REPORT  TO  CONGRESS:

EXTENDING  THE  USEFUL  LIFE OF  SANITARY  LANDFILLS

           AND  REUSING  LANDFILL  AREAS

                    (PHASE  ONE)
               Office of Solid Waste
        U.S. Environmental Protection Agency
                     March 1987

-------
                        ACKNOWLEDGEMENTS
     This report was prepared for the Special Wastes Branch,
Office of Solid Waste, U.S. Environmental Protection Agency by
two organizations.  Dr. James Noble at the Center for Environ-
mental Management, Tufts University, prepared Part One entitled
Cooperative Landfill Arrangements, under an EPA grant.  Part
Two, Methane Production from Closed Landfills, was prepared
by SCS Engineers under EPA Contract No. 68-01-7290.  SCS
personnel involved were Gary Mitchell and Gregory Vogt.  The
EPA Project Officer on both parts was Michael Flynn, and the
EPA reviewers were Allen Maples and Allen Geswein.

-------
                        TABLE OF CONTENTS
EXECUTIVE SUMlnAKY	  LS-1

LIST OF EXHIBITS
   Part I	  v
   Part II	vi
           PART I - COOPERATIVE LANDFILL ARRANGEMENTS

SECTION 1 - Introduction	  1-1
SECTION 2 - Rationale and Background for Cooperative
            Landfills	 2-1

2.1  Motivation for Cooperative Landfill Arrangements	 2-1
2.2  Economies of Scale	 2-2
2.3  Structure of Cooperative Arrangements	 2-4
2.4  Current Practice of Cooperative Landfillin-j	 2-5
2.5  Case Examples	 2-8
2.6  Potential Barriers to Cooperative Landfilling	 2-11
2.7  Overcoming The Barriers	 2-12
2.8  References	 2-13
SECTION 3 - Establishing Cooperative Landfill
            Arrangements	 3-1

3.1  Process for Developing a Cooperative Arrangement	 3-2
3.2  Role of Public Participation	 3-2
3.3  Forms of Organization	 3-3
3.4  Elements of a Cooperative Arrangement	 3-5

     3.4.1  Management Issues	 3-7
     3.4.2  Facilities Issues	 3-7
     3.4.3  Regulatory Issues	 3-7
     3.4.4  Liability Issues	 3-8
     3.4.5  Operational Issues	 3-9
     3.4.6  Cost Issues...	 3-9

3 .5  Implementing An Arrangement	 3-10
3.6  Roles of State and Federal Government	 3-14
3. 7  References	 3-15
SECTION 4 - Solid Waste Management Costs	 4-1

4.1  Understanding True Costs	 4-1
4.2  Component Costs of Landfill Disposal Services	 4-1
4.3  Cost Accounting	 4-4
4.4  References	 4-8
                              11

-------
                        TABLE OF CONTENTS (cont.)

                                                           Page

SECTION 5 - Equity Considerations and Compensation
            Methods	  5-1

5.1  Equity Considerations	  5-1

     5.1.1  Host Municipality	  5-1
     5.1.2  Loss of Future Capacity	  5-3
     5.1.3  Guest Municipality	  5-3
     5.1.4  Liability	  5-4

5.2  Use and Calculation of Tipping Fee	  5-5
5.3  Alternative Methods of Compensation	  5-7
5.4  References	  5-1U
SECTION 6 - Conclusions and Recommendations	 fo-1



        PART II - METKAKE PRODUCTION AT CLOSED LANDFILLS


SECTION 7 - Introduction	 7-1
SECTION 8 - Potential Benefits and Dangers of Landfill
            Gas	 8-1

8.1  Recovery and Use	 8-1
8.2  Migration and Explosion	 8-8
8.3  Regulations	 8-9
8.4  Other Environmental Considerations	 8-15
8.5  References	 8-17
SECTION 9 - Landfill Gas Generation	 9-1

9.1  References	 9-4


SECTION lu - Landfill Gas Recovery	 10-1

10.1  Uses of Recovered Gas	 lu-1
10.2  Criteria for Site Selection	 10-3
10.3  Technical Factors Related to LFG Recovery	 10-7
lu.4  Landfill Gas Processing	 10-11
10 . 5  References	 10-lb
                              111

-------
                        TABLE OF CONTENTS (cont.)


SECTION 11 - Safety Considerations and Potential
             Consequences of Not Recovering or
             Controlling Landfill Gas	  11-1

11.1  Safety	  11-1
11.2  Potential Consequences .of Not Recovering or
      Controlling LFG	  11-2


SECTION 12 - Factors Affecting Economics of Gas
             Recovery	  12-1

12.1  Landfill Considerations	  12-1
12.2  Market Considerations	  12-3

      12.2.1  Medium-Btu Uses	  12-3
      12.2.2  Electrical Generation	  12-b
      12.2.3  High-Btu Uses	  12-7

12.3  References	  12-10
SECTION 13 - Decision-Makers '  Guide	  13-1

13.1  Minimum Criteria	  13-1
13.2  Revenue Vs.  Cost Comparison	  13-2
13.3  Field Test	  13-7
13.4  References	  13-9
SECTION 14 - Summary and Conclusions	  14-1
                               iv

-------
       LIST OF EXHIBITS - COOPERATIVE LANDFILL ARRANGEMENTS
Number                                                     Page

 2-1   Solid Waste Disposal Responsibility and Policies
       for Ten States	  2-7

 3-1   Potential Advantages and Disadvantages of Types
       of hultijurisdictional Approaches	  3-4

 3-2   Potential Advantages and Disadvantages of Public
       and Private Ownership and Operation of Disposal
       Facilities, and the Conditions That Favor Each
       Type of Operation	  3-6

 3-3   Characteristics of Capital Financing Methods
       Available for Solid Waste Management Facilities....  3-llA

 3-4   Potential Advantages and Disadvantages of
       Different Capital Financing Methods, and the
       Conditions that Favor Each	  3-12

 4-1   Landfill Costs:  1975-1985	  4-3

 4-2   Potential Advantages and Disadvantages of
       Taxes and User Charges as Sources of Operating
       Revenues and the Conditions that Favor Each	  4-6

 5-1   An Evaluation Matrix of Incentive and
       Compensation Techniques	  5-8

-------
  LIST OF EXHIBITS  - METHANE PRODUCTION FROM CLOSED LANDFILLS






Number                                                     Page





 8-1.  Active LFG Recovery Sites	  8-3



 8-2.  Planned LFG Recovery Sites	  8-5




 8-3.  LFG Recovery Sites by End Use and Size	  8-7




 8-4.  Landfill Gas Migration Damage Cases	  8-10



 9-1.  Example of LFG Generation Vs. Time	  9-2



10-1.  Landfall Gas Recovery System	  10-8



10-2.  Typical Extraction Well Installation	  10-9"



10-3.  Generalized Schematic of LFG Processing	  10-13




13-1.  Typical Capital and 0 & M Costs	  13-8
                               VI

-------
                       EXECUTIVE SUMMARY


     The mandate for this study is found in the 1984 Hazardous

and Solid Waste Amendments (HSWA) to the Resource Conservation

and Recovery Act (RCRA).  Under Section 702 [8002(s)L  Congress

directed the U.S. Environmental Protection Agency (EPA) to undertake

seven studies with the common theme of extending the useful life

of solid waste landfills.  The text of Section 8002(s)  is as

follows:

     The Administrator shall conduct detailed, comprehen-
     sive studies of methods to extend the useful life  of
     sanitary landfills and to better use sites in which
     filled or closed landfills are located.   Such studies
     shall address—

       (1)  methods to reduce the volume of materials
            before placement in landfills;

       (2)  more efficient systems for depositing
            waste in landfills;

       (3)  methods to enhance the rate of decomposition
            of solid waste in landfills, in a safe
            and environmentally acceptable manner;

       (4)  methane production from closed landfill
            units;

       (5)  innovative uses of closed landfill sites,
            including use for energy production such
            as solar or wind energy and use for metals
            recovery;

       (6)  potential for use of sewage treatment
            sludge in reclaiming landfilled areas; and

       (7)  methods to coordinate use of a landfill owned
            by one municipality by nearby municipalities,
            and to establish equitable rates for such use,
            taking into account the need to provide future
            landfill capacity to replace that so used.
                               ES-1

-------
     This Report to Congress on Section 8002(s) will be



completed in two phases.  Phase I, the present report,  will



address Section 8002(s)(7), methods to coordinate use of a



landfill owned by one municipality with nearby municipalities



and Section 8002(s)(4), methane production from closed landfill



units.  Phase II, to be completed at a future date,  will cover



the remaining five areas.



     The reader should be aware of several other related acti-



vities currently being undertaken by EPA.  The Agency is preparing



a second Report to Congress on the Subtitle D Study, which will



address the adequacy of the current guidelines governing the



disposal of solid waste.  These guidelines, or Criteria, are



entitled "Criteria for Classification of Solid Waste Disposal



Facilities and Practices" (40 CFR Part 257).  This report is



due to Congress by November 1987.  The third major effort by



EPA in the solid waste disposal (or Subtitle D) area is the



revising of these Criteria.  EPA is required to publish final



revisions by March 1988.



     The present report is divided into two parts.  Part One



addresses Cooperative Landfill Arrangements and Part Two



addresses Methane Production From Landfills.





Cooperative Landfill Arrangements (Part One)



     The purpose of this part of the report is to discuss



methods to coordinate use of sanitary landfills owned by one



municipality with nearby municipalities.  Cooperative landfill



arrangements are in place in several areas of the United States



and Canada.   Cooperatives can extend the useful capacity of





                              ES-2

-------
landfills and can offer savings for participating members.   It



is often easier to site one larger state-of-the-art landfill



than several smaller landfills.  Institutional difficulties



can act as potential barriers to the forming of a cooperative



arrangement.  With the use of mediation and dispute resolution,



however, these barriers can be overcome.



     The process for developing a cooperative arrangement



involves the following steps: development of a conceptual



agreement among participants; determination of options for



management of facilities; selection of landfill sites; ratifi-



cation of a final arrangement; and implementation of that



arrangement.  A well-structured public participation program



throughout this process will help ensure success of the arrangement



Strong motivation on the part of one of the municipalities



is usually required in order to get the process moving to form



a cooperative.



     Cooperative landfill use is best coordinated through a



written arrangement which specifies the roles, rights, and



responsibilities of the participants.  This written arrangement



should address the following key issues:  management, facilities,



regulations, liability, operation, and cost.



     The equity of costs and benefits is a prime concern for all



participants in cooperative landfills because of possible uneven



distribution between host and guest municipalities.  Methods



of compensation for the host community should be selected.



Negotiation techniques provide a useful mechanism to equitably



distribute these costs and benefits.
                              ES-3

-------
    . In summary, cooperative landfill arrangements are a viable



option for municipalities dealing with solid waste management



issues.  Current experience shows that these arrangements can



work and that this type of landfill use merits the active



support of State and Federal governments.  EPA supports the



concept of cooperative arrangements as a means to achieve better



landfilling practices.





Methane Production From Closed Landfills (Part Two)



     At both closed and operating landfills, landfill gas (LFG)



is generated as a product of the decomposition of organic matter.



Landfill gas can be either a hazard or a benefit at closed and



operating landfills.  Hazards are associated with the explosive



potential of the methane content of LFG.  Some concern has been



expressed about the presence of trace constituents in LFG, which



may include volatile organic compounds, such as benzene or toluene,



These trace constituents comprise less than 1% of the LFG.



     LFG generation begins almost immediately upon burial of the



waste and increases rapidly with steady generation beginning



within several months to a year.  Relatively steady generation



may continue for 10 years or longer.  The rate of the LFG



production is dependent on a number of site-specific factors:



the age of the landfill, moisture content and distribution, and



solid waste composition and quantity.



     LFG generated at closed and operating landfills poses a



concern for safety.  LFG can migrate both horizontally and



vertically below the surface and may pose an explosive danger
                              ES-4

-------
on the surface of the landfill and nearby surroundings;



fatalities and property damage have resulted from LFG explosions.



Control of these gases through recovery and utilization systems



or control systems can reduce the danger of explosion and may



help abate odors, thus aiding in the beneficial future use of



closed landfills.



     Recovery of LFG for beneficial use is currently practiced



at more than 50 locations nationwide with more than 40 other



systems in the planning stages.  The quantity, quality, and



collectability of LFG, and the availability of markets are



factors critical to the success of a LFG recovery project.



Assuming that LFG markets are present, potential recovery sites



are generally evaluated based on the following criteria:



amount of refuse, refuse composition and moisture content, and



age of the landfill.



     The recovery of LFG is attractive because it can reduce



gas-related dangers while generating revenue.  LFG can be recovered



and used as a replacement for or as a supplement to natural gas.



Such recovery of LFG is generally limited to relatively large



sites which have a nearby market for the recovered gas.



     The recovery of gas via collection systems can help achieve



the positive aspects of migration control, control of surface



emissions,  and recovery of an alternative fuel.  Recovery



systems withdrawing LFG can control migration and thus reduce



the potential for explosions.  Systems recovering LFG for energy



also help control horizontal migration and surface emissions.



     Regulations for LFG exist at both the Federal and State
                              ES-5

-------
level.  Federal standards establish criteria for methane concen-



trations in the soil at a landfill's property boundary and in



structures on the site.  Several States have adopted regulations



concerning LFG that include gas control/migration at both



operating and closed landfills.  Closure requirements often



address landfill gas concerns.  Some States have requirements



for relatively large landfills to collect or vent any LFG that



is generated.  Two States have regulations that encourage or



require collection rather than just venting of LFG.



     In most parts of the country the recovery of LFG is based



almost exclusively on the value of the gas as a fuel.  Where it



is profitable to recover LFG, it will be recovered.  The control



of gas migration is related to site-specific situations and is



driven by safety considerations as well.



     The recovery of LFG as fuel currently rests on economics.



Capital and operation and maintenance (O&M) costs for LFG



recovery systems can be quite high.  Thus, the right combination



of site conditions, gas volumes and market conditions must be



present to make recovery attractive for financial reasons only.



Capital costs will always be well over $1 million; annual



O&M costs are estimated to be more than 10 percent of capital



costs.



     As more States and possibly the Federal government, move



toward additional LFG regulation, recovery will become increas-



ingly attractive.   As these regulations become more common,



installation of recovery systems will become more popular for



both closed and operating sites.  In addition to the economic
                              ES-6

-------
benefits, LFG recovery will aid in meeting landfill surface



emission criteria and/or help control horizontal migration.



The combination of positive and negative motivators (the value



of the gas as a fuel and the regulations) may result in more



sites with control systems.
                              ES-7

-------
             PART ONE
COOPERATIVE LANDFILL ARRANGEMENTS

-------
                           SECTION 1



                          INTRODUCTION






     This portion of the report addresses methods to coordinate



the use of sanitary landfills owned by one municipality with



nearby municipalities.  The focus is the identification of



major issues that may affect implementation of these municipal



cooperative landfill arrangements.



     Cooperative landfilling is a voluntary arrangement whereby



a municipality shares its landfill space with other municipalities



under a set of operating rules and compensation mechanisms.  A .



cooperative arrangement can be financially attractive because a



group of municipalities may have large enough waste volumes to



achieve economies of scale in its operations.



     Cooperative sanitary landfills can be generally defined as



shared facilities established for the benefit of participating



municipalities.  The term "municipalities" includes cities and



towns, counties/ or other local jurisdictions.  A discussion of



the comparative merits of privately owned regional landfills



is beyond the scope of this study.



     As in the case of many other solid waste options, actual



modes of implementation of cooperative landfill use may vary



considerably and are site- and region-specific.  A cooperative




landfill can service as few as two communities.  The simplest



arrangement might base one cooperative landfill in one host



community to serve all members.  Alternatively, several



communities may decide to upgrade and use their joint capacity
                               1-1

-------
in turn.  Other more innovative uses have included bartering,

in which resource-recovery facility privileges are traded for

the right to dispose of residue.

     The main advantages of cooperative landfill arrangements

relate to potential siting flexibility, the economies of scale,

and the ability to pool participating communities' resources.

Appropriate landfill sites may not exist within a particular

community.  Because the siting of any solid waste facility is

difficult, communities may find it easier to establish one,

larger state-of-the-art landfill with good environmental control,

rather than siting several smaller, less sophisticated facili- .

ties.  In principle, the larger size of cooperative landfills

and the fact that they might operate under the auspices of

larger political entities may allow:

     e Improved environmental compliance through state-of-
       the-art technology and increased accountability;

     0 Greater variety of funding alternatives;

     0 Novel means to address liability and risk;

     0 Improved operational controls as a result of
       economies of scale; and

     0 Improved space utilization owing to better
       compaction technology and the need for less
       daily cover material.

     Increasing desire for more sophisticated management and

landfill technology may well lead to the closing of many smaller,

less sophisticated landfills in the following several years.

Experience over the past ten years indicates a trend toward the

closure of smaller sanitary landfills.
                              1-2

-------
     This report also addresses cooperative landfill  imple-




mentation.  A major impediment to such implementation is  that



different governmental entities may have diverse and  conflicting



interests and needs.  Further impediments to implementaton are



the apparent lack of precedents and appropriate institutional



role models, and the issue of equity.   These impediments  can



be overcome, however, through the use of dispute resolution



techniques.



     The issue of equity is a key component in fashioning a



successful arrangement.  Equity is defined as the sharing in a



fair manner, of the costs and benefits among the members  of



the landfill arrangement.  Equity relates to both host and guest



municipalities.  This is especially true for finance, risk and



liability questions.  In addition to the issue of equitable  fee




structures, provisions for future landfill needs of the host



community is also addressed.



     Part I of this report includes six major sections.  Section



1 provides an introduction and Section 2 describes the rationale




and background for cooperative landfill arrangements.  Factors



that may make cooperative landfilling attractive are reviewed




and include:  limited alternatives for waste disposal, reduced



costs compared with operating a single-municipality landfill,



history of cooperation among prospective cooperative members,



and reasonable distances between participants.  Economies of



scale are an important motivating factor for forming cooperatives



and several examples are given.
                              1-3

-------
     Section 2 also discusses the wide variation in prospective



members and indicates that cooperative arrangements must be



crafted carefully to address different interests.   The current




practice of cooperative landfilling is described in general



terms, and examples of cooperative landfills are presented.



Some potential barriers to widespread implementation of coopera-



tive landfill arrangements are identified.  The use of dispute



resolution techniques, especially mediation, in overcoming



these barriers is discussed.



     Section 3 describes forms of a cooperative organization



and outlines a method for coordinating landfill .use by focusing



on elements that should be addressed in a written agreement



among the members.  A process for developing an agreement is



described, and the important role of public participation is



highlighted.  Elements in the written agreement include issues



of management, facilities, regulations, liability, operations,



and costs.  Features of implementation, such as measures of



performance by responsible parties, are addressed, as are



techniques for accommodating changing circumstances (i.e.,



withdrawal or addition of participants).  Various supportive



activities that could be undertaken by State or local governments



are identified.



     Section 4 focuses on costs, which are a major motivating



factor for municipalities to enter into cooperative landfill



arrangements.  Components of landfill costs, such as collection,



transportation and disposal are enumerated.  These cost factors



form an important basis for allowing comparisons between coopera-
                              1-4

-------
tive landfilling and other disposal methods and for negotiating




equitable rates in a cooperative arrangement.



     Section 5 discusses methods for establishing equitable



rates that take into account the need to provide future waste



disposal capacity for participants.  Several of the costs to



the host municipality can be quantified and can be reflected in



the tipping fee.  These include landfill development and opera-



tional costs,  closure and post-closure care, "disamenities"



(e.g., noise,  litter, and odors), loss of development potential,



and road wear.  Other costs include environmental and health



risks, which are best addressed by liability insurance.  Other.



costs that cannot be quantified are best addressed through



negotiation or mediation between prospective members.



     Section 6 contains the conclusions and recommendations for



the report.  The major conclusion is that cooperative landfill



arrangements are a solid waste disposal option that merits



consideration.  These cooperative arrangements are a viable



option for municipalities searching for additional landfill



capacity.  Cooperatives can extend the useful life of landfills



through more efficient use of space.  Municipalities should be



encouraged to take advantage of the benefits of these cooperative




landfill arrangements.
                                1-5

-------
                            SECTION 2

        RATIONALE AND BACKGROUND FOR COOPERATIVE LANDFILLS


     Cooperative arrangements can offer advantages over single-

municipality landfills, but such arrangements have not become

common.  This section describes favorable conditions for

cooperative landfill development, with an emphasis on savings

that can accrue from larger-scale operations.  Background

information is provided on a variety of types of cooperative

arrangements, on current cooperative landfilling activities

and on potential impediments to cooperative arrangements.



MOTIVATION FOR COOPERATIVE LANDFILL ARRANGEMENTS

     Cooperative arrangements allow participating communities

to share sanitary landfills according to agreed on operating

rules.  Such arrangements can benefit:

     0 Communities that have run out of landfill
       capacity and have no alternative available
       in the foreseeable future;

     c Communities that have a small number of
       suitable landfill site candidates; and

     0 Communities that desire to save money by
       achieving economies of scale for equipment,
       operation and personnel.

If these basic conditions are met, three additional factors

could contribute to a community's decision to consider the

cooperative landfill option.  While it is not necessary to have

each of these conditions to establish a successful cooperative

agreement, the more that are available will  lead to a better

chance of success.  They are:
                              2-1

-------
     0 The existence cf an operating landfill in at least
       one of the potentially interested communities.
       This condition avoids the obstacle of siting a  new
       facility.

