United States        Office of
Environmental Protection   Emergency and
Agency           Remedial Response
                               EPA/ROD/R03-91/134
                               June 1991
Superfund
Record of Decision:
First Piedmont Quarry 719,
VA

-------
50272-101
REPORT DOCUMENTATION i. REPORT NO. z.
PAGE EPA/ROD/R03-91/134
4. TOe and SuMMe
SUPERFUND RECORD OF DECISION
First Piedmont Quarry 719, VA
First Remedial Action - Final
7. Authors)
9. Performing Organization Name and Address
12. Sponsoring Organization Name and Address
U.S. Environmental Protection Agency
401 M Street, S.W.
Washington, D.C. 20460
3. Recipienf 8 Accession No.
5. Report Date
06/28/91
6.
8. Perl o H I ill •$ Org&nizfttion Rcpt. No.
10. Projecl/Tssk/WoricUnHNo.
11. Contract(C) or Grant(G) No.
(C)

-------
EPA/ROD/RO3-91/134
First Piedmont Quarry 719, VA
First Remedial Action - Final

Abstract  (Continued)

edge of the landfill.  The Carbon Black Pile contains 100 cubic yards of a tire
reinforcement additive and contaminated soil, and the Waste Pile contains 10 cubic
yards of steel and nylon cords, glass, waste rubber strips, and contaminated soil.  In
1972, the State ordered waste disposal operations to cease as a result of a fire on the
landfill.  This Record of Decision  (ROD) provides a final remedy for all site media
including the landfill material, leachate, the Carbon Black Pile and Waste Pile, and
the contaminated Northern Drainage  soil and sediment.  The contaminants of concern are
metals including antimony, arsenic, lead, barium, and zinc.

The selected remedial action for this site includes excavating and disposing offsite
1,080 tons of waste from the Carbon Black and Waste Piles along with the contaminated
soil and sediment from the Northern drainage areas; performing a TCLP of excavated
material to determine if it is RCRA characteristic waste, and if so, solidifying and
stabilizing the excavated material  prior to offsite disposal; filling the excavated
Carbon Black and Waste Pile areas with clean soil; disposing of 30-40 drums from the
surface of the landfill at a RCRA Subtitle C treatment facility;  decontaminating and
disposing of surface debris at an approved landfill; constructing a RCRA-cap and an
associated leachate collection system over the 2-acre landfill area; covering the cap
with 6 inches of soil and contouring soil to promote run-off, and revegetating the
area; constructing run-off control  berms in the Northern Drainage areas to lessen
landfill cap run-offs; pretreating  leachate, if necessary, prior to transporting to a
Publicly Owned Treatment Works  (POTW), or constructing an onsite treatment system with
onsite discharge to surface water if the POTW will not accept the leachate; draining
the north and south ponds, and transporting and discharging pond water offsite to a
POTW; monitoring ground water and conducting bioassays to assess the effectiveness of
the removal of the Carbon Black Pile and Waste Pile on the reduction of contaminant
levels in the Southern Drainage; and implementing institutional controls including deed
restrictions, and site access restrictions such as fencing.  The estimated present
worth cost for this remedial action is $2,154,000, which includes an annual O&M cost of
$66,200.

PERFORMANCE STANDARDS OR GOALS:  No applicable.

-------
                        RECORD OF DECISION
               FIRST PIEDMONT ROCK QUARRY/ROUTE 719

                           DECLARATION
SITE NAME AND LOCATION

First Piedmont Rock Quarry/Route 719 site
Danville, Virginia


STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action for the
First Piedmont Rock  Quarry site (the Site)  in Danville, Virginia
which  was  chosen in  accordance  with  the requirements  of  the
Comprehensive Environmental Response, Compensation,  and Liability
Act of 1980  (CERCLA),  as amended by the  Super fund Amendments and
Reauthorization Act of 1986 (SARA),  and, to the extent practicable,
the National Oil and Hazardous Substances Pollution Contingency Plan
(NCP). This decision document explains  the factual and legal basis
for selecting the remedy for this Site.  The information supporting
this remedial action decision is contained  in the Administrative
Record for this Site.

The  Virginia Department  of  Waste  Management  concurs  with  the
selected remedy.

ASSESSMENT OF THE SITE

Pursuant to duly delegated authority, I hereby determine, pursuant
to Section  106 of CERCLA,  42 U.S.C. Section 9606,  that  actual or
threatened  releases  of  hazardous  substances  from this Site,  as
discussed  in  "Sw^TY  of  Site  Risks.1*  if  not  addressed  by
implementing the response action selected in this Record of Decision
(ROD), may  present  an  imminent and substantial  endangerment to
public health, welfare, or the environment.

DESCRIPTION OP THE REMEDY

This  remedy  will  address all of the  media   impacted  by  the
contamination at  the Site.   It is  not  warranted at this  time to
split the Site  into smaller  components called  operable units to
address individual media.  Based on  the  information derived through
the Remedial  Investigation, the Site does not  pose any principal
threats to human health. Since wastes will be left in place, long-
term monitoring of the ground water must be performed.   The ground
water monitoring must encompass the full  range of RCRA Subtitle C
requirements  because of the  disposal  of tetrachloroethylene,  a
listed RCRA hazardous waste, into the landfill.

-------
The selected remedy includes the following major components:

     •  Excavation.and offsite  disposal of the Carbon Black, Waste
        Pile and the Northern Drainage  soils and sediments.

     • A RCRA Subtitle C cap on the landfill.

     • Collection of  leachate with treatment at a POTW.

     • Washing and offsite disposal of surface debris.

     • Ground water monitoring.

     • Institutional  controls.

DECLARATION OP STATUTORY DETERMINATIONS

The  selected  remedy  is  protective  of  human  health  and  the
environment, complies with Federal and State requirements that are
legally  applicable  or relevant  and  appropriate  to  the remedial
action,  and is cost-effective.    This remedy utilizes  permanent
solutions   and  alternative  treatment   (or   resource  recovery)
technologies to the maximum extent practicable, and it  satisfies the
statutory preference for a remedy that employs  treatment that reduce
toxicity, mobility,  or volume as their principal element.

Because this remedy will result  in hazardous  substances remaining
onsite, a  review  will be conducted  no less often than  each five
years  after initiation of  remedial action to ensure that  human
health  and the environment  are being protected  by  the remedial
action being implemented.
    •    >        _,
Edwin B. EricksonDate
Regional Administrator
Region III

-------
            DECISION SUMMARY for the RECORD of DECISION

             FIRST PIEDMONT ROCK QUARRY/ROUTE 719 SITE



1*   Site y«m«f Tiocation* and Description

The First Piedmont Rock Quarry Superfund  site (the Site) is located
along  Route   719   in   Pittsylvania  County,  Virginia  near  the
intersection with Route  360.   It is approximately six miles north
of the city of Danville  (see Figure 1).

The Site is  an abandoned rock quarry located on a topographically
high  ridge.    The  quarrying  operation  left a  cut into  the rock
outcrop bounded on three sides by the quarry highwalls.  The fourth
side of the cut is open and slopes to the west.

The majority of the land use in the  immediate Site vicinity is open
space/woodlands.  Directly  across Route  719 and south of the Site
is a residential area,  the Beaver Park community.  The closest home
is approximately 150 feet  from the  Site.   All the homes in Beaver
Park  obtain  residential  water  from either  wells  or  springs.
Approximately  455  people  live  within  one mile  of  the  Site;
approximately  1,893  people live  within  a  two-mile radius  of the
Site.

The Site is  located  within the Piedmont  Physiographic Province in
southern Virginia.   In  general,  the physiography of  this  region
consists of rounded uplands dissected by numerous streams.  The land
surface in the immediate vicinity of the Site slopes gently westward
at a grade of 0 to 8  percent.   Local relief  between the uplands and
valleys in the vicinity of the Site is about 100 feet.

The regional  geology of the area generally consists  of weathered
residuum and saprolite  overlying Precambrian metamorphic  rocks.
Field investigation of outcrops at and near the Site indicate that
the bedrock  is moderately fractured.  Four major  fracture  trends
were observed in the outcrops  (Figure 2).  Most fractures are near
vertical with little parting displacement.   Regional data indicate
that  the  shallow  bedrock  is  fractured,  but  the occurrence  of
fractures decreases with depth.  Fractures probably do not occur at
depths much greater than 50 to 100 feet.

Most of the  soils  in the area are moderately to well-drained clay
to sandy loams.  The soils  range from silty sands to silty clays.
Soils are well developed on flat slopes and thin, poorly developed
on steep slopes.   The soils have little sorptive capacity, with the
highest value found in the northern drainage.

Pittsylvania  County has  a  temperate climate.    The mean  daily
temperature  varies  from  40   F  in  January to  77°  F  in  July.

                     >

-------
                                                                      tl
BASE MApt U.S.G.S.
GREENSBORO, N.C.
r  x 2*

CONTOUR INTERVAL - 50 Ft.
                       fttOIOMAL SIT! LOCATION
          Enrtranamtal
PPMO /  ROOTI  Tit f ITI
    9AMVILLB. VA
                                                     4U&86-93O
                                                                   /4SOQOO

-------
Precipitation  averages 43.48  inches per  year and  is relatively
evenly distributed.

Ground water occurrence in  the Piedmont  Province  is principally
limited to a depth of less than 150 feet; most ground water is found
within 30 feet of the surface.  Most of the ground water within each
ground water basin discharges to  the surface at low points in the
topography.  The  seeps and  springs  upgradient of  the landfill and
south  of the  Beaver  Park  community  are  ground water  discharge
points.   The landfill  is also  a  ground water  discharge  area for
local ground water.  The majority of the ground water at the Site
discharges as leachate along the western edge of the landfill into
the north pond and then into the northern drainage.   Surface water
data  and observations indicate  that  most  of the ground  water
discharged  from  the  north pond re-infiltrates or is  lost  to the
atmosphere via evapo-transpiration.

Drainage from the area  is to Lawless  Creek,  which lies approximately
1400  feet to the northwest of the quarry.    Lawless Creek  is  a
tributary of Fall Creek, which is a tributary of the Dan River.

As depicted in Figure 3, two small  ponded areas/wetlands are located
within the landfill.   The landfill is drained by two areas denoted
on Figure 3  as "Southern Drainage"  and "Northern  Drainage".   Both
drainageways flow toward Lawless Creek;  neither discharges directly
into the creek.  The Northern Drainage contains three wetland areas:
a small  cattail  stand and a small  phragmites stand  in  the upper
reaches  and a larger  cattail  marsh located  in  the  bottom  land
hardwoods along Lawless Creek.  Other than these wetlands, there are
no significant habitat, agricultural  land,  historic  or  landmark
sites directly or potentially affected.   There are no endangered
species or critical habitats within close proximity to the Site.

There  are approximately thirty to  forty  drums remaining on  the
surface of the landfill.


2.   aite History and Enforcement Activities

The Site was initially operated as a quarry for crushed stone.  The
four-acre  property  which  comprises  the  Site  consists  of  the
abandoned quarry and the adjacent  land.   The  Site was leased by the
First Piedmont Corporation to be used as a landfill for industrial
and agricultural waste from April  1,  1970 to  April 1, 1975.  Wastes
were disposed  in the  landfill from April, 1970 to  July,  1972,  at
which point  the  Virginia Health Department ordered  waste disposal
operations to cease due to a fire on the landfill.

The landf illing operations were restricted almost exclusively to the
two-acre quarry  area.   The quarry was  not filled in a systematic
fashion;  no cells  or  segregated disposal  areas  were  used  for
specific wastes.   Hundreds of drums  were buried in the landfill  in
random fashion with other solid waste.   Upon arrival at  the Site,
wastes were generally dumped at the highwall  along the eastern edge

                                -2-

-------
220!
I-tO*





                                              ROSE DIAGRAM OF FRACTURE
                                                 FREQUENCY  (PERCENT)
                                              FIRST  PIEDMONT ROCK QUARRY
                                              ROUTE 719 SITE
                                              4112-88-904 A
                 J^'lifU-
                 
-------
FIGURE 3

-------
of the landfill, where the quarry is approximately 35 feet deep, and
pushed down with a  bulldozer.   Wastes were not covered at the end
of each day.

The landfill contains approximately 65,000 cubic yards of industrial
and agricultural waste and approximately 3,000 cubic yards of soil
used as a cover when the landfilling was stopped.  The industrial
wastes were generated by The Goodyear Tire and Rubber Company and
Corning Glass Works;  the  agricultural  wastes were generated  by
Southern Processors,  Inc.   The wastes from  Goodyear consisted of
tires,  general  plant refuse,  scrap rubber,  rubber  buildup  and
approximately 15,000 gallons of  a mixture of residual MS-20  (a floor
degreaser), water,  carbon black and detergent.  The MS-20 contained
ten percent  by  volume of tetrachloroethylene  which is  a listed
hazardous waste  under the Resource,  Conservation and Recovery Act
as amended, 42 U.S.C. 6901 et seq. (RCRA).  The wastes from Corning
Glass  Works   consisted  of   paper,   glass,   cardboard  and  off-
specification batch materials which contained trace amounts of lead
oxide.  The wastes  from  Southern  Processors, a tobacco processing
company, consisted  of soil  removed  from tobacco  leaves,  tobacco
scrap, paper and wood.

Separate and apart  from  the  landfill are two other areas of waste
disposal on  the site associated  with the  landfilling operation.
These two  areas are  denoted as the  "Carbon Black  Pile"  and the
"Waste  Pile"   on Figure 3.   The  Carbon Black  Pile  consists  of
approximately  100  cubic yards  of carbon black  (a reinforcement
additive  used  in   tire  manufacturing  that  is  comprised  almost
entirely of carbon)  and  contaminated soils.   Zinc oxide bags were
reportedly observed  in the  pile during the construction of access
roads for  the Remedial  Investigation.   The Carbon  Black  Pile  is
approximately  150 feet from the most western edge of the landfill.
The Waste Pile  contains approximately  10  cubic  yards of  waste
material consisting of steel and nylon cords,  some glass,  waste
rubber strips  and  contaminated soils.  The  Waste  Pile is located
about 75 feet  from the western edge of the landfill.

