three of the alternatives described above do not meet

-------
                                      -31-
all public-.health and environmental standards as defined by CERCLA.

GROUNDWATER

     Alternative No. 3 (i.e., 3 lines of recovery wells) was rejected, because
the only advantage it had over Alternative No. 2 (i.e., 2 lines of wells) was
that it would take a shorter time to clean-up the groundwater.  However, it was
more expensive while offering the same level of protection as Alternative No.
2 ($839,000 vs. $599,000).

     Both the plume management alternative and Alternative No. 5 were more
expensive and offered less protection than Alternative No. 2 ($1,720,000 and
$2,285,000 vs. $599,000).

     Plume management was also rejected because it allows for contamination
of the aquifer and natural "finishing" of the contaminants rather than "cleanup"
of the groundwater.

     Alternative No. 5 was rejected because it was determined that it would
not collect all of the contamination in the groundwater.

-------
                                                       STAUFFER" * :"—
                                                    J-N j.:
                  Site Of  rv
                nvttti
ion
                         &#;
 '••
f&?$
n
 \-
                                 <*\ nii
                                 •v-*-'. «• ^~.
                                                       /
^ i=L
                                                         '^
                                                       FORMOSA
                                                            /
                                    >
                                                       i/i
                                          /
                                                           ')V^vvC
          >•
       .10*
lucxf
srrE
LOCAT
STAUFFER CHE MIC A
Q • 1 Q v o r • .City
ROUX
ASSOCIATES
• • * . • ' * • . '
• . »* .. • i.»-^,- • . •„ - *
• • .-.-•_ :- '•'. ..•• - •>. '- •
• . • . • ,-..- .. . ,v .»
ION MAP lr
~+ — .' - . .
U COM^AMr,^^-
, Otl«««fj»-* ' * -,?;?:i?i:
a. oc MAnriNis ?*?"_, ««**-•.•-
•*••» c.notcRTsoM U*,"" I;
MWXCr -c* p
. IIOUX 4AM.IM1

-------
    STORAGE
             vc».
       CD  STORAGE
       CD
REACTOR
BUILDING
PVC MANUFACTURING
       FACILITY
                J
, 	
r 	 1 i
FORMER PVC
RESIN
STORAGE
AREA
1
L J
! 1 1 1 i
|S34
L 	 J
OILAWAMf CITY fIC StTI
ftlMIOIAk ACTION r«A«IBILITV •
SITE PLAN




— i
> i
i
j 1
: 1
i
i
i
5 i
8 1 STORAGE
i I
Pea
FIRE WATER
RESERVOIR
O
Ul _
11
WASTE
TREATMENT
BUILDING
M coi
BAfi
COC
TOV
it", f: >
' *> OFF GRADE
LAGOON
1
in-
1ATCH
PITS
LAGOON (EARTHEN
LAGOON)
          COOLINQ
          TOWER
    REACTOR
    BUILDINQ
                          STORM
                          WATER
                        RESERVOIR
                        (HV POND)
                                        REACTOR
                                      UNLINEO
                                      DITCH
REACTOR
BUILDING
                                                    (01E2
     CONCRETE
     BASIN
     COOLINQ
     TOW^R
                                                       SCALE
                                                              200

-------
120 —
     ISO
5

-------
      LEGEND

         OBSERVATION WELL
         TEST BORING
  •      DOMESTIC WELLS
  0      GETTY WELL
A»—
-------
                                    .TABLE 1
                 ANALYSIS OF DELAWARE CITY OBSERVATION WELLS FOR
                              VCM, EDC, AND TCE
                  SAMPLES COLLECTED AUGUST 21 - AUGUST 23, 1984
                   SAMPLES ANALYZED AUGUST 24 - AUGUST 31, 1984
 Sample

