EVALUATION OF PARTICULATE MATTER




CONTROL EQUIPMENT FOR COPPER SMELTERS

              PEDCo ENVIRONMENTAL

-------
                                 PEDCo ENVIRONMENTAL
                                                 11499 CHESTER ROAD
                                              CINCINNATI, OHIO 45246
                                                      (513) 782-47OO
                  EVALUATION OF PARTICULATE MATTER

                CONTROL EQUIPMENT FOR COPPER SMELTERS
                             Prepared by

                      PEDCo Environmental, Inc,
                         11499 Chester Road
                       Cincinnati, Ohio  45246
                       Contract No. 68-01-4147
                             Task No. 24
                  EPA Task Manager:  Larry Bowerman
                            Prepared for

               U.S.  ENVIRONMENTAL PROTECTION AGENCY
                        Enforcement Division
                              Region IX
                         215 Freemont Street
                 San Francisco,  California  94105

                            February 1978
                                 BRANCH OFFICES
CHESTER TOWERS
                          Crown Center
                          Kansas City. Mo
Professional Village
 Chapel Hill. Nl-C

-------
This report was furnished to the U.S.  Environmental Protec-
tion Agency by PEDCo Environmental, Inc.,  Cincinnati, Ohio,
under Contract No. 68-01-4147, Task No. 24.  Its contents
are reproduced herein as received from the contractor.  The
opinions, findings, and conclusions expressed are those of
the contractor and not necessarily those of the U.S. Environ-
mental Protection Agency.
                              11

-------
                       ACKNOWLEDGMENT

     This interim report was prepared under the direction of
Mr. Timothy W. Devitt.  Mr. Lario Yerino was the Project
Manager and Mr. Vishnu S. Katari was the Assistant Project
Manager.  Messrs. Vishnu S. Katari and Edmund S. Schindler
were the principal investigators of this report.  Task
Manager for the U.S. Environmental Protection Agency was Mr.
Larry Bowerman.
     EPA personnel at several locations were most helpful in
arranging for background information and reports of test
data.  The authors especially appreciate the contributions
of Messrs. Larry Bowerman, and Frank L. Bunyard.  Also, the
contributions of Mr. S. Orem and members of the IGCI com-
mittee are gratefully acknowledged.
                             111

-------
                      TABLE OF CONTENTS


                                                       gage

SUMMARY                                                X

1.0  INTRODUCTION                                      1-1

2.0  PLANT AND PROCESS DESCRIPTIONS                    2-1

     2.1  Magma Copper Smelter - San Manuel,           2-1
          Arizona
     2.2  Phelps Dodge Copper Smelter - Ajo,           2-7
          Arizona

3.0  EMISSIONS AND CONTROLS                            3-1

     3.1  Analysis of Electrostatic Precipitator       3-1
          Performance Data on Reverberatory Furnace
          at Magma Copper Company, San Manuel,
          Arizona
     3.2  Analysis of Electrostatic Precipitator       3-10
          Performance Data on Reverberatory Furnace
          at Phelps Dodge Corporation, Ajo, Arizona

4.0  ADD-ON CONTROL SYSTEM FOR PARTICULATE EMISSIONS   4-1

     4.1  Add-On Control Systems for Magma             4-6
          Copper Company, San Manuel, Arizona
     4.2  Add-On Control Systems for Phelps            4-30
          Dodge Corporation, Ajo, Arizona

APPENDIX A - Conversion Factors                        A-l

APPENDIX B - Technical Specification for Add-On        B-l
             Control Systems for Reverberatory
             Furnace at Magma Copper Company,
             San Manuel, Arizona

APPENDIX C - Technical Specifications for Add-On       c-1
             Control Systems for Reverberatory
             Furnace at Phelps Dodge Corporation
             Ajo, Arizona

APPENDIX D - New Source Performance Standards  for      Q_^
             Primary Copper Smelters and EPA Process
             Weight Regulation

APPENDIX E - Trip Report - Visit to Magma Copper       E-i
             Company San Manuel,  Arizona on 7/22/77
                              IV

-------
                       LIST OF FIGURES
No.

2-1  Simplified process flow diagram of Magma Copper   2-2
     Company plant, San Manuel, Arizona

2-2  Process flow diagram for Phelps Dodge Corpora-    2-11
     tion plant, Ajo, Arizona

3-1  Average inlet and outlet particle size distribu-  3-33
     tions, particle size vs. cumulative percent, for
     the ESP at the Phelps Dodge smelter

3-2  Measured and theoretical fractional efficiency    3-34
     curves prepared by SRI for the ESP on the re-
     verberatory furnace at Phelps Dodge Corporation
                              v

-------
                       LIST OF TABLES
No.                                                    Paqe
1     Capital and annual operating costs for add-on    xi
      control systems on Magma Copper smelter

2     Capital and annual operating costs for add-on    xii
      control systems on Phelps Dodge smelter

2-1   Smelter process equipment and operating data     2-3
      for Magma Copper Company, San Manuel, Arizona

2-2   Reverberatory furnace air pollution control      2-4
      equipment and operating data, Magma Copper
      Company - San Manuel, Arizona

2-3   Chronology of enforcement actions - Magma        2-8
      Copper Company, San Manuel, Arizona

2-4   Smelter process equipment and operating data     2-12
      - Phelps Dodge Corporation, Ajo, Arizona

2-5   Reverberatory furnace air pollution control      2-13
      equipment and operating data, Phelps Dodge
      Corporation - Ajo, Arizona

2-6   Chronology of enforcement actions - Phelps       2-18
      Dodge Copper Company, Ajo, Arizona

3-1   Summary of particulate emission data for         3-2
      electrostatic precipitator on reverberatory
      furnace - Magma Copper Company, San Manuel,
      Arizona

3-2   Particulate emission data                        3_5

3-3   Analysis of metallic elements in gas sample      3-6
      run 2

3-4   Sulfur dioxide emissions                         3-7
                              VI

-------
                 LIST OF TABLES (continued)
No.                                                    Page

3-5   Summary of particulate emission data for         3-11
      electrostatic precipitator in reverberatory
      furnace - Phelps Dodge Copper smelter, Ajo,
      Arizona

3-6   Summary of the sampling effort (July 7 through   3-14
      July 16, 1976) by radian

3-7   Instack vs. outstack particulate loading         3-18
      Phelps Dodge Corporation, Ajo, Arizona

3-8   Analyses of total particulate and vapor          3-21
      phase particulate in flue gas at ESP inlet
      or outlet  (by Radian Corporation)

3-9   Element flow rates in the feed and discharge     3-22
      streams of reverberatory furnace

3-10  Summary of sampling times - reverberatory ESP    3-25

3-11  Total solid input to the reverberatory furnace   3-27
      during shift "A" (8-hr period) on July 26,
      1976 (estimated by the Phelps Dodge staff)

3-12  Summary of sampling data using EPA methods 3     3-28
      and 4 - Phelps Dodge reverberatory furnace ESP

3-13  Summary of particulate, S03/H2SO4 and S02        3-29
      emission data for reverberatory furnace ESP

3-14  Test results - sulfur oxide concentration        3-36

4-1   Design parameters of add-on control fabric       4-8
      filter system for Magma Copper smelter

4-2   Capital cost data for add-on control fabric      4-10
      filter system for Magma Copper smelter

4-3   Annual operating cost data for add-on fabric     4-11
      filter for Magma Copper smelter

4-4   Add-on control scrubber system design para-      4-13
      meter for Magma Copper smelter
                               VII

-------
                 LIST OF TABLES (continued)
No.                                                    Pagt?

4-5   Capital cost data for add-on control scrubber    4-17
      system for Magma Copper smelter

4-6   Annual operating cost data for add-on control    4-19
      scrubber for Magma Copper smelter

4-7   Design parameters of add-on dry electrostatic    4-22
      precipitator system for Magma Copper smelter

4-8   Capital cost data for add-on dry electrostatic   4-23
      precipitator system for Magma Copper smelter

4-9   Annual operating cost data for add-on control    4-24
      dry electrostatic precipitator for Magma
      Copper smelter

4-10  Add-on control wet electrostatic precipitator    4-26
      system design parameters for Magma Copper
      smelter

4-11  Capital cost data for add-on wet electrostatic   4-28
      precipitator system for Magma Copper smelter

4-12  Annual operating cost data for add-on wet        4-29
      electrostatic precipitator for Magma Copper
      smelter

4-13  Design parameters of an add-on fabric filter     4-32
      system for the Phelps Dodge Corporation
      smelter in Ajo, Arizona

4-14  Capital cost data for add-on control fabric      4-35
      filter system for Phelps Dodge Corporation
      smelter

4-15  Annual operating cost data for add-on control    4-37
      fabric filter for Phelps Dodge Corporation
      smelter

4-16  Design parameters of add-on scrubber system      4-40
      for Phelps Dodge Corporation smelter
                             Vlll

-------
                 LIST OF TABLES (continued)
No.                                                    Page

4-17  Capital cost data for an add-on scrubber         4-43
      system for Phelps Dodge Corporation smelter

4-18  Annual operating cost data for add-on scrubber   4-44
      for Phelps Dodge Corporation smelter

4-19  Design parameters for add-on dry electrostatic   4-46
      precipitator for Phelps Dodge Corporation
      smelter

4-20  Capital cost data for add-on dry electrostatic   4-48
      precipitator system for Phelps Dodge Corpora-
      tion smelter

4-21  Annual operating cost data for add-on control    4-49
      dry electrostatic precipitator for Phelps
      Dodge Corporation smelter

4-22  Design parameters of an add-on control wet       4-51
      electrostatic precipitator system for the
      Phelps Dodge Corporation smelter

4-23  Capital cost data for an add-on wet electro-     4-55
      static precipitator system for Phelps Dodge
      Corporation smelter

4-24  Annual operating cost data for Add-on control    4-57
      wet electrostatic precipitator for Phelps
      Dodge Corporation smelter
                              IX

-------
                           SUMMARY

     The Magma Company smelter at San Manuel, Arizona, and
the Phelps Dodge smelter at Ajo, Arizona, are not in com-
pliance with the EPA Process Weight Regulation 40 CFR
52.126(b), according to EPA Test Method 5.
     Substantial technology was available to the copper
industry in 1973 to comply with EPA Process Weight Regulation
40 CFR 52 126(b).  It is possible for these smelters to
achieve compliance with this regulation by applying control
technology that is presently available.  The following add-
on control systems could be installed in series with the
existing ESP's at the subject smelters:
     1.   Gas cooling equipment to reduce flue gas tempera-
          ture to 120°C (250°F) and a dry ESP to reduce the
          flue gas dust loading to an allowable level;
     2.   Gas cooling equipment to reduce flue gas tempera-
          ture to 120°C (250°F) and a wet ESP to reduce the
          flue gas dust loading to an allowable level;
     3.   Gas cooling equipment to reduce flue gas tempera-
          ture to 120°C (250°F) and a fabric filter to
          reduce the flue gas dust loading to an allowable
          level;
     4.   Gas cooling equipment to reduce flue gas tempera-
          ture and a wet scrubber system to reduce the flue
          gas dust loading to an allowable level.
     Tables 1 and 2 present estimated capital costs and
annual operating costs of the add-on control systems for
Magma Copper Company and Phelps Dodge Corporation, respectively.
Magma Copper's add-on control system costs are based on
                              x

-------
X
H-
                           Table  1.  CAPITAL AND ANNUAL OPERATING COSTS FOR ADD-ON


                                    CONTROL SYSTEMS  ON MAGMA  COPPER SMELTER
System Description
1
1)
2)
3)
4)
5)
6)
7)
8)
9)
Spray water cooling of gas to 120°C (250°F) ,
fabric filter followed by a fan
Air dilution of gas to 120°C (250°F), fabric
filter followed by a fan
Two units, each containing a quencher, an
adjustable venturi, a flooded elbow, and
a mist eliminator followed by two fans
Two units, each with a fan and a separate
quencher followed by a venturi scrubber
One unit scrubber system consisting of
a prequench section, a venturi, and a
separator section followed by a fan
Two parallel systems, each containing
a fan, a cooling system, and an ESP
Two parallel systems each containing
a fan, a cooling system, and an ESP
Two parallel systems each containing
a fan, a cooling system, and an ESP
Two parallel systems consisting of a fan,
an evaporative cooling tower, and a NEP
Evalu-
ation
A
B
C
D
E
F
G
H
I
Turnkey Capital
Cost, $
6,168,300
15,607, 000
4 ,824, 100
3,986,000
5,090,000
6,665,500
8,441,200
7,378,900
6,990,400
Annual Operating
Cost,3 $
1,845,700
4,468,000
4,466,100
2,762,800
1,685,500
1,604,000
2,072,900
1,633,500
2,147,100
             a) Includes operating cost and fixed capital charges.

-------
X
H-
M-
                           Table 2.  CAPITAL AND ANNUAL OPERATING COSTS FOR ADD-ON


                                    CONTROL SYSTEMS ON PHELPS DODGE  SMELTER
System Description
1
1)
2)
3)
4)
5)
6)
7)
8)
9)
Spray water cooling of gas to 120°C (250°F) ,
fabric filter followed by a fan
Air dilution of gas to 120°C (250°F) , fabric
filter followed by a fan
An adjustable throat venturi, a flood elbow,
and an entrainment separator, followed by
a fan
A prequencher, an adjustable-throat venturi
scrubber, and a separator section followed
by a fan
A prequencher, an adjustable-throat venturi
scrubber, and a separator section followed
by a fan
A fan, an evaporative cooling tower to cool
gas to 120°C (250°F) , followed by a dry ESP
A fan, a combination of heat exchanger and
dilution air to cool gas to 120°C (250°F)
and two dry ESP's in parallel
A fan, a spray water tower to cool gas to
120°C (250°F) and a dry ESP
A fan, an evaporative cooling tower
followed by a WEP
Evalu-
ation
J
K
L
M
N
P
Q
R
S
Turnkey Capital
Cost, $
2,003,200
3,960,800
724,300
842,800
2,056,800
1,933,800
2,452,400
1,734,700
2,023,400
Annual Operating
Cost,3 $
586,600
1,062,700
878,600
914,000
745,400
621,000
626,900
429,400
564,500
           a)  Includes operating cost and fixed capital charges.

-------
electrostatic precipitator outlet gas flow conditions of
18,264 m /min (645,000 acfm) at 300°C (573°F) and an average
of 1.76 g/m   (0.77 gr/scf) and a maximum of 2.86 g/m  (1.25
gr/scf) particulate content measured at 120°C (250°F). The
system is sized for a minimum of 98.2 percent control
efficiency.  The Phelps Dodge add-on control system costs

                                                          3
are based on outlet gas flow conditions of 5270 m /min
(186,000 acfm) at 314°C  (598°F) and an average of 1.28 g/m'
(0.56 gr/scf) and a maximum of 3.14 g/m  (1.37 gr/scf)
particulate content measured at 120°C  (250°F).  This system
is sized for a minimum of 93.0 percent control efficiency.
     The following conclusions are based on a review of the
information available on particulate testing on the rever-
beratory furnace control systems at the Phelps Dodge Copper
Company, Ajo, Arizona, and Magma Copper Company, San Manuel,
Arizona.
Magma Copper Company, San Manuel
     NEIC tested emissions from the reverberatory furnace
stacks for particulate compliance; they also did some ancillary
testing to evaluate the effect of temperature on particulate
formation.  Prior to NEIC testing, Magma also tested emis-
sions from the reverberatory furnace stack.  However, since
proper isokinetic conditions were not maintained during the
company testing, these test results cannot be considered
valid.
     The following is a brief summary of NEIC test results:
     1.    Three compliance test measurements by NEIC on May
          14 to May 22, 1976, indicate that the reverberatory
          furnaces emitted an average of 989 kg/hr (2180
          Ib/hr) of particulate, which is over 50 times the
          allowable 18 kg/hr (39.7 Ib/hr) for the observed
          process weight rates.  Data are not available on
          ESP dust collection during the testing; however,
          company data show an average of 113.4 metric tons
          (125 tons)  per day were being recycled from both
          the reverberatory and converter electrostatic
                              Xlll

-------
     precipitators to the reverberatory  furnaces.   Th3
     indicates that the electrostatic  precipitator
     efficiency,  measured according  to EPA Method  5,  i
     lower than the design efficiency, which is  based
     f"i n 7± C MT? -4-^-**-«4- «* A j_ i	3
2.    Stack volume flow rates are about 15 percent
     higher than volume flow design of the electro-
     static precipitator.

3.    Average sulfur dioxide and sulfur trioxide emis-
     sions during compliance testing were 5400 ppm
     (8083 kg/hr or 17,820 Ib/hr) and 15.0 ppm (30
     kg/hr or 66.1 Ib/hr), respectively.  The measured
     sulfur dioxide and sulfur trioxide emissions
     during ancillary testing were 2600 to 5000 ppm and
     31 to 93 ppm, respectively.

4.    During the compliance tests with an  inert glass
     probe liner, no sulfates were found  in  the  filter
     or acetone catches.  However, ancillary tests
     showed that particulate sulfate  appears to  be
     formed as the reverberatory furnace  gases pass
     through the instack  filter and glass frit support
     (a considerable amount of sulfate was deposited on
     the outstack filter).  Measured  values  of moisture
     content in the gas averaged 8 percent.   Because of
     the 8 percent average moisture content  of the
     gases, NEIC believes that most of the sulfur
     trioxide would be in the form of sulfuric acid
     mist  (H2SO4) at a temperature of (120°  + 14°C)
     (248° + 25°F).  However, it is possible that  some
     or all of the sulfuric acid would be in the gaseous
     form rather than the liquid  (mist)  form.

5.   No data are available on metallic elements  in the
     gases other than one measured analysis  at the ESP
     outlet.  Copper, arsenic, and zinc  were the
     principal elements detected in the  analysis of the
     reverberatory furnace stack gas.

6.   Most of the arsenic was collected on the filter
     during the compliance tests.  The amount collected
     in the impinger was negligible.
                        xiv

-------
Phelps Dodge Copper Company, Ajo

     Radian Corporation, Southern Research Institute, and

Aerotherm Corporation conducted the testing.  The following

is a brief summary of the results:

     1.   Particulate matter in the gases released from the
          furnace is very cohesive and hygroscopic.

     2.   Apparently, chemical composition differs with par-
          ticulate size.  The ESP inlet and outlet particu-
          late size distribution is bimodal.  The mass
          median diameter of the inlet particle size distri-
          bution was greater than 10 urn.  One component of
          the bimodal inlet particulate distribution had a
          mass median diameter less than 1 pm.

     3.   The ESP may be handling volumes more than 10
          percent over design rate.

     4.   It may be necessary to find out how loadings vary
          as a function of furnace operation cycle.  Three
          test runs by Radian Corporation on July 15, 1976,
          using an instack/outstack filter train determined
          a particulate emission rate of 323 kg/hr (712
          lb)/hr at the ESP outlet.  However, two test
          measurements by Aerotherm on July 29 and 30, 1976,
          determined the particulate emission rate at the
          ESP outlet to be 192.1 kg/hr  (423.5 Ib/hr).
          Approximately the same amount of input material
          was charged to the furnace during these tests.

     5.   The difference in dust loadings in the gas through
          the two parallel inlet ducts leading to the ESP is
          significant according to several measurements by
          Radian Corporation.  Both Radian Corporation and
          SRI reached the conclusion that gas velocity
          distribution is good.

     6.   Only Aerotherm Corporation particulate sampling
          test results are based on EPA Test Method 5.  The
          average of seven particulate emission measurements
          on the ESP outlet was 129.5 kg/hr (285.4 Ib/hr)
          (extrapolated weight)  and the corresponding
          allowable emission rate was 14.2 kg/hr (31.2
          Ib/hr).  Therefore, compliance with the EPA par-
          ticulate emission regulation requires the instal-
          lation of an additional control system with an
                             xv

-------
     89.07 percent efficiency  [measured at 120°C
      (250°F)]  in  series with the existing ESP  [designed
     to operate at 98.8 percent efficiency at  316°C
      (600°F)] .

7.   During  the three tests by Radian  Corporation, the
     particulate  collection on the  outstack  filter at
     120°C  (250°F) was about 96.0 percent of the  total
     collected by the instack/outstack train.   However,
     the corresponding measurements in two runs by
     Aerotherm determined  that only 50 percent of the
     total particulate is  collected on the outstack
     filter  of the instack/outstack filter train. This
     difference could be due to the fact that Aerotherm
     included the probe wash with  "instack particulate,"
     whereas Radian  included the probe wash  with
      "outstack" particulate.  The Radian definition  is
     the most logical.

8.    It is not clearly explained why consistently
     higher  amounts  of particulate  are collected  using
      instack/outstack filter train  than using only an
     outstack filter according to EPA  Method 5.  An
     average of 129.5 kg/hr  (285.4  Ib/hr) particulate
     was measured during seven test runs using EPA
      Method  5, and an average of 192.2 kg/hr (423.8
      Ib/hr)  particulate was measured during  two test
      runs  by Aerotherm using instack/outstack filter
      train.

 9.    Arsenic in the  gas is present  as  arsenolite.

10.    Nearly  all of the arsenic, 50  percent of the
      selenium, and 30 percent of fluorine are dis-
      charged together with the reverberatory furnace
      off-gases.   Arsenic and selenium  escaping the
      electrostatic precipitator are partly in the vapor
      state,  and nearly all of the  fluorine escapes in
      a gaseous state.  Radian tests on an ESP inlet  and
      outlet  wet electrostatic precipitator showed that
      only  about 28 percent of arsenic  measured at
      atmospheric  temperature is collected by the  exist-
      ing ESP. Almost all  the arsenic  collected in the
      ESP at  the outlet was present  as  condensed mate-
      rial.   Arsenic  measurements by Radian at 120°C
      (250°F), using  EPA Method 5, also showed the
      efficiency of the existing ESP for arsenic to be
      about 28 percent.
                         xvi

-------
11.   Measurement of particulate collection efficiency
      of waste-heat boilers will help to define emission
      characteristics of copper reverberatory furnace
      gases.  According to Radian Corporation measure-
      ments of the total 86.2 kg/hr (190 Ib/hr) of
      arsenic entering the furnace, about 0.73 kg/hr
      (1.6 Ib/hr) is present in matte, 0.86 kg/hr (1.9
      Ib/hr) in slag, 34.5 kg/hr (76 Ib/hr) in the ESP
      outlet, and 13.6 kg/hr (30 Ib/hr)  in ESP hopper.
      Another test measurement showed 63.5 kg/hr (140
      Ib/hr) arsenic in the ESP off gases.  That means
      about 8 to 40 percent of the total arsenic in the
      furnace gases may be precipitating in the waste-
      heat boilers and flue leading to the ESP.
                        xvii

-------
                      1.0  INTRODUCTION


     As a result of Petitions for Review filed by the Magma

Copper Company and Phelps Dodge Corporation, the Enforcement
Division of Region IX of the U.S. Environmental Protection

Agency (EPA) is coordinating a study of copper smelters in

the region.  The purpose of this study is to review and

analyze the basis for and the reasonableness of the EPA
Process Weight Regulation  [40 CFR 52-126(b)] as it applies
to the Magma smelter in San Manuel, Arizona; to the Phelps
Dodge copper smelter in Ajo, Arizona; and generally to all

copper smelters in Region IX.
     EPA Region IX provided us with the following documents

which contain emission data of existing control systems on
the smelters at Magma Copper Company and at Phelps Dodge

Corporation:

     1.   National Enforcement Investigations Center and
          Region IX.  Emission Testing at the Magma Copper
          Company Smelter, San Manuel, Arizona, May 12-22,
          1976.  EPA-330/2-76-029, U.S. Environmental Pro-
          tection Agency, August 1976.

     2.   National Enforcement Investigations Center.
          Ancillary Tests at Magma Copper Company Smelter,
          San Manuel, Arizona, conducted on May 14-18, 1976.

     3.   Chronology of Enforcement Actions by EPA on Magma
          Copper Company, San Manuel, Arizona.

     4.   Environmental Protection Agency.   State Imple-
          mentation Plan Inspection of Phelps Dodge Cor-
          poration New Cornelia Branch Smelter, Ajo, Arizona,
          May 1976.
                             1-1

-------
     5.    Radian Corporation.   Trace  Element  Study Around
          the  Reverberatory Furnace and the Electrostatic
          Precipitator  of  a Primary Copper Smelter  (Pre-
          liminary draft).   EPA Contract 68-01-4136,  U.S.
          Environmental Protection Agency, Cincinnati,  Ohio,
          May  9, 1977.

     6.    Acurex Corporation/Acrotherm Division.   Stack test
          results at Phelps Dodge Corporation,  Ajo,  Arizona.
          EPA-68-01-3158,  U.S.  Environmental  Protection
          Agency, Region IX, San Francisco,  California
          94111, March  1977.

     7.    Chronology of Enforcement Actions  by EPA on Phelps
          Dodge Corporation, Ajo, Arizona.

     8.    Southern Research Institute.  Performance Evaluation
          of an Electrostatic Precipitator  Installed on a
          Copper Reverberatory Furnace.  EPA Order No.  CA-6-
          99-2980-J, U.S.  Environmental Protection Agency,
          IERL, Cincinnati, Ohio, January 14, 1977.

     From time to time  EPA Region IX  also supplied additional

information as requested.
     It should be noted that many of  these documents contain

data on tests  conducted for compliance purposes,  and they
lack information on conditions at the inlet  of the smelter

control systems.  These data can be used to  evaluate addi-
tional control requirements for the smelters' compliance

with the process weight regulation.  They are,  however,

insufficient to determine any new control system alternatives
for smelter compliance.

     Based on available information of the process weight

rates to the reverberatory furnace, the allowable emission

rates have been determined by the process weight regulation
40 CFR 52.126(b) for the Magma Copper Company and Phelps

Dodge Corporation.  Using emission test data  on the existing

control system exit and on the allowable emission rate, the

required additional control efficiency has been estimated.
                              1-2

-------
After discussing available emission test data with members
of the Industrial Gas Cleaning Institute (IGCI), it was
decided to evaluate dry and wet electrostatic precipitators,
fabric filters, and wet scrubbers as an add-on control
system for each smelter.  The process weight regulation
requires the flue gas particulate content to be measured at
about 120°C  (250°F).  When the flue gas temperature is
reduced from a higher temperature to about 120°C (250°F) ,
its particulate matter consists of material that has con-
densed from the vapor phase to the solid phase.  For these
reasons it was also decided to cool the gas from the existing
control system to 120°C (250°F) before treating it in an
additional system.
     Specifications for each add-on control system on
individual smelters were prepared on the basis of emission
data from available reports.  The data included such informa-
tion on inlet conditions as gas volume flow rate, temperature,
moisture content, gas composition, and particulate size
analysis, as well as the required control efficiency and the
allowable emission rates.   The specifications were sent to
selected IGCI members with a request for capital and annual
operating cost data and design data for the add-on controls.
These data were tabulated.
     PEDCo Environmental,  Inc., inspected the operation,
existing control equipment, and space available in the
vicinity of each smelter.
     Section 2.0 of the report describes the reverberatory
furnace process and control systems of the Magma and Phelps
Dodge copper smelters.  The section also presents the
chronology of EPA enforcement actions on these smelters.
     Section 3.0 summarizes emission test data obtained from
the available documents.
                              1-3

-------
     Section 4.0 presents evaluations of the different add-
on control systems designed for the compliance of the smelters
under discussion.  The evaluations cover two fabric filters,
three wet scrubbers, three dry electrostatic precipitators,
and one wet electrostatic precipitator for each smelter.
The evaluations present the design parameters, capital
costs, and annual operating costs for each system.  The
fabric filter costs include a gas cooling system, fabric
filter, necessary ductwork, and fan; the scrubber system
costs include a gas cooling system, scrubber, wet particulate
waste treatment equipment necessary duckwork, and fan; and
the dry and wet electrostatic precipitator costs include a
gas cooling system, precipitator, necessary ductwork, and
fan but do not include dry waste treatment  (or disposal)
equipment.
     Appendix A is a table for converting English into
metric units.  Appendix B and Appendix C contain the add-on
control system specifications for Magma Copper Company and
Phelps Dodge Corporation, respectively.  Appendix D contains
the New Source Performance Standards for Primary Copper
Smelters, the EPA Process Weight Regulation for existing
copper smelters in the Phoenix - Tucson Air Quality Control
Region, the EPA Test Methods 1-8 and the ASME "Test Code For
Determining The Dust Concentration in a Gas Stream."  Appen-
dix E contains memorandums on the PEDCo's trips to the Magma
Copper company and Phelps Dodge Corporation.
                              1-4

-------
             2.0  PLANT AND PROCESS DESCRIPTIONS

2.1  MAGMA COPPER SMELTER - SAN MANUEL, ARIZONA*
2.1.1  Plant Description
     The Magma Copper Company operates an underground mine,
concentrator, smelter, electrolytic refinery, and continuous
casting rod plant in the vicinity of San Manuel, Arizona.
Products include electrolytically refined copper, copper
rod, sulfuric acid, and molybdenum.  Average anode copper
production averages 613 to 635 metric tons (675 to 700 tons)
per day.
     Figure 2-1 is a simplified process flow diagram of the
Magma smelter.  Table 2-1 lists the major smelter process
equipment and operating data, and Table 2-2 describes and
provides operating data on the electrostatic precipitator
(ESP's) used for air pollution control.
     Concentrate is conveyed by belt from the concentrator
to storage bins above the three reverberatory furnaces at
the smelter.  Limerock is added to the concentrate in the
storage bins, and silica rock is stored in adjacent bins.
The concentrate and flux (limerock or silica rock) are moved
by belt conveyor from the storage bins to hoppers above and
adjacent to the side walls of the three reverberatory fur-
naces.  Charging doors are opened and the material is fed to
the reverberatory furnaces by gravity flow.
*
  This discussion is based mainly on information from Emis-
  sion Testing at the Magma Company Shelter, San Manuel,
  Arizona, by the National Enforcement Investigations Center,
  EPA-330/2-76-029.  May 2-22, 1976.  Figure 2-1 and Tables
  2-1 and 2-2 have been adopted from the EPA report with
  minor changes.
                             2-1

-------
                                                  EXHAUST
r~T"
WASTE HEATM H
BOILERS M M
EXHAUST
t
i CASTING WHEELS
^^V EXHAUST
10 ANODES TO ANODE *
y!S^ FURNACES
" (4) "
R
iVERBERATO
FURNACES
(3)

-{ ESP M }-*(£
REVERBERATORY
STACK
RY
CONVERTERS
(6)
1 \
HUMIDIFYING
  TOWER
                           HEAT
                         EXCHANGERS

                    CATALYST ^ABSORBING
                    CHAMBERS^iflTOWERS
                           r~*T\
                                                               DRYINGr
                                                               TOWERS •--
                                                       Ow
                                                         MIST
                                                         ESP
                                                         (6)
                                                                                  EXHAUST
                                                                                         ACID
                                                                                         PLANT
                             •Ur ^JT^sfACKS
.Annu
-------
     Table 2-1.  SMELTER PROCESS EQUIPMENT AND OPERATING DATA FOR
               MAGMA COPPER COMPANY, SAN MANUEL, ARIZONA
Parameter
Feed rate:

Concentrates
Flux
Converter slag
Matte
Flue dust
Total
Size of unit:
Width
Length
Height
Diameter
Gas volume gen-
erated at Std.
conditionsf :

Exit gas
temperature:
Reverberatory furnaces
metric
tons/day
2004
202
1089
-
NA
3295
meters
c
31
3.4

m /min

8200

260°C


tons/day
2208
222
1200
-
NA
3630
feet
c
102
11

cfm

289,500

500°F

Converters
metric
tons/day

251



1504
meters

10.7

d
m /min

3 at 690
3 at 1070
704°C


tons/day

276



1656
feet

35

d
cfm

3 at 24,500
3 at 37,700
1300°Fg

  Three units operating 720 to 744 hours per month.
  Six units operating an estimated 432 hours  (60% of 720) per
  month per converter.
° The respective widths of each of the three reverberatory
  furnaces are 9.8 m  (32 ft), 10.4 m  (34 ft), and 11.0 m  (36 ft).
  Three of the six converters are 4m  (13 ft) each in diameter,
  and the remaining are 4.6 m (15 ft) each.
e Undiluted maximum gas flow per converter.  Units do not
  usually operate simultaneously under peak flow conditions.
f Standard conditions are 760 mm Hg  (14.7 psia) and 21°C  (70°F).
" Maximum temperature reached during final copper blow.
                                  2-3

-------
Table 2-2.   REVERBERATORY  FURNACE AIR POLLUTION  CONTROL EQUIPMENT AND OPERATING

                  DATA,  MAGMA COPPER COMPANY  -  SAN  MANUEL, ARIZONA

Control
device
ESP




Manufacturer
Research-Cottrell



Date of
installation/
modification
1975



No. of
units
and stages
c
1-4 stages
<3
1-6 stages

Gas flow
rate, a
m /min
2730

5470
scfm
96,500

193,000

Operating
temp.
°C
260
to
354
op
500
to
670

Pressure
drop
cmb

0.9

inb

0.35


Collection
area
m
6780

13,540
ft*
72,900

145,800

Velocity
m/sec

1.1

ft/sec

3.57

Reten-
tion
time
sec

7.56

   Estimated gas flow through individual units  (Basis for estimate unknown).
   Water column.
 0 West unit.
   East unit.

-------
     On the inside, the three reverberatory furnaces are 31
m  (102 ft) long and 3.5 m  (11 ft) high.  The widths are 10,
10.5, and 11 m  (32, 34, and 36 ft) for Furnaces 1, 2, and 3,
respectively.  Although normally fired with natural gas,
fuel oil is used when gas delivery is interrupted.  Work is
currently underway to convert to coal firing.
     The reverberatory furnace walls are made of basic
brick.  At the slag line, 76 copper water jackets 0.6 m (2
ft) high by 1.5 m  (5 ft) long nearly surround three sides of
the furnaces.  The suspended-arch roof also is constructed
of basic brick.  The walls and arch are maintained by re-
placing brick; no hot patching is used.
     Although the depth of molten material actually varies
among the three furnaces, normal slag depth is approximately
102 cm (40 in.) and normal matte depth is approximately 38
cm  (15 in.).  Slag is tapped near one end of each furnace
and flows through a launder into slag pots, which are hauled
by rail to the slag dump.  Matte is tapped nearer the center
of the furnaces, depending on converter or reverberatory
furnace conditions, and carried in a launder one floor below
the furnaces.  The matte drops by gravity off the launder
into ladles resting on a pallet, which is moved into the
converter aisle by an electric winch and cable unit.
     The matte ladles are picked up by an overhead crane and
charged to one of six Peirce-Smith converters.  Converters
1, 2, and 3 are 4 by 11 m  (13 by 35 ft), and Converters 4,
5, and 6 are 4.5 by 11 m (15 by 35 ft).  An initial charge
to a converter normally consists of two to four ladles of
matte.  Air is blown through tuyeres into the charge, flux
is added, and the slag produced is skimmed into a ladle.
The slag is then returned by overhead crane to one of the
                            2-5

-------
reverberatory furnaces.  Additional matte is added to the
converter until a total of approximately 65 metric tons  (70
tons) of blister copper is produced.
     The blister copper is poured into ladles, then carried
by overhead crane to one of four anode furnaces, two of
which are 4 by 9 m  (13 by 30 ft), and the other two, 4 by 11
m  (13 by 35 ft).  Additional air is blown through tuyeres
into the charge to assure complete oxidation.  Reformed
natural gas or propane is then introduced through the tuyeres
for final copper reduction.  The refined copper is cast  into
anodes of approximately 360 kg  (800 Ib) on either of two
casting wheels.  The anodes are cooled, inspected, and
transferred to the electrolytic refinery.
2.1.2  Emissions Sources and Reverberatory Furnace Control
       Equipment
     The primary particulate sources at the smelter are  the
reverberatory furnaces and the converters, the majority  of
whose exhaust gases are treated by control systems.  Fugitive
emissions from feeding concentrates, skimming converter
slag, or returning converter slag, however, are neither
collected nor treated; they are exhausted directly to the
atmosphere.  The reverberatory furnace matte and slag tap
areas are hooded, and collected gases containing particulate
matter are exhausted untreated directly to individual
stacks above the building.  Converter "smoke" not collected
by the primary hood system is likewise released directly to
the atmosphere.  The anode furnaces also emit some untreated
particulate matter directly to the atmosphere above the
converter aisle.
     The principal reverberatory furnace exhaust gases pass
through a pair of waste-heat boilers following each furnace.
The partially cooled gases are then combined into a common
                             2-6

-------
duct before entering the plenum chamber of two parallel
ESP units.  The unit called the "east ESP" is designed to
handle about two-thirds of the gas volume, and the other
called the "west ESP" is designed to handle one-third.
Shortly after installation, however, the perforation plates
between the plenum and the ESP units were removed because of
excessive plugging.  Assuming that gas flow distribution is
actually as designed, the east ESP handles 5470 m /min
(193,000 scfm), and the west ESP handles 2730 m3/min  (96,500
scfm), as shown in Table 2-2.  The east ESP consists of six
                                               2
stages with a total collection area of 13,540 m   (145,800
  2
ft ), whereas the west ESP consists of four stages with a
                               2           2
total collection area of 6780 m   (72,900 ft ).  Average gas
velocity is 1.1 m  (3.6 ft)/sec and retention time is less
than 8 sec.  The pressure drop across each ESP is 0.8 cm
(0.35 in.) H_0 maximum.  The exit gas stream is exhausted to
a 157-m  (515-ft) stack for discharge to the atmosphere.
2.1.3  Chronology of Enforcement Actions for Magma Copper
       Company at San Manuel, Arizona
     Table 2-3 presents a chronology of enforcement actions
by the EPA.
2.2  PHELPS DODGE COPPER SMELTER - AJO, ARIZONA*
2.2.1  Plant Description
     The New Cornelia Branch of the Phelps Dodge Corporation
operates a mine, concentrator, and smelter at Ajo, Arizona,
for the production of anode copper from a chalcopyrite
(copper-iron sulfide) concentrate.  During 1975, production
averaged 165 metric tons  (185 tons)/day.
*
  This discussion is based mainly on information from State
  Implementation Plan Inspection of Phelps Dodge Corporation,
  New Cornelia Branch Smelter, Ajo, Arizona, by the Environ-
  mental Protection Agency, May 1976.  Figure 2-2 and Tables
  2-3 and 2-4 have been adapted from the EPA report with
  minor changes.
                             2-7

-------
    Table 2-3.  CHRONOLOGY OF ENFORCEMENT ACTIONS -

       MAGMA COPPER COMPANY, SAN MANUEL, ARIZONA3
      Date
                Action
May 14, 1973
July 13, 1973
September -
 November, 1973

April 3, 1974
December 12, 1974


January 6, 1975


March 5, 1975

June 11, 1975



October, 1975




November 26, 1975



December 31, 1975
January 30, 1976
May 12-22, 1976
EPA promulgated process weight regula-
tion 40 CFR 52-126(b).

EPA notified company by letter of
process weight regulation requirements.

Company submitted proposed compliance
schedules.

EPA held public hearing in Phoenix on
proposed compliance schedule.

EPA approved compliance schedules for
converters and reverberatory furnaces.

Magma notified EPA of violations
of both compliance schedules.

EPA issued consent order to company.

Company submitted test results of
converter-side acid plant.  Compliance
demonstrated.

Company conducted tests in reverberatory
furnace stack, which showed emissions to
exceed allowable by a factor of 20 to
30.

Company filed Petition for Reconsidera-
tion and Revision of process weight
regulation (EPA).

Letter from P. DeFalco, Administrator of
Region IX, EPA, to H.A. Twitty, Attorney
for Magma Copper Company, stated that
Region IX would review the process weight
regulation.

National Enforcement Investigations Center
(NEIC), Office of Air Quality Planning
and Standards  (OAQPS), and Region IX
EPA personnel visited the smelter.

Smelter was tested by EPA and NEIC team.
  Provided by Larry Bowerman of EPA Region IX.

 (Continued)
                           2-8

-------
       Table 2-3. (continued)  CHRONOLOGY OF ENFORCEMENT

     ACTIONS - MAGMA COPPER COMPANY, SAN MANUEL, ARIZONA
   Date
            Action
March 28, 1977
May 18, 1977
R.L. O'Connell, Director of Enforcement
Division, EPA, sent letter pursuant to
Section 114 to Magma Copper Company, re-
questing further information about particu-
late removal systems installed for reverbera-
tory furnace gases.

Magma Copper Company responded to EPA letter
of March 28, 1977.
                             2-9

-------
     Figure 2-2 is a simplified process flow diagram for
this smelter.  Table 2-4 lists the major smelter process
equipment and operating data, and Table 2-5 lists the air
pollution control equipment and operating data.  Concentrate
is delivered by a belt conveyor, 61-cm  (24-in.) wide, from
the New Cornelia concentrator to the smelter, where it  is
dried in a rotary dryer fired either by natural gas  (when
available) or by diesel fuel.
     As it enters the smelter building, the belt-delivered
concentrate is mixed with limestone flux in predetermined
proportions, then bedded.  When available, dust from the
collectors is also added to the concentrate and crushed
limestone.  Concentrates from other copper concentrators
 (notably Tyrone, Bagdad, and Bruce) and copper precipitates
from the Phelps Dodge Tyrone operation are also bedded  as
available.
     The various materials to be smelted are put into 9-
metric-ton  (10-ton)  "cans," which are large cylindrical con-
tainers used to charge the reverberatory furnace.  The
filled can is moved  by an overhead crane either to storage
or  to one of six furnace-charging stations for a single
reverberatory furnace.
     The reverberatory furnace, which is 30 m  (100 ft)  long
and 9m  (30  ft) wide on the inside, is mounted on a heavily
reinforced concrete  foundation.  Although the furnace nor-
mally fires  natural  gas, it can run on fuel oil if gas
delivery is  interrupted.
     Reverberatory furnace walls are made of silica brick,
with an interior protective surface of basic brick and, in
the area of  the crucible, a mixture of tamped periclase and
firebrick.   The walls also include copper water jackets,  51
cm  (20 in.)  high, immediately above the crucible.  The
                              2-10

-------
                                                                                   SLAG
ANODES  TO
 REFINERY
    CASTING
     WHEEL
 ANODE
FURNACE
                               REFORMED
                                 GAS
                                                   CONCENTRATES
                   PRECIPITATES
                     LIMEROCK
                  OXIDIZING
                    FURNACE
                                            REVERBERATORY
                                               FURNACE
                                                                        MATTE
                                                                                       SLAG
                                                                           CONVERTERS  (3)
SILICA
                                                                                                 FLUX
                                                                                 AIR
        Figure  2-2.  Process flow diagram for Phelps Dodge Corporation  plant, Ajo,  Arizona.

-------
                Table 2-4.  SMELTER PROCESS EQUIPMENT AND OPERATING DATA -

                          PHELPS DODGE CORPORATION, AJO, ARIZONA
Parameter
     Reverberatory furnace
 Converters
Number of units

Feed rate:

  Concentrates /
  Precipitates(
  Limestone    (
  Reverts      j

  Converter slag


  Matte           1
  Flux (siliceous))
  Reverts         j

Size of unit:

  Width
  Height
  Length
  Diameter

Hours of operation/month

Gas volume generated


Exit gas temperature
      613 metric tons/day
         (676 tons/day)
      431 metric tons/day
         (475 tons/day)
        9.2 m  (30 ft)
        3.4 m  (11 ft)
       30.5 m  (100 ft)
              624

          220 m3/min
          (77,900 scfm)

        309°C (588°F)a
                                         725 metric tons/day
                                            (799 tons/day)
  9  m (30 ft)
  4  m (13 ft)

      522

  1100 m /min
(39,500 scfm)

340°C (6500F)1
  Per recorder following
  Per estimate following
waste-heat boilers.
waste-heat boilers.

-------
                   Table 2-5.   REVERSERATORY  FURNACE  AIR POLLUTION  CONTROL  EQUIPMENT  AND


                             OPERATING DATA,  PHELPS DODGE CORPATION -  AJO,  ARIZONA
Control
devicea
ESP

Scrub-
bersb-c



Liquid
S02 „
plant
Manufacturer
Western
Precipitator
(Type R)






Date of
installation/
modification
8/73

1/75



7/74
NO. Of
units
and stages
2
(with 2
stages
each)

1



1
Gas flow
rate,
m /min
2200
each
unit

700
to
1200



1100
scfra
77,900

25,000
to
43,000



38,500
Operating
temp. ,
°C
309
In
230
°F
588
let
450
Outlet
200
to
290
400
to
550
Inlet
52
to
66
125
to
150
Outlet
32
90
Pressure
drop, H2O
cm
1.3

3.8



Un)
in.
0.5

1.5



cnown
Collection
area,
m^
1927

1



1
ft'
20,738

,Ad



•1A
Velocity,
m/sec
0.9

N



N
ft/sec
3.0

i



V
Reten-
tion
time,
sec
6.6

NA



NA
I
\~>
Ul
              Scrubbers and  liquid S02 plant are noL operating at present.

              Only  includes  humidifying tower, not the cooling tower, preceding  liquid  SO,, plant.

              Design and construction by Stearns-Roger in collaboration with Monsanto;  no special type or model number designated.

              NA -  Not applicable.

              DMA process developed by ASARCO; engineering and construction by Stearns-Roger.

-------
reverberatory furnace roof is a sprung arch constructed of
silica brick.  The furnace walls and arch are maintained by
hot patching with silica slurry.
     The following procedure is followed in charging the
reverberatory furnace.  A container of concentrate is posi-
tioned at one of the six charging stations.  Then the bottom
gates of the container are opened, and the charge falls into
a small feed hopper of the charging machine (referred to as
a "slinger") immediately below.   (The slinger is a short,
high-speed, portable belt conveyor pivoted on a vertical
shaft to permit lateral swinging.)  The concentrate falls
from the feed hopper onto the rapidly moving belt and is
discharged into the furnace as it moves over the belt pul-
ley.  The usual charge is 1.8 to 3.6 metric tons (2 to 4
tons), fed at an average rate of approximately 0.9 metric
ton  (1 ton)/min.
     Normal depth of the molten material in the furnace is
approximately 120 cm  (46 in.), of which 66 to 76 cm (26 to
30 in.) is matte.  Slag is tapped through the side wall and
flows through a launder into slag pots, which are hauled by
rail to the slag dump.  Matte is tapped, as required by
converter or reverberatory furnace conditions, into ladles
resting on electric-powered trucks which can be moved into
the converter aisle.
     The matte ladles are picked up by overhead crane and
charged to one of three Peirce-Smith converters measuring 4
by 9 m (13 by 30 ft).  The initial charge to a converter
normally consists of four ladles of matte weighing 14 metric
tons (16 tons)  each.  Air is blown through tuyeres into the
charge, flux is added, and the slag produced is skimmed into
a ladle.   The converter slag is then returned to the rever-
beratory furnace by the overhead crane.  Additional matte is
                              2-14

-------
added to the converter to produce a total of approximately
50 metric tons  (55 tons) of light blister copper.
     The light blister copper is poured into ladles and
carried by overhead crane to a Great Falls converter, 4 m
(12 ft) in diameter, that has been modified to serve as a
holding furnace for final oxidation.  The charge in the
oxidizing furnace is air-blown through tuyeres to complete
sulfur removal.  Final oxidation in a holding furnace is
considered necessary to prolong brick life in the converters
and anode furnaces.
     Following completion of oxidation in the modified Great
Falls converter, the copper is transferred to the anode
furnace, which is 9m  (30 ft) long and 4 m (13 ft) in diam-
eter.  Reformed natural gas  (cracked methane) is introduced
through tuyeres for final copper reduction.  The anode-grade
molten copper is cast  into 330-kg  (720-lb) anodes on a 22-
mold casting wheel.  Anodes are cooled, inspected, and
loaded on flat rail cars for shipment to the Phelps Dodge
refinery in El Paso, Texas.
2.2.2  Emission Sources and Reverberatory Furnace Control
       Equipment
     The primary particulate sources at the Ajo smelter are
the reverberatory furnace and the converters.  Although most
of the exhaust gas produced by these sources is treated
before exhausting to the atmosphere, fugitive emissions escape
from feeding concentrates, skimming converter slag, or
returning converter slag.  Though the reverberatory furnace
matte and slag tap areas are hooded, the collected particu-
late-laden gases are simply exhausted to the smelter main
stack.  Similarly, converter "smoke" not captured by the
primary hood system is taken by a secondary hood system
directly to the smelter main stack.  The oxidizing and anode
                            2-15

-------
furnaces also exhaust particulate-laden emissions directly
to the atmosphere above the converter aisle.
     The principal reverberatory furnace exhaust gases pass
through a pair of waste-heat boilers before entering a
common plenum chamber for the two independent and parallel
ESP units.  The two units were designed to handle 4200
m3/min  (150,000 acfm) total volume at 315°C (600°F) and 95
kPa (13.8 psia),  but typical gas flow is 4640 m /min (164,000
acfm)  at about 309°C (588°F).  Each ESP unit consists of two
                                             2           2
stages with a total collection area of 1930 m  (20,700 ft ).
Average gas velocity is 0.9 ra/sec (3 ft/sec),  and treatment
retention time is less than 7 sec.  The maximum pressure
drop across a unit is 1.3 cm (0.5 in.) H20.
     Originally,  gas cleaning equipment was installed to
direct about 50 percent [1100 m /min  (38,500 scfm)] of the
ESP exit gas stream through a DMA (dimethylaniline) sulfur
dioxide  (S02) absorption plant, and the other half was ex-
hausted to the 110-m (360-ft) main stack of the smelter.
The duct work for directing ESP exit gas to the the DMA
absorption plant is now blanked off, and the entire gas
stream from the ESP outlet is discharged through the main
stack to the atmosphere.
     In the DMA plant,  which is now inoperative,  the gas
stream first enters a humidifying tower for evaporative
cooling by a weak acid solution and removal of some of the
residual particulate matter.  The gases then enter a cooling
tower, where a weak acid solution percolates down through
packing, which cools the ascending gases and removes more of
the remaining particulate matter.  After passage of the
exhaust gases through a mist precipitator for removal of
acid mist and remaining dust particles, the cleaned gas
stream enters the DMA absorption tower for SO- removal.  The
acid scrubbing section of the DMA absorption tower removes
                           2-16

-------
any acid mist that is formed before the gas stream is
discharged to the atmosphere through a 15-m (50-ft)  stack
atop the tower.
2.2.3  Chronology of Enforcement Actions for Phelps Dodge
       Copper Smelter at Ajo, Arizona
     Table 2-6 presents a chronology of enforcement actions
by the EPA.
                           2-17

-------
       Table  2-6.   CHRONOLOGY OF ENFORCEMENT ACTIONS -

         PHELPS  DODGE  COPPER COMPANY,  AJO,  ARIZONA3
      Date
                Action
May 14, 1973


July 13, 1973


January 23, 1974




March 24, 1975



May 5 and 6, 1975



June 30, 1975

August 28, 1975


September, 1975



October 1, 1975


October 6, 1975
EPA promulgated process weight regula-
tion 40 CFR 52-126(b).

EPA notified company by letter of process
weight regulation requirement.

Company notified EPA that it considers
itself to be in compliance with process
weight regulation.  No stack test re-
sults submitted.

EPA sent company a Section 114 letter
requiring stack test results be sub-
mitted to demonstrate compliance.

Company submitted test results.  The
results showed emissions that were
about three times allowable emissions.

EPA issued a Notice of Violation.

A conference was held between EPA,
Phelps Dodge, and Arizona State Agency.

Company conducted new emission tests,
which showed the emissions were 3.3
times the allowable emissions.

Company filed Petition for Review of
process weight regulation (Ninth Circuit) ,

Company filed application for stay
pending EPA review.
  Provided by Larry Bowerman of EPA Region IX.

 (Continued)
                              2-18

-------
                     Table  2-6  (continued).
   Date
            Action
October 17, 1975


November  5, 1975
November  28, 1975
January 15, 1976
April 7, 1976
July 5-16, 1976
July 15-30, 1976
March 28, 1977
May 9, 1977
Company submitted Petition for Reconsidera-
tion and Revision to EPA.

Letter from Russell E. Train  (Administrator,
EPA) to Senator Goldwater stated that EPA
had agreed to review any new  information
submitted by Phelps Dodge involving the pro-
cess weight regulation.

Letter from P. Defalco, Administrator of EPA
Region IX to John F. Boland,  Jr., advised
that Region IX would review the process
weight regulation and that enforcement action
was stayed.

National Enforcement Investigations Center
(NEIC), Office of Air Quality Planning and
Standards (OAQPS), and Region IX EPA per-
sonnel visited the smelter.

Letter from R.L. O'Connell, Director of En-
forcement Division, EPA, to D.H. Orr, Manager,
New Cornelia Branch, Phelps Dodge Corporation,
indicated installation of sampling facilities
was required pursuant to Section 114.

Extensive testing was conducted by EPA con-
tractors (Southern Research Institute and
Radian)  at the reverberatory  furnace electro-
static precipitator.

Extensive testing was conducted by EPA con-
tractor (Acurex Corporation/Aerotherm
Division)  at the reverberatory furnace ESP
Outlet,  and acid plant outlet, and main
stack.

Letter pursuant to Section 114 from O'Connell,
Director of Enforcement Division, EPA, to
Phelps Dodge requested further information
about installation of particulate-removal
systems reverberatory furnace gases.

Phelps Dodge responded to EPA letter of
March 28,  1977.
                              2-19

-------
                   3.0  EMISSION TEST DATA

3.1  ANALYSIS OF ELECTROSTATIC PRECIPITATOR PERFORMANCE
     DATA ON REVERBERATORY FURNACE AT MAGMA COPPER
     COMPANY, SAN MANUEL, ARIZONA
     At the request of EPA Region IX, the National Enforce-
ment Investigations Center  (NEIC) in Denver conducted emis-
sion tests from May 14 to 18, 1976, on the reverberatory
furnace stack of the Magma Copper Company in San Manuel,
Arizona, to determine compliance with the process weight
regulations, and again from May 19 to 21, 1976, to evaluate
the effect of temperature on the formation of particulate.
Before these tests, Magma Copper had also conducted com-
pliance tests on the furnace stack  (July 30 and 31, 1975).
     Design parameters of reverberatory furnace ESP's,
actual performance data, and compliance test data  (by both
NEIC and Magma Copper) are presented in Table 3-1.
     At the San Manuel smelter, reverberatory furnace ex-
haust gases pass through a pair of waste-heat boilers fol-
lowing each furnace.  The partially cooled gases are then
combined in a common duct before entering the plenum cham-
bers of the two separately housed units of the ESP.
     The two-unit ESP was manufactured by Research Cottrell
and installed in 1975.  It is designed for 98 percent
particulate removal, based on the ASME test methods.  Com-
pliance testing and results on the ESP are discussed in the
following paragraphs.
NEIC Compliance Test Conducted May 14-18
     Using EPA Method 5, NEIC conducted sampling tests on
the reverberatory furnace stack as a part of compliance
                            3-1

-------
             Table  3-1.   SUMMARY  OF PARTICULATE EMISSION DATA FOR ELECTROSTATIC  PRECIPITATOR

                      ON  REVERBERATORY FURNACE-MAGMA COPPER COMPANY,  SAN  MANUEL,  ARIZONA
                                 Item
ESP manufacturer

ESP inlet conditions

 Volume flow at continuous
  rating,  actual: m3/min
                 (acfm)
        standard:
                        Temperature :  °C
                                        m3/min
                                        (scfm)
U>
 I
M
 Gas dust  loadings:
  by instack filter,
       g/m3
       (gr/scf)
       kg/hr
       (Ib/hr)

  by instack/ontstack  filter,
       g/m3
       (gr/scf)
       kg/hr
       (Ib/hr)

  by EPA Test Method 5,
       g/m3
       (gr/scf)
       kg/hr
       (Ib/hr)

ESP outlet conditions

 Volume flow at continuous
  rating, actual:  m3/min
                 (acfm)
       standard:
                       Temperature
                       (Continued)
                                       m3/min
                                       (scfm)
                                                         Design
                                                     Research Cottrell
15,800  (calc.)
(560,000)
8040
(284,000)
260-354
(500-670)
                                                    1.91
                                                     (0.836)
                                                    922 (calc.)
                                                     (2035, calc.)
                                                   Actual
                                                    (1)
15,800  (calc.)
(560,000)
8040
(284,000)
260-354
(500-670)
                 1.91
                  (0.836)
                 922 (calc.)
                 2035, calc.)
                                   Compliance tests
                                 conducted by company,
                                 Oct.  30-31, 1975 (2)
                                   18,280 (calc.)
                                   (645,500,  calc.)
                                   9378t>
                                   (331,200)t>
                                   300
                                   (573)
                                        EPA compliance
                                        tests by NEIC
                                     May 14 to 18, 1976
                                                                                                                             (3)
                                       18,160 (calc.)
                                       (641,  200, calc.)
                                       9316=
                                       (329,000)=
                                       300
                                       (573)

-------
          Table  3-1  (continued).
I
UJ
Item
by instack filter,
g/m3
(gr/scf)
kg/hr
(Ib/hr)
by EPA Test Method 5,
g/m3
(gr/scf)
kg/hr
(Ib/hr)
ESP control efficiency, %
Allowable emissions.
g/m3
(gr/scf)
kg/hr
(Ib/hr)
At ESP outlet
SO2 emissions, ppm
kg/hr
(Ib/hr)
303 emissions, ppm
kg/hr
(Ib/hr)
Moisture content, volume percent
CO2 volume percent
02 volume percent
Metal analysis, kg/hr, (Ib/hr) ^
Tin (Sn)
Arsenic (As)
Cadmium (Cd)
Chromium (Cr)
Copper (Cu)
Lead (Po)
Mercury (Hg)
Molybdenum (Mo)
Nickel (Ni)
Selenium (Se)
Vanadium (V)
Zinc (Zn)
Design

0.02869
(0.01254)
14.04 (calc.)
(30.53, calc;)





98. Og




























Actual
(1)







































Compliance tests
conducted by company,
Oct. 30-31, 1975 (2)






0.275 to 0.898d
(0.1201 to 0.3924)
158 to 486
(349 to 1071)





























EPA compliance
tests by NEIC
May 14 to 18, 1976 (3)






1.76e
(0.77)
99Qf
(2180)


0.032 (calc.)
(0.014)
18
(39.7)

5400h
8100
(17,820)
15. 9i
30
(66.2)
8.7
4.03
(14.17)

0.072 (0.16)
2.34 (5.2)
0.11 (0.25)
0.045 (0.10)
4.32 (9.8)
1.55 (3.4)
0.027 (0.06)
0. 37 (0. 81)
0.014 (0.03)
0.59 (1.3)

2.34 (5.2)k
                  (Continued)

-------
            Table  3-1  (continued) .
                         Footnotes

                          Numbers in parenthesis represent corresponding reference  listed.
                          Average of four compliance test runs conducted by Magma on October 30 and 31, 1975.  Included in Appendix
                          A, Magma Petition for Revision Table 1,  page 4.   NEIC  report.
                         0 Average of three compliance tests conducted by NEIC  from  May 14-22, 1976.  The actual flow rates were 9770,
                          8864, and 9298 m3/min (345,000, 313,000, and 328,300 scfm)  respectively.
                          Actual emissions during four compliance  tests conducted by Magma on October 30 and 31, 1975 were 0.75, 0.50,
                          0.28, and 0.90 g/m3 (0.3268, 0.2202, 0.1201, and 0.3924 gr/scf  respectively.  Isokinetic conditions were not
.,                        met during all the tests.
 I                        e Average of three test runs [1.63, 1.95,  and 1.63 g/m3  (0.71, 0.85, and 0.71 gr/scf)] conducted.
                         £ Actual emissions during the three tests  were 948,  1111, and 907 kg/hr  (2090, 2450, and 2000 Ib/hr) .
                         ' Based on instack filter tests.
                          Average of three test runs.  Actual measurements were  4500, 6670, and 5030 ppm respectively.
                         1 Average of three test runs.  Acutal measurements were  12.8, 16.2, and 18.7 ppm respectively.
                         3 Metals identified in particulates collected by EPA Method 5 in ESP outlet during the second compliance test
                          run.
                         i,
                          Filter zinc results are questionable.
                         Reference
                         1)    State Implementation Plan Inspection  of San Manuel  Division Smelter, Magma Copper Company, San Manuel,
                             Arizona.  June 1976.   In:  Emission Testing at the  Magma Copper Company Smelter, San Manuel, Arizona,
                             by National Enforcement Investigations Center.  EPA-330/2-76-029.  May 2-22, 1976.
                         2)    Appendix A, Magma Petition for Revision In:  Emission  Testing at the Magma Copper Company Smelter,
                             San Manuel, Arizona,  by National Enforcement Investigations Center.  EPA-330/2-76-029.  May  2-22,  1976.
                        3)    Test Results.   In:  Emission Testing  at the Magma Copper Company Smelter, San Manuel, Arizona, bv
                             National Enforcement Investigations Center.  EPA  330/2-76-029.  May 12-22, 1976.

-------
testing at the San Manuel smelter.  During the test program,
NEIC also collected process input data for calculating the
allowable emissions from the reverberatory furnace.
     Three valid sampling runs were reported, using the four
available sampling ports at the 80-m  (262-ft) level of the
157-m  (515-ft) stack.  These test runs were performed within
the isokinetic range of 90 to 110 percent.  The sample
volumes collected during these test runs were 1.692, 1.698,
and 1.632 m3  (59.76, 59.97, and 57.63 ft3) with process
inputs of 159, 157, and 169 metric tons/hr (176, 173, and
186 tons/hr) respectively-  The sample from Run 2 was also
analyzed for its metallic content.
     Table 3-2 presents particulate emissions computed from
the test data, and allowable emissions calculated from
process weight input data.
            Table 3-2.  PARTICULATE EMISSION DATA
Run
1
2
3
Average
Actual particulate
emissions
kg/sec
.263
.309
.252
.275
Ib/hr
2090
2450
2000
2180
Allowable particulate
emissions
kg/sec
.005
-005
.005
.005
Ib/hr
39.6
39.5
39.5
39.5
     Table 3-3 lists quantities of metallic elements detected
in the filter catch and acetone wash of Run 2, the principal
ones being copper, lead, arsenic, and zinc.  The amount of
arsenic caught in the impinger of the sample train was
insignificant compared with that caught in the filter.
During the three tests, the gas moisture contents measured
8.9, 8.3, and 8.9 volume percent respectively-  Sulfur
                           3-5

-------
  Table 3-3.  ANALYSIS OF METALLIC ELEMENTS IN GAS

                      SAMPLE RUN 2
Element
Tin (Sn)
Arsenic (As)
Cadmium (Cd)
Chromium (Cr)
Copper (Cu)
Lead (Pb)
Mercury (Hg)
Molybdenum (Mo)
Nickel (Ni)
Selenium (Se)
Vanadium (V)b
Zinc (Zn)c
Amount detected,
228
7,200
340
144
13,500
4,700
76
1,110
36
1,790
7,200
Emission rate.
g/hr
74.4
2,375
112
47.3
4,453
1,550
25.0
367
11.7
590
2,375
Ib/hr
O.L6
5.2
0.25
0.10
9.8
3.4
0.06
0.81
0.03
1.3
5.2
Includes both filter and acetone wash.

Vanadium results below background levels observed in the
blank filters.

Zinc results include only acetone catch.  The filter zinc
results are questionable because of the high zinc levels
found in the blank filters.
                          3-6

-------
dioxide emissions were about eight times greater than
particulate emissions.  Table 3-4 gives the amounts of S02
and SO^ in the sample tests as calculated by NEIC.
          Table 3-4.  SULFUR DIOXIDE EMISSIONS
Run
1
2
3
Average
S02 cone.
^ppm
4500
6670
5030
5400
SO? emission
Ib/hr
15,680
21,100
16,700
17,820
kg/sec
1.97
2.66
2.10
2.25
SO^t cone.
ppm
12.8
16.2
18.7
15.9
SO^ emission
Ib/hr
56.1
64.5
78.0
66.2
kg/sec
0.007
0.008
0.010
0.008
     The NEIC believes the reported values of sulfur dioxide
emissions are conservative, because the sulfur dioxide gas
dissolved in the first impinger  (water) of the sample train
would not be detected by the sulfate analytical method
(i.e., SO- caught in Impinger 1 is not included in the SO-
emission results).  No sulfate was found in the filter or
acetone wash catches during the testing.
     Based on the test results, NEIC concluded that the high
particulate concentration in the reverberatory furnace flue
gas indicates the ESP is not providing effective control.
According to the Magma Copper data, an average of 114 metric
tons (125 tons) of fines per day is recycled from the rever-
beratory and converter ESP's to the reverberatory furnace.
This amount is substantially less than the 218 metric tons
(240 tons) per day that would be collected by the rever-
beratory furnace ESP if it were operating at least at a 90
percent efficiency level.  Recycle weights were not avail-
able to NEIC for the specific times during which tests were
conducted.
     The average stack gas flow rate during the tests mea-
sured approximately 9313 m /min  (328,900 scfm) and the stack
temperature averaged 300°C (573°F).
                           3-7

-------
NEIC Ancillary Test Data
     NEIC conducted additional testing on the reverberatory
furnace stack on May 19 and 21, 1976, to evaluate the effect
of temperature on particulate formation.  Five tests were
conducted using two sampling trains simultaneously in two
ports, one equipped with an instack filter in combination
with an outstack filter and the other with a standard Method
5 outstack filter.  The sampling probes were about 5 ft
apart.  Particulate was measured using the instackroutstack
filter train in the south port for the first three readings
and in the north port for the other two readings, while the
outstack filter train was kept in the west port throughout
the five runs.  Based on these ancillary tests, NEIC reached
the following conclusions:  a) particulate is apparently
formed as the reverberatory gases are cooled during sampling
from an average stack temperature of 274°C (526°F) to a
filter temperature of 120°C (250°F); (b) particulate sulfate
appears to be formed as the reverberatory gases pass through
the instack filter; and (c) simultaneous samples should be
obtained from sampling points as close to each other as
possible without causing aerodynamic disturbances, in order
to define the effect of temperature on particulate collec-
tion.
     Sample times for the five runs varied from 10 to 58
minutes and sample volumes from 0.169 to 1.028 m3  (6 to 36
scf).  The stack gas temperature measured during sampling
averaged 274°C  (526QF) and ranged from 223° to 306°C  (434°
to 583°F), and the average gas moisture content was 8.8
volume percent with a 3.1 to 13.1 percent variation.  All
measurements were made under isokinetic conditions.
     Consistently less particulate was collected on the
outstack filter train during the first four runs than on the
outstack filter of the instack/outstack filter train.
                            3-8

-------
During the five runs, the particulate collected by the
outstack filter train was 17.44, 61.57, 51.8, 52.34, and
139.29 percent of that collected on the instack/outstack
filter train.  The particulate collected on the instack
filter of the instack/outstack train ranged from 1.4 to 49
percent.  [In all cases, the particulate collected on the
instack filter at approximately 282°C  (540°F) ranged from 2
to 44 percent of that collected by the outstack filter of
the other train.]
     After further study of the tests for sulfate formation,
NEIC made the following observations:  analyses performed on
the outstack filter of the instack/outstack train indicate
that from 19 to 57 percent of the particulate collected was
a sulfate material.  No sulfates were found in the instack
filter nor on the filters for Runs 3, 4, and 5 of the
outstack train.  The data do not explain why sulfates were
present in the front half of Runs 1 and 2 of the outstack
train, but not in Runs 3, 4, and 5.  Analyses of Impingers
1, 2, and 3 indicated SO., concentrations of 31 to 93 ppm and
SO_ concentrations of 2600 to 5000 ppm by volume.  These
amounts show higher SO., concentrations and lower S0~
concentrations than those observed during the compliance
testing.  The arsenic content of Impinger 4 was insignifi-
cant (i.e.,  <0.01 wt. %) when compared to the arsenic con-
tent of the filter.  (NEIC did not give the arsenic content
of the filter.)
Company-Conducted Compliance Tests on October 30 and 31, 1975
     Since isokinetic conditions were not met during the
four company-conducted sampling tests, the results cannot be
considered valid.  Even these test results, however, show
that actual particulate emissions far exceed the allowable
limits.
                            3-9

-------
3.2  ANALYSIS OF ELECTROSTATIC PRECIPITATOR PERFORMANCE
     DATA ON REVERBERATQRY FURNACE AT PHELPS DODGE CORPO-
     RATION, AJO, ARIZONA
     Since 1975, many tests have been conducted to determine
emission characteristics and control system performance of
the reverberatory furnace at the Phelps Dodge Corporation
smelter at Ajo, Arizona.  Basic design parameters of the
ESP, actual data reported by Phelps Dodge, and data from
numerous field tests by Radian Corporation, Southern Research
Institute, and Aerotherm Corporation are summarized in Table
3-5.
     After reverberatory furnace gases pass through the
waste-heat boilers, they are treated in an ESP at a tempera-
ture of approximately 315°C (600°F) and vented to the atmo-
sphere through the stack.
     The ESP, manufactured by the Western Precipitation
Division of Joy Manufacturing Company, was installed in
August 1973.  Design performance of the system was based on
measuring particulate at a system temperature of 315°C
(600°F) by the ASME test method.  The system design does not
comply with EPA process weight regulations, which call for
ESP outlet particulates to be measured by EPA Method 5.
This method measures the particulate collected from the
stream at approximately 120°C (250°F).
     Detailed analyses of various tests and their data are
presented in the following sections.
     Radian Corporation Test Results - Radian Corporation
tested particulate emissions from the reverberatory furnace
ESP at the Phelps Dodge Ajo facility from June 7 to 16,
1976, to evaluate the performance of the ESP.  Table 3-6
summarizes Radian's sampling program.
     Radian reached the following conclusions as the result
of these tests:
                            3-10

-------
 Table 3-5.  SUMMARY OF PARTICULATE  EMISSION DATA FOR ELECTROSTATIC




PRECIPITATOR IN REVERBERATORY FURNACE  -  PHELPS DODGE COPPER SMELTER,




                            AJO, ARIZONA
Item
ESP manufacturer
ESP inlet conditions
Velocity, m/sec
(fps)
Volume flow at continuous
rating, actual: m3/min
(acfra)
standard: mVmin
(scfm)
Temperature, °C
(°F)
Gas dust loadings:
by instack filter.
g/m3

(gr/scf )

kg/hr

(Ibs/hr)
by instack/outstark
filter, g/m3
(gr/scf)
kg/hr
(Ibs/hr)
by EPA Test Method 5,
g/m3
(gr/scf)
kg/hr
(Ibs/hr)
standard m-Vmin
(scfm)
ESP outlet conditions
Velocity, m/sec
(fps)
Design
(l)a
Joy Western




4248C
(150,000)
(2124 calc.)
(75,000 calc.)
315 (max.)
(600)


5.15 (max.)e

(2.25)

655 (calc.
max. )
(1446.43)















Actual
(1)





4644
(164,000)
(2560 avg. calc. )
(90,500 avg. calc.)
232 to 288
(450 to 550)


1.35 (calc.)

