FLUE GAS DESULFURIZATION




 PROCESS COST ASSESSMENT
        PEDCo ENVIRONMENTAL

-------
                  PEDCo-ENVIRONMENTAL
                       SUITE 13  •  ATKINSON SQUARE
                            CINCINNATI. OHIO 45246
                                      513 /771-4330
      FLUE GAS DESULFURIZATION

       PROCESS COST ASSESSMENT
             Prepared by

PEDCo-Environmental Specialists, Inc.
      Suite 13, Atkinson Square
       Cincinnati, Ohio  45246
       Contract No. 68-01-3150
       Technical Series Area 4
             Task No. 2
 EPA Project Officer:  James Speyer
            Prepared for

  Office of Planning and Evaluation
U.S. ENVIRONMENTAL PROTECTION AGENCY
          Washington, D.C.
             May 6, 1975

-------
This report was furnished to the Environmental Protection
Agency by PEDCo-Environmental Specialists, Inc., Cincinnati,
Ohio, in fulfillment of Contract No. 68-01-3150, Technical
Series Area 4, Task No. 2.  The contents of this report are
reproduced herein as received from the contractor.  The
opinions, findings, and conclusions expressed are those of
the author and not necessarily those of the Environmental
Protection Agency.
                              11

-------
                       ACKNOWLEDGMENT






     This report was prepared for the Office of Planning and



Evaluation of the U.S. Environmental Protection Agency.  The



EPA Project Officer was Mr. James Speyer.  PEDCo appreciates



the direction provided by both Mr. Speyer and Mr. James



Ferry, also of the Office of Planning and Evaluation.



     PEDCo also appreciates the assistance provided by the



Edison Electric Institute's Clean Air Coordinating Com-



mittee, its consultant, the National Economic Research



Associates, and several utility representatives, partic-



ularly Mr. Edward E. Galloway of the Cincinnati Gas and



Electric Company, who reviewed early drafts of the report.



     The PEDCo Project Director was Timothy W. Devitt.  Mr.



Robert S. Amick was Project Manager.  Technical support and



analysis were provided by Messrs. Atul Kothari, David Noe,



Thomas C. Ponder, Yatendra Shah, and Lario V. Yerino.  Mr.



Chuck'Fleming was responsible for final report preparation



and assembly.
                              111

-------
                      TABLE OF CONTENTS
ACKNOWLEDGMENT                                         iii

LIST OF FIGURES                                        vii

LIST OF TABLES                                          ix

SUMMARY                                                 xi

1.0  INTRODUCTION                                      1-1

2.0  COST COMPONENTS FOR FLUE GAS DESULFURIZATION      2-1
     SYSTEMS

     2.1  Capital Cost Components                      2-2

          2.1.1  Plant Equipment and Installation      2-2
                 for S02 Control
          2.1.2  Indirect Costs                        2-4

     2.2  Annual Operating Costs                       2-5

     2.3  Replacement Capacity and Energy Penalties    2-6

3.0  COST ESTIMATES FOR FLUE GAS DESULFURIZATION       3-1
     SYSTEMS

     3.1  Capital Costs                                3-6

          3.1.1  Model Plants                          3-6
          3.1.2  Factors Affecting Capital Costs       3-6

     3.2  Annualized Costs                             3-19

          3.2.1  Model Plants                          3-19

4.0  NATIONWIDE FLUE GAS DESULFURIZATION COST ASSESS-  4-1
     MENT

5.0  MANUFACTURER ESTIMATES OF FGD SYSTEM COSTS        5-1

6.0  UTILITY INDUSTRY SURVEY                           6-1

-------
                 TABLE OF CONTENTS  (continued)
                                                       Paqe
APPENDIX A  SLUDGE FROM FLUE GAS DESULFURIZATION       A-l
            SYSTEMS - AN OVERVIEW

APPENDIX B  PROCEDURE FOR CONVERTING UTILITY INVEST-   B-l
            MENT AND EXPENSE INTO ANNUAL REVENUE
            REQUIREMENTS

APPENDIX C  SAMPLE COMPUTER PRINTOUTS OF FGD COSTS     C-l

APPENDIX D  BASIS OF LIME - LIMESTONE PROCESS DESIGN   D-l

APPENDIX E  BASIS OF WELLMAN-LORD PROCESS DESIGN       E-l

APPENDIX F  FLUE GAS DESULFURIZATION COST ESTIMATING   F-l
            METHODOLOGY COST SUMMARY FOR SELECTED
            U.S. POWER PLANTS

APPENDIX G  DETAILS OF UTILITY INDUSTRY SURVEY COST    G-l
            ADJUSTMENTS
                              VI

-------
                        LIST OF FIGURES


Figure                                                  Page

3.1    Incremental Effect of Sulfur Content of Coal on  3-9
       Model Plant Capital Cost

3.2    Incremental Effect of Flue Gas Volumetric Flow   3-11
       Rate on Model Plant Capital Cost

3.3    Effect of Redundancy  (Spare Scrubbing Train) in  3-15
       FGD Systems on Capital Cost

3.4    Impact of Cost Escalation                        3-20

3.5    Effect of Boiler Remaining Life and Correspond-  3-23
       ing Capacity Factor on Model Plant Annual Cost

3.6    Effect of Sulfur Content of Coal on Model Plant  3-25
       Annual Cost

3.7    Incremental Effect of Flue Gas Volumetric Flow   3-26
       Rate on Model Plant Operating Cost

4.1    National Coal Association Regions                4-5

D.I    Typical Process Flow Sheet of Wet Limestone -    D-3
       S03 Scrubbing System

E.I    Typical Process Flow Sheet of Wellman-Lord SO,,   E-3
       Scrubbing System
                              VI1

-------
                       LIST OF TABLES


Table                                                   Page
 1     Summary of Model Plant FGD System Costs

 2     Typical Capital Cost Variations for Site        xiii

 3     Range of Costs Reported for Flue Gas Desul-      xvi
       furization Systems

2.1    Major FGD System Equipment Summary               2-3

2.2    Comparison of Replacement Power Costs            2-10

3.1    Summary of Model Plant FGD Costs                 3-2

3.2    Summary of Characteristics and Assumptions for   3-4
       Model Plants

3.3    Model Plants Capital Costs                       3-7

3.4    Typical Capital Cost Variations for Site         3-8
       Specific Conditions

3.5    Typical Capital Cost Variation with Various      3-13
       Retrofit Requirements

3.6    Costs of Typical Sludge Disposal Options         3-17

3.7    Typical Relationship Between Boiler Capacity     3-18
       Factor and Remaining Life

3.8    Model Plants Annualized Costs                    3-21

4.1    Regional and National FGD Cost Summary           4-3

4.2    Regional and National FGD Cost Summary of Plants 4-4
       Requiring Greater Than 25% S02 Control

4.3    Regional Composition by State                    4-6

5.1    Summary of Manufacturer Estimates of FGD         5-1
       System Costs
                              IX

-------
                  LIST OF TABLES (continued)

Table                                                   Page

5.2    Manufacturer's Capital Costs Summary for Lime-   5-3
       stone System

5.3    Manufacturer's Annualized Cost Summary for       5-4
       Limestone System

6.1    Utility Industry Results                         6-5

A.I    Comparative Annual Land and Solid Waste Impact   A-4
       of 1,000 MW Electric Energy System

A.2    Sludge Production at Current FGD Installations   A-6

A.3    Sludge Generation - 1,000 MW Plant               A-7

A.4    Comparison of Trace Elements Analyses Between    A-12
       Raw Sludge and Leachate from that Sludge
       After Chemical Conditioning by Fixation

A.6    Impact of Various Subset Sludge Disposal Options A-14
       on the Annualized Cost of Sludge Disposal

A.5    Sludge Disposal Costs for the Model Plants       A-15

F.I    Assumed Values for Regional Variables that       F-3
       Affect FGD System Cost

F.2    Flue Gas Desulfurization Summary for Selected    F-5
       U.S. Power Plants
                              x

-------
                           SUMMARY






     This study was sponsored by the U.S. Environmental



Protection Agency in preparation for Congressional hearings



on possible revisions to the Clean Air Act.  The study



represents part of a joint effort being conducted by EPA and



the Edison Electric Institute's Clean Air Coordinating



Committee (EEI/CACC) to determine the cost of flue gas



desulfurization (FGD) systems.



     The capital investment and annualized costs of FGD



systems were estimated using a model plant approach.  The



costs associated with particulate emission control were



deliberately excluded to determine the incremental costs of



SO9 emission control only.  The results of the model plant



analysis are presented in Table 1.  These costs include the



cost of the FGD system and its ancillaries, and sludge



disposal, but do not include replacement power costs (ca-



pacity penalty) or cost escalation through project com-



pletion.



     Site-specific factors which can influence the cost of



FGD systems include the amount of S02 to be removed, flue



gas volume treated, type of application  (new vs retrofit),



degree of system redundancy, particulate emission control
                              XI

-------
                               Table 1.   SUMMARY OF MODEL PLANT PGD  SYSTEM COSTS
Model plant
characteristics
250 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
500 Megawatt Capacity
Retrofit, 3.5% S
New , ^ .','*.. S
Retrofit, 0.6% S
New, 0,6% S
1000 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
Capital costs
Limestone
$ MM
20.2
16.5
18.6
14.7
35.1
29.2
32.3
26.4
69.5
56.8
64.4
52.0
?/KW
81
66
74
59
70
58
65
53
69
57
64
52
Wcllman-Lord
$ MM
30.5
23.8
23.5
17.5
56.9
45.0
44.0
33.4
104.2
85.7
79.9
64.3
$/KW
122
95
94
70
114
90
88
67
104
86
80
64
Annualized costs
Limestone
$ MM/yr
6.8
5.5
5.9
4.6
11.2
9.7
9.6
8.0
22.0
18.6
18.9
15.7
mills/KWH
5.18
4.17
4.47
3.46
4.27
3.68
3.63
3.05
4.18
3.54
3.59
2.97
Wellir.an-Lord
$ MM/yr
8.9
6.7
7.0
5.1
15.3
12.3
12.1
9.4
28.1
23.3
22.0
18.0
mills/KWH
6.76
5.06
5.33
3.86
5.83
4.66
4.59
3.56
5.34
4.44
4.18
3.41
X

-------
requirements and sludge disposal method.  The impact on

total system capital costs due to each of these factors is

summarized in Table 2.


         Table  2.   TYPICAL  CAPITAL  COST  VARIATIONS

                FOR SITE SPECIFIC CONDITIONS
Factor
SO2 removal requirements
Flue gas flow rate
Installation status3 (new vs.
retrofit)
Conditions of terrain and sub-
surfacea
FGD system redundancy
Particulate control requirements
Sludge disposal requirements3
(nonregenerative processes)
Typical
cost
15
10
10
3
10
25
10
total capital
impact, %
- 20
- 30
- 40
- 15
- 40
- 35
- 30
  Variations  in capital cost are from a model plant
  500  MW/existing/3.5%  S boiler.

  Variations  in capital cost for 250 to 1000 MW model
  plants.
     As part of the EEI/CACC effort, a survey was conducted

of the cost of FGD systems currently installed, under con-

struction or planned.  As anticipated, a wide range of

costs, $33 to $197/KW, was obtained because of the varia-

bility in site and system design characteristics.  Lime and

limestone based system costs ranged from $34 to $116/KW.

These costs were adjusted to reflect the incremental cost
                               Xlll

-------
for S0~ control only (e.g. excluded the costs for particu-
late control, added indirect costs, expressed all costs in
January 1975 dollars etc.).  The adjusted costs ranged from
$50 to $87/KW and averaged $70/KW for lime and limestone
based systems and are essentially in agreement with the
costs computed via the model plant approach.
     The costs for FGD systems were also estimated by two
member companies of the Industrial Gas Cleaning Institute
(IGCI).  These cost estimates range from $37 to $74/KW for
new plants and $42 to $78/KW for retrofit applications.  The
IGCI costs for new plants are generally within 10 percent of
those computed using the model approach whereas IGCI's
estimate of retrofit plant cost are an average of 20 percent
below the model plant costs.
     Approximately 130 plants were identified by EPA's
Office of Planning and Evaluation on the basis that their
coal shipments in the first 6 months of 1974 had an average
sulfur content greater than that implied by the projected
S09 emission regulation.  The cost for FGD systems for each
  £
of these plants was roughly estimated based upon available
plant data for the sole purpose of computing regional and
national cost estimates for flue gas desulfurization systems.
It's emphasized that because of the multitude of site
specific factors which could not be incorporated in such a
time and budget limited evaluation, these costs can not be
considered accurate for any specific plant.  The FGD system
                             XIV

-------
costs for individual plants ranged from about $50/KW to over



$250/KW-  The average regional costs varied between $56 and



$68/KW treated, on a megawatt averaged basis.  The national



average was $64/KW.  These costs are somewhat lower than the



average model plant costs primarily because of the limited



amount of SO,, control required.



Conclusions



     There is considerable variation in the costs reported



for flue gas desulfurization systems.  This variation is due



primarily to the differing site conditions and design bases,



and the inclusion or exclusion of cost components, as



illustrated previously by Table 2.  Table 3 summarizes the



range of values presented in this report for the model



plants, and for the manufacturer and utility industry



surveys.  The model plant costs provide the most realistic



estimates of the incremental cost of S0_ control by flue gas



desulfurization for "typical" plants.  Costs for individual



FGD installations will vary above and below these norms.
                             xv

-------
H-
                     Table 3.  RANGE  OF COSTS REPORTED FOR FLUE GAS DESULFURIZATION  SYSTEMS




                                                       ($/KW)
FGD
Process
Regenerable
Nonregenerable
( 1 ime/1 imes tone )
Manufacturers
New

33-74
Retrofit

42-78
PEDCo
New
64-95
52-66
Retrofit
80-122
64-81
Utility industry
As reported
New
107a
33-129
Retrofit
33-197
40-115
Adjusted
New
95a
50-81
Retrofit
115-205
59-87
             Only one plant reported in this category.

-------
                      1.0  INTRODUCTION





     In preparing for Congressional hearings on possible



amendments to the Clean Air Act, the U.S. Environmental



Protection Agency (EPA) is preparing estimates of the total



costs of air pollution controls for the electric utility



industry.  One area of substantial controversy is the cost



of flue gas desulfurization (FGD) systems for sulfur dioxide



emission control.  To develop realistic estimates of the



capital and annualized costs of FGD systems, EPA initiated



two data gathering activities.  First, EPA asked the elec-



tric utility industry, through the Edison Electric Institute



Clean Air Coordinating Committee (EEI/CACC), to conduct a



survey to determine the costs incurred by those utilities



that are installing or planning to install FGD systems.



Second, EPA contracted with PEDCo-Environmental Specialists,



Inc. to prepare estimates of the costs of FGD systems for



representative or model power plants.



     Section 2 of this report presents a brief discussion of



capital and annualized cost components in flue gas desul-



furization systems.  Section 3 presents an analysis of FGD



system costs for typical boiler sizes and identifies varia-



tions in these costs due to site-specific conditions.
                              1-1

-------
Section 4 presents, on a regional basis, estimates of the



total capital and annualized costs for power plants iden-



tified by the Office of Planning and Evaluation as poten-



tially requiring S02 emission control.  Section 5 presents



cost estimates prepared for the Industrial Gas Cleaning



Institute by member companies that manufacture FGD systems.



     Results of the FGD cost survey conducted by the EEI/



CACC are presented in Section 6.  Key plant and FGD process



factors are noted.  Costs for individual facilities are



analyzed and compared with the cost estimates presented in



Section 3.
                              1-2

-------
  2.0  COST COMPONENTS FOR FLUE GAS DESULFURIZATION SYSTEMS






     Total costs of flue gas desulfurization systems include



both capital and annualized costs.  Capital costs are direct



and indirect.  Direct costs are those of plant equipment,



instrumentation, piping, electrical and structural mate-



rials, site work, insulation, painting, and pilings, and the



accompanying costs of installation or application.  Indirect



costs include interest assessed during construction; con-



tractors fees and expenses; engineering, freight, and off-



site expenses; taxes, allowances, and contingencies.



     Annualized operating costs are both fixed and variable.



Variable costs include those of utilities, labor, mainte-



nance, and in some cases overhead.  Fixed costs include



those of depreciation, interim replacement, insurance,



taxes, and capital charges.  The various components of



capital and annualized cost are discussed in greater detail



in Sections 2.1 and 2.2.



     The major items included as representing the cost of



flue gas desulfurization must be clearly identified.  Four



major cost elements are typically included, each of which



includes both a direct and indirect cost component:
                             2-1

-------
     0    S02 emission control


     0    Particulate emission control


     0    Sludge disposal or by-product regeneration/re-
          covery system


     0    Replacement power


     Our analysis excludes consideration of particulate


emission control, since the purpose of the study is to


identify the incremental costs of S02 emission control.


Consideration of sludge disposal and by-product regenera-

                           *
tion/recovery are included.   Cost of replacement power or


"capacity penalty" may be treated in several ways that


impinge upon both capital and annualized costs.  Because of


the interest in this cost element, it is discussed sepa-


rately in Section 2.3.


2.1  CAPITAL COST COMPONENTS

     The major capital cost components of an FGD system


consist of plant equipment, installation, and site develop-


ment; and indirect costs.


2.1.1  Plant Equipment and Installation for SO,, Control


     Table 2.1 lists the major process equipment required


for regenerative and nonregenerative FGD systems.  Instal-


lation of this equipment requires foundations; steel work


for support; buildings; piping and ducting for effluents,


slurries, sludge, steam, overflows, acid, drainage, and


make-up water; control panels; instrumentation; insulation


of ducting, buildings, piping, and other equipment; paint-
* Appendix A presents a brief discussion of methods of sludge
  disposal.
                             2-2

-------
                                       Table  2.1  MAJOR FGD SYSTEM EQUIPMENT SUMMARY
              Equipment
                         Description
to
I
u>
         Material handling-raw
         materials
         Feed preparation-raw
         materials
         SO_ scrubbing
         Flue gas reheat
         Gas handling
         Sludge disposal
         Utilities
         Cake processing
         Regeneration
         Purge treatment
Equipment for the handling and transfer of raw materials  includes unloading
facilities,  conveyors, storage areas and silos, vibrators,  atmospheric emission
control associated with these facilities, and related accessories.

Equipment for the preparation of raw materials to produce a scrubbing slurry
consists of feed weighers, crushers, grinders, classifiers, ball mills, mixing
tanks, pumps, agitators, and related accessories.

Equipment of a nonregenerative system for scrubbing the S02~laden flue gas in-
cludes scrubbers, demisters, effluent hold tanks, agitators, circulating pumps,
pond water return pumps, and related accessories.  In addition,  scrubbing equip-
ment for a regenerative system includes converter, catalyst storage,  conveyors,
and related accessories.

To increase plume buoyancy and minimize condensation the  scrubber exhaust gas is
heated from about 125° to 175°F.  Equipment required includes an economizer,
air/steam or fluid heaters, condensate tanks, pumps, soot blower, and related
accessories.

Equipment to handle the boiler flue gas includes booster  fans, ductwork, flue
gas bypass system, turning vanes, supports, platforms, and related accessories.

Nonregenerative FGD systems require a clarifier, pumps, vacuum filtration, sludge
fixation equipment, and related accessories.

Equipment to supply power to the FGD equipment consists of switch-gear, breakers,
transformers, and related accessories.

Equipment for processing the by-product of regenerative FGD systems includes a
rotary kiln, fluid bed dryer, conveyor, storage silo (MgSO3, etc.), vibrator,
combustion equipment and oil storage tanks, waste heat boiler, hammer mills etc.
Or, evaporators, crystallizers, strippers, tanks, agitators, pumps, compressors,
etc.  Or H2S04 absorber and cooling, mist eliminator, pumps, acid coolers, tanks,
etc.

Equipment for regeneration of the scrubber medium of a regenerative system consists
of: coke material handling system, storage, weight feeder, conveyor,  rotary kiln,
fluid bed calciner, dust collector, storage silo  (MgO, etc.), vibrator, combustion
equipment and oil storage tanks, waste heat boiler, hammer mill, etc.  Or, evapo-
rators, crystallizers, strippers, tanks, agitators, pumps, compressors, etc.  Or
H2SO. absorber and cooling, mist eliminator, pumps, acid coolers, tanks, etc.

Equipment for the removal of sodium sulfate  includes refrigeration,  pumps, tanks,
crystallizer, centrifuge, dryer, dust collector, conveyors, storage,  and related
equipment.

-------
ing; and, in some instances, piling.  Site development

includes right-of-way for sludge disposal? site clearing and

grading; construction of access roads and walkways; estab-

lishment of rail, barge, or truck facilities, and parking

facilities; landscaping; and fencing.

2.1.2  Indirect Costs

     Indirect costs include the following elements:

     Land required for the FGD process, including sludge
     waste or regeneration facility, storage, right-of-ways.

     Interest accrued during construction on borrowed
     capital.

     Contractor's fee and expenses, including costs for
     field labor payroll; supervision field office; per-
     sonnel; construction offices; temporary roadways;
     railroad trackage; maintenance and weld shops; parking
     lot; communications; temporary piping and electrical
     and sanitary facilities; safety security of all types—
     fire, material, medical, etc; construction tools and
     rental requipment; unloading and storage of materials;
     travel expenses; permits; licenses; taxes; insurance;
     overhead; legal liabilities; field testing of equip-
     ment; start-up; labor relations.

     Engineering Costs, including administrative, process,
     project, and general; design and related functions for
     specifications; bid analysis; special studies; cost
     analysis; accounting; reports; consultant fees; pur-
     chasing; procurement; travel expenses; living expenses;
     expediting; inspection; safety; communications; mod-
     eling; pilot plant studies; royalty payments during
     construction; training of plant personnel; field engi-
     neering; safety engineering; and consultant services.

     Legal expenses, including those for securing permits,
     right-of-way sections, etc.

     Freight, including delivery costs on FGD process and
     related equipment shipped F.O.B.

     Off-site expenditures, including those for power house
     modifications; interruption to power generation; and
     service facilities added to the existing plant facil-
     ities.
                              2-4

-------
     Taxes, including sales, franchise, property, and
     excise taxes.

     Insurance, covering liability for equipment shipped and
     at site; fire, other casualty, personal injury, and
     death; damage to property embezzlement; delay; and
     noncompliance.

     Shakedown and contingency costs, including those of
     malfunctions; alterations to design equipment; premium
     time for repairs; start-up utilities; materials for
     process; price changes due to inflation; and wage scale
     increases.

     Spare parts stock to permit 100 percent process avail-
     ability, including pumps, valves, controls, special
     piping and fittings, instruments, spray nozzles, and
     similar items.

2.2  ANNUAL OPERATING COSTS

     Annual operating costs of a flue gas desulfurization

system are comprised of:

     Raw materials, including those required by the FGD
     process for sulfur dioxide control, system loss, and
     sludge fixation.

     Utilities, including water for slurries, cooling and
     cleaning; electricity for pumps, fans, valves, lighting
     controls, conveyors, and mixers; fuel for reheating of
     flue gases; and steam for processing.

     Operating labor, including the supervisory and skilled
     and unskilled labor required to operate, monitor and
     control the FGD process.

     Maintenance and repairs, consisting of both manpower
     and materials to keep the unit operating efficiently.
     The function of maintenance is both preventive and
     corrective to keep outages to a minimum.

     Overhead; a business expense that is not charged
     directly to a, particular part of a, process, but is
     allocated to it.  Overhead costs include administra-
     tive, safety, engineering, legal, and medical services,
     payroll; employee benefits; recreation; and public
     relations.

     Fixed charges, which continue for the estimated life of
     the process, include costs of the following:
                              2-5

-------
     0    Depreciation - the charge for losses in physical
          assets due to deterioration (wear and tear,
          erosion and corrosion) and other factors, such as
          technical changes making the physical assets
          obsolete.

     0    Interim replacement - costs expended during the
          year for temporary or provisional replacement of
          equipment that has failed or malfunctioned.

     0    Insurance - costs of protection from loss by a
          specified contingency, peril,  or unforeseen event.
          Required coverage could include losses due to
          fire, personal injury or death, property damage,
          embezzlement, explosion, lightning, or other
          natural phenomena.

     0    Taxes, including franchise, excise, and property
          taxes leveed by a city, county, state, or Federal
          government.

     0    Capital costs due to interest on borrowed funds.

     Credits, which are negative charges for marketable by-
     products primarily from regenerative systems and
     occasionally from nonregenerative systems.

     Appendix B presents a procedure for translating utility

investment and expense into annual revenue requirements.  It

is based upon the practices followed by regulatory author-

ities in the United States and on statute law with respect

to income tax and the deductability of various items of

expense in calculating the amount of such taxes.*

2.3  REPLACEMENT CAPACITY AND ENERGY PENALTIES

     There is both an energy and replacement capacity penalty

associated with flue gas desulfurization systems.  Replace-

ment capacity is the additional power-generating capacity

required to compensate for the power used by the flue gas

desulfurization system.  The energy penalty is the increased
* Prepared under subcontract to PEDCo by Foster Associates.
                              2-6

-------
number of BTU's required to produce a kilowatt-hour of
electricity.
     Approximately 1.5 to 4 percent of a plant's gross
energy input is required to run a flue gas desulfurization
system; an additional 1 to 2 percent may be required for
particulate emission control using venturi scrubbers.
Alternatively, less than 0.5 percent would be required if an
electrostatic precipitator were used in place of the venturi
scrubber.  It should be noted that there is an apparent
trend towards the use of electrostatic precipitators because
of the FGD process chemistry complications created by par-
ticulate scrubbers.
     The power requirement for an FGD system is approxi-
mately equivalent to the power required to run the boiler
feed pumps and fans in the power plant.  Thus to generate a
net of 1000 MW, a plant must have a gross rating of approxi-
mately 1080 MW (allowing 40 MW to run the plant and 40 MW to
run the FGD system).
     The energy consumed by the FGD system is about equally
split between energy for stack gas reheat and electricity to
run the process equipment (of which about half is to over-
come the system pressure drop and the remainder is for
operation of pumps, ball mills, and the like).  The amount
of energy consumed for stack gas reheat varies with the
amount of reheat required and also somewhat with the type of
reheat system used.  Some types of reheat systems will not
                             2-7

-------
cause the plant to be derated in terms of KWH of electricity



produced  (i.e., there will be only an energy penalty, not a



capacity penalty).  For example, if the plant power pro-



duction is turbine-limited (as opposed to boiler-limited),



the excess steam produced by the boiler can be used to



reheat the stack gases.  Similarly, if a direct-fired re-



heater is used, plant capacity will not be derated although



the energy consumption per KWH generated will increase in



the same manner as if the unit were derated.  Furthermore,



many plants may operate without flue gas reheat or combine



scrubbed and unscrubbed flue gases to attain desired reheat



temperatures.  It is not known how many plants are turbine



limited or how many will be able to use bypassed flue gas



for reheat.  It is unlikely that a significant number of



plants will be able to use direct reheat since either fuel



oil or natural gas, both premium fuels, would be required.



     For regenerative processes, additional energy, which



would usually not result in a generating capacity derating,



is required.  For example, the Wellman-Lord process requires



approximately 8 pounds of steam for every pound of S02



recovered and, if elemental sulfur is produced as the by-



product, requires between 15 million and 80 million SCFH of



natural gas, depending upon the sulfur content of the coal



and efficiency of the sulfur recovery plant.  The total



energy requirement for the regeneration facility would be



approximately 3 percent of the total heat input to the
                              2-8

-------
boiler.  For the Mag-Ox process, approximately 3 percent of

the heat input to the boiler would be required to run the

calciner and crystal dryer in addition to the 1.5 to 4 per-

cent required to run the FGD system and for reheat.  Energy

requirements for the Cat-Ox process would depend upon

whether the catalytic conversion section is installed before

or after the air preheater.  If it is installed after the

air preheater, approximately 3 percent of the total station

heat input may be required to reheat the flue gases to the

temperature required for catalytic conversion.  Thus the

capacity replacement penalty for a regenerable process would

also be between 1.5 and 4%, but the energy penalty would be

between approximately 3 and 5%.

     Among the alternative methods for determining capacity

replacement costs are the following:

     (1)  Capacity replaced by conventional fossil-fuel-
          fired plants at plant costs of approximately
          $350/KW (1975 dollars).

     (2)  Capacity replaced by conventional fossil-fuel-
          fired plants but at the incremental cost for
          expanding a 1000-MW station in a power system to a
          1500-MW station to provide for lost capacity at
          several stations.

     (3)  Capacity replaced by peaking turbines.  Existing
          units would operate at higher capacity factors to
          compensate for the derating, and peaking turbines
          would make up for the lost capacity at peak demand
          periods.  Although the peaking units would entail
          a much higher operating cost, they would operate
          for only short periods of time.  The primary
          advantage is their much lower capital cost of
          approximately $135/KW.
                              2-9

-------
     Computed replacement power costs for each of these

three alternatives are presented in Table 2.2.


      Table 2.2  COMPARISON OF REPLACEMENT POWER COSTS3
Replacement capacity method
 Capital
cost, $/KW
  Annualized
cost, mills/KWH
Conventional coal-fired
  plant at $350/KW

Conventional coal-fired
  plant at incremental
  cost of $300/KW

Peaking turbines at
  $135/KW and operating
  costs of 21 mills/KWH
7.00-14.00
6.00-12.00
2.70- 5.40
   0.31-0.62
   0.28-0.59
   0.29-0.65
  Lower figures are based upon 2% electric power derating
  of station capacity whereas the higher numbers are based
  upon a 4% derating.

  Based upon a 20% capacity factor for peaking turbine
  operation and the same net KWH output from the sum of
  the turbine and derated boiler outputs as the boiler
  before derating due to FGD system installation.
                              2-10

-------
  3.0  COST ESTIMATES FOR FLUE GAS DESULFURIZATION SYSTEMS






     The capital and annualized costs of flue gas desul-



furization systems can vary significantly depending upon



design philosophy and site-specific factors.  Factors having



a major cost impact are plant size (capacity), remaining



life, and capacity factor; FGD process and design; sulfur



content and heating values of the coal; maximum allowable



S02 emission rate; status of FGD installation (new plant or



retrofit); particulate control requirements; and replacement



power requirements.



     To present unencumbered cost estimates and illustrate



the impact of site and process factors on total installed



and annualized costs of FGD systems,  model plants have been



defined and cost estimates have been prepared for each.  A



summary of the results is presented in Table 3.1.  These



costs are in January 1975 dollars and do not include escal-



ation through project completion.  In Section 5 these esti-



mates are compared with those prepared by manufacturers of



control systems and in Section 6, with the costs reported by



utilities that are either installing or planning to install



FGD systems.
                              3-1

-------
                                  Table 3.1  SUMMARY OF  MODEL PLANT FGD COSTS
Model plant
characteristics
250 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
500 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0,6% S
1000 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
Capital costs
Limestone
$ MM
20.2
16.5
18.6
14.7
35.1
29.2
32.3
26.4
69.5
56.8
64.4
52.0
$/KW
81
66
74
59
70
58
65
53
69
57
64
52
Wcllman-Lord
$ -MM
30.5
23.8
23.5
17.5
56.9
45.0
44.0
33.4
104.2
85.7
79.9
64.3
$/KW
122
95
94
70
114
90
88
67
104
86
80
64
Annualized costs
Limestone
$ MM/yr
6.8
5.5
5.9
4.6
11.2
9.7
9.6
8.0
22.0
18.6
18.9
15.7
mills/KWH
5.18
4.17
4.47
3.46
4.27
3.68
3.63
3.05
4.18
3.54
3.59
2.97
Wellman-Lord
$ MM/yr
8.9
6.7
7.0
5.1
15.3
12.3
12.1
9.4
28.1
23.3
22.0
18.0
mills/KWH
6.76
5.06
5.33
3.86
5.83
4.66
4.59
3.56
5.34
4.44
4.18
3.41
OJ
I
NJ

-------
     The 12 model plants analyzed for FGD costs were se-



lected to incorporate four varying cost factors: plant size



(capacity), installation status, FGD system type, and degree



of S0? control required.  Boiler capacities of 250 MW, 500



MW, and 1000 MW were' selected to cover a range representa-



tive of U.S. power plant boilers.  Both new and existing FGD



systems applications were considered for each boiler size.



Wellman-Lord (sodium solution scrubbing) and limestone



scrubbing FGD systems were analyzed for each size plant to



determine costs for both regenerative and nonregenerative



processes.  Each plant size was also analyzed for two S0_



control requirements: high-sulfur coal  (3.5%) with an S02



limitation of 1.2 lb/10  BTU  (Federal New Source Performance



Standard), and low-sulfur coal  (0.6%) with an SO2 limitation



of 0.15 lb/106 BTU.



     Other variables such as remaining plant life and plant



capacity factor were selected to be representative of each



model plant.  Operating costs for such components as raw



materials and utilities, which vary with geographical



location, were selected to be representative of a midwest



location.  Table 3.2 identifies the characteristics and



major assumptions for the model plants.



     Printouts for the model plant cost estimates are



presented in Appendix C.  Appendices D and E present de-



scriptive design information, including process flow sheets,



equipment lists, standard scrubber module sizes, etc. for



the limestone and Wellman-Lord systems, respectively.
                             3r3

-------
                   Table 3.2  SUMMARY OF CHARACTERISTICS AND ASSUMPTIONS FOR MODEL PLANTS
             Model plant parameters
                                             Characteristics and assumptions
00
I
Plant capacities,  megawatts

Plant status

Coal characteristics


S0~ control requirement



Location

Boiler data

  Capacity factor

  Heat rates, flue gas flow
    rates and remaining life
                                            250,  500,  and 1000 (single boilers)

                                            New and existing (retrofit)

                                            Low sulfur coal: 0.6%,  9000 BTU/lb
                                            High sulfur coal: 3.5%, 12,000 BTU/lb

                                            Low sulfur coal: 0.15 lb/10g BTU
                                            High sulfur coal: 1.2 lb/10  BTU (Federal New Source
                                              Performance Standard)

                                            Midwest Location-East North Central Region
                                            Assumed 0.6 for all 12 plants
Capacity,
MW
250 new
250 existing
500 new
500 existing
1000 new
1000 existing
Heat rate,
BTU/KWH
9,200
9,500
9,200
9,200
8,700
9,000
Flue gas
flow rate,
ACFM/MW
3,175
3,275
3,080
3,140
2,980
3,080
Remaining
boiler
life, yrs.
35
15
35
20
35
25
Assumed 310°F for all plants
         Flue gas temperature


           Detailed Cost Estimated for Advanced Effluent Desulfurization Processes, prepared for
           Control Systems Laboratory, Office of Research and Development,  U.S. Environmental
           Protection Agency, under Interagency Agreement EPA IAG-134(d)  Part A, by G. C.
           McGlanery, et.al,  Tennessee Valley Authority,  pp.  66,60.   May 1974.

-------
              Table 3.2 (continued).   SUMMARY OF CHARACTERISTICS AND ASSUMPTIONS FOR MODEL PLANTS
              Model plant parameters
u>
en
Operating cost factors

  Raw materials
     Limestone cost
     Soda ash cost (Wellman-Lord)
     Sulfuric acid credit
       (Wellman-Lord)
     Salt cake credit (Wellman-
       Lord)
  Electricity cost

  Taxes

  Capital cost

  Sludge disposal

  FGD system life

  Retrofit characteristics
                                             Characteristics and assumptions
Based on East North Central Regional averages


$6.00/ton delivered
$55.00/ton
$20.00/ton

$40.00/ton

15 mills/KWH

4%

9%

Assumed on-site disposal of stabilized  (fixed)  sludge.

Assumed 20 years for depreciation purposes.

Longer duct runs, tight space constraints, increased
construction labor costs.

-------
3.1  CAPITAL COSTS



3.1.1  Model Plants



     Capital costs for the 12 model plants are shown in



Table 3.3.  Costs for the limestone system assume on-site



sludge disposal.  Comparison of costs reveals that costs for



the Wellman-Lord system costs are 15 to 50 percent higher



than those for limestone.  Costs per kilowatt for the four



different plants within each size category diminish for both



new and existing plants by about 50 percent as size in-



creases from 250 to 500 MW; it levels off from 500 to 1000



MW for new plants and existing plants, respectively.  The



decrease in kilowatt cost is due primarily to such factors



as economy of scale.  The higher cost of retrofit instal-



lations in each of the three size groups is due to the extra



cost of adapting an FGD system to the fixed conditions of an



existing plant.



3.1.2  Factors Affecting Capital Costs



     The capital costs presented in Table 3.3 can be sub-



stantially modified by varying S02 removal requirements and



flue gas rates, difficulty of retrofit, conditions of ter-



rain and subsurface, system redundancy, particulate control



requirements, remaining plant life, boiler life, and escala-



tion or inflation.  The impact of these factors on capital



costs is discussed in this section.  Table 3.4 presents a



summary of these results.
                              3-6

-------
                                               Table 3.3   MODEL PLANTS CAPITAL  COSTS
U)
I
-j
Model plant
chn t fie.* t.ci i l.iiLicj:!
2^0 Marjawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
500 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
1000 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
Limestone
Scrubbing
5/KW

40
30
38
29
35
28
34
27
36
29
34
28
Sludge ^
disposal
S/KW

6
8
4
5
5
5
3
3
4
4
2
2
Indirect
costsc
5/KW

35
28
32
25
30
25
28
23
30
24
28
22
Total
?/KW

81
66
74
59
70
58
65
53
70
57
64
52
$ MM

20.2
16.5
18.6
14.7
35.1
29.2
32.3
26.4
69.5
56.8
64.4
52.0
Wellman-Lord
Scrubbing
v/KW

64
50
51
38
61
48
48
37
56
46
44
35
ny-
Product
Recovery
C-/KW

8
8
4
4
6
6
3
3
5
4
2
2
Indirect
costsc
?/KW

49
37
40
29
47
36
37
27
43
35
34
27
Total
$/KW

122
95
94
70
114
90
88
67
104
86
80
64
$ MM

30.5
23.8
23.5
17.5
56.9
45.0
44.0
33.4
104.2
85.7
79.9
64.3
         a  Includes  limestone preparation system (conveyors,  storage silo,  ball mills, pumps, motors, and storage tank) and scrubbing
           system  (absorbers, fans and motors, pumps and motors,  tanks,  reheaters,  soot blowers, ducting, and valves).

           Sludge disposal costs do not include associated indirect charges.

         c  Includes  interest during construction, field labor and expenses, contractor's  fees and expenses, engineering, freight,
           offsite,  spares, taxes, contingency, and allowance for shakedown.

           Includes  soda ash preparation system  (storage silo, vibrating feeder,  storage  tank, agitators, and pumps and motors) and
           scrubbing system  (absorbers, fans and motors, pumps and motors,  reheaters,  soot blowers, ducting, and valves) purge treat-
           ment  (refrigeration unit, heat exchanger, tanks, dryer, elevator,  pumps  and motors, centrifuge, crystallizer, storage silo
           and feeder) and regeneration system (pumps and motors, evaporators and reboilers, heat exchangers, tanks, stripper, and
           blower).

-------
         Table 3.4  TYPICAL CAPITAL COST VARIATIONS

                FOR SITE SPECIFIC CONDITIONS
Factor
SO-j removal requirements
Flue gas flow rate
Installation status-^- (new vs.
retrofit)
Conditions of terrain and sub-
surface
FGD system redundancy
Particulate control requirements
Sludge disposal requirements
(nonregenerative processes)
Typical
cost
15
10
10

3
10
25
10
total capital
impact, %
- 20
- 30
- 40

- 15
- 40
- 35
- 30
  Variations in capital cost are from a model plant
  500  MW/existing/3.5%  S boiler.

  Variations in capital cost for 250-1000 MW model
  plants .
         Removal Requirements

     The quantity of S02 to be removed at an FGD installa-

tion is the difference between the actual S02 emission rate,

which varies directly with the coal's sulfur content, and

the rate allowed by the applicable requlation.

     The S02 removal requirement affects the size of the

sludge facilities, including treatment and disposal, re-

quired by nonregenerative systems.  The effect of S0?

removal requirements on capital cost is illustrated in

Figure 3.1, which shows the incremental kilowatt cost
                               3-8

-------
CO
I
VQ
               •fa*)-
+40



+30



+20



+10
               U-
               o
               o
-10



-20
               CL
               «t
               0 -30
                  -40
                                       LOCATION  OF MODEL PLANT
                                       CHARACTERISTICS
                                                          I
                          123456

                                        SULFUR CONTENT OF COAL, wt.%



            Figure  3.1   Incremental effect of sulfur content of coal  on model plant capital

                          Cost (model plant characteristics; 500 MW/existing).

-------
differential for the model 500 MW/existing plant over a



range of coal sulfur contents (allowable 302 emission rate



of 1.2 Ib/MM BTU).  Total capital costs vary from $58 to $70



per kilowatt and $70 to $128 per kilowatt, respectively for



the limestone and Wellman-Lord systems for this model plant.



As the figure shows, capital costs of the regenerative



Wellman-Lord system is much more sensitive to S0_ removal



requirements than is the costs of the nonregenerative lime-



stone process.



     Flue Gas Flow Rate



     Flue gas flow rate is expressed in terms of actual



cubic feet per minute  (ACFM).  This flow rate directly



affects the size of FGD equipment required for both re-



generative and nonregenerative systems.  It varies pri-



marily with boiler design, including such factors as opera-



ting temperature and exit gas temperature, percent excess



air, and efficiency; coal characteristics, including ash,



sulfur, and moisture contents and heating value; and size



and age of the boiler.  In general, the flow rate decreases



with increasing boiler age.  The effect of flue gas flow



rate on capital cost is illustrated in Figure 3.2, which



shows the incremental kilowatt cost differential for the



model plant 500 MW/existing/3.5% S boiler over a range of



flow rates.  The limestone and Wellman-Lord capital cost



differentials behave similarly, the limestone differential



increasing at only a slightly faster rate.  Total capital
                              3-10

-------
      +50
      +40
       +30
    S +20
    UJ
00
^   £,
    o
       +10
<    °
o
       -10
       -20
                                       LOCATION OF MODEL  PLANT CHARACTERISTICS
                                              I
                                                            1
                 2800      3000      3200      3400     3600     3800

                                              acfm AT 310-F PER MW
                                                                    4000
4200
4400
4600
           Figure 3.2  Incremental effect of  flue gas volumetric flow  rate on model  plant capital



                     cost  (model plant characteristics:  500 MW/Existing/3„5% sulfur coal) .