Another disposal area not associated with the  landfilling operations
is located about 100 feet southwest of the Carbon Black Pile.  This
area,  denoted as the "Old  Disposal  Area"  on Figure  3,  contains
miscellaneous  refuse  including bottles, cans  and  metal  debris.
Based on visual observations of this material, disposal  in this area
is  estimated  to have  occurred  20  to  30  years  prior  to  the
landfilling operation and,  as such,  is not within the scope of this
Record of Decision.

In a letter dated June 1, 1981, the Goodyear Tire and Rubber Company
notified the  First Piedmont  Corporation that some  of  the wastes
deposited at the First Piedmont Rock Quarry landfill were hazardous.
The First Piedmont  Corporation  filed a "Notification of Hazardous
Waste Site" form with EPA on June 5,  1981, listing solvents as one
of  the wastes  disposed of  at  the- landfill.     The EPA  Field
Investigation Team subcontractor sampled the media in the landfill
vicinity in July, 1983 to provide data in order for EPA to determine
                      /
                                -3-

-------
whether the landfill should be proposed for listing on the National
Priorities List (NPL).   Based on the  results  of this sampling, a
Hazard Ranking  Score  (HRS) of  37.85 was calculated  in 1985 for the
Site.  Based  on comments received by EPA,  the HRS was rescored to
30.16.  The Site was  listed  on the NPL on July 21, 1987, pursuant
to  Section   105  of  the  Comprehensive  Environmental  Response,
Compensation  and  Liability Act of 1980, as amended  (CERCLA).

Pursuant  to  Section  122(e)  of  CERCLA, EPA sent  Special Notice
Letters on May  6,  1986 to  initiate negotiations  with  the First
Piedmont Corporation,  Corning Glass Works, and The Goodyear Tire and
Rubber Company  (the Potentially  Responsible Parties or  PRPs)  to
perform a Remedial Investigation/  Feasibility Study (RI/FS) for the
Site.  On December 31, 1987, EPA signed an Administrative Order by
Consent  (Docket  No.  III-88-13-DC)  with  the  PRPs  to  undertake
performance  of  the  RI/FS   for  the  Site.    In February,  1988,
Westinghbuse  Environmental  and  Geotechnical  Services,  Inc.  was
contracted by the PRPs to perform the RI/FS.


3.  Co""|>mii,tY Participation

The RI/FS and Proposed Plan for the First Piedmont Rock Quarry site
were released to  the public  in April,  1991.   These documents were
made available to the public in both the administrative record and
an informational  repository  maintained at the  EPA  Docket  Room in
Region  3   and  at the  Pittsylvania  County Library  in  Chatham,
Virginia.    The notice  of  availability for these documents  was
published in the Danville Register-Bee and the Pittsylvania County
Star-Tribune.   The  purpose of  the  notice was  to  announce  the
beginning of a 30-day public comment period on the Proposed Plan for
the site.   The public comment period was held from April 10, 1991,
through May 9, 1991.

In accordance with  Section 117(a)(2) of CERCLA,  a public meeting
was held on April 16, 1991 at the Bethel Baptist Church on Route 36a
in Danville, Virginia.   At this meeting,  representatives from EPA
and the Virginia Department of Haste Management answered questions
about problems  at the  Site and  the remedial  alternatives  under
consideration.  The majority of the comments at the public meeting
were related  to the extent  of the groundwater contamination and
whether Site contamination  would affect  residential wells.    A
response to comments received during  this period is  included in the
Responsiveness Summary,  which  is  part  of this  Record of Decision.


4.   Scope and Role of operable Onit er Response Action Within site
     Strategy

The selected remedy will address  all  of the media impacted by the
low-level contamination at the Site; that is,  the landfill material,
leachate,   the Carbon  Black  Pile,  the Waste  Pile,  the  Northern
Drainage soils and sediments  and the drums and debris on the surface
of the landfill.   The Site does not appear  to pose any principal
                     >t
                               -4-

-------
threats.  EPA has determined that it is not warranted to split the
site remediation into separate operable units to address individual
media .


5.   Summary of site Characteristics

The RI  field activities and  analytical  program were  designed to
define  the  extent of environmental media  contamination,  identify
contaminant migration pathways, and provide data  to support an FS
of potential remedial  actions.  Samples from  the  leachate seeps,
surface  soils,   subsurface   soils,   surface   waters,   sediments,
bioassays, shallow and deep ground water,  and residential wells were
analyzed to  characterize the  quality  of these media.    Sampling
locations are depicted in Figures 4,  5, and 6.

The following discussion summarizes the results  from the RI sampling
program.  Figures 7,  8,  and 11, which are referenced below, contain
the  results of  the  RI  sampling data  for the   four  main  Site
contaminants: arsenic, barium, lead, and zinc.

Leaehate

The ground water  flowing through the wastes in the landfill surfaces
as leachate  along the western edge of the quarry.   The leachate
discharges  to  the north  pond  and  eventually  to the  Northern
Drainage.   Sampling  results  indicate that contamination  from the
landfill contents migrates to the north pond and Northern Drainage
via the transport and deposition of sediments in the leachate.  In
general, the highest  concentrations of contaminants detected in the
Northern Drainage were in the  samples closest to the quarry; levels
decreased with distance from the quarry area.   The contaminants of
concern found in the leachate are arsenic, lead (both of which are
carcinogens) , antimony, and barium.

        Water
Surface water  samples were collected  from the south  pond,  north
pond,  Southern Drainage,  Northern Drainage,  and Lawless  Creek.
Figure 7 denotes the sampling locations as well as the concentration
of the major Site contaminants in surface water.   These sampling
areas arc discussed below.

South Pond.

The sampling data of the water in the south pond indicate that this
water has not been adversely affected by the landfill.  A very low
level of 20 micrograms/ liter (M9/L) of zinc was the only significant
heavy  metal contaminant  detected  in  the  south pond.   The  zinc
concentration detected was below the  background level for surface
water zinc concentrations.
                                -5-

-------

                        EXPLANATION


                PIEZOMETER

                MOIITOft WELL :  *- SHALLOW  WELL
                             • -DEEP WELL

                SURFACE WATER AND SEDIMENT SAMPLING S

                SURFACE WATER FLOW MEASUREMENT STATIC'
            NOTESi
            LOCATIONS FP-2B3A. FP-3B3A. FP-2B7.
            FP-M7. FP-21B AND FP-3IB WERE SAMPLED
            DURING THE SECOND ROUND ONLY.

            TOPOGRAPHY PRODUCED FROM AERIAL
            PHOTOGRAPHY JANUARY 24.1S8S.

            CONTOUR INTERVAL * 2 Ft.
          W\    Westinghouse  Environment!
          )   and Geotechnical  Services,
             	 RICHMOND, VIRGINIA
FIRST PIEDMONT ROCK QUARRY
       ROUTE 719 SITE
         DANVILLE, VA.
                   CMC 11* »1
MONITORING/SAMPL ING
AND STUDY AREA  TOPI
                                 FIGURE 5

-------
       N
                   EXPLANATION;
                     SAMPLING N0»
                                                                       DESCRIPTIONi
                                                                       SOUTH POND (*QJ
                                                                       NOHTN rOC (AOJ
                                                                       LAWLESS
                                                                       LAWLESS CNCOC-OOWMSTRCAM MO)
                                                                          poo CBCOLI
                                                                       NORTH POMO CSOU
                                                                       LAWLCS*
                                                                       LAWLESS
                                                                       soa. iocxc
                                                                       SOJL-«ABTB»< (MM
                                                                             PIU
                                                                       saa.-fls.vorr OMT ru
                              HISTORICAL SITE SAMPLING LOCATIONS
PROJECT
FIRST  PIEDMONT ROCK
     QUARRY
DANVILLE, VA.
,W) Westinghouse
                                 SCALE:  N.T. s
JOB  NO!  4112-88-904 F
 F1G..NO U4	

-------
                                  Route 719
        Empty
             Unknown Tom   Oteayt  BM    John
                   Roytttr Cbtomw Wlnbuth Moflty
                       V
       Spring
                                  \
   X*
   so
   CO
   CD

   CO
   Sample location/I
O Well, no access
O Well, manhole access
El Well, In housing
             Not to Mate
                                     PRIVATE WELL SAMPLING LOCATION MAP
                                                                             Route 360
 PROJECT
FIRST PIEDMONT ROCK QUARRY
ROUTE 7I9 SITE
DANVILLE, VA.
                                  w) Westinghouse
                                                                     SCALE:
               N  T. S.
JOB  NO!  4H2-88-904D
                                                                               FIG NO:  6

-------
North Pond

In the north pond,  concentrations of arsenic, barium, cadmium, lead,
and zinc were detected in concentrations (58,  8420, 8, 21, and 219,
Mg/L, respectively)  which are slightly  above the Site background
levels.

Northern Drainage

The  Northern  Drainage  receives  flow  from  the leachate  which
accumulates  in  the north pond.   In the  upper Northern Drainage,
which  is closest  to the landfill,  arsenic,  barium,  iron,  lead,
manganese, and  zinc were detected at  concentrations  (13.7,  5600,
59,800,  4.1,  1540, and  48.1  Mg/L,  respectively) which  are  above
background levels.  The concentrations of these contaminants rapidly
decrease downstream from the landfill.   In fact, where the Northern
Drainage meets  the Lawless  Creek floodplain,  only very low levels
of barium, lead,  and zinc (109,  2.4,  and 32.8 Mg/L,  respectively)
were detected.

Southern Drainage

Zinc and cadmium  were  detected in the Southern Drainage at the
maximum  level  of  111,000 Mg/L  and  18.2 Mg/L,  respectively.   The
source of these high levels  of zinc and cadmium is considered to be
the Carbon Black Pile because: the pile is located upgradient of the
Southern  Drainage;   the  concentrations  of   zinc   were  higher
downgradient  of the  Pile than  upgradient of  the  Pile; and  the
reported sighting  of  empty zinc oxide bags during the construction
of access roads during  the  RI.   Infiltration of precipitation and
surface water into the  Carbon Black Pile may mobilize high levels
of zinc  from the pile.   The water then moves downgradient  in the
shallow subsurface soil and discharges to the surface water in the
Southern  Drainage.     Sampling   data   indicates  that  the  zinc
concentrations were inversely proportional to flow; in other words,
the  lower the  flow  the higher  the   zinc, concentrations.    This
indicates that  the zinc levels are not due to surface water runoff
but  to shallow subsurface  flow.   The  highest zinc levels  were
detected when there was no surface water runoff  flow except  at a
very small seep  in  the  lower Southern  Drainage.    The  Southern
Drainage also receives surface water runoff from the Waste Pile.

Lawless CreeX

As shown on Figure  7,  three  stations were  sampled  along Lawless
Creek:  FP-312 (the background station), which is approximately 900
feet north (upstream) of the bridge at Route 719; FP-313, which is
approximately 200  feet  below  the  bridge at Route 719; and FP-314,
which is approximately  1300 feet  south of the bridge.  At FP-313,
barium,  iron, manganese,  and  zinc were detected at concentrations
(20.5,  647,  79, and 26.5 Mg/L, respectively)  which are  above the
background concentrations detected at  FP-312.  At FP-314,  iron,
manganese, and zinc were detected at concentrations (604, 57.7, and


                                -6-

-------
16.3   Mg/Lf  respectively)   which   are   above   the  background
concentrations detected at FP-312.

Soils

Figure 8 depicts  the level  of the four major Site contaminants in
soil.  Landfill soil samples have concentrations of arsenic, barium,
cadmium, chromium,   lead,  nickel,  vanadium,  and  zinc  above Site
background  levels with barium, lead, and zinc found in the highest
concentrations.

The  Waste  Pile   soil samples  generally  show  concentrations  of
arsenic,  barium,   cadmium,  lead,  and  zinc  at  levels  exceeding
background  with  barium,  lead,  and  zinc  found  in  the  highest
concentrations.  The concentrations range from twice the background
level  for  arsenic to ten times the  background concentration for
lead.    The  Extraction  Procedure   (EP)   Toxicity  tests  showed
detectable  levels of barium  and  lead but only at concentrations
below  the  EP toxicity  criteria.    The  Toxicity Characteristic
Leaching Procedure  (TCLP)  test has  not been  performed  on this
material.

The Carbon Black Pile soil samples have concentrations of arsenic,
barium, cadmium,  lead,  and  zinc  above background levels.   Lead
concentrations were about twice the background level while zinc was
detected at concentrations ten times the background level.