     0 A history of cooperative efforts by potential
       participants.  Experience and trust gained through
       the experience of cooperative efforts have proven
       to be important to the ten-year-old regional
       landfill program in Alberta, Canada.(1)

     0 Reasonable proximity between potential cooperative
       landfill communities.  Rural communities with
       small landfill sites may be too remote to make
       cooperative arrangements economically feasible.
       Particularly, the increased cost of transportation
       could be greater than any potential savings of
       landfill costs.

While all of these elements are important, many describe condi-

tions (such as lack oi appropriate sites or distance between

communities) over which municipal decision-makers have relatively

little control.  However, efforts to save money by achieving

economies in landfill operation are clearly within the realm of

decision-makers.  The next discussion focuses on this important

aspect of cooperative landfills.
ECONOMIES OF SCALE

     Landfill operations are typically classified by the amount

of waste they receive, with "small" being less then 200 tons

per day and "large" being greater than 1,000 tons per day (2).

There is a correlation between increases in waste received

and increases in certain costs.  Other unit costs, however,

decrease as the amount of waste increases.  One such economy of

scale concerns daily landfill cover material.  The industry

rule of thumb is to estimate a l-to-4 ratio between cover
                              2-2

-------
material and solid waste. (3)  However,  smaller landfills  can  use



up to twice as much cover material per unit of solid waste due



to their smaller daily waste accumulations. (4)  There is



obviously the opportunity for substantial economic savings,



especially if a landfill is importing cover material from  an



off-site source.



     Another important area in which economies of scale operate



is the purchase of compacting equipment.  The most efficient



compactors are the least versatile machines.  Therefore, a



small operation will typically own a tractor that can perform



a variety of functions, including site preparation, spreading



cover materials and waste compaction.  Larger landfills can



support the cost of a specialized steel-wheeled compactor  that



will extend the life of the landfill by producing greater



compaction rates.



     Larger landfills have the potential to spread the cost



of ancillary support and maintenance facilities and monitoring



systems over a larger volume of waste.  Support costs include:



weighing refuse and collecting fees, billing, maintenance,




supervision, shelters, access roads and utilities.  The cost



of monitoring systems and other environmental controls, such as



leachate and methane gas controls, is likely to increase the



minimum practical size of landfills in the future.



     New landfills can plan for economies of scale by incorpor-



ating minimum solid waste flow needs into the design process



and can ensure that they are achieved through cooperative



arrangements, market studies, and rate structures.  Existing
                              2-3

-------
landfills can take advantage of economies of scale by increasing

the waste stream with a cooperative arrangement.   The following

discussion indicates the variety of cooperative arrangements

that may be developed to help communities benefit from landfill

sharing.



STRUCTURE OF COOPERATIVE ARRANGEMENTS

     Several circumstances exist in which cooperative arrange-

ments for landfill use between municipalities may be advantageous.

An important distinguishing factor is whether a new landfill is

to be established, or whether one or more existing landfills

will continue in operation.  In these two cases,  the determination

of the host community, siting issues, risk and liability issues,

and a range of factors affecting choice may be quite different.

     Several variations on these basic cases are possible:

     0 A single multi-'purpose landfill may serve the
       solid waste disposal needs of all members of
       the cooperative;

     0 Several limited-purpose landfills (general
       refuse, construction/demolition wastes, trees
       and stumps, bulky wastes, for example) could
       be located in different municipalities; and

     0 Several general-purpose landfills could be
       used sequentially by cooperative members,  with
       different members serving as  "host" in turn.

     Regardless of the general configuration of the cooperative,

communities must address issues such as siting new facilities,

expanding or modifying existing facilities, and closure of

existing facilities.  The negotiation processes and agreements

will vary with the type, condition,  and number of solid waste
                              2-4

-------
facilities in member communities.  Given these factors,  there
will be considerable variation in the extent of responsibility
and the role of cooperative members who will enter into a
facility-siting process.  Thus, some cooperative members may be
required to make capital expenditures, or may be required to
comply with statutory and regulatory requirements regarding
facility establishment, modification, or closure.  Similarly,
some members must develop, maintain or expand the capability to
manage and operate a landfill.  The manner in which the indivi-
dual members approach a cooperative venture to address equity,
compensation, risk management, and liability also can vary
significantly.  Section 3 discusses the types of information
that should be included in a written agreement among communities.
     The next discussion provides information on the current
practice of cooperative landfills.

CURRENT PRACTICE OF COOPERATIVE LANDFILLING
     No listing of cooperative landfills operating in the
United States is currently available.  This report relies on
publications and personal communications with State officials
as data sources.
     The existing literature on landfilling is dominated by
publications from the mid-1970s, a period of substantial Federal
funding for solid waste studies.  Apparently very little infor-
mation has been published on cooperative landfill use.  The  few
papers mentioning the subject  from 1973 to the present  appear
in U.S. EPA case studies of solid waste practices in various
                              2-5

-------
urban areas across the nation (5).   One case study reviews



solid waste management in the Detroit metropolitan area,  noting



an unsuccessful attempt to obtain a regional landfill arrangement



(6).  A case study of Fresno, California,  mentions regional



landfill facilities as one potential solution to an impending



shortage (7).  There are no recent contributions to the litera-



ture on cooperative landfill usage that could be found.



     Cooperative landfills presently exist in various forms  in



the United States.  For purposes of this study/  ten States  were



contacted that reportedly had or planned to create cooperative




landfills.  Eight of these States have laws or programs



encouraging the planning and implementation of cooperative



landfills, but cooperatives still appear to be in the initial



stages of development.  These contacts provided information



concerning the existence of, or plans for, cooperative landfills



in each State and the potential for this type of landfill's



further development.



     A summary of the jurisdictional level with primary responsi-



bility for solid waste disposal at each of the States contacted



is shown in Exhibit 2-1.  In the majority of States contacted,



some communities have come together to form inter-municipal



solid waste disposal arrangements.  Two States, Delaware and



New Jersey, have strong controls at the State level that are



exercised at the county level.
                              2-6

-------
                         EXHIBIT 2-1.
             SOLID WASTE DISPOSAL RESPONSIBILITY
                 AND POLICIES FOR TEN STATES
                      I        II         III       IV

Connecticut           x                              x

Delaware                        x          x

Illinois              x                    x

Massachusetts         x                              x

New Jersey                      x          x         x

New York              x                              x

Oregon                x

Pennsylvania          x                    x         x

Virginia              x

Wisconsin             x
  I.  Municipality has primary responsibility for solid waste
      disposal in the State.

 II.  State has primary responsibility for solid waste
      disposal/ exercised through the county level.

III.  State has enacted law encouraging intergovernmental
      solid waste disposal agreements.

 IV.  State has policy encouraging intergovernmental
      arrangements for solid waste disposal.
                            2-7

-------
Case Examples

     The following is a summary of cooperative landfilling

efforts in the ten States contacted.   Information provided here

was obtained in telephone interviews  with spokespersons  for  the

State environmental protection agencies.
                        i
       Connecticut - This state has 169 municipalities.
       Eighty of them transport municipal solid waste to
       facilities outside their jurisdictions.  However,
       many of the communities using other municipalities '
       facilities pay tipping fees for disposal privileges.
       The towns of Windsor and Bloomfield have had a coop-
       erative arrangement since 1972.  The host landfill
       is located in Windsor, handles about 200 tons per
       day, and receives no special host compensation.
       The cooperative does not accept waste originating
       in other towns.

                - A autonomous State solid waste authority
       nas existed since 1975.  It controls the State's
       three landfilling facilities in each of three
       counties:  Kent, New Castle, and Sussex.  The
       authority's control over the flow of solid waste
       virtually eliminates inter-county use of landfills.
       Each county facility serves all the municipalities
       within the county's jurisdiction.  Each county
       landfill has about 20 years of remaining capacity.
       The regional nature of the landfills has allowed
       the construction of state-of-the-art facilities,
       in part, due to the economies of scale achieved.

       Illinois - This State passed a law in 1984 (Public
       Act 84-963) that greatly assists intergovernmental
       agreements for solid waste disposal by eliminating
       anti-competition issues from municipal commitment
       of solid waste to a disposal facility (8).  The
       Lake County Landfill, now in the planning stages,
       will be an example of a landfill with cooperative
       features.

       Massachusetts - This State has about 170 municipal
       landfills.  Eight of these accept municipal solid
       waste from beyond their own jurisdiction  (9).  The
       arrangements are generally ad hoc, resulting from
       the closing of an existing landfill.  The proposed
       State solid waste plan endorses regional solid waste
       management, especially for combustion facilities
       and their ash fills.
                               2-8

-------
  New Jersey - New Jersey has  a unique  control  system
  using the State Department of Environment  Protection
  (DEP) and the Board of Public Utilities  (BPU).  The
  State has ninety-three public and private  landfills,
  but eleven of them handle about  95  percent of the
  State's landfilled solid waste (10).  The  DEP directs
  solid waste haulers to certain districts and  the
  BPU assigns each hauler to specific facilities.  The
  State discourages inter-district disposal  with a
  waste importation tax.  It also  encourages hosting
  of regional facilities with  a compensation fee on
  each ton disposed at the facility.

0 New York - This State has an ash fill planned for
  Nassau and Suffolk counties  (Long Island)  (11).
  The facility will be a cooperative  for all the
  communities in those two counties.  The  cooperation
  has been enhanced with significant  State resources
  because of the area's dependence on ground water as
  drinking water.  The facility will  have  a  per ton
  surcharge that will go to the host  community.

0 Oregon - The Portland Metro  Council's St.  John's
  landfill serving Ciackamas,  Multnomah/ and
  Washington counties is an example of  a cooperative
  landfill, and was started in 1932.  In 1983,  the
  Metro Council received responsibility for  operations
  at the St. John's Landfill.   Between  1983  and 1985,
  the landfill received several hundred tons of refuse
  per day from beyond the three counties in  the Metro
  Council.  Ordinance 85-194 now precludes out-of-
  district use of the landfill in  order to extend
  its useful life.  There is a State  law imposing
  a 50 cent per ton fee that rewards  landfill host
  communities.

0 Pennsylvania - A recent State law encourages  the
  transfer of solid waste disposal responsibilities
  from the municipal level to  the  county level  (12).
  This law was created with solid  waste combustion
  facility development in mind, but also encourages
  cooperative landfills.  There are only a few
  existing county landfills, most  are at the muni-
  cipality level.  The county  facilities typically
  serve regions well beyond their  border.  Because
  of the tradition of home rule, however,  their
  formation required many municipalities to  work
  together.  The Lycoming County Landfill, as an
  example, serves more than five counties  for
  municipal solid waste disposal.
                          2-9

-------
     ° Virginia -The primary example of a cooperative
       landfill in Virginia is the Lorton Landfill operated
       by the Fairfax County Public Works Department.   It
       is a 400 acre landfill on a 3,000 acre parcel of
       Federally-owned land that is under the control of
       the District of Columbia (13).  The landfill serves
       the District of Columbia, Fairfax County,  Arlington
       County, the City of Alexandria, and the Alexandria
       Sanitation Authority, through a memorandum of
       understanding.  The size, location, and ownership
       of this landfill make it unique.  Other communities
       in Virginia, such as Norfolk, are entering into
       coooperative arrangements for refuse combustion
       facilities.

     0 Wisconsin - The State has about 700 licensed land-
       fills.  Five to six hundred of these are single
       municipality facilities.  There are about 20 county
       level landfills in existence and another twenty to
       thirty in the planning stages.  The county level of
       government is commonly relied on because individual
       municipalities have difficulty in siting landfills
       within their own borders.  The county assumes
       liability as landfill owner and operator.  Commonly,
       counties exclude non-county wastes to extend the
       useful life of the landfills.  However, counties
       do share landfills in certain situations, such as
       during short-term shortages.  Examples of county
       landfills are found in Lacross and Brown counties.

     0 Alberta, Canada - Cooperative landfills have been
       endorsed and created to eliminate open dumps (14).

     The reason for forming cooperative landfills varies from

case to case.  In rural Massachusetts, many informal cooperative

arrangements have resulted from landfill shortfalls, when exist-

ing landfills reached their capacities and no new facilities

had been sited.  In Long Island, New York, groups of communities

are attempting to form cooperative landfills to accommodate

solid waste combustion facility ash.
                               2-10

-------
POTENTIAL BARRIERS TO COOPERATIVE LANDFILLING

     Institutional barriers of many types may work  against

the formation of cooperative arrangements.   Municipalities

unaccustomed to working together to share services  may find  it

easier to develop individual municipality solutions than to

endure the additional approvals, negotiations,  petitions,  and

assurances that may be required in cooperative arrangements.

Models for cooperative agreements might serve as a  valuable

tool for communities planning or establishing a system of

shared use.
                         »
     Difficulty in establishing equitable rates can be a barrier

and is addressed in Section 5 of this report.  However, problems

can occur even when services are bartered.   The Massachusetts

towns of Norfolk and Framingham developed a proposal in which

the solid waste from Norfolk was to have been incinerated in

Framingham's incinerator, in exchange for which ash would be

deposited in Norfolk's landfill.  The cooperative use never

occurred, however, because Norfolk was concerned over the

potential environmental impacts of landfilling incinerator ash.

     The unsuccessful Norfolk/Framingham cooperative illustrates

an important issue with respect to such arrangements:  the

unknowns in solid waste disposal are a public concern.  Some

of these unknowns could be addressed by performing additional

research on the relevant environmental health issues.  In other

cases, deciding whether and how to share liability for a poten-

tial release of contaminants from a landfill may be a crucial

prerequisite to establishing a cooperative use arrangement.


                               2-11

-------
     Although many States and municipalities favor regional

landfilling over single-municipality landfills,  few State or

federal incentives for cooperatives appear to be available.

Assistance in developing model programs,  resolving legal issues,

providing for public participation, and defraying planning costs

might encourage attempts at cooperatives.



Overcoming These Barriers

     Not all of these barriers are unique to cooperative land-

fill arrangements, and many can be overcome with additional

information or assistance.  One form of assistance is the

use of dispute resolution techniques, especially mediation.

"Mediation is a negotiation process conducted by an impartial

and independent mediator or third party" (15).  Through mediation:

     "... parties to a dispute meet face to face to
     explore the facts, issues, and various viewpoints
     in the dispute and seek to settle their differences
     through bargaining and exploring alternative
     solutions.  If mediation is successful, the parties
     jointly develop a compromise agreement, a package of
     specified terms that each party can endorse". (16)

Although this EPA reference discusses hazardous waste facilities,

information presented in the report was based on a composite of

several successfully mediated disputes over the operation and

siting of sanitary landfills.  There are additional cases demon-

strating the successful use of environmental mediation.  (17, 18)
                               2-12

-------
 REFERENCES
 1.  J. Lapp, Waste Management Branch,  Alberta  Environment,
         Canada, Personal Conununciation,  1986.

 2.  Robinson, W.,  ed.  1986.   The Solid Waste Handbook:   A
         Practical Guide.  John Wiley & Sons, New York,  New York.
         p. 31.

 3.  U.S. Environmental Protection Agency.   1976.  Decision-Makers
         Guide on Solid Waste Management.   SW-500.   Washington,
         D.C. p. 112.

 4.  Kelly, M. 1986.  Equipment Selection for Landfills. Waste
         Age (January): 72.

 5.  Goddard, H. 1976.  Managing Solid Wastes: Economics,
         Technology, and Institutions.   Praeger,  New York,
         New York.   pp. 237-280.

 6.  U.S. Environmental Protection Agency.   1973.  Detroit's
         Municipal Solid Waste Management System.  PB 236-662.
         Washington, D.C.

 7.  U.S. Environmental Protection Agency.   1973.  Fresno's
         Solid Waste Management System.  PB 234-141.  Washington,
         D.C.

 8.  Stein, S. May 1986.  Illinois County Prepares for Regional
         Waste Program.  World Wastes 29 (5): 28-29.

 9.  Massachusetts Office of Environmental Affairs.
         May 29,1985.  A Solid Waste Plan For Massachusetts.
         pp. 1-21.

10.  New Jersey State Department of Environmental Protection  -
         Division of Waste Management.   May 1985.  Fact Sheet:
         An Act Concerning Solid Waste Disposal and Resource
         Recovery.   (A-1778) P.L. 1985, Chapter 38, Effective
         February 4, 1985.  C.13 : 1E-136.

11.  New York State Environmental Facilities Corporation.
         January 31, 1986.  Report to the Governor and Legislature
         on the Long Island Regional Ashfill Project.  Albany,
         N.Y.  pp.  1-32.

12.  Governor Dick Thornburgh.  November, 1985.  Governor Dick
         Thornburgh's Plan to Solve Pennsylvania's Municipal
         Waste Crisis.   Harrisburg, Pennsylvania,  pp. 1-53.

13.  Metropolitan Washington Council of Governments.  August,
         1983.  Evolution of the 1-95 Resource Recovery Land
         Reclamation and Recreation Complex.  Washington, D.C.
         pp. 1-53.


                                   2-13

-------
14.  Alberta Environment.   March 1985.   Overview,  Waste  Management
         Assistance Program.   Edmunton,  Alberta,  pp.  1-31.

15.  U.S. Environmental Protection Agency.   1982.   Using Mediation
         When Siting Hazardous Waste Management Facilities.
         SW-944.  Washington,  D.C.  p.l.

16.  Ibid.

17.  Talbott, Alan R.  Settling Things:   Six Case Studies in
         Environmental Mediation.   Conservation Foundation and
         Ford Foundation.   1983.

18.  Huser, Verne C.  The Crest Dispute:  A Mediation Success.
         Institute for Environmental Mediation.  Seattle,
         Washington.  September, 1982.
                               2-14

-------
                         SECTION 3

         ESTABLISHING COOPERATIVE LANDFILL ARRANGEMENTS


     This section considers the necessary ingredients in the

drafting of cooperative arrangements.   The negotiation process,

the roles and interests of various groups, the purpose and

contents of such arrangements, and matters of implementation and

modification are discussed.  For the purposes of this report,

two terms are defined:  cooperative arrangement and municipality.

     A cooperative arrangement is usually a formal, binding

document signed by authorized representatives of two or more

municipalities which governs the use,  establishment, operation

and termination of a cooperative landfill and support facilities.

The arrangement should do the following:

     0 identify the parties;

     0 establish all appropriate rights and duties;

     0 identify and describe the facilities;

     0 establish payment methods and schedules;

     0 describe operating procedures and standards
       (possibly referencing plans, specifications
       and similar documents);

     0 provide for modification and termination and
       for dispute resolution; and

     0 establish monitoring procedures.

     "Municipality" includes any and all units of local govern-

ment (including county government where it is the only unit of

local government exercising general authority over an area).

Where these units have executed a cooperative arrangement they

are referred to as "members of the cooperative".
                               3-1

-------
PROCESS FOR DEVELOPING A COOPERATIVE ARRANGEMENT

     Organizing a cooperative arrangement involves  the  following

sequential steps:  development of a conceptual agreement  among

participants; determination of options for management of  facil-

ities; selection of landfill sites; ratification of a final

arrangement; and implementation of that arrangement.  Public

participation programs should be an integral part of each step

of the process.  Legal counsel should be sought early in  the

process to make sure these types of arrangements are allowable

in the jurisdiction.  The range of complexity of each step is

potentially very large.  The simplest circumstance, a single

municipality contracting to deposit refuse in the existing

landfill of a neighbor, may raise few issues and involve  few

participants and a limited process.  More complex arrangements

involve several municipalities, substantial concerns about

equity and liability, and potential significant changes in the

solid waste management practices of all members.  These issues

may well preclude agreement unless the cooperative process is

open, well-structured and participated in by all those  persons

having an interest in or affected by the potential arrangement.


Role of Public Participation

     Public participation programs are valuable for all stages

of development for a cooperative landfill arrangement,  from

initial site investigations to landfill post-closure care.

Involving the public may:

     0 Increase the probability of public approval of
       final arrangements;


                               3-2

-------
     0 Ensure comprehensive coverage of issues;

     0 Provide a forum for conflict resolution;

     0 Provide decision-makers with opinions and values
       of the community on non-quantifiable issues;  and

       Increase accountability of decision-makers(1).

     There are two basic types of public participation.   One is

limited to provision of information to the public and receiving

responses; the other is based on two-way communication in which

the public both perceives and has a role in decision-making.

     The first type of participation is appropriate  for the

initial stages of site investigations for a cooperative landfill,

the second type for all other activities.  A lead agency should

provide funding that is required to initiate public  participa-

tion.  There are several possible lead development agencies

including a regional authority, the host community,  a guest

community, or a State agency.

     The lack of an obvious lead agency at this crucial stage of

the cooperative development process may inhibit implementation

of a useful public participation program.  It requires attention

and commitment from the beginning.



FORMS OF ORGANIZATION

     Possible multi-jurisdictional approaches to organization,

with positive and negative attributes, are summarized in

Exhibit 3-1.  The majority of cooperative landfill arrangements

are in the category of "multi-community cooperatives" (2).

     One approach to a cooperative agreement has been the use


                               3-3

-------
                                          EXHIBIT  3-1.


