United States
            Environmental Protection
            Agency
            Office of Emergency and
            Remedial Response
            Washington DC 20460
&EPA
            Superfund
                        OSWER Directive 9380.0-3
Guidance
Document for
Cleanup of Surface
Tank and Drum Sites

-------
                                                 OSWER Directive 9380.0-3
               GUIDANCE  DOCUMENT FOR  CLEANUP
               OF SURFACE  TANK  AND DRUM  SITES
                               Prepared  by:

                       CAMP DRESSER & McKEE INC.
                    WOODWARD-CLYDE  CONSULTANTS
                          ROY F. WESTON, INC.
                  C.C. JOHNSON AND  ASSOCIATES. INC.
                              Project Team
                Jeffrey A. Caaala (Camp  Dresser & McKee)
                Richard C. Cote (Camp Dreaaer & McKee)
          Eward P. Hagarty, P.E. (C.C. Johnson &  Associates, Inc.)
                Edward P. Kunce  (Camp Dreaaer & McKee)
          Leonard C. Sarapas, P.E. (Woodward-Clyde Consultants)
                     John W. Thoraen (Roy F.  Weaton)
                       Work Assignment Managera

                      Edwin Barth and Brint Bixler
                  U.S. Environmental Protection Agency
               Office of Emergency and Remedial Response

                           401  M Street. S.W..
                         Washington, D.C. 20460
This document has been prepared for the U.S. Environmental Protection Agency
                   under Contract No. WA  68-01-6939
                              May 28, 1985

-------
                             TABLE OF CONTENTS


Section                                                              Page

  FOREWORD	 vi i

  1.0    INTRODUCTION 	 1-1

         1.1  Purpose 	 1-1

         1.2  Intended User 	 1-2

         1.3  Organization of Guide  	 1-3

  2.0  LIMITED REMEDIAL INVESTIGATION 	 2-1

         2.1  Develop Site Description and Data Base 	 2-1

              2.1.1  Obtain Available Data 	 2-1
              2.1.2  Review and Evaluate Available Data 	 2-6

         2.2  Site Familiarization and Project Approach 	 2-7

              2.2.1  Prepare Preliminary Base Map 	 2-8
              2.2.2  Prepare Initial Health and Safety Guide 	 2-10
              2.2.3  Prepare Community Relations Plan 	 2-12
              2.2.4  Identify Potential Remedial Technologies 	 2-12

         2.3  Perform Initial Site Characterization 	 2-13

              2.3.1  Conduct Initial Site Visit 	 2-14
              2.3.2  Determine if an Immediate Threat Exists 	 2-16
              2.3.3  Conduct Preliminary Exposure Assessment 	 2-19
              2.3.4  Determine Need  for Continued Limited Activity . 2-20
              2.3.5  Define Data Needed to Conduct Limited
                      Feasibility Study 	 2-21

         2.4  Conduct Detailed Field Investigation 	 2-22

              2.4.1  Prepare Project Operations Plan 	 2-24
                     2.4.1.1  Sampling Plan 	 2-24
                     2.4.1.2  Health and Safety Plan 	 2-32
                     2.4.1.3  Quality Assurance/Quality Control
                               Plan  	 2-36
              2.4.2  Perform Tank and Drum Survey/Inventory  	 2-37
              2.4.3  Conduct Site Characterization 	;	 2-43
              2.4.4  Conduct Sampling Program 	 2-43
              2.4.5  Review Analytical Results for Conformance
                      with QA/QC Program 	 2-45
              2.4.6  Evaluate All Data and Prepare Limited
                      Remedial  Investigation Report 	 2-46

-------
 OSWER Directive 9380.0-3
Section
                             TABLE OF CONTENTS
                                (Continued)
Page
  3.0    LIMITED FEASIBILITY STUDY 	 3-1

         3.1  Identify Major Remedial Alternatives 	 3-3

         3.2  Screen Initial Remedial Alternatives 	 3-10

              3.2.1  Evaluate Technical Reliability and
                      Feasibility 	 3-11
              3.2.2  Evaluate Environmental and Public Health
                      Effects 	 3-12
              3.2.3  Evaluate Costs  	 3-14
              3.2.4  Refine List of  Potential Remedial Action
                      Alternatives 	 3-15

         3.3  Conduct Detailed Analysis of Potential Remedial
               Action Alternatives 	 3-17

              3.3.1  Perform Technical Analysis of Alternatives  .... 3-17
              3.3.2  Perform Cost Analysis of Alternatives  	 3-19
              3.3.3  Perform Environmental and Public Health
                      Analysis 	 3-22
              3.3.4  Perform Regulatory and Institutional Analysis
                      of Alternatives  	 3-23

         3.4  Conduct Comparative Summary of Potential Remedial
               Action Alternatives 	 3-24

         3.5  Prepare Limited Focused Feasibility Study  	 3-27

  4.0    TANK AND DRUM SITE REMEDIAL DESIGN/REMEDIAL ACTION 	 4-1

         4.1  Approach 	 4-1

         4.2  Contracting Procedure  	 4-2

              4.2.1  Fixed Price (Lump Sum) Contract 	 4-2
              4.2.2  Unit Price Contract 	 4-3
              4.2.3  Time and Materials Contract 	 4-4

         4.3  Contract Provisions 	 4-4

              4.3.1  Change Orders 	 4-5
              4.3.2  Special  Provisions 	 4-8

         4.4  Design Requirements 	 4-9

-------
                                                            OSWER Directive 9380.0-3
                             TABLE  OF  CONTENTS
                                 (Continued)
Section                                                               Page

  5.0    REFERENCE GUIDE  	 5-1
APPENDIX A - EXAMPLE OF A SITE  PERSONNEL  PROTECTION AND SAFETY
             EVALUATION FORM  FOR  USE  DURING  INITIAL SITE VISITS

APPENDIX B - EXAMPLE OF A DRUM  HANDLING,  DRUM  SAMPLING, SPECIAL
             WASTE HANDLING,  AND  TANK SAMPLING PROTOCOL

APPENDIX C - EXAMPLE OF A BULKING AND CONSOLIDATION PROTOCOL

-------
 OSWER Directive 9380.0-3
                               LIST OF  FIGURES
 Figure

 2-1       Surface Tank  and  Drum RI  Logic  Diagram  	  2-2

 2-2       Existing Conditions,  Base Map,  Examples  from  an  NPL  Site  ..  2-9

 3-1       Logic  Diagram 	  3-4





                                LIST OF TABLES

 Table                                                                 Page

 2-1       Example of  a  Simple  Procedure for  Evaluation  of  Short-
          Term Hazards  at Tank  and  Drum Site 	  2-18

 2-2       Examples of Data  Needs for Evaluation of Potential
          Remedial  Activities  	  2-23

 2-3       Categorization of Waste Types at an  NPL  Site  Based  on
          Random Sampling of Drums  	  2-29

 2-4       Waste  Treatment Disposal  Categories  	  2-31

 2-5       Example of  Procedures for Tank  and Drum  Sampling:
          Safety Aspects 	  2-34

 2-6       Aspects  of  Aerial  and Ground Drum  Surveys 	  2-38

 2-7       Example Drum  Inventory Form 	  2-40

 3-1       Categories  and Potential  Treatment/Disposal  Technologies  ..  3-7

 3-2       Final  Remedy  for  Hypothetical Abandoned  Tank  Site  	  3-26

 3-3       Limited Feasibility  Study Report Format  	  3-28

4-1       Table  of Contents for Drum Disposal  Technical
          Specifications 	  4~10

-------
                                                           OSWER Directive 9380.0-3
                                  FOREWORD
A U.S. EPA  1982 survey of disposal practices at uncontrolled hazardous
waste sites indicated that over 20 percent of the sites surveyed had drum
related problems  (EPA, 1983).  Although  remedial action has been
implemented at many of these sites, these problems still remain a major
threat to the public health and environment.  This guidance document was
prepared to assist on-scene federal, state and local officials and private
firms that  plan and implement  remedial actions at National Priorities List
(NPL) sites which contain hazardous wastes in surface tanks and drums.

The primary purpose of this document is  to provide guidance on carrying out
concurrent  remedial planning activities  and accelerating project
implementation for the cleanup of surface tanks and drums containing
hazardous waste.  This document is designed to be used in conjunction with
EPA's guidance documents on conducting remedial investigations and
feasibility studies (EPA 1985a,b).

This guidance manual will provide the user with a systematic approach to
remedial  action for hazardous wastes stored in tanks and drums.  However,
there are many unique and potentially hazardous conditions on tank and drum
sites which require very specialized considerations.  This manual  does not
substitute for the services of a competent professional  but is intended to
serve as  a comprehensive planning and technical guidance tool.
                                    vn

-------
                                                           OSWER Directive 9380.0-3

                             1.0  INTRODUCTION
1.1  PURPOSE

This guidance document addresses remedial  actions for the cleanup of
surface tanks and drums containing hazardous wastes, as well  as grossly
contaminated soils associated with the tanks and drums.  Guidance is
provided for a limited remedial  investigation (limited RI), limited
feasibility study (limited FS),  and contracting procedures.  A limited
remedial action addresses one "operable unit" at a site that, in the
estimation of the lead regulatory agency can be investigated, evaluated and
implemented in a relatively short time period.  An operable unit is one
definable problem area or source of contamination at a site that can
basically be addressed independently of other site issues/problems.  It can
typically be thought of as one piece of the total remedial action at a
site.

This is one of three guidance documents on specific remedial  actions.  The
second guidance document is for cleanup of surface impoundments (e.g.,
pits, ponds, and lagoons).  The third addresses development of alternative
water supplies.  All three manuals may be applicable at a complex site.

While the term "remedial action" is used, this document applies either to
removal or remedial actions, since both require a similar decision process.
Limited RI/FS are typically the first steps in the remedial response at a
National Priorities List (NPL) site and must be consistent with the long
term remedy.  Remedial actions, as defined by the National Contingency Plan
(NCP) in Section 300.68(a), "... are those responses to releases on the NPL
that are consistent with a permanent remedy to prevent or mitigate the
migration of a release of hazardous substances into the environment."  Any
remedial action contemplated for implementation at a site must be cost-
effective, stabilize the situation, prevent or limit the  extent of contami-
nation, and/or provide temporary containment.
                                     1-1

-------
OSWER Directive 9380.0-j

Depending  on  the  urgency of  response, removal actions may be taken without
the  preparation of  a  limited  RI/FS, although many of the issues addressed
in this  document  will  be assessed  in an expedited manner.

A typical  limited remedial investigation/feasibility study of this type
should take 5-7 months to complete, if sampling is required to supplement
existing data.  For planning  of a  single operable unit, one can assume a
limited  RI  may last 4-5 months while the limited FS should be completed in
1-2  months.  These  time estimates  are very general and can vary consider-
ably depending on many factors.  Typically the RI and the FS can be
performed  concurrently, with  the limited FS finishing shortly after the end
of the limited RI.

1.2   INTENDED USER

This  guidance manual  is intended to be an aid to state and federal staff
and  private firms for the implementation of a remedial action for the
cleanup  of  hazardous wastes contained in above-ground tanks and drums.  The
manual is  informative rather  than  prescriptive in nature.  The basic
objectives  are to provide a concise description of the necessary steps to
implement surface remedial actions for the cleanup of tanks and drums
within the  provisions of the  NCR.

It must  be  emphasized that this guidance is not to be used as an absolute
reference.  It should be supplemented with other EPA guidance documents and
technical reports/references  as appropriate.  Refer to Section 5.0 for
references  relevant to the performance of a limited RI/FS.  This manual
should be used under the direction of an engineer or scientist experienced
in hazardous waste  remedial projects or equivalent.

Revisions of this manual will be provided, as necessary, to assure
compliance with the NCR.  Revisions will be made available through EPA for
intended users.
                                     1-2

-------
                                                           OSWER Directive 9380.0-3
 1.3  ORGANIZATION OF GUIDE

 This manual  is organized into three major sections:   (1) limited remedial
 investigation, (2)  limited  feasibility study, and  (3) contracting pro-
 cedures.  These sections represent major activities to be conducted for the
 cleanup of surface  tanks and drums.  A detailed review of the steps to
 conduct a remedial  investigation to estimate the characteristics and
 quantities of those above-ground wastes stored in  tanks and drums is
 presented in Section 2.0.   The feasibility study steps are presented in
 Section 3.0; these  steps will lead to the evaluation  and recommendation of
 a cost-effective and environmentally sound remedial alternative for wastes
 stored in drums and tanks.  Contracting procedures, presented in Section
 4.0, include a review of typical remedial design and  remedial action issues
 that may be unique  to tank  and drum sites.

 The guidance presented in this manual represents a compilation of existing
 approaches derived  from similar remedial actions implemented at many sites
 where tanks and drums were  handled as a single operable unit.  However, it
 will be necessary to tailor this approach to meet  the user's particular
 needs and the site  specific characteristics.

 Flow diagrams have  been developed to present a logical sequence of activ-
 ities for the implementation of this type of remedial action.  The flow
 diagrams present the major  activities for remedial investigation and
 feasibility study.  The diagrams are located at the beginning of each major
 section.  Each major activity on the flow diagrams is denoted by a rectan-
 gle.  Diamonds represent decision points and circles  indicate starting and
 ending points for each phase of the entire project.   These activities are
 cross referenced by number t.o the text in this manual.  For example, the
 activity "Conduct Summary Evaluation" is referenced to Section 3.4.1 in the
text, which details the necessary steps to implement  this activity.  The
user may start anywhere on the flow diagram as long as the predecessor
 activity has been completed.
                                     1-3

-------
OSWER Directive 9380.0-3

The execution of a limited RI/FS for a single operable unit is designed to
be very flexible in practice.  While many of the component activities are
similar to a full RI/FS the user should tailor the approach based upon site
specific conditions and other previous and/or ongoing remedial action
activities.  A limited RI/FS for a surface tank and drum site could be
initiated during the execution of a full RI/FS or in parallel with other
limited RI/FSs (e.g., alternative water supply activities).
                                      1-4

-------
                                                           OSWER Directive 9380.0-3

                     2.0  LIMITED REMEDIAL INVESTIGATION
After a decision has been reached to evaluate surface tank and drum cleanup
activities at an NPL site, a limited remedial investigation (limited RI)
should be performed to provide the information necessary to further define
the site, provide the basis to evaluate conditions on the site, and to
develop a remedial program to mitigate potential  adverse public health and
environmental impacts.  The four main components  of a limited RI are:

    1.  Develop site description and data base (Section 2.1)
    2.  Site familiarization and project approach (Section 2.2)
    3.  Perform initial site characterization (Section 2.3)
    4.  Conduct detailed field investigation (Section 2.4)

A description of these tasks and the associated decision points are
presented below.  The logic flow diagram for the  RI is presented in Figure
2-1.

2.1  DEVELOP SITE DESCRIPTION AND DATA BASE

The initial  component of the limited RI is to obtain available data on site
conditions (e.g., the nature, amount, and container condition of tank  and
drum wastes  on-site and unique site features) and to make an initial
evaluation of these data related to cleanup activities for the site.

2.1.1  OBTAIN AVAILABLE DATA

Purpose

Data are collected for the following reasons:

    •  To better define site conditions so that a health and safety plan
       and sampling plan can be prepared (Section 2.4)
                                     2-1

-------
        OSWER Directive 9380.0-3
Figure 2-1.     Guidance flow diagram for surface tank and drum limited remedial investigation.
Obtain Available Data

• Background Data
   —facility description
   —site history
   —past operation and
    disposal practices
   —physiography/
    topography
  —soils/geology
  —climate/weather
  —surface water
  —ground water
  —ecology/land use
  —sensitive receptors
• Agency Data
  —RAMP
  —PASR
  —health & safety plans
  —chronology of agency
    involvement
Review and Evaluate
Available Data

 • Summary maps, tables,
   matrices
 • Executive Summary
 • Evident data gaps
 • Quality of data
                                                   2.1.2
                     2.1.1
Prepare Preliminary
Base Map


 • Underground/overhead
   utilities
 • Availability of water and
   electrical hookups
 • Nearby structures and
   residences
 • Drum & tank locations
 • Location of known
   potential hazards
 • Property lines/
   boundaries
 • Access/security
 • Buildings/structures/
   piping
 • Existing wells and
   sampling locations
                                                                                   2.2.1
                                                             Prepare/Revise Health &
                                                             Safety Plan
                                 Training
                                 Medical screening
                                 Protective and
                                 monitoring equipment
                                 Entry/exit procedures
                                 On-site procedures
                                 Emergency response
                                 Site walkover
                                 (if necessary)
                                                                                   2.2.2
                                                             Prepare Community
                                                             Relations Plan
                                                                                            Identify Potential Remedial
                                                                                            Technologies
Conduct Initial Site Visit

 • Verification of existing data
 • Identification of unusual
   features
   —spills/stained soils
   —evident environmental
     stress/impact
   —special wastes
     (radioactive/explosive)
   —other wastes (drums/
     tanks; closed
     impoundments)
 • Preliminary inventory
   —tanks, drums, pits,
     ponds, and lagoons
 • Access/egress/security
                                                                                                                    2.3.1
                                                                                   2.2.3
                                                           2-2

-------
                                                                                           OSWER Directive 9380.0-3
Figure 2-1.     (continued)
         Is There
      an lmmediate\No
     Public Health or
      Environmental
         Threat?
    Notify Agency and
    National Response
         Center
     as Appropriate
        Continue
      Investigation
   When Appropriate
Conduct Preliminary
Exposure Assessment

• Waste characteristics
• Migration pathways
• Potential receptors
                                           2.3.3
    Is
 Existing
Data Base
Sufficient
for Limited
Feasibility
  Study?
 etermme
 Need for
Continued
 Limited
  RI/FS
Conduct Limited
Feasibililty Study
                            Handle as
                           Part of Full or
                          Expanded RI/FS
                                                          Prepare Project Operations Plan
                                                                                      Sampling plan
                                                                                      Health and safety plan
                                                                                      QA/QC plan
                                                                                      Submit Plans for Agency
                                                                                        Review and Revisions
                                                                                    H>
                                                         2-3

-------
         OSWER Directive 9380 0-3
Figure 2-1.    (continued)
   'repare for Field Activities

   • Indoctrination of field
     personnel
     —site conditions
     —sampling plan
     —activities plan
     —facilities layout
     —health and safety plan
     —emergency
       contingency plan
     —decontamination and
       security procedures
     —documentation/site
       log procedures
     —sample handling and
       chain-of-custody
       procedures
   • Mobilization of field
     facilities
     —office and changing
       trailers
     —decontamination
       stations (personnel
       and equipment)
     —materials and
       equipment
     —site security
     —fixed air monitoring
       stations
Perform Survey/Inventory
of Tanks and Drums
   Drum count
   Condition
   Type
   Isolate special wastes
   Accessibility
   Structural integrity
                      2.4.2
Conduct Site
Characterization
   Survey/property
   Line
   Structures
   Utilities
   Major areas of
   contamination
                       2.4.3
Conduct On-Site
Sampling (Optional)

 • Ship to lab for analysis
 • Conduct on-site analysis
Review Analytical Results
   for Compliance with
 Quality Control Program
                                                     2.4.5
  Evaluate All Data and
Prepare Limited Remedial
   Investigation Report
                                                                                   2.4.6
                       2.4.4
                                Does
                           Additional Data
                      Confirm Basis for Limite
                           Source Control
                              Action?
                              Handle as
                            Part of Full or
                           Expanded RI/FS
                                                            2-4

-------
                                                          OSWER Directive 9380.0-3
    •  To provide a basis for initial site evaluation and identification of
       potential remedial alternatives (Section 2.2.4 and 2.3.1)
    •  To perform an assessment of current on-site hazards (Section 2.3.3)
    •  Identify and evaluate existing data base so that future field
       activities can be planned to fill  data gaps (Section  2.3.6)
    •  To develop a data base for design of an ultimate remedial program
       (contract documents, plans and specifications) (Section 4)
    •  Provide data for evaluation of remedial alternatives  (Section 3)

Techniques

There are many federal, state, and local  agencies which may  have pertinent
information useful in conducting a limited RI/FS at a tank and drum site.
Most of the available data may be general in nature but possibly useful in
establishing a baseline.  Other data sources that may be particularly
useful in obtaining more specific information on the conditions of a site
include:

    •  Site history, ownership, operation/disposal practices (past and
       present, from past owners, operators, and/or generators)
    t  Sensitive receptors in the vicinity of the site
    •  Initial planning documents, such as Remedial Action Master Plan if
       available
    •  Preliminary assessment/site inspection data
    •  Aerial photos of the site
    t  Hazard Ranking System (MRS) documentation

Many other agencies and potential data sources along with types of
information that's generally available from these sources are reviewed in
the Remedial Investigations Guidance Document (EPA, 1985).

Limitations

Effort should not be wasted on obtaining data that are not applicable  to
the scope of the project or obviously generic or duplicative  in  nature.

                                     2-5

-------
 OSWER Directive 9380.0-3
 2.1.2  REVIEW AND EVALUATE AVAILABLE DATA

 Purpose

 The data should be evaluated and summarized in formats that are easy  to
 review for individuals not involved in the collection process.   By
 reviewing and evaluating the available data, an understanding of site
 conditions will be developed and evident data gaps will  be identified.
 During this activity, the quality (i.e., accuracy and precision) of the
 data and its conformance with the quality assurance/quality control
 protocols under which it was collected, should be assessed.

 Techniques

 At this early stage it is important to focus on compiling  as  much  informa-
 tion as possible on the quantity and types of wastes  and the  condition of
 tanks and drums found on site.

 Whenever possible, available data should be summarized in  graphical,
 tabular, or matrix formats.   These formats are compact and allow for
 efficient presentation, comparison, and utilization of large  amounts  of
 data.   A written summary is  also valuable for conveying data  trends and
 general  conditions.   All  summaries, whether graphical, tabular  or  written,
 should identify both  what is known — conditions  at the site  — and what is
 not  known —  evident  data gaps.

 An important  part  of  reviewing and evaluating the available data is an
 assessment  of its  reliability -- the extent to which  the data represent
 site conditions.   The  dates  of maps,  drawings, and plans should be checked;
 sampling  locations should be evaluated for representativeness.   Analytical
 data should be  checked  against internal  laboratory QA/QC criteria  (blanks,
 duplicates, spike/recovery);  and the  methods of sample collection, preser-
 vation, handling, and  sampler decontamination should  be examined for
 potential irregularities.  If more than  one laboratory analyzed  samples
 from the same area on site,  the  results  should be  assessed  for consistency
and variations in methodology should  be  identified.
                                     2-6

-------
                                                           OSWER Directive 9380.0-3
Limitations

The data pool will be examined to  see  if the desired  information is avai-
lable.  A  balance must  be maintained between the need to develop a detailed
data base, the need to  concentrate on  data essential to solving environ-
mental problems at the  site, and the need to arrive at a solution ex-
peditiously.  The quality and accuracy of the data are principal  concerns
along with the relative timeliness of  various data elements.

2.2  SITE  FAMILIARIZATION AND PROJECT  APPROACH

The goal of the second  major component of the limited RI is to develop the
approach (scope) to be  followed in subsequent activities.  This is
accomplished through the preparation of preliminary maps and plans, and the
identification of potential remedial technologies.  The activities
performed  during this component are to:

    t  Prepare a preliminary base  map  of the site (Section 2.2.1)
    •  Prepare initial  health and  safety guidelines (Section 2.2.2)
    •  Prepare a community relations plan (Section 2.2.3)
    •  Identify potential remedial technologies (Section 2.2.4)

Identification of potential remedial technologies that are applicable to
site conditions is a key step in the limited RI.  By identifying these
technologies early in the overall  limited RI/FS process, subsequent data
collection and analysis can be focused on the development and evaluation of
realistic and practicable alternatives.  Preparation of a base map, a
community relations plan, and an initial health and safety plan will serve
to better define site conditions and data needs.  The health and safety
guide will  be prepared in conformance with Standard Operating Safety Guides
(EPA,  1984).
                                    2-7

-------
 OSWER Directive 9380 0-3
 2.2.1  PREPARE PRELIMINARY BASE MAP

 Purpose

 The  purpose  of this activity is to develop an accurate, detailed, up-to-
 date map  of  the  site.  The preliminary site map is needed to effectively
 plan the  field activities of the initial site visit and is used to record
 many of the  observations made during that visit.  In most cases, the
 preliminary  site map will be updated to provide a completed site base map
 which will provide an accurate representation of the drums and tanks on
 site as well  as  grossly contaminated soil areas, facilities on site and
 other key physical features to meet all limited RI/FS requirements.

 Technique

 The  preliminary  base map can be developed from existing site maps, aerial
 photos  or a  site topographic survey.  The EPA Environmental Monitoring
 Systems Laboratory (EMSL) in Las Vegas, Nevada can provide a wider range of
 information  on a site.  EMSL will provide:

     •  Aerial photographs and analysis for a single date
     •  Aerial photographs and analysis over time either for the site itself
        or a  larger area
     •  Topographic mapping at 1 foot to 5 foot intervals
     •  Orthophotographic mapping - a rectified photoimage with a
        topographic map superimposed

These services can be obtained through the regional EPA office.

A sample  base map is included as Figure 2-2.  Features shown on the site
map  should include:

    •   Property  lines, used to identify boundaries for site access control
        and site  security
    •   Drum number and location (noting if drums are stacked)
                                     2-1

-------
                                                                                    OSWER Directive 9380.0-3
Figure 2-2.     Existing conditions base map. example from an NPL site.
                                                                                     Property Line
                        Legend

                            Well Locations

                            Drum Areas
 Radio
 Station
                     12" Water Main
                                                                                   Not To Scale  N
                                                   2-9

-------
 OSWER Directive 9380.0-3
     •  Potential  drum staging/decontamination areas
     •  Tank locations
     •  Existing piping between  tanks
     •  Drainage patterns,  wetlands,  and  other water features
     •  Buildings  and structures
     •  Wells
     •  Access/egress points
     •  Adjacent structures/residences
     •  Prior  sampling locations (on  and  off  site)
     •  Topography
     •  Vegetation and other  environmental  features
     •  Stained  soils, pits,  ponds,  lagoons and other waste  disposal  areas

 Limitations

 Old  figures,  photos  and  maps  may  be  a  useful  source of  historic information
 but  should  not  be relied on  for current  site  conditions.  A fly-over of the
 site to  obtain  aerial  photos  may  be  necessary.

