WATER POLLUTION CONTROL RESEARCH SERIES • 17010 ECZ 02/71
Wastewater Ammonia Removal
       by Ion Exchange
    U.S. ENVIRONMENTAL PROTECTION AGENCY

-------
        WATER POLLUTION CONTROL RESEARCH SERIES
The Water Pollution Control Research Series describes
the results and progress in the control and abatement
of pollution in our Nation's waters.  They provide a
central source of information on the research, develop-
ment, and demonstration activities in the Environmental
Protection Agency, through inhouse research and grants
and contracts with Federal, State, and local agencies,
research institutions, and industrial organizations.

Inquiries pertaining to Water Pollution Control Research
Reports should be directed to the Chief, Publications
Branch, Research Information Division, Research and
Monitoring, Environmental Protection Agency, Washington,
D. C. 20460.

-------
 WASTEWATER AMMONIA REMOVAL BY ION EXCHANGE
Mobile Pilot Plant Studies and Process Design
with Electrochemical Renovation of Regenerant
                     by
             Battelle-Northwest
         Richland, Washington  99352
             Project #17010 ECZ
             Contract #14-12-579
      Process Design with Air Stripping
          Renovation of Regenerant
                     by
     Soutr. Tahoe Public Utility District
     South Lake Tahoe, California  95705
             Project #17010 EEZ
             Contract #14-12-561
                   for the
       ENVIRONMENTAL PROTECTION AGENCY
                February 1971

-------
                EPA Review Notice
This report has been reviewed by the Environmental
Protection Agency and approved for publication.
Approval does not signify that the contents neces-
sarily reflect the views and policies of the
Environmental Protection Agency, nor does mention
of trade names or commercial products constitute
endorsement or recommendation for use.
                        11

-------
                             ABSTRACT
Pilot plant investigations were conducted on the ion exchange removal of
ammonia-nitrogen from clarified and carbon-treated secondary effluents
and from clarified raw sewage.  The ion exchange process utilized clinop-
tilolite, a natural zeolite.  Average ammonia removals from low magnesium
wastewaters were in the range of 93% to 97%.  With a wastewater Mg concen-
tration of 20 mg/1, solids formation presented problems but they appear
surmountable.  The primary method used for regenerant renovation was air
stripping with which a 2N regenerant at a pH of 11.5 is recommended.  Elec-
trolytic regenerant renovation using a neutral solution that is less prone
to solids formation was also piloted during the project.

Two process designs are included giving cost estimates for ion exchange
ammonia removal from tertiary effluent.  With capital costs amortized at
6% for 20 years, the total cost to remove ammonia from 1000 gal. of tertiary
effluent is 14-.8?! for a 7-5 m§cL plant using regenerant air stripping and 12,70
for a 10 mgd plant using electrolytic regenerant renovation.  The 7-5 m§d. de-
sign was prepared by South Tahoe Public Utility District under EPA Project
Number 17010 EEZ and is included for convenience.  Other work discussed in
the report was performed by Battelle-Northwest under EPA Project Number
17010 ECZ.

This report was submitted in fulfillment of Project Number 17010 ECZ,
Contract 1^4-12-579> under the sponsorship of the Water Quality Office,
Environmental Protection Agency.
                                   111

-------
                             CONTENTS
 SUMMARY AND CONCLUSIONS

 RECOMMENDATIONS

 INTRODUCTION

 PILOT  PLANT OPERATION

 ION EXCHANGE EQUILIBRIA

 COLUMN OPERATION

     Single Column  Loading Studies
     Two  Column Semi-Countercurrent Operation
     Zeolite Attrition

 REGENERATION STUDIES

     Normal Pilot Plant Regeneration
     Pilot  Plant Batch Recycle Regeneration

 REGENERANT  RECOVERY

     Air  Stripping  of Regenerant
     Electrochemical Renovation of Regenerant

 ACKNOWLEDGMENTS

 REFERENCES

 APPENDIX A
APPENDIX B  -
APPENDIX C  -
Sample Calculation of Ammonium Ion Loading
Using Activity Coefficients

Preliminary Design of a 10 mgd Ammonia
Removal Plant Utilizing Electrolytic
Renovation of Spent Regenerant

Engineering Design of a 7 = 5 mgd Ammonia
Removal Plant Utilizing Air Stripping for
Recovery of Spent Regenerant
                                                     Page

                                                       1

                                                       3

                                                       5

                                                       7

                                                      11

                                                      15

                                                      15
                                                      19
                                                      2^

                                                      27

                                                      27
                                                      32

                                                      39

                                                      39
                                                      39
50


55


62
                                 V

-------
                                 FIGURES
No.                                                                    jfog

 1    FLOWSHEET FOR AMMONIA SELECTIVE ION EXCHANGE PROCESS               8

 2    PHOTOGRAPH OF MOBILE PILOT PLANT IN OPERATION AT SOUTH             9
      LAKE TAHOE

 3    SELECTIVITY COEFFICIENTS VS. CONCENTRATION RATIOS OF              12
      SODIUM OR POTASSIUM AND AMMONIUM IN THE EQUILIBRIUM
      SOLUTION WITH HECTOR CLINOPTILOLITE AT 23°C FOR THE
      REACTION (Y)   4- (NH. )   =  (NH. )  + Y
                  Z      4 N        4 Z    N
 4    SELECTIVITY COEFFICIENTS VS. CONCENTRATION RATIOS OF              13
      CALCIUM OR MAGNESIUM AND AMMONIUM IN THE EQUILIBRIUM
      SOLUTION WITH HECTOR CLINOPTILOLITE AT 23°C FOR THE
      REACTION (X)z + 2(NH4)N = 2(NH4)Z + XN

 5    MINIMUM BED VOLUMES AS A FUNCTION OF NH3-N CONCENTRATION          17

 6    AMMONIA BREAKTHROUGH CURVES FOR A 6 FT CLINOPTILOLITE BED         18
      AT VARIOUS FLOW RATES

 7    EFFECT OF BED DEPTH ON AMMONIA BREAKTHROUGH AT 4 . 8 gpm/ft2        20
      FLOW RATE

 8    EFFECT OF BED DEPTH ON AMMONIA BREAKTHROUGH AT 9 . 7 bv/hr          21

 9    AMMONIA BREAKTHROUGH CURVES FOR 1ST AND 2ND COLUMNS IN SERIES     23
      WITH TAHOE TERTIARY EFFLUENT

10    PHOTOGRAPH OF WHITE MATERIAL ON TOP OF A BED OF CLINOPTILOLITE    28
      AT POMONA

11    EFFECT OF PURE WATER BACKWASH RATE ON SUBSEQUENT NH3~N BREAK-     29
      THROUGH

12    EFFECT OF ACID WASH ON SUBSEQUENT NH3-N BREAKTHROUGH              30

13    AMMONIA BREAKTHROUGH CURVES FOR COLUMNS FOLLOWING REGENERATION    31
      WITH UNCLARIFIED (1) AND CLARIFIED (2) REGENERANT WITH HIGH
      MAGNESIUM CONTENT

14    FIRST BATCH RECYCLE ELUTION CURVES                                33

15    FIRST AND SECOND BATCH RECYCLE ELUTION CURVES                     34

16    REGENERANT BATCH RECYCLE WITH 3.6 BED VOLUMES OF 1 M CaCl2-0.2 M  36
      NaCl AT pH 11
                                  VI

-------
D .
                                                                  Page
7    EFFECT OF REGENERANT VOLUME AND pH ON AMMONIA ELUTION         37




8    EFFECT OF Mg+2 ON CELL RESISTANCE                             41




9    EFFECT OF H+ ACTIVITY AND FLOW RATE ON CELL RESISTANCE        42




0    BREAKPOINT CHLORINATION OF REGENERANT BATCH //I, RUN  3          45
                                 vii

-------
                                TABLES


No.                                                              Page

1    Typical Composition of Feed Streams                          Ic

2    Tahoe Performance Data for Runs with Two Columns in Sefies   22

3    Performance Data for Seventeen Runs at Blue Plains  with      25
     Two Columns in Series
                                 Vlll

-------
                        SUMMARY AND CONCLUSIONS
1.  The selective ion exchange process for ammonia nitrogen (commonly
called ammonia) removal from wastewater is believed to be best suited
for use in those areas which experience prolonged periods of freezing
weather during winter and where very high degrees of removal must be
consistently maintained.  Other processes such as air stripping^!/
alone and biological nitrification-denitrification(2) may be used in
warm climates at a lower cost but at somewhat lower efficiency.

2.  Process designs provided costs for two alternate ion exchange methods
of ammonia removal from tertiary effluent.  From a Battelle design
utilizing electrolytic regenerant renovation (this project), the cost
per thousand gallons was 9.04
-------
 5.   Batch regeneration by recirculating 4 bed volumes  of 1 M GaCl2,  0.2M
 NaCl and pH 11.5 (adjusted with lime)  solution appears to minimize
 regenerant volume.   However,  a wide range of  concentrations was not
 investigated and steady-state conditions may  not  have  been reached.   The
 regenerant was chosen to include:   (1)  significant Na  which has been
 found to lengthen the service cycle and shorten the.elution cycle; (2)  1M
 (2N) Ca concentration to provide for high elution capacity and approximate
 what would be expected with continued  lime pH adjustment in service; and
 (3) high pH to shift the equilibrium toward NH3 production to facilitate
 air stripping.  Further optimization of the regenerant composition may
 result from experience.  Wasting of regenerant may be  necessary if
 undesirable build-up in concentration  occurs.  On the  other hand,  con-
 siderable salt addition may be necessary due  to dilution of the regenerant
 during use.  Allowances for NaCl and lime additions used in the designs
 discussed in this report may have to be adjusted.

                       '                  '  +2
 6.   Processing of wastewaters with high Mg   concentrations  may require
 clarification of the regenerant to avoid plugging the  bed with Mg(OH)2-
 Additional work is needed to verify this approach.

 7.   Processing of clarified and filtered raw  sewage appears to cause
 some biological growth in the zeolite  beds but is adequately removed
 during the regeneration cycle.

 8.   Zeolite attrition was 0.17% per cycle when using high pH regeneration
 due to backwashing required for solids removal.  Attrition would be  very
 low for the neutral regeneration proposed with electrochemical regenerant
 renovation.  Under neutral conditions  much less solids would form and
 high rate backwashing would be unnecessary.  Zeolite ammonia capacity
 does not change significantly with service.

 9.   Pilot studies demonstrated that air stripping of regenerant is
 practical.  The calcium carbonate scale formed on the  stripping column
 packing did not interfere with the stripping  efficiency for operating
 periods up to 65 days.  The physical character of the  scale varied
 from flaky to hard.  Water spraying removed the flaky  scale to a large
 degree, but water fluidization of the  packing was required for removal
 of  the hard scale.

10.   Laboratory studies and preliminary pilot  studies demonstrated the
 feasibility of electrochemical renovation of  regenerant.  The electrical
 energy required to remove one gram of  NH3-N varied from 35-54 watt hours.
 White scale formation occurred on the  cell cathode.  This is expected to
 be  minimized, however, by promoting turbulence in the  cell with baffles
 or  other cell modifications.

-------
                         RECOMMENDATIONS
Further development of the electrochemical method of removing the ammonia
from the spent regenerant is recommended.  The major advantages of this
approach relative to that of air stripping of the spent regenerant are:

     1.  No precipitation occurs in the zeolite bed during regeneration
         because neutral solutions are used,

     2.  No atmospheric disposal of ammonia is necessary,

     3.  Overall scaling problems associated with the use  of lime
         are eliminated.

Preliminary cost studies indicate that electrochemical renovation of spent
regenerant ,will be competitive with air stripping renovation.

The development program recommended for electrochemical treatment of spent
regenerant from the selective ion exchange process should  include studies
to determine electrode life,  and optimum current density,  pH,  salt concen-
tration and temperature.  Methods to control calcium and magnesium hydroxide
scaling on the cathode should be evaluated to minimize cell resistance.

-------
                             INTRODUCTION
The results of laboratory and initial pilot plant studies on ammonia
removal by selective ion exchange have been reported previously(3»^)-
A naturally occurring zeolite, clinoptilolite, is employed as the ion
exchange medium which preferentially sorbs ammonium ions in the presence
of sodium, calcium, and magnesium ions.  The zeolite can be regenerated
with solutions containing high concentrations of calcium ions.   Spent
regenerant solutions can be renovated for reuse by air stripping or
electrolysis to remove ammonia.  Basically, the selective ion exchange
process concentrates the ammonia into a relatively small volume of
liquid (regenerant) which can be: (1) air stripped even in cold weather
using low heat input to prevent freezing and to maintain high ammonia
removal efficiency; or (2) electrolyzed to convert the ammonia into
innocuous nitrogen gas.

Consistently high ammonia removals from clarified trickling filter
effluent were previously demonstrated in the laboratory^).  The ammonia
removals varied from about 95% for a single zeolite bed with an output
of 150 bed volumes to more than 99% removal for two beds in semi-countercurrent
series operation with an output of 200 to 300 bed volumes.

The main objective of this program is demonstration of the use of the
selective ion exchange process on an engineering scale for removing
ammonia from a variety of wastewaters.  A 100,000 gpd mobile pilot plant
was employed in this effort which included operations at the South Tahoe
Public Utility wastewater treatment plant at South Lake Tahoe,  California;
the Pomona Wastewater Treatment Plant at Pomona, California; and the Joint
WQO-DC Pilot Plant at Blue Plains in Washington, D. C.  Wastewaters
encountered in the pilot plant studies include clarified  (Pomona) and
carbon treated (Tahoe and Pomona) activated sludge plant effluents and
clarified raw sewage (Blue Plains).

The above demonstration sites were selected to give a wide range in
dissolved organic concentrations and dissolved salts concentrations,
particularly magnesium salts.  The dissolved organics may foul the zeolites
directly or indirectly by supporting biological growths which cover the
zeolite particles.  Magnesium precipitates in the zeolite bed during
regeneration with lime and may cause operational problems where the
concentration is high.

Two process designs have been developed for zeolite ammonia removal from
tertiary effluent.  During the present Battelle project, a 10 mgd plant
utilizing electrochemical renovation of the regenerant was designed.  This
design paralleled one developed earlier for a 7.5 mgd plant using regenerant
air stripping by the South Tahoe Public Utility District under WQO/EPA
Contract No. 14-12-561.  The 10 mgd Battelle design is Appendix B in this
present report and the South Tahoe project report is included as Appendix C.

-------
                         PILOT PLANT OPERATION
                                                                          O)
The mobile pilot plant used in these studies has "been described previously
The water treatment unit (Recla-Mate SWB tertiary sewage treatment plant
manufactured by Neptune MicroFloc, Incorporated, of Corvallis, Oregon) was
not used for the most part because clarified water was available at the
demonstration sites.  The 39 in- diameter ion exchange vessels were converted
from 750 gallons capacity to 500 gallons capacity by leaving off the top sec-
tions.  This reduction in size greatly facilitated assembly and disassembly of
the ion exchange vessels by eliminating the use of a crane to lift the top
section to and from the roof of the trailer.   The 500 gallon capacity was en-
tirely satisfactory for the demonstration program.  A flow diagram for the
selective ion exchange process is illustrated in Figure 1 and a photograph of
the mobile pilot plant in operation at South Lake Tahoe is given in Figure 2.

                                                                    (R)
The stripping tower packing consisted of 1 in. polypropylene Intalox^
saddles for ease in removal and repacking.  Column diameter was ^3 in. and
packing depth was 7 ft.

Electrochemical renovation of regenerant involved the use of two 500 amp
electrolysis cells (manufactured by Pacific Engineering and Production
Company of Henderson, Nevada).  The electrolysis cell consists of a lead
dioxide coated graphite anode, ^ l/^ in. diameter by ij-5 in- l°ng» placed in
a copper can that serves as the cathode.

The feed streams were pumped downflow through either a single zeolite bed
or two beds in series.  Regenerant solutions  were pumped upflow through
the beds at rates sufficient to remove precipitated or filtered solids
from the beds.  During semi-countercurrent operation, which permits greater
utilization of the available ion exchange capacity,  the loaded zeolite bed
(first in series) was removed from service for regeneration while a freshly
regenerated bed was placed at the end of the  series.

