AN EVALUATION
            OF  THE
   ATOMICS   INTERNATIONAL
  MOLTEN CARBONATE  PROCESS
             PREPARED FOR
NATIONAL AIR POLLUTION CONTROL ADMINISTRATION
         CONTRACT CPA  70-76
          SINGMASTER & BREYER
CHEMICAL & METALLURGICAL PROCESS ENGINEERS
             NEW YORK, NY.

-------
            AN EVALUATION OF THE

            ATOMICS INTERNATIONAL

          MOLTEN CARBONATE PROCESS
                Prepared for


NATIONAL AIR POLLUTION CONTROL ADMINISTRATION

        Environmental Health Service

            Public Health Service

Department of Health, Education, and Welfare

             CONTRACT CPA 70-76
                      By
             SINGMASTER & BREYER
            235 East 42nd Street
          New York, New York  10017
                                     November 30,  1970

-------
                     TABLE OF CONTENTS

                                               Page Number

    REPORT IN BRIEF                                i

    ACKNOWLEDGEMENTS                              vi

1.  INTRODUCTION                                  1-1

2.  RECOMMENDATIONS                               2-1

3.  PROCESS DESCRIPTION                           3-1

    a)  General                                   3-1
    b)  Process Description                       3-1
    c)  Basis for Material Balance                3-8
    d)  Utilities for Base Case                   3-12
    e)  Heat and Material Balances for
         Alternate Cases                          3-13

        Process Flow Diagram        -PS-218-0001
        Engineering Flow Diagram-
         SO  Removal                -PS-218-0002
        Engineering Flow Diagram-
         Coke Handling Facilities   -PS-218-0003
        Engineering Flow Diagram-
         Lithium Carbonate Recovery -PS-218-0004

4.  PLANT CAPITAL AND OPERATING COST ESTIMATES    4-1

    a)  Base Case                                 4-1
    b)  Alternate Cases                           4-4
    c)  Construction Cost Estimate Summary Sheets 4-27

5.  DISCUSSION OF PROCESS PROBLEMS                5-1

    a)  Absorber                                  5-1
    b)  Reducer                                   5-5
    c)  Reducer Off-Gas Cooling                   5-6
    d)  Regeneration                              5-8
    e)  Fly Ash and Coke Filtration               5-14
    f)  Carbonate Makeup                          5-17
    g)  Carbonate Recovery                        5-21
    h)  Waste Heat Recovery                       5-23
    i)  Integration into Existing Power Plants    5-24
    j)  Copper Smelter                            5-26

-------
                          TABLE OF CONTENTS (Cont'd)

6. ECONOMIC STUDIES
a) Optimum Process Location of
Electrostatic Precipitator
b) Electrostatic Precipitator
Efficiency and Penalties
c) Absorber- Size, Number and
Configuration
d) Reducer- Size, Number and
Configuration
e) Coke - Economic Aspects
f) Lithium Carbonate Recovery Process
g) Copper Smelter
7. -EQUIPMENT - BASE CASE
a) List of Equipment
b) Specifications
c) Vessel Sketches
d) Motor List
8. PLANT ARRANGEMENT DRAWINGS - BASE CASE
Page Number
6-1

6-2

6-6

6-10

6-13
6-22
6-24
6-27
7-1
7-1
7-5
7-20
7-33
8-1
Site Arrangement Plan   Drawing No. PS-218-0501
Site Arrangement-
 Elevations & Sections  Drawing No. PS-218-0502
Filter and Recovery
 Process Building-
 Equipment Arrangement  Drawing No. PS-218-0503

REFERENCES                                    9-1

APPENDIX

Construction Cost Estimate - Base Case Plant
 (Machinery & Equipment - Account 400)

-------
REPORT IN BRIEF

     The Molten Carbonate Process for the removal of sulfur
oxides from power plant stack gases has been evaluated by
Singmaster & Breyer under Contract No. CPA 70-76, National Air
Pollution Control Administration.  This process was developed
by Atomics International.  Singmaster & Breyer reviewed the pre-
vious experimental work and process criteria in the course of
making this evaluation.  The purpose of the evaluation was to
advise the sponsor on the continued course of action regarding
this process.

     The removal of sulfur oxides from an 800 MW power plant
operated with coal containing 3% sulfur was selected as a base
case for evaluation.  Alternate cases were also evaluated from
the results developed for the base case.  Alternate cases in-
volving coal-burning power plants included 2 additional capac-
ities, 400 and 1000 MW, and coal sulfur contents of 1 and 6%.
Various copper smelter situations were also reviewed.  A smelter
producing 200 tons per day of copper by a reverberatory furnace
process was presented as an alternate case.

     The Molten Carbonate Process appears to be technically
feasible.  .Process and engineering problem areas were identi-
fied and potential solutions were examined.  While there are
evident solutions to known problem areas, these proposed solu-
tions still remain to be demonstrated.

     The evaluation of the base power plant case, 800 MW at
3% coal sulfur, resulted in an estimated capital cost of $13-.4
million, to achieve a 95% reduction in sulfur oxides emission.
This capital cost was equivalent to approximately $17 per KW
of station capacity.  The annual operating cost including de-
preciation was estimated to be in the region of 0.9 mills per
station KWH.

     The Molten Carbonate Process converts recovered sulfur
oxides successively to sulfides and I^S.  The final step is
the production of elemental sulfur from f^S gas by the Glaus
process.  This present evaluation did not include the costs
of a Glaus Plant or credit for the value of the sulfur pro-
duced.
                                                  SINGMASTER S BREYER

-------
      This report presents a description of the process,  process
 and design criteria, and the assumptions that were made  to esti-
 mate the costs for the base case sulfur oxides recovery  plant.
 Also included for the base case are process and engineering flow
 diagrams, plant arrangement drawings,  material balances,  heat
 duties and process equipment specifications.

      Costs and material balances for the alternate cases were
 derived from the base case.  Sulfur oxide recovery,  plant capi-
 tal, and operating unit costs responded significantly to coal
 sulfur contents in the range 1 to 6% as described on Figure 1.
 Unit costs at 800 and 1000 MW plant capacity were essentially
 unchanged for a given coal sulfur content.   The unit costs at
 400 MW capacity increased significantly,  according to these
 estimates.

      Major process and engineering problem areas still require
 ing demonstrated solutions suitable for full scale application
 were identified as follows:

      1.   Elimination of melt carryover with the absorber off-
 gas.

      2.   Liquid/gas absorber ratios and absorber design  for
 effective sulfur oxides removal from flue gases.

      3.   Construction materials and fabrication of the process
 melt reducer,  operating at the temperature  of 1500°F.

      4.   The  sequence of reduction reactions  and the required
 internal  design of the reducer.

      5.   Fly  ash and coke filters  capable of  producing a  low
 liquid content  solids cake at  the  process temperature of  850°F.

      6.   The  extent to which the carbonate  components from
 solids filter cakes can  be economically recovered.

     This evaluation also attempted to  account  for the chloride
 content of the  coal,  which would appear in  the  process melt as
potassium chloride,  both in solution and  as a solid.   The pres-
ence of potassium  chloride  was  found to affect  the costs  and

-------
design of the fly ash filter, the reducer exit gas heat exchanger,
and the cost of carbonate recovery from the filtered solids.

     Significant process tradeoffs that were developed during
this evaluation include the following items:

     1.  Electrostatic precipitation of fly ash from flue gases
at the process temperature of 850°F cost significantly less than
precipitation at the lower conventional flue gas exit tempera-
ture of 325°F, followed by reheat to 850°F.

     2.  K high temperature electrostatic precipitator operating
at 99.5% efficiency costs less than higher or lower efficiencies,
as governed by downstream melt replacement costs at the fly ash
filter.

     3.  Type 347 'stainless steel for absorber construction was
economically more favorable than low alloy steel, when both
alloys were applied to compatible process designs.

     4.  Evaluation of reducer criteria showed that a horizontal,
cylindrical vessel configuration with internal refractory lining
was superior to other alternates at the reaction temperature of
1500°F.

     5.  Current market costs and availability now favor green
delayed coke as a reducing agent to convert recovered sulfur
oxides to sulfides, in place of fluidized petroleum coke.

     6.  The complete recovery of all carbonate melt components
from filtered solids should be investigated further.

     7.  Preliminary estimates of smelter operation showed  that
it was more economical to replace an existing bag filter system
with a high temperature  (850°F) electrostatic precipitator.
However, reheating of process flue gases to 850°F was more
favorable for an existing electrostatic precipitator operating
at 600°F.

     A final evaluation and plant design for the Molten Carbon-
ate Process requires further development to establish the char-
acteristics and design for some steps in the process.
                                                 SINGMASTER & BREYER

                                 iii

-------
      This report recommends continued development and  evaluation
 of the process.

                                        SINGMASTER & BREYER
                                           W. Drobot
                                           S. Finkier
                                           D. R. Whitlock
November 30, 1970
                                  xv

-------
            Figure 1.   Capital Cost and Annual

                        Operating Cost for  SOX.

                        Removal vs. Plant Capacity

                        for Various % S Coals
B-  1 • 6




   1.4




   1.2




   1.0




    .8
CO
-H
a
en
O
u
c
•H
-P
nJ
(1)
ft
O
VJ-
O
O
 rd
 4J
•H
 O,
 (fl
 U
     .6
24




22




20




18




16




14




12




10
                            S in
                             Coal
                        3%  .
                             1%
       200  300  400   500  600  700  800   900 1000  1100


                       Plant Capacity, MW
                                                SINGMASTER S BREYER
                              V

-------
     ACKNOWLEDGEMENTS

     The work upon which this publication is based was per-
formed pursuant to Contract No. CPA 70-76 with the National
Air Pollution Control Administration, Environmental Health
Service, Public Health Service, Department of Health, Educa-
tion and Welfare.

     Singmaster & Breyer appreciates the guidance of NAPCA
staff members, Messrs. D.A. Kemnitz, Project Officer and
E.D. Margolin, Chief, New Process Development Section,
during the conduct of this study.

     We also appreciate the cooperation of Messrs. R.D.
Oldenkamp, B. Katz and C.A. Trilling and other members of
the staff of Atomics International who have provided further
clarification of the Molten Carbonate Process; and Mr. W.J.
Cooper of MSA Research for his assistance in evaluating the
chemical aspects of the A.I. Process.

-------
1.  INTRODUCTION

    This study was performed to review and evaluate The Atomics
International Molten Carbonate Process for removal of SO2 from
coal burning power plant stack gases and from copper smelter
gaseous effluents.

    The overall process was examined and each process step was
analyzed according to technical and economic considerations.
From this analysis, a base case plant was defined for removal
of S02 from an 800 MW power plant burning coal containing 3%
sulfur, 0.04% chloride and 10% ash.  Costs of SO2 removal for
alternate cases such as for one and six percent sulfur in coal
and for 400 and 1000 MW power generating stations burning coal
containing one, three and six percent sulfur were also estimated.
In addition, the process was evaluated for removal of SO2 con-
tained in copper reverberatory furnace off-gas.

    The evaluation excluded the capital and operating costs for
a Glaus Plant to recover elemental sulfur from the Molten Car-
bonate Process off-gas.  Furthermore, no credits were allowed
in the operating cost estimate for byproduct sulfur recovery
or for the use of high sulfur coal.
                                                  SINGMASTER & BREYER

                              1-1

-------
2.  RECOMMENDATIONS

    Our recommendations are based on the technical aspects of
the process.  We have not compared the cost of this process
to competitive processes nor have we considered:

    1)  the future availability and price of raw materials.

    2)  the effect of possible release to the atmosphere of
carbonate from the boiler stack if the melt is carried over
with the absorber off-gas, and

    3)  the discharge of soluble salt solutions from the lithium
carbonate recovery process.

    The process appears to be feasible; however, certain problem
areas have been uncovered which should be defined in a thought-
ful pilot program where corrective measures can be tested.  A
complete technical and economic evaluation of the process can
only be performed after the pilot program is completed.

    It is therefore recommended that development and evaluation
of the process be continued.  We believe that a pilot plant is
the next logical step in this development.  Operation of a
materials test loop can either precede the pilot plant or be
carried out as a study parallel to the pilot plant program de-
pending on time and funds available to the program.

    The development program and materials test loop should be
planned to:

    1)  Confirm the selection of construction materials

    2)  Confirm equipment design criteria

    3)  Confirm process performance and reaction yields

    4)  Estimate equipment operating cycles

    5)  Determine maintenance requirements
                                                 SINGMASTER & BREYER

                                     2-1

-------
           6)  Determine control and monitoring procedures

           7)  Identify equipment components requiring intensive
 development

           The pilot plant should be designed to scrub SO2 from
 flue gases from an existing power plant preferably burning both
 coal and fuel oil.  The recommendation for a combination fired
 boiler is based on initially running the pilot plant with flue
 gases produced from fuel oil firing to minimize the  problems
 associated with coal fly ash.   However,  location at  a power plant
 firing only coal would merely mean a rearrangement of priorities
 in the fields of investigation.

           In order to minimize boiler downtime,  we recommend
 that the flue gas be taken from the stack and reheated to ab-
 sorber temperature by direct combustion of low ash fuel.   De-
 pending upon the capacity of the pilot plant it may  be advisable
 to include an indirect exchanger to recover some of  the heat
 available in the absorber off-gas to reduce operating costs;
 but,  this should be evaluated during the planning of the pilot
 plant„

           The absorber is the  critical step in the process for
 it is here that the SC>2  must be removed from the flue gas with
 a  minimum amount of melt carried off with absorber exit gases.
 As a  minimum program,  the absorber must be tested to determine
 scrubber efficiency,  nozzle  performance,  and demister efficiency;
 but,  the amount of melt  required to carry out these  tests only
 may be  substantial and,  it will probably be necessary to regen-
 erate the melt  on a campaign basis to minimize these raw material
 costs.   The  demonstration absorber should be sized so that the
wall  effects that were evident  in the bench scale  tests will be
 negligible.

          The remainder  of the  process steps can be  designed to
operate  on a campaign basis which will require suitable surge
capacity between  the  steps.  The  equipment required  for the re-
maining process  steps need not  be  designed for the same melt
rate  as the  absorber.
                                   2-2

-------
    The pilot work on filtration should be directed to increas-
ing the filter cake thickness consistent with acceptable pressure
drops across the filter cake.  This will aid in minimizing capital
costs and may reduce melt losses associated with discarded filter
cake.

    The operability of the two-zone reducer must be determined
in the pilot plant.  The design parameters must also be con-
firmed as well as the best method for introducing coke into the
reducer.  The advantage of a two-zone reducer lies in the effect
of a more concentrated stream of carbon dioxide on the design
and performance of the regenerator and the effect of a more con-
centrated stream of hydrogen sulfide on the capital cost and
performance of the Claus Plant.  A concentrated stream of carbon
dioxide can be obtained in other ways.
          1
    Regenerator testwork should be directed to confirm the equili-
brium data.  The pilot plant regenerator should be provided with
spare trays of different types that can be installed with the
minimum amount of field modifications to test their efficiency.
The regenerator off-gases can be incinerated and sent to the
stack; it is not necessary to include a small Claus Plant for
recovery of the sulfur since the gas analysis can be used in the
design of a Claus Plant to be installed in a commercial size
plant.

    Initially, no waste heat recovery systems should be installed
but appropriate test units should be included in the pilot plant
to determine the problems associated with this heat recovery.

    Recovery of lithium salts should not be attempted, however,
laboratory work should parallel the pilot plant work to develop
a suitable process for recovery of not only the lithium salts
but sodium and potassium salts as well.
                                                  SINGMASTER & BREYER
                               2-3

-------
3.  PROCESS DESCRIPTION

    a.  General

        The Atomics International Molten Carbonate Process for
removal of SOX from power plant flue gases is depicted on the
attached process flow diagram, Drawing PS-218-0001.  This is
the conceptual scheme for all cases under consideration.  Some
modifications are possible and these variations as well as the
reasons for selection of the process scheme are discussed in
later sections of this report.  The material balance on the pro-
cess flow diagram is for the base case power plant operating at
800 MW and burning coal containing three percent sulfur.

        The attached engineering flow diagrams: -
         I                                  :
        PS-218-0002   SOV Removal
                        it

        PS-218-0003   Coke Handling Facilities

        PS-218-0004   Li2CO_ Recovery

along with the plant arrangement drawings in Section 8 of this
report form the basis for the capital and operating cost esti-
mates for removal of SO., from the base case power plant flue
                       j£
gases.

    b.  Process Description

        In essence, the process consists of scrubbing the flue
gas with a molten mixture of lithium, potassium, and sodium
carbonates  (minimum melting point 750°F).  The melt, containing
up to 32% sulfite salts, is regenerated by heating to 1500°F
where the sulfates formed by disproportionation of the sulfites
can be reduced to sulfides with carbon.  The sulfides in the
melt are converted back to carbonates with the formation of
hydrogen sulfide by reaction at 850-900°F with carbon dioxide
and steam.
                                                 SINGMASTER & BREYER

                               3-1

-------
                1)  SO  Removal - Drawing PS-2 18-0002
                    ^ ________ _______

                    Absorber

                    Flue gases taken before the economizer section
 of the boiler are passed through four electrostatic precipitator
 sections operating in parallel at 800-850 °F where 99.5 percent of
 the fly ash is removed.  The gases are sent from each precipitator
 to an associated absorber for removal of the SOX by the molten
 carbonate stream and are returned to the economizer section of the
 boiler.

                    The absorber reactions can be expressed as:
                    SO2 + M2CO3 - *>    M2SO3 -f CO
                    SO3 + M2CO3 - *•     M2SO4  + CO2

where M represents the eutectic mixture  of sodium,  potassium and
lithium cations.

                    Some of the M2SO_ may be oxidized  to  the  sulfate
by the oxygen in  the  flue gas  as follows:

                    M2so3 + h o2 - *-    M2so4

                    All sulfides are also oxidized to  sulfate as
follows:

                    M2S + 202   - *•    M2SO4

                    The melt from the first absorber,  V-1A, flows
by gravity into one pump tank,  V-2A, and  is recirculated  by P-1A
to the  absorber.   The  net increase of returned melt into the
absorber circuit  from  the Regenerator System is pumped under level
control to the recirculating line of Absorber V-1B.   The melt then
proceeds under level control in series from one absorber pump tank
to the next absorber.   Essentially, the  flue gases  flow  in parallel
and the melt  flows  in  series through the  absorbers.   The M2CO3
content of the melt leaving the last absorber is maintained  above
68 mol percent to keep  the  freezing point  of the melt below  800 °F.
                                  3-2

-------
        Each pump tank is sized to hold all the liquid drained
from its associated equipment.  Each is also equipped with
electrical heaters to remelt frozen process liquid in the event
of a plant shutdown.

        Fly Ash Filtration

        The melt from the last absorber pump tank, V-2D, is
pumped under level control to one of two parallel fly ash
filters, F-l, where the fly ash is removed from the process
melt and sent to the Li^O^ Recovery Process.  When the
pressure drop through the first filter exceeds an allowable
limit the second filter is brought into operation.

        The filtered melt is then split into streams, each
under flow control, for charging to each of four reducers.

        Reducers

        Each reducer is a two-compartment vessel - one an
oxidation zone and the other reduction a zone with liquid
passage between the two compartments for internal melt re-
circulation.

        The endothermic heat for the reduction and the
sensible heat required to raise the melt, coke and air to
the reduction temperature of 1500°F is provided by the oxi-
dation of M2S in the oxidation zone of the reducers.

        At 1500°F the M2SO3 in the melt disporportionates to
M2S04 and M2S"  The M2S04 1S reduced in the reduction zone to
M2S by the carbon contained in the coke.  Part of the reduc-
tion zone melt is recycled to the oxidation zone to oxidize
the M2S and provide the necessary heat.  The oxidation zone
melt also recycles back to the reduction zone to convert the
      to M2S.
                                                 SINGMASTER & BREYER

                               3-3

-------
               The reactions in the reducer may be expressed as
 follows:
               Oxidation:   M2S + 202
               Reduction:  M2SO4  + 2C   - *.  M2S + 2CO2

      Disproportionation:
         Coke  S Recovery:   S  + %C + M2CO3 — w M2S + 3/2 CO2

               The  air  for  the oxidation zone is provided by the
 combustion air blowers, B-l.  These blowers develop sufficient
 head to  overcome the pressure drop of the  reducer, exchanger
 and regenerator and to supply the Glaus Plant with gas at 3 inches
 W.G.  The  combustion air is  preheated in E-2 by oxidation zone
 off-gas  to at least 600 °F  and admitted to  the oxidation zone of
 the reducer through sparger  pipes.  As conceived, coke is charged
 to  the reduction zone  by pneumatic blow tanks.

               The  oxidation  zone off-gas is used to preheat the
 incoming combustion air before being sent  to the boiler with the
 absorber off-gas.  The reduction zone off-gas, consisting essen-
 tially of  CO2,  is  used in  the Regenerator.  An excess of CO2 is
 produced in this zone  and  the excess is diverted to the oxidation
 zone  off-gas  stream.   An equimolar quantity of H20 and CO2 is
 required for  the regeneration step.  The H20 is supplied to the
 CO2  stream by direct injection of both water and/or steam to
 reduce the temperature of  the CO2 stream from the 1500°F level
 to the required regenerator temperature of 850°F.  The steam is
 assumed  to be  available from  the waste heat boiler in the Glaus
 Plant.

              The melt from the reducer at 1500 °F is cooled to
 950 °F by recirculating 850 °F  reduced melt  from the Reducer Product
Cooler.  This recirculation is controlled by the temperature of
the melt in the Reducer Quench Tank.
                                3-4

-------
        The melt from the Reducer Quench Tank is pumped through
the cooler and is recirculated as mentioned above.  The net
excess of melt flows under level control to the coke filters.

        Coke Filtration

        The melt from the reduction step flows to one of two
parallel coke filters, F-2, where the unreacted coke is removed
from the process melt and sent to the I^CO., Recovery Process.
Flow is diverted to the second filter when the pressure drop
through the first unit exceeds the allowable limit.

        The filtered melt is then sent to the Regenerator.

        Regeneration

        The regeneration reaction is expressed as:

        M2S + C02 + H20  	*•   M2C03 + H2S

        The regenerator is a tower consisting of 15 bubble cap
trays where the melt is added to the top of the column and is
contacted with the C02 and 1^0 rising up the tower.

        The regeneration is exothermic and coolers are provided
to remove this heat.  The intermediate cooler takes the total
flow of the upper section of the tower and returns a portion
of this flow under temperature control to the upper section to
cool the tower.  The remainder of the cooled melt is sent under
level control to the lower section of the regenerator.

        The bottoms cooler acts in the same manner as the
intermediate cooler to cool the lower section of the regenera-
tor.  The cooled bottoms which are not recirculated to the
regenerator are returned under level control to the absorber.

        The gases from the Regenerator at 3 inches W.G. con-
taining H_0, C02 and H2S are sent to a Glaus Plant for recovery
of sulfur.
                                                 SINGMASTER & BREYER

                               3-5

-------
               M2CO3
               The eutectic mixture of M2C03  required for the
 initial charge and makeup is prepared in the M2CO3 melt  tank,
 V-9.

               The sodium,  potassium and lithium carbonates  are
 received by truck and fed to individual silos each with  a nominal
 four-day storage capacity.  The lithium carbonate which  is  re-
 covered in the Li2CC>3 Recovery Process is also stored in the
        silo.
               Each melt component is  fed under weigh  control to
 V-9 which is electrically heated to melt the  solid.   The tank
 has a nominal 16-hour capacity which  permits  charging of the tank
 during daylight hours only.

               The  melt is fed  to the  process  under  flow control.

           2)   Coke Handling Facilities - Drawing PS-218-0003

               Green delayed coke of minus 2 inch size is delivered
 in  rail cars and is fed to a crusher  to  reduce its  size to minus
 1/4 inch.  The crushed coke is screened  and the oversize returned
 in  closed circuit  to  the crusher.  The under size material is
 charged to two coke silos with a total of 4 days live storage
 capacity.

               The  coke is withdrawn from the  silos  and fed by
belt  conveyors to  a coke bin associated  with  each reducer.

           3)   Li2CO3  Recovery  Process -  Drawing PS-218-0004

               The  recovery process as conceived has been developed
by Atomics International.  However, in the process concept which
has been evaluated, filtrations  are carried out continuously and
reactions are batch operations.   It has been  assumed  that the
chlorides and heavy metals to be  removed from the Molten Carbon-
ate Process report with  the fly  ash and  coke  filter cakes,
respectively.
                                3-6

-------
        The fly ash and coke filter cakes from the Molten Car-
bonate Process are quenched with water and charged to T-110
where the soluble salts are dissolved.  The slurry is pumped
to a rotary drum vacuum filter, F-101 and the insoluble fly
ash, coke and lithium carbonate are removed as the cake.
The dissolved salts containing the chlorides are removed as
filtrate.

        The cake is slurried with returned filtrate from F-103
or with water and is held in T-102 to await the completion of
the batch reaction in the LiHCO3 Reactor, V-101.  The slurry
is pumped to V^-IO! and CO2» prepared in an inert gas generator,
is bubbled through under back pressure control to convert the
insoluble Li2C03 to soluble LiHC03.  The CC>2 is maintained
under approximately 20 psi partial pressure.

        The carbon dioxide required for the conversion to
LiHC03 can possibly be supplied from either the excess gas
available from the reducer or from power plant flue gases.
These alternate sources were not considered in the evaluation
in order to separate the Li2003 Recovery Facilities from the
Molten Carbonate Process and the power plant.

        The contents of V-101 are discharged to the surge
tank, T-103 to permit charge of the next reactor batch.  The
reactor product is filtered in the filter, F-102 and the fly
ash and coke filter cakes containing the heavy metals are
slurried with the filtrate of F-101, in T-101 and sent to
disposal along with the fly ash from the electrostatic preci-
pitator.

        The filtrate of F-102 is pumped to the Li2CC>3 Reactor,
V-101, where hot air is added to convert the soluble LiHCO3
to the insoluble Li2CO3.  After the conversion is complete,
the reactor is emptied into the surge tank, T-104 and a new
batch is added to the reactor.
                                                  SINGMASTER & BREYER

                                   3-7

-------
              The L±2CO3  slurry  in T-104 is continuously pumped
 to  the I^COg Filter,  F-103.  In order to recover any soluble
 lithium values, the  filtrate  from F-103 is recycled in the pro-
 cess  and used to slurry the filter cake from F-101.  The wet
 lithium carbonate filter  cake from F-103 is dried and conveyed
 to  the I^COo silo,  T-5,  for  use as makeup in the Molten Car-
 bonate Process.

          4)  Instrumentation

              The instrumentation to monitor and control the
 process steps is shown on the engineering flow diagrams.  This
 instrument concept may have to be modified after experience is
 gained in operations of a pilot  plant or a commercial plant.

      c.  Basis for  Material  Balance

          The material balance for the base case plant  (800 MW
power plant burning  280 tons  per hour of coal containing three
percent sulfur and 0.04 percent  chlorine)  which is shown on the
Process Flow Diagram - Drawing No. PS-218-0001 is based on the
 following:

          1)  Coal Combustion

              The coal analysis  is shown as follows, based on
a typical analysis used by Atomics International.  The oxygen
content in the coal was adjusted to allow a typical chlorine
content of 0.04%.
                                3-8

-------
          Coal               Composition
       Component               Weight %

          C                    70.00

          H                     4.80

          0                     5.76

          S                     3.00

          Cl                    0.04

          N                     1.40

          Ash                  10.00

      Moisture                  5.00
                              100.00

        Assumptions used to calculate the boiler flue gas
compositions are:

        Excess Air - 20%
        95% combustion of S
        90% of Cl volatilized to HCl
        85% of ash entrained with the boiler flue gas
        95% combustion of C (unburned C remains in
                               furnace ash)
       100% combustion of H
       100% volatilization of 0, N and H00
                                        £e

    2)  Process Conditions

        a)  All process chemical conversions are 95% except:

            1.  M^S oxidation in absorber - 100%.

            2.  M2SO_ disproportionation downstream of
absorber - 10%.

            3.  M2SOo disproportionation in reducer - 100%.
                                                  SINGMASTER & BREYER

                                3-9

-------
               b)   M2CO3 mol concentration at absorber exit,  68.0%.
 This is a minimum allowable value.

               c)   Absorber recycle  ratio,  1:1 (mols of liquid re-
 cycled to absorber:  mols of liquid  entering reducer).  This  ratio
 is specified as a target.   (Maximum allowable recycle ratio  is
 3:1.  Pumps to be sized for 3:1 recycle).

               d)   The saturation concentration of KCl in process
 melt is 3.0 weight percent at the regenerator inlet,  the point
 of lowest solubility.

               e)   All process streams are  nominally 850°F, except
 where noted.

               f)   Other assumptions used in this calculation are
 listed as follows:

                   Precipitator

                   99.5% fly ash removal.

                   Absorber

                   95% removal of residual  SOX,  fly ash,  and  HCl
 conversion to  KCl.

                   SO  consists of 90 mol % SO9  and 10 mol %  SO3.
                     J^        -                &

                   All entering M2S  is oxidized  to M2SO.,  with the
 consumption of 02  from the flue gas.

                  HCl is converted  to insoluble KCl,  with the
 equivalent consumption of  K2CO3 from the melt.

                  Fly ash  Filter

                  Melt content of fly ash  filter cake,  65 weight
percent.
                               3-10

-------
            Reducer

            Inlet air 600°F, and coke at 70°F

            Reducer temperature, 1500°F.

            The heat generation for the reduction reaction was
derived by air oxidation of equimolar quantities of t^S and
carbon in coke.  Complete consumption of carbon and oxygen for
oxidation was assumed and reduction of M^SO* by carbon was
assumed to be 95% complete.

            95% sulfur in the coke converted to I^S.
(Unconverted coke sulfur remains as solid residue).

            'Coke Analysis:

                              Composition
            Component           Weight,%

               C                  81.6

               S                   6.0

              Ash                  0.4

              Volatiles           12.0
                                 100.0

            Coke Filter

            Melt content in filter cake, 50 weight percent.

            Regenerator

            Inlet CO., and H00 at 85% stoichiometric excess.
                                                  SINGMASTER S BREYER

                               3-11

-------
     d.  Utilities  for  Base Case

         The utilities  required for the base case plant are:

1)  Water

     Process Water(Boiler Feed Water Preferred)
          Regenerator                                     12 GPM

     Raw Water
       Miscellaneous Requirements
        (including Lithium Carbonate Recovery)            100 GPM

2)  Steam (Assumed available from Glaus Plant)
       Regenerator                                   12,000 #/Hr

3)  Fuel (Natural Gas)
       For Lithium Carbonate Recovery Process
         Li2CO3 Dryer                                    800 SCFH
         Inert Gas Generator                           8,000 SCFH
                                           Total       8,800 SCFH

4)  Power
       Approximate Motor Operating Load                2,100 KW
         (See Motor List-Section 7)
       Heat Tracing                                      175 KW
       Lighting                                           25 KW
                           Total Average Load          2,300 KW

       Differential Power for High Temperature
            Electrostatic Precipitator                 1,980 KW

       Differential Power for Boiler I.D. Fan            950 KW
                                           Total       5,230 KW
                               3-12

-------
     e.  Heat and Material Balances for Alternate Cases

         The heat and material balance for the base case plant
(800 MW with 3 percent sulfur in coal) is shown on the Process
Flow Diagram - Drawing No. PS-218-0001.  Heat and material
balances for other power plant capacities and sulfur content
of coal have been prepared and are listed on the attached
tables.  In addition, a material balance for a hypothetical
copper smelter is also presented.

         The attached tables list only the important streams
in the process which can be identified by referring to the
Process Flow Diagram.

         The cases that have been considered are:

Case No.        Flue Gas From        Plant Capacity

  l(Base)       Power Plant          800 MW - 3% S in Coal
  2             Power Plant          800 MW - 1% S in Coal
  3  '           Power Plant          800 MW - 6% S in Coal
  4             Power Plant          400 MW - 3% S in Coal
  5             Power Plant          400 MW - 1% S in Coal
  6             Power Plant          400 MW - 6% S in Coal
  7             Power Plant         1000 MW - 3% S in Coal
  8             Power Plant         1000 MW - 1% S in Coal
  9             Power Plant         1000 MW - 6% S in Coal
 10             Copper Smelter       200 T/D copper
                 Reverberatory
                 Furnace    :
                                                  SINGMASTER & BREYER

                              3-13

-------
                                                        MATERIAL BALANCE
(jO
I
Case No. 2.
Process Gas
SC-2
S03
HC1
co2
H2°
°2
N2
Coke
Volatiles
^2S
Total
Fly Ash
800 MW,

#Mbl/hr
#Mol/hr
#Mol/hr
#Mol/hr
#lfol/hr
#Mbl/hr
#Mol/hr
#Mbl/hr
#Mol/hr
#tol/hr
#/hr
1.0% Sulfxir
2
142
16
5
33900?
7500
7900
179100


228600
238 v
in Coal.
Stream No.

4 5
7
1
0
181 34100
25 7500
7900
864 180000


1070 229500
111-9
Process Gas Input
Air #tfcl/hr
Water
Steam
Temp. ,°F
Flow. M SCFM
#H>l/hr
#Mol/hr




850
1444


850-1120 850
6.8 1450

6 10 11 12 13



326 329 160
329 160


20 20 20
162
346 678 502

1116
108
221
60 850 850 850 850
7.0 2.2 2.1 4.3 3.2

-------
                                                          MATERIAL BALANCE
                            Case No.  2.  800 MW, 1.0% Sulfur in Coal.

                                        Coke Rate, 7600 Ib/hr
U)


M
Ln
   1
   i
   Rl
                                                                Stream No.
Melt Components
v
M2S03
M2S04
M2G03
KCl, Dissolved
Total
Solids
KCl
Fly Ash

#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
Coke Residue #/hr
Total #/hr
Temp.,°F
Nominal
Flow rate, ^pm
Heat Exchanger
E-l:
E-2:
E-4:
E-5:
Duties,
15.4
6.0
3.2
4.8
14
0
258
82
816
44
1200
821.8
461.4
6.0
1289.2
850
120
MM Btu/hr

15
3
116
48
408
22
599
410.9
230.7
3.0
644.6
850
60
17
12
116
55
976
44
1203
410.9
230.7
6.0
647.6
850
120
18
3
114
48
401
22
588
4.1
2.3
0.1
6.5
850
59
19
172
0
7
387
22
588
4.1
2.3
294.1
300.5
1500
59
23
170
0
7
386
22
585
0.0
0.0
3.0
3.0
850
58
' ' Includes Stream




Li2C03 , 4
Na2C03 t 3
KoCOo. 5
26C
8
0
7
568
22
605
0.0
0.0
3.0
3.0
930
60
30,
.2
.0
.1
L) 31
1.0
0.0
0.0
2.2
0.1
3.3
4.1
2.3
291.1
297.5
850
-
#Mol/hr

32
0.1
2.3
1.1
7.4
0.4
11.3
406.8
228.4
3.0
638.2
850
-


                                                                                                   TO"

-------
                                                        MATERIAL BALANCE
U)
Case No. 3.

Process Gas
so2
so3
HC1
co2
H20
°2
N2
Coke
Vo la tiles
H2S
Total
Fly Ash
800 MW,


#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
fttol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
6.0% Sulfur

2
896
100
6
28500
21500
7200
162000


220200
238.0
in Coal.
Stream No.

4 5 6 10
45
5
1
1086 29586 1974
148 21648
7200
5182 167200
120

6416 225700 2094
11.9


11 12 13



1974 960
1974 960


120 120
1014
4068 3054

Process Gas Input
Air
Water
Steam
Temp.°F
Flow, M SCFM
#Mol/hr
#Mol/hr
#Mol/hr





850
1392
6698


850-1120 850 60 850 .
40.5 1.4 42.3 13.3

648
1326
. 850 850 850
12.5 25.7 19.3

-------
                                                         MATERIAL BALANCE
I
M
-J
   I
    to
    i
   I
Case No. 3.
Melt Components
MjS
M2S03
V°4
M2C03
KC1, Dissolved
Total
Solids
KC1
Fly Ash
Coke Residue
Total
Temp.,°F
Nominal
Flow rate, gpm
800 MW, 6.0% Sulfur in Coal.
Coke Rate, 45500 Ib/hr
Stream No.


#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
#/hr
14
0
1547
524
4944
256
7272
821.8
461.4
36.0
1319.2
850
727

15
19
696
315
2472
128
3630
410.9
230.7
18.0
659.6
850
363

17
72
696
357
5894
256
7275
410.9
230.7
36.0
677.6
850
728

18
19
694
314
2464
128
3619
4.1
2.3
0.2
6.6
850
362

19
1066
0
42
2383
128
3619
4.1
2.3
1764.2
1770.6
1500
362

23
1060
0
42
2370
127
3599
0
0
17.6
17.6
850
360

26 UJ
53
0
42
3422
127
3644
0
0
17.6
17.6
930
364

31
6
0
0
12
0
20
4
2
1746
1753


.2
.0
.2
.8
.8
.0
.1
.3
.6
.0
850

-

32
0.1
2.4
1.1
7.6
0.4
11.6
406.8
228.4
17.8
653.0
850
-
Heat Exchanger

   E-l:  94.1
   E-2:  36.0
   E-4:  20.0
   E-5:  30.0
                                     Duties, MM BTU/HR
(1) Includes Stream 30,  #Mol/hr
             Mr*f\    Q Q
            ol*Uo j   O • O

          Na2C03,   6.4

                   7.9
                  23.1

-------
                                                       MATERIAL BALANCE
00
Case No. 4.
Process Gas
S02
so3
HC1
co2
HjO
°2
N2
Coke
Volatiles
H2S
Total
Fly Ash
400 MW,

#Mol/hr
#Mbl/hr
#tol/hr
#Mol/hr
#Mol/hr
#Mbl/hr
#Mol/hr
#Mol/hr
#Mbl/hr
#Mol/hr
#/hr
3.07. Sulfur
2
224
25
3
15500
9800
4200
87800


117600
119.7
in Coal.
Stream No.

4 5
11
2
0
272 15800
37 9800
4200
1296 89100


1605 118900
6.0
Process Gas Input
Air . #Mol/hr
Water
Steam
Temp.,°F
Flow, M SCFM
#Mol/hr
#Mol/hr




"850
742


850-1120 850
10.1 751
.. ,-• • •
6 10 11 12 13



494 494 240
494 240


30 30 30
254
524 1018 764

1674
162
332
60 850 850 850 850
10.6 3.3 3.1 6.4 4.8

-------
UJ


H
     I
     1

     i
     I
MATERIAL BALANCE
Case No. 4.
Melt Components
M.S
M^
M2S04
MjiCOo
KC1, Dissolved
Total
Solids
KC1
Fly Ash
400 MW, 3.0% Sulfur in Coal.
Coke Rate, 11400 Ib/hr
Stream No.


#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
Coke Residue #/hr
Total #/hr
Temp.,°F
Nominal
Flow rate, gpm
Heat Exchanger
E-l:
E-2:
E-4:
E-5:
Duties,
23.7
9.0
5.0
7.5
14
0
387
134
1245
65
1831
410.9
230.7
9.0
650.6
850
183
MM Btu/hr

15
5
174
82
622
32
915
205.4
115.4
4.5
325.3
850
92

17
18
174
92
1482
65
1831
205.4
115.4
9.0
329.8
850
183

18
5
173
81
619
32
910
' 2.0
1.2
0.0
3.2
850
91

19
268
0
10
600
32
910
2.0
1.2
441.1
444.3
1500
91

23
266
0
10
596
32
904
0.0
0.0
4.4
4.4
850
90
' ' Includes Stream
Li2C03, 3
Na2C03, 2
K2C03, _3
8

26^
12
0
10
860
32
914
0.0
0.0
4.4
4.4
850
91

31
1.5
0.0
0.0
3.2
0.2
4.9
1.8
1.6
435.2
438.6
850


32
0.0
1.2
0.6
3.7
0.2
5.7
196.3
112.6
4.4
313.3
850

30, #Mol/hr
.0
.2
.1
.3

-------
                                                        MATERIAL BALANCE
to
I
to
o
Case No. 5.
Process Gas
so2
S03
HCl
C02
H20
°2
N2
Coke
Volatiles
H2S
Total
^ Fiy Ash
400 MM,

#Mal/hr
#Mol/hr
#Mal/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
1.0% Sulfur in Coal.
Stream No.

245
71 4
8 0
3 0
17000 90 17000
3800 12 3800
4000 4000
89500 432 90000


114400 534 114800
119.0 6.0
Process Gas Input
Air #*fcl/hr
Water
Steam
Temp.°F
Flow, M SCFM
#Mol/hr
#Mol/hr



850 850-1120 850
722 3.4 725

6 , 10 11 12 13



163 164 80
164 80


10 10 10
81
173 338 251

558
54
110
60 850 850 850 850
3.5 1.1 1.0 2.2 1.6

-------
                                                          MATERIAL BALANCE
10

10

   1
Case No. 5.
Melt Components
M^S
M2S03
M2S04
M2C03
KCl, Dissolved
Total
Solids
KCl
Fly Ash
Coke Residue
Total
Temp.,°F
Nominal
Flow rate, gpm
400 MW, 1
Coke Rate

#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
#/hr
#/hr
.0% Sulfur in Coal.
, 3800 Ib/hr
Stream No.

14
0
129
41
408
22
600
410.9
230.7
3.0
644.6
850
60

15
2
58
24
204
11
299
205.4
115.4
1.5
322.3
850
30

17
6
58
28
488
22
602
205.4
115.4
3.0
323.8
850
60

18
2
57
24
200
11
294
2.0
1.2
0.0
3.2
850
29

19
86
0
4
193
11
294
2.0
1,2
147.0
150.2
1500
29

23
85
0
4
193
11
293
0.0
0.0
1.5
1.5
850
29

26 (1
4
0
4
284
11
303
0.0
0.0
1.5
1.5
930
30

) 31
0.5
0.0
0.0
1.1
0.0
1.6
2.0
1.2
145.6
148.8
850
—

32
0.0
1.2
0.6
3.7
0.2
5.7
293 .4
114.2
1.5
319.1
850
•»
Heat Exchanger Duties, MM Btu/hr

        E-l:  7.6
        E-2:  3.0
        E-4:  1.6
        E-5:  2.4
^l^ Includes Stream 30, #Mol/hr

       Li2C03>  2.1

       Na2C03>  1.5
               2.6
               6.2

-------
                                                         MATERIAL BALANCE
CO
l
to
to
Case No

Process Gas
S02
S03
HC1
C02
H2°
°2
N2
.6. 400 MW,


#Mol/hr
#Mol/hr
#Mol/hr
- #Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
Coke #Mol/hr
Volatiles
H2S
Total
Fly Ash
Process Gas
Air
Water
Steam
Temp.°F
Flow, M
#Mol/hr
#Mol/hr
#/br
Input
#Mol/hr
#Mol/hr
#Mol/hr

SCFM
6.0% Sulfur in Coal.
Stream No.