 2.2.2 PREPARE  INITIAL HEALTH AND SAFETY  PLAN

 Purpose

 An adequate protocol  to  protect personnel during the initial  site visit
 (Section 2.3.1),  data  collection  period  (Section 2.4),  and  later during
 tank  and drum cleanup, is one of  the most important aspects of the remedial
 investigation phase.   This initial health and safety guide  should be
prepared, (or revised, if available) and  administered by  a  trained
professional.
                                    2-10

-------
                                                           OSWER Directive 9380.0-3

 Techniques


 If  an  existing health  and safety plan  has  been  developed  for  prior  site

 work,  this  plan may be adequate for the initial  site  visit.   This document

 should be reviewed by  a qualified professional  using  the  existing site data

 base.   If no plan exists, guidance must be developed  based on the existing

 data.   Appendix A is a set of site personnel  protection and safety  evalua-

 tion forms  which can be used for this  purpose.   This  guidance must  include:


    •   An objective evaluation of the  goals of  the  site visit and the
        remedial  action

    t   An evaluation of site specific  hazards,  including  airborne contami-
        nants;  potential  radiological exposure;  dermal  hazards; hazards due
        to falls, electrical  shock or other traumatic  injury; hazards from
        heavy equipment operation, enclosed space entry, heat stress, etc.

    •   Medical  monitoring of personnel  going  on-site

    •   Delineation of  contaminated, decontaminated, and clean zones

    f   If tanks  are to be surveyed, specific  protocol  must be included
        describing access  procedures, how personnel  are to open and  check
        tanks,  and how  worker safety will be insured if tank structural
        integrity is uncertain.

    •   A  description of site conditions including the number and condition
        of tanks/drums,  and the nature  of wastes on  site

    •   Contingency plan  for  emergency  action  (e.g., include telephone
        numbers  and locations of local  hospitals, fire departments,  and
        police  etc.)

    •   Training  required


The user  is  referred to the  Occupational Safety and Health Guidance Manual

for Superfund  Activities  (NIOSH,  1984)  and Remedial Investigations  Guidance

Document  (EPA,  1985) and  Standard Operating Safety  Guides  (EPA,  1984) for

additional  information.


Limitations


If only limited  data describing  the potential hazard  level on site  are

available,  the health and  safety  guidance  may be excessively conservative
                                      2-11

-------
 OSWER Directive 9380.0-3
 or  inadequate to protect workers.  Any existing data or past health and
 safety plans should be field verified prior to adoption.

 2.2.3  PREPARE COMMUNITY RELATIONS PLAN

 Purpose

 A community relations plan is a prerequisite for remedial  actions at NPL
 sites because of their high public visibility and public interest.

 Techniques

 The purpose of a community relations plan is to keep the public aware of
 plans and activities related to the site and to receive input from the
 community regarding the site.  This plan includes:  a site description;
 history  of community relations activities; discussion of key parties and
 their concerns; the site specific community relations objectives;
 communications methods; a staffing and budget plan; a site mailing list;
 and work schedule.  Further guidance on these activities is provided in
 Community Relations in Superfund:  A Handbook, Interim Version (EPA, 1983).

 Limitations

 Not applicable

 2.2.4  IDENTIFY POTENTIAL REMEDIAL TECHNOLOGIES

 Purpose

 This activity plays an important role in the development of the remedial
 program and provides the basis to determine if existing data are adequate
 to  support proceeding directly to a limited FS.  A preliminary list of
 potentially applicable technologies is also prepared so that during the
 initial  site characterization, any obvious limitations to a specific
technology or alternative can be identified.  While this step occurs in the
RI  phase, it is actually the initial activity of the limited feasibility
                                    2-12

-------
                                                          OSWER Directive 9380.0-3
study phase.  This overlap in phases helps to expedite the schedule, but
more importantly improves the usefulness of data generated in the limited
RI.

Techniques

The user should use best engineering judgment and working knowledge of
remedial technologies to identify a range of potential remedial  actions.
Documents are currently available which describe remedial technologies for
the cleanup of tank and drum sites (See Section 5.0).

If the project site is a "simple site" (i.e., a site containing  less than
100 drums or a small volume of tankage, less than 10,000 gallons), one may
be able to proceed directly to a limited FS (Section 3.0) and obtain other
required data during the actual cleanup operation.  Based on the small
waste volume, the number of cost effective and feasible alternatives is
limited and obtaining a detailed and extensive data base is not  usually
necessary.

Field activities during the limited RI should be directed towards obtaining
data to aid in the evaluation of the range of remedial technologies that
can be considered feasible at this point in the study.

Limitations

Limited data may make selective identification of potential remedial
technologies difficult.

2.3  PERFORM INITIAL SITE CHARACTERIZATION

The initial site characterization is an important transitional activity
which is centered around an initial site visit.  The  limited RI progresses
from activities that are based upon existing data to activities and
decision points which use information developed from  initial field
activities.  The principal activities in initial site characterization
include:
                                    2-13

-------
 OSWER Directive 9380.0-3

     •   Performing  an  initial  site  visit  (Section  2.3.1)

     •   Determining if conditions could  result  in  an  immediate  threat
        to human  health and/or the  environment  (Section 2.3.2)

     •   Conducting  a preliminary exposure  assessment  so the  scope  of the
        limited  RI/FS  can  be  evaluated  (Section  2.3.3)

     •   Determining the need  for continued- limited  activity  based  upon
        review of additional  information  (Section  2.3.4)

     •   Defining  the data  requirements for conducting the  limited  FS
        (Section  2.3.5)


 2.3.1   CONDUCT  INITIAL SITE  VISIT


 Purpose


 The purpose of this activity  is to:


     •   Verify existing data  (e.g., estimate the number and  location of
        tanks  and condition of drums)

     •   Identify  critical  areas on-site  (e.g., possible future  drum handling
        areas)

     •   Identify  wastes which  require special care  in handling  due to high
        potential risks (e.g.,  cylinders,  lab packs, containers/drums with
        various warning labels  etc.)

     •   Gather additional  data  to support  further site evaluation  (e.g.,
        number and  type of drums, amount of waste in tanks,  areas where
        spills have occurred)


Techniques


After all the preparatory activities described  in  Section 2.2  have been

completed, the user is  ready  to enter the tank  and drum site for the

initial site visit.  While on-site, the provisions of the initial site

health and safety  plan must be strictly observed.  Furthermore, if anything

unanticipated in the health and safety plan happens, discontinue on-site

activities and re-evaluate the situation.
                                     2-14

-------
                                                           OSWER Directive 9380.0-3
The  potential  hazards associated with volatilization of some organic com-
pounds will  be assessed  utilizing a  portable organic vapor analyzer (OVA),
and/or commercially  available  portable photoionization GC.  Indicator tube
sampling  can also  be used  to provide qualitative information or grab
samples can  be collected for later analysis by a laboratory, all  of which
can  provide  important input to the design of the site safety program.  The
sample team  monitors ambient air for the specific compounds identified in
preliminary  information  to determine whether an imminent health hazard
exists.   Typically,  no waste sampling is performed during the initial site
visit.

The  following  activities may be performed during the initial site visit:

     •  Estimate number and types of  drum and tanks found on site.  Note
       general  condition of tanks and drums.  Note any identification of
       types  of wastes contained in  tanks or drums.
     •  Identify
       -  Site  utilities, facilities  and structures
       -  Unusual waste (lab pack, cylinder)
       -  Drainage
       -  Spills, seeps, etc.
       -  Divide site into  zones to facilitate identification of drum/tanks
          and future  remedial actions
    •  Make  preliminary inventory of any waste surface impoundments and
       grossly  (visually)  contaminated soil areas
    •  Locate  access, egress and security points
    •  Note  evident  environmental stress
    •  Perform  air quality monitoring
    •  Interview local  residents
    •  Photograph or videotape site  features

Unique or special  wastes are often found on tank and drum sites.  During the
site visit, note the presence  of any of the following wastes:
                                    2-15

-------
OSWER Directive 9380.0-3
    •  Laboratory packs (drums, cans or boxes containing laboratory
       wastes).  These types of containers may hold biologically or
       genetically hazardous wastes.  More commonly, however, lab packs
       hold small containers of often incompatible materials.
    •  Radioactive materials
    t  Gas cylinders
    •  Explosives/shock sensitive materials
    •  Highly reactive wastes

A much higher level of risk is associated with the disturbance or handling
of these types of wastes.  If any of these wastes are observed on-site,
assistance from trained personnel  who are experienced in dealing with these
types of wastes should be obtained before proceeding further.

Limitations

During the initial site visit, little or no sampling is performed and only
preliminary on-site activities are performed.  Critical information such as
the location number and size of tanks and drums can be obtained.  Tanks
(and possibly a limited number of drums) can be identified by spray
painting identifier numbers on each drum and tank.  This effort could
assist in any future sampling activities.  Unless absolutely unavoidable,
the movement or staging of drums at this point is not recommended.
Depending on site specific features, (e.g., piled and unlabeled drums) it
may be difficult to identify special wastes.

2.3.2  DETERMINE IF AN IMMEDIATE THREAT EXISTS

Purpose

The primary purpose of this activity is to determine if an immediate threat
to human health or the environment exists.  The most common threat would be
the release of hazardous  wastes due to rupture and/or explosion of tanks or
drums.
                                    2-16

-------
                                                          OSWER Directive 9380.0-3
Technique

The following physical conditions justify special  and immediate attention:

    •  The absence of fencing or other measures to prevent direct contact
       between the public and hazardous materials  in or around the tanks
       and drums
    •  The presence of flammable or explosive materials in situations
       making fire or explosion possible or probable
    •  Severely degraded tanks or drums that could result in sudden and/or
       widespread releases of hazardous materials
    •  Air releases above acceptable levels as measured by direct reading
       instruments or other air quality monitoring devices

The presence of one or more of these conditions does not necessarily mean
there is a significant immediate threat to human health or environment.
Other factors should be considered such as:  types of waste materials  in
the tanks or drums; location and exposure routes to sensitive/human
receptors; and existing topographic and physical site features near the
site.

If an immediate threat is observed during the initial site visit, after  all
factors have been considered, the agency responsible for site activities
and possibly the National Response Center [Telephone (800) 424-8802] should
be contacted.

An example matrix which may be useful in evaluating if an immediate hazard
exists on-site has been included as Table 2-1.  The effectiveness of this
type of format will depend on the quantity and quality of available data.

Limitations

If uncertain of the nature and significance of the threat, contact the
agency responsible for site activities and evaluate the situation with them
before contacting the National Response Center.  The focus at this point is
                                     2-17

-------
  OSWER Directive 9380.0-3
                                      TABLE 2-1
                          EXAMPLE OF A SIMPLE PROCEDURE FOR
                EVALUATION OF SHORT-TERM HAZARDS AT TANK AND DRUM SITE
Location
Zone A
Zone C
Zone A & B
Zone C & D
Type
Liquid
Drummed
Waste
Liquid
Tank Waste
Solid
Drummed Waste
Solid
Tank Waste
Inherent
Hazards
(A)
High
High
Low
Low
Quantities
Present
(B)
High
High
Low
Low
Likelihood
Of Contact
(C)
High
High
Low
Low
Character-
istics Of
Concern
(D)
Acute
Toxicity
Highly Reac-
tive
Acute
Toxicity
Flammable
Toxic
Explosive
Toxic
Threat/
Exposure
Potential
(E)
Very
High
High
Moderate
Low
A. From toxicity data and information on presence of caustic and flammable
   wastes (Rated low to high)

B. From data on concentrations in wastes and environmental  media (Rated low
   to high)

C. From information on human activity at or near site and review of
   plausible pathways of exposoure (Rated from low to high)

D. Define characteristics of public health concern (toxicity, reactivity,
   ignitability, etc.)

E. Weighing information in previous columns (fire, explosion, direct
   contact, and acute toxicity)
                                          2-18

-------
                                                           OSWER Directive 9380.0-3

 defining  and  reducing  very  eminent  and  obviously dangerous conditions.

 Waste  material  is  not  generally  removed and typical  actions could include
 fencing and other  security  precautions.


 2.3.3  CONDUCT  PRELIMINARY  EXPOSURE ASSESSMENT


 Purpose


 The  level  of  hazard  posed by  the site is assessed for each of the identi-
 fied receptors,  and  the  need  for further action is determined.  This
 assessment will  be used  and further evaluated during the limited FS to

 determine  if  a  no  action alternative is appropriate.


 Techniques


 The  following steps  may  be  used  to  perform this preliminary assessment:


     t  Identify  probable waste sources  and types from labels or site
       history.  Information  available  on the type of waste in tanks or
       drums and the condition of the waste containers should be noted.
       The example matrix presented  as  Table 2-2 may be used for this
       purpose.  Relevant information may have been collected as part of
       Task 2.3.1  (Initial Site  Visit).  However, no detailed tank or drum
       inventories have  been  conducted,  nor have tank or drum contents been
       sampled.  Therefore, identifying  specific wastes present may not be
       possible.

    •  Identify the  pathways  of  contaminant migration for each waste source
       (surface water, ground water, air transport, ditches, etc.)

    •  Identify receptors of  the migrating contamination (nearby residents,
       wells, wetlands, endangered  species, etc.)

    •  Determine if  a  remedial action is necessary to mitigate the threat
       to human health or the environment.


Evaluation of the  actual or potential threat may include a qualitative

evaluation of conditions such as the likelihood of migration, amount of

contaminant migration, and time  frame of the exposure.  In most cases,

drums and tanks containing concentrated waste without proper maintenance

and controls can be  presumed to present an actual or potential threat to

the public health  or environment.


                                     2-19

-------
OSWER Directive 9380.0-3
Limitations

Data available at this  stage of the investigation  may allow only a very
cursory assessment of exposure and  threats  to public health and the
environment.

2.3.4  DETERMINE NEED FOR CONTINUED LIMITED ACTIVITY

Purpose

The decision  to conduct a limited RI/FS for tanks  and drums should be
re-evaluated  in light of the detailed review of data and the initial  site
visit.   While the basic objectives  of a limited RI/FS may still be valid,
it may  be more appropriate to expand the scope to  include other wastes
found on site (e.g., in lagoons or  within the soil).  The cost-
effectiveness of a focused fast-track tank  and drum project must be
compared with the value of integrating the  tank and drum portion into the
overall site  RI/FS.

Techniques

Criteria for  making a decision on whether to continue a limited RI/FS for
tanks and drums or to expand the scope to include  the entire site will
obviously vary depending upon site-specific conditions.  Some areas which
should  be focused upon  are summarized below:
    •  Public Health and Environmental  Risk - Does fast-track handling of
       drummed and tanked waste significantly reduce potential public
       health and environmental risk?
    *  Cost-Effectiveness - Based upon  new information, is there a
       potential  for implementing a remedial  program for the entire site on
       a  more cost-effective basis than a limited approach?
    •  Schedule - Does  new information  show that the schedule for
       implementing a limited remedial  action would not differ much from
       that  of a  larger scale action?
                                    2-20

-------
                                                          OSWER Directive 9380.0-3
Limitations

In deciding whether to expand the scope of the limited RI, the types of
remedial technologies involved with handling the different contaminated
areas on-site must be considered.  In most cases, the remedial technologies
for disposal of buried wastes, waste piles and waste spills (contaminated
soil and water) are different than those for tank and drum wastes.   Where
these different types of wastes are present, the combination of remedial
technologies may be difficult and may not be cost effective.  However,
wastes contained in surface impoundments may be similar or related  to
wastes in tanks and drums on the same site.  Previous operators of  the  site
may have used the surface impoundments to hold certain waste residues
removed from the tanks/drums, or may have used impoundments as an inter-
mediate step in a waste reclamation process.  In cases such as these, it
may prove cost-effective to combine remedial technologies for the similar
types of wastes.

If the preliminary assessment indicates that migration and/or significant
exposure from hazardous materials from tanks and drums cannot be reasonably
expected in the short term, the limited RI should still continue since  the
tanks and drums are still in an uncontrolled environment with the potential
to cause harm or damage.

In very unique circumstances, it may be possible to discontinue the limited
RI/FS.  For example, all drums may be empty, crushed, and/or filled with
contaminated soil.  With this situation the drums would no longer pose  as
immediate a threat and could be addressed in the full RI/FS along with
contaminated soil, ground water, etc.

2.3.5  DEFINE DATA NEEDED TO CONDUCT LIMITED FEASIBILITY STUDY

Purpose

The data needed to evaluate the feasibility of potential remedial
technologies (identified previously) are compared with the data collected
up to this point in the limited RI.  If the limited RI data base is
                                    2-21

-------
 OSWER Directive 9380.0-3
 sufficient to conduct the feasibility study, the final  component of the
 limited RI can be omitted and the limited FS initiated  directly.  If there
 are deficiencies in the data base which would restrict  the performance of
 the limited FS then additional  data will  be required.

 Techniques

 The types of data needed to evaluate remedial  technologies are often
 described in existing reference documents.   A summary of data needs can be
 prepared for techniques applicable to tank  and drum remedial  actions.
 Table 2-2 has been prepared and presents  a  list of data needs for
 evaluation of on-site disposal  and/or treatment of tank and drum wastes.
 This type of information would  be useful  for many components  of the limited
 FS (e.g., developing costs  and  design evaluation criteria).  If treatment
 options are being considered, the applicability of various technologies to
 the site-specific waste characteristics should be reviewed.

 Comparison of the data needs with the existing data base will  identify any
 data gaps.  The  data gaps for each of the technologies  should be
 consolidated into a master  list and then  evaluated for  significance of the
 missing data. Although certain data may  not be directly available, it is
 often  possible to estimate  certain parameters  or quantities without
 compromising  the validity of a  feasibility  evaluation.   However, current
 EPA policy is that  data must be adequate  enough to prepare a  +50/-30
 percent cost  estimate.

 Limitations

 Not  applicable.

 2.4  CONDUCT  DETAILED  FIELD  INVESTIGATION

Once potential remedial  technologies  have been developed and  data gaps
defined, a limited  field investigation  is performed to  gather  the required
data to evaluate the technologies.   The following  steps  can be  followed for
the final stage of the  limited  RI.
                                     2-22

-------
                                                         OSWER Directive 9380.0-3

                                TABLE 2-2
                   EXAMPLES OF DATA  NEEDS FOR EVALUATION
                     OF  POTENTIAL REMEDIAL ACTIVITIES
•  Flood  prone  (Is the  site  located in the 100-year floodplain?)

•  Seismic  (Is  the site located within 200 feet of a fault which has had
   displacement  in recent  geologic history?)

•  Groundwater  vulnerability  (Does groundwater under site have a rapid
   rate of  travel, i.e.  greater than 100 feet per 100 years?)

t  Is the site  in a wetland?

•  Is the site  in area  with  karst, subsidence or landslide activity?

t  Is the depth  to the  seasonally high groundwater elevation beneath the
   site relatively shallow (i.e., less than 10 feet)?

•  Is the groundwater beneath the site used for individual or municipal
   water  supply?

t  Is the site  topography  relatively steep (i.e., greater than 30
   percent)?

•  Is the site  located  in  the vicinity of a surface water body or a
   groundwater  recharge  area?

•  Have springs or seeps been identified in the area of the site?

t  Has underground mining  previously been performed in the vicinity of
   the site?

t  Is the site located  in  an area with weak and unstable soils?

t  Is the hydraulic conductivity of the bedrock beneath the site
   relatively high (e.g.,  as would be expected within a sandstone or
   fractured zone)?

•  Is the site located  in  close proximity to a residence, school,
   hospital, commercial   area, or other sensitive receptors?

•  Is an  adequate buffer zone present around the site?

•  Is the site located in  close proximity to a public water supply
   (e.g., reservoirs, watersheds or supply lines)?

•  Are there unique and  protected land uses adjacent to the site, e.g.
   parks, historic sites,  etc.
                                  2-23

-------
OSWER Directive 9380 0-3
2.4.1 PREPARE PROJECT OPERATIONS PLANS

Purpose

Prior to beginning on-site elements of the limited RI, certain planning and
preparation must be completed.  The development of project operations plans
will  assist the user in initiating the limited RI, performing the limited
RI in a safe and effective manner, and in being prepared for emergency
situations should they arise.

Techniques and Limitations

The major components of a project operations plan include a sampling plan
and a health and safety plan.  In addition, a quality assurance/quality
control (QA/QC) plan may be included as part of the project operations plan
or as a separate document.  Normally a quality assurance plan is formulated
outside of the project operations plan and quality control is addressed
within the project operations plan.

2.4.1.1  Sampling Plan.  A sampling plan is developed to describe what data
will  be obtained, what sampling will be performed, and how these tasks will
be completed.  The plan is then reviewed by all involved parties to ensure
that  data requirements will be met and that the data will be collected in a
proper and effective manner.

It is important to define specific objectives of the sampling program in
the plan.  How data will be used in the limited FS should be indicated.
Also, the waste categories will be clearly defined with a description of
the relationship of these categories to the limited FS and project
implementation activities.

Many guidance documents exist for preparing a sampling plan (see Section
5), as well  as sampling plans used for completed projects.  A typical plan
for a tank and drum site would address the following topics:

    •  Goals  of sampling effort
                                     2-24

-------
                                                          OSWER Directive 9380.0-3
    •  Use of sampling data (to select treatment or disposal  options)
    •  Types of surveys to be performed (detailed drum inventory,  detailed
       tank survey, air monitoring, tank wall  thickness and  integrity,
       etc.)
    •  Number and type of samples (primarily wastes from tanks and drums)
       and constituents for analysis
    •  Sample analyses/compatibility testing:   organic/inorganic,
       reactivity, flash point, halogen content, PCB, cyanide, sulfide,
       etc.
    •  Methodology describing sampling procedures

The characterization of types of wastes on-site is used to prepare design
reports, feasibility studies, cost estimates for cleanup, and contract
documents.  Drum sampling prior to remedial action is generally limited  to
a random sampling of the above-ground drums; tank sampling may be  more
complete.  The number of drums and tanks to be sampled is dependent upon
the total number on-site, costs, schedule, and physical condition  of the
drums or tanks.

There are basically three strategies for drum sampling:

    1.  Sample all drums (probably requires staging)
    2.  Random sample with little or no staging
    3.  No sampling

The first strategy is the most thorough and also the most costly.   It is
usually not practical for a limited RI/FS.  The second strategy, as indi-
cated, is the most practical and has been the practice/policy at several
drum sites.  Costs are kept fairly low and a limited data base is  provided.
The random sampling approach does not provide a complete data base which
would be available from a full drum sampling program.  However, a  random
sampling program does provide a useful data base without the costs and
potential problems of a full sampling program.  The staging and equipment
requirements for a full sampling program can extend the duration of the
limited RI and can be costly.  No sampling avoids cost and schedule issues
but provides no direct analytical data on the drums.

                                     2-25

-------
OSWER Directive 9380.0-3

Some of the key issues  to  consider when  weighing  the  potential  advantages

and disadvantages of a  particular drum sampling program are  summarized

below:
    1.  A full  sampling program will  require  drum staging  or  at  least
        considerable drum handling  during  the remedial  investigation
        activities.   This will  require special  equipment and  contingency
        planning, including a complete health and safety plan and  equipment
        plus full decontamination  facilities.  These  would not be  necessary
        with a  more  limited sampling  program.

    2.  It would be  very expensive  to conduct a full  sampling program  of
        drums.   For  example,  just the decontamination facilities alone can
        run $10,000  to $30,000  for  equipment  and personnel  and $0.50 to
        $1.00 per gallon for  disposal  of the  wash water.   Added to this
        would be the obvious  cost of  sampling and analytical  activities.

    3.  Before  a cleanup contractor can remove  drummed  wastes off-site it
        may be  necessary to sample  each drum  for the  following reasons:

        - determine  compatibility for bulking

        - provide information for preparing manifest  for shipment  in order
          to meet EPA and DOT requirements [see 40 CFR  262.11(c)]

        - provide additional  information (if  required)  for the TSD facility
          receiving  the waste

        - ensure overall  safety in  handling,  packaging  and transporting
          wastes
        Since  remedial  contractors must  sample all  drums  for manifesting
        prior  to  transportation  and disposal, it  is  usually cost-effective
        to  postpone  a comprehensive drum sampling  until the remedial
        contractor is ready to initiate  on-site activities.  As  a  result
        random sampling  is performed to  provide a  data  base for  the  limited
        FS  and primarily  for  preparation of contract documents.

   4.   Random sampling, while providing a limited  data base can be  a
        useful  alternative to full sampling.  The  data  can be  used to
        expand the general knowledge of  the site,  but more importantly, it
        has a  useful function in preparing competitive  bid documents.

   5.   No  sampling  of drums  is  obviously the least  expensive  way to
        conduct a limited RI.  However,  without even a  random  sampling data
        base,  it becomes difficult to prepare a competitive bid package and
        ultimately contract documents.   Additionally, further  planning and
        design activities have to progress with little or no information on
        the characteristics of drum wastes.
                                    2-26

-------
                                                           UoVVhR Directive 9380.0-3
A drum  sampling  program  should  be  limited to approximately 5-10 percent of
the  containers.   The  reasoning  is  that on an abandoned drum site, the
containers  probably have accumulated  at the site over a period of years,
possibly  from  many difference sources.  Drums may be full of spent cleaning
solutions containing  unknown material or manufacturing by-products.
Additionally,  many of these sites  functioned as recycling centers with the
more homogeneous or quality material  being sold as a product.  If a
manufacturer had a by-product of any  worth or volume, it probably would
have been recycled directly and, due  to transportation costs, would not be
shipped in  individual  drums.  Also, because of the wide range in the types
of materials that may have been accepted at a site, random sampling would
not  be  statistically  significant,  but would only indicate the waste
category  of the  container sampled.  Random sampling could, however, help
delineate between a site with a wide  range of heterogeneous waste and one
with  wastes of a homogeneous nature.  This may provide evidence identifying
a site  where waste was produced on site and the drums were used for
storage.

Random  sampling  can also provide some insight into the types of waste
categories  that  might  be encountered  at the site.  Again, statistically
these data  will  have  limited value in providing an accurate projection of
all the waste  types or quantities, but this data base can be combined with
the drum  inventory, presented in Section 2.4.2, to develop reasonable
estimates.  This  information is particularly important for preparing
contract  documents and may be useful  for the limited FS.

A "stratified" random sampling  technique for drums may be applicable for
many sites.   The  approach differs somewhat from a pure random sample
program in that  selection criteria are developed for groups of drums rather
than treating the entire  site as one group.  For example, a stratified
random sample approach may group drums found on-site into the following
categories:

    •  Drums of similar  color and condition with labeling suggesting one
       source/generator
                                     2-27

-------
OSWER Directive 9380.0-3
    •  Drums with polyliners suggesting similar types of wastes
    0  Areas of drums which have been obviously separated from other drums
    •  Miscellaneous drums not falling into other defined groups

A random sampling procedure would be developed for each group.  A
"stratified" random sampling procedure developed for the different groups
could result in a data base more representative than a pure random sample
selection which considers all drums on-site as a single group.  The results
of a stratified random sampling program may suggest that wastes found in
similar drums or in one area are similar or dissimilar.