Ground Water

The shallow and deep ground water  flow in  the Site vicinity is to
the west,  toward Lawless Creek,   as  shown in  Figures  9  and 10.
Ground water  at the Site occurs mostly in the  bedrock,  except in
areas of thicker overburden or ground  water discharge areas such as
Lawless Creek and the Southern and Northern Drainages.  Most of the
ground water is contained in the bedrock.  It  is locally controlled
by bedrock fractures; The shallow bedrock is probably sufficiently
fractured so that  it acts as a nearly homogenous aquifer.  Potential
contaminant  transport  via the  ground water   system  is  not  a
significant process  at the Site because the  landfill  occurs in an
area of upward shallow ground water flow. However, the ground water
chemistry data indicate that the landfill does have some effect on
the chemistry of the shallow ground water downgradient of the Site.
This effect is manifested mainly as a  change in  major ion chemistry
with  only  son* trace metals  detected at  levels slightly  above
background.   As  depicted  in  Figure 11,  zinc  was  detected  in
monitoring wells FP-006B,  FP-008A, and FP-008B at levels (504, 2050,
and 213 Mg/L, respectively)  which exceed the background  level of
61.3 M9/L.   The ground water sample from monitoring well FP-008A had
the only  level of  lead  (28.8 Mg/L),  which  exceeds  the  proposed
action level of 15 pg/L.
                                -7-

-------
            \
             4FP--10'
                                                       N
                                    LEGEND:


                                   ^ SURFACE WATER h  SEDIMENT SAMPLING  STATIC,
                                               SAMPLE  DESIGNATION
                                               ARSENIC
                                               BARIUM
                                               LEAD
                                          _   ZINC

                                     NOTE>
                                     CONCENTRATIONS IN ug/L

                                     BLANK INDICATES CONSTITUENT NOT
                                     DETECTED  ABOVE QUANTITATIVE LIMITS.
                                                                 FICUKE 7
TOTAL  rONrRNTRATTON9  POP
UPT»TO

-------
                                                                                                                                       EXPLANATIOt,
                                                                                                                                    SOURCE ARC* SAUPLI

                                                                                                                                    S*MPI-E OtSIOHATION
                                                                                                                                    (FT. ABOVE M.S.L
                                                                                                                                       POTENTtOMCTRIC (
                                                                                                                                       (FT. ABOVE MSL )
                                                                                                                                       WHERE  INFERRED
                                                                                                                                       CONTOUR WTCRVAI
                                                                                                                                       SUPPLEMENTAL C

                                                                                                                                       GROUND* AT ER  FLO
                                                                                                                                       ARE* OF UPWARD
                                                                                                                                       HYDRAULIC ORADI1
                                                                                                                                MOTE •  POTENTIOMETRIC D
                                                                                                                                '      K/29/89
                                                                                                                                 LOCATIONS FP-tOM. FP-K
                                                                                                                                 rp-soT.rr-t» AMD rp
                                                                                                                                 •AMPLKO OMIM THE K(
                                                                                                                                  TOPOARAPMT PHOOUCCO F
                                                                                                                                  PHOTOMAPHt MM. M. Iff
                                                                                                                                  CONTOIM MTCJMU. • t f 1
                                                                                                                   Westinghouse  Environment!
                                                                                                          mm    ond  Geolechnical Services,
                                                                                                                       RICHMOND,  VIRGINIA
                                                                                                    FIRST PIEDMONT ROCK  QUARRY
                                                                                                           ROUTE  719  SITE
                                                                                                             DANVILLE. VA.
      SHALLOW
GROUND-WATER
      REV  I /M/9O
   KATCMFCCT

//////  I    (
 ///,'  \  ».    I
                                                                                                                                   FIGURE  9

-------
                                                                                           N
                                                                                LEGEND:


                                                                               > SOIL SAMPLING LOCATION

                                                                               I  TEST PIT LOCATION


                                                                               > SOURCE AREA SAMPLING LOCATION
         SAMPLE DESIGNATION
         ARSENIC
         BARIUM
         LEAD
         ZINC

 NOTE'
 CONCENTRATIONS IN ug/L

 BLANK INDICATES CONSTITUENT NOT
 DETECTED ABOVE QUANTITATIVE LIMITS.


NOTES:


 LOCATIONS FP-203A. FP-303A. FP-207. FP-307.
 FP-210. AND FP-310 WERE SAMPLED DURING
 THE SECOND ROUND ONLY.
                                                                                 Zn-OJ
                                                                                                          FIGURE 8
SELECTED  METAL  CONCENTRATIONS  IN  SOIL  AND  SOURCE MATERIAL:  1" - lOO'-O"

-------
                      N
4- MONITOR WELL: A-SHALLOW. B-DEEP
              SAMPLE DESIGNATION
              ARSENIC
              BARIUM
              LEAD
              ZINC
••-at.
Pk-13
Zn-4321
   NOTE'
   CONCENTRATIONS IN ug/L

   BLANK INDICATES CONSTITUENT NOT  '
   DETECTED  ABOVE QUANTITATIVE LIMITS.
                                 FIGURE  U

-------
Vtfp^pg
jMCrr-^^
                                                                                             SOURCE AREA S»MPLII


                                                                                                 DESIGNATION
                                                                                               POTENTIOMETRIC (

                                                                                               ( FT ABOVE US L )

                                                                                               DASHED WHERE INI

                                                                                               CONTOUR INTERWAl
                                                                                               6ROUNOWATER Ft


                                                                                              POTENTIOMETRIC DAI
                                                                                           LOCATION*
                                                                                           rr-sor. rr-tio AMD FF-I K>
                                                                                                MMMS THE t/K>
                                                                                           ONLY.
                                                                                           TOfOOTAFMV PHOOUCEO F>
                                                                                           FMOTOMUMtV MM. M. IM
                                                                                           CONTOtM WTUMM. • • PT
W                                                                                 Westinghouse Environmento

                                                                          mm)  and Geolechnical Services,
                                                                                    RICHMOND, VIRGINIA
I  \ \v y« Vx vYrv
\V\Wv&
i\\N3n\  -
MWMCfl

FIRST PIEDMONT ROCK QUARRY

     ROUTE 719 SITE

      DANVILLE, VA
                                                                                          llft.1:

                                                                                                  DEEP

                                                                                             GROUND-WATER

                                                                                                  REV l/M/9<
                                                                                             KU;UKK 10

-------
Residential Walla

As depicted in Figure 6, EPA sampled the residential water sources
of ten homes in the Beaver Park community near the Site to determine
if the contamination from the Site was affecting the drinking water
of the residents.  Only two of the ten residential wells sampled had
levels above drinking water standards.   One well had a detection of
466 Aig/1 of  iron, above the  Secondary Drinking Water criterion for
iron of 300  Mg/1.   The other well had  a detection  of  333 Mg/1 of
iron and 65.1 /ig/1 of manganese,  above the Secondary Drinking Water
criteria  for  iron  and  manganese  of  300  M9/1  and  50  Mg/1,
respectively.   Because none of  the major Site contaminants were
detected in the residential  water,  these  results  confirm that the
Site contamination has  not affected any residential wells in the
Site vicinity.
Contaminants may  be transported  from the Site  via  the air  as  a
result of volatization  or  adsorption onto fugitive dust generated
at the Site.  However,  the few volatile compounds detected . during
the sampling  were found  in a  small area at  low concentrations.
Therefore, air transport of contaminants is insignificant,  as most
of the  landfill is covered by soil and most  of the contaminants
detected are non-volatile.

Drums

Solid samples were collected from the contents of two of the drums
on the  surface  of the landfill.  Low concentrations of chromium,
copper, and lead and higher concentrations of cadmium and zinc were
detected  in  one drum.   Low concentrations of cadmium,  chromium,
lead,  nickel, selenium  and vanadium  and  higher concentrations  of
copper and zinc were detected in the other drum sampled.

6*   Summary of Bite Risks

As part of  the  RI/FS  process,  a  Baseline  Risk Assessment  was
prepared for the  Sit* to characterize,  in the absence of remedial
action  (i.e.,  the  "no action"  alternative),  the  current  and
potential threats to human health and the environment that may be
posed by contaminants migrating in  ground water or surface water,
released to the air,  leaching through the soil,  remaining in the
soil,  or bioaccumulating in the food chain at the site.  Figure 12
provides a glossary  of  the key risk  terms from the  Baseline Risk
Assessment that are used in this section of the ROD.

Actual  or threatened releases  of hazardous substances  from this
Site,  if not addressed by implementing the response action selected
in this ROD, may  present an imminent and substantial endangerment
to public health, welfare, or the environment.
                                -8-

-------
                            FIGURE 12
                          KEY RISK TERMS
Carcinogen:  A substance that increases the incidence of cancer
in humans.

Chronic Daily Intake  (CDZ):  The average amount of a chemical in
contact with an individual on a daily basis over a substantial
portion of a lifetime.

Chronic Exposure:  A persistent/ recurring/ or long-term
exposure.  Chronic exposure may result in health effects (such as
cancer) that are delayed in onset, occurring long after exposure
ceased.

Chronic Reference Dose  (RfD):  An estimate (with uncertainty
spanning perhaps an order of magnitude or greater)  of a daily
exposure level for the human population/ including sensitive
subpopulations, that is likely to be without an appreciable risk
of deleterious effects during a lifetime.  Chronic RfDs are
specifically developed to be protective for long-term exposure to
a compound (as a Superfund program guideline/ seven years to
lifetime.

Exposure:  The opportunity to receive a dose through direct
contact with a chemical or medium containing a chemical.

Exposure Assessment:  The process of describing/ for a population
at risk/ the amounts of chemicals to which individuals are
exposed, or the distribution of exposures within a population, or
the average exposure of an entire population.

Hazard Index (HI):  The sum of more than one hazard quotient for
multiple substances and/or multiple exposure pathways.  The HI is
calculated separately for chronic/ subchronic, and shorter-
duration exposures.

Hazard Quotient:  The ratio of a single substance exposure level
over a specified time period (e.g./ subchronic) to a reference
dose for that substance derived from a similar exposure period.

Risk:  The nature and probability of occurrence of an unwanted/
adverse effect on human life or health, or on the environment.

-------
Risk Assessment:  The characterization of the potential adverse
effect on human life or health, or on the environment.  According
to the National Research Council's Committee on the Institutional
Means for Assessment of Health Risk, human health risk assessment
includes:  description on the potential adverse health effects
based on an evaluation of results of epidemiologic, clinical,
toxicologic, and environmental research; extrapolation from those
results to predict the types and estimate the extent of health
effect in humans under given conditions of exposure; judgements
as to the number and characteristics of persons exposed at
various intensities and durations;  summary judgements on the
existence and overall magnitude of the public-health program; and
characterization of the uncertainties inherent in the process of
inferring risk.

Slop* Factor:  The statistical 95% upper confidence limit on the
slope of the dose response relationship at low doses for a
carcinogen.  Values can range from about 0.0001 to about 100,000,
in units of lifetime risk per unit dose (mg/kg-day).  The larger
the value, the more potent is the carcinogen, i.e., a smaller
dose is sufficient to increase the risk of cancer.

Weight-of-Evidence Classification:  An EPA classification system
for characterizing the extent to which the available data
indicate that an agent is a human carcinogen.  Recently, EPA has
developed weight-of-evidence classification systems for some
other kinds of toxic effects, such as developmental effects.

-------
Human Health Risks

contaminants of Concern

The initial step of the  Baseline  Risk Assessment was to compile a
list  of key  indicator  contaminants,  those  which  represent  the
highest potential risk to human health.  The following 14 indicator
contaminants were  judged to represent the major potential health
risks at the Site:

               antimony                 lead
               arsenic                  manganese
               barium                   mercury
               benzene                  nickel
               bis(2EH)phthalate        selenium
               cadmium                  vanadium
               copper                   zinc

Of these  contaminants,  only arsenic,  benzene,  bis(2EH)phthalate,
cadmium, lead  and  nickel are  known  to cause cancer  in  humans or
laboratory animals and thus are classified as carcinogens.  Although
known to be disposed of in the landfill, sampling results have not
detected any levels of tetrachloroethylene that exceed health-based
standards .

         Assessment
The goal of  the exposure assessment is to determine  the type and
magnitude of human exposure to  the contaminants present  at,  and
migrating from, the Site. The exposure assessment was conducted to
estimate the Site risks if remedial action is not taken.

To determine if human and environmental exposure to the contaminants
of  concern   might  occur  in  the  absence  of  remedial  action,  an
exposure pathway analysis was performed.  An exposure pathway has
four  necessary elements: 1)  a source  and  mechanism  of chemical
release;   2) an environmental  transport  medium;   3)  a  human or
environmental  exposure  point,   and;    4)  a  feasible human  or
environmental exposure route at the exposure point.  The potential
for completion of exposure pathways at the Site is described in the
following sections.

Transport Pathways

For  any particular  site, there  may  be  a  variety  of potential
exposure routes, with either simple or complex pathways. The simple
pathways are of primary significance at the  Site.   Such simple
exposure routes for humans  include consumption of ground water,
bathing in ground  water,  consumption  of surface water, bathing or
play in surface water, ingestion of soil,  dermal exposure to soil,
and inhalation of fugitive dust emissions.  The ingestion pathways
are the most important at the Site, based on Site constituents and
contaminant distribution. Complex exposure routes are significantly
less important at the Site than  simple pathways because the primary
                     •»
                                -9-

-------
contaminants, metals, do not bioaccumulate to the extent that many
organics do and they are not relatively mobile in the environment.
Furthermore,  sampling data  indicate  that  only minimal  off-site
migration of  contaminants  has  occurred in any environmental media
to date.

Four transport pathways were evaluated for the Site: ground water;
air; soil;  and  surface water.   Although  ground  water and air are
potential  migration  pathways,  the  RI   data  indicate  that  the
potential extent of off-Site impacts via  the ground water and air
pathways is limited.   No  significant levels of contamination were
detected in the ground water downgradient  of  the  Site.  The private
wells  located in  Beaver  Park  are upgradient of  the  landfill.
Potential  exposure via  the air  pathway is minimal  because  the
transport of contaminants through the air is insignificant.

There  is minimal  potential  for  soil  transport  from the  Site.
However, there is potential for erosion of sediment from the Site,
which would transport adsorbed contaminants from the Site to surface
water  drainage  in  both   the   Northern   and Southern  Drainages.
Sampling data from both  drainages  indicate limited  movement  of
contaminants close to the landfill in these drainages.

The  surface water  migration  pathways include  the  Northern  and
Southern Drainages. Discharge from the north pond and  from leachate
seeps  enters  the  Northern Drainage  while  the  Southern  Drainage
receives discharge from the Waste Pile and the Carbon Black Pile.

Potential Exposure Points

The potential exposure level experienced by the receptor population
will be a function of the concentration of the contaminants at the
exposure point  and  the duration  of exposure.   Potential  human
exposure to contaminants could  be  by five exposure routes:  direct
exposure to source  material,  or direct exposure to ground water,
surface water, soil, and air.

