PB88-113477
COMPENDIUM  OF  COSTS OF
REMEDIAL TECHNOLOGIES AT
HAZARDOUS WASTE SITES
Environmental  Law Institute
Washington,  DC
Oct  87
                U.S. DEPARTMENT OF COMMERCE
              National Technical Information Service

-------
                                                  EPA/600/2-87/087
                                                  October  1987
      COMPENDIUM OF COSTS OF REMEDIAL TECHNOLOGIES
                  AT HAZARDOUS WASTE SITES
                               by
Edward C. Yang,  Dirk Bauma,  Linda  Schwartz, and James D. Werner
                   Environmental Law  Institute
                     Washington, DC 20036
                    EPA Contract  68-03-3113
                       EPA Project  Officer
                          Douglas Anunon
         OFFICE OF SOLID WASTE AND EMERGENCY RESPONSE
          OFFICE OF EMERGENCY AND REMEDIAL RESPONSE
            U.S. ENVIRONMENTAL PROTECTION AGENCY
                     WASHINGTON, DC 20460
        HAZARDOUS WASTE ENGINEERING RESEARCH LABORATORY
               OFFICE OF RESEARCH AND DEVELOPMENT
              U.S. ENVIRONMENTAL PROTECTION AGENCY
                        CINCINNATI, OH 45268

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
1. REPORT NO.
  EPA/600/2-87 7087
             3. RECIPIENT'S ACCESSION NO.
4. TITLE AND SUBTITLE
  Compendium of Costs of  Remedial Technologies at
  Hazardous Waste Sites
                                                           5. REPORT DATE
                                                               October  1987
             6. PERFORMING ORGANIZATION CODE
 . AUTHOR(S)
  Edward C. Yang, Dirk  Bauma.  Linda Schwartz and
  James D.  Werner
             8. PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
  Environmental Law Institute
  1616 P Street, NW
  Washington, DC  20036
                                                           10. PROGRAM ELEMENT NO.
             11. CONTRACT/GRANT NO.

               68-03-3113
12. SPONSORING AGENCY NAME AND ADDRESS
  Hazardous Waste  Engineering Research Laboratory
  Office of Research and  Development
  U.S.  Environmental Protection Agency
  Cincinnati, OH   45268
             13. TYPE OF REPORT AND PERIOD COVERED
               Final. 1/85  -  9/86	
             14. SPONSORING AGENCY CODE
                EPA/600/12
15. SUPPLEMENTARY NOTES
  Project Officer:  Douglas  Ammon  513/569-7876
16. ABSTRACT
  Accurate estimates of hazardous waste site remedial responses  are  important in
  order to: (1) budget the  Superfund Response Fund, (2) estimate costs at specific
  sites, (3) cost-effectively  select remedial actions, and  (4) effectively negotiate
  with private response parties for private action or cost .recovery.   Unfortunately,
  standard engineering costing methodologies have been relatively inaccurate in
  estimating actual response costs.  This is primarily due  to  the uniqueness of the
  site problems and the uncertainties in eventual effectiveness  of the responses.
  The purpose of this document is to record and analyze the  actual expenses incurred
  during remedial responses for seven major types of engineering technologies.  The
  costs documented here are the "bottomline" numbers showing ithe ultimate cost of
  the responses.  The data  supporting this compendium is derived from a series of 31
  case studies of actual hazardous waste remedial responses.  ^This report also
  investigates the divergence  between actual remedial costs  and  estimates from existing
  engineering cost methodologies.  In addition, the compendium lists the major factors
  that cause the costs' movements.  Because of the scope of  the  report coverage and the
  small sample size the data provided here to be viewed as  "bench marks" for the
  estimation of future response costs.  Users are urged to  examine the specific site
  conditions underlying the reported costs by consulting the case studies from which
  these estimates are derived.	\	
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.IDENTIFIERS/OPEN ENDED TERMS  C. COS AT I Field/Group
18. DISTRIBUTION STATEMENT
   Release to public
19. SECURITY CLASS [ThisReport)
   Unclassified
21. NO. Or PAGES
     205
                                              20. SECURITY CLASS (Thispage)
                                                 Unclassified
                                                                         22. PRICE
EPA Form 2220-1 (R«v. 4-77)   PREVIOUS EDITION is OBSOLETE

-------
                      NOTICE

This document has been reviewed in accordance with
U.S. Environmental Protection Agency policy and
approved for publication.  Mention of trade names
or commercial products does not constitute endorse-
ment or recommendation for use.

-------
                                    ABSTRACT
      Accurate estimates of hazardous waste site remedial responses are important in
order to: (1) budget the Superfund Response Fund, (2) estimate costs at specific sites, (3)
cost-effectively select remedial  actions, and  (4)  effectively  negotiate  with private
response parties for private action or cost recovery.  Unfortunately, standard engineering
costing methodologies  have  been relatively inaccurate in estimating actual response
costs.  This is primarily due to the uniqueness of the site problems and the uncertainties
in eventual effectiveness of the responses.
      The purpose  of this  document  is  to  record and analyze  the  actual  expenses
incurred during remedial responses for seven major types of engineering technologies.
The  costs documented here are the "bottomline" numbers showing the  ultimate cost of
the responses.  The data supporting this compendium is derived from a series of 31 case
studies  of actual hazardous waste remedial responses.  This report also investigates the
divergence between  actual remedial costs and estimates from existing engineering cost
methodologies.  In addition, the compendium lists the major factors that cause the costs'
movements.  Because of the scope of the report coverage and the small sample size the
data provided here be  viewed as "bench marks" for the  estimation of future response
costs.   Users  are urged to examine the specific site conditions underlying the reported
costs by consulting the case studies from which these estimates are derived.
                                        111

-------
                                  CONTENTS
NOTICE	ii
ABSTRACT	 . . . iii
TABLE OF CONTENTS	iv
ACKNOWLEDGEMENTS	vi

1.0   INTRODUCTION	1

2.0   Surface Water Controls
          2.1 Surface Sealing	9
          2.2 Grading	19
          2.3 Drainage Ditches	.	23
          2.4 Revegetation	27

3.0   Groundwater and Leachate Controls
          3.1 Slurry Wall  		33
          3.2 Grout Curtain (Aspemix)	^..	44
          3.3 Sheet Piling	52
          3.4 Grout Bottom Sealing	56
          3.5 Permeable Treatment Beds	 59
          3.6 Well Point System	 64
          3.7 Deep Well System	67
          3.8 Extraction/Injection Well System	71
          3.9 Extraction Wells/Seepage Basins	74
          3.10 Subsurface Drain.	79
                                      iv

-------
Contents (continued)                                                    Page

4.0   Aqueous and Solids Treatment
        4.1 Activated Sludge	.88
        4.2 Anaerobic, Aerobic <5c Facultative Lagoons	93
        4.3 Rotating Biological Contactors	99
        4.4 Air Stripping	103
        4.5 Carbon Treatment	119
        4.6 Oil/Water Separator	116

5.0   Gas Migration Control
        5.1 Pipe Vents		122
        5.2 Trench Vents	125
        5.3 Gas Barriers	129
        5.4 Carbon Adsorption	133

6.0   Material Removal
        6.1 Excavation/Removal, Transportation
        and Disposal	139
        6.2 Hydraulic Dredging	163
        6.3 Mechanical Dredging		168
        6.4 Drum Handling		172

7.0   Water & Sewer Line Rehabilitation
        7.1 Sewer Line Replacement	178
        7.2 Sewer Line Repair	  181
        7.3 Water Line Repair	185
        7.4 Water Main Replacement	188

8.0   Alternative Water Supplies
        8.1 New Water Supply Wells			191
        8.2 Water Distribution System	  194

9.0   REFERENCES		.	.............  197

-------
                             ACKNOWLEDGEMENTS
      The Environmental Law Institute (ELI) prepared this report under a subcontract
with SAIC of McLean, Virginia for the US EPA's Office of Research and Development,
Hazardous Waste  Engineering Research Laboratory  and the Office of Solid Waste and
Emergency Response,  Office of Emergency and Remedial Response. This report was
prepared by Dr. Edward C. Yang, Director of ELFs Resources Program, Dirk Bauma,
Linda Schwartz and James  D.  Werner.  Mrs. Nurhan Giampaolo of ELI and Ms. Diane
Simmons of JRB  Associates provided the administrative support for the project.  The
report was prepared under the direction of EPA Task Managers, Bruce Clemens (Office
of Emergency  and  Remedial Response, Policy  Analysis Staff -  - James Lounsbury,
Director) and Douglas Ammon (Hazardous Waste Engineering Research Laboratory, Land
Pollution Control Division - - Ronald Hill, Director).
      The  project  team  greatly appreciates the  overall guidance of the JRB Task
Manager Claudia Furman  and S. Robert Cochran, and the EPA  Task Managers for their
assistance and support.
                                      VI

-------
                                     SECTION 1
                                1.0 INTRODUCTION
 1.1  OVERVIEW
      Response cost information is critical to several aspects of implementation of the
 Comprehensive  Environmental  Response, Compensation  and  Liability  Act  of  1980
 (CERCLA), known as Superfund. These aspects include:

     •    Selecting cost-effective response alternatives
     •    Documenting reasonable costs for cost recovery
     •    Budgeting for fund balancing

 The purpose of this Cost Compendium is to summarize existing cost information for
 these uses.  Actual expenditures and estimated costs are both given  to assemble  data
 from all available sources into  one data  base.  The  immediate use of this centralized
 source of cost information is to  provide consistency in various site-specific costing tasks
 such  as: remedial  alternative costing  as required  in the Feasibility Study Guidance
 Document  (FSGD), and budgeting for immediate and planned removals.  This compendium
 should be viewed as the first installment of an ongoing data base, which will be updated
 periodically as more cost information becomes available from completed Superfund
 responses.    Cost  data  in   this  compendium  are  organized  according to  related
 technologies, such as "Ground-Water Controls" (see Table of Contents). The costs given
are for technologies that have been most commonly used at uncontrolled hazardous waste
sites, although some rarely used technologies are given because estimates are frequently
cited.  Commonly used  technologies may  have been excluded because  of the paucity of
data.  Typically,  however,  the number  of estimates  and  the depth of background
information are often proportional to the frequency of use of the technology.  In addition
to the organization of cost data  according to technologies, several other features of this
cost compendium merits highlighting.
                                         1-

-------
 1.2  ACTUAL EXPENDITURES VERSUS ESTIMATES
      Most available cost information is from engineering estimates.  Few such estimates
 have been field tested, however.  Preliminary comparison of these estimates with actual
 expenditures  has  shown significant differences  in  many cases (ELI/JRB,  1983).  Since
 merging these two types  of data would be misleading to the reader, this compendium
 separates, ex ante, engineering estimates from actually observed expenditures*  Although
 actual expenditure data, which has been "ground truthed",  are  generally more reliable
 than  estimated cost data, estimates are useful because they broaden the range of site
 characteristics and technical circumstances for which costs are available.  The factors
 that  were included in deriving  the  cost estimates may reflect a situation that more
 closely parallels the intended  use of the cost data  than any of the situations for which
 actual expenditure data are available.

 1.3  FOCUS ON UNTT-OOST
      Data are given in a unit-cost form, in terms  of dollars per unit operation, such as
 cost per square foot of slurry  wall, or cost per gallon  of treated water.  Since the units
 used are important, consideration was given to the selection to ensure that they were
 useful and/or standardized throughout the industry.   English measure only is used for
 simplicity.  These unit costs typically include all related costs such as material, labor,
 and equipment and other capital  costs. Operation  and labor costs are given when they
 are applicable and available.

 1.4 INCLUSION OF SUMMARY AND RAW  DATA
      This compendium organizes cost data into two levels: (1) summary data, and (2) raw
data.  The first level  gives summary data  such  as  range, and when possible, mean and
standard error (see Table  1).  This summation of the raw data should be used only  for
very general  cost  screening and budgeting,  since the wide ranges of the data presented,
and the  lack of background explanation on this level render it  unsuitable for more
specific costing purposes.   Such specific cost estimation should use raw data, on the
second level,  which provides more  detail on the data compilation.  This detail can be used
for matching to the circumstances at the site for which it is to be used. The user should
 compare the  site  circumstances  to the factors given in the raw data to estimate the
effect of these factors on the estimated cost.

-------
                                       TABLE 1
         RANGE OF UNIT COSTS ASSOCIATED WITH REMEDIAL TECHNOLOGIES
    Technology
Expenditures
                                                         Range of Unit Costs
                                                                           2
Estimates
4.0   SURFACE CONTROLS
      Surface Sealing
      Grading
      Drainage Ditches
      Revegetation
$0.92 to $15.84/yd2
            N/A
            N/A
            N/A
$1.32 to $16.88/ydz
$4,000 to $16,205/acre
$1.27 to $6.04/linear foot
$1,214 to $8,000/acre
5.0 GROUND-WATER AND LEACHATE CONTROLS
      Slurry Wall              $0.25 to $31.96/ft2
      Grout Curtain           $6.60 to $14.00/ft2
      Sheet Piling
      Bottom Sealing by Grout
      Permeable Treatment Beds
      Well Point System
      Deep Well System
      Extraction/Injection
       Well System
      Extraction Wells/
       Seepage Basin
      Subsurface Drain
            N/A
            N/A
            N/A
            N/A
            N/A

            N/A
$31,269/system
$24 to $l,733/foot
$4.50 to $13.86/ft2
$5.50 to $75.52/ft2
$8.02 to $17.03/ft2
$9   to$116/ft2
$14  to $267/ft2
$803 to $8,284/weU
$4,862 to $13,513/weU

$37.50/ vertical foot

$33,618 to $53,360/system
$1.94  to $218/foot
6.0 AQUEOUS AND SOLIDS TREATMENT
      Activated Sludge
      Lagoons
      Rotating Biological
       Contactors
      Air Stripping
      Carbon Treatment
      Oil/Water Seperator
$6.3 million/mgd
            N/A

            N/A
$182,540/mgd
$0.10 to $0.40/gallon
$289,200/system $12,720/mgd
$200,000 to $390,000/mgd
$80,000 to $3.4 million/mgd

$0.9 million to $29.6 million/mgd
$607,000   to $7.3 million/mgd
$14,132    to $643,000/mgd
                                      -3-

-------
                                         TABLE 1
      RANGE OF UNIT COSTS ASSOCIATED WITH REMEDIAL TECHNOLOGIES (continued)
  7.0  GAS MIGRATION CONTROL
        Pipe Vents                   N/A
        Trench Vents                 N/A
        Gas Barriers                  N/A
        Carbon Adsorption            $188/filter
                                                     $445  to $l,310/vent
                                                     $ 35 to $646/linear foot
                                                     $0.39 to $3.00/ft2
                                                     $635/filter
 8.0 MATERIAL REMOVAL
       Excavation, Transport
        and Disposal
       Hydraulic Dredging
       Mechanical Dredging
       Drum Handling
                              $4.70 to $884/yd3
                              N/A
                              N/A
                              $60 to $l,528/drum
$379 to $434/yd3
$1.25 to $3.54/yd3
$1.37 to $4.09/yd3
      N/A
 9.0  WATER & SEWER LINE REHABILITATION
       Sewer Line Replacement
       Sewer Line Repair/
        Cleaning
       Water Line Repair
       Water Main Replacement
                              N/A

                              $15/linear foot
                              N/A
                              N/A
$53.90 to $141.60/linear foot

$5.75 to $15.9Q/linear foot
$26   to $35.50/linear foot
$58.50 to $119.18/linear foot
 10.0   ALTERNATIVE WATER SUPPLIES
       New Water Supply Wells        N/A
       Water Distribution
        System                      $1,091 to
                                    $10,714/house
                                                    $46.25/linear foot
                                                         N/A
1
2
See individual technology sections for sources of cost data.
Tinit <-n«!t«? are exclusive of operations and maintenance costs.
£ somfc^sS? no rafgeVgiven since only a single data source was
available.
N/A = Not Available.

-------
 1.5  FACTORS FOUND TO AFFECT COSTS
      A  fundamental  concept of estimating costs of technology is  that  a variety  of
 factors  influence  these costs.   This compendium discusses  these  factors for each
 technology.  This brief discussion of the effects of these factors reflects the descriptive
 detail given  for each data source  in  the table of  raw data.  The essential site
 characteristics for  actual expenditure  data  are  typically  described.   These site
 characteristics are drawn from a hypothetical site scenario that is usually established for
 the  purpose of making necessary assumptions for estimating costs. The level of detail
 available for actual site characteristics and hypothetical site scenarios varied widely.

 1.6  CONSTANT 1982 DOLLARS
      Since the source data, on which this compendium  is based, originated in different
 years between 1975 and 1982, all costs were indexed to constant 1982 dollars using the
 Engineering News Record construction cost index.  This index relects  the weighted cost
 trend of common labor (74%), structural steel (15%), lumber (9%), and portland cement
 (2%).  Data  from  1983 documents  were not deflated to 1982  dollars for  two reasons.
 First, most of the  costs for 1983 were actually incurred in  1982 or estimated for 1982
 dollars.  Second, the change in the  ENR index between  1982 and 1983 is expected to be
 very smalL

 1.7  COST OF HEALTH AND SAFETY PROTECTION
      One of the key factors affecting the costs of responses at uncontrolled sites is the
 level of protection for health and safety  of  on-site  workers.   The level of  hazard
 determines the type  of protective  measures the  workers  must take, which ultimately
 affects  the cost  of the response.  Many of  the data sources used in  this compendium,
 however,  did not explicity  note health and safety concerns. The cost data for actual
 expenditures include whatever  protective  measures were  taken  at  the site.   Often,
 however,  the  available  information on the  response action did not fully  describe the
 protective measures.  This defect may be corrected  by further research.   Health and
safety assumptions for estimates  are  usually less clear  than expenditures.  In only one
case did the estimator explicitly consider the cost effect  of various protective measures.
     SCS  Engineers  recently completed  a study on the  cost of health and safety
 protection for  the  U.S. EPA  Office of Research  and  Development.   Six cleanup  firms
 were asked to bid on six hypothetical uncontrolled site scenarios with five levels of
personal protection for the study (see Table 2).  The key results are presented in Table 3,

                                        -5-

-------
                                      TABLE2

                         LEVELS OF PERSONAL PROTECTION
     1.    Level A - requires full encapsulation and protection from
           any body contact or  exposure to materials (i.e., toxic by
           inhalation and skin absorption).

     2.    Level B - requires self-contained breathing apparatus
           (SCBA),  and  cutaneous  or  percutaneous  exposure to
           unprotected  areas of the  body  (i.e.,  below  harmful
           concentration).

     3,    Level C - hazardous constituents known; protection
           required for low  level concentrations in air; exposure of
          unprotected body areas (i.e., head,  face, and neck) is not
          harmfuL

     4.    Level D - no identified hazard present, but conditions are
          monitored and minimal safety equipment is available.

     5.    No hazard protection - standard base construction costs.
Sources   "Interim Standard Operating Safety Guides,"

          EPA, 1982.
                                       -6-

-------
                                   TABLES
              AVERAGE PERCENT INCREASE FOR TOTAL COSTS AT
                      FOUR DEGREE-OF-HAZARD LEVELS*
Unit Operation
Surface Hater Controls:
1. Surface Sealing - Sythetlc Membrane
2. Surface Sealing - Clay
3. Surface Sealing - Asphalt
4. Surface Sealing - Fly Ash
5. Revegetatlon
6. Contour Grading
7. Surface Water Diversion Structures
8. Basins and Ponds
9. Dikes and Berms
Ground Hater Controls:
1. Hell Point System
2. Deep Hell System
3. Drain System
4. Injection System
5. Bentonlte Slurry Trench
6. Grout Curtain
7. Sheet Piling Cutoff
8. Grout Bottom Sealing
Gas Migration Controls:
1. Passive Trench Vents
2. Passive Trench Barriers
3. Active Gas Extraction Systems
Haste Controls:
1. Chemical Fixation (Solidification)
2. Chemical Injection
3. Excavation of Hastes/Contaminated Soil
4. Leachate Reclrculatlon
5. Treatment of Contaminated Water
6. Drum Processing
7. Bulk Tank Processing
8. Transformer Processing
teyeru

1141
109X

..
117X
122X
135X
125X
150X

not
«.»
128T
..
109X
..
._
—


„ •
..

1221
..
3071
„„
119%
2011
19SX
.. +
level C

1191
1191
..
.„
124X
133X
144X
138X
1731

117X
—
138X
„_
1141
„
..
--


...
—

129X
._
3371
«,«>
1211
228X
2481.
293X
Level B

1221
124X
—
--
126X
140X
1511
1451
176%

121X
..
143S
..
132S
..
--
~

„
..
--

133X
--
397%
.•
1261
264X
419%
"*
Level A

124X
1271
--
—
1281
146X
154%
1501
1861

1281
--
148%
--
1361
—
-~
*••

..
-.
0.

137X
— •
71 5X
--
1281
3171
S49X
"*
    * Values given include 100 percent for base construction costs.
    + This unit operation was deemed appropriate for performance
      only at Level C. Costs at Levels D, B, and A were not provided.

Sources   "Worker Health and Safety Considerations:  Cost of Remedial Actions at
         Uncontrolled Hazardous Waste Sites", Draft Final Report, 1983.
         SCS Engineers for U.S. EPA, Covington, Kentucky.
                                      -7-

-------
 and more details are given in the SCS report.  Several items should be kept in mind using
 Table 3:  First, the results are from a final draft version of the SCS report. Additional
 changes may be made to the results.  Second, the validity of the results depends on how
 seriously  the  bidders took the  hypothetical scenarios and whether the  bidders were
 neutral in providing  the estimates (i.e., free from motives that may misrepresent  the
 costs).  And finally, the technologies in Table 3 do not always match the ones given in
this compendium.

-------
                                                  Surface-Water Controls
                                                  Surface Sealing
                                     SECTION 2

                          2.0 SURFACE WATER CONTROLS
 2.1  SURFACE SEALING

 2.1.1     Definition
      Surface  sealing  (capping) involves covering  a site with  any of  a variety of
 materials, including clay, asphalt, cement or a synthetnic membrane, to prevent surface
 water infiltration,  control  erosion, and/or mitigate volatilization from  contaminated
 waste.

 2.1.2     Units of Measurement
      Cost per unit surface area is used, generally, because area best expresses the
 functional attribute of a cap.   Cost per square yard is used specifically because it is
 readily converted to  acres  (X 4,840), sq.ft.  ($/9) and cubic yard volume (X depth in
 yards).

 2.1.3     Summary Statistics

 2.L3.1    Expenditures
      The actual costs of surface seals ranged frorm
          $0.92/yd.2 - 4" thick, loam
            to
          $ 15.84/yd.2 - 6" thick, clay.

The  surface seals for  which actual  costs are given reflect site specific characteristics,
such  as  design parameters  and  availability  of  local material.  The most  costly  seal
involved an engineered cap with carefully controlled  clay/water content.  The  least
costly cap was constructed with on-site clay that required only hauling and compacting.
                                        -9-

-------
                                                Surface-Water Control
                                                Surface Sealing
     Operation  and maintenance costs  included ground-water  monitoring, inspection,
surface upkeep and, possibly, costs of repair.  These costs are accounted for separately
where information on them exists.

2.1.3.2    Estimates
     The eight cost estimates for surface seals ranged from:
          $1.32/yd.2 -                geotextile, level B protection
            to
          $16.88/yd.2-               sand/hypalonAoam.

Operation and maintenance costs involving monitoring of ground-water and inspection of
the cap were generally not included in the estimates. However, the following in costs for
O&M were included in the Radian estimate:
                                                         •

     Item                                        Cost
    Annual Inspection                            $500/year
    Mowing/Revegetation                         $600/year/acre
    Erosion control and drainage
    maintenance                                 $2 00/year/acre
    Repairs resulting from shrink
    swell or freeze/thaw forces                    $200 costs/year
    construction
                                   •
     The extremes of the range of estimated costs are represented by a very simple
temporary cap  at the low  end and a  more complex, three element  cap, intended to be
permanent, at the highest cost end.
                                      -10-

-------
                                                  Surface-Water Control
                                                  Surface Sealing
 2.1.4      Factors Found to Affect Costs

 2.1.4.1    Expenditures
      Generally, cap and cap-related materials affected the costs of surface seals:
           •   Cap materials:
              bentonite/clay
              asphalt
              concrete
              synthetic membrane
              loam soil
     •     Cap-Related materials:
              top gravel
              curbs
              membrane soil anchor

      The  factors influencing  the  actual  costs of surface seals, as outlined above and
 given  in  Table 4, are  generally divided into "Material variations"  and "Dimensional
 variations". They are presented here only  to provide a rough background of the costs for
 general comparison purposes, and not to specifically delineate the proportional effect of
 particular cost components.  It is not possible to determine from the data if there was a
 significant general cost  difference between clay and asphalt caps. Although the costs at
 the California site suggest no significant cost difference, other sites had significant cost
 differences.  These differences, however, may have been due to anomolous availability of
 local material or  other  factors.  The number of observations were inadequate to make
 any  clear conclusions.  Variations in the costs for related materials may have affected
 the total  costs of the various caps. The cost of the bentonite-soil cap at the California
 site  included the cost of the 6-inch (0.15 m) cover of 3/4-inch (1.9 cm) gravel to prevent
 erosion of the cap.  The cost of the curbs for run-off control at the California site was
 not included in the total reported cap cost, but curb installation may have caused an
increase in the  cost not incurred in the other sites lacking this feature.  The use of a
synthetic   membrane  required less  heavy  construction  equipment  for  deployment,
although soil anchors were used. The cap for the New Hampshire site may be considered
 an element of revegetation, but it also had a role in stabilization of the soil.
                                        -11-

-------
         TABLE 4
SURFACE SEAL EXPENDITURES

        (1982 Dollars)
DATA SOURCE
US EPA
ELI/JRB
1981
Maryland
US EPA
ELI/JRB
1981
California
US EPA
ELI/JRB
1980
Arkansas
MATERIAL

clay

gravel over
bentonite-soil
asphalt
clay

THICKNESS

6 inches

6 inches
4-6 inches
data not
available
1 foot

COVERAGE

data not
available

17,333 sq.yd.
15,000 sq.yd.
11 ,111 sq.yd.

UNIT COST

$15.84

$10.98
$11.18
$10.09


-------
                                      TABLE 4

                        SURFACE SEAL EXPENDITURES (continued)




                                    (1982 Dollars)
DATA SOURCE
US EPA
CH2 M Hill
1981
New York
US EPA
Weston
1981
New Hampshire
US EPA
ELI/JRB
1983
Utah

MATERIAL
synthetic membrane



loam soil for
re vegetation


clay - fabric




THICKNESS
data not
available


4 inches



2ft




COVERAGE
216,600 sq.yd.



120,520 sq.yd.



26,340 sq.yd.




UNIT COST
$3.75/sq.yd.



$0.92/sq.yd.



$15/sq/yd




I
(—
u>

-------
                                                 Surface-Water Control
                                                 Surface Sealing
      Finally, dimensions cap (thickness and area covered) appeared to affect unit costs
 of the cap.  Increased  thickness and area  of the cap  generally added  to costs  by
 increasing the volume of cap material and the amount of grading required.  An exact
 generalized function for  this relationship cannot be determined from the available data.
 The unit cap cost, however, is also affected by economies of scale.

