SWRHL~36r
    STATUS OF THE NEVADA TEST SITE
           EXPERIMENTAL FARM
Summary Report for July 1964 - December 1965
                     by
              Richard L.  Douglas
     Bioenvironmental Research Program
  Southwestern Radiological Health Laboratory
         U. S. Public Health Service
 Department of Health, Education, and Welfare
              Las Vegas,  Nevada
               January 17,  1967
  This work performed under Memorandum of
        Understanding (No. SF 54 373)
                   for the
     U. S. ATOMIC ENERGY COMMISSION

-------
                                          SWRHL-36r
     STATUS OF THE NEVADA TEST SITE

           EXPERIMENTAL FARM
Summary Report for July 1964  - December 1965
                      by
              Richard L. Douglas
     Bioenvironmental Research Program
  Southwestern Radiological Health Laboratory
          U.  S. Public Health Service
 Department of Health, Education,  and Welfare
              Las Vegas; Nevada

      Copy No. 55

      Donald Hendricks
      Safety Evaluation Division
      NVOO/AEC
      Las Vegas, Nevada
               January 17,  1967
  This work performed under Memorandum of
        Understanding (No. SF 54 373)
                   for the
     U.  S.  ATOMIC ENERGY COMMISSION

-------
                     TABLE OF CONTENTS

I.     INTRODUCTION                                           1
II.    DESCRIPTION OF THE EXPERIMENTAL FARM
      FACILITY                                                 5
      A.  Specific Site  Characteristics                           5
      B.  Cultivated Area                                       5
      C.  Well and Reservoir                                    6
      D.  Irrigation System                                      9
      E.  Other Agricultural Equipment                         11
      F.  Laboratory and Animal Facilities                      12
      G.  Permanent Research and Support Equipment           14
III.   AGRONOMY PRACTICES                                 16
IV.   RESEARCH PROJECTS - PAST AND FUTURE             20
REFERENCES
APPENDIX I    PRECIPITATION DATA
APPENDIX II   IRRIGATION DATA
APPENDIX III  FERTILIZER APPLICATIONS
DISTRIBUTION

-------
                        LIST OF TABLES
Table 1.  Summer weather conditions in Area 15, NTS
          (four-year average).                                   6

Table 2.  Average reservoir leakage losses.                      8
                        LIST OF FIGURES
Figure 1.   Location of PHS facilities on the Nevada Test
            Site.                                                 3

Figure 2.   Plan of experimental farm.                          10

Figure 3.   Area plan of the experimental farm building
            complex.                                           13
                                ii

-------
                       I.  INTRODUCTION

On July 1, 1963, the U. S.  Atomic Energy Commission (AEC) awarded
a contract to the U. S.  Public Health Service, Southwestern Radio-
logical Health Laboratory (SWRHL) to study the transport of radio-
iodine from the environment to  man.  The most pressing problem
was the determination of the passage of radioiodine through the air-
forage-dairy cow-milk-man food chain.  In order to initiate this pro-
gram, the Bioenvironmental Research Program (BRP) was  established
within SWRHL  for the sole  purpose  of developing a field and laboratory
research program which would  answer the questions posed by the AEC.

In addition to this research on radioiodine, the Research Branch of
the Division of Radiological Health, U. S. Public Health Service,  was
seeking answers to questions about  the uptake by plants of long-lived
fission products and neutron activation products in fallout and subse-
quent passage of these  products through man's food chains.  Since
much of the data and information collected in one of these programs
would also be required by the other, it seemed logical to combine the
two to avoid unnecessary duplication of equipment, facilities, and
effort.  Therefore, the Aged Radionuclide Program was formed as a
sub-section of  the BRP with Public  Health Service funding.  The Aged
Radionuclide Program officially came into being on July 1,  1965,
although its requirements had been  considered earlier along with
those for  the BRP.

Because  an extensive effort was to be devoted to the passage of radio-
iodine  through the human food chain, and because this research was
to be conducted under field  conditions, an experimental farm  facility
was  required.  The Nevada Test Site (NTS), with its sources  of

-------
radioactive materials resulting from various  nuclear detonations and



tests,  seemed to be an excellent area in which to develop this experi-



mental farm.  The original concept of the farm included about 30 acres



of irrigated land,  facilities for a 24-cow dairy herd, and a laboratory



building.







Criteria for  the farm site were drawn up and  the search for a specific



location on the NTS was begun in 1963.   Personnel from several



organizations provided helpful consultation and advice regarding site



selection.  These organizations included the U. S. Weather Bureau,



the U.  S.  Geological  Survey,  the  Clark County Agricultural Extension



Service of the University of Nevada, and Reynolds Electric and



Engineering  Co.  (REECo), the prime contractor at the NTS.  Six



different areas were  evaluated in terms of the following criteria:



     1.  A land area  of about 30 acres



     2.  An adequate and dependable water supply for irrigation of



        this acreage



     3.  Accessability



     4.  Availability  of electrical power



     5.  Construction cost (largely influenced by 2, 3, and 4)



     6.  The presence of significant levels of fallout activity which



        would allow  field research by the Aged  Radionuclide Program



     7.  Soil type and growing season which would permit a simulation



        of current farming practices in the southwestern United States








One site was finally selected  as providing the  best compromise with



all these criteria.  This site  was located at Well UE 1 5d in Area 15



near the north end of the  NTS (see Figure 1).  Although some problems



were anticipated in developing the well for our needs, it  seemed to be

-------
I Nuclear Rccket Development Station
                                                 n*      p^ir
                                                 I    Tlpplpoh f
                                                 \     Spring /'.
                                                                                SCALE IN FEET


                                                                                 1    |    I

                                                                           IO,OOO  0  10,000 2O,000 30,000
    Figure 1.  Location of PHS facilities on the Nevada Test Site.

