EMISSION TESTING REPORT
EPA REPORT NO. 74-KPM-15

  ST.  REGIS PAPER CO.
  TACOMA, WASHINGTON
      PEDCo ENVIRONMENTAL

-------
                            PEDCo- ENVIRONMENTAL
                                 SUITE 8  •  ATKINSON SQUARE
                                      CINCINNATI. OHIO 45346
                                                513 I ~7~7 1-433O
                EMISSION TESTING REPORT

                EPA REPORT NO. 74-KPM-15

                  ST. REGIS PAPER CO.
                  TACOMA, WASHINGTON
                Contract No. 68-02-0237
                        Task 27
                      Prepared by:

                      R.S. Amick
                      W.G. DeWees
                      R.W. Gerstle, P.E,
Submitted by:  PEDCo-Environmental Specialists, Inc.
               Suite 13, Atkinson Square
               Cincinnati, Ohio  45246

-------
                  I.  TABLE OF CONTENTS
                                                        Page

 II.  INTRODUCTION                                         1

III.  SUMMARY OF RESULTS                     .              4

 IV.  PROCESS. DESCRIPTION AND OPERATION                    8

  V.  LOCATION OF SAMPLING POINTS                       . 18

 VI.  SAMPLING AND ANALYTICLA PROCEDURES                 22

VII.  APPENDIX

      A.  PARTICULATE RESULTS, CALCULATIONS AND
          EXAMPLE CALCULATIONS

      B.  PROCESS DATA

      a.  FIELD DATA

      D.  LABORATORY REPORT

      E.  SAMPLING METHODS

      F.  TEST LOG

      G.  PROJECT PARTICIPANTS AND TITLES

-------
II.  INTRODUCTION



     Under the Clean Air Act of 1970, as amended, the Environ-




mental Protection Agency is charged with establishing



performance standards for stationary sources which may contribute



significantly to air pollution.  A performance standard is based



on the best emission reduction systems which have been shown to



be technically and economically feasible.



     In order to set realistic performance standards, accurate



data on pollutant emissions must be gathered from the stationary



source category under consideration.



     St.  -Regis Paper Co. in Tacoma, Washington was designated



as a well-controlled stationary source in the kraft pulp mill



industry and was thereby selected by GAP for an emission testing



program.   The tests were conducted during the period of February 12



to February 19, 1974.



     The specific processes under investigation in this test series



were the No. 2 lime kiln and the No. 4 recovery furnace.  Emissions



from the lime kiln were controlled by a venturi scrubber followed



by a cyclone separator demister.  Emissions from the recovery



furnace were controlled by an electrostatic precipitator (ESP).  A




schematic diagram of the simplified Kraft process and the operations



sampled is shown in Figure 2.1.



     Five particulate tests were conducted in the exit stack of



the recovery furnace to determine filterable and total particulate

-------
    RECOVERY
    FURNACE
   SMELT
           BLACK
           LIQUOR
GAS FLOW
LIQUOR FLOW
                      AIR  PRE-
                      HEATERS
                                                    RECOVERY
                                                    FURNACE
                                                    TEST SITE
              ELECTROSTATIC
              PRECIPITATOR
                                     STACK
FUEL
                            VENTURI
                            SCRUBBER
                                                     LIME  KILN
                                                     TEST  SITE
                 CYCLONIC
                 SEPARATOR
                 DEMISTER
                                     STACK
        Figure  2.1.  Schematic diagram of simplified Kraft process

                         and processes sampled.

-------
emissions.  Simultaneous determination of moisture content and

dry molecular weight of the flue gases were also made.  It was

originally intended that six runs be made; however, the sixth

test was cancelled due to a malfunction in the No. 4 recovery

furnace ESP.  The duration of the recovery furnace tests varied

from 224 minutes to 336 minutes and averaged 315 minutes.  These

relatively lengthy tests were necessary because the No. 4

recovery furnace ESP provided such a high particulate control

efficiency that the exit gas stream was extremely clean, ancj

a longer sampling period was required than normal in order to

obtain a measurable particulate sample.

     Six particulate tests were conducted on the exit stack of

the lime kiln to determine filterable and total particulate

emissions.  Simultaneous determination of moisture content and

dry molecular weight of the kiln flue gases were made.

