Test No.  71-CI-25
        Speedring Manufacturing,  Inc.
   Division of Schiller Industries,  Inc.
             Cullman,  Alabama
            October 25-26,  1971
       Thomas E.  Ward - Durham,  N.C.
            Project Test Officer
       Environmental  Protection  Agency
           Office of Air Programs"
Stationary Source Pollution Control  Programs
        Applied Technology Division
           Emission Testing Branch
    Combustion and Incineration  Section
           Contract No. 68-02-0225
              Task Order No.  3

-------
                     TABLE OF CONTENTS
  I.   Introduction ............ . .................. . ........ P*ge
 II.   Summary of results
III.   Conclusions and Recommendations
                                                            _

                         APPENDIX
  A.   Beryllium Analytical Method	   g
  B.   Project Participants	  71
  C.   Contractor report		.............
  D.   Memorandum	
                                                            .0
                                                           4-Z

-------
 I.   INTRODUCTION
     The  objective of  this test was to determine a test method for sampling
 beryllium  emissions from metal machining operations.  The test was conducted
 at  Speedring Manufacturing,  Incorporated, in Cullman, Alabama, on October 25-
 26,  1971.                                                  i

     This metal machining shop controlls their beryllium emissions using a
 "wet"  baghouse.  Standard cutting oil emulsions of various types, when used,
 are  drawn  into the vacuum inlets which are placed at the interface of the
 cutting  tool and the  machined piece; when they reach the bag, they "wet" the
 bag.
         Figure 1 shows  sampling points.
                                                "Standard Home-Type
                                                  Air Conditioning
                                                   Filters

(o)
f
^

Blower . . Baghouse
                                                               Sampling Point #1
                                                               Sampling Point #2
 Manifolded  vacuum
 inlets,  at  least
 one  for  each  beryllium
 machining operation
                                   Figure  1

     The  memorandum  from  Robert  Neligan to  the Acting Director, Division of
 Compliance  (see  Appendix D)  describes the  test procedure and plan as of the
 October  7,  1971, date  of that memorandum.  On October  14,  1971, John Burkle,
.Project  Engineer, instructed ETB  to  perform  the test in two parts, the first
 part to  consist  of  two days  of  testing,  and  the second part (based upon
                                       1

-------
acceptable results in the first two-day part) to consist of four days of testing.
The updated test method is shown in Table I.
      \
       \
    Mr.  Burkle authorized at the test site the duration of gas sampling time
to be five hours and to. change the sample "bottling" and "packaging" procedure
as shown in Table II.  The stated reason for the packaging change was that if
the total filter and impinger train catch of beryllium was very small, then,
       I
with so many subdivisions of the sample catch, the analysis data would be
"masked" by the analytical procedure.

    Mr.  Burkle directed that the trains be filled with impinger liquids,
assembled,' disassembled, and have their samples transferred to the sample
         /
bottles, all on the roof of the test, site for 2a and 2b; and at a physical
      '/  .               '                    •
location at least one mile away from the test site for 5a and 5b.  The latter
work was performed in a motel room which was more than a mile away from the
test site.
    Soda lime, 6-14 mesh, was used in the eighth impinger to protect the meter
boxes from any possible acid mist carry over.  Figure 2 is a schematic drawing
of the test site.

-------
:"n
4 la
•
2a
'2k
!'3a-
'*4t
C5 O
10 6b
:". •• linrr Tr.-;r. i-* : 1 ) . .', • i r. i ( A' J
Probe 1 Filter
•Yes
Yeo
Yes
Yea
Yes
Yc»
Yes
Ye s
Yes
Yes
Yes
Yen
Yes
Yce
Yas
Yes
1:0
NO
No
No
Yes
Yes
Yes
NO

H,0
10% HCL
10% KKO.
"2°
10% HCL
10% KNO
"2°
10% HCL
3
10% HJvO
10% HCL
H,0
V
1C% HCL
10% H.-.'O
1O:'. !ICL
10* it:x>3
H20
s% n2 so
H£0
5% H2S04
H20
5% HgS04
10% UNO
10% HCL
V
H20
5% H_SO
f **
5% HjSO^,
Empty
Empty
Empty
Empty
E.T,pty
Empty
10X. UNO
10% HCL.
Kmpty
Empty
E,-np ty
F.rapty
1O% HCL
107. liN-C>3
10% UNO
IC'X. liNO,
10% HC1
10% HHO
10% iiCL
j.0% KNO
10% KC1
10% UNO
lirx. HCL
10% n:;o3
J.07. HCL
10% UNO
10% HCL
10.". ('.NO.,
Rer.ova e. , 5
) -'.'leer
"^ r
5'X H_SO.
^ **
5% K2S04
5% JU£C4

5% K,S04
SX "jSO^

5% H0S04

. nr.d 6
Removes 4, 5, and 6
Empty
J:npty
Empty
Empty
Erapty
:,.,pty
,,;>ty
Empty
Jinpty


No
No
NO
No
Yes
Yes
Yes
Yes
No
SO
No
Yes
!!r.;iir.gcr,y
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
• Si lie* go 1
Silica gel
g .
6^7
oil
K*J2
tcdl
6o«.
SW«.
«di
«c<*
BKV^KS
Comparison of Reagents

including clear, up
procedure except no
tl',:.,' collucLed und
onn unir.g method  S tent train with -i.oJ if icjntiono shown in ti...-  tnbicj>'nf It
r i/:pir.g._-rs upstream: w.-itcr-acetor.c war.h  of probe.
 imjMngnra upntrc.ira:   ncid  (10% IIC1,  1C/X  UNO.) wash  of probe.