Since it is not possible to rule out  future uses  of the Site, it is
appropriate to consider the possibility of residential development
of  the  land  adjacent  to  the  landfill.   Under  the  no-action
alternative, such development could result in drinking water wells
in the leachate and direct  contact of children and adults to site
contaminant sources such  as  drums,  seeps,  landfill  pond  water,
carbon black,  and the waste pile.  The potential points of exposure
to Site contaminants, assuming  residential  development,  are shown
below:

     •    Direct ingestion of leachate;
     »    Direct contact or incidental ingestion  of source material
          by children during play and by adults during gardening;
     •    Incidental ingestion of surface water from the north and
          south ponds by children during play;
     •    Ingestion of downgradient ground water;

                     s
                               -10-

-------
     •    Incidental  ingestion  of water  or  sediments from  the
          Northern or Southern Drainage by children during play;
     •    Use  of Lawless Creek  as a  source  of potable water by
          residents;
     •    Incidental  ingestion  of quarry soil  by  children during
          play and by adults during gardening;
     •    Incidental  ingestion of  soil in  Northern Drainage or
          Southern Drainage by  children during play and by adults
          during gardening;
     •    Inhalation of particulate matter.

The potential  points of exposure  described  above  are  based  on a
series of general assumptions as well as on specific assumptions for
the different  scenarios.   These assumptions are derived  from the
following EPA guidance documents:

          1)  Superfund Public Health Evaluation Manual;
          2)  Supplemental Risk Assessment Guidance  for the
              Superfund Program, Draft Final;
          3)  Exposure Factors Handbook;
          4)  Risk Assessment Guidance for Superfund Volume  if
              Human Health Evaluation Manual (Part A).

The following assumptions,  taken from the above guidance documents,
have been used in the Baseline Risk Assessment for the site:

     • adults weigh  70 kg,  adolescents weigh  36 kg,  and children
     weigh 20 kg;

     •lifetime drinking  water  exposures are based  on individuals
     living an entire lifetime  of 70 years, with 10 years childhood
     exposure, 5 years  adolescent exposure,  and  55 years  adult
     exposure;

     •lifetime exposures are based on individuals living an entire
     lifetime of 70 years at the Site;

     •concentrations  of  indicator chemicals below  the  detectable
     limit were  assumed  to be one-half the detection limit  if at
     least one sample had detectable concentrations;

     •if all samples of an indicator chemical had below detectable
     concentrations,  that chemical was assumed not to  be present
     in the sample;

     •for the average case exposure, calculations are based on the
     arithmetic mean concentrations of indicator chemicals;

     •bioavailability of metals  in ingested  soil and sediments is
     assumed to be 50 percent for the average case calculations;

The health criteria for comparison of exposures were obtained from
the  EPA  Superfund  Public  Health  Evaluation  Manual,  personal
correspondence from  EPA regional representatives or  from  the EPA

                               -11-

-------
Integrated Risk Information System  (IRIS).   The  health criteria
utilized in the risk assessment are shown on Table 1.

Exposure Point Concentrations

Data  gathered during  the RI  are adequate  to  predict potential
exposure  concentrations  if the  Site  has  reached  steady-state
conditions  (i,e.,  when the rate  of  transport of  contaminants is
stable and in^equilibrium with the environment). In the absence of
an established trend in historical data indicating the contrary, the
Site was considered to have reached steady-state conditions.

The maximum  and average concentrations of the  fourteen indicator
contaminants were  derived for  each  of the  affected media.   The
average  concentrations   are   the  arithmetic   means   of  sample
concentrations.  The maximum concentrations  are  the lesser of the
upper 95 percent confidence interval or the maximum observed value.
Figure 13 depicts the maximum and average concentrations of ground
water and surface water for the indicator contaminants.

Toxicity Assessment

The risks estimated in the Baseline Risk  Assessment are potential
risks, based on the assumption  that the Site is developed or used
in the future such that there will be some degree of exposure.

Cancer potency factors (CPFs)  were developed by EPA's Carcinogenic
Assessment Group to estimate excess lifetime cancer risks associated
with exposure to potentially carcinogenic chemicals.   CPFs, which
are  expressed  in  units  of  (mg/kg-day)"1, are  multiplied  by the
estimated intake of a potential carcinogen, in mg/kg-day, to provide
an  upper-bound  estimate  of  the  excess  lifetime  cancer  risk
associated with exposure at that intake  level.   The  term "upper
bound" reflects a conservative estimate of the risks an exposure to
a chemical for which a  CPF has been developed. Use of this approach
makes underestimation  of the  actual cancer  risk highly unlikely.
CPFs are derived from the results of human epidemiological studies
or chronic animal  studies from which human  factors  are estimated
based on animal-to-human extrapolation and by applying uncertainty
factors which  would not  underestimate  the potential  for adverse
effects to occur.

Reference  doses  (RfDs)  were developed   by  EPA to indicate the
potential for  adverse health effects  from exposure to chemicals
exhibiting non-carcinogenic effects.   RfDs, which are expressed in
units of mg/kg-day, are estimates  of lifetime daily exposure levels
for humans, including sensitive individuals,  that is not likely to
be without an appreciable risk of adverse health effects.  Estimated
intakes of chemicals from environmental media (e.g., the amount of
a  chemical  ingested   from contaminated  drinking  water)  can  be
compared to the RfD.   RfDs are  derived from human epidemiological
studies or animal  studies to which uncertainty  factors have been
applied  (e.g.,  to  account for  the use  of animal data  to predict
effects on humans). These uncertainty factors help ensure that the

                               •=12=

-------
                             TABLE 1

                        TOXICITY CONSTANTS
                         ORAL
INHALATION
Indicator
Chemical
Antimony
Barium
Cadmium
Copper
Lead
Manganese
Mercury
Nickel
Selenium
Vanadium
Zinc
Arsenic
Benzene
Bis(2eh)
  Phthalate
Reference
Dose
4e-4
5e-2
5e-4
3.7e-2
1.4e-4
5e-l
2e-3
2e-2
2e-3
9e-3
2e-l
NA
NA
2e-2
Cancer
Potency
Factor
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
1.75e
2 . 9e-2
1.4e-2
Reference
Dose
4e-4
1.46-4
5e-4
. le-2
4.3e-4
5e-l
5.le-5
2e-2
le-3
9e-3
le-2
NA
NA
20-2
Cancer
Potency
Factor
NA
NA
e.ieo
NA
NA
NA
NA
1.1960
NA
NA
NA
5e+l
2.9e-2
NA

-------
                        FIGURE  13
                        Ground Hater            Surface Hater
                              (Concentrations in ug/1)
Indicator	
Cheaucal
                  Average     MaxiauB    Average     Heziaua
Antimony
Arsenic
Bariiia
Benzene
Bis (2 -EH)
phthalate
Cadniuo
Copper
Lead
Manganese
Mercury
Nickel
Selenium
Vanadium
Zinc
1.117
BOL
120.9
BOL

7.5
BOL
4.867
BDL
595.6
BOL
BOL
BDL
BOL
140.0
1.317
BDL
139.4
BOL

9.306
BOL
6.73
BDL
1245
BOL
BOL
BOL
BOL
223.3
1.717
17.16
1646
BDL

BDL
23.22
14.21
3.932
901.7
BOL
20.07
BOL
BOL
15546
2.59
30.56
2786
BDL

BDL
41.11
19.85
6.36
1312
BDL
25.11
BOL
BDL
29619

-------
RfDs  will  not  underestimate  the  potential  for  adverse  non-
carcinogenic effects to occur.

The Baseline Risk Assessment  is based  on a series of conservative
assumptions that, taken together, provide a significant margin of
safety  for  estimating potential  risk  from  the  Site.    These
assumptions include the following:

     • The Site will be developed for  residential purposes in the
     future.

     • Children play, or adults garden,  daily or every other day for
     nine months of the year.

     • Children play,  or adults garden,  in source areas or in known
     contaminated areas of the Site.

     • Exposed individuals have an average lifespan of 70 years.

     • Contaminated  soil concentrations do not  account for  the
     presence of clean soil placed over the contaminated material.

     • Individuals will be maximally exposed to contaminants; that
     children and adults are exposed to source material or to quarry
     soil;  that children  play in  the  Northern and/or  Southern
     Drainages every day that they play outside;  and that exposure
     is always to contaminated environmental media.

Based  on  the exposure assumptions,  exposure  scenarios,  sampling
data, and health criteria, the human health risks were calculated
for. the  maximum and average case exposures.   However,  only  the
average case exposure  levels were utilized by EPA  in  determining
whether remedial action would be  warranted for any of  the media.
These risk scenarios are depicted in the Baseline Risk Assessment.

Excess lifetime cancer risks are determined  by multiplying  the
intake level  with the cancer potency factor.   These risks  are
probabilities that are generally  expressed  in  scientific notation
(e.g., 1x10   or 1E-6).  An  excess  lifetime cancer risk  of  1x10
indicates that, as a plausible upper bound,  an individual has a one
in one million chance of developing cancer as a result  of  site-
related exposure to a carcinogen over a 70-year lifetime under the
specific exposure conditions at a site.

The excess lifetime cancer risk determined  under the average case
exposure is 6.46 x 10   from the ingestion of quarry leachate due to
arsenic contamination.  In other  words,  if no remedial action is
taken, six  additional people per one  thousand  have a  chance of
contracting cancer as a result of exposure to the arsenic if, in the
future, the quarry leachate is used as  a residential water source.

Potential  concern  for  non-carcinogenic  effects   of  a  single
contaminant in a single medium is expressed as the hazard quotient
(HQ)  (or the  ratio  of  the estimated  intake derived  from  the

                               -13-

-------
contaminant concentration  in a given medium to the contaminant's
reference dose).  The Hazard Index (HI)  is calculated by adding the
HQs  for  all contaminants within  a medium or across  all  media to
which a given population may reasonably be exposed.  The HI provides
a reference point for gauging the potential significance of multiple
contaminant exposures within a single medium or across media.

To determine  the human health effects from the non-carcinogenic
contaminants,  EPA uses the  HI.   Any media with a cumulative HI
greater than 1.0 is considered  to pose a risk to  human health.  With
His of 3.39, 11.66,  and 193.88, respectively, antimony, barium, and
lead  also pose  human health  risks through ingestion of  quarry
leachate.

The Baseline Risk Assessment identified  lead as a contaminant which
represents a risk to human health assuming incidental ingestion of
soil  by children playing  in source material because it has an HI
of 1.58.  The  exposure  to  lead by children playing in quarry soil
equates to a HI of 1.39.
10'4 or have an HI  equal to or greater than  1.0  are summarized on
The Site media which exceed the EPA acceptable risk range of 10"* to
10"& or h
Table 2.

Environmental Risks
Habitat areas influenced by surface water or animals that might come
into contact  with  contaminated surface water or  soils within the
Site itself have the highest potential to  be  adversely affected.
Although an intensive ecological risk assessment was not conducted,
an indication of potential risk to wildlife  and the environment can
be assessed from toxicity testing (bioassays) and the human health
risk assessment.  Because there is the potential for contamination
of surface water in the immediate vicinity of the landfill, samples
of surface water and sediments were collected along  the Northern
Drainage  and  Lawless  Creek for  aquatic toxicity  testing.   The
samples collected underwent the following tests:

     •    Four 7-day chronic toxicity tests, using Ceriodaphnia and
          fathead  minnows,  were  conducted on  the surface water
          samples.   Three of the tests were undiluted samples and
          one contained a full set of serial dilutions.

     •    Four  7-day  chronic toxicity  tests,  using  Ceriodaphnia.
          were conducted  on the  sediment elutriate.   All of these
          tests were full serial dilutions.

The test  results indicate that the surface water  in  the Northern
Drainage and  in Lawless Creek were not acutely toxic to the test
organisms.  However,  surface water from the upper reaches of the
Northern  Drainage  did result  in significant decreases  in growth
among  fathead  minnows  and reproduction   among  Ceriodaphnia  at
concentrations above 30 percent dilution.


                               -14-

-------
     TABLE  2




MEDIA OF CONCERN
Medium
Quarry Leachate


Source Material
Quarry Soil
Contaminant
Antimony
Barium
Lead
Arsenic
Lead
Lead
HI Cancer Risk
3.39
11.66
193.88
NA
1.58
1.39
NA
NA
NA
6.46e-3
NA .
NA

-------
Significant Sources of Uncertainty

Discussion of  general  limitations inherent in the risk assessment
process as well as the  uncertainty related to some  of  the major
assumptions made in this assessment are included below:

1.  The Baseline Risk  Assessment is based upon the data collected
during the RI and uses RI results of limited sampling to represent
environmental concentrations over large areas.  This extrapolation
contributes to the uncertainty of the risk assessment.

2.  The Carbon Black Pile is considered to be the source of the zinc
found  in  the Southern Drainage.   If the  levels  of  zinc  are not
significantly reduced  after  remediation  of the Carbon Black Pile,
the source of the zinc may have to be investigated further.

3.   Environmental  risks are  assumed to occur  in  the  Southern
Drainage  because  the levels of  zinc greatly  exceed  the  Virginia
water quality standard.  However, the extent  of the toxicity is not
known  because  toxicity tests were  not performed  on  the  water or
sediments since this contamination was identified late in the RI.

7.   Description of Alternatives

In accordance with 40  C.F.R. $  300.430,  remedial  response actions
were identified and  screened for effectiveness, implementability,
and cost during the FS to meet the remedial action objectives at the
site.  The technologies that  passed  the screening were assembled to
form remedial alternatives.  The developed alternatives  were then
evaluated and compared  to nine criteria required by the National Oil
and Hazardous Substances  Contingency Plan, 40 C.F.R. Part 300 (NCP).
The FS evaluated a variety of technologies used in the development
of alternatives for addressing the landfill wastes, the Carbon Black
Pile, the  Waste Pile, the Northern Drainage soils and sediments, and
the landfill leachate.   The  technologies and approaches  contained
in the alternatives listed below have been determined to be the most
applicable for this Site.   The  description of the  alternatives
reflect the descriptions in the FS.