2 4 5 6 10
448 22
50 2
3 0
14200 543 14800 987
10800 74 10800
3600 3600
81000 2591 83600
60

110100 3208 112800 1047
119.0 6.0

3349


850 850-1120 . 850 60 850
696 20.2 0.7 21.2 6.6


11 12 13



987 480
987 480


60 60
507
2034 1527



324
663
850 850 850
6.2 12.8 9.6

-------
                                                          MATERIAL BALANCE
                          Case No. 6, 400 MW,  6.0% Sulfur  in Coal.
                                      Coke Rate,  22800  Ib/hr
CO
l
to
CO
   I
   1
   1
                                                                Stream No.

Melt Components
^s
MrtSOo
MoSCv
Mo C O-i
KCl, Dissolved
Total
Solids
KCl
Fly Ash

#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
Coke Residue #/hr
Total #/hr
Temp.,°F
Nominal
Flow rate, gpm
Heat Exchanger
E-l:
E-2:
E-4:
Duties,
47.1
18.0
10.0
is.n
14
0
774
262
2472
128
3636
410.9
230.7
18.0
659.6
850
364
MM Btu/hr
15
10
348
158
1236
64
1816
205.4
115.4
9.0
329.8
850
182
17
36
348
178
2946
128
3636
205.4
115.4
18.0
338.8
850
364
18
10
347
157
1232
64
1810
2.0
1.2
0.1
3.3
850
181
19
533
0
21
1192
64
1810
2.0
1.2
882.1
885.3
1500
181
23
530
0
21
1185
64
1800
0
0
8.8
8.8
850
180
26 C
27
0
21
1711
64
1823
0
0
8.8
8.8
930
182
'*' Includes Stream 30,
Li2C03, 4.4
Na2C03 , 3.2
K2C03 T 4.0
L> 31
3.1
0.0
0.1
6.4
0.4
10.0
2.0
1.2
873.3
876.5
850
_
#Mol/hr
32
0.0
1.2
0.6
3.8
0.2
5.8
203.4
114.2
8.8
326.4
850
—

11.6

-------
                                                         MATERIAL BALANCE
U)
to
Case No. 7.

Process Gas
so2
S03
HC1
C02
H20
°2
N2
Coke
Volatiles
^2S
Total
Fly Ash
1000 MW,


#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
3.0% Sulfur in Coal.
Stream

2 4
560
63
7
38800 679
24400 92
10500
219500 3239


293800 4010
299.2

No.

5
28
4
0
39500
24500
10400
222800


297200
15.0
- .

6 10 11 12 13



1234 1234 600
1234 600


75 75 75
634
1309 2543 1909

Process Gas Input
Air
Water
Steam
Temp.,°F
Flow, M SCFM
#«bl/hr
#Mol/hr
#Mol/hr





850 850-1120
1855 25.3



850
1878
4186
405
829
60 850 850 850 850
26.4 8.3 7.8 16.1 12,1

-------
                                                          MATERIAL BALANCE


                           Case No.  7.   1000 MW,  3.0% Sulfur in Coal.
                                        Coke Rate,  28400 Ifc/hr


                                                                Stream No.
CO

to
en
   I
   i
   i
Melt Components
M,,S
M2S03
Maso4
M2C03
KC1, Dissolved
Total
Solids
KC1
Fly Ash

#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
Coke Residue #/hr
Total #/hr
Temp.,°F
Nominal
Flow rate, gpm
Heat Exchanger
E-l:
E-2:
E-4:
E-5:
Duties,
59.2
22.4
12.5
18.8
14
0
968
335
3112
162
4577
1027.2
576.8
22.5
1626.5
850
458
MM Btu/hr

15
12
435
204
1556
81
2288
513.6
288.4
11.2
813.2
850
229
17
45
435
230
3706
161
4577
513.6
288.4
22.5
824.5
850
458
18
12
432
202
1549
80
2275
5.1
2.9
0.1
8.1
850
228
19
671
0
26
1498
80
2275
5.1
2.9
1102*8
1110.8
1500
228
23
666
0
26
1490
80
2262
0
0
11.0
11.0
850
226
26U) 31
31
0
26
2150
80
2287
0
0
11.0
11,0
850
229
(1) Includes Stream 30,




Li2C03,
• >
K«CO,
11.0
8.0
19.9
3.9
0
0.1
8.0
0.5
12f.5
4.5
3.. 9
1089.4
1097.8
850

#Mol/hr

32
0.1
2.9
1.4
9.2
0.5
14.1
490.8
281.4
11.0
783.2
850



28.9

-------
                                                         MATERIAL BALANCE
oo
I
to
Case No. 8.

Process Gas
so2
so3
HC1
C02
H2°
°2
N2
Coke
Volatiles
H2S
Total
Fly Ash
1000 MW,


#Mol/hr
#Mol/hr
#M3l/hr
#Mol/hr
#Mbl/hr
#Mol/hr
#Mbl/hr
#Mbl/hr
#Mol/hr
#Mol/hr
#/hr
1.0% Sulfur in Coal.
Stream

2 4
177
20
7
42400 226
9400 31
9900
223900 1080


285800 1337
297.5

No.

5 6 10
9
1
0
42600 . 408
9400
9900
225000
25

286900 433
14.9


11 12 13

-

411 200
411 200


.25 25
202
847 627

Process Gas Input
Air
Water
Steam
Temp.,°F
Flow, M SCFM
#M3l/hr
#Mol/hr
#Mbl/hr





850 850-1120
1805 8.5
1395


850 60 850
1812 8.8 2.8

135
276
850 850 850
2.6 5.4 4.0

-------
                                                          MATERIAL BALANCE
                           Case No.  8.
1000 MW, 1.0% Sulfur in Coal.

Coke Rate, 9500 Ib/hr
                                                                Stream No.
u>
i
to
   I
   i
   i
Melt Components
M.S
M2S03
M2S04
M2C03
KCl , Dissolved
Total
Solids
KCl
Fly Ash
Coke Residue
Total
Temp.,°F
Nominal
Flow rate, gpm
Heat Exchanger
E-l: 19

#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
#/hr
#/hr

Duties,
.1
14
0
322
102
1019
55
1498
1027.2
576.8
7.5
1611.5
850

150
MM Btu/hr

15
4
145
60
511
28
748
513.6
288.4
3.8
805.8
850

75
17
15
145
69
1220
55
1504
513.6
288.4
7.5
809.5
850

150
18
4
142
60
501
28
735
5.1
2.9
0.1
8.1
850

74
19
215
0
9
483
28
735
5.1
2.9
367.6
375.6
1500

73
23
212
0
9
482
28
731
0
0
3.8
3.8
850

73
^ * Includes Stream




E-2: 7.5
E-4: 4.0
E-5: 6
.0





Li CO- , 5
Na CO- 3
£ J 9
K2C03 , 6
15
26<:
10
0
9
710
28
757
0
0
3.8
3.8
930

76
30,
.2
.8
.4
.4
L) 31
1.2
0
0
2.8
0.1
4.1
5.1
2.9
363.9
371.9
850


#Mol/hr



32
0.1
2.9
1.4
9.2
0.5
14.1
508.5
285.5
3.8
797.8
850







-------
                                                         MATERIAL BALANCE
U)
l
to
CD
Case No. 9.
Process Gas
S02
so3
HC1
co2
H20
°2
N2
Coke
Volatiles
H2S
Total
Fly Ash
1000 MW,

#Mbl/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mal/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mbl/hr
#Mbl/hr
#/hr
6.0% Sulfur in Coal.
Stream No.

2 45
1120 56
124 6
7 1
35600 1358 37000
26900 185 27100
9000 9000
202508 6478 209000


275300 8021 282200
297.5 14.9
Process Gas Input
Air #Mol/hr
Water
Steam
Temp.°F
Flow, M SCFM
yjtMol/hr
#Mol/hr




850 850-1120 850
1740 50.6 1.8

6 10 11 12 13



2468 2468 1200
2468 1200


150 150 150
1268
2618 5086 3818

8372
810
1658
60 850 850 850 850
52.9 16.6 15.6 32.1 24.1

-------
                                                           MATERIAL BALANCE
                           Case No.  9.
1000 MW, '6.0% Sulfur in Coal.
Coke Rate, 56900 Ib/hr
                                                                 Stream No.
CO
I

   1
   I

Melt Components
y^s
M2S03
M2SO^
M2C03
KC1, Dissolved
Total
Solids
KC1
Fly Ash
Coke Residue
Total
Temp.,°F
Nominal

#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
#/hr
#/hr
Flow rate,, gpm
Heat Exchanger
E-l:
E-2:
E-4:
E-5:

Duties,
7.6
45.0
25.0
37.5

14
0
1934
655
6180
320
9089
1027.2
576.8
45.0
1649.0
850

909
MM Btu/hr



15
24
870
394
3090
160
4538
513.6
288.4
22.5
824.5
850

454
17
90
870
446
7368
320
9094
513.6
288.4
45.0
847.0
850

909
18
24
868
392
3080
160
4524
5.1
2.9
0.2
8.2
850

452
19
1332
0
52
2979
160
4523
5.1
2.9
2205.2
2213.2
1500

452
23
1325
0
52
2962
159
4498
0
0
22.0
22.0
850

450
26(D
66
0
52
4278
159
4555
0
0
22.0
22.0
930

456
31
7.8
0.0
0.2
16.0
1.0
25.0
5.1
2.9
2183.2
2191.2
850

-
32
0.1
3.0
1.4
9.5
0.5
14.5
508.5
285.5
22.2
816.2
850

-
C1) Includes Stream 30, #Mol/hr


, . - , -









Li2C03 ,
K-jCOo,

11.0
8.0
9.9
28.9







-------
                                                        MATERIAL BALANCE
U)
o
Case No. 10

Process Gas
S02
so3
HC1
co2
H20
°2
N2
Coke
Volatiles
l^S
Total
Fly Ash
. Copper Smelter, Reverberatory Furnace - 200 T/D Copper
Stream No.

24 5 6 10
#Mbl/hr 117 6
#Mol/hr 13 1
#Mol/hr
#Mol/hr 1100 142 1200 258
#Mol/hr 300 19 300
#Mol/hr 300 300
#Mol/hr 5200 677 5900
#Mol/hr 16
#Mol/hr
#Mol/hr 7000 838 7700 274
#/hr 10.0 0.5


11 12 13



258 126
258 126


16 16
132
532 400

Process Gas Input
Air
Water
Steam
Temp.,°F
Flow. M SCFM
#Mol/hr 913
#Mol/hr
#Mol/hr
850 850-1120 850 60 850
44.2 5.3 48.7 5.8 1.7

85
174
850 850 850
1.6 3.4 2.5

-------
                                                                MATERIAL BALANCE
CO
         I
         I
         ft)
         I
Case No. 10. Copper Smelter, Reverberatory Furnace - 200 T/D Copper.
Coke Rate, 5900 Ib/hr.
Stream No.

Melt Components
MsS
MoSO^
Mo SO/,
M2C03
KCl, Dissolved
Total
Solids
KCl
Fly Ash
Coke Residue
Total
Temp. ,°F
Nominal
Flow rate, gpm
Heat Exchanger
E-l:
E-2:
E-4:
E-5:


#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#Mol/hr
#/hr
#/hr
#/hr
#/hr

Duties, MM
11.0
4.7
2.6
3.9

14 15
0 2
202 91
68 41
573 287

843 421


19.0 9.5
4.6 2.3
23.6 11.8
850 850

84 42
Btu/hr

17
9
91
46
697

843


9.5
4.6
14.1
850

84

18
2
91
41
287

421


0.1
0.0
0.1
850

42

19
139
0
5
277

421
,

0.1
230.4
230.5
1500

42

23
138
0
5
275

418


0.0
2.3
2.3
850

42
^ ' Includes Stream
Li2C03,
K2C03,

26^' 31
7 0.8
0 0.0
5 0.0
410 1.7

422 2.5


0.0 0.1
2.3 228.1
2.3 228.2
930 850

42
30, #Mol/hr
0.8
0.6
0.4
1.8

32
0.0
0.0
0.0
0.1

0.1


9.4
2.3
11.7
850

-


-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
4.  PLANT CAPITAL AND OPERATING COST ESTIMATES

    a.  Base Case  (800 MW - 3% S in Coal)

        1)  Capital Cost Estimate

            The construction cost estimate for the base case
plant is based on the following:

            a)  The engineering flow diagrams - PS-218-0002,
-0003 and -0004.

            b)  The equipment arrangement drawings - PS-218-0501,
-0502 and -0503.

            c)  No design or engineering development work is
included.  It is presumed that the technology is known and the
engineering costs are those required to implement the design
of this known technology.

            d)  A soil bearing load of 3000 psf.

            e)  A relatively level and clear site requiring a
minimum amount of clearing and grubbing.

            f)  Steam will be provided from a Glaus Plant or
the power plant.

            g)  Sufficient quantities of adequately treated
water are available.

            h)  The estimated cost for construction labor is
based on an average wage rate of $6.00 per hour.  No premium
time is anticipated, nor are travel or time expenses for con-
struction labor.

            i)  The railroad spur and land acquisition costs are
not included.

            j)  Spare parts, tools and a shop are excluded.

            k)  A conventional industrial plant electrical  sys-
tem with a feeder from the power plant installed by others.  The
electrical work starts at a 13.8 KV switching station.

                                                  SINGMASTER S BREYER

                              4-1

-------
             1)   Electrical heat tracing of process high tempera-
 ture lines.

         The  summary of the Construction Cost Estimate is attached
 to  this  section of the report,   The Construction Cost Estimate
 Detail Sheets  for  the  base case plant are appended.

         Table  4-1A lists  the  Total Estimated Capital Requirement
 for the  base case  plant and excludes any credit for reduction in
 height of  the  power plant stack or reduction in cost of the boiler
 for reducing corrosion.   Furthermore, it does not include the cost
 of  a Claus Plant to recover elemental sulfur.

         The  capital requirements are based on the following:

             1.   A  penalty for providing a high temperature elec-
 trostaticr  precipitator including the penalty for larger insulated
 ductwork.

             2.   The Construction Cost Estimate.

             3.   The inventory of melt in the process.

             4.  A  contingency of 20%.

             5.   Interest  during  construction of 2.3% of the total
plant cost.
                                                     i
             6.  Working capital  of 6.5% of the fixed capital cost.

        2)    Operating  Cost Estimate

             The operating cost estimate for the base case plant is
summarized in Table 4-lB.  It is based on the following:

             Plant Factor - 70%.
                                    4-2

-------
Raw Material Costs  (Delivered)




  Delayed Petroleum Coke  -  $ll/Ton




  Lithium Carbonate       -  42C/#




  Sodium Carbonate        -  2.8£/#




  Potassium Carbonate     -  9.6
-------
              Plant Overhead
Payroll Burdens           -  18.5% of direct labor

                             and supervision.


                             50% of direct labor,

                             maintenance and plant

                             supplies.
Fixed Cost
(Capitalization Charge)    -  14% of the estimated

                             capital requirement to

                             cover depreciation,

                             taxes and insurance.
        The  operating  cost  estimate excludes credits for by-
product sulfur, heat recovery  and  savings in coal costs for using
3%  sulfur  in coal  rather  than  a  lower sulfur coal.
    b.  Alternate Cases

        The construction cost estimates for the alternate cases
were developed from the base case plant estimates.  The exception
is that in the Copper Smelter Reverberatory Furnace Case  (Case 10)
reheat of an existing 600°F electrostatic precipitator off-gas
was considered rather than installing a new electrostatic pre-
cipitator.  The construction cost summaries for the alternate
cases are attached to this section of the report.

        The capital requirements and operating cost estimates for
the alternate cases were derived from the same unit costs or fac-
tors used in the base case plant except for a 90% plant factor
used in the Copper Smelter Case.  The same exclusions apply to
the alternate cases as the base case.
                                4-4

-------
        The estimated capital requirements for Cases 2 through
10 are listed in Tables 4-2A through 4-10A.  The operating cost
estimate for these alternate cases are listed in Tables 4-2B
through 4-10B; and for each case are located immediately after
its associated estimated capital requirement.

        For comparative purposes, the total estimated capital
requirements and operating cost estimate for each of the power
plant cases are summarized in Table 4-11.
                                -, .                  SINGMASTER & BREYER

                                4-5

-------
            Table 4-lA.   Estimated Capital Requirements

                           Case:  1  (Base)

 Plant:   800 MW - 3% Sulfur in Coal                           .
                                                    Cost  ($10J)

 Electrostatic Precipitator Penalty:                    1,850

 Construction Cost Estimate
   (From Summary Sheet)                                 8,338

   Total Construction Cost                             10,188

 Melt Inventory in Process                                 98

   Subtotal                                            10,286

 Contingency                                           2,057

   Total Plant Cost                                   12,343

 Interest During Construction (2.3% of
   Total Plant Cost)                                      284

   Fixed Capital Cost                                 12,627

Working Capital (6.5% of Fixed
   Capital Cost)                                          821

Estimated Capital Requirements                        13,448

                              $/KW  =                  16.81

     The following are excluded:

      (1)  The  total installed cost of the electrostatic precip-
itator.  Includes only the differential cost for using a 99.5%
efficient high temperature electrostatic precipitator instead
of a 99% efficient low temperature electrostatic precipitator.

      (2)  The  cost of a Glaus Plant for recovery of elemental
sulfur.

      (3)  The  credits for reducing power plant stack height
and reducing corrosion at the low temperature portion of the
boiler.
                           4-6

-------
         Table 4-lB.  Estimated Annual Operating Costs

                        Case:  1  (Base)

Plant:  800 MW - 3% Sulfur in Coal

A.  Direct Costs:
                                                     (Cost $103)
    1)  Materials:

          Coke                                           766
          Carbonate                                      929

    2)  Direct Labor  ($3.50/hr)  4/shift                 123

    3)  Supervision   ($9,000/yr) I/shift                  36

    4)  Maintenance  (3% of fixed capital)                379

    5)  Plant Supplies (15% of maintenance)               57
           \
    6)  Utilities                                        220

             Total Direct Cost                         2,510

B.  Indirect Costs;

    1)  Payroll Burdens                                   30
           (18.5% of direct labor & supervision)

    2)  Plant Overhead                                   280
           (50% of direct labor, maintenance
           and plant  supplies)

             Total indirect Cost                         310


C.  Fixed Costs;

    (14% of estimated capital requirement  to
     cover depreciation, taxes and insurances)         1,883

             Total Annual Operating Cost^            4,703

                                 Mills/KWH              0.95

    (1) Excludes credits for byproduct  sulfur, heat
        recovery and  lower cost of high sulfur coal.

                                                  SINGMASTER & BREYER

                               4-7

-------
         Table 4-2A.   Estimated Capital Requirements

                          Case:  2

 Plant:   800 MW - 1% Sulfur  in  Coal
                                                Cost  ($103)

 Electrostatic Precipitator  Penalty:                   830

 Construction Cost Estimate
    (From Summary Sheet)                            6,236

    Total Construction Cost                         7,066

 Melt  Inventory in Process                            33

    Subtotal                                       7,099

 Contingency                                       1,420

    Total Plant Cost    .                            8,519

 Interest During Construction  (2.3% of
    Total Plant Cost)                                  196

    Fixed Capital Cost                             8,715

Working  Capital (6.5% of  Fixed Capital Cost)          566

 Estimated Capital Requirements                    9,281

                               $/KW  =             11.60

     The following are excluded:

      (1)  The  total  installed  cost of the electrostatic pre-
 cipitator.   Includes  only the  differential cost for using a
 99.5% efficient high  temperature electrostatic precipitator
 instead  of  a  99% efficient  low temperature electrostatic
precipitator.

      (2)  The  cost of a Glaus  Plant for recovery of elemental
 sulfur.

      (3)  The  credits for reducing power plant stack height
and reducing corrosion at the  low temperature portion of the
boiler.
                             4-8

-------
      Table 4-2B.  Estimated Annual Operating Costs

                         Case:  2

Plant:.  800 MW - 1% Sulfur in Coal

A.  Direct Cost
    1)  Materials
                                                 Cost  ($103)
           Coke                                      255
           Carbonate                                 721

    2)  Direct Labor  ($3.50/hr)                      123

    3)  Supervision   ($9,000/yr)                      36

    4)  Maintenance   (3% of fixed capital)           261

    5)  Plant Supplies  (15% of maintenance)           39

    6)  Utilities                                    151

                     Total Direct Cost             1,586

B.  Indirect Cost

    1)  Payroll Burdens                               30
           (18.5% of direct labor
            and supervision)

    2)  Plant Overhead                               212
           (50% of direct labor, maintenance
            and plant supplies)

                     Total Indirect Cost             242

C.  Fixed Cost

    (14% of estimated capital requirement to
     cover depreciation, taxes and insurances)     1,299

                Total Annual Operating Cost^     3,129

                          Mills/KWH                 0.63

(1)   Excludes credits for byproduct sulfur and heat
     recovery.


                                                SINGMASTER S BREYER

                            4-9

-------
       Table  4^3A.   Estimated Capital Requirements

                       Case:   3

 Plant:   800  MW - 6% Sulfur  in  Coal
                                                 Cost  ($103)

 Electrostatic  Precipitator  Penalty                  1,972

 Construction Cost Estimate  (From Summary Sheet)    10,028

    Total Construction Cost                       12,000

 Melt  Inventory in Process                             196

    Subtotal                                      12,196

 Contingency                                         2,439

    Total Plant Cost                               14,635

 Interest During Construction (2.3% of Total
                               Plant Cost)             337

    Fixed Capital Cost                             14,972

Working Capital (6.5% of Fixed Capital Cost)          973

Estimated Capital Requirements                     15,945

                               $/KW  =               19.93

    The following are excluded:

    (1)  The total  installed cost of the electrostatic
precipitator.   Includes only the differential cost for
using a 99.5%  efficient high temperature electrostatic
precipitator instead of a 99%  efficient low temperature
electrostatic  precipitator.

    (2)  The cost of a Claus Plant for recovery of elemen-
tal sulfur.

    (3)  The credits for reducing power plant stack height
and reducing corrosion at the  low temperature portion of
the boiler.
                         4-10

-------
       Table 4-3B.  Estimated Annual Operating Costs

                          Case:  3

Plant:  800 MW - 6% Sulfur in Coal

A.  Direct Cost
                                                 Cost ($103)
    1)  Materials

          Coke                                      1,532
          Carbonate                                 1,241

    2)  Direct Labor  ($3.50/hr) 4/shift               123

    3)  Supervision   ($9,000/yr) I/shift               36

    4)  Maintenance (3% of fixed capital)             449

    5)  Plant Supplies (15% of maintenance)            67

    6)  Utilities                                     324

                Total Direct Cost                   3,772

B.  Indirect Cost

    1)  Payroll Burdens                                30
          (18.5% of direct labor
           and supervision)

    2)  Plant Overhead                                320
          (50% of direct labor, maintenance
           and plant  supplies)

                Total Indirect Cost                   350

C.  Fixed Cost

    (14% of estimated capital requirement           2,232
     to cover depreciation, taxes and insurances)

                Total Annual Operating Cost^  '      6,354

                          Mills/KWH                   1.28

    (1)  Excludes credits for byproduct  sulfur, heat
recovery and lower cost of high sulfur coal.


                                                SINGMASTER & BREYER
                            4-11

-------
        Table, 4-4A.   Estimated Capital Requirements

                         Case:  4

 Plant:   400 MW - 3% Sulfur  in Coal
                                                   Cost  ($103)

 Electrostatic Precipitator  Penalty                    1,000

 Construction Cost Estimate  (From Summary Sheet)       5, 320

     Total  Construction Cost                          6,320

 Melt Inventory in Process                                49

    , Subtotal                                         6,369

 Contingency           .                          :     1^274

     Total  Plant Cost                                 7,643

 Interest During Construction  (2.3% of Total
                              Plant Cost)                176

     Fixed  Capital Cost                                7,819

 Working Capital (6.5% of Fixed Capital Cost)             508

 Estimated  Capital Requirements                        8,327

                              $/KW  =                 20.82

     The following are excluded:

     (1)  The total installed cost of the electrostatic pre-
 cipitator.   Includes only the differential cost for using a
 99.5% efficient high temperature electrostatic precipitator
 instead of a 99%  efficient  low temperature electrostatic
precipitator.

     (2)  The costof a Glaus Plant for recovery of elemental
 sulfur.

     (3)  The credits for reducing power plant stack height
and reducing corrosion at the low temperature portion of
the boiler.
                          4-12

-------
       Table 4-4B.  Estimated Annual Operating Costs

                          Case:  4

Plant:  400 MW - 3% Sulfur in Coal


A.  Direct Cost
                                                 Cost  ($103)
    1)  Materials

          Coke                                       383
          Carbonate                                  465

    2)  Direct Labor  ($3.50/hr) 4/ shift              123

    3)  Supervision   ($9,000/yr) I/shift               36

    4)  Maintenance   (3% of fixed capital)           234

    5)  Plant Supplies  (15% of maintenance)            35

    6)  Utilities                                    110

                 Total Direct Cost                 1,386

B.  Indirect Cost

    1)  Payroll Burdens                                30
          (18.5% of direct labor
           and supervision)

    2)  Plant Overhead                               196
          (50% of direct labor, maintenance
           and plant  supplies)

                 Total indirect Cost                 226

C.  Fixed Cost

    (14% of estimated capital requirement to
     cover depreciation, taxes and insurances)     -A
                 Total Annual Operating Cost^    2,778
                           Mills/KWH                1.12

    (1) Excludes credits for byproduct sulfur, heat
recovery and lower cost of high sulfur coal.


                                                  SINGMASTER S BREYER
                             4-13

-------
       Table 4-5A.  Estimated Capital Requirements

                        Case:  5

Plant:  400 MW - 1% Sulfur in Coal
                                                 Cost ($103)

Electrostatic Precipitator Penalty                    420

Construction Cost Estimate (From Summary Sheet)     4,184

    Total Construction Cost                         4,604

Melt Inventory in Process                              16

    Subtotal                                        4,620

Contingency                                           924

    Total Plant Cost                                5,544

Interest During Construction (2.3% of Total
                              Plant Cost)             128

    Fixed Capital Cost                              5,672

Working Capital (6.5% of Fixed Capital Cost)          369

Estimated Capital Requirements                      6,041

                              $/KW  =               15.10

    The following are excluded:

    (1)  The total installed cost of the electrostatic pre-
cipitator.  Includes only the differential cost for using a
99.5% efficient high temperature electrostatic precipitator
instead of a 99% efficient low temperature electrostatic
precipitator.

    (2)  The cost of a Glaus Plant for recovery of elemental
sulfur.

    (3)  The credits for reducing power plant stack height
and reducing corrosion at the low temperature portion of
the boiler.
                          4-14

-------
       Table 4-5B.  Estimated Annual Operating Costs

                          Case:  5

Plant:  400 MW - 1% Sulfur in Coal

A.  Direct Cost
                                                  Cost  ($103)

    1)  Materials
          Coke                                        127

          Carbonate                                   361

    2)  Direct Labor  ($3.50/hr) 4/shift               123

    3)  Supervision  ($9,000/yr) I/shift                 36

    4)  Maintenance  (3% of fixed capital)             170

    5)  Plant Supplies  (15% of maintenance)             26

    6)  Utilities                                       76

                  Total Direct Cost                   919

B.  Indirect Cost

    1)  Payroll Burdens                                 30
          (18.5% of direct labor
           and supervision)

    2)  Plant Overhead                                160
           (50% of direct labor, maintenance
           and  plant supplies)

                  Total Indirect Cost                 190

C.  Fixed Cost                                        846
       (14% of estimated capital requirement to
       cover depreciation, taxes and insurances)

                  Total Annual Operating Cost^1'    1,955

                            Mills/KWH                0.79

    (1) Excludes credits for byproduct sulfur and heat
recovery premium.


                                                 SINGMASTER & BREYER

                             4-15

-------
        Table 4-6A.   Estimated Capital Requirements

                        Case:  6

 Plant:   400  MW -  6% Sulfur  in Coal
                                                 Cost  ($103)

 Electrostatic Precipitator  Penalty                  1,060

 Construction Cost Estimate  (From Summary Sheet)     6,383

    Total Construction Cost                        7,443

 Melt  Inventory in Process                              98

    Subtotal                                       7,541

 Contingency                                         1,508

    Total Plant Cost                               9,049

 Interest During Construction (2.3% of Total
                              Plant Cost)             208

    Fixed Capital Cost                              9,257

 Working  Capital (6.5% of Fixed Capital Cost)          602

 Estimated Capital Requirements                      9,859

                              $/KW  =               24.65

    The  following are excluded:

    (1)  The  total  installed cost of the electrostatic pre-
 cipitator.   Includes only the differential cost for using a
 99.5% efficient high temperature electrostatic precipitator
 instead  of a  99%  efficient  low temperature electrostatic
 precipitator.

    (2)  The  cost of a Glaus Plant for recovery of elemental
 sulfur.

    (3)  The  credits for reducing power plant stack height
 and reducing  corrosion at the low temperature portion of the
boiler.
                          4-16

-------
      Table 4-6B.  Estimated Annual Operating Costs

                       Case:  6

Plant:  400 MW - 6% Sulfur in Coal

A.  Direct Cost
                                                 Cost  ($103)

    1)  Materials
          Coke                                       766

          Carbonate                                  621

    2)  Direct Labor  ($3.50/hr) 4/shift              123

    3)  Supervision ($9,000/yr) I/shift                36

    4)  Maintenance (3% of fixed capital)            278

    5)  Plant Supplies (15% of maintenance)            42

    6)  Utilities                                    162

                  Total Direct Cost                2,028

B.  Indirect Cost

    1)  Payroll Burdens                                30
           (18.5% of direct labor and
           supervision)

    2)  Plant Overhead                               222
           (50% of direct labor, maintenance
           and plant  supplies)

                  Total Indirect Cost                252

C.  Fixed Cost                                     1,380
      (14% of estimated capital requirement to
       cover depreciation, taxes and insurances)

                  Total Annual Operating Cost'-1-'   3,660

                            Mills/KWH               1.48

    (1)   Excludes credits for byproduct sulfur, heat
recovery and lower cost of high sulfur coal.


                                                SINGMASTER S BREYER

                            4-17

-------
         Table  4-7A.   Estimated Capital Requirements

                          Case:   7

 Plant:   1000 MW -  3% Sulfur  in Coal
                                                   Cost  ($103)

 Electrostatic Precipitator Penalty                   2,130

 Construction Cost  Estimate  (From  Summary Sheet)     10,425

    Total Construction Cost                         12,555

 Melt  Inventory  in  Process                              123

    Subtotal                                        12,678

 Contingency                                          2,536

    Total Plant Cost                                15,214

 Interest During Construction  (2.3% of Total
                              Plant Cost)              350

    Fixed Capital  Cost                             15,564

Working Capital (6.5%  of Fixed Capital Cost)         1,012

 Estimated Capital  Requirements                      16,576

                              $/KW  =                16.58

    The following  are  excluded:

    (1)  The total installed cost of the electrostatic pre-
 cipitator.  Includes only the differential cost for using a
 99.5% efficient high temperature  electrostatic precipitator
 instead of a 99% efficient low temperature electrostatic
precipitator.

    (2)  The cost  of a Glaus Plant for recovery of elemental
 sulfur.

    (3)  The credits for reducing power plant stack height
and reducing corrosion at the low temperature portion of the
boiler.
                            4-18

-------
      Table 4-7B.  Estimated Annual Operating Costs

                       Case:  7

Plant:  1000 MW - 3% Sulfur in Coal

A.  Direct Cost
                                                  Cost  ($103)

    1)  Materials
          Coke                                        959

          Carbonate                                 1,161

    2)  Direct Labor  ($3.50/hr) 4/shift               123

    3)  Supervision  ($9,000/yr) I/shift                 36

    4)  Maintenance  (3% of fixed capital)             467

    5)  Plant Supplies  (15% of maintenance)             70

    6)  Utilities                                     275

                 Total Direct Cost                  3,091

B.  Indirect Cost

    1)  Payroll Burdens                                 30
          (18.5% of direct labor
           and supervision)

    2)  Plant Overhead                                330
          (50% of direct labor, maintenance
           and plant supplies)

                 Total Indirect Cost                  360

C.  Fixed Cost                                      2,321
        (14% of estimated capital requirement to
         cover depreciation, taxes and insurances)

                 Total Annual Operating Cost^     5,772

                           Mills/KWH                 0.93

    (1)  Excludes credits for byproduct sulfur, heat
recovery and lower cost of high sulfur coal.
                                                 SINGMASTER & BREYER

                             4-19

-------
       Table 4-8A.   Estimated Capital Requirements

                        Case:   8

 Plant:  1000 MW -  1% Sulfur in Coal
                                                Cost  ($103)

 Electrostatic Precipitator Penalty                    870

 Construction Cost  Estimate  (From Summary Sheet)    7,633

     Total Construction  Cost                        8,503

 Melt Inventory in  Process                             41

     Subtotal                                      8,544

 Contingency                                       1,709

     Total Plant Cost                             10,253

 Interest During Construction (2,3% of Total
                               Plant Cost)             236

     Fixed Capital  Cost                            10,489

 Working  Capital (6.5% of Fixed Capital Cost)          682

 Estimated Capital  Requirements      .              11,171

                               $/KW  =              11.17

     The  following  are excluded:

     (1)  The  total  installed cost of the electrostatic pre-
 cipitator.   Includes  only the  differential cost for using a
 99.5%  efficient high  temperature electrostatic precipitator
 instead  of  a  99% efficient low temperature electrostatic
 precipitator.

     (2)  The  cost of  a Glaus Plant for recovery of elemental
 sulfur.

     (3)-  The  credits  for reducing power plant stack height
 and  reducing  corrosion at the  low temperature portion of the
boiler.
                          4-20

-------
      Table 4-8B.  Estimated Annual Operating Costs

                       Case:  8

Plant:  1000 MW - 1% Sulfur in Coal

A.  Direct Cost
                                                   Cost  ($103)

    1)  Materials
          Coke                                          319

          Carbonate                                     901

    2)  Direct Labor ($3.50/hr) 4/shift                 123

    3)  Supervision ($9,000/yr) I/shift                  36

    4)  Maintenance (3% of fixed capital)               315

    5)  Plant Supplies (15% of maintenance)              47

    6)  utilities                                       189

                 Total Direct Cost                   , 1,930

B.  Indirect Cost

    1)  Payroll Burdens                                  30
          (18.5% of direct labor and
           supervision)

    2)  Plant Overhead                                  243
          (50% of direct labor, maintenance
           and plant supplies)

                 Total indirect Cost                    273

C.  Fixed Cost                                        1,564
        (14% of estimated capital requirement to
         cover depreciation, taxes and insurances)

                 Total Annual Operating Cost^       3,767

                           Mills/KWH                   0.61

    (1)  Excludes credits for byproduct sulfur and heat
recovery.
                                                  SINGMASTER & BREYER

                              4-21

-------
        Table  4-9A.  Estimated Capital Requirements

                        Case:  9

 Plant:   1000  MW  - 6% Sulfur  in Coal
                                                 Cost  ($103)

 Electrostatic Precipitator Penalty                  2,352

 Construction  Cost Estimate  (From Summary Sheet)    12,648

    Total Construction Cost                        15,000

 Melt  Inventory in Process                             245

    Subtotal                                       15,245

 Contingency                                         3,049

    Total Plant  Cost                               18,294

 Interest During  Construction (2.3% of Total
                              Plant Cost)             431

    Fixed Capital Cost                             18,725

Working Capital  (6.5% of Fixed Capital Cost)        1,217

 Estimated Capital Requirements                     19,942

                              $/KW  =               19.94

    The following are excluded:

    (1)  The  total installed cost of the electrostatic pre-
 cipitator.  Includes only the differential cost for using a
 99.5% efficient high temperature electrostatic precipitator
 instead of a  99% efficient low temperature electrostatic
precipitator.

    (2)  The cost of a Glaus Plant for recovery of elemental
sulfur.

    (3)  The credits for reducing power plant stack height
and reducing corrosion at the low temperature portion of
the boiler.
                          4-22

-------
      Table 4-9B.  Estimated Annual Operating Costs

                       Case:  9
Plant:  1000 MW - 6% Sulfur in Coal

A-  Direct Cost
                                                  Cost  ($103)
    1)  Materials
          Coke                                       1,915

          Carbonate                                  1,551

    2)  Direct Labor  ($3.50Ar) 4/Shift                123

    3)  Supervision  ($9/000/yr) I/Shift                 36

    4)  Maintenance  (3% of fixed capital)              562

    5)  Plant Supplies  (15% of maintenance)             84

    6)  Utilities                                      405

                 Total Direct Cost                   4,676

B,  Indirect Cost

    1)  Payroll Burdens                                 30
          (18.5% of direct labor and
           supervision)

    2)  Plant Overhead                                 385
          (50% of direct labor, maintenance
           and plant  supplies)

                 Total Indirect Cost                   415

C.  Fixed Cost                                       2,792
        (14% of estimated capital requirement to
         cover depreciation, taxes and insurances)

                 Total Annual Operating Cost^1^      7,883

                           Mills/KWH                   1.27

    (1)  Excludes credits for byproduct sulfur, heat recovery
and lower cost of high sulfur coal.



                                                  SINGMASTER & BREYER

                              4-23

-------
       Table 4-10A.  Estimated Capital Requirements

                         Case: 10

Plant:  200 T/D Copper Smelter Reverberatory Furnace
        Equivalent Sulfur in Gases - 50 T/D

                                                 Cost (SIO3)

Reheat System                                        376

Construction Cost Estimate  (From Summary Sheet)    2,297

    Total Construction Cost                        2,673

Melt Inventory in Process                             25

    Subtotal                                       2,698

Contingency                                          540

    Total Plant Cost                               3,238

Interest During Construction (2.3% of Total
                              Plant Cost)             74

    Fixed Capital Cost                             3,312

Working Capital (6.5% of Fixed Capital Cost)         215

Estimated Capital Requirements                     3,527


    The following is excluded:

    (1)   The cost of a Glaus Plant for recovery of
elemental sulfur.
                          4-24

-------
      Table 4-10B.  Estimated Annual Operating Costs

                        Case:  10

Plant:  200 T/D Copper Smelter Reverberatory Furnace
        Equivalent Sulfur in Gases - 50 T/D

A.  Direct Cost; - 90% Plant Factor
                                                   Cost  ($103)

    1)  Materials
            Coke                                       246

            Carbonate                                  118

    2)  Direct Labor  ($3.50/hr) 2/Shift                 62

    3)  Supervision ($9,000/yr) I/Shift                 36

    4)  Maintenance (3% of fixed capital)               99

    5)  Plant Supplies (15% of maintenance)             15

    6)  Utilities                                       50

                 Total Direct Cost                     626

B.  Indirect Cost

    1)  Payroll Burdens                                 18
          (18.5% of direct labor and
           supervision)

    2)  plant Overhead                                  88.
          (50% of direct labor, maintenance
           and plant supplies)

                 Total Indirect Cost                   .106

C.  Fixed Cost                                         494
        (14% of estimated capital requirement to
         cover depreciation, taxes and insurances)

                 Total Annual Operating Cost^      1,226

                           $/Ton of Copper           18.66

    (1)  Excludes credits for byproduct sulfur and heat
recovery.


                                                  SINGMASTER  & BREYER
                              4-25

-------
          Table 4-11.   Comparison of Capital & Operating Cost for SOX Removal from Power Plants
to
                   Power Plant
                            Capital  Requirements
                                                                   (1)
Operating Cost
                                                                              (2)
Case No.
1 (Base)
2
3
4
5
6
7
8
9
MW
800
800
800
400
400
400
1,000
1,000
1,000
Sulfur in Coal
3%
1
6
3
1
6
3
1
6
$x!03
13,448
9,281
15,945
8,327
6,041
9,859
16,576
11,171
19,942
$/KW
16.81
11.60
19.93
20.82
15.10
24.65
16.58
11.17
19.94
$xlo3/Vear
4,703
3,127
6,354
2,778
1,955
3,660
5,772
3,767
7,883
Mills/KWH
0.95
0.63
1.28
1.12
0.79
1.48
0.93
0.61
1.27
       Notes:
(1)   includes  penalty for high temperature electrostatic precipitator.   Excludes
     cost of Glaus Plant and credits for reducing power plant stack height and
     reducing  corrosion in boiler.

(2)   Excludes  credits for byproduct sulfur, heat recovery and lower cost of high
     sulfur coal.

(3)   Mills/produced KWH at 70% Plant Factor.

-------
                           CONSTRUCTION COST ESTIMATE
                            SINGMASTER & BREYER
CUSTOMER    NAPC A
LOCATION
DESCRIPTION   SUMMARY

t

A-I. MOLTEN CARBONATE PROCESS
CASE 1
800 M V/
3% S. IM CoAL
«
PROP. MO.
CONT. NO. PS - 2 1 8
MADE BV J.O-J.
APPROVED
ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800
























900





ITEM & DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense f
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense \
Office Payroll Burdens
Indirect Costs-Office __j
f Engi'neeri'ncf Development Cost Nat Included)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee 5%
Equipment Rental 1 Included In Indirect
Small Tools J F,'elcJ Costs.
Royalty/Know-How
Sales Tax fMoi Included.
SUB-TOTAL
Penalties (Precipttatbr $ Vac^s)
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CENTS OMITTED
LABOR
83000
89700
68000
-
103110
267 430
1 41 500
74230
Z610
S 37 550



70% *L.
10 fc x M.





