Environmental l*rotaction
Agency
Emergency and
Remedial Response
August 1984
Superfund
Record of Decision:
Wade Site,  PA

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
1. REPORT NO.
  EPA/ROD/R03-84/009
                              2.
                                                            I. RECIPIENT'S ACCESSION NO. • f
4. TITLE AND SUBTITLE
 SUPERFUND RECORD OF DECISION:
 Wade Site  (ABM),  PA
             5. REPORT DATE
              08/30/84
             6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
                                                           8. PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
                                                            10. PROGRAM ELEMENT NO.
                                                            11. CONTRACT/GRANT NO.
12. SPONSORING AGENCY NAME AND ADDRESS
 U.S. Environmental Protection Agency
 401 M Street,  S.W.
 Washington, D.C.     20460
             13. TYPE OF REPORT AND PERIOD COVERED
               Final ROD Report	
             14. SPONSORING AGENCY CODE

                800/00
15. SUPPLEMENTARY NOTES
16. ABSTRACT
      The Wade site is a three acre  parcel of land on the banks of the Delaware
River.   It is located nine miles  south of Philadelphia in Chester, Pennsylvania.  From
approximately 1950 until the early 1970's the site was the  location of a rubber re-
cycling  facility which shredded tires  and other post-consumer rubber products.  During
the early 1970's the site was converted to an illegal industrial waste storage and
disposal facility.  Drums of waste were emptied either directly onto the ground or
trenches,  severely contaminating soil and the ground water.   Approximately 150,000
gallons  of waste chemicals remain on-site.
      The recommended alternative selected for this site consists of:  removal,
decontamination and disposal of on-site tires and tankers,  removal of on-site waste
piles; demolishing buildings, leveling the site, and filling and grading the property
up to 12 inches over the existing grade to cover any protruding subsurface structures
which have not been removed; removal down to the depth at which the first acceptably
contaminated sample was found  (based on a contamination cutoff level recommended by the
RI/FS contractor); and covering the  site with top-soil and  seeding the cap to
minimize erosion.
      Key Words:  Compliance with Environmental Laws, Negotiations, Capping,
                   Excavation, Ground Water, Cost Recovery,  Potential Responsible
                   Parties
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.lDENTIFIERS/OPEN ENDED TERMS
                           c. COSATi Field/Group
 Record of Decision:
 Wade Site  (ABM),  PA
 Contaminated media:   gw, soil, air
 Key contaminants:  over 100 organics, metal
     and inorganics
18. DISTRIBUTION STATEMENT
19. SECURITY CLASS (This Report/
  None
21. NO. OF PAGES
    30
                                               20. SECURITY CLASS (This page)
                                                 None
                                                                          22. PRICE

EPA Form 2220-1 (R««. 4-77)    PREVIOUS EDITION is OBSOLETE

-------
                                                        INSTRUCTIONS

    1.   REPORT NUMBER
        Insert the LPA report number as it appears on the cover of the publication.

    2.   LEAVE BLANK

    3.   RECIPIENTS ACCESSION NUMBER
        Reserved for use by each report recipient.

    4.   TITLE AND SUBTITLE
        Title should indicate clearly and briefly the subject coverage of the report, and be displayed prominently.  Set subtitle, it' used, in imialicr
        type or otherwise subordinate it to main title. When a report is prepared in more than one volume, rerwat the primary title, aild volume
        number and include subtitle for the specific title.
   6.   REPORT DATE
        Each
        approva*
^•^ • mrr* • ^
report shall carry a date indicating at least month and year. Indicate the basis  on which it wa> selected If.?.. Jan- ofisuie. Jaic of
nal. date of preparation, etc.}.
   6.   PERFORMING ORGANIZATION CODE
        Leave blank.

   7.   AUTHOR (S)
        Give name(s) in conventional order (John R. Doe. J. Robert Dot. cH\). List author's affiliation if it differs from the pcrl'onnini: ,.ijiam-
        zation.

   8.   PERFORMING ORGANIZATION REPORT NUMBER
        insert if performing organization wishes to assign this number.

   9.   PERFORMING ORGANIZATION NAME AND ADDRESS
        Give name, street, city, state, and ZIP code.  List no more than two levels of an organisational hircarcliy.

   10.  PROGRAM ELEMENT NUMBER
        Use the program element number under which the report was prepared. Subordinate numbers may be included in parentheses.

   11.  CONTRACT/GRANT NUMBER
        Insert contract or grant number under which report was prepared.

   12.  SPONSORING AGENCY NAME AND ADDRESS
        Include ZIP code.

   13.  TYPE OF REPORT AND PERIOD COVERED
        Indicate interim final, etc., and if applicable, dates covered.

   14.  SPONSORING AGbNCY CODE
        Insert appropriate code.

   16.  SUPPLEMENTARY NOTES
        Enter information not included elsewhere but useful, such as: Prepared in cooperation with. Translation nf. I'rcsciitcil at owlcirmc of.
        To be published in. Supersedes, Supplements, etc.

   16.  ABSTRACT
        Include a brief (200 words or lessj factual summary of the most significant informal ion contained in the report. II Hie rq«ni unilanis j
        significant bibliography or literature survey, mention it here.

   17.  KEY WORDS AND DOCUMENT ANALYSIS
        (a) DESCRIPTORS - Select from the Thesaurus of Lnginecrir.^ and Scientific Terms the proper aulli«ri/cd terms llial identity the major
        concept of the research and are sufficiently specific and precise to be used us  index entries tor calalopn^.

        (b) IDENTIFIERS AND OPEN-ENDED TERMS - Use identifiers for project nanux, code names, equipment designators, etc. Use open-
        ended terms written in descriptor form for those subjects for which no descriptor exists.

        (c) COSATIMELD GROUP -1 icld and group assignments are to be taken from the 1965 (OSAT I Subject ( aicpory List. Since the ma-
        jority of documents are muUidisciplinary in nature, the Primary Held/Group assignmcnt(s) will be spevilic discipline, urea <>l lumurt
        endeavor, or type of physical object. The application(s) will be cross-referenced with secondary I icid/(iroiip assignments that will lollnu
        the primary posting(s).

