.
*  rf^
    *    UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                     WASHINGTON. D.C. 20400
                                                       OFFICE OF
                          .. «. ~ ./w.               THE INSPECTOR GENERAL
                          JUL 25 1988
MEMORANDUM

SUBJECT:  Audit Report on Superfund Interagency
          Agreements with the Corps of Engineers
          Charles George Waterline Site
          Audit Report No. M5BG8-11-0049-81533
FROM:     Kenneth D. Hockman
          Divisional Inspector General for Audit
          Internal .Audit Division (A-109)

TO:       Harvey Pippen, Director
          Grants Administration Division (PM-216)

                             i
The Office of Inspector General requested the Auditor General
of the Army to perform an audit of design and construction
costs incurred and actions taken by the Corps of Engineers
(COE) under a Superfund interagency agreement.  Attached  is the
Army Audit Agency's (AAA) report of May 27, 1988, on the  Charles
George Waterline Site in Tyngsboro, Massachusetts.  Based on
the recommendations in the report and COE's response to the
report, the COE will correct its accounting records to properly
reflect project costs and will determine whether the architect-
engineer firm was liable for design error.  COE's reponse to
the final audit report is due by July 26, 1988.

EPA can take an active role to assure that costs are being
charged properly.  Accordingly, we are making the following
recommendations .

RECOMMENDATIONS

We recommend that the Director, Grants Administration Division:

     1.  Obtain a copy of the COE's accounting record adjust-
         ments to ensure corrections were made.

-------
     2.  Correct EPA's financial management system as
         appropriate for site specific costs based on the
         COE's adjustments.

     3.  Obtain a copy of the COE's report on architect-
         engineer's liability to determine if the question
         of liability was resolved and documented adequately.

     4.  If the architect-engineer is liable and the COE
         recovers damages from the engineer, ensure that
         the recovered funds are deposited in the Trust Fund
         and adjustments to EPA's accounting records are made
         accordingly.

ACTION REQUIRED

In accordance with EPA Directive 2750, the Action Official is
required to provide this office with a copy of the proposed
determination on the findings within 90 days of the audit
report date.  The Director,  Grants Administration Division, is
the Action Official for this report.

Should your staff have any questions concerning this report,
please have them contact John Walsh on 475-6753.

Attachment

-------
                                             APPENDIX


                     DISTRIBUTION OF REPORT


Chief, Financial and Administrative Management
  Section,  Office of Emergency and Remedial Response (WH-548D)

Director, Financial Management Division (PM-226)

Director, Procurement and Contracts Management
  Division (PM-214)

Chief, Grants Information and Analysis Branch (PM-216F)

Regional Administrator, Region 1

Divisional Inspector General for Audit, Eastern Division

Regional Counsel, Region 1

Agency Followup Official (PM-208)

Agency Followup Official (PM-225)
  Attn:  Resource Management Division

-------

                     «.-,'••   SDPERFOND CONSTRUCTION
                     "^"' CHARLES GEORGE WATERLINE SITE ^  '•"",:
                     r,v  _ .TYNGSBORO, MASSACHUSETTS  ,  ' "
L- •-,'" —^"- -,-v:L*.: ^.:^u*;'Sr^^;'£v;>*^
fc " ' ;.;'•.   -".'••>•."• xv '---.-1" ••'.-" ;C "*•*'••'-".• •'"•"  '•'-<-•*•»-;i.«=---x*- ' .^-' '/"-'-/• '""' ••• •  '*.•
R-, -  £   ' ---T- - -?">••» •'• ~-~~Z:'-'•.'* 'V-~-'   ^—^0^^^te-^ '' •V<*iX-a«''•*•<.-«!»•»?-:. y-^f V-•ri"-'' '•• :"•-'•*.. "  - »•'-"
  ."-• --•    "»*,.--•: ..  .'..
  '  ^.;.-*••"- --;.- >i*{•'"
  »£₯%^m%?5^^
           '
                                                                                 •fc»
s^^SP^-;-;--;
                                  released outside the Department «JT
                                       Itnat period lias elapsed^  the
                       ~released>n "^accordance, with the procedures
     ,' prescribed in ~Army .Regulation 34O-17^ and DepartBent of the
     ^.Ar»y"IleHK>randu» 36-1.;-^JBtowever^ "the results  of audit will
     'be Turnished to the  Inspector General,' V. ~S  Environnental
       Protection Hgencjr^'Who'Veauested this audit«'^
       . .  . _^>	 . —__  _ _-*.., _.r *    ^^ _^.**'i ^_ -^f*^^- »^*  ^^r^ •.. _i" .*• .    T^- -* _ ^  i . .. -^T^

-------
                 DEPARTMENT OF THE ARMY
                 OFFICE OF THE AUDITOR GENERAL
                      31OI PARK CENTER DRIVE
                   ALEXANDRIA. VIRGINIA 223O2 IS00
                        21 Kay 1988
Commander, U. S. Army Engineer Division, New England
Commander, U. S. Army Engineer District, Omaha
     This is our report on the Audit of Superfund Construction
for the Charles George Waterline site at Tyngsboro,
Massachusetts.  The audit was made from June 1987 through
March 1988 at your commands and was part of a multilocation
Audit of Superfund Construction.

     Procurement practices used for both the design and
construction  projects at the Charles George Waterline site
were in accordance with  prescribed procedures for contracts
and contract modifications.  Surveillance of the design and
construction contractors was adequate; but, design changes
identified during construction were not properly evaluated for
potential architect-engineer liability.  Except for
receivables, accounting transactions for the design and
construction projects were generally recorded promptly and
accurately.  The U. S. Army Corps of Engineers' direct and
indirect costs for the design effort of the Superfund project
were generally consistent with established procedures; however,
direct and indirect costs for the construction effort were not
fully consistent with established procedures.  Actions to
implement the Army's Internal Control Program as it relates to
Superfund construction were adequate. The results of audit are
summarized in Part I of this report and the details are in
Part II.  Copies of the report are being furnished to the
activities listed in the Annex.
                          <&> HKR
                          U  The
   OLD L. StPCART
The Auditor General

-------
              AUDIT OF SUPERFUND CONSTRUCTION
               CHARLES GEORGE WATERLINE SITE
                  TYNGSBORO,  MASSACHUSETTS
                          CONTENTS


