United States       Region 6          Fp.
          Environmental Protection   1201 Elm Street        trA
          Agency         Dallas TX 75270        November 1983
          Water

4>EPA     Environmental          Fina|

          Impact Statement
          Martin Lake D Area
          Lignite Surface Mine
          Henderson,  Rusk County
          Texas

-------
This report is available to the public through the
National Technical Information Service, US Department
of Commerce, Springfield, Virginia 22161

-------
TO ALL INTERESTED INDIVIDUALS, GROUPS, AGENCIES AND OFFICIALS:


A Draft Environmental Impact Statement (EPA 906/9-83-003 document) was filed by
Region 6 on March II,  1983 regarding the proposed Martin Lake "D" Area lignite
mine.  This was subsequent to receiving comments  at the scoping meeting  and
comments from agencies on preliminary draft documents.   EPA has held a public
hearing,  received oral  and  written  comments  on  the project  and Draft  EIS,
performed additional evaluation and analysis,  and determined a course of proposed
action on the requested wastewater discharge permit.

We are submitting for your review this Final Environmental  Impact Statement (EIS)
on the Martin Lake "D" Area Lignite Surface Mine Project proposed near Henderson,
Texas by the Texas Utilities  Generating Company.

This Final EIS  includes: (I)  a revised summary; (2) EPA's  responses  to  comments
received on the Draft EIS and summary of other public coordination; (3) revisions
necessary to the Draft EIS to make a more accurate statement; and  (4) preferred
alternatives and EPA's proposed  action.  Unrevised portions of the Draft EIS  are
incorporated by reference.

Major concerns of EPA  regarding  the project  include the potential for  adverse
impacts on surface and ground water resources (especially on water  quality of  the
downstream domestic raw water supply), the loss of U.S. Department of Agriculture
designated prime farmland soils, significant change in vegetation with reduction in
wildlife habitat and species diversity, impacts to wetlands, and losses of archaeolog-
ical and historic resources.

Copies of the public hearing transcript and this Final EIS will be available for public
review at the four public information  depositories: Office of Gregg  County Judge,
Longview, Texas;  Office of Rusk County Judge,  Henderson,  Texas; Rusk County
Memorial Library, Henderson, Texas; and at EPA, Region 6.

Copies of the Final EIS are being distributed  to those who made comments on  the
Draft statement and to those who requested a copy.

Comments or inquiries on  the accuracy or conclusions  of this EIS should  be sent to
Clinton B. Spotts, Regional EIS Coordinator by  the date,   1 2 »PP
 incerely yours,
Dick Whittington, P.E.
Regional Administrator

-------
                  FINAL ENVIRONMENTAL IMPACT STATEMENT
           MARTIN LAKE "D" AREA LIGNITE SURFACE MINE PROJECT


RESPONSIBLE AGENCY: U.S. Environmental Protection Agency, Region 6

PROPOSED ACTION;  Issuance of new source National Pollutant Discharge Elimination
System (NPDES) permit to Texas Utilities Generating Company (TUGCO) for discharge
of wastewater from the Martin Lake "D" area lignite surface mine near Henderson, in
Rusk County, Texas.

COOPERATING  AGENCIES;  Texas Department of Water Resources, Texas Parks and
Wildlife Department, Texas Historical Commission, Texas State Department Highways
and Public Transportation, Texas Air Control Board, USDOI Fish and Wildlife Service,
USDOI Office of Surface Mining, U.S. Army Corps of Engineers, USDA Soil Conserva-
tion Service, Sabine River Authority.

CONTACT FOR COMMENTS/INFORMATION;

              Clinton B. Spotts, Regional EIS Coordinator
              U.S. Environmental Protection Agency
              1201 Elm Street, Dallas, Texas 75270
              (2 1 4) 767-27 1 6 or FTS 729-27 1 6

WRITTEN COMMENTS ON FINAL EIS DUE;    1 2 OEH 1983
ABSTRACT;  TUGCO would discharge wastewater from various sedimentation ponds to
be  located within  the mine  area.  Wastewater receiving streams would  include Dry
Creek,  Mill Creek, Todd  Branch, Boggy Branch,  Dogwood Creek, Boggy Creek, and
other unnamed tributaries. Some I02 million  tons mined  lignite would be  hauled  by
truck to a crusher at the mine site then transported by  rail to  Martin  Lake Steam
Electric Station for burning.  Earth would be disturbed by mining to depths varying to
ISO  feet  and by construction  of ponds, diversions,  haul  roads,  railroad,  and  three
transmission  lines.   Environmental changes  include loss of  existing topsoils, loss  of
native  vegetation  and wildlife  habitat,  removal  of  wetlands, reduction of species
diversity, water quality and stream flow changes, disruption to groundwater levels, loss
of water wells, groundwater quality degradation and land use changes. Mine/reclama-
tion plans have not been reviewed/authorized by Railroad Commission of Texas to date.
General mine and reclamation plans proposed incude random mix of spoil for revegeta-
tion primarily with bermuda grass and pine forest species.  Long-term impacts would
depend  on success of land  reclamation and  level of maintenance  for stability in
revegetation.  Air  and water  quality  control  measures  are proposed to reduce fugitive
dust, crusher emissions, stormwater  runoff, erosion and sedimentation. Identification
of  and  mitigation of impacts  to significant  archaeological  and  historic  sites  are
expected to be carried out according to the Memorandum of  Agreement stiupulated on
the proposed permit.  The project will generate additional taxes and  is  estimated to
provide 240 jobs, and have a payroll of  about  $4,000,000.00  annually. Area highways
will  be directly  affected.   Area  health,  educational, governmental,  housing,  and
commercial service needs will increase due to induced population increases.
    PONSIBLE OFFICIAL:
Dick Whittington, P.E.
Regional Administrator

-------
                        TABLE OF CONTENTS


                                                             Page

PARTI. SUMMARY OF DRAFT AND FINAL EIS                          l-l

A.  PURPOSE AND NEED                                           l-l
B.  ALTERNATIVES AND ENVIRONMENTAL CONSEQUENCES               I-1
C.  MAJOR ISSUES AND/OR CONCERNS                               1-3
D.  MAJOR CONCLUSIONS                                         1-4

PART II.  CONSULTATION AND COORDINATION                        ll-l

A.  ACTIVITIES PRIOR TO THE DEIS                                 ll-l
B.  PUBLICATION OF THE DEIS AND THE PUBLIC HEARING             11-10
C.  THE FEIS AND RECORD OF DECISION                            11-80

PART III. MODIFICATIONS AND CORRECTIONS TO THE DRAFT EIS          III-1

A   REVISIONS TO CHAPTER 5.0-DESCRIPTION AND
    EVALUATION OF ALTERNATIVES                                III-1

B.  REVISIONS TO CHAPTER 6.0-ENVIRONMENTAL
    CONSEQUENCES OF ALTERNATIVES                              111-3
C.  REVISIONS TO CHAPTER 9.0-BIBLIOGRAPHY                     111-19
D.  REVISIONS TO APPENDIX A-SECTION 404(b)( I) ANALYSIS            111-20
E.  REVISIONS TO APPENDIX B-MEMORANDUM OF AGREEMENT         111-20
F.  REVISIONS TO APPENDIX C-PRELIMINARY NPDES PERMIT           111-20

PART IV. PREFERRED ALTERNATIVES                               IV-1

A.  APPLICANT PREFERRED ALTERNATIVE                           IV-1
B.  MOST ENVIRONMENTALLY SOUND ALTERNATIVE                   IV-1
C.  EPA PROPOSED ACTION                                       IV-1

APPENDIX A-DRAFT NPDES PERMIT                                 A-1

APPENDIX B-ADDITIONAL INFORMATION                             B-l

-------
                           LIST OF TABLES


Table                                                            Page

TABLE I-1   ENVIRONMENTAL CONSEQUENCES                         '"6

TABLE 1-2   ACRES OF VEGETATION TYPE TO BE DISTURBED              "'9

TABLE III-1  VEGETATION COMMUNITIES AND LAND USE MARTIN LAKE
           "D" AREA PROJECT SITE                                 M|-21

TABLE 111-2  SUMMARY OF LIGNITE AND ASH CHARACTERISTICS          Hl-22
                           LIST OF FIGURES


Figure                                                           Page

FIG. l-l     PROJECT LOCATION MAP                                1-10

FIG. I-2A    MINING SEQUENCE MAP                                  l-l I

FIG. I-2B    MINING SEQUENCE MAP                                  1-12

FIG. Ill-1     LOADING STATION OPERATION                           111-23

FIG. 111-2    SURFACE WATER MONITORING SITES                      111-24

FIG. 111-3    PROJECTS CONSIDERED IN CUMULATIVE
           IMPACTS ANALYSIS                                    111-25

FIG. 111-4    PROJECT LOCATION AND NEARBY PROJECTS               111-26

-------
                       PART I.
SUMMARY OF DRAFT AND FINAL EIS

-------
PART 1.       SUMMARY OF DRAFT AND FINAL EIS

A.            PURPOSE AND NEED

This Environmental Impact Statement  (EIS) has been prepared to assess the impacts
from the Texas Utilities  Generating Company's proposed Martin Lake "D" Area  lignite
surface mine and facilities construction and operation, and to disclose these impacts to
the public and to decision makers.  EPA must consider public input on environmental
impacts before  making a decision on  the wastewater  discharge permit requested  by
TUGCO.  EPA preparation is  in accordance with the Clean Water Act and the National
Environmental Policy Act.                          >

The objective of TUGCO is  to surface mine  and transport about  102 million tons of
lignite to the 2250-MW three-unit Martin Lake Steam Electric Station (MLSES), to  be
burned as fuel.  An 11.5-mile railroad  and  11.5-mile power transmission line would  be
constructed and  utilized, connecting the mine and MLSES.

B.            ALTERNATIVES AND ENVIRONMENTAL CONSEQUENCES

EPA Permitting  Alternatives. Alternatives available to EPA are: to issue a wastewater
discharge permit for the project as proposed;  issue a permit for a project with certain
conditions  to minimize or  mitigate adverse  impacts; or,  to deny the  issuance of a
permit.

No Action  Alternative.  The "no  action" alternative, i.e., to not develop this project,
could be implemented by the permit applicant or as a result of an EPA decision to deny
a permit.

Applicant Preferred Alternative.   The total project covers about  25,350 acres which
includes 273 acres for a  railroad  corridor  and  114  acres for a transmission line.  The
extent of the lignite reserves within the 24,963 acre mine boundary covers about 16,600
acres.  About 102 million tons of  lignite would be removed from approximately  15,000
acres over  a 30-year period.  The general sequence of proposed mining is shown  in Fig.
1-2, which also shows  generalized mining blocks. The actual  areas to be mined occur
within the blocks shown but are smaller.

Recently (September  1983), a TUGCO electric  power  transmission line has been
proposed to  be  constructed  on the previously  proposed  SWEPCO transmission line
relocation corridor.  Therefore, two separate  138 kv lines  would be constructed  on one
corridor of  170-foot width (see Fig. I-2B).   This  TUGCO line and  the TUGCO line
extending from  the MLSES  into  the southeastern  part of the mine area would carry
power  for  mine facilities and  certain equipment.  Clearing of vegetation and land
leveling would occur on both transmission line corridors and the railroad corridor prior
to construction of those facilities  and before any mining occurs.

Prior to  mining, the  land would  be  cleared of all vegetation.  Surface-water control
facilities such  as  stream  diversions,  catchment  basins, overland flow-interceptor
channels  and sedimentation ponds would be constructed.   A 2,000-foot section  of Dry
Creek would be  diverted for two years  for mining of lignite under the present channel.
Such a diversion requires a variance from RRC surface mining regulations that require
avoidance of a  stream  by a specific buffer zone.  Overburden  removal would  be
performed primarily using electric draglines.   The overburden handling method offered
by TUGCO  for this NPDES permit is the mixed spoil alternative.  TUGCO  proposes to
                                       l-l

-------
reclaim and revegetate  with  mixed spoil.  Overburden removal is scheduled to begin
with one 75-cubic-yard dragline  in May 1985, a second dragline  in operaton by April
1987, and a third in 1994.  Overburden stripping pits would be 120 feet wide and vary
from  3,000  to  10,000  feet long.  Mining  depths would vary  to  150 feet.  Scrapers,
dozers, front-end  loaders, graders, etc.,  would  be  used in overburden  handling  and
lignite loading.

Trucks would haul the lignite  from the pits to the train loading station over  a network
of haul roads.  Once loaded into rail cars, the lignite would be transported to the  MLSES
by an electric train (Fig. I-1).  The train loading station would be located in conjunction
with other permanent mine  facilities  which include an  office,  shop and warehouse
building,  lignite  storage area,  service area,  sewage  treatment  plant,  wastewater
treatment pond, dragline erection site, and fuel storage facilities (Fig. Ill-1  of Final EIS
and Fig. 5-5, DEIS). The spoil  surface would be recontoured to  approximately  premining
conditions and prepared for revegetation with fertilizers and lime.  Final  reclamation
would  be  to a vegetation  cover of woodlands and managed pasture.  The  estimated
proportions are  10 to 50 percent woodlands and 50 to 90  percent pasture.  Generally,
reclamation of mined  lands is proposed by TUGCO  to  be at  a level to meet surface
mining regulations. The RRC regulations  require a topsoiling  procedure, or  a method
shown  to  meet  the surface mining regulations which require productivity  (yield) on
reclaimed land to be at a level "equal to" or "better than" productivity on  nearby
unmined land, or, according to technical standards.  "Equal  to" is generally defined as
90 percent of the existing productivity at a 90-percent confidence level (or 80 percent
on shrub lands) based on the same level of management (see Draft EIS, Sec.  6.2.3.4).

Air pollutant particulate control measures  proposed include vehicular speed control (on
roads), water spray (on roads and at the crusher), and enclosure at the conveyor and rail
car loading area. Gaseous  and particulate air emissions from  lignite  burning would be
minimized by measures taken  at  the power plant. Lignite burning process wastewaters
would  be treated  in  ponds  before  being discharged  to  Martin Lake  or injected
underground.

On-site sanitary waste control  is proposed  by package  sewage  treatment plant to
secondary treatment level with effluent discharge to Dry Creek (see Fig. Ill-1).  Mining
water pollution control is proposed by  collection and settling in  sedimentation ponds.
Polyelectrolyte would be utilized  for lignite fines removal; pH control would be by lime
addition.   Discharges  to streams  are  proposed  based on  new source  alkaline mine
drainage category standards for coal mining.

Environmental Consequences.  The major environmental consequences of the applicant's
proposed project and the no action alternatives are shown on  Table I-1.  Acreages of
various vegetation types to be  disturbed by mining and construction activities  are shown
in Table 1-2.

It should be noted  that  if  the no  action  alternative is implemented, impacts  to the
environment (including soils, vegetation, topography, and air  and  water quality)  will
have occurred from early construction of support facilities. The affected areas could
be recontoured,  topsoil replaced  and revegetated, but wildlife habitat would  require  a
long period for return to predisturbance status. See Appendix B for correspondence and
EPA requirements  regarding construction prior to completion of  the environmental
review.
                                        1-2

-------
C.            MAJOR ISSUES AND/OR CONCERNS

Socioeconomic Aspects.  A major beneficial economic impact will occur from the mine
project for:  the applicant, various  individuals who sell  or  lease  land  and who own
mineral rights or obtain jobs, businesses, and governmental entities.  A concern is that
persons within the affected area (who may choose not to  sell or lease lands for mining
or who have interests where lignite does not occur) should not be inconvenienced or lose
any service if this project proceeds.

Surface Water Quality. A major concern exists regarding  potential  adverse impacts on
the receiving waters used as a public raw water supply, as well as on the water uses for
propagation of fish and wildlife and for noncontact recreation.  A need for establishing
a complete baseline of existing water quality conditions was determined particularly as
some discrepancies  between data  exist and some parameters (mercury, pH, phenols,
ammonia, total dissolved solids,  total  suspended solids,  alkalinity and turbidity)  in
existing waters appear to exceed water quality standards  set  by Texas Department of
Water Resources, U.S. Public  Health Service  and EPA.  In addition, effects of the
project must  be assessed as  to whether  impacts on  stream  water quality  standards
occur. Degradation of surface water quality may  occur on the long  term, after release
of  reclaimed mined lands from  surface mining bonds,  if the  same  levels of  land
treatment and management utilized to obtain bond release  is not maintained.

Stream Diversion and Wetlands. Potential  for loss of water quality function of wetlands
upstream  to Lake Cherokee (public raw water  supply)  by mining activities  (including
transmission line relocation and haul road construction) is of concern.   Where mining
occurs using the mixed spoil alternative for overburden handling, increased potential for
increased acidity,  and  release of  metals is of  concern.   No  specific plans or
commitment for mining or construction procedures  are available to determine actual
short term  impacts, or  whether  fill from  discharge will be maintained to prevent
erosion.  There is no specific plan for restoration  of  wetland vegetation.  Site specific
data  on spoil is  needed to determine whether discharge  in these sensitive areas will
consist of  material  free from toxic  pollutants (in  other  than  trace quantities).
Approximately 10 percent of wetland acreage  in  the Area "D" project boundary would
be  directly affected—however,  if mining dewatering  caused reduced  base flow  in
surface water,  possible cumulative effects, including  desiccation, would occur on  a
larger acreage.

Mine Spoil  Reclamation.   Lack  of a  specific  plan regarding  spoil   handling and
reclamation exists.  TUGCO  has  elected  to submit an application for  mining to the
Railroad Commission of  Texas (state agency  delegated with responsibility  to permit
mines and enforce federal surface  mining  regulations)  later.  Therefore, review of the
justification  for the  use of  mixed  spoil,  which  is  in  variance  to surface mining
regulations,  has  not occurred  by RRC.   Justification  would include  site specific
greenhouse  studies and  field  studies; these are  not now available for  disclosure for
independent review. The proposed mixed spoil  alternative has the highest potential for
acid forming materials and leached metals to occur at the  surface initially and over the
long term. This would create hot  spots, and then, loss of vegetation, erosion, and the
potential for adverse water quality impacts from  sediment, pH and  leached metals. On
a relatively short-term basis, RRC  regulations require inspection and soil monitoring of
reclaimed land during a five-year bond period  to  identify  and  take  mitigative action  if
such  impacts  occur.  Major concern exists with  effects  over the  longer term where
measures necessary  to obtain bond release may not be maintained.  Additionally, some
5,232 acres of prime farmland soils will be lost.
                                         1-3

-------
EPA has requested TUGCO consider entering into a Cooperative Agreement with  the
Rusk County Soil and Water Conservation District. EPA believes that better reclama-
tion management programs can be developed when fully coordinated with the local  soil
and water  conservation  districts  based on  formal  agreement.    While  TUGCO  has
indicated an intent to enter into such an agreement, to date an instrument has not been
signed.  Therefore, EPA has reservations regarding plan development. The applicant's
general  revegetation plan, consisting of 10 to 50 percent reforestation and  50 to 90
percent primarily coastal bermuda pasture, results largely in departure from  native
vegetation  and wildlife habitat. A loss of large acreage of economically significantly
forestland is expected. However, it is noted that within the last year the applicant  has
increased reforestation acreage at Martin Lake "A", "B", & "C" areas to approximately
13 percent of the total area disturbed to date.

Groundwater.   Appropriate ground-water monitoring in downdip areas  as well  as in
reclaimed areas will be necessary to adequately determine mining effects.  The area of
influence on groundwater  under water table and artesian conditions, due  to mining, is
expected to be significantly larger than shown in the Draft EIS.  Monitoring should be
adequate to plan for modifications of surface mining activities, if necessary, to restore
recharge capacity, minimize disturbance to the hydrologic balance, and reduce degrada-
tion of water quality.  Piezometers should be installed  in the  mined/recontoured areas
to monitor recharge and water quality.  Pumping and observation well systems should be
installed so that any connections and effects between the aquifers above and below  the
lignite are determined and so that effects downdip in the upper Carrizo-Wilcox aquifer
can be accurately predicted.  Potential measures to rebuild the aquifer and restore  the
subsurface hydrology should be considered initially.

Pattern  of Land Ownership. Concern for a change in the pattern of  area land ownership
has been raised. Ownership of a large acreage by the utility company or the possibility
of sale,  of all  acreage  owned,  to  one person is a possibility and would result in
permanent relocation of numerous families. A decision to sell or lease mine area lands,
to the private  utility company, or to do neither, is a matter for present landowners. A
concern of EPA is that individuals make decisions based on the  lease stipulations they
may require, knowledge of state-of-the-art reclamation that can be carried out, what
the laws require of  surface mining operations,  how enforcement  is carried  out,  and
knowledge that environmental tradeoffs are necessary when an area  is surface mined.

Cultural Resources.  Known significant cultural resources exist in the project  area  and
other  significant sites are expected to be discovered.  Compliance by TUGCO with  the
Memorandum of Agreement on Cultural Resources between EPA, Texas State Historic
Preservation Officer and the Advisory Council on Historic Preservation, is necessary to
reduce impacts.

D.            MAJOR CONCLUSIONS

The permit  action alternatives evaluated by EPA included: (I) the issuance of a new
source NPDES permit as proposed by the applicant; (2) the issuance of an NPDES permit
with conditions; and (3) denial of an NPDES permit.

EPA has determined its preferred action to be issuance  of a new source NPDES permit
with limits  for acid mine drainage rather than for alkaline mine drainage as proposed by
the applicant,  and with additional conditions. The conditions include: (I) that TUGCO
provide  quarterly monitoring  and reporting of additional  water quality parameters;
(2) TUGCO  compliance with stipulations of the Memorandum of Agreement between
EPA, the Texas State Historic  Preservation Officer, and the national Advisory Council
                                       1-4

-------
on Historic Preservation for cultural  resources  protection; and (3) that there be  no
discharge of dredge and fill material  into any wetlands designated by the Corps  of
Engineers unless TUGCO obtains a Clean Water Act, Section 404 authorization from the
Corps of Engineers for each discharge, based on site specific plans.
                                         1-5

-------
                                               TABLE I-1
                                   ENVIRONMENTAL CONSEQUENCES
        Factor
         Project Alternatives
        No Action Alternative
Geology and
Topography
Soils
Ground Water
Surface Water
Wetlands and
Flood Plains
Irreversible  loss  of bedded  geologic
strata;   minimal   long-term  adverse
impacts   to  topography;  short-term
adverse impacts to oil and gas produc-
tion; irreversible loss of clay and gravel
deposits; 85 percent recovery of lignite
deposits;   no  significant  cumulative
effects.

See Table 6-1; erosion potential would
be   moderate,   overburden   handling
alternatives all have good potential for
success under high-level  management;
alternative  I  has  highest potential for
acid-forming  material and  release  of
heavy  metals at the surface;  cumula-
tive impact  of  removing about 5,000
acres  of prime farmland  soils  from
potential production.

More than  142 wells would likely be lost
or  affected  by  mining;  dewatering
would cause long-term adverse impacts
to   shallow   ground-water   system;
recharge  and  restoration  of  system
would  likely  require more  than  23
years;   dewatering  by   pumping  and
mining would lower water levels under
artesian  conditions  northwest  of the
mine  area;  springs and  seeps  may  be
irretrievably lost but others may form
over the long term;  unknown  level of
degradation  to   ground-water   quality
from  increased  acidity  and  dissolved
solids;   unknown  level  of  cumulative
effects.

Preliminary  assessment   is   that  peak
flows  would  be   decreased  slightly;
runoff   volume  not  significantly af-
fected; no  significant reduction in firm
yield of Lake Cherokee.

Dewatering would decrease  baseflow in
streams; could dry-up upper sections of
tributaries  but should not significantly
affect  Mill  or Tiawichi  creeks; poten-
tial for  long- and short-term  adverse
impacts, mainly from suspended solids
(sediment), to water quality  of  streams;
monitoring   necessary   to   determine
level  of   adverse   impacts to  Lake
Cherokee and streams, as well as any
cumulative effects.

About 84 acres (10 percent)  of wetlands
would be adversely affected by mining;
wetlands or  riparian vegetation  could
be adversely affected in  specific  areas
by dewatering effects on seeps, springs
and upper sections of tributaries; minor
adverse cumulative impacts to water
quality  and important wildlife  habitat
by reduction of wetland acreage.
No adverse impacts to geologic structure
or topography.
Minor  continued erosion  from  present
levels of agriculture.
None.
None.
Continued  increase  in  acreage of bot-
tomland forests despite clearing associ-
ated with  mineral production,  agricul-
ture and timber production;  minor ad-
verse cumulative  impacts by reduction
of wetland acreage.

-------
                                             TABLE I-1 (Cont'd)
        Factor
         Project Alternatives
        No Action Alternative
Terrestrial Biology
Aquatic Biology
Threatened or
Endangered Species

Archaeological and
Historical Resources
Air and
Sound Quality
Land Use and
Recreation
Population
Economy
Long-term adverse impacts  related to
removal   of  upland   and  bottomland
forest acreage with concomitant reduc-
tion of wildlife habitat;  adverse cumu-
lative impacts associated with removal
of wildlife habitat.

Minor short-term adverse impacts  asso-
ciated with  construction  and operation
activities.

None.
Adverse effect has been determined on
Walling Cabin but  minimized by reloca-
tion  to  Henderson;  determination of
effect on known sites and sites yet to
be  discovered  would  be  conducted at
appropriate time; direct and/or indirect
impacts  on  sites  are  adverse to the
resource; mitigation measures would be
beneficial   to   state  of  knowledge;
adverse  impacts would be  minimized
and  beneficial impacts maximized by
compliance with the  Memorandum of
Agreement   which  requires   identifi-
cation  and  mitigation   of   cultural
resources sites.

Minor adverse impacts to air quality
from fugitive emissions and  to sound
quality from construction  and opera-
tional activities.   Long-term adverse
secondary  impacts  would result  from
operation of the MLSES.

Long-term  impacts  would result  from
the reduction in the amount of forested
land on the site and an increase in the
amount of  managed pasture.   Minor,
short-term  adverse  impacts  to  hunting
since  TUGCO  restricts access to its
land  and  long-term  impacts  from re-
duced forested land.

Short-term  increases  due  to  construc-
tion and long-term due to operation of
the  mine.    Additional increases  from
secondary work force.  Average age of
in-migrating population would  be less
than  existing population.  No adverse
impacts to area schools.

Both short-term and long-term benefi-
cial  impacts would result directly from
the project  (wages, land purchases, roy-
alties and capital expenditures); secon-
dary  beneficial impacts also would re-
sult  from stimulation to the local econ-
omy.
Continued adverse impacts from clearing
upland forests and reducing wildlife ha-
bitat; minor cumulative adverse impacts
by reduction of upland forest acreage.
None.
None.
Minor  adverse  impacts caused  by  local
collectors, agricultural or other activi-
ties, and further natural weathering.
No  action alternative  would not avoid
long-term  adverse  secondary  impacts
from continued operation of the MLSES.
Long-term decreases in agriculture  land
and upland forest with increases in  pas-
ture  and residential properties;  minor
adverse impacts to  hunting with reduced
game habitat (upland forest).
Long-term  minor  increases  following
past growth patterns.
Past economic patterns would continue.
                                                     1-7

-------
                                           TABLE I-1 (Concluded)
        Factor
        Project Alternatives
       No Action Alternative
Housing
Community
Services
Transportation
Community Finances
Minor adverse impact on availability of    None.
housing from  increased needs of work
force;   long-term  beneficial  impacts
could occur to housing construction in-
dustry.

Short-term adverse impacts could occur    None.
from stress  on  water treatment  and
storage capacity and sewage treatment
facilities  in  some communities  but
would  be minor since increased need
would occur over a several year period;
long-term  impacts  would  be avoided
because  of increased services in re-
sponse  to  needs;  long-term adverse
cumulative  impacts  could   result   in
combination  with  several  other pro-
posed projects.
Significant increase in deterioration of
area  roads due  to  heavy-load  truck
hauling;  no  significant  short-term or
long-term  adverse  impacts to  trans-
portation systems would result because
of  minor  traffic   increases  due  to
workers    and   induced    population
increase.
Short-term  and  long-term  beneficial     None.
impacts to municipal, county and state
finances associated with tax revenues;
long-term  beneficial  cumulative  im-
pacts  in  combination with  other  pro-
posed projects.
Road  deterioration
present rate.
would  occur  at

-------
                                                 TABLE 1-2
                             ACRES OF VEGETATION TYPE TO BE DISTURBED



Activity
Within Mine Boundary
o
General Construction
Dry Creek Diversion
Mining
4
Mine Facilities Construction
Between Mine and MLSES
Railroad Line
Transmission Line
Bottomland
Hydric
1
Wetlands

21
21
42
0

0
0
Hardwood Forest/
Communities

Nonwetlands

+ 14.4
0.2
7
0

II. 0
13.0



Pastureland

+75.9
6.1
about 9,500
126

142
71.7
Upland Pir
Hardwood <
Regenerat
Forest

+82.6
3.7
about 4,000
55

120
13.7
 Wetlands as defined by U.S. Corps of Engineers within the area of jurisdiction under Section 404 of the Clean
 Water Act.
o
 General construction includes haul roads,  utility  line relocations, and proposed  TUGCO 138 kv  transmission
 line. Acreage figures for most vegetation types cannot be absolutely determined at this time and are indicated
 by, +X acres.
o
 Mining would disturb about  16,000 acres during the life of the project.  The acreage of  bottomland nonwetlands
 would be very small since little mining would occur in flood  plains.  The  acreage  disturbed would  be primarily
 pastureland and upland/regenerative  forest.  The acreages listed  are  based  upon  acreages within mine  blocks
 (17,916 acres) minus almost 2,000 acres not to be disturbed.

 Mine  facilities would occupy about  140  acres  but construction would disturb about  210 acres including those
 listed above, plus about 21 acres of pine plantation and 8 acres of cropland.

 Transmission line construction would disturb a  total  of about 114  acres including the above acreages and about
 15.6 acres of other vegetation types.

-------
      c
                                      -HH+H-  RAILROAD RIGHT-OF-WAY
                                       --- -  TRANSMISSION LINE RIGHT-OF-WAY
STUDY
                                            TEXAS UTILITIES GENERATING  CO

                                                 MARTIN LAKE "D" AREA
                                                          FIG  I~-
                                                 PROJECT LOCATION MAP

-------
              LA
MARTIN
AREA 'C
BOUNDAR
                                                             iiliiiiiiiiiiiiiiiiiitiiiiiiiiiiii
                                                                                                                              iiiiiiiiiiiiiiiiiiiiii
mull
                 iiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiniiiiii
                                                                               iiiifiiiiiiiiiiiiiiiiiiiiiiiiiiil
                                                                 MATCH  LINE
                                                                                                                                                 Mill
                                                     1987-1997  APPROXIMATE
                                                     YEARS TO BE MINED.
                                               NOTE= ACTUAL  AREAS  TO BE MINED
                                                     ARE SMALLER THAN  SHOWN.
                                                                                                        N
                                                                                                                        DATE OF PHOTOGRAPHY: FEB. 1980
                                                                                                              4000
                                                                                                       FEET
                                                                                                                   TEXAS UTILITES GENERATING CO.
                                                                                                                        MARTIN LAKE  'D* AREA
                                                                                                                               Fig. 1-2 A

                                                                                                                       MINING  SEQUENCE  MAP

-------
               MATCH  UNE
              "•IliMiMMr———:——
                •TUGCO
IIIIMIIIIIIflllllllllAii
iSK. Nb." &-•>•& ~*I~?~}
       1987-1997 APPROXIMATE
       YEARS TO BE MINED.
 NOTE:  ACTUAL AREAS TO BE MINED
       ARE SMALLER THAN SHOWN.

	PROPOSED SWEPCO TRANSMISSION
       LINE RELOCATION ANDTU6CO
       TRANSMISSION LINE CORRIDOR
                                                                      i
                                                                      N
DATE OF PHOTOGRAPHY: FEB. I98O
                                                                           4000
                                                     FEET
                                                                   TEXAS UTILITIES GENERATING CO.
                                                                       MARTIN LAKE 'D' AREA
                                                                                              Fig. 1-2 B

                                                                                      MINING SEQUENCE  MAP

-------
                       PART II.
CONSULTATION AND COORDINATION

-------
PART II       CONSULTATION AND COORDINATION

This section of  the  FEIS  summarizes  the consultation  and coordination  activities
with federal, state and  local agencies and the public  which have occurred since  the
Notice of  Intent for  this  project  was published.   The  first part (II.A.) discusses
activities which  occurred  prior to  the release of the  DEIS.  The second  part (II.B.)
discusses the publication of the DEIS and  the  Public Hearing and the last part (II.C.)
describes activities associated with this FEIS and, finally, the Record of Decision.

A.            ACTIVITIES PRIOR TO THE DEIS

A notice of intent to prepare an EIS on  the  issuance of an  NPDES permit  for  the
proposed Martin  Lake "D" Area  project was  issued by EPA, Region 6, on December
18,  1981.   Federal,  state  and  local  agencies,  and the  public were  invited   to
participate  in the  process  for determining the  scope  of  issues to be addressed  and
for  identifying  the significant  issues related to  the proposed  action.   A  public
meeting  (Scoping Meeting) to receive input  was held on  January 28,  1982, at  the
Rusk County Courthouse in  Henderson,  Texas.  The Scoping Meeting was advertised
in  area  newspapers  and  on radio.   The   meeting was  attended   by  over   250
representatives of federal, state and local agencies and general public.

The major  issues and concerns identified by EPA and expressed by federal, state  and
local agencies, organization, and individuals during the scoping process included:

              (I) Potential  for contamination  of major aquifers;
              (2) Successful reclamation  in  terms of  surface  soil suitability  and
                  revegetation efforts;
              (3) Impacts on surface-water quantity and quality;
              (4) Impacts on and protection of wetlands and riparian areas;
              (5) Loss of wildlife habitat;
              (6) Postmining land use and reclamation  impacts on wildlife habitat;
              (7) Assessment of the quality of fisheries habitat;
              (8) Consideration  of the impacts on cultural resources;
              (9) Land use changes due to reclamation;
             (10) Socioeconomic impacts on communities;
             (II) The effects of the work force on area schools; and
             (12) Consideration  of transportation systems and traffic increases.

These 12 major  issues and concerns, and others, were  used to develop  the DEIS.   A
Preliminary Draft Environmental  Impact Statement (PDEIS) was sent  to cooperating
federal  and state agencies  for  review  and comment  concurrent with  EPA  review.
Eight (8) agencies responded with written comments to be  used in the production of
the DEIS.  Agencies that commented were: U.S.  Fish and Wildlife Service; Office of
Surface Mining;  Corps of Engineers; Sabine   River Authority; Texas Department of
Water  Resources;  Texas  Parks  and Wildlife Department; U.S. Soil   Conservation
Service;  and  Texas  Historical  Commission.   The agencies'  major  comments  are
reproduced  below.   Based  upon  these,  the Draft  EIS was prepared.    EPA  can  be
contacted for responses to specific comments.

-------
1-  Section  6.2.3.6.  Reclamation Success and Coat.   This aection of the
    DEIS compares  the  various engineering costs associated with overbur-
    den and  topsoll  handling for the four reclamation alternatives under
    consideration.    It  Is  assumed  that  post-reclamation  management
    expenses  would  be  the  same   for  all  alternatives,  regardless  of
    whether  topsoil  Is  replaced or not.  We believe  this Is a debatable
    assumption,  when one  considers the  fact that  additional quantities
    of line,  fertilizer,  and plant materials will  be  required to estab-
    lish  successful vegetation  without  the benefit  of  topeoll.   These
    considerations  should  be factored  into the  cost  analysis  of  the
    reclamation  alternatives.   Admittedly,  these  concerns  may  be  minor
    costs compared to the  overall  expense of overburden handling) never-
    theless,  the comparative  costs of revegetation  practices should be
    displayed to lend credence to  the  conclusion* reached In the DRIS.

    There are  two other  considerations  which  we  think should  be  men-
    tioned regarding this  type of  reclamation  analysis.  First,  there is
    no detailed  comparison  on  the productivity  of native  soils  versus
    mixed soils.   It  is  very  likely  that  native  soils, given  the  same
    amount of fertilizer  and maintenance care  as reclaimed  nine  lands,
    would have  i greater productivity.   Secondly,  although  it  has  been
    well documented  that  mined  lands  can have  • high  productivity  when
    actively  managed,   what  might happen  to  the land following  bond
    release  and  return to  the original  landowner?     Xf  the landowner
    does not  utilize comparable,  intensive management  practices as the
    mining company,  the land might deteriorate  faster  than native  soils
    due to a lack of fertility,  leaching  of  toxic materials, etc.

2.  Section  6.5.1.1.  Metland Communities.   According  to  the  Corps of
    Engineers' April 1982  wetlands  determination for  the Martin Lake "D"
    Area, there  are  about  13S9 acres of  regulatory wetlands on the pro-
    ject study area  (Appendix D).   However,  the  DEIS quotes a figure of
    8SO acres.   This  discrepancy should  be  rectified.   Also, are the 50
    acres of  regulatory wetlands  to  be  Impacted by  project operations
    for  the  first  5-yr.  mining  Increment  or  the life-of-the-project?
    This clarification, plus the status  of  the Corps'  Section  404  per-
    mitting actions,  should be described in this  section.   Please  note
    that we  have requested  the  Corps  to re-evaluate  the extent of  its
    regulatory  jurisdiction  on  project  area  wetlands,  based upon  new
    hydrologic data  available since  1977.   A  copy  of  our  request  has
    been forwarded to you  for  reference.

3.  Section 6.6.3.1  Vegetation.   The  statement that  "since the pre-min-
    ing clearing will proceed  Incrementally  over a  span of  30 years  with
    concurrent reclamation,  the associated  Impacts are  considered  to be
    short-term*  is both erroneous  and misleading.   Regardless of whether
    the mining area is  cleared  incrementally or not,  the ultimate result
    will be 16,600 acres of  land extremely low In  wildlife  habitat  qua-
    lity under  the mining  company's  proposed  revegetatton  scheme  (i.e.
    pastureland).  Due  to  the length of  time  required  for  nixed forest
    communities  to regenerate through the successlonal  process,  impacts
    associated with mining and reclamation activities must  be considered
    long term as discussed on  pp.6-87 through 6-88.  The only short term
    impacts  associated  with  vegetation  clearing would be erosion,  water
    quality,  etc.  and  not  the  re-establishment of  diverse vegetation
    communities.
4.  Section 6.6.3.2. Wildlife.  On p.6-90 it is stated  that  "reclamation
    activities  will  follow  mining and  will  mitigate  the  short-ten
    adverse impacts  on  wildlife population  reduction  through  re-estab-
    lishment  of  a diversity  of vegetation  (and  thus,  habitat)  types".
    This is  in  direct conflict  with the  statement on  p.5-35 that  the
    thrust of  reclamation  efforts  will  be  to re-establish  pastureland.
    Paaturelands are not diverse plant communities  which  lend  themselves
    to mitigating wildlife  habitat  losses.   The planting  of woody trees
    and shrubs will provide some  diversity  to pasturelands, but  not  the
    quality or  quantity of vegetation  required  to  prevent  long-term,
    adverse wildlife  Impacts.   This  section should  describe  In  more
    detail the  measures which  will be  Implemented on  site to  restore
    impacted  habitats  (i.e.,   the   best  technology  currently  available
    requirements in the surface mining regulations).

5.  Section 6.11.2. Impacts of No Action Alternative.   Based on U.S.D.A.
    statistics, it is suggested that land used for  farms  and pastures In
    the study area  will continue to  decline.  However,  on pp.6-71  and
    6-85,   respectively,  it is  indicated that  wetlands  and  terrestrial
    vegetation will continue to decline in acreage  through their  conver-
    sion to  farmland or  pasture.    This  is  an  apparent  discrepancy on
    land use trends which should be clarified In  the DEIS.

6.  Appendix E. Threatened  or Endangered Species Biological  Assessment.
    If not already accomplished, we  suggest  that  this biological  assess-
    ment be forwarded to our  Regional Director  (Attni Endangered Species
    Coordinator) in Albuquerque Cor official  review and comments.

In summary, our greatest  concern on this project Involves the necessity
for protecting  bottomland hardwoods and  wetlands.   These are the  most
productive  and  threatened  wildlife habitats on  site.    We believe  the
DEIS  should  spell  out  in more detail  what  mitigation  features  and
regulatory actions will be  undertaken to ensure  the  protection of these
important natural resources during  issuance  of  the  NPDES permits.

-------
Soils
1.  The  footnote on page 1-4  states  that present topaoils are
    fine  sandy  Loam.  However,  topsoil as defined  in  the  draft
    EIS  includes a mixture of A,  B  and somet imes C  horizons.
    Such  a  mixture will be heavier  than fine sandy  loam in most
    cases.

2.  An undiscussed alternative,  where mining would  affect the
    luka  soil  type, would be  to  save this fine  sandy  loam
    material  since it would make  excellent rooting  medium.

3.  The  chemical and physical analyses of the  soils are baaed
    on mixed  overburden with  no  cores to identify  potential
    toxic  zones.  Furthermore,  there is no justification for
    relying on only five cores  for  the entire  25,000  acres for
    overburden analysis.

Fish  and  Wildlife Resources

L.  It  is  difficult to assess  impacts on wildlife  without
    knowing the post-mining  ratio of pasture to  woodland.
    Until  this ratio is finalized,  it is impossible to estimate
    the  Loss  of wood I and dependent  species.

2.  Table  1-2,  page 1-9 states  that  no impacts  will occur to
    recreation yet page 6-83  lists  several bird  and mamma 1
    species that are hunted  in  the  area.  Since  habitat for
    these  species will be  reduced there will undoubtedly be a
    reduction in hunting opportunities.

3.  On page 5-24 it is stated that  only one stream will be
    diverted  yet on page  5-29 it is stated that  diversions and
    rerouting of small streams  will be necessary.   This
    contradiction should be  resolved.

4.  It should be mentioned  on page  6-82 that in  addition to
    preying on destructive  insects  and rodents,  herptiles are
    themselves prey for some  birds,  mamma Is and  other herptiles.

5.  Appendix  E contains a  "no effect" assessment of project
    imp acts on threatened  and endangered species.   The final
    EIS  should contain  the  U.S. Fish and Wildlife  Service
    concurrence or disagreement with this dete rm ina 110 n.

Socio-economics '
 L.   Table 6-24 should  breakdown the population into
     cons truetion and operation categories.
2.  It  is  stated  on page 6-131 that project  workers will  earn
    an  averge  of  $25,000 annually while  page 6-140 uses an
    average  of  $22,000.   This dif ferenee should be explained.

3.  An  explanation is needed as to why  "materials'* comprise
    nearly one-third  of  the annual operation and maintenance
    cost shown  on page 6-144.

4.  Section  6.L5.3.L  refers to four other  mine and/or power
    plant  projects in the region during  the  same time period
    yet there  is  not  even a brief narrative  on these projects.
    A tabulation  of employment, population impact s,  residential
    impacts,  school attendance, etc. would be helpful in
    assessing  the cumulative impacts of  these projects.

5.  Considering  the several projects proposed, it is
    conceivable  that  the City of Henderson may attract the new
    residents discussed  on page 6-L30.   If Henderson is
    selected  over Longview, the implications would certainly  be
    significant and deserve discussion.

6.  Although  children will be included  in  the peak population
    influx of 892 persons.  Section 6.15.I.4  contains no
    specific  enrollment  forecasts for schools in the project
    area.

7 .  There  is  no mention  of any impact assistance revenue  for
    local governments which are affected by  this project.
    Section  6.17.3 should explain how the  expected 1.2 million
    dollars  in  property  taxes will be distributed among local
    jurisdicti on 9.

Cultural Resources

I.  Further  discussion of cultural resource  work conducted both
    in and around the project area is needed.

2.  There  should  be estimations of numbers,  kinds and  locations
    of sites  that  might  be expected t.o occur  within  the project
    bound a r i e s.

3.  Top priority  should  be directed toward developing
    identified  cultural  resources, not conducting inventories
    on Lands  that  may be impacted.  Early, detailed  planning
    and intergovernmental-company cooperation ensures  that
    protection  of  cultural  resources will  not delay  proposed
    project  activities.

-------
 Hyd ro logy

 1.   On  page 3-7  some statement  is needed  concerning the  change
     in  elevation of the  watershed in pre-mining  versus
     post-mining  configurations  and the  associated  changes,  if
     any,  in the  time of  concentration.

 2.   The  differences between d imens ionl ess  hydrographs should be
     discussed.   Additional support should  be provided as  to the
     reasons the  SCS personnel believe the  Mockus hydrograph
     will  represent an average d imens ionles s unit hydrograph for
     the  sub-basin.

Ceo logy

 1.   The  chemical  properties of  the overburden and  its method of
     replacement  could have significant  effects on  the potential
     for  contamination of  major  aquifers.   There  should be
     additional chemical  and physical data  presented in the  DEIS
     perhaps as an  appendix.

Transportation
I.
2.
     The use  of diesel versus electricity was discussed in  the
     haul  train alternative  but not  in the  discussion of trucks
     versus conveyors  for within mine transportation.
     In discussion  of  the  railroad,  it is  stated that  the
     railroad  "can  be  designed with  no at-grade cc^rssings s
               ffic  will be  unaffected."  It  is unclear if t
     local  traff
     railroad  will or  can be  so designed.
                                                                 the
Vegetation :

1.
     Page 1-31  refers  to "spontaneous  re vegetat ion" .   The phrase
     "natural  invasion"  should  be substituted.
2.   The discussion of  impacts  pages  1-8, 1-9  indicate  a plan  to
     change  the  ratio  of woodland to  pasture  to a new unknown
     ratio.   It  is impossible  to assess  impacts of such a change
     without  knowing the new  ratio.   This must  be addressed.

3.   Support  is  needed  for the  assertion that  restoration of
     woody species would be difficult.

4.   The statement is made on  page 5-35  that  the predominant
     land use  is pastureland  yet other  statements indicate 50
     percent  pasture and 50 percent woodland.   This
     contradiction should be  resolved.
5.  On  page 6-72 species diversity correlation with  habitat
    variability  is only true  for species composition along
    environmental gradients,  not for  int ra-coramunity diversity.
The following errors In  the document  should be examined.

Section 3.2 5th line,  the statement "the determination of wetland* by" should
read "the determination  of the Area of Jurisdiction by"

5.1.7.1, Line 1  The tern wetlands seems to be an error.

Figure 5-4  Details on this map are extremely difficult to distinguish, and  In
Its present form the map serves no useful purpose.

6.6.1.2.1 Page 6-81, 1st full paragraph, 10th line, the references Kendelgh  and
Fawrer (1981) and Dlckson and Degelqulst (1979) are not listed In the
bibliography.

Page 6-122 2nd paragraph.  This statement uses a 1978 average value for farmland
In the county.  These figures nay not be realistic due to the Inflation rates of
the last four years.

The following paragraphs are In regard to content of the document*

In Section 5.4 It states "the USCE may require Section 10/404 permits for
certain project activities".  This Indicates some confusion as to which activi-
ties require U.S. Army Corps of Engineers (COE) authorization.  Furthermore, the
term "Section 10/404 permit" Is Incorrect since this refers to two statutes  and
separate authorizations. The discharge of dredged and fill material Into
streams and adjacent wetlands during project activities will require authoriza-
tion under Section 404 of the Clean Water Act.  Since no navigable waters of the
United States exist within the project boundaries the project should not affect
these waters, therefore  authorization under Section 10 of the River and Harbor
Act of 1899 Is not required.  Also, In this section the term "USCE Environmental
Section" should read "USCE Fort Worth District Permits Section".

Section 6.5.1.1 2nd paragraph 8th line: Two citations USCOB (1978) and Whitlow
and Harris (1979) are not the only references examined for wetland  plant
tolerances, nor are they necessarily representative.  These citations should be
removed.  Furthermore, the citation USCOE (1978) 1» not particularly suitable
for the Fort Worth District area.  At the top of page 6-67 the EIS states "The
general consensus among  the regulatory agencies Is that the definition of 404
wetlands should also Include annual Inundation sufficient to saturate the soil
throughout the root zone for 30 days during the growing season".  This Is not
the general consensus of the regulatory agencies, and certainly not the
consensus of the Corps of Engineers. This statement should be deleted.

The first paragraph page 6-67 states that 327 acres of "wetland communities"
exist In the project area and seems to  Imply that those wetlands defined by  COE
are something other than "wetland communities".  Since a definition of wetland
communities was not presented, the purpose of this distinction from those
wetlands under COE jurisdiction Is unclear.  The wetland definition In the COE
regulations and quoted In the Y.IS la more conservative than other commonly

-------
accepted wetland  definitions Including that now used by the Fieh and Wildlife
Serlvce.   Since  this  distinction of wetland acreages In the EIS Is only a natter
of  definition  the 372 acre wetland figure should be deleted.  A figure for those
wetlands not within COE  Jurisdiction would be desirable.  The paragraph also
states  that 850  acres of "regulatory wetlands' exist within the study area.
This  It not the  wetland  acreage (1,359) provided with our wetland determination.
From  where was the 850 acre figure derived?

On  page 6-67,  and again  on page 6-74 the E1S states that only 50 acres of
"regulatory wetlands" will be mined.  Ts this figure for the entire mining
sequence or for  the first 5-year plan only?  Will these wetlands be restored or
lost  permanently and  where are these wetlands located?  The mining sequence map
Figure  1-2 shows major Intrusions Into both the Mill Creek and the Tlawlchl
Creek wetland  complexes.  This sequence map should be more specific as to where
mining  will take  place.