 OW-3
 OW-5
 OW-10
 OW-11

 OW-13
 OW-14
 OW-16
 OW-17
 OW-17A2)
 ow-ia
 OW-19
 OW-22
 OW-28
(2)
(2)
(2)
Concentration (ppb)
VCM
ND(3)
310
Det
250
EDC
Det(4)
1,600
230
40
TCE
ND
13
4
4
Other O
ND
ND
One at
Three a
 OW-29
 OW-30
 OW-31
.OW-32* '
 OW-3 3
 Lower Limit of
 Detection
 O.A spikes at 10 ppb
 (Average  percentage
 recovery  from duplicate
 analysis)
ND
ND
ND
210
ND
ND
ND
ND
ND
ND
 50
ND
ND
ND
  1

105%
ND
ND
ND
3,400
Det
ND
ND
ND
ND
ND
1,100
ND
ND
ND
1
4
9
Det
15
Det
ND
ND
ND
15
.ND
Det
7
ND
ND
1
                                93%
94%
               50, and 25 ppb
               ND
               ND
               ND
               One at 3,400 ppb
               ND
               ND
               ND
               ND
               ND
               ND
               ND
               ND
               ND
               ND
               LO
 Notes:

      1.

      2.
      3.
      4.
     Modified version of EPA Method 624 (Purge and trap gas
     ch.omatography with flame ionization detection).
     Saaple split with EPA's contractor, NUS.
     Nil - Not detected.
     Det - Detected below the lower limit of cjuantitation, 3 ppb.
                                        14

-------
                                  _TABLE Z

                  ANALYSIS OF DELAWARE CITY OBSERVATION WELLS FOR
                              VCM, EDC AND TCE U
              SAMPLES COLLECTED DECEMBER 19 - DECEMBER  20,  1984
                SAMPLES ANALYZED DECEMBER 27- DECEMBER  31,  1984
                                        	Concentration  (ppb)
Sample

OW-3
^7-3 (duplicate)
OW-5
OW-11 (Top)
      (Middle)
      (Bottom)
OW-12
CW-15
OW-16
OW-20
OW-21
OW-30
OW-31
OW-3 2
Detection Limit
Q.A. Spikes at 10 ppb and 100 ppb
 (Average % Recovery)
VCM
200
210
1,500
2,600
2,600
2,500
1,400
6°(2)
no1 '
ND
ND
100
ND
ND
1
115%
EDC
2,000
2,100
'14,000
31
36
31
27,000
2S,ooo(3,
ND
ND
2,600
ND
ND
1
106%
TCS
5.7
5.9
21
22
22
21
25
14
Det
ND
8.3
4.7
4.1
ND
1
115%
Notes:
     1.   Modified version of EPA Method  624  (Purge  and  trap  gas
          chromatography with flame ionization  detection).
     2.   ND - Not Detected.
     3.   Det - Detected below the lower  limit  of  quantitation,  3  ppb.
                                       15

-------
                                           0'
          O     O
               PAM KlN«

                    AMCA
                                     OFFICE
                                        SOILf ft
                                         •tea
                     17   l«    IS
                    A   A    A
                    *
                  A"   A'°   V
                       .21
                  I*
                                            f\ ne WAT in  !
                                             MOEKVOI*  |
 100      20O
rccr
   Location of Test Pft
                              22
                                     TTOI
LOCATIONS OF
  TEST  PITS
                                      CMMIO tQ*
                                        Stauffer  8 Formosa  Plastics
                                                               SCMI
                                                               SHOWN
                                                               OATI
                                                               JAN I9M
                            4
                                                                   FIG. 5