Random sampling of drums at two NPL sites involved 6 and 20-25 percent of
the drums, respectively.  A considerable amount of detail was available for
one site and it was possible to determine the number of specific types of
drums and containers at various locations at the site.  This information
was valuable to potential contractors in determining equipment needs and
drum removal costs.  Also, using the data derived from the random sampling
effort, it was possible to develop a gross categorization of waste types
found at the site (Table 2-3).  At the other site a similar approach
resulted in a characterization that provided an accurate engineer's cost
estimate for total  cleanup.

Tank sampling has shown to be an advantage when addressing waste categories
and evaluating remedial action alternatives.  This is primarily due to the
relative cost-effectiveness of a sample taken from a 20,000 gallon tank as
compared to the same sample from a 55 gallon drum.  More importantly the
data on bulk quantities of waste can be very useful in the limited FS along
with helping in the preparation of contract documents.

In tank sampling, two key points should be made.  The first is that tanks,
more so than drums, can maintain an internal explosive atmosphere, and as
such require special  tools (cold cutting).  Therefore, under an RI level of
effort, only tanks  with access ports should be sampled.  Secondly, tanks,
because of relative volume and quiescent condition, tend to stratify.  It
                                     2-28

-------
                                                       OSWER Directive 9380.0-3

                                 TABLE 2-3

                  CATEGORIZATIION OF WASTE TYPES AT AN  NPL
                  SITE BASED ON RANDOM SAMPLING* OF DRUMS
         Solids                                        19%
         Acids                                         16%
         Non-chlorinated Solvents                      14%
         Resins                                         9%
         Aqueous Waste                                  7%
         Alkali Waste                                   7%
         Cyanide Waste                                  6%
         Waste Oil                                      6%
         Paint Waste                                    5%
         Sludges                                        4%
         Chlorinated Solvents                           2%
         Glycols                                        2%
         Empty                                          1%
         PCB Oil                                        1%
* Based on a random sampling  of  20  to  25  percent  of drums,
                                2-29

-------
 OSWER Directive 9380.0-3
 is not  uncommon for as  many as  three phases  (oil,  liquid and sludge)  to be
 discovered.  A sample should be collected  from each phase.   The level  of
 sample  analysis for either  tanks or drums  is  generally limited to that
 which is necessary to determine compatibility and  that required for
 disposal.  Compatibility analysis is usually  restricted to  the tank waste
 during  the RI study but will be performed  on  all of the tank and drum waste
 by the  contractor as part of the consolidation and bulking  protocol.
 Appendix B includes an  example  of a drum and  tank  sampling  protocol for
 waste compatibility, and is followed by  Appendix C, which presents  the
 protocol for bulking and consolidation of  identified compatible waste
 groups.   Depending on  the  structure of  any random drum sampling, a
 compatibility analysis  could be included as part of the drum sampling
 program.  The main categories of compatibility analysis include the
 following:

     •  Ignitability (flash  point)
     •  Radioactivity
     •  Determination of oxidizing or reducing agent
     •  Reactivity
     •  Density
     t  Concentration of organic halides
     t  PCBs
     •  pH
     •  Cyanides
     •  Sulfides

 In order  to further  categorize  wastes in terms  useful  for evaluating
potential  treatment  and/or  disposal  technologies,  additional  waste
characterization  is  needed.   While  compatibility characterization is  a
useful first step more  specific  criteria are  required  for waste
categorization.  Waste  categories useful  in evaluating  various treatment
and disposal technologies are listed  in  Table  2-4.
                                     2-30

-------
                                                          OSWER Directive 9380.0-3
                                 TABLE 2-4
                    WASTE TREATMENT  DISPOSAL CATEGORIES
AQUEOUS WASTES

• Acid:  pH  < 2.0
• Base:  pH  > 12.0
• Base with  sulfur
• Base with  Cyanide

ORGANIC LIQUIDS

• High halogen Content  (>  2%)
• Low halogen Content  (_< 2%)
• PCB Contaminated Liquid
  (50-500 ppm)
• PCB Contaminated Liquid
  (> 500 ppm)

CONTAMINATED WATER

• 2 < pH < 12
• Inorganic
• Organic
• PCB Contaminated Liquid
  (< 50 ppm)
SLUDGES

• PCB Contaminated Classified as liquid
  (50-500 ppm and > 500 ppm)

SOLIDS

• PCB Contaminated
  (> 50 ppm)

SLUDGE/SOLIDS

• Organic Low Halogen
• Organic High Halogen
t Inorganic
• PCB Contaminated (< 50 ppm)
• Flashpoint (< 70 °F)
• Flashpoint (70 - 140 °F)
• Flashpoint (> 140 °F)

SPECIAL WASTES

• Water Reactive
•Air Reactive
• Radioactive
• Strong Oxidizer
• Strong Reducer
• Lab Packs
• Explosives
                                    2-31

-------
 OSWER Directive 9380.0-3
 References have been made to Appendices B and C, example of a "Drum Han-
 dling, Drum Sampling, Special Waste Handling, and Tank Sampling Protocol,"
 and example of a "Bulking and Consolidation Protocol."  Appendix B presents
 compatibility testing procedures which must precede the actual bulking and
 consolidation procedures included in Appendix C.  The material presented in
 these appendices can be used during planning activities for sampling,
 during the actual execution of sampling activities, or during project
 implementation.  The protocols should be tailored to the specific needs of
 the user.  For example, random sampling for drums could include
 compatibility testing if a "stratified" approach were used.  However, the
 use of a more general random selection approach may limit the usefulness of
 a compatibility analysis.  Compatibility analysis will always be required
 before bulking or consolidating wastes.

 In general, field analyses are typically less costly to perform than full
 laboratory analysis.  Sample shipping and chain-of-custody is minimized for
 the majority of samples.

 The user should be aware that any field analysis of samples will not
 produce the litigation-quality documentation available through a
 laboratory.  Instead, field analysis can be used to develop information to
 proceed with the project while a small percentage (e.g., 25 percent) of the
 samples are sent to a laboratory for analysis and verification.
 Additionally, field screening techniques are of limited value in complex
 samples (e.g., oily sludges) and are not available for all contaminants.
 For example, few field instruments measure inorganics.  Additionally,
 because of the concentrated nature of these samples, a laboratory equipped
 to handle such high-hazard samples (such as EPA's hazard laboratory at
 NEIC) may be required.

 2.4.1.2  Health and Safety Plan.  A health and safety plan is developed to
 establish the procedures that will be followed during the execution of the
 detailed field investigation.  This plan is developed from earlier health
 and safety protocols (See Section 2.2.2) and information assembled from
 activities such as the initial site visit (Section 2.3.1).  EPA's guidance
on health and safety can be found in Standard Operating Safety Guides  (EPA,
 1984).
                                     2-32

-------
                                                          OSWER Directive 9380.0-3
To confirm the basis for the site worker respiratory protection protocol
contained in the health and safety plan, both on- and off-site air quality
monitoring should be initiated at the onset of the project mobilization  and
maintained during on-site activities.  Additionally, due to the nature of
waste materials commonly found in tanks and drums and their ability to
rapidly degrade ambient air quality, it is important to continue air
monitoring both on- and off-site during the limited RI so that potential
impacts from handling wastes can be evaluated.

A specific air monitoring program must be established for each site based
on the nature of the wastes present and site conditions.  Sampling may be
performed for organics (volatile compounds), inorganics (cyanide gas), or
airborne particulate (asbestos).  Methods currently used to monitor air
quality at tank and drum sites include:

    •  Direct reading methods
       - Organic Vapor Analyzer (OVA)
       - Photoionizatin detector
       - Infrared gas monitors
       - Explosive gas indicator
    •  Delayed quantification techniques
       - Collection of samples using air sampling pump and sorbent
         charcoal, glass filters, or other media.

Other components of the health and safety plan include training program
(for drum and tank entry and sampling), contingency plan  (for drum breach,
drum explosion, etc.) and guidance on area and access restrictions.

Table 2-5 has been prepared as an example to develop procedures for safely
sampling tanks and drums.  The operations presented in this table are
general in nature and must be modified or supplemented based on actual site
conditions.  Because of the hazards inherent in these operations, safety
plans should be extremely conservative.
                                     2-33

-------
  OSWER Directive 9380.0-3
                                   TABLE 2-5

        EXAMPLE OF PROCEDURES FOR TANK AND DRUM SAMPLING:  SAFETY ASPECTS
 Protective  Equipment:
 Potential  Hazards:
Hard hat, safety shoes, safety glasses,  rubber gloves,
face shield, protective suit, respirator*,  lifeline
(for tank sampling).

Fire and explosion, inhalation of toxic  or  flammable
vapors, skin contact  with waste.
             Operations

  1.   Inspect tank or drum


  2.   Monitor vapor concentrations


  3.   Ground tank or drum


  4.   Minimize exposure


  5.   Remove drum cap
 6.  Measure vapor
 7.  Insert sampler
                          Work Procedures

               Examine tank or drum for signs  of pres-
               sure buildup,  shock,  sensitivity, etc.

               Collect grab samples  to  determine
               concentrations of organic compounds.

               Clean surface  area of tank  and  attach
               ground.

               Position employees upwind from  tank
               hatch or drum.

               Slowly remove  cap or  bung,  and  allow
               vapor to escape.   For drums,  use  of a
               remote or non-sparking bung removal
               apparatus should  be considered.

               Collect grab samples  to  evaluate  concen-
               tration and  flammability of vapor and
               gases.  If vapors are hazardous wait  5
               minutes and  retest.

               For  Tanks:   Lower sampler (Bacon  Bomb-
               ASTM D-720)  to collect samples  of:

               a.   upper sample  - middle - upper third

               b.   middle sample - middle  of tank
*In some cases, the use of self-contained breathing apparatus is required when
 the contents of a tank are unknown or suspected to be a high hazard.  Under
 no circumstances should the user enter the tank.  This table does not address
 tank entry procedures.  See Appendix B for further details.
                                      2-34

-------
                                                            OSWER Directive 9380.0-3
                              TABLE  2-5  (Continued)

       EXAMPLE  OF  PROCEDURES  FOR  TANK AND DRUM SAMPLING:  SAFETY ASPECTS
              Operations
 8.  Collect  sample
 9.  Retrieve sample
10.  For Tanks:  Cover tank
           Work Procedures

c.  lower sample - near bottom

For Drums:  Insert glass sampling thief
into bung hole until solid material  is
encountered.

For Tanks:  Pull out bottle stopper
with sharp jerk of sample line and
allow bottle to fill.

For Drums:  Place finger over end of
thief and remove from drum.

For Tanks:  Raise sampler, wipe off
surface of sampler and place cloth in
disposable plastic bag.  Tag sample and
record data on forms for drums:

Place bottom of thief in glass con-
tainer and release thumb for thief.
Repeat steps 8 and 9 until sufficient
sample is collected (200 ml).

Carefully close tank cover.
11.  For Drums:  Dispose of thief
12.  Monitor vapor concentrations
Insert thief in bung hole and replace
bung.  NOTE:  if wastes are to be trans-
ferred, a screen must be placed on pump
intake to prevent damage by glass
pieces.

Collect grab sample to evaluate
concentration of vapor post-closure.
*In some cases, the use of self-contained breathing apparatus is required when
 the contents of a tank are unknown or suspected to be a high hazard.  Under
 no circumstances should the user enter the tank.  This table does not address
 tank entry procedures.  See Appendix B for further details.
                                      2-35

-------
OSWER Directive 9380 0-3
2.4.1.3  Quality Assurance/Quality Control  Plan.  A quality assurance plan
is an assemblage of management policies, objectives, principles, and
general procedures to be followed in producing environmental monitoring
data of known and acceptable quality.  Quality control  refers to the
routine activities and checks, such as calibration and  duplicate analysis,
conducted under the quality assurance program.

EPA's guidance on preparing quality assurance plans is  found in Guidelines
and Specifications for Preparing Quality Assurance Project Plans, (EPA,
1983).   The  sixteen components of a quality assurance plan according to the
EPA guidance are:

    1.   Title page with provision for approval signatures
    2.   Table of contents
    3.   Project description
    4.   Project organization and responsibility
    5.   QA objectives for measurement data  in terms of  precision, accuracy,
        completeness, representativeness, and compatibility
    6.   Sample procedures
    7.   Sample custody
    8.   Calibration procedures and frequency
    9.   Analytical  procedures
    10. Data reduction, validation and reporting
    11. Internal  quality control  checks
    12.  Performance and system audits
    13. Preventive maintenance
    14. Specific  routine procedures to assess data precision, accuracy and
        completeness
    15. Corrective action
    16. Quality assurance reports to management
                                    2-36

-------
                                                          OSWER Directive 9380.0-3
Some of these components of the quality assurance plans are actually
quality control procedures.  For example, the "Calibration Procedures and
Frequency" section of the QA plan may merely reference the applicable
standard operating procedure (quality control) found in the sampling plan
or health and safety plan.

2.4.2 PERFORM TANK AND DRUM SURVEY/INVENTORY

Purpose

This task will provide information describing the number, type, and
condition of drums, the type of wastes in the drums (liquid, sludge, solid,
etc.), and the source of the drums.  Additionally, important information on
tanks can be obtained by a survey from the air or ground.  This information
will play a major part in the selection and development of the remedial
program, evaluation of disposal technologies, and development of bid
documents.  Preliminary information was developed during the initial site
visit (e.g., estimated number of drums).  This physical survey is more
detailed and comprehensive than the initial site visit.

Techniques

A drum survey is an actual physical inventory and evaluation of drum
wastes.  It is different from random sampling in that no detailed chemical
analyses are performed.  The drum survey must be tailored to the size and
nature of the site.  Two major techniques, aerial survey and ground survey.
are typically used to perform this task.  There are advantages and
disadvantages associated with each of these methods.  Usually an aerial
survey will supplement a ground survey.  The characteristics of these two
types of surveys are summarized in Table 2-6.  Examples of techniques for
examining, handling, staging, (if applicable) and labeling drums are
contained in the references in Section 5.0.  It should be noted that
depending on the number of drums and access to them, it may not be possible
to inspect every drum.  Tasks typically performed include:
                                     2-37

-------
OSWER Directive 9380.0-3

                                 TABLE  2-6


                ASPECTS OF AERIAL  AND  GROUND DRUM SURVEYS
           ASPECT


Drum Count Possible

Identify Drum Type

Identify Overpacks and Polypaks

Label Identification

Evaluate Drum Integrity

Note Presence of Pails, Buckets,
  Boxes, etc.

Note If Drums Have Bulged

Number Drums

Cost of Survey
          METHOD
  AERIAL           GROUND
YES

PARTIAL

PARTIAL

PARTIAL

DIFFICULT


YES

DIFFICULT

NO

LOW
YES

MOST OR ALL DRUMS

YES

YES (IF PRESENT)

POSSIBLE


YES

YES

YES

MODERATE TO HIGH
                                   2-38

-------
                                                          OSWER Directive 9380.0-3

    •  Drum count and aerial classification (number of drums and location
       on site)

    •  Note drum type (bung or lid, steel or plastic)

    •  Presence of polypacks and overpacks (If these types of drums are
       present on site, the contractor should realize that the drums
       probably contain wastes which are capable of degrading steel
       containers or contain drums of low structural integrity.)

    •  Label identification (An attempt should be made to record all
       labeling on drums to assist in the identification of the drum
       contents.  If proper manifesting occurred during site operation,
       this effort may produce very good results.  However,  because waste
       products are often placed in used containers, the labels should  not
       be the sole basis for classifying the drum wastes.)

    •  Noting drum integrity and evidence of leakage (Drum integrity can be
       evaluated by carefully sounding the drums, examining  them for
       degradation, and other non-intrusive techniques.)

    •  Note if drum ends bulge

    •  Numbering drums (for future identification)


An example drum inventory form that could be prepared prior to initiation

of the survey is presented in Table 2-7, although a form allowing more

information on drum identification and condition may be of value. A

computer-compatible form may be useful to allow easy data entry.  This  is

particularly true for sites with a large number of drums.   Information

could be derived from a detailed drum inventory on probable  waste

categories based on the type of drum.  These are presented as follows:


    •  Empty - drums with less than 1 inch of residual  solids in the bottom
       can be crushed and disposed of as an empty drum (see  discussion
       below)

    •  Lab packs - these are 55 gallon ring top drums which  contain
       numerous small  containers of unknown laboratory wastes.

    •  Overpack - these are 80-85 gallon oversized drums used to hold a
       standard (damaged) drum

    •  Polyliner - these are generally 55 gallon drums which contain a
       plastic bladder usually containing highly caustic (acid or alkaline)
       wastes

    •  Polydrums - these are fiber polylined disposable drums which contain
       caustics.


                                     2-39

-------
   OSWER Directive 9380.0-3
                                      TABLE 2-7



                            EXAMPLE  DRUM INVENTORY FORM
LOCATION
Zone A
Zone B
Zone C
Bldg #1
TOTAL
EMPTY
75
3
12
0
90
LAB PACKS
(ACTUALLY
SEEN)
2
0
1
10
13
OVER-
PACKS
25
40
0
0
65
POLY/
LINER
15
0
6
50
71
POLY-
/DRUM
15
0
7
50
72
BUNG
TOP
50
140
15
80
285
RING
TOP
40
40
12
0
92
OTHER
CONTAINER
10a
0
0
15C
25
MISCEL-
LANEOUS
250b

200b

450
TOTAL
482
223
253
205
1163
NOTES:



   a. Unlabeled five gallon containers



   b. Piled drums, access restricted, quantity is estimate



   c. Unlabeled one gallon containers
                                         2-40

-------
                                                          OSWER Directive 9380.0-3
    •  Bung top - this is a standard 55 gallon drum with the typical  2-3
       inch screen hole on the top, used to carry liquids such as spent
       solvent waste
    •  Ring top - these are the standard 55 gallon drums that are open top
       usually containing solids or resins

Under certain conditions, empty drums may be disposed of at a sanitary
landfill.  However, possible restrictions on the disposal of materials
found at NPL sites should be reviewed with appropriate agencies.   Addi-
tional information on the definition of empty drums can be found  in 40 CFR
261.7.  Also, limitations on the reuse of drums can be found in 40 CFR
173.28.

Staging of drums (the process of moving drums from various locations  to one
area in a logical and systematic manner) is not recommended because of high
costs and hazards associated with this activity.  Staging should  be
considered only under the following conditions:

    •  Very obvious hazards if left unstaged (incompatible labeled drums
       next to each other)
    t  Drums are leaking
    •  There are severe access restrictions
    •  Drums can easily be grouped by type (a possible advantage during the
       development of bid documents)

If staging is required, a staging plan should be developed and reviewed by
all involved parties.  In planning staging areas, the size and goals  of the
operation, accessibility of drums in their original locations and the
hazards associated with the drums must be considered.  There may be up to
five staging areas that can be used:

    •  Initial staging area - organize drums and store prior to sampling
    •  Opening area
    •  Sampling area
    •  Holding area - temporary storage area prior to characterization  of
       contents

                                     2-41

-------
 OSWER Directive 9380.0-3
    •  Bulking area - should be  located as near to the site's exit as
       possible

 The number  of areas used and movement of drums should be minimized.  Drums
 are generally staged in rows which allow ease of access and handling.

 The major elements of a tank survey include determination of:

    •  Number of tanks
    •  Tank location
    •  Tank volume and size
    •  Structural integrity  (using visual examination or methods such as
       x-ray and ultrasound)
    •  Accessibility (Is there sufficient ground space and overhead
       clearance to allow use of articulated boom crane?  Can personnel
       climb into tanks?)
    t  Volume of waste in tanks  (methods include sounding, probing, and
       visual inspection)
    t  Nature of waste in tanks
    •  Existing mechanical plant (pumps, compressors, pipes), piping, and
       other connections between tanks.

 Limitations

 The drum survey is designed to gather as much information as possible
 without actual analytical activities.  Drum sampling may or may not be
 performed during the limited RI.  Drum staging should be avoided except for
 very unique  or special  occasions.

 Due to the questionable integrity of certain tanks on-site, only limited
data may be  obtained from these tanks.  Additionally, special equipment and
tools  may be required to open and/or sample these and other tanks.  This
could  include the use of an articulated boom crane to provide access to the
tank,  use of remote opening devices, and use of self-contained breathing
apparatus (SCBAs) by personnel.
                                     2-42

-------
                                                           OSWER Directive 9380.0-3

 2.4.3   CONDUCT SITE  CHARACTERIZATION


 Purpose


 Information  describing  site  conditions  other than  tanks  and  drums  are

 required  for remedial  alternative evaluation and planning.   These  data
 are  obtained as  part of site characterization activities.


 Techniques


 Typical site characterization  tasks  include:


     •   Property  line,  topographic, stadia  and aerial  surveys  (to define
        site  limits,  access,  drainage,  relief, and  layout.)

     •   Confirmation  of  site  utilities  and  facilities  (to determine how
        existing  facilities will  affect  work,  what  utilities  are needed,
        etc.)

     •   Identification of areas of contamination  (may  be  completed  by  visual
        inspection, sampling,  geophysical survey, infrared photography,
        etc.)

     •   Description of subsurface conditions.   (Existing  boring logs, well
        reports,  etc. may be  available.   If these are  not available,
        information is obtained through  a boring and soil testing program,
        which  is  not  usually  a  part of  a limited RI.)


 Limitations


 This information may have been collected during the initial  site visit so
 that no further  site characterization  is required.


 2.4.4   CONDUCT  SAMPLING PROGRAM


 Purpose


 This activity  executes  the sampling  program developed as a  result  of  those

activities described in  Section  2.4   Prepare Project  Operations Plans.   As

previously discussed, all tanks  should  be  sampled, whereas  random  sampling

drums may be  the preferred approach.


                                     2-43

-------
OSWER Directive 9380.0-3
Sampling of drums and tanks prior to removal at a site provides more
information on waste type and volume so that accurate contract documents
can be prepared and a safe and efficient removal operation can be
conducted.  Unit price contract documents can be prepared with limited
sampling data if sampling was done to verify the disposal categories and
volumes of waste.

Data from a sampling program and laboratory analysis would include:

    t  Volume of waste
    •  Type of waste (solid, liquid, sludge, etc.)
    •  Presence of stratified layers in tanks
    •  Chemical composition of wastes in tanks (and possibly randomly
       selected drums)
    •  Characterization of waste by disposal categories  (Section 2.4)
    0  Correlation between drum labels or shipping manifests and drum
       contents
    •  Waste compatibility or treatability (Section 2.4)

Techniques

Detailed drum and tank sampling procedures previously developed are
presented in the references listed later in this manual  (Section 5).
Additionally, examples of drum handling and sampling, special waste
handling, and tank sampling protocols used during remedial actions at an
NPL site are included in Appendix B and C.  Suggested guidance provided in
these appendices should be tailored to fit the structure of the planned
sampling activities and site-specific requirements.

As waste sampling is being performed, many of the compatibility tests can
be performed on-site to reduce turn-around time and make drum staging (if
necessary) more efficient.  However,, most compatibility  testing will focus
on tank wastes since it is typically the practice to sample all tanks
whereas random sampling is only performed on drums.
                                     2-44

-------
                                                          OSWER Directive 9380.0-3
Because there are generally fewer tanks present on-site, and tanks are
usually more accessible than drums, the tank inventory and sampling process
may be simplified.  In most cases, it is possible to sample and inventory
all bulk storage tanks during the limited RI.  This information will  be
valuable in determining the appropriate type of treatment and disposal
technologies for the tank wastes and preparing contract documents.

Limitations

Very strict health and safety procedures should be followed during all
field activities of the limited RI, particularly during sampling
activities (Section 2.4).

2.4.5  REVIEW ANALYTICAL RESULTS FOR CONFORMANCE WITH QA/QC PROGRAM

Purpose

EPA has developed QA/QC protocol and evaluation methodology to verify the
accuracy and reliability of analytical data.  The analytical data generated
during the limited RI must be examined in accordance with these methods to
assure their reliability and subsequent usefulness.

Techniques

Step-by-step QA/QC validation protocol have been developed by EPA (Section
2.4.2.3).

Limitations

Not applicable
                                     2-45

-------
OSWER Directive 9380.0-3
2.4.6  EVALUATE ALL DATA AND PREPARE LIMITED REMEDIAL  INVESTIGATION REPORT

Purpose

The evaluation of data is an ongoing process throughout the limited RI.
However, once all field work has been completed and the data base is
essentially complete, a final analysis is conducted.   The activities of the
limited RI and the results of the data evaluation are  then presented in a
remedial investigation report.  During this final analysis the scope of the
limited RI/FS is again reviewed.

Techniques

This evaluation of data should focus on the needs of the limited FS
(described in Section 3).  The objectives of various data collection
activities are reviewed and then compared to the actual results of the
limited remedial investigation.  It is important to ensure that the data
obtained satisfies the earlier defined objectives.  If the objectives have
been adequately met, the quality of the limited FS, which is based upon
data obtained during the limited RI, will be enhanced.

A remedial  investigation report on the tank and drum operable unit should
integrate and present a discussion of activities and observations made
during the limited RI, and include an evaluation of these data.  Detailed
discussion of the contents of a limited RI report are presented in EPA
guidance documents referenced later in Section 5.0.  A typical  report for a
tank and drum site could contain (but is not limited to) the following
major elements:

    •  Site Background Information
    •  Nature and Extent of Problem
    •  Limited Remedial  Investigation Summary
    •  Overview  of Report
    t  Demography
                                    2-46

-------
                                                          OSWER Directive 9380.0-3
    •  Land use
    •  Natural Resources
    •  Climatology
    •  Updated Base Map
    •  Hydrogeologic Features
    •  Surface Features
    •  Tank(s) Features
    •  Drums Features
    •  Site Health and Safety Features
    t  Bench and Pilot Tests (if applicable)
    •  Potential Receptors
    •  Public Health Issues
    t  Environmental Issues
    •  References
    •  Appendices

Evaluations of the expanded data base could indicate that the magnitude
and/or complexity of the hazardous waste and environmental problems at the
site are too great to remain within the scope of the limited RI/FS
approach.  If this is the case, a full-scale, comprehensive RI/FS may need
to be considered in lieu of a limited single operable unit approach.