-------
                        FILTRATION AND  ION  EXCHANGE
    Wastewater
              Flocculation, Sedimentation
               and Mixed Media Filtration
                  Filter Pump
    Backwash
       <«„-.
   Filtered
Water Storage
           n
                             Filter
                          Backwash Pump
            CD
            cn
               •4-
o>
en
tc
                     c.
                     o
      ["Air and A
                                    m

                                     I
                                     monia Exhaust
                 -J
   Clean Water
    for Reuse                I

Stripping
Tower


Tn Tm T*
jr^-J
Cm
Liqui

Sa
"I
1
t
L
P l-ino
                                       Main Ion
                                    Exchange Pump
                                    Regenerant
                                   and Ammonia
                                 Lime,
                              Salt Addition
                                       Air In
                            Air Blower
                                               Make-up Tank
       ZEOLITE REGENERATION  PROCESS
                                                       Regeneration
                                                          Pump
FIGURE  1.   FLOWSHEET FOR AMMONIA SELECTIVE  ION EXCHANGE PROCESS

-------
FIGURE 2.  PHOTOGRAPH OF MOBILE PILOT PLANT IN
           OPERATION AT SOUTH LAKE TAHOE

-------
                        ION EXCHANGE EQUILIBRIA


The ion exchange equilibria for the systems NH4-Na ,  NH^-K ,  NH4-Ca
and NH^-Mg+2, with clinoptilolite and other zeolites, have been reported
by Ames'3'.   The original data reported by Ames has been extended to
include higher Ca+2: NH^ and Na+: NH^ ratios.  Plots  of the NH^ selectivity
coefficients (defined in Appendix A) vs. the solution  concentration ratios
of the cations are shown in Figures 3 and 4.  This additional data is
useful for computing the equilbria in regenerant solutions.  However,
standard solutions of 0.1N_ were used in obtaining the data.  Corrections
for activity differences were needed to improve accuracy when using the
data in Figures 3 and 4 to predict maximum wastewater ammonia loadings
on clinoptilolite.  An example of the computation is  given in Appendix A.
                                 11

-------
103
102
10
                 Y- Na
0.01
0.1
                                                  10
                 100
                                                    1000
                          (YN)
                         P4JJ)
FIGURE 3.  SELECTIVITY COEFFICIENTS VS. CONCENTRATION  RATIOS  OF SODIUM OR POTASSIUM
           AND AMMONIUM IN THE EQUILIBRIUM SOLUTION WITH HECTOR CLINOPTILOLITE AT
           23°C  FOR  THE REACTION (Y)   +  (NH )   =   (NH . )   + Y
(NH )
   T IN
                                 =   (NH . )
                                       T"  Lj
                                                IN

-------
                 105


                 Iff4


                 103


                 102


                  10
10
                                102     103    104     105    106     107
                                            (NH4)
FIGURE 4.   SELECTIVITY COEFFICIENTS VS.  CONCENTRATION RATIOS OF CALCIUM OR MAGNESIUM
            AND AMMONIUM IN THE EQUILIBRIUM SOLUTION WITH HECTOR CLINOPTILOLITE AT
            23°C FOR THE REACTION  (X)   +  2(NH )   =

-------
                            COLUMN OPERATION
Single Column Loading Studies

Column loading studies were carried out to establish the volume of feed
water that can be processed through a zeolite bed until significant ammonia
breakthrough occurs.  The typical composition of the various feed streams
employed in these studies are listed in Table 1.
                                 TABLE 1
                   TYPICAL COMPOSITION OF FEED STREAMS
                      Activated Sludge Plant Effluent
                          Tahoe
                     Carbon Treated           Pomona*
NHo-N mg/liter

Na mg/liter

K mg/liter

Mg mg/liter

Ca mg/liter
 15
 ^

 10

  1

 51
    16
   120
    18
    20
Clarified Raw Sewage

     Blue Plains

         12

         35

          9
          0.2

         30
pH
  Range
  Avg.
 7-
6.5-8.2*
6.9, 7.8*
          7-9
          7-9
COD

TDS
 11


325
   10
  700
         50

        250
*NOTE:  Approximately half of the runs at Pomona were made with carbon treated
        secondary and the others with alum coagulated secondary.  The average
        pH of the carbon column effluent was 7-8 and the average pH of the alum
        coagulated secondary was 6.9-
                                     15

-------
The  equilibrium NHo-N bed loading computed for each of the wastewaters
listed  in Table 1  is ^.1 g/1, 3-9 g/1. and 4-. 3 g/1. respectively, for
Tahoe,  Pomona, and Blue Plains.  Figure 5 presents equilibrium bed load-
ing  in  an alternate way.  The minimum bed volumes required to attain
equilibrium NH^-N  loading are expressed as a function of the NH-j-N con-
centration in the  wastewater with the concentrations of metal ions held
constant.  For actual operation, the bed volume values given in Figure 5
will normally represent the 50 percent breakthrough point where the ef-
fluent  concentration is 50% of the feed concentration.

Tahoe and Blue Plains column loading data are given below.  However,
Pomona  loading data are thought to be atypical because of magnesium hy-
droxide formation  during' regeneration, and are not reported here.  Ways
of dealing with the magnesium hydroxide solids were investigated at
Pomona  but time did not permit obtaining loading data under realistic opera-
ting conditions.   The Pomona work is discussed in the section on Regenera-
tion Studies.

Ammonia breakthrough curves for a single 6 ft deep bed of clinoptilolite
are  illustrated in Figure 6 for Tahoe tertiary effluent with flow rates
varying from 6.5 to 9-7 bv/hr (bed volumes per hour) with 15 to 17 mg/1
NH3~N in the feed  stream.   A throughput value of 150 bed volumes is
recommended for design.  The average NH^-N concentration of the total
effluent to that point would be about 1 mg/1 or less.   Follow up break-
point chlorination would probably be more effective for removing the
residual, if required,  than greater ion exchange column throughputs.

The  average concentration for each curve is obtained by integrating under
the  curve.  Curve  1 at 8.1 bv/hr has the lowest average effluent NHo-N
concentration (0.67 mg/l)  for 150 bed volumes,  but it also has the lowest
average influent NHo-N concentration (15 mg/l) .  Curve 2, at 6.5 bv/hr,
has  an average of  0.83 mg/1 NH^-N in 150 bed volumes of effluent with an
influent containing 17 mg/1 Nff^-N.  Curve 3,  at 9. 7 bv/hr, has an average
effluent NH/3-N concentration of 1.2 mg/1 and high initial NH^-N leakage,
which is due to insufficient backwash removal of residual lime remaining
in the bed after regeneration.   The effluent pH for Curve 3 was 10.4- at
the  time of the first sample . . Since the ammonia is poorly ionized at high
pH,  the ion exchange sorption decreases and effluent NH^-N was high until
the residual lime washed out.   In spite of this,  NHo-N removals for 150
bed volume throughputs averaged 9^% over the three runs.
Exchange due to the 150 bed volume throughput value selected to maintain
an average NH-^-N concentration at or below 1 mg/1 uses only 55 to 58
percent of the zeolite's equilibrium capacity.  The number of bed volumes
throughput per bed can be increased while maintaining low NH3~N effluent
concentrations with semi-countercurrent operation.  This type of opera-
tion   using two beds will be discussed later.
                                  16

-------
    40
en
    30
    20
    10
     0
       0
                                             D  TAHOE
                                             X  POMONA
                                             O  BLUE  PLAINS
                                         I
100
  200        300
MINIMUM  BED VOLUMES
400
500
      FIGURE 5.  MINIMUM BED VOLUMES AS A FUNCTION OF NH -N CONCENTRATION

-------
00
o
UJ
CO
               o
                      OPERATING CONDITIONS:
                      FLOW RATES:(1)8. Ibv/hr (2)6.5bv/hr,  (3)9.7bv/hr
                      ZEOLITE GRAIN SIZE:  20x50MESH
                      BED VOLUME:  50 FT3
                      AVE. INFLUENT NH^N: (1) 15 mg/l,  (2) 17 mg/l,  (3) 17 mg/l
                      FEED:  TAHOE'TERTIARY EFFLUENT
                        A CURVE 1
                        • CURVE 2
                        O CURVE 3
               20
40
60
80
100
120
140
160
180
                                                   BED VOLUMES
            FIGURE 6.  AMMONIA BREAKTHROUGH CURVES FOR A 6 FT  CLINOPTILOLITE BED AT VARIOUS FLOW RATES

-------
The effect of bed depth at a flow of 4.8 gpm/ft^ is illustrated in
Figure 7.  Two 4.5 ft deep zeolite beds were run in series to provide
simultaneous data on 4.5 ft and 9 ft bed depths.  The average NH^-N
conceatration in 150 bed volumes of effluent from the first bed in
series (Curve 2, 4.5 ft bed depth) was 0.81 mg/1 at a flow rate of 8.4
bv/hr.  The average NHo-N concentration in the effluent from the second
zeolite bed (Curve 1, 9 ft total bed depth) was 0.35 mg/1 at a flow rate
of 4.2 bv/hr.  The average NH3~N concentration in the influent was 12
mg/1.

The effect of bed depth on ammonia breakthrough with two separate
columns at 9.7 bv/hr in each case is illustrated in Figure 8.  Curve
3 from Figure 6 for a 6 ft bed, and discussed previously, is repeated
and shown with data from a 3 ft bed.  In general, the shallow bed of
clinoptilolite was not as effective for ammonia removal as the deep bed
at the same bed volume flow rate.  The shallow bed has a lower flow
velocity which may lead to easier plugging of portions of the screen
or bed by lime or precipitated solids.  Plugging would cause poor
flow distribution and lower bed efficiency.

Two Column Semi-Countercurrent Operation

Several beds in series can be operated more effectively if a column is
removed from the influent end when it becomes loaded while simultaneously
adding a regenerated column at the effluent end.  This procedure moves
zeolite beds countercurrent to liquid flow.  Beds can be loaded nearer
to capacity with this procedure than with single column or parallel
feed multi-column operation.  The most highly loaded column is always
at the influent end backed up by one (if two in series) or more columns
having decreasing loadings and NH^-N concentrations at locations progressively
nearer the end o.f the series.  Removal of a column is not decided by applying
a breakthrough criterion to the column's own effluent but by breakthrough
at the end of the series.

The performance was evaluted for countercurrent operation of three columns
(two on stream while regenerating the third).  Performance data for six
runs with two columns in series are listed in Table 2 for operations at
Tahoe.  The average ammonia nitrogen concentration in the effluent from
the six runs was 0.43 mg/1, and the average influent volume processed
through each column was 250 column volumes.  The ion exchange columns
each contained 4.7 ft deep beds with 39 ft^ of 20 x 50 mesh clinoptilolite.
The average influent ammonia nitrogen for each run varied from 10.3 mg/1
to 16.1 mg/1, and the second column effluent varied between 0.38 mg/1 and
0.66 mg/1 ammonia nitrogen.  The low and high effluent values were obtained
with the low and high influent values, respectively.  Loading on the
first columns in series was terminated when the effluent from the second
columns reached 1-2 mg/1 ammonia nitrogen.  Typical breakthrough curves
for the first and second columns in series with Tahoe tertiary effluent
are illustrated in Figure 9 for an average influent ammonia nitrogen
concentration of 15.1 mg/1.  Ammonia loadings were increased from an
average of 57% to an average of 85% of equilibrium capacity by going from
single bed to series operation; however, the piping necessary for this is
more complicated.  Ammonia nitrogen removals averaged 97%-


                                 19

-------
2
OQ
            OPERATING CONDITIONS
            FLOW RATES:  (1) 4.2 bv/hr, (2) 8.4 bv/hr
            ZEOLITE GRAIN SIZE: 20x50MESH
            BED DEPTH: (1)9 FT (2) 4.5 FT
            BED VOLUME:  (1) 76 FT^, (2) 38 FT3
            AVERAGE INFLUENT NH3~N: 12 mg/l
            FEED: TAHOE  TERTIARY EFFLUENT
             o
                 20
40
60
80
100
120
140
160
180
                                              BED VOLUMES
        FIGURE J.  EFFECT OF BED DEPTH ON AMMONIA BREAKTHROUGH AT 4.8  gpm/ft  FLOW RATE

-------
CD   4
UJ
CO
                 OPERATING CONDITIONS
                 ZEOLITE GRAIN SIZE: 20x50MESH
                 BED VOLUMES: 3 FT DEPTH = 25 FT3, 6 FT DEPTH = 50 FT3
                 AVE.  INFLUENTNH3-N: 17
                 LOCATION:  TAHOE
                                                                        6 FT. DEPTH
                20
                        40
60
80
100
120
140
160
180
                                         BED VOLUMES
       FIGURE 8.   EFFECT OF BED DEPTH ON AMMONIA BREAKTHROUGH AT 9.7 bv/hr

-------
ho
to
                                                          TABLE 2


                              TAHOE PERFORMANCE DATA FOR SIX RUNS WITH TWO COLUMNS IN SERIES
Run No . ILoaded.
Column

1 A
2 C
3 B
4 A
5 C
6 B
Ave . Cone .
of NH3-N
in Product
mg/liter
0.325
0.42
0.38
0.43
0.66
0.44
Ave. Cone.
of NH3-N in
Influent
mg/liter
11.8
15.6
10.3
15.0
16.1
13.3
Column Vols .
Through Loaded
Column to 1.0
mg/1 Effluent
Breakthrough
290
168
311
229
215
306
Percent of
NH3-N Capacity
Used

91
62
90
83
81
102

-------
N3
U>
24

22

20

18

16



12

10

 8

 6

 4

 2
                                        INFLUENT
                                                         FIRST COLUMN
                                                           EFFLUENT
                                                                   SECOND COLUMN EFFLUENT
                         20
                    40
60
80       100
                                                         BED VOLUMES
120
140
160
180
200
                  FIGURE  9.  AMMONIA BREAKTHROUGH CURVES FOR 1ST AND 2ND COLUMNS IN SERIES WITH
                             TAHOE  TERTIARY EFFLUENT

-------
Performance data for 17 semi-countercurrent runs at Blue Plains with two
columns in series are listed in Table 3.  The average bed volumes processed
per run was 232 and the average NHg-N in the influent and effluent was
12 mg/1 and 1.4 mg/1, respectively.   An incomplete regeneration and high
feed pH in two cases caused a significant increase in the average effluent
NH3-N concentration.  Excluding runs 1, 5, 12, and 14, the average NH3-N
concentration is 0.93 mg/1 for an average removal 93%.  The average
bed volumes processed at Blue Plains was about 67% of the total available
capacity, which is less than that experienced at Tahoe.  It is believed
that the relatively high organic concentration in the clarified raw
sewage feed stream at Blue Plains was responsible in part at least.  The
differential pressure increased across the zeolite beds during operations
at Blue Plains as a result of biological growth in the beds.  The growth
was effectively removed during regeneration and backwashing.

The latter runs made at each site should have been closer to steady-state.
However, there did not appear to be  any definite trend in breakthrough
throughputs for specific columns at  Tahoe or Blue Plains.  It appears
that all semi-countercurrent loading runs were essentially at steady-state.
Zeolite Attrition

Accurate zeolite volume measurements were made at Tahoe in "A" column
only since no screen leaks developed in the column with resultant loss
of zeolite.  The total zeolite volume reduction in "A"  column through 15
cycles was 2.6% or 0.17% per cycle.   The average ion exchange capacity
of the zeolite in all columns at the start of operations was 1.64 milli-
equivalents per gram.  The average ion exchange capacity at the termination
of 15 runs per column was 1.63 milli-equivalents  per gram.
                                 24

-------
                                                          TABLE 3
                                           PERFORMANCE DATA FOR SEVENTEEN RUNS AT
                                           BLUE PLAINS WITH TWO COLUMNS IN SERIES

1 (a)
2
3
4
5 (b)
6
7
8
9
10
11
12 (c)
13
14 (c)
15
16
17
Ave . Flow
Rate
(gpm)
30
36
40
40
40
31
30
30
50
50
40
40
40
50
50
50
50
Ave. Cone, of
NH3-N in Influent
(mg/1)
10.0
14.0
11.0
12.3
11.6
12.5
12.2
11.5
11.4
10.6
11.8
10.3
11.7
13.6
13.3
13.4
12.7
Ave. Cone, of NH3~N
in 1st Col. Eff.
(mg/1)
2.4
4.6
6.0
6.9
3.2
6.8
5.8
1.9
4.7
5.9
4.6
4.6
5.6
3.0
5.9
5.9
6.0
Ave .
NIPj-N Cone.
of Product
(mg/1)
0.61
0.78
0.76
0.62
7.0
0.53
0.53
0.38
1.13
1.39
0.96
2.37
1.19
2.29
1.18
0.98
0.84
Bed Volumes
Treated By
Loaded Column
270
355
298
154
154
174
203
154
310
265
152
210
238
262
215
300
237
Percent of
NH3-N
Capacity Used
68
109
79
44
43
56
68
47
95
69
42
54
66
79
64
90
69
(a)  two freshly regenerated beds in series
(b)  second column was not completely regenerated
(c)  feed pH was 10 for 1-2 hours

-------
                         REGENERATION STUDIES
Normal Pilot Plant Regeneration

Normal regeneration during the pilot plant studies utilized a mixture of
NaCl and CaCl2 in a solution adjusted to a pH of about 11 using lime.
The total salt concentration was generally equivalent to 0.1 N_ NaCl
which will equilibrate to a 0.02 iJ NaCl, 0.08N_ CaCl2 solution upon
continued reuse with lime addition.  During regeneration the regenerant
was continuously recirculated through the zeolite bed and air stripping
column with lime addition before return to the bed.  Sodium chloride
is added to the regenerant because significant amounts of sodium ion
have been found to give longer service cycles and more rapid elutions
(see Figure 5 of Appendix C).  Make-up salt is added as needed to replace
that lost due to incomplete removal of regenerant following the regen-
eration cycle.  High pH favors NH3 production necessary for air stripping.
A higher salt solution (total normality about 2) was subsequently chosen
to assure effective ammonia elution by a batch recycle regeneration
method using 4 bed volumes of regenerant at pH 11.  Computations based
on equilibrium data indicate that ammonia elution is increased from 60%
to 88% by increasing the salt concentration of 4 bed volumes of regenerant
from 0.1 _N to 2.2 N_ at pH 11.  Further increases in the salt concentration,
in particular the Ca+2 concentration, will reduce the maximum pH that
can be attained by lime addition to values significantly less than 11.

The problems due to the precipitated solids formed during regeneration
with lime solutions were quite severe at Pomona when employing normal
continuous regenerant recycle.  The magnesium content of the Pomona feed
stream was approximately 20 times that of Tahoe.  Examination of a zeolite
bed after regeneration at Pomona disclosed the presence of large chunks of
white material which was largely composed of magnesium hydroxide.  This
material apparently filtered out on the retaining screens at the top
of the zeolite columns and periodically fell back into the bed when flow
reversals were used to reduce the pressure across the bed.  A photograph
of the chunks of white material on top of a bed of clinoptilolite is
shown in Figure 10.