(0.592)

191e

(421)















Radian
test results
July 6-16, 1976
(2)


16.76 to 17. 37b
(55 to 57)

4531d
(160,000)
2197 (calc.)
(77,580 calc.)
334
(633)


avg. 1.37
(0.39 to 3.5)
(avg. fl.6, range
from 0.17 to 1.55)
avg. 184 (calc.)9

(avg. 402 calc. )
i_
3.57 to 5.65n
(1.56 to 2.47)
468 to 756 (calc.)
(1041 to 1648)





2630 (calc.)
92,840

34.7
(114)
SRI test
results
July 9-10, 1976
(3)



































Aerotherm
test results
July 15-30, 1976
(4)

































23.5
(77.17)
(Continued)

-------
        Table 3-5  (continued).
CO
I
H
N)
Item
Volume flow at continuous
rating, actual: m^/min
(acfm)
standard: m3/min
(scfm)
Temperature °C
(°F)
Gas dust loadings:
by instack filter.
g/n.3
(gr/scf)
kg/hr
(Ib/hr)
by instack/outstack
filter, g/m3
(gr/scf)
kg/hr
(Ib/hr)
by EPA Test Method 5,
g/m3
(gr/scf)
kg/hr
(Ib/hr)
ESP control efficiency, %
Allowable emissions,
g/m3
(gr/scf)
kg/hr
(Ib/hr)
Dust size analysis
'at ESP inlet
at ESP outlet
Gas composition volume, %

H,O
°2
C02
S02
so3
Design
(1)









0.144
(0.063)
18.1 (guaranteed)
(40)










96.83q















Actual
(1)









0.153
(0.067)
21.3^
(47)


























Radian
test results
July 6/16, 1976
(2)

5248
(185,330)
2629
(92840)
314
(598)


v,.w,u
.(0.02)
6.10 (calc.)
(13.44)

1.92 to 3.14™
(0.84 to 1.37)
254 to 414 (calc.)
(560 to 914)














ESP t ESP t
inlet outlet
13.2 12.3
10.7 9.5
6.0 6.5
0.33 0.56
0.006 0.012
SRI test
results
July 9-10, 1976
(3)























9*.7r





S
< 10 urn
< 1 urn







Aerotherm
test results
July 15-30, 1976
(4)

32901
(116,200)
1685 calc.
(59500)
288 to 316
550 to 600


0.96 (calc.)
(0.42)
96. 51
(212.8)

1.89 (calc.)
(0.83)
192n
(423.5)

1.28 (calc.)
(0.56)
129. 4P
(285.4)




14,15
(31.2)



ESP*
outlet
12.2
13.6
4.1
8.1
0.0034

-------
           Table  3-5   (continued).


                       Footnotes

                       a Numbers in parentheses represent corresponding references listed.

                         Actual measurements in each of the two inlet ducts to the ESP were 16.76 and 17.37 n/sec (55 and
                         57 fps) respectively.
                       0 At 0°C and 101.33 kPa  (32°F and 14.7 psia).

                         Average of six tests conducted July 7 through July 10, 1976.  During the test runs, the volume rate
                         varied from 4190 to 4730 m3/min (148,000 to 167,000 acfm).

                       e 1975 tests by Engineering Testing Laboratories, using WP Method 50, hard particulates only.

                         Result of five test runs conducted July 8 through July 10,  1976.  Actual emissions varied from 0.39 to
                         3.6 g/m3 (0.17 to 1.55 gr/scf) .

                       ^ According to Radian, the outlet sampling location was much more favorable than the inlet and for this
                         reason the gas flow rate obtained at the outlet, 2220 mVmin (78,400 scfm) ,  was used to calculate the
                         flow rates of gas through the ESP.  Based on this gas flow rate and average loading of 1.37  g/m3 (0.6
                         gr/scf), Radian calculated a mass flow rate of 154 kg/hr (340 Ib/hr).

                         Results of two test runs performed at a single point in the one duct (two ducts lead into ESP).   Test
                         Run 1 collected 1.33 g/n\3 (0.58 gr/scf) on instack filter and 4.33 g/m3 (1.89 gr/scf)  on outstack filter,
                         and Test Run 2 collected 0.71 g/m3  (0.31 gr/scf) on instack filter and 2.86 g/m3 (1.25 gr/scf).on outstack
                         filter.

UJ                     1 Average of 11 tests conducted July 20 to 30, 1976, during which the volume flow was between  1320 and 1982
 I                        m3/min  (46,700 and  70,000 scfm).
,.                     i Average of five test runs conducted on July 0 to 10, 1976.   The minimum and maximum dust loadings obtained during
                         the test were 0.039 and 0.057 g/m3  (0.017 and 0.025 gr/scf)  respectively.

                         1975 tests by Engineering Testing Laboratories, using EPA Method 5 with sulfates deducted.

                         Average particulates collected on instack filter during two tests conducted by using instack/outstack
                         filters on July 29  and 30, 1976.  The actual readings were 98.5 and 94.5 kg/hr  (217.2 and 208.4 Ib/hr) .
                       m Results of three test  runs.  The actual readings were 2.22, 1.92, and 3.14 g/m3 (0.97, 0.84, and 1.37 gr/scf).
                         Amounts collected on instack  filters in these three test runs were 0.06, 0.17, and 0.044 g/m3 (0.027, 0.072,
                         and 0.019 gr/scf respectively.
                       n Average of two test runs conducted on July 29 and 30, 1976.  Actual readings were 191.9 and 192.3 kg/hr (423.0
                         and 423.9 Ib/hr).
                       P Average of seven test  runs during July 21-28, 1976.  The minimum and maximum readings were 98.1 and 150.3  kg/hr
                          (216.2 and 331.3 Ib/hr) respectively.

                       ^ Guaranteed efficiency  based on instack filter tests.
                       r Using  instack filter method.
                         Overall mass median diameter.

                         Average of many measurements.


                       References

                       1)    Appendix  B.  State  Implementation Plan Inspection of  Phelps-Dodge Corporation, Ajo, Arizona.  May  1976.
                       2)    Radian Corporation.  Stack Test  Results at Phelps-Dodge Corporation, Ajo, Arizona.  Technical Note
                             200-045-57-03.   January  5,  1977.
                       3)    Southern  Research  Institute.  Performance Evaluation of an Electrostatic Precipitator Installed on a
                             Copper Reverberatory Furnace.  Order No. CA-6-99-2980-J.  January 14, 1977.
                       4)    Acurex Corporation/Aerotherm Division.  Stack Test Results at Phelps-Dodge Corporation, Ajo, Arizona,
                             Volume I.  Aerotherm Project 7211.  March 1977.

-------
            Table  3-6.    SUMMARY  OF THE SAMPLING  EFFORT  (JULY  7  THROUGH  JULY 16,   1976)   BY  RADIAN
U)
 I
Date
Location/stream sampled
To evaluate reverb. ESP performance:
July 8 to 10
July 8
July 8 to 10
July 10
July 10
ESP outlet
ESP outlet
ESP inlet
ESP inlet
ESP control room
Parameter

Grain loading
Particle size distribution
Grain loading
Particle size distribution
Electrical performance
To form a material balance around reverb. ESP:
July 11
July 11
July 11 to 13
ESP outlet
ESP inlet
ESP dust
Trace element flow rates
Trace element flow rates
Trace element flow rates
Technique


Instack filter
Andersen cascade impactor (SRI)
Instack filter
Brinks cascade impactor (SRI)
Monitor operating parameters (SRI)

Integral WEP
Integral WEP
Periodic grab sample


                            To form an  approximate material balance around the reverb,  furnace:
   July 13
July 12 to 14

July 11 to 13
July 12 to 14
July 12 to 14
ESP outlet
Reverb feed

ESP dust
Reberb slag
Matte
Trace element  flow rates
Trace element  flow rates

Trace element  flow rates
Trace element  flow' rates
Trace element  flow rates
Integral WEP
Compositing slinger  bin  catches at
 the end of each shift
Periodic grab sample
Periodic grab sample (PD)
Periodic grab sample (PD)
                              To  collect particulate by particle size for trace  element analysis:
                               July  16
                                                ESP outlet
                              To  collect vapor phase emissions:
                               July  16
                                                ESP outlet
                              To  determine amount of condensible material and SO  emitted:
                               July  15


                               July  15



                             To determine

                            July  13  to  14
                            July  13  to  14
                               July 7

                               July 7
                                                ESP inlet
                     ESP outlet
               arsenic emission rates:

                    ESP outlet
                    ESP inlet
                    ESP outlet

                    ESP inlet
                                      Particulate by size frac-
                                                                  Trace element  flow  rates
                                                                   as vapor
                  Condensed particulate
                   (between 600-250°F) and
                   SOj-SOj concentrations
                  Condensed particulate
                   (between 600-250°F) and
                   S02-SO3 concentrations
                 Arsenic emission rate
                 Arsenic emission rate
                 Velocity and temperature
                  traverse
                 Velocity and temperature
                  traverse
                                             Three outstack cyclones  in  series
                                             plus filter
                                                                  Outstack  filter  followed by
                                                                  impingers
                                                                  EPA Method  5  train with  instack filters


                                                                  EPA Method  5  train with  instack filters
                            Modified EPA Method  5 train
                            Modified EPA Method 5 train
                            S-type pilot tube and thermocouples

                            S-type pilot tube and thermocouples

-------
1.   The known major components charged to the rever-
     beratory furnace are copper, iron, silicon, calci-
     um, and aluminum.  Titanium, potassium, magnesium,
     and sodium also are important.

2.   Minor elements of environmental concern are arse-
     nic, cadmium, molybdenum, lead, antimony, seleni-
     um, zinc, and fluorine.  Nearly all of the arse-
     nic, 50 percent of the selenium, and 30 percent of
     the fluorine, are discharged as off-gases from the
     reverberatory furnace.  Nearly all the fluorine
     escapes as gas.

3.   Arsenic and selenium pass through the ESP partly
     as vapor.

4.   The waste-heat boiler seems to act as a collection
     chamber for arsenic and selenium compounds, which
     means that chemical species in the vapor phase
     condense on the heat exchange surfaces because of
     changes in gas temperature.

5.   Actual gas flow rate of 4530 m /min  (160,000 acfm)
     and temperature of 316°C  (600°F) correspond to
     design parameters for the device.

6.   Electrostatic precipitator inlet and outlet grain
     loadings determined at a duct temperature of 315°C
     (600°F) are 1.37 g/m3  (0.6 gr/scf), and 0.046 g/m3
     (0.02 gr/scf) respectively.

7.   When the temperature is decreased from 315 to
     121°C  (600 to 250°F)  (as recommended by EPA),
     condensible materials increase to 3.66 g/m3 (1.60
     gr/scf) at the inlet and to 1.37 g/m3  (0.60 gr/scf)
     at the outlet.

8.   Converter off-gases and gas stream particulates
     not collected in the hot reverberatory furnace ESP
     can be almost completely removed in the gas
     conditioning sections of the DMA plant and the
     contact sulfuric acid plant.  The elements removed
     from the gas streams will ultimately be found in
     the humidifier blowdown streams.  (The DMA plant,
     which was originally installed to treat 50 percent
     of gases from the existing ESP, is not operated.
     The duct connection for these gases to the DMA
     plant is completely cut-off, and all treated gas
     is passed through the stack.)
                       3-15

-------
     During the testing program, Radian observed that dust
loading changes from light to very heavy black and back to
light, all within a few minutes, apparently as a function of
furnace charging.
     The gas flow rates to and from the ESP were determined
from velocity measurements.  Reported average velocities
were 17.4 m/sec  (57 ft/sec) in the east duct, 16.2 m/sec (53
ft/sec) in the west duct, and 34.7 m/sec (114 ft/sec) in the
outlet duct.  The respective inlet and outlet gas temperatures
were 334 and 314°C (633 and 598°F).  Radian reported the
average gas flow rate to be 2220 m /min (78,400 scfm), based
on a measurement at the ESP outlet (the outlet sampling
location was more accessible than the inlet).  Test data
show that the average volume flow rate of six measurements
was 2340 m /min  (82,700 acfm) in the east inlet duct, 2190
m /min  (77,300 acfm)  in the west inlet duct,  and 5247 m 'min
(185,300 acfm) in the outlet duct.  These values would
correspond to 2185 m /min  (77,160 scfm)  at the ESP inlet and
2629 m /min (92,825 scfm) at the outlet.  During all measure-
ments, except the first, outlet flow was higher than inlet,
even though the outlet temperature was lower.  The design
flow through the ESP is 1994 standard m3/min or 4248 m3/min
at 315°C and 92.06 kPa  (70,400 scfm or 150,000 acfm at 600°F
and 13.8 psia).  The flow measurements,  therefore, show
that the actual gas treated in the ESP is about 6.7 percent
higher than design, based on inlet volume flow, and about
24 percent higher based on outlet flow.   This could indicate
leakage of outside air into the ESP-
     During PEDCo's visit to the plant on May 21, 1977,
Phelps Dodge personnel indicated that one hanging damper is
installed in each of the two equally sized inlet ducts to
the ESP.  These dampers may differ slightly in size and thus
                           3-16

-------
be causing differences in velocity and gas dust loadings in
the two ducts.  The flip-flop damper  (installed in the duct
system for guiding gases through the  balloon flue or the
duct work), the manholes on the ESP,  and the access doors on
the hoppers are all possible sources  of air infiltration.
     Average grain loading measurements using instack
filters are based on  five simultaneous test runs conducted
July 8, 9, and 10, 1976, at the two inlet ducts and the
outlet duct of the ESP.  Problems were encountered during
the test program because of the sticky or tacky nature of
particulates, which cause them to plug the filtering media
at the ESP inlet  (and to a lesser extent at the ESP outlet).
The average inlet and outlet particulate concentrations are
1.37 and 0.046 g/m   (0.6 and 0.02 gr/scf) respectively.
These averages are calculated without regard for ESP inlet
grain loading changes in the operating cycle of the reverberatory
furnace.  At the 95 percent confidence level, therefore, the

                                                          3
inlet particulate loading is 1.38 + 0.586 g/m  (0.603 +
0.256 gr/scf) and the outlet loading is 0.046 + 0.0075 g/m~
(0.0202 + 0.0033 gr/scf).  During all five of the simultaneous
test readings at the inlet ducts, loading measurements
varied significantly.  If it were possible to take inlet
concentration measurements in the mixing chamber, the
results might be more accurate.
     Conclusions concerning the amount of condensables
between 315° and 120°C (600 and 250°F), are based on tests
using instack and outstack filter tests.  This determination
was, in essence, a comparison between instack filter and
outstack filter sampling methods.  The results presented in
Table 3-7 are based on two measurements performed at a
single point in the west inlet duct and three measurements
with a six-point traverse at the outlet duct.
                             3-17

-------
                        Table 3-7.  INSTACK VS. OUTSTACK PARTICULATE  LOADING


                               PHELPS DODGE CORPORATION, AJO, ARIZONA
Run
1
2
3
ESP Inlet
Instack
1.33 g/m3
(0.58 gr/scf)
0.71 g/m3
(0.31 gr/scf)

Outstack
4.32 g/m3
(1.89 gr/scf)
2.86 g/m3
(1.25 gr/scf)

Combined
5.65 g/m3
(2.47 gr/scf)
3.57 g/m3
(1.56 gr/scf)

ESP Outlet
Instack
0.062 g/m3
(0.027 gr/scf)
0.16 g/m3
(0.072 gr/scf)
0.044 g/m3
(0.019 gr/scf)
Outstack
2.15 g/m3
(0.94 gr/scf)
1.78 g/m3
(0.78 gr/scf)
3.09 g/m3
(1.35 gr/scf)
Combined
2.22 g/m3
(0.97 gr/scf)
1.92 g/m3
(0.84 gr/scf)
3.14 g/m3
(1.37 gr/scf)
U)
I
M
00

-------
     As indicated by test results using only an instack
filter, the loading varies significantly in the two ducts at
any given time.  The instack and outstack filter tests at
the ESP inlet also should have been conducted at more than
one sampling point in both ducts.  Results do not indicate
whether the test runs were taken continuously, or at dif-
ferent times to allow for the effect of the furnace opera-
tion on the loadings.  Tests using an instack filter train
and an instack/outstack filter train might be more valuable
if they were conducted at the same time and if measurements
were taken repeatedly at different intervals to allow for
variations in particulate loading that result from operating
changes.   Tabular data in Table 3-7  (two measurements)  show
that 77 to 80 percent of the total particulate entering the
ESP's is in a vapor form.  The overall removal efficiency of
the ESP is 46 to 61 percent.  The particulate measurements
were obtained by using instack/outstack filter trains at the
inlet and outlet of the ESP.  The instack filter was at
316°C (600°F) and the outstack filter at 120°C (250°F).
These measurements also indicate that the ESP's are removing
from 77 to 98 percent of the particulate in a solid state at
316°C (600°F) and 38 to 50 percent of particulates in the
supposedly gaseous state at 316°C (600°F).  This poses a
question as to how 38 to 50 percent of gaseous particulate
is removed in the ESP.
     Radian also conducted sampling tests on July 11, 1976,
at the inlet and outlet of the ESP to capture all particu-
late trace elements in the gas streams.  They used a train
containing a wet electrostatic precipitator (WESP), followed
by a series of impingers to collect vapors escaping the ESP.
They also analyzed the dust collected in the ESP by periodic
sampling.   These ESP inlet and outlet samples were collected
                             3-19

-------
isokinetically from a single point assumed to be a point of
average velocity and particulate loading.  The sample col-
lected was analyzed for trace elements by the atomic absorp-
tion method and fluorometry.  The results indicate that
nearly all the trace elements were collected in the WESP,
whereas only negligible amounts were collected by the
impingers.
     On July 13, 1976, Radian also measured the trace ele-
ments content of the flue gas at the ESP outlet, using a
WESP sampler followed by impingers; that was part of a
sampling program for material balance around the reverberatory
furnace.  They conducted a separate test on July 16, 1976,
for trace elements present as vapor in the flue gas at the
ESP outlet.  The collection of vapor phase trace elements
was accomplished using a series of impingers, preceded first
by a cyclone then by a filter to remove particulates.  Table
3-8 presents the results of these tests/analyses of the
total particulate (in the flue gas at ESP inlet and outlet)
and vapor phase particulate (in the flue gas at 'ESP outlet).
Because the values for solid phase trace elements collected
on the cyclone and filter were not measured during the test
for vapor phase trace elements, it is impossible to estimate
accurately the relative proportions of these phases in the
flue gas at the ESP outlet.  The WESP samples indicate that
the ESP now used removes about 26 percent of the arsenic in
the gas (results of particulate measured on July 11, 1976,
from Table 3-8).  Results also show that some copper and
small amounts of cadmium, lead, and zinc present in the
inlet gas were also removed in the following proportions:
98.2, 94.2, 91.6, and 98.1 percent respectively.
     Results of the quantitative analysis of samples col-
lected around the reverberatory furnace are given in Table
3-9.  As shown in Table 3-6, integral WESP samples at the
                            3-20

-------
                  Table  3-8.   ANALYSES  OF TOTAL  PARTICULATE AND  VAPOR PHASE  PARTICULATE


                          IN FLUE GAS  AT  ESP  INLET OR OUTLET  (BY RADIAN CORPORATION)
U)
 I
NJ
Element
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Fluorine
Iron
Mercury
Molybdenum
Nickel
Lead
Sulfur as SO2e
as SO3e
Ant imony
Selenium
Silica
Vanadium
Zinc
ESP inlet
Total particulate
measured on 7/ll/76a'b
kg/hr
86.2
Not de-
0.0059
0.13
0.012
25.4
3.36

0 .00049
3.95
0.042
0.42
598.7
13.61
0.367
0.413

0.018
1.95
Ib/hr
190
.ected
0.013
0.29
0.027
56
7.4

0.0011
8.7
0.092
0.92
1320
30
0.81
0.91

0.041
4.3
Total particulate
measured on 7/ll/76a'c
kg/hr
63.5
Not de
0.0049
0.0073
0.0049
0.454
3.4

0.00039
0.073
0.039
0.034
1002.4
22.67
0.149
0.439

0.002
0.033
Ib/hr
140
:ected
0.011
0.016
0.011
1.0
7.5

0.00087
0.16
0.085
0.075
2210
50
0.33
0.97

0.0047
0.072
ESP outlet
Total particulate
measured" on 7/13/77d
kg/hr
34.5
0.29
0.0015
3.45
0.019
8.16
4.26
0.249
0.015
0.077
0.0049
0.17

.014
0.295

0.77
0.099
Ib/hr
76
0.64
0.0034
7.6
0.044
18
9.4
0.55
0.033
0.17
0.011
0.38

0.03
0.65
1.7
0.027
0.22
Vapor phase content
measured on 7/16/77
kg/hr
6.8
0.12
0.0018
0.00004
0.016
1.33
4.99
0.089
0.028
0.0073
0.014
0.0039

0.0014
0.095

0.009
0.016
Ib/hr
' 15
.27
0.004
0.0001
0.036
2.94
11.0
0.196
0.062
0.016
0.031
0.0087

0.003
0.21

0.02
0.036
               a Particulate collected using wet electrostatic precipitator (WESP).   In addition  to this,  an insignificant
                 amount of trace elements is collected on impingers.

               b Trace elements constituted 0.32 percent of  total sample analyzed.

               c Trace elements constituted 0.12 percent of  total sample analyzed.

                 Trace elements constituted 0.1 percent of total analyzed

               e Sample was not analyzed for sulfur, but its values are based  on SOj-SC^ concentrations in flue gas and the
                 sulfur content of the flue dust,  determined independently of  the WESP sampler.

-------
                         Table  3-9.   ELEMENT FLOW RATES  IN THE FEED AND DISCHARGE


                                        STREAMS OF REVERBERATORY FURNACE
Element
Al
As
Ba
Be
Ca
Cd
Cr
Cu
F
Fe
Hg
Mo
Ni
Pb
Sb
Se
Si
V
Zn
Incoming streams
Reverb.
feed
kg/hr
181
86.4
14.4
0.032
349
26.7
0.034
7260
1.5
4536
0.0082
35.8
0.32
22.2
2.72
4.54
499
0.42
19.0
Ib/hr
400
190
31
0.072
770
59
0.076
16000
3.4
10000
0.018
79
0.70
49
6.0
10
1100
0.92
42

slag
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
Converter
dust
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
Total
kg/hr
181
86.0
14.1
0.032
349
26.7
0.034
7260
1.54
4536
0.008
35.8
0.32
22.2
2.72
4.54
499
0.42
19.0
Ib/hr
400
190
31
0.072
770
59
0.076
16000
3.4
10000
0.018
79
0.70
49
6.0
10
1100
0.92
42
Outgoing streams
Matte
kg/hr
<7.7
0.72
14.97
0.0019
5.4
16.8
29
8165
0.005
4970
0.0091
3.85
0.91
38.1
2.09
0.077
<19
0.15
14.1
Ib/hr
<17
1.59
33
0.0041
12
37
0.64
18000
0.012
11000
0.020
8.5
2.0
84
4.6
0.17
<42
0.33
31
SlaE
kg/hr
318
0.86
19.5
0.015
862
0.15
1.72
998
1.0
5443
0.004
40.3
0.34
5.89
1.54
2.49
21.7
0.39
13.6
Ib/hr
700
1.9
43
0.032
1900
0.33
3.8
2200
2.2
12000
0.0091
89
0.76
13
3.4
5.5
48
0.86
30
Flue gas
kg/hr
0.045
34.5
0.29
0.0015
0.005
3.44
0.019
8.16
4.26
0.25
0.015
0.077
0.0050
0.17
0.014
0.29
0.77
0.12
0.10
Ib/hr
0.10
76
0.64
0.0034
0.011
7.6
0.044
18
9.4
0.55
0.033
0.17
0.011
0.38
0.030
0.65
1.7
0.027
0.22
ESP3 dust
kg/hr
0.49
13.6
0.010
0.0002
0.95
0.33
0.0082
28
0.015
19.3
0.00007
2.99
0.026
2.4
0.58
0.073
0.77
0.005
2.09
Ib/hr
1.1
30
0.023
0.0004
2.1
0.74
0.018
62
0.032
42.6
0.00015
6 *
0.059
5.3
1.3
0.16
1.7
0.011
4.6
Waste heata
boiler dust
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
Total
kg/hr
318
49.4
34.6
0.014
907
20.9
2.04
8165
5.4
10400
0.028
45.4
13.2
45.4
4.26
2.95
2177
0.54
29.9
Ib/hr
700
109
76.2
0.039
2000
46
4.5
18000
12
23000
0.062
100
29
100
9.4
6.5
4800
1..2
66
I
NJ
fO
        a These s

        NA - Not
Creams were not recycled during
available.
                     the time of ESP sampling

-------
ESP outlet were collected on July 13, 1976, and precipitator
dust was collected July 11 to 13, 1976.  The matte and slag
were obtained during sampling from July 12 through July 14,
1976.  The samples of concentrate were taken at the end of
each shift from January 12 to 14, 1976.  The data in Table
3-8 and Table 3-9 show that of a total of 86.2 kg/hr (190
Ib/hr) of arsenic entering the system only 34.5 to 63.5
kg/hr  (76 to 140 Ib/hr) is found in the ESP exit stream and
13.6 kg/hr (30 Ib/hr) is trapped in the ESP dust.  According
to Radian, the remaining 7.3 to 36.3 kg/hr (16 to 80 Ib/hr)
of arsenic, which is unaccounted for, may have settled out
in the surface area of the waste-heat boilers serving the
reverberatory furnace.  As indicated in the table, some of
the other elements may also be settling out in the waste-
heat boilers.
     On July 13 and 14, 1976, Radian conducted a separate
test for arsenic at the ESP inlet and outlet, using EPA
Method 5 with a filter at 120°C  (250°F) followed by a
series of impingers.  During these tests, Radian measured
arsenic emission rates averaging 31.39 kg/hr* (69.2 Ib/hr)
at the ESP inlet [measurements of 26.9 kg/hr  (59.3 Ib/hr),
33.1 kg/hr (72.9 Ib/hr), and 34.2 kg/hr  (75.4 Ib/hr) during
three runs] and 22.6 kg/hr (49.9 Ib/hr) at the ESP outlet
[measurements of 24.4 kg/hr  (53.7 Ib/hr), 20.3 kg/hr (44.8
Ib/hr), and 23.3 kg/hr  (51.3 Ib/hr) during three runs].
These data do not clearly indicate whether the arsenic
emission rates are based on the amount collected on the
filter at 120°C (250°F) only, or on the total amount col-
lected on the filter and impingers.
     Based on these sampling tests, Radian assumes that the
efficiency of the WESP used for sample collection in this
*
  The emission rates are based on flow rate determined by
  Radian and analyzed data obtained by Battelle, Columbus
  Laboratories, Columbus, Ohio.
                            3-23

-------
study can be compared with the expected efficiency of the
WESP for particulate control.  They further assume that
virtually all elements covered in their study can be col-
lected in the spray tower,- packed tower, and WESP arrange-
ment.  The blowdown stream of the cooling-humidifying unit,
however, will have to be treated, because it will contain
all the impurities presently escaping the existing dry ESP
that treats the off-gases of the reverberatory furnace.
     Additional tests produced the following results:  the
reverberatory feed concentrate consists primarily of two
crystalline phases:  chalcopyrite (CuFeS2) and two-quartz
(Si02).  Arsenolite  (As203) was positively identified in the
hopper dust, in the material captured by the instack filter,
in the deposit on the outstack filter as well as in the
impingers.  Hydrates of copper sulfate and arsenolite were
the predominant materials collected on the instack filter.
This material was a bright blue, and the crystalline portion
was almost pure arsenic oxide.  The crystalline portion of
the material collected on the outstack filters at 120°C
(250°F) was almost all arsenolite.
Aerotherm Corporation Test Results
     At the request of EPA Region IX, Aerotherm conducted
particulate emission tests from July 20 to July 30, 1976, on
the ESP outlet of the reverberatory furnace, the acid
plant, and the main stack.  This was done to determine the
compliance status of the copper smelter with the process
weight particulate emission regulation.  During the testing
period, particulate emissions and concentrations of SO-,/H_SO
                                                      *j  ^
and S02 were measured, and the instack sampling method was
compared with EPA Method 5.  Table 3-10 summarizes the
actual time during which test samples were taken at the
reverberatory furnace ESP.  Two trains were used during the
                            3-24

-------
Table 3-10.  SUMMARY OF SAMPLING  TIMES  -
            REVERBERATORY ESP
Run No .
1
2
3
4
5
6
7
8
9
10
11
12
Date
7-20-76
7-21-76
7-22-76
7-23-76
7-26-76
7-26-76
7-27-76
7-28-76
7-28-76
7-29-76
7-29-76
7-30-76
Sampling time
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
A-Port
B-Port
4:15 pm
4:58 pm
5:25 pm
6:00 pm
9:56 am
10:29 am
9:18 am
9:53 am
8:50 am
9:25 am
2:56 pm
3:27 pm
8:35 am
9:08 am
11:13 am
11:44 am
7:16 pm
7:49 pm
10:12 am
10:50 am
4:00 pm
4:34 pm
11:20 am
11:55 am
4:45 pm
5:28 pm
5:55 pm
6:30 pm
10:26 am
10:59 am
9:48 am
10:23 am
9:20 am
9:55 am
3:26 pm
3:57 pm
9:05 am
9:38 am
11:43 am
12:14 pm
7:46 pm
8:19 pm
10:42 am
11:20 am
4:30 pm
5:04 pm
11:50 am
12:25 pm
               3-25

-------
testing:  one sampling train for a combination of EPA
Methods 3 and 4, to measure gas composition moisture con-
tent; and one sampling train for a combination of EPA
Methods 5 and 8, to measure particulate and sulfur oxide
emissions.  The two trains were used simultaneously, one in
each sample port.
     Aerotherm based the following conclusions and observa-
tions on the test results:  a) particulate emissions from
the ESP are much greater than the allowable particulate
emission rate; b) the amount of particulate measured when
using a train with both instack and outstack filters is
consistently higher than the amount measured when using a
sampling train with only an outstack filter (according to
the EPA Method 5 test procedure, required for process weight
emissions regulation); c) particulates captured on both the
instack and outstack filters are hygroscopic in nature, with
a difference between extrapolated and equilibrium weights of
20 to 40 percent on the instack filter and 30 to 50 percent
on the outstack filter; d) a large portion of the particu-
late collected may be sulfuric acid; and e) a chemical
analysis of the particulate should be undertaken to deter-
mine its characteristics.
     To calculate allowable emissions, reverberatory furnace
process weight data were collected for an 8-hr shift on July
26, 1976.  These data are summarized in Table 3-11.
                            3-26

-------
      Table 3-11.  TOTAL SOLID INPUT TO THE REVERBERATORY

    FURNACE DURING SHIFT "A"  (8-HR PERIOD) ON JULY 26, 1976

            (ESTIMATED BY THE PHELPS DODGE STAFF)
Input
Concentrate
Converter slag
Precipitate
Lime
Dust
Total
Quantity
metric tons
159
105
5.4
13.6
7.3
290.3
tons
175
116
6
15
8
320
     The corresponding allowable emission rate based on the
process weight regulation would be 14.15 kg/hr (31.2 Ib/hr).
     It was observed during the sampling program that 2
hours of the total time cycle for normal converter operation
are generally required for a copper-blow.  Table 3-12 records
the test results of a sample train using EPA Methods 3 and
4.  Table 3-13 records the test results of a sample train
using EPA Methods 5 and 8.  Because of the hygroscopic
nature of the particulate matter collected, the filter
gained weight very rapidly during the weighing process by
adsorbing water vapor from the air.  Consequently, no attempt
was made to determine the exact weight of the filter on
completion of sampling.  It was weighed later to calculate
equilibrium weight, from which extrapolated emission weights
were calculated.  Of the 12 measurements taken, Runs 2
through 9 were made by an EPA Method 5 sample train, and the
remaining runs were made by a sample train containing an
instack filter and an outstack filter.  Because of subisokinetic
sampling rates, Runs 1 and 11 on Table 3-13 were rejected.
                           3-27

-------
00
I
N)
00
                  Table 3-12.   SUMMARY OF  SAMPLING DATA USING EPA METHODS  3 AND  4  -


                                  PhELPS JJODGE REVERBERATORY  FURNACE ESP
No.
1
2
3
4
5
6
7
8
9
10
11
12
Date
(1976)
July 20
July 21
July 22
July 23
July 26
July 27
July 28
July 28
July 28
July 29
July 29
July 30
Moisture
%
16.8
12.3
12.3
12.3
12.8
10.1
12.3
9.0
11.1
12.1
11.5
13.8
Vm-dry volume
measured by meter
mJ
1.03
1.27
1.17
1.25
1.13
1.26

1.13
1.41
1.28
1.28
1.28
scf
36.5
44.8
41.3
44.2
39.9
44.7

39.9
49.9
45.2
45.3
45.2
C02
7.
1.0
1.0
3.7
0.9
4.2
4.2
4.2
5.9
6.2
6.3
5.8
5.8
°2
%
18.1
18.1
11.3
18.1
14.0
14.0
14.0
11.3
10.9
10.5
11.5
11.5
Md3
kg/kg mole
or
Ib/lb mole
29.16
28.88
29.05
28.86
29.23
29.23

29.39
29.43
29.43
29.39
29.39
Ms1
kg/kg mole
or
Ib/lb mole
27.29
27.54
28.03
27.53
27.80
28.10

28.36
28.16
28.05
28.08
27.83
VS-gas
velocity
m/sec
23.2
24.8
21.3
25.7
18.8
23.6

27.5
25.4
23.6
23.5
21.9
ft/sec
76.0
81.4
69.9
84.3
61.8
77.4

90.1
83.3
77.5
77.1
72.1
Qs-gas
flow rate
m^/hr scfh
x 10A
8.78
10.2
8.49
10.76
7.93
10.2

11.89
109.8
11.04
11.04
10.2
x 10b
3.1
3.6
3.0
3.8
2.8
3.6

4.2
38.8
3.9
3.9
3.6
                     Md - dry molecular weight.

                     Ms - wet molecular weight.

-------
                          Table  3-13.    SUMMARY OF  PARTICULATE,  S03/H2S04  AND  SO2  EMISSION


                                                 DATA  FOR  REVERBERATORY  FURNACE ESP
Run
No.*
1
2
3
4
5
6
7
8
9
10
11
11
Date
(19761
July 20
July 21
July 22
July 23
July 26
July 26
July 27
July 28
July 28
July 29
July 29
July )0
Extrapolated
weight
1.67 q/m3
(0.731 gr/scf)
1.41 q/m3
(0.617 qr/scf)
1.46 g/m3
10.639 qr/sdf)
0.92 q/m3
(0.400 qr/scf)
1.02 q/m3
(0.444 gr/scf)
1.49 g/m3
(0.651 gr/scf)

i.27 g/m3
(0.555 gr/scfl
1.14 g/m3
(0.500 qr/Bcf)
1.7] q/m3
(0.758 gr/scf)
1.78 q/m3
(0.780 gr/scf)
1.86 g/m3
(0.816 gr/scf)
First
measured
weight
1.68 q/m3
(0.732 qr/scfl
1.41 g/m3
(0.617 qr/scf)
1.46 q/m3
(0.640 qr/scf)
0.92 g/m3
(0.400 gr/scf)
'1.02 g/m3
(0.444 gr/scf)
1.49 q/m3
(0.651 qr/icfl

1.27 q/m3
(0.555 qr/scf)
1.23 q/m3
(0.538 gr/scf)
1.74 q/m3
(0.760 gr/scf)
1.78 g/m3
(0.777 gr/scf)
1.89 g/m3
(0.829 qr/scf)
Equilibr ium
weight
2.14 g/m3
(0.934 gr/scf)
1.72 q/m3
(0.752 gr/scf)
1.83 g/»3
(0.801 gr/acf)
i.40 g/m3
(0.612 gr/scfl
1.55 g/m3
(0.679 gr/scfl
1.95 g/m3
(0.851 qr/scfl

1.49 g/m3
(0.652 qr/scf)
1.64 q/m3
(0.716 qr/scf)
2.24 q/m3
10.980 qr/scf)
2.17 g/m3
10.951 qr/scf)
2.30 g/m3
(1.004 gr/scf)
Extrapolated
we igh t
149 kg/hr
(328.3 Ib/hr)
144 kg/hr
(318.2 Ib/hr)
124 kg/hr
(272.9 Ib/hr)
97.9 kg/hr
(216.2 Ib/hr)
75.2 kq/hr
(175.3 Ib/hrl
150 kq/hr
(330 Ib/hr)

150 kq/hr
(331.3 Ib/hrl
125 kq/hr
(273.3 Ib/hr)
192 kq/hr
(423.0 Ib/hr)
197 kq/hr
(431. 1 Ib/hrl
192.2 kq/hr
(423.9 Ib/hrl
First
measured
weiqht
149 kg/hr
(328.6 Ib/hrl
144 )ta/hr
(318.4 Ib/hr)
124 kq/hr
(273.2 Ib/hrl
97.9 kq/hr
(216.5 Ib/hr)
79.6 kg/hr
(175.6 Ib/hr)
150 kg/hr
(331.1 Ib/hr)

150 kg/hr
(331. 1 Ib/hr)
133 kg/hr
(293.9 Ib/hr)
192 kg/hr
(423.8 Ib/hr)
197 kg/hr
(413.6 Ib/hr)
195 kq/hr
(430.4 Ib/hr)

weight
190 kg/hr
(419.5 Ib/hr)
176 kg/hr
(388.1 Ib/hr)
155 kg/hr
(341.9 Ib/hr)
98.3 kq/hr
(216.5 Ib/hr)
122 kg/hr
(268.4 Ib/hr)
196 kg/hr
(432.8 Ib/hr)

177 kg/hr
(389.9 Ib/hrl
178 kq/hr
(390.9 Ib/hr)
310 kg/hr
(683.8 Ib/hr)
240 kq/hr
(528.2 Ib/hr)
237 kq/hr
(521.6 Ib/hr)


87. 0«
91.41
109.21
92. 0\
107.71
98.81

96.31
104. Ot
92.81
89.71
98.1%
Allowable

14.2 kq/hr
(31.3 Ib/hrl
14.2 kq/hr
(31.4 Ib/hrl
14.3 kg/hr
(31.6 Ib/hr)
14.5 kg/hr
(31.9 Ib/hr)
14.1 kg/hr
(31.2 Ib/hr)
13.8 kg/hr
(30.5 Ib/hr)
14.0 kg/hr
(30.8 Ib/hr)
13.9 kq/hr
(30.7 Ib/hr)
14.4 kq/hr
(31.7 Ib/hr)
14. 3 kg/hr
(31.5 Ib/hr)
14.1 kq/hr
(31.01 Ib/hr)
14.3 kg/hr
(31.6 Ib/hr)
S02
9660 ppm
15,820 ppa
6760 ppra
6340 ppm
4830 ppm
16,190 ppm

5440 ppm
1810 ppm
743Q ppm
3810 ppm
8340 ppm
S°2
emission
2270 kg/hr
(5000 Ib/hr)
4320 kg/hr
(9500 Ib/hr)
1500 kg/hr
(3300 Ib/hr)
1810 kg/hr
(4000 Ib/hr)
997 kg/hr
(2200 Ib/hrl
4320 kg/hr
(9500 Ib/hrl

1720 kq/hr
(3800 Ib/hr)
500 kg/hr
11100 Ib/hr)
21§0 kq/hr
(4800 Ib/hr)
1090 kq/hr
(2400 Ib/hrl
2270 kq/hr
(5000 Ib/hr)
S03/H2SO«
16.4 ppm
49.7 ppm
27.0 ppm
2 . 9 ppm
0 . 0 ppm
32.8 ppm

0 . 0 ppm
42.5 ppm
41.1 ppm
40.6 ppm
44.9 ppm
SOj/H2S04
emiss ion
4.72 kg/hr
(10.5 Ib/hrl
16.9 kq/hr
(31.2 Ib/hr)
7.6 kq/hr
116.8 Ib/hr)
1.04 kq/hr
(2.1 Ib/hr)
0.0 kq 'hr
(0.0 Ib/hr)
10.8 kq/hr
(24.0 Ib.'hrl

0.0 kq/hr
(0.0 Ib/hr)
15.2 kq/hr
(33.7 lb''hr)
15.0 kg'hr
13). 0 Ib/hrl
14.8 Vq/hr
(32.7 Ib/hrl
15.4 kq/hr
1)3, <> Ib/hrl
Ul
I
NJ
          Runs 1  and 11 are re]ected because of subkinetlc conditions.  Runs 10, 11, and 12 were done by using instack/
          outstack filter trains.  Durinq test runs 10 and 12, the particulate emission rate uslnq the inatack filter was
          99.52 1217.2) and 9<>.52 kq/hr  (212.8 Ibs/hr) respectively.

-------
The measurements of Run 7 were not considered, because of
errors in velocity measurements and isokinetic sampling
rates.  The velocity measurement on one of the trains was
low in Run 5, and the measured emission rate reading was
replaced with a corrected emission rate, which is an average
of all particulate emissions collected on the outstack
filters.
     During the test program, Aerotherm observed that, for
                                    P
some undetermined reason, the Teflon  coating on the out-
stack filter holder broke down and flaked at 120°C  (250°F)
in each test.  Since any particulates that may have been
                         R
deposited on these Teflon  flakes would not be included in
the actual particulate measurements, Aerotherm believes the
measured emission rate to be erroneously low.  The magnitude
of this error could not be measured.
     Aerotherm calculated a mean particulate emission rate
of 143.4 kg/hr  (316.1 Ib/hr) and a standard deviation of
32.4  (71.4), using all the valid measurements, including
seven EPA test methods, five runs, and two simultaneous
instack and outstack test runs.
     The data indicated a mean particulate emission rate of
129.5 kg/hr  (285.44 Ib/hr) with a standard deviation of 21.8
(48.13) using EPA Method 5.  Using a 95 percent confidence
level, the limits become 129.5 + 14.4 kg/hr  (285.44 + 31.67
Ib/hr).  A comparison of the average particulate emission
rate of 129.5 kg/hr (285.44 Ib/hr) by EPA Method 5 with the
average particulate emission rate of 192.1 kg/hr (423.45
Ib/hr)  (average of two measurements) by a combination of
instack and outstack filters indicates that about 50 percent
more particulate is collected by the latter than by the
former.  Aerotherm could not explain the weight difference
of the residues from the two sampling trains.
                            3-30

-------
     During  instack/outstack testing, emissions collected on
the instack  filter and residue from the nozzle and probe
were included with the instack filter weight.  The average
particulate  weight collected on the nozzle,  instack filter,
and probe during two  instack/outstack test runs was 96.5
kg/hr  (212.8 Ib/hr),  which  is about 50 percent of the total
collected on the nozzle,  instack filter, probe and outstack
filter.  Comparison of the  average particulate emission of
96.5 kg/hr  (212.8 Ib/hr)  measured on the nozzle, instack
filter, and  probe with the  average particulate emissions of
129.5  kg/hr  (285.44 Ib/hr)  measured by EPA Method 5, shows
that the amount collected by EPA Method 5 is about 134
percent of the amount collected by the former method.
     Calculated mean  emission rates of SO-/H SO. and SO2
from the test data were 11.2 kg/hr  (24.9 Ib/hr) with a 5.62
kg/hr  (12.4  Ib/hr) standard deviation, and 2313.4 kg/hr
 (5100  Ib/hr) with a 1134  kg/hr  (2500 Ib/hr)  standard devia-
tion respectively.
SRI Test Results
     Southern Research Institute performed tests July 9, and
10, 1976, to measure  the  fractional collection efficiency
and the voltage-current characteristics of the ESP system.
A computer simulation of  ESP performance was made simultaneously,
using  a computer system model developed by SRI, and the
inlet  particle size distribution was measured.  The Institute
concluded the following on  the basis of the test results:
a) Measured  efficiency and  design efficiency are identical
within the limits of  experimental error.  (An overall col-
lection efficiency of 96.7  percent was measured by instack
filters, 96.6 percent was calculated from cascade impactor
data,   96.8 is predicted by  the SRI-EPA computer model, and
96.8 percent is the design  efficiency.)   b)  Power supply
versus electrical current characteristics indicates the ESP
                             3-31

-------
is in good mechanical alignment and electrical condition.
c) Particulate resistivity is not limiting the operating
characteristics of the collector,  d) Particle sizes appar-
ently differ in chemical composition.  The mass median
diameter of the inlet particle size distribution was greater
than 10 ym.  The inlet particle distribution was bimodal
with one component having a mass median diameter less than 1
ym.  e) A significant variation in sulfur dioxide concentra-
tion occurs with time.  f) A potential problem with the
application of an ESP to a source of very fine particulate
is presented in suppression of the corona current by a
particulate space charge.  Some reduction in current was
observed at the ESP inlet during the testing, but the degree
of suppression was not large.  This results from the particles
being larger than expected.  Furthermore, the concentration
was rather low, and it was observed that some of the impactor
catches appeared to be hygroscopic.  The difference in the
color of particles noted from stage to stage within the
impactor indicates that their chemical composition was
nonhomogeneous with respect to size.
     Six measurements were made of the particle size distri-
bution during the test, three each at the inlet and outlet,
using a modified Brink cascade impactor.  Southern Research
Institute noted that the validity of the first outlet run
data was questionable because the filter and filtrates for
this run were discovered to be wet when the impactor was
disassembled.  This was probably caused by condensed water
within the probe as it accidentally ran back into the
impactor after being removed from the duct.
     Figure 3-1 presents a plot of the average inlet and
outlet size distributions on a cumulative percentage basis
versus particle size basis for the Phelps Dodge smelter.
Figure 3-2 shows measured and calculated fractional efficiency
                            3-32

-------








Ul
o
QC
LLJ
£X.
UJ
»— l
«C
_l
o













35. 73
99.95
99.9
99.8
99.5
99
98
95
90


80
70
60
50
40
30
20
10
5
2
0.5
0.2
0.1
0.05
0.01
n
1 1
—
-
-
-
-
-
-
-


TlT OUTLET SIZE
rill 1 DISTRIBUTION
Till11
T 1

I1
I
, i X INLET SIZE
T i 1 1 I * l DISTRIBUTION
Ijl
i
_ r
i
X
-
-
_
-
-
» -
1 1 1 1 1 1 II 1 1 1 1 1 1 1 1 II 1 1 1 1 1 1 1 1
10'1 10° 101 10'
                       PARTICLE DIAMETER, ym




   Figure 3-1.  Average  inlet  and outlet particle size



distributions, particle  size vs.  cumulative percent, for



          the ESP at the Phelps Dodge  smelter.
                           3-33

-------
99.99
                                                        0.01
                    1QU    A ^^.^^^^ 1Q,




                     PARTICLE DIAMETER, ym
                                                        10'
Figure 3-2.  Measured and  theoretical fractional efficiency




 curves prepared by SRI  for  the ESP on the reverberatory




           furnace at Phelps Dodge Corporation.
                            3-34

-------
curves for the reverberatory furnace ESP.  The theoretical
curve generated with the SRI-EPA computer model simulation
is predicted for ideal conditions, with no corrections for
rapping losses, poor velocity distribution, or any of the
gas bypassing the active areas.
     The inlet particulate size distribution is bimodal,
with a fine mode having a mass median diameter of 0.8 ym.
Approximately 22 percent of the mass is contained in parti-
cles with diameters smaller than 10 ym  (Figure 3-1) .  The
overall mass median diameter of the inlet particle size
distribution is greater than 10 ym.  It is also evident from
Figure 3-1 that less than 3 percent of the total mass is
0.26-ym in size.  Approximately 80 percent of the total mass
collected at the ESP outlet was under 10 ym in size.  About
26 percent was below 0.26 ym.
     On July 9 and 10, 1976, ESP efficiency measurements of
96.4 and 96.7 percent were made using an impactor train and
96.6 and 96.8 percent using a mass train.  Mass emission
data were provided to SRI by the Radian Corporation from
simultaneously conducted tests.
     Southern Research Institute indicated that the impactor
data may not be reliable, especially regarding particle size
at the ESP outlet, because of their inability to do isokinetic
traverses and the low quantities collected on impactor
stages.  During each sampling, anywhere from one-tenth to a
few tenths milligram weight was collected on each stage.
Figure 3-2, which presents the confidence limits, shows the
unreliability of the data.
     On July 9 and 10, 1976, S0~ sample measurements were
made at the ESP outlet using a sampling system consisting of
a heated, glass-lined sampling probe with a quartz wool
filter, a water-jacketed condenser, and fritted bubbler
                           3-35

-------
containing a 3 percent hydrogen peroxide solution.  The
measurements were made before and after the reverberatory
furnace was charged, because the sulfur oxide concentration
is expected to vary with the furnace operation cycle.  Based
on the test results presented in Table 3-14, SRI speculates
that S02 concentrations in the stack gas are highly vari-
able.
      Table 3-14.  TEST RESULTS - SULFUR OXIDE CONCENTRATION
                     (by volume percent)
Date
7/9/76

7/10/76


Furnace charge cycle
After charging
Before charging
After charging
Before charging
After charging
S02
1.0
0.42
0.73
0.63
1.7
S03
0.024
0.019
0.018
0.025
0.067
     Southern Research Institute concedes that the reliability
of the S03 data cannot be verified because the applicability
of this method of measurement to the nonferrous metal industry
is questionable and the efficiency of the condenser has not
been previously evaluated in this kind of environment;
however,  they do not believe this makes the accuracy of the
S02 measurements suspect.  They do suggest, however, that
accurate  measurement of S03 concentrations with respect to
the furnace operation requires further investigation.
                           3-36

-------
    4.0  ADD-ON CONTROL SYSTEM FOR PARTICULATE EMISSIONS

     As explained in Section 2.0, the principal reverbera-
tory furnace exhaust gases at the Magma Copper Company and
Phelps Dodge Corporation smelters pass through waste-heat
boilers, after which the partially cooled gases are treated
in ESP's before being vented through a stack.  The ESP's
were designed to treat the flue gases at a temperature of
316°C  (600°F).  The efficiency was to be determined by using
the ASTM test method.  This method specifies that partic-
ulate loading of the flue gas be measured at a process gas
temperature, which is about 316°C (600°F) at these two
smelters.  The copper reverberatory furnaces at these
smelters are presently subject to compliance with EPA
Process Weight Regulation 40 CFR 52.126(b), which requires
the flue gas particulate content to be measured at about
120°C  (250°F) in accordance with EPA Method 5.  Most of the
flue gas particulate matter at these two smelters, as
measured by Method 5, is composed of material that has
condensed from the vapor phase to the solid or liquid phase
when the gas temperature is reduced from 316°C (600°F) to
120°C  (250°F) in the sampling apparatus.  Numerous sampling
tests conducted for EPA by different organizations have
shown that the reverberatory furnaces at the Magma Copper
and Phelps Dodge smelters are emitting more particulate
matter than allowed by the EPA Process Weight Regulation.
     The EPA decided to evaluate the feasibility of upgrading
control systems of these smelters as a means of meeting
emission standards, and also (with the assistance of IGCI)
                             4-1

-------
to evaluate new control alternatives if upgrading proves
impractical.  The EPA provided various sampling test data
obtained at the two smelters for examination by IGCI and
PEDCo.  Based on the limited information provided and their
best judgment, IGCI members believe each of the smelters can
comply with EPA regulations by installing an additional
control system in series with the ESP already in operation.
     Effective particulate control can be achieved by first
cooling the gas from the existing ESP outlet, then applying
available control techniques such as electrostatic pre-
cipitation, filtration, or scrubbing.  IGCI suggested one of
the following add-on control systems be installed in series
with the existing ESP's:
     a)   Gas cooling equipment to reduce flue gas tempera-
          ture to 120°C (250°F)  and a fabric filter to
          reduce the flue gas dust loading to an allowable
          level.
     b)   Gas cooling equipment to reduce flue gas tempera-
          ture to 120°C (250°F)  and a wet scrubber system to
          reduce the flue gas dust loading to an allowable
          level.
     c)   Gas cooling equipment to reduce flue gas tempera-
          ture to 120°C (250°F)  and a dry ESP to reduce the
          flue gas dust loading to an allowable level.
     d)   Gas cooling equipment to reduce flue gas tempera-
          ture to 120°C (250°F)  and a wet ESP to reduce the
          flue gas dust loading to an allowable level.
     PEDCo also analyzed the sampling test data provided by
EPA and developed technical specifications for the add-on
control systems.
     The specifications, which included data on flue gas
exiting from the existing ESP such as volume flow rate,
inlet gas loadings, allowable emissions, moisture content,
and gas composition, were issued to selected IGCI members.
They were asked to furnish capital and annual operating cost
                            4-2

-------
data for the add-on control systems specified.  All provided
costs for both gas cleaning equipment and auxiliary equipment,
and some also provided direct and indirect cost items as
well as annual operating cost data.
     More definitive information on the nature of the flue
gas would help in the development of precise technical and
economical add-on particulate control systems for the smel-
ters.  Pilot plant studies of add-on control systems could
determine their feasibility, optimum sizing, system pressure
drop, and efficiency.  Gas composition varies with raw
materials, operating conditions, furnace production cycle,
and also between smelters.  Separate tests at the individual
smelters, relating the emissions rate and composition with
the smelter operating cycle, might provide better information
on which to base control evaluations.  The test program
could also be extended to estimate condensation points of
individual trace elements present in the gas and the dew
point of the gas stream.
     As mentioned previously, available data on the existing
control systems at the Magma and Phelps Dodge smelters
suggest that most of the particulate matter measured by EPA
Method 5 was present as vapor at 316°C (600°F), but was
condensed to a solid or liquid at 120°C (250°F).   The process
weight regulation requires flue gas particulates to be
measured at 120°C (250°F) for compliance.   If compliance is
to be achieved, the gas must be cooled and the volatile
compounds condensed before the gas passes through the add-on
control equipment.   This can be accomplished by evaporative
cooling, dilution,  or convection/radiation heat exchange.
Because control by scrubbing is a wet operation,  the gases
are cooled by water as they pass through a quencher or
scrubber.
     Evaporative cooling with water (also known as spray
cooling)  has two principal advantages.   First, this type of
                             4-3

-------
cooling does not greatly increase the gas volume, and
second, it requires relatively little space.  Consideration
must be given to water availability and corrosion protection,
however, when analyzing an evaporative cooling system.
     Gas cooling with dilution air is the simplest method,
but it is not economical because it greatly increases the
gas volume flow rate to the add-on control system.  This
increased flow rate greatly increases the size and cost of
the control device, and it could necessitate modifications
to or replacement of the existing stack.   Increased gas
volumes would also decrease particulate concentrations in
the gas at the inlet of the control system, thereby making
it more difficult to achieve high particulate removal effi-
ciencies.
     Air-to-air heat exchangers have economic limitations
and are disadvantageous for cooling larger gas volumes.
They require a great deal of space, and the installed cost
of this type of heat exchangers is also higher than any
other cooling method.
     Gas cooling by natural convection and radiation, causes
the duct to become hot (because of the hot gas flowing
through it), and it heats the surrounding air.  Natural
drafts are formed as the temperature of the air increases,
carrying the heat away from the ducts.  Heat is also discharged
by radiant heat to the area surrounding the hot duct.  Both
temperature decreases in the hot gas flowing through a short
duct length and temperature increases in the surrounding air
are limited.
     Those IGCI members who recommended dilution air cooling
expressed the belief that this is the only technically
feasible cooling method,  despite obvious disadvantages.
They rejected spray cooling because it would require the
control device to be operated at a temperature lower than
                            4-4

-------
the acid dew point.  They  rejected  the  air-to-air heat
exchanger because the  skin temperature  of the heat transfer
surface would be below the acid dew point of the gas.
     Data are not available on gas  dew  points for the smelters.
However, calculations  based on gas  composition data  indicate
that the flue gas dew  point is above  120°C  (250°F).  This
could create corrosion problems in  gas  handling and  treatment
equipment.  Some copper  smelters that cool  gases to  temperatures
as low as 93°C  (200°F) before treatment use brick-lined
flues and a brick and  mortar stack  with acid-proof lining.
     At one copper  smelter, gas from  the fluid bed reactor,
electric furnace, and  converters is treated in a fabric
filter control  system; at  three other smelters the gases are
treated in a cold ESP.   No wet scrubbers are used to control
emissions from  copper  reverberatory furnaces in the  United
States.  According  to  some IGCI members, fabric filters have
been successfully used to  clean reverberatory furnace gases
at smelters in  Canada.
     An add-on  control system must  be equipped with  a fan to
handle the additional  pressure drop across the system (a few
inches W.C. when ESP's or  fabric filters are used, and up to
100 inches W.C. if  scrubbers are used).  When the fan is
located upstream of the  control system, the volume of gas
flow is large (because the  gas is at high temperature).
When the fan is located  downstream  of the control system, it
does not have to handle  such a large gas flow (because the
gas is at low temperature); however, the control device must
be of a heavier construction and reinforced because  it must
withstand high  negative  pressures.  In either case,  the fan
must be insulated for  protection against corrosion or constructed
of corrosion-resistant materials.   The duct work must also
be well insulated.
                              4-5

-------
     The following section presents evaluations of different
add-on control systems for application at the Magma Copper
Company and Phelps Dodge Corporation smelters in question.
4.1  ADD-ON CONTROL SYSTEMS FOR MAGMA COPPER COMPANY, SAN
     MANUEL, ARIZONA
     The reverberatory furnace flue gas is now treated in a
hot ESP, which operates at 300°C (573°F)  and has a design
removal efficiency of 98 percent (measured by the ASTM in-
stack methods).   (This efficiency has never been verified by
actual ASTM testing.)  In EPA Method 5 sampling tests, the
flue gas volume flow rate measured 18,264 m /min (645,000
acfm) at 300°C (573°F), and particulates averaged 1.76 g/m
(0.77 gr/scf) at 120°C (250°F), with a maximum of 2.9 g/m
(1.25 gr/scf) at the outlet of the ESP.  The allowable
particulate emission rate for the furnace is 18 kg/hr (39.7
Ib/hr) or 0.032 g/m  (0.014 gr/scf).  Thus, additional
particulate matter control with an average efficiency of
98.18 percent (maximum 98.88 percent) is required for com-
pliance.  The three units of the hot ESP are situated in
parallel (west to east),  and the stack is located to the
north.  These units operate under negative pressure without
a fan.
     Enough space is available for add-on control equipment
south of the existing SCRA* pilot plant.   Evaluations of
different add-on control for the Magma smelter reverberatory
furnace are discussed in this section.  Magma Copper Company
is planning to convert the reverberatory furnaces from gas
and oil firing to coal firing.  The evaluations of add-on
control systems in this section do not apply to conditions
that will prevail after the reverberatory furnaces have been
converted to coal.
*
 Smelter €ee^d-iaa%iftg- Research Association.
                             4-6

-------
Add-on Fabric Filter Control System
     Appendix B presents an add-on fabric filter control
system specification for Magma Copper Company-  Based on
their best judgment, two IGCI members evaluated a system
according to this specification.  Table 4-1 presents the
design parameters for these evaluations.
     Evaluation A on this table involves a system designed
to cool gases from the hot ESP to 120°C (250°F) in a spray
cooling chamber, then to treat the gases in a fabric filter.
Design and instrumentation of the spray chamber must be
precise to keep the exit gas in dry condition.  The chamber
is a cocurrent spray tower made of carbon steel with a
brick-lined bottom.  The top of the chamber requires no
lining.  The gas transportation portion downstream of the
chamber is properly lined to resist corrosion.  Bag material
is fiberglass to insure that no damage occurs if the cooling
system fails.  The baghouse external wall is constructed of
insulated carbon steel.
     Evaluation B involves a system designed to cool the hot
ESP exit gas to 120°C  (250°F) by the addition of dilution
air and to treat the gas in a fabric filter system equipped
with dacron bags.  The dilution air cooling increases the
volume of gas to be treated to about four times that of the
original volume exiting the hot ESP.  The bidder expressed
his belief that although dilution air cooling greatly in-
creases the size and cost of the collection equipment, it is
technically superior to the spray chamber or the air-to-air
heat exchanger.  The inlet and outlet plenums and the plate
compartment walls of the baghouse system are made of 3/16-
in. A36 material.  A mineral wool insulation 3 in. thick and
aluminized steel logging are used in the baghouse.
     The best solution for temperature control appears to be
                             4-7

-------
       Table 4-1.   DESIGN  PARAMETERS  OF ADD-ON  CONTROL

       FABRIC  FILTER SYSTEM  FOR MAGMA COPPER  SMELTER.
       Parameter
                                       Evaluation A
                                                                      Evaluation B
System description



Gas volume flow  rate from the
existing ESP  to  cooling
system:

  Actual conditions

  Standard conditions

  Temperature

  Moisture content

Particulate loading :

  Concentration

  Weight rate

Type of cooling

Number of units

Dimensions of each  unit

Water consumption

Dilution air

Fabric Filter System

Total volume  flow from cooling
system to add-on fabric filter
system:

  Actual conditions

  Standard conditions

  Temperature

  Moisture content
Filter type

Air-to-cloth  ratio  (net)

Air-to-cloth  ratio  (gross)

No. of compartments  (net)

No. of compartments  (gross)

Cleaning mechanism

Fan:  Location

      Number

      Pressure drop

      Power required  (total)
Spray water cooling of gas to
120°C (250°F).  fabric filter
followed by a fan
18,264 m3/min (645,000 acfm)

9,316 m3/min (329,000 scfra)

300°C (573°F)

8.7%



1.762 g/m3 (0.77  gr/scf)

979 kg/hr (2158 Ib/hr)

Concurrent water  spray cooling

2

6.1 m x 21.3 m (20  ft x  70  ft)

61.32 m3/hr (270  gpm)
13,400 m /rain  (474,640 acfm)

10,039 m3/min  (354,310 scfm)

120°C (250°F)

21.1%

Fiber glass

2:1



34
Reverse air

Downstream of the  system

3

2.985 kPa (12 in.  W.C.)

1100 kw (1475 HP)
Air dilution of gas  to 120°C
(250°F), fabric filter followed
by a fan
18,264 nT/min (645,000 acfm)

9,316 m3/min (329,000 scfra)

300°C (573°F)

8.7%



1.762 g/m3 (0.77 gr/scf)

979 kg/hr (2158 Ib/hr)

Dilution air
                               2652 m /min (936,500 scfm)
49,554 nr/min (1,750,000 acfm)

36,990 m3/min (1,306,000 scfm)

120°C (250°F)

2.2%

Combination dacron

1.49:1

1.37:1

38

41

Shaker type

Downstream of the system

8

2.737 kPa (11 in. W.C.)