     During the period of testing the No. 4 Recovery Furnace,

the crew of another contractor,  (Valentine, Fisher, and Tomlinson)

were conducting parallel, simultaneous particulate emission tests

of the recovery furnace with both an in-stack filter sampling
              \
train and an out-of-stack heated filter sampling train.  Their

tests were designed to permit a comparison of the two sampling

train methods.   Results of this test are available in a separate

EPA Report 74-KPM-14.

-------
III.  SUMMARY OF RESULTS



     Recovery Furnace



     A summary of particulate emission and flue gas data for



the five (5) particulate tests on the No. 4 Recovery Boiler



exhaust is presented in Table 3.1.  The data is fairly consistent



when all the tests are considered simultaneously.  Although



the particulate emission concentration varied from 0.00445



gr/DSCF (grains per dry standard cubic foot) (Test 1-3) to



0.01139 gr/DSCF (Test 1-5), this variation is not unexpected,



when ESP efficiencies of 99+ percent and the many possible



process variations are considered.  The average particulate




emission results for the five tests were 11.22 Ib/hr and 0.0087



gr/DSCF.



     Several problems were encountered during the recovery



furnace testing, resulting in the abortion of three tests;



however, none of the five tests shown in the summary tables were



effected.  Twice during testing, the No. 4 Recovery Boiler ESP




malfunctioned, which necessitated a restart of the test since



the resulting uncontrolled recovery furnace emissions overloaded



the sampling trains before they could be shut off.  The other



aborted test resulted from a break in the six foot glass probe



which was discovered during a leak test while changing ports.



Since it was not known when the break had occurred, a new test



was started.

-------
                           Table  3.1  SUMMARY OF PARTICULATE EMISSION RESULTS
                                             NO. 4 RECOVERY FURNACE
Run Number
Date
Volume of Gas Sampled - DSCFa
- (Nm3)b
Average Stack Temperature - °F
- °C
Percent Moisture by Volume - %
Stack Volumetric Flow Rate - DSCFMC
- (Nm3/sec)d
Stack Volumetric Flow Rate - ACFM6
- m3/sec
Percent Isokinetic
Particulates - probe, and
filter catch
mg
gr/DSCFf
(mg/Nm3)9
gr/ACF
mg/irr
Ib/hr
Kg/hr
Particulates - total
mg
gr/DSCF
mg/Nm
gr/ACr
mg/m
Ib/hr
Kg/hr
1-1
2-12-74
176.861
5.01
338
170
21.5
141928
67.0
274310
139
111.0
30.4
0.00265
6.06
0.00137
3.19
3.226
1.46
92.4
0.00806
18.4
0.00417
9.71
9.808
4.45
1-2
2-13-74
182.949
5.18
349
177
22.8
148427
70.1
292782
149
109.8
37.3
0.00314
7.18
0.00159
3.70
4.002
1.82
127.8
0.01078
24.7
0.00545
12.7
13.715
6.23
1-3
2-14-74
388.718
11.0
361
182
23.1
159325
75.2
312178
158
108.7
61.2
0.00242
5.54
0.00126
2.93
3.358
•1.52
112.1
0.00445
10.2
0.00231
5.38
6.152
2.79
1-4
2-15-74
273.535
7.76
347
175
22.1
160461
75.7
299248
152
101.2
39.0
0.0022
5.03
0.00117
2.72
3.026
1.37
154.3
0.00870
19.9
0.00466
10.9
11.973
5.44
1-5
2-18-74
244.558
6.93
345
174
22.9
143142
69.9
294630
150
98.6
43.2
0.00273
6.25
0.00137
3.19
3.461
1.57
180.6
0.01139
26.1
0.00573
13.3
14.471
6.57
a Dry standard cubic feet at 70°F, 29.92 in.  Hg.

  Normal cubic meters at 21.1°C, and 760 mm Hg. - dry basis

c Dry standard cubic feet per minute at 70°F, 29.92 in.  Hg.

d Normal cubic meters per second at 21.1°C, and 760 mm Hg.  - dry basis

e Actual cubic feet per minute.

  Grains per dry standard cubic foot.