-

15'/,
















SUB-CONTRACTS
—
-
•"-
65500
1 {?&400(
—
S800
~*
1^1000
Z, 230300


























, »


MATERIALS
—
120300
157000

1.514220
401 100
284 200
477 3ZG
1 (Hy
Z/?55,230





























TOTAL
O 3 (\ ( '
Q w y • ' •'
2100''
22501:
^5(.'0
3,5813.--'..

v 4435^
55 1 5.;,

6,023,0^0








88 \ 820
6,904900






1,035 M
794050*'
397000


'
83375Cf
1 B500CO





            11-16-70   RFVISIOM HO..
      REVISION DATE.
PAGE NO..
                                                                                      £. 134

-------
CUSTOMER
LOCATION
PROJECT A.I
CONSTRUCTION COST ESTIMATE
SINGMASTER & BREYER
NAPCA DESCRIPTION SUMMARY
CASE 2
800 MW
1% S.tn COAL
• MOLTED L?A,R80KUTe PRotFSS

PKOP. NO. .
CONT. NO. .
MADE BY
APPROVED .

PS-218


ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800

























900




ITEM & DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance \
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense
Office Payroll Burdens
Indirect Costs-Office /






















-


(Encji needing Development Cost Not InoludedL)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee £%
Equipment Rental 1 Deluded |f> Indirect
Small Tools J Field Co${
Royalty/Know-How
Sales Tax; jVJot Included
SUB-TOTAL
Penalties (Precipitafor $ Ducts)
Escalation Labor
Material
Contingency Labor
Material
TOTAL













ESTIMATED COST
CtNT* OMITTED
LABOR
63000
67300
54-500
-
66920
Z IB ^0!)
| |q £00
66.SCQ
2470
654550



70'/. x L,








1554












t



SUB- CONTRACTS
—
-
-
£>5"500
1,43*000
—
1800

152800
ly 664 tOO


























•


MATERIALS
—
90300
\tS5QO

975750
310300
22*7 400
42,^ 50$
930
I, 170310
























"




TOTAL
63 OCO
15760^
180 000
65 500
2480 760
' 534 500
3 54 BOD
4
-------
                    CONSTRUCTION COST ESTIMATE
                    SINGMASTER & BREYER
rnsrourR IX A r t M.
LOCATION
PROJPCT A.I. M»i/rtw CARBflVATE P/?OC,
DESCRIPTION O U M M A K T
CASE 3
800 M W
67. S. IN COAL
£S<

mop. NO.
CONT. NO. PS -

APPROVED

215
U,

ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800
























900





ITEM & DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding -
DIRECT FIELD COSTS
Temporary Construction Facilities "*\
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense f
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance j
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense *
Office Payroll Burdens
Indirect Costs-Office )
(Engineering Development Cost Not Included)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee 5%
Equipment Rental 1 InJurf ^ l>) \h(l \ftrf
Small Tools j f^\d CcX*t
Royalty/Know-How
Sales Tax fjp-r; jnclucfecL
SUB-TOTAL
Pen alt /es ( Free ipifa. tor $ Duct*,)
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CIMTS OMITTED
LABOR
WOO
107600
74-800
_
1234(0
320800
H9400
89 100
ZS80
msw



70% vL
iO'/jkM.







15%













.



SUB.CONTRACTS
—
—
—
65500
Z.ZSbOOO
—
11700

24S300
Z,5B\50Q



























*


MATERIALS
—
144400
I7270D
—
f, 94-7440
48IE00
34j 100
572 &00
U30
S, 661370






























TOTAL
°>16CO
assooo
24 7 50 j
65 50 C
4,3273c;
80&OC1)
53, Z 2C:.»
661 900
25241.)
7, E40460








t, 064- 44(3
8,304^00







1,245,7^
9;5SO;60C
477 400




la oa8,occ
K-
-------
CUSTOMER
LOCATION
PROJECT Aii_
CONSTRUCTION COST ESTIMATE
SINGMASTER & BREYER
NAPCA DESCRIPTION SUMMARY



Moi-TeW CA«?8«*//4TG ftocesy
CA SE A-
400 M u/.
3'/, S. IM COAL

                                                                                PHOP. NO.

                                                                                CONT. NO.  PS *  2 I

                                                                                MADE BY    J • a  J,

                                                                                APPROVED
ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800























900





ITEM & DESCRIPTION
Excavation & GroJing
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities "*
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Stcff, Subsistence & Expense f
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance j"
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense V
Office Payroll Burdens
Indirect Costs-Office J
(Engineering Development Cost Mot Included)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee 5%
Equipment Rental \JhclurJe4 lh Ifccilrtct
Small Tools J p|£/.4 CojTV
Royalty/Know-How
Sales Taxi H/0t Inclt4cjfid.
SUB-TOTAL
Penaitit^ (Pr«clf»/tit«r $ Ductv)
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CENT* OMITTED
LABOR
5S10Q
63000
51000
_.
6\810
IS12.00
104600
44606
1570
571^40



70LL,
lO'/ovM.







15%












t



SUB-CONTRACTS
—
~>
—
6550C
U7S40C
-
6 ^00
—
(15000
\Zb5&b(.


























*


MATERIALS
-
84200
120000
—
903540
"ISQ&OQ
1 Q<^ D0£
286400
700
/ '





























TOTAL
53 IP:)
147 20 •>

6mj

54^80u i
3I05CJ
331001
II7Z7.J
3;8I73£0








5S82ZC
440570C



-


66080(
5066500
25350C




5,320 COG
1 OOOOCO
>




DATE JJ-f6-7<>  pcvisiOM »0._
REVISION OATE-
PAGE MO..
Faun
E-154

-------
CONSTRUCTION COST ESTIMATE
 SINGMASTER & BREYER
CUSTOMER r* (\ f U
LOCATION
PROJECT A •)• Moi-"1?** CAR&I
f\ DESCRIPTION O U M M
CASE
• 4oo h
U S. «M
»tf»T£ "8w«2tf
ART
5
4> W-
COAL


PROP. NO.
CONT. NO. PS ' Z 1 8
UAnr HV- J •»• «*•
APPROVED
ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800























900





ITEM & DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities ~
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense j
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance j
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense r
Office Payroll Burdens
Indirect Costs-Office J
.Eriqineennq Development Cost Not Included)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee 5%
Equipment Rental ) |hcludee{ in. Inject
Small Tools J pifil-4 C*&tt-
Royalty/Know-How
Sales Tax )4(rf |rtc.|uci ed.
SUB-TOTAL
Pen allies (Precjp.'idfd*' t Ducf*)
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CENTS OMITTCO
LABOR
44100
47200
40400
—
43 540
I6E300
63 7fl0
40 100
1 506
463340



70%x L .
tor.xM.'







15*
















SUB-CONTRACTS
-
-
—
6550G
^34-700
»
5500
/*<*
*l 1,700
1 037400
'

























-


MATERIALS
—
63ZQO

—
634 2 W
22.4700
15^100
257 700
600
f 433 560





























TOTAL
4-4 WO
1 I 0500
134700
65 5CO
i £ i o £r, .^
1. w 1 cL .> w v
357 OCO
Z4B 400
2^7 ffliJ
^3 80C
2 ^4300








470700
34^5000






5iq 800
^J I u ** O v V
1 Q Cv ^ rt ^



.
4,184000
420000





PATF  H- \C-1Q
   10..
REVISION DATE-
PAGE NO..
                                              4-31
Font
E-154

-------
CUSTOMER
1 OCAT10N
PROJECT A. /. M*<.
CONSTRUCTION COST ESTIMATE
SINGMASTER & BREYER
^lAPCA DESCRIPTION St/MMdRV

T*U CA88'f>*Tt ^Kac



£4{
CA5G (a
400 M. \A/,
6% -S. /A) COAL.

PROP. NO.
CONT. NO. ^$ '"Llf
Uinr RV V-*J'
APPROVED
ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800























900





ITEM 4 DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities "~\
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense j
Craft Fringe Benefits I
Vacation, Sick Leave & Holiday 1
Payroll Burdens & Insurance J .
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense *
Office Payroll Burdens
Indirect Costs-Office j
Engineering; Development Cost Not Included)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee 5 '/.
Equipment Rental ") Include^ Ih / hfiil r 4 c"f*
Small Tools j fieJ^ £05 1$
Royalty/Know-How
Sales Tax
SUB-TOTAL
penafhes (Prec*f>itct/r ^p^<:f<)
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CENTS OMITTED
LABOR
69 tfQO
75300
56100

74100
224600
IZ5600
55500
I 600
680800



70/iy L-








15%
















SUB-CONTRACTS
-
—
—
65505
1 353600
—
5200

[4
-------
CONSTRUCTION COST ESTIMATE
 SINGMASTER & BREYER
CUSTOMER N A F C #
LOCATION
41 /"* V
,1. M0LY?l) ^-A8Bi>A>AT£ I]
DESCRIPTION -^t-I fV
CA5(
1000
j 3% -S
fe»c*«
1 M A KY
5 7
M.U/,



PROP. NO.
CONT. NO.
MADE BY
APPROVED

?S'T.[%
J.-r.J.

ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800

























^J
^i o o




ITEM & DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities "1
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense f"
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense «•
Office Payroll Burdens
Indirect Costs-Office J
(Engineering Development Cost Not Included)
TOTAL OFFICE COSTS

TOTAL FIELD & OFFICE COSTS
Fee 5'/,
Equipment Rental •) Ucltt4«l 'b Wire*."**
Small Tools \ Fie(fj Cfi f t.
Royalty/Know-How
Sales Tax fJ0-f lhCl'i'4^^
SUB-TOTAL
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CENT* OMITTED
LABOR
103 a1 oc
II t>200
84-bQO
—
128700
340200
177300
I 04400
4000
I,056UO



70%vL
lOT *M
*






15%














,



SUB-CONTRACTS

«•
—
IB 600

' -
10700
2 36 (,00
2/?JfH00































MATERIALS
—
\4l3oo
R7500

f g<\2, g$0
510300
34^^00
sguooo
t ooo
3,6647/30































TOTAL
\Q30VO
Zt>k 100
£82 l£3
16 6CO
4,476700
£50503
537200
242600
7, 52 4 200








1, 1ft ^, 500
8,633760







1 2. ^ 5" 0 06
1, fc I V
o a o $ 7 0 J
4-
-------
CUSTOMER.

LOCATION _
                            CONSTRUCTION COST ESTIMATE
                            SINGMASTER & BREYER
                                     DESCRIPTION
                                                    \OO<>   M-
                           . PROP. NO. .
                           . CONT. NO..
PROJECT
        AL
                           . MADE BY 	
                           .APPROVED.
ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800
ITEM & DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense f'
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance _j
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting J
Purchasing & Accounting J
Office Expense v
Office Payroll Burdens I
Indirect Costs-Office J
(EhjjineeMhcj Development Cost Not Included.)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee 5 In
Equipment Rental ") |nclur!*f/ »n Ipcltr^Tr
Small Tools J £,g j^ fa \
Royalty/Know-How
Sales Tax Vi"\ jrtfrl «fi{ £#f
SUB-TOTAL
\&t*C(\i\e$ C n'c^'pi idS" \ yttc-'iJ
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CENTS OMITTCD
LABOR
71360
QQSbO
235"7oo
3400
72l9ooc

«
>
SU8. CONTRACTS
load
U2bw
2, 0456o6



MATERIALS
\014M
\$t>too
£4\foo




TOTAL
713CJ
312?ol
417 So
I O\ 5o-v

•?864oo

34i?2-Ct5
72 7 0 OCO
3 63 Otic
1 (,13Mb

        DATE
                       Revision »o.l
REVISION DATE.
PAGE NO..
                                                                             4-34
FORM
E. 154

-------
CUSTOMER N
LOCATION
PROJECT A . I . Mfl t-1 ZfJ
CONSTRUCTION COST ESTIMATE
SINGMASTER & BREYER
/4RC4 DESCRIPTION f3tfMM4£Y'



^AF9at)ti7£, ftft3cJeff
r,A5E 9
\ooo M • U/i
(s>'/t $, itn <^^4c*

PROP. NO.
CONT. NO. P £ —"2.1 #
• u»nr RY 4 . J • J •
APPROVER
ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800


























rt
T 0 0




ITEM & DESCRIPTION
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance ^
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense
Office Payroll Burdens
Indirect Costs-Office ^
EngihetftMnef Development Cost Not Included)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS

Fee 5%
Equipment Rental") Udi^W/ '•» l^lt&C^'
Small Tools j pi&ldi £04*4
Royalty/Know-How
Sales Tax \| 4t lh&lufJ£c£
SUB-TOTAL
Penalties CfVtcipif^ttf ^ 3>u&fc.)
Escalation Labor
Material
Contingency Labor
Material
TOTAL














r







>

















ESTIMATED COST
CCMTl OMITTIO
LABOR
IZ4-400
14-1600
1 1 4 3fl£
—
154300
4) 1 100

1 (o^oOC
1106
It? r* jt A
j O A- 1 ^ 0



7o%xL
• ^ f
i






15%













,



SUB-CONTRACTS
—
-»-
—
7B600
Esaeooo
*-•
i "3 00£
—
2g63ad
3 lQ
40140(5
o (tbAffi?
1 1t)D
45ZIZoo






























TOTAL
i e4 400
3 I q I0i)
340806'

5,4-0^200
I 0271Cu
'64^ ICO
6S3005
Z<\Z (00
^, Q14QOO








1,4-ao 5od
104745"oo






I.51UOO
12. 04>?7iy
'/ n? ^n ^




.
12. 64^(5(30
z; 3 52.0 a




DATE
BFVISIOli «0..
REVISION DATE.
PAGE HO..
                                                         4-35
Fo«u
E. IS4

-------


CUSTOMER

LOCATION

PROJECT A.I, to
CONSTRUCTION COST ESTIMATE
SINGMASTER & BREYER
MA PC A DESCRIPTION StfMMARY
C A. *f f™ I ^^
^** ^» B' ^-* 1 tx
CflPPftR. S"HclT$S
£*" ^
\o\st st* CARSOI)AJS. uwie«5


f
PROP. NO.
5- 	 CONT. NO.
MAoe or_
APPROVED




p* -Mg
•J-/.J.

ACCOUNT
NUMBER
000
100
200
300
400
500
600
700
800
900
ITEM & DESCRIPTIOH
Excavation & Grading
Concrete & Masonry
Structural Steel
Building Components
Machinery & Equipment
Piping
Electrical
Instruments & Controls
Insulation, Painting & Scaffolding
DIRECT FIELD COSTS
Temporary Construction Facilities *"N
Miscellaneous Services, Supplies & Expense
Constr. Tools & Equip. (Service & Handling)
Travel Time & Expense (Field Personnel)
Field Staff, Subsistence & Expense
Craft Fringe Benefits
Vacation, Sick Leave & Holiday
Payroll Burdens & Insurance
INDIRECT FIELD COSTS
TOTAL FIELD COSTS
Engineering & Drafting
Purchasing & Accounting
Office Expense <
Office Payroll Burdens
Indirect Costs-Office J
EtiqinaeKirq Development Cost Not Included)
TOTAL OFFICE COSTS
TOTAL FIELD & OFFICE COSTS
Fee 5%
Equipment Rental
Small Tools
Royalry/Know-How
Sales Tax
SUB-TOTAL
Escalation Labor
Material
Contingency Labor
Material
TOTAL
ESTIMATED COST
CCNTS OMtrrco
LABOR
ZZopo
itfxci
70°^x- L
lOHxM.

15%
,.„>
SUB.CONTRACTS
S^CGd
46Sco
4 7 $006



MATERIALS
54200
11 001
4-65loo
//$ 24)



•
TOTAL
32 oca
IIO^OC;)
It04ti
14-0 ZCd
lt t>"5loti
111 OM
/& /% ^ A S*A
/ W £j & I* iS
& (f *** & ** J
7, I ?73Gs)
'376 WO

/I- f7-7a     BEVISIOII  »o..
REVISION DATE.
PAGE NO..
FORK
E-IS4

-------
5.  DISCUSSION OF PROCESS-PROBLEMS
    In evaluating the Molten Carbonate Process for removal of SOX
from new and existing power plants and copper smelters it has be-
come evident that the available bench scale data are insufficient
to fully define the design and economic aspects of the process.

    Certain-problem areas were recognized by Atomics International;
other apparent problem areas have come to light during this study.
Still more may become evident in a pilot plant program.

    This section of the report contains a discussion of both tech-
nical and economic problems that may be encountered should this
process be applied to power plants and copper smelters.

    a.  Absorber

        Atomics International has proposed the following criteria
for the design of the absorber:

        1)  Maximum superficial gas velocity:  25 ft/sec.

        2)  Inlet molar ratio to the absorber, M2C03 to SOX:
10:1 maximum.

        3)  Melt recycle rate to the absorber:  3:1 maximum.

        4)  Mol percent M2C03 in the absorber exit melt:
68.0 minimum.

        Atomics International has reported detailed feasibility
studies on the spray absorption of SOX compounds in molten car-
Donates.  These tests were made on a laboratory bench scale.  Ef-
fective SOX removal was determined at superficial column gas ve-
locities as great as 25 ft/sec.  The adjustment of experimental
results for absorption by the wetted column wall also showed ade-
quate spray absorption at this range of gas velocity.

        The absorption of sulfur oxides in molten carbonates was
also demonstrated on the bench scale using a wetted wall tube and
a baffle column.  The use of absorber designs such as slats, trays
or packed towers was not excluded by Atomics International for
future consideration.

        The proposed absorber design criteria are summarized in
Figure 5-1 with the design range shown as a cross-hatched area.
These demonstration values do not include a small increase in
M2C03 quantity in the melt, as needed to maintain specified molar
                                                    SINGMASTER & BREYER

                                 5-1

-------
Ui
I
ts>
           3
M
O
CO
           4J
           cd

           g
           n)
           M

           1
           U
           a
           o
           O
           U
                  100
90


80


70 i,


60


50


40


30


20


10
                                               L=2724
                                               1=2724
                                             L/G=0.0116
                           68%
                            L=1622
                            1=1622
                          L/G=0.0069
              =3243
             1=1622
           L/G=0.01
                                                                         No Recycle


                                                                         1:1 Recycle


                                                                         2:1 Recycle

                                                                         3:1 Recycle
                 1622
             L/G=0.0207
  1=64^6
  1=1622
L/G=0.0276
                                                                         10:1
                 _L
              I
_L
_L
                                                         _L
I
I
              Design range is shown.
                  cross hatched.

              L is total moIs of melt
                to absorber, per hour.
              1 is total moIs of melt
                to reducer, per hour.
              G is total mols of gas
                to absorber, per hour.

              Recycle is the number of
              mols of melt which is
              returned to the absorber
              divided by the number of
              mols of melt advancing
              to the reducer.

              Flow rates pertain to
              the base case: 800MW,
              3% S in coal.

              Dissolved KCl not in-
              cluded in melt compo-
              sitions.
                      0123456789    10    11
                                  Ratio  of mols  M^CC^:  mols  SO^ Entering Absorber

                      Figure  5-1.  Absorber  Operating Limits (Based on A-I Design  Parameters)
                                                                                    12

-------
concentrations in the presence of dissolved KCl derived from
chlorides contained in the coal.

        A 1:1 ratio of absorber melt to  fresh melt with 68 mol
percent M2C03 concentration in the melt  at the absorber outlet
was selected as a desirable design target.  Higher recycle rati-
os can be achieved by increasing the capacity of the absorber
pumps.  Such an increase in recycle ratio may be necessary if
the absorber design departs from the spray concept proposed by
Atomics International.  These inlet conditions were used for
the material balance appearing in Drawing PS-218-0001, and also
in the materials flows presented for the alternate cases.  All
power plant material balances include dissolved KCl in the melt.

        The process flow diagram (Drawing PS-218-0001) shows a
M2c°3:S°x rati° of 6:1 with a 1:1 melt recycle ratio.  (It
should be noted that the corresponding conditions in Figure 5-1
apply to a slightly lower M2C03:SOX molar ratio of 5.4:1 since
dissolved KCl was not included in these  demonstration calcula-
tions.)  This results in an L/G ratio  (total mols of melt to
total mols of gas) of 0.015, when columns are connected in par-
allel for both gas and liquid flow.  The absorber pumps as de-
signed are capable of a 3:1 melt recirculation ratio.  If oper-
ated in this manner, the M2C03:SOX ratio would be about 10:1,
giving an L/G ratio of about 0.03.

        There are a number of questions  which must still be
resolved for the final design of the absorber.

        1)  The performance of a commercial sized absorber
with this low L/G ratio is questionable.  To improve further
the L/G ratio, the absorbers have been designed for series
flow on the liquir" side (while maintaining parallel gas flow)
at the maximum absorber recycle ratio of 3:1.  This change
further increases the L/G ratio from 0.03 to about 0.12.
This series-parallel arrangement, however, changes certain
flow characteristics basic to the design of the absorber.
Thus, the M2C03:SOX ratio in the first absorber would be
about 40:1.  In the other absorbers, the incoming flue gases
would come into contact with progressively decreasing con-
centrations of M2CC>3.  The melt leaving  the last absorber
remains at the specified minimum M2C03 concentration of 68
mol percent.  The effect of this M2C03 concentration gradi-
ent requires further examination although the ability to
remove SOX is not expected to be significantly impaired.

        2)  The scaleup of the absorber  design from bench
scale data requires confirmation, perhaps more than any
other part of the process.  Particular attention is needed
                                                     SINGMASTER & BREYER

                                 5-3

-------
to  identify  the wetted wall effect in bench or  pilot  scale spray-
tower  absorption.   Atomics  International has attempted to account
for and  to correct for the  wall effect, in their experiments.  How-
ever,  it appears that additional work on a larger unit is necessary
to  check these  initial test results.   Wetted wall effects are ex-
pected to be minimal in full scale operation.

         3)   Atomics International found that spray droplet size
was critical to absorber efficiency.   The critical calculations
indicate a droplet in the range of 100 microns  should prove ef-
fective.  Bench scale tests showed that small droplets performed
much better  than large ones although  actual droplet size proved
difficult to measure with assurance of accuracy.

             The spray nozzles  to be used in a commercial unit
should be thoroughly evaluated.

         4)   The demisters will require detailed study*  The ob-
jective  will be to design a demister  which will hold  melt carry-
over to  an acceptable minimum  while.conforming  with pressure loss
considerations,  and at the  same time  not be plugged with melt or
fly  ash.

             Although Atomics International has  obtained good SOX
removal  efficiencies using  high.gas velocities,  about 25 ft/sec,
the  possible effects of  such high velocities -must be  determined
in  a large unit-.   The prime concern of high gas  velocity is that
in  a spray absorber small droplets of melt will  be carried off
with the  scrubbed  gases,  in spite of  the use  of  demisters.  This
loss of melt is  undesirable from an economic  standpoint and not
acceptable from a  corrosion standpoint because  the scrubbed gases
are  returned to the boiler  where the  materials  of construction
are  not  likely  to be compatible  with  melt.  Furthermore, the melt
carryover may be emitted  to the  atmosphere from the boiler stack
causing  additional  pollution problems.

         5)   The possible  plugging of  the spray nozzles producing
the  fine droplets by fly  ash must be  checked by  additional test-
ing.   The melt  is recycled  to  the absorbers upstream  of the fly
ash  filter,  in  order to reduce  the filter load.  Consequently,
there will be some  fly ash  in  the melt which is  recycled to the
absorbers which may  limit the usefulness  of recycle melt if it
is needed for flushing the  demisters.

         6)  !Another  area where  further work is desirable is the
evaluation of other  types of columns,  such as a  slat  tower, tray
tower or a packed tower.  The work should be performed to evalu-
ate  the absorption  efficiency at  minimum pressure drop and melt
carryover.  These absorbers do not require as fine a  liquid
                                5-4

-------
droplet as the spray tower, and are likely therefore to reduce
melt carryover.  However, the gas pressure drop is considerably
higher for these types than for spray towers and the towers them-
selves are generally more expensive.

            In summary, large scale absorption development is de-
sirable to confirm the bench scale absorption performance re-
ported by Atomics International.  Larger scale tests would also
define demisting requirements as well as localized effects such
as nozzle plugging or solids buildup.  The results of such tests
would develop a firmer basis for design utilizing the unique ab-
sorption properties of molten carbonates.

    b.  Reducer

        There are a number of problems associated with the re-
ducer which are still to be resolved by further experimentation.

        One of the areas which still requires investigation is
the matter of materials of construction.  From this standpoint
this is the most crucial part of the process because the temper-
ature, at 1500° F, is higher than elsewhere in the system.

        In Section 6, Paragraph d, there is a discussion of sev-
eral methods of construction that were investigated.  The method
selected includes the use of a high alumina brick, such as Alun-
dum, as back-up to Monofrax which is in contact with melt.  The
Monofrax (which is much costlier than Alundum and has a higher
thermal conductivity) is known to be resistant to melt.

        The Monofrax, however, is not completely free of voids,
and melt which seeps through the Monofrax voids and joints will
come into contact with the Alundum.  It has been assumed that
melt will not detrimentally affect the Alundum but this will
have to be tested.

        The design of a vessel with three dissimilar materials
in contact with each other presents extensive design problems
because of differential expansion.  It will be necessary to ob-
tain accurate temperature profiles to facilitate the design of
such a unit.

        The concept of a two-zone reducer is another area which
requires additional work to insure operability.  The object of
the two-zone approach is to separate the oxidation gases - ni-
trogen (contained in the combustion air), from the reduction
gases - essentially CO? evolved in the reduction of metal sul-
phates to the metal sulphides.  The oxidation gases, after be-
ing exchanged against combustion air, are returned to the power
                                                    SINGMASTER S BREYER

                                 5-5

-------
 plant along with the scrubbed flue gases.   The reduction  zone  gases
 are  fed to the Regenerator.

         The mechanical design of the reducer will  have  to be inves-
 tigated to determine the proper parameters  for making this  separa-
 tion as fine as possible.  Factors which will have to be  checked
 include area and configuration of openings  between oxidation and  re-
 duction sections to obtain proper circulation.   It is important to
 attain a good separation here because any nitrogen from the oxida-
 tion section which reports with the reducer gases  will  go through
 the  Regenerator, into the Glaus Plant.   Equipment  sizing  would be
 affected,  and the heat content of the gas not be easily recoverable.
 Dilution of reduction zone gases, however,  may be  beneficial to the
 number of  theoretical trays  required in the Regenerator (see Section
 5, Paragraph d).

         A  third area where further test work should be  performed  is
 in the coke addition.   In our estimate,  we  have allowed for blow
 tanks  for  introduction of the coke into the reducer section.   How-
 ever,  it might be better {or necessary)  to  bring the  coke in.as a
 slurry with the melt.   This  could be accomplished  by  installing an
 agitated,  atmospheric tank ahead of the reducers,  where the coke
 could  be added to the melt.   The effect that this  would have on
whether melt input should be to the oxidation or reducer  section
 should be  investigated.

         While  the recovery of relatively pure carbon  dioxide from
 the  reducer would be beneficial it is not critical to the success
 of the process.   An alternate source of carbon dioxide  would be the
 absorption  of  carbon dioxide from a portion of  the boiler flue gas
in a conventional amine  type absorber with  subsequent stripping.
Neither  the  capital investment nor the  operating cost of  such  a
unit are likely  to affect the overall capital investment  or total
operating cost significantly.

     c.   Reducer  Off-Gas  Cooling

         The  process  scheme as  conceived  and shown  on  the  Process
Flow Diagram utilizes  the  heat in the Reducer Oxidation Zone off-
gases  to preheat the  incoming combustion air to a  temperature  of
600° F.  As  a  consequence, the off-gases are cooled from  1500° F
to a temperature of  approximately 1120°  F.   (No credit  has  been
taken  for the  heat  content of  these gases).

         If  the off-gases were  cooled to  850° F,  the combustion air
can be heated  to 915°  F.   The  Air-Oxidation Zone Exchanger, E-2,
has been conservatively  designed for this latter case.  The coke
consumption  for  raising  the  combustion  air  to the  1500° F reducer
temperature has  been based on  the 600° F preheat.
                                 5-6

-------
        Consideration must be given to the possibility that chlo-
rides dissolved in the reducer melt may vaporize and be carried
with the off-gas to condense on the tubes of the exchanger thus
seriously reducing the heat transfer coefficient and introducing
a serious danger of corrosion.  This possibility must be examined
during the pilot plant program as to problems in heat transfer
as well as the release of chlorides to the flue gas stream re-
turning to the boiler.  If it occurs, shot cleaning of the ex-
changer tubes can be incorporated in the design of the exchanger
to minimize the effect of the chloride solids condensing on the
tubes.  The shot cleaning equipment has not been included in the
capital cost estimate.

        Carryover of hot melt with the off-gas must also be con-
sidered since this too may cause corrosion of the exchanger
tubes at temperatures above 1000 °F.  At lower surface tempera-
tures, the entrained melt may condense on the tubes to reduce
the heat transfer coefficient.

        An alternate to preheating combustion air with oxidation
zone gases is to use a portion of the waste heat available in the
reduced melt or in the Regenerator melt streams.  The capital
cost for the exchanger to accomplish the air preheat by this
method has not been estimated but could approximate the cost of
the Air-Oxidation Zone Exchangers.  A danger exists in the use
of this type of exchanger; the melt is cooled by relatively cold
air which may cause freezing.  In the air-cooled exchangers pres-
ently contemplated for cooling the reduced melt and regenerator
streams there is also a danger of freezing melt but these units
are equipped with external air bypasses to recirculate hot air
to temper the inlet air which will minimize the freezing.  They
are also equipped with steam coils to heat the air during start-
up should this be required.  It is probable that a similar system
could be designed for a combustion air preheater using hot melt
as the source of heat.

        There are two advantages that are apparent in elimina-
ting the Air-Oxidation Zone Exchanger.

        1)   The heat available in the return of 1500 °F off-gas
to the boiler above an 850 °F datum is 18 million BTU/HR for the
base case plant.  This is equivalent to an annual saving assum-
ing the boiler equipment can take advantage of this additional
heat, of $33,000 at a value of 30£ per million BTU.

        2)   Any problems associated with chloride or melt con-
densation on exchanger tubes will be eliminated from the process.
The gases can be mixed with the absorber off-gas at 850 °F where
the small amount of chlorides will condense on contact with the
                                                     SINGMASTER & BREYER

                                 5 = 7

-------
 colder gas  and be carried as fine particulate matter  to  the boiler.

             The penalty for not preheating the combustion  air  is
 additional  coke consumed in the reducer.    Waste  heat valued  at
 30£/million BTU's is  being used to replace coke valued at  approxi-
 mately 48C/million BTU's which would otherwise be  required.

             The off-gas from the reduction zone of the reducer is
 cooled to the  Regenerator temperature by  the  addition of water
 and/or low  pressure steam in the amount required for  the regener-
 ation  reaction.

    d.  Regeneration

        Atomics  International,  in their previously reported work,
 used the McCabe-Thiele  approach to determine  the number  of theoret-
 ical trays  required for the regenerator.   It  is believed that this
 approach is  valid from  the  preliminary information contained in the
 reports.

        The  effect of changes  in gas  composition and  flow on the
 number of theoretical trays  required  to accomplish the desired
 regeneration of M2S contained  in the  feed melt has  been  examined.

        These  studies were based on regenerator tower temperatures
 ranging between 850-950°F using intermediate  coolers  and partial
 recycle of cooled melt  to upper trays.  Atomic^ International
 studies were based  on an  isothermal regenerator with  cooling pro-
vided at each  tray  to maintain  the temperature at  850°F.

        Carbon Dioxide Required

        The equilibrium curve for XK^S versus YH2S  is based on the
following Atomics  International  equilibrium equations:

                      !.9x

        Kequil   =
                      1 + 1.24 x 10~3 Pn_  (e15'400)
                                       \*> \J ^     TDT*
                                         ^     i\JL

                      XM2C03  PH2S

                         3  PC02  PH2O
                               5-8

-------
        Substituting


            =   1.9  x   10~6  (e  28/°°0  )   and
                                  rjrn
                                  RT
K2  =  1.24 x  10~3  (e 15f40°  )  in equation  (1)
                         RT      results in

              vs

Kequil  =
                                                                (3)
        Equating equations  (2)  and (3)  at one  atmosphere pressure
where the partial pressure  of  the  gases are equal to their respec-
tive mol fractions results  in  the  following XM2s equilibrium equa-
tion:
        x
              =   (XM2C03)  (YH2S)  (1+K2
                       Kl  (YC02)
                                                                (4)
        at 850  °F,  K2  =   52.9

        at 950  °F,  K2  =   24.7
        For a constant XM2C03, Y{j2Sf  and  YH20 the equilibrium
equation reduces to
        X
         M2S
                 K3  (1+K2
                                                        (5)
                       C02
        When the C02 concentration  in  the  exit gas  is  above about
0.04 mol fraction,  K2Yco2 is  t*16 dominant factor in (l+K2Yco2)  °f
equation (5) and maintaining a C02  concentration of two to three
times this value will make the equilibrium curve substantially in-
dependent of C02.

        Equation  (1) was developed  empirically by Atomics Inter-
national on the theory that M2S and C02  act to form intermediates
such as M2CO2S.  All the tests were carried out with excess amounts
of M2S.   At the bottom of an  actual tower, the concentration of
M2S will be quite small.  Therefore, in  the lower section of the
                                                      SINGMASTER S BREYER
                                 5-9

-------
tower,  the  independence  of  the  equilibrium curve  on YCO$ mav not be-
valid.   If  so,  this would cause the equilibrium curve  to shift un-
favorably requiring more theoretical trays.   It may be necessary to
add only H20 with  less than the required  amount of C02 to the bottom
of the  tower and the  remainder  of  the C02 to  intermediate points.

         Water Required

         Inspection of equation  (4)  shows  that for constant Xjy^CC^,

YH2S and YcO2 •  tne value of X^2S is inversely proportional to Y^O-
This means  that the equilibrium curve will shift  favorably to de-
crease  the  number  of  theoretical trays as YH20 increases.

         Number  of  Theoretical Trays

         To  substantiate  our conclusions regarding the  gas concentra-
tion effect on  the equilibrium  curve,  calculations were performed to
determine the number  of  theoretical trays at  various gas flows and
concentrations.

         Figure  5-2 shows the number of theoretical trays required
for 95%  regeneration  of  M2S as  a function of  gas  flow  for equimolar
concentrations  of  CO2 and H20.   It  also shows the effect on the num-
ber of  theoretical trays for various  gas  flows with a  constant flow
of C02  entering of 620 mols per hour  for  the  base case with the dif-
ference  constituting  H20.   The  constant flow  of 620 mols per hour was
arbitrarily selected  to  maintain the  C02  mol  fraction  in the exit gas
at approximately 0.08.   This is approximately 25  percent above the
stoichiometric  quantity  required as compared  to an 85  percent excess
indicated by Atomics  International.

         For the base  case,  at YcO2  =0-5  and  a C02 flow of 620mols
per hour, an infinite number of theoretical trays is required even
with an  isothermal tray.

         Stoichiometric quantities of  CC>2  and  H20  only  cannot attain
the desired regeneration because it produces  a Yn2S at the regener-
ator outlet of  1.0 which is  above that in equilibrium  with the inlet
feed.

         A diluent  gas such  as N2 would allow  essentially stoichio-
metric quantities  of C02 and H2O to be used.  The diluent would
lower the YH2S  in  the exit  gas  to a point where it would be in equi-
librium with the XM2s ^ the' feed.  However,  a greater number of
trays would be  required as the quantity of H20 and C02  approaches the
stoichiometric  level.  Water vapor  could  also serve as a satisfac-
tory diluent but amounts sufficient to have a significant effect
also have a detrimental  effect  on the  performance of the Glaus plant.
                                5-10

-------
Figure 5-2=  Regenerator Theoretical Trays
11
10
9
to
(0
£ 8
H
m
•3 7
0
O c.
jC
^
o 5
M
V
A/\ 0
/ "^^^
^^^ O
Inlet CO^ = 620 mols/hro — — 	 n

-------
         Tray Efficiency

         The actual number of trays depends on tray efficiency for
 this type of contactor.

         Tray efficiencies of distillation systems range between
 45  and 90 percent with the lower efficiencies generally indicated
 for viscous materials greater than 5 cp.   It is expected that the
 tray efficiency in the regenerator would be below 45 percent be-
 cause

         1)   of the high viscosity and

         2)   the reaction rate must be added to a mass transfer
 rate.   Distillation is a mass transfer operation only.

         The actual number of trays selected for this study is 15.
 The theoretical number of trays required is approximately 4 based
 on  equimolar quantities of CC>2 and H20 at an excess of 85% with
 little or no inert diluents present in the gas.  /The equivalent
 tray efficiency is 27 percent.  It is expected the design of the
 two-zone reducer will minimize the inert diluent gases (N2)  that
 can affect the theoretical number of trays.

         Tray Type

         Sieve trays were suggested by Atomics International to
 permit draining of the tower to the pump tanks.  However, bubble
 cap trays  or valve trays can be designed for drainage.  Sieve
 trays  have  a narrow range of liquid to vapor ratio for satisfac-
 tory operation which in this case is constantly changing through-
 out the tower.   Bubble cap or valve trays have a greater range of
 operation.   Sieve trays must be relatively level whereas minor
 variations  can be tolerated with bubble cap or valve trays.   On
 this basis,  bubble cap trays have been selected for the capital
 cost estimate.

         Temperature Control

         The  regeneration reaction is exothermic and must be con-
 trolled to hold the temperature above the melting point (750-
 800  °F)  and  below 1000 °F to limit corrosion of type 347SS.
 The  range of tower operation has been restricted to between
 850  °F and 950  °F.   To achieve this control,  it is planned to
 recycle cooled  melt from a lower tray in  the  tower to an upper
 tray.   The design that has been used in this  estimate is for
 one  intermediate  cooler with partial recycle  by temperature
 control to the  top section of the tower and one bottom cooler
with partial recycle again under temperature  control to the
                                5-12

-------
lower section of the tower.  This reduces the overall tower effi-
ciency because of the increased liquid to gas ratio and results
in a slight increase in the number of trays.  A rise in tray tem-
perature is corrected by the addition of cooler melt containing
less M2S.  This reduces the rate of reaction due to lower tempera-
ture and lower concentration of reactants.

       More external coolers can be provided to reduce the re-
cycle but each additional cooling unit requires a pump tank,
pumps, cooler and controls which will cost substantially more
than the cost of additional trays and tower height.

       An isothermal tower with cooling coils on each tray can
be employed but was not considered for regenerator cooling be-
cause of the following disadvantages:

       1)  A heat transfer medium is required for the coils.

       2)  The available operating area may be reduced resulting
in a larger diameter tower.

       3)  Higher liquid level will be required on each tray to
submerge the coils increasing the pressure drop and back pres-
sure on the reducer operation.

       4)  Increased costs for installing the tray.

       Tower Design Parameters

       The design parameters furnished by Atomics International
for sizing the tower are:

       Superficial Gas Velocity         4 FPS

       Holdup Time                     15 minutes

       Based on the net flow of melt feed to the tower, a 19
foot diameter column results in one inch of liquid level per
tray to obtain the 15 minute holdup time.  If the recycle melt
used to cool the trays (1:1 recycle ratio) is assumed to be
completely regenerated, the level on each tray will have to be
increased to approximately two inches to maintain the holdup
time.  The actual residence time in the regenerator will prob-
ably exceed the 15 minutes.  The effect of the pump tanks and
external coolers on holdup time has not been considered.

       On the basis of a superficial inlet gas velocity of 4
FPS and an 85 percent excess of CC>2 and H2O with no nitrogen
or other inert diluents,  the tower diameter is less than 14
                                                      SINGMASTER & BREYER

                                 5-13

-------
 feet.   An 18 foot diameter tower has been arbitrarily selected for
 the determination of capital cost.   Reducing the diameter to 15
 feet would lower the capital cost approximately $40,000.

         Pilot plant work is required to:

         1)   Confirm the effect of varying the quantities  and concen-
 tration of CO2 and H20 on tower performance and regeneration.

         2)   Determine the number of trays required to accomplish
 the regeneration at the expected liquid and gas flows and concen-
 trations.

         3)   Establish the design parameters such as retention time
 and superficial gas velocities.

         Additional test work should be  performed to determine the
 effect  of  pressure on regeneration.  Increased pressure has  the
 potential  for reducing the diameter of  the regenerator.

     e.   Fly Ash and Coke Filtration

         In  the Molten Carbonate  Process traces of fly ash, as  well
 as  sulfur dioxide,  are removed from the flue gases.   The  fly ash
 must be  continuously or periodically removed from the molten salt
 stream  otherwise it would accumulate and  make the system  inoper-
 able.   The  fly ash filtration is  performed downstream of  the absor-
 bers.   The  coke filtration,  to remove the unreacted coke  added in
 the  reducers,  is performed downstream of  the reducers.

         Atomics International has done  experimental work  on  fly ash
 filtration  using a Croll-Reynolds wire  wound filter.   This type of
 unit is  not suitable for a commercial size installation because it
 is not  capable of a "dry cake" discharge.   (Dry cake refers  to the
 solids plus  associated wetting liquid).   Discussions were held with
 Croll-Reynolds,  and they indicated  that their unit could  not easily
 be converted to a dry  cake discharge type.

         In  a non-dry cake  discharge type  of filter,  the entire con-
 tents of the filter are discharged  at the end of each cycle.   The
 filter area  required for the  fly  ash filtration based on  data  ob-
 tained by Atomics  International using a Croll-Reynolds test  unit
 is 1000  square feet at a cycle time of  45 minutes.   A 1000 square
 foot Croll-Reynolds  filter has a volume of about 2000 gallons.
 Therefore,  30,.000 pounds  of melt would  be discharged every 45
minutes if such  a unit were employed.   Such a loss  could  not,  of  .
 course, be tolerated.   An  elaborate recovery system would be re-
quired.
                                5-14

-------
        Even "dry cake" discharges carry measurable quantities of
melt.  Atomics International has found that the fly ash cake con-
tains 65% melt, and it has been assumed that the cake from a suit-
able plant scale filter would contain 50% melt.  The implications
of these losses are discussed in Section 5, Paragraph f.

        Hence, the primary problem associated with the filtration
steps is to find a dry cake discharge unit which performs in a
satisfactory manner.

