-------
Table 2.3. (continued)
Aciioo
Requirement
Prmqulsltts
Citation
0
LLW must be disposed of on site: if off-silt
disposal is required due (o lack of capacity,
disposal must be to a DOE facility
Off-site disposal of LLW 10 a commercial facility
requires an exemption from the on-sile disposal
requirements of DOE Order 5820 2A; requests fur
exempli n must be approved by the DOE ORO.
Must m el DOE Order and implementing
procedural requirements for off-site shipments
Shipments of LLW-TBC
Shipmcnis of l.t.W-TBC
DOt Order 5820.2A
DOE Order 5X20.2A
10
UJ
AI.ARA = as low as reasonably achievable
AKAR = applicable or relevant and appropriate requirement
n-'R = Ctnte of Federal Regulations
DOI: = US. Department of Energy
DOT = U.S. Department of Transportation
1-1)1: = effective dose equivalent
IX) = Executive Order
> = greater than
jiul = gallon
< = less ihan
I.DR = land disposal restriction
I.I.W = low-level (...dioactivc) \>aste
nuem = millirem
mSv = millisicven
ORO = Oak Ridge Operations
ORR = Oak Ridge Reservation
% = percent
PCB - polychlorinaicd biphenyl
PPE = personal protective equipment
ppm - parts per million
RCRA = Resource Conservation and Recovery Act nl 1976
SIOU = Surface Impoundments Operable Uml
TBC = to he considered
TDEC = Tennessee Department of Environment and C'mr.ervalion
USC = United Suites Code
-------
radionuclides '.a the ambient air from DOE facilities to amounts thu would not cause any member
of the public to receive an effective dose equivalent of 10 mrem/year or more (-10 CFR 61.92).
40 CFR 61.93(b)(4)(i) requires ..j^oical emission m .e^nts Jl reieu,,. i;"'r with
potential to discharge radionuclides into the air in quantities :hat could cause an effective dose
equivalent in excess of 1 percent of the standard (0.1 mrem/year). All radionuclides that could
contribute > 10 percent of the standard (1 mrem/year) for a release point shall be measured.
TDFC has proposed an equivalent rule in Rules of the Tenness-\ ^ apartment of Environment and
Conservation, Chapter 1200-3-11. Containment and filtration of emissions as needed during
treatment will be required, and dust control measures discussed under the "Fugitive Emissions"
heading will prevent unacceptable emissions of radionuclides during remedial action at SIOU.
To-be-considered guidance from DOE Order 5400.5. "Radiation Protection of the Public
and the Environment," of February 8, 1990. limits exposures to an effective dose equivalent of
100 mrem/year from all exposure pathways and all DOE sources of radiation. The overriding
principle of the DOE Order is that all releases of radioacti"e material shall be as low as
reasonably achievable.
Location-specific requirements set restrictions on the concentration of hazardous substances
or the conduct of activities solely because they are in special locations. Based on current
information for SIOU, the only condition or resource present on or near SIOU that would trigger
location-specific ARARs is that SIOU is located within an historic district. The mitigation
requirements associated with cultural resources and consultation with the State Historic
Preservation Office have already been satisfied.
Performance, design, or other action-specific requirements set controls or restrictions on
particular kinds of activities related to the management of hazardous waste. Selection of a
particular remedial action at a site will invoke action-specific ARARs that may specify particular
performance standard* ui technologies, as well as environment?.! levels for discharged or residual
chemicals. The following text summarizes the action-specific ARARs triggered by various types
of activities anticipated during implementation of the remedial action.
Stormwater Runoff
Stormwater discharges from industrial site activities involving construction operations that
result in the disturbance of 2 ha (5 acres) of land or more have been included in the final rule for
the National Pollutant Discharge Elimination System (NPDES) permits for Stormwater discharges
and incorporated into the TDEC permitting regulations [40 CFR 122; Rules of the TDEC
1200-4-10-.05]. Stormwater discharge requirements are applicable if 2 ha (5 acres) or more are
disturbed; otherwise, they are relevant and appropriate requirements. Compliance with the
T IML Ob" 2-35 September 15. 1997
-------
substantive requirements of the NPDES permitting process for stormwater discharges uuring
construction activities (Rules of the TDEC 1200-4-10-.05) will be required. In particular.
implementation of good site pla-- • P"d hest management practice* to control stormwater
discharges will be required. Stormwater flow controls such as berms, silt fences, hay bales, and
other best management practices will be followed during implementation of the selected remedy
to comply with stormwater runoff ARARs.
Fugitive Emissions
Elevation of airborne paniculate concentrations could result if excavation at SIOU were
not controlled. The TDEC Air Pollution Commission has promulgated applicable requirements
in Rules of the TDEC 1200-5-8-.010, for the control of fugitive dust. An operator must take
reasonable precautions to prevent paniculate matter from becoming airborne. In addition,
fugitive dust may not be released as a visible emission beyond propeny boundary lines for more
than 5 minutes/hour or 20 minutes/day. To ensure compliance with the ORNL site aj' permit
and to meet the substantive requirements of fugitive dust en issior.s, dust suppression measures
(such as water, organic agents, or foams sprayed over the area of concern to prevent dust
generation) combined with ambient air monitoring stations shall be used as a best management
approach for activities during SIOU remediation.
Treatment of Surface Water Removed from SIOU
All waters removed from the impoundments during remedial activities will be sent to
PWTP. The water must first be tested to ensure it meets the WAC for PWTP, and if necessary.
treated before being sent to the facility. PWTP is a part of a permitted NPDES. If PWTP
cannot accept any of the water, a contingency is to use a package treatment plant consisting of
zeolite ion exchange canisters and from there transferring the water to the Nonradiological Waste
Treatment Plant. Any spent zeolite packs must be characterized, and if necessary, managed and
disposed of as a hazardous waste in accordance with 40 CFR 261, 262, and 263 or as a mixed
waste under the Commissioner's Order for the site treatir.en. plan. Section 105 of the FFA, and
DOE Order 5820.2A, "Radioactive Waste Management."
Treatment of Sediments from Impoundments C and D
Sediments and incidental soils from Impoundments C and D will be treated using an
alternate method of disposal per 40 CFR 761.60(e). An alternate method of disposal is required
because no TSCA-permitted incinerators or permitted chemical-waste landfills are currently
available that can also accept the radiological and potentially RCRA-contaminated sediments. The
alternate method of disposal has not yet been finalized; however, chemical dechlorination is the
method used in the cost estimate for the selected remedy. Treatment systems must be evaluated
OT IML.CJE 2-36 Sfpicmner 15.
-------
to de'eTnine the destruction efficiency for PCBs in ;he sediments. If a method other th ..i
chemical dechlorination is used, it will be reviewed and approved by EPA and TDEC with
appropr jte documentation. Protectiveness of hunun health and the environment will be
paramount in selection of the alternate method of disposal. EPA guidance requires that PCBs be
destroyed to a level of < 2 ppm to demonstrate equivalency of performance with a TSCA-
nermitted incinerator. Once destruction requirements for PCBs have been met. the sediments will
exit ". SCA regulatory authority and be eligible for disposal at 2nvir<"care as a mixed wa-te, if
all other WAC are met.
Proposed revisions to the TSCA rules, if finalized, would allow destruction to risk-based
level [proposed Sect. 761.61(c)] or disposal in a landfill that has been deemed protective
(proposed Sect. 761.62). Should methodology capable of the required efficiency be unavailable
for environmental media such as the sediments, the remaining wastes would of necessity be stored
until suitable treatment and disposal facilities are developed.
The sediments from Impoundments C and D may also be RCRA-characteristic waste. The
sediments and incidental soils must be properly characterized per 40 CFR 261. If the sediments
are a RCRA-hazardous waste, LDRs (40 CFR 268) will be legally applicable for disposal of the
wastes at an off-site facility. The sediments will then be treated to meet LDRs and any other
disposal facility WAC. Treatability variances may be required for some of the potential RCRA
constituents. If so, the EPA guidance for obtaining and complying with treatability variances for
soil contaminated with RCRA-hazardous wastes for which treatment standards have already been
set will be followed (Office of Solid Waste and Emergency Respcnse Directive 9347.3-06FS, July
1989). Tanks associated with treatment of the RCRA wastes must comply with RCRA tank
requirements in 40 CFR, Subpan J. Requirements such as secondary containment and closure
of a tank system are included here.
Stabilization of Sediments from Impoundments A and B
Stabilization of sediments and incidental soils from Impoundments A and B will involve
requirements for physically stabilizing the wastes such that the waste can pass the paint filter test
oer RCRA. Subtitle D. ;:r.H can meet WAC of NTS or ot.ier disposal facilities, in addition,
sufficient shielding of the radiological activity must be provided that all other requirements for
transportation, worker safety, public exposure limits, and disposal facility WAC are met.
li? 1ML CJi: 2-37 S*[xcmtxrr 15. IW
-------
Closure of Impoundments
The SIOU scope includes removal and treatment of the sediments and surface water of the
impoundments. Remediation of incidental soils is included only as necessary to support
remediation of the sediments. Contaminated subsoils surrounding the impoundments will be
addressed as pan of the Bethel Valley watershed operable unit (OU) and will be included with
ac'ions for other subsoils. Thus, requirements fcr c'osure -.vitr1 u-sre in place, while relevant.
are not appropriate.
Transportation of Waste for Disposal
Mixed or low-leve1 wastes will be generated during uie SIOU remediation. In accordance
with DOE Order 5820.2A, radioactive waste is to be disposed of on the site where it is generated
if possible; if off-site disposal is necessary because of lack of on-site capacity, disposal must be
at another DOE facility. Because disposal capabilities for the SIOU sediments currently do not
ex it nn ORR, the selected remedy includes off-site disposal of the sediments.