9 Milligrams per dry normal cubic meter.

-------
     Lime Kiln




     A summary of particulate emission data from the six tests



on the No. 2 Lime, Kiln is presented in Table 3.2.  The emission



results of the first three  (3) particulate tests on the lime



kiln (Tests 2-1 through 2-3) were very similar, with an average



grain loading of 0.1113 gr/DSCF and average emission rate of



13.41 Ib/hr.  The final three (3) test results were neither



similar when compared with one another or with the first three



tests.   This probably occured because the fuel used to fire the



rotary lime kiln was changed from oil to natural gas about mid-



way through Test 2-4.  The grain loading for Test 2-4  (0.0856



gr/DSCF) was about midway between the average grain loading for



the first three tests (0.1113 gr/DSCF) and that of Test 2-5



(0.05961 gr/DSCF), which supports the possibility that the fuel



switch to gas caused a decrease in particulate emissions.  This.



rationale also is consistent with the fact that particulate



emissions from oil combustion are generally higher than those from



natural gas combustion.   Test 2-6 yielded a grain loading of only



0.03699 gr/DSCF, but the volumetric flow rate  (11,560 DSCFM) for



this test was well below the average flow rate for the other



five tests (13,467 DSCFM), which could account for this difference.



The production rate was somewhat lower during this run.  (See



Chapter IV).



     The average grain loading for the six kiln tests was



0.08604 gr/DSCF, while the emission rate averaged 11.2 Ib/hr.



There were no problems encountered with the actual testing which



should influence the results.

-------
                           Table 3.2  SUMMARY OF PARTICULATE EMISSION RESULTS
                                                  NO. 2 LIME KILN
Run Number


Date

Volume of Gas Sampled - DSCFa


                      - Nm3 b'


Average Stack Temperature - °F

                          - °C


Percent Moisture by Volume - %


Stack Volumetric Flow Rate - DSCFMC

                           - Nm3/sec d   6.97


Stack Volumetric Flow Rate - ACFM6

                           - m /sec


Percent Isokinetic



Particulates - probe, bypass, and
               filter catch


mg


gr/DSCFf


mg/Nm3 ^

gr/ACF

mg/m3


Ib/hr

kg/hr



Particulates - total


mg


gr/DSCF

mg/Nm3

gr/ACF


mg/m


Ib/hr


kg/hr
2-1
2-12-74
59.589
1.68
151
66
25.2
14755
6.97
22844
11.6
101.0
416.8
0.10794
247
0.06962
162
13.651
6.18
435.3
0.11273
258
0.07271
.69
14.257
6.45
2-2
2-13-74
57.781
1.64
151
66
24.3
14292
6.75
21714
11.0
101.0
363.7
0.09713
222
0.06395
149
11.899
5.39
392.5
0.10483
240
0.06902
161
12.842
5.81
2-3
2-14-74
54.503-
1.54
151
66
25.5
13165
6.21
20357
10.3
103.5
361.5
0.10235
234
0.06632
154
11.550
5.23
411.4
0.11648
266
0.07548
176
13.144
5.94
2-4
2-14-74
56.300
1.59
154
68
30.6
12832
6.06
21337
10.8
109.7
312.3
0.08560
196
0.05152
.120
9.415
4.26
332.9
0.08560
196
0.05492
128
ao.ose
4.54
2-5
2-14-74
58.532
1.66
156
69
27.0
13896
6.56
22016
11.2
105.3
226.3.
0.05961
136
0.03762
87.6
7.100
3.21
336.5
O.C5961
136
0.05599
130
10.567
4.78
2-6
2-14-74
48.010
1.36
152
67
24.5
11560
5.46
17643
8.96
103.5
115.J
0.03C99
3-1. G
0.02-132
56.6
3.678
1.66
198.9
0.03099
B4.G
0.04203
98
6.356
2.88
 a Dry standard cubic feet at 70°F,  29.92  in.  Hg.


 b Normal cubic meters at 21.1°C,  and 760  mm Hg.  -  dry  basis


 c Dry standard cubic feet per minute st 70°F,  29.92  in.  Hg.


   Normal cubic meters per second  at 21.1°C, and  760  mm Hg. -  dry  basis

 g
   Actual cubic feet per minute.


   Grains per dry standard cubic foot.


 " Milligrams per dry normal cubic meter.