        Based on discussions with several filter manufacturers
the "Auto-Jet" pressure leaf filters, as manufactured by U.S.
Filter Corporation, were selected for the capital estimate. Suit-
ability of this type of filter will have to be verified by test.
In this type of unit, the liquid contained in the filter is
drained and displaced by gas prior to discharging the cake.  Hot
flue gas or alternatively heated air will have to be used for
displacing the melt.  The filter leaves are attached to a shaft
which rotates against a fixed wire or blade at each leaf during
cake discharge.

        Atomics International has found the maximum fly ash cake
thickness reached within tests is approximately 1/8" at reason-
able pressure drops of about 50 psi.  This makes it difficult to
design a suitable cake-scraping device, since it is desirable not
to have such scrapers come too close to the filter media.

        Increasing the cake thickness is an area which will have
to be investigated in order to apply the U.S. Filter type machine.
Coke can possibly be used as a filter aid, introduced as precoat
and/or add-mix, to assist in producing a thicker cake and reduc-
ing the melt content of the dry cake.

        Because of the difficulties involved in mechanically dis-
charging a thin cake, another method was investigated.  This en-
tailed the introduction of water directly into the filter at the
end of the cycle, to dissolve and sluice out the cake.  It is
debatable whether this method deserves further study because of
many inherent problems.

        1.  Long periods of time would be required for cool-down
and heat-up of equipment prior to reintroduction of melt.  Cap-
ital costs would be greatly increased because of this necessity
for "idle" time.

        2.  Frequent thermal cycling leads to problems in design
and construction of the units„

        3.  The water initially used for direct cooling flashes
                                                     SINGMASTER & BREYER

                                5-15

-------
 to steam,  which is lost,  as is  the heat content.

         4.   Possible introduction of water into the melt circuit
 may not be desirable.

         5.   Large vents would be required to handle the steam
 generated  (An explosion hazard  exists).

         It is recommended that  this scheme be discarded,  and ef-
 fort concentrated on thickening the cake.   In addition  to easing
 the design of the U.S. Filter type of unit, a thicker cake might
 change  the picture in relation  to the Croll-Reynolds unit, for
 now a tank full of liquid would be discharged, say, every 8  hours
 instead of every 45 minutes.

         The calculation of filter area was based on the following
 empirical  relationships developed by A.I.: (Based on a  Croll-
 Reynolds test unit with 25 micron spacing).

     = 16.3   +  2530£   For^ greater than 0, less than
                                0.067

     = 88    +   610.21   For ^greater than 0.067,  less than
                                1.25

         Where:

         is  pressure drop  across  filter,  psi

   £_    is  ash  loading, Lb Ash/ft2 of filter area

    (j)    is  flow rate per  unit of filtration area,  GPM/ft2

         These relationships were developed for the fly  ash fil-
 ter.  No correlations were developed for the coke filter.  It
has been assumed that these equations will hold for the coke
 filter  also.  On this basis,  the coke filter was  calculated  to
require  about the  same area,  1000 sq.ft.,  and have about  the
same  cycle  time,  45  minutes,  as  the fly  ash filter.   A  total of
four  filters  have  been allowed - 2 for fly ash filtration and 2
for coke filtration.  In  final design, three interchangable  units
may be possible,  two operating with one  standby and automated for
proper time  cycling.

         The  material of construction for all the  filters  was type
347 stainless steel.

        The  possibility of using centrifugal separators was  dis-
cussed with  vendors, but  discounted because of difficulties
                                5-16

-------
associated with the design of high speed-rotational equipment at
high temperatures and the use of centrifuges is not indicated be-
cause of the relatively small difference in melt"and filter cake
specific gravities.

        Several manufacturers declined to propose the use of Ro-
tary Drum Filters because of the service conditions.

    f.  Carbonate Makeup

        In the Molten Carbonate Process, melt is lost in the
cakes discarded from the fly ash and coke filtration steps.  In
addition, melt can be lost from the process in the absorber off-
gas.  It has been assumed that this loss is negligible and there-
fore it was not considered in the determination of operating
costs.  The actual absorber loss can be substantial and must be
determined in future test work.

        The losses of melt associated with the fly ash and coke
filter cakes have been calculated on the following basis:

        1.  An electrostatic precipitator efficiency of 99.5 per-
cent r

        2.  Potassium chloride  (KC1) solubility in melt is limited
to three weight percent and the solids are removed at the fly ash
filter.

        3.  Fly ash and KCl filter cake contains 65 percent melt.

        4.  The coke filter cake contains 50 percent melt.  It
also retains the heavy metals contained in the original coke
charged to the reducer which must be removed from the process.
The coke usage in the reducer and the subsequent unreacted amount
to be filtered from the reduced melt is based on carbon oxida-
tion rather than sulfide (M2S) oxidation to provide the reducer
sensible heat and heat of reduction.  This assumption results in
a lesser amount of coke to be filtered than would be anticipated
if the heat were provided by M2S oxidation.  The M2S oxidation
route could increase the unreacted coke to be filtered by ap-
proximately 50 percent.

        5.  Both fly ash and coke filters provide a dry cake dis-
charge.

        6.  Lithium carbonate can be recovered to the extent of
88 percent in the aqueous recovery process as conceived.  The
justification for this process is demonstrated in Section 6,
Paragraph f.
                                                     SINGMASTER S BREYER

                               5-17

-------
         7.   Potassium and sodium salts  are not recovered in  the
 aqueous  lithium carbonate recovery process.

         The  required makeup of sodium,  potassium,  and  lithium car-
 bonates  associated with the various "inert"  constituents of  the
 filter cakes are indicated in Table 5-1.   In addition,  the potas-
 sium carbonate  required for the reaction  with chlorides in the
 flue gas to  produce the KC1 is also listed in this table.

         Inspection of Table 5-1 shows  the impact of melt losses  on
 the  plant operating costs even with the inclusion  of an aqueous
 process  to recover 88 percent of the lithium salts.

         In the  analysis of melt losses  it has been assumed that
 all  of the chlorides in the flue gas react with potassium carbon-
 ate  (K2C03)  to  form potassium chloride  which must  be rejected from
 the  process  to  minimize its buildup.  The amount of K2C03 required
 for  this reaction is fixed by the chloride content of  the coal
 (0.04%)  and  results in an annual cost of  $220,000  (0.045 mils/KWH).
 Very little  can be done to reduce this  cost  if the reaction  takes
 place  as assumed,  except to use coal with a  lower  chloride content.

         The  melt losses associated with fly  ash filtration depend
 solely on the "wetness" of the cake discharged from the filter.
 Laboratory data on the filtration of fly  ash in melt using a
 wedge-wire wound filter element of 25 micron spacing indicated
 that the cake contained 65 weight percent melt which is under-
 standably high  due to the nature of the cake.

         The  physical form of the fly ash  will have a marked  affect
 on melt  content of the cake.   If the fly  ash is in the  form  of
 hollow particles,  then more melt may be retained by the cake than
would  be expected  with solid particles.   Furthermore, no test work
 has  been performed on the filtration characteristics of fly  ash
 that passes  through the electrostatic precipitator.  This too,
 may  affect the  data used in the evaluation.

         As stated  above,  the KC1 produced by reaction of chlorides
with K2C03 must be removed from the process.   A conservative ap-
proach has been used in this  analysis by  assuming  that  the KC1 is
 removed  at the  fly  ash  filter  and retains  the same amount of melt
 as the fly ash.  The melt content of .a  combined fly  ash and  KC1  fil-
 ter  cake must be determined in  future test work,   in addition, if
 a commercial filter  provides  a  dryer cake than is  available  from a
 test unit, substantial  savings  can be realized.  Furthermore,  an ad-
mix  (body feed)  of  coke to the  fly ash  filter could  possibly reduce
 the cake  "wetness".   Another possibility  to  reduce the  melt  losses
associated with  fly  ash  filtration would  be  to eliminate the step
completely and  filter  the fly  ash with  the unreacted coke from the
                                5-18

-------
                 Table 5-1.  Carbonate Makeup Requirements - Assuming 88% Li2CC>3 Recovery
Ul
     Basis:  Filter Cake Constituent:  Fly Ash - 225#/Hr )
                                       KCl     - 403#/Hr )  ~Removed at the Fly Ash Filter
                                       Coke    - 800#/Hr -  Removed at the Coke Filter
Cost Per Pound

Makeup Ratio Required for
Non-Recovered Salt, #/# of

Fly Ash and KCl Filter
   Cake
Coke Filter Cake
KCl Produced

Annual Replacement
for Loss From

Fly Ash Filter Cake
KCl Filter Cake
Coke Filter Cake
KCl Production

     Total

Annual Cost for Makeup
                                    $0.42
    K2C03

   $0.096
   $0.028
0.067
0.043
_
0.611
0.368
0.926
0.573
0.361
—
                                   93,000#
                                  167,000
                                  211,000
                                  47l,000#
  843,000#
1,510,000
1,805,000
2,288,000

6,446,000#
  791,000#
1,417,000
1,771,000
3,979,000#
SINGMASTER S BRI
Due
to Losses in
Fly Ash Filter Cake
KCl Filter Cake
Coke Filter Cake
KCl Production
Total
Mills/KWH
TOTAL Mills/Kl
$ 39
70
89
$198
0
,000
,000
,000
,000
.041
$ 81,
145,
173,
220,
$619,
0.
000
000
000
000
000
126
$ 22
40
50
$112
0
,000
,000
,000
,000
.023
$142,
255,
312,
220,
$929,
0.
000
000
000
000
000
190
0.029
0.052
0.064
0.045
0.190

-------
 reduced melt in the coke filter.   The unreacted coke could possi-
 bly act as an admix and aid in filtration.   However, serious  prob-
 lems may result in the reducer quench system due to solubility of
 the fly ash in the melt at the elevated reducer temperature and its
 subsequent precipitation at the lower temperature of the  reducer
 quench system.   A benefit of this approach  could be the possible
 rupturing of hollow sphere fly ash particles in the reducer which
 may minimize the amount of melt retained with the fly ash cake if
 it were filtered with the coke.   These variations must be deter-
 mined from actual pilot plant test work.  The fly ash and coke fil-
 ters are the subject of a discussion in Section 5,  Paragraph  e.

         If the KCl were removed from the process in a form other
 than a solid,  the melt losses would be reduced.   It is possible
 that some,  if not all,  the KCl will be vaporized in the reducer
 and be rejected with the oxidizer off-gas stream returning to the
 boiler.   The amount vaporized will depend on its vapor pressure
 and solubility in the melt at the operating conditions of the re-
 ducer.   This would reduce or eliminate the  melt losses associated
 with the KCl filter cake.   However,  the actual location in the
 process  where the KCl is removed  must be determined in a  pilot
 plant program.

         No  test data are available on melt  loss  associated with
 coke filtration.   It is believed  that it will be less than that
 found with  fly  ash filtration.  An arbitrary value of 50  percent
 melt contained  in the cake has been used for the analysis which
 must be  confirmed by test work.

         Delayed petroleum coke has been selected as the source of
 carbon for  reduction (See  Section 6,  Paragraph e).   This  material
 and fluidized petroleum coke,  an  alternate  source of carbon,  con-
 tain heavy  metals,  such as vanadium and nickel in amounts ranging
 up  to 2000  ppm.   No test data are available  on where these heavy
 metals will concentrate.   It has  been assumed that this will  oc-
 cur  in the  unreacted coke  which must be filtered and discarded
 resulting in  a  substantial melt loss.

         If  the  heavy metals  do not concentrate in the  unreacted
 coke, the coke  filter cake can be recycled to the process elim-
 inating  the  carbonate makeup to compensate for the loss,  but  the
heavy metals will have  to  be removed somewhere else from  the  proc-
 ess by some other means.
                              5-20

-------
        The amount of unreacted coke to be filtered  (i.e. 800#/Hr)
is based on complete  (100%) oxidation of carbon in the coke to
provide the reducer sensible heat and heat of reduction.  A con-
version of 95% of the M2S04 to M2S by carbon is assumed resulting
in the 800#/Hr of material to be filtered.  An alternate to pro-
viding the reducer heat by carbon oxidation is to assume oxida-
tion of M2S to M2S04 resulting in a greater recirculation of J^SO^.
to the reduction zone.  This requires more coke for reduction and
perhaps 50 percent more unreacted material to be filtered.  The
actual amount may fall somewhere between these two limits and must
be determined by a pilot plant program.  The increased coke filtra-
tion resulting in an increase in melt loss has not been considered
in the evaluation because of:

        1.  The arbitrary nature of selecting the melt content of
the coke filter cake/ and

        2.  the assumption that the cake must be discarded due to
the rejection of heavy metals.

        The carbonate makeup costs presented in Table 5-1 are arbi-
trary due to the lack of sufficient test data to establish a basis
for analysis.  Pilot plant work is definitely dictated to establish
a firm basis for evaluation.

        If the pilot plant work can demonstrate a reduction in the
melt content of the fly ash filter cake it may change the justifi-
cation for a 99.5 percent efficient electrostatic precipitator and
a lithium carbonate recovery process.

        Decreasing the melt loss with the coke filter cake may also
affect the decision to include the lithium carbonate recovery proc-
ess.

        The use of salts other than carbonate for makeup should be
investigated.  Potassium sulfate is less expensive than the car-
bonate and could possibly be added at an appropriate point in the
process.

    g.  Carbonate Recovery

        1.  Lithium Carbonate Recovery

            The justification for a lithium carbonate recovery
                                                    SINGMASTER & BREYER
                               5-21

-------
 process is  described in Section 6,  Paragraph f.   However,  its
 justification may not be valid if melt losses can be  reduced in
 the fly ash and coke filtration steps  (See  Section  5, Paragraph f) .
 The process will have to be developed  to  determine  recovery data
 and design  parameters.

         2.   Potassium and Sodium Carbonate  Recovery

             The potassium and  sodium carbonate makeup requirements
 are listed  in Table  5-1 of Section  5,  Paragraph  f.  Except for
 ^2^03  needed to react with chlorides,  the makeup requirements are
 arbitrary due to the nature of the  assumptions of the melt losses.

         In  all evaluations,  it has  been assumed  that  the potassium
 and sodium  salts are not recovered  after  the aqueous  lithium car-
 bonate recovery process because:

         1.   The fly  ash filter cake contains the KCl  which is sol-
 uble along  with the  other potassium and sodium salts, and

         2.   The coke filter  cake  contains the heavy metals which
 are removed along with the soluble  potassium and sodium salts.

         The discarded sodium and  potassium  salts are  mixtures of
 carbonates,  sulfites,  sulfates,  and sulfides in  addition to the
 potassium chloride.

         The annual cost for  K2CC>3 makeup  to compensate for the
 mixed  salt  loss,  excluding that required  to react with the chlo-
 rides,  is $399,000?  for Na2CC>3,  it  is  $112,000.   With a capital-
 ization  charge  of 14 percent,  over  $3  million can be  spent for a
 process  plant  to recover potassium  and sodium salts.

         Ion  exchange is a possible  process  for removal of  the
 chlorides reporting  with the fly  ash filter cake.   The remaining
 salts  can be recovered  by evaporation  using the  waste heat avail-
 able in  the Molten Carbonate Process.   The  recovered  salt  can be
 analyzed for  its  constituents  and fresh sodium,  potassium  and
 lithium  carbonate added to prepare  the proper ratio of the eutec-
 tic for  recycle  to the  Molten  Carbonate Process.  The effect of
 any soluble heavy metals  on  ion exchange  will have  to be deter-
mined by test work.   The  justification for  a process  to recover
potassium and  sodium salts will have to be  evaluated  after pilot
plant work  establishes  melt  composition and losses.
                               5-22

-------
        The salts that are discarded may result in a water pollu-
tion problem.  Recovery may be necessary to minimize this poten-
tial problem.  In this study, it has been assumed that the salts
are discarded with the fly ash from the electrostatic precipitator.

    h.  Waste Heat Recovery

        The Molten Carbonate Process provides substantial sources
of heat that must be rejected to maintain the thermal balance of
the plant.

        To maintain melt at 850°F in the base case plant, approx-
imately 15 million BTU's per hour must be removed (approximately
50 million in the reducer quench system and 25 million in the re-
generator coolers).  If this heat is valued at 30C per million BTU,
the annual value of recoverable heat is approximately $138,000.

        It is possible that these streams could be cooled by a
portion of the boiler flue gases exiting the air heater  (approx-
imately 350°F).  The boiler flue gases could be reheated to a
temperature of 600-650°F and be returned to the air heater sec-
tion of the boiler for recovery of the waste heat.  This scheme
was not considered in the evaluation because of the plan to
separate the Molten Carbonate Process from Power Plant operations.

        An alternate to this scheme is to reject the process heat
to a lower freezing ppint cooling medium, such as DuPont Hi Tec,
and recover the heat from the medium by generation of low pres-
sure steam.  This too was not considered because there is no need
for low pressure steam in the process except at the Regenerator
and this was presumed to be available from the waste heat boiler
in the Claus Plant.  The power plant would probably have no need
for any low pressure steam.

        Steam can be generated directly by using waste heat
boilers to cool the process melt.  However, in order to reduce
the possibility of freezing the melt, high pressure boilers are
needed; and it is questionable whether this high pressure steam
would be at a pressure satisfactory for use in the Power Plant.

        Air cooled exchangers were selected for use in the
capital cost evaluation for ease in control and low capital cost.
These exchangers are bare tube units with external air bypassing
                                                    SINGMASTER & BREYER

                              5-23

-------
 to  minimize  the  possibility of  freezing  the melt.  They do not
 recover waste heat.

        The  recovery  of waste heat  from  the process by some alter-
 nate  scheme  must be thoroughly  evaluated at the time the process
 is  considered for  installation  in a power plant or smelter.

    i.  Integration into  Existing Power  Plants

        In existing coal-fired  power plants, a low temperature.
 electrostatic precipitator  is generally  located after the air
 heater.   In  order  to  integrate  the  Molten Carbonate Process into
 existing  plants  the flue  gases  must be reheated to the absorber
 temperature  or alternatively withdrawn from before the economizer
 and a new high temperature  electrostatic precipitator installed.

        In most  power plants, space is at a premium and it will
 be  difficult to  install a large size duct to feed a new high tem-
 perature  precipitator.  The  problem is compounded because a return
 duct  from the absorber to the boiler will also be required.

        The  breechings into  most boilers can be accommodated by
 making modifications to the  boiler  internals.  The return of fly
 ash free  flue gas  to the  boiler will permit smaller extended sur-
 faces to  be  used for the  economizer and  air heater sections rather
 than bare tube sections.  A  boiler  manufacturer has estimated
 that  this modification including breechings, but excluding duct-
 work will cost $1,000,000 and take  ten weeks to install.

        A comparison of the  costs of integrating the Molten Car-
 bonate Process into an existing hypothetical 800 MW power plant
 is  presented in  Table 5-2.   The data are based on the results of
 the investigation  on "The Optimum Location of the Electrostatic
 Precipitator in  the Process" (Section 6,  Paragraph a).

        The  capital costs include the new high temperature elec-
 trostatic precipitator, modification of  the boiler to accommo-
 date the  large breechings, and  the  indirect exchanger to retain
 the existing low temperature electrostatic precipitator.  It
 excludes:

        1)  the  combustion chamber  for the retention of the ex-r
 isting low temperature precipitator because vendors of this type
of  equipment declined to provide estimating prices.
                              5-24

-------
  Table 5-2.  Comparative Cost for Integration into Existing
                            Power Plant
Precipitator
      Existing Low
Temperature Precipitator
   (99.5% Efficient)

         Existing,assumed
         to be amortized
Indirect Exchanger
  Installed Cost
  excluding Combustion   1,950,000
  Chamber

Boiler Modifications  ;
New High Temperature
Precipitator (99.5%
	Efficient)

     3,240,000
                                 1,000,000
  Total                  1,950,000
                                 4,240,000
Annual Costs

Capitalization Charge      273,000

Power for Precipitator      90,000

Power for Indirect
  Exchanger Pressure Loss  128,000
Fuel for Reheat
  (100°F Rise)
  Total Comparative
    Annual Cost
             429,000
             920,000
                                   594,000

                                   149,000
       743,000
                              5-25
                                                   SINGMASTER S BREYER

-------
         2)   ductwork costs.

         3)   modification  or  new boiler  fans  to overcome  increased
pressure loss.

         4)   fly  ash  disposal equipment  for the new high  tempera-
ture precipitator.   It  is assumed that  this  equipment can be
salvaged from the abandoned  low temperature  precipitator.

         5)   scrap and salvage value  of  the low temperature pre-
cipitator if a new high temperature  unit was installed.

         The  operating cost excludes:

         1)   capitalization charge for the existing low tempera-
ture electrostatic precipitator.   It is assumed to be amortized.

         2)   power required to overcome  the combustion chamber
pressure drop if the existing precipitator were retained.

         3)   plant downtime to make internal  boiler modifications
or connections to a  reheat system.

         For  the hypothetical case, the  installation of a new
high temperature precipitator results in a lower annual  cost.
However,  the integration  of  the Molten  Carbonate Process using
this method  into existing power plants  will  depend on the space
available  in the plant  and,  the ability to make the necessary
boiler modifications.   Each  plant must  be individually analyzed
for the  best way to  integrate the process.

    j.   Copper Smelter

         The Molten Carbonate Process shows promise for removal of
SC-2 from copper smelter reverberatory furnace flue gases.  It has
not been considered  for use  with  roaster off-gases because of the
high SC-2 content of  the gases which  can be utilized in a conven-
tional contact acid  plant.   The process has  not been considered
for removal of SC>2 from converter  off-gases  in this study.  The
converter operations  are  of  a  cyclic nature  and some smelters stag-
ger the blow of the  converters to  reduce the cycling so  that the
gases can be fed to  an  acid  plant.   However,  it is possible that
the process can be applied to  such a cyclic process where the gas
                              5-26

-------
flow and SC>2 concentration varies by designing the absorber
system for the extreme gas condition and the remainder of the
process for an average melt flow.  Additional melt surge capac-
ity may be required as a "fly wheel" to compensate for the S02
variation in the gas feed.

        The location in the reverberatory furnace process scheme
where the off-gases should be withdrawn for removal of SC>2 will
depend on the actual plant under consideration.  If the gases
are taken for removal of S02 after an existing low temperature
bag house or electrostatic precipitator then they will have to
be reheated to absorber temperature.  Alternately, the gases
may be taken after the waste heat boiler operating at 800-850°F
and sent through a new high temperature electrostatic precip-
itator.  The point at which the gases should be withdrawn and
how they should be treated to provide the necessary absorber
temperature is discussed in Section 6, Paragraph g.

        The problems that may be encountered in the Molten Car-
bonate Process if it were applied to a copper smelter are es-
sentially those that would be encountered in the power plant
case discussed in previous paragraphs of this section of the
report.  The basic difference between the two, other than SC>2
concentration, is in the contaminants in the gases that are to
be treated.

        Besides a higher SC>2 content of the reverberatory fur-
nace off-gas, these gases may contain fluorides which may react
differently from the chlorides present in power plant stack
gases.  The effect of this contaminant on the process must be
determined.

        Another contaminant present in the gases is the heavy
metals in the fume and particulate matter that is not collected
in the bag house or electrostatic precipitator.  If these are
absorbed in the process melt they will have to be removed at
the point where they concentrate.  This may be at the filter
after the absorber (termed "the fly ash filter" in the power
plant case) or at the coke filter, or elsewhere.

        The particulate matter that is not removed in the bag
house or electrostatic precipitator is different from power
plant fly ash.  Tests would be necessary to determine its
                                                    SINGMASTER S BREYER

                              5-27

-------
filtration characteristics if it had to be filtered.

        The effect of these contaminants on the Molten Carbonate
Process would have to be determined in a pilot plant  program uti-
lizing actual smelter gases.
                             5-28

-------
6.  ECONOMIC STUDIES

    Various economic studies  (tradeoffs) were performed to

     (1)  select the optimum equipment or process scheme,
     (2)  evaluate the necessity for a process operation,
such as lithium carbonate recovery, and
     (3)  establish the lowest cost raw material, such as
the type of coke to use for reduction.

    The results of a pilot program may establish the need
for additional tradeoff studies.  Anticipated future studies
are:

    1.  Recovery of waste heat from process melt or gases
in a fully integrated plant consisting of Power Plant or Copper
Smelter, Molten Carbonate Plant, Lithium Carbonate Recovery
Plant and a Glaus Plant (see Section 5, Paragraphs c and h)„

    2.  Recovery of sodium and potassium salts from waste
streams presently discarded  (see Section 5, Paragraphs g).

    The economic evaluations performed for this study are
contained in this section of the report.  All evaluations un-
less otherwise stated assumed the following:

    a.  base case power plant of 800 MW capacity burning coal
containing 3 percent sulfur and 0.04 percent chlorides and oper-
ating at a 70 percent plant factor.

    b.  an annual capitalization charge of 14 percent of the
installed cost.

    c.  Utility Costs

        Fuel  -  $0.04/million BTU
        Steam -  $0.05/million BTU from the power plant
        Steam was assumed available from the Glaus Plant at no
charge.  No credit to be allowed for export of steam.

        Power -  6 mills/KWH
    Other assumptions relating to the specific evaluation are in-
dicated for each subject.
                                                    SINGMASTER S BREYER

                               6-1

-------
     a«  Optimum Location of the Electrostatic Precipitator
                      in the Process

         Current practice for removal of fly ash in coal-fired
power plants is to locate an electrostatic precipitator operating
at about 300°F after the air heater.  At this temperature it will
be necessary to reheat the gases to obtain the required 850°F
operating temperature of the absorber in the Molten Carbonate Pro-
cess.

         To eliminate reheat, high temperature gases can be
removed from an appropriate point in the boiler and directed
through an electrostatic precipitator before being sent to the
absorber.

         An evaluation was performed to compare the cost of a
high temperature electrostatic precipitator to a low temperature
electrostatic precipitator at different efficiencies.

         In the high temperature case, flue gases are removed from
the boiler before the economizer at a temperature of 850°F.  The
gases pass through the electrostatic precipitator to the absorber
and are returned to the boiler at the economizer.  The temperature
of the gases at any withdrawal point in the boiler will vary de-
pending on the load.   It may be necessary to provide facilities at
the boiler to overcome serious temperature fluctuations that may
affect the absorber.   These facilities are beyond the scope of this
study and have not been considered.

         The process schemes for the above precipitator locations
are shown in Figure 6-1.
                                6-2

-------
             FIGURE 6-1.   ELECTROSTATIC PRECIPITATOR LOCATION
     RETURN TO
                         850 °F
     BOILER
FROM BOILER
  @ 850 °F
ELECTROSTATIC

PRECIPITATOR..
                                   850
                                             ABSORBER
                HIGH TEMPERATURE ELECTROSTATIC PRBCIPITATOR
FLUE GA
  350
         ELECTROSTATIC

         PRECIPITATOR
  TO STACK
                INDIRECT
               EXCHANGER
                    430 °F
                                               850 °F

                                            FUEL
                                      AP = 11 INCHES HoO
                                      (5.5 INCHES EACH SIDE)

                    TEMPERATURE ELECTROSTATIC PRECIPPTATOR

COMBUSTION
CHAMBER
850^.



                                                               SINGMASTER S BREYER
                                       6-3

-------
     Estimated  equipment  costs  for  the two cases were obtained
 from vendors and  utility cost  estimates were calculated from
 data provided  by  the vendors.

      The evaluation of capital costs include only the electro-
 static precipitator and  indirect exchanger  for the low temperature
 case.  It excludes:

      1)  The combustion  chamber for the low temperature case
 because vendors of this  equipment  declined  to provide esti-
 mating prices.

      2)  Increased costs for larger ductwork in the high tem-
 perature case which may  be offset  by more extensive ductwork
 in the low temperature case,
       "i*
      3)  Increased cost  o£ large size boiler breechings in the
high  temperature  case which mayi be offset by the reduced cost of
 the boiler economizer and air heater because of the return of clean
 flue gas.

     4)  Precipitator fly ash disposal equipment which will be
 the same for both cases.

     The operating, costs for the  low temperature case exclude
 the power required to overcome  the combustion chamber pressure
drop.

     The evaluation,  summarized in Table 6-1,  clearly shows that
the high temperature electrostatic precipitator results in a lower
annual cost.  The excluded items listed above economically favor
the low temperature electrostatic precipitator scheme.   As a re-
sult, the high temperature electrostatic precipitator has been
used in the study of the overall process.

      A further study was performed to determine the optimum effi-
 ciency of the  precipitator.  This  study is  discussed in Section 6,
 Paragraph b.                                   *
                               6-4

-------
                       Table 6-1.  Comparative Costs for Location of Electrostatic Precipitator
I
en
   I
   I
                                                    Low Temperature (325°F)

                                                       Efficiency

                                                    99         99.5        99.9
                  Precipitator Installed Cost  $1,640,000  $1,980,000  $2,740,000
Indirect Exchanger Installed
 Cost excluding Combustion
 Chamber

Total Installed Cost

Electrostatic Precipitator
  Power Requirements, KWH

Indirect Exchanger Pressure
  Loss, in
                                                1,950,000   1,950,000   1,950,000
                                               $3,590,000  $3,930,000  $4,690,000

                                                    2,070       2,440       3,650
Reheater Fuel Requirements,
  Million of BTU/Hr.

Annual Costs.$

Capitalization Charge

Power for Precipitator

Power for Indirect Exchanger
  Pressure Loss
                                                       11
                                                      175
                                                 11
    175
                 11
                                                            175
                                                  503,000

                                                   76,000

                                                  128,000
550,000

 90,000

128,000
                                                        657,000

                                                        134,000

                                                        128,000
Fuel for Reheat (100°F Rise)    429.000     429.000     429.000

Total Comparative Annual     $1,136,000  $1,197,000  $1,348,000
  Cost
                                                                      High Temperature (850°F)

                                                                          Efficiency

                                                                     99          99.5        99.9
                                                                 $2,672,000  $3,240,000  $4,448,000
                                                                 $2,672,000  $3,240,000  $4,448,000

                                                                      3,470       4,050       4,700
374,000     454,000     623,000

128,000     149,000     173,000
                       $502,000    $603,000    $796,000
   i

-------
    b»   Electrostatic Precipitator Efficiency & Penalties

         The efficiency of the electrostatic precipitator controls
 the amount  of fly ash that is carried with the flue  gases  to  the
 absorber.   The fly ash which is  not removed in the precipitator is
 removed in  the absorber by the molten carbonate and  is  subsequently
 filtered and discarded from the  melt before the reduction  step.

         The fly ash filtration tests carried but :by  Atomics In-
 ternational used a wedge  wire-wound filter element of 25 micron
 spacing.  They showed that the filter cake contains  65  percent
 melt  and 35 percent fly ash.

         A study was performed to determine the optimum  efficiency
 of the  high temperature electrostatic precipitator to minimize the
 costs associated with melt loss  in the  fly ash filter cake.

         The evaluation was based on the following assumptions:-

         1.   The filter provides  a dry cake discharge -  i.e. no
 melt  is carried along with the fly ash  greater than  the 65 percent
 melt  content of the filter cake.

         2o   Chlorides present in the flue  gas reacts with K2003 to
 form  KCl which is slightly soluble in the  melt.  The insoluble KCl
 is removed  from the process with the fly ash filter  cake.  Therefore,
 filter  installed costs -were not  considered for fly ash  removal since
 a substantial portion of  its  cost is attributable KCL filtration.
 fhe melt loss associated with KCL content  of the fly ash filter cake
was not considered  in evaluating the efficiency of the  electro-*
 static  precipitator since  it  would be a constant at  the different
 efficiencieso

        3o   Lithium salts  can be  partially ^recovered from the dis-
 carded  filter cake  in an aqueous  process as  presently conceived un-
der the following conditions:

             (a)   soluble lithium salts  react with soluble carbon-
ate salts to  form insoluble lithium  carbonate.

             (b)  twelve percent of the  insoluble lithium carbon-
ate cannot be recovered in  the process.

             (c)  delivered  cost  for Li2CC-3 -  $0.42 per  pound.
                                 6-6

-------
    4.  All sodium and potassium salts are lost in the aqueous
lithium carbonate recovery process as presently conceived. De-
livered cost for replacing the salts are:

        K2CO3  -  $0.096 per pound.

        Na2CO3 -  $0.028 per pound.

    The results of the tradeoff study for four high temperature
precipitator efficiencies are summarized in Table 6-2.  The
least annual cost unit falls somewhere above the 99 percent
efficiency with 99.5 percent being the lowest of the four cases
studied.

    For purposes of the process evaluation, the 99.5 percent
efficient high temperature electrostatic precipitator has been
selected as the basis for comparison to precipitator equipment
normally found in a power generating station without an S02 re
covery process.

    Existing power plants generally have located the precipitator
in the flue gas stream after the air preheater.  Consolidated
Edison's Ravenswood No. 30 unit is an exception to this rule.
Selection of the efficiency of the precipitator is based on
existing local codes and no general rule can be applied to
define the typical efficiency.  It is very likely that power
plants will be faced with more stringent fly ash control in the
future.  An efficiency of 99 percent for a low temperature elec-
trostatic precipitator in a power plant without an S02 recovery
system has been selected as the basis for determining the penalty
that must be applied to a 99.5% efficient high temperature pre-
cipitator when installed in a power plant burning 3 percent sulfur
in coal.  Table 6-3 compares these costs and lists a $1,600>000
capital cost penalty that has been applied to the Molten Carbon-
ate Process for use of the more efficient and higher temperature
electrostatic precipitator that the process requires.

    At high electrostatic precipitator temperatures, the resis-
tivity of the dust in the flue gases is not affected by the SC>2
content in the gas and the size, price, and power requirements of
a precipitator are the same for the same efficiency.  This is not
the case at lower temperatures.  A larger size unit is required
for a low temperature precipitator in a power plant burning coal
containing one percent sulfur than is required for burning coal
containing three or six percent sulfur at the same efficiencies.

                                                     SINGMASTER S BREYER
                                 6-7

-------
 Table 6-2.   Melt  Losses Attributable  to Electrostatic
Precipitator Efficiency
Precipitator

Precipitator Installed
Cost
Precipitator Power
Requirements, KW
Fly Ash to Filter, #/Hr.
Equivalent Carbonate
Losses, #/Year
Li C03 (0.067 #/# fly
ash
K2C03 (0.611 #/# fly
ash)
Na2C03 (0.573 #/# fly
ash)
Annual Costs, $
Capitalization Charge
Power
Li2C03 Replacement
K£C03 Replacement
Na2C03 Replacement
Total Annual Cost:
95
$2,000,000*
1,600
2,250
925,000
8,430,000
7,906,000
280,000
59,000
389,000
809,000
221,000
$1,758,000
99
$2,672,000
3,470
450
185,000
1,686,000
1,581,000
374,000
128,000
78,000
162,000
44,000
$786,000
Efficiency
99.5
$3,240,000
4,050
225
93,000
843,000
791,000
454,000
149,000
39,000
81,000
22,000
$745,000

99.9
$4,448,000
4,700
45
19,000
169,000
158,000
623,000
173,000
8,000
16,000
4,000
$824,000
*  Based on A.I. Data
                                      6-8

-------
    Table 6-3.
Molten Carbonate Process Electrostatic
      Precipitator Penalty

          Precipitator
Precipitator
 Installed Cost

Power Consumption
 KW   .   •    .   .

Annual Cost, $
 Capitalization
 Charge

 Power Cost

 Total Annual Cost

 Mills/KWH
       Low
    Temperature
         99%

    $1,640,000
         2,070



       230,000


        76,000

       306,000

         0.062
                                      High
                                   Temperature
                                   	99.5%
               Penalty
$3,240,000   $1,600,000
     4,050



   454,000


   149,000

   603,000

     0.123
  1,980



224,000


 73,000

297,000

  0.061
                                6-9
                                                     SINGMASTER S BREYER

-------
     Table  6-4  lists  the  estimated  installed costs obtained from
 an electrostatic precipitator vendor  for units in an 800 MW plant
 operation   at  different  efficiencies  with 1,3 and 6 percent sul-
 fur in  coal.   These  prices were used  for determination of the
 panalties  to be applied  to the alternate power plant cases.

     c.  Absorber-Size/ Number, Configuration

     The absorber is  the  key  element in the Molten Carbonate
 Process, for it is here  that the sulfur dioxide in the flue
 gas is  scrubbed with the circulating  molten salts.

     Atomics International has expended a good deal of effort
 on experimentation in this area, and  came to the conclusion
 that a  spray tower where the superficial gas velocity is 25
 feet per second and  an average droplet size of 100 microns will
 give a  sulfur  dioxide removal efficiency above 95 percent.

    We  have selected four absorbers,  one per electrostatic pre-
 cipitator.  It is possible to design  for two (or maybe even one)
 absorber, but  we have selected four for the following reasons:

     1.  Duct manifolding becomes complex if there are fewer
 absorbers than precipitators.

     2.  Absorber diameters become quite large if the number
 is  less than four.

     3.  One absorber per electrostatic precipitator gives ad-
 equate  scrubbing ability if  one absorber is out of service.

    The diameter of  each of  the four  absorbers,  based on the
 superficial gas velocity being maintained at 25 ft/sec, is
 28' -6".

    The straight height has been estimated at 34 feet,  made
up as follows:
    2' clearance at bottom.
   11' size of gas inlet connection.
   15' active section,  to inlet spray nozzles,
    3' from spray nozzles to top of deraister.
     3'  top clearance.
                           6-10

-------
  Table 6-4.  Estimated  Installed Cost of Electrostatic



Temperature, °F
350
350
350
350
350
350
350
350
350
850
850
850
Precipitators


S in Coal,%
1
1
1
3
3
3
6
6
6
1,3,6
1,3,6
1,3,6
for 800 MW Power Plant


Efficiency,%
99
99.5
99.9
99
99.5
99.9
99
99.5
99.9
99
99.5
99.9
Estimated*
Installed
Cost, $
2,700,000
3,280,000
4,200,000
1,640,000
1,980,000
2,740,000
1,520,000
1,920,000
2,680,000
2,672,000
3,240,000
4,448,000
* Excludes - ductwork  and fly ash removal equipment.
                                                      SINGMASTER & BREYER




                                6-11

-------
     Type 347 stainless steel has been selected as the material
 of construction, with an allowance for 5" of external insulation.
 This method of construction is ideal from a process standpoint,
 since 347 SS is corrosion resistant to melt below 1000°F and the
 use of external, low conductivity insulation minimizes the heat
 loss.  However, the cost of an all 3_47 SS unit is quite high, so
 other possible construction methods were examined.

         In general, whenever one speaks of a costly stainless
 steel piece of equipment, one is tempted to try using carbon steel
 with a stainless steel cladding.  This approach will not work here
 since, with external insulation, the metal temperature will approach
 melt temperature,  which would be, as a design value, 95QP&. At such
 temperatures,  the stress value of low carbon steel, or low alloy
 steel, is too low.

         Stainless clad steel construction was considered but re-
 jected since the allowable stress in the carbon steel section at
 950°F is so low as to force the use of a very heavy steel plate.

         The next approach is to find a lining material which will
 reduce the metal temperature to the acceptable range for carbon
 steel.  The ideal substance to use would be a low thermal conduc1-
 tivity material such as that used for external insulation.   Un-
 fortunately,  there are,  at present no known low thermal conduc-
 tivity insulating materials which are compatible with the lithium
 carbonate - sodium carbonate - potassium carbonate melt.

         A high alumina brick,  such as Alundum,  is compatible with
 melt,  but has  a relatively high thermal conductivity.   The low con-
 dictivity insulation cannot be used in conjunction with the Alundum
 for the following reasons:

         1,   If the insulation is external,  (melt-Alundum-metal-
 insulation)  the metal temperature will be too high for carbon steel.

         2.   If the insulation is internal,  (melt-Alundum-insulation-
 metal)  the melt can be expected to seep through voids in the Alundum,
 and come into  contact with the insulation with which it is  not com-
patible.
                               6-12

-------
    •This situation is similar to the reducer, as discussed in
Section 6, Paragraph d.

    The alternate to an all 347 SS unit, then, is a carbon
steel or low alloy steel vessel, lined internally with Alundum
only.  A 9" layer of Alundum was investigated as a lining in a
vessel with a low alloy steel shell and floor.  Type 347 SS was
selected for the roof because of anticipated problems with brick
lining.  The diameter of metal shell was 30' to maintain a 28'
-6" inside diameter for gas velocity considerations.

    An absorber constructed in this manner has a much greater
heat loss than an all 347 SS unit with external insulation -
4,000,000 BTU/hr. vessel vs. 407,000 BTU/hr. per vessel.  In
calculating comparative annual costs for the two methods of con-
struction, it has been assumed that the difference in heat loss
would be evident at the power plant, and a value of $.30/million
BTU was allowed.

    Table 6-5 lists the comparative costs of the two types of
absorbers and shows that the units constructed of Type 347 SS
are less expensive.

    There are also problems of a practical nature associated
with theAlundum lined case.  As pointed out previously, ex-
ternal insulation cannot be used in this case, and the metal
temperature would be about 400°F.  This is a dangerous situation,
and great care would have to be exercised in the design of stairs,
operating platforms, connections, etc.

    In the Alundum lined case, about 10% of the capital cost
can be saved if low alloy steel is replaced by low carbon steel.
This would not be enough to change the conclusion.  Furthermore,
it is questionable whether it would be sound to use low carbon
steel here, since localized hot spots could cause the metal tem-
perature to be too high for low carbon steel.

    d.  Reducer - Size, Number and Configuration
        The basic parameters for design of the reducers are:
        Liquid Retention Time    -  20 minutes
        Static Depth of Melt     -  2-3 feet
        Superficial Gas Velocity -  3 FPS
        Bed expansion            -  100% maximum


                                                     SINGMASTER S BREYER
                               6-13

-------
     Table 6-5.  Absorber Costs
                A) Low Alloy Steel
                   w/9" Alundum
Case               internal Lining

Cost of Metal,
 per unit            $136,000

Cost of Alundum,
 per unit             220,000

Cost of Insulation
 per unit
Total Cost,
 per unit            $356,000

Annual Charge,
 per unit              50,000

Annual Value of
 Heat Loss,
 per unit               7,000

Comparative Annual
 Cost, per unit       $57,000

Comparative Annual
 Cost, 4 units       $228,000
B)  347 SS w/5"
   External Insulation
     $305,000
       27,000



     $332,000


       47,000



        1,000



      $48,000


     $192,000
                               6-14

-------
    Calculations of the vessel sizes required to accomplish the
above design parameters were performed for various multiple
units of vertical and horizontal vessels.  For each of the
multiple horizontal units, the lengths were kept constant at
a nominal 20' and the diameter calculated to give the required
retention time and superficial gas velocity.

