Test No. 71-CI-25
Speedring Manufacturing, Inc.
Division of Schiller Industries, Inc.
Cullman, Alabama
October 25-26, 1971
Thomas E. Ward - Durham, N.C.
Project Test Officer
Environmental Protection Agency
Office of Air Programs"
Stationary Source Pollution Control Programs
Applied Technology Division
Emission Testing Branch
Combustion and Incineration Section
Contract No. 68-02-0225
Task Order No. 3
-------
TABLE OF CONTENTS
I. Introduction ............ . .................. . ........ P*ge
II. Summary of results
III. Conclusions and Recommendations
_
APPENDIX
A. Beryllium Analytical Method g
B. Project Participants 71
C. Contractor report .............
D. Memorandum
.0
4-Z
-------
I. INTRODUCTION
The objective of this test was to determine a test method for sampling
beryllium emissions from metal machining operations. The test was conducted
at Speedring Manufacturing, Incorporated, in Cullman, Alabama, on October 25-
26, 1971. i
This metal machining shop controlls their beryllium emissions using a
"wet" baghouse. Standard cutting oil emulsions of various types, when used,
are drawn into the vacuum inlets which are placed at the interface of the
cutting tool and the machined piece; when they reach the bag, they "wet" the
bag.
Figure 1 shows sampling points.
"Standard Home-Type
Air Conditioning
Filters
(o)
f
^
Blower . . Baghouse
Sampling Point #1
Sampling Point #2
Manifolded vacuum
inlets, at least
one for each beryllium
machining operation
Figure 1
The memorandum from Robert Neligan to the Acting Director, Division of
Compliance (see Appendix D) describes the test procedure and plan as of the
October 7, 1971, date of that memorandum. On October 14, 1971, John Burkle,
.Project Engineer, instructed ETB to perform the test in two parts, the first
part to consist of two days of testing, and the second part (based upon
1
-------
acceptable results in the first two-day part) to consist of four days of testing.
The updated test method is shown in Table I.
\
\
Mr. Burkle authorized at the test site the duration of gas sampling time
to be five hours and to. change the sample "bottling" and "packaging" procedure
as shown in Table II. The stated reason for the packaging change was that if
the total filter and impinger train catch of beryllium was very small, then,
I
with so many subdivisions of the sample catch, the analysis data would be
"masked" by the analytical procedure.
Mr. Burkle directed that the trains be filled with impinger liquids,
assembled,' disassembled, and have their samples transferred to the sample
/
bottles, all on the roof of the test, site for 2a and 2b; and at a physical
'/ . '
location at least one mile away from the test site for 5a and 5b. The latter
work was performed in a motel room which was more than a mile away from the
test site.
Soda lime, 6-14 mesh, was used in the eighth impinger to protect the meter
boxes from any possible acid mist carry over. Figure 2 is a schematic drawing
of the test site.
-------
:"n
4 la
2a
'2k
!'3a-
'*4t
C5 O
10 6b
:". linrr Tr.-;r. i-* : 1 ) . .', i r. i ( A' J
Probe 1 Filter
Yes
Yeo
Yes
Yea
Yes
Yc»
Yes
Ye s
Yes
Yes
Yes
Yen
Yes
Yce
Yas
Yes
1:0
NO
No
No
Yes
Yes
Yes
NO
H,0
10% HCL
10% KKO.
"2°
10% HCL
10% KNO
"2°
10% HCL
3
10% HJvO
10% HCL
H,0
V
1C% HCL
10% H.-.'O
1O:'. !ICL
10* it:x>3
H20
s% n2 so
H£0
5% H2S04
H20
5% HgS04
10% UNO
10% HCL
V
H20
5% H_SO
f **
5% HjSO^,
Empty
Empty
Empty
Empty
E.T,pty
Empty
10X. UNO
10% HCL.
Kmpty
Empty
E,-np ty
F.rapty
1O% HCL
107. liN-C>3
10% UNO
IC'X. liNO,
10% HC1
10% HHO
10% iiCL
j.0% KNO
10% KC1
10% UNO
lirx. HCL
10% n:;o3
J.07. HCL
10% UNO
10% HCL
10.". ('.NO.,
Rer.ova e. , 5
) -'.'leer
"^ r
5'X H_SO.
^ **
5% K2S04
5% JU£C4
5% K,S04
SX "jSO^
5% H0S04
. nr.d 6
Removes 4, 5, and 6
Empty
J:npty
Empty
Empty
Erapty
:,.,pty
,,;>ty
Empty
Jinpty
No
No
NO
No
Yes
Yes
Yes
Yes
No
SO
No
Yes
!!r.;iir.gcr,y
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Silica gel
Si lie* go 1
Silica gel
g .
6^7
oil
K*J2
tcdl
6o«.
SW«.
«di
«c<*
BKV^KS
Comparison of Reagents
including clear, up
procedure except no
tl',:.,' collucLed und
onn unir.g method S tent train with -i.oJ if icjntiono shown in ti...- tnbicj>'nf It
r i/:pir.g._-rs upstream: w.-itcr-acetor.c war.h of probe.
imjMngnra upntrc.ira: ncid (10% IIC1, 1C/X UNO.) wash of probe.
I tor and c'tcn imp ing or analyzed for uc. " ~'-~~-.^
not spccifit-d as oin-^ty cont.'»in 100 ml of liquid ae J'pocif ic-d.'
na ao ahown indicate-the crUc-r in-urrich the cu.^plir.g train is pl.-vc.ec; to ;ot:
her. opecifie'd) '> Crecr.burg Smith Irpingers (as indicated) ; :iltcr" (w.cn
Sraitii Inpingcr containing adsorbent to protect the pump and dry gas moucr
Scith Icpingorn may be t>.a ^odific-J type. ,
i .j/ I i . i t I I I
a.T'tf- /1*\ J*in&.cr c^ i *
e BX
er
.-TV-/
:.-.C cro
isok
/J/ s 'Jt.
scection in
ir.otic
su p I in ff
her
spe
r....-.ioly :
cified)
probe
Table 1
1 9~7(
-------
TRAIN
NO.
