NATIONAL FIELD INVESTIGATIONS CENTER
              CINCINNATI
            PLANT PERFORMANCE
                   AT
           WILLIAMSBURG
     WASTE TREATMENT PLANT
      HAMPTON ROADS SANITATION DISTRICT
           WILLIAMSBURG, VIRGINIA
               FEBRUARY 1973

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
  OFFICE OF ENFORCEMENT AND GENERAL COUNSEL
                       \

-------
                  REPORT

                    ON

 OPERATIONAL CONTROL AND PLANT PERFORMANCE

                  OF THE

    HAMPTON ROADS SANITATION DISTRICT'S

    WILLIAMSBURG  WASTE TREATMENT PLANT

                    AT

          WILLIAMSBURG, VIRGINIA

         JANUARY 1972 - JUNE 1972

                    by

          A. W. West, P.E.,  Chief

      J.  B. Walasek,  Pro j ect Engineer


           WASTE TREATMENT BRANCH
        ENVIRONMENTAL PROTECTION AGENCY
    Office of Enforcement & General Counsel
NATIONAL FIELD INVESTIGATIONS CENTER - CINCINNATI
                 FEBRUARY,  1973

-------
                          TABLE OF CONTENTS
                                                           PAGE NO.
ABSTRACT	     1




INTRODUCTION	     4




TREATMENT FACILITIES	     5




SAMPLE COLLECTION AND ANALYSIS	    lU




WASTE CHARACTERISTICS	    16




OPERATIONAL CONTROL METHODS	    20




PLANT PERFORMANCE	    26




SUGGESTED PLANT MODIFICATIONS	    52




SUMMARY	    55




RECOMMENDATIONS	    57
                                 111

-------
                           LIST OF TABLES
TABLE NO.                                                    PAGE NO.



   1         PROJECT AVERAGE BOD, TSS & REDUCTIONS .....         2

   2         CONSULTING ENGINEERS' DESIGN CRITERIA .....         8

   3         TREATMENT FACILITIES ......................         9

   k         SUMMARY OF GENERAL OPERATING CHARACTERIS-
             TICS ......................................        17
   5         SUMMARY OF PROCESS PARAMETERS
   6         SUMMARY OF PLANT LOADINGS AND PROCESS RE-
             SPONSES ...................................        30
   7         SUMMARY OF BOD  PROBABILITY DATA

   8         SUMMARY OF TSS PROBABILITY DATA
                                 IV

-------
                           LIST OF FIGURES



FIGURE NO.                                                   PAGE NO.

    1          PROCESS SCHEMATIC ....................            6

    2          7-DAY MOVING AVERAGE BOD  LOADING ----           39

    3          7-DAY MOVING AVERAGE AERATOR BOD-
               LOADING ......................... . ----           Ul
    k          7-DAY MOVING AVERAGE CLARIFIER OVER-
               FLOW RATE
    5          7-DAY MOVING AVERAGE AERATOR INFLUENT
               AND F.E . BOD  CONCENTRATIONS
    6          7-DAY MOVING AVERAGE AERATOR INFLUENT
               AND F.E. S.S. CONCENTRATIONS .........

    7          PROBABILITY OF FINAL EFFLUENT BOD -
               JANUARY vs PROJECT ...................
    8          PROBABILITY OF FINAL EFFLUENT S.S. -
               JANUARY vs PROJECT
    9          PROBABILITY OF FINAL EFFLUENT BOD -
               JUNE vs PROJECT ......................           50

   10          PROBABILITY OF FINAL EFFLUENT S.S. -
               JUNE vs PROJECT ......................           50

-------
                             APPENDICES
             PROBABILITY OF RAW BOD- & TSS	     A-l   to   A-6

             PROBABILITY OF P.E. BOD  & TSS	     A-7   to   A-12

             PROBABILITY OF F.E. BOD5 & TSS	     A-13  to   A-19

             PROBABILITY OF SECONDARY REDUCTION IN
             BOD_ & TSS	     A-20  to   A-25

             PROBABILITY OF OVERALL PLANT REDUCTION
             IN BOD  & TSS	     A-26  to   A-31
B            SYMBOLS & TERMINOLOGY	      B-l   to   B-6
             OPERATIONAL CONTROL TREND CHARTS	      C-l   to   C-7
                                  vt

-------
                            ABSTRACT









       A technical assistance project was conducted at the Williams-




burg Waste Treatment Plant to demonstrate plant start-up and opera-




tional control procedures.  The project was directed by personnel




of the Waste Treatment Branch, National Field Investigations Center -




Cincinnati with the support of Hampton Roads Sanitation District per-




sonnel -




       The Williamsburg Waste Treatment Plant is a complete-mix acti-




vated sludge plant equipped with surface-mechanical aeration devices.




It is designed to treat 9-6 mgd of combined brewery and domestic waste.




       Only brewery waste was treated during the first three months




of operation.  Organic and hydraulic loads were low during these




months since the incoming flow averaged only 2 mgd.  Plant loadings




reached normal levels in April with the addition of domestic waste




from the City of Williamsburg.  The incoming flow averaged approxi-




mately 5 nigd for the final three months of the project.




       Despite many mechanical and operational problems associated




with the start-up of the new plant, reductions in BOD  averaged 97




percent (529 to 15 mg/l) for the entire project while reductions in




suspended solids averaged 92 percent (320 to 22 mg/l).  Table 1 gives




a summary of project average BOD values,  TSS values,  and reductions.

-------
                    TABLE NO. 1
                 SUMMARY OF PROJECT
        AVERAGE BOD & TSS VALUES & REDUCTIONS
HAMPTON ROADS SANITATION DISTRICT, WILLIAMSBURG - WTF




BOIL



     RAW BOD  	    529 mg/1

     P.E. BOD 	    317 mg/1

     F.E. BOD 	   14.5 mg/1

     SECONDARY REDUCTION IN BOD  	   95 .If %

     PLANT REDUCTION IN BOD 	   97-3 %




SUSPENDED SOLIDS



     RAW SUSPENDED SOLIDS 	    320 mg/1

     P.E. SUSPENDED SOLIDS 	    125 mg/1

     F .E. SUSPENDED SOLIDS 	   22.2 mg/1

     SECONDARY REDUCTION IN TSS  	   8l .6 %

     PLANT REDUCTION IN TSS 	   92.0 %

-------
      Some of the problems that caused the effluent quality to ex-




ceed desired limits at times were:









      1.   Acid wastes that entered the plant during the




           first month of operation.




      2.   Sludge bulking during April.




      3-   Unwarranted recycle of digested sludge from




           the sludge disposal system to the activated




           sludge process.








      With the elimination of these and other problems,  Hampton




Roads Sanitation District personnel should be able to produce a




consistently high quality final effluent at the Williatnsburg Waste




Treatment Plant.

-------
                          INTRODUCTION








       This report describes the results achieved during the fed-




eral technical assistance project conducted at the Williamsburg




Waste Treatment Plant.  Personnel of the Waste Treatment Branch,




National Field Investigations Center - Cincinnati, assisted the




Hampton Roads Sanitation District in the start-up and operation




of their new Williamsburg, Virginia plant.  The request for assist-




ance originated with the Hampton Roads Sanitation District and the




Virginia State Water Control Board and was approved by the Office of




Enforcement and General Counsel, Environmental Protection Agency.




       The cooperative support of the plant management and operat-




ing personnel of the Hampton Roads Sanitation District and the assist-




ance provided by the State Water Control Board is gratefully acknow-




ledged.

-------
                    TREATMENT FACILITIES









       The Williamsburg,  Virginia,  Waste Treatment Plant is a




complete - mix activated sludge (CMAS) plant designed to treat




combined brewery and domestic waste.









FLOW PATTERN




       Brewery waste is pumped from the Anheuser-Busch plant




to the new Williamsburg Waste Treatment Plant where it is com-




bined with raw domestic waste pumped from the old Williamsburg




Municipal Treatment Plant site.  This combined plant influent




then flows through a screening chamber and a grit removal struc-




ture.  After metering through a Parshall flume,  the flow is




divided between two primary clarifiers.  (See Figure 1 for plant




layout.)




       Effluent from the primary clarifiers flows by gravity to




a splitter box where it is diverted to either one or two of the




four existing aeration basins and mixed with return sludge.  Al-




though only two basins were used in the CMAS System, all four




basins have fixed surface mechanical aerators.




       The effluent from the aeration tanks flows "by gravity




to the two peripherally fed circular final clarifiers for solids




separation.  The clarifiers are equipped with combination suction-




scraper type sludge removal devices.




       The clarified effluent is chlorinated and discharged to




the James River-              c

-------
                        AeroMc 0/gesfcr A/a 4-
                 i	   Aeroly/c
                       I
                        >4«/t7/-/cvr Tank  AJa 2
                                  Tanie.
 Plots

• \\6S/* S/Lfdye
                                                                                  FIGURE  i
                                                                                        SCHEMATIC
Primary

TTr/ckeried Sludge  To Land    	
                                                            HAMPTOU £0405 SAA/irATTOU Q&SST

                                                                     V/ILLIAMSBUBQ, I/A

-------
       The settled mixed liquor which is removed from the




secondary clarifiers is pumped to the active aeration tanks;




excess sludge is wasted to the other two aeration tanks,  No. 3  •




and No. k, which are operated as aerobic sludge digesters.




       The aerobically digested sludge is pumped to _ ,-avity




thickeners where it is concentrated prior to disposal aj: a nearby




spray irrigation site.  Overflow from the thickener is returned




to the splitter box ahead of the aeration tanks.









DESIGN CRITERIA




       The consulting engineers' design figures (Table 2),  state




that the total plant capacity utilizing four aeration tanks in the




CMA.S System,  is 9-6 mgd of combined brewery and domestic wastes at




66? mg/1 or 53,376 pounds per day of 5-day BOD.




       The sizes and capacities of the secondary treatment facili-




ties are listed in Table 3•  It should be noted that although four




aeration tanks are listed, areas and volumes are the totals for




only the two tanks providing mixed liquor aeration since the other




two tanks were used as aerobic digestion basins for the duration




of the project.

-------
                             TABLE NO. a

                CONSULTING ENGINEERS'  DESIGN CBTTV.BTA
AVERAGE DAILY FLOW
     Domestic Wastewater	    k.6
     Brewery Wastewater	    !?•()
                                       TOTAL	  9-6 mgd
BOD LOAD  (mg/1)
     Domestic	    200 mg/1
     Brewery	   1000 mg/1
     Combined	    66? mg/1
BOD LOAD  (#/day)
     Domestic	  66?2
     Brewery	 l^JTO1*
                                       TOTAL	53376" #/day
 SUSPENDED SOLIDS  LOAD (mg/l)
      Domestic	    2^0 mg/1
      Brewery	    1*50 mg/1
      Combined	    362 mg/1


 SUSPENDED SOLIDS  LOAD (#/day)
      Domestic	   8006
      Brewery 	21017
                                       T°TAL  	  29023 Ibs./day

-------
                             TABLE NO.  3




                        TREATMENT FACILITIES




        HAMPTON ROADS SANITATION DISTRICT,  WILLIAMSBURG - STP
SCREEN CHAMBER






   Type	Manually and Mechanically Cleaned




   Number of Screen Channels	    2




   Number of Bypass Channels	    1




   Bar Rack - Bar Spacing	    3 in.




   Mechanically Cleaned Bar Screen - Bar Spacing	    1






GRIT COLLECTOR






   Number of Units	    2




   Type	detritor




   Diameter	   28 ft.






PRIMARY CLARIF3ERS






   Number	    2




   Type	Circular,  peripheral feed




   Dimensions (each)	 95'  dia. x 10' s.w.d.




      CSA - Total Clarifier Surface Area -  Sq.. Ft	1^,176




      CVF - Total Clarifier Volume - Cu. Ft	 ikl,?6U




      CVG - Total Clarifier Volume - Gal. 	 1,060,397




   Mechanism Type	  Scraper






                                  9

-------
                             TABLE NO. 3

                               (contd)

                        TREATMENT FACILITIES



        HAMPTON ROADS SANITATION DISTRICT, WILLIAMSBURG - STP




PRIMARY SLUDGE PUMPS






    Number ...........................................            2




    Type .............................................  Centrifugal




    Capacity (ea.) ...................................      100 GPM




    Total Head .......................................     19.5 ft.




    Drive .................................  3 H.P.  Constant Speed






PLANT DRAIN PUMPS






    Number ...................       1                  1




    Type .....................  Centrifugal        Centrifugal



    Capacity .................    1, 200 GPM             200 GPM



    Total Head ...............       35 ft .             29 ft .



    Drive .................... Constant Speed     Constant Speed





AERATION TANKS ( for CMA.S)
    Number ...........................................            2
                                                          Concrete



    Dimensions (each) .................... 250'  L x 50'  W x Ik'  Deep



       ASA - Total Aeration Tank Surface Area - qn  TM-
                   —             —       _      uy..  rt.      2p,000



       AVF - Total Aeration Tank Volume - Cu.Ft.
                                             —             jpOj 000


       AVG - Total Aeration Tank Volume - Gal.
                   —             —        —              e




                                10

-------
                             TABLE NO. 3
                               (contd)
                        TREATMENT FACILITIES

        HAMPTON ROADS SANITATION DISTRICT, WILLIAMSBURG - STP

AERATION EQUIPMENT

     Number of Aerators per Tank	            5

     Type	   2-speed Surface-Mechanical

     Horsepower	   High - 50 H.P.,  Low - 12-5 H.P.
SECONDARY CLARIFIERS

     Number	            2

     Type	     Circular,  peripheral feed

     Dimensions (each)	        130'  dia. x 10'  s.w.d.