    In calculating vertical units/ the height was kept constant
at 6', and the diameter changed to maintain the required resi-
dence time and gas velocity.

    In comparing the costs of the same number of vertical units
to the same number of horizontal units/ the vertical case
always results in a significantly higher cost.  This is due,
primarily, to the fact that vertical units have very large dia-
meters, compared to horizontal units and the thickness of the
vessel shell required to contain the pressure is substantially
greater.  For example, if 4 vertical units were used instead of
4 horizontal units, the diameters would be 18'-6" instead of
ll'-O", and the total weight of 4 units would be about 135,000
Ib. instead of about 50,000 Ib.  On this basis it was decided
to evaluate horizontal vessels for use in the reduction step.

    Several cases for horizontal vessels were evaluated, the
variable being the number of units.  As the n\imber of units
decreases, the diameters, of course, increase.  The total cost
of the units themselves remains about the same as the number
is decreased.  However, the overall cost of the installation
decreases as the number of units is decreased.  This is because
there are fewer foundations, less piping, etc.

    Four horizontal vessels were selected because with this
quantity the calculated diameters are ll'-O" which approaches
the limit for rail shipment and permits the vessels to be shop
fabricated.  It is desired to avoid, where possible, larger
diameter vessels and the need for field fabrication.

    The design temperature of the melt is 1500°F.  Many materials
of construction were studied, bearing in mind the following
considerations:
                                                    SINGMASTER S BREYER

                              6-15

-------
     1.   A fused cast alumina product,  such as Mono f rax, withstands
 melt at 1500°F.

     2o   A high alumina insulating material,  such  as Alundum can be
 used as back-up to the Mono f rax.

     3»   347 stainless steel is corrosion-resistant  to melt below
 1000°Fo

     4,   Silica containing  insulation products are not suitable
 against  melt.

     5.   Carbon steel or low alloy steel  is corrosion-resistant to
 frozen melt.

     The  selection  of Monofrax in  contact with melt  is based on work
 performed by Atomics International.  The selection  of the less
 expensive Alundum  as back-up will have to  be confirmed.

     The  first  reducer construction method  investigated was the
 "skull"  or cold wall concept in which sufficient heat is removed
 from the reducer by an external cooling  jacket to cause a thin layer,
 or  "skull",  of melt to freeze at  the surface.  This frozen layer of
 melt protects  a metal vessel wall.  This method would work if the
 inside coefficient of heat  transfer were low.  However, in an article
 called Designing Gas- Sparged Reactors by J.R. Fair  &' t it is re-
 ported that  inside coefficients in sparged vessels have been found
 to be very high, even with  relatively low  gas flows.  In the re-
 duction  step under consideration, air is provided to oxidize the
M^S to M2SO. and CO2 is produced by the reduction of M2SO4 with
carbon.  Applying the experience of this article to the design con-
ditions of the reducer result in an inside coefficient of heat
transfer on the order of 1000 BtuAr-ft2 -°F.

    This high heat transfer rate makes the "skull" concept imprac-
tical because of the large amount of heat to be transferred which
must be replaced by burning coke.  The heat to be transferred can
be calculated as follows:

    The effective area for heat transfer, in the liquid phase is
approximately 350 square feet for a reducer 11' diameter x 20'
long (based on inside of brick dimensions).  If a skull exists,
                               6-16

-------
it implies that a freezing temperature of approximately 750°
has been attained.  Therefore, the amount of heat transferred
from melt  (at 1500°F) to  skull  (at 750°) would be  (1500-750)
(1000)(350) = 260,000,000 Btu/hr for each of four reducers.
This amount of heat would, of course, also have to be trans-
ferred out of the vessel, and is much higher than can be
tolerated.  Furthermore,  the quantity of coke needed to main-
tain the reducer at the operating temperature is not economi-
cally practical.

    Other methods investigated involved the "hot wall" con-
cept, i.e. non-jacketed vessels with internal insulation,,
The first of the "hot wall" methods evaluated was a vessel
in which 4" Monofrax was  used against melt, followed by 4"
Alundum 4" silica insulation, and then the metal wall.

    This type of configuration gives a low metal temperature
(about 200°F) and a low heat loss  (about 100,000 Btu/hr per
vessel).  However, the temperature profile  (see Figure 6-2
is not satisfactory) because the freezing point occurs some-
what within the silica layer.  Consequently, melt may be in
contact with silica insulation because of the probable seep-
age of melt through Monofrax and Alundum causing attack on the
insulation.

    It will be seen from  Figure 6-2 that Monofrax and Alundum
are relatively poor insulators and result in low temperature
gradients.

    The next "hot wall" approach evaluated, was to use suffi-
cient thickness of Monofrax to lower the metal wall tempera-
ture permitting use of carbon steel.  With 24" of Monofrax
the wall temperature is approximately 500*5" and the heat loss
per vessel is about 800,000 Btu/hr.  This is a satisfactory
design to permit use of a carbon steel shell with only Mono-
frax in contact with melt but the cost of 24 inches of Mono-
frax lining is high.

    If, as has been assumed, the less expensive Alundum can
be used as back-up to Monofrax, then another possible method
of construction is suggested - a relatively small layer of
Monofrax in contact with melt, and then a layer of Alundum.
                                                    SINGMASTER & BREYER

                               6-17

-------
Figure 6-2,
Temperature Profile of
Reducer Internally Lined
with Monofrax, Alundum
and High Silica Insulation
1600
               6-18

-------
Figure 6-3.  Temperature Profile of
             Reducer Internally Lined
             With Monofrax  and Alundum,
             With Various Thicknesses
             of External Insulation
                                                SINGMASTER S BREYER
                          6-19

-------
 This was evaluated for 4"  Monofrax,  9"  Alundum»and various thick-
 nesses of external insulation.   The  temperature profiles  are
 plotted in Figure 6-3 which shows that  carbon steel can be used
 only if no external insulation  is used.   Thus,  we  see that a  low
 thermal conductivity insulating material  cannot be used as internal
 or external insulation.  If used externally,  it raises the metal
 wall temperature above the range of  carbon steel construction. If
 used internally,  it can be expected  to  come into contact with
 melt seepage and be attacked.    At present,  Atomics International
 are not aware of low thermal conductivity insulating materials
 which are compatible with  the melt at the operating temperature
 of the reducer.

     The proposed construction is for 4" of Monofrax and 9" of
 Alundum.   The material selected for  the reducer shell is ASTM A-
 204,  which is a  low alloy  steel that is somewhat more expensive
 than low carbon  steel, but retains usefuL stress values up to
 temperatures of  about 900°P.  The calculated temperature of about
 450°F is within  the useful range of  carbon steel,  but the use of
 A204 will allow  for localized hot spots.   (The  savings in using
 low carbon steel  instead of low alloy steel is  relatively small
 i.e.  in the order of 5-10% of the overall cost  of  the vessel).
 The heat loss is  expected  to be about 550,000 Bjtu  per hour per
 vessel.
                                                           \

     Neither Monofrax nor Alundum are completely free of voids
 or joints.   The possibility of  cracks developing in the lining
 cannot  be overruled.   The  performance of  these  refractories in
 freezing and thawing service remains one  of the areas for inves-
 tigation in a pilot plant.

     Table 6-6 shows the  development  of the capital cost compari-
 son for one reducer 11'  diameter by  20' which leads to the
 selection of the  "no insulation"  case.  The Monofrax and Alundum
would be  present  in all  the  cases, so the cost  is  not shown.
Aside from economic considerations,  the last  two cases above
 should be discarded because  the melt temperature in contact
with  the  347  SS is  too high.
                               6-20

-------
                  Table 6-6.  Reducer Construction
External Insulation

Metal Temperature, °F

Outside Temperature, °F

Heat Loss, Btu/Hr

Material of Construction
   None

    450

    450
950

300
  l"        2"

1,120*    1,270*

  250       200
550,000   300,000   210,000   120,000

  A 204    347 SS    347 SS    347 SS
Cost of Metal                  $11,300   $33,800   $33,800   $33,800

Cost of External Insulation    	0     1,000     1,600     2,500
Total Capital Cost
$11,300   $34,800   $35,400   $36,300
Annual Costs, $

Capitalization Charge

Cost of Coke to off-set
  Heat loss  (based on
  14,000 Btu/lb,$ll/ton Coke)


Comparative Annual Cost
1,600
1,400
4,900
800
5,000
600
5,100
500
 $3,000    $5,700    $5,600    $5,600
  Reject due to anticipated corrosion of vessel wall by melt.
                                                     SINGMASTER & BREYER
                               6-21

-------
     e.   Coke-Economic Aspects

         In Progress Report  No.  3,  Atomics  International  states
 "that almost any form of carbon can be  used  as  a reducing agent".
 Several materials were satisfactorily tested as available
 sources of carbon,  and an economic evaluation performed  by A.I.
 indicated that fluidized petroleum coke was  the least expensive
 source  of carbon.   ^Sreen delayed high sulfur petroleum coke was
 considered as another economically acceptable raw material.

         The present-day prices  for coke reflect, to some degree,
 the  energy shortage which is  now being  experienced.  Table 6-7
 compares the analysis and unit  prices of two forms of coke
 currently available.

         In the base case plant,  approximately 9 tons of  carbon
 are  required per hour to reduce the sulfate  to  sulfide.  This
 neglects any reducing agent advantage that may  occur due to the
 volatile content of the coke.   It  further  assumes that the heat
 of combustion of the  volatile matter is sufficient to satisfy
 the  increased heat  required to  vaporize the  free water contained
 in the  coke.   At a  plant factor of 70 percent,  the operating
 cost saying using delayed coke,  rather  than  fluidized coke,
 amounts  to $215,000 per year.

         The use  of  delayed coke  presents a minor handling
problem  that is  not present with fluidized coke.  In their re-
duction  experiments,  Atomics International used "as received"
delayed  coke of minus % inch.  Most delayed  coke producers do
not  screen coke  fines from their product,  which can be used in
the process; but instead sell their material  as indicated in
Table 6-7  at minus  2  inches with 50% minus %  inch.  It is
possible that this minus  2 inch  coke could be used for reduc-
tion; however  a  crushing and screening  circuit has been provided
in the facilities to  prepare material of the  size used in the
bench-scale work.  These  additional facilities  cost less than
$75,000 to  install, which is equivalent to an annual cost of
$10,500 using  14 percent  capitalization charges.  This is sub-
stantially  less than  the  savings realized by using the delayed
coke, thereby justifying  its inclusion  in  the process scheme.
If further experimentation proves  that  the minus 2 inch  material
can be used,  the crushing and screening circuit can be eliminated.
                               6-22

-------
     Table.6-7    Coke Comparison
                                              Green Delayed
                          Fluidized Petroleum    High Sulfur
                                Coke           Petroleum Coke
particle Size
Analysis (Dry Basis):
    Inerts
    Sulphur
    Volatile Matter
    Fixed Carbon

Water
                          96+% minus 8 mesh
                          0.6 wt.%
                          7
                          6
                         86.4

                          1 wt.%
Cost per ton/FOB works  $10.00

Allowance for Freight,   $5.00
  per ton

Delivered Cost per ton  $15.00
  of coke

Delivered Cost per ton  $17.36
  of carbon
  Minus 2 inch;
  50% minus h inch
  0.4 wt.%
  6
 12
 81.6

  5-8 wt.%

 $6.00

 $5.00


$11.00


$13.48
                                6-23
                                                      SINGMASTER S BREYER

-------
         Tests will be  required  to determine the effect of the
higher volatile  and water  content of the delayed petroleum
coke  on the  reduction  step.

         As a result of the above analysis, delayed petroleum
coke  at a; delivered cost of  $11,00 per ton has been used as
the basis in the operating cost determination; and, the
Engineering  Flow Diagram - Coke Handling Facilities, Drawing
No. PS-218-0003  is the basis for the capital cost of the
process.

         The  continued  availability of coke at these price
levels will  depend on  the  market demand.  Alternate low cost
raw materials should be investigated as sources of the carbon
required for reduction.  Coal is a possible alternate but
the ash content will add appreciably to the load on the coke
filter and may affect  the  reducer operation.

    f.   Li_CO  Recovery Process
          £•  -J

         The  filter cakes from the fly ash and coke filtration
steps  of the process retain  appreciable quantities of melt.
Experimental data indicate that the fly ash cake contains 65
percent melt while the coke  filter cake has been assumed to
contain 50 percent melt.

         In prior work, Atomics  International describes a
theoretical  aqueous process  in which 88 percent of the lithi-
um carbonate can be recovered.  In this study, an estimate
has been made of the value of the lithium carbonate that
can be  recovered by this process and was based on the follow-
ing assumptions:

         1)  KCl if formed  in the absorber by reaction of
the chlorides in the flue  gases with potassium salts.  Its
solubility is 3 percent in carbonate melt and any excess over
this solubility is removed with the fly ash in the fly ash
filter.
                               6-24

-------
    2)  The fly ash filter cake, containing the insoluble
KCl, has a composition of 65 percent melt and 35 percent
solidSo

    3)  The coke filter cake contains the heavy metals
and must be removed from the process.  It contains 50
percent melt.  The coke usage in the reducer and the
subsequent unreacted amount to be filtered from the
reduced melt is based on coke oxidation rather than M2S
oxidation to provide the reducer sensible heat and heat
of reduction.  MoS oxidation may require more coke for
reduction and therefore may also result in more un-
reacted coke to be filtered.  This is the subject of
a discussion in Section 6, Paragraph f.

    4)  Both the fly ash and coke filters provide a
dry cake discharge.

    5)  Soluble lithium salts react in the aqueous
phase with soluble carbonate salts to form insoluble
Li2CO  and is recovered to the extent of 88 percent.
Li CO  delivered cost is 42 cents per pound.

    The result of this evaluation for a high tempera-
ture  electrostatic precipitator operating at an
efficiency of 99.5 percent, is summarized in Table 6-8.
At other efficiencies, only the Li^CO  associated with
fly ash will be affected since the KCl and coke are
constant at the different efficiencies.

    The table lists the equivalent capital investment
required to recover the lithium carbonate contained
in the inerts.  An engineering flow diagram of the
tentative aqueous process was prepared and estimates
indicate that the installed cost for such a process to
recover the lithium carbonate from all sources would
be less than $500,000.  The justifiable capital cost
of the recovered lithium carbonate in the fly ash only,
is substantially greater than the $500,000 installed
cost of the process thereby justifying its inclusion
in the overall process scheme.
                                                    SINGMASTER & BREYER

                               6-25

-------
      Table  6-8.   Value  of I^CO-,  Recovered in
                  an Aqueous Recovery Process


                      Electrostatic Precipitator Efficiency

                                     99.5%

 Filter  Cake Inerts

 FlyAsh, #/Hr.                          225
 KC1,    #/Hr.                          403
 Coke,   #/Hr.                          800

        Recovery,  #/Yr,  From
FlyAsh,  (0.492#/#Flyash)          679,000
KC1,     (0.492#/#KC1)            1,216,000
Coke,    (0.308#/#Coke)           1,511.000

                       Total     3,406,000

Annual Value for Li2C03
Recovered From _

FlyAsh                           $285,000
KC1                               511,000
Coke                              635,000

           Total Annual Value
          of Recovered Li2CO3  $1,431,000

Justifiable Capital Investment
Required to Recover I^CO  From
FlyAsh                         $2,035,000
KCl                             3,650,000
Coke                            4.535,000

                       Total  $10,220,000
                                   6-26

-------
    The engineering flow diagram for the lithium carbon-
ate recovery process is shown on Drawing No. PS-218-0004
and is the basis for the capital costs used in the process
evaluation.    ,                       '

    The economics for inclusion of a lithium carbonate
recovery process should be reevaluated if the associated
melt losses can be reduced at the fly ash filter.

    g.  Copper Smelter

        The study of the removal of SO- from copper
smelter gases has been limited to those gases emanating
from reverberatory furnace operations only.  Roaster
gases contain high SO  concentrations and can be utilized
in conventional acid plants as can the converter gases.
The possibility of converter gases being used as feed to
the Molten Carbonate Process is discussed in Section 5,
Paragraph j.

        The treatment of reverberatory furnace gases for
removal of particulate matter varies considerably from
smelter to smelter.  The gases generally flow from the
reverberatory furnace through a waste heat boiler exiting
at temperatures ranging from 600°F to 700°F.  At this
point some smelters cool the gases to about 350°F by
dilution with ambient air so that a bag house can be used
to remove the particulate matter,  Current practice in
new plants is to employ electrostatic precipitators
operating at the 600°F-700°F temperature level for re-
moval of particulate matter.

        For this study, a hypothetical reverberatory
furnace has been selected that will produce 200 tons per
day of copper.  It has been assumed that the gases from
the furnace and waste heat boiler contain 2 percent S02
by volume with the equivalent of 50 tons per day of
contained sulfur.   -   .   •    •
                                                    SINGMASTER S BREYER

                              6-27

-------
     Several cases have been investigated:

     Case (a):  Integration of the Molten Carbonate  Process  into
 the hypothetical smelter with existing bag house filters by
 reheating the  350°F gas to 850°F by indirect  exchange  of heat
 with absorber  off-gas followed by direct combustion of fuel
 into the gas stream.

     Case (b):  The smelter has an existing  600°F electrostatic
 precipitator and the  off-gases must be reheated as in  Case
 (a).

     Case (c):  The gases from the waste heat boiler exit at
 800-850°P rather than 600-700°F and are passed through a new
 high temperature electrostatic precipitator.

     The  results  of the investigation are listed in Table 6-9.

     The  operating costs have been based on the following:

     1.   7920 hours per year  of operation(90%  Plant Factor).

     2.   Fuel costs for reheat in Case  (a)  and Case (b).

     3.   Penalty  at the value of equivalent fuel for Case
 (c) due  to rejecting heat  at the Waste Heat Boiler at  850°F
 rather than 700°F.  No benefit has been applied to the
 possible use of  the 850°F  absorber off-gas as a source of
 heat  in  a recuperator.

    4.   Power  costs for cases (a) and  (b)  include  in-
 creased  pressure  drop  for  the reheat system and absorber.

    5.   Power  cost  for case  (c)  includes the  increased
pressure  drop  for the  absorber.

    6.  The power  cost  attributable to the bag house pressure
drop in  case (a)   is approximately the  same as the  electron
 static precipitator power  costs  in cases (b)   and (c)  and
therefore these costs were not  considered.
                               6-28

-------
    The capital cost does not include any salvage or scrap
value for discarded equipment.  Nor does it include possible
new fans to overcome the increased pressure drop in cases
 (a) and (b).

    The evaluation shows that in the hypothetical smelter
with an existing bag house it is less expensive to abandon
the bag house and install a new electrostatic precipitator
operating at 800-850°F.  This is not true if the smelter
is equipped with an electrostatic precipitator operating
at 600°F;  it is then less expensive to install the reheat
system."           -

    The capital and operating costs for the application
of the Molten Carbonate Process for removal of S02 from
reverberatory furnace gases has been based on a smelter
equipped with an existing 600°F electrostatic precipita-
tor.

    The method that is to be employed to provide the
800°F-850°F gas to the absorber in the Molten Carbonate
Process must be re-examined when an actual existing
smelter is selected.
          >

    If a new copper smelter were to be considered, it
is clear that an electrostatic precipitator operating
at 800-850°F and a suitable resistivity would result in
lowest cost.
                                                    SINGMASTER S BREYER

                             6-29

-------
            Table 6-9.  Integration Into Existing Typical Copper Smelter
                          Reverberator^ Furnace Circuit
            Type


            Capital Costs

            Reheat System

            Electrostatic
             Precipitator
                       Case (a)

                   Reheat (Off-Gases
                   from Bag House
                   @ 350 °F)
                     $240,000

                   Not Required
cr»
u>
o
Absorber Cost & Size  100.OOP(14'-6"(

         TOTAL       $340,000
     Case (b)

Reheat (Off-Gases
from Electrostatic
Precipitator @ 600 °F)
$176,000

Existing, Assumed
 Amortized

  60^000(9 f-6l'0)

$236,000
    Case (c)

No Reheat (Off-Gases
at 850 °F through
new electrostatic
precipitator)
Not Required

$300,000


  60.000(9'-6"0)

$360,000
             Annual  Costs

             Capital Charges
              (14% of capital costs)47,000

             Fuel(40c/million BTU)  25,300
             Power (6mills/KWH)     14.400

                     TOTAL          87,300
                                           33,000

                                           13,100




                                             8,900

                                           55,000
                               50,400

                               23,300
                             (Penalty  for rejecting
                              waste  heat at  higher
                              temperatures)

                                2.200
                               76,900

-------
7.  EQUIPMENT - BASE  CASE  PLANT

    a.  List of Equipment

        1)  SOX Removal  and  Coke  Handling Facilities

  Tag Number                         Description

B-1A, IB, 1C, ID                Combustion Air Blower

B-2                             Filter  Displacement Blower

C-l                             Crusher

E-1A,1B                         Reducer Product Cooler

E-2A,2B,2C,2D                   Air-Oxidation Zone Exchanger

E-3                             (Not Used)

E-4                             Regenerator Bottoms Cooler

E-5                             Regenerator Intermediate Cooler

F-1A,IB                         Fly Ash Filter

F-2A, 2B'                         Coke Filter

G-l                             Transfer Conveyor with
                                Vibrating  Feeder

G-2                             Bucket  Elevator

G-3                             Coke Bucket Elevator

G-4                             Reversing  Conveyor

G-5                             Coke Belt  Conveyor with
                                Movable Tripper

G-5A                            Elevating   Belt Conveyor

G-6,7,8                         Dust Collectors
                                                   SINGMASTER & BREYER
                               7-1

-------
 G-9                          Carbonate: Bucket Elevator;

 G-10                         Eutectic Conveyor

 G-ll                         M2CO3  Silo Feed Conveyor with
                                     Tripper
 P-1A,1A(S),1B,1B(S)          Absorber Pump
   1C,1  (S) ,10,1
P-2A, 2A(S),2B,2B(S)          Reducer Pump

P-3,P-3(S)                   Regenerator Bottoms  Pump

P-4,P-4(S)                   Regenerator Intermediate Pump

P-5                          Makeup  Pump

S-l                          Screen

T-l,T-2                      coke  Silo

T-3                          Na2C03  Silo w/Dust Collector

T-4                          K2CO3  Silo w/Dust Collector

T-5                          Li2C03  Silo w/Dust Collector

V-1A, IB, 1C, ID                Absorber

V-2A, 2B, 2C, 2D                Absorber Pump Tank

V-3A,3B,3C,3D                Reducer

V-4A,4B                      Reducer Quench Tank

V-5                          Regenerator

V-6                          Regenerator Bottoms  Pump Tank

v-7                          Regenerator intermediate Pump

V-8A,8B,8C,8D                coke  Bin
                               7-2

-------
V-9

W-1A,1B,1C,1D

X-1A,IB,1C,ID

X-2

X-3
                             M2C03  Melt Tank

                             Coke Weigh Feeder

                             Electrostatic Precipitator

                             Instrument Air Compressor

                             Instrument Air Dryer
       2)


Tag Number

A-101

A-10 2


A-103

A-104


A-105


A-106

A-107


B-101

B-102

D-101

F-101


F-102
                  Recovery
                                   Description

                             Agitator for Dissolving Sump, T-110

                             Agitator for Fly Ash & Coke Slurry
                             Tank, T-101

                             Agitator for LiHCOs Reactor, V-101

                             Agitator for Fly Ash Filter Cake
                             Receiver, T-102

                             Agitator for LiHC03 Reactor Product
                             Surge, T-103

                             Agitator for Li2C03 Reactor, V-102
                             Agitator for Li2CO3 Reactor
                             Product Surge, T-104

                             Exhaust Fan

                             Hot Air Blower

                             Li2CO3 Dryer

                             Li2CC>3 Fly Ash Filter  incl.
                             Vacuum Pump

                             Fly Ash Filter incl. Vacuum  Pump
                                                   SINGMASTER S BREYER
                              7-3

-------
 F-103                        Li2CO3 Filter incl. Vacuum Pump

 G-101                        Redler Conveyor

 P-101,101(S)                 Dissolving Sump Pump

 p-102                        Soluble Salt Receiver Pump

 P-103,103(S)                 Fly Ash Goke Slurry Tank Pump

 P-104,104(S)                 LiHCOs Reactor Product Surge Pump

 p-105                        Li2C03 Reactor Transfer Pump

 p-106                        Li2CO3 Reactor Product Surge
                              Tank Pump

 P-107                        Li2CO3 Filtrate Receiver Pump

 P-108                        Li2CO3 Fly Ash Filter Cake Receiver
                              Pump

 P-109                        LiHCO3 Filtrate Receiver Pump

 T-101                        Fly Ash Coke Slurry Tank

- T-102                        Li2C03 Fly Ash Filter Cake Receiver

 T-103                        LiHCOs Reactor Product Surge

 T-104                        Li2C03 Reactor Product Surge

 T-105                        Surge Drum

 T-106                        (Not Used)

 T-107                        Soluble Salt Receiver

 T-108                        LiHCO3 Filtrate Receiver

 T-109                        Li2CO3 Filtrate Receiver

 V-101                        LiHC03 Reactor
                               7-4

-------
V-102                        Li2C03 Reaqtor

X-101                        Inert Gas Generator  including
                             Compressor

    b.   Specifications

         The specifications for major equipment required in
 the SOX removal process are attached to this section of the
 report.   Tftie specifications are of a functional nature rather
 than  a  detailed nature.
                                                 SINGMASTER & BREYER
                             7-5

-------
                Functional Specification for

            Combustion Air Blower B-lA,B,C*D
Number of Units

Gas Handled

Quantity Handled

Design Temperature

Operating Temperature

Suction Pressure

Pressure Difference
 Across Blower
-  4
   Atmospheric air

   6000 SCFM
-  150

-  Ambient
   (range 20 °F
-  Atmospheric

-  7 psi
-90 °F)
                                                   SINGMASTER & BREYER
                               7-6

-------
                Functional Specification for

             Filter Displacement Blower  B-2

Number of Units              -  1
Composition of Gas Handled
Quantity Handled

Design Temperature

Operating Temperature

Suction Pressure

Pressure Differential Across
 Blower
-  N2 - 75% by volume
   CO2- 13%
   H2P-  8%
   02 -  4%
   SO2-  Trace

-  150 ACFM

-  1000 °F

    850 °F

-   10" W.G. negative

    3 psi
        An alternative design would call for air heated
       by melt or electric heaters.
                                                   SINGMASTER S BREYER
                               7-7

-------
    Exchangers E-1A &  IB,  E-4  & E-5  specified hereafter are
to be the air-cooled type  with external air recirculation to
minimize freezing of the process liquid,  and intake air heat-
ing coils for start-up operation.
                                                   SINGMASTER S BREYER

                              7-8

-------
OtNERAL INOINCIRINO D'VI«.ON
,0«M M-S7     *-" «-'
 ITEM NO.   -
                                 HEAT EXCHANGER SPECIFICATION
                                     SINGMASTER & BREYER
                       VENDOR MUST COMPUTE THIS SPECIFICATION SHEET BEFORE RETURNING.
                       ITEM!  MARKED •  MAY BE OMITTED  UNTIL SELECTION OF VENDOR.
                             Reducer  Product  Cooler
                                                                  Req-a:    2  in  parallel
                                                                                SHEET NO.
                                                                                               REV.
                                                                               DATE    10-27-70
                                                                                             CHK'O
                                                                               JOB NO.  PS-218
 n,,TV  23.7X10°
                       _BTU/HR.    EXCHANGER TYPE:  HoHiz.. VERT.   Air-Cooled  "Fin-Fan"  Type
                                              MFRS. IDENT. NO.

TOTAL FLOW 	 LBS/HR
SHELL OR TUBE SIDE 	 	
LIQUID (EXCLUDING WATERJ 	 LBS/HR
DENSITY 	 LBS/CU FT
THERMAL COND.. .BTU/HR X SO FT X V/FT

VISCOSITY 	 CENTIPOISES



THERMAL CONO... BTU/HR X SO FT X "P/FT



STEAM 	 LBS/HR

ADDITIONAL DATA ON SHEET NO 	
OPERATING TEMPERATURES 	 V





roUL. RESIST 	 SOFT X HR X *P/BTU
MIN. CORROSION ALLOWANCE 	 IN.
NUMBER OF PASSES PER SHELL 	
FLOW ARRANGEMENT 	
Air

She

® 'r
9 'r
@ -F
® >
® V


® V
0.25 ®averv
® -F


0 v
A • B7
e v
a -P
e *P


e -P
« V
e 'P
a *F



850


CALC.

TEST
CALC,


EXCH. IN SERIES
TOT. ARIA (HOT! B) BO FT
CORRECTED MTD 	
TRANSFER RATE. CLEAN
SERVICE
CODE REQUIREMENTS.-..
REMOVABLE TUBE BUNDLE
FLOATING HEAD 	
IMPINGEMENT BAFFLE . . .
MATERIALS (MARK STRE9
TU*ES 	



TIC RODS • SPACER*. -

•HELL COVER 	

CHANNEL COVER 	
FLOATING HEAD COVER
REMARKS: * Me






AFI-ASME: TCMA
TES NO
cl*M»-nmc:run.TH»o
YES NO

• HELL (OR SECTS) TOTALNO.
I.D 	
TUBES, NO. PER SHELL. . . .
O.O. X
LENGTH 	

P-ITCM 	
TUBE LIMIT DIAM. OR WIDTH
WEIGHTS
EACH BUNDLE.. .
BUNDLE » SHELL 	
FULL OP WATER 	

S RELIEVED — S.R.. RADIOGRAPHED — X.R.)
Type 347 SS










THICK.. IN.
•
.
•
.
*
*
*
.
.
.

IN.

IN. X

IN.
AVE.. MIN. WALL
IN. A
no
IN.
LBS
LBS
LBS
NOZZLES (NOTE C)
|Hun. 	



RELIEF 	
CASKETS
CROSS SAFFLES. TTPE. .
NUMBER X
• PACING
.
SEGMENT CUT 	
TUBE HOLE
DIAM.. .
.
RADIAL CLEARANCE..
LONG BAFFLE
LENGTH ...
TYPE . .
•
DIST. ABOVE SHELL. .
REBOILER WCIR HEIGHT
SHELL AFTER WEIR. .
TUBE SJTC
SIZE









'

Lt Comoosition. Mol% Aorsrox.! Mif
__ FT-pp^inq Point 750°F
LOlA


RATING







X IN.

• IN.
• IN.

• IN.
IN.
IN.
FT.
SHELL SIDE
LIQ.


VAP. RATING




j


1.3: MoCO, 62.9:KC1 3.8

J

Quantities Listed are for One Cooler.

VOTE Al fO* CONDIN3EIIS *HO THCIMOSTFHCN »CIOIIC« PDCSSUIt D*OP ITATro fHAIL INCIUBI STATIC HtAD •tTWtlK CtNTCIlINC* OF INLET AMD OUTLET ritNCIS.
BOT( S: OUTSIDE TUIt AIEA E1CLUDINC A*tA IN TU1E SHEETS.          ~J _Q             DOTE Cl (ATE Pl» ASA f HE— !•>• 01 At A • Iftf — I Ml.

-------
           t*>HO DIVISION
           *-*• «-•
HEAT EXCHANGER SPECIFICATION
    SINGMASTER & BREYER
                                                                  4  Req'd  in  parallel
                                                                                SHEET NO. 2
                                                                                               REV.
                                                                                DATE
                       VENDOR MU»T COMPLETE THIS SPECIFICATION SHEET BEFORE RETURNING.
                       ITEMS MARKED  * MAY BE  OMITTED  UNTIL SELECTION Or  VENDOR.
                                                    1Q-27-70
        E-2A,B,
 ITEM NO.  CrD    SERVICE   Mr-Oxidation Zone  Exchanger	
 OUTY 4.5  10"	BTTU/HR.     EXCHANGER TYPE: HORIZ.. VERT.	Vertical
                                                  SD
                                                                                             CHK'D
                                              JOB NO.  PS-218
VENDOR MFRS. IDENT. NO.

TOTAL. Ft-OW 	 LBS/HR
SHEUL OR TUBE SIDE 	
LIQUID (CXCLUDIMO WATER) 	 LBS/HR
OENiirr 	 LBS/CU FT
THERMAL COND.. -»TU/HHJ X »OFT X 'F/FT
SPECIFIC HEAT 	 BTU/LB X V


MOLECULAR WE1OMT. 	 	
THERMAL CONO...smi/HR X "OPT X *F/FT


WATER ......-* 	 	 	 LBS/HR
ADDITIONAL, DATA ON SHEET NO 	
OPERATING TEMPERATURES 	 *F






MIN. CORROSION ALLOWANCE 	 IN.
NUMBER OF PASSES PER SHELL. 	
FLOW ARRANGEMENT 	
Air
23.850
Shell

@ V
® -F
a -r
9 V
e -F
23, 350
29
@ *F
0.242® Avg. v
<8 *F
® V
500


153
7


0 V
e v
e v
e v
« V


e v
« V
e v
e v



915°


ALLOW. 6"W-G. CALC,

MIN. ACTUAL 10 TEST
MIN. CALC.

i Gas*
i 25,500
i Tube

a v
e -P
® *F
« v
i @ v

: 30.3
« v
0~271 ® Avcr.v
« v
e v
325


! 1500



9 -r
9 *F
a *F
e v
O V


a v
« *F
a v
« v



850°


I ALLOW. 3PSI CALC.

MIN. ACTUAL TEST
' MIN. CALC.

li
PAR. BANKS OF EXCH. IN SCRIES It PAR. BANKS OF EXCH. IN SERIES
TOT. AREA (MOTE •) SOFT
LMTD 	 	 	

TRANSFER HATE. CLEAN
SERVICE
CODE REQUIREMENTS.-..
REMOVABLE TUBE BUNDLE
FLOATING HEAD. .......
IMPINGEMENT BAFFLE 	
MATERIALS (MARK STRES



TIE MOO* • SPACERS. .
•HELL 	

CHANNEL 	 	 	

PLOAT1MO HEAD COVER
REMARKS: * G<






API-ASME: TEMA
YES NO
ct»M-m»c:miLTMiiu
YES NO

SHELL (OR SECTS) TOTAL NO.
TUBES. NO. PER SHELL. • . .
0.0. X

GAUGE, BWa 	
PITCH 	
TUBE LIMIT DIAM. OR WIDTH
WEIGHTS
EACH BUNDLE...
BUNDLE ft SHELL 	



S RELIEVED — S.R.. RADIOGRAPHED — X.R.)
Type 347 SS










THICK.. IM.
.
.
,
.
.
.
.
.
.
.
NOZZL
INLE
OUT!
DRAI
VEN1
RELI

IN.

IN. X
IN.
AVE.. MIN. WALL
IN. A D O
IN.
LBS
LBS
LBS

CROSS BAFFLES. TYPE..
NUMBER X
SPACING
.

TUBE MOLE
DIAM.. .
.
RADIAL CLEARANCE..
LONG BAFFLE.
LENGTH . . .
TYPE. .
•
DIST. ABOVE SHELL. .
REBOILER WEIR HEIGHT
SHELL AFTER WEIR. .
TUBE SIDE
.ES (NOTE C) SIZE




EF 	
GASKETS



'

as Analysis (Mol%) CO-,-16.8; No-80.





RATING





5; H^O-2.

X IN.

• IN.
• IN.

• IN.
IN.
IN.
FT.
SHELL SIDE
LIQ.


VAP. RATING




1
3 ; Hydrocarb-0 .
— *- f.
Quantities Listed Are For One Cooler.
BOTI *l FOR CO1OCNSEM AND THCHIIOStPXON »ttOllt«S FUESSUIII OtOF ITtTTO *1ft-i INCLUDE STATIC HEAD KTWCtN CCNTCHLINCf OF INLET AHD OUTLET FIANCES.
•Oil »; OUTSmlTUM A»!A HCLU01N6 A«t» IN TU«£ SHtCTJ.          7~10   -         NOTE Cl SATE FCII ASA S III - lt» OK ASA S UII - II4>.

-------
iRiN<5 01 vi now
••»• *-'
           HEAT EXCHANGER SPECIFICATION

               SINGMASTER & BREYER
VENDOR MUST COMPUTE THIS SPECIFICATION SHEET BEFORE RETURNING
                                                         One Req'd
                                                                      SHEET NO.
                                                                                     REV.
                                                                      DATE  1 n-7_7-7D
ITEMS HARKED * MAT BE OMITTED UNTIL SELECTION OF VENDOR. BY SD :: CHK'D
ITEM NO. E-4 SERVICE Regenerator Bottoms cooler
DUTY J0xl0b BTU/HR.
VENDOR

TOTAL FLOW. . . 	 	 LBS/HH
•HELL OR TUBE SIDE 	
LIQUID (EXCLUDING WATER) 	 LBS/HR
DENSITY 	 LBS/CU FT
THERMAL COND... BTU/HR X SO FT X *F/FT
SPECIFIC HIAT 	 BTU/LB X *T



THERMAL COND... BTU/HR X SO FT X 'F/FT



ADDITIONAL DATA ON SHEET NO 	
OPERATING TEMPCHATURES 	 *F





FOUL. RESIST.. .... .SOFT X MR X *F/»TU

NUMBER OP PASSES PER SHELL 	
FLOW ARRANGEMENT 	
EXCHANGER TYPE:
JOB NO. PS-218
HORIZ.. VERT. Air-Cooled "Fin-Fan" Unit
MFRS. IDENT. NO.
Air

Shell

« -r
9 'F
@ -r
9 V
® 'r


& "r
® V
® *F
e -p



70°



a v
e . «P
e v
e v
e *p


c v
e v
« V
e «F






ALLOW. CALC.

MIN. ACTUAL TEST
MIN. CALC.


PAR. BANKS OF CXCH. IN SERIES
Molten Carbonates
300.000
i Tube

e v
e
Q.45 » Avg.v
: « V
e v

; 100 Appro:
« • >
T a v
e >
e v



1 925°



e v
e 'F
® v
« v
« V

<.
e >
« >
« *F
« *F



850°


1 ALLOW. 25 PSI CALC.

MIN. ACTUAL TEST
: MIN. CALC.


PAR. BANKS OF CXCH. IN SERIES
TOT. AREA (MOTE B> SOFT
CORRCCTCO MTD........
TRANSFER RATE. CLEAN
•OIVICX
OOOC RE.OUIREMENT9. . . .
•CMOVABLC TUBE BUMOLC
BfPINUCMCMT BAFFLE . . .
MATERIALS (MARK STRC5

BAFFLKB 	 	
TUBE SUPPORTS 	
TIC RODS • SPACERS..




FLOATIMO HEAD COVER
MEMARKS: Me






AFt.ASME: TCMA
TES NO

YES NO
SHELL (OR SECT!) TOTALNO.
TUBES, NO. PER SHELL. ...
O.O. X
LENGTH 	

PITCH 	
TUBE LIMIT DIAM. OR WIDTH
WEIGHTS
EACH BUNDLE...

FULL OF WATER 	
S RELIEVED — S.R.. RADIOGRAPHED — X.R.)
Tvpe 347SS










THICM.. IN.
•
•
•
•
•
*
•
•
*
*
NOZZl
INLE
OUT!

IN.

IN. X
IN.
AVE.. MIN. WALL
IN. A D O
IN.
LB3
LBS
L8S

CROSS BAFFLES. TYPE. .
NUMBER X
SPACING
.

TUBE HOLE
DIAM.. .

RADIAL CLEARANCE..
LON6 BAFFLE.
LENGTH . • .
TYPE. .
•
DI»T. ABOVE SHELL. .
REBOILER WEIR HEIGHT
SHELL AFTER WEIR..
TUBE SIDE
.ES (NOTE C) SIZE
T 	





RELIEF 	
CASKETS
.




It Composition, Mol% Approx: M-jS 1.
M9CO3 93.3; KCl 3.8; Freezing Point

RATING







X IN.

* IN.
• IN.

• IN.
IN.
IN.
FT.
SHELL SIDE
LIQ.


VAP. RATING



\



.6%; M7S04 1.3?
750°F



-

T AND OUTLET rLANCIS.

-------
                                                                                     One  Req'd
>L tNONEERINO DIV
«.„ «-»4 K-l
NO. E-5
- 1
5xlOb
HEAT EXCHANGER SPECIFICATION
1SION
SINGMASTER & BREYER
VENDOR MUST COMPLETE THIS SPECIFICATION SHEET BEFORE RETURNING.
ITEMS MARKED * MAY BE OMITTED UNTIL SELECTION OP VENDOR.
SERVICE Regenerator Intermediate Cooler
BTU/HR. EXCHANGER TYPE: HORIZ.. VERT. Air— COOled
4
DATE 10-28-70
BY SD CHK'D
JOB NO. PS- 2 18
"Fin-Fan" Unit
VENDOR MFRS. IDENT. NO.

TOTAL FLOW 	 IBS/HR
BHELL, OR TUBE SIDE 	
LIQUID (EXCLUDING WATER) 	 LBS/HM
OtNSITY 	 LBS/CU FT
THERMAL COKO.. .BTU/HR X SOFT X *F/FT
SPECIFIC HEAT 	 BTU/LB X *T



THERMAL. COND... BTU/HR X SOFT X *F/FT



ADDITIONAL DATA ON SHEET NO 	
OPERATING TEMPERATURES 	 *F







NUMBER OF PASSES PER SHELL 	
FLOW ARRANGEMENT 	
Air

Shell

® >
e -F
® V
9 >
e ' v


® V
e v
e v
& -r



70°



a v
« v
9 'P
e v
e v


e v
« v
9 V
« V






ALLOW. CALC.

MIN. ACTUAL TEST
MIN. CALC.

Molten Carbonates
334.000
i .. TyTpe

9 V
® V
0.45 « Avq.v
' « V
e v

: lOOApprox.
a vl
t « v
a v
0 V



qso°



« V
e v
e v
L a v
e v


e v
« >
e -p
« -P



850°


! ALLOW. 25 PSI CALC.

i MIN. ACTUAL TEST
' MIN. CALC.
1
li
PAR. BANKS OP EXCH. IN SERIES |l PAR. BANKS OF EXCH. IN SERIES
TOT. AREA (NOTE B) BQFT

TRANSFER RATE, CLEAN
SERVICE
CODE REQUIREMENTS....
REMOVABLE TUBE BUNDLE
FLOATING HEAD. .......
IUP1NUCMCNT BAFPLE 	
MATERIALS (MARK STRES



TIC ROOS « SPACERS..



