United States
           Environmental Protection
           Agency
             Office of
             Emergency and
             Remedial Response
E PA/ROD/R01 -88/032
September 1988
&EPA
Superfund
Record of Decision
           Landfill & Resource Recovery, Rl

-------
 30277-101
  REPORT DOCUMENTATION
         PAGE
                        1. REPORT NO.

                        	EPA/ROD/R01-88/032
3. Recipient's Accession No.
  4. Titl* and Subtitle
   SUPERFUND RECORD OF DECISION
Lcandfill & Resource Recovery,  RI
•FjjisJi Remedial  Action - Final
^. Auth
                                                                        5. Report Oitt
                                                                                      09/29/88
7. Author<»)
                                                                        8. Performing Organimation Rapt. No.
  9. Performing Organization Nam* and Address
                                                                          10. Project/Task/Work Unit No.
                                                                          11. Contract(C) or Grant(G) No.
                                                                          (G)
  12. Sponsoring Organization Nam* and Address
   U.S.  Environmental Protection  Agency
   401  M Street,  S.W.
   Washington,  D.C.   20460
                                                                        13. Typ* of Report & Period Covered

                                                                          800/000
                                                                        14.
 IS. Supplementary Notes
 16. Abstract (Limit: 200 words)
     The Landfill  &  Resource  Recovery  (L&RR)  site is located in North  Smithfield, Rhode
   Island, and  consists of a  28-acre landfill and a sand  and gravel pit.   Several unnamed
   streams lie  to  the south and east of the  site and flow through wetlands located .adjacent
   to the site  area.  Several  homes near the  site use ground water for  drinking, and  the
   Statesville  reservoir, used for recreational activities,  is located  approximately
   0.5 mile from the site.  The L&RR site  is  a former sand and gravel  pit that began
    ccepting domestic, commercial, and industrial wastes  in  1927.  Site owners claim  the
   hazardous materials were mixed in with  municipal refuse and deposited  in the
   north-central area of the  site, but other  reports indicate hazardous waste was spread
   over the entire site area.   When hazardous waste disposal ceased in  1979 the owners
   placed a PVC cover over the north-central  area to prevent stormwater infiltration.
   Commercial and  domestic wastes were disposed of on top of and around the area in
   subsequent years.  In 1983, the Rhode Island Department of Health installed monitoring
   wells onsite to ensure compliance with  State regulations, and based  on sampling results,
   ordered the  site  closed.   Upon final closure in 1985 the  owners covered 80 percent of
   the landfill area with one  foot of sand,  another synthetic cover and topsoil.  Eighteen
   gas vents'were  installed to vent gases  underlying the  synthetic cover.  The sand used as
   (See Attached Sheet)
 17. Document Analysis  a. Descriptors
   Record of  Decision
   Landfill & Resource Recovery,  RI
   First Remedial  Action - Final
   Contaminated  Media:  air
   Key Contaminants:   hydrogen  sulfide, methane, VOCs  (benzene, PCE, TCE,  toluene)
    b. Identifiers/Open-Ended Terms
   c. COSATI Field/Group
   Availability Statement
                                                          19. Security Class (This Report)
                                                              None	
                                                          20. Security Class (This Page)
                                                              None
                                                                                  21. No. of Pages
                                                                                      154
                                                                                  22. Price
(SeeANSI-Z39.18)
                                         See Instructions on Reverie
                                                                                   OPTIONAL FORM 272 (4-77)
                                                                                   (Formerly NTIS-35)
                                                                                   Department of Commerce

-------
EPA/ROD/RO1-88/032
Landfill & Resource Recovery,  RI
pirst Remedial Action - Final

16.  ABSTRACT (continued)

final cover has eroded into the adjacent wetlands, but sampling indicated no
contamination was present.   Low levels of VOCs and metals including lead, cadmium,  and
arsenic were discovered in downgradient ground water samples,  but levels were sporatic
and all were below MCLs.  This remedial action will upgrade the existing landfill
enclosure ho protect ground water and wetlands, implement wetlands recovery operations,
and collect and treat landfill gas to reduce risks to public health from inhalation.
Primary contaminants of concern affecting the air are hydrogen sulfide and methane  gases
contaminated with VOCs including benzene, toluene, PCE, and TCE.

  The selected remedial action for this site includes:  access restrictions;
stabilization of the steep side slopes of the landfill and installation of a RCRA cap
over the entire landfill,  with revegetation; collection and thermal destruction of
underlying gases, the method of thermal destruction to be determined in design;
excavation of eroded landfill  sand from the wetlands, with replacement onsite, and
vegetation of excavated wetland areas; and ground water and air monitoring.  The
estimated present worth cost of the selected remedy is between $5,674,000 and
$6,790,000, depending on the particular method of slope remediation and thermal
destruction chosen.  O&M costs were not provided.

-------
         UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                             "EOIONI
          J.F. KENNEDY FEDERAL BUILDING, BOSTON, MASSACHUSETTS 02203-2211
                        RECORD OF DECISION

             Landfill t Resource Recovery (LSRR)  Site
                  Horth Smithfield, Rhode Island
8TATEXEHT OF PURPOSE

This Decision Document represents tbe selected remedial action
for the Landfill i Resource Recovery (LiRR) Site developed in
accordance vith the Comprehensive Environmental Response,
Compensation and Liability Act of 1980  (CERCLA), as amended toy
the Superfund Amendments and Reauthorization Act of 1986  (SARA)/
and to the extent practicable, the National Contingency Plan
(KCP) 40 CFR Part 300 et sea.. 47 Federal Register 31180
(July 16, 1982), as amended.  The Region I Administrator has been
delegated the authority to approve this.Record of Decision.

The state of Rhode Island has concurred vith the components of
the selected remedy vhich are consistent vith the 1983 court
Order and Consent Agreement between the Rhode Island Department
of Environmental Management (RIDEM) and Landfill & Resource
Recovery (LiRR), Inc.  In regards to the additional requirements
established by EPA, the State of Rhode Island recognizes that
these requirements are not inconsistent vith the 1983 Court Order
and provide additional protection.  The State of Rhode,Island has
also determined, through a detailed evaluation, that the
selected remedy is consistent vith Rhode Island lavs and
regulations.


8TATEHBBT OF BASIS
This decision is based on the administrative record vhich vas
developed in accordance vith Section 113(X) of CERCLA and vhich
is available for public reviev at the Korth Smithfield Municipal
Annex Building and the EPA Region I Waste Management Division
Records Center in Boston.  The attached index identifies the
items vhich comprise the administrative record upon vhich the
selection of the remedial action is based.

-------
            or m SELECTED REMEDY

Tbe selected remedy ha* four major components vbieb togetber form
• eomprebensivo approacb to Site remediation.
                                                           •
1. Upgrading tbe Landfill closure
                                                   •   *

Tb« •sitting landfill closure will be upgraded to protect tbo
groundvater, to protect tbe vetlands and to meet ARARs.
Upgrading tbe landfill closure includes installing a fence;
developing a post-closure monitoring plan; upgrading tbe surface
vater runoff management system; stabilising tbe stoop sido slopes
and installing a syntbetio eover on tbo uncovered nortbeast area
of tbe landfill; estafelisbing a cover tbiokness of 24 inebesi and
establisbing vegetation.  Tbe syntbetio cover vill proteet tbe
groundvater fej minimising infiltration.  Upgrading tbe existing
surface v&tex management system, stabilising tbe steep'side
slopes and establisbing vegetation vill protect tbe vetlands'by
minimising erosion.  All of tbe components contribute to tbe
remedy attaining JUftARs.

Two alternatives bave been selected for stabilising tbe steep
slopes.  Tbe specific alternative vill be selected during tbe
design pbase of tbe remedial action after slope stability tests
are conducted.


2. Qmm Collection and Tbermal Destruction

Tbe landfill gas vill be treated to reduce tbe potential risks to
public bealtb from inbalation of tbe landfill vent emissions.
Tbe existing landfill vents vill be utilised to collect tbe
landfill gas.  Tbese vents vill be manifolded by a subsurface
piping system vbieb vill direct tbe gaseous emissions to tbe
treatment system.

Tbree tbermal destruction tecbnologie* bave been selected to
treat tbe gaseous emissionsi combustion, flaring and
incineration.  All of tbese tecbnologies burn tbe landfill gas to
destroy tbe basardous constituents.  Typically, tbese
tecbnologies can destroy betveen *0% and t»% of tbe contaminants
in tbe gas tbat enters tbe system.  Tbe specific technology to be
utilised for tbermal destruction vill be ebosen by EVA during tbe
design pbase after pilot tests bave been conducted to insure tbat
tbe remedy is protective.

3. Wetlands Remediation

During tbe Remedial Investigation, tvo areas of tbe vetlands vere
identified as needing remediation due to cover material erosion
and subseguent sedimentation.  In tbese areas, tbe sand vbieb bas
eroded from tbe landfill vill be excavated and tbe vetlands vill
be revegetated.  Since tbe eroded sand is not contaminated, tbe
excavated sediment can be redeposited on-site.  To promote

-------
wetland revegetation, •oils similar to those of the natural
wetland will be placed, and sedges and others species vill be
planted.  During revegetation, the natural contour of the
wetland vill be restored to maintain the easterly flow of the
creek toward the main wetland body.  Additional areas Bay be
defined during the design phase if erosion has caused further
damage since the RI was conducted.

4. Site Monitoring

To insure that the remedy remains protective, both the
groundwater and the air will be monitored periodically for thirty
years.  The existing network of wells plus one new well cluster
will be monitored on a quarterly basis for a number of
constituents that were selected based on site specific
information.  The monitoring results will be reviewed on a
periodic basis to determino if a variation indicative-of a plume
is present.

The air monitoring program will depend on the specific technology
chosen for gas treatment.  This plan will be outlined during the
design phase and will specify the monitoring locations, the
sampling technique, the indicator parameters and frequency of
monitoring.  Depending on the technology, this plan may include
•mM ant* -a±r uruillnring and emissions testing to insure that the
system is protecting public health and the environment.


DBCL&R&TXOH

The selected remedy is protective of human health and the
environment, attains federal and state requirements that are
applicable or relevant and appropriate and is cost-effective.
This remedy partially satisfies the statutory preference for
treatment that permanently and significantly reduces the volume,
toxicity and mobility of the hazardous substances, pollutants and
contaminants, as a principal element.  Finally, it is determined
that this remedy utilizes permanent solutions and alternative
treatment technologies to the maximum extent practicable.
     Date'                            Michael R.  Deland
                                    Regional Administrator
                                                           5Z_

-------
                LANDFILL 6 RESOURCE RECOVERY SITE
                    Record of Decision Summary

                        TABLE OF CONTENTS

Contents                                              Pace
I.      SITE NAME, LOCATION AND DESCRIPTION ...».-....   1

II.     SITE HISTORY AND ENFORCEMENT ACTIVITIES ...... -.   4
          A. Remedial History   ...............   4
          B. Enforcement History    .............   5

III.    COMMUNITY RELATIONS .................   6

IV.     SCOPE OF RESPONSE ACTION  ..............   7

V.      SITE CHARACTERISTICS  ............ ....   7
          A. Air  ......................   7
          B. Groundwater and Subsurface Soils ........   9
          C. Surface Water and Sediments  ..........  11

VI.     SUMMARY OF SITE RISKS ................  11
          A. Public Health Assessment .......  .....  11
          B. Environmental Assessment .......  .....  16

VII.    LANDFILL CLOSURE ASSESSMENT .............  16
          A. Evaluation of the Cover's Performance   .....  18
          B. Compliance with Federal and State RCRA
             Requirements ..................  19

VIII.   DEVELOPMENT AND SCREENING OF ALTERNATIVES ......  19
          A. Statutory Requirements/Response Objectives ...  19
          B. Technology and Alternative Development and
             Initial Screening  ...............  20

IX.     DESCRIPTION/SUMMARY OF THE DETAILED AND COMPARATIVE
       ! ANALYSIS OF ALTERNATIVES  ..............  24
          A. Alternatives Analyzed  .............  24
          B. Gas Treatment Technologies Analyzed  ......  28

X.      DOCUMENTATION OF SIGNIFICANT CHANGES  ........  29

XI.     THE SELECTED REMEDY .................  29
          A. Description of the Selected Remedy     .....  29
               1. Upgrading the Landfill Closure  ......  29
               2. Gas Collection and Thermal Destruction  . .  31
               3. Wetlands Remediation  ...........  36
               4. Site Monitoring ..............  36
          B. Point of Compliance and Target Cleanup Levels  .  38
          C. Rationale for Selection  .....  •.  ......  38

-------
                LANDFILL & RESOURCE RECOVERY SITE
                    Record of Decision Summary

                        TABLE OF CONTENTS

Contents                                              Page
XII.    STATUTORY DETERMINATIONS	  39
          A. The Selected Remedy is Protective of Human
             Health and the Environment	39
          B. The Selected Remedy Attains ARARs  	  40
          C. The Selected Remedial Action is Cost Effective .  42
          D. The Selected Remedy Utilizes Permanent
             Solutions and Alternative Treatment
             Technologies or Resource Recovery Technologies
             to the Maximum Extent Practicable  	  52
          E. The Selected Remedy Partially Satisfies the
             Preference for Treatment as a Principal Element .  52

XIII.   STATE ROLE	53
                         LIST OF FIGURES

Figure Number                            .             Page Number

Figure 1-1: Site Location Map 	 .....   2
Figure 1-2: Site Layout Plan	   3
Figure V-l: Location of Landfill Vents  	   8
Figure V-2: Monitoring Well Locations	10
Figure V-3: Surface Water and Sediment Locations  	  12
Figure VI-l: Wetland Community Section  	  17
Figure XI-1: Comparison of'Slope Stabilization Techniques .  .  32
Figure XI-2: Alternative 3  	  33
Figure XI-3: Alternative 4	34
Figure XI-4: Wetlands Remediation 	  37


                          LIST OF TABLES

Tftbl? Number                                          Page Number

Table VI-l: Contaminants of Concern	  .  13
Table VI-2: Summary of Exposure Routes  	  14
Table VTII-1: Alternatives Developed for L&RR Site  .....  22
Table XII-1: Location-Specific ARARs  	  43
Table XII-2: Chemical-Specific ARARs  	  46
Table XII-3: Action-Specific ARARs  	  48

                           APPENDICES           ;
                                                ^

Responsiveness-Summary  	 ....    Appendix A
Administrative Record Index 	    Appendix B
State Concurrence Letter  	    Appendix C

-------
ROD DECISION SUMMARY                                       page 1
Landfill  & Resource Recovery Site	
I.      SITE NAME, LOCATION AND DESCRIPTION

The Landfill and Resource Recovery.(L&RR) Site ("the Site") is a
closed landfill in the Town of North Smithfield, Rhode! Island
that historically received domestic, commercial and industrial
wastes.  The landfill covers approximately 28 acres of a 36 acre
parcel of land owned by Landfill and Resource Recovery (L&RR),
Inc.  The Site is located on Oxford Turnpike, northwest of Pound
Hill Road (see Figure 1-1: Site Location Map).

The landfilled area extends from the edge of Oxford Turnpike on
the west, to within 50 feet of the property line on the north and
east, and to within 100 feet of an intermittent unnamed stream on
the south.  The Site is located in a rural area primarily
surrounded by woodlands.  A sand and gravel pit exists south of
the landfill, on property also owned by L&RR, Inc.  Three unnamed
streams exist south and east of the Site.  These streams flow
through wetlands, also located south and east of the Site, and
discharge into Trout Brook.  Trout Brook flows north for about
2000 feet to Trout Brook Pond which discharges into the
Slatersville Reservoir.  The Slatersville Reservoir and Trout
Brook are Class B water bodies suitable for fishing, swimming and
other recreational purposes.

There are several homes near the landfill that have private wells
and use groundwater as a source of drinking water.  These homes
are located on Oxford Turnpike, Pound Hill Road and other nearby
roads.  The closest residence is approximately 1200 feet
southeast of the landfill, on Pound Hill Road (see Figure 1-2:
Site Layout Plan).  The landfill is located over the
Slatersville Aquifer which has been designated as a drinking
water source by the State of Rhode Island.

The Site is a former sand and gravel pit that reportedly began
accepting wastes for disposal around 1927.  The Site owners claim
that the hazardous materials were co-disposed with the municipal
wastes in the north-central area of the Site,  other reports
received by EPA have stated that the hazardous waste were co-
disposed with municipal wastes throughout the Site.
Consequently, EPA does not know the full areal extent of
historical hazardous waste disposal.  When hazardous waste
disposal ceased, the so called "hazardous waste area", as
defined by the owners, was covered with a synthetic cover made of
20-mil poly vinyl chloride (PVC).  This action was conducted by a
company under contract to L&RR, Inc., and was intended to reduce
infiltration of rain and melted snow into the waste.  After this
action, the landfill continued operation placing'commercial and
domestic waste on top of and around this area.  When the landfill
was closed by the owner, the landfill was graded and covered with
approximately a foot of sand and another synthetic cover.  This
synthetic cover was placed over approximately 80% of the
landfill.  Additional soil was placed on this cover to establish
vegetation.  The side slopes are steep, ranging from slopes of
3:1 to slopes of 2:1.

-------
                                                               page 2
                    APPROXIMATE LOCATION
                      ESTERN SAND ANC
             . ft. I.. TJ HIMfft '
                                               SITE LOCATION MAP
                                                      L & RR SITE
                                  NORTH SMITHF1ELD, RHODE ISLAND
M1t-O1

-------
                             Figure 1-2
                       Site Layout Plan
                                                                     page 3
—. . —  Property Une
nnnnrr  Access Road
                                                     Tributaries
                                                     Residences

-------
ROD DECISION SUMMARY                                       page 4
        l & Resource Recoverv Site
The landfill contains  18 landfill gas vents which were
constructed to vent gases from below the synthetic cap and soil
that cover most of the landfill.  Gas is generated from decaying
wastes disposed in the landfill.  These vents are installed at
varying depths throughout the top of the landfill and -are
currently closed to prevent gases from being released.

Surrounding the landfill is a fence which consists of strands of
barbed wire attached to wooden posts.  This fence is similar to
those used to restrain cattle and horses.

A more complete description of the Site can be found in the
Remedial Investigation/Feasibility Study (RI/FS) Report on pages
2-1 through 2-7.


II.     SITE HISTORY AND ENFORCEMENT ACTIVITIES

The Site was originally a sand and gravel pit that reportedly
began accepting wastes for disposal around 1927.  In 1969, the
Site began operation as a solid waste disposal area under the
management of Harvey Fortune.  This operation was sold to L&RR,
Inc., in 1974.  A Solid Waste Management Tacility licence was
issued to L&RR, Inc.,  by the State of Rhode Island in December
1976.  In November 1977, L&RR, Inc., submitted plans for
installing 7 monitoring wells to the Rhode Island Department of
Health (RIDOH).  These wells were installed to comply with State
regulations pertaining to hazardous waste disposal.  This
submittal was the first indication that hazardous waste disposal
was occurring at the Site.  In September 1979, Rhode Island
Department of Environmental Management (RIDEM) ordered L&RR,
Inc., to cease accepting hazardous waste.  In December 1979, the
hazardous waste area,  as defined by L&RR, Inc., was covered with
a synthetic cover.  Additional landfilling of commercial and
domestic waste over and around the covered area continued until
1985.  Landfill closure began in 1985 pursuant to a 1983 Court
Order and Consent Order and Agreement ("the 1983 Court Order")
between RIDEM and L&RR, Inc.  To date, most of the closure as
required by the 1983 Court Order has been completed.

        A. Remedial History

The L&RR Site has been the focus of several investigations by
the Environmental Protection Agency (EPA),  the Rhode Island
Department of Environmental Management (RIDEM) and the owners
since 1977.  Between 1977 and 1980, several sets of monitoring
wells were installed and sampled on an irregular, basis.  Between
1980 and 1981, the EPA conducted a Preliminary Site Assessment
of the L&RR Site which resulted in the Site being ranked on the
National Priorities List (NPL) in 1982.  A Remedial Action Master
Plan (RAMP) was completed for the Site in 1983.  The RAMP
evaluated existing data sources, identified data needs and
recommended remedial action activities.  In 1985, L&RR, Inc.,

-------
ROD DECISION SUMMARY                                       page 5
Landfill & Resource Recovery Site	
began to close the landfill under a Court Order and Consent Order
and Agreement with RIDEM.  EPA was not a party to that Court
Order and began a federally funded RI/FS in May 1986.  A more
detailed description of the Site history can be found in the
RI/FS Report on pages 1-3 through 1-9.

        B. Enforcement History

A number of enforcement actions have been taken against L&RR,
Inc., by RIDEM.  On September 6, 1979, RIDEM ordered L&RR, Inc.,
to cease accepting and disposing hazardous wastes.  The landfill
continued accepting commercial and domestic wastes.  On December
1, 1980, the L&RR Solid Waste Management Facility license was up
for renewal.  L&RR, Inc., filed a renewal application and
continued operation.  On October 30, 1981, RIDEM ordered L&RR,
Inc., to cease accepting all wastes and to close the northern
section of the landfill where the hazardous waste was allegedly
disposed.  On November 9, 1981, L&RR ceased operating for a three
week period and appealed the RIDEM order.  On December 28, 1981,
the RI Superior Court issued an order staying the enforcement and
effect of the RIDEM order and allowing the landfill to continue
operating.  Based on new monitoring information, RIDEM issued
another order to close the landfill.  In January 1982, the RI
Superior Court found RIDEM in contempt of the December 28 order
and allowed L&RR to continue operations.  On July 13, 1983, RIDEM
and L&RR, Inc., entered into a Consent Order and Agreement which
set forth terms and conditions governing the continued operation
and eventual closure of the landfill.  This Consent Order and
Agreement was approved by the Superior Court for the State of
Rhode Island and is referred to'in the remainder of this document
as "the 1983 Court Order."  The landfill ceased operating in
January 1985.

In June 1983, L&RR, Inc., requested that EPA accept the reports
and plans developed under the 1983 Court Order as fulfilling the
requirements of an RI/FS.  EPA reviewed and commented on the
1983 Court Order and plans but did not accept them as fulfilling
the requirements of an RI/FS consistent with the National
Contingency Plan (NCP).  Consequently, during 1983 and 1984, EPA
conducted numerous negotiations with L&RR, Inc.  As a result of
these negotiations, EPA sent L&RR, Inc., a proposed consent order
on November 24, 1984 for concurrence.  This consent order would
have allowed L&RR, Inc., to submit the data collected under the
1983 Court Order supplemented by additional investigations and
studies required by EPA to fulfill the requirements of an RI/FS
consistent with the NCP.  L&RR, Inc., failed to respond and
concur with EPA's proposed consent order.  On January 29, 1985,
EPA notified L&RR, Inc., that the Agency was withdrawing from the
process of negotiating a formal agreement with L&RR, Inc.,
regarding the RI/FS.

-------
ROD DECISION SUMMARY                                       page 6
Landfill ft Resource Recovery Si tie
On June 5, 1986, EPA notified L&RR, Inc., of their potential
liability with respect to the Site.  On July 29, 1988, EPA sent a
notice letter to L&RR, Inc., which .formally demanded
reimbursement for past costs; requested information regarding
activities at the Site; and, requested voluntary participation in
undertaking forthcoming remedial activities.

On July 29, 1988, EPA also notified additional parties who either
generated wastes that were shipped to the facility, arranged for
the disposal of wastes at the facility, or transported wastes to
the facility, of their potential liability with respect to the
Site.  EPA expects to carry out negotiations with the PRPs for
conducting the remedial activities.

EPA's formal comment period on the Proposed Plan, which
describes EPA's preferred remedy as well as the other
alternatives considered for the Site in the FS, was from July 20
through September 2, 1988.  An extended comment period, six weeks
rather than the required three weeks, was held to allow
additional time for the Potentially Responsible Parties (PRPs) to
participate in the remedy selection process.  Comments presented
by the PRPs during the public comment period are included in the
Administrative Record.  A summary of these comments as well as
EPA's response, which describes how these comments affected the
remedy selection, are included in the Responsiveness Summary in
this document.
III.    COMMUNITY RELATIONS

Throughout the Site's history, community concern and involvement
has been moderate to high.  The community was- particularly active
in the late 70's and early 80's and repeatedly sought to close
the landfill.  Other concerns expressed by the community include
contamination of the Slatersville Aquifer; development, growth
and property values in the community; and, potential health
effects caused by exposure to the Site.  EPA has kept the
community and other interested parties apprised of the Site
activities through informational meetings, fact sheets, press
releases and public meetings.

In 1983, EPA released a community relations plan which outlined a
program to address community concerns and keep citizens informed
about and involved in remedial activities.  This plan was revised
in October 1986 and on January 7, 1987, EPA held an informational
meeting in the Municipal Anex Building in North Smithfield, RI to
describe the plans for the RI/FS.
                                                *
On July 19, 19£8, EPA held an informational meeting to discuss
the results of the RI, the alternatives presented in the FS and
EPA's preferred alternative.  This information was summarized and
published in EPA's Proposed Plan, July 1988.  The Proposed Plan
was distributed to people on EPA's mailing list and other
interested people at the meeting.  Also during this meeting,  the

-------
ROD DECISION SUMMARY                                       page 7
Landfill  & Resource Recoverv Site
Agency responded to questions from the public.  From July 20 to
September 2, 1988, the Agency held a six week public comment
period to accept public comment on the alternatives presented in
the FS and the Proposed Plan and on any other documents
previously released to the public.  On August 10, 1988, the
Agency held a formal public hearing to accept any oral comments.
A summary of the comments submitted and the Agency's response to
comments are included in' the Responsiveness Summary of this
document.
IV.     SCOPE OF RESPONSE ACTION

The selected remedy has four major components which together
comprise a comprehensive approach for Site remediation.  In
summary, the remedy consists of the following components:
upgrading the existing landfill closure; constructing a gas
collection and thermal destruction system to treat the landfill
gas; remediating the impacted wetlands; and monitoring the Site.
The selected remedy will reduce the principal threats posed by
the Site.  Gaseous emissions from the landfill pose the principal
threat to human health at the Site.  The gas collection and
thermal destruction system will reduce this threat.  The sand
eroding from the landfill poses a principal threat to the
environment.  Specifically, the sand is filling in wetlands that
surround the Site.  Upgrading the landfill closure will reduce
this threat as well as the potential threat to groundwater from
infiltration of rain and -melted snow.  The impacted wetlands will
be remediated.  Site monitoring will insure that the selected
remedy remains protective of human health and the environment.
V.      SITE CHARACTERISTICS

The RI consisted of evaluating existing data and gathering
additional data needed to characterize the Site.  Additional data
was gathered for the following media:  air, groundwater,
subsurface soils, surface water, and surface water sediments.
The significant findings of the Remedial Investigation are
summarized below.  A complete discussion of the Site
characteristics can be found in Sections 7 and 8 of the RI/FS
Report.