5a m
5b U'
2a (3)
2b (*}
SAMPLE AS
GATHERED AND
PACKAGED BY ETB (1)
DESCRIPTION
Probe, water & acetone washings
Probe, acid washings
Filters
Impinger 1 (11), water
Impinger 1 (11), water & acetone
wash
Impinger 2 (12)
3 (13)
ii n ii
Impinqer 4 (14)
Impinger 5 (15)
II ii II
6 (16)
CONSOLIDATION AS
DIRECTED BY DCP
FOR BOTH DAYS (2)
SAMPLE
1
2
1 3
4
5
--'6
7
ANALYSIS DA
TRAIN NO.
5a,0ct.25
(6)
U>)
0.09(6)
FA IN uqm Be (4) (
TRAIN NO.
5b,0ct.25
2.85
0.21
FRAIN NO.
5a,0ct.26
0.9'.
(6)
(6)
5) (7)
TRAIN NO.
5b,0ct.26
Trains 2a & 2b
were reduced to
four samples (3)
No.2a
Oct. 25
No.2b
Oct. 25
(1) On the first day, Oct. 25, 1971, thirty samples were produced and packaged by ETB: 15 for 5a & 15 for 5b. These
were consolidated to fourteen samples as directed by DCP, 7 for 5a & 7 for 5b.
(2) On the second day, Oct. 26, 1971, ETB was directed by DCP to package fourteen samples for trains 5a & 5b, as in
the consolidation described in note (1), above. ^
(3) ETB was directed to consolidate these samples into four containers as shown above in the right hand side of this
Table II and in Table A-II.
(4) All values are <0.15 unless otherwise noted. See-Appendix A.
(5) See Table A-II for .blanks (acetone, water, acids and filters), for which all values are <0.15.
(6) See Appendix A for a description of these values. ^ -
(7) Gas volumes ranged from 231 to 269 ft3 at the meter.
TABLE JE
-------
FIGURE 2.
TEST SITE , SP£UTDR»NG- , INC.
CUULMAN , ALA
A
STACK
G-bS STREAK)
A
m
TWO TOTA^
EACH SiPE
"T
/' DIA.
A-A
SIDE: VIEW
HORIZOMTAL
5a
STACK EXTENS/OM
GAS
SP
FILTER
PLAN
a
-------
II. SUMMARY OF RESULTS
Table II shows the summarized results of the beryllium samples. Seven
samples from each of four runs made a total of twenty-eight samples. Only
three of the twenty-eight samples yielded values >0.15ug beryllium. One of
the samples indicated that a small amount of beryllium, 0.09yg passed the
filter.
Sample gas volumes were 231 to 269 ft .
Table A-II, Appendix A, shows all of the results of the beryllium samples
with appropriate identification codes. The contractor report is given in
Appendix C. The source sampling contractor was instructed to spend no more
than eight man-hours in preparing the report, to include as a minimum a copy
of the raw data sheets, and, as the eight hours permitted, total volume cal-
cidations, isokinetic sampling percentage calculations, and.normal report writing
efforts.
\
The reason for this eight hour restriction was that for this particular
test, the Project Engineer was interested in total volume of gas sampled, and
a very brief report of activities at the test site. The report is excel lent,and
was submitted within six working days after completion of test..
-------
III. CONCLUSION AND RECOMMENDATIONS
The total beryllium catch in the sampling trains is considered too small
to allow conclusions to be drawn about efficiencies of the separate portions
of the train. In turn, no direct recommendations for improvement of the
beryllium sampling train can be made based upon the results 'of this experiment.
The proposed second part of the experiment is cancelled because the results of
the first part indicate that not enough beryllium is in the stack gases to allow
a "train efficiency" experiment. No well founded conclusions can be drawn
relative to previous beryllium testing indications that beryllium stack gas
contaminants are getting "through" filters. It is recommended that a known
source of beryllium be obtained for any further testing. This could be a
commercial or Atomic Energy Commission stack; or it could be a substitute
source such as a lathe which is machining a given amount of beryllium under
JTAC K
controlled conditions as shown below in Figure 3.
FILTER
VACUUM nose
\
.._ CUTTING.
TOOU
BERYLLIUM P°RT ** ' FS'OFrr'irZ
CYLINDER
FIGURE" 3
-------
APPENDIX A
SUMMARY OF ANALYSIS METHOD FOR BERYLLIUM SAMPLES
York Research, Incorporated, used the EPA suggested method to analyze
the beryllium samples. In outline form, the chemical portion of the method is:
1. React with nitric acid
i
2. React above solution with sulfuric and perchloric acid
3. Evaporate to near dryness on hotplate
4. React (dissolve) in hydrochloric acid
5. .Bring to 5 ml total volume
A portion of the 5 ml (usually 1/2 to 1 ml) was decanted and aspirated
into the Atomic Absorption (AA, Perkin-Elmer Model 303) flame. The absorbance
'/ ' .
line produced was then compared to a graph which was previously drawn by reading
absorbance of known concentrations of beryllium solutions. York Research, Inc.,
reports that with their AA unit sensitivity setting of 1 (on a scale of 1 to 10),
and with 1% absorption, the AA will allow a reading of 0.03yg !-3e/ml. This is the
setting which York Research, Inc., used in all cases except the reruns (sample
Nos. 165, 167, 168, 181 and 182 reruns). Those five were run with a sensitivity
setting of 5 which York Research, Inc., reports will allow a reading of O..006yg
Be/ml.
8
-------
Table A-I below shows why the values <0.15 and <0.03 must be used instead
of zero when reporting "negative" analytical results.
TABLE A-I
BERYLLIUM ATOMIC ABSORPTION (AA) READINGS
Sensitivity setting
on AA
Capability of
Sensitivity Setting
in yg Be/ml
Sample volume
as prepared for
Reading by AA
in ml
Minimum Content
of Beryllium
in 5 ml which will
give a reading.
yg Be
0.03
0.15
0.006
0.03 .
Table A-II shows all of the results of the beryllium samples with all
appropriate codes.