                                                      Page

Letter of Transmitted

PART I    -    SUMMARY

               Preface 	   1

               Objectives and Scope 	   2

               Background 	   3

               Observations and Conclusions  	   3

               Command Reaction 	   8

               Responsibilities and Resources  	   8

PART II   -    FINDINGS, RECOMMENDATIONS, AND
               COMMAND COMMENTS

               A - In-House Costs 	  11

               B - Reimbursement Billings 	  17

               C - Project Design 	  20

ANNEX     -    ACTIVITIES FURNISHED COPIES OF
               THE AUDIT REPORT	  23

-------
                  D. S. ARMY AUDIT AGENCY
               ALEXANDRIA,VIRGINIA 22302-1596

              AUDIT OF SUPKRFUND CONSTRUCTION
               CHARLES GEORGE WATERLINE SITE
                  TYNGSBORO, MASSACHUSETTS
MW 88-6O2                                       27 MAY 1988


                           PART I

                          SUMMARY

PREFACE

     The  Comprehensive  Environmental  Response,  Compensa-
tion,  and  Liability  Act  of  1980  (Public  Law  96-510)
mandated  the  establishment  of  the  Hazardous  Substance
Response Trust Fund, which is  commonly  known as Superfund.
The  Superfund, managed by the  U. S.  Environmental  Protec-
tion  Agency,  was  established  to  respond  to  emergency
hazardous  conditions  and  to  fund  the  cleanup  efforts
required to remove or control hazardous waste substances in
instances when the responsible party cannot  be identified
or will  not  perform  the  cleanup  and  the  State will  not
assume responsibility.  In  February  1982,  the Environmental
Protection  Agency and  the U.  S. Army  Corps of  Engineers
reached  an  agreement  for  the  Corps  to  provide  technical
assistance,  contract for design and construction  work,  and
perform contract  administration ±unctions when  the  Federal
Government  assumes cleanup responsibility  for  hazardous
waste  sites.  The  actual  cleanup  is  accomplished   by
contracting with private firms.  Contract costs are paid by
the Corps and then reimbursed  by the Environmental  Protec-
tion Agency.

     The public law establishing the Superfund requires the
Inspector General, Environmental Protection Agency to audit
Superfund as  appropriate and requires  Federal  agencies to
cooperate   with   the   Inspector  General's   efforts.  The
Inspector  General  requested  audit  assistance  from  The
Auditor  General   of the  Army  in  evaluating  the  Corps'
management  of Superfund cleanup efforts.  Representatives
of The  Auditor  General  and the Inspector General  decided
that an  audit during  1987  of  the Corps' involvement with
Superfund would evaluate the  effectiveness  of  accounting,
procurement,  and   contract  administration   for   selected
Superfund projects  and  evaluate the  appropriateness of  the

-------
Corps' in-house costs charged  to  the projects.  This report
gives  our audit  results  for  the design  and  construction
projects for the Charles George Waterline site.

OBJECTIVES AND SCOPE

     By   agreement  with   the   Environmental   Protection
Agency, the mission of the Corps includes providing techni-
cal assistance  for the  construction of  the  Charles George
Waterline  site,   contracting  for  design  and  construction
work  at  the site,  and  performing the  associated contract
administration functions.  Specific audit objectives for our
review of the Charles George Waterline  site  were to deter-
mine whether:

   - Contracts  and contract modifications were  awarded in
     accordance with prescribed procedures and  if procure-
     ment practices ensured  that services were received at
     fair and reasonable prices.

   - Surveillance of contractor performance was adequate to
     ensure  contract requirements  were  met and  payments
     made to contractors were proper.

   - Accounting  transactions   (obligations,  disbursements,
     receivables,  and collections) were  promptly and accu-
     rately recorded in the  accounting records, and if any
     rejected transactions  were corrected and  reentered in
     a timely manner.

   - Direct and indirect cost  charges were consistent with
     established Corps of Engineers procedures.

   - Actions taken to implement the Army's Internal Control
     Program, as it relates to Superfund construction, were
     adequate.

     The  audit,  performed  from  June  1987  through  March
1988,  was  made   in  accordance  with  generally  accepted
government  auditing standards  and,  accordingly,  included
such tests  of internal  controls as we considered necessary
in the circumstances.   The audit was  an  integral  part of
the multilocation  Audit of  Superfund Construction,  and the
results  will  be  included  in  an  overall  report  to higher
management  levels.  Additionally,  the results of audit will
be  furnished   to  the   Inspector  General,   Environmental
Protection  Agency.   Audit  work was  performed  at Headquar-
ters,  U. S. Army  Engineer  Division, New England;  and at
Headquarters,  U. S.  Army  Engineer  District,  Omaha.  The
audit  covered  transactions that were   representative  of
operations  current  at the time of the audit.

-------
BACKGROUND

     The    Cannongate    Condominiums     in    Tyngsboro,
Massachusetts, are located within 1,000 feet of the Charles
George Reclamation Trust Landfill. The  wells that provided
water for the condominiums were taken out of service during
July 1982 because potential  carcinogens were  found in the
water.   The  Commonwealth   of   Massachusetts  paid   for
construction  of  an  emergency overland  pipeline  system to
furnish water temporarily to the condominium complex.   Tn&
Environmental Protection  Agency  and  the  Commonwealth  of
Massachusetts had private  firms  evaluate  several  alterna-
tives for providing  water  on a  permanent  basis.   Based on
the  study  results,  the  Environmental  Protection  Agency
decided that the best alternative was to construct a water-
line  extending  about 4 miles to  the  condominium complex
and neighboring residential  homes from an existing water-
line which services  the city of Lowell, Massachusetts.   The
Environmental   Protection   Agency   also   decided   that
construction  of the  waterline,  referred to  as the Charles
George Waterline, would be  funded  by the  Superfund Trust
Fund.  Other Superfund projects are planned for cleaning up
the Charles George Reclamation Trust Landfill.

     To  accomplish  the Charles  George  Waterline  project,
the Environmental Protection Agency made  available  to the
Corps about $3.5 million.  The  Omaha District  awarded the
design contract  for the  waterline in  March  1984  and the
construction  contract for  the waterline in  June  1986. The
design contract was  administered by  the Omaha District and
the  construction contract  was   administered  by  the  New
England Division. The construction  contract responsibility
was  transferred  to the  New England  Division  following
contract award because the project  site was located within
the New  England Division's  geographic  boundary.  Construc-
tion of  the waterline  was about  93-percent  complete as of
31 October 1987.