The EIS Is not specific  and rather contradictory on the subject of stream diver-
sions.  On page  5-28  (1st paragraph) and again on page 6-75 It Is stated that
mining  operations will avoid major streams presumably Mill and Tlawlchl Creeks.
However, on page  5-28 the F.IS states thst "flood protection levees and stream
diversion  channels may be provided where necessary to prevent floodwaters of
major creeks from entering mine pits".  This statement Is contradictory.
Furthermore, on  page  6-75 It Is stated the "minor streams which are mined
through" and section  5.2.2.3 states that diverting and rerouting small streams
will  be necessary. However, on page 5-24 the F.IS states that only one stream
will  be diverted.  Does  this refer to the 5-year plan only, and which stream(s)
will  be affected  and  how?

On  page 6-73 through  6-75 a discussion Is made on the Section 404(b)(l)
guidelines under  the  heading of operation Impact.  The evaluation Is lost In
this  section and  should  be under an Individual heading or Included as an
Appendix.  The evaluation should follow the format of the 404(b)(l) guidelines
published  In 40 CFR Part 230.  Much of this may take the form of summary state-
ment  which reference  the text.  A statement concerning the water-dependency of
the project and  compliance with the guidelines should be Included.

The sections regarding the Impacts of no action alternatives generally assume
that  a  general development and deterioration of the area will occur.  This Is
not based  on fact. Several statements In these sections are without foundation
and should be  deleted such as that on page 5-1, 3rd paragraph which states
"clear  cutting and natural phenomena such as damage from fires and Insects could
weaken  the present woodland cover and cause a greater potential for accelerated
erosion".  The forest ecosystem ts readily adapted to these natural phenomena
and accelerated erosion  should not result from these ongoing processes.  This
paragraph also states that "vegetative cover would continue to change toward
lesser  diversity  because of silviculture and agriculture".  However, section
6.11.1.1,  page 6-117, states that agricultural lands In the area have decreased
from  55% In 1969  to 48t  In 1978 and the number of cattle decreased 20X  In the
region  from 1976-1980.   This contradicts the statements that this area la being
progressively  developed.
In general, the KIS appears to take a stance of advocacy  rather  than  objectivity
In. the discussion of alternatives for overburden handling procedures.   The  F.IS
falls to document the differences other than engineering. In  these  procedures.
Discussions based on the literature, should Include short and long  terra produc-
tivity of the reclaimed land, revegetated differences, and fertilization  dif-
ferences of each alternative.  In section 5.1.4.4, alternative one  Is chosen
based soley on engineering costs to the company.  Additional  factors  such as
costs of revegetatlon, fertilizer cost for Initial reclamation, long  term fer-
tilizer costs to the landower, long tern loss of agricultural productivity  for
the landowner, and wildlife habitat quality should be Included. These factors
should also be compared to the no action alternative.

Comments on the Cultural Resource Portions of the PDEIS.

1.  The permit area Includes the mine area, railroad spur, transmission lines,
haul and access roads, highway relocations, stream diversions, mine service
facilities, the cooling pond (6-50 shows It outside the mine boundaries)  and any
other proposed facilities.  What portions of the permit area, as discussed, have
been surveyed and what percentage of the permit area does this equal?  What
methodology was employed?

2.  The known sites are not discussed In sufficient detail (page 6-98).   Has
subsurface testing been conducted?  Are subsurface deposits present?  Are these
properties eligible for the National Register of Historic Places (NR)7  If
sufficient Information exists to determine these properties eligible, or  Ineli-
gible for the MR, this should be stated.  The existing environment discussion
(Section 6.9.1) does not provide any Information on the archeologlcal and
historic background of the area, or on the known sites.  Specific locatlonal
Information would be Inappropriate, however a general discussion of topographic
setting, site size and relationship to proposed activities should be Included.

3.  The PDEIS provides conflicting and confusing Information In regard  to
Impacts on cultural resources.  It states that mining will not take place In
sensitive areas such as cemeteries and cultural resource sites (1-5).  However,
It also states that, prior to mining, the area will be cleared of all vegeta-
tion.  Other project Impacts can be expected from the construction of the faci-
lities and related actions discussed earlier.  Will the avoidance Involve all
activities In the entire permit area, or only mining In the raining area?  Total
avoidance would result In no Impact to the cultural properties, however the
PDEIS states variously: that sites will be "disturbed" (1-8), "none of the known
sites within the mine boundary will he affected by this project" (6-99),  and
that there will he an "Irreversible commitment of any cultural resources  that
are within the direct path of construction or mining activities" (6-99).  The
meaning of the words "Irreversible commitment" In regard to cultural resources
Is unclear, but It Is assumed to mean that they will be destroyed.  This  section
should be clarified to present a uniform assessment.

4.  Although the Texas Historical Commission (THC) Is correctly listed as a
cooperating agency (7-1), It Is not listed as having received a PDEIS for review
and comment (7-3), as would be appropriate.  No evidence of the necessary coor-
dination with the THC In the form of a proposed Memorandum of Agreement,  or
discussions Is referenced.  It this coordination underway, or on-going?

5.  The PDEIS gives vsgue, confusing and contradictory Information on the
cultural resources.  The points mentioned above should be addressed, as should
any comments from the THC.  The Information should be discussed concisely, but
with sufficient detail to allow assessment of the consequences of the project's
construction for any significant cultural resources.

-------
Section 5.1.6.1,  Page  5-13

This section  states  that  10-50% of a given acreage will he planted to woodland.
Yet on page 6-29  It  Is  given  that  on other TUGCO mines 9.7Z of the areas have
been planted  to forest,   noes TUGCO propose to plant a higher acreage to trees
on the urea D than  It's other mine areas or will the acreage of trees be much
the same?  If so, the  statements citing 10-50Z forest are contradictory.

Section 5.1.0, Page  50

The PDEIS states  that TUGCO owned  land upon completion of reclamation will be
handled In the most  cost-effective method.  It does not state how TUGCO owned
land will be  reclaimed.   This should be discussed along with the amount of TUGCO
land to be reclaimed.

Section 5.2.1, Page  5-23

This section  states  that  "major stream diversions or rerouting are not antici-
pated.  A 200 foot section of Dry  Creek would be diverted."  This Implies that
Dry Creek Is  not  a major  stream.   However, on the same page It la stated that
"Diversions and rerouting of  small streams  might be necessary."  This statement
Is contradictory  since  It Is  Implied above that Dry Creek, a minor stream, will
be the only stream diverted.   The  number and anticipated length of stream diver-
sions should  be stated  In the FTS.

Section 5.4,  Page 5-33

This section  discusses COR Section 404 alternatives In terms of Individual per-
mit criteria.  The discussion Is somewhat misleading since an application will
not be filed  and  an  Individual permit will not be processed for the mine and
most of the accessory  facilities.   Since moat discharges of dredged and fill
material  Into the waters  of the United States will be upstream of the head-
waters, the work  may be authorized by a genera]  permit Issued on a nationwide
basts provided the  conditions of  the permit are met.  No administrative proce-
dures are necessary  to  receive authorization under the nationwide permit.  If
all the work  Is In  compliance with all conditions, COR alternatives are to take
no action, or to  assert discretionary authority and require an Individual permit
for the proposed  discharge IF the  District engineer has reason to have concern
for the aquatic environment.
Section 6.3.3.2, Page 6-46

The PDEIS states that between 9 and 36 percent of the flow In Mill Creek could
be diverted to the mine pits through dewaterlng of the ground water strata.
However, on page 6-89 Section 6.5.3.2 the PDEIS states that base flows of Hill
and Tlawlchl Creeks "should not he significantly affected and that the quality of
stream flow to downstream ecosystems should not be adversely Impacted over the
long-term."  No data .or reasoning Is provided on which to base these conclu-
sions.  We consider a 36Z reduction In base flow In these streams as a signifi-
cant Impact that may adversely affect the aquatic ecosystem In those streams and
downstream wetlands.

Section 6.3.3.3

The PDEIS states that the "results of the geochemlcal analysis from the overbur-
den cores (see 6.1.1) Indicates that no significant problems should result from
any chemical constituent."  However, we can find no Information In Section 6.1.1
to support this conclusion.  Information on possible water quality Impacts to
ground water Is scattered and inconclusive.  On page 6-48 It Is stated that
"calculations Indicate" a net PH value greater than 4 will exist In ground
water.  These "calculations: are not adequately cited and documented.  On page
6-49 the PDEIS states that "It Is anticipated that concentrations exceeding
water quality standards" (In ground water) "would be restricted to within a  few
hundred feet of the mine."  This statement seems to Indicate that adverse
Impacts to ground water will occur on the mine area.  Presumably the mine will
be relnhablted by landowners following reclamation.  If this Is the case, will
the ground water be unsuitable for human and livestock consumption, and if so,
for how long?  If the monitoring program detects severe water quality Impacts on
ground or surface waters, what action will he taken?

Section 6.5.3.2

On page 6-88, It Is stated "The short-terra Impacts on downstream water quality
and the dependent wetlands should he minimized since all discharges nust comply
with State Water Quality standards for segment 0505 of the Sablne River and
EPA's NSPS for coal mine discharges."

The use of federal and state regulatory standards as justification for a conclu-
sion that the project will not have adverse Impacts Is not logical or conclusive
reasoning.  Impacts should be documented and assessed on their actual potential
effects.

Section 6.6.3.2, Page 6-104, 3rd paragraph, line 11 and 12

These citations are not  Included In the bibliography.

-------
The Draft  EIS states  that  the control of  sediment load, pH  and  iron content of water
 entering  streams from  the mining and reclamation areas is  required by the Railroad
 Commission.   The EIS should discuss more fully what parameters uil] be monitored,
 frequency of monitoring,  concentration and  load allowed  to  be  discharged to
 receiving streams, and  what the Railroad Commission standards  are for discharge
 compliance.
The
 disc
     use  of  pesticides  for  control of weeds,  insects and other  pests as necessary  is
  u...-;cussed  as part of  the  re-vegetation program.   Will any pesticide monitoring he
  performed?  Since it was  indicated that  fertilization to aid  in re-establishment of
  vegetation during the reclamation phase  may temporarily increase nutrient levels of
  surface runoff to area  streams, will pesticides  used in the reclamation phase also
  cause an increase in  these  substances in the runoff?

 In the applicants proposed method for overburden  handling, the potential for exposure
  of layers  high in pyritic sulfur (which  can result in low soil  pH and possible
  release of toxic elements in runoff waters)  appears totally dependent on equipment
  operators  being properly  trained to recognize these thin layers which are high in
  pyrites and selectively placing these layers near the bottom  of the pit.  How
  effectively can this management technique be accomplished?  The Draft EIS does not
  discuss if any monitoring will be done for  toxic elements in  runoff waters or what
  particular parameters are involved.


 "In the discussion of water quality, it is stated  that the mine plan has been formulated
  specifically to avoid major streams to the  extent practicable and that surface runoff
  from disturbed mining areas will be routed  to sedimentation ponds which must meet EPA's
  new source performance  standards for alkaline mine discharges.   There was no discussion
  of what the effluent  concentration guidelines are for these performance standards.  Also,
  will there be any required  periodic monitoring of Mill Creek, Tiawichi Creek and Lake
  Cherokee to determine if  any impacts are occurring to these receiving waters?

 Finally, it was stated that  the prevention of long-term adverse  impacts to downstream
  water quality is assured  by the required certification of compliance with State Water
  Quality Standards of  all  discharges from the proposed project and by the EPA's New Source
  Performance Standards.  However, it is not  clear from the information presented as to
  how this will be accomplished.

In closing,  we would offer  a  comment that  is'broader in scope than  the particular lignite
mine discussed herein.  A significant area of the  Sabine Basin upstream from.Toledo Bend
Reservoir is affected by  existing and proposed lignite mining operations.  Do the various
regulatory agencies consider  the potential cumulative impact from all of these projects
on downstream receiving waters?  Are there any plans to increase  monitoring activities to
evaluate  water quality  trends over the life of the mining projects?
We consider the hydrologic data and the  analytical method (I.e., Soil Conservation
Service  computerized  watershed model, TR-20,  1965) used in  the report ore reason-
able for preliminary study purposes.  However,  we have some reservations as to the
viability of the conclusions reached in the report relative to  soils, ground wafer,
and surface  water, as summarized  in TABLE  1-2 (page 1-8).  Fundamentally, we are
concerned about the viability of two key generalized assumptions  adopted  in the
analysis,  i.e., (I) that  the surface runoff  chemical characteristics  will remain
essentially unchanged  after mining  and reclamation over the 30-year  operational
period (section  6A3.I, page 6-61);  and, (2) that  the treatment of discharged waters
from the system of sedimentation ponds into  existing natural  water courses and
lakes will remain uniform, effective, and uninterrupted under  all circumstances over
the 30-year  operational period (section 6A3.1, pages 6-56 to  6-61).

It  is our opinion that  predictions of:  (I) the  probable quantity and quality of
waters discharged from the active  mining and reclaimed mined sections of Martin
Lake Mine Area "D"j  (2)  the probable effectiveness of the treatment plan for
discharged waters;  (3)  the probable impacts of discharged waters on the quality of
water in Lake Cherokee)  and, (ft) the probable Impacts on other downstream water
right permittees, could be more confidently and  reliably undertaken If complete
physical and chemical  data on the  soil overburden (i.e., soil stability; bulk density;
clay content and type; rock  content; erodibility; acid-forming, alkali-forming,
salineforming, and  trace-metal-forming potentialities) were mode available to and
considered by the environmental  impact analysts.

We believe that the findings and conclusions of the  report relative to surface water
quantity and quality pertaining to Martin Lake Mine Area "D" and Lake Cherokee
should be considered in light of the experience  and results observed by the Texas
Railroad  Commission  and TUGCO in  Mining Areas "A", "B", and "C", regarding:  (I)
the changes  in  storm  runoff from reclaimed mined lands; (2)  the water quality
control effectiveness  and sediment-trapping effectiveness  of the sedimentation pond
system in terms of total  dissolved  solids  (IDS), total suspended solids (TSS), and
hazardous trace metals; and (3) the selenium  problems in Martin Lake.  Available
historical data  on existing sedimentation  ponds in Martin  Lake Mine Areas "A", "B",
and "C" Indicate that  in  regard to  the TSS parameter,  treatablllty has proven to be
Ineffective.  Thus, adverse water quality  impacts could result  If the  same TSS
treatment method  is adopted In the small watershed of Lake  Cherokee, Ipcated In
the Martin Lake Mine Area  "D".  In addition, special consideration should be given
to the  probable effect of ineffectively treated inflows on existing  power plant
cooling water properties  of Lake Cherokee.

-------
On page 1-7 of the document, several Issues are listed that  were  Identified
during the scoping process which express a concern for the Impacts upon, and
losses of, fish and wildlife habitat.  Proper reclamation is  also  Identified
as a major concern.

While the document provides a great deal of Information, it does not provide
the detail needed to enable this  agency to  determine  the quality  of habitat
created following mining and therefore  its suitability to various wildlife
species.  Although the document lists  the vegetative species  that would be
planted  during  reclamation,  it  does not  give  the approximate acreages
allotted  to  various  vegetative   types,  I.e.,  coastal   bermuda,  mixed
herbaceous, pine plantations, mixed woody, etc.

According to Table 6-15,  approximately 41%  of the project  area 1s currently
woody  or  forested  area.    While  this  agency understands  the problem of
providing  a  completed map  that  delineates the  proposed  plantings  on the
entire mining  area,  a plan that  describes  the general Intentions would be
helpful.

In order to provide a reclamation plan that discloses the  needed Information
and would be beneficial to wildlife, the following measures are  suggested.

     (1)  List the percentage or  acreages of  land that would be replanted In
          coastal bermuda, mixed herbaceous cover, pine plantations, mixed
          woody, etc.

      (2)   List  the type planting  patterns  that would be used in planting
           woody  species,  e.g.:
5a)
(b)
                the number of acres in each plot,
                the shape of plots, i.e.,  motts,  strips,  etc.
      (3)   Planting  fence rows  with species  beneficial  to wildlife  would
           provide travel  lanes  for  wildlife.
                                                                                            1.   It should be noted that the four alternatives listed on page 5-10 and
                                                                                                Figure 5-1 do not correspond to alternatives 1n Figure 5-2 and cost
                                                                                                estimates on page 5-17.  It appears alternatives 2 and 3 are reversed.

                                                                                            2.   The plan does not clearly define how "chop cut" method would be accom-
                                                                                                plished.

                                                                                            3.   There 1s continued concern over revegetatlon species.  Based on past
                                                                                                land use and revegetatlon activities, essentially all land not to be
                                                                                                1n woodland has been returned to bermudagrass.

                                                                                            4.   Page 6-21, Prime Farmland, second sentence -   ...very little of the
                                                                                                area qualifies as prime farmland based on soil type and historical
                                                                                                land use."  This statement 1s not entirely correct.  On approximately
                                                                                                one-third of the area the soils qualify as prime farmland.  Although
                                                                                                the Railroad Commission may have Issued a finding on not prime due to
                                                                                                historical use, this does not change the USDA  classification.

                                                                                            5.   Page 6-21, Prime Farmland, last sentence - "It 1s possible that the
                                                                                                postmined soils will enhance production through Improvement of the
                                                                                                root medium, thereby creating a long-term beneficial Impact."  This
                                                                                                1s a rather optimistic statement.   Should we carry this one step
                                                                                                further and suggest that we should mine all of northeast Texas to
                                                                                                improve the soils?  Some attributes of the soil may be Improved,
                                                                                                such as loosening the subsoil, but doubt an overall benefit.
Page 6-16 states "...prime farmland soil as defined under criteria established
     by the SCS."  Should be "...prime farmland as defined In Federal Register
     and identified by the USDA-Soil Conservation Service."

Page 6-176 - the EIS compares fertilizer costs by stating simply that moderate
     amounts of fertilizer and lime are needed.  The same statement is made
     for existing soils.


     Past experience in mined areas of East Texas on Wilcox Geologic materials
     indicate that higher amounts of a complete fertilizer are needed on mine
     spoil areas where existing sojls need mainly nitrogen with small amounts
     of P and K to maintain an acceptable level of production.  Organic matter
     content and micro-organism content are higher on existing soils which has
     a beneficial effect.


     Perhaps a comparison of fertilizer costs would be in order, similar to
     comparison of costs for different mining alternatives.

Reference was made to the chemical properties of mixed overburden,  but could
not find a table that showed the laboratory data.

-------
 Page 6-96-97
     The section on "Existing Environment" appears to be a literature
     review and does  not discuss how the sites will be affected,  nor'
     does it mention  the determinations of affect which have been made.

     No percentages of areas surveyed are given.

     Differentiation  in areas surveyed and not surveyed are not pointed
     out specifically.

     The Walling Cabin, 41RK104, has been-determined eligible for the
     National Register of Historic Places.  If other "old structures exist
     in the area...," they should be recorded or some explanation given
     as to why they have not been recorded.

 Page 6-98
     A discussion regarding the sites found would be desirable; while
     specific locational data is not warranted, a more complete discus-
     .sion of the sites and their occurrence in the project surroundings-,
     i.e., how they will be affected, is appropriate.

 Page 6-99
     The statement concerning the "irreversible commitment" of resources
     is misleading—it should be simply stated.  It is assumed that
     destruction of the sites is the impact of the project.

     The statement concerning the known sites within the mine boundary not
     being affected by the project is not accurate.  Impacts to those sites
     may occur due to stream diversions, land clearing, catchment basins
     and other activities.

     Why will  41RK85  and 41RK86 not be disturbed, since  there is  lignite
     in the area?  According to what directive will J11RK87  be left intact?.
     How has  that decision been reached and under what consultation
     process  has that taken place?

     The decisions concerning 41RK107 and 41RK108 should be explained in'
     terms of  the process involved in reaching that  decision.

     The memorandum of agreement has been drafted in this project and
     should be noted  in the document.

     Avoidance of sites does not always imply preservation.   Indirect
     impacts  occur by changing the surrounding environment, thus affecting
     the sites.

 The cultural  resource section in this PDEIS is vague and does not differentiate
 between areas directly affected by mining and those associated with all the
•ancillary facilities.   These areas are not dealt with succinctly in relation
 to the project impacts.   Specific plans for further compliance procedures
 are not noted.

-------
B.   PUBLICATION OF THE DEIS AND THE PUBLIC HEARING

The Notice of Availability of the Draft Environmental Impact Statement appeared in the
March  II,  1983  issue of the  Federal  Register.  The Notice announced a public review
period ending May 3, 1983.  The public review period  was scheduled to provide concerned
agencies and  the public with an opportunity to review the DEIS and the make comments
on the adequacy of the analysis of impacts of the proposed action and alternatives.  About
350  copies of  the  DEIS were  distributed  to  reviewing  agencies,  organizations and
interested members  of the public.  Copies of the DEIS  also were made available for public
review at three  locations in  the project area.  During the review period, 40 comment
letters were received.

EPA sponsored a Public Hearing on the DEIS at 7:30 P.M. on April 26, 1983 at the County
Courthouse in Henderson, Texas. The meeting was attended by representatives of EPA,
Texas Utilities and  project consultants.  About  175  members of the public, interested
agencies and  organizations attended the hearing.  The hearing  was divided into  three
parts: first, representatives of EPA made formal presentations; second, comment state-
ments were made by interested citizens;  and third,  questions were received  from the
audience. Four individuals read statements during the Public Hearing.

Each of the 40 comment letters and two (2)  of  the  statements  (for a total of 42) are
presented on the following pages, with EPA's responses printed beside the comments.  Two
(2) of the statements read at  the hearing were superceded by letters which are included
prior to the other comment letters on the following pages.
                                      11-10

-------
2


3


4


5


6


7


8


9


10


II


12


13


14


15


16




18


19


20


21


22


23


24


25
                 PUBLIC HEARING





LIMITED  STATES ENVIRONMENTAL  PROTECTION  AGENCY





         ENVIRONMENTAL IMPACT STATEMENT





      TEXAS UTILITIES GENERATING COMPANY


  MARTIN LAKE "D"  AREA LlONITl: SURFACE  .MINE





                 April 26,  1983
             RUSK  COUNTY COURTHOUSE
                nr:"oriRr-^.:,  TEXAS
STATEMENT OF MR. BILLY FURRH
      at the Public Hearing
         April 26, 1983

-------
 2


 3


 4


 5


 6


 7


 8


 9


10


11


12


13


14


15


16


17


18


19


20


2!


22


23


24


25
I-
            MR. HUDSON:   All right.   Mr.  Billy  Furrh.

Mr.  Furrh,  would  you go to the  microphone.

            MR. FURRH:   I am Billy Furrh,  Water

Chairman,  Marshall-Harrison County League of  Women


Voters.   I  would  like  to know among other things

you  state  in the  EIS statement  that in  1981 natural


gas  costs  3.5 times more than lignite per BTU,


I would assume is what  you mean by that,  and  I

would like  to know what the comparable  figures


are  for today, I  think  that we  are all  aware


that natural gas  prices are somewhat lower now

than they were in 1981.   Another thing  I  would


like to know is,  you are talking about  clearing


a large area of vegetation, and how is  this


vegetation  going  to be  disposed of, if  it is  going

to be burned, naturally we would need some data

on how this is going to affect  emissions into the air.
                                JOHN FOSTER
                                                                                                            Responses to the Statement at the Public Hearing
                                                                                                                         by Mr. Billy Furrh
                                                                                        I.  The cost figure stated on page 5-1 of the Draft EIS included the average cost for all
                                                                                           utilities in Texas. System-wide costs for Texas Utilities Company System (TUCS) for
                                                                                           calendar year 1982 are lignite at $0.842 per million BTU and natural gas at $3.499 per
                                                                                           million BTU.  Thus, in 1982 gas cost TUCS about 4.2 times as much per BTU as did
                                                                                           lignite.

                                                                                        2.  As stated on  page 6-124 of the Draft EIS, all  marketable timber or wood products
                                                                                           would be sold while unmarketable vegetative matter  would be burned on site.  The
                                                                                           burning would adhere to  Texas Air Control Board (TACB) regulations. The applicable
                                                                                           TACB regulations are,  Texas Administrative  Code, Title 31,  Natural Resources,
                                                                                           Chapter Ill-Particulates, specifically paragraphs 11.2  (6) C, D, E, F, G and H. These
                                                                                           restrict burning to: outside corporate limits of a city or town, only when the  wind
                                                                                           direction carries smoke  away from  occupied areas,  at least 300 ft. from occupied
                                                                                           areas, dry plant material only, between the hours of 9:00 a.m. and 5:00 p.m., and only
                                                                                           when wind speed is greater than 6 mph but less than 23 mph.

-------
                                                                    22
 1


 2


 3


 4


 5


 6


 7


 8


 9


10


11


12


13


14


15


16


17


18


19


20


21


22


23


24


25
that  I  haven't  seen covered in this  statement.

There is talk about high  level management on  this

reclaimed property for five years.   After five

years,  it reverts to the  landowner,  and I think

the landowner should be made aware of what  they

are going to have to do,  to keep  this property

in production.   On page 1-7, referring to air

and sound quality., it states that long term

adverse secondary impacts will occur.  I think

that  probably we would like to know  in laymen's

language what these  — how long  they will  last.

I also  think with the reclamation that has  been

going on since  1977, it would be  --  or should

be imperative for all groups concerned to be

able  to have a  tour of this area, and I don't

mean  a  tour of  an isolated showcase  project like

we liavp at Fairfield or somewhere like that,  I

mean  let us see how and what you  are doing  on

reclamation work here in  East Texas.  It states

also  that in numerous areas that  eighty to  ninety

percent productivity will be resulted fron  this

reclamation project, but  it's kind of contradictory

I think, it talks in terms  —  are  we talking

about eighty to ninety percent of the wildlife that

we still have hero  --  we are talking about  some
Mr. Billy Furrh
Page 2

3.   Section 6.2.3.5 (pp. 6-27 to 6-29 of the Draft EIS) discusses the fertilizer and lime
    requirements during the bonding period and predicts, in general, the requirements
    after release from bond.  Also, see Response to Comment No. 5 from Dr. Greg Beil.

l\.   The  statement  on  page  1-7 of the  Draft EIS  refers only to  long-term advese
    secondary impacts to air quality—not sound quality. The reference is made in regards
    to operation of the  Martin Lake Steam Electric Station (MLSES).  Long-term refers
    to impacts throughout  the life of the power plant. Adverse refers to a lessening of
    air quality compared to conditions without the plant.  Secondary means that, since
    the EIS concerns mining, these impacts are not directly a result of mining but are due
    to burning the lignite.

5.   TUGCO states that they frequently conduct tours of the Martin Lake "A", "B" and
    "C" mining areas for  groups and individuals.  Anyone interested can contact the
    MLSES office.
                               JOHN FOSTER


                              Hf-OE'JSOSi 1FKA5 75PS;

-------
                                                                           23
 1


 2


 3


 4


 5


 6


 7


 8


 9


10


11


12


13


14


15


16


17


18


19


20


21


22


23


24


25
 of the prime hunting land  in  East Texas,

 which  will  not  only  be barred  to public  use

 for  a  number of years, but what is  going to be

 there  as  far as wildlife goes  after this

 reclamation takes place.   In  other  places

 in the statement, you state that fifty to

 ninety percent  will  be in  improved  pastures.

 Well,  I would   prefer soraething a little more

 specific  than fifty  to ninety  percent.   In

 another area you  say ten to fifty percent will

 be in  forest.    Once  again  I think you could

 be a little  more  specific  on  that.   I would

 like to know why  non-native species of vegetation,

 such as cottonwood and tallow  trees are  introduced.

 I  have  heard that it  is because these species

will grow in sub-standard  soils.   I think the

 major  issues and  concerns  should  be  --   although

 there  are twelve  listed,  the one  that I  think

 the jury is  still out  on,  is number one,  our

 potential for  contanination of  major aquifers.

 Number  two,  again related  to water,  the  impact

on surface water  quality and quantity.   And

number  five,  and  this  is just  s  personal  concern

of  mine,  but I   think  it would  be  shared  by a

number  of people  in  East Texas,  is  the loss of
Mr. Billy Furrh
Page 3

6.   The measure of productivity is based upon reference areas or published standards.
    Reference areas are  parcels of land which have not been disturbed by mining and
    which are used for  comparison  to disturbed areas in determining  revegetation
    success.   Reference areas are  in use at mining areas "A", "B" and "C". Therefore,
    productivity of reclaimed pastureland is  measured against  undisturbed pastureland
    while  the productivity  of reclaimed forest areas  is measured against undisturbed
    forest areas. The productivity refers only to revegetation success, not re-establish-
    ment of  wildlife populations.  The impacts to wildlife and  predictions of postming
    conditions are discussed in Section 6.6.3.2 beginning on page 6-99 of the Draft EIS.
    The use  of a percentage range (10 to 50 percent)  for reforestation is vague.  This
    represents the TUGCO commitment. It is unknown whether this will be acceptable to
    the RRC. For any given acre of land the  vegetative cover to be established may  be
    based upon  factors such as: suitability  of the land (e.g., steep  slopes near  water
    courses may be most suitable  to woody species); adjacent vegetative cover (e.g., a
    small  area of grassland partially surrounded by woody species may be most appro-
    priate); desires of the land owner (e.g., lease conditions  may specify the vegetative
    cover); or regulatory restrictions  of  the RRC (e.g., planting woody species may
    represent a land use change). TUGCO's practices in reforestation at  the "A", "B" and
    "C" areas have increased each year (during the last three  years) and  reforestation
    areas  presently amount to approximately 13 percent of  the total area disturbed to
    date.

7.   The list of species in  Table 6-17 (page 6-98) was developed by TUGCO in consultation
    with  Texas Parks and Wildlife Department, Soil Conservation Service  and Railroad
    Commission of Texas.  The list represents those species which might be used  during
    reclamation. Inclusion of any species does not mean that it  would be used, only that
    TUGCO  has the option  to use  it if conditions warrant.  Some non-native species are
    included for potential use in special circumstances.  The special circumstances which
    might call for the use of introduced (non-native) species  include: (I) unavailability of
    native species; and (2) more optimal growth of the introduced species compared to
    native species. The particular species used in any case, the  freguency of use and the
    acreage  of  coverage must  be determined on a  case-by-case  basis.   The RRC
    regulations (.39!) state that an introduced species may  be used only if approved  by
    the RRC under the following conditions: (I) after appropriate field  trials have
    demonstrated that the introduced species are desirable and necessary to achieve the
    approved postmining land  use; (2) the species are  necessary to achieve a  quick,
    temporary and stabilized cover which aids in controlling erosion and measures  to
    establish permanent vegetation are developed; (3) the species are compatible with the
    plant and animal species of  the region; and (4) the species meet the requirements  of
    applicable state and federal  seed or introduced species statues and are not poisonous
    or noxious.
                                  JOHN  FOSTER

-------
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25


9-





















24
wildlife habitat. It seems to me that TUGCO had
conveniently not furnished the data on what is
happening in their present reclamation projects.
So, I think it would behoove all of us to wait
until it can be demonstrated, that the methods
they are using will do what TUGCO projects it
will do. Thank you.


















Mr. Billy Furrh
Page 4
8. As stated on page 1-9, the twelve concerns listed were identified during the scoping
process. However, the ordering of the items is related to the order in which those
subjects are addressed in Chapter 6, not to their importance (i.e., No. 1 is not
necessarily more important than No. 12). Each individual or agency might attach the
most importance to different concerns, but all twelve are important.






















JOHN   F OSTE  R

-------
 2

 3

 4

 5

 6

 7

 8

 9

10

II

12

n

M

15

16

17

 Ifl

 19

20

21
24
                   PUBLIC  HEARING



UNITED STATES  ENVIRONMENTAL  PROTECTION AGENCY



          Ljr.'VTRONME'lTAL  IMPACT STATEMENT



       TEXAS UTILITIES  GEMMATING  COMPANY

  MARTIN1  L.V-r  "D"  AREA  LinNITi:  SURFACE MINE



                   April  26,  1983
              RUSK COUNTY COURTHOUSE
                  iir\"?i"!*KON, TEXAS
                                                                                                 BEFORE THE UNITED STATES  EUVTROMMKNTAL

                                                                                                            PFDTF.CTION AGENCY


                                                                                                            IN THK MATTER  OF:

                                                                                              PUBLIC  HEARING  - ENVIRONMENTAL IMPACT STATEMENT

                                                                                              MARTIN LAKE  "D"  LIGNITE SURFACE MINE PROJECT
           RUSK COUNTY COURTHOUSE

           HENDERSON, TEXAS  75652

               APRIL 26, 19S3



STATEMENT OF C.US L. BFO'CT! ET UX  BETTY  IV.  BRO'.VN

                P.FD 4 30X 732

           HENDERSON, TE-JiS  75652

        P.ESIPENTS A.ND PROrinTY O'.VMERS

            II-.' THE CAFTtONED A.C;E(\

-------
 I
-J
!.!any  residents ans  property ov.Tners of the  captioned  area are  servei

ty electric, telepV:or.», ar.3 coiiri.jrlty -water cooperative;-.  Ir..jresr

nni f'-f-c-r:- to ap.'i  1'ron thfir  liotnp*:. p.-opc-rt;-,  '.•h'.ireher, -rorvT'j-:'.';.

centers, an: cimeterie,- are by  way o!' "tste ai:ri/or :23.

2.  .j.ll-.•••»•»tfcer. public roais. of E  J?~i?n ar:3 ivic'th eqnal  'o or

    eyceea'nc  tho.TP ir\ tr>.-  K.r°.& at.  f-lii.7  ia^e, he  ~.iirita:'.r.e::  TO ani

     fi-om -,c!i  resi-JencPs.  property.  ..-?. :i--'hes, xttZ'ftrisF ,  com:-mix-'

    cer^v.'rs, p'.ioli^ par^s.  0**^., as  'fiOrc:  ir.  ti'e  ftrpL  TO  of 1:?.:;

     cictn, and  •::it!!ou+.  '. :M?   -iro.i'-y  'not  in exoesj 3f  .".J p~r.?er.*

    of tr.e  present •.!!••:-^r,ce)  to ar--1  .'ron io-.-to:-!,  ler.'.lr'.:.  ;:c.-?I-.als ,

     ?ho:ip:'r:.-  cen^^r.-,  i
                                                                                                                                                Response to Comments in the
                                                                                                                                       Statement of Cos L. Brown et ox Betty W. Brown
I.  Continued electric,  telephone, water, gas and other services  can be expected with
    compliance with Section M22 of the RRC regulations.  This section states (in part)
    "All surface  mining activities shall be conducted  in a manner which  minimizes
    damage, destruction, or disruption of services provided by oil, gas, and water wells;
    oil, gas, and coal-slurry pipelines; railroads; electric and telephone lines;  and water
    and sewage lines which pass over, under, or through the permit area, unless otherwise
    approved by the  owner of those facilities and the Commission."  Water  service is
    further protected by Section .352 which states,  "Any person who conducts, surface
    mining activities  shall replace the water supply of an owner of interest  in real
    property  who obtains all  or  part of  his or  her supply  of  water  for  domestic,
    agricultural, industrial,  or  other  legitimate use from  an underground or surface
    source, where the water supply has been affected by contamination, diminution, or
    Interruption  proximately resulting  from the  surface  mining  activities."   Non-
    compliance with any of the regulations or with the Texas Surface Coal Mining  and
    Reclamation Act would result in the issuance of a Notice of Violation or  Cessation
    Order  as required under Part 843 - Enforcement.  The enforcement procedures  are
    designed to ensure  compliance or  to halt mining activities if  regulations ore  not
    complied with. Some indication of compliance and enforcement can be obtained from
    the Information on violations submitted in the recent TUGCO application to the RRC
    for construction at  the loading station area (Appendix B).   Regarding water wells,
    generally the burden of proof of damage falls on the well  owner. EPA has  no further
    information on enforcement.  In  various instances,  specific  plans have  not been
    addressed so that a review of wliether they will likely meet regulations cannot now be
    made.

2.  The protection of  public roads as well as residential property, cemeteries, churches,
    parks and other private and public structures is addressed by Section .071 of the RRC
    regulations.  Buffer  zones  are required between these properties and mining opera-
    tions.  The buffer zone between mining and an occupied dwelling may be reduced
    after the dwelling owner provides a written waiver consenting to actlvltes closer than
    300 feet. Mining activities may occur closer than 100 feet to  the right of way of a
    public  road (I) where mine access roads or haul roods  join such  o right-of-way line or
    (2) where the Commission allows a public road to be relocated or the area affected to
    be  within  100 feet  of such  a rood  after (a)  public notice (appearing in a local
    newspaper of general circulation) at least two weeks prior to any hearing and a public
    hearing (if one is  requested  by an Interested party or determined necessary by the
    RRC) and ,(b) making a written finding that  the affected public  and landowners will
    be protected.  TUGCO has proposed to relocate a section  of FM 782 (see Part III) but
    no agreement  with the State  Department of Highways and Public Transportation has
    been made and no official request for reduction of the buffer  has been mode to the
    RRC.  The request, if one is  made, should be made in the  mining permit application.
    No mechanism exists to reduce the size of the buffer zones for  cemeteries, churches,
    schools, community or Institutional buildings and public parks. The RRC states (1983)
    that In the past, requests for reductions  in the size of buffer zones have been denied
    in cases where the supporting documentation provided by the applicant was insuf-
    ficient to justify a reduction.

-------
           3.   The noise level, quality  of air, and  water is conducive to good

               health and  productivity of humans, animals, and vegetation, and

               not disruptive to public  places, such as churches and  cemeteries.

           4.   The mir.in/r  operations of  proponents shall not cause  or create

               erosion to  ruch property  or cause a reduction in the useful life

               expectancy  of  buildings,  fences, and/or  other improvements.
CO
          RESPECTFULLY SUBMITTED  THIS 26TH  DAY OF APRIL,  1983

                        0
          GUS L. BRO'.YN
Gus L. Brown et ux Betty W. Brown
Page 2

3.  The RRC regulations provide for the protection from excessive noise (Section .071,
    Buffer Zones), lessened air quality (Section .379) and change in the quality or quantity
    of both surface and ground water (Sections .339 through .355).  In addition, air quality
    is protected by Texas Air Control Board regulations while water quality is protected
    by compliance with permits  from the Texas Department of Water Resources and the
    U.S. Environmental Protection Agency (NPDES permit).  Some measures have been
    described in the DEIS based on information provided by the applicant.  Each  federal
    and state agency promulgating regulations and/or issuing permits have enforcement
    procedures.  Enforcement procedures vary.  The RRC conducts inspections monthly
    and quarterly at  different times of the day and week to  ensure all aspects of the
    mining operation ore inspected.  In  addition,  individuals who feel their property  is
    being adversely affected  may request,  in writing, that  the RRC  hold a  special
    inspection and  may accompany the RRC during the inspection.  The NPDES permit
    from the EPA requires the permittee  to collect and analyze discharge samples and to
    provide monthly, self-monitoring reports.  If a non-compliance event occurs  it must
    be reported to EPA orally  within 24 hours and  in writing within 5 days  of the event.
    It is important for individuals  living outside the permit boundaries  to be aware of
    impacts  to their property.  If  an  individual feels the mining operation is  causing
    adverse  impacts  (e.g., to air quality, sound quality, water quality, etc.) on  their
    property, he or  she should report these conditions to the RRC or EPA.

It.  Property and structures are protected, in  general, by buffer zones  specified under
    conditions of Section .071 of the RRC regulations. Specific regulations  governing the
    control of erosion are found in Sections .335 through .337 (topsail removal, handling
    and storage), .343 (sedimentation control  including erosion control), .363 (disposal of
    excess spoil) and .393 (use  of  mulch and other soil stabilization procedures during
    re vegetation).

    EPA encourages  you  to continue your interest and to follow the project as it may
    proceed through the various  stages of permitting, compliance and enforcement.

-------
    April 26, 1983

    FTOM: Dr. Greg Beil
          President,
          Marshall/Harrison County League of Vtomen Voters
          313 S. Washington St.
          Marshall, TX 75670

    TO:   Clinton B. Spotts
          United States Environmental Protection Agency
          1201 Elm Street
          Dallas, TX 75270

    SUBJECT: Comments on  Draft Environmental Impact  Statement on the
          Proposed Martin Lake "D" Area Lignite Surface Mine

    A. Vfe believe that more data is necessary to justify using Alternative 1
    for handling of the overburden.  Specifically:
          1. More data on potential acidity of soils.   A distribution of
          values should be given in addition to the  ranges reported in
          Table 6-2 of the EIS.
          2. More data on potential heavy metal content of the surface
          soil.
          3. More information on the oxidation of pyrites, particularly
          after 5 years.
          4. Data should  be made available on long-term population of soil
          microorganisms  and other factors affecting continuing soil fertility.
          There are some  studies which claim that it may take as long as
          75 years for topsoil to rebuild.
          5. More data on fertilizer requirements for average to high crop
VO        yields, particularly after 5 years.  Our concern is that most
          plants will die after the 5-year reclamation period without
          continued heavy application of lime and fertilizer by property
          owners.
    B. Vfe believe that more data is necessary on factors which affect the
    quality of surface water, particularly with regard to heavy metal
    concentrations.  Specifically:
     i   I  1. It should be reported how the samples listed in Table 6-15
        I  were taken — whether the coverage was random, total, or selected.
          2. An explanation should be given for the  value of a manganese
     7    sample in this  table which appears to be above the state allowable
          concentration.
    S  I  3. The range of values for Selenium should be given.
     .,   i  4. More data on heavy metal concentrations from the ponds themselves
    1   | .in carder to be  able to estimate the possible effects of discharges.
    C. Vfe believe that more specific information is  necessary on the reclamation
    of forested areas.  Specifically:
          1. More data on the percentage of mined area which would be reclaimed
     10    as forest.  The 10 to 50 percent value given in the EIS leaves a
          considerable latitude.
                             Response to Comments by
                                   Dr. Greg Beil
     The calculated ranges shown on Table 6-2  represent the range of values from five
     cores and each value is  based upon a homogeneous mixture of  the core.   The
     distribution of  potential acidity values for  the five cores is: 0.0, 1.5, 8.3, 21.3 and
     27.5. The ranges were calculated using the weighted averages of the physical and
     chemical  data  from the overburden  analyses of the five  cores (Appendix B).  For
     example,  to determine the potential  acidity resulting from Alternative I, each core
     was considered separately.  The potential acidity for each segment of the core was
     listed and weighted  acording  to  the  length  of the segment.   Then,  since the
     alternative considers a total mix, the weighted averages were averaged to provide a
     potential  acidity value in  a  theoretical homogeneous mixture of overburden repre-
     sented by that  core.  The calculations can be made in the following manner, using
     data for core hole //1128:
Segment
No.
5-1
5-2
5-3
5-4
5-5
5-6
5-7
(A)
Thickness
(ft)
11.8
16.2
12.0
7.0
1.3
3.3
9.8
(B)
Neutralization
Potential
-0.53
5.00
1.25
-0.95
0
2.73
3.80
(C)
%TotaJ
Sulfur
0.31
0.31
0.31
0.31
23.4
11.3
14.7
(D)
B-C3
-0.84
4.69
0.94
-1.26
-23.40
-8.57
-10.90
(E)
AxD4
-9.91
75.98
11.28
-8.82
-30.42
-28.28
-106.82
TOTAL
                                                                         -96.995
The measure of residual bases in the soil expressed as tons of CaCO, per 1,000 tons
material.  A negative number means the soil is acidic.

The measure  of  pyritic sulfur (acidity) expressed as tons of CaCO,  per  1,000 tons
material.

The acidity of each core segment calculated by substracting acidity value from residual
base value.  A negative number indicates potential acidity.

The weighted average acidity of each core segment calculated by multiplying the acidity
times the segment length.  A negative number indicates potential acidity.

The arithmetic total of weighted average acidity  of each  segment.  The negative sign
indicates potential acidity.

Then the average acidity of a hypothetical random mixture of the core can be calculated
by  dividing  the total weighted average acidity (-96.99) by the length of the core (64.1
feet).  The resulting number (1.5) expresses the potential  acidity of such a mixture in
terms of tons of CaCO, per 1,000 tons of material.

-------
             Marshall/Harrison County League of Women Voters — Page 2
            12.
       2.  More definitive projections on  the use of various tree  and
       shrub species.   In particular, we  wonder why such non-native or
       currently unconnon species as eastern cottonwood, Chinese  tallow,
       and black locust are proposed.
       3.  More studies  should be done as  to the effects of mining on
       wildlife populations in forest habitat in east Texas.  It  appears
       that with present reclamation plans  there is little hope for
       reestablishment  of any semblance of  existing wildlife ccmnunities.

In sunmary, we feel that there is insufficient justification for the
Alternative 1 method for handling the overburden.   The economic  benefits
to the power cotpany are outweighed by the adverse effects to soil
reclamation, surface water quality, reforestation, and the general
future use of the land.
N>
O
Dr. Greg Beil
Page 2

2.   Data  concerning the heavy metal concentrations in the overburden represented by
     the five cores are presented in Appendix B. The five cores were spaced evenly over
     approximately the southern half of the project area.  The data do not characterize
     the overburden throughout the project area.

3.   Pyrite can vary significantly in particle size and physical form. It has been found in
     at least six different forms in coal deposits. The  most reactive form is framboidal
     pyrite which has  particles  less  than  0.0004 inches  in diameter.   The rate of
     breakdown (oxidation) of pyrite is not constant over time and may  depend upon pH,
     the amount  of  oxygen present, the presence of  breakdown  products  and other
     factors. The addition of lime, to raise the pH,  tends to slow down the breakdown of
     pyrite.  The  addition of lime to control  pH during early reclamation efforts could
     actually extend the period of time over which lime is needed.  The low pH caused by
     the breakdown  of pyrite has an adverse effect  on the growth of most plants and
     interfers with successful reclamation.  In addition to the direct effects on plants,
     low soil  pH  also increases the rate of  release  of certain heavy metals (copper,
     nickel, zinc, manganese or iron) causing the amount of these metals in soil to reach
     a level which is toxic to plants. This causes further problems with reclamation and
     revegetation.  The RRC regulations  call for the  successful revegetation  of mined
     lands  and establish a  period of extended responsibility (during which  the land is
     under bond) for the permittee to demonstrate  successful reclamation.   No  such
     protection exists to guarantee control  of pH and metals  after reclaimed land is
     released from bond.

4.   Soil fertility is  dependent upon a number of factors including the physical  and
     chemical  characteristics of the soil (e.g., particle size, water  holding  capacity,
     presence of trace metals, pH,  etc.)  and the presence of microorganisms which are
     important for the regulation of the levels of certain elements (e.g., nitrogen).  EPA
     concurs that under natural conditions topsoil rebuilding could take 75 years or much
     more.  Under natural conditions it may take that  long for all physical, chemical and
     microbiological factors to reach pre-disturbance  conditions.  Topsoil rebuilding may
     proceed much more rapidly if physical and chemical factors in spoils are similar to
     pre-mining  conditions  and  when amendments   (such  as  fertilizers  and  micro-
     organisms) are added during the reclamation process.

5.   Data  on  fertilizer requirements for  average to  high crop yields are presented on
     page 6-28 of the Draft EIS.  Although given as the data for 1981,  the figures from
     TUGCO should be considered as the requirements from year two through five of
     reclamation. SCS technical guides for  soils in the "D" area recommend 100 to  130
     Ibs of nitrogen, 40  Ibs of phosphorous and 0 to 40  Ibs of potassium annually to
     achieve high  yields.  At areas "A", "B" and "C" TUGCO applies (1981 figures) 80 to
     160 Ibs of nitrogen,  90 Ibs of phosphorous and 135 Ibs of potassium to obtain high
     yields. Fertilizer requirements on reconstructed soils vary greatly.  For example, at
     areas "A", "B" and "C" the requirement for phosphorous varied from 40 Ibs annually
     to  135 Ibs annually  in  different reconstructed soils.   No reclaimed  mine land in
     Texas has been released from bond and fertilizer and lime requirements over time
     cannot yet be determined.

6.   The  data  reported  in  Table  6-15   were  collected  at  randomly   selected
     locations  during RRC inspection  visits.   The  data  are  spot  samples from
     sedimentation  ponds  throughout  the  Martin   Lake  "A",   "B"  and  "C"  areas
     and cannot  be considered as  long-term  monitoring  effects.  No  information is
     available  to  indicate  whether  the samples were  taken under varying precipita-
     tion conditions.

-------
 Dr. Greg Beil
 Page 3

 7.      The  TDWR allowable concentrations given  in  Table 6-15 are  for  averages
        (weighted by flow) of all samples collected during a one month period.  TDWR
        also  has grab sample standards which should not be exceeded in any individual
        sample.  Because of the apparent collection procedure for these samples,  the
        grab sample standards should have been  used.  fToble 6-15 has been revised to
        reflect this, see Part III.) The grab sample standard for manganese is 3.0 parts
        per million which is not  exceeded by the highest concentration listed on Table
        £-15 (2.8 parts per million).

 8.      All samples showed concentrations of selenium which were  below the detect-
        able limit (0.01 ppm). No meaningful range can be given.

 9.      These data represent the concentrations in  the  sediment ponds.  We have no
        data on metal concentrations in the streams or sediment below the discharges
        to determine constituents released during rainfall events.

10.      The  use of a  percentage range (10  to 50 percent) for reforestation is  vague.
        This represents the TUGCO commitment. It is  unknown whether this will be
        acceptable to  the RRC.  For any given acre of land the vegetative cover to be
        established may be based upon factors such as:  suitability  of the  land (e.g.,
        steep slopes near  water courses may  be  most suitable to woody  species);
        adjacent vegetative cover (e.g., a small  area of grassland partially  surrounded
        by woody species  may be  most appropriate); desires of  the land owner (e.g.,
        lease conditions may specify the vegetative cover); or regulatory restrictions of
        the  RRC (e.g., planting woody species may represent  a  land  use  change).
        TUGCO's practices in reforestation at the Martin Lake "A",  "B" and "C" areas
        have increased each year (during the past three years) and reforestation areas
        presently  amount to approximately  13 percent of the total  area disturbed to
        date.