-------
IV.  PROCESS DESCRIPTION AND OPERATION




     The St. Regis Paper Company mill at Tacoma, Washington pro-



duces 1000 tons of kraft pulp per day.  About 15 percent of the



pulp is bleached and made into paper.  The remaining pulp is made



into a variety of brown paper and paperboard products.  The plant



has been operating since 1928.                            •



     Process Description



     A.  General              .                    ,



     The process for making kraft pulp from wood is shown in



Figure 4.1.  In the^process, wood is chipped into small pieces



and then cooked in digesters  (five batch and two continuous) at



elevated pressure and temperature.  The cooking chemicals, called



white liquor, are sodium hydroxide and sodium sulfide in water



solution.  The white liquor chemically dissolves lignin, leaving



wood cellulose (pulp) which is filtered from the spent liquor and



washed.  The pulp is made into paper.



     The balance of the pulping process is designed to recover the



cooking chemicals.  Spent cooking liquor and the pulp wash water



are combined for treatment to recover chemicals.  The combined



stream, called weak black liquor, is concentrated, in steam heated



multiple-effect evaporators, including a special effect called a



concentrator.  The strong black liquor leaving the evaporators



is burned in a recovery furnace.



     Combustion of the organic matter in the black liquor provides



heat needed to generate process steam.  Inorganic chemicals from



the black liquor are recovered as a molten smelt at the bottom



of the furnace.  The smelt, consisting of sodium carbonate and sodium



sulfide, is dissolved in water and transferred to a causticizing





                              8

-------
      WOOD
  (NaOH +
IQLJOR
Na2S)
DIGESTER
SYSTEM



— U F fl k1
PULP
WASHERS
RI A r ic i T niir
                                                      "PULP

                                                      •WATER
                     RECOVERY
                      FURNACE
                      SYSTEM
      STACK
                              n
                              AIR
                              HEAVY
                              BLACK •
                             LIQUOR
                        MULTIPLE
                          EFFECT
                       EVAPORATOR
                          SYSTEM
o

UJ
C£.
                     \
                   SMELT
              (Na2C03 + Na2S)
          WATER-
                  SMELT
                DISSOLVING
                   TANK
                  GREEN LIQUOR
  L
I WHITE LIQUOR
(RECYCLE TO
 DIGESTER)
CAUSTICIZING
    TANK
                                      LIME
                                         CALCIUM.
                                        •CARBONATE
                                           MUD
Figure 4.1.  The Kraft pulping process at the St. Regis mill
                   in Tacoma, Washington.

-------
tank.  Lime added to this tank converts sodium carbonate to sodium



hydroxide, completing the regeneration of white liquor, which is




then recycled to the digester.  The calcium carbonate mud that  .



precipitates from the causticizing tank, is recycled to a kiln



to regenerate lime.



     B.  Recovery Furnace



     The Number 9 recovery furnace was designed by Combustion



Engineering to burn 108,000 pounds of black liquor solids per hour,



which corresponds to a pulp production rate of about 863 tons per



day.  Auxiliary fuel oil is also burned.



     The furnace is not equipped with direct contact evaporators.



Special steam heated evaporators, called concentrators, are used



instead.  With this design, gases leaving the furnace are not



used to concentrate the incoming black liquor.  Instead, the gases



preheat the combustion air in two parallel heat exchangers called



laminaire heaters, as shown in Figure 4.2.



     Steam is generated in the recovery furnace to provide some



of the process heat requirements.  A portion of the steam is used



within the furnace to blow soot from the boiler tubes.  The soot



blowers operate one at a time, with each complete sequence taking



about 2 1/2 hours.  A new cycle begins as soon as the previous



cycle ends, so that the soot blowers operate continually.



     C.  Electrostatic Precipitator



     The exhaust gases from the Number 9 recovery furnace are



cleaned in an electrostatic precipitator.  The precipitator was



installed in 1973 by Wheelabrator-Lurgi.  The unit was designed
                              10

-------
       RECOVERY
       FURNACE
                       FURNACE
                     COMBUSTION
                        GASES
                                                           SAMPLING  PORTS
                                                    ELECTROSTATIC
                                                     PRECIPITATOR
                                                                               STACK
Figure 4.2.  Recovery furnace and precipitator at the St.  Regis Mill  in Tacoma,  Washington,

-------
to treat combustion gases at a rate of 400,000 ACFM, at a tempera-



ture of 350-475°F.