   18.  DISTRIBUTION STATEMENT
        Denote releasability to the public or limitation for reasons other than security for example "Release (Inliniiictl."  f iu- any availability to
        the public, with address and price.

   19. & 20. SECURITY CLASSIFICATION
        DO NOT submit classified reports to the National Technical Information service.

   21.  NUMBER OF PAGES
        Insert the total number of pages, including this one and unnumbered pages, but exclude distribution list, il any.

   22.  PRICE
        Insert the price set by the National Technical Information Service or the Government Printing Office, il  known.
EPA Form 2220-1 (Rev. 4-77) (R.v.rt.)

-------
                ENFORCEMENT DECISION DOCUMENT
                REMEDIAL ALTERNATIVE SELECTION

Site:  Wade
       Chester, Pennsylvania

Documen.ts Reviewed

     I am basing my decision on the following documents
describing the analysis of the cost and effectiveness of
remedial alternatives for the Wade Site:

  - Focused Feasibility Study, Wade Site, Chester,
    Pennsylvania, Metcalf & Eddy, Inc., April 1984.

  - Draft Report, Result of Soil Analysis and Cost
    Estimates for selected Remedial Activities regarding
    the Wade Hazardous Waste Site in Chester, PA,
    Roy F. Weston, November 1983.

  - Summary of Remedial Alternatives Selection

  - Public Comments and Recommendations

  - Responsiveness Summary

Description of Selected Remedy

  - remove and dispose of tires and tankers

  - remove on-site waste piles

  - demolish buildings

  - test contents, remove contents, and close two underground
    storage tanks

     The building on this site will be demolished and the
remaining slabs will be left on site for future use.  All
demolition rubble will remain on the property and used for
fill material.

  - level debris, fill and grade property

  - remove and dispose of contaminated soil

     The purpose of this activity is to remove from the property
any contaminated material and any material that will.hinder
subsequent efforts to fill and grade the site.

  - cover with topsoil and seed cap

  - operation and maintenance of site

-------
                             -2-
Declarations

     Consistent with the Comprehensive Environmental Response
Compensation and Liability Act of 1980 (CERCLA) and the
National Contingency Plan (40 CFR Part 300), I have deter-
mined the removal, decontamination and disposal of tankers,
tires and debris; destruction of buildings, leveling, filling
and grading the site; and covering with a seeded topsoil cap
at the Wade site is the least costly alternative of all the
remedial options reviewed that provides for current and future
protection of public health, welfare and the environment.
The State of Pennsylvania has been consulted and agrees with
the approved remedy,  in addition, the action will require
future operation and maintenance activities to ensure the
continued effectiveness of the remedy.  Settlements have
been reached between EPA and the responsible parties based
on the selected remedy.

     I have also determined that the action being taken which
includes the off-site transport of contaminated materials to a
RCRA approved lined facility is the least costly alternative
when compared to the other remedial options reviewed, and is
necessary to protect public health, welfare, or the environment,
   / Date
    M. Thomas
Assistant Administrator
Office of Solid Waste and
  Emergency Response

-------
a tSf^J »        UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                            WASHINGTON, D.C. 20460
                                                             OFFICE OF
                                                    SOLID WASTE AV-EMERGENCY RESPONSE
                                 3  I98A
     MEMORANDUM

     SUBJECT:  Enforcement  Decision  Document  Approval for the
               Remedial Action  at  the Wade  Site,  Chester, Pennsylvania

     FROM:     Gene A. Lucero,  Director  O$tl^ n>
               Office of Waste  Programs  Enforcement

     TO:       Lee M. Thomas
               Assistant Administrator

          This Office has reviewed the Enforcement Decision Document

     and the Focused Feasibility Study for  the Wade Site.  I recommend

     that you approve the recommended alternative which will provide

     for future protection  of public health,  welfare, and the

     environment.

-------

           UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                       WASHINGTON. D.C. 20460
                        JUL 30 1984             SOLID WASTE AND EMERGENCY RESPONSE
                        OUL
MEMORANDUM

SUBJECT:  Enforcement Decision Memorandum for Approval of
          Remedial Action at  the  Wade  S|te,/Chester,  Pennsylvania

FROM:     Russel H. Wyer, Director
          Hazardous Site Control  Di^Tsiofe (WH-548E)

TO:       Gene A. Lucero, Director
          Office of Waste Programs  Enforcement (WH-527)


     The Enforcement Decision Memorandum  and the Focused Feasibility

Study for the Wade Site has been  reviewed by my staff.


                              I Concur
                               I  Do  Not  Concur
                               I  Concur  with Comment

-------
     I UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                     WASHINGTON. D.C. 20460
                         AU6   11984
                                                         OFFICE OF
                                                       ENFORCEMENT AND
                                                     COMPLIANCE MONITORING
MEMORANDUM
SUBJECT:  Enforcement Decision Memorandum  for  Approval of
          Remedial Action at  the Wade  Site,  Chester,  Pennsylvania
FROM:     Frederick F. Stiehl   	f	
          Acting Associate Enforcement  Counsel
            for Waste  (LE-134S)

TO:       Gene A. Lucero, Director
          Office of Waste Programs Enforcement  (WH-527)
     The Enforcement Decision Memorandum and the Focused

Feasibility Study for the Wade site has  been reviewed by my

staff.

                      I Concur  	

                      I Do Not Concur
                       1 Concur with  Comment

-------
            Summary of Remedial Alternative Selection
                          Wade Site
                    Chester, Pennsylvania


Site Location, Description and History

     The Wade site is a three acre parcel located on the
banks of the Delaware River, just nine miles south of the
City of Philadelphia, in Chester, Pennsylvania.  The site is
located in the industrial portion of Chester and is two
blocks from the residential portion of the City.  The site
is bounded by the Commodore Barry Bridge, the Delaware
River, a railroad right-of-way, and property owned by the
Philadelphia Electric Company.  From approximately 1950
until the early 1970's, the site was the location
of the Eastern Rubber Recycling Company, a firm which
shredded tires and other post-consumer rubber products.
This use was abandoned during the 1970's and the site was
converted to an illegal industrial waste storage and disposal
facility.  Drums of wastes were emptied either directly onto
the ground or into trenches, thus severely contaminating soil
at several locations, as well as jeopardizing the ground water
beneath the site.  In February 1978, a fire broke out which
was so severe that the Commodore Barry Bridge was closed for
6 hours and 45 firemen required examination at the local
hospital.  As a result of the fire, one of the site buildings
was completely destroyed and two others were seriously damaged.
Large piles of debris containing exploded drums, building
materials, tires, and shredded rubber (from the rubber re-
cycling operations), and chemically-contaminated earth littered
the property.  Approximately 150,000 gallons of waste chemicals
remained after the fire; most of the material was contained
in 2,500 55-gallon drums located inside the fire damaged
buildings, although a large portion was stored in 5 bulk
tankers in the front lot.