-------
the best overall choice among the water supplies available.  A paved



road approached to within one-quarter mile of the site, and an



electrical power line was located within one mile of the site.  Temper-



ature data collected over several years indicated that the growing



season was adequate for forage and grain crops. This site,  located



about three miles downwind from the Sedan crater, was contaminated



with considerable radioactivity from this  1962 Plowshare event.







Design and construction of the facility  began in the  spring of 1964.



The land clearing and reservoir construction was completed and the



first crop was planted that fall.  However, the laboratory and dairy



facilities  were not completed in time for occupancy before the end  of



this report period.







Seventeen Holstein cows were purchased in April 1964 for use in field



studies that spring.   Since the Experimental Farm  -was not completed



then, they were housed in a  temporary barn and corral at Well 3B,



NTS, (see Figure 1), and fed forage purchased on a contract basis.

-------
  II.  DESCRIPTION OF THE EXPERIMENTAL FARM FACILITY

A.  Specific Site Characteristics
The site is located on a gently sloping alluvial fan in a high desert
valley surrounded by mountains on the east, north, and west.  The
average elevation is 4560 feet and the average land slope is 2-4% to
the southeast.  The soil is a gravelly sandy loam with some cobbles
and stones scattered throughout.  The area has a dense desert cover
of natural vegetation,  predominately black brush (Coleogyne ramosis -
sima),  wolf berry (Lycium andersonii),  small rabbit  brush (Chryso-
thamnus viscidiflorus),  desert needle grass (Stipa speciosa),  four-
wing saltbush (Atriplex canescens),  and Indian rice grass  (Oryzopsis
hymenoides).

Prevailing winds during the spring, summer and fall  are from the
south-southwest during the daytime.  Northerly  drainage winds pre-
dominate during summer nights.  During the winter,  the winds are
predominately from the north with some tendency to reverse during
daytime, but less so than in  summer. General weather conditions in
Area  15, averaged over a four-year period, are presented in Table 1.

B.  Cultivated Area
A roughly square area of about 29 acres lying to the southeast of the
well was graded to remove native vegetation and to smooth a few small
natural drainage  channels.  The  contractor was  asked to disturb the
soil as  little as possible consistent with achieving the desired results.
Some of the larger rocks were removed with a tractor and front-end
loader.  The clearing  job was completed about the end of August  1964,
and the area was  fenced with woven wire fence and three strands of
barbed wire on steel posts.

-------
 Table 1.  Summer weather  conditions in Area 15,  NTS (four-year
          average).
 Month	Apr   May  Jun   Jul   Aag  Sep   Qct

 Average Wind Speed;  (miles per hour)

 Average Speed             10     9     9     9     8     7     8

 Relative Humidity:  (percent)

 Mean maximum            51    44    35    31    40    50    53
 Mean minimum            11    10     9     8    11    14    17

 Temperature: (degrees Fahrenheit)

 Mean maximum            72    76    89    95    92    87    72
 Mean minimum           43    47    58    64    62    55    47

 Average annual precipitation:  4. 5 inches


 C.  Well and Reservoir

Well UE 15d was originally drilled as an exploratory water well.  It

had a seven-inch (outside diameter)  casing from the ground surface

to a depth of 1784 feet.  A 4-1/2 inch lining started at 1667 feet and

went down to  5400 feet.  The static water level was at 670 feet, with

80% of the water coming from an aquifer between 5200 and  5300 feet.

The well was  test pumped at a rate of 78 gallons  per minute.


When the well was drilled,  considerable trouble was encountered with

lost circulation of drilling mud  because the casing was ruptured at

several points.  In an attempt to remedy this  situation, large quan-

tities of  cottonseed hulls,  redwood bark, cement, ground rubber tires

and cellophane were pumped down the well to try to plug the ruptures.

This material was to be flushed out when the well was pumped, but

REECo engineers were afraid that it would ruin a pump.  Therefore

-------
they recommended developing the well by jetting it with an air com-
pressor to clean the well out and test its capacity.

Accordingly, a compressor  was set up and jetting began in May,  1964.
The flow rate ranged from 100 to  150 gpm.  After several weeks  of
testing, some drilling material was still being flushed out.   The
engineers concluded that so  much of this material had been injected
that it would probably never be  completely flushed out.  However,
since compressor jetting would not be a practical method for routinely
producing water, they decided to install a special pump designed  to
handle the drilling  material.

A 73-stage Byron Jackson submersible pump (Model D225B) with
a 180 horsepower,  1040 volt motor was installed at the 1700-foot
level during September  1964.  This pump has  a rating of 200 gpm
at 2000-foot head.  Although this pump was designed to handle small
amounts of this type of material, the  amount pumped out exceeded
the capacity of the  pump and caused pump failure on two occasions.
The pump was replaced in June and again in August 1965.

A flow rate of 550 gpm for about eight hours per day were desired
for the irrigation system. Since a maximum flow rate of about 200 gpm
was anticipated from the well, a storage reservoir was necessary to
keep an adequate water supply available for the irrigation pump.   A
reservoir of about  one million gallons capacity was designed and  con-
structed in the summer  of 1964. The reservoir, of trapezoidal cross
section, was approximately  120 feet square at  the top with a design
water depth of 13 feet.   The porosity  of the soil at this  site required
sealing the sides and bottom of the reservoir.  Bentonite  clay was
used as a sealant.