-------
DELAWARE CITY SOIL ANALYSIS
SAMPLES COLLECTED 10/23/84
SAMPLES ANALYZED 10/29/84 - 11/02/84
Depth
( inches )
12
54
36
36
84
12
24
12
24
12
12
30
52
42
32
16
74
53
10
32
7
49
4
48
12
36
Concentration (ppm)
Description
/ •
Soil and white powder
Blackish residue
Soil and white powder
Brown virgin soil
Brown virgin soil
Soil and white powder
Brown virgin soil
Soil and white powder
Brown virgin soil
Brown soil
Soil and white powder
Brown virgin soil
Brown virgin soil
Fine white powder
White slimy clay
White powder
Brown virgin soil
Red soil, strong odor
Soil and white powder
Brown virgin soil
Soil and white powder
Red soil/sand
White powder
Red soil/sand
Red soil
Red soil
VCM
-J »ro(3)
Det
ND
ND
ND
ND
. ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND.
ND:
ND
ND
ND
' KD
ND
ND
ND
EDC
. ND
' 27
14
ND
ND
18
ND
22
ND
ND
14
ND
ND
120
63
24
ND
ND
ND
ND
ND
ND
. D_et
ND
ND
ND
TCE
ND
Det
Det
ND
ND
20
ND
ND
210
ND
Det
Det
ND
150
Det
. ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
             Sample
               No.

               1
               2

 TP-10         1
 TP-10         2
 TP-10         3

 TP-11         1
 TP-11         2
   ./
 TP-12         1
 TP-12         2
 TP-12         3

 TP-13         1
 TP-13         2
 TP-13         3

 TP-14         1
 TP-14         2
 TP-14         3
 TP-14         4

 TP-15         1  '
 TP-15         2
 TP-15         3

•TP-16         1
 TP-16         2

 TP-17         1
 TP-17         2

 TP-18         1
 "TP-18         2

 Notes:                                         ,
       1.    Modified version of EPA Method 624  (Dispersion of  soil  in
             tetraglyme followed by purge and trap gas chromatography with
             flame ionization detection).
       2.    .White powder and white slimy clay have been identified  as  PVC
             resin.  As shown in Appendix C, this material is typically present
             as a thin layer approximately 6 to  12 inches thick within  the  top
             2 feet of the surface.
       3.    ND indicates less than 4 ppm (detection  limit).
       4.   .Det indicates less than 12 ppm  (lower limit of quantitation).
                                       23

-------
                                   TABLE

                         DELAWARE CITY; SOIL  ANALYSIS
                            SAMPLES COLLECTED  11/29/84
                       SAMPLES ANALYZED 12/17/84  -  12/26/84
Test
Pit No.
TP-19
TP-19
TP-19
TP-19
TP-20
TB-20
TP-20
TP-20
TP-21
TP-21
TP-21
TP-21
TP-22
TP-22
TP-22
TP-22
Sample
No.
1
2
3
4
-x^_
1
2
3
4
1
2
3
4
1
2
3
4
                        Depth
                         (inches)    Description
                            18
                        Brown virgin soil
                           48
                           48
                            36
                        Brown soil with
                        traces of white
                        soil
                        Brown soil, no
                        visible powder
                        Brown virgin soil
Concentration (ppm)
VCM
ND
ND
ND
ND
ND(2)
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
£DC
ND
ND
ND
ND
ND
ND
Det
ND
ND
ND
ND
ND
ND
ND
ND
ND
TCS
ND
ND
ND
ND
ND
.. ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
ND
Notes:
      2.
      3.
Modified version of EPA Method 624  (Disperson of soil in
tetraglyme followed by purge and trap gas chromatography with
flame ionization detection).
ND indicates less than 2 ppm (detection limit)
Dec indicates less than 6 ppm  (lower limit of quantitation)
                                       24

-------
                        |'-0" CLAY
          CO
       >
       r
•n

O
             > •
             r r
               h
O   OH
r-   * »
i   :J

C9   * A


?   h
CA   2
z   5
                                                                               LINER



                                                                             6EOTEXTILE
                                                          l'-0" SAND/GRAVEL



                                                       LEAK DETECTION

-------
•n

0
                                      LINER
ui
                          SYNTHETIC LINED DITCH

                                (TYPICAL)
  8
     df
-      "
H2  -4 R «
•"» •  — •«
O
>
cich
z  z : :
ni  m • «
o  D ? °

S  °
H
O
X
SITf
ITT STUDY
TCH
                        CONCRETE  LINED  DITCH

                             (TYPICAL)
                                                                 COVER
                                                — GEOTEXTILE
                                                  GRATING


