FINAL TEST REPORT

         MAIN REPORT

             FOR

     USEPA TEST PROGRAM
          CONDUCTED AT
     PINE HALL BRICK PLANT
  MADISON, NORTH CAROLINA
USEPA CONTRACT NO. 68-D2-0029
   EMB WORK ASSIGNMENT 6
          AUGUST 1993
      ETS CONTRACT NO. 92-655

-------
                        TABLE OF CONTENTS
                                                            PAGE

1.0  INTRODUCTION 	      1

     1.1  SUMMARY OF TEST PROGRAM	      1
     1.2  KEY PERSONNEL	      2

2.0  PROCESS DESCRIPTION AND SAMPLING LOCATIONS  	      2

     2.1  CRUSHING, GRINDING, AND  SCREENING OPERATION  .  .      2

     2.2  SAWDUST DRYER OPERATION  	      3

     2.3  FLUE GAS, PROCESS AND BACKGROUND SAMPLING
          LOCATIONS	      3
          2.3.1  PLANT BOUNDARY LINE	      3
          2.3.2  PRIMARY CRUSHER   	      3
          2.3.3  GRINDING BUILDING  	      4
          2.3.4  KILN OUTER/SAWDUST DRYER INLET  	      4
          2.3.5  CYCLONE OUTLETS   	      4

3.0  SUMMARY AND DISCUSSION OF TEST RESULTS	      4

     3.1  OBJECTIVES AND TEST MATRIX	      4

     3.2  TEST MATRIX	      5

     3.3  FIELD TEST CHANGES AND PROBLEMS 	      5
          3.3.1  AMBIENT SAMPLERS  	      5
          3.3.2  SAWDUST DRYER SAMPLING  	      5
                 3.3.2.1  PERCENT  ISOKINETICS 	      5
                 3.3.2.2  CONTINUOUS EMISSIONS MONITORING
                          CALIBRATION DRIFT 	      6
                 3.3.2.3  ANALYTICAL CHANGES AND PROBLEMS      6
                 3.3.2.4  MISCELLANEOUS  CHANGES AND PROBLEMS   6

     3.4  PRESENTATION OF RESULTS	      6
          3.4.1  CRUSHING, GRINDING AND  SCREENING
                 OPERATION SAMPLING  	      6
                 3.4.1.1  AMBIENT  SAMPLING  	      6
                 3.4.1.2  PARTICULATE AND PM10 SAMPLING  .      7
                 3.4.1.3  PROCESS  SAMPLING  	      8
          3.4.2  SAWDUST DRYER SAMPLING  	      8
                 3.4.2.1  PM, PM10, CPM EMISSIONS AND
                          PARTICLE SIZING 	      8
                 3.4.2.2  TRACE METALS EMISSIONS   ....      9
                 3.4.2.3  TOTAL FLUORIDE RESULTS   ....      9
                 3.4.2.4  HYDROGEN FLUORIDE EMISSIONS  .  .      9
                 3.4.2.5  CO EMISSIONS	      9
                 3.4.2.6  NOX EMISSIONS   	      9
                 3.4.2.7  THC EMISSIONS  	     10
                 3.4.2.8  VOC EMISSIONS	     10

-------
                     TABLE  OF CONTENT  Cont . }
                 3.4.2.9  SVOC EMISSIONS
                 3.4.2.10  PROCESS SAMPLING
4.0  SAMPLING AND ANALYTICAL PROCEDURES
     4.1  TEST METHODS  .................
          4.1.1  AMBIENT PARTICULATE MATTER
                 (PM AND PM10) - HI-VOL  .........     1J-
                 4.1.1.1  AMBIENT HI-VOL AND PM10 ANALYSES11
          4.1.2  VOLUMETRIC FLOW MEASUREMENTS  ......     11
          4.1.3  MOLECULAR WEIGHT DETERMINATION .....     1;L
          4.1.4  FLUE GAS MOISTURE CONTENT  .......     12
          4.1.5  PM10 SAMPLING-EPA METHOD 201 AND 201A   .     12
                 4.1.5.1  SAMPLING TRAIN DESCRIPTION   .  •     12
                 4.1.5.2  PRE-TEST PREPARATION  .....     13
                 4.1.5.3  SAMPLING TRAIN OPERATION   ...     13
                 4.1.5.4  SAMPLE TRAIN RECOVERY .....     13
                 4.1.5.5  PM10 ANALYSES  .........     13
          4.1.6  TOTAL FLUORIDE SAMPLING - EPA METHOD 13B     14
                 4.1.6.1  SAMPLING TRAIN DESCRIPTION   .  .     14
                 4.1.6.2  SAMPLING TRAIN OPERATION   ...     14
                 4.1.6.3  SAMPLE RECOVERY  ........     14
                 4.1.6.4  FIELD BLANKS  .........     14
                 4.1.6.5  TOTAL FLUORIDE ANALYSES  ....     14
          4.1.7  MULTIPLE METALS WITH PM - EPA MULTI
                 METALS PROCEDURE ............     15
                 4.1.7.1  SAMPLING TRAIN DESCRIPTION   .  .     15
                 4.1.7.2  SAMPLE TRAIN PREPARATION   ...     15
                 4.1.7.3  SAMPLE TRAIN OPERATION   ....     15
                 4.1.7.4  SAMPLE RECOVERY AND CLEAN-UP  .     16
                 4.1.7.5  FIELD BLANKS  .........     16
                 4.1.7.6  PM ANALYSES - EPA METHOD  5   .  .     16
                 4.1.7.7  MULTI-METALS ANALYSES
                          EPA MULTI-METALS  .......     16
          4.1.8  PM10/CPM  SAMPLING -  EPA METHOD 201A/202      17
                 4.1.8.1  SAMPLING TRAIN DESCRIPTION   .  .     17
                 4.1.8.2  PRE-TEST PREPARATION  .....     17
                 4.1.8.3  SAMPLING TRAIN OPERATION   ...     17
                 4.1.8.4  SAMPLE RECOVERY AND  CLEAN-UP  .     18
                 4.1.8.5  FIELD BLANKS  .........     18
                 4.1.8.6  CPM ANALYSES - EPA METHOD 202 .     18
                 4.1.8.7  PM10 ANALYSES - EPA METHOD 201A     19
          4.1.9  PARTICLE SIZING - ANDERSON IMPACTOR  .  .     19
                 4.1.9.1  SAMPLING TRAIN DESCRIPTION   .  .     19
                 4.1.9.2  SAMPLING TRAIN OPERATION   ...     19
                 4.1.9.3  SAMPLE RECOVERY AND  CLEAN-UP  .     19
                 4.1.9.4  ANDERSEN IMPACTOR ANALYSIS   .  .     20
          4.1.10  HYDROGEN FLUORIDE  (HF) - EPA METHOD 26     20
                 4.1.10.1 SAMPLING TRAIN DESCRIPTION  .  .     20
                 4.1.10.2 SAMPLE TRAIN OPERATIONS  ....     20
                 4.1.10.3 SAMPLE RECOVERY AND  CLEAN-UP  .     20

-------
                    TABLE OF CONTENT  (Cont.]


                 4.1.10.4 FIELD BLANKS  	    20
                 4.1.10.5 HYDROGEN FLUORIDE ANALYSES  .   .    21
          4.1.11  CONTINUOUS MONITORING FOR 02/  C02, CO,  NOX
                  AND THC - INSTRUMENTAL METHODS  ....    21
                 4.1.11.1 SAMPLING SYSTEM DESCRIPTION .   .    21
                 4.1.11.2 DATA ACQUISITION SYSTEM ....    22
                 4.1.11.3 CALIBRATION 	    22
          4.1.12 METHANE AND ETHANE SAMPLING
                 EPA METHOD 18	    22
                 4.1.12.1  SAMPLING TRAIN DESCRIPTION .   .    22
                 4.1.12.2 PRE-TEST BAG PREPARATION  ...    23
                 4.1.12.3 SAMPLING TRAIN OPERATION  ...    23
                 4.1.12.4 ETHANE AND METHANE ANALYSIS .   .    23
          4.1.13 VOLATILE ORGANICS SAMPLING 	    23
                 4.1.13.1 SAMPLING TRAIN DESCRIPTION  .   .    23
                 4.1.13.2 SAMPLE TRAIN OPERATION  ....    23
                 4.1.13.3 SAMPLE RECOVERY AND CLEAN-UP   .    24
                 4.1.13.4 FIELD BLANKS  	    24
                 4.1.13.5 VOLATILE ORGANICS ANALYSES  .   .    24
          4.1.14 SEMIVOLATILE ORGANICS SAMPLING 	    24
                 4.1.14.1 SAMPLING TRAIN DESCRIPTION  .   .    24
                 4.1.14.2 SAMPLE TRAIN OPERATION  ....    25
                 4.1.14.3 SAMPLE RECOVERY AND CLEAN-UP   .    25
                 4.1.14.4 FIELD BLANKS  	    25
                 4.1.14.5 SEMIVOLATILE ORGANICS ANALYSES     25

5.0   QA/QC ACTIVITIES	    26

     5.1  EQUIPMENT QA PROCEDURES	    26

     5.2  EQUIPMENT QC PROCEDURES	    26
          5.2.1  EQUIPMENT INSPECTION AND MAINTENANCE .   .    26
          5.2.2  EQUIPMENT CALIBRATION  	    26
                 5.2.2.1  PITOT TUBES 	    27
                 5.2.2.2  IMPINGER THERMOMETER  	    27
                 5.2.2.3  DRY GAS METER THERMOMETER ...    27
                 5.2.2.4  FLUE GAS TEMPERATURE SENSOR .   .    28
                 5.2.2.5  DRY GAS METER AND ORIFICE ...    28

     5.3  SAMPLING QC PROCEDURES	    29
          5.3.1  PRE-TEST QC CHECKS AND PROCEDURES  ...    29
          5.3.2  QC CHECKS AND PROCEDURES DURING TESTING     29
          5.3.3  QC CHECKS AND PROCEDURES AFTER TESTING  .    30

     5.4  ANALYTICAL QA PROCEDURES	    30

     5.5  ANALYTICAL QC PROCEDURES	    31

     5.6  QA/QC CHECKS OF DATA REDUCTION	    31

     5.7  SAMPLE IDENTIFICATION AND CUSTODY 	    31

-------
                     TABLE OF CONTENT (Cont.)
                          LIST OF TABLES

TABLE 1.1-1  TARGETED METALS   	     33

TABLE 1.1-2  TARGETED VOLATILE COMPOUNDS   	     34

TABLE 1.1-3  TARGETED SEMIVOLATILE COMPOUNDS   	     35

TABLE 3.2-1  SAMPLING MATRIX  FOR CRUSHING, GRINDING, AND
             SCREENING OPERATIONS    	     36

TABLE 3.2-2  TEST MATRIX  FOR  KILN AND SAWDUST
             DRYER OPERATIONS	     37

TABLE 3.2-3  TEST MATRIX  FOR  THE GRINDING  BUILDING AND
             SAWDUST DRYER   	     39

TABLE 3.4.1-1  AVERAGE AMBIENT SAMPLING CONCENTRATIONS   .     40

TABLE 3.4.1-2  SUMMARY OF METHOD 201:  TOTAL FILTERABLE
               PARTICULATE AND PM10:  GRINDING-SCREENING
               BUILDING DUCT  #1	     41

TABLE 3.4.1-3  SUMMARY OF METHOD 201:  TOTAL FILTERABLE
               PARTICULATE AND PM10:  GRINDING-SCREENING
               BUILDING DUCT  #2	     42

TABLE 3.4.2-1  SUMMARY OF FILTERABLE PARTICULATE AND METALS
               EMISSIONS:  SAWDUST DRYER INLET BUILDING  .     43

TABLE 3.4.2-2  SUMMARY OF FILTERABLE PARTICULATE AND METALS
               EMISSIONS:  SAWDUST DRYER OUTLET A  ....     44

TABLE 3.4.2-3  SUMMARY OF FILTERABLE PARTICULATE AND METALS
               EMISSIONS:  SAWDUST DRYER OUTLET B  .  .  .  .     45

TABLE 3.4.2-4  SUMMARY OF PM10 AND M202  RESULTS:  SAWDUST
               DRYER INLET	     46

TABLE 3.4.2-5  SUMMARY OF PM10 AND M202  RESULTS:  SAWDUST
               DRYER OUTLET A	     47

TABLE 3.4.2-6  SUMMARY OF PM10 AND M202  RESULTS:  SAWDUST
               DRYER OUTLET B	     48

TABLE 3.4.2-9  SUMMARY OF TOTAL  FLUORIDE SAMPLING:  EPA METHOD
               13B:  SAWDUST  DRYER INLET   	     49

TABLE 3.4.2-10 SUMMARY OF TOTAL  FLUORIDE SAMPLING:  EPA METHOD
               13B:  SAWDUST  DRYER OUTLET  A	     50

TABLE 3.4.2-11 HF DATA AND RESULTS:  EPA METHOD 26:  SAWDUST
               DRYER INLET	     51

-------
                     TABLE  OF  CONTENT  (Cont.)


TABLE 3.4.2-12 HF DATA AND RESULTS:  EPA METHOD 26:  SAWDUST
               DRYER OUTLET A 	


TABLE 3.4.2-13 HF DATA AND RESULTS:  EPA METHOD 26:  SAWDUST
               DRYER OUTLET B 	

TABLE 3.4.2-14 SUMMARY OF VOLATILE ORGANICS EMISSIONS:  METHOD
               0030:  SAWDUST DRYER INLET 	    54

TABLE 3.4.2-15 SUMMARY OF VOLATILE ORGANICS EMISSIONS:  METHOD
               0030:  SAWDUST DRYER OUTLET A	    55

TABLE 3.4.2-16 SUMMARY OF VOLATILE ORGANICS EMISSIONS:  METHOD
               0030:  SAWDUST DRYER OUTLET B	    56

TABLE 3.4.2-17 SUMMARY OF EMISSIONS FOR SEMI VOLATILE
               COMPOUNDS:  METHOD 0010:   SAWDUST DRYER
               INLET	    57

TABLE 3.4.2-18 SUMMARY OF EMISSIONS FOR SEMI VOLATILE
               COMPOUNDS:  METHOD 0010:   SAWDUST DRYER
               OUTLET A	    58

TABLE 3.4.2-18 SUMMARY OF EMISSIONS FOR SEMI VOLATILE
               COMPOUNDS:  METHOD 0010:   SAWDUST DRYER
               OUTLET B	    59

TABLE 3.4.2-20 SUMMARY OF TOTAL HYDROCARBONS EMISSIONS:
               EPA METHOD 25A:  SAWDUST DRYER INLET ...    60

TABLE 3.4.2-21 SUMMARY OF TOTAL HYDROCARBONS EMISSIONS:
               EPA METHOD 25A:  SAWDUST DRYER OUTLET A   .    61

TABLE 3.4.2-22 SUMMARY OF TOTAL HYDROCARBONS EMISSIONS:
               EPA METHOD 25A:  SAWDUST DRYER OUTLET B   .    62

TABLE 3.4.2-23 SUMMARY OF ETHANE AND METHANE EMISSIONS:
               EPA METHOD 18:   SAWDUST DRYER INLET  ...    63

TABLE 3.4.2-24 SUMMARY OF ETHANE AND METHANE EMISSIONS:
               EPA METHOD 18:   SAWDUST DRYER OUTLET A  .  .    64

TABLE 3.4.2-25 SUMMARY OF ETHANE AND METHANE EMISSIONS:
               EPA METHOD 18:   SAWDUST DRYER OUTLET B  .  .    65

TABLE 5.5-1  SUMMARY OF VOLATILE EMISSIONS:  EPA METHOD  0030:
             EPA GAS AUDIT CYLINDER #539	    66

TABLE 5.5-2  SUMMARY OF VOLATILE EMISSIONS:  EPA METHOD  0030:
             EPA GAS AUDIT CYLINDER #540	    67

-------
                     TABLE OF CONTENT (Cont.)
                         LIST OF FIGURES

FIGURE 1.1-1 PINE HALL BRICK FACILITY SIT  PLAN	     68

FIGURE 2.1-1 CRUSHING, GRINDING, AND STORAGE OPERATIONS
             PROCESS SCHEMATIC AND EMISSIONS TESTING
             LOCATIONS AT    	     69

FIGURE 2.2-1 SAWDUST DRYER PROCESS SCHEMATIC AND
             EMISSIONS TESTING LOCATIONS AT    	     70

FIGURE 2.3.3-1  SCHEMATIC OF SAMPLING TRAVERSE POINTS FOR THE
                GRINDING AND SCREENING BUILDING OUTLETS       71

FIGURE 2.3.4-1  SCHEMATIC OF THE SAMPLING  LOCATION FOR THE KILN
                OUTLET/SAWDUST DRYER INLET 	     72

FIGURE 2.3.4-2  SCHEMATIC OF SAMPLING TRAVERSE POINTS FOR THE
                KILN OUTLET/SAWDUST DRYER  INLET   ....     73

FIGURE 2.3.5-1  SCHEMATIC OF THE SAMPLING  LOCATION FOR THE
                CYCLONE OUTLETS 	     74

FIGURE 2.3.5-2  SCHEMATIC OF SAMPLING TRAVERSE POINTS FOR THE
                CYCLONE OUTLETS 	     75

FIGURE 4.1.5.1-1  EPA METHOD 201A SAMPLING TRAIN  ....     76

FIGURE 4.1.5.1-2  EPA METHOD 201 SAMPLING  TRAIN  	     77

FIGURE 4.1.6.1-1  EPA METHOD 13B SAMPLING  TRAIN  	     78

FIGURE 4.1.6.3-1  EPA METHOD 13B RECOVERY  PROCEDURE   .  .     79

FIGURE 4.1.6.5-1  EPA METHOD 13B ANALYSIS  PROCEDURE   .  .     80

FIGURE 4.1.7.4-1  MULTIPLE METALS RECOVERY PROCEDURE  .  .     81

FIGURE 4.1.7.1-1  MULTIPLE METALS/TSP SAMPLING TRAIN  .  .     82

FIGURE 4.1.7.7-1  MULTIPLE METALS ANALYSIS PROCEDURE  .  .     83

FIGURE 4.1.8.1-1  EPA METHOD 201A/202 SAMPLING TRAIN  .  .     84

FIGURE 4.1.8.4-1  EPA METHOD 201A/202 RECOVERY PROCEDURE      85

FIGURE 4.1.8.6-1  EPA METHOD 201A/202 ANALYSIS PROCEDURE      86

FIGURE 4.1.9.1-1  ANDERSON IMPACTOR SAMPLING TRAIN FOR
                  PARTICLE SIZING 	     87

FIGURE 4.1.9.3-1  ANDERSON IMPACTOR RECOVERY PROCEDURE   .     88

-------
                     TABLE OF CONTENT (Hont.1


FIGURE 4.1.9.4-1  ANDERSON IMPACTOR ANALYSIS PROCEDURE   .     89
                                                              90
FIGURE 4.1.10.1-1  EPA METHOD 26 SAMPLING TRAIN  	

FIGURE 4.1.10.3-1  EPA METHOD 26 RECOVERY PROCEDURE  ...     91

FIGURE 4.1.10.5-1  EPA METHOD 26 ANALYSIS PROCEDURE  ...     92

FIGURE 4.1.10.1-1  CONTINUOUS EMISSIONS MONITORING DRY
                   EXTRACTIVE SYSTEM FOR EPA METHODS 3A,
                   7E, AND 10 (02,  C02, NOX, AND CO)  ...     93

FIGURE 4.1.11.1-2  CONTINUOUS EMISSION MONITORING SYSTEM
                   FOR EPA METHOD 25A	     94

FIGURE 4.1.12.1-1  EPA METHOD 18 SAMPLING TRAIN      ...     95

FIGURE 4.1.12.3-1  EPA METHOD 18 RECOVERY PROCEDURE  ...     96

FIGURE 4.1.12.4-1  EPA METHOD 18 ANALYSIS PROCEDURE  ...     97

FIGURE 4.1.13.1-1  VOLATILE ORGANIC SAMPLING TRAIN
                   (METHOD 0030)  	     98

FIGURE 4.1.13.3-1  EPA METHOD 0030 RECOVERY PROCEDURE  .  .     99

FIGURE 4.1.13.5-1  EPA METHOD 0030 ANALYSIS PROCEDURE  .  .    100

FIGURE 4.1.14.1-1  EPA METHOD 0010 SAMPLING TRAIN FOR
                   SEMIVOLATILE ORGANICS   	    101

FIGURE 4.1.14.3-1  EPA METHOD 0010 RECOVERY PROCEDURE  .  .    102

FIGURE 4.1.14.5-1  EPA METHOD 0010 ANALYSIS PROCEDURE  .  .    103

-------
                     TABLE OF CONTENT (Cont.]
                        LIST OF APPENDICES

APPENDIX A.O - TEST LOG

APPENDIX B.O - DATA AND RESULTS APPENDICES

     APPENDIX B.I- DATA  AND  RESULTS  FOR  PARTICULATE
                    MATTER  AND MULTIPLE METALS  TESTING
          APPENDIX B.I.I  -  TSP/MM DATA AND RESULTS  - SAWDUST
                            DRYER INLET
          APPENDIX B.I.2  -  TSP/MM DATA AND RESULTS  - SAWDUST
                            DRYER OUTLET A
          APPENDIX B.I.3  -  TSP/MM DATA AND RESULTS  - SAWDUST
                            DRYER OUTLET B

     APPENDIX B.2 - DATA  AND  RESULTS  FOR  PM10  AND CONDENSIBLE PM
                    TESTING
          APPENDIX B.2.1  -  M201A/M202 DATA AND  RESULTS -  SAWDUST
                            DRYER INLET
          APPENDIX B.2.2  -  M201A/M202 DATA AND  RESULTS -  SAWDUST
                            DRYER OUTLET A
          APPENDIX B.2.2  -  M201A/M202 DATA AND  RESULTS -  SAWDUST
                            DRYER OUTLET B

     APPENDIX B.3 - EPA DATA  AND RESULTS  FOR  PM10 AND TOTAL PM
                    TESTING
          APPENDIX B.3.1  -  M201 DATA  AND  RESULTS -  GRINDING-
                            SCREENING  BUILDING - DUCT #1
          APPENDIX B.3.2  -  M201 DATA  AND  RESULTS -  GRINDING-
                            SCREENING  BUILDING - DUCT #2

     APPENDIX B.4 - DATA  AND  RESULTS  FOR  TOTAL  FLUORIDE TESTING
          APPENDIX B.4.1  -  M13B DATA  AND  RESULTS -  SAWDUST
                            DRYER INLET
          APPENDIX B.4.2  -  M13B DATA  AND  RESULTS -  SAWDUST
                            DRYER OUTLET A

     APPENDIX B.5 - DATA  AND  RESULTS  FOR  HYDROGEN
                    FLUORIDE  TESTING
          APPENDIX B.5.1  -  M26 DATA AND RESULTS - SAWDUST
                            DRYER INLET
          APPENDIX B.5.2  -  M26 DATA AND RESULTS - SAWDUST
                            DRYER OUTLET A
          APPENDIX B.5.3  -  M26 DATA AND RESULTS - SAWDUST
                            DRYER OUTLET B

     APPENDIX B.6 - DATA  AND  RESULTS  FOR  VOLATILE
                    ORGANICS  TESTING
          APPENDIX B.6.1  -  M0030 DATA AND RESULTS - SAWDUST
                            DRYER INLET

-------
                     TABLE OF CONTENT (Cont.)