Common Elements

Except for Alternative 1 ("No Action"),  each remedial alternative
for the Site includes the following elements:

Ground Water Monitorlag.  Ground water monitoring will be used to
evaluate  the protectiveness  of  the remedial  action because waste
will be left in place.   Exact monitoring points will be determined
during the remedial design phase and will be  in accordance with the
requirements of the Virginia  Hazardous Waste Management Regulations
(VHWMR),  Section 10.5.    The  ground water  monitoring  will  be
performed for at least thirty years in accordance with the VHWMR.
Because tetrachloroethylene  was  disposed of in the landfill,  the
monitoring must comprise the  full priority pollutant list.  When it
is  demonstrated that only  a limited number of contaminants  are
                     «f
                               -15-

-------
detected over a period of tine, a request can be made to  limit the
monitoring to those contaminants.

Institutional Controls.  Institutional controls, including fencing
and a deed restriction will prevent access to the Site and prohibit
future development of the Site.

Leachate Treatment.  Leachate will be treated until the contaminant
levels meet a 10*6 risk level and an HI less than 1.  At present, the
length  of  time required for treatment of leachate  is  not known,
however, a longer treatment  period is anticipated for Alternatives
7 and 8 in which the ground water  flow through the landfill will be
reduced than for Alternatives 3 through 6 in  which the ground water
flow is not reduced.  In order to evaluate the alternatives on the
same  basis,  the present  worth  costs  developed  in  the FS  for
Alternatives 3 through 9 include 30 years of leachate  collection and
treatment.

Alternative l- No Action

The NCP,  40 C.F.R.  Part  300, which  regulates  Superfund response
actions, requires  that a "no action"  alternative  be evaluated at
every NPL  site in order  to establish a baseline  for comparison.
Under this alternative, EPA would take no further action at the Site
to prevent exposure to the contaminated media or to  reduce risk at
the Site.

Alternative 2- Institutional Controls

Capital Cost:         $44,200
Annual O&M Cost:      $15,690
Present Worth:       $285,400
Months to Implement:         4

.Alternative  2  consists  of  the  implementation of  institutional
'controls and long-tern ground water monitoring.  The institutional
controls include complete fencing of the Site to restrict access and
a deed restriction to prohibit future development of the  Site.

Alternative a- Excavation  and  Off-Site  Disposal of Non-Landfill
               Wastes, Landfill Cap, and Leachate Treatment.

Capital Cost:       $1,258,000
Annual O4M Cost:       $56,110
Present Worth:      $2,120,500
Months to Implement:     6-8

The major  features of Alternative 3 include implementation of the
institutional controls as described in Alternative 2,  excavation and
off-site disposal of the estimated 800 cubic yards from the Carbon
Black  Pile,  Waste  Pile,   and  the  Northern  Drainage soils  and
sediments;  off-site  disposal of  the surface  drums  and debris;
installation  of  a   RCRA  Subtitle  C  cap  over   the   landfill;

                     *
                                -16-

-------
construction of  a passive leachate treatment  unit;  and long-term
ground water monitoring.

After the material from the Carbon Black Pile, Waste Pile, and the
Northern Drainage  is excavated and removed,  the effectiveness of
this action on  the zinc level in the Southern Drainage surface water
and zinc mobility in drainage  sediments  would be assessed.   The
excavated areas  will be backfilled with clean soil,  contoured to
promote run-off,  and planted with vegetation  to control erosion.
Run-off control berms will be constructed in the Northern Drainage.
The berms will act as retention structures to reduce peak run-off
flows from  the  quarry  cap and minimize  erosion in  the Northern
Drainage.   The  surface  drums would be disposed  of at an approved
off-Site hazardous waste facility in accordance with the VHWMR.

To facilitate the landfill cap construction,  the water in the north
and south ponds will be pumped to tanker trucks for transport to a
Publicly Owned Treatment Works  (POTW)  for treatment and discharge.
The water must be tested to determine if it meets the pretreatment
requirements of the POTW.  The cap will include a passive leachate
treatment system which will  consist of  a  tee-shaped  trench system
constructed at the head of the Northern Drainage.  The top of the
tee will act as an  interceptor trench with the stem of  the tee
constituting the treatment area with filter zones and adsorptive/ion
exchange zones.

Alternative 4- Excavation, Treatment and On-8ite Disposal of Non-
               Landfill   Wastes/   Landfill   Cap,  and   Leachate
               Treatment.

Capital Cost:       $1,173,000
Annual O&M Cost:       $56,110
Present Worth:       $2,035,000
Months to Implement:      6-8

The major features of this alternative include implementation of the
institutional controls as described in  Alternative 2; excavation,
stabilization/solidification  treatment  (if required)  and on-site
disposal of  the Carbon Black  Pile, Waste Pile, and  the Northern
Drainage soils  and sediments;  off-site  disposal of  the landfill
surface drums and debris;  installation of a RCRA Subtitle C cap over
the landfill; construction of a passive leachate treatment unit; and
long-term monitoring.

This alternative is identical to Alternative 3 with one additional
element.  Prior to  disposal,  the excavated material,  soils,  and
sediments from the Carbon Black Pile,  Waste Pile, and the Northern
Drainage will  be  tested  utilizing the  Toxicity  Characteristic
Leaching  Procedure   (TCLP)   to  determine  if  they   are   RCRA
characteristic wastes.   If such wastes are  determined to be RCRA
characteristic,  they will  be treated  with  the  stabilization/
solidification process and disposed of on-Site in the landfill prior
to capping  the  landfill.   If the wastes are determined  not  to be


                               -17-

-------
RCRA characteristic, they will be disposed of in an off-Site solid
waste landfill, as described in Alternative 3.

Alternative 5- Excavation/ Treatment and either On-site or Off-site
               Disposal of Non-Landfill Wastes/  Landfill Cap,  and
               Leachate Treatment at a POTW

Capital Cost:       $1,136,000
Annual O&M Cost:       $66,200
Present Worth:      $2,154,000
Months to Implement:     6-8

The major features of this alternative include implementation of the
institutional controls as described in Alternative 2; excavation,
stabilization/solidification treatment (if required) and either on-
Site or off-Site disposal of  the Carbon Black Pile, Waste Pile,  and
the Northern Drainage soils and sediments;  off-Site disposal of the
landfill surface drums and debris; installation of a RCRA Subtitle
C cap over the  landfill;  collection of leachate  with treatment at
a POTW; and long-term monitoring.

The elements  of this alternative  are identical to Alternative 4
except one: the  landfill leachate would be collected and transported
to a POTW  for off-Site treatment  and disposal rather than treated
on-Site in the  passive treatment  system constructed  under the  cap
as in Alternative 4.  It is estimated that 3,000 gallons of landfill
leachate would be generated on a average daily basis.   To maximize
leachate  collection,  the collection system would be constructed
under the landfill cap.   If, during operation, this  collection
system does not collect  all  of the  leachate, a  second collection
trench would be constructed outside of the landfill cap.

Alternative 6- Excavation, Treatment and either On-Site or Off- Site
               Disposal of Non-Landfill wastes,  Landfill cap,  and
               On-Site Leachate Treatment

Capital Cost:       $1/211,000
Annual O&M Cost:       $73,270
Present Worth:      $2/340,000
Months to Implement:     10-12

The major features of this alternative include implementation of the
institutional controls as described in Alternative 2; excavation,
stabilization/solidification treatment (if required) and either on-
Site or off-Site disposal of  the Carbon Black Pile/ Waste Pile,  and
the Northern Drainage soils and sediments;  off-Site disposal of the
landfill surface drums and debris; installation of a RCRA Subtitle
C cap over the  landfill;  collection of landfill  leachate with  on-
Site treatment; and long-term monitoring.

The elements  of this alternative  are identical to Alternative 5
except one:  the landfill leachate  would .be treated  on-Site in a
wastewater treatment plant and discharged to Lawless Creek.   The
discharge  to  Lawless  Creek  must  meet  the  Virginia  Pollution
                     t
                               -18-

-------
Discharge Elimination System  (VPDES)  effluent discharge limits as
established  by the  Virginia  State  Water Control  Board  (VSWCB).
Bench-scale tests of the leachate treatment system would be required
during the design phase.

Alternative 7- Excavation, Treatment and either On-Site or Off-site
               Disposal  of  Non-Landfill  wastes/  Landfill  cap,
               Construction of Slurry Walls/ and Leachate Treatment
               either On-Site or at POTW

Capital Cost:       $1,282,000
Annual O&M Cost:       $39,450
Present Worth:      $1,889,000
Months to Implement:         8

The major features of this alternative include  implementation of the
institutional controls as described  in Alternative 2; excavation,
stabilization/solidification treatment (if required), and either on-
Site or off-Site disposal  of the Carbon Black Pile, Waste Pile, and
the Northern Drainage soils  and sediments; off-Site disposal of the
landfill surface drums and debris; installation of a RCRA Subtitle
C cap over  the landfill;  construction  of slurry  walls around the
inside  perimeter of the quarry highwall; leachate collection with
treatment either  on-Site  or at a POTW;  and  long-term monitoring.

The elements  of this alternative combine the  leachate treatment
options of  Alternatives 5  and 6  and  are identical to the other
elements of these two alternatives except one:  slurry walls would
be constructed around the inside  perimeter of the quarry highwall
in order to  prevent the horizontal flow of ground  water into the
landfill, thus reducing the total amount of  leachate flowing from
the landfill.   However,  leachate production cannot be completely
eliminated by  the  slurry walls  because  ground  water  enters  the
bottom of the landfill due to the fractured bedrock and  flows upward
through the landfill.

Alternative 8- Excavation/ Treatment and either On-Site or Off-Site
               Disposal of  Non-Landfill Wastes,  Consolidation  of
               Landfill Waste  including a Liner  and aa Underdrain
               System/ Landfill Cap, and Leachate Treatment either
               On-Site or at POTW

Capital Cost:       $4/015/633
Annual O&M Cost:       $28/150
Present Worth:      $4/450/000
Months to Implement:         8

The major features of this alternative include  implementation of the
institutional controls as described  in Alternative 2; excavation,
stabilization/solidification treatment (if required); and either on-
Site or off-Site disposal  of the Carbon Black Pile/ Waste Pile, and
the Northern Drainage soils  and sediments; off-Site disposal of the
landfill surface drums and debris; excavation and consolidation of
all of the landfill  wastes onto a liner and under drain system in the
                     t
                               -19-

-------
quarry  area;  installation of  a  RCRA Subtitle  C  cap over  the
landfill; leachate collection with treatment either at a POTW or at
an on-Site treatment plant; and long-term monitoring.

The elements of this  alternative are identical to Alternative 7
except  one:  prior  to  installing  the  landfill cap, the  landfill
wastes  would be excavated, consolidated,  and placed on top  of a
liner in the quarry area to remove the wastes from the ground water,
thus reducing the production of leachate from the landfill.

Alternative  9- Excavation, Treatment and either On-8ite or Off-site
               Disposal    of    Non-Landfill   Wastes,    In-Situ
               Stabilisation of Landfill Wastes, and Landfill Cap

Capital Cost:       $4,573,000
Annual O&M Cost:       $23,750
Present Worth:      $4,940,000
Months to Implement:     6-8

The major features of this alternative include implementation of the
institutional controls as  described in Alternative 2;  excavation,
stabilization/solidification treatment (if required), and either on-
Site or off-Site disposal of the Carbon Black Pile, Waste Pile and
the Northern Drainage soils and sediments;  in-situ stabilization or
solidification  of  the  landfill  wastes;   installation  of  a  RCRA
Subtitle C cap; and long-term monitoring.   Prior to implementation
of this alternative, treatability tests would have to be performed
in  order  to  determine  the  proper  stabilization/solidification
reagents.

The elements of this alternative are  identical to Alternatives 3
through  8 except  that most  of  the  landfill  contents would  be
stabilized or solidified in place.   The 3,000 cubic yards  of soil
cover  and the  65,000 cubic  yards  of landfill wastes would  be
stabilized or solidified in place, thereby reducing the solubility
of the metallic  contaminants  (metals)  and  producing a  waste which
is  of  low  permeability  and  leachability  such  that  leachate
production,  and  the  need  to  collect  or  treat  leachate,  is
eliminated.  The buried drums and tires would not be stabilized or
solidified because the drill mechanism cannot penetrate and properly
blend them.  Therefore, the drums and tires would be excavated and
disposed  of  off-Site at  a hazardous waste facility in accordance
with the VHWMR.
8.

The nine remedial action alternatives described above were assessed
in accordance with the nine evaluation  criteria as set forth in the
NCP  at  40  C.F.R.  S  300.430(e) (9).    These nine  criteria  are
categorized  below into three groups:  threshold  criteria,  primary
balancing criteria, and modifying criteria.
                               -20-

-------
     THRESHOLD CRITERIA

     1. Overall protection of human health and the environment; and
     2. Compliance with applicable or relevant  and appropriate
        requirements  (ARARs).

     PRIMARY BALANCING CRITERIA

     3. Long-term  effectiveness and permanence;
     4. Reduction  of  toxicity, mobility,  or volume  through
        treatment;
     5. Short-term effectiveness;
     6. Implementability; and
     7. Cost.

     MODIFYING CRITERIA

     8. State acceptance; and
     9. Community  acceptance.

These evaluation criteria relate directly to requirements in Section
121 of CERCLA, 42  U.S.C. Section 9621, which determine the overall
feasibility and acceptability of the remedy.