Limitations

Not applicable.
                                     2-47

-------
                                                          OSWER Directive 9380.0-3
                       3.0  LIMITED FEASIBILITY STUDY
There are four major components of the limited FS.  These are:

    •  Identify major remedial technologies (Section 3.1)
    •  Screen initial remedial technologies (Section 3.2)
    •  Conduct detailed evaluation of potential remedial action
       alternatives  (Section 3.3)
    •  Conduct comparative summary of potential remedial action
       alternatives  (Section 3.4)

The process of identifying, reviewing, and screening remedial  technologies
is ongoing throughout limited RI/FS activities.  During the limited RI
phase, technologies that are potentially applicable to the site are
identified.  Then, as the limited RI progresses, site limitations and waste
characteristics are identified which preclude various remedial measures.
This screening leads to the list of remedial  alternative strategies to be
addressed in the limited FS.

There are two major screening and evaluation  phases of the limited FS.  The
first phase involves the identification and screening of alternative
remedial  technologies for each major alternative strategy.  During this
phase the technologies are screened based on  technical feasibility and
reliability, costs, environmental and public  health effects.  The results
of the first phase define the components of each alternative for remedial
action.

The second phase involves the development and evaluation of complete
alternative plans of remedial action.  The evaluation in this phase is
based on more detailed cost, environmental, public health, and technical
data, along with a consideration of regulatory and institutional concerns.

It is important to understand the difference in the meaning of the two
terms "technology" and "alternative".  A remedial technology  is typically
                                    3-1

-------
OSWER Directive 9380.0-3
specific to a waste type or a group of similar waste types.  For example,
incineration is a remedial technology potentially applicable to organic
materials.  A remedial action alternative is specific, in this case, to an
operable unit at a site.  One remedial action alternative could be
comprised  of many different remedial technologies, e.g., an off-site
alternative may involve the incineration of organic wastes, the treatment
of aqueous wastes and the land disposal of various sludges and solids.

A limited  FS is a necessary and logical element in the procedure to develop
specific remedial action alternatives for an NPL site.  The purposes of a
limited FS for a drum and tank site are:
    •  To identify technologies or remedial measures which are most
       appropriate for implementation at the site.  Within each remedial
       measure further analysis may be required to evaluate the cost
       effectiveness of alternative remedial technologies (e.g., high
       temperature incineration, recycle, etc.)
    •  To develop alternatives to abate, stabilize, or minimize release of
       wastes from drum and tank sites
    t  To evaluate the cost-effectiveness of alternative remedial measures
       for treatment, storage, disposal or destruction of wastes within
       drums and tanks at a site
    t  To incorporate these technologies or remedial measures into overall
       remedial action plans for the site and evaluate their comparative
       features.
This evaluation and selection process must be consistent with CERCLA and
Section 300.68 of the National Contingency Plan (NCR).

Specific guidance for conducting feasibility studies at NPL sites can be
found in EPA's Guidance Document for Feasibility Studies Under CERCLA (EPA,
1985).  Guidance for conducting feasibility studies under CERCLA and
procedures for evaluating hazardous waste sites with surface tanks and
drums are contained in the literature (See references for Sections 3.2,
3.3, and 3.4 that are presented in Section 5).  This section presents an
                                    3-2

-------
                                                           OSWER Directive 9380.0-3
 approach  for conducting  a  limited  FS  at  a  surface  tank  and drum site.  A
 guidance  logic  diagram which  displays the  sequence of tasks  is presented as
 Figure 3-1.

 This  section is organized  to  correspond  to the  individual tasks shown in
 Figure 3-1;  text subsection numbers for  these tasks  are directly
 cross-referenced to  the  figure  to  provide  easy  orientation for the user.

 For planning purposes  one  can assume  that  a calendar period  of 1-2 months
 would  be  required to complete a limited  FS.  One should also assume that
 the limited  FS  can begin during the limited RI.  The time requirements for
 the various  tasks will vary from site to site.

 3.1   IDENTIFY MAJOR  REMEDIAL  TECHNOLOGIES

 Purpose

 The purpose  of  this  task is to  review the  data  collected as part of the
 limited RI and  to identify the  conceptual  treatment and/or disposal techno-
 logies and strategies  available for the  different  waste types found at a
 surface tank  and  drum  site.   The major waste types which would be defined
 in the limited  RI  are  reviewed  in  Section  2.4.1.   A preliminary review of
 potential remedial actions would be included in the  limited RI.  This
 review would  include an  identification of  potential remedial  technologies
 (Section  2.2.4)  along with a  refinement  of this list based upon unavoidable
 and restrictive  site features.   The objective of this task is to further
 identify  and  define  "conceptual" technologies and  strategies which are
 potentially reasible for major  waste  types known or suspected in drums and
 tanks.

 Techniques

During this task, the possibility  of  consolidating the individual  waste
types  into a  smaller number of  composite wastes should be evaluated.  It is
essential  that consolidation  procedures  available  in the literature be con-
firmed in the field by sample compositing  or other small scale techniques.

                                    3-3

-------
                                                                                                                                                                                O
   Figure 3-1.     Feasibility study logic diagram.
                                                                                                                                               CD
                                                                                                                                               CO
                                                                                                                                               CO
                                                                                                                                               O
                                                                                                                                               O
CO
 I
                             Identify Major Remedial Technologies
                           • Review data generated during Rl
                           • Generate list of reasonable alternatives
                                                                  3.1
         Begin Project
        Implementation
           Activities
 Conduct Comparative Summary
           of Potential
  Remedial Action Alternatives

Evaluation  criteria
Prepare summary narrative
                                                                3.4.1
                                                                                                                                                                   3.2.2
Screen Initial Remedial
Technologies
Evaluate Technical Reliability
and Feasibility
                                                                                                  3.2
                                                                                                           Evaluate Environmental and
                                                                                                           Public Health Impacts
                                                                                 Perform Technical
                                                                                    Analysis
                                                                               	-3.3.
                                                                                                    ,
  Perform Cost Analysis

                  " 3.3.2J
  Perform Environmental  I
and Public Health Analysis!
  	-3.3.3-I
                                                                              Perform Regulatory and
                                                                               Institutional Analysis
                                                                             	3.3.4 •
                                                                                                                                3.2.1
                                                                                                                                            Evaluate Costs
Detailed Analysis of
Potential Remedial
   Alternatives
                                                                                                                                  3.3
                                                                                                                                                                    3.2.3
  Refine List of Potential
Remedial Technologies and
 Combine into Alternatives
                                                                                                                                                                   3.2.4

-------
                                                          OSWER Directive 9380.0-3

Data available from the sampling program conducted in the limited RI

(Section 2.4.4) should be used to evaluate the potential  for waste bulking.

A more detailed discussion of bulking is presented in an  example bulking

consolidation protocol, included as Appendix C.


The user should identify the remedial technologies that address  cleanup  of

the project site with respect to the contamination migration pathways.   For

surface tanks and drum sites, remedial technologies are primarily those

which provide for direct control of the wastes.  Conceptual  technologies

can be different for tanks than for drums.  Materials stored in  tanks have

the potential for a broader spectrum of control technologies because:


    •  It is more cost-effective to manage bulk quantities than  small
       drummed quantities

    t  Experience has shown that there is more uniformity to wastes in  a
       tank because the material was either a raw product or had the
       potential for recycling or incineration.  Bulking  in  tanks from
       drums or bulk shipments was typically done at these sites to
       maintain a certain quality or characteristic for reuse or processing
       for reuse.


Typical conceptual  technologies for various categories of drum and tank

sites include:
    •  Physical/chemical/biological treatment (or pretreatment)  to reduce
       the hazard

    •  Incineration to destroy the waste

    •  Processing, such as solidification, then land disposal  (review
       current policy with EPA and regulatory agencies)

    •  Deep well injection (review current policy with EPA and other
       regulatory agencies)

    •  Recycle and reuse with or without pretreatment

    •  Direct land application (review current policy with EPA and other
       regulatory agencies)


The designation of appropriate treatment methods will depend largely on the
form of wastes  (e.g. solid, liquid, or sludges) and concentration of the
                                    3-5

-------
 OSWER Directive 9380.0-3
 waste  materials  as well as  various  site characteristics.  Hence, special
 attention  may  have to  be directed toward the evaluation of physical phase
 separation procedures  as a  means of  increasing waste suitability for a
 particular disposal option.

 A matrix has been developed to  relate the type of wastes to be handled at
 drum and tank  sites to the  types of  waste treatment and disposal systems
 available. The  treatment methods available for review are shown in Table
 3-1.  Only those treatment  methods which have potential applicability to a
 given  waste type and/or disposal categories (based on best engineering
 judgment and past experience) should be reviewed.  This information has
 been developed as a planning guide and assigned designations should always
 be re-evaluated  in terms of waste and site specific information.

 Each activity  or option has been designated either:  (1) a reasonable
 option, or (2) a non-reasonable option.  A "reasonable option" designation
 is given for a particular waste if,  from a technical perspective, a
 treatment/disposal option has been shown to be feasible and reliable.  For
 example, the treatment of aqueous wastes from an uncontrolled hazardous
 waste  site by  physical/chemical processes has a fairly well  established
 "track-record."  A non-reasonable designation is given for a particular
 waste  stream when a treatment/disposal option would not be technically
 feasible for a drum and tank site or is only feasible under unique
 conditions.

 After  an initial determination of the technical feasibility of a remedial
 technology, a determination should be made of whether the alternative is
 either prohibited from selection as  a matter of law (such as off-site
 disposal of hazardous waste from a Superfund site at a facility not in
 compliance with  Subtitle C of RCRA)  or is otherwise inconsistent with
 another environmental  standard.  An  alternative which is legally prohibited
 for Superfund actions may not be selected.  On the other hand,
 identification of an apparent inconsistency with another standard or
criteria does not rule out selection of an alternative but should trigger a
more thorough inquiry into the ability of that alternative to achieve
adequate protection of health and the environment.  EPA has proposed a

                                     3-6

-------
                                                                        OSWER Directive 9380.0-3
                           TABLE 3-1  CATEGORIES AND POTENTIAL

                             TREATMENT/DISPOSAL TECHNOLOGIES
                      ON-SITE
                       PREP
                     ACTIVITIES
TREATMENT AMD DISPOSAL
TANK AMO DRUM
WASTE CATEGORIES
AQUEOUS WASTE;
• Acid: pH < 2.0
. Bose-pH > 12.0
• Base with Sulfur
• Base vith Cganida
ORGANIC LIQUIDS
• High Halogen content ( >2%
Organic liquids Including
* Lov Holootn content 4J-2K)
• Oils non-PCS oantvntutxl
PCB Contaminated Liquid
* (50-500 ppm)
PCB Contaminated Liquid
* ( > 500 ppm)
CONTAMINATED WATER

. 2 < PH < 1 2
• Inorganic
• Orgenic
. PCB Contaminated Liquid
( < 50 ppm )
• Pesticide
SLUDGE/SOLIDS
* Organic Lav Halogen
Organic High Halogen
* Inorganic
. Flashpoint << 70° F>
. Flashpoint (> 70-1 40°F)
. Flesh point (> 140° F)
PCB Contaminated Solid
* (<50ppm)
PCB Contaminated Solid
* 050-500 ppm)
PCB Contaminated Solid
(>500ppm)
. Pesticide
. Petroleum Residues
SPECIAL WASTES

> Radioactive
• Strong Oxidlzar
• Strong Reducer
. Lab Pecks
. Explosives
i
m u
1
1
1
1

1
1
1
1
1

1
1
1
1
1

1
1
1
2
1
1
1
1
1
| *
1



2
1
2
2
Absorption/ 1
SoHdtflcjtton 1
2
2
2
2

2
2
2
Z
2

2
2
2
2
2

1
2
1
2*
2
1
1
2
2
2
1



2
2
2
2
!ii
it!
,
i
•
•

2
2
2
2
2

t
1
1
2
1

1
2
1
2
2
1
2
2
2
1
1



1
•
2
2
S«hdlfK«ltoo/
ChtmwAl Fixation
D«ton«tton
2
2
2
2

2
2
2
2
2

2
2
2
2
2

1
2
1
2
2
1
2
2
2
2
1



2
2
2
2
2
2
2
2

2
2
2
2
2

2
2
2
2
2

2
2
2
2
2
2
2
2
2
2
2
ll
:t £
1
1
1
1

2
1
1
1
1

1
1
1
1
.

1
1
1
2
2
1
1
2
2
1
1
: : 1
" * " fc.
: S ' _ : 1 $ „
-, i f - >- => c
III ! i 111 !i
2
2
2
2

2
1
1
2
2

2
2
1
2
1

1
1
2
2
2
2
1
1
1
2
1



2
2
..
1


1
1
1
1


2
2
2
2
2
2
2
2

2
1
1
2
2

2
2
1
2
2

2
2
2
2
2
2
1 •
2
2
2
1



2
2
2
2
2
2
2
2

2
2
2
2
2

2
2
2
2
2

1
1
1
2
I-
1
1
1*
1 •
1
1
2
2
2
2

I
1
1
1
1

2
2
2
1
2

1
t
2
1
1
1
1
1
1
1
1



1
'
1
2


2
2
1
1
1
1
2
2

2
t
1
2
2

2
2
2
2
2

2
2
2
2
2
2
2
2
2
2
1
: . c
: - o
ill!!
II! i!
i
i
2
2

2
2
1
2
2

2
2
2
2
2
1.
1 •
2*
2*

2»
2»
2
2
2

1-
1*
1*
2
2

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2



2
2
2
2


2
2
2
2


2
2
2
2
Phased vaste shall be separated and handled as individual vaste items
Mixed veste shall be classified under the more restrictive disposal cetegoru.
1  - Reasonable Option
2 - Not Reescnablel Impractical,Technically Infesstble)
• • Further detiiled analysis is verranted
                                         3-7

-------
OSWER Directive 9380.0-3

policy on compliance with other environmental  laws which, when final, would

restrict EPA from selecting alternatives which did not attain or exceed

applicable or relevant federal  standards, except in certain limited

circumstances."


The delineation of on-site or off-site treatment processes is also

important from a planning perspective.  In some cases the designation for

similar waste classes and treatment/disposal  options indicate that on-site

options are not as favorable/reasonable as off-site options for tank and

drum sites.  The following issues summarize the reason for this difference:


    •  Off-site options are usually already existing and design, capital,
       and start-up costs and schedule considerations are not a factor.

    •  Infrastructure, i.e. utility, support requirements for some on-site
       treatment/disposal options may be difficult to satisfy on some
       sites.

    •  Physical site features may be restrictive for on-site activities.

    •  Temporary on-site or mobile facilities  may not have the through-put
       capability of more permanent off-site facilities.

    •  The off-site cost may be considerably less since the capital costs
       for a facility erected on-site should be credited entirely to the
       waste managed at that site, whereas if an off-site alternative is
       selected, the capital costs are spread  over all uses of the facility
       over time.  Even though transportation  costs must be incorporated
       into an off-site alternative, this is often far outweighed by
       capital costs, review schedules and practicality.

    •  On-site disposal would require extensive engineering and design, and
       may include meeting post-closure monitoring and maintenance
       requirements.  These factors render on-site disposal more difficult
       from cost, schedule and effort perspectives.


On-site treatment may be limited to pretreatment for the purpose of

consolidating specific waste types or characteristics such as phase

separation, coalescing for oil  extraction, chemical incompatibility,

neutralization, solidification and bulking.


The types of solidification/fixation technologies that could be used for

either on or off-site are dependent on two basic properties of the waste:

1) physical  state, i.e. liquid, sludge and solid, and 2) chemical  nature,


                                    3-8

-------
                                                          OSWER Directive 9380.0-3
i.e. organic and inorganic.  The application of these technologies is
directly related to the final disposal of the material.  Solidification
generally refers to techniques that reduce the leachate production
potential by physical processes whereas fixation techniques typically
reduce leachate potential by chemical  processes.  These terms are often
used interchangeably and both are often referred to as stabilization
techniques.

In many cases, the relative cost per volume (or economy of scale) to
provide the extra handling and meet the analytical requirements for
chemical fixation can be very high.  Chemical fixation is more widely
applicable for inorganic wastes such as, fly ash, scrubber residue, and
metal tooling and plating by-products.  The inorganic wastes can  be readily
mixed with lime, fly ash and ready-mix concrete.  Solidification/fixation
technologies have been more widely applied to inorganic wastes than organic
wastes, however, some developing techniques have been successfully applied
to various types of organic wastes.  Solidification/fixation of wastes can
be performed either on or off-site and is typically appropriate before
final disposal.

Commonly utilized off-site treatment and disposal systems include physical/
chemical treatment, land disposal, and incineration.  Recycle/reuse has
limited applicability for drum wastes, because one would not expect to find
significant volumes of "pure" waste.  It can be more readily applied to
tank wastes, in part because of the larger volume and consistency of waste.

Where unusual or uncertain waste characterization or composition makes
determination of probable treatment efficiencies questionable, it may be
necessary to conduct bench-scale treatability studies or other tests in
order to ensure full-scale success.  For example the BTU value of a waste
may need to be determined if incineration costs are to be accurately
developed or knowledge of the percent solids of a sludge may be necessary
for the evaluation of some technologies.  Additionally, a study utilizing a
                                    3-9

-------
 OSWER Directive 9380.0-3
 small  activated  carbon column may be conducted to determine removal
 efficiency  for various organics.  Evaluated treatment systems which require
 such  pilot- or bench-scale verification should be identified, along with
 the time  and materials needed for their execution.

 Planning  for the handling of empty drums should also begin at this stage of
 the limited FS.  Depending upon waste characteristics and earlier uses and
 activities  at a  site the condition of drums can vary.  Some drums may be
 severely  deteriorated and highly contaminated, while others may be clean
 and never used.  Typically, an empty drum is defined as a drum which has
 one inch  or less of residue left in the bottom of the drum (refer to 40 CFR
 261.7  for further details). If the drum is not cleaned further it can be
 crushed and disposed of as a bulk hazardous waste.  If the drum is cleaned
 it may be recycled/reused or disposed of (possibly in other than a
 hazardous waste  landfill).  The cleaning requirements are very strict
 (refer to 49 CFR 173.28) for the reuse of drums that contained hazardous
 waste.  The cost of drum cleaning would have to be balanced with the
 alternative cost of crushing and direct disposal.

 3.2  SCREEN INITIAL REMEDIAL TECHNOLOGIES

 Section 300.68(h) of the NCR requires that these potential technologies be
 screened  using the following criteria:

    t  Technical, reliability and feasibility (Section 3.2.1)

 As a result  of the technology screening, inappropriate technologies are
 eliminated  from  further detailed analysis.  The remaining technologies are
 screened  for:

    •  Environmental  and public health impacts (Section 3.2.2)
    •  Cost  (Section 3.2.3)

For a  simple site,  one that has a few hundred drums and one or two above-
ground storage tanks,  the user should proceed directly to Section 3.3
because the  low  volume typically limits the applicability of many options.

                                    3-10

-------
                                                           OSWER Directive 9380 0-3

 3.2.1   EVALUATE  TECHNICAL  RELIABILITY  AND  FEASIBILITY

 Purpose

 The  purpose  of this  task  is  to  evaluate  the  feasibility and reliability of
 the  remedial  technologies  given the  location and conditions of the
 hazardous  waste  site and  of  the surface  tanks and drums on the site.
 Additionally, potential  limitations  due  to state-of-the-art applications or
 limited "track record" will  be  defined.

 Techniques

 The  user should  identify the  level of  technology development, performance
 record, and  inherent construction, operation, and maintenance problems for
 each technology  considered.   An  example  of an unreliable technology might
 be an off-the-shelf  process  or  package system that is waste specific.  On
 many drum  sites  the  waste  is  not homogeneous.  On such wastes, waste-
 specific process trains would have a limited application.  Technologies
 which are  unreliable, offer  inferior performance, or are not demonstrated
 processes  should be  eliminated  from  further consideration. Technologies
 available at permitted off-site waste  management facilities can, for the
 most part, be considered proven technologies.

 Technologies that are in experimental  or developmental phases may be
 acceptable, however, they  should be  evaluated very carefully particularly
with regard to waste specificity restrictions.  Experimental processes for
 a drum  and tank  site could include on-site, bio-assimilation, or any such
 "treatment" process with unique performance requirements.  In order to get
a reasonable estimate on technical reliability and feasibility development,
or experimental  processes, may  require fairly extensive pilot testing.
Some may show promise on a specific waste stream or in test operation.  In
most cases, however, these could only  handle a fraction of the material
                                    3-11

-------
OSWER Directive 9380.0-3
(particularly drum wastes) found at the site because of the very
heterogeneous nature of wastes and specificity of many treatment processes.
The potential applicability to large volumes of homogeneous tank waste may
be better than for use on drum wastes.

Limitations

Limitations of various remedial technologies applicable to surface tank and
drum sites are presented in Planning and Implementation of Response Actions
for Hazardous Waste Sites with Drums, U.S.  EPA, Contract No. 68-03-3113.  A
general screening methodology for evaluating the limitations of remedial
technologies at any type of site (not necessarily a tank and drum site) is
presented in the Handbook for Remedial Actions at Haste Disposal Sites
(EPA, 1982).

3.2.2  EVALUATE ENVIRONMENTAL AND PUBLIC HEALTH EFFECTS

Purpose

The purpose of this task is to evaluate the identified technologies that
have significant adverse environmental effects and/or are not likely to
achieve adequate control of the hazardous wastes at the surface tank and
drum site.  Potential positive environmental features should be defined as
we! 1.

Techniques

As indicated, this analysis should focus on both negative and positive
impacts.  Some alternative technologies may have emissions/discharges
requiring careful control, while others may require more materials handling
and increase the risks of exposure or accidents.  From a positive or
beneficial impacts perspective, some technologies could be more effective
in site cleanup and/or waste destruction.
                                    3-12

-------
                                                          OSWER Directive 9380.0-3


Potential adverse environmental and public health impacts which may
preclude the use of an alternative should be identified.  This is most
effectively accomplished by conceptually identifying the major steps
involved in implementing each alternative and then determining if any will
result in adverse environmental or public health impacts.  Positive impacts
of an alternative should be considered against any potential  adverse
impacts from an alternative's implementation.  Representative site and
waste characteristics which could be considered in this analysis are
presented in EPA's Guidance Document for Feasibility Studies Under CERCLA
(EPA, 1985).

Inconsistency with other environmental requirements, such as the following
examples, may indicate that an alternative may not adequately protect
public health and the environment.

    •  Air emissions of chemicals that would exceed Clean Air Act regula-
       tions or state requirements for toxic compounds
    •  Discharges to surface soils that would exceed land disposal
       regulations
    •  Discharges to ground water that would violate federal or state
       regulations
    t  Discharge to surface waters that would violate any applicable
       federal or state regulations

Limitations

When conducting this environmental screening, certain limiting factors
should be considered to control the level of effort expended.  Due to the
limited scope of typical operations, major environmental  issues are  not
usually expected from drum and tank remedial actions.   For example there
would be little excavation of material that would  enhance the
volatilization of organics.
                                     3-13

-------
 OSWER Directive 9380.0-3

 The objective  of the evaluation  is not to extensively evaluate substan-
 tially  similar technologies  but  rather to consider the major differences
 between alternatives.   For example,  similar on-site alternatives can be
 eliminated  if  those technologies  being considered will result in un-
 acceptable  discharges to the environment.  It should be noted that this
 analysis pertains  to on-site remedial actions and transport to off-site
 facilities.  It is  assumed that off-site treatment and disposal would be
 performed in compliance with all  applicable environmental regulations by
 regulatory  permit  conditions.

 3.2.3  EVALUATE COSTS

 Purpose

 The objective  of cost screening  is to evaluate identified technologies, and
 define  those that  have  costs which are significantly greater (e.g., an
 order of magnitude) than other alternatives, and do not provide
 substantially  greater environmental  or public health benefits.

 Techniques

 The screening  can  be divided into three basic tasks: (1) estimation of
 costs for each technology; (2) present worth analysis of each technology,
 if  applicable, and (3)  cost  comparison of the technologies.

 Costs consist  of all  financial outlays required for implementation of the
 action  including engineering, design, construction, operating and mainte-
 nance expenditures, general  and administrative expenses, material
 transportation and disposal, and  other costs as appropriate.  Major cost
 categories and components of cost categories are highlighted in the
 Guidance  Document for Feasibility Studies under CERCLA (EPA, 1985).

Additional costs may exist,  depending upon the particular remedial alter-
native under investigation.  These costs should be identified and evaluated
on a case-by-case basis.  Also, there may be situations where revenues
                                    3-14

-------
                                                           OSWER Directive 9380.0-3
 could  be  realized  as  a  result  of  some  recovery  value of a particular waste
 and  these would  be considered  in  the cost  analysis.

 A  present worth  analysis  may be necessary  to  compare alternatives that have
 expenditures  which occur  over  different  time  periods.  EPA's Costing
 Procedures Manual  should  be  referenced for procedures  on conducting present
 worth  analysis.

 The  focus of  this  screening  analysis is  on relative differences in costs.
 Therefore, the  required detail  is not  as extensive as  a more comprehensive
 design/feasibility type study.

 Limitations

 When preparing  screening  cost  estimates, the  objective in calculating the
 costs  is  to achieve at  least an accuracy of -50 to +100- percent.

 3.2.4  REFINE LIST OF POTENTIAL REMEDIAL ACTION ALTERNATIVES

 Purpose

 This task consolidates  the results  of the  screening activities described in
 tasks  3.2.1,  3.2.2, and 3.2.3.  The principal objective during this task is
 the development  of a  list of potential remedial action alternatives that
 appear reasonable  in  terms of:

    t  Technical feasibility and  reliability
    •  Minimizing  actual  or potential environmental and public health
       impacts from the tanks and drums
    •  Capital,  operation and maintenance  costs

 Techniques

 Treatment  technologies  with severe  constraints  due to  design limitations,
marginal  track records  or application to only a small  fraction of the waste
would be  initially screened from  the candidate  list of potential

                                    3-15

-------
OSWER Directive 9380.0-3

technologies.  Further screening using the criteria of preliminary cost,
general environmental and public health effects would eliminate those
technologies with relatively poor ratings from further consideration.
Technologies with high relative costs with no significant environmental or
technical benefits should be screened out.  Those options with unacceptable
adverse environmental impacts or public health risks would be eliminated.

The remaining technologies would have no major limitations from a technical
feasibility and reliability perspective while at the same time appearing
reasonable in terms of cost and environmental and public health issues.
These remaining technologies would be combined to form various alternative
remedial actions for handling the identified tank and drum waste found
on-site.