CHANNEL. COVER 	
PLOAT1NO HEAD COVER
REMARKS: Me.






AIM-ASME: TEMA
YES NO
«..«^-«1«:~iiTfi«u
YES NO
SHELL (OR SECTS) TOTALNO.
TUBES. NO. PER SHELL. . . .
0.0. X
LENGTH 	

PITCH 	
TUBE LIMIT DIAM. OR WIDTH
WEIGHTS
EACH BUNDLE...
BUNDLE • SHELL 	
PULL OP WATER 	
S RELIEVED — S.R.. RADIOGRAPHED — X.R.)
Tvr>e 347SS










THICK.* IM.
.
.
.
,
.
.
.
.
•
•
NOZZl
INLE
OUT!
DRAI
VEN1
RCLI

IN.

IN. X
IN.
AVE.. MIN. WALL
IN. A O <0
IN.
LBS
LBS
LBS

CROSS BAFFLE!, TTPE. .
NUMBER X SPACINO.
SEGMENT CUT 	
TUBE HOLE DIAM.. . .
RADIAL CLEARANCE..
LONG BAFFLE., TYPE...

DIST. ABOVE SHELL.. .
REBOILER WEIR HEIGHT
SHELL AFTER WEIR..

X IN.

• IN.
• IN.

* IN.
IN.
IN.
FT.
TUBE SIDE SHELL SIDE
.ES (NOTE o size



r 	
EP 	
CASKETS


t


Lt Composition, Mol% Approx.: M2S 1
MofrO-j 81.1; KC1 3.8 Freezincr Point





RATING LIQ. VAP. RATING



-
i
3.8; M7S04 1.3;
750°F


•OTI Ai F0» CONOCKSEIIS «NO TNCITMOSrPNON «f »3ltt«J FUtSSUM DIOP STATED SHAU. INCLUOI STATIC MIAO SITWCEK CtNTE*LIN» Of INLET AND OUTLET FLANCIS.
•OTI B: OUTSIDE TUSE ASE* EICLUOINS A»E» IN TUIE SHEETS.              *7  1O              *"Tt Cl SATE »E» ASA S I»E — lljt OS AS» S 1*1* — !•«.
                                                            7-12

-------
                 Functional Specification  for

              Fly Ash Filter, Tag No. F-1A & F-lB

Types of Units - Pressure leaf
                 2 units in parallel.
                 Cyclic operation -  one unit in operation
                 while other unit is being drained  and
                 "dry" cake is discharged.

Material of   -  Type 347 stainless  steel
 construction
Design Pressure

Design Temperature

Type of Cake Discharge


Filtration Area

Cycle Time

Cake Thickness at
 End of Cycle

Cake Washing

Liquid Flow

Liquid Composition
Liquid Specific Gravity

Liquid Viscosity

Solids Flow

Media Opening

Percent Solids in "Dry Cake"
   150 psig

   1000 °F

   Fixed blades against
    rotary leaves

   1000 sq. ft. per unit

   45 minutes
-  1/8"
-  None

-  180,000 lb/hr.

-  Mixture of molten salts-
    sodium, potassium and lithium
    carbonates, sulphates, sulphites
    and sulphides

-  2.0

-  12 cp
-  630 lb/hr.  (400 lb/hr of KCl,
   230 lb/hr. of fly ash) plus trace,
_  25 micron                   o£ COKe<
-  35%
                                                   SINGMASTER & BREYER
                               7-13

-------
 Type of Units
Materials of
 Construction
   Functional Specification for

Coke Filter,  Tag No. F-2A & F-2B

        -  Pressure leaf
           2 units in parallel
           Cyclic operation - one unit in
           operation while other unit is being
           drained and "dry" coke is discharged.

        -  Type 347 stainless steel
Design Pressure

Design Temperature

Type of Cake Discharge

Filtration Area

Cycle Time

Cake Thickness
 End of Cycle

Cake Washing

Liquid Flow
Liquid Composition
           150 psg

           1000 °F

           Fixed blade against rotary leaves

           1000 sq. ft. per unit

           45 minutes
        -  1/8"
        -  None
Liquid Specific Gravity-

Liquid Viscosity
Solids Flow
Medium Opening
Percent Solids
 in "Dry Cake"
           180,000 Ib/hr.
           Mixture of molten salts
           sodium, potassium and
           lithium carbonates, sulphates,
           sulphites, and sulphides
           2.0
        -  12 cp
        -  880 Ib/hr. of coke plus traces
           of KCL and fly ash

        -  25 microns

        -  50%
                                                    SINGMRSTER & BREYER
                           7-14

-------
P-lB, 1B(S) CtNTftlFUGAl PUMP SPECIFIC*
P-lC, 1C(S) SINGMASTER ft BREYER
P— ID, lD(S) VSJiOOBJ MUST COMPLETE THIS SPECIFICATION SWEET
ITEM NO. SERVICE Absorber Pumps
nON ' •HEKTNO. 1 MKV.
DATE 11-16-70
P""»l •*TV»»I»» *T .._?* • CHK'D.
JOB NO. p.q_21R
NO. REQ'Q. 8 MOTOR DRIVEN. AND DRIVEN. VENDOR MFH'S TYPE NO.
LIQUID PUMPED Molten Carbonate Salt
CORROSION OR EROSION FACTORS
OPERATING CONDITIONS
PUMPING TEMPERATURE OjO — y 00 *r.
FLOW® P.T. 720 «PM DIFFERENTIAL! 1 2 PSI FT. d)
SPEC. en. & P.T. 2.0 DISCHARGE PSIG
VISCOS. @ P.T. 12* CP- SUCTION PSIG
BAROMETRIC PSIA
NPSH AVAILABLE FT.
NPSH REQUIRED FT.

MATERIALS
CASE! INNER
OUTER All Wetted Parts
WJCAR RINGS to be S.S. Type 347
STUDS AND NUTS
GASKETS
IMPELLER
WEAR RINGS
DIFFUIERS
INTERSTO. PIECE
INTERSTO. BUSHING
SHAFT
STUFF. BOX SHAFT SLEEVES
INTERSTG. SHAFT SLEEVE
STUFFING BOX
PACKING GLAND
•LAND STUDS
LANTERN RING
THROAT BUSHING
BALANCING DRUM
PRESS. BAL. SLEEVE
BEARING HOUSING
• t.HMCLl
«(«••• PARTt




















PUMP TYPE: (HORiz: VERT. SUBMCRO: VERT. SUCT.I REBEN. TVJRS.I
PUMP SIZE : NO. OF STAGES : SPEED RPM

BHP @ RATING FOR SP. GR. (1)1
MAX. BHP W/IMPELLER SUPPLIED FOR BP. OR. (1)1
MAX. BHP W/MAX. IMPELLER FOR SP. OR. (1)1
CONSTRUCTION
CASE! SWP (» PSIG O "F.I MYDTEST. PSIC
MIN. THICKNESS *. CORR. ALLOW. ".
SUPPORT TYPEl (CENTERLINE: FOOT: BRACKET)
IMPELLER OVERHUNGl (VE1I: NO)
SPLIT: (HORIZONTAL: VERTICAL! BARREL)
INSULATION
IMPELLER DIAMl SUPPLIED "\ MAX. 'l MIN. *.
TYPE! (OPEN: SIMI -ENCLOSED: ENCLOSES)
IYE VELOCITY & BATING FT./SXC.
DIRECTION OF ROTATION (FACING PUMP COUPLING) (CW: CCW )
CLEARANCE 1 RADIAL) WEARING RINGS '.
INTERSTG. PIECE '| PRESS. RED. DRUM ".
COUPLING. FLEXIOLE. (SINGLE; SPACER: FLOATING)
SLEEVE TYPEl ADJUSTABLE: (YEBiNO)
MFCR.
CUARD
STUFFING bOXESt 8ORC *! DEPTH ".
JACKETED . (YEBI NO)
PACKING TYPE (3)
SIZE: * I.D.: " O.D.: ' SQ.
NUMBER OF RINCS
MECHANICAL SEAL
SMOTHERING GLAND: (YES: NO)
FLUSHING OIL TO. LANTRN RING. ( YES; HO): WEAR. RING! (YES: NO)
BASE PLATE TYPE
FLOOR SPACE REQ-O.
BEARINGS: THRUST. TYPE. (BALLl STEP: KINGSB.) TYPE NO. ; LUBRICATORS (OIL) GREASE) TYPE. CAPi
RADIAL! TYPE: (BALLl SLEEVE) TYPE NO. : LUBRICATORS (OIL: GREASE) TYPEl CAP.
MFGR. SHALL SUPPLY THE FOLLOWING DRAWING NO.
SERIAL NUMBER
PERFORMANCE CURVES (CALCULATED: TEST) (HOTS B>
OUTLINE DRAWING
CROSS SECTION DRAWING

5-W. TOr BEAR'GSi THRl (YEBI NO) OPM WT. OF PUMP LBS.
BEAR'CS. RADl (YEBI NO) «PM WT. OF PUMP AND BASK LBS.
STUFF. BOX. (VEB: NO) CPM WT. OF DRIVER LB«.
PEDESTAL! (YES! NO) OPM SHIPPING WT. LBS.
NOZZLES SIZE RATINGI4) FACING* 4 > LOCATION
SUCTION
DISCHARGE
VENTS
DRAINS
COOLING WATER
WITNESS TEST

STATIC BALANC'O. OFi IMP.i > YESi NO)) ROTVT-C. ASSBY.i (YZSl NO)
DYNAM. BALANC'O. OFi IMP.! (YES: NO)I ROTAT'O. ASSBY.I (YESl NO
 DRIVER:  SUPPLIED BY
                                                                                               MOUNTED BY
EXEC. MOTOR. MAKE
TYPE
SPECIAL INSULATION
M.P. 1 RPM
VOLTB i PH. | CYC.
START. (LOW VOLTAGE! ACROSS LINE)
BEARINGS
BEARINGS LUB.
POWER CONSUMPTION
TURBINE. MAKE
TYP«
M.P.
PRESS. 0 THROTTLE PSIG
TEMPERATURE *F.
QUALITY OBJ SUPERHEAT
BACK PRESS P9IG
WATER RATE LBS./H.P. HR.
MAX. ALLOW. SPEED RPM
ENGINE. MAKE
TYPE
: M.P.
FUEL
HEATING VALUE
FUEL CONSUMPTION
spreo: OPCR.
SPEED REDUCCRt
LHV.
• TU/BHP./MR.
RPM; MAX. ALLOW itPW
IV -BELT: GEAR)
VENDOR SUPPLY: SPEED REDUCER. MUFFLER, RADIATOR. GCNERATCR-
•TARTER
AIR CLEANER. OIL FILTER. FUEL REG.. BATTtIT
REMARK*	   _     _          		    _	

(I) FDt A IARCI OF ST. Bt. US! LOWTST FOI IMrCUtI SIBNC AND CCUEN MEAD. MISHtJT FOI H. f. CALC                 (I) OK SAtt VOIKIHC riESS. SHAU U CIVtR AFTII IUITIACT. COIIOS. AU.OB.
(I) FACKIN8 WILL BE INSTALLED tN HtLa VtNDOl TO SHIP IN INDIVIDUAL LABELLED MCKACeS.                          «) Mil P£> ISA BliC LATtST SUPrUHCXT.    T_1  S
CO Plt/Dm. CUntS MUST INCLUDE: HZAO. CAPAOTY. tmC-SMF. UO^NFSHrOIDCSI«NIHPUUt:AUO MAD. CArAOTT FOI Bit. AII9 MAX. IUPQJLIIS.              '

-------
CENTRIFUGAL PUMP SPECIFICATION
P-2A, 2A(S) SINGMASTER a BREYER
P— 2B» 2B(S) VEWOOSJ MUBT COMPLETE THIS BPEaPlCATION B41EET BETOBE »ETUBJ«U««
ITEM NO. SERVICE Reducer Pumps
NO. REO* 0. 4 HOTOR DRIVEN. AND DRIVEN. VENDOR
LIQUID PUMPED Molten Carbonate Salt
CORROSION OR EROSION FACTORS
OPERATING CONDITIONS
PUMPING TEMPERATURE 950 'f.
FlOW @ FVT. 585 0PM DIFFERENTIAL 15 6pSI FT. <1)
•PEC. CR- @ r.T. 2.0 DISCHARGE PSIC

BAROMETRIC PSIA
NPSH AVAILABLE FT.
NPSH REQUIRED FT.

MATERIALS ..I.NUL
CASEI iwitm *"«•• '*•"
OUTER All Wetted Parts
WE** RING* To Be S.S. Type 347
•TUC> AND HUT*
GASKETS
IMPELLER
WEAK RINGS
OIFFUSEM*
iMTERsre. PIECE
INTXHSTO. BUSHING
•HAFT
STUFF. BOX *MAFT SLEEVES
INTERSTO. BHAPT SLEEVE
•TUFFINO VOX
PACKINO GLAND
•LAND STUDS
LANTERN BUNS)
THROAT BUSHING
BALANCING) DRUM
PWCSS. BA1_ BLECVK
•EARING MOUSING
SHUT NO. ^ NKV.
DATE 11-16-70
BY SF . CHK'D.
JOB NO. PS_?1fl
MFR'S TYPE NO.
PUMP TYPE: IMOIIIZ: VERT. BUBHEROl VKRT. BUCT.I HI6CN. TURB.)
PUMP SIZE : NO. OF STAGES : SPEED RPM

BHP & RATING
MAX. BHP W/IMPELLER SUPPLIED
MAX. BHP W/MAX. IMPELLER
FOB SP. OH. (1)1
POM SP. OR. (1)1
FOR SP. OR. (1»
CONSTRUCTION
CA«CIBWP ' P»IO Q
MIN. THICKNESS
*F.| HYDTEBT. PS la
*. CORR. ALLOW. *.
SUPPORT TYPEi (CENTERLINE: FOOT: BRACKET)
IMPELLER OVERHUNOI
SPLITt (HORIZONTAL:
(YES: NO)
VERTICALl BARREL)
INSULATION
IMPELLER DIAMl SUPPLIED
*! MAX. "| MIN. '.
TYPEi (OPCNt SEMI -ENCLOSED! ENCLOSED)
EYE VELOCITY @ BATING FTVsEC.
DIRECTION OF ROTATION (FACING PUMP COUPUNG) (CW; CCW)
CLEARANCE I RADIAL) WEARING RINGS '.
INTERSTG. 7IECE
"l PRESS. RED. DRUM ".
COUPLING. FLEXIBLE. (SINGLK; SPACER: FLOATING)
SLEEVE TYPEt
ADJUSTABLE: (YES: NO)
MFC*.
GUARD
STUFFING UOXeti BORE
JACKETED
*: DEPTH '.
(YES! NO)
PACKING TYPEO>
SIZE: * I.D.:
" O.D.: * «o.
NUMBER OF RINCS
MECHANICAL SEAL
SMOTHERING GLAND:
FLUSHING OIL TO. LANTRN RING'
(YES: NO)
IYC8I NO): WEAR. RINGl (YES; NO)
BASE PLATE TYPE
FLOOR SPACE REO'D.
BEARINQ9: THRUST. TYPEi (BALLl BTEPl KIMOSB.) TYPE NO. ; LUBRICATORS (OILl CREASE) TYPEi CAPl
RADIAL. TYPE: (BALL: SLEEVE) TYPE NO. : LUBRICATORS (OIL: GREASE) TYPE. ' CAPl
MFCR. SHALJL SUPPLY THE FOLLOWING DRAWINO NO.
BERIAL NUMBER
PERFORMANCE CURVE* (CALCULATIOl TE»T) (NOTI •)
OUTLINE OWAWINO
CROSS SECTION DRAWIHa

C-W. TO. BEAR'OSl THRi (THI NO) OPM WT. OF PUMP LB«.
•EAR'O*! RADl (YE»1 NO) aPM WT. OF PUMP AND BABE LBB.
•TUFF. BOXt  FACINOI4) LOCATION







STATIC BALANCra. OF. IMP.. I YESi NO): ROTATB. ASSBV.t (>«•: NO)
DYNAM. BALANC'O. OFi IMP 1 (YES: NO)I ROTAT'O. ASSBT.I (YCSi NO)
DRIVER:
                                                                      MOUNTED BY
CLEC. MOTOR. MAKE
TYPE
SPECIAL INSULATION
H.P. , nm
VOVTB 1 PH. 1 CYC.
START. (LOW VOLTAGE! ACROSS LINE)
BEARINGS
BEARINGS' LUB.
POWER CONSUMPTION
TURBINE. MAKE
TYPE
H.P.
PRESB. O THROTTLE PSIO
TEMPERATURE *F.
QUALITY OR SUPERHEAT
BACK PRESS - PSIO
WATER RATE LBS./H.P. HR.
MAX. ALLOW. SPEED RPM
ENGINE. MAKE
TYPE
: H.P.
FUEL
HEATING VALUE
FUEL CONSUMPTION
SPEED: OPER.
SPEED REDUCE*!
VENDOR SUPPLY! SPEED
STARTER. AIR
LHV.
• TU/BHP./HR.
RPM: MAX. ALLOW RPM
IV- BELT: GEAR)
REDUCER. MUFFLER. RADIATOR. GENERATOR.
CLCANER. OIL FILTER. FUEL KEG.. BATTERY.
       "•    Vertical  Cantilever  Type  4'   Long  Shaf t-4'  Long Tail  Piece
(I) ro» * tAMCi OF v. •«. o« LOWIST rot IMFOUI «tn«« AND DESIGN HEAD. MICHETT FOI a r. CALC.            u> CAIE wn womnxs p»tss. SHALL K eivui Arnt «J*T*«CT. cotaoi. ALLOW.
(I) P*CKIIie BSLL SI IHITAtUO III FICLO. VCMOOI TO SHIP IN INDIVIDUAL LUEUED FACXACCS.                   (4) MfC FCt «M Sl!£ L*TCST lUFFUMCITr.   7—16
CP POrOEBV CVtYU HUIT tUCLUOt tOAIX CVAOTT. CFTTC. IHP. EEO*D NPSH F0» DCJ)«H IHFCLLEI: ALSO XIAO. CAFAOTT F0» MIX. AM) MAX, IMPtLLim.

-------
CENTRIFUGAL PUMP SPECIFICATION
. . SINGMASTER a BREYER
^~" ' ' V&/ VKNOOM MUBT COMPLETE THIS SPECIFICATION CHUT BEFORE RETURNIHB
ITEM NO. SERVICE Regenerator Bottoms Pump
NO. REO'O. 2 MOTOR DRIVEN, AND DRIVEN. VENDOR
LIQUID PUMPED Molten Carbonate Salt
CORROSION OR EROSION FACTORS
OPERATING CONDITIONS
•UMPINO TEMPERATURE 950 V.
FLOW@P.T. 300 an* DIFFERENTIAL 14>»i 171ir. M>
SPEC. CR. @ P.T. 210 DISCHARGE 147 PSIG
VISCO*. @ P.T. 1 2 CJ". SUCTION 0 PSIO
BAROMETRIC PSlA
NPSH AVAILABLE FT.
NPSH REQUIRED FT.

MATERIALS
CASEl INNER
OUTER. All Wetted Parts
WEAR RING. SS Type 347
STUD* AND NUT»
GASKETS !
IMPELLER . i
WEAK RINa* i
DIFFUSERS
INTERSTO. PIECE
INTERSTO. BUSHING
•HAFT
•TUFF. BOX »HAFT SLEEVES
IHTERSTG. «HAFT SLEEVE
STUFFING BOX
PACKING GLAND
•LAND STUDS
LANTERN RINa
THROAT BUSHING
BALANCINB DRUM
PREIS. BAI_ SLEEVE
BEARING HOUSING,
•RIHNELi
VIA*'* PARTI




















•HCKT NO. ^ NKV.
DATE 11-16-70
•Y SF . CHK'D.
JOB NO. PS 218

	 	 5P 	 — 	
PUMP TYPE: (HORIZ: VERT. SUBHERGI VERT. SUCT.I RECEM. TURB.)
PUMP SIZE : NO. OF STAGES : SPEED RPM

BMP 6 RATING

POM SP. OR. (l)i
MAX. BMP W/IMPCLLER SUPPLIED FOR SP. OR. (1)1
MAX. BHP W/MAX. IMPELLER
FOR SP. OR. (1)1
CONSTRUCTION
CASEl SWP .(*) PSIO O
MIN. THICKNESS
•F.| HYOTEST. PSIB
*. CORR. ALLOW. ".
SUPPORT TYPEI ICENTERLINSI FOOT) BRACKET)
IMPELLER OVERHUNGi

• PLITt 1 HORIZONTAL: VERTICALl BARREL)
INSULATION
IMPELLER DIAMl SUPPLIED
TYPE!
"l MAX. *, MIN. '.
(OPENl SEMI-ENCLOSEDl ENCLOSED)
EYE VELOCITY & BATING PT./SEC.
DIRECTION OF ROTATION (FACING PUMP COUPLING) (CWl CCW )
CLEARANCE (RADIAL) WEARING
(NTERSTO. fllC*
RINGS '.
'l PRESS. RED. DRUM '.
COUPLING. FLEXIOLEi (SINGLE! SPACER: FLOATING)
SLEEVE TYPEi
ADJUSTABLE; (YES: NO)
MFCR.
GUARD
STUFFING bOXCC: BORE
JACKETED
*t DEPTH ".
(YESl NO)
PACKING TVPE(J)
SIZEi * I.D.:
• 0.0. : ' sa.
NUMBER OP RINGS
MECHANICAL SEAL
SMOTHERING GLAND:
(YES: NO)
FLUSHING OIL TOi LANTRN RINGi 1 YESl NO): WEAR. RINGl (YES: NO)
BASE PLATE TYPE
FLOOR SPACE REQ'O.
BEARINGS: THRUSTl TTPEl (BALU BTEP: KINGSB.) TTPE HO. i LUBRICATORS (OILj CREASE) TYPIt CAPt
RADIALl TYPE! ( BALLl SLEEVE) TYPE NO. : LUBRICATORS (OIL: CREASE) TYPEi CAP!
MFOR. SHAUL SUPPLY THE FOLLOWING DRAWINd NO.
BERIAL NUMBER
PERFORMANCE CURVES (CALCULATED: TEST) (NOTE S)
OUTLINE DRAWING
CROSS SECTION DRAWING

C.W. TOi BEAM-aSi THKI fYI«t NO) OfH WT. OF fUHF LBS.
BEAR-aSl RADl (YXSt NO) «PM WT. OF PUMP AND BASK LBS.
STUFF. BOXl (YES: NO) CPM WT. OF DRIVER LBS.
PEOCSTALl (YESl NO) GPM SHIPPING* WT. LBS.
NOZZLES SIZE HATH
SUCTION
DISCHARGE
VENTS
DRAINS
COOLING WATER
•IQHl FACINGI4)| LOCATION

!



WITNESS TEST

STATIC BALANC-a. OFl IMP.i rYES: NOIt ROTATES. ASSBY.I (YE»J NO)
DYNAM. BALANC^O. OF; IMP.t (YES: NO» ROTAT'O. ASSSY.t (YESl NO)
                                                                MOUNTED BY
CLEC. MOTOR. MAKE
TYP«
SPECIAL INSULATION
M.P. 1 RPM
VOLTS I PH. | CYC.
STARTl (LOW VOLTAGE: ACROSS LINK)
BEARINGS
BCARIN6S LUB.
POWER CONSUMPTION
TURBINE. MAKE
TYPE
H.P.
PRESS. & THROTTLE PSIO
TEMPERATURE *P.
QUALITY OR SUPERHEAT
BACK PRESS PSIO
WATER RATE LBS./H.P. HR.
MAX. ALLOW. SPEED RPM
ENGINE. MAKE
TYPE
I M.P.
FUEL
HEATING VALUE
FUEL CONSUMPTION
SPEED: OPER.
SPECO REDUCERi
VENDOR SUPPLY! SPI
STAWTTR.
LMV.
BTU/BHP./MR.
RPM: MAX. ALLOW RPM
(V-SCLT: GEARI
[ED REDUCER. MUFFLER. RADIATOR. GENERATOR.
Ain CLEANER. OIL FILTER. FUEL KEG.. BATTERY.
REMAP*.    *  vertical  Cantilever  Type  -  4'  Long  Shaf t-2'   Long  Tail Piece
 .,..-__	„_ _ —  .„„-...._	            (i) CAJE s»n B-oiwms PUSS. SHALL »t «vt» trriinimtct.
fi)pAcnrw *Tun7iiiTAU£D litntui.VWDCHTO jwiTi-mavtouu.USEOEOr«CK»etv                  (0 »AHn* »»HIMLATTJI SUPTUMENT.   7—17
tt pura«n. CU»YU Murrir»a.uot HEA& CVAOTY. trnc, sw. ETST) NMH res oaisumFiui* AUOHIAD.CAtAOTT ro» MIH. AHOP«»X,
                                                                                                        coitot. ALLOW.

-------
CENTRIFUGAL PUMP SPECIFICATION
P-4~ 4 (S) 8INGMASTER ft BREYER
»EMOOI» MUST COMPLETE TMI* SPECIFICATION SHEET BEFORE RETURN IMS
ITEM NO. SERVICE Reqen«?rator Intermediate Pump
NO. REQ'O. 7 MOTOH DRIVSNVAND OKIVEN. VENDOR
LIQUID PUMPED Molten Carbonate Salt
CORROSION OR EROSION FACTORS
OPERATING CONDITIONS
PUMPING TEMPERATURE 950 V.
PLOW @ P.T. 350 am DIFFERENTIAL 10 IPSI 117 rr. («>
•PTC. en. & P.T. 2.0 DISCHARGE 101 PSIG
viscos. @ P.T. 12 c-r. SUCTION 0 PSIG
BAROMETRIC PSIA
NPSH AVAILABLE FT.
NPSH REQUIRED IT.

MATERIALS .....in
CAM! INNC* ""•'• "«"
oum All Wetted Parts
WXARP.ING. SS Tyt>e 347
STUDS ANO NUT*
GASKETS
IMPELLER
WEAK RINGS
DIFFUSERS ' !
INTERSTG. PIECE
INTERSTG. BUSHING
•HAFT
•TUFF. BOX SHAFT SLEEVES
IMTERSTO. SHAFT SLEEVE
STUFFING BOX
PACKING QLAND
•LAND STUDS
LANTERN »IN«
THROAT BUSHING
BALANCING DRUM
PKCSS. BAL. SLEEVE
•EARING HOUSING
•HOT MO. 4 "EV.
DATE 11-16-70
•Y SP . CHK'D.
JOB NO. PS- 2 18

* 	 • 	 — 	
PUMP TYPE: IHORIZl VERT. SUBUEROl VERT. SUCT.I REOEN. TURB.)
PUMP SIZE : NO. OF STAGES : SPEED RPM

BHP 6 RATING
MAX. BHP W/IMPCLLER SUPPLIED
MAX. BHP W/MAX. IMPELLER

FOR sp. an. (I).
FOR SP. OR. (Ill
FOR SP. OR. (I)|
CONSTRUCTION
CASE! SWP .(1) PSia 9
MIN. THICKNESS
SUPPORT TYPEl ICENTERLI
IMPELLER OVERHUNOl
SPLITt 1 HORIZONTAL:
>.l HYDTEST. PSia
*. CORR. ALLOW. '.
NE: FOOT! BRACKET)
(YESl NO)
VERTICAL! BARREL)
INSULATION
IMPELLER DIAMt SUPPLIED
*l MAX. *i MIN. '.
TTPCi (OPEN: SEMI-ENCLOSEDl ENCLOSED!
EYE VELOCITY & RATING FTystC.
DIRECTION OF ROTATION ( FACING PUMP COUPLING) ICWiCCW)
CLEARANCE 1 RADIAL) WEARING RINGS *.
INTERSTG. PIECE
'l PRESS. RED. DRUM '.
COUPLING. FLEXIOLEl (SINGLE! SPACER: FLOATING)
SLEEVE TYPEt
ADJUSTABLEt (YES.! NO)
MFCR.
GUARD
STUFFING BOXCCi BORE
JACKETED
*i DEPTH '.
(YE*| NO)
PACKING TYPE(J)
SIZEt * I.D.:
* O.D.: ' SO.
NUMBER OF RINGS
MECHANICAL SEAL
SMOTHERING GLAND:
FLUSHING OILTOl LANTRN RING>
(YES: NOl
(YES: NO): WEAR. RING. (YES: NO)
BASE PLATE TYPE
FLOOR SPACE REQ'O.
BEARINGS: THRUST. TYPE. (BALLl STEP: KINOSB.) TTFK NO. : LUBRICATORS (OIL: GREASE) TYPti CAPi
HADIALl TTFC: (BALL) SLEETO) TYPE NO. : LUBRICATORS FOIL: GREAttl TTPEt CAP.
MFGR. SHALL SUPPLY THE FOLLOWING DRAWING NO.
SERIAL NUMBER
PERFORMANCE CURVE* (CALCULATED: TEST) (NOTE S)
OUTLINE DRAWINO
CROSS SECTION DRAWINa

S-W. TOt BCAR'CS. TMIli (YESl NO) OPM VTT. OF FUMP L»S.
•EAR-OSl RADl (YESl NO) OPM WT. OF PUMP AND BASE LBS.
STUFF. BOXl (YES: NO) CPM WT. OF DRIVER LBS.
PEDESTALi (YES! NO) CPM SHIPPING WT. LBS.
NOZZLES SIZE RATIN
SUCTION
DISCHARGE
VENTS
DRAINS
COOLING WATER
WITNESS TEST
a<«> FACINGI4) LOCATION







STATIC BALANC'O. OFl IMP.. .YES; N3): ROTATG. ASSBY.I (YESl NO)
OYNAM. BAUANC-a. OFi IMP.t ( ftS: NOll ROTAT'a. ASSBV.i (YESl SOI
MOUNTED BY
ELEC. MOTOR, MAKE
TTPE
•PECIAL INSULATION
M.P. I RPM
VOLT* | PH. I CYC.
START. ( LOW VOLTAGE! ACROSS LINE)
BEARINGS
BEARINGS LUB.

TURBINE. MAKE
TYPE
H.P.
PRESS. & THROTTLE
TEMPERATURE
PSIG
V.
QUALITY OR SUPERHEAT
BACK PRESS
WATER RATE

P9IG
LBS./H.P. HR.
RPM
ENGINE. MAKE
TYPE
I M.P.
FUEL
HEATING VALUE
FUEL CONSUMPTION
SPEED: OPER.
SPEED REDUCER.
LMV.
• TU/DHP./HR.
RPM: MAX. ALLOW RPM
I V. BELT: GEAR)
VENDOR SUPPLY: SPEED REDUCER. MUFFLER. RADIATOR. GENERATOR.
STARTER.
AIR CLEANER. OIL FILTER. FUEL MO.. BATTERY
         *vertical Cantilever Type  4'  Long  Shaft;  2'  Long  Tail Piece
) roi * UMt or v. •». u * uwwr rot mrtutt jnms «ND DUIGN «AO. HISHEJT ro« H. f . CALC            (U e*« tat wonntn PKJS. 5M»u. K «»w AFrnjujT
) PAcrans wu re mjTAUED m nan. vcxoot TO JHIP IN iKaviDU»L LASCU.U r*CK»«t«.                  W »*i f* **» B"E L»TUT SUPPUWEHT.  / — J.O
 ruroiB. cunts BUST iwauot HEAD, CAPAOTT. tmc. BUT. *vro HWH FO» oait* IMPCUI* AUO KIAO. CAMOTT FO» HJN. ARO MAX. iHpautv
                                        . eot»o». «u o».

-------
• CENTBIFUGAL PUMP SPECIFICATION SHEBT NO. -1
8INGMASTER ft BREYER
_ V**00» MOST COMPLETE THIS SPECIFICATION SHEET
,TEMNO. P-3 __ SERVICE MoCO-, MaVwip Pllmp
HEV.
DATE 11-16-70
BEFORE RZTURMUia *Y $p 1
CHK'D.
JOB NO. PS-21R
NO. REO'D. 1 MOTOB, DRIVEN. AND DRIVEN. VENDOR MFR'S TYPE NO
UQUID PUMPED Molten Carbonate Salts
CORROSION OR EROSION FACTORS
OPERATING CONDITIONS
PUMPING TEMPERATURE oOO *F.
PLOW @ P.T. 4 0PM DIFFERENTIAL 1 2 PSI 14 FT. (1)
•PEC. CM. @ P.T. 2.0 DISCHARGE 1 2 PSIG
VISCDS. @ P.T. 1 2 CP. SUCTION Q PSIG
BAROMETRIC PSIA
NP9H AVAILABLE • FT.
NP8H REQUIRED FT.
'
MATERIALS ....urn.
CASt, INNER •««»'• "»'«
ovrmm All Wf»t-.t-*»rl Part's
KEAR RINGS Type 347 SS
STUDS AND NUTS
BASKETS '
IMPELLER
WEAR RINGS
CirrUSERS
INTERSTG. PIECE
INTZRSTG. BUSHINA
•HAFT
STUFF. BOX SHAFT SLEEVES
INTERSTG. SHAFT SLEEVE
STUFFING BOX
PACKING GLAND
•LAND STUDS
LANTERN RfNB
THROAT BUSHING
BALANCING DRUM
PRESS. BAL. BLXEVK
BEARING HOUSING
PUMP TYPE: (MORIZ) VERT. SUBMERG) VERT. SUCT.I REGEN. TURB.)
PUMP SIZE ; NO. OF STAGES : SPEED RPM

BHP Q RATING FOR BP.
MAX. BHP W/IMPCLLER SUPPLIED FOR SP.
MAX. BHP W/MAX. IMPELLER FOR SP.

OR. (1)1
OR. (1)1
OR. III.
CONSTRUCTION
CASElSWPJS) PSIO 0 *P.| MYDTEBT. PSI«
MIN. THICKNESS *. CORR. ALLOW. '.
SUPPORT TYPEi (CENTERLINE: FOOT. BRACKET)
IMPELLER OVERHUNGl (YES) MO)
SPLIT: (HORIZONTAL) VERTICAL)
BARREL)
INSULATION
IMPELLER DIAMl SUPPLIED "l MAX.
*\ MIN. *.
TYPEi (OPEN) SEMI. ENCLOSED: ENCLOSED)
EYE VELOCITY & BATING
prysEC.
DIRECTION OF ROTATION (FACING PUMP COUPLING) (CW: CCW)
CLEARANCE (RADIAL) WEARING RINGS '.
INTERSTG. 7IECE "\ PRESS. RED.
DRUM *.
COUPLING, FLEXIBLE! (SINGLE) SPACXRt FLOATING)
SLEEVE TYPEi ADJUSTABLE) (YES: NO)
MFGR.
GUARD
STUFFING bOXECt BORE *i DEPTH ".
JACKETED (YESl NO)
PACKING TYPE(S)
SIZEl " I.D.: ' O.D
: 'so.
NUMBER OF RINGS
MECHANICAL SEAL
SMOTHERING GLAND: (YES: NO)
FLUSHING OILTOl LANTRN RINGi IYESI NO): WEAR. RINGl 1 YES: NO)
BASE PLATE TYPE
FLOOR SPACE REO'O.
•EARINO9: THRUST. TYPE. IBALU STEP) KINOSB.) TYPE NO. , : LUBRICATORS (DILI GREASE) TYPEi
RADIAL. TYPEt (BALLl SLEEVE) TYPE NO. : LUBRICATORS (OIL: GREASE) TYPEi
MFGR. SHALL SUPPLY THE FOLLOWING DRAWING NO.
SERIAL NUMBER
PERFORMANCE CURVES (CALCULATED: TEST) (NOTE •)
OUTLINE DRAWING
CROSS SECTION DRAWING

S.W. TOf BEAR'GSi THRi CYEBj NO) OPM WT. OF PUMP LBB.
BEAR-GSl RAOl (YES, NO) OPM WT. OP PUMP AND BASK LBB.
STUFF, BOXl (YES: NO) CPM WT. OP DRIVER LBB.
PEDESTAL,  FACINGI4)
CAPi
CAPi
LOCATION
SUCTION
DISCHARGE
VENTS
DRAINS
COOLING WATEH




WITNESS TEST

STATIC BALANC'G. OFl IMP.i (YES: NO): ROTATG
DYNAM. BALANC'0-OFi IMP.I (YES: NO)! ROTAT'O
ASSSY.i (YES: NO)
ASSBY.i (YXSl NO)
                                                                 MOUNTED BY

TYPE
SPECIAL INSULATION
HJ«. 1 HPM
VOtT« t PM. 1 CTC.
•TART. (LOW VOLTAGE) ACROSS UNO
BEARINGS
BEARINGS LUB.

TURBINE. MAKE
TYPE
N.P.
PRESS. O THROTTLE PSIG
TEMPERATURE *P.
QUALITY OR SUPERHEAT
BACK PRESS P9IG
WATER RATE LBB^H-P. H».
MAX. ALLOW. SPEED RPM
ENGINE. MAKE
TYPE 1 H.P.
FUEL
HEATING VALUE
FUEL CONSUMPTION
SPEED: OPER. RPM: MAX. ALLOW
LHV.
BTU/BHP./HR.
RPM
SPEEO BEOUCERl (V-BELT: GEAR)
VENDOR SUPPLY: SPEED RE3UCER. MUFFLER. RADI
ATOR. GENERATOR.
STARTER. AIR CLEANER. OIL FILTER. FUEL KIG.. BATTERY.
REMAP*.    *  vertical  Cantilever  Type  -  3'   Long  Shaft;   2'  Long  Tail  Piece

(I) ro»* UMI or v. i»..B«L<»mro» IMPCLUI mw »HD DUICN mto. HISHEST roi H. r. CMX.            (t) c»M s«i •OIEIR* r w>s. JH»U re WVM tntt turt»»CT. cotwi. AIIOS.
W P*CKI!«6 WU. n IIIJTALUID III n£La.VENOOI TO JHIf IH IKDIVIDUAL U3EU.E3 MCKASIJ.                  M •»« «» »H BISt UTUT idmiHOn.      /—J.y
W KE*O»«. cums null IMOJIDE; Mi*a orAOTT, OTIC. »HF. scan WJH roi DEJISH IMKUJK »uo HIAO. CWAOTT ro» w». *no MAX. mnuitv

-------
c.  Vessel Sketches

    Sketches of vessels, tanks or bins  required  for  the
removal process that are not provided with major equipment
are attached to this section of the  report.
                                                    SINGMASTER & BREYER

                           7-20

-------
<1

                               -Sjf
/? 5 /6.i
Dgm/s&r
                                   \  i    i     r    i
                                     -for WJmtcUr? ar>t€.
                          of
                                        Itt'-t
                                                            H-®
OATE_?'.

CHK'O	

APP'D
                                          -/A,  B,C,£Z>
                                                                                  VESSEL DESIGN  DATA
                                                                        CODE
                                                                        OTHER SPECS.:
                                                                        DESIGN PRESS. 0 TEMP.
                                                                                                 /PSI«
                                                                        OPER. PRESS. 6 TEMP.
                                                                        STRESS RELIEVING
                                                                        WELD EXAMINATION
                                                                        JOINT EFFICIENCYJSHELL
                                                                                        HEADS
                                                                        CORR. ALLOWANCE (SHELL
                                                                                        HEADS
                                                                        LINING
                                                                        MAX.ALL.PRESS.(NEW ft COLD)
                                                                                                               PS I
                                                                        HYDROSTATIC TEST
                                                                                                               PS I
                                                                        HAKWER TEST
                                                                                                               PS I
                                                                            SHELL
                                                                            HEADS j -Z40 Tf>3-f7
                                                                            SUPPORT
                                                                            INTERNALS
                                                                            TRAYS
                                                                        FIREPROOF ING
                                                                                              THK.
                                                                                                            SQ.FT.
                                                                         INSULATION
                                                                                              THK.
                                                                                                            SQ.FT.
                                                                         INS. SUPP. RINGS
                                                                        PAINT
                                                                        WT. OF
                                                                        TRAYS
                                                                        WT.&NO.
                                                                        OF CAPS
                                                                  fTJRN. BY
                                                                                INST'D BY
                                                                                INST'P BY
                                                                                                              LBS.
                                                                                               REQ'D.
                                                                                                              LBS.
                                                           NET FAB.WT.
                                                                          ,L£JST»*Y5
                                                                          (  AND C*»«
                                                              EMPTY WEIGHT
                                                                            OPERATING WEIGHT
                                                                                                              LBS.
                                                                            TEST WEIGHT
                                                                            WIND
                                                                                                            FT.LBS.
                                                                            EARTHQUAKE
                                                                                              FT.LBS.
                                                                        MANHOLE
                                                                        HANDHOLE
                                                                        NOTES a REF.DWGS.:
                                                                        MC.  RTG.   FCG.  SIZE
                                                                                         to*
                                                                                         l&
                                                                                        13?'
                                                                                         Z 5
                                                                                   NOZZLE  SCHEDULE
                                                                        VESSEL FABRICATOR TO SUPPLY CLIPS ONLY FOR
                                                                        -i o
                                                                        O. U.I
                                                                            NO.
                                                              SIZE
                                                                            WIDTO
                                                                        PLATFORM
                                                                         WEIGHT
                                                                                    83-:
                                                                                                       TYPE  I
                                                                                         TYPE II
                                                                                                       TYPE III
                                                                                    VESSEL DAVIT
                                                          LADDER
                                                                         CAGE
                                                                                       WT.
                                                                        PIPE GUIDES
                                                                        3000*
                                                                       /2 CPUGS.
                                                                        CONTRACT NO.
                                                                                   DWG. NO.
                                                                                                              OA
                                                      7-21
                                                                    SINGMASTER a BREYER

-------
nqrr
    \  \
                HORIZONTAL  VESSEL DESIGN DATA
          CODE STAMP M>- Ur->vc Dzs. <£,
          OTHER SPECS.:
          DESIGN PRESS.  S TEMP.
2.  PSI e
          OPER. PRESS. 8 TEMP.
                                    /  PSI  0
          STRESS RELIEVING  A/<3
                      NOTES » REF. DWGS.
          WELD EXAMINATION
                          '
          JOINT EFFICIENCY  SHELL
                                     * HEADS
          CORR. ALLOWANCE
                         SHELL
                                       HEADS
                                                                          20'
          LINING
          MAX. ALL. PRESS. {NEW 4 COLD)
                                                    PSI
                                       12"
          HYDROSTATIC TEST
                                                    PSI
                                             r/o
          HAMMER TEST
                                                    PSI
                      o
jo"
(D
_!
<

cc
              SHELL   SA-243-  TP 347
              HEADS
                              a/*
                      „£_
                           /So"
     °UMP
              SUPPORT
                                                          M(.
                                                               RTG.   FCG.  SIZE
                                                                       NOZZLE  SCHEDULE
                                                         VESSEL FABRICATOR TO SUPPLY CLIPS ONLY FOR
          FIREPROOFING
                            THK.
                                                  SQ.FT.
                                                         PLATFORM
                                                                                    WT.
          NSULATION
                                                  SQ.FT.
                                                         LADDER
                                                                           CAGE
                                                                                           WT.