I tor  and c'tcn  imp ing or analyzed for uc.     "               ~'-~~-—.^
 not  spccifit-d  as oin-^ty cont.'»in 100 ml of liquid ae  J'pocif ic-d.'
na ao ahown indicate-the crUc-r in-urrich  the cu.^plir.g  train is  pl.-vc.ec; to ;ot:
her. opecifie'd)	'•> Crecr.burg  Smith Irpingers (as indicated)	; :iltcr" (w.cn
 Sraitii  Inpingcr containing adsorbent  to protect the  pump and dry  gas moucr
 Scith  Icpingorn  may  be t>.a  ^odific-J  type.     ,
 i  .j/  I                        i  .    i t           I       I                       I
                                                       a.T'tf-   /1*\ J*in&.cr  c^ i *
e BX
er
 .-TV-/
:.-.C  cro
   isok
/J/  s 'Jt.
                                                                                                            scection  in
                                                                                                            ir.otic
                                                                                                            su p I in ff •
her
 spe
r....-.ioly :
cified)
                                                                                                             probe
                                                                             Table  1
                                                                                                                               1 9~7(

-------

TRAIN
NO.
5a m
5b U'
2a (3)
2b (*}

SAMPLE AS
GATHERED AND
PACKAGED BY ETB (1)
DESCRIPTION
Probe, water & acetone washings
Probe, acid washings
Filters
Impinger 1 (11), water
Impinger 1 (11), water & acetone
wash
Impinger 2 (12)

3 (13)
ii n ii ••— 	
Impinqer 4 (14)

Impinger 5 (15)
II ii II
6 (16)

CONSOLIDATION AS
DIRECTED BY DCP
FOR BOTH DAYS (2)
SAMPLE
1
2
1 3
4
5
-•-'6
7
ANALYSIS DA
TRAIN NO.
5a,0ct.25
(6)

U>)
0.09(6)



FA IN uqm Be (4) (
TRAIN NO.
5b,0ct.25
2.85

0.21




FRAIN NO.
5a,0ct.26
0.9'.

(6)
(6)



5) (7)
TRAIN NO.
5b,0ct.26







Trains 2a & 2b
were reduced to
four samples (3)
No.2a
Oct. 25







No.2b
Oct. 25







(1)   On the first day,  Oct.  25,  1971,  thirty  samples were produced and packaged by ETB: 15 for 5a & 15 for 5b.  These
     were consolidated  to fourteen samples  as directed  by DCP,  7 for 5a & 7 for 5b.
(2)   On the second day, Oct.  26,  1971, ETB  was directed by  DCP  to package fourteen samples for trains 5a & 5b, as in
     the consolidation  described  in note (1), above.  ^
(3)   ETB was directed to consolidate these  samples  into four  containers as shown above in the right hand side of this
     Table II and in Table A-II.
(4)   All values are <0.15 unless  otherwise  noted.   See-Appendix A.
(5)   See Table A-II for .blanks (acetone, water, acids and filters), for which all values are <0.15.
(6)   See Appendix A for a description  of these values.    ^ -
(7)   Gas volumes ranged from 231  to 269 ft3 at the  meter.
                                                  TABLE    JE

-------
       FIGURE    2.
    TEST  SITE  , SP£UTDR»NG- , INC.
       CUULMAN , ALA
               A
STACK
G-bS STREAK)
               A
                 m
      TWO TOTA^

      EACH SiPE
         "T
         /' DIA.
                      A-A
         SIDE:  VIEW
                             HORIZOMTAL
          5a
STACK EXTENS/OM
GAS
SP
                   FILTER
        PLAN
                                 a

-------
II.   SUMMARY OF RESULTS
     Table II shows the summarized results of the beryllium samples.   Seven
samples from each of four runs made a total  of twenty-eight samples.   Only
three of the twenty-eight samples yielded values >0.15ug beryllium.   One of
the samples indicated that a small amount of beryllium,  0.09yg passed the
filter.

     Sample gas volumes were 231  to 269 ft .

     Table A-II, Appendix A, shows all of the results of the beryllium samples
with appropriate identification codes.  The contractor report is given in
Appendix C.  The source sampling  contractor was instructed to spend  no more
than eight man-hours in preparing the report, to include as a minimum a copy
of the raw data sheets, and, as the eight hours permitted, total volume cal-
cidations, isokinetic sampling percentage calculations,  and.normal  report writing
efforts.
      \
     The reason for this eight hour restriction was that for this particular
test, the Project Engineer was interested in total  volume of gas sampled, and
a very brief report of activities at the test site.  The report is  excel lent,and
was submitted within six working  days after completion of test..

-------
III.  CONCLUSION AND RECOMMENDATIONS


      The total  beryllium catch  in  the  sampling trains is considered too small

to allow conclusions to be drawn about  efficiencies of the separate portions


of the train.   In turn, no direct recommendations for improvement of the

beryllium sampling train can  be  made  based upon the results 'of this experiment.


The proposed second part of the  experiment is cancelled because the results of

the first part indicate that  not enough beryllium is in the stack gases to allow

a "train efficiency" experiment.  No  well founded conclusions can be drawn


relative to previous beryllium testing  indications that beryllium stack gas

contaminants are getting "through"  filters.  It is recommended that a known


source of beryllium be obtained  for any further testing.  This could be a

commercial or Atomic Energy Commission  stack; or it could be a substitute

source such as a lathe which  is  machining a given amount of beryllium under
                                                                     JTAC K
controlled conditions as shown below  in Figure 3.
                                                             FILTER

             VACUUM nose
                                                       \
       .._  CUTTING.
           TOOU


BERYLLIUM              P°RT  ** '          FS'OFrr'irZ

CYLINDER
                           FIGURE"     3

-------
                                   APPENDIX A

SUMMARY OF ANALYSIS METHOD FOR BERYLLIUM SAMPLES
     York Research, Incorporated, used the EPA suggested method to analyze
the beryllium samples.   In outline form, the chemical  portion of the method is:
          1.   React with nitric acid
          i
          2.   React above solution with sulfuric and perchloric acid
          3.   Evaporate to near dryness on hotplate
          4.   React (dissolve) in hydrochloric acid
          5.   .Bring to 5 ml total volume
     A portion of the 5 ml (usually 1/2 to 1 ml) was decanted and aspirated
into the Atomic Absorption (AA, Perkin-Elmer Model  303) flame.   The absorbance
         '/                                                         '             .
line produced was then compared to a graph which was previously drawn by reading
absorbance of known concentrations of beryllium solutions.   York Research, Inc.,
reports that with their AA unit sensitivity setting of 1 (on a scale of 1 to 10),
and with 1% absorption, the AA will allow a reading of 0.03yg !-3e/ml.  This is the
setting which York Research, Inc., used in all cases except the reruns (sample
Nos. 165, 167, 168, 181 and 182 reruns).  Those five were run with a sensitivity
setting of 5 which York Research, Inc., reports will allow a reading of O..006yg
Be/ml.
                                           8

-------
       Table A-I below shows why the values <0.15 and <0.03 must be used instead

  of zero when reporting "negative" analytical  results.



                                 TABLE A-I

                     BERYLLIUM ATOMIC ABSORPTION (AA) READINGS
Sensitivity setting
on AA
Capability of
Sensitivity Setting
in yg Be/ml
Sample volume
as prepared for
Reading by AA
in ml
Minimum Content
of Beryllium
in 5 ml which will
give a reading.
yg Be	
                               0.03
                                             0.15
                               0.006
                                             0.03 .
           Table A-II shows all of the results of the beryllium samples with all

           appropriate codes.