        CSA - Total Clarifier Surface  Area - Sq.  Ft.         26,5^6

        CVF - Total Clarifier Volume - Cu.Ft.               265,464

        CVG - Total Clarifier Volume - Gal.               1,985,673

     Mechanism Type	     Suction- Scraper


SLUDGE RECIRCULATIQN PUMPS

     Number	            2

     Type	  Vertical-Centrifugal

     Capacity (ea.)	              7,000  GPM

     Total  Head	              10>5  ft>

       ive	   50 H.P. Variable  Speed
                                 11

-------
                             TABLE NO. 3
                               (contd)
                        TREATMENT FACILITIES

        HAMPTON ROADS SANITATION DISTRICT, WILLIAMSBURG - STP

CHLORINE CONTACT TANK

     Number	

     Number of Passes	           ^

     Detention Time @ 9.6 mgd	     ^5 min.
AEROBIC DIGESTER TRANSFER PUMP  - No. 3 TANK TO THICKENERS

     Number	           2

     Type	    Self-priming Centrifugal

     Capacity  (ea.)	                    700 GPM

     Total Head	                     29 ft.

     Drive	   10 H.P. - Constant Speed
                                  12

-------
                             TABLE NO. 3
                               (contd)
                        TREATMENT FACILITIES

        HAMPTON ROADS SANITATION DISTRICT, WILLIAMSBURG - STP

GRAVITY SLUDGE THICKENERS


     Number	            2

     Diameter	       50 f t.

     Side Water Depth	       10 f t.

     Total Thickener Tank Surface Area - Sq. Ft	    3,927

     Total Thickener Tank Volume - Cu.Ft	     39,270

     Total Thickener Tank Volume - Gals	    293, 7^0



THICKENED SLUDGE PUMP (pumps thickened sludge to irrigation site)


     Number	              1

     Type	   Reciprocating

     Capacity	         200 GPM

     Total Head	          78 f t.

     Drive	   10 H.P. Constant Speed
                                  13

-------
               SAMPLE COLLECTION AND ANALYSIS









SAMPLE COLLECTION




       PLANT INFLUENT - The plant influent samples were collected




every two hours at the screening chamber and composited into a




2k-hour sample for analysis.  The sample point is shown as S-l on




Figure 1 -




       The sample was not an accurate representation of the in-




coming waste, however, since the plant recycle line discharged in




the vicinity of the  sampling point.




       AERATOR INFLUENT - The sample was collected every four hours




at the splitter box  located ahead of the aeration basins.  The




sample point is shown as S-2 on Figure 1.




       Although this sample is not representative of the primary




effluent since it frequently contained overflow from the gravity




thickeners, it is a true representation of the waste load to the




activated sludge system.




       MIXED LIQUOR  - Mixed liquor samples were collected every




four hours from each aeration tank for the settleometer and centri-




fuge test (See Operational Control Methods Section)  and determin-




ation of mixed liquor solids (only run on noon sample).  The  samples




were collected from the discharge box at  the  end of  the aeration




tank, shown as S-k on Figure 1.




       FINAL EFFLUENT - The  unchlorinated  final effluent




was gathered every four hours  at  the manhole  adjacent to the fi







                            Ik

-------
clarifiers.  This sample was composited into a 2^-hour sample for




effluent quality analysis.  The sample point is shown as S-3 on




Figure 1.  Another final effluent sample, this one chlorinated




for discharge to the James River, was collected hourly and checked




for chlorine residual.




       AEROBIC DIGESTER MIXED LIQUOR - At noon each day,  samples




were gathered from the discharge box of the aerobic digesters for




total and volatile suspended solids analysis.  The sample point




is shown as S-5 on Figure 1.




ANALYSIS




       Analysis of all the above samples was done by HRSD personnel




in the Williamsburg WTP laboratory in accordance with procedures




detailed in Standard Methods for the Examination of Water and Waste-




water, Thirteenth Edition.




       All reported plant performance data,  with the exception of




those analyses listed below, are based on the data supplied to NFIC-C




personnel by the HRSD personnel.  All reported BOD values are based




on a 5-day incubation period at 20  C.




       An aliquot of the composite samples (plant influent,  aerator




influent, and final effluent) was filtered through 0.^5 )i membrane




filters daily (by NFIC-C personnel) and shipped along with unfil-




tered aliquot of the composite samples to the NFIC-C laboratory for




Nitrogen, Phosphorus and TOG analysis.  Both the filtrate and the




unfiltered composite sample were preserved for shipment with 1 ml/




liter of H0SO, .

-------
                    WASTE CHARACTERISTICS
       Significant characteristics of the plant influent and




aeration tank influent waste streams are described below.  A




complete tabulation of monthly average BOD,  suspended solids,




and flow values are shown  in Table No. 1+ .     Probability plots




of BOD,- and suspended solids concentrations  are located in




Appendix A.









FLOW




       Flow during the start-up month of January varied from




0-9 mgd to 2.5 mgd and averaged 1.?^- mgd.  Increased flow from




the brewery and the addition of the City of  Williamsburg waste




in early April boosted the raw flow average  to approximately




5.5 mgd for the last two months of the project.









pH



       The 2^-hour composite raw pH values ranged from 3.0 to




11.U, during the entire project,  and averaged 6.3.   The composite




pH values for the aeration tank influent varied from 3  1  to  Q 6




and averaged 6.2 for the project.   At times very low pH (l.s t




2.5) waste streams entered the  plant  but most were of short






                             16

-------
                                                   TABLE NO. k


                                     SUMMARY OF GENERAL OPERATING CHARACTERISTICS
                                             JAN
FEB
MAR
APR
                                                                                             MAY
                                               JUNE
RAW BOD 5   (MG/L)
PRIMARY EFFLUENT BOD  5   (MG/L)
FINAL EFFLUENT  BOD  5   (MG/L)

RAW SUSPENDED SOLIDS   (MG/L)
PRIMARY EFFLUENT SUSPENDED  SOLIDS
FINAL EFFLUENT  SUSPENDED SOLIDS

SUSP. SOLIDS DISCHARGED   (LBS/DAY)
SECONDARY  S. S. REMOVAL   PERCENT
PLANT S. S. REMOVAL  PERCENT

BOD 5 DISCHARGED   (LBS/DAY)
SECONDARY  BOD 5 REMOVAL   PERCENT
PLANT BOD  5 REMOVAL  PERCENT

INFLUENT FLOW   (MGD)
INFLUENT BOD 5  LOAD (MG/L)
INFLUENT BOD 5  LOAD (LBS/DAY)

TFL  TOTAL  FLOW THRU  AER TANKS   (MGD)

AER TANK BOD S  LOAD (LBS/DAY)

MLTSS   (MG/L)
MLVSS   (MG/L)
MLVSS (LBS. IN  AERATION  TANKS)

BOD LONG (LBS/1000  CUFT  AER VOL)
F / M   (LBS BOD/LBS MLVSS)

RETURN  SLUDGE FLOW   (MGD)
RETURN  SLUDGE FLOW   PERCENT

AER TK  DET  TIME AT  FLOW
AER TK  DET  TIME AT  FLOW  PLUS  RTRN

FINAL CLAR. DET. TIME
OVERFLOW RATE   (GAL/SQFT/DAY)

ADT X MLVSS
ADT X MLVSS / MG/L  BOD  IN

HP/1000 SQFT ASA
HP HR/MGD
HP HR/LB BOD 5
HP HR/LB MLVSS
512.00
258.00
12.00
566.00
117.00
15.00
228.93
87.18
97.35
183.15
95.35
97.66
1.83
512.00
7811*. 21*
U.21
3937.65
1800.00
1578.00
17227.10
22.50
0.229
2.380
130.05
17.17
7.1»6
5.66
137.87
27089.82
105.00
18.80
3081.97
l.i»3
0.33
590.00
296.00
10.00
369.00
11*2.00
17.00
320. 1»2
88.03
95.39
188.1*8
96.62
98.31
2.26
590.00
11120.55
l».62
5579.12
2311.00
2207.00
2U093. 93
31.88
0.232
2.360
101*. 1*2
13.90
6.80
5.16
170.27
30679.23
103.65
12.U8
1656.61*
0.67
0.16
5U7.00
3U6.00
12.00
276.00
100.00
17.00
267.96
83.00
93.84
189.15
96.53
97.81
1.89
5U7.00
8622. 11*
l».l»l
51*53.86
2221.00
2088.00
22791*. 80
31.16
0.239
2.520
133.33
16.62
7.12
5.1*0
11*2.39
31*707.17
100.31
13.0U
2069.81*
0.72
0.17
556.00
330.00
21*. 00
259.00
119.00
58.00
211*7.71
51.26
77.61
888.71
92.73
95.68
i».l»l»
556.00
20588.1*5
9.69
12219.76
1316.00
1231.00
26877.78
31*. 91
0.1*55
5.250
118.21*
11*. 15
6.1*8
U.92
167.25
17U20.30
52.79
12.96
1751.36
0.61*
0.28
1*71.00
329.00
17.00
199.00
153.00
11*. 00
701*. 06
90.85
92.96
851*. 93
91*. 83
96.39
6.03
U71.00
23686.68
13.71
1651*5.1*7
2289.00
2127.00
1*61*1*1.11*
1*7.27
0.356
7.680
127.36
10.U2
i». 58
3.1*8
227.15
22163.12
67.37
20.00
1990.01*
0.72
0.26
51
-------
enough duration that they were buffered during treatment.  One,



however, towards the end of January 1972 lasted for several  hours



and destroyed the activated sludge biota necessitating reseeding



the aeration tanks.




BOD




       During January, both the brewery and the plant were  in




start-up mode, therefore,  the  average  plant influent BOD  of 512




mg/1 for this period does not  necessarily represent full  scale




brewery operation.   The  average BOD of the aerator influent for




the same period  was 258  mg/1.  The average plant  influent BOD




for the first three months of operation,  when only brewery  waste




was treated, was 550 mg/1.  The aerator influent  BOD  for  the same




period was  302 mg/1.




        The  City  of Williamsburg force  main was completed  in late




March and the plant started treating a combined brewery and dom-




estic waste on April 5;  1972.  For the final  three months of the




project  (April,  May,  and June) when the combined  brewery  and dom-




estic waste was  treated,  the average raw BOD   was 5lU mg/1  while




the aeration basin influent for the  same  period averaged  33^ mg/1.




COD




       A complete  analysis of the waste  characteristics cannot be




made because COD's  were  not run consistently after  February  23




and not at  all after April 8, 1972.  Available data indicates,




however, average plant influent COD concentrations during the




period when only the brewery was tributary of 1,575 mg/1 in  the





                            18

-------
plant influent and 1,120 mg/1 in the aeration basin influent.




SUSPENDED SOLIDS




       Total suspended solids for the month of January averaged




566 mg/1.  Aeration basin influent TSS for the same period aver-




aged 117 mg/1.   Towards the end of the assistance project,  when




a combined domestic and brewery waste was treated,  TSS averaged




250 mg/1 in the raw influent and 130 mg/1 in the aeration basin




influent.




NUTRIENTS




       The BOD:Nitrogen:Phosphorus ratio of the aeration basin




influent averaged 100:10.2:1.8 for the project.  Nitrogen and




Phosphorus were added to the screen chamber to provide nutrients




based on the recommendations of the consulting engineers.

-------
                 OPERATIONAL CONTROL METHODS
       The operational control procedures described below were



demonstrated to HRSD Williamsburg personnel during the NFIC-C




technical assistance project.




       The series of operational control tests initiated at the




Williamsburg plant by NFIC-C personnel enabled plant personnel




to determine sludge quality, process  status, and effluent -qual-




ity during each 2^-hour cycle.  The results of these tests were




then used to calculate process demands and operational control




requirements and to dictate operational control adjustments.




The tests that were used  for control  are as follows:





1.     Settleometer




             A settling test in which the mixed liquor




       sludge interface level  (settled sludge volume -




       SSV) was recorded  (in cc/1.) at 5-minute inter-




       vals for the first 30 minutes  and 10-minute inter-




       vals for the next 30 minutes.  This test indicated




       sludge settling in the final clarifiers.




2.     Centrifuge Test




             A 15-minute centrifuge spin of the aeration




       tank mixed liquor and return sludge samples  per-




       mitted a quick determination of the suspended solids




       concentrations.  Centrifuge test results were also used  to
                            20

-------
                     ds distribution ratios,  check flow




       measurements, and other process relationships.




3-     Depth of Blanket



             Depth of clarifier sludge blanket interface




       below the surface of the final clarifier was used




       in determinating the amount of solids in the final




       clarifier, solids balance, and wasting requirements •




k.     P.O. Test




             The dissolved oxygen concentration of the mixed




       liquor was measured to determine that aeration require-




       ments were met.




5.     Turbidity Test




             Turbidity of the final effluent, determined 'by




       the use of a standard photoelectric type turbidirneter,




       was used to rapidly determine the effect of process




       changes on effluent quality without waiting for the




       results of conventional monitoring-type tests.