          APPENDIX  B.6.2  - M0030 DATA AND  RESULTS  -  SAWDUST
                           DRYER OUTLET A

          APPENDIX  B.6.3  - M0030 DATA AND  RESULTS  -  SAWDUST
                           DRYER OUTLET B
          APPENDIX  B.6.4  - M0030 DATA AND  RESULTS  -  EPA
                           AUDIT SAMPLES

     APPENDIX B.7 - DATA  AND RESULTS FOR SEMIVOLATILE
                    ORGANICS TESTING
          APPENDIX  B.7.1  - M0010 DATA AND  RESULTS  -  SAWDUST
                           DRYER INLET
          APPENDIX  B.7.2  - MOO10 DATA AND  RESULTS  -  SAWDUST
                           DRYER OUTLET A
          APPENDIX  B.7.3  - MOO10 DATA AND  RESULTS  -  SAWDUST
                           DRYER OUTLET B

     APPENDIX B.8 - DATA  AND RESULTS FOR TOTAL HYDROCARBONS
                    TESTING
          APPENDIX  B.8.1  - M25A DATA AND RESULTS - SAWDUST
                           DRYER INLET
          APPENDIX  B.8.2  - M25A DATA AND RESULTS - SAWDUST
                           DRYER OUTLET A
          APPENDIX  B.8.3  - M25A DATA AND RESULTS - SAWDUST
                           DRYER OUTLET B

     APPENDIX B.9 - DATA  AND RESULTS FOR METHANE AND ETHANE
                    TESTING
          APPENDIX  B.9.1  - M18 DATA AND RESULTS -  SAWDUST
                           DRYER INLET
          APPENDIX  B.9.2  - M18 DATA AND RESULTS -  SAWDUST
                           DRYER OUTLET A
          APPENDIX  B.9.3  - M18 DATA AND RESULTS -  SAWDUST
                           DRYER OUTLET B

     APPENDIX B.10  - DATA AND RESULTS FOR  PARTICLE SIZING
          APPENDIX  B.I0.1 - ANDERSON IMPACTOR DATA AND
                            RESULTS - SAWDUST DRYER  INLET
          APPENDIX  B.10.2 - ANDERSON IMPACTOR DATA AND
                            RESULTS - SAWDUST DRYER  OUTLET  A
          APPENDIX  B.I0.3 - ANDERSON IMPACTOR DATA AND
                            RESULTS - SAWDUST DRYER  OUTLET  B

     APPENDIX B.ll  - SCREEN AND MOISTURE ANALYSIS

     APPENDIX B.12  - AMBIENT MONITORING DATA AND RESULTS

APPENDIX C.O - CONTINUOUS EMISSIONS MONITORING APPENDICES

     APPENDIX C.I - CONTINUOUS EMISSIONS MONITORING  DATA -
                    SAWDUST DRYER INLET

-------
                    TABLE OF  CONTENTS  (Cont.}


          APPENDIX C.I.I - CONTINUOUS  EMISSIONS  MONITORING DATA
                           AND  RESULTS (02, C02,  NOX,  THC)  -
                           SAWDUST DRYER INLET
           APPENDIX C.I.2 - CONTINUOUS EMISSIONS MONITORING DRIFT
                            CALCULATIONS AND ADJUSTMENTS FOR THE
                           SAWDUST DRYER INLET

     APPENDIX C.2 - CONTINUOUS  EMISSIONS MONITORING DATA -
                    SAWDUST DRYER OUTLET A
          APPENDIX C.2.1 - CONTINUOUS  EMISSIONS  MONITORING DATA
                           AND  RESULTS (02/ C02/  NOX,  THC)  -
                           SAWDUST DRYER OUTLET  A
          APPENDIX C.2.2 - CONTINUOUS  EMISSIONS  MONITORING DRIFT
                           CALCULATIONS  AND ADJUSTMENTS FOR THE
                          SAWDUST DRYER  OUTLET A

     APPENDIX C.3 - CONTINUOUS  EMISSIONS MONITORING DATA -
                    SAWDUST DRYER OUTLET B
           APPENDIX C.3.1 - CONTINUOUS EMISSIONS MONITORING DATA
                            AND RESULTS  (02, C02/ NOX,  THC)  -
                            SAWDUST DRYER OUTLET B
           APPENDIX C.3.2 - CONTINUOUS EMISSIONS MONITORING DRIFT
                            CALCULATIONS AND ADJUSTMENTS FOR THE
                           SAWDUST DRYER OUTLET  B

APPENDIX D.O - CALCULATIONS

     APPENDIX D.I - EPA METHODS 1-4 CALCULATIONS

     APPENDIX D.2 - PARTICULATE EMISSIONS CALCULATIONS

     APPENDIX D.3 - MULTIPLE  METAL CALCULATIONS

     APPENDIX D.4 - GASEOUS EMISSIONS  CALCULATIONS

     APPENDIX D.5 - PARTICLE  SIZING CALCULATIONS

     APPENDIX D.6 - CEM CALCULATIONS

APPENDIX E.O - SAMPLING LOG AND CHAIN  OF CUSTODY RECORDS

     APPENDIX E.I - SAMPLE LOG  AND CHAIN OF CUSTODY RECORDS FOR
                    MULTIPLE  METALS AND  PARTICULATE MATTER
                    SAMPLING

     APPENDIX E.2 - SAMPLE LOG  AND CHAIN OF CUSTODY RECORDS FOR
                    PM10 AND CONDENSIBLE PM SAMPLING

     APPENDIX E.3 - SAMPLE LOG  AND CHAIN OF CUSTODY RECORDS FOR
                    TOTAL FLUORIDES SAMPLING

-------
                    TABLE OF CONTENTS tCont.)


     APPENDIX E.4 - SAMPLE LOG AND CHAIN OF CUSTODY RECORDS FOR
                    HYDROGEN FLUORIDE SAMPLING

     APPENDIX E.5 - SAMPLE LOG AND CHAIN OF CUSTODY RECORDS FOR
                    VOLATILE ORGANICS SAMPLING

     APPENDIX E.6 - SAMPLE LOG AND CHAIN OF CUSTODY RECORDS FOR
                    SEMIVOLATILE ORGANICS SAMPLING

     APPENDIX E.7 - SAMPLE LOG AND CHAIN OF CUSTODY RECORDS FOR
                    ETHANE AND METHANE SAMPLING

     APPENDIX E.8 - SAMPLE LOG AND CHAIN OF CUSTODY RECORDS FOR
                    MOISTURE ANALYSIS

APPENDIX F.O - RAW FIELD DATA APPENDICES

     APPENDIX F.I - RAW FIELD SAMPLING DATA FOR PARTICULATE
                    MATTER AND MULTIPLE  METALS TESTING
          APPENDIX F.I.I - TSP/MM RAW FIELD SAMPLING DATA -
                           SAWDUST DRYER INLET
          APPENDIX F.I.2 - TSP/MM RAW FIELD SAMPLING DATA -
                           SAWDUST DRYER OUTLET A
          APPENDIX F.I.3 - TSP/MM RAW FIELD SAMPLING DATA -
                           SAWDUST DRYER OUTLET B

     APPENDIX F.2 - RAW FIELD SAMPLING DATA FOR PM10 AND
                    CONDENSIBLE PM TESTING
          APPENDIX F.2.1 - M201A/M202 RAW FIELD SAMPLING DATA -
                           SAWDUST DRYER INLET
          APPENDIX F.2.2 - M201A/M202 RAW FIELD SAMPLING DATA -
                           SAWDUST DRYER OUTLET A
          APPENDIX F.2.3 - M201A/M202 RAW FIELD SAMPLING DATA -
                           SAWDUST DRYER OUTLET B

     APPENDIX F.3 - EPA RAW FIELD SAMPLING DATA FOR PM10 AND
                    TOTAL PM TESTING
          APPENDIX F.3.1 - M201 RAW FIELD SAMPLING DATA -
                           GRINDING-SCREENING BUILDING - DUCT #1
          APPENDIX F.3.2 - M201 RAW FIELD SAMPLING DATA -
                           GRINDING-SCREENING BUILDING - DUCT #2

     APPENDIX F.4 - RAW FIELD SAMPLING DATA FOR TOTAL FLUORIDE
                    TESTING
          APPENDIX F.4.1 - M13B RAW FIELD SAMPLING DATA - SAWDUS
                           DRYER INLET
          APPENDIX F.4.2 - M13B RAW FIELD SAMPLING DATA - SAWDUS
                           DRYER OUTLET A

     APPENDIX F.5 - RAW FIELD SAMPLING DATA FOR HYDROGEN
                    FLUORIDE TESTING

-------
                    TABLE OF CONTENTS  (Cont.)


          APPENDIX F.5.1 - M26 RAW  FIELD  SAMPLING DATA - SAWDUST
                           DRYER  INLET
          APPENDIX F.5.2 - M26 RAW  FIELD  SAMPLING DATA - SAWDUST
                           DRYER  OUTLET A
          APPENDIX F.5.3 - M26 RAW  FIELD  SAMPLING DATA - SAWDUST
                           DRYER  OUTLET B

     APPENDIX F.6 - RAW FIELD SAMPLING DATA  FOR VOLATILE
                    ORGANICS TESTING
          APPENDIX F.6.1 - M0030  RAW FIELD SAMPLING DATA -
                           SAWDUST  DRYER  INLET
          APPENDIX F.6.2 - M0030  RAW FIELD SAMPLING DATA -
                           SAWDUST  DRYER  OUTLET A
          APPENDIX F.6.3 - M0030  RAW FIELD SAMPLING DATA -
                           SAWDUST  DRYER  OUTLET B
          APPENDIX F.6.4 - M0030  RAW FIELD SAMPLING DATA -
                           AUDIT  SAMPLE CYLINDER 539
          APPENDIX F.6.5 - M0030  RAW FIELD SAMPLING DATA -
                           AUDIT  SAMPLE CYLINDER 540

     APPENDIX F.7 - RAW FIELD SAMPLING DATA  FOR SEMIVOLATILE
                    ORGANICS TESTING
          APPENDIX F.7.1 - M0010  RAW FIELD SAMPLING DATA -
                           SAWDUST  DRYER  INLET
          APPENDIX F.7.2 - M0010  RAW FIELD SAMPLING DATA -
                           SAWDUST  DRYER  OUTLET A
          APPENDIX F.7.3 - M0010  RAW FIELD SAMPLING DATA -
                           SAWDUST  DRYER  OUTLET B

     APPENDIX F.8 - RAW FIELD SAMPLING DATA  FOR TOTAL
                    HYDROCARBONS  TESTING
          APPENDIX F.8.1 - M25A RAW FIELD SAMPLING DATA - SAWDUST
                           DRYER  INLET
          APPENDIX F.8.2 - M25A RAW FIELD SAMPLING DATA - SAWDUST
                           DRYER  OUTLET A
          APPENDIX F.8.3 - M25A RAW FIELD SAMPLING DATA - SAWDUST
                           DRYER  OUTLET B

     APPENDIX F.9 - RAW FIELD SAMPLING DATA  FOR PARTICLE SIZING
          APPENDIX F.9.1 - ANDERSON IMPACTOR DATA AND
                           RESULTS  - SAWDUST DRYER INLET
          APPENDIX F.9.2 - ANDERSON IMPACTOR DATA AND
                           RESULTS  - SAWDUST DRYER OUTLET A
          APPENDIX F.9.3 - ANDERSON IMPACTOR DATA AND
                           RESULTS  - SAWDUST DRYER OUTLET B

APPENDIX G.O - ANALYTICAL DATA APPENDICES

     APPENDIX G.I - GRAVAMETRICS  LABORATORY  DATA
          APPENDIX G.I.I - TSP GRAVAMETRICS  LABORATORY DATA

-------
                     TABLE  OF  CONTEND  (Cont. L


           APPENDIX G.I. 2 - M201A/M202  GRAVAMETRICS  LABORATORY
                           DATA
           APPENDIX G.I. 3 - M201 GRAVAMETRICS  ^OR^**-g^*
           APPENDIX G.I.4 - ANDERSEN  IMPACTOR  GRAVAMETRICS
                           LABORATORY  DATA
           APPENDIX G.I.5 - SILICA  GEL  LABORATORY  DATA

     APPENDIX  G.2  - MULTIPLE  METALS  LABORATORY  DATA

     APPENDIX  G.3  - TOTAL  FLUORIDES  LABORATORY  DATA

     APPENDIX  G.4  - HYDROGEN  FLUORIDE  LABORATORY  DATA

     APPENDIX  G.5  - VOLATILE  ORGANICS  LABORATORY  DATA

     APPENDIX  G.6  - SEMIVOLATILE ORGANICS  LABORATORY DATA

     APPENDIX  G.7  - ETHANE AND  METHANE LABORATORY DATA

     APPENDIX  G.8  - MOISTURE  LABORATORY DATA

APPENDIX H.O - CONTINUOUS  EMISSIONS  MONITORING  CALIBRATION DATA

     APPENDIX  H.I  - CEM CALIBRATION  DATA AND  BIAS CHECKS
                     SAWDUST DRYER  INLET

     APPENDIX  H.2  - CEM CALIBRATION  DATA AND  BIAS CHECKS
                     SAWDUST DRYER  OUTLET A

     APPENDIX  H.3  - CEM CALIBRATION  DATA AND  BIAS CHECKS
                     SAWDUST DRYER  OUTLET B

APPENDIX 1.0 - FIELD EQUIPMENT  CALIBRATION DATA

APPENDIX J.O - MISCELLANEOUS  METHODS NOT CONTAINED  IN CFR 40

     APPENDIX  J.I  - METHOD 29:   DETERMINATION OF  METALS EMISSIONS
                     FROM STATIONARY  SOURCES

     APPENDIX  J.2  - METHOD 0010:   MODIFIED METHOD 5
                     SAMPLING  TRAIN (SEMI-VOST)

     APPENDIX  J.3  - METHOD 0030:   MODIFIED METHOD 5
                     SAMPLING  TRAIN (VOST)

-------
1.0  INTRODUCTION

1.1  Summary of Test Program

     The U.S. Environmental Protection Agency  (EPA), Office of
Air Quality Planning and Standards (OAQPS), Emission Inventory
Branch (EIB) is responsible for developing and maintaining air
pollution emission factors for industrial processes.  EIB, in
collaboration with the Brick Association of North Carolina, is
currently studying the brick manufacturing industry.  The purpose
of this study is to develop emission factors for the crushing,
grinding operations for brick manufacturing facilities and to
develop emission factors for the kiln and sawdust dryer
operations for brick manufacturing facilities using sawdust to
fire the kilns.  The Emission Measurement Branch (EMB) of OAQPS
coordinated the emission measurement activities at this plant.
ETS Incorporated (ETS Inc.) and EMB personnel conducted ambient
and source measurements.  MRI personnel collected samples of the
process materials and collected process data during testing.

     EPA/EIB and the Brick Association of North Carolina
considered the Pine Hall Brick Plant in Madison, North Carolina
to be one of the three facilities representing an advantageous
test site.  Three areas of the manufacturing facility were
tested: (1) the crushing, grinding, and screening operations; (2)
the kiln; and (3) the sawdust dryer.  The primary reasons for
selecting Pine Hall were: (1) the facility was identified by the
North Carolina Brick Association as being representative of
sawdust-fired brick manufacturing plants; and  (2) the grinding,
sawdust drying and brick firing (kiln) operations were configured
in such a way that facilitated emission testing.  A facility site
plan showing the layout of the operation and the sampling
locations is shown in Figure 1.1-1.

     Air sampling at the crushing and grinding operations was
performed for particulate matter (PM) and particulate matter less
than or equal to ten microns (PM10) from October 27 through
November 6, 1992.  In addition, background ambient air sampling
for PM and PM10 was conducted at "upwind" and  "downwind"  plant
boundary locations from October 27, 1992 through November 6,
1992.  Background ambient PM and PM10 monitoring at the grinding
building air intake was also performed during the grinding
building exhaust sampling conducted by EMB from October 26
through October 28, 1992.  Process materials were sampled at the
screening and grinding operations.  Sieve and moisture analyses
were performed on these samples.

     Source sampling at the kiln and sawdust dryer was performed
for PM, PM10, condensible particulate matter  (CPM), particle
sizing, multiple metals, total fluorides, hydrogen fluoride,

-------
carbon monoxide, nitrogen oxides, total hydrocarbons, methane,
ethane, volatile organic compounds (VOC), and semivolatile
organic compounds  (SVOC).  The sampling was conducted from
October 27 through November 7, 1992.  Table 1.1-1 identifies the
metals targeted for measurement and tables 1.1-2 and 1.1-3 show
the VOC and SVOC compounds targeted for measurement in this test
program.

1.2  Key Personnel

     The key personnel who coordinated the test program and their
phone numbers are:

     -ETS Inc. Project Manager, Mike Visneski      703/265-0004
     -EIB Technical Coordinator, Ron Myers         919/541-5407
     -EMB Field Test Coordinator, John Brown       919/541-0200
     -Pine Hall Brick Contact, H. John Dowdle, Jr. 919/548-6007
     -Brick Association of N.C., Peter P- Cieslak  800/622-7425
     -MRI Process Monitor, Brian Shrager           919/677-0249

2.0  PROCESS DESCRIPTION AND SAMPLING LOCATIONS

     At Pine Hall Brick, emissions from the kiln, sawdust dryer,
and the crushing, grinding, and screening operations were
studied.  The kiln outlet at Pine Hall Brick is also the sawdust
dryer inlet.

2.1  Crushing, Grinding, and Screening Operation

     A simplified process schematic for the crushing, grinding,
and screening operations is given in Figure 2.1-1.  This figure
also shows the locations for the emissions testing.

     The raw material is kept in a covered storage pile.  From
this pile the process material is loaded into the primary
crusher.  In the primary crusher the large pieces of material are
broken apart.  From the primary crusher the material is
transported into the grinding building, where it is first ground
and then screened.  From the screening operations the undersized
material is transported into the storage building.  The material
is kept in the storage building until it is loaded into the brick
making operations.

     Particulate emissions from the primary crusher and the
grinding building were measured.  The roof vents of the grinding
building and the conveyor outlet side of the crusher building
were sealed during sampling.  The emission test points consisted
of the exhaust air ducts for the grinding building and ambient PM
and PM10 samplers suspended from the roof joist of the crusher
building.  Ambient PM and PM10 samplers were also positioned on
scaffolding located at the air intake of the grinding building.
Background ambient PM and PM10 monitoring was also performed at

-------
"upwind" and "downwind" plant fenceline locations.  Pj°cJ^
material was sampled at the grinding building for sieve and
moisture analyses.


2.2  Sawdust Dryer Operation

     A stifled process schematic lor the sawdust dryer^
operations is given in Figure 2.2-1.  Tnis nyu-Lc
locations for the emissions testing.

     The exhaust gases from two kilns are combined into * jingle
inlet to the sawdust dryer.  The kiln exhaust 9*ses and the green
sawdust enter the dryer together.  At the opposite end of the
dryer, the dried sawdust is removed and the gas stream is split
into two parallel paths.  Each path consists of a cyclone and
induced draft (ID)  fan.  Following the ID fans, the two gas
streams are independently introduced into a single baghouse.  Tne
gases are then exhausted into the atmosphere from the top ot tne
baghouse.

     The dried sawdust is collected from the end of the dryer,
each cyclone, and the baghouse and fed onto a common conveyor
which transports the sawdust to the dry storage silo.

     The emissions testing for the sawdust drying operations was
performed at three locations simultaneously-  These locations
were the dryer inlet (which is also the kiln outlet) and both
cyclone outlets.  A baghouse is not considered typical of sawdust
drying operations at brick manufacturing facilities and therefore
was not tested.


2.3 Flue Gas, Process and Background Sampling Locations

     Background and emissions sampling was conducted at:  (1) the
plant boundary line; (2) the primary crusher;  (3) the  grinding
building; (4) the kiln outlet/sawdust dryer  inlet;  and (5)  the
cyclone outlets.  Process sampling was conducted  at the grinding
building and the sawdust dryer.

     2.3.1  Plant Boundary Line;  Ambient  air  sampling for  PM and
PM10 was conducted at two locations  along the plant boundary:
the west boundary line  ("upwind") and the  east boundary line
("downwind").

     2.3.2  Primary Crusher;  Emissions  from the  primary crusher
building were sampled using ambient Hi-Vol samplers for PM and
PM10.  The ambient samplers were suspended from the roof of the
building for the test  series.   The  openings  at base of the
crusher building (except for a  doorway required  to  be  kept  open)
were sealed with plastic during sampling.

-------
     2.3.3  Grinding Building;  Ambient air sampling for
background PM and background PM10 was conducted at one location
outside the grinding building.  The ambient samplers were placed
on elevated platforms located between the two air inlet fans
outside the grinding building.  The two outlet exhaust fans were
fitted with temporary ductwork with ports for sampling.  Figure
2.3.3-1 shows the detailed schematic of the traverse and sampling
locations for the grinder building outlet ducts.


     2.3.4  Kiln Outlet/Sawdust Dryer Inlet;  Figure 2.3.4-1 is a
schematic of the sampling location for the kiln outlet/sawdust
dryer inlet.  Two 6 inch diameter test ports were installed for
all wet methods.  A 3 inch diameter port was installed for
single-point sampling for the instrumental analyzer methods.  The
6 inch ports are located less than two stack diameters upstream
from a disturbance, but this was selected as the only practical
location for isokinetic sampling.  Method 1 requires 24 traverse
and sampling points for volumetric flow measurements and
particulate sampling.  Figure 2.3.4-2 is a detailed schematic of
the traverse and sampling locations.

     2.3.5  Cyclone Outlets;  Figure 2.3.5-1 is a schematic of
the sampling locations for the cyclone outlets.  The two cyclone
outlets are identical.  Two 6 inch diameter test ports were
installed for all wet method sampling.  A 3 inch diameter port
was installed for single-point sampling for the instrument
analyzer methods.  Method 1 requires 24 traverse and sampling
points for volumetric flow measurements and particulate sampling.
Figure 2.3.5-2  is a detailed schematic of the traverse and
sampling locations.

3.0  SUMMARY AND DISCUSSION OF TEST RESULTS

3.1  Objectives and Test Matrix

     The purpose of the test program was to develop emission
factors for the brick manufacturing industry.

     The specific objectives of the test program for Pine Hall
Brick were;

     (1)  Measure the following emissions for the crushing,
          grinding, and screening operation;

                    Particulate Matter
                    PM10

     (2)  Measure the following emissions for the kiln and
          sawdust dryer operations;

                    Particulate Matter

-------
                    PM
                    Condensible Particulate Matter
                    Multiple Metals
                    Hydrogen Fluoride
                    Total Fluorides
                    Carbon Monoxide
                    Nitrogen Oxides
                    Total Hydrocarbons
                    Methane
                    Ethane
                    Volatile Organics
                    Send/volatile Organics
3.2  Test Matrix

     Table 3.2-1 presents the sampling and analytical matrix for
measuring emissions from the crushing, grinding, and screening
operations.  Table 3.2-2 presents the sampling and analytical
matrix for emissions measurements performed by ETS, Inc. on the
kiln and the sawdust dryer.  Table 3.2-3 presents the sampling and
analytical matrix for emissions measurements performed by EMB on
the grinding building and the sawdust dryer.

3.3  Field Test Changes and Problems

     3.3.1  Ambient Samplers;   Three of the 54 ambient sampling
runs were voided.  Two of the east end boundary runs were voided
due to flow controller failures.  One run at the primary crusher
was voided due to a filter not properly seated in the sampler.
All sampling data associated with the voided sampler was also
voided and the complete sampling set was repeated in order to
obtain comparable data.


     3.3.2  Sawdust Dryer Sampling

     3.3.2.1  Percent Isokinetics;  The first Method 13 runs at
the sawdust dryer were under isokinetic due to air flow control
problems resulting from blockage in the baghouse on the exit side
of the induced draft fans.  The results of these tests were
included since any bias would be positive giving a worst case
emission rate.

     - I-M13-R1,  Total Fluorides:   89.9%

     - OA-M13-R1, Total Fluorides:   75.3%

One of the particle sizing runs at the sawdust dryer inlet
exceeded the percent isokinetic requirement of ± 10 percent as a
result of a source flowrate change during the test.

-------
     - IN-IMP-R1, Andersen Impactor for Particle Sizing:   68.5%

     3.3.2.2  Continuous Emissions Monitoring Calibration Drift ;
The Calibration drift for the NOX Monitor at Outlet A exceeded
the limit of 3.00% as stated in 40 CFR 60 Appendix A Method 7E.

     - OA-MM-R3, Multiple Metals run, NOX calibration drift
          was 5.21% at the zero span.

     - OA-M0010-R1, Semi-VOST and VOST run, NOX calibration
          drift was 3.32% at the zero span.

     - OA-M0010-R3, Semi-VOST and VOST run, NOX calibration drift
          was -3.16% at the high span.

     3.3.2.3  Analytical Changes and Problems;  The analysis of
the Tenax/Tenax Charcoal VOST tubes for the OB-M0030-R1B sample
and the IN-M0030-R1D sample were voided due to a computer
malfunction during analysis.

     In the analysis of the volatile and semivolatile samples,
several of the detected compounds were either below the method
quantitation limit or above the calibration range.  The values
for these compounds were estimated and the results are footnoted
and included in the B.6 and B.7 appendices.

     The impinger fractions for Runs OB-M23-R1 and OB-M23-R2 were
mislabeled during the analysis of the semi-VOST samples.  The
data for these samples is considered suspect although the two
fractions were analyzed separately and found to be similar.  The
laboratory data for the analysis of semivolatile compounds is
contained in Appendix G.6.

     The initial analysis of the filter blank for the total
fluorides was contaminated giving an inordinately high value.
Subsequent analysis of other blank filters from the same batch
used for field sampling showed nondetectable levels.

     3.3.2.4  Miscellaneous Changes and Problems;  Due to
difficulties encountered in performing a port change at the
sawdust dryer inlet, the EMB test coordinator determined it would
be adequate to traverse the same port twice during the last three
runs for SVOC.  The final run for VOC and SVOC was interrupted
for approximately 30 minutes to repair an electrical problem with
the Outlet B meterbox.  These changes are not expected to affect
the results.

3.4 Presentation of Results

     3.4.1   Crushing, Grinding and Screening Operation Sampling

     3.4.1.1  Ambient Sampling;  Ambient particulate sampling was

                                6

-------
conducted in order to determine background particulate
concentrations at the plant boundaries and at the air intake  to
the grinding building.  To determine particulate emission  rates
from the grinding building, the ambient particulate
concentrations at the air intake vents are important.  Ambient PM
and PM10 measurements were made at the grinding building  air
intake location coinciding with EMB exhaust duct testing for
particulates.   Table 3.4.1-1 shows the average concentration  for
the ambient PM and PM10 at the specified locations.   The  field
and laboratory data for the ambient monitoring is contained in
Appendix B.12.