-------
                                               TABLE A-II
CODE:
Be  - Beryllium
SI  - Speedring Incorporated
 N  - North Stack
 2a, 2b, 5a, 5b, - See Table I dated October 26,  1971  - Test Method
 P  - Probe
 F  - Filters
 11, 12, 13, 14, 15, 15 - See Table I dated  October  26, 1971 -  Impinger Numbers
Sample No.   Code
                                               Description/Date
                                                Analytical Results
                                                yg Be all values
                                                are <0.15 unless
                                                otherwise indicated
    151      Be-SI-N-2a-P
    152      Be-SI-N-2a-F
    153  •    Be-SI-N-2a-ll, 12, 13
    154      Be-SI-N-2a-14, 15, 16
    155      Be-SI-N-2b-P
    156      Be-SI-N-2b-F
    157      Be-SI-N-2b-ll, 12, 13
                        14, 15, 16
    158     ^Be-SI-N-2b-Back Half
    159      Be-SI-Whatman 41
    160      Be-SI-Millipore A7T
    161      Be-SI-Sulfuric acid 10%
Water & acetone washings            10/25/71
Filters .                           10/25/71
Water, water & acetone washings     10/25/71
Acid & acid washings                10/25/71
Water & acetone washings            10/25/71
Filters                            10/25/71
Acid & acid washings                10/25/71

Back Half of filter holder only     10/25/71
BlanL^fiHer                       10/25/71
Blank filter-                      10/25/71
Blank filter                       10/25/71
                                                    10

-------
                                               TABLE A-II,  continued
Sample No.   Code
   Description/Date
Analytical Results
yg Be all values
are <0.15 unless
otherwise indicated
   162      Be-SI-HCL 10% Nitric 10%
   163      Be-SI-Acetone
   164      Be-SI-Distilled Water
   165      Be-SI-N-5a-Pl
   166      Be-SI-N-5a-Pa
   167      Be-SI-N-5a-F
   168,     Be-SI-N-5a-ll
   169      Be-SI-N-5a-12,13
   170      Be-SI-N-5a-14
   171      Be-SI-N-5a-15, 16
   172      Be-SI-N-5b-Pl
   173      Be-SI-N-5b-Pl
   174      Be-SI-N-5b-F
   175      Be-SI-N-5b-ll
   176      Be-SI-N-5b-12, 31
   177      Be-SI-N-5b-14
Blank filter     ..                 10/25/71
Blank filter                       10/25/71
Blank filter                       10/25/71
Water $ Acetone washings           10/25/71
Acid washings                      10/25/71
Filters                            10/25/71
Water, water & acetone washings     10/25/71
Acetone washings                   10/25/71
Acid & acid washings      '         10/25/71
Acid & acid washings               10/25/71
Water & acetone washings           10/25/71
Water & acetone                '    10/25/71
Filters                            10/25/71
Water, water & acetone washings   - 10/25/71
Water, water & acetone washings     10/25/71
Acid & acid washings               10/25/71
    <0.03

    <0.03
     0.09
     2.85
     0.21
                                                   n

-------
                                              TABLE A-II, continued
Sample No.   Code
Description/Date
                                                                                         Analytical Results
                                                                                         ug  Be all values
                                                                                         are <0.15 unless
                                                                                         otherwise indicated
 178        Be-SI-N-5b-15,  16

 179        Be-SI-N-5b-Pl

 180        Be-SI-N-5b-P2

 181        Be-SI-N-5a-F

 182        Be-SI-N-5a-ll

 183        Be-SI-N-5a-12,  13

 184        Be-SI-N-5a-14

 185        Be-SI-N-5a-15,  16

 186        Be-SI-N-5a-Pl

 187        Be-SI-N-5a-P2

 188        Be-SI-N-5b-F

 189        Be-SI-N-5b-ll

 190        Be-SI-N-5b-12,  13

 191        Be-SI-N-5b-14

 192        Be-SI-N-5b-15,  16
 THE  FOU.CHING- WETfe REANAI-YZerD OSi NG- A
 _R£F?UK  165
-RERUN  16 I
 RE RUM  i6£
        ISZ
                                          Acid & acid washings

                                          Water & acetone washings

                                          Acid & acid washings

                                          Filters:

                                          Water, water & acetone washings

                                          Water, water & acetone washings

                                          Acid & acid washings

                                          Acid & acid washings

                                          Water & acetone washings

                                          Acid & acid washings

                                          Filters

                                          Water, water & acetone washings

                                          Water, water & acetone washings

                                          Acid & acid washings

                                          Acid & acid washings
                                             0w THE:  ATOMIC
10/25/71

10/26/71

10/26/71

10/26/71

10/26/71

10/26/71

10/26/71

10/25/71

10/26/71

10/26/71

10/26/71

10/26/71

10/26/71

10/26/71

10/26/71

I0/25/7'
                                                      0.90



                                                     <0.03

                                                     <0.03
                                                THAN rue
                                                    12

-------
                                 APPENDIX B
PROJECT PARTICIPANTS
     1.  Emission Testing Branch, ATD, Thomas E.  Ward -  Project Test Officer,
         on-site during source sampling
     2.  Stationary Source Emissions Methods and  Measurement Section, DCP,
         John Burkle - Project Engineer, and Roy  Bennet  - Observer,  on-site
         during source sampling.
     3.  Engineering Science, Incorporated, Washington,  D.C. - Contract Source
         Sampler.
     4.  National Emissions Standards Development Section, DOC, Dave Patrick -
         Observer, on-site during source sampling.
     5.  Source Sampling Fuels Analytical Branch, DAS, Darryl J. Von Lehmden -
         Observer, on-site during one day of source sampling.  Mr.  Von Lehmden
         is the Project Supervisor of the beryllium sample analysis.
     6.  York Research, Incorporated, Stamford, Connecticut - Contract Beryllium
         Sample Analyzer.
                                         13

-------
 SOURCE TESTING AT SPEEDRING, INC.
  A REPORT OF FIELD TEST RESULTS
                ON
  BERYLLIUM MACHINING OPERATIONS
                AT
          SPEEDRING, INC.
         CULLMAN, ALABAMA
           SUBMITTED TO
MR. THOMAS E. WARD, PROJECT OFFICER
      OFFICE OF AIR PROGRAMS
  ENVIRONMENTAL PROTECTION AGENCY
   RESEARCH TRIANGLE PARK, N.C.
      CONTRACT NO. 68-02-0225
                BY
     ENGINEERING-SCIENCE, INC.
    600 NEW HAMPSHIRE AVE. N.W.
         WASHINGTON D..C.
          NOVEMBER 1, 1971
         	LS	

-------
                          INTRODUCTION





     On October 25 and 26, 1971 stack emission tests were conducted


on beryllium emissions at the Speedring, Inc.  plant located in Cullman,


Alabama .under contract number 68-02-0225 and Task Order 3.  The main


purpose of these tests was to evaluate a sample collection method for the


hazardous pollutant, beryllium.  Results of the mofified sampling train


are intended to provide the basis for determining the most feasible


method for sampling beryllium.