-------
TABLE A-II
CODE:
Be - Beryllium
SI - Speedring Incorporated
N - North Stack
2a, 2b, 5a, 5b, - See Table I dated October 26, 1971 - Test Method
P - Probe
F - Filters
11, 12, 13, 14, 15, 15 - See Table I dated October 26, 1971 - Impinger Numbers
Sample No. Code
Description/Date
Analytical Results
yg Be all values
are <0.15 unless
otherwise indicated
151 Be-SI-N-2a-P
152 Be-SI-N-2a-F
153 Be-SI-N-2a-ll, 12, 13
154 Be-SI-N-2a-14, 15, 16
155 Be-SI-N-2b-P
156 Be-SI-N-2b-F
157 Be-SI-N-2b-ll, 12, 13
14, 15, 16
158 ^Be-SI-N-2b-Back Half
159 Be-SI-Whatman 41
160 Be-SI-Millipore A7T
161 Be-SI-Sulfuric acid 10%
Water & acetone washings 10/25/71
Filters . 10/25/71
Water, water & acetone washings 10/25/71
Acid & acid washings 10/25/71
Water & acetone washings 10/25/71
Filters 10/25/71
Acid & acid washings 10/25/71
Back Half of filter holder only 10/25/71
BlanL^fiHer 10/25/71
Blank filter- 10/25/71
Blank filter 10/25/71
10
-------
TABLE A-II, continued
Sample No. Code
Description/Date
Analytical Results
yg Be all values
are <0.15 unless
otherwise indicated
162 Be-SI-HCL 10% Nitric 10%
163 Be-SI-Acetone
164 Be-SI-Distilled Water
165 Be-SI-N-5a-Pl
166 Be-SI-N-5a-Pa
167 Be-SI-N-5a-F
168, Be-SI-N-5a-ll
169 Be-SI-N-5a-12,13
170 Be-SI-N-5a-14
171 Be-SI-N-5a-15, 16
172 Be-SI-N-5b-Pl
173 Be-SI-N-5b-Pl
174 Be-SI-N-5b-F
175 Be-SI-N-5b-ll
176 Be-SI-N-5b-12, 31
177 Be-SI-N-5b-14
Blank filter .. 10/25/71
Blank filter 10/25/71
Blank filter 10/25/71
Water $ Acetone washings 10/25/71
Acid washings 10/25/71
Filters 10/25/71
Water, water & acetone washings 10/25/71
Acetone washings 10/25/71
Acid & acid washings ' 10/25/71
Acid & acid washings 10/25/71
Water & acetone washings 10/25/71
Water & acetone ' 10/25/71
Filters 10/25/71
Water, water & acetone washings - 10/25/71
Water, water & acetone washings 10/25/71
Acid & acid washings 10/25/71
<0.03
<0.03
0.09
2.85
0.21
n
-------
TABLE A-II, continued
Sample No. Code
Description/Date
Analytical Results
ug Be all values
are <0.15 unless
otherwise indicated
178 Be-SI-N-5b-15, 16
179 Be-SI-N-5b-Pl
180 Be-SI-N-5b-P2
181 Be-SI-N-5a-F
182 Be-SI-N-5a-ll
183 Be-SI-N-5a-12, 13
184 Be-SI-N-5a-14
185 Be-SI-N-5a-15, 16
186 Be-SI-N-5a-Pl
187 Be-SI-N-5a-P2
188 Be-SI-N-5b-F
189 Be-SI-N-5b-ll
190 Be-SI-N-5b-12, 13
191 Be-SI-N-5b-14
192 Be-SI-N-5b-15, 16
THE FOU.CHING- WETfe REANAI-YZerD OSi NG- A
_R£F?UK 165
-RERUN 16 I
RE RUM i6£
ISZ
Acid & acid washings
Water & acetone washings
Acid & acid washings
Filters:
Water, water & acetone washings
Water, water & acetone washings
Acid & acid washings
Acid & acid washings
Water & acetone washings
Acid & acid washings
Filters
Water, water & acetone washings
Water, water & acetone washings
Acid & acid washings
Acid & acid washings
0w THE: ATOMIC
10/25/71
10/26/71
10/26/71
10/26/71
10/26/71
10/26/71
10/26/71
10/25/71
10/26/71
10/26/71
10/26/71
10/26/71
10/26/71
10/26/71
10/26/71
I0/25/7'
0.90
<0.03
<0.03
THAN rue
12
-------
APPENDIX B
PROJECT PARTICIPANTS
1. Emission Testing Branch, ATD, Thomas E. Ward - Project Test Officer,
on-site during source sampling
2. Stationary Source Emissions Methods and Measurement Section, DCP,
John Burkle - Project Engineer, and Roy Bennet - Observer, on-site
during source sampling.
3. Engineering Science, Incorporated, Washington, D.C. - Contract Source
Sampler.
4. National Emissions Standards Development Section, DOC, Dave Patrick -
Observer, on-site during source sampling.
5. Source Sampling Fuels Analytical Branch, DAS, Darryl J. Von Lehmden -
Observer, on-site during one day of source sampling. Mr. Von Lehmden
is the Project Supervisor of the beryllium sample analysis.
6. York Research, Incorporated, Stamford, Connecticut - Contract Beryllium
Sample Analyzer.
13
-------
SOURCE TESTING AT SPEEDRING, INC.
A REPORT OF FIELD TEST RESULTS
ON
BERYLLIUM MACHINING OPERATIONS
AT
SPEEDRING, INC.
CULLMAN, ALABAMA
SUBMITTED TO
MR. THOMAS E. WARD, PROJECT OFFICER
OFFICE OF AIR PROGRAMS
ENVIRONMENTAL PROTECTION AGENCY
RESEARCH TRIANGLE PARK, N.C.
CONTRACT NO. 68-02-0225
BY
ENGINEERING-SCIENCE, INC.
600 NEW HAMPSHIRE AVE. N.W.
WASHINGTON D..C.
NOVEMBER 1, 1971
LS
-------
INTRODUCTION
On October 25 and 26, 1971 stack emission tests were conducted
on beryllium emissions at the Speedring, Inc. plant located in Cullman,
Alabama .under contract number 68-02-0225 and Task Order 3. The main
purpose of these tests was to evaluate a sample collection method for the
hazardous pollutant, beryllium. Results of the mofified sampling train
are intended to provide the basis for determining the most feasible
method for sampling beryllium.
All sampling was conducted under the direction of the Office of
Air Programs, Environmental Protection Agency. Mr. Thomas Ward,
Project Officer, EPA, et. al. developed the method which uses eight
impingers in series with special reagents in .each impinger. Two com-
plete trains were run simultaneously and, in addition., two "background"
trains were set up to determine potential on site contamination.
Testing was conducted after the plant began machining operations under
normal operating procedures and regular work day.