The categories of basic remedial alternative strategies should include:

    •  Alternatives for off-site treatment or disposal
    •  Alternatives which attain applicable or relevant federal public
       health and environmental standards
    •  Alternatives which exceed applicable or relevant federal public
       health or environmental standards
    •  Alternatives which do not attain applicable or relevant federal
       public health or environmental standards but will substantially
       reduce the likelihood of present or future threats from hazardous
       substances
    •  Consideration of the no action alternative to assess the public
       health and environmental threats that exist at a particular waste
       site

Limitations

There may be a tendency to "over analyze" the potential list of alter-
natives in terms of the previously defined screening criteria.  This  entire
screening process should not require a very detailed and/or laborious
effort.  Many of the relative ratings and decisions can be based upon  good
engineering, economic, and scientific judgments and experience.
                                    3-16

-------
                                                          OSWER Directive 9380.0-3
3.3  CONDUCT DETAILED ANALYSIS OF POTENTIAL REMEDIAL ACTION ALTERNATIVES

The objective of this detailed analysis is to develop sufficient
information to permit the comparative evaluation of alternative remedial
actions and, if requested, recommend a remedial  action for a specific drum
and tank site.  In order to address the evaluation criteria outlined in the
NCR, four major areas of analyses are recommended in the evaluation of
alternative remedial actions:

    1.  Technical  features (Section 3.3.1)
    2.  Costs (Section 3.3.2)
    3.  Environmental and public health features (Section 3.3.3)
    4.  Regulatory and institutional issues (Section 3.4.4)

Depending upon the complexity of the tank and drum site, this evaluation of
alternative actions should proceed in a straightforward and timely manner.
The evaluation is not meant to be exhaustive but rather provide sufficient
documentation for the support of a remedial action.

3.3.1  PERFORM TECHNICAL ANALYSIS OF ALTERNATIVES

Purpose

The purpose of the technical analysis will be to evaluate the potential
remedial action alternatives from an engineering standpoint.  To ensure
that specific technical criteria are met, emphasis will be placed on proven
technologies.  Even with proven technologies, a significant degree of
variation can exist between the success of techniques for different wastes
and in different hydrogeological/site specific settings.

Techniques

The user should evaluate each of the remedial action alternatives to
specify major equipment sizes and specifications, personnel and utility
requirements, and specific waste disposal strategies.  Using the

                                    3-17

-------
OSWER Directive 9380.0-3
information developed, the user should compare the alternative actions
using the following technical criteria:

    •  Performance - Effectiveness in accomplishing design objectives,
       useful life
    •  Reliability - Dependable in meeting design objectives, degree of O&M
       requirements to keep operational
    •  Implementability - Suitable conditions for construction (both
       on-site and external to the site), time (to implement, to achieve
       beneficial results)
    •  Safety - On-site personnel, nearby communities, and surrounding
       environment

A tabular summary can be useful  for presenting the key positive and
negative features of an alternative within each of the technical  evaluation
criteria.

Additional guidance regarding the details of appropriate technologies for
actions at tank and drum sites and use of the technical comparison criteria
is available in the referenced literature (Section 5).  Specific informa-
tion on particular technologies  and procedures can also be obtained from
vendors, equipment manufacturers, and cleanup contractors.

Limitations

The "track record" of some innovative and proprietary techniques for
remedial  action is often very limited.  Therefore, the database for eval-
uating their reliability, performance and implementability can be scarce.
One should not unnecessarily expand the scope of technical analyses with a
search for data on unproven technologies.  Good engineering judgment should
be made based upon the data obtained from vendors, literature, and cleanup
contractors.
                                    3-18

-------
                                                           OSWER Directive 9380.0-3

 3.3.2   PERFORM  COST  ANALYSIS  OF  ALTERNATIVES

 Purpose

 The purpose  of  this  analysis  is  to  develop cost estimates  for the
 alternative  remedial  actions  using  the  information developed during the
 technical  analysis of these alternatives.  These cost estimates are
 site-specific and provide  the basis  for comparing the economic features of
 various remedial actions,  not for budgeting the cleanup effort.

 Techniques

 Costs consist of all  capital  outlays, operating and maintenance expendi-
 tures,  general  and administrative expenses, and other costs required for
 implementation  of the action  including  engineering, des-ign, and
 installation, as appropriate.  Cost  data developed during the screening
 analysis of  remedial  technologies are very useful and applicable for this
 more detailed analysis.

 EPA's draft  Compendium of  Cost Remedial Technologies at Hazardous Waste
 Sites (EPA,  1984) reviewed cost  categories unique to drum sites.  Base
 costs were defined considering three broad categories:

    1.  Drum removal  (including  retrieval, staging, overpacking, and
        loading)
    2.  Transportation (on-site  handling, demurrage and off-site transport)
    3.  Ultimate disposal/treatment  (tipping fees, surcharges and taxes)

 Items were defined which affect  the cost within each of these three broad
categories.  For example, drum removal  costs were affected by drum con-
dition, waste type, drum size, access,  etc.; transportation was basically
influenced by material weight and volume relative to distance; and disposal
and treatment were influenced by both the physical and chemical character-
istics of the waste.
                                    3-19

-------
OSWER Directive 9380.0-3

When evaluating the cost-effectiveness of various approaches or alter-

natives, many scenarios must be considered and flexibility should be

maintained.


For example, there are various factors which can influence the overall cost
for handling and treating/disposing drum wastes.  Some general items one

should consider when reviewing various scenarios are summarized below:


    •  It is generally less expensive to handle and transport drum waste if
       they are bulked as compared to overpacked

    0  Disposal facilities generally charge more to handled drummed waste
       than an equivalent amount of bulked waste

    •  Compatibility limitations of various wastes will restrict the amount
       of drum waste that can be bulked


There are many similar cost components for both on- and off-site remedial

alternatives.  For example, drum staging and sampling, and many site prepa-
ration/mobilization costs are similar.  However, there are some major cost

components which are different for both on- and off-site approaches.  For
example, transport requirements could be a major cost component for an

off-site alternative, whereas an on-site alternative may have relatively
minor transport costs.


To analyze the costs for each alternative remedial action, the user should1
perform the following steps:


    •  Estimation of Costs - estimate capital  (direct and indirect) and
       annual operating and maintenance costs of the remedial alternatives.

    •  Economic Analysis - using estimated costs, calculate stream of
       payments and present worth for each remedial action alternative (for
       most short-term remedial actions, e.g., six months, this is not a
       major concern unless there are long-term maintenance and/or
       monitoring requirements).

    •  Sensitivity Analysis - evaluate risks and uncertainties in cost
       estimates.

    •  Input to Cost Analysis - identify input data and reliability
       necessary to evaluate costs of remedial action strategies.
                                    3-20

-------
                                                          OSWER Directive 9380.0-3
Information regarding the procedures involved with these steps  is  presented
in the Guidance Document for Feasibility Studies under CERCLA (EPA,  1985).
References listed in Section 5.0 provide additional  information on the
costs of different technologies.  This information,  plus vendor/contractor
input, should be used to develop the cost estimates.  Additionally,  the
results of remedial activities at other tank and drum sites can provide
cost data which are very useful for comparative purposes.  A range of
discount rates may be useful during the sensitivity analysis.

Limitations

The objective in calculating the costs is to achieve an accuracy within -30
to +50 percent.  Failure to adequately estimate the cost for items such as
contractor mobilization/demobilization, stand-by-costs, as well as waste
transportation and disposal and laboratory analyses can substantially
impact this objective.

A potential area of cost uncertainty is the estimated quantities for
various waste disposal categories (based upon the data obtained during  the
limited RI).  The basis for conducting random sampling is presented  in
Section 2.4 and while providing useful information, the applicability of
the data for some uses can be limited.  Depending upon the approach  of  any
previous drum sampling, one should define the confidence limitations of
extrapolating projections for the entire site from a potentially limited
database.  As long as one is aware of the potential  limitations of the
database, this knowledge can be applied consistently for all alternatives
reviewed.  This is particularly important to consider in the cost  analysis
of alternatives that are particularly sensitive to the estimated quantities
of particular wastes.
                                    3-21

-------
 OSWER Directive 9J80.0-J

 3.3.3  PERFORM  ENVIRONMENTAL AND  PUBLIC  HEALTH ANALYSIS

 Purpose

 Section 300.68(j)  of the NCP requires that the alternative  remedial action
 selected for  implementation at a  surface tank and drum hazardous waste site
 effectively mitigate and minimize damage to and provide adequate protection
 of  public health,  welfare, and the environment.  This activity, as required
 by  the  NCP, evaluates the effectiveness of alternative remedial actions in
 terms of environmental and public health issues.  This analysis not only
 focuses on the  mitigative effectiveness of alternatives but also considers
 possible positive  and negative secondary/indirect effects.

 Techniques

 For the particular site and alternative remedial actions being considered,
 the user must first make three basic determinations.  These are:

    1.   The requirement for an environmental assessment of adverse impacts
    2.   The level  of detail required in the assessment
    3.   The scope  of the assessment

 The environmental  analyses for drum and tank sites are fairly straight-
 forward.   On-site  remedial alternatives typically require more detailed
 environmental analyses than off-site alternatives.  For both concepts there
 are many  similar areas of concern, such as spillage and volatile emissions
 during  drum handling and staging.  Additionally, reuse or destruction,
 whether  on- or  off-site, is environmentally desirable.

 On-site  remedial actions should go through a fairly extensive environmental
 review.   An area of concern for on-site disposal is the risk and potential
 effect of  failure  (e.g., if a liner and leachate collection system fails,
will wastes migrate during high ground water conditions?).
                                    3-22

-------
                                                           OSWER Directive 9380.0-3


Off-site  remedial  actions  involve  receiving  facilities and transport
operations.   Environmentally  sensitive  areas  along  nearby transport routes
have to be considered,  along  with  potential  impacts at the final site of
treatment and/or  disposal.

The Guidance  Document  for  Feasibility Studies  under CERCLA (EPA, 1985)
provides  information  regarding  these determinations.  Literature cited in
the references  provides  useful  information regarding implementing and
summarizing the assessment.

Limitations

This analysis should not be an  exhaustive research exercise.  It's focus
should be clearly  on effectiveness of alternatives in mitigating potential
environmental and  public health  issues  of concern.

3.3.4  PERFORM  REGULATORY AND INSTITUTIONAL ANALYSIS OF ALTERNATIVES

Purpose

This analysis allows a comparative review of the extent to which those
alternatives under consideration are consistent with other environmental
requirements and take into account various institutional constraints.

Techniques

The user  should identify and  meet with  the appropriate officials at the
federal (regional), state, and  local levels to discuss the alternative
remedial   actions being considered for the surface tank and drum site.

Information on the responsibilities, authorities, and potential roles of
federal agencies during the planning and implementation of a remedial
action is presented in Guidance Document for Feasibility Studies under
                                    3-23

-------
OSWER Directive 9380.0-3

CERCLA (EPA, 1985).  EPA is developing policy on the use of permanent
remedies (such as treatment or destruction) and addressing when disposal in
double-lined facilities are appropriate.

In determining what cleanup levels or technologies provide adequate
protection of public health and the environment, EPA considers other
environmental laws and regulations that are applicable or relevant to the
site.  EPA has proposed a policy which would require cleanup actions to be
consistent with these other laws and regulations except when certain
specified situations exist.

Off-site storage, treatment, or disposal facilities must have an applicable
RCRA permit or be in compliance with RCRA.  A RCRA compliance inspection
must have taken place within the previous six months and must demonstrate
that there are no significant violations that affect the satisfactory
performance of the facility.

In selecting an operable unit, which is not by itself the final action
necessary at a site (such as cleanup of drums and tanks at sites where
contaminated soil or ground water exists), the decision document will
indicate what additional problems will be addressed in future operable
units.

Limitations
Environmental permits are not required for on-site Superfund remedial
actions.

3.4  CONDUCT COMPARATIVE SUMMARY OF POTENTIAL REMEDIAL ACTION ALTERNATIVES

Purpose

The National Contingency Plan (NCP), Section 300.68(j) states:  "The
appropriate extent of remedy shall be determined by the lead agency's
selection of the remedial alternative which the agency determines is cost-
effective."  While an important objective is to keep costs to a minimum,
                                    3-24

-------
                                                          OSWER Directive 9380.0-3

the primary goal of the program is to provide adequate protection of the
public health and the environment.  In addition, EPA considers which
alternatives will be most cost effective in the long term, not just if  a
remedy just has lower initial capital cost.  For example, the destruction
or treatment of a waste may be preferred to land disposal even though the
cost of the former may be higher.  This decision would be based on the  need
to assure the long-term protection of the public health and  the environment
and taking into account the long-term cost of operating and  maintaining the
integrity of physical structures necessary to securely contain waste.

Techniques

The results of the detailed analyses of the alternative remedial  actions
should be organized and summarized for comparison.  The analysis should be
conducted with a precision that is consistent with the degree of knowledge
about the problem or expected results.  The framework must be tailored  to
meet the needs of each particular site evaluation by adapting the
evaluation criteria to reflect site-specific conditions, hazards, or public
concerns.

A summary table is a useful tool in organizing and presenting the results
of a composite evaluation of remedial actions involving multiple criteria.
A sample summary table for remedial actions at a hypothetical abandoned
tank site is presented in Table 3-2.  Accompanying the summary table would
be a narrative explanation for each evaluation criterion, presenting the
advantages and disadvantages for each alternative remedial action.

Limitations

Certain comparison criteria are qualitative and subjective.   Thus,
different perspectives may result in different comparison results.  A
tendency in these types of comparative evaluations is to over-emphasize the
relative importance of a particular evaluation criterion, such as costs.
However, increasing attention should be given to alternatives that are
based upon the destruction, treatment, and/or reuse of the waste material.
                                    3-25

-------
       ALTERNATIVE                 COST

  A.   No Action                    $  0



  B.   On-slte Treatment            $3m


      - bulking

      - Incineration of organlcs


      - precipitation and
CO      stabilization of metals
 I
ro
O}    - neutralization of
        corrosives

      - off-site sludge disposal

  C.  Off-site Treatment           $4m


      - on-site bulking

       -  Incineration of organlcs

       -  precipitation and
         stabilization of metals

       -  neutralization of
         corrosives
                                                                                                TABLE  3-2
                                                                            FINAL REMEDY  FOR HYPOTHETICAL  ABANDONED TANK SITE
       PUBLIC HEALTH CONSIDERATIONS

- Tank Mill continue to deteriorate and overflow

- Direct contact threat remains

- Permanent remedy


- Eliminates direct contact threat

- Extensive health and safety controls


- Most of Haste destroyed or modified
- Permanent remedy


- Eliminates direct contact threat

- Most of waste destroyed or modified
                                                         ENVIRONMENTAL CONSIDERATIONS
- Underlying Class I  aquifer threatened
- Site operation above Class I  aquifer
- Discharge to stream

- Transportation through populated  areas
  (sludge)
- Transportation through populated areas
  (untreated wastes)
    TECHNICAL CONSIDERATIONS

  Not appl1 cable
                                                                                                 33
                                                                                                 O
                                                                                                 5
                                                                                                 a
                                                                                                 <'
                                                                                                 CD
                                                                                                 CD
                                                                                                 CO
                                                                                                 CO
                                                                                                 O
                                                                                 PUBLIC COMMENTS 9
                                                                                                 CO
                                                                                 Highly opposed
  Incinerator must be designed     Mild opposition
  and constructed or mobile
- Sldestream management required
  Facility over 200 miles
  distance
                                               - Capacity  limitation
                                                                                                                                     Acceptable

-------
                                                           OSWER Directive 9380.0-3

This summary comparative analyses can provide the basis for this type of
evaluation.

Depending upon the degree of confidence and the extent of the database for
drums, it may be advisable to prepare two summary tables; one for tanks and
the other for drums.  The database for tanks will probably be more
comprehensive.  The database for drums could be limited to that obtained in
the random sampling program (refer to Section 2.4.1).

3.5  PREPARE LIMITED FOCUSED FEASIBILITY STUDY REPORT
A draft FS report should be prepared that summarizes the feasibility study
of alternative remedial actions for the surface tank and drum hazardous
waste site.  The typical section headings for this report are presented in
Table 3-3.  It is not necessary to limit the report to the listed items.
In this report it is not necessary to provide details on site background if
a full RI/FS is being conducted.  A reference to this document with only a
brief summary of a pertinent feature is appropriate.

The Guidance Document for Feasibility Studies under CERCLA (EPA, 1985)
provides additional  information regarding what should be included in the
report and why.
                                    3-27

-------
OSWER Directive 9380 0-3

                              TABLE  3-3

                  LIMITED  FEASIBILITY  STUDY REPORT


           INTRODUCTION

               •  Site Background Information
               •  Nature  and  Extent of Problems
               •  Objectives  of Remedial Action

           SCREENING OF REMEDIAL ACTION TECHNOLOGIES

                  Technical Criteria
                  Environmental/Public Health Criteria
                  Institutional Criteria
                  Other Screening Criteria
                  Cost Criteria
                  Remedial Action Alternative Development

           REMEDIAL ACTION ALTERNATIVES

               •  Alternative 1 (No Action)
               •  Alternative 2
               •  Alternative x

           ANALYSIS OF REMEDIAL ACTION ALTERNATIVES

                  Non-cost Factors
                  Technical Evaluation
                  Environmental Evaluation
                  Institutional Requirements
                  Public  Health Evaluation
                  Cost Factors

           SUMMARY ANALYSIS OF ALTERNATIVES

           RECOMMENDED REMEDIAL ACTION  (Optional)
                                  3-28

-------
                                                           OSWER Directive 9380.0-3
          4.0  TANK AND DRUM SITE REMEDIAL DESIGN/REMEDIAL ACTION
This section provides the reader with the basic approach and procedures of
tank and drum site remedial  action design.  It is not intended to be a
comprehensive guidance document on the development of contract (or
subagreement) documents and the implementation of a remedial action.  The
user should consult EPA's Superfund Remedial Design and Remedial  Action
Guidance (February 1985) for a more complete manual on the design and
construction requirements for Superfund activities.  Federal-lead contracts
should follow the Federal Acquisition Regulations (48 CFR Chapter 15 and 48
CFR Chapter 1, Subpart 1.3), while state-lead subagreements should follow
the Agency's "Procurement Under Assistance Agreements" regulation (40 CFR
Part 33).  In addition, detailed guidance on state procurement under
Superfund cooperative agreements can be found in Volume II of the manual
State Participation in the Superfund Remedial Program to be issued in
September 1985.

4.1  APPROACH

The normal  method of executing site cleanup is to use either formal
advertising or competitive negotiations to procure the services of a
responsive and responsible contractor.  In fact, on state-lead projects
formal advertising must be used to procure construction services during
remedial implementation unless the EPA official  responsible for the
obligation of funds (AA or RA) approves an alternative procurement method
in advance.  Formal advertising cannot be waived in the Superfund remedial
program by a claimed emergency situation since EPA handles  Superfund
emergencies under the removal rather than the remedial program.
Furthermore, a declaration of an emergency under state law  does not
necessarily constitute an emergency under the EPA Superfund program.

The owner must prepare contract documents which  define the  work to  be  done
and provide a basis on which contractors competitively bid  to  perform  the
work.  It is essential that these contract documents  completely and

                                     4-1

-------
 OSWER Directive 9380.0-3

 accurately  define  all the work  required.  The Construction Specification
 Institute  (CSI)  format may  be used  in preparation of contract documents for
 drum and tank  sites.  This  format keeps hazardous waste site design and
 procurement  consistent with the more conventional construction projects.
 The  CSI format breaks the work  into divisions.  Division 0 establishes the
 general project  and contractual procedures, and the technical
 specifications are included in  Divisions  1 through 16  (see Section 4.4).
 Material presented in these sections focuses principally on issues
 involving tank and drum sites.

 4.2   CONTRACTING PROCEDURE

 The  bidding  and  contract requirements define the conditions under which the
 contractor  must  perform the work for the  owner (i.e., the entity which
 provides the funds).  A number  of pricing options may apply to a particular
 contract.   These include firm fixed price (lump sum) or unit quantity and
 time and materials.

 For  fund financed  remedial actions  (state-lead projects), the recipient
 must use the formal advertising procurement method.  Formal advertising
 requires, at a minimum, the following:

     •  A complete, adequate, and realistic specification or purchase
       description of what is required
     •  Two or more responsible  bidders who are willing and able to compete
       effectively for the business
     •  A procurement that lends itself to the award of a fixed-price
       contract
     •  The selection of the successful bidder, made principally on the
       basis of  price

4.2.1  FIXED-PRICE (LUMP SUM) CONTRACT

With this type of contract, the contractor responds with a single fixed
cost price (which  includes labor, overhead, and profit) to perform the work
described in the project plans and bid documents.  This method requires the
owner to develop definitive performance specifications for the bidding
                                     4-2

-------
                                                           OSWER Directive 9380.0-3

 process  and  also  requires  the  greatest  amount  of  sampling and analysis to
 prepare  the  bid.   This  contract  is  applicable  to  such work as:

     •  Mobilization  - This includes the up-front  costs such as  insurance,
       bonding  requirements, obtaining  project-specific  licenses and
       permits, and  the development of  site-specific contingency and health
       and safety plans.
     t  Site  Preparation -  This  includes typical conditions related to
       activities such  as  roadways, clearing,  grading and staging areas and
       decontamination  pad construction.
     •  Temporary  Facilities -  These include  support facilities  such as
       trailers,  clean  zone equipment,  laboratory and utility hook-ups.
     •  Demobilization - This provides for  the  payment of basic  closure
       costs  for  decommissioning  of utilities,  final grading and reporting
       requirements
4.2.2   UNIT  PRICE  CONTRACT

This type  of contract  requires  that  the owner estimate quantities of
materials  to be disposed  of  or  treated in the bid documents.  Potential
contractors  bid on  a per  unit basis  which includes labor, overhead, and
profit.

Unit pricing  is more applicable to the waste handling and disposal areas of
the work.  The basic concept provides for a fixed unit price, per gallon,
cubic yard and/or tons, to be set at the time of bid.  This unit price
would be applied or spread over an estimated quantity of units rather than
a set quantity, since  on  a tank and  drum site only a very small percentage
of the containers may  be  sampled or  even opened.  Waste categories and
quantities are estimated  based  on site history and previous experience.
These quantities are only estimates; the actual quantities on-site will not
be known until the last container is removed.  Therefore, the unit price
system provides a mechanism for the  contractor to be paid for all
quantities found, independent of any deviation from original estimates.

Unit pricing requires that the  price quoted for each unit include the cost
for on-site material handling,  laboratory analysis, labor and equipment,
repacking/overpacking, on-site  consolidation and building, manifesting and
                                     4-3

-------
OSWER Directive 9380.0-3

off-site transfer, and off-site treatment and/or disposal.  These price
quotes are generally considered firm unless there is a significant change
in conditions or, more specifically, if there is a major increase or
decrease in the original  estimate.  The basically accepted rule of thumb is
to provide a 15 percent margin.  Deviations above or below this margin
would lead to renegotiation.  In developing the unit price bid, the
contractor will generally spread fixed costs evenly over the original
estimated quantity.  Therefore, if the actual  quantity significantly
underruns the original estimate, the contractor will not receive
compensation for all of the fixed costs incurred.  If the quantity is  much
greater than the original estimate, the owner may be entitled to a cost
reduction.  Adjustments in price occur through negotiation at the time the
change is recognized.  The unit price concept  provides a basis by which
bids can be compared and  maintains a built-in  flexibility to accommodate
change.

4.2.3  TIME AND MATERIALS CONTRACT

Under this type of contract, the contractor is paid a fixed rate (including
labor, overhead, and profit) for each hour performed and actual cost of
materials.  Because this  contract contains the least incentive to perform
efficiently, it should be used if no other contract is suitable.

It reimburses the contractor for all costs incurred for a specific scope of
work.  This approach does not provide a mechanism by which bids may be
compared, and it requires a much greater level of management by the owner.
The owner also assumes all of the risk under this option.

4.3  CONTRACT PROVISIONS

Provisions must be in a contract to address both the specific work items
comprising the known project scope and the procedures for defining and
handling out of scope activities.  In addition, specific clauses or their
equivalent are required in each contract by 48 CFR Chapter 15, and Chapter
1, Subpart 1.3 and/or 40 CFR 33 for fund-financed actions.  As with any
construction related contract, changes in the work may occur under a

                                     4-4

-------
                                                          OSWER Directive 93800-3

hazardous waste site cleanup type contract due to differing site
conditions.

4.3.1  CHANGE ORDERS

A change order is a written order issued by the owner or its  designated
agent to its contractor authorizing an addition to,  deletion  from,  or
revision of a contract.  A change order is necessary to modify, within the
scope of the project, the contract cost or scope of  work;  to  interrupt or
terminate the project; to revise the completion date; or,  in  general, to
implement any deviation from the original  contract terms and  conditions.
Change orders are issued after the execution of the  contract.  Proper
management of change orders is a key element to avoiding delays,  increased
costs, and potential contractor claims.

Change orders may be required for the following conditions:

    •  Differing site conditions
       - Subsurface or latent physical conditions at the site differing
         materially from those indicated in the contract
       - Unknown physical conditions at the site, conditions  of an  unusual
         nature, or those differing materially from those ordinarily
         encountered and generally recognized as inherent in  work of the
         type provided for in the contract
    0  Errors and omissions in plans and specifications
       - Errors are items which are described incorrectly on  the  plan  or  in
         the specifications
       - Omissions are items which are neither shown nor specified
    t  Changes instituted by changes in regulatory requirements,  such  as:
       - Changes requirements for protecting historical or archaeological
         objects
       - Revisions to building codes
       - Revisions to zoning and land use plans
       - Revisions to federal regulations and policies
       - New congressional legislation
                                     4-5

-------
 OSWER Directive 938U.G-3


     0  Design  changes,  such  as modifications to  existing design which will
        offer a savings  in  excess  of  all  costs  associated with the  change
        order,  including  future operation and maintenance costs
     •  Overruns/underruns  in quantities
     •  Factors affecting time of  completion, such as:
        -  Suspension of  work  (temporary)
        -  Direct acceleration
        -  Time  extension  for delay beyond the contractor's control
        -  Constructive acceleration
     t  Changes in contract administration procedures, such as:
        -  Progress payment  terms
        -  Retainage release
        -  Occupancy
        -  Testing
        -  Acceptance
        -  Warranties
     0   Resolution of claims
     0   Emergency conditions:
        -  Acts  of God
        -  Civil  disturbance

Tank and  drum  sites are unique in the that there are many unknowns about
the  conditions of the site and the waste that will be encountered, all of
which may necessitate change orders.  For example, if lab packs or other
unique  categories of waste materials (e.g., reactive or shock sensitive)
are  known or suspected to be on-site, then the contract document should
specify such.  However, when a contract includes specific provisions for
unique site/waste conditions, but none are found, the contract should
address limited compensation.  While no unique or special site/waste
conditions may  be found, the contractor may have had to mobilize special

                                     4-6

-------
                                                           OSWER Directive 9380.0-3

support equipment or plan for unique contingencies; for example, the
construction of on-site temporary storage facilities along with the staging
of special handling equipment for shock sensitive waste.  These are
legitimate costs which should be paid for by the owner even though no shock
sensitive wastes are found.  Another example calls for detailing the work
by using the existing information.   In this instance, a reasonably
competitive price should be  received for known and definable work items.
Modifications, as they occur, can be handled by change order.