     In 1980 and 1981, contractors were engaged by the
Pennsylvania Department of Environmental Resources (DER) and
the U.S. EPA to remove and dispose of the drums (and their
contents) contained in the buildings, to remove and dispose
of the contents of the tankers, and to perform an investigation
of the site's soil, ground water, and air quality.  WESTON
personnel served as the DER Site Representative for the
day-to-day monitoring of Contractor activities.

-------
                             -2-
     Subsequent to the above on-site activities, CECOS was
engaged by the DER in the summer of 1983 to investigate and
characterize the remaining hazardous and non-hazardous elements
of the site, such as debris piles and contaminated soil.

The following activities composed the scope-of-work for CECOS:

  1.  "pick through" the debris and rubble to isolate
      all drums;

  2.  analyze the contents of drums containing chemicals;

  3.  repackage leaking drums in secure containers;

  4.  stage drums containing chemicals in accordance with
      their contents;

  5.  crush all empty drums;

  6.  analyze soil and debris for contamination;

  7.  determine locations and quantities of contaminated
      soil and debris; and

  8.  determine quantities and compositions of drummed
      chemicals.

     In addition to the above, CECOS staged the debris into
separate piles (for tires and shredded rubber, wood, scrap
metal, and potentially contaminated soil) and transported
and disposed of all drums containing chemicals found during
the site characterization.

     Since the number of drums containing chemicals was not
known until the characterization was complete, removal and
disposal of such drums were not included in the scope-of-work,
as described in the DER's request for proposals for this site
characterization.  It turned out that there were 750 drums
containing chemicals.  It was decided from a cost and safety
standpoint that these drums should be removed and disposed
under this contract rather than placing them in secure storage
on the site for disposal under a later contract.  The
Contractor, therefore, was directed, under an explicit
contract option for "out-of-lump sum" work, to perform the
disposal activities.  Empty drums were not disposed of.

-------
                             -3-
     CECOS was on the site from August 1 to September 10,
1983.  'During that time approximately 5,000 cubic yards
of debris were picked through and staged in separate piles,
approximately 750 drums containing chemicals were characterized;
wastes were repackaged in secure containers when necessary;
combined in compatible groups when possible; 630 drums were
disposed; and 320 soil samples were obtained and analyzed.

     The DER monitored work acceptability and efficiency
through persons formally named (in the CECOS Contract) as
Cleanup Director and Site Representative.  The Cleanup
Director had ultimate responsibility for the site and for
monitoring the Contractor's performance.  The Site Representa-
tive was an employee of WESTON who was on-site full-time
and represented the Cleanup Director in his absence and was
authorized to make specific decisions on behalf of the DER.
All cleanup actions taken to date at the site by the DER
were done with the concurrence of EPA.  The Agency was intimately
involved, both technically and legally, in the development
and implementation phases of the cleanup.  All proposed
actions were reviewed to assure that they complied with
Federal environmental regulations which existed at the time.

     A separate report has been prepared by WESTON titled,
"Cost Estimates for Selected Remedial Activities in Response
to Hazardous Conditions present at the Wade Property in
Chester, Pennsylvania."  The analytical results of the soil
sampling program performed by CECOS are presented in that
report since they provide the basis for the cost estimates of
removing contaminated soil.

     A focused feasibility study (FFS) and Endangerment
Assessment for the Wade site were tasked to Metcalf & Eddy,
Inc., by EPA in February 1984.  The FFS considers the endanger-
ment and recommends the most cost-effective remedial alternative.

-------
                           -4-
Current Site Status

     A* plan of the site is presented in Figure 1.  The
grid markings shown on the figure were used for locating
the soil sampling points.  As can be seen from the figure,
the site contains seven structures, four rubber storage
tanks, seven tankers, a pump pit, and eleven piles of debris.

     The structures vary in structural integrity from
moderate to poor, all having been damaged by the fire in
1978.  Although not indicated by the figure, the concrete
pad underlying grids 22 and 23 was the floor of a two-story
stone and brick building which was completely demolished
in the fire.  There is heavy machinery bolted to this pad
and also in place in the building encompassed by grids
24, 25, and 26.  In general, the buildings on the site
pose a physical hazard, due to lack of structural integrity,
to persons entering them or walking near them.

     The tankers are empty with the possible exception of
rainwater.  Five of the seven tankers were used to contain
solid and semisolid chemicals which were removed and
disposed during the DER's cleanup operation in 1980.
Like the buildings on the site, the structural integrity
of the tankers ranges from moderate to poor and it is
assumed that none of them is able to be towed over the
road supported by its own undercarriage.

     The pump pit is a concrete rectangular structure
greater than 15 feet deep and currently back filled with
soil.  It is not believed that the pit is connected to the
river though it historically contained a pump used to obtain
process water for the rubber company's operations.

     The piles of debris located at several parts of the
site were formed as a result of the site characterization
and contain separate categories of waste, such as:  tires
and shredded rubber, potentially contaminated soil, scrap
metaT, scrap wood, and crushed empty drums.  All of these
separate materials were formerly found mixed together in
scattered piles across the site prior to the site character-
ization.

     The site itself is level and essentially barren of
vegetation due to excavation and grading performed during
the site characterization.  Vegetation was present, however,
prior to those activities and it is expected to return.

-------

-------
                           -6-
     Over one hundred different organic and inorganic
compounds and metals have been identified on the Wade
property during the course of investigations at the site.
While the majority have been identified in surface soils
many have been detected in both air and ground water
samples taken from the site.