        A. Air

During the RI, the 18 landfill vents were opened and the
emissions were evaluated to determine the landfill's impact on
air quality.  The vents were sampled and found to be releasing
methane and hydrogen sulfide gas contaminated with a variety of
volatile organic compounds (VOCs).  Five of the 18 vents
contained significantly higher concentrations of VOCs.  The
locations of these vents (12, 13, 15, 17 and 18) were coincident
with the proximate area where hazardous waste was disposed (see
Figure V-l: Location of Landfill Vents).

-------
                                                                                 LftRR
                                                                                 LANDFILL
                                                                            PROPERTY LINE
(Figure V-l
 Location of Landfill Vents

                                                SITE TRAILER
                                                                           SCALE:
                                                                           1 MUCH » 200 FEET
                                                                                                               oo

-------
ROD DECISION SUMMARY                                       page 9
Landfill  & Resource Recovery Site		
Samples of the air were also taken at locations above the portion
of the landfill that is not covered by the synthetic cap.  These
results indicated that methane and hydrogen sulfide gas
contaminated with VOCs are also released from the uncovered
area.

        B. Groundwater and Subsurface Soils

EPA collected and analyzed groundwater samples from 14 on-site
groundwater monitoring veils (see Figure V-2: Monitoring Well
Locations) and evaluated historical information available from.
earlier groundwater studies.  Low levels of VOCs and metals
(lead, cadmium, and arsenic) were present down gradient from the
Site.  The detection of these compounds was sporadic and unevenly
distributed and the concentrations were all below EPA's drinking
water maximum contaminant levels (MCLs).  The presence of a
plume of hazardous contaminants moving away from the Site is not
evident from present and historical data.  Since historical
information indicates that hazardous wastes have been disposed in
the landfill, there are three possible explanations for the
analytical results seen to date.  The first possible explanation
is that there are migrating hazardous constituents which have not
yet entered the groundwater.  The second possible explanation is
that there is contaminated groundwater which has not .yet been
transported beyond the boundary of the landfill, where the
monitoring wells are located.  The third possible explanation is
that the existing landfill conditions, such as the natural
hydrologic and geologic conditions within the landfill, the
quantity of hazardous-wastes disposed and the existing cover,
could be preventing the migration or detection of a groundwater
contaminant plume.

Iron, manganese, chloride and specific conductance were detected
in the groundwater at slightly elevated levels, above ambient
conditions, down gradient from the Site.  These compounds are
typically found in the groundwater migrating from municipal
landfills and do not have a high toxicity.

The investigation indicated that groundwater in the vicinity of
L&RR flows to the east and southeast and discharges into
tributaries of Trout Brook and wetlands adjacent to the Site.
The average rate of groundwater flow was estimated to range from
5 to 10 ft/year in the upper kame delta deposits and from 230 to
460 ft/yr in the lower ice contact deposits.

EPA also reviewed residential well data generated by the Rhode
Island Department of Health.  Low levels of VOCs were present in
some of the residential wells with no consistent '.trends.  In some
instances, the types of VOCs detected were different than those
detected in the on-site monitoring wells.

Subsurface soil samples were obtained during the drilling of the
groundwater monitoring wells.  The results of the analyses did
not indicate the presence of significant levels of contaminants.

-------

-------
ROD DECISION SUMMARY                                      page 11
Landfill & Resource Recovery Site	 '	
In summary, based on all the data generated, EPA concluded that
a plume of hazardous contaminants is not yet migrating from.the
Site.  All contaminants are below MCLs.  The elevated levels of
iron, manganese, chloride and specific conductance are typical of
an inorganic plume migrating from a municipal landfill.  Finally,
the L&RR Site is not presently impacting the local private wells.
Contaminants found at those wells are presently attributed to
sources other than the L&RR landfill.

        C. Surface Water and Sediments

To characterize impacts to local area streams, samples of the
surface water and sediments were taken (see Figure V-3: Surface
Water and Sediment  Locations).  As in the case of the
groundwater, the surface water and sediments also contain very
low levels of VOCs.  Slightly elevated levels of inorganic
compounds were also detected.


VI.     SUMMARY OF SITE RISKS

Using the data collected during the RI, a risk assessment was
conducted to evaluate the present and future risks posed to
public health and the environment from lifetime exposure to
contaminants at the L&RR Site.  The risk assessment is performed
assuming that further remedial actions will not be conducted and
is intended to indicate which routes of exposure present a risk
that warrants remedial actions.  The risk assessment was
conducted in two parts: a public health assessment and an
environmental assessment.

        A. Public Health Assessment

A Public Health Assessment (PHA) was performed to estimate the
probability and magnitude of potential adverse human health
effects from exposure to contaminants associated with the Site.
Seventeen contaminants of concern, listed in Table VI-1, were
selected for evaluation in the PHA.  These contaminants
constitute a representative subset of the more than 30
contaminants identified at the Site during the RI.  The 17
contaminants were selected to represent potential on-site hazards
based on toxicity, concentration, mobility and persistence in
the environment, and frequency of detection.

Potential human health effects associated with the contaminants
of concern in groundwater, surface water, sediments and air were
estimated through the development of several hypothetical
exposure scenarios.  Table VT-2 summarizes the potential
receptors and the significant routes of exposure for all media at
the Site.

Ingestion of groundwater is considered to be.a.potential future
route of exposure rather than a present route for three reasons.
First, on-site groundwater is not presently used as a drinking

-------
<*:**•/
\4 > - •/

-------
                                                                           page 13
                                  Table VI-1
                            Contaminants of Concern
                                                           MEDIA-

COMPOUND                           Groupdwater   Surface Water   Sediment   Air

o .VOCs

     2-butanone                         X            X            X
     toluene                                         X                      X
     trans-1,2-dichloroethene                        X
     1,1-dichloroethane                              X
     chloroform                                                             X
     1,2-dichloroethane                                                     X
     carbon tetrachloride                                                   X
     benzene                                                                X
     1,1,-dichloroethene                                                    X
     methylene chloride                                                     X
     tetrachloroethene                                                      X
     1,1,2,2-tetrachloroethane                                              X
     trichloroethene                                                        X
     ethyl benzene                                                          X

o  SVOCs

     none selected

o  Pesticides

     none selected

o  Inorganics

     arsenic                            X            X
     lead                               X            X
     zinc                                            X
12.87.73T
0007.0.0

-------
                                                                          page 14
                             Table VI-2
                     Summary of Exposure Routes
             Point of          Route of      Exposed
Medium      Exposure          Exposure       Population   Status

Ground-      Dovngradient      Ingestion     Adults &     Future
water        veils                           children

Surface      Eastern           Dermal        Children     Current
water         Edge             absorption
             Southern
              Edge
             Western
              Edge

Sediments    Eastern           Dermal        Children     Current
              Edge             absorption
             Southern
              Edge

Air          Vents on          Inhalation    Adults &     Current
Emissions    landfill                        children
             and disper-
             sion downwind
 12.87.73T
 0008.0.0

-------
ROD DECISION SUMMARY                                      page 15
Landfill & Resource Recovery Site       	
water source.  Second, based on the information gathered to
date, a contaminant plume is presently not migrating from the
Site and impacting off-site private wells.  Finally, the
landfill is located over the Slatersville Aquifer which is
classified as a potential future drinking water source, so that
there is a threat of future releases from the Site into drinking
water.

The streams near the Site are rather shallow and swimming is not
considered probable.  However, children who might play near the
Site could be exposed by wading in such streams.  Adults are not
expected to use the Site for this purpose and are therefore not
considered to be exposed to contaminants in the surface water and
sediments.

Gaseous emissions from the landfill vents as well as fugitive
emissions from the surface of the landfill are considered to be
potential routes of exposure.  Presently, the landfill vents are
closed and the majority of the gaseous emissions are retained at
the Site. However, these vents will eventually have to be opened
to protect the integrity of the landfill's synthetic cover from
pressure building up within the landfill..  Therefore, inhalation
of the vent emissions is a potential future route of exposure.

EPA's exposure scenarios are designed to identify the level of
clean-up that would be acceptable without the need for long term
management, such as a fence, to prevent on-site exposure.  In
assessing the risks associated with the landfill emissions,
separate exposure scenarios were utilized for children and
adults because children could be expected to play at the Site and
be exposed to the undiluted emissions from the vents.

The conclusions of the public health assessment are as follows:

     o  Of all the potential risks evaluated at the Site,
        exposure to gaseous emissions from the landfill pose the
        highest health risk.  If the vents were opened and
        neighboring residents were exposed throughout their
        lifetime to the gaseous emissions from the vents, a
        potential risk to public health could result from
        exposure to these gases.  Furthermore, children who
        might play on the landfill are at the greatest risk.

     o  Exposure to groundwater at the boundary of the Site does
        not presently pose a significant risk to public health.
        It is important to note that it was determined from the
        data collected that the L&RR Site is not presently the
        source of contamination in the residential wells near the
        Site.  EPA has requested that the State of Rhode Island
        investigate other potential sources of contamination for
        these wells.

     o  Exposure to surface water and sediments adjacent to the
        Site does not presently pose a significant risk to public
        health.

-------
ROD DECISION SUMMARY                                      page 16
A complete discussion of the Public Health Assessment can be
found in Section 11 of the RI/FS Report.

        B. Environmental Assessment
                                     •
This part of the risk assessment evaluated risks posed to the '
wetlands and various wildlife including aquatic organisms at the
Site from exposure to pollutants and contaminants.  The
assessment concluded that the only significant environmental
threat is to the wetlands surrounding the Site (see Figure VI-
1: Wetland Community Section).  The wetlands are being impacted
by soil eroding from the landfill cover.  The eroded soil is not
contaminated; however, it is filling in the wetlands, destroying
vegetation and decreasing the ability of the wetland area to
support indigenous plant and animal life.

A complete discussion of the Environmental Assessment can be
found in Section 10 of the RI/FS Report.


VII.    LANDFILL CLOSURE ASSESSMENT

In 1983, LfcRR, Inc., entered into a Court Order and Consent Order
and Agreement ("the 1983 Court Order")  with RIDEM, to close the
landfill according to plans incorporated into the Order.  EPA
commented on these plans but was not a party to this Court Order.
The 1983 Court Order, the plans and the data supporting them
failed to meet the requirements of the National Contingency Plan
(NCP).  Negotiations for the conduct of an RI/FS in conformance
with the NCP were conducted between EPA and L&RR, Inc., but an
agreement was not reached.  The owner closed the landfill
according to the plans in the 1983 Court Order when landfilling
stopped in January of 1985.

During 1985 and 1986, GCA Corporation,  under contract to EPA,
observed the Site closure operations and evaluated its compliance
with the Resource Conservation and Recovery Act (RCRA), Subtitle
C, regulations.  Section 40 CFR Part 264 of the RCRA regulations
contains requirements governing design, construction, operation,
maintenance, disposal, closure and post-closure of a hazardous
waste facility.  Some of these regulations are considered
relevant and appropriate requirements for the Site since the L&RR
Site contains wastes that are listed in RCRA as hazardous wastes
and these wastes were accepted for disposal prior to 1980 (See
Tables XII-1,2 and 3).  The information obtained by GCA was
intended to supplement information obtained during EPA's RI/FS.
CCA's observations and findings were documented in the Compliance
Oversight Report by GCA, dated June 1986.  EPA began the RI/FS in
May of 1986.  During the RI, EPA evaluated the performance of the
landfill closure as it had been conducted to date.  The
significant finding are summarized below.

-------
  Figure VI-1
  WETLAND COMMUNITY SECTION
                  L ft RH SITE
NORTH SMITHFELD. RHODE ISLAND

-------
ROD DECISION SUMMARY                                      page 18
        A. Evaluation of the Cover's Performance

During the RI, data was gathered from the existing landfill to
assess the performance of the existing cover.  The'landfill was
assessed according to the following factors: cover drainage,
vegetation, erosion of cover soil, and the stability of the side
slopes.

Using the Hydrogeologic Evaluation of Landfill Performance (HELP)
model, Version I, the assessment concluded that approximately
749,000 gal/acre/yr of infiltration enters the waste in the 4.9
acre area without the synthetic cover and subsequently leaches
from the base of the landfill.  This infiltration comprises 59%
of the average annual rainfall.  The maximum infiltration in the
rest of the landfill, which has a synthetic cover as part of the
cover system, was estimated to be 7,690 gal/acre/yr or 0.6% of
the average annual rainfall.  In response to the comments
received during EPA's public comment period, the infiltration in
the uncovered area was recalculated using the Thornthwaite and
Mather method as republished by Fenn, Hanley and DeGeare, in
1977.  Using this method, the infiltration in the uncovered area
was calculated to be approximately 435,00*0 gal/acre/yr which is
34% of the average annual rainfall.

The existing landfill surface water drainage system is not
designed or constructed to handle peak velocity flows from heavy
precipitation and the landfill lacks vegetation, particularly in
the area without a synthetic cover.  Both of these factors result
in the potential for excessive erosion.  Current erosion from'the
landfill ranges from 0.5 to 38.3 tons/acre of cover soil per
year.  Ultimately, the eroded soil is deposited in  wetland areas
surrounding the Site.  The steep side slopes are marginally
stable.  Accepted engineering practice is to design the slopes so
that a factor of safety against cover sliding is at least 1.25.
For the steep slopes at the Site, the factor of safety ranged
from 1.02 - 1.15.

During the RI, EPA also assessed the performance of a
hypothetical cover.  The specifications for this hypothetical
cover were generated using the EPA guidance document entitled
Covers for Uncontrolled Hazardous Waste Sites (EPA/540/2-85/002;
September 1985).  A cover constructed according to this guidance
results in 2% of the average annual rainfall leaching from the
base of the landfill.  Also, an estimated 2 tons/acre of soil per
year would erode from the cover.  The guidance document also
provides information on constructing the surface water drainage
system to handle peak flows and to minimize erosion.  To assess
whether the existing cover met the requirements 6f the RCRA,
Subtitle C, regulations, the performance of the two covers was
compared.  The conclusions of this assessment are presented
below.

-------
ROD DECISION SUMMARY                                      page 19
Landfill  t Resource Recovery Site   	
        B. Compliance with Federal and State RCRA Requirements.

Some of the RCRA, Subtitle C, regulations are considered relevant
and appropriate requirements for the L&RR Site.  During the
assessment, it was determined that the existing landfill closure
does not meet the RCRA regulations as outlined in 40 CFR Subpart
N, § 264.310.  Specifically, it does not minimize erosion; it
does not minimize infiltration of liquids such as rain and melted
snow and it does not function with minimum maintenance.
Furthermore, the present Site security system does not meet the
objectives of 40 CFR Subpart B, § 264.14; the present groundwater
monitoring plan does not meet the objectives of 40 CFR Supart F,
§ 264.90 - § 264.101; and, the post closure plan does not meet
the objectives of 40 CFR Subpart G, § 264.110 - § 264.120.  The
specific deficiencies pertaining to security, the groundwater
monitoring plan, and the post closure plan are discussed in
detail in the GCA Report and the RI/FS Report, which are included
in the Administrative Record.

In addition to the above, the landfill cover does not meet Rhode
Island's Rules for Solid Waste Management Facilities (R.I.G.L.
23-18.9).  These rules require a total of. 24 inches of cover soil
to be maintained on the surface of the landfill.  Presently, the
2:1 side slopes are only covered with approximately 1 foot of
soil.  Furthermore, the erosion of the cap into the wetlands
violates the State's Wetlands law, (R.I.G.L. 2-1).

A complete discussion of the landfill closure assessment can be
found in the GCA Report and Section 9.0 of the RI/FS Report.
VIII.   DEVELOPMENT AND SCREENING OF ALTERNATIVES

        A. Statutory Requirements/Response Objectives

Prior to the passage of the Superfund Amendments and
Reauthorization Act of 1986 (SARA), actions taken in response to
releases of hazardous substances were conducted in accordance
with CERCLA as enacted in 1980 and the revised National Oil and
Hazardous Substances Pollution Contingency Plan (NCP), 40 CFR
Part 300, dated November 20, 1985.  Until the NCP is revised to
reflect SARA, the procedures and standards for responding to
releases of hazardous substances, pollutants and contaminants
shall be in accordance with Section 121 of CERCLA and to the
maximum extent practicable, the current NCP.

Under its legal authorities, EPA's primary responsibility at
Superfund sites is to undertake remedial actions'that are
protective of human health and the environment.  In addition,
Section 121 of CERCLA establishes several other statutory
requirements and preferences, including: a requirement that EPA's
remedial action, when complete, must comply with applicable or

-------
ROD DECISION SUMMARY                                      page 20
relevant and appropriate environmental standards established
under federal and state environmental lavs unless a statutory
waiver is granted; a requirement that EPA select a remedial
action that is cost-effective and that utilizes permanent
solutions and alternative treatment technologies or resource
recovery technologies to the maximum extent practicable; and a
statutory preference for remedies that permanently and sig-
nificantly reduce the volume, toxicity or mobility of hazardous
substances, pollutants and contaminants over remedies that do not
achieve such results through treatment.  Response alternatives
were developed to be consistent with these Congressional
mandates.

Remedial response objectives define the specific aspects of a
site that must be considered during remediation.  For the L&RR
Site, response objectives were formulated for the landfill
closure, wetlands and landfill gas based on environmental
problems defined in the public health, environmental and landfill
closure assessment.  These response objectives are used to
develop appropriate remedial alternatives and are as follows:

     o  remediate the landfill so that federal and state
        applicable, relevant and appropriate requirements
        are met and to insure that the landfill is
        protective of human health and the environment;

     o- reduce present and future impacts to wetlands due to
        sedimentation of eroded landfill cover material;

     o  remediate the wetlands already impacted by
        sedimentation; and

     o  remediate the landfill gas so that VOC concentrations in
        ambient air are reduced and risks to public health and
        the environment are minimized.


        B. Technology and Alternative Development and Initial
           Screening

CERCIA, the NCP, and EPA guidance documents including, "Guidance
on Feasibility Studies Under CERCLA" dated June 1985, and the
"Interim Guidance on Superfund Selection of Remedy1* [EPA Office
of Solid Waste and Emergency Response (OSWER)], Directive No.
9355.0-19 (December 24, 1986) set forth the process by which
remedial actions are evaluated and selected.   In accordance with
these requirements and guidance documents, a range of
alternatives were developed for the Site.  In accordance with
Section 121 of CERCLA, this range must include the following
categories: a no action alternative, alternatives that utilize
containment technologies and treatment alternatives ranging from
an alternative that would eliminate the need for long-term
management (including monitoring) at the Site to alternatives

-------
ROD DECISION SUMMARY                                      page 21
Landfill & Resource Recovery Site	
that utilize treatment to reduce the nobility, toxicity, or
volume of the hazardous substances as their principal element.

Section 121(b)(l) of CERCLA presents several factors that at a
minimum EPA is required to consider in its assessment of
alternatives.  In addition to these factors and the other
statutory directives of Section 121, the evaluation and selection
process was guided by the EPA document "Additional Interim
Guidance for FY  '87 Records of Decision1* dated July 24, 1987.
This document provides direction on the consideration of SARA
cleanup standards and sets forth nine factors that EPA should
consider in its evaluation and selection of remedial actions.
The nine factors are:

1.   Compliance with Applicable or Relevant and Appropriate
     Requirements (ARARs).

2.   Long-term Effectiveness and Permanence.

3.   Reduction of Toxicity, Mobility or Volume.

4.   Slant-term -Effectiveness.

5.   Implementability.

6.   Community Acceptance.

7.   State Acceptance.

8.   Cost.

9.   Overall Protection of Human Health and the Environment.

Section 15 of the RI/FS Report identified, assessed and screened
technologies based on Site and waste characteristics such as
geology and hydrology; availability of space and resources; the
presence of special Site features; the contaminated media; and,
the type and concentrations of wastes.  These technologies were
combined into remedial alternatives that would provide a
comprehensive remedial approach to the Site.  At the conclusion
of this process, 6 remedial alternatives were developed for the
Site: a no action alternative (Alternative 1), four containment
alternatives (Alternatives 2-5)  and a treatment alternative
(Alternative 6).  These alternatives are presented in
Table VIII-1.

Alternatives 3, 4 and 5 contain a landfill gas treatment
component.  Three thermal destruction technologies were
identified for treating the landfill gas: combustion, flaring and
incineration.  During the FS, it was determined that any one of
these technologies could be included with any one of the
alternatives.

-------
                                                         Table VIII-1
                                                  Alternatives Developed for
                                                LANDFILL AND RESOURCE RECOVERY
    Alternative
     Description of
     Key Components
Alternative 1: No-action
             i
Alternative 2: Vegetation
   Establishment
Alternative 3: Synthetic Cover
   Installation/Slope Stabilization
•  Groundwater monitoring for indicators of contaminant Migration.

•  Groundwater monitoring for indicators of contaminant migration.
-  Post-closure plan development to monitor, maintain, and inspect site.
-  Surface water management to minimize erosion of final cover and minimize
   maintenance requirements.
-  Vegetation establishment to minimize erosion of final cover.
-  Vegetation establishment on 2:1 side slope to minimize erosion and enhance
   evapotranspiration.
-  Cover thickness establishment (a minimum of 24 inches to meet ARARs).
-  Hinimal gas control to enhance vegetation and, therefore, minimize erosion and
   maintenance.
-  Sediment removal in wetland and on-site disposal.
-  Fence installation to limit site access.


-  Groundwater monitoring for indicators of contaminant migration.
-  Post-closure plan development to monitor, maintain, and inspect site.
-  Surface water management to minimize erosion of final cover and minimize
   maintenance requirements.
-  Vegetation establishment to minimize erosion of final cover.
-  Cover thickness establishment (a minimum of 24 inches to meet ARARs).
-  Slope stabilization by flattening 2:1 side slope to 2.5:1 and constructing
   terrace along new slope.
-  Synthetic cover installation on terraced 2.5:1 side slope to minimize) maintenance
   and the migration of fluids through the landfill.
•  Landfill gas treatment.
-  Sediment removal in wetlands and on-site disposal.
-  Fence installation to limit site access.
        12.87.85
        0006.0.0

-------
                                                         Table VIII-1
                                                  Alternatives Developed for
                                                LANDFILL AND RESOURCE RECOVERY
                                                             Continued
    Alternative
  Description of
  Key Components
Alternative 4:  Slope Flattening/
   Synthetic Cover Installation
Alternative 5:  RCRA Guidance Cover
   Installation
Alternative 6: Excavation and
   Treatment
Groundwater nonitoring for indicators of contaminant Migration.
Post-closure plan development to monitor, maintain, and inspect site.
Surface water management to minimize erosion of final cover and minimize
maintenance requirements.
Vegetation establishment to minimize erosion of the final cover.
Cover thickness establishment (a minimum of 24-inches to meet ARARs).
Flatten 2:1 side slope to 3:1 in unlined area to minimize erosion and maintenance.
Synthetic cover installation on 2:1 side slope.
Landfill gas treatment.
Sediment removal in wetlanda and on-site disposal.
Fence installation to limit site access.

Groundwater monitoring for indicators of contaminant migration.
Post-closure plan development to monitor, maintain, and inspect site.
Surface water management to minimize erosion of final cover and minimize
maintenance requirements.
Construction of a RCRA guidance cover over the existing cover:
o flatten 2:1 side slope to 3:1
o synthetic cover installation for 2:1 side slope area
o clay cover installation over entire site
o vegetation establishment including a drainage layer
Landfill gas treatment.
Sediment removal in wetlands and on-site disposal.
Fence installation to limit site access.

Excavation of landfill wastes to prevent contaminant migration.
Incineration of removed wastes prior to placement in RCRA-compliant
facility.
Sediment removal and on-site disposal.
        12.87.85
        0007.0.0
                                                                                                                              Jl
                                                                                     (D
                                                                                     K)
                                                                                     U>

-------
ROD DECISION SUMMARY                                      page 24
         & Resource Recoverv Site
In Section 16 of the RI/FS Report, the alternatives were
screened according to effectiveness, implementation and cost.
The purpose of this screening was to narrow the number of
potential remedial alternatives for further detailed analysis
while preserving a range of alternatives for the Site.  As a
result of this screening process, Alternative 6, vhich utilized
treatment (excavation and incineration) as a primary component
and eliminated the need for long-term Site monitoring, was
eliminated as a potential remedy because public health and
environmental risks would be posed by its implementation.  A
detailed discussion of the reasons for elimination are presented
in Appendix AA of the RI/FS Report, and in Section XII.D. of this
document.
IX.     DESCRIPTION/SUMMARY OF THE DETAILED AND COMPARATIVE
        ANALYSIS OF ALTERNATIVES

After the screening process, a detailed analysis was conducted on
the five remaining alternatives.  A detailed analysis was also
conducted on each of the gas treatment technologies.  Based on
the conclusions of the analysis, the selected remedy would
include one of the alternatives and one of the gas treatment
technologies.  This section presents a narrative summary and
brief evaluation of each alternative and each technology
according to the evaluation criteria described above.

        A. Alternatives Analyzed

The five alternatives that were analyzed in detail for the Site
include a no action alternative (Alternative 1) and four
containment alternatives  (Alternatives 2-5).

Alternative 1                     Approximate Present Worth Cost:
No Action                                              $ 850,000.

The no action alternative would not require further remediation
to the landfill closure conducted to date according to the 1983
Court Order between L&RR, Inc., and RIDEM but would consist
solely of long-term groundwater monitoring.  Each existing well
would be sampled on a quarterly basis and analyzed for specific
parameters identified in Table 18-1 of the RI/FS Report.  Because
this alternative results in wastes remaining on-site, the Site
would be reviewed on a periodic basis.

This alternative would not be protective to public health and the
environment because it does not reduce the existing risks
associated with exposure to landfill gas emissions; it does not
reduce impacts to the surrounding wetlands; it would not reduce
the potential for off-site releases into groundwater resulting
from infiltration; and, it would not comply with ARARs,
specifically the RCRA regulations outlined in Section VII of this
document.

-------
ROD DECISION SUMMARY                                      page 25
landfill t Resource Recoverv Si tie         	
A detailed assessment of this alternative can be found in Section
18 of the RI/FS Report.

Alternative 2                     Approximate Present Worth Cost:
Vegetation Establishment                              $3,970,000.

This alternative consists of the following components:

     o  removing sediments and reseeding the wetlands;
     o  installing a chain linked fence;
     o  developing a post closure plan;
     o  upgrading the present surface water runoff management
        system;
     o  establishing a cover thickness of 24 inches;
     o  establishing vegetation; and,
     o  installing a passive gas collection system.

This alternative includes components that would upgrade the
landfill closure conducted to date according to the 1983 Court
Order.  Establishing vegetation and upgrading the surface water
runoff management system would minimize erosion and maintenance.
The wetlands surrounding the Site would be restored and future
impacts would be mitigated.

As discussed in Section VII of this document, EPA's RCRA
regulations, 40 CFR 264 are relevant and appropriate for this
Site.  The RCRA landfill closure requirements in 40 CFR § 264.310
would not be satisfied by this remedy, because it would not
provide long-term minimization of migration of liquids through
the landfill (§ 264.310(a)(1)), in the area that is not capped by
a synthetic cover.  The excess infiltration increases the
potential for groundwater contamination.  Although an organic
plume has not yet been detected, it is expected that one may  .
emerge in the future.  Therefore, the long-term protectiveness of
this alternative is questionable.  This alternative is readily
implementable, taking approximately 2-3 months to design and
construct, and would require long-term monitoring and
maintenance.