 2.1.4.2   Estimates
      Generally, the following factors affected the estimates:
          o  Component material type:
                                     clay
                                     soil
                                     synthetic liner
                                     sand
     •    Number of components:
             single component
             composite
     •    Dimensional variations:
             thickness
             area covered

Generally, estimative information (see Table 5) was  less detailed  than  the data for
expenditures; however, salient information usually was available.  Scenarios from generic
engineering-construction  manuals of cost (JRB, SCS, Radian) and  feasibility studies were
unable to predict unexpected changes occurring during the response.
      Component material the costs were generally qualitative and  quantitative. Four
types of materials  were  assumed in the various estimates:  clay, soil, synthetic liner and
sand.   The more significant consideration, however, was the number of  components
assumed for  the  estimates.  Typically, additional component  costs in composites were
assumed to be additive.  Again, the dimensional variations affected both the volume of
surficial material required and the economies of scale. Increased cap thickness requires
more volume per area. Caps with a larger  area had the  advantage of greater economies
of scale, because previously mobilized  grading and compacting equipment could be used
at a relatively small additional marginal cost.
                                      -14-

-------
                                            TABLES

                                  SURFACE SEAL COST ESTIMATES




                                           (1982 Dollars)
DATA SOURCE
US EPA
JRB-RAM
1980
/
US EPA
Radian
1982
US EPA
SCS
"landfill"
1980
SCS
"impoundment "
1980
MATERIAL
loara over
hypalon over
sand
loam over
hypalon over
sand
bituminous
concrete
bituminous
concrete

THICKNESS
8 inches
30 mil.
1 foot
8 inches
30 mil.
1 foot
3 inches
3 inches

COVERAGE
96,800 sq.yd.
96,800 sq.yd.
66,215 sq.yd.
5,597 sq.yd.

UNIT COST
$16.88/sq.yd.
$9.34/sq.yd.
$6.58-9.13/sq.yd
$4.67-6.90/sq.yd.

Ul
I

-------
                TABLES
SURFACE SEAL COST ESTIMATES (continued)

              (1982 Dollars)
• DATA SOURCE
US EPA
MERL
1979
New Jersey
US EPA
Weston
Feasibility Study
1982
New Hampshire
US EPA
CH2 M Hill
Feasibility Study
1983
New Jersey
US EPA
CH2 M Hill
1983
Arizona
MATERIAL
bituminous
concrete



PVC liner

earthfill over
geotextile


geotextile
THICKNESS
3 inches



30 rail.

8 inches
not given


not given
COVERAGE
5,597 sq.yd.



96,800 sq.yd.

42,000 sq.yd.


not given
UNIT COST
$6.49/sq.yd .



$4.50/sq.yd.

$1 .83/sq.yd.


$1.32/sq.yd.

-------
                                                 Surface-Water Control
                                                 Surface Sealing


The  Radian  estimates  given Table 6  are  based on using the  following list  of  cost

components to construct a surficial seal, the same specifications were established in the
JRB-RAM scenario.
            TABLE 6.  SURFACE SEAL COSTS:  MATERIAL VARIATIONS

                                                 Cost

                                                 $15/yd.3

    Clay hauling, spreading, and compaction        $10/yd.3

    Sand hauling, spreading, and compaction
Direct Capital Cost Items;
Topsoil (sandy loam), hauling,
spreading, and grading (within 20 miles)
    Portland concrete (4 - 6" layer), mixed,
    spread, compacted on-site

    Bituminous concrete (4 - 6" layer),
    including base layer

    Lime or cement, mixed into 5" cover soil

    Bentonite, material only; 2" layer, spread
    and compacted

    Sprayed asphalt membrane (1/4" layer and
    soil cover), installed

    PVC membrane (20 mil), installed

    Chlorinated PE membrane (20-30 mil),
    installed
                                            $18/yd.3
                                            ($9-12,000/acre)


                                            $9-15/yd.2


                                            $4.50- 7.25/yd.2

                                            $2.15 - 3.00/yd.2
                                            $1.90
                                            $2.00 - 3.40/yd."

                                            $1.75 - 2.70/yd.5

                                            $3.25 - 4.30/yd.5
    Elasticized polyolefin membrane, installed$3.10 - 4.15/yd.
    Hypalon membrane, (30 mil), installed

    Neoprene membrane, installed

    Ethylene propylene rubber membrane,
    installed

    Butyl rubber membrane, installed

    Tenon-coated fiberglass (TFE) membrane
    (10 mil), installed

    Fly ash and/or sludge, spreading, grading,
    and rolling
                                            $7.40/yd.2

                                            $7.25/yd.2

                                            $3.60 - 4.70/yd.2


                                            $3.60 - 5.10/yd.2


                                            $23/yd.2


                                            $1.50 - 2.50/yd^
                                         _1 7-

-------
                                               Surface-Water Control
                                               Surface Sealing
Expenditure Sources

    •    ELI/JRB Case Studies, 1983
    •    State and Federal Superfund Work, 1981 - 1983
Estimate Sources

    •    JRB-RAM, 1980
    •    Radian, 1983
    •    EPA, OERR contractor Feasibility Studies, 1981-1983
    •    SCS Engineers, 1981
                                     -18-

-------
                                                  Surface-Water Controls
                                                  Grading
2.2  GRADING

2.2.1     Definition
      Grading is  the general term  for the  process of reshaping the surface of the ground to
control surface-water runoff and infiltration, as well as to minimize erosion and prepare the
site for revegetation or sealing of the surface. The three basic steps in the process are: hauling,
spreading and compacting.  The latter two steps are routinely practiced at sanitary landfills.
The equipment and methods used in grading are essentially the same for all landfill surfaces, but
applications of grading technology will vary on a site-specific basis.  Grading is often performed
in conjunction with surface sealing practices and revegetation as part of an integrated plan for
the closure of a landfill.

2.2.2     Units of Measurement
      The unit cost is given in dollars per acre because grading is usually performed on the scale
of acres.

2.2.3     Summary Statistics

2.2.3.1    Expenditures
      No actual expenditure data were available for grading costs at this time.

2.2.3.2    Estimates
      The grading cost estimates ranged from:
          $4,000/acre
             to
          $16,205/acre
                                        -19-

-------
                                                 Surface-Water Control
                                                 Grading
Operation and  maintenance costs involving ground-water monitoring and cap inspection  were
generally not included in the estimates.  The following in O&M costs, however, were included in
the Radian estimate;

             Item                                Cost
             Annual Inspection                    $500/year
             Mowing/Revegetation                $600/year/acre
             Erosion control and drainage
              maintenance                        $200/year/acre
             Repairs resulting from shrink/
              swell or freeze/thaw forces
              construction                        $200 costs/year

      The lower grading cost  estimates  ($4,000 - 4,720/acre) reflected the costs of on-
site hauling, spreading and compacting of a one^foot thick soil layer and a 6 inch sand
layer.  These estimates assume no  material costs for sand or soil.  The higher grading
estimates by  SCS also exclude material costs, but include the excavation and grading
costs for on-site soil.  Additional costs (30%) were included in these estimates to cover
overhead and a contingency allowance.  The cost for a diversion ditch, included in the
SCS estimates, was subtracted, for consistency with the other estimates.

2,2.4     Factors Found to Affect Costs

2.2.4.1    Expenditures
      No expenditure  data are available at this time.

2.2.4.2    Estimates
          The Following salient factors affected grading costs;
     Material:
          Source of material
          Type of material
                                        -20-

-------
                                                 Surface-Water Controls
                                                 Grading
     Related or additional costs:

          Soil compaction testing
          Surveying
          Overhead
          Contingency allowance

Two variables which affected costs of materials are detailed in Table 7. The source of
the material was either on-site or off-site,  which affected the costs for hauling. The

type of fill material affected the estimate because sand costs more per unit volume to
handle than soil. However, this estimated difference excludes material costs, and only

includes hauling, spreading and compacting.

     The inclusion of related or additional costs varied among the estimates, and hence
affected the costs. The SCS estimates included the following related or additional costs,
which were not included in the JRB and Radian estimates:
Related/Additional
    Costs

Surveying (2 days)
Overhead allowance (25%)
Contingency allowance (15%)

         Total
Landfill
(13.4 acres)
$17,499-20,402
$10,502-12,237
Impoundment
(1.16 acres)

$ 366-614
$2,655-3,469
$1.593-2,077
$28,001-32,639      $4,614-6,160
Estimates Sources


    •     JRB-RAM, 1980

    •     Radian, 1983

    •     SCS,  1981
                                        •21-

-------
                                            TABLE 7


                                    GRADING COST ESTIMATES





                                          (1982 Dollars)
DATA SOURCE
US EPA
SCS
"Impoundment"
1980
US EPA
SCS
"Landfill"
1980
US EPA
Radian

1983
US EPA
JRB-RAM
1980
MATERIAL
on-site
soil
on-site
soil

soil
sand


"fill"
sand
COVERAGE
1.16 acres
13.4 acres

not given



1 5 acres
20 acres
ADDED FILL
1 .5 feet
1 foot

not given



1 foot
6 inches
UNIT COST
$12, 563-16, 205/acre
$7,285-8,469/acre

$4, 000 /acre



$4,720

I
ro

-------
                                                 Surface-Water Control
                                                 Drainage Ditches
2.3 DRAINAGE DITCHES

2.3.1      Definition
     Drainage ditches or trenches intercept overland flow or shallow ground-water flow
to control surface discharge and/or minimize contributions to ground-water contamina-
tion.  Ditches usually run around the perimeter of a site and may complement ground-
water or surface-water control techniques by collecting water from subsurface drains or
off of caps. They may be lined with a clay or synthetic membrane to prevent infiltration
or with stone to prevent erosion.

2.3.2      Units of Measurement
     Costs  are given in  dollars  per linear  foot  (LF) because  length provides a single
simple trench dimension for performing quick estimates.

2.3.3      Summary Statistics

2.3.3.1    Expenditures
          No actual expenditure data are available at this time.

2.3.3.1    Estimates
          The cost estimates range froms
          $1.27 - 2.54/LF            (1-foot deep)
             to
          $6.04/LF                  (6-feet deep)
                                       -23-

-------
                                                 Surface-Water Control
                                                 Drainge Ditches
The cost estimates seemed to be primarily influenced by the volume of soil excavated.
The Radian scenario assumed excavation of over six times as much soil as the EPA site-
specific estimates. The  1 foot deep trench was similar to a shallow french drain since it
was filled with gravel.
     Operation  and  maintenance  costs   such  as  inspection  and  repair  were  not
consistently available. The Radian estimate, however, gave the following estimate:

              Item                                 Cost
             Annual Inspection                    $500/year
             Mowing/Revegetation                $600/year/acre
             Erosion control and drainage
              maintenance                       $200/year/acre
             Repairs resulting from shrink/
              swell or freeze/thaw forces
              construction                       $200 costs/year
2.3.4     Factors Found to Affect Costs

2.3.4.1    Expenditures
      No expenditure data were available at this time.

2.3.4.2    Estimates
      The three primary components affecting the cost estimates weres
          Depth
          Lining
          Overhead and contingency costs
The depth was perhaps the most salient factor altering cost estimates (Table 8) since it
was directly related to  the volume of  material excavated.  Excavation is the primary
task  of  ditch construction, grading and berm construction,  but it  was proportionally
included in all estimates.
                                       -24-.

-------
                                     TABLES
                         DIVERSION DITCH COST ESTIMATES

                                   (1982 Dollars)






1
NJ
tn




DATA SOURCE
US EPA
Radian

1982
US EPA
SCS ( 1 )
"Landfill"

1980
US EPA
ORD-MERL
1979
New Jersey

LINING


none

none




gravel and
stone filled


DEPTH

6 feet


6.5 feet




1 foot


TOTAL COST

$9,060


$13,393 -
$15,741



$8,763



UNIT COST

$6.04/LF


$4.39-5.16/LF




$1.27-2.54/LF


(1 )   Includes overhead  (25%) and contingency  allowance  (15%).

-------
                                                Surface-Water Control
                                                Drainage Ditches
Only the EPA-New Jersey site estimate delineated costs of the lining subtask.  This cost
component could become more significant for deeper ditches.
     Finally, an  overhead allowance (25%) and  a contingency allowance (15%) were
included for the SCS estimate.  The other estimates did not include any surcharges or
allowances for health and  safety  considerations,  so these additional costs  may  be
appropriate to include for some sites. The SCS  estimate included "grubbing" to clear
vegetation from ditches (28,300 sq.ft.) once a year at $378-779.

Estimates Sources

    •     Radian, 1983
    •     SCS, 1981
    •     US EPA, OERR contractor Feasibility Studies
                                       • 26-

-------
                                                         Surface-Water Control
                                                         Revegetation
2.4 REVEGETATION

2.4.1     Definition
      Re-establishing a vegetative cover may stabilize the surface of hazardous waste
disposal sites, especially when preceded by surface sealing  and grading.  Revegetation
decreases wind and water erosion, and contributes to the development of a naturally
fertile and stable surface, and reduces infiltration by enhancing evapotranspiration (i.e.,
increased loss of  soil moisture).  It also can be  used to  aesthetically  upgrade the
appearance of disposal sites that  are being considered for re-use.  Short-term vegetative
stabilization (i.e.,  on  a  semiannual or seasonal basis) also can be  used during ongoing
remedial actions.

2.4.2     Units of Measurement

Costs are given  in dollars per acre because revegetation is usually  given in terms of
acres.

2.4.3     Summary Statistics

2.4.3.1    Expenditures
      No actual expenditure data are available at this time.

2.4.3.2    Estimates
      The revegetation cost estimates ranged froms

Capital:     $l,214/acre             (1.76 acre site)
               to
             $8,000/acre             (20 acre site)
                                        -27-

-------
                                                  Surface-Water Control
                                                  Revegetation
Operation and Maintenance:
             $51/acre/year
               to
             $l,267/acre/year

The range of costs for revegetation reflects  the differences  in  the amount of work
needed for  different site conditions.  The highest cost estimate  was for a proposed
restoration of a secondary growth, temperate, deciduous forest, requiring heavy liming to
neutralize the highly acidic soil.  The lowest  cost was estimated for a hypothetical^
filled and graded fertile soil located on-site.

2.4.4     Factors Found to Affect Costs

2.4.4.1    Expenditures
No actual expenditure data were available at this time.

2.4.4.2    Estimates
      The following factors were found to affect the revegetation cost estimates;
    •    Soils
             New fill and grading required
             Terrain impediments (e.g., slope, berms)
             treatment for fertility
    •    Vegetation:
             Grass and/or trees (successional stage), multi-year planting
             Mulching and/or jute mesh stabilization

The cost of soil was not included in the estimates (see Table 9). However, for the New
Jersey Feasibility Study, 65,000 cubic yards of fill from  off-site was expected to be
necessary for the  72,600  square yard (15  acre) site (0.9  yards deep).  Also,  the  SCS
"landfill"  estimate includes  excavation,  grading  and recontouring  of the site (27,685
m3).  This was about 60% of the total cost of revegetation, including the overhead and
                                        -28-

-------
          TABLE 9
REVEGETATION COST ESTIMATES

         (1982 Dollars)
Data Source
US EPA
Feasibility Study
1983
New Jersey
US EPA
JRB - RAM
1980
US EPA
Radian
1982
Description
grasses
trees: pine &
hardwoods

grasses, mulching
1,000 evergreens
1,000 shrubs
hydroseeding
only (lime,
fertilizer, field
seed)
Soil
acidic
fill cost
separate
neutralized

tilled
loam
not given
Size
15 acres

20 acres
(5 sloped
15 level)
not given 2
assume 17.5
acres
Capital
$8,000/acre

$6,803
$l,791/acre
Operation &
Maintenance
$l,267/acre/year (1)

$1,022
$829/acre/year

-------
                          TABLES
          REVEGBTATION COST ESTIMATES (continued)

                        (1982 Dollars)
Data Source
US EPA
SCS
"Landfill"
US EPA
SCS
"Impoundment"
1980
Description
grading
hydroseed,
mulching
hydroseed,
mulching

Soil
fertile
soil
on-site
fertile soil
on-site

Size
13.4 acres
1.16 acres

Capital
$6,420-
$7m889 (2)
$1,214-
$l,827/acre
(2)

Operation &
Maintenance
$51/acre/year
$81-92/acre/year

(1)  First  5  years;  $140,000} second 5 years:  $50,000
(2)  Includes overhead  (25%) and contingency (10%)

-------
                                                        Surface-Water Control
                                                        Revegetation
contingency.  The  terrain was assumed to be flat in all estimates except  for the JRB

estimate, which assumed 25% sloped terrain and 75% flat terrain. The JRB estimate also

assumed a  three-year  planting schedule.   Different estimates  vary  as to  the type of

vegetation assumed. Hydroseeding was by far the least expensive means of revegetation

($0.37/sq. yd.) since it provides fertilizer, lime, and seed by  mass application  of a sprayed

liquid.  Trees and shrubbery cost significantly more because of higher material and labor

costs of individual  hand-planted nursery stock.  This higher cost of plants will also vary

with the type of stock selected.  The Radian report provided the following list of various

plant costs (in 1982 dollars), which included materials and installation:
    Item                            Cost ($)

Topsoil, furnish and spread
             4"                                   1.43/sq.yd.
             6"                                   1.90/sq.yd.

Sodding, 1-1/2" thick

             Level                                2.86/sq.yd.
             Slopes                               3.74/sq.yd.

Ground Covers

    Pachysandra                                  1.09/sq.ft.
    Vinca Minor                                   1.11/sq.ft.
    Privits, 15" tall planted in hedge row           2.34/LF
    Barberry, 15" tall planted in hedge row         3.03/LF
    Boxwood 16", tall planted in hedge row         2.84/LF

Trees and Shrubs

    Flowering Crab 8' - 10'                        222.12/ea
    Hawthorn 8'-10'                              170.90/ea
    Junipers, spreading 18" - 24"                   33.22/ea
    Junipers, upright 4' - 5'                        58.63/ea
    Yews, spreading 18" - 24"                      45.22/ea
    Yews, upright 2' - 3'                           54.63/ea
    Rhododendron 2'                              7L16/ea
    Fir 8'-10'                                    251.16/ea
    Hemlock 8' - 10'                              283.16/ea
    Beech 8' - 10'                                 222.16/ea
    Pine 8' - 10'                                   249.16/ea
    Tulip 8'-10'                                  244.16/ea
    Maple 2" diameter                             197.15/ea
    Maple 3" diameter                             362.24/ea
    Sycamore 4' - 5'                               46.22/ea
    Gold Locust                                   69.22/ea
         Source: Radian, Inc., 1982

-------
                                              Surface-Water Control
                                              Revegetation
Estimates Sources

    •    JRB- RAM, 1980
    •    Radian, 1983
    •    SCS, 1981
    •    US EPA, OERR contractor Feasibility Studies
                                    -32-

-------
                                                 Ground-Water & Leachate Controls
                                                 Impermeable barrier
                                                 Slurry Wall
                                     SECTIONS

                 3.0 GROUND-WATER AND LEACHATE CONTROLS
3.1  SLURRY WALL

3.1.1     Definition
      A slurry wall  is one  of several types of subsurface cut-off walls that  prevent
leachate formation by redirecting  upgradient ground-water away from a contaminated
area, and/or controlling horizontal leachate movement away from the site. A slurry wall
is constructed by filling a trench with a slurry such as bentonite on bentonite-soil-cement
during excavation.  The backfilled trench has a much  lower coefficient of permeability
than the surrounding soil and thus creates a barrier to flow of ground-water.

3.1.2     Units of Measurement
      Costs are given in dollars per square foot because square feet reflect the functional
area of a cut-off wall.  In  estimating the cost of a cut-off wall, the length and depth
(facial area) requirements are usually fixed by the extent of the waste and the depth of
the aquiclude.  Linear units were  not used because they would obscure the effect of
depth on slurry wall costs*

3.1.3     Summary Statistics

3.1.3.1    Expenditures
      The slurry wall expenditures ranged froms
          $0.25/sq.ft.
            to
          $31.96/sq.ft.
                                       -33-

-------
                                                  Ground-Water & Leachate Controls
                                                  Impermeable barrier
                                                  Slurry Wall
The lowest cost for a slurry wall was for a privately constructed, wall .using extensive in-
house equipment and labor.  The next lowest cost  wall was relatively shallow (14 feet
deep).  The highest  cost slurry wall was built partly in contaminated soil on a stream
bank.   Each scoop of  soil required analysis with  an organic vapor analyzer and  was
disposed at an engineered landfill.  The stream bank restricted and delayed access to the
construction area.  Operation  and maintenance costs involved ground-water  monitoring
and,  possibly,  costs  of repair.   These costs were  accounted for separately  where
information on them exists.

3.1.3.2    Estimates
      Slurry wall cost estimates ranged from?
             $4.50/sq.ft.    soil-bentonite
              to
             $13.86/sq.ft.

The highest slurry wall cost estimate ($11.56/sq.ft.) was for a Wyoming bentonite slurry
wall.   The lowest estimate was for a  competitively bid soil-bentonite slurry wall, for
which another contractor was deemed more  reliable.  Operation and maintenance costs
such  as inspection, ground-water  monitoring, and repair were  not  included in  the
estimates.
                                       -34-

-------
                                                  Ground-Water <5c Leachate Control
                                                  Impermeable barriers
                                                  Slurry Walls
 3.1.4      Factors Found to Influence Cost

 3.1.4.1    Expenditures
      The following factors primarily affected slurry wall expenditures:
          •   Depth
          •   Thickness
          •   Wall material
          •   Inclusion of related costs:
                Staging area set-up
                Contaminated trench soil disposal

 Perhaps the  most salient factor affecting costs (shown  in  Table 10) was  the wall
 material.  Cement-soil-bentonite walls were the most expensive walls; soil-bentonite was
 in the middle  of the cost range, and local clay was the least expensive.  Much of the local
 clay used for  the $1.80/sq.ft. California slurry  wall was dredged from the adjacent bay.
 Depth affected costs since a larger excavator (such as a CAT 215 or clamshell instead of
 a backhoe) was necessary for digging deeper trenches.  Once mobilized, however, larger
 equipment is  capable  of increasing the  trench  depth at a reduced marginal cost.  Wall
 thickness was directly proportional to the volume  of soil excavated and the volume of
 slurry mixed into the  trench.  Since  costs are given in terms of dollars per square foot,
 the cost for this  added volume is not precisely reflected in the face-area cost.  However,
 most of the walls had very similar thicknesses, at  between 30-36 inches, with two walls
 varying  by two  feet.    The  different thicknesses  generally stem from   different
 requirements  set forth in a consent decree state or federal agency mandate, and usually
 account for the variable  permeabilities of different slurry wall materials.
      Other related costs played a significant role in at least two cut-off walls.  At the
 Pennsylvania  site, a large volume of contaminated trench soil required disposal at  an
 engineered landfill.  Adding to these  disposal costs, was the need to test each excavator
scoop with an  organic vapor analyzer, which slowed trench construction.
                                        -35-

-------
         TABLE 10
SLURRY WALL EXPENDITURES

       (1982 Dollars)
DATA SOURCE
US EPA
ELI/JRB
1981
Pennsylvania
US EPA
JRB/ELI
1979
Colorado
US EPA
JRB
Florida A
(Date unknown)
US EPA
CH2 M Hill
1982
New Hampshire
LENGTH & DEPTH
648 feet
X
17 feet

1 ,500 feet
X
20 feet
2,290 feet
X
30 feet


3,500 feet
X
60 feet
THICKNESS
1 foot

30 inches
30 inches


3 feet
MATERIAL
cement-
bentonite

85% soil-
ben ton ite;
1 5 % cement
soil-
bentonite


soil-
bentonite
UNIT COST
$31.96/sq.ft.

$8.33/sq.ft.
$5.88/sq.ft.


$5.64/sq.ft.

-------
                                               TABLE 10
                                SLURRY WALL EXPENDITURES (continued)

                                             (1982 Dollars)
.DATA SOURCE
US EPA
JRB
(Date unknown)
Louisiana
US EPA
JRB
(Date unknown)
Florida B
US EPA
ELI /JRB
(1983 Dollars)
California

US EPA
ELI/JRB
1980
Arkansas

LENGTH & DEPTH
1 ,500 feet
X
20 feet

2,900 feet
X
20 feet

2,765 feet
X
14 feet

2,306 feet
X
48 feet
THICKNESS

3 feet



3 feet


5 feet




3.2 feet

MATERIAL
soil-
r
bentonite

soil-

ben ton ite
local

clay


local

clay
UNIT COST

$2.78/sq.ft.



$2.60/sq.ft.


$1 .42/sq.ft.




$0.25/sq.ft.

OJ
•»J
I
      US EPA
      ELI/JRB
      1983
2360 ft
   x
 30 ft
3 ft
               soil  -
               bentonite
$3.80/sq.ft.

-------
                                                  Ground-Water & Leachate Controls
                                                  Impermeable barrier
                                                  Slurry Wall
The cost given at the Arkansas site may not reflect all slurry wall costs since significant
in-house labor and  equipment were used but not recorded.  Other related costs such as
site preparation and geotechnical investigations were inconsistently noted as separate or
included.  Generally, these costs were excluded from the slurry wall expenditures.
              >.
3.1.4.2    Estimates
      The following factors affected the estimated costs for slurry walls:
    •    Depth
    •    Thickness
    •    Material
    •    Inclusion  of related costs:
          -  Geotechnical investigation
          -  Overhead and contingencies

Material costs were again the most clear cost factor in the slurry wall cost estimates
(Table 11).  The highest cost wall ($10/sq.ft.) was the cement-bentonite wall at the New
York  site.  Slurry wall depth seemed to be, at best, a secondary factor. The deepest (130
foot deep) slurry wall at the New Jersey  site was the second to least costly while the
shallowest (14 foot) slurry wall was the most  costly.
      However, the  construction  of the 130  foot  deep slurry wall  would be greatly
facilitated by  the  coastal plain sediment of  New Jersey for which it  was proposed.
Complete hydrogeological assumptions were not given for all of the estimation scenarios,
but a  1980 paper by Ressi di Cervia (see Table 12) gave the following depth-soil condition
cost matrix.  The slurry wall thicknesses varied less than did those of the wall studied for
the actual expenditures.  Only one hypothetical slurry wail was over 3 feet thick.
                                       -38-

-------
                                                 TABLE 11

                                       SLURRY WALL COST ESTIMATES



                                                (1982 Dollars)
DATA SOURCE
US EPA
CH2 M Hill
1983
New York
US EPA
Weston
1982
New Hampanire
US EPA
Bids
1982
New Hampshire
US EPA
JRB-RAM
1980
LENGTH & DEPTH
7,900 feet
X
14 feet

3,733 feet
X
70 feet (1 )
3,500 feet
X
60 feet

1 ,000 feet
X
40 feet

THICKNESS

over 2 feet


3 feet

3 feet



3 feet

MATERIAL

concrete


soil-
ben tonite
soil-
ben ton ite

soil-
bentonite

UNIT COST

$10/sq.ft.


$8.05/sq.ft.

$7.35/sq.ft.



$7.08-13. 86/sq. ft.

OJ
VD
I
      (1) Dimensions assumed for costing
         (3,125 feet x 50 feet expected).

-------
                                                TABLE 11
                                 SLURRY WALL COST ESTIMATES (continued)

                                               (1982 Dollars)
DATA SOURCE
US EPA
Radian
1982
US EPA
CH2 M Hill
1983
New Jersey Site A
US EPA
SCS
"Impoundment"
1980
US EPA
SCS
"landfill"
1980
LENGTH & DEPTH
100 feet
X
40 feet
114,715 sq.ft.
911 feet
X
49 feet
2,362 feet
X
49. feet
THICKNESS
4 feet
24-30 inches
•3.28 feet
3.28 feet
MATERIAL
soil-
ben ton ite
soil-
bentonite (5ty
Wyoming
bentonite-
water (1 :12)
bentonite-
water (1:12)
UNIT COST
$6.94/sq.ft.
$6/sq.ft.
$6.49-11.56/sq.ft.
$6.02-10.50/sq.ft.
o

-------
               TABLE 11
SLURRY WALL COST ESTIMATES (continued)

              (1982 Dollars)
DATA SOURCE
US EPA
Bids
1982
New Hampshire
US EPA
COM, Inc.
1983
New Jersey Site B
US EPA
Bids
1982
New Hampshire

LENGTH & DEPTH
3,500 feet
X
60 feet

4,257 feet
X
130 feet
3,500 feet
X
60 feet

THICKNESS

3 feet

not given
3 feet

MATERIAL
soil-
bentonite

soil-
ben ton ite
soil-
ben ton ite

UNIT COST

$5.44/sq.ft.

$4.88/sq.ft.
$4.50/sq.ft.