     Sampling by R.F. Weston indicated that contamination
of soils on the site is widespread.  Weston divided the
site into approximately 60 grids and sampled for total
volatile organic compounds (VOC) and total baseneutral
and acid extractable (BNA) fractions of priority pollutants
at four points within each grid.  Their results showed
contamination by VOC, BNAs, or both of the top 12 inches
of soil in nearly every grid.  In general, BNA fraction
was present in higher concentration than the VOC fraction.

     Despite the numerous investigations that have taken
place on the site, the data do not easily permit generali-
zation of the areal extent of contamination by any one
compound.

     Many of the compounds found on site have been
associated with a variety of health effects in humans,
laboratory animals, or both, when inhaled or ingested in
sufficient quantities.  At least six organic compounds or
classes of compounds are suspect human carcinogens;
benzene, chlorinated benzenes, chloroform, tetrachloroe-
thylene, trichloroethylene, and bis(ethylhexyl phthalate).
Certain metals found at the site - hexvalent chromium and
arsenic - are also suspect human carcinogens.  Lead is also
present in the soils and ground water.

     The principal conclusions to be drawn from the site
investigation and endangerment assessment are:

  1. Based on the monitoring results, concentrations of
     volatile organic compounds on the Wade site do not
     present acute exposure hazards to persons on or off
     site.  Although low by acute standards, concentra-
     tions of benzene found did present slighty elevated
     lifetime risks of cancer to persons directly on site.

-------
                          -7-
 2. Inhalation/ingestion of contaminated soil is
    potentially the most serious route of exposure for
    persons entering or playing on the site.  Under the
    assumptions used in the FS, lifetime risks of cancer
    (10~4) from inhaling/ingesting small amounts of
    contaminated soil on the site were higher than risks
    from other routes of exposure.  Sampling results
    indicate that the concentrations of benzene found on
    the site are associated with risks of cancer that
    are 5-10 times higher than those considered as
    negligible.  This finding applies only to persons
    with chronic exposures to soil on the site (i.e.,
    children playing on the site over long periods of
    time) .  No evidence of potential acute health effects
    were found, a finding consistent with results of a
    study by the Center for Disease Control.

3.  Persons entering the site may be exposed to toxic
    chemicals both in the air and in contaminated soil
    and are therefore the most susceptible population at
    risk from contaminants on the Wade Site.

4.  Underground tanks and tunnels, structurally damaged
    buildings, and piles of flammable debris present
    immediate safety hazards to persons entering or
    playing on the site.

5.  Drinking water and fish are not likely to be
    significant routes of exposure to chemicals from
    the Wade site.  Ground water beneath the site is
    not used as a source of drinking water and
    concentrations of chemicals in the Delaware
    resulting from contaminated ground water discharge
    to the Delaware are estimated to be negligible.

6.  Contamination on the Wade site is not expected to
    have a serious impact on the environment either
    through volatilization of chemicals to the air or
    release of contaminants via ground water to the
    Delaware River.  Both releases have been estimated
    to be extremely low.

-------
                           -8-
Enforcement

     In December of 1978/ EPA asked the Regions to list
candidates for RCRA §7003 actions.  The Pennsylvania
DER, which had unsuccessfully ordered Wade and ABM to
clean up the site in 1977, recommended the Wade Site.
Waste leaking, spilled, or otherwise disposed from
drums, tanks or other containers deemed to provide an
imminent and substantial endangerment to health and the
environment by the EPA.  On April 20, 1979, the EPA
commenced a civil action against Wade and ABM.
The Court ordered them to clean up the site.
The complaint was amended in March of 1980 to join
Ellis Barnhouse and Frank Tyson, former presidents of
ABM.  When it became apparent that the current
defendants were insolvent, a year long investigation of
ABM's generator customers took place.  After 32
generators settled for 1.6 million dollars, EPA sued the
remaining 6 generators in the original clean-up action in
December of 1981.  In September of 1982 the Court
dismissed the injunctive relief claims against the
generators and EPA then commenced a CERCLA §107 cost
recovery action which is the current basis for the action
against the generators.  In May of 1984, the remaining
generators agreed to settle with EPA and the State.
Settlement agreements are being negotiated.

-------
                           -9-
Initial Remedial Alternative Screening

     Several alternatives were evaluated by Mitre, NEK,
Weston, EPA and DER.  Based on an initial screening, the
following alternatives were rejected:

   1.  Volatilization of volatile contaminants by
       excavating the soil and spreading it in thin
       layers and turning periodically to expose it to
       the atmosphere or placing the soil in windrows.
       This technique was rejected on the basis of low
       efficiency due to the small size of the site, no
       off-site location available, no removal of BN/A
       contaminants, the requirement of air monitoring,
       unpredictable weather conditions, and the
       possible requirement of mechanical aeration.

   2.  Land farming and composting, for aerobic
       degradation of organic contaminants.  This
       alternative was rejected because of the possible
       requirement for commercially-developed mutant
       bacteria, the low concentrations of organic
       material present in the soil, required treatability
       studies and pilot testing, specialized equipment,
       long processing times, continuous monitoring and
       because the technique had not been proven for
       decontamination of soil.

   3.  Creation of a secure cell on-site, by means of an
       impermeable cover, continuous monitoring of ground
       water and possibly impermeable side walls or liner
       to prevent migration of contaminants away from the
       property boundaries.  This alternative was rejected
       because the contaminated soil would remain in an
       urban area, the cell would have to be perpetually
       monitoried, the hydrological properties of the site
       are not suitable for a secure cell, the property
       would have to be restricted from other use and State
       and Federal permits may be required.

   4.  Total removal and off-site disposal of soil at a
       licensed, secured landfill and backfilling the site
       with imported soil.  This alternative was rejected
       because site investigation shows the soil contamination
       is localized in discrete areas and because of the high
       cost of this solution.

-------
                           -10-
Remedial Alternative Screening

     In order to perform a detailed evaluation,  it was
necessary to develop a list of remedial alternatives which
would include a No Action Remedial Alternative.   Metcalf &
Eddy developed 12 alternatives for the Wade site, based on
Weston's six soil removal options.  (See Table 2 for soil
removal options.)