-------
The reservoir was filled in the fall of 1964, just prior to the  planting

of the first crop.  After filling, it was apparent that the reservoir

leaked badly and it was doubtful if an adequate water  supply for corp

irrigation could be maintained during the summer months.  In the
spring of 1965,  the water in the reservoir was  pumped out and the
sides were coated with cement  grout applied over 2-inch mesh screen.

The bottom of the reservoir was not grouted because the REECo

engineers felt that the thick layer of bentonite on the  bottom (which
had washed off the sides) had sealed it.  However,  the leakage losses

•were still apparent after the grouting.

Data collection was started in June of 1965 so that the actual  reservoir

losses could be  determined.  Since only approximate values were

desired, the leakage losses were calculated as the difference bet-ween
what was pumped  into  and out of the reservoir during a given  period

of time.  If there was  a difference in the water level  in the reservoir

between  the beginning  and end of the period, this was accounted for

in the calculations.


The following table indicates average losses over periods of approx-

imately one month duration.


Table 2.  Average reservoir leakage losses.

Period Covered in 1965          Losses in Gallons per day

June 14 to  July  14                       60,000
July 14 to August  13                     44, 500
August 13 to September 20*              32,000
September 20 to October 20              38,000
October  20 to November 8               33,000
November  8 to December 7              26, 000

*Reservoir nearly empty 30% of the period due to failure of the well
 pump.

-------
The trend of the data indicates a substantial decrease in losses due
to leakage.   This probably resulted from a gradual expansion of the
bentonite with the passage of time, which provided a better seal of
the bottom of the reservoir.

D.  Irrigation System
In the original planning for the irrigation system both sprinkler and
surface flooding methods were considered.  A sprinkler system was
chosen because:  (1) the soil is too porous for a flooding system to
operate efficiently, (2) a flooding system would  require extensive
grading and land leveling, and (3) a sprinkler system allows greater
flexibility.

The irrigation system was installed in the fall of 1964.  It consisted
of a centrifugal  pump mounted on the north bank of the reservoir,
a 900-foot main line, and sixteen 767-foot laterals connected to the
main line at  right angles (see Figure 2).  This  system provided irri-
gation coverage of approximately 16. 5 acres.

The pump (Peerless Mfg. Co.,  Type "A" Size 6A-13) delivers 550 gpm
at 140 feet of head and is powered by a 30 hp -  1750 rpm - 480 volt
electric motor.   At the pump,  a  water meter (Sparling Model CF-115)
indicates both the flow rate and the total gallons of water which have
passed through the meter.  The main line is 6-inch O.D. , 12 gauge
cement-coated steel pipe, buried 18 inches below grade.   The  laterals
are 3-inch O.D. ,  12 gauge,  asphalt dipped, steel pipe, installed on
the ground surface and spaced approximately 60 feet apart.  Each
lateral has 20 Rainbird Model 40B sprinkler heads which at  50 psi
deliver 7. 2 gpm and cover a circle of about 40 feet. The heads
are spaced approximately 40 feet apart and are  mounted 21 inches

-------
7Q
 e
 (V
 3

 O
 i-n

 fD
 X
"0
 CD
      TRANSFORMER STATION
r
                                                                                                       1 LATERAL NO.S

                                                                                                         i
                                SCALE: i" = 200' >,.
                                                                ^
                                                                  BOUNDARY  OF FENCED AREA-

-------
above the lateral on 3/4" galvanized pipe risers.  The water flow

through each lateral is controlled by a gate valve  located just off

the main line.

The system was originally installed with every second lateral 20 feet
shorter than the adjacent one and the heads on alternate laterals

staggered.  Theoretically, this method of spacing should have given
optimum distribution of the water.  However,  in our case it did not,
as there were areas in the middle of the field which did not receive
adequate water.  In addition, the edges of the field were ragged and
hard to farm.  Therefore, in late 1965 the short laterals were
lengthened 20 feet so that the heads on all the laterals are now the

same distance from the main line.

As originally constructed, the  first three laterals joined the main

line at the base of the reservoir bank.  This setup did not leave room
to turn farm machinery without running up on the  bank.  To correct

this situation, in December of  1965 the first 20-foot section of each
of these three laterals was buried to allow turning space.


E.  Other Agricultural Equipment
The following basic pieces of farm machinery were  purchased during

the summer of 1964:

    Tractor                    - Massey-Ferguson Model 35
    Grain drill                  - Massey-Ferguson Model 33
    Forage chopper             - Massey-Ferguson Model Super  60
    Self-unloading wagon        - Gehl Model 85
    Disc                       - Massey-Ferguson Model 25
    Manure spreader           - Massey-Ferguson Model 18
    Manure loader              - Massey-Ferguson Model 38
    Rear-mounted scraper blade - Massey-Ferguson Model 17
    Fertilizer spreader          - Lely Whirlwind
                               11

-------
F.  Laboratory and Animal Facilities
The original concept of the building complex included a 40'x 90' labor-
atory building with milking parlor; an attached 30'x 48' holding barnj
a 120'x 130' corral with feed bunks, water tanks, shade,  and loading
chute; a 26'x 60' hay storage shed and a 26'x 60" machine shed.   Such
a complex was tob  expensive, however, and in the final design the
laboratory building was reduced to 40'x 74' and the holding  barn and
machine shed were deleted.

Sierra Construction Company began construction of the building com-
plex in May 1965.   Figure 3  shows an area plan  of the building com-
plex.

