TECHNICAL NOTE
                            ORP/TAD-77-1
        Evaluation of
            Tritium
    Recycle and Buildup
              in a
Pressurized Water Reactor

            THE UNITED STATES
        ENVIRONMENTAL PROTECTION AGENCY
          Office of Radiation Programs
             March 1977

-------
                                          TECHNICAL NOTE
                                            ORP/TAD-77-1
      Evaluation of Tritium Recycle
and Buildup in a,Pressurized water Reactor
              C. Bruce Smith
   U.S. Environmental Protection Agency
       Office of Radiation Programs
      Technology Assessment Division
      Energy Systems Analysis Branch
                March  1977

-------
                               PREFACE
    Phe Office  of  Radiation  Programs  (ORP)   of  the  Environmental
Protection  Agency carries out a national program designed to evaluate
public health impact from ionizing and nonionizing radiation,  and  to
promote  development of control necessary to protect the public health
and the environment.  This report provides the  technical  information
necessary  for  ORP  to  evaluate the environmental aspects concerning
tritium  recycle  in  a  pressurized  water   reactor   (PWR).    This
information  is  important  since  the  impact  of  tritium recycle is
significantly affected by the design and operation of  PWRs.   Results
of  this  paper  may  be used as input into dose models to analyze the
total environmental impacts of tritium released  for  various  tritium
recycle operations.
                            David s. Smith
                               Director
               Technology Assessment Division (AW-459)

-------
                          TABLE OF CONTENTS
                                              N

                                                                  Page


SUMMARY                                                             i


I.       Introduction                                               1

II.      Physical Model of Activity Transport                       1

         A.   Routine Operations                                    2
              1.   Compartment 1 - Primary Coolant System           2
              2.   Compartment 2 - Liquid Radwaste System           3
                   and RMWST
              3.   Compartment 3 - Spent Fuel Pit                   3
              H.   Compartment H - Refueling Water Storage          3
                   Tank
              5.   Compartments 5 and 6 - Secondary System          4
                   Steam Generators and the Remaining
                   Secondary System

         B.   Shutdown                                              4

III.,     Mathematical Model of Activity Buildup                     5

IV.      Parameter Selection                                        7

         A.   Trojan, FSAR Data, Chapter 11                         7

         B.   PWR-Gale Code NUREG-0017                              8

         C.   Other  Parameters                                      8

         D.   Conclusions of Parameter Values                       9

         E.   Ranges of Parameter                                   9

V.       Analysis and Results                                      10

         A.   Annual Tritium Source Term                           10

         B.   Analysis of a Standard Tritium  Source Term  of        11
              700 Ci/year

         C.   Effects of Secondary System  Parameters               13
              1.   Reactor Losses as a Function  of Steam           13
                   Generator Slowdown

-------
              2.   Reactor Losses as a functiort sof Primary         13
                   to Secondary Leak Rate

         D,   Effects of Various Limiting Concentrations           14

VI.      Significance of Results                                   14

REFERENCES                                                         16

-------
                                TABLES
Table

  1.               Effects of Various  Limiting                      17
                   Primary Coolant  Concentrations

  2.               Parameter Identification                         18

  3.               Base Case Parameters                             22

  U.               PWR Tritium  Releases                             23


                                 FIGURES


Figure

  1.               Schematic of Systems                             24

  2.               Block  Diagram of System                         25
                   During Routine operation

  3.               Refueling Volumes                               26

  U.               Mathematical Models of the                      27
                   Compartments

  5.               Primary Coolant Activities                      28

  6.               Plant  Activity versus Time                      29

  7.               Intentional  Removal versus                      30
                   Source Term

  8.               Time  Until Removal Begins versus                31
                   Source Term

  9.               Activity Buildup in Each Compartment            32
                    (700  Ci/yr  Source Term)

  10.               Tritium Losses from Base Plant Design           33
                    (700  Ci/yr  Source Term)

  11.               Liquid and  Gaseous Environmental                34
                    Releases

-------
12.                Secondary System Releases versus                 35
                  Steam Generator Slowdown Rate
                  (700 Ci/yr Source Term)

13.                Effect of Primary to Secondary                   36
                  Leakage  (700 Ci/yr Source Term)

-------
                               SUMMARY
    Recycling  radioactive  liquid wastes at light-water cooled nuclear
power reactors is becoming  a popular method of .limiting release levels
to as low as practicable.   As a  result  of  recycling  liquid  waste,
almost  all  of the radioactive materials in a  liquid waste stream can
be renoved by  filters,   demineralizers,  reverse  osmosis  units,  or
svaporators.   However,   tritium in the liquid  waste streams cannot be
selectively removed by the  aforementioned conventional liquid radwaste
treatment equipment.   Combined with  its  relatively  long  half  life
(12., 33  years),  recycling   results  in  a buildup of large volumes of
tritium contaminated liquids.

    In a boiling water reactor (BWR), the  production  of  tritium  is
primarily in the fuel and control rods.  The zirconium cladding around
these rods prevents most of the tritium from escaping from the rods to
the  reactor  liquids.   Thus,  the buildup of  tritium in a BWR is not
considered a  significant  plant  problem.   In  a  pressurized  water
reactor  (PWR), tritium is  also produced in the fuel and control rods,
as well as by  production  from  chemicals  (boron,  lithium)   in  the
priaiary  coolant  liquids.   Since the quantities of tritium introduced
into the primary coolant system of a PWR are much  higher  than  in  a
BWR,   the management and impact of tritium at a PWR must be evaluated.
It stiould also be noted that most of the tritium produced in the  fuel
of  PWRs  or  BWRs  remains  in  the clad fuel  and control rods and is
eventually transported to the reprocessing plant.

    To evaluate  the  magnitude  of  the  potential  tritium  handling
problem  at  PWRs  and  to   develop  recommendations  for solutions, a
computerized model of tritium buildup in a  PWR  was  developed.   The
results  from  this  model   will  be  used  to   assess  the  potential
environmental impact of tritium recycle for the entire  nuclear  power
reactor  industry  and will be instrumental in  developing standards or
guidance concerning  tritium  recycle.   The  model  incorporates  six
compartments   -  primary  coolant  system,  liquid  radwaste  system,
condensate storage tank, spent fuel pool, steam  generators,  and  the
remainder   of   the  secondary  system;  and  4  release  pathways
containment   building    leakage,    primary-to-secondary    leakage,
evaporation   from  the  spent  fuel  pool  and  refueling  canal  and
intentional removal from the primary system to limit  the  buildup  of
tritium in the coolant.  A reactor operator can control the buildup of
tritium  in  the  primary coolant system of a PWR by utilizing several
control options - the intentional removal of liquids from the  primary
coolant  system  with  subsequent  offsite  disposal,  the intentional
environmental release of liquids from  the  liquid  radioactive  waste
system,  and  an increase of the evaporation rates from the spent fuel
pit and the refueling water  canal.   To  illustrate  the  effects  of
tritium  recycle,  a  total recycle system with intentional removal of

-------
primary  coolant  liquids  was  selected  as  the   operator   control
mechanism.   Thus,  the  planned release of tritium to the environment
from the liquid radioactive waste system  was  not  included  in  this
analysis.   EPA.  has  not  endorsed  any  of  the previously mentioned
control  mechanisms,  and  will  reserve  judgment  until  a  complete
evaluation  has been made.  The computer model was used to analyze the
environmental tritium releases, buildup of  tritium  in  the  reactor,
volumes  and  activities  of  tritiated  water that must be removed to
control tritium buildup,  the  effects  of  various  source  terms  on
tritium  buildup,  and  the  sensitivity  of  the  buildup  to various
secondary system parameters.   Generally,  the  following  conclusions
were  reached for the base case plant  (discussed later in this report)
that is presented:
    (1)  Based  on  the  reactor  system  analyzed  in   this   paper,
    intentional  removal  of  tritium  from the primary coolant systen
    bacomes necessary during the 40 year life of the  reactor  if  the
    production and release of tritium in the primary coolant system is
    higher  than  625 curies per year.  In the remainder of this paper
    this production and release is  termed  the  "source"  term.   For
    source  terms  greater  than  1,000  curies/year,  removal becomes
    necessary within 5 years of initial operation of the reactor.  The
    removal  (termed intentional removal) involves either  the  removal
    of  volumes  of  tritiated  primary  coolant  system  liquids  for
    solidification and offsite  disposal  or  selective  removal   (and
    disposal)  of  tritium  from  the  primary  coolant liquids.  This
    removal is necessary to limit the concentration of tritium in  the
    primary  coolant  to  established  operating  conditions  for  the
    reactor  (assumed in this paper to be 2.5 jjCi/ml of H3).

    (2)  For a source term Df 700 curies/year, about 80% of the losses
    from the reactor during the reactor life are  equally  distributed
    between  radioactive  decay  and  uncontrollable  releases  to the
    environment.  For larger source terms, intentional removal becomes
    the dominating plant loss mechanism.  This  removal  is  necessary
    for the reasons indicated in (1) above.

    (3)  During the 10 years of operation of a  reactor  whose  source
    term  is  700  curies  per  year,  about 80% of the uncontrollable
    environmental releases are equally distributed between evaporation
    and leakage to the containment building with subsequent release to
    the environment.