This alternative does not contain gas treatment because it is
difficult to implement a treatment system with this alternative.
The landfill gas would be diluted with uncontrolled amounts of
air that would be drawn in from the area which does not have a
synthetic cover.  The air would lessen the combustibility of the
landfill gas.  Therefore, this alternative includes a passive gas
collection system.  This system would direct the landfill gas
away from the uncovered area of the landfill to minimize the
destruction of vegetation in this area.  The existing landfill
vents would be opened to prevent the build up of gases under the
liner.  Since this system does not involve treatment, the
toxicity of the gas would not be reduced and the potential risks
to public health would remain.  Therefore, EPA does not consider
this alternative protective of public health.  In addition, this

-------
ROD DECISION SUMMARY                                      page 26
         ft Resource RACOVATV
alternative dots not satisfy the statutory preference for
treatment, which is satisfied by other alternatives providing gas
treatment.
                                      •
A detailed assessment of this alternative can be found in
Sections 19 and 20 of the RI/FS Report.

Alternative 3                     Approximate Present Worth Cost:
Synthetic Cover Installation/                    ** $ 5,062,000.
Slope Stabilization

This alternative consists of the following components:

     o  removing sediments and reseeding the wetlands;
     o  installing a chain linked fence;
     o  developing a post closure plan;
     o  upgrading the present surface water runoff management
        system;.
     o  establishing a cover thickness of 24 inches;
     o  establishing vegetation;
     o  installing a synthetic cover on the uncovered area;
     o  stabilizing the 2:1 side slopes by slightly extending the
        slope and installing a terrace;  and
     o  gas collection and treatment;

This alternative contains most of the components in Alternative 2
except this alternative includes installing a synthetic cover on
the uncovered area of the landfill and stabilizing the 2:1 side
slope.  Installing the synthetic cover will minimize
infiltration.  Stabilizing the side slopes will minimize erosion
and maintenance as well as protect the integrity of the
synthetic cover.  Therefore, this alternative complies with RCRA
regulations.  Also, since infiltration is minimized and the 2:1
slopes are stabilized, this alternative provides improved long
term protectiveness by minimizing the potential for groundwater
contamination.  In this alternative, the slopes would be
stabilized by extending the slope slightly and constructing a
terrace.  Approximately 1 acre of land adjacent to the landfill
would have to be acquired to implement this alternative.

Due to the steepness of the side slopes, this alternative will be
relatively difficult to implement, taking approximately 9 to 11
months to design and construct.  The stability of the slopes
will have to be tested during the design phase.

This alternative contains a gas collection and treatment process
that would reduce the toxicity of the gas and reduce the risks to
public-health from exposure to the landfill gas,  A discussion of
this system is presented in the next section of this document,
Section X.B.

Because this alternative would be protective of public health and
the environment, and would comply with ARARs, it has been

-------
ROD DECISION SUMMARY                                      page 27
Landfill & Resource Recoverv Site        	
tentatively selected as the selected remedy, pending a
determination of its implementability (see Sections XI of this
document).

A detailed assessment of this alternative can be found in
Sections 19 and 21 of the RI/FS Report.

** Cost does not include the cost of gas collection and
treatment.

Alternative 4                     Approximate Present Worth Cost:
Synthetic Cover Installation/                    ** $ 5,490,000.
Slope Flattening

This alternative contains all of the components in Alternative 3
except this alternative utilizes a different technique to
stabilize the steep side slopes.  In this alternative, the slopes
would be extended and flattened.until a slope of 3:1 is achieved.
This slope is less steep and is recommended in EPA's guidance for
constructing covers that comply with RCRA regulations.  This
alternative would provide the same level of protection as
Alternative 3 but would be easier to implement.because of the
reduction in the steepness of the slopesI  Present estimates show
this alternative to be slightly more expensive than Alternative
3.  Approximately 3 acres of land would have to be acquired to
implement this alternative and it would also take about 11 months
to design and construct.

Because this alternative would also be protective of public
health and comply with ARARs, this alternative has been retained
as an alternate selected remedy (see Section XI of this
document).

A detailed assessment of this alternative can be found in
Sections 19 and 22 of the RI/FS Report.

** cost does not include the cost of gas collection and
treatment.

Alternative 5                     Approximate Present Worth Cost:
RCRA Guidance Cover                              ** $ 11,670,000.

This alternative consists of the following components:

     o  removing sediments and reseeding the wetlands;
     o  installing a chain linked fence;
     o  developing a post closure plan;             —
     o  upgrading the present surface water runoff management
        system;
     o  constructing a cover according to EPA's RCRA guidance
        which would include flattening the 2:1 side slope,
        installing a synthetic cover on the flattened slope,
        placing a clay barrier over entire Site, and establishing
        vegetation (including placement of a drainage layer); and
     o  gas collection and treatment.

-------
BOD DECISION SUMMARY                                      page 28
       l ft Resource Recoverv
This alternative is similar to Alternatives 3 and 4 except that
it complies with both the RCRA regulations and the specifications
in EPA's guidance document discussed in Section VII.  The RCRA
closure guidance is not an ARAR but is to be considered.
Alternatives 3 and 4 would not include all the elements called
for in the guidance, but they would meet the RCRA closure
performance standards.  This alternative provides the same level
of protection as the previous two alternatives but is twice the
cost.  EPA has determined that this alternative is not the most
cost effective alternative.  Due to the additional requirements,
it would take approximately 3 years to design and construct this
alternative.

A detailed assessment of this alternative can be found in
Sections 19 and 23 of the RI/FS Report.

** Cost does not include the cost of gas collection and
treatment.

        B. Gas Treatment Technologies Analyzed

Three thermal destruction technologies underwent detailed
analysis for the L&RR Site: combustion, flaring and incineration.
Thermal destruction consists of burning the landfill gas to
destroy the hazardous constituents.   Typically, these
technologies can destroy between 90% and 99.99% of the gas that
enters the system.  With the concentration of hazardous
constituents from the RI and this removal efficiency, these
technologies will be protective of human health and the
environment and achieve ARARs.  However, each of the technologies
has advantages and disadvantages with regards to factors such as
implementability and cost which can not be adequately assessed
without Site specific pilot tests.  A brief discussion of each
technology is given below.

A detailed assessment of each technology can be found in Section
24 of the RI/FS Report.

Technology 1                      Approximate Present Worth Cost:
Combustion                                            $1,300,000.

The combustion process is a process that burns the landfill gas
and also generates electricity as a useful by-product.
Therefore, this technology is a resource recovery technology.
Several combustion systems have been installed at municipal
landfills and have been demonstrated for burning conventional
municipal landfill gas, typically achieving 90% destruction.
However, little information is available on the:, effectiveness of
burning hazardous constituents.  Also, due to the acidic
compounds present in the gas, corrosion of the equipment may
occur and increase maintenance costs.

-------
ROD DECISION SUMMARY                                      page 29
Landfill t Resource Recoverv Site
Technology 2                      Approximate Present Worth Cost:
Flaring                                                 $612,000.

The flaring process is similar to combustion except that it does
not contain a generator and therefore will not produce
electricity.  Flaring has been demonstrated to be effective in
removing hazardous constituents in miscellaneous gas streams.
Ninety percent (90%) removal efficiencies have been demonstrated.
However, corrosion could increase maintenance costs.

Technology 3                      Approximate Present Worth Cost:
Incineration                                          $1,277,000.

Incineration is a two step process which routinely achieves 99 to
99.99% destruction.  Incinerators have been demonstrated for
burning both municipal landfill gas and gas streams containing
hazardous wastes.  The technology is readily implementable.


X.      DOCUMENTATION OF SIGNIFICANT CHANGES

There are no significant changes from EPA's Proposed Plan in
EPA's selected remedy.


XI.     THE SELECTED REMEDY

        A. Description of the Selected Remedy

The selected remedy has four major components which together form
a comprehensive approach to Site remediation.  The first two
components, upgrading the landfill closure completed to date and
treating the landfill gas, are intended to control the source •
and minimize the potential of hazardous substances migrating from
the Site.  Remediation of the impacted wetlands is the third
major component which will occur after the landfill has been
upgraded.  The fourth component, Site monitoring, will insure
that the landfill and the gas treatment components remain
effective.

           1. Upgrading the Landfill Closure

The existing landfill closure will be upgraded to meet ARARs and
to insure that it effectively contains the hazardous wastes.  Two
alternatives were selected from the  alternatives developed in
the FS: Alternative 3: Synthetic Cover Installation/Slope
Stabilization and Alternative 4: Synthetic Cover "  ~~
Installation/Slope Flattening.  These two alternatives are
equally protective.  Alternative 3 is estimated 'to be slightly
less expensive. However, due to the steepness of the side slopes,
this alternative may be relatively difficult to implement,
causing the costs to increase.  Also, the stability of the side
slopes must be evaluated during the design phase.  Due to the

-------
ROD DECISION SUMMARY                                      page 30
         & Resource Reeoverv Site
question concerning implementability, Alternative 4 has also been
chosen as a possible alternative.  The choice between the two
alternatives will be specified during the design phase.  The
components of these alternatives are described below.

Fence installation;  Site security will meet the requirements of
40 CFR f 264.14.  To limit Site access and maintain Site
security, a chain-linked fence with barbed wire will be
constructed around the facility.  Along this fence, two access-
road gates (at the facility's north and south entrances from the
Oxford Turnpike) and two walkway gates (on the northern and
southeastern sides of the Site) will be installed.  The walkway
gates provide convenient access to off-site monitoring wells.
The gates will be kept locked and the fence will be posted with
warning signs.

Post-closure Plan Development:  Closed hazardous waste disposal
facilities must be inspected, monitored, and maintained to
prevent adverse effects to human health and the environment in
accordance with 40 CFR Part 264.110-264.120; 264.300-264.339 and
264.340-264.599.  The post-closure plan will specify how these
goals will be achieved at L&RR and must be approved by both EPA
and the State.  The L&RR post-closure plan will contain plans for
monitoring groundwater and landfill gas.  In addition, the post-
closure plan will describe planned operations, or maintenance and
inspection activities, and the frequencies of those activities.
At L&RR, these activities will include the following:

     o  inspection and maintenance of gas and groundwater
        monitoring equipment;
     o  periodic mowing;
     o  inspection and maintenance of the cap's integrity;
     o  inspection and maintenance of the gas collection and  .
        treatment system
     o  inspection and maintenance of surface water management
        system
     o  inspection and maintenance of the security fence; and
     o  protection and maintenance of surveyed benchmarks.

The L&RR post-closure plan will include a schedule of activities
planned during the post-closure period.  The post-closure period
begins upon certification by an independent registered
professional engineer that closure has been completed in
accordance with the plan.  Post-closure care must last for 30
years unless the post-closure plan is amended.

Surface Water Management System•  To limit the potential for
further environmental impact due to erosion and to minimize cover
maintenance, the present surface water management system will be
upgraded and expanded.  First, a stone-lined perimeter drainage
channel will be added to transport high-volume storm flows
(i.e., 24 hour, 25-year storm event) to the sedimentation
basins.  The perimeter channel will collect most of the surface

-------
ROD DECISION SUMMARY                                      page 31
       l & Resource Recovery Site
water.  At the southwestern side of the Site, surface water will
discharge to the existing roadside ditch along Oxford Turnpike.
Second, surface water diversions will be more closely spaced,
approximately 200 feet apart on vertical 3:1 slopes.  Finally, if
the slope is extended, the existing sedimentation.pond (P-3) on
the northeastern section of the Site will be relocated.

Cover Thickness Establishment;  Cover soil consisting of an 18
inch sand layer and a 6 inch topsoil layer capable of supporting
vegetation will be added to areas which presently do not have a
cover thickness of 24 inches.

Vegetation Establishment;  Although vegetation is present on the
landfill, it is stressed in some areas.  To enhance vegetation,
stabilized municipal 'waste water treatment plant sludge will be
incorporated into the top soil.  The sludge will be mixed into
the soil using a rototiller or disc harrow and the area will be
hydroseeded using a sprayed liquid mixture of seed (i.e.,
grass/legume) and fertilizer.  During establishment of the*
vegetative cover, erosion will be controlled by applying either
hay mulch following seeding or a chemical (asphalt) binder during
seeding.  Prior to use, the sludge will be analyzed to determine
whether it meets applicable requirements.

Synthetic Cover Installation/Slope Stabilization;  The difference
between Alternatives 3 and 4 is the method of stabilizing the 2:1
side slope and the type of synthetic cover utilized.  In
Alternative 3, the 2:1 slope will be stabilized by extending the
slope slightly to a slope of 2.5:1 and constructing a terrace
midway down the slope (see Figure XI-1: Comparison of Slope
Stabilization Techniques).  Approximately 1 acre of land will
have to be acquired to construct this alternative.   The unlined
area encompasses approximately 5 acres.  A synthetic membrane
will be installed in this uncovered area (see Figure XI-2:
Alternative 3).  To minimize the potential for slipping,  a 20-mil
HOPE membrane with surface texture will be installed.  In
Alternative 4, the 2:1 slope will be extended to a slope of 3:1.
Approximately 3 acres of land will be acquired.  Since the
potential for slipping is much less on a 3:1 slope, a 20-mil PVC
geomembrane will be used in this alternative (see Figure XI-3:
Alternative 4).  Cover soil as described in the section above
would then be added on top of the synthetic membrane.

           2. Gas Collection and Thermal Destruction

Eighteen gas vents have been installed across the top of the
landfill.  Each vent is made of 6-inch, slotted PVC pipe, and set
60 to 80 feet into the waste.  These vents will be manifolded by
a subsurface horizontal pipe system.  Using this system the
collected gas will be directed to the treatment system located
near the southern portion of the Site.

-------
                    Figure XI-1
       Conceptual Comparison of

     Slope Stabilization Techniques
                                       Limn of Existing
                                       Liner I
        Slope Flattening
        Alternative 4
                     Slope Stabilization
                     nerraced Approach)
                      'tentative 3
•**•'
 Bi
 1
Propeity
Unej

   I
                                  Existing Ground
                                  Surface
                     Synthetic
                     Covers

-------
                                Figure XI-2
                • Landfill & Resource Recovery Site
   Alternative 3: Synthetic Cover/Slope Stabilization
                                                                       page 33
Approximate Area to be
Synthetically Covered

Property Line

Approximate Area Outside
Property Line Affected by Regrading
rrrmr:  Access Road

=^==gg^  Wetlands

    	..  Tributaries

          Residences  —
                                                     Undfill & Resource Recovery Site 15

-------
                      Figure XI-3
            Landfill & Resource Recovery Site
Alternatives 4: Synthetic Cover/Slope Flattening
                                                                  page 34
                                            Trout Brook Pond f

                                   rsnr^r:  Access Road

                                    ^^2gM  W«tlands

                                       	Tributariw

                                             Residences
     Approximate Area to be
     Synthetically Covered
—  Property Line
     Approximate Area Outside
     Property Line Affected by Regrading
                                               Landfill ft Resource Rccovtiy Site 17

-------
ROD DECISION SUMMARY                                      page 35
Three thermal destruction technologies have been selected to
treat the gas: combustion, flaring and incineration.  As  • .
discussed above, these technologies will be protective of human
health and the environment and achieve ARARs.  However, each of
the technologies has advantages and disadvantages in regards to
factors like implementability and cost which can not be
adequately assessed without Site specific pilot tests.
Therefore, the specific technology to be utilized for thermal
destruction will be chosen by EPA during the design phase when
specific information regarding the performance of each is
available.  A brief description of each technology is given
below.

CfnniMig^ifrfl;  Because the landfill gas contains approximately 50%
methane, it can be used to generate electricity.  Combustion.is a
four step process that burns the landfill gas and utilizes the
energy created from burning the gas to generate electricity.  The
process is as follows: (1) condensation/acid scrubbing to remove
moisture and organic acids; (2) burning the landfill gas in an
internal combustion engine; (3) electricity production using
generators for resource recovery; and, (4) discharge of
combustion products to atmosphere.

Since organic acids tend to bind to water molecules, the moisture
present in the landfill gas will be used to remove the acids
present in the gas by passing the gas through a condenser.  This
acid waste stream is a RCRA hazardous waste that will be handled
in compliance with the RCRA regulations.  To obtain a proper
burning mixture, some air must be added to the gas.  Auxiliary
fuel will be used to bring the engine to the proper operating
temperature.  After start up,  the methane in the landfill gas
will be used to fuel the engine.  The electricity generated could
be transmitted to area transmissions lines for use.

Flaring;  The flaring system is similar to combustion except it
does not contain a generator to convert the energy created into
electricity.  The steps are as follows: (1) condensation/acid
scrubbing to remove moisture and organic acids; (2) flaring to
thermally degrade VOCs, hydrogen sulfide and methane; and, (3)
discharge of combustion products to atmosphere.  A single
enclosed flare unit, 6 feet in diameter and 24 feet  high, could
be used for a gas generation rate of 775 cfm.

Incineration;  Incineration is a two step process as follows:  (1)
incineration to oxidize hydrogen sulfide, VOCs and methane; and,
(2) discharge of combustion products to the atmosphere.

Unlike combustion and flaring, the incineration process is
conducted in a closed reaction chamber which operates at a much
higher temperature.  This chamber also allows greater control
over reaction time of the gas.  Because of these two factors,
incineration has the potential to achieve greater removal
efficiencies than combustion and flaring.  Furthermore, this

-------
ROD DECISION SUMMARY                                      page 36
         £ RASO
system destroys the organic acids and eliminates the RCRA waste
stream.

           3. Wetlands Remediation

During the RI, two areas of the wetlands were identified as
needing remediation due to cover material erosion and subsequent
sedimentation, Sections 1 and 3 (see Figure XI-4: Wetlands
Remediation).  Additional areas may be defined during the design
phase if erosion has caused further damage since the RI was
conducted.  In these areas, the sand which has eroded from the
landfill will be excavated and the wetlands will be revegetated.
Approximately 2 to 3 feet of sediment from Section 3 and the
southern portion of Section 1 will be excavated.  Since the
eroded sand is not contaminated, the excavated sediment can be
r•deposited on-site.  To promote wetland revegetation, soils
similar to those of the natural wetland will be placed, and
sedges and others species will be planted.  During revegetation,
the natural contour of the wetland will be restored to maintain
the easterly flow of the creek toward the main wetland body.

           4. Site Monitoring

To insure that the remedy remains protective, both the
groundwater and the air will be monitored periodically.

Groundwater Monitoring;  The following monitoring wells will
compose the groundwater monitoring program.

Walla:  MH-101           CW-5 A,B,C     (15 wells)
        MW-102 A,B       CW-6 A,B,C
        MW-103 A,B       CW-7 A,C
        MW-104 A,B

All wells except MW-104 A6B presently exist on-site.  MW-104 A&B
will be located approximately between well clusters CW-6 and CW-
7, near the stream.  Well 104A will be located in the ice contact
deposits and well 104B in the kame delta deposits.

The above wells will be monitored quarterly for the following
parameters: hazardous substance list(HSL)  volatile organic
compounds (VOCs), pH, temperature, specific conductance,
chloride, arsenic, cadmium, iron, manganese and lead.  On an
annual basis, the following additional constituents will be
analyzed for: barium, chromium, fluoride,  mercury, nitrate,
selenium and silver.

Quarterly monitoring results will be compared to drinking water
maximum contaminant levels (MCLs).  If an MCL is exceeded at a
given well, that well will be resampled and analyzed.  Sampling
results will be reviewed on a periodic basis to determine if a
variation indicative of a plume is present.  In addition, the
monitoring program will be reviewed after a minimum of five years
of monitoring is completed and may be modified.

-------
 )   -     i /
/A  *-  /
                 XI-4     ,
           WETLAND AREAS TO BE
    REMEDIATED DUE TO SEDMENTATION
                   L ft RR SITE
     NORTH SMITHFIELD. RHODE ISLAND

-------
ROD DECISION SUMMARY                                      page 38
lAndfi.ll  ft Resource Recovarv Site
 During the  remedial design, a detailed monitoring plan will be
 developed and  approved by EPA and RIDEM.  This plan will
 incorporate the  requirements of this section and at a minimum
 include  a description of the following: sampling techniques,
 development techniques, analytical methods, QA/QC program, data
 presentation formats and monitoring well proposal.

 The groundwater  monitoring program for the LtRR Site has been
 designed to satisfy the requirements of RCRA detection monitoring
 (40 CFR  264.98).  To meet the requirements of this section, a
 monitoring  program must be based on specific hydrologic
 conditions  and capable of identifying a groundwater contaminant
 plume.

 Air Monitoring;  The air monitoring program will depend on the
 specific technology chosen for gas treatment.  This plan will be
 outlined during  the design phase and will specify the monitoring
 locations,  the sampling technique, the indicator parameters and
.frequency of monitoring.  Depending on the technology, this plan
 may include ambient air monitoring and emissions testing to
 insure that the  system is protecting public health and the
 environment.

         B.  Point of Compliance and Target Cleanup Levels

 Target cleanup levels must be set when risks are posed to public
 health and  the environment from exposure to contaminants at a
 site.  The  point of compliance is the location where the target
 cleanup  levels are met (i.e. the perimeter of a site).  The
 target cleanup levels for the gaseous emissions from the landfill
 are the  Rhode  Island Air Toxic Regulations.  These regulations
 set acceptable contaminant specific ambient levels.  Since these
 are ambient levels, the point of compliance will be at the
 boundary of the  Site.

         C.  Rationale for Selection
                           :

 The rationale  for choosing the selected remedy is based on the
 assessment  of  each criteria listed in the evaluation of
 alternatives section of this document.  In accordance with
 Section  121 of CERCLA, to be considered as a candidate for
 selection in the ROD, the alternative must have been found to be
 protective  of  human health and the environment and able to attain
 ARARs unless a waiver is granted.  In assessing the alternatives
 that met these statutory requirements, EPA focused on the other
 evaluation  criteria, including, short term effectiveness, long
 term effectiveness, implementability, use of treatment to
 permanently reduce the mobility, toxicity and volumer and cost.
 EPA also considered nontechnical factors that affect the
 implementability of a remedy, such as state and community
 acceptance.

 EPA found that Alternatives 3 and 4, as described above, while
 meeting  the criteria of protectiveness and compliance with ARARs,

-------
ROD DECISION SUMMARY                                      page 39
Landfill & Resource Recovery Site   	
are more cost effective than Alternative 5.  A permanent remedy
was considered but not selected for reasons described in Section
XII.D. below.  Alternatives 1 and 2 were rejected as not being
protective of public health and the environment.

A number of Site specific factors also impacted EPA's decision
for the Site.  First, the landfill was presently closed with a
synthetic cover over most of the landfill.  Second, although a
contaminant plume was presently not evident in the groundwater,
given the disposal history it is expected that a plume may
migrate from the Site in the future.  Therefore, the landfill
should be closed in a manner that provides the maximum protection
possible.  The selected remedy will minimize infiltration from
the presently uncovered area in order to prevent off-site
migration.  Third, there is evidence of air impacts from the*
landfill vents.  The selected remedy will include treatment to
reduce these impacts.  And finally, the remedy will end the
erosion into the wetlands from the landfill and remediate present
impacts.  Based upon these factors and the assessment outlined
above, which takes into account the statutory preferences of
CERCLA, EPA selected the remedial approach for the Site.
XII.    STATUTORY DETERMINATIONS

The remedial action selected for implementation at the L&RR Site
is consistent with CERCLA and, to the extent practicable, the
NCP.

        A. The Selected Remedy is Protective of Human Health and
           the Environment

The remedy at this Site will permanently reduce the risks
presently posed to human health and the environment from exposure
to gaseous emissions from the landfill; from sand eroding off the
landfill and into the wetlands; and, from infiltration of rain
and melted snow through the landfill and into the groundwater.

The potential risks to public health from exposure to the
landfill gas will be reduced by treating the landfill gas using a
thermal destruction process.  The three thermal destruction
technologies, combustion, flaring and incineration, typically
achieve destruction and removal efficiencies of 90-99.99%.  EPA
established target cleanup levels based on Rhode Islands Air
Toxic Regulations.  The annual average ambient air
concentrations established in these regulations provide a risk
that's within EPA's acceptable target range of 10""4 - 10~7.
With the results obtained during the RI and the 'removal
efficiencies stated above, these technologies will achieve the
target cleanup levels and will protect human health and the
environment.  Pilot tests will be conducted during the design
phase to insure that the selected remedy is protective and
monitoring will be conducted after construction to insure that it
remains protective.

-------
ROD DECISION SUMMARY                                      page 40
The present impacts to the wetlands will be remediated by
removing the eroded sand and establishing vegetation.  The risk
of future impact will be minimized by upgrading the existing
landfill closure to minimize erosion.  Specifically, the remedy
includes establishing a vegetative cover, stabilizing steep side
slopes and upgrading the surface water management system to
minimize erosion and the risks of future impacts to the wetlands.

Although an organic contaminant plume is not yet evident from the
analytical data collected to date, the historical data supports
the-fact that a plume could emerge in the future.  The potential
risk of contaminating the groundwater will be minimized by
minimizing infiltration to the maximum extent practical.
Specifically, the selected remedy includes installing a synthetic
cover on the uncovered area of the landfill to minimize
infiltration and the risk of contaminating the groundwater.
Also, the groundwater will be monitored on a periodic basis to
insure that the selected remedy remains protective of public '
health and the environment.

        B. The Selected Remedy Attains ARARs

This remedy will meet or attain all applicable or relevant and
appropriate federal and state requirements that apply to the
Site.  Environmental laws which are applicable or relevant and
appropriate to the selected remedial action at the L&RR Site are:

Resource Conservation and Recovery Act (RCRA)
Clean Hater Act (CWA)
Safe Drinking Water Act
Fish.and Wildlife Coordination Act
Executive Order 11990 (Protection of Wetlands)
Clean Air Act (CAA)
Occupational Safety and Health Administration (OSHA)
Rhode Island General Law (RIGL)

Three types of ARARs were identified during the RI/FS: location,
chemical and action-specific ARARs.  A brief narrative summary of
these ARARs follows.

Location-Specific ARARsr  Table XII-1 lists the location-specific
ARARs that were identified during the planning stages of the
RI/FS.  This table gives a synopsis of the requirement and how it
was considered in the RI/FS.  For the L&RR Site, the location-
specific ARARs apply primarily to the  landfill and the wetlands.
During the RI, the existing landfill closure was evaluated
according to the requirements outlined in RCRA regulations.  As
discussed in Section VII, it was determined that the-«xisting
landfill closure does not minimize infiltration, does not
minimize erosion and does not function with minimum maintenance.
The selected remedy meets these requirements by1 installing a
synthetic cover on the uncovered area of the landfill to minimize.
infiltration and by upgrading the surface water management
system, stabilizing the steep side slopes, and establishing a

-------
ROD DECISION SUMMARY                                      page 41
Landfill & Resource Recovery Site    	•
vegetative cover to minimize erosion and maintenance.
Furthermore, the selected remedy will protect the wetlands from
future impacts as required by the ARARs for the  wetlands such as
the CWA.