-------
>
              •fHtOIAL
                  I *«0 It l^« •••«•!
                  lOfMTtrtCP  »LJi«B
                           FIG. 3

-------
   LEGEND
> — EXISTING
   WATER LINK

   DOMESTIC
   SUPPLY WELL

   EXISTING
   MONITORING WELL
   PROJECTED
   ' PATH OP PLUME

 •- EXISTING PLUME
   (8/84 DATA)

   PROPOSED
   MONITORING WELL
   EXPECTED
   GROUNOWATER
   DISCHARGE LOCATIONS
112
    OCLAWANI CITY PVC SITt
MIUIOIAk ACTION 'LASIIIUTY STUOT
     ALTERNATIVE Hi
   PLUME MANAGEMENT

                       CIR

-------
                                                                   Tnhlo  r>
                                                            DELAWARE CITY  PVC SITE
Source Alternative
Area Description
j Off-grade A) Excavate, remove sludges,
Pits Batch provide double synthetic
liner
B) Excavate, remove sludges,
provide single synthetic
liner
C) Excavate, remove sludges
i
>\ RV Pond A) Excavate, remove sludges,
provide double synthetic
liner
B) Excavate, remove sludges,
provide single synthetic
liner
C) Excavate, remove sludges,
provide clay liner
l\ Unlined. A) Excavate PVC sludge, pro-
Ditches vide synthetic liner
B) Excavate PVC sludge, pro-
vide concrete trench
C) Install concrete trench
(no contamination removed)
Remedial Action
Present Worth Costs
(Recovery of the
sludge and dis-
posal at RCRA
facility) (I)
$ 500,000
450,000*
460,000*
250,000
227,000*
232,000*
87,000
Alternatives
Present Worth Costs Present Worth Costs
(Disposal at municl- (Disposal at RCRA
pal landfill) (II) landfill) (III)
$ 455,000 $1,440,000
405,000 1,310,000
415,000 1,320,000
208,000 578,000
185,000 570,000
190,000 575,000
45,000 65,000
90,000 115,000
87,000 87,000
| ..
* Afl r":.  .nfnd  hv KPA

-------
                                                            DF.L
                                                                   Table 5 (rout i nno
-------
                                                                Tnhlf *j (ronl iniii-il)

                                                         DELAWARE CITY I'VC S1TK
                                                      Remedial Action Alternative
Source
Area
           Alternative
           Description

 C)    Cap  (double  synthetic mem-
      brane)  entire  area,  cover,
      revegetate entire  area
      (no  contamination  removed)

 D)    Excavate, remove contami-
      nated materials, regrade
      cover,  revegetate  entire
      area
Present Worth Costs
(Recovery of the
sludge and dis-
posal at RCRA
facility) (I)

   295,000
Present Worth Costs
(Disposal at munici-
pal landfill) (II)

    295,000
Present Worth Costs
(Disposal at RCRA
landfill) (III)

     295,000
                                                                            65,000
                                                            143,000
Groundwater  A)
             B)
             C)

             D)
           Description

      Downgradient  pumpage  to
      collect  ground  water  at the
      edge  of  the existing  plume
      in  the buried Valley
      (includes  monitoring)

      Downgradient  and  within
      plume pumpage to  collect
      all contaminated  ground-
      water (includes monitor-
      ing)

      Plume management

      Delaware DNREC  Remedial
      Alternative
                                                       Present Worth Costs
            $  590,000
               830,000
             1,720,000