Both high rate backwashing with tap water and treatment with dilute
acid were temporarily effective in restoring good performance with the
zeolite beds, as illustrated in Figures 11 and 12.  However, the use of
acid is expensive both with respect to the cost of the acid used and the
cost of the acid resistant piping and vessels required.  High rate back-
washing was continued for each run after that for Curve 2 in Figure 11,
but was not consistent in restoring good performance.  The basic problem
occurred during regeneration where a thorough elution was not always
obtained due to particulate matter blocking off portions of the bed.  Removal
of the particulate matter was deemed necessary for satisfactory performance.
The effect of clarifying the regenerant before recycling through the zeolite
bed is illustrated in Figure 13.  Clarification was accomplished with the
slightly inclined tube settlers in the filtration unit.
                                  27

-------
FIGURE 10.   PHOTOGRAPH OF WHITE MATERIAL ON TOP OF A
            BED OF CLINOPTILOLITE AT POMONA
                        28

-------
                                        INFLUENT FLOW:
                                        INFLUENTNH3-N:
                                        BED VOLUME:
                                        PRIOR BACKWASH RATE:
                                        BACKWASH:
                                        LOCATION:
                           (1)  AFTER LOW BACKWASH RATE
                                 (2)  AFTER HIGH BACKWASH RATE
      40GPM
      (1) 21 mg/J
      (1) 291 GAL
      (1) 20GPM
        (2)
        (2) 279 GAL
        (2) 90GPM
      TAP WATER, 2000 GAL
      POMONA
             20       40        60       80       100
                                      BED VOLUMES
120
140
160
180
FIGURE 11.  EFFECT  OF PURE WATER BACKWASH RATE ON SUBSEQUENT NH^N BREAKTHROUGH

-------
LO
O
                   1 -
                        INFLUENT FLOW RATE:  40GPM
                        INFLUENT NH3-N:     (1) 18 mg/£ (2) 22
                        BED VOLUME:         229 GAL
                        ACID WASH:         ACETATE BUFFERED NaCI-HCI AT
                        LOCATION:           POMONA
                     -    (1) BEFORE ACID WASH
                                                                        (2) AFTER AC ID WASH
                             20
40
60       80       100
        BED VOLUMES
120
140
160
                        FIGURE  12.   EFFECT  OF ACID WASH  ON  SUBSEQUENT NH -N BREAKTHROUGH

-------
  Lt
        5  ~
        4 -
        1   -
OPERATING CONDITIONS
FLOW RATES:  (1) 8.3 bv/hr (2) 8.5 bv/hr
AVE. INFLUENTNH3-N:  (1) 20 mg/l (2) 19 mg/l
ZEOLITE GRAIN SIZE:  20x50MESH
BED VOLUMES: (1)39 FT3 (2) 38 FT3
LOCATION: POMONA
                                             80       100
                                         BED VOLUMES
FIGURE 13.  AMMONIA BREAKTHROUGH CURVES  FOR COLUMNS  FOLLOWING REGENERATION WITH UN-
            CLARIFIED  (1) AND CLARIFIED  (2)  REGENERANT  WITH HIGH MAGNESIUM CONTENT

-------
Figure 13 shows significant improvement in regenerant performance
after clarification.  The combination of high rate water backwashing
with regenerant clarification should provide satisfactory regenerant
solids removal with high magnesium operations.

Pilot Plant Batch Recycle Regeneration

In order to minimize the volume of regenerant required to elute the
NH3-N from the zeolite beds, a batch regeneration technique was studied
at Tahoe.  Normal regenerant was recycled through the bed only, deferring
the air stripping operation.  This was done to minimize the liquid volume
to be stripped.  Less liquid volume means less heat input required to
prevent freezing and keep efficiency high during cold weather stripping
operation.

Contact with several recycle batches may be necessary, however, to
obtain good regeneration.  A two batch recycle regeneration could proceed
as follows.  In order to start the regeneration scheme, a first batch
of fresh regenerant could be recycled through a bed followed by a second
batch of fresh regenerant recycled through the same bed.  After this, the
second batch recycle used for one bed could be used for the first batch
recycle for the next bed.  Each second batch recycle would consist of
fresh or renovated regenerant.  Pilot plant data were collected in order
to set process specificatiors on a two batch recycle regeneration scheme.

Single batch recycle data show that the NH3-N concentration in recycled
regenerant increases rapidly from near zero to about 500 mg/1 in a few
hours with a zeolite bed loaded with an average of 2.24 g of NH3-N per
liter of bed.  This loading is equivalent to ammonia removed during
reduction of a 15 mg/1 NH3-N influent to a 1 mg/1 (average) effluent
using a 160 bed volume throughput.  Three elution curves are illustrated
in Figure 14 for this average bed loading using regenerant with a total
salt concentration of 0.1 N_.  Curve 1 shows the lowest NH3~N (450 mg/1)
concentration after 6 hours, which is believed to be the result of the
low pH  (10.8).  The NH^ concentration at 450 mg/1 NH3~N and pH 10.8 is
8.9 x 10-4-M compared with 4.0 x 10~4M NH^ at pH 11.2 and 500 mg/1 NH3-N,
and 2.1 x 10-"% NH^ at pH 11.5 and 520 mg/1 NH3~N.  The amount of ammonia
removed from the zeolite will, therefore, increase with pH (low solution
NH^ concentrations show low NlfJ zeolite adsorption).  Curve 2 shows a
slower rate of NH3-N elution than Curve 3, which is believed due to a
combination of the slower flow rate and lower temperature and pH.  Curve 3
shows that equilibrium was approached after 4.5 hours.  Curves 1 and 3
represent the recycle of 2.2 bed volumes, whereas Curve 2 represents 1.2
bed volumes.

Figure 15 illustrates a first and second batch recycle for a highly
loaded zeolite bed  (3.2 g/liter of bed) using regenerant with a total
salt concentration of 0.1 N.  The first batch was air stripped to 107
mg/1 NH3-N while recycling through both the zeolite bed and the stripping
column.  Regeneration was 75% complete at this point.  The NH3-N increased
by 150 mg/1 in the regenerant after 2 hours in the second batch recycle.
                                  32

-------
              en
              E
OJ
LO
     700

     600

     500

=r    400
n:
^
2    300
3
LJ_
*    200

     100

      0
                      0
                                                         (1)
OPERATING CONDITIONS:
FLOW RATE:
PH:
BED DEPTH:
REGENERANT VOLUME:
   (1)
                                                                   9.4bv/hr
                                                                    10.8
                                                                   4. OFT
                                              TEMPERATURE:
                                                I	i
2.2bv
  14°C
j	
   (2)
6.4bv/hr
  11.2
 6. OFT
1.2bv
 8°C
   i
  (3)
9.4bv/hr
  11.5
 4. OFT
2.2bv
 15°C
        5
                                                      TIME IN HOURS
             9
         10
    11
                                                                                     12
                                     FIGURE  14.  FIRST BATCH RECYCLE ELUTION  CURVES

-------
UJ
UJ
/ uu
600
500
400
300
200
100
n
FIRST BATCH ^^
RECYCLE /
A
/ OPERATING CONDITIONS:
*' FLOW RATE:
y
/ o pH:
Q^SECOND BATCH BED DEPTH:
/T RECYCLE TEMPERATURE:.
{ / BED LOADING, NH3-N:
~ / REGENERANT VOLUME:
/l l I 1 l 1 1


FIRST BATCH
6.4bv/hr
10.5-11.5
6. OFT
13 °C
3.2g/l
1.2bv
l i


SECOND BATCH
4.8bv/hr
11.4
6. OFT
19 °C
0.8g/l
1.2bv
i i
0
                                     4
40
11
12
                                           TIME IN HOURS
                      FIGURE  15.  FIRST AND  SECOND BATCH RECYCLE ELUTION CURVES

-------
The time required for the  second batch recycle  (2 hours) was less than
that  of the first batch  (4-6 hours) due to: l)  the time lag in reaching
the optimum pH at the beginning of the first batch recycle; and 2) the
lower temperature of the first batch recycle (9°C vs. 19°C).

The regenerant system was  temporarily altered at Blue Plains to permit
the recycle of 3.6 bed volumes of regenerant (iM CaCl2 and 0.2M NaCl at
pH ll).  The results of  this regenerant batch recycle are shown in Figure
16.  The first recycle removed 75.4% of the ammonia from the zeolite bed
and the second recycle removed 12.8% with the remainder accounted for by
loss of ammonia during a flush between the two  recycles.  The flush con-
sisted of air stripped first cycle regenerant which was pumped through
the bed to remove regenerant that could not be  drained after the first
recycle..  Essentially no regenerant could be drained from the column since
the regenerant storage vessel was on the same level with the ion exchange
vessel.  The flush was air stripped to reduce the NHo-N concentration to
10 mg/1.

In addition to collecting  elution data, theoretical calculations were
made.  Equilibrium data were used to compute the maximum ammonia elution
from clinoptilolite as a function of regenerant volume and pH.  The
results are given in Figure 17 for a pH range of 7 "to 11 using an equil-
ibrium regenerant solution at ratios of 2, 4 and 6 bed volumes of regenerant
to 1 bed volume of clinoptilolite.  The initial ammonia nitrogen loading
on the clinoptilolite was  0.12 equivalents per  liter or 1.7 grams per
liter.  The data in Figure 17 illustrates the importance of pH in removing
sorbed ammonia during regeneration.  The maximum elution values at pH 11
are higher than that shown for the first pilot plant recycle in Figure 16,
which is believed to be the result of: (l) not  including potassium salt
in the recycled regenerant of the pilot plant run (potassium would build
up naturally in extended recycle service), and  (2) not attaining full
equilibrium even though the pilot plant elution data indicates that a
plateau was reached.

By examining the pilot plant data,  a recommended regeneration scheme has
been devised.  For single  column operation, a regenerant of 0.2 M NaCl,
1 M CaCl2 and adjustment to pH 11.5 with lime is recommended for two
batch recycle operation.   Bed loadings will be lower in practice than used
for the pilot plant studies.  It is suggested that 4 bed volume recycle
batches be used at 10 bv/hr recycle rate with 2 hours for each recycle.
This should permit a change in concentration in the first batch recycle
regenerant from 100 to 600 mg/1 NH^-N (a change of 500 was experienced
experimentally on a fresh  batch) and in the second batch recycle regenerant
from 10 (from regenerant renovation) to 100 mg/1 NHo-N with almost complete
NHQ-N removal from the zeolite beds.

It should be emphasized that further practical  experience may indicate
changes in regeneration procedure specifications.  Calcium and sodium
concentrations were fixed  rather arbitrarily in the experimental studies
                                35

-------
    600
           NH3-N LOADING: 2.4  g/£  OF ZEOLITE

           FLOW RATE:  11.8 bv/hr  (6.5 gpm/FT2)
     400 U
CD
     200 I—
                                FIRST  RECYCLE
                  SECOND RECYCLE
 FIGURE 16.  REGENERANT BATCH RECYCLE WITH 3.6 BED VOLUMES OF
           1 M CaCl2-0.2 M NaCl AT pH 11
                          36

-------
   100
    80
    60
    40
    20
    0
      CONDITIONS:
.TEMPERATURE:   25°C
 EQUILIBRIUM SALT CONCENTRATION
      1M  CaCl
      0.2  M^ NaCl
      0.01M KC1
          REGENERANT VOLUME/
               ZEOLITE VOLUME:2,4,6
                  8
                            I
                    9
                    PH
10
11
FIGURE 17.  EFFECT OF REGENERANT VOLUME AND pH ON AMMONIA ELUTION
                          37

-------
and the regeneration procedure recommended above,  although thought to
be realistic and adequate,  may not be optimal.   Also,  the concentration
suggested for the regenerant need not be fixed  at  start-up.   The process
could be started with 2 N_ NaCl, for example,  and adjusted during operation.
This was actually done during the pilot study on electrochemical renovation
to be discussed later.
                                 38

-------
                          REGENERANT RECOVERY
Air Stripping of Regenerant

The spent regenerant containing ammonia was recovered for reuse by air
stripping in a 3.6 ft. diameter by 8 ft. column packed with 1 inch
polypropylene Intalox(R) saddles.  The regenerant was normally recycled
upflow through the zeolite bed at a flow rate of 4.8-7.1 gpm/ft^ until
the NH3-N approached a maximum concentration.  The regenerant was then
recycled through both the zeolite bed and the air stripper until the Nt^-N
was reduced to about 10 mg/1.  The liquid flow rate to the stripper was
normally 20 gpm with an air/liquid ratio of 150 cfm/gpm.  Ammonia removal
in the air stripper generally averaged about 40% at 25°C.  Calcium carbonate
scaling occurred on the polypropylene saddles, but did not interfere with
stripping efficiency for operating periods up to 65 days at each site.  The
calcium carbonate scale formed during the Tahoe and Pomona operations was
flaky and could be removed to a large degree by spraying with water.  The
scale formed during operations at Blue Plains was relatively hard and
required water fluidization of the packing to remove the scale.

The type of air stripper used in the mobile pilot plant is not recommended
for general plant use because of the energy wasted in blowing air through
the packing.  A modified cooling tower with low differential pressure
across the tower is recommended.

Electrochemical Renovation of Regenerant

The chemical destruction of ammonia in regenerant solutions from the
selective ion exchange process was investigated as an alternative
method to air stripping, since atmospheric disposal of ammonia may be
undesirable in some locations.  The chemical destruction of the ammonia
is accomplished by reaction with chlorine, which is generated electro-
lytically in the regenerant solution.  This process can be carried out
under neutral conditions and is not as prone to solids precipitation as
alkaline lime regeneration.  Regenerant solutions from the selective
ion exchange process are rich in NaCl and CaCl2  (plus MgCl2 when Mg+2 is
present in the feed stream to the clinoptilolite beds).  These salts
provide the chlorine that is produced at the anode of the electrolysis
cell.

The chemical reactions that take place in the electrolysis cell are
illustrated below using NaCl as an example:

               Cathode:  Na+ + e~ = Na                     (1)
                         2Na + H20 = 2NaOH + H2i           (2)

               Anode:    2 Cl - 2e~ = C12                  (3)
                         3C12 + 2 NH4C1=  N2 +  8HC1        (4)
                                  39

-------
The overall reaction for the destruction of ammonia with chlorine is
shown above.  Excess dissolved Cl2 exists as hypochlorite (HOC1).  The
hydrochloric acid produced by reaction (4) is partially neutralized
by the NaOH produced by reaction (2).   However,  an excess of hydrochloric
acid is produced and base must be added to the system to maintain a neutral
solution.  The moles  of base added should be equivalent to the moles  of
NH4C1 to be reacted.  The production of acid, in fact,  is a good indicator
that the reactions are taking place, and the break point is clearly
indicated by stabilization of the pH.

A laboratory model electrolysis cell was obtained for conducting lab-
oratory experiments.  The anode, which is the most vulnerable part of
the cell, is composed of a 5/16 inch diameter graphite  rod coated with
lead dioxide.  The lead dioxide coating is very  resistant to attack by
chlorine or oxychloro-acids.   Commercial anodes  made of this material are
used in the production of chlorate and perchlorate.  It is of interest
to note that ammonia impurity in the brine is destroyed early in the
production of sodium chlorate by electrolysis of brine.

Initial laboratory results with the electrolysis cell show that 5 g of
NH3-N was essentially destroyed in two hours and forty-five minutes
with the cell operating at 10 amps and 5.5 to 9  volts.   A simulated
regenerant solution (1.87 N_ CaCl2, 1.31 N_ MgCl2, 0.14 N NaCl and 0.01 N_ KC1)
containing the ammonia as NH^Cl was recirculated through the cell at
flow rates of 500 to 1000 ml/min.  The cell has  10 in2  of anode surface
area.  At an average of 7.3 volts and 10 amps, the electrical energy
required to destroy one gram of NH3-N is 40 watt  hours.   When related to
the treatment of 1000 gallons of wastewater containing  15 mg/1 NH3~N
(total 57 g), the energy consumption would be 2.3 KW hours.

Although major solids precipitation was avoided, a white material was
formed on the cathode during the above experiment.  Some of this material
was washed off the cathode and collected in the  regenerant container.
Subsequent analysis revealed this material to be a mixture of Ca(OH)2
and Mg(OH)2-  The increase in cell resistance, which required an increase
from 5.5 volts to 9 volts in order to maintain a current of 10 amps, was
due to this coating of mixed Ca(OH)2 and Mg(OH)2 on the cathode.  Calcium
and magnesium are plated on the cathode where they react with water to form
their respective hydroxies.  Due to the low solubility  of these hydroxides,
they tend to precipitate and collect on the surface of  the cathode.
Subsequent experiments with and without MgCl2 in the simulated regenerant
solutions indicate that the Mg(OH)2 increases the conductivity of the
coating but reduces its solubility in acid.  The effect of Mg+2 On the
resistance of the cell is illustrated in the attached Figure 18.

Turbulent flow promoted by baffling or other cell modifications is expected
to minimize the scale formation rate.   The effects of pH and flow rate on
the cell resistance were found to be insignificant.  The data obtained at
pH's of 4 and 5 and flow rates of 4 and 15 1/min are shown in Figure 19.
                                  40

-------
1 .2
1 .0
0.8
0.6
0.4
0.2
                      WITHOUT  MgCl
                                                         REGENERANT:
TEMPERATURE
FLOW RATE:
1 .87N_ CaCl2
0.14N. NaCl
O.OIN^ KC1
40°C
4000 ml/min
                                                                            -O—
                                                             WITH 0.05N_ MgCl2
              10        20         30         40        50
                                      TIME  (MINUTES)
                  FIGURE 18.  EFFECT OF Mg+2 ON CELL RESISTANCE
         60
    70
80

-------
-p-
            1 .0
            0.8
         UU
            0.4
         o:
            0.2
                         O pH5,  4  £/min
                         A pH4,  4  £/min
                         D pH4,  15  £/mii
                                                           REGENERANT:
                                   1 .87N_ CaCl
                                   0.14N, NaCl
                                   0.05N_ MgCl
                                   0.01N KC1
                                                           TEMPERATURE:  40°C
                           40
                      FIGURE 19.
80
200
                120       160
               TIME (MINUTES)

EFFECT OF H+ ACTIVITY AND FLOW RATE ON CELL RESISTANCE
240
280

-------
Preliminary pilot scale studies were conducted at the Blue Plains plant
to further evaluate electrochemical regenerant renovation.  Two 500 amp
electrolysis cells and a 2000 amp, 6 volt rectifier were installed near
the mobile pilot plant for ammonia removal, along with a 20 HP pump and
a 2500 gallon regenerant treatment tank (swimming pool).   Brine (NaCl)
was used as the regenerant in these pilot studies.  Use of a 2 M NaCl
brine was planned but some difficulty was encountered as discussed below
and the actual concentration was 0.9 M NaCl.  Regeneration of the
clinoptilolite beds in the mobile pilot plant was accomplished by pumping
brine from the regenerant storage tank (in the Recla-Mate SWB treatment
unit in the trailer) upflow through the zeolite beds to the regenerant
treatment tank.  When all of the brine was collected in the regenerant
treatment tank, recirculation of the brine through the electrolysis cells
was started.  Based on laboratory data, the two 500 amp cells are capable
of destroying about 150 grams of ammonia nitrogen per hour in chemically
pure solutions.  Chlorine is produced at the surface of the lead dioxide
anode in the cells where it reacts with the solution to produce hypochlorite
Chlorine is produced at the rate of 657 g per hour when the total current
applied to the cells is 1000 amps.