Disposal of the milk from the herd of 24 cows  presented a problem.
Government regulations and  possible radioactive contamination pro-
hibited human consumption.  Disposal to a septic tank was judged
undesirable because of the possible adverse effects the milk might
have on the  biochemical activity in the  tank.  It was decided to use
a liquid manure handling  system to take care  of  both the milk and the
manure which was washed from the barn.  A commercially-available
liquid manure system  designed especially for dairy operations (Easy-
Way Disposal System, manufactured by the Vaughn Co. , Inc.) was
chosen.  This system  consists of an  18, 000-gallon underground con-
crete tank which collects  the manure and milk.  A clock-operated
agitator in the tank keeps the solids in  suspension, and a special
chopper pump empties the tank into a 1100-gallon tank wagon.  The
tank wagon has a spreader with which the contents can be emptied on
the field.
                                12

-------
Figure 3.  Area plan of the experimental farm building complex.
                               13

-------
G.  Permanent Research and Support Equipment
It was  recognized from the beginning of this research project that
weather conditions  affect the passage  of radioiodine through the food
chain,  particularly in the deposition of an aerosol on the ground or
crops.  Therefore, it was desired to have a complete record  of the
micrometeorology of the Experimental Farm.  An agreement was
made with the U. S. Weather  Bureau personnel assigned to the AEC
Nevada Operations  Office to obtain such a record.

The approach used  was to install two permanent instrumentation
towers in the crop area, from which data could be transmitted by
line to readout and  recording  equipment in the telemetry room of
the laboratory.  During 1965, a 30-meter tower was erected at the
midpoint of the No. 6 lateral, a 10-meter tower at the  midpoint of
the No. 12 lateral,  and two electrical  outlet boxes were installed on
each of these laterals (see Figure 2).   Portable one-meter towers
can be plugged into the outlet  boxes and placed anywhere in the crop
area.  Sensors on the towers  are  capable of making the following
measurements:
    30-meter tower
    Wind speed  and direction at one, ten and thirty meters
    Ambient temperature at  one meter
    Temperature difference  between one and ten meters
    Temperature difference  between one and thirty meters
    Dew point at one  meter
    Soil temperature two inches below surface
    10-meter tower
    Wind speed and direction at one and ten meters
    Ambient temperature at one meter
    Temperature difference between one and ten meters
                               14

-------
    One-meter towers (portable)
    Wind speed and direction
    Ambient temperature
    Dew point
    Soil  temperature

At the end of 1965, the meteorology towers and associated power and
telemetry lines were the only equipment permanently installed in the
field.  Installation of the system was essentially complete,  but prob-
lems  were still being encountered with the telemetry equipment.

Other meteorological equipment was set up near the laboratory to
measure insolation, precipitation, and evaporation rate.  Precipita-
tion data from October 1,  1964  through December 1965 are tabulated
in Appendix I.  Insolation and evaporation data for this  reporting
period have not been completely processed.
                               15

-------
                  III.  AGRONOMY PRACTICES

For convenience of operating the farm machinery,  the entire strip
of land between adjacent irrigation laterals was planted to the same
crop.  The laterals were numbered one through sixteen, with lateral
No.  1 being the northernmost one.  (See Figure 2.)  The area between
adjacent laterals is called a land, and the lands are numbered as
shown.   Lands Nos. 1 and 17, being on the ends of the system, are
slightly smaller than the others.  Each of the  15 full-sized lands
(Nos. 2 through 16) is about one acre  in area.

The  cropping  pattern used is  based on the capacity of the  irrigation
system.   The pump was designed  to provide a sufficient flow rate
and pressure  to handle a set of four laterals at once, i. e. , laterals 1-4,
5-8, etc. Each crop type is planted in adjacent lands which are irri-
gated simultaneously by one set of laterals.

When development of the farm site was  begun  in the spring of 1964,
it was hoped that construction would be  finished in time to allow plant-
ing a fall crop in September.  However, due to various delays we
were not able to begin planting until late October.   The local Agricul-
tural Extension Service  agent gave advice pertaining to suitable forage
varieties, seeding rates, and fertilizer application rates  for this area.
Because of the late season, he advised seeding Brevor wheat and
Alpine barley at the rate of 100 pounds of seed per acre.   Hopefully,
these varieties would germinate and become established before cold
weather  set in,  and then make good growth in  the spring.   He also
advised that we apply 100 pounds each of nitrogen  (N) and phosphorus
(P2 O5 ) per acre.
                               16

-------
The phosphorus fertilizer was applied on October 21 and 22, 1964,
with the grain drill, the only  piece of equipment available at that
time.  Treble superphosphate (45%  PzOs) was used as a source of
phosphorus.  An application of 220 pounds of fertilizer per acre
provided the desired 100 pounds  of P2O5 per acre.   The entire field
was disced to cover the fertilizer on October 27.

On October 28,  the lower half of the field (lands 9-17) was irrigated
with 1/4 inch of water prior to planting.  On the same day, lands  1-4
were seeded to Ramona wheat (Brevor wheat seed was not available
locally) and fertilized with 220 pounds of urea (45%  nitrogen) per
acre.  This application rate gave 100 pounds of N per acre.  Lands  5-8
were seeded to Alpine barley  and fertilized with nitrogen at the same
rate as lands 1-4.  On October 29,  the area seeded the previous day
was  irrigated with 1/2 inch of water.  Lands 9-12 were seeded to
barley and lands 12-17 seeded to wheat, and then fertilized with
220 pounds of urea (100 pounds of N) per acre.