-------
costs vary from $60 to $100 per kilowatt and $94 to $145 per



kilowatt, respectively for the limestone ctnd Wellman-Lord



systems for this model plant.



     Installation Status  (new and retrofit applications)



     Higher capital costs are often required for application



of FGD systems to existing plants than for application to



similar new plants.  An FGD system for a new plant can be



incorporated into the overall design of the plant, whereas a



retrofit application requires that the system be adapted to



the rigid configurations of the existing plant; the retrofit



system must be built within fixed space limitations and in a



manner that does not interfere with operation of the plant.



     Configuration of equipment in the existing plant



governs the location of the FGD system.  For instance, if



the boiler stack is on the roof of the boiler house, as it



is in many older plants, the FGD system may have to be



placed at ground level; this location could entail long



ducting runs from ground level to the stack or could require



a new stack.  At some plants the stack is situated directly



adjacent to the boiler house or particulate control de-



vice, a placement that often necessitates locating the FGD



system at some distance, even hundreds of feet away.  At



some plants, especially those located in urban areas, not



enough space is available at ground level to accommodate the



entire FGD system.  In such cases either the FGD scrubber



units must be stacked, one on top of the other, or addi-



tional land must be acquired adjacent to the plant property.
                              3-12

-------
     Other capital cost components that can be increased

because of space restrictions are construction labor and

expenses, interest charges during construction (because of

longer construction periods), contractor fees and expenses,

and allowances for shakedown.  Table 3.5 presents a summary

of the capital cost impact of several retrofit conditions.


       Table 3.5  TYPICAL CAPITAL COST VARIATION WITH

                VARIOUS RETROFIT REQUIREMENTS


                                       Capital cost
 Retrofit requirements	increase, %

Long duct runs                             4-7

Tight space                                1 -18

Delayed construction   (1 year delay)       5 -15

New stack                                  6-20

                         Overall           1 -60


a For a model plant 500 MW/existing/3.5% S boiler.

  Varies with escalation rate during period(s) of delayed
  construction.

     Condition of Terrain and Subsurface

     The terrain of the power plant site affects the capital

cost of the FGD system as well as the cost of the entire

power plant by the sitework and structural requirements it

imposes.  Hilly terrain requires considerable grading and

filling to prepare the site for construction of foundations

and possible additional structural components.  Increase in

capital costs for installation of an FGD system in hilly

terrain can amount to 10 percent, including labor.
                              3-13

-------
     Subsurface conditions can necessitate piling to provide

adequate support for the concrete foundations of the FGD

system.  Additional capital costs for piling can amount to

4 percent, including labor.

     Redundancy

     Reliability of an FGD system can be increased by

providing spare process components that become integral

parts of the system when one of their counterparts fails.

For example, spare pumps are frequently included in the

system; this is simply good design practice, and such costs

are included in the model plant estimates.  Some plants,

however, are considering spare absorber trains.  For ex-

ample, an FGD system design with four absorbing trains might

incorporate a redundant fifth train.

     Figure 3.3 illustrates the effect of a spare scrubbing

train on the capital costs of FGD systems by showing the

capital cost increase per kilowatt over a range of boiler

capacities  (existing model plants burning coal with 3.5

percent S and allowable S02 emissions of 1.2 lb/10  BTU).*

The effect of redundancy decreases with increasing capacity,

since only one scrubber train is added throughout the

capacity range and the number of trains required for the

system increases with increasing capacity,  (for example, a

redundant 300-MW system has three trains instead of two,

whereas a redundant 900-MW system has seven absorbers in-

stead of six).
* A train consists of: ducting, absorber, holding tank,
  agitators, recirculation pump(s), demister, reheater,
  soot blowers, ducting shut-off valves, piping, and
  controls.

                              3-14

-------
i
M
cn
         30
         20
C£


O
       OO
       O
       O
       < 10
       Q-
       
-------
     Particulate Control



     If additional particulate control is required, a



venturi scrubber could be incorporated into the FGD system



prior to each scrubber train.  This would add about 30



percent ($21 per kilowatt for the limestone system and $34



per kilowatt for the Wellman-Lord system) to the capital



cost of a model plant 500 MW/existing/3.5% sulfur boiler.



The cost for an electrostatic precipitator for particulate



emission control would generally range between $20 and $40



per kilowatt depending upon coal properties and the degree



of control required.



     Sludge Disposal Options  (nonregenerative processes)



     The amount of sludge generated by a given plant is a



function of the sulfur and ash contents of the coal, coal



usage, load factor, mole ratio of additive, SO~ removal



efficiency, composition of the sludge, and moisture content



of the sludge.  Several methods are now used for disposal of



scrubber sludge.  The most common are ponding of untreated



sludge and landfilling of treated and untreated sludge.



     The capital and annualized costs of several sludge



dipsosal options for a model plant 500 MW/3.5% sulfur boiler



are presented in Table 3.6.



     Remaining Life of Plant and Related Capacity Factor



     Total boiler life is typically estimated to be 30 to 40



years; remaining life of a boiler is generally estimated



from the current age of the plant, unless more accurate
                              3-16

-------
               Table 3.6  COSTS OF TYPICAL SLUDGE DISPOSAL OPTIONS
     Options
Capital cost
   impact,a
    $/KW
Total annual!zed
   cost impact^-
    mills/KWH
I
H
~J
On-site ponding

     Unstabilized sludge,  water return

     Stabilized sludge, water return

Off-site pond (7 miles from the plant)

     Pumping, water return

     Pumping, stabilization, water
       return

     Trucking from on-site settling
       basin to pond, unstabilized
       sludge

     Trucking from on-site settling
       basin, stabilization
   3.55

   3.80



   9.80

  10110


   4.00



   4.25
       0.17

       0.47



       0.46

       0.74


       1.46



       1.49
  Model plant 500 MW, existing 3.5% S

-------
information is available on the boiler's retirement.

Capacity factor represents the fraction of actual annual

usage compared with potential annual usage at maximum

output.  The capacity factor of a boiler decreases with age,

since the boiler's efficiency declines, maintenance and

overhaul needs increase, and newer, more economical boilers

are added to the plant.  An approximate relationship between

capacity factor and remaining boiler life is shown in Table

3.7.


       Table 3.7  TYPICAL RELATIONSHIP BETWEEN BOILER

             CAPACITY FACTOR AND REMAINING LIFE


     Remaining life,                 Typical capacity
         years                         factor range

      40 - 31                           0.70 - 0.85

      30 - 21                           0.35 - 0.70

      21 - 16                           0.25 - 0.35

      16-0                            0.18 - 0.25


     The capital cost of an FGD system is affected by re-

maining life of the boiler in that the remaining boiler life

determines the size of the sludge pond for a nonregenerative

FGD system.

     Escalation

     Installation of an FGD system from initial design

through construction and subsequent acceptance tests re-

quires approximately 3 years.  Price escalation during this
                              3-18

-------
period directly affects the total capital cost of the



project; consequently, cost estimates must account for some



percentage of increase in costs.  Since progress occurs at



different rates throughout the life of the project, so too



does the outlay of expenditures.  Figure 3.4 illustrates the



effect of escalation on capital cost by showing the percent



increase of capital cost for a range of escalation rates



over a 3-year construction period.  The expenditure rate



assumes 14 percent of the total installed cost expended at



the end of 14 months, 24 percent at the end of 20 months,



and 100 percent at the end of 3 years.



3.2  ANNUALIZED COSTS



3.2.1  Model Plants



     Annualized costs for the 12 model plants for operating



of the Wellman-Lord and limestone FGD systems are presented



in Table 3.8.  Costs for the limestone system assume on-site



sludge disposal.  Comparison reveals that annual costs for



the Wellman-Lord process are 5 to 25 percent higher than



those for limestone.  The higher annual costs for retrofit



application in all three size groups are due to the effects



of the corresponding higher capital costs for retrofitting.



3.2.2  Factors Affecting Operating Costs



     The operating cost components directly affected by



independent factors are raw materials, utilities, operating



labor, and by-products (credits for regenerative FGD systems)



Costs of raw materials contribute 3 to 15 percent and 2 to 5
                              3-19

-------
   50
   45
   40


UJ
GO

CO

in  35
   30
CO
o
GO

£
0
o

LU
Q_
   25
   20
   15
   10
        i   i   i   i
                                                     i   i   i
                                           3 YEARS

                                      (START TO COMPLETION)
                      i   i   i   i  I   i   i   i   i
                                               I
                                                     i   i   i
                   5             10             15

                 ANNUALIZED COST ESCALATION RATE, %
                                                             20
         Figure 3.4   Impact  of cost escalation.
                             3-20

-------
                                            Table  3.8   MODEL  PLANTS  ANNUALIZED  COSTS
Model plant
characteristics
250 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
500 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
1000 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
Limestone
Operating
and
Maintenance
raills/KWH
1.75
1.54
1.31
1.10
1.49
1.33
1.07
0.91
1.44
1.26
1.04
0.87
Fuel
and .
Electricity0
mills/KWH
0.30
0.29
0.29
0.28
0.29
0.28
0.27
0.27
0.28
0.27
0.27
0.26
Fixed.
costs'
mills/KWH
3.13
2.34
2.87
2.08
2.49
2.07
2.29
1.87
2.46
2.01
2.28
1.84
Total
mills/KWH
5.18
4.17
4.47
3.46
4.27
3.68
3.63
3.05
4.18
3.54
3.59
2.97
$ MM/YR
6.8
5.5
5.9
4.6
11.2
9.7
9.6
8.0
22.0
18.6
18.9
15.7
Wellman-Lord
Operating
and
Maintenance
mills/KWH
1.24
0.90
1.30
0.99
1.04
0.74
1.11
0.84
0.93
0.70
1.02
0.81
Fuel
and .
Electricity0
mills/KWH
0.81
0.79
0.40
0.39
0.75
0.74
0.36
0.35
0.72
0.70
0.33
0.32
Fixed
costs3
mills/KWH
4.71
3.37
3.63
2.48
4.04
3.18
3.12
2.37
3.69
3.04
2.83
2.28
Total
mills/KWH
6.76
5.06
5.33
3.86
5.83
4.66
4.59
3.56
5.34
4.44
4.18
3.41
$ MM/YR
8.9
6.7
7.0
5.1
15.3
12.3
12.1
9.4
28.1
23.3
22.0
18.0
I
N)
         b
Includesi  raw materials; watori operating labor, maintenance, ami ovorhoad.

Includes:  power and steam (electricity and fuel costs).  Based upon approximately a  1.2% capacity derating plus a
1.6% energy penalty.

        i  iloi>< ou InLlcjii j in La vim lai'iauomaiiL,  LaxaB, inaujjaiice, and (Jdpitai CO BUB.

-------
percent of the total operating costs for limestone and



Wellman-Lord systems, respectively; these costs depend



primarily on the quantity of S02 to be removed.  Costs of



utilities contribute 5 to 10 percent and 7 to 15 percent of



the annual operating costs for limestone and Wellman-Lord



systems, respectively; these depend primarily on the cost of



electricity, amount of S02 to be removed, and the process



water and horsepower requirement.  The horsepower require-



ment is determined primarily by the size of the boiler (ACFM



to be treated).  Operating labor contributes 1 to 5 percent



of the total operating costs and depends primarily on the



size of the boiler.



     Other operating costs - maintenance, overhead, and



fixed costs - are basically dependent on the fixed invest-



ment of the FGD system and the costs for operating labor and



raw materials.  Depreciation, a fixed cost, also varies with



remaining life of the boiler.  Figure 3.5 illustrates the



effect of remaining boiler life on operating costs of lime-



stone and Wellman-Lord FGD systems.  This analysis differs



somewhat from the model plant cost in which the capacity



factor was assumed constant at 60%.



     The following factors also affect operating costs:



     S00 Removal Requirements
       ^


     The amount of SO- to be removed affects annual oper-



ating costs appreciably, since it is the major factor that



affects the cost of raw materials and utilities.  In addi-
                              3-22

-------
 27
 26
 25
 24
 23
 22
 21
 20
 .19
 18
i 17
(SI
   16
E
in
8  14
!  13
J1
In
   10
   9
   8
   7
   6
   5
n i  I  i    i i  i  rn i  i  i
                                 i  i  i  i   i  i  i  i   i  i  I  i   i  i  i  r
             I  i
                            CtL
                            o
                            -
                            •f.
                            0
                         0.6
                         0.5
                         0.4
                         0.3
                         0.2
                         0.1
                                0,
                                '0
                               5   10   15   20   25  30
                                REMAINING LIFE, yrs
                            WELLMAN-LORD
             LIMESTONE
                      10        15        20        25
                         BOILER REMAINING LIFE, yrs
                                                    30
  Figure 3.5  Effect of boiler remaining  life and corresponding
     capacity factor on model  plant annual  cost (model  plant
       characteristics: 500 MW/existing/3.5%  sulfur coal).
                                 3-23

-------
tion, since capital costs are also affected by S02 removal



requirements, this impact is reflected in the fixed charges.



     Figure 3.6 illustrates the effect of SO- removal re-



quirements on annual FGD system operating costs for the



model 500 MW/existing plant over a range of sulfur contents



(allowable S02 emission rate =1.2 lb/10  BTU).  Operating



cost of the Wellman-Lord system is more sensitive to SO,,



removal requirements than is operating cost of the limestone



process.  For the model plant the variation in total annual



cost amounts to 100 percent for Wellman-Lord and 45 percent



for limestone.  It should be noted that a large part of the



increase in annual operating cost due to increased S0?



control requirements is the fixed cost component, which



increases simultaneously with the increasing capital cost.



     Flue Gas Flow Rate



     Since the volumetric flow rate directly affects the



amount of FGD system equipment required, it also affects the



fixed operating cost components.  Horsepower and utility



requirements are also influenced by flow rate.  Figure 3.7



graphically illustrates the effect of flue gas flow rate on



annual operating cost, by showing the incremental kilowatt



cost differential for a model 500 MW plant, 3.5% sulfur



existing boiler over a range of flow rates.
                              3-24

-------
U)
I .
NJ
Ui
                 +2.0



                 +1.
                 +1.0 —
+0.5
-0.5



-1.0



-1.5
                                    1
                                                         LOCATION OF MODEL PLANT
                                                         CHARACTERISTICS
                              I
I
I
                          1          2          3          4          5          6

                                         SULFUR CONTENT OF COAL, wt %


                  Figure  3.6   Effect of  sulfur content of coal on model plant annual cost


                               (model plant characteristics: 500 MW  Existing).

-------
OJ
I
K)
CTl
    CfL
    00 f>
    o •—
    :z>
    •z.
    •ZL
    =t
+2.6

+2.4

+2.2

+2.0

+1.8

+1.6

+1.4

+1.2

+1.0

+0.8

+0.6

+0.4

+0.2

   0

-0.2

-0.4
                                                                                       •**'  WELLMAN-LORD  _
                                        LOCATION OF MODEL PLANT CHARACTERISTICS
                       I
                              I
I
I
I
I
I
                                                                                            LIMESTONE    —
                       \       j 	     1      .1   	 ^       1      .__ . ft	     *-       '       '
                     2800    3000    3200    3400    3600    3800    4000   4200    4400    4600

                                              acfm AT 310°F  PER MW

              Figue  3.7   Incremental effect of flue gas volumetric  flow rate on model  plant  operating

                        cost  (model plant characteristics:  500 MW/Existing/3.5% sulfur  coal).

-------
  4.0  NATIONWIDE FLUE GAS DESULFURIZATION COST ASSESSMENT






     Capital and annualized costs of flue gas desulfuriza-



tion systems were estimated for 126 power plants in the



United States.  These plants were selected by EPA's Office



of Planning and Evaluation (OPE) on the basis that they re-



ceived shipments of coal in the first six months of 1974



with an average sulfur content greater than that permitted



by projected S0~ emission regulations.  Inclusion of a



particular plant does not necessarily reflect its legal



compliance status and it must be emphasized that the list of



plants may be changed as more accurate information becomes



available.



     Methodology



     Data for estimating capital and operating costs of FGD



systems for the selected plants were acquired from published



sources of power plant data (e.g., capacity, load factors)



and in-house files developed by conducting plant inspections



for EPA.  Some discrepancies in the data from the various



sources were apparent and "most reasonable" values were



selected for conducting the evaluation.  Because of time and



budget constraints, site-specific factors could not be



included in the cost estimates.  Therefore, the costs can



not be considered accurate for any individual plant.  The
                             4-1

-------
sole purpose of preparing such estimates was to aggregate



the individual estimates to develop regional and national



estimates of FGD system costs.



     Appendices D and E present design details of the lime-



stone and Wellman-Lord systems used in this assessment.



Appendix F presents a list of plants with associated cost-



determining characteristics and cost estimates, plus a



description of the cost estimating methodology.



     Cost Assessment Results



     Results of the FGD cost assessment are summarized on a



regional and national basis in Table 4.1 for all selected



plants.  Table 4.2 summarizes the costs for only those



selected plants requiring 25 percent or more control.  The



regions are those established by the Economics and Statis-



tics Division of the National Coal Association and are



illustrated in Figure 4.1.  States within each region are



listed in Table 4.3.  The capital and operating costs were



determined by selecting the lower of the capital costs of



the two FGD systems analyzed.  The operating cost of that



system was also used for the summary, even if the more



expensive system gave a lower annual operating cost.



Regional capital cost varies from $56/KW to $73/KW with an



average of $64/KW.  Individual plants varied from $48/KW to



$259/KW with the same average.  Capital costs for the lime-



stone system were lower than those for the Wellman-Lord
                               4-2

-------
                                  Table 4.1   REGIONAL AND  NATIONAL FGD COST SUMMARY
Region
Number of Plants
Capacity, megawatts
Total3
Units scrubbed3
Remining life of units scrubbed
Capital costs
$ MM3
$/KW scrubbed13
Annualized costs
Total $ MM/yra
Mills/KWH15
Fuel & electricity, $ MM/yra
Mills/KWHb
Operation & maintenance
$ MM/yra
Mills/KWHb
New
England
1
965
695
25
41.0
59
14.7
3.1
2.2
0.5
4.9
1.1
Middle
Atlantic
16
386
192
25
14.0
73
4.9
4.6
0.4
0.4
1.9
1.8
East
North
Central
60
692
366
29
24.4
67
8.8
5.0
0.6
0.3
3.5
2.0
West
North
Central
7
682
220
31
14.9
67
5.0
5.3
0.3
0.2
2.2
2.1
South
Atlantic
22
837
390
33
22.8
64
8.6
4.5
0.4
0.2
3.5
1.8
East
South
Central
17
1173
803
27
47.8
60
15.6
3.9
0.9
0.2
5.8
1.4
West
South
Central
0

-
-
.
-

-
-
-

-
Mountain
3
1520
990
37
70.0
56
16.7
4.0
1.4
0.3
4.9
1.2
Pacific
0

-
-
.
-

-
-
-

-
National
126
765
416
29
26.6
64
9.2
4.5
0.6
0.3
3.6
1.7
I
U)
       Plant average
       Average weighted by capacity

-------
                    Table 4.2  REGIONAL AND  NATIONAL  FGD COST  SUMMARY OF  PLANTS

                               REQUIRING GREATER THAN  25% SO2 CONTROL
Region
Number of plants
Capacity, megawatts
Total3
Units scrubbed
Remaining life of units scrubbed
Capital costs
$ MMa
$/KW scrubbed13
Annualized costs
Total $ MM/yra
Mills/KWHb
Fuel & electricity, $ MM/yra
Mills/KWH**
Operation & maintenance
$ MM/yra
Mills/KWH*3
New
England
1
965
695
25
41.0
59
14.7
3.1
2.2
0.5
4.9
1.1
Middle
Atlantic
7
479
364
25
26.3
72
9.3
4.5
0.8
0.4
3.4
1.75
East
North
Central
44
700
455
28
29.7
65
10.8
4.8
0.7
0.3
4.3
1.9
West
North
Central
5
630
284
31
18.6
66
6.4
5.2
0.3
0.2
1.9
2.1
South
Atlantic
18
740
433
32
27.5
64
9.7
4.4
0.5
0.2
4.0
1.9
East
South
Central
16
1214
847
27
50.3
59
16.4
3.9
0.9
0.2
6.1
1.4
West
South
Central
0

-
m» *
.
-
.
-
-
-

-
Mountain
3
1520
990
37
70.0
56
16.7
4.0
1.4
0.3
4.9
1.2
Pacific
0

-
-
.
-
—
-
-
-

-
National
94
804
521
29
33.3
64
11.4
4.4
0.7
0.3
4.4
1.7
Plant average
Average weighted by capacity

-------
I
U1
                                                  WEST NORTH ]
                                                    CENTRAL  j
EASTNCTH
 CENTRAL
                           / MOUNTAIN I
                   ATLANTIC-
                   —-xs&s.
                      5
                                                                         EASTj SOUTH
                                                                           CETRAL
                                   Figure 4.1  National Coal  Association Regions.

-------
      Table 4.3  REGIONAL COMPOSITION BY STATE
New England

1.   Connecticut
2.   Maine
3.   Massachusetts
4.   Rhode Island
5.   Vermont
6.   New Hampshire

Middle Atlantic

1.   New Jersey
2.   New York
3.   Pennsylvania

East North Central

1.   Illinois
2.   Indiana
3.   Michigan
4.   Ohio
5.   Wisconsin

West North Central

1.   Iowa
2.   Kansas
3.   Minnesota
4.   Missouri
5.   Nebraska
6.   North Dakota
7.   South Dakota

South Atlantic

1.   Delaware
2.   District of Columbia
3.   Florida
4.   Georgia
5.   Maryland
6.   North Carolina
7.   South Carolina
8.   Virginia
9.   West Virginia
East South Central

1.   Alabama
2.   Kentucky
3.   Mississippi
4.   Tennessee

West South Central

1.   Arkansas
2.   Louisiana
3.   Oklahoma
4.   Texas

Mountain

1.   Arizona
2.   Colorado
3.   Montana
4.   Nevada
5.   New Mexico
6.   Utah
7.   Wyoming

Pacific

1.   California
2.   Oregon
3.   Washington
                         4-6

-------
system for about 90 percent of the plants.   Operating costs



for the limestone system were lower than those for Wellman-



Lord for about 85 percent of the plants.
                              4-7

-------
       5.0  MANUFACTURER ESTIMATES OF FGD SYSTEM COSTS
     Manufacturer estimates  of flue gas desulfurization



costs consistent with  the  model plant characteristics de-




scribed in Section  3 were  provided by two member companies



of the Industrial Gas  Cleaning Institute (IGCI)  for lime-



stone systems.  Table  5.1  presents a combined summary of



these estimates.




    Table 5.1  SUMMARY OF MANUFACTURER ESTIMATES OF FGD SYSTEM COSTS
Model plant
characteristics
250 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
500 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
1000 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
Limestone
Capital
costs
$/KW
61-78
56-74
55-58
50-57
55-68
49-68
49-51
43-51
48-66
43-62
42-48
37-48
Annualized
costs
mills/KWH
4.30
4.27
3.33
3.41
3.66
3.76
2.80
2.91
3.47
3.37
2.88
2.67
                                5-1

-------
     One of these member's cost estimates included a break-



down for capital and annual costs;  summaries of these item-



ized capital and annual costs are presented in Tables 5.2



and 5.3, respectively.



     Average manufacturer estimated capital costs for new



plants are an average of 8 percent lower than the new model



plant costs and an average of 20 percent lower for existing



plants.  The larger variation in retrofit costs is primarily



due to the differences in assumed retrofit difficulty.



     Manufacturer estimates of annual costs are an average



of 4 percent lower than model plants for new installations



and an average of 20 percent lower for retrofit applica-



tions.  Again, the larger variation in costs for retrofit



applications is primarily due to differences in assumed



retrofit difficulty.
                             5-2

-------
                Table 5.2  MANUFACTURER'S CAPITAL COSTS  SUMMARY  FOR LIMESTONE SYSTEM
Model plant
characteristics
250 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
500 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
1000 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
Scrubbing
$/KW
39
38
31
30
37
36
29
29
37
35
29
29
Sludge
disposal
$/KW
8
8
4
4
6
6
3
3
5
5
2
2
Indirect
costs
$/KW
31
28
23
23
25
26
19
19
24
22
17
17
Total
$/KW
78
74
58
57
68
68
51
51
66
62
48
48
$ MM
19.4
18.6
14.6
14.2
34.2
33.8
25.7
25.3
65.6
61.9
48.5
48.0
Ul
I
CO

-------
                    Table 5.3  MANUFACTURER'S ANNUALIZED COST  SUMMARY FOR LIMESTONE SYSTEM
Model plant
characteristics
250 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
500 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
1000 Megawatt Capacity
Retrofit, 3.5% S
New, 3.5% S
Retrofit, 0.6% S
New, 0.6% S
Operating
and
Maintenance3
mills/KWH
1.53
1.47
1.17
1.15
1.20
1.20
0.87
0.87
1.08
1.01
1.06
0.73
Fuel
and .
Electricity
mills/KWH
0.17
0.30
0.20
0.35
0.17
0.29
0.20
0.34
0.16
0.28
0.19
0.33
Fixed
costs0
mills/KWH
2.60
2.50
1.96
1.91
2.29
2.27
1.73
1.70
2.23
2.08
1.63
1.61
Total
mills/KWH
4.30
4.27
3.33
3.41
3.66
3.76
2.80
2.91
3.47
3.37
2.88
2.67
$ MM/YR
5.7
5.6
4.4
4.5
9.6
9.9
7.4
7.6
18.0
17.7
15.1
14.0
(Jl
I
            Includes:
         b  Includes:
         c
            Includes:
raw materials; water; operating labor, maintenance, and overhead.
power and steam  (electricity and fuel costs).
depreciation, interim replacement, taxes, insurance, and  capital  costs,

-------
                6.0  UTILITY INDUSTRY SURVEY






     A utility industry survey was conducted by the EEI/CACC



to determine the costs for FGD systems.  All utilities known



to have an FGD system that was operational, under construc-



tion or planned were contacted by the Edison Electric



Institute and requested to complete a fourteen page ques-



tionnaire.  The questionnaire requested information describ-



ing the FGD system and its costs.  Responses were received



for forty-three systems and analyzed by the National Eco-



nomic Research Associates (NERA), EEI/CACC's consultant.



The range of control system costs and averages were computed



for different system types and applications (new vs retrofit)



The results of their final analysis, however,  are not yet



available.



     The EEI/CACC sent copies of the questionnaires to PEDCo



for technical analysis.  As anticipated, the reported costs



covered a broad range due to both site-specific factors and



the lack of uniformity with respect to items included in the



cost estimates.



     Forty-seven responses were received.  Forty-three



questionnaires pertained to FGD systems, 3 to particulate



scrubber systems only and one responded that no scrubber
                              6-1

-------
system was either installed or being considered.  The

responses covered 30 utilities, 32 plants and 68 boilers for

a total capacity of 32,120 MW.  The reported costs ranged

from 33 to 197 $/KW with an average of $94/KW (a = 39.83).

Of these, 22 were lime or limestone based systems.  The cost

for these systems ranged from 34 to 116 $/KW with an average

of $78/KW (a = 26.56).

     PEDCo's analysis of the data centered on adjusting the

estimates to a common basis.  The costs were analyzed solely

to determine representative costs for flue gas desulfuriza-

tion systems, not to critique the design or reasonableness

of the costs reported by any utility.  Adjustments focused

primarily on the following items:

     0    Costs were adjusted to January 1975 dollars.
          Costs were reported in dollar values ranging from
          the years 1970 to 1980.

     0    Particulate control costs were deducted.  Since
          the purpose of the study was to estimate the
          incremental cost for SC>2 control, particulate
          control costs were deducted using either data
          contained in the cost breakdowns or as a per-
          centage of the total direct equipment cost.  The
          percentage reduction varied depending upon system
          design.

     0    Indirect charges were adjusted, usually upward, to
          provide adequate funds for engineering, field
          expenses, overheads, interest during construction,
          start-up, and contingency.

     0    Replacement power costs were deducted since only a
          few utilities reported such costs and these were
          presented using a variety of methods.   Thus the
          adjusted costs do not include replacement power.

     0    Sludge disposal costs were adjusted to reflect the
          costs of SC>2 scrubber sludge disposal only (i.e.,
          not fly ash) and to provide for disposal over the
                               6-2

-------
          anticipated lifetime of the FGD system.  This
          latter correction was necessary since several
          utilities reported costs for demonstration sludge
          disposal systems that would last only a fraction
          of the FGD system life.

     0    Regeneration facility and acid or sulfur recovery
          facility costs were added for those regenerable
          systems not reporting such costs.

     To the extent possible, all cost adjustments were made

using the cost breakdown data provided on the questionnaire.

Where such data were inadequate, costs adjustments were made

based upon system design parameters.  In some cases, no

adjustments were possible because of insufficient data while

in others, no adjustments were warranted because of the

unique conditions of the system  (e.g., demonstration unit

with funds included for experimentation).

     The adjusted costs for all systems with sufficient data

(30 systems), ranged from 50 to 205 $/KW with an average of

$91/KW (a = 33.90).  Both the upper end of the range and the

average costs are high because of an exceptionally high cost

reported by the New England Power Company for a prototype

FGD system; the utility stated that their reported values

should be considered "upper limits."  Excluding the costs

reported by New England Power Company, the costs range from

50 to 137 $/KW with an average value of $85/KW.  Adjusted

costs for lime and limestone based systems reported by

nineteen utilities ranged from 50 to $88/KW with an average

of $70/KW  (a = 9.48).  These adjusted costs are in sub-

stantial agreement with those developed using the model

plant approach.
                              6-3

-------
     The values reported by the individual facilities, the



factors considered in making the cost adjustments, and the



adjusted costs are presented in Table 6.1.  Details of the



cost adjustments for the individual plants are presented in



Appendix G.
                               6-4

-------
                                        Table 6.1   UTILITY INDUSTRY RESULTS
Company
Plant
Location
Alabama Electric Cooperative
Tombigbee Units 2 & 3
Jackson, Alabama
Process - Limestone
Status - Under Consideration
Start-up Date: 3/78, 1/79
Allegheny Power Service Corp.
Pleasants Power Station Units 1 & 2
Willow Island, West Virginia
Process - Lime
Status - Under Consideration
Start-up Date: 8/78, 8/79
Arizona Public Service Company
Choi la Unit 1
Joseph City, Arizona
Process - Limestone
Status - Operational
Start-up Date: 12/73
Boston Edison Company
Mystic Station
Charlestown, Massachusetts
Process - Magnesium Oxide
Status - Operational
Start-up Date: 4/72
Central Illinois Public Service Co.
Newton Station Unit 1
Newton, Illinois
Process - Lime/Limestone
Status - Evaluating Bids
Start-up Date: 12/77
Capacity
MW
357
510
1236
1236
59:9
119.8
150
150
600
600
Reported Costs
Caoital
$ Millions
40.464 .
(1975)

6.55
5.01
(Actual
Costs)

$/KW
113.34

109.35
33.4


Comments
1. Deleted costs for particulate control
1 . No costs available
1. Adjusted costs from 1973 to 1975
2. Deleted costs for particulate control
3. Adjusted pond life and costs from
2 years to 22 years
4. Added limestone preparation and
sludge disposal costs
5. Considered costs for system representa-
tive for treating full 119.8 MW;
only difference between the modules is
that module B is not packed
1. Added regeneration system costs
2. Added reheat costs
3. Added acid plant costs
4. Increased costs from demonstration
unit to permanent installation
1. No costs available; bids being
evaluated
1975 Adjusted Costs
Capital
£ Millions
29.047

7.036
17.005

$/KW
81.36

58.73
113.37

I
Ol
          a Top number Is the F6D system capacity; bottom number 1s the total capacity of the units to which the FGO system 1s applied.

-------
Table 6.1 (continued).  UTILITY INDUSTRY RESULTS
Company
Plant
Location
Cincinnati Gas & Electric Company
Miami Fort Station Unit 8
North Bend, Ohio
Process - Lime
Status - Planned
Start-up Date: 1/78
Columbus & Southern Ohio Electric Co.
Conesville Generating Station
Units 5 & 6
Conesville, Ohio
Process - Lime
Status - Under Construction
Start-up Date: 5/75, 5/76
Dallas Power & Light Company
Texas Electric Service Co.
Texas Power & Light Co.
Martin Lake Steam Electric
Station Units 1, 2, 3, & 4
Rusk County, Texas
Process - Limestone
Status - Under Construction
or Planned
Start-up Date: 2/77, 8/77,
12/76, 12/79
Dallas Power & Light Company
Texas Electric Service Co.
Texas Power & Light Co.
Monticello Steam Electric
Station Unit 3
Titus County, Texas
Process - Limestone
Status - Planned
Start-up Date: 12/78
Capacity
MW
500
500
822
822
1500 (1 & 2)
1500
750
750
Reported Costs
Capital
$ Millions
40.702
(1978)
38.661
(1975)
50.436
(1974)

$/KW
81.40
47.03
33.62


Comments
1. Adjusted costs from 1978 to 1975
2. Added sludge disposal and trans-
portation costs
3. Deleted replacement capacity cost
1. Added indirect costs
2. Deleted costs for particulate control
3. Adjusted pond life and costs from
5 years to 33 years.
1. Adjusted costs from 1977 to 1975
2. Deleted costs for particulate control
3. Added indirect costs
4. Adjusted pond life and costs from
' 7 years to 35 years
5. Costs are identical for Unit 2;
costs given for Units 3 & 4 were
incomplete
6. 1500 MW of capacity
1. Costs given were incomplete
1975 Adjusted Costs
T.;»pif;»l
$ Millions
36.616
61.563
75.082

$/KW
73.23
74.89
50.12


-------
Table 6.1 (continued).  UTILITY  INDUSTRY  RESULTS
Company
Plant
Location
Detroit Edison Company
St. Clair Power Plant Unit 6
Belle River, Michigan
Process - Limestone
Status - Under Construction
Start-up Date: 5/75
Detroit Edison Company
Monroe Units 1 , 2, 3, & 4
Monroe County, Michigan
Process - Limestone
Status - Under Construction
Start-up Date: 1981
Duquesne Light Company
Frank R. Phillips Station
Units 1, 2, 3, 4, 5, & 6
Wireton, Pennsylvania
Process - Lime
Status - Operational
Start-up Date: 1973
General Public Utilities Service
Corp. (Penna. Electric Co. & N.Y.
State Electric & Gas Company)
Homer City Station Unit 3
Homer City, Pennsylvania
Process - Lime
Status - Planned
Start-up Date: 10/77
Illinois Power Company
Wood River Unit 1
East Alton, Illinois
Process - Catalytic Oxidation
Status - Operational
Start-up Date: 8/74
Capacity3
MW
170
325
3000
3000
138.3
414.9
650
650
103
103
Reported Costs
Capital
$ Millions
13.088
(1975)
344.0
(1981)
32.346
(1974)
60.192
(1977)
8.2957
(1975)
$/KW
80.54
114.67
77.96
92.60
80.54
Comments
1. Increased costs from test module to -
permanent installation
2. Deleted costs for particulate control
3. Adjusted pond life and costs from
1 year to 20 years
4. Added limestone preparation costs
1. Adjusted costs from 1981 to 1975
2. Detailed cost breakdown was not
available
1. Adjusted costs from 1974 to 1975
2. Deleted costs for particulate control
3. Adjusted pond life and costs from
3 years to 20 years
1. Adjusted costs from 1977 to 1975
2. Decreased costs for 25% system redun-
dancy
3. Added interest costs
4. Added contingency and start-up costs
5. Deleted replacement power costs
1. Adjusted costs from 1970 to 1975
2. Added interest costs
3. Electrostatic precipitator costs
allowed since the system requires
essentially ash free flue gas
1975 Adjusted Costs
Capital
$ Millions
13.693
262.6
10.456
47.750
10.649
$/KW
80.55
87.53
75.60
73.46
103.39

-------
                       Table 6.1 (continued).   UTILITY INDUSTRY RESULTS
Company
Plant
Location
Indianapolis Power & Light Co.
Petersburg Generating Station
Unit 3
Petersburg, Indiana
Process - Limestone
Status - Planned
Start-up Date: 4/77
Kansas Power & Light Co.
Lawrence 4 & 5
Lawrence, Kansas
Process - Limestone Injection
Status - Operational
Start-up Date: 1/68, 6/71
Kentucky Utilities Company
Green River Power Station
Units 1, 2, S 3
Central City, Kentucky
Process - Lime
Status - Under Construction
Start-up Date: 5/75
Montana Power Company
Col strip Units 1 & 2
Col strip, Montana
Process - Lime
Status - Under Construction
Start-up Date: 7/75, 5/76
New England Power Company
Brayton Point Unit 1
Somerset, Massachusetts
Process - Metal Oxide
Status - Under Construction
Start-up Date: 1/77
Capaci ty
MM
532
532
525
525
60
60
716
716
75
250
Reported Costs
Capital
$ Millions
32.856
(1974)

3.966
(1975)
65.266
(1975)
14.811
(1975)
$/KW
61.76

66.10
91.15
197.48
1
Comments
1. Adjusted costs from 1974 to 1975
2. Deleted costs for particulate control
3. Increased contingency
4. Added sludge disposal costs
1 . No costs available
1. Turnkey contract costs reported
2. Insufficient cost breakdown to
permit cost adjustments
1. Deleted costs for particulate control
2. Added sludge disposal costs - pond
and equipment.
1. Added start-up costs
2. Demonstration unit; costs not
representative of full scale system
1975 Adjusted Costs
Capital
$ Millions
39.120

3.966
51.990
15.341
$/KW
73.53

66.10
72.61
204.55
I
•3

-------
                        Table 6.1 (continued).  UTILITY INDUSTRY  RESULTS
Company
Plant
Location
New England Power Company
Brayton Point Unit 3
Somerset, Massachusetts
Process - Metal Oxide
Status - Under Construction
Start-up Date:
Northern Indiana Public Service Co.
Dean H. Mitchell Plant Unit 11
Gary, Indiana
Process - Wellman-Lord
Status - Under Construction
Start-up Date: 12/75
Northern States Power Company
Sherburne County Generating Plant
Units 1 & 2
Becker, Minnesota
Process - Limestone
Status - Under Construction
Start-up Date: 5/76, 5/77
Ohio Edison Company
Bruce Mansfield Plant Units 1 & 2
Shippingport, Pennsylvania
Process - Lime
Status - Under Construction
Start-up Date: 12/75, 4/77
Philadelphia Electric Company
Eddystone Generating Station Unit 1
Chester, Pennsylvania
Process - Magnesium Oxide
Status - Under Construction
Start-up Date: 6/75
Capacity3
MW
654
654
115
115
1360
1360
1834
1834
103.3
325
Reported Costs
Capital
$ Millions
95.0
(1975)
13.441
(1975)
60.0
(1975)
213.2
(1977)
20.189
$/KW
145.26
116.88
44.12
116.25
186.42
Comments
1. Added start-up costs
2. Utility states that these costs
reported should be considered the
upper limit
1. Wellman-Lord system with Allied
Sulfur recovery process
2. Insufficient cost breakdown to
permit cost adjustments.
1. Added indirect costs
2. Decreased costs for 9% system redundancy
3. Adjusted pond life and costs from
12 years to 30 years
4. Increased sludge disposal costs
5. Available cost breakdown insufficient
to permit proper adjustments
1. Adjusted costs from 1977 to 1975
2. Deleted costs for particulate removal
3. Decreased costs to remove approximately
20% system redundancy
4. Reduced pond cost to account for S02
control only. Original pond & sludge
transport treatment system cost was 42%
of total direct capital cost compared
to typically reported values of 10-15%
1. Adjusted costs from 1972 to 1975
2. Deleted costs for particulate removal
3. Added interest
4. Added acid plant & ancillaries
1975 Adjusted Costs
Capit 1
$ Millions
98.4
13.441
95.689
142.599
14.837
$/KW
150.46
116.88
70.36
77.81
137.00
I
10

-------
                       Table 6.1  (continued).  UTILITY  INDUSTRY RESULTS
Company
Plant
Location
Potomac Electric Power Company
Dickerson Unit 3
Dickerson, Maryland
Process - Magnesium Oxide
Status - Operational
Start-up Date: 9/73
Public Service of New Mexico
San Juan Station Unit 1
Waterflow, New Mexico
Process - Wellman-Lord
Status - Planned
Start-up Date: 12/76
Public Service of New Mexico
San Juan Station Unit 2
Waterflow, New Mexico
Process - Wellman-Lord
Status - Planned
Start-up Date: 6/77
Public Service of New Mexico
San Juan Station Unit 3
Waterflow, New Mexico
Process - Wellman-Lord
Status - Under Consideration
Start-up Date: 5/78
Public Service of New Mexico
San Juan Station Unit 4
Waterflow, New Mexico
Process - Wellman-Lord
Status - Under Consideration
Start-up Date: 5/80
Capacity3
MW
95
184 .
350
350
350
350
550
550
550
550
Reported Costs
Caoital
$ Millions
6.500
(1973)
44.755
(1974)
44.755
(1974)
59.199
(1974)
71.137
(1980)
$/KW
68.42
127.87
127.87
107.63
129.34

Comments
1. Adjusted costs from test module to
permanent installation
2. Adjusted costs from 1973 to 1975
3. Added interest costs
4. Added regeneration and acid plant costs
1. Adjusted costs from 1976 to 1975
2. Decreased costs for 33% system
redundancy
3. Deleted particulate removal costs
4. Chemical plant 100% oversized: no cost
adjustment made
1. Adjusted costs from 1977 to 1975
2. Decreased costs from 33% system
redundancy
3. Deleted particulate removal costs
4. Chemical plant 100% oversized; no cost
adjustment made
1. Adjusted costs from 1978 to 1975
2. Decreased costs for 25% system
redundancy
3. Deleted particulate removal costs
4. Chemical plant 100% oversized; no cost
adjustment made
1. Adjusted costs from 1980 to 1975
2. Decreased costs for 25% system
redundancy
3. Deleted particulate removal costs
4. Chemical plant 100% oversized; no cost
adjustment made
1975 Adjusted Costs
Capital
$ Millions
13.68
39.348
39.348
52.431
52.431
$/KW
144.00
112.42
112.42
95.33
95.33
a\
I

-------
                        Table 6.1 (continued).  UTILITY INDUSTRY  RESULTS
Company
Plant
Location
Salt River Project
Navajo Generating Station
Units 1, 2 & 3
Process - Lime/Limestone
Status - Under Construction
Start-up Date:
South Carolina Public Service Auth.
Winyah Generating Station Unit 2
Georgetown, South Carolina
Process - Limestone
Status - Planned
Start-up Date: 5/77
South Mississippi Elec. Power Ass.
R. D. Morrow Sr. Generating Plant
Purvis, Mississippi
Process - Limestone
Status - Planned
Start-up Date: 6/77
Southern California Edison Company
Mohave Generating Station Unit 2
South Point, Nevada
Process - Lime
Status - Operational
Start-up Date: 1/74
Southern California Edison Company
Mohave Generating Station Unit 1
South Point, Nevada
Process - Limestone
Status - Operational
Start-up Date: 10/74
Southern California Edison Company
Highgrove Generating Station
Col ton, California
Process - Lime,
Status - Operational
Start-up Date: 1/73
Capacity3
MM
2250
2250
140
280
275.28
444
169.85
790
169.85
790
10
45
Reported Costs
Caoital
$ Millions

6.819
(1975)

7.80
(1975)
17.1
(10/74)
0.400
(1973)
$/KW

48.71

45.92
100.68
40.00
Comments
1 . No costs available
1. Deleted costs for particulate removal
2. Added interest costs
3. Added sludge disposal costs
4. Added utilities & services costs
1 . No costs available
1. Demonstration program. Unable to
separate costs or make accurate cost
adjustments
1. Demonstration program. Unable to
separate costs or make accurate cost
adjustments
1. Demonstration program. Unable to
separate costs or make accurate cost
adjustments
1975 Adjusted Costs
Capital
$ Mill ions
'
7.756

"
'

$/KW
'•
55.40

'
'

(Ti
I
H
H

-------
                       Table 6.1  (continued).  UTILITY  INDUSTRY RESULTS
Company
Plant
Location
Southern California Edison Company
Mohave Generating Station Units 1 & 2
South Point, Nevada
Process - Lime
Status - Planned
Start-up Date: 6/77
Southern California Edison Company
Kaiparowits Generating Station
Units 1, 2, 3 & 4
Page, Arizona
Process - Lime
Status - Under Consideration
Start-up Date: 1980
Tennessee Valley Authority
Widows Creek Steam Plant Unit 8
Stevenson, Alabama
Process - Limestone
Status - Under Construction
Start-up Date: 2/77
Virginia Electric & Power Company
Mt. Storm
Mt. Storm, Virginia
Process - Limestone
Status - Under Construction
Start-up Date: 12/77
Capacity
MW
1580
1580
3000
3000
550
550
1147.11
1662.48
Reported Costs
Caoital
$ Millions
129.0
(1977)
300
(1980)
55.636
(1977)
85.739
(1978)
$/KW
81.65
100.00
101.16
74.74
Comments
1. Adjusted costs from 1977 to 1975
2. Deleted costs for particulate removal
3. Decreased costs for 25% system
redundancy
4. Added sludqe pond costs
5. Adjusted sludge disposal costs
1. Adjusted costs from 1980 to 1975
2. No cost breakdown available to
permit proper adjustments
1. Adjusted costs from 1977 to 1975
2. Deleted costs for particulate removal
3. Increased sludge disposal costs
1. Adjusted costs from 1977 to 1975
2. Increased indirect costs
3. Added sludge disposal costs for S02
disposal for 23 years
4. Deleted coal refuse from sludge
disposal costs
1975 Adjusted Costs
Caoital
$ Millions
94.891
189.05
37.681
84.873
$/KW
60.06
63.02
68.51
73.99
CTl
I
M
M

-------
                  APPENDIX A




SLUDGE FROM FLUE GAS DESULFURIZATION SYSTEMS




                  AN OVERVIEW
                       A-l

-------
                         APPENDIX A

       SLUDGE FROM FLUE GAS DESULFURIZATION SYSTEMS -

                         AN OVERVIEW


     Sludge disposal is the major potential environmental

impact associated with flue gas desulfurization systems.