             2,285,000
* As est
>d  by  EPA

-------

Table 6


DELAWARE CITY PVC SITE
1)
2)
3)
4)
5)
6)
7)
. -• RECOMMENDED
Source/Alternative
Off-grade Batch Pits
(Alternative 01-A-I)
RV Pond
(Alternative //2-A-I)
Unlined Ditches
(Alternative 03-A-III)
Aerated Lagoons
(Alternative //4-C-I)
Closed Buried Sludge Pits
(Alternative #5-C-I)
Former PVC Storage Area
(Alternative #6-C-I)
Groundwater
(Alternative #7-A)
REMEDIAL ALTERNATIVES
Capital
Cost($)* 0/M.($/Yr.)*
$450,000 $5,300
$237,000 $1,400
S 55,000 $1,100
$407,000 $2,000
$139,000 $1,700
$281,000 . $1,500
$335,000 $30,000
Present
Worth(S)
$500,000
$250,000
S 65,000
$425, Of*
$155,00.
$295,000
$590,000
    TOTAL                         $1,904,000          $43,000          $2,280,000
*as estimated by EPA

-------
                          RESPONSIVENESS SUMMARY
                          DELAWARE CITY PVC SITE
                       NEW CASTLE COUNTY, DELAWARE
                              SEPTEMBER 1986
     This community relations responsiveness summary is divided into
the following sections:

   Section I:   Overview - A discussion of EPA involvement at the site
                and a description of the EPA's preferred remedial
                action alternative.
   Section II:
Summary of Public Ccnroents Received During the Public
Comment Period and Agency Responses - A summary of comments
categorized by topic and followed by EPA responses.
   Section III: Remaining Concerns - A description of remaining community
                concerns that EPA and the Delaware Department of Natural
                Resources and Environmental Control should consider in
                conducting the remedial design and remedial actions at the
                site.

     In addition to the above sections, a list of EPA community relations
activities conducted at the Delaware City PVC site is included as Attachment
A of this responsiveness summary.

-------
                                   -  2'-
I. Overview

   In  1983, the Delaware City  PVC site was  included on  the National
   Priorities List  (NPL).

   In May, 1984, EPA and the Delaware Department of Natural Resources and
   Environmental Control (DNREC) entered into a Consent Order with
   Stauffer and Formosa to perform a Feasibility Study  (FS) for the site
   and to implement the Approved Remedial Action.  The FS evaluated 18
   alternatives for remediating the six identified sources of contamination
   and four alternatives for groundwater remediation.

   Comrtunity interest and involvement during the time between the signing
•^  of the consent order and the opening of the conment period on the
   preferred alternative were  very limited.

   The FS was released to the  public for review and comment on July 27,
   1986.  This marked the opening of the comment period, which extended
   until September 3, 1986.  During the comment period, the EPA and the
   DNREC recommended preferred remedial alternatives for the six
   contamination sources as well as for groundwater remediation.

   The alternatives are described in detail in Section 5.0 of the FS
   Report.  In summary, the EPA's and DNREC's recommended alternatives
   for the six contamination sources and groundwater are as follows:

   Description of the Selected Remedy;

   1. Off-grade Batch Pits - Excavate and remove existing polyvinyl
      chloride (P\*3) sludge and contaminated soils to the levels to be
      determined at the design stage; install a double synthetic liner,
      install monitoring "wells and perform quarterly sample analysis
      for•trichloroethylene (TCE), 1,2, dichloroethane (EDC) and vinyl
      chloride monomer (\£M),  the contaminants of concern at the site.
      The excavated material will be directly processed and recovered
      as a saleable finished product to the maximum extent possible.
      Non-recoverable material will be disposed of off-site at an
      approved RCRA facility (est. 1 year).

   2. Stormwater Reservoir (RV Pond) - The same remedy as described for
      the above off-grade batch pits (est. 1 year).

   3. Unlined Ditches - Excavate and remove P\C sludge, install a single
      synthetic liner.  The excavated material will be disposed of off-
      site at an approved RCRA facility (est. 8 months).

   4. Aerated Lagoons - Excavate and remove PVC sludge, clean and repair
      lagoons as necessary, install a double synthetic liner, install
      monitoring wells and perform quarterly sampling analysis for TCE,
      EDC and VCM.  The excavated material will be recovered to the
      maximum extent possible  and non-recoverable material will be
      disposed of off-site at  an approved RCRA facility (est 18 months).