-------
    (4)   The rate of steam generator blowdown in the secondary  system
    of:  a PWR has little effect upon losses or buildup of tritium at a
    reactor.  However, if there is  no  primary-to-secondary  leakage,
    there  is a significant reduction in environmental losses from the
    reactor  in  conjunction  with  an  increase  in  the  volumes  of
    tritiated  liquids  that  must  be  intentionally removed from the
    primary coolant system.
    In general, it is concluded that for the base case presented and a
source term production of 700 curies per  year  that  (1) uncontrolled
environmental  releases  can be reduced during the UO year life Of the
reactor by 65% or more by using total recycle of  tritiated  liquids*;
(2)   several  thousand  curies and several hundred thousand gallons of
tritiated water (with a tritium  concentration  of  approximately  2.5
MCi/nl)  must  be intentionally removed for disposal or treatment over
the plant life if "total" tritiated liquid recycle is undertaken;  and
(3)   about  one  million  gallons of water and 5,000 curies of tritium
will be remaining in the reactor systems at the end of its planned  40
year life.
*NOPEJ    Removal of tritium from the reactor is necessary to  maintain
    the  primary  coolant  concentration of tritium to the established
    operating conditions  assumed  in  this  paper   (2.5pCi/ml).   The
    removed  tritium  is  also  assumed  not  to  be  available  as an
    environmental contaminant.
                                    iii

-------
          EVALUATION OF TRITIUM RECYCLE AND BUILDUP IN A PWR
I.   INTRODUCTION

    The major modes of production of tritium in a PWR is by fissioning
in fuel rods, neutron capture reactions with poison material  used  in
control  rods,  and  activation  of primary coolant additives, such as
boron and lithium.  The tritium produced in the fuel rods and  control
rods  is released to the primary coolant either through defects in the
rod  claddings  or  by  diffusion  through  the   cladding.    Tritium
eventually  contaminates  the  liquid  radwaste  system, the secondary
coolant system, the spent fuel pit, and the  condensate  storage  tank
either  during  routine  operations or refueling operations.  To model
the buildup and release of tritium  at  a  PWR  employing  recycle  of
tritium contaminated liquids, the interrelationships among systems and
the  movement  of  tritium to and from these systems must be analyzed.
The following sections describe the physical and  mathematical  models
of tritium recycle and the results of selected parametric studies.

II. PHYSICAL MODEL OF ACTIVITY TRANSPORT

    The  relationships  of  the  PWR  systems,  or  compartments,  are
illustrated  in  a  schematic  model  in  Figure  1.   The PWR systems
containing tritium can be  separated  into  the  following  functional
compartments:    (1)  primary  system;   (2)  liquid radwaste system and
reactor makeup water storage tank  (RMWST) ; (3)  spent  fuel  pit;  (U)
refueling  water  storage  tank;   (5)  steam  generators;  and (6) the
remainder of the secondary system.  A block diagram of  the  transport
of  tritium  into  and  out  of  these  compartments  is  presented in
Figure 2.

    Actually there are  more  leakage  pathways  and  routing  options
available in a PWR than are presented in  Figures 1 and 2.  However, in
modeling  the  movement  of  tritium  in  a  PWR  some pathways may be
combined  or  even  eliminated  without   significantly  affecting  the
overall  modeling.   For  example,  the   leakage  of  liquids from the
primary coolant  system into  the  containment  building   (L)  includes
other leakage pathways.  Some of these leakages are from the auxiliary
building,  radwaste  building,  spent fuel pit, and from various tanks
which are collected and routed back to the liquid radwaste  system  or
which  contribute  as  minor gaseous release pathways.  These leakages
can be accounted  for by  either  adjusting  parameters,  such  as  the
shinbleed  rate   (which  may  also  be  routed from the primary system
ultimately to the radwaste system), or by increasing  the  leakage  to
the containment  building.  Also, the components of the liquid radwaste
system  may  be  modeled by using only the reactor makeup water storage
tank  (RMWST) volume, which herein is considered to include the  liquid
radwaste  system volumes and the actual RMWST volume.  This assumption

-------
is  realistic  since  liquid  radwaste  system   components   do   not
selectively  remove tritium from the liquid stream.  Another option is
the method of indicating the percentage of tritium  recycle  employed.
This  percentage  can be expressed either as the fraction of shimbleed
flow, primary coolant leakage, makeup  flow  from  the  RMWST  to  the
primary  coolant  system,  or any combination of the three.  It should
also be noted that  the  computer  program  used  for  the  parametric
analysis  of  tritium  buildup  includes  a provision for limiting the
primary coolant concentration to a predetermined level  by  increasing
the  intentional  removal   (R)  (see table 2) , as necessary.  R simply
indicates some type of  planned  or  intentional  removal  of  primary
coolant liquids from the primary coolant system (or other systems with
high   tritium  concentrations)  in  order  to  maintain  the  tritium
concentration within the  technical  specifications  of  the  reactor.
This removal may be some type of selective removal of tritium from the
liquids or removal of large volumes of tritiated liquids for disposal.

    The limiting primary coolant tritium concentration that was chosen
was  2.5MCi/ml.  This value, or one within several tenths of 1 jiCi/ml,
was selected because of concerns with potential occupational exposures
in the reactor building atmosphere and spent  fuel  pit  areas  during
operation  and  refueling*»2,3.   Based  on  assumed values of primary
coolant leakage rates  into  the  closed  containment  building,  this
concentration  limits  the  buildup  of  tritium  in  the  containment
building atmosphere to levels previously indicated to be acceptable by
utilities.  Many of  the  recent  PWR's  are  being  designed  with  a
continuous  purge  of  the  containment  building atmosphere, thus the
limiting primary coolant concentration may be increased  significantly
(by  at  the  least  a factor of 2), since the equilibrium containment
concentrations of tritium would be  substantially  lower.   For  these
PWR's,  many  of  the  results and conclusions presented in this paper
would be altered in a manner which is  somewhat  proportional  to  the
limiting  coolant  concentration  used.   The  calculated removals and
environmental releases for  several  higher   limiting  primary  coolant
concentrations  are presented in table 1 and the results are discussed
in section IV.D.

    The following sections  discuss (1) tritium buildup in each of  the
compartments  during  routine  operation  and  shutdown  and   (2)  the
relationship between compartments.

A.  Routine Operations

    1.   Compartment 1 - Primary Coolant System

    Tritium in the primary  coolant system can be transported from  the
system  by  leakage  into   the  containment  building and the auxiliary

-------
building.  The tritium that  remains  in  the  water  phase  of  these
leakages  is  drained to the liquid radwaste system.  The tritium that
is in the gaseous phase is eventually released through the containment
building ventilation system.  A small side  flow  of  primary  coolant
(shitnbleed)  may  be  processed through the liquid radwaste system and
collected in the RMWST.  Primary coolant makeup is  then  returned  to
the  primary  system  from  the  RMWST.  Other losses from the primary
system include primary to secondary leakage,  evaporation  of  tritium
from the refueling canal during refueling shutdown, radioactive decay,
and intentional removal (discussed previously) .

    2.   Compartment 2 - Liquid Radwaste System and RMWST

    As indicated previously relative to tritium, the  liquid  radwaste
system  can  be modeled as simply a tank which includes all the liquid
radwaste system tanks and components  and  the  reactor  makeup  water
storage  tank   (RMWST).   The  additions  to  this  system  come  from
shimbleed  from  the  primary  coolant  system,  the   collection   of
containment  building liquids contaminated by primary coolant leakage,
or via routing of steam generator blowdown  liquids  to  this  system.
Losses  from  this system can result from controlled discharges to the
receiving waters of the plant, makeup to the primary  coolant  system,
radioactive  decay,  and  continuous makeup to the spent fuel pit.  As
indicated tritium can be transported to the liquid radwaste system  by
the  routing of steam generator blowdown liquids; however, in the base
case analyzed in this paper, it is assumed that the blowdown is routed
instead to the main condenser.  Another option, which is  analyzed  in
section   IV.  C.  1,  is  to  route  the  blowdown  directly  to  the
environment.

    3.   Compartment 3 - Sjaent Fuel Pit

    During routine operations tritium is added to the spent  fuel  pit
by  makeup  from  the RMWST.  Removal of tritium from the reservoir is
either by radioactive decay or evaporation.  During refueling shutdown
a portion of the spent fuel pit water becomes mixed with  the  primary
coolant  system  in  the  refueling  canal.   As previously indicated,
during refueling shutdown tritium is removed from the refueling  canal
by evaporation and decay.

    <4.   Compartment 4 - Refueling Water Storage Tank

    Tritium is  transported  to  the  refueling  water  storage  tanks
 (RWSI1) (often  called  condensate  storage tanks) mainly as a result of
refueling operations.  During refueling the refueling canal is flooded
with a large volume of water from the RWST.  At the end  of  refueling
operations,  this  water,  which  is now contaminated with tritium, is

-------
returned to the RWST.  The only loss  from  the  RWST  during  routine
reactor operation is radioactive decay.