-------
                                          TABLE 12
                           SLURRY WALL COSTS:  DEPTH EFFECTS
                       Slurry Trench Prices
                       In 1982 Dollars
                       Soil Bentonite Backfill
                       (Dollars/Square Foot)
Unreinforced Slurry Wall
Prices in 1982 Dollars
Cement Bentonite Backfill
(Dollars/Square Foot)
Depth Depth Depth
30 30-75 75-120
Fee Feet Feet
Soft to
Medium Soil
N 40 3-5 5-10 10-13
Hard Soil 5-9 6-13 13-25
N40-
Oceasional
Boulders 5-10 6-10 10-32
Soft to Medium
Rock, Sandstone,
Shale 8-15 13-25 25-64
N 200
Hard Rock
Granite, Gneiss,
Schist* _____ ™
Depth
60
Feet
19-25
32-38
25-38
64-76
121-178
Depth
60-150
Feet
25-38
38-51
38-51
76-108
178-222
Depth
150
Feet
38-95
51-121
51-108
108-222
•
222-298
Notes: N = standard penetration value in number of blows of the hammer per foot of penetration
(ASTM D1586-67)

*Normal Penetration Only

For standard reinforcement add $8.00 per sq. ft.
For construction in urban environment add 25% to 50% of price
Reference: Ressi di Cervia 1980.
                                            -42-

-------
                                                   Ground-Water <3c Leachate Controls
                                                   Impermeable barrier
                                                   Slurry Wall
     Additional costs were included in at least two of the estimates.  Both geotechnical
investigation (impoundment: $11,210-23,010; landfill:  $4,543-7,694) costs and overhead
(25%) and contingency costs (30%) were included in the SCS estimates.  Geotechnical
investigation and permeability testing costs were grouped together ($23,600-94,400) in
the JRB estimate.
Expenditure Sources
    o     ELI/JRB Case Studies, 1983
    o     JRB,  1983
    o     State and Federal Superfund Work

Estimates Sources
    o     JRB-RAM, 1980
    o     Radian, 1983
    o     SCS,  1981
    o     US EPA, OERR, Feasibility Studies.
                                       -43-.

-------
                                                  Ground-Water & Lacheate Controls
                                                  Impermeable barrier
                                                  Grout Curtain
3.2  GROUT CURTAINS
3.2.1     Definition
      Generally, grouting is the injection under pressure of one of a variety of special
fluids into a rock or soil body to seal and strengthen that body.  Once this fluid gels in
the  rock or  soil  voids, it  greatly reduces  the permeability  of,  and increases  the
mechanical strength of  the grouted mass.   When carried out in the proper pattern  and
sequence, this process can result in a curtain or wall that can be a very effective ground-
water barrier.  Grouting is  rarely used when ground-water has to be controlled in soil or
loose overburden.   The  major use  of  curtain  grouting is  to seal  voids in porous or
fractured rock  where other methods  of ground-water control are impractical.   The
injection process itself involves drilling holes to the desired depth and injecting the grout
with the  use of special equipment.  A line of  holes  is drilled in single, double, or
sometimes triple staggered  rows (depending on the site characteristics) and injecting the
fluid in  either  descending  stages with  increasing pressure, or ascending stages with
decreasing  pressure.  The  spacing  of the  injection holes is  also  site-specific and is
determined  by the penetration radius of the  grout out from the holes. Ideally, the grout
injected in adjacent holes should fuse between them. If this process is done properly, a
continuous,  impervious barrier (curtain) will be formed.

3.2.2      Unit of Measurement
     Costs  are given in  terms of dollars  per unit face-area (square feet) because it best
reflects the functional area  of the grout curtain.  The effect of other dimensions on costs
is discussed in section 3.2.4 (Factors Found to  Affect  Costs).  Since the units used in
existing  engineering estimates  have  varied  widely,  the  effect  of using  different
dimensions is an important consideration for comparing estimates.
                                        .44.

-------
                                                  Ground-Water 
-------
                                                  Ground-Water & Leachate Controls
                                                  Impermeable barrier
                                                  Grout Curtain
3.2.4     Factors Found to Affect Costs

3.2.4.1    Expenditures
      The following factors seemed to affect expenditures:

     o    Market entry losses
     o    Labor costs.

The cost of grout curtains seemed to be primarily affected by market conditions.  The
industrial contacts who supplied the  data in Table 13 noted that, compared to the costs
shown,  the prices  will  decrease and stabilize in the future now that  the  firm has
penetrated  the market.   They  also  noted that the  cost  at the California site was
significantly affected by  the relatively high local labor costs.  For contrast, a privately
built grout curtain in Dallas, for which no data were available, was said to have cost less
than half the latest California wall.

3.2,4.2    Estimates
      The following factors affected grout curtain cost  estimates?
     o    Thickness
     o    Material composition
     o    Installation technique
     o    Inclusion of related costs:
          -  Geotechnical investigation
          -  Overhead and contingency.

The most significant cost factor affecting grout curtain cost estimates (Table 14) was
the wall thickness.  This was assumed to be equal to the center-to-center distance of the
grout injections  for single  row  walls, which is  equal to the diameter for adjacent
injections.   The nine foot  thick wall,  which was expected to be necessary to enclose an
impoundment, was the highest estimate.
                                        =46-

-------
                                   TABLE 13

                         GROUT CURTAIN EXPENDITURES


                                  (1982 Dollars)
Data Source
US EPA
ELI/JRB
California
1982
US EPA
ELI/JRB
California
1980
US EPA
ELI/JRB
Michigan
1980
Length x Depth
2,929 feet
X
17 feet
2,000 feet
X
17 feet
1,465 feet
X
10 feet
Thickness
0.83 feet
0.83 feet

1 foot

Material
ASPEMIX (1)
ASPEMIX (1)

ASPEMIX

Unit Cost
$14/sq.ft.
$8.26/sq.ft.



(1)  Asphalt, concrete and sand  emulsion installed
    with vibrating beam

-------
                                           TABLE 14
                                GROUT CURTAIN COST ESTIMATES

                                          (1982 Dollars)
Data Source
SCS
"Impoundment"
1980
SCS
"Landfill"
1980
' US EPA
JRB/RAM
1982
US EPA
Radian
1982
Length x Depth
902 feet
X
49 feet

7,117 feet
X
49 feet

800 feet
X
20 feet
1,000 feet
X
20 feet
Thickness
9 feet

5 feet


3 feet

3 feet
Material
phenolic
resin

phenolic
resin

silicate

silicate
Portland
cement
Unit Cost
$38.94-75.52/sq.ft.

$33 - 68.44/sq.ft.



$11.54 - 17.17/sq/ft.
$21.80/sq.ft.
$ 11.80/sq.ft.
F

-------
                                              TABLE 14

                              GROUT CURTAIN COST ESTIMATES (continued)



                                             (1982 Dollars)
Data Source
US EPA
ORD - MERL
1979
New Jersey
US EPA
4 bids
1982
New Hampshire
Length x Depth
4 s 600 feet
X
40 feet
3,500 feet
60 feet
Thickness
3 feet
not given
(assume 1 foot)
Material
not
given
ASPEMIX
Unit Cost
$6.22 - 10.48/sq.ft.
$5.50-$6.86/sq.ft.
vo
I

-------
                                                  Ground-Water & Leachate Controls
                                                  Impermeable barrier
                                                  Grout Curtain
Comparing the cost estimates based on dollar-per-linear-foot and a dollar-per-cubic-foot

basis is useful for discerning the effect of thickness on the estimates. The following list
shows that the cost ranking is aberrant compared to the depths when measured on a cost-

per-linear-foot basis.


     Date              Depth        Unit Cost    Cost Ranking ($/sq.ft.)

     1982              60 feet       $  330-412/ LF      6
     1980              49 feet       $1,908-3700/LF     1
     1980              49 feet       $l,619-3353/LF     2
     1979              40 feet       $  249-419/ LF      5
     1982              20 feet       $  230-340/LF      4 a
     1982              20 feet       $  420/LF        3
     1982              20 feet       $  240/LF        4b


The  costs show neither an ordinated ranking according to depth,  nor do they show an
evenness (X= $1,102/LF; SE= $365/LFj n=12) that would suggest that simple length was

the most significant cost factor.

     Similarly, the effect of thickness and depth on cost can be elucidated by comparing
costs on a  per-volume  basis.   The following list shows  that the cost  estimates are

relatively even (X= $5.30/cu.ft.; SD= $2.90/cu.ft.; n= 12).


Date     Thickness     Unit Cost                  Cost Ranking ($/sq.ft.)

1980      9 feet        $4.33-8.26/cu.ft.              3
1980       5 feet        $6.61-13.69/cu.ft.             1
1982      3 feet        $7.30/cu.ft.                   2
1982       3 feet        $3.80-5.72/cu.ft.              4 a
1982      3 feet        $3.90/cu.ft.                   4b
1979      3 feet        $2.03-3.43/cu.ft.              5
1982      1 foot        $5.50-6086/cu.ft.              6
                                       -50-

-------
                                                 Ground-Water <5c Leachate Controls
                                                 Impermeable barrier
                                                 Grout Curtain
     The data are inadequate to provide any accurate generalization about the relative
costs of various grout materials.  Plans for use of phenolic resin for grout curtains, gave
rise to the two highest estimates; two plans for silicate walls were each more costly than
plans for portland cement walls, and four bids to construct an ASPEMIX wall, composed
of an emulsion of asphalt, sand and concrete to be installed with a vibrating beam, were
the least  costly. Since no "control"  estimate  was available to contrast the cost of an
ASPEMIX  wall installed  with a  traditional injection  technique  as  opposed to  the
prescribed installation technique, techniques and materials  cannot  be separately judged
as to their individual costs.  However, the vibrating beam method may be generally less
expensive than the traditional injection technique.
     Finally, the cost of a geotechnical investigation was included only in the JRB and
the SCS  estimates.  The  SCS estimate also included overhead (25%) and contingency
allowance (30%).
Expenditure Sources
    ••    ELI/JRB Case Studies, 1983
Estimates Sources
    •     JRB-RAM, 1980
    •     Radian, 1983
    •     US EPA, OERR contractor bids
    •     SCS,  1980
                                       -51-

-------
                                                  Ground-Water & Leachate Controls
                                                  Impermeable barrier
                                                  Sheet Piling
 3.3  SHEET PILING

 3.3.1     Definition
      Sheet piling can be used to form a continuous ground-water barrier of driven steel
 piles.  Although sheet piles  can also be made of wood or precast concrete, steel is the
 most effective in terms  of cutting  off  ground-water and  ease of installation.   The
 construction of a steel sheet piling cut-off wall involves driving interlocking piles into
 the ground using a pneumatic or steam-driven pile driver. In some cases, the piles are
 pushed into pre-dug trenches.  Piles are commonly 4 to 40 feet long and 15 to 20 inches
 wide.  Because of corrosion and leaky joints usually present between piles, this method is
 often considered a temporary stop-gap measure.
3.3.2     Unit of Measurement
                                                          «
      Costs are given in terms of dollars per square foot because area best reflects the
functional units of a cut-off wall.

3.3.3     Summary Statistics

3.3.3d    Expenditures
      No actual expenditure data for sheet piling cut-off walls were available at this
time.

3.3.3.2    Estimates
     The cost estimates for sheet piling cut-off walls ranged froms
          $8.02/sq.ft.
           to
          $17.03/sq.ft.
                                        -52-

-------
                                                  Ground-Water & Leachate Control
                                                  Impermeable barrier
                                                  Sheet Piling
The largest site, which was constructed with 116,228 sq.ft. of sheet piling, produced the
lowest estimate for a sheet piling cut-off wall.  Costs-per-square-foot of the large wall
was effectively reduced  because the cost of mobilization  of equipment (a fixed cost)
could be spread over a larger surface area.

3.3.4     Factors Found to Affect Costs

3.3.4.1    Expenditures
      No actual expenditure data are available at this time.

3.3.4.2    Estimates
      The following components  affected the cost  estimates for sheet piling cut-off
walls:
     •    Economies of scale
     •    Piling type
     •    Inclusion of related costs:
             Geotechnical investigation
             Overhead and contingency allowances

As  noted above in Comments on the summary statistics, the limited data in Table 15
suggest that economies of scale may be the most significant factor affecting  costs.
Experienced  personnel using specialized equipment  (e.g., pile drivers) may be able to
install sheet piling at  decreasing cost-per-unit area as the  total area of installed wall
increases.  This is due to the high cost  of mobilization and erection of sheet piling as
compared to  other remedial technologies.
                                        -53-

-------
                                                  Ground-Water <5c Leachate Controls
                                                  Impermeable barrier
                                                  Sheet Piling
      Among the estimate scenarios,  the piling types varied both in composition and in
thickness.  Galvanized steel ($10.48/sq.ft. installed) which provides somewhat  greater
corrosion  resistance,  was  slightly  more  expensive  than  black  steel  ($9.41/sq.ft.
installed). The paucity of data on piling thicknesses precludes accurate quantification of
their relationships to  costs.  However,  this  variable  may  often be  dictated  by the
availability of local material and geological constraints.  Piles are typically withdrawn
and  reused, and the thickness of the piles may affect the reusability.  Hence the rebate
value of piles is affected, since a pile which is too thin may buckle upon insertion.  The
effect of thickness and reusability on  the cost may be significant since materials  may be
80% of the total cost of a sheet piling  cut-off wall. The cost estimates given Table 14 do
not  include cost credits for reuse  of the  piles,  but do include varying pile types,  as
indicated. The cost of a geotechnical investigation as noted in Table 15 ($11,210-23,010)
was  included only in the SCS  "impoundment"  estimate.  Additional costs for overhead
(25%) and contingency allowances  (25%) were included  in this estimate and the  SCS
"landfill" estimate.

Estimates Sources

     •     JRB-RAM,  1980
     •     Radian, 1983
     •     SCS, 1980
                                       -54-

-------
                                           TABLE 15

                                  SHEET PILING COST ESTIMATES



                                          (1982 Dollars)
Data Source
US EPA
JRB - RAM
1980
US EPA
Radian
1982
US EPA
SCS (1, 2)
" Impoundment"
1980
US EPA
SCS (2)
"Landfill"
1980
Lenth x depth
1,000 feet
X
20 feet
1,000 feet
X
20 feet
2,372 feet
X
49 feet
2,373 feet
X
49 feet
Weight
186 tons
Not given
487 tons
1,281 tons
Piling
5 guage
black steel
galvanized
5 guage
PMP-22
Unit Cost
$17.03/sq.ft.
$9.41/gq.ft.
$10. 48/ sq.ft;
$8.42-12. 63/sq. ft.
$8.02-11.80/sq.ft.
(1)  Includes geotechnical  investigation
    ($11210 - 23,010)
(2)  Includes overhead  (25%) and contingency
    (25%)  allowances

-------
                                                      Ground-Water «5c Leachate Controls
                                                      Impermeable barriers
                                                      Grout bottom sealing
3.4 BOTTOM SEALING BY GROUTING

3.4.1        Definition
       Bottom  sealing  by grouting is a  direct technique  for  installing  a barrier  to
downward  leachate  migration.  Grout is injected  through the fill material to form a
bottom underneath the contaminants.  The grout is injected horizontally from jets at the
bottom of  a pipe, which is inserted with a pneumatic hammer.  A grid of injected grout
forms  a contiguous bottom  seaL   Grout materials are typically  silicate or portland
cement.

3.4.2        Units of Measurement
       Costs are given in terms of dollars per square foot because area best reflects the
functional  characteristics of bottom sealing.

3.4.3        Summary Statistics

3.4.3.1      Expenditures
       No actual expenditure data are available at this time.

3.4.3.2     Estimates
       The  grout bottom  sealing costs ranged from:
           $9/sq.ft.
             to
           $116/sq.ft.

This wide  range  of estimates seems to reflect  the varying thicknesses  given for
hypothetical seals.   The higher  estimate  was for a 5.25-foot thick seal vs. a 3.25-foot
thick seal for the lower estimate.
                                        •56-

-------
3.4.4
                                                      Ground-Water <5c Leachate Controls
                                                      Impermeable barriers
                                                      Grout bottom sealing
Factors Found to Affect Costs
3.4.4.1      Expenditures    	
       No actual expenditure data are available at this time.
3.4.4.2
Estimates
       In the designs used for the grouting estimates, the following components varied:
      •     Grout thickness
      •     Grout material
      •     Coverage
      •     SoH, fill type
Of these components,  the thickness of grout appeared to be on direct proportion to the
variation in the cost of the two grouting seals shown in Table 16. The "landfill" seal was
2  feet (61%) thicker than the "impoundment" grout.  Thickness appears to  affect the
estimates more than does the type of grouting material.  Material costs for phenolic
resin are  significantly higher  than for portland  cement grout, but overall, a  thicker
cement grout is required for a wall of equivalent permeability.
       Economies of scale may have caused the "landfill" grouting to be less expensive on
a  cost per-unit-area basis than the impoundment grouting since  the  landfill scenario
assumed  ten  times as  much  coverage.    Despite  this disparity in  task size,  the
geotechnical investigation (impoundment:  $11,210-23,010; landfill:  $15,104-25,559) and
equipment cost were relatively similar.
Overhead (25%) and contingency allowances (40%) were the same for both seals.
       The effect of injection through heterogeneous, resistant fill and soil probably is a
significant cost factor  in the "landfill" estimates, although  it is impossible to quantify
from the available information.

Estimates Source

     SCS 1980
                                       -57-

-------
                                                  TABLE 16

                                      GROUT BOTTOM SEALING ESTIMATES



                                                (1982 Dollars)
Data Source
US EPA
SCS
"landfill"
1980
US EPA
SCS
"Impoundment"
1980
Grout Material
Thickness

cement
5.25 feet

phenolic resin
3.28 feet

Depth

49 feet

49 feet

Coverage

559,704 sqft

5,038 sqft

Unit Cost

$60 - $116/sq.ft.

$9 - $18/sq.ft.

I
Ul
00

-------
                                                      Ground-Water & Leachate Controls
                                                      Permeable Treatment Bed
3.5  PERMEABLE TREATMENT BED
3.5.1
Definition
       A permeable treatment bed is subsurface  bed or wall of a permeable filtering
material, typically  constructed as  a  trench  back-filled  with activated carbon  or
limestone, which is designed to decontaminate shallow ground-water as it flows through
the bed.  It is most unusual to "precipitate metalic  ions!"  This may be the latest  on
potential energy storage  systems, since ions  are, by definition,  charged particles  (this
renders them soluableX
       The principal constituent of Calcium  carbonate,  chemically acts to neutralize
acidic ground-water.  Metal ions, once quite  soluable in the more  acidic ground-water,
form  insoluable  metal  liquids or precipitates  as  the  ground-water  becomes  more
alkaline.  Alternatively, metals and organics are both removed by physical and chemical
forces through the use of  activated carbon, which, through  its high surface  area  to
volume ratio and large number of available surface  sites, absorbs  dissolved molecules
directly  from  the ground-water.  The six primary component tasks of treatment  beds
(generally included in the costs) are:
     •     Trench excavation
     •     Spreading
     •     Well-point dewatering
     •     Sheet piling
     •     Walers, connectors, struts
     •     Bedding (limestone or carbon).

Permeable treatment beds represent a developmental remedial technology,  the costs of
which are not well documented  to date.
                                       -59-

-------
                                                     Ground-Water <3c Leachate Controls
                                                     Permeable Treatment Bed
3.5.2       Units of Measurement

      Costs of permeable treatment beds are given in terms of dollars per square foot because it bes
expresses the functional value of the treatment bed.  The width and depth of the leachate plume fo:
which a bed is to be estimated are usually known.


3.5.3       Summary Statistics


3.5.3.1     Expenditures

      No actual expenditure data for permeable treatment was available at this time.


3.5.3.2     Estimates

      The cost estimate for permeable treatment beds ranged from:
           $14/sq.ft.   limestone  bedding

             to
           $267/sq.ft.   activated carbon bedding
                                      -60-

-------
                                                     Ground-Water & Leachate Controls
                                                     Permeable Treatment Bed
       The least  costly permeable treatment bed was for a limestone bed; whereas the
 high estimate was for a bed of granular activated carbon.  Operation and maintenance
 costs,  when  given,  consisted of the  following two cost  items  which  depend on site
 specific variables:
      Operation and maintenance
      Cost Items
     (1)    Ground-water monitoring cost
     (2)    Replacement cost
                                         Site-specific
                                         Variables
                                           contaminants
                                           hydrogeologoy
                                           operational lifetime of
                                           treatment bed
3.5.4
Factors Found to Affect Costs
3.5.4.1      Expenditures
No actual expenditure data are available at this time.

3.5.4.2      Estimates
      The following factors were found to affect the treatment bed estimates:

            •      Bedding Material
            •      Size

The estimates made by  JRB and Radian shown in Table 17 are very similar except that
17%  was added to most of the Radian costs for inflation.  However, the same unit cost
for limestone and carbon was assumed. The  bedding cost was the most significant (90%)
no-cost  out of the total for the carbon treatment bed.  The most significant cost (75%)
for the  limestone treatment bed was the cost of sheet piling.  Conversely, the bedding
cost  was 7% of the total for the limestone  bed; whereas for the carbon bed, the sheet
piling was 8% of the total cost.
                                       -61-

-------
                                                      Ground-Water & Leachate Controls
                                                      Permeable Treatment Bed
      Although all estimates of  cost  are  for  treatment beds of the  same size, the
influence of size on unit costs should be noted briefly: First, increases in the dimensions
of the bed generally will proportionately increase total costs of the treatment bed. The
effect is more pronounced with simultaneous increases in width and depth, in proportion
to the incremental change of width mutiplied by the incremental change in depth. The
cost of a larger carbon trench could be  significantly different than any of the estimates
given in Table 17 due to the high  cost of activated carbon. Second, economies of scale
could reduce the unit costs of limestone treatment beds over that given in the estimate,
since reusable sheet piling, which has significant one-time set up and mobilization costs,
is the major (75%) component cost. Also, the marginal unit cost of dewatering decreases
as trench size increases.
Estimates Sources
     •     JRB-RAM, 1980
     •     Radian, 1983
                                       -62-

-------
                                     TABLE 17
                     PERMEABLE TREATMENT BED COST ESTIMATES

                                    (1982 Dollars)
Data Source
US EPA
JRB - RAM
1980

US EPA
Radian
1983

US EPA
JRB-RAM
1980

US EPA
Radian
1980
Area
1,000 feet
X
20 feet
1,000 feet
X
20 feet
1,000 feet
X
20 feet
1,000 feet
X
20 feet
Width
4 feet

4 feet

4 feet.

4 feet
Bed Material
activated carbon
bed

coarse size
activated
carbon

"gravel and sand
sized" limestone

"gravel and
sand sized"
limestone
Unit Cost
$267/sq^.ft
\.

$201/sq;ft.

$29/sq.ft.

$14-14.67/
sq/ft.
u>

-------
                                                      Ground-Water & Leachate Controls
                                                      Well point system
3.6 WELL POINT SYSTEM

3.6.1        Definition
       Well points are generally used to lower the water table or extract leachate. They
differ from  drilled and cased deep wells in that they are driven, instead of drilled, into
the ground to just below  the leachate plume.  Ground-water is then piped  to a suction
header, drawn by a centrifugal pump, to a  treatment system.  In contrast, deep wells
typically  use submersible  pumps  to  pump ground-water to  a  treatment system.
Treatment costs for costing purposes, are considered separately.

3.6.2        Units of Measurement
       Costs are given in terms  of dollars  per  well.  The extraction rate  (gallons per
minute-gpm) and depth should also be considered.  Since  these characteristics vary with
site- specific hydrology, however, costs given below do not account for pumping rate.

3.6.3        Summary Statistics

3.6.3.1      Expenditures
       No actual expenditure data are available at this time.

3.6.3.2      Estimates
      The cost estimates ranged from
            $803/well
             to
            $8,284/weU

The  highest  cost  estimate (SCS-"impoundment") included  the cost  of  geotechnical
investigation, which comprised  50% of the costs. No related costs were included in the
lowest estimate (Radian).
                                       -64-

-------
                                                      Ground-Water & Leachate Controls
                                                      Well point system
3.6.4
Factors Found to Affect Costs
3.6.4.1      Expenditures
       No expenditure information are available at this time.

3.6.4.2      Estimates
       The foUowing factors affected the cost estimates for the well point systems:
     •      Depth
     •      Pumping rate
     •      Related costs:
                  Geotechnical investigation
                  Overhead allowances
                  Contingency allowances

The  costs shown in Table 18 are relatively similar.  The  effect of depth, which was
expected  to  be an important cost  factor, did not significantly affect the estimates.
Although installation of well point is often charged by the depth, well installation was a
relatively small  component  of  cost compared to pumps and headers.  Hence, depth
affected cost estimates  in proportion to the impact of  well point installation on total
costs, which was  a small fraction of the total.  The pumping rate, which varied with the
size  of the pumps  and the header  system, should affect  both  capital,  operation and
maintenance  costs.  However, no relationship could be identified in the data.
      The most significant  cost factors that could be identified were the related costs.
Over half of the SCS "Impoundment" estimate was for a geotechnical investigation, that
was not included in  either of the other estimates. The SCS "Impoundment" and "Landfill"
estimates included overhead (25%) and contingency (25%) allowances.

Estimates Sources
           Radian, 1983
           SCS,  1980
                                       -65-

-------
                                                   TABLE 18
                                      WELL POINT SYSTEM COST ESTIMATES


                                                  (1982 Dollars)
Data Source
US EPA
SCS
1980

"Impoundment"
US EPA
SCS
1980
"Landfill"
US EPA
Radian

1983

-
# Wells; Depth; Diameter
5 wells
16 feet deep

__
133 wells
16 feet deep
— —
50 wells
25 feet

4 inches

Pumping rate
Aquifer depth
—


• — •
291-396 gpm

— ,
500 gpm


10 feet

Operation &
Maintenance
$9,160-
$9,970/year

10,000 kwh
$10,460-
$ll,270/year
36,000 kwh
$70.88/Mgd




Capital Unit Cost
$4,413-$8,284/well

(1)

g
$1,109-$!, 855/well
(2)

$803/well




vt
                            (1) Includes  geotechnical investigation cost (55%)
                            (2) Includes  geotechnical investigation cost (3%)

-------
                                                      Permeable treatment beds
                                                      Deep well system
3.7  DEEP WELL SYSTEM

3.7.1       Definition
       Deep wells, aside from going deeper, are typically drilled and cased, in contrast to
shallower, driven well  points.  The  deep well systems considered in this section are
designated to dewater soil at greater depths, to extract leachate or to intercept flow of
ground-water upgradient of a site.

3.7.2       Units of Measurement
       Costs  are  given in terms of dollars per well. Cost per well per foot may also be
useful but available cost estimates assume the similar depths.