II.      The  list of species in  Table 6-17 (page 6-98) was developed by TUGCO  in
        consultation  with  Texas Parks and  Wildlife Department,  Soil Conservation
        Service  and Railroad Commission of Texas.  The list represents those species
        which might be used during reclamation.  Inclusion of any species does not mean
        that it would  be used, only that TUGCO has the option to use  it if conditions
        warrant.  Some non-native species  are  included for potential  use in special
        circumstances.  The special circumstances  which might call for the  use of
        introduced (non-native) species  include: (I) unavailability of native species; and
        (2) more optimal growth of the introduced species compared to native species.
        The particular species used in any case, the frequency of use and the  acreage of
        coverage  must be determined on  a  case-by-case basis.   The RRC regulations
        (.391) state that an introduced species may be used only if  approved by the RRC
        under the following conditions: (I) after appropriate field trials have demon-
        strated  that the introduced species are desirable and necessary to achieve  the
        approved postmining land use; (2) the species are necessary to achieve a quick,
        temporary and  stabilized cover which aids in controlling erosion and measures
        to establish permanent vegetation are developed; (3) the species are compatible
        with the plant and animal species of the region; and (4)  the species meet  the
        requirements of applicable state and federal seed or introduced species statues
        and are  not poisonous or noxious.

12.      Comment noted.

13.      Comment noted.

-------
    •.C.OURTNQII3C
                                        DAVID P. BROWN

                                          ATTORNEY AT LAW

                                            ». o. eox caa
                                                                                                                         Response to Comments by
                                                                                                                            Mr. David P. Brown
NJ
N;
                                       April 29,  1953
         I'.r.  Clinton B.  Spottc  (6ESF)
         United Jtates environmental  Protection
         12<"il  ~]n Street
         j.illns, TX   75270
                                                                   m
                                                               MAY  2   1333

                                                                 GE3
         Dear  Xr. Spotts:

         ?o:   .'-".nvironriental  Impact .Statement  on Martin Lake  D Area Lignite
               Surface  Mine in Henderson,  Rusk County,  Texas.

               Cn April 26, 19S3,  I testified  at the  hearing  in the husk  County
         Courthouse  on the above  referred to  Sr.vironraental"lnipac t  Statement
         arid y/as requested to submit written  co::usents.  I had several concerns
         ar:d questions which I raised  at  that meeting  and which  will he  dis-
      According  to the draft if.IS,  T'JGCC  rr.ay only reforest 10 per  cent
 of  the  area to  be mined.   (Their  proposed plans call  for ref orestati T.
 of  fi-o.ii  10 to 50 per  cent  of the  affected area).   Vour table 6-23
 shov.-o  that over 1,0  per cent (Itl.&i) of the area to be r.:ir,ed is  nj'.v
 forest,   I feel that  T'JGCO  should be -required  to reforest  the affect
 area v:i th approximately the sarae  amount of forest as  it- now has, tha*
 is  at  least IjO  per cent.   :/e value both our forest and our  pasture
 lands  in  this area and both are vital and essential to the  agricultural
 Tconomy  of this area.   vVe have many pine  trees  in this area which are
 sold both for timber  and pulpwood,  and  it would be a  severe blow to
 this area to have such a large portion  of our lands which are forest. d
 in  pine  trees cut back to such a  lov; percentage of the affected  area.
 Also,  our hard'.vood trees as well  as our pine trees contribute verv
 significantly to the  beauty of this area.   You  would  only have to"
 drive  through this area one  tine  in the fall of the year tc  appreciate
 the :nany  reds,  yellows,  oranges,  and other colors which adorr. the
 trees  of  this county  and area during the  fall.   I submit that the
 beauty of this  region  in the fall  rivals  that of  any  in our country.
 The tourism is  a growing and important  part of  our local econo.-ny.
 Therefore,  I submit that TUGCO should be  required to  agree  to and
 G-yo.T.it proof that they can  and will return the  percentage cf pasture
 and tinberlands  in the affected area to almost  the si-r.e percentages
 of  pasture  and  tii:.terlajids  that are now found in  that  area.   T'JGCO
 should not  be issued  a permit  from  you  until it guarantees  that per-
ce:it--3ge and shows that it  can  restore that land adequately  to s:;ppor;
approximately ^0  per  cent  forest.
I.   The plan for revegetation as stated to EPA is vague and is of concern to EPA.  If the
    plan for 50 percent reforestation of the area mined is implemented it  would amount
    to  greater acreage  of wooded  vegetation  than now  exists; however, 50 percent
    reforestation is not seriously expected based on past measures taken by TUGCO.  In
    addition  to  the  NPDES wastewater discharge permit, the Railroad Commission of
    Texas has been delegated surface mining regulatory authority, the U.S. Department
    of  the Interior Office of Surface mining has overview responsibility.  The mining
    regulations allow  for a  significant  vegetation  change on disturbed areas from
    woodland to "monoculture" grasses.   TUGCO states that the 10-50 percent range is
    their commitment  and apparently believes a permit  will be obtained from RRC. The
    most environmentally sound revegetation alternative is considered by EPA to be that
    requiring equal acreage replacement utilizing native species for forage and cover for
    maximum recovery of wildlife habitat.  Some of TUGCO's final plan will depend on
    the landowner lease conditions.

2.   Comment noted.

3.   Relatively temporary sediment loading problems are expected  to occur during  and
    after construction  of the mine facilities area but the significance of these impacts to
    water quality is  presently unknown.  Temporary increases in nutrients could occur as
    a result of fertilization during revegetation. The mine facilities area (see  Fig. Ill-l)
    is proposed  to contain two (2) sedimentation ponds as well as facilities  such as a
    sewage treatment  plant, fuel storage  area, maintenance shop, and  handling area  and
    crusher.  Discharges from the  facilities area will be routed through the ponds before
    release into Dry Creek.  The sewage treatment plant discharge will require a permit
    from Texas Department of Water Resources as well as from EPA.  The storage of
    2,500 barrels of  diesel fuel on site will  require TUGCO to have a  site specific Spill
    Prevention, Containment and Countermeasure Plans as called for  by Section 311 of
    the Clean Water Act. The design of the fuel storage site includes containment dikes
    to prevent discharge of any spills in the area of  the tank.  TUGCO states that they
    will obtain an approved plan from EPA before operation of the  facility. Long-term
    monitoring called  for by the Draft NPDES Permit (Appendix A)  may determine if
    effects from heavy metals or other constituents occur.  The discharge to Dry Creek
    should have no effect on cattle drinking the water.

l\.   The quantity of water in Dry Creek during peak flows will be decreased by about 2
    percent during mining operations. More frequent flooding is not expected since  the
    frequency of storm events will not increase and the peak flows will be slightly less
    than at present.

5.   The Dry Creek  diversion is being planned to allow for  mining of a lignite seam
    beneath the present  channel.  Other streams in the project area do not have lignite
    beneath their channels since it  was  washed out during geologic time.  The lignite
    beneath Dry Creek is desirable because it is relatively shallow and can be obtained
    easily and  inexpensively.  The  diversion is planned during the first five years of
    mining.  The construction of the diversion is expected to take six months or less  and
    the  diversion would  be in place  (during mining) for about two years. During that
    time, nonriparian  vegetation would be planted to control erosion and stabilize  the
    soil  surface. Restoration of the channel to the prediversion location also would take

-------
Xr.  Clinton ':•..
Fa~e ?.
Af.fil 39,  19S3
Spotts (62SF)
Your figure 5-6  chows  that  there will be  a discharge  fro:.-, the  retcr.t
pone: at  the loading station-into Dry Creek.  '.Vhat effect v;ill  said
discharge  have on the  water in Dry  Creek?  I am  especially cor.cerne ;
suo t the  effect that  said  discharge v:ill have on the  cattle  drinkir.
•.voter out  of Dry Creek.   Cry Creek  frequently floods  once or  f.vice  •>.'
ye;:r v/hen  there  is a heavy  rain.  This is not a  rare  occurrence,
becy;.:c  I  have see:i it flood quite  often  .r.yself.   .Vhat effec.  v.ill
thi acovo  rcentior.od discharge have  on the qua:- ti ty of  '.rater ir.  ::ry
Creek ur.A  will it cn-;ce  Eoro frequent flooding?

      Your  SIS shows that a  small portion  of Dry  Crack  is jroir.g to "f
tei.-porarily diverted fron its present tanks.  ./hy is  that 3..-.all oori-
of  thMt  creek being diverted? ~ .Thy  ic that the or.l;- creek that is
bsir.£ diverted in the  entire Tdned  area  discussed in  this report?
 .ny Js only a small portion of that creek only beir.g  diverted?  Is
there any  retaliation  because the land in the temporary diversion
has not  been sold to TUGCO,  as have nany  farms in the  area?   ./hen
is  this  diversion planned?   ,Vill this diversion  cause  reclamation
efforts  to take  longer where the diversion is nlar.ned  thnr. they
ivoult: in other areas where  there is no diversion?  You rncntio  ed
in  your  report that a  Railroad Commissior. hearing would be co;iduc-e.:
before this proposed diversion would be  allowed.   ,Yhen will t!:at
hearing  be conducted?   '.Vill the land ov;nors involved  be give!-.  :.otic
of  that  hearing  BO that  they can be present?  ',','ill that heari:::; \>-i
conducted  locally as your hearing has been?

      Your  report states  that FH Koad 782.  will be  diverted,  .'/here
will it  be diverted?   i'/hy will it be diverted?   .'/hen  will it  be
diverted?

      Your  report discusses  whether  there  will be  sufficient law
enforcement officers for the increased population caused "jy this
mining.  However, I do not  find any discussion in your report  T;hat
adequately deals with  the potential increase in  crime.   Statistic;
about the  number of law  enforcement officers needed is nice, but it
doesn't  help ir.uch when your property is  stolen or destroyed.   I kr.sv;
for a fact of certain  increases in  crinc  which occurred when  the
Tl.GCO plant was  being  constructed because I v;as  Assistant County
and District Attorney  in Husk County, Texas, during that period of
time.   The types of crime that particularly increased  during  the
period of  time were the  theft of copper wire (primarily fron ;-5A
lines) and house burglaries.

      :!o  are also concerned  in this  area with what will  be dono with
the enormous ai.-.ount of land  which is being purchased by TUGCO  in
-lining areas.  I am talking  about what will be dor.e with the land
Mr. Dovid P. Brown
Page 2

    about six months. After restoration, the stream channel would be reclaimed to pre-
    mining conditions. The  exact time for this process is presently unknown, but since
    the banks and surrounding area would be reclaimed with riparian vegetation, several
    years could be required before the vegetation  resembles  present conditions.  Pro-
    cedures governing release from bond are stated in Port  807 of the RRC regulations.
    To obtain the release  of an  area  from  bond (including stream  diversions) the
    permittee must file  an  application with the RRC which  includes copies of letters
    notifying (among others) adjacent landowners and local government bodies of the
    intent to seek release and proof of publication of  a newspaper advertisement of the
    application for release  from bond.  The RRC must conduct  a site  inspection and
    evaluation of the reclamation work and, if requested, hold a public  hearing on the
    application for release.  No area can be fully released from bond until  "the permittee
    has successfully  completed all surface coal  mining and reclamation operations in
    accordance with the approved reclamation plan, including the implementation of any
    alternative land  use plan approved pursuant to Section .399 or  .568 and achieved
    compliance with the requirements of the Act, this Chapter, the regulatory program,
    the permit, and the applicable  liability period under Section 23(b)(20) of the  Act and
    Section .306(b) of this Subchapter has expired."

6.   Upon filing  a mining  permit  application with the  Railroad Commission  (RRC),
    TUGCO is required to advertise the application filing in a local  newspaper once a
    week for four  consecutive  weeks (beginning  at  the  time  the complete permit
    application is filed)  and to  file a copy  of  the  application  at  the Rusk  County
    Courthouse for the public to inspect and copy. Until 30 days after the last newspaper
    notice, the RRC  will accept written comments  on the permit  application.   The
    applicant  or any  person with  an  interest which  may  be adversely affected may
    request  a public  hearing but must do so  within 45 days  after the  last newspaper
    publication.  The RRC could decide to hold a Public Hearing without any request. If
    a hearing is held,  it will be held within 30 days of the request or determination by
    RRC, in the locality of the project.

7.   TUGCO proposes to mine the area east of FM 782 (in the southern part of the project
    area) and then divert the road to  a  location  about 1500 feet  to  the east  (onto
    reclaimed land).  The relocation is planned within the first five years  of mining to
    obtain lignite beneath the  present right-of-way.  About a 4 mile portion would be
    diverted  end would tie  into  the existing road through gentle curves (i.e., no right
    angle corners). See Part III for revisions to the text.

8.   Increases  in  crime associated with construction projects are  related to the overall
    size of the construction work force and especially to the number of workers from
    outside  the  project  area (in-migrating work force).  For this project, no direct
    estimates of increased crime rates were made.  The models used for socioeconomic
    analyses for this project do not include factors to directly predict increases in crime.
    However, the small increase in crime which might occur is indirectly accounted for in
    the predictions for the need to  increase police services.  Those predictions are based
    upon  population increases caused by the project and are further affected by state
    recommended standards  for police protection based on the  overall population density
    and type of area  (i.e., rural or urban). The state recommended standards for police
    protection are based on  the level of crime associated with different population sizes
    and the effects of increasing  or decreasing population.  For this project  the in-
    migrating work force would be small  and no significant increase in crime would be
    expected.

-------
N)
-P-
          Mr. Clinton f>.
          Pago 3
          April 39,  1933
                     Spotts (SESF)
    after raining and  reclamation  have been  completed.   This ic an area
    of primarily small  family  farms, and we  do not want one company
    ov.v.inE  all or a large portion of the land.  I feel  that all of the
    land purchased by TUGCO should be returned to the local land owners
    in farms  similar  to  those now found in  that area.

  I       In a related concern, I  would like  to know how TUGCO plans  to
!"•!  keep the  present corners and  boundary lines for farms in  that area
    marked.   This is very essential  to land  titles in that  area.

         Also,  as to a particular  farm owned by :r.y father and  I  in the
    area to be  nined,  there  are two  trees of particular  significance
    which I feel  should  be dealt  with in your report.   The  first is a
    quince  tree which  is  a fruit  tree.   I a-n told  that it is  or.e  of
    only  two such trees in the county.   It  was  a large fruit  tree and
    producing prolifically when my father bought this farm about  1950.
    It is still producing fruit prolifically in  about July or  August  of
   each  year.  Due  to its age and size  I doubt  very  seriously if it
   could be successfully transplanted.   Also,   there  is  a large v;ater
   oak or  pin oak on  our farm which night  even  qualify  for designation
   as the  largest in  the state  or nation.   I do not  know of the  size
   the largest one is,  but this  tree would  probably  take four, if  nor
   irore, men  to reach  around  it with arms  outstretched  at its base.   I
   feel  that  the impact  of destroying such  rare trees should  be  dis-
   cussed in  your report and v;ould be glad  to  take any  of your staff t;
   view these trees at any time.

        These  are some of my main concerns  about the area to be mined.
   I appreciate your giving  me the  time to  speak about  them at your
   recent hearing and accepting these written  cosnents.   -fie would sin-
   cerely appreciate your considering them in  drafting  your final
  report and  deciding whether or not to issue a permit  to  TUGCO to
  nine  the affected area.
Mr. David P. Brown
Page 3

9.  There is no restriction, by surface mining regulation or the Public Utilities Com-
    mission, on the disposition of land owned in fee by a private corporation such as
    TUGCO.

10.  Present  corners  and boundary lines would be re-established on leased land after
    completion of mining. TUGCO-owned land would be surveyed and divided according
    to requirements for disposition of the land. The original corners and boundaries may
    not be re-established.

II.  No regulatory standing or protection  are afforded  to trees based upon size alone.
    Protection might be afforded to trees associated with an historic site or if the tree
    were  declared an historic site.  Possibly, protection of a tree could be included as
    part of  a lease agreement.  The Texas Forest Service (TFS), College Station,
    maintains the "Registry of Champion Big Trees in Texas." Upon request, the TFS will
    send a list of champion big trees and the procedure to measure and register trees.
    Also,  a  national registry of big  trees is maintained by the American Forestry
    Association, Washington, D.C.

The above comments are appreciated.   We encourage you to continue your interest and
follow the project as it may proceed through the surface mining permitting of the RRC as
well as the NPDES wastewater discharge permitting.
                                           Very  truly yours,
                                           David. P.  Brown
        pb

-------
    TEXAS  FOREST  SERVICE
» \           The Tent MM Unltenilf Sytlem

  Am II	        P.O. Drawer 1327
  1214) 657-1033                                          Henderson. Teas  mm.
   6.352                                                        75653-132;
   Environmental Protection Agency
   Interfirst Two Bldg.
   1201 Elm St.
   Dallas, Texas  75270

   Attention:  Jeanene Peckham

   Dear Ms. Peckham:

       Thank you for the chance to review your EIS on the Martin  Creek Lake
   Area D Permit.  I do have some general  comments that are of  concern to me.

       It seems to be a forgone conclusion that this area will  be mined, so
   most of my concerns deal with the reclamation and reveget.ation  of  the mined
   area and the responsibilities of the company to accomplish this.

       The message I percieve from the companies proposals and your  information
   is that reforestation is not going to be considered in the revegetation pro-
   cess except along streams and on steep slopes.  It sounds as  though you ..con-
   sider reforestation too costly and too much trouble to pursue.  At least 33%
   of the land they intend to mine is upland forestland.   As it  stands now, these
   sites are producing valuable commercial timber or at least they have this
   potential.  I cannot agree with changing the land use on these  sites to
   pasture without making an effort to restore them to their pre-mined state;
   forestland.  Your information on the value to timberland is  very discouraging.
   It is estimated that a pine plantation is worth from $100.00 to $125.00 per
   acre, per year over a 35-40 year rotation.  True, it does take  at  least 15
   years to realize initial income but you need to compare value on the same
   basis.  What is an acre of pasture worth each year to a landowner?  What are
   his costs for maintaining this pasture?  I've collected some  figures on the
   initial establishment costs of pine vs. pasture.

                 Costs For Pine Plantation Establishment
                                                                                                                          Response to Comments by
                                                                                                                            Texos Forest Service
                                                                                               I.   The information is sincerely appreciated.
           Treatment

           Seedlings

           Tera Sorb

           Planting
                  Unit/Cost

                  $25/1,000

                  $l/oz.

                  $35/Ac.
                                                     $ 54/Ac-.  Total  Cost
  This should be the only cost incurred in establishing and maintaining a pine
  plantation until the first harvest.
                                  more -
The forest Resource Agency of Texas

-------
NJ
                                           - 2 -

                               Establishment of Pasture!and

                  Treatment               Unit/Cost

                  Seed                    $18.50/Lb.

                  Fertilizer              $185/Ton
                                                      Cost/Acre

                                                      $  9/Ac.

                                                      S 28/Ac.

                                                      $37/Ac.
Application costs are included in the fertilizer costs since the seed can be
mixed with the fertilizer and applied by bulk truck.

     The establishment cost for pine is higher than for pasture but whereas
there are no maintenance costs for growing pine there are yearly-costs for
fertilizer to maintain the pasture.

     I should think that a proposal for at least 30% of the mined area to be
reforested with pine would be acceptable.  Just because the trend has been
in years past for a decline in forested acres does not justify contributing to
this decline in an accelerated manner.  The timber resource is not only
valuable to the landowner but it plays an important role in the economy of  ,,
the county, and the state.  It will always be a challenge for foresters to
ensure an adequate supply of timber for this county and state.

     You have classified certain areas as ecologically sensitive areas because
they are wetlands and highly productive wildlife habitat.  Wouldn't it s'tand to
reason that pine plantations are also ecologically sensitive areas because of
their substantial commercial value? (6.6.1.4)

     Again I would like to thank you for the chance to respond.

     I appreciate the magnitude of the job you are trying to accomplish in
being a good steward of the land for the people of Rusk County.  If I have
raised any questions please feel free to call or write.

                                                 Sincerely,
                                                           Brad Smith
                                                           County Forester
          BS/pj

-------
MARK WHITE
  GOVERNOR
                                 OFFICE  OF THE GOVERNOR
                                          May 25,  1983
                                                                                                                                        Response to Comment by the
                                                                                                                                           Office of the Governor
The comments in individual letters from the different state agencies are responded to
separately for each letter.
            Mr. Dick Whittington, Regional Administrator
            U.S. Environmental Protection Agency
            1201 Elm Street
            Dallas, Texas  75270

            Dear Mr. Whittington:

                 The Governor's Office of Planning  and  Intergovernmental  Relations  has
            received for review and comment  the draft environmental  impact  statement
            prepared on the Martin Lake  "D"  Area  Lignite  Surface Mine  Project  in  Rusk
            County.  The State Environmental  Impact Statement  number assigned  to  this
            project is 3-03-50-008.

                 The following state agency  comments are  provided  for  your  consider-
            ation.  Texas Department of  Water Resources requests that  changes  be  incor-
            porated in the EPA permit to monitor  and report  several  chemical  levels in
            downstream stations in addition  to other locations.  This  request  is  made
            due to inconsistencies in previous water quality reports for  Martin Lake
            and the Sabine River studied by  TDWR.   Texas  Parks and Wildlife Department
            is concerned with the applicant's plan  to use inadequate ground cover for
            reclamation areas and also cites the  need for monitoring downstream fishing
            areas for possible adverse impacts.   The Texas Air Control  Board advises
            the applicant to contact their office to determine the need for
            construction and operating permits for  this facility.  Review coitments  by
            the State Department of Highways and  Public Transportation indicate this
            project will cause extensive damage to  existing  highway  surfaces  in Rusk
            County due to the hauling of materials  and  resulting development  associated
            with this project.  It is recommended that  the applicant consult with SDHPT
            in an attempt to minimize road damage and to  further determine  those  SDHPT
            permits required of the applicant. The Texas Historical Commission is
            notifying the applicant of the location of  a  potential national  historical
            site designation with the request that  this be noted in  the final  impact
            statement.
                 SAM HOUSTON BUILDING
                                           P.O. BOX 13561  •  AUSTIN, TEXAS 78711

-------
         Mr. Whittington
         May 25, 1983
         Page 2
              This office appreciates the opportunity to review and comment on this
         environmental impact statement.  If we may provide additional information
         during the review process, please let us know.
                                       David Nesenholtz, Assistant Director
                                       Office of Planning and Intergovernmental
                                        Relations
         mbs
         Comments enclosed:  Texas Department of Water Resources
                             State Department of Highways and Public Transportation
                             Texas Air Control Board
                             Texas Parks and Wildlife Department
                             Texas Historical Commission
                             General Land Office
NJ

-------
                          TEXAS DEPARTMENT OF WATER RESOURCES
                                        1700 N. Congress Avenue
                                            Austin, Texas
  TT.XAS WATER 1)1:VF.I.O!'Mr.NT BOARD
      Louis A. IWecherl. Jr.. Chairman
      George ft'. McClfskcy. Viijc Chairman
      Cilcn E. Ronry
      W. O. llanbton
      Lonnic A. "lio" Pilgrim
      Louie Welch
NJ
VO
                                                                 TEXAS WATER COMMISSION
                                                                   Lee B. M. Bipgart, Chairman
                                                                   Felix McDonald
                                                                   John D, Stover
                                  Charles E. Ncmir
                                  Executive Director

                                   April 25, 1983
Mr. Harden Wiedemann, Director
Governor's  Office  of Planning  &
  Intergovernmental Relations
P. O. Box  13561
Austin,  Texas  78711

Dear  Mr. Wiedemonn:

Subject:  U.S. Environmental Protection Agency (EPA):  Draft Environmental  Impact
         Statement (DEIS) on MARTIN LAKE D AREA  LIGNITE  SURFACE MINE,
         HENDERSON, RUSK COUNTY, TEXAS.   (EPA 906/9-83-003, March  1983)
         State File Reference:   EIS No. 3-03-50-008.

In response to your March  25  memorandum, members  of the  Texas Department of
Water Resources (TDWR) staff have  reviewed the subject  report being considered by
EPA in  the administrative  review of the application filed  by  the  Texas Utilities
Generating Company (TUGCO), requesting a National Pollutant  Discharge Elimination
System  (NPDES) permit to  discharge wastewaters  from the Martin Lake  "D" Area
Lignite  Surface  Mine, near the City  of Henderson, Rusk County,  Texas.

We suggest that NPDES Permit  (TX  009120) proposed by EPA (Reference:  Appendix
C, subject  report)  be  amended to require  the permittee to monitor and  report  the
concentrations of  ammonia, phenols,  and mercury  at  three selected,  existing down-
stream  water quality  monitoring  sampling stations, in  addition to monitoring the
effluent quality-control  parameters, stipulated in the federal  New  Source Perfor-
mance Standards (NSPS) of October  1982  (Reference:  Table  5-3, page 5-29; and
Appendix C, page  C-2, subject report). This suggestion is based  on  our  con-
sideration of certain findings and inconsistencies observed  between the report of the
Southwest  Research Institute (SWRI) on the ambient water quality sampling and
analysis program in 1974,  and the  reports of the  Sabine River Authority of Texas
(SRA) on water  quality  monitoring program during 1977-1980, in the  Mortin Lake
lignite mining area.  (References:  Section  6.4.1.3, pages 6-54 to 6-64, subject
report;  md,  SRA  Report:   COMPILATION  OF DATA-MILL CREEK  RESERVOIR-
WATER QUALITY  MONITORING PROGRAM-1977-1980, May 1981.)

The  SWRI  program  identified eight water-constituent levels and  quality charac-
teristics which exceeded the maximum-stringency  water-quality standards set  by
EPA, the U.S. Public  Health Service, and TDWR  for drinking-water  supply, aquatic
life, irrigation, livestock and recreation uses.  (Reference:  page 6-58, paragraphs  2
and  3, subject report.)  The water quality parameters identified were ammonia,
                          Response to Comments by the
                      Texas Department of Water Resources


I.   We concur that inconsistencies occur in the water quality data provided to us for
    the area; this presents us with an unknown background for measuring effects.  In
    response, EPA has placed a provision on the draft NPDES permit for monitoring of
    additional parameters as follows:

        In-stream sampling,  analysis and  reporting shall be provided  for
        phenols, ammonia (as N),  pH, alkalinity, turbidity, total suspended
        solids, total dissolved solids and mercury on a once/3 month basis for
        Stream Sampling Stations  TUSI I,  2, and 5, as used in the Sabine
        River Authority's  1977-1980 Water  Quality  Monitoring  Program.
        Grab samples shall be collected  both prior  to, and during,  periods
        when discharges from the mine area are actually occurring.
                                                       r 7 R-7 1 1 •  a .

-------
           Mr. Harden Wiedemann,  Director
           Page  2
           April  25,  1983
                                                                                                       Texas Deportment of Water Resources
                                                                                                       Page 2

                                                                                                       1.   Please note the revised analysis of impacts to groundwater and surface water in Part
                                                                                                           III.
CO
O
mercury, phenols, alkalinity, pH, total dissolved solids, total suspended solids, and
turbidity.  The  proposed NPDES Permit presented  in Appendix C, subject report,
does not require the monitoring and regulation of  any  of these eight  parameters,
except pH and  total dissolved  solids.   We  believe  that ammonia, phenols, and
mercury also  should be monitored  in order  to obtain sufficient data to clarify
inconsistencies and  resolve  uncertainties regarding  the  ambient water  quality of
streams  draining the mine project  area, contained  in earlier reports by  SWRI  and
SRA.  We  believe  this  is essential due to  the  fact that  almost the entire  natural
drainage from the  watershed, and  discharges from  the  mined portions of the
24,960-acre Martin  Lake Mining Area  "D"orea  flow into  Lake Cherokee,  a  major
drinking  water supply source for several local  communities. (Reference:  Page 5-21,
last  paragraph;  and Figure  6-12, page  6-59, subject report.) Therefore, we  suggest
that  water quality sampling, analysis,  and  reporting program of the permittee
include  the continued utilization of Stream Sampling Stations,  TUSI I, 2, and 5,
which were used in the  Sobine  River  Authority's 1977-1980 Water  Quality  Monitoring
Program.   (References:  Figure 6-13—SRA Surface Water Monitoring Sites,  page
6-63, subject  report; and Figure I—Water  Quality  Monitoring  Station Locations,
presented in SRA Report:   COMPILATION OF DATA-MILL CREEK  RESERVOIR-
-WATER QUALITY  MONITORING  PROGRAM-1977-1980, May 1981,  which  was
furnished  to  TDWR by  the  permit  applicant's representative on April  15, 1983).
Further, we suggest  that the  water samples from  these  three  sampling stations be
obtained at least  twice  annually, analyzed for  phenols, ammonia as nitrogen, and
mercury, and  results reported to the  permitting agency.   The  stream  samples should
be collected both prior to,  and during, periods when discharges from  the mine area
are actually  occurring,  and  the evaluations should  be mode in light of earlier SWRI
(1974) and SRA (1977-1980) program data  relative  to ambient  stream  water quality
measurements in order  to provide  current  verifiable data regarding ambient pre-
mining water  quality conditions, and also  to resolve any present uncertainties
regarding the post-mining stream water quality-impacts.

Pending  the completion of our  current  comprehensive staff review of the  hydro-
logical aspects of TUGCO's application to  the  Railroad Commission of Texas  (RRCT)
for a mining  permit, pursuant  to the  administrative agreement of  October  29, 1979,
between TDWR and RRCT, we  hereby note and hold in  abeyance our views regard-
ing the  following  tentative  determinations  and recommendations  presented  in  the
subject  DEIS, relative  to:   (I)  the  anticipated  radius of  influence,  i.e., approximately
3,800 feet) on groundwater  levels,  as a result  of mining area dewatering operations;
(2) the  estimated  number of existing  water wells  (i.e., 142) within the mining
project  boundaries,  and the presently  undetermined impact  on  wells outside the
project  boundaries  which may be affected  by the   mining-area  dewatering operations;
(3) the  possible potential effects of dewatering operations on existing annual  average
streamflows (i.e.,  approximately 10 percent reduction); and, (4) the possible desir-
ability of requiring  the applicant  to "monitor existing  wells downdip  from  earlier
mined areas  to  develop accurate predictions of effects from  dewatering  by pumping
in the northwest area  before mining in that area.  This should coincide with the

-------
Mr. Harden Wfedemann, Director
Page  3,  1983
April  25, 1983
monitoring program required by the RRC."  (References:  Table II, page  IS;
Section 6.3.1, pages  629 to 630;  Subsection  6.3.1.1, pages  633; and, Subsection
6.3.3.2, pages 639  to  644.)  TDWR shall  furnish staff  review comments to RRCT
after the detailed  data on the applicant's proposed mining-area dewatering plan  is
furnished to  TDWR by RRCT for review, pursuant  to  currently proposed Sections
339.61  to 339.71 of  the  Texas Administrative  Code (TAC).

Please  advise if we  can  be of further  assistance.

Sincerely yours,
 Charles  E.  Nemir
 Executive Director

-------
     COMMISSION

ROBERT H OEDMAN CHAIRMAN
A. SAM WALDROP
JOHN «. BUTLER. JR.
STATE DEPARTMENT OF HIGHWAYS
  AND PUBLIC TRANSPORTATION
   DEWITT C CHECK STATE H1GHWAV ILDC.
           AUSTIN. TF.IAS TtTtl
          April  18,  1983
      Draft EIS  H  3-03-50-008
      Martin Lake  "D"  Area
      Lignite Surface  Mine
      Mr. Harden Wiedemann,  Director
      Office of Planning & Intergovernmental  Relations
      Sam Houston Building
      Austin, Texas

      Dear Mr. Wiedemann:
ENGINEER-DIRECTOR
 MARK G GOOOE
                                                 IN REPLV REFER TO
                                                 FILE NO.
                                                 D8-E 854
                                                                                                                                      Response to Comment by
                                                                                                                         State Department of Highways and Public Transportation
                            I.   Thank you for providing information specific to this project area.

                                Discussions  with the State Deportment of Highways and  Public  Transportation
                                (SDHPT)  indicate that several  methods could be useful in mitigating the impact of
                                road deterioration.  Truck routing could be specified to prevent continued passage of
                                heavy trucks over the same roods.  Contractual agreements have been effective in
                                reducing  the  incidence  of overweight vehicles reporting to the job  site.   This
                                approach  requires that suspect vehicles be individually weighed at the job site prior
                                to delivery of materials and that overweight shipments be rejected.  Maintenance
                                agreements, between constructors and the SDHPT,  could be negotiated which call for
                                the constructors to provide maintenance on affected roads (SDHPT, 1983).  TUGCO
                                and the SDHPT do not  presently have any agreement covering  mitigation of  road
                                deterioration.

                                See the revised text in Part III regarding impacts and mitigation.
      Thank you for  the opportunity to review the draft environmental statement
      covering the Martin Lake "D" Area lignite  surface mine project proposed
      near Henderson in Rusk County.

      Experience with  similar operations In other areas has shown that the
      introduction of  a number of heavy trucks and construction equipment will
      have an adverse  effect on area highways.   Although the mined lignite will
      be hauled to Che power station on a private railroad, the area highways
      will be used to  haul heavy equipment to and from the mine; lumber, topsoll,
      iron ore and gravel from the mine; crushed lime to the generating station;
      and flyash from  the generating station.  Many of these loads probably will
      require SDHPT  permits.  Even legal-weight  loads have a cumulative destructive
      effect on the  pavement structure of area highways.  Farm to Market Roads
      designed to carry local traffic are especially affected.

      Presently the  Department has three projects in Rusk County to reconstruct
      roads damaged  by overweight hauling.  These three projects will rebuild over
      ten miles of farm roads at an average cost of $80,000 per mile.  Many other
      highways in the  area also have been damaged and need repairs.  It Is anti-
      cipated that the proposed mining operation in Rusk County will continue the
      adverse effect on area highways.

                                                   Sincerely yours.
                                                  M. G.  Goode
                                                  Engineer-Director
                                             By:
           Clinton Spotts. Regional EIS
           Coordinator Environmental
           Protection Agency
                     Marcus L.  Yancey/^Jr.
                     Deputy Engineer-Director I
                                                                                        1983

-------
              TEXAS  AIR CONTROL BOARD
     JOHN L.BLAIR
     Chairman
     CHARLES R. JAYNES
     Vice Chairman
      BILL STEWART, P. E.
      Executive Director
                                  6330 HWY. 290 EAST
                                 AUSTIN, TEXAS 78723
                                    512HS1-5711
                                                VITTORIO K. ARGENTO, P. E.
                                                        BOB G. BAILEY
                                                        FRED HARTMAN
                                                    D.JACK KILIAN, M. 0.
                                                 OTTO R. KUNZE, Ph. D., P. E.
                                                        FRANK H. LEWIS
                                                       R. HAL MOORMAN
Response to Comments by the
  Texas Air Control Board
                                                                                                The Texas Air Control Board has written a letter exempting the Martin Lake "D" area
                                                                                                facilities site. This letter appears in Appendix B.
         April  12,  1983
CO
CO
Mr. Harden Wiedemann, Director                  _ ,OQ3
Office of  Planning and                     APR  13 1-'OJ
  Intergovernmental Relations                  t	
Intergovernmental Section               Grrivf. !'? ji^l" ".-''Vhi'.KOk
P. O. Box  13561                             O.M.B./&.r...S.
Austin, Texas  78711

Subject:   Draft Environmental Impact Statement for the
           Martin Lake D  Area Lignite Surface Mine Project
           Proposed near  Henderson, in  Rusk  County, Texas by
           the Texas Utilities Generating  Company
           EIS Number 3-03-50-008

Dear Mr. Wiedemann:

It is the  policy of the  Texas Air Control Board (TACB)  not
to require permits for surface mining.  However, associated
stationary sources of air  contaminant  emissions such as
crushers,  classifiers, material handling  facilities, and
power plants do require  TACB permits.   Since crushers and
material handling facilities are planned  for this site, the
TACB must  be contacted for the purpose of determining whether
a construction permit or an exemption  will  be required  for
the proposed facility.   Additionally,  a permit to operate
must be applied for within sixty days  after the facility has
begun operation.

The proposed facility is in a location that meets the
national primary and secondary air quality  standards for
carbon monoxide, nitrogen  dioxide, sulfur dioxide and
particulates (TSP) and is, therefore,  in  a  designated
"attainment area" for these criteria pollutants.  Rusk
County has been designated "unclassifiable" for ozone.
There has  been no designation established for lead.
                       Celebrating ISO Years of Texas Independence 1836 ^1986

-------
       Mr.  Harden Wiedemann          -2-           April 12,  1983
       Mr.  Richard Leard, P.E., Supervisor of Region 12 in Tyler,
       has  been contacted and would be happy to answer further
       questions.   You may reach him at (214) 595-2639.

       Thank you for the opportunity to review this document.  If
       we can be of further assistance, please contact me or our
       regional staff.

       Sincerely,
       /^~)    .  .-•—y
      ''_ ^-'-'^L-^  .^_\p-?c>.£<-(..'  Y,>J_ .>

       Roger R. Wallis, Deputy Director
       Standards and Regulations Program

       cc:   Mr. Richard Leard, P.E., Regional Supervisor, Tyler
CO
•P-

-------
                                           TEXAS
                                 AND WILDLIFE  DEPA  .TMENT
  COMMISSIONERS
  PERRY H. BASS
   Chlimun. Fort Worth
  JAMES « PAXTON
   Vicl-Chiirman. Palestine
  EDWIN L COX. JR.
   Athrni
                                         CHARLES D. TRAVIS
                                        EXECUTIVE DIRECTOR
                                        4200 Smith School Rod
                                         Auitin. T«« 78744
                                                                                COMMISSIONERS
                                                                     ft. B. OSBORN, JR.
                                                                      Sinti El«n>
                                                                     WM. O. BRAECKLEIN
                                                                      Dall.i
                                                                     WM. M. WHELESS, III
                                                                       Houston
                          Response to Comments by the
                       Texas Parks and Wildlife Department


I.   Thank you for the comments.  Your assistance and technical expertise is appreciated.

t.   EPA  concurs and has placed  a provision on the permit for monitoring of additional
    parameters in streams.
          Hay  3,  1983
                                                                   M.I'   5 1SS3
 i
CO
Ol
Mr. Harden Uiedemann, Director
Office of Planning and  Intergovernmental
  Relations
Intergovernmental Section
P. 0. Box 13561
Austin, Texas   78711

Re:  Martin Lake D Area Lignite Surface Mine
     Henderson, Rusk County,  Texas
     EIS II 3-03-50-008

Dear Mr. Wiedemann:
    ^.
This agency has reviewed  Che  above-referenced document and offers the
following comments.-

The information concerning wildlife resources provides an adequate
assessment of current  conditions.   However, the main concern of this
agency pertains to  reclamation following mining.  Utilization of mono-
culture of coastal  bermudagrass will not provide the minimum life
requisites for many wildlife  species.   Reclaiming the mined area to
vegetative cover  comprised of at least 30% woody cover would lessen
adverse impacts upon extant wildlife resources.

Concerning aquatic  wildlife,  adverse impacts upon species important
to public use are not  apparent.  However, surface water discharges
should be monitored to insure that downstream fishing sites are pro-
tected from the adverse effects of sedimentation, turbidity, and releases
of trace metals.
                             Celebrating One Hundred and Fifty Years- 1836 1986

-------
      Mr. Harden Wledetnann, Director
      Page -2-
      I appreciate the opportunity  to review and provide comments on this
      project.

      Sincerely,
      Charles fa. Travis
      Executive Director

      CDT:RWS:jlm

      cc:  Jerome Johnson, U.S. Fish  & Widlife  Service
           Fort Worth, Texas
U)

-------
CURTIS TUNNELL
EXECUTIVE DIRECTOR
                                      April 26.  1983
     •'-'- P.O. BOX 12276
         AUSTIN, TEXAS 78711
         (512)475-3092
     Mr.  Dick Whlttlngton, P.E.
     Regional Administrator
     U.S.  Environmental Protection
        Agency
     Region  VI
     1201 Elm Street
     Dallas,  Texas   75270

     Attn:   Clinton B.  Spotts
             Regional EIS Coordinator

     Re:   Draft EIS - Martin Lake D Area
           Lignite Surface Mine, Henderson,
           Rusk County,  Tx (EIS #3-03-50-008)

     Dear  Sir:

     We have reviewed the document referenced  above pursuant to the National
     Historic Preservation Act of 1966, as amended  and Its implementing regu-
     lations, 36 CFR, Part 800.  We continue to  coordinate and consult with
     all  parties on matters of cultural resources  in accordance with the terms
     of the  Memorandum of Agreement.  Page 6-116, The Vinson Plantation Is
     potentially eligible for the National Register of Historic Places, its
     trinomial site number is 41RK128, these points should be noted in the FEIS.
     We  look forward to future consultation  and  coordination.
     opportunity to comment.

                                               Sincerely,
Thank you for the
                                               LaVerne Herrington, Ph.D.
                                               Deputy
                                               State  Historic Preservation
                                                 Officer
     PEP/LH/lft
          Harden Wiedemann, Officeof the Governor
          Jeanine Peckham, EPA, Dallas Office
                       L/Ae Jinie-Stye/icy for
                                                                                                                                  Response to Comment by the
                                                                                                                                  Texas Historical Commission
I.   The comments  and assistance on cultural resources considerations are appreciated.
    Table 6-18 (pg.  6-113) and pg. 6-116 have been revised to reflect the site number and
    potential eligibility of the Vinson Plantation.  See Part III.

-------
    Garry Mnuro
    Commissioner
    General Land Office
          April  15.  1983
                                                                   '"PR  I 8  13S3

                                                                   ^'^u.-.';.?*'0"
                                                                                                                                    Response to Comment by the
                                                                                                                                General Land Office, State of Texas
                                                                                                          I.  The letter is appreciated and the comment is noted.
           Mr.  Harden  Wiedemann, Director
           Office  of Planning and Intergovernmental
             Relations
           Intergovernmental Section
           P.  0.  Box 13561
           Austin,  Texas 78711

           Re:   Draft  EIS t 3-03-50-008
                Martin Lake D Area Lignite Surface Mine
                Henderson,  Rusk County, Texas

           Dear Mr.  Wiedemann:
 I
00
CO
The General  Land  Office appreciates the  opportunity to review the referenced
report.   It has been  determined by my  staff that state lands  will not be
Involved  or affected  by  the Martin  Lake  D Area  Lignite project;  thus no
substantive comments will be offered.

Sincerely,
           Mike Hlghtower
           Assistant Land Commissioner
           MH/SD/jb
    Slepnen F Ausun Building
    1700 Noftn Congress Avenue
    Austin Texas 78701
    (512) 175-2071

-------
                                                             5
3800 STONE ROAD -KIIGORE, TEXAS 75662 -2U/9B4-8641
     ESVEO

APR   7 1S83
                                                                    SERVING A FOURTEEN COUNTY REGIOf
       April  5, 1983
       Mr. Harden Wiedemann, Director
       Office of Planning and Intergovernmental Relations
       Intergovernmental Section
       P. 0. Box 13561
       Austin, Texas  78711

       Re:  EIS #3-03-50-008

       Dear Mr. Uiedemann:

       The East Texas Council of Governments  (ETCOG)  has reviewed  the Draft Environmental
       Impact Statement (EIS) on the Martin Lake  "D"  Area Lignite  Surface Mine Project
       proposed near Henderson, in Rusk County, Texas by the Texas Utilities Generating
       Company.

       The proposed project is not in conflict with adopted areawide policies, goals,
       and objectives and is in conformance with  the adopted ETCOG Regional Land Resource
       Management Plan and Tri-County Growth  Management and Housing Plan.  Therefore,
       ETCOG gives the proposed project favorable comment and recommends the preparation
       of the final EIS.

       Sincerely,
       Glynn 0. Knight
       Executive Director

       GJK/VE/lm

       cc:  Commissioner Talmadge Mercer
            Rusk County

            Jack Dickerson, City Manager
            City of Henderson
                                                      Response to Comment by the
                                                   East Texas Council of Governments
                                                                                                       I.   The comment letter is appreciated and comments are noted.
        CAMP • CHEROKEE • GREGG • HARRISON • HENDERSON • MARION • PANOU • RAINS • RUSK • SMITH • UPSHUR • VAN ZAKDT • WC"

-------
              United States Department of the Interior

                           OFFICE OF THE SECRETARY
                         Office of Environmental Project Review
                                Post Office Box 2088
                       ALBUQUERQUE, NEW  MEXICO  87103
ER-81/358
MAY 0 3 196J
Mr. Clinton  B.  Spotts
Regional  EIS Coordinator
Environmental  Protection Agency
1201 Elm  Street
Dallas, Texas   75270

Dear Mr.  Spotts:

We have reviewed the draft environmental impact statement (EIS) for the
Martin Lake  D Area Lignite Surface Mine, Henderson,  Rusk County, Texas and
offer the following comments.

General Comments

In general,  we find that the  EIS  accurately describes  existing resources of
the project  area and adequately displays the proposed  project's impacts upon
these resources.   The State of Texas has assumed primary responsibility under
the Surface  Mining Control and Reclamation Act of  1977 for regulating surface
mining in Texas.   The Office  of Surface Mining still maintains an oversight
role in assuring  that coal mining in Texas complies  with that Act.

Although  we  are concerned with many of the applicant's selected alternatives
in the development of this project (i.e., the use  of mixed overburdens, mining
of fragile bottomland hardwoods and wetlands, land use changes from forestry
and grazing  land to pastureland), these options appear to be consistent with
surface mining laws and regulations.  We believe many  of the selected alterna-
tives, especially when considered  cumulatively with other surface mine
projects  within the Texas lignite region, will have adverse, long-tern impacts
particularly on the quantity  and  quality of fish and wildlife habitats.  To
minimize  these impacts the appropriate regulatory  authorities should closely
monitor  the  status of these large scale mining projects with respect to their
impacts  upon fish and wildlife resources and take  whatever measures are nec-
essary to ensure that these resources are adequately protected.

The project  will  have minimal  impacts upon other mineral resources such as
clay, gravel,  oil and gas.

The project  as proposed will  not  impact any present, proposed, or potential
unit of  the  National Park System, the National Wild and Scenic Rivers System,
or the National Trail System.  The memorandum of agreement for consideration
of cultural  resources should  prove to be an effective tool in  preserving
cultural  resources in the project area and we complement the Environmental
Protection Agency (EPA) on its preparation.
                                                                         Response to Comments by the
                                                                        U.S. Deportment of the Interior
I.   Comment noted, EPA concurs.

2.   Comment noted.

3.   A  map showing the  relationship of mining areas "A", "B" and "C" to area "D" is
    included in Part III.   The "A", "B" and "C" areas were  considered  in addressing
    cumulative impacts to all resources as stated on pg. 6-167 and 6-168 of the DEIS.
    Because areas "A", "B" and "C" are  located so close to area "D", the potential for
    cumulative impacts  to geology and topography, soils  and prime  farmland,  ground
    water, surface water, ecology, archaeological and historical resources, air quality,
    land use and recreation, and  socioeconomic  factors does  exist.   These cumulative
    impacts are more evident when considering the "D" area in relation to the "A", "B"
    and "C" areas  than with the  other projects discussed in the section on cumulative
    impacts.

4.   A  table presenting the acreages affected by  project activities has been provided as
    Table 1-2.   A summary table  listing acreages for land  use and vegetation has been
    provided as Table III-1. We trust this clears up the presentation.

5.   The railroad will cross SH-<(3  above the traffic on an overpass constructed such that
    traffic flow will  not  be affected.   In addition, the  railroad will cross two Farm to
    Market roads and three unnamed country roads.   None of the crossings will be at-
    grade and  traffic flow will not be affected during operations.  Construction  of all
    crossings may affect  traffic flow temporarily. See  Part III for detailed information
    on the crossings.

6.   EPA concurs.

7.   EPA concurs that when the preferred alternative  is known it should be included in the
    draft statement.   This  project  is  complicated  regarding disclosure  in  that  the
    significant  aspects of mining  have not yet undergone review by the state agency
    (RRC) which has been delegated authority/responsibility to see that mining require-
    ments are  enforced.  The most environmentally-sound and EPA-preferred alternative
    is  discussed in Part IV. Obviously,  the information  made available in many cases is
    not site specific and, we believe, could not comply  with requirements for a specific
    mining area permit.  Of major concern is  the alternative proposed for  overburden
    handling using mixed  spoil  for a revegetation medium—major justifications required
    by federal  surface mining regulations are not available for review or disclosure.

8.   Section .384 of the RRC regulations state (in  part) that, ". . . all disturbed areas shall
    be returned to their  approximate original  contour." Historically, compliance with
    this section has been determined by comparison  of premining topography maps with
    topography maps of  disturbed areas which  are made  prior  to  the third year of
    extended responsibility (i.e., the third year after land has been placed under bond to
    ensure reclamation).   Premining maps  are  typically produced (at the applicant's
    request) by an  independent aerial survey company.  Aerial photographs of the area
    are used,  in conjunction with  surveyed ground-control points,  to  determine  the
    topography. The postmining topography maps are developed by the permittee using
    aerial photos of the  disturbed areas and the  surveyed  ground-control points  to
    determine  contour lines.  Submission of such maps prior to the third year of extended

-------
Specific Comments

Section 1.2,  PURPOSE AND NEED  and Section 6.18.  CUMULATIVE IMPACTS - A map
showing the location of the  "A",  "B", and "C"  area  mines is needed to show
their relation to the "D" area mine, and the possibility for cumulative
impacts to  some resources.

Section 1.4,  PROPOSED PROJECT  - It would be helpful if the actual acreage
to be disturbed by mining, haul roads and ancillary structures were clearly
shown throughout the EIS.