    5.   Compartment 5 and 6 - Secondary System Steam  Generators  and
         the Remaining Secondary System

    During  routine  operation  tritium  may  leak or diffuse from the
primary coolant system into the  steam  generators  of  the  secondary
system.   From the steam generators a small fraction of the tritium is
carried over in the steam to the turbines and returned  to  the  steam
generators  in  the feedwater.  If the steam generators are blowndown,
tritium can be transported to the  environment,  the  RMWST  (via  the
radwaste  system),  or  the main condenser.  Some of the tritium which
accumulates in the remainder of the secondary system  is  released  to
the  environment  by  steam  leakage,  steam  jet  air ejector exhaust
discharges, and condensate leakage to the turbine building.

B.  Shutdown

    During refueling shutdown,  a  fraction  of  the  primary  coolant
system  is  drained  to  the liquid radwaste system for processing and
then retained in the RMMST for the duration of  refueling  operations.
The  remaining  primary  coolant  water in the refueling canal is then
mixed with a large volume of water from the  refueling  water  storage
tank  (RWST) and a small fraction of the water from the spent fuel pit.
Tritium  losses  from the reactor during refueling operations are from
radiDactive  decay,  evaporation  from  the  spent   fuel   pit,   and
evaporation  from  the  refueling  canal  in the containment building.
Figure 3 illustrates the losses and liquid volumes in the compartments
during refueling.   (Note that the two compartments  of  the  secondary
system are not disturbed during* a refueling shutdown.)

-------
111. MATHEMATICAL MODEL DF ACTIVITY BUILDUP
    Figure H illustrates mathematically the transport to  and from  each
of  the  six  compartments previously discussed.  The six compartments
can  be  mathematically  described  by  the   following    differential
equations.
    1)    dAl(t)/dt = P * N*Al(t) + Q*A2(t)
    2)    dA2(t)/dt = T*Al(t) «• V*A2(t) + H*ASG (t)
2)
3)
dA2(t)/dt = T*Al(t)
dA3(t)/dt = U*A2(t) * W*A3 (tj
dAU(t)/dt = -LAMBDA*AU
-3 •• r*^^ « • k  «_9*_ .  ^^^.^ ^** •*_ m ^ « «
    m   QAH jt;/at: = -LiannuA'aH |tj
    5)   dASG(t)/dt = LL*AS*Al(t) + G*ASG(t) * C*ASEC (t)
    6)   dASEC(t)/dt =  (1-LL) *AS*A1 (t) * D*ASG (t) *  F*ASEC(t)

    The left side of each equation is  the  time  rate  of   change  of
activity  in  that  particular   compartment.   The   right side of each
equation is composed of additions and removals of tritium for each  of
the  compartments.  All terms are in units  of Curies/month.   The terms
of the right side of these equations are:
    Equation 1
                   N*Al(t)
    Equation  2
                   Q*A2(t)
               T*Al(t)
                   V*A2(t)
                         Production     of     tritium     in
                         compartment 1     (primary     coolant
                         system) plus release  of tritium into
                         the primary  system   from   fuel  and
                         control rods

                         Radioactive    decay;    intentional
                         removal;  primary  system  leakage to
                         the containment building,   auxiliary
                         building,  and secondary system;  and
                         shimbleed for compartment  1

                         Reactor    water      makeup     from
                         compartment  2   (RMWST)  and   liquid
                         radioactive waste  system

                         Addition of tritium to compartment 2
                         via leakage  collected  in  building
                         drains and primary system  shimbleed

                         Radioactive decay  in  compartment  2;
                         reactor  water makeup to compartment
                         1  from compartment 2; water   makeup
                         to compartment 3  (spent fuel  pit)

-------
    Equation 3
    Equation <*


    Equation 5
    Equation 6
                   H*ASG (t)
U*A2(t)
                   W*A3(t)
-LAMBDA*A4(t)
LL*AS*Al(t)
                   G*ASG(t)
               Blowdown from compartment ASG (steam
               generators)  if blowdown is routed to
               compartment 2
Water makeup to compartment
compartment 2
3  from
                   C*ASEC(t)
Radioactive  decay  and  evaporation
from compartment 3

Radioactive decay in  compartment  U
(refueling water storage tank)

Primary  to  secondary  leakage  and
diffusion  of tritium into the steam
generator liquids

Steam generator blowdown;  carryover
of  tritium  by  the  production  of
steam  in  the   steam   generators;
radioactive   decay   in  the  steam
generators

Feedwater to  the  steam  generators
from  compartment SEC (the remainder
of the secondary system)
(I-LL)*AS*A1(t)Primary  to  secondary  leakage  and
               diffusion  of  tritium  to the steam
               phase of the steam generators
                   D*ASG(t)        Steam   generator   carryover    and
                                  blowdown  of  tritium from the steam
                                  generators to the remainder  of  the
                                  secondary system

                   F*ASEC(t)       Radioactive  decay;  steam  leakage;
                                  condensate   leakage;   air  ejector
                                  partitioning;    steam     generator
                                  feedwater  from the remainder of the
                                  secondary system

    The definitions of the components of each term  are  presented  in
Table  2.  Each of these equations has been solved for the activity in
each compartment as a function of time*.  The  tritium  releases  from
each  compartment  can  be calculated by integrating the activities to
obtain an average activity during an interval of  time.   The  average

-------
activities are then multiplied by the appropriate removal fractions to
obtain  tritium  releases  for  the time interval.  Description of the
computerized models of the six compartments is not presented  in  this
paper,.


IV. PARAMETER SELECTION

    The computer program that utilizes the equations  in  section  III
requires  the  input  of  33 parameters.  The values of the parameters
selected for the base case reactor system are presented  in  table  3.
For   the  computer  analysis,  these  parameters  are  held  constant
throughout the 40 years of operation of a reactor.  Naturally, for  an
actual  reactor system nany of these parameters will vary considerably
fron year-to-year or even month-to-month.  Thus, the  constant  values
chosen  for  the  parameters  are  considered  the  expected long-term
average over the  life  of  the  reactor.   The  following  paragraphs
indicate  the  basis  of these values, and briefly the significance of
some of them.  The symbols and values of the parameters correspond  to
the listing presented in table 3.

A-  Trojan FSAR Data. Chap_ter 11

    The following parameter  values  were  selected  from  the  Trojan
Nuclear  Plant  FSAR«:  V1,V2,V3,V4,V1REF,LIMIT,FSFP,ELSPO,ELSFPR, and
ELRCR.  For other PWRs the four  volumes  selected   (V1,V2,V3,V4)  may
vary  considerably;  however,  for  almost  all  large PWRs, the total
volume of  these  systems  will  be  around  1,000,000  gallons.   The
selection  of  the  volumes of these systems is not significant to the
overall results presented in this paper.  The fraction  of  mixing  of
the  spent fuel pit water  (FSFP) with refueling water during refueling
shutdown for any reactor will be a small fraction of  the  spent  fuel
pit  water  available  (V3) and is not a critical parameter.  The three
evaporation rates, ELSPO, ELRCR, and ELSFPR are extremely critical  to
the results of this paper and to the tritium recycling operations of  a
PWR.   For  a  sensitivity  analysis  of  these three parameters to be
worthwhile, a better data base is required.  It can be  expected  that
the   water  temperatures  of  these  volumes  are  representative  of
operating PWRs.  However, since evaporation rates are  very  sensitive
to   changes   in  water  temperature,  small  changes  in  the  water
temperatures can significantly affect the evaporation rate of tritium.
In actual operation we would not expect the tritium evaporation  rates
to  decrease  significantly  from  the  values  presented  in table 3;
however, the rates can be increased by approximately factors of 2-U by
increasing water temperatures 30-40°F.  As illustrated in Figure 10 of
this paper, evaporation rate  increases  of  a  factor  of  2-4  would

-------
significantly  affect  environmental  releases and intentional removal
rates during the lifetime of the reactor.

B.   PtfR-Gale Code NUREG-0017

    The Nuclear Regulatory Commission  has  issued  NUREG-0017*  which
discusses  the  parameter  values  used  for LPS (primary to secondary
leakage), LST  (steam leak), LCOND  (condensate  leak),  FCO  (Carryover
fraction  in  the  steam  generator) and LL (indicator that primary to
secondary leakage is into the water phase of the steam generator).  We
assumed that the primary to secondary leak rate includes diffusion  of
tritium  through the steam generator walls.  If a large total transfer
of tritium to the secondary system is assumed, its effect upon tritium
buildup and release at the reactor can be ascertained  generally  from
figure  10  of  this  paper.   Variations in the parameter are of less
consequence than variations  in  water  evaporation  rates  that  were
discussed  in  section  IV.A.   We  also assumed that the carryover of
tritium in a steam generator (FCO) is the same as the iodine carryover
presented  in  NUREG-0017.   The  moisture  carryover  of  PWR   steam
generators  is  much lower  (about 0.1%) and may be more representative
of tritium carryover.   This  parameter  requires  some  verification;
however,  this  parameter   (FCO)  has  very little effect upon tritium
buildup or release at a PWR.