4705.4 kW (6310 HP)
                                       4-8

-------
a combination of spray cooling and dilution cooling.  Cal-
culations show that cooling the gas to 204°C  (400°F) by
water evaporation, then to 120°C  (250°F) by air dilution,
would increase the gas volume to 23,530 m3/min (831,000
acfm), which is only about 50 percent of that which would be
produced by complete reliance upon air dilution cooling.
Add-on Fabric Filter Control System Costs
     Tables 4-2 and 4-3 present a capital and annual operat-
ing cost breakdown for Evaluations A and B.  These evaluations
represent the cost of equipment as of the last quarter of
1977.  Only basic equipment is included; no spares are
represented in these costs.  Duct costs are estimated on the
basis of 110 m (360 ft) of duct from the existing ESP outlet
to the inlet flange of the system, an appropriate length
within the system, and a return duct of 107 m (350 ft) from
the system outlet to the existing stack.  Capital charges in
the annual operating costs were calculated as 17.5 percent
of total turnkey costs.  This rate is based on a 10 percent
interest rate, 15 years equipment life, and 4.3 percent for
taxes and insurance.
     The data show that an add-on fabric filter system to
enable Magma Copper Company to comply with the applicable
emission regulations will entail capital costs of $337.73 to
$854.52 per m3/min  ($9.56 to $24.20 per acfm) of ESP exhaust
gas, depending on the type of cooling system included and
based on a gas flow rate of 18,264 m /min  (645,000 acfm).
System A, which contains a spray chamber for gas cooling and
a fabric filter for particulate control, costs $337.73 per
m /min ($9.56 per acfm) of gas introduced into the system.
System B, which uses dilution air cooling for gas temperature
reduction and a fabric filter for particulate control, costs
$854.52 per m /min  ($24.20 per acfm)  of gas introduced into
                             4-9

-------
           Table  4-2.    CAPITAL COST  DATA FOR ADD-ON  CONTROL

             FABRIC  FILTER  SYSTEM FOR MAGMA  COPPER SMELTER.
       Parameter
                                       Evaluation A
                                                                       Evaluation B
 System description



 Inlet gas flow :

   Actual  conditions

   Standard conditions

   Temperature

   Moisture content

 Contaminant loading :

   Inlet,  concentration

   Inlet,  flow rate

   Outlet, concentration

   Outlet, flow rate

 Cleaning  efficiency,  %
Spray water cooling  of  gas to
120°C (250°F).  fabric filter
followed by a  fan
13,440 mj/min  (474,640 'acfm)

10,000 m3/min  (354,310 acfm)

120°C (250°F)

21.1%



1.6 g/m3 (0.716 gr/scf)

989 kg/hr (2180 Ib/hr)

0.028 g/m3  (0.012 gr/scf)

18.0 kg/hr  (39.7 Ib/hr)

98.2         	
Air dilution of gas  to  120°C
(250°F), fabric filter  followed
by a fan
49,550 mj/min (1,750,000  acfm)

36,980 m3/min (1,306,000  acfm)

120"C (250°F)

2.2%



0.71 g/m3 (0.310  gr/scf

1599 kg/hr (3524  Ib/hr)

0.0092 g/m3 (0.004  gr/scf)

18.0 kg/hr (39.7  Ib/hr)

98.8	
 Gas cleaning equipment cost

 Cost of auxiliaries:

   Fan w/drive

   Screw conveyor/air lock

   Cooling tower/accessories

 Total equipment cost

 Installation costs,  direct:

   Foundation and supports

   Duct workc

   Stack

   Piping

   Insulationd

   Painting

   Electrical

   Other

 Total direct costs

 Installation costs,  indirect

   Engineering

   Construction & field expenses

  'Construction fees

   Start-up

   Performance test

   Contingencies

Total indirect  costs

Turnkey  cost
         $1,447,500



            143,400

             58,800

            263,100

         $1,912,800




         ?   114,800

          1,412,000

                  0

             19,100

            378,800

             47,800

            210,400

            475,000

         $2,657,900




         $   187,500

            994,600

            296,500

             25,500

             17,000

             76,500

         $1,597,600

         $6,168,300
         $6,200,000



          1,000,000

                  a



         $7,200,000
          2,387,000

                  0

                  b

          2,053,000

                  b

                  b

          3,483,000

        $ 7,923,000




                  d

                  d

                  d

        $    22,000

             30,000

            432,000

        $   484,000

        $15,607,000
|* Included in gas cleaning equipment.
  Included in others.
f Includes material  and  labor, necessary
  For gas cleaning equipment only.
6 Included with direct cost.
         insulation, and lining of duct.
                                           4-10

-------
      Table  4-3.   ANNUAL  OPERATING  COST  DATA  FOR ADD-ON

              FABRIC FILTER  FOR  MAGMA  COPPER  SHELTER.
       Parameter
                                       Evaluation A
                                                                      Evaluation  B
System description



Inlet gas flow :

  Actual conditions

  Standard conditions

  Temperature

  Moisture content

Contaminant loading :

  Inlet, concentration

  Inlet, flow rate

  Outlet, concentration

  Outlet, flow rate

Cleaning efficiency

Operating hours  per year
Spray water  cooling of gas to
120°C (250°F),  fabric filter
followed by  a  fan
13,440 nr/min  (474,640 acfm)

10,000 m3/min  (354,310 scfm)

120°C (250°F)

21.1%



1.6 g/m3 (0.716  gr/scf)

989 kg/hr (2180  Ib/hr)

0.028 g/m3  (0.012  gr/scf)

18.0 kg/hr  (3y./ ic/nr)



      8760
                            Air dilution of gas  to  120°C
                            (250°F), fabric filter  followed
                            by a fan
                            49,500 m /min (1,750,000 acfm)

                            36,980 m3/min (1,306,000 scfm)

                            120°C (250°F

                            2.2%



                            0.71 g/m3 (0.310 gr/scf)

                            1599 kg/hr  (3524 Ib/hr)

                            0.0092 g/m3 (0.004  gr/scf)

                            18.0 kg/hr  (39.7 lo/nr)
                                                                    8760
DIRECT COSTS

Operating labor:

  Operator, SlO/man-hour

  Supervisor,  512/man-hour

  Total

Maintenance:

  Labor,  SlO/man-hour

  Materials

  Total

Replacement parts

Utilities

  Electricity, S0.03/kWh

  Water,  SO.25/1000  gal.

  Compressed  air,  50.02/1000  ft3

  Total

Total direct  costs :

  Capital charges

  Total annual cost
 1,

SI.
543,800

  8,800

 52,600



 43,800

  1,900

 45,700
 59,500



473,700

 36,400



510,100

667.900

079,300

747,200
   S41,600



    41,600



   315,500

     4, 200

   319,700
         a



 1,375,000

         a

       500

 1,375,500

$1,716,900

 2,731,200

S4,468,000
a Included in  maintenance  labor.
                                        4-11

-------
the system.  The respective gas cleaning equipment  (including
auxiliaries)  costs are 31 percent of the total turnkey
capital costs for Evaluation A and 46 percent for Evaluation
B.  Annual operating costs of particulate removal are $0.21/kg
($0.09/lb), or $4787/day, for Evaluation A, and $0.32/kg
($0.15/lb), or $12,241/day, for Evalulation B.  Utility
costs and capital charges represent about 91 percent of the
total annual operating costs for Evaluation A and 92 percent
for Evaluation B.
Add-on Wet Scrubber Control System
     Appendix B contains a specification for an add-on wet
scrubber system at the Magma Copper smelter.  Based on this
specification, three bidders used their best judgment to
evaluate the scrubber system.
     Although all three evaluations are based on the same
specification, they are not comparable because the individual
systems are designed for different pressure drops (AP)
across the system.  Pressure drop is a principal design
parameter of a system, usually determined by particle size
distribution and chemical analysis of the particulate
matter.  Because of a lack of sufficient data on these
parameters, the bidders used their experience and judgment
to determine pressure drop.  Table 4.4 presents design
parameters of these evaluations (C, D, and E).
     In Evaluation C, ESP exhaust exit gas is treated in two
identical scrubber units, each containing a quencher, an
adjustable venturi, a flooded elbow, and a mist eliminator
followed by two fans.  Each unit treats half of the total
volume flow,  which is 9132 m /min (322,500 acfm).   Estimated
pressure drop for this system is 24.9 kPa (100 in. W.C.).
The quencher is fabricated of carbon steel at least 1/2 in.
thick.  The inlet flow passage to the quencher, the outlet
                             4-12

-------
                        Table  4-4.   ADD-ON  CONTROL SCRUBBER  SYSTEM DESIGN  PARAMETER FOR

                                                        MAGI1A COPPER  SMELTER
                         Parameter
.to.
 I
                  System description
Gas volume  flow rate from the
existing  ESP  to the system:

  Actual  conditions

  Temperature

  Standard  conditions

  Moisture  content

Particulate loading:3

  Concentration

  Weight  rate

Number of units

Gas volume  flow rate to
quencher/prequencher in each
unit:

  Actual  conditions

  Temperature

  Standard  conditions

Quencher  dimensions


Evaporative water addition to
                                                         Evaluation  c
                               A prequencher,  an adjustable
                               venturi,  a  flooded elbow, and
                               a mist eliminator separator
                               followed  by two fans
                                                 18,264 m /rain (645,000 acfm)

                                                 300°C (573°F)

                                                 9260 m3/min (327,000  scfm)

                                                 8.7%
                                                 1.762 g/mj (0.77 gr/scf)

                                                 979 kg/hr (2158 Ib/hr)

                                                 2
                                                 9075 m /rain (320,500  acfm)

                                                 300°C (573°F)

                                                 4630 m3/min (163,500  scfm)

                                                 3.2 m x 1.07 m (10.5  ft  x
                                                 3.5 ft)

                                                 34.1 m3/hr  (150 gpm)
                                                                                        Evaluation  D
A fan,  a separate  quencher, and
a venturi scrubber
18,264 m /min (645,000 acfm)

300°C (573°F)

9260 m3/min (327,000  scfm)
                                                                                8.7%
1.762 g/m3 (0.77 gr/scf)

979 kg/hr (2158  Ib/hr)

2
9075 m3/min (320,500  acfm)

300°C (573°F)

4630 m3/min (163,500  scfra)

4.6 m x 11.6 m (15 ft x  38  ft)


51.1 m3/hr (225 gpm)
                                                                                                                        Evaluation E
A prequenpher,  a venturi, and
a separator  followed by a fan
18,264 nT/min  (645,000 acfm)

300°C (573°F)

9260 m3/min  (327,000 scfm)
                                                                                                                8.7%
1.762 g/mj (0.77  gr/scf)

979 kg/hr (2158 Ib/hr)

1
9075 m /min (320,500  acfm)

300°C (573°F)

4630 m3/min (163,500  scfm)

5.03 m x 12.2 m (16.5 ft  x
40 ft)

-------
  Table  4-4  (continued).
        Parameter
                                        Evaluation C
                                                                        Evaluation  D
                                                                                                        Evaluation E
 Gas  volume  flow  rate at scrub-
 ber  exit  in each unit:

  Actual  conditions

  Temperature

  Standard  conditions

  Moisture  content

  Particulate loading

 Scrubber  system  clean effi-
 ciency

 Scrubbing water  quantity
 (recycled)

 Venturi scrubber rate

 Makeup water addition rate

 Total scrubber pressure drop

 Scrubber  dimensions


 Demister  dimensions
Fan location

Number of fans per unit

Estimated power required
9872 iri /min (349,160 acfm)

52°C (125°F)

10,800 m3/min (382,220 scfm)

12.94%

0.032 g/m3 (0.014 gr/acf)


98.2%

35.77 m3/min (9450 gpm)


35.7 m3/min (9430 gpm)

1.19 m3/min (314 gpm)b

24.9 kPa (100 in. W.C.)

7.6 m x 10.7 m n 16m  (25 ft x
35 ft x 53 ft)

3.4 m x 5.2 m x  0.6 m (11  ft  x
17 ft x 2 ft)


Downstream of the scrubber

2

2790 kW (3750 HP)
6625 m3/rnin (233,970  acfm)

64°C (148°F)

4660 m3/min (164,500  scfm)

25.4%

0.032 g/m3 (0.014  gr/acf)


99.0%

6.18 m3/min (1635  gpm)
6.2 m3/min (1640 gpm)

1.92 m3/min (503 gpm)c

14.92 kPa (60 in. W.C.)

5.9 m x 11.6 m (19 ft 6  in.  x
38 ft 5 in.)

5.9 m x 0.025 m (19 ft 6 in.  x
1 in. high)
Upstream of the scrubber

1

3251 kW (4360 HP)
11,950 m /min (421,900 acfm)

60°C (140°F)

11,150 m3/min (393,740 scfm)
0.032 g/rrT (0.014 gr/scf)
Minimum 98.2
11.34 m /min (3000 gpm)
1.02 m3/min (280 gpm)

6.47 kPa (26 in. W.C.)

9.1 m x 18.2 m  (30 ft x 60 ft)


9.14 m dia. (30 ft dia.)
18.2 overall length  (60 ft
overall length

Downstream of the system

1

2050 kW (2750 HP)
a Maximum particulate loading during furnace charging is 2.86 g/m  or 1584 kg/hr (1.25 gr/scf or 3504 Ib/hr)

  68.4 m /hr (303 gpm) water for evaporation into the gas in quencher and 2.3 m /hr (10.1 gpm)  water to make up for
  that removed from the system for treatment.
c 101 m3/hr (450 gpm) water for evaporation into the gas in quencher and 14.4 m3/hr (63 gpm)  water to make up for
  that removed from the system for treatment.

-------
flow passage  from  the venturi  to  the  flooded elbow, and
the flooded elbow  itself are all  fabricated of carbon steel
at least 1/2  in. thick, lined  with Ceilcote.  The venturi
scrubber is fabricated of  1/2-in. thick Grade B or Grade C
steel plate.   The  converging throat and diverging sections
are lined with silicon carbide brick.  The wetted parts of
the fan are made of  316 L  SS.
     The system in Evaluation  D contains two scrubber units,
each with a fan and  separate quencher  followed by a venturi
scrubber.  This system operates at a  pressure drop of 14.94
kPa  (60 in. W.C.).   The bidder believes this pressure drop
and associated power requirements could be significantly
lower, and that a  pilot test should be conducted to determine
actual pressure drop.  The preconditioner is constructed of
mild steel with a  Gunite or Savereisin acid-resistant
cement lining.  Flow velocities are low to reduce abrasive
wear.  The scrubber  would  be constructed of 316 L stainless
steel unless  the scrubbing water  is high in chlorides.
     The one-unit  scrubber system in  Evaluation E consists
of a prequench section, a  venturi, and a separator section
followed by a  fan.   The pressure drop of this system is 6.47
kPa  (26 in. W.C.).   The bidder indicated that some study has
been made regarding  the scrubbing of reverberatory furnace
gases in copper smelters;  and, based on limited scrubbing
pilot plant data,  he believes  that a pressure drop of 6.47
kPa  (26 in. W.C.)  is a reasonable choice to produce 96 to 98
percent efficiency by weight.  The general material of
construction is acid-brick-lined steel; the hot gas zones
and high-velocity  sections of  the scrubbers are constructed
of FRP-lined steel.  All alloy parts in the venturi are of
Inconel 625.    The  fan wheel and shaft will be supplied in
Incoloy-825 or  904L material.  Inlet ducting is a 1/4-in.
and 3/8-in. carbon steel with  exterior weatherproof insula-
tion.  The material  of construction for the prequencher and
                             4-15

-------
venturi is 1/4-in. and 3/8-in. carbon steel with 60- to 80-
mil flaked-glass lining plus 3-in. acid brick and foam glass
interior lining.  Alloy parts are of Inconel 625.  The
separator is 1/4-in.,  3/8-in. and 1/2-in. carbon steel with
60- to 80-mil flaked glass lining.  The base of the separator
mill is lined with 3-in. acid brick up to 2 ft. above gas
inlet.  The exit ducting to the fan and stack is of 5/8-in.-
thick FRP-Hetron 197 with flame retardant.
     Carbon steel is the material of construction for the
water treatment systems in all evaluations.
     Based on these evaluations, it is apparent that pilot
plant tests are necessary to produce a wet scrubber with the
desired efficiency.
Add-on Wet Scrubber Control System Costs
     Tables 4.5 and 4.6 present capital and annual operating
costs for the three systems.  These evaluations represent
the cost of equipment during the last quarter of 1977.  They
include only basic equipment (no spare equipment).   The
following parameters were used in the duct cost estimate:
a duct length of 110 m (360 ft) from the existing ESP exit
to the add-on control system inlet, an appropriate duct
length within the system, and a return duct of 107 m (350
ft) from the add-on system outlet to the existing stack.
Capital charges in the annual operating costs were calculated
by using 20.5 percent of the total turnkey cost.  This rate
is based on an interest rate of 10 percent, an equipment
life of 10 years, and a tax and insurance rate of 4.22
percent.
     Data show that the turnkey capital cost of an add-on
scrubber system ranges from $218 to 279 per actual cubic
meter/min ($6.18 to 7.89 per acfm) of gas entering the
system.  The individual turnkey capital cost estimates are
$264.13, $218.24, and $278.69 per actual cubic meter/min
                             4-16

-------
                    Table  4-5.   CAPITAL COST  DATA FOR ADD-ON  CONTROL  SCRUBBER SYSTEM  FOR

                                                        MAGMA COPPER  SMELTER
                     Parameter
£>.
I
System description




Gas flow at scrubber outlet;

  Actual conditions

  Temperature

  Standard conditions

  Moisture content

Contaminant loading:

  Inlet

  Inlet

  Outlet

  Outlet

Cleaning efficiency
               Gas cleaning equipment cost

               Cost of  auxiliaries:

                 Fan with drive

                 Pumps

                 Tanks
                                d
                 Water  treatment

                 Others
                                                     Evaluation C
                                             A prequencher, an adjustable
                                             venturi, a flooded elbow,  and
                                             a mist eliminator separator
                                             followed by two fans
                                              19,744 m /min (698,330  acfm)

                                              51.6°C (125°F)

                                              10,800 m3/min (382,220  scfm)

                                              12.44%
                                              1.76 g/m   (.77 gr/scf)

                                              984.31 kg/hr  (2170 Ib/hr)

                                              0.032 g/m3  (0.014 qr/scf)

                                              18.01 kg/hr  (39.7 Ib/hr)

                                              98.2%
                                          $506,000



                                        $1,183,000

                                            20,000

                                              c

                                           126,000

                                            89,000€
                                                                                    Evaluation  D
A fan,  a separate quencher, and
a venturi scrubber
13,250 m /min  (467,941 acfm)

64°C (148°F)

9320 m3/min  (329,000 scfm)

Saturated
1.76 g/m  (.77  gr/scf)

984.31 kg/hr (2170 Ib/hr)

0.032 g/m  (0.014 gr'/scf)

18.01 kg/hr (39.7 Ib/hr)

98.2%
           $273,600



           $661,400

             29,000

            118,000

            121,300

             75,700
                                                                                                                    Evaluation E
A prequencher,  a venturi, and
a separator followed by a fan
11,950 m3/min  (421,900 acfm)

54.4°C (130°F)

10,050 m3/min  (354, 780 scfm)
1.76 g/m  (0.77  gr/scf)

984.31 kg/hr  (2170 Ib/hr)

0.032 g/m3  (0.014 gr/scf)

18.01 kg/hr (39.7 Ib/hr)

98.2%
         $1,000,000



           $340,000

             50,000

             20,000

            150,000

-------
                 Table  4-5  (continued).
 I
M
CO
Parameter
Total equipment cost
Installation costs, direct:
Foundation and supports
Duct work
Stack
Piping
Insulation^
Painting
Electrical
Other
Total direct costs
Installation cost, indirect:
Engineering
Construe. & fields expenses
Construction fees
Start-up
Performance test
Contingencies
Total indirect costs
Turnkey cost
Evaluation C
51,924,000

S 106,300
2,000,000
0

75,000
12,100
7,600
172,900
$2,373,900

$ 35,400
374,400
5,100
25,300
35,400
50,600
526,200
$4,824,100
Evaluation D
$1,279,000

$ 90,000
2,402,000
0
65,000
25,000
12,800
36,200

$2,631,000

$ 22,000
20,000
5,000
7,000
12,000
10,000
76,000
$3,986,000
Evaluation E
$1,560,000


1,737,000






$l,793,000h








$5,090, 000
                  a Particulate content of the  gas at the inlet and outlet  is based on the gas  flow  rate of 9260 m /min
                    (327,000 scfm) to the system.
                    Includes preconditioning equipment  (quencher),  scrubber, and associated tanks.
                    Included in the gas cleaning equipment cost.
                    Materials and labor.
                  e Piping and instrumentation.
                    Includes material and labor, and necessary insulation and lining of duct.
                  g For gas cleaning equipment.
                  ^ Includes total of direct costs and  indirect costs,  excluding foundation and duct costs.

-------
 Table  4-6.    ANNUAL OPERATING COST  DATA FOR ADD-ON  CONTROL  SCRUBBER FOR

                                      MAGMA COPPER  SMELTER
       Parameter
                                      Evaluation
                                                                     Evaluation D
                                                                                                     Evaluation  E
System description




Gas flow  at scrubber outlet:

  Actual  conditions

  Temperature

  Standard conditions

  Moisture content

Contaminant loading : a

  Inlet

  Inlet3

  Outlet

  Outlet3

Cleaning  efficiency

Operating hours per year
A prequencher,  and adjustable
venturi,  a flooded elbow, and
a mist eliminator separator
followed  by two fans
19,744 m /min  (698,330 acfm)

51.6°C (125T)

10,800 m3/min  (382,220 scfm)

12.44%
1.76 g/m  (0.77  gr/scf)

984.31 kg/hr (2170  Ib/hr)

0.016 g/m3 (0.014 gr/scf)

18.01 kg/hr (39.7 Ib/hr)

98 .2%

8760
A fan,  a separate quencher, and
a venturi scrubber
13.250 m /min  (467,941 acfm)

64°C (148°F)

9320 m3/min  (329,000 scfm)

Saturated
1.76 g/m  (0.77 gr/scf)

984.31 kg/hr  (2170 Ib/hr)

0.018 g/m3  (0.014 gr/scf)

18.01 kg/hr (39.7 Ib/hr)

98.2%

8760
A prequencher,  a venturi, and
a separator  followed by a fan
11,950  m /min  (421,900 acfm)

54.4°C  (130°F)

10,050  m3/min  (354,780 scfm)
1.76 g/m  0.77 gr/scf)

984.31 kg/hr  (2170 Ib/hr)

0.032 g/m  (0.014 gr/scf)

18.01 kg/hr  (39.7 Ib/hr)

98.2%

8760
DIRECT COSTS

Operating labor:


  Operator,  ?10/man-hour

  Supervisor,  $12/man-hour

  Total
  $122,200

    37,000

   159,200
   587,600

    24,000

   111,600
   $27,100

     9,700

    36,800

-------
             Table 4-6  (continued).
 i
NJ
O
Parameter
Maintenance:
Labor, SlO/raan-hour
Materials
Total
Replacement parts
Utilities :
Electricity, SO.Ol/kWh
Water
Chemical water treatment
Total direct cost
Capital charges
Total annual cost
Evaluation c

59,200
41,000
100,200
26,000

3,136,000
31,500
24,200
$3,477,100
989,000
54,466,100
Evaluation D

3,600
3,000
6,600
20,000

1,744,100
53,900
9,500
51,945,700
817,100
52,762,800
Evaluation E

27,100
18,500
45,600
18,500

479,800
29,400
31,800
5641,940
1,043,600
| 51,685,500
               Particulate content of the gas at the  scrubber  inlet and outlet is based on the gas  flow rate
               9260 m3/min (327,000 scfra) to the system.

-------
 ($7.48, $6.18, and  $7.89 per acfm) of gas entering the
 system for Evaluations C, D, and E respectively.  Gas flow
 rate to each system is 18,264 m3/min  (645,000 acfm).  Cost
 of gas cleaning equipment, including auxiliaries, varies
 from 30 to 40 percent of the total turnkey cost.  The respec-
 tive annual operating costs for the three systems are $0.53,
 and $0.33, and $0.20/kg  ($0.24, $0.15,  and $0.09/lb) of
 particulate removed, or  $12,236, $7,569, and $4,618 per day.
 Utilities and capital charges represent 71 percent and 22
 percent in Evaluation C, 65 percent and 29 percent in
 Evaluation D, and 32 percent and 62 percent in Evaluation E.
 Add-on Dry ESP Control System
     Appendix B contains specifications for an add-on dry
 ESP for the Magma Copper Smelter.  Using their best judgment,
 three members of IGCI evaluated the requirements based on
 information given to them.  Table 4-7 presents design para-
 meters of the add-on dry ESP system.
     Evaluations F, G, and H all involve two parrallel
 systems, each containing a fan, a cooling system, and an
 ESP.  The fan is placed on the hot side of the cooling
 system to avoid a potential corrosion and imbalance problem.
 Design and instrumentation of the cooling system must be
 precise to keep the exit gas dry.  A pilot study of the ESP
 is recommended to assess the corrosive and sticky nature of
 the dust.
 Add-on Dry ESP Control System Costs
     Tables 4-8 and 4-9 present capital and annual operating
 cost breakdowns for Evaluations F, G, and H.  The evaluations
 represent the cost of equipment during the last quarter of
 1977.   They include only basic equipment (no spare equipment).
 Duct costs in the three estimates are based on 110 m (360
 ft)  of duct from the existing ESP outlet to the inlet of the
add-on control system, an appropriate length within the
                             4-21

-------
Table 4-7.  DESIGN  PARAMETERS OF ADD-ON DRY ELECTROSTATIC PRECIPITATOR SYSTEM
                           FOR MAGMA COPPER SMELTER
Parameter
System description

Gas volume flow rate fro* the
cipitator to cooling systemi
Under actual condition*
Under standard condition*
Temperature
Type of cooling
Number of unit*
Dimensions of each unit

Hater consumption
cooling systems to add-on
electrostatic precipitator;
Under actual conditions
Under standard conditions
Number of ESP's
Dimension of each

Number of chambers per ESP
Number of fields
Number of passages per
chamber
Length of each field
Field height
number of energizing Means
Current
Voltage
Have form
Migration velocity
Specific collecting area,
net
Total power consumption (ESP)
ran: location
number
Pressure drop
t>ow*r rnquiz-ed
Evaluation T
A fan, evaporative cooling to
120'C <250»r), a dry electro-


IB, 264 »3/»in (645,000 acfn)
9316 B3/»in (329,000 scfrn)
300'C (575'F)
6 7%
Evaporative cooling
2


34.1 m3/hr (150 gpn)


14,470 n3/min (511,000 acini)
10,601 B3/min (381,450 ecfm)
1 20"C ( 250*F)
2
19.8 m x 15. e n -A 15.5 n
(65 ft x 52 ft x 51 ft)«
2
S»
31

2.74 m (9.0 ft)
9.1 B (30 ft)
10
1500 BA
70 kv
Pull
3.96 cm/» <0.13 ft/«)
103.2 B2 p«r •'/• (52< ft2/
1000 acfnic
1400 kH (1170 HP)
Hot fit* of cooling «y«t««
2
O.995 fcPa 14 in. M.C.)
448 kH (fiOO HP)
Evaluation G
A fan, an avaporativa cooling
tower, followed by dry elec-


18,264 n'/nin (645,000 act*)
9316 n'/min (329,000 icfm)
300'C (573T)
8 7%
Evaporative cooling
2
1.99 n dia x 25.5 n length
(29.5 ft dia x 83.6 ft length)
25 m3/hr (110 gpn)


14,040 B3/min (495.830 «cf»)
10,481 B3/min (370,137 acf«)
120*C (250*F)
2
26.5 B L x 14.63 n H
(87.1 ft L x 48.7 ft t»)
1
5b
46

3.61 ro (12.5 ft)
9.40 » (30.83 ft)
10
1250 BA
56 kV
Full
3.41 oo/l (0.112 ft/«)
111 •' per •'/• (597 ft2/
1000 acfii)d
1995 kW (2665 HP)
Hot side of cooling •yateai
3
429 let! (575 -HP)
Evaluation H
A fan, concurrent flow cooling
tower to iii'C (250*F), a dry


11,2(4 »3/»in (64.5,000 acfm)
*31( »3/»in (329,000 acfm)
JOO'C (573T)
1.7%
evaporative cooling
2


34.1 »3/hr (150 gpn)


13,567 m3/nin (479,106 acfm)
9401 •3/min (332,000 acfm)
120*C (250"F)
2


1
3
44

3.24 • (10.625 ft)
10.97 B (36 ft)

3327 BA
45 kV
mil
4.14 CB/l (0.158 ft/a)
12.* B2 per B3/« (421 ft2/1000
•CfB)
1100 kH {1475 HP)
•ot vide of cooling «yeteB
2
l.TH kcPa 17.3 in. N.C.)
44B KM (600 RP)

-------
 I
to
u>
                         Table   4-8.      CAPITAL  COST  DATA   FOR  ADD-ON   DRY  ELECTROSTATIC   PRECIPITATOR

                                                                     SYSTEM  FOR  MAGMA  COPPER  SMELTER
                                               the  aya ten.
                                             b Includes screw conveyor.,
                                             c Access and dust disposal.
                                               Slide gates and dampers.
Parameter
Inlci gas (low:
Standard conditions
Temperature
Contaminant loading •*
Inlet, wt . rate
Outlet, concentration
Out let , wt . rate




Others

Foundation and supports
(MiL)«
Duct work
Stack
Piping
Insulation
Painting
Other

Engineering
Construction fees
Start-up
Model study


Evaluation F
14,470 nVrain (511,000 acfm)
10,801 n3/min (381, 450 «cfm>
102'C <250'F)
984.31 kg/hr (2170 lb/hr(

98.2%
223,000
3B4,OOOb
52.978,000
S 29), 000
1.504,000
0
Not quoted
0
Not quoted
1 , 570, 5009
S3, 367, 500
3
3
3
S 2S.OOO
1
15,000
210,000
S 120,000
'».. bbS.SOO
Evaluation G
14,040 n3/min 1495,810 acf»!
10,481 m3/Bin (370,137 scfnl
120'C (250'F)
i .76 g/mj (0.77 gr/scf )
0.032 q/m3 (0.014 gr/scf)
99.21
11,960,000
300,000
661,000
300,000C
53,423,000
S 216,000
1,513,800
0
Not quotvd
0
Not quoted
417,400
l,829,000h
53,996,200
S 308,000
235,000
84,000
25,000
15,000
50,000
305,000
SI, 022. 000
Si, 441, 100
evaluation H
tator
j
120'C (250T)
1.76 g/«3 (0-77 gr/scf)
984.31 kg/hr 12170 Ib/hr)

98 .21
271,400
683,000
211 ,600d
$3,219,000
S 11.200
1,497,000
0
Not quote J
0
336,000
Not quoted
1,792,000'
53,706,200
k
S 132,000
11,800
51, iOO
358, 300
1 453,700
S ' . 17t . $00
                                             f
                                                                   la
' Irutallatlon labor tor 4** cl*aninq *quip»«nt and •uiiliarl"*
 About  92.5 p«rcant for inctallation oC total gas cleaning «qu
 and r««aininq for Iralqht on *quip^nt
 Included in others.
 Included in vquipSMnt coat.
 Included In co«t of start-up.

-------
    Table 4-9.   ANNUAL  OPERATING  COST DATA FOR ADD-ON CONTROL
       DRY ELECTROSTATIC PRECIPITATOR FOR MAGMA COPPER SMELTER
Parameter
Inlet gas Mow

Temperature
Contaminant loading3
Inlet, wt. rate
Outlet, wt. rate
Cleaning efficiency
Operating hours per year
DIRECT COSTS
Operating labor
Operator, $10/man-hour
Supervisor, 521/man-hour
Total
Maintenance
Labor, SlO/man-hour
Materials
Total
Replacement parts'
Utilities
Electricity, $0.03/kWh
Hater, SO. 25/1000 gal
Total
Total direct costs
Capital charges
Total annual cost
Evaluation P
120°C (250-n, a dry electro-
static precipitator
14,470 m3/min (511,000 acfm)
10,801 m3/min (381,450 scfml
120°C (250°F)
1.76 g/m3 (0.77 gr/scf)
984.31 kg/hr (2170 Ib/hr)
0.032 g/m3 (0.014 gr/scf)
18.01 kg/hr (39.7 Ib/hr)
98. 2»
8760


521,500
4,400
25,900

11,000
7,800
18,800
5,200

367,900
19,700
387,600
437,500
51,166,500
51,604,000
Evaluation G
tower, followed by dry electro-
1«,040 m3/min (495, B30 acfm]
10,481 mj/min (370,137 scfml
120°C (250°F)
1.76 g/m3 (0.77 gr/scf)
984.31 kg/hr (2170 Ib/hrl
0.032 g/m3 (0.014 gr/scfl
18.01 kg/hr (39.7 Ib/hr)
98.2%
8760


532,000
4,500
36,500

12,600
7,800
20,400
b

524,300
14.500
538,800
595,700
51,477, 200
52,072 . 900
Evaluation H
A fan, concurrent flow cool-
ing tower to 120°C (250°F)
tator
13,567 m3/min (479,106 acfm)
9401 m3/min (332,000 scfm)
120*C (250°F)
1.76 g/m3 (0.77 gr/acf)
984.31 kg/h (2170 Ib/hr)
0.032 g/m3 (0.014 gr/scf)
18.01 kg/hr (39.7 Ib/hr)
98.24
8760


$11,000
4,500
15,500

8,000
4,500
12,500
4,500

290,000
19,700
309,700
142,200
51,291,300
51,633, 500
                                                        , 000 S(.-fmJ to
the system.
Included in maintenance.

-------
system, and a return duct of  107 m  (350  ft) from the system
outlet to the existing stack.  Capital charges in the annual
operating costs were calculated by using 17.5 percent of the
total turnkey costs.  This rate is based on a 10 percent
interest rate, 15 years of equipment life, and a rate of
4.35 percent for taxes and insurance.
     The data show the use of an add-on dry ESP system to
enable Magma Copper Company to comply with the applicable
emission regulation will entail capital costs of $365 to
$462 per m /min  ($10.00 to $13.00 per acfm) based on exist-
ing ESP exhaust gas flow rate of 18,264 m /min (645,000
acfm).  The respective turnkey capital costs are $365 per
 3                                                   3
m /min ($10.33 per acfm) for Evaluation F, $462 per m /min
($13.00 per acfm) for Evaluation G, and $404 per m /min
($11.44 per acfm) for Evaluation H.  The respective gas
cleaning equipment costs are 45 percent of the total turnkey
capital costs for Evaluation F, 41 percent for Evaluation G,
and 44 percent for Evaluation H.  Annual operating costs of
particulate removal are $0.19/kg ($0.09/lb), or $4480/day,
for Evaluation F and Evaluation H, and $0.25/kg ($0.11/lb),
or $5679/day, for Evaluation G.  Utility costs and capital
charges represent about 97 percent of the total annual
operating costs for Evaluation F and Evaluation G, and 98
percent for Evaluation H.
Add-on Wet Electrostatic Precipitator (WEP) Control System
     Appendix B contains specifications for an add-on wet
ESP at the Magma Copper smelter.  Table 4-10 presents the
design parameters of one WEP system (Evaluation I).  The
system involves a WEP designed to cool gases from the exist-
ing ESP in an evaporative cooling tower to 120°C (250°F) ,
then to treat the gases in a WEP.   The evaluation involves
two parallel systems consisting of a fan, an evaporative
                             4-25

-------
Table  4-10.    ADD-ON CONTROL WET ELECTROSTATIC  PRECIPITATOR

       SYSTEM  DESIGN  PARAMETERS FOR MAGMA COPPER  SMELTER
                    Parameter
                                                          Evaluation I
      System description



      Gas volume flow rate from  the existing
      electrostatic precipitator to system:

        Actual  conditions

        Standard conditions

        Temperature

        Moisture content

      Cooling system: type

        Number  of units

        Dimensions of each unit

        Liquid- to-gas ratio,  L/G

      Electrostatic precipitator system

      Total volume flow rate at  add-on pre-
      cipitator system inlet or  at gas cool-
      ing system outlet:

        Actual  conditions

        Standard conditions

        Temperature

      Number of ESP's

      Number of chambers per ESP

      Number of fields per ESP

      Number of passages per chamber

      Length of each field

      Field height

      Number of energizing means

      Current

      Voltage

      Wave form

      Migration velocity

      Spray water

      Flush water for inlet transition

      Flush water for ESP plates3

      Specific collecting area

      Fan:  Location

            Number

            Pressure drop

            Power required
Two units  each consists of a fan,  an
evaporative  cooling tower, and a wet
electrostatic precipitator
18,151 m /min  (641,000 acfro)

9313 m3/min  (328,877 scfm)

300°C (573°F)

8.7%

Evaporative  cooling tower

2

8.99 m x 25.98 m  (29.5 ft x 83.6  ft)

        3     3
0.0974 m  per m /min (355 gal/1000  acfm)
14,040 m /min  (495,830 acfm)

10,480 m3/min  (370,137 scfm)

120°C (250°F)

2

1

4a

31

3.33 m (10.92  ft)

9.40 m (30.83  ft)

4

200 mA

55 kV

Full

0.079 m/s (0.262 ft/s)

5686 m /min  (1502 gpm)

1567 m3/min  (414 gpm)

15,490 m3/min  (4092 g.pm)

49.6 m2 per  m3/s  (253 ft2/1000 acfm)

Hot-side cooling tower

2

1.99 kPa (8  in. W.C.)

429 kW (575  HP)
        One field  is redundant.
                                           4-26

-------
cooling tower, and a WEP.  The  fan  is located upstream of
the cooling system to prevent a potential corrosion problem.
The WEP is generally chosen when the particulate tends to be
sticky and does not drop when the plates of a dry ESP are
rapped.  The WEP  is a continuously  sprayed, horizontal flow,
parallel plate, and rigid frame discharge electrodes type.
Water from a precisely designed water nozzle arrangement is
sprayed at the WEP entrance to maintain a low resistivity of
the particles entering into the system.  Water sprays located
above the electrostatic field sections introduce evenly
distributed water droplets to the gas stream for washing all
internal surfaces.  The particulates and water droplets in
the electrostatic fields pick up charges and migrate to the
collecting plates.  The plates are  continuously flushed to
remove the collected material into  the troughs below which
are sloped to a drain.  The WEP parts not sprayed or flushed
with water are constructed of corrosion-resistant materials.
(The portion close to outlet of WEP is not sprayed or
flushed with water in order to remove the carryover liquid
drops and mists before the outlet of the equipment).  The
condensible material collected in the drain liquor can be
separated by means of any sludge removal methods.
Cost of Add-on Wet Electrostatic Precipitator System
     Tables 4-11 and 4-12 present capital and annual operat-
ing cost breakdowns for evaluation  I.  The evaluation re-
presents the cost of equipment during the last quarter of
1977.  It includes only basic equipment (no spares).  Duct
costs in all three evaluations are based on 110 m  (360 ft)
of duct from the existing ESP outlet to the inlet flange of
the gas cooler,  an appropriate length within the system,  and
a  return duct of 107 m (350 ft)  from the system flange to
                            4-27

-------
Table  4-11.   CAPITAL COST  DATA  FOR ADD-ON WET ELECTROSTATIC
           PRECIPITATOR  SYSTEM  FOR  MAGMA  COPPER  SMELTER
                   Parameter
         System  description
         Inlet  gas flow:
          Actual  conditions
          Standard conditions
          Temperature
         Contaminant loading:
          Inlet,  concentration
          Inlet,  wt. rate
          Outlet, concentration
          Outlet, wt. rate
         Cleaning efficiency
         Gas cleaning equipment cost
         Cost of auxiliaries:
          Fan with drive
          Evaporative cooling tower
        •  Water treatment
          Others
         Total equipment cost
         Installation costs,  direct:
          Foundation and supports
          Duct work
          Stack
          Piping
          Insulation
          Painting
          Electrical0
          Otherd
         Total direct costs
         Installation costs,  indirect:
          Engineering
          Construction and field expenses
          Construction fees
          Start-up
          Performance test
          Model study
          Contingencies
         Total indirect costs
         Turnkpy rost-
                                                              Evaluation  I
Two units.   Each  consists of a fan,  an
evaporative cooling tower, and a wet
precipitator
14,010 m /min  (495,830 acfm)
10,481 m3/min  (370,137 scfm)
120°C (250°F)

1.76 g/m3 (0.77 gr/scf)
984.31 kg/hr  (2170 Ib/hr)
0.032 g/m3  (0.014 gr/scf)
18.01 kg/hr  (39.7 Ib/hr)
98.2%
        $1,284,000

           300,000
           863,000

            83,000
        $2,530,000

        $  103,500
         1,455,900
            0

           650,000

           206,000
         1,162,000
        $3,577,400

        $  327,000
           160,000
            60,000
            25,000
            15,000
            50,000
           246,000
        $  883,000
        $6,990,400
          Particulate content  of  the gas at the inlet and outlet  is based on a gas flow rate
         b of 9260 m3/min (327,000 scfm) to the system.
          Includes only material  and labor for precipitator supports.
         j Includes material  and  labor and necessary insulation  and lining.
          Installation costs for  gas cleaning equipment,  auxiliaries, fan, and cooling tower.
                                           4-28

-------
Table  4-12.   ANNUAL  OPERATING  COST  DATA FOR ADD-ON WET

   ELECTROSTATIC  PRECIPITATOR FOR  MAGMA  COPPER SMELTER
         Parameter
                                                    Evaluation I
     System description



     Inlet gas flow:

      Actual conditions

      Standard conditions

      Temperature

     Contaminant loading:

      Inlet , concentration

      Inlet, wt. rate

      Outlet, concentration

      Outlet, wt.  rate

     Cleaning efficiency

     Operating hours  per  year
Two units.  Each consists  of a fan, an
evaporative cooling tower,  and a wet
electrostatic precipitator
14,040 m /min  (495,830 acfm)

10,481 m3/min  (370,137 scfm)

120°C (250°F)



1.76 g/m3 (0.77 gr/scf)

984.31 kg/hr  (2170 Ib/hr)

0.032 g/m3  (0.014 gr/scf)

18.01 kg/hr  (39.7 Ib/hr)

98.2%

8760
     DIRECT COSTS

     Operating labor:

      Operator, $10/man-hour

      Supervisor,  $12/man-hour

      Total

     Maintenance:

      Labor, $10/man-hour

      Materials

      Total

     Replacement parts

     Utilities:

      Electricity,  $0.03/kWh

      Water, $0.25/1000  gal

      Chemicals

      Total

     Total direct costs:

      Capital charges

      Total annual  cost
      $ 21,400

         3,000

        24,400



         8,400

         5,200

        13,600

          b



       414,800

       471,000



       885,800

      S 923,800

     1,223,300

    S2,147,100
     Paniculate  content of the gas  at the inlet
     of 9260 m3/min  (327,000 scfm) to the system

     Included in  maintenance.
                                               and outlet  is based on a  gas  flow rate
                                         4-29

-------
existing stack flange.  Capital charges in the annual
operating costs were calculated by using 17.5 percent of the
total turnkey costs.  This rate is based on 10 percent
interest, 15 years of equipment life, and 4.35 percent for
taxes and insurance.
     The data show that the use of an add-on WEP system
(Evaluation I) by Magma Cooper Company to comply with the
applicable emission regulation entails a capital cost of
$382.74 per m3/ min ($10.84 per acfm) of ESP exhaust gas
(based on a gas flow rate of 18,264 m /min (645,000 acfm).
This system uses an evaporative cooling system to cool the
gas to 120°C  (250°F) before it enters the WEP.  Cost of gas
cleaning equipment  (including auxiliaries)  is 36 percent of
the total turnkey capital cost.  Annual operating costs of
particulate removal are $0.25/kg ($0.12/lb)  or $5883 per
day.  The utility costs and capital charges are about 41
percent and 57 percent of the total annual operating costs,
respectively.
4.2  ADD-ON CONTROL SYSTEMS FOR PHELPS DODGE CORPORATION,
     AJO, ARIZONA
     The reverberatory furnace flue gas is treated in a hot
ESP consisting of two independent,  parallel units (north of
the furnace) followed by a fan and stack.   The ESP operates
at about 316°C (600°F) with a design removal efficiency of
96.83 percent (measured by ASTM instack method).  The
efficiency was tested and verified by Southern Research
Institute and Radian Corporation in July 1976.  EPA Method 5
sampling tests at the existing ESP exit measured a flue gas
                                                      C
                                                      3
volume flow rate of 5270 m /min (186,000 acfm) at 314°C
(598°F),  average dust particulate loadings of 1.28 g/m"
(0.56 gr/scf)  at 120°C (250°F), and maximum particulate
loadings  of 3.14 g/m  (1.37 gr/scf).  Mass emissions aver-
aged 203  kg/hr (447 Ib/hr)  at 120°C (250°F);  the maximum was
496 kg/hr (1094 Ib/hr).   Compliance with particulate regu-
                             4-30

-------
lations require an additional control of  93.0 percent
efficiency during normal operation and  97.15 percent during
furnace charging.
     Enough space is available  for an add-on control system
north of the existing ESP.  Water availability is supposedly
limited.  Evaluations of different add-on control for the
Ajo smelter reverberatory furnace are discussed in this
section.
Add-on Fabric Filter Control System
     Appendix C presents the specification for a fabric
filter add-on control system at the Phelps Dodge Corporation
smelter.  Three IGCI members used their best judgment to
evaluate a system based on this specification.  Table 4-13
presents design parameters of the systems evaluated.
     Evaluation J is for a system consisting of a spray
tower to cool gases from the existing hot ESP to 120°C
(250°F), followed by a fabric filter for particulate con-
trol.  The chamber is a cocurrent spray tower made of
carbon steel with a brick-lined bottom.  The gas transporta-
tion system (i.e., ductwork, fans and control devices)
downstream of the chamber is properly lined to resist corro-
sion.  Fabric filter bags are fiberglass to insure that no
damage occurs if the cooling system fails.
     Evaluation K involves a system designed to cool the hot
ESP exit gas to 120°C (250°F)  by adding dilution air, then
treating the gas in a fabric filter system containing dacron
bags.  Dilution cooling increases the original gas volume of
5670 m3/min (186,000 acfm)  to 14,000 m /min (495,000 acfm).
The bidder expressed his belief that although dilution air
cooling greatly increases the size and cost of the collec-
tion equipment,  it is technically superior to the tower and
air-to-air heat exchanger.   The inlet and outlet plenums and
                             4-31

-------
                   Table  4-13.    DESIGN  PARAMETERS  OF AN ADD-ON  FABRIC  FILTER  SYSTEM  FOR

                               THE  PHELPS DODGE CORPORATION SMELTER IN AJO, ARIZONA
                               Parameter
 1
U)
NJ
System description



Gas volume  flow rate from  the
existing electrostatic precip-
itator to cooling system:

  Actual conditions

  Standard  conditionsa

  Temperature

  Moisture  content

Particulate loading:

  Concentration

  Weight rate

Type of cooling

Number of units

Dimension of each


Water consumption

Dilution air
                                                              Evaluation J
                                                       Spray water cooling of gas to
                                                       120°C (250°F),  a  fabric filter,
                                                       followed by a fan
5270 m /min  (186,000  acfm)

2639 rnVmin  (93,176 scfrn)

314"C (598°F)

12.3%



1.28 g/m3  (0.56 gr/scf)

202.85 kg/hr (447.2 Ib/hr)

Concurrent waterspray cooler

1

7.01 m (23 ft) diameter
24.9 m (82 ft) overall height

0.31 m /min  (82 gpm)
                                                                                           Control system
                                                                                            Evaluation K
                              Dilution air cooling of gas to
                              120°C  (250°F),  a  fabric filter,
                              followed by a fan
5270  m /min (186,000  acfm)

2639  m3/min (93,176 scfm)

314°C (598°F)

12.3%



1.28  g/m3  (0.56 gr/scf)

202.85 kg/hr (447.2 Ib/hr)

Dilution air

-------
                 Table  4-13  (continued).
                                 Parameter
 I
U)
OJ
Total volume flow rate  from
cooling system exit to  add-on
fabric filter system:

  Actual conditions

  Standard conditions3

  Temperature

  Moisture content

Filter type

Air-to-cloth ratio (net)

Air-to-cloth ratio (gross)

No. of compartments (net)

No. of compartments (gross)

Pressure drop across the
system

  Cleaning mechanism

Fan:

  Location

  Number

  Pressure drop
                                                                  Evaluation J
                                                          3700 m /min  (130,690 acfm)

                                                          2763 m3/min  (97,558 scfm)

                                                          120°C (250°F)

                                                          25.3%

                                                          Fiberglass

                                                          2:1



                                                          10
                                                          Reverse air

                                                          Downstream of the system

                                                          1

                                                          2.99 kPa (12 in W.C.)

                                                          298 kW (400 hp)
                                                                                                Control system
                                                                                                 Evaluation K
14,000 m3/min (495,000  acfra)

10,460 m3/min (369,500  scfm)

120°C (250°F)

3.0%

Combination dacron

1.60:1

1.46:1

10

11
Shaker type

Downstream of the system

3

2.74 kPa (11 in.  W.C.)

1175 kW (1575 hp)
                             Standard  conditions are 101.3 kPa (14.7 psia)  and 21°C  (70°F)

-------
the plate compartment walls are of 3/16 in. A36 material.
A 3-in.-thick mineral wool insulation and aluminized steel
lagging are used for baghouse.
Add-on Fabric Filter Control System Cost
     Tables 4-14 and 4-15 present the capital and annual
operating costs for the two systems evaluated (design evalua-
tions are in Table 4-13).  The evaluations represent the
cost of equipment for the last quarter of 1977.   They
include only basic equipment (no spare equipment).  The duct
cost items in the three evaluations are based on a 24 m  (80
ft) straight duct length from the existing ESP outlet to the
inlet flange of the system, an appropriate length within the
system, and a return duct of 34 m (110 ft) from the outlet
to the existing stack.  Capital charges in the annual oper-
ating costs were calculated by using 17.5 percent of the
total turnkey costs.  This rate is based on 10 percent
interest rate, 15 years of equipment life, and a 4.35 per-
cent rate for taxes and insurance.
     The cost estimate data show that treating furnace gas
in an add-on control system (Evaluation J) consisting of a
fabric filter preceded by a water spray tower for cooling
the gas to 120°C (250°F) costs about half of what it costs
to treat the gas in a fabric filter preceded by air dilution
for cooling the gas (Evaluation K).   The turnkey capital
cost of treating gas from the existing ESP outlet by the
system in Evaluation J is $380.11 per m /min ($10.77 per
acfm); by the method in Evaluation K this cost is $751.58
per m /min ($21.30 per acfm).  The total cost of gas clean-
ing equipment (including auxiliaries) is about 37 percent of
the total turnkey cost in Evaluation J and about 57 percent
in Evaluation K.  Annual operating cost for particulate
removal is about $0.14/kg ($0.06/lb), or $1607/day, for the
                             4-34

-------
               Table  4-14.    CAPITAL  COST DATA FOR ADD-ON CONTROL  FABRIC  FILTER  SYSTEM
                                     FOR  PHELPS  DODGE CORPORATION  SMELTER
                     Parameter
 I
U)
ui
System description


Inlet gas flow:3
  Actual conditions
  Temperature
  Standard conditions
  Moisture content
Contaminant loading:
  Inlet, concentration
  Inlet, weight rate
  Outlet, concentration

Cleaning efficiency
                 Gas  cleaning equipment cost
                 Cost of  auxiliaries:
                   Fan w/drive
                   Screw  conveyor w/air lock
                   Cooling  tower w/accessories
                 Total equipment cost
                                       Evaluation  J
                                              Spray water cooling of gas to
                                              120°C  (250°F), a fabric filter,
                                              followed by a fan
                                              3700  m  /min  (130,690 acfm)
                                              120°C (250°F)
                                              2760  m3/min  (97,558 scfm)
                                              25.3%
3.07  g/mJ  (1.34 gr/scf)
508 kg/hr  (1120 Ib/hr)
0.082 g/m3  (0.036 gr/scf)
13.6  kg/hr  (30.0 Ib/hr)
97.3%
                                       3498,000

                                         47,800
                                         17,300
                                        168,200
                                       5731,300
                                         Control system
                                          Evaluation K
                                  Dilution air cooling of gas to
                                  120°C  (250°F), a fabric filter,
                                  followed by a fan
                                  14,020 m /min  (495,000 acfm)
                                  120°C  (250°F)
                                  10,460 m3/min  (369,500 scfm)
                                  3.0%
                                                                                0.792 g/m   (0.346 gr/scf)
                                                                                497  kg/hr  (1095 Ib/hr)
                                                                                0.023 g/m3  (0.01 gr/scf)
                                                                                13.6 kg/hr  (30.0 Ib/hr)
                                                                                97.3%
                                          51,960,000

                                             310,000
                                                c
                                                c
                                          S2,270,000
                 (continued)

-------
               Table 4-14  (continued).
i
U)
Parameter
Installation costs, direct:
Foundation and supports
Duct work
Stack
Piping
Insulation
Painting
Electrical
Other
Total direct costs
Installation costs, indirect:
Engineering
Constr. and field expenses
Construction fees
Start-up
Performance test
Contingencies
Total indirect costs
Turnkey cost
Evaluation J

$ 45,000
188,300
0
7,500
162,200
18,800
82,500
135,000
$ 639,300

73,500
390,000
116,400
12,700
10,000
30,000
$ 632,600
$ 2,003,200
Control system
Evaluation K


$ 241,000
0

394,800


1,034,000
$1,669,800

c
c
c
11,000
10,000
d
$ 21,000
$3,960,800
                To fabric filter from cooling system.
                Based on gas conditions  at fabric filter  inlet.
                Included in others.
                By others.

-------
           Table  4-15.   ANNUAL  OPERATING COST  DATA FOR ADD-ON CONTROL FABRIC FILTER FOR
                                       PHELPS DODGE  CORPORATION SMELTER
 I
U)
-J
                       Parameter
                  System description
Inlet gas  flow:
  Actual conditions
  Temperature
  Standard conditions
  Moisture content
Contaminant loading:
  Inlet, concentration
  Inlet, weight  rate
  Outlet,  concentration

Cleaning efficiency
Operating  hours  per year
                  DIRECT COSTS
                  Operating  labor:
                    Operator, $10/man-hour
                    Supervisor,  $12/man-hour
                    Total
                                                         Evaluation J
                             Spray water cooling  of gas to
                             120°C (250°F),  a  fabric  filter,
                             followed by a fan
                                               3700 m /min  (130,690 acfm)
                                               120°C (250°F)
                                               2760 m3/min  (97,558 scfm)
                                               25.3%
3.07  g/m  (1.34 gr/scf)
508 kg/hr  (1120 Ib/hr)
0.082 g/m3  (0.036 gr/scf)
                                               13.6 kg/hr
                                               97.3%
                                               8760
           (30.0 Ib/hr)
                                       $29,200
                                         7,200
                                        36,400
                                                                        Control  system
                                                                         Evaluation  K
                                  Dilution  air cooling of gas to
                                  120°C  (250°F), a fabric filter,
                                  followed  by a  fan
                                  14,020  m  /min  (495,000 acfm)
                                  120°C  (250°F)
                                         3
                                  10,460  m  /min
                                  3.0%
              [369,500 scfm)
0.792  g/m   (0.346 gr/scf)
497 kg/hr  (1095  Ib/hr)
0.023  g/m3  (0.024 gr/scf)
13.6 kg/hr  (30.0 Ib/hr)
93.0%
8760
                                            $20,800
                                             20,800
                   (continued)

-------
                Table 4-15  (continued).
i
OJ
CO
Parameter
Maintenance :
Labor, $10/man-hour
Materials
Total
Replacement parts
Utilities:
Electricity, $0.03/kWh
Water, $0.025/1000 gal
Total
Total direct costs:
Capital charges
Total annual cost
Evaluation J

30,200
700
30,900
17,500

140,400
10,800
151,200
$ 236,000
350,600
$ 586,600
Control system
Evaluation K

4,200
84,600
88,800


260,000
0
260,000
$ 369,600
693,100
$1,062,700
                 To fabric  filter from cooling system.

                 Based on gas conditions  at fabric filter inlet.

-------
system in Evaluation J and $0.25/kg  ($0.11/lb), or $2912/day,
for the system in Evaluation K.  Utilities costs represent
about 25 percent of total annual operating costs for both
systems.
Add-on Wet Scrubber Control System
     Appendix C contains a specification for an add-on wet
scrubber system at the Phelps Dodge  smelter.
     Three bidders used their best judgment to evaluate the
scrubber system on the basis of this specification.  Their
evaluations are not comparable, however, because the in-
dividual systems are designed for different pressure drops
(AP) across the system.  System pressure drop, a principal
design parameter, is usually determined by particulate size
distributions and chemical analysis.  Because of lack of
sufficient data on these parameters, the bidders used their
experience and judgment to determine pressure drop.  Table
4-16 presents the design parameters of these evaluations
(Evaluations L, M, and N).
     In Evaluation L, ESP exhaust gas is treated at a rate
of 5270 m /min (186,000 acfm) in a scrubber system consist-
ing of an adjustable throat venturi, a flooded elbow, and an
entrainment separator followed by a fan.  Estimated pressure
drop for this system is 17.43 kPa (70 in. W.C.).  The
venturi scrubber is made of 1/4-in.  316L SS.  The flooded
elbow, inlet and outlet transition pieces leading to and
from the flooded elbow, the mist eliminator, and all connec-
tions are of 1/4-in. carbon steel with Ceilcote lining.
     The scrubber system in Evaluation M consists of a fan
and a quencher, followed by a venturi scrubber.  This
system operates at a pressure drop of 14.94 kPa (60 in.
W.C.).  The bidder believes this pressure drop and asso-
ciated power requirements could be significantly lower, and
                             4-39

-------
                   Table 4-16.  DESIGN PARAMETERS OF ADD-ON SCRUBBER SYSTEM FOR



                                 PHELPS DODGE CORPORATION SMELTER
 I
*>
o



system3
Actual conditions
Standard conditions
' P
P rt te lo d ng.
Weight rate
Quencher dimensions
to gas in the quencher
Number of units
Gas volume flow rate at
scrubber exit:
Actual conditions
Temperature
Standard conditions
Moisture content
Pressure drop across scrub*
her

Weight rate
Scrubbing system cleaning
efficiency
(recycled)
Venturi scrubber, water rate
Makeup water addition rate
Total scrubber pressure drop
Demister dimensions
Fan location
Number of fans per unit
Total power required



followed by a fan
5270 m3/mm (186,000 acfm)
314°C (598"F]
2639 m3/mm (93,176 scfm)
12.5
1.28 g/m3 (0.56 gr/scf)
199.04 kg/hr (438.8 Ib/hr)
2.44 in IE 0.20 m x 5.56 in
(8 ft :c 0.67 ft x 18.25 ft)
0.37 m3/min (97.2 gpml
I
4431 m3/min (156,455 acfml
66.1°C (151'F)
3132 mVmin (110,587 scfm)
21. Oft
16.17 kPa [65 in W.C.)
0.074 g/m3 (0. 32 gr/scfl
13.93 kg/h (30.7 Ib/hr)
93ft minimum
13.14 m3/min (3450 gpm)
17.55 mVmin (4636 gpm)
0.41 m3/min (107 gpm)
17.43 kPa (70 in. W.C.I
0.28 m x 0.2 m x 5. 50 m
(8 ft x 0.67 ft x 18.25 ft)
0.24 m x 0.24 m x 0.6 m
(8.5 ft i; 8.5 ft 11 2 ft)
Downstream of scrubber
1
1731 kW (2320 hp)
Control system
Evaluation M
and vuntun scrubber
5270 mj/min (186,000 acfm)
314°C (59B°F)
2639 m3/min (93,176 scfm)
12.5
1.28 g/m3 (0.56 gr/scf]
199.04 kg/h (438.8 Ib/hr)
4.57 m x 11.6 m
(15 ft x 38 ft)
0.36 m3/min (94 gpml
1
3643 m3/min (128,661 acfml
65.6°C (150°FI
3166 m3/min 111,787 scfm)
12. 3»
i 13.44 kPa 154 in H.C.)
0.085 g/m3 (0.037 gr/scf)
15.65 kg/h 134.5 Ib/hr
. 93l minimum
2 . 3 m /mm (607 gpm)
2.44 m3/min (643 gpm)
0.49 m /mm (130 gpml
12.45 kPa (50 in. W.C. )
2.2 m x 11.6 m
(7.2 ft x 38 ft]
Upstream of scrubber
2080 kW 12788 .hp)

i n N
A preijuencher, venturi scrubber.
5270 m3/min (186,000 acfm)
314"C (598°F)
2639 m3/mm 193,176 scfm)
12.5
1.28 g/03 (0.56 gr/scf)
199.04 kg/hr (447.2 Ib/hr)
5.03 m X 12.2 m
(16.5 ft x 40 ft)
1
3462 m3/mm (122,250 acfm)
66*F (150'F)

-------
that a pilot test should be made to determine actual pres-
sure drop.  The preconditioner is constructed of mild steel
with a gunite or Savereisin acid-resistant cement lining.
The scrubber would be 316L stainless steel to protect against
scrubbing water, which is high in chlorides.
     The scrubber system in Evaluation N consists of a pre-
quencher, an adjustable-throat venturi scrubber, and a
separator section, followed by a fan.  The pressure drop of
this system is 5.23 kPa  (21 in. W.C.).  The bidder indicated
that some study has been made regarding scrubbing reverbera-
tory furnace gases in copper smelters, and based on the
limited scrubbing pilot plant data, he believes that a
pressure drop of 5.23 kPa  (21 in W.C.) is a reasonable
selection for producing 96 to 98 percent efficiency by
weight.  The materials of construction are steel lined with
acid brick, with FRP-lined steel in the hot gas zones and
high velocity sections of the scrubber.  All alloy parts are
in Inconel 625 in the venturi.  The fan wheel and shaft
would be of Incoloy-825 or 904L material.  The inlet ducting
is of 1/4-in. and 3/8-in. carbon steel with exterior weather-
proof insulation.  The material of construction for the
prequencher and venturi is 1/4-in. and 3/8-in. carbon steel
with 60- to 80-mil flaked-glass lining plus 3-in. acid brick
and foam glass interior lining.  Alloy parts are of Inconel
625.  The separator is 1/4-in. 3/8-in., and 1/2-in. carbon
steel with 60- to 80-mil flaked-glass lining.  The base, up
to 2 ft above the gas inlet, is lined with 3-in. acid brick.
The exit ducting to the fan and stack is of 5/8-in. thick
FRP-Hetron 197 with flame retardant.
     These evaluations point up the necessity of running
pilot plant tests to evaluate a wet scrubber that will
produce the desired efficiency.
                             4-41

-------
     Carbon steel is the material of construction for the
water treatment systems in all three evaluations.
Add-on Wet Scrubber Control System Costs
     Tables 4-17 and 4-18 present capital and annual operat-
ing costs of the three systems.  The evaluations represent
the cost of equipment for the last quarter of 1977.  They
include only basic equipment (no spare equipment).  The
following parameters were used in the duct cost estimate:  a
duct length of 24 m (80 ft) from the existing ESP exit to
the add-on control system inlet, an appropriate duct length
within the system, and a return duct of 34 m (110 ft) from
the add-on system outlet to existing stack.  Capital charges
in the annual operating costs were calculated by using 20.5
percent of the total turnkey cost.  This rate is based on an
interest rate of 10 percent, an equipment life of 10 years,
and a tax and insurance rate of 4.22 percent.
     Data show that the turnkey capital cost estimates for
an add-on scrubber system in the Evaluations L, M, and N are
$137, $160, and $390 per actual m /min ($3.90,  $4.53 and
$11.05 per acfm), respectively, of gas entering the system.
Gas flow rate to each system is 5270 m /min  (186,000 acfm).
Cost of gas cleaning equipment, including auxiliaries,
varies from 40 to 60 percent of the total turnkey cost.  The
respective annual operating cost for the three systems are
$0.53, $0.55 and $0.45/kg ($0.24, $0.25 and $0.20/lb) of
particulate removed, or $2407,  $2504, and $2042 per day.
Utilities and capital charges represent 54 percent and 17
percent of the total annual cost in Evaluation L, 67 percent
and 19 percent in Evaluation M, and 30 percent and 57 per-
cent in Evaluation N.
                            4-42

-------
                                 Table  4-17.    CAPITAL  COST  DATA  FOR  AN  ADD-ON  SCRUBBER  SYSTEM


                                                        FOR  PHELPS   DODGE  CORPORATION   SMELTER
*>.
 I
U)
Parameter

Gas flow at scrubber outlet i
Actual conditions
Tsmparature
Standard conditions
Moisture content
Contaminant load ing i*
Inlet, concentration
Inlet, weight rate
Outlet, concentration
Outlet, weight rate
Cleaning efficiency
Gas Cleaning equipment cost
Pan w/drive
Pumps
Tanks
Others
Total equipment cost
Foundation and supports
Duct work
Stack
Piping
Insulation
Painting
Electrical
Other
Total direct costs
Installation costs, indirect
Engineering
Construction fc field eupt 11
Construction fees
Start-up
Contingencies
Total indirect costs
Turnkey cost
Evaluation L
elbow and mist eliainator
follow by a fan
4411 B3/Bln (156,455 ac(»)
66.1*F (151'F)
3132 B3/Bin 1110,587 acfB)
26.111
1.28 g/m3 (0.56 gr/scf)
240.8 kg/hr (530.8 Ib/hr)
0.087 g/B3 (0.038 gr/scf)
13.6 kg/hr (30.0 Ib/hr)
93.3%
$102,500
92,000
11,500

116,800
16,500
$339,300
i 26,000
146,000
0
12,500
18,700
5,000
3,000
50,000
$261,200

$ 8,700
is 92,000
1.300
2,000
4 800
15,000
$121,800
$724.300
Evaluation H
A fan, a separator quencher
and a venturi scrubber
3643 m3/nin (128,661 acfB)
65.6'C (150'F)
3166 B3/Bin (111,787 scfa)
Saturated
1.28 g/m3 (0.56 gr/scf)
202.85 kg/hr (447.2 Ib/hr)
0.087 g/a3 (0.038 gr/scf)
13.6 kg/hr (30.0 Ib/hr)
93.3%
$120,100
90.000
20,000
60,000
118,500
87,100
$.495,700
$ 59,400
127,000
0
42,900
18.500
4,000
27,200

$279,000

$ 16,000
18,000
5,000
7,000
12 000
10.000
$ 68,000
$142,700
Evaluation N
A prequencher, a venturi scrub-
ber, separator, followed by a fan
3462 B3/Bin (122,250 acfB)
66'C (150'F)
2821 B3/Bin (99,850 scfB)

1.28 g/B3 (0.56 gr/scf)
202.85 kg/hr (447.2 Ib/hr)
0.087 g/B3 (0.038 gr/scf)
13.6 kg/hr (30.0 Ib/hr)
93.3%
$535,000
140,000
33,000
12,000
105,000
$ 125,000

$ 123,500
0





$1,108,300°







S2.0<.f.,800
                                   * &*»•<) on .lyatMi  inlet, (i.e.  furticulAta content in the gam Mow rate)  of  2639 » /»in l9J,.7b  •ct.ij to th« «y«t««.
                                   b
                                     Materials and  labor.

                                     Total of direct and Indirect
                                                                 r.,ma.  a«cluding duct cost.

-------
                                Table 4-18.    ANNUAL OPERATING COST  DATA FOR ADD-ON
                                   SCRUBBER  FOR  PHELPS DODGE CORPORATION SMELTER
                         Parameter
*>.
 I
System description


Gas flow at scrubber  outlet:
  Actual conditions
  Temperature
  Standard conditions
  Moisture
Contaminant loading:
  Inlet, concentration
  Inlet, weight  rate
  Outlet,  concentration
  Outlet,  weight rate
Cleaning efficiency
Operating  hours  per year
                    DIRECT COSTS
                    Operating  labor:
                      Operator, ?10/man-hour
                      Supervisor,  S12/man-hour
                      Total
                    Maintenance
                      Labor,  $10/man-hour
                      Materials
                      Total
                    Replacement parts
                    Utilities
                      Electricity,  $0.03/kWh
                      Water,  $0.25/1000 gallon's
                      Chemicals
                      Total
                    Total direct  costs
                      Capital  charges
                      Total annual cost
                                                           Evaluation  L
                                                 A venturi scrubber, a  flooded
                                                 elbow, and a mist  eliminator,
                                                 followed by a fan
4431 m /min  (156,455 acfm)
66.1°C (151°F)
3132 m3/min  (110,587 scfm)
26.13%

1.28 g/m3  (0.56 gr/scf)
202.R5 kg/hr  (4/17.2 Ib/hr)
0.087 g/m3  (0.038 gr/scf)
13.6 kg/h  (30.0 Ib/hr)
93.3%
8760
                                       $122,200
                                         37,000
                                        159,200

                                         59,200
                                         25,600
                                         84,800
                                         16,200

                                        450,700
                                         14,100
                                           5100
                                        469,900
                                       $730,100
                                        148,500
                                       $878,600
                                                                                        Evaluation M
A fan,  a separator quencher,
and a venturi  scrubber
                                                                                   3643 mj/min  (128,661 acfm)
                                                                                   65°C (150°F)
                                                                                   3166 m3/min  (111,787 scfm)
                                                                                   Saturated
1.28 g/m  (0.56 gr/scf)
202.85 kg/hr  (447.2  Ib/hr)
0.087 g/m3  (0.038  gr/scf)
13.6 kg/hr  (30.0 Ib/hr)
93.3% (minimum)
8760
      $ 87,600
        24,000
       111,600

         3,600
         3,000
         6,600
        10,000

       576,800
        12,400
        23,800
       613,000
      $741,200
       172,800
      5914,000
                                                                                                                          Evaluation N
A prequencher,  a  venturi
scrubber,  and  a separator,
followed by a  fan
                               3462 m /min (122,250  acfm)
                               66°C (150°F)
                               2828 m3/min (99,850 scfm)
1.28 g/nT (0.56 gr/scf)
202.85 kg/hr (447.2  Ib/hr)
0.087 g/m3 (0.038  gr/scf)
13.6 kg/hr (30.0 Ib/hr)
93.3%
8760
          $27,100
            9,700
           36,800

           27,100
           18,500
           45,600
           18,500

          196,000
            7,500
           19,400
          222,900
         ?323,800
          421,600
         $745,400
                      Based on system Inlet  (I.e. particulate content in the gas flow rate) of 2639 ro /min "(93,176 scfm} to the system.