                  POTENTIAL ADVANTAGES AND DISADVANTAGES OF  TYPES
                          CF MULTUURISDICTIGNAL  APPROVES*
   Alternative
          Pounaai
         advantage*
                                                   Potential
                                                diaedvantat*
     Condition* whicn
      favor aJternaovt
Authority       Can finance without voter
               approval or regard to local
             . debt limit
               Political influence minimised
               becauae boart member* art
               pnvata cmsena
               Autonomoua from municipal
               budgetary aad adminiatraove
               eonaminta

               Can generate iaeeme to make
               aervice *elf-«upporang

               Capital fiaancinc ia tax
               exempt

Nonprofit       Tax-exempt tutaa

pu^i!L         Can finance without voter
eorporaoona     approval or ref art to local
               debt limit
               Aaaeta revert to community
               after bond* art paid
Muldecmmunity Tax -exempt ttatuti* available
cooperative      Oo— not j^,^ $u»
               approval
Special diitneu
Corutituaney ia a diaoact
(nap of r«nd«Bta. not
acattatvd beod-heidan
Local aatoeoar cu bt
protactad by barutc county
oOdalt aarrt on boart
Govtmaaoul
afrtvaaata
Flaxftla and aBferetcbU
matbod of eoopanaoa
BajkfwvBBaai
an aot duacad
Can bt implaaMntad qvckijr
aadawily
                                          Financinf it eeapltx
                                          C&B bocoait rtmou from
                                          public control
                                          Can compw with phvau
                                          mdu*rry IB *omt anu.
                                          ndun&( lAaaacy of both
                                          PobbcaJ influtnca may bt
                                          tstrud boeauM boart
                                          mtmbm art (ovtrnmtat
                                          offtoaii

                                          Difftcuh to diamaatlt r»tn if
                                          bttur Mrviet can bt provided
                                          by other
                                          Financing ia not backed by full
                                          faith aad credit of
                                          community

                                          Member eommunioea loae
                                          wmt aatanony
                                          Ability (0 raiat capiul
                                          depend* on lead community'*
                                          debt capaoty aad flnaflffina*
                                          Lead community caa be hun
                                          ftaaacially ualeaa conncia
                                          with other commuamee an
                                          written properly

                                          Powtrt limited by State
                                          etanu
                                          Muat rtry on tpedal tax lento
                                          requirinf voter approval
                                          Createa aa addittoaal uait of
                                          fovemmeat aot directly
                                          elected by aoiena

                                          May be difBedt to raiae
                                          capital aiact each eommuairy
                                          •vat bonw
                                          No aiaffle corporate body, ee

                                          •ay deciaioB
                                          If coamcta art not earerdly
                                                    Debt eeilinf prohibiu
                                                    ftnannnf by the municipality
                                                    Voter approval of finannni
                                                    will dtiay urftnt project
                                                    Politic*] activity ha* huidtrtd
                                                    acnvtry in paat
                                                    Autonomy from municipal
                                                    budf etary and adminiitrauvt
                                                    control would mtan raort
                                                    tCfioent delivery of xrviet
                                                    City wiahee to ihift financuif
                                                    requirtmenti to an
                                                    orfanizaoon outatde
                                                    municipal bureaucracy

                                                    City wiahet te avoid
                                                    adminicvaevt detail* of
                                                    providinc aoiid vote
                                                    manaf ement •ervteet
                                                    On* city ia willing to ukt itad
                                                    in »ecunn( ftnannnj
No other (ovtrnmentaJ unit
caa provide eervict
Service or Aucoon to be
provided ia not cootJy or
                                          •ay
      SOUFCE:   U.S.  Environmental Protection  Agency,  1976.  Decision-Makers  Guide
      in Solid Waste Management.   S.W.-500.   U.S.  Environmental Protection Agency,
      Washington, D.C. p.  scciv.

                                        3-A

-------
of a contractual mechanism.   This usually requires  the  host




community to bear ultimate responsibility and liability for  the




landfill and its impacts.   With growing concern over liability,



the host is likely to seek a form of organization that  distri-



butes liability among the users.  A more complex arrangement




may result, and the prospective guest municipalities may be



apprehensive about potential liability.   Advantages and



disadvantages of each type of liability distribution should




be thoroughly explored.



     There are a number of regulatory, organizational and



financial issues that should be addressed in the process of



cooperative landfill planning.  They are linked by the issue



of cost savings, a primary advantage of any kind of regional




facility.  Cost savings can be understood only in the context



of the particular organizational structure and financial methods



selected for the cooperative landfill arrangement.   These organ-



izational and financial methods must be allowable within the




overall legal and regulatory framework of State and local laws.



     State-of-the-art landfills can require significant capital.




Before deciding on an organizational structure and a method  for



capital financing, communities must carefully weigh the options



of private or public ownership of the landfill.  Advantages  and



disadvantages of each are summarized in Exhibit 3-2.








ELEMENTS OF A COOPERATIVE ARRANGEMENT



     An arrangement should contain a number of common elements.




The amount of attention that must be given to each will vary






                                 3-5

-------
                                    EXHIBIT  3-2


       POTENTIAL  ADVANTAGES  AND  DISADVANTAGES  OF  PUBLIC AND
    PRIVATE  OWNERSHIP AND OPERATION  OF DISPOSAL  FACILITIES
      AND  THE CONDITIONS THAT  FAVOR EACH  TYPE  OF  OPERATION*'
  Alternate*
         Potential
        advanugee
         Potential
       disadvantages
      Conditions which
      favor alternative
Public
Private
Tax-free
Nonprofit

Can obtain low.inurest rates
and. or government grants for
capiui-inunaive systems
Local f ovemment dot* not
need to raiae capital
Often eaiier for private firm
to buy land for a processing or
disposal ute
               Community 4on not bear
               •nor* n*k associated with
               new technology
Community may not have
ex penis* to operate
sophisticated capital-
intensive facility
City may lack mark*ting
txpeniM
Restrictive budget policin
may affect equipment
replacement and
maintenance

Community may  have no
central of fee* if only privately
operated fanliuei are
available
Operator may baae decisions
on bam of financial reward
rather than community needs
Letal eonatrtinta may prevent
city from iifninf long-term
contract

Displacement of city
employees
Municipality must locate
acceptable firm and
negotiate contract
Public predisposition towards
ffovemmtnt operation of
public services
Creation of public jobs desired
Government employees are
available to operate facility
Borrowing power of
community and or voter
approvals for bond issues
needed for capital
improvements in disposal
facilities are limited or not
available
Flexibility is needed to make
chanfes in operations that
would result in labor savings
and other coat reductions
Desire of local f ovemment to
avoid administrative details
in operation of disposal
facilities
Community lacks sufficient
technical and management
expertise for efficient
operation of the type of
advanced system it would like
to install
Territorial flexibility is needed
to permit operation across
political boundaries, where
appropriate regional
agencies do not exist
Commercial markets are,
available for recovered
products
Deeire to brpaas civil service
rcfuiaaons
 *  SOURCE:   U.S.  Environmental Protection Agency.   1976.   Decision-Makers Guide
    in Solid Haste ffenagenent.  SW-500.  Washington, O.C. p. xxvii.
                                       3-6

-------
from site to site.  The elements are listed below and  discussed.

Management Issues

     There are a wide variety of management issues relevant

to cooperative arrangements.  The authority,  responsibility,

rights, and duties of each party must be stated.   The  arrangement

must include a management structure and procedures,  and a

decision-making and dispute resolution process.   The governing

structure of the proposed cooperative organization should

respect the autonomy of the local entities.

Facilities Issues

     In the cooperative arrangement, the planned or agreed-on .

facilities and their usage should be clearly set forth.  Items

that should be incorporated include:

     0 Description of present status and condition
       of site and/or facility;

     0 Location and description of facility(ies);

     0 Definition of final capacity, ultimate
       configuration and use of landfill site; and

     0 Design and specifications for landfill
       including expansion/modification.

Regulatory Issues

     Regulations concerning landfill siting, design, construc-

tion, modification, operation and closure vary widely  in the

United States.  They may have a major impact on the nature and

form of the agreement and of the facilities.  Requirements for

long-term care of the landfill and protection of the environment,

especially ground water, are sensitive and potentially costly

items.  These items should be discussed during the negotiations
                               3-7

-------
process and then made a part of the cooperative arrrangement.

It is, therefore, essential to:  (1) identify the present

regulatory authorities and/or regulations and (2) to recognize

that future regulatory developments may impose significant

changes.  Compliance with these regulations will affect landfill

operation and costs.  Responsibility for compliance should be

specified.  Since all parties should be aware of any regulatory

actions affecting any of the cooperative facilities, a communica-

tion mechanism for this purpose should be established.  Regular

meetings with appropriate State and local officials for this

and other purposes are suggested.

     Though federal standards exist for solid waste disposal

facilities, the principal planning, and regulatory authority

rests with the States.  State agencies should be consulted

concerning State solid waste regulations.

Liability Issues

     The use of solid waste management facilities creates some

risk.  Risks may translate into potential liabilities.  Insurance

can cover some but not all liabilities.  Therefore, the arrange-

ment should cover the following points:

     0 Insurance issues;

     0 Establishment of specific liability;

     0 Identification and allocation of responsibility
       for any known or potential liabilities at the
       onset of cooperative activities; and

     0 Agreement on responsibility and procedures for
       claims.
                               3-8

-------
Operational Issues




     Each party will most likely be concerned that  its  short



and long term interests (e.g.,  avoidance of risk/liability,



preservation of capacity, economic operation) are protected.



Proper operation of the cooperative facility is necessary to



meet that objective.  Therefore, the arrangement should specify



the principal operational requirements of each facility affected



by the arrangement.



     Restrictions on the receipt of certain waste streams



should be addressed in the arrangement.  For example,  the arrange-



ment may prohibit receipt of bulky wastes, tires, or construction



debris.  Daily amounts of solid waste accepted by the landfill



also should be specified.



     Use of facilities for other than specified wastes from



members of the cooperative will continue to be a difficult



issue.  Of concern are matters of using up capacity presumably



reserved for members, hidden revenue streams, and unauthorized



types of wastes.  Unless only the municipal collection vehicles



of the members are to be allowed, a reasonably secure system



of permits or other identification will be required.



Cost Issues



     Cost issues are discussed in depth in Sections 4 and 5,



but some mention is needed here.  A clear delineation of costs



is critical to a successful, stable arrangement.  Financial



arrangements for cooperative landfills relate to the size and



complexity of the proposal.  A wide variety of organizational



and financial combinations is possible, but most of the more






                               3-9

-------
complex combinations are appropriate for large landfills.



     The types of costs typically associated with a cooperative



arrangement will include capital, operating,  administrative,



monitoring, and transportation/transfer expenditures.   Costs



may eventually be incurred for remedial action, liability and



damages, closure, and long-term custody of facilities.   The



parties also may elect to address the issue of future waste



disposal, which would include the costs of replacement facilities,




to provide for those costs.



     The arrangement should establish the authority and responsi-



bility for incurring costs and for accounting.  To the extent .



that capital costs are known, it is appropriate for the arrangememt



to allocate dollars; otherwise, the arrangement should establish



the bases and procedures for allocation of all costs.



     Exhibit 3-3 compares seven basic financial methods as to



their complexity of application, ability to raise capital, cost



of capital and constraints on use.  Exhibit 3-4 outlines the



advantages, disadvantages and favorable conditions for each



method.  The large number of options displayed in these exhibits



emphasizes the complexity of selecting the most appropriate



combination for a particular facility.








IMPLEMENTING AN ARRANGEMENT



     The arrangement should include measures and procedures  to



assure that its terms are fairly and consistently complied with



and to assess performance by each responsible party.  It should



establish criteria for acceptability of performance and should





                               3-10

-------
      EXHIBIT 3-3.  CHARACTERISTICS OF CAPITAL FINANCING METHODS AVAILABLE FOR SOLID WASTE MANAGEMENT FACILITIES*
                                                 Types of Financing
      Parameter
    General obligation
    bonds
    Municipal revenue
    bonds
   Municipal bank
   loans
    Complexity of
    application
    Ability to
    raise capital
I
I—•
•—•
    Cost of
    capital
    Constraints
    on use
No project information
required.
No project analysis required.
Short lead time.
Minimum $500,000 due to
fixed transaction costs, but
can combine several smaller
unrelated projects.
Function of community credit,
not of particular project.
Lowest interest rates for
long-term capital.
Interest cost 2-3 percent
less than corporate bonds.
Indirect costs include
bond counsel and possibly
financial consultant, but
costs are relatively low.
Voter approval often
required.
Legal debt ceiling may exist.
Can only be .used by
jurisdictions with taxing
powers.
Most complex.  Bond circular
must contain detailed
economic and technical
data certified by outside
consultants.  Requires
more time to arrange.

Minimum $1,000,000 due to heavy
fixed transaction/administrative
costs.  In pure form, not suited
for technologically risky
projects.  Maximum is function
of protected project revenues.
Somewhat higher than general
obligation bond.  Is directly
related to the probability of
maintaining adequate revenue.
Municipality can minimize cost
of capital by giving revenue
bond the risk attributes of a
general obligation bond.
Indirect costs higher than for
general obligation loans.

Can be used only for specific
projects.  Good only for rela-
tively large long-term capital.
Must he managed by district
authority or .igency.  Requires
stable, long-term revenue source.
Less complex than
especially if
has bank line of credit
Very short lead time.
No external advice or
certification needed.

No heavy fixed trans-
action costs makes
it useful for smaller
dollar needs.  Maximum
limited by bank lending
capacity.  Better than
short- and medium-term
loans than bond.

Similar to general
obligation bond in
terms of risk and
security, but affected
by loan size and terms.
Shorter loan terms than
bond.
Smaller dollar amounts
than bond.

-------
  EXHIBIT 3-3.
CHARACTERISTICS OF CAPITAL FINANCING METHODS AVAILABLE FOR SOLID WASTE MANAGEMENT FACILITIES*
(continued*)
                                             Types of Financing
  Parameter
       Leasing
 Current revenue
capital financing
    Private financing
 Leveraged leasing
Complexity of
application
Ability to
raise capital
Cost of
capital
Constraints
on use
  Somewhat simple.
  Minimal analysis
  required.
  Very short lead
  time.
  Small short-term
  (6-year) loans.
  Applicable to
  specific equip-
  ment, especially
  rolling stock.

  High effective
  annual interest
  (9-18%).  Same
  rate for public,
  private leases.
  Short term.
  Small dollar
  amounts.
  State-imposed
  restrictions on
  municipalities
  with multi-year
  noncanceliable
  leases.
 Least complex
 of municipal
 finance
 alternatives.
 Current revenue
 needed for
 major capital
 expenditures
 usually
 unavailable.
 No legal
 constraints.
 Economic
 constraint
 on amount of
 available
 capital.
Problems may be locating
adequate firm, negotiating
contract and proposed
facility site, public job
reductions, other management
or organizational issues.
Technical and economic
analysis by private firm.

Depends on credit rating
of firm and soundness of
project.  Firms may be
limited to smaller capital
than municipality with
general obligation bond.

Higher for private firm
than for municipality.  Can
be lowered by mechanisms
like industrial revenue
bond or leveraged leasing.
Legal constraints on long-
term noncancellable contracts.
Inadequate profit potential
for risk.  Administrative
legal problems of potential
mechanisms (leveraged
leasing, industrial revenue
bond).  Current mechanisms do
not benefit marginal firms.
Legally complex.
New to public
finance.  May
need IRS ruling
in beginning;
therefore, requires
6-month lead time.
Raises 20-50% of
required capital.
In pure form, not
for technologically
risky projects.
Good potential.

If city provides
remaining 6O-80%
capital, cost lower
than general obliga-
tion bond.  Lessor
absorbs other costs.

State restrictions
on city's signing
of multi-year
contracts.  Public
decision-makers
unfamiliar with
concept.
•Resources Planning Associates, Incorporated.  Financing Methods for Solid Waste Facilities.  U.S. EPA, 1974.
 (Distributed by National Technical Information Service, Springfield, Virginia, as PP-234-612).

-------
                                          EXHIBIT
       POTENTIAL ADVANTAGES  AND  DISADVANTAGES OF  DIFFERENT CAPITAL
           FINANCING  METHODS,  AND THE  CONDITIONS THAT  FAVOR EACH*
  Alternative
          Potential
         advantai ea
         PounnaJ
       dijadvanufe*
      Condiooni which
      favor
Borrow-in f"

   Centra)
   obligation
   bonds
   Municipal
   revenue
   bonds
   Bank loaaa
On* of the mo»t flexible and
Itaii co«Uy public borrowing
methoda

Require* no technical or
economic analym of
particular projecta to bt
funded

Small projecu may be grouped
to obtain capital
Leaat difficult to market
Riqutrti vottr approval, and
tlccnont may bt txptnmvt .
Muit aot ticwd
oiunjcipality's dtbt limit
U luir.f jur.idiruon reuit havt
po«tr to levy ad vaJorwn
proptrry tax
Trannction eetu impoat a
btnchaark minimua of
ssoo.ooo

Capital raiatd btcomat pan of
f tnvral city trvaaury. thua
other nty txptnditum could
draw en amount, unltta
ipteifcaUy tarmarktd for
•olid waaw
Sinet cartful proj«et
tvaJuaoon u aot rvquind
dffcifion-maktn may bt
una«art of t*chnoloficaJ  and
tconontc naka
Projected revenuaa guarantee
payment
Can be u*d by uutitadoni
lacking taxing powtr. luch a*
region*! authonon and
nonprofit corporadona
DOM net require votar
approval
It not eonftraintd by
municipality't debt
limitaoooj
Small ••eal* capital
rvqurtmfau for ahon-tam
fondinf (5 ytan or Ua*>
Somt m*diua-urm fandi&f
•eplkability tinet BOIM may
bt raflaaaeid M tbty apin
IUlativ«ly lev iawrvt coat
bteauat inurvt paid by
municipaiirf u tai-frw to
bank
Some* of totda on abort node*
No axurnal technical or
•eonomic anaJyii* nquind
     of raiainf capital ia a
dtumnt to chanya in txiannf
public' private reanaftrntnt
ma. litilt inctntive for
offir.aia to conaider uat of
prwau ayatam optratora

Effect) v* minunum iaaue of SI
milbon. thua only uatful for
capiial-inunaivfl proitcw

In/oraacion requirement* of
the bond curular aretvunaivt

TechAieal and economic
analyna of project muat be
performed by exptru ouuide
the auainpal fovemment

Coat ia haf her than general
obligation benda
Can bt oaed only for (pacific
pnjt
Lo» maximum
Short urm
Not oatral for capital-
iataaaiva projecta
Sis* of community ia amall or
m odium
VOUT approval likely
Capital-inunaive proiecu

Kefional faeUinaa deeired
Muninpality'a debt limit hi
been reached
IniQaonf inaonjoona lack
tazinf pover
Capital requirement ia amall
Funda needed on ahon node*
                                        3-12

-------
                              EXHIBIT  3-4.  (Continued)

    POTENTIAL ADVANTAGES AND DISADVANTAGES OF  DIFFERENT CAPITAL FINANCING
                   METHODS, AND THE  CONDITIONS THAT FAVOR EACH*
   Alternative
                     Pounnal
                    advantage*
                                                   PountiaJ
                                Condition! which
                                 favor alternative
    Lea* ing
Bank loan* |  Caacntiaily no ainimum
  (conn   |  Rajatjvtly ineapemaive
            Voter approval generally not
            required
            No debt ceiling*
            Can be naed by Institution*
            lacking taxing power

            Useful aa inuhn financing for
            equipment needed before
            appropriation* or lonf-urra
            capital arrangements can be
            made
            Negotiating agreement ia
            linplc and faat
            Only certification required ia
            assurance of municipality'*
            credit aunding
            Rvdueaa dtmand on
            reunicipvl capital outlay*
            ainea onfinal capiui raised by
            phvau corporation

            Least eempln •tehantaa
            availabl*
            No eonsulunt or Itf aJ advic*
            rtquirad
            No n»ad for formal financial
            decuman ta
Currant rwvnvt
capita]
Anancviff
Privata
ftnannnr
            MuaicipaJity naad not borrow
            eapiuJ
            Proridaa lonff-tara flaability
            for BonieipaJity
laaainf
            RadttCM dtmaad 00 moaibptl
            capttaJ fuada
            Intaraat rttt on tntira
            finaneiaJ paekaf* may bt
            lowar than |aatral obli(aaon
            bondj
         Kifh annual
inurcat rau (9-18 ptrctnt)
Amount of capital ia aaually
Umiud

Ltut urrni an rtntrally 5
yean or In*
Somt Stataa prohibit
municipalities from enterinf
mulnyear. noncancellabie
convacta
Ciry will not own ••»«( unlaac
it punch OM facility upon
complenon of leaat ptnod

No coat in the conventional
aenae ( but hif her uxaa raault)
Coromunioe*' ability to
f enerau iuiyluj capita] ia
frequently ladtiaf
Current uzpayen ihould not
have to pay for a tynan that
will b« uaed far into the future
SoKd waate project* muat
compew with other municipal
denanda

MuaicipaJity mu*t locate
acceptable Ant aad n*f otiau
convact
Hif her coat of capital reflected
in fyttaa chart e*
There may be legal
conatrmiata which prevent
       of lont-term contract
Equipment needed before
appropriation* available
Municipality ha* rood credit
rating
Displacement of city
employeea

Laf ftOy eomplea
City will not own aaaet oaleaa
h pwchaaea facility apon
ee0plecjoD of leajtar period
Amount of capital neceaaary ia
•mail
Municipality'* debt limit ha*
been reached
Municipality wiahea to avoid
administrative detail* of
operating aolid waau facility.
 SOUPCE:   U.S.  Ehvirontental Pzx>tection Agency.  1976. Decision-Makers Guide
 in  Solid Waste Management.  SW-500.   U.S. Envirormental  Protection  Agency, '
 Washington,  D.C. pp. xxii-xxiii.
                                       3-13

-------
include a system of sanctions or penalties and provide  for




their administration.