     The following observations are made:

     1) The ambient particulate concentrations at the grinding
building are approximately two times greater than the ambient
concentrations at the plant boundaries.

     2) The ambient PM10 at the grinding building was
approximately 57% of the total PM concentration.

     3) The fenceline particulate concentrations varied
considerably from day to day.  There was reasonable  correlation
between the "upwind" and "downwind" stations.  The average
"downwind" PM was 61.5 ug/m3.   The  average  "upwind"  PM was 45.6
ug/m3.   The  average  "downwind"  PM10 was 26.0 ug/m3.   The  average
"upwind" PM10 concentration was slightly higher at 30.9 ug/m3.

     Ambient particulate monitoring was also performed at  the
crusher building in order to determine emissions of  PM and PM10
resulting from the crushing operation. The monitors  were
suspended from the roof joist of the crusher building and
operated during the day during the normal hours while the  crusher
was operating.  The average PM concentration was determined to be
1357 ug/m3 and the average  PM10 concentration was 585 ug/m3.
These are averages of two consecutive days of sampling.

     3.4.1.2  Particulate and PMin Sampling:  Sampling for  total
filterable particulate and 10 micron or smaller particulate was
conducted simultaneously at two outlet ducts using Method  201.
The total particulate emissions averaged 0.01102 gr/dscf with a
range of 0.00736 to 0.01584 gr/dscf.  The PM10 emissions  averaged
0.001022 gr/dscf and ranged from 0.00072 to 0.00185  gr/dscf.  The
ducts for this testing were custom made to use existing  exhaust
ventilation  wall fans on the upper north wall for air flow.   The
flowrate for duct #1 and duct #2 averaged 25,005 and 29,277
dscfm,  respectively.  The untested ventilation fans  were turned
off and the  building ridge vent was sealed during the tests to
achieve optimum capture of the particulate matter inside the
building.  Detailed summaries for each Method 201 test run
conducted on the grinding room exhaust ducts are contained in
Tables  3.4.1-2 and 3.4.1-3.

-------
     3.4.1.3  Process Sampling;  Process samples of the raw clay
material from conveyor at the exit of the grinding room building
were collected for sieve and moisture analyses.  The data for the
sieve and moisture analyses is contained in Appendix B.ll.  The
sieve analysis was consistent for three of four samples
collected.  The fourth sample showed a greater amount of larger
(> 20 mesh) particles.  The average of the three consistent
samples was 27.5% compared to 42.5% for the apparent outlier.
The mid-range (< 20 > 200 mesh) average for the three consistent
samples was 66.5% compared to 52.0% for the apparent outlier.
All four samples had comparable composition of fine particles (<
200 mesh).  The average of the four samples was 4.5%.  Moisture
analyses for the four samples ranged from 13.0% to 14.2%.


     3.4.2  Sawdust Dryer Sampling;  The sawdust dryer was
sampled at the inlet and two outlets simultaneously.  The inlet
of the sawdust dryer is the outlet of the kiln.  The sawdust
dryer outlet splits to feed two identical cyclones.  The outlet
of each cyclone was tested.  The test log for all sawdust dryer
testing is contained in Appendix A.O.

     3.4.2.1  PM, PMin. CPM Emissions and Particle Sizing:
Method 5 particulate testing was combined with the multiple
metals sampling.  The total particulate emissions for the inlet
averaged 0.0557 grains per dry standard cubic foot corrected to
7% 02 (gr/dscf @ 7% 02) .  The total particulate emissions for the
cyclone outlets averaged 0.0636 gr/dscf @ 7% O2 for outlet A and
0.5631 gr/dscf @ 7% 02 for outlet B.   The high particulate
concentrations for outlet B are consistent over 3 runs performed
over two days.  A comparison of the metals analyzed from the same
runs do not show correspondingly high values for the cyclone
outlet B.  Tables 3.4.2-1, 3.4.2-2 and 3.4.2-3 contain summaries
of the detailed data contained in Appendix B.I.

     PM10 was  sampled simultaneously at the sawdust dryer inlet
and outlets using Method 201A.  Method 202 was used to measure
the condensible particulate matter (CPM).  These runs were
performed together over two sampling days.  The PM10 emissions
for the inlet averaged 0.0928 gr/dscf @ 7% 02.   The PM10 emissions
for the cyclone outlets averaged 0.0722 gr/dscf § 7% 02 for
outlet A and 0.0597 gr/dscf @ 7% 02 for outlet B.   The CPM for
the inlet averaged 57.06%.  The CPM for the cyclone outlets
averaged 16.72% for outlet A and 14.0% for outlet B.  Tables
3.4.2-4, 3.4.2-5 and 3.4.2-6 contain summaries of the detailed
data contained in Appendix B.2.

     Particle size distribution was determined on samples
collected simultaneously on the dryer inlet and two outlets using
Andersen impactors.  The data for each run is shown in Figures
3.4.2-1, 3.4.2-2 and 3.4.2-3 and detailed data is contained in

                                8

-------
Appendix B.10.

     3.4.2.2  Trace Metals Emissions;  Trace metal sampling was
performed together with total particulate sampling.  Tables
3.4.2-1, 3.4.2-2 and 3.4.2-3 contain summaries of the detailed
data contained in Appendix B.I.  The trace metal emissions were
in agreement within a factor of 2 of the mean from run to run
except for a high manganese on the inlet run 3 (IN-MM/TSP-RJ) .
This result was voided due to suspected backhalf contamination by
permanganate.  Samples were analyzed for antimony, arsenic,
beryllium, cadmium, chromium, lead, manganese, mercury, nickel,
phosphorous and selenium.  Detectable quantities of all of the
metals were present in one or more of the sample runs.

     3.4.2.3  Total Fluoride Emissions; Total fluorides were
measured at the inlet and one of the outlet ducts from the dryer
cyclones.  Sampling at the other cyclone outlet was not possible
due to a malfunctioning induced draft fan.  Total fluoride
emissions averaged 1.197 Ib/hr ranging from 0.048 to 3.248 at the
inlet and averaged 0.334 Ib/hr with a range of 0.173 to 0.524 at
the outlet.  The inlet averaged 1.772 Ib/hr while the outlet
averaged 0.349 Ib/hr if the first subisokinetic runs are
discarded.  There is no obvious explanation for the low inlet
total fluoride compared to the inlet hydrogen fluoride data,
especially since the outlet data agree well.  Tables 3.4.2-9 and
3.4.2-10 contain summaries of the detailed data contained in
Appendix B.4.

     Variable fluoride emissions are considered typical for brick
manufacturing and have been described as micro-geographic
dependant ("Ceramic Bulletin" Vol. 54 No. 11 coauthored by Hugh
H. Wilson of Clemson University and Larry D. Johnson of EPA-
AREAL) .

     3.4.2.4  Hydrogen Fluoride Emissions;  The hydrogen fluoride
emissions were inconsistent and highly variable.  The inlet
concentrations ranged from 118 to 281 ppmdv @ 7% 02.   The outlet
A concentrations ranged from 27 to 194 ppmdv @ 7% 02.   The outlet
B concentrations ranged from 1.0 to 159 ppmdv % 7% 02.   Tables
3.4.2-11, 3.4.2-12 and 3.4.2-13 contain summaries of the detailed
data contained in Appendix B.5.

     3.4.2.5  CO Emissions;  Carbon monoxide emissions were
monitored instrumentally (Method 10) throughout the sawdust dryer
test program.   The averages for CO are contained in the summary
tables for each wet method test series.  The CO concentration at
the inlet averaged 450 ppmdv.  The CO concentration at the outlet
averaged 342 ppmdv for outlet A and 345 ppmdv for outlet B.
Detailed data for GEM testing is contained in Appendix C.

     3.4.2.6  NOx Emissions;  Nitrogen oxide emissions were
monitored instrumentally (Method 7E) throughout the sawdust dryer

-------
test program.  The averages for NOx are contained in the summary
tables for each wet method test series.  The NOx concentration at
the inlet averaged 34.4 ppmdv.  The NOx concentration at the
outlet averaged 22.7 ppmdv for outlet A and 22.0 ppmdv for outlet
B.  Detailed data for GEM testing is contained in Appendix C.O.

     3.4.2.7  THC Emissions;  Total hydrocarbon emissions were
monitored instrumentally (Method 25A) during the VOST sampling.
THC emissions averaged 14.90 ppmdv as carbon at the inlet, 45.39
ppmdv as carbon at outlet A and 32.64 ppmdv as carbon at outlet
B.  The results show a significant increase in THC emissions
following the sawdust dryer.  Tables 3.4.2-20, 3.4.2-21 and
3.4.2-22 contain summaries of the Method 25A test program.

     Methane and ethane samples were collected as integrated bag
samples during the semi-VOST sampling.  These samples were
analyzed by gas chromatography in the laboratory.  The samples
were all below the detection limit of 40 ppmdv for ethane and 152
ppmdv for methane for all inlet and outlet samples except Run 2
on outlet A  (OA-M18-R2) which gave a value of 9223 ppmdv for
methane.  This result is inconsistent with all other measurements
recorded and is an obvious outlier.  There is no explanation for
the value observed.  Tables 3.4.2-23, 3.4.2-24 and 3.4.2-25
contain summaries of the detailed data contained in Appendix B.9.

     3.4.2.8  VOC Emissions;  VOST samples were analyzed for
chloromethane, bromomethane, methylene chloride, chloroform,
trichlorofluoromethane, iodomethane, carbon tetrachloride,
trichloroethene, benzene, tetrachloroethene, acetone, carbon
disulfide, acrylonitrile, 2-butanone, 1,1,1-trichloroethane,
vinyl acetate, 2-hexanone, toluene, ethylbenzene, styrene, o-
xylene, and m-/p-xylene using Method 0030.  Detectable quantities
of chloromethane, bromomethane, methylene chloride,
trichlorofluoromethane, iodomethane, benzene, acetone, carbon
disulfide, acrylonitrile, 2-butanone, toluene, ethylbenzene, o-
xylene, and m-/p-xylene were found in one or more of the sample
runs.  Tables 3.4.2-14, 3.4.2-15 and 3.4.2-16 contain summaries
of the detailed data contained in Appendix B.6.

     3.4.2.9  SVOC Emissions;   Semi-VOST samples were analyzed
for phenol, naphthalene, 2-methylphenol, dimethylphthalate,
dibenzofuran, di-n-butylphthalate and bis(2-ethylhexyl)phthalate
and were scanned for compounds on the list of 189 Hazardous Air
Pollutants (HAPs) using Method 0010.  Detectable quantities of
phenol, naphthalene, dimethylphthalate, dibenzofuran, di-n-
butylphthalate, bis(2-ethylhexyl)phthalate were found in one or
more of the sample runs.  Tables 3.4.2-17, 3.4.2-18 and 3.4.2-19
contain summaries of the detailed data contained in Appendix B.7.

     3.4.2.10  Process Sampling;  Process samples of sawdust were
collected for sieve and moisture analysis.  Eight samples of
dried sawdust were taken on successive days.  One sample

                                10

-------
represented the wet feed sawdust.  The data for the sieve and
moisture analyses is contained in Appendix B.ll.  The  sieve
analysis was consistent for all nine samples collected.  The
sawdust samples showed a greater amount  (73.6%) of larger (> 20
mesh) particles.   The mid-range (< 20 > 200 mesh) average for
all samples was 26.3%.  Less than 0.1% of the composition of all
of the samples consisted of fine particles (< 200 mesh).  The wet
sawdust had a moisture content of 47.2%.  The average  of the
eight dried sawdust samples was 2.7% moisture.

4.0 SAMPLING AND ANALYTICAL PROCEDURES

4.1  Test Methods

     4.1.1  Ambient Particulate Matter (PM and PM,n^ -  Hi-Vol;
Ambient sampling of PM was collected in accordance with 40 CFR 50
Appendix B.  Ambient sampling of PM10 was collected in  accordance
with 40 CFR 50 Appendix J.  Ambient sampling was used  to
establish background PM and PM10 concentrations at the  plant
boundary and at the air intake to the grinding building.  Ambient
samplers were also used to determine PM and PM10 concentrations
at the crusher building door during the crusher operation.

     The background samplers were operated for at least 8 hours
per day.  The samplers located at the crusher building were
operated during the day while the crusher was operating.  All
ambient sampling was performed with collocated PM and  PM10
samplers.  The background samplers were placed on platforms at
least 6 feet above the surrounding terrain.  The crusher building
samplers were suspended from the roof of the building.

     4.1.1.1  Ambient Hi-Vol and PMin Analyses; Filters used in
the ambient sampling monitors were weighed before and  after
sampling.  The weight gain represented the particulate content of
the air volume sampled.  Prior to weighing, the filter was
conditioned to a controlled temperature and humidity for at least
24 hours.  Filters were inspected for tears or pinholes which, if
present, cause the filter to be voided.  Filters were  weighed to
the nearest 0.1 mg.

     4.1.2 Volumetric Flow Measurements;  Volumetric flow
measurements were made in accordance with EPA Method 2 at the
grinding building outlet ducts and the sawdust dryer inlet and
outlet ducts using stainless steel Type-S pitot tubes  to measure
the gas velocity heads.  The pitot tubes were calibrated against
a NIST traceable pitot tube in accordance with Method  2.
Calibrated Type-K thermocouples were used to determine gas
temperatures. Velocity and temperature measurements were made at
each of the traverse points determined by EPA Method 1.

     4.1.3  Molecular Weight Determination;  Gas compositional
measurements (02  and C02) for determining the average molecular

                                11

-------
weight of the stack gases were done instrumentally  in  accordance
with EPA Reference Method 3A.  Sampling was done by obtaining
integrated gas samples as part of the continuous emissions
monitoring.

     4.1.4  Flue Gas Moisture Content;  The flue gas moisture was
measured in conjunction with each of the pollutant  tests
according to the sampling and analytical procedures outlined in
EPA Method 4.  The flue gas moisture for each test  was determined
by gravimetric analyses of the water collected in the  impinger
condensers of the pollutant sampling train.  All impingers  were
contained in an ice bath throughout the testing in  order  to
assure complete condensation of the moisture in the flue  gas
stream.  Any moisture which was not condensed in the impingers
was captured in the silica gel contained in the final  impinger.

     Moisture content was determined gravimetrically in
accordance with Method 4 by measuring either the volume or  mass
gains of each impinger in the pollutant sampling trains.


     4.1.5  PM,n Sampling - EPA Methods 201 and 201A;  EPA Method
201A was used for determination of PM10 emissions from  the
sawdust dryer inlet and outlets.  This procedure utilized an in-
stack PM10 sizing device and an in-stack filter in conjunction
with an EPA Method 17 train.  Gravimetric analyses  were performed
as described by EPA Method 5.

     EPA Method 201 was used to determine PM10 emissions from the
grinding and screening building outlets.   This method  employs  an
in-stack cyclone to separate particulate greater than  10  microns
and an in-stack glass fiber filter to collect PM10.   To maintain
isokinetic flowrate conditions at the tip of the probe and  a
constant flowrate through the cyclone, a clean, dried  portion  of
the sample gas at stack temperature is recycled into the  nozzle.
Gravimetric analyses were performed as described by EPA Method 5.

     4.1.5.1  Sampling Train Descriptions;  The Method 201A train
consisted of a cyclone followed by a 47 mm diameter glass fiber
(Gelman)  filter.   These in-stack components were attached to an
unheated stainless steel probe.   The Method 201A sampling train
is shown in Figure 4.1.5.1-1.  The stack gases were drawn through
the cyclone where a portion of the airborne particulate is
separated before it passes through a Gelman filter.  The  size
fraction of the particles that have a 50 percent probability of
exiting the cyclone to the Gelman filter are defined as the
cyclone cut size (D50).  The required particle size  for a  valid
test run ranges from 9 urn to 11 urn.  After the sample  gas passes
through the Gelman filter,  it then enters a stainless  steel
conduit which leads into a glass impinger train consisting  of
four impingers immersed in an ice bath.  The first,  second  and
third impingers each contained 100 milliliters of water.  The

                                12

-------
fourth impinger was initially empty and the fifth impinger
contained approximately 200 grams of color-indicating silica gel.

     The Method 201 train consisted of an in-stack cyclone
followed by an in-stack glass fiber filter.  The Method 201
sampling train is shown in Figure 4.1.5.1-2.  The stack gases
were drawn through the cyclone where PM greater than PM10  is
removed.  The PM10 is  then collected on a glass fiber filter.
This train is designed to maintain isokinetic sampling rates
while maintaining sufficient flow through the cyclone by
recylcling a portion  of clean, dried stack gas at stack
temperature through the nozzle of the sampling probe.  The amount
of recycled gas is maintained between 10 and 80%.

     4.1.5.2  Pre-Test Preparation:  Before sampling, a velocity
traverse of the stack was performed.  This traverse, along with a
gas analysis of the stack gas, was used to determine the nozzle
diameter(s) needed to maintain a flow rate through the cyclone to
achieve a cut size of 10|im.  A nozzle was selected by comparing
the velocity heads from the velocity traverse with the Ap,,^ and
APmax calculated for each nozzle.  The nozzle was chosen to
bracket all the Ap's  from the velocity traverse.

     4.1.5.3  Sampling Train Operation:  Throughout the sampling
run the orifice pressure head was maintained at the pretest
calculated value.  If the stack gas temperature varied by more
than 28°F from the pretest average temperature,  then the orifice
pressure head was determined using the pretest average ± 28°F.

     Sampling was started at the first traverse point.  Sampling
time (or dwell time)  at this point was determined by the pretest
calculations.  After  moving to the next traverse point, the dwell
time at this point was determined by the velocity head at this
point.  This procedure was repeated for the remainder of the
traverse points.

     4.1.5.4  Sample  Train Recovery;  During the run, if
necessary, and following the run the filters were quantitatively
recovered into their  original tared and labeled foil wrappers.
Following the run, the particulate matter was quantitatively
recovered using acetone from all of the surfaces from the cyclone
exit to the front half of the in-stack filter holder, including
the "turn around" cup inside the cyclone and the interior
surfaces of the exit  tube.  The rinsings were placed into labeled
glass bottles.  The filters and rinsings were transported to the
ETS laboratory for gravimetric analyses as described by EPA
Method 5.  The impinger water and silica gel were recovered as
per EPA Method 4 procedures.

     4.1.5.5  PM10 Analyses;  Analyses of the glass  fiber  filters
and cyclone acetone rinses from the Method 201 and 201A sampling
trains were performed gravimetrically in accordance with  EPA

                                13

-------
Method 5 procedures.  The total PM10 catch included  the
particulate collected in the acetone rinses from all or the
surfaces from the cyclone exit to the front half of the in-stack
filter holder, including the "turn around" cup inside the cyclone
and the interior surfaces of the exit tube, as well as the
particulate collected by the glass fiber filter.

     4.1.6 Total Fluoride Sampling- EPA Method 13B;  Sampling  for
total fluoride was performed in accordance with EPA Method 13B.
This method involved absorbing the fluorides in distilled water,
and analyzing the solution for total fluorides using a ion
specific electrode procedure.

     4.1.6.1  Sampling Train Description;  Figure 4.1.6.1-1 shows
the Method 13B sampling train.   A heated stainless steel probe
with a quartz liner was used to withdraw the gas sample.  The
probe was equipped with an appropriately sized integrated quartz
nozzle fused directly to the liner for isokinetic gas withdrawal.

      From the nozzle and probe, sample gas was pulled through an
impinger train.  The impinger train consisted of four glass
impingers iinmersed in an ice bath.  The first and second imping-
ers each contained 100 milliliters of deionized distilled water,
the third impinger was initially dry, and the fourth initially
contained approximately 200 grams of silica gel.  A Whatman No. 1
paper filter was located between the third and fourth impinger.

     4.1.6.2  Sampling Train Operation;  The sampling train was
operated in accordance with Method 13B and Method 5 procedures
and specifications, including leak checking, isokinetic sampling
rate and stack traversing.

     4.1.6.3  Sample Recovery;   At the completion of each test
run, the train components were recovered according to Method 13B
procedures.   The probe was rinsed with deionized distilled water.
The volumes of the impinger contents were measured, and the
liquids quantitatively transferred to Nalgene sample bottles.
The impingers were rinsed with distilled water, and the rinses
collected into the sample bottles with the impinger contents.
The Whatman filter was placed in with the impinger solutions.
The silica gel in the last impinger was recovered into its
original container.  A schematic of the recovery process is shown
in figure 4.1.6.3-1.

     4.1.6.4  Field Blanks:  One field blank was collected during
the test program for the Method 13B tests.  The field blank
consisted of a complete sampling train set up on site and
recovered during the recovery of the normal stack test samples.

     4.1.6.5  Total Fluoride Analyses;  The Method 13B filter and
rinsates were analyzed for total fluoride using sample digestion
followed by analysis by a fluoride ion specific electrode.  The

                                14

-------
analysis is schematically shown in figure 4.1.6.5-1.

     4.1.7  Multiple Metals with PM - EPA Multi-Metals Procedure;
Sampling for antimony, arsenic, beryllium, cadmium, total
chromium, lead, manganese, mercury, nickel, phosphorous, and
selenium was performed in accordance with EPA Method 5 in
conjunction with Section 3.1 of "Methods Manual for Compliance
with BIF Regulations  (EPA/530-SW-91-010)".  This methodology is
commonly referred to as the Multi-Metals procedure.  In addition,
the filter and probe washes were analyzed for determining PM in
accordance with EPA Method 5.

     4.1.7.1  Sampling Train Description;  The testing was
conducted utilizing the Multi-Metals sampling train as
illustrated in Figure 4.1.7.1-1.  A heated stainless steel probe
with a quartz liner was used to withdraw the gas sample.  The
probe was equipped with an appropriately sized integrated quartz
nozzle fused directly to the liner for isokinetic gas withdrawal.

     From the nozzle and probe, sample gas was pulled through a
heated glass filter holder which holds a Pallflex ultra-pure 2500
QUAT-UP quartz filter supported on a teflon frit.  The filter was
maintained at a temperature sufficiently high to prevent the
condensation of water (248 ± 25°F).  Sample gas subsequently
passed through an impinger train consisting of seven glass
impingers immersed in an ice bath.  The first impinger was
initially empty.  The second and third impingers each contained
100 milliliters of 5% nitric acid/10% hydrogen peroxide solution.
The fourth impinger was initially empty.  The fifth and sixth
impingers each contained 100 milliliters of 4% potassium
permanganate/10% sulfuric acid solution.  The seventh impinger
contained approximately 200 grams of silica gel.  The amount of
moisture collected in the sampling train was quantified in order
to determine the stack gas moisture content in accordance with
EPA Method 4.

     4.1.7.2  Sample Train Preparation;  All glassware components
of the multiple metals sampling train were pre-cleaned before
use.  The following cleaning procedure was used:

     1)   Wash with hot water and detergent.
     2)   Rinse with tap water three times.
     3)   Rinse with deionized, distilled water three times.
     4)   Soak in a 10% nitric acid solution for four hours.
     5)   Rinse three times with deionized water.
     6)   Rinse three times with acetone and allow to air dry.

     All glassware openings were covered with Teflon tape until
sampling to prevent contamination.

     4.1.7.3  Sample Train Operation;  Sampling was done in
accordance with EPA Method 5 procedures and specifications,

                                15

-------
 including  leak checking, isokinetic sampling rate  and stack
 traversing.

      4.1.7.4  Sample Recovery and Clean-up;  At  the completion of
 each  test, the probe was removed from the train  and the ends of
 the probe  and sample train capped.  The probe was  cleaned on the
 test  platform, while the remainder of the sample train was
 transported to a clean-up site for recovery.  The  sample recovery
 procedure  is shown in Figure 4.1.7.4-1:

      4.1.7.5  Field Blanks;  One field blank was collected during
 the test program for each location from which metals sampling was
 conducted.  Each field blank consisted of a complete sampling
 train set  up on site and recovered during the recovery of the
 normal stack test samples.

      4.1.7.6  PM Analyses - EPA Method 5;  Particulate matter was
 determined in accordance with EPA Method 5 procedures .   The
 filter was analyzed gravimetrically to a constant  weight.   The
 front half rinse was evaporated and analyzed gravimetrically to a
 constant weight.  The total particulate catch equaled  the sum of
 the front  half rinse and the filter.

      4.1.7.7  Multi-Metals Analyses - EPA Multi-Metals;   The
 filter, front-half rinses, and contents of impingers  1  through 4
 of the multi-metals sampling train were analyzed for antimony,
 arsenic, beryllium, cadmium, total chromium, lead, manganese,
 nickel, phosphorous, and selenium.   The rinses and contents of
 impingers  5 and 6 were analyzed for mercury.

      Analyses of the filters and front-half acetone  rinses  were
 conducted after completion of the Method 5 gravimetric  analyses.
 SW-846  Method (atomic absorption) was used to determine  the
 metals  concentrations .