6.     Physical Observations of Plant Conditions




             As samples for testing were collected, physical




       observations of process features such as, sludge color,




       amount of foam on the aeration tank surface, presence




       of "klumping" or straggler floe in the final clarifier,




       etc. were noted by the operators.




7.     Flow Meter Readings




             Flow meter readings were also recorded as part of




       the testing procedure for use in calculating process




       demands.





                              21

-------
       The above full series of tests were run three times  per



day; at k:00 AM, 12:00 Noon, and 8:00 PM.  In addition,  partial



tests in which the depth of blanket, centrifuge test results,



and the first 20 minutes of the settleometer test were recorded,




were run at midnight, 8:00 AM, ^:00  PM.



       The results of the settleometer and centrifuge tests  were




used to determine  settled sludge  concentration (SSC).   The SSC




curve, which  defines  sludge quality,  is  calculated from the




settled sludge  volume  (SSV) and the concentration (in percent)




of  the mixed  liquor leaving the aeration tank (ATC). This is




expressed  as:




                        ssc  = 100° ATC
                                SSV




        Illustrative  settling curves (SSV) and concentration




curves  (SSC)  are  shown in Appendix "C-7" • The curve labeled "Fast"




illustrates a sludge  characterized by  rapid  settling  and  compaction,




the curve labeled "Normal"  illustrates a normal settling  and com-




pacting  sludge, while the  curve labeled "Slow" represents  a slowly




settling sludge with  almost  no compaction.




       Trend  Chart Plots of  the process parameters (SSC, SSV  efflu-




ent turbidity) were plotted  on two-cycle, semi-log paper at the con-




clusion  of each full  test  series described above.   An illustration of




the SSV, SSC  and  effluent turbidity trend charts  for the period




from January  2k,  1972 to February 21,  1972 appears in  Appendix  "C-l,2&3".



By referring  to these charts the operator could see the  relat'





                              22

-------
response of the process factors to the three main control adjust-



ments, i.e., return sludge flow, waste sludge flow, and aeration



intensity.



       At the end of each day the individual test data were aver-



aged  for the day and the parameters listed in Table  c<   were



determined.  Three of the parameters, XSU, SDT and BLT were also



plotted on semi-logarithmic paper for use as trend charts to deter-



mine  excess sludge wasting policy.  A summary of the monthly aver-



ages  of such parameters may be found in Table  5   and a list of



the symbols used in this table may be found in Appendix B.



       Return sludge flows were determined on the basis of process



demands, i.e., after each full test series the operator would insert



the current value of the ATC, RSC, SSC  and CSF into the clarifier
                                      ~c


sludge flow demand formula, -





                     CSD = rSF x RSC - ATC
                     CbD   CoF x     _ ATC

                                    u




where SSC,  = Settled Sludge Concentration at some sludge settling
         t


time  (SST) to calculate new clarifier sludge demand (CSD).  It



should be noted that when the excess waste sludge flow (XSF) was



zero,  or XSF was minimal compared to the return sludge flow (RSF),



RSC and RSD would be substituted for CSF and CSD to yield:



                                 RSC - ATC
                     RSD = RSF x
                                 SSC.- ATC
                                    t
       For the most part, excess sludge wasting rates were adjusted



to maintain an approximate sludge age of 5 days.  At times, however,



                              23

-------
         TABLE NO. 5




SUMMARY OF PROCESS PARAMETERS
UATU
VDK
ATC
RSC
SLR
RSP
METERF.D API
R3F
r.rp
f.'FP/HSP
XSF
CSf
CALC. AF1
TFL
ADTUFI )
ADT(TFL)
CDT(TFL)
OFR(AFI)
SLU/DMY/C3A
ATOADT
DOB
3L7
ASU
CSU
1SU
ASH- CSU
RSU/OAY
RSU/GAL! API )
RSU/GAL*ADT( ffLj
SDT
ADT/'JOf
SMH
SAf-
XSU/rtAY
AGE
A/.G
SCR
LT & FC
JAM 1972
AVG
5.75
10.02
1.71)3
1.3U7
1.760
2.380
1 .7-52
1.001*
0.090
2.1*70
1.83k
••t.211*
17.13
7.1*5
:.es
138.19
18.26
l»?.86
9.1*6
0,051*0
0.0753
O.OOU2
0.0795
17.801(6
0.2385
0. 1300
0.9692
0.1*099
18.18li9
22.71*9
0.9'*8
0.0090
8.82
8.36
1.751
1-1
FEB 1972
AVG
8.31
15.93
1.917
1.091
2.220
2.360
1.063
0.975
0.100
2.U60
2.256
I*. 616
13.93
6.81
5.16
169.95
28.90
56.56
9.1*1
0.0590
0.1088
0.0071
0.1159
15.3217
0.3759
0.1667
1.131*1*
0.1*31*8
15.6537
22.559
0.91*0
0.0159
7.27
6.81*
1.086
1-1
MAR 1972
AVG
6.98
11.93
1.709
1.1*10
1.800
2.520
1.1*00
0.993
0.11*6
2.666
1.891
l*.l*ll
16.62
7.12
5.UO
11)2.1*1*
23.19
1*9.72
8.96
0.101*0
0.0911*
0.0098
0.1011
9.3588
0.3006
0.1590
1.1326
0.7367
9.6686
21.750
0.906
0.0171*
5.81
5.26
0.826
1-1
APR 1972
AVG
3.05
5.51
1.807
1.21*0
I*. 180
5.250
1.256
1.013
0.21*9
5.1*99
l*.l»35
9.685
lit. 17
6.1*9
U.92
167.08
11.13
19.79
i».77
0.5230
0.0798
0.01*1*1*
0.121*3
1.7965
0.2893
0.0652
0.1*231
3.5207
1.81*26
15.557
0.61*8
0.0137
9.06
5.87
0.966
2-2
MAY 1972
AVG
7.08
12.1*5
1.758
1.318
6.090
7.680
1.261
0.956
0.275
7.955
6.03U
13.71U
10.1*1
i*.58
3.1*8
227.29
36.57
32.1*1*
8.92
0.1080
0.1851*
0.0209
0.2063
8.8511
0.9562
0.1585
0.7261
0.5075
9.0286
21.607
0.900
0.031*2
6.03
5.1*2
1.003
2-2
JUNE 1972
AVG
M V U
5.81
9.26
1.591*
1.681*
5.11*0
8.370
1.628
0.967
0.315
8.685
5.157
13.527
12.18
l».6d
3.52
191*. 27
29.61
26.99
8.69
0.1310
0.1521
0.0196
0.1717
7.760li
0.7751
0.1503
0.6981
0.581*9
7.9*11
21.316
0.888
0.0291
5.89
5.23
0.855
2 -2

-------
it was necessary to adjust wasting to develop a different quality




sludge; thus in April, sludge waiting was reduced in an attempt




to develop an older, higher density, better settling sludge.

-------
                      PLANT PERFORMANCE



       Monthly average overall BOD reductions exceeded 95
-------
       Immediately prior to start-up, 65,000 gallons of seed




sludge from the HRSD James River Waste Treatment Plant were added




to Aeration Tank No. 1 that had previously been filled with city




water.  Only three of the five mechanical surface aerators, set




at low speed, were operated, and the return sludge pumps were set




to discharge about 50% of the incoming waste flow.




       On Day 1 (Tuesday, January k, 1972) of NFIC-C assistance,




mixed liquor total suspended solids  (MLTSS) concentrations were




in the 500 to 600 mg/1 range and the settleometer test revealed




a rapid settling sludge  (SSV  = 100, SSVg = 70).  The Return Sludge




Flow (RSF) was immediately increased to more than 100$ of the in-




coming flow.  On Day 2, the two idle aerators were turned on,  with




all five units remaining on the low  speed setting.  On Day 3,  all




five aerators were switched to the high setting, thereby increasing




the oxygen transfer capacity approximately fourfold.  Sludge settl-




ing characteristics and final effluent turbidity responded favor-




ably to these operational changes as evidenced by the first week




reduction in final effluent turbidity from 16 to 6 JTU.




       Effluent quality did not improve during the first few days




of the second week.  In fact, the turbidity increased slightly from




6 to 8 JTU.  To build up the low mixed solids concentration, primary




sludge was being pumped to the aeration tanks.  This practice most




probably impeded further improvement, especially when the volume of




sludge  ncreased with the increase in incoming flow.  On Thursday




this practice was discontinued and all primary sludge was sent to





                               27

-------
the aerobic digesters.  Final effluent quality then improved



dramatically and the turbidity was reduced to 2.2 JTU by the end




of the week.



       Luring the third week a plant upset occurred when the




return sludge pumps  and the  final clarifier  mechanism failed.




The aerators were also inadvertently  switched from high to low,




and control became  difficult due to the erratic operation of the




plant flow meters.




        On Saturday  of the third week,  the pH of the incoming waste




suddenly dropped to 1.6  as a result of a slug of acid waste acci-




dentally released from the brewery during a weekend shutdown for




maintenance and cleaning.  This destroyed all biological life in




the  secondary system and caused the final effluent turbidity to




jump  from h to 60 JTU.




       At the start of the fourth week (Monday, January 24-th) the




 idle  Aeration Tank  No. 2 was seeded with sludge from the No. 4




Aerobic  Digester and placed in service.  No. 1 Aeration Tank con-




 taining the acid mixed liquor was taken out  of service.  All pri-




mary  effluent and return sludge  was then rerouted to this aera-




tion  tank.  Process characteristics started  to improve Immediately




 thereafter, and by  Saturday the  final  effluent turbidity had been




 reduced from 60 to  3.5 JTU.   On  Saturday the process  was  again up-




 set by another  slug of acid waste.  Fortunately this  acid slug was




less  destructive than  the previous  and  it was  not  necessary to re-




 seed  and switch aeration  tanks again.   Effluent  quality was, how-




                              28

-------
ever, degraded almost as much as during the first slug, and by

Sunday the final effluent turbidity again increased to 60 JTU.

       Even with these start-up problems in January, final efflu-

ent BOD ranged from 1.0 to 5^ mg/1 averaging 12 mg/1 for the
                                               -£
month with an overall plant reduction of 97.7%.   Suspended

solids in the final effluent ranged from 1.0 to 52 mg/1 averaging

15 mg/1, for a plant reduction of 97-^.  A summary of plant per-

formance figures may be found in Table 3 (Page 9)•

       As shown by the following, the average plant loading was

considerably below the theoretical treatment capability during

start-up:
Ibs. BOD /1,000 cu. ft. Aeration Tank Volume	22.5
Ibs. BOD^/lbs.  MLVSS  	  0.23


Aeration Tank Detention Time @ Flow alone	17*2  hrs.
Aeration Tank Detention Time @ Flow & Return....  7-5  hrs.


Final Clarifier Detention Time	  5*7  hrs.
Final Clarif ier Surface Overflow Rate	  138  gals ./d/sq..ft.
       Despite plant upsets during this month, the average mixed

liquor sludge settling and concentration characteristics were excel-

lent and the sludge blanket remained deep down in the final clarifier

       A complete listing of general operating characteristics on a

month-by-month basis is shown in Table k (Page 17), and a summary of

plant loadings and process responses for the four major project seg-
ments is shown in Table 6.
                            Raw Concentration - F.E. Concentration
\ f f*±    ^ ^m  --i  *     «  |  ^     -^L »^^T/ wm ^mf ^tf A--i^*' ^•^ w-i \f ^» ^w^p ^f ^^M- ^i*^-»»   ^» -*^»     •^
* Overall plant reduction = 	Raw Concentration
                              29

-------
   SUMMARY OF PLANT LOADINGS AND PROCESS RESPONSES




HAMPTON ROMS SANITATION DISIEICT - WILLIAMSBURG STP
Line
No.
Column Number

1
2

3
1.
5
6
7
8
9


10
11
12
13

lit
15
16
17

18
19
20

21
22
23
2l«
25
26
27
UHIIS HI SERVICE
No. of Aeration Tanks
Ho. of final Clarifiers
AERATION INTENSITY
Average H.P.
H.P./1000 sq. ft. ASA
H.P. Hrs./MGD AFI
H.P. Hrs./lb. Influent BOD
H.P. Hrs./ASU
H.P. Hrs./lb. MLVBS
Resultant Aeration lank D.O. mg/1
PLANT LOAPniGS (to Act. SI. System)
Metered Flows in MGD
AFI - Aeration Tank Influent Flow
RSF - Return Sludge Flow
TFL - Total Flow
XSF - Excess Sludge Flow to Waste
Unit Flow Rates in Rrs.
ADT - Aeration Detention Time at AFI
ADT - Aeration Detention Time at TFL
CDT - Clarifier Detention Time at TFL
OFR - Clarifier Overflow Fate at AFI
BOD - Aeration Basin Influent
Concentration (mg/1)
Haas (log/day)
Aerator Loading (Ibs. BOD/1OOO cu. ft.)
PROCESS LOADINGS (As Functions of Ooerational Control!
ATC X ADT/mg/1 BOD
LbB RSTSS/lb. BOD
Organic Loading F/M (Ibs. BOD./ Ib. MLVSS)
j
RSP - Return Sludge Percentage (% of AFI)
SCR - Sludge concentration Ratio
AGE - Sludge Age (day)
AAG - Aerator Age (days)
Jan. Feb. & Mar.
Start-up Brewery Waste
1 2