C.   Other Parameters

    A number of parameter values  in  table  3  indicate  the  options
chosen for operating the reactor.  First it was decided not to include
planned  releases of tritium from the liquid radioactive waste system,
i.e., this reactor is considered as a  total  tritium  recycle  plant.
Thus  FRM,  FRC  and  FS are 1.0.  The parameter values for FBV, BLDN,
INDBN, and RR  specify  the  mode  of  operation  of  steam  generator
blowdown.    Variations   of  steam  generator  blowdown  options  are
discussed later in this paper.  The secondary system  flow  rates  and
liquid  masses  (STR,MS,MSG)  were selected based on reasonable values
from currently designed large PWRs.  Variations in these parameters do
not have a significant effect on the results of this  paper.   One  of
the  secondary system parameters, the tritium partition factor for the
air ejector  (PAG), was estimated from  available  information  in  PWR
safety  analysis  reports; however, any reasonable value chosen should
not significantly affect the results of  this  paper.   The  years  of
operation   (YROP),  the  range  indicator   (RANGE),  and the volume of
refueling water used during refueling  (V4REF)  were chosen arbitrarily.
If YROP is chosen to be less than 40 years, results of interest can be
extracted from the tables and figures presented.  It is  assumed  that
almost  all the refueling water available  (V4REF) would be used during
a refueling shut down.  The shimbleed  (S) rate that was  chosen  is  a

-------
reasonable  value for large PWRs.  It could vary by a factor of two or
more; however, its value does not significantly affect the results  of
this  paper.   The  containment building leak rate (L) and fraction of
this leakage that remains in the  liquid  phase  (FL)  (and  thus,  is
returned  to  the  liquid  radioactive  waste  system)     were chosen
somewhat arbitrarily.  Values of FL were not  available;  however,  in
choosing the value of 0.5 it is assumed that about half of the leakage
will  be  hot   (thus,  being  in a vapor phase) and about half will be
relatively cold  (thus, remaining as a liquid).  The value selected for
L is higher than the  value  presented  in  NUREG-0017.   The  primary
coolant   leakages  from  systems  in  the  containment  building  and
auxiliary  buildings  were  assumed  to  be  included.   Any   leakage
remaining  as  a  liquid  was assumed to be eventually returned to the
liquid radioactive waste system.  More  information   concerning  these
two  parameters   (L  and  FL)  is necessary, since they can affect the
results of this paper significantly.

D.  Conclusions of Parameter Values

    The major conclusions concerning parameter selection are that more
information is necessary for the parameter values of   (1)  evaporation
rates  (ELSPO,ELSFPR,ELRCR),   (2)  the  transfer  of  tritium  to  the
secondary system  (LPS), and  (3) the  primary  system  leakage  to  the
containment  and  auxiliary  building   (L)  and  the  fraction of this
leakage remaining in the liquid phase  (FL).

    The values of these parameters significantly affect the results of
this paper.  The values chosen for this paper are reasonable, and  the
results  of  this  paper  may  be  generally  applied to a large PWR.
However, for a tritium recycle  analysis  of  a  specific  PWR,  these
parameter  values  should  be  derived for the specific system of that
PWR.

E.  Ranges of Parameter

    The expected ranges for the parameters in table  3 are:

         1)   V1+V2+V3+V4    800,000 - 1,250,000 gallons
         2)   V1REF          30,000 - 40,000 gallons
         3)   V4REF          200,000 - 350,000 gallons
         U)   YROP           30 - UO years
         5)   L              UNKNOWN
         6)   LIMIT          1.0 - 3.0MCi/ml applicable NRC Regulatory
                             Guide for  the  majority of  PWRs.   5.0
                             -7.5pCi/ml  is  applicable for continuous
                             purge systems in containment buildings.
         7)   S              0.7 - 3.0 gpm

-------
         8)    FSFP           0.10 - .20
         9)    ELSPO          25 - 150 gallons/day     (estimate)
         10)  ELSFPR         75 - 300 gallons/day     (estimate)
         11)  ELRCR          300.- 1500 gallons/day   (estimate)
         12)  LPS            0-50 gallons/day  (estimate of  leakage
                             rate    which    also   compensates   for
                             diffusion)
         13)  FL             0.5 - 1.0
         14)  BLDN           0 - 350,000 Ib/hr
         15)  LST            340 - 1700 Ib/hr
         16)  LCOND          UNKNOWN
         17)  MS             1,500,000 - 5,000,000 Ib
         18)  MSG            400,000 - 500,000 Ib. total for all stean
                             generators
         19)  FBV            0 - .33
         20)  PAJ            UNKNOWN
         21)  STR            1,300,000 - 1,700,000 Ib/hr
         22)  FCO            0.0008 - 0.002 or   (moisture  carryover)
                             0.01 - 0.10         (iodine carryover)

V.  ANALYSIS AND RESULTS

    The Trojan reactor components and operational characteristics were
chosen as the base case for a parametric analysis of the  buildup  and
release of tritium at a large PWR.  Table 3 presents the values of the
parameters   (which  are  defined  in table 2) for the base case.  Each
analysis is based  on  the  values  presented  in  table  3  unless  a
different parameter is specifically indicated in the discussion of the
analysis.  The parametric study can be divided into three groups which
are discussed in the following sections.

A.  Annual Tritium Source Term

    Four annual tritium source terms (350; 700; 1,000;  1,400  curies)
were  arbitrarily  chosen  for analysis using the base case parameters
presented in table 3.  Figures 5 and 6 indicate the tritium buildup in
the primary coolant system and the total reactor plant over a 40  year
time  period.   In figure 5 the primary coolant activities represented
by curves 2, 3,  and  4  reach  their  limiting  concentration  (which
corresponds to about 2.5 jiCi/ml concentration) within approximately 12
years.   This  limiting concentration  (about 850 curies in the primary
coolant system for the base case) for the primary  coolant  system  is
controlled  by  the  intentional  removal  of primary coolant liquids.
These removed liquids can either be solidified and disposed  of  at  a
waste  burial ground or treated for selective removal of tritium, if a
system is available, and the tritium then disposed of as a solid.  The
increase in tritium activity in the primary coolant system is  a  slow


                                 10

-------
procass  and  is  also  greatly  influenced  by the activity levels in
compartment 2 (RMWST and  liquid  radioactive  waste  system).    Thus,
intentional  removal  of  tritium can be accomplished effectively from
either the primary system, the RMWST, or the liquid radioactive  waste
system  on  a  continuous  or  batch  basis.   This flexibility allows
selective removal techniques to be utilized that have low  flow  rates
but  which can operate continuously for long periods of time.  Curve 1
indicates that a production term of 350 Ci/yr would not result in  the
limiting  concentration  during  the  normal  lifetime  of  a reactor.
Figure 7 indicates the tritium removal rates (in curies or gallons  of
tritiated  liquids)  that  will be required for various tritium source
terns.  Removal becomes necessary when the annual tritium source  term
in  the primary coolant system reaches 625 curies/year.  Also for each
incremental increase  (above 625 curies) of 100 curies  in  the  annual
source  term  ,.  the  total  volume  of tritiated liquids that must be
removed (over the lifetime of the reactor) from  the  primary  coolant
system increases approximately 400,000 gallons.

    As  indicated  in  figure 8, during the first few years of reactor
operation, it is not necessary to intentionally  remove  tritium  from
the  primary  coolant  system.   However,  it should be noted that for
source terms larger than about 1,000 curies  per  year,  removal  does
become  necessary  within  five  years  after initial operation of the
reactor.

B.  Analysis of a Standard Annual Tritium Source Term of 700 Cj/year

    For an analysis of various aspects of tritium in a PWR, a constant
annual source term of 700 Ci/yr was chosen.   The  selection  of  this
source  term  was  somewhat  arbitrary  but appears reasonable for the
following reasons:

    1)   700 Ci/year  is  consistent  with  tritium  source  terms  of
         operating  reactors  based on available data, as indicated in
         table 4.

    2)   700 Ci/year is a high enough source term so that removal from
         the primary coolant system may be included in the analysis.

    The activity buildup in each compartment and in the total  reactor
plant  is  presented in figure 9.  It should be noted that the primary
coolant system, secondary system, and  reactor  makeup  water  storage
tank   (RMWST) reach a stable activity level much sooner than the spent
fuel pit or the refueling water storage tank.   The  secondary  system
retains  very  little  tritium  and is not a concern at the end of the
plant's useful lifetime.  The equilibrium level  of  tritium  of  this
reactor case is approximately 5,100 - 5,500 curies.


                                 11

-------
    Figure  10  presents the tritium losses and retention for the base
plant design for a 700 Ci/yr source term.  The losses are divided into
three groups - radioactive decay, uncontrolled  environmental  losses,
and  intentional  removal.   Decay  and  environmental losses combined
constitute more than 80X of the total tritium losses from  the  plant.
Each  of  these  loss mechanisms are approximately equal in magnitude.
Note, the intentional removal could  be  discharged  directly  to  the
environment  thus  significantly  increasing  the  fraction of liquids
discharged.  However, in this paper it is  assumed  that  the  liquids
that are intentionally removed from the primary coolant system are not
discharged to the environment.

    The environmental losses are divided into three major categories -
evaporation   (during  normal  operation  from  the  spent fuel pit and
during shutdown from the spent fuel  pit  and  the  refueling  canal),
leakage  from  the  containment  building, and secondary system losses
(primarily from steam leakage and condensate leakage).  About  80%  of
the  environmental  losses  are  from  evaporation and leakages to the
containment building with both pathways being approximately  the  same
over  the  40  year  life  of the plant.  It should also be noted that
intentional removal is assumed to be necessary after 11 years 9 months
of operation.  The hatched area in  figure  10  indicates  the  annual
increase  in  activity  that is retained in the plant.  After about 30
years, the plant activity is stabilized.  Thus, block 3 in  figure  10
is  indicative  of the losses of the system not only for the 40th year
but also for each year from the 30th year through the 40th year.