      The sampling train components  (including the  digested
 filter, probe washes, and impinger contents and  rinses)  were
 prepared for analysis in accordance with the procedures  given  in
 the EPA draft method.  All digestions were performed using  a 600-
 watt microwave digester and Teflon pressure relief vessels.
 After preparation,  the  samples were analyzed with  a  Perkin  Elmer
 Plasma 2000 inductively coupled plasma (ICP) atomic  absorption
 spectrometer for antimony,  arsenic,  beryllium,  cadmium,  total
 chromium,  lead,  manganese,  nickel,  phosphorous,   and  selenium.  A
 Coleman 50A cold vapor  atomic absorption spectrometer  (CVAAS) was
used to analyze  the samples for mercury.
          S*t?Ja?aly8eB were Performed on all metals samples.  In
          field blanks were analyzed.   Spikes were added to the
samples to determine the metals recovery efficiencies. A
schematic of  the analytical procedure  is contained in Figure
4 • J_ • /•/"I,
                               16

-------
     4.1.8 PMin/CPM Sampling  - EPA Method  201A/202;   Sampling  of
PM10/CPM at the  cyclone  outlets was  conducted with a  combined
Method 201A/202 sampling train.  The analyses of the samples
included Method 201A procedures for determining PM10  and Method
202 procedures  for determining CPM.

     4.1.8.1  Sampling  Train Description;  The Method 201A/202
train consists  of  a cyclone  followed by a 47 mm diameter glass
fiber (Gelman)  filter.  These in-stack components were attached
to a heated stainless steel probe.  For sampling at the cyclone
outlets, a teflon  liner was used with the sample probe.  The  high
temperatures at the sawdust dryer inlet prevented the in-stack
use of teflon.  The Method 201A/202 sampling train is shown in
Figure 4.1.8.1-1.

     The stack  gases were drawn through the cyclone, then the
Gelman filter and  into  the glass impinger train consisting of
five glass impingers immersed in an ice bath.  The first, second,
and third impingers each contained  100 milliliters of deionized
distilled water.   The fourth impinger was initially empty, and
the fifth contained approximately 200 grams of silica gel.

     4.1.8.2  Pre-Test  Preparation;  Before sampling, a velocity
traverse of the stack was performed.  This traverse, along with
an analysis of  the stack gas, was used to determine the nozzle
diameter(s) needed to maintain a flow rate through the cyclone to
achieve a cut size of 10|im.  A nozzle was selected by comparing
the velocity heads from the velocity traverse with the Ap^n and
Apmax calculated for each nozzle.  The nozzle chosen bracketed all
the Ap's from the  velocity traverse.  Nozzle changes during the
sampling run were  not required since the velocity head at the
sampling points were within the Ap,,^ and Ap^,^ for that nozzle.
The details of  the calculations are given in Method 201A.
Two additional pretest  calculations were also needed.  The
orifice pressure head needed to maintain the necessary cyclone
flow rate was calculated.  And finally, dwell time for the first
traverse point was calculated from the pretest traverse.  These
calculations are also detailed in Method 201A.

     4.1.8.3  Sampling  Train Operation;  Throughout the sampling
run the orifice pressure head was maintained at the pretest
calculated value.   If the stack gas temperature varied by more
than 28°F  from the pretest average temperature,  then the orifice
pressure head was  determined using the pretest average ± 28°F.

     Sampling was  started at the first traverse point.  Sampling
time (or dwell time) at this point was determined by the pretest
calculations.  After moving to the next traverse point, the dwell
time at this point was  determined by the velocity head at this
point.   This procedure was repeated for the remainder of the
traverse points.
                                17

-------
     4.1.8.4  Sample Recovery and Clean-up;  During the run,  if
necessary, and following the run the filters were quantitatively
recovered into petri dishes.  Following the run, the particulate
matter was quantitatively recovered using acetone from all  ot the
surfaces from the cyclone exit to the front half of the in-stack
filter holder, including the "turn around" cup inside the cyclone
and the interior surfaces of the exit tube.  The rinsings were
placed into labeled glass bottles.  The filters and rinsings  were
transported to the ETS laboratory for gravimetric analyses  as
described by EPA Method 5.

     The back-half of the sampling train (impingers plus
connecting glassware) was recovered in accordance with EPA  Method
202 procedures.  The pH of the first impinger was measured
immediately after the test.  If the pH was less than 4.5, then
the entire impinger train was purged for one hour using purified
air in accordance with Method 202 procedures.  If the pH of the
first impinger exceeds 4.5, then the purge was omitted.
A schematic of the recovery of the combined 201A/202 train  is
presented in figure 4.1.8.4-1. The analysis for the 201A and  202
sampling trains were slightly different.

     4.1.8.5  Field Blanks;  One field blank was collected  during
the test program for each location where PM10/CPM were tested.
Each field blank consisted of a complete sampling train set up on
site and recovered during the recovery of the normal stack  test
samples.

     4.1.8.6  CPM Analyses - EPA Method 202;  The determination
of the total condensible particulate matter (CPM) in the back-
half of the sampling train was determined in accordance with
Method 202 procedures.  The total sulfate concentration of  the
impinger contents and aqueous rinses were determined by analyzing
an aliquot of each sample using ion chromatography.  The impinger
contents and aqueous rinses were then combined with the methylene
chloride rinses and extracted twice with methylene chloride using
a separatory funnel.  The samples were divided into organic
(methylene chloride) and inorganic (aqueous) fractions.  The
organic fraction was  evaporated at room temperature and
pressure,  and the resulting residue gravimetrically analyzed  to a
constant weight.

     The inorganic fraction was evaporated to dryness at 105°C.
If the pH of the original impinger solutions was less than  4.5,
then the resulting residue was redissolved in 100 milliliters  of
distilled water,  and made basic using concentrated ammonium
hydroxide.   The resulting solution was evaporated to dryness  at
105°C once more,  and  the  residue  determined gravimetrically.  If
the pH of  the original solution was greater than 4.5, then  the
ammonia addition step was omitted.

     The back-half condensible particulate catch will equal the

                               18

-------
organic residue plus the inorganic residue plus the combined
water removed by the acid-base reaction based on the impinger
analysis for sulfate.

     The total particulate catch will equal the front-half probe
rinse and filter plus the back-half condensibles.  A schematic of
the analytical procedure is contained in Figure 4.1.8.6-1.


     4.1.8.7  PMin Analyses -  EPA Method 201A:  Analyses  of the
glass fiber filters and cyclone acetone rinses from the  PM10
sampling were performed gravimetrically in accordance with EPA
Method 5 procedures.  The total PM10 catch included the
particulate collected in the  acetone rinses from all of  the
surfaces from the cyclone exit to the front half of the  in-stack
filter holder, including the  "turn around" cup inside the cyclone
and the interior surfaces of  the exit tube, as well as the
particulate collected by the  glass fiber filter.  A schematic of
the analytical procedure is contained in Figure 4.1.8.6-1.

     4.1.9  Particle Sizing - Andersen Impactor;  Particle sizing
was performed using an eight-stage Andersen-style cascade
impactor, following the general procedures recommended by the
impactor manufacturer.

     4.1.9.1  Sampling Train  Description;  Figure 4.1.9.1-1 shows
the major components of the impactor sampling train.  Stack gas
was pulled through an appropriately sized stainless steel nozzle
to insure isokinetic sampling.  From the nozzle, the sample gas
was then pulled through an Andersen Mark III Cascade Impactor
consisting of eight fiberglass filters and a single back-up
filter.  Each filter was supported on a perforated stainless
steel disc designed to separate particles according to their
terminal velocity through the perforations in the disc.  The
gases were then passed into an impinger train consisting of four
glass impingers immersed in an ice bath.  The first two  impingers
initially contained 100 milliliters of deionized, distilled
water.  The third impinger was initially empty, and the
fourth initially contained approximately 200 grams of silica gel.

     4.1.9.2  Sampling Train  Operation; Sampling was done in
accordance with the procedures recommended by Andersen 2000 for
leak checking, isokinetic sampling rate and stack traversing.

     4.1.9.3 Sample Recovery  and Clean-up;  Recovery of  the
cascade impactor sampling nozzle was accomplished  and using a
teflon-fiber probe brush.  The nozzle was rinsed with acetone
three times and brushed between rinsings.  The impactor  filters
were individually collected and placed back into their original
tared containers.  The impinger contents were measured for
moisture gain and discarded.  The silica gel from the fourth
impinger was transferred back to its original Nalgene container.

                                19

-------
The amount of moisture collected in the sampling train was
quantified in order to determine the stack gas moisture content
in accordance with EPA Method 4.  A schematic of the recovery
process is shown in figure 4.1.9.3-1.

     4.1.9.4 Andersen Impactor Analysis;  Mass gains for the
filters of each stage of the cascade impactor will be determined
in accordance with EPA Method 5 procedures.  Each filter will be
analyzed gravimetrically to a constant weight.  A schematic of
the analysis is shown in figure 4.1.9.4-1.

     4.1.10  Hvdroaen Fluoride (HF^ - EPA Method 26;  HF
emissions were measured in accordance with EPA Method 26.  The
procedure involves absorbing the HF in dilute sulfuric acid and
analyzing the solution for total fluorides using an ion
chromatography technique.

     4.1.10.1  Sampling Train Description;  A schematic of the
Method 26 sampling train is shown in Figure 4.1.10.1-1.  A heated
glass probe was used for sample withdrawal.  The gas stream was
passed through a heated Teflon filter and five glass impingers.
The impingers were immersed in an ice bath.  The first impinger
was initially left empty, a shortened tube is used to prevent
bubbling of the gas sample through the collected condensate.  The
second and third impingers were each  charged with 15 ml of 0.1
Normal sulfuric acid solution for HF absorption.  The fourth
impinger was charged with 15 ml of 0.1 Normal sodium hydroxide to
absorb acid gases harmful to the dry gas meter.  The fifth
impinger was charged with silica gel to absorb any moisture
before the stream enters the dry gas meter.

     4.1.10.2  Sampling Train Operation;  The gas stream was
sampled at a single point in the center of the stack for 120
minutes at a sampling rate of approximately 2 liters per minute.
All sampling procedures, such as leak checking and system
purging, were in accordance with EPA Method 26.  The impingers
were maintained in an ice bath during the sampling period.  The
sample train was initially leak checked from the probe and
subsequently checked at the three way stopcock for the following
runs. The sample trains were leak checked to demonstrate a
leakage rate not in excess of 2% of the average sample.

     4.1.10.3  Sample Recovery and Clean-up;  A schematic of the
recovery of the Method 26A sampling train is contained in figure
4.1.10.3-1.                                                 y

     4.1.10.4  Field Blanks;  One field blank was collected
during the test program for each location from which HF was
tested.   The field blank consisted of a complete sampling train
set up on site and recovered during the recovery of the normal
stack test samples.
                               20

-------
     4.1.10.5  Hydrogen Fluoride Analyses;  The contents of the
first three impingers of the Method 26 train were analyzed for
fluoride in accordance with EPA Method 26 procedures.  The
contents of the fourth impinger (sodium hydroxide) was not
analyzed.  Ion chromatography was employed in the analyses.  A
schematic of the analytical procedure is contained in Figure
4.1.10.5-1.

     4.1.11  Continuous Monitoring for Q.,.  C07. CO. NCL. and THC -
Instrumental Methods;  Instrumental monitoring of the stack gases
were performed in accordance with the following procedures:
GAS
02
CO,
CO
NO,
THC
REFERENCE METHOD
  Method 3A
  Method 3A
  Method 10

  Method 7E
  Method 25A
INSTRUMENT TYPE
Teledyne Model 32OA Chemical
Cell Portable 02  Analyzer

HORIBA Model PIR-2000 NDIR
C02 Analyzer

TECO Model 48 NDIR CO Analyzer

TECO Model 10AR Chemilu-
minesence NOX Analyzer

J.U.M. Model VE-7 Heated
THC Analyzer  (FID)
     All of the  analyzers except the hydrocarbon analyzer
measured gas concentrations on a dry volume basis.  The
hydrocarbon analyzer measured the concentrations in parts per
million wet volume  as propane (ppmwv as C3H8) .

     4.1.11.1  Sampling System Description;  An integrated,
remote instrumental system housing the pollutant gas analyzers as
well as the diluent gas (02 and C02) monitors were  used.  The
design incorporated a dry extractive system.   All of the
instruments were housed in a trailer located at ground level.

     Figure 4.1.11.1-1 is a schematic of the dry sampling system.
Each dry sampling system consisted of a heated stainless steel
probe located at the stack port location.  A heated glass fiber
filter was attached to the probe for rough particulate removal.
A short section  of  heated Teflon sample line delivered the sample
to an ice-cooled condenser designed to remove the  flue gas
moisture.  An unheated Teflon sample line transported the dry gas
sample from the  stack port location down to the instrumental
system.  The sample gas exiting the Teflon sample  line was pumped
to the 02/  C02, CO,  and NOX monitors.

     The sampling system for each hydrocarbon analyzer
incorporated a heated stainless steel probe, a heated glass fiber
filter, and a heated Teflon sample line.  The sample line was
                                21

-------
heated along its entire length from the stack sampling location
to the analyzer.  Figure 4.1.11.1-2 is a schematic of the wet
sampling system used for Method 25A.

     4.1.11.2  Data Acquisition System;  The response outputs  of
the monitors were recorded digitally by a Campbell Scientific
Model CR10WP multi-channel data acquisition system.  The system
sampled at a rate of 60 Hz, and stored one-minute average values.

     4.1.11.3  Calibration;  At the beginning of every test day,
each monitor in the dry sampling system was zeroed, using Zero
Nitrogen, and spanned, using a certified calibration gas (EPA
Protocol 1 certified or ± 1% Traceable Standards) with a
concentration of 80-100% of the instrument span.  Following local
calibration a mid range gas, 40-60% of the instrument span, was
introduced locally to each monitor to check for response
linearity.  The mid range response error did not exceed 2% of  the
instrument span as required by EPA Reference Method 6C.

At the beginning of every test day in which THCs were to be
measured, each THC monitor was zeroed, using Zero Nitrogen, and
spanned, using a certified propane calibration gas (EPA Protocol
1 certified or ± 1% Traceable Standards) with a concentration  of
80-90% of the instrument span.  Following local calibration a  mid
range gas (45-55% of the instrument span) and a low range gas
(25-35% of instrument span) was introduced locally to each
monitor to check for response linearity.  The mid range response
error did not exceed 5% of the respective gas value as required
by EPA Reference Method 25A.

     After locally calibrating all monitors, calibration gas was
introduced remotely through the probe in order to verify the
absence of sampling system bias.   The bias error did not exceed
5% of the instrument span as required by EPA Reference Method  6C.

After each test run, Zero Nitrogen and a high range calibration
gas was introduced locally to each monitor to check for
calibration drift error.  In accordance with Methods 6C and 25A,
the instrument drift did not exceed 3% of the instrument span
except, for the run to be considered valid.

     At the end of every test day, calibration gas was again
introduced remotely through the probe in order to verify the
absence of sampling system bias.   The bias error did not exceed
5% of the instrument span except for the runs noted in the field
test changes and problems section of this report.

     4-1-12  Methane and Ethane Sampling - EPA Method 18;  EPA
Method 18 was conducted for sampling methane (CH4)  and
ethane(C2H8).  Samples were collected using the Flexible Bag
Procedure with some modifications.
                               22

-------
     4.1.12.1  Sampling Train Description;  A stainless steel
probe was affixed to the pollutant sampling probe for sampling
purposes.  A teflon-lined leak-free diaphragm pump, delivering
500 to 750 mL/min of flue gas, was used to fill a Tedlar bag.
Figure 4.1.12.1 shows a schematic of the sampling train.

     4.1.12.2  Pre-Test Bag Preparation; Each new, unused tedlar
bag was checked for contamination before testing by filling with
an inert gas (zero nitrogen), allowing it to sit overnight, then
analyzing the contents with by FID.

     4.1.12.3  Sampling Train Operation; Multi-point, integrated
sampling was used to obtain a constant rate sample of flue gas
concurrent with the VOST and Semi-VOST.  Sampling was of the same
duration (except purges following port changes) as the pollutant
runs.  A sampling schematic is shown in figure 4.1.12.3-1.

     4.1.12.4  Ethane and Methane Analysis;  Bag samples were
analyzed for methane and ethane using a GC in accordance with EPA
Method 18, Section 7.1.5 "Analysis of Bag Samples" (40 CFR 60,
Appendix A).  Analysis for methane and ethane was performed by
injection of an aliquot of the gas sample on a gas chromatograph
and analyzing the sample by FID.  A schematic of the analytical
procedure is shown in Figure 4.1.12.4-1.

     4.1.13  Volatile Organics Sampling;  Sampling for volatile
organics was conducted in accordance with Method 0030 of SW-846.

     4.1.13.1  Sampling Train Description; A schematic of the
volatile organic sampling Train (VOST) is shown in Figure
4.1.13.1-1.  The primary components of the VOST system were the
probe, condenser, condensate trap, a second condenser, and a
backup resin trap.  The first cartridge was packed with
approximately 1.6 grams of Tenax-GC resin.  The second cartridge
was packed with Tenax-GC and petroleum-based charcoal (1 gram of
each, approximately 3:1 by volume), with the charcoal on the
outlet end of the cartridge.  The first trap retained most of the
higher boiling analytes.  Lower boiling analytes and the portion
of the higher boiling analytes that break through the first
cartridge were retained on the second trap.  Analytes that
collect in the condensate trap were purged into the second trap
and condenser units.  The metering system consisted of vacuum
gauges, a leak-free pump, a calibrated rotameter, and a dry gas
meter.

     4.1.13.2  Sampling Train Operation;  Sampling was done in
accordance with Method 0030 of SW-846 procedures, including leak
checking and sampling rate.  The train was leak checked by
closing the valve at the inlet to the first condenser and pulling
a vacuum of 10 in. Hg above the normal operating pressure.  The
traps and condensers were isolated from the pump and the leak
check noted.  The leak rate was less than 0.1 in. Hg per minute.

                                23

-------
After leak checking, sample collection was accomplished by
opening the valve at the inlet to the first condenser,  turning on
the pump, and sampling at the rate of approximately  one liter per
minute  (1 1pm) for 20 minutes.  At this point, the train was
leaked checked at the highest vacuum achieved during the sampling
run, and the first pair of sorbent cartridges were replaced with
a  new pair of cartridges.  This procedure was repeated  until  a
total of six pairs of sorbent cartridges were used.   This
resulted in a sampling time of 120 minutes per run.

     4.1.13.3  Sample Train Recovery and Clean-up;   At  the end of
each 20-minute sampling period, each pair of sorbent cartridges
was removed from the sampling train, the end caps were  replaced
on the cartridges, and the cartridges were stored in a  cooler
with "Blue Ice" until analysis.  A schematic of the  recovery  is
shown in figure 4.1.13.3-1.

     4.1.13.4  Field Blanks;  A single pair of sorbent  cartridges
was taken to each sampling location and the ends removed for  a
period of time while the two pairs of sorbent cartridges on the
VOST system were exchanged.  At the end of this period,  the end
caps were replaced, and the cartridges were stored and  analyzed
with the samples cartridges.

     4.1.13.5  Volatile Organics Analyses - Method 0030;   The
VOST sorbent cartridges were analyzed for Volatile Compounds
listed in Table 1.1-2.  The analyses were performed  using thermal
desorption and gas chromatography with mass spectroscopy (GC/MS)
in accordance with Method 0030 procedures.  A schematic  of the
analytical procedure is contained in Figure 4.1.13.5-1.

     4.1.14  Semivolatile Organics Sampling;  Sampling  for semi-
volatile organics was conducted in accordance with Method 0010  of
SW-846.

     4.1.14.1  Sampling Train Description;  Figure 4.1.14.1-1
illustrates the Method 0010 sampling train.  The train  employed a
single piece quartz nozzle and probe for sample withdrawal.   The
nozzle opening was appropriately sized to maintain isokinetic
sampling.   Particulate matter was removed from the gas  stream by
means of a heated gas filter supported on a Teflon frit.   The
filter temperature was maintained at 248 + 25°F.   After
particulate removal, the gases passed into a water-cooled glass
condenser and enter an XAD resin sorbent trap.  The  sorbent trap
was packed with pre-cleaned,  quality control checked amberlite
XAD-2 resin.   Coolant water maintained at wet-ice temperature was
continuously recirculated into the assembly using a  submersible
water pump.   The condenser cooled the sample gases and  condensed
part of the moisture.   The cooled gases and condensate  flowed
down through the XAD-2 resin which retained the organics.   After
passing through the sorbent trap, the sample gases passed through
a chilled  impinger train to remove the remaining moisture.  The

                               24

-------
impinger train consisted of five glass impingers immersed in an
ice bath.  The first impinger was left blank to facilitate
collection of the condensate which passed through the XAD-2 resin
trap.  The second and third impingers each contained 100
milliliters of distilled water.  The fourth impinger was
initially empty and the fifth impinger initially contained
approximately 200 grams of silica gel.  All components from the
nozzle to the fourth impinger were made of glass.  All
connections from the probe to the exit stem of the fourth
impinger were sealed with Teflon 0-rings.  Sealing grease was not
used on any connections before the fifth impinger.

     4.1.14.2  Sampling Train Operation;  Sampling was performed
in general accordance with EPA Method 5 procedures and
specifications, including leak checking, isokinetic sampling
rate, and stack traversing.  Sampling was performed for 7.5
minutes at each of the 24 traverse points, yielding a 180-minute
test per run at each test location.  A minimum sample volume of
106 dry standard cubic feet was obtained for each run.

     4.1.14.3  Sample Recovery and Clean-up;  At the completion
of each test run, the probe was removed from the train, and the
ends of the sample train capped with hexane-rinsed aluminum foil.
The probe was immediately recovered at each sampling location,
while the remainder of the sampling train was transported to a
clean-up site for recovery-  Sample recovery proceeded as follows
(figure 4.1.14.3-1);

     Immediately upon recovery, all samples including liquid
rinses, filters and sorbent traps were placed into insulated
coolers packed with ice, thus protecting the samples from light
and heat.

     The samples remained inside the coolers during transport to
the analytical laboratory.  While in the custody of ETS, the
temperatures inside the coolers were periodically measured to
insure that the samples did not exceed 32°F.   All samples were
express mailed directly to the analytical lab for analysis.
While at the lab, the samples were kept in a refrigerated
compartment until analyzed.

     4.1.14.4  Field Blanks;  Three field blanks were collected
during the test program for the Method 0010 tests.  Each field
blank consisted of a complete sampling train set up on site and
recovered during the recovery of the normal stack test samples.

     4.1.14.5  Semivolatile Oroanics Analyses;  Analysis of the
Method 0010 sample train components were performed in accordance
with the procedures outlined in Method 0010 of SW-846.  Analyses
were performed for the Semivolatile compounds listed in Table
1.1-3.  The analyses were performed with high resolution gas
chromatography/mass spectrometry (GC/MS).  A schematic of the

                                25

-------
analytical procedure is contained in Figure 4.1.14.5-1.


5.0  QA/QC ACTIVITIES

     Specific quality control (QC) procedures were followed to
ensure the continuous production of useful and valid data
throughout the course of this test program.  The QC checks and
procedures described in this section represent an integral part
of the overall sampling and analytical scheme.  Strict adherence
to prescribed procedures is quite often the most applicable QC
check.  A discussion of both the sampling and analytical QC
checks that were utilized during this program are presented
below.

5.1  Equipment: QA Procedures

     For all test methods requiring a dry gas meter, an EPA
supplied calibrated critical orifice was used for auditing.
Limits of acceptability and procedures followed those recommended
in Method 5, Section 7.2 of 40 CFR 60.  Data sheets for the above
procedures were provided by the EPA.


5.2  Equipment QC Procedures

     5.2.1  Equipment Inspection and Maintenance;  Each item of
field test equipment was assigned a unique, permanent
identification number.  An effective preventive maintenance
program was necessary to ensure data quality.  Each item of
equipment returning from the field was inspected before it was
returned to storage.  During the course of these inspections,
items were cleaned, repaired, reconditioned, and recalibrated
where necessary.

     Each item of equipment transported to the field was
inspected again before being packed to detect equipment problems
which may originate during periods of storage.  This minimizes
lost time on the job site due to equipment failure.

     Equipment failure in the field was unavoidable despite the
most rigorous inspection and maintenance procedures.  For this
reason, ETS routinely transported to the job site spare equipment
for all critical sampling train components.

     5.2.2  Equipment Calibration;  New items for which
calibration was required were calibrated before initial field
use.  Equipment whose calibration status may change with use or
time was inspected in the field before testing began and again
upon return from each field use.  When an item of equipment was
found to be out of calibration, it was repaired and recalibrated
or retired from service.  All equipment was periodically

                                26

-------
                           ji      f i-v,a outcome of these regular
recalibrated in full,  regardless of the outcome o
inspections .

     Calibrations are conducted in a manner  and at a ^^7
which meets or exceeds U.S.  EPA ^Jhodsf and those
                                            ethoas, a
w                       .                      hods  an
calibration procedures outlined in the EPA Methoas, a
recommended within the Quality Assurance Handbook for _Air
                                Volume III (PA-eou/*  / u
Pollution Measurement Systems:   Volume III
August, 1977).  When these methods were in,  .
Sods such as those prescribed by the American Society for
Testing and Materials (ASTM) .