Since both the Recla-Mate SWB unit and the regenerant treatment tank each
holds only half of the required volume of regenerant, it was necessary
to put the regenerant through each bed twice.  Data on elution with neutral
regenerant is included in Appendix B.  Ammonia destruction was accomplished
after each transfer except for the second batch of the final run.  Ammonia
elution from the clinoptilolite beds did not appear to be as rapid as that
expected for a 2 M solution.  Although sufficient salt (2000 Ibs NaCl) was
added to the SWB unit to make a 2 H NaCl solution, subsequent analysis
of the regenerant showed that it contained only 0.9 moles per liter.  It
is believed that some concentrated brine was lost through the filter of
the SWB unit during the dissolution step.  Since the conductivity of
the solution in the electrolysis cells was satisfactory,  no significant
loss was suspected at the time.

Three zeolite beds were regenerated with the brine; however, only two
of the beds were loaded with ammonia.  The first bed was assumed to be
partially loaded after regeneration with a lime-salt solution, but was
subsequently found to contain very little ammonia as evidenced by the low
NH3-N concentrations in the brine during the first run.

The highest NH3~N levels were attained in the first batches of brine from
the second and third runs and were 248 mg/1 and 210 mg/1 for 1800 gal and
2100 gal, respectively.  The difference in regenerant volumes was due to
incomplete draining of the column during the second run.  Gassing in the
zeolite bed caused by release of nitrogen from the destruction of ammonia
was suspected as the cause of the incomplete draining, since a significant
amount of hypochlorite was present in the brine after the first run.
Gassing was also observed in the laboratory when a clinoptilolite bed
was eluted with brine containing a relatively high concentration of hypo-
chlorite.  The electrical energy consumed by the first batches from the
second and third runs was 5.67 x 10? coulombs and 4.60 x 10? coulombs,
                                  43

-------
respectively.  The amount of energy per gram of NH3~N was 33,600 coulombs
and 27,500 coulombs with a power consumption of 54 and 46 watt hours/g,
respectively.  The energy and power consumed in the second batch of brine
in the second run was 22,000 coulombs and 35 watt hours per gram, respectively.
The second batch contained 72 mg/1 NE^-N.  The electrolysis cells were
operated at 1000 amps and 5.8 to 6.0 volts for the most part.  No significant
increase in cell resistance was noted, but the differential pressure across
the cells increased with time as a result of scale formation.  The
difference in electrical energy consumption may be due to a difference
in the amount of organic matter in the regenerant, although this has
not been determined yet.  The zeolite beds were given a short backwash
to remove slime from the bed prior to regeneration and some variation in
the amount of this material remaining after backwash may have existed
between the two runs.  Clarified raw sewage was used to load the zeolite
beds at Blue Plains and this may have caused the slime.  The slime
problem will not be significant if the zeolite columns are operated
after carbon columns which sorb the organic nutrients causing the slime.

Breakpoint chlorination for the first batch of regenerant in Run 3
is illustrated in Figure 20.  The total NH^-N remaining in the brine
after 13 hours of treatment was 0.16 mg/1.  The nitrate-nitrogen present
in the brine was 8.0 mg/1.  The latter represents the total produced by
the two runs or a 1.7% conversion of NH3~N to N03~N.  No ammonia was
detectable by direct nesslerization at the breakpoint of each batch.
The Ca"1"^ increased from 1900 mg/1 in 1800 gal after the second regeneration
to 2700 mg/1 in 2100 gal after the third regeneration.  Lime was used
to neutralize the acid formed by the destruction of NH^Cl.

Ammonia leakage was relatively high after regeneration with the 0.9 M
NaCl.  The high leakage (1-3 mg/1 NH3-N) is attributed largely to high
pH in the zeolite beds during the initial part of the service cycle.  The
high pH was apparently caused by residual lime left in the system by
previous lime regenerations.  The service cycle times were 37 hours
and 34 hours (318 bed volumes and 292 bed volumes, respectively) on the
two loaded columns regenerated with electrolytically renovated brine.
                                  44

-------
  100
   80
 C\J
o
ct:
o
   60  —
   40  -
   20  -
1000 AMPS
6.0 VOLTS
30-35°C
6-
2100 GAL
210 mg/1
TOTAL CURRENT:
VOLTAGE:
TEMPERATURE:
pH:
REGENERANT VOLUME
                                                            INITIAL  NH3-N:
                                                                                       13
                                           TIME, HOURS

              FIGURE  20.  BREAKPOINT CHLORINATION OF  REGENERANT BATCH #1, RUN 3

-------
                            ACKNOWLEDGMENTS
The studies reported herein were conducted by personnel of the Pacific
Northwest Laboratories, otherwise known as Battelle-Northwest,  a division
of Battelle Memorial Institute.  Basil W. Mercer and Ronald G.  Arnett
served as Technical Director and Pilot Plant Engineer,  respectively.
The efforts and assistance of the following Battelle personnel contri-
buted to the successful completion of the project.   Pilot plant operations:
Neil Bonney, James A. Coates, Marvin J. Mason,  Richard  G. Parkhurst,
R. Gregory Swank and Robert G. Upchurch.  Bench scale and theoretical
studies: John G. Adams, David A. Cochran, Gaynor W.  Dawson, and R.  Jeff Serne,
Technical and administrative assistance: Lloyd L. Ames, Gordon L.  Gulp,
Douglas E. Olesen, Alan J, Shuckrow and C. Joseph Touhill.

Our sincere appreciation is extended to the following individuals outside
Battelle whose cooperation and assistance made this  work possible.
Mr. Russell L. Gulp of the South Tahoe Public Utility District,  South Lake
Tahoe, California; Mr. David R. Evans of Cornell, Rowland, Hayes,  and
Merryfield, Engineers and Planners, Corvallis,  Oregon;  Messrs.  Jerry C.
Wilson and Harlan E. Moyer of Glair A. Hill and Associates, Consulting
Engineers, Redding, California; Mr. Charles W.  Carry of the Sanitation
Districts of Los Angeles County, Los Angeles, California; Mr. John N.
English of the Environmental Protection Agency, Water Quality Office,
Pomona, California; Mr. Gerald Stern of the Environmental Protection
Agency, Water Quality Office, Los Angeles, California;  Mr. Dolloff F.
Bishop of the Environmental Protection Agency,  Water Quality Office,
Washington, D. C.; and Mr. Alan Cassel of the District  of Columbia
Sanitation District, Washington, D. C.

The support of the project by the Environmental Protection Agency,  Water
Quality Office and the assistance and suggestions provided by Dr.  Robert
B. Dean, WQO Project Officer, are gratefully acknowledged.  Also appreciated
are the technical and editorial suggestions made by  Dr. Harry Bostian of
the Environmental Protection Agency during review of the report.

-------
                                REFERENCES
1.  Slechta, A. F. and G. L. Gulp  "Water Reclamation Studies at the
    South Tahoe Public Utility District".  Journal Water Pollution
    Control Federation, p. 787 (1967).


2.  Johnson, W. K. and G. J. Schroepfer.   "Nitrogen Removal  by Nitrifi-
    cation and Denitrification".   Journal Water Pollution Control Federa-
    tion, p. 1015 (196^)-


3-  Ames, L. L.,  Jr.  "Zeolitic Removal of Ammonium Ions from Agricultural
    and Other Wastewaters".   Proceedings  of the Thirteenth Pacific North-
    west Industrial Waste Conference, Washington State University,  Pullman,
    Washington (April, 1967).


ik  Mercer, B. W.; Ames, L.  L.; Touhill,  C. J.; Van Slyke, W.  J.;  and
    Dean, R. B.  "Ammonia Removal from Secondary Effluents by Selective
    Ion Exchange".  Journal  Water Pollution Control Federation,  ^2, Part 2,
    R95, (1970).

5.  Glasstone, S.  "Textbook of Physical  Chemistry,"  Second Edition, New
    York.  D. Van Nostrand Company,  Inc.  19^6,  p.  956-59.

-------
                              APPENDIX A
                  SAMPLE CALCULATION OF AMMONIUM ION
                  LOADING USING ACTIVITY COEFFICIENTS
The experimentally measured selectivity coefficient is defined as
               K
                A
(B)   (A)a
   s    z

(A)a (B)b
   s    z
                                                  (A-l)
where
     (A),
(B)   =  normality of  cations  A and B in equilibrium solution
   S
     (A)z> (B)z = equivalent fractions of cations A and B on the zeolite

     a, b = the number of cations A and B represented in the chemical
            reaction for exchange of A and B.

A "thermodynamic"selectivity coefficient incorporating activity coefficients
can also be defined:
               'A
                  thermo
                              b  x_x b
                             Y   (B)
                                                               (A-2)
The y's are activity coefficients that correct for solution non-ideality
and the "thermodynamic" selectivity coefficient is therefore a constant
value for solutions having different concentrations of ions but the same
ratio of A to B.  It is assumed that corrections are not necessary for
ions adsorbed on the zeolite.  The invariance in the thermodynamic
coefficient serves as the basis for a procedure to correct experimental
values and calculate equilibrium zeolite loadings.

The experimental selectivity coefficients were determined in a reference
solution of 0.1 _N in cations.  The thermodynamic selectivity coefficient
can be expressed in terms of this reference solution:
                A
                  thermo
                               b /T,Nb  , , a
                               B (B)S  (A)Z
                    a /, \ a ,  -.b
                    A (A)S (B)z
                                              0.1H Cad,
                             / b
                                   ,1 N CaCl,
                                               K;
                                                 0.1 N. CaCl,
                                                                  (A-3)
                                  50

-------
Since the thermodynamic selectivity coefficient is independent of
reference solution, the above specific expression can be equated to
the general expression giving,
         (I
              A
                 0.1  N  CaCl,
               0.1 N CaCl,
                                   B  <»>*
Rearranging, the B ion loading can be expressed in terms of the A ion
loading
          (B)
(YB/Y*) do*
-D JTX O
b, a\
B A 0.1 N CaCl
Z
(A)!
.£.
a RB
s A o.i



N CaCl0
— 2
                                                                  (A-4)
Activity coefficients may be neglected in univalent-univalent exchange,
but are necessary in univalent-divalent exchange.  The activity coefficients
can be predicted using Debye-Huckel theory.  A sample calculation using
the above expression to predict equilibrium zeolite loading is shown next.

To calculate the ammonium ion loading on clinoptilolite, the fact that
the equivalent fractions of all the ions on the zeolite must sum to
one is used:
(Ca)
                       (Mg)
(A-5)
where (A)  represents the equivalent fraction of the cation exchange
capacity of the zeolite occupied by ion A.

From typical simulated secondary effluent (SSE) specifications in Table A-l
                
                       =  4.75
                               (K)
                                       =   0.317
                       =  2083
                                             (NVs
                                       =   1458
where (A)  = normality of ion A in solution.
         s
From Debye-Huckel theory   , the activity coefficient of ion i is:
                                    ,2,
         .(5)

           = -0.509

 I  =  1/2  ZM±  Z±2  ,   I is  ionic  strength
                                   51

-------
                               TABLE A-l




                   SIMULATED SECONDARY EFFLUENT, SSE
Cations	Concentration, mg/1	Normality




Na+                              130                         5.7  x 10~3




K+                                15                         3.8  x 10~4




NH*                               20                         1.2  x io~3




Ca+                               60                         3.0  x 10~3




Mg"1"1"                              25                         2.1  x 10~3
                                  52

-------
     M^ = concentration gram ions/liter of ion i



     Z. = charge on ion i



for SSE



     Na+  =  5.70 x 10~3



     K+   =   .38 x 10~3M



     NH4'  =  1.20 x 10~3M
       4
       i i               o

     Ca   =  1.50 x 10  M  (1/2 normality)

       i i               Q

     Mg   =  1.05 x 10~ M  (1/2 normality)


       -             -3
     Cl   = 12.4 x 10  M  (assuming  that Cl   is the  only negative  ion)



for SSE



     I = 0.0149



Using the Debye-Huckel relationship



     log1Q YCa++ = -0.509  (2)2 A/0.0149


           Yp -H- =  0.564
            (-13.



     Iog10 ^H4. =  -0.509  (I)2




           ^H4" =  0.868
              4


For ~0.1 N_ CaCl2 solution  used to determine  selectivity coefficients

(NH, in the equilibrium solution can be neglected),



     I = 1/2 [(0.05) (2)2  +  (0.1)  (I)2]



     I = 0.15


                              2
     Iog1() rCa   =  -0.509  (2)'



           Yo ++ =   0.162
     Iog10 YNHt =  -0.509  (I)2  A/0.
           YNH~I" =   0.635
              4
                                   53

-------
               SSE
                             = 0.747
                               0.41
                                              1.83
               0.1 N CaCl,
This factor of 1.83 is the correction factor between the SSE solution
and the 0.1 N solution used to determine the values of the selectivity
coefficient,
Since Mg   has the same charge as Ca  ,  we will assume that the correction
factor for K|&»  is also 1.83.  Univalent-univalent exchanges will not
require an activity correction.  Using equation A-4,
      Na

         0.1 N CaCl,
         0.1 N CaCl,
                     = 11,  (Na)z  = 4.75
                     = 0.33,   (K)  = 0.317   (NH,)
                                  Z   0.33       4
         0.1 N CaCl,
                     = 760 ,    (Ca) = (2083) (1.83)  (NH )'
                                   Z       760          4
         0.1 N CaCl,
                     = 2400,   (Mg)   = 1458    (1.83)  (NH.)
                                   Z    2400               4
Substituting in Equation A-5 ,
(NH4)z  +5.02
+1.11
                                        +0.96
                                                      +0.43  (NH )  = 1  ,
     2.39 (NH. )  +6.13 (NH. )  -1=0,
             4  z           4 z
     (NH )
        4 z
                 -2.39 + A/5.71 + 2452
                                           =  0.254
                         12.26

Since 1.81 meq/g is the total capacity of the zeolite

     (.254) (1.81)   =  0.46 meq/g

compared to 0.4 meq/g determined experimentally.
                                  54

-------
                              APPENDIX B
            PRELIMINARY DESIGN OF A 10 MGD AMMONIA REMOVAL
     PLANT UTILIZING ELECTROLYTIC RENOVATION OF SPENT REGENERANT
    design of a plant using electrolysis for removal of ammonia from
    spent regenerant must be considered preliminary at this time due to
   ack of pilot scale data needed to optimize the operating parameters.
    service flow rates are the same as that (6 bv/hr) used in South
   toe's design of an air stripping lime regeneration process in Appendix C;
   /ever, this flow rate is believed to be very conservative.  No problems
   poor flow distribution because of solids plugging associated with the
   2 of lime are anticipated.  This is because the electrolysis process
   .1 be operated at neutral conditions.  Laboratory data has indicated
   at flow rates up to 20 bv/hr can be used without significant leakage or
   emature breakthrough.

   e capital cost of this installation is minimized through the use of
  enforced concrete tanks for the ion exchange beds rather than closed
  :eel tanks as specified in South Tahoe's design.  Further, open concrete
  inks will be acceptable with respect to ammonia volatilization in the
  Lectrolysis process since very little ammonia will volatilize from the
  sutral regenerant solution.  Where lime solids are a problem, the steel
  ressure tanks noted in Appendix C offer an advantage of quick removal
  nd cleaning of distribution screens.  Fouling of the gravel underlayer
  f an open concrete tank would pose a serious problem of cleaning.

 he ion exchange units are patterned after those used for water softening
 .t the LaVerne Filtration Plant of the Metropolitan Water District of
 iouthern California.  The LaVerne units have been operated successfully
 )ver a period of thirty years for softening Colorado River water.  The
 Largest ion exchange units presently used in the LaVerne Plant have a
 zross section of 1590 square feet.  The ion exchange beds in this design
 nave a cross section of 800 square feet.  This ammonia removal process
 employs  four zeolite beds each containing 3200 cu ft of 20 x 50 mesh
 clinoptilolite.  Three beds will be in service at any given time while
 the fourth bed will be undergoing regeneration.  The zeolite beds will
be operated in parallel to 150 bed volumes each before removal from service
 for regeneration.  The service flow direction will be downflow and regen-
 eration will be accomplished upflow.  The relatively high density of the
wet clinoptilolite granules (1.7 g/cm^) will prevent localized fluidization
 or channeling during the upflow regeneration.  The design specifies 15
volumes of neutral regenerant, which contains two equivalents per liter of
mixed calcium, sodium, magnesium and potassium chlorides, for eluting the
ammonia from the beds at 23°C.  Laboratory elution data for a similar
 solution are given in Figure B-l and shows almost 90% elution after 15
volumes of regenerant throughput.  The evolution of heat during the
                                  55

-------
electrolysis step will increase the temperature of the regenerant,  which
is expected to increase the ammonium ion elution rate.  However,  no high
temperature elution data are available to confirm a significant reduction
in regenerant volume or regeneration time.