3.7.3.      Summary Data

3.7.3.1     Expenditures
       No expenditure data was available at this time.

3.7.3.2     Estimates
       Cost estimate ranged from
           $4; 862/well
             to    (both wells were at 46 feet deep)
           $13,513/weU

It  should  be  noted (see  Table  20) that 62% of the low estimate and 85% of the high
estimate were for (1) a  geotechnical investigation, (2) an overhead allowance (25%); and
(3) a contingency allowance (30%).  On the above range of cost, a cost-per-foot-per-well
basis would be $106-295/foot/welL
                                       -67-

-------
                                                      Permeable treatment beds
                                                      Deep well system
 3.7.4       Factors Found to Affect Costs

 3.7.4.1      Expenditures
       No expenditure data are available at this time.

 3.7.4.2      Estimates
       The following factor affected the cost estimates:
     •      WeU depth
     •      Well diameter
     •      Pumping capacity
     •      Related costs:
                  geotechnical investigation
                  overhead allowance
                  contingency allowance
Variations  in depth of  well are not quantified in the data,  but  costs of drilling wells
typically vary with depth. Variations in diameters of wells are also not given in the data,
and therefore  are not quantifiable, but costs for wells of larger diameter are generally
proportionally higher because of increases in costs of labor, equipment and material. The
effects of  pumping capacity on capital expenditures are difficult to quantify because of
the importance of site-specific hydrogeology to well yield (e.g., increasing the pump size,
and hence  cost, may have no  effect on well yield if the well does not recharge quickly
enough  to  justify the larger pump).   Any consideration of cost functions for'pumping
capacity must regard hydrogeology, pump capacity and well design.  Costs of electricity
for pumping comprised about  5-10% of the costs of operation and maintenance.  Hence,
this component  of cost, which varies directly  with pumping capacity has  a relatively
small effect  on total O&M costs compared to the other cost items of operation and
maintenance such as sampling  and analysis.
                                       -68-

-------
                                                    Permeable treatment beds
                                                    Deep well system
Related costs had the greatest discernible effect on cost estimates since they comprise
the majority of  both  estimates.  Table 19 shows the proportion of total capital cost
involved in these related components for estimates given in Table 20.
                                    TABLE 19
                 COMPONENT COSTS OF DEEP WELL ESTIMATES
Estimate     Geotechnical   Overhead   Contingency
source      Investigation   Allowance  Allowance   Total
SCS          30%       25%      30%      85%
"Impoundment"

SCS           7%        25%       30%      62%
"Landfill"
The reason for the significantly higher proportional and absolute cost estimate for the
smaller impoundment (1.16 acres, 5 wells) compared to the landfill (13.4 acres, 13 wells)
is unclear.
Estimated Sources
     •     SCS 1980
                                      -69-

-------
                                        TABLE 20
                               DEEP WELL COST ESTIMATES

                                       (1982 Dollars)
Data Source
US EPA
SCS
"Impoundment"
1980

US EPA
SCS
"Landfill"
1980


Depth, diameter, // wells
46 feet deep

6 inches pvc

5 wells
46 feet deep
6 inches pvc
13 wells


Pumping
submersible
pumps 574 foot
header to 3 'deep
discharge trench

submersible
pumps. 1 hp,
984 foot header
to gravel
filled discharge
trench


Ooeration &
Maintenance
$9,110-9,9207
year



$9,830-
$10,640/year




Capital Cost
$7,443 - $13,513/well

(1)


$4,862 - $7,976/well
(2)



(1)  Includes  geotechnical  investigation  (30%)
    overhead  (25%)  and  contingency  (30%) allowance.
(2)  Includes  geotechnical  investigation
    (7%),  overhead  (25%) and  contingency
    (30%)  allowance.

-------
                                                      Ground-Water «5c Leachate Controls
                                                      Extraction/Injection Well System
3.8  EXTRACTION/INJECTION WELL SYSTEM

3.8.1       Definition
       Extraction/injection  wells are usually well points,  which are driven  into the
ground, or they are occasionally deep wells, which are drilled and cased.  A series of
extraction and injection wells (well points or cased, drilled wells) is given as the basis of
design from which  to compare costs.  Costs for  water treatment are not included.  The
system used as a basis  of design is sometimes referred to as a leachate recirculation or
plume containment system. In addition to decontamination of ground-water, this system
may be used to control migration of leachate.

3.8.2       Units of Measurement
       Total capital costs are given instead of unit costs for two reasons.  First, unlike
most other remedial technologies, extraction/injection systems are composed of several
components that are not readily interchanged since they  act as a unit.  Extraction,
injection and monitoring wells all comprise roughly equal parts of the system.  Capacity
in terms of gallons-per-minute was not used  because of its dependence  on  hydrogeology,
and this information was not usually available.

3.8.3      Summary Data

3.8.3.1     Expenditure
       No expenditure data was available at this time.

3.8.3.2     Estimates
       A range of estimates cannot  be given since the units of the two estimates were
not comparable (see Table 21).
                                       -71-

-------
                                 TABLE 21
                EXTRACTION/INJECTION WELL COST ESTIMATES
                                 (1982 Dollars)
Data Source
US EPA
JRB - RAM

1980

US EPA
Radian
1983



Extraction
7, six inch
well, 35 feet
deep
pvc casing

10, six inch
wells (1)
average depth
50 feet



Injection
7, six inch
wells (+ four
back up wells
pvc casing

six inch wells



Pumping
4 inch
submersible
pumps
8 inch transfer
pipe, 1,000 feet
submersible
pumps
50 gpm per well



Operation &
Maintenance
Not given




$70.88/Mgd
electricity
and
monitoring


Total Capital

$321,432



Not given (2)
C;$37.50/vertical
foot")


•
(1)  Based on "50 gpm per well,
    500  gpm/site".
(2)  Assuming 20 wells, 50 feet deep,  total
    capital cost = $37,500

-------
                                                      Ground-Water & Leachate Controls
                                                      Extraction/Injection Well System
3.8.4 Factors Found to Affect Costs

3.8.4.1      Expenditure
       No expenditure information is available at this time.

3.8.4.2      Estimates
       The following factors contributed to the cost estimates of the extraction/injection
well systems:
            •      number of wells
            •      depth of wells
            •      diameter of wells
            •      casing
            •      submersible pump capacity
            •      transfer pipe length and diameter

The paucity  of data precludes quantification of the effects of these factors.

Estimate Sources
            •      U.S. EPA, JRB-RAM, 1980
            •      U.S. EPA, Radian, 1983
                                       -73-

-------
                                                      Ground-Water & Leachate Controls
                                                      Extraction Wells/Seepage Basins
3.9  EXTRACTION WELI.S/SEEPAGE BASINS

3.9.1       Definition
       A series of extraction wells  is  used  to collect  ground-water, and a  seepage
basin/trench or recharge basin is used to recharge the ground-water.  This system, as
with the extraction/injection well system above, may have a treatment system placed in-
line, or it may be used simply to control flow of leachate.   Costs of treatment are not
considered in this section. Seepage basins are often used in permeable soil, such as the
glacial till, where injection wells are not needed for infiltration.

3.9.2       Units of Measurement
       Total capital cost  is  given instead of unit costs because, unlike most  other
remedial  technologies,  extraction  well/seepage  basins  are   composed  of  several
components that are not readily  interchanged since they  act as a unit.  Extraction and
monitoring wells, trench/basin size and pumping/transfer equipment all comprise roughly
equal parts of the system.  Capacity in terms of gallons-per-minute was not used because
of its dependence on hydrogeology.

3.9.3       Summary Data

3.9.3        Expenditures
       The one expenditure found  wass

            Total capital                    $31,269 (9.5 gpm total extraction,
                                           two 100-foot long seepage trenches)

Operation and maintenance                  $27,500/year

The expenditure was for two extraction trench wells (one 80 x 10 x 4 feet, another 4x10
x 16 feet) and two recharge trenches (100 x 4 x 10 feet).
                                       -74-

-------
                                                      Ground-Water & Leachate Controls
                                                      Extraction Wells/Seepage Basins
3.9.3.2      Estimates
       The range given in the one available source of estimate was:

     Total capital:                          $33,618 - 53,360
     Operation and Maintenance:             $10,856 - 11,812/year

This is actually from a single source that predicts a range of costs in the U.S.

3.9.4       Factors Found to Affect Costs

3.9.4.1      Expenditures
       The following factors affected expenditures:
     •      Number of wells
     •      Size of wells
     •      Depth of wells
     •      Pumping capacity
     •      Seepage basin design

Because of inadequate data and the lack of a similiar site, comparison of these factors is
not possible  (see Table  22).   However,  it should be  noted  that  many of the factors
affecting expenditures are similar to those affecting the subsurface drain, especially the
design  of the extraction well trench using stone of  decreasing size toward the inside of
the  trench.   This increased  capital expenditures, but  probably decreased  costs of
operation and maintenance.

3.9.4.2      Estimates
      The following factors affected cost estimates:

     •      Overhead allowance
     •      Contingency allowance
     •      Well size and number
     •      Pumping capacity
                                       -75-

-------
                                      TABLE 22
                   EXTRACTION WELLS/SEEPAGE BASIN EXPENDITURES


                                     (1982 Dollars)
Data Source
US EPA
ELI/JRB
1982
New Jersey



Extraction, .
(trench-well)
A. 80x4x10 feet-
12 inches (1)
8.16x4x10 feet-
8 inches pvc
TOTAL: 143 cuyd



Seepage basin
two trenches :
100x4x10 feet
(2)
TOTAL: 296 cuyd



Pumping
9.5 gpm
submersible
pump



Operation &
Maintenance
$27,500 (3)



Total Capital
$ 31,269
($71/cuyd)



(1)  Dual media, stone/pebble,  filter.
    Well slotted 2.5 feet.
(2)  Plywood shoring construction
(3)  Conservatively assumed
    to be 1/3 of water
    biotreatment operation
    & maintenance

-------
                                                      Ground-Water & Leachate Controls
                                                      Extraction Wells/Seepage Basins
The overhead and contingency allowance comprised 25% and 20%, respectively, of the
total  estimated  capital cost.  Size and  number  of wells would be expected to  be
proportional  to the cost, but  quantification is not  possible without other estimates for
comparison (see Table 23).  Pumping capacity would also be expected to be proportional
to cost, but hydrogeological factors affect this on a  site-specific basis.

Expenditure Sources

     •      ELI/JRB Case Studies, 1983


Estimates Sources

     •      SCS, 1980
                                       -77-

-------
                                                  TABLE 23

                              EXTRACTION WELLS/SEEPAGE BASIN COST ESTIMATES



                                                 (1982 Dollars)
Data Source
US EPA
SCS - "Leachate
Rec ir culat ion—
Landfill"
1980



Extraction
six deep wells
46 feet deep
(drilled, cased)



Injection
2,067 x 2x3
feet
6 inch cement
pipe, perforated
3/4 inch gravel



Pumping
six
submersible
pumps



Operation &
Maintenance
$9,200-
10,010/year
$10,856-
$ll,812/year

•

Total Capital
$33,618-553,360 (1)



I
-J
00
                                 (1) Includes 25% overhead and 20%

                                     contingency allowance

-------
                                                       Ground-Water & Leachate Controls
                                                       Subsurface Drain
3.10 SUBSURFACE DRAIN

3.10.1       Definition
       A subsurface drain is  basically an underground, gravel-filled trench designed to
intercept and transport leachate or infiltrating water away from the waste site.  Often,
perforated pipe or tile is laid along the trench bottom, draining to a collection sump or
tank.  The sides and bottom of the trench may be lined with plastic or clay before the
trench is backfilled with gravel.

3.10.2       Units of Measurement
       The unit costs for subsurface drains are given in dollars-per-unit-length  for three
ranges of trench depth  because facilitates quick cost estimates from a  single  trench
dimension.  Depth of trench was found to be the greatest  single factor affecting costs.
The  ranges in depth given in the Summary section 3.10.3.1 were determined  by the
aggregation found for the costs of the different trenches.  Variations may have  been
caused by technical factors discussed in section 3.10.4, such as type of excavator used
and sheet piling required.

3.10.3       Summary Statistics

3.10.3.1     Expenditures
       The expenditures for subsurface drains in three groups of depth ranges weres

     Cost per Unit Length
            $24/LF
     X =    $370/LF (SE=$208/LF, n=4)
            $1,733/LF
                                        -79-

-------
                                                       Ground-Water & Leachate Controls
                                                       Subsurface Drain
The 2 subsurface drains at  the high end of the range involved significant marginal costs
for false-starts, delays, and overdesigning.  The lowest cost drain was shallow enough
that  it  did not require sheet piling or wooden  shoring during construction.  Costs of
operation and  maintenance involve sampling and replacement costs.   Drains typically
remain  unclogged  for  10-20 years, but site  conditions and design of drains affects  this
operational period. Costs of operation and maintenance accounted for separately, where
they were encountered.

3.10.3.2     Estimates
      Estimates of cost for subsurface drains ranged from:
                  Capital:
                        $1.94/LF
                           to
                        $218/LF

                  Operation and maintenance:
                        $10,337/year
                           to
                        $ll,293/year

The range  of estimates spanning two orders of magnitude resulted from ancillary costs
and variations  of  depth.  The plan for the most costly drain included the cost for a
geotechnical investigation,  which accounted for  50%  of the  estimated cost.  The least
costly hypothetical drain  was  installed  1-2  feet  deep.    Costs  of operation  and
maintenance were  frequently noted but not consistently quantified.
                                       -80-

-------
                                                      Ground-Water <5c Leachate Controls
                                                      Subsurface Drain
 3.10.4      Factors Found to Affect Costs

 3.10.4.1     Expenditures
       The following factors were found to affect the costs of subsurface drains shown in
 Table 24.
            1.     contaminated soil removal
            2.     trench length and depth
            3.     plumbing complexity
            4.     gravel installation
            5.     storage tank or sump size

 Contaminated  soil,  which  may require  secure disposal,  may be encountered while
 constructing the trench or the sump.  Excavation of contaminated soil, which resulted in
 additional  costs  for  disposal,  occurred  when  trenches were constructed within  a
 contaminated area,  rather than at the site perimeter. This additional cost was incurred
 at the ELI/JRB Wisconsin  site #1 where hexavalent chromium-contaminated soil was
 disposed of from the  hole  excavated  for a sump.  The  PCB-contaminated soil at the
 ELI/JRB California  site #1, however,  was returned to the cap  because the system was
 considered an "Immediate Remedial Measure", not a long term remedy.  This provision
 eliminated the cost of off-site disposal of  the PCB-contaminated soil.
      The importance of the trench length and depth is discussed above in connection
 with unit  costs.   The  size of trench depended  on factors such as type  of  waste,
 permeability of soil, climate and purpose of the system. A relatively large, three-armed
 drainage system was used at the most costly site, ELI/JRB California site #1, because of
 the compact soil and the strong adhesion of the PCBs to the soil,  and because of the
seasonally  heavy  rains in the Mediterranean climate.  The length  of the drain at the
 ELI/JRB Michigan site  reflected its purpose of relieving hydraulic pressure on the  asphalt
 emulsion cut-off  wall.   The purpose of the relatively small drain  at trench A of the
 ELI/JRB New Jersey  site,  was to collect  contaminated water by creating  a  cone of
depression  of the water  table.   The size of the drains affected costs of construction by
dictating different installation methods between the deepest and the shallowest drains.
Steel sheet piling was driven into place to  support the 30 foot (10m) deep trenches

                                        -81-

-------
                                              TABLE 24

                                   SUBSURFACE DRAIN EXPENDITURES
                                             (1982 Dollars
Data Source
US EPA
ELI/JRB
1981
Wisconsin #2
US EPA
ELI/3RB
1982
Wisconsin #1
Length x trench
(filter) depth
240 feet
X
12 ( ) feet
750 feet
X
3 ( 1/3) feet
Width
4 feet

2 feet
Sump depth, etc.
15 feet

2 sumps :
4 feet
6 feet
Operation and
maintenance
$648/year
(a)
72,000 gal.
not given
Unit cost-capital
$36/LF

$24/LF
00'
N5
I

-------
                                                       Ground-Water 
-------
                                                      Ground-Water <5c Leachate Controls
                                                      Subsurface Drain
 were generally proportional to the size  of the collection trench.  The storage systems
 differed in types as well as size.  Large prefabricated concrete sumps were used at the
 end of some drains, whereas steel tanks or pipes were used at others.
 3.10.4.2     Estimates
 The following factors affected the estimates of subsurface drain cost shown in Table 25.

     •      trench (filter) depth and length
     •      storage tank or sump size and type
     •      related costs

 Trench and filter depth and length affected drain estimates in a manner similar to that
 described in the expenditure section above.   However, technical details (such  as  the
 gravel size, thickness, and  permeability  of  the filter and  backfill)  were often  not
 available for consideration.

 The SCS estimates were significantly affected by the inclusion of related costs such as:

                  geotechnical investigation
                  overhead allowance
                  contingency allowance

      The cost  of the geotechnical investigation was included only in the estimate for
 "Impoundment"  drain.  This element  comprised 50% of the  total cost of the drain.
 Overhead  (25%) and contingency (25%) allowances were added to both the "Impoundment"
 and "Landfill" estimates. The variations in the estimated costs of subsurface drains from
 JRB and  SCS were caused by a combination of two factors.   First, the JRB estimates
used unit  costs at the high  end of the range used by SCS.  Second, the JRB estimates
included three components not  included in the SCS estimates.  However, since these
 items were responsible for only $24.70 of the $694/LF difference (11%) in total unit cost
 between JRB and SCS, their influence was relatively insignificant.  The influence of
 component  unit  costs that  were  included was  therefore  more, significant r than  the
influence of component costs that were not included in the JRB  estimates.
                                       -84-

-------
                                                  TABLE 25

                                    SUBSURFACE DRAIN COST ESTIMATES
                                                (1982 Dollars)
Data Source
US EPA
SCS
"Impoundment"
1980
US EPA
SCS
"Landfill"
1980
US EPA
Radian
1982
US EPA
JRB-RAM
1980
Length x trench
(filter) depth -
197 feet
X
16(4) feet (1)
835 feet
X
20(13) feet (1)
1,000 feet
X
20(10) feet (1)
3,300 feet (3)
X
20(2) feet (1) .
Width
3.3 feet
3.3 feet
4 feet
4 feet
Sump depth, etc.
sump depth not
given
cement pipe in
drain
depth not given
4 inch cement
pipe in drain
sump depth not
given
perforated pvc
in drain
4 manholes;
2 wet wells;
15 lateral
drains (20' each)
Operation and
maintenance
$10,337-
$ll,293/year
50 gpm .
$10,337-
$ll,293/year
50 gpm.
$70. 88/
Mgd
50 gpm
not given
2 x 25 gpm
Unit Cost
$113 - 218/LF (2)
$26 - 38/LF
$28/LF
$15/LF
 I
'00
Ol !
 I
         (1) Trench (filter) depth shows excavated

             volume vs of gravel installed.,;

             respectively
(2)  Includes peotechnical

    investigation  (50%)
(3)  Includes  laterals

-------
                  TABLE 25
SUBSURFACE DRAIN COST ESTIMATES (continued)

                (1982 Dollars)
Data Source
US EPA
CH2 M Hill
Feasibility Study
1983
US EPA
Feasibility Study
1981
New Jersey
US EPA/NYS DEC
CH2 M Hill
Bids 1982
New York
Length x trench
(filter) depth
3,250 feet
X
15 (?) feet
2,495 feet
X
1-2 (?) feet
3,250 feet
X
15(?) feet
Width

not
given
not
given

not
given

Sump depth, etc.

not
given
4" slotted

not
given

Dperation and
maintenance

not
available
not
available

not
available

Unit Cost

$5.50/LF
$1.94/LF

$12/LF
$11.70/LF
$ 7/LF
$ 5/LF
$ 4/LF

-------
                                                   Aqueous & Solids Treatment
                                                   Activated Sludge
Expenditure Sources
     •     ELI/JRB Case Studies, 1983


Estimated Sources


     •     JRB-RAM, 1980

     •     Radian, 1983

     •     US EPA OERR contractor bids

     •     SCS 1980
                                     -87-

-------
                                                      Aqueous & Solids Treatment
                                                      Activated Sludge
                      4.0  AQUEOUS AND SOLIDS TREATMENT
4.1 ACTIVATED SLUDGE

4.1.1        Definition
       This treatment  technology involves introducing organic-laden wastewater into a
reactor where  an aerobic bacterial culture is maintained in suspension (mixed liquor).
The bacteria respire a moeity of the organic materials to form carbon dioxide, water,
and metabolic byproducts and assimilate another fraction to form more cells.  Oxygen is
supplied to the  reactor by mechanical or diffused aeration with air or an oxygen-enriched
gas stream. Intimate contact between wastewater, sludge, and oxygen is maintained in a
properly operating reactor.  A portion  of the mixed liquor is continuously passed to a
settling  tank  (clarifier)   where sludge  (primarily bacterial cells)  is  separated from
                                                        •
wastewater.  A portion of the settled sludge is returned to the  reactor to maintain the
proper balance of microorganisms, while the remainder is removed from  the  system.
Typical equipment includes aeration tanks and basins, clarifiers, compressors, aerators
(diffused or mechanical),  and recycle pumps and plumbing.

4.1.2       Unit of Measurement
       Costs are given  in terms of dollars per gallon treated.  Estimates from one source
were  available  only in terms of cost-per-pound of Biochemical Oxygen Demand (BOD)
reduction.  Also, where available, assumptions of the volumetric capacity of a system are
given, but cost-per-unit estimates of reduction of mixed organic contaminants were not
calculable.
                                       -88-

-------
                                                               Aqueous or Solids Treatment
                                                               Activated Sludge
4.1.3.       Summary Data

4.1.3.1      Expenditures
       The following expenditure was found:

     Capital:                               $6.3 milUon/Mgd ($87,514/13,680 gpd)
     Operation & Maintenance:               $0.0165/gal.

This system was a nutrient-enhanced biodegradation system, constructed with retrofitted
5,400-gallon milk trailers for aeration and settling tanks.  It was not a standard engineer
designed and activated sludge system,  though the cost components  were very similar.
The  cost  of operation and  maintenance  includes a  relatively  small  expenditure  for
nutrient salts ($19.20/day; $0.0014/gallon;  8%).  The use  of previously used or salvaged
material generally produced significant savings in costs over the expected cost for new
materials.

4.1.3.2      Estimates
       Cost estimates ranged from:
     Capital:                                $200,000/Mgd
                                             to
                                            $390,000/Mgd

     Operation & Maintenances               $18,000/Mgd/year
                                             to
                                            $25,000/Mgd.

      The compilation of these estimates is unclear from the available data.
                                       -89-

-------
                                                      Aqueous or Solids Treatment
                                                      Activated Sludge
4.1.4       Factors Found to Affect Costs

4.1.4.1      Expenditures
       The following factors were found to contribute to expenditures:
            Materials (used and salvaged)
            In- house design and maintenance
            In-house power and process steam
            System flexibility (access holes)

       Although no expenditure data  for a system constructed of new  components  is
available  for comparison, the cost  of this system given in Table 26 may  have been
significantly lower than that of a system using new equipment and contractor labor.  One
cost item that increased the  capital expenditure,  possibly  unnecessarily, was  the
construction of a roller mount and access ports for the pipe air spargers. This part of the
system  was intended to allow the spargers to  be  cleaned of biomass buildup without
sending a technician into the tank.  This  maintenance has not been necessary in over 2
years of operating the system (as of August 1983).

4.1.4,2      Estimates
      The lack  of technical detail about  the hypothetical systems for which estimates
were given precludes consideration of specific factors affecting the costs (see Table 27).

Expenditure Sources
     •      ELI/JRB Case Studies, 1983

Estimates Sources
     •      Radian, 1983
     •      SCS, 1981
                                       -90-

-------
                                                TABLE 26


                                     ACTIVATED SLUDGE EXPENDITURES




                                               (1982 Dollars)
Data Source
US EPA
ELI/JRB
1982
New Jersey
0
I

Capacity; rate
0.014 Mgd (1)



Aeration
20 cfm
through stone
pipe diffusers



Design
retrofitted
milk trailers
used for
aeration tanks



Operation &
Maintenance
$2.89/Mgd(2)
$226/day
$0.0165/gal.



Direct Capital
$6.3 million/Mgd
($87,514)



I
VO
                         (1)  Million gallons per day

-------
                                                   TABLE 27

                                      ACTIVATED SLUDGE COST ESTIMATES



                                                 (1982 Dollars)
Data Source
US EPA
Radian

"Conventional"

1983
US EPA
SCS
February 1981
1980 ;


Capacity; rate

1.0 Mgd (1)
5.0 Mgd
10.0 Mgd



7.2 Mgd (1)
(5,000 gpm)



Aeration

1.1 lb 02/lb
BOD 5 removed




Not given




Design

40 year service
life
detention time
6 hours


10 year service
life



Operation &
Maintenance

$25,000/Mgd
$24,000/Mgd

$18,000/Mgd

Direct Capital

$390,000/Mgd
$250,000/Mgd'

$200,000/Mgd


$358,720/Mgd (2)
$709,180/Mgd


'


I
VO
to
                          (1) Million gallons  per day

                          (2) First year O&M.

-------
                                                      Aqueous & Solids Treatment
                                                      Aerobic, Anaerobic, &
                                                      Facultative Lagoons
4.2 AEROBIC, ANAEROBIC, AND FACULTATIVE LAGOONS
4.2.1       Definition
       Aerobic,  anaerobic  and facultative  lagoons  are large,  earthen impoundments
designed for microbial  degradation of organic wastes.  They may be used as detached,
individual  treatment devices  or,  more commonly,  in  combination with other in-line
treatment systems.
       Aerated lagoons are 6  to 20 feet deep.   Aeration  devices  supply supplemental
oxygen and partial mixing.  A sludge blanket accumulates on the bottom and undergoes
anaerobic decomposition. A non-aerated cell (clarifier) usually follows to allow solids to
settle before discharge of the supernatant effluent.
       Anaerobic lagoons are deep (20 feet). High organic loadings and a gas impervious
layer of grease  on the  surface promote thermophilic anaerobic  digestion.   Wastewater
enters near the  bottom and exits below the surface.  Excess sludge is washed out with
effluent; waste recirculation is unnecessary.
       Facultative lagoons are  3 to 8 feet deep basins in which wastewater is allowed to
stratify into aerobic, intermediate, and anaerobic zones.  Stratification is enhanced by
settling solids, water temperature and density variations. Oxygen in the surface layer is
provided by diffusion of air  across the air-water  interface  and by photosynthesis.
Mechanical aeration devices are not used to introduce oxygen to facultative lagoons.

4.2.2       Units of Measurement
       Costs are given  in dollars-per-million gallons-per-day treated.  This cost  basis
assumes similarly effective treatment, as well as extrapolative total costs.
                                       -93-

-------
                                                      Aqueous <5c Solids Treatment
                                                      Aerobic. Anaerobic, &
                                                      Facultative Lagoons
4.2.3       Summary Data

4.2.3.1      Expenditures
       No actual expenditure data are available at this time.

4.2.3.2      Estimates
       Cost estimates ranged from

Capital:                 $0.08 million/Mgd            (7.2 Mgd)
                          to
                        $3.4 million/Mgd              (0.14 Mgd)

Operation &             $0.005 mtUion/Mgd           (10 Mgd)
Maintenances              to
                        $1.23 million/Mgd             (0.14 Mgd)

The  estimates  reflect widely varying scales of operational assumptions.   Large (5-10
Mgd) scale  scenarios were  at the bottom  of  the range  of unit cost estimates, while
smaller operations (under one  Mgd) had generally higher estimates.  The lower estimates
excluded certain related components such as land, pumping and liners.

