United States
            Environmental Protection
            Agency
Office of Air Quality
Planning and Standards
Research Triangle Park NC 27711
EMB Report 78-NMM-10
February 1979
           Air
&EPA      Non-Metallic Minerals

            Emission Test Report
            Edward C. Levy
            Detroit, Michigan

-------
         FUGITIVE EMISSION  EVALUATION REPORT
               NON-METALLIC MINERALS
                   Edward  C.  Levy
                  Detroit, Michigan
                December 19-21,  1978
                  Prepared  for  the
      U.S. Environmental Protection Agency
          Emission Measurement  Branch
Research Triangle Park,  North  Carolina     27711
                     Prepared by
    Clayton Environmental Consultants,  Inc
             25711 Southfield Road
          Southfield, Michigan  48075
              EMB REPORT NO. 78-NMM-10
              Work Assignments 8 and  13
               Contract No. 68-02-2817
                    February 1979

-------
                 TABLE  OF  CONTENTS




                                                    Page




1.0    Introduction                                   1




2.0    Discussion of Results                          2




3.0    Process Description  and  Operation              6




4.0    Observation Locations  and  Emission  Points      7




5.0    Observation Procedures                        10









APPENDICES




A.     Project Participants




B.     Field Data Sheets




       B-l.    Visible  Emissions




       B-2.    Fugitive Dust




C.     Summary of Visible Emissions




D.     Method 22

-------
                   LIST OF FIGURES
Figure                                       Page

  4.1   Plan view of crushing and screening
       operation                              8

-------
                  1.0  INTRODUCTION




    The U.S. Environmental Protection Agency  (EPA)




retained Clayton Environmental Consultants, Inc.  to




conduct both visible and fugitive emissions observa-




tions at the Edward C..Levy Company} Plant No.  2,  in




Detroit, Michigan.  EPA Methods 9 and 22 were incor-




porated to evaluate emissions from the screening  and




crushing operations buildings on December 19 through




21, 1978.




    The results of this study will be used in research




and development efforts for a state-of-the-art  emission




evaluation of slag processing plants.  This study




was commissioned as Project No. 78-NMM-10, Contract




No. 68-02-2817, Work Assignments 8 and 13.

-------
             2.0   DISCUSSION OF  RESULTS




General Observations




    Weather  conditions  during,  the  testing  period  were




extremely poor.   Cloud  cover was very  low, with a




gray sky.  Temperatures  ranged from  30-40F.   These




low temperatures  caused  exce'ssive  steam  to rise from




the hot slag, thus masking actual  emissions.




    Water sprays  were used to  cool the slag




prior to crushing  and to reduce  dust emissions when




transferring the  crushed slag  onto the screens.




When sprays were  used, higher  amounts of steam were




observed emanating from  both the crusher building and




the screening room through doors, windows, cracks,




and chute openings.




    The temperature of the slag varied within the same




pile depending on how recently it had been dumped.




This could account for the great fluctuation of steam




present in the screening room.




    Difficulty was encountered distinguishing between




dust and steam.   Therefore, "less  than"  and  "greater




than" values were incorporated to estimate percent opacity,




It was  assumed that the  steam contained dust particles.




    More dust appeared to be generated by  trucks  on the




haul roads and at  the dump stations  than by  the processes




themselves.  At times these occurrences  interfered with




obtaining emission readings.
                            - 2  -

-------
    The  slag piles  themselves did not appear  to  be  discrete




emission  sources.   Only  steam was observed emanating




from  the  hot slag as  it  was  transferred  to the  crusher




unit.  When the  slag  was dumped onto the grating  for




transfer  into  the crusher  building  however,  much dust  was




generated.  During  the entire study, a constant




shower of dust was  noted;  dust on the data sheets,




on ears,  in the  mouth and  nose.




Screening Building




    More  dust was emanating  from material transfer




points,  i.e., the hoppers, than from the actual




screening.  Dust from the  conveyors and  transfer




points  appeared  to  be dependent upon the amount  and




type  of  material on the  conveyor, wind direction, and




moisture  from  rain  or water  sprays.




    A sand hopper,  located east of the three  blend




hoppers, was a definite emission source.   A steady  plume




of  sand  dust escaped  from  the hopper as  it  filled.




A front end loader would remove the sand which had




accumulated on the ground below the hopper so that  a




truck could drive underneath the hopper to receive  a




load of sand.   The sand dust plume subsided after the




hopper had been emptied and reappeared  as soon as the




hopper began to fill.
                          - 3  -

-------
Screening Room




    For practical purposes, each of the three screens




was considered an emission source.  However, only one




combined reading was reported.   In most cases, steam




and dust were interspersed between and among each of the




screens, making discrete readings of the individual




screens impossible.