Mr. Ward assisted in engineering a through test by arranging for
stack extension, ladders, electricity, and other test facilities,
t
providing the special reagents for the several impingers, and assisting
in sample recovery to assure proper handling and disposition of each
speciman.
All samples were turned over to EPA at the conclusion of the field
tests for subsequent analysis by EPA. Under Mr. Ward's guidelines one
man-day of effort was used to prepare this report. The report contains
two sections in addition to this Introduction; a Discussion which
describes the test procedures and an Appendix which includes copies of
the raw field data.
-------
Messrs. Michael E. Lukey and John Chehaske conducted the field
test for the EPA, made the associated calculations and prepared this
report. This report does not contain a discussion of the laboratory
results.
17
-------
- DISCUSSION
The purpose of the two day source tests was to determine the
s
feasibility of a modified sampling train for testing the deleterious
pollutant, beryllium. The plant was located in Cullman, A?.abama
and produced machined/tooled beryllium components. The machining
operations are similar to mild steel machine shops and include
I '
drilling, milling, cutting, sanding and close tolerance lathe operations.
Because beryllium is a brittle metal, the machining operations emit
a fine metalic (beryllium) dust. Speedring, Inc. used a vaccum system
connected to two baghouses to remove the dust from the work area.
All .of the' testing was performed on the north stack, on a roof top
with a,/halfmoon shape. Mr. Thomas Ward, EPA Proj'ect Officer, made
<
arragements for the temporary stack extension (made of sheet metal
having one foot inside diameter), electricity and other ancillary
supplies.
Beryllium emissions are quite low when compared to other mass
emission rates from combustion sources. No visible emissions were
noted during any of sampling periods. The filters were checked
periodically during the sample runs (as a check for rapid buildup)
however, only slight color change existed at the very end of the sam-
pling time. Because of the low emission rates, the conventional par-
iculate train (EPA Method 5) has to be modified to improve the collection
effeciency of the sub micro particulate. Eight impingers were used
in series with a variety of reagents. The first two impingers contained
100 ml of deionized distilled water. Impinger three was empty.
-------
Impinger four contained 100ml of an acid solution (HC1/HNO-) .
Impinger five contained 100ml of suifuric acid solution. (The
exact concentrations of both acid solutions were not reported nor
asked for by the test team. Impinger seven contained 175 grams of
silica gel and the'last impinger contained about 50 grams of soda
lime pellets to protect the pump. Figure 1 shows the schematic dia-
gram of the sampling scheme.
A total of six runs were made over the two day period. Two
trains were run simultaneously during all tests. Trains labeled
5a and 5b were assembled in a inotel room located approximately 8
miles from the test site. In addition to these two complete trains,
two "background" stations were setup (assembled and reagents added)
on the roof top of the plant and the probe tip was placed in the
stack. No sampled air was pulled through the background units 2a
and 2b. These units were set near 5a and 5b for the same "run"
time. Sample recovery for the two background units was made on the
roof top of the plant. Sample recovery for 5a and 5b were made at
the motel room.
Figure 2 shows the stack configuration and sampling points for
the two units. A velocity traverse was made to determine probe tip
size stack velocity and flow as well as tip location. The probe
tip was placed at the point of average velocity and not moved during
the entire sampling periods. Figure 1 and Figure 3 indicate the exact
contents of each of the trains.
A summary of the field data and calculations is offered in
Table 1.
-------
The stack temperature was nearly constant and did not vary more than
10 degrees from the average temperature of 110°F during the entire
sampling period. The average velocity of the stack was 44.7 feet per
second. The flow rate at standard conditions (70°F and 1. atm.) was
1805 scfm. The four sample volumes ranged from 231 to 269 dry cubic
i
feet with an average of about 250 cubic feet. The moisture content
for four samples was about 3.370.
The actual field sampling was without .incident for the two day
tests. Only slight adjustments had to be made to obtain the sample
flow for isokinetic sampling conditions. All of the raw data
sheets appear in the Appendix.
-------
APPENDIX
FIELD DATA SHEETS
21
-------
FIGURE 1
FIGURE A-l. ParttcuUte Saapllng Train.
Buttonliook-typc probe tip
Stainlrss Stcul Coup ling
Probe
Cyclone and Flask
Fritted Clnss Filter Holder
Ik-occd S.-rr,plc Ho*
7. Ice Bath
12. Tlicrv.oncter
13. Check Valve
K. Lnbilical Cord
IS. Vacum f.iuge
16. !:ccdlc Valve
17. V^CUIUTI pur^p
18. 3y-?.is3 Valve
19. Dry Cjs I'.i'ter i
:0. Calibrated Orifice
21. Inclined-Vertical Manometer
22. Pltot Tube
SAMPLE NOS. 2a, 5a, 5b OCT. 25, 1971 and 5a, 5b OCT. 26, 1971
IMPINGER NO.
II
12
13
14
15
16
17
18
IMPINGER CONTENTS.
100ml. HLO
100ml. HO GS Impinger
Empty
HC1/HNO, solution
100ml. H SO, solution
Empty
175 grams of Silica Gel
50 grams of Soda Lime
ZZ.
-------
31-
1 Ft. Inside Dia.
Outlet
O
103'
S-l = SAMPLE BOX #1
S-2 = SAMPLE BOX #2
89"
0 i »
CROSS SECTION VIEW
OF SAMPLE PORT
FIGURE 2
STACK CONFIGURATION
-------
FIGURE 3
STACK WALL
'/
\
I \
r ~~\
V
r ~\
\
r \
II 12 13
14 . 15
16
17 18 I
FIGURE Arl. ^articulate Sampling Train.