The  seed planted in the fall of 1964  did not provide a good crop in
1965.  Apparently, the main reason for  the failure was the fact that
the seed was planted so late that seedlings did not become well estab-
lished before winter.  Consequently, the entire field was replanted
in the spring of 1965.  On May 27, the upper half of the field (lands  1-9)
was seeded with 100 pounds per acre of Alpine barley.  At the same
time, 220 pounds of urea (100 pounds of N) were applied per  acre.
The lower half of the field  (lands 10-17) was fertilized at the same
rate  and seeded with 30  pounds per  acre of Piper Sudan grass.

A heavy infestation of aphids was noticed in mid-June.  On June 28,
the entire field was sprayed with 4-1/2 gallons of 56. 5% Malathion,
applied at the rate of one quart per  acre.
                                17

-------
Approximately 32 tons of surplus ammonium nitrate (33. 5% nitrogen)



was obtained from REECo for use as a top dressing.  On July 13, 1965,



the entire field was top dressed with 340 pounds of ammonium nitrate



(110 pounds of N) per acre.  On August  13,  the Sudan grass was



fertilized with 85 pounds of nitrogen per acre, and on August 18 the



barley was fertilized with  105 pounds of nitrogen per acre.  On



September 12, the Sudan grass was fertilized with an additional



50 pounds of nitrogen per acre, applied as urea.








The Sudan grass  planted on the lower half of the field germinated



well and produced a good stand.  However^  the barley planted at the



same time on the upper half of the field did not make a good crop.



The exact reason or reasons for this poor crop is not known, but



apparently it was due to at least two factors.  It seemed to have been



damaged more by the aphids, and was also hurt  by the lack of water



when  the well pump failed  in June.








On September 16, 1965, the barley in the first nine lands was disced



under.  This area was then fertilized with 300 pounds of treble super-



phosphate (135 pounds P2O5) per acre and seeded with a mixture  of



Kanota oats and Lahontan alfalfa.  The  oats were seeded at the rate



of 35  pounds per  acre,  and the alfalfa at 25 pounds per acre.  Thirty



pounds of nitrogen per acre were applied at the time of  planting.



On September 25, the Sudan grass in lands 10-17 was fertilized



with 25 pounds of nitrogen per  acre.








During October the Sudan grass was harvested with the  forage chopper.



An amount that the dairy cows  could eat was chopped each  day, and



this "green  chop" was taken to the barn at Well 3B and fed to the



cows.  About nine tons  of green chop were cut from lands 10-13





                               18

-------
(approximately four acres).  Lands 14-17 were not harvested because
they were heavily infested with Russian thistle.

When the green chopping was completed in late October, the Sudan
stubble in lands 10-13 was disced three times and the area was seeded
to rye grain.  The area was  fertilized prior to planting with 200 pounds
of treble superphosphate (90 pounds of P2O5) and 300 pounds of
ammonium nitrate (100 pounds of N) per acre.  On November 4, rye
grain was seeded  at the rate of 100 pounds per acre.  An additional
55 pounds of urea (25 pounds of N) per  acre was applied at the time
of planting.   The last four lands  (14-17) were disced and left fallow.
Appendix II shows the amount of water applied by date and the total
amount during the report period.  It should be recognized that all
areas under irrigation did not receive exactly the amount of water
stated.  Some of the factors which cause non-uniform water applica-
tion are evaporation losses,  wind drift of the spray, damaged or
improperly adjusted sprinkler heads,  irregular spacing of laterals
and heads, and leaks in the system.

The types and amounts of fertilizer applied by date  and the total
amount applied during the  report period are summarized in Appendix III.
                                19

-------
        IV.   RESEARCH PROJECTS - PAST AND FUTURE








Only one major  experiment, designated Project Hayseed, was per-



formed at the Experimental Farm during the reporting period.  On



October 4, 1965, a diatomaceous earth aerosol tagged with J 3 11 was



released over a section of growing Sudan grass, a stack of spread



hay, and a stack of spread  green chop.  The growing Sudan grass



was cut as green chop, and each of the three types of contaminated



forage were fed to groups of lactating dairy cows.  An additional



group of cows was placed in the aerosol cloud for an inhalation study.



The levels of l 31I in the milk were related to l 31I concentrations in



forage and air.  Further details  of this study have been published in



References  1  and 2.








Two major experiments are planned for 1966.  In the early summer,



a dry aerosol tagged with 131I is to be released over a mixed stand



of oats  and alfalfa (Project  Alfalfa) in a study very similar to Project



Hayseed.  A study is planned  for late  summer where a 13ll tagged



solution will be  sprayed over  a portion of the field to simulate the



"rainout" of radioiodine (Project Rainout).






Experiments will be started within the Aged Radionuclide Program to



study the movement in the soil and the uptake by plants of the long-



lived radionuclides from Sedan fallout.  An  auxilliary  irrigation system



is planned which will allow  irrigation  of small  plots  of undisturbed



soil.  These micro plots will  be  used  for experiments and pilot studies



which could not  conveneintly be conducted in the main  crop area.
                                20

-------
                          REFERENCES







1.   Earth, D.S.,  nl 31I Dairy Cow Uptake Studies Using a Synthetic



    Dry Aerosol", SWRHL-28r, to be published.





