EMISSION TESTING REPORT
    EPA REPORT 74-LIM-3-A
WOODVILLE LIME AND CHEMICAL CO.
       WOODVILLE, OHIO
           PEDCo ENVIRONMENTAL

-------
                  PEDCo-EN VI RON MENTAL-
                       SUITE is  •  ATKINSON  SQUARE
                             CINCINNATI. OHIO 4524.6
                                       513 I-7-7 1-433O
       EMISSION TESTING REPORT

        EPA REPORT 74-LIM-3-A

   WOODVILLE LIME AND CHEMICAL CO.
           WOODVILLE, OHIO
             Prepared by:

          William G. DeWees
      Richard W. Gerstle, P.E.

PEDCo-Environmental Specialists, Inc,
      Suite 13, Atkinson Square
       Cincinnati, Ohio  45246
       Contract No. 68-02-0237
          Task Order No. 26

-------
                      I.   TABLE OF CONTENTS




                                                       Page




 II.  INTRODUCTION                                       1




III.  SUMMARY OF RESULTS       .                          3




 IV.  PROCESS DESCRIPTION                               9




  V.  LOCATION OF SAMPLING  POINTS                      11




 VI.  PROCESS OPERATION             .                    13




VII.  SAMPLING AND ANALYTICAL PROCEDURES               16




      APPENDICES




      A.  PARTICULATE  RESULTS AND EXAMPLE CALCULATIONS




     .B.  GASEOUS RESULTS AND EXAMPLE CALCULATION




      C.  VISIBLE EMISSION  RESULTS




      D.  OPERATIONAL  RESULTS




      E.  FIELD DATA




      F.  LAB REPORT




      G.  SAMPLING METHODS




      H.  TEST LOG




      I.  RELATED REPORTS




      J.  PROJECT PARTICIPANTS




      K.  SUMMARY OF  TESTING COST

-------
                      II.  INTRODUCTION






     Under the Clean Air Act of 1970, as amended, the Environ-



mental Protection Agency (EPA)  is charged with, the establishment



of performance standards for stationary sources 'which may con-



tribute significantly to air pollution.  A performance standard



is based on the best emission reduction systems which have been



shown to be technically and economically feasible.



     In order to set realistic performance standards, accurate



data.on pollutant emissions must be gathered from the stationary



source category under consideration.



     Woodville Lime and Chemical Company in Woodville, Ohio, was



designated as a well-controlled stationary source in the lime



producing industry and was thereby selected by EPA for an emission



testing program.  The tests were conducted during the period of



May 20 to 21, 1974.  The process under investigation in this test



series was the No. 1 lime kiln at the Woodville plant.  Emissions



from the lime kiln are controlled by a cyclone in series with an



electrostatic precipitator.  During the test period difficulties



encountered with process operation and above-normal production



rates resulted in nontypical emissions; the test program was



therefore rescheduled for a later date  (July 8, 1974).



     Results obtained in preliminary testing on May 20 and in



one complete test on May 21 are presented here.  The complete

-------
test run included measurements of filterable particulates, total



particulate, oxides of nitrogen, and sulfur dioxide in effluent



from the exit .stack of the lime kiln.  In addition, moisture



content and dry molecular weight of the exit gas were determined,



and opacity of visible emissions was recorded by two trained



observers and also with a continuous opacity transmissometer.

-------
                  III.  SUMMARY OF RESULTS






     A summary of data on particulate emissions from the No. 1



lime kiln ESP exit stack is presented in Table 1.   The pre-



liminary test (A), which was conducted on May 20,  1974, covered



only 40 of the 48 traverse points; the second test (No. 1), con-



ducted on May 21, 1974, covered only 44 of the 48  traverse



points.  In addition, the plant was operating at an above-normal



production rate, which caused overloading of the ESP emission



control device.   Therefore, the emissions data presented in



this report are considered to be questionable and  nonrepresentative



of a well-controlled lime producing process.



     The EPA Process Engineer decided to conduct several tests



on the effluent gas stream from the ESP even though the process



rate exceeded normal operational parameters.  This decision was



based on the need for information with which to determine.



correlation of emissions concentrations and visible opacity



observations.  EPA had transported to the plant site a continuous



monitoring transmissometer for opacity measurements; the emission



measurements therefore were performed for purposes of correlation



with readings from this instrument, even though emission rates



were known to be above normal for this plant.