     The cooperative arrangement should recognize and provide  for



changing circumstances.  Withdrawal or addition of a participant



should be addressed.  Also, procedures to handle upsets in  opera-



tion, such as strikes and natural disasters,  should be  included.





ROLES OF STATE AND FEDERAL GOVERNMENT



     State and Federal governments often provide three  functions:



regulation, advice, and financial assistance.  The principal



importance of the regulatory role is that it sets conditions



for landfill siting, design, and operation to ensure protection



of human health and the environment.  Monitoring and enforcement



actions can lead to facility closure and thus provide an impor-



tant stimulus to establishment of cooperative arrangements.



     An advisory role could be important throughout the process



of developing an arrangement.  Guidance in law, technology and




economics, public participation, for example, could be  useful.



In some cases, the State could be a party to the arrangement as a



result of an enforcement action or for other reasons.



     Financial assistance is a potentially powerful tool for



implementing State or Federal policy in solid waste disposal.



Currently, no Federal aid is available for landfill operations.



The amount of aid available from States for localities  varies.
                               3-14

-------
RERERENCES

1.  U.S. Environmental Protection Agency.   April,  1981.  Solid
        Waste Landfill Design and Operation Practices (Draft).
        Contract No. 68-01-3915.  Washington,  D.C. p. 2-2.

2.  U.S. Environmental Protection Agency.   1976.   Decision-Makers
        Guide on Solid Waste Management.  SW-500.   Washington,
        D.C.  p. 10.
                              3-15

-------
                           SECTION 4



                  SOLID WASTE MANAGEMENT COSTS






UNDERSTANDING TRUE COSTS



     Understanding solid waste management costs,  particularly



landfill disposal service costs,  is essential if  municipalities



are to evaluate cooperative landfill proposals  realistically.



The participation of each member in a cooperative landfill




arrangement will be based on its perception of the benefits to



be gained.  This section provides a description of cost compo-




nents that should be evaluated when considering cooperative



arrangements.  A municipality will not recognize  the full costs



of its existing landfill if costs are understated or obscured



in a large category item in the municipal budget.  It will



underrate the real benefits of the economics of a cooperative



landfill arrangement.  Communities that have paid the true



costs of landfill disposal are more likley to recognize the



value of cooperative arrangements.



     Unfortunately, the typical municipality in this country



underbudgets and underaccounts the costs of its landfill disposal



service.  The following discussion sets out the component costs



associated with landfill disposal, and is followed by a section




on accounting for municipal solid waste costs.








COMPONENT COSTS OF LANDFILL DISPOSAL SERVICES



     Total landfill disposal costs represent the summation of



collection, transportation and disposal site costs.  Collection



costs are municipal-specific and vary depending on factors such
                             4-1

-------
as road patterns, demographics/  competition,  vehicle type,  crew



size, labor union strength,  frequency and type of service and



State and local regulations.  In general, transportation costs



are increasing as existing landfill sites become fewer and



newer sites become more remote from population centers.  Trans-



portation costs also vary greatly depending on local conditions.



Transportation and collection costs are closely related, and



for the purposes of this discussion will be considered as one



category.



     Disposal site costs include all costs at a disposal site,



among which are site identification, acquisition, planning,




preparation, operation, closure and post-closure care.  They



have increased dramatically over the past 10 years.  This



increase is primarily due to the incorporation of improved



environmental protection measures.



     Increases in costs of disposal from 1975 to 1985 are



illustrated in Exhibit 4-1.   The largest percentage increase,



nearly tenfold, was in the cost of site preparation and construc-



tion, an item that reflects the incorporation of environmental



protection measures.  Predevelopment cost increases reflect a




more stringent siting process.  The site closure and  long-term



care categories also reflect an increased awareness of  the



environmental impacts of landfills, which can continue  after a



facility stops receiving waste.



     Overall, disposal has become more capital-intensive;




therefore, total landfill disposal service costs are  influenced.



Changes in the mix of capital and operating costs will  influence






                               4-2

-------
                                               EXHIBIT 4-1.

                                          LANDFILL COSTS:   1975-1985
19751 19852
- Percent of . Percent of
COST ITEM $/ton total cost $/ton total cost
Pre-development
costs 0.25 6 1.30 9
Site preparation and
construction costs 0.52 12 4.90 33
i
*** Site operation 3.2 76 6.50 43
Site closure 0.26 6 0.70 5
Long-tera care 0.0 0 1.60 11
Percent change
from 1975 to 1985
300Z
960%
200Z
270*
N/A
 TOTAL (excluding
 business  profit)
4.23
100
15.0
100
360Z
 1.  Four-foot  earthen  liner,  leachate collection system, 40-acre  site,  1,000,000 tons/2,000,000  cubic yards,
     15-year  site  life.
                                                                                                 *
 2.  Five-foot  clay  liner  (on-site clays),  leachate collection system, 40-acre  site,  1,000,000  tons/2,000,000
     cubic  yards,  15-year  site life,  30-year  long-term care period.

 3.  Costs  are  In  1985 dollars.

 *Sourrr:   Hlcb, R., and  E. Scaro. 1985.  Cost Accounting for Landfill Design  and  Construction Past and Present-
 W.islo  T«-cli  "85 Proceedings,  National Solid  Waste Management Association, Washington, D.C.

**  excluding land  costs

-------
the budgeting of municipal resources for solid waste disposal,
since budgeting for capital costs requires consideration of
longer-term financial options than does budgeting for operating
expenses.
     The relationship between the costs of transportation and
onsite disposal costs is also changing.  In 1916, a rule of
thumb for judging the acceptability of total solid waste
management costs was that for every $1 spent on disposal, $4
would be spent on transportation (1).  This national average
might still apply in rural areas without landfill capacity
shortfalls.  In urban areas experiencing shortfalls and sharp
increases in disposal costs, however, this benchmark may be
outdated unless transportation costs have increased proportion-
ately.  These increased transportation costs are usually due to
the necessity of using even more remote facilities.
     Increases in total landfill costs are occurring in an
atmosphere of uncertainty regarding the future stability of
those costs.  Variability within the regulatory process, potential
problems in obtaining environmental liability insurance, and
prospective changes in the U.S. tax code all contribute to this
atmosphere.  Uncertainty always increases costs, because service
providers need to be compensated for taking the increased
risks.

COST ACCOUNTING
     While the landfill costs have been increasing, the  impact
of the cost increases on the market is diminished by two factors:
                               4-4

-------
(1) problems in accounting for the costs of solid waste disposal



and (2) the lack of connection between the service provided and



the fees paid to the service provider (i.e.,  between the service



and the fees paid by the consumer).  Accounting for costs of



solid waste disposal is complicated by hidden and underestimated



costs.  Many components of solid waste disposal services are



provided by governmental departments that are charged primarily



with responsibilities other than solid waste disposal.  These



departments typically provide inspection, enforcement, legal,



accounting, and payroll support to the solid waste disposal



service (2).  Their costs are usually not attributed directly



to the function cf solid waste disposal and,  therefore, are



hidden.  In addition, tacit agreements among municipal depart-




ments often provide public institutions such as schools and



hospitals with "free" disposal service.  Such service is free



only from the public institution's point of view; in reality,



the municipality pays for the service.  Municipal landfills are



usually fully amortized, and municipalities may overlook many




of the additional costs associated with new landfill siting



when they are faced with replacing their landfill capacity.



     Most revenue-generating methods for solid waste disposal



services feature convenience rather than accountability.  The



general fund, supported primarily by property tax assessments,



does not encourage accountability.  It is the most common revenue




source for municipal solid waste services.  The advantages and



disadvantages of collecting solid waste service costs through



property taxes and through other methods are delineated  in





                                4-5

-------
                                   EXHIBIT  4-2


               POTENTIAL ADVANTAGES AND  DISADVANTAGES OF
     TAXES, AND  USER  CHARGES AS SOURCES OF OPERATING  REVENUES
                   AND THE  CONDITIONS THAT FAVOR EACH*
  Alurnetivt
         Pounds!
        advanucet
                                 Potential
                               dieadvantafte
                             Ceadiooni whuh
                              favor
Property tax
Saletux
Municipal
utility ui
Special tax
ItVMS
UMT eharf eo
Simple ta tdmmuur— no
aeparate billinc and collection
tyiuns aeceaeary
If pan of local property tax. it
it deductible from Federal and
Suit income taxet
Siaplt to adaiauur
Siaplt to adnuuaur
Mort oquiubl* than ad
vaiortm taxat
Can b* iarataud without
vour approval

Vour approval uually not
nquind
Enable* localiQM te balanet
tht coot of providing oolid
vuu atrvicM with rwanuo*
Cituinj an awar* of OMU of
atrvKt and can prortd*
iapotoa for aort ttf^iaat
optraboM
                        Solid waiu naaaf tmtnt it   Tradition of Ui Ananang for
                        ofun a low-pnonty iwa in tht moot pubUe
                        budftt and rocrw
                        inadoquau fund*
                        CMU an hiddtn— law
                        iDcanavt for iffincnt
                        oporaaon
                        Commtrdal Mublishacnu
                        pay u>« for Mrvie* taty ouy
                        not roemvt
                        VahabU monthly i
                        Rcquira voter approval
                        Ineomt may not bo adequate
                        Commercial •ubluhmeau
                        pay tazee for ttmet they may
                        not neeivt

                        Variable monthly income
                        Ineomt may be inadequate
                        KecmB'oB anai with hiyh
                        tountt pradt
                        Ceiling oa property tax rate*
                        Tradiaon of tax flnanoaf for
                        moot public i
                        Amouat limited by
Men eompla to adniauter
Caa cauM problem* for Men
oa fixed tacomeo
                        Ceilinf oa property tax rauo
                        Tradition of tax financial for
                        meet public
                                                Cttiiaf on property tax ratee
  •  9OJBCE:   U.S.  Btvirorrental Protection Agency. 1976. Decision-Makers Guide
     in Solid Waste Management.  SW-500.   U.S. Bfiviromental Protaction Agency,
     Washington, D.C. p. xxiii.
                                    4-6

-------
Exhibit 4-2.  All of the alternative revenue-generating methods




in the -exhibit, except for the user charge,  indiscriminately



target the general population.  These methods spread the costs



of providing the service over the population in a general



manner, instead of on a pay-as-you-use basis.  The tipping fee,



on the other hand, is one mechanism used by providers of waste



disposal services to collect revenues from users.
                                4-7

-------
REFERENCES
1.  U.S. Environmental Protection Agency.   1976.   Decision-
         Makers Guide on Solid Waste Management.   SW-500.
         Washington, D.C.  p. 13.

2.  Ibid.
                                4-8

-------
                           SECTION 5




             EQUITY ISSUES AND COMPENSATION METHODS






     In cooperative landfill arrangements,  the concept of



equity becomes a major issue.  Equity involves both  fair



distribution of costs among member municipalities and adequate




compensation of the host municipality.  Among the many consid-



erations involved in establishing equity are host municipality



costs, market considerations/ future landfill capacity and




waste management policies on the local, regional, State and



federal levels.  Future disposal capacity and liabilities for




the host municipality can also form obstacles to successfully



negotiating a cooperative landfill arrangement.  Tipping fees



should relate directly to actual landfill usage and may be used




to raise revenues to pay for operating a cooperative landfill.



Tipping fees and other methods are also used to compensate the



host municipality.  Broad equity considerations, methods of




calculating tipping fees and alternative ways of providing



compensation are discussed in this section.








EQUITY CONSIDERATIONS





Host Municipality



     Equity for the host municipality of a cooperative landfill



is critical to any negotiated agreement.  It can be approached




intitially by balancing the costs and benefits of any proposed



arrangement.  The costs include direct and external costs of



the landfill, potential increases in risk and  liability, and
                               5-1

-------
loss of future landfill capacity.   Potential host municipality
benefits are improvements in landfill design,  operation,  closure
and costs which all may contribute to a decrease in future
liabilities.
     Host municipalities bear more of the costs associated with
cooperative landfills by virtue of the presence of the landfill
within their boundaries.  The most common tangible costs to the
host municipality are those associated with increased truck
traffic, including road wear, noise, air pollution and possible
traffic congestion.  A less obvious cost to the host municipal-
ity during the operation and post-closure periods is the loss
of potential development benefits of the acreage dedicated to
the landfill.  Other potential costs depend on the landfill's
physical attributes, design features and operational integrity.
These potential cost categories include litter; odor; aesthetics;
contamination of air, surface and ground water; methane gas
migration; and potential human health effects.
     An additional cost to be considered is the concern of
possible decrease in property value of land abutting the land-
fill.  The incidence of decreases in land values has not been
documented.  In fact, a report on a closely analogous facility
type, hazardous waste landfills, found both decreases and
increases in property values of surrounding land parcels (1).
     It is possible that many of the above host municipality
costs can be significantly reduced.  For example, state-of-the-
art design features will reduce the potential environmental
problems.
                               5-2

-------
Loss of Future Capacity



     A concern of a host municipality is that it will be deprived



of access to disposal services in the future if it allows



surrounding municipalities to use its landfill.  This factor



is difficult to quantify, and is even more difficult to present



systematically and convincingly to skeptical members of the



host municipality.  As a result, the capacity issue is a common



and frequently paramount barrier to attaining the prospective



host municipality's acceptance of a cooperative landfill; but



it can be overcome.



     Future landfill capacity within a region will depend on



several elements with entirely different schedules.  Specifically,



population growth, municipal budgets and political changes will



vary within each of the area's municipalities.  These changes



will affect the availability of suitable landfill sites within



the host municipality and guest municipalities.



Guest Municipality



     A municipality in a cooperative arrangement that does not
                                            (


host the landfill site can be termed a "guea't" municipality.



Guest municipalities do not always have the ability to site a



landfill in their jurisdictions.  This inability will greatly



influence their level of benefits from a cooperative arrangement.



Clearly, the primary benefit for a guest municipality is the



ability to use a nearby disposal facility.  Some guest municipal-



ities will probably incur higher transportation costs, however.



The relative magnitude of all costs and benefits for host and



guest municipalities will vary with local conditions.  The most
                               5-3

-------
difficult issue usually arises in negotiating agreeable conditions


with the host community.



Liability

     A major difficulty affecting equity and other factors is

management of the environmental and human health risks.  Landfill

owners and developers face substantial potential liability.   The

relative lack of knowledge concerning the dynamics of the solid

waste decomposition process and its interaction with environmental

factors such as climate, geology, groundwater, and precipitation

magnifies the problem of obtaining liability insurance.  The

extent of responsibility for environmental damages from landfills

is dependent on case-by-case circumstances.

     A cooperative landfill is an alternative to a set of single-

municipality landfills.  Other alternatives, such as a commercial

landfill, a municipal incinerator or waste-to-energy facility

may also be available.  Whatever the alternatives, the relative

risks of each and the insurability of the risk* should be factors
                                              /
in the decision process.  Possible alternatives to traditional

insurance include self-insurance by the cooperative or a larger

pool of communities.  Several communities or persons are required

for viable self-insurance programs.  Therefore, smaller landfill

facilities with limited service areas may be unable to consider

this option without outside assistance.  State and Federal funds

for insuring landfills are not currently available.
                               5-4

-------
USE AND CALCULATION OF TIPPING FEE

     The host municipality can incorporate the above costs  with

traditionally incurred costs of landfill operation and develop-

ment into their tipping fee.  This holds true for actual costs

and perceived costs.  The following list summarizes the costs

that should be reflected in an equitable tipping fee:

     0 Landfill development and operational costs
       (operational costs will vary considerably
       depending on volume received);

     0 Closure costs and post-closure care;

     0 Disamenities for host municipality (noise, litter,
       odors, etc.);

     0 Economic losses (loss of development potential of
       i^n^fill property itself, road wear, etc.); ars^

     0 Risks and uncertainties  (e.g., groundwater and
       drinking water contamination from leachate).

     The concept of equity is usually incorporated implicitly

rather than explicitly because accurate data concerning the

multitude of factors involved and their interactions is lacking.

Incorporating these various considerations is ^usually accomplished
                                              /
                                             /
via negotiation.  Through negotiation, the me'mber municipalities
                                             /
of a cooperative landfill can set the range of possible tipping

fees for any site, determining an upper and lower bound.

     The upper bound for tipping fees is usually derived from

the costs of the alternative disposal services available.

Calculating these costs is complicated by the wide variety of

pricing systems used by alternative services  (some using flat

fees, some differentiating by waste composition, and others

providing membership incentives) and by the different  life
                                  5-5

-------
expectancies of these alternatives.  Market alternatives,  even


with the complexities of comparison, are the best approximations


of the maximum tipping fees that could be charged by cooperative


landfills considering only market conditions.  The maximum fees


of the market should not be seen as practical,  however.   It is


necessary in cooperative arrangements to take into account


non-market factors, such as establishing goodwill and working


relationships among member municipalities, when setting actual


fees.  All of these factors enter into the negotiation process


of fashioning an agreement that suits the participating members.


     The lower bound for tipping fees usually can be defined


by calculating the costs of planning, development, operation/


closure, and post-closure of the landfill and distributing


those costs over its projected lifetime.


     In addition to the level of tipping fees,  cooperative land-


fills need to address the structure of the fees.  Fee structure,

the method of ascribing fees to users, will have a large impact on

                                             t
the equity of the tipping fee.  The simplest Structure is based
                                             /
                               »
on a flat fee charged at the time of tipping/ it is easily


administered and is usually supplemented either by making a


lump sum payment to the host municipality or by dedicating a


portion of the tipping fee for use by the host municipality.


Alternatively, fees could be assessed annually to host and


member municipalities.  Other fee structures could include per


capita ceilings., large-volume penalties, per container charges,

per volume charges, and varying charges on the basis of waste
                                 5-6

-------
composition (e.g., bulky waste, yard waste,  incinerator ash,


etc.).


     The complexity of tipping fee calculation rises with the


number of participating municipalities.   The number of alternative


disposal methods available to each participating municipality


will further complicate the calculation process.  Host munici-


palities may want to establish a low tipping fee to encourage


landfill use.   High tipping fees might serve as an incentive


for use of disposal options with more negative environmental


impacts.  Overall, the complexity of the fee calculation task


requires thorough analysis of the implications for participating


and interested communities and coordination at all levels


of government.  In summation, the tipping fee has important


implications for the equity of the cooperative arrangement and


the region's solid waste management strategy.





ALTERNATIVE METHODS OF COMPENSATION


     Tipping fees are only one method of compensating host
                                            /

municipalities and encouraging municipalities to consider host-


ing cooperative landfills.  Various incentives and compensation


techniques for parties affected by the presence of hazardous


waste management facilities have been evaluated and are presented


in Exhibit 5-1.  The U.S. EPA has also published a handbook


which discusses compensation and incentives in siting hazardous


waste managment facilities (4).  Most of the concepts developed


are relevant to non-hazardous waste facilities.  Incentives  and


compensations which can be applied to sanitary  landfills/ are



                               5-7

-------
                                                           EXHIBIT 5-1.
                                 AN EVALUATION MATRIX OF  INCENTIVE AND COMPENSATION TECHNIQUES*
                                                                                       SOURCE OF FUNDS
ft
Landfill Ownrr/OaxTBIor

•pra*f4
ration and
mtcnafict
_ » «•
?e
•S
«
w
e
«
c
•>
6
>•
a
•• «
c •>
•> 3
s-
*r-
e t
je
•5 a.
H
5 o2
* s?
X E 5.
4 >. _
V « —
!? t *
"" "•.•!

1=
V »
».
• *
4
..»

•*
U
i»
*-
s
fc
«
f.
6
*;•
S 5
3 2
ii
Jl
••
••
7
?
t»
o
|
>ik Of..
•
w
£
tajnpa»Oi
t**u) i(ii
<« ex
^
•»
M
.-ralor
«
c
"3.
t
•
i
u
•I
cloturt ci
1
^
c
ni«re»( la.
W city
•
0
Primer ilv

W
o
•*
c
ft.
u

i rtv«nut-
.iyinrnt!>

Stale
i
ll
1

I
«.
fr
t ?
m
\
•*
J5
           Mysleal (•pact*
             nou*. AMI, Ml let,
             truck Irafftci 4*l*ttoMll«t
In

00
     4«cr«*M to potpOTty ••!«••
     «*cllf» to »••! ••••!• <«»«
     rc«lrlcl*4 la«4 ••* •ftlatu
  Serial >•*••€!•
     c*u«« to ^MHir »r ur*
     to** IN •••iMlIc *ato«
  Milk* «M! MNc«rlatotU«
                                                            »
                                                            0
      0
      0

      0
      0
      0
              fir* wt4
              fcraldk
         M«M(cto«l f •v«ra»**t
              Itwck traffic
           Kc«*omlc
           SaclaJ laiftac
           Mt»k«
                                 v«l«r
                                                   •

                                                   0

                                                   •
                                                   •

                                                   •
                                                   •
                                                   •
                                                                 0
                                                                 0
                                                                 0
                                                                 0
                                                                        0
                                                                        0
                                                                        0
• 0 •
• 0 <
^ •
* +
0 0
. •
« 0 <
« 0
• ,
• • • 0
» • 0 0
» 0 0 •
> 0 0 •
> 0 0 •
» • 0 0
» • • •
» • • »
• • • •
0
0
0
•
0
0'
0
0
0
0
0
0
0
•
0
0
0
0
0
0
0
0
•
0
0
0
0
0
0
0
0
•
0
0
0
0
0
0
0
0
•
0




                                                            0
                                                            0
0
0

0
0
0
      0
      0
0
0
0
0
0
0
0
0
0
0
                                                                           0
                                                                           0
#
.
0
e
0
•
•
•
•
«
•
•
0
0
•
»
0
•
•
*
•
0
•
•
•
0
0
• •
•
• '
0
0
0
»
0
•
•
0
•
•
»
0
0
•
0
*
0
0
•
0
•
0
0
•
0
KCTi
                                               •pccUlc
              • Fat
              • N» •ffcctl
        * SOUICE:  Stoith, M. et al. 1985. Costs and Benefits to Local Government Due to the Presence of a Hazardous
          Waste Management Facility and telated Ccnpensation Issues. Institute of  Environmental Studies at the
          University of North Carolina,  Chapel Hill, North Carolina. p.J'2.