     Data obtained during calibrations were recorded on
standardized forms, which were checked for complet jness and
accuracy by the quality assurance director or the quality
assuranL managed  Data reduction and ^se?ue^sCal^^^°Sons
were performed using ETS's own computer facilities.  Calculations
were checked at least twice for accuracy.

Emissions sampling equipment requiring calibration included pitot
tubes, pressure gauges, thermometers, dry gas meters, ana
barometers.  The following sections elaborate on the calibration
procedures followed by ETS for these items of equipment.

     5.2.2.1  Pitot Tubes;  All Type-S pitot tubes used by ETS,
whether separate or attached to a sampling probe, are constructed
in-house.  Each new pitot was calibrated in accordance with the
geometric standards contained in EPA Method 2.  A Type S pitot
tube, constructed and positioned according to these standards,
had a coefficient of 0.84 ± 0.02.  This coefficient should not
change as long as the pitot tube was not damaged.  The actual
coefficient of each pitot tube was determined using a wind tunnel
calibration against a standard NIST traceable pitot tube.  These
calibrations were performed in accordance with EPA Method 2
procedures .

     Each pitot tube was inspected visually upon return  from the
field.  If a cursory inspection indicated damage or raised doubt
that the pitot remained true to its original calibration, the
pitot tube was refurbished as needed and recalibrated.

     5.2.2.2  Impinger Thermometer;  Prior to the  start  of
testing, the thermometer used to monitor the temperature of the
gas leaving the last impinger was compared with  a mercury-in-
glass thermometer which meets ASTM E-l No. 63F specifications.
The impinger thermometer was adjusted when necessary until  it
agreed within 2°F of the reference thermometer.   If  the
thermometer was not adjustable, it was labeled with  a correction
factor.

     5.2.2.3  Dry Gas Meter Thermometer;  The thermometer  used to
measure the temperature of the metered gas sample  was checked

                                27

-------
prior to each field trip against an ASTM mercury-in-glass
thermometer.  The dry gas meter thermometer was acceptable if the
values agree within ± 5.4°F.  Thermometers not meeting this
requirement were adjusted or labeled with a correction factor.

     5.2.2.4  Flue Gas Temperature Sensor;  All thermocouples
employed for the measurement of flue gas temperatures were
calibrated upon receipt.  Initial calibrations were performed at
three points (ice bath, boiling water, and furnace).  An ASTM
mercury-in-glass thermometer was used as a reference.  The
thermocouple was acceptable if the agreement is within 1.5
percent (absolute) at each of the three calibration points.

     On-site, prior to the start of testing, the reading from the
flue gas thermocouple-potentiometer combination was compared with
an ASTM mercury-in-glass reference thermometer.  If the two agree
within ± 1.5 percent  (absolute), the thermocouple and
potentiometer were considered to be in proper working order for
the test series.  After each field use, the thermocouple-
potentiometer system was compared with an ASTM mercury-in-glass
reference thermometer at a temperature within ± 10 percent of the
average absolute flue gas temperature data.  If the absolute
temperatures agree within +1.5 percent, the temperature data
were considered valid.

     5.2.2.5  Dry Gas Meter and Orifice;  Two procedures were
used to calibrate the dry gas meter and orifice simultaneously.
The full calibration was a complete laboratory procedure used to
obtain the calibration factor of the dry gas meter.  Full
calibrations are performed over a wide range of orifice settings.
A simpler procedure, the post test calibration, was designed to
check whether the calibration factor had changed.  Post test
calibrations were performed after each field test series at an
intermediate orifice setting (based on the test data) and at the
maximum vacuum reached during the test.

     Each metering system received a full calibration at the time
of purchase and a post test calibration after each field use.  If
the calibration factor Y deviated by less than five percent from
the initial value, the test data were acceptable.  If Y deviated
by more than 5 percent, the meter was recalibrated and the meter
coefficient (initial or recalibrated) that yielded the lowest
sample volume for the test runs was used.  EPA Method 5 requires
another full calibration anytime the post test calibration check
indicates that Y had changed by more than 5 percent.  Standard
practice at ETS is to recalibrate the dry gas meter anytime Y was
found to be outside the range of 0.98 to
1.02.

     An orifice calibration factor was calculated for each flow
setting during a full calibration.  If the range of values did
not vary by more than 0.15 in. H20 over the range of 0.4 to 4.0

                                28

-------
in. H20, the arithmetic average of the values obtained during  the
calibration was used.

5.3  Sampling QC Procedures

     5.3.1  Pre-Test PC Checks  »"*  Procedures;   The following
pretest QC checks were conducted:

          All  sampling eguipment was  thoroughly checked to ensure
          clean and operable components.

          Eguipment was inspected for possible  damage from
          shipment.

          The  oil manometer used to measure  pressure across the
          Type S pitot tube was leveled and  zeroed.

          The  number and location of  the  sampling traverse points
          were checked before taking  measurements.

          The  temperature measurement system was visually checked
          for  damage and operability  by measuring the ambient
          temperature prior to  each traverse.

          All  cleaned glassware and sample train components were
          kept sealed until train assembly.

          The  sampling trains were  assembled in an environment
          free from uncontrolled dust.

          Each sampling train was visually inspected for proper
          assembly.

          Pretest calculations  determined the proper sampling
          nozzle size.

     5.3.2  QC Checks  and Procedures  During  Testing;  The
following  checks and procedures will  be conducted during testing:

          Readings  of  temperature and differential  pressure were
          taken at  each traverse point.

          All  sampling data and calculations were recorded on
          Preformatted data sheets.

          All  calibration data  forms  were reviewed for
          completeness  and accuracy.

          Any  unusual  occurrences were noted during each run on
          the  appropriate data  form.

          The  project  supervisor reviewed sampling data  sheets

                               29

-------
          daily during testing.

          The roll and pitch axis of the Type S pitot tube and
          the sampling nozzle were properly maintained.

          Leak check the train before and after any move from one
          sampling port to another during a run or if a filter
          change took place.

          Conduct additional leak checks if the sampling time
          exceeded 4 hours.

          Maintained the probe, filter and impingers at the
          proper temperature.

          Maintained ice in the ice bath at all times.

          Make proper readings of the dry gas meter, delta P and
          delta H, temperature, and pump vacuum during sampling
          at each traverse point.

     -    Maintained isokinetic sampling within ± 10% of 100%.

     5.3.3  QC Checks and Procedures After Testing;

          Visually inspect the sampling nozzle.

          Visually inspect the Type S pitot tube.

          Leak check each leg of the Type S pitot tube.

          Leak check the entire sampling train.

5 .4  Analytical QA Procedures

     All analytical QA procedures followed those given in each
test method.  Each test method along with the prescribed
reference sections regarding auditing procedures are as follows:

          Test Method              Reference

          Method 29          -    Method 29, Section 7
                                  proposed to be added to
                                  Appendix A of 40 CFR 60

          Method 26          -    Method 26, Section 6.2
                                  of 40 CFR 60

          Method 18          -    Method 18, Section 7.4.4.3
                                  of 40 CFR 60
                                30

-------
          Method 0030        -    Method 0030, Section 7.0
                                  of SW - 846

          Method 0010        -    Method 0010, Section 11.0
                                  of SW - 846

5.5  Analytical QC Procedures

     All analyses for this program were performed using accepted
laboratory procedures in accordance with the specified analytical
protocols.  Adherence to prescribed QC procedures ensured data of
consistent and measurable quality.  Analytical QC focused upon
the use of control standards to provide a measure of analytical
precision and accuracy.   Also, specific acceptance criteria were
defined for various analytical operations including calibrations,
control standard analyses, drift checks, blanks, etc.  The
following general QC procedures were incorporated into the
analytical effort:

          The on-site project supervisor reviewed all analytical
          data and QC data on a daily basis for completeness and
          acceptability.

          Analytical QC data was tabulated using the appropriate
          charts and forms on a daily basis.

          Copies of the QC data tabulation were submitted to the
          quality assurance manager following the completion of
          the test program.

          All hard copy raw data (i.e., strip charts, computer
          printouts, etc.) were maintained in organized files.
5.6  QA/QC Checks of Data Reduction

     Calculations that were to be used in the field were checked
by the QA officer prior to testing with predetermined data.  The
QA officer performed random checks in the field to insure data
was being properly recorded.  Upon completion of the testing,
data was then transferred from the data sheets to the computer.
This process was also reviewed and checked by the QA officer.
When multiple tests were performed in one location, data from
each test were compared.


5.7  Sample Identification and Custody
/• ^ Each test run was assigned a unique run identification
JOQ*   ^v!1? consisted of a 3 digit code for the location, the
test method and the specific test run.   Labels were pre-printed
                               31

-------
with the test method, the container number, a unique
client/sample i.d., a space to write in the run number described
above and the contents of the sample container.  As each sample
was recovered, its sample label was attached and the sample
number and contents were recorded in the chain of custody section
of the run sheet.  The run identification, the sample number and
contents were then recorded in a bound field sample log that was
maintained by the sample recovery person. A glue on label
carrying the signature of the recovery person was placed around
the lid to the shoulder of the sample bottle in such a way that
the label must be broken for the sample bottle to be opened.  A
three way check was then made by the recovery person to insure
that the sample label information, the log book information and
the run sheet chain of custody all corresponded correctly.

     When the samples were returned for analysis, the team leader
again checked to see that the sample label information, the run
sheet chain of custody and the field log book information all
corresponded correctly.  Any discrepancies were brought to the
attention of the project manager.  If any condition existed that
may influence the integrity of the sample, it was noted and
brought to the attention of the project manager (i.e. broken
seals, leaking samples, improper storage temperature).  All of
the chain of custody information was entered into a database. A
print out of the computerized field log  was made and checked
against the chain of custody on the test run sheet.  A copy of
the computerized chain of custody accompanied the samples  to the
location where they were to be analyzed.  Each sample label was
checked again against the computerized field log as it was sent
from sample management.
                                32

-------
Table l.l-l:   Targeted  Metals
                               METAL
                             antimony
                              arsenic
                             beryllium
                              cadmium
                             chromium
                               lead
                             manganese
                              mercury
                              nickel
                            phosphorus
                             selenium
                               33

-------
TABLE 1.1-2:    Targeted Volatile Compounds
COMPOUND  (VALIDATED1)
COMPOUND (NOT VALIDATED2)
chloromethane

bromomethane

methylene chloride

chloroform

trichlorofluoromethane*

iodomethane

carbon tetrachloride

trichloroethene*

benzene

tetrachloroethene
acetone

carbon disulfide

acrylonitrile

2-butanone

1,1,1-trichloroethane

vinyl acetate

2-hexanone*

toluene

ethylbenzene

styrene

o-xylene

m-/p-xylene
2 Validated Analytical Method
t Not a Validated Analytical Method
 Not a listed HAP.
                             34

-------
TABLE 1.1-3:   Targeted Semivolatile Compounds


COMPOUND (VALIDATED1)   	COMPOUND (NOT VALIDATED2)

phenol                            2-methylphenol*

naphthalene                       dimethylphthalate

                                   dibenzofuran

                                   di-n-butylphthalate*


	bis(2-ethylhexy)phthalate

  Validated Analytical Method
f Not a Validated Analytical Method
  Not a listed HAP.
                                35

-------
Table 3.2-1:
Sampling Matrix for Crushing,  Grinding, and Screen!na
Operations at Pine Hall Brick (Madison, North Carolina)
Run #
Date
1
10/27/92
2
10/28/92
3
10/29/92
4
11/02/92
5
11/03/92
6
11/04/92
7
11/05/92
8
11/06/92
Sample
Type
>
>
p>
PM
>
PP>
>
"P>
>
Test
Method
Ambient Hi-Vola
Ambient Hi-Volb
Ambient Hi-Vola
Ambient Hi-Volb
Ambient Hi-Vola
Ambient Hi-Volb
Ambient Hi-Vola
Ambient Hi-Volb
Ambient Hi-Vola
Ambient Hi-Volb
Ambient Hi-Vola
Ambient Hi-Volb
Ambient Hi-Vola
Ambient Hi-Volb
Ambient Hi-Vola
Ambient Hi-Volb
Sample location/Time
Boundary and Grinding
7:00-16:04
8 1/2 hrs
Boundary and Grinding
7:08-16:46
9 1/2 hrs
Boundary and Grinding
7:10-15:31
8 1/4 hrs
Boundary and Crushing
8:00-17:50
10 hrs
Boundary and Crushing
6:55-15:01
8 3/4 hrs
Boundary and Crushing
6:45-15:20
9 1/4 hrs
Boundary
7:05-15:19
8 1/4 hrs
Boundary
16:15-9:03
7 1/4 hrs
  40 CFR 50,  Appendix B
  40 CFR 50,  Appendix J
                                      36

-------
Table 3.2-2:
Test Matrix for Kiln and Sawdust Dryer Operations at Pine
Hall Brick (Madison, North Carolina).
RUN #
DATE


1
11/02/92




2
11/02/92




3
11/03/92




4
11/03/92




5
11/04/92




6
11/04/92




7
11/04/92


SAMPLE
TYPE


PS
HF
o2/co2
CO
NOV

PS
HF
o2/co2
CO
NOV

PS
HF
o2/co2
CO
NOV

PM1Q
CPM
o2/co2
CO
N0v

PM10
CPM
o2/co2
CO
NOV

S»
o2/co2
CO
NO,

MM
PM
"*£*
N0*
TEST
METHOD


Imp
M26C
M3AC
M10C
M7EC

Imp
M26C
M3AC
M10C
M7EC

Imp
M26C
M3AC
M10C
M7EC

M201A
M202
M3AC
M10C
M7EC

M201A
M202
M3AC
M10C
M7EC

M201A
M202
M3AC
M10C
M7EC

M0012
PMa
M3AC
M10C
M7EC
SIMULTANEOUS
SD- INLET SD-OUTLET SD-OUTLET
A B
13:11-15:28
120 minutes
120
120
120
120
17:33-19:42
120 minutes
120
120
120
120
9:15-11:32
120 minutes
120
120
120
120
16:54-19:36
120 minutes
120
120
120
120
10:15-12:55
120 minutes
120
120
120
120
14:12-16:45
120 minutes
120
120
120
120
19:40-22:41
120 minutes
120
120
120
120
                                        37

-------
Table 3.2-2  (Continued)
RUN #
DATE

8
11/05/92



9
11/05/92




10
11/05/92



11
11/06/92





12
11/06/92





13
11/07/92



SAMPLE
TYPE

MM
PM
o2/co2
CO
NOV

MM
PM
o2/co2
2co 2
NOV

PS
o2/co2
co 2
NOV

VOC
SVOC
o2/co2
CO
NOX
THC

VOC
SVOC
°2/C02
CO *
NO
THC

VOC
SVOC
o2/co2
CO
NO
THC
=^==i
TEST
METHOD

M0012
PM8
M3AC
M10C
M7EC

M0012
PMa
M3AC
M10C
M7EC
Imp
M3AC
M10C
M7EC


M00306
M0010e
M3AC
M10C
M7EC
M25AC

M0030e
M00106
M3AC
M10C
M7EC
M25AC

M00306
M00106
M3AC
M10C
M7EC
M25AC
:==:=
SD- INLET SD-OUTLET SD-OCTLET
A B
9:28-11:53
120 minutes
120
120
120
120
13:25-15:50
120 minutes
120
120
120
120
16:44-17:55
120 minutes
120
120
120
11:47-16:38
120 minutes
120
120
120
120
120
17:34-21:42
120 minutes
120
120
120
120
	 120 	
9:02-13:12
120 minutes
120
120
120
120
120
:^ 	 	 ^^=s
^Sg'sr^SL0^11""^ Wl^ RTF *"n(™/530-S*-91-010)
^40 CFR 60,  Appendix A
                                       integrated bag sample for GC  analysis
                                   Waste,  Third Edition, Report SW-846,  U.S.
 ~t\j ^c f\ uu,  nppefllUXX A
dM18 of 40 CFR 60,  Appendix 1
eTest Methods for Evaluating
                                       38

-------
Table 3.2-3!
Test Matrix for the Grinding Building and Sawdust Dryer.
Testing performed by the EPA EMB.
Run #
Date
1
10/26/92
2
10/27/92
3
10/28/92
4
10/29/92
5
10/30/92
Sample
Type
PM10
PM10
PM10
Total
Fluoride
Total
Fluoride
Test
Method
M201
M201
M201
13B
13B
Sample Location/ Time
Grinding Building
Grinding Building
Grinding Building
Sawdust Dryer
Sawdust Dryer
                                     39

-------
Table 3.4.1-1: Average ambient sampling concentrations.
Pollutant
TSP
PMm
East end
M9/m
61.5
26.0
West end
pg/m3
45.6
30.9
Grinding
/jg/m3
104.1
59.0
Crusher
Aig/m3
1356.9
584.6
                                  40

-------
TABLE 3.4-1-2:
      SUMMARY OF METHOD 201: TOTAL FILTERABLE  PARTICULATE  AND  PM1Q:
      GRINDING-SCREENING BUILDING
RUN NUMBER D1-M201-R1 D1-M201-R2 D1-M201-R3
DATE 10/27/92 10/28/92 10/28/92
SAMPLING DATA
Metered Volume - cf
Total Test Time - min
% Isokinetic
GAS PARAMETERS
Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
GAS FLOWRATE
Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
TOTAL FILTERABLE PARTICULATE
Concentration - gr/dscf 0
Mass Rate - Ib/hr
TOTAL PM10 EMISSIONS
Concentration - gr/dscf 0
Mass Rate - Ib/hr

62.641
240
98.8

72
20.9
0.0
1.0

31.13
23471
22709
EMISSIONS
.01166
2.270

.00094
0.183

51.108
180
98.4

61
20.9
0.0
1.0

33.64
26163
25891
0.00777
1.724

0.00077
0.171

52.638
180
98.2

69
20.9
0.0
1.0

34.87
27119
26414
0.01284
2.907

0.00072
0.163
AVERAGE

55.462
200
98.5

67
20.9
0.0
1.0

33.21
25585
25005
0.01076
2.300

0.00081
0.172
Note:
Dl is duct #1 off the Grinding-Screening building.

See Appendix F.3.1 for detailed field sampling information.

A duct size of 48.0 inches was used in calculating flowrates.   This
information was gathered from ETS, Inc. files pertaining to the duct  work.
                                           41

-------
TABLE 3.4.1-3:
     SUMMARY OF METHOD 201: TOTAL FILTERABLE  PARTICT) 7VI.
     GRINDING-SCREENING BUILDING
                                                                       AND
                                                                             MO'
RUN NUMBER
DATE
             D2-M201-R1  D2-M201-R2  D2-M201-R3
                10/27/92    10/28/92     10/28/92
                                                                AVERAGE
SAMPLING DATA

Metered Volume - cf
Total Test Time - min
% Isokinetic
                  45.031
                     240
                    99.2
  35.88
    180
  104.2
 36.691
    180
  102.6
 39.201
    200
  102.0
GAS PARAMETERS

Gas Temperature  -  oF
Oxygen -  %
Carbon Dioxide - %
Moisture  -  %
72
20.9
0.0
1.0
61
20.9
0.0
1.0
67
20.9
0.0
1.0
67
20.9
0.0
1.0
 GAS  FLOWRATE

 Velocity  -  ft/sec
 Actual  Volume  -  acfm
 Standard  Volume  -  dscfm
                   38.15
                   28764
                   27883
  38.50
  29943
  29668
  39.72
  30891
  30280
  38.79
  29866
  29277
 TOTAL  FILTERABLE PARTICULATE EMISSIONS

 Concentration - gr/dscf      0.01584      0.00736      0.01064   0.01128
 Mass Rate - Ib/hr              3.786        1.872        2.762     2.806
 TOTAL PM1Q EMISSIONS

 Concentration - gr/dscf
 Mass Rate - Ib/hr
                 0.00185
                   0.442
0.00097
  0.247
0.00088
  0.228
0.00123
  0.306
 Note:
D2 is duct #2 off the Grinding-Screening building.

See Appendix F.3.2 for detailed field sampling information.

A duct size of 48.0 inches was used in calculating flowrates.   This
information was gathered from ETS, Inc. files pertaining  to  the duct work.
                                          42

-------
TABLE 3.4.2-1: SUMMARY OF FILTERABLE PARTICULATE AND METALS EMISSIONS:
               SAWDUST DRYER INLET.
RUN I.D.
DATE
TIME STARTED
TIME ENDED

SAMPLING PARAMETERS
IN-MM/TSP-R1
    11/04/92
       19:40
       22:41
Metered Volume  -  dcf         74.087
Corrected Volume  - dscf      73.648
Total Test  Time - min           120
% Isokinetics                 102.3

GAS PARAMETERS

Gas Temperature - oF          496.9
Oxygen - %                     15.5
Carbon Dioxide  -  %              4.9
Moisture -  %                   7.97

GAS FLOWRATE

Velocity -  ft/sec            58.50
Actual Volume - acfm          55826
Standard Volume - dscfm       28005

FILTERABLE  PARTICULATE EMISSIONS
Concentration  -  gr/dscf
Cone.  -  gr/dscf  @  7% O2
Mass Rate  -  Ib/hr

METALS EMISSIONS - Ib/hr

Antimony
Arsenic
Beryllium
Cadmium
Chromium
Lead
Manganese
Mercury
Nickel
Phosphorus
Selenium
CO EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr

NOx EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr  (as NO2)
      0.0201
      0.0515
        4.83
IN-MM/TSP-R2
    11/05/92
       09:28
       11:53
                    83.040
                    82.184
                       120
                      99.8
                     494.6
                      16.1
                       4.8
                      6.52
                     65.49
                     62490
                     32033
      0.0206
      0.0595
        5.64
      453.23
       55.36
       34.12
        6.85
IN-MM/TSP-R3
    11/05/92
       13:25
       15:50
                    76.204
                    74.533
                       120
                     100.5
                     495.0
                      16.1
                       4.6
                      7.37
                     60.11
                     57357
                     28862
      0.0196
      0.0560
        4.84
                               AVERAGE
      401.98
       56.16
       39.39
        9.04
                  77.777
                  76.789
                     120
                   100.9
                   495.5
                    15.9
                     4.8
                    7.29
                   61.36
                   58558
                   29634
0.0201
0.0557
  5.10
< 1
9
9
1
5
5
1
1
3
1
1
.24E-04
.52E-04
.06E-06
.06E-04
.68E-04
.66E-03
.88E-02
.65E-04
. 55E-04
.92E-02
.97E-03
< 1
9
9
2
9
2
1
9
6
3
3
.24E-04
.09E-04
.28E-06
.91E-04
.23E-04
.92E-03
.72E-02
.02E-05
.10E-04
.09E-02
.70E-04
1.
7.
1.
4.
1.
8.
6.
2.
7.
2.
5.
97E-04
53E-04
84E-05
79E-04
19E-03
04E-03
08E-01
45E-04
81E-04
16E-02
12E-04
< 1.
8.
1.
2.
8.
5.
2.
1.
5.
2.
9.
48E-04
71E-04
23E-05
92E-04
93E-04
54E-03
15E-01
67E-04
82E-04
39E-02
50E-04
      369.35
       46.50
       34.02
        7.03
408.19
 52.67
 35.84
  7.64
                                          43

-------
TABLE 3.4.2-2: SUMMARY OF FILTERABLE PARTICULATE AND METALS EMISSIONS;
               SAWDUST DRYER OUTLET A.
RUN I.D. OA-MM/TSP-R1
DATE 11/04/92
TIME STARTED
TIME ENDED
SAMPLING PARAMETERS
Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics
GAS PARAMETERS
Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
GAS FLOWRATE
Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
19:40
22:41

81.477
78.602
120
102.7

180.9
17.2
3.3
12.22

44.78
24634
17170
OA-MM/TSP-R2
11/05/92
09:29
11:53

80.045
77.167
120
103.3

190.8
17.1
3.4
11.37

43.91
24157
16756
OA-MM/TSP-R3
11/05/92
13:25
15: 50

83.415
80.166
120
104.1

194.2
17.2
3.3
11.85

46.11
25365
17273
AVERAGE



81.646
78.645
120
103.3

188.6
17.2
3.4
11.81

44.93
24719
17066
FILTERABLE PARTICULATE EMISSIONS
Concentration - gr/dscf
Cone. - gr/dscf @ 7% O2
Mass Rate - Ib/hr
METALS EMISSIONS - Ib/hr
Antimony <
Arsenic
Beryllium
Cadmium
Chromium
Lead
Manganese
Mercury
Nickel
Phosphorus <
Selenium
CO EMISSIONS
Cone. - ppmdv
Mass Rate - Ib/hr
NOx EMISSIONS
Cone. - ppmdv
Mass Rate - Ib/hr (as NO2)
0.0150
0.0565
2.21