Sludge is produced, however, only by nonregenerable FGD

processes.  This brief overview describes the quantities of

sludge produced, sludge properties and their environmental

impacts, disposal methods to reduce the environmental

impacts, and the costs of environmentally acceptable sludge

disposal methods.

SLUDGE GENERATION RATES

     A 1000-megawatt coal-fired power plant would produce

approximately 345,000 tons per year (dry basis) of sludge.

The same plant would produce approximately 307,000 tons per

year (dry basis) of coal ash (3% sulfur, 12% ash).  The

following figures may provide perspective from which to view

the sludge disposal issue.   The amount of sludge generated

by controlling 35 percent of the coal-fired power plant

generating capacity in Ohio would be 8.5 million metric tons

(dry basis) annually by 1978.  By comparison:
  Adapted from: Disposal of Lime/Limestone Sludges.  Radian
  Corporation.  Prepared for the U.S. Environmental Protection
  Agency, Research Triangle Park, North Carolina, under Con-
  tract No. 68-02-0046, Task No. 12.  September 1973.
                              A-2

-------
     0    36 million tons of phosphate rock slime from
          fertilizer manufacture were disposed of by ponding
          in 1967;

     0    25 million tons of gypsum from fertilizer manu-
          facture were disposed of in 1973 by ponding and
          surface piles;

     0    18 million tons of Ohio municipal refuse were
          disposed of in 1973 by landfill and incineration;

     0    10 million tons of fly ash from Ohio power plants
          were disposed of by ponding and landfilling in
          1973.

Thus, in terms of quantity, the estimated production of

sludge from Ohio's scrubbers in 1978 would present a dis-

posal problem similar to that of the current disposal of fly

ash.  In terms of weight, the present disposal of phosphate

rock slime and gypsum from fertilizer manufacturing in

Florida alone presents a problem 4 to 6 times that of dis-

posal of scrubber sludge in Ohio.

     Approximately 25 acres is required per 100 MW of plant

capacity to dispose of the scrubber sludges generated over

the 30-year period of life of a power plant (assuming 30-

foot depth).  This requirement is approximately equivalent

to the total area occupied by the power plant proper.  On a

broader basis, as indicated in Table A.I, it is approxi-

mately one percent of the total area required for power

production  (i.e., land for mining, transportation, power
                                2
plant siting, fly ash disposal).
2
  Environmentally Acceptable Disposal of Flue Gas Desul-
  furization Sludges: The EPA Research and Development
  Program.  J. W. Jones presented at the Symposium on
  Flue Gas Desulfurization, Atlanta, Georgia, November
  1974.

                               A-3

-------
                     Table A-l.   COMPARATIVE ANNUAL LAND AND SOLID  WASTE IMPACT OF 1,000 MW
                                     ELECTRIC ENERGY SYSTEM  (0.75  LOAD FACTOR)

Land Affected,
acres"
Solid Waste
Produced ,
short tons
En vi r onme nt al
Impact
Typical Tech-
nique (s) Avail-
able to
Minimize
Impact
Mining (Coal)
Deep
9,120
9~,141 (wet,
97% solids)
(101,3^6
with acid
drainage
sludge)
l) potential
land degra-
dation due
to subsi-
dence; 2)acic
mine drainage
water pollu-
tion problem;
l)no well
developed
cost-effec-
tive tech-
nology to
control sub-
sidence;
2)neutraliza-
tion of mine
drainage
with lime
Surface
1U.010
2,762,000 (wet,
98% solids)
(2,762,328
with acid
drainage
sludge)
1) mined land
made barren
precluding
wildlife
habitat ,
recreation
and most
other uses;
2)acid mine
drainage
water pollu-
tior. problems
1) intensive
land recla-
mation can
restore most
strip-mined
land;2) neu-
tralization
of mine drair
with lime
Processing
161
1»5^,092 (wet,
59% solids)
1 ) culm piles;
2) water pollu-
tion: a) acid
drainage ;
b)siltation;
3)air pollu-
tion: a)Dts-
charges S02, CO
&HpS; b)potentia
spontaneous com-
bustion
compacting in
holes, mines,
quarries, etc.
age
Transport
2,213
0
use of land for
railroad beds
1
N/A

Conversion
(plant site)
350
0
use of land for
power plant site
N/A

Limestone FGD
System
Untreated
Ponded Sludge
367
(30 ft. deoth)
l,UUo,000 (wet,
50% solids)
l) potential
groundwater
pollution
problems;
2)land poten-
tially made
useless if
sludge not
treated or
permanently
•lewatered
l) although
reclamation is
feasible, no
well developed,
cost-effective
technology has
been demonstrat
2) sound pond ma
ment, use of im
able pond
liner and opera
of FGD system i
closed-loop mod
n-ir.imize water
ponding, chemic
to have potenti
and land reclarn
Transmission
17,188
0
use of land for
transmission
line right of
way
N/A
Totals
Deep
29,399
1,991,233
N/A
N/A
Surface
34,289
14,656,092
N/A
H/A
ed;
nage-
perme-
tion
n
e can
pollution. (As an alternative to
al fixation with landfill appears
al for solving both water pollution
aticn problems . )
>

-------
Variables Affecting Sludge Quantities



     The amount of sludge generated by a given plant is a



function of the sulfur and ash contents of the coal, coal



usage, load factor, mole ratio of scrubbing additive, SO-



removal efficiency, composition of the sludge, and moisture



content of the sludge.



     Limestone scrubbing processes ordinarily produce sludge



containing CaSO -1/2 H_0, CaSCK •2 H-O, and CaCO .  For coal-



fired installations where efficient particulate removal is



not installed upstream of the wet scrubber, such sludges can



contain large quantities of coal ash.



     Variations in state emission regulations cause sulfur



dioxide removal efficiency to vary from one flue gas desul-



furization system to the next.  Removal efficiencies of in-



stalled units vary from approximately 60% to 80%.  Sludge



production is a direct function of the pounds of sulfur



dioxide removed.



     Since unreacted limestone is disposed of with the



sludge, the stoichiometric ratio of limestone addition



(CaCO3/SO2 mole ratio) influences the amount of sludge



generated.  The stoichiometric ratio varies from system to



system but is generally in the range of 1.0 to 1.5 Ib moles



of limestone per Ib mole of S02 removed.



     The sulfite to sulfate ratio in the sludge effects the



weight of sludge product since CaSO.*2 H20 is heavier than



CaSO^'1/2 H20.  Various FGD systems have sludges of almost
                              A-5

-------
 100%  sulfite while  other  systems  have  100%  sulfate  sludge.



 Few if  any, plants  directly  control  the  sulfite  to  sulfate



 ratio.  Table A.2 illustrates  the variations  in  the quan-



 tities  of  sludge produced for  existing facilities with their



 differing  sulfite/sulfate ratios  and stoichiometric ratios.






  Table A.2  SLUDGE PRODUCTION AT CURRENT FGD INSTALLATIONS



        Sludge Produced  -  Dry Basis (excludes  fly ash)
Plant
Lawrence 4 and 5
Hawthorn 3-
Hawthorn 4
Will County
Stock Island
La Cygne
Cholla
Paddy 'a Run
Mohave
CaS03-l/2 H20
Ibs/lb S02
removed
0.510
1.046
1.007
1.648
1.702
1.577
1.011
1.968
0.041
CaS04'2 H20
Ibs/lb S02
removed
1.574
1.308
1.362
0.494
0.425
0.591
1.348
0.056
2.654
CaC03
Ib/lb SO2
removed
0.254
0.262
0.888
0.659
6.298
1.183
0.000
0.000
0.000
Total
Ibs/lb S02
removed
2.338
2.616
3.257
2.801
8.425
3.351
2.359
2.024
3.064
     Table A.3 illustrates the typical quantities of sludge



produced by an FGD system on a 1000 MW plant for both the



lime and limestone systems for two different sulfur content



coals.



SLUDGE PROPERTIES/ENVIRONMENTAL IMPACTS



     The environmental impacts of sludge disposal are



dictated by its chemical and physical characteristics.



These characteristics vary considerably depending upon such



factors as coal chemistry including its sulfur content,
                              A-6

-------
        Table A.3  SLUDGE GENERATION - 1000 MW PLANT
Sludge generation
rate
Stoichiometric
ratio
TONS/HR
Dry
60% Solids
50% Solids
With flyash
45% ash/60% solids
65% ash/60% solids
TONS/YR (thousands)
Dry
60% Solids
50% Solids
With flyash
45% ash/60% solids
65% ash/60% solids
TONS/YR/KW
Dry
60% Solids
50% Solids
With flyash
45% ash/60% solids
65% ash/60% solids
High Sulfur, 3.5%
Lime
1.1


39.5
65.9
89.1

119.9
188.3

208
346
415

630
989

0.208
0.346
0.415

0.630
0.989
Limestone
1.3


61.3
102.2
122.6

185.8
291.9

322
537
644

976
1533

0.322
0.537
0.644

0.976
1.533
Low Sulfur 0.6%
Lime
1.1


10.1
16.9
20.2

30.7
48.3

53
89
107

163
255

0.053
0.089
0.107

0.163
0.255
Limestone
1.3


15.7
26.2
31.4

47.6
74.8

83
138
166

252
395

0.083
0.138
0.166

0.252
0.395
Notes:

High sulfur coal meets a 1.2 MM/BTU emission regulation.
Low sulfur coal meets a 0.15 MM/BTU emission regulation.
Capacity factor is 60%.
Limestone system produces 3.14 Ibs dry sludge/lb S02
  removed.
Lime system produces 2.01 Ibs dry sludge/lb S02 removed.
Ash percentages refer to the ash percent by weight of the
  dry solids in the sludge/fly ash mixture.
                              A-7

-------
reactant and system water chemistry, scrubber operating

conditions, ash content, and sludge pH.  A sludge's chemical

properties have the greatest potential for impacting directly

on the environment.  The physical properties of untreated

sludges may make land reclamation impossible.

     Important chemically related sludge characteristics

which could impact on the environment include:

     0    Soluble toxic compounds and elements.

     0    Chemical oxygen demand.

     0    High total dissolved solids.

     0    High levels of compounds or elements not generally
          thought to be toxic.

     0    High suspended solids.

     Physical properties of sludges also vary widely.  These

properties must be considered in the design of the scrubbing

system since they determine the difficulty in handling,

transporting, and treating the sludge.  Scrubber sludges can

be thixotropic in nature, have poor load bearing character-

istics, and retain water.  The sulfite concentration in the

sludge determines its physical properties.  High sulfite

sludges have low bearing strength and rewater readily.

     Tests for comparing physical properties of sludges

include: particle size measurements, the total surface area

of dry solids (Elaine Index), viscosity, bulk density, gel

strength, shrinkage, penetration, and compression.
                              A-8

-------
Environmental Impact



     The disposal of scrubber sludges entails potential



pollution of land, air, and water.  Surface waters such as



rivers, streams, lakes, and ponds can be contaminated by



leaching and percolation of sludge liquor into the ground-



water through soil and sludge storage areas.  Large areas of



land could deteriorate from the storage of amounts of



sludge materials that typically contain 50 to 75 percent



water.  This land could be made useless by the nonsettling



characteristics of untreated sludge.



     Leachates and runoffs from scrubber sludges pose poten-



tial water pollution problems.  Trace elements in these



leachates may exceed the standards for drinking water.



Although these elements are present in ash pond overflows



they are more concentrated in sludge liquors.  The chemical



oxygen demand is higher due to the large quantities of



sulfites.  Excess dissolved solids are also a problem.



Since it may take years to detect contamination in ground-



water (and years for it to dissipate) contamination must be



avoided.  In the past, other types of pond effluent overflow



into receiving streams was permitted with little treatment



beyond neutralization, skimming, and settling.  New reg-



ulations will likely reduce or eliminate this practice.  The



use of closed loop (no discharge into a receiving body) will



be required for scrubbing systems.
                              A-9

-------
     Air pollution by scrubber sludges may be a problem if



the materials can not support vegetation.  A barren sludge



pond could be a potential source of fugitive dust emissions.



At present, no attempts have been made to reclaim sludge



disposal areas.  The tendency of untreated dried sludge to



rewater and its. limited load bearing strengths are major



drawbacks in land reclaimation.



SLUDGE DISPOSAL AND TREATMENT METHODS



     Several methods are now used for disposal of scrubber



sludge.  The most common are ponding of untreated sludge and



landfilling of treated and untreated sludge.  An alternative



to disposing of scrubber sludge is commercial utilization.



This technique is practiced extensively in Japan, where



scrubber sludges are oxidized to form the long fiber gypsum



necessary for wallboard production.  Although such tech-



niques could be applicable in the United States if the



economic incentives were adequate, at best they would



account for only a minor fraction of sludge requiring



disposal.



Ponding



     Sludge disposal in a pond without providing environ-



mental protection (such as chemical fixation or impervious



liners) against seepage to water supplies constitutes a



potential water quality hazard.  The degree of hazard depend



upon such site specific characteristics as topography,



weather, soil characteristics, and proximity of ground and
                              A-10

-------
surface waters to the disposal site.  In addition, there



exist a significant number of other disposal variables



(e.g., chemical constituents of the sludge and the condition



of sludge disposal) that may impact the potential hazard



posed by such a sludge pond.



     Pond linings have been finding greater favor in recent



years.  Lining is an effective method to prevent groundwater



contamination.  On many areas, clay, concrete, wood or metal



have been used as liners.  Synthetic materials are finding



increased use.  These synthetic materials include polyvinyl



chloride, rubber, synthetic rubber, polyethylene, propylene,



and nylon.  Since economics is a major factor, clay and



synthetics will be the primary materials used for sludge



liners.  To be useful, liners must have long-life, endured-



temperature variations, and remain flexible.  Several manu-



facturers are offering acceptable liner materials.



Landfilling



     The second method for disposal of scrubber sludges is



use of either a dewatered or a stablilized  ("fixed") sludge



for landfill.  Sludges can be dewatered by vacuum filtration



or centrifugation to form a solid material that can be used



for landfill.  Since these dewatered sludges can reabsorb



moisture and regain their original water content if un-



treated, chemical and physical stabilization or fixation



processes are increasingly being used.
                              A-ll

-------
     Chemical fixation of scrubber sludge is currently

offered by several commercial groups including Dravo Corpo-

ration, I.U.C.S., Inc., Chicago Fly Ash, and The Chemfix

Corporation.  These commercial systems use fly ash, lime,

silicates, and polyvalent metal ions (usually about 5 per-

cent of the amount of sludge on a dry weight basis) to form

a low-grade concrete.  The product is a stable, inert mate-

rial that will not release toxic metal ions or soluble

species.  It has sufficient strength to support buildings

and will support vegetation.  Table A.4 presents data on the

leachate rate bearing data for chemically stabilized sludges.

Chemical fixation processes and landfilling represent the

most suitable method for scrubber sludge disposal.

Table A.4  COMPARISON OF TRACE ELEMENTS ANALYSES BETWEEN RAW

     SLUDGE AND LEACHATE FROM THAT SLUDGE AFTER CHEMICAL

                  CONDITIONING BY FIXATION3


Constituents

Arsenic (As)
Cadmium (Cd)
Chlorides (Cl~)
Total chromium (Cr)
Copper (Cu)
Iron (Fe)
Lead (Pb)
Mercury (Hg)
Nickel (Ni)
Zinc (Zn)
Phenol (C6H5OH)
Cyanide (CN~)
Sulfate (S04~)
TVA Shawnee
TCA limestone
raw sludge
(ppm)
2.2
0.30
2,000
2.8
1.5
120
26
<0.10
3.5
16
<0.25
<0.10
>10,000

Leachate water from
conditioned sludge
(ppm)
<0.10
<0.10
64
<0.25
<0.10
<0.10
<0.10
<0.10
<0.10
<0.10
<0.10
<0.10
400
  Disposal of Byproducts from Nonregenerable Flue Gas De-
  sulfurization Systems.  Aerospace Corporation, El Segundo,
  California.  Prepared for the U.S. Environmental Protection
  Agency.  Research Triangle Park, North Carolina under
  Contract No. 68-02-1010.  May 1974.

                             A-12'

-------
DISPOSAL COSTS

     The following factors affect the capital and annualized

operating costs of sludge disposal:

     1.   Capital Cost

          a.  Pond location
          b.  Lining requirement
          c.  Leachate monitoring
          d.  Overall size
          e.  Dewatering method

     2.   Annualized Operating Cost

          a.  Fixation chemicals
          b.  Utilities
          c.  Trucking

The split between capital and annual costs is not clearcut.

For example, several firms will operate sludge disposal

systems on a per ton basis.  The utility will not be re-

quiredxto invest capital in the system.  However, these

contracts normally have "take or pay" clauses to protect the

sludge disposal firm's capital investment.  In essence, turn

key disposal merely shifts the fixed charges of sludge

disposal to direct operating expenses.  In addition, pumping

sludge instead of trucking sludge increases capital but

reduces annual costs.  Sluice lines and pumps are part of

the capital costs borne by utility, while trucks to haul

sludge are normally borne by trucking contractors.  Another

area which affects capital and annualized operating costs is

dewatering.  Horsepower requirements are reduced if ponding

is used to dewater sludge instead of vacuum filtration or

centrifugation.  Capital costs increase however, since the

pond must be larger and more complicated.
                              A-13

-------
     Table A.5 depicts the disposal costs for the 250, 500

and 1000 MW model plants used in this study.  Capital costs

include clarification, vacuum filtration, chemical fixation,

and a clay lined pond with a life equal to the remaining

plant life.  Annualized costs include fixation chemicals,

utilities, operating labor, supervision, maintenance,

supplies, overhead, and fixed charges.  Sludge is disposed

of on-site and there are no trucking charges.

     Table A.6 identifies the annualized cost impact of

various subset conditions for sludge disposal for a new 500

MW plant burning high sulfur coal.


 Table A.6  IMPACT OF VARIOUS SUBSET SLUDGE DISPOSAL OPTIONS

          ON THE ANNUALIZED COST OF SLUDGE DISPOSAL3

Base Case
Synthetic Lining
Fixation
Trucking - 5 miles
Trucking - 10 miles
Trucking - 15 miles
Pumping - 5 miles
Pumping - 10 miles
Pumping - 15 miles
Retrofit
Low Sulfur
Mills/KWH
0.463
0.451
0.204
1.023
2.046
3.069
0.224
0.336
0.448
(0.040)b
(0.337)
$/Dry Ton
7.54
7.35
3.32
16.67
33.33
50.00
3.65
5.47
7.30
(.65)
7.17
$/Wet Ton
4.53
4.41
2.00
10.00
20.00
30.00
2.19
3.28
4.38
(.39)
4.30
  The various costs shown are additive to the "Base Case"
  cost which is an unlined pond without chemical fixation.
  Numbers in parentheses are negative.
                              A-14

-------
                                 Table A.5  SLUDGE  DISPOSAL  COSTS  FOR  THE MODEL PLANTS'

Capital Cost
$/KW
Annualized Cost, mills/KWH
Fixation chemicals
Electricity
Water
Labor
Supervision
Maintenance
Supplies
Overhead:
Plant
Payroll
Fixed costs
Total, mills/KWH
S,.ton, Dry
$/ton, wet
250 MW
3.5% S
Retrofit
11.0
0.216
0.012
0.001
0.014
0.002
0.083
0.013

0.056
0.003
0.425
0.825
12.74
7.64
New
13.3
0.209
0.011
0.001
0.021
0.003
0.101
0.015

0.071
0.005
0.472
0.909
14.50
8.70
0.6% S
Retrofit
6.65
0.055
0.011
0.001
0.010
0.001
0.051
0.008

0.035
0.002
0.258
0.432
25.94
15.57
New
7.70
0.054
0.010
0.001
0.014
0.002
0.058
0.009

0.042
0.003
0.272
0.465
28.83
17.30
500 MW
3.5% S
Retrofit
8.05
0.210
0.011
0.001
0.006
0.001
0.062
0.009

0.039
0.001
0.287
0.627
10.00
6.00
New
8.93
0.204
0.010
0.001
0.008
0.001
0.068
0.010

0.044
0.002
0.319
0.667
10.87
6.52
0.6% S
Retrofit
4.55
0.054
0.010
0.001
0.004
0.001
0.034
0.005

0.021
0.001
0.160
0.291
18.04
10.82
New
5.07
0.053
0.010
0.001
0.005
0.001
0.038
0.006

0.025
0.001
0.179
0.319,
20.22
12.13
1000 MW
3.5% S
Retrofit
6.13
0.204
0.010
0.001
0.004
0.001
0.046
0.007

0.029
0.001
0.216
0.519
8.46
5.08
New
6.13
0.198
0.010
0.001
0.004
0.001
0.046
0.007

0.029
0.001
0.217
0.514
8.66
5.20
0.6% S
Retrofit
3.33
0.053
0.010
0.001
0.002
0.001
0.025
0.004

0.016
0.001
0.119
0.232
14.70
8.82
New
3.33
0.051
0.009
0.001
0.002
0.001
0.025
0.004

0.016
0.001
0.118
0.228
14.95
8.96
l-»
en
      U Capital costs include associated indirect costs.  Indirect costs for the  total FGD system were reported as a separate

        category in Table 3.3.

-------
                  APPENDIX B




PROCEDURE FOR CONVERTING UTILITY INVESTMENT AND




   EXPENSE INTO ANNUAL REVENUE REQUIREMENTS
                       B-l

-------
                      APPENDIX B
 PROCEDURE FOR CONVERTING UTILITY INVESTMENT AND EXPENSE
            INTO ANNUAL REVENUE REQUIREMENTS
Introduction
          This report describes the development of a

procedure for translating utility investment and expense

into annual revenue requirements.  It is based upon the

practices followed by regulatory authorities in the United

States and statute law with respect to income tax and the

deductability of various items of expense in calculating

the amount of such taxes.  The important variations in

methodology between jurisdictions are pointed out.

Typical parameters have been selected to illustrate the

procedure with a quantative example.


Plant Investment

          Plant investment refers to the initial investment

in utility plant having a useful life greater than one year.

No adjustment is made for the effect of regulatory practices

which modify the value of plant for rate making purposes to

take into account the effects of inflation and changes in

technology.  This is not to be inferred as a disparagement

of the fair value approach in determining plant investment.

In the interest of a simplified analysis of alternative

plans, such refinements have been avoided.  This is believed

to be a reasonable approach.  It is doubtful that any

utility planner in a so-called "fair value" rate jurisdiction

includes in a projection of revenue requirements outside the

pale of a rate case, changes in the fair -value of plant
a) Prepared by R.H. Sarikas of Foster Associates under sub-
   contract to PEDCo-Environmental Specialists,
                            B-2

-------
investment through time.  Plant investment is identified



as item P in table V of this report.  That table has been



identified as Table V so as to conform to a similar table



in a report prepared by another organization.





Life Estimates
i"*"*


          The procedure provides for separate estimates of
I


physical, book, and tax life.  While conformity is possible



a framework for alternative calculations wherein these



lives differ is more realistic.  The estimate of physical



and book life are discussed in the  following paragraphs.



The estimate of life for income tax depreciation is discussed



in a later section of the report dealing with the calculation



of the revenue requirement for income taxes.





Physical Life



          Retirement history is not available for flue gas



desulfurization equipment since only a few test installations



are in existence and these have only been installed for a



relatively few years.  The estimated life used in this



report is fifteen years.  It is identified as item Lp in



Table V of this report.  Equipment  for the manufacture of



chemicals and allied products that  is similar in nature



typically is depreciated over a somewhat shorter period.



The selection of a life estimate for that purpose is very



likely influenced by the possibility of plant retirement



due to obsolescence of the particular process.  This



estimate is about one-half of the physical life normally




                             B-3

-------
attributed to a fossil fired steam electric generating

station.


Life for Book Depreciation

          An estimated life of thirty years is used for

book depreciation purposes.  It is identified as item Lfo

in Table V of this report.  This is generally in line with

the life estimate commonly used by utilities to depreciate

fossil fired electric generating plant.   The flue gas de-

sulfurization equipment would normally be depreciated at

the rate applicable to the entire steam production plant
                        /
or the rate specifically applicable to Account 312, Boiler

Plant Equipment.


Construction Time

          A construction time of two years has been assumed

for the flue gas desulfurization equipment.  This is less

than one half of the construction time of a typical fossil

fired power plant.  However, it is believed to be a fair

estimate of the time required for the construction of such

a device.  It is identified as item N in Table V of this

report.


Interest Rate During Construction

          The Interest rate During Construction (IDC) also

identified in current literature as the Allowance for Funds

used During Construction  (AFDC) is normally established at

a rate lower than current debt cost.  While ideally the

figure should be representative of total rate of return on


                             B-4

-------
the utility plant investment,  the lower rate provides some



recognition of the fact that this rate is an after-tax



rate and has no bearing upon the calculation of the amount



of federal income taxes.  The  regulatory justification for



AFDC is that it avoids having  present day rate payers



contribute for cost incurred .to construct plant which will



benefit future rate payers.   This goal is achieved by



capitalizating or adding to the cost of plant the amount



of IDC.  There are, of course, minor exceptions to this



practice in certain regulatory jurisdictions.  This



practice has distorted the operating earnings picture



for a number of electric utilities since a substantial



amount of what is identified as earnings in financial



statments actually is a result of this practice of charging



interest during construction and adding the amount to



reported book earnings.  This  item is identified as ic in



Table V of this report.






Capitalization



          The capital structure is frequently defined in



terms of capitalization ratios, that is the ratio of



debt to total capital, as well as the ratio of preferred



stock to total capital and common equity to total capital.



The choice of these ratios is  determined by factors such



as the times interest earned coverage of debt expense as



well as the coverage ratio with respect to preferred stock



dividends.  The ratio is also dependent upon the degree of



financial leverage desired by the firm.  Coverage ratios





                           B-5

-------
have been lower in recent years as a result of combination



of higher interest rates and reduced equity earnings.   The



maintenance of satisfactory bond ratings are important in



maintaining the ability of a  utility to attract needed



reasonable capital at a reasonable cost.  Suggested



parameters are shown in Table V of this report and are



identified as d, p, and c.  Suggested parameters are 50,



15, and 35% respectively.   Recently available 'figures



for investor owned electric utilities are as shown below:



          Type of Capital           Capitalization Ratio



          Long term debt                 53.7%



          Preferred Stock                11.7



          Common Stock Equity            34.6



          Total Capitalization          100.0%






          The source of this information is Table 55 S of



the Edison  Electric Institute Statistical Yearbook for



1972.  The above figures are in reasonable conformance



with the recommended input parameters, especially when



the need for adequate coverage interest and preferred



dividend ratios are taken into account.  Imbedded rates



are expected to increase in future years as a  result of  a



preponderance of new issues in total debt capitalization.





Interest Rate on Debt



          The interest rate on long term debt  will depend



upon the overall level of interest rates for the entire



economy and also upon the bond rating of the particular






                              B-6

-------
utility.  This latter item is associated with the 'financial

and business risk individual utility.  While the factors

affecting the risk of a particular utility are numerous,

the more significant include coverage ratios or the

amount of earnings in excess of the bond interest.   The

percent of total capitalization that is debt, the type of

customers, (i.e. mix of residential, commercial, and

industrial sales) stability of revenue, particular utility,

regulatory climate and related items.  Recent (November,

1974) yields on public utility issues for the various

bond ratings are shown below:

          Rating                     Interest Percent per
                                    	Annum	
          Aaa                              9.08%

          Aa                               9.51

          A                               10.43

          Baa                             11.39


Source of the yield data is Moody's  Public Utility Manual

and Bond Survey.

          The interest rate on debt  is identified as i^

in Table V of this report.  An input parameter of 10%

has been selected.


Dividend Yield on Pf. Stock

          The dividend yield on preferred stock will depend

upon many of the same factors which  affect the level of

interest rates.  Recent (September,  1974) yields on public

utility issues for the various preferred stock issues are
                             B-7

-------
shown below:



          Rating                    Dividend Yield



          High Grade                    10.34



          Medium Grade                  10.85





          Source of the data is Moody's Preferred Stock



Yields.  While the dividend payment is not deductible



for income tax purposes by the utility, the use of



preferred capitalization aid in providing the interest



coverage.  The attractiveness of such issues to corporate



investors is that utility preferred dividends are partially



deductible for tax purposes.  The interest payments of



the more secure utility bonds are not.  Dividend yield is



identified as rp in Table V of this report.  An input



parameter of 101 has been selected.





Percent Return on Common Equity



          The percentage return on common equity must be



adequate to properly compensate owners of the stock in



line with comparable risk securities in unregulated business.



For a growing utility, and most electric utilities have been



growing at a rate which doubles their electrical load every



decade, this rate of return must be also adequate to attract



capital from new investors.  This is probably the most



significant and argumentative item in any electric rate



case.  It is generally accepted that this rate of return



must exceed the interest rate on debt because of the greater



risk of equity investment.  It must also be comparable to
                             B-8

-------
the equity rate of return earned by comparable risk non-

regulated businesses if the utility is to be able to sell

its common ;>tock issues and raise the requisite amounts

of capital.  Equity rate of return is identified as rc in

Table V of this report.  A rate of return of 151 has been

used as an input parameter.


Income Tax Rate

          The statutory federal income tax rate for a

corporation is a normal tax of 22% with a surtax of 26%

on all taxable income over $25,000.  Since virtually every

utility will have taxable income in excess of $25,000, the

incremental tax rate is the sum of those two components or

48%.  In addition, a number of the states have levied an

income tax on corporations.  The magnitude of the rate

depends upon the particular jurisdiction.  In most

instances, the federal income tax liability is not deduct-

ible for state income tax purposes.  However, in

computing the amount of the federal income tax, state income

tax is always a deductible item.  Assuming a state income

tax of 4% the composite tax rate would be 50% (or more

precisely 50.08%) calculated as follows:

          Composite Tax Rate = f + s - fs =

                             =  0.48  + 0.04  -  0.48  x  0.04  =  50.08%

               where
                           f = Federal income tax rate =48%

                           s = State income tax rate   =  4%


                               B-9

-------
For that reason, an input parameter for this item of 50%



is recommended.  The item is identified as t in Table V



of this report.






Life for Tax Depreciation



          In any individual situation the income tax



depreciation rate is dependent upon the rate actually



approved for the particular utility by the Internal Revenue



Service (IRS).  This, in turn, is based upon figures



published in guidelines issued by IRS and the ability of



the tax payer to demonstrate the justification for any



departure from these guidelines.  This is accomplished by



means of plant life studies using well-known statistical



techniques.  With respect to flue gas desulfurization



equipment, the tax depreciation rate which may be applied



depends in part upon the installation date of the electric



generating station with which it will be associated.  An



agreement between the taxpayer and the IRS with respect



to useful life is made on IRS Form 2271.  It is binding



on both parties and can be modified only upon proof of the



existence of facts or circumstances which were not taken



into consideration when the agreement was made.  Normally,



in the case of a new generating plant, the utility will



depreciate its property under the Class Life Asset



Depreciation Range System (ADR).  This is a system of



broad industry classes of assets.  A tax payer using ADR
                             B-10

-------
does not have to justify his retirement and replacement



policies.  However, the depreciation period selected



cannot be changed during the remaining period of use of



the asset.  All classes of assets have a range of years



called the Asset Depreciation Range that extends 201 above



and below the asset guideline.period.  Presumably the util-



ity would select a life that is the minimum permissible



under ADR.  With respect to electric generating equipment,



the asset guideline period is 28 years, with the lower



limit at 22.5 years.  Thus, if the facility is part of the



power plant, the utility could use a 22.5 year life unless



it could demonstrate to the satisfaction of the IRS that



some other life is more appropriate.



          If the facility is placed in service before 1975,



and is associated with a plant placed in operation before



1969 and remaining life is fifteen years or less the environ-



mental project can be written off over a five year period.



If the remaining life exceeds fifteen years the amount of



the five year write-off is adjusted by the ratio of fifteen



to the remaining life in years.  If the plant is installed



after 1969 the life for tax depreciation is the same as



plant itself.



          A  tax life of 23 years has been selected as an



input parameter.  This is identified as item Lt in Table V



of this report.  The guideline life parameter, required



for normalization and identified as Lg is assumed to be



28 years.





                             B-ll

-------
Operating Expense

          Operating expense includes all expenditures for

labor  and materials having a useful life less than one

year.   Items  includable under  this category are labor

required for  maintenance and operation, plus raw materials

less any credit  for by-products  sold.  This item is

identified  as E  in Table V of  this report.



Land

           Investment  in land is  normally set up in a

separate category when calculating revenue requirements.

For most purposes, land is assumed to be non-depreciable

for book and  income tax purposes.  In other ivords, it is

assumed to  have  infinite life.   In this analysis, separate

.input  parameters are  provided  for the amount of land

required, measured in appropriate units such as square

feet or acres with the unit cost of land measured in  terms

of  the same units.  Total land required is identified as

item q,  the unit cost of land  is identified as  item n in

Table  V of  this  report.



Property Tax  Rate

          Most state  and local jurisdictions levy a

property tax  on  all real estate  and personal property

owned  by the  utility.  This rate is normally not uniform

throughout  the utility's territory but  is dependent upon

the methods used for  appraising  the value of the plant  for
         i
tax purposes  and the  tax levy  which is  in turn  related  to

the tax revenue  needs of the particular jurisdiction.   A


                             B-12

-------
typical input parameter of 1.51 has been included for

this component.   The item is identified as A in Table V

of this report.   For a particular utility it could be

calculated by dividing the amount of such tax paid by

gross plant investment.  Ideally, it should be based upon

an estimate of the tax liability of a particular facility

prepared by the utility's tax department.


Cross Receipts Tax Rate

          Many state and local jurisdictions apply a

public utility tax on the gross receipts of the utility.

This corresponds to a sales tax on other transactions.

As an example, a state may levy a 5% tax on gross receipts.

This means that 5% of the revenues collected are turned

over to the state.  In some jurisdictions, this is not

identified as revenue by a utility, although the tax  is

collected as part of the customer's bill.  Since the

amount to cover expenses and plant related cost must

ultimately be derived from revenues, the revenue require-

ments must be appropriately increased to provide for  this

amount of tax.  As an example, given a public utility tax

of 4°o, the revenue which must be collected to pay $1  of

expense is    1   = $1.0417.  A figure of 4% has been
          (1-0. 04)
selected as an input parameter.  It is identified as  item G

in Table V of this report.
                             B-13

-------
Insurance



          Another plant related cost is the expense of




providing insurance.  The cost of insurance will depend



upon the evaluation of risk by the underwriter.  Usually




a utility has a substantial deductible provision in order



to minimize the premium.  The recommended figure of 0.1%




is typical of generating plant coverage with the exception



of nuclear liability insurance.  This item is identified as



U in Table V of this report.






Percent Return on Rate Base



          Percent return on rate base is calculated by



the general formula shown in the table.  Thus, it depends



upon the various capitalization ratios as well as the



interest rate, preferred dividend yield, and rate of



return on common equity.  For the sample input parameters



the total rate of return is 11.75% calculated as follows:



r = 0.5 x 10 + 0.15 x  10 +  0.35 x 15 = 11.75%.



This is shown as item r in Table V of this report.






Total Land Cost



          Total land cost is merely the product of the



number of units of land required and the unit cost, of the



land.  It is identified as B in Table V of this report.
                              B-14

-------
Working Capital



          Working capital for an electric utility typically



consists of the inventory of maintenance materials and



fuel as well as items such as cash on hand required for



transactions, plus amounts to take into account the lag in the



payment of expense as compared to the receipts of revenues.



With respect to flue gas desulfurization equipment, working



capital would consist primarily of maintenance materials



and the inventory of raw materials used in the process.



A figure of 12.51 of expenses has been suggested as an



input parameter.  This item is identified as W in Table V



of this report.
                            B-15

-------
Start Up Requirements



          Start up expenses refer to labor and maintenance



cost required to obtain satisfactory operation of the



equipment prior to commercial operation.   This amount is



normally capitalized and added to the investment, rather



than being expensed in the year in which it is incurred.



This item may be highly variable depending upon the



difficulties encountered.   A figure of 251 of annual



expenses has been recommended as an input parameter.



This item is identified as S in Table V of this report.





Interest during Construction



          The general formula for IDC assumes that plant



expenditures are uniformly incurred over the construction



period.  It also assumes that IDC is applied only to



plant investment exclusive of land.  The past practice of



many utilities has been to include IDC on land plus plant



investment.  The current trend is to omit land from that



calculation.  If the previous recommendations with respect



to input parameters are accepted, calculated IDC is equal



to 91 of plant investment.  This item is identified as



item I in Table V of this report.





Total Capital Requirement



          The total capital requirement for plant is the



sum of plant investment, IDC, working capital and start-



up cost.  The total capital requirement for land is B.



These two items are identified as Cp  nd C^ in Table V of



this report.





                              B-16

-------
Depreciation Annuity



          The depreciation annuity is the level annual



percentage of depreciable plant,  which when added to



the rate of return on rate base and applied to the plant



investment in each year, will have the same lifetime



present worth revenue requirement as the return on net



plant in each year, plus straight line depreciation.