-------
divided into three major categories:

     0  Preventive measures to assist the host municipal-
        ity in avoiding adverse impacts (e.g., purchasing
        a buffer zone);

        Mitigating measures to reverse adverse impacts
        experienced by the host (e.g., provisions to
        repair roads suffering from excessive wear); and

     0  Compensation measures to provide the host
        municipality with benefits in recognition of
        those lost by virtue of the landfill's proximity
        (e.g., funding for construction of a park or a
        library [2]).

     Each of the sixteen methods surveyed in Exhibit 5-1 has a

different degree of effectiveness in mitigating impacts on the

various affected parties.  Improved operation and maintenance

proves to be one of the most effective measures for a majority

of the affected parties.  This conclusion coincides with current

findings that the public is more interested in reducing perceived

risks through better operational procedures and design features

than it is in monetary compensation.(3)  It has been traditionally

argued that balancing costs and benefits will convince people
                                            *
to accept undesirable public service facilit4.es.  This has not

proven realistic in efforts to site new landfills.

     The assessment of equity of any cooperative arrangement will

differ with each participant.  The differences will vary with

local circumstances.  Only after each participant recognizes

its actual solid waste management costs can they evaluate

whether any compensation alternative is appropriate, including

tipping fees, lump sum payments, service bartering or other

methods.
                                5-9

-------
REFERENCES
1.  Smith, M., et al. 1985. Costs and Benefits to Local
        Governments Due to the Presence of a Hazardous Waste
        Management Facility and Related Compensation Issues:
        Final Report. Institute for Environmental Studies,
        University of North Carolina, Chapel Hill, North
        Carolina, p. 3.

2.  Massachusetts Hazardous Waste Advisory Committee, Pollution
        Liability Work Group. 1985. Legislative Proposal for
        Long-Term Solution to Unavailability of Pollution
        Insurance.  Department of Environmental Quality
        Engineering, Boston, Massachusetts, p. 76.

3.  Portney, K. 1984  Allaying the NIMBY Syndrome:  The Potential
        for Compensation in Hazardous Waste Treatment Facility
        Siting.  Hazardous Waste and Hazardous Materials 1:3.

4.  U.S. Environmental Protection Agency.  1982.  Using
        Compensations and Incentives When Siting Hazardous
        Waste Management Facilities.  SW-942.  Washington,  D.C.
                               5-10

-------
                            SECTION 6


                 CONCLUSIONS AND RECOMMENDATIONS




     Cooperative landfill arrangements are in place in several



municipalities, and other areas could benefit from landfill


sharing.  Cooperatives can extend the useful capacity of land-



fills by using space more efficiently, and members can experience



net savings in waste disposal costs if the waste volume can



create economies of scale.



     Cooperative landfill use is best coordinated through a



written agreement.  However, there is great variation among



municipalities, and a number of factors should be addressed.



     Several conditions may exist in a community that can make



cooperative landfill arrangements an attractive option for solid



waste disposal.  These include landfill capacity constraints,



high costs of operating a single-municipality landfill, history



of cooperative efforts by potential participating communities,


and reasonable distances between prospective members of the
                                             /
                                             /
cooperative.                                t

                                            /

     Economies of scale may be achieved when cooperatives are



formed, because the larger waste flows may allow purchase of



more efficient compacting equipment and the use of less cover



material for a given volume of solid waste, both of which will



extend the useful capacity of the landfill.  Other economies of



scale may result from improved administrative procedures and



more effective use of personnel.
                               6-1

-------
     Information in the literature on cooperative landfilling

is scarce.  However, there are examples of existing cooperatives


and attempts at cooperatives that are instructive.   Experiences

in ten states have been discussed and these examples show that


cooperative landfill arrangements can work.

     Institutional difficulties can act as barriers to the


formation of shared landfill arrangements.  However, these


problems can be overcome through the use of mediation and assis-


tance to communities in the areas of planning,  implementation,

public participation and legal support.

     The process for developing a cooperative arrangement

consists of a series of sequential steps:  development of a


conceptual arrangement among participants; determination of


options for management of facilities; selection of landfill


sites; ratification of a final arrangement; and implementation

of that arrangement.  Throughout the process a well-structured

public participation program is essential to success.  The key
                                             *
for successful development of a cooperative arrangement is a

mediation-negotiation process whereby all the prospective mem-


bers meet to fashion the arrangement.  As part of this mediation


process, all the various roles and interests of the parties


involved are discussed and resolution on these issues is reached.


     There are six key issues involved in any cooperative

arrangement:  management, facilities, regulations,  liability,


operation, and cost.  Management issues entail deciding on

authority, responsibilities, rights, and duties of  the members.


A management structure and a dispute resolution process,  for



                               6-2

-------
solving complaints after the arrangement has been formed,  both



need to be designed.  The issue of facilities concerns  the



present status of all facilities involved and related capacity



issues.  Participating municipalities should also be familiar



with applicable State and Federal regulations,  as they will



affect an agreement.



     Liability issues must be worked out in drafting a coopera-



tive arrangement.  The most common approach is for the host



community to assume the majority of the responsibility and



liability of the project.  Operational issues,  such as daily/



weekly amounts of solid waste to be accepted and possible waste



restrictions should also be decided.  The issues related to



various costs must also be resolved.



     After the major elements of the arrangement are worked out



and the agreement is in place, attention is then turned toward



implementation of the arrangement.  A process should be designed



to assure that the responsibilities of the various parties are

                                             t
carried out.  The arrangement should also be/structured to
                                            i
                                            •.

accommodate changing situations,  (withdrawal or addition of



members) and to plan for unforeseen events  (floods, strikes,



etc. )



     The possible roles of State and Federal government in set-



ting up a cooperative arrangement should be considered.  Applicable



regulations, technical assistance and advice, monitoring and



enforcement actions, and financial assistance will impact a



cooperative arrangement.
                               6-3

-------
    Costs are an important motivating factor in solid waste


decision-making, but difficulties in landfill cost accounting


may obscure the real costs of single municipality landfill


operation.  This factor may inhibit formation of cooperative


landfills.


     Cooperative landfills are pursued on the basis of their


perceived benefits and efficiencies.  The full efficiency of a


cooperative landfill cannot be clearly seen without a delinea-


tion of present disposal costs for use in comparing proposed


disposal options.  Capital and operational costs will depend


on local conditions and will affect the municipality's budget


allocations and priorities.


     Transportation costs that limit a cooperative landfill's


market area will become more important in rural areas or other


areas without easy access to alternative disposal facilities.


Accurate accounting of a municipality's solid waste disposal


costs is necessary to clarify the net benefits that accrue to


the cooperative landfill alternative.       f>
                                            t

     The equity of costs and benefits is a prime concern for


all participants in cooperative landfills because of possible


uneven distribution of these costs and benefits among host and


guest municipalities.  The equity of the costs and benefits


is crucial in obtaining voluntary participation by all of the


municipalities.  Each cooperative proposal should be evaluated


before selecting an appropriate strategy to achieve an equitable


arrangement.
                               6-4

-------
     Municipalities need to evaluate other factors  that  affect

solid waste management decisions,  in addition to the cooperative

landfill option.  For instance, the solid waste management

policies of relevant Federal and State agencies and regional

authorities can significantly affect a municipality's perception

of the value of various options, including cooperative landfills.

     The risks and uncertainties placed on the host of a

cooperative landfill have usually been covered by insurance.

Insurance is a particularly useful method for municipalities to

equitably share the risk of a cooperative landfill among all

participants.  However, the current difficulty in obtaining

environmental insurance in general may inhibit development of

cooperative landfill arrangements.

     After establishing a need for compensation of the host

municipality, the method of compensation should be selected.

Differential tipping fees are a common method used at landfills

and can be used as a compensation vehicle.  However, lump sum
                                             t
payments and bartering can be used as compensation methods to
                              t
accommodate particular local circumstances. 7Negotiation is

required in order to reach equitable compensation schemes

among participating municipalities.

     A great deal of motivation is required to ensure the suc-

cess of such a complex voluntary agreement among municipalities.

One key person should be "in charge of" the effort.  In some

cases, this motivation is provided by circumstances  facing one

of the prospective members.  Federal and State governments

could provide incentives, in the form of technical and  legal
                               6-5

-------
assistance, to entourage more municipalities to use landfill



sharing.



     Preparing a written agreement that sets out in advance



the responsibilities of member municipalities with respect to



liability, insurance, future solid waste disposal capacity,



financial support, and other matters requires a thoughtful



process.  Without such agreements, however, municipalities



having capacity are unlikely to share landfill space.



     Cooperative landfill arrangements, whether for solid waste



or for ash, are a type of landfill use that merits the active



support of State and Federal governments.  EPA supports the



concept of cooperative arrangements as a means to achieve




better landfilling practices.
                               6-6

-------
               PART n
METHANE PRODUCTION AT CLOSED LANDFILLS

-------
                            SECTION 7



                          INTRODUCTION




     At both closed and operating landfills, landfill gas (LFG)



is generated as a product of the anaerobic decomposition of



organic matter and consists of nearly equal parts of methane


and carbon dioxide plus trace amounts of other gases.



     LFG generated at closed and operating landfills poses a



concern for safety.  LFG can migrate both horizontally and


vertically below the surface and may pose an explosive danger



on a landfill and nearby surroundings:  fatalities and property



damage have resulted from LFG explosions.  Control of these gases



through recovery and utilization systems or control systems



can reduce the danger of explosion and may help abate odors,



thus aiding in the beneficial future use of closed landfills.


     The Federal regulations for the control of LFG are published



at 40 CFR Part 257.3-8.  These regulations establish criteria
                                               /


for methane concentrations in the soil at a landfill's property


boundary and in structures on the site.



     Several states have adopted regulations concerning LFG



that include gas control at both operating and closed landfills.


Often, closure requirements address gas concerns, as in the



State of Washington, where most relatively large landfills are



now required to collect or vent LFG.



     LFG can be recovered and used as a replacement for or as



a supplement to natural gas.  Such recovery of LFG is generally



limited to relatively large sites with nearby markets for the
                               7-1

-------
energy.  The recovery of LFG is attractive because it can



reduce gas-related dangers while generating revenue.   However,



limited sites across the nation are viable candidates for LFG



recovery, because potential sites generally must contain a



minimum volume of refuse and have a market for the recovered gas.



The latter sections of this report include discussions of economic



factors that have an impact on gas recovery, and a decision



maker's guide is also provided which describes a methodology that



can be used to perform a preliminary assessment of the viability



(technical and cost) of gas recovery.
                               7-2

-------
                            SECTION 8


          POTENTIAL BENEFITS AND DANGERS OF LANDFILL GAS




     During the natural decomposition of organic waste in waste


disposal sites, gases generated are referred to as landfill gas


(LFG).  LFG is composed of roughly equal quantities of methane


and carbon dioxide, in addition to other trace gases.  Methane


is the principal gas of concern because it can be recovered and


used as an alternative fuel; however, its explosive potential


can pose a danger to persons, structures, and equipment on or


near a disposal site.




RECOVERY AND USE


     At some landfills, LFG can be recovered for beneficial use.


The technical and economic viability of LFG recovery depends on


size and depth of the disposal site and the presence of markets,


among other factors.  Recovery of LFG is similar to that for
                                                *
                                                /

natural gas, in that wells are installed, and a/e connected by
                                 »

manifolds called header pipes.  Gas is withdrawn by applying a


suction to the header pipes.  Before the gas is used, it usually


undergoes processing that removes water and sometimes separates


the methane from other constitutent gases, specifically carbon


dioxide.


     Landfill gas can be used in several ways.  It can replace


or supplement natural gas as a boiler fuel or in other combus-


tion applications.  It is frequently used as a fuel for internal


combustion engines (turbines are used at very large sites) to
                               8-1

-------
generate electricity.  LFG can also be upgraded to pipeline

quality and injected into natural gas pipelines.  This requires

extensive processing to remove the carbon dioxide and other

constituents.

     In the United States, more than 50 sites recover LFG for

commercial utilization (Exhibit 8-1).  Exhibit 8-2 lists LFG

recovery sites that are currently planned.  California currently

leads the list of States with the greatest number of operating

commercial LFG recovery facilities.  Many more projects in other

parts of the country are being evaluated, designed, or have

begun operation.  Within the past several years, State-mandated

closure regulations specific to LFG have increased landfill

owners' interest in using LFG to help offset closure costs and

comply with closure regulations.

     The data in Exhibits 8-1 and 8-2 are summarized in

Exhibit 8-3 to provide a perspective of the end ^use and energy
                                                /
production rate ranges of the 89 active and pla'nned LFG recovery
                                               /
facilities.  More than half (49) of these sites are generating

electricity or plan to do so/ but of the direct gas utilization

sites, only 18 percent (7 out of 40) upgrade LFG to a high-Btu

content.  These figures reflect the versatility of electricity

generation and the limited applicability of upgrading LFG.

     The minimum size of landfill at which LFG can be profitably

recovered is quite variable and highly market dependent.  One of

the smallest landfills at which LFG is profitably recovered is in

Brattleboro, VT, which serves a residential population of about

19,000 plus associated commercial and industrial waste sources.
                               8-2

-------
            EXHIBIT  8-1.  ACTIVE LFG RECOVERY SITES
 Location - Output

 CALIFORNIA

 Azusa  -  1.7  mcf
 Corona - 5 mW
 City of  Industry -  0.5 mcf
 Duarte - 2.3 mW
 Lompoc - 0.6 mW
 L.A. Bradley East - 3.0 mcf
 L.A. Lopez Canyon - 2.0 mcf
 L.A. Mountaingate - 4.0 mcf
 Marina - 1.2 mW
 Martinez (Acme) - 2.0 mcf
 Menlo  Park - 2.0 mW
 Monterey Park - 4.0 mcf, H
 Mountain View - 0.5 mcf
 Mountain View (Shoreline Park) -
  3.5  kW
 Napa County  (American Canyon) -
  1.5  mW                ,
 Olinda - 5.7 mW 1 mcf
 Oxnard - 15.8 mW (in phases)
 Palo Alto -  electricity
 Palos  Verdes - 1.3  mW
 Penrose  - 9.4 mW
 Salinas  - 1.4 mW
 San Fernando (North Valley) -
  1.1  mcf
 San Jose (Newby Island) - 2.0 mW
 San Leandro  (Davis  Street) - 3.0 mcf
 Santa  Barbara County (Tajiguas) -
  electricity                   r
 Santa  Clara  City -  1.4 mW
 Santa  Clara  County  (Guadalupe) -
  1.5  mW
 Stockton  - 1 mW
Sun Valley (Sheldon-Arietta) -
  1.7 mcf, H
Toyon - 9.4 mW
Upland - 0.5 mW
Whittier'(Puente Hills A)
Whittier (Puente Hills B)
Wilmington - 2.5 mcf

CONNECTICUT

Naugatuck - 0.5 mW
4.0 mW
0.17 mcf
  MARYLAND

  Rockville  (Gude) -
    2.8 mW

  MICHIGAN

  Detroit ("Holloway
    Junior") - 1 mcf
  Lansing -  130 mcf/year

  MISSOURI

  St. Louis  - 0.2 mcf

  NEW HAMPSHIRE

  Manchester - 0.7 mW

  NEW JERSEY

  Cinnaminson - 0.5 mcf
  Deptford Township - 2 mW
'  Dover Township - 0.4 mW

  NEW YORK

  Babylon -  0.5 mW
  Holtsvi£le - 0.5 mW
  Huntin/^ton - 1.0 mW
  Onondaga (Syracuse) -
    2 mV/
  Riverhead  - 0.5 mW
  Smithtown  (public) - 0.5 mW
  Smithtown  (private) -
    1 mW
  Staten Island (Fresh

    Kills) - 10.0 mcf, H
  Yaphank -  2.0 mW

  NORTH CAROLINA

  High Point - 3 mcf

  OREGON

  Oregon City - 2 mcf, H
                               8-3

-------
         EXHIBIT 8-1.  ACTIVE LFG RECOVERY SITES (CONT.)
FLORIDA

Pompano Beach - 3.3 mcf, R

GEORGIA

Atlanta - 3 mcf
Macon - 2 mcf

ILLINOIS

Blue Island - 4.0 mcf
Calumet City - 2.5 mcf, H
Chicago (CID) - 3.5 mcf

CANADA

Germanton - 6.6 mW
Kitchener - 0.5 mcf
PENNSYLVANIA

Lebanon - 1.2 mW
Montgomery County - 6mW
Scranton - 2 mcf, H

VERMONT

Brattleboro - 0.3 mW

WASHINGTON

Vancouver (Leichner) -
  0.35 mcf

WISCONSIN

Franklin - 3.3 mW
NOTE:

Output figures, actual or estimated, are in millions of cubic feet
per day (mcf) of natural gas or in megawatts (op kilowatts) of a
site's electrical generation capacity.  The letter "H" in the copy
indicates high-Btu gas is produced by a site; all others report.
medium Btu output.         •                   >
SOURCE:  Waste Age, March 1986,
                               8-4

-------
             EXHIBIT 8-2.  PLANNED LFG RECOVERY SITES
Location - Output

CALIFORNIA

Bonsall - 1.4 mW
Burbank - 500 kW
Fresno - 3.5 mW
Fresno (BFI) - 1 mW
Fresno County - 750 kW
Kern County (China Grade) -
  1.5 mW
Orange County (Coyote Canyon) -
  20 mW
Otay - 1.9 raw
Ox Mountain - 1 mW
San Jose (Singleton Road) -
  1.0 mW
San Marcos - 1.9 mW
Saugas - 1.4 mW
Whittier (Puente Hills) - 40 mW
Yolo County - 2 mW       /
Yuba/Sutter - 1.5 mW

CONNECTICUT

New Milford - 1.2 mW
Torrington - 0.25 mW
Wallingford - 0.6 mcf

DELAWARE

Pigeon Point - 1.5 mcf

FLORIDA

Lantana/Lakeworth - gas
Pasco County - electricity

ILLINOIS

Barton - medium Btu gas
MARYLAND

Montgomery County - 2.5 mW
Prince Georges County -
  1.0 mcf, 30 mW

MASSACHUSETTS

Amesbury - 2.5 mW
Worcester - 2.3 mcf

MICHIGAN

Detroit (Holloway) - 6.0 mcf,
  H
Riverview - 7.5 mW

NEW HAMPSHIRE

Nashua - 2.0 mW

NEW JERSEY

Kearny - 6 mcf

NEW YORK

Albany - 1.5 mcf
Bronx - eleptricity
Brooklyn (Bountain Ave.) -
  6 mcf
Goshen - 245 mW
Islip - 2 mW
Merrick - electricity
Oceanside - gas, H
Oyster Bay - 2 mW
Port Washington - 1 mcf

NORTH CAROLINIA

Greensboro - 3 mcf
Winston-Salem - 0.85 mcf

OHIO

Cincinnati (Rumpke) - 6.0 mcf
                               8-5

-------
         EXHIBIT 8-2.  PLANNED LFG RECOVERY SITES (CONT.)
OREGON

Newburg - 1.5 mW

PENNSYLVANIA

Boyerton - 1 mW
F. R. & S. - 1.3 mW
GCS  (PenArgyl) - 2 mW
Helva (Whitehall) - 1.2 mW

RHODE ISLAND

Cranston - medium Btu gas
Cumberland - 0.8 mcf
Johnston (Central Landfill) -
  4.5 mW
SOUTH CAROLINA

Greenville - gas

TEXAS

Ft. Worth - gas or
  electricity
Houston (McCarty road)
  89.0 mcf

VERMONT

Rutland - 500 kW
NOTE:

Output figures, actual or estimated, are in millions of cubic feet
per day (mcf) of natural gas or in megawatts (or kilowatts) of a
site's electrical generation capacity.  The letter "H" in the copy
indicates high-Btu gas is produced by a site; a,ll others report
medium-Btu output.                            /
SOURCE:  Waste Age, March 1986.
                               8-6

-------
                           EXHIBIT 8-3


     LFG RECOVERY SITES BY END USE AND ENERGY PRODUCTION RATE
                    Generation of Electricity
    Active
Planned
Energy Production Rate Range
(Megawatts) No.
0- 2
2- 5
5-20
Total
10
9
J5
24
Energy Production Rate Range
(Megawatts) No.
0- 2
2- 5
5-40
Total
13
8
^4
25
                          Medium Btu Gas
    Active
Planned
Energy Production Rate Range
(mcf/day) No.
0- 2
2- 5
5-10
Total

Active
13
9
_2
23
High Btu Gas

Energy Production Rate Range
(mcf/day) No.
0- 2
2- 5
5-10
Total
1
-1
4
Energy Production Rate Range
(mcf/day) No.
0- 2
2- 5
5-10
Totffl
/
Planned
5
3
10


Energy Production Rate Range
(mcf/day) No.
0- 2
2- 5
5-10
Total
1
0
_2
3
Totals may not add to that shown on Exhibits 2-1 and 2-2 due to
mixed-use facilities where no end use quantity was specified.
                               8-7

-------
The site receives approximately 40 tons of refuse per day and has

some 360,000 tons of refuse in place.(1)  This site is far smaller

than the 400 tons per day often considered to be the minimum

required for profitable LFG recovery, thus illustrating the

site-specific, variable nature of such projects.