1
1

235
18.80
3082
1A3
0.075
0.33
7-3


1.83
2.38
1*.21
0.090

17.13
7 AS
5-65
138

258
3938
22.5

0.166
15.12
0.23
130
1.75
8.82
8.36

1
1

160
12.77
1870
0.70
0.038
0.17
5-8


2.07
2A1*
U.51
0.121*

15-32
6.97
5.28
156

322
551"*
31-5

0.165
ll*.8o
0.2k
118
0.95
6.52
6. 02
April May & June
Bulking Stable Operation
3 "<

2
2

162
12.96
1751
0.61*
0.097
0.29
3-2


1*.1*1*
5-25
9.69
0.21(9

lU.17
6.U9
l*-92
167

330
12220
3U.9

0.060
7.81*
0.1*6
118
0.97
9.06
5.87

2
2

500
20.0
2139
0.76
O.lUl
0.27
l*.l


5.61*
7-99
13-63
0.293

11.20
U.61
3.50
213

329
15736
1*5.0

0.091
1U.95
0.35
11*2
0.91*
5.97
5.3U
Last Week
of Project
6/19 to 6/25
5

2
2

500
20.0
2139
0.76
0.199
0.27
1*.2


U.8U
8. 1*7
13-31
0.352

13.35
U .75
3.61
182

361
1U863
1*2.5

0.06
13.66
0.37
175
0.83
6.32
5-23
Project
Average
6

2
2

282
16.10
2131
0.83
0.081*
0.25
5-1


3-59
1*.70
8.29
0.191*

ii*.o9
6.20
l*.7l
173

317
9706
35-0

0.121
13-65
0.31
131
1.08
7-15
6.15

-------
                    TABLE NO.  6
                      (contd)

   SUMMARY OF PLANT LOADINGS AND PROCESS RESPONSES

HAMPTON ROADS SANITATION DISTRICT - WILLIAMSBURG STP
Line
No.
Column Number
PROCESS RESPONSES

28
29
30
31
32
33
3>*
35
36
37
38
39
1*0
1*1
1*2
1*3
1*1*
1*5
1*6
1*7
1*8
1*9
50
51
52
53
5l+
55
Sludge Settling
SSV (cc/1)
SSV6Q (cc/1)
DOB ( ft . )
BIT (£ of CWD)
Sludge Solids (in Terms of Sludge Units)
ATC - Aeration Tank Cone. (%)
WCR - Weight to Centrifuge Ratio (KLTSS/ATC)
RSC - Return Sludge Cone. (%)
SSCg0 - Settled Sludge Cone, at t = 60 min. (£)
SCR - Sludge Cone. Ratio (SSC6o/RSC)
SLR - Sludge Ratio (RSC/ATC)
SDR - Sludge Distribution Ratio (ASU/CSU)
SDT - Sludge Detention Time (hrs.)
STR - Sludge Detention Time Ratio (ADT/SDT)
SCY - Sludge Cycles (No. per Day'
SAH - Sludge Aeration Hours (Hrs. /day)
ASU to Final Clarifier (Million SLU/day)
Clar. Floor Loading (SLU/day/sq. ft.)
Sludge Solids (in Terms of Weight)
MLTSS (mg/1)
MLVSS (mg/1)
% Volatile
RSTSS (mg/1)
RSVSS (mg/1)
$ Vol.
SVI
SDI
ML Solids to Final Clarifiers (Ibs/day)
Clar. Floor Loading (Ibs/D/sq.ft. )
Jan,
Start-up
1
760
1*20
363
9-1*6
0.051*
5-75
313
10.02
18.37
1.75
1.71*
17.80
0.1+1
18.18
3-05
22.75
0.105
7-91
1800
1578
87.7
3000
271*0
91.3
233
0.1*3
271+72
2.07
Feb. & Mar.
Brewery Waste
2
938
71+6
615
9.18
0.082
7.62
297
13.86
0.95
1.81
12.2U
0.59
12.56
3-17
22. lit
0.158
11.90
2265
211*6
94. 7
1*011
3721+
92.8
329
0.30
39103
2.95
April May & June
Bulking Stable Operation
? 1*
957
794
650
U.77
0.523
3.05
1*31
5-51
5-32
0.97
1.81
1.80
3-52
1.81*
2.1*0
15-56
0.135
5.09
1316
1231
93-5
2187
2108
96.1+
603
0.17
1+8731
1.81*
91*1
778
660
8.8r
0.118
6.51
335
11.03
10.1*5
0.9!*
1.68
8.36
0.51*
8.5!*
l*.66
21.1+8
0.367
13.82
2183
2031*
93-2
3531
321*6
91.9
356
0.28
102683
3-87
Last Week
of Project
6/19 to 6/25
5
971*
872
TJk
7.87
0.213
It.bO
1*1*1
7.12
5.86
0.83
1.55
7-1?
0.95
7-31
1*.21
20.09
0.223
8.1*0
2030
1908
91*. o
287!*
261+3
92.0
1+30
0.23
8191+2
3.09
Project
Average
o
911+
712
595
6.35
0.165
6.18
323
10.89
11.87
1.08
1.76
10.09
1.05
10.33
3-31
20.89
0.222
8.36
2000
1861
93-1
3379
3133
92.8
356
0.28
59881
2.26

-------
                                                                  TABLE HO.  6
                                                                    (contd)
                                                   SUMMARY OF PLANT LOADINGS AND  PROCESS RESPONSES

                                                HAMPTON ROADS SANITATION DISTRICT - WILLIAMSBUHG STP
 Line
 No.
 56
 57
 58
 59
 60


 61
 62


63
61*
     Column Number

PROCESS RESPONSES

    Effluent Quality

        F. E.  Turbidity (JTU)

        F. E.  BODj  (mg/1)

        F. E.  BOD,  (Its. discharged)

        F. E.  TSS  (ag/1)

        F. E.  TSS  (Iba. discharged)

    Reductions by Act.  SI.  Process

        BOD,.        »)

        TSS        »)

    Overall Plant Reduction

       BODj        (%)

       T3S        «)
                                                              Jan.
                                                              Start-up
Feb. & Mar.
Brewery Waste
April
Bulking
May & June
Stable Oper.
Last Week
of Project
6/19 to 6/25
                                                                                                                                                  Project
                                                                                                                                                  Average
9.79
12.0
183
15.0
229
95A
87-2

97-7
97. U
6.76
11.0
1B9
17.0
293
96.6
85 .1*

98.1
9U.6
21.9
2k. 0
889
58.0
21U8
92.7
51.3

95.7
77.6
5.01
1U.3
685
12.2
571*
95-7
91.0

97.0
9U.U
2.U7
87
•j
ok?
3*7
8.1*
339
97-7
on. 8
yw.w
08 1
yO'-i-
96-2
9-29
U*.5
1*68
22.2
696
95-1*
81.6

97-3
92.0

-------
BREWERY WASTE ALONE
       Daring the months of February and March, when only "brewery-
wastes were treated, effluent turbidities fluctuated widely in a
2 to 20 JTC range.  One rise in turbidity, just after the start
of recovery from the second acid spill, was caused by an open valve
on the No. k Aerobic Digester effluent line which permitted digested
sludge to flow into the final clarifier, and thence to the aeration
basin as return activated sludge.  This resulted in a mixed liquor
with a dark gray color.  Other fluctuations during this period were
related to an overflow of digested sludge from the thickener to the
aeration tank and numerous mechanical and electrical difficulties.
       Final effluent BOD ranged from 5 to 26 mg/1 averaging 11 mg/1
during these two months for an overall plant reduction of 98 «0^.
Final effluent suspended solids concentrations ranged from 5 to 38
mg/1 averaging 17-0 mg/1 for an overall plant reduction of $k.6%.
       Though the February-March two-month average incoming flow
increased 15% and the BOD,- increased Uofo over January, the plant
loadings were:
Ibs. BOD /1,000 cu. ft. Aeration Tank Volume	31.5
Ibs. BOD /Ibs.  MLVSS	  0.2k

Aeration Tank Detention Time @ Flow alone	15-3  hrs.
Aeration Tank Detention Time @ Flow plus Return.  7-0  hrs.

Final Clarifier Detention Time	  5-3  hrs.
Final Clarifier Surface Overflow Rate..           156 gals./d/sq.ft.
                               33

-------
COMBINED BREWERY AND DOMESTIC WASTES




       During the last week of March, sludge settling became pro-



gressively worse and the  sludge blanket in the final clarifier be-




gan  to rise.  Since the  additional load of domestic  sewage was




anticipated  from the City of Williamsburg,  a second  aeration basin




was  placed  in operation to use sludge dilution as a  method to in-




crease  sludge settling.  This interim method worked for-about a




week until  the  system became so glutted with sludge  that bulking




became  inevitable.  Even the addition of the second clarifier at




this time did little to improve the situation.  Sludge was being




lost over the final clarifier weirs intermittently during this




period.




        A sludge loss occurred even on days when the sludge blanket




was two to three feet below the final clarifier water surface be-




 cause of the excessive velocity currents in the vicinity of the




weirs and around the submerged effluent pipe.  Proper leveling of




 the final clarifier weirs should eliminate this part of the problem




by providing uniform overflow velocities.




        When waste activated and primary sludge were  handled as des-




 cribed on Page  5 of this report,  problems were encountered.   For




 instance, when high sludge wasting rates  were employed,  the  aerobic




 digestion tanks frequently filled faster  than the thickened  sludge




 could be transferred to the irrigation site.   This would  cause liquid




 levels to rise  in the tanks to the point  where the aerator blades




 would become submerged,  overdraw amperage, and shut  off.   Furthermore

-------
sludge detention times in these tanks were minimal,  at best,  and


during periods of high wasting were insufficient for sludge stab-


ilization.


       A more conventional and perhaps better method of waste sludge


handling would have been to waste sludge directly to the gravity


thickeners and thence to the aerobic digesters.  This mode of opera-


tion would allow the sludge to be concentrated before digestion re-


sulting in a lesser volume of sludge to be aerobically digested.


Longer detention times would then be possible and volatile solids


reduction would probably be enhanced.


       The quantity of sludge wasted cannot be accurately documented


because the meter used to measure waste sludge was inaccurate at


low flow rates.  During April, however, a general effort was  made to


increase sludge age by decreasing the volume of sludge wasted.  The


return sludge flow was gradually increased from 3-5  mgd to 6.8 mgd.


These high return sludge flows (about 200$ of the incoming flow)

                                                                    •x-
were instrumental in increasing the sludge concentration ratio (SCR)


from 0.8 to about 1.6.  By the 25th of April settling was greatly


improved,  no sludge was lost over the weirs, and the daily average


turbidity was again reduced to below 10 JTU.


       During this period D.O- levels were maintained from about 1.5


mg/1 D.O.  to 5 mg/1 D.O.   Experience gained while operating  other


plants since the Williamsburg project showed, however,  that proper




* Sludge Concentration Ratio(SCR)=6° ***! fettled Sludge Concentration^ )
      B                     v   '       Return Sludge Concentration(RSC)




                               35

-------
dosages of ferric chloride and/or polymers can improve the settl-
ing characteristics of bulking sludges.  It is, therefore, desirable
that facilities  (feeders, meters, controllers and piping) be avail-
able at the Williamsburg  plant for  the  emergency addition of these
chemicals when bulking  occurs.
       Final  effluent BOD ranged from 10 to 33 mg/1 averaging  2k- mg/1
during April  for an overall plant reduction of 95-7%-  Suspended
solids removal in April was poor, however,  with final effluent con-
centrations ranging from 3 to 300 mg/1 averaging 58 mg/1 for an over-
all plant reduction of  77-6%.
       Plant  loadings and detention times for April reflect the effect
of the reduced mixed liquor concentrations  and the increased flow from
the City of Williamsburg  as shown below:
 Ibs.  BOD^/1,000 cu.  ft. Aeration  Tank Volume	3^-9
 Ibs .  BOD5/lbs .   MLVSS	  0.1*6

 Aeration Tank Detention Time @  Flow alone	 Ik.17 hrs.
 Aeration Tank Detention Time @  Flow plus Return...  6.1*9 hrs.

 Final Clarifier Detention Time	  1* .92 hrs .
 Final Clarif ier Surface Overflow Rate	   igy gals ./d/sq .ft.
                               36

-------
STABLE OPERATION PERIOD




       The final two months of the technical assistance project




(from May 1, to June 25, 1972) were characterized by relatively




stable plant operation.  Effluent turbidities were generally




below 6 JTU and higher turbidities, when they occurred, were




almost always due to an overflow of digested sludge from the




thickener to the aeration basins.




       During the first two weeks of May, sludge overflowed the




thickener weirs almost daily causing an increase in turbidities




and a general degradation of sludge settling characteristics.




In order to minimize this problem it was recommended that thickener




sludge blanket levels be recorded hourly and that sludge pumping




to the thickeners be regulated closely when there was danger of the




sludge overflowing the weirs.




       When the above practice was adhered to, and process demands




followed rigorously, turbidities below k JTU were not uncommon.




Final effluent turbidities for the final week of Federal assistance




(June 19 - June 25, 1972) averaged about 2-5 JTU.  BOD  and suspend-




ed solids averaged less than 9 mg/1 during the same period.




       Final effluent BOD  ranged from k to 32 mg/1 averaging lU mg/1




during the last two months for an overall plant reduction of 97.0%.