     All sampling was conducted under the direction of the Office of


Air Programs, Environmental Protection Agency.  Mr. Thomas Ward,


Project Officer, EPA, et. al. developed the method which uses eight


impingers in series with special reagents in .each impinger.  Two com-


plete trains were run simultaneously and, in addition., two "background"


trains were set up to determine potential on site contamination.


Testing was conducted after the plant began machining operations under


normal operating procedures and regular work day.


     Mr. Ward assisted in engineering a through test by arranging for


stack extension, ladders, electricity, and other test facilities,

        t
providing the special reagents for the several impingers, and assisting


in sample recovery to assure proper handling and disposition of each


speciman.


     All samples were turned over to EPA at the conclusion of the field


tests for subsequent analysis by EPA.  Under Mr. Ward's guidelines one


man-day of effort was used to prepare this report.  The report contains


two sections in addition to this Introduction;  a Discussion which


describes the test procedures and an Appendix which includes copies of


the raw field data.

-------
     Messrs.  Michael E.  Lukey and John Chehaske conducted the field




test for the  EPA, made the associated  calculations and prepared this




report.  This report does not contain  a discussion of the laboratory




results.
                                17

-------
         -                  DISCUSSION



     The purpose of the two day source tests was to determine the
       s
feasibility of a modified sampling train for testing the deleterious

pollutant, beryllium.  The plant was located in Cullman, A?.abama

and produced machined/tooled beryllium components.   The machining

operations are similar to mild steel machine shops  and include
       I                                  •           '
drilling, milling, cutting, sanding and close tolerance lathe operations.

Because beryllium is a brittle metal, the machining operations emit

a fine metalic (beryllium) dust.  Speedring, Inc. used a vaccum system

connected to two baghouses to remove the dust from the work area.

All .of the' testing was performed on the north stack, on a roof top

with a,/halfmoon shape.  Mr. Thomas Ward, EPA Proj'ect Officer, made
      <
arragements for the temporary stack extension (made of sheet metal

having one foot inside diameter), electricity and other ancillary

supplies.

     Beryllium emissions are quite low when compared to other mass

emission rates from combustion sources.  No visible emissions were

noted during any of sampling periods.  The filters were checked

periodically during the sample runs  (as a check for rapid buildup)

however, only slight color change existed at the very end of the sam-

pling time.  Because of the low emission rates, the conventional par-

iculate  train (EPA Method 5) has to be modified to improve the collection

effeciency of the sub micro  particulate.  Eight impingers were used

in  series with a variety of reagents.  The first two impingers contained

100 ml of deionized distilled water.  Impinger three was empty.

-------
Impinger four contained 100ml  of an acid solution (HC1/HNO-) .




Impinger five contained 100ml of suifuric acid solution.  (The




exact concentrations of both acid solutions were not reported nor




asked for by the test team.  Impinger seven contained 175 grams of




silica gel and the'last impinger contained about 50 grams of soda




lime pellets to protect the pump. Figure 1 shows the schematic  dia-




gram of the sampling scheme.




     A total of six runs were made over the two day period.   Two




trains were run simultaneously during all tests.  Trains labeled




5a and 5b were assembled in a inotel room located approximately  8




miles from the test site.  In addition to these two complete trains,




two "background" stations were setup (assembled and reagents added)




on the roof top of the plant and the probe tip was placed in the




stack.  No sampled air was pulled through the background units  2a




and 2b.  These units were set near 5a and 5b for the same "run"




time.  Sample recovery for the two background units was made on the




roof top of the plant.  Sample recovery for 5a and 5b were made at




the motel room.




     Figure 2 shows the stack configuration and sampling points for




the two units.  A velocity traverse was made to determine probe tip




size stack velocity and flow as well as tip location.  The probe




tip was placed at the point of average velocity and not moved during




the entire sampling periods.  Figure 1 and Figure 3 indicate the exact




contents of each of the trains.




     A summary of the field data and calculations is offered in




Table 1.

-------
The stack temperature was nearly constant and did not vary more than



10 degrees from the average temperature of 110°F during the entire



sampling period.  The average velocity of the stack was 44.7 feet per



second.  The flow rate at standard conditions (70°F and 1. atm.) was



1805 scfm.  The four sample volumes ranged from 231 to 269 dry cubic
                                                           i


feet with an average of about 250 cubic feet.  The moisture content



for four samples was about 3.370.



     The actual field sampling was without .incident for the two day



tests.  Only slight adjustments had to be made to obtain the sample


flow for isokinetic sampling conditions.  All of the raw data



sheets appear in the Appendix.

-------
APPENDIX
FIELD DATA SHEETS
         21

-------
                                FIGURE  1
                                         FIGURE A-l. ParttcuUte Saapllng Train.
                                 Buttonliook-typc probe tip
                                 Stainlrss Stcul Coup ling
                                 Probe
                                 Cyclone and Flask
                                 Fritted Clnss Filter Holder
                                 Ik-occd S.-rr,plc Ho*
                               7. Ice Bath
                    12. Tlicrv.oncter
                    13. Check Valve
                    K. Lnbilical Cord
                    IS. Vacum f.iuge
                    16. !:ccdlc Valve
                    17. V^CUIUTI pur^p
                    18. 3y-?.is3 Valve
                    19. Dry Cjs I'.i'ter           i
                    :0. Calibrated Orifice
                    21. Inclined-Vertical Manometer
                    22. Pltot Tube
SAMPLE  NOS.  2a,  5a,  5b   OCT.  25,  1971  and  5a, 5b OCT.  26,  1971
IMPINGER NO.


II

12

13

14

15

16

17

18
 IMPINGER CONTENTS.


 100ml. HLO

 100ml. HO  GS Impinger

 Empty


HC1/HNO,  solution

100ml.  H  SO,  solution

 Empty

 175  grams  of  Silica Gel


 50 grams  of Soda  Lime
                                        ZZ.