DOT requirements for shipping and packaging (49 CFR 172 and 175) and for transport
on a public highway (49 CFR 177) of hazardous materials will be applicable to remedial actions
at SIOU. General requirements for shipping hazardous materials are defined in 49 CFR 172,
with specific marking, labeling, and placarding regulations for radioactive materials in 49 CFR
172.510. 172.405, and 172.556, respectively.
Regulations governing transportation of hazardous materials by public highway are found
in 49 CFR 177, and specific loading and unloading requirements for radioactive materials are in
49 CFR 177.842. The number of packages in any one motor vehicle must be limited so that the
total transport index number does not exceed 50. The total transport index is the sum of the
numbers expressing the maximum radiation level in millirems per hour at 1 m (3.3 ft) from the
external surface of each package (49 CFR 173.403bb).
EPA and TDEC regulations governing generators and transporters of hazardous waste
found in 40 CFR 262-263 and Rules of the TDEC 1200-1-11-.03 to .04. are also ARAR for
remedial activities at the SIOU. Rules of the TDEC i200-l-l i-.03 (40 CFR 262) requires
generators to ensure and document that the hazardous waste they generate is properly identified
and transported to a treatment, storage, and disposal facility.
Requirements for manifesting [Rules of the TDEC 1200-1-11-.03(3); 40 CFR 262.20-23],
packaging. labeling, marking, and placarding [Rules of the TDEC 1200-1-11-.03(4); 40 CFR
262.30-33] will be followed. In addition, there are record-keeping and reporting requirements
rrouww IML.CJE 2-38 Scrxmncr is. \*K
-------
[Rules of the TDEC 1200-1-11-.03(5); 40 CFR 262.40-43). Pretransport requirements
referenced under DOT regulations 49 CFR 172. 173, 178. and 179 are also applicable.
In the event that an on-ORR disposal facility becomes available, the above regulations for
packaging, labeling, and transport would be relevant and appropriate rather than applicable.
Off-Site reposal of Low-Level Wastes
CERCLA Section 121(d)(3) requires that the off-site transfer of any hazardous substance,
pollutant, or contaminant generated during CERCLA response actions be to a facility that is in
compliance with RCRA and applicable state laws. EPA has established procedures and criteria
at 40 CFR 300.440 for determining whether facilities are acceptable for the receipt of off-site
waste. Per 40 CFR 300.440(a)(4), EPA will determine the acceptability of the facility selected
for disposal of CERCLA wastes. DOE will request the determination from EPA once facility
availability is apparent. Once wastes generated from a CERCLA response action -re transferred
off site, all administrative as well as substantive provisions of all applicable requirements must
be met.
An off-site facility licensed for disposal of radiological waste and approved by EPA to
accept CERCLA waste will be used for sediments from Impoundments A and B. The wastes
must also meet the acceptance criteria of the off-site disposal facility. If the sediments from
Impoundments C and D are RCRA hazardous, they would be treated to meet LDRs before
disposal. After destruction of PCBs and treatment to remove RCRA characteristics, the
sediments would be disposed of as low-level waste.
Decontamination of Equipment
Decontamination activities will include washing equipment and collecting the
decontamination water with temporary sumps connected to PWTP. The decontamination water
must meet WAC for this facility before treatment.
Institutional Controls
Institutional controls will remain in place for SIOU until superseded by the Bethel Valley
watershed ROD. No regulatory requirements specify institutional controls for CERCLA units.
For the containment and long-term management of residual contamination at inactive
hazardous waste sites-,* Rules of the TDEC 1200-l-I2-.08(3)(a)4.(iv) controls are to include, at
a minimum, deed restrictions for sale and use of the property and securing the area to prevent
human contact with hazardous substances. Also, RCRA contains general requirements for
IML/CJE 2-39 Scpcmber 15. IW
-------
institutional controls following closure of RCRA units (40 CFR 264.14). which are relevant and
appropriate for any RCRA waste left on site. Although residual contamination v/ill remain in the
si'rrounding media, these req-. ... '•*• . ::o: Veer: .jded ac TA" -.OU beep
removal of the sediments will not leave waste in place as defined by the scope of this action.
DOE Order 5400.5. Chapter IV, requires administrative (institutional) controls for long-
term management ,.. ureas containing residual radioactivity above guidance levels based on basic
dose limits in the DOE Order.
These and other measures mandated by health and safety standards will continue to protect
workers and the public after remedial action at SIOU is completed and pending remedial action
on the Bethel Valley watershed OU.
COST EFFECTIVENESS
Actions taken under CERCLA must consider the estimated total present-worth cost of
alternatives. Alternative 6 meets regulatory requirements, reduces risk to human health and the
environment to acceptable levels, and allows beneficial reuse of the site, which offsets some of
the cost associated with this remedy. Alternative 6 is considered a cost-effective remedy for the
protection of human health and the environment.
USE OF PERMANENT SOLUTIONS TO THE MAXIMUM EXTENT PRACTICABLE
The selected remedy represents the maximum extent to which permanent solutions can be
used in a cost-effective manner for the SIOU sources at this time. Of the remediation
alternatives, the selected remedy provides the best balance of trade-offs in terms of long-term
effectiveness and permanence; reduction of toxicity, mobility, or volume through treatment;
short-term effectiveness; implementability; and cost. The ir"p::; of any residual contamination
will be assessed in the Bethel Valley ROD; additional action could be taken pursuant to that
decision.
PREFERENCE FOR TREATMENT
CERCLA Section 121 establishes a preference for alternatives that use treatment to
permanently reduce toxicity, mobility, or volume of hazardous substances. The selected remedy
will use stabilization/solidification to reduce mobility of the contamination in the waste removed
from Impoundments A and B. If sampling results indicate that treatment of waste removed from
IML.OE 2-40 S^mhr, I!. IW
-------
Impoundments C and D is needed 10 meet TSCA regulations or disposal facility WAC. perman^..t
reductions of toxicity or mobility could result from implementation of the selected remedy.
The selected remedy, therefore, meets the CERCLA prefeience for treatment.
EXPLANATION OF SIGNIFIC '.NT CHANGES
The proposed plan, which was released for public comment on June 30, 1997, identified
Alternative 6 as the preferred alternative. DOE received oral comments during the public
meeting on July 15, 1997, and written comments as documented in the "Responsiveness
Summary." DOE, EPA, and TDEC reviewed the comments and determined that no significant
changes to the remedy, as originally identified in the proposed plan, were necessary.
REFERENCES
DOE (U.S. Department of Energy). 1997a. Proposed Flan for Surface Impoundments Operable
Unit. Waste Area Grouping 1, Oak Ridge National Laboratory, Oak Ridge. Tennessee,
DOE/OR702-1427&D3/R1. Oak Ridge. TN.
DOt. 1997b. Final Waste Management Programmatic Environmental Impact Statement for
Managing Treatment, Storage, and Disposal of Radioactive and Hazardous Waste,
DOE/EIS-0200-F. DOE, Office of Environmental Management, Washington, DC.
DOE. 1995. Remedial Investigation/Feasibility Study for Surface Impoundments Operable
Unit, Waste Area Grouping 1, Oak Ridge National Laboratory. Oak Ridge, Tennessee,
DOE/OR/02-1346&D2. Oak Ridge, TN.
Energy Systems (Lockheed Martin Energy Systems, Inc.). 1996. Engineering Support
Studies Report - Geo'echnical and Treatabiliry Results for the Technical Work Plan for
Surface Impoundments Operable Unit Engineering Support Studies, X-OE-791. Energy
Systems, ORNL, Environmental Restoration Program, Oak Ridge, TN.
Yu., C., A. J. Zielen, J. J. Cheng, Y. C. Yuan, and L. G. Jones. 1993. Manual for
Implementing Residual Radioactive Material Guidelines Using RESP*D. Version 5.0,
ANL/ESD/LD-2. DOE, Washington, DC.
? IML-CJE 2-41 September 15.
-------
PART 3. RESPONSIVENESS SUMMARY
JTIXMOW? IML.CJE Stjxcmbrr 15.
-------
RESPONSIVENESS SUMMARY
This responsiveness summa: c ihre^ major purposes. Fir?' c rms DOE. EPA.
2"d TDEC of community "~ncerns about the site and the community's preferences regarding the
proposed remedial alternative. Second, it demonstrates how public comments are integrated into
:w decision-making process. Finally, it allows DOE to formally ...ipond to public comments.
This responsiveness summary documents all public comments on the Proposed Plan for
the Surface Impoundments Operable Unit, Oak Ridge, Tennessee (DOE 1997a). The proposed
plan was issued in June 1997; the public comment period was June 30-July 30, 1997. DOE
announced the availability of the proposed plan in The Knoxville News-Sentinel. The Roane
County News, and The Oak Ridger June 30, 1997. A public meeting was held July 15, 1997.
Comments made during the public meeting and those received in writing during the public
v-ommeru period are addr.ssed here.
This summary is prepared pursuant to the terms of the 1992 FFA among DOE. EPA. and
TDEC, as well as other requirements, including.
• CERCLA as amended by the Super fund Amendments and Reauthorization Act of 1986
(42 USC Sect. 9601, et seq);
• NCP (40 CFR 300.430); and
• Community Relations in Super/and, A Handbook (Yu et al. 1993).
COMMUNITY PREFERENCES
DOE received 36 comments on the proposed plan. The.- j comments are summarized with
DOE's responses. DOE recorded 19 public comments at the July 15, 1997, public meeting.
Written comments we— received from the EPA National Remedy Review Board, ORR
Environmental Management Site Specific Advisory Board (ORREMSSAB), Mr. Alfred A.