-------
Add-on Dry Electrostatic Precipitator  (ESP), System
     Appendix C presents the  specification for an add-on dry
ESP for the Phelps Dodge smelter in Ajo.  Three IGCI members
used their best judgment to evaluate a dry ESP system based
on this specification.  Table 4-19 presents design para-
meters of the systems evaluated.
     The system in Evaluation P consists of an evaporative
cooling tower to cool gases from the existing hot ESP to
120°C  (250°F), followed by a dry ESP for particulate con-
trol.  The fan, necessary to overcome  0.96 kPa (4 in. W.C.),
is located on the hot side of the evaporative cooling tower
to avoid possible corrosion and imbalance problems.  Design
and instrumentation of the cooling tower spray chambers must
be precise to keep the exit gas dry because wet gas in the
ESP can cause a corrosion problem and  lead to premature
system failure.  An ESP pilot study would be required to
assess the corrosive and "sticky" nature of the flue gas and
particulate load.
     The particulate control add-on system in Evaluation Q
consists of a combination heat exchanger and dilution air to
cool the gas to 120°C (250°F) and two dry ESP's in parallel.
The fan is located upstream of the cooling system to take
advantage of the smaller gas stream which  requires less
power, and to prevent corrosion and imbalance problems.  The
combination heat exchanger and dilution air cooling is
believed to be the most economic from the viewpoint of cost
per Btu transferred and prevention of an increase in the
sticky and corrosive nature of the gas stream that is caused
by water spray cooling.
     The add-on system in Evaluation R consists of a water-
spray cooling tower, which cools the gas to 120°C (250°F) ,
and a dry ESP for particulate control.   The fan is located
                             4-45

-------
                  Table  4-19.   DESIGN PARAMETERS  FOR  ADD-ON  DRY  ELECTROSTATIC  PRECIPITATOR

                                              FOR  PHELPS  DODGE  CORPORATION  SMELTER
 I
£»
(TV
Parameter
Gas volume flow rate from
system:
Actual conditions

Type of cooling
Number of units
Hater consumption
Total volume flow rate to
outlet:
Temperature
Number of ESP's
Dimension of each
Number of chambers per ESP
Number of fields
Number of pai««g« par chimb
Field height
Voltage
Have form
Specific collecting area
Total power consumption
Pan:
Number
Location
Pressure drop
Power required
Evaluation P


314"C IS98T)
12.251
1
i.02 m3/h 1270 gpm)
120°C I250°F)
1
14.3 m x 12.8 m x 14. 3 m
2
•Ul
2.7 m (9.0 It)
7.3m (24 ft]
B
1000 mA
70 kV
Full
0.04 m/s (0. 13 ft/s)
74.4 m2 per m3/s H
(37B ftVlOOO acfm)
94 5 kW
1
Hot side of cooling tower
0.99ft kPa <4 in. H.C.)
280 kW (175 hpl
Evaluation 0

5267 re3 /nun (186,000 acfm)
314"C (598°F)
12.25*
air-
2b
629 3/ 22 192 f )

120°C (250'F)
1
1
4C
JO
J. 33 m (10.94 ft)
9.40 m (30.83 ft)
4
1250 mA
55 kV
Full
0.41 m/s (0.133 ft/s)
77.4 rn2 per m3/9 .
1393 ft /1000 acfm)
680 kW
1
Hot side of cooling system
1.992 kPa (8 in. H.C. 1
294 kH (335 hp]


2633 at3 /nun (93,000 scfm)
314*C (598'F)
12.25%
1
3535 mVmin (12.4,820 acfm)
120'C (250'F)
2
(49 ft x 42. S ft x 59.1 ft)
1
3
20
2.7B m (9.125 ft)
3
1300 mA
45 kV
Full
0.0322 m/s (0.0098 ft/s)
58.7 m2 per m3/s
(298 ft /1000 acfm)
233 kH
I
Hot side of cooling tower
297 kH (400 hp)
                                    " Heat exchanger cools qas to 177'C (350*F) and dilution ai
                                     Pertains only to heat exchanger.
                                    c One field is redundant.


                                    * Net gro«« X03 a2 per m3/s (524 ft2/1000 acfm).
                                                                            further cools gas to 120"C (250DF).

-------
on the  hot  side  of  the  cooling  tower  to  prevent  corrosion
and  imbalance  problems  that  can occur with  this  type of gas.
Costs of  an Add-on  Dry  Electrostatic  Precipitator
     Tables 4-20 presents  the capital cost  breakdown for the
evaluations P, Q, and R.   Table 4-21  presents  the  annual
operating cost breakdown for Evaluations P,  Q  and  R.   The
evaluations represent the  cost  of  equipment during the
quarter of  1977.  They  include  only basic equipment (no
spare equipment).   Duct cost estimates in the  three evalua-
tions are based  on  24 m (80  ft)  of duct  from the existing
ESP  outlet  to  the inlet of the  system, an appropriate  length
within  the  system,  and  a return duct  of  34  m (110  ft)  from
the  system  flange to the existing  stack.  Capital  charges in
the  annual  operating costs were calculated  by  using 17.5
percent of  the total turnkey costs.   This rate is  based on
an interest rate of 10  percent,  an equipment life  of 15
years,  and  tax and  insurance rate  of  4.35 percent.
     The  data  show  that the  use of an add-on dry ESP system
to enable Phelps Dodge  Corporation to comply with  the
.applicable  emission regulation  will entail  capital costs of
$329 to $466 per m  /min ($9  to  $13 per acfm) of  ESP exhaust
gas, depending on the type of cooling system involved.  A
gas  flow  rate  of 5267 m /min (186,000 acfm)  is used as the
basis for all  three evaluations.   System P,  which  uses an
evaporative cooling tower  for gas  cooling and  a  dry ESP for
particulate control, costs $367.12 per m /min  ($10.40  per
acfm) of  gas introduced into the system.  System Q, which
uses a  heat exchanger and  dilution air cooling system  and
two  dry ESP's  in parallel  for particulate control,  costs
$465.62 per m  /min  ($13.19 per  acfm).  System  R  which  uses
a water spray  cooling tower  for gas cooling  followed by a
dry  ESP for particulate control, costs $329.35 per m /min
                             4-47

-------
             Table  4-20.   CAPITAL COST  DATA FOR  ADD-ON  DRY  ELECTROSTATIC  PRECIPITATOR SYSTEM

                                               FOR PHELPS  DODGE CORPORATION  SMELTER
 I
£..
00
ParoiMter
Inlet gas flow:
Actual conditi
Temperature
Contaminant loading4
Inlet, concentration
'

Cleaning efficiency
cost
Fan -/drive
Dry cooling chamber
Other

direct:
ports6
(material fc labor)
Duct -or ic1
Stack
Piping
Painting
Other
Total direct costs
Complete erection
Engineering
Construction t field e
Construction fees
Start-up
Performance test
Hodel study
Contingencies
Turnkt-y CUM
Evaluation P

I -j
"l20*C (250*FJ
1.28 g/m3 (0.56 gr/scf)
93

93.2*
$ 645,000
87,000
168,000
123,600b
i.

112,000
175,100
0
Not quoted
Not quoted
505, bOO1*
5 792,700
:
xpenses 3
3
' 12,500
1
9,000
96,000
si ,-*n,Boo
Evaluation Q
dry ESP
1 3 , 5 «c a)
120*C <250'F)
1.28 g/m3 (0.56 gr/acf)
"' 93 ' lt> ^^
g g /sc )
93.2%
$470,000
87,500
277,000
7B,000C


SO, 000
154,000
Q
Not quoted *
Not quoted
729,400h
51,008,400
261,000
63,000
36,000
12,000
7.SOO
31,000
101,000
$2,4,52,400
Evaluation ft
dry ESP
3535 m^/nin (124,820 acfm)
120'C I2SOT)
1.28 g/nra' (0.56 gr/scf)
93
g/nm . g
93.21
5555,900
65,000
168,000
»7,BOOd


7,500
168,100
Not quoted
93,000
36B.6001
$ 692,200
k
49,900
5,900
25,700
74,400
Sl.734,700
                                    systt-m.
                                    Includes screw conveyors, slid* gates and lower dampers.
                                    Access and dust disposal.
                                    Slide-gate conveyors, dampers.
                                     Inc
                                     Includes duct, insulation, lining, materials and labor.
                                    costs connected with engineering and construction.
                                   1 About 92.5 percent for installation of total gas cleaning equipment and remaining for freight on equipment.
                                   1 Included in "other"
                                   1 Included in cost of s.tart-up.

-------
                       ELECTROSTATIC  PRECIPITATOR  FOR PHELPS  DODGE CORPORATION  SMELTER
                 Parameter
 I
•C*
            System description
Inlet gas flow:
  Actual conditions
  Standard conditions
  Temperature
Contaminant loading:
  Inlet, concentration
  Inlet, wt.  rate
  Outlet, concentration
  Outlet, wt. rate
Cleaning efficiency
Operating hours per
year
                                               Evaluation P
                         A fan,  an evaporative cooling
                         tower cooling gas to 120°C
                         (250°F),  followed by a dry
                         electrostatic precipitator
                                     407
                                        8 m /min  (149,000 acfm)
                                     3044 m3/min  (107,490 scfm)
                                     120°C  (250°F)

                                     1.28 g/m3  (0.56 gr/scf)
                                     199.04 kg/hr  (438.8 Ib/hr)
                                     0.087 g/m3  (0.038 gr/scf)
                                     13.6 kg/hr  (30.0  Ib/hr
                                     93.2%
                                     8760
             DIRECT COSTS
             Operating  labor:
              Operator, $10/man-hour
              Supervisor,  $12/man-hour
             Total
             Maintenance
              Labor, $10/man-hour
              Materials
              Total
             Replacement parts
             Utilities
              Electricity,  $6.03 kWh
              Water, $0.25/1000 gal
              Total
             Total direct  costs
              Capital  charges
              Total  annual  cost
                                   $ 8,100
                                     1,900
                                    10,000

                                     4,200
                                     2,200
                                     6,400
                                     1,800

                                   248,000
                                    10,800
                                   258,800
                                  f277,000
                                   344,000
                                  $621,000
                                                                     Control system
                                                                      Evaluation Q
A fan, two heat exchangers,
a dilution air fan, to cool
gas to 120°C (250°F) ,  follow-
ed by a dry electrostatic
precipitator
4371 m /min (154,374 acfm)
3262 m3/min (115,192 scfm)
120°C (250°F)

1.28 g/m3 (0.56 gr/scf)
199.04 kg/hr (438.8 Ib/hr)
0.087 g/m3 (0.038 gr/scf)
13.6 kg/hr (30.0 Ib/hr)
93.2%
8760
          $ 10,700
             1,500
            12,200

             4,200
             2,600
             6,800
              b

           178,700
                 0
           178,700
          $197,700
           429,200
          5626,900
                                                                                                                     Evaluation R
A fan, water spray cooling to
120°C (250°F), followed by a
dry electrostatic precipitator
3535 m3/min (124,820 acfm)
2149 m3/min (75,900 scfm)
120°C (250°F)
1.04 gr/m  (0.456 gr/scf)
199.04 kg/hr (438.8 Ib/hr)
0.087 g/m3 (0.038 gr/scf)
13.6 kg/hr (30.0 Ib/hr)
93.2%
8760
          $ 5,500
            2,300
            7,800

            4,000
            2,200
            6,200
            1,400

           99,600
           10,800
          110,400
         $125,800
          303,600
         $429,400
            a  Particulate  content ol  the  gas  at  the  inlet  and  outlet  is  based  on  a gas  flow  rate of 2639 m /min  (93,176 scfm) to the
              system.
              Included in  maintenance.

-------
($9.33 per acfm).  Cost of gas cleaning equipment including
auxiliaries for the Evaluations P, Q, and R, respectively,
is 53 percent, 37 percent, and 51 percent of the total
turnkey capital charges.  Annual operating costs are $0.38/kg
($0.17/lb) or $1701/day, of particulate removed for Evalua-
tion P; $0.39/kg ($.18/lb), or $1718/day, for Evaluation Q;
and $0.26/kg  ($0.12/lb), or $1176/day, for Evaluation R.
Utility costs and capital charges represent about 97 percent
of the total annual operating costs for all three evaluations,
Add-on Wet Electrostatic Precipitator (WEP) Control System
     Appendix C contains the specification for an add-on wet
ESP at the Phelps Dodge smelter.  Based on the specifica-
tion, one IGCI member used his best judgment to evaluate a
system.  Table 4-22 presents the design parameters of that
system (Evaluation S).
     The system involves a WEP designed to receive gases
from an evaporative cooling tower at 120°C (250°F).  The
system consisting of a fan, an evaporative cooling tower,
and a WEP-  The fan is located upstream of the cooling
system to prevent a potential corrosion problem.  The WEP is
generally chosen when the particulate tends to be sticky and
does not drop when the plates of a dry ESP are rapped.  The
WEP is a continuously sprayed, horizontal flow, parallel
plate, and rigid frame discharge electrode type.  Water from
a precisely designed water nozzle arrangement is sprayed at
the WEP entrance to maintain a low resistivity of the particles
entering into the system.  Water sprays located above the
electrostatic field sections introduce evenly distributed
water droplets to the gas stream for washing all internal
surfaces.   The particulates and water droplets in the
electrostatic field pick up charges and migrate to the
collecting plates.   The plates are continuously flushed to
                             4-50

-------
 I
Ul
               Table 4-22.   DESIGN  PARAMETERS OF AN ADD-ON  CONTROL  WET  ELECTROSTATIC

                    PRECIPITATOR SYSTEM  FOR  THE  PHELPS DODGE CORPORATION SMELTER
                                  Parameter
System description


Gas volume  flow rate from the existing
ESP to the  cooling system:

  Actual  conditions

  Standard  conditions

  Temperature

  Moisture  content

Type of cooling system

Number of units

Dimensions  of  each unit

Liquid-to-gas  ratio, L/G

Electrostatic  Precipitator System

Total volume flow rate to add-on precip-
itator system  inlet or cooling system
outlet:

  Actual  conditions

  Standard  conditions

  Temperature

Number of ESP's

Dimension of each
                                                     Evaluation S
                                                              One evaporative  cooling tower to cool gas
                                                              to 120°C (250°F), one fan, and one wet ESP
5267 mJ/min  (186,000 acfm)

2633 m3/min  (93,000 scfm)

314°C (598°F)

12.25%

Evaporative  cooling tower

1

7.99 m  x  18.8 m  (26.24 ft  x  61.7  ft)

0.097 m  per m /rain (355 gal/1000 acfm)
                                                               4046 mj/min (142,892 acfm)

                                                               3021 m3/min (106,673 scfm)

                                                               120°C  (250°F)

                                                               1
                 (continued)

-------
                      Table 4-22  (continued).
                                      Parameter
t

-------
remove the collected material into the troughs below which
are sloped to a drain.  The WEP parts not sprayed or flushed
with water are constructed of corrosion-resistant materials.
(The portion close to outlet of WEP is not sprayed or
flushed with water in order to remove the carry over liquid
drops and mists before the outlet of the equipment).  The
condensible material collected in the drain liquor can be
separated by means of any sludge removal methods.
Costs of Add-on WEP System
     Tables 4-23 and 4-24 present capital and annual operat-
ing cost breakdowns for Evaluation S.  The evaluation
represents the cost of equipment during the last quarter of
1977.  It includes only basic equipment (no spares).  Duct
cost estimates in the evaluation are based on 24 m (80 ft)
of duct from the existing ESP outlet to the inlet of the
system, an appropriate length within the system, and a
return duct of 34 m (110 ft) from the system to existing
stack.  Capital charges in the annual operating costs were
calculated by using 17.5 percent of the total turnkey
costs.  This rate is based on an interest rate of 10 per-
cent, an equipment life of 15 years, and a tax and insurance
rate of 4.35 percent.
     The data show that the capital cost of an add-on wet
ESP system to enable Phelps Dodge Corporation to comply with
the applicable emission regulation is $384.17 per m /min
($10.88 per acfm) of ESP exhaust gas [based on a flow rate
of 5,267 m /min  (186,000 acfm)].  The evaluated system uses
an evaporative cooling system to cool the gas to 120°C
(250°F) before it enters the WEP.  Cost of gas cleaning
equipment including auxiliaries is 43 percent of the total
                             4-53

-------
turnkey capital charges.  Annual operating costs for partic-
ulate removal are $0.35/kg ($0.16/lb), or $1547 per day.
Utility costs and capital charges represent about 98 percent
of the total annual operating costs.
                           4-54

-------
                    Table 4-23.   CAPITAL COST DATA FOR AN ADD-ON WET  ELECTROSTATIC

                       PRECIPITATOR  SYSTEM FOR PHELPS DODGE  CORPORATION  SMELTER
                                  Parameter
 I
ui
en
System description

Inlet gas  flow:
  Actual conditions
  Standard conditions
  Temperature
Contaminant loading:
  Inlet, concentration
  Inlet, wt. rate
  Outlet,  concentration
  Outlet,  wt.  rate
Cleaning efficiency
                    Gas cleaning equipment cost
                    Cost of auxiliaries:
                      Fan with drive
                      Evaporative cooling tower
                    Total equipment cost
                    Installation costs, direct
                      Recipitator supports (M&L)
                      Duct work
                                                     Evaluation S
                                                               One evaporative cooling tower to  cool the
                                                               gas to 120°C  (250°F), one fan,  and one wet ESP
4046 m /min  (142,898 acfm)
3021 m3/min  (106,673 scfm)
120°C (250°F)

1.28 g/m3  (0.56 gr/scf)
199.04 kg/hr  (438.8 Ib/hr)
0.087 g/m3  (0.038 gr/scf)
13.6 kg/hr  (30.0 Ib/hr)
93.2%
                                                     $   435,100
                                                     $    28,000
                                                         87,500
                                                        314,000
                                                     $   864,600

                                                     $    23,500
                                                        154,400*
                    (continued)

-------
                      Table  4-23  (continued).
I
Ul
Parameter
Stack
Piping
Insulation (material & labor)
Painting
Electrical (material & labor)
Other
Total direct costs
Installation costs, indirect
Engineering
Construction and field expenses
Construction fees
Start-up
Performance test
Contingencies
Total indirect costs
Turnkey cost
Evaluation S
0



87,500
340,900C
$ 606,300

$ 350,000d
52,000
36,000
12,000
7,500
95,000
$ 552,500
$2,023,400
                      3  Particulate content of the gas  at  the inlet and outlet based on a  gas  flow rate of
                        2639 m3/min (93,176 scfm)  to the system.
                        Includes duct, insulation lining,  materials and labor.
                      c  Installation cost Of ESP,  auxiliaries, and fan.

                        Includes $31,000 model study.

-------
Table  4-24.   ANNUAL OPERATING COST  DATA FOR ADD-ON  CONTROL  WET

ELECTROSTATIC PRECIPITATOR  FOR  PHELPS DODGE CORPORATION SMELTER
               Parameter
          Evaluation S
 System description


 Inlet gas  flow:
   Actual conditions
   Standard conditions
   Temperature
 Contaminant loading:
   Inlet, concentration
   Inlet, wt. rate
   Outlet,  concentration
   Outlet,  wt. rate
 Cleaning efficiency
 Operating  hours per year
One evaporative cooling tower to  cool gas
to 120°C (250°F) and one fan, followed by
one ESP
4046 m /min  (142,898 acfm)
3021 m3/min  (106,673 scfm)
120°C (250°F)

1.28 g/m3  (0.56 gr/scf)
199.04 kg/hr  (438.8 Ib/hr)
0.087 g/m3  (0.038 gr/scf)
13.6 kg/hr  (30.0 Ib/hr)
93.2%
8760
 Direct costs
 Operating labor
   Operator, $10/man-hour
   Supervisor,  $12/man-hour
   Total
 Maintenance
   Labor,  $10/man-hour
   Materials
   Total
          $  7100
            1500
            8600

            3500
            2300
            5800
 (continued)

-------
                      Table  4-24  (continued)
                                     Parameter
 I
cn
oo
Replacement parts
Utilities
  Electricity,  $0.03/kWh
  Water,  $0.25/1000  gal
  Chemicals
  Total
Total direct costs
  Capital charges
  Total annual  cost
                                                     Evaluation S
  76,900
 119,200
    b
 196,100
$210,500
 354,000
$564,500
                        Included in maintenance cost.
                        Included in electricity cost.

-------
APPENDIX A
    A-l

-------
                     CONVERSION FACTORS
   To convert
 English units
  Multiply
     by
    To obtain
    SI units
British thermal unit (Btu)

Cubic foot (ft3)

Degrees fahrenheit

Foot

Gallon (U.S. liquid)

Gallon (U.S. liquid)

Horsepower (hp)

Inch

Inches of water

Pound
    1056

   0.0283

5/9 C°F-32)

   0.3048

   0.0038

   3.7854

   746.0

   0.0254

   248.8

   0.4536
Joule  (j)

Cubic meter  (m )

Degrees Celsius  (C)

Meter  (m)
              3
Cubic meter  (m )

Liter  (1)

Watt (w)

Meter  (m)

Pascal  (pa)

Kilogram  (kg)
                            A-2

-------
APPENDIX B
    B-l

-------
                                PEDCo  ENVIRONMENTAL
                                                     CHESTER ROAD

                                              CINCINNATI, OHIO 45346

                                                      (513) 782-47OO
               TECHNICAL SPECIFICATIONS FOR ADD-ON

                CONTROL SYSTEMS  FOR REVERBERATORY

                FURNACE AT MAGMA COPPER COMPANY,

                       SAN MANUEL,  ARIZONA
                            Prepared by

                    PEDCo Environmental, Inc.
                       11499  Chester Road
                    Cincinnati,  Ohio   45246
                  PEDCo Project Number:  3287-B
                          June  28,  1977
                                 BRANCH OFFICES
CHESTER TOWERS
                          Crown Center
                         Kansas City. Mo.
Professional Village
 Cnapel Hill. N.C

-------
                      TABLE OF CONTENTS


                                                       Page

SCOPE OF WORK                                            1

GENERAL INFORMATION                                      3

DESIGN CRITERIA AND GUARANTEE                            3

SPECIFIC OPERATING CONDITIONS FOR ADD-ON EQUIPMENT       5

DESIGN LOADS                                             6

CONTROL SYSTEM SUPPORT STRUCTURE                        12

     ADD-ON CONTROL EQUIPMENT:  ELECTROSTATIC           12
     PRECIPITATOR, DRY TYPE

     ADD-ON CONTROL EQUIPMENT:  ELECTROSTATIC           18
     PRECIPITATOR, WET TYPE

     ADD-ON CONTROL EQUIPMENT:  COOLING CHAMBERS        19

     ADD-ON CONTROL EQUIPMENT:  VENTURI SCRUBBER        20

     ADD-ON CONTROL EQUIPMENT:  FABRIC FILTER           21
     BAGHOUSE

SKETCHES                                               A-l
                           11

-------
                       LIST OF TABLES
NO.
     Summary of Particulate Emission Data for
     Electrostatic Precipitator on Reverberatory
     Furnace - Magma Copper Company, San Manuel,
     Arizona
                           111

-------
                       LIST OF SKETCHES


No.                                                    Page

A-l  Dry Electrostatic Precipitator with a Cooling     A-l
     Chamber

A-2  Wet Electrostatic Precipitator with a Cooling     A-2
     Chamber

A-3  Wet Electrostatic Precipitator                    A-3

A-4  Cooling Chamber                                   A-4

A-5  Venturi Scrubber                                  A-5

A-6  Fabric Filter Baghouse                            A-6
                            IV

-------
          TECHNICAL SPECIFICATIONS (COPPER SMELTER)






     It is the intent of these specifications to provide the



contractor with sufficient information to furnish and in-



stall a gas-cleaning system, including the control equipment



to treat exhaust gases from an already-installed electro-



static precipitator on a copper concentrate smelting rever-



beratory furnace at the Magma plant at San Manuel, Arizona.



SCOPE OF WORK



     Major items of work to be accomplished by contractor



consist of the following:



     1.   Engineer, design, procure materials and equipment,



          fabricate, and erect from ground level from the



          discharge of the existing hot electrostatic



          precipitator flue to the inlet nozzles of the



          required add-on control equipment.  The contractor



          shall provide heat insulation on flues.



     2.   Engineer, design, procure materials and equipment,



          fabricate, and erect from ground level up the



          required support structure for the add-on control



          equipment, including all required walkways, stair-



          ways, and handrails.  The supporting structure

-------
     system will exclude foundations, which will be



     supplied and furnished by others.



3.   Engineer, design,  procure materials and equipment,



     fabricate and deliver add-on control equipment,



     complete with all  electrical equipment required to



     place the unit into operation.



4.   Erect the add-on control equipment, including



     furnishing and installing heat insulation on the



     add-on control equipment where required.  The



     erection portion excludes furnishing wire and



     conduit or a control room for electrical equip-



     ment.



5.   Engineer, design,  procure materials and equipment,



     fabricate, and erect from ground level up the



     discharge flues starting at the outlet nozzle



     flange of the add-on control equipment and termi-



     nating at the new inlet to the present stack.



6.   Provide qualified personnel for the initial start-



     up of the complete system.  Start-up is to include



     all testing, adjustments, and modifications neces-



     sary to ensure proper operation of the units at or



     above the collection efficiency levels specified



     herein.  Start-up is also to include the training



     of owner's operating and maintenance personnel to



     operate and maintain the equipment.

-------
     7.    The contractor shall provide the services of a



          qualified Field Erection Engineer who shall give



          supervision and technical assistance as required



          during assembly, field erection, and start-up of



          the equipment.



     8.    The contractor will furnish a test model of the



          add-on control equipment and the flue systems for



          gas-flow study.



GENERAL INFORMATION




     An additional fan to handle the pressure drop shall be



included with any add-on control equipment.



     All electrical, water, and other services will be



within 100 feet of the new facilities.



     Site leveling and preparation by others.



     The units are to operate 24 hours per day, 365 days per



year.



     The layouts for particulate removal control systems are



shown on attached Sketches A-l through A-6.  The length of




duct runs are shown on the sketches.



DESIGN CRITERIA AND GUARANTEE



     1.    Collection Efficiency



          The add-on control equipment will have a minimum



          guaranteed collection efficiency of 98.2 percent



          by weight of the entering particulate matter as

-------
     determined by EPA Test Method 5, with a filter



     temperature of 250°F.



2.   Efficiency Tests



     The owner shall make regular tests to check the



     collecting efficiency.  The contractor and owner



     shall jointly test the add-on control equipment



     for collection efficiency immediately after com-



     pletion of all construction, at 6 months and at 11



     months after completion.   The test at 11 months



     will determine the guarantee performance.



3.   Efficiency Curves



     The contractor shall furnish with its proposal



     expected efficiency curves, showing the guarantee



     point.  Curves will show expected efficiency



     versus volume, grain loading, percent moisture,



     gas temperature, percent SO3 in gas, percent lead,



     and any other significant parameters affecting



     efficiency of the add-on control equipment.



4.   Draft Loss



     The draft loss between inlet and outlet flanges of



     the nozzles will be held to a minimum to attain



     the removal efficiency required.

-------
     5.    Gas Velocity

          The gas velocity through the precipitator proper

          will not exceed 3 feet per second; and the veloc-

          ity through a venturi scrubber or baghouse shall

          be recommended by the vendor.

     6.    Gas Flow Study

          The contractor shall construct a test model of the

          system from and including the outlets of the waste

          heat boilers to the stack.

     7.    Redundancy

          The control equipment shall be sized with a con-

          fidence level of at least 90 percent when the

          system is operating at a full mode.

SPECIFIC OPERATING CONDITIONS FOR ADD-ON CONTROL EQUIPMENT

     The add-on control equipment will be capable of han-

dling copper smelting reverberatory furnace exhaust gases

described as follows:

     1.    Amount of gases per precipitator:  329,000 scfm.
                                             (641,000 acfm)
     2.    Operating temperature of gases:  573°F.

     3.    Short-term temperature surges to 650°F during

          furnace charging periods.

     4.    Nominal dust particle inlet loading is 0.77 grain

          per SCF.  Estimated dust particulate inlet loading

          is 1.25 grains per SCF during furnace charging

          periods.

-------
     5.   Particle size analysis - flue gas at 573°F con-



          tained about 77 cuitunulative percent particulate



          present in a size less than 7 micrometers and about



          26 cummulative percent particulate present in a



          size less than 0.26 micrometers.



     6.   Expected volumetric analysis of gas component and



          percent:  See attached Table 1.



     7-   Estimated bulk density of collected dust, dry



          pounds per cubic foot:  Not available.



     8.   Acid dew point of gas:  Not available.



     9.   Expected composition of dust:  See attached Table



          1 and use outlet composition.



DESIGN LOADS



     This should include vertical live loads, lateral loads,



and earthquake considerations.



FLUE SYSTEM:



     1.   The flue system shall begin at the outlet flange



          of the existing hot electrostatic precipitator and



          proceed to the inlet flanges of the add-on control



          equipment.



     2.   The ductwork from the outlet flange of the exist-



          ing hot electrostatic precipitator to the add-on



          control equipment shall be sized for minimum gas



          velocity of 3500 feet per minute under maximum

-------
Table  1.   SUMMARY OF  PARTICULATE  EMISSION  DATA  FOR  EXISTING  ELECTROSTATIC  PRECIPITATOR

              ON REVERBERATORY FURNACE -  MAGMA COPPER  COMPANY,  SAN MANUEL, ARIZONA
           Item
                                           Design
              Actual
                (1)
               Compliance tests
                conducted by
                  company
               October 30 and
                31, 1975 (2)
EPA compliance
tests by NEIC
May 14 to  18,
  1976 (3)
      ESP manufacturer
      ESP Inlet Conditions

      Volume flow at continuous
       rating,             acfm

                          scfm
      Temperature, °F
      Gas dust  loadings:
       by instack filter,
                  gr/scf
                   Ib/hr

       by instack/outstack filter,
                  gr/scf
                   Ib/hr
       by EPA Test Method 5,
                  gr/scf
                   Ib/hr

      ESP Outlet Conditions

      Volume flow at continuous
       rating             acfm
                          scfm
Research
 Cottrell
 560,000
 (Calc.)
 284,000
 500-670
 0.836
 2035
(calc.)
560,000
(calc.)
284,000
500-670
0.836
2035
(calc.)
                                331,200
                                170,000
                                     329,000
                                     169,000

-------
          Table  1  (Cont'd).   SUMMARY OF  PARTICULATE EMISSION DATA FOR EXISTING ELECTROSTATIC

           PRECIPITATOR ON REVERBERATORY FURNACE  - MAGMA  COPPER COMPANY,  SAN MANUEL,  ARIZONA
oo
                    Item
ESP Outlet Conditions
 (continued)~

Temperature,  °F
Gas dust loadings:
 by instack filter
                  gr/scf
                   Ib/hr
 by instack/outstack filter,
                  gr/scf
                   Ib/hr
 by EPA Test  Method 5,
                  gr/scf
                   Ib/hr
ESP control efficiency,  %
Allowable emissions,
                  gr/scf
                   Ib/hr
               At ESP Outlet
               SO-  emission, ppm

               SO,  emissions, ppm
                   Ib/hr

                   Ib/hr
               COji volume percent
               O2» volume percent
               H2O, volume percent
                                                    Design
                                                   0.01254
                                                  30.53  (calc.)
                                                  98. Og
                                                  Actual
                                                   (1)
Compliance tests
 conducted by
  company  (2)
 October 30 and
    31, 1975
                                                                                    573
                                                                              0.1201  to 0.3924d
EPA compliance
tests by NEIC
May 14 to  18,
  1976 (3)
                         573
                         0.77?
                         2180f
                                                                                                      0.014 (calc.)
                                                                                                       39.7
                       5400
                      17820
                       15.91
                       66.1

                       4.03
                      14.17
                       8.70

-------
        Table  1  (Cont'd).   SUMMARY OF PARTICULATE  EMISSION  DATA FOR EXISTING ELECTROSTATIC
         PRECIPITATOR ON REVERBERATORY FURNACE  - MAGMA COPPER  COMPANY, SAN  MANUEL,  ARIZONA




Item
Metal analysis, Ib/hr
Tin (SnP
Arsenic (As)
Cadmium (Cd)
Chromium (Cr)
Copper (Cu)
Lead (Pb)
Mercury (Hg)
Molybdenum (MO)
Nickel (Ni)
Selenium (Se)
Vanadium (V)
Zinc (Zn)



Design
(Da
















Actual
(1)













Compliance tests
conducted by
company ( 2 )
October 30 and
31, 1975














EPA compliance
tests by NEIC
May 14 to 18,
1976 (3)

0.16
5.2
0.25
0.10
9.8
3.4
0.06
0.81
0.03
1.3

5.*
VD
                                                                                                     Included  in Appendix

                                                                                          The actual  flow rates were
  Numbers in parenthesis represent corresponding reference listed.
  Average of four compliance test runs conducted by Magma on October 30 and 31,  1975.
  A, Magma Petition for Revision Table 1, page 4.  NEIC report.
  Average of three compliance tests conducted by NEIC from May 14-22,  1976.
  345,000, 313,000, and 328,300 scfm, respectively.
  Actual emissions during four compliance tests conducted by Magma  on  October 30 and 31,  1975 were 0.3268,
  0.2202, 0.1201, and 0.3924 gr/scf, respectively.  Isokinetic conditions were not met during all the tests.
  Average of three test runs (0.71, 0.85, and 0.71 gr/scf) conducted.
  Actual emissions during the three tests were 2090, 2450, and 2000 Ib/hr.
" Based on instack filter tests.
  Average of three test runs.  Actual measurements were 4500, 6670, and 5030 ppm, respectively.
  Average of three test runs.  Actual measurements were 12.8, 16.2, and 18.7 ppm, respectively.
-1 Metals identified in particulates collected by EPA method 5 in ESP outlet during the second compliance
  test run.
1^
  Filter zinc results are questionable.

-------
Table 1  (Cont'd).   SUMMARY OF  PARTICULATE EMISSION DATA FOR EXISTING  ELECTROSTATIC

 PRECIPITATOR ON  REVERBERATORY FURNACE -  MAGMA COPPER  COMPANY,  SAN MANUEL,  ARIZONA
      Reference

      (1) State  Implementation Plan Inspection of San Manuel Division Smelter, Magma Copper Company,  San
          Manuel, Arizona.  June 1976.  In:   Emission Testing at the Magma Copper Company Smelter,  San
          Manuel, Arizona, by National Enforcement Investigations Center.  EPA-330/2-76-029.  May 2-22, 1976.

      (2) Appendix A, Magma Petition for Revision In:  Emission Testing at the Magma Copper Company Smelter,
          San Manuel, Arizona,  by National Enforcement Investigations Center.  EPA-330/2-76-029.  May 2-22,
          1976.

      (3) Test Results:  In:  Emission Testing at the Magma Copper Company Smelter, San Manuel, Arizona, by
          National Enforcement Investigations Center.  EPA 330/2-76-029.  May 12-22, 1976,

-------
     future gas flow conditions of 641,200 acfm.  This



     ductwork shall be rectangular in crosssection,



     fabricated of 1/4-inch-thick  (minimum) steel plate



     consistent with the acidity of the gas stream, and



     be equipped with suitably reinforced stiffeners.



     An expansion joint in both the vertical and hori-



     zontal portions of this ductwork shall be pro-



     vided.  Any right-angle turns in this ductwork



     shall be of the largest centerline radius possible



     and designed to minimize pressure drop.  The



     interface between the throat of the right-angle



     turn and the gathering plenum shall be designed to



     minimize any particulate material buildup.  Turn-



     ing vanes will be installed to streamline the flow



     where required.  Flue shall also be tapered so as



     to minimize the entry pressure loss.



3.   Outlets from the gathering flue to the nozzles of



     the control system shall be optimized and designed



     to provide uniform distribution of flow to the



     inlet nozzles, with a minimum pressure drop re-



     quired to achieve this optimization.  Each outlet



     shall also include an air-lock damper at the inlet



     nozzle to the add-on control equipment and all



     necessary platforms, headframes, and hoists re-



     quired for operation of the air-lock dampers.
                       11

-------
     4.   Expansion joints shall be provided at the inter-



          face of the inlet nozzles and the gathering plenum




          outlets.



     5.   Gas sampling stations and access platforms shall



          be provided at points designated by the EPA method



          of testing (at system inlet and outlet).



CONTROL SYSTEM SUPPORT STRUCTURE



     The add-on control equipment support structure shall be



provided complete with access and stairway landings.  Struc-



tural elements required to support the add-on control equip-



ment, access walkways,  and stairways should be designed to



provide clearance for any roadways or railroad equipment



that must continue to operate during construction and after



completion of the project.



ADD-ON CONTROL EQUIPMENT:



Electrostatic Precipitators;  Dry Type (Sketch A-l)



     1.   The electrostatic precipitators will be horizon-



          tal-flow, plate-type of heavy-duty construction



          and shall be sectionalized and compartmentized for



          flexibility.   Two separate inlet and outlet noz-



          zles are to be provided to make each compartment



          isolated from the other one.



     2.   Mild-steel, high-voltage insulator compartments



          are to be provided.  These compartments are to, be
                            12

-------
          insulated and heated by hot-air, positive pressure



          blower systems utilizing electric heating and



          inlet air filtering.




     3.   Access doors and internal walkways between elec-



          trical sections will be provided.



     4.   All access openings will be provided with an



          automatic key interlock system to protect per-



          sonnel and equipment.  Structural and component



          design will provide allowance for free expansion



          so as to prevent permanent structure deformation at



          continuous gas operating temperatures of 600°F.



     5.   The precipitator housing is to be able to with-



          stand the maximum internal negative pressure that



          might be created in operation.



PRECIPITATOR CASING



     1.   The precipitator casing will be of steel plate



          construction properly reinforced to withstand the



          acidity of the gas stream.  Materials will meet



          specifications as described in the latest edition




          of the ASTM Standards.



     2.   Inlet and outlet nozzles to precipitator are to be



          provided by the contractor.  Each nozzle will



          include necessary internal supports, guide vanes,



          distribution plates and appropriately located U
                            13

-------
          tube and sample ports.  Flanges for attaching
          flues are to be included.
     3.    Casing and nozzles will be fabricated; from steel
          plate.
HOPPERS
     1.    Dust hoppers will be located under the collecting
          sections and shall be V-shaped trough or bunker
          type.
     2.    Hoppers will be constructed of steel plate with &
          minimum thickness of 1/4 inch and to withstand the
          acidity of the gas stream.
     3.    Hoppers will be welded construction, having a.
          minimum slope of 60°.
     4.    Each hopper will be provided with a 15" x 15" x 1"
          manual impact plate spaced at 3—foot centers along
          both sides of hoppers at accessible locations.
          Impact plate and poke holes are to be combined.,
     5.    Provisions shall be made with double "Plattco"
          type valves or equivalent to prevent infiltration
          of air through the screw conveyors to the gas
          stream.
     6.    Screw conveyors shall be provided beneath all
          precipitator hoppers.  Conveyors shall be sized
          and powered to handle expected dust loading, but
                            14

-------
          in no case shall they be less than 12 inches in



          diameter or have less than 7-1/2 horsepower drives,



RAPPERS




     1.   Rappers are to be of the electromagnetic or drop-



          hammer type with a heavy rapping force.



KEY INTERLOCKS




     1.   Key interlocks, to deenergize the unit, will be of



          lock and key type to protect operating personnel



          from high-voltage electrical equipment.  Inter-



          locks will be provided for the power panel, high-



          voltage switches, rectifier-transformer sets, and



          all access doors in the shell, housing, and hop-



          pers that provide entrance into the electrodes in



          the high-voltage connections.



ELECTRODES



     1.   Collecting plate electrodes are to be minimum



          16/18 gauge steel and designed to provide minimum



          reentrainment of dust by gas stream during rapping



          periods to be compatible with the acidity of the




          gas stream.



     2.   Discharge wires or solid electrodes will be held



          in place parallel to and at equal distances from



          the collecting plates by structural steel frames



          hanging from high-voltage, with isostatically
                            15

-------
          pressed alumina or equivalent support insulators



          located in the shell roof.



     3.   Approximate spacing between collecting plates will



          be 9 inches.



RECTIFIER-TRANSFORMER SETS



     1.   Each precipitator field will be supplied with its



          own separately controlled rectifier-transformer



          set.



     2.   The selenium rectifier-transformers will be 50%



          oversized, have adequate surge protection, and



          will be the oil-emersed, self-cool type.



     3.   The rectifier-transformer will be capable of half-



          wave or full-wave power by way of the associated



          switch.



     4.   Other accessories should include automatic control-



          ler, and meters for primary current, primary volt-



          age, secondary current, and secondary voltage.



PRECIPITATOR DISCHARGE FLUE



     1.   The precipitator discharge flue shall begin at the



          outlet nozzle flange of the precipitators and



          terminate at the interface of this flue with the



          same point of discharge now used by the hot



          electrostatic precipitator.



     2.   A manually operated poised-blade louver damper



          shall be installed at the outlet nozzle flanges of
                            16

-------
          each precipitator.  Damper and operating mechanism



          shall be fabricated of type 316 stainless steel



          and shall have a minimum-leakage characteristic.



     3.   An air-lock damper and an expansion joint shall be



          installed between the flow-control damper and the



          main flue on each of the two precipitator outlets,



          along with all necessary platforms.



     4.   Gas sampling stations and access platforms shall



          be provided at points designated by EPA Method 5



          testing.




     5.   Structural elements required to support the dis-



          charge flue, access walkways and stairways shall



          be designed to provide clearance for railway



          equipment that must continue to operate during



          construction and after completion of the project.



     6.   Expansion joints shall be provided as required to



          prevent permanent structural deformations from



          occuring at a continuous operating temperature of




          600°F.



PRECIPITATOR REDUNDANCY



     1.   The precipitation equipment shall be designed so



          that guarantee is met with one full width elec-



          trical field out of service.



     2.   The precipitation equipment shall be sized with a



          confidence level of at least 90 percent when all




          fields are in service.
                           17

-------
Electrostatic Precipitator;  Wet Type  (Sketch A-2 & A-3)



     See attached Sketch A-7 for the wet electrostatic ,



precipitator circuitry.



     The portions of the specification for the dry electro-



static precipitator that are applicable to the wet electro-



static precipitator shall apply.



     The following factors shall be included:



     1.   Materials of construction shall withstand the



          corrosive atmosphere of acidity present in the gas



          stream.



     2.*  Heavy rapping forces are required, 50 "g's" or



          greater and continuous cleaning.   (Lead and zinc



          in the discharge stream can form lead or zinc



          oxides that tend to destroy the cleaning capa-



          bility of inlet field of the precipitator, there-



          fore the necessity of continuous cleaning; zinc



          will galvanize to the collecting surfaces and thus



          the requirement for heavy rapping.)



     3.   If the wet ESP system as shown in Sketch A-7 is



          quoted as a complete system with hold tank, pH



          control, clarifier, vacuum filtration, pumps,



          etc., identify the major materials of construc-



          tion, gpm, and estimated sludge discharge  (in gpm)



          to the pond.
* not applicable
                              18

-------
     4.   If the wet ESP system as shown in Sketch A-3




          consists of only the electrostatic precipitator,




          indicate the gpm of water required, the number of



          nozzles for water sprays being supplied, and the



          head in inches of water required at the point of



          discharge into the precipitator.  Also the esti-



          mated gpm discharged from the hoppers of the wet



          electrostatic gravity and the gpm of make-up water



          required.



     5.   As shown in Sketch A-2, a cooling chamber ahead of



          the wet-electrostatic precipitator would cool the



          gas to 250°F  (+25°F) prior to its entry into the



          wet electrostatic precipitator.



     6.   As shown in Sketch A-3, the wet electrostatic



          precipitator receiving a gas stream at approxi-



          mately 600°F would discharge the cleaned and



          cooled gas stream at 250°F (+25°F).




     7.   The removal efficiency required would be 98.2%.



COOLING CHAMBERS:  (Sketch A-l, A-2, A-4, A-6)



     Supply a complete system consisting of but not limited



to the following:  two cooling chambers of the downflow type



and dry bottom design with a water filtration and pumping



system, automatic apparatus for control of exit temperature,



and all necessary piping, insulation, etc.  Also supply the
                            19

-------
supports and ductwork, with insulation, to convey the cooled



gases at 250°F (+25°F) from the discharge of the cooling



tower to the precipitator.  The chamber will have clean-out



doors permitting man-entry and front-end unloaders for



clean-up purposes.



     The water system will be a closed-loop type.  The



materials of construction shall be compatible with the



corrosive atmosphere of the gases.



     Foundations will be by others.



VENTURI SCRUBBER:  (Sketch A-5)



     Supply a complete system consisting of but not limited



to the following:  one venturi scrubber with a holding tank,



pumps, piping, variable-throat control, pH control, clari-



fier, vacuum filtration, flocculant additive system, struc-



tural supports, walkways, platforms, insulation, valving,



ductwork as required, demister, etc.  The pressure drop will



be suggested by bidder.  The materials of a construction



shall be compatible with the corrosive atmosphere of the



gases.



     The water system will be a closed-loop type.



     The materials of construction shall be compatible with



the corrosive atmosphere of the gases.



     Foundations will be by others.
                            20

-------
FABRIC FILTER BAGHOUSE:   (Sketch A-6)




     Supply a complete system consisting of but not limited



to the following:  one fabric filter  (pulse-jet type, etc.



will be left to the discretion of the vendor), baghouse,



readily changeable bags, clean-out doors for interior clean-



ing of collectors and inspection; cooling chamber, pumps,



etc.  The bags and materials of construction shall be



compatible with the acidity of the treated gases.



GENERAL DESIGN COMMENTS




     1.   All systems will be tabulated and broken down into



          major components, i.e., electrostatic precipitator,



          ductwork, structural steel, controls,  (electrical,



          etc.) with their erected costs.



     2.   Each major piece of equipment  (i.e., electrostatic



          precipitator, baghouse, etc.) will be reported as



          to square feet of collection area, number of



          fields, rapping force, type of electrodes, mate-



          rials of construction, total weight in tons, size,



          height, duct size, number of bags, size, type,




          etc.).



     3.   Annual operating costs with quantities of elec-



          tricity, water, etc. used; operating manpower,



          maintenance manpower, and costs; estimated life of



          the control equipment.
                            21

-------
4.    Equipment shall be in conforraance with the National



     Electrical Code, OSHA, Federal, State, and local



     regulations.



5.    Satisfactory performance tests will be as indi-



     cated in the dry electrostatic precipitator.
                         22

-------
SKETCHES

-------
S^AtLT£R
                                     GENERAL NOTES: N.T.S.

                                       DUCTWORK

                                       TO FAN     100'
                                       TO C.C.     20'

                                       TO ESP      50'
                                       TO STACK   150'
REFINERY
 OFFICE
                                      MAGMA:  SMELTER AT
                                      SAN MANUEL,  ARIZ.
                                      RETROFIT OF  DRY
                                      ELECTROSTATIC  PREC.
                                      WITH A COOLING
                                      (SPRAY TYPE) CHAMBER
                                      AS ADD-ON UNITS   .

-------
                    a
                        CZD
~^4~
         •;H
     !.(
       V..
/'on
                     i   *•<'.
                     IM •'.,'•
                    •i-W"

                                                 Coots A/6-
                                                           STATION
                                  >-	V
                                                                     P/LOr f*tArtT
                                                                              f — x —X,
                               //
                               /' SN\LTR
                               OFF»Ct-
                                              ri''f&#se
                                                        -£>L/sr/zeifc;i
                                                                             -*G43
                                                                             -- f,.f.
                                          6-^
                                                       SHELTER
                                                                       c
                                                                       k^.'^&(. Wi
           w'••*$>
                                         ^©•••fe.©,©-:-S
                                                                                    GENERAL NOTES: N.T.S.
                                                                                     DUCTWORK
                                                                                     TO FAN    100'
                                                                                     TO C.C.    20'
                                                                                     TO ESP     50'
                                                                                     TO STACK  150'
                                                                                    MAGMA: SMELTER AT
                                                                                    SAN MANUEL, ARIZ.
                                                                                    RETROFIT OF WET
                                                                                    ELECTROSTATIC PREC.
                                                                                    WITH A COOLING
                                                                                    (SPRAY TYPE) CHAMBER,
                                                                                    THICKENER, VACUUM
                                                                                    FILTER, ETC. AS ADD-
                                                                                    ON UNITS

-------
SMELTER
             DU-.-S7
                   •'/>.
              ST^CK
GENERAL NOTES:  N.T.S.

  DUCTWORK
  TO FAN     TOO'

  TO C.C.      20'
  TO ESP      50'
  TO STACK   130'
        R6F1MEUV
         OFFICE
                                     MAGMA: SMELTER AT
                                     SAN MANUEL, ARIZ.
                                     RETROFIT OF WET
                                     ELECTROSTATIC PREC..
                                     THICKENER, VACUUM
                                     FILTER, ETC. AS ADD-
                                     ON UNITS

-------
  TXA*A ****g*y,j\
  **tr#*»rJ'r£ "f/rs
             $ So  ^^MVEHTtR)[,  -_
                                           GENERAL NOTES: N.T.S.
;-l>.
                                            MAGMA:  SMELTER AT

                                            SAN MANUEL, ARIZ.


                                            RETROFIT  OF COOLING

                                            (SPRAY  TYPE)  CHAMBER

-------
STACK      .
 iCOUVtSTtR)
                      GENERAL NOTES: N.T.S.

                        DUCTWORK
                          TO FAN      100'

                          TO C.C.      20'
                          TO VENTURI   50'
                          TO STACK    130'
                       MAGMA: SMELTER TO
                       SAN MANUEL, ARIZ.

                       RETROFIT OF VENTURI
                       SCRUBBER, THICKENER,
                       VACUUM FILTER, ETC.
                       AS ADD-ON UNITS

-------
   I
,_/ -
 -T^/^ f
                                                            	V 	fc.
                                                            ic^frrl
                    A»^T
J"_
                                                     •f—x,
                                    //
                                   //SN\\JR
                                     OPF^Ct-
           •Xr-'-A li-- v" •-
           ^^.^V;
                                                                    J      ^
                                                                    J J/   ^ G
                                      :r«.
           n'str/sse
                                       /'.
                                        MAY
                                       tift-i
             rv
                     S BELTER
d
                                       ^ZZZl"
                                                     \
                              •^ •»
                             s
                                                                    *V7f
                                                                  SLoiJffc
                                                                    use:
  T/MF cez
                                                                     REFINERY
                                                                      OFFICE

      ^-s  f~\      '          " "••'
                                                         GENERAL  NOTES:  N.T.S.
                                                           DUCTWORK

                                                           TO FAN       100'
                                                           TO C.C.       20'
                                                           TO BAGHOUSE   50'
                                                           TO STACK     150'
                                                         MAGMA:  SMELTER AT
                                                         SAN MANUEL, ARIZ.

                                                         RETROFIT OF FILTER
                                                         BAGHOUSE, COOLING
                                                         (SPRAY TYPE) CHAMBER,
                                                         ETC. AS ADD-ON UNITS

-------
APPENDIX C
    C-l

-------
                                PEDCo  ENVIRONMENTAL
                                                11499 CHESTER ROAD
                                              CINCINNATI. OHIO 45246
                                                      (513) 7S2-4VOO
               TECHNICAL SPECIFICATIONS  FOR ADD-ON

                CONTROL SYSTEMS FOR  REVERBERATORY

             FURNACE AT PHELPS DODGE COPPER COMPANY,

                           AJO, ARIZONA
                            Prepared  by

                     PEDCo Environmental,  Inc.
                        11499 Chester Road
                     Cincinnati, Ohio    45246
                  PEDCo Project Number:   3287-B
                           June 28, 1977

                                 BRANCH OFFICES
CHESTER TOWERS
                          Crown Center
                         Kansas City. Mo.
Professional Village
 Chapel Hill. N.C.

-------
                      TABLE OF CONTENTS


                                                       Page

SCOPE OF WORK                                            1

GENERAL INFORMATION                                      3

DESIGN CRITERIA AND GUARANTEE                            3

SPECIFIC OPERATING CONDITIONS FOR ADD-ON EQUIPMENT       5

DESIGN LOADS                                             6

CONTROL SYSTEM SUPPORT STRUCTURE                        12

     ADD-ON CONTROL EQUIPMENT:  ELECTROSTATIC           12
     PRECIPITATOR, DRY TYPE

     ADD-ON CONTROL EQUIPMENT:  ELECTROSTATIC           18
     PRECIPITATOR, WET TYPE

     ADD-ON CONTROL EQUIPMENT:  COOLING CHAMBERS        19

     ADD-ON CONTROL EQUIPMENT:  VENTURI SCRUBBER        20

     ADD-ON CONTROL EQUIPMENT:  FABRIC FILTER           20
     BAGHOUSE

SKETCHES                                               A-l
                           11

-------
                       LIST OF TABLES
NO.
     Summary of Electrostatic Precipitator Design
     Parameters and Operating Data at Phelps Dodge
     Copper Company, Ajo, Arizona
                          111

-------
                      LIST OF SKETCHES






No.




A-l  Dry Electrostatic Precipitator                    A-l




A-2  Wet Electrostatic Precipitator/Cooling Chamber    A-2




A-3  Wet Electrostatic Precipitator                    A-3




A-4  Cooling Chamber                                   A-4




A-5  Venturi Scrubber                                  A-5




A-6  Fabric Filter Baghouse                            A-6
                          IV

-------
          TECHNICAL SPECIFICATIONS (COPPER SMELTER)





     It is the intent of these specifications to provide the



contractor with sufficient information to furnish and in-



stall gas-cleaning systems, including the control equipment



to treat exhaust gases from an already-installed electro-



static precipitator on a copper concentrate smelting rever-



beratory furnace at the Phelps Dodge plant at Ajo,  Arizona.



SCOPE OF WORK



     Major items of work to be accomplished by contractor



consist of the following:



     1.   Engineer, design, procure materials and equipment,



          fabricate, and erect from ground level from the



          discharge of the existing hot electrostatic



          precipitator flue to the inlet nozzles of the



          required add-on control equipment.  The contractor



          shall provide heat insulation on flues.



     2.   Engineer, design, procure materials and equipment,



          fabricate, and erect from ground level up the



          required support structure for the add-on control



          equipment, including all required walkways, stair-



          ways, and handrails.  The supporting structure



          system will exclude foundations, which will be



          supplied and furnished by others.

-------
3.   Engineer, design, procure materials and equipment,



     fabricate, and deliver add-on control equipment,



     complete with all electrical equipment required to



     place the unit into operation.



4.   Erect the add-on control equipment, including



     furnishing and installing heat insulation on the



     add-on control equipment where required.   The



     erection portion excludes furnishing wire and



     conduit or a control room for electrical equip-



     ment.



5.   Engineer, design, procure materials and equipment,



     fabricate, and erect from ground level up the



     discharge flues starting at the outlet nozzle



     flange of the add-on control equipment and termi-



     nating at the present discharge to the ducting



     utilized by the existing hot electrostatic pre-



     cipitator.



6.   Provide qualified personnel for the initial start-



     up of the complete system.  Start-up is to include



     all testing, adjustments, and modifications neces-



     sary to ensure proper operation of the units at or



     above the collection efficiency levels specified



     herein.  Start-up is also to include the training



     of owner's operating and maintenance personnel to



     operate and maintain the equipment.

-------
     7.    The contractor shall provide the services of a



          qualified Field Erection Engineer who shall give




          supervision and technical assistance as required



          during assembly, field erection, and start-up of



          the equipment.




     8.    The contractor will furnish a test model of the



          add-on control equipment and the flue systems for



          gas-flow study.



GENERAL INFORMATION



     An additional fan to handle the pressure drop shall be



included with any add-on control equipment.



     All electrical, water, and other services will be



within 100 feet of the new facilities.



     Site leveling and preparation by others.



     The units are to operate 24 hours per day, 365 days per




year.



     The layouts for particulate removal control system are



shown on attached Sketches A-l through A-6.  The length of




duct runs are shown on the sketches.



DESIGN CRITERIA AND GUARANTEE



     1.    Collection Efficiency



          The add-on control equipment will have a minimum



          guaranteed collection efficiency of 93 percent by

-------
     weight of the entering particulate matter as



     determined by EPA Test Method 5, with a filter



     temperature of 250°F.



2.    Efficiency Tests



     The owner shall make regular tests to check the



     collecting efficiency.  The contractor and owner



     shall jointly test the add-on control equipment



     for collection efficiency immediately after com-



     pletion of all construction, at 6 months and at 11



     months after completion.   The test at 11 months



     will determine the guarantee performance.



3 .    Efficiency Curves



     The contractor shall furnish with its proposal



     expected efficiency curves, showing the guarantee



     point.  Curves will show expected efficiency



     versus volume, grain loading, percent moisture,



     gas temperature, percent SO3 in gas,  percent lead,



     and any other significant parameters  affecting



     efficiency of the add-on control equipment.



4.    Draft Loss



     The draft loss between inlet and outlet flanges of



     the nozzles will be held to a minimum to attain



     the removal efficiency required.

-------
     5.    Gas Velocity




          The gas velocity through the precipitator proper



          will not exceed 3 feet per second;  and the veloc-



          ity through a venturi scrubber or baghouse shall



          be recommended by the vendor.



     6.    Gas Flow Study




          The contractor shall construct a test model of the



          system from and including the outlets of the waste



          heat boilers to the stack.



     7.    Redundancy



          The control equipment shall be sized with a con-



          fidence level of at least 90 percent when the



          system is operating at a full mode.



SPECIFIC OPERATING CONDITIONS FOR ADD-ON CONTROL EQUIPMENT



     The add-on control equipment will be capable of han-



dling copper smelting reverberatory furnace exhaust gases




described as follows:



     1.    Amount of gases per precipitator:  186,000 acfm.



     2.    Operating temperature of gases:  598°F.



     3.    Short-term temperature surges to 650°F during



          furnace charging periods.



     4.    Nominal dust particle inlet loading is 0.56 grain



          per SCF.  Estimated dust particulate inlet loading



          is 1.37 grains per SCF during furnace charging



          periods.

-------
     5.    Expected dust screen analysis mesh and percent:




          Not available.



     6.    Expected volumetric analysis of gas component and



          percent:  See attached Table 1.



     7.    Estimated bulk density of collected dust, dry



          pounds per cubic foot:  Not available.



     8.    Acid dew point of gas:  Not available.



     9.    Expected composition of dust:  Table 2 presents



          element analysis at existing electrostatic pre-



          cipitator inlet and outlet.



DESIGN LOADS



     This should include vertical live loads, lateral loads,



and earthquake considerations.



FLUE SYSTEM:



     1.    The flue system shall begin at the outlet flange



          of the existing hot electrostatic precipitator and



          proceed to the inlet flanges of the add-on control



          equipment.



     2.    The ductwork from the outlet flange of the exist-



          ing hot electrostatic preeipitator to the add-on



          control equipment shall be sized for minimum gas



          velocity of 3500 feet per minute under maximum



          future gas-flow conditions of 186,000 acfm.  This



          ductwork shall be rectangular in cross section,




          fabricated of 1/4-inch-thick (minimum) steel plate



          consistent with the acidity of the gas stream, and

-------
Table 1.  SUMMARY OF  PARTICULATE EMISSION DATA FOR EXISTING




  ELECTROSTATIC PRECIPITATOR ON REVERBERATORY FURNACE -




         PHELPS DODGE COPPER SMELTER, AJO, ARIZONA
Item
ESP manufacturer
ESP inlet conditions
Velocity, fps
Volume flow at con-
tinous rating, acfm
scfm
Temperature, °F
Gas dust loadings:
by instack filter.
gr/scf

Ib/hr

by instack/outstack
filter, gr/scf
Ib/hr

by EPA test method 5,
gr/scf
Ib/hr
ESP outlet conditions
Velocity, fps
Volume flow at con-
tinuous rating, acfm
scfm
Temperature, °F
Gas dust loadings:
by instack filter,
gr/scf

Ib/hr

Design
(l)a
Joy Western

at 13.8 psia
150,000°

75,000 (calc)
600 (max.)


2.25 (max.)6

1446.43
(calc max. )















0.063

40 (guar-
anteed)
Actual
(1)



164,000


450 to 550


0.592
(calc.)
42ie
















0.067
(calc)
47D

Radian
test results
July 6-16, 1976
(2)


55 to 5^
160,0003

77,580 (calc)
633


avg. 0.6 (9. 17
SRI test
results
July 9-10, 1976
(3)










to 1.55)e f
avg. 403 (calc)


1.56 to 2.4713
1041 to 1648
(calc.)




114

185,330
92,840 (calc)
598


0.021

13.44 (calc)





















Aerotherm
test results
July 15-30, 1976
(4)





















77.17
U
116,200"
59,500 (calc)
550 to 600


0.42 (calc)
V-
212. 8*


-------
            Table  1  (continued).   SUMMARY OF PARTICULATE EMISSION  DATA FOR EXISTING




                   ELECTROSTATIC PRECIPITATOR ON REVERBERATORY  FURNACE -




                           PHELPS DODGE COPPER SMELTER, AJO, ARIZONA
op
Item
ESP outlet conditions
(continued)
by instack/outstack
filter, gr/scf
Ib/hr

by EPA test method 5,
gr/scf
Ib/hr
ESP control efficiency, %
Dust size analysis
at ESP inlet
at ESP outlet
Gas composition, %

H20
°2
co2
S02
S03
Design
(l)a









96.83P










Actual
(1)




















Radian
test results
July 6-16, 1976
(2)



0.84 to 1.371
560 to 914
(calc.)







ESPS ESPS
inlet outlet
13.2 12.3
10.7 9.5
6.0 6.5
0.33 0.56
0.006 0.012
SRI test
results
July 9-10, 1976
(3)









96.7*3

>10ymr








Aerotherm
test results
July 15-30, 1976
(4)



0.83 (calc.)
423. 5"1


0.56 (calc.)
285. 4n




ESP3
outlet
12.2
13.6
4.1
8.1
0.0034

-------
Footnotes
a
  Numbers in parentheses represent corresponding references listed.
b Actual measurements in each of the two inlet ducts to the ESP were  55 and 57  fps, respectively.
c At 32°F and 14.7 psia.
d Average of six tests conducted on July 7 through July 10, 1976.  During the test runs,  the  volume  rate
  varies from 148,000 to 167,000 acfm.
e 1975 tests by Engineering Testing Laboratories, using WP Method 50, hard particulates only.
  -  , ct:'f £/1V! te8t run8 conducted ^ly 8 through July 10, 1976.  Actual emissions varied from 0.17
  to 1.55 gr/scf.
f According to Radian, the outlet sampling locations was much more favorable than the inlet and for this
  reason to gas flow rate obtained at the outlet 78,400 scfm was used to calculate the flow rates of gas
  through the ESP.  Based on this gas flow rate and average loading of 0.6 gr/scf, Radian calculated
  a mass flow rate of 340 Ib/hr.
9 Results of two test runs performed at a single point in the one duct (two ducts lead into ESP).  Test
  run 1 collected 0.58 gr/scf on instack filter and 1.89 gr/scf on outstack filter, and test run 2
  collected 0.31 gr/scf on instack filter and 1.25 gr/scf on outstack filter.
h Average of 11 tests conducted July 20 to 30, 1976, during which the volume flow was between 46,700 and
  70,000 scfm.
1 Average of five test conducted on July 8 to 10, 1976.  The minimum and maximum dust loadings obtained
  during the test were 0.017 and 0.025 gr/scf, respectively.
J 1975 tests by Engineering Testing Laboratories, using EPA method 5 with sulfates deducted.

  Average particulate collected on instack filter during two tests conducted by using instack/outstack
  filters on July 29 and 30, 1976.  The actual readings were 217.2 and 208.4 Ib/hr.
  Results of three test runs.  The actual readings were 0.97, 0.84, and 1.37 gr/scf.  Amounts collected
  on instack filters in these three test runs were 0.027, 0.072, and 0.019 gr/scf, respectively.
m Average of two test runs conducted on July 29 and 30, 197G.  Actual readings were 423.0 and 423.9 Ib/hr.
n Average of seven test runs during July 21-28, 1976.   The minimum and maximum readings were 216.2 and
  331.3 Ib/hr, respectively.
P Guaranteed efficiency based on instack filter tests.
^ Using instack filter method.
r Overall mass median diameter.
s Average of many measurements.

-------
  Table 2.  ANALYSES OF TOTAL PARTICULATE  (SOLID PHASE AND
    VAPOR PHASE PARTICULATE AT THE EXISTING ELECTROSTATIC
           PRECIPITATOR OUTLET (IN POUNDS PER HOUR)
Element
As
Ba
Be
Cd
Cr
Cu
F
Fe
Hg
MO
Ni
Pb
Sb
Se
V
Zn
Total particulate
(measured on
7/11/76)
140
ND
0.011
0.016
0.011
1.0
7.5
_
5.6xlO-3
0.16
0.085
0.079
0.33
0.97
0.062
0.082
Total particulate
(measured on
7/13/76)
76
0.64
3.4x10-3
7.6
0.044
18
9.4
0.55
0.033
0.17
0.011
0.38
0.030
0.65
0.027
0.22
Vapor phase
(measured on
7/16/76)
15
0.27
< 4x10-3
l.lxlO~4
0.036
2.94
11.0
0.196
0.062
0.016
0.031
8.7x10-3
3.0x10-3
0.21
0.020
0.036
  Existing ESP in operating at 598°F.

  In addition, 2210 Ibs/hr of sulfur was collected as S02
  and 50 Ib/hr sulfur as S03.

     (Radian Corporation conducted gas particulate sampling
on the reverberatory furnace and its control system at
Phelps-Dodge Copper Company during July 1976.  During the
sampling program, they measured the total particulate solid
phase and vapor phase, present in the existing electrostatic
precipitator outlet by using a wet electrostatic precipitate
sampler in series with a set of impingers.  They also
measured only vapor phase particulate content of the gas at
the existing ESP outlet by using a cyclone and filter to
separate solid phase particulate of the gas, and a set of
impingers in series to trap the vapor phase particulate.
Table 2 presents analyses of total particulate and vapor
phase particulate.)
                             10

-------
     be equipped with suitably reinforced stiffeners.



     An expansion joint in both the vertical and hori-



     zontal portions of this ductwork shall be pro-



     vided.  Any right-angle turns in this ductwork



     shall be of the largest centerline radius possible



     and designed to minimize pressure drop.  The



     interface between the throat of the right-angle



     turn and the gathering plenum shall be designed to



     minimize any particulate material buildup.  Turning



     vanes will be installed to streamline the flow



     where required.  Flue shall also be tapered so as



     to minimize the entry pressure loss.



3.   Outlets from the gathering flue to the nozzles of



     the control system shall be optimized and designed



     to provide uniform distribution of flow to the



     inlet nozzles, with a minimum pressure drop re-



     quired to achieve this optimization.  Each outlet



     shall also include an air-lock damper at the inlet



     nozzle to the add-on control equipment and all



     necessary platforms, headframes, and hoists re-



     quired for operation of the air-lock dampers.



4.   Expansion joints shall be provided at the inter-



     face of the inlet nozzles and the gathering plenum



     outlets.
                        11

-------
     5.   Gas sampling stations and access platforms shall



          be provided at points designated by the EPA method



          of testing.



CONTROL SYSTEM SUPPORT STRUCTURE



     The add-on control equipment support structure shall be



provided complete with access and stairway landings.  Struc-



tural elements required to support the add-on control equip-



ment, access walkways, and stairways should be designed to



provide clearance for any roadways or railroad equipment



that must continue to operate during construction and after



completion of the project.



ADD-ON CONTROL EQUIPMENT:



Electrostatic Precipitators;   Dry Type (Sketch A-l)



     1.   The electrostatic precipitators will be horizontal-



          flow, plate-type of heavy-duty construction and



          shall be sectionalized and compartmentized for



          flexibility.  Two separate inlet and outlet noz-



          zles are to be provided to make each compartment



          isolated from the other one.



     2.   Mild-steel, high-voltage insulator compartments



          are to be provided.  These compartments are to be



          insulated and heated by hot-air, positive-pressure



          blower systems utilizing electric heating and



          inlet air filtering.
                             12

-------
     3.    Access doors and internal walkways between elec-




          trical sections will be provided.




     4.    All access openings will be provided with an




          automatic key interlock system to  protect per-




          sonnel and equipment.  Structural  and component




          design will provide allowance for  free expansion




          so as to prevent permanent structure deformation




          from occurring at continuous gas operating tempera-




          tures of 600°F.




     5.    The precipitator housing is to be  able to with-




          stand the maximum internal negative pressure that




          might be created in operation.