-------
                                                          •31-
                 1 Ft. Inside Dia.
                                     Outlet
•O
                                        103'
             S-l = SAMPLE BOX #1
             S-2 = SAMPLE BOX #2
                                89"
                                                                                             0 i  »
                                                                                        CROSS SECTION VIEW
                                                                                         OF SAMPLE  PORT
                                   FIGURE   2
STACK CONFIGURATION

-------
                              FIGURE  3
STACK WALL
         '/
\

I — \

r ~~\

V

r ~\

— \

r — \


II      12     13
                                                     14   .  15
                                    16
               17    18    I
                                           FIGURE Arl. ^articulate Sampling Train.
 I. Buttonhoolc-type probe  tip
 2. Stainless Sltul Coup line
 3. Probe
 4. Cyclone and Flask
'5. Fritted CInss niter Holder
 6. Ui.-3t.cd S.x-plc Box
 7. Ice Cal.lt
12. .V!\cn=
-------
                                               SUMMARY OF FIELD DATA
Sample
Number/
Date

5a/0ct.25
5b/0ct.25
2a/0ct.25
2b/0ct.25
5a/0ct.26
^ 5b/0ct.26
v - .-
Start- Sample Sample Average Moisture Probe Probe Precent Average
up Time Volume Stack tip length Isok£netic (in.H20)
Time (min.) (ft.3 dry) ~Temp.(OF) (%) size (in) (ft) /
•_ 	 AP AH
09;00 am 300 248.98 112 3.3 % 5 96 .53 2.34
9:00 300 269.05 112 3.4 5 103 .55 2.42
9:00 -* - - - % ' ' 5 -
9:00 -* - - % ••- 5 - -
7:24 300 253.03 110 3.2 \ 5 97 .52 2.19
7:24 300 231.69 110 3.3 fc 5 .90,. .48 2.33)
*   Background samples

-------
                                               Test.  Ilo.     ~7-
                                                       ..— -... .j«~r_ ^.^,
                                              Date
                                      A.  Hist.  frc-~ inr, id? of  fo- ^;-;!l  tc  o-.j'.c.
                                          near v/3li, i:; ., -      '^. __  . _  _
                                           i-K^Xitt '")^'l^i *&X4.4& j
                                      B .  We 11 t h i ck rie :, s , i n . ,  =      "
                                       ..  Inside .diameter of  staci: = A-P>

                                          Stack Area  = __

                                      Co;;i:ients:
Sketch  of stock cross-section
shO'-.-ing sr.nplinq  holes

Calculations:
      H>3i»
                    3 '
                    V
£>UTi£T
Point
!
%
3
^
S
&•





X Die. for
circular stack
ci, v
/vJr 7
?. -'•' • 5
70- >
.-?•-,..?>
• ^?s,t





I
Oist. from outsidf: !
of sa~nle r,ort, in. '•
1
O.S !
/, ?5
•j.s i
? c; 1
o ..5 i
i
&•* \
\
'//,-*_ .. \
i
i
i
1
1
i
i
i
1

Cfilculator

-------
                            .  VELOCITY TRAVERSE FIELD DATA
                                                                             /I
         Plant
         test
£>
         Location'
         Operator   /;;/ry,     ^7" d	•_
                           /   ~
         Meter AH
 (l)-'AP,  in. H90  Average
             £.        - ____
 (2) AP,  ir., I-LO  Average	
                        --1 J —-i- -r-
Clock
T i iiic









•



Point
i
2-
^
^
5
fc
fe
9
lj_
3
Z
1

' .0)
AP, TT~H?0
0 ,31
0,3'fr '
P.^-
yo,v^
O. <7 1/
0,Jtr
6,38
^V-3
a^
' «^7
a^o
0,37
nfr**
nM^

.











ill
AP, in. H,0




.
'







v flif j T /I • HrjH !
«- i












Sta<
(
//


"!



-

'



                                                                                 T
                                                                                  T"
                                                                                  .L.
                                                                                  i
                                                                                 -T"
CoMw.ehts:

-------
                                                        •
 Scir.pl i ng 1 ccsti on  -	£V
             N        * -'~L-*"~m ' —'
              \


 STACK DATA FOR NOMOGRAPH:



 1.   Meter AH	I. 33              in



 • . '   •      .         "     '"        '      '
              t

 2.   Avg. meter tempt  (ambient + 20°
 3.   Moisture  (volume)	
                 /    •                                                •
 4.   Avg. static/press.  *  .  Q.2-S   in. 1LCX.073  -  -!•    -;o 2^	in.  Mfj.
                /         "~~ "*"                ^.                    -.. ..

        •••'/.-    .  •'     '               ••..•'"       .'•••'••
             *  . •                         .                .               '

 5\   Bar. press  sampling point    2.*?.37- in.Kg +    ;oz    (static press  inlllg)


                  3V	in.  iig. -      -• .  . ....  ;•.     .. .' .             ...
 G.   Bar press of  meter    -z.q.3 2-    in. l!g.
 7   P /P  -   5.     2.q.3'/'_  in. Hg
 '•  rc-/'ir> ~	~	-
 Ge  Avg. stack  temperature            //^).	°F.               ;'.




 9.  Avg. stack  velocity (AP)	    0. V	in H^O.    MAX. VELOCITY,.



          •  C  factor (1)  -.    1.IZ	(?.}



10.  Probe Tip size      ^//'/.'v.r.L.   Sl*>.i*^>

-------
   PLANT
Run No.

Location

Date
                     J
                     .  /

fb~7 3- ~7^
''*-. "?X-. -04-
• •/.-<•' . /.:•.