This latter combination of return and depreciation would



be a non-uniform series.  Straight line depreciation



would be a constant.  However, return on rate base would



decrease each year since rate base is equal to initial



investment less accumulated depreciation.  This latter



figure would increase each year as depreciation charges



are accumulated in the reserve for depreciation.  Use of



rate of return on the rate base,  plus straight line



depreciation would overstate the revenue requirement for



those two cost components in every year except the initial



year of plant life.  Use of the sinking fund annuity in



calculating the depreciation component of levelized



revenue requirements in no way implies the existence of



sinking fund depreciation for book or tax purposes.  The



life use in this calculation is the physical life.  If the



figure is 11.751 is substituted for r and physical life



of 15 years is substituted for Lp in the general formula



shown in Table V, the resulting annuity is 0.027 on a per



unit basis or 2.7% of the total capital requirement for



plant.  Since land is nondepreciable the depreciation
                            B-17

-------
annuity for land is zero.   The item is identified as D in



Table V of this report.





SYD Annuity



          The general formula for the calculation of the



SYD annuity is given in Table V.  This parameter is needed



in the formula for the income tax annuity involving



accelerated depreciation which is subsequently presented.



A tabular calculation of this expression, using the



previously indicated parameters, is provided in Appendix A



to this report.





Income Tax Annuity



          The income tax annuity is shown for three



alternatives, namely, straight line depreciation for book



and tax purposes; straight line depreciation for book



purposes, accelerated depreciation for tax purposes, with



deferred taxes normalized; and straight line depreciation



for book purposes, accelerated depreciation for tax purposes



with flow through of the tax saving.  The composite tax



annuity is applied to capital investment in plant or land



as appropriate in order to compute the revenue requirement



for income taxes.



          A minor discrepancy is incurred when the tax



annuity is applied to total capital investment which



includes interest during construction.
                            B-18

-------
          Such a calculation infers  that  there  is  a revenue



requirement for income tax associated with capitalized



interest during construction.   Actually,  this is not the



case,  since the revenue requirement  for return  and



depreciation on the portion of plant represented by capitalized



interest during construction is excluded  when calculating



income taxes.   Since the present worth of return and



depreciation over one life cycle is  equal to initial



investment, the present worth of interest during construction



added to net income is exactly equal to the present worth



of return and depreciation on the capitalized interest



over one life cycle.  Also since income tax was not paid



on the amount of IDC added to net income, it is inappropriate



to consider tax depreciation as applicable to that component



of plant investment.



          The error introduced by applying the tax annuity



to total plant capital requirement in the general formula



in Table V is minor and will help to offset the error



introduced by not considering the revenue requirement for



interest during construction, which precedes the initial



service date of the plant from which point physical life



and book life is estimated.






Income Tax Annuity-Straight Line




          The general formula for the income tax annuity,



assuming straight line depreciation  for book and tax
                            B-19

-------
depreciation is given in Table V of this  report.   The
item is identified as T  in that table.   It is  no longer
                       j
a common practice for utilities to use straight line tax
depreciation except for plant installed prior to 1954 ,
or used equipment acquired since that date.  The formula
is provided for completeness.  It is also used  to calculate
the tax annuity for land which is non-depreciable for
both book and tax purposes.  The calculation, using the
previously developed parameters,is given in Appendix B to
this report.  A tax life equal to the guideline life of 28
years was used.  If the 23 year life were to be elected it
would be necessary to normalize the difference  in tax lives
as described for accelerated depreciation.

Income Tax Annuity-Normalized
          The next formula given in Table V is  the formula
for the income tax annuity assuming straight line depre-
ciation for books, SYD depreciation for taxes,  with the
deferred taxes normalized.  The calculation, using the
previously developed parameters, is given in Appendix C
of this report.  The current practice of the Federal Power
Commission with respect to utilities under its  jurisdic-
tion is to allow deferred taxes to be normalized.  Under
that approach, income is calculated by treating as income
tax expense the sum of current and deferred taxes.  The
amount of the deferred tax, which is the difference between
                            B-20

-------
taxes computed on a straight line basis and taxes computed


on the basis of SYD depreciation, is set up in a tax re-


serve (balance sheet account) as a liability.   The straight


line tax rate is required by tax regulations to be the


guideline life or book life.  Current regulatory practice


is to deduct the amount of the deferred taxes from the


rate base in calculating return on rate base.   In the gen-


eral formula, the deferred tax is the expression t(Dt-_l).

                                                      Lg
The general formula assumes that the quantity to be


normalized is the difference between tax depreciation on


a straight line and on an accelerated basis.  It would also


be possible to normalize differences between book and tax


lives if desired.  However, suitable modifications would


have to be made to the general formula for the income tax


annuity,



Income Tax Annuity-Flow Through


          The next formula shown in Table V is the expres-


sion for the income tax annuity assuming straight line


depreciation for books, SYD depreciation for taxes, with


deferred taxes flowed through to income.  This method of


tax treatment is used in a number of the state jurisdic-


tions.  However, the intent of congress as expressed in


recent tax legislation favors the normalized approach.


The levelized tax annuity is identical with the results
                             B-21

-------
obtained using the normalized approach if there is no debt



in the capital structure.   The calculation of this annuity



using the previously developed parameters is given in



Appendix D to this report.





Investment Tax Credit



          The investment tax 'credit can be claimed on the



flue gas desulfurization equipment unless the rapid  (5 year)



amortization is claimed.  At the present time the credit



for utility property is 4%.  The intent of Congress  is that



this credit be normalized and not flowed through.  Also,  it



is not to be deducted from rate base.  Tax regulations re-



quire that tax life for other purposes be used in computing



the investment tax credit.   The formula for the investment



tax credit annuity identified as T  is given in Table V of



this report.



          The legislative history of the investment  tax



credit is unlikely to inspire long-run confidence in its



future availability.



          The Investment Tax Credit was introduced by the



Revenue Act of 1962, suspended by the Suspension Act of



1966, restored by the Restoration Act of 1967, and repealed



by the Tax Reform Act of 1969.  A revised Investment Tax



Credit was reinstated by the Revenue Act of 1971.  Recent



proposals by the Administration again call for changes in
                            B-22

-------
the Investment Tax Credit.   In view or the foregoing,  the



investment tax credit was omitted from the calculation of



total revenue requirements.   It can be included by off-



setting the amount of the credit from the income tax annuity,






Total Levelized Annual Revenue Requirement



          The general formula for the total levelized annual



revenue requirement for plant and for land is shown in



Table V.  Note that the expression is divided by 1 minus



the gross receipts tax.  This is to provide revenues suffi-



cient to cover the gross receipts tax plus the other com-



ponents.  If it is desired to determine the portion of the



carrying charge rate on investment attributable to the gross



receipts tax, this can be dpne by evaluating the expression



shown in the general formula both with and without the ex-



pression (1-G) and computing the difference.  Note that the



sum of the various components of the fixed charge rate such



as return, depreciation, and taxes is applied to total in-



vestment Cp .  This implies depreciation of working capital



and other similar components of total capital, which is not



strictly correct.  However,  this is commonly done because



the refinements to determine precise revenue requirements



would unduly complicate the analysis.
                             B-23

-------
                                                                                       TABLE V

                                                                                COST ANALYSIS PROCEDURE

                                                                                         FOR

                                                                               FLUE GAS DESULFURIZATION
                                    ITEM
w
I
to
Input Paramaters



     Total plant investment



     Plant life estimate



          Physical Life



          Book depreciation



     Construction time



     Interest rate during construction



     Capitalization



          Debt fraction



          Preferred Stock fraction



          Common Stock  fraction



     Interest rate on debt



     Dividend yield on  preferred  stock



     Percent  return on  common  equity



     Income Tax rate



     Plant life estimate for  tax  depreciation








     Net operating expense
                                                                                GENERAL FORMULA
                                                                                                         TYPICAL PARAMETERS
From  cost  estimates







15 years



30 years



2 years



9%







50%



15%



35%



10%



10%



15%



0.50  (48%  Federal, 4%  State)



23 years



28 years




From cost  estimates

-------
                                                                                         TABLE V

                                                                                        Continued
                                     ITEM
03
 I
to
U1
Input Parameters(cont'd.)


     Total Land required


     Unit cost of land


     Property Tax rate


     Gross Receipts tax rate


     Insurance


Calculated or Input Parameters


     Percent return on rate base


     Total land cost


     Working capital


     Startup Expenses


     Interest during construction




     Total capital requirement


          Plant


          Land


     Depreciation annuity
                                                                                  GENERAL FORMULA
 A


 G


 U






* Prp


 qn


 W


 S
                                                                                  C = P + I  + W + S


                                                                                       CB =  B
                                                                                 rj =	_	

                                                                                      (1 +  r)S  -  1
                                                                                                                             TYPICAL PARAMETERS
From cost estimates


From cost estimates


1.5%


4%


0.1%





r=ll.75%





0.125E


0.25E


0.09P







Cp = 1.09 P + 0.375E





0.027C,,

-------
a
 i
to

ITEM
Calculated or Input Parameters (cont'd)
Sum of Years Digits (SYD) Annuity
Income Tax Annuity
Assuming straight-line depreciation
for books and taxes
for books, SYD depreciation for
taxes, with deferred taxes normalized
Assuming straight-line depreciation
for books, SYD depreciation for
taxes, with deferred taxes flowed
through to income
Investment tax credit
Total levelized annual revenue requirements ,
Plant


TABLE V
Continued
GENERAL FORMULA

r(l+r)LP ^fzCLt - a+l)}{ 1 }~1
(l+r)LP - 1 °| Lc(Lt + 1) (l+r)Lt 1
where a = any year between o and Lt
[i ~) 1 1
Lb r 1 Lg Lb
t P 1 1~] dic 1
N VT 	 > IT T u J t^Ut , JIv-*- I c<.ut , /
1-t Lb L8 I r Lg
F ~ 1-t Lb r ' Lg I
T ( t j! 0-04r(l+r)(Lg~1) + O.OA |
C 1-t 1 (l+r)LS~' Lg 1
L_ * J
/- + D + T + A + U-i r
(1 - G)
(r + D + T + A} r
(1 - G)

TYPICAL PARAMETERS

0.0675
0.0615 Cp
0.0675 CB
On^ftft r
0.0321 Cp
-0.00583 Cp
0.2313 Cp using Ts,
0.2076 using TN,
0.2006 using Tp
0.2083 CB

-------
              APPENDIX C




COMPUTER PRINTOUTS OF FGD SYSTEM COSTS




     FOR THE MODEL PLANT ANALYSIS
                   C-l

-------
           STC< 2bO US KLTKOF1T
                	LlhECT COSTS	
               PKEPAKAIION
     .CONVEYORS
     STORAGE SILO
 PUWPS AND MOTORS
_STp!ur. P S-.AN P._MO.Tp.RJS.	
     SLUO&E POfviU
     MOBILE EGUIPMEMT

    .TOTAL C =.
                                            201302.
                                            190354.
                                              7328.
                                             2bb75.
                                             51468,
                                           1033U21.
                                             bfa740.
I).   PAKTICULATE REMOVAL
     VEWTURI SCKUBBEK
    _TAIiKS	
     PUMP'S AND MOTORS

    "TOTAL7"o~-
                                                 o.
                                                 o.
                                                 o.
                                                 o.
       COSTS" FOR LIMESTONE FGD  SYSTEM FOR  250 MW/3.5%  SULFUR/RETROFIT  MODEL  PLANT

-------
     GKANO TOTAL FUR  IliSTALLLU UlKEtT CbST^
******»***************»**<
                                        , **********
                	IN01KECT COSTS	
                         DUKIMG CONSTRUCTION
               FIEl-0  OVERHEAD
               CONTRACTORS FEE ArJO EXPENSES
                           ___ __
               FKEIhHT
             _ OFFSlTt
               TAXEs
               SPAl,}34.
                                                  171604.
                                                   S7201.
                                                  b7i:Ul3.
                                                 b 1 1 fa 9 7 0 .


                                                 3371419.

                                                 ~ -------
                                                2022bo94.


                                                    4267.


                                                    60.91

-------
OI'LKAI llMli
                                         f'uK  Lli-lLbTuNL  bLKUbUINb b
 	   A.   HAW  C,A1LKIAL
              FIXATION CHEMICALS
	D.. . UTILITIES

	ELECTRICITY
              WATEK
       	 KCHLAT
                                           UUAN1ITY
                                             11.0
                          TON/H
                 _3183,_ .KW.
                  82.5   GAL/MN
                  36.6   MM  bTU/H
                                             UNIT COS!
       b.oo  I/TON
       2.0U  S/TON
    15.0  nlLLS/KWH
      O.Olo  i/MGAL
      0.761*  $/MM  bill
                                    ANNUAL COST($)
                                                                                                           _251003._
                                                                                                                  "
          C.   OPEKATING LABOR
              DIRECT LABOR
                     2   MEN/DAY
    8.00 i/MANHUUH
IbSi OF UIKIiCT  LAbOK
                                                                                                            140160.
O
              LABOR ANO MATERIALS
              SUPPLIES	
              OVEKhF.AO
              PLANT
              RAYKOLI	
                                  H* OF FIXED  INVESTMENT
                                Ibfc OF LABOR AND  MATERIALS
                             5056 OF OPERATION  AND  MAINTENANCE.
                                  208. OF OPERATING LABOR
                                             809117.
                                             121372.
                                             515851.
                                              32236.
          F.   FIXEo COSTS
              DEPRECIATION
             _INTE«IM REPLACEMENT
              TAXES
             .INSURANCE..	
              CAPITAL COSTS
              TOTAL FIXED CHARGES
                     &.£>&%
                     0.35S
                     1.00%;
                     0.3 %
                     9.00%
                    20.31%
                                                                                                           1109796.
                                                      TOTAL ANNUAL COST
                                                                                  6810011.
                                                       MILLS PER MLOWATT-HOUR
                                                                                                               5.18

-------
            PLA^T  MAf'.c.-
       STO  250   HS
                                  	DlKtlCT COSTS	
                      .. I ilfl-S T-0 Ivi i_HkEEAKAXiO N_
                      CGfvvLYORS
                      STORAGE-SILO
                      BALL MILLS
                     -£Un HS-A ivO~!4 O-I-OHS-
                          rtbt; TA.MIvS
                      TOTAL A =
                                                                    351219.
                                              1173501.
 I
<£_
                      SCRUBBING
 FANS AND MOTORS
-gimps AND iviC|T0RS
 TANKS
-Ki.HCfi.TEkS	
 SOOT bLOWERS
,-OUCTIlVG. A,4a_.

 TnT'[_ f =
                                                                    342755.
                                                                    233586.
                                                                    271936.
                                                                    .961123._
                -C..	SLUOGE^.DISPOSAt...
                      CLAKIFIL'KS
                     -VACuUf, FILTLRS 	
                      TANKS fit-iD KIXE.RS
                     -FIXAT.lOt-i ChLi1ICAL_STjQ&AGE	
                      PUF'.PS A.xiD MOTORS
                           t-.-PQNU	
                      MOkiJLE EQUIPMENT

                      TOTAL C =
                                               1U0136.
                                             . ..180567..
                                              1890471.
                      PARTICULATE  KCMOVAL
                	 . V'ENTIJRI..SCKUSbEli
                      TANKS
                	BiiKP^ QMt.
                                                    0.
                                                    0.
                  	J.O.T-AI	0_s			       0.	

                 	CQSff-S  FOR  LIMESgQNE-fGD- SYSTEM  -FOR-2 50 -MW/J-.-5*- -SWJUR-/NBW

-------
     TOTAt  INSTALLED DlKLCf COSTS =
**********».
               	INDIRECT COSTS	
          DURING CONSTRUCTION
          RHEAD ......
 COMIKACTORS FEE AND EXPENSES
 FRElGHT
 OFFSiTE  -
 SPARES
           FOR SHAKEDOWN
TOTAL INDIKECT COSTS =
CONTINGENCY
 TOTAL  INSTALLED COSTS =
-TOTAL- HORSEPOWER
 COST  PER  KILOWATT
                                                 9t0659.
                                                 9
-------
                OPERATING COSTS FOK LIMESTONE SCRUBBING SYSTLM
A,  RAW r-,ATERU>L
    LIMESTONE
    FIXATION
                                              10.6  TOM/h
                                              3 £ i  TI \ i\i / l-i
                                                              UNIT COST
                                                              6.00
                                                              2  Qu  1-^J.0J-l_
                                                                                                      ANNUAL COST(S).
33691*5,
B.  UTILITIES

    ELECTRICITY
                                  3060.   KW
                                                                     15.0  hILLS/KWH
                                                                       OQ16
    REHEAT
                                            35.5  l"ih bTU/H
                                                             0.76"*  »/Hh faTU
                                                          .S.00  S/MflMHOUA.
    SUPEijCE
    CAPITAL  COSTS

    TOTAL F1XE13  CHARSf-S
                                               0.35'A
                                               H.OOi
                                               0.3 %
                                                                                                             3079504,
                                      	TOTAL..ANNUAL  COST	
                                                                                                     	5H90&96..-
                                              MILLS PER >>ILOulATT-HOUR
                                                                                                                 t.17

-------
           STD   25U   LS   KLTKOFIT
                	DIKLCT  COSTS	
     LIKESTC/KE  PREPARATION
    .COfviVf.YORS.
     STOKAL.E  SILO
    JLALL  MILLS   	
     PUI",PS AND MOTORS
    _STORAbE  TANKS
    _.TC_TAL..A._=_. .
529U26.
 76951.
                                               1126113.
     SCKUBQING
AbSORBEKS
FANS AM) MOTOKS
PUMPS AND MOTORS
TANKS
REHEATEhS
Y SOOT tfLOVoERS
00 DUCTliviG AND VALVES
4079199.
400327.
2fa2i>98.
88b763.
299U40.
, ...ff""":
     TOTAL B =
     SLUDGL DISPOSAL
     CLARIF-IEHS      ________________
     VACUUM FILTERS
     TANKS AND MIXERS
     FIXATION CHEMICAL STORAGE
     SLUDGE PONO
    _NOBILE .EQUIPMENT

    _TOTAL. .C. =
102071.
217008.
 17413.
955189.
0.
     PARTICULATE REMOVAL
             SCRUBUEK
     TANKS
           AND MOTOKS
     0.
     0.
     0.
     TOTAL D =                                       0.
        COSTS FOR  LIMESTONE  FGD  SYSTEM  FOR 250 MW/0.6%  SULFUR/RETROFIT  MODEL- PLANT—

-------
                        GKANU TOTAL FCK INSTALLED OIKECT COSTb = l Ub236i! 1.
                                  	INDIRECT  COSTS	
1NTEKEST UUKlNb  CONSTRUCTION
      OVERHEAD
            FE1E  AlxiU  EXF'E.NStS
FREIGHT
OFFbiTt.
TAXES
          FOK  SHAKEDOWN
n
 i
                   TOTAL INDIRECT COT S =
             	 CONTINGENCY
TOTAL INSTALLED  COSTS =
          	TOT.AL..HORSLPOWEK .
                                                                    Illbb25.
                                                                     bb77fc2.
                                                                     157o57.
                                                                      b\ibl9.
                                                                     52bl91.

                                                                    t985029.
                                                                    3101370.
                                                                   10606i;20.
                   COST-DOLLAKS PEK KILOWATT                          74.13

                   ***************»*******«***|t********>******* ******

-------
                CI'LKAllUb LUSTS  (-UK  LliSLSlO(\;L liCKUlibiNO
 A.   RAW MATLKIAL
     FIXATION CHEMICALS
                                   UUANT 11 Y
   2.8  TON/h
   fa.9  TON/H
                            UNIT  CUt.T
                                                              (..on   S/TON
                                                              il.OC   i/TON
                                                                                           ANNUAL  COST(S)
 72924.
.B.  .UTILITIES

	ELECTRICITY...
     WATEh
 2^66.  KUi
8^.1  GAL/MIM
36.6  MM DTU/H
                                                           15,0   MILLS/KWH
                                                             O.OlU   i/rfbAL
                                                             U.76"*   4/Hi"l bTU
233905._
 C.   OPERATING LABOR
     DIRECT LABOR
   2  MEN/DAY
                                                           6.00  $/^AUHOUR
                                                       Ib4, OF DIKLCT  LABOK
140160.
 21024.
 D.   MAINTENANCE
     LABOR AND MATERIALS
     SUPPLIES		
                485 UF  FIXED  INVESTMENT
              158. OF LABOK AND MATERIALS
                                                                                                    744328.
                                                                                                    111649.
 E.   OVERHEAD
      PLA^T
	PAYROLL. ...
                                             5CS OF OPERATION AND  MAINTENANCE
                                                  20S OF OPERATING LABOR
                                                                 508581.
                                                                  32236.
 F.   FIXEo COSTS
     DEPHE.CIATIuN
     INTERIM REPLACEMENT
    .INSURANCE
     CAPITAL COSTS
     TOTAL FIXED CHARGES
   4.00%
   0.3 ^
  20.31%
                                                                                                  3780570.
                                             TOTAL ANNUAL COST
                                                                                                  5632672.
                                              MILLS PER KILOWATT-HOUR
                                                                                                      4.47

-------
             PLAM
       STQ   £50   LS
                               ...	UIHEXT-_CGSTSr	
                                    AR AT I G
                      COhVEYCRS
                      -STORAGE-S1LCX	
                      HALL ISILLS
                      Pl^'.PS AND fiOTORS
                      STORAGE TAT.'KS
                      TOTAL A =
                                            31<+.3fo2.
                                             47313.
	O~
                      SCRUBBING
-ABSORBERS	
 FA'MS  AiVO  MOTORS
-jaimnS—AfeUj  MOTORS
 TANKS
                      SOOT
                      TOT/vLB~
                                                                 i si i n7 1
233b8b.

27193&!
                  ^	SLUDGE-DISPOSAL.
                      CLAKIFIE.RS
                      -VACUUM FILTERS	19B071..
                      TAi\KS AiMD MIXERS                             3>798.
                      .FIXATION CHEM1CAL_SIQRAGE	   ...	15755..
                      PUP"PS AND MOTORS                            23702.
 MO&ILE  EQUIPMENT

 TOTAL C =
                                                                1104566.
                      PARTICULATE REMOVAL
 TAKKS
 PUMPS
                                                                       0.
                                                                       0.
                                "OTQBS
                      -TOTAL Q~-	  	  .  .                0.                 	         .   .
                          COSTS FOR LIMESTONE  FGD  SYSTEM  FOR 250 MW/0.6%  SULFUR/NEW MODEL PLANT

-------
        TOTAL INSTALLED L>I*LC1 COSTS =
                                               6370*06,
   *************************************************
                  	INUIKECT  COSTS	
INTEREST DURING CONSTRUCT ION
FIEL^ OVERHEAD     	  -  	
CONTRACTORS FEE AMU EXPENSES
   FREIGHT
   OFFSjTC
   SPAKES  -  •      -
   ALLOWANCE FOR SHAKEDOWN
   TOTAL  INDIRECT COSTS =
   CONTINGENCY	
   TOTAL  INSTALLED COSTS =
                                                    837020.
                                                    837620.
                                               __B37a2Q»_
                                                104727.
                                                251346.
                                                •UtoSlO.
                                              11703753.
	TOTAL -HORSEPOWER
                                                  3665.
   COST HER KILOWATT                                    56,

   *********************»**************•».************

-------
                              OHU
                                                            T.OTAL ANNUAL  COST.,
                                                             MLLS PER KILOWATT-HOUR

-------
PLA^T MAf.E- .
      STD  50U
                 US  RETROFIT
                    	L/1KLCT  GUSTS	
         LIMESTONE PREPARATION
        .CONVEYORS
         STORAGE. SILO
        _UALL_cJl LkS	
         PUKPS ANO MOTORS
                                           bb2b66.
                                           107o91.
                                           230265.
       __T_QT.A.L .A._=	
                                          1820912.
 	B.	
SCRURBINti
         TOTAL B =
                                         1572799t.
         SLUDGE. DISPOSAL
         CLARIFILRS
         VACUUM FILTERS
         TANKS AND illXEKS
         FIXATION CtlEMlCAL STORAGE
         PUM P S_A N D _ r, p TO_K_S	
         SLUDGE POND
         MOL'ILE EOUIPMEIMT
                                           280102.
                                           19b232.
                                             9707.
                                            ibafcl.
                                            83126.
                                          1661050.
AbSORBtRS
FAI\IS A(MD MOTORS
PUMPS AND MOTORS
TAfMKS
RtHEATE.KS
Q SOOT BLOWLRS
1 DUCTING AND VALVES
M
78822^9.
789015.
336b33.
4fa7u75.
1711567.
41US60.
t09097t.
         TOTAL C =
                                          2323821.
         PAKTICULATE REMOVAL
                 SCRUBBER
         TANKS
         PUMPS AND MOTORS
                                                0.
                                                0.
                                                0.
         TOTAL D =                                       0.

            COSTS  FOR  LIMESTONE  FGD  SYSTEM FOR 500 MW/3.5%  SULFUR/RETROFIT  MODEL  PLANT

-------
                           TOTAL  FOR  INSTALLED DIRI.CT cobTS=i9672727.
                                	INDIRECT  COSTS	
                INTEhEST DURING  CONSTRUCTION
             	FIELD OVERHEAD
                CONTRACTORS  FEE  AMU  EXPENSES
                FREU-HT
   _______________ _____ ; OFFSiTEI
                TAXES
                ALLOWANCE  FOR
                TOTAL  IIVDIKECT  COSTS  =
 O
-I—
	 CONTINGENCY.
                TOTAL  INSTALLED  COSTS =
               ...TOTAL.. HOkSEHOlwER
                                                        210fa309.
                                                        1U53254.
                                                        202/U16.
                                                         24B409.
                                                         29dU90.
                                                          99363.
                                                         993636.
                COST-DOLLARS  PER  KILOWATT
 9409736.


 585b492.


36138957.


    7972.


    70.27

-------
              		OPERATING CuSTS FOR LIMESTONE  SCRUHblUU SYSTEM
	A...RAW.MATERIAL
         FIXATION CHEMICALS
  	@_»	UTILITIES	

  	ELECTRICITY
         WATEh
                                      UUANTlTY
   21.3  ToN/H
   52.2  TON/H
  5947.  KU
lt»9.4  GAL/NIN
 70.6  MM bTU/H
                                                                 UNIT CUbl
   6.00
   2.CO  S/TON
15.0  MILLS/KWH
  0.010  i/MGAL
  0.764  S/MH bTU
                                                                                              ANNUAL COST<$)
                                                                                                      673679._
                                                                                                     ~54~9157.
J*68925.
    950.
 2faH707,
     C.   OPERATING LAbOR
                LABOR                    2   MEN/DAY.           8.00 i/MAUhOUK
         SUPERVISION                                      15s. OF UIKECT LttBOK


     F.   MAINTENANCE

         IABOR AM; fiATtRIALS                         "t» OF "FIXED INVESTMENT
         SUPPLIES	   	  ....    iss OF LABOR AND MATERIALS

               		 .
     E.   OVERHEAD

         PLANT                                   boji""b"F" "OPERATION ANU "MAI'NIENA'NCE
         PAYROLL	   __	                   2U* OF OPERATING LABOR


     FT  FIXED COSTS

         DEPRECIATION                    5.0USS
         INTERIM REPLACEMENT  	   	   0.355S
         TAXES                           H.OOK
         INSUKANCE._    	   	 	      0.3 %
        "CAPITAL COSTS                   9.oca
                                                                  140160.
                                                                   21024.
                                                                 X405558.
                                                                  210833.
                                                                  688788.
                                                                   32236.
         TOTAL FIXED CHARGES
                                                                                                     6553415.
                                                 TOTAL ANNUAL COST
                                                                                                    11229437.
                                                  MILLS HER MLOwATT-HOUR
                                                                                                          4,27

-------
              PLANT MANE-
                             STO   500   HS
                                  	DIRECT CuSTS	
                      _LmEST-OWE. PKEPftRATION
                       CONVEYORS
                      -STCKAGt SILO	
                       BALL MLLS
                      _fiU#pS-ftND f.-,c^I-aH5	
                       STORAGE TAiiKS
                       TOTAL A =
                                            399990.
                                             9bb87.
                                           1513*56.
                       SCRUBBING
         		AtSORbLKS
                       FAMS AND MOTORS
                       PUiv-PS /•, ;\j Q i"i Q T 0 R S
                       TA;*JKS
                      -REHE
SOOT BLOWLKS
      r^.AfMD_VAL-V-ES-
                       T 0 T >\ L B ^_
                                           703UH81.
                                            670^77.
                                                                   407^0'*.
	C._._._ SLUUGE..DISPOSAL.	
                       CLARISIEKS
                       VACUUM FILTERS  ...  	 	
                       TANKS AND MIXEKS
                       FIXATION CHEMICAL STOKAbE
                       PUf'iPS AfJD MOTORS
                       MOBILE EQUIPMENT

                       TOTAL C =
                                            177603.
                                              o745.
                                             3i:196.
                                          -Xai6.7J£u^.
                                             5341b.
D. PARTICIPATE KEMOVAL
	 . 	 	 _ ..VLi'JTUKI SCKubBE-K
TAf-KS
piiMps AMU HnTLiks

XO.TJVL U = 	 .

0. . 	 	 . .
C.
o ,

o.
                          COSTS  FOR LIMESTONE FGD  SYSTEM FOR  500  MW/3.5%  SULFUR/NEW MODEL PLANT

-------
                    TOTAL INSTALLED DlKECT COSTS =
                              	IfjDlKECT COSTS	



               IWTEfjLST DURING CONSTRUCTION                    Ibfabbdb.
               FIEL(.: -OVERHEAD	-	        16bbb85.
               CONTACTORS FEE At\iD EXPENSES                     832792.
               ENG-ItxCLR-UOG	.	Lfafaib65_
               FHElGHT                                          206190.
_ 		OFPSjTtL. .. ...          ......_._....           t9«Jo75.
               TAXES                                            2t9637.
	SRARtS			         03279.
               ALLOWANCE FOR SHAKEDOWN                          832792.

               TOTAL INDIRECT COSTS =                          7703331.


_Q	 	 CONTINGENCY	 .  -		  -   -    1871636.
 M	
               TOTAL INSTALLED COSTS =                        29231020.


        	TOTAL-HORSEPOWER				_	       ..    7609.


               COST PER KILOWATT                                    58.

               ****:|^**********************»********************

-------
                       OPERATING COSTS FOR LIMESTONE.  SCRUbbING SYSTEM
A.  RAW MATERIAL

    LIMESTONE.
                                         UUANTllY
                                          20.9   TOU/H
                                         -bl^-1	TON/h
                                                              UNIT COST
                                                              6.00  4/TON
                                                            -_2..-Q-0	sy TON-
                                                                                                 ANNUAL  COST(S)
                                                                                                          659261,
       B.  UTILITIES

           ELECTRICITY
      	WJX-TCw	
           REHEAT
                                   5626.  KW
                                        MM BTU/H
                                                          15.0  MILLS/KWH
                                                         	£U 01*—-i/fiGAI	
                                                            0.7bf  i/HM  BTU
                                                                                                   t5932S.
                                                                                                   279267.
       C.---OPERATIMG-LABOR	

                   ^ ADOR	
           SUPERVlSlOi\j
-D.. — MAINTENANCE	  	

	I AROH	Afcfl M&TFKTALK
           SUPPLIES
	E-.._. OVERHEAD..	
                                                         >i  OF  CilKECT LABOR
                                                                                                           2102t.
                                                            OF FIXED  INVESTMENT
                                                    OF  LAbOR AND MATERIALS
                                                                             NTENANCE
                                                                                                  1169240.
                                                                                                   175586.
                                                                                                   7529Q5t
PAYROLL
F, FIXLb COSTS
nrpRFClATiorj
INTERIM REPLACEMENT
TAXES
INSURANCE
- _ CAPITAL COSTS

TOTAL Fivrp CHARTS
20S OF OPERATING LABOR 32236.

5.00-^
0.35*
4.00S
0.3 %
9.00^

18.65K 54515Q5.
                                                    TOTAL ANNUAL COST  .
                                                                                    	  	 __9678736.
                                                     MILLS PER KILOWATT-hOJR
                                                                                                       3.68

-------
		PLANT NAME-
S'! U  'jUO Lii   HLIKUf II
                            	UlKECf Co-STS	
                 LIMESTONE PREPARATION
            	CONVEYORS                                  449529.
                 STORAGE: SILO                                6o24«.
            	BALL .BILLS		555665.
                 PUMPS ANO MOTORS                            97191.
            	.STORAGE.TANKS. .._.._                         56695.

            	.TOTAL. A. =.	   	  ._..                     1219530.



            J3_.	SCRUHBIMG.


                 "AHSORUERS                     "
            	FATviS AiMU HOT.OKS	789015...
                 PUMps AMU MOTOKS                           33db33.
            	TANKS..  		  .   _    467075.
                 REHEATEKS                                  1711567.
            	S.OQT .BUO.WEHS			 ._		  ^tabto.
                 DUCTING AND VALVES                         t09097U.

                 TOTAL B _                                 1572799*».



            ~C.SLUDGE DISPOSAL"""


            	CLARIFIERS       „_  _...._                   1H2090.
                 VACUUM FILTERS            ~""      "         204055.
            	TANKS AMD MIXERS            _                5503.
                 FIXATION CHEMICAL STOWAGE                  20062.
            	PUHPJS_ANU_MOT_ORS	 H<«bi6.
                 SLUDGE PONO                         	842615.
                 MOBILE EQUIPMENT                            58740.
                __TOTAL .C..=
                                   1316385.
                 PAKTICULATE  REMOVAL
                 VENTURI SCRUtlBEK
                 ...TANKS	
                 PUMPS AND MOTOKS

                 "T'OT'AL "D ~="
                                         o.
                                         o.
                                         o.
                                         o.
                    "COSTS"FOR LIMESTONE FGD SYSTEM FOR  500  MW/0.6% SULFUR/RETROFIT MODEL PLANT

-------
                       GkAND TOT/.L FOR  INSTALLLO OIKF.LT COST S =
                                 	INDIRECT COSTS	
                  INTEREST UURIMG  CONSTRUCTION
             	FIElLu OVERHEAD
                  CONTHACTORS FEE  ANO  EXH'.NSES
             	ELNG liSiEEB. 1I1&_	
       ______________ OFFilTL
                  TAXES
       ________ SPARES
                            FOR  SHAKEOOWlM
     I
    to
   -1-*-
                  TOTAt INOIKFCT  COSTS =
                 ..CONTINGENCY .
                  TOTAL IlMSTALLEU  COSTS =
	TOTAL HORSEPOWER^
                  COST-UOLLARS  PER  KILOWATT
 182fab91.
 1936106.
 1663122.
  226323.
  517977.
   91329.
  913295.
 5382963.


"32297702 J""


     7395.

-------
                          OHLKA1
           A.   KAW P.AILKIAL

          	LIMLSTUNE	
               FIXATION CHEMICALS
                                             (JUAMITY
   3.4  TOU/H
  13.4  TON/H
                                                                             COST
   6.00  S/TON
   2.00  I/TON
                                                         ANNUAL COST(S)
173359.
I«fl315.
          ..B._.UTILIT1ES.  ..

          	ELe.ClB.lC.IJ.1L
               WATER
               RCMEAT
 5517.  KW
      (iAL/MIN
70,tt  MK BTU/H
15.U  hlLUS/KWH
  0.010  S/MGAL
  0.764  */«M  6TU
134970.
   y»9."
264707.
           C.   OPEKATING LABOR
                      LABOR
               SUPERVISION
                                               2  MEN/LAY
                         8.00  i/MANHOUR
                     IbSb  OF  UIKC.CT LABOK
                                         140160.
                                          21024.
 O
-4—
 to
           0.
               LABOK AND KATERIALS
            	SUPPLIES	
           E.   OVERHEAD
               PLANT
             	FAYHOLI	
                4S OF  FIXEO INVESTMENT
                  OF LAbOR  AND MATERIALS
           50S OF  OPERATION ANO MAINTENANCE
                 204  OF  OPERATING LABOR
                                        1291911.
                                         193766.
                                          32236.
           F.   FIXED COSTS
               DEPHtCIATION
     	liMTERIM.REf.LACLMENT.
               TAXES
     	INSURANCE	
               CAPITAL COSTS
               TOTAL FIXED CHARGES
   3.00%
   0.35S*
   4.00%
   0.3 *>
   9.00i8
                                                                                                            6023536.
                                                       TOTAL ANNUAL  COST
                                                                                                            9561398.
                                                        MILLS PER KILOWATT-HOUR
                                                                                                                3.63

-------
              PLANT NA^E-    STU  500 LS   New
                                  	UlKLCT COSTS	
                       COIWEYOKS                                  326471.
                  	STORAGE SILC	 —		        b4459.
                       BALL MILLS                                 504205.
                                ,-Mfj-TQR-£-      	
                       STOKAGL TANKS
                       TOTAL A =                                 1016234.
                  B.   SCRUBBING
 	ABSORBERS	
                       FAKS AND MOTORS                            670277.
                       pnypg AMC MQTnR-S	.	2.64.5.2SU.
                       TANKS
                    	REHEATERS	
._.                      SOOT BLOWERS                               407904.
l|i	OU.C.T IN.G ..A^U...VALVES	2254706 ^
to	
W	TOTAL U =	
                 _CL.	S.UUOGE.D.ISP.OSAU	
                       CLARIFIERS                                  127768.
                    	VACUUM FILTERS	1U6552.
                       TAI^KS Ai\iO MIXERS                             4960.
                    	FlXATlCU CHEMICAL .STORAGE	 __.  _.. 	  .16135...
                       PUMPS AND MOTORS
                    	SL
                       MOBILE EQUIPMENT                            53416.

                       TOTAL C =                                  1429678.
                       PARTICULATE REMOVAL
                  	VENTUKI SCKUBBER          	                  0.
                       TANKS                                            0.
                  	PUMPS AI\iD hOTORS	D.»_
                      JTOTAL-O-S		     . .      -     0.
                           COSTS FOR LIMESTONE  FGD  SYSTEM FOR  500  MW/0.6% SULFUR/NEW  MODEL  PLANT

-------
     TOTAL INSTALLED DIRECT COSTS  =
i502UU7fl.
                      ****************************
               	INUIRECT  COSTS	
INTEREST DURING CONSTRUCTION                    1502007.
FIELo OVERHEAD         -    -                    1502007.
CONTRACTORS FEE A NO EXPENSES                     761003.
-£WGl,JEeH-tW6	1502007..-
FREIiHT                                          187750.
OFFSiTE  -—	  	-- --		  -       150602.
TAXES                                            225301.
SPARES-  -  - --     			         75100.
ALLOWANCE  FOR SHAKEDOWN                          751003.

TOTAL INDIRECT COSTS =                          6946766.


CONTINGENCY  -		-	     .4393i72.


TOTAL INSTALLED COSTS =                        26360237.


TOTAL-HORSEPOWER		  ...._. .   ...    7260.


COST PER KILOWATT                                    52.

*************************************************

-------
                       CPE.KATING  COSTS  FOK LIMESTONE bCRUB&IiMG  SYSTEn
        A.   RAW MATERIAL
tUAIwTITY


  5.3  TOIO/M
        8.   UTILITIES

            ELECTRICITY
                              5116.  KW
                                                                     ur.n COST
                                                         b.OO  S/TON
                                                  	2.UU-—
                        15.0  MILLS/KWH
                       	0 -, 0-18	$y-W6AU
                                                                                      ANNUAL COST(S>
                                                                                                          169561.
437025.
            REHEAT
                             fa9.<*  MM BTU/h
                          0.76H  $/«M  BTU
                                                                                                          2792fa7.
       -C.   OPERATING-LABOR	
                                               MKM/nAY
                                                                   .J) n
                                                              158i  OF C'.IRECT LABOR
                                                                                                21021.
	0.-- -MAINTENANCE	
                 __ Af'jp MATERIALS
                                                             OF  FlXEil
            SUPPLIES
                                            158i  OF  LABOR AND MATERIALS
                                                                 153161.
           -RLAK-T	
            FAYKuLL
                                                      ^, OF  OPERaTIOM flMD MAINTENANCE
                                                                                                          666677.
                                              2CJS  OF OPERATING LABOR
                                                                  32236.
           _ FIXEu.COSTS__
I.'-JTERIM REPLACEMENT
TAXES _______
INSURANCE
CAPITAL-COSTS-^
                                            0.35*;
                                            1.00£
                                            U.3 £
                                            9.00?d
           -TOTAL FIXED CHAKEFS-
                                                                                              4916181,
                                              	TOTAL  ANNUAL COST
                                                                                      	OQ2.1058i.._.
                                                     MILLS  PER  KILOWATT-HOUR
                                                                                                  3.05.

-------
PLANT NAKE-
STD 1000 HS RETROFIT
        LIMESTONE PREPARATION
CONVEYORS
STORAGE SILO
BALL MLLS
PU;viPS AND' MOTORS
STORAGE TANKS
TOTAL A =

B. SCRUBBING

ABSORbERS
FANS AND MOTORS
PUMPS AND MOTORS
TANKS
REHEATERS
SOOT BLOWERS
DUCTING AND VALVES
O
I TOTAL B =
to

C. SLUDGE DISPOSAL
CLARIFIERS
VACUUM FILTERS
TANKS AND MIXERS
FIXATION CHEMICAL STORAGE
PUMPS AND MOTORS
SLUDGE POND
MOBILE EQUIPMENT
TOTAL C =

D. PARTICULATE REMOVAL

VENTURI SCKUBBEK
TANKS
PUMPS AND MOTOKS

TOTAL 0 =
693215.
" 166838. ... -
9192i>0.
4l488i.
540613.
2736799.
-

,
15463305.
15"*7876.
712644.
966654.
33S7723.
1046640.
9997973.

33094217.


391063.
193601.
13053.
£>fe22£.
14b690.
23ye09».
58740.
3457471.



u.
0.
u.