OBSERVATIONS AND CONCLUSIONS

     Contract and contract modifications  for  the Charles
George Waterline  design  were awarded  in  accordance  with
prescribed  procedures,  and  procurement practices ensured
that services were received  at  fair  and reasonable prices.
The design project was  advertised in the Commerce Business
Daily    and    14 architect-engineer    firms    responded.
Preselection  and selection  boards  evaluated  each  firm's
qualifications  and   ranked  the  firms  for  contract  award.
Negotiations  were held with  the  prospective firm selected,
and  a government cost  estimate  was  used to  evaluate the
reasonableness  of the  bid  proposal.  A  firm fixed-price

-------
contract, valued at $101,026, was awarded during March 1964
for route  selection and concept design  for  the waterline.
There were  five  modifications,  valued at $130,170,  to the
design  contract.  Modifications  were  issued  in accordance
with  the   Federal  Acquisition   Regulation   and  Engineer
Federal  Acquisition  Regulation  Supplement.  A  government
cost estimate  was  used for each modification and negotia-
tion results were documented.

     Contract  and  contract  modifications  for  the  Charles
George  Waterline  construction  were awarded  in accordance
with  prescribed   procedures,   and   procurement  practices
ensured that services  were  received at  fair  and reasonable
prices.  The construction  contract was  advertised  in  the
Commerce Business  Daily and  three  prospective contractors
responded.  A government cost estimate was used to evaluate
bid  proposals  received,   and   the  lowest   bid  proposal
submitted  by  a responsive  contractor  was  selected  for
contract  award.  A firm fixed-price  contract  for  about
$2.9 million-vis awarded during June 1986 for the construc-
tion    project.    There   were   five    issued   contract
modifications,   valued  at   $93,766,  as  of  31 July  .1087.
Modifications  were issued  in accordance with  the  Tcderal
Acquisition  Regulation  and  Engineer  Federal  Acquisition
Regulation  Supplement.  A government  cost estimate was used
for each  modification that  met the dollar criteria  for an
estimate and the negotiation results were documented.

     Surveillance  of   the  design contractor's  performance
was  adequate  to   ensure  that  requirements   were met  and
payments  made  to  the contractor were  proper. All  design
products  required  by  the  contract were submitted  by  the
contractor, and promptly reviewed by the Corps.  Corps per-
sonnel  verified that  services were  performed before giving
approval to 11 requests for progress payments received from
the contractor.

     Surveillance  of  the construction  contractor's  perfor-
mance was  generally adequate to ensure that  the contract
requirements were met  and payments made to contractors were
proper,  but   information   on  apparent  design  omissions
identified  during  construction  was not properly assessed
for possible  architect-engineer  liability  as  required by
regulatory   guidance.   Corps    inspectors    made   daily
observations of construction  progress to ensure provisions
and  specifications   of  the  contract  were  being  met.
Inspection  reports were prepared,  and  deficiencies noted
were  monitored until  resolved.  Monthly progress  reports
were  sent  to the  Environmental   Protection  Agency  as
required by the  interagency agreement.  Cumulative progress
payments  of about  $1.8 million for  the period  September
1986 • through  June  1987  were  proper  except  for  about

-------
$143,000.  The  first  progress payment  for September  1986
included about $142,000 for mobilization expenses;  however,
mobilization was  not  a  line  item  of  the contract or  an
allowable  expense  for progress  payments. Corps  personnel
recognized the error  and made an  appropriate  adjustment to
the fifth progress payment. The contractor received payment
of about  $142,000  about 9 months too soon because  of  the
error  concerning  mobilization  expenses.  The  contractor
was also paid $920 twice on  the third progress payment  for
pipe used  for a  stream crossing.  An adjustment  for  this
double  payment  was  made  on the ninth progress  payment.
During  construction,  changes  were   made and,   in  some
instances, design omissions were cited as the  basis for  the
changes.  Information on the  apparent design  omissions  was
not furnished to the design activity as required by regula-
tory  guidance,   and  local   guidance  did   not   include
procedures for projects where design was accomplished by an
activity other than  the construction  division. Action  was
needed to  furnish information on  apparent design  omissions
to  the  design  activity so  the  potential for  architect-
engineer  liability  could  be  assessed and determinations
documented.

     Except  for  receivables,  accounting  transactions  for
the  design   and   construction  projects  were   generally
recorded  accurately  in  the   accounting  records,   but  many
transactions  were  not   recorded  in  a  timely   manner.
Rejected  transactions  were  corrected and generally reen-
tered to the accounting records in a timely manner.

   - Obligations of  about  $230,000  were  recorded  for  the
     design  effort   during  March   1984  through  September
     1986,  and  obligations  of  about  $3.3  million  were
     recorded for the  construction  effort during  September
     1984  through  May   1987.  An   obligation   for   the
     construction  contract  was  accurately  recorded  for
     about $2.9 million but  it was  recorded 6 months after
     contract award. The design contract  and  modifications
     to  both the design and  construction contracts  were
     obligated in the month  issued.  Labor,   overhead,  and
     various small expenses such as  supplies or vehicle use
     were  obligated  in  the  month  of the  expense  using
     miscellaneous  obligation  documents.  A  reimbursable
     order   issued   for   the  construction   project   was
     obligated in the  month  the order was accepted. - Travel
     was  obligated  in  the month  the  travel -orders  were
     issued, but an obligation of $585 was recorded twice;
     a correction was later made by  Corps personnel.

-------
Disbursements of about  $226,000  were  recorded for the
design  effort  during  March 1984  through  September
1986,  and disbursements  of about  $1.4 million  were
recorded  during September  1984  through May  1987 for
the  construction effort.  In total,  35  transactions
were recorded.  Disbursements were made  for  construc-
tion and  design contractor  invoices,  purchase orders,
travel vouchers, imprest fund purchases, and reimburs-
able order invoices.  All but 1 of the 28 disbursement
transactions  reviewed  were promptly  and  accurately
recorded  within 30  days of the  approval  for payment.
The other disbursement was recorded accurately 36 days
after approval  for payment.