Chemical-Specific ARARs;  Table XII-2 lists the chemical-specific
ARARs, criteria, advisories and guidance for the L&RR Site.
During the RI, the chemical-specific ARARs were used to assess
the contamination at the Site and to conduct the risk assessment.
The table gives a synopsis of the requirement and explains how
these requirements were considered in the RI/FS.  The significant
findings are outlined below.
                                              i
The concentrations of contaminants in the groundwater at the
boundary of the Site were below their drinking water maximum
contaminant levels (MCLs) and the risk posed by consuming the
groundwater was within EPA's acceptable range.  The selected
remedy includes groundwater monitoring to insure that it
continues to achieve ARARs.

For the surface water, some of the samples contained contaminants
(cadmium, chromiua and cine) ±2ia± vere slightly above aquatic
water quality criteria (AWQC).  However, the risk assessment
indicated that the risk posed by exposure to the surface water
was within EPA's acceptable range and the local environment did
not appear stressed by the occasional exceedance.  It is not
known whether these slight exceedances of the AWQC are caused by
releases from the landfill or by other causes including natural
causes.  Releases from the landfill that would contribute to
surface water would come through groundwater, and can therefore
be detected in the planned groundwater monitoring which includes
cadmium and chromium on a quarterly basis.  In addition, the
1983 Court Order between PTPEM and L&RR, Inc., calls for surface
water monitoring.  EPA believes that the selected remedy will
prevent the landfill from causing or contributing to AWQC
exceedances in the surface water.  The groundwater monitoring
plan will confirm whether or not releases of contaminants from
the landfill are affecting the surface water after completion of
the remedy.  If after completion of the remedy releases that
contribute to exceedances of AWQC are not prevented, further
remedial action will be taken acording to the provisions of
CERCLA and the NCP.

Finally, the existing landfill emissions from the uncapped vents
exceeded Rhode Islands Air Toxic Regulations and pose a potential
threat to public health.  The selected remedy utilizes thermal
destruction to reduce the concentration of contaminants in the
landfill gas.  With the results in the RI and the removal
efficiency of ^90-99.99%, the selected remedy wili achieve these
ARARs.  Pilot "tests will be conducted during the design phase to
insure that the selected remedy achieves ARARs.

-------
ROD DECISION SUMMARY                                      page 42
Action-Specific ARARst  Table XII-3 lists the action-specific
ARARs which were common to all the containment alternatives.
(Alternatives 2-5).  The table gives a synopsis of the
requirement.  During the remedial action, the selected remedy
will comply with all relevant and appropriate RCRA requirements,
including the general closure performance standard (40 CFR S
264.111), and the monitoring, closure and post closure
requirements of 40 CFR Subparts F and G, the landfill closure
requirements of f 264.310, and the other relevant and appropriate
requirements of 40 CFR Subparts B-E, N and O.  Because there is
presently no off-site release of groundwater contamination, the
relevant and appropriate portions of Subpart F are those dealing
with detection monitoring, 40 CFR § 264.90-.98.  The selected
remedy will also comply with OSHA requirements such as those
which apply to working.with hazardous materials.  Additionally,
wetlands remediation will be conducted according to the CWA and
the other requirements, listed in Table XII-1, associated with
dredging and restoring wetlands.  Finally, State requirements
associated with transporting and utilizing municipal waste water
treatment sludge will be followed during establishment of
vegetation.

        C. The Selected Remedial Action is Cost Effective

In the FS, a range of alternatives were developed for
remediating the landfill.  Three of these alternatives,
Alternatives 3, 4 and 5, were equally protective and attained
ARARs.  Once EPA has identified alternatives that are protective
and attain ARARs, EPA analyzes those alternatives to determine a
cost-effective means of achieving the cleanup.  Alternatives 3
and 4 were similar in cost with a net present worth of $5,062,000
and $5,490,000, respectively.  Alternative 5, however, was over
twice the cost of both of these alternatives with a net present
worth of $11,670,000.  The selected remedy will utilize either
Alternative 3 or 4, the most cost effective of the alternatives
developed in the FS for remediating the landfill.  During design,
if factors such as implementability influence the cost of these
alternatives, the most cost-effective one will be chosen.

For treating the landfill gas, three technologies were developed
in the FS: combustion, flaring and incineration.  The costs of
each of these technologies were as follows: $1,300,000, $612,000
and $1,277,000, respectively.  However, the estimated costs are
highly dependent on the cost of operating and maintaining the
system and could vary significantly due to such things as
equipment replacement costs due to corrosion.  Section 121(a) of
CERCLA.requires EPA to take into account the total short- and
long-term costs, including the cost of maintenance for the entire
period during which such activities are required!  Therefore,
before EPA can select the most cost effective technology from
these three, pilot tests are needed to assess the impacts of the
L&RR landfill gases on the operating costs of each system.

-------
      SITE FEATURES
             REQUIREMENTS
                                                             STATUS
      Table XII-1
   LOCATION-SPECIFIC ARARS
     URR SITE

       REQUIREMENT SYNOPSIS
      APPLICATION FOR THE RI/FS
Landfill

Federal Regulatory
Requirement!
RCRA - Standard! for Owners  and     Relevant and
Operator! of Permitted Hazardous    Appropriate
Waste Facilities
 40 CFR 264.13-.16
General facility requirements
outline waste analysis, security
sttssures, and training require-
ments.
Because RCRA-listed hazardous waste* were placed
before 1980, RCRA Subtitle C requirements are
relevant and appropriate.
                      RCRA  - Preparedness snd Prevent-
                      ion (40 CFR 264.30 - 264.37)
                      RCRA - Contingency Plan and
                      Emergency  Procedures (40 CFR
                      264.SO - 254.56)
                      RCRA - Croundwater Protection
                      40 CFP 264.98
                      RCRA - Closure  snd  Post-closure
                      (40 CFR 264.110 - 264.120)
                                   Relevsnt snd    This regulation outlines safety
                                   Appropriate     equipment and spill-control
                                                   requirements for hazardous waste
                                                   •facilities.  Part of the regulation
                                                   includea a requirement that
                                                   facilities be designed, maintained,
                                                   constructed, and operated so that the
                                                   possibility of an unplanned release
                                                   threatening human health or the
                                                   environment could be minimized.

                                   Relevsnt snd    This regulation outlines the
                                   Appropriate     requirements for emergency
                                                   procedures to be used following
                                                   explosions snd fires.  This
                                                   •regulation also requires that
                                                   threats to public health and the
                                                   environment be minimized.

                                   Relevant and    Under this regulation,
                                   Appropriate     groundwater monitoring program
                                                   requirements are outlined.
                                    Relevant.snd   This  requirement details the
                                    Appropriate    specific  requirements  for
                                                   closure and  post-closure of
                                                   hszsrdous waste fscilities.
                                         RCRA requirements were considered when
                                         evaluating  the effectiveness of the present
                                         landfill, and will be further considered
                                         when evaluating  the design of potential
                                         alternatives.
                                         BCRA requirements were  considered when
                                         evaluating  the effectivenss of the present
                                         landfill, and will be further considered
                                         when evaluating  the design of potentisl
                                         alternatives.
                                         Croundwater  SMnltoring must be  considered
                                         for each alternative.  During alternatives
                                         snalysis, the locstion and depth of
                                         monitoring wells  will be  evaluated for
                                         use in this  monitoring program.

                                         Long-tens monitoring and  maintenance
                                         portions of  the  regulstion will be
                                         considered during remedial design.
         12.87.ST
         0001.0.0
                                                                                                                                                              CO

-------
                                                                             Table XII-1 - continued
                                                                            tOCATIM-SKClFIC ARAMs
                                                                              un SITE
      SITE FEATURES
                                  REQUIREHEHTS
    STATUS
                                                                                            sniopsis
                                               APPLICATION FOR Ttt RI/FS
Federal Regulatory
Requirements
(continued)
                     RCRA  - Landfills (40 CFR 264.300
                     24.339)
Relevant and
Appropriate
State Regulatory
Requirements
                      Fiab and Wildlife
                      Coordination Act
                      (16 U.S.C.  Ml)
                      Rhode Island Rules  for Solid
                      Waste Management Facilities
                      (RIGL 23 -  It.9)
                                                         Applicable
Applicable
                      Rhode Island Hazardous Waste
                      Rules and Regulations (RIGL
                      23 • 18.9)
                                                         Relevant and
                                                         Appropriate
Wetlands. Trout Rrook

Federal Regulatory
Requirements
                      Clean Water Act (CWA) - 40 CFR
                      Section 404
State Regulatory
Requirementa
                      Rhode laland Freshwater Wetlands
                      law-Rhode laland General Lav
                      (RIGL) • Title 2 Chapter 1  (2-1)
Applicable
Applicable
                      Rhode laland Vater Quality          Applicable
                      Regulations (RICL 46-12. 42-17.1,
                      42-35)
Covers design and operating
requirements, aa well aa
post-closure care options
for landfills.  Closure and
post-closure care must be attained
in accordance with the outlined
disposal requirements.

This regulation requires sny
federal agency proposing to
•edify a body of water to consult
with the U.S. Fish and Wildlife
Services.  This requirement is
addressed under CWA Section 404.

Outlines regulations for sanitary
landfills.  Includes Initial
investigation, site grounduster,
operating and closure plans.  Closure
requirements include 24 inches of
cover Material to be maintained on
all surfacea and faces of the land-
fill.

These requirements correspond to
RCRA hazardoua waste regulations.
Compliance with RCRA'will generally
achieve compliance with theae
regulations.
Regulates dischargee of dredged or
fill material into U.S. waters.
Regulstes snd preserves swamps,
marshes, and wetlands.  Includes
maintaining capscity to support
wildlife snd set ss buffer xome for
flood conditions.

Regulates restoration, enhancement,
and preservation of stste waters.
The landfill cover must comply with require
ments for disposal closure.  Performance
evaluation of eiisting cover has been
completed snd any potential remedial
alternatives must address areas of non-
compliance to attain disposal closure.
                                                         During the identification,  screening,  and
                                                         evaluation of alternatives, the effects on
                                                         wetlands will be evaluated.  If an alterna-
                                                         tive would modify a body of water, U.S. Fisl
                                                         and Wildlife Services will  be consulted.
Potential remedial alternativea must addres
sreas of landfill cover that do not meet
24-inch requirement, aa well aa any other
areaa of noncompliance.
                                                         Where RCRA regulations have jurisdiction,
                                                         these requirements will generally correapoo<
                                                         and be attained if more stringent than RCRA
Protection of the  adjacent wetland.  Applie
to sedimentation cauaed by erosion of  land-
fill cap  fill material.

Considerations such as reducing  aedimentati<
to maintain the adjacent wetland'n water
storsge capsbilities will be addressed for
the RI/FS.          <  I
                                                                                                                  Potential remedial alternatives must addres>
                                                                                                                  this regulation because the adjacent wetlauf
                                                                                                                  is a state water.
                                                                                                                                                           1
         I2.I7.ST
         0002.0.0

-------
                                                                            Table XII-1 -  continued
                                                                            LOCATION-SPECIFIC ARARS
                                                                              L&RR SITE


      SITE FEATURES	REQUIREMENTS	STATUS	REQUIREMENT SYNOPSIS	APPLICATION FOR THE RI/FS	

State Regulatory      Rhode  Island Water Quality          Applicable      Water quality standards to be aiain-      During identification,  screening,  and evalu-
Requireiaenla          Standarda  (RICL 46-12)                              tained in atate watera.  Generally, a    atioo of  alternatives,  BHPa will be  conaidered
(continued)                                                              cheaiical-apecific ARAR, but applicable   to control  sedimentation to the wetland
                                                                         aioce it provides physical criteria,     cauaed by erosion of the landfill  cover
                                                                         such aa Best Management Practicea        material.
                                                                         (BHPa), to control aedimeotation.

Federal Criteria,      Wetlanda Executive Order            To be           Prohibits the undertaking of new         This regulation  will be conaidered during  th'e
Guidance, Adviaories  (EO 11990)                          Conaidered      construction in wetlands.                RI/FS for uae in planning remedial actions.
to be Considered

                      EPA Guidance - "Covers for          To be           Outlinea the three components            These design guidance criteria were  used
                      Uncontrolled Hazardous Waste        Considered      that offer detailed guidance for         for the preliminary cover assessment aa  a
                      Sites" (EPA/540/2-85/002)                           the design of a cover system which       baseline  for determining the  compliance  of
                                                                         will achieve the specified per-          the existing cover  with RCRA  requirements.
                                                                         formance standards of RCRA landfill      These criteria will also be conaidered during
                                                                         covera.                                  alternative development and evaluation.
                                                                                                                                                             I
                                                                                                                                                              in
         12.B7.5T
         nnni i n

-------
quiremeat Type
           Requirement
                                                                        Table XII-2
                                                COMICAL-SPECIFIC ARARS AND CRITERIA, ADVISORIES. AMD GUIDANCE
                                                                           LUUt Sin
                                                     Requirement Synopaia
          consideration in the m/rs
deral Regulatory
quiremeata
SDWA • Maiimum Contaminant Level•
(MCLa) (40 CFR Ul.ll - 141.16)
deral Criteria,
Iviaorlea, aad
idaace
                                           NCLa have been promulgated for a  number of
                                           organic aad inorganic contaminanta.
                                           Theae level* regulate the concentration of
                                           contaminants in public drinking water
                                           supplies, but may alao be considered relevant
                                           and appropriate for groundvater aquifera
                                           used for drinking water.
Wfcen tlM risk* to kwaaa nealtk due to coMtavption
of groondwatar wen aaaeaaed, contaainant
cencentrationa were compared to their NCLa.  Only
iron and aanganeae eiceeded tneir aecondary
levels.  Secondary atandarda are not health-
baaed; therefore, iron and annganese are not
considered contaminants of concern.
                       Federal AoMent Water Quality
                       Criteria (AWQC)
                                        Federal AUQC are health-baaed  criteria
                                        that have been developed for 95
                                        carcinogenic and noncarcinogenic  compounds.
                                                                                           AWQC wert  conaldered  in characterizing  riaka  to
                                                                                           human  health and aonatlc organiama dne  to
                                                                                           contaminant  concentrationa  in the wetlanda  and
                                                                                           Tront  Irook.   lecawae thia  water ia not naed  aa a
                                                                                           drinking water aource. the  criteria developed for
                                                                                           aquatic ornaoiama                    were un«-«l.
                       Health Adviaorles (EPA Office of
                       Drinking Water)
    EPA Riak Reference Doeea  (RfDa)


1   '   f  ?
                          •

    EPA Carcinogen Asaessment Croup
    Potency Factora
                                        Health adviaoriea are eatimatea of  risk due
                                        to consumption of contaminated drinking
                                        water; they conaider noncarcinogenic
                                        effecta only.

                                        RfDa are dose levela developed by
                                        EPA for noncarcinogenic effecta.
                                                               Potency factora arc developed by EPA
                                                               from Health Effecta Aaaeaamenta or
                                                               evaluation by the carcinogen assessment
                                                               group.
                                                                                           Health adviaoriea were  considered  for  contaminanta
                                                                                           in groundwater that may be used for  drinking
                                                                                           water.
                                                                                                              EPA RfDa were uaed to characterise riaka dtte to
                                                                                                              expoauro to groundwater comtaminanta.  They were
                                                                                                              conaidered for noncarcinogena including 2-butanone
                                                                                                                 ' lead.
                                                                                       EPA carcinogenic potency factora were uaed to
                                                                                       compute the individual incremental cancer riak
                                                                                       resulting from expoamre to araenie.
       12.17.
       0001.0

-------
                                                                         Table XII-2  - continued
                                                  CHEMICAL-SPECIFIC ARARs AND CRITERIA, ADVISORIES, AND GUIDANCE
                                                                            L&RR SITE


Requirement Type	Requirement	Requirement Synoptit	Consideration in the RI/FS	

                        Acceptable Intake - Chronic (AIC)        AIC and AIS  values  are developed  fro* RfDa      AIS and AIC values were used to characteriie the
                        and Subchronic (AIS) - EPA Health        and HEAa for noncarcinogenlc  compounds.         risks due to several noncarcinogens in ground-
                        Assessawnt Documents                                                                   water and aurfsce water.  These noncarcinogens
                                                                                                               include 2-butanone, trans-1,2-dichloroethene,
                                                                                                               1,1-dichloroethane, lead, and zinc.

Rhode Island           ' Rhode Island Water Quality Standards    Freshwater guidelines were  developed for        Water quality stsndsrds were compared to AWQCs
Criteria,  Advisories,    (RIGL 46-12)                            several organics snd inorganics.                for compounds such as toluene and araenic.
and Guidance
                        Rhode Island Air Toxics Regulation      Esiissions standards developed for traditional   Air modeling results were compared to these
                                                                and nontraditional  stationary sources           regulations when airborne risks were characterized.
                                                                including landfill  vents.
                                                                                                                                                                *
         12.87.99T
         0002.0.0

-------
                                                                               TablS  XII-3
                                                                             ACTION-SPECIFIC AMAHS

                                                                   LANDFILL AND RESOURCE RECOVERY
                                  REQUIRMKTS
                                        STATUS
                                         REQUIREICNT STNOFSI8
Federal Regulatory
Requirements
ROW - Subpart I:
Standards
General Facility
                      RCRA - Subpart C: Preparedness
                      and Prevention (40 CFR 264.30 -
                      264.37)
                      RCRA - Subpart  D: Contingency
                      Flan and Emergency  Procedures
                      (40 CFR 264.SO  - 264.56)
Relevant and    General facility requirements
Appropriate     outline waste analysis, security
                measures, and training require-
                ments.

Relevant and    This regulation outlines safety
Appropriate     equipment and spill-control
                requirements for hazardous waste
                facilitiea.  Fart of the regulation
                includes a requirement that
                facilities be designed, maintained,
                constructed, and operated to minimize
                the possibility of an unplanned release
                that could threaten human health or
                the environment.

Relevant and    This regulation outlines the
Appropriate     requirements for emergency
                procedures to be used following
                explosions and firea.  This
                regulation also requires that
                threats to public health and the
                environment be minimiied.
                      RCRA - Subpart F:  Releases  From     Relevant aod
                      Solid Waste Management  Units        Appropriate
                                                   Under  this  regulation,
                                                   groundwater monitoring progri
                                                   requirements  are  outlined.
                      RCRA - Subpart C:  Closure  and      Relevant and
                      Post-Closure (40 CFR 264.110  -      Appropriate
                      264.120)
                                                   This  requirement  details the
                                                   specific  requirements  for
                                                   closure and post-closure of
                                                   hazardous waste fscilities.
        1.M.11IT
             0.0
                                                                                                                                       CD

-------
                                  REQUIREMENTS
                     'able XII-3 -  continued
                    ACTION-SPECIFIC ARARS

          LANDFILL AND RESOURCE RECOVERY

    STATUS	REQUIREMENT SYNOPSIS	
Federal Regulatory
Requirementt
(continued)
                      RCRA -  Subpm N: Landfills
                      (40 CFR 264.300  - 264.339)
Relevant and
Appropriate
                      RCRA - Subpart 0:  Incinerators
                      (40 CFR 264.340  -  264.599)
                      Clean Water Act  (CVA)  (Section
                      404) .

                      Clean Air Act  -  National  Air
                      Quality Standarda  for  Total
                      Suspended Participates
                      (40 CFR SO.6 - 50.7)

                      OSHA • General Industry Standards
                      (29 CFR 1910)
Relevant-and
Appropriate
Applicable


Relevant and
Appropriate
Applicable
                      OSHA - Safety and Health Standards   Applicable
                      for Federal  Service Contracta
                      (29 CFR 1926)

                      OSHA - Recordkeeping,  Reporting,     Applicable
                      and Related  Regulations
                      (29 CFR 1904)

                      DOT Rules for the Transportation     Applicable
                      of Hazardous Haterials
                     i(49 CFR 107, 171.1 - 171.500)


                      Fish and Wildlife                   Applicable
                      Coordination Act
                      (16 U.S.C. 661)
Covers design and operating
requirements, as well as
post-closure care options
for landfills.  Closure and
post-closure care must be attained
in accordance with either the
outlined disposal requirement* or
by the site-specific alternate
method.

This regulstion specifies the per-
formance standards, operating
requirements, monitoring, inspection,
and closure guidelines of any
incinerator burning hazardous waste.

Regulates discharges of dredged or
fill material into U.S. waters.

This regulation specifies maximum
primary and secondary 24-hour
concentrations for particulate'
matter.

This regulstioo specifies the 8-hour,
time-weighted average concentrations
for various organic compounds.

This regulation specifies the type of
safety equipment and procedures to be
followed during site remediation.

This regulation outlines the record-
keeping and reporting requirements for
'an employer under OSHA.

This regulation outlines procedures
for the packaging, labeling,
manifesting, and transport of
hazardous materials.

This regulstion requires any
federal agency that proposes to
modify • body of water to consult
with the U.S. Fish and Wildlife
Services.  This requirement is'    '<
addressed under CVA Section 404.  '
                                                                                                                                                                n
                                                                                                                                                                a.
         1.88.HIT
         0007.0.0

-------
                                                                             Table XlI-3 - continued
                                                                             ACTION-SPECIFIC ARAKS
                                                                   LANDFILL AND RESOURCE RECOVERY
                                   REQUIRCHENTS
    STATUS
REQUIREMENT SYNOPSIS
State Regulatory
Requirements
                      Rhode Island Rules for Solid
                      Watte Management Facilities
                      (November 1, 1912)
                      Rhode Island Natardous Watte
                      Rules aid Regulations
                      (June 21, 1984)
                      Rhode Island Freshwater Wetlands
                      Law - Rhode Island General Law
                      (RICL) - Title 2 Chapter 1 (2-1)
                      Rhode Island Water Pollution
                      Control Law (RICL 46 • 12)
                      Rhode Island Water Quality
                      Regulations (RIGL 46-12, 42-
                      17.1, 42-35)

                      Rhode Island Water Quality
                      Standards (RICL 46-12)
                     'Rhode Inland Air Pollution
                      Control Regulations
                      (August 2, 1967)

                      Rhode Island Air Pollution
                      Control Act  (23-23, 23-23.1)
Applicable      Outlines regulations for sanitary
                landfills.   Includes initial
           .     investigation, site groundwater,  and
                operating and closure plans.   Closure
                requirements include 24 'inches of
                cover Mterisl to he Maintained on
                •11 surfaces and faces of the land-
                fill.

Relevant and    These requirements correspond to
Appropriate     RCRA hazardous waste regulations.
                Compliance with RCRA will generally
                achieve compliance with these
                regulations.

Applicable      Regulates and preserves swamps,
                marshes, and wetlands.  Includes
                maintaining capacity to support
                wildlife and act as buffer zone for
                flood conditions.

Relevant and    These requirements correspond
Appropriate     to CWA regulations.  Compliance
                with the relevant sections of
                CWA will generally achieve
                compliance with these requirements.

Applicable      Restoration, enhancement, and pre-
                servation of state waters.
Applicable      Water quality standards to he main-
                tained in stste waters.  Generally, •
                chemical-specific ARAR, hut applicable
                because it provides physical criteria
                such as Rest Nanagement Practices
                (RHPs) to control sedimentation.

Relevant and    Details the requirements, limitations,
Appropriate     and exemptions of state air emission
                regulations for specified substances.

Relevant and    Outlines the policy of preserving,
Appropriate     protecting, and improving the air
                resources of Rhode Island.       ;
            jlllT
            (0.0

-------
                                                                            Table  XII-3  - continued
                                                                            ACTION-SPECIFIC ARAKS

                                                                  LANDFILL  AND RESOURCE RECOVERY
                                  REQUIREMENTS
STATUS
REQUIREMENT SYNOPSIS
State Regulatory
Requirementt
Federal Criteria.
Guidance, Advisories
to be Considered
                     Rhode Island Rules and              Applicable
                     Regulations Pertaining to the
                     Disposal, Utilization, and
                     Transportation of Waitewaler
                     Treatment Facility Sludge.
                     (September 1985)

                     Rhode Island Air Toiic              Applicable
                     Regulations (Regulation No. 22)
                     Wetlands Executive Order            To be
                     (EO  11990)                          Considered
                      EPA Guidance Document - "Covert     To be
                      for Uncontrolled Hazardous Waste    Considered
                      Sites"  (EPA/540/2-85/002)
            Thla requirement applies to the
            diaposal of sludge by land
            application or incorporation of
            the sludge into the soil for
            silvicultural purposes.
            Liaiits the emission of listed
            substances fro» stationary sources.
            Prohibits the undertaking of new
            construction in wetlands, which
            includes dredging.

            Outlines the three components
            that offer detailed guidance for
            the design of a cover system which
            will achieve the specified per-
            formance standards of RCRA landfill
            covers.
                                                                                                                                                                in
        1.88. HIT

-------
ROD DECISION SUMMARY                                      page 52
        D. The Selected Remedy Utilizes Permanent Solutions and
           Alternative Treatment Technologies or Resource
           Recovery Technologies to the Maxima Extent
           Practicable

During the FS, EPA developed one alternative that was considered
a permanent solution, Alternative.6.  This alternative consisted
of excavating the landfill wastes; incinerating the removed
wastes at an off-site, RCRA compliant facility; and, wetlands
sediment removal and disposal.  However, this alternative was
eliminated from further consideration during the initial
screening process for a number of reasons.  The significant
reasons are summarized below.

First, significant public health and environmental risks would be
posed by its implementation.  Excavation of the wastes is likely
to release VOCs and particulates to the atmosphere, including
asbestos and metal fibers known to be disposed at the Site,
creating both on-site and off-site risks due to inhalation.
Second, because the area of hazardous waste cannot be clearly
defined, it was assumed that all of the landfill wastes must be
removed and treated.  It would take approximately 90 years to
implement this alternative.  Third, incinerator capacity nation
wide is insufficient for the quantity of wastes in the landfill
and extremely costly.  The estimated cost was $2.6 billion
dollars.  A more detailed discussion of the reasons for
elimination of the excavation and treatment alternative is
presented in Appendix AA of the RI/FS Report.

In conclusion, the long term uncertainties associated with the
selected remedy, a land disposal remedy, are much less than the
risks posed, the implementation problems and the costs associated
with implementing a permanent remedy.  Furthermore, the selected
remedy includes Site monitoring to insure that it remains
protective.  Therefore, the selected remedy utilizes permanent
solutions and alternative treatment to the maximum extent
practical.

The selected remedy identifies three technologies to treat the
landfill gas.  One of these technologies, combustion is
considered a resource recovery technology because it generates
electricity while destroying the hazardous constituents in the
gas.  This factor may reduce the costs of implementing this
technology.  EPA will consider this factor when selecting the gas
treatment technology during the design phase.