0.
           COSTS  FOR LIMESTONE  FGD SYSTEM FOR  1000 MW/3.5% SULFUR/RETROFIT  MOUh^

-------
                   GRAND TOTAL FOR INSTALLED DIRECT  COSTS=39268488.
                             	1NUIKLCT COSTS	~~
              INTfc-REST  DURING CDf-lbTKUC I ION
              FIELD  OVERHEAD
             TR E TG H T
              OFFSiTE
              TAXt-S
              SPARES
             "ALTWATJCT

              TOTAL  ISTDIRECT CO~STS"
                                                 20622897"
                                                 tooy'+as.
                                                  ^9iioer
                                                 1178654.
                                                  5B5327T"
                                                  19&H42.
O
              CONTINGENCY
"TOTAL rN"S
                              COSTS =
                                                11578317.
              TOTAL HORSEPOWER
                               KILOWATT
                                                   15351,

-------
                OPERATING  COSTS  FOR LIMESTONE SCRUBBING  SYSTEM
 A.   RAW hATERIAL

     LIMESTONE
     FlXAtlCW'CBEMlCALS"
                                 "-QUANTITY""
 tl.8  TON/H
102.2  TON/H
                           UNIT COST
6.00  */TON
2.00  S/TON
                                                                                           ANNUAL COST(S)
1318526.
1074812.-
 B.   UTILITIES
     ELECTRICITY                  11<»52.  KW               15.0  MiLLS/KWH                         902883.
	fcWTEK	~	J12;7  GAL/MIN	" 	0.018  S/MGAL	  	       1864.
     REHEAT	136.9  MM BTU/H	°_>76JL_l./'lfl EI^1	55653f.


~CT~  OPERATING" LABOR~'             	     	    '"	    ""'  " " "      	

	DIRE1CT"LABDR	~	3""HEN/DAY "'" 	 "   8.00 S/MANHOUR   	  		—r"  	2102<«0.-
     SUPEKVISION	158S_ OF IJlRf^TJ-^BOR	_3jL5i5_l


"DV""~MAINTENANCE	'				   -  --.         .-   .. -		 	   	

	L ABOK "ANCTITATER lAtTS	:	   "»K OF  FIXED INVESTMENT  "	  2778796-.-
     SUPPLIES	ISK^OF  LABOR AND MATERIALS	f!6819.


~ET~ "OVERHEAD                                      "  	""	        ~

     PLANT       !                            50So"X)F-OPERATION ANIT'MftlNTENANCE--                   r7rB6"95T"
     PAYRQLL	20a  OF OPERATING LABOR	t6355.


~T~.   FIXEcTCOSTS

              nm                    svrros                               '                   •
    	     REPLACEMENT	0.35%	
     TAXES4.00S
    JNSURANCE    	0.3 %	


    "TOTAL FIXETT~CTiAK5E5            1B.&5%



    	nrrsL~ANwoAU"T:osT	
                                              MILLS  PER  KILOWATT-HOUR
                                                                    t.18

-------
                                            DIRECTCOSTS=323^3031.
           --»**-*-* *"*^*v* *******************"*******************
                         ...... ----INDIRECT COSTS- —
                             COWSI KUCTIOT3                    3231 303";
             FIELD OVERHEAD                                  3234303.
             CONTRACTORS-FEE' ANCrrXPENSES '  --------------- ...... --------- 1617151.
             ENGINEERING                                     3231+303.
            :~FRElGHT                             "~ ...... "       40H267.
             OFFSiTL __ ____     970290.
             T'AxTs           '
             SPAKES                                           161715.
                                                         ...... ' 1617151.
             TOTAC~INDIRECT~C'OSTS~=
             CONTlNGENCY
o                                                     	
N>            T OTA L~I NS T ALLE cTCfO"Srs~~=56762020.
vo
             TOTAL HORSEPOWER                                  14858.
            TO~ST-. DOLL AR'STPrfTKTl.O WATT                          5"6776

-------
PLANT N/Vf,l -
iTU 10UO Mf. NLW
                 	JjIRECT COSTS—- -
A. LIMESTONE PREPARATION '
CONVEYORS
STORAGE. SILO
BALL MILLS
PUMPS AND MOTORS
STORAGE TANKS
TOTAL A =

B. SCRUBBING

AbSOKBERS
FANS AND MOTORS
PUMPS AND MOTORS
TANKS
REHEATERS
SOOT BLOWERS
DUCTING AND VALVES
o
I TOTAL B =
u>

C. SLUDGE DISPOSAL
CLARIFIERS
VACUUM FILTERS
TANKS AND MIXERS
FIXATION CHEMICAL STORAGE
PUMPS AND MOTORS
SLUOGE POND
MOBILE EUUIPMENT
TOTAL C =

D, PARTICULATE REMOVAL

VENTURI SCRUBBER
TANKS
PUMPS "AND" MOTOKS


*»97162.
i«*97<+b.
823212.
327277.
«»672J*2.
2261671.



lie>ui)211.
1297030.
518502.
8196,66.
29bH2b1.
815608.
6bb06ba.

26571333.


350357.
1/blO I .
11690,
t9665.
117090.
27^8^98.
5ifl6.
3507026.



0.
0.
0.

       TOTALl) =
                                   0.
          COSTS FOR LIMESTONE FGD SYSTEM FOR 1000 MW/3.5% SULFUR/NEW MODEL PLANT

-------
                               OPERATING COSTS  FOR  LIMESTONE  SCRUBBING SYSTEM














0
1
U)
M












A. RAW MATERIAL
LIMESTONE
FIXATION CHEMICALS
B. UTILITIES
ELECTRICITY
WATER
REHEAT

C. OPERATING LABOR
DIRECT LABOR
SUPERVISION

D. MAINTENANCE
LABOR AND MATERIALS
SUPPLIES

E. OVERHEAD
PLANT
PAYROLL

F. FIXED COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES





QUANTITY UNIT COST ANNUAL COS! IS)
HO. 4 TON/H 6.0U 5/TON 1274577.
98.8 TON/H 2". 00 "S/TON . - j.038985.

11084. KW 15.0 MILLS/KWH 873881.
302.6 GAL"/PI1N 0.016 5/PIGAL 1803.
134.4 MM BTU/h 0.764 i/MM BTU 540400.


3 FILN/UAY 8.00 4/MANHOUR 210240.
1555 OF DIRECT LABOR 31535.
.

4S OF FIXED INVESTMENT 2270480.
15S OF LAbOR AND MATERIALS 340572.


bOfc OF OPERATION ANU MAINTENANCE 1426414.
20fe OF OPERATING LABOR 48355.


5.0 OS
0.3555
4.00%
0.3 K
9. DOS" ' " " "

16.65K I0ti6bllb.


TOTAL ANNUAL COST ' " 18643363.
MILLS PER KILOWATT-HOUR 3.54
o

-------
PLANT NAME-     STD  1000 LS KETROFIT
                    	D"I R ETCT~CO"ST5="- - -
         CIWESTONE-PREPARATION—	
         CONVEYORS
        "STORAGE  SILO"
         BALL  KILLS
        "PUMP S~A N D~ M OTOTCS"
         STORAGE  TANKS
         TOTAL  A  =
 483226.
  75966.
 600294.
•16110"*.
 101897.
         SCRUBBING
ABSORBERS
FANS AND MOTORS
PUMPS AMD MOTORS
TANKS
REHEATERS
SOOT BLOWERS
DUCTING AND VALVES "
o
1 TOTAL B =
U)
	 	 15463305. 	 	
1547876.
712044.
968654.
33!>7723.
1046640.
9997973.

33094217.
CLARIFIERS
VACUUM FILTERS
TANKS ANU MIXERS
FIXATION CHEMICAL STORAGE
PUMPS AND T10TORS
SLUDGE POND
MOBILE EQUIPMENT
TOTAL C =
196732.
19flb2i!.
7250.
25296.
70309.
1317616.
58740.
1&76468.
         PARTICULATE  REMOVAL
        "VENTURI  S'CWJD3ETT
         TANKS
      0.
        "PTJWPS AND  MOTORS
         TOTAL 0  =
            COSTS FOR LIMESTONE FGD SYSTEM FOR 1000  MW/0.6%  SULFUR/RETROFIT  MODEL PLANT

-------















o
1
oo
OJ





• GRAND TOTAL FoR INSTALLED DIRECT

*********************»***************4

	 INDIRECT COtJTS----

1NTEKEST DURING CONST RUC1 IUN
FIELo OVERHEAD
CONTRACTORS FEE AND EXPENSES
ENGINEERING
•FREIGHT
OFFSITE
7AXE-S
SPARES
ALLOWANCE FOR SHAKEDOWN

TOTAL INDIRECT COSTS =
CONTINGENCY


TOTAL INSTALLED COSTS =
TOTAL HORSEPOWER


COST-DOLLARS PER KILOWATT

•c"OSTS=36i»'01177.

t***********



ibHOll 1 .
aesabz1*.
19i9ibi.
5712920.
4bb01!4.
1092035.
S46U17.
182U05.
1620058.

172^5^57.
10727427.


&';ib'*5&2.
14236.


64. 5fa

-------
                         OPERATING COSTS FOR LIMESTONE SCRUBBING SYSTEM
                                        	QUANTITY
          A.   RAW MATERIAL
              LIMESTONE
            "FIXATION" CHEMTC'ALS "
                                10.7  TON/H
                               "26.2  TON/H
          B.   UTILITIES
              ELECTRICITY
           	WATER	-"
              REHEAT
                              10620.  KW
                             3I"2.6~~"GAU7
                             138.9  MM 8TU/H
                                                         UNIT COST
6.00  S/TON
2.00  S/TON
         15.0  MILLS/KWH
           0.018S/MGAL
           0.761  S/MM 3TU
                                        ANNUAL" C0STT5T
                                                 339122.
                                                 276139Y-
                                     837334.
                                    	1863V
                                     558531.
          C.~-""OPERATING~ LABOR

         	DTR ECT"LABOR	
              SUPERVISION
                                "3—MEN/DAY
    	-- 8.00 S/MANHOUR
     15* OF DIRECT LABOR
                                  	210210V
                                      31535.
         TJ-;	MAI N T EWA NC ET"
             '"LABOR
              SUPPLIES
                                            " UK OF FIXED INVESTMENT-
                                            15S OF LABOR AND MATERIALS
                                                2571582V
                                                 386187.
n
 I
00
""OVERHEATT'

'IPLAMT   7
  PAYROLL
OF OPERATION AND" HAINTENANCE-
 20% OF OPERATING LABOR
                                   -T.601272.
                                      18355.
              INTERIM REPLACEMENT
              TAXES
              INSURANCE
              TOTAL FIXED CHARGES
                                 0 . 35%
                                 0.3
                                -9YOOS
                                10.65%
                                              -1700J990V
                                                     'TOTAL~ANNUAL~ COST"
                                                                                           T.-8869159.-
                                                      MILLS PER KILOWATT-HOUR
                                                                                                 3.59

-------
             "**»*********V* ***********************************
                             •---«-! NDI RECT"COSTS----
FIELD OVERHEAD
CONTRACTORS FEE AND EXPENSES
ENGINEERING
FKE.IGHT
OFFSiTE
SPARES
"•ALLOWANCE FOR SHAKEDOWN 	 ' 	

1 2964845; " " ~" 	 	 "'"" ' '" " " " 	
"1482422. 	 	 ~ "' 	 '
.2964645.
370fe05. 	 	 	 " " 	 " " 	 " 	
869453.
444726.
146242.
1482422. • • •-• -- -• 	 - 	 --

               ) T A L T N DIR ECT~COST S~=
O
              CONTINGENCY
8672172.
                                                              52033033.'
              TOTAL HORSEPOWER
  13787.
             ~C0STVcrotiTARS~PER KILOWATT
   52. T) 3^

-------
PLANT NAf,C-
STO  1000  LS
IMLW
                    	-CIIRE.CT  C05TS----
         CONVEYORS
         BALL HILLS
        ~PW.PS~XlTO
         STORAGE TANKS
                                     319856.
                                     "68lOt.'
                                     500.
                                   	22678.
                                      56689.
                                   ~l"3T938«r
         VACUUM FILTERS
         TANKS AND MIXERS
        "FIXATION rHEMICAL~~3TOKA5ir
         PUMPS AND MOTORS
        ~"STU 0 G E~P O'ND	
         M05ILE EQUIPMENT
         TOTAL C =
                                    18915«H.
    D.   PARTICIPATE REMOVAL

VENTURI SCRUBBER
TANKS
PUMPS AND MOTORS


0.
0.
o. --

         TOTAL 0 =
             COSTS FOR LIMESTONE  FGD  SYSTEM  FOR 1000 MW/0.6%  SULFUR/NEW MODEL PLANT

-------
OPERATING COSTS FOR LIMESTONE! SCRUBBING SYSTEM

A. RAW MATERIAL
LIMESTONE
FIXATION CHEMICALS
B. UTILITIES
ELECTRICITY
WATUt
REHEAT

C. OPERATING LAbOK
DlKt-CT LABOK
SUPERVISION

D. MAINTENANCE
LAUUR AND MATERIALS '
SUPPLIES

0 E. OVERHEAD
OJ PLANT
-J PAYROLL

P. FIXED" COSTS
DEPKECIATIOM
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES


"


UUANTIIT UNIT CCJiJT
10.3 TON/H 6.00 S/TON
25.4 TON/H 2.00""S7TON

10285. KW 15.0 MILLS/KWH
302.5 GAL/MIN 0.016 4/MGAL
131. <» MM BTU/H 0.76t S/MM BTU


3 MEN/DAY a. 00 3./MANHOUR
15K OF DIRECT LABOR


t& OF FIXED INVESTMENT
15S OF LABOR AND MATERIALS


SOK OF OPERATION AND MAINTEMANCE
20* OF OPERATING LABOR


5.00%
0.35^0
4.00%
0.3 %
9.00%

16.65%


TOTAL ANNUAL COST - -. .
MILLS PER KILOWATT-HOUR

ANNUAL LObl JS)
327795.
267<;ub. ' '

810910.
1603.
540400.


210240,
31535.


2U81321.
312198.


1317647.
40355.






97041bO.


15&55S74.
2.97

-------
             PLANT
STD  1000  LS    NEW
	i-.-PIRECT'CaSTS1
                "A".'   'NA2C03  PREPARATION
                      STORAGE  SIUO
VIBRATING 'FEEDER' ' " " ' 	
STORAGE TANK
AGITATORS ' -
PUMPS + MOTOR
TOTAL A =
4533.
47021.
16126. 	 - 	
1456.
117605.
                      S02 SCRUBBING
e-
                      FANS +  MOTORS
                     'PUMPS + 'MOTWS"
                      REHEATERS
                     ISOOT^DLUWETRS	
                      DUCTING
                      VALVES
                                   TT917550T"
                                      16JJ133.
                                   ~  524419.
                                     3131510.
                                   —2175488V
                                                               "28^36069.
                      PUKGE TRLATMENT
                      REFRIGERATION UNIT
                                      b09ttbl.
HLAT EXCHANGER
TANKS
UKYER
ELEVATOR
PUMPS + MOTOK
CENTRIFUGE
CRYSTALL1ZER
STORAGE SILO
FEtUEK

TOTAL C =
53167.
23104.
12140.
331 ?3H.
1019703.
1223644.
56014.
bb2U.

3314167.
                        COSTS  FOR WRT.T.MAN-T.QRn FGD  SYSTEM FOR 1000  MW/0.6%  SULFUR/NEW MODEL  PLANT

-------
                      D.    REGENERATION

PUMPS + MOTORS
EVAPORATORS + REBOILERS
HLAT EXCHANGERS
TANKS
STRIPPER
BLOWER
TOTAL 0 =

E. PARTICIPATE REMOVAL

VtNTURI SCRUbbtK
TANKS
PUMPS + MOTORS

TOTAL E =

TOTAL INSTALLED DIRECT COST =

O
U)

2b2«*33.
28i7<*|*5.
367919.
<»7fa99.
103b2b.
119700.
3708721*.



0.
0.
0.

D.

35476567.



O

-------
 IMTFULST  UUKIluG  COUSTHUCTlON              ib"«7bbf>.
 FJCLD  LABOK  AND  EXPENSES                  35H7656.
 CONTRACTORS  FEE  AND  EXPANSES              1773028.
 ENGINEERING                                3547656.
 FREIGHT                                     <*H3457.
                                       ---- 1D64297.-
SPARES                                      177382.
TAXES               "           '"•            532116.
ALLOWANCE  FOR  SHAKEDOWN                   1773828.
"ACID PLANT  ............ ~ .........   1661990.
 TOTAL  INDIRECT  COST  =                     16072902.
 CONTINGENCY                               10709693.
 GKAND  TOTAL
                                              8I9ST

                                              2955."
 STEAM-PROCESS  (BTU/HRJ

                                        365^532771
 COST-DOLLARS  PER  KILOWATT

-------
WELLMAN-LORD ANNUALIZEO COSTS


A. RAW MATERIALS
SODA ASH
B. UTILITIES
ELECTRICITY
PROCESS WAtER
COOLING WATER
REHEAT STEAM
PROCESS STEAM

C. OPERATING LABUK
DIRECT LABOR
SUPERVISION

D. MAINTENANCE
LABOR AND MATERIALS
SUPPLIES

9 E. OVERHEAD
I-1 PLANT
PAYROLL

F. FIXED COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXEs
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES

6. CREDITS
SULFuRIC ACID
NA2S04





"QUANTITY

O.S3 IUTJ/H

6677. KW
295^.0 GAL/MIN
1159.5 MGAL/KIN
112.5 MM BTU/H
119.6 MM BTU/H


1 MEN/DAT





50%


5.002
0.3555
1.00%
0.3 85 .
9.008 ' "

18.658"


7.43 TON/H
0.53 TON/H





UNII CU5.

55.00 S/TON

15.0 KILLS/KwH
0.001 i/MGAL
0.761 S/Mn BTU
0.764 S/MM BTU


8.UU »/l"iAlMI1K
1585 OF DIRECT LABOR


IS OF FIXEU iNVt-b 1 Plt-IM 1
155» OF LABOR AND MATERIALS


UP OPERATION AND MAINTENANCE
20% OF OPERATING LABOR








"TOTAL COST 	 "
20.00 S/TON
40.00 'S/TON ^
TOTAL CREDITS '

IMLl «NNUAU tUST
KILLS"PER KILOWATT-HOUR

ANNUAL tUiil ( * J

155768.

526191.
17612.
16993.
601147.


12048.


385556.


64473.






11984371.

1U857131. "
781833.
113286.
-- - • - - 895119. 	 	 - -

' 	 17962011.
A. HI

-------
PLANT NA«E-
STO 1000 LS RETROFIT
	 	 DIRECT COSTS----

" A". '"NA2C03 PREPARATION 	
STORAGE SILO
VIPHATING FEEDER
STORAGE TANK
AGITATORS
PUMPS + MOTOR
TOTAL A =

B. S02 SCRUBBING

AbSORdERS
FANS •»• MOTORS
PUMPS + MOTORS
REHEATERS
SOOT bLOWERS
DUCTING
VALVES

TOTAL & =
1
I^J C. PURGE TREATMENT
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
DRYER
ELEVATOR
PUMPS "+ "MOTOR
CENTRIFUGE
CRYSTALLIZER
STORAGE SILO
FEEDER

TOTAL c =

COSTS FOR WELLMAN-LORD



5<*617.
5007.
55096.
18703. " 	 	
1762.
135107.



197070.
3559187!
239232U.
3122356.
2639070.

S59ZMS*.


579183.
8b922.
59974.
25639.
13350.
377030.
1156966.
1390760.
6685.

3771728. 	

FGD SYSTEM FOR 1000 MW/0 .£%-SULFUR/RETROF"fr MODEL PLANT

-------
D.   REGENERATION

PUMPS + hOTOKS
EVAPORATORS + REBOILERS
HEAT EXCHANGERS
TANKS
STRIPPER
BLOWER
TOTAL D =

E. PARTICIPATE REMOVAL

VtNTURI SCKUbBtK
TANKS
PUMPS -t- MOTORS

TOTAL E =

TOTAL INSTALLED DIRECT COST =


1

283310.
3204267.
418570.
53655.
11571H.
136160.
4211696.



0.
0.
u.

0.

»«HW067.




-------
           	INDIRECT COSTS	
 INTEREST DURING CONSTRUCTION
 FIELD LABOR AND EXPENSES                   4666671.
 CONTRACTORS FEE AND EXPENSES               233H335.
 ENGINEERING~~ 	   ""        <*'^92'*9^.
 FREIGHT                                     550550.
-"OFFsftE	1321522."
 SPARES                                      220220.
"TAXES            	~" "                    660661.
 ALLOWANCE FOR SHAKEDOWN                    2202203.
"A'CIIT PLANT'"  ~"		
 TOTAL INDIRECT COST =                     22553910.
 CONTINGENCY                               13319595.
 GRAND TOTAL                               79~9T7573T
"PRDTESS
 STEAM-PROCESS (BlU/HR)                   1547701701)^

"TTOOLING WATER rG~ATIS7YR)'377996"51"65."

 COST-DOLLAHS PER KILOWATT	79T9I"

-------
WELLMAN-LORD ANNUALIZEO COSTS


A. RAW MATERIALS
SODA ASH
B. UTILITIES
ELECTRICITY
PROCESS WATER
COOLING WATER
REHt-AT STEAK
PROCESS STEAM

c'. OKE.NATIN& LABOR
DIKLCT LABOK
SUPERVISION

0. MAINTENANCE.
LAHOR AND MATERIALS
SUPPLIES
0
1 e. OVERHEAD
.&.
1/1 PLANT
PAYROLL

F. FIXt-D COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES

G. CREDITS
SULFuRIC ACID
NA2SQ4





UUANTITY UNII COS!

0.55 TON/H 55.00 S/TON

6899. KW 15.0 MILLS/KWH
3056.3 GAL/MIN ~ U.018 i/MUAL
1199.3 MGAL/MIN 0.004 S/MGAL
147.3 MM BTU/H U.fb4 */nn UIU
154,7 MM BTU/H 0.764 S/MM BTU


4 MEN/DAT B.UO */l"l«UnK
15K OF DIRECT LABOR


4% OP FIXLU ilMVt-S 1 MtlM 1
15B OF LABOK AND MATERIALS


50% OP OPERATION ANU PIAlNTt-NANCL
2058 OF OPERATING LABOR


5.00%
0.35%
4.00%
0.3 %
9. DOS

16.65%

TOTAL COST
7.69 TON/H 20.00 S/TON
0.55 TON/H 40.00 S/TON
TOTAL CREOI-TS

	 - NLT ANNUAL COST
MILLS PLK KILOWA1 1 -HOUK

ANNUAL COS 1 1 * >

lbll.30.

543983.
io^ib.
17576.
DyiiU'+b.
621919,


cou 3^0 .
4204S, "


3i^b ^U«i ,
479505.


ivy^iiaB.
64473.






14904627.

22921ttbU.
808849.
11 ^Ud. -
926049.

-~ - - 21995810". - -
4. 10

-------
0.   REGENERATION

PUMPS * MOTORS
LVAPORATORS * REBOIUERS
HtAT EXCHANGERS
TANKS
STRIPPER
BLOWER
TOTAL D .=

E. PARTICIPATE REMOVAL

VENTURI SCRUbBLR
TANKS
PUMPS + MOTORS

TOTAL E =

TOTAL INSTALLED DIRECT COST =

(•}
1
*>.

716100.
10638067.
1<*30590.
117917.
200011.
<+6b<»36.
13766953.



u.
0.
0.

0.

46273606.




-------
       ~PLANT~N"AME>
       STD  1000 HS NEW
            	DIRECT COSTS-
            A.~~~~TJA2C03~ PREPARATION"
                 STORAGE SILO
                 STORAGE TANK
                 AGITATORS
                 TOTAL A =
                                           150506.
                                           ~  «*557."
                                            81307.
                                            16126.
                                           253955.
                 S02 SCRUBBING
n
"ABSORBTRS"
 FANS  -f  MOTORS
 PUMPS" "T'fioiroRS	
 REHEATERS   	
"S 0 0 T " BL'O SIR'S
 DUCTING
                 VALVES

                ~fOTAL~B~^~
                                                         1791765U.
                                                           Ibbl33.
                                                          3131510.
 2099911.
"23219567
                                         28336069;
                 PURGE TREATMEN1
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
DRYER
ELEVATOR
PUPiPS + MOTOR
CENTRIFUGE
CRYSTALLIZER
STORAGE SILO
FEEDER

TOTAL C =
509851.
76177.
67056.
12140.'
776756. . ... .
1019703.
182715!
5532.

3914620.
                   COSTS FOR WELLMAN-LORD FGD SYSTEM FOR  1000  MW/3.5% SULFUR/NEW MODETj-PLANT

-------
                           	INDIRECT COSTS	
                 INTEREST DURING CONSTHUCTION
                 FIELD LABOR AND EXPENSES
                 CONTRACTORS FEE AND EXPENSES
                "ENGINEERING—	""'		
                 FREIGHT
                •OFFSITE	
                 SPARES
                "TAXES"
                 ALLOWANCE FOR SHAKEDOWN
                 ACTO PLANT	
     4627360.
     4627360.
     2313fa80.
     4627360.
      576420.
   "'1388208;'"
      231368.
      69110"+.
     2313680.
     3740331*.
                 TOTAL INDIRECT COST =
    25141877.
                           ******************** ******~* * 
.. 	^925.

	9305.
                 COST-DOLLARS PER
                                                               65~.~69~ "

-------
                                        WELLMAN-LOKU
                                                                 COSTS
                                  QUANTITY"
JTT~C~05T
TINMUAL COSriS)
A.  RAW MATERIALS
SODA ASH
B. UTILITIES
ELECTRICITY
PROCESS WATER
COOLING WATER
REHEAT STEAM
PROCESS STEAM

C. OPERATING LABOR
DIRECT LABOR
SUPERVISION

D. MAINTENANCE
LABOR AND MATERIALS
SUPPLIES
o
1 E, OVERHEAD
^ PLANT
PAYROLL

F. FIXED COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES

6. CREDITS
SULFuRIC ACID
NA2SQ4



2.09 TON/H 55.00 S/TUN

9595. KW 15.0 MILLS/KWH
93o5.9 GAL/MIN 	 o.oie WMOAL
3730.1 MGAL/MIN 0.001 t/MGAL
112.5 MH BTU/H 0.761 »/MM 8TU
581.6 MM BTU/H 0.761 $/M» BTU


1 MEN/DAY 8.00 5/MANHK
15* OF DIRECT LABOR


1% OF FIXED INVt.5 1 MLNI
15S> OF LABOR AND MATERIALS


50ft OF OPERATION AMU MAINTENANCE
20% OF OPERATING LABOR


5.00%
0.35%
1.00%
0.3 8
9.00%

18.65S

TOTAL COST
28.91 TON/H 20.00 */TON
2.09 TON/H 10.00 S/TON
TOTAL CREDITS

	 NET ANNUAL COST
fcUDbfb.

756500.
bb1b&.
51671.
572821.
2337159.


12018.


511191.


2132251 .
61173.






15982785.

-2GS26612.
3010025.
110193.
"3180518.

23316091.

-------
PLANT NAME-
      STO 1000 HS RETROFIT
          - --- DIRECT' COSTS-
NA2C03 PREPARATION
STORAGE SILO
VIBRATING FEEDER 	 '
STORAGE TANK
AGITATORS
PUMPS + MOTOR
170717.
5012.
95253.
18703. ------
1762.
        TOTAL  A =
                                        29l<+«*9.
    8.
S02 SCRUBBING

AbSORBERS
FANS + MOTORS
PUMPS + MOTORS
REHEATERS
SOOT BLOWERS
DUCTING
VALVES

TOTAL 6 =
1
Ul
VJ C. PURGE TRLATMtNT
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
DRYER
ELEVATOR
PUMPS + MOTOR
CENTRIFUGE
CKYSTALLIZER
STORAGE SILO
FEEDER


25Hl9<*Oy.
197070.
596UHU.
3559187.
2392320.
3122356.
2639070.

35925H3H.


579H83.
86922.
75171.
13i50.
883270.
1156966.
1390760.
227908.
6691.

TOTALC =
 COSTS  FOR WELLMAN-LORD FGD SYSTEM FOR 1000  MW/3.5% SULFUR/RETROFIT-MODEL PLANT

-------
                0.    REGENERATION
                    PUMPS + MOTlJRS
                    EVAPORATORS + REBOILE8S                  12i27b92.
                   ~HL AT~rxEH AGGERS	' 1627125.
                    TANKS                                       132668.
                   "STRYPFTR	~	
                    BLOWER
0
Ul
                    TOTAL 0 =                                15650115.
               E.    PARTICIPATE REMOVAL

VtNTURI SCKUbBEK
TANKS
PUMPS + MOTORS


0.
0.
0.

                    TOTAL E =
                    TOTAL INSTALLED DIRECT COST =             56335885.

-------
                            ----1NUIKLC1 tUSIS—--
                  INTEREST DURING CONSTRUCTION              5fa33b88.
                  FIELD LABOrt A\D EXPENSES                  5971603.
                  CONTRACTORS FEE AND EXPENSES              2985601.
                  "ENGINEERING     	      "      """'      5746.>60.
                  FREIGHT  	                             704196.
                  ~OFFSITE~              ""  ~"  ""        """1690076.
                  SPARES                                     281679.
                  "TAXES           	 "~    "  ' "    "         8<»503fi.
                  ALLOWANCE FOR SHAKEDOWN                   281b79t.
                  "ACID PLANT		  	  	  "	3816678.
                  TOTAL INDIRECT COST =                     30491719.
                  CONTINGENCY                               17365520,
                  "BRAND TOTAT

I
Ol
                                                               10252T

                                                                9626T"
                  STEAM-PROCESS  (BTU/HR)601755000.

                                                         12161839060."
                                   KILOWATT

-------
WLLLMAN-LUKU  ANNUALI2EU  CUliTb














n
i
(Jl
(0


















A. RAW MATERIALS
SOOA ASH
B. UTILITIES
ELECTRICITY
PROCESS WATER
COOLING WATER
REHt-AT STEAM
PROCESS STEAM

C. OPEKATING LABOR
DIRtCT LABOR
SUPERVISION

D. MAINTENANCE
LABOR AND MATERIALS
SUPPLIES

E. OVERHEAD
PLANT
PAYROLL

F. FIXED COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FTXED CHARGES

6. CREDITS
SULFuRIC ACIO
NA2S04





HUANTITY UNI I CUbl

2.16 TON/H bS.OO */TON

9911. KW 15.0 MIULS/KWH
9626.1 GAL/MIN "O.Olfl S/MGAL
3B58.8 MGAL/MIN 0.00^ $/MGAL
147,3 MM BTU/H Q.tbH S/Hfl b 1 U
601.7 MM BTU/h 0.764 S/MM BTU


4 MEIM/OAT 8. 00 S/MANHK
15* OF DIRECT LABOR


48 OF FIXED INVt-blMLNI
15X OF LABOR AND MATERIALS


50K OF OPERATION ANU HAINTLNAIMCL
20% OF OPERATING LABOR


5.00%
0.35%
4.00S5
0.3 %
9. DOS 	

18.65K 	

TOTAL COST
29.91 TON/H 20.00 S/TON
2.16 TON/H 40.00 */1UN
TOTAL CREDITS

Nt-T ANNUAL COST 	
MILLS PLK KILOWAI I-HOUK

ANNUAL COSI ( S)

b26bb3.

731673.
57374.
56552.
d^^UHb.
2416061.


2uuo<:u .
42048. .


4167 f 23.
625158.


2bb/b^>b.
64473.






19432017.

31701641.
3144853.
4!3Dbtt2.
"" " 3600536.

23101104.
i>.34

-------
PLANT
STD  bOO LS   NLW
     	DIRECT COSTS-
A. NA2C03 PREPARATION
STORAGE SILO
VIBRATING FEEOE.K
STORAGE TANK
AGITATORS
PUMPS «• MOTOR
TOTAL A =

B. S02 SCRUBBING

ABSORBERS
FANS + MOTORS
PUMPS + MOTORS
REHEATERS
SOOT BLOWERS
DUCTING
VALVES

TOTAL B =
o
1
- C. PURGE TRLAICItNF
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
DRYER
ELEVATOR
PUMPS + MOTOK
CENTRIFUGE
CRYSTALLIZER
STORAGE SILO
FEEDER

TOTAL C =
COSTS FOR WFT,T.MAN-T.ORn FfJD '

31389.
36450.
16126.
89976.



170675.
271008.
1616297.
1006379.
999947.

14413509.


263460.
39522.
32779.
12140.
526960.
3610ft!
5b27.

1714863.
^VQTFM Pop ^QO MW/Q 6^ SULFUR /NEW MODFT PT ANT

-------
                D.
                    EVAPORATORS + REBOILEKS
                    HEAT EXCHANGERS	"'
                    TANKS
                    STRIPPER
                    BLOWER
                                                                T795TTT'
  190316.
   30737.
   75650.
   61918.
                    TOTAL 0 =
 2006275.
               E.    PARTICIPATE REMOVAL

VEWTURI SCKUbbER
TANKS
PUMPS + MOTORS


U.
0.
0.

                    TOTAL E =
                    TOTAL INSTALLED DIRECT COST =
182516'+'+.
 O
~~
-tn-

-------
                             	IfvDIRECT COSTS	
                   INTEREST DURING  CONSTRUCTION              1825461.
                   FIELD LABOR  AND  EXPENSES                  16254&1*.
                   CONTRACTORS  FEE  AND  EXPENSES               912732.
                  "ENGINEERING" ........ ~ -----------------     '  " 1825464.
                   FREIGHT   _          _               22al83.
                                                               547639.
                   SPAKES                                       91273.
                  "TAXES                           ........... 273619.
                   ALLOWANCE FOR  SHAKEDOWN                    912732.
                   "ACItrpL'A'NT --------------------- ...... ------- ....... ~  ----- 1124063.
                   TOTAL INDIRECT  COST =                     9566836.
                              ****** *fi ******** *-*•*-*-*-****•**•***•*•*-* *"
                   CONTINGENCY                                5564296.
                   GRAfJTJ" TOTAL                               53"3"85777.
Q                             ***********************************

ui
                                                                  4955.'
                   "STEAM-PROCESS  (BTU/HR)773850TnrT

                                  CGALS/YK)
                   C05T-DOLLAKS  PtK  KILOWATT65T7T"

-------
HELLMAN-LOKU  ANNUAL1/LU


A, RAW MATERIALS
SODA ASH
B. UTILITIES
ELECTRICITY
PROCESS kATER
COOLING WATER
REHEAT STEAM
PROCESS STEAM

C. OPEKAT ING LABOR
DIRECT LABOR
SUPERVISION

0. MAINTENANCE
LABOR AND MATERIALS
SUPPLIES
O
t^, E. OVEKHEAD
-J
PLANT
PAYROLL

F, FIXED COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES

G. CREDITS
SULFuRIC ACID
NA2SQ4




QUANTIIT UNIT COSI

0.27 TON/H 55.00 S/TON

3988. KW 15.0 MILLS/KMH
1528.1 GAL/MIN o.oio S/MGAL
599.6 MGAL/MIN 0.004 S/MGAL
73.6 MM 6TU/H U.7b4 S/i"ll"l UTU
77.3 MM BTU/H 0.764 S/P.M BTU


2 MEN/DAY 8.UO S/MAIMHK
15S5 OF DIRECT LABOR


ttf OF FIXED INVLSIMbNT
15S5 OF LABOR AND MATERIALS


50fc OF OPERATION ANU MAINTENANCE
20S OF OPERATING LABOR


5.00%
0.35X
4.00»
0.3 %
9.005S 	

16.658)

TOTAL COST '
3.64 TON/H 20.00 S/TON
0.27 TON/H 40.00 S/TON
TOTAL CREDITS

	 NET ANNUAL" 'COST

ANNUAL CUi> 11%)

80575.

314422.
9108.
6768.
310959.


IHUlbU .
21024.


200314.


3223b!






b22fa447.

»o*aSa7.
404424.
bUbOO .
' 463024.

" 	 93609'.42.
                    MILLS PS.R KILOWAI T-HOU

-------
PLftNT NAHT-
STIJ  *it)0 L S   KI.THOF IT
   	DIRECT COSTS---
A. NA2C03 PREPARATION
STORAGE SILO
VIBRATING FEEDER
STORAGE TANK
AGITATORS
PUMPS * MOTOR
TOTAL A =

B. soa SCRUBBING

ABSORBERS
FANS + MOTORS
PUMPS + MOTORS
REHEATERS
SOOT BLOWERS
DUCTING
VALVES

TOTAL B =
o
1
Ul
w C. PURGE TREATMENT
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
DRYER
ELEVATOR
PUMPS + MOTOR
CENTRIFUGE
CRYSTALLIZED
STORAGE SILO
FEEDER

TOTAL C =

- 	 - .
34968.
5007.
42520.
18703.
1602.
102800.



200909.
1814261.
1196161).
3212564.
1121033.

19786570.


295386.
44307.
36555.
22242.
13350.
195061.
590772.
708926.
6664.

1959966,

        COSTS  FOR WELLMAN-LORD_F.QD _SYSTEM_EQR_500 MW/Q.6%  SJILEUB/EETBQPJLT..MQDEL^PLANT_.

-------
              D.   KLGLME.KATION
                  "PUMPS "V MOTORS" ~ "                         199650.
                   EVAPORATORS  +  KLBOILEKS                   1649861.
                   HEAT EXCHANGERS                            213973.
                   TANKS                                        34303,
                   STRIPPER    "	"'  ~   """        ~	       ""84065.
                   BLOWER                                       69615.
                  TOTAL D  =                                  2251468.
                  PARTICIPATE  REMOVAL
                 •'VENTURT'SCROBBER—		 	•	0.
                  TANKS                                             0.
                 ' "PUMPS > MOTORS                    "       	~"~o.
                  TOTAL  E  =                                         Oi"
                   TOTAL  INSTALLED  DIRECT COST =             24100808.
 I
01
vo

-------
	INDIRECT COSTS	

IMERtST DURING CONSTRUCTION
FIL.LU LABOR AND EXPENSES
CONTRACTORS FEE AND EXPENSES
ENGINEERING
FREIGHT
OFFSITE
SPARES
TAXES
ALLOWANCE FOR SHAKEDOWN
ACID PLANT

TOTAL INDIRECT COST =



CONTINGENCY

GRAND TOTAL
ft**************************!
1
85.
1277442.
21*58262.
301260.
723024.
12U501*.
36X512.
1205040.
1139002.

125b()735.


1
7330308.

"ti^aiaai.
r***«4t**


5050.
1561.
79116424.
193103695b.
87.96

-------
                                                 WELLMAN-LORO ANNUALIZED COSTS
"AT "RAH MATERIALS

--- SOOA~ASH ------
UTILITILS_

ELECTRICITY
PROCESS WATER
COOLING WATER
REHTAT"SrCAH
PROCESS STEAM
                                  QUANTITY
                                              0.28 TON/H
                                      4065.   KW
                               1561". 2"  GAL/MIN ...........
                               612.6  MGAL/MIN
                                 75".T~~MH "BTU/R
                                 79.1   MM  BTU/H
                                                            UNIT COST
                                                           55.00 S/TON
                                                          15.0  MILLS/KWH
                                                            0.018   $/MGAL
                                                            0.004   i/MGAL
                                                          "OV76* '$/««  BTU
                                                          0.76H  S/KM  BTU
                                                                                                   ANNUAU'COSTm
                                                                                                            82380
                                                                                                           320521.
                                                                                                             9305.
                                                                                                             6.979.
                                                                                                           101789.
                                                                                                             L7925.
        ~CT. — 10PEKATING" LABOR
             SUPERVISION
                                                        6 T
                                                    isss OF DIRECT  LABOR
                                                                                                             2102"*.
n
            "MAINTENANC
     pfB'OR AND MATERIALS
        "E.
                                                  *8 ~OF FI XETJTTNVErSTT'iENT
                                                15K OF LABOR AND  MATERIALS
                                                                                                          T759Z7TT
                                                                                                           263691.
                                            5TnrnCTF~CrPERST 1 0"N~~ATNfD~fl ATNTEWANCE
                                                                                                           109217^7
                                                                                                             32236*
DEPRECIATION
INTERIM REPLACEMENT
TAXES
C AP I t ffLTCOSf S
                                              5.00'iS
                                              0.35K
                                              >r.6Q%
                                              ?*3 a
                                              9TOOS
                                                                                                  B2T52615.

                                                                                                  T2552278;
TOTAL FIXED CHARGES
         G.  CREDITS
SULFuRIC ACID
                                             18.6bS
                                                                 TOTAL  CO^T
                                             3.93  TON/H
                                                                  20.00   S/TON
                                                                  40.00 - S/TON
                                                                                                            413483.
NA2S04
                                                 TON/H
                                                   TOTAL "CREDITS

                                                   N£T-ANNUAC--COST
                                                                                                            4T3396

                                                                                                          T2T0788S2
                                                                MILLS  PLR KILOWATT-HOUR
                                                                                                               4.39

-------
PLANT NAME-     STD   500   HS  NEW
        "MA2C03  PREPARATION"'
         STORAGE  SILO                                84177.
        •VlbR-ATTNtrFEEDTR	
         STORAGE  TANK        	                     62063.
        "AGITATORS	~  16126.
         PUMPS  +  MOTOR
         TOTAL  A  =                                  160379.
         S02  SCRUBBING
ABSORBERS
FANS + MOTORS
PUMPS •»• MOTORS 	
REHEATERS
SOOT BLOWERS
DUCTING
VALVES

- 9259457. -•• 	 ' ....
17CI67b.
2/1U08.
1616297.
' 108 //44. .
1006379.
999947.