    Observations were made while standing in the midst




of the emission due to space limitations,  timeliness




of the project, and at the request of EPA.  This made




it very difficult to determine percent opacities ,




especially with steam present.  However, dust was




indeed present; the data sheets were constantly covered




with a layer of dust.  Better results could have




been obtained if the observer were located, away from




the emission source enabling  vision  of the entire process,




Crusher Building




    Most of the dust was emitted during loading of




the crusher via the dump station located adjacent to




the crusher building.  As was stated above, observing and




distinguishing between dust and steam emissions with the




adverse sky conditions present during the study presented




a problem.  Most of the observations, however, indicated




no visible emissions.  This would usually be the case,




if the material was already cold and water sprays were




used on the transfer conveyor which moves the slag from




the loading station to the crusher.







                        - 4 -

-------
    If steam was present the readings were less than




5-percent.  This is of,course, the best judgement that




could be given to this process in view of the variables




encountered during the observation period.
                         - 5 -

-------
       3.0  PROCESS DESCRIPTION AND  OPERATION
Supplied and completed by EPA.
                        -  6  -

-------
   4.0  OBSERVATION LOCATIONS AND EMISSION POINTS







    Figure 4.1 presents a plan view of the crushing




and screening operation  along with respective observa-




tion points.




    Observation point A  was approximately 200 feet




northwest of the screening building at ground level.




This location permitted  optimum observation of  the




dumping station, the conveyors, and the building  itself.




    Observation of the crusher building initially began




at Point B.  About 40-minutes into the test, observers




moved to location C.  Point C was approximately 200  feet




west of the crusher building at ground level and




provided a better view of the entire operation  including




the slag dumping into the crusher, the chute opening,




and doorway.




Screening Building




    The screening building is approximately 55  feet  above




ground level.  The building and its dumping station  were




observed separately since both were emissions sources.




 Screening  Room




     The  screening  room,  located  about 40  feet




 above  ground  level,  is  approximately  28  x 32  x




 15  feet  high  at  the  building  center.  The observers




 were  located  within  5  feet  of  the  screens.   Background
                         - 7 -

-------
                                                                       Slag  pile
                                                                                         Opacity meter
i

00
                                                    water  sprays
                                                                             Covered
                                                                             conveyor
Screening building-*)
                  -4  Covered return 6onveyor-\
                                                                            ri -—Chute
                      Covered conveyor
                                              To screening operation
                                   Observation
                                   Point A
                                                     Observation
                    \\\   I   /
                       Slag pile
                                                   Slag pile
Observa•
t ion
Point C
             Figure 4.1.    Plan view of crushing and screening operation.

-------
consisted of walls,  floor,  ceiling^ and  railings




which were  covered with gray  colored  accumulated




dust.   Steam was present  throughout the  observation




period; at  times the screens  were not visible.  At




times dust  particles appeared to be so  fine  that




they could  not be seen unless observed  directly




below a light source (0-percent readings were recorded




at this time).




Crusher Building




    Observations at  the crusher building were similar




to those noted at the screening building.  The




building itself was  approximately 30 x 30 x  20 feet high,




and located at ground level.  The building openings




were two doors, a conveyor opening, and a chute opening.




Three-fourths of the crusher was located below ground




level alo^ng the east wall of the building.
                       - 9  -

-------
             5.0  OBSERVATION PROCEDURES






    Visible emission observations were performed  in



accordance with Method 9,  Visual Determination of




the Opacity of Emissions from Stationary Sources  and




Method 22, Visual Determination of Fugitive Emissions




from Material Processing Sources.




    Four one-hour observation periods were conducted




on the crusher building and five periods on the




screening building.  One observation period was




conducted inside the screening room for approximately




one hour.  Further evaluations at this location were




terminated due to difficulties which are discussed




in Section 2.0.  In all cases, the one-hour fugitive




emissions observation periods were divided into three




20-minute segments, with a five minute break between




each segment, as required by Method 22 (Appendix  D).




The fifth evaluation of the screening building was




conducted without any breaks so that the entire test




could be completed before dark.




    Opacity readings were documented simultaneously




with the fugitive emission readings by a certified




visible emissions observer.  "Less -than" and "greater




than" values were estimated when steam was present.
                         - 10 -

-------
In this case, it was assumed that dust was present




in the steam since the processes themselves were of




a dusty nature.   Visible emissions data are summarized




in Appendix C.
                        - 11 -

-------