The regeneration step will require about 7.5 hours at 2 bv/hr.   Regenerant
will be pumped from the regenerant storage tank through the bed to  the
regenerant processing tank.  At the end of the regeneration cycle,  a
rinse step will be initiated to push the remaining regenerant out of the
zeolite voids to the regenerant processing tank.  The regenerant in
the processing tank will be pumped through a bank of electrolysis cells
which generate chlorine for destruction of the ammonia.  A flow diagram
of the regeneration processing step is given in Figure B-2.  A total of
530 cells, operating at about 6 volts and 500 amps, will be employed in
the electrolysis of the spent regenerant.  A lime slurry will be fed to
the cell effluents to maintain a neutral pH.  The regenerant will be pumped
through an enclosed tank (50,000 gal) to capture the hydrogen evolved
in the process.  The hydrogen is vented to the atmosphere or burned.
Approximately 7 cu ft of hydrogen gas will be generated from the destruction
of ammonia in 1000 gallons of wastewater at an NH3-N concentration  of
15 mg/1.  A 10 MGD plant will therefore be producing about 70,000 cu ft
of hydrogen per day.  The cost of recovering the hydrogen, including
scrubbing to remove the nitrogen trichloride, is more than the thermal
value of the hydrogen.

Figure B-3 illustrates the design of the reinforced concrete tanks  for
the zeolite beds.  The beds are contained in tanks measuring 40 ft  in
length, 20 feet in width, and 8.25 ft in depth.  The zeolite beds are
4 ft deep and are supported on 12 in of 4 layers of graded gravel.   The
total height of 8.25 ft allows for backwash and the distrbution system.
The distribution system over the beds for regenerant draw-off and
service feed consists of a trough running down the middle of the tank
lengthwise with connecting troughs with overflow weirs running laterally,
spaced 4 feet apart.  The distribution system under the beds consists of
the perforated concrete units of the type employed at the LaVerne plant.

Summaries of costs for a 10 MGD plant for treating tertiary effluent
and using electrochemical renovation of the regenerant are shown in
Tables B-l and B-2.  The estimates are patterned after those used by
South Tahoe in Appendix C except where electrochemical renovation or the
modifications discussed above require changes.  One exception is that
a flat 46% of capital is used to estimate auxiliaries, contingenices
and engineering design.  This is roughly equivalent to similar expenses
which are itemized in Appendix C.  Less make-up clinoptilolite is
required than in the design in Appendix C because neutral operation
will eliminate solids precipitation and the need for backwashing with
the accompanying zeolite loss.  Electrical energy for electrolysis  was
assumed to be 50 watt hours/g NH3-N.  The costs for lime and NaCl are
the same as for the South Tahoe design.  Although the chemistry is different,
the net amount of lime required for neutralization is the same.  Make-up
NaCl is required to compensate for losses; there is no net consumption by the
chemical reactions  in either process.
                                  56

-------
   1 .0
 o
X
                              8     10
                               COLUMN
               12    14
            VOLUMES
18    20
22
             FIGURE B-l.
ELUTION OF HECTOR CLINOPTILOLITE,  30 g,
20-50 MESH, LOADED WITH 1. 2N_ NH/jCL + 0.83 N_
KC1, XQ = 37.3 MEQ NHj/30 g COLUMN.   SEVEN
COLUMN VOLUMES/HR ELUTION RATE.   ELUTING
SOLUTION CONTAINED 0.1425 N NaCl + 0.0095 N_
KC1 + 1.8747 N_ CaCl2 + 1.3122 N^ MgCl2-
X/X0 = FRACTION ELUTED.
                                     57

-------
                      H0 DISPOSAL
Ln
OO
REGENERANT
PROCESSING
    TANK
REGENERANT
 STORAGE
   TANK
                                 ELECTROLYSIS
                                    CELLS
              RECTIFIER
                             FIGURE B-2.  REGENERANT PROCESSING FLOWSHEET

-------
      FEED
      INLET'
                     ON-OFF  VALVE
                                                FLOW  CONTROL  VALVE
      ON-OFF VALVE
 SPENT REGENERANT
               GRAVEL
         ON-OFF VALVE
REGENERANT BRINE  INLET
                       -C&J-
REGENERANT DISTRIBUTOR
         HEAD


     ON-OFF VALVE
                                                             PRODUCT  WATER OUTLET
                       FLOW CONTROL VALVE
            FIGURE B-3.  TYPICAL VALVE ARRANGEMENT FOR ION EXCHANGE TANK

-------
                               TABLE B-l

       PRELIMINARY CAPITAL COSTS - ELECTROLYSIS PROCESS - 10 MGD
             Description

Electrolysis unit complete with cells,
  rectifier, piping and bus bars with
  20% extra cells

Ion exchange beds with distribution
  system

Regenerant processing and storage
  tanks — 500,000 gallon

Hydrogen recovery tank

Piping

Instrumentation

Valves

Regenerant processing pumps—
  15,000 gpm

Product water pumps—4,000 gpm

Regenerant-backwash pumps—6,000 gpm

Zeolite
Plus 46% auxiliary, contingencies and
  engineering design
Quantity

636 cells
                                                             Total Cost
$  420,000
                    48,000
                    96,000
1
-
-
30
3
3
3
12,400 cu ft
Equipment Total

28,000
139,000
79,000
77,000
17,000
7,000
9,000
124,000
$1,044,000
480,000
                                          Total Capital Cost$l,524,000
                                  60

-------
                         TABLE B-2




PRELIMINARY ESTIMATE OF TOTAL COST FOR ELECTROLYSIS PROCESS







                                                Cost/MG




    Lime                                        $  6.50




    Make-up Sodium Chloride                        6.90




    Make-up Clinoptilolite                         0.20




    Chlorine                                       6.40




    Electricity                                   42.80




    Anode Replacement (2 yr life)                  4.40




    Operational Labor                             14.00




    Maintenance, Material and Labor                9.20




                      Total Operating Cost        90.40




    Capital Amortization, 6% for 20 yr            36.40




                      Total Cost                $126.80
                            61

-------
                             APPENDIX C
        ENGINEERING DESIGN OF A 7.5 MGD AMMONIA REMOVAL PLANT
      UTILIZING AIR STRIPPING FOR RECOVERY OF SPENT REGENERANT
This appendix presents an engineering design report prepared by the
South Tahoe Public Utility District, South Lake Tahoe, California.
Experimental data used in the design, and discussed in preceding sections,
were obtained when Battelle's mobile pilot plant was located at South
Lake Tahoe.  This design was for a plant utilizing air stripping to
remove ammonia from the clinoptilolite regenerant.  The report is
appended here to combine designs with alternate approaches to regenerant
recovery in a single publication.

The Environmental Protection Agency (EPA) should be substituted for the
Federal Water Quality Administration (FWQA) in the following report.
                                  62

-------
                    PHASE I  ENGINEERING DESIGN REPORT

             SUPPLEMENTING AMMONIA STRIPPING WITH FURTHER
              NITROGEN REMOVAL BY SELECTIVE ION EXCHANGE
                       AND BREAKPOINT CHLORINATION
                                      by
         Jem- C. Wilson                 and                 David R. Evans
     Clair A. Hill & Associates                      Cornell, Howland, Hayes & Merryfield
       Consulting Engineers                               Engineers & Planners
    Redding, California  96001                            Corvallis, Oregon 97330
        Project Director:                                 Technical Consultant:
     Russell L. Gulp, Manager                               Harlan E. Moyer
 South Tahoe Public Utility District                        Clair A. Hill & Associates
South Lake Tahoe, California  95705                         Consulting Engineers
                                                     Redding, California  96001
                                     for the

                 FEDERAL WATER QUALITY ADMINISTRATION
                              Program #17010EEZ
                              Contract #14-12-561
                        FWQA Project Officer, Dr. R. B. Dean
                   Advanced Waste Treatment Research Laboratory
                                Cincinnati, Ohio
                                   April, 1970
                               Project No. L-145.98
                                       63-

-------
                                 ABSTRACT
Pilot  plant  investigations of the efficiency of nitrogen removal from  a  tertiary
treated sewage effluent were conducted at the South Tahoe Public Utility District.
The nitrogen removal process utilized ion exchange and employed a natural zeolite,
clinoptilolite, which is  selective of  ammonium  ions  in  the  presence of sodium,
magnesium, and calcium  ions. Regeneration of  the exhausted clinoptilolite is
accomplished with solutions or slurries containing lime. Lime provides hydroxyl ions
which react with the ammonia ions to yield an alkaline aqueous ammonia solution.
The ammonia solution is processed through a heated air stripping tower  to remove
the ammonia  which is exhausted harmlessly  to  the atmosphere. The regenerant
solution  is  not  discarded  and  the  process  generates no liquid  wastes.  Ammonia
removals as high as 99% can be obtained using this process.

The  pilot plant investigation provided the design criteria on which a preliminary
design of a  IVz mgd plant is based. The plant design provides a system utilizing 12
exchange beds, nine of which are in  service at all times, and three of which are in a
regenerant cycle. Each bed would  be  12 feet in diameter and have an effective
clinoptilolite depth of 8 feet. The flow through the bed would be 6 bed volumes per
hour or 680 gpm.

The construction and operating costs of the 7/2 mgd plant are estimated. Based on
current costs in  the Lake Tahoe region, the process is estimated  to cost $84.95 per
million gallons to operate, and capital costs amortized at 6% interest for 20 years are
estimated to be $63.10 per million gallons.

This report was submitted in  fulfillment  of  Contract  14-12-561 (17010 EEZ)
between the Federal Water Quality  Administration and the South Tahoe Public
Utility District.
Key Words:  Nitrogen  Removal, Ion Exchange, Clinoptilolite, Ammonia Stripping,
             Tertiary Treatment Costs.
                                      65

-------
                         TABLE OF CONTENTS

       SECTION                                                  PAGE

INTRODUCTION                                                   71
PROPOSED PROCESS AND DESIGN CRITERIA
       Process Description                                           75
       Breakpoint Chlorination                                       78
       Design Criteria                                               79
PILOT PLANT STUDIES
       Service Cycle                                                 81
       Elution Cycle                                                84
       Ammonia Stripping Cycle                                      88
       Temperature Requirements for Elution & Air Stripping              91
THE PROPOSED PLANT
       Service Cycle                                                 93
       Ion Exchange Beds                                           93
       Clinoptilolite Transfer Tank                                    93
       Regenerant Cycle                                             94
       Elutrient Storage Tanks                                        94
       Lime Storage & Feeders                                        95
       Sodium Chloride Storage & Brine Feeder                         95
       Lime and Salt Mixing Basin                                     95
       Ammonia Stripping Tower & Recycle Basin                       96
       Process Controls                                              96
       Heating of Elutrient and Stripping Tower Air                      98
       Sludge Collection                                             98
FINANCIAL REQUIREMENTS
       Construction Cost  Estimates                                   101
       Incidental Cost Estimates                                      101
       Operating Cost Estimates                                      101
      Total Project Cost                                            102
REQUESTED GRANT PROGRAM
       General                                                     105
       Proposed Schedule                                           1°6
       Project Grant Costs                                          107
                                 67

-------
                 LIST OF TABLES AND FIGURES
TABLE OR
FIGURE NO                 TITLE                      PAGE

TABLE A     TYPICAL CARBON COLUMN EFFLUENT
            QUALITY BEFORE CHLORINATION               76

TABLE B     PROPOSED DESIGN CRITERIA                   80

FIGURE 1     AMMONIA BREAKTHROUGH CURVES
            FOR A 6 ft CLINOPTILOLITE BED
            AT VARIOUS FLOW RATES                      82

FIGURE 2     AMMONIA BREAKTHROUGH CURVES
            FOR TWO 4.5 ft CLINOPTILOLITE
            BEDS IN SERIES                              83

FIGURES     FIRST BATCH RECYCLE ELUTION CURVES         85

FIGURE 4     FIRST AND SECOND BATCH RECYCLE
            ELUTION CURVE                             86

FIGURE 5     EFFECT OF SALT ADDITION ON NH3
            ELUTION DURING BATCH RECYCLE              87

FIGURE 6     PERCENT AMMONIA REMOVAL VS CUBIC FEET
            OF AIR PER GALLON WASTEWATER TREATED
            FOR VARIOUS DEPTHS OF PACKING              8 9

FIGURE 7     PERCENT AMMONIA REMOVAL VS SURFACE
            LOADING RATE FOR VARIOUS DEPTHS
            OF PACKING                                90

TABLE C     ESTIMATED CAPITAL COSTS                    103

TABLE D     ESTIMATED OPERATION COSTS                 104
                           68

-------
                      LIST OF DRAWINGS

DWG NO      (Drawings are bound at end of the report)

   0         VICINITY MAP & LOCATIONS PLAN
   1         TOTAL PLANT FLOW DIAGRAM
   2         PROCESS FLOW DIAGRAM
   3         MECHANICAL PLANS
   4         SECTIONS & DETAILS
   5         SECTIONS & DETAILS
                             69

-------
                              INTRODUCTION

The  potential benefits of removing nitrogen from wastewaters are well known and
will not be recited here in detail. The principal benefits from nitrogen removal to a
low residual include restriction of algal growths, and elimination of the toxic effects
of ammonia nitrogen  on fish and aquatic life.  Ammonia removal also enhances the
efficacy of chlorination in disinfection of wastewaters.

Today,  advanced wastewater treatment processes are developed  to the extent that
practical,  reliable, and plant-proven methods  are available to produce  reclaimed
water of such high quality that it may be used for any desired purpose.

The  costs are reasonable  too, with two notable  exceptions, the costs for nitrogen
removal and for dewatering  of sewage-chemical sludge mixtures. The latter problem
can  be  avoided by separate settling and  handling of sewage sludge and  chemical
sludge in those situations where the mixture is too expensive to dewater. Also, it is
possible that methods may be developed to cut the cost for handling difficult sludge
mixtures.

Unfortunately, there does not appear to be in the offing a solution to the high cost
of nitrogen  removal.  Ammonia stripping  is by far the cheapest means of nitrogen
removal which has, at  this  time, a high degree of reliability and  ease of control.
However,  ammonia stripping is subject to considerable loss of efficiency at water
and air temperatures near freezing, and it is not practical to operate  the process at all
at air temperatures below freezing.

Deposition of scale on stripping tower packing is a problem at present, but it appears
probable  that  this problem  can be solved.  Assuming  solution  of the  calcium
carbonate deposition problem, which appears likely, then ammonia  stripping may be
a good method for nitrogen removal in warm climates. It could be supplemented by
breakpoint  chlorination where  required  to remove residual ammonia  following
stripping.

In cold  climates it is  undoubtedly still economical to use  ammonia stripping at air
temperatures above  freezing, provided it can be supplemented  at temperatures
slightly  above  freezing and  supplanted entirely  by another method  of nitrogen
                                    71

-------
removal at air temperatures below freezing. This project was undertaken with this
approach in mind. The existing ammonia stripping tower was to be supplemented or
supplanted, according to air temperatures, by the selective ion exchange process for
the removal of ammonia nitrogen from wastewater as developed to the pilot plant
stage by Battelle-Northwest under contract to FWQA. The process employs a natural
zeolite, clinoptilolite,  which  is selective of ammonium ions in the  presence of
sodium, magnesium,  and calcium ions.  Regeneration of the exhausted clinoptilolite
is  accomplished  with solutions or slurries containing lime. Lime provides hydroxyl
ions which react with the  ammonium  ions  to yield an alkaline aqueous ammonia
solution. This ammonia solution is processed through a heated air stripping tower to
remove the ammonia which is exhausted harmlessly to the atmosphere. The spent
regenerant is then fortified with more lime and recycled to the zeolite bed to remove
more  ammonia.  Since the regenerant is  not discarded, the process generates little
liquid wastes. Ammonia removals as high as 99% can be obtained using this process.
The last 0.5 to  1.0  mg/1  of  ammonia  nitrogen can then be removed by  use of
breakpoint chlorination. Battelle-Northwest  has constructed a 100,000 gpd mobile
demonstration plant  for further study of this process. They very kindly conducted
tests over a period of several months last year at the Tahoe plant. The results of their
pilot plant  work on the Tahoe reclaimed water established the design criteria for the
full-scale plant on which this report is based.

Phase I of the contract with FWQA consists of the preparation of an engineering
design report. Phase II is the construction of full-scale plant facilities using selective
ion exchange for supplemental  nitrogen removal. Phase  III covers collection,
analysis, and reporting of data on the efficiency and cost of nitrogen removal by ion
exchange, ammonia stripping, and breakpoint chlorination, for a 2-year operational
period.