        E. The Selected Remedy Partially Satisfies the Preference
           for Treatment as a Principal Element
                                                A
As stated above, excavation and treatment of the source material
is impractical, involves unacceptable risks and is not cost
effective.  The selected remedy has three components: upgrading
the landfill closure; treating the landfill gas and monitoring
the Site.  The second component, treating the landfill gas, will

-------
ROD DECISION SUMMARY                                      page 53
             'source Recovery Site	:	
reduce the volume, toxicity and nobility of the hazardous
substances in the gas and the risks posed from exposure.
Therefore, the gas treatment component partially satisfies the
preference for treatment as a principal element of the remedy.
XIII.   STATE ROLE

The Rhode Island Department of Environmental Management  (RIDEM)
has reviewed the various alternatives presented in the
Feasibility Study and EPA's preferred alternative as presented in
the Proposed Plan.  The State has also reviewed the Remedial
Investigation and Feasibility Study to determine if the selected
remedy is in compliance with applicable or relevant and
appropriate State environmental laws and regulations.  The RIDEM
concurs with the components of the selected remedy for the L&RR
•Site which are consistent with the 1983 Court Order and Consent
Order and Agreement between RIDEM and L&RR, Inc.  In regards to
the additional components, RIDEM recognizes that they are not
inconsistent with the 1983 Court Order and provide additional
protection.  RIDEM also recognizes that EPA's selected remedy,
are required by CERCLA and the NCP.  A copy of the declaration of
concurrence is attached as Appendix C.

-------
           APPENDIX A






     RESPONSIVENESS SUMMARY






Landfill i Resource Recovery Site

-------
                LANDFILL t RESOURCE RECOVERY SITE
                      Responsiveness Summary
                        TABLE OF CONTENTS
Contents                                             page
Preface 	   1

I.   RESPONSIVENESS SUMMARY OVERVIEW  	   2
     A.   Site Background	   2
     B.   Overview of Remedial Alternatives and EPA's
          Proposed Plan	   2
          1.   Remedial Alternatives  	   3
          2.   Gas Treatment Technologies 	   3
          3.   EPA's Proposed Plan	   4
     C.   Overview of Comments Received During the Public
          Comment Period  	 	   4
          1.   Overview of Comments from Community Members   .   4
          2.   Overview of Comments from RIDEM  	   5
          3.   Overview of Comments from the Potentially
               Responsible Parties (PRPs) 	   5

II.  BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS ....   6

III. SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC COMMENT
     PERIOD AND EPA RESPONSES TO COMMENTS 	   7
     PART 1.   COMMUNITY COMMENTS	   7
               A.   CONCERNS REGARDING THE RESPONSIBLE PARTY  .   7
               B.   GROUNDWATER MONITORING  	   9
               C.  . MISCELLANEOUS	10
     PART 2.   RIDEM COMMENTS	11
               A.   TECHNICAL CONCERNS REGARDING EPA
                    INVESTIGATIONS AND THE PROPOSED PLAN  .  .  11
               B.   ALTERNATIVE PREFERENCE  	  16
     PART 3.   POTENTIALLY RESPONSIBLE PARTIES COMMENTS ...  17
               A.   TECHNICAL CONCERNS  	  17
               B.   LEGAL CONCERNS REGARDING EPA
                    INVESTIGATIONS AND THE PROPOSED PLAN  .  .  40

IV.  REMAINING CONCERNS 	  50

-------
RESPONSIVENESS SUMMARY                                     page 1
Landfill t Resource Recovery Site	
                             Preface


     The U.S. Environmental Protection Agency (EPA) held a public
comment period from July 20, 1988 through September 2, 1988 to
provide an opportunity for interested parties to comment on*EPA's
Remedial Investigation (RI), Feasibility Study (FS), and Proposed
Plan for the Landfill and Resource Recovery Site (L&RR) in North
Smithfield, Rhode Island.  On August 10, 1988, EPA held an
informal public hearing to provide an opportunity for the public
to submit oral comments to EPA.
     The purpose of this Responsiveness Summary is to document
EPA's responses to the comments and questions raised during the
public comment period.  EPA considered all of the comments
summarized in this document prior to the Agency's final selection
of a remedy for the L&RR Site.

     This Responsiveness Summary is organized into the following
sections:

I.   Responsiveness Summary Overview — This section briefly
     outlines the history of the Site and the remedial
     alternatives evaluated in the FS, including EPA's preferred
     alternative.  This section also includes an overview of the
     comments that EPA received during the public comment period.

II.  Background on Community Involvement and Concerns — This
     section provides a brief history of community interests and
     concerns regarding the L&RR Site.

III. Summary of Comments Received and EPA Responses — This
     section provides a detailed summary of both the written and
     oral comments received during the public comment period and
     provides EPA's responses to these comments.   Part 1
     summarizes comments received from citizens and other
     community interest groups.  Part 2 summarizes comments from
     the Rhode Island Department of Environmental Management
     (RIDEM).  Part 3 summarizes comments received from
     potentially responsible parties (PRPs).  All of the parts
     are arranged by subject matter.

IV.  Remaining Concerns — This section describes concerns that
     will continue to be addressed by EPA during design and
     implementation of the selected remedy.

     Attachment A — This attachment includes a list of the
     community relations activities conducted by\RIDEM and EPA
     during the remedial history of the Site.

-------
RESPONSIVENESS SUMMARY                                     page 2
I.   RESPONSIVENESS SUMMARY OVERVIEW

     A.   Site Background

     The L&RR Sit« is an inactive landfill that covers
approximately 28 acres of a 36 acre parcel of land on Oxford
Turnpike in North Smithfield, Rhode Island.  The landfill was
reportedly used from 1927 until 1985 for the disposal of
commercial, industrial, and residential waste.  Between 1977 and
1979, the landfill reportedly accepted hazardous waste.  From
1974 to 1985, the landfill was operated by Landfill and Resource
Recovery, Incorporated (L&RR, Inc.), the current property owners.
     In 1979, L&RR, Inc. covered what they defined as the
hazardous waste area of the landfill with a synthetic cover.  The
Site was added to the Superfund National Priorities List (NPL), a
list of the nation's hazardous waste sites eligible to receive
federal Superfund monies for cleanup, in 1982.
     In 1985, the landfill owners ceased accepting wastes and *
began closing the landfill as specified in plans included in a
1983 Court Order and Consent Order and Agreement, referred to in
the remainder of this document as "the 1983 Court Order", between
RIDEM and L&RR, Inc.  As part of this process, the landfill
owner covered approximately 80% of the landfill with another
synthetic cover and soil to support vegetation.
     In 1988, EPA completed a comprehensive study at the L&RR
Site called a Remedial Investigation/Feasibility Study (RI/FS).
The RI was conducted to define the nature and extent of
contamination in the groundvater, air, and nearby surface waters.
The FS was conducted to identify and evaluate remedial
alternatives that would be effective in addressing contamination
at the Site.  The Record of Decision (ROD) is written at the end
of the RI/FS phase of the Superfund process and describes EPA's
selected remedy as well as EPA's rational for selection.

     B.   Overview of Remedial Alternatives and EPA's Proposed
          Plan

     Using the information gathered during the RI, EPA identified
three general objectives for the Site:  1) treat the landfill gas
to reduce the potential public health risks from exposure to the
landfill vent emissions;  2) restore the wetlands that have been
affected by erosion from the landfill and prevent future adverse
impacts caused by erosion; and 3) close, maintain, and monitor
the landfill so that it is protective of public health and the
environment and complies with federal and state regulations.
     After identifying site-specific objectives, EPA developed
and conducted a detailed analysis of five remedial alternatives
and three gas treatment technologies for the Site.  The remedial
alternatives and the gas treatment technologies analyzed for the
L&RR Site in the FS are summarized in the following sections.

-------
RESPONSIVENESS SUMMARY                                     page 3
Landfill & Resource Recovery Site     	
          1.   Remedial Alternatives

No Action fAlternative 11.  This alternative would consist solely
of long-term groundwater monitoring.

.Vegetation Establishment  (Alternative 2).  This alternative would
involve upgrading the existing landfill closure by covering the
landfill with 24 inches of soil and planting vegetation.  This
alternative would also include the following components:
removing sediments from and reseeding the wetlands; installing a
fence around the site; developing a landfill post-closure plan;
upgrading the surface water runoff management system; and
installing a passive gas collection system.

Synthetic Cover Installation/Slope Stabilization (Alternative 31.
This alternative would include all of the components of
Alternative 2 but would also involve stabilizing the steeply  .
sloping sides of the landfill in the northeast portion of the
Site by grading the slope and adding a terrace.  Then a
synthetic cover would be installed over the stabilized slope.
Additional soil would be placed on the synthetic cover and
vegetation would be established.  In addition, this alternative
includes installing a gas collection and treatment system rather
than the passive gas collection system in Alternative 2.

Synthetic Cover Installation/Slope Flattening fAlternative 41.
This alternative is identical to Alternative 3 except the steep
slopes would be stabilized by flattening them to a greater
degree.

RCRA Cover Guidance (Alternative 51.  This alternative would
involve flattening and covering the steep sides of the landfill
as well as placing a clay barrier, drainage layers and a new
vegetative cover over the entire landfill.  This alternative was
developed according to an EPA guidance document for constructing
covers for hazardous waste sites.  Alternative 5 also would
include all of the other components included in Alternatives 3
and 4 and gas treatment.

          2.   Gas Treatment Technologies

Combustion.  Combustion would entail burning the landfill gas in
an internal combustion engine to produce electricity as a useful
by-product.

Flaring.  The flaring process would burn the landfill gas in a
manner similar to combustion but does not produce electricity.

Incineration.  Incineration would burn landfill gases at high
temperatures in a closed reaction chamber.      '<

-------
RESPONSIVENESS SUMMARY                                     page 4
          3.   EPA*s Proposed Plan

     EPA*s selection of a preferred alternative, as outlined in
the Proposed Plan, was the result of a comprehensive evaluation
and screening process.  EPA's Proposed Plan included the
following three components:

     o    The existing landfill closure would be upgraded to
          effectively contain the wastes.  EPA selected
          Alternatives 3 and 4 as the Agency's preferred
          alternatives for this component of the Proposed Plan.
          EPA will choose one of the two alternatives during the
          remedial design phase of the project after site-
          specific tests have been conducted;

     o    A landfill gas collection and thermal destruction
          system would be constructed to treat the landfill gas.
          EPA has chosen three thermal destruction technologies
          for treatment of the landfill gas.  The specific
          technology will be selected by EPA during the design
          phase of the project, when specific information
          regarding the performance of each technology is
          available; and,

     o    The groundwater and air would be monitored on a regular
          basis to ensure the Site remains protective of public
          health and the environment.

For more details on the FS alternatives and EPA's preferred
alternatives, refer to the Proposed Plan.

     C.   Overview of Comments Received During the Public Comment
          Period

     EPA received comments from three community members, RIDEM,
technical and legal representatives of L&RR, Inc., and General
Dynamics.  In Section III of this document, these comments are
summarized and EPA responses are provided.  A general overview of
the comments received is provided below.

          1.   Overview of Comments from Community Members

     Community members, including a representative of Protect Our
Water, a local citizens' group, indicated general support of
EPA's Proposed Plan.  However, each commenter expressed serious
concern about the possibility that the landfill owner might
operate the landfill gas treatment system.  Area residents also
expressed concern that the groundwater monitoring wells are not
close enough together to ensure that a contaminant plume would be
detected.  Community comments and EPA responses ;are provided in
Section III, Part 1 of this document.

-------
RESPONSIVENESS SUMMARY                                     page 5
Landfill & Resource Recovery Site  	
          2.   Overview of Comments from RIDEM

     In general, RIDEM recommends that EPA consider the
implementation of the closure measures outlined in the 1983
Court Order between RIDEM and L&RR, Inc., combined with wetlands
restoration as the remedy for the L&RR Site.  RIDEM stated that
EPA should provide additional justification to support the need
for a synthetic cover on the uncovered portion of the landfill.
RIOEM's comments and EPA responses are provided in Section III,
Part 2 of this document.

          3.   Overview of Comments from the Potentially
               Responsible Parties (PRPs)

     Wehran Engineers, Inc., and Dean Temkin, Esq., submitted
extensive comments on behalf of the owner and operator of the
L&RR Site.   Both commenters stated their strong belief that the
1983 Court Order between RIDEM and L&RR, Inc., includes
appropriate and adequate measures to ensure protection of public
health and the environment, and that no additional remedy is
needed.  Other general issues addressed by the commenters
included the following:

o    The appropriateness of the risk assessment exposure
     assumptions-relating to the landfill vent emissions;

o    The validity of the model used by EPA to measure the
     performance of the landfill;
                                                        •
o    EPA's interpretation of which federal and state regulations
     must be complied with; and,

o    The appropriateness of including wetlands remediation as
     part of a Superfund action.

     The commenters also included clarifications of the Site
history, particularly relating to the 1983 Court Order between
RIDEM and L&RR, Inc.  PRP comments and EPA responses to these
comments are provided in Section III, Part 3 of this document.

-------
RESPONSIVENESS SUMMARY                                     page 6
landfill £ Resource Recoverv Site
II.  BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS

     According to Site records, community concern about and
interest in the L&RR Site has been moderate to strong since the
aid 1970s, when trucks travelling to and from the landfill-caused
most neighbors to become aware of the landfill for the first
time.  In response to complaints about L&RR and other hazardous
waste sites in the area, two citizens groups formed — Protect
Our Waters (POW) and Saving the Environment of North Smithfield
(SENS).  These groups were very active in the late 1970s,
coordinating media events, disseminating information about the
sites, and organizing rallies.  The groups repeatedly sought to
close L&RR.  Although the efforts met with little immediate
success, POW was instrumental in the passage of two state laws to
ban hazardous and solid waste facilities from being located over
aquifers.

     In 1978, the North Smithfield Town Council formed a task
force on hazardous waste that included members of POW and SENS.
One of the goals of the task force Was to build a case to
convince the state legislature, the courts, RIDEM, and EPA to
take some type of action at L&RR.  In 1979, when the hazardous
waste portion of the landfill was closed, the task force
disbanded and POW and SENS became less active.  At present,
community members including members of POW remain very interested
in area environmental issues and have expressed concerns about
preventing risks to public health from exposure to hazardous
waste, protecting the Slatersville Reservoir, and managing
community growth and development.

-------
RESPONSIVENESS SUMMARY                                     page 7
Landfill & Resource Recoverv Site
III. SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC COMMENT
     PERIOD AND EPA RESPONSES TO COMMENTS

     This Responsiveness Summary addresses the comments received
by EPA on the Remedial Investigation (RI), Feasibility Study
(FS), and Proposed Plan for the Landfill and Resource Recovery
Site (L&RR Site) in North Smithfield, Rhode Island.  During the
public comment period, EPA received written comments from six
parties and the Rhode Island Department of Environmental
Management (RIDEM).  There were two oral comments given at the
public hearing held on August 10, 1988.  Copies of the hearing
transcript are available at the information repository located in
the Municipal Annex Building in North Smithfield and at the EPA
Records Center, 90 Canal Street, in Boston, Massachusetts.

     In Part 1 of this section, comments received from the
community are summarized and EPA responses are provided.  Part 2
summarizes and provides EPA responses for comments received from
RIDEM.  Part 3 summarizes and provides EPA responses to comments
submitted on behalf of Potentially Responsible Parties (PRPs).
PART 1.   COMMUNITY COMMENTS
A.   CONCERNS REGARDING THE RESPONSIBLE PARTY

     Several commenters (area residents and members of Protect
Our Water) raised specific concerns regarding the past and future
activities of the landfill owner.

1.   Comment;

     Each of the four written comments EPA received from
     community members referred to a newspaper article stating
     that the landfill owner wants to burn the landfill gas and
     create electricity for sale.  Members of Protect Our Water
     expressed specific concern that the gas treatment system
     would be operated for profit by the landfill owners, stating
     that the landfill owners have never evidenced concern for
     public health and welfare.  The commenters stated further
     that any profit gained from selling electricity generated
     from the landfill should be returned to the government or
     used toward the closure of the Site.

     EPA Response;

     The selected remedy utilizes thermal destruction to treat
     the landfill gas.  EPA will choose one of the following
     three thermal destruction technologies during the design
     phase; combustion, flaring or incineration.\  All three burn
     the gas to destroy the hazardous constituents but only one
     has the potential to produce electricity, combustion.  This

-------
RESPONSIVENESS SUMMARY                                     page 8
Ijtndifi.il ft Resource Recovers
     technology may not be a profit making technology due to the
     operation and maintenance costs.  Pilot tests will be
     conducted during the design phase to provide EPA with
     information necessary to identify which of the three
     technologies is protective and cost effective.

     EPA will negotiate with all of the potentially responsible
     parties, including the site owners, to implement the
     remedy.  If the responsible parties agree to implement the
     remedy, they must implement the remedy in accordance with
     the Comprehensive Environmental Response and Liability Act
     (CERCLA) which requires it to be protective of public health
     and the environment.  EPA will monitor the design and
     construction of the remedy to insure that it is protective.
     Furthermore, the selected remedy includes an air monitoring
     program to insure that during operation, the selected remedy
     remains protective.
2.   Comment !
     Protect Our Water stated their concern with the landfill
     owners being the operators and maintainers of a gas
     collection system that is necessary to safeguard air quality
     and asked the following specific questions regarding the
     proposed gas treatment system:

     1.   Which of the three gas collection systems proposed in
          the EPA report is the system of choice for the
          situation as it exists at L&RR?  We ask this noting
          that only combustion, of the three systems discussed,
          makes the gas available for sale and also noting that
          incineration is the most efficient in the destruction
          of contaminants.

     2.   Who will determine if the system is properly operating?

     3.   Who will maintain the system?

     4.   What will happen if the system becomes unprofitable?

     5.   Who will determine when and if the system should be
          discontinued?

     EPA Response;

     As stated in response to comment |2, EPA will select the
     specific gas treatment technology during the design phase,
     after pilot tests are conducted.  A monitoring plan will be
     implemented to insure that the system is protective.  EPA
     and RIDEM will review the monitoring data on a periodic
     basis to insure that the system remains protective.
     If the responsible parties agree to implement the remedy,
     they will be responsible for maintaining the system.  The

-------
RESPONSIVENESS SUMMARY                                     page 9
Landfill & Resource Recovery Site    	
     selected remedy includes a post-closure plan which
     specifies routine inspections and maintenance requirements.

     The system will be operated as long as necessary to reduce
     the risks from exposure to the landfill gas.  EPA will
     decide when the system is no longer needed.  EPA doubts that
     any of the systems will be profitable because of operation
     and maintenance costs.  However, this issue will not
     influence EPA's decision on whether treatment is needed.
B.   GROUNDWATER MONITORING

1.   Comment;

     Protect Our Water and a community resident expressed their
     concern with the great distances between monitoring wells in
     place at the Site.  In particular, the group is concerned
     about protecting the Slatersville Aquifer, which provides
     one third of the town's water supply.  The organization
     recommended that EPA install three additional monitoring
     wells in specific locations.  They stated that the estimated
     $30,000 cost to install the three additional wells is
     relatively -ggmTi in comparison with the $6 million EPA
     proposes to spend to implement the Proposed Plan.

     EPA Response:

     A number of factors must be considered when establishing a
     network of groundwater monitoring wells at a site.
     Presently there are 14 groundwater monitoring wells
   .  installed around the perimeter of the Site.  Nine of these
     wells were installed by the present Site owner.  After
     reviewing hydrologic and geologic information for the Site,
     EPA installed five additional monitoring wells during the
     RI/FS to gather information to characterize contamination at
    . the Site.  In response to this concern, EPA reviewed once
     again all the data collected to date and established a
     revised long-term groundwater monitoring plan which is
     outlined in the Record of Decision (ROD).  This plan
     requires a new cluster of wells.  This cluster will have two
     wells and will be located between monitoring well clusters
     CW-6 and CW-7.  The specific location of this cluster will
     be decided during the design phase.  Given the geologic
     conditions at the Site, this monitoring well network will
     identify a contaminant groundwater plume migrating from the
     site.

-------
RESPONSIVENESS SUMMARY                                    page 10
Landfill & Resource Recovezv Site
C.   MISCELLANEOUS

1.   Commentt

     One resident stated his belief that the contamination'at the
     Site should be removed and neutralized, minimizing the
     threat of spreading contamination in the future.

     EPA Response;

     During the Feasibility Study, EPA developed an alternative
     that would permanently destroy the source of contamination
     at the Site.  This alternative consisted of excavating the
     wastes and treating them in an incinerator.  This
     alternative was not chosen as the selected remedy for the
     following reasons.  First, significant public health and
     environmental risks would be posed by its implementation.
     Excavation of the wastes is likely to release volatile
     organic compounds (VOCs) and particulates such as asbestos
     into the atmosphere creating on-site and off-site risks from
     inhalation.  Second, since the location of the hazardous
     wastes is unknown, EPA assumed that all of the wastes must
     be removed and treated.  This would take approximately 90
     years to implement. Third, incinerator capacity nation wide
     is insufficient for the quantity of wastes available.
     Finally, this alternative would cost nearly 2 billion
     dollars to implement.

2.   Comment:

     One citizen took exception to an EPA report that stated that
     the landfill accepted waste for disposal since .1927.  The
     commenter stated that he is able to produce evidence
     disproving the date in question.

     EPA Response;

     It was stated in the RI/FS Report that wastes had reportedly
     been accepted for disposal at the Site since 1927.  This
     information was based on discussions with past owners and
     other people with historical knowledge of the Site.  EPA
     would welcome any information regarding historical waste
     disposal activities at the Site.

-------
RESPONSIVENESS SUMMARY                                    page 11
Landfill & Resource Recovery Site        	
PART 2.   RIDEM COMMENTS
A.   TECHNICAL CONCERNS REGARDING EPA INVESTIGATIONS AND THE
     PROPOSED PLAN

     Formal comments from the State of Rhode Island were
submitted by the Department of Environmental Management (RIDEM).


1.   Comment:

     RIDEM has questions about the runoff and infiltration
     quantities projected from the modelling of the existing
     cover system at the landfill.  The Department requests a
     more detailed explanation of the modelling procedures,
     capabilities, and results.  RIDEM is interested in how the
     data influences EPA's selection of the remedy.  In addition
     to the RIDEM comment, Wehran Engineering, the consultant for
     L&RR, Inc., also commented on the appropriateness of the
     methods used by EPA to predict the infiltration and runoff
     quantities.  The response to this comment is presented in
     Part 3.A.2.

     EPA Response;

     Two methods were utilized to assess infiltration in the
     landfill and specifically the area without a synthetic
     cover, the Hydrogeologic Evaluation of Landfill Performance
     (HELP) mpdel, Version I, and the Thornthwaite and Mather
     water balance model as republished by Fenn, Hanley and
     DeGeare, in 1977.  Both models are designed to predict
     infiltration based on, among other things, rainfall and
     runoff characteristics and both are controlled by
     assumptions and input parameters.  Its also important to "
     note that both methods give approximations based upon
     impirical data and reasonable assumptions.

     In response to Wehran's comments, EPA reviewed all of the
     methods utilized and the results obtained.  It was
     interesting to note that Wehran Engineering calculated two
     different results using the same model.  In 1983, Wehran
     performed a water balance for the uncovered area of the
     landfill using the method of Thornthwaite as modified by
     Fenn and calculated an infiltration of 19.3 inches/yr.
     Using this same method in their September 1988 comments on
     EPA's RI/FS, Wehran calculated a value of 6.8 inches/yr.
     These differences demonstrate the variation in infiltration
     that can result when different assumptions .are used with the
     method.  Using the HELP Model, EC Jordan, EPA's consultant,
     calculated infiltration as 27.64 inches/yr.  In response to
     Wehran's comment, EC Jordan recalculated infiltration using
     the Thornthwaite method as modified by Fenn with similar
     assumptions as those utilized in the HELP model

-------
RESPONSIVENESS SUMMARY                                    page 12
     calculations.  In this instance, Jordan's calculations
     resulted in an infiltration of 16 inches/yr (See Memo from
     EBASCO dated September 26, 1988 in the Administrative
     Record).

     EPA agrees with the Wehran comment that the HELP model is
     limited in its ability to accurately represent slopes
     greater than 10%.  The HELP model represents a conservative
     approach which has been utilized at many sites with slopes
     steeper than 10%.  EPA further agrees that the Thornthwaite
     method, as modified by Fenn, is a more appropriate method
     for representing the infiltration at the L&RR Site.
     However, the Thornthwaite method, as modified by Fenn,
     results in a range of values for infiltration between 6.8
     in/yr and 19.3 in/yr.  As Wehran points out in their
     comment, the results are strongly influenced by the
     assumptions and in particular the assumed runoff
     coefficient.  Without site-specific information and
     information concerning the input assumptions, made by Wehran,
     EPA cannot evaluate which of the approximations calculated
     is a closer representation of the actual field conditions at
     the L&RR Site.

     Based on a review of EC Jordan's assumptions and results,
     EPA believes that the actual infiltration in the uncovered
     area could realistically be in the range between 6.8 in/yr
     and 19.3 in/yr which represents 185,000 gallons/acre/yr and
     524,000 gallons/acre/yr, respectively.  The maximum
     infiltration calculated for the rest of the landfill, which
     has a synthetic cover as part of the cover, system, was
     estimated to be 7,690 gal/acre/yr.  Given the long-term
     uncertainties associated with land disposal and the lack of
     information regarding the location of the wastes, the amount
     and types of hazardous wastes disposed and the hydrologic
     flow in the landfill, EPA finds this range of infiltration
     in the uncovered area unacceptable.  In order to meet the
     objective of the objectives of CERCLA, to protect human
     health and the environment and to meet applicable relevant
     and appropriate requirements (ARARs), the synthetic
     impermeable membrane is necessary on the uncovered area of
     the landfill.
2.   Comment
     RIDEM requests that EPA consider alternative groundwater
     monitoring programs that would provide adequate monitoring
     but include flexibility in the frequency and/or parameters
     chosen, dependent on the trends in analytical data
     collected.
                                                \

     EPA Response;

     EPA established a groundwater monitoring program in the ROD
     that was different from the ones discussed in the RI/FS

-------
RESPONSIVENESS SUMMARY
Landfill & Resource Recovery Site
                                           page 13
     Report.  The monitoring plan is outlined below and nay be
     revised based on trends in analytical data.
     Wells:
MW-101
MW-102 A,B
MW-103 A,B
MW-104 A,B**
CW-5 A,B,C
CW-6 A,B,C
CW-7 A,C*
(15 wells)
            *  EPA does not think that CW-7B is needed.
           **  MW-104 is a new well cluster located between
               CW-6 and CW-7.
     Parameters!
        Quarterly:  VOCs
               Indicators
               Chloride
               pH
               Temperature
               Specific Conduct.
                Metals
                Arsenic
                Iron
                Lead
                Manganese
                Cadmium
         Annually: Barium, chromium, fluoride,  mercury, nitrate,
                   selenium and silver (from the 1983 Court
               Order)

3.   Comment;

     RIDEM requests a more detailed cost analysis breakdown of
     the associated operation and maintenance costs that are
     anticipated.