-/./ "•; ••• . •
-, . ... , -.
-' -•• ; .~ r>
— • .- .-, .7



Pi tot
in. KgO
AP
o.- --yd
n.^'i
n.*-i

o.. Jl
- ... 0,

' * » ~" '•*
**• y. • ?
"»
,-).--<,
s- .-.--!
.0 ^-o



Orifice
in Hc
Desired
J7, .. Z>. O
3, , "^ .-5"
__
;2. .'^ s'
.•^ . ^ 5"
.-7 . • ; ,•••>
-•,.--

^,- -' '<
' ^ . -T /o
.-. ^- .^.
-> .- --
-? -i" -•"
^ ,-r.<

Dry Gas Temp.
°F
Inlet Outlet
V-f- -7  -S' -7 .i?
9/v- 7.-T
•7 7 7 J-.
'V •-,
o ;-. - :;
• * ' ''»'*'
CD ? - '7
/ :0 ,0 ff .-)
; ', ,'"• ::- /
/.OJL N?.i»
; .-, 0 ^ -,
x--.s-> >? /

Pu^ip
Vacuum
In. Hg
Gauge
••3 \'"i-
^. .-r
..^ .. -5"
^t ^
'f <^
-^. ^
.:•>
(>.?>
•' . ^
-J. .-r
— i -rT"

-=-?. .-^
-^. i^
 n

Box
Temp.
°F
















Invpir.ger
TCTip
" °F .
<-:-
6,0

O
, ^
'.•• r.<
:'•••
•i
- -
s. -r
." _-'•
^ -r
/:, _-•--
^".-r

Press
in. fig
















Stack
TC.T.O
°F
/ / O
no !
liO
J /Ci
4-^?>
/ • "-" " *
• *\
*' •
• - •.
.' ' ->
^
t i i_— ••
. . ,

i •->


KCAP-27  (12/67)

-------
•
;L, c-:...^:-.;. •;
> s+ ... _^ _~-
	 ;'


, .--',-' " i
ZT& a.-!'
; x •»



























"




i
j ; '.'.:;•
i
'. ~ '. . T • '
'<;,,. ,'.-....:.
.1)-, ,^ ;,...',
1^,,^
J.}.. . -: ' ....'.
s\.f .,• '. •..


















'
•

'






.



\ p G,s
! Mo-:-r5 CF

p'.r ,-,' .^> t

-P .•- ^, _-r ,0
SG 6 , 7y
:-"'V.-i . .'.-•:'
Sv^ -? s Z*
9 -T •', „ ' 4-












. '
;

















in. K?0
Ap

<. -v.-^
(5/c:^
r>. •"-.<
^. £' -^ '

'&••-*• 0.5" 5"
v





























*" Orrf': co
Dos i red
i


—I .- 1 <"
^.v^
i * -"*
.-?../ o


•







•










•










.0 "
7 Ac^us 1

-? ..^ -••'
_J? -/-<9
2 J..^

3 -~~-r'-;-
.r ..'/?

/M... •?.'/?-
^


















•










Jry tTcl
! °f"
In "let
i
! /^o «'.
/,o.--
i as
1 /OY
y/9 <.-

"^~-


















••












" Tc;v.p .
0-jtlct

57 ^
^*
,!^>^
f9^
^/^
:v/?
































In. Hg
Gcu{ie

^''J A -^»


6/r?
; ^
^l<








'"






•
















'"'*
• °F






































.
Tcr.:o" iPrc;: I Terr; *\-
CF :-;:-!. i:~ °" i
! ; •.
• 1

.v.o; •- \ )IJ? '*•
& f \ • .' c o 1
krt i/.1^ !
.'•,
-------
                                                YART! cue ATL~ ~~ ID ' DATA
  PLANT
Rur. No. ' ^,4_ VERY IMPORTANT - FILL IK ALL
Location ',. ' ... . /'. (!
Date ,«.-•; -N. tf~>.l
Operator .>••.• < T$ L
Sample Box No. S:-,}\
I-'.eter Box No. .'•'•/"
METER AH /.Lp;
C FACTOR
1
DRY GAS Pi uOt
Clock METER. CF in. H20
Point Time f ^ ..;..-•-.. •: AP
i i ^ * - .. . *
! - • /• ..
i • -.- 1 ' •
Read end record at the start
each test point.
BLANKS
of
Ar.ibient Temp °F ~?o
Bar. Press. "Hg •? >?.,3z_
Assumed Moisture % /%
PATHOLOGICAL INCINERATQRS-
read and record every ;~5 minutes.
Heater Box Setting., /0F —
Probe Tip
Dia., In. //^
Probe Length .cr '
Probe Heater Setting . —

Orifice AH
in H,0
Desired "j Actual
'.;.-: '.••• '
-~~ .'"' .V " .' *^~'
| -. r~ • • ,'_>•• \
\ • • • • , . • •
!-•/. ..••-.... 1 ......

' ,
1 , . . . .. -, - .. .., _,. -.
. ,
! / ' - - '- • - -•-.-' ' . -. '
i - • j, . , , - -

1 " . * '
- . i -
. .- -. , ..
-:. ; - -...-.

Dry Gas
°F
Inlet

Temp .
Outlet
'',••• • .• .








. -. . .- ..... j -,...-
. ., ..-.,.
).-•'-• > •' :'
!->..-- • •.-. .^. -•'. 1 .- - , L -. - - ' .-, ;
! ! ' •• -.. •• r . _• ., j - .- -
j

i -;.. ;c,:,,;. i /!.•>••/. ^'/ o. / o
:>.'/<> ?.,yo
\ \ \
. . .
/of> tfC
//V 9o

t,om;r.er."cs ' . .^y-^--^--- ^.' '......•.....•....•..•...-. _....•. i. -i, c /' ... 7~ /^.ti ;)}<\
-AVG. AP
Pump
Vacuum Box
In. Hg Temp.
Gauge °F
": . ! •
.•/ /-.
• .
AVG. AH
Iir.plr.ger Staclc Stack
Temp Press Tcmo
°F in. Hg °F
i /TO
j . ..
-:- ' . ! ' 1

! -• • 1 •
I -- -- 1 •
...- -- 1 •- i
• ••
' .--
'
.- .- j . . ..
-' ' 1 i -• •• ! •
, , j j ,, - ! , -,-
- -. I
-;•
-f-'y 0 1
6,0
!
j . .
1
>-. ! ! //o
I
1 ;

MCAP-27 (12/67)

-------
-	^ _ i
                                    in.  H?0 .
)rif-:ce.  Af,
                                                                          y
Or-
 r

                                                                                i r\.-
                                                                                - ufc
      '-!.-•{- '
      l. : i. L |
VuCUU!;!
1 n.  Hg
Giuge
                             "n
          ;D'i^cK;r
TG~?. !    Tasp
                                                                                   0-7
                                                                                            6--0
                      :i /-••, -77
                                      n-o.s^
                                      Vi

-------
                                                 PARTICULAR   _LD DATA
  PLANT
Run N:0. SB / ' VERY IMPORTANT - FTL IN ALL BLANKS
Location (X.. ,'',"•?>.. . JV, /?. X7
Date c^t >t^ K)7/
Operator ->:r- , ' r, <•
Sample Box No. .<•-- 0
S-'s'ccr Box No. ' JE&
METER AH /, •-? V
C FACTOR
1
DRY GAS Pi tOt .
Clock METER. CF in. H20
Point lima r/7A ^ 	 AP •
': •'. .' (••:• ". ••'-, r, •!.-,
i i - ' •••-•':, /") ' <
Read and rscord at the start of
each test point.
PATHOLOGICAL- INCINHR'ATORS-
read and record every 5 minutes.