    Figure 11 indicates the fraction  of  the  environmental  releases
that  are  gases or liquids.  Over the 40 year lifetime of the reactor
almost 90% of the environmental tritium release is expected to  be  in
the  gaseous phase.  All of the tritium which is intentionally removed
during the 40 years  of  operation   (2,780  curies)  and  the  tritium
retained  at  the  end  of the 40 year period  (5,460 curies) is in the
liquid phase.  A determination of the ultimate fate of  these  liquids
is outside the scope of this paper.
                                  12

-------
c'   Effects of Secondary System parameters

    1.   Reactor Losses as a Function of Steam Generator Slowdown

         Figure 12 indicates the effects of recycling steam  generator
    blowdovm  liquids versus routing them directly to the environment.
    The increase in the total environmental releases from the  reactor
    is  less  than  3%  for  direct release of blowdown.  However, the
    gaseous  releases  now  decreased  to  about  80%  of  the   total
    environmental  release  for  the cases with blowdown discharged to
    the environment,  versus  90%  for  the  case  where  blowdown  is
    recycled.   This  results from the liquid releases almost doubling
    while the gaseous releases are decreased by  about  8%.   For  the
    case  of  the  blowdown  routed  to  the  environment, the rate of
    blowdown  has  very  little  effect  on  the  magnitude   of   the
    environmental  releases.   Thus,  blowdown  rates of 5 gpm or even
    several hundred gpm (average annual blowdown rates)  will  produce
    similar results as those presented in Figure 12.

2-   Reactor Losses as a Function of Primary to secondary Leak Rate

    Figure 13  indicates  the  environmental  losses  and  intentional
removcil  necessary  for a reactor with no primary to secondary leakage
and one with an 18.7 gpm leakage rate.  The annual  source  term  used
was   700  curies.   The  radioactive decay losses and the retention of
tritium in the  reactor  are  similar  for  both  primary-to-secondary
leakage  cases   (see  figure  10).  Several conclusions may be reached
concerning  the  results  of  zero  primary-to-secondary  leakage   in
comparison to a reactor with 18.7 gpm leakage.

    1)   There are  no  liquid  environmental  releases;  the  gaseous
         releases  are  9% lower; and total environmental releases are
         19% lower.

    2]i   Intentional removal becomes necessary almost 3 years sooner.

    3)i   The number of curies of tritium that  must  be  intentionally
         removed  is 61% higher  (1,480 curies versus 2,780 curies) and
         the volumes of liquids that are required to  be  removed  are
         67% higher  (500,000 gallons versus 300,000 gallons).
                                  13

-------
D.  Effects of Various Limiting Concentrations

    Table  1  indicates  the   impacts   of   limiting   the   tritium
concentrations  in  the  primary  coolant system of a PWR.  Two source
terms (700 Ci/yr and 1,400  Ci/yr)  were  chosen  and  three  limiting
primary  coolant  concentrations  (2.5,  5.0,  and  7.5  pCi/ml)  were
analyzed for these source terms.  As  discussed  previously,  for  the
base  case  parameters chosen, intentional removal is necessary if the
sourca term is greater than 625 Ci/yr and the  limiting  concentration
is  about  2.5  pCi/ml.   For  the  two higher limiting concentrations
selected, intentional removal would not become necessary until a  much
higher  source term is reached.  For these two cases the environmental
releases, primary coolant concentration, and total curies built up  in
the reactor would stabilize primarily as a result of radioactive decay
in  the  plant and uncontrolled environmental losses.  The significant
environmental losses are from the refueling canal  evaporation  during
refueling,  evaporation  from  the spent fuel pit during refueling and
routine  operation,  primary  system  leakage  into  the   containment
atmosphere with subsequent release to the environment, and release via
secondary system leakages.

    For  the 1,400 Ci/yr source term, intentional removal is necessary
for the 5 jiCi/ml limit but not for the 7.5 pCi/ml limit.  Doubling the
source  term  from  700  Ci/yr  to  1,400  Ci/yr  and   doubling   the
concahtration   limit   from   2.5pCi/ml   to   5.0MCi/ml  results  in
approximately the same  quantity  of  primary  coolant  that  must  be
intentionally   removed   (300,000  gallons  versus  250,000  gallons);
however, the curies of tritium intentionally removed from the  primary
coolant  system  increases  by almost a factor of two  (2,785 curies to
4,525 curies).  Also the initial time period after reactor startup for
commencing removal is fairly close  (12 years 9 months versus 13  years
10 months).

    A  major  conclusion  from  this  overall  analysis is that as the
limiting primary coolant concentration is increased there is a  nearly
proportional  decrease in intentional removal required, an increase in
uncontrolled environmental releases, and an increase in the buildup of
tritium in the reactor.

VI. SIGNIFICANCE OF RESULTS

    The results presented in Section IV will provide  the  information
to  make  an  assessment  of  the environmental and inplant impacts of
decisions related to the recycle of tritiated liquids  in  pressurized
water  reactors.  The data provided in this paper presents an estimate
of the reduction in discharges of tritium  to  the  environment  under
various  conditions;  the rate of buildup and the equilibrium level of


                                  14

-------
tritium in the reactor plant liquids; and the amount of tritium  which
will  be  discharged  to  the  environment  through  plant ventilation
systems and from the secondary system leakages which may be considered
unavoidable.

    Further, this paper indicates  the  time  at  which  the  limiting
conditions  of  operation  will  be attained and the amount of tritium
which would have to be intentionally removed  in  order  to  meet  the
coolant  specification  limits  for a given tritium source term.  This
information will enable an assessment to be made of the rate at  which
tritium  must  be removed from the coolant system and subsequently the
capacity of the tritium removal systems  which  must  be  employed  to
achieve  the  desired ends.  Because of the slow buildup of tritium in
the coolant system, the tritium may be controlled on a periodic, batch
basis during plant shutdowns.  This will be particularly  advantageous
since,  if it is necessary to add a tritium control system, it will be
possible to provide this treatment  capability  independent  of  plant
operation.   Thus,  the  tritium control system will not impact on the
plant reliability and the plant safety during operations.

    In summary this paper, while it has not reached conclusions as  to
the desirability of recycle of tritiated liquids nor the necessity for
provision  of a tritium control system in a pressurized water reactor,
it  has  documented  a  realistic  estimate   of   the   inplant   and
environmental  release  source  terms associated with tritium recycle.
Froai this information the impact on plant personnel, plant  operation,
and  the population doses may be directly evaluated, and decisions may
be made regarding tritium control options.
                                  15

-------
                              REFERENCES
1.   tfilson, Robert L. and  Jay  Y.  Lee.   "Radioactive  Liquid  Waste
    System  for  a  Dry  Site,"  for  presentation  at  the ANS Annual
    Meeting, Las Vegas, Nevada, June 19-22 (1972)
                                                 .
2.   "Technical Paper Oconee Radiochemistry Survey Program," Summary of
    four presentations presented to the American Nuclear Society,  New
    Orleans, Louisiana, June 8-13 (1975).

3.   Final Safety Analysis Report for  Sequoyah  Nuclear  Power  Plant,
    Units 1 and 2, NRC Docket Nos. 50-387 and 388, Appendix 11A.

4.   Korn, G rani no A. Ph.D., and Theresa M. Korn, Mathematical Handbook
    for Scientists  and  Engineers,  Page  416,  Sylvester's  Theorem,
    Second  edition,  McGraw  Hill,  1968 (Library of Congress Catalog
    Card Number 67-16304) .

5.   Final Safety Analysis Report of the Trojan  Nuclear  Power  Plant,
    Docket No. 50-344.

6.   Calculation of Releases of Radioactive Materials  in  Gaseous  and
    Liquid  Effluents from Pressurized Water Reactors (PWR-Gale Code) ,
    NUREG-0017,  Office  of  Standards   Development,   U.S.   Nuclear
    Regulatory Commission, April, 1976.