Section 5.1.3. Transportation  Systems and Routes -  It is not clear how  the
railroad will cross SH-43.   It is stated that  it would not be a grade
crossing,  but would there be a bridge installed  on  the highway?  What would
these impacts be?

Section 5.1.8, Other Project Components - The  reference to Figure 1-1 should
be to Figure 1-2.

Section 5.3,  ALTERNATIVES AVAILABLE TO EPA - This section should indicate
the  preferred alternative.   If certain conditions (stipulations) are  to  be
attached to the permit, they also should be  indicated.  The public should
have a chance to comment on  them.

Section 6.1.3, Impacts of Project Alternatives - It would be better  to
include a  map of the proposed  postmining topography instead of referencing
a map of the existing topography.

Section 6.2.1.5, Group V - Miscellaneous Land  Types - It appears the  refer-
ence to Figure 6-6 should be Figure 6-5.

Section 6.3,  GROUND WATER RESOURCES - Leakage  through the aquitard  into the
upper Wilcox aquifers is  indicated as occurring  under existing conditions
(e.g., p.  6-33, 6-34, 6-38;  figs. 5-3, 6-4).   As dewatering of the affected
upper Wilcox aquifers progresses over the  life of the project, differences
in head between the deeper Wilcox aquifers and the upper Wilcox  aquifers
will be increased; presumably  leakage will also increase.  We suggest that
the  statement address both existing leakage  and  any changes in upward leak-
age  that may occur as a result of the project.  It would be helpful  if
current heads existing  in the  upper and  lower  aquifers were compared  in the
EIS  including a map of  the potentiometric  surface of the shallow aquifer,
inasmuch as appendices F and G are not available.  Any pertinent observa-
tions from experience in mining in similar situations would aid  in  the
assessment.  It is because  leakage from  the  lower aquifers might result in
significant impacts beyond  the project boundaries  that the potential  for
leakage during mining should be addressed.

TABLE 6-5,  GROUND-WATER SAMPLES COLLECTED  BY TUGCO - The volumes for TDS
are  suspect since they are  less than  the sum of sulfates and chlorides.
This should be checked.

Section 6.3.3.3, Reclamation - The second  paragraph should read  "Alterna-
tives 2 and 4  . . . (than  1  or 3)  .  .  .".
 U.S. Department of the Interior
 Page 2

     responsibility  allows determination of compliance with Section .384 and is one step
     toward release of an area from bonding.   Surface  mining with  draglines  typically
     results in postmining topography that is similar to the premining conditions. Major
     features such  as hills and valleys are present after mining but the general contour of
     the  land is smoother than the premining contour.  The elevation is generally a few
     feet higher after mining because of the initial volume increase (bulking) of the spoil.

 9.   EPA concurs.

10.   Present downward leakage is  minor since the only connections between upper and
     lower  sand bodies are sand channels and the deeper sands are confined by  clay and
     lignite strata. It can be seen on Figure 6-3 and 6-4 that the minor sand  channels
     (shown as a dashed  pattern on the  figures) which connect the upper  and lower sand
     bodies are discontinuous.  At no point on the cross section could a particle  of water
     move  vertically in a direct line more than about 100 feet. Vertical movement would
     be prevented by either clay (in white)  or lignite (in black on the figures) strata, or by
     both types of strata.  In several places on the figures, the small lateral extent of the
     sand bodies is apparent since a sand body of a few hundred feet in width has lignite or
     clay strata extending horizontally  from both sides.  Thus,  not  only would water
     moving vertically have to frequently move laterally  before continuing its  vertical
     movement, but the channels providing vertical connections are limited in area making
     vertical movement  more difficult.  There are numerous clay and lignite strata below
     the  upper mineable lignite seams as shown  in Figures 6-3 and 6-4.  The clay strata
     vary individually in thickness from about 2 to 20 feet.  Cumulatively they have a
     thickness of over 50 feet and extend over the entire area. Analysis  of electric logs
     taken  from the first five-year mining area  shows  that these clays are  typical of the
     low  permeability clays characteristic of the Wilcox formation.   To obtain  specific
     information regarding leakage, it would be necessary to run pumping tests with a well
     installed to the lowest lignite seam to be mined and observation  wells completed in
     the  first significant aquifer below the seam to be mined and in the shallow aquifer
     above.  If no drawdown was  detected in the lower  well, then it  would be assumed
     there  is no connection.  TUGCO  states they have not experienced problems  with
     upward leakage.  Although not shown  on a map, the current heads in the upper sand
     bodies are stated as being between 5 and 50 feet below ground level with most levels
     between 5 and 15 feet  (DEIS, pg.  6-30).  Figure 6-8 shows that  the potentiometric
     head of the deeper Wilcox sands varies from  less than 330 feet mean sea level (msl) in
     the  northwestern part of the project  area to just over 380 feet msl  in  the
     southeastern  portion.  Figures 6-3 and 6-4 show that the lignite  to be mined varies
     from about 320 feet msl to just over 380 feet msl.  Dewatering of the upper Wilcox
     sands  during  mining would  decrease the  head  to  approximately  the  top of the
     potentiometric head of the lower  sand bodies.  In  areas not containing connecting
     channels, no  leakage problems would exist.  Where mining occurs in the vicinity of
     the localized sand channels of  restricted areal extent, two possibilities exist. One, if
     the  lignite  lies  above the potentiometric head  of  the lower  sand bodies,  then
     conditions of  "no flow" would  exist and downward leakage would  cease.  Two, if the
     lignite lies below the potentiometric head of the lower sand bodies, lowering the head
     of the upper sand body would  allow upward  leakage to occur and further dewatering
     would be required.  However, because of the small head difference  (i.e., the lignite
     only a few feet below the potentiometric head) and the restricted areal extent of the
     sand channels, the  amount of additional dewatering required would be minor and the
     cone of depression  would be limited.  The possibility of impacts significantly beyond
     the project boundaries  and monitoring to determine such impacts were discussed on
     pg.  6-40 of the DEIS.

-------
Section 6.4.1.2,  Hydrologic Characteristics - The soil associations  discussed
in this section  should be correlated  to the soil groups described  in the
soils section.

Section 6.5.3,  Impacts of Project  Alternatives - It is noted  in  this section
of the E1S  that  approximately  1,136 acres of bottomland hardwoods, wetlands,
and hydric  plant communities occur in the mining blocks.  An  additional 96
acres of  floodplains and wetland plant communities would  be  impacted by
ancillary facilities construction.

The U.S.  Fish  and Wildlife Service (FWS) classifies these bottomlands and
wetlands  as  Resources Category  2,  of  high value for wildlife  evaluation
species and  scarce or becoming  scarce (FR 46(15): 7644-7663,  January 23, 1981).
To minimize  long-term losses to these diverse, productive wildlife  habitats,
we recommend "inkind replacement"  of  floodplain/wetland communities  during
the reclamation  phase of the project.  Specifically,  the  hydrologic  balance
of these  wetland areas should  be restored, appropriate wetland  vegetation
established, and management practices undertaken to promote  the long-term
recovery  of  these ecosystems.   These  practices are required  to  ensure the
biological  integrity of these  important habitats pursuant to  the surface
mining performance standards of the Texas Railroad Commission (Surface Coal
Mining Regulations, Sections 342 and  380, respectively).  We  recommend that
the final EIS  discuss more concisely  what measures will be undertaken by the
applicant to restore these impacted floodplain and wetland habitats.

Section 6.18.9,  Socioeconomics_ - The  last sentence on this page is  incomplete.

APPENDIX  B.  MEMORANDUM OF AGREEMENT

Two references  in the agreement should be changed or  noted for  future refer-
ence.  On page B-3, the correct address for the National  Architectural and
Engineering  Record (NAER) for  projects in Texas should be Chief, Division
of Cultural  Resources, National Park  Service, Rocky Mountain  Region, P. 0.
Box 25287,  Denver, Colorado 80225.

Also on page B-3, the reference to the Interagency Archeological Service
should be changed to Interagency Resources Division,  National Park  Service,
Department  of  the Interior, Washington, D.C. 20240.

APPENDIX  C.  Preliminary NPDF.S  Permit  - On August 9, 1982, the FWS provided
comments  to  EPA on the proposed draft HPDES permit for this  facility.  The
comments  recommended that the  "NPDES  permit be conditioned  to require  that
any retention  ponds, discharge  structures, etc. making up outfall 001  not be
located in  wetlands as designated  by  the Corps of Engineers," unless individ-
ual authorization is obtained  from the Corps.  We request that  Part  III of
the MPDES permit incorporate this  provision.  A comparable stipulation was
recently  included in the nearby South Hallsville Lignite  Surface Mine  mow
permit.

He hope these comments will be helpful in the preparation of the final  ETS

                                     Sincerely,
                                         .^~fr^_Jf^C-7tA>
                                      Pfeymond  P.  Churan
                                     'Regional  Environmental Officer
 U.S. Department of the Interior
 Page 3

11    The IDS values in Table 6-5 are incorrect.   The chloride and sulfate values are
     correct and are within the range in analyses of other groundwater samples from the
     area.  Apparently, incorrect calculations resulted in IDS values (shown in Table 6-5)
     which are approximately 1/10 of the real  value.  Revised  Table 6-5 in  Part III
     includes the corrected TDS values.

12   EPA concurs.

13   The Hydrologic Group  Classifications were  determined for  the  soil  associations
     designated by the SCS.   Four soil associations make up the total project area and
     contain  nine major soils. Each of the associations fall  into a different Soil Group
     (Section 6.2.1.1, Table 6-1,  DEIS) while only  two (B  and  C)  Hydrologic  Group
     Classifications are   represented.    The Kirvin-Bowie-Cuthbert  association (Soil
     Group II) and  the  Nahatchie-Mantachie association (Soil Group IV) ore  in the Hy-
     drologic Group C while  the  Nacogdoches-Trawick (Soil Group I) and Lilbert-Tenaha
     (Soil Group 111) associations are in Hydrologic Group B.

\l\   Table 1-2 has been prepared to help clear up confusion  on acreages.  Within the mine
     blocks,  1092 ac of bottomland hardwood forests (1039 ac) and hydric  communities
     (53 ac) occur.  These 1092 ac include wetlands identified by the COE.  Activities to
     occur within the mine blocks are: construction of ancillary facilities;  the Dry Creek
     diversion; construction of haul roads; and pipeline/transmission line ROW relocations.
     These activities would affect about 42 ac of wetlands as determined by the COE.  An
     additional 42 ac  would  be  affected  by  mining for a total of 84 ac  of wetlands.
     Construction of the railroad and transmission  line between the power plant and mine
     would affect  about  24  ac  of bottomland hardwood forest  and hydric communities
     (some of which might be classified as wetlands).  Mining activities would affect an
     undetermined acreage of bottomland hardwood forest  and hydric communities which
     are not wet lands.

 15   The RRC regulations  (.337-.339, .341-.347,  .384-.3B8 and .390-.396) require re-
     establishment of the hydrologic balance after mining and/or stream diversions as well
     as topsoil replacement, backfilling,  grading and revegetation of disturbed areas.  A
     major  feature of restoration  is the  re-establishment  of  the  hydrologic balance.
     Backfilling and grading  to approximate original contour is a requirement for all areas.
     TUGCO  has  not  made c  commitment  to  specific  measures which could ensure
     compliance to these regulations for these areas.

 16   The last sentence on pg. 6-171 (concluding on pg. 6-172) contains two typographic
      errors.   The sentence   should read  (typographic  errors underlined), "Two  of  the
      projects (the proposed  plant/mine in Harrison County and the Troup project) ore in
     planning stages and are  not scheduled to begin in the near future."

 17    The address has been corrected. See Part III.

 18    The address has been corrected. See Part III.

 19.   To ensure that specific plans and commitments are made for mitigation on disturbed
      designated wetlands, EPA has placed the following condition on the proposed permit:
      "There  shall be no discharge of dredge and fill material into wetlands as designated
      by the Corps of Engineers unless TUGCO submits specific plans for each wetland area
      discharge proposed,  to  the Corps of Engineers for authorization by the Corps under
      Section 404 of the Clean Water Act.

-------

                                                                                                               Response to Comments by
                                                                                                               Mr. and Mrs. Gus L. Brown
                                                                                  I.   The Texas Surface Mining  and Reclamation  Act  (the Act)  and RRC regulations
                                                                                      require that an applicant's past  performance be considered before a permit is issued.
                                                                                      The RRC determines if an applicant's records show "a demonstrated pattern of willful
                                                                                      violations  of the  Act" and,  if  so, the RRC must deny a permit  to the applicant.
                                                                                      Compliance  is partially a function of enforcement by the RRC. A list of violations at
                                                                                      TUGCO's three existing operational mining  sites, as shown in a recent application
                                                                                      submitted  to RRC for construction of the railroad loading facilities, is included in
                                                                                      Appendix B.  The monthly, self-monitoring reports required by  NPDES permits for
                                                                                      TUGCO's three existing mine sites show numerous violations of  the Total Suspended
                                                                                      Solids (TSS) discharge limits from sediment.  These were proposed to be during storm
                                                                                      events, and  not under dry weather conditions.  Recently (October  13,  1982),  EPA
                                                                                      published new rules on allowable TSS concentrations during storm  events.  The new
                                                                                      rules  do not consider  such  TSS concentrations during storm events as violations.
                                                                                      Based upon overall potential  impacts  to the "D" area  site, EPA is considering this
                                                                                      permit area as a "new source."

                                                                                  2.   The Rusk County  Tax Collector states (1983) that taxes are levied against land that
                                                                                      TUGCO owns or leases in the same manner as for  other taxpayers.   Land which is
                                                                                      being  mined will be taxed at full market  value  but not above the value of the land
                                                                                      itself.  Land which contains  improvements  (i.e., mine facilities,  railroad corridor,
                                                                                      houses, etc.) will be taxed based upon the value of the improvement.  TUGCO could
                                                                                      not qualify for homestead exemptions for residences it owns.  Other lands (not being
                                                                                      mined and not containing improvements) would be taxed either at  full market value
                                                                                      or might qualify for a lower rate  based upon productivity (i.e.,  agricultural exemp-
                                                                                      tion).   Over time  appeals  could  be made by TUGCO (as by  anyone else) for
                                                                                      reclassification  of its property and  reduction of  its tax  rate  (possibly for an
                                                                                      agricultural exemption).
(Secure  folded sheet  with tape or  glue)

-------
   THIS FORM CAN BE USL_  TO SUBMIT  COMMENTS RELATED TO mE ENVIRONMENTAL
   IMPACT STATEMENT ON THE  MARTIN LAKE  "D" AREA LIGNITE SURFACE  MINE  IN
   HENDERSON, RUSK COUNTY,  TEXAS.
fit  it
                                         a-
Mr. and Mrs. Gus L. Brown
Page 2

3.   Comment noted.

4.   Comment noted.  Address has been changed.
     Mrs. G. L. Brown
     Rt. 4, Box 281-A
     Henderson, TX  75652
  Gus L. Brovjn
  Route 4
  Henderson,  TX  75652
                MAY  5
                         1983
                   6E3
                   (Secure  folded  sheet with tape or glue)

-------
                 TtXAS-
                  ELECTRIC
SEKWECE
        COMPANY
   Response to Comment by
Texas Electric Service Company
                                                                                              I.   Comments are noted.  No response is necessary by EPA.
                                                          May 2, 1983
 Clinton  B. Spotts
 EIS Coordinator
 U.S.  Environmental Protection Agency
 1201  Elm Street
 Dallas,  Texas  75270

 Dear Mr.  Spotts:

      Texas Electric Service Company (TESCo)  appreciates the opportunity
 to  comment on the EPA's draft environmental  impact statement for Texas
 Utilities Generating Company's (TUGCo)  Martin  Lake D Area Lignite Surface
 Mine  near Henderson in Rusk County, Texas.   TESCo provides electric power
 to  78 incorporated cities and has 561,486  customers in an area of 18,500
 square miles in central and west Texas. Like  TUGCo, we are an operating
 company  in the Texas Utilities system who  is concerned with the cost of
 providing electricity to our customers.

      Lignite coal is the least expensive fuel  which TU uses to produce
 electricity.   Over 55 percent of all electric  power generated by TU is
 produced by burning lignite.  Because of lignite's low cost, we plan to
 take  full advantage by generating as much  electricity in the future with
 this  fuel.  We have reviewed the EPA's  draft EIS and it is our hope that
 the subsequent permit will  be issued so that we can begin using this
 valuable new fuel supply and avoid any  additional costs to our customers.
                                                          Sincerely,
                                                          W. Keel
                                                          Superintendent
                                                          of Power
ddb

cc:  0. R.  Robertson

-------
 United States  Environmental
 Protection Agency
 Region VI
 Dallas,  Texas  75270             5-2-83
 ref;  TUGCO impact study  for Henderson, Tx

 Your  report is inacurate  in that my water well
 is  not shown in your report.
 My  well is active .
 I know of other wells that  are  not included in
 your  report

 I do  not  believe that waste water should  be
 placed  into creeks and other water because it
will  pollute the land banks etc.
                                                                                                                            Response to Comments by
                                                                                                                               Mr. R. Allen Green
I.   EPA appreciates notification concerning wells not shown on the map.  Specific data
    on your well and others, including locations, would be helpful.  The information has
    been given to TUGCO for use in updating the water well map to be included in the
    RRC permit application.  If  TUGCO disturbs or interrupts your water  supply by
    mining activities,  RRC  regulations require  that  they  replace  that  water supply.
    Measures for replacement include drilling a new well, providing other service (for
    example, via a water supply company) or monetary compensation.

2.   Comment noted.
                      .Allen Green
                     RT 4 box 702
                     Henderson, Tx. 75652

-------
                   TEXAS UTILITIES SERVICES INC.
                      WHII IIHYAN-niWKH l>\IJ.\S.TKXAS 7r.ytll rurrfl

                            May 3, 1983
 Response to Comment by
Texas Utilities Services, Inc.
                                                                                               I.   We appreciate the letter and note the comments.
 Regional Administrator
 U.S.  Environmental Protection Agency
 Region VI
 1201  Elm Street
 Dallas, Texas  75270

 Attn: Mr.  Clinton Spotts
                                         Martin Lake Mining Area "D"
                                         Draft Environmental Impact Statement
                                         Review Comments
 Dear  Sir:

 We have reviewed  the Draft Environmental  Impact  Statement dated March 1,
 1983,  for our proposed Martin Lake Mining Area "D" project  and wish to
 provide the  following comments.

 Our review Indicates the draft EIS provides an accurate description of
 TUGCO's project plans and the need for development of  the mine.  The
 document also presents a complete and informative evaluation of the exist-
 ing environment of the project area.

 While we do not agree with several of the predictions  concerning the
 probability of occurrence and the severity of some of  the impacts, we
 believe that all  the significant environmental Impacts have been identi-
 fied.  It Is evident that the requirements of state and federal surface
 mining regulations and provisions of the  preliminary NPDES  permit will
 ensure that any potential adverse impacts are minimized or  prevented.

We are not submitting specific comments at this  time on the preliminary
 permit presented  in the DEIS.  We will comment at the  appropriate time
when a draft permit Is prepared.

Please let us know If you have any questions concerning these comments.
We are prepared to provide whatever assistance is needed from the Company
 in responding to  other EIS comments.

                                          Very truly yours.
                                          H. B. Coffmln
JRR:11

-------
                        DEPARTMENT OF THE ARMY
                     FORT WORTH DISTRICT. CORPS OF ENGINEERS
                                 P. O. BOX I73OO
                             FORT WORTH. TEXAS 76IO2
                                 April 29. 1983
Office Operations  Branch
Mr. Clinton  B.  Spotts
U.S. Environmental Protection Agency
1201 Elm Street
Dallas, Texas   75270

Dear Mr. Spotts:

     This  is in regard to the Draft Environmental  Impact Statement (DEIS) for
Martin Lake  Area  D Lignite Mine proposed by  Texas  Utilities Generating Company.
The U.S. Army Corps of Engineers (COE) working  as  a cooperating agency with
the Environmental Protection Agency has completed  a review of the DEIS.

     The DEIS adequately assesses the  impacts of the project and is correct in
regard to  COE jurisdiction and permit  requirements under Section 404 of the
Clean Water  Act.   Although the DEIS provides little mitigatory measures for
the loss of  wildlife habitat, we believe the applicant  has made a conscientious
effort to  avoid adverse impacts to wetlands  and other waters of the United States.

     Thank you  for this opportunity to comment  on  the document.  If you have any
questions  concerning this letter or our comments,  you may contact Alan Brackney
at FTS 334-4624.

                                          Sincerely,
                       Response to Comments by the
       Department of the Army, Fort Worth District Corps of Engineers
We have determined that  there  is a lack of a specific plan and commitment to
restoration of sensitive areas such as jurisdictional wetlands under Section bQb of the
Clean Water Act.

To ensure that there will be restoration of these areas that have important wildlife
habitat and water quality improvement functions, the following condition is placed on
the permit:

    There shall be no discharge of dredge and fill material into wetlands
    as designated by  the  Corps of Engineers unless  TUGCO submits
    specific plans,  for each  wetland  area  discharge proposed, to the
    Corps of Engineers for authorization by the Corps under Section 4(M
    of the Clean Water Act.
                                          Allie J.  Major
                                          Chief,  Operations Division

-------
                 THIS FORM CAN BE USED TO SUBMIT COMMENTS RELATED TO THE ENVIRONMENTAL
                 IMPACT STATEMENT ON THE MARTIN LAKE "0" AREA LIGNITE SURFACE MINE  IN
                 HENDERSON,  RUSK COUNTY, TEXAS.
                                                                                                                                            Response to Comment by
                                                                                                                                             Mr. Ervin B. Henrichs
                                                                                                                   Two parcels of your land were located within the proposed first five-year mining
                                                                                                                   area. A third parcel was not located. The location of the well noted in your letter
                                                                                                                   is unknown  based on available information.  Specific  data on your well(s) and its
                                                                                                                   location would be appreciated.  If TUGCO disturbs or interrupts your water supply
                                                                                                                   by mining activities, RRC regulations require that they replace  that water supply.
                                                                                                                   Measures for replacement include drilling a new well, providing other  service (for
                                                                                                                   example, via a water supply company) or monetary compensation.
                                                                                            Fold
i-
VQ

                                                                                           Fold
                                                             8
Address
                                                             C L / A/   /?J>
                                                                          773
                                   (Secure folded  sheet with tape or  glue)

-------
                                 T° SUBMIT COMHENTS REI-ATED TO  THE ENVIRONMENTAL

                                                "°"  *"" LIG"ITE
Cn
O
                                                                                                                                                Response to Comments by
                                                                                                                                                    Mr. R. K. Barrett
                                                                                                                      Neither the Public Utilities Commission (PUC, 1983) nor the Railroad Commission of
                                                                                                                      Texas (RRC, 1983) have regulations restricting the disposition of land owned in fee.
                                                                                                                      Disposition could include sale to private individuals. But it could also include trading
                                                                                                                      for acreage in future mining areas or sale to non-individuals (i.e., companies).

                                                                                                                      Official  monuments, such as property corner markers, highway right-of-way markers
                                                                                                                      and National Geodetic Survey (NGS) markers must be re-established. On leased land
                                                                                                                      the  original property  lines  will  be re-established  after  completion  of  mining.
                                                                                                                      TUGCO-owned  land will be  surveyed  and divided according to requirements for
                                                                                                                      disposition  of  the land.   The  original  corners  and boundaries  may  not be re-
                                                                                                                      established.  Highway right-of-way markers will be re-established when the road  is
                                                                                                                      replaced, or established in  a new  location if  the road is  relocated  by the State
                                                                                                                      Department of Highways and Public Transportation.  Any NGS  monument  which  is
                                                                                                                      disturbed would be re-established by NGS.   The quality of all surveying done in Texas
                                                                                                                      is monitored by the Texas Board of Land Surveyors under the authority of the Land
                                                                                                                      Surveying Practices Act of  1979. Surveying is monitored by registration of surveyors,
                                                                                                                      release of manuals and guidelines  to determine acceptable practices  and, in some
                                                                                                                      cases, by an investigation and a hearing in response to complaints to the Board from a
                                                                                                                      third party (or  the Board may institute proceedings on its own behalf).  See  revisions
                                                                                                                      to the text in Part III.

                                                                                                                      The comments are appreciated and revisions to page 5-18 of the DEIS are included in
                                                                                                                      Part  III.
                          (Secure  folded sheet with tape or  glue)

-------
                        TEXAS POWER & LIGHT COMPANY
                         1511 Bryan Street • P. O, Box 226331 • Dallas, Tex«s 75Zfe6
                                                                            APR  JJ9 I9M
                                                                              6ES
                                                                                                                           Response to Comment by
                                                                                                                         Texas Power & Ligjit Company
                                            April  27,  1983
                                                                                                   The  comments are noted; no response  is necessary  from EPA.
                                                                                                   appreciated.
                                                                                                                                                                        Your  letter  is
         Mr. Clinton B.  Spotts (6ESF)
         U.S. Environmental Protection Agency
         First International Building
         1201 Elm Street
         Dallas, TX 75270

         Re:  Martin Lake "D" Area Lignite Surface Mine
              Draft Environmental Impact Statement
 I
Ln
Dear Mr. Spotts:

      Texas Power & Light Company is an investor owned  public utility
serving over 750,000 customers in 51 counties of north, central, and
east Texas.  TP&L is a joint owner of the Martin Lake Steam Electric
Station and, thus, has an interest in the referenced Environmental
Impact Statement.  The Martin Lake "D" Area Lignite Surface Mine would
supply part of the fuel source required for the generation of electricity
at Martin Lake S.E.S. to meet the continued need of our customers.

      We believe that the draft EIS adequately addresses the environmental
concerns that are associated with the project and urge  the Agency to
finalize the EIS.

      We appreciate the opportunity to comment on the draft EIS and request
your consideration of our comments.

                                    Sincerely yours.
         GBerman:ln

-------
                DEPARTMENT OF HEALTH A HUMAN SERVICES
                                                                              Public Health Service
 I
l/l
NJ
       3,
                                                 lc
                                                                              Center! for Disease Control
                                                                              Atlanta GA 30333

                                                                              (404) 452-4257
                                                                              April 25,  1983
                                   .      .
Dick Whittington, P.E.
Regional  Administrator, Region VI
U.S. Environmental Protection Agency
1201 Elm  Street
Dallas, Texas  75270

Dear Mr.  Whittington:

We have reviewed the Draft  Environmental Impact  Statement for Martin Lake D
Area Lignite Surface Mine,  Henderson, Rusk County,  Texas.  We are responding
on behalf of the U.S. Public  Health Service.

The lignite  seam to be rained  is contained in  Che  shallow ground-water system.
It appears that the shallow aquifer system, particularly the upper Wilcox, is
a primary source of ground  water in the project  area.   Approximately 142 active
wells  are used for domestic and stock use.  Although the trend is shifting away
from the  upper Wilcox to use  of the deeper Wilcox aquifer, some of these wells
will be eliminated and other  wells indirectly affected  during construction.  It
is stated on page 6-47 that the "wells eliminated by mining would be compensated
for under terms of the lease  agreement."  The final statement should identify
what compensation measures  are applicable.  Specifically, what alternative water
supply would these people use if their wells  are  eliminated?

A second  concern regarding  ground water is the potential for the release of chemi-
cal constituents from the overburden into the ground water.  "Some layers of the
overburden contain concentrations of certain  constituents (e.g., pyrites) which
may cause short-term adverse  impacts . . . ." "It is  anticipated that concen-
trations  exceeding water quality standards would  be restricted to within a  few
hundred feet downgradient of  the mine" (p. 6-47).  The  identified constituents
of greatest  concern are sulfate, iron, and total  dissolved solids, all of which
pose no significant health  problems, although sulfate may act as a laxative  in
some people.  Monitoring wells are planned by the applicant.  However, since there
are numerous wells in the area,  consideration should also be given to selective
sampling  of  existing wells, and a public awareness program which would alert the
local  population to any changes in groundwater quality  or drawdown which may affect
them.

We have some concerns regarding the maintenance  of surface water quality and air
quality.   However, the Draft  EIS has addressed these potential impacts and
mitigation plans.  Proper operation and maintenance of  the proposed project  is
essential in minimizing potential insults to  the  environment.  Adequate  operator
staffing,  training, and laboratory and process controls are necessary  for  approp-
riate  quality assurances.   Standard conditions required for receiving  and main-
taining NPDES Permits should  ensure appropriate  operation and maintenance of
pollution controls.
                                                                                                                              Responses to Comments by the
                                                                                                                       Department of Health & Human Services, P>LS.
I.   The  compensation  measures applicable  to  eliminated wells are cash settlement,
    redrilling the well, or connection to a public water supply.  Which measure is selected
    depends upon the lease  agreement terms where well  loss occurs on leased lands.
    Replacement wells could be completed in the deeper Wilcox sands. Compensation by
    connection  to  a water  supply  system  could be  to one of the existing  systems
    (depending upon the property location) or to another system, if one  existed at the
    time of compensation.  Information provided by the existing systems  (New Prospect
    Water Supply Cooperative  and Crims Chapel Water Supply Company) indicate that
    sufficient capacity exists or is planned  to accommodate  additions.  Surface mining
    regulations (with RRC as the delegated authority) require compensation for affected
    wells even  if  they are  located  on land  the  applicant does not  own or lease.
    Compensation measures would be the same as for wells covered by lease agreements.
    The burden of proof for claims is on the well owner.

2.   RRC regulations (Section .350) require monitoring by the permittee to determine the
    effects of mining on ground-water quantity and quality. Section .350 states (in part)
    that  "Ground water levels, infiltration rates, subsurface flow and storage character-
    istics, and the quality  of ground water shall be monitored in a manner approved by
    the Commission, . .  ." and "Monitoring shall include measurements from a sufficient
    number of wells and mineralogical  and chemical analyses of aquifer, overburden, and
    spoil that are adequate to  reflect changes in ground water quantity and quality . . ."
    The  monitoring  program must  be  developed on a case-by-case  basis  to take into
    consideration  any site-specific  geologic or hydrological characteristics.   TUGCO
    states that, at the existing "A", "B" and "C" mining areas, most monitoring wells have
    been installed by the company.  EPA's review of water well monitoring data for areas
    "A",  "B" and "C", provided  by TUGCO, notes that the location of wells is too great a
    distance from mining  that has occurred to date to indicate water quality effects.
    TUGCO indicated that piezometers had not been installed in wells on mined areas and
    no data on water levels or water  quality analyses exist.

    No structured, on-going  "public  awareness program" is conducted by EPA,  RRC or
    other agency. To date, the public  has been made aware of general and some specific
    project details during  the NEPA process.  This includes the  Public Scoping Meeting,
    DEIS and the Public Hearing on the DEIS and will continue with the FEIS and Record
    of Decision.  During the RRC permitting process, TUGCO must publish notice of its
    application  in local newspapers and file a copy of  the application for public  review.
    Within 45 days of the last publication of the Notice  of Application, the applicant or a
    member of the  public may request a Public  Hearing.  During this time,  the RRC
    may, on its own motion, call a hearing.  The RRC  must publish notice of any Public
    Hearing in local newspapers, accept  input from the public, and publish a summary of
    its decision in a newspaper or similar periodical of  general circulation in the  general
    area  of proposed  operation.  The RRC also  must provide  a complete copy of  its
    decision to  each person or agency who filed a written objection or comment to the
    application.   During  mining operations  the public may become aware of  project
    details.  Upon  request to the  EPA and RRC, the enforcement  files, monitoring
    reports and  other non-confidential data are  available to  the public.  In addition,
    Section .221 of the RRC  regulations  require that the permittee must notify any
    person  whose health and safety is in imminent danger due to a non-compliance on the
    part  of the permittee. According to the RRC (1983)  to date no instance  where a

-------
    Page 2 - Dick Whittington, P.E.

    Thank you for the  opportunity to review  this  draft document.  We would  appreciate
    receiving a copy of  the Final EIS when it  becomes available.  If you  should have
    questions regarding  our comments, please contact Mr. Ken Holt at (404)  452-4163
    or FTS 236-4163.

                                    Sincerely yours,
Department of Health & Human Services, P.H.S.
Page 2

    permittee has needed to notify the public of imminent danger has occurred in Texas.
    Instances  have  occurred in  mountainous regions  of eastern  Kentucky  and West
    Virginia in relation to unsafe dams constructed from mine refuse.

3.  EPA concurs regarding concerns for maintenance of surface water quality. Adequate
    enforcement procedures apparently are necessary to approach appropriate operation
    and  maintenance  of pollution  controls.   Violations of  surface  water discharge
    limitations have occurred at mining areas "A", "B" and "C".
                                    Frank S. Lisella,  Ph.D.
                                    Chief, Environmental Affairs Group
                                    Environmental  Health Service Division
                                    Center for Environmental Health
 I
tn
CO

-------
   _^y\xJbe,
RIVER  flOTHOBin
            of/---'   b
                                                                                   27  1933
                                                                                   ES
                                                                    F* O BOX 579


                                                                       77G3O
                                             April 23,  1983
                                                                                                                      Response to Comments by the
                                                                                                                         Sobine River Authority
                                                                                                          Based on further evaluation of information  available  to  us, EPA has placed  a
                                                                                                          provision on the draft NPDES permit (see Appendix A) for long term monitoring at
                                                                                                          three stations to establish ambient water quality baseline and to measure effects of
                                                                                                          the mine project.
          Mr.  Clinton B. Spotts
          Regional  EIS Coordinator
          Environmental Protection Agency
          Region VI
          1201 Elm  Street
          Dallas, TX  75270
Ln
    2.
 Dear Mr. Spotts:

 We are writing in reference to the Draft Environmental Impact Statement
 (EIS) on the Martin Lake "D" Area Lignite Surface Mine Project proposed
 near Henderson, in Rusk County,  Texas by the  Texas Utilities Generating
 Company.  The following comments are offered  for your consideration.

 As we stated in our comments on  the Preliminary Draft EIS, the Authority
 owns and operates Toledo Bend Reservoir  jointly with the Sabine River
 Authority, State of Louisiana.   As a result,  we are primarily concerned
 with any potential impacts on water quality in principal tributaries,
 the main-stem Sabine River and the downstream headwaters of Toledo Bend
 Reservoir.

 The draft EIS discusses a number of potential impacts that lignite mining
 could have on surface receiving  waters,  and concludes that the effluent
 limitations and the constituents to be monitored provide the necessary
 protection for the area receiving streams.  However, it appears to us
 that there is a need for monitoring of Mill Creek, Tiawicki Creek, and
 Lake Cherokee in order to document the effectiveness of the discharge
monitoring program presented in  the draft EIS.

There are two major areas of general concern which we would like to
 address.  First,  a significant area of the Sabine Basin upstream from
 Toledo Bend Reservoir,  a major drinking  water supply reservoir, is
affected by existing and proposed lignite mining operations and their
associated steam  electric stations.  We  believe increased water quality
monitoring is needed for the principal tributaries affected by mining
activities,  the main-stem Sabine River and the headwaters of Toledo Bend

-------
    s
mm DIVER RUTHORITY
          page  2
Sabine River Authority
Page 2

2.   We  concur.  Any further  studies should be coordinated with Texas Department of
    Water Resources and Sabine River Authority.  See Part III, B for revisions to impacts
    on water resources.
     z.
      Reservoir in order to assure that  this  drinking water supply reservoir
      is not affected by any potential cumulative impact from all the mining
      projects.  Second, appropriate studies  should be conducted and any necessary
      action taken in order to assure that mining and reclamation activities
      do not reduce the firm yield of downstream water supply reservoirs.

      We would like to thank you for this opportunity to present our comments
      on the draft EIS.

                                          Sincerely,
                                               Ja^k W.  Tatum
                                            	Development Coordinator
Ln
Cn
          JWT:njb

-------
                                     25  (983
                                                                                                                                           Response to Comments by
                                                                                                                                                 Mr. Bill Snow
                                                        ?cC.  £  TV?.
                                                       /7 "> J^fro-* ,
//f
r     f*
                                        .Ls     //,     E.lS.    f.r
z.
             *~,ji^. -**^    .   .

            A'/     "^     (7~*'^
The EIS will be revised to state that regardless of the final vegetative cover, a high
degree of management  would be required  for  the initial period.  For  revegetation
with woody species, a cover crop must be established to prevent erosion early in the
process.  Once established, forested land requires little management.

The use  of a percentage range (10 to 50 percent) for reforestation is  vague.  This
represents the TUGCO commitment. It is unknown whether this will be acceptable to
the RRC. For any given acre of land the vegetative cover to be established may be
based upon factors such as:  suitability of the land  (e.g., steep slopes near water
courses may be most  suitable to woody  species); adjacent vegetative cover (e.g., a
small  area of grassland partially surrounded by woody species may  be  most  appro-
priate  for mitigation  of wildlife habitat loss);  desires of the land owner (e.g., lease
conditions may specify  the vegetative  cover); or regulatory restrictions of the RRC
(e.g.,  reclamation  to a  pasture in a previously  wooded area, which was not used for
grazing, may represent a land use change).  TUGCO's  practices in reforestation at the
"A", "B" and "C" areas have increased each year  (during the past three years)  and
reforestation areas presently amount to approximately  13 percent of the total area
disturbed to date.
           v>-«»

-------
                                /,
^/-y   y«J   ;y
   A-/    •> / c//.
                    *•« /     fi>?e7

                   /*/"   
-------
                       '          /
                        «J -c    ,  (f  -  ItO
tn
00
Mr. Bill Snow
Page 3

5.  The percentage range for  revegetation to pasture and woody species represents the
    commitment made at this time by TUGCO.

6.  The emissions from  the  crusher were  calculated  from information in the source
    document (EPA, I977a) listed at the bottom of Table 6-20.  This document states that
    primary  crushers release emissions at a  rate of  0.02  Ib per  ton of western coal
    crushed.  Lignite, since it  contains more moisture than  western coal, would release
    emissions at a  lower  rate  but actual emission rates for lignite are not available.
    TUGCO states that they will mine (and crush) 3.5 million tons of lignite per year (pp.
    5-19, DEIS).   The  crusher would  release  35 tons  of emissions per  year under
    uncontrolled conditions (0.02  Ib/ton x 3.5 million  tons/year x  1/2000 Ib/ton).   The
    crusher emissions will be  controlled by water sprays (Table 6-20, DEIS) which are
    rated as 50  percent efficient (i.e., reduce the emissions  to one-half the  uncontrolled
    amount).   Thus, the  actual  yearly emissions are calculated  as 18 tons/year (35
    tons/year x 0.5  = 17.5 tons/year). The TACB, in  a letter dated March  8,  1983 (see
    Appendix B), has exempted the facility from the TACB permit procedures "because it
    will not make a significant contribution of air contaminants  to  the atmosphere . . ."
    According to the level of significance used by TACB, this  means that the fugitive
    emissions will add less than I  microgram (1/1,000,000 grams) per cubic  meter of air
    for the annual average and less than 5 micrograms per cubic meter of air for the 2A
    hour average.  No  dust problems from  crusher emissions are expected beyond the
    permit boundary nor at the nearest residences.  See revisions  to the text in Part III.

1.  The analyses for construction and operational noise levels are conducted on "worst-
    case" conditions (pp. 6-129 and 6-131)  to assess the impacts. It is unknown whether
    the  worst-case  conditions would occur;  the noise  experienced may be lower than
    projected.  The construction  activities  and many operational  activities are short-
    term.  The only significant operational impact would be in the community of Oak Hill
    when mining occurred at the edge of the  nearest pit. This also would be a short-term
    adverse  impact.  Operations  near  the edge of the nearest pit would occur for 24
    hr/day for about a  one week period four to  five times per  year over a  one and one
    half (Ife)  year period.  That is, the worst-case conditions might occur about seven to
    eight times  for one week periods. Possible mitigation measures include berms to act
    as noise barriers. TUGCO has not committed to specific mitigation measures.

-------
           .
                 C-ur
.          r-J'-"*-  A

  * "         /v~«
                                                                              Mr. Bill Snow
                                                                              Page 4

                                                                              8.   The figure for 1979 lumber production on pp. 6-139 is incorrect. The proper figure
                                                                                  for pine is 50,469 thousand board feet (i.e., 50,469,000 board ft). The figure for ties
                                                                                  is correct but it was not made clear that there were only 2,053 pine ties produced.
                                                                                  Total cross-tie production was 71,291 of which 69,238 were hardwood ties. The unit
                                                                                  of time associated  is one year (i.e., 1979, the most recent year for which data were
                                                                                  available during production of the DEIS). The source for the data was the Texas
                                                                                  Forest Service (1980).
7U     C.
 'fck,
                                                 
-------
         f^<  .
         0^
                              '
               o         .  ~

                -^.^-»-!,    , i r*» ^      c

            f     7*   /    ^J"*"     7
           > /."i


         '//  '*/cr*J7/  ^/    cr/
                                       IS \t^f ^
                                         y   x /  •

                                        C/7/C
O\
O
Mr. Bill Snow
Page 5


9.  The information on agricultural uses and commercial forest acreage was taken from
   reports prepared by the U.S. Department of Commerce (I98IW, the East Texas
   Council of Governments (1977) and Earles (1976).

-------
SIERRA
      CLUB
LONE STAR CHAPTER

601U Woodbrook
Houston, TX 7?:X>8
Ap. 21, 198?
     Clinton Spoils,  Reg. EIS Coordinator
     U... E.P.A.
     1201 Elm  St.
     Dallas. TX 75270

     Re: Draft Environmental Impact St=te-nent
         Martin Lake  "D" Area Lignite Surface Mine Project

          We are  concerned about proposed  reclamation method-alternative
     number  one.   This method will admittedly adversly effect soil ph,
     Increase  acid runoff to contaminate surface and  ground water and
     adversely effect the "primary ofjective of  revegetation operations
        to establish an enduring self propagating and  ecologically
     sound vegetative cover..."  It seems  that the Texas R.R.C.  definition
     of prime  farm land undervalues the long term land productivity
     value by  using farming history as a criteria. The protection of
     the long  term land productivity resource must be the chief concern
     of any land  reclamation project.
          Wo propose  that all 26,291 a. of U.S.Soil  and Conservation
     Service classified prime farmlands be protected  by Alternative four •
     methods of mining and reclamation.  V.'e recommend that topsoil be
     placed over  oxidized spoil in these U.S.S.C.S. prime farmlands.
          Special  care should be taken to  avoid  contamination ofx ground
     water.  The applicant should monitor  grcundwater at several sites
     around the area  to assure water quality.
          Thank you for this opportunity to respond.

                                           Yours_ truly,
Response to Comments by the
Sierra Club, Lane Star Chapter
                                                          I.  Comment noted.

                                                          2.  Comment noted.

                                                          3.  The  total  acreage of  Soil  Conservation  Service  (SCS) prime  farmland  soils
                                                             within the project  boundary  is  8,365 ac  with  6,152  oc occurring within  the
                                                             mining  blocks.   Of  the  prime farmland soil  acreage within  mining  blocks,
                                                             some 920 ac  is  luka fine sandy loam,  which  is associated  with  flood plains
                                                             of streams.   Most of  the  luko fine sandy loam  will  not be disturbed since
                                                             mining  will not  occur  in the  flood plain  of streams, except  for  the  Dry
                                                             Creek  diversion,  which will  disturb  about  30 ac  of  luka  fine  sandy  loam.
                                                             Construction  of  the  railroad and  transmission line  could  affect  76  oc  of
                                                             prime  farmland  soils  outside  the   mining  blocks.    It  is  estimated  that
                                                             mining   activities  (including   haul   roads,   facilities,   railroad  and  trans-
                                                             mission  line) could disturb about 5,340 ac (6,152  ac - 920  ac +  30 ac +  76
                                                             ac) of prime farmland soils.

                                                          4.  Comment noted.
                                           George Smith
                                           Conservation Chair
"When we try to pick out anything by itself, wr find it hitched to everything else in the universe." John Muir

-------
                                                  RUSK COUNTY
                                                  Chamber of Commerce
                                                            2M-657-S528 *  201 NORTH MAIN
                                                              HENDERSON, TEXAS 75652
                                                                   April 12, 1983
                                                                                                                      Response to Comment by
                                                                                                                 Rusk County Chamber of Commerce
                                                                                                          The comments  are  noted.  We  encourage you  to  be  interested in the natural
                                                                                                          environment as the project may proceed through additional permitting, construction
                                                                                                          and operation.
ON
tsj
Mr. Clinton Spotts
U. S. Environmental  Protection Agency
1201 Elm Street
Dallas,  Texas  75207

Dear Mr. Spotts:

In response to your  request  for comments on the Environmental Impact
Statement for the Martin  Lake D Area Lignite Surface  Mine, the Board
of Directors would like to go on record In support  of the project.

We are aware that there will be short and long term beneficial
Impacts to the local economy resulting from wages,  land purchases,
royalties and capital expenditures from the project.

Our people recognize that any large mining project  will have some
environmental impacts.  At the same time your document has done a
good job of identifying those Impacts and the procedures that will
be used to insure that there will be no major environmental effects.
Texas Utilities Generating Company has established  a  good reclamation
program at Its mines In Panola County, and we expect  that they will
conduct a similarly  beneficial environmental protection program at
the new nine in Rusk County.
           Sincerely,
           B. G. Davis
           President

           BGD/db
                                                              APR

-------
CO
                                                                         501 Sautk M.in
                                                                     HENDERSON. TEXAS
                                                                                 75652
                                                                        APR £0 IS
                                                                          6ES

                                    HOWARD-DICKINSON HOUSE -US5
                                          Restored 1f<7

          Mr. Clinton  B.  Spotts,  Regional EIS Coordinator
          U.S.Environmental  Protection Agency
          1201 Elm  Street
          Dallas, Texas,  75270
                                                   April 16, 1983
          Dear Mr.  Spotts:
                                       RE:  ENVIRONMENTAL  IMPACT  STATEMENT
                                            MARTIN LAKE D AREA
                                            LIGNITE SURFACE MINE
                                            HENDERSON, RUSK COUNTY,  TEXAS
                                                                   (Draft)
The abstract on page  2,  Mr.  Myron 0. Knudsen, for Mr. Dick Whlttlngton,
P.E. Regional Administrator, is enough to scare the daylights out of us,
when It comes to environmental change generally and archaeological and
historic sites In particular.   And Table 1-J, doesn't help much;  for Instance
page 1-7 ARCHAEOLOGICAL  AND  HISTORIC RESOURCES:  "Adverse effect has been
determined on Walling Cabin, but minimized by re-location to Henderson  ...."
Minimized Is right  and we are glad to gat the cabin, but how come we weren't
given a chance to transfer some of the bulbs and ancient shrubs  and plantings
around that cabin?  The  place was awash with blooms - and the ancient Bois  d'Arc
tree near the road  -  not in  the way of anything - could have been left  there.
It may well have been the larges Bois d'Arc tree In Texas, but it went  down
within hours - bull-dozed and burned.  What was the hurry?  Nothing has been
done there since.

Now as to 41RK86 -  THE TOWN  OF MILLVILLE.  Se surely want that site disturbed
as little as possible, if at all.  Before and for some time after the 1850's
Millvllle was a flourishing  town, and an important one In Rusk County.  There
were at least five  Mills there - Tannery, Grist Mills, Cotton Gin, etc.   I  know
of my own knowledge that at  least one of the Mills was owned by  the Galloway
Family, and one of  the Grist Mills was owned by Col. Jesse Walltng.  Dr. O. L.
Sure, besides his medical practice, owned a Drug Store there in  which the U.S.
Post Office was located.  There were numerous other businesses  Hotel,  Stage
Coach  Way Station, Churches and Schools.

We have numerous old  Ledgers and accounts of life in Millville,  and with the
exception of Gen. Sam Houston, It would be hard to find two more colorful
characters that old Col. Jesse and Dr. Burt.
                                                                                                                            Response to Comments by
                                                                                                                         Rusk County Heritage Association


                                                                                                    EPA is also concerned regarding the disturbance and loss of the Walling Cabin site
                                                                                                    shortly after archeological work was carried out.  Oral  assurance had been given to
                                                                                                    EPA that work on the railroad corridor would begin at the power plant site and that it
                                                                                                    would be months before the cabin site would be reached;  adequate time was expected
                                                                                                    to receive the  Archaeologists reports and  determine survey completeness and site
                                                                                                    eligibility.   At  that time it was  believed unnecessary  to provide  direction  to  the
                                                                                                    applicant.

-------
                       Page 2 - Spotts
          We  are told thatthe Mlllvllle site will  not be mined for ten years  Yet.
     7-.   So  tltlt  We DO NOT want that site mined at all.  It is Important  to
          Rusk County.

          ABOUT 41RK87 - THE MONTGOMERY HOUSE.   This house was a beautifully  built
          and decorated house,  the scene of much entertaining in Its day.  Whoever Is
     3-   responsible for the bull-dozing of the site did a dis-servlce  to This County.
          The House itself could  have been saved years ago If we had had the  money or/and
          the  cooperation of the family.  We had  neither.

          41RK128 THE JOHN VINSON SR., house -  still standing but in a sad state of
          delapldatlon.  Though an affluent man, his house did not reflect it.

          THE RICHARD B. TUTT PLANTATION - so far  as we know, Richard B.  Tutt and his
          family never lived on the plantation,  but built and operated THE WHITE TAVERN
          in  Henderson, Texas.

          THE RICHARD MAGEE PLANTATION - Part of this lies within the prospective
          mining zone.  There was a large plantation house, cotton gin  ,  plus other
          usual plantation structures here.  I  have personally seen  (many years ago)
          some of the foundation  for the main house, a rather large excavation - perhaps
          t cellar, other evidences of structures.  Bulbs cover the slope where the
          house was in the springtime, and many brambles from an evidently extensive
          planting of roses.  The saga of Richard  Magee is an interesting one: from
          Plantation owner, early Conmlssloner  of  Rusk County, to part owner  and Captain
          of  a Steamboat called THE GENERAL RUSK,  built by Rusk County men to ply the
          waters of the Sabine  River.