Brooks, Ms. Janet L. Westbrook, and a commentor v>hose signature was illegible. Two
commentors (including ORREMSSAB) supported selection of the preferred alternative
(Alternative 6) presented in the proposed plan. Four commentors supported selection of
Alternative 3. Clarifications or modifications to alternatives were suggested by 18 of the
comments.
rn»wo7 IML/CJE 3-2 sepemher is.
-------
INTEGRATION OF COMMENTS
The selected remedy described in this ROD includes clarifications of the preferred
alternative based on public input. These c.edifications did not change the intern or the selection
of the preferred alternative.
ISSUES, COMMENTS, AND RESPONSES
Because many comments dealt with similar issues, the comments are categorized into the
issues identified below. The transcript of the public meeting and all written comments are
included in the Administrative Record. Comments from that meeting and written comments
received during the public comment period are either summarized below or presented in full.
DOE's response to each issue follows the statements and summaries of comments for that issue.
ISSUE 1: ALTERNATIVE 6 SHOULD BE THE SELECTED REMEDY
Comment I: ORREMSSAB, July 9, 1997.
[ORREMSSAB] is in general agreement with the preferred alternative (Alternative 6) of.
removal, treatment and disposal of surface impcundment sediments as presented in [DOE's]
proposed plan of June 30, 1997.
Alternative 1 (no action) is unacceptable because of the continued release of contaminants
'o groundwater, leakage through Impoundment B berm, migration of contaminants to surface
water, and resultant unacceptable risk to ecological receptors. The possibility of flooding of the
impoundments also remains a concern under the no action scenario. In addition, the potential risk
to human health if the water cover over the impoundment sediments is lost would be at an
unacceptable level.
Although both Alternative 3 (on-site consolidation cell) and Alternative 6 would prevent
continued releases of contaminants to groundwater. Alternative 6 is preferable because the source
material would be remove^ and this portion of the Bethel Valley area of [ORNL] would not be
restricted from future surface use. This area is desirable for future surface use as it is adjacent
to other well-developed and highly used areas of [ORNL]. Alternative 6 is also preferable to
Alternative 3 because long-term stewardship of the SIOU would not be required. It is also
desirable to create as few waste disposal areas as possible, and by transporting the impoundment
ni.tui.rt-i,- IMI. CJi: 3-3 September 15.
-------
sediments to either an on-site waste management facility (which would accept CERCLA wastes
from many areas on [ORR]) or [NTS], the creation of a waste disposal area solely for the
impoundment sediments would be avoided.
Comment 2: Mr. Pride, Transcript of Public Meeting, July 15, 1997.
From my own personal view I want to also favor A!tern:'ive 6. the cleanup alternative.
Some comments were made to the rem exposure [see Issue 3]. I certainly believe that the costs
probably could be improved from a personal standpoint. But even more so from Janet
fWestbrook]'s viewpoint, I think that the rem exposure is probably very, very high.
And. of course, if you do use this, there's a probability that the transport and disposal
cost to [NTS] would run S20 million-S25 million just for that. So that doesn't count the actual
work activity there. It will be contributing costs.
DOE Response: DOE agrees that Alternative 6 should be ue selected remedy. Comment
I states that, for Alternative 6. "... long-term stewardship of the SIOU would not be required."
While this is true for the wastes included in the SIOU scope, the level of cleanup or long-term
stewardship required to ..JJress the residual conta...ination in soil and groundwater on the SIOU
site will be determined in the Bethel Valley Watershed ROD. For Comment 2, please see the
response to Issue 3 regarding radiation exposures and the response to issue 4 regarding costs.
ISSUE 2: ALTERNATIVE 3 SHOULD BE THE SELECTED REMEDY
Comment 1: Ms. Westbrook, Transcript of Public Meeting, July 15, 1997; and Janet
L. Westbrook, [Written] Comments Made at the DOE Surface Impoundments Project
Public Meeting, Oak Ridge, Tennessee, July 15, 1997, with Notes Added 16 July 1997.
I am a radiological engineer, a Registered Professional Engineer, a Certified Health
Physicist, a resident of Oak Ridge, and a taxpayer. Since some of you will recognize me as
being in the rad protection organization at [ORNLJ, I must state that I am speaking for myself,
as a concerned person, and not for Lockheed Martin or ORNL.
Most of my work involves evaluating radiation work and the associated dose. The choice
of Alternative 6 over Alternative 3 disturbs me for several reasons. [See Issue 3, Comment 1;
Issue 10. Comment 2; and Issue 13. Comment 9.]
IMl CJi: 3-4 ' Scjvii'he' 15. '.•*>*
-------
I suggest that Alternative 3 be chosen. Then take the cost difference between the
alternatives, about S40 million. Take half of it and use it for ether projects. Take the other half.
S20 million, and invest it at, say. 8 percent for 30 years. At the end of that time vou'll have
grown the S20 million to $200 million. Then, if ORNL docs g~ awa> ..i 30 years, you can
further remediate the capped Alternative 3. It will be easier and cost less dose, because the
cesium and strontium will have decayed to half of their original values and the cobalt to about
> percent of its original value.
I made this suggestion in jest, of course, since DOE would never establish a S20 million
trust fund for the impoundments. Yet DOE is willing to spend $53 million and 36 man-rem or
more on it now. Why?
In the DOE method, as best as I could tell from the project fact sheet, each [CERCLA
evaluation] criterion was treated separately and more or less equall) (e.g., five criterion chock
marks in the criterion table might be taken to beat three check marks, even though the criteria
were in fact not of equal importance).
In an optimization study, any "trump" or veto criteria would cause an alternative to be
weeded out at once. However, DOE apparently did not realize that the state would oppose any
action that did not immobilize the waste essentially forever or else did not completely remove the
waste from the site (from the fact sheet: "TDEC stated that Alternative 3 is unacceptable because
the long-term effectiveness of the cell is not protective for the life of the defined risk . . . and also
promotes a strategy of maintaining small pockets of contaminated media throughout ORR that the
state wii; not support"). Thus it appeared that there were two options, 3 and 6, when in fact
there was only one. In that case, the money to evaluate Alternative 3 was unfortunately just
wasted.
I also did not **ve time in the meeting to go into the engineering uncertainties of the
project and this point was only lightly touched on by others. But mcae uncertainties should be
considered seriously especially since, as I did note, the company performing the remediation may
choose to deviate from the method proposed in Alternative 6 and is not required to keep under
the dose estimated. As a radiological engineer, I favor the proven technology, the tested
:echnique, over less predictably controllable methods that may result in more dose, take longer
than planned to execute, etc. I also favor a method that, once the project begins, will minimize
external impacts on schedule, e.g., that will depend on the fewest entities or organizations and
will not depend oii political decisions, such as the opening of NTS to ORNL waste, to be
completed. This is a reason to favor Alternative 3.
uT |MI. OF. ^ 3-5 Sepwinhcr I?.
-------
Comment 2: Mr Brooks. Transcript of Public Mutiny. Julj 15. 1°97.
I have a question on cost. Offhand comment that roughly S35 million an acre is a high
price to pay for land. I would ponu out that the [End-Use Working Giuupj aid not recommend
Alternative 6, and Alternative 3 would fully meet their criteria, which was not to leave any
-.xclusion areas, and I think, as indicated (by DOE during July 12. 1997, presentation], will be
a satisfactory recreational area.
Frankly, my own personal preference would be for [Alternative 6], but only if you can
assure me that you're not going to jeopardize some other project down the road ... [only] if we
could be assured that there is plenty of money to do the things that we have to do and something
of equal importance ... or several things of lesser importance will not be set aside under fully
endorsed Alternative 6.
But under these circumstances, since Alternative 3 docs meet ill the acceptance criteria,
and considering that land across the road certainly wouldn't go more than S10.000 an acre, then
I really can't see the need to return this ... to the pristine state ... especially since right in that
same valley you've got White Oak Creek, and on the next valley over, there will be acres of sites
that have material left, all of those contributing to White Oak Creek. Granted that this is a big
contribution, but that can be another way to lower costs.
We went through a process [East Fork Poplar Creek CERCLA decision] where EPA was
persistent on certain cleanup levels. The public was dissatisfied. It's a matter of record 'vhat
the outcome was. EPA listened to the public. I think as a pan of this process now, you have
the public with you to help you discuss it and reach what seems to be a reasonable conclusion.
I don't think the other conclusion [East Fork Poplar Creek] really factored in public opinion, and
I think now the EPA knows how intensive it can be.
Comment 3: Ms. Sigal, Transcript of Public Meeting. July 15, 1997.
[T]he [End-Use Working Group] has already provided community input on the surface
impoundments, and it's my understanding that we recommended a controlled industrial use,
uhich our definition of that term means that industrial service use is appropriate, soil should be
clean to a depth of 2 ft, shall the soil disturbance permit it, to a depth of 2 ft. No groundwater
use, no use of surface water, and federal government owner,hip. So you have the community
input for this project, and I think maybe you ought to take another look at it and maybe revisit
your alternative because 1 don't think Alternative 6 is what we had in mind when we talked about
controlled industrial use.
*
J|'«aw-i.i- IMI. CJI 3-6 Vpiirnitvr l< 1W
-------
Comrrtnt 4: AJfred A. Brooks, Letter to Margaret Wilson, July 17, 1997.
These comments are based 01. ...~ CERCLA Criteria, .... End-L' Working v
Community Guidelines, and the Recommendations for the End Use of Bethel Valley.
Both Alternatives 3 and 6 generally meet the above requirements; however, in the areas
of remediation worker safety and cost. Alternative 3 is more in tun- with the CERCLA criteria
and community's expressed wishes. Contrary to some public statements, the End-Use Working
Group did not endorse Alternative 6. The [End-Use Working Group's] objectives are to
recommend end uses for contaminated areas, not to recommend remediation methods.