This report completes Phase I  of the  project, and gives  a basis for consideration of
proceeding with  Phase  II.  It  presents  the design criteria  developed by Battelle-
 Northwest in their pilot plant work as  applied to a preliminary design of a full-scale
plant  for  ammonia  removal  by  selective  ion  exchange.  The description of the
proposed plant is illustrated by drawings showing the general layout and design of
the facilities.  Cost estimates  are  also presented.  The proposed  plant  has been
designed  for a  nominal  capacity of 7H mgd,  which corresponds  to that  of the
existing advanced wastewater treatment plant. The decision to build a T^-mgd plant
addition is  based upon several  important considerations. First, it has been observed
                                     72

-------
that most of the great number of visitors who tour the plant and export facilities, as
well as local residents, judge the accomplishments of the plant almost solely on the
quality  of the  final  effluent as represented by the appearance of the Indian Creek
Reservoir. If only  part of the plant flow is treated, then  the quality of the reclaimed
water as produced by the plant does not truly reflect the process capabilities. This is
not just an idea,  it is a fact which has already been  driven home as a result of
experience with the  ammonia stripping tower which has a capacity of only one-half
that of  the rest of the plant. This means even during low flow seasons, that part of
the plant flow must be bypassed during maximum hourly flows. Test data can be
gathered  under these  conditions, but the  value  of  plant  scale demonstration is
completely  lost,  or even  becomes negative,  so far  as visitor  impressions are
concerned. We are of the firm opinion that a successful plant scale  demonstration
absolutely requires that the capacity  of all facilities be built to full 7Vi-mgd capacity.
There is more than visitor  impressions  involved. Indian Creek Reservoir is being
intensively studied so  far as algal  growths are  concerned.  Since  the reservoir is
drained down to about one-third full capacity each summer for irrigation purposes,
it  is  possible  to  test  under  natural conditions  the effects of nitrogen removal.
Actually, phosphorus reductions to a residual of about 0.1 mg/1 have  given excellent
control  of algal growths in the reservoir.  Against this background of field  data,
further possible benefits from nitrogen removal can be evaluated.
                                      73

-------
                PROPOSED PROCESS AND DESIGN CRITERIA

Process Description

The selective ion exchange process developed  by Battelle-Northwest11'  for removal
of ammonia nitrogen from wastewater is the basis for a proposed full-scale plant at
the South Tahoe Water Reclamation Plant.

The  process  employs a  natural  zeolite, clinoptilolite,  which is  selective  for
ammonium ions in the presence of sodium, magnesium, and calcium ions.'2' A high
pH lime solution  containing NaCl  and CaCl2 is used to regenerate the exhausted
clinoptilolite.  The solution provides  both ions  for exchange with  the  ammonium
ions  and  hydroxyl ions to  yield an alkaline  aqueous ammonia  solution. The
following equation approximates this reaction:
          2NH4+1R-! + Ca(OH)2 — Ca+2R2-! + 2NH3 + 2H2O
The presence  of a significant amount of sodium on the clinoptilolite  lengthens the
service cycle and shortens the elution cycle.

After the  ammonium ion is  eluted  from  the clinoptilolite,  the high pH alkaline
aqueous ammonia solution  is  passed  through  an air stripping tower where the
ammonia is stripped from the  regenerate or  elutrient. Make-up lime and salt  are
added to replace the exchanged calcium and sodium.

At  the South  Tahoe Water Reclamation Plant, the proposed clinoptilolite exchange
process would be added to the existing plant following the carbon adsorption step as
shown on Drawing No.  1. The quality of the water, see  Table A,  is such  as to
preclude organic fouling of the ion exchange beds.

A schematic diagram of the proposed ion exchange beds, lime elutrient system, and
ammonia air stripping system is shown on Drawing  No. 2. For design flows, nine
beds would be in service and three beds in regeneration.

The direction of flow for the beds in service would  be downflow. All beds would
operate in parallel.
   (1) Developed by Battelle Memorial Institute, Pacific Northwest Laboratories Division, under contract with
the Federal Water Pollution Control Administration.
   (2) Battelle-Northwest, "Research Report, Ammonia Removal from Agricultural Runoff and Secondary
Effluents by Selective Ion Exchange to the FWPCA," December 1968, 56 p.
                                          75

-------
                                Table A

                  Typical Carbon Column Effluent Quality
                           Before Chlorination
BOD (mg/1)                                               1  2
COD(mg/l)                                              5   15
Turbidity (JU)                                           0.3 - 0.8
MBAS(mg/l)                                            0.1-0.2
pH                                                     7.0-8.0
Coliforms (mpn/ 100ml)                                  less than 50
Nitrogen (mg/l-N)
    Ammonia                                            4-20
    Nitrite                                             0.1 - 0.6
    Nitrate                                               1 - 2
Suspended Solids (mg/1)                                      -0-
Total Dissolved Solids (mg/1)                               250 - 350
Phosphorus (mg/1 PO4-P)                                 0.05 - 0.15
Alkalinity (mg/1 CaCO3)                                  150 - 250
Hardness (mg/1  CaCO3)                                    50-175
Chlorides (mg/1)                                            25
Sulfates (mg/1)                                              25
Carbon Fines                                          some present
                                  76

-------
When a given volume of carbon column effluent has passed through a set of three
beds, for example, beds 1, 2, and  3, this set of beds would  be taken off line for
regeneration.  At this  time, from a previous regeneration, elutrient tank A  would
contain elutrient water with a very high ammonia content (say 600 mg/1); tank B
would contain elutrient water with a low ammonia content (say 100 mg/1); and tank
C would contain ammonia-free elutrient water (say 10 mg/1). The contents of tank A
would be  air stripped during the regeneration of exchange beds 1,  2, and 3. The
regeneration would proceed as follows:

     1.   Exchange beds 1,2, and 3 would be drained to the final effluent.

     2.   Low ammonia content elutrient water from tank B  (100 mg/1) would be
recirculated upflow through the three exchange beds and back through tank B to the
exchange  beds until  the  concentration of  ammonia  in the elutrient  began to
approach a maximum value (say 600 mg/1). Throughout the recirculation, make-up
rime and salt would be added. A pH of about 11.5 would be maintained.

     3.   After an allotted time (long enough for elutrient from tank B to approach
a maximum ammonia concentration, the elutrient would be changed to recirculation
to and from tank C through beds 1, 2, and 3. Tank C with its ammonia-free elutrient
water would be recirculated for an allotted time (long enough for  elutrient from
tank C to  reach about 100 mg/1). At this stage of the elution, the small amount of
ammonia left on  the  zeolite would be  distributed uniformly throughout the bed.
Tank A with  ammonia-free water (10 mg/1  NH3,  water  stripped during the
regeneration of beds  1,  2, 3) would be pumped once  upflow through the bed to
further polish the lower portion of the bed and prevent leakage of ammonia during
the downflow service cycle.

The elutrient in tank B (600 mg/1  NH3) would be held for air stripping during the
regeneration of the next set (say  beds  4, 5, and 6) of ion exchange beds. Tank C
with  100 mg/1  elution water would become the lead tank for this next set of ion
exchange beds. Tank A with ammonia-free elution  water (10 mg/1   NH3,  water
stripped during the regeneration of beds 1, 2, 3) would be used as the polishing tank
for beds 4, 5, and 6.

     4.   Once the elution of beds 1, 2, and 3 was completed, the three beds would
be drained back to tank A.
                                      77

-------
     5.   Beds 1, 2, and 3 would then be filled slowly (from the bottom to remove
trapped air) with product water from the other nine beds in service.

     6.   After the beds were filled with product water, more product water would
be pumped at a high rate through beds 1, 2, and 3 in sequence. The backwash water
would  be routed through the sludge line to  the floe basin, which is located just
ahead of the chemical clarifier in the existing plant. (See Drawing No. 3)

     7.   After backwashing was completed,  ion exchange beds 1, 2, and 3 would
be placed in service and beds 4, 5, and 6 would be taken offline for regeneration.

Ammonia in the elutrient solution would be removed by air stripping at a pH of
about 11.5. In the preceding example, during the regeneration of beds 1, 2, and 3,
the very high ammonia content (600 mg/1) in the elutrient solution of tank A was to
be air stripped. The following procedure would be used:

     1.   The  contents of tank A would pass through the tower down  into the
recycle basin below the tower.

     2.   The contents of the recycle basin would then be pumped back up through
the tower once again. This time, however, the effluent from the tower would flow
back to tank A.

     3.   The contents of tank A would now contain about 10 mg/1 of ammonia,
and would be ready  to serve  as the polishing volume during the regeneration of ion
exchange beds 4, 5, and 6;

Breakpoint Chlorination

In order  to remove  the last  0.5   1.0 mg/1 NH3-N remaining after treatment with
clinoptilolite, breakpoint chlorination would  be accomplished just prior to pumping
the reclaimed water to Luther Pass. No new equipment is needed for this purpose, as
the existing chlorinators are adequate.
                                   78

-------
Design Criteria

Phase I of the District's research contract with the FWQA includes the collection of
pilot plant  data using the Battelle-Northwest mobile pilot plant and carbon column
effluent from the reclamation plant. The data are used in preparing this report.

A  summary of the design criteria based on the pilot work accomplished September
through December 1969 is listed in Table B.
                                       79

-------
                               TABLE B

         PROPOSED DESIGN CRITERIA - AMMONIA REMOVAL BY
      SELECTIVE ION EXCHANGE AND BREAKPOINT CHLORINATION
          AT THE SOUTH TAHOE WATER RECLAMATION PLANT
Capacity                                                    7.5 mgd

Ammonia Concentration
     Influent                                            15-20 mg/1 NH3-N
     Ion Exchange Effluent                               0.5-1.0 mg/1 NH3-N
     Chlorinated Effluent                                     0 mg/1 NH3-N

Exchange Beds
     Length of Service Cycle                                    150 bv W
       Service Cycle Loading                                   6 bv/hour
     Bed Depth                                                  8 ft
     Bed Diameter                                              12 ft

Exchange Bed Regeneration
     Quantity of Elutrient                                        8 bv
     Elution Rate                                               10 bv/hr
     Elutrient (Initial - Ca build-up during service)
       Calcium Oxide                                          500 mg/1
       Sodium Chloride                                          2.0 N
       pH                                                     H.5

Ammonia Stripping Tower
     Capacity                                                  300 gpm
     Air/Water Ratio                                         300 cfm/gpm
     Hydraulic Loading                                        3.5 gpm/ft2
     Packing Height                                             24 ft
     Efficiency per Pass                                          85%
     Number of Passes                                            2

Temperature
     Elutrient                                                   740
     Stripping Tower Air                                         740

Breakpoint Chlorination                                10 mg Cl2/mg NH3-N
(1) bv means gross bed volumes
                                  80

-------
                           PI LOT PLANT STUDIES
Service Cycle

Pilot scale studies on ammonia removal from  South Tahoe Public Utility District
tertiary effluent by selective ion  exchange were conducted over a 4-month period
with a 100,000-gpd mobile pilot plant. This plant has three 500-gallon ion exchange
vessels (3.25 ft in diameter by 8 ft high) which were filled with 38 ft3 (284 gal) to
50  ft3 (374 gal) of the  natural zeolite, clinoptilolite. Feed water was  percolated
through  the zeolite  beds either singly or  in  series until  ammonia breakthrough
occurred. The beds were  regenerated with solutions containing  lime, NaCl  and
CaCH. The spent regenerant containing ammonia was recovered  for reuse by air
stripping the ammonia from the regenerant solution in  a  3.6  ft  diameter by  8 ft
column packed with one-inch polypropylene Intalox (R) saddles. The flow rate to
the stripping column was normally 20 gpm with an air/liquid ratio of 150 cfm/gpm.
Ammonia  removal  in  the air stripper averaged about  40% at 25°C.  The spent
regenerant was normally recycled  through the air stripper and zeolite bed until the
NH3-N concentration in the stripped regenerant was reduced to 10 mg/1.

Zeolite ammonia loading studies were carried  out to establish the volume of  feed
water that  can be  processed through  a  zeolite  bed  until  significant ammonia
breakthrough occurred. The computed NE^-N  loading on two 4.5 ft beds of zeolite
(9 ft total bed depth) with South Tahoe Public Utility District  tertiary effluent
containing 12  mg/1 NH3-N was 6.52 g of NH3-N per gallon of zeolite. The average
NH3-N concentration in the effluent was approximately 0.4 mg/1 at a flow rate of
4.2 bed volumes per hour.  On this basis the  volume processed for  the 9-ft bed was
150 bed  volumes. The volume selected for full-scale plant design is  150 bed volumes
at a flow rate of 6 bed volumes  per  hour with a 12-foot-diameter bed, 8 feet in
depth. An average  effluent NH3-N concentration of 0.5 to 1.0  mg/1  is expected
under these conditions, with 15-20 mg/1 NH3 in the influent.

Figure 1  illustrates  NH^-N breakthrough curves for a single 6-foot  bed of zeolite
operated  at flow rates varying from 6.5 to 9.7  bed volumes per hour with 15 to 17
mg/1 NH3-N in the influent. Curve 1 at 8.1  bed volumes per hour shows the lowest
average effluent NH3-N concentration (0.67  mg/1) to 150 bed volumes but also has
the lowest average  influent NH3-N concentration (15  mg/1). Curve 2 at 6.5  bed
volumes  per hour shows  an average of 0.83 mg/1 NH3-N  in 150  bed  volumes of
                                    81

-------
00
to
OPERATING CONDITIONS:
FLOW RATES:(1) 8.1 bv/hr (2) 6.5 bv/hr, 6) 9.7 bv/hr
ZEOLITE GRAIN SIZE:  20x50MESH
BED VOLUME: 50 FT3
AVE. INFLUENTNH3-N:  (1) 15 mg/l, (2) 17 mg/l, (3) 17 mg/l
FEED: TAHOE TERTIARY EFFLUENT
                             FIGURE 1
  A CURVE 1      AMMONIA BREAKTHROUGH CURVES
                    FOR A 6ft. ClINOPTILOUTE BED
  A PIIRVF ?
  9 ^ur\vL t          AT VAR|OUS FLOW RATES
  O CURVE 3
                      20
           40
60
80
100
120
140
160
180
                                                 BED VOLUMES

-------
00
      Q
      UJ
      CO
                OPERATING CONDITIONS
                FLOW RATES: (l)4.2bv/hr, (2)8.4bv/hr
                ZEOLITE GRAIN SIZE: 20x50 MESH
                BED DEPTH: (1)9 FT  (2) 4.5 FT
                BED VOLUME: (1) 76 FT^, (2) 38 FT3
                AVERAGE INFLUENT NH3-N: 12 mg/l
                FEED: TAHOE TERTIARY EFFLUENT
                  o
                                          FIGURE 2
                            AMMONIA BREAKTHROUGH CURVES
                              FOR TWO 4.5ft. CLINOPTILOLITE
                                       BIDS IN SERIES
                                                                                       (2)
                      20
4U
60
80
100
120
140
160
180
                                                  BED VOLUMES

-------
effluent with an influent containing an average of 17 mg/1 NH3-N. Curve 3 at 9.7
bed volumes per hour shows an average effluent NH3-N concentration of 1.2 mg/1
NH3-N. Curve 3 also shows an initial high NH3-N concentration which is the result
of insufficient backwash  removal  of residual lime  remaining  in  the  bed  after
regeneration.

Ammonia-nitrogen breakthrough curves for two 4.5-foot zeolite beds operated in
series are illustrated in Figure 2.  The average  NH3-N concentration in 150 bed
volumes from the first bed in series (Curve 2) was 0.81 mg/1 at a flow rate of 8.4 bed
volumes per hour. The average NE^-N concentration in the effuent from  the second
zeolite bed (Curve  1) (total 9-foot bed depth) was 0.35 mg/1 at a flow rate of 4.2
bed  volumes per hour. The average NH3-N concentration in the influent was 12
mg/1.

It is evident from the data above and from series operation  data that  the higher
influent  NH3-N  concentrations  will  produce  higher  effluent  NH3-N  values.
Breakthrough and leakage are influenced by bed  packing characteristics and are
subject  to variation, other factors being equal. In general, deep  beds at low flow
rates will yield the low leakage and sharp breakthrough curves.

Elution Cycle

In order to minimize the volume of regenerant required to elute the NH3-N from the
zeolite beds, a batch regeneration technique was studied. A minimum  volume of
regenerant is desired to maintain a low heat input during the air stripping operation
in cool weather. Pilot plant data show that the NH3-N concentration in recycled
regenerant increases rapidly from near zero to about 500 mg/1 in a few hours with a
zeolite bed loaded  with  an average of 8.5  g of NH3-N per gallon of bed.  Three
elution  curves are illustrated in Figure 3 for average bed loading of 8.5 g of NH3-N
per gallon of bed. Curve 1  shows the lowest NH3-N (450 mg/1) concentration after 6
hours, which is  believed to   be the  result of the  low pH (10.8). The NH+4
concentration at 450 mg/1 NH3-N and pH 10.8 is 8.9 x 10"% compared with 4.0 x
10-4M NH+4 at pH 11.2  and  500 mg/1 NH3-N and 2.1 x  10-4M NH+4 at pH 11.5
and  520 mg/1 NH3-N. The amount  of ammonia removed from the zeolite will,
therefore, increase  with  pH (low solution NH+4  concentrations show low NH+4
zeolite adsorption). Curve 2 shows a slower rate of elution of the regenerant solution
than curve 3, which is believed due to a combination of the slower flow rate and
lower temperature and pH. Curve 3 shows  that equilibrium was attained after 4.5
hours.
                                    84

-------
00
                                                                      FIGURE 3
                                                                FIRST BATCH RECYCLE
                                                                  ELUTION CURVES
                                    OPERATING CONDITIONS:
                                    FLOW RATE:
                                    PH:
                                    BED DEPTH:
                                    REGENERANT VOLUME:
   (1)
9.4bv/hr
 10.8
 4. OFT
2.2bv
                                    TEMPERATURE:
                                      i	i
 I
  14°C
   (2)
6.4bv/hr
  11.2
 6. OFT
1.2bv
 8°C
  (3)
9.4bv/hr
  11.5
4. OFT
1.2bv
 15°C
                                                                           10
                          11
                     12
                                            TIME IN HOURS

-------
00
     UJ
/ uu
600

500
400
300
200
100
n
FIRST BATCH -x^
RECYCLE/'* FIRST
FIGURE 4
AND SECOND
BATCH
>^ RECYCLE ELUTION CURVE
^
/ OPERATING CONDITIONS
•/ FLOW RATE:
/ o P*
Q^SECOND BATCH BED DEPTH:
/T RECYCLE TEMPERATURE:
{ / BED LOADING, NH3-N:
/ REGENERANT VOLUME:
/ l l l 1 l 1 1

: FIRST BATCH
6.4bv/hr
10.5-11.5
6. OFT
13 °C
3.2g/l
1.2bv
l i

SECOND BATCH
4.8bv/hr
11.4
6. OFT
19 °C
0. 8 g/l
1.2bv
i i
0
                                                               8
10
11
12
                                            TIME IN HOURS

-------
CO
260
240
220
200
180
160
14O
120
100
80
^ fin
E 60
Z
m
I"
-n20
O
c
•a
m
01









•X*












t
i











/
y











/,
v
>












r












Salt
Added
•^ r






EF






/>
^s'






:FECT




>
/
/






OF SAL
Dl


/
V
•)








f
.TADD
JRING

P
/











OPE RATH
Cl




IGURE
ITION(
BATCH
TE
pH
RE
BE
SA


5
DN NH;
RECY(







SJG cor
OW RA
MPERA
GENEF
D VOL
LT AD[


|-N ELL
:LE







4DITIO
TE
TURE
ANT V
JME
DED


ITION








*JS:
OLUME

























i








22°C
11.2
2 3 bv
240^1
10lbs


















































91 23436789 10
TIME IN HOURS

-------
Curves 1 and 3 represent the recycle of 2.2 bed volumes; whereas, curve 2 represents
1.2 bed volumes. In order to attain a sufficiently high NH3-N removal, the recycle of
4 bed volumes of regenerant is recommended at pH 11.5 with regenerant containing
0.2M Na+ plus 1M Ca+2 which is in equilibrium with the Na+. At 500 mg/1 removal
in the 4 bed volumes of recycled regenerant (average loading of 10 g of NH3-N per
gallon of zeolite), the first batch recycle will elute 75% of the loaded NH3-N.