ON        All of these sites should be marked,  and some of them qualify  for  the National
          Register of Historic  places.

          There are many archaeological sites:   41RK82 Bottom land wast  side  of Mlllvllle;
          41RK83 - north of the confluence of Mill and Dogwood Creeks;   41RK106 East Bank
          of  Mill Creek at FM 782 and 42-RK109,  West of 106 above knoll  overlooking Mill
          Creek, to name a few.  These should all  be checked out thoroughly  before being
          irretrievably lost.

          We  are not ANTI-Progress;  we ARE Pro-Conservationists - from  Historical sites
          to  Flora and Fauna, to  the fullest extent possible.

                                          Very truly yours,

                                          RUSK COUNTY HERITAGE ASSOCIATION
                                          RUSK CWKTY HJSWRICAkJCOMMISSION

                                          BY:
                                                                Rusk County Heritage Association
                                                                Page 2

                                                                2.   Regarding 4IRK86 - The Town of Millville. The information is appreciated and points
                                                                    further to significance of the area.

                                                                    EPA, instead of requiring identification and determination of eligibility and appro-
                                                                    priate mitigation on all sites over the entire project area before any permit action,
                                                                    entered into an agreement with the Texas State Historic Preservation Officer and the
                                                                    Advisory  Council  on  Historic Preservation  (which  has responsibility  to  see  that
                                                                    agencies  carry  out consultation on  cultural resources according  to  the  National
                                                                    Historic Preservation Act) so this could be done over the 30-year period of mining,
                                                                    one permit area  at a time.

                                                                3.   4IRK87.  While the structure  is lost and much of the area has been disturbed, (see
                                                                    Part III) by gravel mining and other activities, the applicant has been informed that
                                                                    the area  is considered to  have  high  probability for discovery  of  resources during
                                                                    mining activities.

                                                                t\.   4IRKI28.  Effects of mining and mitigation to John Vinson, Sr., house and site would
                                                                    be  addressed by the applicant about the year 2005.  However, as noted in  our response
                                                                    to  the  Rusk County  Historic Commission,  other  interested parties such as  that
                                                                    Commission or Rusk County Heritage Association could pursue a determination of
                                                                    eligibility and/or nomination to the National Register of Historic Places, so that the
                                                                    importance could become known earlier. This is also true for the other known sites.

                                                                5.   EPA encourages you to be familiar with cultural resources protection requirements of
                                                                    agencies that  may  have permit actions in this county so that you  may continue to
                                                                    assist, in all permit actions, with public input and to help ensure agency and  applicant
                                                                    compliance. We have forwarded a copy of the federal regulations  EPA should comply
                                                                    with  regarding  cultural resources.  Under the National Environmental Policy  Act,
                                                                    EPA should ensure, before permitting, that a project meets all state and local laws;
                                                                    to  do so requires public input.

                                                                    In  addition, you  are encouraged to follow actions by federal and state agencies which
                                                                    propose changes to their  requirements from  time to time.  (Federal regulations and
                                                                    changes are printed in the Federal Register).  Industry, as a regular work  practice,
                                                                    provides  comments to  agencies on  regulations.   It  may  be  beneficial to  the
                                                                    environment for you to review and provide comments that promote  your interests as
                                                                    well.
                                                                    The Association  comments are sincerely  appreciated.
                                                                    information of the Draft EIS in Part III of this Final EIS.
                                                                                                                          Please  note  revisions  to
             Carl
          rltage
Member of  the  Commission
                                                                            ecretary

-------

                                                                      APR
                                                 MAX H. TANNER, JR.
                                                 VICE PRESIDENT
                                                April  19,  1983
6ES
                                                                                                                                     Response to Comment by
                                                                                                                                   Dallas Power & Light Company
                                                                                                          I.  Comments are noted.  No response is necessary by EPA.
          Mr.  Clinton  B.  Spotts  (6ESF)
          U.S.  Environmental  Protection  Agency
          First International  Building
          1201  Elm  Street
          Dallas, TX   75270
                           Martin  Lake "D" Area Lignite Surface Mine
                           Draft  Environmental  Impact Statement (EIS)

           Dear  Mr.  Spotts:

           Dallas  Power  6  Light Company owns and operates production, transmission, and
           distribution  facilities  to serve a population of approximately one million
           within  Dallas County,  Texas.  As part of the Texas Utilities Company System,
           DPsL  is a joint owner  of the Martin Lake Steam Electric Station with the
           Company's share of electrical output from the station distributed to customers
           within  the Company's  service area.  The Company has an Interest in the draft
OS         EIS and the proposed operation of the Martin Lake "D" Area mine because of
           the  increasing  importance of lignite as a fuel resource.

           The Company believes  that the draft EIS adequately addresses all environmental
           issues  associated  with the project and urges the Agency to accept the document
           as  fulfilling the  needs  for which it was developed.  The cost of fuel for the
           Company's gas fueled generation continues to escalate.  Lignite fuel has proven
           to  be a valuable stabilizing influence in our overall fuel cost.  With the
           continued and expanded use of lignite fuel, our Company is meeting the energy
           needs of  our  customers at the most reasonable price.

           We  appreciate the  opportunity to provide comments on and to support the adoption
           of  this document.

                                                Yours very truly,
                DALLAS POWER & LIGHT COMPANY • 1506 COMMERCE STREET • DALLAS. TEXAS 75201 (214) 698-7000

-------
xJSj\  United Stales
IflAJ})  Department of
\3B^  Agriculture
ON
ON
   Soil
,-. rConservation
H Service
                                               t.  0.  Box 648
                                               Temple,  TX
                                             ' 76503
                                                                   April 14, 1983
         Mr.  Dick Whittington,  P.E.
         Regional Administrator
         U.S.  Environmental  Protection Agency
         1201  Elm Street
         Dallas, TX 75270

         Dear  Mr. Whittington:

         We have reviewed  the Draft Environmental Impact Statement  (EIS) on the
         Martin Lake "D" Area Lignite Surface Mine Project proposed near Henderson,
         Rusk  County, Texas  and have no comments for improvement.   The comments
         we made in January  1983 have been Included in this draft.

         Thank you for the opportunity to review this EIS.

         Sincerely,
                                                                                                                                          Response to Comment by the
                                                                                                                             U.S. Department of Agriculture; Soil Conservation Service
                                                                                                            I.   Your letter is appreciated and your comments noted.
     'State  Conservad-foiTist

      cc:  Audrey Baker, AC,  SCS,  Nacogdoches
          The Soil Conservation Service
          is an agency ol the
          Department of Agriculture

-------
                        (Ettg of jJbnbe

                             400 JBesl (flHahi
                        jMcnttcrean, QTexaa 75652

                             April 14, 1983
Mr. Clinton Spotts
U. S. Environmental Protection Agency
1201 Elm St.
Dallas, Texas           75207

Dear Mr. Spotts:

We have reviewed the draft Environmental  Impact Statement for the
TUOCO proposed new Martin Lake "D" Area Lignite Mine.  We found it
very interesting and informative as to the environmental conditions
that will result to the City of Henderson because of this mining
operation.  It appears that the planning  and study  that has been made
will result in a successful operation for the area.

In reviewing the environmental concerns and effects upon the environ-
ment of the City of Henderson and its citizens, we  conclude that the
project is in the best interests of all concerned.  It appears that the
environmental impacts will not adversely  affect the City of Henderson
in its operations and will be a contributing factor for the orderly
growth and development of the City of Henderson.

In conclusion, we would recommend to EPA  that a National Pollution
Discharge Elimination System Permit be issued to Texas Utilities Generating
Co. for the project.
                             Sincerely
                             /Jack Dickerson
                              City Manager
JD:cka
   Response to Comment by
City of Henderson, City Manager
                                                                                                    The comment  letter is appreciated and comments are noted. We encourage you to
                                                                                                    continue to be interested in the natural environment as the project proceeds through
                                                                                                    additional permitting, construction and operation.

-------
                          DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT
                                    FORT WORTH REGIONAL OFFICE
                                           P.O. BOX 3905

                                      FORT WORTH, TEXAS 70113
CD
           April 14,  1983

           Mr.  Clinton B. Spotts
           Regional EIS Coordinator
           Region 6
           U.S.  Environmental Protection Agency
           1201 Elm Street
           Dallas,  TX  75270
                                             "twl
                                                 APR  15  1983
                                                    6ES
Dear Mr. Spotts:

     The Draft Environmental Impact Statement for the Martin Lake D

Area Lignite Surface Mine near Henderson in Rusk County, Texas, has

been reviewed in the Department of Housing and Urban Development's

Dallas Area Office and Fort Worth Regional Office, and it has been

determined that the subject document adequately addresses this

Department's special areas of environmental concern.

                              Sincerely,
                                                                                                                                  Response to Comment by the
                                                                                                                         U.S. Deportment of Housing ond Urbon Development


                                                                                                         I.  The comment letter is appreciated and comments are noted.

-------
                                                                                                           Response to Comments by
                                                                                                            Floyd ond Betty Holcomb
                                                                               I.   The area near  the Oak Hill Community is planned to be mined after  the year 2005
                                                                                   (see Fig. 1-2, DEIS).   Present plans do not call for mining the land on which the
                                                                                   community  itself is located.  More details based upon the exact location of your
                                                                                   property may be obtained by contacting the TUGCO land office in Henderson.
 Name -f.-

 Address
(Secure folded  sheet with tape or  glue)
APR  15  '983

   6ES

-------
                            Wildlife  Managementlnstitute
                                      .    ,1  ii ,, "i. '(•• O
                            709 Wire Building; 1000 Vermont Ave., N.W.. Washington, D.C. 20005 •
                                                                                202 /347-1774
                                              EPA
                                             -
       DANIEL A. POOIE
       Pr«/denf
       I. R. |AHN
       V»ce-fV«'denf
       L. L WHIIAMSON
       Sefretary
       |ACK S. PARKER
       Board Chairman
                                    | f ICt"
                                                                Murny T. Wallon
                                                                Southcentral Representative
                                                                Star Route 1A, Box 30C
                                                                Dripping Springs, Texas 7B620
                                                                512-825-3475
                                               April 7, 1983
 I
^1
O
2.
3.
                                                                      APR  14 1985

                                                                         6ES
Mr. Dick Whlttington,  Regional Administrator
U.S. Environmental Protection Agancy
1201 Elm Street
Dallas, Texas   75270

Dear Mr. Whittlngton:

     The Wildlife Management Institute has  reviewed  the Draft Environmental
Impact Statement for Martin Lake D Area Lignite Surface Mine, Henderson,
Rusk County, Texas.  The proposed action will  disrupt approximately 15,000
acres including  approximately 300 acres of  wetlands  and aquatic habitats
and over 1,000 acres of bottomland hardwood forest.

     The Institute favors topsoll replacement  (alternative 2) for overburden
handling,  especially for all prime farmlands.   We also favor the proposed
revegetation alternative of pasture and woodland,  bu"t we recommend that
additional native species be used.  The Institute does not find, however, that
the proposed actions are sufficient to mitigate wildlife losses.  To further
mitigate such  losses, we recommend that TUGCO  make all suitable portions of
Its 5,460  acres  of fee lands In the project area available to the Texas Parks
and Wildlife Department for Wildlife Management Area purposes upon the comple-
tion of mining and reclamation.

     Thank you for the opportunity to comment  on this document.
                                                                                                                                   Response to Comments by the
                                                                                                                                   Wildlife Management Institute
I.   Within the  mine blocks, 1,092 ac of bottomland hardwood forests (1,039 ac)  and
    hydric communities (53 ac) occur. These 1,092 ac include wetlands identified by the
    COE.  Activities to occur are:  construction of ancillary facilities; the Dry Creek
    diversion; construction of haul roads; pipeline/transmission line ROW relocations; and
    mining.  These activities would affect about 8^ ac of wetlands as determined by the
    COE within  the mine blocks.   Construction of the railroad and transmission  line
    between the power plant and mine (outside the mine blocks) would affect about 2b ac
    of bottomland hardwood forest and hydric communities (some of which  might be
    classified  as  wetlands) (see   Table  Ill-l).    Mining   activites  would affect  an
    undetermined acreage of bottomland hardwood forest and hydric communities which
    are not wetlands.  A  100-ft. buffer between mining activities and a stream is stated
    by mining regulations, although approval to mine more closely to streams can be
    obtained. In the case of the Dry Creek diversion proposed by TUGCO, it is  presently
    unknown how the buffer  requirement will  be applied.

2.   Comment noted.

3.   Comment noted.

k.   EPA has informed TUGCO of  the mechanism to  donate or  lease land to the Texas
    Parks and Wildlife Department (TPWD) for wildlife management purposes.   Decisions
    by TPWD to accept or reject  such offers  are made on  a case-by-case basis.  Some
    considerations  in making such  decisions are suitability of the land for management
    purposes, need for the additional  acreage  and availability (long- and short-term) of
    funding needed to develop and/or maintain the land.  The disposition to make any land
    available to TPWD would remain with TUGCO.

Your letter is sincerely appreciated. Thank you for the information on wildlife habitat
impact mitigation.
                                               Sincerely,
                                                Mufray T.  tfalt
                                                Southcent/a]/Representative
                                  DEDICATED TO WILDLIFE SINCE 1911

-------
DONALD R. ROSS
  Judic 4ih Judicial Dtmt
LINDA J. CARItOLL
  Reporter 4th Judicial Dut,
JAMES B. PORTER
  County Judge
TALMADOE MERCER
  Co. CoRifnlinlomr. Pet. 1
HAROLD KUYKCNDALL
  Co. Commtuioncr, Pet. X
DAN D1CKESON
  CO. ComralMloner. Pet. 3
KENNETH 11. ASHBY

HELEN SILLICK
  County Cter*
MIKE STRONG
  County Sheriff
TOMMY IIASK1NS. JR.
  Co. T« ArsMcorOrileclor
WM. H. FERGUSON
  County Atu>rn«r
PAT ENDSLET
  Dlitrlcl Clwk
RUSK  COUNTY

     HENDERSON, TEXAS
            75652
vmdtl, COLE
  County Tr«	
OnAVES II. BPIVET
  County Auditor
AMIEKT H. EVANS. JH
  County Superintendent
STEVE COTTOELL
  County Ubrarlan
JEFF JONES
  County Scrvlc* Ofrinr
STELUA SWANN
  Co WvUirc Worker
TOMMY McDANIEL
  County ABCTIt
WILLIAM H. BROWN
  Criminal InTMtlpitor
JON H. JOHNSTON
  Probation officer
  Response to Comment by
James B. Porter, County Judge
                                                                      I.   We appreciate your letter and note your comments.
           April 12,  1983
           Mr. Clinton B. Spotts
           Regional  Administrator
           U.S. Environmental  Protection Agency
           1201 Elm  Street
           Dallas, TX 75270

           Re:  Rusk County  Area D Lignite Mine

           Dear Mr.  Spotts:

           I  am writing with regard  to the letter dated April  10, 1983,
           from Ms.  Virginia Knapp,  Chairman  of the Rusk County  Histo-
           rical Commission.

           At this point, I  have not received enough  input all around
           to take any particular position.   The point  of this letter
           is to state that  Ms.  Knapp and the members of this  commission
           are all well respected and very practical minded people in
           our County.  Their  concern for the protection of the  environ-
           ment is admirable and I wanted you to know that I have found
           myself always in  agreement with her.

           Thank you for your  courtesies in this matter.

           Sincerely,
                     B.
  On.
          James B.  Porter
          CO|u|ity Judge
             j
          nk
                         APR  13
                                 1983
                                                        6ES

-------
                                         RFC
        ENERAL SAVINGS
            ASSOCIATION
April 11, 1983
                                                             P. O. BOX 250 • S. MAIN AT HWY. TO
                                                                  HENDERSON, TEXAS 7M52
                                                                                                                            Response to Comment by
                                                                                                                           General Savings Association
                                                                                                    The  comments are noted.  We encourage you to  continue with an interest in the
                                                                                                    natural environment as specific planning and additional permitting may proceed.
Mr. Dick Whittington, P.E.
Regional Administrator
United States Environmental Protection Agency
Region VI
1201 Elm Street
Dallas, Texas 75270

Dear Mr. Whittington:

I have recently reviewed your Environmental Impact Statement  on  the
Martin Lake "D" Area Lignite Surface Mine Project proposed  near  Henderson,
Rusk County, Texas.

At this point, please allow the following comments:

     A.  Previous mining operations in the area have  had  positive
         impacts on our local economy by providing jobs and a
         source of new cash to land owners.
     B.  Inspection of mining operations and reclaimed land does
         not, in my opinion, have an overall negative Impact.
     C.  Area "D" should be similar In final reclamation  as other
         areas in Panola/Rusk County due to the consistency of
         operation for which Texas Utilities Generating Company  is
         noted.
     D.  The new citizens who have Joined the community in  associ-
         ation with the project have been of highest  quality.

We encourage your agency to issue a favorable decision concerning the
necessary permits and/or permission to proceed as proposed  In the report.

The short term as well as long-term impact of this project  certainly has
more positive end results than negative end results  In our  opinion.

Sincerely,
Mark R. Hale
President
MRH:lsa

-------
        DEPARTMENT OF TRANSPORTATION
        FEDERAL AVIATION ADMINISTRATION^ . ,  , r  ,--,
LO
                                                        SOUTHWEST REGION
                                                        P. Q, BOX 1«B«
                                                   v
                                             ct Statement  - Martin Lake  D Area
April 8, 1983
                          fcl
ASW-43A

INFORMATION:  Environmental
Lignite Surface Mine,  Hendersqp'j|iRuBk County, Texas

Manager, Budget and Planning Branch, ASW-43

Mr. Dick Whittlngton,  P.  E.                        ^_p=rv •"  ~~ * " "" ^ iFi
Regional Administrator
U. S. Environmental Protection Agency
Region VI                                                  j^H  >\  133'
1201 Elm Street
Dallas, Texas 75270                                          r fT^

Dear Sir:

We have reviewed  the subject draft environmental impact  statement  and

find no interference with existing or planned FAA facilities/airports.

Thank you  for the opportunity to comment.
             E. B. McCoy
             cc:
             OST P-37, N. Cooper
             FtW OST Rep, J. Abby
                 Response to Comment by the
U.S. Department of Transportation, Federal Aviation Administration
                                                                                                            I.  The comment letter is appreciated and comment noted.

-------
                                                                                                                                       Response to Comment by
                                                                                                                                       Preston ond Lodie Gibson
                                                April 8, 1983
                                                                                                    Comments are noted.   We encourage you to continue an interest in the  natural
                                                                                                    environment  in  the  mine area as  the  project may proceed through additional
                                                                                                    permitting, construction and operation.
-J
-P-
Mr. Clinton Spotts
U.S. Environmental  Protection  Agency
1201 Elm Street
Dallas, TX  75207

Dear Mr. Spotts:

This is in response to your  request for comments  on  the  Martin  Lake
"D" Area Lignite Mine proposed by  Texas Utilities Generating  Company.
As landowners in "D" Area, we  have a strong  interest In  the economy
and well being of Rusk County.   We believe  this  project  will  be good
for the people of Henderson  and surrounding  areas.

We have reviewed the Environmental  Impact Statement.  We believe the
project will be good for  the overall  economy of  the  area.   It will
be large enough to  provide increased employment opportunities and
significant tax revenue to Rusk County  and Henderson ISO.

It seems that all the potential  environmental  impacts  have been well
identified in the document and  procedures will be followed to minimize
the environmental effects.

We are in favor of  development  of  the project and request that  a permit
be issued.

                                     Sincerely,
                                                Preston Gibson
                                                V7 J
                                              CT&LSf*'
                                                Lunie Gibson
            /da

-------
                                           RUSK COUNTY
                                   HISTORICAL COMMISSION
RUSK COUNTY HISTORY BOOK

      COMMITTEE

     Miss Virginia Knapp
      Central Chairman

      Mrs. Maid* Jaggers
 Topical & General History Chairman

     Mrs. Mary Frank Dunn
   Field Representative Chairman

      Mrj. Gene Lmeter
     Publicity Chairman
      Mrs. Susan Weaver
         Artitl

     Miss Ruth Kirkham
      Editorial Chairman

 RUSK COUNTY HISTORICAL

   COMMISSION MEMBERS

     Miss Virginia Knapp


      Mr. Cecil Williims
         Tatum

      Mrs. Maida Jaggenj
        Henderson

     Mrs. Margaret Brown
        Henderson

     Mrs. Gene Lasseter
        Henderson

      Mrs. Nita Byrd     ,
        Henderson       I

      Mrs. Bertha Camp
        Henderson

      Mr. Homer BrycB
        Henderson

      Mr. Reuban Ellis
        Henderson

     Dr  Dorman Winfrey
         Austin

     Mrs Dorothy Hunter
        Henderson

      Mr. James Porter
     Judge of Rusk County
     Mrs Bettye Streeter
        Overton

     Mrs Belly Jo Walker
        Monroe       ^..

      Miss Mary Craig
        Henderson

     Mrs. Pud Patterson
        Henderson
      Dr. J. W. Griffith
        Henderson

     Mrs. Mabel Blackwell
        Henderson
                                          April 10,  1985
Mr. Clinton B.  Spotts
Regional Administrator
U.S.  Environmental Protection Agency
1201  Elm Street
Dallas,  Tx. 75270

Dear  Mr. Spotts:

      As  chairman  of the Rusk County Historical Cora-
mission, I wish to make some comments  on both the
Environmental  Impact Statement of the  Martin Lake
Area  D Lignite  Surface Mine, Henderson,  Rusk County,
Texas and to add  to it some  comments on  the findings
in the same area  by Jack Jackson and Henry Moncure
of the Texas Archeological Survey Commission.at
Austin.

      In the last  twenty years Rusk County has just
begun to uncover  its past history.  Prior to the
1960's only six historical sites had been located
by interested  persons of the county.   Since 1960
there have been a total of forty-eight historical
markings and four more are in the process of being
approved for markers.

      While the  coming of Texas Utilities Company and
its surveys have  helped speed the findings of this
140-year-old county, it has  also jeopardized some
of the preservation and investigations of the sites
within its mining areas.

      The T.J.  Walling Log Cabin was a  special find,
and we are grateful for its  recovery and the chance
to preserve it.   Progress is being made  in the
restoration of  the cabin with the help of Texas
Utilities and  the Archeological team that discovered
it.   With all  the Texas Utilities good intentions,
the site of the Walling Cabin was cleared, bulldozed,
and leveled the day after the archeologists finished
their excavations.  No chance was given  to either
the Rusk County Historical Commission  or the archeol-
ogists to return  to the site for more  work.  We of
the Historical  Commission wanted to retrieve the
bulbs and other plantings to use around  the cabin
in its new location.  On the Monday following the
archeologists  work, we of the Commission returned
to the site only  to find the immense Bois-d'arc
tree,  the flowers, and bulbs all flattened and in
a pile	burning.  No work was started on that part
of the rail line  until the first of the  year.
                                                                                       Response to Comments by the
                                                                                     Rusk County Historical Commission
                                                                                         I.   Comments are noted.

                                                                                        2.   The matter  of the  clearing and grading of the T. J. Walling Cabin site is also of
                                                                                            concern to EPA.  While the cabin structure had been determined eligible  for the
                                                                                            National Register of Historic Places, a determination of eligibility of the cabin site
                                                                                            was pending on completion and review of the archeological investigations.  A
                                                                                            summary of  findings at the site is now included in Part III.
                  P.O. BOX 1773, HENDERSON. TEXAS 75652 -  (214) 657-7B3 2>Z.6/

-------
I
-J
ON
                                                                     Page  2
            We are also concerned about  the bulldozing of  site
      41RK87-The Montgomery  House.  Although TUGCO officially
      denies  any responsibility of this distruction, local observers
3.    put  the blame  on them.   The site  could have provided us with
      artifacts and  knowledge  to add  to our county history.  B.F.
      Montgomery was a very  important settler  in our early history
      and  his many descendents would  have profited from the
      investigation.

            If this is what is  to be expected of TUGCO, we of the
      Historical Commission  are concerned about the other sites
 A.    listed  for possible investigation.  I speak specifically of
      pre-historic sites 41RK82, 41RK83, 41RK106, and particularly
      41RK109.  The  findings  there may  be far  more significant than
      preliminary investigations show.
            In addition to the  pre-historic sites, the historic site
      of 41RK86-Millvil!fe Town  site can  and does play a great part in
      our  history.   Although  the Millville site is located in an
      area that will not be  mined for ten years, we are interested
      in its  preservation both as a National Historic Site and
      possibly as a  preservation open to the public for viewing.

            Two plantations,  the Richard Tutt and John Vinson, Sr. ,
      are  either within the  project area or bounded by the project
      area.   These two are our concern, and we are wanting to make
      plans for the  marking  of these  sites.

            Both Henry Moncure  and Jack  Jackson of the Texas Archeological
      Survey  Commission have  been extremely helpful to the Rusk County
      Historical Commission.   They have offered advice and help
      particularly in the recovery of the Walling Log Cabin.

            Ms. Jeangne Peckham of the Evironmental Protection Agency
      has  spent much time and  effort  learning  about our county and
      our  historical work and  plans.   She has  covered on  foot, with
      me and  other Commission  members,  many miles of Rusk County in
      order to prepare herself for her  report  to the EPA.  She has
      sought  our advice and  our help  in locating many sites within
      this mining area.  Her report on  the "Archaeological and
      Historical Resources"  is fair,  competent and shows  her
      understanding  of our county and its history.

            We intend to report to EPA if these sites are  not examined
      by competent investigators and  if cooperation with  the Rusk
      County  Historical Commission is not sought     This is our
      duty and responsibility  to the  County Commissioners Court,
      Judge James Porter and the people of Rusk County.

           We thank  you for  the opportunity to comment on the Impact
      Statement.
                                                                        ommission
Rusk County Historical Commission
Page 2

3.   4IRK87 - The Montgomery House and site is also of concern to EPA.  The applicant
    was informed at a meeting in Austin, November 30,  1982, that the area is considered
    to have high probability for discovery of cultural resources during any clearing and
    mining activities.

4.   4IRK82 and 4IRK83 are  to be investigated further in the  future by Texas Utilities
    under the Memorandum of Agreement (MOA) before any ground disturbance in the
    mine permit area. Regarding 4IRKI06,  I09, 110, and 11 I sites; the sites should not
    be disturbed by mining or  relocation of the SWEPCO transmission line according to a
    map, recently submitted, of the transmission line route.  See Fig. I-2B.

5.   Under stipulations of the  MOA on cultural resources and permit provisions, TUGCO
    would be  required to provide an intensive survey  of the  area before any ground
    disturbance  in the permit area.  4IRK86 has been  recommended as eligible to the
    National Register of Historic Places by the archeologists in the reconnaissance report
    of  I960.   Mitigative measures, including the  possibility  of  avoidance, would  be
    determined in accordance  with stipulations of the MOA.  However, prior to that time,
    interested parties such as the Rusk County Historical Commission can take measures,
    in conjunction with  the  Texas  State Historic Preservation Officer  at the Texas
    Historic Commission (a State agency) to obtain a determination of eligibility to the
    National Register of Historic Places.  If eligible, the  nomination  to the National
    Register could be carried out; this effort  would include  notification  and concurrence
    of the landowners.

6.   A site  number, 4IRKI28, has been  assigned the Vinson plantation.  While under the
    present MOA, the applicant TUGCO would not be required to address the areas for
    some time.  The County Historic  Commission or other interested party could proceed
    earlier as described above on the plantations noted, to obtain a final determination of
    eligibility.  4IRKI28 has been determined potentially eligible by the Texas SHPO and
    EPA.

Please note the comment letter  of the Texas  Historical  Commission and revisions to the
text of the EIS.

The comments  are sincerely  appreciated.  We propose  to the Rusk County Historical
Commission that where there are other permit or grant actions  in Rusk County, that you
become involved very early in the process.
                                             Rusk

-------
THIS FORM CAN BE USED TO  SUBMIT COMMENTS RELATED TO THE  ENVIRONMENTAL
IMPACT STATEMENT ON THE MARTIN LAKE "0"  AREA LIGNITE SURFACE MINE IN
HENDERSON. RUSK COUNTY, TEXAS.
                                                   Response to Comment by
                                                       Prentiss L. Irwin
                                                                                                The Irwin Cemetery was not included on project maps. The cemetery (see Fig. I-2A)
                                                                                                has been located and the archaeologists notified regarding inclusion of the cemetery
                                                                                                as an historic site in the project reports on cultural resources.  The applicant has
                                                                                                been notified of the site, and if mining occurs in the area, the cemetery is to be
                                                                                                avoided.  The following site number has been assigned by the Texas  Archeological
                                                                                                Research Laboratory: 4 IRK 130. (Site numbers are interpreted as follows: 41 = Texas,
                                                                                                RK = Rusk County, 130 = specific site number in the county.) Additional information
                                                                                                has been included in Part III of the final EIS.
       M£^J ^sC*>*~	 -   ,
       -*-       */jzk~  M^i^i« i/ <*«-'•  ~"
-------
                   HENDERSON INDEPENDENT SCHOOL DISTRICT
                            P.O. >OX 7JB           314 SSI.gSll
                                HENDERSON, TEXAS 75532
                                                                                                                     Response to Comment by
                                                                                                               (Henderson Independent School District
                                  March 25, 1983
                                                                                              Comments are noted.  We encourage you to continue to follow the project through its
                                                                                              mine permitting process, and construction and operation, as well os enforcement of
                                                                                              requirements.
»»J
CO
Mr. Clinton Spotts
United States Environmental  Protection Agency
1201 Elm Street
Dallas, Texas      75207

Dear Mr.  Spotts:

After studying the draft copy of  the Environmental Impact Statement
issued in connection with Texas Utilities Generating Company's proposed
0 Area near Henderson, I wish to  express my appreciation for the opportunity
to comment.

I found the report to be very informative about  the mine and environmental
conditions of the area, as well as the expected  economic impact. As super-
intendent of the Henderson Independent School District, within whose boun-
daries Area D lies, I see no reason why the project should pose any threat
to property or people.  On the contrary, TUGCO's plans for restoration of
land productivity and beauty should be beneficial.

In addition, the project will have a positive economic impact on Henderson
town and  the school district. The long term project should blend in well
with  the expected population growth of the county, and the added tax
revenues  it will provide will also be beneficial.  From personal obser-
vation of the mine areas in  our neighboring county, and from personal know-
ledge of  good citizenship qualities displayed by TUGCO staff people, I fail
to understand why an element of fear should be expressed.

I support the issuance of a  permit as soon as possible, and again, I thank
you for allowing me to tell  you how we feel about the question.
          Very truly yours,
                                                                   ^^^s
                                                                      VlM<
                                                                          2ft
                                                                             \°>&
                                                                         6^S

-------
  CRAIG A Tips
2B24 DANIEL COURT
^J
VO
                                                                                                                                                 Response to Comments by
                                                                                                                                                     Mr. Craig A. Tips
                                                                                                                    I.   EPA has sent a copy  of Figure 1-2 from  the  Draft  EIS with the location of the
                                                                                                                        property in question imposed on it.

-------
C.   THE FEIS AND RECORD OF DECISION

This FEIS was prepared after consideration  of  comments received on  the DEIS, re-
evaluation of some  analyses and to afford the inclusion of additional information.  The
FEIS is divkled into four (4) parts in the main body and has two (2) appendices attached.
Approximately  100  copies  were distributed: to agencies, organizations  and  individuals
commenting on the DEIS; to those requesting copies and to three  (3) depositories  in the
project area. The Notice of Availability of the FEIS appeared in the Federal Register and
included an announcement of a 30-day public review period during which comments will be
received from agencies, organizations and members of the public.

After the comment  period ends,  EPA will consider public impact and  make a  decision
concerning the  issuance of an NPDES permit.  A Record of Decision will be issued to the
mailing list.

Any permit  would be issued simultaneously and would  become  effective 30  days after
issuance.
                                      11-80

-------
                                     PART III.
MODIFICATIONS AND CORRECTIONS TO THE DRAFT EIS

-------
PART 111   MODIFICATIONS AND CORRECTIONS TO THE DRAFT EIS

Modifications and corrections to the Draft Environmental Impact Statement  (DEIS)
as a result of re-evaluations by EPA or because of comments or information from
agencies or  individuals  are presented  in  this section.    Modifications to  the
SUMMARY (DEIS, Chapter  1.0)  are not included  in Part  III since the entire summary
has been updated and is included in Part I of  this document.  Revisions to Chapter
7.0 (COORDINATION)  of  the DEIS  are  included in Part II  CONSULTATION AND
COORDINATION.

Revisions  are  located  by  Section,  page number  and paragraph and sometimes  line
numbers.  Reference to a paragraph means either a full or partial paragraph; number
one on  a  page is the  first full or  partial paragraph and the  last paragraph may be
either full  or  partial.  Line number  is determined  from the top of  the  paragraph.
Major and minor revisions are addressed in order, by DEIS page number.

A.         REVISIONS  TO  CHAPTER 5.0-DESCRIPTION AND  EVALUATION OF
           ALTERNATIVES

Section  5.1   ALTERNATIVES AVAILABLE TO THE APPLICANT

Page 5-1, paragraph 3, an error in the range of BTU per Ib of coal is corrected:

Western coal  is a  low-sulfur (less than 0.8 Ib SO^ per  million  BTU),  medium-BTU
(8,300 to 10,500 BTU per Ib) coal,  which  is available in  adequate supply and can be
used as  a fuel in an environmentally  acceptable manner.

Page 5-4, paragraph 4, the  following is added to clarify the  route of the railroad
from MLSES to the mine facilities area and the roads to be crossed by the railroad.

The selected route  requires  six (6) road crossings, none  of which are at grade (i.e.,
the train will  cross either over or  under the road).   All  state and county approvals
have been obtained  for these crossings (see Appendix B).   The  following  roads will be
affected:

                                       Distance from Railroad      Type of Crossing
                                          Origin in MLSES         (railroad over or
        Road                        	(miles)	       under road)

        FM2685                                0.7                 Over
        Unnamed County Road                    2.6                 Under
        Unnamed County Road                    5.0                 Under
        Unnamed County Road                    6.9                 Over
        SH43                                   8.2                 Over
        FM 1716                               10.2                 Over


Page 5-6, paragraph 3, the correct reference on mining equipment is:

(Bucyrus-Erie,  1982; Mattern, 1979; Price et al.,  1973)

Page 5-11.  The section on comparison  of overburden handling alternatives should be
revised to include the following statements:

-------
Regarding  alternatives 2 and 4-surface mining  regulations prohibit excess  compac-
tion  when  topsoil  is  redistributed  (Section  .337); therefore, this would not  be a
limiting factor as previously indicated in selection of either alternative.

Page 5-13,  paragraph 3, add the following to the section on Pasture and Woodland;

The  final  vegetative  cover  for  any given acre  of  land would  be  determined based
upon factors such as: suitability  of the land (e.g.,  steep  slopes near  water  courses
may be  most suitable to woody species); adjacent  vegetative  cover  (e.g.,  a small
area of grassland partially surrounded  by  woody  species may be  most appropriate);
desires of  the  land  owner (e.g., lease conditions  may specify the vegetative cover);
or regulatory restrictions of the RRC  (e.g.,  planting woody species may  represent a
land use change).

Page 5-13.  Forest.   Delete  the first  three sentences regarding level of management,
expense,   difficulty  of  accomplishment  and   commercial   value  to  landowners
attributed  to reforestation as an alternative for revegetation.

Page 5-16.  Comparison of Alternatives for Revegetation and Reclamation.

Upon  re-evaluation   of  the  alternatives  considered  for  revegetation  based  on
information  provided  by Texas Forest  Service,  Soil  Conservation  Service  and
individuals, the alternative  for reforestation  may  meet criteria for  success,  local
need   and  conditions,  wildlife  habitat and  management  costs  as  easily as  an
alternative for combination of pasture and woodland.

Page 5-17, paragraph 5:  The  figure  showing  the general  sequence of  mine blocks
should be correctly  identified as Fig.   1-2.  The figure is included in this document as
Fig. I-1.

Page 5-18, paragraph 2,  add the following information to describe how boundary and
other markers are re-established after mining;

Official  monuments, such as property  corner markers, highway right-of-way  markers
and National Geodetic Survey (NGS) markers must be re-established.  On  leased  land
the  original property lines  will be   re-established.   TUGCO-owned  land  will be
surveyed  according  to  requirements   for  disposition and  all  original corners  and
boundaries  may not  be  re-established.   Highway   right-of-way  markers and  NGS
monuments would be re-established  by the State Department of  Highways and Public
Transportation   and  the  National  Geodetic  Survey,  respectively.   Other surveying
would  be done  by TUGCO.  All surveying in  Texas is monitored by the Texas Board
of Land Surveyors under the authority of the Land Surveying Practices Act  of  1979.
Surveying  is monitored  by registration  of  surveyors,   release  of   manuals  and
guidelines  to determine acceptable  practices and, in some  cases, by an investigation
and hearing in  response to complaints  to the Board  from a third party (or the Board
may institute proceedings on  its own behalf).

Page 5-25, loading station revisions are  shown  on Fig.  Ill-1.

Section 5.2 ALTERNATIVES PROPOSED BY APPLICANT

Page 5-18,  lignite and ash characteristics are shown in a summary  table (Table 111-2).

Page 5-26, paragraph I,  add the following additional information concerning the FM
782 relocation:
                                         1-2

-------
The  relocations are planned to obtain  lignite  which lies beneath the present rights-
of-way.  About a 4-mile portion of FM  782 in the southern part of  the project area
would  be diverted  approximately  1,500 ft to the  east  onto land  reclaimed  after
mining.  It would tie into the existing road  through gentle curves (i.e., no right-angle
corners).   No  agreements have  been  established  between TUGCO and the  State
Department  of Highways  and  Public  Transportation  for  the proposed  FM  782
relocation.
B.            REVISIONS TO CHAPTER 6.0--ENVIRONMENTAL CONSEQUENCES OF
              ALTERNATIVES

Section 6.2  SOILS AND PRIME FARMLAND

Page  6-15, paragraph  6, the  reference  regarding Miscellaneous Land  Types  was
incorrect and should read:

Because miscellaneous  land  types occur in small  scattered acres,  this group could
not be shown at the map  scale presented in Fig. 6-5 but is shown  in Fig.  6-6  as  Map
Unit 21.

Page  6-17, paragraph  I,  estimated acreage of  prime farmland soil to be lost by  the
Dry Creek diversion was incorrect and should read:

A 2,000-foot  stretch of  Dry  Creek  is  planned to be diverted for  mining a lignite
seam  beneath  the  present  channel  during  the first five years.  Approximately 30
acres of prime farmland soils affected by the diversion are addressed in Sec. 6.2.3.4.

Page  6-18, paragraph 2, more detailed  information  shows that  the acreage disturbed
by ancillary  facilities  construction  would be  greater  than originally  estimated and
should read:

The  construction  of the ancillary  facilities  would disturb  about  210   acres,  the
railroad about  273  and  the  transmission line  about   114  acres.    The  SWEPCO
transmission  line  relocation  and  proposed  TUGCO 138  kv  line within the  same
corridor would disturb about  100 acres.  The  activities would  constitute a long-term
adverse  impact on  a  total  of  about   697  acres where reclamation  would  not be
initiated for  at least  30  years.   Of  these  approximately  226 acres  are  prime
farmland soils.

The same total acreage  applies to the entire discussion on page 6-18.

Page  6-18,  paragraph  5, Characterization of  Overburden.   Physical and chemical
data from  the five  cores is  provided in Appendix  B.  TUGCO proposes  these  cores
are acceptable to  RRC as representative of the first five-year  mine area.  The five
cores do not characterize  the entire project mine area.

Page  6-19,  Table 6-2, to  provide  additional  data on  the calculation  of  average
potential acidity in each core with  Alternative  I.   Mixed Spoil, footnote  I  should
read.

Tons of CaCO-j needed per acre  to neutralize  a  six-inch layer  of soil.  The average
potential acidify in each of  the five cores  for Alternative I  was calculated as:  Core
No. 972, 0.0;  Core No. 1128,  1.5; Core no. 964,  8.3; Core  No. 1009,  21.3; and Core
No. 562, 27.5.   See Fig. 6-2 for the  location  of the cores.  The  calculations can be
made  in the following manner, using data for core hole //I 128:

                                       111-3

-------
Segment
No.
5-1
5-2
5-3
5-4
5-5
5-6
5-7
TOTAL
(A)
Thickness
(ft)
11.8
16.2
12.0
7.0
1.3
3.3
9.8
(B)
Neutralization
Potential
-0.53
5.00
1.25
-0.95
0
2.73
3.80
(C)
% Total
Sulfur
0.31
0.31
0.31
0.31
23.4
11.3
14.7
(D)
B-C3
-0.84
4.69
0.94
-1.26
-23.40
-8.57
-10.90
(E)
AxD4
-9.91
75.98
11.28
-8.82
-30.42
-28.28
-106.82
-96. 995
The measure of residual bases in the soil expressed as tons of CaCO^ per 1,000 tons
material.  A negative number means the soil is acidic.

The  measure  of  pyritic sulfur (acidity)  expressed  as tons of CaCOg per 1,000 tons
material.
The acidity of each core segment calculated by substracting acidity value from residual
base value. A negative number indicates potential acidity.

The weighted average acidity of each core segment calculated by multiplying the acidity
times the segment length.  A negative number indicates potential acidity.

The arithmetic total of weighted average acidity of each segment.  The negative sign
indicates potential acidity.
Then the average acidity of a hypothetical random mixture of the core can be calculated
by dividing the total  weighted average acidity (-96.99) by the length of the core (64.1
feet).  The resulting  number (1.5) expresses the potential acidity of such a mixture in
terms of tons of CaCCX, per 1,000 tons of material.

Page 6-20.   Alternative  I.  With  the use  of lime to neutralize acid, reburial of the
acidic surface layers and/or covering  the area  with  topsoil, impacts from  excess
acidity  and release of heavy metals are reversible on a relative  short term for  each
individual occurrence.   As pointed  out  in  other sections,  acid forming materials
oxidize  at  varying rates  and  as  this  alternative has  greatest  potential  for  such
material to occur at  or near the surface (as  the layers just above  the lignite are  last
removed  from a  pit and placed on  the adjacent open pit, then smoothed out) the
impacts  may occur over  a long period of  time  where maintenance of vegetation
after bond  release may  be  less  and  breaks  down  to re-expose surface.  Adverse
impacts would result from low fertility, little  or  no  organic matter, little or  no soil
microbial population, lack of surface structure and surface  crusting.  These would be
expected  to  be  reversed as  fertilizer  is  applied   and vegetation  re-established,
however, the short term, one to two years, is withdrawn from the prediction.

Page 6-25,  paragraph 2,  since  the estimate of  the total  area  to  be disturbed by
construction  of  the  ancillary facilities has increased, the  area  of prime  farmland
soils to be disturbed also has increased and lines 2 and  3 should read:
                                        111-4

-------
Construction of  the  ancillary facilities,  railroad spur and  transmission  lines would
require  disturbing a total  of approximately 226  acres of prime  farmland soils.   As
much as 140 acres of prime farmland soils might be disturbed by construction of  the
ancillary facilities area.

Page 6-25,  paragraph 3 also  should  address  the revised  total acreage  of disturbed
prime farmland soils;

The  disturbance  of 226  acres is  considered  a  long-term adverse impact to prime
farmland  soils.   This impact  is irreversible  (therefore significant) for a presently
unknown portion of the 226 acres.

Page 6-26,  paragraph  I, should contain  the  corrected estimate of  luka  soil to be
disturbed;

Approximately 30 acres of  luka soil  would be disturbed by the temporary diversion
of a  2,000-foot section of Dry Creek.

Page 6-26,  Revise  discussions on mining regulations on soil.   Mining regulations
require  use of topsoil on all areas.

RRC designated  prime farmlands would  require  selective  handling  of several layers.
To propose  an alternative without  use of topsoil, for any area, requires obtaining a
variance from RRC.   To selectively handle  a layer (such  as  topsoil)  or a type of
material  (such  as oxidized  material)   need  not  mean  stockpiling—but  could  be
accomplished  by  a  combination  of  machinery  such as  bucket-wheel  excavators,
conveyors and draglines.

Page 6-27, paragraph 3, the information on pyrites should be revised to read:

Pyrite can vary significantly in particle  size and  physical  form.  It  has been  found in
at least six different  forms in coal deposits.   The most  reactive form  is  framboidal
pyrite  which  has  particles  less  than  0.0004  inches in diameter.    The  rate  of
breakdown (oxidation) of pyrite is not constant over  time and  may depend upon pH,
the  amount  of  oxygen present,  the presence  of  breakdown  products  and other
factors. The  addition of lime, to  raise the pH, tends to slow down the  breakdown of
pyrite.   The addition  of lime to control pH  during  early reclamation  efforts could
actually extend the period of time  over which lime is needed.  The  low  pH caused by
the  breakdown of pyrite has an adverse effect  on  the growth of most  plants  and
interferes with successful reclamation.   In addition  to the  direct  effects on plants,
low  soil pH also increases  the rate of release of  certain heavy metals  (copper,
nickel,  zinc, manganese or iron) causing the amount  of these metals  in soil  to reach
a  level  which  is toxic to plants.  This causes  further  problems  with reclamation and
revegetation.   The RRC regulations  call  for the  successful  revegetation of mined
lands and establish a  period  of  extended responsibility  (during which the  land is
under bond)  for  the  permittee to demonstrate successful  reclamation.    No such
protection  exists to  guarantee control   of pH and  metals  after  reclaimed  land is
released from bond.

Page 6-28, paragraph  I, the discussion  of  fertilizer and lime requirements should be
revised  to include the following statements:

Although  given as data from 1981,  the  figures  are proposed  by TUGCO as  the
requirements from year two  through five of reclamation.   No reclaimed  mine land in
                                        1-5

-------
Texas  has  been released  from bond  and fertilizer  and lime requirements over time
cannot yet  be determined.

Section 6.3  GROUND-WATER RESOURCES

Page  6-30.  Existing  Environment.  The Draft EIS states that groundwater  in  the
shallow system  (Carrizo  and upper  Wilcox)  occurs under  water table (unconfined)
conditions.  It should be added that this  is on part  of  the area; however, on some of
the project area, artesian  conditions exist as demonstrated by on-site  pump  test
data.

Page  6-30, Paragraph  I.  Regarding  water wells.   It has come  to our attention  that
other water wells occur in  the project area  which  are not shown  on the Draft  EIS
Map,  Fig.  6-7.  See the comment  letters, including Mr. Green's letter and Mr.   and
Mrs.  Gus  Brown's  statement,  pointing  out  wells that are   not  included.    The
information has  been  passed on  to  TUGCO  for addition  to project plans and  for
complete  presentation in any mine permit application for  determination of settle-
ment on wells affected (Final EIS, Part II).

Page  6-33.   Regarding ground  water  recharge  and  movement.   The  question  of
leakage can only  be  determined  on the basis  of  appropriate  pumping test   and
observation well data with  wells  completed to the  depth  of  the  lignite seam  and
wells completed  in the first significant aquifer below  the lignite seam to be mined.
Dr. Mathewson  has described the  reference cited as a generic  study  and states  the
need for more site specific data exists (Telecommunication, August, 1983).

Page  6-37, Table  6-5 included  data on TDS concentrations   that were incorrect,
information now provided is:

                      Sample                                 TDS
                      Location	(mg/l)
                      Pump Well                              240
                      Test Pit                                 140

Page  6-39, paragraph  2,  line 17 included reference to the  incorrect alternative  and
should read:

Alternatives 3 and 4 would result  in two layers (oxidized and unoxidized zones) with
permeabilities reflecting the  percentage  of sand, silt  and clay  in those  layers prior
to mixing.

Page  6-39.  Impacts of Project Alternatives  on Groundwater.  Regarding  impacts on
the public  water  supply wells  and  other wells completed in the  deeper Wilcox
aquifer—note  that  if  depressurization  of the deeper  Wilcox   is   not  required  for
mining and there is no connection  between that aquifer and the upper aquifer, then
reduction  of water levels in the  lower Wilcox,  or of production  from the wells is  not
expected.   There are numerous clay and  lignite strata  between  the lignite to  be
mined and  the lower Wilcox as shown in Figures 6-3 and 6-4. The clay strata vary in
thickness  from about 2 to  20 feet.  Cumulatively  they have a  thickness  of over 50
feet and extend over the entire  area.  Analysis of  electric  logs taken from  the first
five-year  mining area shows that  these clays are  typical  of   the  low permeability
clays characteristic of the  Wilcox formation.  The clays  should  provide a barrier
separating  the upper and lower Wilcox aquifers.
                                        1-6

-------
Page 6-39, paragraph 2. Corrections to predicted effects should be added.

The proposed alternative  I  (mixed spoil)  and Alternative 2  (topsail over spoil) would
significantly  disrupt the aquifer system  extending for a long-term after recharge is
complete.  Alternatives 3 and 4 which  include  handling of two  layers (oxidized and
unoxidized) of  materials would  provide some aquifer rebuilding—and could be further
refined to selective handling of Carrizo sands and of Wilcox materials.