     The filterable particulate, as measured by the probe and



filter catch, averaged 30.35 pounds per hour at a concentration of

-------
              Table 1.  SUMMARY OF PARTICULATE RESULTS

                              LIME KILN
Run Number

Date

Volume of Gas Sampled,-DSCFa

Average Stack Temperature, °F

Percent Moisture by Volume

Stack Volumetric Flow Rate, DSCFM

Stack Volumetric Flow Rate, ACFMC

Percent Isokinetic

Feed Rate , ton/hr

Particulates - probe, bypass, and
               filter catch

mg

gr/DSCF

gr/ACF

Ib/hr

Ib/ton

Particulates - total

mg

gr/DSCF

gr/ACF

Ib/hr

Ib/ton
A
5/20/74
56.155
675
12.17
26994
66504
99.3


5/21/74
121.814
686 681
10.65 11.41
27142 27068
66504 66504
98.2
30.62
277.2    1463.4

  0.0762    0.1854

  0.0310    0.0757

 17.6      43.1

            1.41



635.2    1586.8

  0.1746    0.2010

  0.0710    0.0820

 40.4      46.8

            1.53
 0.131

 0.0533

30.35
 0.188

 0.0765

43.6
  Dry- standard cubic feet at  70°F,  29.92  in Kg.
b Dry standard cubic feet per minute  at 70°F,  29.92  in.  Hg
0 Actual cubic feet per minute.

-------
0.131 grains per DSCF.  Total particulate emissions averaged 43.6



pounds per hour at a concentration of 0.188 grains per DSCF.



Results of the second test yielded higher concentrations of



filterable particulate than were obtained in the first test,



probably because of discontinuities in process operation and



production rates.




     Emissions of oxides of nitrogen and sulfur dioxide were



determined only during the second test.  A summary of oxides



of nitrogen data is presented in Table 2.  These data show



average emissions of 481 ppm by volume and 93.2 pounds per hour.



     The method for sampling of sulfur dioxide was intended to



measure emissions in the 1000 ppm range.  Analysis of the samples



obtained,.however, showed sulfur dioxide concentrations much



lower than those expected, about 20 ppm; sample volume was there-



fore inadequate to yield measurable results.  This low concen-



tration was attributable to the neutralization of the sulfur



dioxide by the alkaline dust produced in the process.



     Determinations of visual opacity of emissions from the lime



kiln stack were performed independently by two PEDCo personnel.



using Federal Register Method 9.  Opacity was also measured by the



Lear Siegler continuous transmissometer*  Data on visible emissions



are summarized in Table 3.  The average opacity was 14 percent



for all readings during the test periods.  A 20 percent opacity



level was exceeded about 8.5 percent of the test time.  This high



visible opacity was another indication of emissions much higher



than those expected.

-------
     Table 2.  SUMMARY OF NITROGEN OXIDES EMISSIONS FROM

                          LIME KILN
Test no.

Date :

Time,  24 hr

Flow rate, DSCFM

Sample volume, ml

Milligrams of NO2

Concentration, ppm

Emissions, Ib/hr
5/21/74

  1249

 27142

  1025.46

     0.979

   500.7

    96.94
5/21/74

  1339

 27142

  1145.04

     1.009

   462.2

    89.48
                                   Average
                                   column
27142
  481.5

   93.21

-------
Run No.  2

Date  V21/74
Table  3.  'Summary  of Visual  Opacity Readings
                                        Lear
                                        Siegler
Interval  of  Observations
                       1
                          Start


                          • -End
Duration  of  Observation (niin)


Total  No.  of Readings


No.  of Readings  Unobservable


No.  of Readings  @ 0% Opacity


                 5%


                10%


                15%


                ' 20%


                '25%


                30%


                35%
                • 50%


Percent Readings  Unobservable


Percent Readings  (? .0% Opacity


                  5%


                 10%


                 1 5%


                • 20%


Percent Readings  Exceed ing 20%
Obs, 1
1158
1441
163
653
-
0
0
189
388
54
21
1
0
0
0
0
-
0
0
28.9
59.4
8.3
3.4
Obs. 2
1158
1458
180
720
-
• ' . 4
118
'201
270
64
22
15
18
6
2
0
-
0.6
16.4
27.9
37.5
8.9
8.8
Obs. 1























2
	 	 "~l
1530
1550
20
80
-
0
0
42
24
14
0
0
6
0
0
0
- .
0
0
52.5
30.0
17.5
0
Obs. 1























Obs.























      24-hour  clock  start and end times
     p            .
     "Excluding  the  time that readings were not  recorded  for period- of observation.

      Readings recorded at 15-second intervals unless other v/ise noted.

     Observer 1  -  W. DeWees


     Observer 2  -  R. Amick

-------
     The testing series was terminated by OAP personnel before



the desired number of tests were run because the lime kiln.was



running at a high production rate, and visible emissions were



exceeding the average 5 percent opacity level that was normal



for the No. 1 lime kiln exit stack.