4,2.4       Factors Found to Affect Costs

4.2.4.1      Expenditures
      No actual expenditure data are available at this time.
                                       -94-

-------
                                                       Aqueous <5c Solids Treatment
                                                       Aerobic, Anaerobic, &
                                                       Facultative Lagoons
 4.2.4.2     Estimates
       The following factors appeared to significantly affect the cost estimates:

      •     Scale of operation
                  land, pumping, liner
                  containers and overhead
      •     Effectiveness of Treatment
      •     Extent of Aeration
      •     Climate

 The estimates were significantly related to the scale of operation, as noted in section
 4.2.3.2.   This effect results  partly  from  the economies  of scale inherent in larger
 operations,  but it also  reflects the different nature of general construction estimating
 manuals (see Table 28).
       The  large  hypothetical systems  estimated by  Radian excluded the costs of
 pumping as well as  costs of liners and land.  These systems were similar in design to
 those that would be part of a  sewage or  industrial treatment plant. A contingency and
 engineering cost of  30% was included in the New Hampshire Feasibility Study estimate.
 The inclusion of this cost in the other estimates is unclear from the available data.
       The estimates include a variety of levels of contaminant removal.  These levels
 were  generally given in terms  of  BOD or COD.  These  may  not provide accurate
 estimates of removal effectiveness for many refractory or highly toxic organics but they
provide useful standards for comparison.  In cases where removal efficiency information
was available, no relationship with total unit costs  was apparent. However, for similarly
designed systems, effectiveness of removal would probably be proportional to cost.
                                       -95-

-------
                     TABLE 28
   ANAEROBIC, AEROBIC AND FACULTATIVE LAGOONS


                    (1982 Dollars)
Data Source
US EPA
OERR 1982
Feasibility Study
New Hampshire
US EPA
Radian
1983
US EPA
Radian
1983
US EPA
Radian
(coll climate)
1983
Design
AEROBIC
28 day detention period
4 cells, 12 feet deep
3,500 CFM aeration
AEROBIC
7 day detention time
88% BOD/COD removal
10 feet deep
30 year service life
ANAEROBIC
gravity flow, Excludes
land, pumping, liner
60% BOD removal
50 year service life
FACULTATIVE
gravity flow; excluded
land, pumping and liner
20 Ib BOD5/acre/day
80% BOD/COD removal
Capacity
144,000 gpd
(0.14 Mgd) (2)
1 Mgd
10 Mgd
1 Mgd
10 Mgd
1 Mgd
10 Mgd
Operation &
Maintenance (1)
$1^23 million/
Mgd
$0.03 million/
Mgd
$0.07 million/
Mgd
$0.0125
million/Mgd
$0.005 million
Mgd
$0.015
million/Mgd
$0.006
million/Mgd
Capital
$3.4 million/Mgd
$0.03 million/Mgd
$0.02 million/Mgd
$0.5 million/Mgd
$0.3 million/Mgd
$1.5 million/Mgd
$0.7 million/Mgd
(1) Annual
(2) Million gallons per dav

-------
                                              TABLE 28

                       ANAEROBIC, AEROBIC AND FACULTATIVE LAGOONS (continued)



                                             (1982 Dollars)
Data Source
US EPA
Radian
(warm climate)
1983

US EPA
cpq
1981
(mid -1978 dollars )


Design

FACULTATIVE
gravity flow; excludes
land, pumping and
liner.
40 Ib BOD5/acre/day
80% BOD/COD removal
AEROBIC

70% removal
100 ppm BOD


Capacity


1 Mgd
10 Mgd


7.2 Mgd



Operation &
Maintenance (1)


$0.015
million/Mgd(22)
$0.006
million/Mgd


$0.03
million/Mgd


Capital


$0.65 million/Mgd
$0.35 million/Mgd



$0.08 million/Mgd


I
VD
                      (1) Annual
(2) Million gallons per day   (3) First year cost

-------
                                                     Aqueous &. Solids Treatment
                                                     Aerobic, Anaerobic &
                                                     Facultative Lagoons
       The extent of aeration varied among the treatment systems^ The cost of aeration
equipment,  in terms of both capital, and operation and  maintenance costs,  may be
significant.  This difference in design and cost also significantly alters performance. For
example, the hypothetical aerobic system had a presumed efficiency of 88%; whereas the
anaerobic system achieved only 60%. This difference suggests the need to quantify costs
in terms of dollars  per unit of contaminant removed per unit of time when comparing
systems for  the same  waste stream.   The  climate affects system performance of
facultative systems  and  hence,  it affects costs.  The facultative  system in a warm
climate was more efficient than the cooler climate system.

Estimates Sources

     •     Radian,  1983
     •     SCS, 1983
                                     -98-

-------
                                                      Aqueous & Solids Treatment
                                                      Rotating Biological Contactors
4.3 ROTATING BIOLOGICAL CONTACTORS

4.3.1        Definition

       This  system is a  form of fixed-film biological treatment.   A slime layer of
microorganisms grows attached to polystyrene or polyvinyl chloride disks 6 to 12 feet in
diameter. The disks are mounted vertically on a horizontal axis of rotation in treatment
tanks.  Rotation of the disks  exposes  the  slime surfaces alternately to oxygen in the
atmosphere  and organic matter in the wastewater. Both oxygen and organic matter are
metabolized, the organic  material is assimilated as microbial mass or degraded to form
carbon dioxide, water and other metabolic byproducts by aerobic microorganisms.  The
rotation mixes and aerates the contents of the tank and causes excess slime layers to be
sloughed off as growth continues.   Sloughed slime is subsequently separated from  the
supernatant  in a settling system.  A complete  RBC system usually  consists of  two or
more  trains  of disks with each train consisting of several stages.

4.3.2        Units of Measurement
       Costs are given in terms  of dollars-per-million-gallons-per-day treated, when
available, for comparison with other  water treatment technologies.

4.3.3        Summary Data

4.3.3.1      Expenditures
       No actual expenditure data are available at this time.

4.3.3.2      Estimates
      The range of cost estimates was:
     Capitals      $0.9 million/Mgd           (10 Mgd)
                    to
                  $29.6 million/Mgd         (0.144 Mgd)
                                       -99-

-------
                                                      Aqueous & Solids Treatment
                                                      Rotating Biological Contactors
 Operation & Maintenance: $22,500/Mgd/year                     (10 Mgd)
                              to
                             $4.6 million/Mgd/year              (0.05 Mgd)

 The range of estimates reflects a widely varying scale of operation assumed for the four
 estimates from two sources.  The high estimate is derived from dividing the total (capital
 or O&M) by the treatment rate, in million gallons per day.  This method of scaling up the
 estimates of smaller system may result in the multiplication of some fixed costs. The
 low  estimates  are  derived  from  estimates  for  very  large scale sewage  treatment
 systems.  The actual costs can be derived by multiplying the unit cost by the  treatment
 rate.

 4.3.4       Factors Found to Affect Cost

 4.3.4.1      Expenditures
       No actual expenditure data are available at this time.

 4.3.4.2      Estimates
       The following factors appeared to have significant effects on cost estimates.

     o      Scale of treatment
     o      Inclusion of related costs
                  overhead allowance
                  contingency allowance
                  settling tanks,  etc.

The scale of treatment operation appeared to  significantly affect costs (see  Table 29).
The estimate may  for this reason, be of limited comparability since the Radian estimate
is for a very large system, compatible with flow rates at a municipal sewage  treatment
system, or large industrial waste plant.
                                      -100-

-------
                                      TABLE 29
                 ROTATING BIOLOGICAL CONTRACTOR COST ESTIMATES


                                     (1982 Dollars)
Data Source
US EPA
OERR

1982-
New Hampshire

US EPA
Radian
1983




Design basis
for volatiles removal;
follows neutr. and ppt.
includes nutrient salt
mixing tanks, clarifier
dewatering, sludge
recycle

100,000 sq ft of media
per Shaft
80-90% BOD removal
99% ammonia removal
cost excludes 1° and
2° clarifiers
i

Capacity
0.05 Mgd


0.144 Mgd

1 Mgd (1)


10 Mgd


Operation &
Maintenance
$4.6 million/
Mgd

$3.9 million/
Mgd
$32,500/Mgd


$22,500/Mgd


Capital
$29.6 million/Mgd (2)


$23 million/Mgd

$0.9 million/Mgd


$0.9 million/Mgd


(1)  Million gallons per day.
(2)  Includes engineering &  contingency
    (30%), and contractor's overhead
    (25%).
(3) Annual

-------
                                                      Aquous & Solids Treatment
                                                      Rotating Biological Contractors
       The effect  of  inclusion of related costs on the estimates is unclear.   The New
Hampshire Feasibility Study  assumed an additional 30% for contractor overhead.  It is
unclear whether these costs are included in the Radian estimate.
       The exclusion of certain systemic components from the Radian estimate may have
produced  an underestimation  of  the costs,  compared  to  those given  in the feasibility
study.   The Radian estimate included only those particular components  used for  the
rotating biological contactor  and excluded settling tanks, clarifiers and chemical mixing
units.   Generally,  the Radian  estimate  gave information  on a unit which  is to be
retrofitted to a primary treatment plant.
Estimates Sources

     •     Radian, 1983
     •     US EPA OERR contractor Feasibility Studies
                                      -102-

-------
                                                       Aqueous <5c Solids Treatment
                                                       Air Stripping
4.4 AIR STRIPPING
4.4.1       Definition
       The air stripping process enhances volatilization of volatile organic compounds
(VOC) by increasing the air-liquid interfactial surface area and the velocity of the air
passing over it.   Towers  and basins  have both been used;  however, only towers  are
considered here.  The typical tower  is similar in construction and configuration to a
water cooling tower.  Contaminated water enters near the top of the tower and flows
through a distribution plate and then downward over the packing,  which may consist of
plastic beads, saddles or piping. A blower forces air in at the lower sides and bottom of
the  tower and forces it past the water  and packing,  and then  out through  the  top.
Stripped water is  collected at the bottom of the tower, and exits into the distribution
system (or as effluent).  Basins,  which consist of a  temporary swimming pool  with a
series of spray nozzles across them have been used for  leachate stripping, but  no costs
were available for them at this time (August 1983).

4.4.2       Units of Measurement
       Costs  are given in dollars per million  gallons per day for ready comparison with
other water treatment technologies.

4.4.3       Summary Data

4.4.3.1      Expenditures
       The one source of actual expenditure data indicated the following costs.

      Capital:                               $182,540/Mgd (million gallons per day)
      Operation & Maintenance:               $9,921 - 11,905/Mgd
                                       -103-

-------
                                                               Aqueous & Solids Treatment
                                                               Air Stripping
 No comparison with other site data is possible at this time since this is the only actual
 expenditure information  available (August 1983).  This expenditure was  significantly
 lower than those estimated with engineering/construction costing manuals.
4.4.3.2      Estimates
      The following range of estimates for air stripping systems was found:
     Capital:            $607,000/Mgd                 (1.44 Mgd)
                          to
                         $7.3 million/Mgd              (0.0504 Mgd)

     Operation &
      Maintenance:      $89,000/Mgd                  (1.44 Mgd)
                          to
                         $3.2 million/Mgd              (0.0504 Mgd)

The  range  given is for two out of the three estimates that were available.  The third
estimate is not shown in  the above range because the estimate reflects only shipping and
set-nip costs for a borrowed tower, and not construction costs. The above range seems to
reflect the economies of scale for varying size systems.  The less costly system on a unit
rate basis  ($607,000/Mgd capital; $89,000 O&M) was the larger (1.44 Mgd); while the
more costly system ($7.3 million/Mgd  capital; $3.2  million/Mgd) was the smaller system
(0.0504 Mgd).  Therefore, in absolute terms the smaller the system, the higher the cost.

4.4.4.      Factors Found to Affect Costs

4.4.4.1      Expenditures
      The  following factors appeared to affect the costs:
     •     Capacity (VOC reduction and flow rate)
     •     Blower size
                                      -104-

-------
                                                      Aqueous & Solids Treatment
                                                      Air Stripping
       The relationship of the cost and the capacity of the system considered was nearly
linear (see Table 30).  It was stated in the Feasibility Study that the cost would increase
about the  same amount for each  of the five towers added.  The VOC reduction  was
expected to be related to costs, but no quantitative comparison is possible without more
expenditure data. The blower size significantly affected the operation and maintenance
(O&M) since most O&M cost was involved  in electrical power for the fans.  The O&M
expenditure was  relatively low since power costs in the northwest U.S. were  unusually
low during the estimation period.

4.4.4.2      Estimates
       The following factors seemed to affect the cost estimates

      •      Capacity contaminant (reduction and flow rate)
      •      Blower size
      •      Included costs
      •      Packing material

Estimates of cost varied directly according  to rate of flow of the untreated influent (see
Table 31).  This variability was reflected in  increased size of towers, volumes of packing
and capacities  of pumps.  Varying economies of scale seemed to be the most significant
factor affecting costs. The least costly system on a cost-per-unit treated-per  day basis
($607,000/Mgd  capital; $89,000 O&M) was the largest (1.44 Mgd); while the most costly
system ($7.3 million/Mgd caital; $3.2 million/Mgd O&M) was the smallest system  (0.0504
Mgd).  Hence, in absolute terms tlie smallest system was the least costly, but on relative
cost-per-million-gallons-per-day basis,  the economies of scale gave a unit cost advantage
to the larger system.
                                       -105-

-------
                                                TABLE 30


                                       AIR STRIPPING EXPENDITURES




                                               (1982 Dollars)
•Data Source
US EPA
OERR
CH2 M Hill
Washington
1983

*

Design
Five towers:
12 feet dia. x
30 feet high;
60 hp blower;
29,000 cfm/ tower



Capacity
5.04 Mgd
(3,500 gpm)
95% removal



Operation &
Maintenance (1^
$9,921-
11,905/Mgd
(2)



Capital
$182,540/Mgd



I
I—'
o

I
                            (1) Annual cost
'(2)  Estimated,  actual  expenditures not yet

    encountered (8/83)

-------
                                                TABLE 31


                                      AIR STRIPPING COST ESTIMATES





                                               (1982 Dollars)
Data Source
US EPA
OERR - Weston
Faasibllity Study
1982
New Hampshire
US EPA
Radian
1983
US EPA.
OERR-CH2 M Hill
Feasibility Study
1983
Minnesota

Design
23 foot high tower

two 600 cfm blowers
5 hp motors
15 psig steam boiler
20 foot high tower;
sch 80 pvc pipe
packing, cross-stack;
400 cuft/gallon
one tower;
12 feet dia. x 300 feet
30 feet high;
barrowed from other
site; shipping/set up
only

Capacity
0.0504 Mgd
(35 gpm)

0.144 Mgd
(100 gpm)
0.144 Mgd
1.44 Mgd
80% removal
average:
1 Mgd.
maximum :
2.16 Mgd.
95% removal

Operation &
Maintenance (1)
$3.2 million/
Mgd

$2.3 million/
Mgd
$286,000/Mgd
$89,000/Mgd


$60,765/Mgd

$28,131/Mgd


Capital
$7.3 mi 11 ion /Mgd


$3.9 million/Mgd

$1.07 million/Mgd
$607,000/Mgd


$124,610/Mgd (2)

$57,690


o
-J
I
               (1) Annual cost
(2)  "Capital"  costs  include only shipping of treatment tower

    from  Tacoma, Washington, and set up costs (pad, appurtenances,  etc.)

-------
                                                      Aqueous & Solids Treatment
                                                      Air Stripping

       The effectiveness of reduction of the contamination in the various systems  was
reflected in the costs. Since a variety of factors affect removal efficiency, it is difficult
to relate these many factors to costs.  These factors include,  but are  not limited to:
pumping rate, climate, and air flow rate  and packing type.
       Increased pumping rates may increase the total amount removed, but decrease the
percentage removed and, in combination with  the increase in electrical costs  caused by
higher pumping rates, produce  both a less  efficient system and a less cost-effective
system.   Climatic  effects are primarily related to  ambient temperature; increases in
temperature  produce  a higher  volatilization  of  contaminants.   Correlated  to  this
phenomenon are the costs of heating the  influent  stream to offset seasonal cooling or
increase efficiency.  Air flow rate, which affects  stripping efficiency, is a function of
the size and speed  of operation of blowers, each of which affect both capital and O&M
costs.
       Packing types also varied among the estimates and had some, unquantified effect
on efficiency and costs.  The proportion  of costs devoted to tower packing is unclear  but
the costs of different  packing  materials  of varying effectiveness  were given in one
estimate.  ($15/cu.ft.  - $95/cu.ft.).   Therefore,  an optimization  is necessary  when
choosing a packing type in order to acheive a given level of removal  with  a  certain
system size.
       The variation in included costs is  especially noteworthy for the system estimated
in the  Minnesota  Feasibility  Study.    This   cost  estimate  did not  include  tower
construction, but rather only included the shipping  and erection of a tower  borrowed
from the Tacoma, Washington site. Although this system was estimated for a four month
operation (while an alternate water system  was to  be installed), the  cost given  are
trebled for  annualized  comparison.   All  of the estimates given include engineering
overhead, at about 25 - 30%.

Expenditure Sources
     •     State and Federal Superfund  work

Estimates Sources
     •     Radian, 1983
     •     US EPA OERR contractor Feasibility Studies
                                       -108-

-------
                                                       Aqueous 
-------
                                                      Aqueous & Solids Treatment
                                                      Carbon Treatment
 4.5.3.2      Estimates
       The cost estimates range from:

 Capital:                 $643,000/Mgd      (complete construction cost)
                          to
                         $14,132/Mgd       (erection of leased system)

 Operation and
 Maintenance:             $ll,786/Mgd/year
                          to
                         $1.5 million/Mgd/year

 The wide range of cost estimates reflects a variety of included costs.  The lowest cost
 system  does not include the entire cost of purchased materials, but rather the costs of
 rental and erection of the system. The highest estimated cost includes complete costs of
 materials and construction.

 4.5.4       Factors Found to Affect Costs

 4.5.4.1      Expenditures
      The following factors affected the expenditures for carbon filtration:

     •      Inclusion of pretreatment costs
     •      Rental/purchase expenditure

 Costs of pretreatment are included in the cost given for the carbon treatment system for
both expenditures detailed in Table 32.  Although these costs for pretreatment may have
been necessary for efficient carbon use, and may comprise a minority of the component
costs, it is important  to note that they were included.  The higher cost system included a
clarifier for removal  of suspended solids from the influent, and an air stripping system
for preliminary removal of of methylene chloride from  the waste stream.  The  waste
stream  of  this  system  was  subsequently filtered  through the  four  cascade carbon
towers.   The lower cost system included only pea-gravel and lime for precipitating  and
filtering out solids.
                                      -no-

-------
                     TABLE 32
         CARBON TREATMENT EXPENDITURES

                    (1982 Dollars)
Data Source
US EPA
ELI-JRB
1980
New Jersey
US EPA
ELI-JRB
1979
Missouri
•

Design
clarification
air stripping
four cascade
carbon filter
pre-gravel/
lime prefilter;
three stage carbon
2,400 Ib carbon


Capacity
0.25 Mgd
25-150 gpm
Not given


Operation &
Mai n fpnanrp
$0.3
. $0.1


Capital
0 - 0.47/gallon (1)
3 - 0.23/gallon (1)


(1) Rented system and related  costs.

-------
                                                       Aqueous <5c Solids Treatment
                                                       Carbon Treatment
Both expenditures  given  are  for  leased  systems.    The  costs  generally  included
transporting the filter units, erection, and operating labor.

4.5.4.2      Estimates
       The following factors affected the cost estimates.
     •      Size
     •      Inclusion of related costs
                  rental/construction
                  carbon regeneration
                  additional prefiltering or treatment

The total system cost estimates varied directly with size (see Table 33). The cost-per-
million-gallons-treated-per-day  was relatively  more constant, though it varied over one
order of  magnitude  for  capital  costs, and three orders  of  magnitude for costs of
operation and maintenance (O&M).  No economies of scale were apparent since,  even
from the  same  data  source, cost-per-million-gallons-treated-per-day of larger  systems
was sometimes higher than for smaller systems.
      Renting a system appeared  to be less costly than most construction scenarios in
two instances.  Quotes for leased systems were obtained from vendors for the feasibility
studies  at the Illinois and Minnesota sites.  Costs included set-up and operation labor,
materials  and  equipment.  It is unclear whether regeneration costs were included in  most
examples.  It is presumably included in rented costs of rented systems if a carbon change
was not necessary during the lease period, such as in the Minnesota scenario.
      Costs for additional prefiltering and treatment,  aside from carbon, were included
only in two estimates.   In  the second  highest  systemic estimate  (the  New Jersey
feasibility  study), the  costs of sulfur dioxide gas treatment  to precipitate out  iron,
airstripping to remove volatile organics, and neutralization to stabilize the pH were
                                       -112-

-------
                                          TABLE 33
                             CARBON TREATMENT COST ESTIMATES


                                         (1982 Dollars)
Data Source
US EPA
Radian
1983
US EPA/NJDEP
COM
Feasibility Study (F.S)
1983
New Jersey
US EPA
CH2 M Hill
(vendor quote for F.S.)
1983
Illinois
US EPA
SCS 1981
(mid 1978 dollars)
Design
30 min. contact time;
1 Ib per 5,000 gal;
off-site regeneration
S02 for Fe ppt.
air stripping
neutralization (3)
1 Ib per 1,000 gall.

sand filters
carbon tanks
rented system

pressurized
pretreated
in situ regeneration
Capacity
0.14 Mgd
(100 gpm)
1.4 Mgd
(1,000 gpm)
2 Mgd
(1,389 gpm)
7 Mgd
(4861 gpm)

0.28 Mgd
(200 gpm)
2.16 Mgd
(1,500 gpm)

7.2 Mgd
(5,000 gpm)
Operation &
Maintenance
$357,000/Mgd
$250,000/Mgd
$1.5 million/
Mgd
$1.3 million/
Mgd

$ll,786/Mgd
(2)
$222,000/Mgd

$883,200
Capital
$143,000/Mgd
$643,000/Mgd
$473,500/Mgd
$471,429/Mgd (4)
$138,000/Mgd (5)

$346,429/Mgd (1)
$476,852/Mgd

$234,600
(1)  Includes  set-up and breakdown of all major        (2)  System rental     (3) All costs included
    equipment,  piping, controls, utility, erection,                         (4) First 5 years
    transportation, carbon and sand. No purchase.                           (5) After 5 years.

-------
                                              TABLE 33


                            CARBON TREATMENT COST ESTIMATES (continued)





                                             (1982 Dollars)
Data Source
U.S. EPA
CH2 M Hill
Feasibility Study
1983
Minnesota

-

Design
pressurized system
13 min. contact time
80,000 Ib carbon



Capacity
2.16 Mgd
(1,500 gpm)



Operation &
Maintenance
$82,000/Mgd



Capital
$!4,132/Mgd (1)



*-
I
                       (1) Includes set-up and breakdown  of all major equipment, pippin, controls,

                           utility, erection,  transportation, carbon and sand.  Not purchase.

-------
                                                    Aqueous & Solids Treatment
                                                    Carbon Treatment
included.  The costs  of  neutralization and  clarification  were included  in the SCS II
estimate.  The costs of chemicals and power comprised 90% of the O&M costs for this
system.

Expenditure Sources

     •     ELI/JRB Case Studies, 1983

Estimated Sources

     •     Radian, 1983
     •     US EPA OERR contractor Feasibility Studies
                                     -115-

-------
                                Aqueous and Solids Treatment
                                            Oil/Water Separation
4.6  OIL/WATER SEPARATOR
4.6.1     Definition
      An  oil/water  separator skims  oil  off of  water  by taking  advantage  of  the
immiscibility of these liquids.  The two general types of oil/water separators are (1) a
floating skimmer-type, and (2) a tank-type, coalescing plate separator. Costs are given
in this section for the second type.  This type, which is typically larger, uses a series of
horizontal and  vertical  hydrophilic and  hydrophobia  plates  to enhance oil  globule
flotation. These systems may be used in series with each other and with other treatment
technologies, which may provide "polishing" to remove residual low level contaminants.

4.6.2     Units of Measurement
      Costs   are  given  in  dollars-per-million-gallons   treated-per-day  when data
availability make it possible.

4.6.3     Summary Data

4.6.3.1    Expenditure
      The one expenditure available was:

Capital:              $289,200                (includes hookup and controls)

Operation and
Maintenance:         $50,000/year            (capacity unknown)
                     $2.70-4.16/gallon        (1,000-1,500 gallons/month)
                                       -116-

-------
                                            Aqueous and Solids Treatment
                                            Oil/Water Separation
The cost-per-gallon is relatively high because of the low rate of treatment.

4.6.3.2    Estimates
      The single estimate available was:

Capital:            $91,587                 5,000 gpm capacity
                    $12,720/Mgd            (7.2 Mgd)

Operation and
Maintenance:        $267,456/lst year
                    ($0.0001/gallon)

The assumptions for this system suggest that  it is intended as an auxiliary to a larger
treatment system.  Appurtenances and control  costs are not included as they are for the
above expenditure.  This causes an underestimate for the capital cost because of the
excluded costs and a low estimate for the O&M because the maximum capacity flow rate
was assumed for deriving the unit cost.

4.6.4.     Factors Found to Affect Costs

4.6.4.1    Expenditures
     The following factors affected estimates:
    •     Flow rate (utilization of capacity)
    •     Inclusion of related costs:
               appurtenances
               controls
               tank housing
                                       -117-

-------
                                            Aqueous and Solids Treatment
                                            Oil/Water Separation
 Flow rate was probably the most important factor affecting the expenditure (see Table
 34). The combination of a locally tight soil with a high organic content, and the natural
 adhesion of oil to such highly  organic soE resulted in a very low flow rate of only 1,000-
 1,500 gallons  per month for the California case study site. The effect on operation and
 maintenance unit costs by flow rate is  even more clear. The relatively low flow rate
 divided into the annual operation and maintenance costs results in a relatively high unit
 O&M cost.
      The expenditure data included a variety of related costs that may not be accounted
 for in estimates or  other expenditures.  They include upgrading of appurtenances to
 connect the lines for the treated  effluent to the local POTW, a building to enclose the
 storage tanks, and  a control  system for operating the separator.   These related fixed
 costs may be  spread  among other systemic components for a larger system in which the
 oil/water separator is a minor component, such as in a large POTW  or complex industrial
 waste (pretreatment operation.

 4.6.4.2    Estimates
     The following  factors affected the estimate (Table 35):

    •     System capacity
    •     Related costs

The estimate of unit costs includes only costs of basic materials and assumes a capacity
flow rate.  Therefore, it was probably  an  underestimate of unit  costs of an installed
system to the  extent that the actual flow rate is generally less than  capacity.  .
     Since this hypothetical system appears to be designed  as an auxiliary to a large
POTW or an industrial (pre)treatment system certain related fixed costs may be excluded
or spread among  the  larger system  components.    The  flow  rate variations may
overestimate the actual contaminant removal range because the bulk of the flow through
                                                       *
an oil/water separator is water rather than oily contaminant.  Therefore,  estimates may
be made  more accurate by calculating  the  cost per volume of contaminant  removed.
However,  the cost of removal of contaminants is very difficult to measure because of the
                                      -118-

-------
                                            TABLE 34

                               (ML/WATER SEPARATOR EXPENDITURES




                                           (1982 Dollars)
Data Source
US^ EPA
ELI/JRB
1983
California



Design, capacity
Coalescing plate
separator
capacity unknown
1, 000-1, SOOgallons/
month

i

Contaminant
PCB/oil,
10 c oil
in water from
french drain
sump



Operation &
Maintenance
$50,000/year
($2.70-
$4.16/gallon)

-

Capital
$289,200



I
»—'
I—•
co

-------
                                                 TABLE 35

                                   OIL/WATER SEPARATOR COST ESTIMATES



                                                (1982 Dollars)
Data Source
US EPA
1

scs
1981
(1978 Dollars)



Design, capacity
Coalescing plate
separator

maximum 5,000 gpm
(7.2 Mgd)




Contaminant
Not given







4
Operation &
Maintenance
1st year =

$267,456
($0.0001/
gallon)




Capital
$91,587 ($12,720/Mgd)

(simple average cost =
$1.98/1,000 gallons)





I
H-
to

-------
                                           Aqueous and Solids Treatment
                                           Oil/Water Separation
variations in contaminants  and removal  efficiencies.  The  removal efficiency of an
oil/water  separator  is  affected  primarily by  oil drop  size; retention  time,  density
differences between the aqueous and the organic phases, and the temperature.

Expenditure Sources

    •     ELI/JRB Case Studies, 1983

Estimate Source

    •     US EPA, SCS, 1981
                                      -121-

-------
                                            Gas Migration Control
                                            Pipe Vents
                          5.0 GAS MIGRATION CONTROL
5.1 PIPE VENTS

5.1.1      Definition
      Pipe vents are vertical or lateral perforated pipe installed in, through or around the
landfill for controlling gases. They are usually installed at a landfill perimeter on 30 to
60 foot centers and extend down to  the  water table or the landfill base, sometimes in
combination with trench vents for the control of lateral gas migration.  Pipe vents are
usually surrounded  by a  layer of coarse gravel to  prevent clogging  by solids or  water.
They  may discharge passively to the  atmosphere or be connected to a negative pressure
collection system for possible treatment.

5.1.2      Unit of Measurement
      Unit cost is given in dollars-per-pipe vent.  Other units such as depth and diameter
are used to describe each pipe vent.