I. Buttonhoolc-type probe tip
2. Stainless Sltul Coup line
3. Probe
4. Cyclone and Flask
'5. Fritted CInss niter Holder
6. Ui.-3t.cd S.x-plc Box
7. Ice Cal.lt
12. .V!\cn=
-------
SUMMARY OF FIELD DATA
Sample
Number/
Date
5a/0ct.25
5b/0ct.25
2a/0ct.25
2b/0ct.25
5a/0ct.26
^ 5b/0ct.26
v - .-
Start- Sample Sample Average Moisture Probe Probe Precent Average
up Time Volume Stack tip length Isok£netic (in.H20)
Time (min.) (ft.3 dry) ~Temp.(OF) (%) size (in) (ft) /
_ AP AH
09;00 am 300 248.98 112 3.3 % 5 96 .53 2.34
9:00 300 269.05 112 3.4 5 103 .55 2.42
9:00 -* - - - % ' ' 5 -
9:00 -* - - % - 5 - -
7:24 300 253.03 110 3.2 \ 5 97 .52 2.19
7:24 300 231.69 110 3.3 fc 5 .90,. .48 2.33)
* Background samples
-------
Test. Ilo. ~7-
.. -... .j«~r_ ^.^,
Date
A. Hist. frc-~ inr, id? of fo- ^;-;!l tc o-.j'.c.
near v/3li, i:; ., - '^. __ . _ _
i-K^Xitt '")^'l^i *&X4.4& j
B . We 11 t h i ck rie :, s , i n . , = "
.. Inside .diameter of staci: = A-P>
Stack Area = __
Co;;i:ients:
Sketch of stock cross-section
shO'-.-ing sr.nplinq holes
Calculations:
H>3i»
3 '
V
£>UTi£T
Point
!
%
3
^
S
&
X Die. for
circular stack
ci, v
/vJr 7
?. -'' 5
70- >
.-?-,..?>
^?s,t
I
Oist. from outsidf: !
of sa~nle r,ort, in. '
1
O.S !
/, ?5
j.s i
? c; 1
o ..5 i
i
&* \
\
'//,-*_ .. \
i
i
i
1
1
i
i
i
1
Cfilculator
-------
. VELOCITY TRAVERSE FIELD DATA
/I
Plant
test
£>
Location'
Operator /;;/ry, ^7" d _
/ ~
Meter AH
(l)-'AP, in. H90 Average
£. - ____
(2) AP, ir., I-LO Average
--1 J -i- -r-
Clock
T i iiic
Point
i
2-
^
^
5
fc
fe
9
lj_
3
Z
1
' .0)
AP, TT~H?0
0 ,31
0,3'fr '
P.^-
yo,v^
O. <7 1/
0,Jtr
6,38
^V-3
a^
' «^7
a^o
0,37
nfr**
nM^
.
ill
AP, in. H,0
.
'
v flif j T /I HrjH !
«- i
Sta<
(
//
"!
-
'
T
T"
.L.
i
-T"
CoMw.ehts:
-------
Scir.pl i ng 1 ccsti on - £V
N * -'~L-*"~m ' '
\
STACK DATA FOR NOMOGRAPH:
1. Meter AH I. 33 in
. ' . " '" ' '
t
2. Avg. meter tempt (ambient + 20°
3. Moisture (volume)
/
4. Avg. static/press. * . Q.2-S in. 1LCX.073 - -! -;o 2^ in. Mfj.
/ "~~ "*" ^. -.. ..
'/.- . ' ' ..'" .''
* . . . '
5\ Bar. press sampling point 2.*?.37- in.Kg + ;oz (static press inlllg)
3V in. iig. - - . . .... ;. .. .' . ...
G. Bar press of meter -z.q.3 2- in. l!g.
7 P /P - 5. 2.q.3'/'_ in. Hg
' rc-/'ir> ~ ~ -
Ge Avg. stack temperature //^). °F. ;'.
9. Avg. stack velocity (AP) 0. V in H^O. MAX. VELOCITY,.
C factor (1) -. 1.IZ (?.}
10. Probe Tip size ^//'/.'v.r.L. Sl*>.i*^>
-------
PLANT
Run No.
Location
Date
J
. /?/
Operator c-' .' . -''£-
:UAiA
VERY IMPORTANT - FILL IN ALL BLANKS
Read end record at the start of
seen test point.
PATHOLOGICAL INCINER'ATORS-
read and record every 5 minutes.
Ambient Temp °F
Bar. Press. "Hg
9;. 3
Assumed Moisture % L. O
Heater Box Setting, °F
Sr~*in 1 c* Rn.v Mn
t-« *\fJt\~ L' W' iTb I W
i-'.otcr Box No.
l-ETER AH
C FACTOR
Probe Tip Dia., In. o.
Probe Length *? /-y
/.. y/r
Probe Heater Setting Q
AVG. AP
AVG. AH
i
Point
i «
( *
i
i
1
i
'
-,
, --
"
Clock
Time
O ','/« i
,s-
-s.-r
4- <"
')
f.-u. /;-r.,.,'
Vf
_
-
... ,
..- -. J
0 , ,(. J.T,
';, rn
-=-.. / .;
DRY GAS
METER.CF
(,3V. 2/7
£-£ A -":?/
^, rf.'-/ -^y
S, .v/.. c--. r>
fb~7 3- ~7^
''*-. "?X-. -04-
/.-<' . /.:.
-/./ "; .
-, . ... , -.
-' - ; .~ r>
.- .-, .7
Pi tot
in. KgO
AP
o.- --yd
n.^'i
n.*-i
o.. Jl
- ... 0,
' * » ~" '*
** y. ?
"»
,-).--<,
s- .-.--!
.0 ^-o
Orifice
in Hc
Desired
J7, .. Z>. O
3, , "^ .-5"
__
;2. .'^ s'
.^ . ^ 5"
.-7 . ; ,>
-,.--
^,- -' '<
' ^ . -T /o
.-. ^- .^.
-> .- --
-? -i" -"
^ ,-r.<
Dry Gas Temp.
°F
Inlet Outlet
V-f- -7 ..
y -y ci -y
^ "2- 7 /
> -S' -7 .i?
9/v- 7.-T
7 7 7 J-.
'V -,
o ;-. - :;
* ' ''»'*'
CD ? - '7
/ :0 ,0 ff .-)
; ', ,'" ::- /
/.OJL N?.i»
; .-, 0 ^ -,
x--.s-> >? /
Pu^ip
Vacuum
In. Hg
Gauge
3 \'"i-
^. .-r
..^ .. -5"
^t ^
'f <^
-^. ^
.:>
(>.?>
' . ^
-J. .-r
i -rT"
-=-?. .-^
-^. i^
n
Box
Temp.
°F
Invpir.ger
TCTip
" °F .
<-:-
6,0
O
, ^
'. r.<
:'
i
- -
s. -r
." _-'
^ -r
/:, _---
^".-r
Press
in. fig
Stack
TC.T.O
°F
/ / O
no !
liO
J /Ci
4-^?>
/ "-" " *
*\
*'
- .