Receivables  of  about $290,000 were  recorded  for the
design  effort  during  March 1984  through  September
1986,  and  receivables  of  about  $1.9 million  were
recorded  during September  1984  through May  1987 for
the  construction effort.   In  total,  34 transactions
were recorded.  The  receivables  were based on monthly
bills sent to the Environmental  Protection Agency.  Of
the  17 receivable   transactions   reviewed,   16  were
promptly  and accurately recorded within the same month
that  bills  were  sent  to  Environmental  Protection
Agency   for   reimbursement.  The  other   receivable
transaction,   recorded  during  December  1986  for the
construction  effort,  overstated  Corps  earnings  by
about  $521,000;  this  amount  was  included  in  the
January bill  sent  to Environmental Protection Agency
for  reimbursement.   Monthly billings  were  suspended
during  June   1987  to  make  up   for  the  overbilling;
however,  contract costs of about  $1 million were not
billed  after   the   overbilling   was   corrected.  The
U. S. Treasury  incurred interest costs that could have
been avoided  had the billings been made.  Action was
needed to bill  the Environmental Protection Agency -for
contract  costs  not  billed  and  to  resume  monthly
billings.

Collections  of  about $283,000 were  recorded  for the
design  effort  during  March 1984  through  September
1986,  and  collections  of  about  $1.3 million  were
recorded  during September  1984  through May  1987 for
the  construction effort.   In  total,  27 transactions
were  recorded.   Of   10 collections reviewed,  8  were
promptly  and  accurately recorded within  3 workdays
after  receipt  of the check.  The other two  collec-
tions  were  recorded  accurately  4  and  30 workdays,
respectively, after receipt of the checks.

-------
   - A total  of 26 rejected  transactions occurred  during
     March  1984 through September  1986  for  the  design
     effort, and 117 rejected  transactions  occurred  during
     January through June 1987 for the construction effort.
     Of  the  25 rejected transactions  reviewed,  15  were
     corrected  in the  same  month,  7 were corrected  in the
     next month,  and  3  were  corrected  2  or more  months
     after the reject occurred.

     Direct and indirect Corps costs charged  to  the  design
project  were  generally  consistent  with established  Corps
procedures.  As of September 1986,  in-house costs  were about
$64,000.. According  to Engineer Regulation 37-2-10,  in-house
expenses such as labor,  travel, supplies,  and reimbursable
orders that can be  directly related to  a specific  Corps
project should be charged to the specific project.  Overhead
and indirect costs  are then charged to the project based on
a predetermined  rate  applied to actual direct labor  hours
incurred.  Of  about  $21,000  of  in-house  costs  reviewed,
about  $20,650  was  appropriately  charged as  expenser  that
directly  benefited the  Charles  George  Waterline  design
effort. Reviewed costs included expenses for labor, travel,
reproduction,   supplies,  and  reimbursable  work.  Costs  of
about  $350 for labor,  associated  overhead,  and  indirect
expenses of one Corps  employee were  incorrectly  charged to
the  project because  of  a  coding  error.  We advised  the
finance  office  of  the discrepancy.  The only overhead and
indirect costs  charged to the design project were amounts
based  on direct labor hours.  Overhead and indirect  costs
charged to  the  Charles George  Waterline  design effort were
based on the same allocation method  and  rates used for all
projects performed by the Omaha District.

     Direct and indirect Corps costs  charged against  the
construction project were not  fully  consistent with estab-
lished Corps procedures.  As of July 1987, in-house costs of
about  $248,000 were   charged  to  the  project.  Actual
expenses and obligations exceeded the  amount  authorized in
the  interagency agreement  by  about $45,000 and  $57,000
respectively,    when   the  project   was  only   75-percent
complete.  Although  in-house  costs  exceeded  the  amount
authorized,   total   funds  authorized  by  the  interagency
agreement   were not  exceeded.  Rather  than   requesting
additional fund authority from the Environmental  Protection
Agency,  expenses  totaling about  $34,000 were  transferred
from  the project  to  an  indirect cost  account  and  later
absorbed by other  reimbursable work. New  England Division
needed to request an amendment to the interagency agreement
for  additional  fund  authority  to  complete  the  project.
The  actual  direct  and  indirect  expenses transferred from
the  project  should  be  charged  back   to  the  project.

-------
Conversely, inappropriate costs totaling  about  $18,400 for
labor and travel were  charged  to  the  project  and billed to
the  Environmental  Protection  Agency.  The  inappropriate
charges  resulted  in  funds  intended  for  the  Superfund
project  being  used   to  finance  other   Corps- missions.
Periodic  reviews  of accumulated  obligations and  expenses
versus authorized  ceilings  were  needed.  Also,  action was
needed to transfer the inappropriate charges to the correct
account and to require Corps personnel working on Superfund
projects to sign their timesheets attesting that Superfund
charges  are  valid.  The only  overhead and indirect  costs
charged to the  construction project were amounts  based on
direct labor  hours and were based on the  same allocation
method and  rates  used for  all projects  performed by New
England Division.                                 •

     Actions taken to implement the Army's Internal Control
Program,   as   it  relates  to Superfund construction,  were
adequate.  Superfund functions  were  not  designated  as  a
separate assessable unit but rather the various aspects of
Superfund  functions were  included in several  assessable
units. No DA or Corps internal control checklists published
specifically for  the Superfund functions were available at
the time of our review. Both Omaha District and New England
Division required key managers with Superfund responsibili-
ties to have internal control responsibilities in their job
descriptions  and  performance  standards.  Omaha  District
completed  10  internal  review   checklists   during   the
19 months ending June 1987;  10 more were in progress at the
time  of  our  review.   New England Division completed  four
internal  control  checklists  during  the  19 months  ending
June 1987 and eight were in progress.   Some of these check-
lists related to aspects of Superfund functions.

COMMAND REACTION

     The  Commander,  U. S.   Army  Engineer  Division,   New
England,  agreed  with  the findings and stated  that correc-
tive  actions  had  been   or   would  be  taken   on   all
recommendations.  Detailed  command comments are presented
after each recommendation  in Part II  of  this  report.   The
Ariry's official position on the findings, recommendations,
and command comments will be established  when the official
command-reply process prescribed by AR 36-2 is completed.