-------
                                    - 3'-
     S.^Closed Buried Sludge Pits - Place a drainage layer on top of the
        existing synthetic cap, and cover with a second synthetic cap
        (or conparable substitute in compliance with the requirements of
        RCRA) and topsoil and then revegetate (est. 1 year).

     6.  Former PVC Storage Area - Cover and cap the entire area with a
        double synthetic cap (or comparable substitute in compliance with
        the requirements of RCRA) and then revegetate (est. 6 months).

     7.  Groundwater - Install a line of six groundwater recovery wells at
        the northern edge of the contaminant plume, and- another six wells
        at the southern edge.  Reuse the collected groundwater in Formosa's
        plant operations.  During periods of low water demand in the plant,
        treat the groundwater in the existing waste water treatment plant.
        Install two monitoring wells at the southern edge of the plume.
        Provide an alternate water supply for existing contaminated wells.

     8.  Operation and maintenance (O&M) for the remedy will include as a
        minimum, regular inspections and, as necessary, repairs to the
        liners and caps.  The groundwater recovery system will be routinely
        monitored to assure that it is capturing the contaminated plume.


II.   Summary of Public Comments Received During the Public Comment Period
     and Agency Responses
     Comments raised during the Delaware City P\C site public comment
     period are summarized briefly below.  The comments received during
     the comment period, July 27 to September 3, 1986, are categorized by
     relevant topics.

     Remedial Alternative Preferences

     1.  One ccmmentor suggested that EPA and DNREC should consider an
        alternative which would completely remove all of the contaminants
        and dispose of them in a separate landfill or appropriate facility.
        This same ccmmentor was concerned about the preferred alternative
        leaving contaminants in place for future generations.

        EPA Response - High cost and dwindling landfill space makes land-
        filling of all contaminated material undesireable when similar
        environmental results can be achieved by the techniques described.
        However, EPA will consider total removal before signing the ROD.

     2.  A suggestion was made to create a common hazardous waste treatment
        plant or disposal facility for all of the sites in the Delaware
        City. area.

        EPA Response - DNREC answered that at this time, private industry
        has not indicated an interest in building such a plant.

-------
                               - 4 --
Technical Questions/Concerns Regarding Remedial Alternatives

1. One conmentor questioned whether there  is an existing market for
   refined PVt: sludge.

   EPA Response - Formosa Plastics Corporation is currently recovering
   PVC sludge from the lagoons on site, rather than disposing the
   sludge as a waste.

2. Vtao has the final selection authority?

   EPA Response - After considering all relevant comments, EPA will
   decide which option is most environmentally sound and economically
   feasible.

3. A question was raised regarding the time frame for cleanup at the
   site.

   EPA Response - Following the close of the public ccnment period, EPA
   will prepare a formal Record of Decision (ROD) identifying the
   recommended alternative.  Subject to the conditions in the Consent
   Order, the responsible parties will have 30 days to begin implemen-
   tation of the preferred alternative.

4. One ccmmentor asked what would be left behind after the remedial
   cleanup is completed.

   EPA Response - Under the preferred alternative, all PVC sludge
   will be excavated and removed from four of the six contamination
   sources, including the off-grade batch pits, RV pond, unlined
   ditches and aerated lagoons.  The excavated material will be
   directly processed and recovered as a saleable finished product
   to the maximum extent possible.  Non-recoverable material will be
   disposed of off-site at an approved RCRA facility.  Synthetic
   liners will also be installed.  The closed buried sludge pits will
   be covered with a RCRA type cap, and revegetated.  The former P^
   storage area will be capped with a RCRA type cap and revegetated.

5. Another conmentor questioned what would be done to alleviate
   groundwater contamination.

   EPA Response - Under the preferred alternative, the remedial action
   would include installing one line of six wells at the northern
   edge of the contaninant plume, and another six wells at the southern
   edge.  The collected groundwater would be reused in Formosa's
   plant operations.  During periods of low water demand in the plant,
   the groundwater would be treated in the existing waste water
   treatment plant.  TWo monitoring wells would be installed at the
   southern edge of the plume and an alternate water supply would be
   provided for existing contaminated wells.