     The precipitator has two parallel chambers with four sec-



tions in each chamber.   The middle sections have independent power



supplies; the two inlet sections share one power supply and the



two outlet sections share one power supply.



     The insulator compartment is heated to protect it from



corrosive condensation.  Five fans blow hot air over the in-



sulators, with each fan supplying about 800 CFM.  The total heat-



ing air is only 1 percent of the design capacity of the precipita-



tor, and does not lower the particulate concentration significantly.



     Dust collecting on the precipitator electordes is shaken loose



by a system of rappers.  The rappers operate in continual cycles,



with each cycle lasting 3 1/2 minutes.  The collected dust falls



into dry hoppers and is removed by screw conveyors to a mix tank.



In the tank, the dust is dissolved in black liquor and recycled



to the process.  If the conveyors are stopped by a malfunction,



the precipitator power is automatically shut off to prevent clogging



the conveyors.  This happened twice during the test series.



Each time, the precipitator was off for only a few minutes but the



surge of particulate through the stack forced the cancellation



of both test runs.



     The precipitator is located near ground level and the exhaust



gases discharge through a tall stack.
                              12

-------
     D.  Lime Kiln and Venturi Scrubber



     The Number 2 lime kiln was designed by Traylor Company to



produce 80 tons of lime per day.  This is equivalent to a pulp



production rate of about 320 tons per day.  This rotary kiln is



170 feet long, with an inside diameter of 8 1/2 feet.  It is fired



with either natural gas or No. 6 fuel oil.




     The feed to the kiln is the calcium carbonate slurry that



precipitates from the causticizing tanks.  The slurry is washed



and then dried on a rotary vacuum drum, as shown in Figure 4.3.



The dried cake is removed from the drum on a knife edge and con-



veyed to the kiln.  In the kiln, the calcium carbonate mud is



roasted and carbon dioxide is driven off, leaving calcium oxide



(lime) as product.



     Noncondensable gases from the multiple-effect evaporators



are burned to destroy odors.  These gases are burned in either of



the two kilns operated at the plant.  Dregs from the green liquor



clarifier are not burned in the kilns.



     The combustion gases from the kiln are cleaned in an adjust-



able throat venturi scrubber.  They then pass through a demister



and out a 100 foot stack.  The scrubbing water is recycled from



the demister and blended with fresh water makeup.  A portion of



the recycled water is purged to prevent fexcessive accumulation of



solids, and used elsewhere in the process.



     Process Operation



     A.  General



     The purpose of the tests was to measure emission levels during
                              13

-------
LIMESTONE
   MUD —*
 MUD
WASHER
                         VACUUM
                         FILTER
           SAMPLING  PORTS
                                            EXHAUST
                                              GAS
                                                                   STACK
   AIR
   GAS OR
   NO. 6 OIL
FRESH
WATER'
             LIME
           (PRODUCT)
                                                 VENTURI
                                                                          \
                             DEMISTER
                 •RECYCLE-
                                                           -»-BLEED
  Figure  4.3.   Flow  diagram  of  the No.  2  lime  kiln  at  the  St.  Regis mill

                               in Tacoma, Washington.

-------
normal plant operation.  Process conditions were carefully observed,



and testing was done only when the test facility appeared to be



operating normally.



     The laminaire heaters on the furnace are cleaned daily.



During cleaning, the flow rate of black liquor to the furnace is



reduced.  By arrangement with the plant, the heaters were cleaned



after the test periods, so that during the test the full charge



of black liquor would go to the furnace.



     As previously mentioned the precipitator lost power twice



because of malfunctions to the screw conveyors under the hoppers.



Power was lost at 1130 hours on February 13, and at 1247 hours on



February 19.  Particulate sampling was stopped on both occasions



and the test runs were aborted.



     The plant has installed a Lear-Siegler transmissometer to



monitor the stack gas opacity.  The chart record of this instrument



was very steady throughout the tests, indicating an opacity of



4.5 to 6 percent.  The opacity readings were observed to increase



slightly when the black liquor charging rate increased by about



40 gpm.  During both precipitator malfunctions mentioned above,



the opacity readings went off scale.  The readings are recorded



on the process data sheets in Appendix B.