Page 6-39.  Section 6.3.3.2  Dewatering, the area of influence on water levels by the
dewatering that occurs from mining alone and  by well pumping (to ensure highwall
stability)  has been re-evaluated.  Evaluation was based on  the Theis non-equilibrium
equation using  Selected Hand-Held  Calculator Codes for  the Evaluation  of Cumula-
tive Strip-Mining  Impacts  on Groundwater  Resources, prepared for  the  Office  of
Surface Mining (Prickett  and Voorhees,   1981).   Transmissivities  used were the high,
low, and  average  transmissivities from  the  pumping test  data  provided  by TUGCO.
Storage coefficients of 0.01 (water  table conditions) and  0.0001  (artesian  conditions)
were used.  Dewatering of a pit 5,000 feet long  was  simulated by evaluating a line  of
pumping wells.  Pumpage  was adjusted  to cause 150  feet  of  drawdown at the line
sink.   The line sink model  more closely  approaches  conditions that  will occur during
mining operations—as  actual  dewatering  would  be expected as  a lineal sink, in the
form of wells or seepage into the mine.   The water level  drawdowns at distances  of
3,800,  10,000 and 15,000 feet from center  of line sink were calculated:

                             Drawdown Due to Line Sink
   Storage
Coefficient
Transmissivity
   (gpd/ft)
       Distance (ft)
Perpendicular from Center
       of Line Sink
 Draw--
down  '
  (ft)
Artesian Conditions
.0001                     6,712
.0001
.0001
.01
.01
    14,296
    20,952
Water Table Conditions
.01                       6,712
    14,296
    20,952
           3,800
          10,000
          15,000
           3,800
          10,000
          15,000
           3,800
          10,000
          15,000

           3,800
          10,000
          15,000
           3,800
          10,000
          15,000
           3,800
          10,000
          15,000
   108
    85
    75
   109
    88
    79
   113
    92
    82

    80
    43
    28
    86
    53
    38
    92
    59
    44
                                        1-7

-------
These calculations assumed complete saturation of  ISO feet overburden.  For saturated
  overburden of less than 150 feet use:
         Thickness of saturated overburden
                       150
X  Calculated drawdown = Drawdown
  Drawdown would be affected (i.e., it could be less) by varying subsurface conditions in
  the  horizontal  dimension;  information available  to EPA  is  not adequate to  fully
  determine these conditions.


  The  3,800 feet radius of influence distance to zero drawdown stated in the Draft EIS  could
  not be verified using any of the transmissivity figures stated in the DEIS (from  literature
  on the region or from site data) and is withdrawn. (The radius of influence distance in the
  DEIS also was based on  150 feet drawndown at the sink.)  Subsurface conditions  likely are
  different in  other areas of the project, therefore, other site-specific tests and data are
  needed to estimate effects under different conditions.

  Should  Texas Utilities  carry out additional  studies to examine the varying subsurface
  conditions at the site, it  is  desirable  that  the studies  obtain  data from  appropriately
  located and installed test wells—and that pumping test data based on pumpage of at least
  a week's duration be utilized. It is desirable that such a study  be planned and coordinated
  with TDWR  and EPA;  both agencies are  interested in  accurate information on impacts
  from the specific project as well as the addition of information to the State's hydrologic
  information base.

  Page 6-44, paragraph 3, lines 3  and 4 contained a  mix-up in alternative number and
  should read:

  Postmine recharge  from  precipitation might  be  slightly reduced regardless  of the
  overburden handling alternative used since  the overall  permeability  of  the replaced
  overburden would be less  than  that of the premine  overburden.   Alternatives 2 and 4
  (those with  topsoil  replacement) would cause a greater  reduction  (than  I  or 3) in
  infiltration rates if the  "A", "B" and "C" horizons were used.

  Page 6-44, paragraph 3. Regarding recharge.  The statements on recharge are qualified
  by other information regarding recharge  in  the Carrizo-Wilcox aquifer.  Information
  from a surface lignite  mine in Milam County indicates  recharge occurred in  25 years.
  However, this is  considered an ideal  situation, a "forced recharge"  for groundwater
  recovery,  in  that  abandoned  pits remained which  held precipitation and  recharged
  horizontally.  Calculations in the  DEIS  (pg. 6-44) based on recharge by infiltration used
  a 20 percent porosity.  Porosity could easily be 30 percent, requiring a longer recharge
  period.  Therefore,  the estimated time for recharge  at this area should be increased to
  more than 25 years. Recharge from below would be essentially nonexistent because of
  the  multiple strata  of low permeability clay  (see corrections  to pg. 6-39) between  the
  lower Wilcox and the replaced spoil.

  Mitigation measures that could  be  undertaken to  reduce the  significant  long-term
  effects on the  aquifer include use of  end pit lakes to force recharge or/and use of
  overburden handling procedures similar  to  alternatives 3 and 4, generally  replacing
  Wilcox material in the bottom of the mined pit and Carrizo material above that. Other
  machinery could be combined with the  draglines to reduce  acreage involved as shown in
  the Draft EIS for Alternatives 2, 3 and 4.
                                          111-8

-------
Monitoring of wells (or piezometers) installed in  mined/recontoured areas should be
used to determine the rate of recharge and the need for changes  in mining procedures
to reduce impacts on ground water.

Page 6-46, delete paragraphs 2, 3 and 4.

Page 6-47, delete paragraphs I and 2. Add:

Data from Martin Lake "A", "B" and "C"  monitoring wells was provided in Draft EIS
Appendix G.  The data show there has been no contamination of those wells. However,
EPA now believes that the location of the wells are at such a distance from  mining that
a conclusion cannot be drawn from the  monitoring, as mine waters would not yet have
moved that far.

Measures could be taken early to monitor  for and  mitigate for degraded groundwater.
Piezometers could be installed in the mined areas to monitor changes in water quality
to determine need for  lime  (or  other treatment)  of  spoil to prevent increased acidity
and leaching of constituents, or  need for revising  of  mining/spoil  handling alternatives
to prevent  occurrence of  unoxidized  materials  in  the  zone of infiltrating waters.
Surface  mining regulations  require monitoring but plans have not been developed for
this project and are not available for public review.

Page 6-47, paragraph 3, Discussion on Ground Water Supply should  be revised to provide
a more detailed explanation of possible procedures for compensation  if  water wells are
affected, directly or indirectly, by mining activities:

Some of  the  142+ wells in the mine area would be eliminated and other wells could be
indirectly affected. The compensation measures applicable to eliminated wells are cash
settlement, redrilling the well, or connection to a public water supply.  Which measure
is selected depends  upon the lease  agreement terms.  Replacement  wells could be
completed in the deeper Wilcox sands.  Compensation by connection to a water supply
system could be to one of the existing systems (depending upon the property  location) or
to another  system,  if one  existed  at the time  of compensation.   Surface  mining
regulations (with RRC  as the delegated authority) require  compensation for affected
wells even  if  they  are  located  on  land  the  permittee does not  own or  lease.
Compensation measures would be the same as for wells covered by lease agreements.
The  impact  to   ground-water  production   in  the  units  above  the mined lignite  is
considered a significant and long-term adverse impact but not irreversible.

Section 6.4  SURFACE-WATER  RESOURCES

Page 6-51, Hydrologic Characteristics, the discussion of soil associations categorized
into  different Hydrologic  Groups (based  on  runoff  potential) does not relate those
associations to Soil Group I through IV (pg.  6-11) which are based on features other than
runoff  potential; to clarify  this, both Hydrologic Group and Soil Group designations
should be given for each association and the following changes are needed:

Paragraph 3:

The  Kirvin-Bowie-Cuthbert  soil  association (Soil  Group II,  pg.  6-14)  has  an  overall
Hydrologic Group Classification of C.
                                       111-9

-------
Paragraph 4:

The  Nacogdoches-Trawick soil  association (Soil Group I,  pg.  6-11) has  a hydrologic
classification of B.

Paragraph 5:

About 10  percent  of the  project  area is made up  of  soils in the  Lilbert-Tenaha
association (Soil Group III, pg. 6-14).

Paragraph 6:

Soils  of the Nahatachie-Mantachie association (Soil Group  IV, pg.  6-15) are found along
Mill Creek and Tiawichi Creek in the project area.

Page  6-68, paragraph 2, sentences 3 and 4 regarding retention of flood waters  due to
need  to meet pH, iron, manganese and total suspended solids limits.

It should be noted that  due to changes in the standards, Federal Register, October 13,
1982—treatment pond discharges from  mines  are exempt  from  limits on pH, total
suspended  solids, manganese  and iron  during rainfall  events.  Instead, less stringent
limits using the "settleable matter" parameter are in  effect. Therefore, retention time
could be  less  than previously explained.   Additionally,  based on the  above and re-
evaluation of other assumptions, for  example,  that soil  runoff  characteristics from
premining conditions  remain unchanged  for all  overburden handling alternatives—EPA
has determined a level  of confidence cannot  be placed  on  the study.    It  may be
considered  reasonable  for  a preliminary  study; any  further  study should  be fully
coordinated with the Texas Department of Water  Resources and the Sabine River
Authority.

Page  6-73, paragraph 2, add the following  to clarify that  the past performance of an
applicant is considered during the mining permit  application process:

TUGCO's  record of compliance  (past performance) also will be considered by the RRC
during the mining permit application process.  The Texas Surface  Mining and Reclama-
tion  Act requires the RRC to  deny a permit to any  applicant "with  a demonstrated
pattern of willful violations."  See Appendix B for a listing of violations and corrective
actions  by  the company which  were  submitted for an RRC  permit  at  the  railroad
loading and dragline maintenance facility.  The RRC did not find a pattern of  willful
violations.

Page  6-73, paragraph 2. Revise to include these  concerns on surface-water quality;

A state agency has pointed out that sediment pond treatment has not been effective in
preventing excessive  sediment from entering streams  from mined areas.   Also, while
sediment pond  water  discharge samples have not indicated toxic  levels  to fish (at the
existing Martin Lake areas),  data from sediment  in streams  below discharges is not
available.  Further, inconsistencies  in ambient  stream data on and below  the  Martin
Lake  D project area are noted by Texas Department of Water  Resource (TDWR letter
to EPA,  Part  II.B, Final EIS).   The Draft EIS discussed  (page  6-58  and  page 6-62)
constituents that exceeded water quality standards or drinking water standards.  These
are: mercury, phenols, pH, alkalinity, dissolved  solids,  suspended solids, turbidity, and
ammonia. Additionally, groundwater data for the area  show manganese, mercury, iron,
phenols, copper, and pH  levels that  exceed limits—with ammonia and arsenic  close  to
                                       111-10

-------
limits.  Groundwater will  be pumped out of pits  to sediment ponds and  eventually
discharged  to streams with mine area surface runoff and constitutes a source to be
considered  in determining limits on pond discharges to streams.  Further, surface spoil
materials constitute a source of acidity of surface waters.

With these  concerns in mind, EPA has made the following determinations  to protect the
surface water: based on occurrence of surface waters,  on site, with pH as  low as 5.3 and
4.3 at TUSI I and  2 sampling stations shown on  Fig. 6-13 (Draft EIS) and groundwater
with pH as low as  4.3—any NPDES permit  should be  based on the acid mine  drainage
sub-category new  source  performance  standard.  Effluent characteristics, discharge
limitations  and monitoring requirements would  be as follows:

            Effluent Characteristic                  Discharge Limitations

                                                   Daily Avg.      Daily Max
                  3
            Flow-m /Day (MGD)                    Report flow     Report  flow
            Total Suspended Solids                   35.0 mg/1       70.0 mg/1
            Iron, Total                              3.0 mg/1        6.0 mg/1
            Manganese, Total                        2.0 mg/1        4.0 mg/1
            pH                                     shall  not  be   less  than  6.0
                                                   standard units nor greater than
                                                   9.0 standard units.

            Effluent Characteristic                  Monitoring Requirements

                                                   Measurement    Sample
                                                   Frequency      Type

            Flow-m /Day (MGD)                    One/day.       Estimate
            Total Suspended Solids                   One/day.       Grab
            Iron, Total                              One/day.       Grab
            Manganese, Total                        One/day        Grab
            pH                                     One/day        Grab

             When discharge occurs


EPA  has determined to require,  by special  provision to the permit,  water quality
monitoring  on a quarterly basis at the TUSI  I, 2 and 5 sampling stations.  Parameters to
be  sampled,  analyzed  and  reported  are  pH,  ammonia, mercury, phenols,  alkalinity,
turbidity, total suspended solids, and total dissolved solids (see Appendix A,  Part  III of
draft permit).  Locations of proposed sampling stations are shown on Fig. 111-2 of this
FEIS. Previous sampling locations were shown  in the DEIS on pages 6-59 and 6-63.

Because of concerns for potential water quality impacts to the downstream  drinking
water supply and due to the important water quality function of wetlands—a provision is
applied to the permit to require  the company to  submit site specific plans to the Corps
of Engineers for each proposed wetland area discharge and obtain a Clean Water Act
Section 404 authorization from the Corps of Engineers.

A sewage treatment plant, for secondary level  treatment of sanitary waste, is  proposed
at  the  railroad loading and  mine  maintenance  facility.   Effluent characteristics,
discharge  limitations and  monitoring would  be as  follows (see Appendix  A,  draft
permit):

-------
Effluent Characteristic          Discharge Limitations       Monitoring Requirements

                               Other units (specify)           Measure-
                                                            ment    Sample
                                                            Freq.    Type
                               Daily Avg   Daily Max

Flow-m3/Day (MGD)             Report Flow                   I/week  Grab
Total Suspended Solids           30mg/l    45mg/l           I/week  Grab
Biochemical Oxygen
 Demand (5-day)                30mg/l    45mg/l           I/week  Grab
pH                             Not less than 6.0              I/week  Grab
                               standard units nor
                               greater than 9.0
                               standard units
Page  6-75, the TDWR allowable  concentrations given  in Table  6-15  were for daily
averages (of multiple samples in a 24-hour period) when the applicable standards are for
grab samples,  i.e., the concentration of  an individual sample collected in less than 15
minutes. Insert the following standards:
                           Revised Table 6-15 (in part)
                                                       TDWR Allowable
                                                     Concentration, Crab
             Metal                                     Sample (ppm) '
             Manganese                                      3.0

             Selenium                                        0.2

             Arsenic                                         0.3

             Cadmium                                        0.2

             Chromium                                       5.0

             Lead                                            1.5

             Mercury                                        0.01

             Zinc                                            6.0
            2
             ppm - parts per million

            ^SOURCE:   Texas Department of Water Resources, 1979.
             Permanent  Rules,  as  amended.    Section  156.19.15.002.
             Austin, Texas.
                                     111-12

-------
Section 6.5  WETLANDS AND FLOOD PLAINS

Page  6-79.   Impacts of Project Alternatives,  add the following regarding value of
wildlife habitat and recommendations;

The U.S. Fish and  Wildlife Service (FWS) classified the bottomlands and wetlands as
Resources  Category  2,  of high value  for  wildlife evaluate species and  scarce or
becoming scarce (Federal  Register 46(15):   pages  7644-7663, January 23, 1981).  FWS
recommends "in kind replacement of floodplain wetland communities during reclama-
tion and  calls for specific measures to restore the  hydrologic balance in wetland areas,
establishment of wetland vegetation  and management practices  to promote long-term
recovery of the  ecosystems (U.S. Department of Interior letter to EPA, Final EIS, Part
II.B).

EPA  has further evaluated  potential impacts of  the project proposed,  including the
concerns stated above and particularly the  water quality improvement function of the
wetlands in relation to the downsteam drinking  water supply.  In addition,  no  site
specific plans regarding restoration of the  hydrologic regime  (which  includes  surface
and ground water) based on site specific information regarding characteristics of mine
spoil  that  will  occur at the surface  or near  surface in  these wetland areas,  are
available.  EPA has coordinated  with the  Corps  of Engineers  regarding this  project
evaluation.  Subsequently, a provision has been put on the draft  permit which requires
that TUGCO submit specific plans for  each wetland area  discharge proposed to the
Corps of Engineers for authorization by the Corps under Section 404 of the Clean Water
Act.

Section 6.6  TERRESTRIAL BIOLOGY

Table III-1  in this Final  EIS  is provided  as a comparison table of vegetation types and
land use categories in  the project area.  The  table may be  used  as a reference to
prevent  misunderstandings  which could be  caused by  different acreages for  similar
categories.

Page  6-95, paragraph 3, the sentence concerning the transmission line relocation should
be changed to read:

The SWEPCO transmission line relocation  and  the TUGCO 138 kv line construction
within the  project area would preempt an additional 100  acres; of which 6 acres are
bottomland hardwoods, 5.5 acres  are pine  plantations,  31  acres and  pastureland, and
50.5 acres are regeneration/cutover areas and upland pine/hardwood forest.

Page  6-95, paragraph 3, add the following sentence to reflect the improved estimate of
total  acreage and vegetation types to be disturbed by construction of the mine facilities
area;

The mine facilities area (Fig. Ill-1) (office, shop, train loading station,  dragline erection
pad, etc.) would preempt about 210 acres composed of  pastureland (126  acres); upland
pine/hardwood  and  regenerative forest (55  acres); pine  plantations  (21 acres); and
cropland (8 acres).

Page  6-96, paragraph 3, in response  to  several comments about the percentage range
for planting of woody species and to better  explain the factors involved in determining
final vegetative cover, add the following sentences  between lines I I and 12:
                                       111-13

-------
This percentage  range  is vague but  represents  TUGCO's  commitment.   The final
vegetative cover  established  on any given  acreage may be based upon factors such as:
suitability of the land (e.g., steep slopes for woody species); adjacent vegetative cover
(e.g., establishing "pockets" of woody vegetation within pastureland); landowner desires
(e.g., lease conditions); and regulatory decisions of the RRC (e.g., on land use changes).
To be consistent  with the total acreage to be mined (17,916-2,000  = 15,916), the 10 to
50 percent range for  upland pine/hardwood reforestation would amount to 1,592 and
7,958 acres respectively.

Page 6-98,  Table  6-17,  revegetation  species  for wildlife habitat,  should have  the
following note added at the bottom:

Note:   This  list  represents  those species which  might be  used  during reclamation.
Inclusion of any species does  not mean that it would be used,  only that TUGCO has  the
option  to  use  it if  conditions  warrant.   Some  nonnative  species  are included  for
potential use in special circumstances such as:  (I) unavailability of native species; and
(2) more optimal  growth compared to  native species.

Page 6-100, paragraph 3,  line  5 should be changed to emphasize that the  percentage
range for final vegetative cover represents TUGCO's commitment at this time:

From 50 to 90 percent  of the  mined area would be reclaimed as improved  pasture
(TUGCO's commitment).

Page 6-100, paragraph 4, change sentence 2 to include that a gound  cover  such as clover
also would be  planted, delete  sentence 3  and  add the following  sentence after the
sentence ending ". . . mature forests.":

Immature forests not only represent  future timber resources  but provide benefits such
as; rebuilding the soil,  soil stabilization and cover for wildlife.

Page 101,  last paragraph, and  page  102.   Add the following regarding  mitigation  to
wildlife habitat loss;

While a project specific revegetation or a fish and wildlife plan has not been developed,
the general measures discussed  in the Draft EIS would reduce habitat loss  where carried
out.

Other possible  mitigation  measures for loss of wildlife habitat from  the reclamation
proposed could  include making lands available to Texas Parks and Wildlife Department
for  wildlife management after  bond release.   Through  their  programs,  areas  may be
utilized for displaying applied range and wildlife management practices  as well as  for
research under  controlled conditions.  Some areas  may be used to  provide brood stock
for  depleted wildlife  ranges.   Possibilities for recreational use  by the  public are
considered.  Measures are taken to ensure lands have food and cover for wildlife,  for
example, this may require planting grain or providing other vegetation such as woody
shrubs  if an area contains primarily coastal bermuda grass.   Management may include
grazing  practices and utilization  of  hunting to regulate wildlife populations.   Where
public recreation is considered,  access to an area and the number of persons are taken
into  account in planning; for  example, this may include  hunter permit drawings where
hunting  is part  of the  management. Actual procedures for a  given area are based on a
mutual agreement between TPWD and landowners, which in this case would be TUGCO.
This information  has been  forwarded to TUGCO with a request for their consideration
for  entering into  such an agreement  as a potential enhancement measure for the Fish
                                       1-14

-------
and Wildlife  Plan for the mining permit  application to the Railroad Commission of
Texas.

Section 6.9  ARCHAEOLOGICAL AND HISTORICAL RESOURCES

Page  6-113, Table 6-18 should have the following added after  Site No.  4IRK 124 to
incorporate additional information about the Vinson Plantation  which was provided by
the Texas Historical Commission; as well as recommendations for the four prehistoric
sites:
Site No.
4IRKI28
4IRKI30
4IRKI06
4IRKI09
4IRKIIO
4IRKIII

Site Name
Vinson Plantation
Irwin Cemetery
Unnamed
Unnamed
Unnamed
Unnamed

Survey/
Reference
THC 1983
TAS 1983
TAS I960
TAS I982b
TAS I982b
TAS I982b
.
Cultural
Affiliation
Historic
Historic
Prehistoric
Prehistoric
Prehistoric
Prehistoric
•
Recom-
mendation
"NRHP" '
Avoid
Test/"NRHP"'
Test/"NRHP" '
Test/"NRHP"'
Test/'-NRHP"1

Page 6-116, after paragraph  5,  add the  following paragraph  regarding  the  Vinson
Plantation;

Site 4IRKI28, Vinson Plantation may fall within the project area.  The house, a single
story classic Anglo center-hall house,  is still  standing but is  not in good repair.  The
Texas Historical  Commission,  in a letter  to  EPA  dated April  26,  1983  (see Part II),
states that  the Vinson Plantation is potentially eligible for the National Register  of
Historic Places.

Page 6-117, paragraph I, add the following  information concerning  the Irwin Cemetery
and other cemeteries which could occur in the  project area:

Several cemeteries, in addition  to  those  listed in Table 6-18, occur  throughout the
project area.  One such cemetery, the Irwin  Cemetery, was  located for EPA  by Mr.
Prentis Irwin (letter,  Part  II, FEIS) and  was then surveyed by archaeologists from the
Texas Archaeological  Survey in 1983. The cemetery contains  13  graves with the oldest
burial date  being 1863 and the latest 1880.  Three family names  (Irwin, Sanders and
Jones) are represented with  traditionally  shaped markers. The cemetery is located just
east of SH 322 about 0.3 miles south of the Crims Chapel Cemetery (see Fig. I-2A. It is
not  located in  the first five year period  area, but if mining  takes place near the
cemetery at a later date, RRC regulations  as well  as specific state law require that it
be avoided.  Texas Utilities has been notified to place  the cemetery location on  mine
plans.

Page 6-118, after Paragraph  I, add the following on mitigation measures and findings on
the Walling Cabin;
                                        1-15

-------
The  Walling Cabin, 4IRKI04, was determined eligible for nomination to the National
Register of Historic Places based on surface survey information, archival determination
of its age (1841) and its attribution to an early Rusk County settler.  Mitigation was
required by  EPA  and  the  Texas  State  Historic Preservation  Officer to  provide
protection  for the historic  and architectural  significance of the  cultural property.
Texas Archeological Survey of the University of Texas at Austin was responsible for:

I)   Archival search and review aimed at establishing as complete a documentation/
     background as possible.

2)   Mapping the site.

3)   Producing a photographic record to Historic American Building Survey standards.

4)   Surface  and subsurface artifact recovery, fracture  identification and appropriate
     documentation utilizing visual  and metal detector search,  hand excavation and
     machine dug test trenches.

5)   The conduct of collection, sampling, testing and salvage operations as dictated by
     the initial surface and subsurface collections/excavations.

6)   The production of a report on the above actions and their results.

Archival study has enriched the history of the cabin's occupancy and given  important
insights  into  its possible furnishings.   Photographic  documentation  fulfills Historic
American Building Survey criteria for National Register of Historic Places nominees
and  provides  a basis  for reconstruction.   Analyses of the building  materials  has
identified construction  techniques and differentiated between original and replacement
structural components.  As  the  restoration  and eventual nomination  to the National
Register at the  new site depends upon accurate reconstruction using original materials
or reuse of others of  that  time period, this  facet  of  the study,  coupled with  the
subsurface excavations, was of prime importance.  For example, the original hypotheti-
cal plan of the structure indicated a  masonry chimney based on the exposure of a rock
base. Excavations at the  foundation  uncovered undressed dry-masonry laid stone which
was  considered  evidence  for foundation for  a  mud cat type chimney originally.
Handmade  bricks uncovered indicate that  a brick chimney  was later constructed, but
probably after 1843, when bricks as well as brickmasons were more available (according
to the census). No stone masons were listed on the census.

Metal detector searches, followed by subsurface sampling, provided  a large  sample of
artifacts, largely from the later  periods of  the  cabin's occupancy.   The  few early
examples will be  used as  part of  a museum display  in the  reconstructed  cabin.
Numerous associated features such  as wells, root cellars, and  chicken houses, were
documented in this study and the absence of others explained by modern  land use which
probably obliterated any traces.

Restoration of the cabin is expected  to  be complete in  mid-September in time for
Henderson's centennial celebration.  Data derived from the archeological  study has been
supplied to  the Rusk  County Historical  Commission to assist them in determining the
original materials and construction techniques used.  All replacement parts, necessary
where  original materials  had  deteriorated or  were absent, have been  obtained from
sources known to date to the appropriate period.  The structure, when  nominated for
the  National  Register, will consist of the original  single-pen  log structure slightly
modified by the addition of entrances cut during its first decade  and a  fireplace-
chimney of handmade brick, the first permanent materials employed.


                                       111-16

-------
A  complete report in the form of a  Technical  Bulletin will be available  from Texas
Archeological Survey.

Page 6-118, last paragraph.  Regarding four significant  prehistoric sites in  first 5-year
area, add:

The route  for  relocation of the  SWEPCO transmission line and a recently proposed
TUGCO 138 kv line in the same corridor is proposed as  shown on Fig. I-2B. While the
corridor is proposed to avoid 4 IRK 106, 109,  110, and I I  I, the area is considered a high
probability area  for  cultural  resources  and construction  of  the  new  line  and  the
relocation  of the SWEPCO  line present a source of potential impact.  The east-west
segment  of the  proposed  corridor (Fig.  I-2B) has  now  been intensively  surveyed
(October,  1983).  Preliminary information is that no sites were found. Texas Utilities is
expected to provide any  measures necessary to  comply with the MOA  regarding high
probability areas and discovery of sites during construction.

Section 6.10  AIR AND SOUND QUALITY

Page 6-120, paragraph 2 should be deleted and replaced with the following paragraph to
clarify the existing regional air quality  and to include information  provided by the
Texas Air Control Board.

The air quality in  the  project area is acceptable.  The project is  located within Air
Quality Control Region  (AQCR) 022.   The  proposed  facilities are  in a location that
meets  both national primary and secondary air quality standards for carbon monoxide,
nitrogen dioxide,  sulfur dioxide and particulates (TSP).  It is, therefore, in a designated
"attainment area" for those criteria pollutants.  Rusk County  has been  designated as
"unclassifiable" for  ozone and there has been no designation established for lead.

Page 6-126. The question of the amount and impacts from controlled crusher emissions
was raised; calculations of the primary crusher emissions and impacts should be added
to the section on  impacts  of project alternatives:

The 18 TPY of controlled process emissions  are calculated from data  for release of
emissions  from crushers (EPA,  I977a) and project-specific information.  Crushers
release emissions at a rate  of 0.02 Ib  per ton of material crushed and TUGCO states
they will process 3.5 million tons/year of lignite.   Thus the crusher would release 35
tons/year of uncontrolled  emissions (0.02 Ib/ton x 3.5 million tons/year x  1/2000 Ib/ton).
The crusher emissions will be controlled by water sprays  which are 50 percent efficient,
so the  controlled release  will  be about 18 TPY (35  tons/year x 0.50 = 17.5 tons/year).
The TACB, in a letter dated March 8,  1983 (see Appendix B),  has exempted the facility
from the TACB permit procedures "because it will  not make  a  significant contribution
of air contaminants to the atmosphere . . ."  According to the level of significance used
by TACB,  this means  that the fugitive  emissions will add less than  1  microgram
(1/1,000,000 grams) per cubic meter  of air for the  annual average and  less than 5
micrograms per cubic meter of air for the  24 hour average.   No dust  problems from
crusher emissions  are expected  beyond the  permit  boundary nor at the nearest
residences.

Page 6-126, paragraph 4, delete the EIS reference to  a  generic dust control plan;  it is
unknown what will  be submitted to RRC, but the regulation appears to call for a site
specific plan per mine area.
                                        1-17

-------
Page  6-132, paragraph  2, insert  the  following sentences between lines  12  and 13 to
provide additional information  on the frequency and length of time worst-case noise
conditions might occur near the community of Oak Hill;

If  worst-case  conditions were  to  occur, operations near the edge of the nearest pit
would occur for 24 hr/day for about a one week period four  to five times  per year over
a one and one-half (^2)  year period.   That  is, worst-case conditions might occur about
seven to eight times for  one week periods.

Section 6.1 I  LAND USE AND RECREATION

Table III-1 in  this Final EIS is  provided as a comparison table  of vegetation types and
land use categories in  the project area.   The table may  be used as a  reference to
prevent misunderstandings which could be  caused  by  different acreages for  similar
categories.

Page  6-139, paragraph  3, the  description of timber production should be corrected to
state:

In 1979, there were five saw mills in Rusk  County producing 50,469,000 board  feet of
pine and 2,053 pine ties  (from a total of 71,291 cross-ties produced).

Section 6.16 TRANSPORTATION

Page  6-164, paragraph I, add the following additional impacts from construction of the
over- and underpasses for the railroad between MLSES and the mine area:

The construction of railroad overpasses on SH43 and FM  1716  will cause disruption of
traffic  for  about 4  months.   All necessary state and county approvals have  been
obtained for the railroad crossings and all crossings will be constructed before expected
traffic  increases occur  from  other  mining activities  and  induced  population.   See
Appendix B for approvals.

Page 6-164, paragraph 5, add specific  impacts expected to existing roads;

Based on past  experience with similar operations  by  the State Department of Highways
and Public Transportation (SDHPT) area highways deterioration would be escalated by
project activities such  as hauling heavy equipment to and from the  mine;   hauling
lumber, topsoil,  ore, gravel  and clay from the mine; and hauling crushed limestone to
the mine. Many  loads would be expected to  require SDHPT permits due to load weight.
Presently, due to overweight hauling, farm road rebuilding projects over  more than ten
miles of roads in Rusk County  are  costing an  average of $80,000 a  mile  (SDHPT
comment  letter to EPA, Part  II  FEIS).

Page  6-164, paragraph  5, in response to  a comment from the State Department of
Highways and  Public Transportation  more information was obtained concerning poten-
tial mitigation of road  deterioration  caused by construction-related  truck traffic; the
following sentences should be added to the end of  the paragraph:

Several methods could be useful in mitigating the impact of road  deterioration.  Truck
routing could be specified to prevent  continued passage of heavy trucks over the same
roads.    Contractual  agreements could  be effective  in  reducing  the  incidence of
overweight vehicles  reporting  to  the job  site.  This approach  requires that  suspect
vehicles be individually  weighed at the job  site prior to delivery of materials and that
                                        1-18

-------
overweight shipments be rejected.  Maintenance agreements, between constructors and
the SDHPT, could be negotiated which call for the constructors to provide maintenance
on  affected  roads.   TUGCO and  the SDHPT do  not presently  have any agreement
covering mitigation of road deterioration (SDHPT, telecommunication, 1983).

Section 6.18  CUMULATIVE IMPACTS

Figure  II1-3 shows  the  general location  of  the  eight projects considered during the
cumulative impacts analysis. Figure  111-4 shows a more detailed relationship of four of
those projects to the "D" area.

Page 6-168.   Geology and  Topography.  The sentence  regarding  the  acreage of site
specific impacts should read:

The mine projects would cause site specific adverse impacts to more than 100,000 acres
of presently undisturbed geologic units.

Page 6-168. Groundwater Resources.  Delete the last three sentences and state:

Recharge of  the spoil would likely take more than 25 years, but would depend on site
specific factors and whether any measures to force  recharge (such as with end pit lakes)
or  to rebuild the aquifer (with selective spoil replacement) are  taken.  The level of
groundwater  contamination by leached constituents from the spoil will depend on spoil
handling/reclamation procedures.  (Some mine projects in the Carrizo-Wiicox predict
significant increase in Total Dissolved Solids and  in  leached metals.)  No monitoring
data available  on  present mine projects  can be  utilized to  predict  as wells are at a
distance from active mining that affected waters have not moved that far.

Page 6-169. Surface Water Resources. Add:

Several of the  mine projects  propose stream diversions which  will provide sediment
loading and  leached constituents  (extent depending on overburden  handling).   The
proposed  Martin Lake  "D"  diversion of  Dry Creek (.38 miles)  may not  contribute
significantly  to adverse  water quality in the Sabine  River and Lake  Cherokee  if
overburden is replaced by selective handling as close to existing conditions as possible
and remaining wetlands  are left  intact.  Monitoring  included  in  the  draft permit
(Appendix A to this Final EIS)  is  proposed to detect changes in water quality in streams
tributary to the Sabine River, that may be affected by this project, so that changes in
limits can be instituted if necessary.

Page 6-171,  paragraph  3,  line  13  and  Page  6-172, paragraph  I,  line 2  contained
typographical errors and  should read:

Two of the projects (the proposed plant/mine in Harrison County and the Troup project)
are in planning stages and are not scheduled to begin in the near future. These projects
could become operational within the Martin Lake "D" Area project life (about 30 years).

C.            REVISIONS TO CHAPTER  9.0-BIBLIOGRAPHY

The following references were used (in addition  to  those references listed in the  DEIS)
during the preparation of the FEIS and should be added to  the bibliography in Chapter
9.0:
                                         1-19

-------
 Fresquez, P. R. and W. C. Lindemann.  1982.  Soil and rhizosphere microorganisms in
     amended coal mine spoils. Soil Sci. Soc. Am. J.  46:751-755.

 Miller, R. M. 1978.  Laboratory  research studies on the reestablishment of the below
     ground  ecosystem.  |n Argonne Land Reclamation  Program Annual Report.  Jul.
     1976-Oct.  1977, ANL-LRP-2.

 Rusk County Tax Collector.  1983. Personal communication with Dr. Larry Sanburg of
     Espey, Huston & Associates, Inc.

 State  Department of Highways and Public Transportation.  1983.  Personal communi-
     cation by Mr. Marcus L. Yancey,  Jr. with Mr. Charles Jasper of Espey, Huston &
     Associates, Inc.

 Texas Historical  Commission.   1983.  Letter dated  April 26. 1983 from  LaVerne
     Herrington, Ph.D. addressed to  Mr. Dick Whittington,  P.E., Regional  Adminis-
     trator,  EPA Region 6.

 Prickett, T.  A. and M. L. Voorhees.   1981.  Selected Hand-Held Calculator Codes for
     the Evaluation of Cumulative Strip-Mining  Impacts on Groundwater Resources.
     Prepared for the Office of Surface Mining, Region V, Denver, Colorado.


D. REVISIONS TO APPENDIX A-SECTION 404(b)(I) ANALYSIS

Revisions to the analysis of impacts from the discharge  of dredged and fill materials
into Waters of the U.S. according to the Clean Water Act, Section 404(b)(l) guidelines
will be made as site-specific plans are provided by the applicant  to  the  Corps of
Engineers.

E. REVISIONS TO APPENDIX B-MEMORANDUM OF AGREEMENT

Page B-3, paragraph 2, the address for the National Architectural and Engineering
Record has changed since establishment  of the Memorandum of Agreement.   The new
address is:

National  Architectural  and Engineering  Record (NAER) (Chief,  Division of  Cultural
Resources, National Park Service, Rocky Mountain  Region, P.O. Box 25287, Denver,
Colorado 80225).

Page B-3, paragraph 6,  the reference to the Interagency Archaeological Service was
incorrect in the Memorandum of Agreement and should read:

Interagency  Resources  Division (National  Park Service, Department of the  Interior,
Washington, D.C. 20240).


F. REVISIONS TO APPENDIX C-PRELIMINARY NPDES PERMIT

See Appendix A for revisions to Outfall 001 regarding discharges from mine areas; and
Outfall 002   regarding  discharges  from  the sewage  treatment plant;  and Part  III
regarding special provisions.
                                       1-20

-------
                                  TABLE Ill-l

                  VEGETATION COMMUNITIES AND LAND USE
                     MARTIN LAKE "D" AREA PROJECT SITE
Total Project Mine Site
Category
Vegetation Communities:
Pine Plantations/Managed Pine
Forests
Regeneration/Cutover Areas
Upland Pine/Hardwood Forests
Bottomland Hardwood Forest
Communities
Pasturelands (Improved, Native,
Hayfields, Oldfields)
Croplands
Hydric Communities
Other Aquatic Habitats
TOTAL
Land Use:
Pasture (P)
Forestry
Mature (F)
Transitional (F*)
Grazingland (G)
Cropland (C)
Undeveloped
Water (UW)
Forest (UF)
Water (W)
Commercial-Industrial (C-I)
TOTAL
Acres
1,218
3,795
3,290
1,924
13,135
1,229
162
210
24,963
10,396
1,949
3,749
1,589
1,336
257
5,327
200
160
24,963
Percent
4.9
15.2
13.2
7.7
53.6
4.9
0.6
0.8
41.6
7.8
15.0
6.4
5.4
1.0
21.3
0.8
0.6
Within Mine Blocks^
Acres
665
2,822
2,079
1,039
10,259
865
53
134
17,916
7,915
1,452
2,804
1,211
979
188
3,186
130
51
17,916
Percenl
3.7
15.8
11.6
5.8
57.3
4.8
0.3
0.7
44.2
8.1
15.7
6.8
5.5
1.0
17.8
0.7
0.3
 The categories listed  for vegetation are based upon different criteria than land  use
 categories.  Thus, acreages for categories with similar names are not the same in both
 tables.

"See Fig. 1-2 A and B for location of generalized mine blocks.
                                      1-21

-------
                               TABLE II1-2

             SUMMARY OF LIGNITE AND ASH CHARACTERISTICS
   Component
Average
Std. Dev.
Maximum
Minimum
Lignite
Total Sulfur
Moisture
Ash
BTU/Lb.
Ash Load ///MMBTU
Sulf. Diox. ///MMBTU
Thickness in Feet
Ash
Silicon Dioxide
Ferric Oxide
Aluminum Oxide
Calcium Oxide
Magnesium Oxide
Sodium Dioxide
Potassium Oxide
Titanium Oxide
Base/ Acid Ratio
Iron/Calcium Ratio

1.34
34.94
7.09
7,112.16
10.18
3.85
7.58

34.33
18.88
18.73
10.65
2.38
.36
.00
1.17
.64
2.76

.56
5.21
2.42
774.07
4.12
1.73
3.57

9.22
9.55
5.52
5.28
1.17
.20
.00
.43
.29
3.16

3.56
44.40
18.29
8,477.00
31.52
10.33
32.96

57.28
45.08
34.65
23.81
5.81
1.05
.00
2.14
1.47
19.71

.49
6.52
3.16
2,310.00
4.74
1.33
1.60

4.32
1.22
4.74
.06
.39
.01
.00
.08
.18
.21
Number of Records with no area // = 0

Wed, Oct. 27, 1982, 2:50 P.M.

Mill Creek Area - 363
Seam I
73 prox
75 ash
                                   1-22

-------

                                 FACILITIES
                                 CONSTRUCTION
                                 PERMIT  BOUNDARY
                                          j
                                            T ol K
001- TO TRIBUTARY OF DRY,
    THEN TO MILL CREEK

002- TO MILL CREEK THROUGH
    POND AND 001
                         L—
^^^^~~~~™J
                                                                                                        N
                                                                                                    NOT TO SCALE
                                                                                             TEXAS UTILITIES GENERATING CO.
                                                                                                MARTIN LAKE 'D1 AREA
                                                                                                       Fig.m-l

                                                                                                LOADING  STATION OPERATION

-------
	PROJECT BOUNDARY

T I  CORRESPONDS TO(V)ON FIG. 6-13'
     IN DEIS
                              Martin
                              Laxe SE5
              Texas Utilities Generating Co
                Martin Lake ' D" Area
                SURFACE  WATER
              MONITORING  SITES
SOURCE SWR1, ;37«.

-------
                           ElDDO\B3SSIER   V.'EESTER  CLftlBORNE
                              LOUISIA-NA
Project
Acres

(1)
(2)
(3)
W
(5)
(6)
(7)
(8)

Martin Lake "D" Area Mine
MLSES and Mining Areas "A", "B", "C"
Darco Mine and plant
Henry W. Pirkuy Power Plant/South Hallsville Mine
Proposed power plant and mine
Proposed Troup Project, mine and facility
Dolet Hills Power Plant and mine
Castor Bayou Mine
Project
Area
25,350
24,680

20,770


30,000
1 1 , 200
Directly
Disturbed
18,400
23,000
_
11,000
-
36,000
16,200
10,300
                                   TEXAS UTILITIES GENERATING CO.
                                       MARTIN LAKE "D" AREA
                                               FIG. ffl- 3
                                    PROJECTS  CONSIDERED  IN
                                    CUMULATIVE IMPACT  ANALYSIS

-------
                                                                 PROPOSED
                                                                 MINERS
                                                           154
                                                           v_>

                                                      MARSHAL
                     LONGVIEW
                       I
                                    PIRKEY POWER  PLANT   '
                                    AND SOUTH HALLSVILLE
                                    MINE (A
                                                            DARCO  MIN
                                                          MARTIN
                                                          MINING AR
  PROJEC
LOCATION
                                                         CARTHAGE
          HENDERSON
                                                      RAILROAD RIGHT-OF-WAY
                                                 	 TRANSMISSION LINE RIGHT-OF-WAY
                                      PROJECTS  CONSIDERED  FOR
                                      CUMMULATIVE ANALYSIS
                                                      TEXAS UTILITIES GENERATING CO.
                                                         MARTIN LAKE "D" AREA
                                                                 FIG. H-4

                                                         PROJECT LOCATION AND
                                                         NEARBY PROJECTS

-------
               PART IV.
PREFERRED ALTERNATIVES

-------
PART IV.      PREFERRED ALTERNATIVES AND ERA'S PROPOSED ACTION

A.            APPLICANT PREFERRED ALTERNATIVE

The applicant preferred alternative is summarized  in Part I, B  of this document  and
described  in Section 5 of the Draft EIS.  TUGCO proposes to mine lignite  utilizing a
random mix spoil  mining  and reclamation procedure,  with revegetation  to  10  to 50
percent woodlands and  50  to 90  percent  pasture  (using mainly  bermuda  grass).
TUGCO proposes reclamation will be at  a level to meet surface mining regulations
under  authority of the  RRC  of  Texas.   Wastewater discharges  to streams during
mining would  be in accordance with  new source performance standards  for  alkaline
mine drainage.

B.            MOST ENVIRONMENTALLY SOUND ALTERNATIVE

While  significant  disruption to the  natural  environment  will  occur from  surface
mining  regardless  of  the  alternative procedures  used,  the   most environmentally
sound alternative would  be to proceed according to surface mining  regulations with
no variances to replacement of earth layers or required  buffer  zones.  Replacement
of earth for aquifer reconstruction would be utilized.  Additionally,  stream diversion
would  not occur;  designated  wetlands  would  be   avoided; and all SCS designated
prime  farmland  soils  would  be replaced;  in-kind  revegetation would  be utilized.
Wastewater discharge limits  would  be  based  on acid mine drainage category  new
source performance standards.

C.            EPA PROPOSED ACTION

With  reservations  due  to  the  lack  of  an approved mining/reclamation plan,  EPA
proposes  to  issue  a  permit  for  the project,  with  modifications, conditions,  and
provisions as follows.

Mine  wastewater  discharge limitations  are  according to acid mine drainage  new
source performance standards with effluent limits on  pH,  total  suspended solids,  iron
and  manganese.   Discharges  during  and immediately following  rainfall  events of
magnitude up to the  10-year,  24  hour precipitation event could qualify  for effluent
limits  on  pH  and settleable  solids only.  Discharges within  24 hours of a rainfall
greater than  the  10 year,  24 hour   event  could   qualify for  only  pH limitations.
However,  the operator must prove that discharge  during  or following precipitation
was caused by the applicable rainfall event  to qualify for the  less  stringent limits.
Mining  discharges  from  reclamation  areas  during the  bonding period  would  have
limits on pH and settleable solids. The reference for  the above  standards is 40 Code
of Federal Regulations,  Part 434.35.   See  the draft permit in Appendix  A, Parts  I
and III  for the limits.

Sanitary waste  discharge  limitations  would be according to  the secondary  level
treatment  effluent limits for total  suspended solids, pH,  and biochemical  oxygen
demand. (See Appendix A, Part I of draft permit).

TUGCO would provide instream water quality monitoring  at sites on Mill  Creek and
Tiawichi  Creek.   Sampling,  analysis  and  reporting for  pH,  mercury,  phenols,
ammonia,   alkalinity,  total dissolved solids,  total  suspended  solids, and turbidity
would occur quarterly.
                                       IV-1

-------
No  discharge into any  Corps  of Engineers  designated  wetlands would be  allowed
unless  Clean  Water Act,  Section 404 authorization is obtained from the COE for
each discharge,  based on site specific plans.   This includes any mining or construc-
tion activity proposed as well as transmission line or pipeline relocations.

Stipulations of the Memorandum  of  Agreement on cultural resources  (Appendix B of
draft  EIS) must  be complied with for consideration of historic  and archaeological
resources before earth disturbance in  a  permit area and for instances of discoveries
during earth disturbance.
                                       IV-2

-------
                             APPENDIX A.
DRAFT NPDES PERMIT FOR THE MARTIN LAKE "D"
                AREA LIGNITE SURFACE MINE

-------
                                          DRAEI
                                         Permit No. TX0091120
                                         Application No. TX0091120
                   AUTHORIZATION TO DISCHARGE UNDER THE
             NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM
In compliance with the provisions of the Federal Water Pollution Control  Act,  as
amended, (33 U.S.C. 1251 et. seq; the "Act"),


                      Texas Utilities Generating Company
                      2001 Bryan Tower
                      Dallas, Texas 75201
 is authorized to discharge from a facility located at Martin Lake Mining Area D,
 near Henderson, Rusk County, Texas
to receiving waters named the Sabine River via Mill, Martin and Tiawichi  Creeks
in accordance with effluent limitations, monitoring requirements and other
conditions set forth in Parts I, II, and III hereof.

This permit shall become effective on

This permit and the authorization to discharge shall expire at midnight,



Signed this      day of
Myron 0. Knudson, P.E.
Director, Water Management Division (6W)
                                        A-

-------
                                        PART I

                                        Page   2   of  19
                                        Permit No.  TX0091120
                                  PART I
                      REQUIREMENTS FOR NPDES PERMITS
SECTION A. EFFLUENT LIMITATIONS AND MONITORING REQUIREMENTS - Outfall 001

During the period beginning the effective date and lasting through the
expiration date

the permittee is authorized to discharge from Outfall(s) serial number(s) 001,
intermittent discharge from various retention ponds**-

Such discharges shall be limited and monitored by the permittee as specified
below:
Effluent Characteristic
              Discharge Limitations
   kg/day(lbs/daylOther Units (Specify)

Daily Avg    Daily Max    Daily Avg   Daily Max
Flow-mS/DayfMGD)
Total Suspended Solids
Iron, Total
Manganese, Total
Effluent Characteristic
N/A
N/A
N/A
N/A
N/A * *
N/A 35.0 mg/1 70.0 mg/1
N/A 3.0 mg/1 6.0 mg/1
N/A 2.0 mg/1 4.0 mg/1
Monitoring Requirements
                                       Measurement
                                       Frequency

                                       One/day
                                       One/day ****
                                       One/day ****
                                       One/day ****
                               Sample
                               Type

                               Estimate ***
                               Grab
                               Grab
                               Grab
Flow-mS/DayfMGD)
Total Suspended Solids
Iron, Total
Manganses, Total

   * Report
  ** See Part III, Paragraph B
 *** See Part III, Paragraph E
**** When Discharge occurs

The pH shall not be less than 6.0 standard units nor greater than 9.0 standard
units and shall  be monitored one/day**** by grab sample.

There shall be no discharge of floating solids or visible foam in other than
trace amounts.

Samples taken in compliance with the monitoring requirements specified above
shall be taken at the following location(s): At the flow measuring device prior
to discharge to a tributary of the Sabine River.
                                      A-2

-------
                                        PART I

                                        Page   3   of  19
                                        Permit No.  TX0091120
                                  PART I
                      REQUIREMENTS FOR NPDES PERMITS


SECTION A. EFFLUENT LIMITATIONS AND MONITORING REQUIREMENTS - Outfal1 002


During the period beginning the effective date and lasting through expiration
date

the permittee is authorized to discharge from Outfall(s) serial  number(s)
002, discharge from a sewage treatment plant.

Such discharges shall be limited and monitored by the permittee as specified
below:
Effluent Characteristic                Discharge Limitations
                            kg/day(lbs/da7JOther Units (Specify)

                         Daily Avg    Daily Max    Daily Avg   Daily Max

Flow-mS/DayfMGD)         N/A          N/A          *           *
Total Suspended Solids   N/A          N/A          30 mg/1     45 mg/1
Biochemical Oxygen
  Demand (5-day)         N/A          N/A          30 mg/1     45 mg/1
Effluent Characteristic                Monitoring Requirements

                                       Measurement      Sample
                                       Frequency        Type

Flow-nP/DaytMGD)                       I/week           Grab
Total Suspended Solids                 I/week           Grab
Biochemical Oxygen
  Demand (5-day)                       I/week           Grab

 * Report

The pH shall not be less than 6.0 standard units nor greater than 9.0 standard
units and shall be monitored I/week by grab sample.


There shall be no discharge of floating solids or visible foam in other than
trace amounts.


Samples taken in compliance with the monitoring requirements specified above
shall be taken at the following location(s): Prior to discharge  from the
treatment plant to Dry Creek, tributary to Mill Creek.