In comparing these alternatives, consideration has been given to the fact that some of the
alleged advantages of Alternative 6 over 3 is simply the transfer of liabilities for ORR to other
sites which are only incrementally better for their accommodation. In addition, the fact that
SIOU and Melton Valley, which will contain future similar subsurface wastes, are on the White
Oak Creek is considered. The uncertainties associated with estimated costs and future budgets
have also been considered in making these judgments.
1. The additional remediation worker exposure of Alternative 6 is significant and contrary
to the Community Guidelines.
2. The cost of Alternative 6 exceeds the cost of Alternative 3 by $37 million for which
".bout [1.5] acres are restored from recreational or iite beautification use to light
building use. Given that a site needs some green areas, this is a high price to pay per
acre for the additional benefit especially with the ready availability of land near by.
A choice of Alternative 6 seems contrary to CERCLA requirements.
3. The requirement 10 reduce the PCB levels to below 2 npir. when the disposal level is
SO ppm is not cost effective especially since the sediment concentrations are only
slightly above SO ppm. DOE should request a waiver and EPA should grant it. To
enforce this regulation would incur the needless expenditure of several millions of
dollars that could be better spent on other cleanup. This would be contrary to
CERCLA's requirement for cost effectiveness.
For the above reasons, [Alternative 3] is preferable to [Alternative 6].
IJ? IMl. OH 3-7 ' S
-------
Comment 5: Signature Not Legible. Letter to Margaret Wilson, JuJy 20, 1997.
I disagree with the selection of Alternative 6 as the preferred alternative for remediation
of SIOIT. I believe that Alternative 3, as presented in the proposed plan, is the option that should
be the selected remedy in the [ROD] for this project.
DOE Response: O\. evaluation of the nine (. tivCL/\ criteria. Alternative 6 oners superior
performance in five criteria (overall protectiveness. compliance with ARARs. long-term
effectiveness, preference for treatment, and state acceptance). Alternative 3 is better in three
criteria (short-term effectiveness, implementability. and cost). Regarding public acceptance, the
last evaluation criterion, both alternatives have received support. Two commentors. including
ORREMSSAB, provided four comments supporting Alternative 6. Four commentors provided
16 comments supporting Alternative 3.
Remedies such as Alternative 3, which incorporates disposal at or near SIOU, can result
in small pockets of contaminated media distributed throughout ORR. The state and
ORREMSSAB oppose the formation of small pockets of contaminated media (see Issue 1,
Comment 1). The permanent requirement for maintenance and monitoring is not reflected in the
cost estimate, which assumes a 30-year project life per EPA guidance. Land use would remain
restricted in perpetuity.
Comment 1 says that the state's "veto" of Alternative 3 indicates the money spent to
evaluate it was wasted. The evaluation of all alternatives was performed according to CERCLA
guidance to develop a range of potential remedial actions. This is done to truly evaluate the
technical ramifications of varying remediation options.
Comment 1 states that the remediation contractor "is not required to keep under the dose
estimated." The estimated doses (see Issue 3, Comment 1) were prepared recently and were not
reviewed by DOE. AI! ~,*j\L contractors are required to ensure that workers are protected and
that radiation exposures are maintained ALARA (see Issue 13, Comment 9).
Commemor 1 favors "the proven technology, the tested technique, ... a method ... that
will minimize external impacts on schedule ... such as the opening of NTS to ORNL waste ...."
Although DOE agrees that these are valuable elements to strive for in the selection of an
alternative, the methods of addressing uncertainties associated with Alternative 6 are considered
reliable. See responses for Issues 7. 8. 9, 10, 11, and 13.
IM1. Ol:. 3-8 Vptcmtvr 15. :*
-------
Comments 1, 2. and 4 address the cost differential between Alternatives 3 and 6, and the
concern thai funding for other projects will not be available if Alternative 6 is selected. DOE
recognizes that Ainding is limited and that expenditures on SiOU may reduce funding available
for other ER projects. However, L>\JC. believes that the expenditures iuf Alternative 6 are
appropriate for remediation of the impoundments (see response to Issue 4). Furthermore, DOE
expe.ts to significantly reduce costs from those projected for Alternative 6 in the proposed plan,
based on the use of a competitive procurement process. Although Alternative 3 would remain
less costly to implement, the cost difference is not expected to apprcnch the amounts discussed
in the comments.
Comments 2. 3, and 4 address the effectiveness of Alternatives 3 and 6 in meeting the
End-Use Working Group Community Guidelines and the Recommendations for the End Use of
Bethel Valley. DOE agrees that both alternatives meet the land use recommendations as stated
in the comments. Alternative 6 is superior to Alternative 3 in meeiing the following End-Use
Working Group guidelines:
• End-use decisions for contaminated lands should not impede the continuing use and
development of ORR lands, and should allow for future employment and research
opportunities.
• Institutional controls in lieu of remedial actions should only be used in cases where
DOE has satisfied the community that further restoration is not feasible.
* End-use decisions should strive to reduce the amount of land requiring long-term
control.
Comment 4 states that "... additional remediation worker exposure of Alternative 6 is
significant and contrary to the Community Guidelines." Pltisc see response to Issue 3.
Comment 4 addresses the EPA requirement for PCB treatment for Alternative 6. Please see
response to Issue 7.
Specific responses to Comment 5 are provided under Issues 5, 6, 7, 8, 9, 10, and 12.
IML.CJi; 3-9 Sepicmhtr 15.
-------
ISSUE 3: RADIATION EXPOSURE TO WORKERS WILL BE HIGH FOR
ALTERNATIVE 6
Comment 1: Janet L. V -t, ,i;. f\V.ntt^n] Comments M- ' -•* the DOE Surface
Impoundments Project Public Meeting, Oak Ridge, Tennessee, July 15, 1997, with Notes
Added July 16, 1997; and Transcript of Public Meeting, July 15, 1997.
Most of iuy work involves evaluating radiation work and the associated dose. The choice
of Alternative 6 over Alternative 3 disturbs me for several reasons.
First consider the collective dose estimates. Altern?'ive "* is estimated to cost around 13
man-rem. while Alternative 6 costs 36 man-rem, nearly three times as much. Note that the
Alternative 6 estimate does not include the dose from babysitting the drums until they are shipped
to Nevada, and that the company doing the remediation is not constrained to use this method or
to keep under the dose estimates.
How much is [36] man-rem conceptually? According to a published DOE report, the
DOE complex and all of DOE in the United States, annual collective external dose ranged from
1.500 to 1,600 man-rem in the years 1990 to 1994. The 36 man-rem would increase that total
by about 2.5 percent.
The ORNL annual collective dose was between 40 and 45 man-rem for the years 1993 to
1995 and was 59 man-rem last year; the 36 man-rem for Alternative 6, if most of the work were
done over a year, would thus nearly double the typical annual collective dose for ORNL, and
would increase it by 60 percent over last year, a very high year. This would mean that ORNL's
typical contribution to the DOE collective dose would be increased to about 80 man-rem. or about
five percent of the typical total.
Second, consider the individual worker's dose. \.".. : does 36 man-rem mean when we
consider individuals? If the work is done over about a year, is that one rem to each of 36
people? Is it 2 rem to each of 18 people? Three rem to each of nine people? In each of the
years 1992 to 1994 in the DOE complex, between 40 r.nd 90 people received 1 to 2 rem of
external dose; having 36 people receiving a rem woulc :hus increase that number by 40 to 90
percent. In those years, nobody in the DOE complex got between 2 and 3 rem. And according
to the DOE report, only one person and in only one year got more than 3 rem. Obviously,
givine 36 people 1 rem or more, or fewer people more in a single operation is not typical of
work in the DOE complex.
IMI. CJi; 3-10 Wpeinhcr 15. IW
-------
In each of the years 1993 to 1995, ORNL': highest single dose was about 950 man-rem.
that is. just under 1 rem; in 1996 the highest dose was 1.3 rem, which only i person got.
Obviously, 36 people getting In. . . i Ceiling i rein etc.. would ' ic a huge increase
in the number of people ;r. the higher bracket at ORNL.
Possibly the collective and individual doses will be spread over more than one year. But
even so, this is a subsiantial chunk of dose to a relatively large rroup of people.
Well, third, if it is urgently necessary to remediate these impoundments, then surely it's
necessary to spend all that dose for the good of the community. As every person involved in rad
work knows, we sometimes have to give some dose to some people in order to save dose to other
people. In this case, those other people are mainly members of the public. But how much dose
to them is being saved? What is the dose to the maximally exposed member of the public if the
impoundments are unremediated? That's Alternative 1 How many people would get a dose
uver, say, 10 mrem"7 I ujn't know, as these numbers do not appear in the DOE fact sheet, only
risks; but the risks have wrapped up in them the assumptions of particular scenarios, usually very
conservative ones.
Still, the doses are presumably fairly significant, or why remediate at all? Significant, that
is, if the water is lost, if the wind is blowing in the right direction, and so forth. Then what are
the respective doses to the members of the public from Alternative 3 as compared to Alternative
6? We are not told what these are, but the risks for these two are given in the fact sheet as the
same over 30 years. Why would there then be a preference for Alternative 6?
The bottom line seems to be that the state wants the radiation to be out of there, period,
end of sentence. That is because to have it off the site and completely out of Tennessee would
leave the site pristine and available. A baby could play in the grass growing on the site. But
available for what? It makes sense to insist on cleanup for a site like K-25 which has lost its
r.ission and would be a community asset if it were made unrestricted or at least only lightly
limited industrial use. But ORNL is not something that's supposed to go away in 30 years. Its
mission is not ended yet. For example, ORNL and DOE are looking for ways to extend the
[High Flux Isotope Reactor's] life another 30 years. .' hy is it that if today we clean up the
surface impoundments to where they no longer constitute a threat to the public or worker health,
we must clean them up to pristine standards and must achieve that today? Why clean up an area
to final release criteria (which, per DOE Order 5400.5, aren't supposed to apply until the area
is actually released), until it is released? I submit that this is not justified.