                REATHEN1
         REFRIGERATION UNIT	            263480.
        "HEAT' EXCHA"N~GO~                              39522.-
         TANKS	!*3.2.96 •
         OR Y E~R                                      2 9 2 627"
         ELEVATOR                                    12140.
        "PUMP S~^fiOTO"R	
         CENTRIFUGE                                 526960.
        TRYSTACLTZETJ	6323537"
         STORAGE  SILO                               102191.
         FEEDER                                       5529,
         TOTAL  C  =
          COSTS FOR WELLMAN-LORD  FGD SYSTEM FOR 500 MW/3.5%  SULFUR/NEW MODEL  PLANT

-------
                D.    REGENERATION

' PUMPS + MOTORS
EVAPORATORS + REBOILERS
HEAT EXCHANGERS
TANKS
STKIPPER
BLOWER
TOTAL D =

E. PARTICULATE REMOVAL

VLNTURI SCRUBBER
TANKS
PUMPS + MOTORS

TOTAL E =

TOTAL INSTALLED DIRECT COST =

n
— i 	

1+19132.
5632131.
739960.
76000.
210743!
7253007.



0.
0.
u.

u.

23693666.


U)

-------
                              	INDIRECT COSTS	
                    INTEREST DURING CONSTKUCTION
                    FIELD LABOR AND EXPENSES
                    CONTRACTORS FEE AND EXPENSES
                    ENGINEERING—	   	"
                    FREIGHT
                   ""6TFSITC
                    SPARES -
                   ~TAXES  ~~
                    ALLOWANCE FOR SHAKEDOWN
                   ~AC ID "PLANT
                    TOTAL INDIRECT COST =
                                2389368.
                                2389368.
                                2389368.
                                 296671.
                                 71o810Y
                                 358105.
                                119'r&e1».
                                2525059.
                               13575890.
                             -*-*-* ****** K
                    CONTINGENCY
                                7H93915.
O
 I
                    GRAND TOTAL
***********************************
                     OTA"C~HORSCPOWER—FOR
                                                                  4813T
                    STLAM-PROCt-SS (BTU/HRJ

                   "COOLIN& WATLK (
                               SU Q8775U0.
                        -UULLAKS> h-LK KIUOWATI

-------
WLLLMAN-LOKU   ANNUALIZEU














o
1
CTi


















A. RAW MATERIALS
SUUA ASH
8. UTILITIES
ELECTRICITY
PROCESS WATER
COOLING WATER
REHLAT STEAtf
PROCESS STEAM

C. OPERATING LAbOK
DiKt-CT LAbOK
SUPERVISION

D. MAINTENANCE
LABOR AMD MATERIALS
SUPPLIES

E. OVEKHEAU
PLANT
PAYROLL

F. FIXED COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXEO CHARGES

G. CREDITS
SULFUKIC ACID
NA2S04





UUAN 1 I 1 T UINI I LUd 1 »IMNuAl_l,Ui>^(3>)

l.UB TON/H " 53.00 i/TON 313281.

5495. KW 15.0 MILLS/KWH 433238.
4813.0 GAL/MIN 	 0.018 i/MGAL 2BSU7.
1929.4 MGAL/MIN 0.004 S/MGAL 28276.
73.6 Ml"! bTU/h U./64 s/rtri mu iiybU2i.
300.8 MM BTU/H 0.764 S/HM BTU 1209030.


2 HLN/UAT tt.Ou i/ilAlMnR 1401bU.
15« OF DIRECT LABOR 21024.


HIS l^ (-IXEU INVESTMENT l/9t>5a9.
15iS OF LABOR AND MATERIALS 269780.


50fc OF OPERATION AND MAINTENANCE 1114/bii.
20* OF OPERATING LABOR 32236.


5.00%
0.35S
4.00SJ
0.3 %
9.00ft

10.65% aieab^i.

TOTAL COST 	 14u70723.
14.95 TON/H 20.00 S/TON 1572426.
1.06 TON/H HO.UO */TOI\i Z2IB1*!,
TOTAL CREDITS 1600268.

(JET ANNUAL COST ' "' "" " " 12270454.
M1LL6 HtK KILOWA 1 1 -HOUK H.Ob

-------
PLANT  NAME-
           SOO   US  KE.TKUHT
          	DIRECT"COSTS---
        'NA2C03 PREPARATION
         STORAGE SIUQ	
         VIBRATING FEEDER
        _STORAGE: TANK
         AGITATORS
         PUMPS * MOTOR
         TOTAL A =
                                          94276.
                                          —5W9T
                                          7235"*.
                                          18703.
                                           1762.
                                         192106.
    B.
S02 SCRUBBING
ABSORBERS
FANS + MOTORS
PUKPS + MOTOKS
REhEATERS
SOOT BLOWERS
DUCTING
VALVES

TOTAL B =
O
1
(Tv
11957613.
200909.
30402b.
1814261.
119&160.
321256H.
1121033.

1978btj/0.

         PURGE THt-ATMENl
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
DKYER
ELEVATOR
PUMPS + MOTOR
CENTRIFUGE
CHYSTALL1ZER
STORAGE SILO
FEEDER

295386.
14307.
46220.
32496.
13350.
4S3669.
590772.
706926.
125859.
bb87.
.
         tOTAlT~C =
                                        "23T9676T
          COSTS FOR WELLMAN-LORD FGD SYSTEM  FOR  500_ MW/3_._5% SULFUR/RETROFIT MODEL PLANT

-------
                0.    REGENERATION
                   "PUriPS" V MOTORS                             " H6B103.
                    EVAPORATORS + REBOILEKS                    6327863.
                    HEAT EXCHANGERS  	-••-••                  831505.
                    TANKS                                         64769.
                    STRIPPER                 	       "      	161179.
              	SLOWER	270526.

               	TOTAL__D_ =	                  81«HK>"»a.



               E.    PARTICIPATE REMOVAL	


                    VENTURT^SCRUSBETR"""	          ~	"    ''  0.
              	  TAfJKS           	    	                  0.
                    PUNrpS"";T"M"OTOR'S"                             	  " 0.

                    TO'TAL E =                                         o~;"




                    TOTAL INSTALLED  DIRECT COST =             3Cm2t01.
 O
_!_
 en
 -j

-------
           	INDIRECT COSTS	
 UJTEPEST DURING CONSTRUCTION
 CONTRACTORS FEE AND EXPENSES
"ElvGlNEE
 FREIGHT
 OFFSITE
 SPARES
 ALLOWANCE FOR SHAKEDOWN
~ACIU PLANT
 304-+240.
"3226094.-
 1613447.
"3105121*.-
  360530.
  152212.
  1*56636."
 1522120.
 TOTAL INDIRECT COST =
16972300.
           ***********************************
 CONTINGENCY
 GRAND TOTAL
56897642.
**********************:
1
CM
00
TOTAL HORSEPOWER FOR PLANT
PROCESS WATER (GAL/MINI)
STEAM-PROCESS (faTU/HR)
COOLING WATER (GALS/YR)
COST-DOLLARS PER KILOWATT
*************


5960.
4917.
307456687.
6212841784.
113.79

-------
                                         tJELLMAH-LORD ANNUALIZED COSTS
                                   QUANTITY""
~A".~  R'AW MATERIALS

	SODA ASH"	'~
                                      1.10 TON/H
                                                                  UNIT  COST
            55.00 S/TON
                                      "ANNUAL"
                                                                                            	320132;	
B. UTILITIES
ELECTRICITY
PROCESS WATER
COOLING WATER
REHLAT STEAM
PROCESS STEAM


- - - ^9-17.3
1971.2
75.1
307.4

5604. Ktg
' GAL/MIN 	
MGAL/HIN
MM-BTU/fi —
MM 8TU/H

15.0 MlLLS/K'rfH
~ ' - 0.018 5/MGAL "
0.004 4/MGAL
"'" STfCf" '$XPIM"BTO
0.764 $/MM BTU

441&56.
------ -•- • 29309". '
23689.
1235468.
'IT.   "OPERATTNG'OBOR"
    T5TR E c"T~O B 0 ft~
     SUPERVISION
                                    2  HEN/DAY
    	STOTJ  $/RA"NHR
     15K OF DIRECT LABOR
	rro-160—
        21024.
~D7~"MArNTEWAWC'E~
     LATJCR SNO MATrRTATTS"
     SUPPLIES
	4 ST~0"F"FIXETJ 'TlWrs TM E NT	
 158  OF LABOR AND MATERIALS
                                                                                                     341385.
Q
1
(Ti











E. OVEKHEAO
PLANT
PAYROLL

F. FIXLD COSTS
DEPRECIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES

G. CREDITS


50» Of OPERATION ANU MAINTENANCE 1^8^237.
20» OF OPERATING LABOR 32236.


5.00%
0.35%
4.00%
0.3 %
9.1)0%

18.65% 1061141U.

TOTAL COST 17ib6&05.
     SULFURIC ACID
                                    15.28   TON/H
             20.00   S/TON
                                                                                                    1606810.
NA2SQ4 1.10 TON/H 40.00 S/7UIM
"TOTAL CREDITS

NLT ANNUAL COST
.ii^ti^-.
	 - 1839634.

153291/1.
                                                         MILLS  PE.K  KILOWAn-HUUK
                                                                                                        t>.

-------
PLANT NAME-
STD
 250  LS  NEW
-=•-"01R E C T C OSTS •
A. NA2C05 HKEHA «TlUN
STORAGE SILO
VltiR'ATING FttULK
STORAGE TANK
AblTATORS
PUMPS * MOTOR
TOTAL A =

B. S02 SCRUBBING

AttSOKBt-Hb
FANS + MOTORS
pu^ps +• MOT OKS
REHEATERS
SOOT BLOWERS
DUCTING
VALVES

TOTAL B =
0
-J
C. PUKbL 1 Rt-A ll"ltNl
REFRIGERATION UNIT
TANiKS
ORYER
ELEVATOR
PU'^PS •»• MOTOK
CENTRIFUGE
CRYSTALLIZE.K
STORAGE SILO
FEEDER

TOTAL C =


22155.
2630o!
ifaliifa.
1156.
72891.



HI?l55l!
I3bbo3.
827536.
1197871
Slliifa.

rdtiub^i.


131731.
2021U.
20999.
Idbll.
12110.
269168.
2726o!
bb27.

923570.

       COSTS  FOR WELLMAN-LORD FGD SYSTEM FOR 250 MW/0.5% SULFUR/NEW MODEL J?XANT

-------
                  D.    REGENERATION
                     "PUMPS'"*" MOTORS		"  	
                      EVAPORATORS * REBOILEKS                     757m3.
                      HEAT EXCHANGERS                              97289.
                      TANKS                                        19651.
                      STRIPPER	    	 "~ ~             55299.
                      BLOWER                                       31652.
                      TOTAL D =                                  1095525.
                 E.    PARTICULATE REMOVAL
                    " VENTURI'SCRUBBER	'	  —	 '-   0.
                      TANKS                                            0.
                    ""PUMPS"* "MOTOR'S	"" ""      	    0 ."
                     TOTAL E =	0V
                      TOTAL INSTALLED DIRECT COST =              9H72616.
Q

-------
           ---- INDIRECT COSTS ----
 INTEREST DUftING CONSTRUCTION
"FIELD LABOfT'AND 'EXPENSES — "
 CONTRACTORS FEE AND  EXPENSES
 FREIGHT
  947261.'


  116407.
 OFFSITE
 SPARES
TA-XTS	
 ALLOWANCE FOR SHAKEDOWN
 'ACID PLANT	
   47363.

  473630.
 TOTAL INDIRECT COST  =
 5134633.
 CONTINGENCY
 2921450.
T5KAND TOTAL
I7b287DO.
"TOTAL HORSETPOWEK"F0«~PrAtJr

"PR0C Ess^irs TE:R~ r GTALV PTT R-J	
 	3249T

     78IV"
 STEAM-PROCESS  (BTU/HR)

~CUDnMC"lfffTLK  (GW.S7YRT
T03T=I5'OrrAKS~TrE7n
-------
    WELLMAN-LORD ANNUALIZEO COSTS


                                 - COST-
                                                                                                      -A NNU At"t 0 ST
           "AT "RAW MATERIALS

           	SODA—
•TJ.lt  TON/H
55.00 S/TON
                                                              -—41190.		
            B.  UTILITIES
ELECTRICITY
PROCESS WATER
COOLING WATER
RLHUT STEAM
PROCESS STEAM

C. OPt-RAI ING LABOR
DIKLCT UABOK
SUPERVISION

7fal.2
306.5
2572. KW
~ T3A'L/RIN 	 " — '
MGAL/MIN
37.6 MM bTU/H
39.5 MM BTU/H



S/TON
S/TON



PLK KILOWAI I-HUUK
206741.
jjyyofa.
236698.

5079H27.
o.ob

-------
PLANT NAML-     STU   2'jo   us   KLTKOFIT
                    	DIRECT  COSTS	
         NA2C03  PKEPARATION
STORAGE SILO
VI3RATING FLTTJLR
STORAGE TANK
AGITATORS
PUKPS •»• MOTOR
TOTAL A =
2b022.
5006.
33133.
- 18703.
1762.
63628.
         soa  SCRUBBING

ABSORBERS
FANS + MOTORS
PUMPS + KOTORS 	 "
REHEATERS
SOOT BLOWERS
DUCTING
VALVES

TOTAL B =
-J
C. PUKbt TRt-AlflErJI
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
URYER
ELEVATOR
PUMPS + MOTOR
CENTRIFUGE
CRYSTALLIZE*
STORAGE SILO
FEEDER


bl/duuy.
207948.
"157234.
933909.
	 598060. 	 •- 	 ' 	 - 	 	 	 ' 	
1733304.
SB01b2.

10393639.


152666.
22930. •
23553.
13350.
305733.
366600.
33405.
6683.

         COSTS  FOR WELLMAN-LORD  FGD  SYSTEM FOR 250 MW/0.6%  SULFITR/RFTROFTT MnnP!Tj PLANT

-------
KLGEM-KA1 ION
PUMPS + MOTORS • "
EVAPOKATOhS + RtBOILERS
Ht-AT EXCHANGERS
TANKS
STRIPPER
BLOWER
TOTAL D =

E. PARTICIPATE REMOVAL

VENTURI 5CKUbbt.K
TANKS
PUMPS + MOTORS

TOTAL E =

TOTAL INSTALLED DIRECT COST =

O
1
-J
1H92V6.
658917.
22069.
6170b. 	
3592t.
1230331.



0.
0.
0.

0.

1276t919.




-------
                                	INDIRECT  COSTS	
                      IMTt.RE.ST DURING CONSTKUCTION               1276191.
                    "FIELD LABOR AND EXPENSES                   1353081.
                      CONTRACTORS FEE AND EXPENSES                676510.
                    "'ENGINEERING   -•    -         •               1302021.
                      FREIGHT   	     	                       159561.
                      OFF'slTE                    	""   "  "     3B2917.'
                      SPARES                                       63821.
                    "TAXES             	  •— "~             191173.
                      ALLOWANCE FOR SHAKEDOWN                     636245.
                     "A'CI'D" PLANT                      	" 	    767861.
                      TOTAL INDIRECT COST =                      6812053.
                      CONTINGENCY                                3915391.
                      G^AND TOTAL
...                               I****************************:******
                      rOTSITTfORSEPOUIER-FOR-FCANT	3319 r
                     ~PRtrCT5S~~W7Tr ER~T"G7ir7KTTn                        8 0 6T"
                      STEAM-PROCETSS (BTU/HFTJ

                                                               997153669T'
                     "COST-DOLLARS PLR KILOVR

-------
WELLMAN-LORD ANNUALIZED COSTS


A. RAW MATERIALS
SODA ASH
B. UTILITIES
ELECTRICITY
PROCESS WATER
COOLING WATER
REHEAT STEAM
PROCESS STEAM

C. OPERATING LABOR
DIRt-CT LABOR
SUPERVISION

D. MAINTENANCE
LABOR AND MATERIALS
SUPPLIES
O
^ E. OVERHEAD
PLANT
PAYROLL

F. FIXED COSTS
DEPKE.CIATION
INTERIM REPLACEMENT
TAXES
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES

G. CREDITS
SULFuRIC ACID
NA2SQ4




UUAN1 I 1 T UNI) CUS>I ANNUAL C 1 < * I

0.14 10N/H . bb.uo s/fuN 42bll.

2652. KW 15.0 MILLS/KWH 209134.
806.2 GAL/KIN 0.018 $7Ht,AL 4BUb.
316.3 MGAL/MIN 0.004 S/MGAL 4636.
38. fl MM BTU/H 0.764 S'/MH BTU 1561S1.
40.6 MM BTU/H 0.764 S/MM BTU 164062.


Z MLN/UAY 8.00 S/P1ANHK IHUlbU.
15So OF DIRECT LABOR 21024.'


15K OF LABOR AND MATERIALS 140954.


50)5 OF UPtKAlIUN AIMU MAIN 1 LNANCL biiU^lb.
20% OF OPERATING LABOR 32236.


6.66%
0.35K
o!3 %
9.00%

20.31J4 477iidbb.

TOTAL COST 7249183.
2.02 TON/H 20.00 */TON 213374.
0.14 TON/H 40.00 */TON 30917.
~ ~ 	 " ' TOTAL CREDITS " 	 244291.

Nt.T ANNUAL COST 	 	 " 7004892. '"
               MILLS  PtK  KILOWAT I-HOUK

-------
PLANT
                  '^30  HS  MLW
                  	DIRECT COSTS-

A. NA2C03 PREPARATION " "
STORAGE SILO
VIBRATING FEEDER
STORAGE TANK
AGITATORS
PUMPS + MOTOR
TOTAL A =

B. so2 SCRUBBING

FANS + MOTORS
PUMPS -f MOTORS
REHEATERS
SOOT 6LOWEUS
DUCTING
VALVES

TOTAL B =
O
1
-J
C. PUKGE TRLAI MLNI
REFRIGERATION UNIT
HEAT EXCHANGER
TANKS
DRYER
ELEVATOR
PUMPS '+ MOTOR
CENTRIFUGE
CRYSTALLIZLR
STORAGE SILO
FEEDER

TOTAL C =



19132.
17531.
1156.
119101.



171551.
l3sb83.
827538.
119787.
SllS-ifa.

7,56ofo2i.


131731.
20210.
26991.
12110.
2&9168.
60011.
bb2H.

lUtibfaii.

          COSTS FOR  WELLMAN-LORD  FGD SYSTEM_FOR _2.50._MW/_3_,_5%._SULFUR/_NEW _MODEL PLANT. .

-------
                 D.   REGENERATION
O
                    -PUMPSTT-MOTORS—:		 25663"*.
                     EVAPORATORS + REBOILERS                    269b317.
                     HEAT EXCHANGERS	                     376108.
                     TANKS                                        
-------
	INUIKLCT   COSTS	
INTEREST DURING CONSTRUCTION
FIE.LD LAbOR AND EXPENSES
CONTRACTORS FEE AND EXPENSES
ENb INEERING
FREIGHT
OF-FSITE.
SPARES .
TAXES
ALLOWANCE FOR SHAKEDOWN
ACID PLANT

TOTAL INDIRECT COST =



CONTINGENCY

GKAND IUIAL
_. ft***********************
1
CO

TOTAL HORSEPOWER FOR PLANT
PROCESS WATER IGAL/MIMJ
SltAM-PROCLSS IbTU/HK)
COOLI^G WATER (GALS/YR)
COST-DOLLARS PEK KILOWATT
1239301.
1239301. ' 	 ~ "
bl'JhSO.
123yiul.
151+912.
57179U.
61965.
103tt95.
619650.
1692ii5.

7H2H30H.



3963H6H.

zoTouT&^m
n***********


3701.
2*t60.
ISAf ^faHOH.
3108036049.
9b.l2

-------
                                         WCLLMAN-LOKU ANNUALI^LU  COSTb
                                 •-QUATJTTTY-
A. 'RAW MATERIALS

	SODA  ASH  	
                                  0.55 TON/H
                                                                  UNIT COST
            55.00 S/TON
	 160116.
B. UTILITIES .
ELECTRICITY
• "PROCESS wATER 	 '
COOLING WATER
REHEAT STEAM
PROCESS STEAM


"2160.0
986.1
37.6
153.7

3342. KW
GAL/MIN "'
MGAL/MIN
- MM BTU/H ~
MM BTU/H

15.0 MILLS/KHH
	 0.018 S/MGAL " 	 " " 	 ' '
0.001 S/MGAL
U.7fc>1 S/MM B1U 	 • '
0.761 t/MM BTU

263511.
11662. ' " - - -• -
11152.
151375.
617927.
    SUPERVISION
                                                               " S7ITANHR"	
                                                      15J5 OF DIRECT LABOR
                                               T10T6TJV"
                                                 21021.
D.  MAINTENANCE.
TTABOR~
 SUPPLIES
               fiATLRlALb
	ISrOF'FIXEO'TNVESTME-NT	
 152 OF LABOR AND MATERIALS
                                                                                                    112681.
1
00
I—1
E. OVERHEAD
PLANT
PAYROLL

bOS OF OPERATION AND MAINTENANCE b27550.
208 OF OPERATING LABOR 32236.
    "FIXED—COSTS"
    DLPKECIATIOIT
    INTERIM  REPLACEMENT
    "TAXES
    INSURANCE
    "C API T AL~C1TST3	
                                  5.00%
                                  0.35%
                                  LOOS"
                                  0.3 B
                                 -?7WE"
    TOTAL  FIXED CHARGES
G.  CREDITS
                                                         "TOTAL COST"-
                                                       ~TOTAU  CREDITS-
                                                        "NET"'ANNUWtrTCST
                                                                                               —920105T-

                                                                                               -^6-519177-
SULFURIC ACID
NA2SQ1
7.61 TON/H
O.bb TON/H
20.00
HU.UU
S/TON
*^ 1 Oi^J
803b56.
llblHU.
                                                        rlZLLb  PLK KILOwAT T-HOUK

-------
 PLANT NAME-    STD 250 HS RETROFIT
			     ----DIRECT 'COSTS-
    A. " NA2C03 PREPARATION
STORAGE SILO
STORAGE TANK
AGITATORS
PUMPS + MOTOR
55661.
...... . 5007.
55653.
	 18703.
1762.
         TOTAL A =                              136791.
         S02 SCRUBBING
ABSORBERS
FANS + MOTORS
"PUMPS + MOTORS
REHEATERS
SOOT BLOWEKS
DUCTING
VALVES

TOTAL B =
n
1
00
fj C. PUKGt lRt.AlWt.rj)
REFRIGERATION UNIT
HEAT EXCKANGLK
TANiKS
DRYER
ELEVATOR
PUMPS + MOTOR
CENTRIFUGE
CRYSTALLIZED
STORAGE SILO
FEEDER

61/43009.
207918.
157231.
938909.
173330l!
3SGlb2.

10393639.


152666.
32162,
25820.
13350.
237001.
305733.
366880.
71312.
6685.

        TOTAL c =
         COSTS FOR WELLMAN-LORD FGD SYSTEM FOR 250  MW/3.5% SULFUR/RETROFIT MODEL PLANT

-------
D,   REGENERATION

EVAPORATORS + REBOILERS
Ht.AT EXCHANGERS
TANKS
STH1PPER
BLOWER
TOTAL. D =

E. PARTICIPATE REMOVAL

VLnlURI SCRUBbEK
TANKS
PUMPS •»• MOTORS

TOTAL E =

TOTAL INSTALLED DIRECT COST =


1
CO

~<>Bflt>B.
328b875.
429466.
54582.
11713U.
139725.
4315568.



0.
0.
u.

D.

16084042.




-------
                   IMF-REST DURING CONSTRUCTION
                   FIELD LABOR AND EXPENSES
                   CONTRACTORS FEE AND EXPENSES
                   ENGINEERING"'  	"   ' —
                   FREIGHT
                  ~OT f SIT £~	
                   SPARES
                  'TAXES 		"
                  _ALLOWANCE FO_R SHAKEDOWN 	
                  ~A~C1 D" PL" ANT
                   TOTAL INDIRECT COST =
      1606404.
      170490P.
      1640b72.
       201050.
        30420.
      1725269.


      9341063.
                   CONTINGENCY
      5005021
                   GKANO TOTAL
O
oo
                   TOTAIT"HORSEPOWER- FOrTTLANT
         "3819,

         -2540.
                   STLAM-PROCESSfBTU/HR)

                  "COOtlNG
	^3209345187.

	122.04

-------
RIMNO«l-l<:t.U  two 10


A. RAW MATERIALS
bUUM ASH
B. UTILITIES
ELECTRICITY
COOLING WATER
PROCESS STEAM

C. OPERATING LABOR
DIRtCT LABCK
SUPERVISION

D. MAINTENANCE
LABOR AND MATERIALS
SUPPLIES
0
& E.. OVEKHEAD
Ul
PAYROLL

f. HXtD LUSTS
DEPKEC'IATlUR
INTERIM REPLACEMENT
INSURANCE
CAPITAL COSTS

TOTAL FIXED CHARGES

G. CREDITS
SULFuRIC ACID
NA2S04





UUANTITT UNI'I LOST

"'O'VbT TON/H " 55.00 S/TON

3447. KM 15-0 MILLS/KWH
2540.1 GAL/MIN 0.018 S/MGAL.
1018.2 MGAL/MIN 0.004 S/MGAL
38. fl MM BTU/H U./bH S/MM BTU
158.7 MM BTU/H 0.764 $/M« BTU


2 MtN/UAY 8.0U i/MANHK
15X OF DIRECT LABOR


4)5 O^ hlALCl IWVE&T|"IE!\|T
15» OF LABOR AND MATERIALS


3U% Oh UPt-KAl IUl»l Ai'^U NAlN 1 C.IMANLE.
20X OF OPERATING LABOR


0.35%
0.3 %
9.00S

20.31«

TOTAL COST
7.89 TON/H 20.00 S/TON
0.57 TON/H 40.00 S/TON
IOTAL CREDITS

" 	 ' 	 NET ANNUAL'COST"
HILLS PLK KILUWAI T-HUUR

ANNUAL COST15J

i65o^o.

271807.
1492s!
Ibbltil.
638110.


14016Q.
21024. .


lk!i!U4U5.
163060.


32236.






6196640.

9C3Vi6U.
829905.
12Q2S1.
" ' " 	 950157. " "

""• 	 CS89203.
b. Ib

-------
                 PLANT NAME-     STD  500   HS  RETROFIT
                                                                                                  PLANT  ESCALATION FACTOR-   1.214
       	A...   NA2C03  PREPARATION    	.._  _.'...


                           STORAGE SILO                                 85731.
0  			VIBHATING- FEEUER	4555.
                           STORAGE TANK                                 62607.
   	AGITATORS-  	16126..
r''                          PUttPS  + r-'OTOR                                 1456.
   	• • — — • — » — — — — — •• — ••
                           TOTAL  A =                                   170477.



~:'                    B.    so2  SCKU&BING

 CO
""en	    .	   _		AbSOKBEKS _._ 	[  9439636.
                           FANS +  MOTORS                               173999.
     —	  - 		  PUr.PS - •»- MOTuRS	27b287..
                           KEHEATtRS                                   matSS.
   	SOOT—ULOWERS	1087-Z-'*-'W-
                           DUCTING                                    25H0337.
   —			— .	VALVt-S	 2036054..
        	TOTAU-B-=	  	
   	X5969515.
             	C«	PURGE- TREATMENT-	
                           REFRIGERATION UNIT
                           TANKS
                           DhYER -----------------
                           ELF.VATOR
                          -PUMPS  + MOTOR
                           CENTRIFUGE
                           STOKAGE  SILO
                          -FtEOEB	

                          -TOTAL  C -=	
         266613.
        	.4029.1-^
          43650.
        .  2955U.
          12140.
         412550.
         537226.
         104078.
	5530.  .

	.	209850.1. __

-------
                     REGENERATION
                          _*_MQIORS..
-OT
                    EVAPORATORS + REBOILERS
                                     	7bfal<40.
                    TANKS                                         7710«t.
                    cTB Tupro	
                    BLOWER
                    TOTAL D =                                   7<»05698.
                    PARTICIPATE REMOVAL
                         R1_S£RUBBEJR	0 .•_
                    TAhKS                                             0,
                   .PUMPS <
                   JtOIAL-E-S	0_._
                    TOTAL INSTALLED  DIRECT COST =             256Hi»395,

-------
	 INDIRECT COSTS 	 	

INTEREST CURING CONSTrtUCTION
P1ELO 1 ABOR "MJ FXPFN-SFS
CONTRACTORS FEE AND EXPENSES
FKEIGHT
QFFSITE
SPARES
TAXES
ALLOWANCE FOR SHAKEDOWN
ACID PLAMT


1 TOTAL INDIRECT COST =
00


2564439.
2564439.
1202219.
320554.
126221.
1262219.


1HH16356.

           *»*»*»»*»«»*»«»*»»»»**»«*»*»**»*»»»
 CONTINGENCY
    6012550.
           ***********************************
                                         	5960.._
 PRflrr«;g MATrK
_STEAM^PROCESS...(BIU/HR)	




 COOL ING-WATER—tGAtS/JfR)	
__307H56667..
 COST-POLtftftS PER KILOWATT
         96

-------
                                         WELLMAN-LORD  ANNUALIZED COSTS
                                  -.QUANTITY.	_UNIJ_JCOST_
                    -ANNUAL_XOSTL*)_
 A.	RAW-MATERIAL S-



	SODft ASH	
S/TON
32Q132,
B. UTILITIES
ELECTRICITY
DBf\C r*Z*Z Ll A 1 r D
COOLING WATER
REHFAT RTE/\M
PROCtSS STEAM
C „ QP£R^TIWG LABnR
DIRECT LABOR
SUPERVISION
O D. MA1WTENANCE
^ LARD* ANQ MATERIALS
SUPPLIES
E OVERHEAD
PI AMT
PAYKoLL
f, FT^KU COSTS
DEPKLC1ATIOD
INTEKIM REPLACEMENT
INSURANCE
CApI^AL COSTS

... .. -TOTAu fJXED-CHARGES 	


G. CREDITS
SULFuRIC ACIO





5604. KW 15.0 MILLS/KWH
4q17 3 GAL/HIM n.018 $/MGAL
1971.2 MGAL/MIN 0.004 S/MGAL
19,7 MM BTU/H 0.7fc4 S/MM BTU
307.4 MM BTU/H 0.764 $/MM BTU

a. 00 S/MANHR
15S8 OF DIRECT LABOR

4K OF FIXED INVESTMENT
15% OF LABOR AND MATERIALS

50% OF OPERATION AND MAINTENANCE
20% OF OPERATING LABOR

s nuK
I*, 00%
0.3 %

Ifl.feSK

TOTAL COST

' 15.28 TON/H 20.00 S/TON
\t\Q TOM/H 40.00 $/TON
TUTAL CREDITS

NTT Af|fJUAL TOST
MILLS PER KILOWATT-HOUR

441856.
75447! ._ 	 .• . .
1235468.

140160.
21024.

1923012.
288451.

1186323.
32236.





8966043.

14688355.

1606810.
232B23.
1839634.

12A48721.
4.88

-------
   APPENDIX D




    BASIS OF




LIME - LIMESTONE




 PROCESS DESIGN
      D-l

-------
           BASIS OF LIME/LIMESTONE PROCESS DESIGN






     A.  Design Values



     The process design basis for the wet limestone system



used in this study was determined after review of process



designs used or proposed for use at various installations



and discussions with control system manufacturers.  Figure



D.I presents a typical process flow sheet for the wet lime-



stone process.



     The plant evaluated for illustration of design basis is



similar to the 500 MW existing model plant evaluated in this



study.  It is a single 500 MW, pulverized coal fired boiler



with a remaining life of 30 years.  The coal burned has a



heating value of 12,000 BTU/lb and a 3.5 percent sulfur



content.  The allowable sulfur dioxide emission rate is the



New Source Performance Standard Limitation of 1.2 Ib/MM BTU



of heat input.  The average annual capacity factor is 60



percent.  The plant is assumed to be meeting particulate



emission rate limitations and thus requires no additional



particulate control.



     Values of the major overall design parameters are



tabulated below:



   0 Flue gas rate: 1,500,000 ACFM



   0 Flue gas temperature: 310°F



                                D-2

-------
D
I
U)
                         REHEATER
                                     ENTRAINMENT SEPARATOR
                                                                                                                                    (TRUCK
                                                                                                                            HOPPER   03 R.R.
1
-c— •>.
TO ASH ^
DISPOSAL
POND
\
\_
1
-t — i


mf

J 	 2S 	 1
CLEAN CAS TO STACK
PLENUM
FAN
ri ii r rue ,. — • 	
1
*=-<
	 »i
VENTUR
              CE
              FROM ISP
              FROM TRAINS
          •'VENTURI CIRC. TANKS
                   EFFLUENT SLURRY SURGE
                   TANK & PUMPS
                                                                                  DEAD STORAGE PILES (30 days)
VENTURI CIRC.  ABSORBER CIRC.
TANK & PUMPS  TANK & PUMPS
                                                   ClARIFIER
                                                                                                         SLUDGE FIIATION TANK
                                                                                  FIICD SLUDGE
                                                                                           TO DISPOSAL -*J
                  Figure D.I   Typical process  flow  sheet of wet  limestone  -  SO_ scrubbing  system.

-------
   0 Flue gas pressure: atmospheric

   0 Average inlet S02 concentration: 5.54 ib/MM BTU (3.5%
     S coal)

   0 Outlet S02 concentration: 1.2 Ib/MM BTU (allowable)

   0 Reheat: 50°F above dew point  (from 125 to 175°F)

   0 Limestone consumption: 130% stoichiometric

Limestone System

     Unloading hopper: 100 ton capacity

     Dead storage pile: 17,280 tons  (30 day storage)

     Feeders, Conveyors: Capacity = 139.2 ton/hr (5.8 x
     maximum limestone flow)

     Live storage silos: 3 @ 576 tons capacity (3 days
     storage)

     Ball mills: 2-15 tons/hr capacity units

     Limestone slurry storage tank: 2 tanks @ 35,535 ft
     capacity  (24 hours storage)

     Limestone slurry feed pumps:  2 pumps/train with 1
     spare for each 2 operating pumps

     Raw water pumps: 2

     Clarifier: 3 units

     Sludge pond: 142 acre pond with 50 foot dike which
     would cover the remaining plant life of 30 years

Scrubbing System (each train)

     Fan: 1-100% unit

          Type - Double inlet centrifugal

          AP = 16.0" H20

     Absorber: type - TCA with 2 beds

          AP = 10" H20

          L/G =65 GPM/MACFM  (inlet gas to absorber scrub-
          ber)

          Slurry concentration =8%  (wt.)


                               D-4

-------
          S02 removal = 85%+

          Gas velocity =10 FPS, absorber

          Circulating tank - 10 minutes retention, absorber

          Pumps = 4/train plus 1 spare pump for each train

     Entrainment Separator: Chevron vane type

          Number passes - 2

          AP = 2" H20

          Gas velocity = 7 FPS

     Reheater: type - indirect tubular

          AT = 50°F (inlet temperature = 125°F; outlet
          temperature = 175°F)

          Heating medium - low pressure steam

     B.  Design Rationale

     The design rationale used in the study are listed
below:

   0 The unloading hopper was sized to hold 100 tons in
     order to accommodate unloading of railroad cars as well
     as trucks.

   0 The limestone dead storage pile was sized for 30 days
     storage to allow the plant to continue operating in the
     event of an interruption in the supply of limestone.

   0 The live storage silos were sized for 3 days storage.

   0 The feeders and conveyors were sized at 5.8 times the
     maximum limestone flow to allow the unloading of lime-
     stone to take place during a 40 hour week while the
     plant operates continuously.

   0 2-15 tons/hr capacity ball mills were provided and
     sized to allow the power plant to generate at maximum
     capacity while burning high sulfur content coal.  In
     the event 1 mill was out of service, the other mill
     could keep the plant operating for 64 hours.

   0 The limestone slurry storage tanks were sized for 24
     hours storage to allow the scrubbing trains to continue
     operating for 59 hours with 1 mill out of service or
     for 24 hours if maintenance required complete shutdown
     of the 2 ball mills.
                                 D-5

-------
   0  In general,  all pumps in the process are provided with
     spares.

   0  3 thickeners and a new pond (142 acres)  were used with
     diking to provide sufficient pond space for the life of
     the plant.  The thickener concentrates the effluent
     slurry from 15% solids to 30% solids and then dis-
     charges the 30% effluent slurry to the vacuum fil-
     tration units.   The effluent leaves the filtration unit
     with a slurry 60% by weight and then enters a mixing
     tank where the fixation additives are stirred in with
     the 60% slurry and then pumped to the sludge pond.

   0  A UOP* Turbulent Contact Absorber (TCA)  was selected
     for removal of the bulk of the SO?.  This unit has 2
     beds of hollow plastic spheres which move randomly
     between support grids and provide the contact area
     necessary for mass transfer of SO- from the gas to the
     liquid phase.  The absorber is designed for an L/G of
     65 GPM/MACFM (inlet gas to the absorber) and a pressure
     drop of 7" H20.  Slurry concentration will be 8%; gas
     velocity in the unit will be 10 FPS; and S02 removal is
     specified to be about 85% plus.  The size or the
     turbulent contact absorbers will be 15'  x 35' approxi-
     mately in cross-section and will treat 375,000 ACFM,
     respectively of saturated gas.  Four absorbers will be
     required for this unit.

   0  Each absorber has a circulating tank sized to provide a
     10-minute retention time based on the slurry circulat-
     ing rate.  This retention time is essentially the same
     as that reported by others and should provide suffi-
     cient time for desupersaturation and thus reduce
     scaling potential.

     However, if long retention times are required, the
     incremental cost would be small since the circulating
     tanks do not represent large cost items, but space
     limitations may require locating a secondary tank some
     distance away and require additional piping.

   0  The Chevron vane-type entrainment separator was se-
     lected to remove mist which is carried over in the gas
     from the absorber.  This unit contains two stages of
     Chevron vanes which are washed continuously with water.
     Superficial gas velocity through the unit is 7 FPS and
     the pressure drop is expected to be about 2" H^O.
     Design of the unit is based on information from C-E,
     Chemico and UOP.
* Universal Oil Products Company
  (Air Correction Division)
                               D-6

-------
0 The gas leaving the entrainment separator must be
  reheated to desaturate it and provide buoyancy for it
  for adequate atmospheric dispersion.   The number of
  degrees of reheat necessary is variable and dependent
  on a number of factors such as stack  height, local
  weather conditions, population density, terrain of the
  area, maximum allowable SO? ground-level concentration,
  etc.  For this study,  a reheat AT of  50°F was used;
  this is believed to be about the minimum acceptable
  value.  Obviously, the lowest acceptable reheat AT
  should be chosen since each increase  of 50°F of the
  flue gas temperature requires about 1.5% of the gross
  heat input to the plant.

  An indirect finned tubular heat exchanger was selected
  for the reheater.  The first 33% of the rows of tubes
  are constructed of Alloy 20 for corrosion resistance to
  the gas which enters at it's dew point.  The remaining
  67% of the rows are constructed of carbon steel.
  Heating medium for the unit is low pressure saturated
  steam.  Pressure drop through the reheater is calculated
  to be about 4" H20.

0 Based on experience at an existing installation, a
  retractable soot blower is used for each 25 ft^ of
  scrubber exit duct cross-section for  the heat exchanger.
  Half of the soot blowers will be on the entry side, the
  remainder on the exit side of the heat exchanger.

0 Cost of reheat was based purely on a  coal conversion
  cost in BTU's.
                           D-7

-------
  APPENDIX E




   BASIS OF




WELLMAN - LORD




PROCESS DESIGN
      E-l

-------
            BASIS OF WELLMAN-LORD PROCESS DESIGN


     A.  Design Values

     The process design basis for the Wellman-Lord system

used in this study was determined after review of process

designs used or proposed for use at various installations

and discussions with Davy Power Gas.  Figure E.I presents a

typical process flow sheet for this process.

     The plant evaluated for illustration of design basis is

similar to the 500 MW existing model plant evaluated in this

study.  It is a single 500 MW, pulverized-coal-fired boiler.

The coal burned has a heating value of 12,000 BTU/lb, and a

3.5 percent sulfur content.  The allowable sulfur dioxide

emission rate is the New Source Performance Standard Limi-

tation of 1.2 Ib/MM BTU of heat input.  The average annual

capacity factor is 60 percent.  The plant is assumed to be

meeting particulate emission rate limitations and thus

requires no additional particulate control.

     Values of the major overall design parameters are

tabulated below:

  0  Flue gas rate: 1,500,000 ACFM

  0  Flue gas temperature: 310°F

  0  Flue gas pressure:  atmospheric

  0  Average inlet S02 concentration: 5.54 Ib/MM BTU (3.5% S
     coal)

                               E-2

-------
w
I
OJ
              Figure E.I   Typical  process  flow sheet of Wellman-Lord SO2 Scrubbing System.

-------
  0  Outlet S02 concentration: 1.2 lb/MM BTU (allowable)

  0  Reheat: 50°F above dew point (from 125 to 175°F)

  0  Soda ash consumption:  5% stoichiometric

Soda Ash System

     Unloading Hopper: 100 ton capacity

     Storage Silo: 893 tons (30 day storage)

     Feeders: Capacity = 3.72 tons (3.0 x maximum soda ash
     flow)
                                       3
     Na2C03 Slurry Storage Tank: 570 ft  (4 hours)

     Na2CO_ Slurry Feed Pump:  1 pump

     Raw Water Pumps: 2

Scrubbing System  (Each Train)

     Fan: 1-100% unit

          Type - Double inlet centrifugal

          AP = 16.0" H20

     Absorber: Type - Seive tray with 2 stage (4 required)

          AP = 8" H20

          L/G = 3 GPM/MACFM/stage (inlet gas to absorber
          scrubber)

          Slurry Concentration = 25% (wt.)