The second batch recycle is expected to bring the elution up to more than 90% and
will contain about 100 mg/1 NH3-N. Since the second batch recycle is used without
air stripping for the first batch recycle of the next regeneration, it then will  attain an
ultimate NH3-N concentration of 600 mg/1 at 75% elution. Figure 4 illustrates a first
and second batch recycle for a highly loaded zeolite bed (3.2 g of NH3-N per liter of
bed). The first batch was air stripped to 107 mg/1 NH3-N while recycling through
both the zeolite bed and the stripping column. Regeneration was 75% complete at
this point. The NH3-N increased by 150 mg/1 in the regenerant after 2 hours in the
second batch  recycle, which  indicates that the regeneration will be close  to 100%
with 4 bed volumes. The time required for the second batch recycle (2 hours) was
less than that  of the first batch (4-6 hours) due to : (1) The time lag in reaching the
optimum  pH  at  the beginning  of  the  first batch recycle  and;  (2) the  lower
temperature of the first batch recycle (9°C vs  19°C).

The effect  of  salt (NaCl) addition during a batch recycle is illustrated in Figure  5.
The salt was added when the NH3-N concentration in the regenerant appeared to be
leveling off  at  155 mg/1. The NE^-N  concentration then increased at a rate  higher
than that prior to the salt addition. The loss in regenerant per cycle is about 5% of a
bed volume  based on laboratory data which is approximately 1.3% of 4 bed volumes
of regenerant.  The total salt lost per  thousand gallons of water treated is estimated
to be 0.32  Ibs of NaCl from a regenerant solution  containing mixed salts (CaCl2 +
NaCl) at a concentration of 2.2 equivalents per liter. The maximum pH that  can be
attained by adding lime to this regenerant is  11.5.

Ammonia Stripping Tower

The design  criteria for  the ammonia stripping tower were  based  on pilot plant
studies by the South Tahoe Public Utility District/1) Figures 6 and 7 indicate that
85% removal at 74°F can be achieved with an air-to-liquid ratio of 300 cfm/gpm and
a surface loading of 3.5  gpm/ft2 in a 24 ft tower.
  (I) Smith and Chapman, "Recovery of Coagulant, Nitrogen Removal, and Carbon Regeneration in Waste
Water Reclamation." FWPCA Grant WPD-85, June 1967.
                                     88

-------
   100
                                           24' DEPTH
<
O
LJ
O
IT
LLJ
Q.
   80
	^	12 FEET OF PACKING

          20 FEET OF PACKING
	h	   24 FEET OF PACKING
               200
                          400
                                     600
                                                800
                                                          1000
                                                                    1200
                       CUBIC FEET AIR/GALLON TREATED

                                  FIGURE6
                   PERCENT AMMONIA REMOVAL VS CUBIC FEET
                   OF AIR PER GALLON WASTEWATER TREATED
                       FOR VARIOUS DEPTHS OF PACKING
                                     89
                                                                      FIGURES

-------
               <
               >
               o
               tr
               <
               H
               O
               cc
                                                                                  1 2 FEET OF PACKING


                                                                                  20 FEET OF PACKING


                                                                                  24 FEET OF PACKING
                                  1.0
                                            2.0        3.0         4.0         5.0


                                               SURFACE LOADING RATE - gpm/ft2



                                                          FIGURE?


                                     PERCENT AMMONIA REMOVAL VS SURFACE LOADING RATE

                                               FOR VARIOUS DEPTHS OF PACKING
                                                                                        6.0
                                                                                                   7.0
c
33
m

-------
 An  open packing such as found  in cooling towers was chosen over other types of
 packing such as Intalox^ saddles  or Raschig rings in order to avoid high, expensive
 pressure losses and to utilize existing pilot plant data.

 Temperature Requirements for Elution and Air Stripping

 The choice of 23°C (74°F) as the elution  water and air stripping temperatures was
 based on laboratory and pilot  plant work by Battelle-Northwest. It was felt there
 was not enough data to accurately predict elution and air stripping requirements for
 lower or higher temperatures.

 L.L. Ames showed  that at 23°C (74°F)  the  elution rate probably represented  an
 optimum  between  Ca(OH>2  solubility in the eluting solution and  the  cation
 exchange  kinetics.'1) He  reported that  zero degrees  and 80°C represented the
 slowest elution rates, requiring 80 to 120 bed volumes.

 If the laboratory work by Ames at low temperatures were  used  to  design the
 proposed South Tahoe plant, the elution  rate would be at least twice as long. For
 the  proposed design flows at the longer elution rate, 15  ion exchange beds instead of
 12 would be needed. The size of each exchange bed would be about the same. Nine
 beds would be in service and six in regeneration. Each elution tank and the tower
 recycle basin would have to be about  100% larger than required for 12 exchange
 beds.

 The  flow  rate  to the stripping tower  would be  about the same, however, for a
 24-foot-high  tower,  about four times JT ore surface area would  be needed at the
 cooler temperatures. The fan would have to deliver nearly four times as much air.

 The  larger tower would  also require  greater maintenance expense for  removal  of
 calcium carbonate.
    (1)  Ames, L.L. "Zeolitic Removal of Ammonium Ions From Agricultural Wastewaters," 13th Pacific
Northwest Industrial Waste Conference Proceedings, 135,152, Washington State University, April 1967.
                                        91

-------

-------
                           THE PROPOSED PLANT
Service Cycle

At a design capacity of 7.5 mgd, nine ion exchange beds would be in service at all
times. The beds would be operated  in parallel. When a total of 450 bed volumes
(3.05 mg) had passed  through  three beds (150 bv  per bed), these beds would be
taken off line and three freshly  regenerated beds would be put on line in their place.
A flow totalizer would be used to  measure the 150  bed volumes and automatically
initiate an elution cycle.

Ion Exchange Beds

Drawing  No. 4 shows a typical cross-section of an ion exchange bed. Each bed would
be 12 feet in diameter and have an effective clinoptilolite depth of 8 feet. The flow
through  a bed would be six bed volumes per hour or 680 gpm. The surface loading
rate  would be 6 gallons per square foot per minute.  Overdesign is about 20% due to
choosing an integer (ft) diameter.

Due to calcium carbonate deposition during regeneration with pH 11+ lime solution,
the inlet and outlet screens for  each bed are removable for cleaning. The screens can
be taken out of the bed without removing the clinoptilolite.

Tne  beds have also been designed such that clinoptilolite can be added or removed
by means of  a water/clinoptilolite slurry. A special transfer header is included to aid
in moving the clinoptilolite out of the bed and into the transfer line.

Clinoptilolite Transfer Tank

The transfer tank would be used for both washing and adding make-up clinoptilolite.
To  add  make-up clinoptilolite, about 5% of an exchange bed volume could be
dumped  from bags into the transfer tank, washed if necessary, and then transferred
to the top of any of the exchange  beds in a  slurry by pressurizing  the transfer tank
with water.

If clinoptilolite in an exchange  bed required  washing, it would be removed from the
bottom by pressurizing an exchange vessel, put into slurry form, and moved to the
transfer tank.  After washing, the clinoptilolite would be returned in a slurry to the
top of the exchange bed.
                                    93

-------
Regeneration Cycle

At design flow the service cycle for a set of three beds would be about 25 hours. On
the basis of nine beds in service and 25-hour service cycle, a set of beds would have
to be regenerated about every 8 hours.
                                                                    i
Under  the elution procedure outlined earlier, the elution of ammonium ions would
take place in two phases. Four bed volumes (81,600 gal.) would pass through a set
of three beds for each phase;  or a total of 8 bed volumes would be needed to
completely elute the ammonium  ion from each of the three exchange  beds. Each
elution phase would last about 4 hours. The elution would be upflow at a rate of 10
bed volumes per hour or 10 gallons per square foot per minute.

Two of the three  1,700-gpm pumps (Drawing No. 3) would be needed to provide
enough flow to elute three  exchange beds in  parallel. The three pumps would be
rotated so that one could be offline in order to remove lime build-up. After elution,
one  of the three  pumps would be used to backwash the bed. Each bed would be
washed upflow in sequence at a rate of 15 gpm/ft^.

It is anticipated that most of the pipes, valves, and pumps, particularly those items
which  handle  the lime elutrient, would have to be routinely cleaned. To facilitate
cleaning of the pipes, all changes in  direction would be made by using crosses with
blind flanges. Wafer stock valves would be used in order that the pipe cleaning device
would  readily pass through the valve.

The  regeneration  cycle, as was  the  case for  the service  cycle,  will be completely
automatic.

Elutrient Storage Tanks

Three  covered concrete elutrient  storage  tanks, each holding  94,500  gallons, or
approximately 20% more than the anticipated elutrient volume, would be used.

The  elutrient  tanks  would  also  function as  settling basins for  excess calcium
carbonate. The tank floors have a l-to-12 slope to a sludge draw-off sump. A slotted
pipe is  used to remove the elutrient in order to avoid disturbing the settled sludge. In
the same manner, elutrient returning from the exchange beds flows into a stilling
well before entering the tank.
                                    94

-------
Approximately a 4-hour period would elapse from the time ammonia-free elutrient
returned from the stipping tower to the elutrient tank until it was needed for an
elution polishing cycle. The return flow from the stripping tower would enter at the
back of the tank and be used to move the settled solids toward the sludge sump. The
4-hour delay would allow time to clarify the elutrient. The rectangular tank design
would permit, if necessary, the addition of mechanical sludge collection equipment.

Lime Storage and  Feeders

At a design flow of 7.5 mgd, theoretically 2,300 Ibs/day of calcium oxide would be
required  for elutrient  make-up if the ion exchange  beds  were to remove 19 mg/1
NH3-N. If a 40%  safety factor is included and the lime the District can purchase has
a CaO content of 90%  approximately 3,600 Ibs of lime per day would be needed.

The proposed storage bin was sized to provide 10 to 14 days of storage.

About  one-half of the ammonia  is eluted from the exchange beds in  the first hour
regeneration. To meet this high demand for calcium hydroxide in the first hour, the
lime feeder and slaker would have to be capable of handling about 800 Ibs/hr. Two
800 Ibs/hr feeder-slakers would be needed to allow for down-time for cleaning and
maintenance.

Sodium Chloride Storage and Brine Feeder

Sodium chloride,  0.2  N,  was found to be helpful during the elution of ammonia
from the clinoptilolite. To make  up 0.2N NaCl in the elutrient, 4,700 Ibs/day would
be needed, or on the basis of the proposed 2-week  storage period,  66,000  Ibs of
sodium chloride would have to be stored.

Lime and Salt Mixing Basin

The mixing  basin would  be used for  both  the addition of calcium hydroxide and
sodium  chloride makeup and for initial clarification of the elutrient. The elutrient
velocity through the basin would be about 0.1  ft/sec and the detention time about 9
minutes. The  baffles  within  the basin would provide for 60 feet of linear flow
distance. A hopper bottom would permit sludge draw-off.
                                     95

-------
Automatic pH monitoring equipment at the inlet and outlet to the basin would be
used to control the lime feeder. The  brine feeder would be paced by flow in the
basin.

Ammonia Stripping Tower and Recycle Basin

The ammonia stripping tower has been sized to treat the contents of an elutrient
tank in 8  hours, using two passes through the tower  at 85% removal per pass. At a
flow rate  of 300 gpm, an air-to-water ratio of 300 cfm/gpm, and a loading of 3.5
gpm/ft2, approximately 86 ft2 of packing and 90,000 cfm air would be required/1)

To prevent loss in stripping efficiency  due to calcium carbonate build-up, the tower
packing would be removable in sections for cleaning. The catch basin below the
packing is sloped to the recycle basin below the tower  to aid in sludge removal.

The design of the recycle basin below the tower would be similar to that of the
elutrient tanks. A sloping bottom and sludge draw-off are included. The design is
such that  mechanical sludge collection could be added, if necessary, at a later date.

Process Controls

The selective ion  exchange  process  has three  basic  operations; service cycle,
regeneration  cycle,  and  air  stripping  of the  high   ammonia regenerant. These
operations occur simultaneously during normal operation of the process. The zeolite
beds have four headers, bed influent and bed product, regenerant in and out,  each
header  requiring  a valve  at each bed. During normal operation,  nine beds are in
service and three beds are in regeneration; when  three  beds are regenerated,  they
must be placed on line and  three more beds taken off line for regeneration.  This
requires the opening or closing of 24 valves, plus the regenerant storage tank valves.
While  the bed  regeneration is  proceeding, the  regenerant from the  previous
regeneration  must  be passed through the  ammonia  stripping tower  twice.  It is
obvious the three  basic operations  must  be  automated with  pneumatic  or
hydraulically actuated valves.
   " ' On the basis of processing 4 bv regenerant/requiied ion exchange bed volume, the tower is overdesigned
by about 9%. On the basis of actual bed volume about 11% underdesign is indicated but this is an unrealistic
basis because the beds are overdesigned. The tower should be more than adequate as specified.
                                      96

-------
In addition, to maintain the three-bed-regeneration sequence, a flow totalizer must
be placed on a minimum of every third bed, and preferably on every bed, to record
the number of bed volumes  passed before regeneration is necessary. Also, each bed
should have a flow rate recorder to maintain equal flows to each of the three beds.

After the three beds are regenerated, product water from  the nine beds in service
must  be diverted and  pumped  through the  three beds for backwashing. A flow
controller must be placed on the product water to throttle the flow and divert the
required supply  of water for backwashing. Also, valves should be placed  on the
present carbon  column effluent line  or bed influent header and on the product to
chlorination line to  provide  for bypassing of the ion exchange process, if necessary.

The regeneration backwash pumps and the tower pumps must be automated in one
control center, since both elution and stripping operations will be proceeding at the
same time.

Information  obtained   during  pilot plant  operation  indicated  the  optimum
temperature and pH to achieve  maximum efficiency of the elution  and stripping
operations were at least  74°F and  a  pH of 11-11.5. Also, the presence of a
significant  amount of sodium  increases the service cycle and shortens the elution
cycle.  In order to maintain  optimum conditions, a pH monitoring system must be
provided  on the entrance  and  exit  of the mixing basin  to control lime  slaker
operation.  The salt brine addition equipment must be automated in accordance with
the  flow  through  the  mixing  basin,  to  maintain  an  approximate  .2  molar
concentration in the regenerant. Temperature  monitoring  and controls must  be
placed  immediately up stream  of the  zeolite beds and  the  stripping tower to
maintain the optimum temperature in the regenerant for elution  and stripping. In
addition, the air utilized by  the stripping tower must be maintained at the optimum
temperature of 74°F. The air temperature  monitoring and heat addition equipment
must be automated to maintain optimum temperature conditions.

The accumulation of solids  in the mixing basin, regenerant storage tanks, and the
tower  recycle basin will require daily pumping of sludge to the existing lime floe
basin. Sludge pumping and the necessary valving can be accomplished manually.

In the pilot plant studies there was evidence of the  zeolite "mudballing" with the
cohesive solids in the regenerant. Manually operated valves have been provided to
remove the zeolite from the bed, transfer the zeolite in a slurry to the transfer tank,
wash it, and transfer it back to the bed.
                                    97

-------
During  the initial  start-up of the process, a large number of ammonia-nitrogen
determinations  will be required to determine a more accurate time period for the
two elution cycles. When approximate time periods are established, the regeneration
cycle  can be placed on an automatic time basis, and should eliminate laboratory
analysis except  for periodic checks. Also, ammonia-nitrogen determinations will be
required initially to verify the expected efficiency of the ammonia stripping tower,
and  the  150  bed  volume  service  cycle  before  one mg/1 ammonia-nitrogen
breakthrough.  After  these  design  criteria  are  verified only  the routine  plant
operation analysis  will be required,  except for periodic  checking of decreased
efficiency of  the stripping tower as a result of calcium carbonate incrustation on the
tower fill. Periodically the fill will be removed and cleaned.

Heating of Elutrient and Stripping Tower Air

In order to maintain both the elutrient and stripping tower air at 74°F, five separate
heating systems would be needed.

The design has  been based on utilizing the 500-gpm scrubber water off the exising
lime and sludge furnaces to preheat the air to the tower. The remainder of the  air
heating would be accomplished  with 180°F hot water from a new boiler. The heat
would  be transferred to the air  by means  of coils occupying  a 7-foot-wide  by
11-foot-high area on each end  of the building opposite the open tower packing.