IM1. OH 3-11 Scplrmher 15 l«*»7
-------
Also, the AL.ARA process, as described and required by 10 CFR 835 (occupational and
rad protection), DOE Order 5400.5 (protection of the public), etc., has not been applied here in
a rigorous form. Optimization proce .. as described in the » us authr ::ive rau r. ..ection
standards and reports, do not appear to be employed in the way that one would expect to see.
This is why the more costly alternative from the money and dose point of view, and the more
dubious, from the technical point of view, seems to be chosen on a single basis—tc get the
ladioactivity out of here. This is a pretty parochial view tor o ir radiologically sophisticated
community to take.
DOE Response: DOE agrees that the cumulative dose to all workers during the remedial
.-iction for the selected remedy will be higher than the dose would be if Alternative 1 (no action)
or Alternative 3 were selected. However, doses will be received over a 4-year period and annual
doses will be reduced accordingly. Controls will be maintained to ensure that no individual
worker receives a dose in excess of allowable DOE or regulatory limits. Furthermore, the
remediation contractor will be required to develop and implement remedial design and health and
s^iciy work plans will institute procedures to ensure that doses to workers implementing the
selected remedy are ALARA. Although upcoming remediation of this site and other ORR sites
to meet the goals established in the June 1997 draft Accelerating Cleanup: Focus on 2006 will
require actions that expose a larger work force to more cumulative dose, this occupational risk
is considered necessary to better manage wastes that are currently releasing contamination to
groundwater and surface water and could potentially release contamination to the atmosphere.
Because exposures of each individual worker will be maintained within acceptable limits and
ALARA for the given remediation scenario, the benefits resulting from cleanup will outweigh the
risks.
DOE agrees that current exposures are acceptable and that extraordinary events (loss of
water cover or direct hit by a tornado) would be required to disperse airborne contamination that
would expose the community to an unacceptable dose. Thes-* -vents ?.re possible, and the
resulting exposed population and internal doses received would be severe. This low-probability,
high-adverse-effect scenario is one driver for remediation. Another is the continuing release of
contamination to groundwater and to White Oak Creek.
DOE also agrees that exposures after completion of Altermtive 3 would be no greater than
exposures resulting from Alternative 6 for the time frame (30 years) considered in the comment.
CERCLA requires consideration of long-term effectiveness, which favors Alternative 6. DOE
agrees that cleanup to "prisiine" standards is not necessary today to meet DOE requirements.
However, this would allow release of the site for other beneficial uses and would eliminate the
need for future actions to address the same wastes.
JT'«J"l»"0" !Ml. CJE 3-12 SepiL-niNrr If. I»T
-------
In summary, although DOE agrees that worker exposure, as evaluated under the CERCLA
shon-tetin effectiveness criterion, favors Alternative 3. this alone is not sufficient to warrant
selection ./. Alternative 3 over Al; ..native 6.
ISSUE 4: COST PROJECTIONS ARE INCORRECT FOR ALTERNATIVE 6
Comment 1: Mr. Unger, Transcript of Public Me*>t:n<;, July 15, 1997.
I have a question about the cost estimate .... You said that Alternative 6 is three times
Alternative 3, yet you don't know how you're going to treat this water for PCBs or sludge for
PCBs. and you also said that there's going to be a lot of other contaminants to be treated. Will
those contaminants be treated by an off-site or by a private company, or will they go through
[ORNL's] treatment system? Does the $64 million [for Alternative 6] include the programmatic
costs, or does that include the contractors coming and taking the waste away and treating it and
(Jibpjsing of this waste.' You want to presuppose maybe letting i contractor come up with an
idea there because I can't imagine that costing $64 million to do that job. I'd like to offer to do
that job for half that right now.
Comment 2: Mr. Brooks, Transcript of Public Meeting, July 15, 1997.
A concern about cost is that the estimated cost for [Alternative 6] was between $20 million
and $30 million, and now it's gone up to $52 million. Furthermore, we have said that the
numbers that we were using in the end-use exercise were consistent with the $6 billion budget
[proposed in Congress for DOE nationwide for FY 1998].
DOE Response: The cost projection of S53.1 million present worth in the proposed plan
is based on a detailed analysis of direct costs (equipment and materials needed, actions to be
pcrformed, crew sizes needed to perform those actions, personnel protective equipment, and
productivity losses necessary to ensure adequate protection of remediation personnel) and indirect
costs (contractor profit and overhead, oversight personnel including profit and overhead, project
design and planning, and others). Contingencies were added to each line item based on the
assumed difficulty or uncertainty associated with the action. The capital and operating costs
(e.g., equipment, materials, worker salaries) are well defined and based on industry standards,
previously executed projects, and standard cost estimating procedures. The indirect costs (e.g.,
profit, overhead, inflation, discount rate) are based on the contracting methodology in place at
ORNL. The remediation contractor's costs in the estimate are on the order of half of the total
project cost.
i\i|. CJL 3-13 Sepicniher I?. :<
-------
The cost for treatment of PCBs and. potentially, fur RCRA hazardous materials was
estimated based on an assumed technology with adequate contingency to address any likely
treatment nic.iiod. Vendors win K* approached to propose any treatment technologies and
remediation methodologies that would meet ARARs and performance specification requirements.
Liquid wastes, pretreated by the vendor as necessary, are assumed to be discharged to the Process
W ;ste Treatment Plant at ORNL, adjacent to the SIOU site. DOE expects the selected vendor's
proposal to be 'ess than the costs used ;n the estimate.
The purpose of the cost projections in the proposed plan is to allow a comparison between
alternatives. The same team of engineers and estimators used the same methods for estimating
costs for all alternatives. The relative cost, with Alternative 6 about three times more costly than
Alternative 3. is considered accurate. Innovative contracting methodologies could significantly
reduce costs, but the relative comparison would remain the same. Pan 2 oi'this ROD shows the
revised cost estimates that reflect the M&l contracting methodology.
Disposal of treated waste from Impoundments A and B in an on-ORR disposal cell could
reduce costs by up to S3.6 million. If final revisions to EPA regulatory requirements allow (see
response to Issue 7), treatment of waste from Impoundments C and D for PCBs could be
eliminated, reducing costs by over S4 million. Even with these potential savings. Alternative 6
would be almost three times the cost of Alternative 3.
In response to Comment 2, the S20 miIlion-S30 million cost for off-SIOU disposal
previously presented to the End-Use Working Group was based on assumptions and a different
scope of work that are not considered valid in the proposed plan. Those cost estimates assumed
no treatment of waste before transport, no requirement to meet DOT containerization or transport
requirements, and stabilization of the sediment in the disposal facility at no cost. The difference
between the costs previously used and the current projections are not a significant change to the
S6 billion budget, but DOE Oak Ridge Operations will bav^ :c revise their budget before
remediation begins.
Cost was not a key factor in the selection of Alternative 6 as the selected rt;;.jdy.
Although more costly. Alternative 6 is the most app-opriate remedy for protection of human
health and the environment. To implement the remedy. DOE will select the most advantageous
contracting methodology and develop the most cost-effective design practical that meets the then-
current regulatory requirements.
n'«ui.w-ti-!M|.cjF. 3-14 Sepicmber 15.
-------
ISSUE 5: COST VERSUS RISK REDUCTION BENEFITS FAVORS ALTERNATIVE 3
Comment I- Signature Not LegiMe, Letter to Margaret Wilson, Ju1 20, 1997. See
AJso Issue 7, Comment 3.
The primary reason that Alternative 3 should be selected is that the projected risks are less
than i x 10* for either Alternative 6 or Alternative 3. >et ihe cost for Alternative 6.
S53.1 million (present vaiue) is 3 times or almost S37 million greater than the cost tor
Alternative 3 (S16.3 million). Selection of Alternative 6 will allow less restricted use of about
2 acres of the 6-acre SIOU site. The difference in remediation costs necessary to reduce, but not
eliminate, industrial land use restrictions comes to over $18 million per acre. Even in the main
area of ORNL. property is not worth this investment.
Although no engineered facility can be guaranteed forever, the proposed plan states that
the Alternative 3 cell will be protective as long as institutional controls are maintained. The risk
assessment in Table 1 indicates that the risk at all receptor locations is less than 1 x 10" for
Alternatives 3 and 6. In other words. Alternative 6 offers no better long-term reduction of risk
as long as institutional controls are maintained at the site for Alternative 3. Even if maintenance
is discontinued, a properly designed disposal cell will last for hundreds or even thousands of
years if no one deliberately disturbs the ccr.tainment features. This level of protection will
eliminate the risk from direct radiation from short-lived gamma emitters which will decay to
nonhazardous elements. The transuranic elements would only be hazardous if they become
airborne. Substantial erosion or intrusion would be needed to expose significant quantities of
transuranics to the atmosphere. The long-term effectiveness of Alternative 3, while not as high
as Alternative 6, is sufficient to preclude tripling the costs to ship the wastes out of Tennessee.
Although the [End-Use Working Group's] goal to reduce the number of sites requiring
lone-term institutional controls and maintenance is admirab'e, there is not enough funding
available to greenfield all currently contaminated sites. In borne cases, remediation in place is
warranted, particularly when risk reduction is the same and significant funds can be saved for
remediation of ether sites SIOU is such a case where remediation in place (Alternative 3) is
warranted and the coato for shipping waste out of my back yard (Alternative 6) is not warranted.