Threshold criteria must  be satisfied in order for  a remedy to be
eligible for  selection.    Primary  balancing criteria are  used to
weigh  major trade-offs  between remedies.    State   and community
acceptance are modifying criteria formally taken  into account after
public comment is  received on the Proposed Plan.   A summary of the
relative performance of the alternatives with respect to  each of the
nine  criteria  follows.    This  summary  provides   the  basis  for
determining  which  alternative  provides the "best  balance1*  of
tradeoffs with respect to the nine evaluation criteria.

1.   Overall Protection of Human Health and the Environment

A primary requirement of CERCLA is that the selected remedial action.
be protective  of human health and  the environment.  A remedy is
protective if it reduces current and potential risks to acceptable
levels within  the established risk  range posed by  each  exposure
pathway at the Site.

Alternatives  1  and   2  accomplish  none  of  the above.    Because
contaminants are migrating and contaminant  levels  already exceed
health-based levels,  Alternatives 1  and  2 would  not be protective
of human health or  the environment.   Since protection of  human
health and  the environment  is a threshold criteria for any Superfund
action, these two alternatives cannot be  selected and thus will not
be evaluated any further with regard to the nine criteria.

The selected  alternative.  Alternative 5,  is protective of  human
health  and the  environment  because  it would  reduce  the  risks
associated with direct contact of the Site contaminants to within
the EPA acceptable risk range by excavation  of  and,  if required,

                               -21-

-------
stabilization/solidification treatment of the non-landfill wastes;
off-Site  disposal of the  non-landfill  wastes, surface  drums and
surface debris;  installation of  a RCRA  Subtitle  C cap  over the
landfill; and collection and  treatment  of leachate. Alternative 9
is the most protective of human health and the environment because
it entails treating all of  the contamination at the Site, including
the  landfill  wastes  which  would eliminate  the  production  of
leachate.  Alternatives  3,  4, 6,  7, and  8 would  provide adequate
protection of  human  health and  the  environment by  eliminating,
controlling or reducing Site-related risks through a combination of
treatment, engineering controls,  and  institutional  controls.   The
slurry walls installed under Alternative 7 and the consolidation of
the landfill wastes in Alternative 8 do not provide any additional
protection because their purpose  is to  reduce,  but  not eliminate,
leachate  production,  thus  leachate  treatment  would  still  be
required.

2.   Compliance with ARARs

This criterion addresses whether  or not a remedy will  meet all of
the Applicable or Relevant and Appropriate Requirements (ARARs) of
other environmental statutes and/or provide grounds for invoking a
waiver under the NCP at 40 C.F.R.300.430(f)(1)(ii)(c).

All alternatives will meet the respective ARARs  of Federal and State
laws.   Prior to disposal  in  an off-Site  solid waste  facility in
accordance with the VSWMR,  the  non-landfill wastes  will undergo a
TCLP to determine if they are RCRA characteristic wastes.  If such
wastes are determined to be characteristic, they will be treated by
stabilization/solidification. The cap construction in Alternatives
3 through 9  will  meet the  action-specific ARARs,  including a RCRA
Subtitle C cap  and the full range  of monitoring for  thirty years
because tetrachloroethylene was disposed into the landfill.

Although    the    landfill   contains    RCRA-regulated    wastes
(tetrachloroethylene), the  RCRA Land  Disposal  Restrictions (LDRs)
are  not  applicable  requirements  to Alternatives  3  through  9.
Alternatives 3 through 7 do not provide for treatment or placement
of  the landfill  wastes.   Although  Alternative 8 includes  the
excavation and  placement  of  landfill  wastes,  the  LDRs  are  not
applicable requirements because the wastes are consolidated in the
same Area of  Contamination and the wastes are not treated.  The LDRs
are not applicable to Alternative 9 because the wastes are treated
in place and no placement of treated waste occurs.

In all alternatives, the water from the north and south ponds will
be tested prior to discharge to the POTW to assure compliance with
the pretreatment requirements of the POTW.  In Alternative 5, and,
possibly Alternatives  7  and 8,  the leachate will also have to be
tested  for  compliance with the pretreatment requirements  of the
POTW.   Any  water to  be  discharged  which does  not  meet  the
pretreatment requirements must be pretreated on-Site to meet these
requirements.  Alternative  6, and,  possibly Alternatives 7 and 8,
will to meet the VPDES effluent discharge requirements established

                     "         -22-

-------
by  the VSWCB.   The residuals  of any  on-Site treatment  will be
disposed of in a hazardous waste facility because the water was in
contact with the landfill wastes.

The loss of the wetland areas of the north and south ponds and the
small  stands  of cattail and  phragmites in the  Northern Drainage
will  be mitigated  by  replacement with  plantings of  additional
wetland species in the berms along the Northern Drainage.

3.   Lona-Term Effectiveness and Permanence

This  evaluation criterion addresses  the long-term protection of
human health and the environment once remedial action clean-up goals
have been achieved, and focuses on residual risks that will remain
after completion of the remedial action.

The selected alternative, Alternative 5, would reduce the risk posed
by the contaminated media.  Even though the landfill contents would
not be  treated, the  risk of  exposure would be reduced  to the EPA
acceptable  risk range  by  installing a  RCRA  Subtitle  C  cap and
implementing institutional controls to prohibit development of the
Site.     Because  Alternative   9   incorporates   solidification/
stabilization treatment of  the landfill wastes, it does not require
long-term management of waste on-Site.  As such, Alternative 9 would
have a greater  degree  of permanence  than Alternatives 3 through 8
where the landfill wastes are left in-place without any treatment.
Bench scale testing would be required to confirm the effectiveness
of Alternative 9's treatment system.   Alternatives 3 through 9 all
provide for the off-site disposal  of  the surface drums  and debris
as well as  the excavation  and disposal of the Carbon Black Pile,
Waste Pile,  and the Northern Drainage soils and sediments, thus they
are  all equal  with respect  to  the  lack of  residual risk  from
contaminated materials.

Alternative 5,  with collection  and  discharge  to a  POTW, has  a
greater degree of permanence than Alternatives 3 and 4,  which rely
on passive  treatment systems on-Site.   Alternative 5 would  also
allow the natural flow of ground water through the landfill contents
in order to  continue the flushing of contaminants from the landfill,
which  should   decrease the  total period in  which  contaminated
leachate is produced and requires treatment.   By reducing the time
needed for leachate treatment, Alternative 5 offers a higher degree
of long-term effectiveness than Alternatives 7  and 8  which reduce,
but not eliminate, the  flow of ground water through  the landfill.
The  on-Site  leachate   treatment   system of  Alternative  6  and,
possibly. Alternatives 7 and 8  (if on-Site treatment  is utilized)
have the least long-term effectiveness.  Since the treatment system
would  be  on a  remote  unmanned location, a  malfunction  could go
undetected and cause a  release of inadequately treated water to the
environment.
                               -23-

-------
4.   Reduction of Toxicitv. Mobility, or Volume through Treatment.

This evaluation criterion addresses the degree to which a technology
or remedial alternative  reduces  the  toxicity,  mobility,  or volume
of a hazardous  substance.   Although Section 121(b)  of  CERCLA,  42
U.s.c.   Section  9621(b),  establishes  a preference for  remedial
actions that  permanently and  significantly reduce  the  toxicity,
mobility,  or volume of hazardous substances,  EPA  expects  to use a
combination  of  treatment  and  engineering controls  to  achieve
protection of human health and  the environment,  as set forth in the
NCP at  40  C.F.R. S 300.430(a)(iii).   EPA's expectations  are that
treatment should be utilized whenever principal threats occur and
that  containment  will  be considered   for wastes that  pose  a
relatively low long-term threat or where  treatment is impracticable.

Alternative 5 is in conformance  with these expectations since the
low-level  risks  associated with the   landfill  wastes  will  be
contained and the  non-landfill wastes,  surface drums and landfill
leachate will be treated.

Alternatives 4 through 9 provide for treatment of the Carbon Black
Pile, Waste  Pile,  and the  Northern  Drainage  soils and sediments
should such material be determined to be  RCRA characteristic wastes.
Such treatment would be solidification/stabilization, which reduces
toxicity  and  mobility,  but  increases  volume.     Because  the
contaminants of  concern  in  these areas  are metals,  this treatment
should effectively render the wastes non-characteristic by binding
the  contaminants,.   If these  wastes are   determined  to  be  RCRA
characteristic, Alternative 3 would not reduce the mobility of the
contaminants because it does not provide for any  treatment of the
wastes.   Alternatives 3  through 9  all address the toxicity and
mobility of surface debris  by  providing for the off-site  disposal
of the surface drums in an approved RCRA facility.

Alternative  9 would  markedly  reduce the   volume  of leachate  by
immobilizing   the   landfill   wastes    in  the   solidification/
stabilization process, thus eliminating  the need to treat leachate.
Alternative 8 would reduce the leachate volume to a greater extent
than Alternatives 3 through 7 by raising the landfill wastes above
the ground water and placing the wastes on a liner.  Alternative 7
would also reduce  the amount of  leachate  produced,  although to a
lesser extent than Alternative 8, via  use of  slurry walls around
the landfill.  Alternatives 3 through 8  all reduce the mobility and
toxicity of leachate by collecting and treating the leachate.

5.   Short—Term Effectiveness

This evaluation  criterion  addresses  the period of  time needed to
achieve protection of human health  and the environment,  and any
adverse impacts that  may  be  posed during the construction and
implementation period of a remedy, until cleanup goals are achieved.

Alternatives 3 through 9 provide for the excavation of the Carbon
Black  Pile,   Waste  Pile  and  the   Northern   Drainage  soils  and

                               -24-

-------
sediments;  thus,  these  alternatives  are  equal  in terms  of the
associated  short-term  impacts.    Environmental  impacts will  be
minimized by installing erosion and sedimentation controls such as
runoff control berms in the Northern Drainage  and siltation fencing
as needed.

Alternatives  3  through  6  have the  least potential  to adversely
affect the  community or  Site workers during remedial activities
because these alternatives do not  involve any  disruptive activities
on the landfill wastes except for the removal of the surface drums
and debris.  Conversely, the implementation of Alternatives 7,  8,
and 9  require the  excavation of  landfill  waste.    Alternative  7
includes  the excavation  of  approximately  1,500  cubic yards  of
landfill waste to install a slurry wall around the quarry perimeter.
Excavation  could uncover  and  bring to  the  surface potentially
contaminated materials  that could pose a health risk to the Site
workers.   Also,  a  water  management system  will  be  required  to
collect  potentially contaminated  run-off and  sediment from the
excavation zone to prevent release to the environment.  Alternative
8, which provides  for  the  excavation of  68,000  cubic yards  of
material, would require an extensive run-off  and sediment management
system  and  would  be  far  more  disruptive  than  the  excavation
associated  with  Alternative 7.  In addition,  it  would be  very
difficult to move this large  quantity of waste because of the quarry
highwall and the surrounding steep slopes.  The  auger ing and mixing
action   of   the   solidification/stabilization  treatment   under
Alternative  9  would  be  less  disruptive  than  the  excavation
associated  with  Alternatives 7  and  8.    However,  because  the
equipment cannot penetrate  and mix the buried drums and tires, these
items must be excavated prior to initiating the treatment process.
Such  excavation  would  be  complicated to   perform  due  to  the
difficulty in determining the location  of drums  and tires below the
surface of the landfill and conducting work on the unstable landfill
surface.

Alternative 5 would have the fewest short-term effects of all the
alternatives with regard to  leachate.   Discharging to an existing
treatment plant would  result in proper leachate treatment  in the
shortest  amount  of  time.    The  passive  treatment  system  of
Alternatives 3 and 4 and the on-Site treatment plant of Alternative
6  would necessitate  a  start-up  time until  leachate was  being
properly treated.   These plants then would  allow  the discharge of
partially treated leachate until such time as when they were fully
operational and meeting discharge limits.

6.   Imolementabi1itv

This evaluation criterion addresses the technical and administrative
feasibility of a remedy, including the availability of materials and
services needed to  implement the chosen remedy.

Alternative 5 would be  the most technically feasible to implement
because  it  entails  discharge to an  existing wastewater treatment


                               -25-

-------
 plant.    The leachate  would be  properly treated  by meeting  the
 pretreatment requirements of the POTW.

 Alternatives 3 through 9 all provide for the excavation and disposal
 of the  non-landfill wastes as  well  as  installation of  a  RCRA
 Subtitle C  cap  over  the  landfill.    These activities  could  be
 implemented  easily, using readily available materials and  equipment
 such  as front-end loaders  and  roll-off  boxes or tarpaulined  dump
 trucks.   Cap construction  is  a known technology.   The  confined
 nature  of the  landfill,  however, with the  quarry  walls  on three
 sides,  may present implementation difficulties which would have to
 be taken into account during the design phase. Alternative 8 would
 be complex to implement  because of the difficulty  of determining
 appropriate   engineering   controls to  prevent  or  minimize   the
 production of contaminated water and sediment which would occur  from
 precipitation falling onto  the open face of the landfill during the
 excavation  of the landfill  contents.  Alternative  9 would be  the
 most difficult alternative to implement because the buried  drums and
 tires  would  have to be  excavated prior  to the blending of  the
 columns to prevent jamming the  drill rig.

 Alternative   3  could not  be implemented if the non-landfill wastes
 are determined to be RCRA  characteristic wastes because these wastes
 would then have to be treated prior to disposal.

 7.   Cost

 CERCLA  requires selection of a  cost-effective remedy that protects
 human health and the environment and meets  the other requirements
 of the  Statute.   The alternatives are compared with respect to  the
 present worth  cost, which  includes  all capital  costs  and   the
 operation and  maintenance  costs  incurred  over  the life  of   the
 project.  Capital  costs  include  those expenditures necessary  to
 implement a  remedial action, including the construction cost.