-------
6. One. ccmmentor asked how much PVC sludge was estijTiated to be in
   'the lagoons.

   EPA Response - According to the Feasibility Study, there are
   approximately 84 tons of PVC sludge contained in the lagoons on
   site.

7. Formosa Plastics Company conmented that it was in agreement with
   EPA's and DNREC's concept of excavation of sludges and engineering
   controls to eliminate future contamination, however, it disagreed
   with EPA's and DNREC's requirement for disposal of excavated
   material as a hazardous waste.

   EPA Response - It is EPA's policy that all CERCLA-designated
   hazardous substances be disposed of at a facility in compliance
   with all requirements of RCPA.  In fact, the agency interprets
   CERCLA as requiring their disposal at a RCRA facility.

8. Stauffer Chemical Company commented that it agreed with EPA's and
   DNREC's preferred alternative for remediation of the groundwater,
   however it disagreed with EPA's and DNREC's requirement that the
   closed buried sludge pits and the former PVC storage areas be
   capped with a double synthetic nenbrane cover because it is not
   cost effective.  In the alternative, Stauffer commented that
   consideration should be given to the use of a soil member having
   equivilent permeability characteristics as one of the two synthetic
   membrane members proposed.
                                          •
   EPA Response - EPA believes that the double synthetic membrane cover
   is far more environmentally effective and reliable than a single
   synthetic cap.  Given this additional protection and the fact that
   EPA does not believe that the cost for this alternative far exceeds
   the cost of a single synthetic cover, EPA believes that the preferred
   alternative represents a cost-effective remedy for these sources.
   EPA will consider the use of a soil membrane having equivalent
   permeability characteristics as the synthetic membrane proposed.
Public Health/Environmental Concerns

1. A question was raised concerning how the EPA and the DNREC can
   justify leaving carcinogenic materials at the site.

   EPA Response - EPA explained that the major threat to the public
   exists from migration of the groundwater plume toward receptors.
   The recovery wells will interest and collect the contaminated
   groundwater before it reaches the downgradient users.  The RCRA
   caps and liners proposed will prevent further contamination of
   the groundwater by stopping leaching of these contaninants into
   the groundwater.

-------
                                    - 6 -
     Other Issues

     1. One corunentor asked  if the Stauffer Chemical Company had commented
        on the preferred remedial alternative.

        EPA Response - Yes,  the comments received fron the StaufEer Chemical
        Company are described in this document.

     2. A question was raised concerning the Consent Order - is there any
        clause in the order  that prevents Formosa from selling its land
        holdings, which in turn may ccnprcmise the cap and recovery wells?

        EPA Response - Deed  restrictions would prevent this.


III. Remaining Concerns

     Issues and concerns expressed during the comment period that the EPA
     was unable to address during remedial planning activities include:

     1. Concern was raised about the financial security of Formosa Plastics
        Corporation and their ability to make assurances that the remedial
        actions will be carried out to completion and repaired as necessary.

     2. Concern remained over how much of the PVC sludge could be recoverable.
        (It is estimated by  Formosa to be 80-85%)

     3. The liability of both ccnpanies (Formosa and Stauffer) was raised
        as a point of concern.  One ccmmentpr recommended that the companies
        should post bonds to ensure their liability.

-------
                               Attachment A
                 Community Relations Activities Conducted
                      at tin«» Delaware City PVC Site
0  A press release announced that public conrnents would be accepted on
   the administrative consent order, May 1984.

0  A press release announced the extension of the comment period on the
   consent order, July 1984.

0  The completion of the Feasibility Study, its availability at local
   repositories and the opening of the public comment period on the
   proposed cleanup alternatives were announced in a press release,
   July 1986.

0  A fact sheet identifying the preferred remedial alternatives was
   prepared,  August 1986.

0  An informal meeting was held on August 27, 1986 to answer questions
   and accept comments on  the proposed cleanup.

-------