2.   Earth, D.S. ,  and Seal, M. ,  "Radioiodine Transport Through the



    Ecosystem, Air-Forage-Cow-Milk Using a Synthetic Dry Aerosol",



    Radioecological Concentration Processes, Proceedings of an



    International Symposium held in Stockholm,  April 25-29,  1966.
                               21

-------
                          APPENDICES






APPENDIX I.     PRECIPITATION DATA                        22



APPENDIX II.    IRRIGATION DATA                            24



APPENDIX III.   FERTILIZER APPLICATIONS                  30

-------
                           APPENDIX I

                      PRECIPITATION DATA
The precipitation gauge was  set up at the Experimental Farm on

October  1, 1964.  The daily  precipitation (in inches) is tabulated

by months during the report  period.
DATE

October 29, 1964
       Total:

November 9, 1964
          10
          13
          15
          16
          17
       Total:

December 2, 1964
          11
          19
          28
          31
       Total:

January 7, 1965
       19
       Total:

February  6, 1965
INCHES

 0. 06
 0. 06
 0. 10
 0. 05
 0. 03
 0. 04
 0. 27
 0. 02
 0. 51

 0. 01
 0. 02
 0. 02
 0. 03
 0. 02
 0. 10

 0. 09
 0. 02
 0. 11
 0. 01

March




April






1
1
1
1

Total:
12, 1965
13
27
31
Total:
1, 1965
2
3
4
6
8
9
0
1
2
3
Total:
0. 01
0. 69
0. 20
0. 08
0. 17
1. 14
1. 09
0. 09
0. 58
0. 50
0. 01
0. 17
0. 15
0. 15
0. 02
0. 27
0. 12
3. 15
DATE

May 2, 1965
     3
    14
    22
    24
        Total:

June 3, 1965
    16
    25
        Total:

July 15, 1965
     16
     17
     18
     19
     24
     25
     31
        Total:

August 10, 1965
        11
        12
        13
        15
        16
        17
        18
        Total:

September,  1965

October, 1965
INCHES

 0. 01
 0. 03
 0. 05
 0. 05
 0. 02
 0. 16

 0. 13
 0. 01
 0. 01
 0. 15

 0. 01
 0. 08
 0. 04
 0. 01
 0. 01
 0. 10
 0. 04
 0. 10
 0. 39
 0. 07
 0. 01
 0. 11
 0. 02
 0. 30
 0. 34
 0. 01
 0. 12
 0. 98
                                (22)

-------
DATE
INCHES
November 14, 1965
15
16
17
18
22
23
24
25
Total:
0. 15
0. 13
0.64
0.48
0.06
1.08
0.06
0.03
0.03
2.66
DATE

December  9,
          10
          11
          12
          13
          29
          31
       Total:
                                                 1965
INCHES

  1. 13
  0.02
  0.03
  0.05
  0, 01
  1.40
  0. 04
  2.68
               Total precipitation for report period

              October 1,  1964 to December 31, 1965

                         = 12. 10 inches
                               23

-------
                          APPENDIX II

                       IRRIGATION DATA


The water applied during  the reporting period is tabulated by date of

application and by four sets of laterals.  The figures recorded are

gallons  of water applied,  as determined by the difference between

the irrigation pump meter readings before and after irrigation. The

gallons  of water applied through each set of laterals is totaled for

the period of October  28,  1964 to  May 31,  1965, and monthly there-

after to the  end of 1965.  Each of  these totals  is converted to inches

of water applied, using the conversion factor of  28,000 gallons through

four laterals being approximately equal to one-quarter inch of water

over the area covered. The water depths are rounded to the nearest

one-quarter inch. The total depth of water applied through each set

is summarized at the  end of the Appendix.
                      Gallons Applied
                      Lateral Numbers
DATE
Oct
Oct
Oct
Nov
Nov
Dec
Dec
Mar
Mar
>\;
May
28, 1964
29
31
2
6
11
17
2, 1965
8

24
1
--
57
44
57
28
28
28
28
28
47
--
- 4
--
, 000
,000
, 000
,000
, 000
,000
,000
,000
, 000
--
5 .
--
57
45
57
28
28
28
28
28
47
--
- 8
--
, 000
,000
,000
,000
, 000
,000
, 000
,000
,000
--
9 •
28
--
44
57
28
28
28
5
--
47

-12
, 000
--
, 000
, 000
, 000
, 000
,000
,000
--
,000
--
13
28
--
45
57
28
28
28
--
--
47
6
-16
, 000
--
,000
, 000
,000
,000
, 000
--
--
, 000
,000
TOTAL,
56,
114,
178,
228,
112,
112,
112,
61,
56,
188,
6,
000
000
000
000
000
000
000
000
000
000
000
*No record of how this water was applied since it was done by REECo
 personnel testing irrigation system.  Assumed to be applied uniformly
 over the field.
                                24

-------
Lateral Numbers
DATE
May 26, 1965
May 28
May 31
Total gallons
applied during
period
Inches of water
applied during
period
June 2, 1965
June 4
June 7
June 9
June 1 1
June 14
June 16
June 18
June 21
June 23
Total gallons
applied in
June
Inches of
water applied
in June
July 1, 1965
July 6
July 9
July 12
July 13

1 - 4
57,000
57,000
57,000
516,000
4-1/2"
57,000
28,000
28,000
28,000
28,000
28, 000
28,000
28,000
36,000
28,000
317,000
2-3/4"
57,000
29,000
58,000
58,000
58,000

5-8
57.000
57,000
57,000
517,000
4-1/2"
57,000
28,000
28,000
28,000
28,000
28,000
28,000
28,000
28,000
34,000
315,000
2-3/4"
56,000
29,000
58,000
58,000
58,000
25
9 -12
57,000
14,000
57,000
393,000
3-1/2"
57,000
28,000
28,000
28,000
28,000
28,000
28,000
28,000
28,000
	