.' ' ->
^
t i i_
. . ,
i ->
KCAP-27 (12/67)
-------
;L, c-:...^:-.;. ;
> s+ ... _^ _~-
;'
, .--',-' " i
ZT& a.-!'
; x »
"
i
j ; '.'.:;
i
'. ~ '. . T '
'<;,,. ,'.-....:.
.1)-, ,^ ;,...',
1^,,^
J.}.. . -: ' ....'.
s\.f ., '. ..
'
'
.
\ p G,s
! Mo-:-r5 CF
p'.r ,-,' .^> t
-P .- ^, _-r ,0
SG 6 , 7y
:-"'V.-i . .'.-:'
Sv^ -? s Z*
9 -T ', ' 4-
. '
;
in. K?0
Ap
<^ s'/s,
^), <^"
/>. -v.-^
(5/c:^
r>. "-.<
^. £' -^ '
'&-* 0.5" 5"
v
*" Orrf': co
Dos i red
i
I .- 1 <"
^.v^
i * -"*
.-?../ o
.0 "
7 Ac^us 1
-? ..^ -'
_J? -/-<9
2 J..^
3 -~~-r'-;-
.r ..'/?
/M... ?.'/?-
^
Jry tTcl
! °f"
In "let
i
! /^o «'.
/,o.--
i as
1 /OY
y/9 <.-
"^~-
" Tc;v.p .
0-jtlct
57 ^
^*
,!^>^
f9^
^/^
:v/?
In. Hg
Gcu{ie
^''J A -^»
6/r?
; ^
^l<
'"
'"'*
°F
.
Tcr.:o" iPrc;: I Terr; *\-
CF :-;:-!. i:~ °" i
! ; .
1
.v.o; - \ )IJ? '*
& f \ .' c o 1
krt i/.1^ !
.', 1 // <"
,'..-- 1 .- -;.' "
i 1
i
;.
I
i
! '
i !
! i i
i
!
1 i i
; . -'
i .
1
i [
i ;
!
i i
t ;
! ! !.
!
j :
|
' t-
i i '
!
i
i ;
i i i-
-------
YART! cue ATL~ ~~ ID ' DATA
PLANT
Rur. No. ' ^,4_ VERY IMPORTANT - FILL IK ALL
Location ',. ' ... . /'. (!
Date ,«.-; -N. tf~>.l
Operator .>. < T$ L
Sample Box No. S:-,}\
I-'.eter Box No. .''/"
METER AH /.Lp;
C FACTOR
1
DRY GAS Pi uOt
Clock METER. CF in. H20
Point Time f ^ ..;..--.. : AP
i i ^ * - .. . *
! - / ..
i -.- 1 '
Read end record at the start
each test point.
BLANKS
of
Ar.ibient Temp °F ~?o
Bar. Press. "Hg ? >?.,3z_
Assumed Moisture % /%
PATHOLOGICAL INCINERATQRS-
read and record every ;~5 minutes.
Heater Box Setting., /0F
Probe Tip
Dia., In. //^
Probe Length .cr '
Probe Heater Setting .
Orifice AH
in H,0
Desired "j Actual
'.;.-: '. '
-~~ .'"' .V " .' *^~'
| -. r~ ,'_> \
\ , .
!-/. ..-.... 1 ......
' ,
1 , . . . .. -, - .. .., _,. -.
. ,
! / ' - - '- - --.-' ' . -. '
i - j, . , , - -
1 " . * '
- . i -
. .- -. , ..
-:. ; - -...-.
Dry Gas
°F
Inlet
Temp .
Outlet
'', . .
. -. . .- ..... j -,...-
. ., ..-.,.
).-'- > ' :'
!->..-- .-. .^. -'. 1 .- - , L -. - - ' .-, ;
! ! ' -.. r . _ ., j - .- -
j
i -;.. ;c,:,,;. i /!.>/. ^'/ o. / o
:>.'/<> ?.,yo
\ \ \
. . .
/of> tfC
//V 9o
t,om;r.er."cs ' . .^y-^--^--- ^.' '....................-. _..... i. -i, c /' ... 7~ /^.ti ;)}<\
-AVG. AP
Pump
Vacuum Box
In. Hg Temp.
Gauge °F
": . !
./ /-.
.
AVG. AH
Iir.plr.ger Staclc Stack
Temp Press Tcmo
°F in. Hg °F
i /TO
j . ..
-:- ' . ! ' 1
! - 1
I -- -- 1
...- -- 1 - i
' .--
'
.- .- j . . ..
-' ' 1 i - !
, , j j ,, - ! , -,-
- -. I
-;
-f-'y 0 1
6,0
!
j . .
1
>-. ! ! //o
I
1 ;
MCAP-27 (12/67)
-------
- ^ _ i
in. H?0 .
)rif-:ce. Af,
y
Or-
r
i r\.-
- ufc
'-!.-{- '
l. : i. L |
VuCUU!;!
1 n. Hg
Giuge
"n
;D'i^cK;r
TG~?. ! Tasp
0-7
6--0
:i /-, -77
n-o.s^
Vi
-------
PARTICULAR _LD DATA
PLANT
Run N:0. SB / ' VERY IMPORTANT - FTL IN ALL BLANKS
Location (X.. ,'',"?>.. . JV, /?. X7
Date c^t >t^ K)7/
Operator ->:r- , ' r, <
Sample Box No. .<-- 0
S-'s'ccr Box No. ' JE&
METER AH /, -? V
C FACTOR
1
DRY GAS Pi tOt .
Clock METER. CF in. H20
Point lima r/7A ^ AP
': '. .' (: ". '-, r, !.-,
i i - ' -':, /") ' <
Read and rscord at the start of
each test point.
PATHOLOGICAL- INCINHR'ATORS-
read and record every 5 minutes.
Orifice AH
in H,0
Desired
/.:-:.
L '' "
Actual
: - "
;. v--'
i - , . .[-
; . j ......
^ . ; . I . , .- - 1 ...
Y i '..[-".< 1 '"
i '.'.... 1 -1 - , ' "
i ' -...] -- - (> - j - : ' '
,.."...! ' i .--
! i ..:..., - -. , .
i i i
Dry Gas Temp.
o
r
Inlet Outlet
""> !,- "
v;7-/. .-'..-2
^? .'