     During the tests, important process conditions were monitored



and recorded on data sheets.  Readings were taken about once every



half-hour.  These data, and a key to the entries, are in Appen-



dix B.  The readings made on the precipitator include voltage



and amperage of the primary and secondary circuits of all six
                             15

-------
  control fields.  Charging rate and other significant operating



  variables were also recorded.  Furnace temperatures cound not



  be recorded because the monitors were not operational.



       Based on available precess data and conversations  with the



  operators, the furnace and precipitator operated normally during



  the tests, with the exception of the two precipitator power-outages,



  The black liquor charging rate was in its normal range  of 190 to



  240 gpm.  Soot blowers operatied continually during the testing,



  as normal.



       The gas flow rate through the precipitator during  the tests



  is compared to the design flow rate in Table 4.1 below.  As shown,



  the flow rate during the tests averaged 74 percent of the design



  rate.





       Table 4.1.  Gas Flow Rates Through the Precipitator
                              Gas Flow Rate, ACFM
Run Number
Date, 1974    During Test
Design
% of Design
1-1
1-2
1-3
1-4
1-5

Feb.
Feb.
Feb.
Feb.
Feb.

12
13
14
15
18

274
292
312
299
294

,310
,782
,178
,248
,630

400
400
400
400
400

,000
,000
,000
,000
,000

69
73
78
75
74
7 4 Avg .
       C.  Lime Kiln



       During the tests,  important process conditions were monitored



  and recorded on data sheets.   Readings were taken about every half-
                               16

-------
  hour.   These records and  a  key to the entries are  in Appendix B.

  As  far as known from the  process information and conversations

  with the operators, the kiln and scrubber operated normally during

  the tests.  The main process information is summarized in

  Table  4.2 below.

      As shown, the particulate emissions ranged from 0.04 to

  0.11 gr/dscf.  The three  highest emissions occurred while the kiln

  was fired with oil; the two lowest emissions occurred while the kiln

  was fired with natural gas;  an intermediate emission level occurred

  when the kiln was fired with oil for half the sampling period, and

  then switched to gas.  It should also be noticed that the kiln

  charging rate was lower during gas firing  (50 compared to 60 gpm

  of  mud).  The combination of gas firing and lower  charging rate

  apparently reduced particulate emissions about 50  percent.
               Table 4.2.   Summary of Lime Kiln Process Data
                            During Particulate Sampling


                       Mud.     Venturi   Fuel     Fuel
                      Charging  Pressure  Gas     Oil      Particulate
       Date   Sampling   Rate,     Drop,   Rate,    Rate,      Emissions,
Test    1974     Hours      gpm     in H20   mscfh    Ib/hr    gr/dscf (total)
2-1
2-2
2-3
' 2-4
2-5
2-6
Feb. 12
Feb. 13
Feb. 13
Feb. 14
Feb. 14
Feb. 14
1225-1555
1000-1225
1400-1628
0908-1213
1235-1538
1605-1834
60-61
60
60
0-60a
50-60
50
31-32.5
32-32.5
32-32.5
30-32
29.9-31
24.5-28
0 1650-1760
0 1660-1780
0 1680-1710
25-27b 0-1790b
22-26 0
22 0
0
0
0
0
0
0
.11
.10
.12
.09
.06
.04
a Feed was off briefly while the kiln was switched from oil to gas firing.
k Kiln was switched from oil to gas at 1025 hours.
                                17

-------
V.  LOCATION OF SAMPLING POINTS



     Recovery Furnace



     Figure 5..1 illustrates the locations of the sampling ports



and points for Recovery Boiler No. 4.  The sampling site was



located at a point approximately 70 ft.  (5.0 stack diameters)



from the top of the stack and 74 ft.  (6.7 diameters) from the



outlet of the ESP  (also the closest upstream disturbance).  The



diameter of the stack at the sampling site is 14.0 ft.  Twenty,



eight (28) traverse points  (14 along each of two perpendicular



diameters) were selected as prescribed by the Method 1 of the



Federal Register.



     The sampling platform was especially constructed for



testing and consisted of a metal grating floor surrounding the



stack and enclosed on the top and sides by corrugated plastic.



Access to the sampling points was accomplished through four  (4)



ports (at 90° separation), since the 14.0 ft. diameter stack



was too wide to traverse along one diameter through a single



port.