          AINT
                                                                              PUMP
          NET FAB WEIGHT
          3SO 0 LBS.
          EMPTY WEIGHT
                                                   LBS.
          OPERATING WEIGHT
                                                   LBS.
          EST WEIGHT
                                                   LBS.
         MANHOLE
                                                         CONTRACT  NO.
                                                DWG. NO.
          HANDHOLE
                    DATE
                                           APP'D
                                                                       PS-2/&-40/&
                                                         7-22
                                  SINGMASTER ft BREYER

-------
           HORIZONTAL VESSEL  DESIGN DATA
    CODE STAMP /V<9- UPVC
                                                     NOTES ft REF. DWGS.
    OTHER  SPECS.:
    DESIGN PRESS. « TEMP.
                                PSJ
    OPER. PRESS. 8 TEMP.
                                    PSI  0
    STRESS RELIEVING
    WELD  EXAMINATION
JOINT EFFICIENCY  SHELL
                                7O •>. HEADS   /£?«•>
    CORR. ALLOWANCE   SHELL    	
                                     HEADS
    LINING  —
                                                      /r.f
                                                                             20"
                          S-SSL  CiT/vV
•»„
    MAX. ALL. PRESS. (NEW « COLD)
                                                    PSI
    HYDROSTATIC TEST
                                                    PSI
                                                      D
    HAMMER TEST
                                                    PSI
        SHELL
                               3^7
5
                                                                        -10
        HEADS
                                                      A
                                                                                   PUMP
        SUPPORT
                                  V "
                                -. C- .
                                                          MK.    RTG.   FCG.   SIZE
                            ?
^ ^xJ £ r 'S
                                                                         NOZZLE SCHEDULE
                                                         VESSEL FABRICATOR TO SUPPLY CLIPS ONLY FOR
     IREPROOF ING
                         THK.
                                                  SQ.FT.
                                                         PLATFORM
                                                                                       WT.
    NSULATION
                 g" THK.
                                                  SQ.FT.
                                                         LADDER
                                                                              CAGE
                                                                                               WT.
    A INT
   NET FAB WEIGHT
                                                   LBS.
   EMPTY WEIGHT
                                                   LBS.
                                                                    V-2D
    PERATING WEIGHT
                                                   LBS.
    EST WEIGHT
                                                   LBS.
   MANHOLE
                                                         CONTRACT  NO.
                                                                                  DWG. NO.
   HANOHOLE
               DATE
                                         APP'O
                                                          7-23       SINGMASTER & BREYER

-------
                                                                              LE6END
                                                                               - Mo no fray
                                                      2/8-40/9   r—B
                                    4
       HORIZONTAL VESSEL DESIGN DATA
CODE STAI*>    Yes -  U Pvc- jLafesf
OTWER SPECS.:
DESIGN PRESS, a rap.
OPER. PRESS. 8 TEMP.
                            <£, PSI  e
STRESS RELIEVING
WELD EXAMINATION
JOINT EFFICIENCYISHELL
                                             NOTES ft  REF. DWGS.
                                                                           6-2:£~4oje>
CORP.  ALLOWANCE   SHELL  	
                                             JL
                               HEADS
                                                                3*
                                                                            'ff- 2 f
LINING
MAX.  ALL. PRESS. (NEW & COLO)
                                             PSI
                                                                C,"
                                                                         HI/ i-trie.
HYDROSTATIC TEST
                                             PSI
HA^WER TEST
                                             PSI
cr
UJ

|
SHELL
                  2 O4
                                                 _B
     HEADS
SUPPORT
                             C  (or be
                                                                    Me/r fn/af
                                              MK.
                                                   RTG.   FCG.  SIZE
     INTERNALS
                                                                NOZZLE SCHEDULE
                                                  VESSEL FABRICATOR TO SUPPLY CLIPS ONLY FOR
 (REPROOFING
                    THK.
                                           SQ.FT.
                                                  PLATFORM
                                                                             rr.
 NSULATION
                    THK.
                                      SQ.FT.
                                                  LADDER
                                                                     CAGE
                                                                                    WT.
 AI NT
 ET FAS WEIGHT
                              24.000  LBS.
EMPTY WEIGHT
                                            LBS.
DERATING WEIGHT
                                            LBS.
 EST WEIGHT
                                            LSS.
MANHOLE ("j;s»,8')    g- Daw Fed
                                             CONTRACT NO.
HANOHOLE
           DATE
                    f/iCHK'D
                                   APP'D
                                                                           DWG. NO.


                                                                  PS- 2/8- 40/3
                                                  7-24
                                                              SINGMASTER & BREYER

-------
oaco
  ' 0
 Dctcff/3 f
                          or
V-2A,  £,  Cf»
                                               CONTRACT NO.
                                DWG. NO.
                                 7-25
                                        SINGMASTER & BREYER

-------
        HORIZONTAL VESSEL  DESIGN DATA
 CODE STAW     No- UPVC  D£s.
J(ELD EXAMINATION
JOINT EFFICIENCY JSHELL
                             b* HEADS
                           /CO %
CORR. ALLOWANCE   SHELL   —
                                 HEADS —
                                                                       2-2
                                                            LEVEL co.'M/.
LINING
MAX. ALL. PRESS. (NEW & COLD) —
                                               PSI
HYDROSTATIC TEST—
                                               PSI
                                   D
                                                                         3'
HAMMER TEST
                                               PSI
                                                                         £>
 LU
     SHELL
      J,° 547
     HEADS
                     '! J
                                   A
     SUPPORT  .
                                                      MK.   RTG.    FCG.  SIZE
     INTERNALS ^ - 2 4 O TP 3J 7
                                                  NOZZLE SCHEDULE
                                                     VESSEL FABRICATOR TO SUPPLY  CLIPS ONLY FOR
 IREPROOF ING
                     THK.
                                             SQ.FT.
                                                     PLATFORM
                                                                                  WT.
 NSULAT i ON
<5" 'THK .
                                             so . FT.
                                                     LADDER
                                                                         CAGE
                                                                                          WT.
 A 1 NT
NET FAB WEIGHT
                                                 .   I/-
EMPTY WEIGHT
                                              LBS.
OPERATING WEIGHT
 EST WEIGHT
                      , ?^ ^LBS .
                                                    CONTRACT NO.
                                                               DWG. NO.
HANOHOLE
           DATE
                                     APP'D
                                                    7-26
                                                                 SINGMASTER a BREYER

-------
,
           BY tf .


           DATE


           CHK'D


           APP'O
                                                                               VERTICAL  VESSEL  DESIGN  DATA
                                                                           CODE STAMP
                ^•.g - 6' A3 i/ £'• /s _fj°!p*cs.   	.	_'	
CONTRACT  NO.
                           DWG. NO.
                                                             7-27
           SINGMASTER & DREYER

-------
                                             '  f3'-0
           HORIZONTAL VESSEL  DESIGN DATA
    CODE STAMP /V>
                               CoMSt-
    OTHER SPECS.:
    DESIGN PRESS. » TENP.
                            .£  PSI  8     tOOO °F
    OPER.  PRESS. S TEMP.
                                    PSI  9
    STRESS RELIEVING   /V<3
    WELD EXAMINATION   /VO
JOINT EFFICIENCY I SHELL
                                     HEADS
                                                     NOTES ft REF. DWGS.
                                                         H
                                                                         3"
    CORR.  ALLOWANCE   SHELL     —
                                     HEADS  —
                                                                         2'
    LINING  ~
                                                                               He t
    MAX.  ALL. PRESS. (NEW ft COLD)
                                                    PSI
                                                                            2o
    HYDROSTATIC TEST
                                                    PSI
                                                     D
                                                                             2"
                              o
    HAKWER TEST  -
                                                    PSI
                                                     0
 o:
 u
         SHELL
              - 2 4O-  7P 34-7
         HEADS
                   d
A
ISO
         SUPPORT
                                                          M<.    RTG.    FCG.  SIZE
                                                                         NOZZLE  SCHEDULE
                                                         VESSEL FABRICATOR TO SUPPLY CLIPS ONLY FOR
    FIREPROOF ING
                         THK.
                                                  SQ.FT.
                                                         PLATFORM
                                                                                       WT.
     NSULATION
                                                  so. FT.
                                                         LADDER
                                                                              CAGE -
                                                                                               WT.
\J
     A 1 NT
                                                                                   BOTTOMS
    NET  FAB WEIGHT
                                       9 OO ^LBS.
                                                               POMP
    EKff>TY WEIGHT
                                                   LBS.
    OPERATING
     EST WEIGHT
                                      44 > 09 3 LBS.
    MANHOLE (* L*tllif*}
                                                     CONTRACT  NO.
                              DWG. NO.
    HANDHOLE
               DATE
                           CHK'D
                                         APP'D
                                                          7-28
                                                                      SINGMAST^-R & BREYER

-------
                                           is'-o
        HORIZONTAL VESSEL  DESIGN DATA
CODE STAI*> Mo-UPVC
OTHER
DESIGN PRESS. S TEKP.
                                PSI  S
                    /OOO°f
OPER. PRESS.  8 TEMP.
       O PSI 9
.5.5V3 °F
 Tf?ESS RELIEVING
                    A/i>
WELD EXAMINATION
JOINT EFFICIENCY | SHELL     "TO CHEAPS
  ENSITY
I »
CORR. ALLOWANCE   SHELL   —
                                 HEADS
                               NOTES ft REF. DWGS.
LINING
                                /r
                             is"
MAX. ALL.  PRESS. (NEW a COLD)
                                               PSI
HYDROSTATIC TEST  —
                                               PSI
HAVMER TEST
                                               PSI
                               C
     SHELL    64- 240  TP 347
                              6
     HEADS
                               A
     SUPPORT
                                                      MK.   RTG.
                                                                  FCG.  SIZE
                       >'•'£>- -S A  /93
                                              NOZZLE  SCHEDULE
                                                     VESSEL FABRICATOR TO SUPPLY CLIPS ONLY  FOR
 IREPROOFING
                     THK.
                                             SQ.FT.
                                                     PLATFORM
                                                                                  WT.
 NSULATION
                                             SQ.FT.
                                                     LADDER
                                                                         CAGE
                                                                                         WT.
 AINT  —
 ET FAB WEIGHT
                  & OOOLBS.
EMPTY WEIGHT
                                              LBS.
                                                                     V-7
 PERATING WEIGHT
                 £,/,
 EST WEIGHT
                 33, /OijLBS.
MANHOLE {"'""V*
                               CONTRACT  NO.
                                      DWG.  NO.
HANDHOLE
           DATE
                       CHK'D
                APP'D
                                                     7 — 29       SINGMASTETR ft EREYER

-------
                    VESSEL DESIGN DATA
          CODE
          OTHER SPECS.;
          DESIGN PRESS. 0 TEMP.
                   PS I
          OPER. PRESS. 8 TEMP.
                                     PSI 0
          STRESS RELIEVING
          WELD EXAMINATION
          JOINT EFFICIENCY SHELL  —   % HEADS—
          CORR. ALLOWANCE [SHELL /a    \CoM= &
          LINING
          MAX.ALL.PRESS.(NEW ft COLD)
                                                  PSI
          HYDROSTATIC TEST
                                                  PSI
          HAMPER TEST
                                                  PSI
              SHELL.COH5£  TOP- A -££$
              HEADS
              SUPPORT
              INTERNALS
              TRAYS
          5F1/77-
          FIREPROOF ING
                                THK.
                                               SQ.FT.
          INSULATION
                                THK.
                                               SQ.FT.
          INS. SUPP. RINGS
          PAINT
          WT. OF
          TRAYS
          WT.ft NO.
          OF CAPS
FURN. BY
                  INST'O BY
FURN. BY
                  IHST'O BY
                                                 LBS.
                             REQ'D.
                                                 LBS.
          NET FAB.WT.
     /LES9TKAY9 >
     (*«» CAP! I
3/ 2OO   LBS.
              EMPTY WEIGHT
                                                 LBS.
              OPERATING WEIGHT
                               LBS.
              TEST WEIGHT
                                                 LBS.
              WIND
                                              FT.LBS.
              EARTHQUAKE
          "8 =
        FT.LBS.
          LAAUU/V C  /
          MANHOLE  (
                    HINtID Oil
          HANDHOLE
          NOTES ft REF.DWGS.:
          E>
            .  RTG.   FCG.  SIZE
                          IS'
                          12
              QtJH^r
              Level
                     NOZZLE  SCHEDULE
         VESSEL FABRICATOR TO SUPPLY CLIPS ONLY FOR
          • vi
          _i Oi
          0. U.|
             NO.
             SIZE
             WIDTH
          PLATFORM
           WEIGHT
                                         TYPE
                                         TYPE II
                                         TYPE III
                  VESSEL DAVIT
         LADDER
                        CAGE
                                       WT.
           IPE GUIDES
         CONTRACT NO.            DWG. NO.
           	PS- ?!*-4oi7
7-30
  S1NGMASTER & BREYER

-------
        HORIZONTAL  VESSEL DESIGN  DATA
CODE STAMP
 C Dfs,^CcA/$r/?,
OTHER SPECS.:
DESIGN PRESS. 0 TEW.
          £7 PSI  9
&SO  °F
OPER. PRESS. 8 TEMP.
           Q PSI  0
QOO
                                 NOTES & REF. DWGS.
STRESS RELIEVING  //i>
WELD EXAMINATION
„''•->
JOINT EFFICIENCY | SHELL
          7O%| HEADS
             ? MAT L -
CORR. ALLOWANCE   SHELL
                                HEADS -
                                                                       SO"
LINING
MAX. ALL.  PRESS. (NEW & COLD)
                                               PSI
                                                     14
HYDROSTATIC TEST   —
                                               PSI
                                  D
                                     T.'
HAMMER TEST
                                               PSI
                                                     12
     SHELL
                 -
     HEADS
                                        150
     SUPPORT
                                                     M<.
                                                           RTG.
                                                                 FCG.   SIZE
                                                                 R c- M <-\
     INTERNALS
                                                                    NOZZLE SCHEDULE
                                  B3C.
                                                    VESSEL FABRICATOR TO SUPPLY CLIPS  ONLY FOR
FIREPROOF ING
                     THK.
                                             SQ.FT.
                                                    PLATFORM
                                                                                  WT.
 NSULATION
                                             SQ.FT.
                                                    LADDER
                                                                        CAGE
                                                                                         WT.
 AINT
NET FAB  WEIGHT
                                              LBS-
EMPTY WEIGHT
                                              LBS.
OPERAT 1 NG WEI GHT
                                              LBS .
 EST WEIGHT
                 2 9' OOC LBS.
MANHOLE
                                                    CONTRACT  NO.
                                                              DWG. NO.
HANDHOLE
                                                                 - 4005
           DATE
                       CHK'D
                                     APP'D
                                                    7-31.
                                                                • SINGMASTER a BREYER

-------
M NJ
CHK'D_

APP'D
v$//0S
   T'3

   J-S
                                                                                    VESSEL DESIGN DATA
                                                                           CODE STAMP  -/\l0~ Jr'.  ,'• D?J, f
                                                                           OTHER SPECS.:
                                                                           DESIGN PRESS. 6 TEMP.
                                                                                                       PSI
                                                                           OPER. PRESS. 6 TEMP.
                                                                                                 fj
                                                                                                       PSI
                                                                           STRESS RELIEVING  —
                                                                           WELD EXAMINATION  —
                                                                           JOINT EFFICIENCY|SHELL    r_> %| HEADS
                                                                           CORR. ALLOWANCE  SHELL  —
                                                                                                         HEADS —
                                                                           LINING
                                                                           MAX.ALL.PRESS.(NEW a COLD)
                                                                                                                   PSI
                                                                           WDROSTATIC TEST
                                                                                                                   PSI
                                                                           HAMMER TEST
                                                                                                                   PSI
                                                                               SHELL -  />- ££
                                                                              HEADS
                                                                              SUPPORT
                                                                               INTERNALS
                                                                              TRAYS
                                                                           FIREPROOF ING
                                                                                                 THK.
                                                                                                                SQ.FT.
                                                                           INSULATION   .. -
                                                                                                 THK.
                                                                                                                SQ.FT.
                                                                           INS. SUPP. RINGS  —•
                                                                           PAINT- ' v
                                                                           WT. OF.
                                                                           TRAYS
                                                                           WT.& NO.
                                                                           OF CAPS
   FURN. BY
                                                                                   INST'D BY
   FURN. BY
                                                                                   INST'D BY
                                                                                                                  LBS.
                                 REQ'D.
                                                                                                                  LBS.
                                                                           NET FAB.WT.
                                                                                                                  LBS.
NDAT
DATA
                                                                               EMPTY WEIGHT
                                                                                                           ,
                                                                                                                  LBS.
                                                                               OPERATING WEIGHT V
                                                                                                              >?-?LBS.
                                                                               TEST WEIGHT
                                                                                                                  LBS.
                                                                               WIND
                                                                                                                FT. LBS.
                                                                               EARTHQUAKE
                                                                                                                FT. LBS.
                                                                           >i«uunl c   / MINSto on ,
                                                                           MANHOLE   (  PAVITIO  )
                                                                           HANDHOLE
                                                                           NOTES a REF.DWGS.:
                                                                          Mtt
                                                                           D
                                                                           fl
/SO'
                                                                           MK.  RTG.
                                                                           f?.r
            CO
                                                                                            4'
                                                   12"
                                                                                      FCG. -SIZE
                                                                                      //<7/.»-
                 Lcv-
                                                                                                 So t:
                                                                                                           TYPE III
                      VESSEL DAVIT
                                                                          LADDER
                                                                                         CAGE
                                                                                                        WT.
                                                                          PIPE GUIDES
       i/|°??rcs.
                                                                          CONTRACT NO.
                     DWG. NO.
                                                                7-32
                                                                                     SINGMASTER flc BREYER

-------
d.  Motor List

    t?he list of motors  for all required equipment are contained
in the following pages.   This  list was used to estimate the elec-
trical construction cost.
                                                    SINGMASTER S BREYER

                               7-33

-------
EQUIP.
NO.
B-2

F-1A&1E


P-1A;1/
P-1B;1E
P-1C;1C
P-1D;1E

V-1A
V-1B
V-1C
V-1D

V-2A
V-2B
V-2C
V-2D


SERVICE
Filter Displacement Blower

Fly Ash Filter-Drive
-Screw

(S) Absorber Pumps
(S)
(S)
(S)

Absorber Bypass Valve 3@
3@
3@>
3@

Absorber Pump Tank-Elec.Htr.

•



HORSE POWER
OPER.
10

2
5

125
125
125
125

3
3
3
3

30K
30K
3010
3010


SPARE


2
5

125
125
125
125






fj
V
•7
V


SYN.
R.P.M.





















VOLTAGE
480

480
480

480
480
480
480

480
480
480
480

480
480
480
480


NO. OF
PHASES





















MOTOR
ENCL.





















MOTOR ENCLOSURE * MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
0 - OPEN DRIP-PROOF SYN • SYNCHRONOUS
OE - OPEN, ENCAPSULATED - WR • WOUND ROTOR
TENV - TOTALLY ENCLOSED NON-VENTILATED CP1 • CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC • TOTALLY ENCLOSED FAN COOLEO CP2 • CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP • EXPLOSION PROOF CP3 - CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP - SPLASH PROOF MW • MULTI-WINDING
SPLE - SPECIAL - SEE REMARKS OTHER • SPECIFY AS REQUIRED

F.L.
CURR.





















DATA
EST.
X

X
X

X
X
X
X

X
X


X
X

X
X
X
X


SINGMASTER &
PREPARED BY
S.F.
DATE
11-20-70
SH. 1 OF
FIRM





















REMARKS*




















,
BREYER NEW YOf'.K. N.Y.
MOTOR LIST
A.I. Process
Absorber Area
JOB NO. PS-218 REV.
FORM  E-471

-------
EQUIP.
NO.
B-1A
B-1B
B-lC
B-1D

E-1A
E-1B

F-2A&B


P-2A;2A
P-2B;2B

V-4A
V-4B

W-1A
W-1B
W-1C
W-1D
SERVICE
Combustion Air Blower




Reducer Product Cooler 2 @
2 @

Coke Filter - Drive
- Screw

S) Reducer Pumps
s)

Reducer Quench Tank-Elec.Htr.


•
Weigh Belt Feeder



HORSE POWER
OPER.
300
300
300
300

10
10

2
5

150
150

30
30

2
2
2
2
SPARE








2
5

150
150

KW
KW





SYN.
R.P.M.










'










VOLTAGE
2400
2400
2400
2400

490
480

480
480

480
480

480
480

480
480
480
480
NO. OF
PHASES





















MOTOR
ENCL.





















MOTOR ENCLOSURE * MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
0 • OPEN DRIP-PROOF SYN • SYNCHRONOUS
OE - OPEN, ENCAPSULATED • WR - WOUND ROTOR
TENV - TOTALLY ENCLOSED NON-VENTILATED CP1 - CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC - TOTALLY ENCLOSED FAN COOLEO CP2 - CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP- EXPLOSION PROOF CP3 • CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP- SPLASH PROOF MW - MULTI-WINDING
SPLE - SPF.CIAL - SEE REMARKS OTHER - SPECIFY AS REQUIRED

F.L.
CURR.





















DATA
EST.
X
x
X
X

X
X

X
X

X
X

X
x

X
X
X
X
SINGMASTER A
PREPARED BY
S.F.
DATE
11-20-70
SH. 2 OF
FIRM





















REMARKS*




















,
BREYER NEW YO>K. N.Y.
MOTOR LIST
A.I. Process
Reducer Area
JOB NO. PS-218 REV.
FORM E'471

-------
EQUIP.
NO.
E-4
TC-5


P-3;3(S
P-4;4(S


V-6
V-7











SERVICE
Regen. Bottoms Cooler 2@
Regen. Intermediate Cooler 2d>


Regenerator Btms Pump
Regenerator Intermediate Pump


Regen. Btms Pump Tank-Elec.Hti
Regen. Int. Pump Tank-Elec.Hti







•



HORSE POWER
OPEN.
5
1%


75
60


.30KV
.30KV











SPARE




75
60



j











SYN.
R. P.M.





















VOLTAGE
480
480


480
480


480
480











NO. or
PHASES





















MOTOR
ENCL.





















MOTOR ENCLOSURE * MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
0 - OPEN DRIP-PROOF SYN • SYNCHRONOUS
OE • OPEN, ENCAPSULATED • WR • WOUND ROTOR
TENV - TOTALLY ENCLOSED NON-VENTILATED CP1 - CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC - TOTALLY ENCLOSED FAN COOLEO CP2 - CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP - EXPLOSION PROOF CP3 • CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP - SPLASH PROOF MW - MULTI-WINDING
SPLE - SPECIAL - SEE REMARKS OTHER - SPECIFY AS REQUIRED

F.L.
CURR.





















DATA
E5T.
X
X


X
X


X
X











SINGMASTER &
PREPARED BY
S.F.
DATE
Ll-20-70
SH. 3 OF
FIRM





















REMARKS*




















,
BREYER NEW VOf-.K, N.Y.
MOTOR LIST
A.I. Process
Regenerator Area
JOB NO. PS-218 REV-
FORM  E-47*

-------
EQUIP.
NO.
C-l
C-l

G-l
G-l
G-2
G-3
G-4
G-5
G-5A
G-6
G-7
G-8

S-l






SERVICE
Crusher - Driv#> »A"
Crusher - Drive "B"

Transfer Conveyor & Feeder
Transfer Conveyor & Feeder
Bucket Elevator
Bucket Elevator
Reversing Belt Conveyor
Coke Belt Conveyor w/Tripper
Elevating Belt Conveyor
Dust Collector
Coke Silo Dust Collector
Coke Silo Dust Collector

Coke Screen






HORSE POWER
OPER.
inn
125

1
1
3
5
3
5
5
5
2
2

7%






SPARE





















SVN.
R. P. M.





















VOLTAGE
4an
480

480
480
480
480
480
480
480
480
480
480

480






NO. OF
PHASES





















MOTOR
ENCt.





















MOTOR ENCLOSURE 'MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
0 - OPEN DRIP-PROOF SYN • SYNCHRONOUS
OE- OPEN, ENCAPSULATED . WR • WOUND ROTOR
TENV • TOTALLY ENCLOSED N ON -VENTILATED CP1 - CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC - TOTALLY ENCLOSED FAN COOLEO CP2 • CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP • EXPLOSION PROOF CP3 - CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP - SPLASH PROOF MW - MULTI-WINDING
SPLE • SPF.CIAL - SEE REMARKS OTHER - SPECIFY AS REQUIRED

F.L.
CURR.





















DATA
EST.
X
X

X
X
X
X
X
X
X
X
X
X

X






FIRM





















REMARKS*




















,
SINGMASTER A BREYER NEW YO>.K, N.Y.
PREPARED BY
S.F.
MOTOR LIST

DATE
11-20-70
A.I. Process
Coke Handling
SH. 4 OF JOB NO. PS-218 "EV.
KOHM  K-47K

-------
EQUIP.
NO.
G-9
G-10
G-ll

W-2
W-3
W-3

V-9

T-2
T-3
T-4

P-5






SERVICE
M2CC>3 Bucket Elevator
M2COo Conveyor
M?CO., Silo Feed Conveyor

Weigh Feeder
Weigh Feeder
Weigh Feeder

M^COo Melt Tank Elect. Htr.

Silo Dust Collector
Silo Dust Collector
Silo Dust Collector

M2C07 Makeup Pump






HORSE POWER
OPER.
5
2
3

1
1
1

2-1:

2
2
2

5






SPARE '








5KW <












SYN.
R.P.M.








sach












VOLTAGE
480
480
480

480
480
480

480

480
480
480

480






NO. OP
PHASES





















MOTOR
ENCL.





















MOTOR ENCLOSURE * MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
0 • OPEN DRIP-PROOF SYN • SYNCHRONOUS
OE • OPEN, ENCAPSULATED ' WR • WOUND ROTOR
TENV • TOTALLY ENCLOSED NON-VENTILATED CPl - CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC - TOTALLY ENCLOSED FAN COOLEO CP2 • CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP - EXPLOSION PROOF CP3 • CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP - SPLASH PROOF MW - MULTI -WINDING
SPLE • SP» CIM - SI T HF MARKS OTHF.R • Sf'FOlr Y AS INQUIRED

F.L.
CURR.





















DATA
EST.
X
X
X

X
X


X

X

X
X
X

X






SINGMASTER &
PREPARED BY
S.F.
DATE
11-20-70
SH. 5 OF
FIRM





















REMARKS*









.










.
BREYER NEW YOhK, N.Y.
MOTOR LIST
A.I. Process
M2CO3 Makeup Area
JOB NO. PS-218 REV.
t>47*

-------
EQUIP.
NO.
X-2

X-3


















SERVICE
Instrument Air Compressor

Instrument Air Dryer









%








HORSE POWER
OPCR.
50

10KW


















SPARE





















SYN.
R. P. M.





















VOLTAGE
480

480


















NO. OF
PHASES





















MOTOR
ENCL.





















MOTOR ENCLOSURE * MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
0 - OPEN DRIP-PROOF SYN • SYNCHRONOUS
OE - OPEN, ENCAPSULATED • WR • WOUND ROTOR
TENV • TOTALLY ENCLOSED NON-VENTILATED CP1 - CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC • TOTALLY ENCLOSED FAN COOLEO CP2 - CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP • EXPLOSION PROOF CP3 • CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP • SPLASH PROOF MW - MULTI-WINDING
SPLE - SPECIAL - SEE REMARKS OTHER - SPECIFY AS REQUIRED

F.U.
CURR.





















DATA
EST.
X

X


















SINGMASTER ft
PREPARED BY
S.F.
DATE
11-20-70
SH. 6 OF
FIRM





















REMARKS*




















,
BREYER NEW YOhK. N.Y.
MOTOR LIST
A.I. Process
Utility Area
JOB NO. PS-218 JREV.
	 I '
FORM  E-4TI

-------
EQUIP.
NO.
A- 101
A- 10 2
A- 10 3
A- 104

A- 10 5
A- 10 6

B-101
B-102

D-101
D-101
D-101

F-101





SERVICE
Dissolving Sump Agitator
Fly Ash-Coke Slurry Tank Agit,
LiHCOo Reactor Agitator
LiiCO-,-Fly Ash Filter Cake
«• J
Receiver Agitator
LiHCO., Reactor Prod. Surge Rec,
Li0C00 Reactor Product Surge

Exhaust Fan
Hot Air Blower

LioCO'^ Dryer Drive
** J
LioCO0 Dryer I.D. Fan
Li0CO_, Dryer Feeder
c. J
Li0CO.,-Fly Ash Filter-Agit.
-Drive
-Vac . Pumj
-Filtrate Pum{
( P i n "> \


HORSE POWER
OPER.
5
3
5

5
5
5

5
25

ik
5
2

1
1
>50
> 2


SPARE





















SYN.
R. P.M.





















VOLTAGE








480
480

480
480
480

480
480
480



NO. OF
PHASES





















MOTOR
ENCL.





















MOTOR ENCLOSURE * MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
C • OPEN DRIP-PROOF SYN - SYNCHRONOUS
OE • OPEN, ENCAPSULATED • . WR - WOUND ROTOR
TENV -TOTALLY ENCLOSED NON-VENTILATED CP1 - CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC • TOTALLY ENCLOSED FAN COOLEO CP2 - CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP - EXPLOSION PROOF CP3 - CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP- SPLASH PROOF MW - MULTI-WINDING
SPLE - SPECIAL - SEE REMARKS OTHER - SPECIFY AS REQUIRED

F.L.
CURR.




















DATA
EST.
X
X
X
X

X
X

X
X

X
X
X

X
X
X


FIRM




















' 1
SINGMASTER ft
PREPARED BY
S.F.
DATE
11-20-70
SH. 7 OF .
REMARKS*








,











.
BREYER NEW YOI'.K. N.Y.
MOTOR LIST
A.I. Process
Li0C00 Recovery Area
JOB NO. PS-218 REV.
FORM K-47S

-------
-o
 I
EQUIP.
NO.
F-102



F-103




G-101

P-101,1
P-102
P-103,1
P-104.1
P-105
P-106
P-107

X-101

SERVICE
Fly Ash Filter - Drive
- Agitator
- Vacuum Pump

Li2C03 Filter - Agitator
- Drive
- Vacuum Pump
- Filtrate Pump
	 	 — / r> n ni ^
(c— J-U / ;
Dried Li2CO_ Conveyor

)1(S) Li»CO^-Fly Ash Fil.Feed Pun
See F-101
)3 (S) Slurry Disposal Pump
)4(S) Fly Ash Filter Feed Pump
Li0CO0 React. Prod. Pump
£. J 	 — 	 Jr
Li^CO Filter Feed Pump
2 3
See F-103

CCU Generator-Blower
£.
-Compressor
HORSE POWER
OPER.
1
1
50

h
h
20
ih

2

IP ih

i
i
iJ?
l


30
200
SPARE











1*

1
1






SYN.
R. P. M.





















VOLTAGE
480
480
480

480
480
480
480

480

480
480
480
480
480
480
4RO

480
480
NO. OF
PHASES





















MOTOR
ENCL.





















MOTOR ENCLOSURE * MOTOR TYPE - SQ. CAGE IND. UNLESS OTHERWISE NOTED
0- OPEN DRIP-PROOF SYN - SYNCHRONOUS
OE • OPEN, ENCAPSULATED . WR - WOUND ROTOR
TENV - TOTALLY ENCLOSED NON-VENTILATED CP1 - CONSEQUENT POLE 2 SPEED - CONSTANT HP
TEFC • TOTALLY ENCLOSED FAN COOLEO CP2 - CONSEQUENT POLE 2 SPEED - CONSTANT TORQUE
EP - EXPLOSION PROOF CP3 - CONSEQUENT POLE 2 SPEED - VARIABLE TORQUE
SP- SPLASH PROOF MW • MULTI -WINDING
SPLE - SPECIAL - SEE REMARKS OTHER - SPECIFY AS REQUIRED

F.L.
CURR.





















DATA
EST.
X
X
X

X
X
X
X

X

X
X
X
X
X
X
X

X
X
SINGMASTER &
PREPARED BY
S.F.
DATE
11-20-70
SH. 8 OF


FIRM





















REMARKS*




















.
BREYER NEW YOI'K. N.Y.
MOTOR LIST
A.I. Process
Li^CO- Recovery Area
JOB NO. PS-218 REV.
                                                                                                                                                                                                            FORM  F.-478

-------
    8.  PIANT ARRANGEMENT DRAWINGS - BASE CASE

        fhe conceptual arrangement of equipment required to accom-
plish the removal of SOx from the base case power plant flue gases
and to recover Li2CC>3 from the discarded filter cakes is shown on
the attached drawings:

        PS-218-0501  -  Site Arrangement - Plans
        PS-218-0502  -  Site Arrangement - Elevation, Sections
        PS-218-0503  -  Filter & Recovery Process Bldg. -

                             Equipment Arrangement

        It was assumed that makeup carbonate salts would be
shipped to the plant by truck and that coke would be delivered
by rail cars.

        Changehouse facilities for plant operating personnel
were presumed to be available at the power plant.
                                                   SINGMASTER S BREYER

                                8-1

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
9.  REFERENCES

 (1)   "Development of a Molten Carbonate Process for
       Removal of Sulfur Dioxide from Power Plant Stack
       Gases" Atomics International, North American
       Rockwell.

 (la)   Progress Report No. 1 - June 1, 1967 to February
       28, 1968  (Summary Report)

 (Ib)   Part I - Process Chemistry, Reduction.

 (Ic)   Part II - Process Chemistry, Regeneration.

 (Id)   Part III -  Materials Studies.

 (le)   Part IV - Contactor Development.

 (If)   Part VI - Fly Ash Studies.

 (Ig)   Part VI - Small Pilot Plant and Component Test
       Loop,  Conceptual Design,

 (Ih)   Part VII - Plant Analysis.

 (li)   Progress Report No. 3 - October 28,1968 to
       July 31, 1969.

 (2)   Fair,  J,R. "Designing Gas Sparged Reactors"
       Chemical Engineering 74; 67-74, July 3, 1967;
       207-214, July 17, 1967.

 (3)   Johnstone, RoE0 and Thring, M.W, "Pilot Plants,
       Models,  and Scale-up Methods in Chemical Engineering"
       New York, McGraw-Hill Book Company,1957.

 (4)   Turnbull, A.G. "Thermal Conductivity of Molten
       Salts,  II - Australian Journal of Applied Science
       12: 324-329,  19610
                                                  SINGMASTER S BREYER
                              9-1

-------
(5)   Gairibill, W.R. "Fused Salt Thermal Conductivity"
      Chemical Engineering 66i 129-130, August 10, 1959,

(6)   Janz, G.J. and Lorenz,M.R. "Solid-Liquid Phase
      Equilibrium for Mixture of Lithium, Sodium and
      Potassium Carbonates" Journal of Chemical and
      Engineering Data 6_ (3): 321-323, July, 1961.,

(7)   Marshall, W.L.,  Loprest, F.J. and Secoy, C.H.
      "The Equilibrium Li2C03 (s)+C02+H20  —*-
      2 Li+2 HCC-3- at High Temperature and Pressure"
      Journal of the American Chemical Society 80;
      5646-5648, November 5,  1958.

(8)   "Modern Refractory Practice"  Harbison-Walker
      Refractories Company.

(9)   "Properties of Hitec" E.I. duPont,  de Nemours &
      Company.

(10)   "Coal Gasification Using Molten Sodium Carbonate"
      M.W.  Kellogg & Company.  Final Report Under Contract
      14-01-0001-380 for U.S. Department  of the Interior.
      September, 1967.

(11)   "Systems Study for Control of Emissions-
      Primary Nonferrous Smelting Industry"
      Arthur G. McKee  & Company. Final Report Under
      Contract PH-86-65-85  for U.S. Department of Health,
      Education and Welfare.   June,1969.
                              9-2

-------
APPENDIX
     Construction Cost Estimate - Base  Case  Plant
        (Machinery & Equipment - Account 400)
                                                     SINGMASTER & BREYER
                               App.

-------
                                           CONSTRUCTION COST ESTIMATE
                NAPC
SINGMASTER & BREYER
 DESCRIPTION      BASE   CASE
LOrATION

A

•X-

MOLTEN

CARBONATE



PROCESS

37«


&00
S. IM

A/C
M \A/
COAL

4-OO
, , . , PRO" "B-,
CONT. MO.
uinr nv
APPSOvrn

PS- 21«
J.S. J,

ACCOUNT
NUMBER
4<50

CODE
ITEM & DESCRIPTION
MACHINERY £ EQUIPMENT
ABSORBER AREA
REDUCER AREA
REGENERATOR AREA
COKE HANDLING AREA
M<> CO, MAKE- UP AREA
Li? C0a RecovERY AREA
ANCILLARISS
TOTAL A/C 400
QUANTITY

UNIT

UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
19800
42400
8100
*noo
7200
15310
tzoo
103 110
SUB
CONTRACTS
f, 120000
540000
23000C
7400Q
*
1^64000
MATERIALS
330220
619160
149240
91400
89340
216540
13300
1,514220
TOTAL
1,470020
1t20t(580
3S7340
174500
96540
231 850
19500
3,581330
                                                                                                                 (E 153)
                                        DATE
                                           , 9-    -70
                                                      . REVISION NO..
                          .REVISION DATE
                                                                                              PAGE NO..

-------
CUSTOMER.

LOCATION.
NA  PCA
 CONSTRUCTION COST ESTIMATE

    SINGMASTER & BREYER
	  DESCRIPTION	•_
oo  M.W.
PROJECT A.I  MQLTgM  CARBONATE  PROCESS
                                              3V» SUUFUR  JM CdAtT
                                                                ABSORBER    ARE A
                                                  A/C  4 oo
                        PROP. NO	
                        CONT. no  PS.'Z \B
                        MADE BY S.f.   * J.J.

                        APPROVED 	
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY * EQUIPMENT
TAG N? V-IAJB, 1C * ID
ABSORBER :
28-*"DiA. x 34-0"sTR.SIPE
MATU COMST.- 347 STN.STL.
EQUIPPED WITH SPRAT NOZZLES
WT. =
DEMISTER FOR ABOVE
MATU. CONST. - 347 STM. STL.
635 S.F. - INCLUDES SUPPT, f T
-------
CUSTOMER.

LOCATION.
                    N.APCA
 CONSTRUCTION COST ESTIMATE

   SINGMASTER & BREYER
	  DESCRIPTION	
800  M W
                                                                  3% SULFUR (M  COAL.
                                                                ABSORBER   AREA
PROJECT A.I  MOLTEN CARBDklATE PROCESS
 A/e  4.00
                                                   PROP. NO	
                                                   CONT. no-  PS " 2. \ O

                                                   MADE BY  .S.ft	*' • J

                                                   APPROVED 	
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY « EQUIPMENT
TAG NSV2D
ABSORBER PUMP TANK
T-O"BIA.* I3''0"U
MATL. CONST. 347STN.STL,
LOCATE In PIT.
WT. » qooo*
IMMERSIOKI HEATER (ELEC.*)
WITH ON-OFF THER^y10STAT
30 KW - Fow 1/-2A.B,C* p
MATL. CONST. 347 STN. STL.
T/XIJK INSULATED WITH
5" THK, THSKCM^BESTOS • See
A/C 800
TAG N|2VeA,64G
ABSORBER PUMP TANK
t'-OW » 7-0'U.
MATL.. CONST, S47 STN. STL,
QUANTITY
1
4
3
UNIT
ect.
ed.
e^.
UNIT COSTS
,
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
400
800
IZ00
SUB
CONTRACTS
-
MATERIALS
18400
2800
16200
TOTAL
18800
3600
17400
                                        DATE
                                              ' ' i ' 70
                                                                                                                  (E 153)
                                                       REVISION NO ___
   .REVISION DATE
                                                                                               PAGE NO..

-------
CUSTOMER.
LOCATION.
NAPCA
                                          CONSTRUCTION Co., ESTIMATE
                                             SINGMASTER & BREYER
                                              DESCRIPTION.
800 M.W
                                             3'/0 SULFUR (H COAU
                                                              ABSORBER    AREA
PROJECT A.T. MOLTEN CARBONATE
                                                                    A/c. 400
                                                                        PROP. NO	
                                                                        CONT. no.  "5 ' C. I 5
                                                                        MADE BY 9,F|
                                                                        APPROVED 	
                                                                                                        
-------
   CONSTRUCTION COST ESTIMATE



      SINGMASTER & BREYER
CUSTOMER 1
LOCATION
PPOIECT A.I.MottEN
IN H r u M

CARBONATE
DESCRIPTION



PROCESS
0 U U (VI . W.
3% SULFUR !w COAL
REDUCER AREA

A/C4-00

pp()B W(V
CONT- NO. P O
c c
u»nr BV » ,r.
APPBOvrri

-218
J.J.

ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY 1 EQUIPMENT
TAG N? B-lA.p.c* D
COMBUSTION AIR BLOWER
fcooo CFM FREE AIR @T »;
AP
MATL.- CONST.- CARS, 5reEL
Iwot-upci MOT«K • 300 H.P.
CrtWFLFTC-
4
QUANTITY
4
UNIT
eat
UNIT COSTS
LABOR

SUB
CONTR

MAT'L
I5&00
ESTIMATED COST
CENTS OMITTED
LABOR
4 800
SUB
CONTRACTS

MATERIALS
62400
TOTAL
£7200
                                                                             (E 153)
DATE
          -70
              . REVISION NO..
.REVISION DATE
                                                         PAGE NO..