PRECIPITATOR CASING




     1.    The precipitator casing will be of steel plate




          construction properly reinforced to withstand the




          acidity of the gas stream.  Materials will meet




          specifications as described in the latest edition




          of the ASTM Standards.




     2.    Inlet and outlet nozzles to precipitator are to be




          provided by the contractor.  Each  nozzle will




          include necessary internal supports, guide vanes,




          distribution plates and appropriately located U




          tube and sample ports.   Flanges for attaching




          flues are to be included.




     3.    Casing and nozzles will be fabricated from steel




          plate.
                           13

-------
HOPPERS



     1.   Dust hoppers will be located under the collecting



          sections and shall be V-shaped trough or bunker




          type.



     2.   Hoppers will be constructed of steel plate with a



          minimum thickness of 1/4 inch and to withstand the



          acidity of the gas stream.



     3.   Hoppers will be welded construction, having a



          minimum slope of 60°.



     4.   Each hopper will be provided with a 15" x 15" x 1"



          manual impact plate spaced at 3-foot centers along



          both sides of hoppers at accessible locations.



          Impact plate and poke holes are to be combined.



     5.   Provisions shall be made with double "Plattco"



          type valves or equivalent to prevent infiltration



          of air through the screw conveyors to the gas



          stream.



     6.   Screw conveyors shall be provided beneath all



          precipitator hoppers.  Conveyors shall be sized



          and powered to handle expected dust loading, but



          in no case shall they be less than 12 inches in



          diameter or have less than 7-1/2 horsepower



          drives.
                            14

-------
RAPPERS




     1.   Rappers are to be of the electromagnetic or drop



          hammer type with a heavy rapping force.



KEY INTERLOCKS




     1.   Key interlocks, to deenergize the unit, will be of



          lock and key type to protect operating personnel



          from high-voltage electrical equipment.  Inter-



          locks will be provided for the power panel, high-



          voltage switches, rectifier-transformer sets, and



          all access doors in the shell, housing, and hoppers



          that provide entrance into the electrodes in the



          high-voltage connections.




ELECTRODES



     1.   Collecting plate electrodes are to be minimum



          16/18 gauge steel and designed to provide minimum



          reentrainment of dust by gas stream during rapping



          periods to be compatible with the acidity of the



          gas stream.



     2.   Discharge wires or solid electrodes will be held



          in place parallel to and at equal distances from



          the collecting plates by structural steel frames



          hanging from high-voltage, with isostatically



          pressed alumina or equivalent support insulators



          located in the shell roof.
                             15

-------
     3.    Approximate spacing between collecting plates will




          be 9 inches.



RECTIFIER-TRANSFORMER SETS



     1.    Each precipitator field will be supplied with its



          own separately controlled rectifier-transformer




          set.



     2.    The selenixim rectifier-transformers will be 50%



          oversized, have adequate surge protection, and



          will be the oil-emersed, self-cool type.



     3.    The rectifier-transformer will be capable of half^



          wave or full-wave power by way of the associated



          switch.



     4.    Other accessories should include automatic con-



          troller, meters for primary current/ primary



          voltage, secondary current and secondary voltage.



PRECIPITATOR DISCHARGE FLUE



     1.    The precipitator discharge flue shall begin at the



          outlet nozzle flange of the precipitators and



          terminate at the interface of this flue with the



          same point of discharge now used by the hot



          electrostatic precipitator.



     2.    A manually operated poised-blade louver damper



          shall be installed at the outlet nozzle flanges of



          each precipitator.  Damper and operating mechanism



          shall be fabricated of type 316 stainless steel



          and shall have a minimum-leakage characteristic.
                            16

-------
     3.    An air-lock damper and an expansion joint shall  be




          installed between the flow-control damper and the




          main flue on each of the two precipitator outlets,




          along with all necessary platforms.




     4.    Gas sampling stations and access platforms shall




          be provided at points designated by EPA Method 5




          testing.




     5.    Structural elements required to support the dis-




          charge flue, access walkways, and stairways shall




          be designed to provide clearance for railway




          equipment that must continue to operate during




          construction and after completion of the project.




     6.    Expansion joints shall be provided as required to




          prevent permanent structural deformations from




          occuring at a continuous operating temperature of




          600°F.




PRECIPITATOR REDUNDANCY



     1.    The precipitation equipment shall be designed so




          that guarantee is met with one full-width elec-




          trical field out of service.




     2.    The precipitation equipment shall be sized with a




          confidence level of at least 90 percent when all




          fields are in service.
                            17

-------
Electrostatic Precipitator;   Wet Type (Sketch A-2 & A-3)



     See attached Sketch A-7 for the wet electrostatic




precipitator circuitry.



     The portions of the specification for the dry electro-



static precipitator that are applicable to the wet electro-



static precipitator shall apply.



     The following factors shall be included:



     1.   Materials of construction shall withstand the



          corrosive atmosphere of acidity present in the gas



          stream.



     2.   If the wet ESP system as shown in Sketch A-7 is



          quoted as a complete system with hold tank, pH



          control, clarifier, vacuum filtration, pumps,



          etc., identify the major materials of construc-



          tion, gpm, and estimated sludge discharge  (in gpm)



          to the pond.



     3.   If the wet ESP system as shown in Sketch A-3



          consists of only the electrostatic precipitator,



          indicate the gpm of water required, the number of



          nozzles for water sprays being supplied, and the



          head in inches of water required at the point of



          discharge into the precipitator, amount of water



          required for flashing and water flushing frequency.



          Also the estimated gpm discharged from the hoppers
                            18

-------
          of the wet electrostatic gravity, and the gpm of



          make-up water required.




     4.   As shown in Sketch A-2, a cooling chamber ahead of



          the wet-electrostatic precipitator would cool the



          gas to 250°F (+25°F) prior to its entry into the



          wet electrostatic precipitator.



     5.   As shown in Sketch A-3, the wet electrostatic



          precipitator receiving a gas stream at approxi-



          mately 600°F would discharge the cleaned and



          cooled gas stream at 250°F (+25°F).



     6.   The removal efficiency required would be 93%.



COOLING CHAMBERS:  (Sketch A-l, A-2, A-4,  A-6)



     Supply a complete system consisting of but not limited



to the following:  two cooling chambers of the downflow type



and dry bottom design with a water filtration and pumping



system, automatic apparatus for control of exit temperature,



and all necessary piping, insulation, etc.  Also supply the



supports and ductwork, with insulation, to convey the cooled



gases at 250°F (+25°F) from the discharge of the cooling



tower to the precipitator.  The chamber will have clean-out



doors permitting man-entry and front-end unloaders for



clean-up purposes.



     The water system will be a closed-loop type.  The




materials of construction shall be compatible with the




corrosive atmosphere of the gases.
                            19

-------
     Foundations will be by others.



VENTURI SCRUBBER:  (Sketch A-5)



     Supply a complete system consisting of but not limited
                                              \


to the following:  one venturi scrubber with a holding tank,



pumps, piping, variable-throat control, pH control, clari-



fier, vacuum filtration, flocculant additive system, struc-



tural supports, walkways, platforms, insulation, valving,



ductwork as required, demister, etc.  The pressure drop will



be suggested by the bidder.  The materials of a construction



shall be compatible with the corrosive atmosphere of the



gases.



     The water system will be a closed-loop type.



     The materials of construction shall be compatible with



the corrosive atmosphere of the gases.



     Foundations will be by others.



FABRIC FILTER BAGHOUSE:  (Sketch A-6)



     Supply a complete system consisting of but not limited



to the following:  one fabric filter  (pulse-jet type, etc.



will be left to the discretion of the vendor) , bagliouse,



readily changeable bags, clean-out doors for interior clean-



ing of collectors and inspection; cooling chambers, pumps,



piping, etc.  The bags and all materials of construction



shall be compatible with the acidity of the treated gases.



Temperature of gases to the baghouse will be 250°F (+25°F).
                            20

-------
GENERAL DESIGN COMMENTS:




     1.   All systems will be tabulated and broken down into




          major components, i.e., electrostatic precipitator,




          ductwork, structural steel, controls (electrical,



          etc.) with their erected costs.



     2.   Each major piece of equipment  (i.e., electrostatic



          precipitator, baghouse, etc.) will be reported as



          to square feet of collection area, number of



          fields, rapping force, type of electrodes, mate-



          rials of construction, total weight in tons, size,



          height, duct size, number of bags, size, type,



          etc.).



     3.   Annual operating costs with quantities of elec-



          tricity, water, etc. used; operating manpower,



          maintenance manpower and costs; estimated life of



          the control equipment.



     4.   Equipment shall be in conformance with the National



          Electrical Code, OSHA, Federal, State, and local




          regulations.



     5.   Satisfactory performance tests will be as indi-



          cated in the dry electrostatic precipitator.
                            21

-------
SKETCHES

-------
  PHELPS DODGE AT
  AJO, ARIZONA
  SK-A-1
  DRY  ELECTROSTATIC
  PRECIPITATOR
GENERAL NOTES: N.T.S.
  DUCTWORK
  TO FAN    20.0'
  TO C.C.    20.0'
  TO ESP    45.0'
  RETURN   140.0'

-------
             .  .. ?*.i-j£i '.~TL ?31-<•;!.
  -V40.-  -1	<*•-»-:•<>--
                                                                                        PHELPS DODGE AT
                                                                                        AJO, ARIZONA
                                                                                        SK-A-2
*"m  RIB]  .
                                                                                        WET ELECTROSTATIC
                                                                                        PRECIPITATOR
CB/.\.LOOM  » LUE C
                 LIU	_
                                                                                                  GENERAL NOTES:  N.T.S.
                                                                                                    DUCTWORK
                                                                                                    TO FAN   20.0'
                                                                                                    TO C.C.  20.0'
                                                                                                    TO ESP   45.0'
                                                                                                    RETURN  140.0'

-------
                                                                                                             crrw?
         PHELPS DODGE  AT
F \LTEg.   AJO, ARIZONA
r WM w  .	I - *  tt-«
	'  RIB  .
                                                                                                   WET  ELECTROSTATIC
                                                                                                   PRECIPITATOR
                                                                                             GENERAL NOTES: N.T.S.
                                                                                               DUCTWORK
                                                                                               TO FAN    20'
                                                                                               TO ESP    45'
                                                                                               RETURN   110'

-------
                           uiTh/ouT
                 6-c- * outr
                 TO ACID
                                         PHELPS DODGE AT
                                         AJO,  ARIZONA
       UUCT
TO  sr A. ci<
                                         SK-A-4

                                         COOLING  CHAMBER
                                     GENERAL NOTES: N.T.S.

-------
/ !   C/r
      PHELPS  DODGE AT
      AJO, ARIZONA
     SK-A-5
     VENTURI SCRUBBER
   GENERAL NOTES: N.T.S
     DUCTWORK
     TO FAN       20.0'
     TO VENTURI   50.0'
     RETURN      110.0'

-------
   PHELPS DODGE AT
   AJO, ARIZONA
GENERAL NOTES: N.T.S.
  DUCTWORK
  TO FAN      20.0'
  TO C.C.     20.0'
  TO FILTER   45.O1
  RETURN     140.0'

-------
APPENDIX D
    D-l

-------
         EPA PROCESS WEIGHT REGULATIONS:




PARTICULATE MATTER FROM STATIONARY PROCESS SOURCES,
                       D-2

-------
Subpart P — Standards of Performance for
        Primary Copper Smelters 26


{MM Ml   Apiilirnltililjr  ami (Initiation
    of »(Tc<-U-d furilil)-.

  The provisions of this Kubpart are ap-
plicable to the following affected facilities
in  primary  copper  smelters:   Dryer.
roaster,  smelting  furnace,  and  copper
converter.
{AIM A I
  As used in this subpart, all terms not
defined herein shall have  the meaning
given them  in the Act and in subpart
A of this part.
  (a) "Primary  copper smelter" means
any installation  or  any  Intermediate
process  engaged  in the production of
copper from  copper sulfide  ore concen-
trates through the use of pyrometallurgl-
cal  techniques.
  fb> "Dryer"  means  any facility In
which a copper sulflde ore concentrate
charge Is heated In the  presence of air
to  eliminate a portion of  the moisture
from the charge, provided less  than 5
percent of the sulfur contained In  the
charge Is eliminated  In the facility.
  (c) "Roaster"  means  any  facility In
which a copper sulfide ore concentrate
charge Is heated In the presence of air
to eliminate a significant portion (5 per-
cent or more)  of the sulfur contained
in the charge.
   "Total smelter charge" means the
weight (dry basis)  of all copper sulfides
ore concentrates processed at a primary
copper smelter,  plus the weight of all
other solid materials introduced Into the
roasters and smelting furnaces at a pri-
mary copper smelter, except calcine, over
a one-month period.
  (1)  "High level of volatile Impurities"
means a total smelter charge containing
more than 0.2 weight percent arsenic, 0.1
weight percent antimony, 4.5 weight per-
cent lead or 5.5 weight percent zinc, on
a dry baiU.
§ 60.162  Slandurd for pirlirnUir  mul-
     \er.

  (a) On and after the date on which
the performance test required to be con-
ducted by 5 60 8 is completed, no owner
or operator subject to the provisions of
this subpart shall cause to be discharged
Into the atmosphere from any dryer any
gases which contain particulate matter
In excess of 50 mg/dscm (0.022 gr/dscf).


§ 60.163  Standard for nulfur 
-------
§60.166  TrM  mrllitid* and prarriliireii.
   (a>  The  reference  methods  In Ap-
pendix A to this part, except as provided
for in S 60.8 For Method 5, Method 1 shall  be
used for selecting the sampling site and
the number  of traverse points, Method 2
for determining velocity and volumetric
flow rate and Method 3 for determining
the gas analysis. The sampling time for
each run shall be at least 60 minutes and
the minimum sampling volume shall be
0.85 dscm (30 dscf) except that smaller
times or volumes,  when necessitated by
process variables  or other factors, may
be approved by the Administrator.
             D-4

-------
8 52.12ft  Control Mratcpy  anil  regula-
    tion*: I'iirlivuliilc mutter.
  (a) The requirements of §551.13 and
51.22 of this chapter are not met since
the plan does not provide the degree of
control  necessary to attain and main-
tain the national standards for particu-
late  matter  in  the  Phoenix-Tucson
Intrastate Region.  Therefore,  Regula-
tion 7-1-3.6  (process industries)  of  the
Arizona Rules and .Regulations for  Air
Pollution Control,  Rule 3,1 (E)  (process
Industries i  in  Regulation  III  of  the
Maricopa County Air Pollution  Control
Rules and Regulations, and  Rule 2(Bi
 (process industries) in Regulation II. of
the Rules  and Regulations of the Pima
 County Air Pollution  Control  District
are disapproved for the Phoenix-Tucson
 Intrastate Region."
   (b)  Replacement regulation for Regu-
 lation  7-1-3.6 of the Arizona Rules  and
 Regulations for Air Pollution Control,
 Rule 3KE) of Regulation III of the Mari-
 copa County Air Pollution Control Rules
 and Regulations, and Rule 2(B) of Reg-
 ulation II of the Rules and Regulations
 of  Pima County Air Pollution  Control
 District (Phoenix-Tucson Intrastate  Re-
 gion).—(1) No owner or operator of  any
 stationary process source in the Phoenix-
 Tucson Intrastate Region (§ 81.36 of  this
 chapter)  shall discharge or cause  the
 discharge of participate matter into the
 atmosphere in excess of the hourly rate
 shown in the following table for the proc-
 jss  weight  rate  identified  for such
 source:
Proem
weight rat*
(pounds
per hour)
W
100
(00 	
1,000..
8,000
10,11110. .
ao.ouo

Emission
rate
(pounds
per hour)
0 X
0 55
1.53
2.25
ft 31
9 73
14 IW

Process
weight rale
(pounds
per hour)
60 000
ftO 000
120 000
100 nou
2IX) 01)1)
400 1)111)
1 000 OUO

Emission
rate
(pounds
per hour)
29.60
31.19
33.28
14. US
3fi. 11
40.36
40. n

    (i)  Interpolation of the data in the ta-
  ble for process weight rates up to 60,000
  Ibs/hr shall be accomplished by use of
  the equation:

          E = 3.59P"M  F<30tons/h

  and Interpolation and  extrapolation of
  the data for process weight rates in ex-
  cess of 60.000 Ibs/hr shall be  accom-
  plished by use of the equation:
         £ = 17.31 P°."  P> 30 tons/h
  Where: E = Emissions In pounds per hour
        P= Process weight  In tons  per hour
  Cii) Process weignt is the cotai weign>
of all materials and solid fuels introduceu
into any specific  process. Liquid  and
gaseous  fuels and combustion air will
not be considered as part of the process
weight. For a cyclical or batch operation,
the process weight per hour will be de-
rived by  dividing the total process weight
by the number of hours in one complete
operation  from  the beginning of  the
given process to  the completion thereof,
excluding  any time during which  the
equipment is idle. For  a continuous op-
eration,  the process weight per hour will
be derived by dividing the process weight
for a given period of time by  the num-
ber of hours in that penod.
  (iii) For purposes of this regulation,
 the total process weight from  all similar
 units  employing a similar type process
 shall be used in determining  the  maxi-
 mum  allowable  emission  of participate
 matter.
   (2)  Paragraph  'b;(l> of this section
 shall  not  apply  to  incinerators,  fuel
 burning installations, or Portland cement
 plants having a proce-,:; weight rate in
 excess of 250,000 Ib/h.
   (3) No owner or operator  of a Port-
 land cement plant in the Phoenix-Tucson
 Intrastate Region (§ 81.36 of th;s  chap-
 ter) with a process weight rate in excess
 of 250,000 Ib/h  shall discharge or cause
 the discharge of participate matter into
 the atmosphere in excess of the amount
 specified in  § 60.62 of this chapter.
    (5) The  test  methods and  procedures
 used  to determine compliance with this
 paragraph are set forth below. The meth-
 ods referenced  are contained in  the ap-
 pendix  to part 60 of this chapter.  Equiv-
 alent methods  and procedures may  be
 used  if approved by the Administrator.
    (i) For each sampling repetition, the
 average  concentration  of  participate
  matter  shall be determined by  using
 method 5.  Traversing during sampling
  by method  5 shall be according to  meth-
 od 1. The minimum sampling time shall
 be 2  hours and the minimum sampling
 volume  shall be  60 ft1 (1.70 m1), cor-
 rected  to standard conditions on  a dry
 basis.
    !cctii!cr.t rcouic.ticn /or Regu-
lation 7-.'~'!*c)  (Fasil fuel-fired sti-am
tj,. -i-.'ratjrs i.-t Ckc  four Curncrs  Intcr-
sU-le r.so'.on) . (1) Tins pai-agrai/ii ;:; sxp-
V/ik"il>.i!  to the  fossil fuel-nren  i.team
generating  equipment  designated  as
Units :,  L', and 3 it the Nav.ijo Power
Pla,;',. in  the A:';/.ona pori.on of the Four
Corners  Interstate  Region  (§ S1.11U oi
this chapter) .
   (2) No owner  or operator ol the fossil
 fuel-fired steam generating equipmem
 to  which this  paragraph  is  applicabl*
 shall discharge or cause the discharge ol
 sulfur oxides into the atmosphere in ex-
 cess of the amount prescribed by the fol-
 lowing equations:
 where:  E — Allowable sulfur oxides emissions
            (lb./lO«B t u.).
      e = Allowable suuur oxiaes enuvjioua
           (gm/10" gm.-c«l.).
      S = Sulfur content.  In  percent  by
           weight, of fuel being burived.
      7/ = Hcat content of fuel (B.t.u./lb.).
      7i = Heat  content of  fuel  (gm.-cal./
           gm.) .

   (3) For  the purposes  of this para-
graph :
   (i)  E shall not exceed 0.90 Ib.  SO'/IO*
B.t.u. (1.6 gm.  SO./10* gm.-cal.).
   (ii) If emissions  are less than  0.16 Ib.
SO:/10* B.t.u. (0.29 gm'. SO/10' gm.-cal.) .
the requirements of paragraph (c) (2) of
this section shall not apply.
   (4) Compliance  with  this  paragraph
shall  be in accordance with  the provi-
sions of § 52.134 (a).
   (5) The  test methods and procedure;
used to determine compliance with this
paragraph  shall  be those  prescribed In
§ 60.46 (c), (d), and (e) of this chapter.
                                                        D-5

-------
EPA TEST METHODS 1 THROUGH 8 PROCEDURES
                 D-6

-------
  THURSDAY, AUGUST 18,1977
        PART II
 ENVIRONMENTAL
    PROTECTION
      AGENCY
    STANDARDS OF
 PERFORMANCE FOR NEW
  STATIONARY SOURCES
  Revision to*Refercnce Method f-8
D-7

-------
                                                                                                               • t
417S4
     CHAPTER
         PROTECTION AOO4CV
PART  60— STANDARDS OP PERFORM-
ANCE FOR NIW STATIONARY SOURCE*

    ftevteton to Reteranea HotfMfe l-»
AOTOCT:  Eavlroemaratftl  Prot«cHo»
Agency.

ACTION: Final Bute
SUMMARY: This rule revises Reference
Methods 1 through 9, the detailed re-
quirements  used to  measure emission*
from affected  facilities  to detennln*
whether  they are in compliance with a
standard of pert ormance.  The methods
wera originally promulgated December
23, i»71. and since that time several re-
vtetae became apparent  which would
clarify, correct and improve the mettt-
odd. These revisions  make the methods
easier to us®, and Improve their accuracy
and reliability.
            DATS: September 19.

ADDRESSES: Copteo of the comment
letters are available for public Inspection
and copying at the UJ3. Environmental
Protection  Agency, Publle  Information
Reference  Unit  (EPA Library). Room
2932, 401 M Street, S.W.. Washington,
D.C. 20460. A summary of the comment*
and EPA 'a response*  may  be  obtained
upon written request from the EPA Pub'
lie  Information  Center (PM-218).  401
M Street. 8.W, Washington. D.C. 204«C
(specify  "Publlo  Commeot Summary:
Revisions to Reference Methods 1-1 In
Appendix A of Standard! of Performance1
for New Stationary Source*").

FOB FUKTHKH INFORMATION CON-
TACT:

  Don R. Goodwin, Emission Standards
  and Engineering Division,  Environ-
  mental Protection Agency, Research
  Triangle Park.  North  Carolina 27711,
  telephone No. S19-541-5371.

SUPPLEMDJTABY   INFORMATION:
The amendments  were proposed on June
8. 1976 (40  FB 23060) . A total of 50 com-
ment letters  were received during  the
comment period — 34 from  Industry. 19
from governmental agencies, and 9 from
other interested parties. They contained
numerous suggestions  which were Incor-
porated in the final revisions.
  Chaagae  comrade to all eight of  the
reference methods are: (1) the clarifica-
tion of procedures and equipment spec-
ifications resulting from the comments,
(2>  the  addition of guidelines for aJ-
.temative procedures and equipment to
make prior approval of the Administra-
tor unnecessary and (3) the addition of
an  Introduction to each reference meth-
od  discussing  th« general use  off  the
method  and delineating the procedure
for using alternative methods and equip-
ment
  Specific changes 69 toe me&ods are:

              MBTHGSJ 1
  1. Th« provision for the  us® of more
than two traverse diameters, when spes-
      RULfS AND  REGULATIONS

ifled  1*r ta* Administrator, has  bees*
deleted. If one traverse diameter is in a
pla&e containing the greatest expected
concentration variation, the  Intended
purpose of the deleted paragraph will be.
fulfilled.
  a. Based on recent data from Fluldynt)
(Parttculat*  Sampling  Strategies  for
Large Power Plants Including Nonuni-
form  Flow,  EPA-aoo/a-7«-170,   Juns>
1979)  and  Entropy Environmentalists
(Determination of the Optimum Number
of Traverse Points:  An  Analysis  of
Method 1 Criteria (draft), Contract No.
88-01-3173),- the number  of traverse
point* for velocity measurements  has
been reduced and the 2:1 length to width-
ratio requirement for cross-sectional lay-
out of rectangular  ducts has  been re-
placed by A "balanced matrix" scheme.
  3. Guidelines for  sampling In stack*
containing  eyctoale flow  and  stacks
smaller than about  031  meter in diam~
eter or 0.071 m* in  cross-sectional are*
will be published at a later date.
  4. Clarification has been mad* as to
when  a check for cyclonic flow Is neces-
sary;  also, the suggested procedure for
determination of unacceptable flow con-
ditions has been  revised.

              MKHOB »
  1. The calibration of certain pitot tubes
has been made optional Appropriate con-
struction and application guidelines have
been Included.
  2. A detailed calibration procedure for
temperature gauges has been  included.
  3. A leak  check  procedure for  pitot
lines has been included.
              MRHOB S

  1. The applicability of the method has
been  confined to fossil-fuel combustion
processes and to other processes where It
has been, determined that components
other  than O,. CO.,  CO,  and N, are not
present  in concentrations  sufficient to
affect the final results.
  2. Based on recent research  informa-
tion (Partitulate Sampling Strategies for
Large Power Plants Including Nonuni-
form  Plow,  EPA-600/2-76-170,   June
1970), the requirement for  proportional
sampling has been dropped and replaced
with the requirement for constant rate
sampling. Proportional and constant rate
sampling have been found to give essen-
tially  the same result.
  3. The  "three consecutive" require-
ment  has been replaced  by "any three"
for the   determination  of  molecular
weight, CO,  and  O*.'
  4. The equation for excess air has been
revised to account for the presence of CO. •
  9. A clearer distinction has been made
between molecular weight determination
and   emission  rate correction  factor
determination.
  6. Single  point,  integrated  sampling.
has been Included.

              MITHOB 4-

  1. The sampling  time of  1 hour has
been changed to a  total sampling time
which will span  the length of time the
pollutant  emission rate  is being deter-
mined or such time as  specified  in aa
appllca&to subpart of the standard*.
   3. Th» requirement for proportional
 sampling has been dropped and replaced
 with the requirement for constant rate
 sampling.
   3. The leak check before the test run
 has been made optional; the leak check
 aft^y th^ ru& remains mandatory.

              METHOD  ft

   1.  The  following  alternatives- have
 been included in the method:
   a. The use of metal probe linen.   -
'  b. The use of other materials of con-
 struction for filter holders  and probe
 liner part*.
   o. The use of polyethylene wash bot-
 tles and lamp1^ storage containers.
   d. The use of deslccants other than
 silica  gel  or- ralclnm  sulfate,  when
 appropriate.
  . e. The use of stopcock  grease other
 than silicons grease, when appropriate.
   f. The drying of filters and probe-filter
 catches at elevated temperatures, when
 appropriate.
   g. The combining of  the  filter and
 probe washes into one container.
   3. The leak check prior to a test run
 has been made optional. The post-test
 leak check remains mandatory. A meth-
 od for correcting sample volume for ex-
 cessive leakage rates has been included.
   3. Detailed leak check and calibration
 procedures for the metering system have
 been included.
              Mrrao*. 8

   1. Possible interfering agents of the
 method have been delineated.
   2. The options of: (a) using a Method
 8 impinger system, or (h>  determining
 SO,  simultaneously  with  partlculats
 matter,  have  been  Included  in the
 method.
   3. Based OB recent research data, the
 requirement for  proportional sampling
 has been dropped and replaced with the
 requirement for constant rate sampling.
   4. Testa have shown that Isopropanoi
 obtained from commercial sources oc-
 casionally has peroxide impurities that
 will cause erroneously low SOi measure-
 ments. Therefore, a test for detecting
 peroxides In Isopropanoi has been  In-
 cluded in the method.
   5. The leak check before the test run
 has been made optional; the  leak check
 after the run remains mandatory.
   6. A detailed calibration procedure for
 the metering system has been Included
 in the method.

              MSTHOO 7
   1. For variable wave length  spectro-
 photometen, a scanning procedure  (or
 determining the point of maximum ab-
 sorbance has  been incorporated as aa
 optic*.
              MSTBOB S

   1. Known interfering compounds hare
 been listed to  avoid misapplication of
 the method;
   a.  The.  determination of  filterable
 particulate matter (Including acid mist)
 simultaneously  with SO, and SO, has
 been allowed where applicable.
   3. Since occaaatonaUy  some commer-
 cially available quantities of Isopropanoi
                             ras«M MWTsa. vot, 43, NO. 1*0—THUIJOAV, AIKMJST it. 1*77
                                                     D-i

-------
                                        AND
                                                              4I755
  Have peroxide Impurities that wffl oaus*
   betarion of Bctbod* IB thb app«n41i I
 •a ao •Ddomment or tenU) of Ihtir appUoabllltj u>
           K, & test T^JT pci t>i.ld8s bi
  panol has been included to the method.
    4. The gravimetric technique for mois-
  ture content  (rmther  than volumetric)
  hae been ipeclfled because a  mixture of
  Isopropyl alcohol and water will have a
  volume less than the cum of the volume*
  •fits content.
    ~t.  A  closer correspondence  has been
  made between  similar parts of Methods
  tandS.
                •AlSCCLLAMEOUS

    Several  commenters  questioned  the
  meaning of the term  "subject to the ap-
  proval of the Administrator"  in relation
  to using alternate test methods and pro-
  cedures. As  defined In I 00.2  of subpart
  A, the "Administrator" Includes any au-
'  thorlzed representative  of  the  Adminis-
  trator  of the Environmental  Protection
  Agency. Authorized representatives  are
  f2PA officials in EPA Regional Offices or
  State, local, and regional governmental
  officials who have been delegated the re-
  sponsibility of enforcing regulations un-
  der 40 CFR 60. These officials in consulta-
  tion  with other staff members  familiar
  with technical aspects of  source testing
  will render  decisions regarding accept-
  able  Alternate  test procedures.
    In accordance with section  117 of the
  Act,  publication of  these  methods  was
  ejteteJed by consultation with appropri-
  ate  advisory  committees, Independent
  experts, and Federal  departments, and
  agencies.

  . M-404, «4 Atftt.
  1603; *ec. i(a) of Pub. L. Mb. 61-004. M Btat.
  U87; eec. 9 Of Pub. U No. 90-148, 81 Btat. MM
  |«3 U.S.C. lH7e-e. IM7o-«, 186Tg(ft) ).)

  ^ Hon.— The   •JtovlronmentaJ   Protection
  agvnc; baa determined that  thla document
  doe* not contain • major propoeeJ requiring
  SjMpentton of an •oonomic Impact Analyst*
  under Kxecutlre Orden 11831 and 11M9 and
  OUB Circular A-107.

    Dated : August 10, 1977.

                  DOUGLAS M. OOSTLE,
                         .• JUlmtMittrator.

    Part 60 of Chapter X of Title 40 of the
  Code of Federal Regulations Is amended
  by  revising Methods 1 through 8 of Ap-
  pendix   A — Reference   Methods    «s
  follows:

         AFPENDtx A— Hxntaxxcx IICIBOM
    The reference methods ID thh Bppr 'ill err wrenrd to
  to 140.8 (Performance TMU) end I «0. 11 (Compliance
  With Standards end Maintenance Reqatramntt) of *0
  CFR Pert 60, Buhpert A (Omen) Piuviitom). Specific
  BOM of these reference methods ere described tn the
  efandardt of performance contained tn  tbt fnbparta,
  bee luninf with Bubnart D. .
    Within wen standard of performance, t section titled
  "Test  Methods  and  Procedures" si provided to (1)
  Identify the test methods applicable to Uu
  •object to the iwpecUTt tUnaird and (2) IdeoUty ao;
  »peel»l IciinicUoiu or eoudltlom to b« fcllowfd wbco
  apply IK a nuthod u> tbt rctpMtlTe kdllt^. Bueb In-
  •InicUont (for uamplt, wUbUab •ampling latct TO)-
  •m*>, or Umpwaturai) an to be oasd elibw lo addition
  to, or M a lubtUtuU tor procodnr** In a nltitoet nwtliod.
  SlmiWIy. lor louraM mb)«et to unlKton mODiurti^
  nqoiremcou, ipectftc itutnietloni pcrtalnlnf to any HM
  •f a ralerenoe BMUtod an prorMvd la UH iitbpan «r la
  Apptndii B.
     ttrtbod* tn pofeflUalrx «ppbtab>» to othw t
     iver, applleablUty tboujd b* oonfirmrd by tartful
 and appropnatf traiuatioo of UM eoodlUoiu pnraluii
 at *neh louroei.
  ' Tbt approach feTJovtd In th* fennnlatton of UM rcf-
 OMOM metbodi IOTOITM tpcdlVoaUora  tor  tqarpacDt.
 procwdurrs, and pertonntnrr. ID oODocpt. a porfcji uianrr
 •ptelficallon approacb would b* Dnfarablr in all mttbodi
- bteaoM thu iJlowi the fnateti ftdlbUlly lo the otrr
 In prvllct, hoveTcr, tbii approacb U IrapncUcal In moil
 ratrn  bccanw  prrtonutnet cpeclflcatfora  cannot bt
 •Mabllshed.  Most »f tht roetbodj  dtterlbrd bertln
 Uvreforr, InToUt tpKlfic «]mmnenl cpKiftraiioni and
 prorrdurn. and onl; t few mrUiodi In tLu a|ipo>du r*ly
 on perlonntnn crilrrlt.
   Minor  chaniH In Ibt  nfcrenot mrtbodi aboold not
 rMmmrily  tlt'-rl th» Tilidliy of Ihr rrturu and  II  to
 nvngnlrx)  tbai tltfmahTt and *milT»lrnt mtthodi
 nltt Section MJ K provldet aKborlti for  tht Administra-
 tor lo ipfcify  or approve 0) tqolTtlenl method], (2)
 allmutlTe  mffhoda, and  (I) minor ehanfrc In tbe
 metbodolory of Wit nioranre mflhodi It thonld b>
 clearly andrmobd  that  nnkae otberwiw kteotined all
 •ucb m* Ihodf and dhanf «e mult have prior approTt)  of
 In* AdmtnlntraloT. An owner employlnf >urh mttbofli or
 4evtabons irtrm the reference methods without dblalninc
 prior approi-ftl  dora to tt the rt«k of mtnx|u>nl dlaa|v
 proral and relMlini wltb approrodarUiods.
   •Titbin tbe ralerane* mctbadi. certain •yrclftc eqolp-
 ue-nt or proctdunt an raoornlMd at btlnt aonptable
 or potentially acceptable and arc ipfclflc*lly Identified
 tn tbt metbodt. Tbt lUnu MtnUfltd M acceptable op-
 ttoiu ma; b> n»d withottt approval but n»ut bt Idtnu-
 ftod la tb» t«ft report. Tbt potentially  approTable op-
 ttoot are aMed a> "nb]e«t to tbe approral of iht
 AdmlnMrator" or ai "or oqnlTalent." Buch potentially
 •pprovible ttennlquM or altcmatlT*s may bt njeetlOD2.4),  (113 In.') la aim lac
 ttonal ana, or (8) tbe meaniremtnl rite li txai than two
 •tack or duct diameters downstream or !«• than a half
 ejametn utaueaiii from a Bow disturbance.
   The requirements of this method most bt aDnddered
 Mbn otmitroctkm of a new facility from which emiarioni
 vfll be meamred; tallore to do so may nxjulir so berg arm
 -alttrsttons 10 Ibt stack or dtvlation from tbe standard
 procedure CMgs  Involvinc variants an  sablect to tp-
 pnrva) by  tbe  Administrator,  TJ.B. Environmental
 ProtecUon JLstnry.
   X.I Baterlon  ef  Meaaorrmmt  Bite.  Bempllnf  er
 velocity BMasonment Is performed at a site knated at
 least esjhl suck or duet diameters downstream and two
 • distances:

                  «    aiR'
                              1, VOL 4J, MO.  ls>0  IHUtlDAT, AHOUn 18. 1*77
                                     D-9

-------
4175ft
                            RUlU AH® REOUUriQNt
    SO
    40

 8
 UC
      O.S
DUG? DIAMETERS UPSTREAM FROM PLOW DISTURBANCE (DISTANCE A>

                1.0                       1.§                       2.0
                                                                 2.5
                     I
                 I
I
I
I
 I30
     20




 S

 I  10
\ I'
1
T
A

i
1

•
\
1




I
i
DISTURBANCE

MEASUREMENT
:- SITE

*
DISTURBANCE
r— i - .
                FROM POINT OF ANY TYPE Of
                DISTURBANCE (BEND, EXPANSION. CONTRACTION, ETC.)
                     I
                                                             6
                                                                      8
                                                                 10
               DUCT DIAMETERS DOWNSTREAM FROM FLOW DISTURBANCE (DISTANCE B)


                Figure 1-1.  Minimum number of traverse points for particulate traverse*
                                        where £-lencth and If-width.
                                         2J Determining Uw Number ol Tr»T«rse Point*.
                                         2.2.1 ParttouUU Traverse!. When the ei»ht- and
                                        two-diameter criterion can be met, the mi,.im.im n umbel
                                        ol travera poLnU ahtll bet (1) tweln. Cor clrcolaf of
                                        reottnfnlmr itioki with dlunetan (or equivalent dl-
                                        uneton) pmtar thtn O.«l  meter (M la.); (2) elf ht, tot
                                        circular itteki with dUnuten between 0.30 uid 0.m«t«r criterion cumat b*
                                        met, the minimum number of traverse polDU Is deter-
                                        mined from Figure 1-1. Before referrlnc to the flfure,
                                        however, determine the dl5taoeee from the chown me*»
                                        urement rite to the neanet upstream and downjtreaiB
                                        dlsturbenoea, and divide each dlatanoe by the stack
                                        diameter  or equivalent diameter, to determine UM
                                        distance In termi of the number of duet dlamelen. Then.
                                        determine from Pleura 1-1 the minimum number ot
                                        traverse polnU that comeponda: (1)  to the number of
                                        duet  dlameten upstream; and (2) to the number ot
                                        dlameten downstream. Select  the hl(her of the  twe)
                                        mtnimnm numben of traTerae polnU, or a (reater valna>
                                        so that for circular stack? the number U a multiple of 4.
                                        and tor rectanfolaf itaelo, the number U one M thoe«
                                        shown In Table 1-L
                                        Tiai» l-l.
                                                                 rtttt»fwltr Mete
                                                 umejr of rrtxrw peMtr
                                           11..
                                           U...
                                           ax.
                                           2*..
                                           3D..
                                           St..
                                                                           (Ha
                                                          ut
                                                          S<4
                                                          5t
                                                                           ta
                                     JIWtStH. V9I. 41, NO. 14f—THUKSOAT,  AU4UST \»,
                                                          D-10

-------
      0.5
                                        AND  IIOUUTKmS


DUCTO4AMETERS UPSTREAM FROM FLOW DISTURBANCE (DISTANCE A)

                    1.0                         1.6      ,                  2.0
                                                                                                                      41757
                                                                                    25
                      1
I
                                     \
I
I
    40
fc
85.
    20
                                                                                              T
                                                                                              A
                                                                                              6

                                                                                              i
                                                            ^DISTURBANCE


                                                                MEASUREMENT
                                                            h  >-    SITE
1  10
                                                                DISTURBANCE
                                                   I
                            I
                                                                               I
        !            3            4             5             678             9            10

             1>UCT DIAMETERS DOWNSTREAM FROM FLOW DISTURBANCE (DISTANCE R)


         Figure 1-2. Minimum number of traverse points for velocity (nonparticulate) traverses.
                                           12.2  Velocity  (Non-Partteulau) Tr»T«fM.
                                          valocJty or volumetric floir rale it to be determined (bat
                                          not partlcalate matter), the aune procedure w that far
                                          ••rBcnlaw tnrcoM (Section 2.2.1) to followed,  amp*
                                          that Kurort 1-2 may be o*ed Injtead of Flfurt 1-1.
                                           M Croa»-8«cUana) L*yaol and Location ol Tnrem
                                          Point*.
                                           ZJ-1  CinakLT Bucks. lxx»t« tb« OKTITH wrtntt on
                                          tvt) p«rpendicul*r dl&met«n ftdoordiuf lo T«bl« 1-2 And
                                          4he «xamplt  tfaown ic Fl« BlbUocrapby) thai
                                          «j»<* lb< «»mr ralo«> M tboac In Table 1-2 may b» and
                                          to tteo of Table 1-1
                                          • For particulat« tTBTerve*. ooeof UHdiaroetcnmoit b«
                                          is  plant contMnlnf theimlnt upect«d oooouitnUoo
                                          UOD. »J . aher btDOi, on« diameter thalJ be in UM
                                          pi.r • nf th» bend. Thll requirraQent btoomn kali erlllaal
                                          at UK dliiaooe tmr, tbe dljturbanoe locnaae«, ibenJon,
                                         jafhfi diA-mf t«r kical k>M may o* ucad, iub)ect to approral
                                         »«f Ibc Administrator.
                                           In addiuon  for nackj buTinj  diarn«<«> (ntUr Uiaa
                                          atl ID (» In.) oo tnttne pcHnO >bal] be tocaux] within
                                          ».» «nilmet«n (1.00 In ) of the »uek milt, AIM! It* clack
                                          4iamet«n equal to or leB tbao 0.61 m (24 ID.), DO traverae
                                          pelnuihaUbetocaied within l.tcm (0.60in.) of tb«Mack
                                          walli To nucl tb«M criteria, otmrr* ttM  prooadim
                                          KlTco below.
                                           U 1.1  «cacki With DiuMtan Onatw Tbao «,«! m
                                          CM in.). When any of tbe tr»rtr»t  prtnu at loeaud in
                                          fctkm2J.1 fcBiHtbJn2Jem (1.00io.)oAT, JttftMCT M, f*T7

-------
41751
   TRAVfM
      POINT
        I
        4
        9
                  Ftgun t4L  Eiumfto ttowfng circular stack era* section dfvkted fata
                  12 tqu«8 *rw*4 with location of tnvcn* points IndlcatM^
                                                         -
                                                  the iam
                                                                                                                              In'rtr
                                                                                                              w«*«h Untf to hMhxs* nrtrUnc; la
                                                                                                            UM umtnt* or abtanc* at cyclonic Bow at •
                                                                                                            * location mo* b* detanmW. Th* Uknrfem
                                                                                                                   p....!- 1- .1.1. .... - '~"-t
. .. 1 .
•« . 0 ' J «
-r- |- -
« 0 1 0
1
1 1
? ;
1 .
_i
1
1
1 *
L
                                                   RgurtM. Example showing rctangil*
                                                  MCtkMi divided Into 12 tqu«l *r**t, with
                                                  point it centre*) of MC*) aratv
    Tabfe 1-2,  LOCATION Of TRAVERSI POINTS IN CIRCULAR STACKS

             (Pfcrcant of stack d'omettr from Inside will to travtm point)
Tr«v«rs«
point
m«b«r
on * .
(ilMttrt
I
2
a
j
8
J
8
9
10
11
' "1
13
14
IS
If
J7
18
If
2
tntar  mutt b*  eootaetod tor reeoluUoa  of r
  ».«             "
                                                   L*r«i tad M« th* nuromnNr. Comnet • ISrpt •
                                                  pttot tub* to to* mtnnin««r. Padttoa ID* TTP* • pilot
                                                  cab* u <*oh tnrtn* point. In 5ocoeMl*n, •> thit  to*
                                                  pUaM ot UM (MM openlif* of the pltot tab* tnmrandkv
                                                  ulv to UM fUok cro3»-»cUoa»l ptoat: when tn* Tn« •
                                                  pMot rab»ta in tUi partttgB, It U M "0* ntltrane*." Now
                                                                                                   tte dlffannital pragun (Ap) nodlnf tt Mob Ofnrm
                                                                                                     • -   "-     •- •    '   •• •     ••   •    •  • ^^ _. a
                                                                                                            i null (uro)  pltot reading It obtained i
                                                                                                   referenc* tt t gives) traverse point, tn aoaaptabst now
                                                                                                   condition esJatt at that point. ills* pltot reading b not
                                                                                                   s*n**ITTtprtotrabe(npto±«r< yt*7
                                                                                                   angle), until aasslnadlag Isobtalned. C artfully deltnDln*
                                                                                                   tadnmrd the value ol th* rotation aagl* (a) I* tb*
                                                                                                   nearest degree. After tn* noil technique tut been applied
                                                                                                   tt etch trtTTs* point, «»i«ni»«» th* treng* of tb* abso-
                                                                                                   lute T&hiat of a; anlgn a Tthu* of If to thoee pokttt (or
                                                                                                   which no rotation was required, tnd Inclad* these  ta tbt
                                                                                                   overall tTerage. If the aTerageValu* of a Is greaUr thai
                                                                                                   10*. the overall flow condition In the stank It limn. naOhU
                                                                                                   tnd tlternatlTe methodoloiy, subject to th* appro-rat of .
                                                                                                   tb* Administrator, moat  be used to partorm taswtt*
                                                                                                   sampl* and Teloetty trar
                                                                                                    1. Detarmlnlni Dntt ConetntrtUoa hi t Ot* ftrMB.
                                                                                                   ASMK. Ptrfarmtnet T«tt Cod* No. S7. Ntw  York.
                                                                                                   1967.
                                                                                                   •_». DoTorMn.  Howtrd, »< , ti. Ate PtOtUloti Boon*
                                                                                                   THlU*J ***"M^ ASf PuttUltOB CVDttVl  DittflOt. Lot.
                                                                                                   Angela, CA. Noremb«r IMi
                                                                                                    3. Methods tor D*unnlntUoa ol Vgfcetty. Vohnnt,
                                                                                                   Dust tnd Mist Content of Out*. Western PnelpiUtlOB
                                                                                                   DtVUon  of JOT MtaatetalacCo. Lot Anfttat, CA.
                                                                                                   BnH«tn> WP-W. WB*X
                                                                                                    4. Standard Method tor BtmpUM Stacks tor PirUooJtU
                                                                                                   Mtttar. tn:  1971 Book of ASTM SttndtnU. Ptrt &
                                                                                                   ASTM Deelfnation D-JWS-71. Pblladelphl*, Ft. 1971.
                                                                                                    5. Banna. H. A..et tL PsrtlcaltU Sunpunt 8tnte(l*>
                                                                                                   tor Larn Pow*r Plant* lortncMnf Nononlrann  Flow.
                                                                                                   D3EPA. ORD, ESRL, Research Trltnfl* Park, NX!.
                                                                                                   EPA-fl«y2-7»-170. June 197«.
                                                                                                    «. Entropr EnrtroamentaUiti. Ino. Detarmlnttkm ol
                                                                                                   the Optimum Number of Sampling Point*: An Analyst
                                                                                                   of Method 1 Criteria. Environmental Protection Anna*.
                                                                                                   Research Trlanfte Park. N.C. BPA Contnet No. e*-0t-
                                                                                                   3173, Ttak 7.

                                                                                                   MlTBOD  J— DmUONiTIOK OF STACK Oil VU.OOTT '
                                                                                                    AMD VOLDMtTUC FLOW BAT! (TTTI S PJTOT TDBt)

                                                                                                   L Prindfli tmi AppOcuMHt

                                                                                                    1.1  Principle. The treraf* (M Telocity la t stack to
determined tram the gas density and from m<	
of the average Telocity head with a Typ* 3 (Stanstehelb*
or reverse type) pltot tub*.
  1.3  Applicability.  This method  la  eppllcabl*  tor
measurement of the tTeragt Telocity of t gta stream tod
(or quantifying gas now.
  This procedure Is not applicable at measurement sltat
which nvll  to meet the criteria of Method I. Section 1L
Also, the method cannot be used (or direct measurement
tn cyclonic or swirling (as streams; Section 1.4 of Method
1 shows how  to determine cyclonic or swirling flow cot>
dltlons. When unacceptable conditions eilst, altarnatl<»
proeedurea, subject to the approral of the Administrator,,
U.S. Environmental  Protection  Agency, mutt b* ena>
ployed to make accurate flow rate  determlnauontL
examples of snob  alternatlTe procedures an: (1) to Instil
straightening Tanas; (3) to calculate tha total votametrs*
flow rat* itolchlometncally, or (t) to move to anothlf
measartmant alt* at which th* flow ls tootptabkv
      	 .  ._         .	thegrtdoon-
     loa.  DlTld* ta* fttck era*t-**ctiam lot* a* many  
-------
                                         jtUUES. AND
                                                                    41759
].iO-2.Mcm«
{I 75 • 1.C in.)
              rVvfllB^X^ZIsSI^M^^^^

               i  7.62 cm (3 in.)*
                                 -|    TEMPERATURE SENSOR
                                                                                  LEAK-FREE
                                                                               'tONNECTIONS
                •SUGGESTED (INTERFERENCE FREE)
                 fITOT TUBE • THERMOCOUPLE SPACING
                               Figure 2-1.  Type S pitot tube manometer assembly.
                                       1.1
 _                  .         I atu* tab*
(ftgan 4-1) ihall b* made o( m«ul tQbtnf (iu., lUlri-
(•» n«el). It to noonuBiDdx) tint UM vurnd
                                          Trp* i Hurt Tob«. Tb« Trp*
                                            4-1) ihall b* made o( m«ul tQbtnf
   0.«6
                             PA uxl
                                 U b»
                                 ptun
                                             (dtmrailoD D,, flfan }-2b) b*
                                                 tan (Vi. w>d H loot).
                                                 « (ram ttx b«M of «*ot k
                                      tebe to lu ko*-«p«nlQf piu» -3b); it U raoonim«r>ded tbtt t
                                     - .>«i»iii-m 1U> uid 1JC OJD« tbe CTHTD»J table* Ml
                                      TtM tec* op*alQft of lb> pttot tcW tb^D, piwnb); to*
                                     ;BUCT>«J H tborn In rtftm 3-1, bcnr»T«» , tOibt ml^iro-
                                      ••QU of tb« ofwolDfi v« pcrmlMJ b)« CM* Ti^m >-fl) .
                                       ft* Trp* 8 pilot utw cx»U kin t knm «n«ffltii«m,
                                      4n«inlii«d w ooUirxri In ••ettoo t Ac M«ctlAa»Uoii
                                         b«» ab*ll b* iiatnnil U UM pttat ttrtw
                                          b*
                                                     murtw) «r
                                                                  «e UM feody
                                                                 »AY, «O«*VtT M,
                                                D-]

-------
                               iUllf ANfc
                  TRANSVERSE
                   TUBE AXIS.
                                       FACE
                                   p*- OPENING'
                                      PLANES
                                       A SIDE PLANE
IQTCITUDINAi
  T&Sf AXIS-
NOTE:

1.05Dt
-------
AND REGULATIONS
                                                                                        «761
        TRAKSVERSE
         TUBE AXIS  "
10NGITUDINAL
  TUBE AXIS—
            Figure 2-3.  Types of face-opening misalignment that c«n rwult from field UM or Im-
            proper construction of Type S pltot tubes. These wiU net affect the baseline value
            of Cp(s) «o  long as 01 and a2 < 10°, Ui and 02 < 5°. z < 0.32 cm 11/8 In.) and w <
            CX08 cm (1/32 In.) (citation 11 In Section 6).
                                 VOL M», MO. l«l—fMU*S»AY,

                                     D-15

-------
&tttt^&ESSSS$ °££Z2
and 4.2;  nofa, how*«ff, thai to» statta and Impart
prestof* tolas ol standard pltot tabes an nasarptlbls fe
plootaf  IB  partlculete-ladsn  fat  itr
                                                           RUUf  AN0
                                                   canton fton and net b* attached t* tt* pttot tubs*
                                                   it* alterna^T*-!* rantat*  »  UM appall tt  tha
                                                                                                       MarrlagaX
                                                                                                       pltot tab*
                                                                                                                 or O) by cattbradoo
rwtlcal maammtar, bartsaj Mi-la. UjU oinnons on to*
0- ta 14n. InaUnod seal*, and awo, HiO dlTiiloot on Uw
1- to 104n. wdcal wal»,  Tht* trpe ol mcnometw (or
otber gaufa of cqnlnOant  woaltlTtty) b satlilactory ft*
tha maaionmeat «< Ac nluea at tnr ss 1.3 mm (0.06 In.)
HiO. How*7«r, a  dtffiarenttal preesor* sang* ol greater
amUtlTUy ateli t» etad (»abj«t I* tka a«4>ro*al oi U»
Admlnfcittator), U an* *j  aeteBowtef S fcnad k> b*
                                         M  t t
                                                     1*  Pressure Pro be and O»ug». A p
                                                   within 3J mm Hg (0.1 In. Hg) may be oasd.  In many
                                                        , the barometric reading may D* obtained from •
                                                            	i station,  In  wWon  —-
                                                                                       it*  baronu
                                                   pressure) shall  b* requested and an adjustment tor
                                                   eleTaUoo differences between th* weather, station and
                                                   the sampling point shall be applied at a rate  ol mlnu*
                                                   3.3 mm (0.1 In.) Hg per 30-meter (100 loot)  elevation
                                                   Increase, or rice-Tana for eleTation decrease.
                                                     2.6  Oat Density Determination Equipment. Method
                                                   3 equipment, U needed (see Section 3.6), to determine
                                                   th* stack gat dry motanatar weatka, aad Reference
                                                   u..h~< i or Method 9 equipment lor moisture content
                                                   determination; other  method* may ba uaad tobjaot t*
                                                   approval ol tbe Administrator.
                                                     2.7  Calibration  Pltot Tuba. Wben caUanUaB of r -
                                           tandeftfi
      !uli~wfa~M~!O; (2) for torena «* Uof more point*, more than IS
psnwol  ol tn* IndlTldnal A« nadiogs an baloB U am
(O.S5 In.) HjO; (V far Ust<«M ol fewar than 11 potata,
more than OWB 4preading te M0wl.tnnM.oein.) HiO.
ClteOm !3 In Section tTdetofte* onmmenlallr anilabl*
Instrameatatiaa kc ib* maamramaat oltatr-nng* g*a
TWAMUUSW,
 •A£ aa altematlT* ta crltjrte (1) tnroaga (») abor*, tba
K4levtng calnnlatlmi may b* performed ta determiiie taa
neaesliy ol natat] a more mn&ttTa diflercnUal pnaaor*
  &iti— Individual
                                    i at a I
        'otal nomba? ol DBTI
        19 mm HuO wben mei
       0.003 la H*O wkaa XngUfb onltt an

D T to greata? ttea  1.0*. tbe velocity bead data an
nnaceeptabl* and a men saoatU** dlflerantial vtmfM*
gauge mutt be Mad,
  NOTS.-U dlSereotial prtawra gaaga otnar  thas
IncUoed manonwters are used (e.g,, magnebelic satvaft).
their calibration moat  be checked after eaoh test"ted**,
To chock the calibration ol a dUhrentlal pcaaaare gsaga.
eompsn Ap nadiagi ol tbe fauge with tbote olagmgs-
oll manometor at a minimum tf three points, apfsnst-
mataly reprasentmg the range ol Ap Talues In the stack.
I/, ft£ eacb point, the values ol Ap sa read by the diflentft.
tial  presfon gang* and gauge-oil manometer urat a*
within i percent, tbe diflerentlal preason gauge abaat be
considered  to be In  proper calibration. OttMrwta*. dw
teat series shall oltbar be voided, or procedures la e4M
the measnrftd Ap values and anal resulu sbafl be us*a>
sobject to the approval ol th* Administrate.
  2J Temperaton  Oangs.  A  thermoconpla, l!qold-
fillad bolb  thermometer, blmetalll« tharmomeUr. mar-
cury-in-glefii thermometsr, or other  faoge  capable of
ateaeorlng temperaton to within 1.3 percent ol tbe mini*
mum abeolut* stack temperature shall  be  osed. Th*
temperature K»og« shall be attached  to the pltot mb*
sues that the sensor Up does not touch any metal; tot>
gauge shall b* In an Interference-free ei i ai SIIIM nirt  wtt
respeet  to the  pltot  tube (ace opvrtass (sm  FlgQn M.
and alt* Fl«Tin2-71n 3ecUoa4). AltamatepceiUonsaBaii
be uasd U tbe pttoe tutw-tsmtMs^B* iimijt svataa ti
calibrated according to th* procedur* ol Section 4. Pm-
vlded that a dlAereces ol not more than 1 percent In tha
        velocity Eneecs&«me9S U) Introduced, tb* '•"
                                                   f*g*
                                                   tub»
                                                   VUUM»U, prelerably, hav*a &uu «»»«««»»., vu»»^_
                                                   either (1) directly from the National Bureau ol Stand-
                                                   arda, Boot* 270, Qolnm Orahard Road,    •-   •	
 tbe external tube, following the 90 degree bend.
  2.7.4  Static preamre hole* ol equal alia (epproitmalej*
 0.1 D). equally spaced In • ptesometar ring conAgaraUosl
  3.7.*  Ninety dcgn* bead, wltb curved or altar*!
 Junction.
  2.6  Differential Pretenn Gang* tor Typ* • Ptto*
 Tab* Calibration. An Inrllnad manometer or eqalvaUot
 to used. II the  single-velocity calibration technique to
 employed (see Section 4.1.2J), the calibration differen-
 tial pressure gaog* shall b* readable to the nearest 0.11
 mm HtO (0.009 In. HrO). For moltiveloclty calibration*.
 tbe rauge shall ba readable to the nearest O.u mm HiO
 (0.006 In HjO) lor Ap value* betweea 1.3 and 25 mm HjO
 (0.06 and 1.0 In. BK». aad t* th* assnat IJ mm Hi"
     lav HsO) lay A> valoet abwr* 25 mm HrO 0.01
 	;. A rpedal, man seastttv* faaaa wtU be r*qi
to read  Ap vane* below  L» mm HsO [OM La.
 (*** Cltatia* U aa Section  t).
                                                                                           f
                                                                                                            CURVED Off
                                                                                                        MITEREO JUMCT101
                                                                                                                         STATIC
                                                                                                                          HOLES

                                                                                                                         (-0.101
                                                                                                             HEMISWIERICAL
                                                                                                                    TIP
                                                               Figure 2-4.  Standard pitot tube design specifications.
                                                     8.1  Set np th* appantot at shown In Flgua* 3-1.
                                                   Capillary tubing or surg* tanks Installed between to*
                                                   manometer and pltot tube may be used to dampen AB '
                                                   fluctuation*.  It U recommended, but not required, that
                                                   a pretest leak-check be conducted, at lollowt: (1) blow
                                                   through the pltot Impact opening until at least 7.6 am
                                                   (3 in.) H
-------
                         
-------
4178*


 34  DvtarmtaM tit* stock (** dry motonifM
For oombmttoB proaaaM or promo* the* emit
Ually COi, On CO, andiNi, a» Method 3. For [UTii.iimejl
emitting nj*anHiilly air, an analytli and not b* «e>
ducted; a» a dry  molerolM weljbt a! 29.0, Far otto
pf ni MM*, other method*, jubjert to UM approval al tba
AdmlnlJtrator, moat b* awl.
 3.7  Obtala UM  molftun eontan* am  ReJarem
Method 4 (or aqalnlmt) or bam Method it
 34  Determine UM eroaMcUonal an* of UM «task
or  dart  U tb* aunptlne; location.  Wb*o«»» ponibaa,
pbrrtcaUy m*aann UM rtaek ftlnMmitoin rather USA
uttnf blu*pcliitB>

«. CWeratie*              '              r

 4.1  TTP» 8 Ptfart Tuba. B«faf» Ni InltWust,
fully txudno UM Type 8 pilot tub* In top, aid*.
«nd Ttovt t* nrtty that tb* (M* op«nln(i o( tb* tub*
•ntllnMd within UurndflcattontUluitnttd IB Finn
M or"5-». Tb* plUH bib* ttuJl not b* OM! U It MM t»
m**t UMM sU&nu&t im
                         •UUf  AIM-REOUlATIONft
                                                   ,  dlftADCW
  Aft* TtrUjrlat UM ku» optoloc kllfnnMnt. m**jon
•sit mart UMloDMwtDB •f-~-"'J*-T «« UM pita) tnb«
(») UM at«n«l tabtn* dtamftw (<
i-lb); u4  (b) tlMbM*-«o-op«nini ,	
(dJnundoai Pi and Pi. Flmr* i-Jb). & fl, U b*tw««
0.48 and 0.96 em W, wd H In.) «nd U ^ »nd P. M»
*qtml and b*tw«« 1.06 and 1 SO R,, then an two pcodbl*
options: (1) UM pltot tub* may b* cullbnUd aooordlna
to UM procwdun outllnad In  BvMoot 4.1.J throu«§
4.1J bdow.  or (2) a bawlln* (l»olat*d tub*) co«fflcl*nt
valoa of O.M may b* lajlfnod to UM pltot tab*. Not*,
how»r*r, that If th* pltot tub* It part of an unmbly,
callbratlaD may fUM b*  rtqolnd, doplta knowl«d«*
of UM turtllnt eo*fflcl«ni r»lu* CM* Scctloo  4.1.1V
  If Dt, PA,  and Pi an outdd* th« ip*cifl«d limit*, UM
pltot tub* must b* calibrated a* outlined In 4.1.J throtufc.
11.5 baloir.
  4.1.1 Typ* 8 Pttot Tab* Aaanbllal. Darin* aampk
and nlodty trartraM, tb* Isolated Typ* 8 pitol tab* to
not alwayi mod: In many Uutano**, tb*  pltot tab* I*
and In combination wltb other source aampllng oompoa-
•nt* (thennoeoapu,  sampUnf prob*, ooul*) M part at
an "aawmbly." Th* presence of other aamplloc oompa*
nentt can aom«tlme* afleot the baaelln* value ol the TyjM
8 pltot tab* ooefflotent (Citation tin Section 6); tbenbr*
an aialfn*4  (or otherwl** known) hamlln* coemeUn*
feaaelln* and aawmbly ooefflclent rafaei will b* !•	._
only when tb* reiatiT* placement of tb* component* ji
the uaembly la  «aen_that aerodrnamlc  Inlerfeteaot
                                                             effe«u an eliminated. Plfnna 2-6 throat b 2-« Uhutrala
                                                             Interfennee-In* oomponent arranajemanti lor Typ* f
                                                             pilot tabea barlni eiternal tablnc dlameten betwtai
                                                             0.41 aod O.M cm (H. and H In.). Typ* 8 pltot tDbeaaHBk
                                                             bile* that 1*0 to meet any or all of th* ipeelflcatloai <3
                                                             Flcnre* 1-6 throacb t-t shall b* c^bnteTaeoocdlnii Z
                                                             lh* prooedon oatUned  la Section) 4.1.1 throath 111
                                                             below, and prior to calibration, tb* Tahua of tb* lni*>
                                                             component ipaclnn  (pltoUooul*, pltot-t
                                                             pttotprob. ab«UbTaaaa b* mea^and a
                                                               Nora.—Do not o*a any Typ* 8 pilot tab* l
                                                             which li coutractod inch that UM Impaot praoon O.
                                                             In* plan* of th* pltot tab* li bale* UM anln pteeaaftb*
                                                             notal* (ae* Finn J-6b).
                                                               4.1.2 Calibration Setop. If UMTTpaBnltoltabibfj
                                                             b* callbnted, one let of tb* tab* ihaU b* parmaomU*
                                                             marked A, and th* other, J. Calibration ihaUb* done hi
                                                               flow ryitaM bawtaf  UM  loOowtnf awaUil ««*]•
                                  IfL
                         TYff SmOTTUli
                                                 £ 14ft en (3/4 it) FOR 0N • U tm (1/2 tal
                        A.  iOTTGM VIEW SNOWIM6 MINNNUM rITOT-NOZZlE SEPARATION;
              SAMHIN0
               PROM
                     11
v
                           SAMPIIN8
                            NOZZLf
                                                      STATIC rHESSVIH»
                                                       OPENIN6 PLAMt
                                                                                                   IMPACT PRESSUMI
                                                                                                    OPENING PLANt
                                  TYPit
                                mOTTUBI
                                                      NOZZLE ENTRY
                                                           PLANI



                               SIOE VIEW: TO PREVENT PITOT TUII
                               FROM INTERFERING WITH GAS FLOW
                               STREAMLINES APPROACHING THI
                               MOZILE. THE IMPACT PRESSURI
                               OP£E9tNG PLANE OF THE PITOT TUII
                               SHALL 8£ EVEN WITH OR A10VI THI
                               NOZZLE ENTRY PLANE.
                      F!gurt 2-0. Proper pitof tut* • sampling nozzla configuration to preV«ht
                      atrodynamte Interference; buttonhook • type nozzle; centers of nozzi*
                      and pi tot opening aligned; Dj between 0.48 and 0.95 cm (3/16 and

                      3/8 in.).
                                FCOKM IMtlTn, VOL 41, NO, IwQ—TMUISOAXr AUOUSf !•» \977
                                                  -  • '       •»       .                •  - , -  ^ • I
                                                           D-18""

-------
                                                                     •EGULATONS
                                                                                                              4J-
                                                                                                  TmtmtTTaW
                                 figure 2-7.  Proper thermocouple placement to prevent Interference;
                                 Dt between 0.48 and 0.95 cm (3/16 and 3/8 in.).
                                                                         TYPE SPITOT TUBE
  figure  2-8.   Minimum phot-sample probe separation needed  to prevent  interference;
  Ot  between XJ.48 and 0.95  cm  (3/16  and 3/8 in.}.
  4JAI  n» flowing (M ftraam tms* b* confined to a
 Aid *f daOnlle eran-aactional ana, cither etrcnlar or
 ncUoiulv.  For dreulv uumtKUaat, Urn
 eta <£am*t« *halj be WJ omXli In. )-.-fcr
 «n»i sections, U> width tvborter tide) stall b* at
 11.4 cm (lOln.X
  «.1A»  Th» !•>«• s».*Luml arm a* tb« oahbraUm 4wi
 •at b* mrutam rr«r » (tourer ol 10 «r man tort
 ttameUrt. For a recUmular anm mctton, oat i
 tan diameter imloal*t«d (ram UM tallowing
 te4i»eml»« tke nnmb«r«< doe* dtemeim:
•tarn
                              £qu»Uan2-l   -JX^Jd^
  V-WidUi

  T» «raoj» UM prmnoe of iUbit, tuUj d«T«lop*d flow
•ptlUnu »>  tb« o»llt>rrUoD ij{«, or "Met MCUOD." th«
«U mnji b* tooted »t U»sl ««hi diuoeUn downstream
    rvo diftm«t4n opvtraam from UM iMarwt
  Ncrt.—Tbe aifbt- aod two-diameter criteria ar* not
abeotat*; other test section locaUocu may be oasd (sob-
Ject to spproTsJ ad tbe Adjnlninrwtor), proTlded that tbe
low at the u«t slu to (table and damoomablr paralkJ
*> Ih* duct ails.
  4.1JJ Tb* flow syvtam ahaD have UM eapaeltr to
      > a laa) ssrhnti raioolty aroond tit so/min 9JOOO
        Thl> »
•actioriaJ plane durlaf calibration. To fecUjtau allxn-
nent of the pltot tubes diiriuc oaUbrauon, It U advisable
that tbe ust MCUOD be oooom«
other transparent material.
  4.1J  Call braUon Prooedora. NoU that thlj prooednjt
to a  feoeral ooe and nui5t Dot b« ojed without flnt
raterrlnf U) tbe ipcclal ooaslderaUonj praanled Lc Bee-
COD 4.1-5. Nou also that thii  procedure  applies onJf to
•tnfle-Tsloclit oaLbratloa. To obtain oallbraUoD  data
tor tbe A Rod B tide* o( UM Type B pltot tab*, prooted
as loUowi:
  4.1J 1  44ti« »3J» that  UM macomeUr  It proptrtj
fllied and Uiat the oU If CTM from contamination and U of
the proper denjdir. Inipect and taak-ch«ct all pltot HUM;
npalr «r raplaoe U pini«ir).
   -     Lml and avo th* maDometer Turn on tha
kn and allow UM flow to Kihllli* Saal UM Tjpe B antry
  4.1 JJ Xnmnthattb«iMDonwtarbtrralandMroed.
FodUoo tbe (tacdard pilot tuhe at UM oaUbraUon point
(determined as outlined in  fiction 4.U.1), and allfn the
tube Mtbat in Up to poumd directly Into the flow. Par
ticalar oan airaura be taken In allfninc the to be to aroid
raw and pitch  aniles. Make «irt that  UM entry port
•irroundint UM tqbe li propwly nal«d.
  4.1J4 ttead AIWW and record IU Talu* In a data table
elmllar to th* oo* «bown  In Hfnr» a-g Ramove tb*
•tandard pltot tDB« trom the duct and disconnect U trom
tb* manometer. Seal UM itandard entry  port
  4.1-US Ooonert the Type 6 pilot tub* to the manom-
eter. Open UM TTTX B entry port. Cheok the »«~-n.
•Ur lereJ and aero, inswl and alien tb* Type B prftot tube
•D Uiit IU A Bde Impart opdlnj to at tb* aame petal u
VM UM ataadvd ptutt tob* and ts pctaUd dirsnUy into
m* Uvw. Make aon that O» amtry pert mamuidiot the
tube ii properly sealed.
  4J J « £ead 4p, and enter IU rain* in UM data UbU.
Bamon thi Type B prtot  tub* (ram UM daot and dii-
•ounecl It from UM manom«ter.
  4.1.17 Repeatnene4.1XtUm)a(h4.14.«abov*imtU
thr*» pain of Ap raadiufi hare been obtained.
  4.1 J.I Eepeat supe 4.1.LI throo(h 4.1O.7 abe-*« br
tb* B Ude of the Type 8 pltot tube.
  4-1J » Perlorm oalculaUooi, at ilaauinoj IB &KUOD
*.!.« baiow.
  a.1.4  OakossOoos.
  4.1.4.1 for each at tb* ill pain of a* nolioci 0^.
thne £rotn *ld«  A and  thra* trom dd* B) abtaLwd  In
••eUoo 4.1J abort, aajcolate th* ralo*  of tb* Type •
pltot tub* unaffrlam at toUowi.