     Lime Kiln



     Locations of the sampling ports and points for Lime Kiln



No. 2 are shown in Figure 5.2.  The sampling site was located



at a point approximately 30 ft. (7.5 stack diameters) from the



top of the stack and 10 ft. (2.5 stack diameters) from the



demister exit (also the nearest upstream restriction).  The



diameter of the stack at the sampling site is 4.0 ft.  Forty
1) Federal Register, Vol. 36, No. 247, December 23, 1971.
                             18

-------
  SAMPLE POINT LOCATION FROM INNER STACK WALL
               (inches)
N-l   3.0
           E-l   3.0
                      S-l   3.0
                                 W-l   3.0
     9.5
    16.75
    24.5
    33.75
    47.5
    61.5
 9.5
16.75
24.5
33.75
47.5
61.5
 9.5
16.75
24.5
3.75
47.5
61.5
        14  ft ID
        28  SAMPLING  POINTS
            3  5  7°  6  4  2
          ooooooo  ooooooo
           246°753
 9.5
16.75
24.5
33.75
47.5
61.5
                                           70 *
                                           74
RECOVERY
FURNACE


ESP
   Figure 5.1  Sample port  and  point locations on  Recovery
                 Furnace  No.  4.
                                     19

-------
      SAMPLE POINT LOCATION FROM INNER STACK WALL
                   (inches)
   S-l
    2
    3
    4
    5
    6
    7
    8
    9
   10
 1.0
 2.0
 3.25
 4.5
 6.5
 8.0
 9.75
12.0
14.25
18.25
S-ll
  12
  13
  14
  15
  16
  17
  18
  19
  20
29.5
33.5
36.0
38.25
40.0
41.5
43.5
44.75
46.0
47.0
W-l
  2
  3
  4
  5
  6
  7
  8
  9
 10
 1.0
 2.0
 3.25
 4.5
 6.5
 8.0
 9.75
12.0
14.25
18.25
           4  ft  ID
           40 SAMPLING  POINTS
          LIME
          KILN
B-ll
  12
  13
  14
  15
  16
  17
  18
  19
  20
29.5
33.5
36.0
38.25
40.0
41.5
43.5
44.75
46.0
47.0
                  VENTURI
                  SCRUBBER
                                                   30*'
                                                    10'
                                                    /
                                                           2-3"
                                                           Ports
                                                             6
                                                  DEMISTER
Figure 5.2  Sample port  and  point  locations on Lime  Kiln No. 2,
                                    20

-------
 (40) sampling points  (20 along each of two perpendicular diam-



eters) were selected, as prescribed by Method 1 of the Federal



Register.




     The sampling platform was especially constructed for



sampling and consisted of a metal grating floor around approxi-



mately 270° of the stack circumference enclosed on the top and



sides.  Access to the sampling points was provided by two ports



at 90° separation..
1)  Federal Register,  Vol.  36,  No.  247,  December 23,  1971,
                             21

-------
VI.  SAMPLING AND ANALYTICAL PROCEDURES



     All sampling procedures were selected by EPA prior to



field sampling.  All analyses of collected samples were



performed by PEDCo.  Appendix E contains detailed descrip-



tions of the sampling and analytical procedures employed for



the tests.  These procedures are described briefly below.



     Velocity and Gas Temperature



     All gas velocities were measured with a calibrated type



S pitot tube and inclined draft gage.  In all cases veloc-



ities were measured at each sampling point across the stack



diameter to determine an average value according to pro-



cedures described in the Federal Register  - Method 2.



Temperatures were measured with long stem dial thermometers.



     Molecular Weight



     An integrated sample of the stack gases was collected



daily throughout the testing periods by pumping the gas into

        •p
a Tedlar  plastic bag at the rate of approximately 0.015



CFM.  This bag sample was then analyzed with an Orsat ana-



lyzer for C0~» Oy, and CO as described in the Federal



Register , Method 3.



     Particulates


                                              2
     Method 5 as described in Federal Register , was used to



measure particulate matter.  A rigid train consisting of a



heated glass lined probe, a 3" glass fiber filter, and a



series of Greenburg-Smith impingers was employed in all



particulate tests.  A water wash of the probe and filter



portion of the train was made in addition to the acetone



rinse.
1) Federal Register, Vol. 36, No. 247, December 23, 1971

2) Federal Register, Vol. 36, No. 159, August 17, 1971




                              22

-------