-------
   CONSTRUCTION COST ESTIMATE



       SINGMASTER & BREYER
i nrATinw
PpniPrTAI MoiTeM CARBONATE PpocCS
3% SULFUR IN COAL
REDUCER AREA

s A/C400
                          PROP. NO



                          CONT. un-



                          MADE BY



                          APPROVED
                                                                      P 3 '  L, \ O
                                                                      5. P.
               J J
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY 4 'EQUIPMENT
TAG N? E-1A £ 1B
REDUCER PRODUCT
COOLER
AIR-COOLSD UNIT WITH
EXTERNAL AIR RECIRCULATION
( STE^M COIL.
COMPLETE WITH 2-10H.R FANS EACH
^ ALL INSTRUMEWTATIOKJ. ETC,
MATL. CONST.: 347 STN. STL,
Q eacK: f3,7«104 Btu/Hu,
A P- 40psi
I3'-0" WIDE > 30-0"Lft.
*
QUANTITY
2
UNIT
ea.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
8000
SUB
CONTRACTS

MATERIALS
1ZOOOO
TOTAL
128000
                                                                                     (E 153)
DATE
     *•} -2. '70   REVISION NO..
.REVISION DATE
PAGE NO..

-------
   CONSTRUCTION COST ESTIMATE



      SWGMASTER & BREYER
CUSTOMER
LOCATION
PROJECT A I
1
IN M K 0 ,H
DESCRIPTION
ouu IYI
3% SULFUR 1

MOLTEN

CARBOKATC PROCPS
RE

,s-
DUC£R

A/e 400
w
N COAL.
AREA



opnp un
P<
CONT. MO. F «
uinr BY Si
APPBOVF1 ,

f?-P



IS
J.J.

ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY ^EQUIPMENT
TAG, N? P-2Afs) ^e6(s)
REDUCER PUMP
5 85 G. P.M. - I56psi AP
4-0" Lc1t SHAFT -4'-o"u, TAIL PIECE
VERTICAL
M ATL . CONST - 347 STN, STL.
MOTOR- ISO H.»J
TAG N2 V-3A.3B,3C^3D
REDUCER (STL.'A-Z04^.A)
M'-O" Qia. y 20-0" T*«T- F^O HEAOi
9"THt, AUUNDUM LlUi>Jf|
4'TMK., MoN'tlFRA^ LitJiNfi,
FULL MouoPjfAX' P/«KTIT/OO
A /fj • ^f*f SSf?*'
COKE BLOW CHA^ofi'R
2 REQ'D. PER REDUCER
QUANTITY
4
4
4
8
UNIT
ecf,
ect
UNIT COSTS
LABOR
(A
SUB
CONTR
iSS'jflfl
/
llowa*
MAT'L
8E25
>ce)
ESTIMATED COST
CENTS OMITTED
LABOR
3200
1600
SUB
CONTRACTS
540,000
MATERIALS
32 900
teodo
TOTAL
36 100
7980
540,000
13600
                                                                            (E 153)
DATE
          -TO
              . REVISION NO._
                                .REVISION DATE
                                                        PAGE NO.

-------
                                            CONSTRUCTION COST ESTIMATE
CUSTOMER
N APCA
SINGMASTER & BREYER
 DESCRIPTION.	800  M. W
                                                                 3% SULFUR  IN COAL
LOCATION.
PROJECT A.f.MoLTEM CAPBDMflTE PROCESS
                                            REDUCER   AREA
                                                  A/e 4.00
                                                 PROP. NO	

                                                 CONT. MO-  PS " 2 I O

                                                 MADE BY  S.F.

                                                 APPROVED 	
                                                                                                             J. J,
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY- £ EQUIPMENT
TAG N2 E-2A, 2(^20 * 2D
AIR-OXIDATION ZONE
EXCHANGER
HEATIMG, SURFACE 770. S.F,
MTL. TUBS £io*-34i STN. 5n.
NiUUAT 6 1> Of.' All? SIDE
Q eorch - 4.5" xlO6 Bta/H«.
A P- , OOO ^/HRj ldOtf5
-------
CUSTOMER.
LOCATION.
N A  PGA
                                              CONSTRUCTION COST ESTIMATE
                                                 SINGMASTER & BREYER
                              DESCRIPTION.
800  MW
                                                 3% SULFUR IN COAL
                                               REDUCER   AREA
PROJECTA.I.MoL-reM CflRBONATS
                                                    A/c.  400
                           PROP. NO	
                           CONT. MO.  PS
                           MADE BY 	
                           APPROVED 	
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY 6 EQUIPMENT
TAG NS V-4A T 4B
REDUCER QUENCH TANK
^'-O'oiA. x 15-0" LoMfi
MATL, CONST. '347 STN, STL,
WT, •• 12,500*
IMMERSION HEATITR (ELEC.)
WITH ON-OFF THERMOSTAT
SOKvv-Fo* ABOVE TANK
MATL. CONST. 347 STN.STU.
TANK INSULATED WITH
5" THK. TueRNiogESTos - 5*6E
A/c 800
4
TAG N* V-8A,6Bf6C78D
COKE BIN
6'-o'x t'-o" - 60* CONE BTM.
4 TON CAPACITY
MATL. CONST.I CARB. STL.
QUANTITY
2
4
UNIT
ea.
eot.
ea.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
800
400
goo
SUB
CONTRACTS
-
MATERIALS
55200
1400
6500
TOTAL
56000
1800
7300
                                                                                                                       (E 153)
                                           DATE  ^-3-70   REVISION
                                             NO._
                                                        .REVISION DATE
                                                                                PAGE NO..

-------
CUSTOMER
N.A. P.C.A
                                          CONSTRUCTION COST ESTIMATE
                                             SINGMASTER & BREYER
DESCRIPTION.
8DQ  M W
                                                                3% SuuFug IM
LOCATION.
PROJECT A I MOLTEN  CARBONATE	PROCESS
                                            REDUCER   AREA
                                                 A/c  400
                                             PROP. NO	
                                             CONT. MO-  P S ' fc. \ S
                                             MADE BY Si T
                                             APPROVED 	
                                                                                                        J.J.
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY? EQUIPMENT
TAG N2 W-IA. IB,1C * ID
WEIGH BELT FEEDERS
S,000*/HR MAX, EACH
INCLUDES LOCAL * REMOTE
IKSTRUMEWTATIOKI AND 2 H-R
Mof^R GA.
«
TOTAL- REDUCER AREA

QUANTITY
4
UNIT
ect.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
2400
4E400
SUB
CONTRACTS

540000
MATERIALS
30000
619180
TOTAL
32400
f,aQ 1,580
                                       DATE
                                                - 70
                                                                                                              (E 153)
                                                     REVISION NO._
                                                                      .REVISION DATE
                                                                                            PAGE NO..
                                                                                                      IQ

-------
CUSTOMER.

LOCATION.
N.A PC A
 CONSTRUCTION COST ESTIMATE

    SINGMASTER & BREYER
	  DESCRIPTION	
&00  M W
                                               3% SULPlJR  In COAL.
PROJECT A.I. MOLTEN  CARBONATE  PROCESS-
                                           REGENERATOR AREA
                                                A/e  4PO
                                                   PROP. NO..
                                                   CONT. NO..

                                                   MADE BY

                                                   APPROVED .
                                 PS-218
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY 4 EQUIPMENT
TAG NS E-4
REGENERATOR BOTTOMS
COOLER
AIR Cooueo UN)IT WITH
EXTERNAL AIR RECIRCULAT/^N
^ ST EAM Coiu
CoMPueT6 WITH 2-5 H.P, FAMS
EACK. 6 ALL INSTRUMENTATION,
MATL. CONST- • 347 STN, STL,
0 eac.hr |0x 10' Biu/HRk
AP - 85 psi
S'-O'W'oe / 24-0 U,
>
QUANTITY
1
UNIT
erf.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
1800
SUB
CONTRACTS

MATERIALS
35000
TOTAL
36800
                                                                                                                 (E 153)
                                        DATE ^ '  *> • 7 0   REVISION
                                                              NO..
                                                     ..REVISION DATE
                                                                                              PAGE NO..

-------
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
CUSTOMER
LOCATION
PROJECT £L
INAKCA DESCRIPTION SUU Mi.W
37» SULFUR

I,

MOLTEN

CAR BOH

Are

p


ROCSSS
P E; .3 j£ (Nj

A/
E

c
R/

4
IN Co^L,
MOR AR

00
ppnp ^n

u»nr nv 5.1% J/J/
APPRnurn
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY a EQUIPMENT
TAG N2 -E-5
REGENETRATOR
INTERMEDIATE COOLER
AIR C^dLGD UNIT WITH
EXTERNAL AIR RECIRCUUATION
^ SJ-CAM COIL
CoMPi-r?Te WITH 2- "7 IE. H,f? FAN*
EACtV, ^ ALU iN^tRUMCK/fATlOfJ
MATL. CONST -347 5TN, 5TL,
Oeao^« I5v 10" BtuV H«,
A P £ 25-f>si '
)OvO"v^»&e y 'E.41-0'
-------
CUSTOMER
                  N A PCA
 CONSTRUCTION COST ESTIMATE

    SINGMASTER & BREYER
	  DESCRIPTION..	
800  M.M/
                                                                    SULFUR
                                                                                 COAL
LOCATION.
                                                             REGENERATOR  ARE.A
PROJ ECT
                   H  GftRSOMATl?
    *  4-00
                                                    PROP. NO	
                                                    CONT. no- »  5 "2 1 8

                                                    MADE BY ^'P'
                                                    APPROVED
                                                                                                            JJ.
ACCOUNT
NUMBER
400







CODE
ITEM & DESCRIPTION
MACHINERY * EQUIPMENT
TAG, |\|e V-5
REGENERATOR
IS'-O" pi A. x 34'6"STf?. 5 |DE
p. £ p, HEAD ^
MATL. CONST 347 STN. STL,
4 ffX.eif. VC. M&~0oo*"
RSe*?u * £7* w r 1" ^ t- 7/4/^01*
TAG N2 V-6
REGEtsJERATOR BOTTOMS
PUMP TANK
7'-0"DlA. X 1310"
MAT L. CONST* 347 STN. STL.
wei^ PT 1 c?^oo''*'
IMMERSION HEATER (EL EC,)
WITH 0NI-0FP THeF?M05TAT
30 KV/ FOP ABOVE TAMK
MATL. CON-ST,- 347 ^"TN . 5TU,
(M5ULATE TANK. WITH
O'THK. THERMO6K5T"0$. SEE
A/o 800
QUANTITY
\



1
I

UNIT
CO..



ea.,
ed.

UNIT COSTS
LABOR







SUB
CONTR







MAT'L







ESTIMATED COST
CENTS OMITTED
LABOR
-

*

400
ZOO-

SUB
CONTRACTS
£30000






MATERIALS
-



18500
700

TOTAL
£30000



18,100
qoo

                                         DATE
                                                \~-f
                                                   ~lO
                                                                                                                   (E153)
                                                        REVISION NO.
                                                                         .REVISION DATE
                                                                                                PAGE NO..
                                                                                                           13

-------
CUSTOMER
N  ARCA
                                          CONSTRUCTION COST ESTIMATE
                                             SINGMASTER & BREYER
                            DESCRIPTION.
BOO  M .
                                                                 SULFUR  IN COAL.
LOCATION.
PROJECT A. I. MOLTEN CARBONATE  PROCESS
                                        REGENERATOR   AREA
                                                Afc AOQ
                         PROP. NO	
                         CONT. UP- rS,~~ Z. I
                         MADE BY ^•^'
                         APPROVED 	
                                                                                                        J.J.
ACCOUNT
NUMBER
400


















CODE
ITEM & DESCRIPTION
JvjACHINERYi EQUIPMENT
TAG-N9 V-7
REGENERATOR
INTERMEDIATE PUMP TANK
&'-&"DIA;< I2.V'L«
MATL. CONST, ;347 STN.STL.
WEIGHT.' 6000*

IMMERSION HEATER (ELBC.)
WITH 0N-0FF THERMOSTAT
30 KW -FOR AB(5Vfc" TAM<.
MATL . COM5T. - 347 STK. STU
INSULATE TANK WITH
5"TH«. THERMOS ESTO^ -See /4/t9
TAG N^ P-3A (s)
REGENERATOR BTMSPUMh
300 Q.P.M. 147 psi AP
4'-C"Lci. SHAFT -Z-O"!.^ TAIL PIECE
VERTICAL • C4KITILEVER
MATL. CONS! 347 STN.STL.
Moto*-75H.r..
QUANTITY

1






I



30.
2
1




2
UNIT

edt






ea,




e«.





eo.
UNIT COSTS
LABOR




















SUB
CONTR




















MAT'L







3





8225





1065"
ESTIMATED COST
CENTS OMITTED
LABOR

500





*
200




1600





•r
SUB
CONTRACTS

.






-




_






MATERIALS

\3bOO






700




16450





2130
TOTAL

14000






too




18050




_ . . — at
2130
                                                                                                              (E 153)
                                       DATE
                                                     REVISION NO..
                                                                      .REVISION DATE
                                                                                           PAGE NO..

-------
CUSTOMER.

LOCATION.
                  N  A P C  A
                                           CONSTRUCTION COST ESTIMATE
                                              SINGMASTER & BREYER
DESCRIPTION.
800  M W
PROJECT A.T. MOLTEN CARBONATE  PROCESS
                                                           	3*A>  SULFUR m COAL
                                                           REGENERATOR    AREA
                                              PROP. NO	
                                              CONT. ™.  PS '21ft
                                                     S.t*.    JJ.
                         400
                          MADE BY
                          APPROVED
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY £ EQUIPMENT
TAG Ne p-4A Cs)
REGENERATOR
INTERMEDIATE PUMP
350 G.P.M. - lOlpcl AP
4'-0"U. SHAFT. -2-0"U.TAiLP«Ece
V/ERT/CAL - CANTIUEVE*
MATL, CONST; - 347 STN. STL,
MOTOR- 60H.P,
TOTAL-REGENERATOR
/-\ r\ L. M,

QUANTITY
e
z
UNIT
ed.
«.Cu.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L.
7470
IUO
j
ESTIMATED COST
CENTS OMITTED
LABOR
1400
»•
8100
SUB
CONTRACTS
—
230000
MATERIALS
14 W
3320
M
-------
                                           CONSTRUCTION COST ESTIMATE
CUSTOMER.

LOCATION.
N  A  P C A
SINGMASTER & BREYER
 DESCRIPTION	
800
                                              3% SULFU*  IN COAI-
PROJECT A.I MOLTED CARBONATE.  PROCESS
                                           COKE  HANDLING  Af?(=A
                                                   a/£40o
                         CONT. NO..

                         MADE BY ,

                         APPROVED .
ACCOUNT
NUMBER
400





CODE
ITEM & DESCRIPTION
MACHINERY ? EQUIPMENT
TAG. N2 C-1
COKE RECEIVING HOPPER
BELOW Qf?At>e /-OR (?,!?, UjjLdADiMft
50 TotJ CAPACITY
MATL. CONST;- GARB, STL,
TAG N* C-IA
CRUSHER -50"
2. ROW CAGE MU-L
Iwcuuoes • OwE-l25H.P. MOTOR
ONE- !OOH,fk MOTOR
QUANTITY
1

1


UNIT
ect.

~


UNIT COSTS
LABOR





SUB
CONTR





MAT'L




^
ESTIMATED COST
CENTS OMITTED
LABOR
400

1500


SUB
CONTRACTS
—

-.'


MATERIALS
4900

23500

•
TOTAL
5300

E5000


                                                                                                                (E153)
                                        DATE
                                                      REVISION NO..
                                                     .REVISION DATE
                                                                                             PAGE NO..
                                                                                                         /6

-------
                                             CONSTRUCTION COST ESTIMATE
CUSTOMER.

LOCATION.
M A P C  A
SINGMASTER & BREYER
 DESCRIPTION	800  M W
                                                 3*/o SULFUff  Ikl
PROJECT A.IMOLTEH CARBOHATE  PROCg55
                                                     UANPUN6  AffEA
                                                           4DP
                                                  MOP. MO.     	
                                                  COMT. no  PS ' 2 IP

                                                  MADE BY £• f-

                                                  APPROVED .
                                                                                                                J.J
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
^/1ACHlNERY^ EOUIPMENT
TAG N^ G-l
TRANSFER CONVEYOR
i FEEDER
50 TOMS/HR,
INCLUDES 2 • 1 H.P. MOTORS
TAG NS G-2
BUCKET ELEVATOR
50 TONS/HR. - 25l-oHi,T» t
iNcuuoes • ONE 3H.P, MOTOR
QUANTITY
1
1
UNIT
ed
&
-------
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
msTOMER IN.M.K. UA
I nrATinw
ppmerTA.7. MOLTEN CARSOWATP PR<
DESCRIPTION £5UU FVI W
3/a SlJLFt/f? IN O0AL.
COKE1 HANDUN6 AREA

3CES5 4/C 400

fltOf xn

... M*nr BY Jf'f'.. 	
iPDnnyfn __ 	 ..,_

?i£
J.«i

ACCOUNT
NUMBER
400






CODE
ITEM & DESCRIPTION
MACHINERY i EQUIPMENT
TAG N« G -3
BUCKET ELEVATOR
50 TOhJs/HR - 60-0" 
-------
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
LOCATION
PROJECT .

A

J-

MOLTEN

CARBONATE PROCESS

CO


3 'A
KE


SUUFUR IN COAL.
HANDLING

Ale 400
AREA


PROP. NO __
e
CIHfT. NO. r
"APE PY _£j


'£ • 2 / «
.IT, J.



J-

ACCOUNT
NUMBER
400





CODE
ITEM & DESCRIPTION
MACHINERY 4 EQUIPMENT
TAG N2 G-B
C0i<£ BELT. CONVEYOR
liNcuupes DISTRI 6Uf IPN
CONVEYOR W»TH BELT
Owe- 5 u.R MOTOR.
TAG N5 G-6
DUST COLLECTOR
TA& N2 G-5A
ELEVATING BELT CONVEYOR
IS" Wipe X 170-0" incuopes
MOTOR Ak

MAT'L



ce)

ESTIMATED COST
CENTS OMITTED
LABOR
1200

s
900
1400
SUB
CONTRACTS
-


-

MATERIALS
13000


6000
16500
TOTAL
14200
•

6900
!7
-------
CUSTOMER.
LOCATION.
                 N.A.P C A
 CONSTRUCTION COST ESTIMATE
   SINGMASTER & BREYER
	  DESCRIPTION	
800  M  W
                     3% SULFUR
                                                                             COAI
pROJECTATi MOL.TEN  CARBONATE  PROCESS
                                                         COKE  HANDLING AREA
                            401)
                        PROP. NO	
                        CONT. no. rS * 2. * O
                        MADE BY 4* ft
                        APPROVED ______
                                                                                                       JJ.
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY 4 EQUIPMENT
TAG. N2 G-7 ^ 6-8
COKE SILO DUST COLLECTOR
Mou»Jrao ON TOP OP T-l \ T-2.
INCLUDES ONE _H,P, FAM each.
v
TAG N2 S-1
COKE SCREEN
50 ToiMs/HR. V
ROTGX • 5 -O" Kll'-o*
IMCLUDB*- T/v w,p, M
-------
CUSTOMER.
LOCATION.
N A P. C A
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
       DESCRIPTION
                              800
                     COKE
PROJECT A.I. MQL.TEM  CARBON/ATS
                             Ac 400
                                                                                PROP. NO
                                                                                CONT. NO. _£_£_
                                                                                MADE BY   *'*•
                                                                                APPROVED
                                                                      J.J.
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY ^EQUIPMENT
TAG N2 T-f i T-2
COKE STORAGE SILO
sooioN-LivE STORAGE EACH
CONCRETE. STAVG
^0-0" Dlft. X- 60'-0"H»SH
Does NOT iMCUUorJO F^U^PAT-IOW
•»
TOTAL -COKE HANDLING
	 ARtLA

QUANTITY
2
UNIT
edt.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
fe
Sioo
SUB
CONTRACTS
74000
74000
MATERIALS

91400
TOTAL
74000
*
174500
                                                                             (E153)
DATE
               . REVISION NO..
                                 .REVISION DATE
                                                         PAGE NO..
                                                                    21

-------
                                          CONSTRUCTION COST ESTIMATE
CUSTOMER.

LOCATION.
                 MA  PC A
 SINGMASTER & BREYER
  DESCRIPTION	
                                                                   800
                  3% SULFUR la  COAL.
               UCOg MAKE-l/P AREA
PROJECT A.T MaiTEM  CARBONATE
                                                                                           PROP. NO --
                                                                                           CONT. NO. r 5 " g IO

                                                                                                   >    »* ** •
                                                                       400
                                               MADE BY

                                               APPROVEO
ACCOUNT
NUMBER
^00







CODE
ITEM & DESCRIPTION
MACHINERY* EQUIPMENT
TAG N* G-
-------
CONSTRUCTION COST ESTIMATE
   SINGMASTER & BREYER
riJSTOMER N
LOCATION
PROJECT AT- MOLTEN
AHUM DESCRIPTION OW IYI W

CARSONATP



PROCESS
3% SUUPUJ? IN COAJ-
tVUCCU MAKE-UP ARE

A/c 400
PROD un-

u.nr BV 6. F. «l • J»
APRROvrn ,
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY f EQUIPMENT
TAG NS W-2,3 T4
WEIGH FEE"DER
foo LBS/HK. CAPACITY
WITH ReMOTC 1 WSTRUMeh/TS
^ ONE H.^ Marop}.
TAG N2 V-9
M^COs MELT TANK
MATL, CcPN^'H' 347 STN.^TL,
WE IGHT. i", 5"(3c) L0 5.
IMMERSION HEATER (euec>
Vv'lTU OH -OFF TH6flM05TAT.
MAIL, CONST, 347 5TN. 5TL,
IMSULATE TANV^- U/ITH 5'TH^/
J/-i£'KM(7 6£i Jo5 - ?6G ^/o 500
QUANTITY
3
1
2
UNIT
CO.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
2300
400
500
SUB
CONTRACTS
-
MATERIALS
25000
11300
4600
TOTAL
27300
*
11700
5iOO
                                                                          (E 153)
   I ' 
-------
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
CUSTOMER
LOCATION
PROJECT A I M0
IN A K U H

'LTGM CARBONATE PROCB^S
DESCRIPTION OUV IYI.W,
3% SULFUR IN COAL
M«C03 MAKE-UP AREA
fa •*•
A/c 4-00

......_ PROP. HO-.
___ ^o«T »0- ,.
... M'OF PY ,
APPHm/rn

PS-218
S.F J.J.

ACCOUNT
NUMBER
400

CODE

MAC
ITEM & DESCRIPTION
HlNERY t EQUIPMENT
TAG N2 T*3.4^ 5
Ntf,C03 SILO, K2CQ3 SILO
* L.2 C03 SlLb 3
IO'.OWDIA. x201-OuSTR.-60°CONE
MAIL. CONST.: CARB. STL.
DUST COLLECTOR FOR
ABOVE SILOS
TAG N-° P-B
M2C03 MAKE-UP PUMP
4 GPM 1Z psl
VERTICAL
3'-0" SHAFT • 2'-0" TAILP(£C&
MATL. CONST. -347 STM. STL.
MSTOR- 5H.P
TOTAL-M2C03 MAKE-UP AREA

QUANTITY
3
3
1
1
UNIT
e
-------
CUSTOMER
N A  P C A
 CONSTRUCTION COST ESTIMATE

   SINGMASTER & BREYER
	  DESCRIPTION	
800 M  W
                                                                3%> SULFUR  IN COAL.
LOCATION.
PROJECT A.I.MOLTEN CARBONATE PROCESS
                                          LUGO* RECOVERY AR£A
                                                A/c  400
                                                  PROP. NO..

                                                  CONT. NO.

                                                  MADE BY

                                                  APPROVED
                              PS-2 18
                                     N.P.
ACCOUNT
NUMBER
400

CODE
ITEM X DESCRIPTION
MACHINERY \ EQUIPMENT
TAG MS B-IOI
EXHAUST FAN
3600 CFM @ 3"H20 ' 5 H.R
TAG Ne B- \OZ
HOT AIR BLOWER
ZSH.P. KOTO* P« ^S»l/J
QUANTITY
1
f
UNIT
e<*
e- 10-70
                                                                                                               (E 153)
                                                      REVISION NO..
                                                                      .REVISION DATE
                                                                                            PAGE NO..

-------
CUSTOMER
LOCATION
N A P CA
CONSTRUCTION COST ESTIMATE

   SINGMASTER & BREYER
    DESCRIPTION
800 M

II MOLTEN CARBONATE



PROCESS

LU
*"*

3% SULFUR IN COAL
CO, RECOVERY AREA
**
A/c 4-00
,,,„ PROP, >"> -
_ rnwT uo. "
. , M'PF HY J?l,
^ APPROVED

S -2.IB
j»t M,^

ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY EQUIPMENT
TAG N? D-101
Ll^COa DRVER
570LBS/HR. DRV LLZ C03
4540 MOISTURE FEED
DIRECT F/RED 800,000 Btu/HR.
NAT. GAS
4-0" DIA. x 30'-0"L<;;. COMPLETE
WITH 7'/7.HF5DRi\/e. 5 HP, FA* 4
PAS FILTER
MATL. CONST. -CARB. STL,
FEEDER Iwcu. ZHR MOTOR
QUANTITY
1
1
UNIT
e<*
ea,
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
1500
eoo
SUB
CONTRACTS
-
MATERIALS
26700
1500
TOTAL
ZBZ06
i700
                                                                                                                  (E153)
                                         DATE
                                                      . REVISION NO._
                                                                        .REVISION DATE
                                                                                               PAGE NO..

-------
CUSTOMER.

LOCATION.
                N.-A.P.C A
 CONSTRUCTION COST ESTIMATE

   SINGMASTER & BREYER
	  DESCRIPTION	
800 M.W
                                                             3'/* SULFUR  (N COAL
PROJECTft.I.MouteN CARBONATE  PROCESS
                                                         Lt»CO* RECOVERS AREA
                                                                                        PROP. ""••
                                                      PS -
                         d/g  400
                        MADE BY
                        APPROVED .
                                                                                              s.t.
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY ^ EQUIPMENT
TAG N2 F- 101
Li2C03 FLY ASH FILTER
150 S.F. -6'-0"DiA x&-OuFfics
COMPLETE WITH ;
VACUUM PUMP -50 HP.
T (07
P-102 POMP 4 2 HP MOTOR
FiuTER DRIVES- IMP. M
-------
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
CUSTOMER IN A K U M
LOCATION
pRoiPrr A.I. MOLTEN CARBONATE PROCESS
DESCRIPTION

Lu


ovu m.w,
3% SULFUR IN COAL
CO* RECOVERY ARE-fi

A/e 4-00

.. — PROP. HO-
Y . _ eouT. uft. ,
	 	 uinr av
,, APPROvrn

P5.-2/S
S'.R /«.f?

ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY i EQUIPMENT
TAG N^ F-102
FLY ASH FILTER
(SAME AS r-toi)
TAG Ne F-103
Li2 C0a FILTER
COMPLETE WITH f
VACUUM PUMP - 20 H,e
P-I07 PUMP i \^tiiP> MOTOR
A^JTATo1? DRIVE = '/^ H-R MOTCJ?
t-iLTcr? DRIVH v yz. H.R Moyon
QUANTITY
1
f
UNIT
ea.
eci.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR

1600
1600
SUB
CONTRACTS

MATERIALS
35000
20000
TOTAL
3 6 BOG
21600
DATE  ^-10-73 REVISION WO
REVISION DATE
                      PAGE NO
                                 O
                                                                         (EI53)

-------
                                           CONSTRUCTION COST ESTIMATE
CUSTOMER.

LOCATION.
NAPC A
SINGMASTER & BREYER
 DESCRIPTION	
                                                                     800
                                                 3%, SULFUR w COAL
                                              ; CO, RECOVEFPV AREA
PROJECT A I  MflLTEM CARBOtlATR
                                                PROP. "»-.

                                                CONT. MQ-
                                                                                                        "fc »O
                                                    A/c 400
                                                   BY .^* *
                                               APPROVED _
                                                                                                          N.P.
ACCOUNT
NUMBER
tl00

CODE
ITEM X DESCRIPTION
MACHINERY 1 EQUIPMENT
TAG KJ2 G-IOI
PRIED LL2C03 CONVEYOR
PEDLEK TYP*£
- 40'-0X RUN)
INCLUDES 2 HR MOTOR
MAIL. CONST, - CAR£, 5TU-
QUANTITY
1
UNIT

eat
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
400
SUB
CONTRACTS

MATERIALS
3000
TOTAL
3400
•
                                                                                                                 (E 153)
                                         DATE
                                                       REVISION NO..
                                                                        .REVISION DATE
                                                                                              PAGE NO..

-------
CUSTOMER.
LOCATION.
                 N  A P C A
                                            CONSTRUCTION COST ESTIMATE
                                               SINGMASTER & BREYER
       DESCRIPTION.
                             BOO  M.W
                                                                   3%  SUC.RIR  IN COAL
PROJECT A I MoLTEU CARBOMATE PROCESS
                     Lu
                                                                                      ARE.A
                              A/c 400
PROP. NO
CONT. ""-
MADE BY  5. F
APPROVED
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY* EQUIPMENT
TAG Nep-1Q1A^B
U2C03 FLY ASH FILTER
3 FEED PUMP
20 GPKf 
-------
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
CUSTOMER
LOCATION
PROJECT AJ
IM

MOLTEN
H K U H

CARBONATE


PROCESS
DESCRIPTION
3%
LuCO*
** *"'

<_/UU IVI, V
SUURJR IM
V

COAL
RECOVERS

A/c 400

AREA


PROP
CONT.
MADE
NO
NO.
BY

PS-
t.F.

21*
M.J».
APPROvrn
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY* EQUIPMENT
TAG MS P-104A
FLY ASH FILTER FEED
PUMP
3o GPM @ 70'-o" TDH
SPEC. GR-M - HORIZONTAL
INCLUDES 1 HP MOTOR
MATL. CONST,- CAST IRON
TAG N? P-I04-B
SPARE PUMP FOR
P-I04A £ P-I06
TAG M5 P-105
Li7C03 REACTOR PRODUCT
PLTMP
EOO GPM @ !5'-6" TDH
SPEC, GR. r l»l ^ hoRIZOUTAL
INCLUPKS J'A H.P. MOTOR
MATL. CONST,' CAST IRON
QUANTITY
1
I
I
UNIT
ea.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR

ISO
180
200
SUB
CONTRACTS
-
MATERIALS
750
750
900
TOTAL
930
930
1100
                                                                            (E IS3)
     -'"   II  - *7 f\
DATE  I   ' '   '*J REVISION NO..
                                 .REVISION DATE
PAGE NO..
          3/

-------
                                          CONSTRUCTION COST ESTIMATE
CUSTOMER
N A  P  C  A
SINGMASTER & BREYER
 DESCRIPTION	
                                                                    800  M
LOCATION.
PROJECT A. i. MOLTEN CARBOHATE  PROCESS
                                               3% SULFUR IN COAL
                                            LuCQ3 RECOVERY  AREA

                                                   A/c 400
                                               PROP. NO..

                                               CONT. NO..

                                               MADE BY  5. P.

                                               APPROVED -
P5-2 (8
                                                                                                         H.P.
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY t EQUIPMENT
TAG Ne P- (06
Li2C03 FILTER FEED
PUMP
3D GPM @ 70'-0" TDH
SPEC. GR. :UI •HOR1ZONTAJL
INCLUDES 1 HP MOTOR
MATL. CONST,- CAST IRON
TAG N2 p-107
TAG N4 P- 108 4 ?lo<\
LitCOs REACTOR FEFO PUMP
2006PM 
-------
CUSTOMER
N  A P C A
 CONSTRUCTION COST ESTIMATE
    SINGMASTER & BREYER
	  DESCRIPTION	
BOO   M  W
                                                                 3% SULFUR IN COAL
LOCATION.
PROJECT A.I. MOLTEN  CARBONATE Process-
                                                    RECOVERY  AREA
                                                   PROP. NO	
                                                   CONT. MO-  r S ' C, \ D
                                                          S.F.
                                                  A/c  4-00
                                                   MADE BY
                                                   APPROVED
                                                                                                           N.P.
ACCOUNT
NUMBER
400


















CODE
ITEM & DESCRIPTION
MACHINERY $ EQUIPMENT
TAG NS T-101
FLY ASH CAKE SLURRY
TANK
5'-0"DIA,x 6'-0"STB. -60° COME
BTM, - OPEW TOP
MAIL. CONST, --CARB. STL,
TAG N5 A-102
AGITATOR FOR TANK T-J01
INCLUDES 3H.P. MOTOR
TAG N? T- 102
Li2C03 FLY ASH FILTER
CAKE RECEIVER
6'-D"DiA. > 5-o"STR. - 60° CONE
BT M, - OPEN TOP
MAIL. CONST. - CAR6. STL-
TAG m A-104
AGITATOR FOR TANK T'I02
INCLUDES 5H.P, MOTOR

QUANTITY

1





I


f





1



UNIT

ea.





e.a.


ec?,





eo..



UNIT COSTS
LABOR




















SUB
CONTR




















MAT'L




















ESTIMATED COST
CENTS OMITTED
LABOR

300





ieo


300





150



SUB
CONTRACTS

-





-


m









MATERIALS

3500





500


4Z00





600



TOTAL

3800





620


4500





750



                                                                                                                  (E 153)
                                         DATE
                                                    -70
                                                       REVISION NO..
                                                                        .REVISION DATE
                                                                                               PAGE NO..
                                                                                      33

-------
   CONSTRUCTION COST ESTIMATE
      SINGMASTER & BREYER
LOCATION
PROJECT 4.

1, MOLTEN

CARBC?UATE PROCESS-
3% SULFUR Id COAL.
Li, CO* RECOv/eRV AREA

A/c400
                                                           PROP. NO
                                                           CONT. MO- PS* £ 18
                                                           MADE BY  ^'F-	
                                                           APPROVED
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY $ EQUIPMENT
TAG N2 T-103
LiHC03 REACTOR PRODUCT
SUR5E TANK
7-0 DIA. V 7-0'5TR. •
?O*CONE STM. • OPEN TOP
MATL, CONST.-- GARB. STL.
TAG N2 A- 105
AGITATOR FOR TANK T-103
[uc-Luoes B H, P. MOTOR
TAG NS T-104
LI:C03 REACTOR PRODUCT
SURGE" TANK
T-O'DIA.X 7'0"5TR,
^0" cone 3iM.- OPEN TOP
MAIL. CONST: CARB, STL,
TAG N? A- 107
AGITATOR FOR TANK T-104
iNCtuaec 5 H.P- MOTOR
QUANTITY
1
1
1
f
UNIT
e&,
ea.
ea.
ea.
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
300
150
30(3
150
SUB
CONTRACTS
—
MATERIALS
3W
550
3900
550
TOTAL
4-ZOQ
700
4aoo
700
                                                                                 (E 153)
DATE
                REVISION NO..
                                   .REVISION DATE
                                                            PAGE NO..
                                                                       34-

-------
CUSTOMER.

LOCATION.
N -A P C A
 CONSTRUCTION COST ESTIMATE

    SINGMASTER & BREYER
	  DESCRIPTION	
                                                                  800
                                                  SULFLIK IN COAL
PROJECT A,I MOLTED  CARBONATE  PROCESS-
                                                   RECOVB?y  AREA
                                                   A/e 400
                                                  PROP. NO	
                                                  CONT. MO-  PS* C I "

                                                  MADE BY  S'F'

                                                  APPROVES	
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY { EQUIPMENT
TAG N2 T- 105
WET Li2C03 SURGE DRUM
4'-0"x4'-0**x4-0" - '/4"THK,
ATMOS. PRESS,
MAIL, COMST- CARB, STL,
TAG N5 T-10^>
LU C03 STORAGE
fO'-o'DiA.y T-0"5Tfz.
60" COME BTM- FuArT-sp
MATL, CONST- CARB. STL.
QUANTITY
1
i
UNIT
e
-------
                                          CONSTRUCTION COST ESTIMATE
CUSTOMER.

LOCATION.
                N A  PC  A
SINGMASTER & BREYER
 DESCRIPTION	800  M.W.
                                                               3% SULFUR  In COAL.
                                                                    RECOVERY AREA
PROJECT A.I. MOLTEN  CARBONATE
                                                                   A/c  40CT
                                               PROP. NO

                                               CONT. MO- PS' 2 18

                                               MADE BY  £•'•   "'**

                                               APPROVES
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY \ EQUIPMENT
TAG N? T-107
SOLUBLE SALT RECEIVER
TAG MS T-108
LiHCOj FILTRATE RECEIVER
TAG Ne T-IO?
Li2C03 FILTRATE RECEIVER-
QUANTITY
1
1
1
UNIT
ed,
eoL
ei,
UNIT CC3TS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
INCLUDE!
INCLUDED
INCLUDED
SUB
CONTRACTS
> IN COST
IN COST
IN COST
MATERIALS
OF M01
OF P-102
OP F-103

TOTAL
—
                                        DATE  \ ' '" '/ 0   REVISION NO..
                                                                       .REVISION DATE
                                                                                             PAGE NO..
                                                                                                               (E 153)

-------
                                         CONSTRUCTION COST ESTIMATE
CUSTOMER

LOCATION.
N..AP. C..A.
S1NGMASTER & BREYER
 DESCRIPTION	   800
                                                 SULFUR IN COAL
PROJECT A.I. MOLTEN CARBOUATE  PROCESS
                                                  RECOVERY AREA
                                                 A/c 4 00
                                             PROP. NO

                                             CONT. HO.

                                             MADE BY S-'»

                                             APPROVED
•2 16
ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY { EQUIPMENT
TAG N? T- HO
DISSOLVING SUMP
CONCRETE •£ COMPARTMCMTS
6'-0"x fe'"0"x 6-0' A<3ITATtOM COM P.
E-0\ fe'-O'x 6-0* PuMPifj^ CoMP,
TAG Ns A -101
AGITATOR rORSUMPT-110
lNcLuz»ir«i
-------
CONSTRUCTION COST ESTIMATE
   SINGMASTER & BREYER
ruvroMER IN M r ^ H DESCRIPTION OUU ]YI, W,

inrATiow

PROJECT A. 1. MOLTEN CARBONATE PROCESS
3% SULFUR IN COAL
LI, CO, RECOVERY
' **"
A/c 400
AREA


_ PROP. V°-,
CONT. NO.
MADE SY
	 	 	 APPROVES
.
PS-210
5.f- N.P,

ACCOUNT
NUMBER
400

CODE
ITEM & DESCRIPTION
MACHINERY i EQUIPMENT
TAG N? V-10!
LiHC03 REACTOR
t'-CoM.yg'-O* T.L. IDDLB, DESIfjN PRESS,
MAIL- CONST, -CARS. STL.
TAG N* A- 103
AGITATOR FOR REACTOR V-101
INCLUDING 5 H-P. MOTOR
TAG MS V-102
L[2C03 REACTOR
(,'- t'jr SV TL. - 10 |.B, DESl6f4 PRPS5
MATL. CDKST, rCARB. STL.
TAG N2 A- 106
AGITATOR FOR REACTOR V-ID2
IwcLUDiKiq 5H.P. MOTOR
QUANTITY
1
1
1
1
UNIT
e
-------
                                         CONSTRUCTION COST ESTIMATE
CUSTOMER
        N A PC A
SINGMASTER & BREYER
 DESCRIPTION	
                                                                 800  M  W
                                                             3 7o SULFUR IN COAL
PPOiPcr
A-LMoLTEM CARBONATE  PpocESi
                                                  l^CO* RECOVERY ARE/T
                                                                                         PROP. NO..
                     A/c 400
CONT. NO

MADE BY -$ P-

APPROVES 	
                                                                                              PS - 2T8
ACCOUNT
NUMBER
400






CODE
ITEM & DESCRIPTION
MACHINERY ( EQUIPMENT
TAG N? X" 101
C02 GENERATOR (|2% C02)
70,000 SCFM OF GAS
6,500 SCFM OF COZ
FUEL -- NATURAL GAS • 3,000 SCFM
f, G. GEKIERATOR BLOWER
, 30 H,F? MOTOR
COMPRESSOR To SUPPLY 75psi GAS
200 «,p. MOTOR
COOLJMQ WATE^ » 75 GPM
ALL OF THE ABOVE SKIP
MOUNTED
TOTAL- Li2C03 RECOVERY

QUANTITY
t





UNIT
ea.





UN IT COSTS
LABOR






SUB
CONTR






MAT'L






ESTIMATED COST
CENTS OMITTED
LABOR
E000





15310
SUB
CONTRACTS
«•»





—
MATERIALS
47000




-f 10
El 6540
TOTAL
49000




f!6
23 1 S50
                                                                                                           (E 153)
                                       DATE;
                                           1-10-70
                                                    REVISION NO..
                                                                    .REVISION DATE
                                                                                          PAGE NO..

-------
CONSTRUCTION COST ESTIMATE
   SINGMASTER & BREYER
LOCATION.
PROJECT A.
3% SULFUR IN Co A

I,

MOLTGM

CARBONATE


PROCESS
AMCILLARIES

400
U i PDnP, 1"n
eouT. un. PS.* 2.1 O
u»nr BV 6 P- •/-«•
APPRnv/rr, ,
ACCOUNT
NUMBER
400
k
CODE
ITEM & DESCRIPTION
MACHINERY 4 EQUIPMENT
INSTRUMENT AIR
COMPRESSOR AMP
RECEIVER- 5-0 H.P, Morale,
INSTRUMENT ./\IR
DRY ER ~ i° K^-
TOTAL -ANCILLARIES
QUANTITY
1
1
UNIT
LOT
ex
UNIT COSTS
LABOR

SUB
CONTR

MAT'L

ESTIMATED COST
CENTS OMITTED
LABOR
w
300
1200
SUB
CONTRACTS
-
-
MATERIALS
12300
6000
I830Q
TOTAL
13200
6300
moo
                                                                         (E 153)
     cj
DATE  I
            . REVISION NO.
                              .REVISION DATE
                                                     PAGE NO..

-------