MIGRATION AND EXPLOSION


     Landfill gas is generated below the surface of disposal sites

and tends to migrate along paths of least resistance, eventually

venting into the atmosphere above the site.  If a natural or man-

made, relatively impermeable layer is present and overlays a

relatively permeable layer, LFG can migrate laterally.  Lateral


migration can extend up to several thousand feet or more from a

landfill and create a hazardous condition.  LFG tends to accumulate

in enclosed spaces such as cavities in the landfill or in basements,


crawl spaces, or even rooms in structures.  As a primary compo-

nent of LFG, methane accumulated in such spaces* poses danger
                                              /
because it is explosive even whefo it comprise^ as little as 5

to 15 percent of the air mixture (referred to as the lower

explosive limit or LEL).  When methane comprises more than 15

percent methane, the mixture is flammable. (2)  Although explo-

sions of LFG are not common, such events have damaged structures

and equipment and caused injuries and fatalities.  Explosions


have occurred on landfills and in adjacent structures including

occupied houses.  Exhibit 8-4 is a tabulation of some of the

damage cases attributed to LFG migration.
                               8-8

-------
     Migration of LFG and its explosive potential can be controlled.



Numerous engineered systems can be used to prevent the migration of



LFG from a disposal site or to protect individual structures.  These



systems often include gas monitoring facilities.  Generally, gas



control systems prevent migration through the use of barriers or



by safely venting LFG to the atmosphere.





REGULATIONS



Federal



     There are no Federal regulations for the recovery and use



of LFG.  The Environmental Protection Agency has published the



Criteria for Classification of Solid Waste Disposal Facilities



and Practices at 40 CFR Part 257.3.  These criteria essentially



define a sanitary landfill, but are neither binding on the



States nor Federally enforceable.  Explosive gases (methane) are



addressed in 40 CFR 257.3-8, which specifies that methane is not



to be present in the soil at the property bounda/y above its LEL,
                                                /


nor is it to be above 25 percent of the LEL in atay site structure.



State



     Several states have adopted regulations that address LFG



control at both operating and closed landfills.  In many states,



closure requirements often address gas concerns.



     States with LFG regulations include Florida, Pennsylvania,



California, and Washington.  Florida has closure plan regulations



requiring sanitary landfills to conduct a gas migration inves-



tigation.  This investigation must include monitoring of test



points along the property boundary and within on-site structures.
                               8-9

-------
                                                                EXHIBIT 8-4

                                                    LANDFILL GAS MIGRATION  DAMAGE CASES
         Landfill  Name,
         Location,
         and Date
                          Methane Detected
                          Off-Site AboveLEL?/
                          Di stance*
                       Explosion/    Landfill  Characteristics
                       Fire?**       And Corrective Action*
                                         Damages and Other
                                         Comments
                              Data Sources
         Bakersfield
         Fresno,CA.
         April  1984
            Landfill
Yes/N/A
Yes           Control system installed
On-Site       after incident.
Fresno police bomb squad
used site for practice
A bomb was buried and
was detonated causing
LFG explosion.

Explosive levels of
methane were migrating
off-site
oo
Operating Industries
Landfill
Monterey Park, CA
August 1983
                                   Yes/No information      No
                                   aval table
                                     Class 1  landfill
                                     LFC recovery system
                                     present
                                     Control  system existed
                                     prior to incident.
                                         Vinyl  chloride detection
                                         casued SCAOMD to  order
                                         30-day shutdown of  land-
                                         fill.   It  reopened,
                                         subject to closure  in
                                         six-months.
         BKK Landfill
         West Covina, CA
         August-October 198%
         WalHngforrf Landfill
         Wallingford, CT
         June 1984
         Shawnee County Landfill
         Topeka, KA
         August 1983
                          Yes/250                Yes
                          Yes/No Information     No
                          available
                          Yes/NO information     No
                          available
                                     Class I  Landfill
                                     Control  System
                                     expanded after
                                     incident.

                                     LFC recovery
                                     system present.
                                      No information
                                      aval I able
                                         Twenty residences  temporarily
                                         evacuated due  to explosive
                                         methane levels  in  adjoining
                                         soiIs.

                                         Explosive levels of methane
                                         detected in dog pound.
                                         Dog  pound temporarily closed,
                                         ventilation system to be
                                         installed.

                                         Home abandoned  due to high
                                         methane levels.
                                  I,  2
                                  1,
         Symbols

         N/A   Not applicable
         *     Reported distance (in feet)  of maximum migration,  or  distance  to
               affected structure.
         **    Personal injuries sustained  and/or  death occured.
         *     Landfills are municipal  solid waste landfills  (publicly  or  privately
               owned/operated)  unless otherwise noted.
                                                                            Sources

                                                                            I.   UPI or other  news sources
                                                                            2.   SCS Engineers
                                                                            3.   Contact with  local officials
                                                                            4.   Princeton's Risk Assessment of the Monument Street Landfill
                                                                            5.   "Gas Control  in Landfills:  A Case Study"  paper presented
                                                                                by Donald  L.  Feuerstein at the Fifth National Congress
                                                                                On Paste Management Technology and Resouce and Energy
                                                                                Recovery,  Dallas, TX, December 7-9, 1976.

-------
                                                                EXHIBIT  8-4  (con't)

                                                        LANDFILL  GAS  MIGRATION DAMAGE CASES
          Land?III  Name,
          Location,
          and Date
             Methane Detected
             Off-Site Above LEL?/
             Distance*
                        Explositon/
                        Fire?**
               Landfill  Characteristics
               and Corrective Action
                           Damages and Other
                           Comments
                              Data Sources
oo
 I
          Anderson Township Landfill
          Cincinnati, OH
          1983
          Warner Hill  Landfill
          Cleveland, OH
          1980
          Fells Street Landfill
          Richmond, VA
          1975
                Yes/300
                Yes/I00
                Yes/20
          Fells Street
          Richmond, VA
          1982
Landfill
No/tN/A
                        Yes**
                        Off-Site
                        Yes**
                        Off-Site
                        Yes
                        Off-Site
Yes**
On-Site
          Ocean County Landfill
          Manchester, NJ
          December 1983
          Hanaque, NJ
          March, 1984

          Babylon Landfill
          Comaek, NJ
          May 198%
                No/N/A
                No Information
                available

                Yes/50
                        Yes
                      k-»n-Site
                                                              Yes
                        Yes**
                        On-Site
               No Iiner present.
               Control  system in-
               stalled  after  the
               incident.

               No liner present.
               SoiIs consist  of
               silt  and clay.
               Control  system in-
               stalled  after  the
               incident.

               No liner present.
No information
available.
               Ventilation and alarm
               systems to be installed
               in the remaining mainten-
               ance garage.
               Control  system proposed
               for school  located on  a
               closed landfi11.
               No liner present.  Sandy
               Soils.   Control  system
               installed after  incident.
                           Explosion destroyed re-              2
                           sidence across the street
                           from the landfill.  Minor
                           injuries reported.

                           Explosion killed foundry             2,  3
                           worker on site adjacent
                           to landfill.
In 1975, explosion occurred in       2, 3
nearby apartment building.
The City decided to buy and de-
molish it.  Two schools sited
on the landfill were closed until
a control system was installed.

The 1982 incident occurred when      2, 3
children trespassed onto the
landfill site, entered a control
system manhold, and lit a match,
resulting in an explosion.  The
nature of the associated injuries
has not been disclosed.  The
case is in litigation.

Spark from landfill pump probably    1
ignited methane gas, causing ex-
plosion and fire.  One person
sustained first and second degree,
and flash burns. .Office building
destroyed.

No information available.             1
                                                                                 Methane migrated to the scale-        1,  2
                                                                                 house on-site.  Explosion killed
                                                                                 one person and injured another.
          Symbols and Sources (Refer  to first page)

-------
                                                             EXHIBIT.8-4  (con't)

                                                     LANDFILL GAS MIGRATION  DAMAGE CASES
          Landfill Name
          Location,
          and Date
                          Methane Detected       Explosion/
                          Off-Site Above LEL?/   Fire?**
                          Distance*
               Landfill  Characteristics
               and Corrective Actions-
Damages and Other
Comments
Data Sources
          Monument Street Landfill  Yes/No Information     No
          Baltimore, MA.            available.
          April  1983
oo
I
          PJP Landfill              No/N/A
          Jersey City, NJ
          I98
-------
                                                             EXHIBIT 8-4 (con't)
                                                      LANDFILL  GAS  MIGRATION DAMAGE  CASES
         Landfill  Name,
         Location,
         and Date
                          Methane Detected
                          Off-Site Above LEL?/
                          Dlstance*
 Explosion/     Landfill Characteristics
 Fire?**       and Corrective Action*
Damages and Other
Comments
Data Sources
         Lees  Lane Landfill
         Louisville,  KY
         1978
                          Yes/I,000
         Allegheny County Landfill  Yes/200
         Frostburg, MD
         1978
oo
U)
>
Beantown Dump
Rockvitle, HD
1980
         Winston Salem, NC
         1969
                                   NO/N/A
                          Yes/100
         Port Washington Landfill   Yes/200
         North Hempstead, NY
         1981
         Snithtown Landfill
         Smlthtown, NY
                          Yes/200
 Yes**        No  liner present.
 Off-Site     Soils  are clayey silt
              to  gravelly  sand.
              Control system  installed
              after  the incident.

 Yes**        No  liner present.
 Off-Site     Soils  are silt  and
              clay.  Control  system
              installed after the
              incident.
,Yes**         Old,  inactive  dump
 Off-Site      site.   Building con-
               structed on  inactive
               disposal site.
               Control system in-
               stalled after  the
               incident.

 Yes**         Codisposal
 Off-Site      No liner present.
               Control system in-
 .-,             stalled after  the in-
  v»         cident.
 Yes**         Liner  present
 Off-Site      Soils  sandy with  some
               clay and  silt  layers.

 Yes**         Liner  is  present.
 Off-Site      Soils  are sandy
Small fires and explosions.
Several houses evacuated 
-------
                                                            EXHIBIT 8-4  (con't)

                                                   LANDFILL GAS MIGRATION  DAMAGE CASES
       Landfill  Name,
       Location,
       and Date
                             Methane Detected
                             Off-Site Above LEL?/
                             01 stance*
                        Explosion/     Landfill  Characteristics
                        Fire?**        and Corrective Action*
                                           Damages and Other
                                           Comments
                                                            Data Sources
       Hardy Road Landfill
       Akron, OH
       1984
                             Yes
                             500-1,000
                        Yes**          No liner present.
                        On-Site        Control  system in-
                                       stalled  after incident.
                                           One house destroyed.
                                           Ten houses evacuated
                                           temporarily.  Several
                                           minor injuries.
                                                                1, 2
oo
*—•
u>
00
       Landfill  near
       Lake Township
       Canton, OH
       198%
Tyler, TX
Nay 1982
       I-95 Landfill
       Lorton, VA
       1984
                             Yes/No information
                             available
No/N/A
                        No
"No
                             Yes
                             300-1,000
                        Yes**
                        Off-Site
                                       No information
                                       available.
Control system existed
prior to incident.
                No  liner present.
                Soils range  from
                clay to sandy clay
                to  sand.
                Control system
                installed after the
                incident.
                                           Two homes and a day
                                           care center temporarily
                                           evacuated.
TOPS office building sited
on closed landfill.   Methane has
caused problems since early 1970's.
Failure of ventilation exhaust fan
resulted in "significantly high"
levels of methane in the building.
One man was fatally injured and
another burned over 50% of his
body during explosion and limited-
f i re.
                                                                I,  2
       Creentree Hills Landfill      Yes
       Madison, Wl                   100-150
                        Off-Site
                                                                    Soils  are  composed of
                                                                    clay,  glacial  fill,
                                                                    sand,  weathered  and
                                                                    fractured  bedrock.
                                           Explosion blew out one sidewall  of    1,3
                                           a townhouse.  Three adjacent apart-
                                           ment buildings and several  homes
                                           evacuated for 20-30 days.   Two
                                           people seriously injured.  Claims filed
                                           against the; City total  $5.2 million.'
                                           dollars.
       Symbols and Sources  (Refer  to  first page)

-------
Gas control systems are required at sites where methane concen-


trations exceed the LEL in soils at the property boundary


or 25 percent of the LEL within structures on the property.   In


addition, Florida's sanitary landfill criteria require that,


"All sanitary landfills where gas generated by decomposition of


wastes is not readily dispersed into the atmosphere shall be


provided with a gas control system."(3)  The criteria further


requires that emissions from a gas control system not violate


state air quality standards.  Gas control systems have also


been installed to reduce odors.


     Most States have adopted EPA's criteria for methane


concentrations in on-site structures and in the soi] at property


boundaries, or have more stringent criteria.  For example, the


State of Washington requires that methane must not be present


in off-site structures above 100 parts per million by volume of


hydrocarbons.  Their criteria apply to both operating landfills
                                                *
                                                /
and those closed after the effective date of the' legislation,
                                  r

November 27, 1985.(4)  Landfill operators in Washington State may


be required to monitor for LFG at the property boundary and in


on-site structures and to report the results to county health


departments on a quarterly basis.  A State-approved LFG monitoring


plan may be required.  Operators of large landfills in Washington


(greater than 10,000 cu. yd. per year) must continuously collect


methane either for sale, for flaring, or for utilization as


energy.  However, operators of smaller landfills are not subject


to this requirement, and may vent LFG in lieu of the above.(4)
                             8-14

-------
OTHER ENVIRONMENTAL CONSIDERATIONS


     Aside from safety aspects of explosion and fire,  there are


othar environmental concerns associated with landfill gas and


collection systems.  First is the subject of condensate.   When


landfill gas is first removed from extraction wells, it is usually


quite warm and high in entrained moisture which will drop out as


liquid (or "condensate").


     In general terms, there are two types of condensate associated


with collection systems.  The first type drops out in collection


pipelines.  Unless handled properly, these liquids can accumulate


at low points and eventually block gas flow.  To prevent this,


collection piping is sloped to pre-defined low points.  Dedicated


"moisture traps" collect condensate for control.


     The second type of condensate is that which drops out at the


gas processing facility, usually the result of active LFG dehydra-


tion.  Most States will not allow disposal of these liquids back


to the landfill.  States typically require that these liquids be
                                                 t
                                                 r
treated and/or hauled off-site.  Depending on composition, con-
                                  r
densate may be a hazardous waste, increasing further the cost for


condensate handling.


     Trace constituents are a second environmental concern


associated with gas control and recovery systems.  Trace consti-


tuents comprise less than one percent of LFG, and may include


volatile organic compounds (VOCs).  Vinyl chloride, benzene,


toluene,  and xylene are examples of VOCs.  Many of those compounds
                               8-15

-------
are toxic at certain concentrations.  Though the concentrations

of those compounds do not usually exceed applicable health

standards, they may exceed some State ambient air guidelines/

standards in some instances, and have garnered attention from

State and local regulatory authorities.  Proper LFG control and

combustion should reduce VOC concentrations to below acceptable

levels.

     A third environmental concern is flaring of LFG.  Disposal of

collected LFG can be a problem at gas control sites, or even

recovery sites where more gas is withdrawn than can be used.  If

freely vented, LFG can cause odor problems and/or other concerns

(see above).  The usual approach is to combust the gas on-site.

Simple combustion uses the methane content of the LFG itself, and

auxiliary fuel is not usually required.  Burning the LFG is mostly

successful in abating any odor problems (malodorous compounds are

destroyed), and in reducing VOCs to safe levels.  LFG combustion
                                               /
can be performed with simple candle flares, or/with more sophisti-

cated combustion units (e.g., ground flares and even incinerators)

which enclose the combustion process, may require auxiliary fuel,

and generally achieve greater gas destruction.
                               8-16

-------
REFERENCES
1.  Personal Communication, Lewis Audette,  President,  New England
        Alternate Fuels, June 2, 1986.

2.  National Fire Protection Association,  Fire Protection Guide
        on Hazardous Materials, 7th Edition.   Section 325 M.  1978.

3.  Florida Administrative Rules 17-7.073,  Sanitary Landfill
        Closure Plan Requirements.

4.  Washington Administrative Code 173-304, Minimum Functional
        Standards for Solid Waste Handling.
                               8-17

-------
                              SECTION 9


                       LANDFILL GAS GENERATION




     When organic matter decomposes, it is transformed into a


variety of simpler organic materials by the action of micro-


organisms abundant in solid waste.  Some of the components in


the solid waste have already begun to decompose before being


disposed in a landfill.  Typically, early decomposition of such


components is caused by aerobic bacteria utilizing readily


available oxygen.  The oxygen is readily depleted and anaerobic


processes then begin decomposing the organic constituents.


     These processes, both aerobic and anaerobic, produce


principally methane and carbon dioxide.  The rate of the LFG


production is dependent on a number of site-specific factors,


including the age of the landfill, moisture content and solid


waste composition and quantity.  Other factors that affect LFG


generation are temperature conditions in the lajfdfill, nutrients,
                                               /

infiltration of oxygen, and the in-place density of the refuse.


     LFG generation begins almost immediately upon burial


and increases rapidly with steady generation beginning within


several months to a year.  Relatively steady generation may


continue for ten years or longer.(1)  Thereafter, the generation


rate decreases, but gas generation continues for many years.


These changes in generation rates are illustrated in Exhibit 9-1


and are based on the assumption that LFG generation is based


on so-called "zero order reaction rates".  Not all authorities


agree with this assumption and since LFG research has only been
                              9-1

-------
                            EXHIBIT  9-1  EXAMPLE OF LFG GENERATION VS TIME
 o
 c
 o
 o

 *J
 
      0.75 -\
      0.50
      0.25 4
                      5
10
15
                                                          20
                                   25
                                    30
                                             Time (years)

-------
conducted for the past 10 to 15 years, little data are available



to support one hypothesis over another.



     There is current research relating to enhancing methane



production through utilization of sewage sludge.  Preliminary



results show that with the addition of sludge cake to municipal



refuse, the production of LFG is hastened.  Total gas production



from test cells vs. control cells (those without sludge added)



is about the same.
                               9-3

-------
REFERENCES
    Lockman and Associates, Inc. Recovery, Processing,  and
        Utilization of Gas from Sanitary Landfills.
        U.S. Environmental Protection Agency.  Report No.
        EPA-600/2-79-001.  February 1979.
                              9-4

-------
                            SECTION 10

                      LANDFILL GAS RECOVERY


     Recovery of LFG for beneficial use is currently practiced

at more than 50 locations nationwide with more than 40 other

systems in the planning stages, as shown in Exhibits 8-1 and

8-2 respectively.  This section addresses four topics related

to LFG recovery:  uses of recovered gas, criteria for the

selection of sites suitable for gas recovery, technical factors

related to LFG recovery, and LFG processing techniques.


USES OF RECOVERED GAS

     LFG can be used directly as a medium-Btu fuel or upgraded

through processing to a higher heating value.  LFG recovery

projects to date have concentrated on three general uses:

     0 Direct use of medium-Btu gas by industrial customers after
       minimal processing for water removal.

     0 Combustion of medium-Btu gas to generate/'electricity for
       sale to the local utility^             '

     c Upgrading of LFG to pipeline standards (high-Btu) for
       injection into utility (natural gas) pipelines.

     The production of medium-Btu gas for direct use in boilers

or similar applications is the simplest process.  In this case,

LFG is typically processed to remove entrained moisture and

particulates.  The product gas has an energy value ranging from

400 to 600 Btu per cu. ft.(l), making it suitable as a boiler

fuel, and can be sold for this purpose to industries nearby.

Industries currently utilizing LFG include refineries, chemical

plants, and power plants.
                              10-1

-------
     Medium-Btu LFG can also fuel internal combustion engines

or gas turbines to generate electrical power after moisture,

particulates, and corrosive materials have been removed from

the gas.  Although steam boilers could provide higher efficiencies

than internal combustion engines, the capital and operational

costs of a steam plant require a large-scale operation (greater

than 20 megawatts) to be economically viable.(2)  At present,

no LFG recovery projects employ a steam boiler for on-site

power production; only some of the nation's largest landfills,

such as the Fresh Kills Landfill on Staten Island, produce

enough LFG necessary to run a 20 mW (megawatt) plant.  Generation

of electricity may be enhanced with passage of legislation

requiring public utilities to purchase electricity from qualifying

facilities at the utility company's avoided cost.  The avoided

cost represents the cost to the electric utility of generating

the next increment of electricity.  However, these prices are
                                               /
sensitive to costs for fossil fuels used to generate electricity.