281,000
2-1/2"
28,000
29,000
58,000
58,000
58,000

13-16
57,000
57,000
57,000
438,000
3-3/4"
57,000
28,000
28,000
28,000
28,000
28,000
29,000
28,000
28,000
28,000
310,000
2-3/4"
28,000
29,000
60,000
58,000
58,000

TOTAL
228,000
185,000
228,000
1,864,000
228,000
112,000
112,000
112,000
112,000
112,000
113,000
112,000
120,000
90,000
1,223,000
169,000
116,000
234,000
232,000
232,000


-------
Lateral Numbers
DATE
July 14, 1965
July 16
July 19
July 21
July 23
July 26
July 28
July 30
Total gallons
applied in
July
Inches of
water applied
in July
Aug 2, 1965
Aug 4
Aug 6
Aug 9
Aug 11
Aug 13
Aug 18
Aug 26
Aug 27
Aug 30
Total gallons
applied in
August
Inches of
water applied
in August
1 - 4
29,000
58, 000
58,000
58, 000
29, 000
58,000
58,000
29,000
637,000
5-1/2"
58,000
67, 000
58, 000
58, 000
63,000
66, 000
58,000
	
	
52, 000
480,000
4-1/4"
5-8
29,000
58,000
58,000
58,000
34, 000
58,000
58, 000
29, 000
641,000
5-1/2"
58, 000
58, 000
58, 000
58, 000
58,000
58,000
58,000
	
	
51, 000
457, 000
4"
9 -12
29, 000
58,000
58, 000
58, 000
29,000
58,000
58,000
29,000
608,000
5-1/4"
58, 000
58, 000
58, 000
61,000
58, 000
48,000
	
	
58,000
58,000
457,000
4"
13-16
29,000
58,000
58,000
58,000
29, 000
59, 000
58,000
29,000
611,000
5-1/4"
58,000
73, 000
58, 000
58,000
58, 000
74,000
	
58,000
	
58, 000
495,000
4-1/2"
TOTAL
116,000
232,000
232,000
232, 000
121,000
233,000
232,000
116,000
2,497,000
232,000
256,000
232,000
235, 000
237,000
246,000
116, 000
58,000
58,000
219,000
1,889,000

     26

-------
                          Lateral Numbers
DATE
Sept 1, 1965
Sept 2
Sept 3
Sept 6
Sept 9
Sept 10
Sept 12
Sept 17
Sept 20
Sept 21
Sept 22
Sept 23
Sept 25
Sept 26*
Sept 27
Total gallons
applied in
September
Inches of
water applied
in September
1 - 4
29,000
	
58,000
58,000
29,000
58,000
	
58,000
46,000
36,000
39,000
29,000
58,000
30,000
73,000
601,000
5-1/4"
5-8
	
58,000
58,000
58,000
29,000
58,000
	
58,000
46,000
36,000
39,000
29,000
58,000
30,000
35,000
592,000
5-1/4"
9 -12
87,000
	
87,000
58,000
58, 000
	
87,000
58,000
58,000
	
58,000
	
58,000
30,000
58,000
697,000
6-1/4"
13-16
87,000
	
87,000
58,000
58,000
	
87,000
58,000
58,000
	
	
	
58,000
30,000
62,000
643,000 2,
5-3/4"
TOTAL
203,000
58,000
290,000
232,000
174,000
116,000
174,000
232,000
208,000
72,000
136,000
58,000
232,000
120,000
228,000
533,000

*Between September 25 and September 27, the records on 120,000 gallons
of water were lost. It was assumed to be applied uniformly over the
entire field on September 26.
*Sept 28-
Oct 4, 1965
Oct 5
Oct 6
Oct 7
200,000
30,000
36,000
32,000
200,000
58,000
46,000
29,000
200,000
74,000
29,000
70,000
200,000
58,000
29,000
29,000
800,000
220,000
140,000
160,000
*During this period, the records on 798, 000 gallons of water were lost.
 However, this water was known to be applied approximately uniformly
 over the entire field.
                                27

-------
Lateral Numbers
DATE
Oct 8, 1965
Oct 9
Oct 11
Oct 12
Oct 13
Oct 14
Oct 15
Oct 16
Oct 18
Oct 20
Oct 21
Oct 23
Oct 25
Oct 26
Oct 29
Total gallons
applied in
October
Inches of
water applied
in October
Nov 1, 1965
Nov 3
Nov 4
Nov 5
Nov 8
Nov 10
Nov 12
Nov 18
Total gallons
applied in
November
Inches of water
applied in Nov
1 - 4
35,000
94,000
29,000
29,000
29,000
42,000
34, 000
29, 000
29, 000
29, 000
29,000
29.000
15,000
29,000
58,000
837, 000
7-1/2"
48,000
	
	
29,000
66,000
	
23,000
18,000
184,000
1-1/2"
5-8
29,000
29, 000
29, 000
29, ooo
60, 000
51,000
51,000
29, ooo
29,000
29, 000
29,000
29,000
16,000
29, 000
95,000
896,000
8"
48,000
	
58, 000
29,000
29, 000
	
29,000
	
193,000
1-3/4"
(28)
9 -12
58,000
58, 000
70,000
29, 000
72, 000
	
53,000
	
	
	
	
	
	
	
53, 000
766,000
6-3/4"
68,000
84, 000
29,000
29,000
18,000
29,000
	
257,000
2-1/4"
13-16
94, 000
39,000
42,000
	
15,000
	
58,000
30,000
48,000
21, 000
	
29,000
29, 000
	
	
721, 000
6-1/2"
	