2.72E-05
1.97E-04
2.31E-06
8.12E-05
2.72E-04
2.41E-03
2.63E-03
1.34E-04
3.17E-04
7.04E-03
4.60E-04

346.92
25.98

24.40
3.00
0.0153
0.0563
2.19

< 2.76E-05
2.31E-04
< 1.44E-06
1.52E-04
6.78E-04
9.18E-04
3.78E-03
8.62E-05
4.51E-04
4.71E-03
4.51E-04

360.91
26.38

26.86
3.22
0.0207
0.0781
3.07

< 2.65E-05
2.60E-04
8.84E-06
5.79E-05
1.52E-04
1.11E-04
6.43E-03
6.10E-05
1.19E-04
< 6.93E-03
4.29E-04

349.77
26.35

19.91
2.46
0.0170
0.0636
2.49

< 2.71E-05
2.30E-04
< 4.20E-06
9.71E-05
3.67E-04
1.15E-03
4.28E-03
9.39E-05
2.96E-04
< 6.23E-03
4.47E-04

352.53
26.24

23.72
2.90
                                          44

-------
TABLE 3.4.2-3:  SUMMARY  OF  FILTERABLE  PARTICULATE AND METALS  EMISSIONS:
                SAWDUST  DRYER  OUTLET B.
RUN I.D.
DATE
TIME STARTED
TIME ENDED

SAMPLING PARAMETERS
OB-MM/TSP-R1
    11/04/92
       19:40
       22:41
Metered Volume  -  dcf         75.403
Corrected Volume  -  dscf      75.053
Total Test Time - min          120
% Isokinetics                 102.0

GAS PARAMETERS

Gas Temperature - oF          180.6
Oxygen - %                     17.3
Carbon Dioxide  -  %              3.3
Moisture - %                  11.77

GAS FLOWRATE

Velocity - ft/sec            42.73
Actual Volume  - acfm          23505
Standard Volume - dscfm      16507

FILTERABLE PARTICULATE EMISSIONS

Concentration  - gr/dscf     0.1370
Cone. - gr/dscf @ 7%  O2     0.5248
Mass  Rate  -  Ib/hr            19.39

METALS EMISSIONS  -  Ib/hr

Antimony                 < 7.10E-05
Arsenic                    9.19E-05
Beryllium                  2.33E-06
Cadmium                    2.71E-04
Chromium                   2.40E-04
Lead                       2.12E-03
Manganese                  3.57E-03
Mercury                    1.62E-04
Nickel                     2.03E-04
Phosphorus                 9.05E-03
Selenium                   1.73E-04

CO EMISSIONS
 Cone.  -  ppmdv
 Mass Rate  -  Ib/hr

 NOx EMISSIONS

 Cone.  -  ppmdv
 Mass Rate  -  Ib/hr (as NO2)
      345.75
       24.89
       19.85
        2.35
OB-MM/TSP-R2
    11/05/92
       09:28
       11:53
                    72.906
                    72.342
                       120
                     101.1
                     181.5
                      17.3
                       3.3
                     10.56
                     40.99
                     22551
                     16044
                    0.1465
                    0.5625
                     20.15
                < 7.16E-05
                  1.85E-04
                < 1.47E-06
                  2.80E-04
                  6.81E-04
                  7.04E-04
                  4.30E-03
                  3.96E-05
                  3.66E-04
                < 7.17E-03
                  4.67E-04
      352.00
       24.63
       23.73
        2.73
OB-MM/TSP-R3
    11/05/92
       13:25
       15:50
                                             AVERAGE
72.615
70.768
120
101.8
180.1
17.3
3.2
11.25
40.37
22208
15595
0.1555
0.6020
20.78
3.15E-05
9.80E-05
< 1.46E-06
2.63E-04
3.91E-04
3.96E-05
3.37E-03
5.98E-05
2.67E-04
< 7.14E-03
3.76E-04
335.80
22.84
25.14
2.81
73.641
72.721
120
101.6
180.8
17.3
3.2
11.20
41.36
22754
16048
0.1463
0.5631
20.11
< 5.80E-05
1.25E-04
< 1.75E-06
2.72E-04
4.37E-04
9.54E-04
3.75E-03
8.71E-05
2.79E-04
< 7.78E-03
3.39E-04
344.52
24.12
22.91
2.63
                                          45

-------
TABLE 3.a.2-4: SUMMARY OF PM1Q AND M202 RESULTS: SAWDUST DRYEF
RUN I.D.
DATE
TIME STARTED
TIME ENDED
IN-M201A-R1 IN-M201A-R2 IN-M201A-R3
   11/03/92    11/04/92    11/04/92
      16:54       10:15       14:12
      19:36       12:55       16:49
                                                                AVERAGE
SAMPLING PARAMETERS

Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics
D50
     59.176
     58.972
     131.25
      114.8
       9.59
56.140
56.639
 125.5
  95.5
  9.58
58.603
58.246
129.75
  98.8
  9.63
57.973
57.952
128.83
 103.0
  9.60
GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
      486.0
      15.63
        4.8
       6.66
 492.0
  15.7
   4.9
  6.35
 503.2
  15.4
   5.1
  6.05
 493.7
  15.6
   4.9
  6.35
GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
      49.89
      47604
      24714
 60.58
 57812
 29814
 59.01
 56312
 28690
 56.49
 53909
 27739
PM DISTRIBUTION

% Filterable
% Condensible
      39.98
      60.02
 41.75
 58.25
 47.09
 52.91
 42.94
 57.06
PARTICULATE EMISSIONS

Concentration - gr/dscf
Mass Rate - Ib/hr
     0.0404
       8.56
0.0339
  8.67
0.0324
  7.97
0.0356
  8.40
CO EMISSIONS

Cone.  - ppmdv
Mass Rate - Ib/hr
     405.75
      43.74
478.80
 62.26
485.13
 60.71
456.56
 55.57
NOx EMISSIONS
Cone. - ppmdv                   31.32       37.20
Mass Rate - Ib/hr (as NO2)        5.55        7.95
                              35.73
                               7.34
                       34.75
                        6.94
                                          46

-------
TABLE 3.4.2-5: SUMMARY OF PM1f1 AND M202 RESULTS:  SAWDUST DRYER OUTLET A.
RUN I. D .
DATE
TIME STARTED
TIME ENDED

SAMPLING PARAMETERS

Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics
D50

GAS PARAMETERS
OA-M201A-R1 OA-M201A-R2 OA-M201A-R3
   11/03/92    11/04/92    11/04/92
      16:54       10:15       14:12
      19:27       12:42       16:45
                                      AVERAGE
     52.652
     52.724
      120.9
      112.2
       8.97
46.381
47.097
   117
 101.6
  9.41
56.995
55.901
 135.1
  99.1
  9.21
52.009
51.907
124.33
 104.3
  9.20
Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %

GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
      186.9
      17.55
        2.6
      10.93
      43.35
      23848
      16845
 185.9
  17.0
   3.5
 11.50
 44.54
 24502
 17177
 183.7
  17.3
   3.2
 11.48
 47.01
 25861
 18099
 185.5
  17.3
   3.1
 11.30
 44.97
 24737
 17374
PM DISTRIBUTION

% Filterable
% Condensible
      88.37
      11.63
 97.29
  2.71
 64.17
 35.83
 83.28
 16.72
PARTICULATE EMISSIONS

Concentration - gr/dscf
Mass Rate - Ib/hr
     0.0155
       2.24
0.0139
  2.05
0.0266
  4.12
0.0187
  2.80
CO EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr
     259.80
      19.09
385.83
 28.91
337.84
 26.67
327.82
 24.89
NOx EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr  (as NO2)
      15.33
       1.85
 24.09
  2.96
 22.40
  2.90
 20.61
  2.57
                                           47

-------
TABLE 3.4.2-6:
SUMMARY OF PM,n AND M202 RESULTS: SAWDUST DRYER  OUTLET
                                                                      B.
RUN I.D.
DATE
TIME STARTED
TIME ENDED

SAMPLING PARAMETERS

Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics
D50

GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
           OB-M201A-R1 OB-M201A-R2 OB-M201A-R3
              11/03/92    11/04/92    11/04/92
                 16:54       10:15       14:12
                 19:24       12:55       16:41
                                                                AVERAGE
                45.427
                44.870
                 114.1
                  94.3
                  9.61
                 176.2
                 17.08
                  3.41
                 11.19
65.889
66.492
 146.7
 108.6
  8.84
 178.5
 17.08
  3.36
  9.37
50.230
50.122
 127.9
  92.8
  9.62
 179.2
 17.12
  3.40
 11.02
53.849
53.828
129.57
  98.6
  9.36
 178.0
 17.09
  3.39
 10.53
GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
                 45.78
                 25181
                 18067
 45.18
 24852
 18081
 46.90
 25801
 18311
 45.95
 25278
 18153
PM DISTRIBUTION

% Filterable
% Condensible
                 83.25
                 16.75
 90.02
  9.98
 84.73
 15.27
 86.00
 14.00
PARTICULATE EMISSIONS

Concentration - gr/dscf
Mass Rate - Ib/hr
                0.0196
                  3.04
0.0124
  1.91
0.0170
  2.67
0.0163
  2.54
CO EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr
                338.85
                 26.70
375.25
 29.59
367.27
 29.33
360.46
 28.54
NOx EMISSIONS
Cone. - ppmdv                   19.04       20.29
Mass Rate - Ib/hr (as NO2)        2.46        2.63
                                         22.97
                                          3.01
                       20.77
                         2.70
                                          48

-------
TABLE 3.4.2-9:  SUMMARY  OF TOTAL FLUORIDE  SAMPLING:  EPA METHOD 13B:  SAWDUST DRYER INLET
RUN NUMBER
DATE
IN-M13-R1  IN-M13-R2  IN-M13-R3  AVERAGE
 10/29/92   10/29/92   10/30/92
SAMPLING DATA

Metered Volume  -  cf         130.045
Corrected Vol.  -  dscf       124.192
Total Teat Time - min           120
% Isokinetic                   90.0
             101.348     97.560  109.651
              97.313     94.436  105.313
                 120        120      120
                96.6       94.2     93.6
GAS PARAMETERS

Gas Temperature  -  oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
      451
     18.3
      3.0
      5.3
   412
  18.3
   3.0
   5.4
   451
  18.3
   3.0
   5.0
   438
  18.3
   3.0
   5.2
GAS FLOWRATE

Velocity - ft/sec             46.68       46.57
Actual Volume - acfm          44545       44440
Standard Volume - dscfm      23861       25090
                          48.84    47.36
                          46609    45198
                          24948    24633
FLUORIDE EMISSIONS

Concentration - mg/1
Sample Vol. - ml
Cone.  - ppmdv
Cone.  - ppmdv @ 7% O2
Mass Rate - Ib/hr
      1.8
   1043.1
     0.68
     3.61
    0.048
   6.5
1329.1
  3.97
 21.22
 0.295
  73.8
1259.3
 44.00
235.25
 3.248
  27.4
1210.5
 16.22
 86.70
 1.197
Notes:       Sample values for 2-M13-LOCE and  2A-M13-LOCE  were  combined for IN-M13-R2.

            Sample values for 3-M13-LOCE and  3A-M13-LOCE  were  combined for IN-M13-R3.
                                         49

-------
TABLE 3.4.2-10;
      SUMMARY  OF  TOTAL FLUORIDE SAMPLING:  EPA  METHOD  13B:  SARI
      DRYER OUTLET A.
RUN NUMBER
DATE
             OA-M13-R1  OA-M13-R2  OA-M13-R3
              10/29/92    10/29/92    10/30/92
                                                           AVERAGE
SAMPLING DATA

Metered Volume - cf        104.366     78.196
Corrected Vol. - dscf      105.663     80.150
Total Test Time - min          120        120
% Isokinetic                  75.4       94.7
                                      85.682
                                      87.015
                                         120
                                       105.9
                    89.415
                    90.943
                       120
                      92.0
GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
                   149
                  19.1
                   2.2
                  6.15
  141
 19.1
  2.2
 8.05
   155
  19.1
   2.2
 10.32
  148
 19.1
  2.2
 8.17
GAS FLOWRATE

Velocity - ft/sec            72.81      43.40      43.13     53.11
Actual Volume - acfm         42033      25052      24897     30661
Standard Volume - dscfm      32995      19911      19339     24082
FLUORIDE EMISSIONS

Concentration  - mg/1
Sample Volume  - ml.
Cone. - ppmdv
Cone. - ppmdv  @ 7% O2
Mass Rate -  Ib/hr
                   8.4
                 883.9
                  3.14
                 24.26
                 0.307
  8.0
657.1
 2.93
22.65
0.173
  13.6
1310.3
  9.16
 70.71
 0.524
 10.0
950.4
 5.08
39.21
0.334
 Note:
Sample values for 3-M13-LOCF1 and 3A-M13-LOCF1 were combined  for  OA- •
                                          50

-------
TABLE 3.4.2-11: HF DATA AND  RESULTS:  EPA METHOD  26:  SAWDUST  DRYER INLET.
RUN NUMBER
DATE
START TIME
END TIME
IN-M26-R1
 11/02/92
    13:11
    15:28
IN-M26-R2
 11/02/92
    17:33
    19:42
IN-M26-R3
 11/03/92
    09:15
    11:32
                                      AVERAGE
SAMPLING DATA

Initial Meter Volume  -  1       2158.380    2289.670     2411.150    2286.400
Final Meter Volume -  1         2278.440    2409.690     2531.190    2406.440
Net Meter Volume - 1            120.060     120.020      120.040     120.040
Average Meter Temp. - F           77.4        79.4         80.0        78.9
Barometric Pres. - in.Hg          29.48       29.57        29.72       29.59
Avg. Meter Pres. -in.W.C.          1.0         1.0          1.0         1.0
Meter Cal. Factor - Gamma        1.0047      1.0047       1.0047
Corr. Meter Volume -  dscf         4.132       4.128        4.145       4.135
Oxygen - %dv                      15.22       14.46        15.59       15.09
GAS FLOWRATE DATA

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
    54.90
    52390
    27292
    55.55
    53009
    27249
    51.22
    48878
    25509
  53.89
  51426
  26683
LABORATORY DATA

Fluoride Analysis
 Total Liquid Volume  -  ml
 Floride Cone. - mg/liter
     40.0
    252.0
     40.0
    300.0
     33.0
    127.0
   37.7
  226.3
HF EMISSIONS

Concentration - ppmdv
Cone. - ppmdv @ 7% O2
Mass Rate - Ib/hr
  109.071
  266.916
    9.275
  129.977
  280.540
   11.036
   45.209
  118.343
    3.593
 94.752
221.933
  7.968
                                            51

-------
TABLE 3.4.2-12: HF DATA AND RESULTS: EPA METHOD 26: SAWDUST DRYER OUTLET A.
RUN NUMBER
DATE
START TIME
END TIME
                             OA-M26-R1
                              11/02/92
                                 13:11
                                 15:28
OA-M26-R2
 11/02/92
    17:33
    19:42
OA-M26-R3
 11/03/92
    09:15
    11:32
                                                                   AVERAGE
SAMPLING DATA

Initial Meter Volume - 1       211.050     457.060     716.460
Final Meter Volume - 1         453.850     714.760    1092.400
Net Meter Volume - 1           242.800     257.700     375.940
Average Meter Temp. - F           64.3        65.3        68.0
Barometric Pres. - in.Hg         29.46       29.57       29.72
Avg. Meter Pres. - in.W.C.         1.0         1.0         1.0
Meter Cal. Factor - Gamma       1.0007      1.0007      1.0007
Corr. Meter Volume - dscf        8.525       9.065      13.225
Oxygen - %dv                     16.79       16.65       17.76
                                                                    292.147
                                                                          ^
                                                                          n
                                                                        1.0

                                                                     10.272
                                                                      17.07
GAS FLOWRATE DATA

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
                                 42.15
                                 23185
                                 17478
    41.12
    22622
    16774
    41.96
    23081
    17029
 41.74
 22963
 17094
LABORATORY DATA

Fluoride Analysis
 Total Liguid Volume - ml
 Fluoride Cone. - mg/liter
                                  40.0
                                 105.0
     40.0
    300.0
     40.0
     45.8
  40.0
 150.3
HF EMISSIONS

Concentration - ppmdv
Cone. - ppmdv @ 7% O2
Mass Rate - Ib/hr
                                22.028
                                74.499
                                 1.200
   59.190
  193.587
    3.094
    6.194
   27.420
    0.329
29.138
98.502
 1.541
                                          52

-------
TABLE 3.4.2-13: HF  DATA AND RESULTS:  EPA METHOD  26:  SAWDUST DRYER OUTLET  B
RUN NUMBER
DATE
START TIME
END TIME
OB-M26-R1
 11/02/92
    13:11
    15:28
OB-M26-R2
 11/02/92
    17:33
    19:42
OB-M26-R3
 11/03/92
    09:15
    11:32
AVERAGE
SAMPLING DATA

Initial Meter Volume  -
Final Meter Volume -
Net Meter Volume -
Average Meter Temp
Barometric Pres. -
Avg. Meter Pres. -
Meter Cal. Factor
Corr. Meter Volume
Oxygen - %dv
ie - 1
- 1
1
- F
in.Hg
in.W.C.
Gamma
- dscf

455.560
702.150
246.590
73.2
29.48
1.0
1.0009
8.521
16.81
703.230
956.900
253.670
75.7
29.57
1.0
1.0009
8.753
16.64
955.120
1198.630
243.510
85.6
29.72
1.0
1.0009
8.291
16.91
704.637
952.560
247.923
78.2
29.59
1.0

8.522
16.79
GAS FLOWRATE DATA

Velocity - ft/sec
Actual Volume -  acfm
Standard Volume  - dscfm
    35.79
    19690
    15377
    38.62
    21243
    15734
    38.55
    21209
    16346
  37.65
  20714
  15819
LABORATORY DATA

Fluoride Analysis
 Total Liquid Volume  -  ml
 Fluoride Cone.  - mg/liter
     40.0
      1.4
     40.0
    238.0
     40.0
    200.0
   40.0
  146.5
HF EMISSIONS

Concentration  - ppmdv
Cone. - ppmdv  @ 7% O2
Mass Rate - Ib/hr
    0.294
    0.999
    0.014
   48.635
  158.691
    2.384
   43.145
  150.304
    2.197
 30.691
103.331
  1.532
                                          53

-------
TABLE  3.4.2-14;
RUN I.D.
DATE
TIME STARTED
TIME ENDED
SUMMARY OF  VOLATILE  ORGANICS EMISSIONS:  METHOD  0030:  SAWDUST
DRYER  INLET.
           IN-VST-R1
             11/06/92
                11:37
                15:05
IN-VST-R2
 11/06/92
     17:42
     20:47
IN-VST-R3
 11/07/92
     09:02
     12:27
                                                                           AVERAGE
VOLATILE ORGANIC EMISSIONS  - Ib/hr
Acetone
Aerylonitrile
Benzene
Bromomethane
2-butanone
Carbon  Disulfide
Carbon  Tetrachloride
Chloroform
Chloromethane
Ethylbenzene
2-Hexanone
lodomethane
Methylene Chloride
M-/p-xylene
O-xylene
Styrene
Tetrachloroethane
Toluene
1,1,1-trichloroethane
Trichloroethene
Trichlorofluoromethane
Vinyl Acetate
3
4
9
5
3
2
4
4
1
2
4
2
1
4
1
4
4
2
4
4
1
4
.94E-03
.43E-04 «
.60E-03
.62E-04
.23E-04 «
.66E-04
.94E-06 «
.94E-06 <
.50E-02
.20E-04
.94E-06 «
.66E-03
.72E-04
.23E-04
.39E-04 *
.94E-06 <
.94E-06 <
.05E-03
.94E-06 <
.94E-06 «
.17E-04
.94E-06 <
2.
: 3.
9.
7.
c 5.
3.
: 5.
: 5.
1.
1.
: 5.
3.
6.
1.
: 5.
c 1.
: 5.
1.
' 5.
: 5.
7.
C 5.
79E-03
46E-04 <
50E-03
44E-04
05E-06 «
32E-04
05E-06 <
05E-06 «
68E-02
07E-04
05E-06 <
64E-03
90E-05
85E-04
97E-05
17E-05 <
05E-06 •
08E-03
05E-06 «
05E-06 <
75E-05
05E-06 «
1.
c 3.
6.
1.
c 5.
2.
c 5.
c 5.
2.
1.
: 5.
3.
1.
8.
9.
: 5.
: 5.
2.
: 5.
c 5.
9.
: 5.
29E-02
OOE-04
70E-03
19E-03
13E-06
15E-04
13E-06
13E-06
30E-03
OOE-04
13E-06
88E-03
33E-04
35E-04
OOE-05
13E-06
13E-06
14E-03
13E-06
13E-06
50E-05
13E-06
6
<3
8
8
<1
2
<5
<5
1
1
<5
3
1
4
9
<7
<5
1
<5
<5
9
<5
.55E-03
.63E-04
.60E-03
.32E-04
.11E-04
.71E-04
.04E-06
.04E-06
.14E-02
.42E-04
.04E-06
.39E-03
.25E-04
.81E-04
.64E-05
.27E-06
.04E-06
.75E-03
.04E-06
.04E-06
.64E-05
.04E-06
Notes:
               Emission values for IN-VST-R1 represent the average of  five separate vost tube analyses.  Sample IN-
               M0030-R1D was lost due to  laboratory computer failure (see Appendix G.5 case narrative accompanying
               laboratory data report).   Emission values for runs IN-VST-R2 and IN-VST-R3 represent the  averages of six
               separate vost tube analyses.  See Appendix B.6.1 for more detailed test results.

               All  VOST tubes were analyzed in tandem according to the guidelines of Methods 8240 and 5040.  The
               response factors used are  the average response factors  from the initial calibration.  Amounts reported
               for  target compounds that  are not detected are denoted  as < 0.001.  The reported laboratory values for
               non-detected target compounds are calculated using an area of 20 counts.

               The  acquisitions for samples OB-M0030-R1B and 1N-M0030-R1D were lost due to laboratory computer failure.

               Alt  field samples were observed to contain condensation within the Tenax and Tenax-charcoal tubes prior
               to analysis.  Saturation of target analytes or TICs may have inhibited target analyte recoveries. All
               saturated compounds should be considered underestimated and may interfere with the detection or
               quantisation of target analytes.

               Compounds found in the field samples at levels  less than five times the amount found in the associated
               blank  should not be considered native to the samples.  The majority of the samples had one or more
               compounds at levels over the calibration range.  This occurrence is identified with an '£'  label, these
               quantitations should be considered estimates.

               Ketone results for VOST matrices should be considered semi-quantitative as these compounds often
               experience erratic recovery from VOST.

               See  case narrative accompanying the volatile organics laboratory data, Appendix G.5, for additional
               information.
                                                     54

-------
TABLE 3.4.2-15:
                      SUMMARY  OF VOLATILE ORGANICS  EMISSIONS:  METHOD 0030:
                      SAWDUST  DRYER  OUTLET A
RUN  I.D.
DATE
TIME STARTED
TIME ENDED
OA-VST-R1
 11/06/92
     11:47
     16:38
              OA-VST-R2
                11/06/92
                   17:34
                   21:42
                           OA-VST-R3
                             11/07/92
                                09:02
                                12:47
                                         AVERAGE
VOLATILE  ORGANIC  EMISSIONS  - Ib/hr
Acetone
Aerylonitrile
Benzene
Bromomethane
2-butanone
Carbon Disulfide
Carbon Tetrachloride
Chloroform
Chloromethane
Ethylbenzene
2-Hexanone
lodomethane
Methylene Chloride
M-/p-xylene
0-xylene
Styrene
Tetrachloroethane
Toluene
1,1,1-trichloroethane
Trichloroethene
Trichlorofluoromethane
Vinyl Acetate
   5.96E-03
<  7
    .39E-05
  3.87E-03
  3.27E-04
  1.03E-03
  1.07E-04
6.15E-03
1.48E-04
4.24E-03
3.38E-04
6.53E-04
1.35E-04
< 3.30E-06 < 3.25E-06 <
                            1.09E-02    7.67E-03
                            2.18E-04 <  1.46E-04
                            4.12E-03    4.08E-03
                            4.70E-04    3.78E-04
                            4.79E-03 <  2.16E-03
                            1.50E-04    1.31E-04
                            3.33E-06 <  3.29E-06
< 3
8
8
< 3
1
2
4
7
< 3
< 3
3
< 1
< 3
< 1
< 3
.30E-06
.41E-03
. 16E-05
.30E-06
.55E-03
.59E-04
. 64E-04
.60E-05
.30E-06
.30E-06
.91E-03
.89E-05
.30E-06
.51E-04
.30E-06
< 3
1
6
< 3
1
1
1
4
< 3
< 3
4
< 3
< 3
< 9
< 3
.25E-06
.12E-02
.73E-05
.25E-06
.83E-03
.76E-03
.68E-04
.77E-05
.25E-06
.25E-06
.OOE-03
.25E-06
.25E-06
. 15E-05
.25E-06
<


<




<
<

<
<

<
3
1
1
3
2
4
2
7
9
3
3
3
3
1
3
.33E-06
.16E-02
.10E-04
.33E-06
.07E-03
.41E-04
.56E-04
.56E-05
.28E-06
.33E-06
.82E-03
.33E-06
.33E-06
.56E-04
.33E-06
<


<




<
<

<
<
<
<
3
1
8
3
1
8
2
6
5
3
3
8
3
1
3
.29E-06
.04E-02
.63E-05
.29E-06
. 81E-03
. 19E-04
.96E-04
.64E-05
.28E-06
.29E-06
.91E-03
. 50E-06
.29E-06
.33E-04
.29E-06
Notes:
              The emission values for each  run represent  the average of  six separate vost tube analyses.  See Appendix
              B.6.2 for more detailed test  results.