-------
                       IV.  PROCESS DESCRIPTION



     Limestone consisting primarily of calcium carbonate or combina-

tions of calcium and magnesium carbonate with varying amounts of

impurities is quarried at the Woodville Plant.  The limestone is

calcined or burned to form lime, commonly divided into two basic pro-

ducts—quicklime and hydrated lime.  Calcination expels carbon

dioxide from the raw limestone, leaving calcium oxide (quicklime).

With the addition of water, calcium hydroxide (hydrated lime) is

formed.

     The basic processes in production are:   (1) quarrying the lime-

stone raw material,  (2) preparing the limestone for kilns by crushing

and sizing, (3) calcining the limestone, and  (4) optionally processing

the quicklime further by additional crushing and sizing followed by
                                                                     i
hydration.  The majority of lime is produced in rotary.kilns which

can be fired by coal, oil, or gas.  Rotary kilns have the advantage

of producing high production per man-hour and a more uniform product.

However, they do require higher capital investment and unit fuel

costs than most vertical kilns.

     The Woodville Lime and Chemical plant has two rotary kilns

each equipped with a Buell electrostatic precipitator.  The kilns

are almost identical.  The feed for both is a dolomitic stone,

quarried on the site and  fed in sizes ranging from 1 inch to

2  1/4  inches at a rate of about 700 tons per  day.  There is no

-------
preheater.  Normally the kiln is fueled with a mixture of



95 percent Number 6 fuel oil and 5 percent natural gas.  Both



kilns have two heat transfer sections, each 20 feet long.  The



product, about 350 tons per day, is cooled in a.Neims cooler before



storage.  There is no product crushing, but undersize material



is separated and returned to the kiln.  The majority of the



product is used in the steel industry, mostly in basic oxygen



furnaces;, none of the product is hydrated.



     The electrostatic precipitator on kiln Number 1 was put in



operation in July 1971.  In this kiln the main process fan is



located before the ESP, with a cyclone before the fan to reduce



fan blade erosion.  The precipitator on kiln Number 2 was put in



operation in December 1973;  The main process fan is after the



ESP and there is no .cyclone.



     In both systems the inlet gas to the precipitators is cooled



to about 600°F with a combination of water injection and/or



tempering air.  Each precipitator has 28,800 square feet of



collecting surface area, which includes one cell and two fields;



design gas velocity is 1.5 feet per second and treatment time,



10.0 seconds.



     At present the dust collected from the precipitators is



disposed of in the quarry.  It is expected that in the future the



dust will be granulated and used as a component of dry mix



fertilizers that are blended in another part of the complex.
                             10

-------
               V.  LOCATION OF SAMPLING POINTS






     Figure 1 shows the sampling ports and sampling points used



in the No.  1 lime kiln exit stack.  The sampling ports were



located in a 63.5-inch inside-diameter vertical stack, 4 feet



(0.75 diameter) from the stack exit, and 12 feet (2.26 diameters)



from the nearest downstream disturbance.  In order to meet the



sampling requirements of Methods 1 and 5 of the Federal Register,



Vol. 36, No. 247, it was necessary to install a stack extension



on the ESP exhaust outlet.  Forty-eight traverse points (24



along each of two perpendicular diameters) were used as described



in the Federal Register Method 1.  Additional sampling points in



the existing stack at a lower site were used for some of the gas



sampling.
                             11

-------
                          Scaffolding
                                           Edge of roof
                                                         W
                                                           1          1
                                                          CROSS SECTION
                                            All Dimensions in Fool Arc Approximate
                              Port 3 " Diameter.
                             S Porl 6" Diameter J
                                       _  87' lo ground
              ELEVATION
Figure  1.   Test Site-No. 1  Kiln Precipitator Outlet.
                              12

-------
                   VI.  PROCESS OPERATION






     The EPA project engineer arrived at the plant at 3:00 p.m.



on Monday, May 20.  At this time the plant was running at 5 to



10 percent over the normal production rate.  Because the



Pfizer Chemical Company lime plant in Perrysburg, Ohio, had



just gone on strike,.production at the Woodville plant had



been increased to the absolute maximum in anticipation of



increased demand.  Neither stack was clear (about 20% opacity),



and the ESP voltage and amps were reading low. .'It was assumed



that the higher opacity was due to the increased production rate,



which caused the process to emit greater concentrations of dust.



The kiln feed rate was calculated by multiplying the factor of



0.7291666 times the total indicated tonnage recorded from the



control room stone totalizer meter (see reference letter in



Appendix D).



     On the morning of May 21, kiln No. 1 was processing an



average of 30.62 tons of stone per hour.  The ESP voltage and



amp readings were still low, and opacity readings still high.