< ,-. -'_- -; ,..-,.
- > -
- - . -
.'. -~.-r-
- .- -
j . ;'K- ---, .- .. ,- .,' . - - - .-
1- - i '.I--- -'? -- .1 i " "7 i r? >.-!
i . :- --
^. .,-
. -: v
:~ ' '. '"
zi - -i i
Ambient Te
Bar. Press
- Assumed We
Heater Box
Probe Tip
Probe Ler.g
Probe Heat
AVG. AP
Pump
Vacuum
In. Hg
Gauge
u
Box
Temp .
Op
- _.
. / -.
:mp °F Ast ° '
. "Hg
risture % J^ "^
Ic^/-/.--^,.- op ~« - -
oe vi. i iiy » r
Dia., In. ^/./
th c; '
.er Setting . "
«?,«' . AVG. AH ,
I~,pir.ger Stack Stack
Tc-Tsp Press Tcrr.o
°F in. Hg °F
.-:-. t /^
i -',-0
1 / . 1
.- i . .- -
; -'
.-' -r
r. .'
,''"' O -- "X -7 j . '. ,'-'
.. , ...
-.' . 1 "
- '. ' -
, -. --. _., ^.
- .'
'I ' / -f
, ..'. J -, -:. (. ...
-~',; , '/.'.,,,-! --' - - ! ' .'.--' ?. /.- i j <" /./ 1 -v-v i .--.-..:
! ::-.«. o/, :.i -. -- . -. -// i -> ..: " \ ?. .0 o
-. \ - K-, '.! O./ 7 - S3 i ' -0
/.'... -.,..: 1 C, :'_, ^;o 1 &.-/'?
i i
?.- , ?- 0
2 , 1C
:..-* >
'' . 2. »
? . / O
/-/ t -/->
/' ' -
/ / .... / n
I
.' --
S , o
t".
1
' 1 '
! 1 - ,
1 i / -
./. ! i
.--.--. ! 1 / - -
i
i i -.^
I i '----I
1 i "
! ! .'-:> !
' i" '-. ;' o
\ !
KCAP-37 (12/67)
-------
!
1
;Cc:::~e:-tc
"<>--'
S
\
j Clcc::
I Ti:-:2
- ... . - -.....
!.//,.«;,..'..
'i '. - .; ... .'.-
-' tt
/* f .. IV.
-£^/^I...'M
'
.
;
| Dry Gas
; Mot:;;-, CF
i /"*..;
.-,./- 0, --VO
i £?<-.-:. /£-
'-'. ' .- . -> .^
, ', - z>.~ ?
A '9/0. '. ~>
-7 n -y . ? <-/-
?.3I. t-'V !
!
i
1
i
1
i
i
.
I
1
1
I
i
i
' !
!
I
!
I
~ Pi tot
in. HoO
Ap
^. ,-,r
O . <-, >/
j Orifice
I i:"! i>
De-sired
!
1 -7 = .--
' x-, -3^
.^?. ,"? O
^ . o .0
3. . ~ ^
'
A:-
>o
] Actual
i -../o
^ /y^
?.5.<
(
'"^ "^ i^
|
?.J9
.
" Dry Gcs
or
1"
T " " ,-. >
i ii ; U <.
i
1
i /o '.
/'/ O
; /.c
/ -1 -r
' rf/
~^-~
.
.
'
V
J-
1 tn-.p .
Outlet
& w
P-;
..»"
Vacuuw
In. Hg
iGiuse
5-.0
^. .<
! .-.-. ,->
.<.^
"
i
.
'
2c;<
Tj-.-r.'-v
* \~.'.*~j »
°F
.
Iir.p'ir.ccr b.-c:: i ^_.cu:'.
Tar.:0 SProsi i T--1
O^~ Jj^ '.'*' ^*TT
i »
' '
,- " .'"* 1 ; ' -^
C'1 ' i /7./3
^,.0 1 ! //<*
.<<- 1 //-r'
t-r> \ ' //.<"
: ;
i !
j
i
i
t
i
i i
! 1
j :
; i
i *
!
i
i j
; 1
1
!
i
i
i '
i i
i i
1 i
J j
!
! !
! !
i
i i
i
! !
! i
: i
i
i
! i
i
! !
-------
PARTICULATM CLEANUP SHEET
oa to dVJL 2- 6 , / 1 7 /
3 - - /
j
,un Number £>ty
L
Operator: /}?(££-
\
Sample box number : -S/?-
Plant: JJ ^^,- 7W, ««^V^.- W
Location of sample port:
Barometric pressure:
Ambient temperature:
:1 """ ' ' ' , "
Impinger H20
1
jVolume after sampling
TVolume collected
j T .
tf "*
^ *>*/> / S&Q *j>» t-t- /*'/ (2
«?*.- /OO'V"* *Ti.^ /* *i.
ml -3 £^,v,|Ttr Impinger pr<
mi i^^^ir^'
V ^e^.A. rti£
=>fATea-with . ml
; oo o-4
^Impingers and back half of
i filter, acetone wash:
'Container No
Extra No.
Probe, cyclone, flask, and
front half of filter,
acetone wash,;
Container No,
Extra No-
Filter number
*
Filter Papers and Dry Filter particulate
Container number Filter number.
Container number
Silica Gel
Weight after test:
Weight before test:
Moisture weight collected:
Container number: 1
y7
2.
3.
4.
^50 -7'^
^J^7__
. -2-»-£.
io f~~j
-3
Moisture
total J?7..t> ?
Sample number:
Analyze for
Method determination:
Comments:
8 -
-------
PARTICULATE CLEANUP SHEET
a te
Plant; j/xW :>'... T->
.un Number 5 A _ //?; d_/ 2- .£"£-
operator :
.:?-<:,
Sample box number:
/SAC-ZgP
Location of sample port;
Barometric pressure:
Ambient temperature
1
i
Impinger H^O
j/olume after
Volume collec
1
0, .i:'f.f '.J.iJZrn^.
fl6l ,'oo>.(. .'-,0 . J ...
sampling ml $ f,.^ -Impinger "pr
7 .00 W .''/-'^ / /rC£^
:ted ml ^. /o° /-'_.% ov
1 < »- '
flJSj\j^
2"f Tiled with ml
'lOZ.t^
>.<. ,
£-1 it-
"Impingers and back half of
j filter, acetone wash:
Container No
Extra No.