DOE Response: DOE agrees that risks to workers and the public are the same for
Alternatives 3 and 6, while institutional controls for Alternative 3 are effective. DOE also
recognizes that costs for Alternative 3 are much lower. In the vry long term (i.e.,
> l.uOOyears). short-lived radionuclides would have decayed awa., and risks from direct
exposure to gamma radiation would be negligible. However, if institutional controls are lost, an
rr"ntf>r IMI. or 3-15 v-jxemhei 15. i«w:
-------
inadvertent intruder would be subject to unacceptable risks from inhalation of long-lived alpha-
emitting transuranic radionuclides. The selection of Alternative 6 eliminates the need for
permanent institutional controls .. .usus in .he scope of this proje.
ISSUE 6: SHORT-TERM RISKS FAVORS ALTERNATIVE 3
Commert 1: Signature Not Legible, Letter to Marciret Wilson. July 2U, 1997. See
Also Issue 2, Comment 1; Issue 8, Comment 1.
[T]he short-term risk to workers for constructing and operating two treatment facilities and
transporting waste across the country must be significantly greater than the simple operations
proposed for Alternative 3. The remediation and attempted treatment of the K-25 Pond Waste
cost several times the original estimates and resulted in the death of a remediation worker, not
from radiation exposure, but from a simple industrial accident. The likelihood of such an
accident is far greater fur Alternative 6.
DOE Response: DOE agrees that short-term risks favor Alternative 3 as stated in the
above comment. However, key factors for determination of the selected remedy were long-term
effectiveness, reduction of toxicity and mobility through treatment, and state acceptance. DOE
believes the short-term risks are controllable through the use of ALARA studies, engineering,
design, and operations.
ISSUE 7: TREATMENT OF PCBS, REGULATORY ISSUES
Comment 1: Mr. Brooks, Transcript of Public Meeting, July 15, 1997.
[PCBs] are officially designated as B-2 carcinogens, evidence of cancer in test animals,
no evidence in humans. They actually are probably not f..r different than the B-l carcinogen
known as saccharine. I would suggest that the public apply coercion to EPA as to that rather
ridiculous requirement where you have to reduce something by a factor of 25 over [a disposal
facility's waste] acceptance criteria before you can dispose of it.
Comment 2: Ms. Gawarecki, Transcript of Public Meeting, July 15, 1997.
If EPA can issue waivers under CERCLA action, why cannot there be a reasonable waiver
for the TSCA issues whereas the higher PCB waste could be treated to bring it down in line with
the impoundments that have lower levels of PCBs, which some are considerably higher than
IMLXJE 3-16 September 15.
-------
2 ppm. You know, this is a situation where the regulations really g»t in the way of getting the
job dor.i effectively. I think that EPA needs to recognize that and work with it.
It's my understanding that.. ^ ine waste in the two b...-.ier pond. ..wt has the mgher levei.
of PCBs. Would there be a waiver available, for example, if that waste were to be pumped into
the larger ponds and then composite samples taken?
(In response to EPA presentation of EPA requirements, see r"sponse below.) Okay. Well.
be sure and send us all the house and senate bill numbers so we can write in support of this.
Thank you.
Comment 3: Signature not legible, Letter to Margaret Wilson, July 20, 1997.
Alternative 3 does not need to meet [the] unnecessary and costly PCB treatment
requirement thac does net reduce overall risk. PCB treatment is, however, required to comply
with applicable regulations for Alternative 6. If treatment does not sufficiently reduce PCB
concentrations, then the waste will remain classified as TSCA waste, there will be no disposal
facilities that can accept the waste, and the waste would have to be stored indefinitely with
associated maintenance costs and risks of releases not accounted for in the proposed plan.
DOE Response: DOE agrees that, although PCB treatment will reduce toxicity, the
contribution to overall risk from PCBs is negligible, and any of the disposal options considered
(including Alternative 3) would adequately contain the PCBs present in the was"* without
treai.iism. Howevei, if waste is removed from a site and transported off site, CERCLA will not
allow waivers from meeting any applicable regulations. If further characterization confirms
current data showing Impoundments C and D contain TSCA-reguIated waste, once the waste
leaves the site EPA cannot waive the TSCA requirements.
EPA has proposed revisions to the TSCA rules regarding treatment of PCB waste that may
offer some relief to the treatment requirements. The new rules are scheduled to be promulgated
in the first quancr of fiscal year 1998. If the new rules are promulgated before Impoundments
C and D are remediated, DOE will incorporate the modified requirements into the remedial
design and remedial action planning documents for Impoundments C and D, as required.
If the wastes from Impoundments C and D are removed and placed into Impoundments
A and B. all of the waste would be regulated under TSCA.
ijiWOT IM1. CJI: 3-17 Sepicmhcr
-------
If resampling Jata indicate that rhe concentration of PCBs in the waste remc ed from
Impoundments C and D is < 50 ppm, the waste would not be regulated under TSCA and the
:reatmen' '?quirei... >ould r^ ' -^"er apply
ISSUE 8: TREATMENT OF PCBs, TECHNICAL IMPLEMENTABILITY ISSUES
Comn-^nt I: Signature Not Legible, Letter to Mary-.,.. Wilson, J'jJy 20, 1997.
The technical implementability and regulatory uncertainties for Alternative 6 should
preclude its selection. Treatment of mixed waste containing gamma emitters and transuranics to
reduce PCBs to 2 ppm. as would be required for Impoundments C and D, has never been
performed full scale.
DOE Response: As noted in the comment. DOE is not aware of any fully developed
fe.->tment technologies .hat have been demonstrated u reduce PCC concentrations < 2 ppm in
sediment contaminated with fission products and transuranic elements. The activity levels of
radionuclides in Impoundments C and D are very low, thus reducing the concerns regarding
mixed waste treatment somewhat. DOE intends to solicit proposals from private industry to
propose technologies that will meet the then-current regulatory requirements (see response to
Issue 7) based on the final characterization of the waste. Based on the proposals, the remedial
design including the DOE-recommended technology will be submitted to the regulators for
approval. If necessary, a treatability study will be performed to ensure that the selected
technology will meet all regulatory and disposal facility requirements. DOE believes that the
uncertainties regarding PCB treatment can be reasonably addressed within the cost allocated to
this phase of the project and that no revisions to the preferred alternative are necessary.
ISSUE 9: TREATMENT OF RCRA HAZARDOUS WASTE, TECHNICAL ISSUES
Comment 1: Signature Not Legible, Letter to Margaret Wilson, July 20, 1997.
[I]f it is not knwn whether Impoundments C and D are RCRA hazardous, how do you
know if the waste can be treated to meet RCRA Lard Disposal Restrictions?
DOE Response: DOE agrees that if the waste in Impoundments C and D is characterized
as RCRA hazardous based on new sampling data, the waste would have to meet RCRA LDRs
before disposal. As discussed under the response to Issue 8, DOT- will request treatment
proposals from vendors based on final waste characterization results. Vendors may choose to
treat the waste on site to meet RCRA LDRs (if applicable). In addition, Envirocare will accept
rn>»«-(IT IMI. CJi: 3-18 Scpun-.her 15. |wi-
-------
mixed waste for treatment and disposal provided PCB and radionuclide concentrations are within
acceptable levels. After treatment by the vendor for PCBs (if necessary based on new
characterization and then-current regulations), wastes from Impoundments C and D are expected
to meet Envirocare waste acceptance criteria for treatment. As an option, Lnvirocare could then
treat the wastes, most likely using a stabilization process, to meet RCRA LDRs and other
Envirocare disposal criteria. DOE expects that the waste will pass TCLP without treatment and
uas not included addkio..J treatment costs fa' mixeu wjiir treatment. Howe.cr. even if
treatment is required, overall project costs will not significantly increase because of the small
volume of waste in Impoundments C and D. DOE believes that the uncertainties regarding waste
that may be classified as RCRA hazardous are acceptable and that no revision to the preferred
alternative is necessary.
ISSUE 10: AVAILABILITY OF DISPOSAL FACILITIES, STORAGE
Comment 1: ORREMSSAB, July 9, 1997.
On page 10 of the Proposed Plan, it is stated that "Waste would be solidified into
containers meeting DOT requirements and staged on the SIOU site for curing and transport.
After curing, waste would be immediately shipped to the disposal facility." These statements
presume that either tNTS], an on-site waste management facility, or some other facility will be
available when remediation of the impoundment begins. ORREMSSAB hopes that this is the
case. It would be undesirable to store the treated sediments in DOT containers indefinitely.
Comment 2: Janet L. Westbrook, [Written] Comments Made at the DOE Surface
Impoundments Project Public Meeting, Oak Ridge, Tennessee, July 15, 1997, with Notes
Added July 16, 1997.
If the drums of Alternative 6 are generated but cannot be shipped to NTS immediately,
then where will they t tored? Have the costs of building and maintaining a warehouse for them
for several months or years or even decades been considered?
Comment 3: Ms. Walton, Transcript of Public Meeting, July 15, 1997.
I like the NTS thing, and if it's only a DOE order [that prohibits ORNL from shipping
waste to NTS], you should be able to get them to change it. I would hope that would be a
feasible equity-type consideration with regard to the ROD that's coming out of the waste PEIS.
Because if you can't store at NTS, then possibly [Alternative 3] would be better, or we might
07 I Ml. OF. 3-19 September 15.
-------
need to do some more work. Because 10,000 years is a long, long time, and you don't want
to have to have institutional controls on anything that long because you cannot guarantee the long
life of the institutions.
And ... I do have one question. The funding for the NTS disposal versus the funding for
the on-site cell. Is that a wash? Do they cost the same?
Comment 4: Mr. Pride, Transcript of Public Meeting, JuJy 15, 1997.
You indicated that you would not favor going out and solidifying the Nevada option, and
I disagree with that. I think if the process is done correctly you will not have the ground
situation you have at K-25. if you use the correct process control on this. And above-ground
storage or enclosed storage certainly are going to be an alternative in here, relative to no action.
because the Nevada Test Site might not be available from the regulator standpoint.