7.   Gruhlke, James M. , "Pressurized Water Reactor  Effluent  Discharge
    Trends  in  the  United  States,"  U.S.  Environmental  Protection
    Agency,  Office  of  Radiation  Programs,  Technology   Assessment
    Division,   Energy  Systems  Analysis  Branch,  Washington,  D. C. ,
    Presented at the ANS Annual Meeting, June 13-18, 1976, in Toronto,
    Canada.
                                  16

-------
         Table 1.   Effects of Various Limiting Primary Coolant Concentrations
Primary
Coolant
Limit
(uCI/ml)
2.5
5.0
7.5
2.5
5.0
7.5

Source
Term
Tritium
Buildup
After 40
years of
Operation
(Ci/yr) (Curies)
700
700
700
1,400
1,400
1,400
5,500
6,400
6,400
5,700
11,300
12,900
Intentional
Removal

Gallons for
40 years
300,000
0
0
2,900,000
250,000
0

Curies for
40 years
2,7850 )
0
0
28,220(2)
4,525(3)
0
After

Intentional
Removal
105
0
0
770
140
0
                                                           After 40  Years  of  Operation
                                                                 (Curies/year)
                                                                   Environmental
                                                                   Releases

                                                                        290
                                                                        335
                                                                        335

                                                                        310
                                                                        595
                                                                        670
Radioactive
Decay

    305
    355
    355

    320
    625
    710
Intentional  Removal Started After:
  (1)   12  years   9 months
  (2)    3  years   7 months
  (3)   13  years  10 months

-------
                  Table 2.  Parameter Identification
Parameter                    Definition
Al(t),A2(t),A3(t)            Activity of each compartment as a
AU(t),ASG(t),ASEC(t)         function of time, Ci

P                            Production and release  of  tritium  into
                             compartment 1, Ci/month

N                            -LAMBDA-30.U*(L+R+S+LPS)/V1,   fractional
                             removal  per  month from compartment 1 by
                             radioactive   decay,   leakage,   planned
                             removal,   shimbleed,   and   primary ' to
                             secondary leakage, month"1

Q                            30.4*(L+R+S+LPS) /V2, fractional  addition
                             per month to compartment 1 as a result of
                             makeup  from  compartment 2 to maintain a
                             proper   liquid   volume    balance    in
                             compartment 1, month-1

T                            30.U*(L*FL*FRC  +  S*FS)/V1,   fractional
                             addition  per month to compartment 2 from
                             compartment 1 via shimbleed  and  primary
                             coolant   leakage   returned   to  RMWST,
                             month-*

V                            -LAMBDA-30.4*(L+R+S+LPS)/FRM*V2-
                             30.4*ELSPO/V2,   fractional  removal  per
                             month  from  compartment 2 by radioactive
                             decay,  makeup  to  compartment  1,   and
                             makeup to compartment 3, month"1

U                            30.U*ELSPO/V2,  fractional   makeup   per
                             month  to  compartment 3 from compartment
                             2, month"1

W                            -LAMBDA-30.4*ELSPO/V3, fractional removal
                             per   month   from   compartment   3   be
                             radioactive    decay   and   evaporation,
                             month— J
                                  18

-------
                  Table 2.  (Continued)


Parameter                         Definition


H                            30.4*2U*INDBDN*BLDN*(1-FBV)/MSG,
                             fractional   addition   per   month    to
                             compartment  2 from blowdown of the steam
                             generators, month-*

AS                           30.U*LPS/V1,  fractional   addition   per
                             month  from  compartment  1  to the steam
                             generator  liquids  or  secondary  system
                             Steam  via  primary  to secondary leakage
                             and diffusion, month"1

G                            -30.4*24*BLDN/MSG-30.4*24*FCO*STR/MSG-
                             LAMBDA,   fractional  removal  per  month
                             from  the  steam  generators by blowdown,
                             moisture  carryover  in  the  steam,  and
                             radioactive decay, month-1

C                            30.4*24*STR/MS, fractional  addition  per
                             month  to  the  steam generators from the
                             remainder of  the  secondary  system  via
                             feedwater, month-*

D                            30.4*24*FCO*STR/MSG + 30.4*24*RR*BLDN*(1-
                             FBVJMSG,  fractional addition  per  month
                             from   the   steam   generators   to  the
                             secondary system  by  moisture  carryover
                             and   blowdown   routed   to   the   main
                             condensers, month-1

F                            -LAMBDA-(LST+LCOND+STR/PAJ)*30.4*24/MS
                             -30.4*24*STR/MS, fractional  removal  per
                             month   from   the  secondary  system  by
                             radioactive   decay,    steam    leakage,
                             condensate     leakage,    air    ejector
                             partitioning, and feedwater makeup to the
                             steam generators, month-1

V1,V2,V3,VU                  Volumes of compartments 1 through 4, gal.
                                   19

-------
                  Table 2.   (Continued)
Parameter
     Definition
MSG,MS
S

LPS
ELSPO



FL



FS

FRM



FRC



FBV


FCD




BLDN
     Mass  of  liquids   in   the   steam
generators   and  the  remainder  of  the
secondary system, Ibs.

Primary system leakage to the containment
building, gal/day

Shimbleed, gal/day

Primary   to   secondary   leakage    and
compensation  for diffusion through steam
generator tubes, gal/day

Removal  of  tritium  from  the   primary
coolant  system  in  order to control the
primary  coolant  tritium  concentration,
gal/day

Evaporative losses from  the  spent  fuel
pit, gal/day

Fraction of L that remains in the  liquid
phase

Fraction recycle of shimbleed

Fraction recycle of RMWST  flow  used  as
makeup to the primary coolant system

Fraction  of  L*FL   liquids   that   are
recycled
Fraction  of  steam  generator
vented in the gaseous phase
blowdown
Fraction of tritium carried over from the
steam generators to the secondary  system
steam

Steam generator blowdown rate, Ib/hr
                                   20

-------
                  Table 2.  (Continued)
Parameter
     Definition
INDBDN
LST
LCDND
LL
PSJ



STR


RR


LAMBHft.
Indicator, equals 1 if BLDN is routed  to
the; RMWST else it equals 0

Steam leakage from the secondary  system,
Ib/hr

COndensate  leakage  from  the  secondary
system, Ib/hr

Indicator, equals 1 if LPS  is  into  the
steam  generator liquids, equals 0 if LPS
is: into the  steam  phase  in  the  steam
generator

Partition factor of  the  steam  jet  air
ejector

Steaming rate of  the  steam  generators,
Ib/hr

Indicator,, equals 1 if BLDN is routed  to
the main condenser else it equals 0

Radioactive decay constant, month"1
                                  21

-------
                                     Table 3  Base Case Parameters
ro
ro
90000
210000
394000
350000
35000
340000
40
1
68
0
2.5
0.1
2920
0.15
48.4
131
464
18.7
1
0
1
8400
1700
2400
1
2000000
300000
1
0
200000
17000000
0.01
1
VI VOLUME PRIMARY SYSTEM, GAL
V2 VOLUME WATER RADWASTE AND COND STR, GAL
V3 VOLUME WATER SPENT FUEL PIT, GAL
V4 VOLUME WATER REFUELING STR POOL, GAL
V1REF VOLUME PRIMARY WATER IN CORE AT SHUTDN, GAL
V4REF VOLUME REFUELING WATER USED DURING REFUELING
YROP YEARS OF OPERATION
IND2 INDICATOR 0=MULTI-RUNS 1=TABLE, 2=PLOT,  3=ANN
L PRIMARY SYSTEM LEAKAGE GAL/DAY
INDBDN INDICATORS IF BLDN ROUTED TO RMWST ELSE=0
LIMIT TRITIUM CONC LIMIT IN PRIMARY SYS, UCI/ML
RANGE INDICATOR FOR CONTROLLING H-3 CONC, UCI/ML
S SHIMBLEED FLOW, GAL/DAY
FSFP FRACTION MIXING SPENT FUEL WATER W/REFUEL H20
ELSPO EVAP LOSS FROM SPENT FUEL PIT OPERATING, GAL/DAY
ELSFPR EVAP LOSS FROM SPENT FUEL SHUTDN, GAL/DAY
ELRCR EVAP LOSS FROM REFUEL CANAL REFUEL, GAL/DAY
LPS PRIMARY TO SECONDARY LEAKAGE, GAL/DAY
FS FRACTION RECYCLE SHIMBLEED
FL FRACTION PRIM COOL LEAK IN LIOUID
FRM FRACTION RMWST RECYCLED
BLDN SLOWDOWN RATE, LB/HR
LST STEAM LEAK, LB/HR
LCOND CONDENSATE LEAK SEC SYS, LB/HR
FRC FRACTION REACTOR DRAIN RECYCLED
MS MASS SECONDARY SYSTEM, tR
MSG MASS OF ALL STEAM GENERATORS, LB
LL INDICATORS , LPS INTO STEAM GEN LIQ
FBV FRACTION BLDN VENTED AS GAS
PAJ PARTITION FACTOR AIR EJECTOR
STR STEAMING RATE, LB/HR
FCO CARRYOVER FRACTION IN STEAM GENERATOR
RR INDICATORS , ROUTED TO CONDENSER ELSE=0

-------
                   Table 4.  PWR Tritium Releases7
                   Year           Tritium Releases  (Ci/year)

                   1972           10U2
                   1973            715
                   1974            685
Note:    1)   PWRs  (zircaloy Clad Fuel) with at least one  prior year  of
              commercial operation.

         2)   All release data is normalized to a 3400 MWth  reactor
              which operates at full power 80% of the year (292 days) .
              (Note that the operating cases in this paper are  for a
              reactor operating at  full power for 11 months  of  the year).