RESPONSIBILITIES AND RESOURCES

     By  agreement,  the Corps  of  Engineers is  responsible
for managing the design and construction of Federal cleanup
sites paid for by  the  Environmental  Protection Agency with
money from the Superfund trust fund. Design work is managed
within the Corps'  Missouri  River  Division and construction
                             8

-------
is  managed  by  the  Corps'   district   or  division  with
jurisdiction over  the geographic  location of  the  cleanup
site.  The   Environmental   Protection  Agency   authorized
$295,682 for  the design of  the Charles  George Waterline;
$230,622 was for  the  contract and  $65,060  was for  the
Corps'  in-house  costs.  For   the  construction  project,
$3,471,914 was authorized; $3,268,614 was for the contract
and  $203,300  was for Corps'  in-house  costs.  Engineering,
construction, contracting, and resource  management person-
nel  are  directly  involved   in   carrying  out  Superfund
functions at the performing Corps'  districts or divisions.
The Commander, U. S. Army Corps of Engineers is responsible
for  ensuring  that  action is  taken on the recommendations
addressed to the New England Division.

-------
                          PART II

      FINDINGS. RECOMMENDATIONS.  AND COMMAND COMMENTS

                    FOR THE COMMANDER,
         U. S. ARMY ENGINEER DIVISION,  NEW ENGLAND


                    A - IN-HOUSE COSTS

FINDING

     In-house  costs  for  the  Charles   George  Waterline
construction  project  were   not  properly  recorded   and
managed. As  of 31 July 1987,  when  the  project  was  about
75-percent  complete,   recorded  expenses  and  obligations
exceeded the amount authorized in the interagency agreement
by  about $45,000  and $57,000 respectively,  but had  not
exceeded   total   funds   authorized   by   the   interagency
agreement.  U. S. Army Engineer Division,  New England  had
not established  effective procedures for monitoring  costs
and estimating  future  needs to  complete the  work.  Rather
than   requesting  additional  fund  authority   from   the
U. S.  Environmental Protection Agency, appropriate charges
totaling about $34,000 were transferred from the project to
an indirect cost account.  As  a  result,  other  reimbursable
work in the New England Division  absorbed costs incurred in
support  of  the  waterline  project.  At  the  same  time,
inappropriate  costs  totaling about  $18,400  for  labor  and
training were  charged  to  the waterline  project and billed
to the  Environmental Protection  Agency.  Division personnel
did not  sign  their timesheets  att-s'-ting  to the validity of
Superfund  labor  charges.  Also,  the   cost  for  general
training   courses  was   charged   apparently   because   the
project  had  available  funds at  the  time of the training.
The inappropriate  charges resulted  in funds  intended  for
the  Superfund project  being  used  to  finance  other  New
England Division missions.

                        DISCUSSION

1.   Background.  Each government agency is directed by law
to establish  and maintain an  adequate  system of accounting
and    internal   control    over    obligations,    accrued
expenditures,  applied  costs,  and outlays.  The U. S.  Army
Corps   of   Engineers   uses  the   finance  and  accounting
subsystem of  the Corps of Engineers  Management Information
System  to  record accounting  transactions for site-specific
funds provided  by  the Environmental Protection Agency  for
Superfund   work.   Engineer   Regulation 37-2-10   provides
guidance concerning the accounting treatment of the Corps'
in-house costs for Superfund work. The general rule is that
                             11

-------
costs which directly  apply to  a  specific  project should be
charged to that project.  The interagency agreement between
the Corps  and the Environmental Protection Agency  for  the
Charles  George  Waterline construction  project  gives  an
authorized    ceiling    for   in-house    costs.    Engineer
Regulation 1110-2-500  provides  guidance   for  requesting
changes to Superfund interagency agreements.

2.   Recorded Costs.  Actual in-house costs for the Charles
George Waterline  construction  project  exceeded the ceiling
authorized  by  the  interagency  agreement,  but  had  not
exceeded total funds authorized.   Instead of requesting the
additional needed fund authority,  in-house costs incurred
in direct  support of  the waterline were transferred  to an
indirect  account that  was allocated  to  all  reimbursable
construction work being performed by New England Division.

     a.   Authorized Ceiling.   The ceiling for  the  Corps'
in-house costs was  exceeded before the construction of the
waterline was complete.  The interagency agreement provided
$203,300  for  the Corps'  in-house costs.  As of  31 July
1987,  when  the  project was  about  75-percent  complete,
recorded  in-house  expenses  totaled  $247,864,  or  about
$45,000  over  the  ceiling;  recorded  obligations  totaled
$260,729,  or  about  $57,000   over  the  ceiling.  In-house
costs will continue until the project is  completed during
1988.  Recorded in-house expenses over the authorized ceil-
ing  as  of 31  July  1987 were  billed  to  the  Environmental
Protection Agency and reimbursed from the Superfund  trust
fund.

     b.   Monitoring of Costs.   New  England  Division  had
not established effective procedures for monitoring the use
of in-house fund  authority or estimating the need for addi-
tional authority.  Personnel of  the New  England Division's
Construction Division  told us  that some  reviews  were made
of accumulated direct labor costs and associated indirect
and New England Division overhead costs.  However, there was
no set schedule for the reviews,  such as at certain comple-
tion points  during the project.  Other  in-house expenses
such as  laboratory  costs and  reimbursable  orders to  other
Corps elements were not monitored.  As a result, personnel
of the Construction Division did not  know the actual  total
of in-house costs incurred. Periodic  estimates of in-house
funds needed to  complete the waterline were also not made.
Without such estimates  and periodic  reviews o.f accumulated
obligations  and  expenses  against  authorized  ceilings  for
Superfund work,  personnel  did  not  have sufficient informa-
tion  for  controlling  in-house  expenses  and  requesting
additional fund authority when necessary.
                             12

-------
     c.   Cost: Transfer.  In-house costs  of  about  $34,000
were  transferred from  the  construction project's  account
during  September 1987  to an  indirect cost  account.  The
costs  represented direct  labor  plus  associated  indirect
costs  and  New England  Division's  overhead costs for five
Corps  personnel  who  had performed work  in support  of the
construction   project.   Construction  Division   personnel
assumed that  the in-house cost ceiling of  the interagency
agreement  was a not-to-exceed  limit that  could  not  be
changed; therefore,  an amendment  to increase the  ceiling
was  not requested.   The  cost  transfer was  an  attempt  to
reduce  recorded  expenses below the authorized ceiling; but
because the total amount  of in-house costs were not known
and only labor expenses were considered, the  transfer made
did   not   meet   the   intended  objective.  Costs   charged
against the  indirect costs account  were  allocated  to all
reimbursable construction projects being performed;  there-
fore the transfer of  about  $34,000 of  expenses resulted in
other reimbursable work absorbing costs incurred in support
of the waterline construction project.