So I very strongly disagree with no action, if Nevada i., not available. I think we should
include the possibility of the storage here either on concrete pads, as the other transuranic
contaminants are stored, or other options, and go ahead and do this and get this action done.
Comment 5: Signature Not Legible, Letter to Margaret Wilson, July 20, 1997.
[NJone of the proposed disposal facilities can currently accept the waste from
Impoundments A and B. Radionuclide concentrations are too high for Envirocare. ORR is not
on the NTS list of approved generators and the state of Nevada is fighting additional shipment
to the state. The proposed disposal facility on ORR may never be approved and built, and if it
is, may not accept wastes from SIOU. If neither facility is available to accept SIOU wastes, then
either the project would be delayed and releases to the environment would continue or the waste
v ^uid have to be stored indefinitely at great expense and rr-k akin to the K-25 Pond Waste
Management Project. Alternative 3 could be implemented immediately with none of the technical
and regulatory uncertainties.
DOE Response: DOE agrees that as of the date of this ROD, no facilities are available
that can accept treated waste from Impoundments A and B tor disposal. DOE believes that it is
highly likely that NTS will be authorized to accept waste from ORR by the time remediation of
those impoundments is scheduled to begin in FY 2000. There is also uncertainty regarding the
availability of a mixed waste disposal facility on ORR that can accept olOU wastes, but the
possibility exists that such a facility will be available.
rr-«>nw-|i- IMI. or. 3-20 Vpiemher 15. IW
-------
Comment 3 suggested that the administrative impediments to disposal at NTS are internal
to DOE and should be overcome. DOE agrees and expects this will occur, but the decision is
a nationwide issue that is outside the control of this project.
Comment 3 requested a comparison of disposal costs at NTS versus an on-ORR disposal
facility. The proposed plan stated that cost savings of u,> to S5.5 million would result from
disposal on ORR. This was based on expected saving k transportation, overhead, and
contingency and assumed that there would be no disposal fee a: any on-site facility. Current
DOE policy is to consider that capital construction costs for an on-site facility would be funded
separately, and that remediation projects would be assessed a fee of S200/ydJ for disposal. This
would reduce the projected savings to about S3. 6 million.
Comment 4 suggests that remediation of the impoundments should continue regardless of
the availability of disposal capacity, and that waste removed should be stored after treatment.
DOE and several commentors disagree. Such storage would require acres of enclosed storage
facilities, more robust (and more costly) containers, multiple handling and transportation
operations for the same containers, and surveillance and maintenance of the storage facilities and
waste. This would greatly increase worker risk and restrict land use for the interim period until
disposal capacity is available. Total present value costs would increase by almost S7 million.
DOE has determined that no changes to the preferred alternative are appropriate based on
the availability of disposal facilities.
ISSUE 11: EFFECTIVENESS OF DISPOSAL AT NTS, CONTINGENT DISPOSAL AT
AN ON-ORR DISPOSAL FACILITY
Comment 1: ORREMSSAB, July 9, 1997.
If it is determined that an on-siie waste managp'neii. f ':iity can be safely operated at
[ORR] and that waste acceptance criteria include the surface impoundment sediments, it would
be preferable to dispose of the impoundment sediments on-site rather than at an off-site location
because of reduced risks of transportation accidents and reduced costs.
Comment 2: Ms. Walton, Transcript of Public Meeting, July 15, 1997.
What yt>j just said [NTS is in the middle of a desert, there's no public within miles, it's
a dry atmosphere] is a very good reason not to have an on-site disposal cell. F am opposed to
that part of Alternative 6.
IML Of: 3-21 fcpiemhcr 15. !«"7
-------
This idea of an on-siie cell as a disposal si'e isn'i very much different from an
Alternative 3 solution. So I would be very unwilling as a taxpayer to do an Alternative 6, and
then put in an oil-site cell. Because we do have the wrong hydrology and et cetera to have a
long-term storage of this kina 01 stuu here in Oak Ridge.
Is the on-site disposal cell for a panicular class of waste, maybe small level? Because,
you know, a lot ot this stuff is lower-level stuff and this 's vc.y hi^i <»ctivit\. So I don't like that
you're mixing high activity material with low activity material, and then having low activity
material stored in on-site cells is an awful lot different than storing high activity.
Comment 3: Ms. Gawarecki, Transcript of Public Meeting, July 15, 1997.
About 10,000 years age there was an event known as a Pluvial in which all of the
enclosed basins out West and Nevada and Utah were giant lakes. So keep in mind [geologic
changes that can occur] in 10.000 years time.
DOE Response: DOE agrees with Comment 1 that on-site disposal would be preferable
to disposal at NTS if such a facility is available when needed and SIOU wastes meet the waste
acceptance criteria.
DOE understands the concern expressed in Comment 2 that disposal in Tennessee is not
as secure as disposal in Nevada based on climate, hydrogeology, and population. These issues
are being considered and analyzed in a separate CERCLA decision-making process regarding the
evaluation of waste disposal alternatives. On-ORR and off-ORR disposal are being thoroughly
reviewed, and a RI/FS and a proposed plan will be available for review by the public. These
documents will evaluate the on- and off-ORR options based on all CERCLA criteria. If the ROD
for the waste disposal alternatives selects on-ORR disposal based on analysis of CERCLA criteria
including public input, and if SIOU wa«'e meets on-ORR disposal facility's waste acceptance
criteria, it is presumed that disposal at such a facility would be safe and acceptable. Therefore,
designation of an on-ORR facility as a contingency disposal site is considered reasonable and
appropriate.
DOE recognizes the information provided in Comment 3.
JTor.W(p|ML.CIE 3-22 S«T»rn,her 15. IW
-------
. ISSUE 1?: LAND oSE ISSUES
Comment 1: Mr. Brooks, T<"»nscript of Public M""';ng, July 15. 1997
I have a question on cost. Offhand comment that roughly [S35 million] an acre is a high
price to pay for land. I would point out that the [End-Use Working Group] did not recommend
5 i'ernative 6, and Alternative 3 would fully meei their '...:.i. which was not to leave any
exclusion areas. I think, as indicated, [Alternative 3] will be a satisfactory recreational area.
Comment 2: Signature Not Legible, Letter to Margaret Wilson, July 20, 1997.
Alternative 3 meets land-use recommendations and guidelines established by the [End-Use
Working Group] as reported in The Oak Ridger on June 16. 1997. In particular, the [End-Use
Working Group] states that "waste should be relocated only to reduce total risks to people and
the environment." Alternatives matches this guideline much better than Alternative 6.
Recommendations for Bethel Valley Watershed land use are "... it is essential that DOE
remediation decisions achieve, at a minimum, a controlled industrial end use for the entire ORNL
Bethel Valley area. A controlled industrial use should at least provide for surface use of
contaminated lands." Alternative 3 meets this standard. [End-Use Working Group] land use
recommendations continue: "Currently, thj:; are areas where contamination results in the need
for controlled access. Reducing such areas would enhance the overall viability of the laboratory.
Remediation should result in lands that are safe for surface use by laboratory employees."
Alternative 3 meets this standard. "DOE should make the best practical use of existing
browntields while recognizing that not all land needs to be available for every use. If situations
occur where DOE cannot meet the surface use criteria due to excessive risks or costs, these
exceptions need to be discussed openly in a public forum." Alternative 3 provides the fullest
release possible for two thirds of the 6 acre site. The remaining 2 acres would be available for
surface use, proviu<.J no excavation, drilling, or structures penetrate the consolidation cell.
Alternative 3, therefore, already meets the surface use cutenon tor the entire site and exceeds
the criterion for 2/3 of the site. The extra S37 million necessary to allow building construction
on 2 acres in ORNL is not warranted given the availability of underutilized buildings at the East
Tennessee Technology h'ark. the declining missions and excess facilities at Y-12 and ORNL, and
the releases of significant acreage (for example, the Parcel A golf course and subdivisions and
the 1,000 acres at Parcel ED-1) of [ORR).
DOE Response: DOE recognizes the high cost of reducing restrictions on the small area
of land that would be permanently impacted by the consolidation cell .n Alternative 3 by shipping
the waste off site per Alternative 6. This cost is justified, in part, because of the unique nature
rinun-J-ii-: i\i|. OF 3-23 September I?. I*""1
-------
of the property in rhe heart of ORNL. The facility across the street is the High Temperature
Materials Laboratory'. ORNL's long-term plan is to construct an advanced materials
characterization laboratory at the site of SIOU. A consolidation cell could interfere with
development of this or other facilities in their optimal locations. In addition, the selected remedy
was determined based on all of the nine CERCLA evaluate criteria, and not just on cost and
associated land use issues.
ISSUE 13: MISCELLANEOUS ISSUES AND RESPONSES
Comment 1: ORREMSSAB, July 9, 1997.
In descriptions of the preferred alternative (Figure 4 and Page 10), there is discussion that
sediment from Ponds A and B would be removed and allowed to settle in a settling tank. After
settling, the supernatant would be decanted from the tank and returned to the impoundment.
S,;;ietime later, the impoundments would be back-filled with clean soil. There is no discussion
about what would happen to the supernatant. Would it b- treated? Would it be allowed to
percolate into soils and groundwater? The [ROD] needs to specify that any significantly
contaminated supernatant would be treated before release.
DOE Response: DOE agrees. The proposed plan states on page 7, column 1, second full
paragraph that "all water removed from the impoundments will be treated at the existing
[PWTP]." The FS provides additional detail regarding the treatment sequence and the discharge
of all water to PWTP. The description of Alternative 6 in this ROD has been modified to clarify
that surface water in the impoundments will be treated at PWTP.