-------
4179*
                                                      RUUS  ANO
 PITOTTUBI IDENTIFICATION NUMBER*

 CALIBRATED lYf _ ___ _
                                                                  . OATff.

RUNN&
1
2
3
"A" SIDE CALIBRATION
'AM •
e»H20
OcHjO)




AKi)
««HjO
(ln.H20>



Op (SIDE A)
CpM




g
DEVIATION-
Cp(») • CpUf-





RUUO*.
1
I
3
"B" SIDE CALIBRATION
Afttf
ernHjO
(!•. H20)




Ap;j
cnHzO
(ta.H20>



Cp (SIDE B)
c>w





•
' DEVIATION
Crfd-VW
•

.••-

      AVERAGE DEVIATION •  0 (A OR B)
                                               £JC,(t)-?,(AORB)}
                                                                          •MU3TBCO.B1
      j (^ (SIDE A)-if, (SIDE B)]


                        Figure 2-9.  Pitot tube calibration data.
                                Equttioa 3-2
   J-TTP* 8 ptto* tab* otaOetal
.(•a -Standard pttot tub* m»ffl,-Velocity head mea*m«i by tk* Typ* B pttat
         tuba, em HiO (to. HjO)
  4.1.4J  Calcalato C, (eld* AX the •>•*• A-*U* ee*V
Bclvt, and ?, (aid* 3\  to*
eakoaH*  th* dlffcrane*  b*ti
          •( C,(.) from ?, (rid* A X "id th*d*rl*ttatf
•Mb B-dd* nb» o< C,(.) from C, feldt B). U» UM W.
                                                                                                                                      or B)

                                                                                                                                    Equation 2-3
                                                                                                     4.1.4.4  Cileukto ». th*
                                                                                                     • (side A of B)-
                                 Equation 2-4

  4.1.4.4  Uw U>* TTP* B pilot Wbt only Utb*nlDw<<
* did* A) ud r did* B) m km Una oc tqaal to 0.01
•nd If Uu *b«tDt« Trnln* of th* dUTtnnM bihim ?,
(A) «nd Z1, (B) U 0.01 or IML
  4.1.1  Specif ootaldwmaon*.
  4.1 J.1  8«l«ettOD of caUbntion point.
  4.1 J.I.I  When in  Intatod Trp* 8 pilot tub* li etB*
bnod, «ol«ct t otUbrmtton point *t or new the center ot
UM duot, tod follow the procedorw oatllned In SeeUon
4.1.3 4nd 4.1.4 tbOT*. The Type S pilot mfflctenti •
obuined, L*.,?, (aid* A) *nd ?, (ride B), will b* Tilli
» lone u either: (i) UM lioUt«d pilot tab* I* nod; at
(2) the pilot tab* ta used with other component) (notilt,
thernuwoaple, Mm pie probe) In «a urmnfenunt that to
Ire* from Mrodynimw Intcrfmng* eActi (M* Flnni
3-6 through M).
  4.1J.O  For Typ* 8  pltot  tabe-Uxrmoooople oov>
binttfon* (without tampl* probe). Mlect * eutbntloi
point M or near th* center of th* duet, and follow th*
procedure* outlined In  Section* 4.1 J and 4.1.4 •boru
The coefficient* to obtained will b* TaUd w leaf u the
pltot tube-tnermooottpl* combination  la osed bj ItMH
or with other component! In an Interfereoec-fre* imo(*>
ment (n«nn* 3-
-------
                                                                 AMD tfOULATrONS
                                                                                          «T767
                                     w
                                                      ESTIMATED
                                                      SHEATH
                                                     '•LOCKAGE
                           OUCTAREA
                                                tflfl
                          Figure 2-10.   Projected area models fpr  typical pi tot tube assemblies.
   4-U PWd Use knd E«MJIbf»tkm.
   4J.H.1 Meld Use.
   4.1.8.1.1  Worn » Typ* S pilot tab* (tooiktad tube or
 •Kmbly) ui naed In the n*ld, tat ipproprteu oaefficknit
 Vklut (wbetber udcned or obtained by calibration ) thill
 M used to  perform T«lodtr calculation!  For csJibrkted
 Trpe B pilot tub«. tbe A tide coefficient tbAll be u*»d
 When the A sidcoftbe tubefkcm tbe Bow, knd the B side
 coefficient shsll be used when the B  title luxe tbe  Bow;
 •HemstlTeJy. the arithmetic kTerkf t  of tbe A knd B ride
 weffldenl Ttltnt m»j be need, IrrespectlTe of which dde
 hon the Bow.
  4.1.U.2   When  t probe tssembly li used to simple •
 •mil dart  (12 to M In. In dl»metwX tbe probe kbektb
 smneUmee  blocb k stfnlnasnt put of tbe duct craft-
 action, ovuinj a reduction  In tb* kdectlre  Tklue ot
 T.I.I  Consult Citation 8 In Section « lor details  Coo-
 TtnUonal _plUH-*kmpltnj  probe  knembUes  are  not
 Mcommended lor use in  duett hkTirjf Inside diameters
 smaller than 13 Inches (Oltttton 16 to Section 6).
  4.1.6.2 EKkllbretlon.
  lie.I.l   I«ol*t«dPluitTa>>« AA«r neb field use, tfae
 Jltot tube tb*U be omfullyraaiKmlned In top. tide, «Dd
 mi Tlewi  II Ibe pilot (»» openlnfs are »U11 ilined
 within tbe tpectnatlont Uluitnted to Flfure 2-2 or 2-*,
 • OKI be unimed th»t tbe Dwell ne omffldmt ot tbe pltot
 Bbe DM not cbknied 11, bowev«r,  tbe tube bu been
 4tmi|M) u> tbe extent th»t It no lonfer meeta tbe tpeclfi-
 •tlonj of Plfure 1-2 or J-s. the d*m*«e «t*lJ either b*
 ni^lnd to revtore proper frUrnment of tb« SAO* ocwnlcn
 • lb< tube inal] be ditorded
 4.U^J  PltM Tub* AvembllM. AfKr web field DM.
 •«* lh« h« opexdrn »llj[imeDt of tbe pilot tob«,  w
» B*ctloc 4.1.4J.1, klio. rameMurf tbe toteroomponeDt
 •pKlnfioflheuMmblT. If the totercompocent (pkclrin
 HTI not cbknfed kod tbe btoe  openinf  illioment u
*ce»pUblt. It cm  be ummed Ibtl th« ooefflcicDt of th«
     blj bu nol cbAnjed. If the t*oe o
•Mm                 .
• no kmrw within tht fpeclflotflonj of Flfim* t-i or
M wtber nptlr tbe dAmw or replace th« pilot tob«
to»llbr»tlnt tbe new mrm'-lj , U rrnrmT)  U tbe Inter-
tomponant BD«cln{0 b»
V*cui(i or rallbrtU
 U  Standard pltet tube (U »pplio«bVe) . U«ft»nd«rt
plot toU li med fcr tb* rejoclt 7 cnrtne tb< tobe itul)
bioonitruin«(3*ooordin4 to thearturi* of Beclloo 2.7 *cd
    b« MrtxDed k b*Klln> eo«fflrient Tklue ot CL»
              « tab* H BMd M pkrt
4tw tab* *b*ll be Ic
<*Db)«ot to tb* kpprcTkl of the Ad
  4-1  TMnpmton  O.
kraU (Ukl UMrmameWn,  liqnlcMUlad  butt)
•ten, thvnvjeoople-potentlaiiMtar iy«t
  « 4  Bwmotar. O*Ubnt* tb* b*roaMt«r ia»d ^ktoct
• mercury b*roro*t*r.
  Omrrr out CklcolktloTts. rttklnJac kt tast OEM oxtn
declmkl 6fun beyond tbkt of tb* koqulnd tetk Bound
off fifun* kfxef ft"*i okloiilkUon.
  $.\
     -Wkl«r T»por In the cat stnkm droci Matbod 6 or
       Bcforenw Method  «),  proportion by
    ,»Ptto< tube ao*ffld*ot, din
    ,-Pius tube OODSUCI,
     -. 0_    ^
           »ec
                   (•K)(mmH,0)

fcr tb» «a*tric sr*Um kod
                                                                      ^         - n*.  dry buls  (M
                                                        •Motion a.t) tft-cnok Ob/lb-mole).
                                                      Jt-Moleculai wvicbt of stack gaa, vvt bMk,  t/i-
                                                    Pw«,-B»rometrtc prwwn kt »>*««rim«iil Mu, jam
                                                        Hi (In. BLi)
                                                      P,-Bl*c» »utjc pr»mmr», mm Bf On_ Hj)
                                                      /•.— Abkoluu suok (w pncsnn, mm H« (In. HI).
       m.
                                                                  kbcnmte piitjun, Mo mm Bf (3B.H

                                                              romnMCrto sUok CM flow rkte eornoUd to
                                                        *undkrd eondltloni, djcmAir (d*ct/iu).
                                                       (,— Buck temperature, *C rF).
                                                      r.-Absoluu iUak umnmtan, *X (•£).
                                                                                  t.ao'K rsir iu
                                                              —^  	v—	>, m/nc (ft^ec).
                                                     Ap- Vktocity n«*d of stack n*, mm HiO (In- BiO).
                                                    •XtOO^OonTvtlon factor, avc/nr.
                                                     U.O-Molecular v«lfbt of mar,  sjr--
                                                        sool*).
                                                   U  Arsnt* Mask pi **loelty.

                                 Equation 2-0

                 L («s dry Tohuaatrte Bow tkta^


 «--8,600(l-B..)f.X (^^) (^)


                               EouAtJon 8-10
   CT^ H • • i i
   JHNBIf IBJMf
  1. Mark. L S. M*nhairlea.l Knrlnwn' Handbook. Ntw
Tort  McOrkw-HJU Book Co  In* 1W1
  t:P1JT7, > B  Chmmloal  KncUMn- Handnoot. K.w
Tcrt  taoOnw-Hlll Book CoTTlao. IMa
                                                                 D-2J

-------
41768*
                                                   RfOUATIONfr
  S. Shlgehcn, B. T., W~. F. Todd, and W.  8. Smitfc.
Slgnificaae* of Emm In Stack Sampling Measurement*.
U.S.  Environmental Protection  Agency,  RteeeroB
     tie Park, N.C. (Presented at the Annual Meeting of
                                                                             Probe*. Prepared br the Unlvmtty of Wtadwr to th»
                                                                             MlnlstrTof the InTiiiMsiert, Toronto, Caned*. F«»>
                                                                             ruary 1874,
the Ahr Pollution Control Association, St Louis,Ho.,
June 14-19, 1979.)
  4. Standard Method to Sampling Stacks for Paniculate
Matter. In: 1*71 Book of ABTM Standards, Part 2S.
Philadelphia, Pa. 1971. A8TM Designation D-29»-n.
  i. Vennard, J. E.  Elementary Fluid Meobanlos. New
York. John Wiley and Sons, In*. 1947.
  «.  ThM  Meters—Their  Theory and  Application.
American Society of Mechanical Engineers^ New York,

  7. ASH BAB Handbook of Fundamentals. 1977. p. Me..
  $. Annual Book OS ASTM Standards, Part tt. 1974. p.

  ». VoUare, B. F.  Guideline* to Type 8 Pltot Tab*
r&Ubmlott. U.S. Environmental Protection Agency.
Research Tlangls Park, N.C. (Presented at 1st Annual
Meeting, Source Evaluation  Society,  Dayton, Ohio,
September U, 197t.>
  ia Vollaro.  B. F. A Type 8 Pltot Tub* Calibration
Study. U.S. Envtronmeotai Protection Agency, Eml*.
sloo MeaguremoDt  Brands, Heeenfih  Tnangi* Park.
N.C. July 1W1
  11. Vouare,  B. F. The ECfcts of Impvet  Opening
Mlnllgumeat on the Vame of the Type 8 Pltot Tube
                       Co«fflcl«at U.S.  EBTtroaznantai  ProttotlOB A|«noT.
                       EmlMioa  Mneoramart  Braaefa,  B«w*nfa  Trlenfl*
                       Pufc, N.C. October 197&
                         !1 VolUro. B. F. E«t*l>U«tun«i« a( * BuMlln* CotSA-
                       ctea*  V&h» to Proparly ConstrucWd  Type B Pltot
                       Tubt*. U.S. EnTiroamenUJ Protoctton  AiencT, EmJ»
                       9k>n Me*innmu>t Breoeli, Bn»n»r«*i  Tnaafk Puk,
                       N.C.  NoTtmbw 1»78.
                         13. Vollcre, B.  F. Affl Enhutlan of  Slngto-Vdoelty
                       C allbratloa Technique! u a MMUB a( Determining Typ»
                       S Pltot Tab« CoefflcienU. U.S. EoTlronmenUl Protee-
                       tioa Acme;, EmiMion M«*5imm«Dt Branch,  Ramnb
                       Trtu»l> Part, N.C. Auput 197S.
                         147volluo, B. F. Th« UM of Typ* 8 Pltot Tnbw to
                       the MeMaran«ntof Low VdocltlM. U.S.  Environmental
                       Protection  Agency.  Emlaion Mttuonmeat Branch,
                       R«m*reh Triangle Park, N.C. Noremoer 197*.
                         IS. Smith. Marrui L. Velocity Calibration of EPA
                       Type Soon* Sampling  Probe. United Toehnologlw
                       Corporation,  Pratt  and Whitney  Aircraft DlTtdoa,
                       Bait Barttod, Conn. Itn.
                         14. Vollaro, R. F. R«ooounended Proeednre to Sample,
                       Traverm* In Doeti Smaller than 13 Inchec In Diameter.
                       U.S.  Environmental  Protection  Aj«wy.  Frnlnriea
                       Meaetirament Branah,  Begeareb Trl«n»le Park, N.O.
                       November ItTt*
                         17. Oww, B. and B. C^PanUmnt. Th« Meeenrnoee*
                       »> Air Flow, 4tb Ed.. London, Peffamon Prwe. 19M.
                         18. Vollaro, B. F. A sorrey of Commercially Available
                       InitrameDtatfen ^ the  Meaurement  of Low-Range
                       Oee Velocities, U.S. EnvlrormienUl Proteetloa Agency,
                       Emlsdon  Mraforement  Branch,  R«merch  Tnangle
                       Park, N.C. November 1978. (Unpublished Paper)
                         19. Onyp, A.  W,. C. C. 8t Pierre, D. 8. Smith, D.
                       Motion, and J. Steiner. An Experimental Investlfaaoa
                       of the Effect at Pltot Tube-Sampling Probe Conngnre-
                       lions on the Magninde of the S Type Pltot Tube Co-
                       efficient to Commercially  Available 8o«n* Sampling
                                                                             Mmov 9— OA» AJfainel ro» CAIBO*  DIOHD*V
                                                                              Ononr, ZXCIM Am, am Day Mououva* WEBB*
                                                       1.1  Prlndpl*. A cae ample U extracUd from a ftack,
                                                     by oae of the foUowtng  methodi: (1) slngU-point, grab
                                                     sampling* (]) dngle-poliK, integrated aampUng;  or (»
                                                     muiu-polnt.  Integrated  mmpUng. The gai sample )•
                                                     analyud (or percent carbon dioxide (COi). percent OTJ-
                                                     gen (Oi), and, I/ neceoaary,  percent carboo monoildie
                                                     (CO). Ii a dry molecular weight determination U to be
                                                     mad*, either an Onst or  a Fyrlte < analyier may be naei
                                                     for the analyali; for exceei air or emiuloa rate correction
                                                     factor determination, an Oraat analyier mint be OMd.
                                                       1.3  Applicability.  Thl* method U applicable for de-
                                                     termining COi and Oi  concentration!, eicese air, and
                                                     dry molecular weight of  a sample from a gu itraam of. »
                                                     loa»ll-riiei oombtutlon procee*. The method may al*o be
                                                     applicable toother nroceaaee where It haf been determined
                                                     that compound! other than CO>, Oi, CO, and nltmgeB-
                                                     (Nt) are not  pmenf la concentnttooi «nM»i«iit |«
                                                     affect the result*.
                                                       Other methoda, ai well u modlfteatloM to the  proce-
                                                     dure deacrlbed herein, are also applicable for some or all;
                                                     of the above determination*. Eiamplei of specific  meth-
                                                     od] and modification! Include: (1) a multi-point  samp-
                                                     ling method  using an Onat anatyur to analyze lndn>
                                                     Tlcfnal grab aample* obtained at each point; (2) a method-
                                                     osing COi or Oi and stolchlometrle calculation! to  deter-
                                                     mine dry molecular weight and eicea air; (3) aadgnlng e
                                                     value of 30.0 for dry molecular weight, In lien of actual
                                                     measurement*, (or procenea burning natural gu, coal, at
                                                     o4L These method! and modincaUon! may be used, btft
                                                     are subject to the approval of the Administrator.

                                                     2. /ifiperetw

                                                       Aj an alternative to the sampling apperatni and sy»>
                                                     tenu deacrlbed herein,  other sampling system!  (e.g.,
                                                     liquid displacement) may be used provided such system*
                                                     are  capable of obtaining a representative sample and
                                                     maintaining a constant sampling rate, and an otherwise ~
                                                     capable  of yielding  acceptable  result*.  Use of  such
                                                     systems l! subject to the  approval of the Administrator.
                                                       2.1  Grab Sampling (Figure 3-1).
                                                       2.1.1  Probe. The probe should be made of stalnleat.
                                                     iteel or boroetlicote gJaei  tubing and should be equipped
                                                     with an In-etack or out-otack niter to remove pertlcwatB
                                                     matter (a plug of glass wool is satisfactory lor this pur-
                                                     pose). Any other material Inert to Ot COt, CO, and Ns
                                                     and resistant to temperature at sampling conditions maw
                                                     be used  (or the  probe; eiamples of sueh material am
                                                     aluminum, copper, quartz glass and Tenon.
                                                       2.1.2 Pump.  A  one-way squees* bnlb, or equivalent,
                                                     Is used to transport  the gas sample  to tin enelyMSV
                                                       2.2  Integrated Sampling (Figure 3-1).
                                                       2.2.1  Probe. A probe sochai that described in Seetkal
                                                     2.1.1 is sol tabte>
                                                      i Mention of trade names or specific products does net
                                                     constitute endorsement by the Environmental Protec-
                                                     tion Agency.
                                                               43,
                                                                   D-22

-------
                                    AND  REGULATIONS
            41769
                        PROBE
                                                FLEXIBLE TUBING
            \
                FILTER (GLASS WOOL)
                                    tQUEEZEBULB
TO ANALYZER
                                 Fjgure3-1. Grab sampling train.
          AIR-COOLED
          CONDENSER
PROBE
    \
       FILTER
     {GLASS WOOL)
                                      flIGID CONTAINER
                          figure 3-2. Integrated gas-umpling train.
                                                     
-------
                                                           RUUi  AMfr 81 GUUTfOMBk
  1.3,2  CondttWT. Aa alii«eoJ*d *r vatar-eooM
d«nctf,  o*  «4fe» oasdsnew that will act remove O«,
COt, CO, tad Nfc may b» OMd to ramon mtm moMo*
which  tb* opsratea of tb» pomp
and flew ia*tef.
  1.7.1  ValTO, A zK*ate wl*a la and t» adjwt samp**
go* flow rate,
  2.J.«  Poet*, A letk-fev, dtaenragin-t™ pomp. V
eqoivtknt. It awd to transport sample1 gat ta to* fleilbw
big. Install a small tors* tank between ta* pomp ant
nit*  ta*ter  to eUminat* th* polaaUae «fi«9t a( tb* dt*>
phragm munp on the rotazneur.
  1.3.6  Rate M«Ur. Th«  rotam*t*r, or equivalent raft)
met*r, mod should tw capsbl* of measuring flow rate
to within ±3 poroent  o( In* selected flow rate. A 00V
rat* rang* of tuX) to  1000 cm'/mra Is surfest»d.
  •2.2.S  Flezlbl* Ba*. Any leak-free plastic («.f.. TedTaT,
Mylar, Teflon) or plastic-coated aluminum (e.g., aluml-
nlud Mylar)  bac,  07 equivalent,  bavin*  * capacity
cunsiewat with the selected Bow ral« ana rim* length
of UM tat ma, mar b« ottd. A capacity In UM rang* ol
M to «0 liters is suggest*!
  To leak-check the oaf, connect It to a water manomet**
andprearorli* the baglo S to 10cm HtO (2 to 4 In. HiO).
Allow to stand tot 10 mlnnta*. Any displacement In th*
«n»4«r nwnomet«r Indicated a leak. An alternative leak-
cb«ek mothon! to to  preasurlM th* b«f to 4 to 10 cm HiO
<2 to 4 in. HiO) and allow to stead overnight. A deflat«d
tec Indicate a l«Jt.
  117   Preesun Gangs. A watar-ftltod TJ-tub* manom-
Mar. « «quiv»J«nt, of  about» em  (12  In.) la used te
th* flexlbb bag leak-cheek.
  3-JJ  Vacuum O*ug».  A  mercury  manom*t*f.  at
•qoinlant, of Bt least 780 mm  He (30ln. Hf)Kuw4 te
tba sampling train le*j[-checiL.
  S.J Analyst.  For Ortat and Fyrlt* anatynr maln-
tenaae* and operatkm procedures, follow tb* Instruction
recommended by ths manufacturer, anksjj  oth*rvl*»
specified hereto.
  2.3.!   Dry Motoeolfls Weight Detvmtoatioa. Aat Orat
amlyiar as Fyrtt* typ* cambatttan CM anaiyiaT may tw
•5*-  !^»w»i»"f"to»i"i**«bt*»»*at«tawdlMt»v  «.
S3T'
  2.1 J  Imlatai Bate Conrotion Tartar « EXCM Atr
DoctnalMtkx). An Orsat wiatytw most b*  and. Tor
low COt (l«a tba« 4.0 pcrcant) or hl(b O> (greetar thin
19.0 poreojrt) eoacentratloD*, tb* m«a
cJbeek la opUooftL
  3.1^  Puc* tbo prob« In the stack, with t!w Hp of tb*
probe potttloned at tba sampling point; pargt the sampi*
iof lloa. Dmv a sample Into the aoalyter and Unm*-
dlauly uialTMltforperoeat COjand peroeot  Ot Det«r-
mlM  tb« psrtenus* ol the CM that Is Ni and CO by
subtracting the sum of ths percent COt and percent Oi
(ram 100 percent. Cakulat* the dry molcealM ««Kbt «
Indicated In Section «.»,
  3.1.4  Repeat the aampllnf. analytta, end calculation
procedures, until the dry molecular v*t«hu of any thr»*
(Tab sampla*  dlflat from their mean by no man than .
8.J «A-mol» (OJ lb/lb-moi«). Arerac* tbe*» thr«
 .                        .
ular veifht%  and  report tb* noalto to tb* n*anft
*.l|/(-mol* Ob/lb-mote).                          ,
  3.3  Slngto-PoSnt, Ina«»teJ8smpHasaad Analytical
Procedure.
  3.2.1  The mrapling point In th* dnot abaJl be located
a*q*cinedln8*elton3,l.l.              ,
  3.2.2  L»kst. connect  the '>«« and make sun that an
cnnnnMlont are Ught and le«6 fre*.
  3.2.3  Sample at  a constant rat*.  Tbe sampling ran
nhoiud  ta ilmultanami* wltfi,  and  tor tb* a%m* total
Irnrtb ol time tt, the pollutant omuaioti rat* deurmlnav
n'yriw-typa combus^on |aa analyur. If an Oraat ao*j>
lyief U ua*d. It I* recommended that tb*  Orsat leek-
. heck de*crlb«d In 8«ctlo,i 9 be p«r(brm*d before thto
determin&Uoo;  bowever, UM i-hork is optional.  D«Ut>
mine Uu parcaoUg* of Uie f»e that 1< Ni and CO by tub*
        tb* turn «i  Ui* pvcaat  COj and peroavt Oi
        (XI  Bjpatt ttx analyt and eaJculattai preoriuia
      rnittl tb* IndlTidual dry molecular welgbti te any tbnt)
      nulm* diflar from tbair aimn by no  morc than OJ
      g/g-mol* (OS Ib/lb-moke). Anragt) UM*> tan* DobcolaT
      wtlgbt9,and report UM ntnlt* to to* ncanat O.I g/g mol*

        S.«  UulU-Foint, Int*«n««d SampMng and AaarrUcai
        1X1  (Jaleat  otharwlH speclded by tt* Admlnia-
      trator, a mlnlmnm of eigbt traTent point* shall b* and
      fat eijcular itackt baring diameters len tben 0.61 m
      CM In.), a minimum of nine shall b* used for rectangular
      stacks baring *q.alTalent dlameten leal thin O.il m
      (34 In.), and a minimum of twelr* traverse point* shaU
      b* and tar all other case*. The traverse polnu shall b*
      located according  to Method 1. The use of lewer point*
      U subject to approval of tb* Administrator.
        3.JJ Follow the procedam outlined  In Sections 3.2J
      through 3.2.1, eicrpt tor the (oljowlng: traverse all sam-
      pling point* and sampl* at each point for an equal length
      of Urn*. Record sampling daU at shown In Figure 3-t.
  Nora.—A ryrtt*4yp» eombmtlon rat analyiar d a*«
 aooepUbl* te 
% DEV *


i


                                                            (MUST BE < 10%)
                        Figure 3 3-   Samplirx| rate data.
        4.1.1  Plae* tbe probe In the stack, with tbe tip al tbo
      probe positioned at the sampling point; pane the mm-
      pllng Un*. Craw a sample Into tbe analyser. For emission
      rat* eomotloo  faetor determination. Immediately ana>
      ly» tbe sample, as outlined In Sections 4.1.4 and 4.1.4,
      for percent  COi or percent Oi.  If uceas ate is dostntd,
      proceed a* follows: (1) immediately analyu the sampl*,
      at In Sections 4.1.4 and 4.1.S, (or perosnt COi. OL and
      CO;  (2)  determla* tb* percentage of the «at that la Ns
      by snbtracting  the sum of th* percent CO), percent Ot,
      and percent CO  from  100  peraant; and (3) calculate
      percent excess air at outlined In Section ft.2.
        4.1.4  To ensure complete absorption of th* COi, Os,
      or If applicable, CO, mike repeated passes throngb. nacb
      ftbeorblng solution  until  two consecutive readings ar*
      the same. Several pasa«a (three or four) should b* mad*
      between reading!.  (If  constant  readings cannot  b*
      obtained alter  three consecutive reading*, replace tb*
      absorbing solution.)
        4.1.4  After the  analyst*  Is  completed,  teak-cheek
      (mandatory) the Orsat inalyter once again, as described
     Jn Section J. For the result* of th* analysis to b« valid,
      the Orut analyter mutt past this leak  test t»fon  ana
      after  the analysis.  NTorc.—Sine* this single-point, grab
      sampling and analytical procedure Is normally conducted
      In conjunction  with a single-point, grab sampling  and
      analytical procedure for a pollutant, only one analysto
      li ordinarily conducted. Thrrtfon, great can must ba
      taken to obtain a valid sample and analysis.  Although
      In moat  ca**t only COi or Oi I* required. It li rwom.
      mendad  that both COi and  Oi  b* meamnd. and ths*
      Citation 5 In tbe  Bibliography b* u**d Us valldat* Uk»
    >  analytical data.
        4.J dlnglft-Polnt, Intograted Sampling and Analytical
      Procedun.
        4.2.1  The sampling point In the duct shall be located
      as specllVil In Section 4.1.1.
        4.2.2  Lenk
tween readings. (It constant readings cannot b* obtain*!
after tbre* oonawutlv* readings, replaoa tb* abMfbtnf
solution.)                                       .
  4.2.«  Repeat tb* analyiU until UM bOowini o««l»
are met:
  4.2.4.1  For percent COt, repeat  th* analytkal pro-
cedure, until th* retulu of any thre* analyse* differ by *•
more than (a) 0.3 percent by volume when COi Is irtttit
than 4.0 percent or (b) 0.2 pemnt by votom* when COt
Is let* than or equal to 4.0 peraut. Average th* three *»
ceptabl* varnet o* pereent COi and report th* ratnltiia
th* neareMO.l peroanL
  4.2.U  For paroentOt, repeat tb* anarytwal pfo*t4at»
unUl tb* ratulti of any tbn* analyse* dUwr by a* toam
                                                            VOL  4X,  M&.  1*4—TNUMOAT,  AU«at tw,.


                                                                       D-24

-------
                                                           -JRH.ES  AND  IEGULAT1QNS
                                                                                                 41771
<|»n (a) OJ parwnt b; vorome when Oi I* la* than IS 0
Bjrmnl or (t>> 0.2 p»rc*n< bv volume, when Qi U nmler
(teo 15 0percent. Arera«e lie thrw aomxrtablt vaJae* of
prowl Oi and  raport  UM  multi  to la* Marat  0.1
    .    Foe p«rc«iit CO, nfMt  Uw aoaJvtioal  proof-
ton until the raculu at any thrw analvmi dfflw by no
     than O.t  EwroMit  Avwaft  the  thrw  aooepuble.
     of pvnot CO and report UM NBoUi to Uw
                                                                                                                      DrrwfWATion  or Wocrmi
^1 pcroaol.
  tl?  After  tb» «nalv«ls  1*  completed,  Wai-cheek
(BandiUrj) th» On*l analywrooc* Kiln, u «aund, and that Citation 5 m the Bibliography
^mHJ to validate the analytical data
  II Multi-Point, Integrate*) Sampling and AoalyUoal
PlDoadurc.
  O.1  Both the minimum numbw of aamplinf polnU
Vid the •impllng poiot  location ioall  b* u ip«cln«d ID
lection S.3.1 of thl£ melbod. Tbe u*e of fewer points ID»D
MdJtod y *ob)«ct to tb* ipprortJ of the AdjaloLrtrmUir
  4JJ  follow the proc«durw outliDeO In Sections C2 J
throuxh  4.2.7, except lor the  loUoving  Tr»TerB* til
MrBpuni polot« KDO Mjnplf ml  kftch point for ftn equ&l
|u(tb oTtime. Baoord «un[xUas d*U u Jho» n ID Figure
»-J.
I. I«i-Ct Pro<»^*rf /or Or Ml Amtiitm

  UoTlnf ao Orwt HQAlyler fr«qD«ntJy o&uses It to ta&k.
Therelore, in Or»»t »n»lyi«r tbould be thoroughly le&k-
tttacked on cite b«lbr« the Bue (is t&mple u  Intxoduoed
totolt. The procedure for ta*k-ob«ckjni ao Orwt aamlyx«7

  A.I.I  Brine the Uqald level In eftcb  plp^tt« ap to the
rtlereooe mjk on tbe oapiuary tubing and then dose the
plpett* itopoork
  1.1.2  lUm tbe terellnf balb •nfficlenlly to brint the
eonnolnf liqujd meaiicus onto the  (rrmduftted porUou of
the burette and then close the manifold uopcock.
  ft. 1.8  Record tbe meniscus poslUon.
  6.1.4  Observe tbe meniscus  In Uie btirette and the
liquid level ID tbe pipette (or movement over tbe nert 4
minutes.
  6.1. J  For tbe Ormt analyw to p*« UK tak-ebeck,
tvo oondltloDj must b« met.
  6.1.1.1  Tbe liquid level In each  pipetU mnrt not fall
below the  bottom of tbe capillary tubinf  durini tbi<
4-mlnn te I n terval .
  1.1.&.2 Tbe menlnni In the btmtu most  not ohamje
by more than 0.2 ml during tbis 4- minute Interval.
  t.l.t  U tbe analyur falu the leak -check procedure, an
robber oonneotioa* and itopoccks iboula  b< checked
nntll the cause ol the leak l» Identified. Leakini nopoocki
mu»t be dlmasembled, cleaned, and nfreased. Leaklnf
robber oonnectionfl moft be replaced. Alter tbe analyi«r
fa naasembled,  tbe  leak-cbeck  procedure  mull be
repeated.
  Cl  NomeixJatnre
     J*/-Dry molecular »«l»bt.i/t-Baok (Ib,1b-moU).
 . %EA»P«rtnn( excen air.
  %OOi-P«ro»ni COiby volume (drr b*rii).
     Oi«»P»roent Oi bv volume (drf baalsK
     ^O«Peroerit CO by voltune (ory basis).
      s't-Paroent Ni by volume (dry t	
      W-Ratio of Oi to Ni LD air, v/v.
   OJ80-Molecular w-eljhl of N,or CO,  divided try JOO.
   6.190- Molecular waif M of Oi divided by  100.
   »,**0-Molecular watfbl of COi divided by MO.
  $.2  Pejroent Eioe** Air  Calculate the pffl-c*ru eseess
ftlj  flf  applicable),  by  iUb*lltuUaK  tbe  appropriate
values of perwntOs.CO.fcnd NI (obuJrwd from B«cdon
4.1.1 Of « 2 4) Into Equation »-l
%EA,
                   %O,-0.5%CO
                                               100
            1-264 %N,( %O,-0.5 %CO)

                                    Equation 3-1

  NOTT —The *qn&tlon  above amiiini 11 thai  ambient
air lj u»e-d a* the »ouroe of Oi and that  the fuel does not
contain appreciable arooiLntj of Ni (aa  do ooke ove.n  or
blast fumaoe taAps)  For Ihow ca«e« when appreciable
amounts of  Ni are oreBrnl (ooal, oil.  and natural iraa
do Dot oonlatn appreciable amounts  of NI)  or when
oarien enrtchjue.nl is osM, alternate mfttbodj;. wbject
to approval of  tbe AdjulnLitrmtor, are required
  OJ   Dry  Molecular  Weight  Ute  Equation (-2  to
calculate the  dry  motacular w&lfht of  tbe (tack fas
                                    Equation 3-2

  NOTI —The above  equation doe« not aooslder arfon
lo air  (about 00 p«roent, molecular veifbt  of ff7 7).
A Degative error  of  about  04 percent la Introduced
Tbe tepUr may opt to Include argon in tbe analyBb using
procedure* aublect to approval  of  tbe  Administrator


  1.  AlUbuQer A P. Btoraft of OaMB and Vapors In
Plaitlc  Baits  International  Journal o(  Aii and Waur
  2. Conner, William D. and J. B. Nader. AJr Sampling
Plaatic BagB. Journal ot the American Industrial By-
(lene Araociallon. US)\-1S>1. 1»64.
  V Barrel] Hanuul lor  Oas Analy>t>, 8»vt«Jtb edition.
Surrell  Corporation,  2Z23  Flftb  Avanue,  Pituburib,
Pa. 16218  1951.
  4. Mitchell. W.I. and M. R. Mldietl. n«ld fijiUablUty
•/ tbe Orsat Analyur. Journal of Air PoilnUoo Cootrol

  t. 8bif ehara, R T., R. M. Neulioht, end W. 8. Smith.
Valldadng Orsat Analyils Data from Fooil Fuel-Fired
BnlLs  Btack Bampllnf Nev». ^(2)21-26. Aoput, l»7fi
                                                                                                             1.1  FrUkdpVe  A r« MmpW U citracttd at a
                                                                                                           trnt* from Uw iwurc*, mot*Uirt ij fmmr>v*xl from Lh* t
                                                                                                                       and
                                                                                                             IJ  AppltcahflJty  Thti  method  to  appUcabk for
                                                                                                           4*t*TTT] LaJ o/ lh« moLrturt oociani of Kack ji-
                                                                                                             TV^ ja^>o*dur« are  |1»en  7l>« ftrtt  it  t raterrno*
                                                                                                           •wthod, tor aocurau determinatkmj of molnure oonifnt
                                                                                                           (fl&cb u arc Dwd^d to eaJcuitle vmlMlon  dau1  Thr
                                                                                                           eeoond U an approilmatlon  meihcxJ.  which prcndf*
                                                                                                                    of pert* n I moLnurr to aid In *ettln4 uokmfuc
                                                                                                                    raws  prior u> a pollutant soul**! on ro*»*uri*-
                                                                                                                 run Tbe  »pproilmaiion  m«tho<3 de*chb*<3 herein
                                                                                                           b  only  a iu()te«iT>d approach,  aK*raaLlTt  m*>-
                                                                                                           «i*Jy vltb t pollutant «Di»km meAJiirement run, when
                                                                                                           H L*. oaiculauon of parotm L*okln*tlc. poUutani amlarion
                                                                                                           rate, etc , tor tbe run aoail bv b**ed upon tbt> re*ulu> of
                                                                                                           tb* rfifcrpnce melhod or lu equlTaleoi. the»e oaicuiationj
                                                                                                           aoall noi be based upon the re*uJu of the approujnalton
                                                                                                           method,  onJe»  thr approximaUon method U abown. to
                                                                                                           tbe sattalariion of ibc Adjnloistraior. V 8 EnTironiDen-
                                                                                                           taJ Protection Afency,  10 b* capable of  fleJdJOf rwuJu
                                                                                                           wlthJn 1  percent BrO of tbe referenc* method
                                                                                                             NOTE — Tbe refertnce method may  yVeld queetiooabW
                                                                                                           nruJt! vb«n apphod  to •aturmU^l (u vtmuDJ or to
                                                                                                           •treamj that oonLaJn w»ter  dropl*t.i  TbereJorc  when
                                                                                                           tbeee> cotidltlon* exIM or  arr »u»peirLfd.  a aecond dei«--
                                                                                                           miaatJon of the moisturr content thai) be made nmul-
                                                                                                           taneoualy with the relerenr* method, as (oliowi AJwiune
                                                                                                           tbat  the  fas ertreajB Li Miuraind  Attach a temperaiurv?
                                                                                                           •enaor [oapablf  of meajrunn^ u>  »]° C (2*  F)| to tbe
                                                                                                           raferenre method probe  Measure U« itark n» tempera-
                                                                                                           ture.  at eftcb travane point (ie* Section 221) during tbe
                                                                                                           rvterenoe method tracers? caJrulaU  tbe averfeftf  rta^ k
                                                                                                           fu teraperatiire Netrt.  determine tbe motrture pen^nt-
                                                                                                           •gc.  eltner  by.  (1)  nslng a  prycbrometric  chart  and
                                                                                                           y**V-ing   appropriate oorrrcUonj  U vtack  preaEure.  U
                                                                                                           dWerent  (rom that of the cb*rt,  or (2) tnlni mturauon
                                                                                                           Tftpor pre^nin; table* lu  cases wbare  tbe peychrometnc
                                                                                                           chart or  tbe iaturation  rapor prM5ure table* are not
                                                                                                           Applicable (b«aed on eraJuauon of Uve proc«cs), alleraaU
                                                                                                           method!, tub)ect to tbe appro r*J of tbe AdmlniAraXor,
                                                                              '
                                                        Tbe proosdur* 4Mcrfbed tn Method 5 lor determinint
                                                      a»»ljtur» content Is acceptable ai a r%JereJic* OMthod
                                                        t-1  Afpftratiu   A KaemaLic  of tbe mmpllnc train
                                                      •ad In Ibis raieraiio* metbod LJ abown tn Ftfurv 4-1.
                                                      All components abail b*  nmlnt*Jn*d and f*librmted
                                                                to tbe prooadort outlined Ln Method &
                                                             VOi. -41, MO.
                                                                                                             I,  «977

-------
                                                           EUUf ANB  REGUlATIONf.
        FILTIR
 fEITHER IN STACK
 OR OUT Of STACK)
STAC*
 WALL
CONDENSER-ICE BATH SYSTEM INCLUOINO-
                         SILICA GEL TUBE —y
                                                                                                                 AIR-TIGHT
                                                                                                                    PUMP
                                          Figure  4-1.  Moisture sampling train-reference method.
  11.1  Probe Th« probe )i  constructed  o( stalnlen
•tmi  or sJaM  tubing, sufficiently heated  to  prevent
wator condensation, and Is equipped with »  filter, either
In-iuck (e.f., > pluf of (laat wool  inserted Into the fad
tt Vh» probe) or heated out-rtack  («-f., w described In
Method 8), to remove paniculate matter.
  When stack conditions permit, other metals or plaatio
to blng m»7 be used to th« probs, subject to the approval
of th« Administrator.
  IIJ  Condenser.  Th«  condenser  consist*  o< tool
toapingCTS connected la seriee with ground glan, leak-
tree fittings or any similarly teak-free non-contaminating
fitting*. The Am, third, and tounh implngers shall  b*
of the Oreeuburg-Snuth design, modified by replacing
the tip  with t 1.3 oentimett*  !H Inch) ID tlaa tab*
extending to about 1.3 cm  (M  In.) Irom the bottom at
tin flaik. The lecond implnger shall be of the Oreenbuif-
Smllh design with the standard tip, Modification* (e.g.,
using  flexible connections between the impingers, using
mataruJs other lhan glaas. or using fleilble vacuum line*
to connect the niter holder to ibe roadenser)  may  b»
used,  subject to the approval of the Administrator.
  The •first two Impincen shall contain known  volume*
•I wtur, the third shall be empty, tnd the  fourth shall
contain a known weight of ft- to 16-meab indicating typ*
falioa  gel, or equiTtient deftocact. II  th« silica gel haft
been prerloualy used, dry at 17»* C IJW F) for 2 boon.
New liilci gel may tx uied w re«elT«L A thennotnetar,
capable of meanrlng temperature to within I* C (f F),
thai] be placed »t the ouUct of the lourth Unplngtr,  tac
monitonnK purpoAec.
  AlternAtlvely, any system msr b« o*e4 <*qb)aQi t«
the Approril of the Adminlatntor) that cooto tn* sampto
KU stream and aiiows measorem«at ol boUa th« wfttaf
that hai be*n oondenaed and the  moUton learlnfl th«
condenser, eeteh to within 1 ml or 1 g.  AcccptobU meaa*
are  to  meuon  UM condenod  water,  either  grmrt*
metrically or TotaiD«tr1cai}y, and  to meaftin the mota»
ton   learlnf  Uw  eoodetus by: (1) mooltorini UM
temperature and pi amm At tha exit ol  to* oonaanaar
uid uatng Dalton'B law of partial pnoorw, at (2)
           th« sample rat stream  through a  tared silica gel (or
           equivalent deaiccant)  trap,  with exit guta kept below
           20° C (08* F). and determining, the weight gala.
             II means other than suioa gelare used to determine tba
           amount of moisture leaving the condenser. Ik Ls recom*
           mended that silica gel (or equivalent) still be used be-
           tweeo  the condenser ryst«m and  pump, to prerent
           moisture  condensation  In  the pomp  and  meterlnc
           dericM and to  avoid  the need to maie oorrectiotu tor
           moisture In the met«red  roluma.
             2.1.)  Cooling System. An loe bath  container and
           crushed Ice (or equivalent) an used to aid In condensing
           moil ton.
             2.1.4  Metering System. This system Includes a vac-
           uum gauge,  leak-tree pump,  thermometers capabl* of
           measuring temperature to within 3* C (5.4° F), dry rat
           meter capable of measuring  volume  to within 2 percent,
           and related equipment ai shown in Figure 4-1.  Other
           metering  systems, capable  of maintaining a constant
           sampling rate and determining sample gai  volume, may
           be used, subject to the approval of the  Administrator.
             2,1.0  Barometer. Mercury, aneroid, or  other barom-
           eter capable of measuring atmospheric pressure to within
           2.A mm Hg (0.1 in. Qg) may be used. In many caiefl, tha
           barometric reading may be  obUiined from  a nearby
           national weather service station, in which case the sta^
           tlon value (which 14 the absolute barometric pressure)
           shall be  rcqueeted and an  adjustment  tor elevation
           dlfferencee between the weather station and tbe sam-
           pling point shall be applied at a rate of minus 2.S mm Hf
           (01 In. Hg)  per 30 m (100 ft) elevation increase or rto»
           vena (or elevation decrease,
             3.1.8   Graduated Cylinder  and/or  Balance.  Theea
           lUnu an used to meaiure condensed water and mobtur*
           caught In the silica gel to within 1 ml or OJ g. Graduated
           cylinder* shall  have subdlvlslont no greater than 1 mL
           Moat laboratory balances ore capabU of weighing to to*
           nearett 04 g or last. Then balance* an lullabla  tar
           UM ben.
             2.1  Pnmhm. The feuowlnc procedure b written tar
           a  -rm'ltnnr  sr*t*m (such  a* the Implngar sysUm de>
                            scribed in 3«ction 2.1.2) incorporating volumetric analy-
                            sis to measure the condensed moisture, and silica gel and
                            gravimetric analysis to measure the moisture leaving the)
                            condenser.
                              2.2.1  Unless otherwise specified by the Administrator,
                            a minimnm  of eight traverse polnta  shall be used foe
                            circular stacks having diameters leas than 0.61 m (24 In.).
                            a minimum of nine points shall be used for rectanfolir
                            stack* having equivalent diameten  lee*  than O.A1 •
                            (24 in.), and a minimum  of twelve travers points shall
                            be used In all other case*. Tbe traverse points shall be
                            located according to Method 1. The use of fewer point*
                            is aubject to the approval of the Administrator. Select •
                            suitable probe and probe length  such that all traven*
                            points can be sampled. Consider sampling from op posit*
                            tide* of the stack (four total  sampling ports) for large
                            stacks, to permit use of shorter probe lengths. Mark tn*
                            probe with heat resistant tape or by aome other method
                            to denote the proper distance Into the stack or duct tar
                            each sampling point. Place knovra volume* of water la
                            the  first two impingers. Weigh and record  the weight ol
                            the  silica gel to  the nearest 0.5 g, and transfer the slliejk
                            gel  to the fourth implnger; alternatively, the silica get
                            may first be transferred to the implnger, and the weigM
                             of the silica gel plus impinger recorded.
                              2.2.3 Select a total sampling time such that a  mint
                            mum total fat volume of O.oO sera (21 xi) will b* oai>
                            lected, at a rate no greater than 0.021 rn'/uun (0.73  ctmk
                            When both moisture content and pollutant emission raB
                            an  to be determined, the moisture determination IhM
                            be simultaneous with, and for the same total length ai
                            time M. the pollutant emlatlon rate run, uolesaotherwlaa
                            specified In an applicable subpart of the staodarda.
                            condenser; allow Urn* for the Umperaton* to rtalHtaai
                            Place crushed loe In the loe bath container, It la reopay
                            mended, but not required, that a l*ak ebeok b* ooaa, •*
                            follows: Dlaoonnect tb* protM from tba arat laplafat**
                                       FBMfiM tfOOTiiX VQI. «V NO.  Uft—THWBOJrT,  AUQtOC ]«,  1


                                                                            D-26

-------
                                                      «O12S  AND  RfGULATK>NS
                                                                                                                                             41773
fliapplloabl*) from tb«flH*r bold«v Pli* Ui e tiJ«t to UM
StumpImw (of an*r boldv) UM) poIJ a MO mm (16 to.)
HI radium. » lowv Tacuum mat tx aj*i, prtrrld*d tbal
Jill DO!  eioepdfcd during Lb«  wt A  Uaiafe  rate ID
    3 of 4 percent or tbe a^arat* mnpllof r»U or 0.00067
      (0 02 dm),  vblcbevftr  Li WM, U  on*oo«pl»bl«
                  '   *      i£»*ct Lb* prob« to Ui*
   ..	-"train.
   J 4 LHirtrn UM mnpunf run, muntun \ »mp 11114
        t 10 parownt ot oorut^nt rmt«, or M vpeotfied by
lb»  A4minl*tr»tor  For **cb run, noonj tb« d&t« r»-
•ulr»d on UM u&mpl*  tbr
                                                                                                      ~~
                                                                                                     LI
                                                                                                         Flfun 4-1 ) and onlculftU UM moljtorr
                                                                                                               In
                                                                                                   tt* kCQULnd d»U. Eouod oC
                                                                                                   tton
                                                                                                                                         rond
                                                                                                                                        ftrukl oklcult-
(•CATItm.
   I HO..
MIIIErr TOITERATUM-

MMMETRIC raCSURE_

r*OU LEBtTX >(*!)
.
















•MUMPlt TBft»E«»TUHE
AT B*Y MI METUt
•arr
rr«j.»cm












•


*
-------
41774
RUlH ANOF REGULATIONS
                                        INITtM.
                         1U  NestteoLatara. '                          ~
                             S«-Proportioo of watoi vapor,  by volunu, la
                                  the gu rtream,
                              Mm- Molecular weight at water. 18,0 j/j-mole
                                  (18.0lb/lb-mole).
                              PM«Absolut« preasnn (lor thU  method, sam*
                                  u barometrlcpretiun) at the dry g M mete*
                                  mm Hg (In. EJg).
                             Pwj™ Standard  abaoluU preesor*, 760 mm  HI
                                  (29.93 In. Hg).
                               J7-Ideal  KM oonttent, 0.00231 (mm Hg) (m*)/
                                  (g-mole) (°K) for metric QnlU and 21.84 (In.
                                  Hg) (ff)/(ib-mole) (°R) for  English unlta.
                              T.- Absolnte temperature at meter, *K (°R).
                             T*t~ Standard  abaolut*  temperalun, 2M*  K
                                  (52T R).
                              Vm- Dry gu volume meararoit by dry gal meter,
                                  dom (dot).
                             AK»» Incremental dry ga* volume meanmd by
                                  dry (at meter at each Inverse point, don»
                                  (dcO.
                           V.(M<)~Dry fm voJum* meaturad by the dry ga*
                             ,,   ~meter, oometed to  staadard  condltioaa,
                            '                         ~
                         14. J
                                  dsom (dao'                ,       ~
                             («<>— Vamme o< water vapor condensed correeted
                                  to standard condition*, som (scl).        —
                             iatt -Volnm* of water  vapor collected In aUlco
                                  gel cometed to standant condition*, sea
                                  (sal).
                              V/ - Final volume of condenser water, mL  •
                              V,- Initial  volume, U any, of condenser wafer,
                                  mL
                              IT, -Final weight of allies gel or silica gel pint]
                                  Implngtr, gs
                              ITi-Inltlal  weight o< silk* gel or silk* gel plo*
                                  implnger, g.
                               V-Dry gu meter calibration factor.
                              r.- Density  ol  water,  O.Mtt g/ml  (0.0002m
                                  Ib/ml).
                              Volume of water vapcc-eondeosed.
                                         =/r,(v>-r.)
                                                            Equation 4-1
                       where:
                         £\—O.QOl3& mVml for metric onlta
                            -0.04707 rt'/ml far English nnltt
                         t.t.t Volume at water vapor collected In silica geL

                                 „           (Wf-W<)RTtli
                                                            Equation 4-2
                       -17 « '
                                                                                            fcun Hg fcr melrfc uiilU
                                                                                            a. Hf tor English anin
                                                                                No™.— H th* pott-tet* leak mtt (Seotlon  7.2 » *»•
                                                                              ceede UM allowable rmU, correct  the rain* of V, la
                                                                              Equation 4-4, at described In 3«etlon » I o< Method i~
                                                                                3.3.4  Moiaturs Content.
                                                    j (til)
                                      '/i fer metric anlta
                            -0.047U ff/gtar English anlt»
                         34.4 Sample gu volume.
                                                      Equation 4-4

                     N'OTt.—fn saturated  or moisture droplet-laden gas)
                   streams, two calculations of the moisture content of the)
                   stack gae shall be made, one using a value baaed upon
                   the saturated conditions (see Section 1.2), and mother
                   based upon the result*  of the implnger analyata. Tbe>
                   lower of these two valuea of Bm shall be considered cor-
                   rect.
                     2.3 a  Verification of constant sampling rale. For each
                   time Increment, determine the  AK_  Calculate  the)
                   averti*. If the value for any time Increment differs from
                   the average by more than 10 percent, reject toe result*
                   and repeat the ran.

                   3. Apprazinutin \ttOwt

                     The approximation method described below la pre-
                   sented only at a suggested method (see Section 1.2).
                     3.1  Apparatus.
                     3.1.1  Probe. Stainless steel or glass tubing, sufficiently
                   heated  to prevent water condensation  and equipped
                   with a Qlter (either In-slack or heated out-stack) to re-
                   more particulate matter. A plug of glass wool. Inserted
                   into the end of the probe, Is a satisfactory Biter.
                    3.1.2  Impingers. Two midget Implngen, eacb with
                   30 ml capacity, or equivalent.
                    3.1.3  Ice Bath. Container nd Ice, to aid In condens-
                   ing moisture In implngen.
                    3.1.4  Drying Tube. Tube packed with new  or re-
                   generated ft-  u> It-mesh indicating-type silica gel  (or
                   equivalent deekcaat), to dry the sample gu and to pro-
                   tect tile meter and pump.
                    3.1.5  Valve. Needle valve, to regulate the sample gss>
                   flow rate.
                    3.1.a  Pump. Leak-free, diaphragm  type, or equivo-
                   lent, to pull the gu sample through the tralnv
                    3.1.7 Volume meter. Dry gu meter, soflUlently ac-
                   curate to measure the sample volume wtthin 2%, and
                   calibrated over the range of flow  rates and oondltiona
                   actually encountered during sampling.
                    3.1.8  Rate Meter.  Rotameter,  to measure  the flow-
                   range from 0 to 31 pm (0 to 0.11 eta).
                    3.1.9  Graduated Cylinder. 25 mL
                    3.1.10   Barometer. Mercury, aneroid, or other baronv-
                   eter, u described In Section J.I.5 above.
                    3.1.11  Vacuum Oauge. At least 780 mm Hg (30 In.
                   Hg) gauge, to be used lor the sampling leak  cheek,
                    3.J  Procedure.
                    3.3.1  Place eiactly 5 ml distilled water In each Im-
                   pinger. Assemble the apparatus without the  probe u
                   shown in Figure 4-4. Leak check the train  by placing a
                   vacuum gauge at the inlet to the first  Implnger and
                   drawing a vacuum of at  least 250  mm Hg  (10 to.  Hg),
                   plugging the outlet of the rotameter, and then turning
                  off the pump. The vacuum shall remain constant  for at
                  east one  minute. Carefully release th* vacuum gaugsk.
                  Ibefore unplugging the rotameter end.
                                                                  .  HO. i«o—THUISBAY,

                                                                   D-28

-------
                         $ ftNO IFCUIATIONS
                                                                          "41775
HEATED PROBE
           \
                 SILICA GEL TUBE
I
i
•M^H

r
 MIDGET IMPINGERS
                                PUMP
      Figure 44. Moisture sampling train - approximation method.
LOCATION.
TEST
                                                 COMMENTS
DATE
OPERATOR
BAROMETRIC PRESSURE
CLOCK TIME

.
•


GAS VOLUME THROUGH
METER, (Vm),
m3 (ft3)





RATE METER SETTING
m3/min. (ft3/min.)





METER TEMPERATURE.
CC (°F)


i
-

  Figure 45. Field moisture determination • approximation method.

-------
4177*
                                                         RUL8S ANO- •EOWATIOf*
                          SJLJ Connect til* profe* Insert It Into th« rtaok, an*}
                        nanpl* at s eomtant rat* oi 2 1pm (0.071 otm). Contlnnev
                        sampUnf until tbs dry gat meter reglaten about  W
                        ateri(U ft") or until vWbl* Uqold droplets are carried
                        ova? from the firm tmplnger to tbe second.  Record
                        temparatcre. preiiiair*, tod  dry  ga* mater reading* a*'

                         3A»  After collseUng th* auapl*, eombia* th* ectv
                        Uota ol UM tva tapio(«n uid meonn lb« Toioau to tte
                        ne*rat0.8mL
                         it  Caloul»Uon*. Th* calculation method prevented to
                        designed ta eetlmMe tb* mol*tur* IB tbe tuck gt*;
                        thereto*, other data, which are  only Decenary for ee-
                        ear*** moUtan determination*,  an not collected. The)
                        foll*wlzig eqnatktn* adequately «0tlm»U tb* motatnre
                        mcuot, tof UM parpen ol detMmlnln« UokinxJc  aia-
                        pllnj rate nttlncL
                         i-i.1  Nom«nclator%.
                            B.o-Approilm»t»  proportloB,  \>r   TOloro*,  ol
                                 wmttr rapor In tb* CM itreun l«*Ttnf
                                 second Impinge, 0.02&
                              ^- wmr T»p« In UM jus itraa, projMrtlae by
                                                  rf  mt«,  U.O c/l-mot*
                                 (I8.01b/lb-mol«)
                             Pa-AbaotaU preoon (tar toll a«tbod, MOM a*.
                                 b&romclrlo praamn) «t tb* dry u* mct«r.
                            J».w- Standard absolute  proatraa,  7(0  mm  Hf
                                 (29.M In. HI).       _
                              R— Ideal (U ooniUat, O.OBa* (mm Hf) (m
                                          °                    and 21
                                 (•-mote) (°K)  foe metrlo nnlU
                                 (In. HO cm/Ib-mol*)  (°B) lor
 T.
7M<
 V>=
 Vd»I
                                     ,
                                 Abaohit* tampantDn at metw, *C (*R)
                                 8tandvd  abaolnt* Umptraton,  2ST  I
                                 (52T B)
                                 Ftaatl TOhmM «t Implnccr cestcnti, mL
                                 Inltljhl Tobun* of ImplTLfftr eontfiixtt, mL
                            F.™ Dry ru Tommc nuatond by dry (M auUr;
                                 dom (d«f).
                         V»(iu)»Dry (a* Totmu meafond by dry gat metar.
                                 oorraettd  to  rundard  condluoaa,  dMB
                                 Idaof).
                         V«.(.u>**Volam« of water rapor eondennd, «gmet«a1
                                 to standard condition*, son (set).
                                              T. 0.9983 sMl (0.003301 Ib/ml).
                                                        Equation 4-5
                             O.Otin* m>/ml lor metric unite
                             0.0*707 ftVml tor EngUjb nnlta.
                                                        Equation 4-6
                                  "K/rnm Eg for metric onita
                           -17.M 'B/tB. Eg for Engllaii ontta
                                                                                 Eqoatioa 4-7
                                                  4.1  for tb* reformat method, allbrat* equipment M
                                                 tpecloed In tb* following atctloni of Method 8: Section ».»
                                                 (meterln* syitem);  Beetlon J.S (temperatnn (ante*);
                                                 and Section 9.7 (barometer). Tb* recommended leak
                                                 cbeck o/ the metertnf lynem (Section 5.8 of Method •)
                                                 alao appllet to the reterenc* method. For tb* approxlmo
                                                 Uon method, OM the prooedurw ontllned In Section 5.1.1
                                                 of Method • to  callbrat* tb* mettrlng syitem, and tlM
                                                 prooednn o< Method  », S*eUoa 6.7 M ailbrmt* UM
                                                 barometatv
  1. Air Pollution Enflneertci Manual (Beoond Edition).
DanlelMB, /. A. (ed.). U.S.  EnTlronmental Protecdoo
Agency, Offle* of Air Qoaltty Planning and Standard*.
Rraecrcb TrUngl* Park, N.C. PubUoation No, AP-*8,
1»7».
  3. DeTorkm, Homrd, «t al. Air Pollution Soon* Te*V
Ing ManoaL Air Pollntion Control Dlatrlet, La* Angola*,
CtUl. November, 19M.
  3. Method* (or Determination  of Velocity, Votamav
Doit and Mlat Content ol OtM*. Wattem Pradplutloa
DlYldon of Joy Manafactarlng Co., Lot An«>i««. Calif.
Bulletin WP-JO. im,
                                                            mmidRnioii or riBncuun KHUOOICS
                                                            FROM BtiisONi*! Sotxci*
                                                  1.1  PrtoclpK Partiealaia matty to withdrawn 1m-
                                                Unatically from til* soure* and colleoted  oo a g'aai
                                                fiber altar maintained at a temperature In the range of
                                                12O±H« C (24S±2S* F) or  such other temperature *•
                                                speclnad by an applicable subpart ol  tba standard* or '
                                                approved by tbe Admlnl*trator, U.S. EnYlronmenMk
                                                Proteetloa Agency, (or a particular application. Th»
                                                partteiilat* ma**,  which  Inclode* any  material that
                                                condenae* at or above tbe al&adon temparatare, •*
                                                determined gnTtmetrlaally after ramom of ilnmmMi»i
                                                W*I*T.
                                                  1 J  Applicability. Thie method I* appUeable fer tbe>
                                                determination of particulat* emlssloni tram lUtknary
                                                aooreei.