'The  present  worth costs  developed in the  FS for comparing  the
 alternatives included 30 years of leachate collection and treatment.
 At present,  the  length of time required for treatment is not known,
 however, a longer treatment period is anticipated for Alternatives
 7  and 8 in which the ground water f low is reduced.

 Of Alternatives 3 through 9, Alternative 7  has the lowest present
 worth cost.   However, because it includes the installation of  cut-
 off walls to reduce the amount  of leachate produced,  Alternative 7
 will  incur higher treatment costs than Alternatives 3 through 6.
 In other words, leachate will have to be treated for a longer period
 of time in  Alternative  7 than  for  Alternatives 3 through  6.
 Alternatives 8  and 9 are the most costly with present worth costs
 of $4,450,000 and $4,940,000, respectively.  The difference in  cost
 among  Alternatives  3  through  6  is  minimal;  costs range   from
 $2,035,000  to $2,340,000.   The cost  of the  selected alternative,
 Alternative  5,   is  $2,154,000.    A breakdown of the costs of  the
 selected alternative is provided in Table 3.


                                -26-

-------
                             TABLE 3
                          Alternative 5
                       Capital  Cost Summary

              O
Institutional Control                         $    44,200
Remove and treat carbon black,
waste pile and northern drainage
soil and assess removal action                $   210,020
Cap Construction                              $   745,107
Testing and Design Cost  .                     $   113,426
Leachate Collection system                    S    23.700
TOTAL CAPITAL COST                            $ 1,136,453

-------
8.   state Acceptance

The Commonwealth of Virginia has  concurred with the remedy selected
in this Record of Decision.

9.   Community Acceptance

On April 16, 1991, a public meeting was held at the Bethel Baptist
Church on Route 360 in Danville, Virginia to discuss EPA's preferred
alternative as  described in the Proposed Plan.  A  public comment
period for the Proposed Plan was held from April 10, 1991, through
May 9, 1991.   Comments  received  during the  public meeting and the
public comment  period are discussed  in the  Responsiveness Summary
attached to this ROD.

9.   Selected Remedy

EPA has selected Alternative 5 with some modifications (as indicated
below) to remediate  the contamination at the Site.  Based on the
findings in the RI/FS and the nine criteria listed in Section 8 of
this Decision  Summary,  Alternative 5 represents the best balance
among the evaluation criteria.

Performance Standards

The remedy selected addresses all of the contaminated media at the
Site and consists primarily of excavation and off-Site disposal of
the non-landfill wastes, off-Site disposal of the surface drums and
debris, installation of  a RCRA Subtitle C cap over the landfill, and
collection and treatment of leachate.  By instituting all of these
components, the Site risks (exposure to leachate,  source material,
and quarry soil) would be reduced to within the EPA acceptable risk
range.   The  major  components  of  this alternative  include  the
following:

     • To  reduce the risks to  human health and the  environment
     attributed to the source material, approximately 1080 tons of
     material  from the  carbon  Black Pile,  Waste  Pile,  and  the.
     Northern Drainage  soils and sediments  shall be excavated and
     disposed of off-Site. The Carbon Black Pile and the Waste Pile
     shall be excavated down to  the  bedrock.   To determine if the
     soils  and  sediments  from  these  three  areas   are  RCRA
     characteristic  wastes,  a TCLP  shall be  performed  on these
     materials prior to disposal.  If it is determined through the
     TCLP that  the  soils and sediments are  characteristic wastes,
     they shall be solidified/stabilized prior to disposal.   EPA
     will determine the specific  treatment during the design phase.
     Disposal shall be in a solid waste landfill in accordance with
     the VSWMR.    All excavated areas  shall be filled  with clean
     soil, contoured to  promote run-off, and planted with vegetation
     to control erosion. Run-off control berms  shall be constructed
     in the Northern Drainage to  lessen peak run-off flows from the
     landfill cap and shall be planted with wetland-type vegetation
     to mitigate the loss of the Site wetland areas.  In addition,

                               -27-

-------
the effectiveness of the removal of the Carbon Black and Waste
Piles  on the reduction  of the  zinc  levels in  the Southern
Drainage shall be assessed, including sampling and bioassays.

• To reduce the risk to human health attributed to the source
material, the drums on the landfill surface shall be disposed
of   in  a  RCRA   Subtitle  C   treatment   facility  because
tetrachloroethylene, a  RCRA  listed waste, was placed  in the
drums.  It is estimated  that there  are approximately thirty to
forty drums on the  surface of the landfill and along the quarry
highwall.  To help  maintain the  integrity of the landfill cap,
the surface debris  shall be decontaminated and then disposed
of in a landfill approved by the Virginia Department of Waste
Management.

• To reduce the  risks to human health attributed to the quarry
soil,  a  RCRA Subtitle  C  cap shall  be   constructed over the
landfill area, which is approximately 2 acres in  size.   The
north  and  south  ponds  shall  be  drained  and  the  water
transported to a POTW for  treatment and  discharge.   Prior to
discharge, the water shall be analyzed to determine if it meets
the pretreatment requirements of the POTW.  Clean  fill shall
be placed  onto  the  existing  surface  of the landfill  before
constructing the cap to fill in the north and south ponds and
to establish the requisite  slopes for the cap.  A 6-inch layer
of topsoil shall be placed on top of the cap and vegetated to
control erosion.  As part of the cap construction,  a leachate
collection  system  shall  be  installed  under  the  cap  to
effectively capture all of the leachate generated through the
landfill.   If,  during  operation,  EPA  determines  that  this
collection system does not capture all of  the leachate,  another
collection trench shall  be  constructed outside of the landfill
cap.

•  To  reduce  the  risk  to human  health  attributed  to  the
leachate,   the  leachate shall  be  transported  to a POTW for
treatment.  The leachate shall be analyzed prior to transport
to  the POTW  to determine whether  the  leachate  meets  the
pretreatment requirements of the POTW or whether pretreatment
is required. EPA, in consultation with the POTW, will determine
if pretreatment is  needed and whether it may be  conducted at
an on-site facility or at  an  industrial  user's facility.   If
a POTW does not agree to accept the  leachate or if the leachate
cannot be pretreated to meet the pretreatment  requirements of
the POTW, a treatment system  shall be constructed  on-Site to
treat the leachate, with discharge to Lawless  Creek.  On-site
treatment of leachate shall meet the VPDES effluent discharge
limits set by the VSWCB.  Collection and  treatment of leachate
shall continue until the contaminant levels meet a 10   risk
level and an HI less than 1.

• To ascertain that the remedy  is  protective of  human health
and  the  environment,   long-term  post-closure  ground  water
monitoring  shall  be performed.   Ground water monitoring,

                          -28-

-------
     including the  full list of priority  pollutants specified in
     TCL/TAL, shall be conducted after the  cap  is constructed.  The
     ground water monitoring shall  be performed for thirty years or
     as  long as leachate  is  collected and treated,  whichever is
     longer.  EPA will determine the appropriate number and location
     of  monitoring  wells during the design phase.   If continued
     monitoring  over a  period of time  indicates the existence of
     only a  limited number of contaminants, a  request may be made
     to  limit the monitoring to those specific contaminants.

     • To restrict access and development of the Site, institutional
     controls shall be  implemented,  including  fencing of the Site
     and  implementing  deed restrictions to prohibit residential
     development of the Site.

EPA may  modify  or  refine the selected  remedy  during the remedial
design and construction.  Such modifications or  refinements,  if any,
would generally reflect results of the engineering design process.
The  estimated  present  worth  cost  of the   selected  remedy  is
$2,154,000.  Details of the costs for the selected remedy are shown
in Tables 4 through 8.


10.  Statutory Determinations

EPA's  primary  responsibility at  Superfund sites  is  to  select
remedial  actions that  are  protective  of human  health and  the
environment.  In addition,  Section 121 of  CERCLA,  42 U.S.C. 9621,
establishes  several other  statutory requirements  and preferences.
These specify that,  when complete,  the selected remedial action for
this Site must comply with applicable or relevant  and appropriate
environmental  standards   established  under   Federal  and  State
environmental laws, unless a statutory waiver is  justified.   The
selected remedy  must also  be  cost-effective and  utilize permanent
treatment  technologies  or  resource  recovery  technologies  to  the
maximum extent practicable. The statute also contains a preference
for remedies that  employ  treatment  as a principal  element.   The
following  sections  discuss how  the  selected  remedy  for  the Site
meets these statutory requirements.

     Protection of, Iftflyan Health and the Environment.

In order to meet the remedial objectives  outlined  in the FS,  the
risks associated with exposure to the contamination at the Site must
fall within the acceptable risk range for carcinogens  and non-
carcinogens.  Removal of the Carbon Black Pile, Waste Pile and the
Northern Drainage soils and sediments,  capping the landfill,  and
leachate collection  will assure the Site risks fall within this
range.    The  selected  remedy  protects  human  health  and  the
environment by:

     1.   Reducing contaminant  levels  in  the  Carbon Black Pile,
          Waste Pile and the Northern Drainage soils and sediments

                     »«
                               -29-

-------
                             TABLE 4
                          Alternative 5
                          Capital Cost
                     Institutional Controls
Material and Labor Cost
     Survey fence line           3000 Ft. @ $1.00 /Ft.    $ 3,000
     Prepare Plat                                             500
     Galv. Fence 6 Ft. high      3000 Ft. @ $13.40/Ft.   .  40,200
     File Deed Restriction                               '     500
                                 Total                    $44,200

-------
                             TABLE 5
                           Capital Cost

EXCAVATE CARBON BLACK, WASTE PILE AND NORTHERN DRAINAGE SOILS
CARBON COST
                              80 hrs. @ $75/hr.
                             100 hrs. @ $42/hr.
                             100 hrs
                              16 hrs
                              32 hrs.
         § $32/hr.
         @ $100/hr.
         @ $75/hr.
Site Supervisor
Equipment Operator
Technician
Project Manager
Project Manager
Secretarial
Expenses
EQUIPMENT AND MATERIAL

     Mixer
     Dump Truck
     Track Excavator
     Pressure Washer
     Wind Meter
     Water Tanker
     Level. D Equipment
     X-Met Analyzer
     X-Met Analyzer
     Trailer
     Delivery & Removal
     Telephone
     Power
     Toilet
     40' X 100' X 6 ML Polyethylene @ $140/roll X
     Geotextile Silt Fence 1000 Ft. @ $1.35/LF
     Seeding   1000 SY § $1.16/SY
     Mulch     1000 SY @ $180/1000 SY

                                     Subtotal
                               4 hrs. § $30/hr.
                                    Subtotal
10 days § $200/day
10 days § $300/day
10 days € $300/day
10 days § $75/week
 2 week @ $50/day
 2 week @ $350/wk
10 days @ $45/lay
      Training
      Rental
      2 week 8 $150/wk
$ 6fooo
  4,200
  3,200
  1,600
  2,400
    120
  3.600

$21,120
                                                   $ 2,000
                                                     3,000
                                                     3,000
                                                       750
                                                       100
                                                       700
                                                       450
                                                       450
                                                     1,400
                                                       300
                                                       500
                                                        50
                                                       100
                                                        50

                                                       560
                                                     1,350
                                                     1,160
                                                       180

                                                   $14,900
     Treatability Testing
     8 Samples Total Zinc f $50/ea.
     6 Samples TCLP Metals i $350/ea.
     Treatment 1080 Tons § $50/ton
                                     Subtotal
ASSESSMENT OF REMOVAL ACTION

TOTAL
                           $17,500
                               400
                             2,100
                            54.000

                           $74,000

                           $100.000

                           $210,020

-------
                             TABLE 6
                          ALTERNATIVES 5

                          CAPITAL COSTS

                         CAP CONSTRUCTION
MATERIALS AND LABOR
Clear Light Trees
Grub Stumps
Clearing  (debris and trash)
Dewater Ponds Pump
Tank Truck Rental
Disposal Cost POTW
Fill For Quarry
Haul Fill 5 Miles
Compact Fill
Clay, Select Fill
Haul Fill 5 Miles
Bentonite
Spread Bentonite
Compact
Drainage Layer
Haul 5 Miles
Topsoil
Haul 5 Miles
Grass Seeding
Mulch
2 acres i $2, ISO/acre
2 acres @ $l,025/acre
2 areas § $2,100/acre
2 days @ $ 100/day
2 days § $ 320/day
25,000 gal@ $1.5/1000 gal
15,000 cy e $ 7.00/yd
15,000 cy § $ 2.79/5 miles
15,000 cy § $ 6. 25/cy
8,000 cy @ $10. 85/cy
8,000 cy § $ 2. 79/cy
800 cy e $ 6.75/cy
800 cy § $ 3. 25/cy
8,800 cy 6 $ 6. 25/cy
2,000 cy § $10. 85/cy
2,000 cy § $ 2. 79/cy
2,000 cy 6 $14.70/cy
2,000 cy @ $ 2. 79/cy
15,000 sy § $ 1.16/sy
15,000 sy @ 5 1.80/1000 sy
$ 4,300
2,050
4,200
200
640
37
105,000
41,850
93,750
86,800
22,320
5,400
2,600
55,000
21,700
5,580
29,400
5,580
17,400
2.700
                                             Subtotal    $506,507
EQUIPMENT RENTAL, HEALTH AND SAFETY, MANAGEMENT AND EXPENSES
Pressure Washer
Trailers
Delivery and Removal
Telephone
Power
Toilets
Water Tanker
Health and Safety
Level D
Site Supervisor
Secretary
Expenses
4 months 9 $
4 months 6 $
     400/mo
     300/mo
4 months
4 months
4 months
4 months
120 days
120 days
120 days
120 days
120 days
§ $  100/mo
8 $  150/mo
@ $  200/mo
e $l,700/mo
8 $  900/day
§ $   45/day
8 $  600/day
8 $  240/day
8 $  100/day

Subtotal
$  1,600
   1,200
   1,000
     400
     600
     800
   6,800
 108,000
   5,400
  72,000
  28,800
  12.000

$238,600
Materials, Labor and Equipment
         TOTAL

-------
                             TABLE 7

                          ALTERNATIVE 5

                          capital cost

                       Leachate Collection
Excavate Trench
Geotextile
Stone
Sump Pumps
Piping
Storage Tank
Containment
Design
Installation
30 cy rock § $75/cy
60 sy 6 $3/sy
70 cy § $20/cy

100 ft @ $7.50/ft
10,000 gallon
$ 2,250
    ISO
  1,400
    500
    750
  6,000
  2,500
  2,700
  7.420
                                     TOTAL
                          $23,700

-------
                             TABLE 8

                          ALTERNATIVE 5

              s             O  & M COST


Cost sane as Alternative 3 less treatment system          $20,750

LEACHATE COLLECT AND HAUL

     Haul 170 trips @ $125 ea.                             21,250
     Discharge fee $1.5/1000 gallon                         1,500
     Testing annual                                         1,700
     Monthly monitoring 12 x 250                            3,000
     Labor 4 hrs x 180 x $25/hr.                            is.OOP

                                         Subtotal         $45,450

     O & M COST                                           $66,200

-------
           by excavating,  treating (if required), and disposing  of
           these wastes in an approved off-site facility;

      2.    Eliminating direct contact  with  the landfill wastes  by
           constructing a  RCRA  Subtitle  C  cap over the  landfill,
           meeting the RCRA  landfill  closure  requirements,  and
           implementing deed  restrictions to prohibit  residential
           development of  the Site.   Landfill  closure will  also
           reduce the likelihood of  contaminant migration;  and

      3.    Reducing the contaminant  levels in the landfill  leachate
           by collecting the leachate and treating it at a  POTW.  it
           is not  known at this  time how  long the leachate  will
           remain contaminated.