Suspended solids concentrations ranged from 3 to 37 mg/1 averaging




12 mg/1 for an overall plant reduction of 9^'5°/o.
                             37

-------
       The higher influent flows  in May  and June coupled with the


increased return sludge flow percentages required to meet process


demands increased aerator loadings and lowered detention times as


shown below:
Ibs. BOD../1, 000 cu. ft. Aeration Tank Volume...  if 5-0
        5
Ibs. BOD^/lbs.   MLVSS	  0-35
        5
      ^>

Aeration Tank Detention Time @ Flow alone        11.2 hrs.

Aeration Tank Detention Time @ Flow plus Return  k.6 hrs.



Final Clarifier Detention Time	  3-5 hrs.

Final Clarifier Surface Overflow Rate	  213 gals ./d/sq.ft.
PLANT LOADING


       According to the engineers' design figures the total BOD,-


loading to the  secondary aeration tanks  (k tanks) was to be 40,000


Ibs. of BODj. per day; i.e., 10,000 Ibs.  of BOD,- per day per tank.


For the first three months of operation  the BODj- loading to the one


tank in service averaged less than 6,000 Ibs./day or about 60$> of


the design load.  With the addition of the City of Williamsburg


load in April the BOD^ load to two tanks increased to 15,000 Ibs./


day or about 75% of the design load for  two tanks.   Figure 2 is a


7-day moving average plot of BOD^ load to the aeration tanks in


Ibs./day.


       The aerator load (Ibs. BOD.-/1, 000 cu. ft. of aeration tank


capacity) was well within the capabilities of a complete-mix acti-


vated sludge plant throughout the duration of the project.  In fact


during the first four months of the project the average aerator load


 (30.1 Ibs. BOD/1,000 cu. ft.) was below  the somewhat conservative


                               38

-------
                                                    FIGURE 2
                                      7-DAY MOVING AVERAGE OF BOD LOADING
  20-
  18
  16-
c
c
o
H 1 1
Q12

C
 in
O 10
C'
0

U
C
w
   8-
   6-
   2.
     JAN.  4
FEB.  1
MAR.  1
   APR. 1



1972
MAY  1
                                                                                          JUNE  1

-------
                 .
10-Btate Standard   value of kO Ibs.  BOD /I,000 cubic feet.

 The increased load after the City of Williamsburg came on

 line caused this value to be exceeded 73% of the time during

May and June for  a mean of kl-k Ibs. BOD /1,000 cu. ft.   Figure 3

is a 7-day moving average plot of aerator  load.

       The organic loadings  experienced at Williamsburg were  also

well within  the plant's  treatment capabilities.   The  project

average was  0.31 lb •  BOD,-./lb.  MLVSS with January having the lowest

average F/M  ratio of 0.23 and April the highest at O.h6.  April's

average was  relatively high because of the decrease in mixed  liquor

solids during  the bulking phase.

        Hydraulic loadings in the  plant were light throughout  the

project.   This is particularly evident in the clarifier surface

overflow  rate  which  averaged only 173 gal./d/sq.ft. for the project.

Figure U    is  a 7-d.ay moving average plot of clarifier surface

overflow  rates.


SUMMARY OF PLANT PERFORMANCE

        The Virginia  State Water Control Board has set final efflu-

ent discharge  standards  of 35 mg/1 BOD and 20 mg/1 suspended  solids

 (monthly  average values)  for the  Williamsburg Sewage  Treatment Plant.

The monthly  average  final effluent BOD throughout the project was

less than the  State  certification value and except for the month of

April, when  an average of 2k mg/1 was  recorded, the final effluent

BOD was consistently  below 17 mg/1.  With  the  exception of April
   Recommended Standards  for  Sewage Works, 1971 edition.

-------
                                                        FIGURE 3
                                      7-DAY M3VING AVERAGE OF AERATOR BOD  LOADING
     90
     80
     70

     60
     50

     ao-


     30.
I
 •
t,
 •
u
   o 20
   c

   |n

   CQ
jr-  rn
^  S 10
   D

   ffl
   c
   I
   w
TEN STATES STANDARDS VALUE - UQ LIL  BOD,.71000 C.F./DAY
        JAN.
                      FEB.  1
              MAR. 1
APP.  1
1972
'1AY  1

-------
                                                FIGURE  It




                              7-EAY MOVING AVERAGE OF CLARIFIER OVERFLOW RATE
JAN.
JUNE  1

-------
when bulking caused the monthly average of suspended solids to




reach 58 mg/1, the final effluent suspended solids were also




consistently below 17 mg/1.




       Figure 5 is a 7-day moving average plot showing the rela-




tionship of aerator influent BOD concentrations to that in the




final effluent.  Also shown on Figure 5 is the dashed line repre-




senting the State certification value of 35 mg/1 BOD.  The small




hump in the final effluent BOD curve towards the end of January




was due to the acid waste which hit the plant during start-up.




       Figure  6  is a 7-day moving average plot of aerator influ-




ent suspended solids and final effluent suspended solids.  The




plot shows that the VSWCB certification limit of 20 mg/1 suspended




solids was exceeded only during the start-up month of January,




for a short period during February (undetermined cause) and, of




course, during April when bulking was experienced.  Analysis of




the BOD and suspended solids curves further indicates that final




effluent quality was more a function of operational control pro-




cedures (aerobic digesters and sludge thickeners as well as the




activated sludge system) than a response to variations in influent




flow and BOD loadings.  Seven-day moving averages were used in




these plots since they tend to level out immediate fluctuations




and smooth out a curve.




       Probability plots of final effluent BOD'   and suspended solids




  •licentrations and percent reductions were also developed to permit

-------
450
                                                 FIGURE 5




                 7-DAY MDVING AVERAGE OF AERATOR INFLUENT AND FINAL EFFLUENT BOD5 OWGENTRATIONS
                                                                        VSWCB Certification-35
    JAN
JUNE  1

-------
350
                                                  FIGURE 6



                 7-DAY MOVING AVERAGE OF AERATOR INFLUENT AND FINAL EFFLUENT SS CONCENTRATIONS
    JAN.  4
                                                                                            JUNE 1

-------
more detailed evaluation of the effluent quality (See A-l to A-3l) •




A summary of this probability data is tabulated in Table 7 and 8.





Performance - Start-up vs Entire Project (Figures 7 and 8).





         Figures 7 and 8 are of special interest since they show




the relationship of final effluent BOD's and suspended solids dur-




ing the  start-up month of January to that of the entire project.





         Entire Project Curves (January k, 1972 - June 25, 1972)





         The probability plots of all the final effluent BOD and




         Suspended Solids data from January k, 1972 to June 25,




         1972 are labeled "Entire Project" in Figures 7 and 8.




         They exhibit a wide variation in slope, which because of




         the somewhat uniform aeration tank influent BOD and Sus-




         pended Solids Concentrations (BOD range of 258 to 3^ mg/1




         averaging 317 mg/1, TSS range of 100 to 153 mg/1 averag-




         ing 125 mg/l), is  indicative of changes in treatment per-




         formance .





         Start-up Curves (January 1972)





         The BOD and Suspended Solids curves for January 1972  (Fig-




         ures 7 and 8) display the same wide variation in slope as




         the project curves.  This variation is logical when one




         considers the problems that were associated with the




         Williamsburg start-up, for instance, the acid brewery




         waste which killed all the aeration tank biota.  The




         steeply sloping portion of the January curves corres-




         ponds to this acid waste period.

-------
                                                      TABLE  NO.  7

                                           SUMMARY OF BOD  5  PROBABILITY  DATA

                                  HAMPTON ROADS SANITATION DISTRICT  -  WILLIAMSBURG  STP
Probabllity % Equal
To Or Less Than
Jan. 72
             Feb. 19
                                                                      March  72
                                                                                   April  72
                                                    May 72
June 72
Raw BOD 5 (me/1 )
50%
10%
90%
Aeration Tank Influent BOD 5 (mg/1)
50%
10%
90%
Final Effluent BOD 5 (me/1)
50%
10%
90%
Secondary Reduction in BOD 5 %
50%
10%
90%
Overall Plant Reduction In BOD 5 (%)
50%
10%
90%
580
2i»i»
626

286
150
317
8.0
2.6
29.0
96.8
83.0
98.8
98. i»
91.3
99.6
582
U60
70it

297
25I»
3UO
10.3
7.2
13. C
96.6
95.7
97.5
98.2
97.6
98.8
530
280
850

33i»
283
l»33
12.0
6. it
18.8
95.9
9i».0
98.2
97.8
95.6
98.9
500
290
955

333
273
393
2I».0
18.3
29.8
92.U
91.5
9U.8
95.3
91 .5
97. U
U55
280
7UO

332
256
i»10
17.5
9.0
26.0
95.1
92.6
96.6
96.3
92.7
98.1
5U
32U
703

3UO
25l»
1*00
1 1 .6
6.5
16.7
96.9
93.8
98.2
98.0
95.3
99.0

-------
                      TABLE NO. 8



SUMMARV OF TOTAL SUSPENDED SOLIDS (TSS) PRORABILITY DATA




  HAMPTON ROAOS SANITATION PI STRICT - WILLIAMSBURG STP
Probab! 1 i ty ? Equal
To Or Less Than
Raw Total Suspended Sol Ms (mc/1 )
50$
10%
90?;
Aeration Tank Influent TSS (m^/1 )
50?
in?
1(1°;
Final Effluent TSS (rip/I )
50°;
10$
no*
Secondary Reduction In TSS (?)
50?
in?
90?
Qypral 1 Plant Reduction in TSS (?)
50?
in?
90?
Jan. 72

335
120
lOfiO

120
Ul
196

q
?.<4
Ul

qi.n
5B.I4
97.3

«)7.5
88.5
qq.3
Feb. 72

336
I7n
620

115
UU
311

16
9
32.3

85.0
fin. 3
95.0

9U.O
90.0
97. «
March 72

270
86
l»60

93
62
153

li»
10
27.5

82. R
7U.7
90.7

93.7
89.5
97.7
April T>.

255
118
klS

112
80
170

35
10
125

71.8
U3.6
96. U

85.0
58.0
98.5
May 72

186
82
290

100
52
380

111
5
26

86.6
71.1
97. l»

92.6
82.6
97.6
June 72

278
166
389

100
71*
200

10
l».3
15.8

91.6
83.6
95.7

96.7
92.9
99.1

-------
                                 FIGURE 7

                     PROBABILITY QF FINAL EFFLUENT BODC
                                         I   I
  60
  50
  30 J
w
  20
  10
                                                  30.5
                                                        29.0
                    I      •    '
                   10               50                90
                  PERCENT OF  TIME LESS THAN OR  EOUAL TO

-------
                                    FIGURE  8

                 PROBABILITY OF FINAL EFFLUENT SUSPENDED SOLIDS
   60
8  50
M
•J
c
g 40
Q
2
W
(A
S3
EH
a
K
D
  30
w
  20
  10
                     I       '    '    «    I    '   «    «       I

                     10                 50                90
                  PERCENT OP  TIME LESS THAN OR EOUAL TO

-------
               FIGURE  9

    PROBABILITY OF FINAL EFFLUENT BOD
  I      '     '   '   I
 10               50                 90
PERCENT OF TIME LESS  THAN OP EOUAL TO

-------
                                       FIGURE 10

                      PROBABILITY OF FINAL EFFLUENT SUSPENDED SOLIDS
ro
                                           I
                        10                50                 90
                     PEPCENT  OF TIME LESS  THAN OR EOUAL TO

-------
Performance - June 1972 vs Entire Project (Figures 9 and 10).





         Figures 9 and 10 are similar to Figures 7 and 8 except




that the June BOD and Suspended Solids curves are compared to  the




project curves.





         Entire Project Curves (January k,  1972 - June 25,  1972)





         The "Entire Project Curves/' described on Page k6,  are




         also reproduced on the Figures 9 and 10 for compari-




         son with the "Stable Operation Curves."





         Stable Operation Curves (June 1972)





         The curves representing June's data are straight and




         do not exhibit much slope which indicates a more




         stable plant operation.  The reason for this improved




         performance in June was the absence of mechanical




         problems and the increase in operator familiarity with




         the plant and control techniques.  It should be noted




         that the 50 percentile effluent BOD and Suspended




         Solids concentrations for June were well below the




         discharge limits set by the State of Virginia; even




         the 90-Perceft"kile values were below 17 mg/1 for both




         BOD and Suspended Solids.
                              53

-------
                  SUGGESTED PIANT MODIFICATIONS








       The following are suggested improvements for the Williams-




burg Waste Treatment Plant:





CONTROLS




       It is necessary to  adjust Return Sludge Flow  (RSF)  and




Excess Waste Sludge Flow (XSF) to meet the process demands.  The




plant operators at Williamsburg were  severely hampered in  their




control attempts  since the appropriate meters could not be viewed




by one man while  the actuating valves were being turned.   There-




fore, two men  were required to make the flow adjustments.  The




job was made doubly hard because the waste sludge and return sludge




lines branched off a common header, and any adjustment of  one flow




would affect the  other-  The  installation of remote manual control-




lers for RSF and  XSF are,  therefore,  recommended to enable one opera-




tor to make the necessary  adjustments while observing the  appropri-




ate meters at  the control  building meter panel.