Orifice AH
in H,0
Desired
/.:-•:.
L '' "
Actual
: • • - "•
;. v--'
i - , . •.•[•-•
; . j ......
^ . ; •• • . I . , .- - 1 ...
Y i '•„..[- - • j - : '• '
,•.."...!• ' i .--
! i • ..•:..., - -. , .
i i i • • •


Dry Gas Temp.
o —
r
Inlet Outlet
• •""> !,•- "
v;7-/. .-'..-2
•^? .'

< ,-. -'_- -; ,..-,.
- •> -
- - .• -
.'. -~.-r-
- .-• -
j . ;'K- --••-, .- .. ,-• .,' . - - - .-•
1- • - i '.I--- •-•'? -- .1 i " "7 i r? •>.-!
i . •:-• •--
— • ^. .,-•
. -: v
:~ ' '. '•"
•zi -• -i i
Ambient Te
Bar. Press
- Assumed We
Heater Box
Probe Tip
Probe Ler.g
Probe Heat
AVG. AP
Pump
Vacuum
In. Hg
Gauge
u
Box
Temp .
Op

- _.
. / -•. •
:mp °F Ast ° '
. "Hg
risture % J^ "^
Ic^/-/.--^,.- op ~« - •-
oe vi. i iiy » r
Dia., In. ^/./
th c; '
.er Setting . •"
«?,«•' . AVG. AH ,
I~,pir.ger Stack Stack
Tc-Tsp Press Tcrr.o
°F in. Hg °F
.•-:•-. t /^
i -',-0
1 / • . 1
• .- i . .- -
•; -•'
.-' -r
•r. .'•
,'•'•"' O --• "X -7 j . '. ,'-'
.. , ...
-.' . 1 •"•
- '. ' -
, -. --. _., ^.
-• .' •
'•I ' / -f
• , ..'. J -, -:. (. ...

-~',; , '/.'•.,,,-! --•'••• - - ! '• .'.--' ?. /.- i j <" •/.•/ 1 -v-v i .--.-..•:•
! ::-.«. o/, :.i •-. -- . -. -// i -> ..: " \ ?. .0 o
-. \ - K-, '.! O./ 7 - S3 i '• -0
•/.'... -.,..: 1 C, :'_
'' . 2. »
? . / O

/-/ t -/•->
/' ' -•
/ / .••... •/ n
I
.' --
S , o
t".
1
' • • 1 '
! 1 - ,
1 i / -
./. ! i •
.--.--. ! 1 / - -
i
i i • -.^
I i '----I
1 i " •
! ! .'••••-:> !
' i" '-. ;' o
\ !
KCAP-37 (12/67)

-------
!
1
;Cc:::~e:-tc
"<•>--'



S























•













\
j Clcc::
I Ti:-:2

• -• •... . - -.....•„
!.//,.«;,..'..

• 'i '. • -• .; ... .'.-
-' • tt
	 /* f .. IV. •
-£^/^I...'M
















'


.















;
| Dry Gas
; Mot:;;-, CF
i /•"*•..;•
.-,.•/- 0, --VO
i £?<-.-•:. /£-
'-'. ' .-• . -> .^
, ', - z>.~ ?
A '9/0. '. ~>
-7 n -y . •? <-/-

?.3I. t-'V !




!
i


•



1

•
i
1

i
i



.
I
1
1
I
i
i
' !
!
I
!
I
~ Pi tot
in. HoO
Ap

^. ,-,r
O . <-, >/

































j Orifice
I i:"! i>
De-sired
!
1 -7 •=• .-•-
' x-, -3^
.^?. ,"? O
^ . o .0
3. . ~ ^



'
































A:-
>o
] Actual

i -../o
^ /y^
?.5.<
(
'"^ "^ i^

|
?.J9











.





















" Dry Gcs
or
1"
T " " ,-. >
i ii ; U <.
i
1
i /o '.
/'/ O
; /.c
/ -1 -r
• ' rf/

~^-~



.








.

'
V












J-





1 tn-.p .
Outlet


& w
P-;

.•.»"


































•

Vacuuw
In. Hg
iGiuse


5-.0
^. .<
! .-.-. ,->
.<.^
"





i

.
'

























•
2c;<
Tj-.-r.'-v
* \~.'.*~j »
°F






































.



Iir.p'ir.ccr b.-c:: i ^•_.cu:'.
Tar.:0 SProsi i T--1
O^~ Jj^ '.'••*' ^*TT
i »
' ' •
,- •" .'"* 1 ; • ' -^
C'1 ' i /7./3
^,.0 1 ! //<*
.<•<- 1 //-r'
t-r> \ ' //.<"
: ;
i !
j
i
•
i
t
i
i i
! 1
j :
; i
i *
•
!
i
i j
; 1
1
!
i
i

i '
i i
i i
•
1 i
J j
!
! !
! !
i
i i
i
! !
! i
: i
i
i
! i
i
! !

-------
                        PARTICULATM CLEANUP SHEET
oa to dVJL 2- 6 , / 1 7 /
3 - - /
j
,un Number £>ty
L
Operator: /}?(££-
\
Sample box number : -S/?-
Plant: JJ ^^,- 7W, ««^V^.- W
Location of sample port:
Barometric pressure:
Ambient temperature:
:1 """ ' 	 ' • ' — • , " — •
Impinger H20
1
jVolume after sampling
TVolume collected
j T .
tf • "*
^ *>•*/> / S&Q *j>» t-t- /*'/ (2
«?*.- /OO'V"* *Ti.^ /* *i.
ml -3 £^,v,|Ttr Impinger pr<
mi i^^^ir^'
V ^e^.A. rti£
=>fATea-with . ml
; oo o-4
^Impingers and back half of
i  filter, acetone  wash:
                                         'Container No
                                         Extra No.
Probe, cyclone,  flask,  and
  front half  of  filter,
  acetone wash,;
                                         Container No,
                                         Extra  No-
Filter number
          *•
                Filter Papers and Dry Filter particulate