                                                2. Appmtmt

                                                  11  Sampling Train. A schemata  ol tb* sampttnf
                                                train oaad In thl* method 1*  shown bi Figure 5-1. Com-
                                                plete construction  detail*  are jiren  In APTD-OMt
                                                (Citation 2 In  Section 7); commercial model* of tnir
                                                train are alio available. For change* from APTD-Osn
                                                and for allowable modlAcatlon* of the train ibown la
                                                Flgor* 5-1, see toe following  subetction*.
                                                  Tbe operating and malotenanoe procednn* for UM
                                                aampllng train are described In APTD:O67« (Citation t
                                                In Section 7). Since correct usage 1* Important In obtain-
                                                ing valid result*, aJQ oaen should reexl  APTD-0878 and
                                                adopt tb* operating and maintenance procedure* out-
                                                lined In it, unleei otherwise specified herein. Tbe »am-
                                                pllng train conslit* of tbe following component*:
                                                              4t,  M,, >«•—IMUMBAV,


                                                                   D-30

-------
                                       tUWXATOWS
                                                                                                                                       •err:
                         ¥p»>
ERATURESENSOR
                  rTTJJTTUBE
                                   ~1KOBE

                                    TBpVERATURE
                                         KNSOB
                         WOBE    /M    STACK
                               V-/   [>-
                REVERSE TYPE
                   HTOTTUBE
                                                                                             TRAIN efTfONAL.WAY 8E P«Er»tACEO
                                                                                         lYANEOUIVAlENTCOKDENSER
                                                                                                    CHECK
                                                                                                    VALVE
                                                                                                                                    VACUUM
                                                                                                                                      ilNE
                                                                                                                \
                                                                                                               VACUUM
                                                                                                               CAUCE
                                THERMOMETERS


                                                   fcflY.ASWETER         AIRTJGJHT
                                    ^jp
                                                                                                   m*l!N VALVE
                                                   Figure 5 1.  J*arUcutate-ttmplkig train.
                       •*» fUel ()U) er flM with
.a«rj>, kpm) haillni edge.  Th* aa«le of taper iball
 fe SID* and the taper ataall b» oo th* ouuld* to pnecrte
 temtaol tnternaldlarattfr  Th« proble noule thai! be
 at thi bcttcro-book  or elbow dWrn,  onleei otherwise
 •wdJ&ed bj the  Administrator. I/ mad* of Rainier*
 •Mi, the Doule shall be oomtructed from saamleai w b-
 aar other material! of oomtrucucra may a» and, sab)ect
 % tbe approval of tbe Administrator.
   A range of naule stae* suitable tor l"""r****f ^n»pli"f
 *ould be eTailabie, K., OJ2  to U7 em (H to H ln.>—
 • kviw U hither Tolum« ««inpi*i»f traira an m*»a—
 Mde diameter (ID) coiilel  In tncnmwa of Q.U em
 (fci la.), Kecb noai* shall b« aallbrated aaaanttoc to
: Be preaedani outlined in Section 6.
   II. J  Probe Liner. Boroailicate or quvtx (}MB tnbinf
       U Uu alt wd dann( mmpiinj oTiatbtH0 C
        f ), er neb Mber t*n>peratun M tpKLted by
 -—	y opt tooparmte lb* •qulpiiMOt.it»Umpcrmture
 tonr HUB Out upcci^d.) Since Lhf *ctxuU tasmmnture
 «tb»ouU*< of the probe ti not iwu-Ux mooltona darlnf
 •mpllnj.  probM oooitruct*d fcooardinj to APTD-0681
 ftft<1 DOiiuin tb« tmUbrmQofi earr*. of APTD-067. (or
 «lJbnu the »ppnyr»j ol tbe Admini*-
      T^P  ftolXminx  tKnptriUxm t>r  borodlicifti*)  !•
     ; Q#r F). and'far qTmni U u 1 fa • C V,TK? F)
         t praciicaJ, vr«ry aflon should b* made to B*»
         t or ojDara rlaas prob* ttnerv A-rlenieulvely.
         \- I . tlf iril-'-r PteeJ Inootoy 826 ' or other
         m«a^t  Bpetali} *"*^t* of aaem^eH mhtr>^ may
  I oaad, sob>*c. 14 ttM approraJ at Lh«  A dmlnlxtralor
  t-U Pltol Tab* Trpe B, ai iaaolbed In Secttoo 2 1
 • Method  2. er ether etna apprtrr*d by DM Admlnl*-
   '   Tbe pltet cube Aall b* ulecDed to Ikejjrot*  i*i

      > 4SoAy  tte
   U«tloc eJ tnwk r»m«i or ^ndflc prcxtocu doM oat
                    by t^* XnrlrcfXiDiaUA} Frot«o-
                plan* of the pilot «nb«

                          b* Trp* B pilot
                        *ffi
ob« afaall be mo with or abort tbe  tac tenperatore to alBloi  F C V F) -
                •t&l may U o«ed.
                  t.1.7 Oocdwer. Tb»  faUowltu »ra*3i tSjifl bt and
                t>  fcnimita  the  Keek fa* naoutum BpaWEt:  Fair
                tapuaon nnnrnraod  In Mrtei  with  lemfc-lrae cmind
                |lus fltuiip or any similar k*ai-trte DOo-«anlamInaUa(
                Bt^"ir" Tbe am,  third, and (oonh Implnfen **>aJi b*
                «l the OfMnburt-6mJib  djaifn Bodlned by noUelnf
                tax up viUi 1J UD CH In.) ID |iec lob* •ncndinc lo
                About  LJ cm CH In.)  Crom the bottom of U>e Aaak.. Tbe
                oaoood bmpti^er aball b* »f the Or«anburi-&iilLrj dealgo
                     Ibf et*odArd tip. UodlnaaJJooi '* |  oMnf flexible
                            lim '• MBI  the  LmpiAgerv  oa^ot
                 •Our tbac I'LMI  *r u«a» flexible racuam Uo«
                 tfce oit*r it^rf**  to lh* oonderjaer) nuy be QJ*d    r
                 lo the approval •' Uke Admlnlnrator . Ttx  fim and
                 ••ocmd  lni(.«tn«n aball *ooi*Jn  known  qoanuua  ol
                 w»ter (Becilcm C1J). the third (ball be tmpty  and th*
                 feonb abAlJ oonialn a tnowc  «r«ijhi of «U
  tared dlloa  icl (or  aqmnlerjl desiooanU trap
  It ftam kept b*brw  Sr C (•* T) and detem
a
mi
                                                                             with
                                                                      rtetarmlrlnt
                                     ttam kept
                                          (ain.
                                   I/ neani other Man wOtm |*i ar» «a»d to ilalaalnu
                                          l at maoKan  haavlnc  tte  anriiianier.  It U
                                              ttet  alllrja |«l  (or «iulT»let)0 attll  b*
                                 •••MJ l"'4 • aau the orjodeaw tyvbu and pomp to pmect
                                 moUture ooodooaUOE to la* pomp and Beurlnf drrton
                                 •ad toa*old tbtoaad to aaa*« eorraoUm lor auattor* In
                                •Ih* meUnd vohuna.
                                   Mori — II a doUnntnattiD trf the partteilen aanir
                                «oll«ote<] In tha Lrjrpixnon to (iealrad to addlUoo W noU-
                                 tan oontanl. tb4 lmpln|er ryuam described aber« aball
                                 to Bead.  wlthoDl  Bodlnoatioo.  ladlridoai  Buua or
                                 ••Qtral attcoiB nqolrlni tho  InJomnuJoo anail  b*
                                 emlaetad M U) tbe aaple naunij ajtd afMOjtai *i tbe
                                 bnpfnfer oonunu.
                                   tlJ  Uelertnt  »7»lem. VaoaoD  Bare, taal-trw
                                 yump, thtrmnm«1en oapable of m«a»anoi Mmperatun
                                 is wlihln f C (!> 4*F),dry(ai m*ur capable of meaaurlnt
                                 walome to wlLtic t paroacu aod ralaied
                                 •bcwr, tn F1(un »-l. Other naterlnf
                                 malnUklnJof atrnpllnt nua within 10 percent of too-
                                        and a^ dFUrmlalA( auopit Toiam*> lo within i
                                       t nay Iw UMd,  aubjeol  u> th* aprjrjTaJ  ol the
                                           ur. Vban Ik* Baurtaf  1711*10  U aaed In
                                 •oajuocuoo wltb a pilot tsba. La* qrttam (ball (Bable
                                 •tMckj al IcokiDetlc rait*.
                                   n-~ rMr< mini nlllir1ni»at arl nirrrt amir] aUxpafl fcr
                                 fctgeer flcrw ruet Uui thai doaerlbed In AJTD-OiSJ or
                                 APTD-067e may b* OMd  pnrleW  UMi La*
                                 4tons &i ^ Mr aaj^hfid art otaL
                                   £.1.9 n.~~.... w ----- y --- ^ trf
                                 «apable of maMurlni  aLmaepberic pnasun to  within
                                 t-6 mm HI (0.1 In  Rji  In macy earn, the  baromttrlo
                                                                   ,
                                        may b« obtained Cnrm a nearby o*ttoaa] weather
                                       Aauon, In whlob OBM Uw itatioc rain* (which I*
                                                                             wwwwtr,  mwtffr

-------
                                                             ilKIS AND  MIOULATtONS
 the abeoiuw bsotBatria is-aaars) aS»B ba r«qaraM! oat
 an adjustmsm  fgr «!®vMl«B  dlfiowwas l»tw»en to*
 w«»U» station tAd sMBplieg £«*nt shall b« applied tt »
 r»t* os aJaa 13 mm Hg (0.1 la.  Hg) par 30 a» (100 ft)
 f loraHsffl Inma** car « approval of to* Administrator.)
  9.2  Sampfe  a««w«?y.   Ttes foOowtntr ItHBa M«
                                                                         r«(tBti»nn«alr«4totk*iM^

                                                                     . 8«M M Mt               •
                                                              Derieawt. Aohydrooj eatatora nUtto, IndJea*.
                                                      lot typ*. Altenutlvelr, other tnm of dedceant* ma; b*
                                                      usad, fubjor* ta tto» appront ol tb* Admlniitrattr.
  32.!  ProHtos-Uner tad Probs-Norato Brush**. Kyiad
brtstks brashea with jtainleaB 3t**l win handle*. Tb*
probs brosb shall hav* extsndons (at toast a* long M
tb» probe) oi rtainlses steal, Nylon, Teflon, or similarly
in«rt materiel. Tb» bruahe* shall b* properly sited And
sh&ped to brush out tbs probe liner and no**J*>
  2.2.2  Wart  Bottle*— Two. Glass waah bottle*  an
reooELtaandsiS; polyethylene wash bottle* may be used
us, tha opttoD ol the tefrwr. It la recommended that aceton*
not b* stared. to polyethylene bottba lot tongor then ft
mon&M.
  2 3.8  aiass  Stmplt 8teas» ContdiMn. ChemlaJlf
razlstant, boroKlllcat« ti»" bottlo, lot acetone wsabm,
MO ml or 1000 ml. Bcrav c»p linen shall either be rubber-
backed Teflon us1 snail tra oomtroctad co u to be leaker**
and resijftsot Co chemical ftttsck bv antoo«. (Namnr
mouth cletB bottlei have 'MSB found to be lex pron* to
tefitafjis.) AU«rn»t!'?a!T, poljatbyloi*  botUe« may b*
used.
  2 2.4  Fetri Dlsltes.  Foi Mt«f samples, cla* or polA-
ethyleiM,  unJ«a  otlMrvin ipteiiM bjr  UM Admln-
tetntof.
  3.2.6  OraaSuisiwI CjUnd«f aad/or Belcac*. To meair
on MoAmewJ vat«r to withto 1 ml or 1 (- areduat«£
cTllDdera stutll h&n subdlTtaiani no greater than 2 nd.
Moat luboratasT balancaa s,™ capable oi weighing to th»
nearect 0.9 s or \et». An; o! tbeaa balanoM U suluble fcr
ua9 here asm In 3«ctloa 2.3.4.
  2 2 .6  FlacUe 8torag» Cca^ians. AU-UgJrt omtataoc
t» store silica get
  3J.7   FunjMt! aod  Babba?  Folkvnaau  To  kM ix
traoiw of slUon gal to container; no* meoMnar U sUta*
je! bt welghiHl In tb« SoM.
  2.2J  Fimjist. Qtaw ex pst^UilaM, to &M In nmpto
recowry.
  2.8  Aaslj«tB. For ssn«Jy^», tfes toDowlnf eqalpmsat to

  2.8.1   Olaes Weishtef DW6S6.
  23J  DaskcfiJ.tw.
  3.S.S   AnaJjtlta! B»itea«s»J'o mewura ta withls 0.8
  nl^.
  2.3.4   Batesss. Te measrafu to wlUnSn OJ j,
  2.S.8   Bes^rs. 260 ml
  2.3.8   HrpTjiaffiw To mee«ro UM rolatlm humidity
8$ UM tsboratory aaslronmcat.
        Tempermt^;^ Ofiues< To meaoaire the temp«ra>
                                 In amgtilnt sra
a. Rattfste

  8.1  8&£9&&bs*^ Tbd

  J.I.I  FihVsn.  QlMffi fifev  fitter*,  without
binder, exhibiting at le»*t 8».*S psroent efficiency (, be used.  SomotteMS.  guppllert trantiar
        to glca bonks Erora metal  contain*?*-, tbM,
   oo» bl&akii ituUl to ran prtss te field out and  ooly
tociMM with low bl*ate Tdaw <<(Uffl p*nMDt) shaU^b*
   ".  In Effl CSBS atiaij e blaaJi  ram* of greater tout f
   4.1  SampUog. Th* complexity of thlf method I* snekr
 that. In order to obtain reliable remit*; tetter* ibonld b*
 trained and experienced with th* te*t  procedure*.
   4.1.1  Pretest Preparation. AH the  component* anal
 b* maintained and calibrated according to the procedure;
 described  in APTD-0479,  onlen  otherwise  specified.
 herein.
   Weigh several 200 to MOr portions of silica gel In air-tight
 container* to tbe nearest o.i g. Record the total weight of
 th*  silica gel pin* container, on each container.  As aa
 alternative, tbe silica gel need not be prewelghed, btrt
 may b* weighed directly In It* implnger or sampling
 bolder lust prior to  train assembly.
   C neck filters visually against light tor Imgnlaritle* and
 fiaw* or plnhol* leak*. Label niters of the proper diameter
 on the back side near the edge using numbering mac bin*
 Ink. As an alternative, label the shipping container*
 (glow or plastic petri dishes) and  koep  the niters In these
 container* at aD time* except  during  sampling  and
 weighing.
   Deeiccau the filters tt  20±8.«* C («8=fclO* F)  and
 ambient presrar* for at least  24 boon and weigh at in-
 terval*  of  at lean 6 hours to a constant  weight,  I.e.,
 <0.5 mg change (ram prevtou* weighing; record remit*
 to the nearest 0.1 mg. During each weighing the filter
 must not be exposed to the laboratory atmosphere (or e
 period greater than 2 minute* and a relative  humidity
 above M percent. Alternatively (unless otherwise speci-
 fied  by the  Administrator),  the nlten ma;  b* oven
 dried at 106* C (220* F) for 2 to S boors, desiccated for 2
 boor*, and weighed.  Procedure* other than  thoa* de-
 scribed, which aeeount for relative humidity effect*, may
 be used, subject to the approval of the  Administrator.
  4.1.2  Preliminary- Determination*.  Select  tbe sam-
 pling site and the minimum number of sampling point*
 according to Method 1 or as specified by the Administra-
 tor.  Determine the stack pressure, temperature, and th*
 range of velocity heads using Method 2; It is recommended
 that a leak-check of the pilot lines (see Method 2, Sec-
 tion  3.1) be performed. Determine tbe  moisture content
 using Approximation Method 4  or  it* alternative*  (or
 the purpose of making Isotlnetic sampling rate settings.
 Determine the stack gas dry  molecular weight, u des-
 cribed In Method 2, Section 3.8; if. Integrated Method a
 sampling is used for molecular weight determination, th*
 Integrated  bag sample shall  be  taken simultaneously
 with, and for the same total length of time m, the par-
 tlculate sample run-
  Select a nozzle size based on the range of velocity head*,
 such that It Is not necessary to change  the nozile size In
 order to maintain isoklnetlo sampling rate*. During the
 ran,  do not Chang* the nozzle size.  Ensure that  tb*
 proper differential pressure gauge Is chosen (or the range
 ol velocity  head* encountered  (see Section 2J2 ol Method
 2).
  Select a suitable probe liner and probe length soeb that
 an traverse point* can b* sampfsd. Tor large stack*
 consider sampling from oppoelt* side*, it the stack to
 reduce the  length of probe*.
  Select a total sampling time greater  than or equal to
 the minimum total  sampling  tlm* specified in toe test
 procedure* (or the speolAo Industry such that (1)  th*
 sampling time per point is not lee* than 2 mln  (or some
greater time interval a* specified by tb* Administrator).
 and  (2) the sample volume taken  (corrected to standard
conditions) will eiceed the required minimum total ga*
sampl* volume.  Th* latter  1* based on an approximate
average sajnpling r»u>
  It  i* recommended that tha number of minute! Sana-
plod  at eacb. point b* an Integer or an  Integer pin* oo*>
haif minut*, in order to avoid  timekeeping error*.
  In  some circumstance*, e.g., batch cycles, it ma; be)
 necessary  to  sample for shorter  time* at th*  traverse
 points and to o4>t«in smaller ga* sampi* volume*,  la
 these case*, the Administrator1! approval mu*t  Orel
 be obtained.
  4 1.3  Preparation of Collection Train. During prep-
 aration  and aswmbly of tb*  sampling train, keep  all
opening* where contamination can occur covered until
lust prior to assembly or until sampling Is about to begin.
  Place 100 ral of water In each of the first rwo Implnger*,
 lee.v* the third Implnger empty, and  transfer appral-
 mat«ly 200 to MO g of  prewelghed  >W« gel (ram It*
 container to th* fourth Implnger.  More silk* gel ma; b*
 ueed, but  can should be taken to ensure that It I*  net
 entrained  and carried  out  from th*  Implnger during
 sampling.  Place tb* container In  « clean place  lor later
 us* In tb* sempl* recovery. Alternatively, the weight of-
 th* dike gel plu* Implnger may be determined to  tb*  sam
 nearest 0 3 g and recorded.  .
  Using a  tweeter or clean dtspoeabl* rurglcal i
 plan* a labeled  (Identified) an4  weighed niter '      .
 Altar bolder. B« sore that the AHer I* property center**!
 and  th* gukct property placed  *o  M to  prevent  th*
 lampl* res stream from circumventing tbe Alter. Check
 tbe alter (or teen after asetmbl; 1* completed.
  When class linen ar* ueed. Install  tb* selected nonfe
 aUng a vitoo A O-ring when stack temperature*  era
 lesTihan MC» C (SCO* r) and an eseerto* Wring pita*
 wtesn t/BnsMS-stu™  an Mgb*».  8*»  AiTD-Og?*  Iv
 detail*, Other ceonscttng ryitou ualng eitber 3M itaisr
 lesD rteei or Teflaa temle*< may b* used. When metal
 liner* are need. Install tb* noul* a* above ar by »leak-
 fra* direct mechanical connccdoji.  Mark tb* probe with
 beat resistant tape or by some other method to denote
 tb* proper dlftane* Into tb* stock or duct far each •sa-
 pling point.
   Bet up the train a* In figure 9-1, orlni (If necessary)
 a very light' coat of slllcone grease on all ground (lass
 Joint*, greasing-only tb* outer portion (see APTD-067J)
 to avoid  possibility of contamination  b; tb*  ilUcon*
 gnat*. Subject to tb* approval of  tb* Administrator, *
 flu* cyclone may be used between tb*  probe and liter
 bolder when tb* total partlculat* catch I* expected to
 eiceed 100 mg or when water droplet* an present In the
 stack ga*.
   Flac* crushed Ic* around tk* Implngtn,
   4.1.4 LeakrCheck Procedure*.
   4.1.4.1  Pretest Leak-Check. A  pretest leak-check I*
 recommended, but not required.  If tb* teeter  opt* to
 conduct th* pretest leak-check, tb* following procedure
 shall beu**d-
   After th* sampling train ha* been assembled, turn on
 and set th* fitter and probe heating system* tt tb* desired
 operating temperature*. Allow time for the Km pen tun*
 to stabilise. If » VIton A O-rtng or other leak-free conn**-
 tlon Is used In assembling the probe notilo to th* probe
 liner, leak-check the train at the sampling sit* by plug.
 ling  th* notal*  and pulling a 380  nun  Hg (14 In, Hg)
 vacuum.
   Nor».—A lower vacuum ma; b* used, provided that
 ft I* not exceeded during the teat.
   If an a&besto* string Is used, do not connect th* prob*
 to tb* train during the leak-check. Instead, leak-check
 tbe train by first plugging the Inlet to the Biter hold*
 (cyclone, If applicable) and pulling a 380 mm Hg (U In.
 Hg) vacuum (see Note immediately above). Then con.
 nect the probe to the train and leak-check at about 15
 mm Bg (fin. Hg) vacuum; alternatively, the probe miy
 be leak-checked  with the rest of the sampling train. In
 one step, at 380  mm Hg (15 In. Hg)  vacuum. Leakage
 ratee  In excess of 4 percent of tbe average sampling rat*
 or 0.00067  m >/mln  (0.03 ctm), whichever i* !*•, an
 unacceptable.
   The following leak-check Instructions for tbe sampling
 tiain described In APTD-0676 and APTD-OM1 may b*
 helpful. Start the pump with bypass valve fully open
 &nd coarse adjust  valve completely closed.  Partially
 open  the coarse adjust valve and slowly close th* bypau
 valve until the deeired vacuum Is reached. Do not revert*
 direction of bypas* valve; this will cause water to back"
 up Into tha filter bolder. If tbe desired  vacuum 1* ex-
 ceeded, either leak-check at this higher vacuum or tod
 the leak check as shown below and start over.
   When the leak-check Is completed, first slowly remov*
 tbe plug from tbe  inlet to the probe, filter holder, or
 cyclone (If applicable) and Immediately  turn off tb*
 vaccum pump. This prevents the water In tbe Implngen
 (rom  being forced backward Into the fitter hoMer and
 silica gel from being entrained backward into tb* third
 Impinger.      '
  4.1.4.2  Leak-Checks During Sampl* Run. If, during
 the sampling run, a component (e.g., filter asMmblr
 or Implnger) change become* necessary,  a leak an  isokln*ti*  sampling rMi
 (within 10 percent of tro* laoktaMtte nnl«*i ethenrtu
specified  bv  th* Administrator)  and a  tampantnr*
around tbe Blur of 1M±14* C (24a±2»' 7), or *Mh other.
 tamperaton a* tpecifbd by an apnUeabl* sobpart a! tin
standard* or approved by lb* Administrator.     •
  For e*oh run, record the daU required on a date ih*»
•nob a* tb* om* shown In Flgnn »-J. B* son to record tk*
 Initial dry gu metar reading.  Record tb* dry I** maW
 reading* at tb* beginning and and of each  •ampllng OM
 InermneDt, wben change* IB flow rat** ar* mad*. •*»•»
and «/*« *nh M cbttk, and wbaa twpJtftg • a****
                                                            vot,
                                                                    D-32

-------
                                                                    AND
                                                                                                                                                 41779
«vv,
        e        i tworaired by Mrare t-t at l*at* MM
 •leach *an>ple point dorlnf Moh ttm» tncniDwl  and
 TVTtton.i readlnp wbec atiTufloant ohacf e»  CX> percent
 wl>Uon In »»>oclty bead  nadinp)  oeoeaaltau addl-
 Znal adjustment! in How rale.  L»T»]  tod Mm  tb«
 Lvuomtter  Beoauae tht mtrtnmjiter laral and aero may
 ErTdii* to TlbreUoni and temperature cfeanfee, ntakt
 Zfftodlc obeoki durun Ux tnnm.
  Ol*u the mrttoeM prter to tb* tat rm to
tht obvno» of (uapiiof topotittd material Te  becto
BKDpttnf.  moon tb« DOCU* aac, Tirtty tint tb* flJur
•ad prom beatini rynecM art np to tampemnre. and
that th« plux CUM and probe in properly petitioned.
PoaiUon UM noaiLle »t th« am trarto*jjolul with the Up
Minting directly Into tb* |u ttfuuLi. Ijumediately start
MM pump tod adjust tb* flow to tooklnetk wndiuonj.
Namofraphj *n erauabU, which aid In tb* r»pld adjuil-
                                                     	   •< tfc* lant-ttiarki *»o>pUac ran wlUwm
                                                     Mnpc tattoo*. Than aotnofrapiu an  dadrowj tor o*e
                                                           UM TTP* I pi tot cob* eoeffioieoi u tJitOJE  and
                                                              fu •qaJTktau d*o»1t7 (dry motamiv «T^h;
                                                             to »±rt APTLM3f.?t d«Ulli  U» pnxwdon fcr
                                                           U» ncmu(nphi  I/ C, >od  U. tn  gouldr ihr
                                                                ^ rv>(« dc DM CM UM oocoofrkptij aa«w
                                                                Ran «•• C)t»Ucrc I Lo ttclloa  7) » tiieo
                                                                u far I
   K.MT	

   UCATW»___

   •KMTOR,	

   MTE	

   mm NO	

   IMPLEIOXNO..

   WTEK 10X10..
  tFACTOR_	

  KTOTTUIE COEFFICIENT, C.
                                                 KHEKATIC OF STACK CWSS MCTIO!<
                                            **OIEU8STH,B(J|J.	,	

                                            "HOZZLE If EKTIFICATIOT DO	

                                            AVERAGE CALIIRAHD »02Zll MAtKUR. I

                                            WOBE HEATER tFTTMe	

                                            IIAK RATE. nl/»*v4d»)	___

                                            WIOIE Ut»ER MATERIAL	

                                            iTATIC MEKURE, M Hi U*. H^	

                                            BLTER BO	
TUVWH rowr
.NUWU









,


TOTAL
(AMP1ING
TIME
l«1. Mlru













AVEKAGE
VACUUM
mmH«
«n.H^














(TACK
ra«Mnj«
Hji
•C(»F)














VH-ocin
HCAD
lAPfc).
•MCn.^HjO


-




fc






fKSSUK
WFnKNTIAL
ACKOSS
•CWIFICE
ffitTEB
— MlO
fta. MjOl














QA3 SAMPU
VOUAE
Wlfl'l














OAS tAxru •reurouTuw
AT t*T OAJ kCTTR
•Arc
•c en










,

A^-
CWTUT
•c i*n












A^.
Av». .
f K.TU HOLD«
TBraukTud.
•CI'FI














TtkTOATUM
' Of OAJ
UAVINO
CONOCNSf* 0*
LAST fcTIHOU.
•C(f I






.







  Wbm U» tUck b undfr df nUtoot nentlr« pracon
 Owl|bt of UnplDcv Hem), uk« eftre to don tb« antnt
 MJuit »mlT« btton kuertlnj the prob« Into Che §t»ck to
 pnnt mt«r (ram b»ckanj Into  tb«  Alter boldor. If
 •'••17, Uw pump m»7 be cam«3 an vitb tb* OOVM
 •dluit nlTt cloand
  Vtwn Uu probe It In position, tlocl oft tlx opeoln(>
 •nmd the prob«  and porthoM to  pttrant unrepre-
 MUtirc dJlutlon ol the CM !rtr»Arn
  TnnrwtbtiUck (Too-Mctloii, u required by Uotbod
 l*Hlptcll)«d by tbe AdmlnlltrtUiT, bcioj cmjVul not
 w blUDp ibe  prob* notiJe Into the rtAck wmlis when
 •oiplJni netr the w»Uj or when removing or limrUtu
 5* fn°t throu(b  the portbolM;  thii miT rw« fliuir »»emblr U LajtAUsd  conduct >  l«i-
••« tow 8«rUon 4 1 «J)  Tbe total paniculate  weight
«»u include tbf nimmmtlon of aU ftluf a«embl7 oatche«-
'  A «tnf le train »haU b« u»ex3 lor the anur* •anopl* run.
       Man wbtrr «lniiilt*D«oui ian3|>lki< U required
       mm •epar»l» ductj or at two or mor» 4ifl«rent
      i withiB tht iam« durt, or, In oaM« »b«r» tqulp-
•«ii dUur. DKMtltaio t chaise o/ tralru ID all oUx»
•"•Ooru, tb* UM of two or mor» trahu wlJ) b« mb>ect to
*** kpproral of IV
         Flgur*  6-2.  Particular field data.


  Note that wban two or mon train* are o»ed, aapartt*
ta^eJnxe of  the trout-half and (If applicable) Imptnfer
oatcbe* from each train ahAll be performed, unless identl-
flaj uo*rl* sliat were osed oc all trains, In which oaee, tb*
feral-half oalchei from  She  todlrldual train* m»y b*
combined (*< may tbe Imping*/ oaUihaa) and on* anal y^ls
atf front-half  '-ten  and on* analysis ol Implnier catch
may be periomed   ConroJt with the AAmlnljtrator for
detail] concern -\g tbe calculation of reculu wben nro or
more trains are ued
  At the end of (-be sample run, torn on tbe coane adjust
valve,  remoTt tbe probe and  nottlt troro the stack, turn
06 tbe pump, record tbe final dry ra» rostw nt-lini and
eondurt  a posi-teet leak-cbeck, at outlined In  Section
4.1 4 8  Al»o  leak-check  the  pilot lines at described In
Method 2, Section 8.1; the lin« must pan this teak-dwelt,
to order to validate the Taloclty bead data
  4.1.6  Calculation  of  Paroant  JjoMnetlc   Calculate
percent laokiasUc (see CalculiUoru. Section  6) to deter-
mine whether the  run ww  valid or Another test run
aiould be made  If  there ww difficulty Ln mainttlnlni
toofanetk rate* du* to aource conditions, consult  with
tbe Administrator Jar p«wibl< ™lanc* oo th« torAlntUc
nun
  4.2  Sample ReoorirT.  Proper  cleanup   proe*dore
beflnj  u aoon ti the prow Is remoTed from the stack at
tie end d the iarnpUnj period  AJlow the probe to cool.
  When tie probe  oac be saieJy handled, wipe ofl all
•rternal  nanlculait mstter neir tbe tip  ol the probe
Doc tie ana pLfcr* a cap over it to prevent lofllQc* or  ninl n^
partlculat* mattar.  Do not cap ofl tbe probe tip Ucbtly
while the aamplloi train iJ oooUn^ down M thlt would
on*u a racuum Ln the filter bolder, tiius drawlflj «r»t*r
from the Implnf erg Into the filur bolder
  Before  moTlni the aample train -.0 the cleanup tiu,
f«aoT» tbe  probt from tbe iampl* Sratn. wipe orS tbe
                                                                                                              (raate, aod ap th* op«n ootM o/the prob*. B«
                                                                                                            _ not to lo«e any ooodenale that mifbl be pnaent.
                                                                                                        'Ipe ofl tbe slllcone (reaae from thl filttr Inlet when tbe
                                                                                                       probe wat fastened and  oap  It.  Eamon tb* nmbllloal
                                                                                                       •crd from tbe last Lmplnffer and oap tb* bnpiofw. II a
                                                                                                       flexible line la oaed batvMc  tbt first Imxtlnfer or eorj-
                                                                                                       denaar and tb* filter boldar,  dijoorineoi  tb* UIM at the
                                                                                                       filter  balder  and M  aoy  eoodeaaed water or liquid
                                                                                                       drain Into the lmpin»T« or ooodenaer AJW wlplnf ofl
                                                                                                       tb* silicon* irreaae, -oap oC the filter bolder oatlat and
                                                                                                       fanpinfer Inlet  Klther  rnrand-claat  ttoppen, plastic
                                                                                                       •jap*, or aerum oap* may be oa*d to oloae  theae opaninf I
                                                                                                         TVaniler the probe and filler-lmplnrer aaaembly to the
                                                                                                       el*i.TUp area. Toil area  should be clean aod protected
                                                                                                       rom t£« wind K that the  chanoe* at oontamlnarlni or
                                                                                                       asdnx the aample will be  minimii*d
                                                                                                         BaT* a portion ol to*  aceten* aaed tor elaannp M  a
                                                                                                       biazik. Take 90C ml  of thii acetooe directly from tb* waab
                                                                                                       eottle belnf and and plaoe It  In a fje* Hzonet oootainv
                                                                                                       labeled "aouon* blank."
                                                                                                       sett any
                                                                         .
                                                              tht tralo prtor to and dnrinf fttamiTnbrr
                                                              fcteormal  eoodldou. Tnat UM aampl*
                                                                                                                                                     and
                                                                                                                                                       a*
                                                                                                         O*(*fafr Wt. f. O»r»ralry rwnor» the firur fr«n tb«
                                                                                                       filter bolder and plaoe tt In la IdeirclDad peul diab oon.
                                                                                                       talne:  Vtt a pair  o/ tww»«n and/or ci»rj  dlrpo*abl«
                                                                                                                     to handle It* filter. If It U
                                                                                                       RLT-jIca! jkiT* to  ane I*  ter.        oicui
                                                                                                       kJcf tbt filter, do to  inch  that th* parOcolan oate U
                                                                                                       la*de tbe lold. 0»ra(uUy trauifer to the pwtn di»b any
                                                                                                       paniculate matter andjor 41t*r fibtn wnJci adher* u>
                                                                                                       the fljtor holder  r&ike', .  by talni » dry nylon bn»tl*
                                                                                                       broib andjor » ihjtrp-«lred blads. 9«aJ Ut« oocUloar
                                                                                                         Cpmahu-r S't  t Ta£n«  oar» to •" that du* oo tk«
                                                                                                       eerulds of ttx prota or other erurtor  mrtao** doe* a
-------
                                                         RUU»AND  RMULATION*
 BttSna, press, faae, aed tan* ha* of tin att«r hoM* 1>y -
 wachtag t&tao uacpsotnM «U) agaten* and ptaamf tb*.
 wart la a (Ian «ont»tes». DistilM mrtw may b* and •
 insert at ta*ans vtxn aparomd by Ml* Admfcilatabv
 tad eaall b* osad when taKuM br the Administrator;
 m then oaam a»e a water blank tod toUow KM Admin-
 uuMor-i dnotioac oa a&alyah. Psrfona UM ae*yan»)-
 rto*M M MlevK   ,
  Carefully remoT* the pn&* naatle ted clean the Inalda
 «urffcte by riming with acetone fnna a wash bottle and
 bnulung with a nykiu brtsito  brush.  Brush until th*'
 .icMon* rtns.  showi no risible panlclea, after whlok
 make « And rln» of th* Inside surface with acetone.
  Brush and rtnas  th* Inside  partt  of th* Swaceloil
 fitting  with acetoM In »  simuoff way until no slsibl*
 particle* remain.
  RJru* tha probe Hrws with ftfrton*  by llltlnj tnd
 routing the probe while sqmrUnc antww lot* lu uptMt
 rnd »  that aQ (nsld* suttscua will be w«tted with ac«-
 tont. L«i th« ao«ioa« dr&la from tlM lover end Into tht.
 sampto conulnfr. A fuoarl (glaw ot polyethylene) may
 be used to aM ia traB*teTtn|| liquid wubei to th* «»-
 lolner.  Follow th« Metons HUM wltb a probe brush.
 Hold Ute prata In aa liyllnxl  pn«iii«i, sriuln aceton*
 tnto the upptf eitd at ib« pmb« brusb Ij being pushad
 uiib a  twlotaf aotiaa thrmi(k Uw pro*>»; bold t mmpM
 rontatuer undenmUi the  lower end of th* probe, aod
 riuelt  afiT nMens  end panteulM* matter which to
 brushed trora Uw probe.  Run  the bruah  tbrooth th*
 proba chrM tlraea or morq antfl ao visible parnculmt*
 uiMtef  b carried out  with the acetone or until noo»
 rFTDatm In the  probe  How oo rtsual  Inspection. Wltb
  at UM bout baU at tk*>
 Hur bolder by rubbing the stirfar*s with a nylon brlitl*
 bruah aod rmaing wiUi aMtoaa.  pinrt oach  luiiasa
 three Um« or mon If needed to remove visible partleo
 IM*.  laaku • ftn«J rln* «t Uw brut* and ftMw boMar.
 Carefully rinse out the glaai cyclone, also (if applh-ubbe).
 Atur all tfotoae —'•'•t' utd pvtieulM* mailer h**«-
 be*o collected la the sample container,  tighten the lid
OB tt»  tan^tt esntaiiiM •> that acetone will not leak
out whan it U shipped to the laboratory. Mark th*
n«i«at al UM fluid le*«J t* determine whether or Re*
 leakage occurred during cniuport, Label th* container
to clearly MaaUf* >
  Contatiuf Nt. I. Note tbe color af th* indicating stile*
gal w determim Hit ha* been eonpietery spent an«Tmab»
a notation of lu condition. Transfer the silica gel from
the fourth Imprnger t* iu critical container and seai.
A funnel may make It easier to pour the silira gel without
«pllllat. A rubber poUrana* m*r  be uaed at an aM In
removing tbe silica i«l from tb*  impinger.  It  to  not
iMteawry/1* reowT* U* mall amount •! duat partMea-
that may adhere to tbe impinger wall and are difficult
t* iMi^£V4. dine* the gws tn weight to to be toed for
moisture  calculations,  do  not UM any water  or other
liqmh •» livaala th* srt*r» get. U a balance » errailaMa-
ia the  field, follow the procedure for container" No. 3
in Bertlon * 8.
  Imptnfrr Wtla. Treat the impingen u follows: Mak*
a notation of any color or film In the liquid catch. Measura
tbe liquid which is in tbe first three imptngera to within
* 1  ml by using a graduated cylinder or by weighing It
to within *0.3 g by using a balance ' If one is available).
Record th* vorarn* or wricnt W liquid at mot. Tml»
inionnaclon i» requirvd t* rtZrnift* tha moutun oootwat
of the WTroent as.
  Dtjrard the liquid afarr  neamrlnf and reeordrnt ta*
v»Unn* or weiglit, oukni analyck of It* i
u required 
-------
                                                          *UUS  AND  tlGULATtOMS
   Alternatively, the aampJe may be oran dried at 106* O
  B«/ f) to J u> t noun cooled  to tb*  > ooMtant wal*b.t, anl**i otharwiae apeclAed
  wToe Administrator. Tb« tealer may alao opt  lo oven
  E, the aamplf el 106 ' COM' F) (w »to » boon, wat«b
  •>• aunplt. and oae thlt waif bt at t final w«l«bl.
   Ontika No I. Note tbe level ofllquld In tbe container
  •ideacflnn on the analytli aheet  whether or Dot haakiij
  picamd  durtnf transport.  U t  noticeable amoont  of
  r-t-f hw  occurred  either rold tb« (ample  or OK
  •jflhodi. anb)«ct to the approval of the Adminlstr»tor.
  to correct tb« flnaJ raaulu. Meajrure Uie liquid In this
,  •agtalDer  either volumetrleaDy  to ±1 ml  or jr»r1-
  •atrically to ±0.4 I  Tranifer the contents to  t tared
  •Jf>mJ beaker and evaporate to drynen at ambient
  afinparaiure and pressure.  Daalccate tor M bourt arid
  wel(b to t oondanl welf bt.  Report the ratulu u> the
  Marat 0.1 m|.
   CMatorr M>. J. Welfh the nwnt allloa fel for ilHoa • el
  aim Implnt er) to the nearMt 0.5 • ualnf l balance. TblJ
'•Up may b« conducted in tbe field.
   •Otoionj BUmt"  Qmiehwr. Mearare  acetone In thli
  aontalner  either  volumetrioally or  vravtmetrioally.
  franker the acetone to a tared SSO-ml beak or aad arap-
 arate to dryneai at ambient Umperature and prearore.
  Dailocate (or M boon and welch to a oontaant  w«l«ht
  Beport tbe result* to tbe nearest 0.1 m(.
   NOTE —At  the option of tbe tester,  tbe oonUntt  o*
  CooUlner No. 3 as well a» the acetone blanl  oontainer
  my be eraporated at temperaturee bt(her than ambi-
  aot. U eTaporatlon lj  done at an  aierated  temperature,
  the temperature must be below the boiling point of the
  Blrent, alao, to prerent "bumping,"  the evaporation
  prooen must be oloaely raperrlAed, and the oontents  of
  the beaker must be twirled oocaalonalty to maJntarn &n
  •Ten temperature. 0M extreme oare, afi acetone If bLfbly
  ftunmabb and hat a low flaah point.

  LChlfcrarkm
   y.Inf.In t laboratorr lot of an calibration!.
   6.1 Probe Noule. Probe oouloi aball bt callbratod
  More tbeir Initial oae In tbe field. Uaing a mlcroroct«r,
  Btuure the Inside diameter of the notile to tbe aoareflt
                                              (.OK mm (O.OD1 In. ). HI|I|-I ttirni rapiiratii inaamiirnimili
                                              ••lai dlflerent dlam*ten s*ch Uxne, and obtain tbe arer-
                                              •ceolthemMnirmmacU The diflerenoe twtweeo the hifb
                                              •Dd  low Dumben ahall not rroxiil 0.1  mm (O.OM Ic.).
                                              when ooulw twoome tUotwJ daeted, oc oorrodad. they
                                              at»li b« rathapod.  atavpeoad, and  rmllbruad  bafcn
                                              »•«.  Kach ooui* ihall b* ptnuMcUf and  oaiaotij
                                                       .
                                                U  Pilot Tub* Tin Typ* 8 pttot tnb« najimlli ihaH
                                              W oalibrated ajcoardiaf  tc  UM  prooadart *QlIiQ«d la
                                              •action t ol MeLhoO 3.
                                                a-S  MeUrtaj 8yttem  Be/or» lu (nitUJ OK ID tbe a«ld,
                                              tbe meterlnj iriUm aball b« caJIbrated according to the
                                              prooedure outlined In APTD-0578 Ln»t«a
                                              t*m. H  It aocfMted that a leak-check be  conducted
                                              For metering sy»t*m» harinf diaphragm pump«.  the
                                              ftormal l«ak-checll prooedure will not detect l«a^a(ea
                                              within Ibe pump. For  tbeae oaMe  tbe loUowinj l«ai -
                                              »b«tt proc*dore U satseated make a 10- minute calibra-
                                              tion mn al O.OOOS? m Vmin (a 02  CTJB), at the and of tbe
                                              ran, takp the difference of tbe measured wet  leal meter
                                              and dry t>? melxr yoiumei  dlrlde the diflerenoe by 10
                                              to eet tbe loak  rate The teak raU ahoald  not  aoo«6d
                                              0.00057 m 'Anin (0.02 oto).
                                                After each  field UK, the calibration of the m«terlnf
                                              vyvtein khall  b« checked br perlonnlnc three calibration
                                              roaft at a tingle, tntcrmeaiate orlfkie aettlnf  (baaed on
                                              tbe prerlouj  Qeld t«ct). wUb  th« Tacoum  aet  at tbe
                                              muJjiiuxil T&iue  roakcb«d durinf UM te*t  aw^«i.  To
                                              •jdjust tbt Tacaam, Inaert a  TalTe between the wet teat
                                              meter and tbe Inlet of tbe mtitertof tyitexn  Calculate
                                              ti>e aTera^e value of the oallbratlon factor  I/ tb* oallbra-
                                              tlon hw chanjKrd  by more than  t> percent  raoollbrate
                                              tbe meter over tbe roll mn£r of orlAoe aetOAfa, u ocrt-
                                              Un«d In APTD-0676.
                                                ARernatl re procedure, e.g . oalnjE the orifice meter
                                              ooeffidenu, may be oaed, aubject  to the approval ol the
                                              A dminl stra-tor .
         —If UK dry fti matar oraAatent nhxe oKaloed
  ••ore and afwr a t«»t aerlea dJSw »y more thic Jperceni
  tke Mat aerlai ahall eltber be voided, or oalculauonj Ir.i
  Oe ten aarlai ahalJ b* parlcnDed laloc whlcbeTer metrr
  •vafBdecl raiue 0 «..  Mm-r or afur; firm 1^4  tow,
  OhM of total ample rainm'
   »-4  Probe  Raau*  OailbnUoo   TU  probe  kwUrur
        atell b* a«llbr*t«l b^ore ru Initial oae in tb-
     I aooordlnf to the prmedort ootllned In APTD-Ot'e
     b« ooeutrootad aeoordlni to APTCMWI need nm
    aaJibrmud U tt» aallbtaUon ecrrai In  APTD-067*
  anond
   ».S  TaoptntDTe  Oxifea.  Cat  U»  praxdure  ID
  fiactloc CJ of Method I to oaHbrate In-tlack umperaturr
  ttaft Dial tbwTEcmieKn, neb ki an D*>d tor  the dry
  fu meter acd aoodeujer ootlet,  ahall  ba «atibraud
  ajmlofi maraory-ia-(lM) UkermomeUn.
   l.e  Leal Check of MeurLnc •yrtein Sbxrwo In Urun
  M. Thai portion of the aamfkjni  tralD from the pomp
  totbeorlnot meter ibooid  be Mak obeoked prior u> initial
  oae and after each ihjpmect  Lamkace after the pomp will
  ravult ki law rolume  balni raoorded Uian  U aeuiallr
  •kmpled  Tbe foUowlof  prooadore  If IDClened  i»r»
  Flfure H)  Cloae  the  main ralr«  oo Uu  m«Ur boi
  Imen a one-bole  rabtxr  r>opp«r  with robber tntHoj
 vOacbM] Into the orlfloe •* ha/1** plpa. Dtaooonect and
  want the bw aide ot tb* orlftoe manometer  Otoae ofl the
  low aide ortn£« t*p  Praarortu tbe fyn«n U> 11 to U cm
  (t to 7 m.) water  oolomn by blowtnf lnu> tbe rubber
 tabinj Pinch oB the mbinf and  otMrre the manomeler
 to on' mloaU  A koai  of praajon on th*  nuuiometar
 tedioaUi a UaJt In tb« BUMr  box, taakj, U praaant, molt
 •a oorrected
   a.7  B«romeUr  Oatfbrate  •falost a nvoary  bvrom-
   Carry ocl oakailaaoTU.  retaining at Uajrt one artra
 •aTHlmil Ofnre berood that cf the aoqolrad dala  Round
 •B flfurea afler the final oairuiMJcm Other tornu of the
 •quatloai may b« oaad u  kxif u they plv* aqulralftot
 fwulu.                                     *
                     ftUIBER
                     TUBING
                                      RUBBER
                                      ITOWER
                                                   ORIFICE
                                                                                                               VACUUM
                                                                                                                SAUCE  '
   •LOW INTO TUBING
   VNTIL MANOMETER
 HEADS 6 TO 7 INCHES
     WATER COLUMN
                                 ORIFICE
                              MANOMETER
                                                      Figure 5-4.   Leak check  of meter box.
  11
  i:
  c.
Nomendatnre                        '
  — Croaa-aecuooal araa of ooctlt, m' (ftri
  • Water vapor In tb* pa atraam. proportion
   l>7 vohiine,
  —Aoatone blaok raaldoe coooauSPMiBta.
  • Ooooentration of paniculate mattar In
   f M, dry basu, corrected to otandjtrd eoodi-
   tionj, |M*cm (k/dtcf).
  • Percent of laokloetle ««TTipiint
  •Mai Imtim acceptable Icalace ntt tor aithar a
      Stan k*k check or lor a Wk ebaok loUow-
       a aomponent ebanfe, aqual M 0^0067
      mln (0.02 dm) or 4peroent at DM »vw»f»
           rate, whitbeVar It law.
                                                     V.
                                                     V. .
L,    • Indfvlduaf l«aka|e rate obaervad dnrtnc tb»
        aaak  check conducted prior to tb*   I1*"
        •omponent ofaavoc*  (1-1,  J,  1 .	*>),
        aoVmin (cfm).
I*    ^LaaltafT rate obaernd «urlnj tk*
        taak check, m'/min (etm).
•.    •Total amount of pankulau mattar
        tog
*V.   -Moiecnlar  «tant »f War, If4>
        fU.Olb/lb-mole).
••    •Uaa» of raaidu* of ac*ton» altar *v»poratkin,

A«  •Barom*trk traamrt at tb* ««rnpH»;  «    •Ab*olni»«»ci r»> pnaaare.Kin H« fln_ Hil.
fmt  •Bundard  ab«olou  riraHinun. KO »*^ £4
        0*^310. EX).
                                                          .
                                                         r
                                                        AH
   	1 rts ex«»tant, 8.0S2W mm '
   raote (21-&5 In Hj-hTR-lb-mole)
 «Ab«olut« avrj~af« dry rat matar tazaparatar*
   -fsee Firore S-2), 'K CK).
 >  VU.jlul* avarafe ttkck ga* aKsparWora (aw

 •gULDuird  kbwrat*  ttmparatnre,  aW  E
   J&28° K).
 v>volume of aoaiooe blad, ml
 •Volume of acetone tued in wash, ml.
K« Total volume of liquid coUaetad lo Impinctn
   •od tillcft |el CRae Flffure fr-8), SO
.- Volume of (M ample M mMKirwl by *7 pJ
   B«t«r, dcm (dcf)
t) ^Voiums &' fM ^mpld m4fit^aj by toe dry
  eat £D«t«r, comctad  to AandArd oocditlotu,
  ^cm (d*c/r
1-Volume of niee v»p«f to ti» S*> tta'f^
  ^eirrwted to standard co&dlliocii, acm UKJ)
',*>§t9cJi jw valoclry oJculaud by Method S,
  SquauoD  ^-6,  oainf daXa  gHmtrrH  from
  Method  S,  m>K  (fl&ec)
  • Weight  of rwidoe In aoaunc vxii, mg.
  •Dry gw meter calibration a%ctot.
  • A?ar»«e pre»jur» dlflcnuttai acro« tb« orlfloa
  5Mt«r (a&i  Drura 4-»), mm  HrO On. H«O)
        i— tampUnc ttme mtanrtl, Irom tbe baflnnlnf
          tt a run Kntil tb* ftrat nr«nrior>ant-at«j §00
          oaflalva oocipoDent obac4*%f, I»ag1 nTilrn with
          to* mtkrral barwaan to* fint  and aaoocd
      •,-Bamplim dm* mtarraX trom tb* final («u!
          •amptmant ebanre  until tb* and  */ tb*
          ammpUnf TUTL, xnin
     H.6-Bpecinc tranty a/ marom-y
      •0-Bec/mln
      WJ-Convwilori to parcent
  «J  l.mce dry (U m*t«r Umparaturt and avmtr
arliot praavum drop Bae data lhaet 'Tifum 6-ii
  U  Dry  OM Vokoo*  Correct uw aample vorom*
• ijtiiin 1 by the dry raj matar to atandard ooodlUonj
       WO mm B| «r  «T F, •  B In. E|) by  uainf
                                                                                                                        r
                                                                                                                  r.w\
                                                                                                                  -yr- H
                                                            bottle)
                                                            Ib/nJ)
                                                          *~ TooJ •°"r*Hf ttma, wtiri
                                                                                                                                    p
                                                                                                                                ^.+ C Ag/13 6)
                                                                                                                                      r.
                                     •*»«SAI
                                                     VOL  «, wo
                                                                                           , Aiwun  i*, i»rr
                                                                   D-

-------
4178*
                                RUUS  AM* REGULATION*
  _     H'KtesHgiormiMgimrst
    ™> I7.fte * &jm. Hg far ffngtlnh cmtti

  Wwi»—K II
" r «• 4, runes A* Equation *-l mutt b* modified M

         _  X*  WO OMBpOMtn CTtCRfM ITTftCH oWTISff
        urn, la Uttt CMS, raplao* V. In Equation M
                          (a)
                                                                          stack ga> th*" b* mada* on* from tb* tmpmger analyilf
                                                                          (BonaooB »-31,  and a second (ma th* assumption «f
                                                                          aatonud condition*.  Tb* lower «*a»S" »***•» *
                                                                          fl_ .K.U t,« oonsldarwl oorrwt. Th* prooedur* to det*»>
                                                                          minmc th* molstur* content baaed upon assumption of
                                                                          i*tajat«d oondlttons Is fjTen In th* Not* at Section U
                                                                          (rf Method 4. F« th* porpo.«t^ thJ* metood,t^ aT*raf»
                                                                          stack m temDeratur* from Flguta VJ may b* oaaa i*j
                                                                          maka thii^etermlnaUon, proridad that tha accnne* at
                                                                          ^^.^ ^^ _«..„	H J/»WT.«—» .« j-tit^ m\
                                                                          th* Irntack tfflnperaturs asnsor I* * I* C W FV
                                                                            6.*  Acetone Blank Co
  (b) Caa» n, OBB «r man eompoaarit
durtng  tb* aunplljig nxn. In this ~"tr. replac* K(
XojtMka 4-1 by th« aipresstow
                                                                                                              KqatUenS-t
                                                                                          r.-c.v..^.
                                                                            M  Total  ParttenlBt* Wtdglit.	   ^^_i
                                                                                       b Cram tb* ram of UM weight* obtain**!
                                                                                   	1 and 3 las* the acetone blank «.mm atfrt te DMtrtc aoite
                             -0.04707 Wml tar Ea(Uab u
                          «J MiiAstaso Comiet
                                                                            e.u.1  Calculation 7rom_Ba* Datsv.

                                                    100r.[JT.y,.-KVJ7'.)i
  Jd-4.0D3tM mm Bg-nVml-'K lor metric antta,
    -O.OCa6«* In. Hg-rV/rnl-'R far Bngllah unrt»
  4.11-J  CalcnltHos rrora Intaonai"
                                                                            «. Voltero, R. F. A Bantj at Commarcl^ ArailaU*
                                                                          IiutnDn«aUtlon For tie Meunnm«at o( Low-EU^»
                                                                          OM Vsloeitie*. U.S. EnTironmenUl Protection Agency,
                                                                          Emlartoa  MccoonnMUt  Branch.  R«m«reh  Trianu
                                                                          Puk, N.C. Norembar. 1978 (uopobUitMd ptptr).
                                                                            9. Anntul Book of A8TM Stiuidvds. Put 26. OMMB»
                                                                          Fuel*; Coal ud Cok*; Atmoipberla AnalTtl*. Amerlc*a
                                                                          Society for T«tm« «n4  Matvulft. f blUd*lpki% F*v
                                                                          JW4. pp. 917-W3.

                                                                          METBOB  «— DcmuciHATioit  or  Spircm   DIOXIDI
                                                                                 £Hiano«* FBOH  BTATIO.XJLAT Sovuru
                                                            Eqoatim 1-4   L Ptintflt tmd
                         vhertc
                          K,-«.X» for mrtrie unite
                             «O.OMoO lor Eliwluti ootts.
                          113  AoxpUbl* fi«nIM. II M permit  e Ud Annual Mwtlnj of the Air PoBn,
                         tioa Cantni Anodatloo,  St.  Loula, Uo. Jen*
                         1JTO.
                          t. Smith, W. 0 et aL Stack Oa> SampUnj
                         and Blmpdnad Wrib N*v  Eqolpmwt. APCA Papar
                         No. «7-H9.1«7.
                          *, apeclflcatka kr Indnenttr Tafttnc at Fedanl
                         Pactbtle*. PHfl, NCAPO. !««.
                          7. Sbliebara. B. T. A^ttutmanti In th« EPA Norao
                         rreob lor Dlfferont Pilot  Tub* CoeOeinti and Dn
                         Wnmte  Weight*. Stack SampBm  Nen t:4-lL
                         Oetcbs, 1«4,                                ' •
                                                   1.1  Principle,  A rat anrph 13 eitracted from th*
                                                 aampilnf point In  toe slack.  To* imUuh* aoid mlat
                                                 iincludraj oolfar Lnoikie) and th* mlfor  dlotrde an
                                                 Mparated. Th* nilror dloxid* traction I* measured by
                                                 the bariam-thortn dtradoa method.
                                                   1.9  Applicability. Tbla method ll applicable for tb*
                                                 determination of sulfur dioxide *Tni«»ian« from stationary
                                                 source*. Tbe minimum detectable limit at tbe method
                                                 has been determined to b« 3.4 milligrame (mg) of SOt/m*
                                                 (2.12X10-1 ib/tt'). Althoufb no upper limit bai been
                                                 Mtablished,  test* have shown  that concentration* a*
                                                 h%a aa 80,000 mg/B' at SOi  can be collected efficiently
                                                 in tvo midget Lmplncera, each containing 15 miloliten
                                                 of 3 percent  hydrogen peroxide, at a rata of 1.0 Ipm for
                                                 20 mlnntM. Based on theoretical calculations, tb« nppar
                                                 concentration limit in a 20-liter sample \t about 93,300
                                                   Pcoslbl* Intarfennta are free «TnTnnni»
                                                  cailona, and  fluorides. Tbe cations ana fluoride*
                                                  reauxrea b; |U*a wool niters and an laopropanol bubblac.
                                                  and Denoe do not affect tbe 3Oi analysli. when nmtU
                                                  an being taken (rom a gas stream with blgh concentnr
                                                  tiona of very flu* metaiilo fumes  (such at  In Inlet* (•
                                                  control detlce*), a high-elBcieocy glut fiber nltat mat
                                                  be used m plaoa oi tbe glas* wool plug U.*., tb* on* tm
                                                  the probe) to remore the cation inlerlenuU.
                                                   Free ammonia Interfen* by reacting with  8Oi to  fora
                                                  partlculaU nilnta and by reacting with th* Indicator.
                                                  If free «jnmnnt% is  preaent (thl* oan b* determined by
                                                  knowledge at tbe procea* and "^'"'"g white parckul»t»
                                                  matui In tbe probe and laopropanol bnbbler), altaro*>
                                                  UTC mathoda, subjert to the tpfntal of UM  Adramiattfe
                                                  t«,   DJ.  EnTirwimtntal   Protection  Agency,  art
                                                  rattolrtd.
                      uouia.  VOL 43.  MO. i*«— THUISOAJ,

                                            D-36
                                                                                                    it, 1*17

-------
                                                         tUUS  AND REGULATIONS
                                                                                                                                          41783
                                                                                                                   THERMOMETER
           (END PACKED
     WITH QUARTZ Oft
       fVREXVOOL)
                                                                                                                                 •ILICA QEL

                                                                                                                                OftYING TUBE
                                             Figure 6-1.  BC>2 sampling  train.
                                                                                                 •WIGETANK
   11
         component
  tetter hai the option  of wnDititQtlnf eampllnf equip-
  ment deecrlbed In Method 8 ID place o( the mldfrt 1m-
  Mniw equipment of Method ft. Howvrer, the Method I
.  hilDnumbeittxlined to Inelixta a heeWttlter between
  tM probe and laopropanol impintw, sad the operation
 4 ue aunpUnt train and aunpie analytic man be  at
  Ite flow ratee and eolation Totamee defined In Method t.
   Tbt tarter alao ha«  the option of determining SO,
                                                 •mple and to protect the mater and pomp. B the afliac
                                                   ' '    '       '    '   ily, dry aUTS* C (WO" P) tor
                                                                       r be need at reoelred- Aiterna-
                                                  fal hai baan oaed prertooaly, dry at.
              with partlctiJale matter ud
 AatarmlnaUoni by (1) nplactnf the water In a Method 4
 toplnro lyitem with I percent partoiide eotaUon,  er
 2L"? &***!>* .th« H*** » «w« taptafw
 with i Method I taopranaol-aiUr-fMraliie intern. The
 MtMi lor BO, mvt U MraMiril with the proedm

   ll.l trH rnrn»Hln«ti fha in ilelnlea rtnl (rfiw
 ••Mali of eonftracUon m*r be wed, *ab)eet to the
 JPWuTil of the Admlnlitntor), •pproxlmuelT »-mm
 Mlde diameter, with > he»ttn« fjitem to prarent w»ter
 •ODdetmUon ind » (UUr (eltber ln- • mSt*Ktorr fllMr.
   iU Bobbler ud toptncwl. One nddfet bobbter,
 Ttlb medhuD«o>ne |ku§ bit u>d boroillloMe er quvu
 •»• wool packed to top dee Flfure  »-l) to  pr»Tem
 MUuric teld  mlit evrrorer,  tnd three W-ml mldnt
 •ViDfcn. The bubbler tad mJdjrt Inplnf en mult be
 WD&Kled In nrlei with talk-tree (tes  oonnecton. 8111-
 *•• Dwut mey be need. If neeetmry, to prrtcnt leiJun.
   At the option of the te*tar, e mldj et Imptofv BUT be
 4M to {0*oe of the mldtet bubbler.
   Othw ooUKttoD tbeorben ud flow rate* m»T be and,
 Mt in labrKt to the tppnrnl of the Admintotrmtor.
 *»», «BD»rttan •fflclmcr man be ihown to be el le*tt
        "     *  "  "
«•»! aouaraoD emcMncy mun
Jl Pana t tor each tert run and :
••report. If the efficiency li fauj
• Mai of three  U*U, rortber
                      li lound to be caoetiUble kfler
          ---- ,   rtber docmnmuilon li not
        To eondart the affldencT tot, in ertn eb-
      B penent.
«allbratad  at the aalerml *ff* rate  and eaadldooi
•ctoallr anooontered dnrtnt  irmir^'T  and equipped
wttb a tamparaton faafe (dial thermomater, or eqolv
•lant)  aajpable of XHaanxinff  tanpanfcore to within

  U.ll  Barametar. Maroury,  aaerold, or other barom-
•av eapeble of meajnrtflj atmoaphvlc prearon to within
11 mm H: (01 In H«). In nacy oa»»». th« barometric
leeillni m»7 be obtained from e nearby national weather
awrrloe »ltUin, In which oan the nation Tatae (which
b the abaoku baromealc pneKire)  I hill be reqnected
god  an adjutment far tteratlaii dUlarenca between
(be weather (taUoo and aunpllrv point anall b* appUed
at«raUafmlna»J-5mm HJ (0.1 In. Hi) par atlm 000ft)
•Jarmdcm Uineaai or vtee raraa far ebratloii decreaac.
  S I 13 Vacuum Oaoje  At lead TtB mm B«  (M In.
Hi) (ai«e, to be oaad  tor laak eback af Ue aunpUnf


  & V^SS^P-y-tryi- m *-. ~ ml.

*\°U Monet BoMet. Peiyethylana, MO a»L w. awn
       r aunpiee (ooa per aunpie).
                                                                                                  apeclnoatJou  DllM-74.  Tn» t. At the aptton af the
                                                                                                  •awlrtt. the EMnO, teat far artlliaMe ortack Batter
                                                                                                  «UT be amttud wben  hkh eooatanOoa af arfauk
                                                                                                  ••net are not arrnrud  to be preaent.
                                                                                                    U 3 laopropaiwl. K paraenl hUi H ml af kvpra-wol
                                                                                                  with Kmlofoetoniied dlettUed wmter. Check eaehlotor
                                                                                                  •opropanol far peraide to perl On a* fallowi. ab«ke 10
                                                                                                  •1  of laopropanol  with 10 ml of kwihly  prepared 10
                                                                                                  •araent poleannm todldi aotatioo  Prepare a blank by
                                                                                                  ateiUarlr tnaOoi 10 ml of dlrtlltad erater. After ImliaU,
                                                                                                  read the  aheorbaoce al IU naaom*4en on a  (paetro-
                                                                                                  photometer. If abecrbanee awaadt  OO. rejeoj alnohol tar
                                                                                                  w*>
                                                                                                              ay be iwmnwl wen  laruwnramfii by Mdto-
                                                                                                         or by  tuawer ttoraub a eohzmn  of aetintad
                                                                                                        »;  howmr.  natant  fnde  kopropanol  with
                                                                                                  avlubly low prroddt levab may be obtaJDed fnm eom-
                                                                                                  •erctal aoanee  Rejection of —
                                                                                                                                         Ma nmy,
                                                                                                  Ibanfan, bt a more efficient nrooednre.
                                                                                                    I.1J  B>dror» Panolde, I Panant. DUntaKnanaBt
                                                                                                                                          afitlUed
                             don.
         	      	jant-I	
	   peroilde l:t  (T^) with datonlied, ,	
water 90 ml li rwed«d per aampie). Prnan fnah daily.
  <,!.« PotaMtam Iodide BoloUon, 10 Pareant. DlaanlTe
10.0 frami El In *»fa-»i«»«i. distilled water and dthUe to
HO ml Prepare whan needed
  (.1  iampk Baeorery
 1.11 Water Dfioolaed, OattUad. at u 11.1.
  I.S.I laopropanol. 10 Pareant Mil at)ml efk
with » ml of faitnii^ «etiu^ «u>
                                                                                                    U.I  Waur. DeionhMd. 4MUM. •
                                                                                                    aVIJ  laopropanol. KB pareant.
       QlH* Wool BoratftaiU or qn«rt»
•fblecQloime (reaae may be oa*d. V
.  IU Temperature  OWfe. Dial  	
     •tnt, to maaiure Umparatore ef ne laartat t»-
     traln to within 1 • C CT P.)
             Tube. Tube packed with «• ta llaiarh
             alUea (al, at aqnlTalem, *a dry tka (*•
     i  Borattai. b- aad »>ml alaai.
     I  Krlenmeyw rauki. MO BKalaa Una tor aaefe
     * blank, and atandard).                .,
       Dropplnf Bottle. 116-mJ aUe, to add tamewtar.
  «jj  Oriduaud Cylmdar. 100-ml ifte.  _____
  11.7  jpeorophntnmalar. To aaiHiii ab«*b«u«» at
                                                                                                    «_14 •errom ParofeloraJe tatottoc. *xm«  N  Dbr
                                                                                                     _                             .
                                                                                                  jotre l.tSjof barium eerehlonu trthrdraU [»«(CIO«h
                                                                                                  •BiO] In fco ml dKdUad water and dilute to 1 bur with
                                                                                                  .•opropaool  Alteradnly
                                                                                                         aool  Alteradnly. 1 J3 | af [BaCb-lHiOl auy
                                                                                                          Inatearf of Ue parahknte. wainrWlai « to
                                                         VOL 41, MO. t«C—VNMSOAT, AUHKT II,


                                                                  D-37

-------
  41784
                                                           RULES AND  RfOULATIONS
  1A8 JhUftsria Add Standard, O.OM9 N. Parent* or
rtuutonflai to <*KJ.OOOJ N agslnS 0.0108 N NeOH which
   ^ PraTlOT5?l?  bwn stftnderdljed  against  pntmrimn
  4.1  SempUsg.
  UJPnparitJoa of enflertSeu train. Meaton U ml of
» pereaat tiopropanol Into UM midget bubbler tod U
ml at * psreent hydrofeB peroxid* Into each o( to* flnl
y» midget Impinges. Lean UM final midget Implnger
dry.  Asetmble UM train u ihown In Finn 9-1. Adjust
prob« heater to a temperature sufficient To prevent water
conduuuka. Flam crusted la and water around  tat
Impugns,
  4. IS  Leak-ebKk pRncdta*. A Ink ctxrk prte to tta
ssmpU&s ran Is optional; bowsvw. a leek chock after tat
sampling ran U mandatory. To* laak-efeeck procedure I*
fe) tolIOWK
  With th* DroC» dtaeonnacted. plaa t veeasm t»u«e a*
tb» Inlet to the bubbler and pull > vacuum of HO mm
(10 In.) Hr pluf or pinch off to* outlet of to* flow meter,
and then torn off the pump. Th* vacuum shall remaia
stable lot  at leatt 36  seconds.  Carefully release  to*
vacuum gaoge babre relMstng UM do* m*ttr end to
prevent bark flow of the implnger Hold.
  Other laak cb«cte  procedures may b» used,  subject to
tits approval at UM  Adnunijtratar, U B. Environment*!
ProtactloB Agency. The proosdur* QMd In H*Unxl  5 t*
oat suitable fi» dl&phr^m pump*.
  4.1.J  Sample  collection.  Record  the Initial dry  gsfl
m«*ef reeding and  barometric praam. To begin ma-
plint, podtloo ta«Upofth«prob«atth«a«mpUnt point,
oonneci U» prob* to UM bubbiw, and start to* pump.
Adjust th«  «%mpl« Sow  to 8  constant ret* of  ap-
proiimat«ly 10 ut«r/raln as Indicated by UM roUractar.
Malnteln thto oonitaat  ml* (*10 percent) dnrtnf  UM
enUn nmpllna ran. Take reading (dry f*t metar.
tamptrature* «i dry ipw meUf and at Implnnr outM
and rets maUr)  at V«k «wy 9 mlnat**. Add mora to*
during UM ran  to  kmp UM taDptntun  of  UM ia*M
Issrlnf UM lut Implnfor at 30" C («• F) or l«x. Attte
conclusion of «£h run, turn off UM pump, ramor* prob*
trom UM staek, tnd reoord tbt final nttdlnfi. Conduct *
le*k chark ta In Soctkm 4.1.1 (Thl> U»k chwk U manda-
tory.) U a Iwfe U ferand. Told tba t»t ran. Drain th« lea
fafttb, and puin UM rnnmining part of UM train by drap-
ing cWc unbWt ate through to* ryston lor U minnt» '
at to* wmpllnt rate.
  Cl«an ambtaet air c*a b» prerldad by pualnt air
thraoga a charcoal altar or Uuomh an extra  midget
Implngv with U ml of t parctnt  HiOt. Th« t»t«r m*r
opt to itmpty u» ambtcnt 4r, wlthont purtOcatloii.
  4JS  Svnplc RaaoTwy. Dlaoonnwt the Imptngan afUr
purging. DtaanS th* oratenti at UM mldftt bubbur. Poor
UM content! of  UM mldgvt  Implnran Into a laak^ra*
poljcthylan* bctU» for shTpm&nt. Buu* the thrae mldgc*
          &nd to* oomuctlns toixe with  •1filirnltT\
  (Now.-Pratart  UM  0.01W N
                                       peraalon$B
toOewK pern t naam geoge it the Ink* to UM drytnf
tub* and pan a vacuum ofz» aim (10 In.) Hg; plug or
pinch oS the outlet or toe How meter, and thai torn OB
UM pomp. The vacuum shall remain table for at least
         . Carefullr relaaa* the vacuum gauge beta*
nleaitng the flow meter end.
  Next, calibrate the metering fyftam (at the avnnllnf
flow rate specified by the method) at follow* conneo*
an appropriately dud wet Uet  meter («-f.,  1 liter par
rerolutlon) to the Inlet of th* drying tub*. Make three
Independent calibration runs, oilng at leeat AT* rerote-
tloni of the dry tat meter per run. Calculate the calibra-
tion factor, Y (wet tan meter calibration roluma dlTided
by the dry rai meter Tolome, both Totumee adjnited te>
the same reference temperature and procure), lor eeom
ran, and average the renlta. If any r vaha* deTleue by
more  than 3 percent from the  arerag*, the meterlal
ryMem lJ unacotpubw for us*. Otherwue, OM the arer-
ag* u th* callbraUon outor tor sutmqoent  Utt ran*.
  5.1J Poet-Test Calibration Cheek. After  each field
teet tariea, conduct e calibration check a* In Section 5.1.1
above, except for the foUowtnf variation*: (a) the leak
check If not to be conducted, (D) three, or more revomv
tionj of th* dry gai meter may b* used, and (c) onlr two
Independent rune need be mad*. If the calibration factor
doe* not deviate by  more than I percent trom the Initial
calibration factor (determined In Section 5.1.1), then the
dry gat metar volume* obtained daring the  Urt aerial
an acceptable. If the calibration factor deviate* by nun
than 9 percent, recalibrate the metering system a* la
Section i.1.1, and for the calculation*, us* the calibration
factor (initial or recallbntlon) that yield* the lower gatt
volume for each test ran.
  3J  Thermometers. Calibrate agajnat  merenry-iB-
glaao thermometer!.
  J.J  Rotameter. The rotameter need not be calibrated
bat should be cleaned and maintained according to tte
manumctnnr'i Instruction.
  5.4  Barometer. Calibrate againat t mercury befw*-
•tar.
  54  Barlma  Perenfente Sohrtoo. 8tandardl*a Us*
barium perchlorat* solution acalnit » ml o< standard
snlfurlo add to which 100 ml of 100 panent Uopropanal
ha* been added.
dlitillad water, and add UM wadilEn ta tb« lam* nora*
container. Mart tt» floM tsnL M and Identify th*
(ample oontxlaar.
  4-»  3cmptoAnatyd(.Not«lmlo(UcmldlnoontafaiaTf
and eonflrm wbather any aample wat not during shto>-
meat: oot* thla oa analytkai data tbeet. If a notlcaeMa
smcaat of leakage hn oocurmt, elUMr void UM aampto
or me methods, rabjaet to UM tpymval el UM Admlnk*'
troisr, to correct the 9na4 molts.
  Tnisgbg the contenta at UM ftorage  eontatoer  to •
100-ml  TolomeGrlc ftMk and  dltat» to exactly 100 ml
wlta detonlxed, dl*ttUed water. Pipette a 20-ml aliquot at
thU KptattoB Into a 240- ml BrtenmeTer flaik, add SO ml
of 100 percent laapropanol and two to toni dropa of tborta
Indicator, and titrate u> e pink endpolnt cuing 0 0100 N
barmm perchJarstB. Rep«et and arerage  the tltratloa
Tohmua-  Ron a blank with each atrlei of aunple*. Reptl-
case  OtrattoiB most »grsa wlUmi 1 percent or 0 J mi,
wfekherar It tergw.
                                                       d-d. MM 'Vmm Hg tor sMrte unto.
                                                          - I7.S4 • R/ln. Hg tor BngUsa unlta,
                                                       «J  Sulfur dtaddeooooantmfc.0.
                                                       JTi-B-Oi mg/mea. tor metrto anttB.
                                                         -7.M1X10-* Ib^neq. tor Kngtbh nnttm>
  Carry ont ralmilationa, retaining at lea*t one extra
decimal figure beyond that of the acquired data. Round
off figures after final cekinlasion.
  8.1  Nomenelatxir*.

    C--Concentration cf sulfur dtoilrta,  dry  Das**
          corrected to stsfldard OQSMlitlonB, mg/daem
       .   (Ib/dsef).
      .V-Normality of  barium  perchlorate tltrant,
          mllllequivalentj/ml.
    J\w— Barometric pressure at th* exit orifte* cf the
          dry ca* meter, mm Hg (In. Hg).
    J>,u-8tandard  abeotnte [imamr*. 7*1  mm H|
          (3.93 In. Hg).
     T.- Average dry gas meter abaesot* tempemtara,

    rM-Standard  abeotate  temperature,  JBsJ*  K
          (52*' E).
      V.-Voloroe of sample aBqoot Utrated. mL
     V.-Dry ga* rohnne u meaanred by the dry ga*
          meter, dcm (def).
  f»GM)-Dry ga* vorum* measured  by the dry fa*
          meter,  corrected to standard  conditions,
          dsem (dscf).
    V^,-Total volume o( solution In which the sulfnr
          dioxide sample U contained, 100 ml
      Vi-Volum* of barium perchlorat* titrant and
          for  the samps*, ml (average  of replloata
          tltrationa).
     V,.-Volume of barium perehlonte Utiant used
          for th* blank, mL
       Y- Dry (a* meter calibration factor.
    H.BJ- Equivalent weight of sulfur dkaddk
  «J  Dry sample ga* voUnao, oometed  U standard
CODdltlOCS).
                                                     T.