         3)   Releases per year are assumed to be the same as the  source
              term for the year since none of the reactors employ  tritium
              recycle.
                                  23

-------
                                                                               EQUIPMENT:
                                            U
                                          1



D






4^^
t
i

^^^
1
: i




ro
                                           FIGURE 1 SCHEMATIC OF SYSTEMS
 A. REACTOR & PRIMARY
    COOLANT SYSTEM
 B. STEAM GENERATOR
 C. LETDOWN DEMIN-
    ERALIZER
 D. BORON THERMAL
    REGENERATION SYSTEM
    (WESTINGHOUSE DESIGN)
 E. VOLUME CONTROL
    TANK
 F. SHIM BLEED HOLDUP
    TANK
 G. DEMINERALIZER(S)
 H. BORIC ACID EVAPORATOR
 I.  REACTOR MAKEUP
    WATER STORAGE TANK
    (RMWST)
 J.  REACTOR COOLANT
    DRAIN TANK(S) (RCDT)
 K. SPENT FUEL PIT
 L. REFUELING WATER
    STORAGE TANK
 M. TURBINE
 N. CONDENSER

 O. EVAPORATION

 P.  PRODUCTION, Cl/yr.
 R. REMOVAL FOR TRITIUM
    CONTROL
 S,  SHIM BLEED
 F.  SLOWDOWN (NOTE:

    OPTIONS TO ROUTE: TO

   ENVIRONMENT; MAIN CONDENSER

   RADWASTE SYSTEM, OR RMWST

 U. STEAM LEAK

 V. CONDENSATE LEAK

 W. PRIMARY TO SECONDARY LEAK

 X. PRIMARY COOLANT LEAK

 Y.RACTION OF PRIMARY COOLANT
   LEAK LEAVING AS A GAS

 Z. RADIOACTIVE DECAY

AA. DISCHARGE FROM RCDT

 BB. DISCHARGE OF  SHIMBLEED

 CC. DISCHARGE FROM RMWST

-------
                                                                               AND  6
          PRODUCTION
              IP)

            DECAY
           (LAMBDA)
                                PRIMARY COOLANT
                                SYSTEM
                                A1.V1
                                                          PRIMARY TO
                                                          SECONDARY
                                                           LEAKAGE
                                                            ILPS)
                           REMOVAL FOR
                              TRITIUM
                             CONTROL
                                (R)
             EVAPORATION
               (IFL'L)
ro
in
           OPTION 1
          DISCHARGE
             (01)
             DECAY
            (LAMBDA)
                          C (SEE NOTE)
                               OPTION 2
DISCHARGE
   (D2)
               OPTION 3
DISCHARGE
   (D3)
                                                         O
                                                         Ul
                                                       >2°-
                                                        ui
                                                STEAM
                                             GENERATORS
                                           AND REMAINING
                                           SECONDARY SYSTEM
r
   REACTOR
   MAKEUP
   WATER
   STORAGE
   TANK (RMWST)
   A2. V2
                                                         	I
                                                              MAKEUP FOR
                  SPENT FUEL
                PIT EVAPORATION
                    (ELSPO)
                                                                                            DECAY (LAMBDA)
                                                                                            STEAM (LST)
                                                                 LEAK

                                                              CONDENSATE
                                                                 LEAK
                                                                (LCOND)
                                                                                      j_ DISCHARGE
                                                                    REFUELING
                                                                    WATER
                                                                    STORAGE
                                                                    TANK
                                                                    A4. V4
                                                                                                               DECAY
                                                                                                              (LAMBDA)
                   SPENT
                   FUEL
                   PIT

                   A3. V3
                                                                                                DECAY
                                                                                               (LAMBDA)
                                                                                               EVAPORATION
                                                                                                  (ELSPO)
                    NOTE: IN MODELING THE LEAKAGE AND SHIM&LEED
                          THIS ROUTING OPTION IS ELIMINATED SINCE A
                          SIMILAR CONFIGURATION IS POSSIBLE VIA
                          MANIPULATION OF DISCHARGE OPTIONS.
                                  FIGURE 2 BLOCK DIAGRAM OF SYSTEMS DURING ROUTINE OPERATION

-------
ro
cr
           >•
           <
           O

                en
                2
5
UJ
p
                                            REFUELING
                                            WATER
                                            STORAGE
                                          E TANK
                  o
                  UJ
                  o
REACTOR
MAKEUP
WATER
STORAGE
TANK (RMWST)
V2
                                                    o
                         OL
                         O
                         o.
                         <
                         UJ
                                               U
                                               UJ
                                               O
                                                                 cc.
                                                                 O
                                                                 a.
                                             SPENT
                                             FUEL
                                             PIT
                                             V3
                                                     V3 -FSFP'V3
  IUVUU VOLUME IN PRIMARY COOLANT
         SYSTEM AND REFUELING CANAL
         DURING REFUELING
  YS/SA VOLUME STORED IN RMWST
         DURING REFUELING
  »    \ VOLUME OF SPENT FUEL PIT
         WATER NOT MIXED WITH PRIMARY
         COOLANT
  I    } VOLUME REMAINING
         IN REFUELING WATER
         STORAGE TANK

 DISCHARGE FROM THE REACTOR
  DURING REFUELING
© LAMBDA'AI, A2, A3. A4 (RADIOACTIVE DECAY)
(2) EVAPORATION FROM REFUELING
   CANAL (ELRCR) AND FROM
   SPENT FUEL PIT (ELSFPR)

 FSFP FRACTION OF
 SPENT FUEL PIT
 WATER MIXING
 WITH PRIMARY
 COOLANT SYSTEM
 WATER
                                                    EVAPORATION IN SPENT
                                                    FUEL PIT
                                                                            30.4*ELSFPR''A3*n-FSFP)
                                                                                  V3FSFP«V3
                       EVAPORATION IN REFUELING CANAL

                SCU'ELRCRMAI'VIREF/Vl + A3"FSFP + A4*V4REF/V4)
                            VI +FSFP*V3 + V4REF
                                   FIGURE 3 REFUELING VOLUMES

-------
       COMPARTMENT i
      COMPARTMENT 2
COMPARTMENT 3

' N'AII
P


t)
PRIMARY COOLANT
SYSTEM
Q

VA2(t)

A2(t)

REACTOR MAKEUP
WATER STORAGE
TANK (RMWST)
A2 M. V2
T*


VI (t)
\SG(t»

SPENT FUEL
PIT
A3 (1). V3
WA310
U*A2(t)

N—LAMBDA-p0.4*JL+R+S+LPS)/V1

O"30.4'(L+R+S+LPS)/V2




       COMPARTMENT 4
     REFUELING WATER
     STORAGE TANK
     A4(t). V4
   -LAMBDA*A4(t)
V— LAMBDA-30.4*(L+R+S+LPS)/FRM*V2
  -30.4'ELSPO/V2

T-30.4*«L'FL'FRC+S'FS)/V1

H-30.4*24*INOBDN*BLDN>(t-FBV)/MSG

    COMPARTMENT 6 (SGI
 W— LAMBDA-30.4* ELSPO/V3

 U-30.4*ELSPO/>V2




    COMPARTMENT 6 (SEC)
LL'AS'A
G'ASG(t)

STEAM GENERATORS
ASG(t). MSG
(t)
C


'ASEC(t)

SECONDARY SYSTEM
ASEC(t). MS
(1-LLI
D-A
AS'AI(t)
SG(t)
* \
F*ASEC(t>
1
    AS-30.4*LPS/V1
    G--30.4*24*BLON/MSG
     -30.4*24'FCO'STR/MSG-LAMBDA

    C-30.4'24'STR/MS
                                                                                 0-30.4*24*FCO'STR/MSG
                                                                                   +30.4*24*RR*BLON'(1-FBVI/MSG

                                                                                 F—LAMBDA-(LST+LCOND+STR/PAJ)*30.4'24/MS
                                                                                   -3a4*24*STR/MS
                             FIGURE 4 MATHEMATICAL MODELS OF THE COMPARTMENTS

-------
ro
oo
       CO
       UJ

       oc

       =>
       o


       to
       UJ
       o
       o
       o
       o

       >-
       cc
       tc
       a.
                                                                                          700 Ci/yr SOURCE TERM
                                                                                           z.
                           1400 Ci/yr SOURCE TERM
1000 Ci/yr SOURCE TE RM
                                                                                         350 Ci/yr SOURCE TERM
                                               NOTE: PRIMARY COOLANT CONCENTRATION  LIMITED TO 2.5 pC1/ml
                                  I   I   I  I   I  I   I   I  III
                              I   I  I   I  I   I   I  i
l   I  I   I   I  I   I   1
                                                 15    17   19   21    23

                                                   WAR OF OPERATION
                                                                  35    37
                                   FIGURE 5 PRIMARY COOLANT ACTIVITIES (PRIOR TO REFUELING)

-------
ro    —
                             ANNUAL TRITIUM PRODUCTION
                                      1400 Ci/yr
                                       ANNUAL TRITIUM PRODUCTION
                                                700 Cl/yr
                                                               ANNUAL TRITIUM PRODUCTION
                                                                        350 Cl/yr
                            ANNUAL TRITIUM PRODUCTION
                                    1000 Ci/yr
                                         NOTE:  PRIMARY COOLANT CONCENTRATION LIMITFO TO  2.5
                                                                       I   i  i   i  i   i
                                                   16   18   20    22

                                                  YEAR OF OPERATION
                                          FIGURE 6 PLANT ACTIVITY VERSUS TIME

-------
    5x10*
    4x10*
    3x10°
M

O
o
    2X106
    1x10*
                                                         5x10*
                                                         4x10*
                                                         3x10*
                                                                 o
                                                                 3
                                                         2x10*
                                                         1x10*
                              MOTE:  PRIMARY COOLANT CONCENTRATION
                                     LIMITED TO 2.5  yCi/ml
         500
750
1000
1250
1500
1750
2000
2250
                            SOURCE TERM (P) CURIES/YEAR