Ultimate responsibility for  change order administration rests with the
owner.  Specifically, the owner is responsible for:

    •  Determining whether a contract change order is warranted, based on
       the terms of the existing contract and a review of the circumstances
       responsible for the alleged changed
    •  Negotiating a fair and reasonable price for price contract changes
    •  Maintaining accurate  and complete cost records for the change,
       including records of  negotiation
    •  Adequately documenting for future reference a description of the
       agreed change and reason for this change
    •  Maintaining current and accurate fiscal projections of contract and
       project completion costs
    •  Executing contract change order documents efficiently and in a
       timely manner
    •  Resolving disputes which may arise as a result of a proposal for a
       change
    f  Assessing the impact of change orders on progress toward project
       completion and acting to mitigate resulting project delays
In order to expedite review and approval of change orders, contractors
must:

    t   Adequately describe the reason for each change request
    t   Submit change order proposals in accordance with the procedures set
       forth  in the contract documents, and enter into meaningful
       negotiations on a necessary contract change
                                     4-7

-------
OSWER Directive 9380.0-3

    0  Furnish and certify the accuracy and completeness of cost and
       pricing data on enable the owner to determine the necessity and
       reasonableness of the cost proposed

Project delays and disputes resulting from change order administration can
be limited by effective and frequent communication between the owner and
contractors.

4.3.2  SPECIAL PROVISIONS

There are areas of a project that are unique to the site that are not
necessarily unknown but fall under the term "considerations."  These are
"considerations" of work items specific to the project  that the owner
expects the contractor to take into account in preparing the bid.  For
example, it is possible to encounter deteriorated drums, which are not
structually sound, at a site.   If the contractor moves  these drums,  spills
may occur.  It is not practical  for the owner to be involved in the
decision on how every drum should be handled, typically this is left up  to
the experience of the contractor.  However, the owner does not want  to be
responsible for the contractor's mistakes that result in spills, so  the
owner under such a scenario would put a provision in the contract
requesting that the contract provide a contingency plan for handling spills
and that the contractor reflect  this in the bid price.   This builds  a
maximum level  of care into the contractor's drum handling operation.

The owner may also want to make  the contractor aware of other conditions
that the owner will not take responsibility for, but that the contractor
should take under consideration.  These could include provisions for:

    •  Conducting cleanup operations during the summer  and winter months
       under level "B" protection
    •  Allowing for periods of inclement weather when scheduling cleanup
       activities
    •  Providing enough support  equipment (e.g., air compressors) to allow
       optimum use of on-site personnel with the level  "B" protection
                                     4-8

-------
                                                          OSWER Directive 9380.0-3

    •  Safety and contingency procedures to handle the discovery of very
       unique situations not detected in previous sampling activities or
       field work (e.g., radioactive material which may require involvement
       of the Nuclear Regulatory Commission)

Experienced contractors should be familiar with these and other standard
operating conditions at tank and drum sites; however, it is  in the owners
best interest to include such items in the contract.

4.4  DESIGN REQUIREMENTS

As stated previously, the bid document presents the basis for conducting
project design and implementation.  In general, a tank and drum remedial
design will contain the General Condition section; the up-front boilerplate
or contractual language similar to most construction projects.  The next
section of source of information is the Technical Specifications section
which outlines specifically how the work will be conducted.   Table 4-1  is a
typical table of contents of the Technical Specifications section.  Much of
the material under Divisions 1 and 2 present the basic project
requirements, which closely coincides with the lump sum items.  Division 13
focuses on the special conditions of tank and drum waste and details how
these materials are to be handled.  Because each drum probably contains
waste with unique characteristics, the common basis for design and
specifications for tanks and drums is health and safety.

Drums are handled individually by specially designed equipment.  All drums
are sampled and tested for reactivity and potential compatibility.  Drums
on-site are probably not Department of Transportation (DOT)  approved;
therefore, if an individual container is to be removed, it must be repacked
or overpacked.  To the maximum extent possible, compatible wastes are
consolidated and the original drum is crushed for disposal as bulk waste
material  at secure land disposal facilities.  Depending upon drum
conditions, empties could be recycled once strict regulatory requirements
have been met (see 49 CFR 173.28).
                                     4-9

-------
OSWER Directive 9380.0-3
                                   TABLE  4-1

                      TABLE  OF  CONTENTS FOR DRUM  DISPOSAL

                          TECHNICAL  SPECIFICATIONS
   DIVISION  1   -   GENERAL  REQUIREMENTS

        01010      Summary  of Work
        01018      Site  Utilities
        01030      Special  Project  Procedures
        01060      Regulatory Requirements
        01150      Measurement  and  Payment
        01203      Job Site Administration
        01300      Submittals
        01590      Temporary Facilities
        01700      Contract Closeout

   DIVISION  2   -   SITE  WORK

        02100      Site  Preparation

   DIVISION  13  -  SPECIAL  CONDITIONS
        13571
        13572
        13573

        13574
        13575
        13576
        13577
        13578
        13579

        13580
Drum Handling Protocol
Drum Sampling Protocol
Bulking and Consolidation Protocol  (Analytical
  Procedures Included)
Securing of Radioactive Waste
Securing of High Hazard Waste
Disposal of Chemical Waste
Collection and Handling of Sludges
Transport of Hazardous Material
Sorting, Identification, Packing and Disposal of
  Packaged Laboratory Chemical Wastes  (Lab Packs)
Securing, Identification, Transport, and Disposal of
  Pressurized Cylinders Containing  Toxic, Explosive,
  and/or Other Material
  APPENDIX
  Waste Transport Route
  Summary of Waste Categorizations Found On-Site
  Personnel Safety/Protection Standards
  Special Category of Wastes for Disposal
       A
       B
       C
       D
       E
High PCB (>500 ppm), Low Flashpoint Liquids
PCB-Contaminated Solids
Waste Resins
Glycols
Classification of Sludge Materials
                                   4-10

-------
                                                          OSWER Directive 9380.0-3

                            5.0  REFERENCE GUIDE
The references included in this section are organized according to the
section titles of this guidance manual.  References are not duplicated even
though many apply to several areas.  In searching for additional material
on a particular subject, do not limit your search to the section headings
covering your specific area of interest.  Some sections do not have
additional referenced material and therefore are not listed.  Review the
references listed under other headings to complete your search within this
manual.  Some references are cross referenced when the reference is
particularly applicable to more than one section.

Note that Section 3.3.1 contains a lengthy compilation of articles
regarding potential alternative technologies that may be considered while
searching for available alternative remedial actions.  The list is
intentionally long to provide the users of this manual  with the wide range
of alternatives available and to stimulate additional creative thinking
along the lines of alternative treatment and disposal techniques,
especially for alternatives to land burial  of hazardous wastes.
FOREWORD
       U.S. Environmental Protection Agency.  1983.  Draft Survey and Case
       Studies of Remedial Actions at Hazardous Waste Sites.  Washington,
       DC: JRB Associates and Environmental  Law Institute.  Prepared for
       U.S. Environmental Protection Agency Municipal Environmental
       Research Laboratory, Cincinnnati, Ohio.
       	.  1985a.  Guidance on Remedial Investigations Under
       CERCLA.  Washington, DC: EPA Hazardous Waste Engineering Research
       Laboratory (Cincinnati), Office of Emergency and Remedial  Response,
       and Office of Waste Programs Enforcement.  Prepared by: JRB
       Associates.  May.
       	.  1985b.  Guidance on Feasibility Studies Under CERCLA.
       Washington, DC:  EPA Hazardous Waste Engineering Research Laboratory
       (Cincinnati), Office of Emergency and Remedial Response, and Office
       of Waste Programs Enforcement.  Prepared by: JRB Associates.  May.
                                     5-1

-------
OSWER Directive 9380.0-3

2.0  LIMITED REMEDIAL INVESTIGATION

2.1  DEVELOP SITE DESCRIPTION AND DATA BASE

       Hillenbrand,  E.  and B. Burgher.  1982.   Spill  Incidents at Hazardous
       Material  Storage Facilities:  An Analysis of Historical Data From
       the PIRS  and  SPCC Data Bases.   In:  Management  of Uncontrolled
       Hazardous Waste  Sites National  Symposium.  EPA et al.   Washington,
       DC. November  29  - December 1.

       See EPA (1985a)  under Foreword

2.2  SITE FAMILIARIZATION AND PROJECT  APPROACH

       U.S. Environmental  Protection Agency.  OERR Environmental  Response
       Branch.  1984.  Standard  Operating  Safety Guides. Washington, DC:
       EPA.  November.

2.2.2  PREPARE INITIAL  HEALTH AND SAFETY GUIDE

       Bareis, D.; Cook, L.; and Parks, G.   1983.  Safety Plan for
       Construction  of  Remedial  Actions.  In:  Proc. National  Conference on
       Management of Uncontrolled Hazardous Waste Sites.  Washington, DC.
       October 31 -  November 2.

       Buecker,  D.A. and Bradford, M.L.  1982.  Safety and Air Monitoring
       Considerations at the Clean Up  of a  Hazardous  Waste Site.  In:
       Management of Uncontrolled Hazardous Waste Sites National Symposium.
       EPA et al. Washington,  DC.  November 29 - December 1.

       Sax, N.I.  Ed. 1979.   Dangerous Properties of  Industrial  Materials.
       5th Ed. Van Nostrand: New York, 1979.

       International Technical  Information  Institute.   1976.   Toxic and
       Hazardous  Industrial  Chemicals  Safety Manual for Handling and
       Disposal  with Toxicity and Hazardous Data.  Tokyo, Japan:
       International Technical  Information  Institute.

       Merck & Co.  1968.   Merck Index, An  Encyclopedia of Chemicals and
       Drugs. 9th Ed.   Rahway.

       Meyer, E.   1977.   Chemistry of  Hazardous Materials.  Englewood
       Cliffs, NJ: Prentice-Hall, Inc.

       NIOSH. 1984. Occupational  Safety  and  Health  Guidance Manual for
       Superfund  Activities.

       Roos,  K.;  Scofield,  P.  1983.   Health and Safety Considerations:
       Superfund  Hazardous  Waste Sites.  In:  Proc. National  Conference on
       Management of Uncontrolled Hazardous Waste Sites.  Washington, DC.
       October 31 -  November 2.

       U.S. Army  Corps  of  Engineers.   1982.  Safety and Health Requirements
       Manual.  Washington,  DC.: USACOE.  EM-385-1-1.


                                     5-2

-------
                                                           OSWER Directive 93800-3
       U.S. Environmental Protection Agency.  1979.  Safety Manual for
       Hazardous Waste Site Investigations (draft).  Denver: Office of
       Occupational Health and Safety, and the National Enforcement
       Investigation Center.

       See U.S. Environmental  Protection Agency (1984) under Section 2.2
       and (1985a) under Foreword

       Wallace, L.; Martin, W.  1983.  Hazardous Wastes Worker Health and
       Safety Guidelines.  In: Proc. National Conference on Management of
       Uncontrolled Hazardous Waste Sites.  Washington, DC.   October 31 -
       November 2.

2.2.3  PREPARE COMMUNITY RELATIONS PLAN

       U.S. Environmental Protection Agency, OERR.  1983.  Community
       Relations in Superfund:  A Handbook (interim version).  Washington,
       DC: U.S. Environmental  Protection Agency.  September.

2.2.4  IDENTIFY POTENTIAL REMEDIAL TECHNOLOGIES

       Neely, N.; et al.  1981.  Survey of On-Going and Completed Remedial
       Action Projects.  Cincinnati: EPA 600/2-81-246.  September.

       Wagner, K.; et al.  undated.  Planning and Implementation of
       Response Actions for Hazardous Waste Sites With Drums (draft final).
       Cincinnati: U.S. Environmental Protection Agency, MERL, ORD.
       Contract No. 68-03-3113.

2.3  PERFORM INITIAL SITE CHARACTERIZATION

2.3.3  CONDUCT PRELIMINARY EXPOSURE ASSESSMENT

       Heer, J.; Hagerty, D.  1977.  Environmental Assessment and State-
       ment.  Van Nostrand Press.

       See U.S. Environmental  Protection Agency (1985a) under Foreword.

2.3.5  DEFINE DATA NEEDED TO CONDUCT LIMITED FEASIBILITY STUDY

       See U.S. Environmental  Protection Agency (1985a) under Foreword.

2.4  CONDUCT DETAILED FIELD INVESTIGATION

2.4.1  PREPARE PROJECT OPERATIONS PLANS

       de Vera, E.R.; Simmons, B.P.; Stephens, R.D. and Storm, D.L. 1980.
       Samples and Sampling Procedures for Hazardous Waste Streams.
       Cincinnati:  EPA-600/2-80-018.  January.

       McNeil, D.  1979.  Barrels of Chemicals Rot as Disposal Fails.  New
       York Times.  July 5.
                                     5-3

-------
 OSWER Directive 9380.0-3

       Tewhey, J., Sevee, J.; and Fortin, R.  1982.  Silresim:  A Hazardous
       Waste Case Study.  In: Management of Uncontrolled Hazardous Waste
       Sites National Symposium.  Washington, DC: EPA et al.  November 29 -
       December 1.

       U.S. Environmental Protection Agency, ORD.  1983.  Interim
       Guidelines and Specifications for Preparing Quality Assurance
       Project Plans.  EPA-600/1-83-004.  NTIS PB83-170514.  February.

       See U.S. Environmental Protection Agency (1985a) under Foreword and
       (1984) in Section 2.2., and Wagner et al. (undated) under Section
       2.2.4.

2.4.2  PERFORM TANK AND DRUM SURVEY/INVENTORY

       Ember, L.R.  1979.  Needed:  Hazardous Waste Disposal  (But Not in My
       Backyard).  ES&T.

       Ritthaler, William E.  1982.  Callahan Uncontrolled Hazardous Waste
       Site:  During Extreme Cold Weather Conditions.  In: Management of
       Uncontrolled Hazardous Waste Sites National  Symposium.  EPA et al.
       Washington, DC.  November 29 - December 1.

       Wetzel, R.; Wagner, K.; and Tafuri, A.  1982.   Drum Handling
       Practices at Abandoned Sites.  In: Management  of Uncontrolled
       Hazardous Waste Sites National Symposium.  EPA et al.   Washington,
       DC.  November 29 - December 1.

       See also Wagner et al. (undated)  under Section 2.2.4.

2.4.3  CONDUCT SITE CHARACTERIZATION

       Barbara, M.; Morahan, T.; and Teets, R.  1983.  Site Security and
       Waste Removal  Activities at an Abandoned  Hazardous Waste Site.  In:
       Proc. National  Conference on Management of Uncontrolled Hazardous
       Waste Sites.  Washington, DC.  October 31 - November 2.

2.4.4  CONDUCT SAMPLING PROGRAM

       Dahn, C.J.   1980.  Chemical Compatibility and  Storage Considerations
       for Process Systems Hazards Analysis. J.  of Hazardous  Materials,
       4:121-127.

       Hina, C.;  Garlauskas, A.; and Carter, T.   1983.   Techniques for
       Identification  and Neutralization of Unknown Hazardous Materials.
       In: Proc.  National  Conference on  Management of Uncontrolled
       Hazardous  Waste Sites.  Washington, DC.  October 31 - November 2.

       King,  M.V.; Eller, P.M.;  and Costello, R.J.   1983.  A Qualitative
       Sampling Device for Use at Hazardous Waste Sites.  Proc. of The
       American Industrial  Hygiene Association and American Conference of
       Governmental  Industrial  Hygienists Hazardous Waste Sysmposium.
       Philadelphia.   May.
                                     5-4

-------
                                                           OSWER Directive 9380.0-3

       Lynn, J.P. and Rossow, H.E.  1970.  Classification of Chemical
       Reactivity Hazards.  Alexandria, VA: National Technical Information
       Center.

       Myers, L.C.  1980.  The Chemical Reactivity Test-A Compatibility
       Screening Test for Explosives.  J. of Hazardous Materials.  4:77-87.

       Simmons, B.P.; Tan, I.; Li, T.H.; Stephens, R.D.; and Strom, D.L.
       1982.  A Method For Determining the Reactivity of Hazardous Wastes
       (preliminary). Cincinnati, OH: U.S. Environmental Protection Agency.

       Turpin, R.D.  1982.  Oxidation/Reduction Potential Field Test Kit
       for Use at Hazardous Material Spills.  In: Proc. Hazardous Material
       Spills Conference.  April.

       Vecera, M. and Gasparic, J.  1971.  Detection and Identification of
       Organic Compounds. New York: Plenum Press

       Wolbach, C.D.  1983.  Protocol for Identification of Reactivities of
       Unknown Wastes.  In: Proc. National Conference on Management of
       Uncontrolled Hazardous Waste Sites.  Washington, DC.  October 31 -
       November 2.

       See Wagner et al. (undated) under Section 2.2.4.

3.0  LIMITED FEASIBILITY STUDY

3.1  IDENTIFY MAJOR REMEDIAL TECHNOLOGIES

       Chemical  Manufacturers Association.  1981.  Drum Consolidation
       Protocol.  Washington, DC: CMA.

       Freestone, F.J. and Brugger, J.E.  1980.  Incineration of  Hazardous
       Wastes at Uncontrolled Dumpsites.  In:  Proc.  National Conference on
       Management of Uncontrolled Hazardous Waste Sites.  Washington D.C.
       October.

       Ghassemi, M.; Yu, K.;  Quinlivan, S.; and Freestone, F.J.  1980.
       Comparative Evaluation of Processes For the Treatment of
       Concentrated Wastewaters at Uncontrolled Hazardous Waste Sites. In:
       Proc.  National  Conference on Management of Uncontrolled Hazardous
       Waste  Sites.  Washington D.C. October.

       Hatayama, H.K.; Chen,  J.J.; de Vera,E.R.; Stephens, R.D. and Storm,
       D.L.   1980a.  A Method for Determining  the Compatability of
       Hazardous Wastes.  Cincinnati, OH: EPA  600/2-80-076.  April.

       	.   1980b.  Hazardous Waste Compatibility.  In: Disposal of
       Hazardous Waste—Proceedings of the Sixth Annual Research  Symposium.
       Cincinnati,  OH:  EPA 600/9-80-010.
                                     5-5

-------
OSWER Directive 9380.0-3

       Houston, R.C.  1980.   Incineration of Hazardous Waste at Sea.  In:
       Proc. National  Conference on Management of Uncontrolled Hazardous
       Waste Sites. Washington, D.C. October.

       Thorsen, J.W. et al.   1983.  Classification Protocol  For Waste at
       Remedial Action Sites.  University of Wisconsin Municipal  and
       Industrial Waste Sixth Conference.  Madison, Wisconsin.
       September 14-15.

3.2  SCREEN INITIAL REMEDIAL TECHNOLOGIES

3.2.2  EVALUATE ENVIRONMENTAL AND PUBLIC HEALTH IMPACTS

       Vanderlaan, G.A.  1981.  A Fast Track Approach to Impact Assessment
       at Uncontrolled Hazardous Waste Sites. In: Proc. Second National
       Conference on Management of Uncontrolled Hazardous Waste Sites.
       October.

       See JRB Associates (1983) under Section 3.3.4.

3.2.3  EVALUATE COSTS

       Rishel, H.L.; Boston, T.M.; and Schmidt, C.J.  1984.   Cost of
       Remedial Response Actions at Uncontrolled Hazardous Waste Sites.
       Park Ridge, NJ: Noyes Data Corp.

       U.S. Environmental Protection Agency.  1984.  Compendium of Cost  of
       Remedial Technologies at Hazardous Waste Sites (draft).  Washington,
       D.C.: EPA Office of  Emergency and Remedial Response.   February.

       Vanderlann, G.A.  1983.  The Impact of Limited Competition on
       Removal Project Cost  Budgets.  In: Proc. National Conference on
       Management of Uncontrolled Hazardous Waste Sites.  Washington, DC.
       October 31 - November 2.

       Walsh, J.J.; Lippitt, J.M.; and Scott, M.  1983.  Costs of Remedial
       Actions at Uncontrolled Hazardous Waste Sites - Impacts of Worker
       Health and Safety Considerations.  In: Proc. National Conference on
       Management of Uncontrolled Hazardous Waste Sites.  Washington, DC.
       October 31 - November 2.

3.3  CONDUCT DETAILED ANALYSIS OF POTENTIAL REMEDIAL ACTION ALTERNATIVES

3.3.1  PERFORM TECHNICAL ANALYSIS

       Alberti, B.N. et al.   1982.  Peroxidase for Removal of Hazardous
       Aromatics from Industrial Wastewater. In:  Biological Detoxification
       of Hazardous Wastes.  Exner, J.H. ed. Ann Arbor, MI: Ann Arbor
       Sience.

       Anderson, C.E.   1972.  Potassium Permanganate Control of Certain
       Organic Residues in  Air and Wastewater.   In: Symposium, Progress  in
       Hazardous Chemical Handling and Disposal.   Institute of Advanced
       Sanitation Research  International.

                                     5-6

-------
                                                     OSWER Directive 9380.0-3
Andres, D.R.  1977.  Managing Hazardous Wastes:  Disposal  System
Swallows Cyanide.  Waste Age, 8(ll):65-66, 68. November.

Augustine, R.L.  1969.  Oxidation Techniques and Application in
Organic Synthesis. Vol. 1. New York: Marcel  Dekkar, Inc.

Barry, J.  1981.  The World's Largest Hazardous Waste Treatment
Plant:  Is it Safe for Louisiana?  Dangerous Properties of
Industrial Materials Report. (7)12 September-October.

Berkowitz, J.B.; Funkhouser, J.T.; Steven, J.I.; and DeRenzo,  D.
1978.  Unit Operations for Treatment of Hazardous Industrial Wastes.
Park Ridge, NJ: Noyes Data Corporation.

Bidleman, O.T.F. and Williams, R.R.  1978.  Toxaphene Degradation in
Estuarine Sediments.  J. Ag. Food Chem. 26:280-282.

Bureau of National Affairs, Inc.  1982.  Biotreatment of Ammonia.
Environment Reporter.  Washington, DC: BNA.

Bouwer, E.J.  1981.  Anaerobic Degradation of Halogenated  1 and 2
Carbon Organic Compounds.  Environ. Sci. Tech. 15:596-599.

Brunotts, V.A.; Emerson, L.R.; Rebis, E.N.;  and Doy, A.J.   1983.
Cost Effective Treatment of Priority Pollutant Compounds With
Granular Activated Carbon.  In: Proc. National Conference  on
Management of Uncontrolled Hazardous Waste Sites. Washington,  DC.
October 31 - November 2.

Christinsen, D.C. et al.  1980.  Enhanced Photo Degradation of
Persistent Halogenated Organic Materials. In: Proc. of the 34th
Industrial Waste Conference.  Purdue University.  Lafayette, IN

Cytox.  undated.  CTX Bioxtreatment System,  Technical Data Sheet.
Allentown, Pennsylvania, .

Deever, W.R. et al.  1978.  Composting Petroleum Refinery Sludges.
Port Arthur, TX: Texaco, Inc.

Dinapoli, J.J.  1982.  The Exhumation Program for the SCA
Wilsonville Site. In: Management of Uncontrolled Hazardous Waste
Sites National Symposium.  EPA et al.  Washington, DC.  November 29
- December 1.

Epstein, E. et al.  1980.  Enhanced Biodegradation of Oil  and
Hazardous Residues. In: Proc. of the Conference on Oil and  Hazardous
Material Spills.  Silver Spring, MD:  Information Transfer,  Inc.

Farb, D.G.  1978.  Upgrading Hazardous Waste  Disposal Sites:
Remedial Approach. Cincinnati, OH: SW-677,  U.S. Environmental
Protection Agency.
                              5-7

-------
OSWER Directive 9380 0-3

     FMC Corporation.  1979.  Industrial Waste Treatment with Hydrogen
     Peroxide.   Philadelphia: Industrial Chemicals  Group.

     Gomma, M.H. et al.  1971.  Kinetics of Chemical Oxidation of
     Dipyridylium Quarternary Salts.  Agri. and Food Chem. 19:302 March.

     Halbouty, M.T.  1979.  Salt Domes Gulf Region, United States and
     Mexico. Second Edition. Houston, Texas.

     Haller, H.D.  1978.  Degradation of Monosubstituted Benzoates and
     Phenols by  Wastewater.  J. WPCF 50:2771-2777.

     Hill, R.D.  et al.  1981.  Four Options for Hazardous Waste Disposal.
     Civil Engineering. 51(9):82-85 September.

     Hill, R.D.; Schomaker, N.B.; and Wilder, I.  1980.  U.S.
     Environmental Protection Agency Research Program:  Uncontrolled
     Hazardous Waste Sites. In: Proc. National Conference on Management
     of Uncontrolled Hazardous Waste Sites.  Washington, DC.  October.

     Hooper, M.W.; Geiselman, J.N.; and Nael, T.E.  1983.  Mined Cavities
     in Salt - A Land Disposal Alternative.  In: Proc. National
     Conference  on Management of Uncontrolled Hazardous Waste Sites.
     Washington, DC. October 31 - November 2.

     Hopper, R.  1979.  Beyond RCRA:  Awful  as it Sounds Feds Need More
     Hazardous Waste Authority.  Waste Age. 10(1):36-40 January.

     Huddleston, R.L. et al.  1982.  Evaluation of Subsurface Effects of
     Long-Term Land Farming.  In: Land Disposal of Hazardous Waste.
     Proc. of the 8th Annual Research Symposium. MERL, EPA 600/992-002.

     Huddlestion, R.L. et al.  1976.  The Disposal of Oily Waste by Land
     Farming.  Presented to the Management of Petroleum Refinery
     Wastewater  Forum.  Tulsa, OK.  January.