5.1.3      Summary Data

5.1.3.1    Expenditures
      No actual expenditure data are available at this time.

5.1.3.2    Estimates
      The estimates ranged from:
          $445                 (6 feet deep)
               to
          $1,310                (30 feet deep)

No information was available about the assumptions for the lowest estimate. But the
highest (capital) estimate included additional items such as PVC casing and a blower fan,
which was not included in the lower estimates.
                                      -122-

-------
                                             Gas Migration Control
                                             Pipe Vents
 5.1.4 Factors Found to Affect Costs

 5.1.4.1    Expenditure
      No actual expenditure data are available at this time.

 5.1.4.2    Estimates
      The following factors affected the cost estimates for pipe vents:
     •    Depth
     •    Pipe diameter
     •    Casing
     •    Ventilation fan size
 The factors affecting cost estimates are very similar to those affecting well points, deep
 wells and monitoring well costs, since construction elements are similar. Well costs are
 typically proportional to their depth.  Costs also increase with pipe diameter because of
 increases in costs of materials, installation,  labor and equipment.  Some estimates for
 some components  were  given  in terms of  dollars-per-inch  diameter-per-foot  depth,
 indicating diameter (in inches) and depth (in feet) affect cost proportionately.
      Casing (pvc) was included in the JRB and  Radian cost estimates, but not the more
shallow New Jersey  Feasibility Study estimates (see Table 36). This element added $4.50
to 6.50/LF for 4 - and 6 - inch casings, respectively.
      The fan  affects both capital and operation and  maintenance costs.  The fan size,
and  its  capital cost estimate when given was  identical.  The reason for the differing
operation and maintenance cost from these sources  is unclear.

Estimates Sources
     •    JRB-RAM, 1980
     •    Radian, 1983
     •    US EPA OERR contractor Feasibility Studies
     •    US EPA OERR contractor bids
                                       -123-

-------
                                                     TABLE 36

                                             PIPE VENT COST ESTIMATES
                                                   (1982 Dollars)
Data Source
US EPA
JRB - RAM
1980
US EPA
Radian
1983
US EPA-NH State
CH2M Hill
Bids
1982
New Hampshire
US EPA
CH2M Hill
RI/FS
1983
New Jersey
Depth
30 feet; incl.
mushroom cap
30 feet; incl.
mushroom cap
Not given
6 feet
90° elbow + T
Diameter
pipe: 4 inches
pvc casing:
6 inches
pipe: 3 inches
pvc casing:
4 inches
Not given
4 inch
pvc, sch 40
Ventilation
one fan/pipe-
0-136 cfm
@ 3 inches
H20
one fan/pipe-
0-136 cfm
@ 3 inches
H20
Not given
none
Operation &
Maintenance
$18/year
$85/year
Not given
none
given
Capital Unit Cost
$1310each
$975 iftch
$520 each
$500 "
$500 "
$445 each
I
I—I
bo

I
                                     (1)  Includes 800 LF of vent piping;  + 10%  contingency

-------
                                            Gas Migration Control
                                            Trench Vents
5.2 TRENCH VENTS

5.2.1      Definition
     Trench vents are deep, narrow trenches backfilled with gravel, forming a path of
least resistance through which gases migrate upward to the atmosphere or to a collection
manifold. They are typically constructed around the perimeter of a waste area, or across
a section of the site  to  form a barrier against lateral migration of methane or toxic
vapors. Trenches can be open, or capped with clay and fitted with collection laterals and
riser pipes, venting to the atmosphere or connecting to a negative pressure fan or blower.

5.2.2      Unit of Measurement
     Unit  cost is  given in terms  of dollars-per-linear  foot  because it  reflects the
functional value of mitigating gas migration across an area.

5.2.3      Summary Data

5.2.3.1    Expenditures
     No actual expenditure data are available at this time.

5.2.3.2    Estimates
     The cost estimates for trench vents ranged from:

               $35/LF (20 feet deep)
                 to
               $646/LF (20 feet deep)
                                       -125-

-------
                                             Gas Migration Control
                                             Trench Vents
The highest estimate included significant  costs for sheet piling, geotextile trench lining
and well-point dewatering of the excavated trench, none of which were included in any of
the other three estimates.   The lowest estimate was for a simple passive trench vent
with no piping or ventilation.

5.2.4     Factors to Affect Costs

5.2.4.1    Expenditures
      No expenditure data are available at  this time.

5.2.4.2    Estimates
      The following factors were found to affect the trench vent estimates:
     •    Trench size
     •    Pipe vent size
     •    Ventilation for size
     •    Inclusion of related costs:
               sheet piling
               geotextile lining
               overhead allowances
               contingency allowances
               well point dewatering

      Trench depth seemed  to have the most significant effect on costs (see Table 37).
The 20-foot depth scenario used for the JRB-RAM estimate required sheet piling, which,
despite  reuse assumptions,  comprised  81% of the total capital cost.  Also, well-point
dewatering (14% of total capital cost) was considered necessary for this deep trench
vent.
      Pipe vents, added to the  trench  vent designs,  varied among the estimates given.
The pipe  vents  for the highest and lowest estimates were not detailed in the design
plans.  However, the length of laterals and risers for the'two SCS "Landfill" estimates
was identical; only the pipe diameter varied. This did not appear to significantly affect
the costs.
                                       -126-

-------
                                                   TABLE 37
                                         TRENCH VENT COST ESTIMATESA


                                                  (1982 Dollars)
Data Source
US EPA
JRB - RAM
1980
US EPA
SCS-active
control
"Landfill"
1980
US EPA
SCS-gravel
trench vent
"Landfill"
1980
US EPA
SCS-gravel trench
vent
"Landfill"
1980
Trench Size
500 feet (1)
X
20 feet (d)
X
4 feet (w)
3,068 feet (1)
X
12 feet (d)
X
4 feet (w)
3,068 feet (1)
X
12 feet (d)
X
-4 feet (w)
3,068 feet (D
X
20 feet (d)
X
4 feet (w)
Pipe vents
laterals
and risers=
500 feet
risers-
951 feet x
4 inches
laterals -
3,068 feet x
8 inches
risers- 951
feet x 6 inches
laterals-3,068
feet x 12 inch
none
Ventilation fan
none
2 hp
1,250 cfm
none
none
Operation &
Maintenance
not
given
$7,015 -
$13,777/year
$897 -
$l,888/year
$130 -
$283/year
Capital unit cost
$646/LF (1)'
$41 - 63/LF
$40 - 87/LF
$35 --^2/LF
to
                                     (1) Includes  sheet piling construction
                                          and geotextile lining

-------
                                           Gas Migration Control
                                           Trench Vents
The operation and maintenance costs were significantly higher (by an order of magnitude)
for the estimate which included a ventilation fan.  This increased cost was presumably to
cover additional electricity and maintenance.  The cost of synthetic trench lining (12% of
total capital costs) was included only in the JRB-RAM estimate, which assumed $2.38/sq
ft for hypalon.

The SCS estimates included allowances for overhead and contingencies as follows:

    Estimate Scenario         Overhead    Contingency
    Active control               25%          30%
    Passive control              25%          20%
    Gravel trench               25%          15%
Estimates Sources

    •     JRB-RAM, 1980
    •     SCS, 1980
                                      -128-

-------
                                            Gas Migration Controls
                                            Gas Barriers
5.3 GAS BARRIERS
5.3.1      Definition
      A synthetic membrane can be used in combination with other technologies to form
a barrier against horizontal or vertical gas migration. Clay or concrete slurry walls and
grout  curtains  may  also perform a similar  function, but  at a  higher  cost; these
technologies are usually reserved for barriers to  migration of ground-water.  Synthetic
membranes  may be installed during construction of a trench vent or a subsurface drain,
each of which involve digging a  trench.  The cost of the trench and other tasks may be
derived from the section on that technology.  Similar information on barriers to vertical
migration may be taken from the surface sealing section.  Considering costs of materials,
synthetic  membranes may need to be doubled or layers of sand may need to be included
to prevent punctures from gravel and stones.  Also, an additional several feet should be
allowed for  the membrane at the top of the trench to allow for proper anchoring. Trench
bottoms should also be lined.

5.3.2      Unit of Measurement
     Costs  are  given in terms of  dollars per square foot because it best expresses the
functional value of gas barriers.

5.3.3      Summary Data

5.3.3.1    Expenditures
     No expenditure data are available at this time.
                                       -129-

-------
                                             Gas Migration Control
                                             Gas Barriers
5.3.3.2    Estimates
      The cost estimates ranged from:

     Capital    $0.39/sq.ft.      asphaltic concrete
                 to
               $3.00/sq.f.t      hypalon (36 mil)
Operation and
Maintenance   $900/year        (24 four hour inspections/year)
The information source does not explicitly state whether both installation and material
costs are included in these estimates.

5.3.4     Factors Found to Affect Costs

5.3.4.1    Expenditure
      No expenditure data are available at this time.

5.3.4.2    Estimates
      The following factor primarily affected gas barrier cost estimates:

     •    Installation
     •    Material type
     •    Material amount

The inclusion of installation costs  is  the most important  factor  affecting these cost
estimates.   Although the  references for  estimates  drew data from the same sources,
Table 38 shows that there are significant differences that may have been caused by the
                                                        *
inclusion or exclusion of installation costs.
                                       -130-

-------
                                                    TABLE 38

                                         GAS BARRIERS COST ESTIMATES


                                                  (1982 Dollars)
Barrier Material
Synthetic liners:
Hypalon
Teflon
Geotextile backing
Gunite
Asphaltic concrete
Clay
Design assumptions
36 mil thickness
10 mil thickness
heavy weight, 2 layers
4 inch, layer with
wire mesh
4-6 inch layer
including base
Material cost, hauling,
backfill by dozer,
vibratory compaction
every 6 inches for
trench vent only.
JRB - RAM, 1980
,$0.71-0.77/
sq.ft.
$2.62/sq.ft.
$1.77-2.367
sq. f t.
$5.45-$9.91/
sq.ft.
Sfl. 39-0. 667
sq.ft.
$0.51/cu.ft.
Radian, 1983
$2.40-3/sq ft
$2.22/sq ft
$1.50-2/sq ft
$5.50-10.307
sq ft
$0.33-0.567
sq ft
$0.43/cu ft
Operation & Maintenance (1)
$900 - 1,062/year
 I
I—I
CO
t—»
 I
                               (1) Operation and maintenance  cost  estimated by Radian only

-------
                                              Gas Migration Control
                                              Gas Barriers
     The  types and  amount of materials  affected cost estimates,  but  the data  were
inadequate to quantify these effects.
Estimates Sources


    •    JRB-RAM, 1980

    •    Radian, 1983
                                     -132-

-------
                                             Gas Migration Control
                                             Carbon Adsorption
 5.4  CARBON ADSORPTION (GAS)
 5.4.1     Definition

      Carbon  filters are  added to  vents  to collect gaseous  contaminants (typically
 volatile organics) from the vent gases.  Large gas filtration systems (10,000 and 100,000
 cfm - roughly 1,000 cu.ft. of carbon) used in manufacturing processes are available, but
 this section includes information on relatively  small systems (7  cu. ft.  of carbon) for
 passive venting systems.

 5.4.2     Units of Measurement
      Costs are given in terms of dollars per filter. Units such as  volume of air filtered
 or amount of contaminant collected are important for  describing a given filter unit, when
 available.

 5.4.3     Summary Data

 5.4.3.1    Expenditures
      One expenditure for carbon gas  filtration was available:

          $188/filter

This cost does not include the cost of the used 55 - gallon drums that were retrofitted, or
the cost  of labor  to fill these drums with  carbon. Only the cost of  materials for the
granular activated carbon is included.  Each of four improvised filters was saddled over
the vents of  5,400 gallon activation  and settling tanks used to biodegrade butanol and
acetone from contaminated ground-water.

Operation and maintenance  costs include carbon testing and regeneration/replacement
costs.
                                       -133-

-------
                                             Gas Migration Contronl
                                             Carbon Adsorption
5.4.3.2    Estimates
      One estimate was available from price quote sheets (this may be considered similar
to expenditures except that no record of an expenditure is available).

          $635/Ventsorb (for orders of 1-3)

Ventsorb is a commercial carbon filter, very similar to  the improvised filter for which
costs are given above.  Related costs of construction (drum cutting, filling, painting) are
included in the delivered cost.

5.4.4     Factors Found to Affect Costs

      The  following factors affected the cost of the  carbon vent adsorber (see Tables 39
and 40):
                                                          •
     •    Size
     •    Related costs
     •    Flow rate

      Cost increases due to increases in the size of the filters were correlated only to the
amount of activated carbon filler used, since the drums used were reconditioned waste
barrels. Any containment structure would affect costs at a relatively small incremental
proportion of the cost, since the cost of carbon (roughly $1.00Ab) is more significant.
      The vent filters were mounted on the cylindrical tanks using wooden pallets, and in-
house labor was used to retrofit and fill the drum canisters.  The cost of these related
components would be expected to increase the cost of a factory-built carbon filter, as
noted below.
                                       -134-

-------
            TABLE 39
 GAS TREATMENT EXPENDITURES
           (1982 Dollars
Data Source
US EPA
ELI - JRB
New Jersey
1982

«

Filter Size
55 gallon drum (1)



Contaminant
butanol
acetone



Operation &
Maintenance
not
available



Total Cost
$188/each (2)



            -135-
(1)  Retrofitted use drum
(2)  Includes carbon cost only

-------
                                                TABLE 40


                                     GAS TREATMENT COST ESTIMATES





                                               (1982 Dollars)
Data Source
Industry vender
quote (1983)

•

Filter Size
55 gallon drum



Contaminant
not given



Operation &
Maintenance
not given
varies with
contaminant
concentration



Total Cost
$635 each



i
t—>

o>

-------
                                            Gas Migration Control
                                            Carbon Adsorption
     The air flow rate affects costs in general, because of the specific costs of a fan and
the higher rate of adsorption. The fan would not only add to the capital cost, but would
add to the operation and maintenance costs in two important ways: First, the fan itself
would require electricity and maintenance to keep running. Second, the higher rate of
adsorption would increase the frequency of replacement for the filter. The paucity and
similarity of available data obviates contrast of factors between sources.  However, the
following brief listing of factors is appropriate:

    •     Filter size
    •     Flow rate (use of ventilation fan)
    •     Contaminant concentration

     Flow rate is probably the most important independent factor of the above factors.
     Neither of the passive-type vent  filters for which costs  are  given above  included
costs for  a fan,  which would significantly increase costs of operation and maintenance.
JRB Remedial Action Manual (Rogoshewski, et al., 1980) included the relationship shown
in Figure 1.  The hypothetical system for which  these costs were estimated is a large
carbon filtration unit, several orders of magnitude larger than the ventsorbs noted above.
Expenditure Sources

    •     ELI/JRB Case Studies, 1983

Estimates Sources

    •     US EPA OERR contractor bids
                                       -137-

-------
   100
  to
  Ctf
  o
  o

  PL,
  o

  to
  a
  z
  <
  to
  3
  O
  K
  E-"
  E-
  to
  o
  u

  a
  UJ
  H
  O
    90
   80
   70
   60
    50
   40
H  30
C/D
2
    20
    10
               Figure 1. CAPITAL AND OPERATING COSTS

           FOR NONREGENERATIVE CARBON GAS VENT FILTER
Total
Installed
                            Annual

                            Operating
                                                          1000




                                                           900 >

                                                               2
                                                               G
800




700



600




500




400
                                         o

                                         m


                                         H
                                         i—i
                                         2
                                                               n
                                                               o

                                         H
                                         a:
                                         o
                                         c
                                         C/3
                                    300  §
                                         C/3
                                                            200
                                                            100
                                                               o
                                                               •n

                                                               o
                                                               o
                                                               r1
                                                 8
              FLOW  RATE  (X1000 CUBIC FEET  PER  MINUTE)

          OF VENT GAS  CONTAINING 50 PPM TRICHLOROETHYLENE
SOURCE: CALGON,  1980
                              -138-

-------
                                            Material Removal
                                            Excavation/Transportation/
                                            Disposal
                              6.0 MATERIAL REMOVAL
6.1 EXCAVATION/REMOVAL TRANSPORTATION AND DISPOSAL/TREATMENT
6.1.1     Definition
      Excavation, transportation and disposal costs are grouped here because, (1) similar
factors are involved in all three tasks, and (2) some actual expenditure data are available
only in terms of the three aggregated tasks.  Excavation refers to the work necessary to
remove and load the hazardous material, ready for transport from  its found position.
(This may involve significant digging and waste classification, or only surface scraping.)
Transportation  involves hauling  loaded materials  off-site to  a  disposal/treatment
facility.  Disposal/treatment may include landfilling, incineration or treatment.

6.1.2     Units of Measurement
      Costs are given in dollars per cubic yard (cy) because  it serves as a standard soil
excavation measure.  A cubic yard is assumed to  weigh  one ton, which is a common
assumption at landfills.  Disposal and  transportation costs in several cases are given in
terms of dollars/ton because haulers and landfills used weight measures.

6.1.3     Summary Statistics

6.1.3.1    Expenditures
     The following ranges of excavation/removal, transportation and  disposal/treatment
expenditures were found:

     Excavation/Removal:       $15 - $460/cuyd
     Transportation:            $29 - $145/cuyd
     Disposal Treatment:        $17 - $356/cuyd
                                      -139-

-------
                                            Material Removal
                                            Excavation/Transportation/
                                            Disposal
These cost elements cannot necessarily be summed, since the extremes of the ranges are
derived from different sources with different scenarios and assumptions.  The sum of the
three unit operations from the highest and lowest cost sites, results in the following site
total

     Excavation, Transportation and Disposal:
                   •  $4.70 - $884/cuyd

The  lowest cost site (Texas-$6.06/cuyd) required only pumping a liquid into a tank truck
for removal, while the highest cost site reflected the use of boats and level A protective
gear to retrieve floating pails from a canal.  The salient reasons for  the  low cost  of
transportation  at the lowest cost site  were  unclear, but at  the  highest cost site
(Massachusetts -$145/cuyd),  a relatively  high demurrage  (compensation for delay) was
charged because of sample analysis delays.  The disposal/treatment costs varied greatly
with the waste compatibility.  The lowest disposal cost (New York City - $17/cuyd) was
charged for oil heavily  contaminated with highly  volatile solvents, which facilitated
incineration.    The  highest  disposal cost  (Florida - $356/cuyd) was  for  disposal  of
extremely  caustic  "super tropical bleach"  (calcium  oxide-chlorinated lime),  which
required treatment and  neutralization  prior  to  disposal.   Costs  of  operation and
maintenance   may   involve   monitoring   of  ground-water  or   site  inspections   or
implementation security measures to prevent illegal dumping, which is often repeated at
former sites.  These costs were accounted for separately when they were encountered.

6.3.1.2   Estimates
     The following ranges of cost estimates for excavation/removal, transportation, and
disposal/treatment were found:

     Excavation/removal:        $0.85 - 4.09/cuyd
     Transportation:            $1.67 - 94.40/cuyd
     Disposal/treatment:         $  12 - 283.20/cuyd
     Site Total:                 $ 379 - 434/cuyd
                                       -140-

-------
                                            Material Removal
                                            Excavation/Transportation/
                                            Disposal
The lowest estimates (SCS "impoundment" - $0.85 - 1.27/cuyd) required use of a front-
end loader for excavation/removal, whereas the highest estimate (SCS "landfill" - $3.42-
4.09/cuyd) required an excavator for deeper excavation. The low transportation estimate
was  extrapolated  from a construction-engineering manual, whereas the high estimate
reflected actual bids from different types of hauling firms.  Disposal costs varied from
$12/cu.yd. at a sanitary landfill,  to  $283.20/cu.yd. for contaminated  sediment at an
engineered landfill.

No  operation  and  maintenance  costs  were  assumed for  the  excavation/removal,
transportation and disposal/treatment cost estimates.

6.1.4 Factors Found to Affect Costs

6.1.4.1    Expenditures
     The  following  technical   factors  were   found   to  affect    the  costs  of
excavation/removal, transportation and disposal/treatment:

    Excavation or On-site Transfer:
          1.    Excavation depth
          2.    Site surface characteristics
          3.    Health and Safety requirements
          4.    Material - liquid/solid/drums
          5.    Waste quantity

    Transportation:
          1.    Distance to disposal facility
          2.    Accessibility to road
          3.    Material - liquid vs. solid
          4.    Waste quantity
                                       -141-

-------
                                            Material Removal
                                            Excavation/Transportation/
                                            Disposal

     Disposal:
          1.    PCB Waste
               (a)  Concentration-over/under 500 ppm
               (b)  Material-solid vs. liquid

          2.    Non-PCB RCRA Hazardous Waste
               (a)  Solid vs. liquid
               (b)  Aqueous vs. organic

In addition, the following primary non-technical factors affected costs:
     A.    Community relations
     B.    Interstate relations
     C.    Inflation and regulatory factors.

     The effect of excavated depth on the costs shown  in Tables 41 and 42 is probably
non-linear, since the  most significant changes  in  cost resulted  from differences in
equipment.  For example, the depth of excavation at the Case Study sites in Idaho, New
Jersey and Massachussetts #1 necessitated the use of a Caterpillar 235, which is a large,
treaded backhoe, with a 30 foot (10 m)  arm, which rents for about $70/hour without
crew.  A smaller, less expensive backhoe such as a Case 580C was used at other  sites
where the excavation depth was  shallower.  A front loader, which is generally even less
expensive, was used at sites where only surface scraping was performed.
     Excavation  was performed  at a relatively quicker  pace,  which reduced labor and
rental  costs, at sites  with  sandy and unconsolidated soil.   No excavation costs  were
incurred  at the New York City #1 and California #2 Case Study Sites, because removal
involved  pumping liquid waste into trucks from tanks and ponds, respectively.  Surface
characteristics  of  the site probably  had a  relatively  small effect on  the costs of
excavation at most of the  case  study sites.  The waste was  excavated from  a steep
embankment  at Case  Study  Massachussetts #1.  Clean fill was  removed from the top of
the embankment  to prevent its cross-contamination with the wastes that were buried at
the toe of the  slope during the excavation.  This process added a small amount to the
labor and rental charges.
                                      -142-

-------
                                                TABLE 41
                                       EXCAVATION EXPENDITURES


                                               (1982 Dollars)
Data Source
US EPA
EEI/JRB
1981

California //I
US EPA
ELI/JRB
1980

California #2
US EPA
ELI/JRB
1981
New Jersey
US EPA
ELI/JRB
1980
Michigan
Length x trench
(filter) depth
216 feet (a)
X
22.5 (21.5)
feet

261 feet
X

14. 5 (10) feet
280 feet (c)
X
10(6) feet
990 feet
X
8.5(6) feet
Width

3 feet




4-6 feet



4 feet
not given

Sump depth, etc.
29.5 feet

triple level
drain pipes

20 feet
+ bucket well


no sump
pea gravel
around pipe;
gravel jacket
rebuilt drain
(d)
Operation and
maintenance
$54,000/
year (b)

(1,000-1,500)
gallons

$307/year
excludes
treatment
(10 mil,
gallon)
$89,640
year (b)
(19 mil. gal.)
not given

Unit Cost-capital

$1,733/LF



$936/LF



$424/LF

$85/LF (d)

it*
CO
      (a) Three drain arms summed;  slotted
          pvc piping stacked 3 feet apart
      (b) Includes water treatment  O&M
(c)  Three  trenches  summed:  2 injection,
    1 withdrawal
(d)  Includes  original and renovation costs

-------
                                                 TABLE 41
                                   EXCAVATION EXPENDITURES (continued)

                                               (1982 Dollars)
Data
Source
US EPA
OERR
1982
Florida
US EPA
ELI/JRB
1981

Calif.
US EPA *
ELI/JRB
1981
Mass.
US EPA
ELI/JRB
1981
Idaho


Material
liquid;
5 gal.
pails

bottles,
pellets


soil
sludge

soil

sludge


Quantity
18.7 cuyd;
757
pails

430 cuyd


1,052 cuyd
and
151 drums
(3)

817 cuyd



Contaminant
Ca oxide
chlorinated
lime

pesticides
(DBCP, etc.)


chlorinated
solvents

pesticides

solvents

Excavation
Depth

surface


15 feet


3-15 feet


13 feet


Excavation
Removal
$460/cuyd



$158/cuyd


$ 51/cuyd

'Trans.
(Distance)
$0.17/cuyd/
mi.
(2 trucks)
$68/cuyd (4)
Disposal
Treatment (1
$356/cuyd



$119/cuyd
(140 miles)

$145/ton
(513 mi.)

$90/ton

$207/cuyd
(254 mi.)



Total
$18,155
(2,4)

$884/cuyd
$276/cuyd


$285/ton


$207/cuyd

	 1
(1)  Landfilled unless other wise noted
(3)  615  cuyd  disposed; cuyd:ton ratio  (4) If 400 miles assumed

-------
                                                   TABLE 41

                                     EXCAVATION EXPENDITURES (continued)
                                                  (1982 Dollars)
Data
Source
US EPA
ELI/JRB

Mass .
1981
US EPA
ELI/JRB
1979

Missouri
US EPA
ELI/JRB *
1978



US EPA
ELI/JRB
1982

NYC

Material

drums

soil

soil


drums


soil
oil




Quantity


A 81 cuyd


2,635cuyd


4,770 cuyd



229 cuyd




Contaminant


solvents


pentachloro-
phenol


solvents
metals


solvents



Excavation
Depth


surface


surface


3-13 feet



surface



Excavation
/Removal

Not
Available


$39-87/
cuyd


$15/cuyd



Not
Available


Trans .
(Distance)

$77/cuyd

(480 miles)

$29/cuyd
(170 miles)

$92/ton
u

(497 mi.)
$89/ton

(818 mi.)

Disposal/
Treatment (1

$91/ton



$61/ton


$55/ton



$17/cuyd
(2)



Total

__



$110-
159/cuyd


$164/ton








-------
                                                 TABLE 41
                                   EXCAVATION EXPENDITURES (continued)

                                                (1982 Dollars)
Data
Source
U.S. EPA
OERR
1982
Indiana
U.S. EPA
1982
OERR
Texas
US EPA
ELI/JRB
1981
Calif.
US EPA
ELI/JRB
1981
New
Jersey
Material
liquids
sludges

liquid
soil

drums ,
soil
Quantity
2,500 gal.
27 cuyd.
Tot. =55
cuyd
99,000
gallons

3,185
cuyd

5,101
cuyd
Contaminant
solvents
still
bottoms
adhesives
metals
PCB (4)
xylene

pesticides

solvents
metals
Excavation
Depth

surface
surface

15 feet

15-26 feet
Excavation
/Removal

$89/cuyd
$0.03/gal.
vacuum
truck
$158/cuyd

$37-74/
cuyd
Trans.
(Distance)

Not
Available
Not
Available

Disposal/
Treatment) (1)

$28/cuyd
(2)
(landfill,
recycle)
Not
Available

$38/cuyd
(140 miles)
$62 /cuyd
(440 miles)
$43/ton
Total

$10,362
(3)
$3,186
(3)

$19 5 /cuyd

$124-
171/cuyd
(1)  Landfilled unless otherwise noted
                                               (3)  State waste category

-------
                                                   TABLE 41

                                     EXCAVATION EXPENDITURES (continued)
                                                  (1982 Dollars
-a
i
Data
Source
US EPA
ELI/JRB
1982

Wise.
US EPA
ELI/JRB
1980
Calif.
US EPA
ELI/LRB
1980
Calif.


US EPA
ELI/JRB
1980

Calif.
US EPA
OERR
1982
Arizona


Material

soil


waste-
water

waste-
water



waste -
water



liquid




Quantity

100 cuyd


46,037
cuyd
9.3 x 106
gal
190,950
cuyd;
38.6 x 106
gal


268,114
cuyd
54.2 x 106
gal.

10,000 gal.