          SO - Removal = 90%+

          Gas Velocity = 8 FPS

          Solution Storage Tanks - 24 hour storage

          Pumps = 2/stage plus 1 spare pump for each unit

     Entrainment Separator: Chevron vane type (2/absorber)

          Number passes = 2

          AP = 2" H^O
                               E-4

-------
          Gas Velocity = 7 FPS

     Purge Treatment:

          Refrigeration: Temperature 40°F; Flow - 5% of
          recirculation rate

          Centrifuge: Solids - 5% of stoichiometric Na2C03

     Acid Plant:

          Size: 415 tons/day (125% of average S02 flow)

     S0~ Regeneration:

          Evaporators:  30% slurry of Na HSC>3 based on SO,,
          absorbed.  Evaporators are sized for one hour
          retention and 50% free space.

          Reboilers:  7.5°F temperature rise; 8 Ibs of steam
          per Ib of S02

          Stripper: Overhead is 1 Ib SO- and 1 Ib H20
          for every 1 Ib of S02

     Reheater: type - indirect tubular

          AT = 50°F  (inlet temperature = 125°F;
                    outlet temperature = 175°F)

          Heating Median - low pressure steam

B.  Design Rationals

The design rationale used in the study are listed below:

  0  The soda ash storage silo was sized for 30 days storage
     to allow the plant to continue operating in the event
     of an interruption in the supply of soda ash.

  0  The feeders were sized at 3.0 times the maximum soda
     ash flow.

  0  The soda ash slurry storage tank was sized for 4 hours
     storage.

  0  In general, all critical pumps in the process are
     provided with spares.

  0  A sieve tray was selected for removal of the bulk of
     the SO2«  This unit has 2 stages of sieve trays to
     provide the contact area necessary for mass transfer to


                               E-5

-------
S0~ from the gas to the liquid phase.  The absorber is
designed for an L/G of 3 GPM/MACFM/stage  (inlet gas to
the absorber) and a pressure drop of 8" H20.  Slurry
concentration will be 25%; gas velocity in the unit
will be 8 FPS; and S02 removal is specified to be about
90%.  Four units will be required and each will treat
375,000 ACFM of saturated gas.

The absorbers have common solution storage tanks sized
to provide a 24 hour storage of the slurry.  This .
storage time allows the absorbers to operate for
approximately 24 hours in the event the acid plant
should breakdown.

The Chevron vane-type entrainment separator was se-
lected to remove mist which is carried over in the gas
from the absorber.  This unit contains two stages of
Chevron vanes which are washed continuously with water.
Superficial gas velocity through the unit is 7 FPS and
the pressure drop is expected to be about 2" H20.

The gas leaving the entrainment separator must be
reheated to desaturate it and provide buoyancy for it
for adequate atmospheric dispersion.  The number of
degrees of reheat necessary is variable and dependent
on a number of factors such as stack height, local
weather conditions, population density, terrain of the
area, maximum allowable S02 ground-level concentration,
etc.  For this study, a reneat AT of 50°F was used;
this is believed to be about the minimum acceptable
value.  Obviously, the lowest acceptable reheat AT
should be chosen since each increase of 50°F of the
flue gas temperature requires about 1.5% of the gross
heat input to the plant.

An indirect finned tubular heat exchanger was selected
for the reheater.  The first 33% of the rows of tubes
are constructed of Alloy 20 for corrosion resistance to
the gas which enters at it's dew point.  The remaining
67% of the rows are constructed of carbon steel.
Heating medium for the unit is low pressure saturated
steam.  Pressure drop through the reheater is calculated
to be about 4" H20.

Based on experience at an existing facility,«a re-
tractable soot blower is used for each 25 ft  of
scrubber exit duct cross-section for the heat exchanger.
Half of the soot blowers will be on the entry side, the
remainder on the exit side of the heat exchanger.
                        E-6

-------
0  Cost of reheat was based purely on a  coal  conversion
   cost in BTU's.

0  Purge treatment equipment was based for the  most part
   on TVA cost estimates.

0  The acid plant cost was based on costs furnished by
   Wellman-Lord.
                             E-7

-------
                APPENDIX F




NATIONWIDE FGD COST ASSESSMENT METHODOLOGY
                     F-l

-------
         NATIONWIDE FGD COST ASSESSMENT METHODOLOGY


     Data used in estimating the capital and annualized

costs of FGD systems for the selected plants were obtained

from:

     (1)  Steam Electric Power Plant Factors/1973 Edition,
          National Coal Association.

     (2)  The L.S.U. data file (Strategies and Air Standards
          Division, U.S. EPA).

     (3)  Directory of Electric Utilities, 1974-1975  (83rd
          edition).

In several cases, more accurate information, obtained

through plant inspections and contacts, was available from

PEDCo files.  Where discrepancies existed between data

sources, a "most reasonable" value was selected.

     It is emphasized that because of site-specific factors

which could not be determined and evaluated due to time and

budget limitations, the costs reported for individual plants

are not accurate.  Individual plant costs were determined

solely to generate national and regional estimates.  These

estimates, however, are considered to be reasonable since

the errors in individual plant estimates should cancel.

     In many cases, only a portion of total plants flue gas

required control to meet an emission limitation.  The re-
                              P-2

-------
quired degree of control was computed by  assuming a 90% S0_

removal  efficiency for  the flue gas treated.   For example,

if S0~ control requirements at a 1000 megawatt plant amounted

to 40 percent overall control, cost estimates were prepared

                                              40%
on the basis of controlling 445 megawatts (r x 1000 MW) .
The individual boilers  selected for control  were chosen on


the basis  of remaining  lives,  with the newer boilers con-


trolled  first.

      Individual plant data necessary for  FGD cost estimates


which were not available  (without direct  plant contact) ,

were  estimated using applicable regional  averages as itemized

in Table F.I and delineated below.



      Table F.I  ASSUMED  VALUES FOR REGIONAL VARIABLES

                  THAT AFFECT FGD SYSTEM COST

                                          Region
                                     East     West           East
                       New    Middle   North   North   South    South
Regional characteristic       England Atlantic Central  Central  Atlantic  Central  Mountain

Operating labor rate, $/man-hr   8.0     9.0     8.0     7.0     7.0     6.50     7.25
Power cost, mills/KWH        25.00    20.00    15.00   13.00   13.00    12.00    19.00

Limestone cost, $/ton         9.00     5.00     4.50     4.25    5.00     4.00     8.00
     Sludge Disposal  (Limestone system)  -  Sludge disposal
     was determined to be either on-site or off-site accord-
     ing to each plant's  location.  Plants located in rural
     areas were assumed to have adequate land for on-site
     disposal,  whereas plants in urban areas were assumed  to
     require offsite disposal.

     Capacity Factor - Assumed to be 0.6 if data not avail-
     able.

     Capital Cost - Assumed to be 9% (after taxes) for all
     plants.
                                F-3

-------
     Soda-Ash Cost (Wellman-Lord) - Assumed to be $55/ton
     for all plants.

     Acid Credit (Wellman-Lord)  - Assumed to be $20/ton for
     all plants.

     Salt Cake Credit (Wellman-Lord) - Assumed to be $40/ton
     for all plants.

     Table F.2 presents a summary of the estimated plant FGD

system costs.
                             F-4

-------
                  Table F.2   FLUE  GAS DESULFURIZATION SUMMARY  FOR  SELECTED  U.S.  POWER  PLANTS'
REGION
State
Plant name
Power Co.
NEW ENGLAND
Massachusetts
Bray ton Pt.f
New England
Power Company
MIDDLE ATLANTIC
New York
Charles Huntleyf
Niagara Mohawk
Power Corp.
Dunkirk
Niagara Mohawk
Power Corp.
Goudey
N.Y. State E. &
G. Corp.
Scrubbed
units
Rem.
lifeb

25

23
25
20
Cap.
(MW)

695

233
103
16
Total
plant
cap.
(MW)

965

828
628
146
Sulfur
content
of
coal, %

1.00

2.53
2.9
2.3
Cap.
factor
(1973)

0.79

0.56
0.69
0.53
Sludge
disposal
Off-
site

X

X


On-
Site




X
X
Capital costs
Wellman-Lord
$ MM ($/KW)

57 (82)

22 (96)
11 (109)
3 (179)
Limestone
$ MM ($/KW)

41 (58)

15 (63)
9 (87)
4 (255)
Annualized costs
Wellman-Lord
Total •
fuel and , power
O&M
$ MM/yr
(mills/KWH)

17 (3.6)
4.2 (0.9)
2.26 (0.5)

6.5 (5.7)
0.9 (0.8)
1.4 (1.2)
3.5 (5.7)
0.70 (1.1)
0.82 (1.3)
1.1 (14.7)
0.08 (1.1)
0.4 (5.9)
Limestone
Total
fuel and power
O&M
$ MM/yr
(mills/KWH)

14.7 (3.1)
2.2 (0.5)
4.9 (1.1)

4.5 (3.9)
0.4 (0.3)
1.4 (1.2)
3.1 (5.0)
0.3 (0.5)
1.1 (1.8)
1.4 (19.3)
0.05 (0.7)
0.6 (8.3)
 I
tn
           Costs presented in this table are based on S0? removal efficiencies required to meet projected emission
           limitations.   All $/KW costs are based on KW's of plant capacity scrubbed.
           Weighted by unit capacity.
           Fuel and electricity costs.
           Operation and maintenance costs, excluding fuel and electricity costs and fixed costs.
           Net operation and maintenance costs (Includes byproduct credits), excluding fuel and electricity costs and
           fixed costs.
           Requires 25% or more S02 control.

-------
Table F.2 (continued).  FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S.  POWER PLANTS'

REGION
State
Plant name
Power Co.
New York (cont. )
Green idge
M.Y G « E Co.
Mi 111 ken
N.Y. State E &
Gas Co.
Rochester 3
Rochester Gas &
Electric Corp.
Rochester 7
Rochester Gas &
Electric Corp.
Pennsylvania
Cheswickf
Duquesne Light
Co.
Croniby
Phil. Elec. Co.
Eddystone
PM1. Elec. Co.

Scrubbed
units
Rem.,
lifeb
18
23
24
22

35
20
25
Cap.
(MW)
12
30
7
21

525
361
608

Total
plant
cap.
(MW)
167
270
196
253

525
418
707

Sulfur
content
of
coal , %
2.4
2.3
2.6
2.47

2.3
2.4
2.5

Cap.
factor
(1973)
0.71
0.68
0.38
0.62

0.77
0.75
0.6

Sludge
disposal
Off-
site


X




X
On-
Site
X
X

X

X
X

Capital costs

Wellman-Lord
$ MM (S/KW)
3 (209)
4 (144)
2 (259)
3 (156)

55 (104)
35 (97)
52 (86)

Limestone
$ MM ($/KW)
4 (320)
5 (165)
4 (487)
4 (206)

39 (75)
24 (67)
36 (59)
Annualized costs
Wcllman-Lord
Total c
fuel and^power
O&M
$ MM/yr
(mills/KWH)
1.0 (13.5)
0.08 (1.1)
0.44 (5.0)
1.5 (8.5)
0.20 (1.1)
0.50 (2.9)
0.82 (33.1)
0.03 (1.2)
0.44 (17.8)
1.2 (10.6)
0.12 (1.1)
0.47 (4.2)

15 (4.4)
3.2 (1.0)
1.7 (0.5)
10 (4.4)
2.2 (1.0)
1.6 (0.7)
15 (4.7)
2.2 (0.7)
3.0 (0.9)
Limestone
Total c
fuel andepower
O&M
$ MM/yr
(mills/KWH)
1.4 (18.8)
0.06 (0.8)
0.6 (8.0)
1.7 (9.7)
0.10 (0.57)
0.70 (3.8)
1.3 <52.1
0.03 (1.2
0.60 (23.9
1.5 (13.3)
0.07 (0.6
0.63 (5.6

13 (3.7)
1.33 (0.4)
4.54 (1.3)
8.3 (3.5)
0.92 (0.4)
2.88 (1.2)
13 (4.1
1.1 (0.4
5.2 (1.6

-------
       Table F.2  (continued).  FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS



REGION
State
Plant name
Power Co.
Pennsylvania
(cont.)
Holtwood
Penn. P 8 L Co.

Mitchellf
Allegheny Power
Service Corp.
Newcastle f
Penn Power Co.

Phillipsf
Duquesne Light
Co.
Seward
Penn. Elec. Co.

Springdale-^
W. Penn Power
Co.



Scrubbed
units
Rem.
lifeb


20


23


29


20


22


17

Cap.
(MW)


41


444


133


298


55


179




Total
plant
cap.
(MW)


75


449


426


411


268


416




Sulfur
content
of
coal, %


2.2


2.4


3.2


2.3


2.95


1.6




Cap.
factor
(1973)


0.51


0.6


0.64


0.6


0.6


0.66




Sludge
disposal
Off-
site








X


X







On-
Site


X


X








X


X

Capital costs



Wellman-Lord
$ MM ($/KW)


5 (135)


43 (97)


16 (117)


36 (121)


5 (83)


16 (92)




Limestone
$ MM ($/KW)


5 (135)


29 " (66)


11 (84)


22 (72)


6 (102)


13 (70)

Annualized costs
Wellman-Lord
Total

fuel and, power
O&M
$ MM/yr
(mills/KWH)





1.8 (10.02)
0.21 (1.2)
0.57 (3.2)
12 (5.3
2.3 (1.0
2.1 (0.9



4.8 (6.4)
1.0 (1.3)
0.89 (1.2)
11 (6.7)
2.3 (1.5)
1.5 (1.0)
1.6 (5.5)
0.15 (0.5)
0.61 (2.1)
5.2 (5.0)
0.85 (0.8)
1.1 (1.1)
Limestone
Total
fuel and power0
OSMe
$ MM/yr
(mills/KWH)


1.9 (10.3)
0.09 (0.5)
0.79 (4.3)
9.6 (4.1)
0.86 (0.4)
3.3 (1.4)
4.5 (6.0)
0.31 (0.4)
2.11 (2.8)
8.9 (5.7)
0.62 (0.4)
4.26 (2.7)
1.9 (6.5)
0.13 (0.5)
0.73 (2.5)
4.3 (4.1)
0.42 (0.4)
1.44 (1.4)
I
-J

-------
      Table F.2  (continued).   FLUE GAS DESULFURIZATION SUMMARY  FOR SELECTED U.S. POWER  PLANTS'



REGION
State
Plant name
Power Co.
EAST NORTH
CENTRAL
Illinois
Baldwin
111. Power Co.
Coffeen
Central 111. Pub.
Service
Da 11 man
Springfield Water
Light & Power
Dept.
Dixon
Com. Edison Co.
Jolietf '
Com. Edison Co.
Kincaidf
Com. Edison Co.



Scrubbed
units
Rem.
lifeb



38
36
37

18

30

33
Cap.
(MW)



891
216
26

22

1407

397



Total
plant
cap.
(MW)



1246
1006
160

119

1862

1320



Sulfur
content
of
coal, %



2.8
3.63
3.75

4.4

3.03

4.2



Cap.
factor
(1973)



0.66
0.36
0.60

0.67

0.60

0.45



Sludqc
disposal
Off-
site












On-
Site



X
X
X



X

X
Capital costs



Wellman-Lord
$ MM ($/KW)



93 (104)
26 (122)
5 (179)

4 (192)

130 (98)

50 (127)



Limestone
$ MM ($/KW)



54 (60)
15 (70)
5 (194)

4 (204)

77 (58)

30 (75)
Annualized costs
Wellman-Lord
Total
fuel and, power
O&M
$ MM/yr
(mills/KWH)



25 (4.8)
4.0 (0.8)
3.3 (0.6)
7.1 (10.4)
0.78 (1.1)
1.4 (2.1)
1.5 (11.0)
0.17 (1.3)
0.46 (3.4)

1.4 (11.0)
0.17 (1.3)
0.42 (3.3)
35 (5.0)
5.2 (0.7)
5.6 (0.8)
13 (8.5)
1.9 (1.2)
2.0 (1.3)
Limestone
Total
fuel and power
O&M6
$ MM/yr
(mills/KWH)



18 (3.5)
1.46 (0.3)
6.54 (1.3)
f
4.8 (7.1)
0.20 '(0.3)
1.8 (2.7)
1.7 (12.5)
0.06 (0.4)
0.71 (5.2)

1.6 (12.4)
0.05 (0.4)
0.69 (5.3)
25 (3.6)
1.93 (0.3)
8.79 (1.3)
9.6 (6.1
0.5 (0.3
3.6 (2.3
I
00

-------
Table F.2 (continued).  FLUE GAS DESULFURIZATION  SUMMARY FOR SELECTED U.S. POWER PLANTS'

REGION
State
Plant name
Power Co.
Illinois (cont.)
Lakeside
Springfield
Water L & P Dept.
Marion
S. 111. Power
Cooperate
Venice
Union Elec. Co.
Waukegan
Com. Edison Co.
Will County f
Com. Edison Co.
Wood River
111 . Power Co.
Indiana
f
Baily
No. Ind. Public
Serv. Co.

Scrubbed
units
Rem.
lifeb
30
37
15
26
28
27
32
Cap.
(MW)
21
19
61
451
612
486
486

Total
plant
cap.
(MW)
146
114
500
1042
1269
657
616

Sulfur
content
of
coal, %
3.8
3.95
1.2
1.83
0.92
3.1
3.6

Cap.
factor
(1973)
0.21
0.52
0.25
0.45
0.44
0.47
0.49

Sludge
disoosal
Off-
site
X


X


X
On-
Site

X
X

X
X

Capital costs

Wellman-Lord
$ MM ($/KW)
4 (182)
4 (202)
6 (95)
40 (89)
47 (77)
51 (104)
45 (93)

Limestone
$ MM ($/KW)
4 (202)
5 -(237)
6 (95)
27 (61)
34 (56)
33 (68)
27 (55)
Annualized costs
Wellman-Lord
Total
fuel and, power0
0&Ma
$ MM/yr
(mills/KWH)
1.3 (32.7)
0.05 (1.3)
0.5 (13.5)
1.3 (14.8)
0.1 (1.1)
0.5 (5.4)
1.9 (14.2)
0.08 (0.6)
0.64 (4.8)
11 (6.1)
1.0 (0.6)
2.5 (1.4)
13 (5.3)
1.0 (0.4)
2.8 (1.2)
14 (6.6)
1.7 (0.8)
2.4 (1.2)
12 (5.5)
1.7 (0.8)
1.9 (0.9)
Limestone
Total
fuel and power
O&M
$ MM/yr
(mills/KWH)
1.5 (37.9)
0.02 (0.4
0.69 (17.3)
1.5 (17.7)
0.04 (0.5)
0.62 (7.32)
2.0 (14.4)
0.05 . (0.4)
0.75 (5.4)
10.8 (6.1)
0.51 (0.3)
5.19 (2.9)
10.2 (4.3)
0.60 (0.3)
3.16 (1.3)
10.3 (5.0)
0.60 (0.3)
3.49 (1.7)
14 (6.4)
0.50 (0.2)
8.48 (3.9)

-------
      Table F.2 (continued).   FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS'

REGION
State
Plant name
Power Co.
Indiana (cont.)
Clifty Creek
Ind.-Ky. Elec.
Corp.
Culley
S. Ind. G & E
Co.
Dresser
Pub. Service Co.
Edwardsport
Pub. Service Co.
Elmer Stout
Ind. P & L Co.
Logansport
Logansport Mun.
Utilities
Michigan Cityf
No. Ind. Pub.
Service

Scrubbed
units
Rem.,
lifeb
21
31
15
15
38
37
15
Cap.
(MW)
135
92
24
138
260
29
118

Total
plant
cap.
(MW)
1304
397
150
144
752
39
236

Sulfur
content
of
coal, %
3.6
3.5
4.1
2.8
2.7
2.1
2.9

Cap.
factor
(1973)
0.83
0.49
0.3
0.24
0.36
0.27
0.45

Sludge
disposal
Off-
site




X


On-
Site
X
X
X
X

X
X
Capital costs

Wellman-Lord
$ MM ($/KW)
15 (113)
11 (124)
4 (172)
16 (114)
25 (97)
5 (158)
14 (118)

Limestone
$ MM ($/KW)
10 (78)
9 . (93)
4 (182)
11 (81)
18 (70)
5 (176)
10 (85)
Annualized costs
Wollmnn-Lord
Total
fuel and^power0
O&M
$ MM/yr
(mills /KWH)
4.4 (4.52)
1.0 (1.0)
0.6 (0.6)
3.3 (8.3)
0.40 (1.0)
0.75 (1.9)
1.4 (22.5)
0.07 (1.1)
0.5 ' (8.2)
4.7 (16.0)
0.27 (1.0)
4.2 (4.1)
6.9 (8.3)
0.6 (0.7)
1.6 (1.9)
1.5 (21.4)
0.06 (0.8)
0.60 (8.3)
4.2 (9.1)
0.46 (1.0)
0.90 (2.0)
Limestone
Total
fuel and power0
O&M
$ MM/yr
(mills/KWH)
3.8 (3.8)
0.29 (0.3)
1.56 (1.6)
2.8 (7.2)
0.13 (0.3)
1.07 (2.7)
1.5 (24.4)
0.03 (0.5)
0.57 (9.2)
3.6 (12.2)
0.09 (0.3)
1.24 (4.2)
6.2 (7.6)
0.24 (0.3)
2.57 (3.1)
1.6 (23.8)
0.03 (0.4)
0.62 (9.2)
3.4 (7.3)
0.15 (0.3)
1.23 (2.6)
i
M
O

-------
Table F.2 (continued).   FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS



REGION
State
Plant name
Power Co.
Indiana (cont.)
Mitchell*
No. Ind. Pub.
Serv.
Petersburg
Ind.

State Linef
Com. Edison

Tanners Creek
Ind. & Mi. Elec.

Twin Branch
Ind. & Mi. Elec.

Wabash Riverf
Pub. Service
Co. of Ind.
Warrick #4f
S. Ind. G & E




Scrubbed
units
Rem.
lifeb

26


34


24


25


1


28


32


Cap.
(MW)

456


28


622


927


102


700


650





Total
plant
cap.
(MW)

529


650


964


1098


394


962


732





Sulfur
content
of
coal, %

3.0


3.0


1.5


3.5


4.4


2.6


3.4





Cap.
factor
(1973)

0.71


0.68


0.63


0.74


0.25


0.59


0.36





Sludge
disposal
Off-
site







X.














On-
Site

X


X





X


X


X


X


Capital costs



Wellman-Lord
$ MM ($/KW)

46 (101)


a (154)


53 (85)


99 (107)


14 (133)


69 ' (99)


79 (122)





Limestone
$ MM ($/KW)

28 (62)


5 .(175)


39 (63)


58 (63)


8 (83)


45 (64)


45 (70)


Annualized costs
Wellman-Lord
Total c
fuel and,power
O&M
$ MM/yr
(mills/KWH)

13 (4.5)
2.7 (0.9)
1.6 (0.6)
1.4 (8.5)
0.16 (1.0)
0.43 (2.6)
14 (4.2)
1.7 (0.5)
2.4 (0.7)
27 (4.4)
5.0 (0.8)
3.2 (0.5)
4.5 (20.1)
9.3 (1.3)
1.0 (4.3)
19 (4.7)
3.0 (0.7)
3.12 (0.8)
21 (10.2)
2.5 (1.2)
3.7 (1.8)
Limestone
Total
@
fuel and-power
O&M
$ MM/yr
(mills/KWH)

9.7 (3.4)
0.8 (0.3)
3.6 (1.3)
1.7 (10.0)
0.07 (0.4)
0.72 (4.2)
15 (4.5)
1.00 (0.3)
6.78 (2.0)
20 (3.3)
1.6 (0.3)
7.36 (1.2)
3.! (13.9)
0.08 (0.4)
1.03 (4.6)
15 (3.7)
1.20 (0.3)
5.11 (1.3)
14 (6.8)
0.6 (0.3)
4.94 (2.4)

-------
Table F.2 (continued).  FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS'



REGION
State
Plant name
Power Co.
Michigan
Cobbf
Consumers Power
Co.
Conners Creek
Det. Edison Co.

Eckert #5, #6 f
Lansing Board
of W and L
Erickson
Lansing Board
of W & L
Karn
Consumer Power
Co.
Marysville
Det. Edison Co.

Pennsalt
Det. Edison Co.




Scrubbed
units
Rem.
lifeb

21


5


35


38


26


12


14


Cap.
(MW)

354


118


77


74


156


76


15





Total
plant
cap.
(MW)

510


460


160


160


530


200


37





Sulfur
content
of
coal, %

2.8


1.6


2.8


2.7


3.0


2.5


2.13





Cap.
factor
(1973)

0.82


0.63


0.60


0.60


0.79


0.54


0.23





Sludge
disposal
Off-
site

X





X














On-
Site




X





X


X


X


X


Capital costs



Wellman-Lord
$ MM ($/KW)

34 (96)


11 (91)


9 (116)


9 (119)


15 (99)


8 (110)


3 (200)





Limestone
$ MM (S/KW)

22 (62)


8 . (71)


8 (100)


8 (104)


11 (73)


70 (92)


4 (269)


Annualized costs
Wellman-Lord
Total
fuel and^power
O&M
$ MM/yr
(mills/KWH)

9.7 (3.8)
2.0 (0.8)
1.3 (0.5)
4.8 (7.4)
0.4 (0.6)
0.8 (1.2)
2.7 (6.6)
0.36 (0.9)
0.66 (1.6)
2.6 (6.8)
0.37 (1.0)
0.60 (1.6)
4.5 (4.2)
0.89 (0.8)
0.73 (0.7)
2.8 (7.7)
0.29 (0.8)
0.68 (1.9)
1.1 (36.8)
0.02 (0.7)
0.44 (14.7)
Limestone
Total
(^
fuel and power
O&M
$ MM/yr
(mills/KWH)

8.5 (3.4)
0.8 (0.3)
3.62 (1.4)
4.0 (6.2)
0.2 (0.3)
1.03 (1.6)
2.6 (6.3)
0.14 (0.3)
1.02 (2.5)
2.5 (6.5)
0.13 (0.3)
0.95 (2.5)
3.9 (3.6)
0.3 (0.3)
1.46 (1.4)
2.5 (7.1)
0.10 (0.3)
0.85 (2.4)
1.4 (46.7)
0.01 (0.5)
0.54 (17.9)

-------
     Table F.2 (continued).  FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER  PLANTS'



REGION
State
Plant name
Power Co.
Michigan (cont.)
River Rouge
Oet. Edison Co.

St. Clairf
Det. Edison Co.

Trenton Channel
Oet. Edison Co.

James De Young
Holland Board
of Pub. Works
Ohio
Avon Lake
Clev. Elec.
Illumination Co.
Beckjord
C.G. & E. Co.

Burger
Ohio Edison Co.




Scrubbed
units
Rem.
lifeb

23


30


5


37



24


28


20


Cap.
(MW)

495


1054


421


60



81


1174


471





Total
plant
cap.
(MW)

842


1905


800


77



1275


1221


544





Sulfur
content
of
coal, %

2.8


3.1


2.5


3.5



2.9


3.6


2.8





Cap.
factor
(1973)

0.65


0.74


0.71


0.60



0.53


0.37


0.60





Sludge
disposal
Off-
site

X


X















X


On-
Site







X


X



X


X





Capital costs



Wellman-Lord
$ MM ($/KW)

47 (94)


104 (99)


43 (101)


9 (158)



9 (113)


123 (105)


40 (84)





Limestone
$ MM ($/KW)

30 (60)


66 . (62)


27 (65)


8 (136)



7 (92)


70 (59)
•

25 (54)


Annualized costs
Wellman-Lord
Total
«
fuel and ..power
0&Md
$ MM/yr
(mills/KWH)


13 (4.5)
1.9 (0.7)
2.1 (0.7)
28
5.3
3.3
4-1)
0.8)
0.3)
18 (6.8)
1.6 (0.6)
2.0 (0.8)
2.8 (8.8)
0.35 (1.1)
0.70 (2.2)


2.7 (7.2)
0.33
0.67
0.9)
1.8)
33 (8.6)
3.8 (1.0)
6.3 (1.6)
11 (4.1)
2.0 (0.7)
1.7 (0.6)
Limestone
Total
fuel and power
O&M
$ MM/yr
(mills/KWH)

14 (5.0)
0.80 (0.3)
7.66 (2.7)
34 (4.9)
1.9 (0.3)
19 (2.9)
13 (5.0)
0.75 (0.3)
3.08 (1.2)
2.6 (8.4)
0.12 (0.4)
0.9£ (3.2)

2.5 (6.6)
0.12 (0.3)
0.98 (2.6)
22 (5.7)
1.0 (0.3)
7.5 (2.0)
9.8 (3.6)
0.70 (0.3)
4.4 (1.6)
I
M
U)

-------
      Table F.2  (continued).   FLUE GAS DESULFURIZATION  SUMMARY FOR SELECTED U.S.  POWER PLANTS'



REGION
State
Plant name
Power Co.
Ohio (cont.)
Clev. Div. of.
Pwr. & Light T
Same
Cardinal
Ohio Power Co.

Conesville
Col. and S. Ohio
Elec. Co.
East Lakef
Clev. Elec.
Illumination Co.
Gavin
Ohio Power Co.

George
Ohio Edison Co.

Kyger Creek
Ohio Valley Elec.
Co.



Scrubbed
units
Rem.
lifeb

20


32


27


37


40


12


20


Cap.
(MW)

144


286


143


460


2340


80


337





Total
plant
cap.
(MW)

160


1180


434


1275


2600


87.5


1086





Sulfur
content
of
coal, %

3.15


3.5


4.8


3.3


3.7


3.23


3.8





Cap.
factor
(1973)

0.60


0.75


0.70


0.76


0.60


0.58


0.75





Sludge
disposal
Off-
site

X








X











On-
Site




X


X


X


X


X


X


Capital costs



Wellman-Lord
$ MM ($/KW)

17 (115)


30 (104)


20 (137)


48 (104)


261 (112)


11 (137)


40 (119)





Limestone
$ MM ($/KW)

12 (84)


20 . (71)


12 (85)


32 (69)


160 (68)


8 (97)


21 (64)


Annualized costs
Wellrnan-Lord
Total
fuel and oowerc
0&Md
$ MM/yr
(mills/KWH)

4.7 (6.3)
0.67 (0.9)
0.94 (1.2)
8.2 (4.4)
1.6 (0.8)
1.1 (0.6)
5.6 (6.3)
1.2 (1.4)
0.69 (0.8)
13 (4.2)
2.2 (0.7)
1.9 (0.6)
69 (5.5)
11 (0.9)
9.1 (0.7)
3.6 (8.8)
0.47 (1.2)
0.69 (1.7)
11 (4.9)
2.5 (1.1)
1.0 (0.4)
Limestone
Total
fuel and powerc
0&Me
$ MM/yr
(mills/KWH)

4.4 (5.8)
0.20 (0.3)
1.9 (2.6)
7.0 (3.7)
0.55 (0.3
2.64 (1.4
4.4 '(5.0)
0.30 (0.3)
1.83 (2.1)
12 (3.9)
0.9 (0.3)
5.2 (1.7)
53 (4.3)
3.5 (0.3)
19.7 (1.6)
3.0 (7.2)
0.12 (0.3)
1.2 (2.8)
8.0 (3.6
0.6 (0.3
3.4 (1.5
I
M
*>

-------
       Table F.2 (continued).  FLUE GAS DESULFURIZATION SUMMARY  FOR  SELECTED U.S.  POWER PLANTS'



REGION
State
Plant name
Power Co.
Ohio (cont.)
Lake Road
Clev. Div. of
L & W
Lake Shore
Clev. Elec.
Illumination Co.
tfiami Fortf
C. G. & E. Co.

Muskingum River
Ohio Power Co.

Philof
Ohio Power Co.

Piquaf •
Piqua Municipal
Power System
Poston
Col. & S. Ohio
Elec. Co.



Scrubbed
units
Rem.
lifeb

35


26


20


28


8


14


18


Cap.
(MW)

129


283


249


1036


382


46


132





Total
plant
cap.
(MW)

160


541


387


1466


500


53


232





Sulfur
content
of
coal, %

2.2


2.5


3.5


5.0


3.7


2.86


3.1





Cap.
factor
(1973)

0.19


0.52


0.57

.
0.71


0.33


0.35


0.57





Sludge
disposal
Off-
site

X


X











X





On-
Site







X


X


X





X


Capital costs



Wellman-Lord
$ MM ($/KW)

12 (90)


27 (96)


27 (109)


133 (128)


48 (125)


5 (117)


16 (121)





Limestone
$ MM ($/KW)

10 (79)


19 (68)


17 (68)


73 (71)


25 (65)


5 (117)


11 (84)


Annualized costs
Wellman-Lord
Total
fuel and,powerc
0&Md
S MM/yr
(mills/KWH)

3.3 (15.5)
0.11 (0.5)
1.0 (4.8)
7.4 (5.8)
0.88 (0.7)
1.5 (1.1)
7.6 (6.1)
1.3 (1.0)
1.3 (1.0)
35 (5.4)
7.9 (1.2)
2.4 (0.4)
14 (13.0)
1.5 (1.2)
2.0 (1.8)
1.8 (12.8)
0.09 (0.6
0.60 (4.3)
4.7 (7.1)
0.70 (1.0)
0.90 (1.4)
Limestone
Total
c
fuel and power
O&M
$ MM/yr
(mills/KWH)

3.0 (14.1)
0.07 (0.3)
1.0 (4.9)
6.7 (5.2)
0.40 (0.3)
2.76 (2.2)
5.7 -(4.6)
0.38 (0.3)
2.2 (1.8)
26 (4.1)
1.9 (0.3)
12.4 (1.9)
8.7 (7.8)
0.34 (0.3)
3.0 (2.7)
1.9 (13.3)
0.04 (0.3)
0.72 (5.1)
3.7 (5.6)
0.22 (0.3)
1.37 (2.1)
I
M
Ul

-------
Table F.2 (continued).   FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS'

REGION
State
Plant name
Power Co .
Ohio (cent.)
Sammis
Ohio Edison Co.
Stuartf
Dayton Power &
Light Co.
Tiddf
Ohio Power Co.
Toronto
Ohio Edison Co.
Vine Street
Orrville Mun.
Utilities
WEST NORTH
CENTRAL
Iowa
Ames #2f
Ames Elec. Oept.

Scrubbed
units
Rem.
life13

34
37
12
14
37


37
Cap.
(MW)

1255
342
201
51
35


42

Total
plant
cap.
(MW)

1980
1830
222
176
64


68

Sulfur
content
of
coal, %

2.7
1.9
3.4
3.0
3.5


3.56

Cap.
factor
(1973)

0.71
0.71
0.57
0.49
0.37


0.40

Sludge
disposal
Off-
site








X
On-
Site

X
X
X
X
X



Capital costs

Wellman-Lord
$ MM ($/KW)

122 (97)
31 (90)
22 (107)
5 (147)
5 (138)


5 (111)

Limestone
$ MM ($/KW)

78 (62)
22 (65)
14 (69)
5 (152)
5 (145)


5 (127)
Annualized costs
Wcllman-Lord
Total
fuel and power
0&Md
$ MM/yr
(mills/KWH)

33 (4.2)
4.9 (0.6)
5.4 (0.7)
8.4 (4.0)
1.0 (0.5)
1.6 (0.8)
6.8 (6.8)
0.90 (0.9)
1.1 (1.0)
1.6 (11.9)
0.13 (1.0)
0.53 (3.9)
1.5 (13.6)
0.10 (0.9)
0.49 (4.4)


1.5 (10.0)
0.07 (0.5)
0.57 (3.8)
Limestone
Total
fuel and powerc
O&M6
$ MM/yr
(mills/JCWH)

26 (3.3)
2.2 (0.3)
9.4 (1.2)
7.1 (3.3
0.60 (0.3
2.4 (1.1
5.0 (5.1)
0.3 (0.3)
1.6 (1.6)
1.7 (12.8)
0.06 (0.4)
0.65 (4.9)
1.7 (14.8)
0.04 (0.3)
0.72 (6.2)


1.7 (11.5)
0.04 (0.3)
0.68 (4.6)

-------
     Table P.2  (continued).  FLUE GAS  DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS*



REGION
State
Plant name
Power Co.
Minnesota
Blackdogf
N. States Power
Co.
High Bridge
N. States Power
Co.
Kingf
N. States Power
Co.
Missouri
Meramec
Union Elec. Co.

Rush Island
1, 2 Union Elec.
Co.
Sioux
Union Elec. Co.




Scrubbed
units
Rem.,
life*1

25


5


33



26


40


33


Cap.
(MW)

25


20


301



433


102


619





Total
plant
cap.
(MW)

487


438


574



923


1184


1100





Sulfur
content
of
coal, %

1.6


1.6


3.0



1.47.


2.4


2.74





Cap.
factor
(1973)

0.77


0.61


0.60



0.62


0.60


0.39





Sludge
disnosal
Off-
site

X





X



X





X


On-
Site




X









X





Capital costs



Wellman-Lord
$ MM ($/KW)

3 (139)


3 (149)


32 (108)



36 (82)


9 (88)


53 (85)





Limestone
$ MM ($/KW)

4 (173)


4 -(186)


20 (67)



27 (61)


8 (75)


38 (61)
'

Annualized costs
Wellman-Lord
Total
fuel and power0
O&Md
$ MM/yr
(mills/KWH)

1.2 (6.9)
0.10 (0.6)
0.44 (2.6)
1.5 (13.8)
0.07 (0.7)
0.43 (3.9)
8.5 (5.4)
1.2 (0.8)
1.3 (0.8)

9.5 (4.0)
l.'l (0.5)
1.8 (0.7)
2.6 (4.9)
0.34 (0.6)
0.59 (1.1)
14 (6.5)
0.84 (0.4)
3.3 (1.6)
Limestone
Total
fuel and power0
OSMe
$ MM/yr
(mills/KWH)

1.5 (9.1)
0.06 (0.4)
0.63 (3.8)
1.8 (17.1)
0.04 (0.4)
0.59 (5.6)
7.5 "(4.8)
0.40 (0.3)
3.3 (2.1)

9.7 (4.1)
0 55 (0.2)
4.2 (1.8)
2.5 (4.7)
0.14 (0.3)
2.0 (1.8)
12 (5.7)
0.5 (0.2)
4.5 (2.1)
I
I-1
^J

-------
      Table F.2 (continued).  FLUE GAS DESULFURIZATION SUMMARY  FOR SELECTED U.S. POWER PLANTS*

REGION
State
Plant name
Power Co.
SOUTH ATLANTIC
Delaware
Delaware City
Delmarva Power
& Light Co.
Florida
Big Bendf
Tampa Elec. Co.
Cristf
Gulf Power Co.
Gannon
Tampa Elec. Co.
Lansing Smith
Gulf Power Co.
Georgia
Hammond
Georgia Power
Co.

Scrubbed
units
Rem.,
lifeb

24
35
37
30
31

35
Cap.
(MW)

130
742
810
970
244

365

Total
plant
cap.
(MW)

130
900
1128
1270
305

953

Sulfur
content
of
coal, %

7.03
3.0
3.4
3.1
3.0

3.5

Cap.
factor
(1973)

0.60
0.54
0.62
0.48
0.83

0.64

Sludge
disposal
Off-
site

X
X

X



On-
Site



X

X

X
Capital costs

Wellman-Lord
$ MM ($/KW)

13 (96)
67 (90)
80 (99)
84 (87)
27 (111)

44 (120)

Limestone
$ MM ($/KW)

10 (75)
43 (58)
49 (61)
50 (52)
17 (69)

30 (81)
Annualized costs
Wellman-Lord
Total
fuel and,power
O&M
$ MM/yr
(mills/KWH)

3.6 (5.2)
0.45 (0.7)
0.8 (1.2)
17 (4.8)
1.9 (0.5)
2.6 (0.7) .
20 (4.6)
2.4 (0.6)
2.7 (0.6) .
22 (5.3)
2.2 (0.5)
4.2 (1.0)
7.3 (4.1)
1.4 (0.8)
0.8 (0.5)

13 (6.1)
2.4 (1.2)
2.4 (1.2)
Limestone
Total c
fuel and power
O&M
$ MM/yr
(mills/KWH)

3.8 (5.5)
0.20 (0.3)
1.8 (2.7)
20 '(5.6)
0.50 (0.1)
11.5 (3.2)
16 (3.6)
0.70 (0.2)
6.1 (1.4)
22 (5.4)
0.62 (0.2)
12.0 (3.0)
6.0 (3.4)
0.50 (0.3)
1.38 (1.3)

9.5 (4.6)
0.60 (0.3)
3.4 (1.6)
I
M
00

-------
Table F.2 (continued).   FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS'

REGION
State
Plant name
Power Co.
Maryland
Chalk Pointf
Pot. Elec. Pw.
Co.
Dickerson
Potomac Elec.
Power Co.
Morgantown
Potomac Elec.
Power Co.
South Carolina
Urquhart
S. Carolina Elec.
& Gas Co.
VI rg i n i a
Potomac River
Potomac Elec.
Power Co.
West Virginia
Albrightf
Allegheny Power
Service Corp.

Scrubbed
units
Rem.
life*5

30
27
36
32

22
19
Cap.
(MW)

571
227
424
20

158
66

Total
plant
cap.
(MW)

710
570
1451
250

486
200

Sulfur
content
of
coal, %

1.9
1.9
1.7
1.6

1.0
2.8

Cap.
factor
(1973)

0.43
0.73
0.67
0.72

0.56
0.85

Sludge
disposal
Off-
site

X
X
X


X

On-
Site




X


X
Capital costs

We 1 Ima n- Lo rd
$ MM ($/KW)

47 (82)
19 (84)
33 (77)
4 (125)

11 (71)
8 (116.)