                    FIGURE 7 INTENTIONAL REMOVAL VS. SOURCE TERM
                                     30

-------
      50
      40
      30
tn
cc
<
at
      20
      10
                         PRIMARY COOLANT  CONCENTRATION

                         LIMITED TO ?.5
                  I
                    I
                              I
        500
750
1000
1250
1500
1750
2000
2250
                              SOURCE TERM (P) CURIES/YEAR


                   FIGURE 8 TIME UNTIL REMOVAL BEGINS VS. SOURCE TERM

-------
CO





s
z
Ul
13
ii
Ul
1C

ST.
g
OC
Jb
to
Ul
QC

u
z
X
>
Li
<




5000
4500
4000
3500
3000
_ja
IM
1800
1700

1600

1500
1400
1300

1200

1100

1000

900
800
700
600
500
400
300
200
100
                                                      OTAL ACTIVITY IN REACTOR
                                                      REACTOR MAKEUP WATER STORAGE TANK (RMWST
                                                              & LIQUID RADWASTE SYSTEM
                                                                   SPENT FUEL PIT
                                                                      REFUELING WATER
                                                                   PRIMARY COOLANT SYSTEM
                                                                        40TH YEAR OF OPERATION
                                  SECONDARY SYSTEM
                               (-94% IN STEAM GENERATORS)
                            6
12
14
24   26
                     16   18   20   22

                    YEAR OF OPE RATION

FIGURE 9 ACTIVITY BUILDUP IN EACH COMPARTMENT (700 Ci/yr SOURCE TERM)
30   32    34    36
                                                                38
        NOTE:  PRIMARY COOLANT CONCENTRATION LIMITED TO 2.5 uCi/ml

-------
       BLOCK 1
ANNUAL AVERAGES OVER
   A 40 YEAR PERIOD
   BLOCK 2
40 YEAR TOTALS

DECAY
ENVIRONMENTAL
EVAPORATION
CONTAINMENT
SEC. SYSTEM
REMOVAL
RETENTION
Ci/yr
253
241
(101)
(91)
(49)
70*
137
GAL/YR
7500*

DECAY
ENVIRONMENTAL
EVAPORATION
CONTAINMENT
SEC. SYSTEM
REMOVAL
RETENTION
CURIES
10.120
9.640
(4.000)
(3,600)
(2.000)
2,780
5.460
FRACTION OF
GALLONS SOURCE TERM, %
300,000
1.044,000"
36
34
M4)
(13)
(7)
10
20
       BLOCK 3
40TK YEAR OF OPERATION
Ci/yr %
DECAY
ENVIRONMENTAL
EVAPORATION
CONTAINMENT
SEC. SYSTEM
REMOVAL
RETENTION
305
136
99
55
105
0
44
19
14
8
15
0
      •DURING THE YEARS OF
       ACTUAL REMOVAL (12 THROUGH 40)
       THE ANNUAL AVERAGES
       ARE 100 Ci/yr AND 11,000 GAL/DAY
       AND THE CONCENTRATION IS 2.46 p Ci/ml
  •EXCLUDES SECONDARY
   SYSTEM VOLUMES
   WHICH CONTAIN VERY LITTLE TRITIUM
800
                                                    800
                                                           TOTAL SYSTEM LOSSES
                                       ENVIRONMENTAL LOSSES + INTENTIONAL REMOVAL
                                                                   RADIOACTIVE DECAY
                                         95% OF     TOTAL ENVIRONMENTAL LOSSES (UNCONTROLLED)
                                       40TH YEAR EVAPORATION LOSSES
                     REMOVAL BEGINS     ocVcAcr           \      CONTAINMENT BUILDING LEAKAGES
                 AFTER 11 YEARS 9 MONTHS
                                                         INTENTIONAL REMOVAL OR DISCHARGE
                                                          .    SECONDARY SYSTEM RELEASES
                                                          I  I   i  i  i  i  i   i  i   i  i   i
                                         16   18   20   22

                                         YEARS OF OPERATION
                  FIGURE 10 TRITIUM LOSSES FROM BASE PLANT DESIGN (700 Ci/yr SOURCE TERM)
                  NOTE:  PRIMARY COOLANT CONCENTRATION LIMITED TO 2.5 jj Ci/ml

-------
co
^>-
o
Ol
111
lit
cc
300
280
260
240
220
210
200
180
160
140
120
100
 80
 60
 40
 20
            0
                                                                         GASES
ENVIRONMENTAL RELEASES
  GASES   8600   CURIES
  LIQUIDS  1070   CURIES
  GASES    215   Ci/yr
  LIQUIDS    27   Ci/yr
                                                PRIMARY  COOLANT CONCENTRATION LIMITED TO 2.5 pCi/ml
                                                                         LIQUIDS

                       I  I   I  I  I   I  I   I  I  I   I  I   I   I  I  I   I  I  I   I  I   I   I  I   I   I  I   I   I  I  I   I   I  I
                            10   12    14    16   18    20   22
                                          YEARS OF OPERATION
  24
                                                                            26
28   30
32
34
36   38
                        FIGURE 11 LIQUID AND GASEOUS ENVIRONMENTAL RELEASES (700 Ci/yr SOURCE TERM)

-------
         0.0 SLOWDOWN
         RECYCLE TO MAIN CONDENSER
         40 YEAR RELEASES (TOTAL PLANT)
          LIQUIDS = 1070 CURIES
          GASES  = 8600 CURIES
          TOTAL = 9670 CURIES	
                                         8400 LB/HR SLOWDOWN
                                         DIRECT RELEASE TO THE ENVIRONMENT
                                                                          84.000 LB/MR SLOWDOWN
                                                                          DIRECT RELEASE TO THE ENVIRONMENT
                                         40 YEAR RELEASES (TOTAL PLANT)
                                          LIQUIDS = 1996. CURIES
                                          GASES  = 7911 CURIES
                                          TOTAL = 9907 CURIES	
                                                                          40 YEAR RELEASES (TOTAL PLANT)
                                                                            LIQUIDS = 2000. CURIES
                                                                            GASES  = 7907. CURIES
                                                                            TOTAL  = 9907. CURIES
CO
in
O

in
ui
t/j
<
UJ
_J
UJ
cc
55.0

50.0

45.0

40.0

35.0

30.0

25.0

20.0

15.0

10.0

 5.0
          0
                           0.0 SLOWDOWN RECYCLE TO MAIN CONDENSER
                      -8400 LB/HR SLOWDOWN
                        DIRECT RELEASE TO ENVIRONMENT
                      84.000 LB/HR SLOWDOWN
                        IS ESSENTIALLY THE SAME
                                               NOTF:   PRIMARY COOLANT CONCENTRATION LIMITED  TO 2.5 yd/ml
                I  I   I  I   I  I   I  I   I  I  I  I   I  I   I   I
                                                        I  I   I  I   I
                                                                      I  I   I  I   I   I  i  I   I  I   I   I
                                10
                                 12   14
16
18
20
22
24
26   28
30
32   34
36
38
                                               YEARS OF OPERATION
           FIGURE 12 SECONDARY SYSTEM RELEASES VERSUS STEAM GENERATOR SLOWDOWN RATE (700 Ci/yr SOURCE TERM)

-------
                                                   40 YEAR TOTALS

LIQUID RELEASES
GASEOUS RE LEASES
TOTAL ENVIRONMENTAL
RELEASES
INTENTIONAL REMOVAL
RADIOACTIVE DECAY
ACTIVITY RETAINED
REMOVAL (LIQUID VOLUME)
REMOVAL BECAME
NECESSARY AT
0.0 LEAK
RATE
O.O CURIES
7800 CURIES
7800 CURIES
4480 CURIES
10,300 CURIES
5400 CURIES
500,000 GALLONS
8 YEARS, 11 MONTHS
18.7 gpm
LEAK RATE
1070 CURIES
8600 CURIES
9670 CURIES
2780 CURIES
10,120 CURIES
5460 CURIES
300,000 GALLONS
11 YEARS, 9 MONTHS
           KEY
           18.7 PRIMARY TO SECONDARY LEAK

           0.0 gpm PRIMARY TO SECONDARY LEAK
       300
en
       250
                                                                TOTAL ENVIRONMENTAL RELEASES
o
cc.
O

o

LU
DC

5
O
cc
"-  100
CO
LU
       200
       150
    O
        50
                                                             INTENTIONAL
                                                             REMOVAL
NOTE:  PRIMARY COOLANT CONCENTRATION LIMITED  TO 2.5 pC1/ml
                                                                  300



                                                                  250



                                                                  200



                                                                  150



                                                                  100



                                                                  50
                                   I   I  .'l  I   I  I   I
                              8   10    12    14    16    18    20    22   24


                                                  YEARS OF OPERATION
            I   I  I  I   I  I   I   I  I   I  I   I   I  I   I   I  I   I   I  I
                                26    28
                                                                                    30    32
34
36   38
                       FIGURE 13 EFFECT OF PRIMARY-TO-SECONDARY LEAKAGE (700 Ci/yr SOURCE TERM)

-------