SLUDGE HANDLING




       Density sensors coupled to automatic control devices are




recommended to regulate the pumping of primary sludge and  thickener



sludge.  Minimum  sludge volumes at maximum sludge density  could be




achieved by the addition of automatic controllers, thereby increas-




ing the effective capacity of existing thickeners and aerobic

-------
digesters, and minimizing the deleterious recycle of septic sludge




to the activated sludge system.  While greatly reducing the number




of man-hours needed for sludge control,  such controllers should




also induce improved performance of both the activated sludge pro-




cess and the waste sludge disposal system.




       Most important, however, is the need to accelerate the




construction program for the sludge disposal facilities discussed




in the Engineers' report.  This sytem consists of centrifuging the




thickened sludge followed by incineration.




       In the future, when the Williamsburg WTP hydraulic load reaches




or exceeds the true plant capacity, additional meters and control




gates will be needed to insure accurate balancing of flows between




multiple units.  The recommended additional meters and valves in-




clude :




             1.   Control valves and meters on the mixed




                  liquor inlet line to each final clari-




                  fier-




             2.   Control valves and meters on the sludge




                  withdrawal line from each final clari-




                  fier.




             3-   Each of the valves noted above should




                  be provided with remote manual control-




                  lers at the central meter-control panel.
                            55

-------
Another automatic controller that should be considered for the




Williamsburg plant when operating at design flows and loads is




a one to proportion return sludge pumpage according to the vary-




ing incoming wastewater flow rates.

-------
                          SUMMARY
       The Hampton Roads Sanitation District and NFIC-C person-




nel demonstrated during the six-month technical assistance pro-




ject at the Williamsburg WTP that this plant when properly oper-




ated will produce an excellent final effluent when treating




brewery waste alone, or a combined brewery and domestic waste.




It should be noted, however, that during the first three months




of operation, when only brewery waste was treated, both organic




and hydraulic loads were light.  During the final three months




of the project normal organic loadings were experienced but the




clarifier surface overflow rate remained low.  Throughout the




project numerous mechanical and operational problems were en-




countered, but despite these problems reductions in BOD- averaged




97% (530 to 15 mg/l) while reductions in suspended solids averaged




S2/o (320 to 22 mg/l) .




       Three basic problems predominated causing intermittent high




effluent BOD and suspended solids levels:





       1.    Acid spills entered the treatment plant during




             start-up.  Closer cooperation between brewery




             and District personnel has prevented this prob-




             lem from recurring.

-------
      2.    Sludge bulking during April.  This bulking sludge




            could probably have been  controlled more effect-




            ively and rapidly by the  application  of coagulant




            aids •




      3-    Unwarranted  recycle of  septic sludge  from the




            sludge disposal  system  to the activated sludge




            process.  This problem  should be  eliminated by




            the addition of  the proposed sludge handling




            facilities.





      Elimination of these and other  identified difficulties




should enhance process control and further improve overall plant




performance and final effluent quality.




      A prime reason for the success  of this  project was that




even though process  imbalances did occur frequently, the demon-




strated operational  control tests that were  used to monitor  plant




performance permitted such upsets to be quickly recognized and




corrected.

-------
                      RECOMMENDATIONS
       The following recommendations are made in order that the




Williamsburg Plant may consistently produce the high quality




effluent of which it is capable:





       1.    The use of the full series of control tests




             demonstrated during the NFIC-C assistance




             project should be continued.




       2.    Return sludge flows and waste sludge flows




             should be determined by process demands.




       3•    An improved method of sludge disposal should




             be implemented as soon as possible to replace




             the temporary compromise waste sludge handl-




             ing system.




       k.    As the incoming BOD  load increases, the two




             tanks now used as aerobic digesters should be




             put into service as additional aeration tanks.




             The first additional tank will be needed when




             the average load to the aeration tanks exceeds




             20,000 Ibs. BOD  per day.




       5.    Remote manual controllers should be installed to




             permit proper regulation of return sludge flow




             and waste sludge flow.
                                59

-------
6.    Installation of automatic density controllers




      should be considered to regulate the concentra-




      tion and pumpage of primary sludge and thickener




      sludge for more efficient sludge disposal.




7.    Additional control valves and meters should be




      considered to enable the balancing of flows




      between multiple units when the average hydraulic




      load approaches plant capacity.




8-    Chemical feed equipment and piping should be




      installed to permit emergency addition of metallic




      salts and/or polymers to the aeration tanks or




      final clarifiers to assure maintenance of satis-




      factory effluent quality in the event of bulking.
                   60

-------
    APPENDIX A







 PROBABILITY PLOTS




JANUARY - JUNE 1972

-------
                                                         A-l
                                           PROBABILITY  OF RAW BOD-JAN.
  800 :
  700
  600
  500
  400
I
   300
   200
   100
           0.05  0.1  0.2   0.5   1   2
                                   5    10     20   30   40  SO   60   70   BO     90    95
                                     PERCENT OP TIME LESS THAN OR EQUAL TO
                                                                                     98  99      99.8 99 9
                                    PROBABILITY OF  RAW SUSPENDED SOLIDS-JAN.
   800
   100
                                      __!° _  »    30  40   50  SO   70   BO      30
                                      PERCENT OP TIME LESS THAN  OR EQUAL TO
                                                                                 95    98   99
99.9       99.99

-------
                                                          A-2

                                           PROBABILITY OP RAW BOD-FEB.
                                    m
  800
  700
  600
  500
                                                                                        f:::
  1100
1
  300
  200
  100
      0.01    0.05 0.1  0.2   as  1   2      5    10      20   30   40  50   60   70   80     90    95     98   99      99.8 99.9      99.99
                                      PERCENT OF TIME LESS  THAN OR  EQUAL TO
   800
   700
  600
  S0(f
  400
  30d
  200
  100
9.99
E3
=
=t
— -
= =f:i
^FF
.:
— r~
— r-]- ~
99.9
1.^
-;;--
W4
• -J-
~-~
19.9
=t
— t
•-[
—
3
9
-1
*-«
'

PROBABILITY OF RAW SUSPENDED SOL
9 91 95 90 10 70 60 50 10 30 20
	 ::::::::: :::: rttT ~qrrt ::::::::::::::::::::
-.:: J_i L: .K|irfc:J3_! .TTrn t - • : mjjj I "HUti
ijfe^ : : - 1$& .p^|p'^'Hf:P | | 1
PERCENT OF TIME LESS THAN OR E(
IDS-FEE.
10 5 2 1 0.5 0 2 O.I 0.05 0.0
;;;;i;E!EEEEi-;i!!!:;!!!E;-:ipEp
! . . f 	 — -, 	 	 	 . 	
1
!.i!::::i«»p 	 1 	 	
:: :::::::iz 	 :::;: ±:::— ;- ::::?-
:::::::i:=j|- H:::r::: : ::::
- " ' 	 1 	 •- -r-|- tf-f- •- i 1 - — i — . *-i-t- ...^ .. — •
90 95 98 99 99.« 999 """"Tl
?UAL TQL

-------
                                             PROBABILITY  OP RAW BOD-MAR.
  800
  700
  600
  500
  400
  300
  200
  100
      0.01    0.05 0.1  0.2  0.5   1   2     5    10      20   30   40   50  60   70    80     90    95     98   99      99.8 99.9

                                       PEHffcHT OF  TIME tESS THAN  OR EQUAL TO
                                     PROBABILITY OF RAW  SUSPENDED SOLIDS-MAR.

     99.99       99.9 99.8      99   98     95    90      80   70   60   50  40   30   20      10    5
                                                                                             1   0.5   02 0.1 0.05    001
                                                                                           W---=
                                                                                           11- Ui
  800
  700
  600
0500
H
  400
  300
  200
  100


     'o. 1     0-05 "•'  0'Z   0.5  1   2     5    10     20    30   40  50   SO   70   80      90    95     98   99      99.8 99 9       99 99
                                       PERCENT OP  Tim LESS THAN OR EQUAL TO

-------
                                           PROBABILITY OF RAW BOD-APR. '
  800
  700
  600
 '500
                                              :tru
                       -ffl
§
I
400
                                         I
  300
  200
  100
           :!BEr
                         * -Hi-1 —1---
                         :-^--l=r-
                                   cas
                                                                        t
                                                 ttffl
      0.01    0.05  0.1 O.Z   O.S  1
                                   5    10     20    30  40   SO  60   10   to     90    95     98   99      99.8 99.9
                                     PERCENT OP TIME LESS THAN OR  EQUAL TO
                                   PROBABILITY OF  RAW SUSPENDED SOLIDS-APR.
                                  95    90     BO    TO   60   SO  40   30   20      10     S
                                                                                     Z   1   O.S   0.2 0.1 0.05    °"
   800
                                      PERCENT
                                                30   40  50   60   70
                                            OF  TIME LESS  THAN OR EQUAL TO
                                                                           90    95     9B  99

-------
800
                                                        A-5

                                           PROBABILITY OP RAW BOD-MAY
    0.01    0.05 0.1  0.2   0.5   1   2
                                        0     20    30   40  SO   60   70   80     80    95     98   99      99.8 99.9
                                      PERCENT OF TIME LESS THAN OR EQUAL TO
                                   PROBABILITY OP  RAW SUSPENDED  SOLIDS-MAY
                                  95	  90	  80    70   GO  50   -10   3J   2'J      10     5      2    1   O.a   D 2  0.1  0.05    001
800
                                  5    w      20   30   40   50  60   70    »0     00    ?5
                                     .PERCENT OF TIME  LESS THAN OR EOUAL TO
99       S98 999

-------
                                                         A-6
                                           PROBABILITY  OP RAW BOD-JUNE
 800
 700
 600
  500
  400
  300
  200
  100
      0.01     0.05 0.1  0.2   0.5   1    2     5    10      20   30   «  50   60   70   10      90    95     98  99      99.» 99.9
                                      PERCENT OF TIME LESS THAN OR EQUAL TO
                                    PROBABILITY  OF RAW  SUSPENDED SOLIDS-JUNE

     99.M       999 Wi      99   98 _   95    90      80   70   6J  50  «   M   :J      13    5     I    1   O.b   0!  O.I  0.05    "II
  800






  700







•J600


S



D 500
£ too
                                                                                            trr
                       ±t±t
tn
D
I
  300
  200
  100
                          ffi
                       -i+r-
                   +±
                                      PERCENT J°OF  T°IME4°LE5SS THAN° OR'"EOUAL'°TO  "

-------
                                                      A-7
900  r-
800  :
PROBABILITY OF  PRIMARY EFFLUENT BOD-JAN
                        55EET
200
100
   MI    0.05 0.1 OS  0.5  1
                                      10     20   90   40  50   60  70    80     90    9b
                                   PERCENT OF TIKE LESS  THAN  OR EQUAL TO
                            PROBABILITY OF  PRIMARY EFFLUENT SUSPEHDED SOLIDS-JJIN.
                       99   98     95    90     80   70   SO   59  40   30    iH     !0    5
                                                                                           0.5   0.2 0.1 0.05
                                 »    10     20   JO   40  SO  Ml   70   80     90
                                    PERCENT OF TINE  LESS THAN OR EQUAL TO

-------
                                                      A-8
                                  PROBABILITY OF  PRIMARY  EFFLUENT BOD-FEB.
900
800
    ' 0.01     0.05  0.1  0.2   0.5   1   2     5     10     20   30   40  50   60   70   80     90    95     98   99      99.S 99.9
                                    PERCENT OF TIME LESS THAN OR EQUAL TO
                           PROBABILITY OF PRIMARY EFFLUENT SUSPENDED SOLIDS-FEB.
                        99   9'    «     9°     ti   '0   60  50   40  30    20     10    5     21   0.5   02  0.1 0.05    001
                                   PERCENT OF TIME LESS THAN OR EOUAL TO
                                                                                               99.1 99)

-------
                                                          A-9
                                     PROBABILITY OF  PRIMARY EFFLUENT  BOD-MAR.
  900
  800
  700
{J600  —
« 500
u
D
  400
 K
 0.
   200
   100
      0.01    0.05 0.1 0.2   0.5   1   2     5    10     20   30   40  50   60   70   80     90    95     98   99
                                       PERCENT  OF TIME  LESS THAN OR EOUAL TO
 8300  Eh-:::Sr:rr
                              PROBABILITY OF PRIMARY EFFLUENT SUSPENDED SOLIDS-MAR.