     d.   Aaendaent.   An  amendment   to  the  interagency
agreement  should have been  requested if the  in-house cost
ceiling was insufficient to cover the Corps' actual  cost to
manage  the project.   Guidance  on  requesting  amendments  to
Superfund  interagency agreements  is included in  Engineer
Regulation 1110-2-500.  The timely request  for an amendment
by New England  Division  and a favorable  response  by the
Environmental Protection Agency would have  negated the need
for  a  cost  transfer due to  an  authorized  ceiling  being
exceeded.

3.   Inappropriate Charges.   About $18,400  was  improperly
charged  to  the Charles   George Waterline   construction
project for Corps' expenses relating to labor and  travel,
including  the  cost  of  general  training.  Improper  charges
were  about 7 percent  of the recorded  in-house expenses as
of  31 July 1987.  The  inappropriate  charges resulted  in
funds  provided by the Environmental  Protection  Agency for
the  waterline project  being  used  to finance  other  New
England Division missions.

     a.   Direct: Labor.  Labor was charged  to the waterline
construction project  for  four  Corps  personnel who  had not
performed services in support of  th-^ construction  project.
We interviewed  11 of  19  individuals who  had direct labor
charged to the  project and determined  that 2  had never
worked  on the project.  The value  of  their direct labor and
the associated indirect and New England Division overhead,
about  $3,900, should  not have been charged  to the  project.
After we discussed the inappropriate  labor  charges with the
                             13

-------
project manager, two  other  individuals  were identified who
had not worked on the project but had about $7,900 of their
direct, labor and associated indirect  and division overhead
charged to  the  project.   A cost transfer was  initiated by
the  waterline   project  manager  during  September 1987  to
reduce the recorded in-house costs by about $11,800 for the
inappropriate labor  charges  of  the  four  individuals.  In
our  Audit  Report  MW 86-605,  Superfund Management,  dated
24 April 1986,  we recommended that all employees performing
work   on   Superfund   projects   sign   their   timesheets.
Headquarters, Corps of  Engineers agreed and  reported that
the  recommendation had  been  implemented.  Timesheets  for
Corps  personnel working  on  the  waterline  project  were
prepared and signed by  timekeepers; the employees  had not
signed the timesheets.  A signature by the employee attest-
ing that Superfund charges  were  correct may have prevented
the inappropriate charges to the waterline project.

     b.   Travel.  Travel costs were  charged  to the water-
line  construction  project   for   11  trips   that  did  not
specifically benefit  the  project.  According  to Engineer
Regulation 37-2-10,   costs   that   cannot   be   d-r^ctly
associated with a  specific  project should be  charged co an
indirect  or overhead  account.  The  interagency agreement
for the waterline project also states that reimbursement is
to be for actual costs  incurred.   During July 1986 through
May 1987, travel  costs  for  18 trips  totaling  about $4,200
were charged to the project.   We  reviewed the appropriate-
ness of  12  of  these  charges  and  found that  11, totaling
about $3,200, were for  travel to  general  training courses
such   as   contract  negotiating,   network   analysis,   and
manpower distribution.  Although the  11  travel  charges may
have provided  some benefit  to the waterline  project,  the
training was  not technical  training  in direct  support of
the project.  The expenses  should  have been charged  to an
indirect  or overhead account.  Corps  personnel said  the
expenses were charged to  the waterline project because the
project had available funds  at  the time of  the training.
Documentation was  not retained  on the  other  six expenses
for travel  so we could not review them for appropriateness
of charges to the waterline construction project.

     c.   Labor During Training.  Along  with   the  travel
expenses, labor costs of  about $3,400  for  the employees'
time while  attending  the general  training  were charged to
the  waterline  project.  The  expenses  should  have  been
charged  to   an  indirect  or  overhead  account  because  the
labor  costs  did   not  directly   support   the  waterline
construction project.
                             14

-------
RECOMMENDATIONS AND COMMAND COMMENTS

A-l  Issue local written guidance:

   - Establishing  a  requirement for  periodic  reviews  of
     accumulated obligations  and expenses  against  autho-
     rized ceilings  for Superfund work.  Specify  that  the
     reviews  cover all costs,  not  just  direct labor  and
     associated indirect and overhead  costs.  Also, require
     that periodic estimates be made of the amount  of funds
     needed to complete the work.

   - Reemphasizing the requirement  for charging  in-house
     expenses  to  Superfund  projects  and  the need  for
     requesting amendments to  Superfund interagency agree-
     ments when required.

Command agreed and stated  that the  Construction Division's
Quality Assurance  Branch  was directed  on  19  February 1988
to establish  procedures to track and review  all costs  for
Superfund  projects.  Emphasis  will  be  placed  on  ensuring
that all costs associated with a project are charged to the
proper   accounts.  Accumulated  project   costs   will   be
reviewed  on  a quarterly  basis  and  project  cost  tracking
will  begin   within   one  month  after  receipt   of  the
contractor's  work  schedule  for the construction  project.
The  quarterly reviews  will  consider the  amount  of  funds
needed  to  complete  the   project  and,  when  appropriate,
additional funding or  a  change in  an  authorized ceiling
will be requested from the Environmental Protection Agency.

A-2  Determine the total amount of  in-house costs  incurred
to  date  for  the  Charles George  Waterline  construction
project  and  estimate   the  cost needed  to  complete  the
project.  Compare  this total to the  ceiling authorized for
in-house costs by  the  interagency  agreement and request an
amendment to  the interagency agreement  for the  difference.
Move the  in-house  costs of about $34,000  transferred from
the project during September 1987 back to the project.

Command agreed and stated  that all  costs,  current  and pro-
jected,  associated  with  the  Charles  George  Waterline
construction  project will  be  determined  and corrected.  A
change  to thd  interagency agreement  will be  coordinated
with the Environmental Protection Agency by fourth quarter,
FY 88.