 Of all of the  alternatives  evaluated, Alternative 5 provides the
 best protection to human  health without significant adverse  impact
 to the environment.   No  unacceptable short-term risks or  cross-
 media impacts would  be caused by implementing  this  remedy.

      Compliance  with  Applicable  or  Relevant  and   Appropriate
      Requirements.

 The selected remedy will comply with all Applicable or Relevant and
 Appropriate  Requirements  (ARARs)  as depicted in Table 9.

 Chemical-Specific ARARs:    The  selected  remedy  will  achieve
 compliance with chemical specific ARARs related to the non-landfill
 wastes.   Specifically, the Carbon  Black Pile, Waste Pile and the
 Northern  Drainage soils and  sediments would undergo a TCLP test  to
 determine if they are RCRA characteristic wastes in accordance  with
 40 C.F.R. Part  261.

 Action-Specific ARARs:  If the non-landfill wastes  are determined
 to be RCRA  characteristic wastes,  they  will  be treated  (either
' solidified or stabilized) prior to disposal.  The surface drums  will
 be sent to a RCRA facility for disposal.   The  surface  debris  will
 be decontaminated on-Site and  sent to a solid waste  landfill  in
 accordance with  the VSWMR.   Transportation  to a  RCRA-permitted
 treatment/disposal facility  would conform with RCRA regulations  at
 40 C.F.R.  Parts  262  and 263,  the  Department of Transportation
 regulations of  Title 49 of the U.S. Code and Part VII of the  VSWMR.
 Capping of the  landfill with a RCRA  Subtitle C cap will conform  with
 the requirements set forth at 40 C.F.R. Part 264 and Part  10  of the
 VSWMR.   The  substantive  requirements of the Virginia  Erosion and
 Sediment  Control Law will be achieved. The landfill leachate  will
 be treated at a POTW if it meets the  pretreatment requirements.

 Location-specific ARARs:  To mitigate the loss of wetlands  that  will
 be filled in or excavated  as part of the remedial action, plantings
 of wetland vegetation will be made in the  newly constructed berms
 in the Northern Drainage.

 Other Criteria, Advisories or Guidance To Be Considered:   None

                                -30-

-------
Standards,
Requirements,
Criteria,
or Limitations

Solid Waste
Management Act
(SWMA)
SWMA
Citation

40 C.F.R.
Section 261
40 C.F.R.
Section 268
(Subpart D)
SWMA
40 C.F.R.
Section 268
(Subpart D)
SWMA
40 C.F.R.
Section 268
(Subpart D)
                                          TABLE 9

                                   ACTION-SPECIFIC ARARs
Description

Hazardous Waste
determinat ion
requirements
Applicable/
Relevant and
Appropriate

   yes/no
Land Disposal          yes/no
Restrictions
for off-site
disposal of
non-landfill
wastes, if RCRA
characteristic waste.

Land Disposal          yes/no
Restrictions
for on-site
disposal of
non-landfill
wastes, if RCRA
characteristic waste.

Land Disposal          no/yes
Restrictions
for on-site
consolidation of
landfill wastes.
     Discussion

Alternatives 4-9.
Non-landfill wastes
will undergo TCLP to
determine if RCRA
characteristic
waste.

Alternative 3.
Alternatives 5-9.
               Alternatives 4-9.
               Alternative 8.

-------
Standards,
Requirements,
Criteria,
or Limitations

Clean Water Act
(CWA)
                                   TABLE 9 (continued)

                                   ACTION-SPECIFIC ARARs
Citation

40 C.F.R.
Section
122.44(a)
Description

Discharge of
treatment system
effluent to
Lawless Creek.
Applicable/
Relevant and
Appropriate

   yes/no
CWA
CWA
40 C.F.R.
Sections
125.100,
125.104,
122.41(1),
136.1-136.4
40 C.F.R.
Part 230,
33 C.F.R.
Parts 320,
and 330
Discharge of
treatment system
effluent to
Lawless Creek.
Discharge of fill
material into
wetlands.
   yes/no
   no/yes
     Discussion

Alternatives 6-9.
Best available
technology
economically
achievable and best
conventional
pollution control
technology required
to control toxic and
nonconventiona1
pollutants and
conventional
pollutants,
respectively.

Alternatives 6-9.
Best Management
Practice Program
to prevent release
of toxic
constituents to
surface waters.

Alternatives 3-9.

-------
Standards,
Requirements,
Criteria,
or Limitations

CWA
Virginia Water
Quality Standards
Virginia Erosion
and Sedimentation
Control Law
Virginia Hazardous
Haste Management
Regulation (VHWMR)
VHWMR
Citation

40 C.P.R.
Section
122.44
Virginia
Regulation
680-21-00
VA Code
Sections
10.1-560
et seq.

VHWMR
Section 10.5
VHWMR
Section 10.6
                                    TABLE 9  (continued)

                                   ACTION-SPECIFIC ARARs
Description

Ambient Water
Quality Standards
for discharge of
treatment system
effluent into
Lawless Creek.

State Water Quality
Standards for
discharge of
treatment system
effluent to
Lawless Creek.
                                   Applicable/
                                   Relevant and
                                   Appropriate

                                      yes/no
Ground water
monitoring
requirements
for closure.

Closure and
post closure
requirements for
hazardous waste
facilities.
yes/no
                       yes/no
yes/no
yes/no
                 Discussion

            Alternatives 6-9.
                                                  Alternatives 6-9.
                                                  Alternatives 2-9.
                                                  Alternatives 2-9.

-------
Standards,
Requirements,
Criteria,
or Limitations

VHWMR
Citation

VHWMR
Section
10.13.K
                                    TABLE 9 (continued)

                                   ACTION-SPECIFIC ARARS
Description

Landfill closure
requirements.
Applicable/
Relevant and
Appropriate

   yes/no
     Discussion

Alternatives 2-9.

-------
Standards,
Requirements,
Criteria,
or Limitations

Safe Drinking
Hater Act
Virginia Water
Quality Standards
Citation

40 C.F.R.
Section
141.11
Virginia
Regulations
680-21-00
                                    TABLE 9 (continued)

                                  CHEMICAL-SPECIFIC ARARs
Description
Maximum Contaminant
Levels for discharge
of treatment system
effluent to Lawless
Creek.

Site specific limits
for discharge of
treatment system
effluent to Lawless
Creek.
Applicable/
Relevant and
Appropriate

   yes/no
   yes/no
     Discussion

Alternatives 3-9,
Alternatives 3-9.

-------
Standards,
Requirements ,
Criteria,
or Limitations

Executive Order
11990 (Wetlands
Protection)
Citation

40 C.F.R.
Part 6
(Appendix A)
  TABLE 9 (continued)

LOCATION-SPECIFIC ARARs
Description

Wetland protection
and restoration.
Appl icable/
Relevant and
Appropriate

   yes/no
                                         Discussion

                                    Alternatvies  3-9.
Clean Water Act
40 C.F.R.
Part 230,
33 C.F.R.
Parts 320,
and 330
Discharge of fill
material into
wetlands.
   no/yes
                                    Alternatives 3-9.

-------
     Cost-Effectiveness

The selected remedy is cost-effective because it mitigates the risks
posed by the Site contamination within a reasonable period of time.
Section 300.430(f)(ii)(0) of the NCP requires EPA to evaluate cost-
effectiveness by first  determining if  the alternative satisfies the
threshold criteria: protection of human health and the environment
and compliance with ARARs.  The effectiveness of  the alternative is
then  determined by  evaluating the  following three  of  the  five
balancing   criteria:   long-term  effectiveness   and   permanence;
reduction of  toxicity,  mobility or volume  through  treatment;  and
short-term effectiveness.  The selected remedy meets these criteria
and  is  cost-effective  because  the  costs  are proportional  to  its
overall effectiveness.   The estimated present worth  cost for the
selected remedy is $2,154,000.

     Utilization of Permanent Solutions and Alternative Treatment
     (or  resource recovery)  Technologies   to the Maximum  Extent
     Practicable fMEPl.

EPA has determined that the selected remedy represents the maximum
extent to which permanent solutions and treatment technologies can
be utilized in a cost-effective manner for remediation of the Site.
Of those alternatives that are protective of human health and the
environment  and comply with  ARARs,  EPA has determined  that  the
selected  remedy,  Alternative  5,  as  modified,  provides  the  best
balance  of  trade-offs  in terms  of  long-term  effectiveness  and
permanence;  reduction   in toxicity,  mobility  or  volume  through
treatment;  short-term  effectiveness;   implementability;  and cost;
while also considering the statutory preference for treatment as a
principal element and considering state and community acceptance.

Alternative 5  was selected because it offers a higher  degree  of
long-term   effectiveness,    implementability,    and    short-term
effectiveness  than the  other  alternatives.    The  strategy  for
remediating the leachate is to allow the  natural flow  of  ground
water through the  landfill contents with collection and treatment
of leachate.   By maintaining  the natural  flow  conditions, it  is
projected that the leachate  will meet health-based  levels in  a
shorter period of time than reducing the flow as in Alternatives 7
and 8.  Utilizing a POTW offers more long-term effectiveness for the
treatment of leachate than the on-Site treatment plants contained
in Alternatives 3, 4, and 6 and, possibly,  7 and 8.   Alternative 5
was selected over Alternatives 3,  4 and 6 because the use of a POTW
to treat the leachate has greater reliability than a small on-Site
treatment system since the POTW would have close monitoring of the
plant operations  while  the on-Site plant would be unmanned in  a
remote  area.   In addition,  utilizing an  existing  POTW  would
eliminate the  need for a start-up  period  for  the treatment  of
leachate.

Although Alternative 9  would be more  protective and  have greater
long-term effectiveness  than the other alternatives,  it was  not
selected  because  it may not be  implementable.    The  in-situ
                     • i
                               -31-

-------
stabilization/solidification of the landfill contents in Alternative
9 would require the excavation of all of the  buried drums and tires
which, at best, would  be very difficult to locate.   It would also
be difficult  to perform  this  removal work on the  surface  of the
landfill.

Alternative 8,  and,  to a lesser  extent,  Alternative 7 would have
short-term effects  from the excavation  of  the landfill material,
Alternative 7 in placing the  slurry  walls around the landfill and
Alternative 8 in consolidating all of the landfill material onto a
liner.  Alternative  9  would also have short-term effects from the
excavation of the buried drums and  tires,  although  to  a lesser
extent than Alternatives  7 and 8.

The Virginia Department of Waste Management has concurred with the
selected remedy.  The  Proposed Plan  for the Site was released for
public comment  on April  10,  1991.  The  Proposed Plan identified
Alternative 5 as the  preferred  remedy.   As  a result  of  public
comment, EPA decided to modify the preferred remedy described in the
Proposed Plan to include  the option of leachate pretreatment at an
industrial user's  facility prior  to  discharge to the POTW.   The
Proposed Plan included only pretreatment in an on-site treatment
plant.  This change allows a choice between either the on-site plant
or an existing  industrial user's facility.   If a determination is
made that pretreatment is required,  EPA, in consultation with the
POTW, will  determine  during  the  design phase  how and where  to
pretreat.

     Preference for Treatment as a Principal Element.

The selected remedy satisfies,  in part, the statutory preference for
treatment as  a principal element.   The major human  health  risk
associated with the  Site is from  ingestion  of landfill leachate.
The selected remedy reduces the levels of arsenic, antimony, barium
and  lead in  the  leachate by  using the  POTW  to remove  these
contaminants  in the  treatment  process.   Also,  if the Carbon Black
Pile, Waste Pile or the soils and sediments of the Northern Drainage
are  determined to  be RCRA characteristic  wastes,  they will  be
treated by either solidification or  stabilization so that they no
longer constitute characteristic wastes.

11.  Doctfi|<^T^jfttion of  significant Changes

The Proposed Plan, which identified Alternative 5 as EPA's preferred
alternative for the Site, was released for public comment on April
10, 1991.  EPA  reviewed all written  and verbal comments submitted
during the public comment period and  determined that  no significant
change to the  remedy identified in the Proposed Plan was necessary.
                               -32-

-------