     J.J.  Keller & Associates, Inc.  1981a.  Hazardous Materials Guide -
     Shipping, Materials Guide and Transport.  Neenah, WI.

      	.  1981b.  Hazardous Waste Services Directory -
     Transporters, Disposal Sites, Laboratories and Consultants. Neenah,
     WI.

      	.  1981c.  Hazardous Waste Management Guide - Regulations,
     Compliance and Management Guidelines.  Neenah, WI.

     Kinacannon, C.  1972.  Oily Waste Disposal by Soil Cultivation
     Process.  Washington, DC: EPA R-2-72-110.

     Krupa, M.J. et al.   1980.  Biological Methods for Detoxification of
     Hazardous Organic Materials.  National  Conf. on Hazardous and Toxic
     Waste Management.  Newark, NJ: New Jersey Institute of Technology.
     June  1980.
                                   5-8

-------
                                                      OSWER Directive 9380.0-3

 Lubowitz,  H.R.  and  Telles,  R.W.   1981.   Securing  Containerized
 Hazardous  Wastes with  Polyethylene  Resin  and  Fiberglass
 Encapsulates.   EPA  600/2-81-138.  July.

 Lubowitz,  H.R.  et al.   1981.   Securing Containerized  Hazardous Waste
 with Welded  Polyethylene  Encapsulates.   EPA-600/2-81-139.  July.

 Malone,  P.G.;  Larson,  R.J.; and Meyers,  I.E.   1980. Stabilization/-
 Solidification  of Waste From Uncontrolled  Disposal Sites.  In: Proc.
 National Conference on Management of  Uncontrolled  Hazardous Waste
 Sites.   Washington, DC.  October.

 McDowell,  C.S.  et al.   1980.   Biological Methods  for  In Situ Cleanup
 of Oil Spill Residues. Presented at  Coastal  and  Offshore  Oil
 Pollution  Conferences. The French/American Experience.  New
 Orleans, LA.   September.

 Morrison,  A.   1981. Can  Clay  Liners  Prevent  Migration of  Toxic
 Leachate?  Civil Engineering  ASCE 51(7):60 July.

 Mullins, D.E.  et al.   1981.   Preliminary Studies  Evaluating
 Composting as  a Means  of  Pesticide  Disposal.   Hazardous Waste
 Proceedings  of the  7th Annual  Research Symposium.  Inland  Disposal.
 Philadelphia.

 Munemon, M.  et al.   1980.   Simultaneous Removal of Hazardous Metals
 from Wastewater and Disposal  of Resultant  Sludge.  Toxic and
 Hazardous  Waste Disposal. 3:97-105.

 Murry, D.E.  and Reitz,  H.M.   1978.  Development of a  Hazardous Waste
 Disposal Facility.   Presented  at Applied Research and Practice on
 Municipal  and  Industrial  Waste First  Conference.  Madison, WI.
 September  10-13.

 Neely, N.S.  et al.   1981.   Remedial Actions at Uncontrolled
 Hazardous  Waste Sites.  In:  Land Disposal  of  Hazardous Waste.
 Proceedings  of the  Seventh  Annual Research Symposium.  Philadelphia.
March 16-18.

 Rose, W.W. et al.   1968.  Fate of Pesticides  in a Composted
Agricultural Waste.  Washington, DC:  National  Canners Association.

Sanders, D.  1979.  Deep  Well  Disposal of  Hazardous and Toxic
Wastes, Tulsa City-County Health Department.   In: Proc. National
Conference on Hazardous Materials Risk Assessment, Disposal and
Management. Miami Beach,  FL.

SCS Engineers.  1979.   Selected Biodegradation Techniques  for
Treatment  and/or Ultimate Disposal  of Organic  Material.  Cincinnati,
OH: EPA 600/2-79-006.
                              5-9

-------
OSWER Directive 9380 0-3

     Sikora,  L.J.  et  al.   1982.   Degradation  of Pentachlorophenol  and
     Pentachloronitrobenzene  in  a Laboratory  Composting  System.   Land
     Disposal  of  Hazardous  Waste.  Proc.  of the 8th  Annual  Research
     Symposium. MERL,  EPA  600/9-82-002.

     Sills, M.A.;  Struzziery,  J.J.;  and Silbermann,  P.T.   1980.
     Evaluation of Remedial Treatment, Detoxification  and  Stabilization
     Alternatives.  Proc.  National  Conference on Management of
     Uncontrolled  Hazardous Waste Sites.   Washington,  DC.   October.

     Sn'vastava,  V.K.  and  Haji-Djafari, S.  1983.   In-Situ
     Detoxicifcation  of  Hazardous Wastes.   In:  Proc.  National Conference
     on Management of  Uncontrolled  Hazardous  Waste  Sites.   Washington,
     DC. October  31 -  November 2.

     Tolman,  A.   1978.   Guidance Manual for Minimizing Pollution  from
     Waste  Disposal  Sites.  Cincinnati, OH: EPA 600/2-78-142.

     Tracy, K.D.  et al.  1979.   Mutant Bacteria Aids  Exxon  Waste  Systems.
     Hydrocarbon  Processing.

     Troop, W.M.   1977.  Alternative Methods  of Phenol Wastewater
     Control.  J.  Haz. Mat. 1:319-329.

     TRW Systems  Group.  1973.   Recommended Methods  of Reduction,  Neut-
     ralization,  Recovery  or  Disposal  of  Hazardous  Waste.  Volume  3.  PB
     224-582.  August.

     U.S.  Environmental  Protection  Agency.  1982.   Handbook for Remedial
     Actions  at Waste  Disposal Sites.  Washington,  DC: EPA 625/6-82-006.
     June.

     	1983.  Assessment  of Current  Status  of  Using Mined
     Space  for Long-Term Retention  of Nonradioactive Hazardous Waste.
     Cincinnati,  OH:  RFP CI 83-0094.

     Wassmann, T.H.  1983.  Cavity  Utilization  in  the  Netherlands.
     Hengelo,  The  Netherlands.

     Whinney,  W.N.  1980.   Evaluation of  Alternatives  for  Disposal of
     Heavy  Metal  Solution  Containing Nitrate.  Proc.  of  U.C.C.-ND and GAT
     Waste  Management  Seminar  (Union Carbide  Corporation  and Good Year
     Corporation).  Published  by Oak Ridge National  Laboratory,
     Tennessee.

     Zitrides, T.G.  1978.  Mutant  Bacteria for Disposal  of Hazardous
     Organic  Wastewater.   Pesticide Disposal  Research and Development
     Symposium. U.S.  Environmental  Protection Agency.  Reston,  VA.
     September.

     	.   1981.   Method Converts  Organic Wastes to an Inert
     Powder.   Chem. Engr.  88(21):99,101.
                                   5-10

-------
                                                          OSWER Directive 9380.0-3
       	.   1981.  Alternatives to the Land Disposal  of Hazardous
       Wastes. Governor's Office of Appropriate Technology.   California.

       	.   1981.  Hazardous Waste Market-Handling, Storage &
       Disposal. New York: Frost & Sullivan, Inc.

                   1982.  Mutant Bacteria in Cleaning Up of  a California
       Formaldehyde Spill.  Chem. Eng.  89(18).

       	.  1983.  Management of Hazardous Industrial  Wastes:
       Research and Development Needs.  (NMAB-398).  National  Materials
       Advisory Board, Commission on Engineering and Technical  Systems,
       National Research Council Washington, DC.

       See Wagner et al. (undated) under Section 2.2.4.

3.3.2  PERFORM COST ANALYSIS OF ALTERNATIVES

       Environmental Law Institute.  1983.  Remedial Action Cost
       Compendium. July.

       Environmental Law Institute/JRB Associates.  1983.   Survey and Case
       Studies of Remedial Actions at Hazardous Waste Sites (final  draft).
       Prepared for: U.S. Environmental Protection Agency  Office of
       Research and Development.  April.

       ORB Associates.  1983.  Remedial Action Costing Procedures Manual.
       McLean, VA: JRB Associates.  August 26.

       McGraw-Hill Information Systems Company.  1983.  Dodge Guide.   New
       York:  McGraw-Hill.

       Robert Snow Means Company, Inc.  1983.  Building  Construction  Cost
       Data 1983.  Kingston, MA.

       SCS Engineers.  1981.  Costs of Remedial Response Actions at
       Uncontrolled Hazardous Waste Sites.  Prepared for:  U.S.  Environ-
       mental Protection Agency Office of Research and Development.  April.

       U.S. Environmental Protection Agency.  1981.  Remedial  Actions at
       Hazardous Waste Sites:  Survey and Case Studies.   Washington,  DC:
       EPA 430/9-81-05 SW-910, Oil and Special Materials Control Division.
       January.

       U.S. Office of Managment and Budget.  Circular No.  A-94.  Revised
       3/27/82.

       Werner, J.D.; Yang, E.J.; and Nagle, E.  Remedial Action Management
       and Cost Analysis.  In: Proc. National Conference on Management of
       Uncontrolled Hazardous Waste Sites.  Washington,  DC.

       See U.S. Environmental Protection Agency (1982) under Section  4.2.3
       and JRB Associates (1983) under Section 3.3.4.
                                     5-11

-------
 OSWER Directive 9380.0-3


3.3.3  PERFORM ENVIRONMENTAL AND PUBLIC HEALTH ANALYSIS

       TetraTech, Inc.  undated.  Water Quality Assessment:  A Screening
       Procedure for Toxic and Conventional  Pollutants, Volume I and II.

3.3.4  PERFORM REGULATORY AND INSTITUTIONAL ANALYSIS

       Anderson National  Standard Institute, Inc.  Safety Requirements for
       Working in Tanks and Other Confined Spaces.  New York: ANSI-Z117.1.

       NIOSH.  Criteria for Recommended Standard:  Working in Confined
       Spaces.  Washington, DC:  Publication No. 80-106.

       OSHA.   General  Duty Clause, Section 5 A-l of Occupation Safety and
       Health Act (Public Law 91-596). Washington, DC.

       Shea,  K.  1976.  Hot Spot in Oregon.  Environment.  18(10):6
       December.

       See U.S. Environmental Protection Agency (1985b) under Foreword

4.0  TANK AND DRUM SITE REMEDIAL DESIGN/REMEDIAL ACTION

       Camp Dresser &  McKee Inc.  1981a.  Draft Design Report for Surficial
       Cleanup and Disposal of Chemical Wastes at the Pollution Abatement
       Services Site - Oswego, N.Y. Boston:  COM.  November.

        	.  1981b.  Contract Documents & Specifications Surficial
       Cleanup and Disposal of Chemical Wastes P.A.S. Oswego, N.Y. Boston:
       COM.  November.

       Cooper, E.W.  1983.  Emergency Removal  Action at the Bankrupt
       Crystal Chemical  Plant, Houston, Texas.  In: Proc. National
       Conference on Management  of Uncontrolled Hazardous Waste Sites.
       Washington, DC.  October  31 - November 2.

       Moran, B.V. and Turner, J.R.  1983.  Lessons Learned by the Corps of
       Engineers on Two Superfund Remedial Projects.  In: Proc. National
       Conference on Management  of Uncontrolled Hazardous Waste Sites.
       Washington, DC. October 31 - November 2.

       Nadeau, P.F,; Dehn, W.T.; and Goldstien, P.  1983.  Status of
       REM/FIT EPA Contracts.  In: Proc. National Conference on Management
       of Uncontrolled Hazardous Waste Sites.   Washington, DC.  October 31
       - November 2.

       Paige, S.F. et  al.  1980.  Preliminary Design and Cost Estimates for
       Remedial  Actions  at Hazardous Waste Disposal Sites.  In: Proc.
       National  Conference on Management of Uncontrolled Hazardous Waste
       Sites.  Washington, DC. October.
                                     5-12

-------
                                                     OSWER Directive 9380.0-3
Pease, R.W. Jr.; Menke, J.L.; and Welks, K.E.  1980.  Management of
Abandoned Site Cleanups:  Wade Property, Chester, Pennsylvania.
Proc. National Conference on Management of Uncontrolled Hazardous
Wastes Sites.  Washington, DC.  October.

Robbins, J.C.  1983.  Minimizing Liability Exposure When Contracting
Hazardous Waste Services.  In: Proc. National Conference on
Management of Uncontrolled Hazardous Waste Sites.  Washington, DC.
October 31 - November 2.

U.S. Environmental Protection Agency.  1985.  Superfund Remedial
Design and Remedial Action Guidance.  Washington, DC: EPA Office of
Emergency and Remedial Response.  February.

 	. 1985.  State Participation in the Superfund Remedial
Program.Washington, DC: EPA.  Scheduled to be issued in September.
                              5-13

-------
                                           OSWER Directive 9380.0-3
              APPENDIX A

    EXAMPLE OF  A  SITE PERSONNEL
PROTECTION AND  SAFETY EVALUATION FORM
           FOR  USE DURING
         INITIAL SITE VISITS
                    A-l

-------
SITE PERSONNEL PROTECTION & SAFETY EVALUATION FORM
                                      EPA WA NO.	
              PAGE 1 OF «
REM II DOC. NO..
SITE
LOCATION

EPA REGION
EVALUATOR


RITE DESCRIPTION






SITE MAPS ATTACHED H


BACKGROUND ENVIRONMENT
AIR

SOIL

ADDITIONAI HA7ARHR ON-SITF


SURFACE WATER

GHOIIKinWATFH




   INFORMATIONAL SOURCES USED.
O
ts>
                                                                                               33
                                                                                               a
                                                                                               CO
                                                                                               CO
                                                                                               00
                                                                                               O
                                                                                               O

-------
         SITE PERSONNEL PROTECTION & SAFETY EVALUATION FORM
                             PAGE 2 OF 6
                                                                             REM II DOC. NO..
I
CO
            FIELD INVESTIGATION ACTIVITIES COVERED UNDER THIS SEF



            TASK NO     DESCRIPTION
POP DOCUMENT CONTROL NO._
                       PRELIMINARY
                       SCHEDULE
                                                                                                                    O
                                                                                                                    ID

                                                                                                                    O
                                                                                                                    ct
                                                                                                                    <£>
                                                                                                                    CJ
                                                                                                                    00
                                                                                                                    O
                                                                                                                    b

-------
SITE PERSONNEL PROTECTION & SAFETY EVALUATION FORM
PAGE 3 OF 6
                                                           REM II DOC. NO..
CONTAMINANTS OF CONCERN
GUIDELINE
SHEET I.DL H SOURCE/QUANTITY ROUTE OF SYMPTOMS OF
CONTAMINANT ATTACHED (PPM) CHARACTERISTICS EXPOSURE ACUTE EXPOSURE





































INSTRUMENT RESPONSE
FACTORS
P.I D1 F.I D.1 OTHER
















1 KJNIZATION POTENTIAL (*0
2 % AS CH,
                                                                                            O
                                                                                            en
                   m
                   3)
                                                                                            oo
                                                                                            p
                                                                                            o

                                                                                            OJ

-------
SITE PERSONNEL PROTECTION & SAFETY EVALUATION FORM
           PAGE 4	OF 6

REM II DOC. NO.	
SITE PERSONNEL SITE ACTIVITY
PERSONNEL
NAME S.S NO F








PERSONNEL PROTECTIVE EQUIPMENT VERIFY
( )
( )
( )
( )
( )
( )
( )


DECON


RW





















LEVEL OF
REGION PROTECTION CONTINGENCY VERIFY
( )
( )
( )
( )
( )
( )


FIELD MONITORING EQUIPMENT VEWFY
( )
( )
( )
( )
( )
( )
( )




                                                                                        (£>
                                                                                        CO
                                                                                        00
                                                                                        p
                                                                                        b

-------
            SITE PERSONNEL PROTECTION A SAFETY EVALUATION FORM
                                                                                               PAGE 5 OF 6
                                                                                         REM II DOC. NO..
I
cn
               CONTINGENCY CONTACTS
                    AGENCY
                                       • DENOTES REQUIRED INFORMATION
                                      CONTACT
                                                       PHONE NO
                                                                        AGENCY
• FIRE DEPARTMENT



  POLICE DEPARTMENT



  HEALTH DEPARTMENT

• POISON CONTROL

  CENTER

• STATE
  ENVIRONMENTAL AGENCY _



• EPA REGIONAL OFFICE  _



• EPAERT, ICOM

• STATE SPILL

 CONTRACTOR
                                                               	 STATE POLICE



                                                               	 FA.A.



                                                               	 CIVIL DEFENSE



                                                               	»ON SITE COORDINATOR


                                                                   2-1 Hft,
                                                                   OF
                                                                                          CONTACT
                                                                                                           PHONE NO.
                                                                                                                                    3

                                                                                                                                    D
                                                                                                                      CD
                                                                                                                      00
                                                                                                                      CO
                                                                                                                      p
                                                                                                                      b
MEDICAL EMERGENCY
NAME OF HOSPITAL ADDHFSS
NAUF OF CONTACT ADDRESS
MAP r>B nniiTF in HDSPITAI

PHONE NO
PHONE NO



TRAVEL TIME DISTANCE TO NAME OF 24 HH.
FROM SITE (M'NUTFS) HORPITAI (Mil FS) AMBUI ANHF RFRVICF




-------
SITE PERSONNEL PROTECTION A SAFETY EVALUATION  FORM
                                          PAGE 6 OF 6
                                                                                     REM II DOC. NO.
    SEF REVIEW     I have read, understood, and agreed with the information set forth in this Personnel Protection and Safely Evaluation Form (and
                    attachments) and discussed in Presile Visit Health and Safety briefing.
   S.H S.C. SIGNATURE
   COMMENTS:.
   SITE PERSONNEL
    H.S.M. APPROVAL
                                      DATE
                                      DATE
                                                                R H S.S. SIGNATURE
                                                                COMMENTS:.
SITE H & S BRIEFING


CONDUCTED AT	


BY	
                                                                BRIEFING TOPICS.
                                                                 REM II H & S INPUT BY
                                                                                                   DATE
                                                                                                   ON_
                                                                                                   DATE
                                                                                                                                     m
                                                                                                                                     33
                                                                    CD
                                                                    CO

                                                                    00
                                                                    p
                                                                    o
                                                                    CO

-------
                                                           OSWER Directive 9380.0-3


                                 APPENDIX B



           DRUM HANDLING, DRUM SAMPLING. SPECIAL WASTE HANDLING,

                         AND TANK SAMPLING PROTOCOL
Drum and Special Waste Handling Protocol

A   Personnel involved in handling and transporting drummed waste shall
    work in teams containing no fewer than two people.  Visual contact
    shall be  maintained between members of the working team at all  times.
    All team members shall be able to communicate between themselves and
    with the Safety Officer by two-way radio at all  times on the work site.

B   Preliminary Classification

    1.  Prior to physically handling a drum, the following preliminary
        classifications check list shall be completed:

        a.  Is the drum radioactive?

        b.  Does the drum exhibit leakage or deterioration, i.e., is it
            unsound?

        c.  Does the drum exhibit apparent internal  pressure?

        d.  Is the drum empty?

        e.  Does the drum contain markings which would indicate that the
            contents are potentially explosive?

    2.  The results of the preliminary classification checklist shall
        dictate which specific procedures specified below shall be
        followed.

C   Leaking or Deteriorated Drums

    1.  The contents of drums that exhibit leakage or apparent deteriora-
        tion such that movement will cause rupture (determined by the
        Safety Officer) shall immediately be transferred to a  repack drum.
        Equipment, including transfer pumps used in the repack operation,
        shall be of explosion proof construction.

    2.  Leaking drums containing sludges or semi-solids, drums that  are
        structurally sound but which are open and contain  liquid or  solid
        waste, and drums which are deteriorated but can be moved without
        rupture, shall be immediately placed in overpack containers.
                                     B-l

-------
 OSWER Directive 9380.0-3

 D    Bulged  Drums

     1.   Drums which potentially may be under  internal pressure,  as
         evidenced  by  bulging, shall be sampled  in place.   Extreme care
         shall be exercised when working with  and adjacent  to potentially
         pressurized drums.

     2.   Should movement of a pressurized drum be unavoidable, handling
         shall be by a  grappler unit constructed for explosive containment.
         The bulged drum shall be moved only as  far as necessary  to allow
         seating on firm ground or shall be carefully overpacked.

     3.   Openings into  pressurized drums shall be plugged and the bung holes
         fitted with pressure venting caps set at 5 psi release.

 E    Drums Containing  Explosive or Shock Sensitive Waste

     1.   Drums that contain wastes that have been identified by sampling, or
         are suspected  by visual examination to  be explosive in nature,
         shall be handled with extreme caution.  Initial handling shall be
         by  a grappler  unit constructed for explosive containment.  Drums
         shall be palletized prior to transport  to high hazard interim
         storage and disposal area.

     2.   If  at any time during remedial activities, an explosive, pursuant
         to  provisions  of Title 18, U.S. Code, Chapter 40 (Importation,
         Manufacture,  Distribution, and Storage  of Explosive Materials, 1975
         Explosives List) is identified, it should be secured and the
         appropriate state and federal agencies  notified.

     3.   Identification of an explosive substance during the course of a
         remedial action is usually based on the experience of the on-site
         personnel.  Potentially explosive materials usually may  be
         identified by their physical characteristics -- texture, color,
         density, etc., as well as the way they  are packaged or labeled.
         Most explosives are solids.  In some  cases they are packaged in
         water-tight containers to exclude water, while in  other  cases they
         are packaged wet to preclude explosion.

    4.   Prior to handling or transporting drums containing explosive
        wastes,  personnel  working in the area shall be removed to a safe
         distance.  Continuous contact with the  communication base shall be
        maintained until  handling or transporting operations are complete.
        An  audible siren signal system, similar to that employed in
         conventional  blasting operations, shall be used to signify the
        commencement and completion of explosive waste handling  or
        transporting activities.

F   Drums Containing Radioactive Waste

    1.  Drums containing radioactive wastes shall  not be handled until
        radiation levels have been determined by an initial field survey
        conducted by the contractor.  Survey  shall include direct gamma
        readings and laboratory analysis of drum surface wipe samples.


                                     B-2

-------
                                                           OSWER Directive 9380.0-3
    2.  Depending on the  level of radiation encountered, handling and
        transport may  require special  shielding devices to protect
        personnel.  Following handling and transport, equipment used shall
        be surveyed by the Safety Officer and decontaminated to background
        levels prior to recommencing work.  Surveys shall also be made of
        the ground surface in the vicinity of original drum storage to
        identify potential soil contamination by spilled or leaked
        radioactive waste.  Prior to recommencing work in the area,
        radioactive soil  areas shall be isolated to prevent tracking of
        radioactive contaminants about the site.

G   Packaged Laboratory Wastes (Lab Packs)

    1.  Drums known or suspected of containing discarded laboratory
        chemicals, reagents or other potentially dangerous materials in
        small volume,  or  individual containers shall be handled with
        extreme caution.  Until otherwise categorized, they shall  be
        considered explosive or shock  sensitive wastes.  Initial  handling
        shall be by a  grappler unit constructed for explosive containment.
        Drums shall be palletized and  overpacked if required prior to
        transport to the  Lab Pack staging for sorting, identification,
        repacking and/or  stabilization.

    2.  Prior to handling or transporting Lab Packs from the existing drum
        area, personnel working in the immediate area shall  be removed  to a
        safe distance.  Continuous contact with the communication  base
        shall be maintained until handling or transporting operations are
        complete.  An audible siren signal system,  similar to that employed
        in conventional blasting operations will be used to signify the
        commencement and  cessation of Lab Pack handling or transporting
        activities.

H   Air Reactive Wastes

    1.  If the presence of an air reactive substance is verified  or even
        suspected by a contractor, the material  should be immediately
        segregated and transported to a separate high hazard interim
        storage and disposal  area.

    2.  Air reactive wastes may be discovered during opening or sampling
        operations.  Air  reactive substances normally require special
        packaging.  They may  be stored under water or some other liquid to
        minimize air contact.  They may also be found in sealed ampules,
        corrugated drums,  stainless steel  canisters, or specially  lined
        drums.  Some chemicals, such as white phosphorus or barium oxide,
        react with oxygen  in  the air, while others, such as sodium, cesium
        or various metal  hybrids, react with the moisture or water vapor in
        the air.   Many of  these compounds are explosive when they  come in
        contact with air or water.
                                     B-3

-------
OSWER Directive 9380 0-3

I   Gas Cylinders

    1.  Gas  cylinders, when encountered, should be stored and disposed of
        on a specific case basis depending on the integrity of the
        cylinders and type of substance they are expected to contain.

J   Empty Drums

    1.  Empty drums containing less than 1 in. of solid residual  waste and
        those resulting from on-site bulking and repack operations shall be
        loaded by grappler into transport equipment and placed within the
        empty drum staging area.  Residuals, where possible, shall be
        transferred to repack containers prior to movement.  Additional
        information on the definition of empty drums can be found in
        40 CFR 26L7.  Also, limitations on the reuse of drums can be found
        in 49 CFR 173.28.

K   General  Drum Handling Procedures

    1.  The  handling, movement, and transport of drums should be by use of
        mechanical equipment only; no drums should be handled manually.

    2.  Remote drum handling equipment shall consist of a grappler equipped
        backhoe or front end loader.  Drum transportation should be with
        front end loaders or fork lifts with modified carrying platforms.

        Portions of equipment that contact drums or canisters should be
        constructed of non-ferrous metals or contact portions should be
        coated or lined to preclude spark generation.

        Handling and transport equipment should be equipped with full
        frontal and side splash and explosion shields.  Class ABC fire
        extinguishers shall be fitted to the body of each piece of
        equipment.

        Equipment should be maintained in first class condition.  The
        ignition manifold and exhaust components shall be maintained to
        prevent backfiring or generation of sparks within the exhaust
        gases.
                                     B-4

-------
                                                          OSWER Directive 9380.0-3

                           DRUM SAMPLING PROTOCOL


A  General Drum Sampling Protocol

The protocols for drum sampling performed at two NPL sites are presented in
Figures I to VII (at the end of the Appendix).  These protocols are a
systematic plan for the identification, segregation/isolation, consolida-
tion, and bulking of unspecified waste materials stored at an abandoned
hazardous waste site.  The analytical methods and references for the waste
testing are presented in Figure VII.  These methods are provided for
guidance only.  The protocol established herein is designed to provide
analytical data, compatibility and consolidation information consistent
with cost effective environmentally sensitive removal and disposal of
hazardous waste from the site.  The quality assurance for these activities
should be consistent with the procedures specified in "Enforcement
Consideration for Evaluation of Uncontrolled Hazardous Waste Disposal Sites
by Contractors" (U.S. EPA, National Enforcement Investigation Center, April
1980).