     The third category of LFG use is upgrading to pipeline

quality standards.  The production of pipeline quality gas

(950 to 1,000 Btu per cu. ft.) requires removal of carbon dioxide,

moisture, and particulates, and possibly other trace gases.

Carbon dioxide can be removed via several treatment processes

including physical absorption, chemical absorption, and membrane

separation.  If nitrogen is present, it can be removed by

fractional liquifacation.  The cost is usually so great, however,

that this option is precluded when significant air (nitrogen)

intrusion is present.  Because of this, high-Btu gas production


                              10-2

-------
systems typically withdraw less of the available LFG than other


systems in order to prevent the air intrusion caused by high


pumping rates.




CRITERIA FOR SITE SELECTION


     The quantity, quality, and ability to collect LFG, and the


availability of markets are factors critical to the success of


a LFG recovery project.  Until LFG is collected and sold, it is


merely a waste product representing a potential odor or migration


liability.


     Assuming that LFG markets are present,  potential recovery


sites are generally evaluated based on the following five criteria:


     1.  Amount of refuse — The quantity of LFG produced depends


         first on the amount of refuse available for decomposition.


         For commercial applications, an LFG recovery site should


         have a minimum of roughly one million tons of refuse in


         place, an average depth of 40 feet, and a fill area of  40
                                               /
                                              /

         acres.(1)  These figure? are general guidelines based on


         engineering experience.  Generally, sites which fall below


         these limits are too small (thus producing too little


         gas to be economically recovered and used), or too shallow


         (thus making it difficult and/or expensive to recover).


         An engineering evaluation and projection of LFG use for


         each site should be conducted.


     2.  Refuse composition and moisture content — Waste compo-


         sition can limit both the total yield and rate of LFG
                              10-3

-------
    production.  In general, LFG production is stimulated

    by a waste having a high percentage of readily decompos-

    able organic materials  (e.g., food and garden wastes).


    The recoverable landfill gas is derived from biodegra-

    dation of these and other organic constitutents.

    Sufficient moisture must be present to support the

    biological activity and nutrient transport necessary for

    LFG production.  Moisture content and movement are

    generally the limiting  factors in LFG production,  with


    disposal sites in arid  locations generating LFG at a

    slower rate for a longer duration.  Too much moisture

    can inhibit LFG migration to the collection system,


    plug collection wells,  and promote the generation

    of leachate.  In addition, toxic industrial wastes or

    other inhibitory materials present can upset the

    activity of methane-forming bacteria and reduce LFG


    generation rates.
                                            /
3.  Age of the landfill — As biodegradaticfh of organic
                                           /
    materials is completed, LFG production is reduced to

    a minimal level.  Therefore, older disposal sites will

    produce less LFG because the decomposition rate has


    decreased.  The rate of LFG generation through decomposition

    of buried wastes determines the useful life of a landfill


    for gas recovery.  This generation rate varies


    significantly among landfills, but the total volume

    of LFG generated is thought to be fairly constant.
                         10-4

-------
    The area under the curve illustrated in Exhibit 9-1

    is the total volume of LFG generated.   Basically,  the

    LFG generation rate increases with time during active

    filling.  Shortly after filling is complete,  the rate

    levels off and remains relatively constant.   This

    steady-state condition may endure 10 or more years,

    depending on the actual conditions which exist in  the

    landfill.  For example, a moist landfill with a high

    generation rate per unit mass will have a shorter

    life than a dry landfill with a lower generation

    rate.(3)  In either case, a point is reached where

    the generation rate begins to decline as the quantity

    of decomposable matter decreases.  At some stage,  the

    rate of LFG production is reduced to an amount below

    that necessary for viable recovery.

4.  Receipt rate — The average age of the refuse in a
                                           /
    landfill is directly related to the rate at which

    refuse was received during the site's operational

    life.  The lower the receipt rate, the greater the

    decomposition at the time of closure.   To assure an

    adequate quantity of LFG production, a potential

    recovery site should have a receipt rate of at least

    400 tons per day or more.(4)  However, much smaller

    sites are recovering LFG, including the landfill at

    Brattleboro, VT, where waste receipts average less

    than 40 tons per day.(5)
                         10-5

-------
5.  Permeability of cover and surrounding soils  — Landfill


    sites constructed in or with impermeable soils or  materials


    are favorable for LFG recovery.   Because LFG tends to


    travel the path of least resistance,  its tendency  to


    migrate increases with the permeability of surrounding


    soils.  High permeability soils,  i.e.,  sand and gravel,


    allow LFG to escape from the landfill,  thereby inhibit-


    ing recovery.  Landfills constructed  with impermeable


    materials, such as clay soils and synthetic caps,


    prevent the escape of LFG and inhibit the entry of air


    into the landfill during LFG recovery.   This containment


    is important because air decreases LFG quality and also


    inhibits methane production by anaerobic bacteria.



    At closure a sanitary landfill is to  be provided with a


    cap of compacted soil.  Such caps decrease LFG escape


    through the surface.  Post-closure construction activities
                                          t

    such as paving or compacting the landfall surface  also


    aid in preventing LFG escape.  However, one drawback of


    making the landfill surface less permeable is that it


    promotes lateral migration if the surrounding subsurface


    soils are more permeable than the cap.   Thus, if LFG is


    not being extracted from a capped landfill,  the landfill


    perimeter should be monitored to detect any migration


    and identify the possible need for LFG control.
                            10-6

-------
TECHNICAL FACTORS RELATED TO LFG RECOVERY


     The first component in LFG recovery is the collection

system.  The design of the collection system depends primarily


on landfill conditions.  LFG collection typically involves an

induced exhaust well system, which extracts LFG through a net-

work of wells joined by a header pipe to a blower.  Exhibit 10-1

depicts a typical layout of an extraction system.  Wells are

drilled in the refuse with perforated pipe placed into a gravel-

packed section of each boring.  This perforated zone is typically

designed to be about half the depth of the well and is located

in the lower portion to minimize air intrusion.  Exhibit 10-2

shows a detail of a typical LFG extraction well.  Other design


elements include the well depth, spacing, and setback distance


from the landfill perimeter.

     The design of the collection system does not depend on the

intended end use for the LFG, but rather on landfill conditions.
                                                i
For example, recovery well depths are typically designed to be

50 to 90 percent of the landfill depth.(6)  Similarly, the

setback distance from the landfill perimeter will depend on the

cover material.  Since the permeability of the cover material

determines the likelihood of air intrusion through the side

slopes, the setback distance will vary accordingly to minimize

intrusion.  The steepness of the sideslopes must also be

considered since flatter slopes decrease the possibility for

such intrusion.

     Well spacing depends on the planned flow rate, and is
                              10-7

-------
                                                                    FACTORY.
O
oo
                REFUSE FILL
                                  EXHIBIT  10-1   LANDFILL GAS RECOVERY SYSTEM

-------
            HEADER PIPE
                                            *»" DIAMETER PVC PIPE
                                              3' IMPERMEABLE PLUG
                                                GRAVEL BACKFILL
                                               SL9TTED PIPE
    REFUSE
                                 HOLE
EXHIBIT  10-2    TYP1CAL
                             10-9

-------
usually based on a concept called the "radius of influence."


The radius of influence describes that landfill area within


which the extraction well causes a change in pressure.  The


size of the radius depends on such parameters as refuse density,


LFG production rate, and landfill depth, and is often determined


empirically, using data from a pump test program.  A typical


test program will apply varying pumped withdrawal rates to an


extraction well, and measure the corresponding pressure changes


in surrounding monitoring wells.  After the radius of influence


is estimated, the well-spacing for the full-scale design can


be determined.


     In addition to the vertical well systems described above,


LFG can also be extracted by means of a trench collection


system, also called a horizontal well system.  This type of


system requires installation of trenches as the landfill


progresses.  The trenches consist of rows of crushed stone
                                               /

running the length of the landfill and located^ at various
                                »

levels as the landfill expands vertically.  The stone surrounds


a perforated pipe connected to a header pipe at one end, and


as with a vertical well system, LFG is extracted by a blower


connected to the header pipe.


     Regardless of the type of collection system, vertical or


horizontal wells, the rate of LFG production at the specific


site determines the upper boundary of recovery rates.  Ideally,


the recovery system should collect LFG at the same rate it is


being produced within the landfill.  Under such ideal conditions,


no LFG would be available for migration, and no air would be




                              10-10

-------
drawn into the landfill.


     A well-designed and constructed recovery or control system


need not have negative impacts on the end use of the site.


Both horizontal and vertical well systems can be built with


virtually all collection pipes and equipment below the surface.


Only blowers, gas processing equipment, controls, and flares


are above the surface, where they can be centrally located and



designed for minimum visual and operational impact.  An excellent


example of a methane recovery system designed to complement


landfill end use is the Industry Hills Civic-Recreational-


Conservation Area located in the City of Industry, California.


There, a vertical well system recovers methane from a closed


municipal landfill.  The surface of the site is used as a golf


course with the gas used for space and water heating at a



convention complex next to the golf course.  This project was


selected as the Outstanding Civil Engineering Achievement of
                                                /

1981 by the American Society of C^ivil Engineers'. (7)
                                               /



LANDFILL GAS PROCESSING


     Landfill gas is seldom used directly upon withdrawal from


a site.  The type and degree of processing depends on the charac-


teristics of the gas and the end use.  Exhibit 10-3 illustrates


typical processing steps.  Each step is briefly described below


followed by a methanol process that combines three operations.


Particulate Removal



     Particulates are sometimes entrained in the LFG stream


as the gas is drawn from the landfill.  The simplest removal
                              10-11

-------
technique is reduction of gas velocity, whereby LFG passes


through a tanK-like vessel where its velocity decreases and


particulates drop out via gravity.  Another method is the use


of a venturi scrubber.


Trace Constitutent Removal


     Trace constituent removal can be accomplished using any


of a number of solvent, membrane, and carbon treatment systems.


For example, the solvent process involves absorption of these


constituents in a relatively small amount of the solvent, which


is regenerated by application of heat sometimes aided by the


addition of air.  The membrane technology process, also called


physical membrane separation, is a proven technique for removing


trace constituents (gases) using mechanical separation.


Carbon Dioxide Removal


     Carbon dioxide is removed for high-Btu applications.  Its


removal results in the production of pipeline quality methane.
                                               7

The most practiced methods by which carbon dioxide is removed


from LFG are adsorption.  Carbon dioxide removal can also be


accomplished using membrane technology.


Dehydration


     Landfill gas usually has a high moisture content as it


first comes from a well collection field.  This moisture is


highly corrosive, and can cause problems with recovery, proces-


sing, transmission and user equipment.  Depending on the


initial moisture content and the end-use requirements, various


methods can be applied to remove this water.  Once removed,
                              10-12

-------
                                 EXHIBIT  10-3

                     GENERALIZED SCHEMATIC  OF LFG  PROCESSING
                                     Raw LFG
                                        J
                               Participate Removal
                                        J
                             Compression/Dehydration
                                        I
                            Trace Constituent Removal
                                        I
                             Carbon Dioxide Removal*
                                        I
                                     End Use

BSSeBS»SS88BS=SSS88SSBS3SBSB8SBS3SBSBSSS83SS88BS388B8S3SSS83SBSS8BSS88SBS3BSaSS

NOTE:

Any combination of unit processes may be used depending on gas characteristics and
end use.                                          /
*  Only for high-Btu applications'
                                     10-13

-------
the liquid is known as condensate.



     One way in which water is removed from the gas stream is



cooling of the gas.  A certain amount of cooling is inevitable



in any collection system, as hot gas is removed by wells deep



in the landfill and brought into contact with cool ambient air



in collection pipes on or near the surface.  This liquid is



collected and controlled via "moisture traps" (see page 8-15).



     Additional processes can further reduce the remaining



moisture content of LFG.  One of the most effective approaches



for a landfill gas application is cooling of the gas using



mechanical refrigeration.  The refrigeration cools the gas to



a temperature usually above 32° F and condenses the majority



of the water vapor.  The water vapor is then separated as a



condensate and the partially dehydrated gas is then available



for use.  Additional dehydration can be achieved by reducing



the temperature to below 32° F.  However, in order to avoid



freezing,  a substance such as methanol must be ipjected so
                                                /
                                               /
that the condensate can be removed as a liquid.'

                                               /

     Other methods of dehydration have been attempted with LFG



but have not been completely successful.  These methods include



the use of triethylene glycol which is used in the natural gas



industry for dehydration.  This method is sensitive to chlorides



and oxygen that may be present in LFG and will deteriorate the



glycol solution, creating a corrosive product.
                              10-14

-------
Methanol Wash
     Methanol wash is a non-proprietary process that removes
chlorinated trace constituents, carbon dioxide, and moisture in
a single process.  It is based on the process of using methanol
for removal of trace constituents and carbon dioxide from coal
gas and natural gas.  Several variations on the methanol
wash process have been demonstrated at the pilot scale.
This process offers the promise of being an economical way
to remove trace constituents, carbon dioxide, and moisture.
                              10-15

-------
REFERENCES
    Johns Hopkins University Applied Physics Laboratory.   Landfill
        Methane Utilization Technology Workbook.   Prepared for  U.S.
        Department of Energy, Division of Building and Community
        Systems.

    Gas Recovery Systems.   The Economics of Landfill Gas  Projects.
       GRCDA 9th International Landfill Gas Symposium,  May 1986.

    SCS Engineers.  Toyon Canyon Landfill Gas Utilization Study.
        Prepared for Bureau of Sanitation, Department of  Public
        Works/  City of Los Angeles,  California.   December 1982.

    Bogardus,  Ellen R.  Landfill Gas Recovery Comes of Age.   14th
        Composting and Waste Recycling Conference,  Washington,  D.C.
        May 8,  1984.

    Personal Communication with Lewis Audette, President, New England
        Alternate Fuels, June 2, 1986.

    EMCON Associates.  Methane Generation and Recovery From Landfills.
        Ann Arbor Science.  Ann Arbor, Michigan.   1982.

    Ugly Dump Site Transformed Into Recreation Mega-Facility.  Civil
        Engineering, American Society of Civil Engineers.  Vol. 51,
        No. 6.   June 1981.
                              10-16

-------
                             SECTION 11



          SAFETY CONSIDERATIONS AND POTENTIAL CONSEQUENCES


           OF NOT RECOVERING OR CONTROLLING LANDFILL GAS



SAFETY

     Safety is a primary concern in dealing with any combustible

gas.  Landfill gas is combustible and can cause explosions and

fires if allowed to accumulate in confined areas.  Subsurface

features such as underground trenches, vaults, utility conduits,

and other structures may allow gas to accumulate.  LFG can also

be an asphyxiant displacing oxygen in enclosed areas.

     Structures on closed landfills should be monitored and

protected from LFG.  Closed landfills operated as recreation


areas or other public uses should include LFG protection for

restrooms, pavilions, equipment and administrative buildings,

and other enclosed structures.  The dangers of LFG may mandate
                                                /

strict safety precautions at closed landfills, particularly

during construction.  Testing of the subsurface and the near-

surface atmosphere at construction sites may dictate appropriate

safety measures, including forced ventilation, specialized

breathing apparatus, or non-sparking tools and equipment.

     Closed landfills present potential LFG problems for

buildings both on and near the site.  Closure of landfills


includes installation of an impermeable cap to prevent

moisture movement through the solid waste and subsequent

production of leachate.  The cap also retards emission of gas

through the landfill surface.  The subsequent LFG production
                              11-1

-------
creates pressure in the landfill, forcing the gas to migrate



laterally through the most permeable soil lenses.  Gas has been



documented to travel up to several thousand feet laterally from



a site  (see Exhibit 8-4).  Whenever structures are located near



landfill areas, monitoring should be performed to determine if



gas is  migrating toward the structure.  Site conditions may



preclude migration? however, landfills can be expected to generate



LFG, and should be assessed by specialists familiar with gas



migration and control.  In questionable situations, subsurface



gas monitoring may be appropriate.  If gas is found in the soil



at the property boundary at or above the LEL, an engineered



control system is needed.





POTENTIAL CONSEQUENCES OF NOT RECOVERING OR CONTROLLING LFG



     The consequences of not recovering or controlling LFG from



a landfill will vary according to the site conditions and the



quantity of gas generated.  The potential consequences, both



environmental and economic, however/ can be quite significant.



Foremost, is the danger of LFG migration that is likely to occur



without recovery or migration controls.  LFG migration presents



serious risks/ including fire, explosion, and asphyxiation, to



residents and workers on and near a landfill.  LFG can also be



harmful to vegetation.  It is an asphyxiant to many plants,



trees/ and shrubs, causing vegetative kills by precluding the



presence of air at normal levels.



     Without recovery or migration control, the primary mechanism



preventing migration is the natural venting of LFG into the
                              11-2

-------
atmosphere.  However, this may cause environmental problems



in the form of odors.  Although methane is odorless, other


constituents of LFG, such as hydrogen sulfide, are odorous even



in trace quantities.  Some LFG control systems incinerate the



gas to control odors; others merely vent to the atmosphere with


no odor treatment.



     Although they are effective in controlling LFG hazards,



control systems without recovery do not take advantage of the


potential economic benefits.  LFG recovery systems .can provide



revenue through the sale of generated electricity or gas.  In



addition, the use of LFG reduces the overall consumption of



non-renewable fuels.  Therefore, LFG recovery systems should be


considered over control-only systems at landfill sites where



recovery is economically feasible.  At sites where recovery is



unwarranted, LFG control measures may still be necessary to


protect the surrounding area and allow future use of the closed
                                               /
                                               /
landfill.  Where recovery is warranted, separate control



features may be required beyond that included in a recovery



system to ensure that complete control coverage is provided.
                              11-3

-------
                            SECTION 12

           FACTORS AFFECTING ECONOMICS OF GAS RECOVERY



LANDFILL CONSIDERATIONS

     In assessing the economic viability of landfill gas recovery,

the landfill characteristics are the first set of conditions

to be investigated.  These characteristics impact the quantity

of gas generated, the percentage that can be collected, the

quality of the gas, and the gas generating lifetime.  Generally,

three factors influence total gas generation: (1)


     1.  Waste Quantity.  All things being equal, landfills

         with more waste will generate more gas than smaller

         sites.  Thus, gas recovery and utilization is generally

         more profitable at sites with large quantities of

         refuse.  One million tons of refuse in place is a

         commonly-used minimum figure.  However,* smaller sites
                                               /
         may be economically viabjle.

     2.  Age of the Waste.  If the refuse was recently deposited,

         it is likely to be at its peak generation rate.  Refuse

         in-place for 10 to 20 years may have passed this peak,

         and recoverable quantities of gas will be less than at

         younger sites.


     3.  Other Considerations.  Factors relating to the type

         of waste and its current condition include moisture

         content, pH, organic content, etc.
                              12-1

-------
     The second set of considerations relating to landfill
gas recovery deals with collection capability.  The following
factors affect collection capability: (1)
     1.  Depth vs. Area.  Deep landfills are preferable to  those
         spread out over large areas and shallow depths.  Generally,
         landfills more than 40 feet deep allow collection  of a
         high percentage of the gas generated.  In addition,
         collection systems are less expensive when one deep well
         can collect gas from the same waste volume as multiple
         shallow wells.
     2.  Mounded vs. Subsurface Configuration.  The less surface
         area exposed to atmosphere, the less gas will dissipate
         into the air and escape the collection system.  When
         landfills are constructed below grade, a larger portion
         of gas generated can be recovered than from mounded
         fills.
                                                *
     3.  Cover Soil Permeability.  Generally, tne tighter the
         cover soils, the greater the gas retention and the
         greater volume of gas collected.   Permeable cover  soils
         allow gas to dissipate to the atmosphere and escape the
         collection system.
     4.  Water Content.  High moisture content at the site
         generally increases the rate of waste decomposition
         and gas generation compared to dry sites.  Higher
         gas generation rates normally improve the viability
         of a gas recovery project.  Excessive moisture in
                              12-2

-------
         the fill, however, can be a problem because if wells


         flood with water, the ability to collect the gas is


         reduced.




MARKET CONSIDERATIONS


     All existing landfill gas recovery and utilization projects


can be classified into three general types:  (1) medium-Btu


applications, (2) electric generating applications, and (3)


high-Btu applications.  Market considerations that impact gas


recovery viability differ according to those types of end uses.


Medium-Btu Uses


     Typical medium-Btu gas uses include boiler fuel, space


heating, water heating, steam generation, or industry-specific


process applications.  In these cases, only nominal removal of


particulates and moisture is performed before the gas is used.


Typically,  medium-Btu gas applications entail transmission of


the gas to users near the landfill site.  Factors impacting

                                              f
the viability of medium-Btu applications include:


     1.  Proximity of User.  This is a critical consideration


         in the viability of a medium-Btu project.  A market


         should exist near the landfill gas site (e.g., within


         5 miles) in order for the gas to be transmitted at


         reasonable cost.


     2.  Transmission Distance and Access.  As the transmission


         distance increases, the cost of installing and main-


         taining transmission lines increases proportionately.


         Consideration must be given to the distance, securing
                              12-3

-------
    right-of-way, terrain, obstacles such as rivers,  and

    transmission line maintenance over such distances.

3.  Quantity of Gas Used.  Ideally, most or all of the

    landfill gas that can be collected should be used.

4.  Variability of Gas Use.  Natural gas use (and potential

    landfill gas use) for space and water heating, may  be

    highly seasonal.  Under these circumstances, gas demands

    may be quite high during the winter months, but demand

    could be low or non-existent during warm summer months.