     EPA Response:

     A detailed cost breakdown for each alternative is found in
     Appendix BB in the RI/FS Report.   Its important to note  .
     that the cost analysis in the FS  is primarily conducted to
     provide EPA with an estimated comparative cost for each
     alternative.  These estimates are made with a number of
     assumptions and the actual costs  may vary between -30 and
     +50 percent.  The detailed cost information is developed
     during the design phase.

     Its also important to note that as discussed in response to
     comment #2, the groundwater monitoring plan established in
     the ROD is different than the one outlined in the FS.  EPA
     estimates the costs for this plan will be as follows:

-------
RESPONSIVENESS SUMMARY
     page 14
     VOCs         $225/smpl x 15 smpl/qtr x 4 qtr/yr
     Metals        $80/smpl x 15 x 4
     Indicators    $40/smpl x 15 x 4
     C.O. Metals  $160/smpl x 15 x 1

     Total Analytical Costs:

     2 people x 3 days x 8 hrs x $20/hr x 4 qtr/yr

     Total Sampling Costs:

     Comment:
  $13,500/yr
-  $4,800/yr
-  $2,400/yr
-  $2,400/yr

- $23,100/yr

»  S3.84Q/vr

- $26,940/yr
     RIDEM has questions about the results of the air monitoring
     at the landfill and the risk assessment developed based on
     this data.  RIDEM believes that more accurate analytical
     results are needed in order to develop an appropriate risk -
     analysis.

     EPA Response:

     EPA believes that the results are appropriate and sufficient
     for the purpose of selecting a remedy for the Site.  The
     difficulties encountered at the Site such as the high
     moisture content and high pollutant concentrations of the
     gas made the use of conventional sampling techniques such as
     sorbent traps tenuous.  The results were based on techniques
     designed specifically for L&RR after standard sampling
     methodology failed.

     EPA1s conservative position is that although there may be
     questions regarding the validity of the quantitative data,
     qualitatively, the risk assessment justifies the necessity
     for gas treatment.

     Comment:

     RIDEM stated that the Department and the owners of L&RR
     entered into a Consent Agreement in July 1983 (the 1983
     Court Order) which addressed closure measures for the
     landfill.  Many of the components of EPA's Proposed Plan are
     similar to the requirements outlined in the existing Consent
     Order and Agreement.  The restoration of wetlands and the
     addition of a synthetic cover on the northeast portion of
     the landfill have not been included as part of the closure
     plans submitted to date.  The Department agrees that
     compliance with all applicable wetlands requirements must be
     addressed, in addition to all of the other closure measures
     required under the 1983 Court Order.  The Department also
     agrees that installing the additional cover, on the northeast
     side slopes would further reduce infiltration of liquids
     into the landfill; however, given the concerns identified in
     the Department's first comment (A-l, above),  the Department
     requests that EPA provide further justification for the

-------
RESPONSIVENESS SUMMARY                                    page 15
Landfill & Resource Recovery site	
     proposed cap.

     EPA's Response;

     There are a number of reasons why EPA is proposing to
     upgrade the present landfill closure and, more specifically,
     install a synthetic cover and stabilize the slopes on the
     northeast portion of the Site.  EPA's primary reasons for
     installing the synthetic cover is to protect public health
     and the environment and attain ARARs.  The installation of
     the synthetic cover will protect the groundwater and insure
     compliance with the provisions of the RCRA Subtitle C
     regualtions (40 CFR 264).

     EPA considered the following facts when selecting the remedy
     for the Site.  First, the landfill is situated over the
     Slatersville Aquifer which is designated as a potential  .
     future drinking water source.  Second, EPA has no definitive
     .information regarding the location, amount and types of
     hazardous wastes within the landfill. ' Third, EPA also has
     no information regarding the hydrologic flow patterns within
     the landfill.  There is a potential that the flow could be
     channelized to areas containing the hazardous wastes.
     Fourth, although presently there is no indication of an
     organic contaminant plume migrating from the Site, there is
     a potential that one could emerge in the future due to
     transport mechanisms, such as gravity, that occur regardless
     of the amount of infiltration.  In light of the fact that we
     know hazardous wastes were disposed of in the Site, there
     are three possible explanations for the groundwater
     monitoring results seen to date.  First, the hazardous
     contaminants have not yet entered the groundwater.  Second,
     the groundwater containing the hazardous contaminants has
     not yet reached the boundary of the Site.  Third, the
     existing landfill conditions, such as the natural hydrologic
     and geologic conditions within the landfill, the quantity of
     wastes disposed and the existing cover, could be preventing
     the generation or detection of a groundwater plume at this
     time.  If the first two explanations are correct, we can
     expect to see an organic contaminant plume in the future.
     In light of all of these knowns and unknowns,  EPA believes
     that it is necessary to protect the groundwater and to
     minimize infiltration to be protective of public health and
     the environment.

     The statutory requirements established in CERCLA mandate
     that EPA select a remedy that meets ARARs.  In order to
     comply with the RCRA Subtitle C regulations (40 CFR 264),
     the landfill cover must minimize infiltration as discussed
     in response to comment 1.  A synthetic cover over the entire
     landfills/ill minimize infiltration.

-------
RESPONSIVENESS SUMMARY                                    page 16
Landfill & Resource Recoverv Site
B.   ALTERNATIVE PREFERENCE

1*   Commentt

     RIDEM recommends that EPA consider the implementation of the
     closure measures outlined in the 1983 Court Order, in
     addition to wetland restoration, as an effective and
     appropriate remedy for the L&RR Site.

     EPA Response;

     The existing closure conducted to date under the 1983 Court
     Order between RIDEM and L&RR, Inc., was evaluated during the
     RI/FS.  The existing closure conducted to date does not meet
     the requirements of CERCLA.  More specifically, the existing
     cover does not protect the groundwater.  In addition, the
     existing surface water drainage system and vegetation
     establishment does not minimize erosion.  Erosion from the
     landfill has severely impacted and continues to deposit soil
     in the wetlands.  Before the wetlands are remediated, the
     landfill erosion must be minimized; otherwise, continuous
     wetland remediation will be needed.  The 1983 Court Order
     requires a methane recovery system.  This system has yet to
     be designed or constructed.  This system must be designed
     and constructed in accordance with EPA's Record of Decision
     (ROD) to meet the requirements of CERCLA.  EPA reviewed the
     existing groundwater monitoring plan.  In light of the
     hydrologic and geologic data collected to date and the fact
     that there is a potential for a groundwater plume to emerge
     in the future, a more aggressive groundwater monitoring plan
     is needed to meet the requirements of CERCLA.  Finally, the
     post-closure monitoring plan must take into consideration
     EPA's selected remedy and the requirements in EPA's ROD to
     meet the requirements of CERCLA.

-------
RESPONSIVENESS SUMMARY                                    page 17
Landfill & Resource Recovery Site	
PART 3.   POTENTI&T.T.Y PRSPQNSIBT.F PAPTIES COMMENTS
A.   TECHNICAL CONCERNS

     Wehran Engineers, Inc. submitted extensive comments on
behalf of the owner of L&RR, Inc.  These comments and EPA
responses to these comments are summarized, by subject area,
below.

1.   Landfill Gas Emissions and Risk Assessment

a.   Comment;

     Wehran questions the validity of utilizing so-called
     "future conditions" (uncovered vents) as the basis for the
     air exposure and risk assessment.  Wehran theorizes that -
     the landfill gases would never be uncontrollably released
     into the environment because the 1983 Court Order requires a
     methane recovery system.  Therefore, the "future conditions"
     do not represent any anticipated actual future conditions.
     The air risk assessment should be based upon current
     conditions using fugitive emissions data for landfill gases
     which may.be emanating from the Site.

     EPA Response;

     The risk assessment was based upon emissions from 5 sampled
     air vents, of the 18 total vents found at the landfill.  The
     best approach to estimate fugitive emissions was thought to
     be use of actual emissions from some portion of the total
     vents, rather than introducing additional uncertainties by
     modeling estimated fugitive emissions.  The five vents
     sampled, which are less than 1/3 of total vents, was
     considered to present an acceptable estimate of future
     fugitive emissions due to fissures in the uncovered portion
     of the landfill.

     Although the 1983 Court Order requires a methane recovery
     and removal system, one has yet to be constructed at the
     Site.  As concluded in the RI/FS, a large volume of gas  .
     (775 cubic feet per minute (CFM)) is being generated within
     the landfill.  To protect .the integrity of the synthetic
     cover, the gases generated in the landfill must eventually
     be released.  While it may be true that the vent gases may
     never be uncontrollably released into the environment, the
     landfill gases needed to be characterized not only for the
     purposes of risk assessment but also for design, and
     construction.  Ultimately, when the treatment system is
     designed and constructed, it must protect human health and
     the environment.  Information regarding the degree of hazard
     associated with the untreated gas is necessary to design a
     system that is protective.  The RI/FS Report and EPA's
     Proposed Plan clearly states that the vents are currently

-------
RESPONSIVENESS SUMMARY                                    pag* 18
     closed.  With the information obtained during the RI/FS, EPA
     has concluded that these vents should remain closed until a
     treatment system is constructed.
b.   Comment T
     The vent velocity measurement technique does hot utilize
     standard methodology or account for any variation across the
     diameter of the pipe.  The vane anemometer method does not
     provide an accurate flow measurement as per EPA Method 2 and
     could contain large errors.  A more accurate velocity
     measurement could have been obtained by attaching a larger
     diameter duct to the vent pipe with access ports to permit
     traverses and the utilization of a pilot tube and micro
     manometer system.  In addition, the vane anemometer utilized
     is easily affected by ambient wind conditions and may
     include a bias.  No ambient wind data during sampling is .
     provided in the report.  Ultimately, this error results in a
     reduced risk characterization.

     EPA Response;

     The vane anemometer employed a shield around the blades to
     minimize ambient wind influences.  The data .gathered with
     the anemometer were used to assess the character of the vent
     emissions and were not intended to provide a detailed
     analysis of such emissions.  The alternative method
     recommended by Wehran (EPA Method 2) would have proven
     highly inaccurate without hydrogen, oxygen and moisture
     preanalyses of each vent to determine gas density.
c.   Comment;
     On page 7-12 of the RI/FS Report, reference is made to the
     six inch pipe diameter stamped on the sides of the vent  •
     pipe.  Is this ID or OD, and why wasn't an accurate measure
     taken to confirm the pipe size?

     EPA Response;

     The pipe size was 6 inches, inner diameter.  The stamping
     was discovered after the initial measurement and only
     served to confirm the measurement.
d.   Comment;
     The calculated percent changes in temperature between
     uncapped and vented scenarios presented in Table 7-3 of the
     RI/FS Report are incorrect; for example, the reported Vent 2
     result is +46.3*.  Referring back to Table 7-2, the
     following calculation results in (1.8 - 7.5)/ 7.5 - -76%.
     Many of the other reported values are incorrect as well.

-------
RESPONSIVENESS SUMMARY                                    page 19
Landfill & Resource Recovery Site	
     EPA Response;

     The calculated percent change in temperatures presented in
     Table 7-3 were calculated using temperature in degrees
     Celsius.  For example, in vent 10, a +100% change in
     temperature was noted for a corresponding temperature
     increase of 68°F to 104°F.  This percent change was
     actually calculated using Celsius values of 20°C and 40°C.

e.   Comment:

     A footnote on Table 7-6 of the RI/FS Report indicates that
     vent pipe velocity and temperature measurements were not
     collected during the VOC sampling events.  With the noted
     variability of the vent flow rates, this is a significant
     loss of data.  No comparison of physical characteristics of
     the vent emissions can be made between the sampling events
     and the flow measurement events.  With this missing data,
     actual emission rates at the time of sampling could also
     have been determined.

     EPA Response;

     The footnote referenced in the comment was incorrectly
     written. The footnote should have indicated that velocity
     data was not available for the 48 hour period of venting.
     Section 7.4.5 of the RI/FS Report references this loss of
     data.  Exhaust parameter data was available for the
     remaining VOC sampling events.

f.   Comment;

     Review of Table 7-7 in the RI/FS Report indicates that the
     duplicate sample of vent 18 did not replicate the
     identification of three compounds:  1,1,1 - trichloroethane,
     trichloroethene, and bromoform.  The discussion contained in
     the RI/FS Report does not accurately represent that 3 of the
     11 compounds were not replicated.  Potential mis-
     identification or field sampling error is indicated by these
     results.  Furthermore, if detection limit values are '
     utilized for these non detected results, high relative
     percent differences are indicated.  This error results in
     reduced risk characterization.

     EPA Response:

     It is noted that the duplicate samples from vent 18 did not
     replicate the results for the three compounds noted and
     field sampling error could have effected these results.
     However, 1,1,1-trichloroethane was detected in 18 of 21
     samples, trichloroethene was detected in 20 of 21 samples
     and bromoform was detected in 13 of the 21 samples.  All of
     the compounds were detected at significant levels.  Of the
     three compounds, only trichloroethene contributed to the

-------
RESPONSIVENESS SUMMARY                                    page 20
     risk.  Therefore, this fact is not expected to have
     influenced the risk.

     Commentt

     On page 7-33 of the RI/FS Report, the worst case scenario
     for the odor impact is based on the exit parameters from the
     immediately uncapped scenario.  However, no data exists to
     determine a realistic estimate of the potential duration of
     this scenario.  Velocity or temperature data is presented
     for the following periods of venting: 0, 12, 24, and 48
     hours.  On page 7-36, a statement is made that velocity did
     not stabilize until the 12th hour of venting.  Stabilization
     could have occurred at some time period less than 12 hours.
     If the vent flows had been more fully investigated, it would
     have been possible to determine when flows stabilized and
     subsequently to assess more realistically the duration of
     this scenario.

     EPA Response!

     It is agreed that stabilization could have occurred before
     12 hours of venting and the report should have indicated
     this.  Since it was not known when stabilization would
     occur, the intervals of 0, 12, 24 and 48 hours were selected
     to investigation a range of possibilities.  To be
     conservative and account for the uncertainties of computer
     modeling and risk assessment, the worst case scenario was
     based on the results from the immediate uncapped scenario.
     It is also important to note that the vents are presently
     closed due to down wind odor problems.
h.   Comment:
     As discussed on page 7-43 of the RI/FS Report, Wehran
     questioned the potential, impact on the modeling results of
     the terrain reductions in the receptor elevation input.

     EPA Response:

     Of the 53 terrain points reduced, 36 were associated with
     the 100 meter on-site ring with maximum reductions of 13
     feet.  This ring was only of concern for on-site exposure.
     The reductions made for off-site receptors numbered 17 and
     occurred from 600 meters and beyond.  The low plume exit
     characteristics resulted in the worst-case impacts within
     600 meters.  Furthermore, the 17 off-site receptors with
     reduced terrain were located east-southeast and south-
     southwest of the Site, areas that were away from the maximum
     impact locations.  The terrain reductions had little impacts
     on predicted concentrations.'

-------
RESPONSIVENESS SUMMARY                                    page 21
Landfill & Resource Recovery Site       	
i.   Comment t

     The VOC averaging scheme discussed on page 7-43 of the RI/FS
     Report introduces a significant increase in the average VOC
     concentrations utilized for many of the seventeen compounds.
     The results reported as non detected (ND) were discarded
     from the averaging as if the only valid results are those
     reported above detection limits.  For those values reported
     as ND, the method detection limit value could be utilized
     for calculating the average.  This bias impacts the air
     dispersion modeling results as well as the risk
     characterization results, through the over estimation of VOC
     concentrations in vent pipe emissions.

     EPA Response:

     Owing to the inherent limitations of any scientific study,
     any bias towards conservatism is desirable, especially in
     regards to a public health assessment.

j.   Comment t

     The description of exposure -scenarios for inhalation of vent
     pipe emissions are all based on the uncontrolled venting of
     the five worst case vents.  The qualification addressing
     "should more vents be uncovered and have emissions similar
     to these tested" presents a hypothetical situation not
     likely to occur considering the Site conditions and history.
     First of all, the Report describes the five worst case vents
     as orders of magnitude greater (peak areas) than the
     remaining vents on page 7-25.  Therefore, similar emissions
     are not likely from other vents.  Second, there are no
     current or future plans which incorporate uncontrolled
     venting of the landfill gases.  Although it is used as a .
     worst case scenario for modeling and risk characterization,
     the discussion of risk should include a statement that the
     vents are not now or in the future proposed to be allowed to
     vent to the atmosphere.

     EPA Response:

     The first point made by Wehran "similar emissions are not
     likely from other vents" cannot be substantiated.
     Currently, the emissions from 13 of the 18 vents are less
     significant than the emissions from the 5 worst case vents.
     This point does not mean that the emissions from the 13
     vents may not pose a health hazard.  The sample technique
     utilized was specifically developed to assess high
     concentrations. Other techniques could be utilized to detect
     contaminants in the other 13 vents.  Furthermore, while the
     13 vents have lower emissions at the present time, there is
     nothing to indicate that the landfill will continue to emit
     at its present rate.

-------
RESPONSIVENESS SUMMARY                                    page 22
     AS stated in response to comment i.a. in this section, the
     RI/FS Report and EPA's Proposed Plan clearly indicates that
     the vents are presently closed.  Given the potential risk
     to public health from the vent emissions, EPA will insist
     that they remain closed until a gas treatment system is
     constructed that meets the objectives of EPA's Record of
     Decision (ROD).
k.   Comment t
     The calculation of adult cancer risk is based on exposure
     over a 70 year lifetime.  The landfill gas generation rates
     and concentrations will not only vary greatly, but the
     generation lifetime for the landfill is much less that the
     70 year exposure period.  At a minimum, the flows will be
     greatly reduced over time.  The risk calculation does not
     account for the major reduction in landfill gas emissions,
     which will naturally occur over the lifetime of the
     landfill.

     EPA Response:

     While it is agreed that gas emissions will decrease over the
     life span of a landfill; there is no information to
     indicate with any degree of certainty what reductions will
     occur over what time period.  Therefore, emissions were
     assumed to continue over a full human lifetime.  It should
     be noted however, that for the most probable case, it was
     assumed that exposure would only occur 75% of the time.
1.   Comment;
     The risk assessment states that there are no residences at
     the off-site point of maximum impact.  If not, why was this
     location used in the risk assessment?  Is this an expected
     future condition?  If so, this should be stated in the risk
     assessment.

     EPA Response:

     Risks were calculated assuming exposure at the off-site
     point of maximum impact to present a worst case scenario.
     In addition, risks were calculated assuming exposure at 3
     residential locations to present a most probable case.
m.   Comment;
     The predicted concentrations at the on-site maximum impact
     point remain constant for at least the period of exposure (9
     years).  There is no basis for this assumption provided in
     the RI/FS Report.  It is probable that if the landfill
     vents were opened, emissions could decrease with time.

-------
RESPONSIVENESS SUMMARY                                    page 23
Landfill & Resource Recovery Site	
     EPA Response;

     As stated previously, there are no quantitative data on the
     decrease in gas generation rates or concentrations over the
     life span of a landfill.  Therefore, it was assumed that
     fugitive emissions would remain constant.  It should be
     noted that the concentrations at the on-site maximum impact
     point is an annual average value and that although higher
     concentrations would occur due to metrological conditions,
     the annual average is the most realistic value.

n.   Comment;

     The realistic worst case analysis is based on the assumption
     that children will visit the on-site maximum impact point
     twice a month for nine years and remain at that location
     for four hours each time.  There is no evidence to support
     any of these assumptions.  Furthermore, if a fence with
     barbed wire is installed around the Site, there is no
     probability of this circumstance happening at any time in
     the future.

     EPA Response;

     There is physical evidence that the Site has been accessed
     by individuals.  This includes dirt bike tracks and trash.
     The ventilation rate is consistent with a moderate activity
     level, which is considered appropriate for children at play.
     These assumptions apply to the Site as it exists now, which
     are considered baseline conditions that would not require
     long-term management and oversight, including site security
     such as a fence.

o.   Comment;

     Source terms for air quality modeling are suspect and yet
     greatly impact the health risk assessment.  Specifically,
     selection of source emission properties based on
     measurements taken before the source has reached equilibrium
     may not provide an accurate estimate.  Second, failure of
     the velometer prevents proposing the assumption that the
     emissions have stabilized.  Finally, vent velocities may not
     be accurately assessed without barometric pressures
     measurements.

     EPA Response;

     Vent gas exit velocities averaged 2.5 miles per, hour after
     12 hours of venting and continued at this rate at 24 hour
     point.  The value represented a drop from the immediately
     uncapped value of 5.1 mph.  Since the drop continued after
     12 hours, flow equilibrium was reached within the period of
     sampling.

-------
RESPONSIVENESS SUMMARY                                    page 24
       l I Resource Recoverv Site
     Although it has been suggested that atmospheric (barometric)
     pressure affects landfill gas emissions,  it is not expected
     to be significant in this case.  For a landfill the size of
     L&RR, the primary source of emissions is the methane .
     generated, which is a function of material decay and
     decomposition.  Atmospheric pressure will not direct the
     rate of decay nor will atmospheric pressure significantly
     alter an emission volume of 775 cubic feet per minute.

     It is doubtful that the source terms will remain constant
     for 70 years, nor was it ever stated in the RI/FS Report.
     The uncertainty associated with this change is the reason
     why worst case assumptions were used in completing the risk
     assessment.

     Comment t

     There is no validation of the quantitative emissions
     concentrations derived from field GC studies.  A large part
     of the risk assessment from the air exposure is due to two
     compounds: 1,2, dichloroethane and carbon tetrachloride.
     6C/MS samples failed to confirm the presence of these
     compounds.

     EPA Response:

     Observed differences between the field GC sampling results
     and the laboratory analyzed tenax and charcoal tubes may be
     due to a variety of factors.  Quantification of the charcoal
     and tenax tubes was hampered by breakthrough and probable
     loss of certain hazardous substance list (HSL) compounds of
     concern due to displacement from the tubes by high
     concentrations of other HSL and/or non-HSL organics.
     Initial CLP laboratory analyses confirmed the existence of
     high organic loadings on certain tubes.  In addition, during
     sorbent tube sample collection, water vapor condensation was
     a recurring problem.  The presence of water can adversely
     affect sorbent tube performance.  The field gas analyzed
     samples were collected in gas bulbs which were not subject
     to breakthrough or desorption losses as are sorbent tubes.

     Sample analyses using the field GC based all comparisons of
     peaks to volatile standards containing the targeted
     compounds, with a standard analyzed at the start of the day
     and every eight hours until the analysis day was complete.
     Retention times (RTS) were matched based upon the observed
     drift of the RTS in the samples and by generating relative
     retention times (RRTS) to a late eluting compound (toluene).
     Therefore, the identifications are considered valid.

     As discussed in the RI, the sorbent tube data confirm the
     field GC results indicating the presence of a wide variety
     of chlorinated and non-chlorinated organic compounds in the
     vent emissions.  Both the charcoal and tenax tube data for

-------
RESPONSIVENESS SUMMARY                                    page 25
Landfill & Resource Recovery site          	
     samples from several vent locations indicate the presence of
     many HSL organics in both the front and back tube portions
     indicating the occurrence of breakthrough.

     With respect to field GC data, it should be noted that
     carbon tetrachloride was detected in four different samples
     from each of five different vent locations and 1,2-
     dichloroethane was detected in multiple samples from two
     different vent locations.

     From the health perspective, the realistic worst case
     estimate .of health risks (1.1 x 10~3)  to children due to
     the inhalation of air contamination from vents exceeded the
     EPA target range for risk of 1 x 10~4  by approximately an
     order of magnitude.  This total risk was due to significant
     contributions from several air contaminants including
     chloroform and tetrachloroethene/ 1,1,2,2-tetrachloroethane,
     in addition to 1,2-dichlroethane and carbon tetrachloride.
     The calculated risk due to any one of  the constituents
     considered individually approached or  exceeded the EPA
     target level of 1 x 10~4.

     In addition, for this scenario the total calculated risks
     from several other structurally similar chlorinated organics
     (methylene chloride, 1,1-dichloroethene, and
     trichloroethene) and benzene , all of  which were detected,
     were within a factor of three of the 10~4 upper bound target
     risk.

     In summary, the air sampling results indicate the presence
     of a wide variety of organic constituents in the vent
     emissions.

     Comment;

     The screening of gas treatment technologies in the FS was
     not conducted correctly.  To determine the reduction in
     health risks achieved by each gas treatment technology,  the
     ambient concentrations produced by the five vent sources was
     reduced by the destruction and removal efficiencies of each
     technology.  After treatment, there will be one source,  the
     stack.  Ambient concentrations from one source will be
     significantly less.

     EPA Response;

     It was acknowledged in the RI/FS Report that the selected
     technology will change source emission parameters.
     However, the intent of the investigation was to-characterize
     the source contaminant term and the exhaust, parameters.
     Although the exhaust parameters will change, the overall
     contaminant feed rate and quantity will not differ because
     of the selected technology.  Knowledge of these terms will
     allow a proper control technique, to be sized and
     implemented.

-------
RESPONSIVENESS SUMMARY                                    page 26
Landfill £ Resource Recoverv Site
r.   Comment;

     Some design efficiencies and cost estimates have not been
     adequately assessed, particularly in regards to the gas
     treatment technologies.

     EPA Response;

     The cost analysis in the FS is primarily conducted to
     provide EPA with an estimated comparative cost for each
     alternative.  These estimates are made with a number of
     assumptions and the actual costs may vary between -30 and
     +50 percent.  The detailed cost information is developed
     during the design phase.

2.   Landfill Performance Model

a.   Comment t

     The amount of leachate generated from the uncapped area of
     the Site was determined by use of the HELP model.  The
     results of this hydrologic modeling are presented in Table
     9-1 and 9-2 of the RI/FS Report.  Based on a leachate
     generation rate of 59% of the total incident precipitation
     in uncapped areas, as compared with 0.7% for capped areas,
     capping of this area was determined by the RI/FS as'
     beneficial.  However, upon inspection of Tables 9-1 and 9-2,
     it is apparent that the modeling results are significantly
     in error.  Wehran Engineering has calculated the water
     balance for the L&RR landfill using a method developed by
     C.W. Thomthwaite, as applied to solid waste disposal sites
     by D.G. Fenn, et.al.  The results of the water balance for
     the uncapped landfill areas show a percolation rate of 6.8
     inches per year.  This rate is 15% of the average annual
     46.2 inches of incident precipitation, rather than the 59%
     as calculated by the HELP model.  Therefore, the RI/FS
     assumption is approximately 400% off.

     EPA Response:

     Both of the methods utilized, the HELP model and the
     Thomthwaite method as modified by Fenn, use analytical
     methods to evaluate infiltration.  However, both are
     controlled by assumptions and input parameters and both
     result in approximations.  Wehran did not submit their input
     assumptions with their comment or at the request of EPA.
     Therefore, EPA could not evaluate the validity of Wehran's
     results.  In response to this comment, EC Jordan utilized
     the Thomthwaite water balance method as modified by Fenn
     with a set of input assumptions which were similar to the
     ones utilized for the HELP model and acceptable to EPA.
     This approach resulted in an infiltration of 16 inches/yr
     (See Memo in Administrative Record from EBASCO dated
     September 26, 1988).