A-3  Require Corps personnel who work on Superfund projects
to sign their timesheets attesting that the time charged to
Superfund projects is valid.
                             15

-------
Command  agreed  and  stated  that  personnel  who  work  on
Superfund  projects were  directed  on  19 February 1988  to
sign-their  timesheets in order to support the  validity  of
time charges.

A-4  Transfer the inappropriate expenses for travel,  total-
ing  about   $3,200,   and  labor,   totaling   about  $3,400,
during general  training from the  Charles George Waterline
construction  project  to  proper  indirect  or  overhead
accounts.

Command  agreed  and stated  that  the  cost transfer will  be
completed by fourth quarter, FY 88.
                             16

-------
                    FOR THE COMMANDER,
         U.  S. ARMY ENGINEER DIVISION,NEW ENGLAND
                 B - REIMBURSEMENT BILLINGS

FINDING

     New  England  Division  did  not   properly  bill  the
Environmental Protection Agency for contract costs incurred
for the Charles George Waterline construction project.  The
January 1987  billing  included about $521,000  for contract
costs  not  yet  incurred.  Monthly billings were  suspended
during June 1987 to correct the overbilling. However, after
the  overbilling  was  corrected,  contract  costs  of  about
$1 million  were  not  billed.  Billings  were  not  resumed
because  a  new  individual   became responsible   for  the
billings,  and that individual did  not  know the  status of
corrective  action for  the  overbilling or  when  to  resume
billings.  Untimely billings resulted in $4,800 of needless
interest expenses for the U.  S. Treasury.

                        DISCDSSIOH

1.   Background.  Interagency  agreements  between  the Envi-
ronmental Protection  Agency  and the Corps  are established
to  provide  the  necessary funding  for Superfund projects
managed by  the Corps.  An agreement,  such  as the  one for
the  Charles  George Waterline  project,  provides  the Corps
with program authority for a specified timeframe.   As costs
are  incurred,  the Corps establishes an account receivable
and  bills  the  Environmental  Protection Agency  for  the
amount   spent.  The    Environmental    Protection   Agency
reimburses the  Corps  with a check from  the  Superfund trust
fund  for  deposit to  the  U.  S. Treasury.   The  New  England
Division  operates  on  an  accrual  basis  of  accounting.
Estimates are recorded in  the accounting  records  at the
beginning of  each month for expected  contract and in-house
costs. The  estimates  are then reversed when  corresponding
actual costs are recorded.  The automated accounting system
used by New England Division generates  a  bill to  the Envi-
ronmental Protection  Agency  around the 15th of  the month
for  costs  recorded against Superfund  projects during the
previous month.

2.   Billings.  Billings  were  not  properly   sent  to  the
Environmental  Protection   Agency   for   contract   costs
incurred  for  the Charles  George  Waterline  construction
project.  New  England Division paid the  construction con-
tractor a total of about $2.9 million  through 30 November
                             17

-------
1987; however,  only  about  $1.9  million  of these costs were
billed  to   the  Environmental   Protection  Agency   as  of
31 December  1987.

     a.   Early Billings.  About $521,000 was billed on the
January 1987 billing for  contract  costs that had  not yet
been incurred.  Contract costs  were overstated  because an
estimate of •costs recorded at the beginning  of  the period
was  not  reversed when  actual  costs   were  recorded.  The
automated accounting system included both the estimated and
actual  costs  on   the  billing  sent to the  Environmental
Protection   Agency,  and  New  England   Division  received
reimbursement  for the  billing  during   April  1987.  Corps
personnel identified the overbilling during June  1987 and
decided that monthly billings for contract  costs would be
suspended until accumulated actual costs exceeded the total
amount billed.

     b.   Late  Billings.  About  $1 million was  not billed
during the months  after contract costs were recorded.  With
the ninth progress payment to the contractor during August
1987,  accumulated actual  costs  exceeded the  total amount
billed.  But, billings for contract  costs were not  resumed
and no billings were submitted  during the period September
through December  1987. Progress payments to  the contractor
during  this  period  exceeded the total  amount billed by
about  $1 million.  A new  individual became  the accountant
in  the  Civil  Funds Section  of New  England  Division's
Finance and Accounting Office during the fall of 1987.  The
new accountant  did not know the status of corrective action
for the overbilling  or have  an  understanding of when bill-
ings should be  resumed.

3.   Funds.   Improper  billings  for  the  construction  con-
tract  costs  resulted  in  interest  costs  to  the  U. S.
Treasury that could have been avoided.

     a.   Honey Froa the  Trust Fund.   The  U.  S.  Treasury
had the use  of  money from  the Superfund trust fund earlier
than provided by the interagency agreement for the contract
c^sts  billed too early.  About  $521,000 received during
April 1987 was  available too soon.

                            Number of Months
              Amount'       Available Too Soon

              $452,730              3
                68.180              4

              $520.910
                             18

-------
     b.   Use  of Appropriated Funds.  Appropriated  funds
were used longer than  necessary for  contract costs  that
were not billed.

                           Number of Months
              Amount     Longer Than Necessary

             $370,915             4
              191,141             3
              254,960             1
              138.908             1

             $955.924

When the  Corps pays for  incurred costs with appropriated
funds,  the U. S. Treasury has  to  borrow  and incur interest
until reimbursement is received from  Superfund trust fund.
Using an annual rate of 7 percent and assuming a consistent
number of days for collection of billings sent to the Envi-
ronmental  Protection Agency,  about  $14,300  in  interest
accrued  for  contract  costs not  billed.  This amount  was
offset, however, by about $9,500 in interest avoided to the
U. S. Treasury due to the inappropriate early billing.

RECOMMENDATIONS AND COMMAND COMMENTS

B-l  Determine the total amount of  contract costs incurred
for the Charles  George Waterline  construction project  that
have  not  been   billed   and  submit  a   billing  to   the
Environmental Protection Agency.

B-2  Resume monthly  billings to  the  Environmental  Protec-
tion Agency  for  contract  costs  incurred  for the  Charles
George Waterline construction project.