(about 15%, with some as high as 30%).  A water spray was added



to the feed end of the kiln to increase the conductivity .of the



gas stream in the ESP, but no effect on collection performance



was noticed.  Plant officials believed that increasing the
                             13

-------
production capacity may have resulted in "heavy .combustibles"



(oil) passing into the ESP.  This oil possibly combined with



dust to build up a coating on the wires and plates.  This



coating would eventually be removed by the rappers but this



process might require several weeks.  Further testing was post-



poned until the time when the plant and the ESP resumed normal



operation.  The operating variables are summarized in Table 4.
                             14

-------
        Table 4.  SUMMARY OF OPERATING VARIABLES
Test No.                           1

Stone feed rate , (tons/hr)         30.62

Oil rate, (gal/hr)                388

Gas to oil ratio, (BTU .Basis)

Mid kiln temp.,(°F)              1490-1530

Feed end temp.,(°F)              1040-1100

Before ESP temp.,(°F)             690-740

Stack temp.,(°F)                   675-710

Electrostatic Precipitator Data

A Field

Primary current,(amps)             35-46

Primary voltage,(volts)           210-245

Precipitator current,(amps)      0.17-0.21

B Field

Primary current,(amps)             22-39

Primary voltage,(volts)           200-245

Precipitator current,(amps)      0.12-0.21
NOTE:  No operational data were collected during the
       preliminary run on May 20, 1974.
                           15

-------
          VII.  SAMPLING AND ANALYTICAL PROCEDURES




     Sampling procedures were designated by EPA.  Analyses of


collected samples were performed by PEDCo.  Appendix G presents


detailed sampling and analytical procedures.


Velocity and Gas Temperature


     Gas velocities were measured with a calibrated type S


pitot tube and inclined draft gage.  Velocities were measured


at each sampling point across the stack diameter to determine


an average value according to procedures described in the


Federal Register  - Method 2.  Temperatures were measured with


the use of a thermocouple.


Molecular Weight


     A 4-hour integrated sample of the stack gases was collected


during test 1 by pumping the gas into a Tedlar plastic bag at


the rate of approximately 0.005 CFM.  This bag sample was then


analyzed with an Orsat analyzer for C02, 0-,  and CO as described


in the Federal Register, Method 3.                 .       .


Particulates

                                               2
     Method 5 as described in Federal Register,  was used to


measure particulate matter.  A rigid train consisting of a heated


glass-lined probe, a 3" glass fiber filter, and a series of Green-


burg-Smith impingers, as shown in Figure 2, was employed in all


particulate tests.
1)  Federal Register, Vol. 36, No. 247, December 23, 1971.

2)  Federal Register, Vol. 36, No. 159, August 17,  1971.

                             16

-------
                                  FILTER
                                                                        THERMOMETER
HEATED
GLASS
PROBE
                                          Jj_qO_m.L_ OF WATER
                                       THERMOMETERS
UMBILICAL
CORD
        CALIBRATED ORIFICE
            MANOMETER- I
                        Figure  2.  Particulate Sample Train

-------
     Sampling was conducted under isokinetic conditions



by monitoring the velocity with a pitot tube and adjusting



the sampling rate accordingly.  Because of the heavy dust



loading during a 4-hour test, two filter changes were required



during Test 1.  After 131 minutes of testing on Test 1 the



high temperature and high vacuum pulled a hole in the poly-



vinyl vacuum line in the meter box.  The hole was detected



immediately because of the vacuum that was required to sample.



The test was terminated at this point.



     Sample recovery consisted of triple-rinsing the nozzle,



probe, cyclone by-pass, and front half of the filter holder



with acetone into a glass container.  The back half of the



filter holder, impingers, and connecting tubes were first



rinsed with distilled water, then placed in a glass container



along with the impinger contents.  These components were then



triple-rinsed with acetone and the washings placed in another



glass container.  The filter was placed in a separate con-



tainer.  Blank samples of water and acetone were also taken.



     N0x





     Nitrogen oxides were collected in evacuated 2-liter



flasks containing 25 ml of a dilute sulfuric acid/hydrogen



peroxide absorbing solution.  The sampling and analytical



procedure was as described in Method 7 of the Federal Register



except that the final flask vacuum was read immediately after



sampling.
1) Federal Register, Vol. 36, No. 247, December 23, 1971,
                             18

-------
The samples were analyzed by the PDSA method.  Two samples



were lost in the lab by breakage.



     so2



     Sulfur dioxide was determined by passing a measured volume



of flue gas through a set of midget impingers at a rate of



approximately 0.025 cubic foot per minute.  The first impinger



contained 15 ml of 80 percent isopropanol; the second and third



impingers contained 15 ml each of hydrogen peroxide in water



solution.  The hydrogen peroxide solution was titrated with



barium chloride using a Thorin indicator to determine sulfur



dioxide  (S0?).  Because the concentration was so low, less than



1 ml of titrant was required and an accurate measurement was



not possible.
                             19

-------