-------
RESPONSIVENESS SUMMARY                                    page 27
Landfill & Resource Recovery Site       	
     In 1983, Wehran performed a water balance for the uncovered
     area of the landfill using the method of Thornthwaite as
     modified by Fenn and calculated an infiltration of 19.3
     in/yr.  Using this same method in their comments on EPA's
     RI/FS, Wehran calculated 6.8 in/yr.  These results
     demonstrate the variation that can occurr in approximating
     infiltration with different input parameters and
     assumptions.

     Using the HELP Model in the RI/FS, EC Jordan calculated
     infiltration as 27.64 in/yr.  The HELP model represents the
     most conservative approach to calculating infiltration,
     particularly on the uncovered area.

     Based on a review of EC Jordan's assumptions and results,
     EPA finds that the infiltration could realistically be in
     the range between 6.8 in/yr and 19.3 in/yr or rather 185,000
     gallons/acre/yr and 524,000 gallons/acre/yr, respectively.
     The maximum infiltration calculated for the rest of the
     landfill, which has a synthetic cover as part of the cover
     system, was estimated to be 7,690 gal/acre/yr.  Given the
     uncertainties associated with landfilling of wastes and the
     lack of information regarding the location of the wastes,
     the type and amount of wastes disposed and the hydrologic
     flow in the landfill, EPA finds this range of infiltration
     in the uncovered area unacceptable.  To meet the objectives
     of CERCLA, to protect human health and the environment and
     meet ARARs, a synthetic cover is needed in this uncovered
     area.

b.   Comment;

     The specific version of the HELP model used was not
     documented.  However, in all versions Wehran has reviewed,
     the model is not meant for landfill slopes greater than 10%
     In the RI/FS Report, the model was used on slopes of 33% and
     50%.  One effect of using these slope factors in the model
     is an inability to accurately predict average runoff
     conditions.  It is widely recognized in hydrologic
     calculations that when the slope of the land is steepened,
     the fraction of rainfall which becomes runoff increases.  In
     Table 9-2, for existing conditions, the percentage of runoff
     at a 3% slope was calculated by the model at 21.37% of the
     total annual precipitation.  At a 33% slope, rather than the
     runoff fraction increasing, the fraction decreased to 0.62%
     of the total annual precipitation.  The soil structure data
     was identical for both slopes, as shown in Table 9-1.  When
     no cap barrier was included in the model design at 50%
     slopes, the rainfall fraction, which was previously removed
     from the model system by the barrier drainage layer at 33%,
     was now.percolated vertically into the landfill.  In fact, a
     substantial amount, of this percolation (and the barrier
     layer drainage at 33%)  should have been calculated as
     runoff.

-------
RESPONSIVENESS SUMMARY                                    page 28
     EPA Response;

     EPA agrees that the HELP model is limited in its ability to
     accurately represent slopes greater than 10% and it was
     utilized as a conservative approach to the Site.  The*
     Thornthwaite method as modified by Fenn is probably a more
     appropriate method for representing the infiltration at the
     L&RR Site.  However, the Thornthwaite method as modified by
     Fenn is also strongly influenced by the assumed runoff
     coefficient.  Therefore, the estimates can be very
     subjective since the user projects their "best" estimate as
     to what the percent precipitation is actually running off.
     EPA finds that the infiltration in the uncovered area could
     realistically be in the range between 6.8 and 19.3 in/yr.
     Given the uncertainties associated with the Site as
     discussed above, EPA finds this range of infiltration
     unacceptable.  EPA believes that in order to meet the
     objectives of CERCLA, to protect human health and the
     environment and meet ARARs, a synthetic cover is needed in
     this uncovered area.
3.   Applicable or Relevant and Appropriate Requirements (ARARs)

a.   Comment;

     Given the fact that the HELP model results contained an
     error regarding infiltration calculations and that runoff
     rates in the non-capped area were not adequately considered,
     the conclusion that the final cover does not achieve
     applicable or relevant and appropriate requirements (ARARs)
     is not adequately justified within the RI/FS Report.

     EPA Response;

     As discussed in previous responses, EPA believes that the
     infiltration in the uncovered area most probably falls
     between the range of 6.8 in/yr to 19.3 in/yr.  However,
     without site-specific tests, the infiltration could not be
     exactly determined.  In light of the uncertainties
     associated with landfilling wastes and the lack of
     information regarding the location of the hazardous wastes,
     the types and quantities of wastes, and the hydrologic flow
     in the landfill, EPA finds this range of infiltration
     unacceptable for meeting the ARARs and in particular the
     requirements of RCRA Subtitle C regulations which require
     the landfill cover to minimize infiltration and migration of
     liquids through the landfill.

b.   Comment;

     On page 2-7, the FS Report states that "although not
     directly applicable" and "generally RCRA regulations have
     jurisdiction at hazardous waste facilities that accepted

-------
RESPONSIVENESS SUMMARY                                    page 29
Landfill 6 Resource Recovery Site	__^_	
     RCRA-listed wastes after November 19, 1980; L&RR ceased
     accepting hazardous waste in September 1979".  However, EPA
     proceeded to evaluate these RCRA regulations as if they were
     relevant and appropriate requirements and then recommended
     implementation of remedial alternatives on the basis of
     these regulations that are "not directly applicable".  The
     basis for landfill ARARs at this Site should be the 1983
     Court Order executed between L&RR and RIDEM.

     EPA Response:

     Section 121 of CERCLA requires EPA's selected remedy to
     attain applicable or relevant and appropriate requirements.
     For the L&RR Site, RCRA Subtitle C is not applicable
     because the Site accepted hazardous waste prior to November
     19, 1980.  However, the RCRA Subtitle C regulations are
     relevant and appropriate because the Site contains wastes
     that are similar or identical to RCRA hazardous wastes and
     hazardous constituents and the CERCLA action involves long-
     term landfilling disposal.  Furthermore, these regulations
     address problems or situations sufficiently similar to those
     encountered at the L&RR Site and their use is well suited to
     the Site.  Relevant and appropriate requirements must be
     complied with to the same degree as if it were applicable.
     Under the terms of Section 121, the 1983 Court Order is not
     a requirement of general applicability which would govern a
     CERCLA remedy.

c.   Comment;

     Wehran asked whether current air concentrations meet the
     ARARs.  Wehran stated that the Air Toxic regulations are not
     clearly presented.  Wehran asked whether these are emission
     standards as referred to in Table 11-9 or ambient levels as
     referred to on page 11-17.  In either case, why aren't they
     provided in Table 11-16, and how do the current landfill
     conditions compare to them?-  There is some indication of a
     standard/guideline on Table 11-2, but it appears this refers
     to the Risk Reference Dose (RfD).

     EPA Response;

     The Rhode Island Air Pollution Control Regulation No. 22,
     "Air Toxics" present acceptable ambient levels.  However,
     minimum quantities of emissions, above which a generator
     must report, are also stated.  The Air Toxics regulations
     are presented and discussed in Appendix Y of the RI/FS
     Report.  In addition, a discussion is presented in a
     Technical Memorandum from EC Jordan dated July 15, 1988 and
     included in the Administrative Record.  The; existing
     landfill vent emissions do not presently meet these
     regulations.  Since fugitive emissions were not
     quantitatively characterized, it could not be determined if
     the fugitive emissions meet these regulations.

-------
RESPONSIVENESS SUMMARY                                    p«g« 30
4.   EPA1s Proposed Plan

a.   Commenti

     Steep side slopes, up to 50%, can be readily stabilized with
     proper drainage controls and suitable vegetative cover.  •
     Should a particular area show to be more susceptible to
     erosion, the topsoil can be strengthened with a synthetic
     mesh material.  The key to proper vegetation establishment
     is prompt re-dressing of any areas showing signs of erosion
     and continual maintenance until a sturdy rootmat has been
     established.  Wehran feels that such an approach would
     alleviate the need for any flattening of the existing slope.

     EPA Response:

     Based on observations made during the RI, the existing
     vegetative cover is considered to be in "poor" condition on
     the steep side slope areas.  The existing root mat is thin
     and plant density is low.  Sandy, well-drained soils such as
     those of the existing topsoil typically have difficulty in
     establishing the good to excellent vegetative cover
     necessary to stabilize those types of soils on steep grades.
     Excessive soil loss, which has historically been a problem
     at the Site, dan be temporarily lessened with synthetic mesh
     materials, however, long-term minimization of soil erosion
     without continued maintenance depends on vegetative
     establishment which the existing soil on the steep side
     slopes has not supported.

     Flattening the steep slopes would reduce the potential for
     excessive soil erosion and provide an opportunity for the
     establishment of a higher quality vegetative cover.

b.   Comment:

     The conclusions of the RI/FS indicate that "an organic
     plume is not migrating from the Site" and that "the L&RR
     Site is not presently impacting the local private wells".
     This, along with the incorrect results from the HELP model,
     do not justify the need for capping the existing uncapped
     side slopes on the northeastern side of the landfill.
     Wehran believe that these areas should be revegetated after
     the methane gas extraction system comes on-line.  In the
     interim, the side slopes should be reseeded where needed to
     prevent erosion.

     EPA Response;

     As discussed in detail in*response to comment A.5. in Part
     2, there are a number of reasons for upgrading the present
     landfill closure and more specifically installing a
     synthetic cover on the northeast portion of the landfill.
     Although the groundwater monitoring results indicate that a

-------
RESPONSIVENESS SUMMARY                                    page 31
Landfill & Resource Recovery Site	
     plume of hazardous contaminants is not presently migrating
     from the Site, historical information indicates that a plume
     could emerge in the future.  Furthermore, EPA must select a
     remedy that protects groundwater.  The infiltration in the
     uncovered area has been estimated to be 27.64 inches per
     year, as calculated in the RI/FS Report using the HELP
     model, 19.3 inches/yr, as calculated by Wehran in their 1983
     closure plans using the Thornthwaite method as modified by
     Fenn, 16 inches/yr, as calcualted by EC Jordan using the
     same method, and 6.8 inches/yr, as calculated once again
     using this method by Wehran in their 1988 comments.  EPA
     believes that the actual infiltration realistically falls
     within the range between 6.8 in/yr and 19.3 in/yr.  The
     covered portion of the landfill reduces infiltration to
     approximately 0.3 inches/yr.  It is clear that a synthetic
     cap on the uncovered portion of the landfill will minimize
     infiltration and the migration of liquids through the
     landfill to the lowest practical extent and protect
     groundwater.

c.   Comment t

     The first component of EPA's Proposed Plan is upgrading the
     existing landfill closure to conform with either Alternative
     3 or Alternative 4 of the RI/FS Report.  Wehran's position
     is that the final cover plan proposed in the Court Order and
     Consent Order and Agreement, dated July 13, 1983 (the 1983
     Court Order), is appropriate and adequate for the L&RR Site.

     EPA Response;

     The closure plans established by Wehran for the 1983 Court
     Order are not appropriate or adequate because they do not
     meet the requirements of CERCLA.  In order to meet the
     requirements of CERCLA, the landfill closure must protect
     human health and the environment.

     It is evident from observing the impacts to the wetlands
     that the existing closure is not protecting the environment.
     The existing surface water runoff management system, slopes
     and vegetation are not minimizing erosion and the eroded
     soil is filling in the wetlands.  The selected remedy will
     upgrade the existing surface water management system,
     stabilize the slopes and establish vegetation to minimize
     erosion.  Furthermore, the impacted wetlands will be
     remediated and re-vegetated.

     By not minimizing infiltration, the existing closure is not
     protecting the groundwater.  Considering the lack of
     definitive information regarding the location, types and
     amounts of hazardous wastes and the hydrologic flow within
     the landfill, the synthetic cover in the northeast area is
     necessary to protect the groundwater aquifer which is
     designated as a potential future drinking water source.

-------
RESPONSIVENESS SUMMARY                                    page 32
d.   Comment t
     The second component of EPA's Proposed Plan is installing a
     gas collection and thermal destruction system.  The gas
     management program established by the 1983 Court Order will
     provide the required benefits of controlling landfill gas
     emissions.

     EPA Response;

     EPA has proposed three technical approaches that will reduce
     gaseous emissions to levels that will eliminate the
     estimated risk and be protective of public health.  As
     stated in the Proposed Plan, the effectiveness of the gas
     treatment technologies proposed will have to be determined
     by pilot testing programs of individual systems during the
     design phase.  The effectiveness of individual systems will
     be judged by actual data generated during the pilot
     programs.  A methane recovery and removal system required by
     the 1983 Court Order will have to demonstrate, prior to
     construction, the capability to reduce emissions to levels
     that are protective of public health and the environment.
e.   Commentt
     The third component of EPA's Proposed Plan requires regular
     monitoring of the groundwater, surface water, and air.
     Wehran Engineering supports a monitoring program as included
     per the 1983 Court Order.

     EPA Response;

     The 1983 Court Order contains plans for monitoring the
     groundwater and surface water.  After consideration of the
     comments made on the Proposed Plan, EPA established a
     groundwater monitoring plan in the Record of Decision (ROD)
     which is different than the ones discussed in the RI/FS
     Report.  In establishing the monitoring plan, EPA considered
     the monitoring plan presented by Wehran as well as all of
     the hydrologic and geologic data collected to date.  The
     groundwater monitoring plan established in the ROD is
     necessary to meet the requirements of CERCLA.  This plan
     takes into consideration the fact that EPA is not selecting
     a permanent remedy, the uncertainties associated with
     landfilling of wastes and the fact that the landfill is
     situated over the Slatersville Reservoir which is a future
     potential drinking water source.  It is also important to
     note that the 1983 Court Order does not contain plans for
     air monitoring.  This monitoring is also needed-to meet the
     requirements of CERCLA to insure that the gas treatment
     system is protecting human health and the environment.

-------
RESPONSIVENESS SUMMARY                                    page 33
Landfill & Resource Recovery Site 	
f.   Comment:

     In as much as the preferred alternative is aimed at reducing
     the impacts of contaminants in the groundwater, General
     Dynamics does not understand how the alternative can be
     evaluated relative to reducing health impacts.

     EPA Response;

     As discussed in response to comment A.5. in Part 2,
     although a plume of hazardous contaminants is presently not
     migrating from the Site, there is a potential for one to
     emerge in the future.  The selected remedy is designed to
     protect public health and the environment from the threat
     posed by future releases.  Presently, a potential risk to
     public health and the environment is not posed from
     ingesting the groundwater.  However, the landfill is located
     over the Slatersville Aquifer which is designated as future
     drinking water source.  The selected remedy is designed to
     prevent a release to the groundwater while at the same time
     monitoring to insure that any threat from a release will not
     impact the intended use of the aquifer.

5.   Wetlands

a.   Comment;

     The first paragraph on page 10-25 of the RI/FS Report states
     that "the most severe environmental effects from the L&RR
     Site are due to erosion of landfill soils and subsequent
     sedimentation in the wetland floodplain".  Wehran contends
     that this conclusion is not a CERCLA issue.'

     EPA Response;

     Section 104(a)(1) of CERCLA states that "Whenever (A) any
     hazardous substance is released or there is a substantial
     threat of such a release into the environment, or (B) there
     is a release or substantial threat of release into the
     environment of any pollutant or contaminant which may
     present an imminent and substantial danger to the public
     health or welfare, the President is authorized to act,
     consistent with the national contingency plan, to remove or
     arrange for the removal of, and provide for remedial action
     relating to such hazardous substance, pollutant or
     contaminant at any time, or take any other response measure
     necessary to protect the public health or welfare or the
     environment."

     There are substantial threats of releases qf hazardous
     substances at the L&RR Site.  The sand cover was installed
     to prevent releases of hazardous substances.   The correction
     of the erosion from the sand cover at the Site, including
     the restoration of the wetlands affected by that erosion, is

-------
RESPONSIVENESS SUMMARY                                    page 34
     a response action necessary to protect public health, or
     welfare and the environment.  Section 101 of CERCLA defines
     "response" to include "removal", and defines the latter to
     include "such other actions as may be necessary to prevent,
     minimize or mitigate damage to public health, welfare'or the
     environment which may result from the release or threat of a
     release."

     Section 101 states that the term "pollutant or contaminant"
     includes "any element, substance, compound, or mixture,"
     which, "after release into the environment and upon
     exposure, ingestion, inhalation or assimilation into any
     organism, will or may reasonable be anticipated to cause
     death,."  At the LtRR Site, the sand eroding from the
     landfill cover is a substance that is causing death to
     organisms in the wetlands.  Furthermore, this sand is
     preventing the reestablishment of the wetlands.  The sand
     needs to be remediated and future impacts need to be
     prevented.  CERCLA gives EPA the authority to remediate this
     substance from the wetlands and prevent future impacts.
b.   Comment t
     The third paragraph on page 10-25 states "that continued
     erosion is expected to prevent recolonization by wetland
     plant species".  Wehran notes that during the Site visit
     conducted on August 5, 1988, recolonization by wetland plant
     species was, in fact, observed in many locations impacted by
     sedimentation.

     EPA Response;

     Recolonization of some sections of the wetland plant species
     was observed on August 5, 1988, indicating sediment loading
     rates were lower than expected in some areas.  However, in
     other areas, die off of alders which had been alive during
     wetland investigation was observed, including that impacts
     to the wetland are continuing to occur.  Additionally, the
     wetland continues to have a low value in terms of aquatic
     habitat and other functional attributes.
c.   Comment;
     Extrapolation of effects from acute toxicity tests performed
     in many different laboratories to field situations is an
     inappropriate practice.  The hypothesis that an impact on
     the system exists based on chemical analysis of samples from
     the wetland media is suspect.  Furthermore, hardness data
     was not collected to adequately assess the aquatic water
     quality criteria.

-------
RESPONSIVENESS SUMMARY                                    page 35
Landfill & Resource Recovery Site	.	
     EPA Response:

     Extrapolation of laboratory test data to predict impacts in
     the field is a widely utilized EPA approved practice,.in
     lieu of field test data.  In addition, the toxicity data
     reported were from tests reviewed by EPA according to
     stringent protocol and deemed valid; they are listed in the
     EPA Water Quality Criteria Document for each chemical.

     Hardness of the water was not measured during the
     environmental sampling; however, EC Jordan contacted RIDEM,
     who said that 50 mg/1 is a typical hardness value for
     surface waters in Rhode Island and should be used to
     calculate protective criteria in the absence of site-
     specific hardness data.

d.   Comment;                                               .  -

     The effectiveness of the remedial alternatives at reducing
     the environmental impacts to the wetlands cannot be assessed
     because no objective system of quantifying damage is
     available.  Remediation may cause more damage to the
     wetlands.

     EPA Response;

     The sampling survey was qualitative in that no calculation
     of diversity indexes or population densities were made.
     However, it was clear from the species of invertebrates
     identified and the numbers of individuals collected that
     markedly lower population densities and fewer taxa existed
     in areas containing large quantities of erosional sediment
     compared with relatively unaffected areas.  Although low
     levels of toxicants were detected in the wetlands, the
     deposition of erosional sediment has greatly reduced the'
     value of the wetland in terms of aquatic habitat and other
     functional attributes.  Therefore, remediation is warranted
     and will not result in significantly greater damage than has
     already occurred.

     The magnitude and degree of damage to the wetlands is
     adequately described and the areas that require remediation
     are clearly delineated in the RI/FS Report.  Further details
     will be gathered during the design phase of remediation and
     erosion management will be completed prior to proceeding
     with wetland remediation.

6.   Remedial Alternatives Analyzed

a.   Comment;

     Wehran concurred with the results of the RI/FS Report that
     gas evacuation with some type of combustion system is
     worthwhile for the L&RR Site.  However, gas evacuation

-------
RESPONSIVENESS SUMMARY                                    page 36
     systems have performed well in non-capped sites.  Individual
     gas wells can be adjusted for optimal vacuum pressures,
     thus, assuring that air intrusion is not a significant
     factor in the combustion process.  Should a minor amount of
     air penetrate through the cover soils and be collected
     within the system, a possible soil and waste drying effect
     would result and further reduce potential leachate
     generation.  Therefore, Wehran does not feel the argument
     favoring a synthetic cover, based on the grounds of air
     intrusion, has any merit and requests further consideration
     of Alternative 2 and an active gas collection system.

     EPA Response;
                                •
     Although gas extraction systems can be operated on sites
     without synthetic covers, to obtain the best operating
     conditions the gas extraction system should be operated in
     conjunction with a synthetic cover in the northeast area.
     An uncovered landfill affords the opportunity for air to
     enter the landfill and dilute the landfill gas.  The concern
     is not only that there would be dilution, but also that the
     dilution would be uncontrolled.  This situation would reduce
     the quantity of combustible methane gas being drawn, reduce
     the quality of the gas to be burned, and introduce a greater
     variability into the landfill gas composition.  In turn, the
     efficiency production would be reduced.

     Landfill gas is generally combined with 4 to 6.5 volumes of
     air per volume of gas to obtain a proper burning mixture.
     With the current cover system, an unknown quantity of air
     would be drawn into the landfill.  It would be difficult to
     control the air to gas ratio required for proper operation
     without supplemental fuel and continuous monitoring of
     system performance.

     Gas treatment is required due to the presence of hazardous
     constituents in the landfill gas.  Installation of the liner
     would increase the probability of attaining the destruction
     and removal efficiencies expected with the systems.

     Additionally, the primary reason for installing the
     synthetic cover in the northeast area of the Site was to
     protect the groundwater.  Alternative 2 does not include a
     synthetic cover and therefore does not provide the necessary
     groundwater protection.
b.   Comment;
     There were no investigations in the landfill.  Since
     geophysical surveys were not conducted within the limits of
     the landfill, the contaminant source has not been adequately
     characterized.  Without this information, the effectiveness
     of the alternatives at minimizing infiltration can not be
     properly assessed.

-------
RESPONSIVENESS SUMMARY                                    page 37
Landfill & Resource Recovery Site	___	
     EPA Response:

     EPA's RI/FS for the L&RR Site was conducted using a phased
     approach.  At the conclusion of the first phase,  EPA
     discovered that a plume of hazardous contaminants was not
     migrating from the Site.  Therefore, EPA did not believe it
     was necessary to conduct investigations within the landfill
     and disrupt the existing landfill cover which may be
     protecting the groundwater.  Instead, EPA believes that it
     is more effective to implement a groundwater monitoring
     program to assess the performance of the Site.

7.   Site History

a.   Comment;

     The information presented on page 1-9 and ES-2 of the RI/FS
     Report is incorrect.  In 1985, Wehran prepared a Remedial
     Investigation Summary Report.  This was not a separate
     investigation but a summary report utilizing data from
     numerous engineering investigations and reports for the
     L&RR Site.  The purpose of this report was to identify to
     EPA that an adequate amount of investigative data was
     available to initiate remedial activities in conformance
     with the Court Order between L&RR and the RIDEM. 'Wehran was
     never advised that this report was evaluated by EPA's
     contractor (GCA Corporation) or that there were data gaps
     or deficiencies noted during this evaluation, nor was Wehran
     given any opportunity to correct any alleged deficiencies.

     EPA Response:

     EPA acknowledges Wehran's comment and adds the following
     clarifying points.  Between June of 1983 and January of
     1985, EPA conducted numerous negotiations with L&RR, Inc..,
     to conduct an RI/FS.  An agreement was not reached and EPA
     withdrew from the process of negotiations on January 29,
     1985, intending to conduct an RI/FS using federal funds.
     The owner proceeded to close the landfill in January of 1985
     according to the 1983 Court Order and plans developed by
     Wehran.  During 1985 and 1986, GCA under contract to EPA,
     observed the Site closure operations and evaluated its
     compliance with RCRA Subtitle C regulations.  The
     information obtained by GCA was intended to supplement
     information obtained during EPA's RI/FS.  EPA notified
     L&RR, Inc., of deficiencies in the closure operations in a
     number of written correspondence throughout the closure
     operations.

-------
RESPONSIVENESS SUMMARY                                    page 38
8.   Groundvater and Geophysical Investigations

a.
     The number, location and design of the wells is insufficient
     for characterizing current or future impacts of contaminants
     on groundvater.

     EPA Response;

     A number of factors must be considered when establishing a
     network of groundwater monitoring wells at a site.
     Presently there are 14 groundwater monitoring wells
     installed around the perimeter of the Site.  Nine of these
     wells were installed by the present Site owner.  After
     reviewing hydrologic and geologic information for the Site,
     EPA installed five additional monitoring wells during the
     RI/FS to gather information to characterize contamination at
     the Site.  The long-term groundwater monitoring plan
     outlined in the Record of Decision requires a new cluster of
     wells.  This cluster will have two wells and will be located
     between monitoring well clusters CW-6 and CW-7.  The
     specific location of this cluster will be decided during
     the design phase.  Given the geologic conditions at the
     Site, this monitoring well network will identify a
     contaminant groundwater plume migrating from the Site.
     Given that above background concentrations of inorganic
     substances and other parameters in the groundwater have been
    .detected down gradient from the Site, this suggests that
    'these wells are properly located to also intersect organic
     contamination .
b.   Comment
     The geophysical investigation was extremely limited since
     only six stations were vertically sounded.  Furthermore, the
     zones of high conductivity were interpreted to be due to
     possible leachate.  However, the high conductivity could be
     due to the power lines, buried drums or other metal objects
     within the landfill.

     No explanation was given for the inability to interpret
     vertical resistivity soundings B, E and F.

     EPA Response;

     The data from vertical electrical resistivity soundings was
     very limited as noted and the data was not used in a
     quantitative sense for the construction of geologic
     profiles.

     During the RI, the proximity of the power lines was not
     expected to substantially affect the results.  Data that was
     expected to be the result of or affected by buried drums and

-------
RESPONSIVENESS SUMMARY                                    page 39
Landfill & Resource Recovery Site       	  	
     debris was indicated as such in the results.

     No solutions are presented for vertical soundings B, E and F
     because the data quality was not sufficient to provide
     reliable solutions.  There was "scatter" present in all
     three of these data sets, perhaps due to lateral variation
     in stratigraphy/moisture conditions.

c.   Comment;

     Bedrock interpretations in the RI were base on five test
     borings and geophysical data.  The spacial distribution is
     not adequate for accurate bedrock elevation interpretation.

     EPA Response:

     It is correct that fewer hydrogeologic data were obtained
     from the bedrock flow system.  In an attempt to further our
     understanding of the bedrock flow regime, a water balance
     was conducted to determine the flow into or out of the
     bedrock aquifer.  Exploration of the bedrock would have been
     conducted during a latter phase of study if significant
     overburden contamination was encountered in the first phase.

d.   Comment;

     Fate and Transport of the groundwater is not adequately
     characterized.  It is likely that the ice contact deposits
     form the primary pathway for migration of contaminants from
     the landfill to off-site areas since the permeability of
     this unit is estimated to be more than the kame delta
     deposits.

     EPA Response:

     A specific figure for indicating groundwater flow in the ice
     contact deposits was not developed for several reasons.
     First, the ice contact deposits do not appear to be aerially
     extensive and seemed to occur as a lense.  Second, where
     they were encountered, the potentiometric surface was very
     similar to the overlying kame delta deposits.