Command agreed with Recommendations B-l  and B-2  and stated
that billings were aggressively worked and monthly billings
to  the Environmental  Protection  Agency  were resumed  in
March 1988.
                             19

-------
                     FOR THE COMMANDER,
         D. S. ARMY ENGINEER DIVISION, NEW ENGLAND
                     C - PROJECT DESIGN

FINDING

     Procedures   used  to  investigate   potential   design
omissions  for the  Charles  George Waterline  construction
project  were not in  accordance with  regulatory  guidance.
Construction  Division  personnel  at  New England  Division
decided that there was no possibility of architect-engineer
liability.  Therefore,  information pertaining  to  potential
liability was not provided  to  the responsible activity for
review,  and documentation  supporting  liability  determina-
tions was not included in the  contract files.  Information
on  apparent  design  omissions  was  not  furnished  to  the
responsible  design  activity  because  local  implementing
procedures did not  cover instances where design  was accom-
plished by an activity other than the New England Division.
As a result, proper liability  determinations were not made
for  construction contract  changes  totaling  about  $76,000
and  a  complete  record of the  architect-engineer's  perfor-
mance was not maintained for use in evaluating the firm for
future services.

                         DISCUSSION

1.   Background.  Architect-engineer     contractors     are
responsible   for   the   professional  quality/   technical
accuracy, and coordination  of all  services  required under
their contracts.  An  architect-engineer  firm may  be liable
for government costs resulting from errors and deficiencies
in designs  furnished  under the firm's  contracts.  When  a
modification  or  change  to  a  construction  contract  is
required because  of an error or deficiency  in the services
provided under an architect-engineer  contract, the  Federal
Acquisition  Regulation  requires   that  the  potential  for
liability of the architect-engineer  be evaluated  and the
results  documented  in  the  contract  file.   Procedures  and
responsibilities  within the Corps of Engineers for investi-
gating  and  pursuing possible  architect-engineer  liability
are  included  in Engineer  Regulation 715-1-10  and  local
procedures  are  included in  New  England Division Engineer
Regulation 1180-1-11.

2.   Evaluation.  The   potential    for  architect-engineer
liability  was not   assessed  by  the  proper activity  for
possible design  omissions at the  Charles George  Waterline
site.  As of 31  July  1987,  the construction  contract had
                             20

-------
seven changes  issued  or pending valued at  about $187,000.
Of  the  changes  initiated by  New  England  Division,  four
valued-at about $76,000 specifically cited design omissions
as the reason for the change. For example, one construction
change  involved  materials  and  dimensions  for  a  culvert
different from those  specified in the plans.    Lack  of an
onsite review during design was given as the reason for the
change.

     a.    Documentation. New England's Construction  Divi-
sion personnel told us  that  they had evaluated each change
and  had determined  that no  potential liability  existed.
Determinations made on the potential for architect-engineer
liability were not documented  and  included in  either the
architect-engineer or construction contract files,  and per-
sonnel  at  the U.  S.  Army  Engineer  District,   Omaha,  the
design  activity,   did not  make any liability  reviews  so a
final    conclusion     was     not    documented.  Engineer
Regulation 715-1-10 requires  that a  written  determination
be  made for  all  apparent  design  omissions  covering the
extent  of  liability  and the  appropriateness of  pursuing
recovery action.  In addition, the results of investigations
should  be  reflected in  the  architect-engineer performance
evaluation  and  considered  when selecting  future  design
contractors.   Without   documentation,   architect-engineer
firms may not be  held accountable for their mistakes.

     b.    Coordination.   According to  Engineer  Regulation
715-1-10, when construction  is  accomplished by an activity
different than the design activity,  the design activity has
responsibility for investigating  and pursuing  architect-
engineer   liability.   The   construction   activity   has
responsibility for providing  all necessary  information and
cooperating  fully  with  the  design  activity.  New England
Engineer Division Regulation 1180-1-11 does not address the
situation where different activities perform the design and
construction efforts. Omaha  District,  the design activity,
was  aware  of construction contract changes and  acted as a
liaison  between   the  architect-engineer  firm  and  the
construction activity.  But Omaha District did not have all
information  necessary to  assess for  potential  liability.
Personnel at  the  design activity are  in  a  better position
to  investigate for potential  liability because they have a
more thorough knowledge  of the design issues  affecting the
project.
                             21

-------
RECOMMENDATIONS AND COMMAND COMMENTS

C-l  Provide  Omaha District with  complete information  on
potential design   omissions  for the Charles  George  Water-
line    site.   Request    written  documentation   on    the
determinations be  returned to the  New  England Division for
inclusion in the construction contract file.

Command agreed  and stated that all  contract  modifications
indicating  design  deficiencies  for  the  Charles  George
Waterline  construction project  will  be forwarded  during
third quarter FY 88 to the Omaha District for investigation
of possible architect-engineer liability.

The  Commander,  U. S.  Army Engineer  District,  Omaha  also
provided  comments  on  the  finding  and  recommendations  and
stated  that,  after receipt  of  documentation from the  New
England Division,  a  review will be  conducted for possible
architect-engineer liability on actions  considered to  be a
result of design errors.

C-2  Revise    New  England  Division  Engineer  Regulation
1180-1-11  to  include  procedures  for  architect-engineer
liability review  in  instances  when the  design  activity is
outside the division.

Command  agreed and  stated  that procedures for architect-
engineer  liability  review  in  instances when  the  design
activity  is  located  outside the division will  be included
in a fourth quarter,  FY 88 revision of New England Division
Engineer Regulation 1180-1-11.
                             22

-------
                                                     ANNEX
Copies of this report are being furnished  to  the following
activities:

Inspector General, U.  S.  Environmental Protection Agency
Assistant Secretary of the Army (Civil Works)
Assistant Secretary of the Army (Financial  Management)
The Inspector General
Director of the Army Staff
Chief of Public Affairs
Deputy Chief of Staff  for Personnel
Deputy Chief of Staff  for Logistics
Chief of Engineers
Commanders
  U. S. Army Corps of  Engineers
  U. S. Army Criminal  Investigation Command
  First Region, U. S.  Army Criminal Investigation Command
Commandant, U. S. Army Logistics Management College
This report is not to be released outside the Department of
the Army  for  60 days.  After that period  has elapsed, the
report may  be released  in  accordance with  the procedures
prescribed in Army Regulation  340-17  and Department of the
Army Memorandum  36-1.  However,  the results  of audit will
be furnished to  the  Inspector  General,  U.  S. Environmental
Protection Agency, who requested this audit.
                             23

-------