              All VOST tubes were analyzed  in tandem according to the guidelines of Methods 8240 and 5040.  The
              response factors used are the average response factors from the initial calibration.  Amounts reported
              for target compounds that are not detected  are denoted as  < 0.001.  The reported laboratory values for
              non-detected target compounds are calculated using an area of 20 counts.

              The acquisitions for samples  OB-M0030-R1B and IN-M0030-R1D were lost due to laboratory computer failure.

              All field samples were observed to contain  condensation within the Tenax and Tenax-charcoal tubes prior
              to analysis. Saturation of target analytes or TICs may have inhibited target analyte recoveries.  All
              saturated compounds should be considered underestimated and may interfere with the detection or
              quantitation of target analytes.

              Compounds found in the field  samples at levels less than five times the amount found in the associated
              blank should not be considered native to the samples.  The majority of the samples had one or more
              compounds at levels over the  calibration range.   This occurrence is identified with an 'E' label, these
              quantitations should be considered estimates.

              Ketone results for VOST matrices should be  considered semi-quantitative as these compounds often
              experience erratic recovery from VOST.

              See case narrative accompanying the volatile organics laboratory data. Appendix G.5, for additional
              information.
                                                  55

-------
TABLE  3.4.2-16:
        SUMMARY OF VOLATILE ORGANICS  EMISSIONS: METHOD C03C
        SAWDUST DRYER OUTLET  B
RUN I.D.
DATE
TIME  STARTED
TIME  ENDED
                   OB-VST-R1
                    11/06/92
                        11:47
                        16:37
OB-VST-R2
 11/06/92
     17:32
     21:46
OB-VST-R3
 11/07/92
     09:05
     12:45
                                                                           AVERAGE
VOLATILE ORGANIC EMISSIONS  - Ib/hr
Acetone
Acrylonitrile
Benzene
Bromomethane
2-butanone
Carbon  Disulfide
Carbon  Tetrachloride
Chloroform
Chloromethane
Ethylbenzene
2-Hexanone
lodomethane
Methylene Chloride
M-/p-xylene
O-xylene
Styrene
Tetrachloroethane
Toluene
1,1,1-trichloroethane
Trichloroethene
Trichlorofluoromethane
Vinyl Acetate
9
2
6
4
1
1
3
3
1
1
3
2
2
2
7
8
3
3
3
3
1
3
.61E-03
.21E-04 <
.12E-03
.35E-04 «
.44E-03 «
.80E-04
.10E-06 «
.10E-06 «
.29E-02
.19E-04
.10E-06 <
.19E-03
.07E-04
.26E-04
.16E-05
.52E-05 <
.10E-06 <
.52E-03
.10E-06 «
.10E-06 «
.05E-04 <
.10E-06 <
9
: 2
4
c 3
c 1
1
c 3
c 3
1
6
c 3
2
3
1
4
c 1
c 3
2
c 1
c 3
c 5
: 3
.
^
f
f
f
•
•
m
•
•
.
•
m
w
•
^
^
^
^
^
^
w
47E-03
03E-04
99E-03
73E-04
59E-03
63E-04
09E-06 <
09E-06 <
02E-02
89E-05
09E-06 <
17E-03
45E-04
47E-04
65E-05
04E-04 <
09E-06 <
93E-03
19E-05 <
09E-06 <
84E-05
09E-06 <
9
2
4
4
2
1
2
2
1
6
2
2
6
1
4
2
2
3
2
2
8
2
.
.
.
.
,
•
*
•
.
a
^
^
.
,
•
•
^
^
B
B
^
f
83E-03
13E-04
59E-03
69E-04
60E-03
81E-04
87E-06
87E-06
35E-02
OOE-05
87E-06
41E-03
79E-05
66E-04
56E-05
62E-05
87E-06
44E-03
87E-06
87E-06
71E-05
87E-06
9
<2
5
<4
<1
1
<3
<3
1
8
<3
2
2
1
5
<7
<3
3
<5
<3
<8
<3
.64E-03
.12E-04
.23E-03
.26E-04
.88E-03
.75E-04
.02E-06
.02E-06
.22E-02
.27E-05
.02E-06
.26E-03
.07E-04
.80E-04
.46E-05
.18E-05
.02E-06
.30E-03
.97E-06
.02E-06
.35E-05
.02E-06
Notes:
Emission values  for OB-VST-R1 represent the average of  five separate vost tube analyses.  Sample OB-
M0030-R1D was lost due to  laboratory computer failure (see Appendix G.5 case narrative accompanying
laboratory data  report).   Emission values for runs IN-VST-R2 and  IN-VST-R3 represent the averages of six
separate vost tube analyses.  See Appendix B.6.1 for more detailed test results.

All VOST tubes were analyzed in tandem according to the guidelines of Methods 8240 and 5040.  The
response factors used are  the average response factors  from the initial calibration.  Amounts reported
for target compounds that  are not detected are denoted  as < 0.001.  The reported laboratory values for
non-detected target compounds are calculated using an area of 20  counts.

The acquisitions for samples OB-M0030-R1B and IN-M0030-R1D were lost due to laboratory computer failure.

All field samples were observed to contain condensation within the Tenax and Tenax-charcoal tubes prior
to analysis.  Saturation of target analytes or TICs may have inhibited target analyte recoveries.  AH
saturated compounds should be considered underestimated and may interfere with the detection or
quantisation of  target analytes.

Compounds found  in the field samples at levels less than five times the amount found in the associated
blank should not be considered native to the samples.  The majority of the samples had one or more
compounds at levels over the calibration range.  This occurrence  is identified with an '£'  label, these
quantitations should be considered estimates.

Ketone results for VOST matrices should be considered semi-quantitative as these compounds often
experience erratic recovery from VOST.

See case narrative accompanying the volatile organics laboratory  data. Appendix G.5, for additional
information.
                                                     56

-------
TABLE 3.4.2-17:
SUMMARY OF EMISSIONS FOR SEMIVOLATILE COMPOUNDS:  METHOD 0010:
SAWDUST DRYER INLET
RUN I.D.
DATE
TIME STARTED
TIME ENDED

SAMPLING PARAMETERS

Metered Volume -  dcf
Corrected Volume  - dscf
Total Test Time - min
% Isokinetics

GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide -  %
Moisture - %

GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm

SEMIVOLATILE EMISSIONS (Ib/hr)

Bis(2-ethyIhexy)phthalate
Dibenzofuran
Dimethylphthalate
Di-n-butylphthalate
2-methylphenol
Naphthalene
Phenol

CO  EMISSIONS

Cone. - ppmdv
Mass Rate -  Ib/hr

NOx EMISSIONS

Cone. - ppmdv
Mass Rate -  Ib/hr (as NO2)
            IN-M0010-R1  IN-M0010-R2  IN-M0010-R3  AVERAGE
                11/06/92     11/06/92     11/07/92
                   11:37        17:42        09:02
                   15:19        21:02        13:12
104.311
105.646
180
101.5
502.3
16.42
4.5
5.60
54.94
52427
26998
6.49E-04
5.81E-04
< 3.38E-08 <
< 3.38E-08
< 3.38E-08 <
1.71E-02 <
< 3.38E-08
433.13
51.00
39.36
7.61
105.158
108.272
180
100.4
494.8
16.0
4.3
4.43
55.78
53228
27968
4.68E-04
1.73E-04 <
3.42E-08
3.04E-04 <
3.42E-08 <
3.42E-08 <
3.18E-03
474.74
57.91
26.47
5.30
108.266
111.242
180
100.8
498.5
16.3
4.4
5.79
57.83
55184
28623
3.13E-04
3.40E-08
5.10E-04
3.40E-08
3.40E-08
3.40E-08
4.36E-04
493.83
61.65
32.00
6.56
105.912
108.387
180
100.9
498.6
16.3
4.4
5.27
56.18
53613
27863
4.77E-04
<2.51E-04
<1.70E-04
<1.01E-04
<3.40E-08
<5.70E-03
<1.20E-03
467.23
56.86
32.61
6.49
                                            57

-------
TABLE 3.4.2-18:
                  SUMMARY OF EMISSIONS FOR SEMIVOLATILE COMPOUNDS:  METHOD 0010:
                  SAWDUST DRYER OUTLET A
RUN I.D.
DATE
TIME STARTED
TIME ENDED

SAMPLING PARAMETERS

Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics

GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %

GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
SEMIVOLATILE EMISSIONS  (Ib/hr)

Bis(2-ethylhexy)phthalate
Dibenzofuran                 <
Dimethylphthalate            <
Di-n-butylphthalate
2-methylphenol               <
Naphthalene                  <
Phenol                       <

CO EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr

NOx EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr (as NO2)
                             OA-M0010-R1 OA-M0010-R2 OA-MOO10-P.3
                                11/06/92    11/06/92     11/07/92
                                   11:37       17:32        09:02
                                   15:19       21:02        13:12
                                                                    AVERAGE
120.273
120.642
180
102.0
185.7
16.97
3.5
9.67
44.93
24718
17689
3.44E-04 <
1.94E-08 <
1.94E-08 <
3.63E-04 <
1.94E-08 <
1.94E-08 <
1.94E-08
325.22
25.09
23.78
3.01
120.553
121.676
180
103.6
185.5
17.2
3.4
10.51
45.00
24755
17558
1.91E-08
1.91E-08 <
1.91E-08 <
1.91E-08
1.91E-08 <
1.91E-08 <
1.33E-03
353.45
27.07
24.11
3.03
121.899
123.588
180
103.1
186.0
17.2
3.4
9.51
45.21
24869
17918
3.21E-04 <
1.92E-08 <
1.92E-08 <
1.28E-04 <
1.92E-08 <
1.92E-08 <
1.59E-03 <
349.82
27.34
23.24
2.98
120.908
121.969
180
102.9
185.7
17.1
3.4
9.90
45.05
24781
17722
2.21E-04
1.92E-08
1.92E-08
1.64E-04
1.92E-08
1.92E-08
9.74E-04
342.83
26.50
23.71
3.01
                                           58

-------
TABLE 3.4.2-19:
SUMMARY OF EMISSIONS FOR SEMIVOLATILE COMPOUNDS: METHOD 0010:
SAWDUST DRYER OUTLET B
RUN I.D.
DATE
TIME STARTED
TIME ENDED

SAMPLING PARAMETERS

Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics

GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %

GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm

SEMIVOLATILE EMISSIONS

Bis(2-ethylhexy)phthalate
Dibenzofuran
Dimethylphthalate
Di-n-butylphthalate
2-methylphenol
Naphthalene
Phenol

CO EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr

NOx EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr (as NO2)
OB-MOO 10-R1 OB-MOO 10-R2 OB-MOO 10-R3
11/06/92 11/06/92 11/07/92
11:37 17:32 09:02
15:19 21:02 13:12
110.613
111.720
180
98.9
181.9
17.19
3.3
6.46
41.11
22612
16895
(Ib/hr)
te 8.94E-04
< 2.00E-08 <
< 2.00E-08 <
3.82E-05
< 2.00E-08 <
< 2.00E-08 <
5.86E-04
313.89
23.13
24.84
0,) 3.01
113.298
115.140
180
101.5
182.3
17.5
3.2
8.46
42.17
23200
16954

4.49E-03
1.95E-08 <
1.95E-08 <
8.63E-05
1.95E-08 <
1.95E-08 <
9.24E-04
341.50
25.25
21.78
2.65
107.111
109.810
180
103.8
182.3
17.3
3.2
8.05
38.98
21443
15821

9.08E-04
1.91E-08 <
1.91E-08 <
1.75E-04
1.91E-08 <
1.91E-08 <
7.67E-04
338.45
23.35
20.58
2.33
AVERAGE
110.341
112.223
180
101.4
182.2
17.3
3.2
7.65
40.75
22419
16557

2.10E-03
1.95E-08
1.95E-08
9.98E-05
1.95E-08
1.95E-08
7.59E-04
331.28
23.91
22.40
2.66
                                           59

-------
TABLE 3.4.2-20:
SUMMARY OF TOTAL HYDROCARBONS EMISSIONS:  EPA METHOD
SAWDUST DRYER INLET
RUN I.D.
DATE
TIME STARTED
TIME ENDED
         IN-M25A-R1  IN-M25A-R2  IN-M25A-R3
           11/06/92    11/06/92    11/07/92
              11:37       17:42       09:02
              15:19       21:02       13:12
                                                                AVERAGE
SAMPLING PARAMETERS

Metered Volume - dcf          104.311     105.158     108.266   105.912
Corrected Volume - dscf       105.646     108.272     111.242   108.387
Total Test Time - min             180         180         ISO       180
% Isokinetics                   101.5       100.4       100.8     100.9
GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
              502.3
              16.42
                4.5
               5.60
 494.8
  16.0
   4.3
  4.43
 498.5
  16.3
   4.4
  5.79
 498.6
  16.3
   4.4
  5.27
GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
              54.94
              52427
              26998
 55.78
 53228
 27968
 57.83
 55184
 28623
 56.18
 53613
 27863
CO EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr
             433.13
              51.00
474.74
 57.91
493.83
 61.65
467.23
 56.86
NOx EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr  (as NO2)
              39.36
               7.61
 26.47
  5.30
 32.00
  6.56
 32.61
  6.49
THC EMISSIONS

Cone. - ppmwv  (as Propane)       4.49
Cone. - ppmdv  (as Propane)       4.76
Cone. - ppmdv  (as Carbon)       14.27
Mass Rate -  Ib/hr (as Carbon)    0.72
                           4.85
                           5.07
                          15.22
                           0.80
              4.78
              5.07
             15.22
              0.81
            4.71
            4.97
           14.90
            0.78
 (*)  Gas  flowrate  data was taken  from  IN-M0010-R1,R2,  and R3,  respectively.
                                          60

-------
TABLE 3.4.2-21:
                  SUMMARY OF  TOTAL  HYDROCARBONS EMISSIONS:  EPA  METHOD  25A;
                  SAWDUST DRYER OUTLET A
RUN I.D.
DATE
TIME STARTED
TIME ENDED
OA-M25A-R1  OA-M25A-R2  OA-M25A-R3
  11/06/92    11/06/92    11/07/92
     11:37       17:32       09:02
     15:19       21:02       13:12
                                     AVERAGE
SAMPLING PARAMETERS

Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics
   120.273
   120.642
       180
     102.0
120.553
121.676
    180
  103.6
121.899
123.588
    180
  103.1
120.908
121.969
    180
  102.9
GAS PARAMETERS
Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
     185.7
     16.97
       3.5
      9.67
  185.5
   17.2
    3.4
  10.51
  186.0
   17.2
    3.4
   9.51
  185.7
   17.1
    3.4
   9.90
GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
     44.93
     24718
     17689
  45.00
  24755
  17558
  45.21
  24869
  17918
  45.05
  24781
  17722
 CO EMISSIONS

 Cone. - ppmdv
 Mass Rate - Ib/hr
    325.22
     25.09
 353.45
  27.07
 349.82
  27.34
 342.83
  26.50
NOx EMISSIONS
 Cone. - ppmdv                    23.78       24.11
 Mass Rate -  Ib/hr  (as  NO2)        3.01        3.03
                             23.24
                              2.98
                        23.71
                         3.01
 THC EMISSIONS

 Cone. - ppmwv  (as Propane)        2.67        17.86
 Cone. - ppmdv  (as Propane)        2.96        19.96
 Cone. - ppmdv  (as Carbon)         8.87        59.87
 Mass Rate - Ib/hr (as  Carbon)     0.29         1.97
                             20.34
                             22.48
                             67.43
                              2.26
                        13.62
                        15.13
                        45.39
                         1.51
 (*) Gas flowrate  data was taken from OA-M0010-R1,R2,  and R3,  respectively.
                                           61

-------
TABLE 3.4.2-22:
SUMMARY OF TOTAL HYDROCARBONS EMISSIONS: EPA METHOD 252\
SAWDUST DRYER OUTLET B
RUN I.D.
DATE
TIME STARTED
TIME ENDED
         OB-M25A-R1
           11/06/92
              11:37
              15:19
OB-M25A-R2
  11/06/92
     17:32
     21:02
OB-M25A-R3
  11/07/92
     09:02
     13:12
                                                                AVERAGE
SAMPLING PARAMETERS

Metered Volume - dcf
Corrected Volume - dscf
Total Test Time - min
% Isokinetics
            110.613
            111.720
                180
               98.9
   113.298
   115.140
       180
     101.5
   107.111
   109.810
       180
     103.8
110.341
112.223
    180
  101.4
GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
              181.9
              17.19
                3.3
               6.46
     182.3
      17.5
       3.2
      8.46
     182.3
      17.3
       3.2
      8.05
  182.2
   17.3
    3.2
   7.65
GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
              41.11
              22612
              16895
     42.17
     23200
     16954
     38.98
     21443
     15821
  40.75
  22419
  16557
CO EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr
             313.89
              23.13
    341.50
     25.25
    338.45
     23.35
 331.28
  23.91
NOx EMISSIONS

Cone. - ppmdv
Mass Rate - Ib/hr  (as NO2)
              24.84
               3.01
     21.78
      2.65
     20.58
      2.33
  22.40
   2.66
THC EMISSIONS

Cone. - ppmwv  (as Propane)       9.70        7.57
Cone. - ppmdv  (as Propane)       10.37        8.27
Cone. - ppmdv  (as Carbon)        31.11       24.81
Mass Rate - Ib/hr (as Carbon)    0.98        0.79
                                      12.87
                                      14.00
                                      41.99
                                        1.24
                            10.05
                            10.88
                            32.64
                             1.00
 (*) Gas flowrate data was  taken from OB-M0010-R1,R2,  and R3,  respectively.
                                          62

-------
TABLE 3.4.2-23:
                  SUMMARY OF ETHANE AND METHANE EMISSIONS: EPA METHOD  18:
                  SAWDUST DRYER INLET
RUN I.D.
DATE
TIME STARTED
TIME ENDED
IN-M18-R1
 11/06/92
    11:37
    15:19
11/06/92
   17:42
   21:02
IN-M18-R3
 11/07/92
    09:02
    13:12
                        AVERAGE
GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
    502.3
    16.42
      4.5
     5.60
   494.8
    16.0
     4.3
    4.43
    498.5
     16.3
      4.4
     5.79
  498.6
   16.3
    4.4
   5.27
GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
    54.94
    52427
    26998
   55.78
   53228
   27968
    57.83
    55184
    28623
  56.18
  53613
  27863
ETHANE EMISSIONS

Cone. - ug/ml
Cone. - ppm
Cone. - mg/m3
Mass Rate - Ib/hr
 <  0.050
 < 40.012
 < 50.000
 <  5.056
<  0.050
< 40.012
< 50.000
<  5.238
 <  0.050
 < 40.012
 < 50.000
 <  5.361
< 0.050
<40.012
<50.000
< 5.218
METHANE EMISSIONS

Cone. - ug/ml
Cone. - ppm
Cone. - mg/m3
Mass Rate - Ib/hr
 <  0.101     <  0.101     <  0.101  <  0.101
 <151.469     <151.469     <151.469  <151.469
 <101.000     <101.000     <101.000  <101.000
 < 10.214     < 10.581     < 10.829  < 10.541
(*) Gas flowrate data was taken from IN-M0010-R1,R2, and R3, respectively.
                                        63

-------
TABLE 3.4.2-24:
SUMMARY OF ETHANE AND METHANE EMISSIONS:  EPA METHOD 13:
SAWDUST DRYER OUTLET A
RUN I.D.
DATE
TIME STARTED
TIME ENDED
        OA-M18-R1
         11/06/92
            11:37
            15:19
OA-M18-R2
 11/06/92
    17:32
    21:02
OA-M18-R3
 11/07/92
    09:02
    13:12
                                                                 AVERAGE
GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
            185.7
            16.97
              3.5
             9.67
    185.5
     17.2
      3.4
    10.51
    186.0
     17.2
      3.4
     9.51
  185.7
   17.1
    3.4
   9.90
GAS FLOWRATE

Velocity - ft/sec             44.93
Actual Volume - acfm          24718
Standard Volume - dscfm       17689
                         45.00
                         24755
                         17558
                 45.21
                 24869
                 17918
               45.05
               24781
               17722
ETHANE EMISSIONS

Cone. - ug/ml
Cone. - ppm
Cone. - mg/m3
Mass Rate - Ib/hr
         <  0.050
         < 40.012
         < 50.000
         <  3.313
 <  0.050
 < 40.012
 < 50.000
 <  3.288
 <  0.050
 < 40.012
 < 50.000
 <  3.356
< 0.050
<40.012
<50.000
< 3.319
METHANE EMISSIONS

Cone. - ug/ml
Cone. - ppm
Cone. - mg/m3
Mass Rate - Ib/hr
         <  0.101        6.150     <  0.101  <   2.117
         <151.469     9223.083     <151.469  <3175.340
         <101.000     6150.000     <101.000  <2117.333
         <  6.692      404.468     <  6.779  < 139.313
(*) Gas flowrate data was taken from OA-M0010-R1,R2, and R3, respectively.
                                          64

-------
TABLE 3.4.2-25:
                  SUMMARY OF ETHANE AND METHANE EMISSIONS:  EPA  METHOD 18:
                  SAWDUST DRYER OUTLET B
RUN I.D.
DATE
TIME STARTED
TIME ENDED
OB-M18-R1
 11/06/92
    11:37
    15:19
OB-M18-R2
 11/06/92
    17:32
    21:02
OB-M18-R3
 11/07/92
    09:02
    13:12
AVERAGE
GAS PARAMETERS

Gas Temperature - oF
Oxygen - %
Carbon Dioxide - %
Moisture - %
    181.9
    17.19
      3.3
     6.46
    182.3
     17.5
      3.2
     8.46
    182.3
     17.3
      3.2
     8.05
  182.2
   17.3
    3.2
   7.65
GAS FLOWRATE

Velocity - ft/sec
Actual Volume - acfm
Standard Volume - dscfm
    41.11
    22612
    16895
    42.17
    23200
    16954
    38.98
    21443
    15821
  40.75
  22419
  16557
ETHANE EMISSIONS

Cone. - ug/ml
Cone. - ppm
Cone. - mg/m3
Mass Rate - Ib/hr
 <  0.050
 < 40.012
 < 50.000
 <  3.164
 <  0.050
 < 40.012
 < 50.000
 <  3.175
 <  0.050
 < 40.012
 < 50.000
 <  2.963
< 0.050
<40.012
<50.000
< 3.101
METHANE EMISSIONS

Cone. - ug/ml
Cone. - ppm
Cone. - mg/m3
Mass Rate - Ib/hr
 <  0.101     <  0.101     <  0.101  <  0.101
 <151.469     <151.469     <151.469  <151.469
 <101.000     <101.000     <101.000  <101.000
 <  6.392     <  6.414     <  5.985  <  6.264
 (*) Gas flowrate data was taken  from OB-M0010-R1,R2,  and  R3,  respectively,
                                           65

-------
Table 5.5-1
                   SUMMARY OF VOLATILE EMISSIONS:  EPA METHOD CC30:
                   EPA GAS AUDIT CYLINDER #539.
RUN I.D.
DATE
C539-VST-R1A  C539-VST-R1B  C539-VST-R1C
    11/12/92      11/12/92      11/12/92
            AVERAGE
 POLLUTANT CONCENTRATION - ug/Nm3

 Acetone                    <       0.110
 Acrylonitrile              <       0.110
 Benzene                    <       0.110
 Bromomethane                       5.280
 2-butanone                         4.620
 Carbon Disulfide          <       0.110
 Carbon Tetrachloride      <       0.110
 Chloroform                 <       0.110
 Chloromethane                     11.220
 Ethylbenzene               <       0.110
 2-Hexanone                 <       0.110
 lodomethane                <       0.110
 Methylene Chloride               10.120
 M-/p-xylene                        1.430
 0-xylene                   <       0.110
 Styrene                    <       0.110
 Tetrachloroethene         <       0.110
 Toluene                            4.510
 1,1,1-trichloroethane            32.450
 Trichloroethene                  30.580
 Trichlorofluoromethane           23.540
 Vinyl Acetate              <       0.110
                     0.089
                     0.089
                     0.089
                     7.199
                     5.866
                     0.089
                     0.089
                     4.000
                    11.021
                     0.089
                     0.089
                     0.089
                     1.689
                     0.089
                     0.089
                     0.089
                     0.089
                     0.622
                    31.464
                    30.042
                    22.043
                     0.089
 2.857
 0.110
 0.110
 6.153
 6.043
 0.110
 0.110
 0.110
11.098
 0.110
 0.110
 0.110
 0.989
 0.110
 0.110
 0.110
 0.110
 0.440
27.250
32.744
33.073
 0.110
 1.019
 0.103
 0.103
 6.211
 5.510
 0.103
 0.103
 1.407
11.113
 0.103
 0.103
 0.103
 4.266
 0.543
 0.103
 0.103
 0.103
 1.857
30.388
31.122
26.219
 0.103
                                           66

-------
 Table 5.5-2      SUMMARY OF VOLATILE EMISSIONS.- EPA METHOD 0030:
                  EPA GAS AUDIT CYLINDER #540.
RUN I.D.                 C540-VST-R1A  C540-VST-R1B  C540-VST-R1C      AVERAGE
DATE                         11/12/92      11/12/92      11/12/92


POLLUTANT CONCENTRATION - ug/Nm3

Acetone                       141.184        26.843        17.146       61.724
Acrylonitrile           <       0.097 <       0.101 <       0.099 <      0.099
Benzene                         2.221         1.013 <       0.099 <      1.111
Bromomethane            <       0.097 <       0.101 <       0.099 <      0.099
2-butanone                      0.579 <       0.101         0.690 <      0.457
Carbon Disulfide        <       0.097 <       0.101 <       0.099 <      0.099
Carbon Tetrachloride    <       0.097 <       0.101 <       0.099 <      0.099
Chloroform                      0.290         0.203         4.434        1.642
Chloromethane           <       0.097 <       0.101 <       0.099 <      0.099
Ethylbenzene            <       0.097 <       0.101 <       0.099 <      0.099
2-Hexanone              <       0.097 <       0.101 <       0.099 <      0.099
lodomethane             <       0.097 <       0.101 <       0.099 <      0.099
Methylene Chloride             82.663        13.067        15.668       37.132
M-/p-xylene                     3.187 <       0.101 <       0.099 <      1.129
O-xylene                <       0.097 <       0.101 <       0.099 <      0.099
Styrene                 <       0.097 <       0.101 <       0.099 <      0.099
Tetrachloroethene       <       0.097 <       0.101 <       0.099 <      0.099
Toluene                        44.518        30.996        31.631       35.715
1,1,1-trichloroethane           5.504         0.608         1.478        2.530
Trichloroethene                 0.483 <       0.101 <       0.099 <      0.228
Trichlorofluoromethane          0.869         2.938         0.690        1.499
Vinyl Acetate           <       0.097 <       0.101 <       0.099 <      0.099
                                          67

-------
cr\
oo
                     / West
                    ./  Ambient''
                       Monitoring
                       Station
Outlet A


   SAWDUST DRYER
N
                                                                                         Grinding Room
                                                                                         Outlet Sampling
                                                                                         Locations
                                                                                                                 Crushers Ambient
                                                                                                                 Monitoring Station
                                                                                                                (inside  open building
                                                                                                                 suspended from roof)
                                                                 Grinding Room
                                                                 Inlet Ambient
                                                                 Monitoring
                                                                 Station
                                                                      East
                                                                      Ambient
                                                                      Monitoring
                                                                      Station
                        Figure 1.1-1:   Pine  Hall Brick  Facility  Site Plan.