Limestone
$ MM ($/KW)

31 (54)
13 - (58)
26 (61)
5 (143)

10 (64)
7 (99)
Annualized costs
Wellman-Lord
Total
fuel and,powerc
O&M
$ MM/yr
(mills/KWH)

12 (5.8)
1.0 (0.5)
2.3 (1.1)
5.2 (3.6)
0.67 (0.5)
1.0 (0.7)
8.8 (3.5)
0.9 (0.4)
1.8 (0.7)
1.3 (6.5)
0.10 (0.5)
0.50 (2.3)

3.3 (4.3)
0.26 (0.3)
0.93 (1.2)
2.3 (4.7)
0.40 (0.8)
0.50 (1.0)
Limestone
Total
fuel and power
O&M-
$ MM/yr
(mills/KWH)

9.5 (4.4)
0.8 (0.4)
3.0 (1.4)
4.8 (3.3)
0.40 (0.3)
2.0 (1.4)
8.0 "(3.2)
0.57 . (0.2)
2.58 (1.0)
1.5 (7.6)
0.0,' (0.4)
0.58 (2.9)

3.2 (4.1)
0.20 (0.3)
1.1 (1.4)
2.3 (4.7)
0.15 (0.3)
0.91 (1.8)

-------
     Table F.2 (continued).  FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S.  POWER PLANTS'



REGION
State
Plant name
Power Co.
West Virginia
Amos
Appalachian
Power Co.
Cabin Creek
Appalachian
Power Co.
Ft. Martinf
Allegheny Power
Service Corp.
Harrison
Monongahela
Power Co.
Kammer
Ohio Power Co.

Mitchellf
Ohio Power Co.

Mt. Storm f
Va. Electric &
Power Co.



Scrubbed
units
Rem.
life6

36


5


33


40


23


36


38


Cap.
(MW)

276


12


535


691


601


1049


470





Total
plant
cap.
(MW)

2900


273


1107


1280


675


1633


1662





Sulfur
content
of
coal, %

1.13


1.0


3.7


4.1


4.1


3.9


1.0





Cap.
factor
(1973)

0.64


0.42


0.73


0.60


0.60


0.48


0.40





Sludge
disposal
Off-
site




X

















On-
Site

X





X


X


X


X


X


Capital costs



Wellman-Lord
$ MM ($/KW)

16 (57)


2 (199)


51 (95)


78 (112)


49 (81)

•
122 (116)


43 (91)





Limestone
$ MM ($/KW)

17 (62)


4 -(325)


36 (68)


50 (72)


25 (42)


78 (74)


29 (62)


Annualized costs
Wellman-Lord
Total
fuel and ,power
O&M
$ MM/yr
(mills/KWH)

4.5 (2.9)
0.25 (0.2)
1.3 (0.9)
1.2 (27.9)
0.03 (0.7)
0.38 (8.9)
13 (3.9)
2.0 (0.6)
1.5 (0.5)
20 (5.5)
2.7 (0.7)
2.8 (0.8) .
13 (3.7)
2.9 (0.8)
1.0 (0.3)
31 (7.1)
3.1 (0.7)
5.2 (1.2)
11 (6.8)
0.80 (0.5)
2.2 (1.3)
Limestone
Total
J. V UU .*.
fuel and power
O&M
$ MM/yr
(raills/KWH)

5.0 (3.3)
0.4 (0.3)
1.4 (0.9)
1.8 (42.4)
0.04 (1.0)
0.46 (10.9)
12 "(3.5)
0.8 (0.2)
4.5 (1.3)
16 (4.4)
0.9 (0.2)
5.8 (1.6)
9.4 2.7)
0.6 0.2)
4.1 1.2)
24 . (5.4)
1.0 (0.2)
8.5 (1.9)
8.7 (5.3)
0.40 (0.2)
2.9 (1.7)
I
10
o

-------
Table F.2 (continued).   FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS



REGION
State
Plant name
Power Co.
West Virginia
(cent.)
Rivesville
Allegheny Power
Service Corp.
Willow Islandf
Allegheny Power
Service Corp.
Washington D.C.
Benning
Potomac Elec.
Power Co.
EAST SOUTH
CENTRAL
Alabama
Barry
AT. Power Co.

Chickasaw
Al . Power Co.




Scrubbed
units
Rem..
lifeb


5


25



5





35


14


Cap.
(MW)


55


116



45





1058


55





Total
plant
cap.
(MW)


175


215



134





1771


120





Sulfur
content
of
coal, %


3.8


3.2



0.8





2.4


1.9





Cap.
factor
(1973)


0.55


0.81



0.44





0.65


0.53





Sludge
disposal
Off-
site





















On-
Site


X


X



X





X


X


Capital costs



Wellman-Lord
$ MM ($/KW)


7 (136)


13 (113)



4 (92)





97 (92)


6 (115)





Limestone
$ MM ($/KW)


6 (104)


10 (82)



5 (106)





65 (61)


6 (105)


Annualized costs
Wellman-Lord
Total
fuel andjpower-
O&M
$ MM/yr
(mills/KWH)


3.3 (7.0)
0.40 (0.9)
0.38 (0.8)
3.7 (4.5)
0.73 (0.9)
0.53 (0.6)

2.0 (11.3)
0.07 (0.4
0.54 (3.0)



25 (4.2)
2.7 (0.5)
4.2 (0.7)
2.0 (7.9)
0.15 (0.6)
0.56 (2.2)
Limestone
Total
fuel andg power0
O&M
$ MM/yr
(mills/KWH)


3.0 (6.3)
0.15 (0.3)
0.95 (2.0)
3.4 (4.1)
0.23 (0.3)
1.4 .(1.6)

2.3 (13.0)
0.06 (0.3)
0.64 (3.6)



20 (3.3)
1.3 (0.2)
6.6 (1.0)
2.0 (7.7)
0.07 (0.3)
0.73 (2.8)

-------
      Table F.2  (continued).  FLUE GAS DESULFURIZATION  SUMMARY  FOR SELECTED U.S. POWER PLANTS'

REGION
State
Plant name
Power Co.
Alabama
Colbertf
Tenn. Valley
Auth.
Widows Creek
Tenn. Valley
Auth.
Kentucky
Cane Run
Louisville Gas
& Elec. Co.
Dalexf
Rural Elec. Co.
Ghentf
Ken. Utilities
Co.
Green River
Ken. Utilities
Co.
Mill Creek f
Louis. Gas &
Elec. Co.

Scrubbed
units
Rem.
lifeb
24
26

29
-
39
22 .
37
Cap.
(MW)
1043
1180

890
-
391
176
100

Total
plant
cap.
(MW)
1220
1675

992
194
525
263
330

Sulfur
content
of
coal, %
4.0
3.4

3.7
1.4
3.2
3.0
3.8

Cap.
factor
(1973)
0.59
0.60

0.59
0.60
0.60
0.61
0.50

Sludge
disposal
Off-
site







. X
On-
Site
X
X

X
X
X
X

Capital costs

Wellman-Lord
$ MM ($/KW)
109 (104)
109 (92)

91 (102)
Allowable emiss
40 (103)
20 (115)
11 (115)

Limestone
$ MM ($/KW)
61 (58)
70 - (59)

50 (57)
ons greater th<
27 (69)
14 (79)
9 (86)
Annualized costs
Wellman-Lord
Total
fuel and power0
O&Md
$ MM/yr
(mills/KWH)
28 ' (5.2)
4.1 (0.8)
3.6. (0.7)
28 (4.6)
3.4 (0.6)
4.4 (0.7)
•
24 (5.1)
3.7 (0.8)
3.3 (0.7)
n actual emissions'
10 (5.0)
1.4 (0.7)
1.1 (0.5)
5.6 (6.0)
0.80 (0.9)
1.0 (1.1)
3.2 (7.3)
0.38 (0.9)
0.68 (1.5)
Limestone
Total
fuel and powerc
O&M
$ MM/yr
(mills/KWH)
20 (3.7
1.3 (0.2
7.4 (1.4
22 (3.6)
1.4 (0.2)
7.6 (1.2)

'17 (3.7)
1.1 (0.2)
6.5 (1.4)

8.6 (4.2)
•tt.50 (0.20)
3.1 (1.5)
4.5 (4.7)
0.27 (0.3)
1.7 (1.7)
2.8 (6.3)
0.10 (0.2)
1.1 (2.5)
I
M
N)

-------
     Table F.2 (continued).   FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S. POWER PLANTS'

REGION
State
Plant name
Power Co.
Kentucky (cont.)
Paddy's Run
Louisville Gas
& Electric Co.
Paradise
Tenn. Valley
Auth.
Shawnee
Tenn. Valley
Auth.
Tennessee
Cumberland
Tenn. Valley
Auth.
Gallatinf
Tenn. Valley
Auth.
Johnsonville
Tenn. Valley
Auth.
Kingston
Tenn. Valley
Auth.

Scrubbed
units
Rem.
lifeb

15
32
19
38
24
18
20
Cap.
(MW)

219
2064
1332
1486
573
1365
1270

Total
plant
cap.
(MW)

338
2504
1750
2600
1245
1485
1700

Sulfur
content
of
coal, %

3.0
4.2
3.5
4.4
4.1
4.1
2.1

Cap.
factor
(1973)

0.17
0.68
0.69
0.45
0.61
0.53
0.64

Sludge
disposal
Off-
site








On-
Site

X
X
X
X
X
X
X
Capital costs

Wellman-Lord
$ MM ($/KW)

20 -• (91)
189 (91)
134 (101)
197 (133)
66 (114)
135 (99)
107 (84)

Limestone
$ MM ($/KW)

13 (61)
103 - (50)
71 (53)
122 (82)
37 (65)
73 (54) .
62 (49)
Annualized costs
Wellman-Lord
Total
fuel and power
o&yfl
$ MM/yr
(mills/KWH)

5.7 (17.4)
0.20 (0.6)
1.5 (4.5)
47 (3.9)
8.9 (0.7)
34.5 (2.8)
33 (4.1)
3.0 (0.4)
4.3 (0.5)
49 (8.4) .
3.4 (0.6)
8.9 (1.5)
17 (5.5)
2.5 (0.9)
2.3 (0.8)
32 (4.9)
2.9 (0.4)
3.9 (0.6)
28 (4.4)
3.5 (0.5)
4.6 (0.7)
Limestone
Total
fuel and power
O&M6
$ MM/yr
(mills/KWH)

4.0 (12.3)
0.08 (0.2)
1.22 (3.8)
38 (3.1)
2.7 (0.2)
16.0 (1.3)
24 '(3.0)
1.0 (0.1)
9.4 (1.2)
36 (6.2)
C.9 (0.2)
12.3 . (2.1)
12 (4.0)
0.8 (0.3)
4.3 (1.4)
24 (3.6)
0.85 (0.1)
9.5 (1.4)
20 (2.8)
1.6 (0.2)
6.8 (1.0)
I
M
CO

-------
Table F.2 (continued).  FLUE GAS DESULFURIZATION SUMMARY FOR SELECTED U.S.  POWER PLANTS'

REGION
State
Plant name
Power Co .
Tennessee (cont.)
T.H. Allenf
Tenn. Valley
Auth.
Watts Barf
Tenn. Valley
Auth.
MOUNTAIN
Arizona
Navajo
Salt River Dis.
Proj.
Nevada
Mo have
S. Cal. Edison
Co.
New Mexico
Four Corners
Arizona Pub.
Service Co.

Scrubbed
units
Rein.
life0
24
9

40
35
30
Cap.
(MW)
330
116

1671
705
595

Total
plant
cap.
(MW)
990
240

2250
1510
802

Sulfur
content
of
coal, %
3.1
4.1

1.0 .
0.4
1.0

Cap.
factor
(1973)
0.61
0.47

0.60
0.40
0.39

Sludge
disposal
Off-
site






On-
Site
X
X

X
X
X
Capital costs

Wellman-Lord
$ MM ($/KW)
34 (102)
14 (123)

119 (71)
52 (74)
46 (78)

Limestone
$ MM ($/KW)
21 (63)
9 - (79)

89 (53)
44 (62)
33 (56)
Annualized costs
Wellman-Lord
Total
fuel and powerc
0&Md
$ MM/yr
(mills/KWH)
8.8 (5.0)
1.1 (0.6)
1.4 . (0.8)
4.7 (9.9)
0.40 (0.8)
0.76 (1.6)

33 (3.7)
3.5 (0.4)
7.3 (0.8) .
14 (5.7)
0.60 (0.2)
3.7 (1.5)
13 (6.3)
1.4 (0.7)
3.0 (1.4)
Limestone
Total
fuel and power0
O&M
$ MM/yr
(mills/KWH)
6.8 (3.8)
0.40 (0.2)
2.5 (1.4)
3.5 (7.4)
0.10 (0.2)
1.2 (2.5)

28 (3.2) .
2.8 (0.3)
8.6 (1.0)
12 (5.0)
0.80 (0.3)
3.0 (1.3)
10 (4.9)
0.7 (0.3
3.1 (1.5)

-------
                    APPENDIX G




DETAILS OF UTILITY INDUSTRY SURVEY COST ADJUSTMENTS
                         G-l

-------
Plant   Alabama Electric Cooperative
        Tombigbee Units 2 and 3
        Jackson, Alabama
Boiler capacity, megawatts                      2 @ 255         510

Boiler flue gas scrubbed, megawatts                             357

FGD system                                      Limestone

Installation status      New         Under consideration
                                        Unit No. 2   3/78
                                        Unit No. 3   1/79

Sulfur content of fuel, percent by weight       2.5% coal

Capital cost analysis

  Reported capital cost for                     $ 40,463,880

  Corrected capital cost for 1975                 40,463,880

    Particulate removal equipment adjustment     -10,000,000a

    Redundancy adjustment

    Indirect cost adjustment                     - 1,417,000

    Sludge disposal adjustment



  Adjusted cost for 1975                          29,047,000

  Adjusted cost per rated kilowatt for 1975               81.36
Notes;

All cost corrections are in terms of 1975 dollars.

aSubtracted cost of electrostatic precipitators for control
 of particulate emissions.
 Subtracted indirect costs to reflect for precipitator removal.
                              G-2

-------
Plant   Arizona Public Service  Company
        Cholla Unit 1
        Joseph City,  Arizona
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status            Retrofit
              119.8

               59.9

   Limestone

Operational   12/73
Sulfur content of fuel, percent by weight

Capital cost analysis

  Reported capital cost for

  Corrected capital cost for 1975

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment
0.4-1.0% coal
$ 6,500,000

  8,371,000*

 -2,888,000C
    588,000'
    964,000
  Adjusted cost for 1975

  Adjusted cost per rated kilowatt for 1975
  7,035,000
         58.72J
Notes:

All cost corrections are in terms of 1975 dollars.
aBase year for cost reported not given.  Construction started 2/72
 and system became operational 12/73 (assumed 1973 cost basis).

bAdjusted reported costs (assumed 1973) to 1975 dollars.
cSubtracted adjusted cost of venturi scrubber system for particulate
 controls.
 Added cost of sludge pond for extended life from 2 years to
 to 22 years.
f^
 Added cost for dewatering sludge (clarifiers and vacuum filters)
 and crushing limestone (plant is presently buying crushed lime).

 Considered costs for system representative for treating full 119.8 MW;
 only difference between the modules is that Module B is not packed.

                               G-3

-------
Plant    Boston Edison Company
         Mystic Station
         Charlestown,  Massachusetts
Boiler capacity, megawatts                                       150

Boiler flue gas scrubbed, megawatts                              150

FGD system                                   Magnesium-oxide

Installation status          Retrofit        Demonstration  unit
                                             (April  '72  - June  '74)
                                             now shut down

Sulfur content of fuel, percent by weight    2.5% oil

Capital cost analysis

  Reported capital cost for  1974             $  5,010,000a

  Corrected capital cost for 1975              6,430,000

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment                       - c

    Sludge disposal adjustment                          ,
     Acid plant,  calcining system,  reheat     10,575,000
      and design changes

  Adjusted cost for 1975                      17,005,000
                                                           Q
  Adjusted cost per rated kilowatt for 1975          113.37
Notes:

All cost corrections are in terms of 1975 dollars.
 Reported cost does not include cost of calcination at the acid
 plant or costs to regenerate and recycle MgO back to the power
 plant; costs shown are actual; construction began 2/71 and was
 completed 4/72.
 Adjusted reported costs (1974) to 1975 dollars,  assuming 90% of
 costs generated by 4/72 and 10% by 12/73.

°No reheat to discharge flue gas.

 Calcining costs from data sheets and added:  acid plant, heat
 exchanger and equipment design changes.

 Costs are for totally intergrated plant.


                                G-4

-------
Plant  "    Cincinnati Gas & Electric Company
           Miami Fort Station Unit No.  8
           North Bend, Ohio
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status        New
Lime (probably)

Planned
500

500



1/78
Sulfur content of fuel, percent by weight    2.72% coal

Capital cost analysis

  Reported capital cost for 1978 (Jan. 1)     $ 40,617,000'

  Corrected capital cost for 1975              32,465,000

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment
    Sludge disposal adjustment
   4,151, 000*
  Adjusted cost for 1975

  Adjusted cost per rated kilowatt for 1975
  36,616,000

          73.23
Notes:

All cost corrections are in terms of 1975 dollars.
aReported costs of January 1, 1978 made mid 1974.

 Adjusted reported cost to 1975 dollars, after removing capability
 loss capital costs and including operating personnel training and
 start-up.
°Added costs for sludge disposal pond, sludge dewatering, and
 sludge pumping.
                               G-5

-------
Plant
Columbus & Southern Ohio Electric Company
Conesville Generating Station, Units 5 and 6
Conesville, Ohio
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status       New
                         2 @ 411



                         Lime

                         Planned
     822

     822
No. 5 - 3/76
No. 6 - 1/78 (?)
Sulfur content of fuel, percent by weight     4.67% coal

Capital cost analysis

  Reported capital cost for 1975            $ 38,661,000
  Corrected capital cost for 1975
                         38,661,000
    Particulate removal equipment adjustment - 8,360,000

    Redundancy adjustment
    Indirect cost adjustment

    Sludge disposal adjustment
                        +26,289,000

                        + 4,973,000C
  Adjusted cost for 1975                      61,563,000

  Adjusted cost per rated kilowatt for 1975           74.89



Notes:

All cost corrections are in terms of 1975 dollars.

   Reported 1975 costs are direct costs  (indirect costs not
   reported).

   Subtracted cost of electrostatic precipitator for particulate
   emission control.

   Added indirect costs.
 j
   Added cost for enlarged pond to extend its life from 5 to 33
   years.  Also added cost for closed-loop piping system and
   associated pumping facilities.
                               G-6

-------
Plant
Dallas Power & Light Company
Texas Electric Service Company
Texas Power & Light Company
Martin Lake Steam Electric Station Unit 1
Rusk County, Texas
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status           New
                                                  750

                                                  750

                              Limestone

                              Under construction 2/77
Sulfur content of fuel, percent by weight    1.5% lignite

Capital cost analysis

  Reported capital cost for  1974            $ 25,218,392

  Corrected capital cost for 1975              28,641,000

    Particulate removal equipment adjustment  -11,990,000

    Redundancy adjustment                      11,439,000
    Indirect cost adjustment

    Sludge disposal adjustment
                                 6,995,000

                                 2,506,000*
  Adjusted cost for 1975

  Adjusted cost per rated kilowatt for 1975
                                37,591,000

                                        50.12
Notes:

All cost corrections are in terms of 1975 dollars.
aAdjusted reported direct costs (1974)  to 1975 dollars.

 Subtracted cost of electrostatic precipitator for particulate
 control.
°Added indirect and contingency costs to adjusted 1975 direct
 costs.
 Added cost of larger sludge pond for extended life to 35 years.

eAdded cost for disposal equipment (clarifiers and vacuum filters)
                               G-7

-------
Plant
Detroit Edison Company
Monroe Units 1, 2, 3, 4
Monroe County, Michigan
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status       Retrofit
                              4 @ 750        3000

                                             3000

                              Limestone

                              Under consideration - 1981
Sulfur content of fuel, percent by weight     2.8 - 3.5% coal

Capital cost analysis

  Reported capital cost for 1981            $ 344,000,000

  Corrected capital cost for 1975             262,600,000a

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment



  Adjusted cost for 1975                      262,600,000

  Adjusted cost per rated kilowatt for 1975            87.53
Notes:
All cost corrections are in terms of 1975 dollars.

   Adjusted reported 1981 costs to 1975 dollars, using reported
   5% escalation.
                                G-8

-------
Plant
Detroit Edison Company
St. Clair Power Plant Unit 6
Belle River, Michigan
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status       Retrofit
                                                     325

                                                     170

                                 Limestone

                                 Under construction - 5/75
Sulfur content of fuel, percent by weight

Capital cost analysis

  Reported capital cost for
                                 4% coal
                                 $ 13,088,000

                                   13,088,000
  Corrected capital cost for 1975

    Particulate removal equipment adjustment   -2,612,000'

   . Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment
  Adjusted cost for 1975

  Adjusted cost per rated kilowatt for 1975
                                    1,411,000"
                                      665,000°
                                    1,141,000

                                   13,693,000

                                           80.55
Notes:

All cost corrections are in terms of 1975 dollars.
 Proportioned & removed cost of venturi for control of particulate
 emissions.

 Since test is for 1 year & ponding not a problem, added a pond for
 19 years additional for system comparison.

°Added costs for ball mill to mill CaCCU (study plant plans include
 CaCO-j purchased ready to use, whereas in operations for a commercial
 operation a ball mill is used).   Also added costs for sludge dewatering
 equipment  (clarifier and vacuum filter).
                                G-9

-------
Plant
Duquesne Light Company
Frank R. Phillips Station Units 1-6
Wireton, Pennsylvania
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status       Retrofit
                                             414.9

                                             138.3

                              Lime

                              Operational since 1973
Sulfur content of fuel, percent by weight     2.3% coal

Capital cost analysis

  Reported capital cost for 1974            $ 32,346,000

  Corrected capital cost for 1975             35,715,000a

    Particulate removal equipment adjustment -25,941,000

    Redundancy adjustment                         -     *°

    Indirect cost adjustment
    Sludge disposal adjustment
                                 682, OOO1
  Adjusted cost for 1975                      10,456,000

  Adjusted cost per rated kilowatt for 1975           75.60



Notes:
All cost corrections are in terms of 1975 dollars.

 a Adjusted reported cost ('70-'74)  to 1975 dollars.

   Proportioned & subtracted cost of venturi scrubbers for particulate
   control and redundant S02 control equipment (spare scrubber train) .
 ^
   Added cost of enlarged pond for extension of life  for an
   additional 17 years.   Cost only includes SC>2 sludge disposal,
   i.e.  does not include fly-ash disposal portion. Present pond
   will be sufficient for 3 years more.
                                G-10

-------
Plant           General Public Utilities Service Corporation
                Pennsylvania Electric & N.Y. State Electric & Gas Co.
                Homer City Station Unit 3
                Homer City, Pennsylvania


Boiler capacity, megawatts                                   650

Boiler flue gas scrubbed, megawatts                          650

FGD system                                    Lime

Installation status       New                 Planned  10/77



Sulfur content of fuel, percent by weight     2.3% Aver.,2.8% Max coal

Capital cost analysis

  Reported capital cost for 1977            $ 60,192,000

  Corrected capital cost for 1975             54,702,000a

    Particulate removal equipment adjustment

    Redundancy adjustment                     -8,608,000^

    Indirect cost adjustment                   4,426,000°
                                                        d
    Sludge disposal adjustment

                                              -2,770,000e

  Adjusted cost for 1975                      47,750,000

  Adjusted cost per rated kilowatt for 1975           73.46
Notes;

All cost corrections are in terms of 1975 dollars.

 a Adjusted reported cost (1977)  to 1975 dollars.

   Subtracted cost of the system's spare scrubber train
   (five trains were installed and only four are required).

   Added interest costs at 8% for 3 years with progressive  payments
   after removing the capitalized value of capability,  escalation,
   reported interest calculated,  & redundancy.  Also added  costs
   for allowance for start-up & modifications (based on 5%  of the
   above costs) and contingency.

   Ponding costs appear high for 10 years service; consequently
   nothing additional was allowed for remaining plant life.
 G
   Subtracted capitalized value of capability $2,770,000.


                               G-ll

-------
Plant
Illinois Power Company
Wood River, Unit 4
East Alton, Illinois
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status       Retrofit
                                             103

                                             103

                              Catalytic oxidation

                           (?) Under construction 8-15-74
Sulfur content of fuel, percent by weight     3.1% coal

Capital cost analysis

  Reported capital cost for 1974            $ 8,295,700a

  Corrected capital cost for 1975             9,860,000b

    Particulate removal equipment adjustment     -     c

    Redundancy adjustment
    Indirect cost adjustment

    Sludge disposal adjustment
                                789,000C
  Adjusted cost for 1975                     10,649,000

  Adjusted cost per rated kilowatt for 1975   103.39



Notes;

All cost corrections are in terms of 1975 dollars.

   Actual reported costs expended over 3.7 year construction
   period to 8/74 and modifications to date.

   Adjusted reported actual costs (1971rl974)  to 1975 dollars,

   Electrostatic precipitators required since system for SO7
   removal tolerates only a small fraction of flyash.      ^

   Added interest for cost of capital.
                                G-12

-------
Plant
Indianapolis Power & Light Company
Petersburg Generating Station Unit 3
Petersburg, Indiana
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status            New
                                             532

                                             532
                             Limestone
                              Planned   4/77
Sulfur content of fuel, percent by weight     4.5% coal

Capital cost analysis

  Reported capital cost for  1974  (Oct.)     $ 32,855,658
  Corrected capital cost for 1975
                              33,400,000'
    Particulate removal equipment adjustment  -4,365,000

    Redundancy adjustment

    Indirect cost adjustment                   5,501,000°
    Sludge disposal adjustment
                               4,584,000C
  Adjusted cost for 1975                      39,120,000

  Adjusted cost per rated kilowatt for 1975           73.53



Notes:

All cost corrections are in terms of 1975 dollars.

 a Adjusted reported 10-74 cost to 1975 dollars.
 r^
   Subtracted direct and indirect costs for electrostatic
   precipitators for control of particulate emissions.
 c
   Added interest for capital with progressive equipment payments
   and increased contingency costs.

   Added costs for a sludge disposal system, including sludge pond,
   piping and pumping for a closed-loop system.
                                G-13

-------
Plant           Kentucky Utilities  Company
                Green River Power Station Units  1,  2,  3
                Central  City,  Kentucky
Boiler capacity, megawatts                    3  @  20          60

Boiler flue gas scrubbed, megawatts                          60

FGD system                                    Lime

Installation status       Retrofit            Under construction  4-75



Sulfur content of fuel, percent by weight     3.8% coal

Capital cost analysis

  Reported capital cost for  1975            $  3,966,156a

  Corrected capital cost for 1975             3,966,156

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment



  Adjusted cost for 1975                      3,966,156

  Adjusted cost per rated kilowatt for 1975          66.10
Notes;
All cost corrections are in terms of 1975 dollars.
 Turnkey operation.
 Costs for Green River's engineering,  operator's training,  etc
 were not reported.
                                G-14

-------
Plant
The Montana Power Company
Colstrip Units 1 and 2
Colstrip, Montana
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status       New
                                             358

                                             358

                              Flyash alkalinity w/Lime

                              Under construction
                                  No.  1   7/75
                                  No.  2   5/76

                              0.77 - 1.0% coal
                                            $  32,633,000

                                              32,633,000
Sulfur content of fuel, percent by weight

Capital cost analysis

  Reported capital cost for  1975/1976

  Corrected capital cost for 1975

    Particulate removal equipment adjustment -11, 258, 000a

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment                 2,066,000

                                               2,554,000C

  Adjusted cost for 1975                      25,995,000

  Adjusted cost per rated kilowatt for 1975           72.61
Notes;

All cost corrections are in terms of 1975 dollars.

 a Subtracted cost of venturi scrubbers for particulate
   emissions control.

   Added costs for enlarged sludge disposal pond to increase
   its life to 30 years.

   Added costs for sludge dewatering  equipment/ including
   clarifier and vacuum filter.
                               G-15

-------
Plant
New England Power Company
Brayton Point Unit I
Somerset, Massachusetts
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status       Retrofit
                                             250

                                              75

                              Metal oxide regenerative

                              Under consideration
Sulfur content of fuel, percent by weight     2.5%  coal

Capital cost analysis

  Reported capital cost for  1975            $  14,811,000

  Corrected capital cost for 1975             14,811,000

    Particulate removal equipment adjustment

    Redundancy adjustment
    Indirect cost adjustment

    Sludge disposal adjustment
                                 530,000'
  Adjusted cost for 1975                      15,341,000

  Adjusted cost per rated kilowatt for 1975   204.55
Notes:

All cost corrections are in terms of 1975 dollars.

   Added allowance for start-up and modifications.
                               G-16

-------
Plant
New England Power Company
Brayton Point Station Unit 3
Somerset, Massachusetts
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status      Retrofit
                                             654

                                             654

                              Metal oxide regenerative

                              Under consideration
Sulfur content of fuel, percent by weight    2.5% coal

Capital cost analysis

  Reported capital cost for 1975           $ 95,000,000

  Corrected capital cost for 1975            95,000,000

    Particulate removal equipment adjustment

    Redundancy adjustment
    Indirect cost adjustment

    Sludge disposal adjustment
                               3,400,000'
  Adjusted cost for 1975                     98,400,000

  Adjusted cost per rated kilowatt for 1975         150.46
Notes;

All cost corrections are in terms of 1975 dollars.

   Added allowance for start-up and modifications
    (5% of direct cost).
                               G-17

-------
Plant           Northern Indiana Public Service Company
                Dean H. Mitchell, Unit 11
                Gary, Indiana
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system                            Wellman-Lord   Allied Chemical

Installation status       Retrofit            Under construction - 12/75



Sulfur content of fuel, percent by weight     3.16% coal

Capital cost analysis

  Reported capital cost for 1975            $ 13,441,000

  Corrected capital cost for 1975             13,441,000

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment



  Adjusted cost for 1975                      13,441,000

  Adjusted cost per rated kilowatt for 1975          116.88


Notes:
All cost corrections are in terms of 1975 dollars.
                               G-18

-------
Plant
Northern States Power Company
Sherburne County Generating Plant Units 1 and 2
Becker, Minnesota
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status           New
                              2 @ 680
1360

1360
                              Limestone
                                                 1-5/76
                              Under construction 2-5/77
Sulfur content of fuel, percent by weight     0.8% coal

Capital cost analysis

  Reported capital cost for  1975            $  60,000,000a

  Corrected capital cost for 1975             60,000,000a

    Particulate removal equipment adjustment     0
    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment
                              -7,056,000'

                             +40,800,000C

                             +   685,000C
                                            -I-  1,260,000

  Adjusted cost for 1975                     95,689,000

  Adjusted cost per rated kilowatt for 1975           70.36
Notes:

All cost corrections are in terms of 1975 dollars.

   Reported 1975 costs are direct costs  (indirect costs hot
   included).

   Subtracted the cost of one scrubber train (twelve provided,
   one to serve as a spare).

 ° Added indirect costs.

   Added costs for vacuum filter and clarifier for sludge
   dewatering.

 e Added cost for sludge pond for S02 sludge only.
                               G-19

-------
Plant
Ohio Edison Company
Pennsylvania Power Company;  Cleveland Electric Illuminating
Co.; Bruce Mansfield Plant Units 1 and 2
Shippingport, Pennsylvania
Boiler rating, megawatts

Boiler flue gas scrubber, megawatts

Process description

Status   New

Sulfur content of fuel, percent by weight
Sludge disposal shown as 42% of costs
Capital cost analysis

  Reported capital cost for 19 77

  Corrected capital cost for 1975

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment

  Adjusted cost for 1975

  Cost per rated kilowatt for 1975
                                  2 @ 917
1834

1834
                                  Lime
                                         .  Unit 1-12/75
                                  Planned:  Unit 2-4/77

                                  4.75% coal
                                  $ 213,200,000

                                    173,400,000a

                                    -25,617,000b

                                     -8,393,000°

                                    +28,354,000d

                                    -25,045,000e

                                    142,699,000

                                             77.81
Notes:

All cost corrections are in terms of 1975 dollars.

a Removed contingency, escalation and interest before correcting to
  1975 dollars.
  Proportioned cost of venturi scrubbers for particulate emission
  control and subtracted same.
c Adjusted cost for spare scrubbing train.
  Added the interest and contingency in terms of 1975 dollars plus
  increased contingency allowance to 20%.  Proportioned engineering
  and field expenses to account for reduced cost of SC>2 control
  only  (i.e., no particulate emission control).
6 Subtracted proportion of sludge transport and site costs in
  proportion to the amount due to particulate emission control.
                              G-20

-------
Plant          Philadelphia Electric Company
               Eddystone Generating Station Unit 1
               Chester, Pennsylvania
Boiler capacity, megawatts                                  325

Boiler flue gas scrubbed, megawatts                         108.3

FGD system                              Magnesium-oxide

Installation status       Retrofit            Under construction



Sulfur content of fuel, percent by weight    2.5 - 3.0% coal

Capital cost analysis

  Reported capital cost for 1972           $ 20,189,500

  Corrected capital cost for 1975            22,887,000a

    Particulate removal equipment adjustment-13,684,000

    Redundancy adjustment

    Indirect cost adjustment                    650,000°

    Sludge disposal adjustment                         ^
    Acid plant, recovery & regeneration       4,984,000
     facilities

  Adjusted cost for 1975                     14,837,000

  Adjusted cost per rated kilowatt for 1975         137.00



Notes;

All cost corrections are in terms of 1975 dollars.

 a Adjusted reported cost (mid '72)  to 1975 dollars.

   Proportioned cost of venturi scrubbers for particulate  control
   and subtracted same.
 ^
   Added interest during construction.
                               G-21

-------
Plant    Potomac Electric Power Company
         Dickerson Unit 3
         Dickerson, Maryland
Boiler capacity, megawatts
Boiler flue gas scrubbed, megawatts
FGD system
Installation status      Retrofit
Magnesium-oxide
Operational
184
 95


9/73
Sulfur content of fuel, percent by weight  3%
Capital cost analysis
  Reported capital cost for                $ 6,500,000*
  Corrected capital cost for 1975            8,242,000*
    Particulate removal equipment adjustment
    Redundancy adjustment
                    Coal
    Indirect cost adjustment
    363,000
    Sludge disposal adjustment                         ,
    Acid and regeneration, etc. facilities   5,075,000
  Adjusted cost for 1975                    13,680,000
  Adjusted cost per rated kilowatt for 1975        144.00

Notes:
All cost corrections are in terms of 1975 dollars.
aAssumed reported costs on  (mid-'72-'73) dollars.
 Adjusted reported costs to 1975  dollars.
°Added cost of capital  - interest of 8% for 16 months with
 progressive payments.
 This adjusted cost includes the  cost of a recovery or regenerative
 system and a by-product acid plant.  This then becomes an
 intergrated unit.
                              G-22

-------
Plant
Public Service Company of New Mexico
San Juan Station Unit 1
Waterflow, New Mexico
Boiler capacity, megawatts

Boiler flue gas scrubbed, megawatts

FGD system

Installation status     Retrofit
                                                    350

                                                    350

                                Wellman-Lord S02 Recovery
                                 System
                                Planned             12/76
Sulfur content of fuel, percent by weight  1.3%

Capital cost analysis  (for one Unit)

  Reported capital cost for 1974           $44,755,000

  Corrected capital cost for 1975           50,044,000a

    Particulate removal equipment adjustment-6,756,000
                                                    Coal
    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment
                                 -3,940,000
  Adjusted cost for 1975

  Adjusted cost per rated kilowatt for 1975
                                 39,348,000
                                        112.42V
Notes:
All cost corrections are in terms of 1975 dollars.
 Adjusted reported cost  (mid  '74) to 1975 dollars.

 Proportioned cost of venturi scrubbers for particulate control
CAdjusted cost of one spare scrubber train  (four provided three
 needed).
 Unit 2's costs are identical.
                              G-23

-------
Plant      Public Service Company of New Mexico
           San Juan Station, Unit 3
           Waterflow, New Mexico
Boiler capacity, megawatts                                550

Boiler flue gas scrubbed, megawatts                       550

FGD system                      Wellman-Lord  SO-  Recovery System

Installation status         New     Under Construction 5/78
Sulfur content of fuel, percent by weight         1.3%   Coal

Capital cost analysis

  Reported capital cost for 1974                  59,199,000

  Corrected capital cost for 1975                 66,195,000a

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment
                                                            b
  Adjusted cost for 1975                          52,431,000

  Adjusted cost per rated kilowatt for 1975               95.33°
Notes;

All cost corrections are in terms of 1975 dollars.

a Adjusted mid-1974 costs to 1975 dollars.
i_
  Proportioned costs similar to San Juan Unit 1 & adjusted for
  redundancy differences.

  Unit 4's cost are identical.
                               G-24

-------
Plant        South Carolina Public Service Authority
             Winyah Generating Station Unit 2
             Georgetown, South Carolina
Boiler capacity, megawatts                                280

Boiler flue gas scrubbed, megawatts                       140

FGD system                                   Limestone

Installation status              New         Planned     5/77



Sulfur content of fuel, percent by weight    1.0%        Coal

Capital cost analysis

  Reported capital cost for 1975             $ 6,818,613

  Corrected capital cost for 1975              6,818,613

    Particulate removal equipment adjustment  -l,838,773a

    Redundancy adjustment

    Indirect cost adjustment                     273,000

    Sludge disposal adjustment                 1,092,000°

    Utilities & Service                        l,411,000d

  Adjusted cost for 1975                       7,756,000

  Adjusted cost per rated kilowatt for 1975           55.40



Notes:

All cost corrections are in terms of 1975 dollars.

a Subtracted direct equipment cost for electrostatic precipitator
  for particulate control and subtracted indirect costs for this
  ESP by proportioning its relative contribution to total direct
  costs.

  Added interest during construction period.  Also added indirect
  costs for sludge pond, utilities and services.

c Added cost for a sludge pond to accommodate expected life of
  plant (30 years).

" Added cost for utilities and services to serve FGD system.


                                G-25

-------
Plant      Southern California Edison Company
           Kaiparowits Generating Station Units I, 2, 3, 4
           Page, Arizona   (Vicinity of)
Boiler capacity, megawatts                     4 @ 750        3000

Boiler flue gas scrubbed, megawatts                           3000

FGD system                                     Lime

Installation status          New    Under Consideration  1981 to 1984



Sulfur content of fuel, percent by weight   0.52% Aver        Coal

Capital cost analysis

  Reported capital cost for 1980              $ 300,000,000

  Corrected capital cost for 1975               189,050,000a

    Particulate removal equipment adjustment

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment



  Adjusted cost for 1975                        189,050,000

  Adjusted cost per rated kilowatt for 1975     63.02
Notes:

All cost corrections are in terms of 1975 dollars.

a Adjusted reported 1980 costs to 1975 dollars.
                               G-26

-------
Plant
Southern California Edison Company
Mohave Generating Station, Units 1 and 2
South Point, Nevada
Boiler capacity, megawatts


Boiler flue gas scrubbed, megawatts

FGD system


Installation status        retrofit
                                   2 @ 790




                                   Lime


                                   Planned
               1580

               1580




               6/77
Sulfur content of fuel, percent by weight


Capital cost analysis


  Reported capital cost for 1977


  Corrected capital cost for 1975


    Particulate removal equipment adjustment


    Redundancy adjustment


    Indirect cost adjustment


    Sludge disposal adjustment
0.6%max.
                                   $ 129,000,000'


                                     110,597,000*
                                     -20,682,000
                                       4,476,000
                                         500,000
                                                  Coal
  Adjusted cost for 1975

  Adjusted cost per rated kilowatt for 1975
                                      94,891,000

                                              60.06
Notes;

All cost corrections are in terms of 1975 dollars.


  Costs estimated by Southern California Edison Co.

  Adjusted reported 1977 costs to 1975 dollars.
c
  Subtracted cost for one spare scrubber train (five scrubber
  trains were provided, only four needed).

  Added costs for sludge disposal pond and pumping.
Q
  Added costs for sludge dewatering.
                                 G-27

-------
Plant      Tennessee Valley Authority
           Widows Creek Steam Plant Unit 8
           Stevenson, Alabama
Boiler capacity, megawatts                                   550

Boiler flue gas scrubbed, megawatts                          550

FGD system             '                    Limestone

Installation status            Retrofit    Under Construction 2/77



Sulfur content of fuel, percent by weight        4.3%       Coal

Capital cost analysis

  Reported capital cost for  1977                $ 55,636,000

  Corrected capital cost for 1975                  49,516,000a

    Particulate removal equipment adjustment      -17,083,000

    Redundancy adjustment

    Indirect cost adjustment

    Sludge disposal adjustment                      2,620,000°

                                                    2,628,000d

  Adjusted cost for 1975                           37,681,000

  Adjusted cost per rated kilowatt for 1975                68.51
Notes:

All cost corrections are in terms of 1975 dollars.
a Adjusted reported 1977 cost to 1975 dollars.
  Proportioned cost of a venturi scrubber for control of particulate
  emissions and subtracted same.

  Added costs for sludge pond to cover the life of the plant
  (20 years) .

  Added costs for sludge dewatering, including a clarifier and
  a vacuum filter.
                               G-28

-------
Plant
Virginia Electric & Power Company
Mt.  Storm
Mt.  Storm, West Virginia
Boiler capacity, megawatts
Boiler flue gas scrubbed, megawatts
FGD system
Installation status        Retrofit
                              2 @ 570.24
                              1 @ 522
                             Limestone
                         Under Consideration
1662.48
1147.11


   6/78
Sulfur content of fuel, percent by weight   2.4-2.8% Coal
Capital cost analysis
  Reported capital cost for 1978            $ 85,739,000
  Corrected capital cost for 1975             69,209,000a
    Particulate removal equipment adjustment
    Redundancy adjustment
    Indirect cost adjustment                   7,716,000
    Sludge disposal adjustment
  Adjusted cost for 1975
  Adjusted cost per rated kilowatt for 1975
                                 5,544,000^
                                 2,404,000d
                                84,873,000
                                        73.99
Notes;
All cost corrections are in terms of 1975 dollars.
a Adjusted 1978 reported costs to 1975 dollars.
  Increased indirect costs.
0 Added costs for sludge disposal pond.
  Added costs for sludge pumping & piping.
                               G-29

-------