    During these times, the landfill gas cannot be stored,

    but rather is vented to the atmosphere or flared without

    economic return.  Intermittent operations are also

    undesirable.  The ideal medium-Btu user is one that

    consumes the landfill gas for process uses at uniform

    rates throughout the year with operations 24 hours  per

    day, 7 days per week, and 52 weeks per year.
                                           *
                                           7
5.  Quality  Requirements.  The quality ne^ds of the

    medium-Btu user are highly variable.  The first quality

    requirement relates to moisture content.  Landfill  gas

    is wet compared to natural gas, and some users may  be

    able to tolerate a relatively wet gas, but others may

    not.  If the gas must be as dry as natural gas,

    considerable capital expense may be required to remove

    the moisture.

6.  Trace Constituents.  Aside from removing moisture from

    the gas stream, other trace constituents are present


    that may have a deleterious impact on equipment.  Many


                         12-4

-------
    of the hundreds of trace compounds in landfill gas

    are corrosive.  Considerable capital cost may be

    required to treat landfill gas to reduce trace

    constituent levels to those usually found in natural

    gas.


7.  Pressure Requirements.  Ideally,  the landfill gas


    developer can deliver gas to the  medium-Btu user at

    the minimum pressure necessary for transmission.


    In some cases, however, high pressure requirements

    at the point of use may exist, thus necessitating

    additional compression of the landfill gas to


    pressures as high as in large natural gas pipelines.


8.  Price Paid.  The largest determinant of medium-Btu


    landfill gas use viability is the price paid by the

    user.  Typically this price is a  function of the


    current natural gas cost.  Some discounts will have
                                           /
    to be offered compared to natural gas iprices in order

    to encourage the user to convert  to LFG.  These

    discounts have ranged between 10  and 40 percent, and

    can be more depending upon the bur-den of retrofit


    placed on the user.



    Natural gas prices were quite high several years ago,

    thus creating additional impetus  for development of


    medium-Btu landfill gas projects.  In 1985 and 1986,


    natural gas prices have decreased to record low levels,


    resulting in a decreased economic viability for

    medium-Btu uses.
                         12-5

-------
Electrical Generation


     A second use for landfill gas is electrical generation.


In this case, nominal removal of participates and moisture may

be performed.  The gas is used as the fuel for internal combus-


tion engines connected to a generator to produce electricity.


Gas turbines have been used for several electrical generation


projects at exceptionally large landfills.  The electricity is


usually sold to the local electric utility.  Under the Public


Utilities Regulatory Policy Act (PURPA), electric utilities


are required to buy electricity from small generators such as

those found at landfill gas sites, and pay the "avoided cost,"


which is essentially the utility's cost of generating the next

increment of electricity.  A separate set of criteria impacts


the economic viability of electric generating projects.  These


may include:

     1.  Proximity to Connection Points.  This is usually
                                                t
                                                f
         not a significant problem, as electric/lines are

         often close to the landfill.  The only question

         then is whether they are of adequate capacity.


     2.  Access to Connection Point.  In certain cases,


         transmission for long distances may be necessary.


         Access across adjoining properties and acquisition

         of appropriate right-of-way may then be required.


     3.  Switching Requirements.  A large cost associated

         with electric generating facilities is the special-

         ized switchgear needed to connect to the local


         utility.  These are highly variable and generally



                              12-6

-------
         depend upon the requirements of the specific utility


         and the conditions at the point of connection.


     4.  Utility Cooperation.  Although PURPA requires utilities


         to purchase electricity from small generators, some


         electric utilities are more cooperative than others.


         Obviously, good cooperation can speed up the contract


         execution process, and allow for prompt project start-up.


     5.  Avoided Cost Paid.  Utilities usually publish


         schedules of current avoided cost and estimated


         future escalations, which are highly variable.


         Avoided costs are quite high in New York, the


         New England States, and throughout California,


         but are much lower in the Midwest and South since


         the majority of electric power is derived from


         burning coal.  Thus, more electric generation


         projects have been initiated in New York City and
                                                /

         California than elsewhere.            /
                                 »

High-Btu Uses


     High-Btu gas is the third application for landfill gas use


to be discussed.  For these uses, LFG is processed to remove


the carbon dioxide.  The resultant gas is similar to natural


gas in terms of energy content.  Considerations impacting the


economic viability of these projects are:


     1.  Available Pipeline of Adequate Capacity.  Unlike


         electric lines that are usually convenient and


         accessible, large natural gas pipelines of sufficient


         capacity near to a landfill site are not commonplace.
                              12-7

-------
2.  Utility Cooperation.  Sale of an upgraded high-Btu


    gas may be made either to the local natural gas


    utility, or perhaps to a major pipeline company.


    Unlike electric generation where utility companies


    are required by law to purchase the electricity,


    there is no requirement in most jurisdictions for


    gas utilities or pipeline companies to purchase


    high-Btu gas.


3.  Ease of Transmission.  Transmission to the point


    of pipeline injection can be costly and acquisition


    of right-of-way may be both expensive and time


    consuming.  The same transmission considerations


    applicable to medium-Btu use apply to high-Btu use.


4.  Pressurization Requirements.  Large natural gas


    pipelines typically operate at high pressures, but


    natural gas lines operated by small utilities usually
                                           T

    are not operated at such high pressure's.  In either
                                          /
    instance/ however, some pressurization of the gas


    will be required, possibly adding considerable cost.


5.  Quality Requirements.  Different gas utility and


    pipeline companies have varying criteria for


    acceptance of gas, which usually relate to moisture


    content, energy (Btu) content, oxygen content, and


    trace constituent levels.


6.  Price Paid.  In order to secure the cooperation of


    the gas utility, a discount on the current price


    paid by the utility for natural gas will likely be



                         12-8

-------
necessary.  Since natural gas costs are currently



quite low, contracts negotiated during 1985 and 1986



are generally not favorable for the gas developer.
                      12-9

-------
REFERENCES

1.  SCS Engineers.  Landfill Gas Resource,  Evaluation,  and
        Development Guidebook.  Gas Research Institute.   Report
        No. 85/0250.  November 1985.
                              12-10

-------
                            SECTION 13


                      DECISION-MAKERS' GUIDE




     When a landfill is considered for gas recovery, a three-


step process is appropriate.  The first step involves comparing


landfill site characteristics against various minimum acceptable


criteria.  If the characteristics exceed these minimum values,


a more detailed feasibility study can then be performed using


more site specifics and formulas for gas recovery quantities,


revenues, and costs.  Finally, a field testing program should


be performed.  A testing program will confirm the rules-of-thuir.b


utilized in the first two steps and provide data that can be


used to design and construct the well field.




MINIMUM CRITERIA


     The first assessment consists of comparing basic landfill


characteristics against selected minimum acceptable criteria.
                                               i
                                               r

These include:                                /

                                              /
     1.  In-Place Waste Quantity.  A value generally accepted


         in the industry is that a landfill must have in excess


         of 1 million tons of refuse in place.(1)  Where condi-


         tions for gas utilization are ideal, exceptions to


         this minimum value may exist.  However, in many cases,


         landfills smaller than 1 million tons have proven to


         be uneconomical.


     2.  Operational Status.  Organic material has a limited


         gas production lifetime.  The volume of gas generation


         initially will increase, and then start to decrease.



                              13-1

-------
         Within a period of time (10 to 30 years),  the rate of



         gas generation will decrease to a point where the cost



         of operating the recovery system exceeds revenues.  It



         is best that the site being considered either be



         operational or have been recently closed.



     3.  Depth.  For gas recovery to be economically viable,



         the minimum landfill depth should be about 40 ft.(l)



         Recovery from a landfill shallower than this is margi-



         nal even when the total waste quantity is  in excess



         of 1 million tons.



     4.  Area.  The landfill should have at least 40 acres of



         fill area.(l)  Most landfills with more than 1 million



         tons meet this criterion.



     If a site passes all of the above criteria, a  more detailed



feasibility investigation should be performed.  If  the site fails



only one of the criteria and there are other strpng indications
                                                /
                                               /
of viable recovery, an expert in LFG recovery should be consulted



to assess recovery feasibility.  An estimated 10 to 25 percent



of currently active landfills should pass the test  for minimum



criteria.  For those sites, the more detailed analysis below is



appropriate.





REVENUE VS. COST COMPARISON



     The second more detailed assessment of LFG recovery viabil-



ity consists of estimating gas quantities and potential revenues,



estimating capital and operation and maintenance (O&M) costs



for collection and utilization, and comparing revenues against



costs to determine profitability.





                              13-2

-------
 In t	,,  yua «-juaui.icies, these values can be used:

 1.   Generation Rate.  Gas generation rates can vary from

     0.08 to 0.28 cu.  ft. per. Ib. of refuse per yr.(2)  A

     typical value is  0.15 cu. ft. per. Ib. per year.(3)  Note

     that this  figure  is for  total generation, and that

     collection will be a percentage of this value.  In

     determining the total number of pounds of waste at a

     landfill,  some assumption about landfill density must

     be used; densities may range from 600 to 1,500 Ib. per

     cu. yd.(4)  If site densities are not known, a figure

     of 1,000 Ib. per  cu. yd. is a commonly used assumption.

 2.   Collection Rate.  Not all landfill gas generated can

     be collected.  Collection efficiency is a function of

     the landfill geometry, the layout, and design of the

     collection system.  Typical collection efficiencies

     range from 25 to  75 percent of the gas generated.(3)
                                          *
    An average  of 50  percent is reasonably/for estimating
                           »
     purposes.(4)                         /

 3.   Energy Content.   Methane concentrations in LFG average

     about 50 percent; under  conditions of collection, this

     value may  change.(4)  Typical methane content of LFG
     V
     ranges from 40 to 60 percent, with equivalent energy

     values of  400 to  600 Btu per cu. ft.(l)  In the absence

     of other information, 500 Btu per cu. ft. is a reasonable

    assumption.

4.  Operational Downtime.  Further reductions to derive

    ultimate gas collection volumes should be applied to


                         13-3

-------
    account for downtime of the collection and recovery
    system.  Values typically range from 5 to 15 percent,
    depending upon the quality of the collection system,
    the degree of sophistication and the level of main-
    tenance.  For estimating purposes, the landfill gas
    recovery industry uses values of 5 percent for medium-
    Btu systems,  10 percent for electric generating plants,
    and 15 percent for high-Btu processing plants.(2)
5.  Gas Revenue Rates.  Sale prices for medium- and
    high-Btu gas vary as a function of prevailing local
    prices for natural gas.  Over the past several years,
    these rates have ranged from a low of about $2 per
    million Btu,  to a high of $6 per million Btu.  In
    order to compete with natural gas, a landfill gas
    developer must offer a discount on natural gas prices
    to the potential user.  These discounts are typically
                                           *
                                           /
    from 10 and 40 percent.  Local gas utilities can
    provide data on their rates and a discount factor
    applied.  The discount should be directly proportional
    to the degree of retrofitting required by the gas user.
6.  Electricity Revenue Rates.  Under PURPA, electric
    utilities are required to buy electricity from small
    generators, such as landfill gas recovery facilities.
    The value paid is the avoided cost, and may range from
    $0.01 to $0.10 per kwh.  The local electric utility's
    avoided cost must be obtained and converted to a
    price per Btu.  A typical conversion factor used is
    17,500 Btu per kwh.(2)
                         13-4

-------
     7.  Energy Escalators.  An escalator from current rates to


         rates in the initial year of operation should be used


         in the feasibility analysis.  The cost for electricity


         can be expected to escalate in the future.  In certain


         cases, electric utilities may be able to provide pro-


         jections of future avoided costs.  In other instances,


         escalations have to be assumed.  Values between 5 and


         10 percent per year are often used. (2)




         Similarly, escalation rates of 5 to 10 percent for


         natural gas prices have been used.  With the reduction


         in natural gas prices over the past two years, cost


         escalation predictions may not be reliable.




     Costs for gas recovery and utilization systems are highly


variable depending upon site location, degree of sophistication,


useful life of equipment, site conditions, and other factors.
                                                *
                                                /
Despite such variability, there has been some agreement within
                                 t

the industry on general rules-of-thumb for calculating capital


and O&M costs for gas recovery facilities.  These formulas have


been presented in a document prepared for the U.S. Department


of Energy.(2)  In this document, capital costs in 1982 for


various systems were described as follows:


     1.  Medium-Btu Facilities.  Capital cost = $(0.2)(cu.


         ft. per day) + $1,000,000.  This formula is valid for


         an operating range of 2 to 20 million cu. ft. per day


        ,of input gas.
                              13-5

-------
     2.  High-Btu Facilities.  Capital cost = $(0.7)(cu.  ft.


         per day) + $1,000,000.  This formula is valid for an


         operating range of 2 to 10 million cu. ft. per day of


         input gas.


     3.  Electrical Generating Facilities.  Capital cost =


         $(1.0)(cu. ft. per day) + $1,000,000.  This formula


         is valid for an operating range of 2 to 10 million cu.


         ft. per day of input gas.


     O&M costs are also quite variable, depending on plant


technology, labor requirements, and site factors.  For example,


excessive landfill settlement may damage the collection system,


and necessitate frequent repairs or replacement.  First year


O&M costs are estimated to be about 10 percent of capital cost.(2)


Some escalation in the O&M dollar amount thereafter to allow


for general inflation is appropriate.  In addition, some non-


routine O&M expenditures at 5 or 10 year intervals may be
                                                *
                                                7

necessary for repair or replacement of process /and blower

                                               /
facilities.  A summary of expected capital and O&M costs for


facilities of various sizes based on these formulas has been


included as Exhibit 13-1.


     Taxes can have a significant impact on the economic via-


bility of a gas recovery and utilization project when private


parties are the developers.  Historically, investment tax credit


and energy tax credits have been advantageous to the development


of many projects,  turning otherwise non-profitable or marginal


facilities into economically viable programs.  However, tax


benefits vary widely depending on the nature of the individual




                              13-6

-------
project, and the tax status of the developing organization.


     For 1987 only, qualifying LFG recovery projects can claim


a 10% tax credit.  This credit is referred to as an Energy Tax


Credit or Business Energy Credit and is described in Internal


Revenue Code (IRC) Section 46(b)(2)(A).  This credit is eliminated


after 1987.(5)


    An Alternate Energy Production Credit is also available to


LFG recovery projects and is described in IRC Section 29(a).


It provides for a tax credit worth (in 1986 dollars) approximately


§4.50 per barrel of oil equivalent that an LFG recovery project


displaces.  This credit applies to LFG facilities that were in


service after 1979 and will include facilities in service before


January 1, 1990.  Credits are available through the year 2000,


and are variable as are described in the IRS Code.(5)


     The estimated revenues and costs should be calculated on


an annual basis and compared.  Capital costs should be annual-
                                               *
                                               /

ized and include debt service using interest ra&es and other
                                 >

costs appropriate to the situation.  If the cost analysis does


not show a break-even or profitable outlook, the concept of a


gas recovery and utilization facility should be abandoned


unless there are extenuating circumstances; e.g., a requirement


to provide odor or migration control.




FIELD TEST


     If the cost analysis is favorable, a field test should


be conducted to confirm the estimates related to gas recovery.


Specialized equipment and experienced LFG engineers are required
                              13-7

-------
                                      EXHIBIT  13-1

                               TYPICAL CAPITAL AMD O&N COSTS

Plant
Capacity
Mediu«-Btu
End Use

Electric Generation
End Use

High-Btu
End Use

                X
(LFG Inflow  Capital      First  Year    Capital    First Year      Capital   First Year

In m cfd)     Cost       O&N Cost       Cost     0AM Cost         Cost    O&M Cost
    2.5     $1,500,000     $150,000  *$ 3,500,000   $  350,000  $2,750,000   $275,000




    5.0      2,000,000      200,000    6,000,000      600,000   4,500,000    450,000


                                                                          14

    7.5      2,500,000      250,000    8,500,000      850,000   6,250,000    625,000




   10.0      3,000,000      300,000   11,000,000    1,200,000   8,000,000    800,000
 Jpour-foot earthen liner, leachate collection system,  40-acre site,  1,000,000 tons/
  2,000,000 cubic yards, 15-year  site life.
 2Five-foot clay  liner (on-site clays), leachate  collection system,  40-acre site,
  1,000,000 tons/2,000,000 cubic  yards, 15-year site life, 30-year  long-term care  period.
 3Coats are in  1985 dollars.
 *Source:  Gleb,  R., and E. Scaro.   1985.  Cost Accounting for Landfill Design and
  Construction  Past and Present.  Waste Tech 1985 Proceedings, National Solid Waste
  Management Association, Washington, D.C.

-------
REFERENCES

1.  Johns Hopkins University Applied Physics Laboratory.   Landfill
        Methane Utilization Technology Workbook.   Prepared for U.S.
        Department of Energy, Division of Buildings and Community
        Systems.  Report No. CPE-8101.  February 1981.

2.  Argonne National Laboratory.  Methane from Landfills:   Pre-
        liminary Assessment Workbook.  Prepared for U.S.  Department
        of Energy, Office of Renewable Technology.  Report No.
        ANL/CNSV-31.  1982.

3.  Walsh, J.J., and R.E. Zimmerman.  Elements of a Landfill Gas
        Utilization Feasibility Study.  Report of the Landfill Gas
        Feasibility Study Subcommittee of the Landfill Gas Committee,
        Governmental Refuse Collection and Disposal Association.
        Silver Spring, Maryland.  April 1984.

4.  Lockman and Associates, Inc.  Recovery, Processing, and
        Utilization of Gas from Sanitary Landfills.  Prepared for
        U.S. Environmental Protection Agency.  No. EPA-600/2-79-001.
        February 1979.

5.  Internal Revenue Code.  Washington, D.C.  1986.
                              13-9

-------
                          SECTION 14


                   SUlWiARY AND CONCLUSIONS



     Landfill gas can be either a hazard or a benefit at closed


and operating landfills.  Hazards are associated with the explosive


potential of the methane content of LFG.  Additionally, concerns


have been raised (at least in California) about surface emissions


of LFG from landfills and their contribution to air pollution.


The gas is being recovered as an alternative fuel at several


sites where the economics are favorable.


     When organic matter decomposes in a sanitary landfill, it


is transformed into a variety of simpler organic materials by the


action of microorganisms abundant in solid waste.  These processes


produce principally methane and carbon dioxide.  The rate of the


LFG production is dependent on a number of site-specific factors,


including the age of the landfill, moisture content and distri-


bution, and solid waste composition and quantity.

                                                 t
     LFG generation begins almost immediately upon burial and


increases rapidly with steady generation beginning within several


months to a year.  Relatively steady generation may continue for


10 years or longer.  Thereafter the generation rate decreases,


but gas generation continues for many years.


     Recovery of LFG for beneficial use is currently practiced at


more than 50 locations nationwide with more than 40 other systems


in the planning stages.  The quantity, quality, and collectability


of LFG, and the availability of markets are factors critical to


the success of a LFG recovery project.  Assuming that LFG markets
                             14-1

-------
are present, potential recovery sites are generally evaluated

based on the following criteria:

     0 Amount of refuse — The quantity of LFG produced
       depends first on the amount of refuse available
       for decomposition.  For commercial applications,
       an LFG recovery site should have a minimum of
       roughly one million tons of refuse in place and
       an average depth of 40 feet.

       Refuse composition and moisture content —
       Waste composition can limit both the total
       yield and rate of LFG production.  In
       general, LFG production is stimulated by a
       waste having high percentage or readily
       decomposable organic materials (e.g., food
       and garden wastes).

     0 Age of the landfill — As biodegradation of
       organic materials is completed, less LFG is
       produced (and eventually none is produced at
       all).  Therefore, older disposal sites will
       produce less LFG because the rate of decom-
       position has decreased.  Recovery sites
       should be recently closed, or preferably,
       have active fill life remaining.

     Capital and O&M costs for LFG recovery systems can be quite

high.  Thus the right combination of site condition, gas volumes

and market conditions must be present to make recovery attractive

for financial reasons only.  Capital costs will always be well
                                            /
over $1 million with O&M costsrof more than ^.0 percent of capital

costs occurring every year.

     The recovery of gas via collection systems can help achieve

the positive aspects of migration control, control of surface

emissions, and recovery of an alternative fuel.  Recovery systems

withdrawing LFG can control migration and thus reduce the poten-

tial for explosions.  Other types of control systems including

pressure curtains and vent trenches do not reduce surface emissions
                           14-2

-------
and actually encourage them.  Systems recovering LFG for energy also


help control horizontal migration and surface emissions.  However,


no one system will optimally meet all three goals, as mentioned


above.


     State regulations exist and primarily focus on the control


of LFG* migration.  However, both California and Washington have


regulations that encourage or require the collection, rather then


venting, of LFG.  Thus in most parts of the country the recovery


of LFG is based almost exclusively on the value of the gas as a


fuel.  Where it is profitable to recover LFG, it will be recovered.


The control of gas migration is related to site-specific situations


and is driven by safety considerations.  This is true for both


closed and operating landfills.


     The recovery of LFG as fuel currently rests on economics.


As more States, and possibly even the Federal government, move


toward LFG regulation, recovery will become increasily attractive.


As these regulations become more common, installation of recovery


systems will become more popular for both eloped and operating
                                             /

sites.  In addition to the economic benefits. LFG recovery will


aid in meeting landfill surface emission criteria and/or help


control horizontal migration.  The combination of positive and


negative motivators (the value of the gas as a fuel and the


regulations) may result in more sites with control systems.
                             14-3

-------