-------
                                    TEST
                                  LOCATIONS
     RAH
    STORAGE
                         PRIMARY
                        CRUSHER
GRINDING
BUILDING
STORAGE
BUILDING
Figure  2.1-1:   Crushing, grinding, and storage  operations process schematic and emissions
                testing  locations at Pine Hall Brick.

-------
o
                DRYER INLET
                (KILN OUTLET)
               TEST LOCATION
           EXHAUST GASES
            FROM KILNS
           SAWDUST TO  _
          DRY STORAGE SILO
BAGHOUSE
      7-
        	 SAWDUST FROM
         GREEN STORAGE SILO
                                                                                            EXHAUST GASES
                                                                                            TO ATMOSPHERE
                                              CYCLONE OUTLET
                                              TEST LOCATIONS
      Figure 2.2-1:   Sawdust dryer process  schematic  and emissions testing locations at Pine
                       Hall Brick.

-------
                                                48.00'

POINT

1
2
3
4-
5
6

% ID

4.4
14.6
29.6
70.4
85.4
95.6
DISTANCE FROM
INSIDE OF PORT
(inches)
2.09
7.03
14.20
33.80
40.97
45.91
INSIDE
STACK
DIAMETER
48
0
in
4
0
ft
Figure 2.3.3-1: Sampling and Traverse Point Locations for
                Grinding Building Ducts.
                               71

-------
      PLAN VIEW
                     3" Test
                     Port
         •••i    a
                    -94"-
     6" Test
     Ports
                                •98"
                                                         From  Kiln
                                  From Kiln
                                        -Catwalk
       SIDE VIEW
                    3" Test
                    Port
        6"  Test
        Ports

                                                 From Kilns
     To  Dryer
                                          Scaffolding

                                          To Access
                                          Test  Port
                                                        Drawina Not To Scale
Figure 2.3.4-1:
Schematic of the Sampling Location  for the
Kiln Outlet/Sawdust  Dryer Inlet at  Pine Hall
Brick.
                                       72

-------
                                            54.0"
Point
1
2
3
4
5
6
7
8
9
10
1 1
12
%ID
2.1
6.7
1 1.8
17.7
25.0
35.6
64.4
75.0
82.3
88.2
93.3
97.9
Distance from
Inside of Port
(inches)
1 13
3.62
6.37
9.56
13.50
19.22
34.78
40.50
44.44
47.63
50.38
52.87
Inside Stack Diameter
Distance Upstream from
Disturbance
Distance Downstream from
Disturbance
54.0 in.
94.0 in.
98.0 in.
4.5 ft.
1 .74 Dia.
1.80 Dia.
Figure 2.3.4-2:
Schematic of Sampling and Traverse Points  for
the Kiln Outlet/Sawdust Dryer Inlet at Pine
Hall Brick.
                                 73

-------
             FRONT VIEW
           6" Test Ports
           3" Test Port
      Scaffolding
      To Access
      Test Ports
                          TOP VIEW

                         6" Test Ports
                          90° Apart
                                 3" Test
                                  Port
       ,,6" Test Ports
       -3" Test Port
                              w
                                                       SIDE VIEW
                                 f
                                120"
                                168"
                                 i
11 •• I   —	 From Cyclone



..6" Test Ports  90° Apart
X
-3" Test Port
                                                     To Fan
          Scaffolding
          To Access
          Test Ports
                                                                     Drowina Not To Scale
Figure  2.3.5-1:
Schematic  of  the  Sampling  Location  for the
Cyclone  Outlets at Pine  Hall  Brick.
                                            74

-------
POINT
1
2
3
4
5
6
7
8
9
10
1 1
12
% ID
2.1
6.7
1 1.8
17.7
25.0
35.6
64.4
75.0
82.3
88.2
93.3
97.9
DISTANCE FROM
INSIDE OF PORT
(inches)
1.00*
2.75
4.84
7.27
10.25
14.58
26.42
30.75
33.73
36.16
38.25
40.00*
           (*) Points  were adjusted  to 1-inch away from  stack wall.
INSIDE STACK DIAMETER
DISTANCE UPSTREAM FROM
DISTURBANCE
DISTANCE DOWNSTREAM FROM
DISTURBANCE
41.0 in
14.0 ft
10.0 ft
3.4 ft
4.1 DIA
2.9 DIA
Figure 2.3.5-2:
Schematic  of Sampling and  Traverse  Points for
the Cyclone Outlets at Pine Hall Brick.
                                   75

-------
STACK'J
                               Inclined       Dry Cos
                              Manomoter      Meter
             Figure  4.1.5.1-1:   EPA Method  201A Sampling  Train
                                           76

-------
-i
ro
n>
t-t-
rr
o
0.

rvi
o
OJ
3
-
-5
PJ
                       PITOT TUBE
                                            EGR PROBE ASSEMBLY

                                                                                                          METER AND FLOW

                                                                                                         CONTROL CONSOLE
)—f\\ RECYCLE

)—LJ FLOW LFE
                                                                                                  C    SAMPLE

                                                                                                        ORIFICE
                                                                                                                  EXHAUST
                                                     SEALED PUMP
                                                                                         [ DRY GAS METER            I

-------
                                                      Thermometer
                                             Vone
                                             PufTID
Figure  4.1.6.1-1:    EPA Method 13B Sampling Train
                                   78

-------
      - r o D e  and
     r':'. er  holder
   Erusri  and rinse
   tnree times with
    distilled  water
      "liter
       I
Carefully  remove
   and place
  in  container
                                         moinaers
 Measure  contents
 of each  impmger
         I
 Limpty contents of
   each impinger
    into sample
     container

         +
Rinse  each impinger
 three times with
   distilled water
                                                                      V
                                                               Empty  contents
                                                                  into  sample
                                                                   container
                        Container  1
                                            Container  2
Figure 4.1.6.3-1:  EPA Method 13B Recovery Procedure
                      Source:  40 CFR Part 60,  Appendix A
                                      79

-------
Container 1
Rinses and Container 1 Conta ner 2
contents of Impingers Filter Silica Gel

I
Macerate filter
1
lf total Add 100 mg CaO and
volume > 900 ml, H20 to form slurry
make filrate i
basic and j




0 6 1° Evaporate H20 keeping
|
1
Heat until filter chars
1
I
Reduce contents to ash
in muffle furnace
1
1
Add 4 g of NaOH and
fuse samples in
muffle furnace
V
Combine and dilute
to 1 liter
I
1
Distill known
aliquot rapidly
1
Transfer to 250 ml flask and
dilute to mark with distilled water
1








J *
Combine aliquot (25 mi) with Weigh to
equal volume TISAB and analyze nearest 0.5 g
for F using ISE
Figure 4.1.6.5-1: EPA Method 13B Analysis Procedure
                  Source: 40 CFR Part 60, Appendix A
                                80

-------
Probe and Front -half Impinger 1 and Impinger 7
Filter of Filter Holder Back-half of
T
Carefully remove
with teflon tweezers
and place in
petri



dish



\
Rinse back — hall
Filler Holder Impinge rs 2 — J Impinqer 4 Impinqers 5 — 6 Silica Gel
| |

of filter holder Measure Measure Measure
and all connecting lines contents of contents of contents of
three times with each imping er impinger each impinger
0.1 N
Record th
HNOj
e volume
of tht condensate
capured In the
Brush loose Brush with nonmetalllc brush
first Implnger






Empty contents
Inta sample
container
Empty contents Empty contents
porticulate and rinse probe and front— half 1 into sample into sample
onto filter of filter holder three Empty contents container container Rins« eoc




times with acetone lnto s°mPle



Seal polri dish














container


Rinse first impinger
three tin
' 0.1 N
1
Rinse probe, front — half
of filter holder, and
connecting lines
three times with
0.1 N HN03
i
»












Empty contents
into sample
T Imoinaer container
thr«« times with
acidified KMn03




nes with Rinse each impinger Rinse impinger Rlnaa eoch Impinger
HMO] three time! with three times with with distilled water
0.1 N HN03 0.1 N HN03
















	 T
•
Rinse each impinger
once «ith 8 N HCL

1












Container 1 Container 2 Container 3 Container 4A Container 4B Container 5A Container 58 Container 5C Container 6
Figure 4.1.7.4-1: Multiple Metals Recovery Procedure
                  Source: 40 CFR Part 266, Appendix IX, Section 3

-------
            integrated
            Quartz
    STACKH    Nozzle
Heated Quartz Filter
                                                           Thermometer
                     Inclined
                    Wanometer
         Vane
         PumD
Figure  4.1.7.1-1:  Multiple Metals/TSP Sampling Train
                                            82

-------
00
UJ
               Container  3
             FH Nitric  Rinse
Acidify  to PH  2
with cone  HNOj
            Reduce  volume  to
            near  dryness and
             digest with  HF
             and cone.  HNO^
                       Container 2
                    FH Acetone Rinse
    Container  1
       Filter
                                 Reduce  to dryness
                                 in a  tared beaker
                                 Determine  residue
                                  weight in  beaker
                                 Solubilize residue
                                  with COnc. HNOT;
  Container 4
Impingers 1  - 3
                                                       Desiccate to
                                                      constant weight
Container 5A.  5B, &  5C
   Impinqers 4-6
                                                                                         "I
                                                      Determine filter
                                                     particulate weight
 Divide into 05  g
sections and digest
 each section with
cone. HF and HNO^
                                                                   Aliquot  taken
                                                                    for  CVAAS
                                                                  for Hg analysis
                                                                    Fraction 2B
                                                                  Digest  with acid
                                                                 and  permanganate
                                                                at 95°C for 2  hours
                                                                   and analyze
                                                                 for  Hq  by  CVAAS
                                                  Acidify
                                                 remaining
                                              sample  to PH  2
                                              with cone  HNOj
                                                Fraction  2A

                                                     I
                                              Reduce volume
                                              to  near dryness
                                              and digest with
                                              HNOj and  H202
                                                                                                     Analyze
                                                                                                    by ICAP for
                                                                                                 15 target metals
                                                                                       Analyze by
                                                                                         GFAAS
                                                                                       for  metals
                     Filter and dilute
                    to known volume
                       Fraction 1
                                      Remove 50 to 100 r
                                         aliquot for Hg
                                     "  analysis by CVAAS
                                           Fraction 1 B
                     Analyze by ICAP  for
                        target  metals
                        Fraction IA
                                  Analyze  for
                                metals by  GFAAS
                                  Fraction 1A
                                                                            Digest with  acid and
                                                                          *" permanganate at 95°C
                                                                          a water  bath  for 2 hours
                         Analyze  aliquot for
                           Hg using CVAAS
   Individually, three
  separate digestions
    and analyses.
   digest with acid
  and permanganate
  at  95°C for 2  houis
     and analyze
   for Hg by CVAAS
  Fraction 3A. 3B, 3C
                                                     '   '' ,
                                                 '"a'e'A °
           'Analysis  by AAS  for metals  found at less than 'i ug/ml  in digestate  solutions,  if  desired  Or analyze  (or each metal  by AAS, if desired
       Figure  4.1.7.7-1:  Multiple  Metals  Analysis  Procedure
                                    Source:  40  CFR Part  266,   Appendix IX,   Section  3

-------
     STACK
            Inclined      Dry Cos
           Manometer      Meter
Vone
Pump
                                                   Silica Gel  B|ank     Woter
Figure  4.1.8.1-1:     EPA Method  201A/202  Sampling Train
                                         84

-------
00
                 Filter
            Corefully remov
              and  place in
               petn dish
              Brush  loose
               particulote
               onto  filter
             Seal petn  dish
  Cyclone and     Front-half of
"Turnaround Cup"  Filter Holder
                                  Cyclone
                                  Housing
 Rmse
  with
acetone
 Rinse
  with
acetone
 Rinse
 wtlh
acetone
              Container  1
                                         Container 2
                                Container 3
                                 (Discard)
                                     Back-half of
                                   Filter Holder  and
                                   Impinqers  1 - 4
                                                    Rinse filter
                                                   housing  twice
                                                 nth distilled water
                                                                                     Measure contents
                                                                                     of each imprnger
                                                                                     Empty  contents
                                                                                       into  sample
                                                                                        container
                                                    Rinse  twice
                                                   with distilled
                                                      water
                                                                                    Container 4 and 5
                                                                                                          Back-half
                                                                                                         Acetone Rinse
                                                                                                                           Impingers
                                                                            Impirifjer
                                                                             Silica G
                                                                        Brush and rinse
                                                                    back-half of filter holder
                                                                        three times with
                                                                         distilled  water
Rinse
with
MeCl0
L'rnply  c unten ta
 into sample
   container
                                                        Container 6
                                                         (Discard)
                                                                                                                             Container 7
                                                                                                                                                Con toil
       Figure  4.1.8.4-1:  Method  201A/202  Recovery  Procedure
                                      Source:   40  CFR  Part  51,   Appendix  M

-------
00
en
             Container  I
                Filter
   Container  2
  
-------
    STACK>
                                                Silica Gel
                                                      Blank
Figure 4.1.9.1-1:  Andersen Impactor  Sampling Train  for Particle
                   Sizing
                                    87

-------
oo
CD
             Set of
            9 Filters
Impactor nozzle
Impingers  1  — 3
Impinger 4
 Silica  Gel
        Carefully remove
           each  filter
         from  impactor
                                 Brush and rinse
                                   three  times
                                   with acetone
                       Measure contents
                          of  impingers
                         Empty  contents
                           into sample
                            container
           Place filter
          back  into its
        original  tared  foil
           Container  1
  Container 2
     Discard
                                                                                   Container  3
     Figure 4.1.9.3-1: Andersen Impactor Recovery Procedure
                        Source:  Manufacturer's Recommended  Procedure Manual

-------
        o n t c i n e r
         Set of
        9 Filters
      Desiccate to
     constant  weight
  Determine particulate
         weight
        V
    Reduce to
     dryness
Determine residue
     weight
  Weigh  to
nearest 0.5  g
Figure 4.1.9.4-1: Andersen Impactor Analysis Procedure
                  Source:  Manufacturer's Recommended Procedure
                           Manual
                                   89

-------
                                          3-Woy
    STACK
                                             Stopcock
                                    Empty   0.1 N    0.1 N
                                                  NoOH
                     Inclined
                   Manometer
Vane
Pumo
Figure  4.1.10.1-1:   EPA Method  26 Sampling Train
                                         90

-------
     Measure impmger
         contents
            V
      Empty contents
       into  sample
         container
  Rinse three  times with
       distilled water
                                lmpinaer
   Measure impinger
       contents
Rinse  three  times  with
    distilled water
        Container
     Container 2
       (Discard)
Empty  contents
  into  sample
   container
                                                       Container 5
Figure 4.1.10.3-1: EPA Method 26 Recovery Procedure
                    Source:  40 CFR Part 60, Appendix A
                                    91

-------
         container
       m DI nae rs  '
.ontainer  2
 m D i n q e r  4
  .ontainer ,
  Siiica  Gel
     Transfer  to  100  ml
     flask  and di ute  to
  mark with distilled  water
       Analyze  aliquot
       using 1C for Cl
  Discard
  Weigh to
nearest 0.5 g
Figure  4.1.10.5-1:  EPA Method 26 Analysis Procedure
                    Source: 40 CFR Part  60, Appendix  A

-------
                      Heated Stainless S(««l Probe
           Data Acquisition
             System
                                     H«ot«d
                                     Filter
                                   Teflon
                                   Sample Line
                                           Dual-l

n
3ass
•atrve
iser
HIIHIIli


Unheoted Teflon
/ Sample Une
To Individual ^
                                               I  I
                                                      Calibration Manifold
                                                      Calibration Cases
Figure  4.1.11.1-1:
Continuous  Emissions  Monitoring  Dry
Extractive  System for EPA Methods 3A,  7E,
and 10  (02,  CO   NOx,  CO) .
                                         93

-------
    STACK
                                             3-Way
                                             Valve
                   Heated Stainless Steel Probe
                                                         Flowmeter
                                       Heated
                                       Filter
   VOC (ppmwv)
     Signal
  To Datalogger
   VOC
 Analyzer
                                Heated
                                Teflon
                                Sample Line
Figure  4.1.11.1-2:
Continuous Emissions Monitoring System for EPA
Method 25A
                                           94

-------
                                                             Teflon Sample Line
                      Stainless Steel Probe
                                               Fine Adjust
                                                 Valve
                                                 Vacuum Pump
                                                                           Quick Connect
                                                                                 Check Valve
                                                                                 Flexible Bag
                                                                     Riaid. Protective Container
Figure  4.1.12.1-1:    EPA Method 18  Sampling  Train
                                                 95

-------
                               'edlar baa
                               Make  sure
                                bag is
                               not leaking
                              Protect from
                                sunlight
                                 Label
Figure  4.1.12.3-1:  EPA Method 18 Recovery Procedure
                     Source: 40 CFR Part  60,  Appendix  A
                                 96

-------
                             ontainer  ;
                             edlar 6 a q
                      Analyze for methane  and
                  ethane  using gas chromatography
Figure 4.1.12.4-1: EPA Method 18  Analysis Procedure
                   Source:  40 CFR Part 60,  Appendix A
                                 97

-------
                                                Teflon Lines
        Pressure
         Gouge
                                   Vane
                                   Purno
Figure 4.1.13.1-1:   Volatile Organic Sampling Train  (Method  0030)
                                     98

-------
                               enox lube
                              emove  tube
                              from tram
                             Cap off ends
                               of tube
                              Insert into
                            protective sheath
                                            Tengx
                                                        T'.pe
  Remove tuDe
   f rom tram
 Cap off ends
    of tube
  Insert into
protective sheath
                          Label and refrigerate   Label  and refrigerate
Figure 4.1.13.3-1:  Method 0030  Recovery  Procedure
                         Source:  EPA  600/8-84-007
                                          99

-------
     . oncainer  1
      
-------
     STACK
                 Cuartz
                 Nozzle
                            Heatea Filter
                      Heated Quartz Probe
                                                Condense

                                                         
-------
o
to
                  Filter
              Carefully remove
               and place in
                 petri dish
                Brush loose
                 particulote
                 onto filter
               Seal petri dish
                 Container 1
                                     Probe &.
                                    Front-half   Back-half
                                                           Condenser
                                                                              Impinger  1
                                  Impinger  2-4
                                                       Impmger 5
                                                        Silica Gel
                                            Rinse three times
                                            with acetone and
                                          brush between rinsings
Record impmger volume
                                            Rinse three times
                                          nth methylene chloride
                                                          with toluene
                                                               I
                                              Container  2A  Container
                              Measure impinger  volumes  Empty contents
                               to determine moisture       into sample
                                     content              container
              Rinse three  times
                with toluene
                                                                             Container  4A Container  4B
     Sor bent
     Cartndqe
                                                                          Cap  oft  ends
                                                                          of  cartridge
 Cover with hexane
rinsed aluminum  foil
                                                                                                          Discard contents     Container 5A and 5B
                                                                                                                                               Label and refrigerate
                                                                                                                                                   Container 6
          Figure  4.1.14.3-1:   Method  0010  Recovery  Procedure
                                           Source:   EPA  600/8-84-007

-------
o
u>
        Container  1
            Filter
                Container 6
             Sorbent  Cartridge
Containers  2A,  3,
   4A,  and 4B
   Train Rinses
 and Condensate
Containers  5A and  5f
      Silica Gel
                                    Spike
                                           Spike
                                                      Separatory  funnel
                                                         extraction
                    Transfer to
                   glass thimble
 Soxhlet extraction
1 6 hours  with MeCI
                               Extractions  are  combined
                                and analyzed by  GC/MS
                                                                 Weigh  to
                                                               nearest  0.5
     Figure 4.1.14.5-1: Method  0010  Analysis Procedure
                         Source:  EPA  600/8-84-007

-------
  MEASUREMENT OF AIR FLOW INTO PRIMARY CRUSHER AT PINE HALL BRICK

     Emissions  inventory testing  at  the  #  4  brick  production
facility of Pine Hall  Brick Co was conducted during the weeks of
October 23 through November  7,  1992.  Part of this testing included
sampling for total and PM10 particulate  from the primary crushing
operation.  The primary crusher is  housed in a building completely
open on the charging side and  largely open  on the output side.
Particulate sampling was done with  standard ambient  total and PM10
collectors located inside and at the top of the charging area.  An
approximation of air flow was determined by using plastic sheeting
to block the open area around the output conveyor and installing a
total air flow meter in the  center  of the plastic.   The flow meter
used has reversing capacity to measure positive and negative flow
giving a net total flow in feet.  For these tests  positive flow was
air entering the crusher building around the output  conveyor.  The
Total volumetric  flow  rate  was determined by recording the total
measurement time and multiplying the flow by the  area of the meter
face (0.0873 sq= ft.).
     Air  flow was  not  measured on  the first  day (Nov.   2)  of
particulate testing because the  flow meter  was not  available.
DATE
TIME
11-3-92  Start  09:30
         Stop   10:00
         Start  10:02
         Stop   11:02
         Start  11:05
         Stop   14:05
         Start  14:07
         Stop   14:57
         Start  15:00
         Stop   17:35
         Total  Time:475 minutes
 TOTAL FLOW
  0
  2,902
  0
- 1,515
  0
-28,834
  0
    202
  0
 11,370
 Net flow:-16,279  ft
 Net CFM:  -  2.99
11-4-92   Start  07:00
          Stop   09:00
          Start  09:02
          Stop   12:02
          Start  12:03
          Stop   15:03
          Start  15:04
          Stop   17:34
          Total  Time:630  minutes
                             0
                            21,
                             0
                            28,
                             0
                            19,
                             0
                             2,
                            Net
                            Net
    578

    475:

    865

    121
     flow:  72,039  ft
     CFM:  9.983
11_5_92   Start  07:10
          Stop   15:10
          Total  Time:480  minutes
                             0
                            71,678
                            Net flow: 71,678 ft
                            Net CFM: 13.036

-------
11-6-92 (Crusher not run on Fridays, charging hopper completely
       empty, total flow measured to check empty hopper effect,
         if any)
         Start 07:15                        0
         Stop  15:00                       43,379
                                           Net flow: 43,379 ft
                                           Net CFM: 8.144

     As expected, air flow into and through  the crusher building
seems^to be determined primarily by air movement and winds in the
immediate vicinity of the building.  November  3  was the only day
with noticeable  wind in  the area  and  they were  light.    This
probably explains the negative flows observed on Tuesday.

-------