                        Container number  Filter number.
                 Container number
 Silica  Gel
  Weight after test:
  Weight before  test:
  Moisture weight  collected:
  Container number:           1
                                 y7
                                      2.
3.
4.
  ^50  -7'^
^J^7__
  .  -2-»-£.
         io f~~j
          -3
Moisture
total    J?7..t> ?•
 Sample  number:
                                                  Analyze for
 Method  determination:
 Comments:
  8 -

-------
                        PARTICULATE CLEANUP SHEET
 a te
                                         Plant; j/xW :>'... T->

 .un Number    5 A _ /.(. .'-•,0 . J ...
sampling ml •$ f,.^ -Impinger "pr
7 .00 W .''/-'^ / /rC£^
:ted ml ^. /o° /-'„•_.% ov
1 	 <• • »- '

flJSj\j^
2"f Tiled with ml
'lOZ.t^
••>.<. ,
                                      £-1 it-
"Impingers  and back half of
j  filter,  acetone wash:
                                         Container No
                                         Extra No.
 Probe,  cyclone,  f^ask,  and
  front half  of  filter,
  acetone  wash:
                                         Container No,
                                         Extra .No.
                Filter Papers and Dry Filter Particulate

Filter  number          Container number  Filter number         Container number
 Silica  Gel
Weight after  test:
Weight before test:
Moisture weight  collected:
Container  number:           1. &£)
                                    i/
                                  A 9
                                          2-3. 0
                                               3.
                                                      4.
                                                                    4,
Moisture
total
                                                                          13 .6
 Sample  number ;   EJ B •
                                                  Analyze for
 'Icthod determination:
 Comments :
   .
 J

-------
                       PARTICULATE CLEANUP SHEIIT
                                        Plant:
    Number
                     /2-fl C /
Operator;  j'/:GLt  JC~
?ample box number ;
                              /
                                        Location of sample  port:

                                        Barometric pressure:_	

                                        Ambient temperature:
i
i
Impinge r H?0
i
jVolume after
Volume collec
-i
^Impingers and
2Wiv' C>»-.A' • /^AkvX/.c!
sampling ml ^ £••'•'* Impinger
V /o/ -*JL H n% f h t. L.
ted ml A: 
-------
                        PART1CULATE CLEANUP SHEET
7:)ate £y~ G
pperator: hjtr-J 3"C
^
s
Sample box number : SyEf
Location of sample port:
Barometric pressure:
Ambient temperature:
i ! j
Impinger HpO
I
..Volume after sampling ml
Volume collected ml '
1
Impingers and back half of
filter, acetone wash:
Probe, cyclone, flask, and
: front half of filter,
acetone wash-
/
2_ /^O *»J? //'<,o (p-S ) QQ '/)L-''
Impinger prefi i^Ved-Vwith ml
«-A •G-fv.-ly\ "^ —
'/ A£d*_ C~*J
^ T£. / Container No.
l'D' Extra No.

.Container No.
Extra No.

                Filter Papers and Dry Filter Particulate
i
Tilter  number          Container number  Filter number
                                                               Container number
 Silica  Gel
Weight after test:
Weight before  test:
Moisture weight  collected:    37.7 t+~-j)
Container number:           1. #y   2.
                                              3.
                                                      4.
Moisture
total   J7.7
 Sample  number :
 Method determination:
                                                  Analyze for
Comments :
                                        Q> y>3^

-------
                           APPENDIX    D
                         .  ENVIRONMENTAL PROTECTION AGENCY
                     -  ....           Office of Air Programs
                        Research Triangle Park, North Carolina 27711

Reply to
 Attnof:          '  .              .                                    Date: -70CT 1971

 Subject:  Beryllium Testing Methods Development
                                          x
     TO:  Acting Director, Division of Compliance

         1.  A test plan has been developed by the Chief of Stationary Source
         Emission Methods and Measurement Section (DCP), who will  fund the test.
         An exact description of the test follows:

            a.  EPA gas pumping and measuring equipment will be used.
            b.  The collection trains are listed-in Table 1.
            c.  The probe ind glassware will  be washed with liquid, the
                same as in the first impinger of the collection train used.
                •In the case of water in the first impinger, an additional rinse
                of acetone will be used; and an acid rinse will be used after
                the acetone rinse.

            d.  Each impinger will be individually "bottled".
                Each wash will be individually "bottled".
                Each filter will be individually "packaged".

                This will allow for Beryllium analysis of individual components
      •          of the collection system.-

           1 e.  The probes will be placed in the exit horizontal  stack 8 diameters
                downstream and 2 diameters upstream from any obstruction as follows
                in Figure 1.
                                                      HORIZONTAL LINE

            TRAIN "B" -«	/"     \  *>J  "K /'     J-	P* TRAIN "A1



                                                           PROBE TIPS


                                        Cross Section of Stack

                                             Figure 1
                 Isokinetic gas sampling rates will be used.  Single point
                 sampling will be used.  Mi Hi pore AA "filters with Whatman
                 41 backup will be used.
                                       4-2

-------
Page 2 - Acting Director, Division of Compliance


2.  Some input for consideration in establishing the test plan was
furnished by the Source Sampling Fuels Analytical  Branch (DAS) via
Darryl J. VonLehmden and Robert E. Lee, and the Emission Testing Branch
(DAT) via Thomas E. Ward and Roger T. Shigehara.

3.  The objective of the test is:                           '

        a.  To establish an acceptable method for the collection of the
            Beryllium sample from a machine shop source.
        b.  To validate (or invalidate) previous test data, specifically,
            The American Beryllium Company, and Speedring, Inc.

4.  The execution of this test is tentatively scheduled for October 25
through 29.  An alternate date could be November 1  through 5.   The place
is Cullman, Alabama, Speedring, Inc.,North Stack.   There is room at the
test site to accommodate up to ten people comfortably.

5.  This memo is to inform all involved groups of the test plan and schedule.
This memo is also to request input/concurrence in writing of the test plan
and schedule as they may apply to the involved group(s).
Robert E. Meligan
Acting Director
Division of Applied Technology

cc:   Mr. D. VonLehmden, SSFAB,DAS
      Dr. R. E. Lee, SSFAB,DAS
      Mr. J. Nader, SSEMMS.DCP
      Mr. ,0. Burkle, SSEMMS.DCP
      Mr. D. Patrick, NESDS.DOC
      Mr. J. Peoples, NESDS,DOC
      Mr. J. De Santis, NESDS.DOC
      Mr. J. McGinnity, ETB,DAT
      Mr. W. Basbagill, ETB,DAT
      Mr. R. Shigehara, ETB,DAT,CIS

Attachment
                                  4-3

-------