                                      A-3

-------
                                        PART I

                                        Page  4    of   19
                                        Permit No.  TX0091120
SECTION B. SCHEDULE OF COMPLIANCE
The permittee shall achieve compliance with the effluent limitations
specified for discharges in accordance with the following schedule:

    NONE

-------
                                        PART  II

                                        Page   5    of    19           DRAFT
                                        Permit No. TX0091120
                                 PART  II
                  STANDARD CONDITIONS  FOR NPDES  PERMITS


SECTION A. GENERAL CONDITIONS

1.  Duty to Comply

The permittee must comply with all conditions of this permit.  Any permit non-
compliance constitutes a violation of  the Clean  Water Act and  is grounds for
enforcement action; for permit termination,  revocation and  reissuance, or
modification; or for denial of a permit  renewal  application.

2.  Penalties for Violations of Permit Conditions

The Clean Water Act provides that any  person who violates a permit condition
implementing sections 301, 302, 306, 307, 308, 318, or 405 of  the Clean Water
Act is subject to a civil penalty not  to exceed  $10,000 per day of such
violation.  Any person who willfully or  negligently violates permit conditions
implementing sections 301, 302, 306, 307, or 308 of the Clean  Water Act is sub-
ject to a fine of not less than $2,500 nor more  than $25,000 per day of
violation, or by imprisonment for not  more than  1 year, or both.

3.  Duty to Mitigate

The permittee shall take all reasonable  steps to minimize or correct any adverse
impact on the environment resulting from noncompliance with this permit,
including such accelerated or additional monitoring as necessary to determine
the nature and impact of the noncomplying discharge.

4.  Permit Actions

This permit may be modified, revoked and reissued, or terminated for cause
including, but not limited to, the following:

    a.   Violation of any terms or conditions of this permit;

    b.   Obtaining this permit by misrepresentation or failure to disclose
         fully all relevant facts; or

    c.   A change in any condition that  requires either a temporary or
         permanent reduction or elimination  of the authorized  discharge.

The filing of a request by the permittee for a permit modification, revocation
and reissuance, or termination, or a notification of planned changes or antici-
pated noncompliance, does not stay any permit condition.
                                       A-5

-------
                                         PART  II

                                         Page   6     of    19
                                         Permit No.   TX0091120
5.  Toxic Pollutants

Notwithstanding paragraph A-4, above,  if a  toxic  effluent  standard or prohibi-
tion (including any schedule of compliance  specified  in  such  effluent standard
or prohibition) is established under Section  307(a) of the Act  for a toxic
pollutant which is present in the discharge and such  standard or prohibition  is
more stringent than any limitation for  such pollutant in this permit, this  per-
mit shall be modified or revoked and reissued to  conform to the toxic effluent
standard or prohibition and the permittee so  notified.

The permittee shall comply with effluent standards or prohibitions established
under section 307(a) of the Clean Water Act for toxic pollutants within  the time
provided in the regulations that establish  those  standards or prohibitions, even
if the permit has not yet been modified to  incorporate the requirement.

6.  Civil and Criminal Liability

Except as provided in permit conditions on  "Bypassing" Section  B,  Paragraph B-3
and "Upsets" Section B, Paragraph B-4,  nothing  in this permit shall  be construed
to relieve the permittee from civil or  criminal penalties  for noncompliance.

7.  Oil and Hazardous Substance Liability

Nothing in this permit shall be construed to  preclude the  institution of any
legal action or relieve the permittee  from  any  responsibilities, liabilities, or
penalties to which the permittee is or  may  be subject under Section  311  of  the
Act.

8.  State Laws

Nothing in this permit shall be construed to  preclude the  institution of any
legal action or relieve the permittee  from  any  responsibilities, liabilities, or
penalties established pursuant to any  applicable  State law or regulation under
authority preserved by Section 510 of  the Act.

9.  Property Rights

The issuance of this permit does not convey any property rights of any sort,  or
any exclusive privileges, nor does it  authorize any injury to private property
or any invasion of personal rights, nor any infringement of Federal, State  or
local laws or regulations.

10.  Severability

The provisions of this permit are severable,  and  if any  provision of this
permit, or the application of any provision of  this permit to any circumstance,
is held invalid, the application of such provision to other circumstances,  and
the remainder of this permit, shall not be  affected thereby.
                                       A-6

-------
                                        PART  ,1      *>RAFT

                                        Page   7   of    19
                                        Permit  No.   TX0091120
SECTION B. OPERATION AND MAINTENANCE OF POLLUTION CONTROLS


1.  Proper Operation and Maintenance

The permittee shall at all times properly operate and maintain all facilities
and systems of treatment and control (and related appurtenances) which are
installed or used by the permittee to achieve compliance with the conditions of
this permit.  Proper operation and maintenance  includes effective performance,
adequate funding, adequate operator staffing and training, and adequate labora-
tory and process controls, including appropriate quality assurance procedures.
This provision requires the operation of back-up or auxiliary facilities or
similar systems only when necessary to achieve  compliance with the conditions of
the permit.

2. • Duty to Halt or Reduce Activity

Upon reduction, loss, or failure of the treatment facility, the permittee shall,
to the extent necessary to maintain compliance  with its permit, control produc-
tion or all discharges or both until the facility is restored or an alternative
method of treatment is provided.  This requirement applies, for example, when
the primary source of power of the treatment facility fails or is reduced or
lost.  It shall not be a defense for a permittee in an enforcement action that
it would have been necessary to halt or reduce  the permitted activity in order
to maintain compliance with the conditions of this permit.

3.  Bypass of Treatment Facilities

    a.   Definitions

         (1) "Bypass" means the intentional diversion of waste streams from any
             portion of a treatment facility.

         (2) "Severe property damage" means substantial physical damage to
             property, damage to the treatment  facilities which causes them to
             become inoperable, or substantial  and permanent loss of  natural
             resources which can reasonably be  expected to occur in the absence
             of a bypass.  Severe property damage does not mean economic loss
             caused by delays in production.

    b.   Bypass not exceeding limitations.  The permittee may allow any bypass
         to occur which does not cause effluent limitations to be exceeded, but
         only if it also is for essential maintenance to assure efficient
         operation.  These bypasses are not subject to the provisions of
         paragraphs c and d of this section.

    c.   Notice

         (1) Anticipated bypass.  If the permittee knows in advance of the  need
             for a bypass, it shall submit prior notice, if possible  at  least
             ten days before the date of the bypass.
                                       A-7

-------
                                        PART II

                                        Page  8    of   19
                                        Permit No.  TX0091120
         (2) Unanticipated bvpass.  The permittee shall submit notice of an
             unanticipated bypass as required in Section D, Paragraph D-6
             (24-hour notice).

 d. Prohibition of bypass.

         (1) Bypass is prohibited and the Director may take enforcement action
             against a permittee for bypass, unless:

              (a) Bypass was unavoidable to prevent loss of life, personal
                  injury, or severe property damage;

              (b) There were no feasible alternatives to the bypass, such as the
                  use of auxiliary treatment facilities, retention of untreated
                  wastes, or maintenance during normal periods of equipment
                  downtime.  This condition is not satisfied if the permittee
                  could have installed adequate backup equipment to prevent a
                  bypass which occurred during normal periods of equipment down-
                  time or preventive maintenance; and

              (c) The permittee submitted notices as  required under paragraph c
                  of this section.

         (2) The Director may approve an anticipated  bypass, after considering
             its adverse effects, if the Director determines that it will meet
             the three conditions listed above in paragraph d(l) of this
             section.

4. Upset Conditions

 a. Definition.  "Upset" means an exceptional incident in which there is unin-
    tentional and temporary noncompliance with technology-based permit effluent
    limitations because of factors beyond the reasonable control of the
    permittee.  An upset does not include noncompliance to the extent caused by
    operational error, improperly designed treatment  facilities, inadequate
    treatment facilities, lack of preventive maintenance, or careless or
    improper operation.

 b. Effect of an upset.  An upset constitutes an affirmative defense to an
    action brought for noncompliance with such technology-based permit effluent
    limitations if the requirements of paragraph c of this section are met.  No
    determination made during administrative review of claims that noncompliance
    was caused by upset, and before an action for noncompliance, is final
    administrative action subject to judicial review.

 c. Conditions necessary for a demonstration of upset.  A permittee who wishes
    to establish the affirmative defense of upset shall demonstrate, through
    properly signed, contemporaneous operating logs,  or other relevant evidence
    that:
                                       A-8

-------
                                        PART II               DRAFT

                                        Page   9    of   19
                                        Permit No.  TX0091120
         (1)  An upset occurred and that the permittee can identify the specific
             cause(s) of the upset;

         (2)  The permitted facility was at the time being properly operated; and

         (3)  The permittee submitted notice of the upset as required in Section
             D, Paragraph D-6.

         (4)  The permittee complied with any remedial measures required under
             Section A, Paragraph A-3.

    d.  Burden of proof.  In any enforcement proceeding the permittee seeking to
       establish the occurrence of an upset has the burden of proof.

5. Removed Substances

Solids, sludges, filter backwash, or other pollutants removed in the course of
treatment or  control of wastewaters shall be disposed of in a manner such as to
prevent any pollutant from such materials from entering navigable waters.
                                       A-9

-------
                                        PART  II

                                        Page  10    of  19
                                        Permit No.   TX009112Q
SECTION C. MONITORING AND RECORDS
1. Representative Sampling

Samples and measurements taken as required herein shall be  representative  of the
volume and nature of the monitored discharge.  All samples  shall be taken  at the
monitoring points specified in this permit ands unless otherwise specified,
before the effluent joins or is diluted by any other wastestream, body of  water,
or substance.  Monitoring points shall not be changed without notification to
and the approval of the Director.

2. Flow Measurements

Appropriate flow measurement devices and methods consistent with accepted
scientific practices shall be selected and used to insure the accuracy and
reliability of measurements of the volume of monitored discharges.  The devices
shall be installed, calibrated and maintained to insure that the accuracy  of the
measurements are consistent with the accepted capability of that type of device.
Devices selected shall be capable of measuring flows with a maximum deviation of
less than _+ 10% from true discharge rates throughout the range of expected
discharge volumes.  Guidance in selection, installation., calibration and opera-
tion of acceptable flow measurement devices can be obtained from the following
references:

 a. "A Guide to Methods and Standards for the Measurement of Water Flow",  U. S.
    Department of Commerce, National Bureau of Standards, NBS Special
    Publication 421, May 1975, 97 pp.  (Available from the  U. S. Government
    Printing Office, Washington, D. C. 20402.  Order by SD  catalog No.
    CIS.10:421).

 b. "Water Measurement Manual", U. S. Department of Interior, Bureau of
    Reclamation, Second Edition, Revised Reprint, 1974, 327 pp.  (Available from
    the U. S. Government Printing Office, Washington, D. C. 20402.  Order  by
    Catalog No. I27.19/2:W29/2, Stock No. S/N 24003-0027).

 c. "Flow Measurement in Open Channels and Closed Conduits, U. S.  Department of
    Commerce, National Bureau of Standards, NBS Special Publication 484, October
    1977, 982 pp. (Available in paper copy or microfiche from National Technical
    Information Service (NTIS), Springfield, VA 22151.  Order by NTIS No.  PB-273
    535/5ST).

 d. "NPDES Compliance Sampling Manual", U. S. Environmental Protection Agency,
    Office of Water Enforcement, Publication MCD-51, 1977,  140 pp. (Available
    from the General Services Administration [8FFS], Centralized Mailing Lists
    Services, Building 41, Denver Federal Center, Denver, CO 80225).
                                       A-10

-------
                                         PART II

                                         Page  ll    of   19
                                         Permit No.  TX0091120
3. Monitoring Procedures

Monitoring must be conducted  according  to  test  procedures approved under 40 CFR
Part 136, unless other test procedures  have  been  specified in this permit.

4. Penalties for Tampering

The Clean Water Act provides  that  any person who  falsifies,  tampers with, or
knowingly renders inaccurate,  any  monitoring device or method required to be
maintained under this permit  shall,  upon conviction, be punished  by a fine  of
not more than $10,000 per violation, or by imprisonment for  not  more than 6
months per violation, or by both.

5. Reporting of Monitoring Results

Monitoring results must be reported  on  a Discharge  Monitoring Report (DMR)  form
(EPA No. 3320-1).  Monitoring  results obtained  during the previous 3 months
shall be summarized for each  month and  reported on  a DMR form postmarked no
later than the 28th day of the month following  the  completed reporting period.
The first report is due 	.   Duplicate copies of  DMR's signed
and certified as required by  Section D, Paragraph D-ll, and  all  other reports
required by Section D, Reporting Requirements,  shall  be submitted to the
Regional Administrator and the State at the  following addresses:

Myron 0. Knudson, P.E., Director        Director, Surface Mining  & Reclamation
Water Management Division (6W)          Texas Railroad Commission
U.S. Environmental Protection  Agency    P.O. Drawer 12967, Capitol Station
Region VI                               Austin, Texas 78711
First International Building
1201 Elm Street
Dallas, Texas 75270
6. Additional Monitoring by the  Permittee

If the permittee monitors any  pollutant  more  frequently than required by this
permit, using test procedures  approved  under  40 CFR  136 or as specified in this
permit, the results of this monitoring  shall  be included in the calculation and
reporting of the data submitted  in  the  DMR.   Such  increased frequency shall also
be indicated.

7. Averaging of Measurements

Calculations for all limitations which  require  averaging of measurements shall
utilize an arithmetic mean unless other  wise  specified by the Director in the
permit.
                                       A-1

-------
                                        PART II
                                                               DRAFT
                                        Page  12   of   19
                                        Permit No.  TX0091120
8.  Retention of Records

The permittee shall retain records of all monitoring information,  including all
calibration and maintenance records and all original strip chart recordings for
continuous monitoring instrumentation, copies of all reports required by this
permit, and records of all data used to complete the application for this
permit, for a period of at least 3 years from the date of the sample,
measurement, report or application.  This period may be extended by request of
the Director at any time.

9.  Record Contents

Records of monitoring information shall include:

    a.   The date, exact place, time and methods of sampling or measurements;

    b.   The individual(s) who performed the sampling or measurements;

    c.   The date(s) analyses were performed;

    d.   The individual(s) who performed the analyses;

    e.   The analytical  techniques or methods used; and

    f.   The results of such analyses.

10.  Inspection and Entry

The permittee shall allow the Director, or an authorized representative, upon
the presentation of credentials and other documents as may be required by law,
to:

    a.   Enter upon the permittee's premises where a regulated facility or
         activity is located or conducted, or where records must be kept under
         the conditions of this permit;

    b.   Have access to and copy, at reasonable times, any records that must be
         kept under the conditions of this permit;

    c.   Inspect at reasonable times any facilities, equipment (including moni-
         toring and control equipment), practices, or operations regulated or
         required under this permit, and

    d.   Sample or monitor at reasonable times, for the purposes of assuring
         permit compliance or as otherwise authorized by the Clean Water Act,
         any substances or parameters at any location.
                                      A-12

-------
                                        PART  II

                                        Page   13   of   19
                                        Permit No.   TX0091120
SECTION D. REPORTING REQUIREMENTS


1.  Planned Changes

The permittee shall give notice to the Director as soon as possible of any
planned physical alterations or additions to the permitted facility.

2.  Anticipated Noncompliance

The permittee shall give advance notice to the Director of any planned changes
in the permitted facility or activity which may result in noncompliance with
permit requirements.

3.  Transfers

This permit is nontransferable to any person except after notice to the
Director.  The Director may require modification or revocation and reissuance of
the permit to change the name of the permittee and incorporate such other
requirements as may be necessary under the Clean Water Act.

4.  Monitoring Reports

Monitoring results shall be reported at the intervals and in the form specified
in Section C, Paragraph C-5 (Monitoring).

5.  Compliance Schedules

Reports of compliance or noncompliance with, or any progress reports on,  interim
and final requirements contained in any compliance schedule of this permit  shall
be submitted no later than 14 days following each schedule date.  Any reports of
noncompliance shall include the cause of noncompliance, any remedial actions
taken, and the probability of meeting the next scheduled requirement.

6.  Twenty-Four Hour Reporting

The permittee shall report any noncompliance which may endanger health or the
environment.  Any information shall be provided orally within 24 hours from the
time the permittee becomes aware of the circumstances.  A written submission
shall  also be provided within 5 days of the time the permittee becomes aware  of
the circumstances.  The written submission shall contain a description of the
noncompliance and its cause; the period of noncompliance, including exact dates
and times, and if the noncompliance has not been corrected, the anticipated time
it is  expected to continue; and steps taken or planned to reduce, eliminate,  and
prevent reoccurrence of the noncompliance.  The Director may waive the written
report on a case-by-case basis if the oral report has been received within  24
hours.
                                      A-13

-------
                                         PART  II

                                         Page  14    of   19
                                         Permit No.   TX0091120
The following shall be included as  information which  must  be  reported  within  24
hours:

    a.   Any unanticipated bypass which exceeds  any effluent  limitation  in  the
         permit.

    b.   Any upset which exceeds any effluent limitation in the  permit.

    c.   Violation of a maximum daily discharge  limitation for any  of  the
         pollutants listed by the Director  in Part III of  the permit to  be
         reported within 24 hours.

7-  Other Noncompliance

The permittee shall report all instances  of noncompliance  not reported under
Section D, Paragraphs D-l, D-4, D-5, and  D-6 at  the time monitoring reports are
submitted.  The reports shall contain the information  listed  in  Paragraph D-6.

8.  Changes in Discharges of Toxic  Substances

The permittee shall notify the Director as  soon  as it  knows or has  reason to
believe:

    a.   That any activity has occurred or  will  occur  which would  result in the
         discharge of any toxic pollutant which  is not limited in  the  permit, if
         that discharge will exceed the "notification  levels" described  in  40
         CFR 122.61.

    b.   That they have begun or expect to  begin to use or manufacture as an
         intermediate or final product or byproduct any toxic pollutant  which
         was not reported in the permit application.

9.  Duty to Provide Information

The permittee shall furnish to the  Director, within a  reasonable time, any
information which the Director may  request  to determine whether  cause  exists  for
modifying, revoking and reissuing,  or terminating this permit, or  to determine
compliance with this permit.  The permittee shall also furnish to  the  Director,
upon request, copies of records required  to be kept by this permit.

10. Duty to Reapply

If the permittee wishes to continue an activity  regulated  by  this  permit after
the expiration date of this permit, the permittee must apply  for and obtain a
new permit.  The application should be submitted at least  180 days  before the
expiration date of this permit.  The Director may grant permission  to  submit  an
application less than 180 days in advance but no later than the  permit expira-
tion date.
                                       A-14

-------
                                         PART  II

                                         Page  15   of    19
                                         Permit  No.    TX0091120
11. Signatory Requirements

All applications,  reports or  information  submitted to the Director  shall be
signed and certified.

    a.   All permit applications  shall be  signed as follows:

         (1)  For  a corporation:  by  a principal executive officer  of at least
              the  level of  vice-president;

         (2)  For  a partnership or  sole proprietorship:  by a general partner or
              the  proprietor,  respectively; or

         (3)  For  a municipality, State,  Federal, or other public agency:  by
              either a principal  executive officer or ranking elected official.

    b.   All reports required  by  the  permit and other information requested by
         the Director shall be signed by  a person described above or by a duly
         authorized representative  of that person.  A person is a duly
         authorized representative  only if:

         (1)  The  authorization is  made in writing by a person described above.

         (2)  The  authorization specified  either an individual or a position
              having responsibility for the overall operation of the regulated
              facility or activity, such  as the position of plant manager,
              operator of a well  or a well field, superintendent, or position of
              equivalent responsibility.   (A duly authorized representative may
              thus be either  a named  individual or any individual occupying a
              named position.); and

         (3)  Certification.  Any person  signing a document under this section
              shall make the  following certification:

              "I certify under penalty of  law that I have personally examined
              and am familiar with the information submitted in this document
              and all  attachments and that, based on my inquiry of
              those individuals immediately responsible for obtaining the
              Information,  I believe that the information is true,  accurate, and
              complete.  I am aware that there are significant penalties for
              submitting false information, including the possibility of fine
              and imprisonment."

12. Availability of Reports

Except for data determined to be  confidential under 40 CFR Part 2,  all reports
prepared in accordance with the terms of this permit shall be available for
public inspection at the offices  of the State water pollution  control  agency
                                      A-15

-------
                                        PART  II

                                        Page  16   of   19
                                        Permit No.  TX0091120
and the Regional Administrator.  As  required by the Act,  permit  applications,
permits and effluent data shall not  be considered confidential.

13. Penalties for Falsification of Reports

The Clean Water Act provides that any person who knowingly makes any  false
statement, representation, or certification in any record or other document sub-
mitted or required to be maintained  under this permit, including monitoring
reports or reports of compliance or  noncompliance shall,  upon conviction, be
punished by a fine of not more than  $10,000 per violation, or by imprisonment
for not more than 6 months per violation, or by both.
                                      A-16

-------
                                        PART III

                                        Page   17  of  19
                                        Permit No.  TX0091120
                                   PART III
                               OTHER CONDITIONS
A.  The "daily average" concentration means the arithmetic average  (weighted by
flow value) of all the daily determinations of concentration made during a
calendar month.  Daily determinations of concentration made using a composite
sample shall be the concentration of the composite sample.  When grab samples
are used, the daily determination of concentration shall be the arithmetic
average (weighted by flow value) of all the samples collected during that
calendar day.

The "daily maximum" concentration means the daily determination of concentration
for any calendar day.

B.  The sampling points (sedimentation ponds) shall be numbered and reported as
101 through 991 as developed within the areas identified in the Mining Sequence
Map, Figure 1-2 of the consolidated application.

C.  Locations may be revised by the permittee if it becomes necessary to
eliminate or establish new holding ponds.  For any revision the permittee shall
submit appropriate maps redesignating the holding pond location.

Any revised pond or outfall location should be consistent with and fall within
the mining area boundary as defined in the applicant's State Mining Plan.

Any revised pond or outfall location shall be limited to discharging to the same
receiving body of water.

D.  Drainage which is not from an active mining area shall not be required to
meet the limitations set forth in Part I-A of this permit as long as such
drainage is not commingled with untreated mine drainage which is subject to the
limitaions in Part I-A of this permit.

E.  Methods of flow estimating shall be by the "California Pipe Method" as
described in section 7.4.2.2. of the Handbook for Monitoring Industrial
Wastewater, August 1973, U.S. Environmental Protection Agency, Technology
Transfer.
                                        A-17

-------
                                       PART III

                                       Page  18  of  19
                                       Permit No. TX0091120

F.  Effluent Limitations for Precipitation events

    (a)  Any discharge or increase in the volume of a discharge caused by
precipitation within any 24-hour period less than or equal to the 10-year,
24-hour precipitation event (or series of storms or snowmelt of equivalent
volume) may comply with the following limitations instead of the otherwise
applicable limitations:

         Affluent Limitations During Precipitation

                                      Average of daily
Pollutant or         Maximum for      values for thirty
Pollutant Property   any one day	consecutive days

Settleable Solids        0.5 ml/1         N/A
j)H	Within the range of 6.0 to 9.0 at all times

     (b)  Any discharge or increase in volume of a discharge caused by
precipitation within any 24-hour period greater than the 10-year, 24-hour event
(or series of storms or snowmelt of equivalent volume) may comply with the
following limitations instead of the otherwise applicable limitations:

          Effluent limitations During Precipitation

                                      Average of daily
Pollutant or         Maximum for      values for thirty
Pollutant Property   any one day	conseenit 1 ve days

jpJH	Within the range of 6.0 to 9.0 at all times

      (c)  The operator shall  have the burden of proof that the discharge or
Increase in discharge was caused by the applicable precipitation event described
in subsections (a) and (b).

G.  10-year 24-hour Precipitation Event

The term "10-year, 24-hour precipitation event" means the maximum 24-hour
precipitation event with a probable recurrence interval  of once 1n ten years as
defined by the National Weather Service and Technical  Paper No. 40, "Rainfall
Frequency Atlas of the U.S.," May 1961, or equivalent regional  or rainfall
probability information developed therefrom.

H.  Effluent Limitations for Reclamation Areas

     The following standards apply to discharges from reclamation areas until
SMCRA bond release
                                      A-18

-------
                                        PART III

                                        Page   19  of  19
                                        Permit No.  TX0091120


                   Effluent Limitations

                                             Average of daily
     Pollutant or        Maximum for         values for thirty
     Pollutant Property  any one day	consecutive days

     Settleable Solids         0.5 ml/1            N/A
     j>H	Within the range 6.0 to 9.0 at all times


I. Determination of Settleable Solids

     The following procedure shall be used to determine settleable solids:

     Fill an Imhoff cone to the one-liter mark with a thoroughly mixed sample.
Allow to settle undisturbed for 45 minutes.  Gently stir along the inside
surface of the cone with a stirring rod.  Allow to settle undisturbed for 15
minutes longer.  Record the volume of settled material in the cone as
milliliters per liter.  Where a separation of settleable and floating materials
occurs, do not include the floating material in the reading.

     The method detection limit for measuring settleable solids shall be
0.4 ml/1.

J. The Memorandum of Agreement executed by EPA, the Advisory Council  on Historic
Preservation, and the Texas State Historic Preservation Officer for the coal
mining operation which is the subject of this permit is hereby incorporated by
reference and expressly made a part of this permit.  The permittee shall comply
with the stipulations of such Memorandum of Agreement.

K. There shall be no discharge of dredge and fill material  into wetlands as
designated by the U.S. Army Corps of Engineers unless TUGCO obtains a Clean
Water Act, Section 404 authorization from the Corps of Engineers  for each  such
discharge, based on site specific plans.

L.  In-stream sampling, analysis and reporting shall be provided for  phenols,
ammonia (as N), pH, alkalinity, turbidity, total  suspended  solids, total
dissolved solids and mercury on a once/3 month basis  at  Stream Sampling  Stations
TUSI 1, 2 and 5, as used in the Sabine River Authority's 1977-1980 Water Quality
Monitoring Program. Grab samples shall be collected both prior to, and  during,
periods when discharges from the mine area are actually  occuring.
                                      A-19

-------
           APPENDIX B.
ADDITIONAL INFORMATION

-------
                     APPENDIX B-TABLE OF CONTENTS


Item                                                                  Page

I            Letters Concerning Early Construction Requests                  B-l

2.           TUGCO Violations Submitted to RRC                          B-10

3.           TACB Letter Exempting Martin Lake "D" Area
            from PSD                                                 B-l4

t\.           Overburden Core Analyses - 5 Cores                           B-17

5.           Agreement for Railroad Crossings                             B-29
                                    B-i

-------
I.  Letters Concerning Early Construction Requests
                     B-l

-------
                  TEXAS UTILITIES SERVICES INC.
                     2()01 HHYAN TWVfcH • DA1.LAS. TKXAS 7r,2Ol
                        June 11, 1982
Mr. Clinton Spotts
Regional EIS Coordinator
U.S. Environmental Protection Agency
1201 Elm Street
Dallas, Texas  75270
                                    Martin Lake Mining Area "D"
                                    Environmental Impact Statement
                                    Railroad Start of Construction
Dear Mr. Spotts:
The purpose of this letter is to seek concurrence for start of construction
of the railroad that will transport lignite from our proposed Martin Lake
Area "D" lignite mine to the existing Martin Lake Steam Electric Station.
An environmental impact statement is currently under preparation to obtain
an NPDES permit for the mine.  The EIS preparation schedule calls for
review and effective permit date of March 22, 1983.  Construction of the
mine will begin immediately upon receipt of the NPDES period in order to
maintain a reliable fuel supply required for continued operation of the
existing three generating units at Martin Lake Steam Electric Station.

Start of construction for the railroad will be required earlier than
for the mine so that the railroad can be in service by the time the mine
begins producing lignite.  To meet this schedule requirement, construction
of the railroad must begin with preliminary clearing on September 1, 1982.

Based upon our review of the applicable regulations and definitions per-
taining to NPDES permit requirements, we believe that the railroad is
an off-site transportation facility that is separate from the NPDES new
source mine.  The railroad has no water discharges and is not included in
the definitions of "coal mine" or "active mining area" in the EPA Effluent
Guidelines for Coal Mining (40 CFR 434).  Since the railroad is a separate,
off-site facility that does not require an NPDES permit, we believe the
on-site construction commencement requirements of 122.66(c)(4)(i) do not
apply to the railroad start of construction.

We recognize that the NEPA regulations require the EIS to address all
the environmental impacts resulting from construction of the mine includ-
ing secondary impacts from construction of the railroad.  The impacts of
the railroad have been addressed in the Preliminary Draft EIS and no
significant or irreversible adverse environmental impacts have been
identified.  The following factors can be used in justifying no significant
or irreversible impact:
                                     B-2

-------
Mr. Clinton Spotts
U.S. EPA
June 11, 1982
Page 2.
    1.  The selected rail route passes through a rural, low populated
        area.

    2.  No endangered species or habitat will be affected.

    3.  Overpasses will be constructed at all public road crossings so
        that there will be no effect on automobile traffic.

    A.  There will be no adverse effect on archaeological or historical
        National Register or eligible properties.  A plan has been
        developed and will be implemented to protect and gather all
        historic information from the one potential National Register
        eligible site located on the railroad right-of-way.

    5.  The Corps of Engineers has reviewed the proposed rail route and
        determined that the rail crossings occur above the headwaters of
        area streams and are therefore authorized by a nationwide permit.
        Crossings will meet the requirements of 33 CFR 323.4-2(b).

In summary, we request that EPA concur in the start of construction based
on either (1) the railroad is a separate off-site transportation facility
from  the NPDES permitted mine or (2) a determination that start of con-
struction of the railroad will not cause a significant irreversible adverse
impact.

If there are any questions about this request or if any additional information
is required, please contact me or Mr. Dick Robertson.

                                    Very truly yours,
                                               nan

JRRrjl
                                     B-3

-------
                UNITED S'   ES ENVIRONMENTAL PROTECTION A
Mr. Howard B. Coffman
Texas Utilities Services, Inc.
2001 Rryan Tower
Dallas, Texas  75201

Dear Mr. Coffman:

This letter 1s 1n response to your request for concurrence on early
construction of the railroad to be used to transport lignite froin the
proposed Martin Lake "D" mina north of Henderson, Texas to the Martin
Lake Steam Electric Station.  We have determined that the area proposed
for location of the railroad 1s part of the new source project site, and
the regulations, 40 CFR Part 122.6 (c)(4)(l), do apply.

Based on review of all the Information submitted, we offer our approval
to proceed with the railroad construction provided that the following
conditions are met:

     1.   Clearance 1s provided from the U.S. Army Corps of Engineers,  Fort
          Worth District, regarding construction 1n wetlands;

     2.   Measures are developed for minimizing of effects on the prime
          farmland soils so that no irreversible Impact will occur on
          these;

     3.   The mitigation plan for protecting the significance of the
          Walling Cabin, as related to the archeologlcal survey of the
          site and recordatlon and relocation of the cabin property, is
          completed before any construction begins.

We resarve the right to withdraw this authorization should further
Information Indicate the conditions will not be met or that construction
work will cause significant environmental Impact.

-------
     In the event the final HS reveals that your project cannot be under-
     taken as presently planned, we are Informing you that any construction
     activities commenced on the proposed railroad corridor are at your own
     risk.  If you have any questions, please contact Clinton Sootts at (214)
     757-2716.

     Sincerely yours,

/s/ Framces E. Phillips for

     irlck WhHtlngton, P.E.
             Administrator
                                             B-5

-------
         UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                                  REGION VI

                    iNTERFlRST TWO BUILDING. I2OI ELM STREET
                             DALLAS.TEXAS 7527O
August 1, 1983


Mr. L. F. Fikar
Texas Utilities Generating Co.
2001  Bryan Tower
Dallas, Texas  75201-3050

Dear Mr.  Fikar:

We have reviewed your June 8, 1983, request for approval  to begin construction
at the site of the loading station and dragline erection  area associated
with the Martin Lake "0" area lignite mine project.  The  recent application
made by TUGCO to the Railroad Commission of Texas for construction at"this
particular site was obtained and reviewed in addition to  information supplied
to us for the EIS.

Based on  our review of the information available, we offer our approval  to
proceed with construction at the designated site in accordance with variance
procedures in 40 CFR 122.66(c)(4)(i), provided the following conditions  are
met:

1.  Site  specific measures are carried out to minimize effects on the prime
    farmland soils so that no irreversible impact will occur to them.  The
    measures are to include removal of a minimum of the top four inches  of
    topsoi 1  in any area that is to be cut or covered with fill and placement
    of that soil at one or more locations in the loading  station area to be
    available for future use.  Exposed areas should be revegetated to control
    erosion immediately as construction activities in an  area are completed.

2.  The appropriate stipulations of the Memorandum of Agreement for protection
    of cultural resources between EPA, the Texas State Historic Preservation
    Officer and the Advisory Council on Historic Preservation are complied
    with to ensure protection of archeological or historic properties that
    may be discovered during earth disturbance.

We reserve the right to withdraw this authorization should further information
indicate  that the conditions will not be met or that construction will  causo
other significant environmental impact.  In such an event, TUGCO shall
immediately cease construction activities and take measures to restore the
affected  environment.
                                        B-6

-------
                                     -2-

You should be aware that although this construction may include construction
of a sedimentation pond(s), you are not authorized to discharge from a pond to
any surface water without a final NPDES permit.

EPA's approval  for this limited construction does not obligate EPA in. any
way regarding the final NPDES decision for the Martin Lake D Area mine project.
Should the NEPA review underway by EPA, Region 6, result in a determination
that the NPDES permit is denied or that the proposed facility should not be
constructed at the proposed location, TUGCO shall return the area disturbed
to its approximate original contour and revegetate the area to the satisfaction
of EPA.

We ask that you keep us apprised of your activities relative to this author-
ization.  If you have any questions, please contact Clinton Spotts at 767-2716.

Sincerely yours,
Dick Whittington, P.E.
Regional  Administrator

cc: Howard Coffman
                                       B-7

-------
                  TKXAS rriUTIKS SKKYIU.S  i.V.
                     • 'i n M m n i, x n »\\ i i { 11 \ i i \*- ' i \ '.    •'  ' >  > >

                          June 8,  1983
                                                                   -  i-O
                                                                  6  E-b
Mr. Clinton Spotts
Regional EIS Coordinator
U.S. Environmental Protection Agency
1201 Elm Street
Dallas, Texas  75270
                                    Martin Lake Mining Area "D"
                                    Environmental Impact Statement
                                    Loading Station Start of Construction
Dear Mr. Spotts:
With this letter we are requesting approval to begin initial construction
activities at the site of the loading station and dragline erection area
for our proposed Martin Lake Mining Area "D" project.  We seek this appro-
val based on the provisions of 40 CFR 122.66(4)(i) which allow certain
construction activities prior to obtaining a final NPDES permit when the
Administrator determines that the construction will not cause significant
or irreversible environmental Lmpact.

We believe this determination can be made based on the limited acreage
involved for the proposed construction as well as the data and analysis
of impacts that have already been evaluated and commented on by agencies
and the public in the ongoing preparation of the Environmental Impact
Statement for the project.

The proposed construction would be limited to Company owned property within
the boundaries of the 428 acre site designated as the loading station and
dragline erection area.  Proposed facilities as described in the DEIS and
Railroad Commission Permit Application would only occupy 140 acres within
the larger boundary.  The environmental review of this area has indicated
there are no wetlands, sensitive areas, national register archaeological
sites or endangered species in the aroa.  No mining or handling of lipnite
would be conducted before obtaining the NPDES permit.  No work would begin
until authorization is provided by the Railroad Commission.

The projected date for completion of the final EIS and issuance of the NPDES
permit is still several months away.  We have delayed the start of the pro-
posed work for several months and additional delay would jeopardize the entire
project schedule and projected fuel supply for the Martin Lake Power Plant.
We seek to begin by July 1, 1983.  This would allow us to have an area and
facilities prepared to receive dragline parts scheduled to arrive in December
of this year.  There would be an environmental benefit in starting early
enough in the year to allow growth of vegetation on some of the disturbed
areas prior to the winter season.
                                   B-8

-------
Mr. Clinton Spotts
U.S. EPA
June 8, 1983

Page 2.
We have previously submitted the drawings, maps and descriptions of the
loading station area and facilities.

If you need additional information, or if there are any questions,
please call me or Mr. Dick Robertson.

                                              Very truly yours,
JRRtjl
                                   B-9

-------
2.  TUGCO Violations Submitted to RRC
              B-IO

-------
DATE:  August 6,  1979

AUTHORITY:  Texas Railroad Commission,  Surface Mining Division

DESCRIPTION OF VIOLATION:  Failure to meet water quality standards and
   effluent limitations at pond B-l-D.

DESCRIPTION OF ADMINISTRATIVE OR JUDICIAL PROCEEDINGS:

   None

STATUS OF PROCEEDINGS:  N/A

ABATEMENT ACTION TAKEN BY THE APPLICANT:  B-l-D sediment pond enlarged to meet
   the 10-year, 24-hour.,rainfall event.


DATE:  August 6, 1979

AUTHORITY:  Texas Railroad Commission, Surface Mining Division

DESCRIPTION OF VIOLATION:  Failure to use best technology on "C" haul road
   adding excessive suspended solids to Pin Oak and Prairie Creeks.

DESCRIPTION OF ADMINISTRATIVE OR JUDICIAL PROCEEDINGS:

   None

STATUS OF PROCEEDINGS:  N/A

ABATEMENT ACTION TAKEN BY THE APPLICANT:  Hay bale and  rock check dams
   installed  in  roadside ditches.  Reroute water  (where possible) through
   sediment ponds.


DATE:  October 16,  1979

AUTHORITY:  Office  of  Surface Mining Reclamation  Enforcement

DESCRIPTION OF VIOLATION:  Discharge from disturbed  area  failed  to mee-t
   minimum effluent limitations.

DESCRIPTION  OF ADMINISTRATIVE  OR  JUDICIAL PROCEEDINGS:

   None

STATUS OF PROCEEDINGS:   Completed.

ABATEMENT ACTION TAKEN BY  THE  APPLICANT:  Treatment  system installed.
                                   B-ll

-------
DATE:  October 16, 1979

AUTHORITY:  Office of Surface Mining Reclamation Enforcement

DESCRIPTION OF VIOLATION:  Exceeding discharge limitations.

DESCRIPTION OF ADMINISTRATIVE OR JUDICIAL PROCEEDINGS:

   $2300 assessment proposed.  No penalty following assessment conference.

STATUS OF PROCEEDINGS:  Assessment conference scheduled.

ABATEMENT ACTION TAKEN BY THE APPLICANT:  Treatment pond B-5 installed to
   treat water from B-2 and B-3 sediment pond.


DATE:  November 4, 1979

AUTHORITY:  Texas Railraod Commission, Surface Mining Division

DESCRIPTION OF VIOLATION:  Failure to meet water quality standards and
   effluent limitations at pond B-4.

DESCRIPTION OF ADMINISTRATIVE OR JUDICIAL PROCEEDINGS:

   None

STATUS OF PROCEEDINGS:  Not  applicable.

ABATEMENT ACTION  TAKEN  BY THE APPLICANT:  Water treatment  system installed.


DATE:  May  29,  1980

AUTHORITY:  Texas Railroad  Commission

DESCRIPTION OF  VIOLATION:   Drainage  from a  new  scraper  pit spoil  is  leaving
    the permit area without  passing  through  a sediment pond.

 DESCRIPTION OF  ADMINISTRATIVE OR JUDICIAL PROCEEDINGS:

    None

 STATUS OF-PROCEEDINGS:   Not applicable.

 ABATEMENT ACTION TAKEN BY THE  APPLICANT: Drainage control facilities
    constructed.
                                  B-12

-------
DATE:  August 26, 1980

AUTHORITY:  Texas Railroad Commission

DESCRIPTION OF VIOLATION:  Excavation within 100 feet of a pipeline during
   exploration activity.

DESCRIPTION OF ADMINISTRATIVE OR JUDICIAL PROCEEDINGS:

   None.

STATUS OF PROCEEDINGS:  Not applicable.

ABATEMENT ACTION TAKEN BY THE APPLICANT:  Exploration activities within 100
   feet of pipeline were discontinued.


DATE:  July 14, 1981

AUTHORITY:  Texas Railroad Commission, Surface Mining Division

DESCRIPTION OF VIOLATION:  Failure to cover acid-forming materials.

DESCRIPTION OF ADMINISTRATIVE OF JUDICIAL PROCEEDINGS:

   None

STATUS OF PROCEEDINGS:  N/A

ABATEMENT ACTION TAKEN BY THE APPLICANT:  Chemical treatment.
                                   B-13

-------
3.  TACB Letter Exempting Martin Lake "D" Area from PSD
                       B-14

-------
                                 6330 HWY. 290 EAST
                                AUSTIN, TEXAS 78723

JOHN L. BLAIR                         51^^11                 VITTORIO K. ARGENTO, P. E.
Chairman                             XP=3X,                         BOB G. BAILEY
CHARLES R.JAYNES                    /§S=^K\                       FRED HARTMAN

Vice Chairman                        / M^W\                   D- JACK KILIAN- M- D-
                                 OltT^ NOT/               OTTO R. KUNZE, Ph. D., P. E.

BILL STEWART. P. E.                    \?£&&7                       FRANK H' LEWIS
Executive Director                        X^TT^X                       R. HAL MOORMAN
   March  8,  1983
                                                                      m

   Mr.  L.  F.  Fikar                                               JUS I
   Vice President
   TEXAS UTILITIES SERVICES, INCORPORATED
   2001 Bryan Tower
   Dallas,  Texas  75201

                                      Re:  Permit Exemption
                                           Permit Application No.  C-9243
                                           Lignite Train  Loading Facility
                                           Henderson,  Rusk County

   Dear Mr. Fikar:

   This is in response to your permit application, Form PI-1, concerning
   the  proposed construction of a lignite train loading facility.   We
   understand that fugitive particulate matter emissions  from this
   facility are estimated to be 18.2 tons per year.

   Pursuant to Section 3.27(a) of the Texas Clean Air  Act, I  have  deter-
   mined to exempt your proposed facility from the permit procedures of
   this Agency because it will not make a significant  contribution of air
   contaminants to the atmosphere if constructed and operated as described
   in your application.  You are reminded that regardless of  whether a con-
   struction  permit is required, this facility must be in compliance with
   all  Rules  and Regulations of the Texas Air Control  Board  at all times.

   The  issuance of this exemption is contingent upon the  condition that
   this facility shall comply with all requirements of Environmental
   Protection Agency Regulations on Standards of Performance  for New
   Stationary Sources promulgated for coal preparation plants in Title 40
   Code of Federal Regulations Part 60 (40 CFR 60), Subparts  A and Y.
                   Celebrating 150 Years of Texas Independence 1836 • 1986

-------
Mr. L. F. Fikar                     -2-              March 8, 1983
Thank you for providing the information necessary for our  evaluation of
your proposal.  If you have further questions concerning  this  exemp-
tion, please contact Mr. James E. Crocker of our Permits  Division.
             t P.E.
Executive Director

cc:  Mr. Richard Leard, P.E., Regional Supervisor, Tyler
                                    B-16

-------
4.  Overburden Core Analyses - 5 Cores
               B-17

-------
                                   CORE LABORATORIES,  INC.
                                          ANALYTICAL REPORT

                                                13 HAY 81

                                      DISTRIBUTION OF FINAL REPORTS

  COPIES SENT TO:

ESPEY,  HUSTON AND ASSOCIATES, INC.
P.O.  BOX 519
AUSTIN, TEXAS  78704
ATTN:   MR.  RAY RISNER
TEXAS  UTILITIES GENERATING COMPANY
P.O.  BOX 948
FA1RFIELD.  TEXAS  75B40
ATTN:   MR.  I.EGETT CARRETT

  CLIENT I.D.:
  M810U2
  P.O.  NO.  G90-0533
  OVERDURDEN PROJECT ANALYSTS FOR TEXAS UTILITIES GENERATING COMPANY
  MILL  CREEK PROJECT

HOLE  1128   E1IA 5   0'    64.1'
HOLE  562    E!IA 2   0'    87.2'
HOLE  100'J   EI1A 1   0'  - 131.4'
HOLE 972    EI1A 3   0'  - 82.2"
HOLE 964    EI1A 4   0'    122.5'
                                               B-18

-------
         ESPEY,  HUSTON AND ASSOCIATES, INC.
         TEXAS UTILITIES GENERATING COMPANY
         MILL CHEEK OVERBURDEN PROJECT
         MS1002
                               COMPOSITE LIST OF SAMPLES
CD

VO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
13
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
1128
1128
1123
1128
1128
1123
1123
562
562
562
562
562
562
562
562
562
562
562
1009
1009
1009
1009
1009
1009
1009
1009
1009
1009
1009
1009
1009
1009
972
972
972
EHA
EHA
EHA
EHA
EHA
EHA
FHA
EHA
FHA
EHA
EHA
EHA
EHA
FHA
FHA
FHA
EHA
EHA
EHA
FHA
EHA
EHA
EHA
EHA
EHA
FHA
FHA
FHA
EHA
EHA
EHA
EHA
FHA
EHA
EHA
5-1
5-2
5-3
5-4
5-5
5-6
5-7
2-1
2-2
2-3
2-4
2-5
2-6
2-7
2-8
2-9
2-10
2-11
1-1
1-2
1-3
1-4
1-5
1-6
1-7
i-a
1-9
1-10
1-11
1-12
1-13
1-14
3-1
3-2
3-3
0-11.
11.
28
40
49
51
.
.

,
54.
0'
10
14
17
21
24
34
50
63
74
75
0'
3.
16
29
33
41
51
59
65
78
92
a
0
0
7
0
3
1
1
t
'
1
1
-10
.
.
.
.
.
.
.
.