      99.99       99.9 99.8      99   98     95    90     60    70   60   50   40  3T    TO     1,0    5     2    t   0 "i   r ;  0 1  0 05     001
                                      __ '0     20    30   «  50   60   Ji

                                      PERCENT OF TIME LESS  THAN
•0   Pn

OR EOUAL TO

-------
                                                       A-10
                                   PROBABILITY OP PRIMARY  EFFLUENT BOD-APR.
900
800
     nm    005 0.1  0!   0.5   i
                                  5     10     20   30   40  50   60  10    10     90    95
                                    PEPCFNT OP TIME LESS THAN OR EQUAL  TO
                            PROBABILITY OF PRIMARY EFFLUENT SUSPENDED SOLIDS-APR.
                        5?   98     95   90    80   'Ci   6:  50  40  30    13     10    5      2
                                                                                            i.i   o; o.i o.os	o_oi
          0.05  0.1 02   05   1
                                       10     20   30  40  50  to
                                   PERCENT OF TIME LESS THAN OR EQUAL TO

-------
900
800
                                                        A-ll

                                   PROBABILITY  OP PRIMARY EFFLUENT BOD-MAY
100
    0.01     0.05 0.
              102051    2      5     10     20   30   40  50   60   70   80     90    95     98   99      99.8 99.9
                                    PERCENT OF  TIME LESS THAN OR EQUAL TO
                           PROBABILITY OF PRIMARY EFFLUENT SUSPENDED  SOLIDS-MAY
             9.9 996      99  99    95    90     80   70   60  50   40  30   20      10     5     21   0.5   02 0.1  0.05     001
                                  5    10      20   30
                                    PERCENT  OF TIME
10  50
 LESS THAN OR

-------
                                                     A-12

                                 PROBABILITY  OF PRIMARY  RPFLUENT BOD-JUNE
900
 800
 700 =f
i500
. ttOO
1300
 200
 100
     0.01    0.05 0.1  0.2   09
                                  5     10     20   30   40  50   60   70   80     90    95     98
                                    PERCENT OF TIME LESS  THAN OR EQUAL TO
                                                                                         99      99.8 99.9      KM
                            PROBABILITY OF PRIMARY EFFLUENT SUSPENDED  SOLIDS-JUNE
                        99  98     •     90     80   70   fO  50  40   30   20      10     5     2
                                                                                            0.5   0.2 0.1 0.05    001
  800
     0.01     0.05  01  0
                                  5     10     20   30   40  50   GO  70   80     M    95
                                     PERCENT  OF TIME LESS THAN OR EQUAL TO

-------
  90.0
                                                           A-13

                                      PROBABILITY OF  FINAL EFFLUENT BOD-JAN.
  80.0
  70.0
4*60.0
  50.0
  ao.o
                                                                             ill!
Eso.q
  20.0
   10.0
            0.05 0.1  0.2   0.5  1   2     5     10     20   30  40   50  60  70   80     90    95     98   99
                                          10     20   30  40   50  60  70   80     90
                                       PERCENT OF TIME LESS THAN OR EQUAL TO
                                                                                                    99.) 99.9       M.99
                               PROBABILITY OF  FINAL EFFLUENT  SUSPENDED SOLIDS-JAN.
                               98     95     90     80   70   60   SO  40   30    20     10    S     21   0.5   0 2 0.1 0.05    0 0]
    10
      a i    o.o5 0.1 0.2   0.5   i    2
                                    5    10      20   30   40   50  60   70    80     90    95
                                      PERCENT OF TIME  LESS THAN OR  EQUAL TO
                                                                                         98   99      99.8 999       99.99

-------
                                                          A-14
                                      PROBABILITY  OF FINAL  EFFLUENT BOD-FEB.
45.0
40.0
    °0 1      05  1  02    5   1   2     5    10     20    30  «0   50  60   70   80     90   95     91   99      99.8 99.9      99.99
                                    PERCENT OF  TIME LESS THAN OR EQUAL TO
                            PROBABILITY OF FINAL EFFLUENT SUSPENDED SOLIDS-FEB.
                        99   91    95    90    80    70   60   50  40   30   :0     10     5     2   1   0.5   12  0 1 0.05
  10
                                   PERCENT OF TIME  LESS THAN OR EOUAL TO
                                                                                               91J n.<

-------
05.0
40.0
                                                      A-15

                                    PROBABILITY OP FINAL  EFFLUENT BOD-MAR.
          0.05 0.1  0.2   0.5  1
                            2     5     10     20   30   40   50  60   10   80     90   95    98   99
                                    PERCENT OF TIME LESS HiAN OR BQOAL TO
                             PROBABILITY OF FINAL  EFFLUENT  SUSPENDED SOLIDS-MAR.
                                  95    90     80    70   BO   50  40   30   20      10    >      2   1   0.5   0 2  01 0.05    001
   "O. 1    0.05 0.1 0.2
                                             20    30  40   SO  60  71
                                    PERCENT OF TIME LESS THAN
'0   80     90    95
OR EOUAL TO

-------
                                                 A-16

                              PROBABILITY OF FINAL EFFLUENT BOD-APRIL
0.01    0.05 0.1  0.2   0.5   1   2
                                  10     20   30  40  50  60   70   BO     90    95
                               PERCENT OF TIME  LESS THAN OR EOUAL  TO
                                                                                   99      998 99.9
                        PROBABILITY OF FINAL EFFLUENT SUSPENDED SOLIDS-APR.
                   99   9»     95    90     «0   70   80  50   40  30    20     10
                                                              10     90    95
                              PERCENT OF TIME LESS THAN  OR EQUAL TO

-------
                                                     A-17

                                  PROBABILITY OF FINAL EFFLUENT BOD-MAY
15.0
UO.O
35.0
< 30.0
g
« 25.0
f
£ 20.0
B 15.0
10.0
5.0
0.0
0.

Dl

0.0

5 0.1

0.2
	 ^
0.5
:::. .
. _:£ 	
1 2
I^^fflSftMt^U
mSifiisi
	 ~ - 	
:z' :s::: ' 	 :""; ''
~: 	 ?si ::):::• : ::::• :;•::•;
	 	 l--i'-> 	 T-
	 	 1 C t-- 	 	
	 *--• i 	 -- 	 -- -4
~2~-:::::::::: : ::::: ::::: ::
5 10 20 30 40
PERCENT OF TIME L
^4±FF]^ FIE?!-
- -' ----r^-±- -••'•'• W^^~
• 7T;'35:±+:E:5tBEi-
1 i;;.-4it|::itt:! -'iitlr-
-! 	 L 	 . , -j 	 ^,4.. _ . _| 	 I-L
T. -~p iii:-4:|;;rif ,T4 'id
: :::::::::::|:|:::::::::;±j
: ii::::::: 	 :•' 	
_ ..-..-"^[j_^i:t::: ti::iii _^
	 -;.! 	 	 f-r 	
, ,- 	 1 TT_- U.I IT JT r _f_J
;::::::;:;; ;::r:ir;:::;:^EE
: . ±:. + ::::::+ [4. + :::::__
^ .:::-T:::::;;: -;•::::: ^::_
: :::::::::::::: ::T::::^
SO 60 70 80 90 S
ESS THAN OR EOUAL TO
2
5
/L

=:H$I
	 [i-f
— ^ i
m
^ r,1i: T
- 1 ' !~r ;
-t-rti
— ^E i
— rr- r i
ff -i- <
— '-M-
11 M
H^ffl
98 99
E:E —
-)-, 	 1 	
j. _ ~t
t:: 	
i:::-~
m\
i — —
99
tftj
:-^|-
.
^
^
1 ..:.-
-, !f
~ff
--
8 99.9
1
--1- 	
99
                           PROBABILITY OF FINAL  EFFLUENT  SUSPENDED  SOLIDS-MAY
                      99   98     95    90     80   70   60   50  W   30   10      13    5      !   I   O.S   02  0.1 0.05    001
10
        O.OS 0.1 0.2  0.5   1   2
                                S     10     20   30  40   50  60   7
                                  PERCENT OP TIME  LESS THAN
'0   8"     90    95
 OR EOUAL TO

-------
                                                      A-18

                                   PROBABILITY OF FINAL EFFLUENT BOD-JUNE
90.0
80.0
      1    0.05 0.1  0.2   0.5   1   2     S _  10	20  JO   40__SO   «>  70    «0	'»__  "    91  "
                                    PERCENT OF TIME LESS THAN OR EDUAL TO
                             PROBABILITY OF FINAL EFFLUENT SUSPENDED SOLIDS-JUNE
                        99   98     95    90     60   70   63  JO   <0  30    :0     10    5      :   I   0.5   0 2  01 0 05
                                       10     20   30   40  SO   GO   70   80     90    9S     9|  99
                                     PERCENT  OF TIME LESS THAN OR EQUAL TO

-------
 90.0>-
 80.0
 70.0
 60.0
i 50.0
I 40.0
 30.0
 20.0
 10.0
                                                        A-19
                                   PROBABILITY OF FINAL EFFLUENT BOD-PROJECT
                                                                            90    95     98   99      99.8 99.9       99.99
     0.01    0.05 0.1  0.2   O.S  1   2     i    10     20    30  40   50   SO  70
                                   PERCENT OF  TIME LESS THAN  OR EQUAL  TO
                           PROBABILITY  OF FINAL EFFLUENT SUSPENDED SOLIDS-PROJECT
              J9.9  99.8       99   98    95   90     80   70   60   50  40   30   20     10    5     21   0.5   02  0.1 0.05     0.01
  0.

-------
                                                    A-20


                          PROBABILITY OF  SECONDARY  REDUCTION IN BOD.-JAN. 72
100  ^~r—r
    0.01    0.05 0.1  0.2   0.5  1    2     5    10     20    30  40   50  60   70   80     90   95    98   99      99.8 99.9      9UI
                                    PERCENT OP TIME  LESS THAN  OR EOUAL  TO
  82
 it,oMM
                             PROBABILITY  OF SECONDARY REDUCTION IN S.S.-JAN. 72
                        99  98     95    90     80   70   60   50  40   30   20     10     5     21   0.5   0.2 0.1  0.05    0.01
                                           iiiimm+mT
  90
  80

w
B,
  70
in


V)



H



§
S*
  60
-P
O
o
H
in
U)
O
NJ

O
  10 t=t
     0.01     0.05  0.1 0.2   0.5   1
                                       10     20   30   40  50   60  70    80     90    95    99  99

                                    PERCENT OF TIME LESS  THAN  OR EQUAL TO
                                                                                                           Ml

-------
                                              A-21
                   PROBABILITY OF SECONDARY REDUCTION  IN BOD5-FEB. 72
0.06 0.1 0.2   O.S   1   2
                        5    10     20   30   40  SO   60   70   CO     SO    95     J'.   99
                           PERCENT OF TIME LESS  THAN OR EQUAL TO
                   PROBABILITY  OF SECONDARY REDUCTION  IN S.S.-FEB. 72
              99   it     95    90     80   70   60  50   40   30   20     10     5     21  0.5   0.2  0.1 0.05 	0.01
005 0.1  0.2   0.5   1    2
                           PERCENT
                                    20
                                    OF
 30  «  50   60   70
TIME  LESS  THAN OR EOUAL TO
                                                                  90    ii     91  9'<

-------
                                                      A-22
 100
  98
  96
                            PROBABILITY OF SECONDARY REDUCTION IN BOD5-MAK. T2.
£
 .94
 in

§

592
  90
  88
  86
  8«

  82
                                                                      ftrt
     0.01    0.05  0.1 0.2  0.5
                                 5    10     20   30   40  50   60  70    90     90    95    98
                                    PERCENT OF  TIME LESS  THAN OR EQUAL TO
  100
                             PROBABILITY OF  SECONDARY REDUCTION IN  S.S.-MAR. 72
                            9«    95    M	«0   70   60  50   40  30    n	10    5
  10
                                                       SO  60   70   BO     90    95
                                   PERCENT OF TIME  LESS THAN OR EQUAL TO

-------
                                                      A-23
100
                            PROBABILITY OP
                                            SECONDARY REDUCTION IN BOD^-APR.  72
   0.01    0.05 0.1 0.2  0.5  1   2
                                 5     10     20   30   40  SO   60   70   to
                                   PERCENT OP  TIME LESS  THAN OR  EOUAL TO
100'
                             PROBABILITY OP  SECONDARY REDUCTION IN S.S.-APR. 7f
                       99   98     95    90     80   70   60   SO  40   30   20      10     5     ^   10502010 OS    0.01
                                      10     20
                                   PERCENT OF
 30  40  50  60   70   60     SO    85    36
TIME  LESS THAN  OR EOOAL TO

-------
                             PROBABILITY OP  SECONDARY REDUCTION IN BOD. ...»  .-
100
   ' 0.01    0.05  0.1  0.2   0.5   1    2      i     10     20    30   40  50  60   70    BO     90    95    it  99
                                     PERCENT OF TIME LESS  THAN  OR EOUAL TO
                                                                                                    999 99.9       99.99
 100
                              PROBABILITY  OP SECONDARY REDUCTION  IN S.S.-MAY  72
              99.9 99.8      99   98     95    90      80   70   60   50  40   30    20     10     5      2    1   0.5  0 2 0.1 0.05    0.01
  20
  10
    0.01     0.05 0.1  0.2   0.5  1   2     5    10
                                               20   30   40   50  60  '<
                                      PERCENT OF TIME LESS THAN
'0   10      »    95     98
 OR  EQUAL TO

-------
100
                                                       A-25

                            PROBABILITY OF SECONDARY  REDUCTION IN BODs-JUNE 72
    0.01    0.05 0.1  0.2   0.5  1   2     5     10     20   30  40   50
                                                                                95     98  99      99.8 99.9      99.> 9
                                    PERCENT  OF TIME  LESS THAN OR EOUAL TO
  80
  82
                             PROBABILITY OF  SECONDARY REDUCTION IN  S.S.-JUNE 72
                        99   98     95    90     80    70  60   50  40   30    20     10    5     2    1   0.5   0.2 0.1  0.05
 10
                                  5    10     20    30  40  50   60  70   80     91
                                    PERCENT OF TIME  LESS THAN OR EQUAL
10    95
 TO
                                                                                          99      99.8 99.9