Three  water-to-water  heat exchangers  would be used to heat the elutrient. Heat
exchanger No. 1 would reheat to 74°F the elutrient going to the top of the stripping
tower  from  either the elutrient storage tank or  from the stripping tower recycle
basin. Heat exchanger No. 2 would reheat the elutrient after it had made the second
pass through  the stripping tower  but before it reached the elutrient storage tanks.
The third heat exchanger,  No. 3, would heat the elutrient to 74°F as it passed from
a storage tank to an ion exchange bed during the elution cycle.

Sludge Collection

Ammonia removal studies were  conducted with the mobile demonstration plant at
the Richland  wastewater treatment plant. From these studies it has been estimated
that 0.4 Ibs of dry solids per 1,000 gal of treated water would be generated. For the
proposed process at the South Tahoe Water Reclamation Plant, approximately 3,300
Ibs of dry solids would be produced per day.
                                     98

-------
The sludge would be pumped from the chemical mixing basin, each elutrient tank,
and the stripping tower recycle basin through a 12-inch  pipe to the existing lime
flocculation basin. The 12-inch  pipe would  also be used to carry  1,700  gal per
minute of backwash water from the final ion exchange bed  rinse.

One  530-gpm  sludge pump, operating for 15 minutes per day,  would be used to
pump the sludge to the floe basin. The high pump rate would be necessary in order
to maintain scouring velocities in the 12-inch  pipe. A second 530-gpm pump would
be provided as a stand-by unit.

A new lime transfer pump at the existing chemical clarifier and a new centrifuge
would be needed to handle the additional sludge.
                                       99

-------
                        FINANCIAL REQUIREMENTS

This section presents  the estimated project costs  and a brief  summary of the
required project financing.

Construction Cost Estimates

The  construction cost  estimates are based on the quantities and character of work
described  for each  element  of  the  project.  Materials prices were  obtained from
manufacturers and were added to estimated labor costs plus contractors' overhead
and profit, to obtain individual costs. These prices were then compared to actual bid
prices  for similar  work,  adjusted  as  necessary to  reflect  past  experience in
construction  contract costs for  the Lake Tahoe  area.  The estimates are based on
construction  starting in 1970. If the project is delayed then the  cost estimates must
be escalated to account for probable increases in material and labor costs. Table C is
a detailed estimate of the project construction cost.

Incidental Cost Estimates

An allowance for incidental  costs must  be added to the construction cost. These
costs are an  integral part of  the project cost and include engineering, construction
inspection, administration of the project, and collection and publishing of operating
data after completion of the project.

Operating Cost Estimates

Operation of the  project will lead  to increased costs  for the District. Table D shows
the estimated operating cost  for the nitrogen removal plant when it is in complete
operation. These  costs  are based on a design flow of 7.5 mgd and  will be somewhat
higher  per millon gallons for  flows less than the design capacity, since some of the
costs are fixed. Labor costs are based on one operator per shift, 3 shifts per day,  365
days per  year.  Chemical costs  are based  on predicted dosages  required  for
continuous operations. All prices are based on delivery to Tahoe. Electric power and
natural gas costs are based on  current rate schedules at Tahoe.
                                      101

-------
Total Project Cost

The  total estimated  construction cost,  including  engineering and inspection,  is
$1,981,500. The average annual capital cost, amortized over 20 years at 6% interest,
would be $172,700 per year. Based on a  plant capacity of 7.5 mgd the capital cost
per  million  gallons  would  be $63.10.  The estimated annual  operating cost  is
$232,100.
The data collection and publication phase upon completion  and operation of the
project is estimated to cost $72,000 per year, based on two engineers being assigned
full time to the project.
                                    102

-------
                                TABLE C
                       ESTIMATED CAPITAL COSTS
    DESCRIPTION
QUANTITY    UNIT    UNIT COST   TOTAL COST
Move-in
Bonds £ Insurance
Excavation & Backfill
Concrete
Steel Building
Painting
Welded Steel Pipe
Large & Special Valves
Misc. Fabricated Steel
Floe Basin
Ion Exchange Beds
Clinoptilotite
Lime Storage & Slakers
Salt Storage & Feeder
Salt Conveyor
Booster Pump
Regenerant Pump
Sludge Pump
NH3 Tower Pump
NH3 Tower Structure
Boiler & Accessories
Air Heat Exchanger
Water Heat Exchangers
Hot Water Pumps
Electrical Work
Instrumentation
Heating & Ventilating
Misc. Piping & Plumbing
Operational  Tests
Cleanup
        1
      12
  12,000
       2
       3
       2
       2
LS
LS
LS
LS
LS
LS
LS
LS
LS
ea
ea
cf
LS
LS
LS
ea
ea
ea
ea
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
LS
$30,000
 27,000
     10
  4,500
  5,000
  1,500
  1,500
    TOTAL ESTIMATED CONTRACT PRICE

         Construction Contingencies
         Design Engineering at 6.37%
         Construction Inspection ($3,000/mo x 18 mos)

    TOTAL ESTIMATED CAPITAL COST
$    5,000.00
     2,000.00
    15,000.00
   165,000.00
    65,000.00
    25,000.00
   275,000.00
    60,000.00
    25,000.00
    30,000.00
   324,000.00
   120,000.00
    30,000.00
    30,000.00
    20,000.00
     9,000.00
    15,000.00
     3,000.00
     3,000.00
    50,000.00
    24,000.00
     8,000.00
     8,000.00
     4,000.00
   100,000.00
   200,000.00
    15,000.00
    10,000.00
     5,000.00
     2,000.00

$1,647,000.00

   165,000.00

$1,812,000.00

   115,500.00
    54,000.00

$1,981,500.00
                                    103

-------
                              TABLE D
                    ESTIMATED OPERATION COSTS
                                                        AT 7.5 mgd
                                        COST/YR         COST/mg
Makeup Lime                             $  19,900         $   7.30
Makeup Sodium Chloride                      18,900             6.90
Makeup Clinoptilolite                        53,600            19.60
Operational Labor                           50,800            18.60
Maintenance, Material & Labor                 25,000             9.15
Chlorine                                   17,400             6.40
Natural Gas                                 20,300             7.40
Electricity                                  26,200             9.60

    Total Operating Costs                  $232,100         $ 84.95
    Amortized Capital Cost                 172,700           63.10
       (6% - 20 yr.)

    TOTAL CAPITAL & OPERATING COST                  $ 148.05
                                104

-------
                       REQUESTED GRANT PROGRAM

General

The removal of nitrogen from sewage effluent remains as one of the most difficult
problems to solve in the advanced waste treatment field. The various methods that
have been tried at South Tahoe, both as pilot plant studies and full-scale operation,
have not accomplished the complete removal of nitrogen that is necessary if sewage
disposal in the Lake Tahoe basin is ever to be considered.  The need for a complete
nitrogen  removal process is, of  course, a national problem, not limited  to Lake
Tahoe only.

The proposed ion exchange process as  envisioned in this  report, gives promise of
being a most satisfactory means of complete nitrogen removal. The pilot plant work
that has  been completed strongly indicates that ion exchange is effective,  but also
indicates that the process will  be relatively expensive and also will be relatively
sophisticated to properly operate.

The only assured means to adequately demonstrate the effectiveness of the process,
will be to construct and  operate a full-scale plant. Experience of South Tahoe with
other elements of the advanced waste treatment process has clearly shown that full
plant operation  is the only effective means for demonstrating  performance. Pilot
plant studies, while necessary and effective, do not  give the  proof that the process
can be operated on  a continuous daily  basis  and that the  process can work within
the limits of dependability and operating limitations imposed  by full-scale plants.

Therefore,   the  South  Tahoe  Public Utility District strongly  believes that the
effectiveness of the proposed  ion exchange process  for nitrogen removal can be
proven only by  constructing  and operating  a full-scale  TVi-mgd  capacity  plant.
Construction and  operation  of the full-scale plant will make  available complete,
accurate, and dependable information  on nitrogen removal and will demonstrate
that the  operation can be done on a continuous, effective basis. Such information
will be of inestimable value in the coming decade, when the water quality control
program will be instigated on a nation-wide basis.
                                      105

-------
It is only logical that the ion exchange plant be constructed at South Tahoe, since
the  District has  available the  only  full-scale operating advanced  wastewater
treatment plant in the  nation  along with the  trained,  skilled operating personnel
required to operate  the ion  exchange plant,  and also has available through  its
manager and engineering consultants, the technical experience and expertise to make
the design, construction, and operation phases a success.

Proposed Schedule

The design  of the full-scale plant  can be initiated immediately upon approval being
given by FWQA.  The  design  can  be  completed  within a 6-month period and
construction bids can be obtained within 30 days after approval of these final plans.

The District will utilize its consulting engineers, Clair A. Hill & Associates,  to
accomplish the design.  The consultants will be associated with Cornell, Rowland,
Hayes and  Merryfield Consulting Engineers of  Corvallis, Oregon, during the design
and  operation  of  the  ion exchange plant.   These  consultants  have previously
designed, supervised  construction,  and  trained the  operating  personnel for  the
District's advanced waste treatment plant.

The construction of the  plant will  require approximatley 9 months on an accelerated
schedule. A  one-year construction period would be advisable in order not to pay a
premium for earlier completion.  Construction  would  be  done through  a public
bidding  procedure and  the contract would  be awarded to the  lowest responsible
bidder. Inspection of the construction, to assure compliance with  the approved plans
and specifications, would be done  by the District's consulting engineers.

Allowing adequate  time for  review of this report, design of the final plant, and
construction of the plant, indicates that operation could begin sometime during the
spring of 1972. Since the proposed process is new and untried, an operating and data
collection program extending over a 2-year period is  recommended. This would
mean that the final project report  would be submitted in 1977.
                                         106

-------
Project Grant Costs

The proposed project as outlined here would be financed entirely by grant funds
from  the FWQA. The District would  make available its advanced waste treatment
plant, laboratory facilities, and administrative offices to the project. In addition, the
District Manager, Russell L. Gulp, would serve as the Grant Project Director at no
charge to the project.

Financial requirements for  the grant would therefore need to be disbursed by the
FWQA in accordance with the following schedule:

                                                              GRANT
      FISCAL YEAR        DESCRIPTION OF WORK         AMOUNT

          1970-71           Engineering Design                 $115,500
          1970-71           Construction & Inspection            927,000
          1971-72           Construction & Inspection            939,000
       1972 thru 1977        Operation & Data Collection          323,000/yr

The above costs are requested to be  paid by the FWQA under a continuing grant
program.
                                       107

-------
o
00
                             VICINITY   MAP
                                LOCATION   PLAN
                                                                   H-
CLAIR A. HILL  &. ASSOCIATES
       CONSULTING ENGINEERS
                                                                                                                          FUH.K. UTILITY
IOKI  EXCMAM6E. MITeQ4CM REMOVAL PUtJT

  VICIMITV MAJ»  t. LOCATIOM

-------
 MAJCM TYPES
r'f TREATMENT
  PROVIDED
RIMARY TREATMENT
ISOLIOS SEPARATION
SECONDARY TREATMENT
 (BIOLOGICAL TREATMENT)
                      1      BASIC
CHEMICAL TREATMENT   {    NITROGEN
& PHOSPHATE REMOVAL  I    REMOVAL
                                                                                     FILTRATION
ACTIVATED
  CARBON
ABSORPTION
                                                                                                                                  ION EXCHANGE
                                                                                                                                    DISINFECTION
                    MARSHALL FLUMES
                    FLOW MEASUREMENT
                    AND DIVISION

                 SARMINUTORS
                                                                                                                                                                      RECLAIMED
                                                                                                                                                                      WATER TO
                                                                                                                                                      RESERVOIR
WASTE WATER
FLOW THRU
PLANT

SOLIDS
HANDLING LIME
AND CARBON
RECLAMATION
& ION EXCHANGE
REGENERATION
                 STERILE ASH TO
                .  DISPOSAL
CARBON
OE FINING
TANKS


                                                                                                                   CARBON TO
                                                                                                                   HE USE
                                                                           ft
                                                                CLAIR  A.  HILL &. ASSOCIATES
                                                                         CONSULTING ENGINEERS
                                                                                         IOVJ
                                                                                        UTIt-iTV DISTRICT
                                                                                          REMOVAL PUNT
                                                                                                                                TOTAJ-  PLAKJT  PLOvV

-------
                                                                       INFLUENT HEADER ,
                                                                                                      INFLUENT FEED
                                                                                                      FROM CARBON COLUMNS
ION
EXCHANGE
BEDS __---
                   r
                                                                REGENEBANT
                                                                                                                                                      10
. r
i^?i rT-
f

] HEGENEHANT SOLUTION INLET HSABIB I I I I
1
>
WASTE
                   'HEGENEHANT SOLUTION
                    INLET HEADER
                    HEGENERANT
                    PUMPS
                    BACKWASH SUPPLY LINE
                                                                HEGENEHANT SOLUTION SUCTION LINE
                                                                                                                                                         BACKWASH
                                                                TOWER INFLUENT
                                                                PUMPS
                                                                                                        REGENEHANT STORAGE TANKS
                                            AMMONIA
                                            STRIPPING
                                             TOWER
                                                                               TOWER INFLUENT LINE
     TOWER EFFLUENT LINE
                                                TOWER
                                               STORAGE
                                                TANK
-TOWER
 RECYCLE
 LINE
1 BEDS 1. 2 & 3 ARE SHOWN IN REGENERATION CYCLE
2 BEDS 4 - 12 ARE SHOWN IN SERVICE CYCLE
3 TOWER SHOWN STRIPPING FROM  REGENERANT
  TANK A SINGLE CYCLE
  TANKS B &. C ARE IN REGERATION CYCLE.
4 ® INDICATES VALVE CLOSED
  X INDICATES VALVE OPEN  4

                                                                                     H-
                  CLAIH A.
                                                                      IOM EXCMA.M6E NITRO^EM
                                                      2

-------
L A.NJ
                                                           4"    i"    r
                                                 DEDUCED  r LAIS'
H-
   CLAIR  A. HILL &  ASSOCIATES
           CONSULTING ENGINEERS
,\i ?EUOVAL PLAWT
                                                   VI£.C^:A.M:CA~- PI_AUS

-------
J-*
to
                                                                                                                              T-/PICAL
                                                                                                                                                  "
                                                                                                                                        IENCCI  n»is
'••>w-=.
 CMliF CIVIL
                                                                           H-
CLAIR  A. HILL &  ASSOCIATES
        CONSULTING ENGINEERS
                                                                                                                               scrtou&  e.
                                                                                                                                            4

-------
BUILT-U" •-
                                                                             •mca nus


-""w"M;ft£
OATV


ICLAIR A. HILL & ASSOCIATES
CONSULTING ENGINEERS
'OKJ c\CH.\k!£E M'iT2jD6EKJ REMOVAL PLAWT

5
jam MO U>M««

-------
_L
Access/on Number
W
5
2

Subject Field & Group
05D
SELECTED WATER RiSOURCIS ABSTRACTS
INPUT TRANSACTION FORM
Or&anization
     South Tahoe Public Utility District, South Lake Tahoe, California   95705
   Title

     WASTEWATER AMMONIA REMOVAL BY ION EXCHANGE
10
   Aathorfe)
                                      16
Project Designation

 EPA Project #17010 ECZ
                                    21
                                        Note
22
    Citation
23
     Descriptors (Starred First)

      *Waste  Treatment, *Ammonia, *Ion Exchange, ^Electrolysis,  *Cost  Comparisons,
      Sewage,  Sewage  Effluents, Municipal Wastes, Waste Water  (Pollution),  Nitrogen
      Compounds,  Cation Exchange, Zeolites, Separation Techniques,  Air-Water
      Interfaces,  Cost Analysis, Design, Design Criteria
25
     Identifiers (Starred First)

      *Clinoptilolite,  ^Stripping, Air Stripping
27
     Abstract
      Pilot plant  investigations were conducted on the ion exchange  removal  of ammonia-
      nitrogen from  clarified and carbon-treated secondary effluents  and  from clarified
      raw sewage.  The  ion exchange process utilized clinoptilolite,  a  natural zeolite.
      Average ammonia removals from low magnesium wastewaters were in the range of 93%
      to 97%.  With  a wastewater Mg concentration of 20 mg/1, solids  formation presented
      problems but they appear surmountable.  The primary method  used for regenerant
      renovation was air stripping with which a 2N_ regenerant at  a pH of  11.5 is recom-
      mended.  Electrolytic regenerant renovation using a neutral solution that is less
      prone to solids formation was also piloted during the project.

      Two process designs  are included giving cost estimates for  ion  exchange ammonia
      removal from tertiary effluent.  With capital costs amortized  at  6% for 20 years,
      the total cost to remove ammonia from 1000 gal. of tertiary effluent is 14.8£ for a
      7.5 mgd plant  using  regenerant air stripping and 12. 7£ for  a 10 mgd plant using
      electrolytic regenerant renovation.  The 7.5 mgd design was prepared by South Tahoe
      Public Utility District under EPA Project Number 17010 EEZ  and  is included for
      convenience.   Other  work discussed in the report was performed  by Battelle-
      Northwest under EPA  Project Number 17010 ECZ.  (Mercer - Battelle-Northwest)
Abstractor
_ _   Basil
            W.  Mercpr
                              IriNtilution
                                       Battelle-Northwest
WFi:ID2  (REV. JULY 1969)
WRSI C
                            SEND, WITH COPY OF DOCUMENT.
                                                       - WATER RESOURCES SCIENTIFIC INFORMATION CENTER
                                                        U.S. DEPARTMENT OF THE INTERIOR
                                                        WASHINGTON. D. C. 20240
                                                             4U.S. GOVERNMENT PRINTING OFFICE: 1972 484-483/85  1-3

-------