0
5
5
0
0
5
0
0
0
3
•
1
'
'
'
1
1
1
1
1
-8.
0
.
.
.
.
.
.
.
.
.
t
0
2
5
0
4
7
7
0
0
107.
119.
121.
O1
7.
10
-
'
1
1
1
1
1
t
t
1
2
6
5
-7.
6
.
8'
-28.
-40.
-47.
-51.
-54.
-64.
.0'
-14.
-17.
-21.
-24.
-34.
-45.
-63.
-64.
-75.
-87.
0'
16.0
-29.
-33.
-41.
-48.
-59.
-65.
-78.
-92.
-107

0'
0'
0'
0'
3'
1'

5'
5'
0'
0'
5'
5'
0'
6'
3'
2'

1
2'
5'
0'
0'
7'
7'
0'
0'
.2'
'-109.2'
'-121.5'
'-131.4'
6'

'-10. r
1
1
-11.
2 *
ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
MILL GREEK OVERBURDEN PROJECT
MS 1002
                                                                                                                                COMPOSITE LIST OF SAMPLES  (CONT.)
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
S3
34
LI
L2
L3
L4
L5
L6
SI
32
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLS 964
HOLE 964


HOLE 1128
HOLE 562
HOLE 1009
HOLE 972
HOLE 972
HOLE 964


EHA 3-4
EHA 3-5
EHA 3-6
EHA 3-7
EHA 3-3
EHA 3-9
EHA 3-10
EHA 3-11
EHA 3-12
EHA 3-13
EHA 4-1
EHA 4-2
EHA 4-3
EHA 4-4
EHA 4-5
EHA 4-6
EHA 4-7
EHA 4-8
EHA 4-9
EHA 4-10
EHA 4-11
EHA 4-12


LI
LI
LI
LI
U
LI


11.2'-14.2'
15.2'-20.7'
20.7'-36.1'
36.1'-52.3'
54.2'-55.7'
55.7'-59.0'
59.0'-61.4'
68.6'-69.5'
69.5'-75.0'
75.0'-82.2'
O'-IO.O1
10.0'-22.0'
22.0'-35.4'
35.4'-47.8'
47.3'-54.4'
56.6'-60.3'
60.3'-75.1'
75.1'-90.a'
90.8'-104.7'
104.7'-105.6'
112.1'-114.0'
114.0'-122.5'


47.0'-49.7'
64.6'-74.0'
109.2'-119.6'
52.3'-54.2'
6l.4'-68.6'
105.6'-H2.1'



-------
ESPEY,  HUSTON AND ASSOCIATES,  INC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
CORE LABORATORIES,  INC.
       ANALYTICAL REPORT
        DATE:     27 MAR 81
        ANALYST:  JMA/ETK
FILE NO.:  MB 1002, pg. 1
LOCATION:  TYLER COAL LAB
SAMPLE
NUMBER
1
2
3
4
5
6
7
8
9
10
10 DUP
11
12
13
14
15
16
CLIENT I.D.
HOLE 1128 EHA 5-1 O'-ll.S1
HOLE 1128 EHA 5-2 11.8'-28.0'
HOLE 1128 EIIA 5-3 28.0' -40.0'
HOLE 1128 EHA 5-4 40.0'-47.0'
HOLE 1128 EHA 5-5 49.7'-51.0'
HOLE 1128 EHA 5-6 51.0'-54.3'
HOLE 1128 EHA 5-7 54.3'-64.1'
HOLE 562 EHA 2-1 O'-IO.O'
HOLE 562 EIIA 2-2 10.0'-14.5'
HOLE 562 EHA 2-3 14.5'-17.5'
HOLE 562 EIIA 2-3 14.5'-17.5'
HOLE 562 EHA 2-4 17.5'-21.0'
HOLE 562 EHA 2-5 21.0'-24.0'
HOLE 562 EHA 2-6 24.0'-34.5'
HOLE 562 EHA 2-7 34. 5 '-AS. 5'
HOLE 562 EHA 2-8 50.0'-63.0'
HOLE 562 EHA 2-9 63.0'-64.6'
B!i*
4.5
4.7
5.0
5.6
4.4
4.4
5.8
4.2
3.9
3.7
3.7
3.1
3.8
3.1
4.3
4.3
4.1
COND*
32
18
25
21
317
213
317
53
62
94
93
718
82
823
416
291
374
«pll AND CONDUCTIVITY ON A 1:1 HATER AND SOIL MIXTURE
CONDUCTIVITY EXPRESSED AS Umlioa @ 25°C
ALL OTHER ANALYSIS PERFORMED ON 1 : 3 HATER EXTRACT OF Ala
ppm
Ca
2.4
2.0
2.0
1.9
21
19
19
1.9
1.7
2.8
3.3
9.2
2.4
30
25
11
26
ppm
0.7
0.4
0.4
0.4
11
10
9.5
0.9
0.8
1.4
1.2
4.2
1.1
20
24
8.6
18
ppra
Ha
14
12
18
231
29
21
26
8.7
11
9.6
9.3
12
21
20
26
26
32
ppm
K
2.7
2.0
1.6
1.1
19
11
15
5.4
9.0
11
11
22
4.3
18
29
25
30
ppm
Cl
21
15
17
18
12
9
5
24
29
25
25
11
27 •
22
20
15
18
ppra
1ICO
0
3
5
7
0
0
4
0
0
0
0
0
0
0
0
0
0
ppra
J C03
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
ppm
50^
<10
<10
<10
171
146
160

-------
                                CORE  LABORATORIES,  INC.
                                       ANALYTICAL REPORT
ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
DATE: 27 MAR 81
ANALYST: JMA/ETK
FILE NO.: M81002, pg
LOCATION: TYLER COAL
. 3
LAB
MILL CREEK OVERBURDEN PROJECT
SAMPLE
NUMBER
32
33
34
35
36
37
38
39
40
41
42
42 DUP
43
44
45
46
47
HOLE 1009
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 972
HOLE 964
HOLE 964
CLIENT I
EHA 1-14
EHA 3-1
EIIA 3-2
EIIA 3-3
EIIA 3-4
EHA 3-5
EIIA 3-6
EIIA 3-7
EIIA 3-8
EIIA 3-9
EIIA 3-10
EIIA 3-10
EIIA 3-11
EIIA 3-12
EIIA 3-13
EIIA 4-1
EIIA 4-2
.D.
,21. 5'-. 31. 4"
0'-7.6'
7.6--10.1'
10.1--11.2'
11.2--14.2'
15.2'-20.7'
20.7'-36.1'
36.T-52.3'
54.2--55.71
55.7'-59.0'
59.0 '-6 1.4'
59.0'-61.4'
68. 6 '-69. 5'
69.5'-75.0'
75.0'-82.2'
O'-IO.O1
10.0'-22.0'
pll*
7.7
4.5
4.4
3.7
6.5
7.4
8.1
8.3
7.8
8.3
7.4
7.4
7.2
8.1
8.4
5.1
5.1
COND*
451
44
80
580
755
539
652
637
1225
789
853
867
745
406
629
92
89
ppm
Ca
41
2.0
2.8
78
26
39
57
53
91
54
59
59
41
20
26
2. 1
1.3
ppm
16
1.2
1.6
39
16
20
26
24
41
22
26
25
19
7.0
10
0.3
0.1
ppm
Na
28
11
12
34
32
34
47
49
77
70
76
76
78
57
88
28
28
PP">
K
21
6.9
12
28
22
19
20
19
41
35
32
31
31
18
20
9.0
1.5
ppm
Cl
25
14
13
15
31
8
11
15
12
9
24
25
39
57
42
27
22
ppm
HC03
52
0
0
0
24
71
124
105
315
235
314
312
213
118
200
a
8
ppm
COj
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
ppm
SO/i
190
21
45
495
216
198
249
234
294
155
134
135
132
84
63
39
50
*pH AND CONDUCTIVITY ON A 1:1  WATER AND SOIL MIXTURE
 CONDUCTIVITY EXPRESSED AS Umlioa @ 25°C
 ALL OTHER ANALYSIS PKI1FORMED  ON 1:3 WATER EXTRACT OF AIR DRIED SAMPLE
  ESPEY, HUSTON AND ASSOCIATES,  INC.
  TEXAS UTILITIES GENERATING COMPANY
  MILL CREEK OVERBURDEN PROJECT
CORE  LABORATORIES, INC.
       ANALYTICAL REPORT
        DATE:     27 MAR 81
        ANALYST:  JMA/ETK
FILE NO..  M81002, pg.  4
LOCATION:  TYLER COAL LAII
SAMPLE
NUMBER
48
49
50
50 DUP
51
52
53
54
55
56
57
S3
S4
CLIENT I.D. pll*
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE


964
964
964
964
964
964
964
964
964
964
964


EHA 4-3
EIIA 4-4
EIIA 4-5
EIIA 4-5
EIIA 4-6
EIIA 4-7
EIIA 4-8
EIIA 4-9
EIIA 4-10
EIIA 4-11
EIIA 4-12


22.0'-35.4' 4.4
35.4'-47.8' 3.0
47.8'-54.4' 4.2
47.8'-54.4' 4.2
56.6'-60.3' 3.3
60.3'-75.1' 4.2
75.r-90.8' 4.4
90.8'-104.7' 5.2
104.7'-I05.6' 4.7
112.r-114.0' 5.2
114.0'-122.5' 7.3
6.2
4.2
COND*
75
926
41
38
395
104
71
34
44
458
499
540
210
ppm
Ca
1.1
16
1.3
1.1
9.2
1.1
1.1
1.3
2.6
31
30
46
7.2
ppra
0.2
8.4
0.5
0.4
2.7
1.4
0.9
0.8
1.3
14
12
23
5.6
ppm
Na
22
19
12
13
17
27
27
20
11
32
38
22
22
ppm
K
3.3
44
4.1
4.4
21
9.0
8.4
4.6
4.7
20
17
33
22
ppm
Cl
25
12
23
22
17
19
18
23
13
•15
9
20
19
ppra
IIC03
3
0
3
3
0
2
2
5
2
11
71
30
0
ppm
CO 3
0
0
0
0
0
0
0
0
0
0
0
0
0
ppm
28
1125
14
14
332
61
45
12
24
196
143
263
102
   •pll AND CONDUCTIVITY ON A 1:1 WATER AND SOIL MIXTURE
   CONDUCTIVITY EXPRESSED AS llnilioa @ 25°C
   ALL OTHER ANALYSIS PERFORMED ON 1:3 WATER EXTRACT OF AIR DRIED SAMPLE
                                                   B-21

-------
ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
HILL CREEK OVERBURDEN PROJECT
CORE  LABORATORIES, INC
       ANALYTICAL REPORT
        DATE:     27 MAR 81
        ANALYST:  JMA/ETK
FILE NO..  H8I002, |)g.  5
LOCATION:  TYLER COAL LAI)
SAMPLE
NUMBER CLIENT I.D.
1 HOLE 1128 EHA 5-1 O'-ll.B'
2 HOLE 1128 EI1A 5-2 11.8'-28.0'
3 HOLE 1128 EIIA 5-3 28.0'-40.0'
4 HOLE 1128 EHA 5-4 40.0'-47.0'
5 HOLE 1128 EHA 5-5 A9.7'-5l.O'
6 HOLE 1128 EHA 5-6 51.0'-54.3'
7 HOLE 1128 EIIA 5-7 54.3'-64.1'
8 HOLE 562 EHA 2-1 O'-IO.O'
9 HOLE 562 EIIA 2-2 10.0'-14.5'
10 HOLE 562 EIIA 2-3 14.5'-17.5'
10 DIIP HOLE 562 EIIA 2-3 14.5'-17.5'
11 HOLE 562 EHA 2-4 17.5'-21.0'
12 HOLE 562 EHA 2-5' 2).0'-24.0'
13 HOLE 562 EHA 2-6 24.0'-34.5'
14 HOLE 562 EHA 2-7 34.5'-45.5'
15 HOLE 562 EIIA 2-8 50.0'-63.0'
16 HOLE 562 EHA 2-9 63.0'-64.6'
Z TOTAL Z TOTAL
SULFUR SULFUR*
<0.0l <0.31
<0.01 <0.31
<0.01 <0.31
<0.01 <0.3l
0.75 23.4
0.36 11.3
0.47 14.7
0.01 0.31
0.02 0.62
0.02 0.62
0.02 0.62
1.37 42.8
<0.01 <0.31
2.16 67.5
1.53 47.8
0.70 21.9
1.10 34.4
NEUTRALIZATION
POTENTIAL*
-0.53
5.00
1.25
-0.95
0
2.73
3.80
-3.05
-1.70
-0.75
-1.03
-4.25
-0.48
-1.75
9.25
4.00
0.78
CATION EXCIIANCF.
CAPACITY**
9.53
1.17
3.68
0.61
15.2
4.51
11.1
13.3
8.44
4.00
3.94
9.26
3.25
4.78
13.1
16.8
16.4
EXCIIANGEAnl
CATIONS*'
2.21
0.76
1.14
0.48
8.43
2.70
8.01
1.13
0.51
0.38
0.33
0.36
0.33
0.61
5.29
6.89
6.10
*CaC03 EQUIVALENT: TONS PER 1,000 TONS MATERIAL
**M[|.LIEQUIVALENTS PER 100 CRAMS
CORE

ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
SAMPLE
NUMBER CLIENT I.D.
17 HOLE 562 EIIA 2-10 74.0'-75.3
18 HOLE 562 EIIA 2-11 75.3'-87.2'
19 HOLE 1009 EIIA 1-1 0'-8.0'
20 HOLE 1009 EIIA 1-2 8.0'-16.0'
20 DUP HOLE 1009 EIIA 1-2 8.0'-16.0'
21 HOLE 1009 EHA 1-3 16.0'-29.2'
22 HOLE 1009 EIIA 1-4 29.2'-33.5'
23 HOLE 1009 EHA 1-5 33.5'-41.0'
24 HOLE 1009 EHA 1-6 41.0'-48.0'
25 HOLE 1009 EIIA 1-7 51.4'-59.7'
26 HOLE 1009 EIIA 1-8 59.7'-65.7'
27 HOLE 1009 EHA 1-9 65.7'-78.0'
28 HOLE 1009 EIIA 1-10 78.0'-92.0'
29 HOLE 1009 EHA 1-11 92.0'-107.2'
30 HOLE 1009 EIIA 1-12 107. 2'-109.2'
30 DUP HOLE 1009 EHA 1-12 107.2'-109. 2 '
31 HOLE 1009 EIIA 1-13 1 19.6'-121.5'
LABORATORIES,
ANALYTICAL REPORT
DATE: 27 MAR 81
ANALYST! JMA/ETK

Z TOTAL Z TOTAL
SULFUR SULFUR*
0.10 3.13
0.04 1.25
0.02 0.62
<0.01 <0.31
<0.0l <0.31
0.04 1.25
1.28 40.0
2.74 85.6
0.36 11.3
1.43 44.7
1.82 56T9
0.12 3.75
0.04 1.25
1.18 36.9
1.33 41.6
1.28 40.0
0.14 4.38
INC.





FILE NO.: M81002, pg. 6
LOCATION: TYLER COAL I.AB

NEUTRALIZATION
POTENTIAL*
2.78
4.50
-1.25
-2.28
-2.25
-2.50
-1.25
-2.50
0.05
-0.75
0
0.30
0.50
5.38
5.38
5.75
4.00

CATION EXCHANGE
CAPACITY**
11.2
13.2
9.66
8.42
8.46
9.03
7.50
12.9
2.40
8.55
10.8
1.13
0.65
11.7
17.7
17.8
9.33

EXCHANGEABLE
CATIONS**
6.18
9.23
0.94
0.56
0.51
0.43
0.59
3.13
0.51
3.01
3.36
0.46
0.43
8.35
15.5
14.9
7.14
     *CaC03 EQUIVALENT:   TONS PER 1,000 TONS MATERIAL
    **MI!.I.TEOIIIVAI.ENTS PER  10O CRAMS
                                                     B-22

-------
ESPEY,  HUSTON AMD ASSOCIATES, INC.
TEXAS UTILITIES GENERATING  COMPANY
HILL CREEK OVERBURDEN PROJECT
                                    CORE  LABORATORIES,  INC.
                                           ANALYTICAL REPORT
                                             DATE:     27 MAR 81
                                             ANALYST:   JMA/ETK
                                                                          FILE NO.,  H81002, pg.  7
                                                                          LOCATION:  TYLER COAL I.AB
SAMPLE
NUMBER

 32

 33

 34

 35

 36

 37

 38

 39

 40

 41

 42

 42 DUP

 43

 44

 45

 46

 47
         CLIENT 1.1).

HOLE 1009  EIIA 1-14

HOLE 972   EIIA 3-1

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 972

HOLE 964
                               0'-7.6'
                      EHA 3-2

                      EIIA 3-3

                      EIIA 3-4

                      EIIA 3-5

                      EIIA 3-6

                      EIIA 3-7

                      EHA 3-8

                      EIIA 3-9
            HOLE 964
          lO.r-11.21

          11.2'-14.2'

          15.2'-20.7'

          20.7'-36.1'

          36.T-52.3'

          54.2'-55.7'

          55.7'-59.0'

EIIA 3-10   59.0'-61.4'

EIIA 3-10   59.0'-61.4'

EHA 3-11   68.6'-69.5'

EIIA 3-12   69.5'-75.0'

EHA 3-13   75.0'-82.2'

EHA 4-1    O'-IO.O1

EHA 4-2    10.0'-22.0'
X TOTAL
SULFUR
0.03
0.03
0.04
3. 19
1.28
0.42
0.27
0.17
0.33
0.12
0.19
0.20
0.22
0.18
0.03
<0.01
<0.01
I TOTAL
SULFUR*
0.94
0.94
1.25
99.7
40.0
13.1
8.44
5.31
10.3
3.75
5.93
6.25
6.88
5.63
0.94
0.31
0.31
NEUTRALIZATION
POTENTIAL*
5.25
-1.50
-1.25
-2.75
3.63
12.7
14.2
15.0
6.85
4.50
8.20
8.13
10.3
5.50
10.0
0
-1.78
CATION EXCHANGE
CAPACITY**
7.20
8.85
7.07
36.9
23.4
10.5
9.25
10.3 '
25.9
21.3
31.7
31.7
22.5
8.66
23.0
10.0
9. 11
EXCHANGEABLE
CATIONS**
6.56
1.14
1.52
3.43
20.1
9.47
9.60
10.3
26.6
22.3
28.3
27.8
18.8
8.08
20.6
3.92
1.37
  *CaCOj EQUIVALENT:  TONS PER 1,000 TONS MATERIAL
 **MILI.IEQIUVAI,ENTS PER 100 GBAMS
   ESPEY, HUSTON AND ASSOCIATES,  INC.
   TEXAS UTILITIES GENERATING COMPANY
   MILL CREEK OVERBURDEN PROJECT
                                       CORE  LABORATORIES,  INC.
                                              ANALYTICAL REPORT
                                               DATE:     27 MAR 81
                                               ANALYST:   JMA/ETK
                                                                            FILE NO.:  M81002,  pg.   8
                                                                            LOCATION:  TYLER COAL LAB
SAMPLE
NUMBER
48
49
50
50 DUP
51
52
53
54
55
56
57
S3
S4

HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964
HOLE 964


CLIENT I.D,
EIIA 4-3
EIIA 4-4
EHA 4-5
EIIA 4-5
EIIA 4-6
EIIA 4-7
EIIA 4-8
EIIA 4-9
EIIA 4-10
EIIA 4-11
EHA 4-12



22.
35.
47.
47.
56.
60.
75.
90.
104
112
114



.0'-35.4'
4'-47.8'
8'-54.4'
8'-54.4'
6--60.3'
3'-75.1'
P-90.81
8'-104.7'
.7'-105.6'
.l'-114.0'
.0'-I22.5'


I TOTAL
SULFUR
<0.01
1.75
<0.01
<0.01
0.92
<0.01
<0.01
<0.01
0.42
0.82
0.28
1.12
0.59
I TOTAL
SULFUR*
<0.3l
54.7
<0.31
<0.31
28.7
<0.3l
<0.31
<0.31
13.1
25.6
8.75
35.0
18.4
NEUTRALIZATION
POTENTIAL*
-1.
-3.
0
0
-1,

1.
1.
0.
0.
5.
6.
3.
25
00
.25
.23
.75
0
.00
,00
75
50
50
63
38
CATION EXCHANGE
CAPACITY**
8.
96
10.6
1.
1.
6.
1.
2.
0.
0.
18
17
10
16
06
06
48
84
19
58
99
,5
.3
.5
.3
EXCHANGEABLE
CATIONS**
1.23
0.34
0.32
0.37
0.28
0.34
0.30
0.42
0.65
12.3
15.7
8.68
7.75
   *CaC03 EQUIVALENT:  TONS PER  1,000 TONS MATERIAL
  "MILLIEQUIVAI.ENTS PER 100 GRAMS
                                                       B-23

-------
ESPEY. HUSTON AND ASSOCIATES. INC.
TEXAS  UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
CORE  LABORATORIES, INC.
       ANALYTICAL REPORT
        DATE:     27 MAR 81
        ANALYST:  .IMA/ETK

      FORMS OF SULFUR (OVERBURDEN)
                                                FILE NO.:  H81002, pg.  9
                                                LOCATION:  TYLER COAL LAB
SAMPLE
NUMBER
5
6
7
11
13
14
15
16
22
23
24
25
26
29
30
30 UUP
35
X TOTAL

HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE

1128
1128
1128
562
562
562
562
562
1009
1009
1009
1009
1009
1009
1009
1009
972
CLIENT I.D
EHA 5-5
EI1A 5-6
EHA 5-7
EHA 2-4
EHA 2-6
EHA 2-7
E1IA 2-8
EHA 2-9
EHA 1-4
EHA 1-5
EHA 1-6
EHA 1-7
EHA 1-8
EHA 1-11
EHA 1-12
EHA 1-12
EHA 3-3
SULFUR
49.7'-51.0'
51.0'-54.3'
54.3'-64.1'
17.5'-21.0'
24.0'-34.5'
34.5'-45.5'
50.0'-63.0'
63.0'-64.6'
29.2'-33.5'
33.5'-41.0'
41.0'-48.0'
51.4'-59.7'
59.7'-65.7'
92.0'-107.2'
107.2'-109.2'
107.2'-109.2'
lO.l'-ll^1
0.
0.
0.
1.
2.
1.
0.
1.
1.
2.
0.
1.
1.
1.
1.
1.
3.
75
36
47
37
16
53
70
10
28
74
36
43
82
18
33
28
19
X SULFATE
SULFUR*
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
0.
03
09
16
26
40
15
08
17
41
34
U
22
20
21
18
14
10
I PYRITIC
SULFUR**
0.
0.
0.
0.
1.
1.
0.
0.
0.
2.
0.
1.
1.
0.
40
11
08
97
60
10
38
69
75
16
20
06
33
75
0.80
0.
2.
87
46
Z ORGANIC
SULFUR***
0.32
0.16
0.23
0.14
0.16
0.28
0.24
0.24
0.12
0.24
0.05
0.15
0.29
0.22
0.35
0.27
0.63
   *IICl EXTRACTADLE
  "IINOj EXTRACTABLE
 ***HON-EXTRACTABI.E
ESPEY, HUSTON AND ASSOCIATES,  INC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
CORE  LABORATORIES, INC.
       ANALYTICAL REPORT
        DATE:     27 MAR 81
        ANALYST:  JMA/ETK

     FORMS OF SULFUR ( OVERBURDEN)
                                               FILE NO.:  M81002, pg.  10
                                               LOCATION:  TYLER COAL I.AB
SAMPLE
NUMBER
36
49
51
55
56
S3
S4


HOLE
HOLE
HOLE
HOLE
HOLE




972
964
964
964
964



CLIENT I.
EHA 3-4
EHA 4-4
EHA 4-6
EHA 4-10
EHA 4-11



D.
11.
35.
56.
104
112




2'-14.2'
4'-47.8'
6'-60.3'
.7'-l05.6'
.l'-114.0'


X TOTAL
SULFUR
1.28
1.75
0.92
0.42
0.82
1.12
0.59
X SULFATE
SULFUR*
0.
0.
0.
0.
0.
0.
0.
27
46
21
20
14
06
04
X PYRITIC
SULFUR**
0.
1.
0.
0.
0.
0.
0.
81
09
61
14
41
65
32
X ORGANIC
SULFUR***
0.20
0.20
0.10
0.08
0.27
0.41
0.23
  *HC1 EXTRACTABLE
 **HN03 EXTRACTABLE
 ***NON-EXTRACTABLE
                                                    B-24

-------
ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
CORE  LABORATORIES,  INC.
      ANALYTICAL REPORT
        DATE:     27 MAR 81
        ANALYST:  JMA/ETK
FILE NO.:  MB 1002. pg.  11
LOCATION:  TYLER COAL LAD
SAMPLE
NUMBER
1
2
3
4
5
6
7
8
9
10
10 OUP
11
12
13
14
15
16
CLIENT I.D.
HOLE 1128
HOLE 1128
HOLE 1128
HOLE 1128
HOLE 1128
HOLE 1128
HOLE 1128
HOLE 562
HOLE 562
HOLE 562
HOLE 562
HOLE 562
HOLE 562
HOLE 562
HOLE 562
HOLE 562
HOLE 562
EHA 5-1
EI1A 5-2
EHA 5-3
EHA 5-4
Ell A 5-5
EHA 5-6
EHA 5-7
EHA 2-1
EHA 2-2
EHA 2-3
EHA 2-3
EHA 2-4
EHA 2-5
EHA 2-6
EHA 2-7
EHA 2-8
EHA 2-9
o'-u.a'
11.8'-28.0'
28.0'-40.0'
40.0'-47.0'
49.7'-51.0'
51.0'-54.3'
54.3'-64.1'
O'-IO.O1
10.0'-14.5'
14.5'-17.5'
1«.5'-17.5'
17.5'-21.0'
2I.O'-24.0'
24.0'-34.5'
34.5'-45.5'
50.0'-63.0'
63.0'-64.6'
ppm
B*
0.16
0.06
0.08
0.06
2.09
' 0.48
0.48
0.17
0.27
0.18
0.13
0.58
0.09
1.83
0.87
1.23
2.29
ppm
Cd
1.0 •
1.5
1.0
1.5
2.5
0.5
1.0
1.5
2.0
0.5
0.5
1.0
0.5
2.0
2.0
3.0
1.5
ppm
Cr
41
12
19
10
68
39
38
56
43
19
25
41
18
35
58
69
57
ppm
Cu
11
4.5
7.0
3.5
35
11
16
15
7.5
3.5
4.5
7.5
4.5
6.0
18
22
23
ppra
Mn
49
19
13
a.s
62
89
167
31
21
22
23
18
13
77
395
405
159
ppra
Ho
10
5.0
15
10
25
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
10
10
ppm
Pb
10
5.0
5.0
5.0
10
35
35
40
20
15
20
25
25
15
20
35
30
ppm
Zn
21
4.5
6.0
4.5
140
105
77
25
12
9.5
10
19
7.0
60
82
90
87
ppn
Aa
37
a
29
13
118
84
82
86
45
21
19
51
25
41
70
75
78
ppra
Se
<2.0
<2.0
<2.0
<2.0
2.8
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
2.3
2.0
<2.0
  ALL ANALYSIS DONE ON TOTAL  BASIS
 *IIOT WATER EXTRACTABLE
 ESPEY,  HUSTON AND ASSOCIATES,  INC.
 TEXAS UTILITIES GENERATING COMPANY
 MILL CREEK OVERBURDEN ANALYSIS
CORE  LABORATORIES,  INC.
       ANALYTICAL REPORT
        DATE:     27 MAR 81
        ANALYST:  JMA/ETK
FILE NO.:  M81002, pg.  12
LOCATION:  TYLER COAL LAH
SAMPLE
NUMBER
17
18
19
20
20 DUP
21
22
23
24
25
26
27
28
29
30
30 DUP
31
CLIENT I.D.
HOLE 562
HOLE 562
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
HOLE 1009
EHA 2-10
EHA 2-11
EHA 1-1
EHA 1-2
EHA 1-2
EHA 1-3
EHA 1-4
EHA 1-5
EHA 1-6
EHA 1-7
EHA 1-8
EHA 1-9
EHA 1-10
EHA 1-11
EHA 1-12
EHA 1-12
EHA 1-13
74.0'-75.3'
75.3'-87.2'
0'-8.0'
8.0'-16.0'
8.0'-16';0'
16.0'-29.2'
29.2'-33.5'
33.5'-41.0'
41.0'-48.0'
51.4'-59.7'
59.7'-65.7'
65.7'-78.0'
7B.O'-92.0'
92.0'-I07.2'
107.2'-109.2'
107.2'-109.2'
119.6'-121.5'
ppra
B*
2.39
0.71
0.71
0.15
0.17
0.21
0.66
1.37
0.17
0.47
2.72
0.27
0.09
0.58
0.90
0.83
1.21
ppra
Cd
2.5
2.0
2.0
3.0
2.5
0.5
0.5
1.0
2.0
1.5
1.0
1.0
3.0
1.5
2.0
2.5
2.5
ppm
Cr
54
54
51
50
55
48
30
46
17
42
44
13
12
60
72
69
51
ppm
Cu
23
23
42
9.5
9.5
9.0
6.0
8.5
2.0
6.0
1.0
3.0
3.0
23
31
31
20
ppn
Mn
145
287
82
22
20
23
26
40
22
36
35
49
53
342
169
167
114
ppm
Ho
5.0
5.0
5.0
10
10
5.0
5.0
5.0
5.0
5.0
10
5.0
10
5.0
5.0
5.0
10
ppm
Pb
35
35
80
30
40
20
25
30
15
25'
20
15
15
30
40
40
30
ppra
Zn
82
95
80
22
22
19
56
75
15
61
41
10
9.0
97
110
110
77
ppm
Aa
60
66
71
47
50
36
23
34
13
32
28
21
11
66
99
105
100
ppm
Se
3.5
2.5
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
2.5
<2.0
<2.0
<2.0
<2.0
<2.0
<2.0
  ALL ANALYSIS DONE ON TOTAL BASIS
 •MOT WATER EXTRACTABLE
                B-25

-------
ESPEY. HUSTON AND ASSOCIATES, IMC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
CORE  LABORATORIES, INC.
      ANALYTICAL REPORT
        DATE:     27  MAR 81
        ANALYST:  JMA/ETK
FILE NO.i   MB 1002, pg.  13
LOCATION:   TYLER COM. LAB
SAMPLE
NUMBER
32
33
34
35
36
37
38
39
40
41
42
42 DtIP
43
44
45
46
47
CLIENT l.D.
HOLE 1009 EHA 1-14 121 .5' -131.4 '
HOLE 972 EHA 3-1 0'-7.6'
HOLE 972 EHA 3-2 7.6'-10.1'
HOLE 972 EHA 3-3 10.1'-11.2'
HOLE 972 EHA 3-4 H.2'-14.2'
HOLE 972 EHA 3-5 15.2'-20.7' '
HOLE 972 EHA 3-6 20.7'-36.1'
HOLE 972 EHA 3-7 36.1'-52.3'
HOLE 972 EHA 3-8 54.2'-55.7'
HOLE 972 EHA 3-9 55.7'-59.0'
HOLE 972 EHA 3-10 59.0'-61.4'
HOLE 972 EHA 3-10 59.0'-61.4'
HOLE 972 EHA 3-11 68.6'-69.5'
HOLE 972 EHA 3-12 69.5'-75.0'
HOLE 972 EHA 3-13 75.0'-82.2'
HOLE 964 EHA 4-1 O'-IO.O'
HOLE 964 EHA 4-2 10.0'-22.0'
ppm
B*
0.70
0.52
0.26
5.28
0.43
0.32
0.27
0.31
1.95
0.86
5.05
5.22
4.24
0.60
0.79
0.67
0.35
ppm
ca
3.5
2.5
4.0
2.5
2.5
1.0
0.5
1.5
2.5
2.5
0.5
0.5
0.5
1.0
1.5
4.0
0.5
I'P'»
Cr
52
40
61
55
71
50
36
39
62
74
68
58
66
44
56
78
48
PPm
Cu
15
23
21
35
34
18
12
13
61
30
30
29
43
15
23
25
8.0
ppm
Mn
138
43
31
22
60
512
497
710
73
103
49
49
141
166
367
145
32
ppm
Mo
5.0
5.0
5.0
5.0
5.0
15
5.0
5.0
10
10
5.0
5.0
5.0
10
10
10
5.0
ppm
Pb
30
35
25
20
20
30
25
25
40
35
30
30
35
25
25
55
30
ppn
Zn
72
36
13
77
210
95
65
60
100
110
40
39
87
82
87
85
20
ppm
Aa
92
49
96
62
125
83
57
55
106
99
110
103
51
48
25
48
20
ppm
Se
<2.0
<2.0
2.0
<2.0
<2.0
2.0
<2.0
<2.0
2.5
3.5
2.3
2.8
3.3
2.8
<2.0
<2.0
<2.0
ALL ANALYSIS DONE ON TOTAL BASIS
*IIOT WATER EXTRACTABLE

CORE
ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
SAMPLE
NUMBER
48
49
50
CLIENT l.D.
HOLE 964 EHA 4-3 22.0'-35.4'
HOLE 964 EHA 4-4 35.4'-47.8'
HOLE 964 EHA 4-5 47.8'-54.4'
50 DUP HOLE 964 EH A 4-5 47.8'-54.4'
51
52
53
54
55
56
57
S3
S4
HOLE 964 EHA 4-6 56.6'-60.3'
HOLE 964 EHA 4-7 60.3'-75.1'
HOLE 964 EHA 4-8 75.T-90.81
HOLE 964 EHA 4-9 90.8'-104.7'
HOLE 964 EHA 4-10 104. 7 '-105.6'
HOLE 964 EHA 4-11 112.1'-114.0'
HOLE 964 EHA 4-12 114.0'-122.5'


LABORATORIES,
ANALYTICAL REPORT
HATE:
ANALYST
ppm
B*
0.41
1.30
0.19
0.27
0.50
0.24
0.25
0.17
0.25
2.48
0.19
0.82
1.81
INC.


27 MAR 81
: JMA/ETK
ppm
Cd
0.5
0.5
1.5
0.5
<0.5
0.5
<0.5
<0.5
<0.5
0.5
0.5
0.5
0.5
ppm
Cr
49
44
12
a
40
23
18
10
13
77
49
54
61
ppm
Cu
8.5
11
4.0
3.5
8.5
4.5
4.0
7.5
9.5
37
20
23
26
ppm
Mn
21
25
12
12
16
12
7.5
10
7.0
48
220
335
340
ppm
Mo
5.0
5.0
5.0
5.0
10
5.0
15
10
10
10
5.0
5.0
5.0

FILE
LOCAT
ppm
Pb
20
25
15
15
25
20
20
15
10
35
35
25
30

NO.i
J.ON:
ppm
Zii
20
31
3.0
4.0
24
5.0
2.5
2.0
6.0
135
95
95
90

MB 1002
TYLER
ppm
As
26
33
7.0
9.0
16
11
8.0
11
6.0
98
70
72
69

. PB. 14
COAI. LAB
ppm
Se
<2.0
2.8
<2.0
(2.0
<2.0
<2.0
<2.0
<2.0
2.8
<2.0
<2.0
<2.0
<2.0
   ALL ANALYSIS DONE ON TOTAL BASIS
  *IIOT WATER EXTRACTABLE
                                                   B-26

-------
ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
CORE LABORATORIES,  INC.
      ANALYTICAL REPORT

        RATE:     27 MAR 81
        ANALYST:  JHA/KTK
FILE NO.:   MB 1002, pg.  IS
LOCATION:   TYLER COAL LAB
SAMPLE
NUMBER
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
WATER HOLDING CAPACITY**
CLIENT I.D. 1/3 BAR
HOLE 1128 EIIA 5-1 0'-11.8'
HOLE 1128 EHA 5-2 11.8'-28.0'
HOLE 1128 EIIA 5-3 28.0'-40.0'
HOLE 1128 EIIA 5-4 40.0'-47.0'
HOLE 1128 EHA 5-5 49.7'-5l.O'
HOLE 1128 EHA 5-6 51.0'-54.3'
HOLE 1128 EHA 5-7 54.3'-64.1'
HOLE 562 EHA 2-1 O'-IO.O'
HOLE 562 EHA 2-2 10.0'-14.5'
HOLE 562 EHA 2-3 14.5'-17.5'
HOLE 562 EIIA 2-4 17.5'-21.0'
HOLE 562 EHA 2-5 21.0'-24.0'
HOLE 562 EHA 2-6 24.0'-34.5'
HOLE 562 EHA 2-7 34.3'-45.5'
HOLE 562 EIIA 2-8 50.0'-63.0'
HOLE 562 EHA 2-9 63.0'-64.6'
12.2
7.5
8.3
3.9
36.2
19.6
20.5
25.4
16.3
9.0
21.1
10.7
14.6
25.3
30.3
19.0
SOIL TEXTURE ANALYSIS
Z 15 BAR Z ZSAND
6.0
2.8
4.1
3.4
16.6
7.4
7.4
10.6
6.4
3.6
8.3
3.8
5.9
15.7
13.6
8.5
52
86
86
94
10
62
48
24
58
68
40
80
58
36
24
22
ZSILT
22
12
10
4
32
18
36
38
22
20
32
a
18
30
42
48
ZCLAY
26
2
4
2
58
20
16
38
20
12
28
12
24
34
34
30
CLASSIFICATION
SANDY CLAY LOAM
SAND
LOAMY SAND
SAND
CLAY
SANDY CLAY LOAM
LOAM
CLAY LOAM
SANDY LOAM
SANDY LOAM
LOAM
SANDY LOAM
SANDY CLAY LOAM
CLAY LOAM
C1.AY LOAM
CLAY LOAM
"REPORTED AS % DRY HEIGHT

CORE
ESPEY, HUSTON AND ASSOCIATES, INC.
TEXAS UTILITIES GENERATING COMPANY
MILL CREEK OVERBURDEN PROJECT
SAMPLE
NUMBER
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
LABORATORIES,
ANALYTICAL REPORT
PATE:
ANALYST:
27 MAR 81
JMA/ETK
INC.

WATER MOLDING CAPACITY**
CLIENT I.D.
HOLE 562 EIIA 2-10 74.0'-75.3'
HOLE 562 EHA 2-11 75.3'-87.2'
HOLE 1009 EIIA 1-1 O'-B.O1
HOLE 1009 EHA 1-2 8.0'-16.0'
HOLE 1009 EIIA 1-3 16.0'-29.2'
HOLE 1009 EIIA 1-4 29.2'-33.5'
HOLE 1009 EIIA 1-5 33.5'-41.0'
HOLE 1009 EIIA 1-6 41.0'-48.0'
HOLE 1009 EIIA 1-7 51.4'-59.7'
HOLE 1009 EHA 1-8 59.7'-65.7'
HOLE 1009 EIIA 1-9 65.7'-78.0'
HOLE 1009 EIIA 1-10 78.0'-92.0'
HOLE 1009 EHA .1-11 92.0'-107.2'
HOLE 1009 EHA 1-12 107. 2'-109. 2'
HOLE 1009 EIIA 1-13 119.6'-121.5'
1/3 BAR
24.0
22.0
20.0
13.0
12.8
16.4
15.9
31.2
15.1
13.3
3.5
2.6
24. 1
31.9
19.5
Z 15 BAR
2.0
9.0
11.0
9.0
7.6
14.4
7.6
15.0
5.4
5.7
1.3
1.0
9.1
16.9
13.3
Z ZSAND
36
16
60
42
64
68
30
74
40
50
82
88
24
6
50



FILE NO.:
LOCATION:

MB1002, pg. 16
TYLER COAL LAD
SOIL TEXTURE ANALYSIS
ZSILT
38
80
12
28
10
10
40
22
30
30
a
6
38
38
26
ZCLAY
26
4
28
30
26
22
30
4
30
20
10
6
38
56
24
CLASSIFICATION
LOAM
SILT
SANDY CLAY LOAM
CLAY LOAM
SANDY CLAY LOAM
SANDY CI.AY LOAM
CLAY LOAM
LOAMY SAND
CLAY LOAM
LOAM
LOAMY SAND
SAND
CLAY LOAM
CLAY
SANDY CLAY LOAM
 "REPORTED AS Z DRY WEIGHT
                                                 B-27

-------
ESPEY, HUSTON AND ASSOCIATES. INC.
TEXAS UTILITIES  GENERATING COMPANY
HI I.I. CREEK OVERBURDEN PROJECT
CORE  LABORATORIES, INC.
       ANALYTICAL REPORT

        DATE:     27 MAR 81
        ANALYST:  JHA/ETK
FILE NO.i  H8I002. pg. 17
LOCATION:  TYLER COAL LAB
                      WATER HOLDING CAPACITY**
                                                                         SOIL TEXTURE ANALYSIS
onnri.lj
NUMBER
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47

HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE
HOLE

1009
972
972
972
972
972
972
972
972
972
972
972
972
972
964
964
CLIENT I.D.
EIIA 1-14
EIIA 3-1
EIIA 3-2
EIIA 3-3
EIIA 3-4
EIIA 3-5
EIIA 3-6
EIIA 3-7
EIIA 3-8
EIIA 3-9
EIIA 3-10
EIIA 3-11
EIIA 3-12
EIIA 3-13
EIIA 4-1
EIIA 4-2

121.5'-1
0'-7.6'
7.6'-10.
lO.l'-ll
11.2--14
15.2'-20
20.7'-36
36.T-52
54.2'-55
55.7'-59
59.0'-61
68. 6 '-69
69.5'-75
75.0'-82
O'-IO.O'
10.0'-22

31.4'

r
.2'
.2'
.7'
.1'
.3'
.7'
.0'
.4'
.5'
.0'
.2'

.0'
1/3 BAR Z
17.3
21.3
15.8
30.1
37.6
22.1
34.3
31.3
34.6
34.2
42.6
28.4
41.7
25.6
20.1
17.9
15 BAR Z
7.9
10.2
13.5
24.2
34.1
18.2
20.0
14.7
23.0
30.6
31.7
25.2
13.9
2.1
10.8
9.0
ZSAND
36
50
26
42
12
50
66
68
8
8
12
46
54
20
50
38
ZSILT
42
18
38
34
64
30
22
22
24
32
28
30
34
56
16
40
ZCLAY
22
32
36
24
24
20
12
10
68
60
60
24
12
24
34
22
CLASSIFICATION
LOAM
SANDY CLAY LOAM
CLAY LOAM
LOAM
SILTY LOAM
LOAM
SANDY LOAM
SANDY LOAM
CLAY
CLAY
CLAY
LOAM
SANDY LOAM
SILTY LOAM
SANDY CLAY
LOAM
"REPORTED AS Z DRY WEIGHT
  ESPEY, HUSTON AND ASSOCIATES,  INC.
  TEXAS UTILITIES GENERATING COMPANY
  HILL CREEK OVERBURDEN  PRO.IECT
 CORE LABORATORIES, INC.
        ANALYTICAL REPORT

          DATE:     27 MAR 81
          ANALYST:  JT1A/ETK
  FILE NO.:   M8I002, pg.  18
  LOCATION:   TYLER COAL LAB
                       WATER HOLDING CAPACITY **
                                                                            SOIL TEXTURE ANALYSIS
SAMPLE
NUMBER
48
49
50
51
52
53
54
55
56
57
S3
S4
CLIENT I.D.
HOLE
HOLE
HOLE
HOLE
IIOLK
HOLE
HOLE
HOLE
HOLE
HOLE


964
964
964
964
964
964
964
964
964
964


EIIA 4-3
EIIA 4-4
EIIA 4-5
EIIA 4-6
FIIA 4-7
EIIA 4-8
EIIA 4-9
EIIA 4-10
EIIA 4-11
EIIA 4-12


22.0
35.4
47.8
56.6
60.3
75.1
90.8
104.
112.
114.


'-35.4'
'-47.8'
'-54.4'
'-60.3'
'-75.1'
'-90.8'
'-104.7'
7'-105.6'
l'-114.0'
0'-122.5'


1/3 BAR I
8.9
16.8
4.0
13.1
A.I
3.7
6.9
2.7
32.5
12.4
27.7
29.3
15 BAR Z
6.0
7.3
2.6
2.6
2.9
3.0
3.4
1.5
18.2
11.7
16.4
15.1
ZSAND
70
34
86
48
74
94
94
94
10
22
30
16
ZSILT
10
40
10
28
18
6
4
4
34
50
46
58
%CLAY
20
26
4
24
8
0
2
2
56
28
24
26
CLASSIFICATION
SANDY CLAY LOAM
LOAM
LOAMY SAND
LOAM
HANDY LOAM
SAND
SAND
SAND
CLAY
CLAY LOAM
LOAM
SILTY LOAM
  "REPORTED AS  Z DRY WEIGHT
                                                    B-28

-------
5.  Agreement for Railroad Road Crossings
                B-29

-------
                                                Rusk  County
                                                P.M.  Road 2658
                                                State Highway 43
                                                P.M.  Road 1716
                            AGREEMENT BETWEEN

                           THE STATE  OF  TEXAS

                                   AND

                      TEXAS UTILITIES SERVICES  INC.

                  FOR THE  CONSTRUCTION AND  MAINTENANCE

               OF RAILROAD STRUCTURES OVER  P.M.  ROAD 2658,

                  STATE HIGHWAY 43, AND  P.M. ROAD  1716
STATE OF TEXAS    j

COUNTY OF TRAVIS  j
     THIS AGREEMENT,  entered  into  this  /$"•   day of   A4*S*=          1982,
by and between  the  State  of Texas,  hereinafter called  the  "State",
represented by  the  Engineer-Director  of the State Department  of  Highways  and
Public Transportation,  acting for  and in  behalf of  the State  Highway  and
Public Transportation Commission,  and Texas Utilities  Services  Inc.
hereinafter called  the  "Company",  acting  by and through >EM.
-------
                            A iill-ii^ T

     NOW, THEREFORE, in consideration of the premises  and  of  the mutual
covenants and agreements of the parties  hereto,  to be  by them respectively
kept and performed as hereinafter set forth, it  is agreed  as  follows:

     ARTICLE 1.   For and in consideration of one dollar ($1.00) paid by
the Company to the State, receipt of which is hereby acknowledged,  the
State grants to the Company license and  permission to  construct, maintain,
and use highway-railway grade separation structures, hereinafter called
Structures, and suitable approaches over and across Farm to Market  Road
2658, State Highway 43, and Farm to Market Road  1716 at the approximate
locations indicated on Exhibit "A".

     ARTICLE 2.   The Company at its entire cost  and expense shall prepare
complete construction drawings and specifications for  the  Structures,
approaches thereto, and any incidental work required.   No  construction
work shall be performed on highway right of way  until  these plans and
specifications have been approved by the State and after such approval
has been given, no changes or alterations shall  be made without the
written approval of the State.

     The plans and specifications, after having  been approved in writing
by the State, are hereby adopted as the  plans and specifications covering
the construction of said Structures,approaches thereto, and incidental
work as required.  A copy of the approved plans  and specifications  shall
be marked Exhibit "B", attached hereto,  and made a part of this agreement.

     ARTICLE 3.   The Company shall provide such  detours, barricades, warning
signs, flares, flashing light signals, and flagmen as  are  deemed necessary
by the State to direct and protect vehicular traffic while the construction
work and related activities, as hereinafter described  to be done on
highway right of way, is in progress. Details of these traffic handling
measures shall be shown on the plans.  If, during construction, it  becomes
necessary or desirable to modify the traffic control measures shown on the
plans, prior approval must be obtained from the  State's District Engineer
in Tyler.

     ARTICLE 4.   The Company agrees that where structural  steel is  used  in
construction of the Structures, the plans will show what protective
coating, if any, is to be applied to those portions visible from the
roadway, and that future maintenance of  the Structures shall  retain the
same appearance and color as that shown  on the approved plans unless
otherwise agreed in writing by the State.  The Company also agrees  to
keep the Structures free from all advertising matter or insignia except
such identification lettering as may be  approved by the State.

     ARTICLE 5.   The Company shall construct, at its entire cost and
expense, the Structures and incidental  items referred  to  in Articles  1 and
2.  The State shall have the right to inspect the work on  highway  right
of way at any time during the progress of the work and to  make a final
inspection thereof.  The Company shall  correct any deficiencies revealed
                                   B-31

-------
by the State's inspection of the work or the traffic protection measures
where such deficiencies could have an adverse effect on public use of
the highway or the safety and convenience of the travelling public.

     ARTICLE 6.  The Company shall reimburse the State for all expenses
it incurs in connection with construction of the Structures.  These may
include, but are not limited to, expenses for review of plans, construction
inspections, travel, and meetings related to the project.

     Upon execution of this agreement, the Company shall pay to the State,
by check made payable to the State Treasurer, Account Trust Fund No. 927,
an amount of $10,000  which is estimated to be the total of all costs
that will be incurred by the State in connection with the construction of
the Structures.

     If, at any time, it becomes apparent that the amount previously
deposited by the Company will not be sufficient to cover the State's costs,
the Company, upon request from the State, shall make additional payments
to the State to cover these costs.

     After all construction is completed, the State will make a final
accounting in accordance with its established accounting procedures.  Any
funds previously deposited by the Company and not expended for the cost  of
these Structures will be returned to the Company.

     ARTICLE 7.  The Company shall assume the entire financial responsibility
for the maintenance and use of the Structures on the State's right of way
as shown on Exhibits "A" and "B", and nothing contained herein shall ever
be construed to place upon the State any liability for injury to or death
of persons, or for damage to or loss of property arising from or in any
manner connected with the construction, maintenance, or use of the tracks
and Structures on State property.

     ARTICLE 8.  It is understood that should any or all of the Structures
licensed hereunder cease to be required or cease to be maintained for the
intended purpose for a period in excess of two years, the license for the
affected Structure or Structures shall expire and be terminated and the
Company agrees that it shall then, at its entire expense, remove the
Structure or Structures from the State's right of way and restore that right
of way to a condition satisfactory to the State.

     ARTICLE 9.  The Company agrees to indemnify the State against any
damages or claims for damages, including those under the Texas Torts Claims
Act, which may be inflicted upon the property of others or to persons,
whether one or more, arising out of, incidental to, or in any manner
associated with or attributed to the construction, use, maintenance, or
possible subsequent removal of the Structures covered in this agreement.

     ARTICLE 10.  The license granted hereby shall not in any way prevent
the State, at its expense, from changing the highway on the right of way over
which license has been granted, provided such changes will not adversely
                                   B-32

-------
affect the intended use of the Structures or compromise the safety of the
rail traffic.

     ARTICLE 11.  The State reserves the right to attach vertical  clearance
information signs to the fascia of the Structures.  Said signs will
thereafter be maintained by the State in a manner which will not interefere
with the Company's operations.

     ARTICLE 12.  The contract or contracts let by the Company for con-
struction of the Structures and incidental work shall  provide for
insurance as follows:

     1.  Standard Manufacturers' and Contractors' Liability Insurance.

     The Contractor shall  furnish evidence to the State that, with respect
     to the operations he performs, he carries regular Contractors'
     Liability Insurance providing for a limit of not  less than one
     million dollars ($1,000,000.00) for all  damages arising out of  bodily
     injuries to/or death of one or more persons in any one occurrence,
     and Property Damage Liability Insurance providing for a limit of not
     less than five hundred thousand dollars ($500,000.00) for all damages
     arising out of injury to/or destruction of property in any one
     occurrence and subject to that limit per occurrence, a total  (or
     aggregate) limit of one million dollars ($1,000,000.00) for all
     damages arising out of injury to/or destruction of property during
     the policy period.

     If any part of the work is sublet, similar insurance shall be
     provided by or in behalf of the subcontractors to cover their
     operations.

     2.  Contractors' Protective Liability Insurance.

     The Contractor shall  furnish evidence to the State that, with respect
     to the operations performed for him by subcontractors, he carries  in
     his own behalf regular Contractors' Protective Liability Insurance
     providing for a limit of not less than one million dollars ($1,000,000.00)
     for all damages arising out of bodily injuries to/or death of one  or more
     persons in any one occurrence, -and Protective Property Damage Liability
     Insurance providing for a limit of not less than  five hundred thousand
     dollars ($500,000.00) for all damages arising out of injury to/or
     destruction of property in any one occurrence and subject .to that limit
     per occurrence, a total (or aggregate) limit of one million dollars
     ($1,000,000.00) for all damages arising out of injury to/or destruction
     of property during the policy period.

     ARTICLE 13.  The approval hereby granted shall cease and be null and
void unless actual construction of the Structures herein described is
commenced within three years and completed within five years.

     ARTICLE 14.  The terms of this agreement shall transfer to and be binding
upon any successors and/or assigns of Texas Utilities  Services Inc.
                                  B-33

-------
     IN TESTIMONY WHEREOF, the parties hereto have caused these  presents
to be executed in duplicate on the day above stated.
TEXAS UTILITIES SERVICES INC.
ATTEST:
THE STATE OF TEXAS

Certified as being executed for
the purpose and effect of acti-
vating and/or carrying out the
orders, established policies, or
work programs heretofore approved
and authorized by the State
Highway and Public Transportation
Commission:
                                          By:	
                                                  Engineer-DiVector
                                          Executed and  approved  for  State
                                          Highway and Public Transportation
                                          Commission  under authority of
                                          Commission  Minute Order No.  78501,
                                          dated May 20, 1981.
                                          RECOMMENDED FOR EXECUTION:
                                          District Enaineer
                                          Chief Engineer of Highway
                                          Director,  Finance
                                              -—
                                           ssistant Ewirfeer-Director
                                  B-34

-------
ON

-------