Contaminant
hexavalent
chromium


pesticides
class I (3)

carbamate
fungicide
class II-I
(3)


ammonia
fertilizer


sulfuric
acid



Excavation
Depth

4 feet


pumped from
lagoons

pumped from
lagoons
i

pumped from
lagoons


leaking
tank



Excavation
/Removal

$15/cuyd


Trans.
(Distance)

Disposal/
Treatment (1)

$61/cuyd
(227 miles)



$35.75/cuyd
(15 miles)

$28 /cuyd
(50 miles)








$4.70-7/cuyd
(60 miles) (2)


$0.70/ gal.
$141/cuyd

vacuum
truck
$2.56/mile/
truckload





$0.40/gal
$80/cuyd

landfill


Total

$76/
cuyd

$35.'75/
cuyd

$28/
r 11 vd

!
i
$4.70-77
cuyd


$17,000
(1)



              (1)  Landfilled unless otherwise noted; Total includes other tanks (2) Landfarmed, USEPA subsidized  project

                                                                                (3) State waste category

-------
                                                   TABLE 42
                                         EXCAVATION COST ESTIMATES
                                                  (1982 Dollars)
Data
Source
US EPA
JRB-RAM
1980

SCS
"impound."
1980
SCS
a
"landfill"
1980
US EPA
CH2MHill
1983

New
Jersey
Material

sediments


soil,
sludge

soil



topsoil
fill

Quantity

10 cuyd


4,368 (2)
cuyd

780,000
cuyd



100 cuyd
51,876
cuyd
Contaminant

not given



"hazardous"

"hazardous"



none;
solvents,
Hg, Be
Excavation
Depth

not given


not given


not given



not given


Excavation
/Removal

$1.77/cuyd


$0.85-1.27/
cuyd
$44.84-7
67.26
$3.42-
4.09/cuyd



$2.49/cuyd
$1.18/cuyd

Trans.
(Distance)

$94.40/cuyd

(200 miles)
$1.67*4.397
ton
(20 miles)
$5.27-11.96
cuyd
(20 miles)


not given


Disposal/
Treatment (1

$283.207
cuyd

$214.177
ton

$214.177
ton



not given


Total

$379.377
cuyd

$216,69- !
219,237
ton
(2)
$222.87-
230.237
ton


—


oo
I
                      (1) Landfilled
                      (2) SCS assumes one cuyd =  1.89 tons

-------
                                                   TABLE 42


                                     EXCAVATION COST ESTIMATES (continued)
                                                  (1982 Dollars)
Data
Source
US EPA/
NJ DEP
Dames &
Moore

1982
N.J.
US EPA/
NJ DEP
Dames&
Moore
1982
N.Jersey

US EPA/
NJ DEP
Dames &
Moore
1982

US EPA
SCS
1983


Material

soil,
sediment




soil,
sediment




soil,
sediment





not
given


Quantity

not
available




not
available




not
available





not
given


Contaminant

solvents





solvents




solvents






not
given

Excavation
Depth

not
available




not
available




not
available





not
given

Excavation
/Removal

not
available




not
available




not
available





not
given

Trans.
(Distance)
$17.50/ton
.32/ton/mi.


(55 miles)


$17.50/ton

(100 miles)


$70/ton



(400 miles)

$52-76
$0.13-19/
cuyd (2)
(see text)
Disposal/
Treatment (1
$12-20/
cuyd;
sanitary

landfill


$30-50/
ton/mi.

interme-
diate
landfill
$60-80/
cuyd


engineered
landfill
not given




Total

	







	



	








I
I—•
ilk
to
             (2)  Assumption:  20  tons/truckload,

                             400 miles

-------
                                            Material Removal
                                            Excavation/Transportation/
                                            Disposal
      Muddy conditions at the Missouri Case Study site caused some delays in excavation
work.  The pails at the US EPA, OERR cleanup in Florida, were in a canal.  Technicians
in full level A protective gear had to retrieve them by boat.
      Health and safety requirements and costs were rarely documented and hence, their
actual effects  on  costs are not accurately quantifiable.  Since the relative effects of
these requirements  are potentially  greater for excavation/removal than  from other
technologies, their approximate effect warrants brief recapitulation here.
Given the following level of personal protection:

     1.    Level A - requires full encapsulation  and  protection from any
          body  contact  or exposure to  materials (i.e., toxic by inhalation
          and skin absorption).
     2.    Level B - requires self-contained breathing apparatus  (SCBA),
          and cutaneous or percutaneous  exposure to unprotected  areas of
          the  body (i.e.,  neck and back of head) be within acceptable
          exposure standards (i.e., below harmful concentrations).
     3.    Level C - hazardous constituents known; protection required for
          low level concentrations in air; exposure  of  unprotected  body
          areas (i.e., head, face, and neck) is not harmful.
     4.    Level D - no  identified  hazard  present,  but conditions are
          monitored and minimal safety equipment is available.
     5.    No hazard - standard base construction costs.
     Source:    "Interim Standard Operating Safety Guides," EPA 1982
     The following levels of productivity have been assumed for other estimates:

    Site Level                 Productivity     Equipment
         A                    10%-  15%      50%
         B                    25%-  50%      60%
         C                    25%-  50%      75%
         D                    50%-  70%
         E                    70%-100%
Source: CH9 M Hill, Inc.
                                      -150-

-------
                                             Material Removal
                                             Excavation/Transportation/
                                             Disposal
This effect on productivity is already reflected in the expenditure data, but inadequate
technical data was available to detail the protection levels for each site.
      The loading costs for liquids were lower than for solid, and were generally too low
to  be significant.   But costs of solidification or  incineration may have negated the
savings.  Liquid wastes at  the New York City #1 and California #2  Case Study sites were
quickly and continuously pumped into trucks or trains instead  of by the bucket load  as
with contaminated soil and sludge.  Drum handling was most efficiently performed with a
hydraulic drum grappler at the Case Study Massachusetts # 1 and New Jersey sites.  This
backhoe  attachment rented for over $200/day, but use of it reduced labor costs and other
equipment charges by speeding up the loading process.  The net effect on cost is unclear
from  the available case study data, but the use of this apparatus by experienced removal
contractors suggests an economizing value.
      Waste  quantity  probably  affected  excavation  costs  through  unquantifiable
economies of scale.  Larger sites such as the Maryland and California # 1 Case Study sites
could maximize the use of backhoes because of the greater amount of waste present and
thus reduce the cost-per-unit removed.   However,  this effect does not appear to be
significant since waste quantity and unit excavation cost among the case study sites does
not appear to be related.

Transportation -
      The  distance  between  the removal and  disposal  sites is  generally  the  most
significant factor affecting transportation  costs.   Since  the costs for transportation  of
PCB  waste  did  not   appear  to  vary  significantly  from  non-PCB   RCRA waste,
transportation costs  for both waste types are listed together in Table 43.  The average
cost for  the twelve sites  for which separate  transportation costs were  available was
$0.17/ton/mile (SD = $0.04/ton/mile).
                                       -151-

-------
                                        TABLE 43
                            TRANSPORTATION EXPENDITURES
(1)
Data Source
ELI/JRB-Massachussetts #1
ELI/JRB-New Jersey
ELI/JRB-Massachussetts #2
ELI/JRB-Missouri
ELI/JRB-Connecticut
ELI/JRB-N.Y. City #1
ELI/JRB-Minnesota
ELI/JRB-N.Y. City #1
ELI/JRB-N.Y. City #1
ELI/JRB-N.Y. City #2
EPA,OERR-Florida
EPA,OERR-Arizona
Unit
Weight Cost
(divided by)
$135 /ton
$ 57/ton
$ 72 /ton
$ 24/ton
$ 67/ton
$ 90 /ton
$ 34/ton
$250/ton
$242/ton
$ 94/ton
$ 68 /ton
$ 38/ton
Distance =
513 mUes
440 miles
480 miles
170 miles
497 miles
818 miles
140 miles
1,740 miles
1,420 miles
400 miles
400 miles
(2)
400 miles
(2,3)
Unit
Distance Cost
$0.26/ton/mile
$0.13/ton/mile
$0.15/ton/mile
$0.14/ton/mile
$0.13/ton/mile
$0.11 /ton/mile
$0.24/ton/mile
$0.14/ton/mile
$0.17/ton/mile
$0.19/ton/mile
$0.10/ton/mile
$0.17/ton/mile
(1)   assume 1 cuyd = 1 ton unless specified other wise by contractor or hauler.
(2)   assumed; actual distance unknown
(3)   15 cu yd/3,000 gallon truckload assumed
                                 -152-

-------
                                             Material Removal
                                             Excavation/Transportation/
                                             Disposal
      The  accessibility  of  the  site  to  major roads  was  found to  affect  costs  of
transportation at the California  Case Study site #1. The contractor stated that a lower
price was charged because the site was  near a major interstate highway which led to the
disposal site.   This proximity  to  the highway minimized the distance travelled  on
secondary roads and was said to  cause less wear and tear on the trucks. This factor may
have affected transportation costs at other sites where it was not stated explicitly.
      The  type of  waste  material  affected  transportation  costs  by  dictating  the
transportation method.  Liquid wastes were most economically transported in bulk using
truck or train tankers. Solid waste was generally transported via truck, which required
extra costs for plastic lining and sealing  of tailgate.  Sealing of bulk liquid tanks was
quicker because it only required closing and checking valves, instead of silicon foam or
asphalt sealing necessary on dump truck tailgates.  Relative costs of transporting roll off
dumpsters was not distinguishable.
      The cost  of transportation  was  also affected  by  the  waste quantity,  which
influenced  the type of transportation  used.  Economies  of scale were achieved by using
bulk tank trucks and rail cars for large quantitites of liquid waste at sites New York City
#1 and California #2 Case Study sites. Rail tankers, which carried several  times as much
as trucks, provided the lowest unit transportation cost,  as shown by the New York City
#1 Case Study site.  Economies  of scale with solids transportation costs were generally
limited by state laws regarding weight per axle. Hence, the five axle, 20  cubic yard (15
  o
m ) tractor-trailer dump truck was generally used.

Disposal/treatment -
     The most significant factor affecting disposal costs was whether the wastes were
PCB contaminated.  The disposal of cost for PCB waste was roughly double the disposal
cost for non-PCB RCRA hazardous waste.   Among  the PCB wastes, waste oil with over
500 mg/1 PCB at the New York City Case  Study Site #1 was disposed of separately from
PCB oil with between 50-500 mg/1.  The disposal cost alone was the  same for waste oil
above  and below  500  mgA,  but the  required  separate handling affected other costs
because of economies  of scale.   Liquids from this site were disposed of by incineration,
at a slightly higher unit cost than disposal of solids, which were landfilled.

                                       -153-

-------
                                             Material Removal
                                             Excavation/Transportation/
                                             Disposal
      A wide variation in disposal costs for non-PCB RCRA hazardous waste is shown in
Table 44.  Liquid wastes that were solidified prior to landfilling> such as the ELI/JRB
Missouri case study site, cost more per excavated weight because the weight and bulk
increased due to the added solidification material such  as sawdust or lime.  Aqueous
wastes such as those at Case Study California site #2 had lower tipping rates than the
organic wastes at other sites.
      The non-technical  factors affecting costs are difficult  to  quantify  fully.   An
increase in disposal cost was encountered at Case Study Minnessota site when community
opposition blocked five  initial proposals, which required a  more expensive disposal option
to be used.  Delays and more expensive disposal options  were encountered at the Case
Study New York City site # 1 when an out-of-state landfill  refused to accept wastes.
The city's consultant stated that this problem "had less to do with waste characterization
data discrepancies as with inter-state regulatory political factors" (CH2M HILL, 1982).
Pre-1981  costs were significantly lower than the post-1981 costs.  This may have been
primarily due to the anticipated RCRA landfill regulations, and secondarily to inflation.

6.1.4.2    Estimates
      The  following  factors  affected  the  cost  estimates  for  excavation/removal,
transportation, transportation and disposal/treatment:
   •      Excavation:
               depth
               method
   •      Transportation:
               distance
               contractor
   •      Disposal:
               Method
Generally, the factors affecting estimates (Table 44) were similar to those the affecting
the expenditures, which was of significantly  less technical detail was available  for the
estimates scenarios.
                                       -154-

-------
                                         TABLE 44
                              PCB EXCAVATION EXPENDITURES
                                        (1982 Dollars)
Source
US EPA

ELI/JRB
1982
N.Y.C.
US EPA"
ELI/JRB
1981
Mass.
US EPA
ELI/JRB
1980
N.'Y.C.
Material
OIL


pump able
sludge
soil
sludge

f lyash/
oil,
soil

Quantity
163
tons


240 tons
82 tons

2,793 tons

Contaminant
PCB
(3)


PCB
(3)
PCB
(3)

PCB
(3)

Excavation
Depth
surface
tanks


surface
tanks
3-15 feet

surface

Excavation
/Removal
Not
Available


Not
Available
%51/cuyd

Not
Available

Trans.
(Distance)
$248/ton
(1,740 mi.)

$240/ton
(1,420 mi.)
$145/ton
(513 miles)
$86/ton
(400 mi.)

Disposal
Treatment O
$249/ton
(2)


$233/ton
ton
(2)
$221/ton

$226/ton

Total
$498/ton


$473/ton
$425/ton

$313/ton

(1)  Landfilling unless otherwise noted
(2)  Incineration
(3)  50-500 ppm

-------
                                                  TABLE 44

                                   PCS EXCAVATION EXPENDITURES (continued)



                                                 (1982 Dollars)
Data
Source
US EPA
ELI/JRB

1982

N.Y.C

*


Material

solidifi-
ed

sludge





Quantity


7 tons







Contaminant


PCS






Excavation
Depth


surface
tanks





Excavation
/Removal


not
available





Trans.
(Distance)
Disposal/
Treatment

$238/ton


(400 miles)








Total

$238/ton







I
k-
tn

I

-------
                                            Material Removal
                                            Excavation/Transportation/
                                            Disposal
Excavation -
      Excavation cost estimates seemed to reflect primarily varying depths.  The SCS
"impoundment" estimate and the New Jersey RI/FS assumed that a frontloader would be
adequate to scrape up the contaminated soil.  The need for a  shovel excavator to dig
deeper at other sites caused higher estimates.  The excavation estimates in all cases
were  about an order of magnitude lower than the expenditures given above.  The reason
for this difference may  be  that excavation of hazardous material does not simply add
costs  to  the estimate  for  additional  tasks  such  as  health  and  safety protection
requirements. Rather it affects all tasks involved in excavation,  such as reduced labor
productivity  due  to  encumberances from protective  gear  and  delays  due to slow
turnaround time for chemical  analyses.   Standard  Construction-Engineering manual
estimates (see examples Table 45) fail to  account for the effect of these factors.

Transportation -
      The transportation cost estimates  ranged from  $1.42 - 94/ton as shown in Table
46. The distance  strongly affected the  cost of transportation for a ton of waste.  The
cost-per-ton-per-mile  estimates  are given in Table 46.   They  ranged  from  $0.07 -
0.51/ton/mile.   The  mean  was $0.25/ton/mile (SE=$0.04/ton/mile,  n=10),  which was
almost twice the average expenditures found for transportation.  However, the distances .
assumed for the estimates were significantly lower (3.6 times)  than those found  to be
necessary for actual sites. (Average distance found for transportation expenditures = 618
miles, SD=485 miles; average distance assumption given for transportation estimates =
168 miles, SE=65, n = 7).
                                      -157-

-------
                                     TABLE 45

            ESTIMATES FROM ENGINEERING CONSTRUCTION MANUALS
Item
Design Basis:
Cost
Excavation with
dragline
3/4 yd bucket, 90 swing,
rating 33 yd/hr

1.5 yd bucket, 90 swing,
rating 65 yd/hr
$2.47/cuyd


$1.76/cuyd
Excavation with
backhoe
Hydraulic, crawler mounted
1 yd bucket, rating 45 yd/hr       $2.17/cuyd

  1.5 yd bucket, rating
  60 yd/hr                       $1.96/cuyd

  2 yd bucket, rating
  75 yd/hr                       $1.93/cuyd

  3.5 yd bucket, rating
  150 yd/hr                      $1.48/cuyd

Wheel Mounted
0.5 yd bucket,  rating
20 yd/hr                         $3.95/cuyd

0.75 yd bucket, rating
30 yd/hr                         $2.92/cuyd
Excavation with
clamshell
0.5 yd bucket, rating
20 yd/hr

1 yd bucket, rating
35 yd/hr
$4.34/cuyd


$2.93/cuyd
Source:  Radian, Inc., 1983
                                   -158-

-------
                                       TABLE 46
                          TRANSPORTATION COST ESTIMATES
Data Source
JRB-RAM
SCS
"impoundment"
SCS
"landfill"
New Jersey # 2
RI/FS #2
New Jersey
RI/FS #2
New Jersey
RI/FS #2
SCS 1983
Unit Weight
Cost (divided by)
$94/ton
$1.42-3.27/ton
$4.47-10.14/ton
$17.50/ton
$17.50/ton
$70/ton
$52-76/ton
Unit Weight
Distance = Distance Cost
200 miles $0.47/ton/mile
20 miles $0.07-0. 19/ton/mile
20 miles $0.22-0. 51/ton/mile
35 miles $0.32/ton/mile
100 miles $0.18/ton/mile
400 miles $0.18/ton/mile
400 miles(l) $0.13-0.19/ton/mile
(1) Assumed:  400 miles, see text
The hauling cost estimates were also found to depend on the type of transporter as shown
in Table 47.   These specific  costs are not necessarily representative but do  show a
pattern of relative costs.
                                      -159-

-------
                                      TABLE 47

            AVERAGE TRANSPORTATION COSTS BY TYPE OF TRANSPORTER
   Type of Transporter
Unit distance
cost/ntruckload"
Unit weight
distance cost (1)
Treatment, Storage, and Disposal
 Facilities Providing Servic
 to Customers
$2.67/mile
($1.66/km)
$0.13/ton/mile
($0.09/Mt/km)
General Freight Transportation
 Companies Which May Haul
 Hazardous Waste on Request
$3.60/mile
($2.24/km)
$0.18/ton/mile
($0.12/Mt/km)
Hazardous Waste Transportation
 Companies Specializing in
 Hazardous Waste
$3.70/mile
($2.30/km)
$0.19/ton/mile
($0.13/Mt/Km)
   Source: SCS Engineers, 1983.
   (1) Assume 20 tons (18 Mt)/truckload
                                     -160-

-------
                                            Material Removal
                                            Excavation/Transportation/
                                            Disposal
Disposal/Treatm ent
     The most salient factor affecting disposal cost estimates was the method used in
the disposal.  Cost estimates from the RI/FS from the New Jersey site show a doubling of
disposal.  Cost for each increase in landfill security. However, since hazardous waste
cannot be safely or legally disposed in  a sanitary landfill, this  cost is inappropriately
compared with other estimates  for engineered landfills.  Also, the other estimates are
significantly  higher  than  the  actual costs found.  Table 48 shows  price quotes from a
sample of disposal/treatment firms.

Expenditure Sources

   •     ELI/JRB Case Studies, 1983
   •     State and Federal Superfund work
Estimates Sources

   •      JRB - RAM, 1980
   •      Radian, 1983
   •      US EPA OERR contractor Feasibility Studies
   •      SCS 1980
                                      -161-

-------
                               Table 48

        AVERAGES OF HAZARDOUS WASTE MANAGEMENT QUOTED PRICES  FOR ALL

        FIRMS IN 1980 AND FOR NINE MAJOR FIRMS IN 1981* (in 1982 Dollars)
TYPE OF WASTE
MANAGEMENT
INCINERATION
CHEMICAL TREATMENT
DEEP WELL INJECTION
LANDFILL
LAND TREATMENT
TYPE OF FORM OF
WASTE
clean liquids
high BTU value
liquids
solids; heavy
toxic liquids
acids/
alkalines
dyanides , heavy
metals (2)
oily
waste water
toxic
waste water
Drum
Bulk
All
UNIT COST
1980 1981
$0.65/gal
$131/cuyd
$2.12/gal
$429.50/cuyd
$0.21/gal
$42.50/cuyd
$1.30/gal
$262/cuyd
$0.13/gal (1)
$26/cuyd
$0.59/gal
$119.90/cuyd
$2.43/gal
$490/cuyd
$0.24/gal
$47.50/cuyd
$1.76/gal
$355/cuyd
$0.13/gal
$26/cuyd
$0.88/gal
$179/cuyd
$35.40/55?gal.
drum
$53/ton
$45.90/55 gal.
drum
$67.50/ton
$0.07/gal
$14/cuyd
             (1)   Some cement kilns and light aggregate
                   manufacturers are now paying for waste

             (2)   Highly toxic waste

Source:   U.S.  Environmental Protection Agency.
         "Review of Activities of Major Firms in the
         Commercial Hazardous Waste Management Industry:
         1981 Update".  SW-894.1.  May 1982.
                                     -162-

-------
                                            Material Removal
                                            Hydraulic Dredging
6.2 HYDRAULIC DREDGING
6.2.1     Definition
      Hydraulic dredges  are used to remove liquid, slurry, or semi-solid (sludge) wastes
from  waste  impoundments,  bays,   lakes, ' and  channels  containing  contaminated
sediments.  Once removed,  the wastes can be pumped to treatment and dewatering
facilities, or transported to acceptable nearby land disposal sites.

6.2.2     Units of Measurement
      Costs are  given in dollars per cubic yard because it provides a useful standard
measurement that is comparable to excavation.

6.2.3     Summary Statistics

6.2.3.1    Expenditure
      No expenditure data are available at this time.

6.2.3.2    Estimates
      The hydraulic dredging cost estimates ranged from:

          $3.54/yd3  Contractor dredging only
               to
          $1.25/yd3  Includes related fixed costs: sheet piling, silt curtain, coffer
                                            dam etc.

The  lowest  cost estimate includes  only contractor prices for the dredging  and pumping
phases of the operation.
                                       -163-

-------
                                                Material Removal
                                                Hydraulic Dredging
6.2.4     Factors Found to Affect Costs

6.2.4.1    Expenditures
      No data was available at this time.

6.2.4.2    Estimates
      The following factors affected estimates of cost for hydraulic dredging:

   •      Equipment type
   •      Pumping system capacity
   •      Sludge density
   •      Transportation of slurry
   •      Related costs

      The most important factor affecting costs was the inclusion of related costs. The
Feasibility Study for the Illinois site included a variety of necessarily related tasks that
are listed in Table 49.  These tasks accounted for $119 cu/yd of the total $125/cu/yd unit
price (see Table 50). Assuming similar included costs, other site specific factors affect
costs. Among these are the type of equipment, which varied with the site.  Land based,
floating and barge-mounted hydraulic dredges represent increasing costs  with increasing
depths and waterway sizes.  The JRB-RAM and Radian estimates did not specify the
dredger type, but the Illinois feasibility study assumed a barge-mounted dredger.
                                       -164-

-------
                                     TABLE 49

     ADDITIONAL RELATED COST ITEMS ESTIMATED FOR HYDRAULIC DREDGING-
                       EPA OERR, CH2 M HILL, ILLINOIS, 1983.
Task/Cost Item
Pipeline to lagoon
Sheet pile caisson -
double ring-13400 SF
PS 27
Remove sheet -
pile cofferdam
Replace existing piles
& floating docks
New boat hoisting
facility
Sediment control -
2 x silt curtain
Quantity Unit Cost
1,200 LF $11.97/LF
181 tons $23.36/ton
181 tons $11.68/ton
690 LF $195/LF
1LS $15,000
600 LF $ 95/LF
Total
$14,364
$422,816
$211,408
$134,550
$15,000
$ 57,000
$855,138
$855,138/7,200 cuyd = $119/cuyd related costs + hydraulic
dredging ($6.12/cuyd) = $125/cuyd
                                    -165-

-------
                                                   TABLE 50

                                      HYDRAULIC DREDGING COST ESTIMATES



                                                  (1982 Dollars)
Data Source
US EPA
JRB-RAM
1980
EPA - OERR
CH2 M Hill
Feasibility Study
Illinois
US EPA
Radian
1983

Quantity /design
694/yd3/day
suction or cutter head

925/yd3/day



Not specified


Contaminant

Not
specified

PCB
contaminated
sludge


Not
specified
1

Pumping
Distance

1,000 ft

900 ft



1,000 ft


Cost

$3.54 - 5.90/yd3

$6.12/yd3
(excludes significant
fixed and related costs)

$4-8/yd3


o>
05
 I

-------
                                               Material Removal
                                               Hydraulic Dredging
     The system  capacity  likely affected unit  costs  through  economies  of scale.
Inadequate data were available to confirm this effect.
     The sludge density affects unit costs because, after dewatering, low density sludge
may yield less  contaminated sediment volume than a higher density sludge. This effect
must be considered in light of the higher suction rate possible  with a lower density
sludge.
     The different means of transporting the sludge affected costs, since the JRB-RAM
and Radian scenarios assumed that only piping would be necessary; whereas the Illinois
feasibility study assumed the need  for a barge-mounted hopper as well as a pipeline.

Estimated Sources
   •      JRB-RAM, 1980
   •      Radian, 1983
   •      US EPA, OERR contractor Feasibility Studies
                                       -167-

-------
                                               Material Removal
                                               Mechanical Dredging
6.3  MECHANICAL DREDGING
6.3.1     Definition
      Mechanical dredging with draglines, clam shells, or backhoes  is used to remove
contaminated sediments from shallow streams, rivers, lakes, and other basins of water.
The stream is usually diverted with temporary cofferdams; the sediments are dewatered,
excavated, then loaded onto haul vehicles for transport to a disposal site.

6.3.2     Units of Measurement
      Costs are given in dollars  per cubic  yard  because it  provides a useful standard
measurement that is comparable to excavation.

6.3.3     Summary Statistics

6.3.3.1    Expenditures
      No expenditure data are available at this time.

6.3.3.2    Estimates
      Mechanical dredging cost estimates ranged from
          $1.37
           to
          4.09/yd3.

The range  reflects varying equipment assumptions  derived  from  a single  estimate
source.  The low end involves use of a simple backhoe, while  the high  end involves use of
a clam  shell.   Mobilization  and demobilization  costs  for  the backhoe  added $1.50.
Hauling and disposal costs  of the dredge material was  not included  (see excavation,
transportation and disposal).
                                      -168-

-------
                                                Material Removal
                                                Mechanical Dredging
 6.3.4     Factors Found to Affect Costs

 6.3.4.1   Expenditures
      No expenditure data are available at this time.

 6.3.4.2   Estimates
      The following  factors appeared to affect the  cost  estimates from  mechanical
 dredging:
          •     Equipment
                     Use of Barge
                     Excavation method (backhoe, clam shell, or dragline)
          •     Site condition
                     Depth of sediment
                     Water table

                     Additional costs:  Barge
                     Sheet piling (pile driver).

Since mechanical dredging is most suited to dredging shallow water, the cost will rise in
proportion to the depth of the water and the size of the dredging surface. The use of a
barge  would  double or  triple  the unit cost  for mechanical dredging; hence,  the
accessibility of  the sediments  has  a significant  effect on costs.  Also, wet excavation
may require sheetpiling or a cofferdam  to  support the dredging.  Table 51  shows the
estimated cost for these additional tasks and the pile driver is shown to be  significant.
     The  basic  costs of  dredging  equipment varied with the  scenario (see  Table  52).
Dredging using a hydraulic backhoe (1-3.5 cu/yd bucket) the lowest  cost scenario,  was
$1.37-2.10/cu/yd.  Intermediately, a dredging operation with a 0.75-1.5  cu/yd dragline
was estimated at $1.64-2.43/cu/yd.  The highest cost scenario was estimated with a 0.5-1
cu/yd clamshell  at $2.74-4.09/cu/yd.
                                       -169-

-------
                                    TABLE 51

             ADDITIONAL COSTS TO BASIC MECHANICAL DREDGING
                                                                    q
Barge-mounted dragline or                                $5.31-7.67/yd
clamshell, hopper dumped,
pumped 1000' to shore dump
Sheet piling, steel, high
strength (55,000 psi); temporary
installation (pull and salvage):
                              20' deep                   $9.72/ft?
                              25' deep                   $7.82/ft2
Pile driver; mobilize
and demobilize:
                               50 mile radius             $ 6,726 total
                              100 mile radius             $11,151 total
   Source:    EPA, Manual for Remedial Actions at Waste Disposal Sites

              625/6-82-006


Estimate Source

   •     JRB-RAM, 1980
                                     -170-

-------
                                                   TABLE 52
                                    MECHANICAL DREDGING COST ESTIMATES


                                                  (1982 Dollars)
Source
US EPA
JRB-RAM


1980


*

Volume

10 yd3







Contaminant

unspecified







Site
Dimension

7.5 feet
X
30 feet

stream bed



Unit Cost

$1.37 - 4.09/yd3







I
I—"
-4
(-•
I

-------
                                            Material Removal
                                            Drum Removal/Transportation/
                                            Disposal
6.4 DRUM REMOVAL, TRANSPORTATION AND DISPOSAL/TREATMENT
6.4.1     Definition
      Drum  handling includes  excavation  in  cases  where  the drums (bucket, pails,
containers etc.)  were  buried and/or  staging, overpacking and loading  for  transport.
Transportation involves hauling loaded  material  to  an off-site disposal  or  treatment
facility.   Disposal/treatment may include landfilling  and/or  other  technologies such as
neutralization, solidification or treatment.  These are  combined here because the cost
for all three tasks are often combined into a unit price.