                                                       t. Atmo*pherta emission* from Snlfurie Add Msjia
                                                     (actnrlng Proeeeaai. U.S. DHBW, PH8, DlvUlon of Ahr
                                                     PoUntlon.  Publle Health  Service  PubUcatlem  Na\
                                                     wa-AP-U. Cincinnati, Ohio. llMt.
                                                       J. Corbett. P. T. Th* Determination of 8Oi and BO,
                                                     In Fin* Oaeea. /oomal of the Inatltnte of ItuL «*V JW-
                                                     2tt, 1M1.
                                                       3. Mattr. B. B. and B. C. DlefaJL Meanrlng rtne-Oa*
                                                     BOi and SOv Power.  101: M-9T. Novwmber 1C67.
                                                       4. Patton, W. r. and J. A. Brink, Jr. New Equipment
                                                     and Technique* tor Sampling Chemical Proeeai Oaass.
                                                     I. Air Pollution Control Asaoeiatlon. 15.- 182. let*.
                                                       5. Rom, ]. 1. Maintenance. Calibration, and OperaOoa
                                                     of Uosdnetie Souree-SampUng Equipment. Offle* of
                                                     Air  Program*,  Environmental  Protection  Ageneyv
                                                     Reaterch Tiiangl* Park, N.C. APTD-OfTS. March \m.
                                                       4. Hamil, H.  r. and D. B.  Cemann.  Collaborative
                                                     Study of Method for the Determination of Sulfur Dioxlda
                                                     Emlaxtoni trom Stationary Source* ( FoaaU-Puel Fired
                                                     Steejn Oeneraton). Bnvlronmental Protection AI
                                                     Reeearen   Triangle  Park;  N.C.  EPA-WV4-;
                                                     December 197SL
                                                       7. Annual Book of A8T1I Standard*. Part n;  Water.
                                                     Atmospheric Analyda.  American Society lor  Testing
                                                     and "•*— <•"« PMi^.iph'-, Pa. 1974. pp. 40-tt
                                                       8. Knoll, /. B. and II. R. Mldgett. The Application of
                                                     EPA Method • to High Sulfur Dioxide Concentration*.
                                                     Environmental Protection Agency. R^eeanb Triangle
                                                     Park. N.C. KPA-«00/4-7»-Oa>. July an.

                                                     afsrano  7— Dnrucounow  or  NrnoosOf  OnDss
                                                            Btcaesoir* FBOM 8TAOOir&BT Sotrmcisi
                                                     1.1  Prlndpla. A grab aunple Is collected In an e
                                                   ated flaak containing a dilute  mlfurte add-hydrogem
                                                   peroxide abeorblng soluUoa, and  the nitrogen oxlaea.
                                                   except  nitron* oxide,  are measured eolorimeterlcatty
                                                   ojing the pliflnnMlsnlfrirfllo add (PD8) procedure.
                                                     1 J  Applicability. This method I* appllcabU to the
                                                   measurement of nitrogen oxide* emitted from stationary
                                                   source*. Th* range of the method ha* been determined
                                                   to be 1 to tfO mllllgrain* NO. (a* NOi) per dry standard
                                                   cable meter, without having to dilute the sampav
                                                    ri  HsuBplrng (at* figure 7-1). Other grab sampUaf
                                                   system* or  equipment, capable of measuring samps*
                                                   volume to within ±2.0 percent and collecting a inlHiliait
                                                   sampl* volume  to allow analytical reprodadbUrt* to
                                                   within ±6 percent, will be considered acceptable altar-
                                                   native*, subject to approval at UM Administrator, U J.
                                                   Environmental  Protection  Ageney.  The  following
                                                   eqoipment 1* naed In ••Tip^r'y
                                                    11.1  Probe. BoroaUlcete glassi tnbUsg,  snnVtentry
                                                   heated to prevent water condensation and  eqalppaa
                                                   with an uvctaek or ooVeteek filter to remove partlcuiBt*
                                                   matter (a plug  of glees wool la  satisfactory tor  thai
                                                   pnrposa). SUlnlees steel or Tenon * tubing may also be
                                                   used far th* probe. Heating I* not n«iMs*ry Uta* prob*
                                                   remain* dry doling the purging pavML
  &l  MetertM       .
  8.LI  InlttaTCallbratiBB. Before It* Initial me In taa
 flald. ftnt teak cheek UM metering lyitom (drying tub*.
 estate vetTa, ^me, rotHneter, and dry gM meter) as
ttoime,
              49, NO.  i«o~Txut»AY. AUOUH

                     D-38
                                                                                                           1*77

-------
                                                     'tULES AND  IIGULAT10NS
                                                                                                                            41785
      fetTER



•WOUND-GLASS SOCKET

      |Np. 1278
               WO mn
MAT STOPCOCK
T40K. i FVREX.
2«m BORE. t-iNn OO
                                          WOUND-GLASS
                                          SOCKET. § NO
                                          nrrex
OHOUN
 STANDARD TAPER.
| SLEEVE NO. 24/40
                                                                                                                    ENCASEMENT
                                                                                                         ING FLASK-
                                                                                                    S-LITER. KXMo-Krrrou. SHOKT NECK.
                                                                                                    WITH   SLEEVE NO. 24/40
                                           7-1.  Sampling t/aln. fla»k valv*. and flat*.
   1U  OoOeettoo Ftaak. Two-liter bondncata, rotmd
  •otteffl flatk, with abort neck and 44/40 cjandard taper
  aprclni, jgrotected asainat Impledon or braakaf e.
   IIJ  Flatk Valve. T-bon etopooek connected te a
  MMOetandard taper Joint.
   11.4  Tunpcrature Oaofc Dial-type tbermotneter, or
  •tber temperature faof.e, capable  of ncMurlnf 1* C
  B*F) Interrali from -ttatVC OS to 135* P).
   1U  Vacuum Line. Tnblnf capable of witbatandlJBi
  rjaoonm of ?t mm Hi (> In. Hf) abeoinu ujaauii, with
  •T" oonnecUon and T-bore atopooek.
   IX)  Vacnnm Oauir  C-tnbe manometer, I nat«r
  CK ID.), with 1-mm (0.1-ln.) dlvWoni, or outer faac e
  WahU gmeajuilnt pnejm*  to within *U mm  HI

   11.7  Pump. Capable of  >e»mieHnj tbe oanentkm
  •at te  a preajun equal to or leej tban 7» BUD Hi (I In.
  Hi) abaolou.
   tlJ  Bqueue Bulb. One-eray.
   fl.9  Volumetrio Pipette.» ml.
  Jtl-10  Itopcock and  Oronnd Joint Omce. A m»b-
  5?".um' blfb-umperatort chloronuorocarboo freaw It
  imired. Halocarbon 2MB hat been (oood to beeffectlTe.
   W.ll  Baromtte. Mercury, aneroid,  or otber baram-
  PV capable of meaenrlnt almotpherlc prtwure to within
 U mm HI (0.1 In. HI). ID many caeca, the barometric
  ••dlni may be obtained from a nearby national weather
 •rnniteUon, ID which eaee the elation value (which to
. "••nwlnu barometric praarun) thai] be raqueeUd and
  U edjuttmtnt  far ateratlon dlflerenoea between tbe
 ^•uar  elation and eampUni point thai) be applied at a
 •U of mum U mm HI (0.1 In. H<) per K  m (100 ft)
 •rnttonjneraaac, or Tiot vena for  deration (leiieaei
  _V.  Jample fteoorery. Tbe  tollowlnf aqmpmejpt b
  "l*»a (or tempi* reeoeeiy:
    ••I  Oradaaied CyUndrr. M> B) wnb l-Bl dlTMoni.
                          Leak tree    '   '  '
              Wp«tu. Two 1 ml, two J »L
                   MM] MM » Hi te •
                                                10J  rereeteln Knpondaf DWuL 1T>- te
                                               «ar»dty wltb lip tor poartni. oo« far each Mmpl* ud
                                               •ch tuadard. The Coon No 4M06 (ihkllow-torm. 1M
                                               ml) hu been toond to b* otlitartory  AJUm»aT«ly,
                                               pofrmettiyl pent»nt boken (Ntl|e No. UOa, UOml). or
                                               (ku§ bmken (WO ml) may be DMd Wb« (law (Makers
                                               •n DMil M£hlD| of the beaken may oaim tolld matter
                                               to be praent In the analytical CUD. UM •olldi eboold be
                                               rtmoTad byftltntlon (•«« Section 1.1).
                                                Ul 5  8tmiD Bath. Low-ternpentun orem or tberoo-
                                               etaUcelly controlled bot ptatei kept beik>w TV C (MO* T)
                                               iff eeoeptablo aJteraatiTee.
                                                U 4   Dropping Pipette or  Dropper. Tone nqmral
                                                U 5  Polyethyleor PoUoeman. On* tar each eamrO*
                                               end each iUndard
                                                U.I  Graduated CyUndir.  100ml wtth 1-mldlTWoDi.
                                                LJ 7   V-tomecrlc  Flaeki  Mml (one tor each eamplr).
                                               100 ml  loo* (or each lainpli and earb  etaodard. and one
                                               •jrUMwcrt'nceUDdanTENOi aalaUon). end MOO ml
                                               (OIK)
                                                «««   aDeetropbotaseter. Te njeteini abecrbanee «t
                                               eflOnm.
                                                U.e   Ondmted Plpetu U ml wtth O.I-nl dlTWcni.
                                                14.10 Ten Paper far ladtoatln* pH. To otmr UM
                                               •E raofe ot 7 U14.
                                                UL11  eVmlrtkml  BeJaooe. T* uieeeai «• wttMn OJ
                                                  '
                                                UUMei otberwlie  Indleated. It k) Intended  that aH
                                              reaienu oooJorm te tb* ipedfloatloni aMabUabed by tbe
                                              CommJtlet on  AnalytloeJ  BeajralJ of  the American
                                              Clxmlca! Sodety. wbert tocb tpeclocatlont an avail
                                              •cle otberwlM, oar the beet tvallable |rad>.
                                                a.1  Sampllni  To pnpan tbe *beorblnt "Inllon.
                                              eaodcnuly add 2J ml  oooctntntrf H^O, fo 1 Ut* of
                                              tWonlud dUUDed  water, kill well and  add ) ml of I
                                              paroent  hydro|Bn peroildf.  treahly prepared  from 10
                                              percent  hydrofen  peroUde  aoluUon  The  ibaDrblnf
                                              Julian thoaldbe ated within 1 week of la preparatlan-

                                                 "  feunple Recovery. Two ree«eca en •^J.—] tor

                                                    "JodlS HyonaJde (IN). BltKtn «I NaOH
                                                         dlttlUed water and dUote to  1 Bter
                                                         DIJW-H.
                                                                          At the  epOoc
                                                                                    eejalyet. tbe EKNO, te«t tor — «••*— >^>
                                                                                    •ay  be emitted wbeo kteti eemmoiaUone of «canfc
                                                                                    •Batter en not expected to Be preerot
                                                                                                a .tat ike
  U  AnalyDa .
enngnlred
                                                                                                   at ike tmaty^ji, tbe Mkvwkw ne«e
  	  -	-^	—§ paVDIDt OT ^rlaWllt
eree enlfur tnuloe. HANDLX  WITH  CAUTION.
  »JJ  Phenol. While aotld.
  aJJ  •otturtc Add.  Oeocentreted, w3 peraeart
          ~        WITH CAtmohT
                                                                                                      .
                                                                                              HANDLK WITH
                                                                                     «J 4  Poteailam Nitnu. Dried at 106 to 11O> C (t»
                                                                                    to W7* r) tor a minimum of 1 kem loet prtor te prepara-
                                                                                    tkm of euodard ntaitian.                   «--^-
                                                                                     iOJ  (taodard  KNO,  •obnton- Dtooln enetly
                                                                                    tJMt I of dried poteeHom altme (ZKOi) In 4eto«li«l.
                                                                                    •&U1M water and  dltau to 1 (her  with eWnnliarl.
                                                                                    ettetlUed water In a UBO-ml nlametrte flaik
                                                                                     M-6  WortlDi Btaadard ENOi lototled. DOoU 10
                                                                                    •U of the  •undard eolution to 100 ml with 4etooled
                                                                                    ••tilled water. One mllllllter of the wnrtflnf etaodard
                                                                                    •atotlan le equlraknl te WO « nrmno dtodd* fKOi)
                                                                                     AJ-7  Water. DaloolMd. dleUUed ee  to fcctloo 1A1.
                                                                                     aJJ-TbeooldlinltinJe  Acid Dolutioc  Dtaeoln H |
                                                                                    et pm wblte phenol In  1*0 ml tmeeoOUed euHurtc
                                                                                    •otd «• a eteam bath  Ont, add 7» ml (umloc euMurlc
                                                                                   ••eX, and beat at 100- C&TT) tor I boon. Mm In
                                                                                    fjaak. ratainlac a •amdeat qmn9ty far nee In prepanof
                                                                                    the callbraUon (tandardi loaert tbe fiaak valve etopper
                                                                                    teto tbe fiatk with tbe vain tn  tbe "porn" ponUon
                                                                                    AaaembW tbe eampUnt bain ae aho*u In Flejun T-l
                                                                                    and  place tbe probe at tbe eunpUni point taaka eon
                                                                                    thai all Btttn«i an tl(ht and Wak-fria, and thai all
                                                                                    {round fjaai lolntt bave bean properly fianert with a
                                                                                    Bib-vacuum,  bkfh-tamperatun  ebxrvfluoraoarbon-
                                                                                    freiefl Kopcock peaei  Tom tbe laak vain and tbe
                                                                                    •nmc val»e te tbetr  "•vaeuate" poalUont  BvaenBU
                                                                                    tbe Batk to Ti mm HI 9 tn. HI) abtolute praaaun. er
                                                                                    kea  KvacaaOon te a  pi •mi approaching tbe vapor
                                                                                    praarure o< water at tbe exlitlni temperature le eVaalrable
                                                                                    Turn tb* pump vain le ttt rivent  poaluoc and Cum
                                                                                    	 pump  Obeck tor
                                                                                           tor any
                                             anm voc 4», wo. I*O-WO«»AY, AOOWT i§. itrr
                                                              D- 39

-------
   urn
                                                           RUlfi AND  lEGULATIONft
tntfa
I nunn
         Man W mm Hs (D.« IB. Eg) o*» t period at
         , ti aot acceptable, end the flau: 1* not to to
      until  UM leakage probta 1* corrected.  Prawn
 In tfej flu& I* oo« to exceed 79 nun Hg (J In. Hgl absolute
 at UM ami) sampling \a commenced.) Record the volume
 of UM Oteis en
 mo*po«ro until UM Sitk prenm* It almo* cquel t*
 Wroospiurle pranta*.
  4-2  Sample H«»Twy. Lst UM flaak  set fcr« mlnlnram
 oS l« boon and tbon shtto UM contenti t» 2 minute*.
 Connect the flitk to a mercury filled U-tub* nuLnnmirlinf
 Open UM rain tram UM 9aik to tbe maoometar  and
 record  tbe  fiaik  temperaton (T/), tbe  barometric
 prawn, tnd UM dln*»r«nca bocwssn the marcurj I*T*|§ "
 n  UM  manomatar.  Tb« absolute  Internal praowr* In
 tba UMk (Pi) ta UM barometric preanre \tm tb« m»a-
 omeUr reading. Tranate tbe conunt* of tbe ftaak ta «
 DMk-dw  pol7«thylan» bottle.  Rlnn tne Oaik  twice
 with i-ial porUono of dclonlied, dlitllled watar and add
 UM rtnM mtar ta tbe bottte. Adhut tb« pH to botww»
 » and 13 by adding ndlum bydroilde (I N), dropirlaB
 (aborat SS to  «8 drops). Check tbe pH  by  dipping a
 jtintnc rod lute Uw solution and tban touching the rod
 to tb* pH tan paper. Hamoira as Unle m»t»rtal u pooribM
 during liiit, sup. Mark UM bftlgbt of tbe liquid Vrel ae
 that UM  contamar era to  cnackad  for leakage attar
 tramport. Tehftl Uw container to clearly IdvUi^ Its
imtanti  Seal tbe container tor shlpplnj.
  «J  Analyal*. Note UM 1«T«1 of the liquid In container
 and confirm whether or not any temple mi \ost during.
 shipment; note  Uui on the analytical data abeet. If a
 noticeable amount of leakage hai occurred, either Told
 UM nmpie or on nutbodX  5ab)ect to tbe approval at
 tne Artmlnlitratar, to correct the Anal result*. Immedi-
 ately prte to analyda,  trani&r tbe contents of  UM
 snipping  container to  a 30-ml volumetric Ouk, and
 rinae tbe oontaioar twice wltb S-ml portloni of delonlxed.
dlAUlad w&tar.  Add the rinat water  to the nuk and
 dilute to tbe mark with deloolfed, dlJtlllad water; mix
 tboroQgbly. Pipette a 2&*ml euqaot Into tbe procelato
 eraporatlns di*.  Return any  oniaed portion of  tb*
 aample to tbe polyethylene (torage bottla. ETaponta
 Uu 25-ml aUqoot to drynew on a steam batb and alktw
 to oooL Add 2 ml phenoldifulfoolc add solution to tbe
dried retidne uid triturate thorougbly wltb a poyletbfi-
 ene p^ii^^rMm Make sun the solution contact* all tne
 ratidiw. Add  1  ml  delonlted, custiUed water and (oar
 drop* of oaacentrated niifmio add. Heat the solution
 on a *taKn bith Cor 3 mlnotei wltb occasional stlrrlnf,
 Allow tba solution to cool, add 3D ml delonlud, duttllla*
 watar,  mix well by itirrtng,  and add  concentrated MS-
 monlon tiydrorld*, dropwut, with  conotant stlrrinf>
 until tbe  pH 1«  10 (M determined by  pH paper). If UM
 sample contalnt ooildo,  tbeai  moat  to remoTed by
 llJtretSoo  (centrlfugadon I* an  acceptable alUmatlT*,
 subject to tbe spproT*! of tbe Administrator), a* foUowc
 flltar tbrooch wbotmaa No. 41 alter paper into a 100-ml
 Tolumetrle flaik: rtna>  tb« eTaporatlng dl*o wltb thraa
5-ml portiooa of dalonitsd. dljtllled water niter tbem
tone rtajas. Waa& ti>« Bltar wttb sf,  laeat three U-fflS
 portion! at delooJiad.  cUnill«d water. Add  tbe Bltar
 waahlncs to the coatamU of the Tolumetrle fU*k  ana
dilute £o  tbe  murk wltb deloniied, distilled water. U
solldi are abeant. th@ aalution can be tranfiferred dtreotrff
to in* lOO-mi Tolumetrk Oatk and diluted to tbe mark
 wltb deioal&sd.  di*tUl*d wat«. Mix tba content* of to*.
 daik thoroughly, and  meaoura tbe abavbano* at Uk9
optimum wsTueDgtb ussd tor  tbe standard* (Section
3 J-l). using tbe blank wlutlon u a tero ntmaat. DlloU
tbe sample and  the blank wltb equal  Tolumei of deioa-
lud, dlitliled w&ta If UM abrarbanea txceada A* UM
abanrbsae* of tb* «M as NOi xaadard  (•• geotiaa 4JJ».
 water, to the stopcock. Muaauii the votem* of water t*
 ±10 ml. Record this volume on tbe aaafc.
  9.2 SpecCropbotometer Calibration.             ._
  9.11  Optimum Wavelength Detarmlnarlnn. For botk
 fixed and  variable wavelength  spectre-photometer*.
 calibrate against standard certified wavelength of  «1B
 nm, every « months. Alternatively, for variable w*v»
 length spectropholometM*. scan the spectrum totwea*
 400 and 419 nm using a 200 i*j NOi standard solution (la*
 Section 9.2.2). If a peak doe* not occur, tbe spectropbo-
 tometer Is protobly malfunctioning, and should to re-
 paired. When a peak Is obtained within the 400 to 419 na
 range, the wavelength at which this peak occurs  snail to
 the optimum waTelength for  the measurement of eo-
 sortonoe for both the standards and sample*.
  9.2.2  Determination of Sprctrophotometar Calibra-
 tion Factor K.. Add 0.0, 1.0, 2.0, 3.0. and 4.0 ml of too
 END, working standard solution (1 ml-100 * NOO to
 a series of five porcelain evaporating dishes. To each, add
 21 ml of absorbing solution, 10 ml deloniied, distilled
 water, and sodium  hydroxide (IN), dropwtse, until UK)
 pH Is between  9 and 12 (about 25  to 98 drops each).
 Beginning with  the evaporation step, follow the analy-
sis procedure of  Section 4.*. until the solution ha* bean
transferred to the 100 ml volumetric flask and diluted to
tto mark. Measure the atoorbance of each solution, at UM
optimum wavelength, as determined In Section 9.XI.
This calibration procedure must to repeated on each day
that samples are analyted. Calculate tb* ipectropbotota-
eter calibration factor as follows;
                                                                                                         ft.4 Bainple
                                                            .-100
                                                                                   Equation 7-1
                                                  whan:
                                                    tf.-Ceaoration factor
                                                    Xi-Absorbance of the 10(H4 NOi standard
                                                    A,- Abeorbanee of the 200-« NOi standard
                                                    /ti-Abaorbanoe of the 30O*« NOi standard
                                                    At- Absorbent* of tbe UXh* NOi standard
                                                    9.*  Barometer. Calibrate agaln*t a mercury baraB-
                                                  eter.
                                                    9.4  Temperature Oange. Calibrate dial thermameten
                                                  agalnat mercnry4n^iHi thermometen.
                                                    5J  Vacuum Gauge- Calibrate mechanical taoge*, U
                                                  ueed, agalnat a mercory manometer such a* that spod-
                                                  nedlnTTA
                                                    9.«  Analytteal Balanea. Calibrate agaiiut standard
                                                  weigbta.

                                                  *. CUtilttttm

                                                    Carry oat the calculatton*, retaining at leait one atra>
                                                  decimal Ogon beyond that of the acquired data. Bound
                                                  off figures after final calculation*.
                                                    4.1  Nomenclature.
                                                      A-Absorbanc* of sample.
                                                      C-Concentration o(  NO, a* HOi, dry  beahi, cor-
                                                         rected   to   standard   oondUiooa,   mg/dasni
                                                         Ob/dad).
                                                      J?-Dilution factor (I e., 2S/9, 2»AO, etc, required
                                                         only  If sample dilution was needed  to  rednea
                                                         the ebaorbanc* Into the  range o( calibration).
                                                     jT.-Spertrophotometer calibration factor.
                                                      m-HBM of NO, M NOi In gas sample, «r.
                                                     PI- Final absolute pmsure of flask, mm Hg (In. Hg).
                                                     Pi-Initial abeolute preawn of flMk. mm Hg (In.
                                                         Hg).
                                                    Pnj- Standard abaomte pKuauia, TtOmm Hg (29.92 In.
                                                         Hi).
                                                     T/- Final absolute temperature of flask ,°K ("R).
                                                     T,-- Initial abeolute temperature offlaak. °K (°R).
                                                    Tat- Standard absolute temperature, TSOf K (528* B)
                                                    V,.- Sample  volum* at standard condition*  (dry
                                                         baiii), ml.
                                                     V/- Volume of fiaak and valv*. ml.
                                                     V.- Volume of absorbing solution, It mf-
                                                      2-80/24. the aliquot (actor. (If other than a 2a-ol
                                                         allnnot wa* used for analyslf,  the correspond-
                                                         ing factor must to substituted).
                                                    6.2  Sample vorama, dry bad*, corrected to standard
                                                  condition*.


                                                  '--ft <"-'•> K-ft]
                                                  whan:'

                                                    JT,=-0.3858
                                                                  mm Hg
                                                                                   Equation 7-2 '
   for metric unit*
                                                         •17.64
for English unit*)
  t.l  TTflrit VoNiaM- The Tohim* of UM esUeetka
fl&ak nj7< combLnarkn moat bt known prior to »sar
pLLDj. Ammbl* tto UtaU: Mtd  Sw& ralTe and flO wl»
                                                                 in. Hg

                                                   S-i  Total <« NOi par lamnto.
                                                                                   Equation 7-3

                                                    Nora.— If other tha* a 25-ml aliquot I* uaad tor analy
                                                  il(,  tbe facto* t mast b* replaced by' a oomepondlnf
                                                                                                                                        Equation 7-4
                                                                                                                         for metiio unit*
                                    6.243X 10-*
                                                                                                                                  for EngUt* unite
                                                                                                       1. Standard Method* of Chemical Analy*BX ttk aft,
                                                                                                     New  York. D. Voa Noitnad Co., In*. IMaV. Vat, t,
                              2. Standard Method of Teat tor Oride* *f Nttrogio to
                             Oaseou* Combustion  Product* (Phenoldlnlimk Add
                             Procedure). In: IMS Book of A8TM Standard*, Part 2a,
                             Philadelphia, Pa. 1M(. AflTM Deaignatlon D-UDMaV
                             p. 725-7J*,
                              a. Jacob, U. B. Tb* Chemical Analysl* of Air PoDnt-
                             *nt».  New  York.  Intandanea PubUaban,  Ina. IM*.
                             Vol. 10, p. 3S1-36*.
                              4. Beerty, B. L., L. B. Bargar, and H. H. Schrenk.
                             Determination of Oilda* of Nitrogen by UM PhenoldlsoV
                             fonic  Acid Method. Bunao of Mine*, U.S.  Dept. of
                             Interior. B. I. 38*7. February lUi.
                              9. Hamll, H.  T. and D.  E. Camann.  CoUaboratlva
                             Study of Method tor tbe  Determination of  Nltrogaa
                             Oxide Bmiarion* from Stationary Source* (Foaall roaV
                             Fired Steam Generators). Soutbweet Beatarch Instltnt*
                            report for Environmental Protection Agency.  Beaaarck
                             Triangle Park, N.C. October 9, 197*.
                              8. Hamll, H.  T. and B.  E.  Tnomam.  CouabontlT*
                             Study of Method tor tba  Drtermlnatlon of  Nttrogea
                             Oilde Emiadon* from Stationary Source* (Nitric Add
                             Plant*).  South weet  Beeearch Initttnt* report for En-
                            vironmental  Protection Agency.  Beeearch  Triangle
                             Park. N.C. May 8, 1974.
                            Mmoo t—DrmnnLatau or  Buinme Acrn Mar
                              ii»i> SuLnnt Dnxn>B EmiBiaiai  )*IOH STATIOIIAXT
                              Souacn     •

                            1. PrtndpU n* XppUeaMatr
                              1.1  Principle. A gas sample U extracted  boklnetfcaBy
                            from the stack. The sulfnrlc acid mlit  n'10~> pounds/cubic  foot) for sulfur trioddt
                            and 1.2 mg/m> (0.74   10-' lb/ft') for sulfur dioxide. No
                            upper limit* have been established. Baaed on theoretical
                            calculation*  for  200  milllliten of 3 percent  hydrogen
                            peroxide  solution, tbe upper concentration limit far
                            sulfur dioxide In  a 1.0 m> (39J ft') ra* sample ll abort
                             12.600 mg/m> (7.7X10-1 lb/n>). The  upper limit can to
                            extended by Increasing tbe quantity of peroxide sointlOB
                            in the impingan.
                              Possible Interfering agent! of this method are ftaorldea,
                            free ammonia, and dimethyl aniline.  If  any  of that*
                            Interfering agent* are prernnt (this can to determined by
                            knowledge of the procee*), alternative method*, subject
                            to the approval of  the  Administrator, are required.
                              Filterable paniculate matter may to determined aloof
                            with SOi and SOt (subject to the approval of the Ad-
                            ministrator); however, the procedure used for partlculat*
                            matter must to consistent  with tb* speclncatioD* and
                             procedure* given In Method a.

                            3. Xpperara*
                                                                                                       2.1  Sampling. A  r-»Miinatf
                                                   •traction detail* an described In APTD-06S1. Change*
                                                   from tba APTD-OSU document and allowable moot
                                                   ficadoo*  to Figure t-1  an  dlaroased In UM taUowla*
                                                   subeecoooa,
                                                     The operadng and maintenance procedural tor taw
                                                    am plug train an dens! tod In APT D-flST*. Sine* oomat
                                                   usage li Important In obtaining valid remit*, an uaaw.
                            should read tha APTD-057S <<~-iimjj—TMUUOAY,  AUOUJT !•,
                                                                        D-40

-------
417»
        KUlll AND  t&OULATlON*
      SoUOrt* Add Standard (0.0100 Nl PMrehaaa a*
      laa » ±00aai N afalnjt 0.0100 N NeOH that
      Tfcneiy  boa  (tandardliad  ecatnat  primary
       potaealojHi eald phthalasa.
 (1.1  Pret aft PrwparaUoav Follow the procedure ovt-
yoed IB Method ». Section 4.1.1;  filten ihould be uv
nerted, bat need not be dedocated, w«i|had, or Identl-
Gi U the effluent rat can be oonaldered dry La., mote,
tort tree, the ilUoa ral  need not be welfhed.
 41 j Preliminary Delermlnaltooa.  Follow Uw pfw*
ado* outlined In  Method 5, Section 4.1.1.
 i u Preparation of Collection Train. Follow the pro-
arfun outlined In Method  J, Section 4.1.1 (eicept tar
111 anond paragraph and other obnoualy Inapplicable
re/tl) and oat nror» e-1  Inrlaad at Flron 5-1  Replaoa
X anond pancraoh  with: Place  100 ml at SO percent
iBoropaoai In  the am Implnrer,  100 ml  of 1 percent
tydnifaa paroied* In both  the anond  and third (at-
 P*"**™  retala a ponton at eaah  n««en» tor am m a
 blank eomtlon. Place abom 3001 of aUica eel In UM ban*
 Unplncar.
  Norm.—I/ moljtor* coo tent  U to be detarained'by
 Implnjer analyjia, weljh eetch of the ftnt three LmpLnrer*
 Iploa abeorblnfialatlon) to the o«ar«*t 0.3 < and reoord
 theee wtlrita. The welf ht of the Ullca eel (or Ullca rai
 fiat container) moat alao be determined  U> the  nan eat
 0-5 | and recorded.
  4.1.4  Prate**  Leak-Check  Procedure. Follow  Uw
 baate procedure  outlined In Method 5, Section  4.1 4-1,
 noting that the  probe heater ihall be adjusted to the)
 minimum Umperatun required to preTent coodenaa*
 Uoo, and tJao that vorbece tuch aa.   * * pluct^nx the)
 InM  to the filter holder • • V" ihall be replaced by,'
 "• • • pltiMlnt the Inlet to the ftrat  Impinfer  • • V*
 The pnteat leal-check U optional.
  4.1J Train  OperarJon. Follow UM  baato proeadoni
 outlined In Method 6, Section 4.1 J,, In  conjunction with
 UM toUowlnt fpacMJ Inatmctlona. DaU ahall b* retorted
 on a (beet atmOar to the one In Ftenre *-«. The i	_
 rate ihall no« exceed 0.030 m'/mln (1.0 rfm) dnrlnj
 ran. PertodlcaTly durtn< the tee*, obeerre the connect
 line between the probe and firat  Lmpinfar lor  ilfot
 ccndenaatlon. U It  doe* occur, adjujt the probe beat*

 to prrrant coodacjatkn. U compoaentchanfai beccnaa
 ornearr during a  ran. a leak-check shall be done  (m-
 mediately befcn each ehanre, aooordlnf to the procedtar*
 ootllned In Section  4.1.4J of Method i (with approprua*
 mnrtlflrallocii  u  manttoned In  Section 4.1.4 at that
 method); record aD  leaet rata*. U the  laraci rate
 eioaad the epedfiad rate, the teeter ahall either roid UM)
 ran or ihall  plan to correct the aunpl* rolume at oeaV
 lined In Section ej  at Method 9. Ti"mrtl«ter)- after coaa.
 poneot  thaarea, leak-cheek*  an opoooai.  U  Uvaaa
 leak an  don*\ the procedure outlined  In Seedea
 i.1.4.1  at Method. *  (with appropriate
inaUbai
  rXA»t_
  IOCATIOI -

  OKRATOH _

  OATI _

  RUIM. -

  SAM1EIOXM..

  MCTUUXIML.
  CFACTOH
  rTTOT TUlf COEFFICIENT. Cf.
                                                        mm Hf da. «•>.

                                      AMJIEITT TEMfERATUBt	

                                      SAROMCTRIC PfltSJUHl	

                                      ASSUMED MOUTURE, %	

                                      PROIE LER8TH. • (ft)	
                                              SCHEMATIC Of STACK CROSS SECTION
                                      NOZZLE IDENTIFICATION NO

                                      AVERAflE CALIIRATED NOZZLE DIAMETER,

                                      PROIE HEATER SETTINt

                                      LEAK RAT!, m3tm*,(ttm)

                                      PROBE LINER MATERIAL

                                      FUTtHNw.
TMVI Wl MHNT
NUMHK












TOTAL
SAMFtUM
TMfl
(«),a*.













Avuuua
VACOOat
oTrt}














HACK
TEMKIUniRI
fTl*.
•tfn-














vHocrrr
MEAN
. 














PRE0UM
DIFFEREimAL
ACROSI
ORIFICI
METER,
mm Hj9
(ia. HjOJ










-



GASSAMPtl
VOLUMI.
ar3(hJ»














8AI SAMPtE TEMftRATURf
AT DRY 6Af METER
INIET.
•ci»n












Ayfl
OUTLET,
•€(•«












Av«
A«f
TtMFtRATUM
OFQAI
LEAVmt
CONDENSER OR
LAST IMrMNeER,
»C(»F)














  itar tornlnf otT UM pomp and ^•••K«JJJ Us* 9am\
l^liiff at to* oonrlniioo of each ran. remor» tha probe
no lh< rtack. Coodoet a (Mat-teat (mandatory) leak-
™t*ai la Section 4.1.44 o( Method 5 (with approprlat*
annotation) iod record Uu  leak rat*. U UM poat-taat
'»U(i rtu riceedi the tpeclnad ecceptabU raU, UM
•W" Hull (Ithar correct the aunpU rolonM, M outlined
*%*U°o «-> of Method 5. or ihall rold UM ram.
  "nta th* lo> baih and,  w-tth UM probe dlanxuMoUaV
mrri the nmalolni part ot the train, by drawln* clean
uMant air throofh UM rritam lor U mlnot*) a* taw
"«d Bow rate ua>d to aunplln*.
 J*on.—Clean nnblent air can be prorlded br pi
»throaa*, charcoal Oltar. At the option at the I
""blent ilr (vlthoot cleaolnr) mar be ua»d-
  UJ  CtlculatloD  of Peroant IioklnetM.  FoDrar tft*
»»ednr. outlined In Method J. Section 4.1 A
  u 9ample Reoorary.
  U4  Cooulaer Me. 1. U •  moiatare oontamt anatyatt
             Flgur* 8-2.  Fltld dataV

U to be done, w«lcb tha ftnt Impinfar pin* oaatentt (•
Uie neanet OJ ( and record Uilj weight.
  Tranitar the coatcaU of the Orrt Imptnter to a 190-ml
rraduated cylinder. Rlnje the probe, flrat Unplnfar. a&
corui^rtlrn lUarware t»(ore the filter, and the front half
of the alter holder with 90 percent Laoproconol. Add UM
do*) »luUoo to the cyllnaer. Dilute to 2M ml with M
percent iKpropanoL Add the filter to the »lution, "^
and a^ntltf to the rtoraf e cootalnar. Protect the loiuUaa
a«alnat ermporadoo.  Mark the lenl at llqoM cm  t»|
container and Identify the aunple oontalrjar.
  4.U Container No. B. U a molitun contant analyvJv
U  to be done, •«lth  the eeeood and third  lmpln«an
ipluj contenU) to the aeanat  OJ ( and  noord tbea*
wel«hta.  AUo. welfh the tpent illloa ral  (or illlea ral
ptujtmplniar) to the QearectO^|.
  Trantfar  the  Kludonj  tram  UM leoood  aad '>•>"<
lmpln«^rt to a I000-ml rraduated cylinder.  Rlnai aQ
ocxmectlnl flaareran (Includini back hal/of Alter bokME)
between toe filter and illlea faTlrnpln(ar with  lilrnlteef
dlittDad water, and add thlt rlnja water to the
Dilute to a roloma of 1000 ml with d«^ni-r1.
water. Tranifar the solution to a ttoraf* oootalnar.
the leral of Uquld on the >~.t»i~> a«al aod IdeoOty tee)
sajuple ccouloer.
  44  Analrale,
  Note the UTB! at Uqold In container* 1 aad I and
firm  whether or oo< any aunple wu loat dnrln( e
ment; note thii on the analytical data ibeel  It a noUoa-
abte  amoont ol leakan hat  occurred, either rold
mmple or ua» method*, tub feet to the apti
Administrator, to correet the final raauttav  •
  4.»,1  Container No. 1.  Shake the container *>^*«-a
the l»propaaol solcrOoo  and the  filter. U the flrtar '
brtarj up, allow the rrafmenU to »nle tor a hw mlniriaa
b«lon remcrlm > ample. Pipette  a  100-tnl  allqao* at
thll lolutlon Into a 110-mJ Erlenjneyar fleet, add 1 U 4
dropa of thorin Indicator, and titrate to a pink endpoinl
ulln4 0.0100 N barium perchlorate.  Repeat the Utrattoil
with > atoond allqaot of aunpk and 11 aiaeje the Ut   '
                                               MOIfTa*. VO*. el,  NO.  1 •«—THUISOAT.  AUOUST  It,  IfTT
                                                                        D-41

-------
                                                    tULES  AND •EOULAT10NS


                              1VMK NATURE SEKSOR
                                                                                                                               4178
                                                                                                         ^HERMOMCTER
                        rrroT TOIE
                        tCMTC MATURE KMSOR
                                                                                                                       •VACUUM
                                                                                                                         «AU6E
                                                                                                           MAIN VALVE
                                        TEST METER
                                          figurt 8-1. SuMuftc acid mitt campling train.
  14.4
       VUter Eoldor. Bercaflloat* ria», wttb a UM
felt filter auupal and a aUicont robber (aaket. Other
•ekat material*, M . Tenon or VI ton, may b* and *ob-
fccl to tb* approval of the AdmlalnraUr. The holder
•nilpi aball prorld* a poUQT* eetl afalnfl taakaf e tmm
tb* ontrfde or aroond the filter. Tb* filter bolder aball
we placed between the ant and tee and Imgtafan. Note:
Do not beat the filter bolder.
  1.1.8  Imptnfert—Vow,  a* ehowB la Tlnre 1-1. Tb»
flnt and third (ball b* at  th* Or»eobori*mlUi daalrn
with naodaril tip*. The anood and (rarth aball be of
to* Oreaabarf-Smllb dedcn, modified by repkdiic the
I men wlub aa approHaately U millimeter (OJ ln.1  ID
ftea tobe, haTliu an tmoonttrleted tip located 11 mm
JBJ In.) from UM bottom i
                     o) UM fluk.
                                  llw
wfttama, which bar* boas «ppror»d by UM Admlato-
-^—	ay baoMd.
J.L10
         S, hcttm 11.10.
        T«D(Mntan Otai*.
              UM
' Buianr tnln to wtUdn I
                 ump«tnr» of UM |u
                 dnI*0 (T F).
                                                1X4  TripBtta
                                              t&tixr""*""
                                                U
                                                     OndoaUd Cyttnd*. MO nl
                                                     Trip BataacB. HO |
                                                    otbtnrta. Indicated. aD nafno an to «onfcrm
                                            to U» (ptdfiaiUow ««lihinh«d by UM CommlttM on
                                            AaalrtJcal Ktaftnu of UM AHMruan Cbonkml BoOMtj,
                                            vbv< nub ipKlficaaoni an anUabk. OUMrwte. MI
                                                                                             ,,„   U.- hl*± UltfUlh) Mid ~*^ iMMBWMet. Vl
                                                                                             UM tollowtaf teet tor detects* paroxidei In each tot I
                                                                                             bnpropanol: Shtka 10 ml of the leopropano) with 10 •
                                                                                             •Ifrcahly pnpared 10 percent imlaerlnni loJM* tontBot
                                                                                             Fnpan a blank by almlkrly traado* 10 ml of dletfll*
                                                                                             •ater. After 1 mJooU, read the abaorbanee on a epaetn
                                                                                             - •• ptometei at «U nanomoten. U the aheorbaaei *n*d
                                                                                                the taopropanol aball not be oaed. Paradda may b
                                                                                                toved from leopropano] br ndlitilllnf. or by pa«a»
                                                                                             t&OKflib a f^"*^" of actiTated alojnloa, Bowever, n
                                                                                             ajut-crvU l»opropanol with Biltably low panddeleral
                                                                                             • nadUy aTaUable from eommerdbl aooreei, thenew
                                                                                             nAectioD of T^"1irnlnetti1  lot* •**»T  he nor* et^
                                                                                                  mllowlni the peroxide ramoTaTprMadan.
                                                                                                 t  BydrafeQ Parozlde, I PenaoU Dlrot* !
                                                                                                 percent hrdrofan pwodd* to I Mar wHb **
                                                                                                 M wau». Prapan frawj dally.
                                                                                                    Oraahadle*.
                                                                                             &J4
                                                                                             U
                                                                                             «J-1  W
                                                                                                   pM
                                                                                                   aW
                                                                                                                .
                                                                                                         laBM M U J.
                                                                                                               ~
  _-
ftvo).
                                               4U tampUoc.
                                               U.I  Ttivm. teoM M Melted I, tatfan U O.
                                               •J J  Hlka (M. iam« M MAbod I, lanUoa U J.
                                               (.U  WaUr. rMoolud, dliUUad to oonJnrm M AITM
                                              j^arlftnailon Dllva-74, Typ» «. At  UM opOoo of UM
                                              •oajjitf Uu KUflOi t«t far wtfltiiHt ar(aiilo mtUM
                                             laay b* onltud whan hkb oonontraUont rf
                                              «Mitt€r an not axpaoMd to b* pi ••lit.
                                                               M Fraot. Kb
                                                                                               U  Analrilt
                                                                                               •J.I  WaUr.
                                                                                               U.1 bDpropanol. MO PanaM.
                                                                                               iO.1 Tbortn lodicatar. H
      .OradoMed -Oyttadan. m mi, t I
      •--•	ly alao b* wad.)
                                                Hon.—
                                                      KzparMnee hai ebown that only A.CJ. (rade
                                                      >1  u eatlebvyry.  Teats  have ahown  that
                                                                 from erffnTiMiclal	
                                                                               wfll
                                                                                             1 J6
                                                                                             to
                                                                                             with
                                                                                                               .
                                                                                                 t-dunllonk add, dtoodinB nit, or
                                                                                                  O.K | la 100 ml of datonlMd, dtalUad
                                                                                             A«  Bartnin Pmhlonu (0.0100 Normal).  Dto*
                                                                                             6 1 of bartom panhuraU trUiydnt* (Ba(C10iMB«
                                                                                             m ml d«lonlud, dinllwd watar. aad dllnw «o 1UM
                                                                                               UDDTO panel, i J3 | of partom ohkrld; dlhydrml
                                                                                               lrjS^5)m.T b* ovd tanuad at tb* todnm *•
                                                                                                u. tundardlu wNh mlftirt* add a> In i*«U|"l U
                                                                                               mfaUon m»at b* pulaaail mtnat iiayaiillai I
                                                                                            ebwrai
                                                                                            ThlJi
                                                                                            •0
                                                     VOl. 41, NO. «


                                                           D-42
                                                                                 , *MU*T It, IfTT

-------
                                 tULIS  AND IIOULAHONS
                                                                                                                  41789
  •hm  afepUeate tttntkni maet a«ni *1Uilii 1 percent
   OJ ml vhioiMTw to freaux
  44J  OocUliMi No  J. Tboroofhly mil UM mlntJoc
  ~l UM oooUlnjr boWlnj Uw gooUoU of Ui« Mood aad
  -1rd Implujwi. Plpetu* 10-ml aliquot of awnpl* Into i
   >-mJ Krlenmeyv Beak. Add ml of leopropaooL 1 to
 4 drop* of tharin Indicator , and titrate to » pi ok md point
 feint aaiOO N barium perohloraU. Bepeal UM Utratlon
 With • leoood aliqaot of eunpk and mrwi the Utratton
 « btonka la toe eun* meaner M UM Ti
                                                                            NoUU»l
                                                              b« ooMKiMxJ d/7,
                                                        mdtetun oacUot and Dot t» ««>r«H»1«r1
                                                          •alfartc «old mM CUatodH* §O»)
  4.1  Oallbrvt* equipment ariaf tb* procedure! epeet-
       	nTofWbod 4: BecttooSJ
   -
 fv) to UM fcUovtaf
          •yvtaxn); Beottop 4.2  (texDperatint  §aoc«e)
 Motion {.7 rbaromrter)  Not* that lie rtoommended
 leak-obter. of Uie metering tnum. deacrlbed U> BecQon
 44 of Method 5. aleo applie* io thlj method
  a_> Btandardlu the bartam nerohjoraU nlutkn with
 • ml of ttandard eolrark *old, to which 100 ml of 100
       : enpropanol bee been added.
                                                                                               8-2
                                                      JTt-aoejot i/mOUeiTatTaent far metrfc
                                                        -LOElXlo-ilb/nMCi tar Bo
                                                      44  Bolttu dkoide eeneei
   Nett.— OVTT eat
       .
 •ptn of noule, m> (Tt1).
      B»— W»t«r rmpor In UM (>• Anam,
             by rohime
         ,-»u)hu-k: Kid (tootodli* BOO
             tMloin Ob/djcf)
     OBOi-Balfiu dicaid* MDentratioc,
             dKf).
        /-P«ro«nt of l»okln«tic «mplltn.
        N— Normality of twrlom pvchkntc tttnnt, f
             •qolT»leotj/Ul«r
                  rU t«i«iiiiii d UM f-~rtnt rtu,
             MUuH* (In. Hf).
         ,— Ab»olat«  Mack (M t»i»mi, BUD  Hi On

        d-BUndard
                                                                                    Kqu&tion 8-8
                                    JTt— (tOOO! (MMQ tor metric anru
                                      • 7JKlX10--ilb?nMq tor
                                    4.7  baklootlc Variation.
                                    4.7.1  OalfmbfVm from rav data.
       f •— A
  abeolnU

abeomte dry •
                                B).
                                  tv ta
                                           mtn
                                                                                    Kqu*Uon 8-4


                                                      JCi-OJDMM mm Hf-rnVml-T tor metric nntu.
                                                        -0,OCOeT6 In. Hi-rV/ml-'B tor Knfll«fa onru.
                                                      4.7 J  Oakroktiacihan tnarmtdlaU
            Fl«nr«»-a),' K f* B).
     TKd-BUruUrd  abiolatc tamfMntim,
            air B).
                                         M*  K
                                                                    T.Vm
  V«<»bD
                   .
       V.-VoJam* of Mmpfe kUooot tttntel, WO ml
            tor Hi6O, and 10 ml tor 8Oi.
                     « of Uanld ealkotad IB tnptncOT
            md mioaitl. ml.
       F.-VolmiM of nj mmpl* a« inaa»n1 ¥7 dry
           •EM nrtiflT, don} (dcO-
         -Vol£ime o/(M mm pie nmilnml by tb* dry
           •M BMttr oometod to
           •nm
                            to iUcdard ootidrtlooi.
                                                             7-
                                    JTi-4JX> tor M^rki miu.
                                      -4UM60 far *n»li»b nnlu.
                   ftack iw  ntoettr. —'—'-•-' br
           Method J, Kgoa&on t-0 Qfln» data obtaltMd
           from M«tnod 8, m/tee (ft/we).
    Katn-Total  roJome of nlotlon in wltich UM
           •oltarlr add  or  fnlfui  dioxide Mmpl«  to
           «ontain«d. VO ml or 1,000 ml, rMpteUTarr.
      - Vr~ Volume of bartom penhioraU tftnnt g«>d
           tor UM lam pi*, ml
      Vu-VolpnM of baiUun pvshknU tttrmnt «a*d
           tor UM bbuxk, ml.
       Y"Drj gu m*Ur eaUbratioTJ tootor.
      AB-Anrue uiMmit drop
           arm (In.) HrO.
       • ••Total mmplmf tim», mln.
                                                                              .
                                                      44 AowpUbl* RMOTU. If «0 nvant . CalibraOon, and qDeratton
                                                                          pllDf  Eoolpment. Ofon *f
                                                                          menlal Protectloc  Afeney.
                                >-K AH/13.8)
                                -
                                           8-1
  Xi-flJ4M 'I/nu» HI tor nutrlc tmto
    • 1744 'BAo. Effar ro«ll*h nsiu.

  Won -U UM teak raU ebMrrwl durtnj any maoda-
ajry Uak-olMek> arowl< Ui« n«cHWrt anetptabU rau,
4h* un«r thall *lth«r oornet UM rmlo* M V. In Eo
 -1 AY,  pUWOTt  It, 1*77
                                           D-43

-------
APPENDIX E
 E-l

-------
                     PEDCo ENVIRONMENTAL, INC.

                          MEMORANDUM


TO=   Project File                              DATE:  August 8, 1977

SUBJECT:  Trip Report - Visit to Magma Copper    FROM'-  V. Katari
        Company,  San Manuel,  Arizona on
        7/22/77

FILE:  3287-B                                    cc:   L. Yerino
                                                    T. Devitt
                                                    R. Gerstle
 After visiting the Phelps-Dodge Copper Company at Ajo,
 Arizona, on July 21, 1977, Larry Yerino and I drove to
 Tucson, Arizona, with Larry Bowerman and Bill Thurston of
 EPA Region IX.  The following day, we were joined by Steve
 Schwartz of BAQC, and all of us visited the Magma Copper
 Company at San Manuel, Arizona.

 Larry Bowerman explained the purpose of our visit during a
 brief meeting attended by the following people:

      Bill Wood - Magma Copper Company
      J. D. McCaine - Magma Copper Company
      Art Verdugo - Magma Copper Company
      F. C. Davis - Magma Copper Company
      D. C. Ridinger - Magma Copper Company
      Mike McCarthy - Magma Copper Company
      Dale E. Zabel - Magma Copper Company
      Ralph Sievwright - Attorney for Magma Copper Company
      Larry Bowerman - EPA, Region IX
      Bill Thurston - EPA, Region IX
      Steve Schwartz - BAQC
      Larry Yerino - PEDCo Environmental, Inc.
      Vishnu Katari - PEDCo Environmental, Inc.

 As stated during the meeting, the purpose of the visit was
 to inspect reverberatory furnace operations at the smelter,
 including charging practices and the flue gas handling and
 control system, and also to survey the available space for
 an add-on emission control system in the vicinity of the
 current system.

 Art Verdugo and Mike McCarthy of Magma showed us the re-
 verberatory furnace and its emission control system.  All
 three reverberatory furnaces were in operation during our
                             E-2

-------
                               -2-
inspection.  Furnace No. 1 was being charged with concen-
trate delivered by a conveyor belt system.  An operator
manually opened the furnace doors on the side  (three at a
time) to allow the concentrate to drop into the furnace.  As
each charge dropped into the furnace, it produced a big
cloud of dust.

The three reverberatory furnaces are located in parallel,
from south to north.  After the concentrate is mixed with
precipitator dust, limerock, and flux, it is stored in
gravity-type feeders.  It is transported from storage to the
furnaces by conveyor system.  The addition of converter slag
to the concentrate is necessary because it aids in the
formation of a bottom bed in the furnace.  Matte, the
furnace product, is tapped near the center of the furnace,
is gravity-fed into laddies, and then is moved to the
converter area.  The slag formed in the furnace is tapped
near one end of the furnace and flows into slag pots, which
are hauled by rail car to the slag dump.

Exhaust gases from each furnace pass through a set of two
waste-heat boilers into a common balloon flue, then through
an electrostatic precipitator header to three independent
electrostatic precipitator units.  The treated gases pass
into a common header and then are vented through a natural
draft stack operating at a negative pressure of from 2.0 to
2.5 inches water.  A manually controlled header installed
underneath the gas header collects any dust carryover.  A
bypass duct connects the balloon flue to the common header
for the treated gases.  A duct system is installed to take a
bleed stream of treated gases to an SCRA* pilot plant, which
is not operating at present.

Each electrostatic precipitator consists of three fields,
and two hoppers, is equipped with inlet and outlet dampers,
and each ESP can perform independently.  According to Magma
personnel, each precipitator inlet is installed with one
diffusion plate.  They do not know, however, whether the
transformer-rectifier (TR) units are working efficiently, or
whether any air infiltration sources are present in the
entire gas handling and treatment system.

Heavy material collected in the waste-heat boilers is
charged to the converter, and fine dust is charged to the
reverberatory furnace.  The ducts are periodically cleaned
to remove settled dust.   The matte and slag areas are
hooded, and the collected gases are exhausted directly to
* Smelter Control Research Association.
                            E-3

-------
                               -3-
individual stacks.  Magma personnel believe that particulate
emissions from matte tapping are negligible; therefore, they
have never conducted particulate testing under the hood
system.  Some sulfur dioxide may be emitted from the tapping
hood area.

Magma personnel indicated they have never tried to pelletize
the converter slag before adding it to the reverberatory
furnace.

Usually five converters are operated and one is held as a
spare during the operation of all three reverberatory
furnaces.

Magma is planning to convert their reverberatory furnaces
from oil and gas firing to coal firing.  They predict that
they may have to improve the waste-heat boiler system and
flue gas handling system.  They are also prepared to install
any required add-on control system.  The EPA Region IX
informed Magma that the facility will be subject to NSPS
regulations.  EPA is planning to conduct particulate sam-
pling on the reverberatory furnaces before and after con-
version to coal.  The Arizona EPA in planning to conduct
particulate sampling on September 12 and 13, 1977.

Our inspection revealed that enough space is available in
the vicinity of the current control system and stack to
install any necessary add-on equipment.  The following
figure (not in scale) depicts the location of the current
control system and indicates the space available for add-on
equipment.

Magma will make available to PEDCo (through EPA Region IX)
general drawings of the current particulate control system
and different material stream analyses.
                           E-4

-------
\/e
f o t
Loc
                                             t>
__   cf-
                                                            f j r
    E-5

-------
                     PEDCo ENVIRONMENTAL, INC.

                          MEMORANDUM


TO=  Project File                                DATE: August 3, 1977

SUBJECT:   Trip Report -  Phelps-Dodge Copper      FROM'-  V. Katari
         Company,  Ajo on 7/21/77

FILE'   3287-B                                    «:  L. Yerino
                                                   T. Devitt
                                                   R. Gerstle
  On July 21,  1977,  Larry Yerino and I visited the Phelps-
  Dodge Copper Company at Ajo,  Arizona.   Messrs.  Larry Bower-
  man and Bill Thurston of EPA  Region IX accompanied us to the
  plant and Mr.  Steve Schwartz  of BAQC joined us  there.  The
  purpose of the visit was to acquire data on the reverbera-
  tory furnace operating procedures and the air pollution
  control equipment  operation,  and to survey the  available
  space for an add-on control system in the vicinity of the
  current control equipment.

  Mr.  F.  R.  Rickard,  the smelter manager,  briefly described
  the reverberatory  furnace operation and later showed us the
  furnace and  its control system.

  The reverberatory  furnace burners are designed  for burning
  natural gas, or diesel oil, or No.  6 oil.   The  plant has not
  been operating because of a strike, but the reverberatory
  furnace has  been kept hot by  firing natural gas, a necessary
  step to keep the silica arc support inside the  furnace from
  falling down;  rebuilding the  arc would require  4 to 5 weeks.
  Phelps-Dodge Copper Company maintains a smelter repair team
  at the plant.

  Phelps-Dodge Copper Company at Ajo, usually smelts con-
  centrate prepared  from its  own mined ore;  however, custom
  concentrates are sometimes  smelted on an optional basis,
  depending upon the furnace  availability (production never
  exceeds design capacity).

  The concentrate is brought  to the plant, stored in cans, and
  taken through a double arc  gate to the hopper.   Its typical
  moisture content is 6 1/2 to  7.0 percent.   The  concentrate
  is charged onto a  variable-speed belt conveyor  and is
  dropped into a small feed hopper of a slinger machine.  Lime
  rock addition to the furnace  is continuous.  The flue dust
                              E-6

-------
                              -2-
collected in the reverberatory furnace electrostatic pre-
cipitator is recycled back to the furnace.  The usual
material charging rate to the furnace is 1-1/2 to 2 tons/min
when the slinger machine is in operation.  About 700 tons of
charge (of which about 94 percent is concentrate)  is fed to
the reverberatory furnace per day.  Table 1 presents a
typical material charge.  The elapsed time between charging
the furnace to tapping the matte is usually 4 hours.
Approximately 30 to 36 taps are made per cycle.  The furnace
has three matte tapping holes (two operate at a time), and
one slag tapping hole.  The matte is tapped into laddies,
picked up by overhead cranes and are charged to one of three
converters.  Usually two converters are kept hot (one
operates at a time).  The converter cycle time is roughly 6
hours.  The number of converter chargings corresponds to the
number of tappings.

Exhaust gases from the reverberatory furnace pass through a
pair of waste-heat boilers, then enter a balloon flue and a
common plenum chamber for the two independent, parallel,
electrostatic precipitator units.  A heavy load of dust is
accumulated on the waste-heat boiler walls.  The dust is
removed from the walls every 2 hours by the use of soot
blowers.   The waste-heat boilers do not contain radiant
cooling sections, these are required to recover heat from
flue gas generated by smelters using coal as fuel.   The gas
collection system was designed orignally so that 50 percent
of the gas stream from the electrostatic precipitator could
be directed through the DMA SC>2 absorption plant,  and the
remaining 50 percent could be exhausted to the stack.
However,  at present the duct arrangement for the gas stream
going to the DMA plant is completely cut off, so the entire
gas stream from the precipitator is exhausted through the
stack.  An ID fan installed downstream of the precipitator
moves the gases through the stack.  A flip-flop damper is
installed in the duct system so that the gases can be guided
either through the balloon flue or the duct work.

The reverberatory furnace matte and slag tap areas are
hooded, and the collected gases containing particulate
matter are exhausted directly to the smelter main stack.

The acid plant is not operating, but it is being kept in
operating condition by continuously checking for leaks and
material corrosion.

Any heavy particulate material dropped out in the waste-heat
boiler is recycled back to the converter; and the fine dust,
                             E-7

-------
       Table 1.  MATERIAL CHARGE TO THE REVERBERATORY

                  FURNACE ON JUNE 15, 1977

     Material*                          Amount

Concentrate                               636

Precipitates                                9

Lime rock                                  31

Flue dust from reverberatory furnace        7

Reverts                                     7

Flue dust from converter precipitator       6
* In addition, 341 tons per day of converted slag is added.
  Metallurgical Department of Phelps-Dodge Copper Company has
  analyses of individual material changed.  The data can be
  obtained on request.
                             E-8

-------
                              -3-
depending on the quality, is recycled back to the reverbera-
tory furnace or the concentrator.  Dust collection in the
waste-heat boilers is up to 6 tons per day on vertical
tubes;  the amount collected on water wall sections is not
known.   Analysis of the dust collected in the waste-heat
boiler hopper is available on a monthly composite basis.

According to Mr. Rickard, the furnace design is not suitable
for using pelletized converter slag as is the practice at
Kennecott Copper Company.  In his opinion, converter slag is
used in the reverberatory furnace primarily for charge
recovery purposes and may not improve environmental conditions

Because the converter operation is exothermic, it is es-
sential to burn all the silica in the converter.  For this
reason the heavy particulate from waste-heat boilers is
charged to the converters.

Mr. Rickard expressed that the flip-flop damper, the man-
holes on the ESP, and the access doors to the hoppers are
possible sources of air infiltration.  The expansion joint
on the downstream side of the ID fan failed this year and
was a source of air infiltration.  The reason for the
difference in measured velocity through the two ducts could
be due to size differences in the hanging dampers installed
in each duct.

Corrosion problems are being experienced from the electro-
static precipitator on the converter, usually when the flue
gas temperature is lower than 465°F, because of formation of
sulfuric acid.

Mr. Rickard does not know if the two new mist precipitators
installed can be utilized as add-on equipment to treat
reverberatory furance gases.
                         E-9

-------
BIBLIOGRAPHIC DATA
SHEET
                   1. Report No.
                     EPA 909/9-78-001
                  3. Recipicnt'c Accession No.
4. Title and Subtitle
  Evaluation of  Particulate Matter Control Equipment for
  Copper Smelters
                                                                   5. Report Date
                                                                   February 1978  (issue)
                                                                   6.
7. Author(s) Vishnu  S.  Katari, L. Yerino,
 Edmund S. Schindler.  and T. W. Devitt
                                                                   8. Performing Organization Rept.
                                                                     No- 3270-1-X
9, Performing Organization Name and Address
 PEDCo Environmental,  Inc.
 11499 Chester Road
 Cincinnati, Ohio   45246
                                                                   10. Project/Task/Work Unit No.
                                                                    Task 24
                                                                   11. Contract/Grant No.

                                                                   No.  68-01-4147
12. Sponsoring Organization Name and Address
 U.S. Environmental  Protection Agency,  Region  IX
 Enforcement Division (Task Manager-Larry Bowerman)
 215 Fremont Street
 San Francisco,  California  94105
                                                                   13. Type of Report & Period
                                                                     Covered
                                                                   Final (1977)
                                                                   14.
 15. Supplementary Notes
5. supplementary Notes
EPA Region IX Project  Officer for  this  report was Larry Bowerman
 fo._A;b>tracts  In  1977  at the request  of  EPA, Region  IX,  Enforcement  Division, PEDCo En-
 vironmental, Inc. conducted an investigation of particulate matter control equipment
 which could be installed at two copper smelters located in Arizona.   The two  smelters
 investigated were the New Cornelia Branch copper  smelter of the Phelps Dodge  Corpora-
 tion located in Ajo,  Arizona and the  Magma Copper  Company copper  smelter located in San
 Manuel, Arizona.  The purpose of the  investigation was to determine the technical fea-
 sibility of compliance and the cost of control equipment necessary to comply  with the
 particulate matter  control regulation.  Fabric filters, scrubbers,  dry and wet  electro-
 static precipitators  were investigated with the assistance of Industrial Gas  Cleaning
 Institute member companies (through Task 2 of EPA  Contract No. 68-02-7532, Office of
 Air Quality Planning  and Standards, Strategies and Air Standards  Division).   This re-
 port includes  a description of each smelter; an analysis of available emission  data for
 each smelter;  and a summary of capital costs, annual  costs and technical control equip-
 ment data for  9 control options for each smelter.	
 17. Key Words and Document Analysis.  17a. Descriptors
 Copper                   Smelter
 Particulate Matter

 Instack Filter

 Control Equipment
 Description and Cost
 Scrubber
'7b. Identifiers/Open-Ended Terms
Air Pollution Control

Operating Data

Control Equipment  Costs
                        Emission Measurement

                        Sulfur Dioxide

                        EPA Methods 5 and  8
                        Dry Electrostatic
                         Precipitator
                        Air Pollution


                              Stationary Source
                              Emission Results
                              Emission Control
Sulfur Trioxide
Fabric Filter
Wet Electrostatic  Precipitator
        Sampling Methods
'7c. COSATI l-ield Or
               oup
                       13B,  14A, 14D,  11F
'8. Availability Statement
Release Unlimited
                                                       19. Security Class (This
                                                          Report)
                                                            UNCLASSIFIED
                                                        20. Security Class (This
                                                           Page
                                                             UNCLASSIFIED
                            21. No. of Pages
                               256
                                                                             22. Price
FORM NTis-33 (REV. 10-731  ENDORSED BY ANSI AND UNESCO.
                                                  THIS FORM MAY BH REPRODUCED

-------
    INSTRUCTIONS  FOR  COMPLETING FORM  NTIS-35         (Bibliographic Data Sheet based on COSATI
   Guidelines to Format Standards for Scientific and Technical Reports Prepared by or for the Federal  Government,
   PB-180 600).

    1.  Report Number.  Each individually bound report shall carry a unique alphanumeric designation selected by  the performing
       organization or provided by the sponsoring organization.  Use uppercase letters and Arabic numerals only.  Examples
       FASEB-NS-73-87 and FAA-RD-73-09.

    2.  Leave blank.

   3.  Recipient's Accession Number.  Reserved for use  by each report recipient.

   4.  Title and Subtitle.  Title should indicate clearly and briefly the subject coverage of the report, subordinate subtitle to the
       main title. When a report is prepared in more than one volume, repeat  the primary title, add  volume number and include
       subtitle for the specific volume.

   5-  Report Date. !• ach  report shall carry a date indicating at least  month and  year.  Indicate the basis on which it was selected
       (e.g., date of issue,  date of approval, date of preparation, date published).

   6-  Performing Organization Code.  Leave blank.

   7.  Aothor(s).   Give name(s) in conventional order (e.g.,  John R. Doe, or  J.Robert  Doe).  List author's affiliation if it differs
       from the performing organization.

   8.  Performing Organization Report Number.  Insert if performing  organization wishes to assign this number.

   9.  Performing Organization Name and Mailing Address. Give name, street, city, state, and zip  code.  List no  more than two
       levels of an organizational hierarchy.  Display the name of the  organization exactly as  it should appear in Government in-
       dexes  such as  Government Reports Index (GRI).

  10.  Project/Tosk/Work Unit Number.  Use the project, task  and work unit numbers under which the report was prepared.

  11.  Contract/Grant Number.  Insert contract or grant number under which report was  prepared.

  12-  Sponsoring Agency  Name and  Mailing Address.  Include  zip code. Cite main sponsors.

  13-  Type of  Report and Period Covered.  State  interim, final,  etc.,  and, if applicable, inclusive dates.

  14.  Sponsoring Agency  Code.  Leave blank.

  15.  Supplementory Notes.  Enter  information not included  elsewhere but  useful, such  as:  Prepared in cooperation with . . .
       Translation of       Presented at conference of     . To be published in   .   Supersedes . . .       Supplements
       Cite availability of related parts, volumes, phases, etc. with  report number.
  16.  Abstract.  Include a brief (200 words or less)  factual summary of the  most significant  information contained  in the report.
       II  the report contains a significant bibliography or  literature survey, mention it here.

  17.  Key Words and  Document Analysis,  (a).  Descriptors.  Select from the  Thesaurus of Engineering  and Scientific Terms  the
       proper authorized terms that identify  the major  concept of  the  research  and are sufficiently specific and precise  to be used
       as  index entries for cataloging.
      (b).  Identifiers and Open-Ended Terms.  Use identifiers for project names, code names, equipment designators, etc.   Use
       open-ended terms written in descriptor form for those subjects for which no descriptor exists.
      (c).  COSATI Field/Group.   Field and Group assignments are  to be taken from  the  1964 COSATI  Subject  Category  List.
       Since ihc majority of  documents are multid isciplinary in  nature, the  primary Field/Group assignments)  will be the specific
       discipline, area of human endeavor, or type of physical object.  The applicat ion(s) will be cross-referenced with secondary
       Fie-Id/Group assignments that will follow the primary posting(s).

  18. Distribution Statement.  I /enote public releasability, for example "Release unlimited",  or limitation for reasons other
       than security.  Cite any  availability to the public,  other than  NTIS, with address, order  number and price, if known.

  19 & SO. Security Classification.   Do  not submit classified reports  to the National Technical Information Service.

  21.  Number of  Pages. Insert the  total number of pages, including introductory pages, but excluding distribution list, if any.


  22.  NTIS  Price. Leave  blank.
FORM NTIS-35 (REV  10-73)                                                                                   USCOMM-DC 8263-P74

-------