Probe, cyclone, f^ask, and
front half of filter,
acetone wash:
Container No,
Extra .No.
Filter Papers and Dry Filter Particulate
Filter number Container number Filter number Container number
Silica Gel
Weight after test:
Weight before test:
Moisture weight collected:
Container number: 1. &£)
i/
A 9
2-3. 0
3.
4.
4,
Moisture
total
13 .6
Sample number ; EJ B
Analyze for
'Icthod determination:
Comments :
.
J
-------
PARTICULATE CLEANUP SHEIIT
Plant:
Number
/2-fl C /
Operator; j'/:GLt JC~
?ample box number ;
/
Location of sample port:
Barometric pressure:_
Ambient temperature:
i
i
Impinge r H?0
i
jVolume after
Volume collec
-i
^Impingers and
2Wiv' C>»-.A' /^AkvX/.c!
sampling ml ^ £''* Impinger
V /o/ -*JL H n% f h t. L.
ted ml A: * v<; ^50" "
^ t;:/:'.\, <^.
S c J ' '
back half of Containe
67 ^<
pre^illed
.70 WL
w 8C^
r No.
-t
with ml
"^ fJ/'?S"i<:t~i , ,-
./Uy^/|_. U^/C.^- M'T) Ll
^
Extra No.
Probe, cyclone, flask, and
front half of filter,
acetone wash:
Container No,
Extra No.
Filter Papers and Dry Filter Particulate
Filter number , Container number Filter number
JL ' .
Container number
Silica Gel s£c£t.«v~ ^ 2~ ^3^,
Weight after test:
Weight before test:
Moisture weight collected:
Container number: 1 .1*
2.^.7 900 ** ^^
_lii^ C 7 O ^^4, Atti^ *l«-t.^
/?£»«, ' "3o^£. £,
tfl-i.'&<.& Z-1/,?^,.,^ Moisture ^0,0
#2- ' 2. ^fc " 3. 4. total ^c..4? gr
-z==r'-
Sample number:
Analyze for:
'lothod determination:
C omm c n t
s :
Q
.
-------
PART1CULATE CLEANUP SHEET
7:)ate £y~ G
pperator: hjtr-J 3"C
^
s
Sample box number : SyEf
Location of sample port:
Barometric pressure:
Ambient temperature:
i ! j
Impinger HpO
I
..Volume after sampling ml
Volume collected ml '
1
Impingers and back half of
filter, acetone wash:
Probe, cyclone, flask, and
: front half of filter,
acetone wash-
/
2_ /^O *»J? //'<,o (p-S ) QQ '/)L-''
Impinger prefi i^Ved-Vwith ml
«-A G-fv.-ly\ "^
'/ A£d*_ C~*J
^ T£. / Container No.
l'D' Extra No.
.Container No.
Extra No.
Filter Papers and Dry Filter Particulate
i
Tilter number Container number Filter number
Container number
Silica Gel
Weight after test:
Weight before test:
Moisture weight collected: 37.7 t+~-j)
Container number: 1. #y 2.
3.
4.
Moisture
total J7.7
Sample number :
Method determination:
Analyze for
Comments :
Q> y>3^
-------
APPENDIX D
. ENVIRONMENTAL PROTECTION AGENCY
- .... Office of Air Programs
Research Triangle Park, North Carolina 27711
Reply to
Attnof: ' . . Date: -70CT 1971
Subject: Beryllium Testing Methods Development
x
TO: Acting Director, Division of Compliance
1. A test plan has been developed by the Chief of Stationary Source
Emission Methods and Measurement Section (DCP), who will fund the test.
An exact description of the test follows:
a. EPA gas pumping and measuring equipment will be used.
b. The collection trains are listed-in Table 1.
c. The probe ind glassware will be washed with liquid, the
same as in the first impinger of the collection train used.
In the case of water in the first impinger, an additional rinse
of acetone will be used; and an acid rinse will be used after
the acetone rinse.
d. Each impinger will be individually "bottled".
Each wash will be individually "bottled".
Each filter will be individually "packaged".
This will allow for Beryllium analysis of individual components
of the collection system.-
1 e. The probes will be placed in the exit horizontal stack 8 diameters
downstream and 2 diameters upstream from any obstruction as follows
in Figure 1.
HORIZONTAL LINE
TRAIN "B" -« /" \ *>J "K /' J- P* TRAIN "A1
PROBE TIPS
Cross Section of Stack
Figure 1
Isokinetic gas sampling rates will be used. Single point
sampling will be used. Mi Hi pore AA "filters with Whatman
41 backup will be used.
4-2
-------
Page 2 - Acting Director, Division of Compliance
2. Some input for consideration in establishing the test plan was
furnished by the Source Sampling Fuels Analytical Branch (DAS) via
Darryl J. VonLehmden and Robert E. Lee, and the Emission Testing Branch
(DAT) via Thomas E. Ward and Roger T. Shigehara.
3. The objective of the test is: '
a. To establish an acceptable method for the collection of the
Beryllium sample from a machine shop source.
b. To validate (or invalidate) previous test data, specifically,
The American Beryllium Company, and Speedring, Inc.
4. The execution of this test is tentatively scheduled for October 25
through 29. An alternate date could be November 1 through 5. The place
is Cullman, Alabama, Speedring, Inc.,North Stack. There is room at the
test site to accommodate up to ten people comfortably.
5. This memo is to inform all involved groups of the test plan and schedule.
This memo is also to request input/concurrence in writing of the test plan
and schedule as they may apply to the involved group(s).
Robert E. Meligan
Acting Director
Division of Applied Technology
cc: Mr. D. VonLehmden, SSFAB,DAS
Dr. R. E. Lee, SSFAB,DAS
Mr. J. Nader, SSEMMS.DCP
Mr. ,0. Burkle, SSEMMS.DCP
Mr. D. Patrick, NESDS.DOC
Mr. J. Peoples, NESDS,DOC
Mr. J. De Santis, NESDS.DOC
Mr. J. McGinnity, ETB,DAT
Mr. W. Basbagill, ETB,DAT
Mr. R. Shigehara, ETB,DAT,CIS
Attachment
4-3
------- |