6.4.2     Units of Measurement
      Costs are usually given in terms of dollars per drum (bucket, pail, containers, etc.)
for comparison purposes.  However, these costs may include other component  tasks such
as overpacking and handling adjacent contaminated soil,  as noted.

6.4.3     Summary Statistics

6.4.3.1    Expenditures
      The  following   ranges   of   expenditures   were  found  from  drum   removal,
transportation and disposal/treatment:
          Drum removal:        $60-l,168/drum
          Transportation:       $15-261/drum (30-480 miles)
          Disposal/treatment:   $36-360/drum

These cost elements cannot necessarily be summed, since the extremes of the  ranges are
derived from different sources with different scenarios and assumptions.
                                                       *
               Site Total:      $60-l,528/drum
                                      -172-

-------
                                            Material Removal
                                            Drum Removal/Transportation/
                                            Disposal
Some of the costs for the above three tasks may have been combined in the new data.
The  high  expenditures for the removal costs,  may reflect the  use of overpacking and
containerization. Transportation cost of a drum likely varied with distance, but distance
information was rarely available.  Some of the disposal costs given also include disposal
of contaminated soil.   Operation and  maintenance costs may include groundwater
monitoring and, possibly,  site inspections  or security  to prevent future illegal dumping,
which is often repeated at former sites.  These costs were accounted  for separately,
when they were encountered.

6.4.3.2    Estimates
     No handling cost estimates data are available at  this time.

6.4.4     Factors Found to Affect Costs

6.4.4.1    Expenditures
     The  following factors were  found to affect drum  removal expenditures  given in
Table 53 in the Raw Data section.
          Removal -            Waste type
                               Drum condition
                               Drum size
                               Drum situation, depth
                               Adjacent soil contaminant
                               Demurrage
                               Economies of scale
          Transportation -      Distance
          Disposal -
Waste type
                                       -173-

-------
                                           TABLE 53

                                DRUM HANDLING EXPENDITURES
                                         (1982 Dollars)
Source
US EPA
OERR
Date
unknown
PMla.
US EPA
OERR
Date
unknown
Calif. -
#1
RI.DEM
US EPA
1981
Rhode
Island
US EPA
OERR
Date
unknown
Florida
Material
solid
liquid

drums
soil

one, 30
gal.
pail

Quantity
0. 6 cuyd.
one
55 gal.
drum

4,500
unknown

0.15 cuyd

Contaminant
caustic
soda
unidentified

solvents


Calcium-

Excavation
Depth
surface
surface

average
20 feet
(3-35 feet)

surface

Excavation
/Removal
$400/drum
$1,468/
cuyd
(2,4)
$686/drum
(5)

$363/
drum


$129/drum

Tans.
(Distance)
$230/drum
Disposal/
Treatment
$75/drum
not
available
$ 106/drum


$10.20/mile

$300/drum

Total
$1,410
(1)
$686/
drum

$469/
drum


$453
(1)

(l)Total cost may  include other tasks
(2)Overp acking
(3)  50-500 ppm? minor component

(4)  drum = 0.27 cuyd
               —

-------
                                                       TABLE 53

                                       DRUM HANDLING EXPENDITURES (continued)



                                                      (1982 Dollars)
Data
Source
US EPA
OERR
1982
Florida
ELI/JRB


1981
New
Jersey
ELI/JRB '


Conn.
1978
ELI/JRB



Massach.
1978
Material
liquid;
5 gal.
pails


drums,
soil



drums


soil


drums




Quantity
18.7 cuyd;
757
pails



5,101
cuyd



4,770 cuyd





481 cuyd
(3)


Contaminant
Ca oxide
chlorinated
lime

solvents


metals


solvents

metals




solvents



Excavation
Depth

surface

15-20 feet





3-13 feet






surface



Excavation
/Removal
$460/cuyd


$34-69/
cuyd





$ll/cuyd




Not
Available



Trans.
(Distance)
$0.17/cuyd/mi
(2 tucks)
$68/cuyd (4)

$57/cuyd


(440 miles)



$67/ton

(494 mi.)


$7 I/ cuyd

(480 miles)


Disposal/
Treatment (1)
$356/cuyd


$40/ton






$40/ton




$84/ton




Total
$18,155
(2,4)
$24/pail
($884/cuyd






$119/ton





	




-a
en
 I
                 (1)  Landfilled  unless other wise noted

                 (2)  Total  cost  may  include other tasks
(3)  615  cuyd  disposed;  cuyd:  ton ratio used by

    T^nn0*?? =  1:1'3;  276 Cuyd aerated on-site
    If 400 miles  assumed

-------
                                            Material Removal
                                            Drum Removal/Transportation/
                                            Disposal
Removal -
      The waste  types found  at  the  Michigan, California  #2,  Florida,  Vermont  and
Philadelphia sites seemed to have had  a significant effect on the removal costs.  In all
cases, the cyanide, caustic soda, ethyl ether (highly flammable),  aromatic hydrocarbons
and super tropical bleach (calcium oxide-chlorinated lime), required that Level A or B
protective  gear,  treatment (solidification  or  neutralization) and recontainerization be
added  to the  removal costs.   Careful  management of these more hazardous wastes
generally increased the time necessary for  the various elements of the operation such as
labor  and equipment.  Inadequate technical detail was available, however, to quantify its
effect.
      Poor drum condition increased removal costs because it necessitated overpacking.
In cases  where waste had leaked out increased costs were incurred for transferring the
waste  and  emptying  and crushing the drums.   Overpacking 30 and 55  gallon  drums
required  55 and 80 and gallon overpacks at increased costs.
      Most  drums  were removed  from  the surface.   The  removal actions requiring
excavation did not  cost significantly more than the removals of drums on the surface,
suggesting that the added costs of backhoes and drum grapplers were less significant than
other items of cost such as treatment or protective gear necessary for hazardous waste.
Also,  a drum of an unidentified liquid floating in a Los Angeles, California river required
additional expenditures for a boat, but was not significantly  more expensive than  other
surface removal actions.
     The extent of soil contamination varied  among  the sites given.  The total cost in
some  cases included removal of bulk soil, but the unit cost is derived by dividing only this
total by  the intact or overpacked drums.  Hence, the removal cost per drum may  be an
overestimate in some  cases.  For the  ELI-JRB sites in New Jersey,  Connecticut,  and
Massachusetts, the drums were emptied, crushed and bulked along  with contaminated soil
necessitating a bulk volume unit cost.  More analysis of  technical details is necessary to
reaggregate these costs.
                                      -176-

-------
                                            Material Removal
                                            Drum Removal/Transportation/
                                            Disposal
      Based on two observations the economies of scale appeared to affect the unit costs
of removal.  First, there was a general inverse relationship between the total site costs
and the unit cost-per-drum.  Second, certain minimum costs were charged for component
tasks such as  mobilization of technicians and equipment. Mminimum charges also apply
to transportation as noted in the discussion of excavation cost factors in the previous
section.   However, the Michigan site cost for transportation ($2/truck/mile;  $60 one
truck, 30 miles) was lower than many minimum hauling charges.

Transportation -
      Inadequate information  was available to compare cost per mile of transportation,
but the effect of  distance, as well  as the rates can  be expected  to be similar to those
found in the above excavation section.  Demurrage was not found  to significantly affect
the costs since it was explicitly charged only at the Philadelphia site ($50 out of $1,410-
4%).

Disposal -
      The   reasons  for the  widely  varying  disposal costs were unclear  because of
inadequate  technical detail availability,  but they parallel  those  given in the material
removal section.

6.4.4.2    Estimates
      No cost estimate data are available  at this time.

Expenditure Sources

   •      ELI/JRB Case Studies,  1983
   •      State and Federal Superfund work
                                       -177-

-------
                                           Sewer & Water Line Rehabilitation
                                           Sewer Line Replacement
                  7.0  WATER AND SEWER LINE REHABILITATION
7.1       SEWER LINE REPLACEMENT

7.1       Definition
     The   process   of   sewer  line  replacement,  required  when   damage   and/or
contamination of piping  is extensive, involves the excavation and removal of existing
pipework and bedding and replacement with new materials. The remaining trench  is then
backfilled and compacted to restore the  repair site.  Preliminary inspection and location
of affected sections are considered part of this sewer system rehabilitation method.

7.1.2      Units of Measurement
     Costs are given in dollars  per linear foot  (LF) because it provides  a simple and
standardized measure of sewer lines.

7.1.3      Summary Data

7.1.3.1    Expenditures
     No actual cost data are available at this time.

7.1.3.2    Estimates
     Cost estimates for storm  sewer  (reinforced  conrete)  pipe  replacement  ranged
(Table 54) from:
          $ 55.46/LF           (36 inch diameter)
           to
          $141.60              (60 inch diameter)
                                                      *
These estimates included preliminary  inspection, trench excavation,  pipe placement,
backfill and compaction.  Allowances for removal of surface pavement and the
                                      -178-

-------
                                                 TABLE 54

                                  SEWER LINE REPLACEMENT COST ESTIMATES



                                                (1982 Dollars)
Data Source
US EPA

JRB - RAM

1980
US EPA

Radian

1983
*

Design
Inspection, excavation
section removal, pipe
and bedding replacement
backfill and compaction

Inspection, excavation
section removal,
pipe and bedding
replacement , backfill
and compaction


Pipe Type
reinforced
concrete



reinforced
concrete





Pipe Dia.
36 incb
42 inch
48 inch
54 inch
60 inch
36 inch
42 inch
48 inch
54 inch
60 inch


Unit Cost
$55.46/LF
$68.44/LF
$87.32/LF
$107.38/LF
$141.60/LF
$53. 90/ LF
$66. 60/ LF
$85/LF
$104.50/LF
$137.90/LF


-a

-------
                                           Sewer & Water Line Rehabilitation
                                           Sewer Line Replacement
dewatering of trenches have not been made and may increase costs considerably. Costs
of handling  and disposal of contaminated  soil excavated from sewer-line-replacement
sites have not been calculated as they are site specific.

7.1.4      Factor Found to Affect Cost

7.1.4.1    Expenditures
     No actual cost data available at this time.

7.1.4.2    Estimation
     The  following factors affected sewer line replacement cost estimates:

   •      Pipe size
   •      Pipe composition
   •      Depth of excavation

     Pipe size and  depth seemed to be most directly related to the replacement costs
for sewer lines.  The cost of excavation, which is a major component of replacement, was
affected by the depth and size of the pipe.  The cost of the new pipe, which is the major
material cost factor, was largely a function of the pipe size and composition.  Since
reinforced concrete  pipe was  assumed for both  estimates, cost estimates vary mostly
with size.

Estimates Sources
   •      JRB-RAM, 1980
   •      Radian, 1983
                                      -180-

-------
                                            Sewer & Water Line Rehabilitation •
                                            Sewer Line Repair
7.2 SEWER LINE REPAIR
7.2.1
Definition
      Sewer lines contaminated by migrating leachate may be reconditioned in place if
pipe damage is limited.  The procedure includes interior inspection, cleaning (mechanical,
hydraulic or chemical means) and  repair of damaged sections. The upgradient source of
contamination is assumed to have been removed or encapsulated for the purpose of this
section.
7.2.2
Units of Measurement
     Costs  are  given  in dollars per linear foot  (LF) because it provides a simple and
standardized measure of sewer lines.
7.2.3
Summary Statistics
7.2.3.1    Expenditures
     The only expenditure for cleaning and flushing contaminated sewer lines was:
          $15/LF.

The cost per foot for cleaning sewer lines was the same for all piping sizes, which ranged
in diameter from 10-21 inches.  No cost comparison was possible since only  one actual
expenditures was available.

7.2.3.2    Estimates
     Cost estimates to recondition 12 - inch diameter sewer lines ranged from:

          $5.75
           to
          $15.90/LF
                                      -181-

-------
                                            Sewer <5c Water Line Rehabilitation
                                            Sewer Line Repair
Cost estimates for repair included cleaning, interior inspection and internal grouting for
pipe in average  condition.  Higher estimates were expected for larger diameters and/or
more extensive  grouting.  Disposal costs  of  removed contaminated material were not
included in these estimates.

7.2.4     Factors Found to Affect Cost

7.2.4.1    Expenditures
     The  paucity  of data regarding expenditure precludes quantification of  component
costs and the factors affecting total unit costs (see Table 55).

7.2.4.2    Estimates
     The  following factors affected cost estimates for sewer line reconditioning (see
Table 56):

   •      Diameter of piping
   •      Extent of damage

Although the paucity of data hinders quantification of the cost factors, the above two
factors appeared to directly affect the level of effort required for repair, and hence, the
cost.  The extent of the damage was probably the primary factor affecting costs since it
was directly related to the amount of repair that was required. The size of the pipe was
less directly related to costs, but still affected the area to be repaired. These costs of
contaminant  handling  and disposal  were  not  included  in the estimates and  must be
considered as a site specific factor.

Estimates Sources
   •      JRB-RAM, 1980
   •      Radian,  1983
                                       -182-

-------
                                                    TABLE 55

                                         SEWER LINE REPAIR EXPENDITURES



                                                   (1982 Dollars)
Data Source
US EPA
CH2 M Hill
1983
New York



Design

Cleaning and
Flushing





Total Length

29,426 feet





Pipe Dia.

10 - 21
inches




Unit Cost

$15/LF





oo
CO
I

-------
                                                      TABLE 56

                                          SEWER LINE REPAIR COST ESTIMATES




                                                      (1982 Dollars)
Data Source
US EPA
JRB - RAM
1980
US EPA
Radian
1982


Design
Cleaning, T.V.
inspection and
grout repairs
Cleaning,
T.V. inspection and
grout repairs


Length

not
specified

not
specified


Pipe Dia.

12 inches


12 inches



Unit Cost

$5.90/LF (1)
•"

$5.75/LF (1)



I
I—•
OD

 i
               (1) Avprage Cost; cost will vary with

                  pipe diameter and extent of  grouting

                  repairs.

-------
                                            Sewer & Water Line Rehabilitation
                                            Water Line Repair
7.3  WATER LINE REPAIR
7.3.1
Definition
      Municipal water lines, contaminated by infiltration of contaminated ground-water
or runoff, may be repaired and reconditioned if damage and potential health hazards are
limited.  After location and inspection of faulty sections, cleaning procedures followed
by pipe relining (where necessary) can rehabilitate an effected system.  This work may be
done in place, without costly excavation.
7.3.2
Units of Measurement
      Costs  are  given  in dollars-per-linear  foot (LF) because if provides  a simple and
standardized measure of water main lines.

7.3.3.     Summary Statistics

7.3.3.1    Expenditures
      No actual cost data was available at this time

7.3.3.2    Estimates
      Cost estimates for water main repair ranged from:

          $26/LF                8" diameter
           to
          $35.50/LF 24" diameter

Restoration of 24 inch diameter concrete pipe was in the same range as smaller diameter
iron pipe.  Included in the  cost-per-linear  foot estimate was provision for preliminary
T.V. inspection.
                                       -185-

-------
                                            Sewer & Water Line Rehabilitation
                                            Water Line Repair
7.3.4     Factors Found to Affect Costs

7.3.4.1    Expenditure
     No actual cost data are available for water main repair.

7.3.4.2    Estimates
     The following factors affected cost estimates for water main repair:

   •      Pipe size
   •      Extent of damage and contamination
   •      Accessibility

Pipe size was the primary factor which directly affected the cost estimates for repair
(see Table 57).  Site specific factors such as accessibility of damaged sections and degree
of contamination and damage  would directly affect costs, but the cost estimate data
were inadequate to quantify these factors.

Estimates Sources
   •      JRB-RAM, 1980
   •      Radian, 1983
                                      -186-

-------
                                                 TABLE 57

                                     WATER LINE REPAIR COST ESTIMATES


                                                (1982 Dollars)
Data Source
US EPA
JRB - RAM
1980
US EPA
Radian
1983
»

Design
In-Place cleaning,
and cement relining
of pipes
In-Place cleaning
and cement relining
of pipes


Lilne Type
ductile iron
ductile iron
concrete
ductile iron
ductile iron
concrete


Pipe Dia.
8 inch
12 inch
24 inch
8 inch
12 inch
24 inch


Unit Cost
$29.50/LF
$35.40/LF
$29. 50/35. 40/LF
$28.75/LF
$34.50/LF
$28-34. 50/LF


00
-3
I

-------
                                            Sewer & Water Line Rehabilitation
                                            Water Line Replacement
7.4 WATER MAIN REPLACEMENT
7.4.1      Definition
     Water  main replacement involves  the excavation  and removal  of extensively
damaged and contaminated water pipe sections and bedding, sleeving new sections with
polyethelene sheet and relaying them.  This is followed by backfilling and compaction of
the trench.   Preliminary investigation by inspection and analysis is required prior to the
replacement procedure.

7.4.2      Units of Measurement
     Costs  are given in dollars-per-linear foot (LF) because it  provides a simple  and
standardize  measure of water lines.

7.4.3      Summary Statistics

7.4.3.1    Expenditures
     No actual cost data are available at this time.

7.4.3.2    Estimates
     Water  line replacement cost estimates ranged from:

          $  58.50/LF            8" diameter
           to
          $119.18/LF            24" diameter

These  estimates  covered all  basic  pipe  replacement  costs  including  preliminary
inspection procedures.  Costs were generally proportional to pipe size.
                                      -188-

-------
                                            Sewer 
-------
                                                TABLE 58

                                 WATER LINE REPLACEMENT COST ESTIMATES



                                               (1982 Dollars)
Data Source
US EPA
JRB - RAM

1980


US EPA
Radian
1983

*

Design
Inspection, excavation,
old line removal,
Polyethylene sleeving ,
pipe laying, backfill,
and compaction

Inspection, old line
removal, Polyethylene
sleeving, pipe laying,
backfill, and com'?
paction


Material
Iron

Iron

Iron
Concrete
Iron
Iron
Iron
concrete


Size (Dia.)
8 inch

12 inch

16 inch
24 inch
8 inch
12 inch
16 inch
24 inch


Unit Cost
$60.8/LF

$71.98/LF

$95.58/LF
$119.18/LF
$58.50 /LF
$70.00/ LF
$93.00/ LF
$116,00/LF


CD
o
I

-------
                                            Alternative Water Supply
                                            New Supply Wells
                        8.0 ALTERNATIVE WATER SUPPLIES
8.1 NEW WATER SUPPLY WELLS

8.1.1      Definition
      New water wells usually involve drilled rather than driven wells, and are typically
cased with a PVC sleeve.  The costs of providing and operating a pump, and the cost of
storage tanks may also be included in the operation. Bottled water from outside sources
may also serve a temporary water supply, although  cost information on this source is not
included in this section.

8.1.2      Units of Measurement
      Costs are given in dollars per linear foot depth because it provides a standard unit
for comparison within the water well industry.

8.1.3      Summary Data

8.1.3.1    Expenditures
      No expenditure data was available at this time.

8.1.3.2    Estimates
     The single cost estimate found for new well installation was:

Capital:             $46.25/LF

Operation and
Maintenance:        $265/year

The capital cost estimate  covers labor, equipment and materials.  However, costs for
preliminary geologic investigations for well siting were not included. The operation and
maintenance figure has been calculated for a well 200 feet deep.
                                       -191-

-------
                                            Alternative Water Supply
                                            New Supply Wells
8.1.4     Factors Found to Affect Costs:


8.1.4.1    Expenditures

      No data was available at this time.


8.1.4.2    Estimates

      Due to the limitations of well cost estimation data (see Table 59), no comparison of
cost factors can be made. As noted above, however, well depth and diameter as well as
hydrogeologic site conditions are general determinants in total costs for well installation.


Estimates Sources

      US EPA, OERR contractor Feasibility Studies.
                                      -192-

-------
                                                  TABLE 59

                                          NEW WELL COST ESTIMATES



                                                 (1982 Dollars)
Data Source
US EPA
Radian
- 1973
(1978 dollars)



Design
4 inch diameter
pvc casing
submersible pump
5gpm



Depth
200 feet



Operation &
Maintenance
$265/year



Capital
$46.25/LF
($9,250 Total)



to
CO

-------
                                            Alternative Water Supply
                                            Water Distribution
8.2 WATER DISTRIBUTION SYSTEM
8.2.1      Definition:
      Water distribution, systems consist of a network of pressurized pipes connecting
individual households with  existing water  sources, such  as  mains  or  reservoirs,  and
municipal hydrants to a common water source.  No source costs for wells or reservoirs
are assumed in this section; only connection costs are given.

8.2.2      Units of Measurement
      Costs are given in dollars per household connected as this is a common factor in the
available data and  allows an approximation of the numbers of people served by a new
water system.

8.2.3      Summary Data

8.2.3.1    Expenditures
      The range of expenditures was:
          $1,091/household
           to
          $10,714/household

The   costs  components  of  the  higher  expenditure include  fire  hydrants  and  all
appurtenances; while the lower cost system did  not include these costs.  Operation and
maintenance costs,  which may be significant, were  not available.

8.2.3.2    Estimates
      No estimates data are available at this time.
                                      -194-

-------
                                            Alternative Water Supply
                                            Water Distribution
8.2.4     Factors Found to Affect Costs

8.2.4.1    Expenditures
      The following factors  were found to affect the costs of new  water distribution
systems (see Table 60):

          •    Size (pipe length/diameter)
          •    Inclusion of related costs

The  inclusion of related costs was probably the most  important factor  that affected
costs.  The more  costly system included design work and  fire hydrants  along  all
connected  streets.  The less costly system included only the costs of construction  for
basic domestic water supply.  The two systems shown vary somewhat in size, in terms of
both length and diameter.  The lower cost Minnesota system connected houses that were
closer together than the California system.  Also the California system was built to allow
for connection of more houses in the  future, by using oversized mains that  exceeded
present system needs.  Operation and maintenance costs, which may be significant, are
not  included.   Also  excluded is the fee  usually charged by  a municipality for a
connection.

8.2.4.2    Estimates
      No estimates data are available at this time.
                                       -195-

-------
                                                    TABLE 60

                                         WATER DISTRIBUTION EXPENDITURES




                                                    (1982 Dollars)
Data Source

US EPA

ELI/JRB
1979
Minnesota
US EPA
ELI/JRB
1982
California
e

Design
domestic

water distribution
system


Includes construction,
services, fire
hydrants



Units served


11 houses



28 houses
fire hydrant
system



Total Cost


$12,000



$200,000
$300,000



Unit Cost j


$l,091/house



$7, 143-10, 714/house




to
a>

-------
                            ANNOTATED REFERENCES
CH2M HILL, December  1982.   "Draft  Engineering Services Report/Quanta Resources
   Clean-up"    Reston,  Va.  For  New  York  City  Department  of  Environmental
   Protection.    Invoices  and  daily logs  were  used to  assemble  actual  removal
   expenditures.

ELJ/JRB Environmental Law Institute, Washington,  D.C. and JRB Associates, McLean,
   Va. Case Studies of Remedial Responses at Hazardous Waste  Sites. 1983/85. Invoices,
   correspondence, reports and vouchers were used as part of this compilation of 23
   case studies around the U.S.

JRB  - RAM, 1980.  These cost  estimates were drawn  from the "Manual for Remedial
   Actions at Hazardous Disposal Sites" Draft final report by JRB Associates, McLean,
   Va. June  20,  1980.   This manual was subsequently published by U.S. EPA as the
   "Manual  for  Remedial  Actions at Hazardous  Wastes  Sites."   EPA  625/6-82-006.
   Cincinnati, Ohio, 1982, and again by Noyes Publishing  Company, Englewood Cliffs,
   New Jersey, 1983.  The initial draft final report was used because it contained the
   greatest  cost  detail.   These  estimates  were drawn principally from construction
   estimation manuals such as (1) the Means  Manual (Godfrey, R.R. (Ed.), 1980,  Building
   Construction Cost Data  1980,  38th Annual Edition, R.S. Means Company,. Inc.; (2)
   Dodge Manual (McMahon, L.; Pereira, P. (Ed.) 1979.   1980 Dodge Guide to Public
   Works and Heavy Construction Costs.  McGraw-Hill Information Systems Co., New
   York, N.Y.;  (3) Richardson Rapid Construction Cost Estimating System (Richardson
   Engineering  Services,  1980); and supplemented with a large number of price quotes
   drawn directly  from industry and commercial sources.  Hypothetical site scenarios
   are given for many of the technologies.

Radian, 1983.  These estimates are drawn  from  the last  section of "Evaluating Cost-
   effectiveness of Remedial Actions at Uncontrolled  Hazardous Waste Sites" - Draft
   Methodology Manual by the  Radian  Corporation, Austin, Texas, January 10,  1983.
   These estimates  were indexed to constant dollars  for March  1982.  Many of the
   estimates were derived from EPA's "Handbook for Remedial Action at Hazardous
   Waste Sites."   EPA 625/6-82-006. Cincinnati,  Ohio, 1982.  This source  was always
                                      -197-

-------
   supplemented  or supplanted by many other estimation sources, including specialized
   papers for specific technologies, and general construction estimating manuals.

SCS  (Engineers),  1980.  These cost estimates  came from "Costs of Remedial Response
   Action  at  Uncontrolled Hazardous  Waste Sites" by SCS  Engineers,  Long Beach
   California, April 1981.  According to this methodology:  "For the most part the  1980
   Means (Godfrey, R. (Ed.) 1979. Building construction cost data: 1980. Robert Snow
   Means Company, Inc. Kingston, MA. and Dodge Guides McMahon, L., Pereira, P.  (Ed.)
   1979.  1980 Dodge Guide to Public Works  and Heavy Construction Costs.; McGraw-
   Hill Information Systems Co. New York, N.Y. were used to obtain the costs needed."

SCS  (Engineers),  1981.   These cost estimates are derived from  Cost  Comparison  of
   Treatment  and Disposal Alternatives for Hazardous Materials (EPA - 600/52-80-188)
   published  in  February  1981  by  the  US EPA Municipal Environmental Research
   Laboratory. The estimate compilation was performed by SCS Engineers for a greater
   Chicago area scenario using the 1978 Means Construction Cost  Manual. Hence, mid-
   1978 costs  were originally estimated.  For comparison purposes these cost estimates
   were converted from simple average costs, and the raw data  on capital and operation
   and maintenance costs were used in stead.

US EPA,  OERR  contractor Bids.   Losing  bids for Superfund  work are used  here  as
   estimated  costs since  they  did  not  serve as the  basis for  actual construction.
   However, these estimates reflects a higher level of detail than many other estimates
   since specific local capabilities are considered.  Most of the  cost estimates are from
   1982 and 1983  estimates.

US EPA, OERR contractor Feasibility Studies.  Cost estimates from feasibility studies
   are generally  drawn from non-bid estimates from  contractors.  Most of these  cost
   estimates are from 1982 and 1983.

US EPA, OERR State and Federal Superfund Work.  Records from initial Superfund work,
   such as bid and change order  reports,  and spread sheet printouts.  All sites are
   numbered for  anonymity, but state locations are given because of its relevance  to
   cost factors such as labor and materials, and site characteristics such as climate.
                                      -198-

-------