Alternatives:

     1.  No Action
     2.  Remove, decon & dispose of tires & tankers, remove
         on-site waste piles; demolish buildings, level site,
         fill and grade property.
     3.  Remove, decon & dispose of tires & tankers, remove
         on-site waste pile; demolish buildings, level site,
         fill and grade property, cover with asphalt cap.
     4.  Remove, decon & dispose of tires & tankers, remove
         on-site waste piles; demolish buildings, level site,
         fill and grade property, cover with topsoil and
         seeded cap.
     5.  Remove, decon & dispose of tires & tankers, remove
         on-site waste piles; demolish buildings, level site,
         fill and grade property, soil removal option 1A,
         cover with asphalt cap.
     6.  Remove, decon & dispose of tires & tankers, remove
         on-site waste piles; demolish buildings, level site,
         fill and grade property, soil removal option 1A,
         cover with topsoil and seeded cap.
     7.  Remove, decon & dispose of tires & tankers,
         remove on-site waste piles; demolish buildings,
         level site, fill and grade property, soil
         removal option 1C, cover with asphalt cap.
     8.  Remove, decon & dispose of tires & tankers,
         remove on-site waste piles; demolish buildings,
         level site, fill and grade property, soil
         removal option 1C, cover with topsoil and seeded
         cap.
     9*  Remove, decon & dispose of tires & tankers,
         remove on-site waste piles; demolish buildings,
         level site, fill and grade property, soil
         removal option 2A, cover with asphalt cap.
    10.  Remove, decon & dispose of tires & tankers,
         remove on-site waste piles; demolish buildings,
         level site/ fill and grade property, soil
         removal option 2A, cover with topsoil and seeded
         cap.

-------
                           -11-
     11.  Remove, decon & dispose of tires & tankers,
          remove on-site waste piles; demolish buildings,
          level site, fill and grade property, soil
          removal option 2C, cover with asphalt cap.
     12.  Remove, decon & dispose of tires & tankers,
          remove on-site waste piles; demolish buildings,
          level site, fill and grade property, soil
          removal option 2C, cover with topsoil and seeded
          cap.

Screening Considerations:

A.  Ground water

     The hydrological evaluation determined that
the Delaware River is the outflow point for ground
water from the Wade site.  The results of the evaluation
indicate that, based on all organic contaminants detected
in ground water at the site, continued input of contami-
nated ground water to the Delaware River under the no-action
alternative would not have a measurable adverse impact on
water quality or biota, if contaminated soil was removed from
the site.  The concentrations of individual organics after
mixing of ground water with both the estimated full flow
and half flow of the Delaware River are all well below all
applicable Ambient Water Quality Criteria and U.S. EPA
Health Advisories for ingestion of toxic and carcinogenic
compounds in water (Table 1).  Therefore, due to the negli-
gible impact of ground water on the off-site environment and
public health, groundwater interception and withdrawal
remedial actions were eliminated from further consideration.

B.  Soil Excavation/Removal Remedial Alternatives

     Six remedial alternative soil excavation/removal
options (1A, IB, 1C, 2A, 2B and 2C) were developed by
Roy F. Weston based on either of two threshold levels of
organic contaminants for defining whether the soil is
contaminated (See Table 2.)  One threshold level on which
three of the alternatives (1A, IB, 1C,) were based was 100
mg/kg for both the volatile and base neutral/acid (BN/A)
fractions.  The second, on which the remaining three (2A,2B,
2C) alternatives were based, was 100 mg/kg for the volatile
fraction and 500 mg/kg for the BN/A fraction.  Metcalf &
Eddy reviewed the confirmed contaminated soil excavation
quantities and potentially contaminated soil quantities for
Options 1A, 1C, 2A and 2C, determined by R.F. Weston.  A
conservative approach was taken due to possible synergistic
effects.

-------
TWLC i.  OCUUnWC HIVCM CONTAMINATION ASSESSMENT
Oo^»M
Adk&A^AA
flCvfONI •
Ac*taM> w4.0tetMv tellM*
AmtoM •* Ofwffcyf SnlfM*
^^_ ^M^
BMBM
BMiylcMorMd
CMaratanww
CMarabMMM
Oklaretara
CMorofom
3ttarofar»
CM or of or*
>larofom
CMaroprm*
CMaro«r«n«
DIcMorotMINM.
OlcMarOOMBtW
. OlcftloroBtlMM
. OlcklorMtfcm
. OlchloroatlwM
. OlcHlorovttWM
, Olcklora*ttt«i«
. OlcMora*«lMn«
. OlcMorocthwtt
, Olctilara*«1«OT«
, DIcttlorwtkHM
. Dldilora*ttMM
. Ole«ilora»ra»aii«
. Olc*laro»ra»m«
. Olc«larapra»«n«
, OlehlirafrapOT*
, Olckloro*rao*n«
. Olchlora»ra»an*
. Oldilaraprapw*
, Ole»oro»rap«ii>
Dla»t»U>M*t»
flraundwtcr
CaicOTtrctlen
(«q/L»
IW.OOO
t.OOO
f.wn
3,100
<2.0
21
2.200
M
27.000
146
144
n
w
30
21
6TO
<2.0
3.400
•W
III
M
•.MO
m
M
T4
30
24
7.0W
1,780
4W
237
2»
W
33
1*
9.000
StctlM GMemtratlaii In 6* !••»•• M.ni
M»>ir •!*»• •Ulna-rull Flo> (w|/l)
B4A
B6A
•W
B4A
M.M
• 1A
B2
M
B4A
e»
BM
B4
§1
BIA
M
82
M.M
MA
BM
B»
B2
B3A
BM
B4
M
88
B2
B3A
B4A
B9
B«A
BM
87
B8A
M
B3A
O.I3«2
0.0093
0.0078
0.00)2
0.000002052
0.000022
0.0073
0.0000377*
0.078
O.OOOI4M
0.0001483
0.0000)9
0.000032
0.000432
0.000022
0.0007
0.000002062
O.OOMO?
0.00088
0.000173
0.0000337
0.0067
0.00079087
0.00009
0.0000764
0.0000304
0.000023
0.0073
0.00184
0.0004642
0.00074
0.000236
0.000037
0.0000361
0.0000196
0.0032
CWMiitraHiM In D»l«w» H.OI tatUnt Niter QMlIt* O-lt*rl«
•1*
0.000004
0.007
0.00173
0.00074
0.0001
0.0134 113.000 m>n. lMMt*»
0.00036
0.0002
0.00019 . •
O.OOdD62
0.00003
0.00003 10.200 m>n. (MMt*)) 430 ««A drailc
0.0149
0.00)7
0.0003
0.0003
0.000113
0.00007
0.00004
0.01