-------
                                                      A-26
                                PROBABILITY OF PLANT REDUCTION IN BOD^-JAN.
100
 98
 82
                                      1C     20   30   40  50   f"   70   80     90    95     98  99      99.8 99.9      99.99
                                   PERCENT OF TIME LESS THAN OR EpUAL TO
 100'
                                 PROBABILITY OF PLANT REDUCTION IN S.S.-JAN. 72
                                 r)5 	"0     BO    70   60   50  40   30   20  	 10     5     2   1   0.5   0 2  0.1 0.05    0.01
  82
                                    PEPCEJJT OF TIMH  T.FS? THAN  OR P""'T ,m

-------
                                                        A-27
100
                                 PROBABILITY OF  PLANT REDUCTION IN BODg-FEB.
    0.01    0.05 0.1 0.2   0.5   1
 10D'
                                  5    10      20   30   40  50  60   70   10      90    95
                                     PERCENT OF  TIME LESS THAN  OR EQUAL TO

                                PROBABILITY  OF PLANT  REDUCTION IN S.S.-FEB.  72
                                  95   90      80   70   60   50  40   30   20      10
                                                                                       2    1   0.5   0.2 0.1  0.05    0.01
p,     —
  82
         ~0 5 0.1  0.2   0.5   1    2
                                              20   30   40   50  60   70    80     90    95     98  99
                                     PERCENT OF  TIME LESS THAN  OR EQUAL TO

-------
                                              A-28
                           PROBABILITY OF PLANT REDUCTION  IN BODg- ,„„.
 100
 98
  82
    0.01   0.0% 0.1 0.2   05  1   2
                                      20  30  4C  50  60  70   8&    90   95    98  99

                               PERCENT OF TIME LESS THAN OR EOUAL TO
                                                                                99.1 99.9      99.99
 100
 98
                         PROBABILITY OF PLANT REDUCTION IN S.S.-MAR. 72

           W9 991     M  9«   95    90    SO  70   60  50  40  30   20    10    5    2   1  0.5   02 0.1 0.05   001
            W
                         -5:rj7t±
Hit1


u
K
U
6.
w

u

e
.,

VO
N»
                                 -^~
        --H^--,--H-:^M
'.O
o
g88


t-



O- 86
                              " —T
CD
ro
                                                                            -f
                                                                               -1-
                                                                   	h-
                                10    J'j   »  40  so  f  ;o  u     9o   45

                              PERCENT OF TIME LESS  THAN OR EOUAL TO

-------
                                                        A-29
100  r-
                                 PROBABILITY OF  PLANT REDUCTION IN BODg-APR.
   ' 0.01    0.05 0.1 0.2   0.5
                         12      5     10     20   30   40   50  60   70    80     90    95     98   99
                                     PERCENT OF  TIME LESS THAN OR EQUAL TO
                                PROBABILITY  OF PLANT REDUCTION IN  S.S.-APR. 72
                                  95    90	80   70   60   50   40  30   ?0	10     5	2   1  0.5   0.2  0.1 0.05    0.01
  90,
  80
  70

§50
  40
  30
 20
 10
                                                                                                       :rtt
                                             Ji±::
                                                                         1
          0.05 0.1 0.1   OJ   1    2
                                   5     10     20   30   40   50  60  70    80     90    95
                                     PERCENT OF  TIME LESS THAN  OR EQUAL TO

-------
                                                       A-50
                                 PROBABILITY OP PLANT REDUCTION  IN BOD.-MAY
100
    0.01    0.05 0.1  02  0.5   1   2     5    10     2Q   30   40  SO  60   70    80     90    95     98   99       99.8 99.9      99.99
                                     PERCENT OF TIME LESS THAN  OR EOUAL TO
 82
 100
                               PROBABILITY OF  PLANT  REDUCTION IN  S.S.-MAY 72
                        99  IS     K    90      10   70   60   50  40   30    10     10	5
                                                                                               0.5   o? o.i 0.05    o.m
    0.01    0.05  0.1  0,2   OS   1    2
                                              20    30  40  50   60   70   10      90    95     98   99
                                     PERCENT  OF TIME  LESS  THAN OR EQUAL TO

-------
                                                        A-31
  100
   98
   96
                                  PROBABILITY nF  PLAI1T REDUCTION  IN BOD,-JUNE
   9U
                                                                             0)   !
w
A.
 in
n
   92
   90
EH
U


g
   88
   86
         £E£
   82
     0.01    0.05  0.1  0.2   0.5   1    2
                                    5     10     20   30   40   50  60   70   80      90    95    98   99      99 8 99.9

                                      PERCENT OF  TIME LESS THAN OR EOUAL TO
  100"
   98
   96
                                 PROBABILITY OF PLANT  REDUCTION IN S.S.-JUNE  72

                                    95    90     80    70  60  50   40   30    20     !0    5     2    1   0.5   0 2  0 1 0 05     0 01
       EEEF
                       -I-M-!

                       rfrt!
=liE
                           dill
 g
   92
   90
   88
   86
   84

                                                            frr1
                        5F
                                                     ru.;
   820^—'— 0.05 o.i  oT
                                       PERCENT  OP TIME*"LESS THAN7" OR
                                                                                   95    98   99       99.8 99.9       99.99

-------
             APPENDIX B







       SYMBOLS AND TERMINOLOGY




               USED IN




ACTIVATED SLUDGE PROCESS CALCULATIONS

-------
                     SYMBOLS AND TERMINOLOGY

                             USED IN

              ACTIVATED SLUDGE PROCESS CALCULATIONS
AAG         Aerator Age (Days sludge under aeration)

ADT         Aeration Detention Time (Hours - based on
                                     AIF + RSF)
            (Sludge ADT will differ from Sewage ADT in
             "STEP" operation)

AFI         Aerator Flow - Inf luent
            "(MOD of "waste Water)

AGE         Calculated Sludge Age  (Days)

ASU         Aerator Sludge Units

ATC         Aeration Tank Concentration
            t$> by Centrifuge)

AVP         Aeration Tank Volume (Cu. Ft.)

AVG         Aeration Tank Volume (Gallons)

-------
                             B-2
BLT         Clarifier Sludge Blanket Thickness
            (Either in feet, or fraction of CWD)

BLV         Glarifier Sludge Blanket Volume
            (Either in gallons or fraction of CVG)

BLX         Clarifier Sludge Blanket Index

BOD         Biochemical £xygen Demand
            T5-day - Unless stated otherwise)
CDT         Clarifier Detention Time
            THOUTS based on TFL)

GET         Clarifier Effluent Turbidity
            Tin JTO)

CFI         Clarifier Flow - Influent
            ITFL  - XMF in MGD)

CFO         Clarifier Flow - Out
            TCFI  - CSF in MOD)

CMC         Clarifier Mean Sludge Concentration
            TATC  + Rscj
            (     2    )

CSA         Clarifier Surface Area
            TSquare Feet)
CSD         Clarifier Sludge Flow Demand
CSF         Clarifier Sludge Flow ~"
            TRSF  + XRF in
 CSP         Clarifier Sludge Flow Percent
            TRSF + XRF as a % of CFI)

 CSU         Clarifier Sludge Units
            Tin sludge blanket)

 CVF         Clarifier Volume
            Tcubic Feet)

 CVG         Clarifier Volume (Gallons)

 CWD         Clarifier Mean Water Depth (Feet)

-------
                              B-3
DOB         Depth Of Sludge Blanket
            "(Feet from Water Surface)
ESU         Final Effluent Sludge Units
            (Total~Suspended Solids lost in
             Final Effluent - expressed as SLU)
FEC         Final Effluent Concentration
            ^Suspended Solids converted to
             by Centrifuge)

FET         Final Effluent Turbidity (J1U)

FLI         Raw Flow - Into Plant (MGD)

FLO         Effluent Flow - Out of Plant
JTU         Jackson Turbidity Units
LOD         Load (Lbs. BOD/Day to Aerator)

Lod         Load (jng/1 BOD to Aerator)
MLTSS       Mixed Liquor Total
            Suspended Solids (mg/l)

MLVSS       Mixed Liquor Volatile
            Suspended Solids (mg/l)

-------
OFR         Clarifier Overflow Rate
            (Gal./Sq. Ft./Day based on CFO)

OIX         Oxidation Index
            "(Based on Optimum SSV)
PET         Primary Effluent Turbidity
            TJTU)

PFI         Primary Flow Into Primary Sedimentation Tank (MGD)

PFO         Primary Flow Out of Primary Sedimentation Tank (MOD)

PSF         Primary Sludge Flow (MOD)
RFD         Return Sludge Flow Demand (MOD)

RFP         Return Sludge Flow Percentage
                 as a % of AFI   by meter)
RSC         Return Sludge Concentration
            T# by Centrifuge)

RSF         Return Sludge Flow (MGD)

RSP         Return Sludge Percentage
            T# of AFI - Usually calculated
             from ATC and RSC)

RSTSS       Return Sludge Total Suspended Solids (mg/l)

RSU         Return Sludge Units (To aerators)

RSVSS       Return Sludge Volatile Suspended Solids (mg/l)

-------
                               B-5

SAH         Sludge Aerator Hours (Hours per day in aerator)

SAP         Sludge Aerator Hours iu Percent of Day
            "(Either % or decimal fraction)

SCO         Settled Sludge Concentration - ttt Optiiuuci
            (Optimum SSC - ^ by Centrifuge)
SCR         Sludge Concentration Ratio  (SSC/R3C)
SCY         Sludge Cycles  (per day)

SDR         Solids Distribution Ratio
            "(Between aerators and clarifierc -- ASU/CSli)

SDT         Sludge Detention Time
                   in clarifiers)
SIB         Sludge Ratio  (RSC/ATC)

SIU         Sludge Units
            "(Volume  in gallons  x %  concentration
             as a decimal fraction)

SSC         Settled  Sludge  Concentration
            Tcalculated $ by Centrifuge)

SSV         Settled  Sludge  Volume
            Tcc/1 in Settleometer )

SVO         Settled  Sludge  Volume at  Optimum
            tcc/1 in Settleometer)
 TDT         Total Sludge  Detention Time
             TADT + SDT in Hours)

 TFI         Thickner Flow Into (MOD)

 TFL         Total Flow
                  out of aeration  tanks)
TFO          Thickener Flow Out (MGD)

             ^n^ Ratio  (AVG/CVG)

-------
                             B-6


TSF         Thickener Sludge Flow (MGD)

TSS         Total Suspended Solids (MQ/i)

TSU         Total Sludge Units
            TASU + csu)

TXU         Total Excess Sludge Units So Waste
            TXSU + ESU)
XFP         Excess Sludge Flow (As Percent  of Sewage Flow)

XMF         Excess Mixed Liquor Sludge Flow To Waste  (MGD)

XRF         Excess Return Sludge Flow To Waste (MGD)

XSF         Total Excess Sludge Flow To Waste (MGD)

XSU         Excess Sludge Units To Waste

-------
           APPENDIX C
OPERATIONAL CONTROL TREND  CHARTS

-------
                                                C-l

                                     SETTLED SLUDGE VOLUME - SS\?
   M
1/2U/72

-------
                                                C-2

                                  SETTLED SLUDCE CONCENTRATION - SSC
   M
1/2U/72
   M
1/31/72
  M
2/7/72
   M
2/1U/72
   M
2/21/7

-------
                                                     C-3


                                            FINAL EFFLUENT TURBIDITY
  00

  80
  70

  60
= 30
K
-3


v20


o

00
Q£
=>
j  5

I  H
         M
      1/2U/72
   M
1/31/72
  M
1/7/72
   M
2/1U/72
   M
2/21/72

-------
                                      EXCESS SLUDCZ UNITS WASTED/EAY - XSU/t&Y
 0.09
 0.08
 0.07
 0.06
 0.05

 O.OI»

 0.03
 0.02-
 0.01
0.009
0.008
0.007
0.006
0.005

O.OOl*

0.003-


0.002-
                                             Zttto
                                                         Z&O.O
                                            ZEKO
                                         Zeoo
           M
        1/2U/72
   M
1/31/72
   M
2/7/72
   M
2/1U/72
   M
2/21/72

-------
                                                  , C-5

                                            BLANKET THICKNESS-ELT
  0.8
  0.7 •
  0.6 -
  0.5 •

  O.J» -

  0.3 -


  0.2 -
zO.l •
£0.09
* 0.08
£0.07
 H0.06
""0.05
OQ
  0.01*
  0.03-
  0.02-
                                                                            	1	
                                                                               M
                                                                            2/U/72
—r
   M
 2/21/72
   M
1/2U/72
   M
1/31/72
  M
2/7/72

-------
                                                            C-6
                                                 SLUDGE DETENTION TIME - SDT
   9.0
   8.0
   7.0
   6,0

   5.0

   U.O

   3.0
CO
C£.
   2.0
o 1.0
K .9
£ .8
K .7
o .6
tit r

I in
_J
to
i   3

B '
   .2  -
           M
         1/2U/72
   M
1/31/72
 M
2/7/72
   M
2/1U/72
  M
2/21/7

-------
                                                           C-7
                  SSV CURVE'S ~ HfcSD
                                                             SSC  CUEVES ~ HESD
       tooo
c
In
O
                                      '/fe/72 - 1200

                                         FAST-
10   !•>  20  W  -90

    SST- SLUDC^fc
                                         40
                                                        60
                                            TIME-
10   («>  20  25  30      40       50
   SST~ sc.uoc,cr serr«-i>iQ TIME-

-------