The following are the standard materials and equipment required for
sampling:

    1.  Personnel protection equipment

    2.  500 ml, wide-mouth amber glass bottle with teflon cap liner

    3.  A uniquely numbered sample identification label  affixed to sample
        container

    4.  Chain of custody data sheets

    5.  4-ft. x 3/4-in. ID glass sampling thief

    6.  Remotely operated, pneumatic ram or check key device

    7.  One gallon covered cans half-filled with absorbent (for off-site
        shipment only)


During the initial  reconnaissance and characterization, any customized
containers, suspicious looking drums, or drums labeled as containing
hazardous materials (explosives, etc.) should be clearly marked for special
handling.  Maximum care and caution shall be exercised when opening drums
containing materials of an unknown origin.  A drum should not be moved or
opened unless it has been ascertained beyond reasonable doubt that the drum
is structurally sound and an external gross gamma scan is negative.

Drums should be sampled in place.  All drums and mechanical equipment
should be grounded prior to the commencement of sampling.  If the bung can
be removed, sampling contained liquids shall be by a glass thief, which
shall them be broken and discarded within the barrel.  A barrel that has a
badly rusted bung,  or that cannot be sampled as above, shall be safely
                                     B-5

-------
 OSWER Directive 9380 0-J

 entered with a hydraulic penetrating device operated remotely-  All
 openings  shall be plugged except during sampling operation.

 B    Specific Sampling Procedure Using a Glass Thief

     1.  Remove cover from sample container.

     2.  Insert glass tubing almost to the bottom of the drum or until a
        solid  layer is encountered.  About 1 ft. of tubing should extend
        above the drum.

     3.  Allow the waste in the drum to reach its natural level in the tube.

     4.  Cap the top of the sampling tube with a tapered stopper, ensuring
        liquid does not come into contact with stopper.

     5.  Carefully remove the capped tube from the drum and insert the
        uncapped end in the sample container.  Do not spill liquid on the
        outside of the sample container.

     6.  Release the stopper and allow the glass thief to drain completely
        and fill the sample container.  Fill  the container to about 2/3 of
        capacity.

     7.  Remove tube from the sample container, break it into pieces and
        place the pieces in the drum.

     8.  Cap the sample container tightly and place prelabeled sample
        container in a carrier.

     9.  Replace the bung or place plastic over the drum.

     10. Transport sample to on-site laboratory for analysis.

 C    Sample preservation and packing procedures for drummed waste samples

     1.  No preservatives shall be used.

     2.  Place sample in a ziplock plastic bag.

     3.  Place each bagged container in a 1-gallon covered can containing
        absorbent packing material.  Place lid on can.

     4.  Mark the sample identification number on the outside of the can.

     5.  Arrange for the appropriate transportation mode consistent with the
        type of hazardous waste involved.

D   Considerations for Analytical  Program

At the certified laboratory, each of the waste phases from all tanks should
first be tested for compatibility.  Many wastes, when mixed with others,
can produce potentially adverse human health and environmental conditions
                                     B-6

-------
                                                           UbWhn Directive 9380.0-3

such as:  (1) heat generation,  (2) violent  reaction,  (3)  release  of  toxic
fumes and gases,  (4) release of toxic substances  in case  of  fire  or
explosion, (5) fire or explosion, and (6) generation  of flammable  or toxic
gases.

A summary list of potentially incompatible  waste  materials or  components
and the adverse consequences of mixing waste  in one group with waste in
another group is presented in Appendix C.   The mixing of  a Group A waste
with a Group B waste may have the consequences noted.

The results of the compatibility characterization should  be  used to  sort
bulk waste into compatibility categories for  ultimate disposal.  A
composite sample of each compatibility category will  then be analyzed for
all major chemical components.
                                     B-7

-------
OSWER Directive 9380.0-3

                           TANK SAMPLING PROTOCOL


A   Regulatory Requirements

    1.  Guidelines have been developed to ensure the safety of the opera-
        tions personnel which shall be consulted by the contractor.  These
        are as follows:

        a.  OSHA - "General Duty Clause", Section 5 A-l of the Occupational
            Safety and Health Act (Public Law 910596).

        b.  NIOSH - "Criteria for Recommended Standard; Working in Confined
            Spaces", Publication No. 80-106.

    2.  In addition, reference material  shall also be used, such as the
        Anderson National  Standard Institute, Inc. (1430 Broadway, New
        York, NY 10018) "Safety Requirements for Working in Tanks and Other
        Confined Spaces",  ANSI-Z117.1

B   Tank Structural Survey

The external  structural characteristics  of each tank and tanker shall be
observed and  uniquely recorded and potential sampling points shall be
evaluated for safety, accessibility and  sample quality.

C   Tank Entry Procedure

    1.  Prior to opening a tank for internal inspection, the tank entry
        team  shall:

        a. Review safety  procedures and emergency contingency plans with
           the Safety Officer.

        b. Ensure that tank is properly grounded.

        c. Remove all sources of ignition from the immediate area.

    2.  All members of the tank entry team shall be fitted with
        self-contained breathing apparatus.

    3.  Each  tank shall be mounted using appropriate means and the manway
        covers removed using non-sparking tools.

    4.  Obtain and record  the following information at each potential
        sampling location.

        a. Lower explosion limit (LEL)  reading directly above the sampling
           port and the tank head space.

        b. Organic vapor  concentration directly above the sampling  port
           and in the tank head space.
                                     B-8

-------
                                                           OSWER Directive 9380.0-3

        c.  Percent oxygen concentration directly above the sampling port
            and in the tank head space.

        d.  Physical characteristics of tank contents (liquid, sludge, or
            solid).

        e.  Distance from sampling port flange to the surface of tank
            contents.

        f.  Presence of toxic vapors.

        g.  Accumulation of pyrophoric deposits.

        h.  Ionizing radiation.

        i.  Additional potential physical hazards.

    5.  After the above information has been obtained, each opening shall
        be closed and secured.

D   Profiling of Contents

    1.  Personal protective equipment and respiratory protection shall  be
        determined by the Safety Officer based on information gained from
        the reconnaissance work specified above.  Minimum protection shall
        be Level C.

    2.  Material and equipment required for profiling and/or sampling are
        as follows:

        a.  Personal protection equipment as specified in Health & Safety
            Plan

        b.  OVA, Organic Vapor Analyzer, or equivalent

        c.  Explosimeter/Oxygen meter

        d.  Geiger counter

        e.  Flashlight (explosion proof)

        f.  Trowel-stainless steel

        g.  Weighted sampler

        h.  Gem scoop

        i.  Bottom sediment sampler

        j.  Aluminum foil

        k.  Glass thief

        1.  Log book


                                     B-9

-------
OSWER Directive 9380.0-3

      m.  Intrinsically safe high volume blower

      n.  Wide mouth amber glass (550 ml)  bottle with teflon cap liner

      o.  Sample identification  labels affixed to sample bottle

      p.  Chain-of-Custody forms

      q.  Metal  paint can (1 gallon)  half-filled with absorbent

      r.  Camera

  3.  Prior  to commencing any profiling, the tank head space shall  be
      cleared of any toxic or explosive vapor concentration  using a high
      volume blower.  No work shall  start  in any tank if the LEL exceeds
      10% (as methane).

  4.  The preliminary safety guidelines outlined above shall  be observed.

  5.  Profiling Procedure

      a.  Determine the depth of any  and all  liquid  solid interface using
          a  weighted probe line.

      b.  Determine the depth of any  bottom sludge layer using a weighted
          probe line.

      c.  Collect  liquid samples from 1 ft. below the surface, from mid
          depth of the liquid,  and from 1  ft. foot above any bottom
          sludge layer.  Samples shall  be  collected  a weighted bottle
          sampler  (ASTM Method  D270).

      d.  Visually compare the three  samples.  If no visual  phase
          difference is observed, perform  field test as required to
          verify that no phase  differences are present in the tank.
          Field tests selected  shall  be determined by the type of
          material  found in the  tank  (organic, aqueous) and  include:

               Specific Conductivity
               Specific Gravity
               Refractive Index
               PH
               Solubility (water,  methanol, methylene chloride)
               Viscosity

     e.   If  any sampling indicated a phase difference, a systematic,
          interactive sampling procedure shall be performed  by halving
          the  distance  between two discrepant sampling points until the
          depth  of  the  phase change can be determined.  This  phase
          difference shall  be verified  by  field tests specified in  d
          above.

     f.   Verify the profile information from at least one other access
          port when  possible.


                                  B-10

-------
                                                       OSWER Directive 9380.0-3

     g.   The  mutual  incompatibility  of  all  phases  shall  be  verified.

     h.   Determine the  volume  of wastes in  each  phase and the  volume  and
         depth  of  any sludge.

 Sampling Procedure

 1.   The  method utilized  to  sample the  tanks  shall  be based  on  the
     physical characteristics  of the material.   Liquid materials  shall
     be sampled with a  weighted  bottle  or  glass  thief; gels  and sludges
     shall  be sampled with a scoop or bottom  sediment sampler.

 2.   Liquids  shall  be sampled  as follows:

     a.   Determine the  depth to  any  and all liquid/solid interfaces
         using  a weighted probe  line or glass thief.

     b.   Determine the  depth of  the  bottom  sludge  layer using a weighted
         probe  line or  glass thief.

     c.   For  liquids with a  depth of greater than  5 ft.:

         1.  Collect samples from 1  ft.  below the  surface, from mid
            depth  of the liquid, and from  one-foot above any bottom
            sludge layer.   Using a  weighted bottle sampler  (ASTM Method
            D270).

         2.   If a  visual  examination of  sample indicates phase
            difference,  a systematic,  interactive sampling  procedure
            shall  be performed  by halving  the distance between two
            discrepant sampling points  until the  depth of the phase
            change can be determined.

     d.   For liquids with a  depth of 5  ft or less:

         1.  Collect liquid  samples  using a glass  thief inserted in the
            full  depth of the liquid.

         2.  Transfer the liquid sample  to  a glass sample bottle and
            dispose of thief  in tank.

         3.  A  maximum of three  composite samples  shall be obtained from
            each sampling port.

3.  Sludges shall be sampled using  a scoop of modified bottom  sediment
    sampler.   A maximum  of  three sludge samples from each sampling port
    shall be obtained at various depths within the tank.

4.  Between each sampling event, the samplers shall  be cleaned, rinsed,
    and dried  prior to use.

5.  Samples shall be placed in  500  ml wide mouth  amber bottles.   The
    bottles shall not be filled beyond  2/3 capacity.
                                 B-ll

-------
OSWER Directive 9380.0-3

   6.  Sample bottle openings shall  be  covered  with  aluminum foil  and
       capped with teflon  lined caps.

   7.  Sample identification information  and  locator information shall be
       recorded in a log book.  A descriptive narrative shall  accompany
       each sample obtained from the tanks.
                                    B-12

-------
Figure I     Waste segregation protocol.
                                        Bulking and Consolidation Protocol
                                                                                       OSWER Directive 9380.0-3
               (Solid)
                I
                                  External Scan for Radioactivity
                                               Positive
                                               Isolate
                                   Confirm Structural Integrity of Drum
                                             Damaged
                                             Leaking
                                                                               On Site Consolidation
                                                                                    if Available
                                                                         Overpack
Characterize Drum Contents
with Brass Probe Rod


     (Liquid)
     I
           Label and Inventory
              See Fig.
Label and Inventory
     See Fig.
                                                      B-13

-------
OSWER Directive 9380.0-3


Figure II.     Solid materials.
                                        Bulking and Consolidation Protocol
               Open Drum
                  I
          O
MScan for Radioactivity
Alpha, Beta, Gamma
                            Positive
                            Isolate
                 Confirm Solid
                           Negative
                           or Free Liquid
             (Unspecified Solid)
                   1
                       See Consolidation Protocol
                       for Compatibility Categories
                       (Appendix C)
                  T
                        Composite PCB Testing
                                                               Resegregate (Liquid) or
                                                                    See Fig.
                                                               See Fig. IV
                                         >50
                                                               ppm
         For SD and •  •• determine flashpoint (17) for ultimate disposal requirements for solid materials.
                   PCB
                                                     B-14

-------
Figure III.     Liquid materials.
                                                                                       OSWER Directive 9380.0-3
                                       Bulking and Consolidation Protocol
    I  Open
                                              Drum
                                            Scan for Radioactivity
                                            Alpha, Beta, Gamma
                                                         Positive
                                                         Isolate
                                                   N©Q3t i VG
                                            Test for Perioxides, Oxidizers
                                            and Strong Reducing Agents
                                                              >- Resegregate (Solid) or (Other)

                                                                        [See Fig. II^L|See Fiv. IV |
                                             Test for Water Reactivity,
                                             Solubility and Density
                                                    Water Reactive
                                                    Isolate
             (Water Insoluble)
              (Organic Liquid)
                    t
                              (Water Soluble)
<10% H20
1
(§) Test
1
                                                                     Test for Water Content
(7)Spot Test for Organic Halides |

  Negative Test (Positive Test
                                 (Aqueous)
                                    7
                               (§) Test for pH
      Density H20
                                                             <7.0
                                                                              >70
                                       Retest
                          <2% Halide
                                      >2% Halide
                     (Aqueous Acid)

                   pH >2.0  pH<2.0
 (Organic Liquid)
   Low Halogen
         See Consolidation Protocol
         for Compatibility Categories
         Specified - See Fig. V
(Organic Liquid)
 High Halogen
       I
       I
	J
         Composite PCB Testing
50 ppm
<2% Halide^ PQB
50 ppm
Halide/^ p^g
                                                                    (Unspecified Aqueous)
                                                                    Base/Neutral
                                                                             I Test for Sulfide
                                                                                                     Positive,
                                                                              Positive  I/. ,\_     I      /_•.
                                                                             	——In yRetestl	< S
                                                                             Negative1^ |    -'isolate^/
                                                                    |(j2JTest for Cyanide]
Positive-
                                                 Positive
                                                                                   Negative
                                                         [13)Retest|	12.0
                                                     B-15

-------
OSWER Directive 9380 0-3
Figure IV.    Other materials
                                         Bulking and Consolidation Protocol
     Miscellaneous
        Dispose
                                         Other Materials


Unknown
or Forbidden
Materials


Treat
Stabilize
Consolidate



Dispose

Repack

Dispose
4
                                                                                   Multi-Phase
Compatibility Testing
 Individual Phases*


Solid
See Fig. II



Liquid
See Fig. Ill
*lf phases are incompatible, they must be separated and repacked.
                                                      B-16

-------
                                                                                    OSWER Directive 9380.0-3
Figure V.    Consolidation protocol for compatibility categories specified

                                     Bulking and Consolidation Protocol
                                           Compatibility Testing of
                                          Individual Drum or Solid
                                                 Samples
                              Liquids
                                                        Incompatible
             10 Drum or 6000 Ib
               Composite*
<5ppmPCB
   Bulk on Site
   50 Drums or
   30,000 Ibs**
                                                     Solids
                                                                    10 Drum
                                                                    Composite
                                                                 -A Composite PCB
                                                                     Analysis
                                                                      < 5 ppm PCB
15)  Composite PCB Analysis
                     Reanalyze Individual Samples
                                                                                             From Fig. IV
Sludge
                                                                            > 5 ppm PCB
                                                                        Reanalyze Individual
                                                                            Samples
                                                                            < 50 ppm PCB  > 50 ppm PCB
        Chemical
        Characterization
  'Composite is based on the threshold value for determining PCB waste and field detection limits.
  'Quantities based on typical truck capacity; may vary at specific sites.
                                                    B-17

-------
OSWER Directive 9380.0-3

                                  FIGURE VI

                             DISPOSAL CATEGORIES
                       (In diamonds on Figures I to V)


     R               RADIOACTIVE MATERIAL (Solid or Liquid)

     OX             STRONG OXIDIZER

     RD             STRONG REDUCING AGENT

     WR             WATER REACTIVE MATERIAL

     A               AQUEOUS ACID pH <2.0

     B               AQUEOUS BASE pH >12.0

     PCB
     50-500         PCB CONTAMINATED LIQUID 50-500 PPM
     ppm

     PCB
     >500           PCB CONTAMINATED LIQUID >500 PPM
     ppm

     OH             ORGANIC LIQUID WITH HIGH (>2%) HALOGEN CONTENT

     OL             ORGANIC LIQUID WITH LOW (
-------
                                    FIGURE  VII

                                ANALYTICAL  METHODS
                          (In  circles  in  Figures  I  to V)
                                                           OSWER Directive 9380.0-3
DESIGNATION

    1

    2

    3


    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16


    17
              METHOD

RADIOACTIVITY, ALPHA, BETA, GAMMA

OXIDATION REDUCTION POTENTIAL  (ORP)

CONFIRMATION TEST FOR PERIOXIDES AND
OTHER OXIDIZING AGENTS

CONFIGURATION TEST FOR REDUCING AGENTS

TEST FOR WATER REACTIVITY AND  SOLUBILITY

TEST FOR WATER CONTENT

SPOT TEST FOR PRESENCE OF HALOGENS

TEST FOR HALOGEN CONTENT

pH ANALYSIS

SPOT TEST FOR SULFIDE

CONFIRMATION TEST FOR SULFIDE

SPOT TEST FORCYANIDE

CONFIRMATION TEST FOR CYANIDE

COMPATIBILITY PROCEDURE

COMPOSITE PCB ANALYSIS

CHEMICAL CHARACTERIZATION AS REQUIRED
FOR DISPOSAL

IGNITABILITY
    REFERENCE

*MUHWS (110)

MUHWS (112)

DCP (5.9)


*TBQIA (564)

DCP (5.1)

DCP (5.20

*SIOC (174)

DCP (5.6)

DCP (J5.3)

*LEAD ACTIVE PAPER

DCP (5.50)

*DCP (5.4)

*SM (412E)

DCP (5.8)

DCP (5.7)

Section 13573,
1.03B

SW-846 (1010, 1020)
*See Analytical Notes.
                                      B-19

-------
OSWER Directive 9380.0-3

                                   FIGURE VII

                               ANALYTICAL METHODS
                                  (Continued)
   DCP - Drum Consolidation Protocol, A Hazardous Waste Site Management
         Plan (Chemical Manufacturers Association, Washington, D.C., 1982)

 MUHWS - National Conference on Management of Uncontrolled Hazardous Waste
         Sites (U.S. EPA Hazardous Materials Control  Research Institute),
         October 1981

  SIOC - The Systematic Identification of Organic Compounds, Shriner et
         al., 5th Edition, Jon Wily & Sons, New York, NY, 1964

 TBQIA - Text Book Quantitative Inorganic Analysis, Kolthoff, I.M., 3rd
         Edition, McMillion Co.

    SM - Standard Methods for Examination of Water & Waste Water, 15th
         Edition, 1980

SW-846 - Test Methods for the Evaluation of Solid Waste Physical/Chemical
         SW-846, U.S. EPA, 1984.
                                   B-20

-------
                                 APPENDIX C               OSWER Directive 9380.0-3

                                EXAMPLE OF A
                     BULKING AND CONSOLIDATION PROTOCOL

Purpose

The concept of the bulking and consolidation protocol is to segregate
wastes based on water content, acidity, water solubility, and reactivity in
anticipation of ultimate disposal.

Technique

The protocol (a) assumes the waste contains complex mixtures of  solids  and
liquids of unknown source and concentration; (b) subdivides  the  liquids
into general disposal categories; (c) determines that wastes within a group
are compatible by actual compatibility testing; (d) provides that  each
compatibility group composite is tested for PCB to ensure that contaminated
material is disposed of properly; and (e) provides that compatible
materials are then bulked in batches for disposal  ("Disposal Units") -  for
liquids and solids, 50 drums or 30,000 Ibs, respectively.  All solid
material should be moved off-site in individual containers only.

Other points considered in this approach include the following:

     «  Radioactive waste shall be identified both at the initial  stage of
        site evaluation as well as during the sampling of individual con-
        tainers.
     •  Waste containing peroxides, and toxic gas-forming compounds
        (cyanide, sulfide) should be identified and segregated for special
        treatment.  Consolidation at a later date may be advisable but  only
        after performing the compatibility testing procedure as  outlined in
        the protocol.
     •  Tests for water solubility, reactivity and water content shall  be
        used to classify organic, aqueous-soluble organic and inorganic
        wastes.  (The organic/aqueous and aqueous wastes include
        emulsions).  Very often density is an indication of structure
        (i.e., if liquid is heavier than water, halogen is  probably
        present).
     •  Samples shall be tested for organic halogen content,  however, the
        test procedures done in the field only detect gross amounts; 1-2
        percent.  Samples shall be retested for PCBs before disposal, and
                                    C-l

-------
OSWER Directive 9380.0-3
         before  one  contaminates  larger  batches.   This  is why  lab  size  con-
         solidated mixtures  are tested prior  to  consolidation  to avoid
         contamination.

      •   Wastes  containing multiple  phases  shall  be treated  separately  and
         all  phases  analyzed.

      •   The  compatibility test shall be performed on-site by  mixing  small
         samples  (left over  from  analyses).   Visual observation for
         precipitation,  or phase  separation and  temperature  measurement  (to
         test  for chemical reactions) shall be made.

      •   All  of  these analytical  tests shall  be  performed on-site  using
         relatively  simple procedures and equipment.  Analysis for EP
         toxicity and PCBs shall  be  done by the  contractor.

      •   The  analytical  procedure for determining halogen content  shall
         determine gross halogen  content (>1%).  Tests  for PCBs shall be
         done  to determine ultimate  disposal  if  disposal is  in a non-PCB
         approved incinerator.  Tests shall be conducted on  the lab
         composites  prior to mixing  drum contents so one can isolate the
         contaminating container  and/or change the mixing sequence as
         required to avoid PCB contamination.


A  simplified  logic  diagram  for the  consolidation protocol is  presented in

Figure  1.


Chemical characterization in anticipation of ultimate  disposal, is designed

to test  composite samples taken  from individual drum sample aliquots.  No

bulking  or consolidation should  be  done until the result of the analyses of

the  "lab scale" composite are reviewed to preclude the inadvertent

contamination of a  consolidated  lot by a highly concentrated  component such
as PCB.  The  testing and analytical procedures to be used on  the

consolidated  materials  should be that required for transport  and  disposal

of material which will  vary dependent on the method of disposal.
Following chemical characterization, those wastes that for chemical or
physical reasons cannot be bulked should be consolidated in approved drums

pending disposal.  The Contractor should, as far as practical, use the full
volume of each drum.  Shipment from site of partially empty drums of solid
waste should be kept at a minimum.


Limitations


Not applicable

                                    C-2

-------
                                                                                      OSWER Directive 9380.0-3
Figure 1.    Simplified logic diagram waste consolidation protocol.
               Unspecified Waste
        Chemical/Physical Characteristics
                    I
      Determine Specific Disposal Categories
             Compatibility Testing
                Consolidation
                   Bulking
              Off-Site Disposal
                                                                         Isolation of Noncompatible Wastes
                                                                         for Special Handling of On-Site
                                                                         Treatment
R     Radioactive

OX   Strong Oxidizer

RD   Strong Reducing Agent

WR   Water Reactive Material

A     Aqueous Acid

B     Aqueous Base

CN   Cyanide Waste

S     Sulfide Waste
                                                      C-3

-------
OSWER Directive 9380.0-3
                  COMPATIBILITY OF HAZARDOUS WASTE GROUPS
Group 1-A

Acetylene sludge
Alkaline caustic liquids
Alkaline cleaner
Alkaline corrosive liquids
Alkaline corrosive battery fluid
Caustic wastewater
Lime sludge and other corrosive
  alkalies
Lime wastewater
Lime and water
Spent caustic
Group 1-B

Acid sludge
Acid and water
Battery acid
Chemcial cleaners
Electrolyte, acid
Etching acid liquid or solvent
Liquid cleaning compounds
Picking liquor and other
  corrosive acids
Spent acid
Spent mixed acid
Spent sulfuric acid
Potential consequences:  Heat generation, violent reaction.
Group 2-A
Group 2-B
Asbestos waste, and other toxic
  wastes
Beryl 1ium wastes
Unrinsed pesticide container
Uaste pesticides
Cleaning solvents
Data processing liquid
Obsolete explosives
Petroleum waste
Refinery waste
Retrograde explosives
Solvents
Waste oil and other flammable
  and explosive wastes
Potential consequences:  Release of toxic substances in case  of  fire  or
                         explosion.
                                    C-4

-------
                                                           OSWER Directive 9380.0-3
Group 3-A                                   Group 3-B

Aluminum                                    Any waste  in Group  1-A or  1-B
Beryllium
Calcium
Lithium
Magnesium
Potassium
Sodi urn
Zinc powder and other reactive
  metals and metal hydrides

Potential consequences:  Fire or explosion; generation of flammable
                         hydrogen gas.
Group 4-A

Alcohols
Water
Group 4-B

Any concentrated waste in
  Groups 1-A or 1-B
Calcium
Lithium
Metal hydrides
Potassium
Sodium
                                             S02,  C12.  SOC12,  PC13,  CH3,
                                               SiCU  and  other water
                                               reactive wastes
Potential consequences:   Fire,  explosion,  or  heat generation;  generation
                          of  flammable  or  toxic  gases.
                                     C-5

-------
OSWER Directive 9380.0-3
Group 5-A
Group 5-B
Alcohols
Aldehydes
Halogenated hydrocarbons
Nitrated hydrocarbons and other
  reactive organic compounds and
  solvents
Unsaturated hydrocarbons
Concentrated Group 1-A or 1-B
  wastes
Group 3-A wastes
Potential consequences:  Fire, explosion or violent reaction.
Group 6-A
Group 6-B
Spent cyanide and sulfide
  solutions
Group 1-B wastes
Potential  consequences:  Generation of toxic hydrogen cyanide
                         or hydrogen sulfide gas.
                                     C-6

-------
                                                           OSWER Directive 9380.0-3
Group 7-A

Chlorates and other  strong
  oxidizer
Chlorine
Chlorites
Chromic acid
Hypochlorites
Perchlorates
Permanganates
Peroxides
Group 7-B

Acetic acid and other organic
  acids
Concentrated mineral  acids
Group 2-B wastes
Group 3-A wastes
Group 5-A wastes and  other
  flammable and combustible
  wastes
Potential consequences:  Fire, explosion, or  violent reaction.
Source:  "Law, Regulations and Guidelines  for Handling of
            Hazardous Waste."
         California Department of Health,  February 1975.
                                    C-7

-------