-------
TAflLt 1 fOnMlMM). OCUMMC m«tM OMTMIIMTKM ASSCS9CNT
Cnewfctloi Station CoMCMtratlai In tolawr* M» Omantrctloi In 0*U«r« R.lll A*t«*t *tv Owllty
rju — 1< C«u/lt -inbT- *«tv •(»tfi<|-Fi>l« Ft«nt ««q/U •<*••• C.NIWI .1/2 Flow («N/LI Criteria for Saltwtar Acwtfe Ufa
ftkyl BMWM
ftkyl Bw»aMa
Ctfcytatl«r
CtkyUtlW
iMtroayl Alekakol
••oprtwyl AldMAel
Ixwrotyl Alekekol
lM*r<»rl BMIBII*
lM*ro*yl Bwtwt*
NithyUldMfiel
Nttkyldi* ChlerM*
N»tkyl«w CMorM*
N»t*iy (•»*» 1 totow
Mtfcyl llatetylk*tawi
Mvtfcyl Itotetyll^ai*
MBtbyl iMtaityltetow
••tttyl liotntyltotow
MBthyl ItotMtylkcton*
•bttiyl Itotefyltotoi*
Mtky 1 Mthwry 1 at*
n-ffopflstcholiol
TcfTMll I OTMtfcyl MM
T«tr»chl«ro»t1iyl«i»»
TatrikytfrofirM
TctrMiydrotvM
TvtrakvdrelwMi
T«tr«h««re«vM
TatrchydrofwOT
T«tr*liydro«V4n
T»tr (hydro* «•••
T*tr«hytfrotir»
TeliMii*
TolDMW
Trwt-1.2 DIcMoroBtfcylOT*
Tratcl.2 OleHlvactftylM*
Tr«n«-l,2 Ole*le»-o»ttiylw>«
TM
14
•.0
4.0
17.000
900
400
100
1)
1.200
11.400
114
T.100
05.000
1.770
400
80
42
S.O
1.100
200
21
12
26.000
2.300
1.400
MO
200
190
170
170
12.400
<*.o
MO
M
•.0
B4A
BO
BU
B2
MA
B3A
B2
MA
B3A
B3A
MA
B5A
MA
MA
B9A
BBA
B34
M
B5
MA
B2
BOA
B9
B3A
B9A
B8
BIA
B9
B7
B6A
B6A
MA
B6.6A
B8A
BO
B2
0.00733
0.00001444
0.00000879
'0.000004
0.017)3
0.00093
0.000413
0.000103
0.0000134
0.00124
0.012
0.00012
0.0079
0.0877
0.00131
0.000413
0.000062
0.00004332
O.000003I
0.00113)
0.00071
0.000007062
0.0000124
0.07682
0.007372
0.0014
O.OOOM94
0.0078
0.000196
0.00017)3
0.00017)3
0.013
0.000007062
0.000 3O94
0.0000309
0.0000062
0.01508
0.00003
0.000016
O.OOOON
0.0)3
0.0010
0.0006
0.00021
0.00003
0.0075
0.0733
0.0007
0.0138
0.1753
0.00762
0.0008
0.000174
0.000087
0.0000062
0.0073
0.0004
0.000043 10.200 «a/l Aartvi 450 X/V eftrailc
0.000025
0.054
0.0047
0.0078
0.00062
1 0.000)7
0.00004
0.00033
0.00033
0.076 t.100 mn. (•af«)«3.000 w/l Idrmlel.
0.000004
0.00062 224.000 «nA l«atHI
0.00062
0.0000124

-------
TABU I <0»tlm»4>.  KUMMC MIVCM OMrMIIMTION ASSCS9CNT
CwcMtratlai Statloi OMMiitratloii In 0»l«w« •."' Concentration In 0»l«wr* •.."' A*l**t Mtar QMllty
Oi^ninl («f/U Nuater altar Bluing-full Flow <«g/l» cttar Bluing .1/2 Flo* iMg/LI CHtarl* »•
%I«W
%|BM
%l*n*
%!•*•
%I«M
21.400
425
77
72
49
10
5. MO
24
17
14.700
• I*
6)
60
M
54
42
M
M
It
II
<2.0
4.0
B4A
BM
BB
B4
B)
BM
BM
B4
B)
BM
BM
B)
B4
BM
BM
BM
BM
B2
B5
Bl
B2A
BM
0.022)
0.0004M
0.0000794
0.000074
0.0000)09
0.0000 10)
0.0099
0.000029
0.0000010)
0.0192
0.0006)9
O.OOOO69
0.000062
0.0000)776
0.0000997
0.0000*1)2
0.0000402
0.0000)7
0.00002
0.00001 1)
0.000002062
0.000002062
0.0449 M.200 «(A (MHt«»
0.0009
0.00016
0.00019
0.0001
0.00002
0.0109 2.000 «|/l <*Mt*>
0.00009
0.0000)9
0.0)
0.001)
0.0001)
0.000124
0.0001
0.0001
O.OOOOM
o.ooooa
0.000074
0.00004
0.00002)
0.000004
0.000004

-------
                           Table 2


        Soil Excavation/Removal Remedial Alternatives
1.  Remove contaminated soils exceeding organic contaminant
    concentration of either 100 mg/kg volatile organics or
    100 mg/kg base, neutral/acid organics.


         A. Excavate to Last Contaminated Depth1
         B. Excavate to intermediate Depth?
         C. Excavate to Uncontaminated
2.  Remove soils exceeding an organic contaminant concentration
    of either 100 mg/kg volatile organics or 500 mg/kg base,
    neutral/acid organics.