9.   Miscellaneous

a.   Comment;

     Tables 11-1 and 11-2 are not provided in the RI/FS Report
     and, as such, Wehran is unable to provide comment.  Wehran
     requests that these tables be made available for review and
     comment.

-------
RESPONSIVENESS SUMMARY                                    page 40
         & Resource Recoverv Site
     EPA Response!

     These tables were present in the original RI/FS document.  A
     copy of the original document was submitted to L&RR, Inc.
     Wehran could have requested a copy of these tables from the
     original document from either EPA or L&RR, Inc., during the.
     comment period.  Additionally, a complete copy of these
     documents were available for public review in two
     repositories as indicated in EPA's Proposed Plan.

b.   Comment!

     None of the data from the previous reports were used in the
     RI/FS completed by EC Jordan.

     EPA Response!

     The L&RR Site has been the focus of several investigations.
     The information and data developed in these prior studies
     and investigations has been considered, and where
     appropriate, has been used in the evaluations for the L&RR
     RI/FS.  Most of this data could only be used qualitatively
     because quality assurance/quality control information was
     not available for the data.
B.   LEGAL CONCERNS REGARDING EPA INVESTIGATIONS AND THE PROPOSED
     PLAN

1.   Site History

a.   Comment;

     The company that conducted the RI/FS, namely E.C. Jordan
     Company, used to be known as Perkins Jordan, Inc.  The RI/FS
     Report fails to mention that the consultant which was
     advising the State of Rhode Island in matters regarding the
     L&RR Site leading up to the Consent Order and Agreement was
     none other than this identical firm, at the time called
     Perkins Jordan.  Consequently, the credibility of the
     current recommendation by this firm to spend five to six
     million dollars on the slopes is undermined by the fact that
     in 1983 this same firm studied this Site and did not make
     this recommendation.

     EPA Response!

     It is correct that in 1983, Jordan Co. personnel working as
     part of Perkins Jordan, Inc., served as consultants to the
     RIDEM.  Jordan's role at this time was to provide expert
     testimony on the potential for the L&RR landfill to impact
     domestic wells in the area.  Jordan personnel reviewed
     available data provided by RIDEM and indicated that, in
     their professional judgement, the potential for impact to

-------
RESPONSIVENESS SUMMARY                                    page 41
Landfill & Resource Recovery Site    	         	
     wells existed.  However, during that study no samples were
     collected or analyzed and no engineering evaluations were
     made regarding landfill design closure.

b.   Comment;

     Nowhere in the RI/FS Report is there any mention that in
     1983 the RIDEM and L&RR, Inc., entered into a Consent Order
     and Agreement setting forth how to close the Site in an
     "environmentally sound manner".  Furthermore, at a. contested
     hearing on July 13, 1983, the Superior Court of the State of
     Rhode Island approved that Consent Order and Agreement,
     entered it as a Court Order, and retained jurisdiction over
     the Site.  The 1983 Court Order approved and instituted
     stringent plans for:  final operation, closure, capping,
     methane recovery and removal, post-closure monitoring,
     setting aside money for long-term monitoring, stabilization
     of slopes, vegetating slopes, and litter and dust control.
     The plans for these were explicitly incorporated as part of
     the Court Order.

     EPA Response;

     The purpose of this RI/FS Report was not to give a detailed
     explanation of the history of the litigation between RIDEM
     and L&RR, Inc.  EPA is aware of the 1983 Court Order.
     However, EPA was not a party to the State Court proceedings
     and is not bound by its terms and conditions.  The
     Administrative Record contains extensive documentation
     regarding the history of the Site as well as a copy of the
     1983 Court Order.  All of this information was reviewed by
     EC Jordan prior to conducting the RI/FS.

c.   Comment:

     The RI/FS fails to mention that before the RIDEM agreed to
     enter into the Agreement on June 29, 1983, the RIDEM sent
     all these plans and proposals to the EPA for review.  These
     plans explicitly dealt with slopes and covers as well as the
     extent of infiltration and steps to minimize it.  After
     intensive review by EPA and meetings between and among the
     EPA, the RIDEM, and L&RR on June 20, 1983 and June 26, 1983,
     the EPA gave the RIDEM its OK to enter into the Consent
     Order and Agreement (the 1983 Court Order).  In reliance on
     that, on June 29, 1983, the RIDEM proceeded to sign the
     Consent Order and Agreement.

     Along those lines, the RI/FS Report also fails to mention
     that the EPA reviewed the 1983 Court Order as a" remedial
     action and as a RI/FS back in 1983.  The EPA analyzed the
     1983 Court Order from that point of view and made comments.
     Those comments are set forth in an EPA letter dated July 26,
     1983.  Consequently, the credibility of this report's
     recommendations is eroded by the fact that the report fails

-------
RESPONSIVENESS SUMMARY                                    page 42
     to mention that the EPA in 1983 reviewed the 1983 submission
     both as a remedial action and as an RI/FS and did not find
     fault with those parts which the current report finds fault
     with.

     EPA Response;

     EPA did not approve the 1983 Court Order between L&RR, Inc.,
     and RXDEM, either as a fulfillment of the requirements of
     the National Contingency Plan (NCP), 40 CFR Part 300, or in
     any other sense.  EPA's July 26, 1983 letter to David Wilson
     explicitly states that RIDEM had recommended the settlement
     to EPA, as they were required to do by the terms of the
     Court Order, but the letter does not say that EPA had
     accepted the RIDEM's recommendation.  In fact, EPA's letter
     recommended substituting a different groundwater monitoring
     plan and specifically queried whether remedial action had
     been considered to prevent off-site groundwater
     contamination.  The record shows that after reviewing the
     July 26, 1988 letter, L&RR, Inc., with its consultants,
     Wehran Engineering,  met with EPA and discussed additional
     work to be covered by an administrative consent order to be
     issued by EPA on consent to L&RR, Inc.

     The record shows that in subsequent months, EPA attempted to
     negotiate with L&RR, Inc., for the performance of a Remedial
     Investigation/Feasibility Study which would satisfy federal
     requirements.  The record shows that EPA considered the
     available information on the Site insufficient for EPA to
     approve L&RR's closure plans.  Specifically, EPA wanted
     further investigation of the bedrock aquifer, the potential
     for off-site groundwater contamination, the extent of off-
     site contamination,  if any, the extent of impacts on off-
     site surface water and wetlands and the effect of the risk
     posed by air releases.

     In a letter dated December 13, 1984, David Wilson of L&RR,
     Inc., informed EPA that L&RR, Inc., would not sign EPA's
     proposed consent order.  Mr. Wilson proposed to submit new
     information to EPA in an effort to convince the Agency that
     the order was unnecessary.  EPA replied in a letter dated
     January 29, 1985, stating that EPA was withdrawing from
     negotiations with L&RR, Inc., and clearly stating that EPA
     was reserving the right to take further actions, either on
     its own or through its enforcement powers to obtain a
     complete RI/FS.  EPA indicated its willingness, on the basis
     of a satisfactory RI/FS, to consider whether closure under
     the Court Order would be sufficient to allow delisting of
     the Site from the National Priorities Lists (NFL).  In the
     same letter, EPA detailed the history of its communications
     with L&RR, Inc.  EPA emphasized that it did not agree with
     L&RR's position that EPA's July 26, 1983 letter constituted
     an "approval" of the 1983 Court Order.  EPA stated that it
     had never found that the closure satisfied EPA's

-------
RESPONSIVENESS SUMMARY                                    page 43
Landfill & Resource Recovery Site	
     requirements, and indicated that only compliance with the
     landfill closure standards of RCRA would satisfy EPA's
     policy  (That policy has since been made statutory in SARA).

     EPA wrote to L&RR, Inc., on May 13, 1985, re-iterating that
     EPA was not a party to the Court Order. . The letter offered
     comments, emphasizing that the comments were not offered as
     conditions for EPA approval of L&RR's work, which EPA would
     hot give outside of an enforceable consent order with EPA.
     EPA's comments specified that the closure did not appear to
     satisfy the requirements of 40 CFR Subparts F,G and N.  EPA
     specifically indicated that the proposed cover appeared
     unlikely to provide long-term minimization of infiltration.
     Subsequently, in letters dated June 7, August 13, and
     October 10, 1985, EPA commented on certain aspects of L&RR
     activities, while re-establishing that EPA was not prepared
     to give L&RR formal approval of its closure.  EPA noted
     that it did not have the authority to enforce the state'
     consent order, and did not have resources to carry out a
     comprehensive review of activities carried out by a party
     which had refused to enter an enforceable consent order with
     EPA.  EPA's comments were offered only as "comments and an
     indication of the standards against which the Site closure
     may be evaluated by EPA in the future."  EPA again
     reiterated its position and set forth in detail its
     concerns about L&RR's closure in a letter dated November 1,
     1985, identifying specifically the lack of a cap in the area
     which EPA now proposes to cap.  This letter was sent to L&RR
     before completion of the closure.  In summary, the record
     clearly indicates EPA's disapproval with the closure
     conducted by L&RR to date.

d.   Comment;

     The RI/FS forgets to mention that the Superior Court of the
     State of Rhode Island has retained jurisdiction over the
     Site.  With due respect to the EPA, no one has any authority
     to do anything to the L&RR Site except in conformity with
     the terms and conditions of that Court Order.  While federal
     courts generally have jurisdiction in Superfund cases, it is
     doubtful that a federal court would intrude on the existing
     exercise of state court jurisdiction, given the doctrine of
     comity, notions of estoppel, and the conclusion of the RI/FS
     that neither groundwater nor the surface water nor the
     sediments pose a threat to public health.

     EPA Response;

     The state proceedings have not deprived EPA of the authority
     to carry out response actions or take enforcement under
     CERCLA.  In fact, CERCLA §122(e)(6) specifically prohibits
     any responsible party from undertaking any remedial action
     without authority from EPA after EPA has commenced an RI/FS.
     Thus, L&RR may not carry out further remedial action without

-------
RESPONSIVENESS SUMMARY                                    P*?e 44
     federal approval.

e.
     There are several inaccuracies regarding the history of the
     Site in the RI/FS Report.  This comment is intended to
     correct some of them.

     L&RR's landfill license was up for renewal as of December 1,
     1980 and L&RR filed a timely renewal application.  Since
     L&RR had made a timely and sufficient application for the
     renewal of its license, its existing license did not expire.
     Its application was finally determined by the department at
     the end of October 1981 and pursuant to 6.L. 42-35-14 (b),
     the reviewing court in successive orders continued the
     license in effect through mid-January 1985.

     On November 9, 1981, L&RR ceased operating in response to a
     RIDEM order.  L&RR went to court to get a court order.
     L&RR ceased operations from November 9, 1981 until December
     28, 1981, at which time the Superior Court of the State of
     Rhode Island ruled.  The Court ruled that the RIDEM decision
     dated October 30, 1981 was "replete with procedural and
     substantive anomalies of grave proportions" and issued a
     court order allowing L&RR to continue to operate.  L&RR
     resumed operation that afternoon.

     The RIDEM tried to appeal the Superior Court order but was
     not successful.  At that juncture, the RIDEM issued a second
     order against L&RR to cease operations.  L&RR went to court
     and asked to have the RIDEM held in contempt.  On January
     20, 1982, the Superior Court of the State of Rhode Island
     held the RIDEM in contempt and issued an order that L&RR
     could continue to operate under the supervision and
     jurisdiction of the State of Rhode Island.  The RIDEM on -or
     about January 22, 1982 withdrew its second order.  However,
     L&RR remained under the supervision and jurisdiction of the
     court which is in effect today.  L&RR closed pursuant to a
     Superior Court order issued on July 13, 1983 which allowed
     L&RR to continue operating through mid-January 1985.  As
     January 1985 approached, there was a dispute as to whether
     certain conditions set forth in the court order would allow
     L&RR to stay open longer than the date originally planned
     for, which was January 13, 1985.  L&RR and the RIDEM brought
     this to the attention of the court before that date.  Court
     hearings were held, at the close of which on January 20,
     1985 the court ruled that the conditions justifying L&RR
     staying open further had not been met and L&RR was ordered
     to close in conformity with the previous court order, which
     it did.

-------
RESPONSIVENESS SUMMARY                                    page 45
Landfill & Resource Recovery Site	
     EPA Response;

     EPA acknowledges this information and entered it into the
     Administrative Record.


2.   Applicable or Relevant and Appropriate Requirements (ARARs)

a.   Comment;

     The 1983 Court Order have extraordinarily strong bearing on
     what are the applicable and relevant and appropriate
     standards by which this Site should be judged.  CERCLA
     indicates that ARARs are supposed to be site-specific.
     There is hardly anything more site-specifie than a Court
     Order in a contested case determining what is
     environmentally sound for this Site.  Therefore, as a matter
     of law, that Court Order sets forth the applicable and
     relevant and appropriate standards.

     EPA Response:

     CERCLA §121 establishes the clean-up standards to be met
     under CERCLA.  A court order is not a "promulgated standard,
     requirement, criteria or limitation" which must be met by a
     CERCLA remedial action.  Section 121(d)(c)(iii) specifically
     requires that state ARARs be of "general applicability", and
     be based on "hydrologic, geologic, or other relevant
     considerations."  Moreover, §121 does preclude imposition of
     more stringent federal standards where state clean-up
     standards are less stringent than relevant federal ones.

b.   Comment t

     The RI/FS Report discusses applicable Rhode Island
     regulations governing covers for hazardous waste sites and
     specifically a cover thickness requirement of 24 inches.
     However, the 1983 Court Order contains a statement by the
     Rhode Island Department of Environmental Management and its
     Director that they accept and approve this Court Order and
     Agreement, "as full compliance with and fulfillment of any
     and all requirements of all applicable rules, regulations,
     and statutory provisions under the jurisdiction of the RIDEM
     and the Director".  This statement negates the RI/FS
     Report's claim that state ARARs require more.

     EPA Response;

     EPA finds the 24-inch cover requirement to be "relevant and
     appropriate," even if it is not "applicable*1 because of
     RIDEM's settlement with L&RR.  See also preceding
     responses.

c.   Comment:

-------
RESPONSIVENESS SUMMARY                                    page 46
       l & Resource Recoverv Site
     The RI/FS assumes that the RCRA standards are "relevant and
     appropriate" to the entire Site.  However, that fact is not
     substantiated by the record.  It is particularly not
     substantiated with regard to the steeper slopes.  The'RCRA
     standards are applicable to hazardous waste sites.  The
     RI/FS states that hazardous waste was placed in one area of
     the landfill and covered with a synthetic cover in 1979.
     More trash was placed on top of this area and then another
     synthetic cover was placed pursuant to the 1983 Court Order.
     Therefore, the RCRA standards are not relevant and
     appropriate.

     EPA Response;

     EPA finds that the RCRA requirements are relevant and
     appropriate at this Site because they address problems or
     situations that are sufficiently similar to those at other
     hazardous waste sites.  There is information that clearly
     indicates that hazardous wastes was disposed of at the Site.
     However, there is no definitive information regarding the
     location of the hazardous waste.  The Site owner states that
     hazardous waste was co-disposed in the north-central area of
     the Site and covered with a synthetic cover in 1979.  Other
     reports in the Administrative Record indicate that this nay
     not be entirely correct.  Information regarding the existing
     condition of the cover installed in 1979 is not available.
     Information regarding the hydrologic flow within the
     landfill is also not available.  Channelized flow could
     result in infiltration from uncovered landfill areas
     impacting areas containing hazardous waste.  RCRA Subtitle C
     regulations for closure of landfills are well suited to
     address the situation at this Site and must be applied to
     the entire landfill.

     In addition, CERCLA is concerned with preventing a release
     of "hazardous substances" and the closure standard in the
     RCRA regulations is designed to prevent the release of
     "hazardous constituents."  The hazardous waste is not
     necessarily the only source of hazardous substances or
     hazardous constituents.  EPA therefore believes that the
     RCRA clousre performance standard should apply to the entire
     landfill.  EPA also believes that extension of the synthetic
     cover would be required under other closure standards
     applicable to solid waste landfills including RCRA Subtitle
     D, the Rhode Island Solid Waste Management Act and Rhode
     Islands's Groundwater Protection Act.

d.   Comment;
                                                \
     The key date in the analysis of relevant and appropriate
     requirements is July 13, 1983, the date the Superior Court
     of the State of Rhode Island determined what would be the
     appropriate way to close the Site in "an environmentally

-------
RESPONSIVENESS SUMMARY                                    page 47
Landfill & Resource Recovery Site	
     sound manner."  The RI/FS Report sets forth the .laws,
     regulations, and guidances it relied on.  Virtually all of
     them were adopted after that date.  There already was a
     remedial action in effect on July 13, 1983, before any of
     these things took effect.  The issue of the appropriate
     remedial action has already been determined in a contested
     case by a court of competent jurisdiction in 1983.
     Therefore, amendments to the federal law after the fact are
     not relevant.

     EPA Response:

     Nothing in CERCLA §121 supports the contention that
     standards adopted after the settlement of a state
     enforcement action are not relevant and appropriate.

3.   Landfill Gas Emissions and the Risk Assessment

a.   Comment t

     The report concludes that five million dollars must be spent
     on the steep side slopes because of the risk to the public
     from air emissions.  However, the report never tested the
     air emissions from the side slopes.  Therefore, there is no
     evidence in the record to substantiate that conclusion.

     EPA Response;

     The RI/FS report does not state that five million dollars
     must be spent on the steep side slopes because of the risk
     to the public from air emissions.  The work on the steep
     side slopes is primarily being conducted to protect the
     groundwater and the wetlands.  The synthetic cover proposed
     will also enhance the treatment of the gases from the vents
     which poses a potential risk to public health.  Detailed'
     information on the cost analysis is presented in Appendix BB
     of the RI/FS Report.  It is clearly stated that the cost for
     the work on the steep side slopes is estimated to be between
     $600,000 and $700,000.

4.   Remedial Alternatives Analyzed

a.   Comment t

     The RI/FS Report's repeated reference to the no-action
     alternative as meaning no remedial action is a material
     misstatement of fact.  There already is a court-approved
     remedial action in place.

     EPA Response:

     In conducting an RI/FS according to the NCP, EPA must
     evaluate what is referred to as the "no action" alternative.
     The evaluation of the no action alternative provides EPA

-------
RESPONSIVENESS SUMMARY                                    page 48
                    Recoverv Site
     with information regarding the risks posed to human health
     and the environment if no remedial actions are conducted at
     the Site.  In the case of L&RR, the Site owner had conducted
     work at the Site prior to completing an RI/FS.  The "no
     action" alternative evaluated by EPA considered the work
     conducted by the Site owner at the time of completion of the
     RI/FS.
5.   EPA's Proposed Plan

a.
     Under CERCLA Section 121, even if RCRA standards were
     relevant, no remedy can be approved unless it is "cost-
     effective".  This proposal patently is not.  The RI/FS
     Report states that, "On the basis of an assessment of
     existing site hydrogeologic and chemical data, the
     groundwater, surface water, and sediments do not pose a
     threat to public health." Given the fact that there is
     already a remedy in place and the remedy is working, it is
     not obvious in any manner whatsoever how spending an
     additional five million dollars could be cost-effective.

     EPA Response;

     As discussed in many responses previously, the selected
     remedy and specifically the synthetic cover is intended to
     protect the groundwater.  Although groundwater impacts are
     not evident to date, it is possible that a groundwater
     contaminant plume may emerge in the future.  EPA must chose
     a remedy that is protective of human health and the
     environment, meets ARARs, is cost effective and utilizes
     permanent solutions to the maximum extent practicable.

     Comment t

     The RI/FS Report argues that one small part of the Site does
     not minimize infiltration.  However, from the point of view
     of the entire Site, the Site as a whole minimizes
     infiltration.  If the landfill owner had not put a cover
     over 80% of the Site pursuant to the 1983 Court Order and
     Consent Order and Agreement, we would find ourselves in a
     situation today where we would have to determine over what
     part of the Site it would be cost-effective to put a liner.
     The only logical conclusion that could be reached would be
     that the only cost-effective area for placing a liner is the
     identical area where the liner now exists.  Consequently,
     had no liner ever been put down, a report done today would
     conclude that placing a liner over 80% of the Site would
     effectively minimize infiltration.

-------
RESPONSIVENESS SUMMARY                                    page 49
Landfill & Resource Recovery Site
     EPA Response;

     The RCRA Subtitle C regulations in 40 CFR § 264.310 are
     relevant and appropriate at the L&RR Site.  These
     regulations, among other provisions, require an owner'or
     operator at final closure to'cover the landfill with a final
     cover designed and constructed to provide long-term
     minimization of liquids through the closed landfill.  L&RR
     chose to close the landfill by capping approximately 80% of
     the landfill surface area with a synthetic cover.  This
     leads one to conclude that L&RR felt that a synthetic cover
     was a practical solution to reducing infiltration to the
     landfill.  EPA believes that to reduce the infiltration to
     the smallest amount, requires a synthetic cover over the
     remaining 20% of the landfill surface area.  A synthetic
     cover over the entire landfill will attain a standard of
     performance equivalent to the RCRA Subtitle C closure
     standard and assure protection of human health and the -
     environment.

c.   Comment;

     With regard to a methane recovery system, we note that the
     1983 Court Order requires a methane recovery system.  There
     is no reason for EPA to get involved in that because the
     state already has that within its jurisdiction.
     Furthermore, on February 11, 1987, L&RR, Inc., entered into
     a contract with O'Brien Energy Systems, Inc., for the
     installation of a methane recovery system at the Site.  The
     RI/FS establishes that once that system is in place, it will
     remedy any air problem, if there is one.

     EPA Response;

     Section 122(e)(6) of CERCLA specifically prohibits any   .
     responsible party from undertaking any remedial action
     without authority from EPA after EPA has commenced an RI/FS.
     Thus, L&RR may not carry out further remedial action without
     federal approval.  Due to the potential risks posed by the
     landfill's gaseous emissions,  this system must be
     implemented in accordance with EPA's Record of Decision and
     meet EPA's approval.

     The RI/FS Report does not establish that any particular
     methane recovery and removal system will remedy air
     pollution problems.  The RI/FS evaluated technologies that
     are capable of reducing the gaseous landfill emissions to
     the levels necessary to protect public health.  Since EPA
     has not evaluated a specific design, it is .not clear that
     the O'Brien Energy Systems, Inc., gas control system will
     achieve the emissions reductions necessary to meet the
     standard set by EPA's Record of Decision (ROD).

-------
RESPONSIVENESS SUMMARY                                    page 50
IV.  REMAINING CONCERNS

At the public informational meeting held in North Smithfield on
July 19, 1988, and at the informal public hearing held on August
10, 1988, local residents raised issues of concern for the'L&RR
Site regarding the design and implementation phase of EPA's
selected remedy.  The principle issues are described below, along
with statements about how EPA intends to address these concerns.

1.   Groundwater

     Citizens continue to be very concerned that a contaminant
     plume may form in the groundwater beneath the landfill and
     fail to be detected by the existing monitoring wells.  They
     are concerned that their residential wells may become
     contaminated as a result.

     As a result of this concern, EPA once again reviewed the '
     hydrologic and geologic information for the Site and
     established a groundwater monitoring plan that would detect
     a groundwater plume emerging from the Site.-  As part of this
     new plan, a new cluster of wells, consisting of two new
     wells at different depths, will be installed between
     existing clusters CW-6 and CW-7.

2.   Landfill Owner's Role in Implementing the Remedy

     Citizens feel strongly that the cleanup would not be
     conducted thoroughly by the landfill owner.  In particular,
     citizens are concerned about the landfill owner possibly
     operating the landfill gas treatment system.

     According to the law, EPA must negotiate with the
     responsible parties for conducting the remedial action.  If
     the responsible parties agree to implement the selected  -
     remedy in accordance with CERCLA, EPA will monitor the
     design and construction to insure that it is protective of
     public health and the environment.  Furthermore, the
     selected remedy includes an air monitoring program to insure
     that during operation the selected remedy remains
     proteqtive.

-------
                           ATTACHMENT A

                 COMMUNITY RELATIONS ACTIVITIES
                              AT THE
               LANDFILL AND RESOURCE RECOVERY SITE
                IN NORTH SMITHFIELD, RHODE ISLAND

Community relations activities conducted at the Landfill and
Resource Recovery Superfund Site (L&RR Site) have included'the
following:

o    1983 — EPA released a community relations plan describing
     citizen concerns about the L&RR Site and outlining a program
     to address these concerns and to keep citizens informed
     about and involved in Site activities.

o    October 1986 — EPA revised the community relations plan to
     reflect changes in the level of community concern and to
     plan activities designed to meet new community needs.

o    January 1987 — EPA held an informational meeting to
     present to the community EPA's plans for a Remedial
     Investigation and Feasibility Study (RI/FS) at the L&RR
     Site.

o    July 1988 — EPA arranged for the publication of two public
     notices in the Providence Journal and the Woonsocket Call
     announcing a public informational meeting and describing
     EPA's Proposed Plan for addressing contamination at the L&RR
     Site.

o    July 1988 — EPA mailed the Proposed Plan announcing EPA's
     preferred alternative for addressing contamination at the
     L&RR Site to all parties on EPA's site mailing list. .

o    July 19, 1988 — EPA held an informational public meeting to
     discuss the results of the RI/FS and to present EPA's
     Proposed Plan for the Site.

o    July 20 - September 2, 1988 — EPA held a six-week public
     comment period to accept public comments on the FS
     alternatives and the Proposed Plan.  The six week comment
     period included a three-week extension that EPA held to
     allow additional time for interested parties to participate
     in the remedy selection process.

o    August 10, 1988 — EPA held an informal public hearing to
     accept oral comments on the remedial alternatives evaluated
     in the FS and on EPA's Proposed Plan.

-------
           APPENDIX  B
   ADMINISTRATIVE RECORD INDEX
Landfill & Resource Recovery Site

-------
           APPENDIX  C






    STATE CONCURRENCE  LETTER






Landfill & Resource Recovery Site

-------
     STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
     Department of Environmental M*n«ctm«nt
     OFFICE OF THE DIRECTOR
     9 Hayn SttMl
     Providence. !U. 02908
                                   September 21, 1988
Mr. Michael Deland
E.P.A. Region  I
J.F. Kennedy Federal  Building
Boston, Massachusetts 02203

Dear Mr. Deland:

    I am writing  concerning  EPA'S proposed plan for remediation
at the Landfill and Resource Recovery Site (L&RR) in North
Smithfield, Rhode Island.

    This Department concurs  with those portions of the proposed
plan which are consistent  with the closure requirements
outlined in the 1988  Solid waste Consent Order and Agreement
between RIDEM  and L&RR,  Inc.   We understand your laws and
regulations may require  more stringent remedial actions and it
appears the additional components of your proposed remedy/
although more  protective,  are  not inconsistent with the closure
measures required by  the State's consent agreement.

                                   Very truly yours,
                                   Robert L. Bendick, Jr,
                                   Director
RLB/ms
cc: Torn Gate
0652B

-------