	
	
	
	
29,000
	
29. 000
1/4"
TOTAL
216,000
220,000
170,000
87,000
176,000
93,000
196,000
88,000
106,000
79,000
58,000
87,000
60, 000
58,000
206,000
3,220,000
96, 000
68,000
142,000
87,000
124,000
18, 000
110,000
18,000
645,000


-------
Lateral Numbers
DATE
Dec 7, 1965
Total gallons
applied in
December
Inches of
water applied
in December
1 - 4
29,000
29,000
1/4"
SUMMARY OF
DATE
Oct, 1964 thru
May, 1965
June, 1965
July, 1965
August, 1965
Sept, 1965
Oct, 1965
Nov, 1965
Dec, 1965
Total for period:

1 - 4
4-1/2"
2-3/4"
5-1/2"
4-1/4"
5-1/4"
7-1/2"
1-1/2"
1/4"
31-1/2"
5-8
29,000
29,000
1/4"
9 -12
58,000
58,000
1/2"
INCHES OF WATER
Lateral
5-8
4-1/2"
2-3/4"
5-1/2"
4"
5-1/4"
8"
1-3/4"
1/4"
32"
Numbers
9 -12
3-1/2"
2-1/2"
5-1/4"
4"
6-1/4"
6-3/4"
2-1/4"
1/2"
31"
13-16 TOTAL
	 116,000
	 116,000
0
APPLIED

13-16
3-3/4"
2-3/4"
5-1/4"
4-1/2"
5-3/4"
6-1/2"
1/4"
0
28-3/4"
      29

-------
                              APPENDIX III



                       FERTILIZER APPLICATIONS





Nitrogen was applied as urea (45% nitrogen) or ammonium nitrate (33. 5%



nitrogen).  Phosphorus was applied  as treble superphosphate (45% PzO5).



Fertilizer applications are expressed as units,  or pounds,  of actual



nutrient per acre.



                        Lands 1-4   58        9-12      13-17
DATE
10/21-
22/64
5/27/65
7/13/65
8/13-
18/65
o / i 9 / At;

9/16/65
9/25/65
1 0/28 /65

1 1 /04/65

Jt orm oi 	 — — -r-
NITROGEN N 2 5
Urea 100 100
Urea 100 	
Ammonium
Nitrate
Ammonium
Nitrate
TTri=>a 	

Urea 30 135
TJrpa 	
Ammonium
Nitrate


N P2o5 N P2o5 N P2o5
100 100 100 100 100 100
100 --- 100 --- 100 	
110 --- 110 --- 110
105 --- 85 	 85 	
RO ^0

30 1^5
	 	 7c oc
- inn on inn on

25 25

           TOTALS:     445   235    445   235   595    190    595   190
                                    30

-------
                         DISTRIBUTION
 1  - 20   SWRHL, Las Vegas, Nevada
    21   .lames K. Reeves, Manager, NVOO/AKC. I,,IK Veyas,  Nevada
    22   Robert H. Thalgott,  NVOO/AEC, Las Vegas, Nevada
    23   Chief, NOB/DASA, NVOO/AEC,  Las Vegas, Nevada
    24   Donald Edwards, Safety Evaluation Div. ,  NVOO/AEC,  Las Vegas
    25   DOS,  USAEC, Washington, D.  C.
    26   JohnS.  Kelly, DPNE,  USAEC, Washington,  D.  C.
27  - 28   Philip W. Allen,  ARFRO/ESSA, NVOO, Las Vegas,  Nevada
    29   G. D. Ferber,  ARL, ESSA, Washington,  D.  C.
30  - 34   Charles L. Weaver,  NCRH, USPHS,  Rockville, Maryland (5)
    35   Program Director, NCRH, USPHS Region IX, San Francisco
    36   Bernd Kahn,  DRH, RATSEC, Cincinnati,  Ohio
    37   Northeastern Radiological Health Lab. , Winchester,  Mass.
    38   Southeastern Radiological Health Lab. , Montgomery, Ala.
    39   William C. King, LRL, Mercury, Nevada
    40   John W.  Gofman, LRL, Livermore, California
    41   William E. Ogle, LASL, Los Alamos, New Mexico
    42   Ed Fleming,  LRL, Livermore, California
    43   Harry S. Jordan, LASL, Los Alamos, New Mexico
    44   H. J. Reynolds, LRL,  Livermore, California
    45   Roger E.  Batzel, LRL, Livermore, California
    46   Victor M. Milligan,  REECo. , Mercury; Nevada
    47   Clinton S. Maupin, REECo. , Mercury, Nevada
    48   Director, DMA, USAEC,  Washington, D. C.
    49   Byron Murphey, Sandia Corporation, Albuquerque, New Mexico
    50   USGS, Las Vegas, Nevada
    51   T. L. Jackson,  Soils Dept. , OSU,  Corvallis, Oregon
    52   R. H. Wilson,  University of Rochester, Rochester; N. Y.

-------
     53   Verle Bohman,  College of Agriculture,  U of N, Reno, Nevada



     54   Clifton Blincoe, College of Agriculture, U of N, Reno,  Nevada



55 - 58   Donald Hendricks,  Safety Evaluation Div. , NVOO/AEC, Las  Vegas (4)



     59   Mail & Records, NVOO/AEC,  Las Vegas, Nevada



     60   DTIE, Oak Ridge,  Tennessee




     61   Library,  Nevada Southern University, Las Vegas,  Nevada

-------