         A. Excavate to Last Contaminated Depthl
         B. Excavate to intermediate Depth?
         C. Excavate to Uncontaminated Depth3
I/  Soil removed down to depth at which last contaminated
    soil was found.

2/  Soil removed down to depth at which last contaminated sample
    was found if threshold level exceeded by 20 percent or less;
    one foot deeper than last contaminated depth if threshold
    level exceeded by 21 to 100 percent; and down to depth at
    which first Uncontaminated sample was found if threshold
    level exceeded by greater than 100 percent.

3/  Soil removed down to depth at which first Uncontaminated
    sample was found.

-------
                             -16-
     There are currently no standards for exposure to total
volatile organic (VOC) or base neutral/acid extractable (BNA)
fractions in soil.  The toxicity of the contaminated soil
depends in part on the individual compounds present and in
part on any additive or synergistic effects that the
compounds may exert together.  Since no compelling toxico-
logical evidence supports a threshold of 100 rag/kg of total
VOCs or BNAs versus 50 mg/kg or 150 mg/kg, it is unlikely
that any meaningful distinction can be made between excavat-
ing to "clean" depth or to one foot below the last contami-
nated sample on the basis of public health impact.

     In several grids, the concentration composites indicated
contaminant levels greatly exceeding the set threshold
levels, yet analysis of the quadrants' analytical data
indicates the opposite.  In other grids, this relationship
was reversed.  These results suggest that the sampling
method may not be an accurate indicator of the extent of
contamination of the whole grid.  While this lack of corre-
lation is a general problem with all the soil removal
options, it suggests that making distinctions between soils
that are 20%, 21-100% or greater than 100% over the threshold
is not valid over an entire quadrant.  On the basis of the
toxicological issues and the sampling discrepancies, Metcalf
& Eddy concluded that soil removal options IB and 2B are
unjustified and should be excluded.

C.  Remove Debris

    Removal and disposal of on-site, crushed drums and
contaminated soil pile(s) were included in the Removal of
Debris remedial item.  These had been included under the
contaminated soil removal activity, however, it is more
appropriate to consider them as part of removing site debris.
A 50 percent swell factor was used for estimating the volume
of crushed drums after loading into trucks for subsequent
hauling to a final disposal site.  A 15 percent swell factor
was used for estimating the loading volume of soil from above-
ground soil piles or excavated from the site for subsequent
hauling to a final disposal site.

D.  Demolish Building

     Several items were added to the Demolish Buildings
remedial activity.  These included the following:

     - Rough grading and site leveling up to 12 inches
       over existing grade in order to cover any pro-
       truding subsurface structures which have not been
       removed.

     - On-site sump sampling and analysis and waste
       removal.

-------
                             -17-
     - Underground fuel oil tank/contents removal.

     - 'Underground waste chemical/solvent tank
       contents removal.

     - Closure of underground tunnel, filling in of
       building basements and vehicle weighing station
       pit.  The tunnels and pit are potential reservoirs
       for off-site contamination.

     These items were added to the Demolish Buildings
remedial activity because it would be appropriate to under-
take these items during the building demolition activity.
Off-site, handling quantities of building demolition debris
were calculated for the following scenarios:  remove all
debris from site for each soil excavation option under
consideration (1A, 1C, 2A, 2C).  These quantities are used
in the subsequent cost analysis of remedial alternatives.

     The site remains a safety hazard to persons entering or
playing on the site and in abandoned buildings.  Despite
locked gates to the site, persons from the surrounding
neighborhood are known to gain access to the site.

     Initial remedial activities on the site have not removed
all safety hazards from the site.  Two partially full under-
ground tanks, an underground 4-foot x 4-foot tunnel beneath the
main building, and structurally damaged buildings present
serious physical hazards to persons gaining access to the site.
The identity of compounds in the remaining underground tanks
have not been established as of this writing but nevertheless
the tanks themselves are at least partly accessible from the
ground.  Both the tanks and the tunnel may contain oxygen
deficient or toxic atmospheres that increase the likelihood
of accidents.  The major fire at the Wade site in 1978 damaged the
structural integrity of several buildings on-site, increasing the
likelihood of unexpected collapse.  Finally, remaining piles of
debris (wood and tires) are potential fire hazards.

E.  Site Capping

     The results of the Endangerment Assessment for the No
Action remedial alternative, as previously discussed, in-
dicated minimal risks as a result of on-site ground water
contamination.  On this basis, ground water interception,
withdrawal and treatment remedial alternatives were elimi-
nated from further consideration and detailed evaluation.
The site capping options range from relatively impermeable
clay capping to asphalt capping to relatively permeable
topsoil/seeding capping.  Clay capping is the most effective
of these capping options at preventing infiltration of
precipitation into the unsaturated soil zone (contaminated
soil) and subsequent movement into the ground water.

-------
                             -18-
     Precipitation has and does infiltrate the unsaturated
zone on-site and recharges the ground water, but its effect
on ground water does not pose significant risks as previously
discussed.  Therefore, it is not necessary to prevent
infiltration by installing a relatively impermeable clay cap
or asphalt cap on the site.

-------
                             -19-
Cost Analysis

     Table 3 presents the site implementation costs for
all the 12 remedial alternatives based on Metcalf & Eddy's
cost estimates for site Debris Removal, Building Demolition,
Site Capping and Contaminated Soil removal.

Post Closure, Long Term Monitoring Plan

     Once remedial activities have been completed on the
Wade site, it is required that the site be further monitored
for a period of 30 years to determine the effectiveness of
the remedial activities.

     The plan includes the following tasks:

     1.  Site Inspection:

          The site inspection will include a visual
     inspection of surface conditions and the monitoring
     we 11 s.
     2.  Installation of Upgradient Monitoring Wells:

          Two upgradient monitoring well clusters will
     be installed in off-site locations in order to
     monitor the water quality of the ground water
     before it flows under this site.

     3.  Water Sampling:

          The purpose of this sampling is to determine
     ground water quality before ground water enters the
     site and ground water quality as it leaves the site.

     4.  Laboratory Analysis:

          Both water and soil samples will be analyzed for
     priority pollutants, cyanide and TOX based upon
     contaminants identified in previous site sampling.
     After five years of sample collections, the sampling
     protocol will be re-evaluated to determine if certain
     pollutants can be targeted such that there can be a
     reduction in the cost of laboratory analysis without
     any reduction in monitoring effectiveness.

-------
TABLE 3    REMEDIAL ALTERNATIVE COST ANALYSIS
Remedial
Alterna-
tive
No.
1.
2.
• 3.
J».
5.
6.
7.
8.
9-
10.
11.
12.
Site
Debris
Removal
($)
o :
529,029
529,029
529,029
529,029
529,029
529,029
529,029
529,029
529,029
529,029
529,029
Demolish
Bldgs
(1)
0
268, 715
268,745
268,745
252,750
252,750
243,156
243,156
260,871
260,871 '
256,439
255,439
Site
Capping
(I)
0
0
331,930
75,620
331,930
75,620
331,930
75,620
331,930
75,620
331, 930
75, (>20
Soil
Excava-
tion
($)
0
0
0
0
1,191,250
1,191,250
1,979,755
1,979,755
714,530
714,530
1,012,512
1,012,512
Total
Implemen-
tation
Cost
($)
0
797,774
1,129,704
873,394
2,304,959
2,048,649
3,083,870
2,827,560
1,836,360
1,580,050
2,129,910
1,873,600

-------
                             •21-
      5.   Replacement  of  Monitoring  Wells:

           The present three  downgradient well  clusters
      were  originally  constructed with galvanized pipe and
      it  is anticipated that  the wells will  need to  be
      replaced in  10 years.   The two upgradBent wells will
      be  constructed with stainless  steel pipe  and it is
      anticipated  that the wells will need to be replaced
      in  15 years.  Monitoring well  deterioration may
      result from  corrosion of the pipe or screen,
      accumulation of  silt in the well, or plugging  of the
      screens.

      6.  Well Maintenance and Rehabilitation:

           A program of/well  maintenance and rehabilitation
      will  be implemented every five years to insure that
      the monitoring wells will provide representative
      samples and  that the surface integrity of the  well
      has not been compromised.

      7.  Topsoil Maintenance;

           A program of topsoil maintenance will be  implemented
      every two years  to  insure that the topsoil cap completely
      covers the site.  Periodically it may be  necessary to fill
      in erosion channels, to add topsoil to areas where the
      vegetation has become sparse.

      8.  Mowing of Grass:

           Once the topsoil cap has been constructed and it has
      been  seeded and  sodded  it will be necessary to mow the
      new grass during the growing season.  The task would be
      performed on a yearly basis probably during the summer
     months and will  become  a integral part of the  site
     maintenance.

Commun i ty  Re1at ion s

      public meetings  were held in October 1982, July 1983,
and September 1983 to discuss the remedial work performed
by CECOS and the studies  conducted by Roy F. Weston.  various
types of media (e.g., newspaper ads, fact sheets, radio) were
utilized to notify the public of these meetings.  Representa-
tives of U.S. EPA, State, local governments and the community
were  all well represented.   Copies of reports and data were
provided, with a 20 day  comment period.

     A public meeting to  discuss the Wade site feasibility
study was held at Chester City Hall on Wednesday, June 13, 1984.
The meeting, was conducted by the PA DER and EPA.  public officials
and citizens were very interested in the future use of the site as
well  as the timeframe for completion of the cleanup.  There were no
written comments received.

-------
                            -22-
Recommended Alternative

     Seption 300.68(j) of the National Contingency Plan
(NCP) [47 FR 31180, July 16, 1982] states that the appropriate
extent of remedy shall be determined by the lead agency's
selection of the remedial alternative which the agency
determines is cost-effective (i.e., the lowest cost
alternative that is technologically feasible and reliable) and
which effectively mitigates and minimizes damage to and
provides adequate protection of public health, welfare, and
the environment.  Based on our evaluation of the cost-
effectiveness of each of the 12 proposed alternatives, the
comments received from the public, information from the
Endangerment Assessment, and information from DER and
Weston, we recommend that alternative 10 be implemented.
This alternative includes:  the removal, decontamination,
and disposal of tankers, tires and debris; destruction of
buildings; soil removal; leveling, filling, and grading
the site, and covering with a seeded topsoil cap.

     The recommended alternative is the least cost alternative
that is technically feasible and reliable, that meets the
requirements of the NCP and provides for future protection
of public health, welfare, and the environment.  It also complies
with RCRA by calling for offsite disposal of contaminated
soil at a RCRA approved lined facility, and the level of cleanup
was determined in a manner consistent with the RCRA methodology.
In comparison with the other alternatives, alternative 10 has
the following:

     1.  Fewer monitoring requirements as a result of
         the topsoil cap;
     2.  Requires less time to implement of all the soil
         excavation options (lowest quantity of contaminated
         soil requiring excavation);
     3.  Easiest to install of the soil options due to the
         smaller soil excavation quantities;
     4.  Uses relatively proven technology, i.e., contaminant
         source removal with proper disposal;
     5.  More durability with a topsoil cap than asphalt due
         to a longer period of time that the level of effective-
         ness can be maintained;
     6.  More effective than the no action remedial alternative
         and non source removal alternatives;
     7.  If no action was chosen, we would still have the
         problem of a release occurring which would ultimately
         end in a ground water investigation;

-------
                           -23-
     8.  The exposure rate of most concern for the Wade
         Site from the standpoint of public health is
       -  inhalation/ingestion of contaminated surface
         soils.  Further removal of soil beneath the
         5 foot level (Alternative 12) would have no
         impact on this route of exposure, and;

     9.  Removal of contaminated soil down to 5 feet
         allows for protection of human health and
         environment in the future.

The estimated costs for the recommended action are:

Remedial Action                       Estimated Cost

Site Debris Removal                    $  529/029

Demolish Buildings                     $  260/871

Site Capping                           $   75/620

Soil Excavation                        $  714/530

           Total Implementation Cost = $1/580/050

Operation & Maintenance                $  320/000

                               Total = $1,900,050


Project Schedule

     - Approve Record of Decision     July 1984
     - Award Contract                 September 1984
     - Start Construction             September 1984

-------