Comment 2: ORREMSSAB, July 9, 1997.
In Table 1, the short-term effectiveness of the preferred alternative is described as having
the potential for ver, !.;feh, adverse short-term effects. The [ROD] needs to describe how this
potential will be avoided or mitigated.
DOE Response: The proposed plan states on page 14, paragraph 2 under "Short-term
effectiveness," that "For Alternative 6, short-term risks to remediation workers and the public
along the transportation route would be controlled to acceptable levels through compliance with
Occupational Safety and Health and DOT requirements, DOE as-low-as-reasonably-achievable
principles, and project specific health and safety plans as for Alternative 3. However, much
greater control would be needed than for Alternative 3. and more intensive handling of
radioactive waste would significantly increase worker exposure to radiation and the potential for
m»*i
-------
spills or other releases. Transportation of waste would increase the likelihood of accidents." The
analysis remains accurate, and the mitigation proposed will control risks to acceptable levels.
DOE req~ -ements such as spill prevention, control, c ,r,tainment, and cleanup plans; waste
management plans; operationa. .^adiness reviews; and .....er overs.0.n requirements will h^.^
mitigate risks. See also response to Issue 3 comments.
Comment J: .Mr. Jernard, Transcript of Public Meeting, July 15, 1997.
What is the maximum exposure that you expect a citizen, a nonworker, to receive over
the life of [the Alternative 3] cell?
DOE Response: Assuming that there is no failure of the engineered consolidation cell
over the life of the risk and no intrusion into the cell, no exposures to workers or the public
would result from the waste contained in the cell.
Comment 4: Ms. Greer, Transcript of Public Meeting, July 15, 1997.
Can you compare [Alternative 3J to ... [the] Y-12 ... S-3 ponds which are now a viable
... parking lot. Ms. Walton. Transcript of Public Meeting. July 15, 1997. I attended a meeting
on that recently. The problem is the cell hitting the groundwater. So that's why the state wants
them to do something better than that here because it's very hard to guarantee institutional
control for 10,000 years because institutions don't last that long.
DOE Response: A cap was placed over the S-3 ponds at the Y-12 Plant and a parking
lot was constructed on the cap. No liner was placed under the wastes at the S-3 ponds.
Significant quantities of contamination, mostly uranium, technetium, and nitrates, were released
to groundwater before the S-3 site was capped. These contaminants continue to migrate
downgradient. New releases since placement of the cap have been greatly reduced. Alternative
3 proposes removing the wastes from SIOU, constructing a liner at the former location of
Impoundment A with a double leachate collection/detection system, replacing the wastes in the
liner and constructing a cap. This would contain the wastes th*t have not already beer. '•"leased
much more effectively than the cap at the Y-12 S-3 ponds. The cap at SIOU could be used as
green space (e.g., grass and picnic tables). It is possible that a parking lot could be constructed
on the cap, but that would depend on the final configuration of the consolidation cell, the
elevations if the cap and the surrounding roads, and other considerations.
IMLCIEl 3-25 September 15. IW7
-------
Comment j; Ms. Gawarecki, Transcript of Public Meeting, July 15, 1997.
[If] this waste does not meet the criteria to be TRU wiste. could [it] then be treated under
the [request for proposals c J Aaste] mat was just dibC»ss. ...-r this evening?
DOE Response: There is a potential, depend;ng upon the selected technology for
treatment of TRU waste, that SIOU waste could i -' ir.aied using ih<. saj.ie technology and
equipment. Treatment of wastes other than TRU waste has not been considered in the TRU
RFPs. Many details would have to be considered to make use of the TRU facility including
schedule and availability, transportation of sludge, and cross contamination. This idea will be
considered during remedial design.
Comment 6: Ms. Gurney, Transcript of Public Meeting, July 15, 1997.
I wanted to ask a question about the cleanup criteria. We've talked about the
groundwater becoming contaminated because it had a connection with the sediments when the
groundwater levels rose. That says, to me. there's a connection through the clay. Therefore,
I'm wondering have we located the bottom, the depth of contamination, and also, if not, then
how are we calibrating our model that is going to predictably tell us what we've got to clean up?
We don't have any even source term, from what I understand, because we don't have a
good random sampling that will allow us to know that from the top to the bottom what
contamination we're dealing with throughout the pond. My question is, how can you calibrate
the model without proper sampling?
A lot of us here may know that those kinds of contaminants are not going to travel very
far through this type of matrix, and one thing that I'm wondering why it wasn't looked at is why
not look at lowering the groundwater level there just to keep that—you know, a couple of more
alternatives.
DOE Response: The prediction of the radionuclide concentration at a hypothetical
receptor location on White Oak Creek was determined for various levels of sludge removal and/or
stabilization in the impoundments by assuming the following elements:
• assessment of contaminant volumes and radionuclide concentrations from existing
sampling data:
~: IML.CJl 3-26 SffHetnber '5
-------
• source-term modeling to determine the leaching of hazardous constituent from the
impoundments and release to the surrounding soil, bedrock, or man-made features due
to groundwater int .1. »icn :\.c waste;
• groundwater flow and transport modeling from the impoundments to White Oak Creek
(wher? the near-surface groundwater has been fhown to discharge); and
• estimation of modeled contaminant concentrations at White Oak Creek resulting from
surface water dilution of the groundwater flux of contaminants by the Creek's flow.
Because of uncertainties associated with the hydrogeologic system underlying the surface
impoundments and the leaching characteristics of the contaminated sediment, conservative
assumptions were applied to ensure that the predicted concentrations were not underestimated.
In addition, the predicted concentrations from the model were compared with actual samples from
White Oak Creek a:id the surrounding groundwater monitoring wells, and there was good
correlation between the two results.
For source-term modeling, it is assumed that lateral groundwater flow contacts the waste
after liner failure, which releases contaminants from the sediments. Contaminant releases are
modeled using a surface rinse with a solid-to-liquid partitioning mechanism (Kp) for unstabilizeo
sludge and a matrix diffusion-controlled mechanism (effective diffusion coefficient, De) followed
by a surface rinse without partitioning for cement-stabilized sludge. Contaminated groundwater
flow in the stratigraphic units underlying the impoundments and the flow regime to White Oak
Creek were then modeled.
For groundwater transport from the impoundments to White Oak Creek, a conservative,
but realistic, scenario is assumed. Contaminated groundwater travels 30-300 ft in or around
groundwater suppression pipes and storm drain lines urri! it discharges into White Oak Creek.
To complete the transport pathway, an effective 3-in (iG-ft) soil/upper bedrock pathway is
incorporated to hydraulically connect the groundwater suppression and storm drain systems or
to represent other preferential flow paths through porous man-made features.
All radionuclides in the impoundments were modeled, and their relative impact on White
Oak Creek water quality was gauged by comparing modeling concentrations with criteria set forth
in 40 Code of Federal Regulations 141 and DOE Order 5400.5. Strontium-90, which is highly
mobile in the groundwater regime, was the only contaminant signif.rantly affecting White Oak
Creek's water quality. Therefore, this radionuclide was the only contaminant comprehensively
modeled to predict concentrations in White Oak Creek.
IML on 3-27 Stpicmtvr 15. I-WT
-------
The commentur suggested evaluating lowering the water table or evaluation of other
alternatives. Many other remedial technologies and alternatives were evaluated in the feasibility
study that were not presented ir J>fiil in the proposed -'-•' Lowering the •• - • - tabie was
among the technologies considered. That concept was determined to be ineffective because of
the hydrogeology at the SIOU site. The site is in a recharge area and receives groundwater from
most of the main ORNL plant area. Significant volumes of water would have to be pumped
-•oniinuo-.isly to keep the water table from encroaching «. sediment in it? current location.
This water most likely would need to be treated at great cost, l-unhermore. dewatering could
also draw water out of nearby White Oak Creek, and concentrate the contamination in the creek.
This concept was screened out of the feasibility study before development into an alternative.
Comment 7: Ms. Walton, Transcript of Public Meeting, July 15, 1997.
(Wjhen I got this I thought I had a plan and now ... I see it's called a fact sheet ....
And when I heard about the dosage I started looking through this. Well. I didn't see that
in here anywhere. Because my first reaction when I got this, I looked at it. and I looked at your
response to the state, and the EPA comment was, "Welj, this looks pretty good," and I liked it.
DOE Response: The document is a final proposed plan. All recent proposed plans issued
in Oak Ridge have been presented in the "fact sheet" format. The dosage information discussed
in Issue 3 was based on information recently prepared at ORNL that was not reviewed by DOE,
considered in the proposed plan, or placed in the Administrative Record. The commentor,
though employed at ORNL, commented as a private citizen, not on behalf of ORNL or DOE (see
Issue 13, Comment 9).
Comment 8: Mr. Kinunel, Transcript of Public Meeting, July 15, 1997.
What was the risk level associated with the contamination or the migration [of]
contamination at present?
DOE Response: The surface impoundments are in an industrial setting typical of most
national laboratories, with institutional controls such as posted areas, fencing, engineering
controls, and security features. Access to contaminated areas is restricted, and employees
entering SIOU are medically monitored. Because of these active institutional control measures.
risk levels to current human receptors are acceptable and well below EPA criteria.
/TiluiN-i|7 !M|. Oi: 3-28 September 15. IW
-------
Ecological risks are unacceptable only for those receptors (e.g.. fish) living in the
impoundments, and to birds and mammals thai eat those fish. Institutional controls are in place
to discourage p- ' *;on by fish-eating animals. The :lude small r"»sh fenr:~^ to prevent the
entrance and exit of frogs, snak . .artles. etc. and a gri ..k of v.; . jbove in.. ...ipoundrr.
to deter the entrance of water foul and other birds.
Comment 9: Janet L. Westbrook, [Written] Cup .^its Made &. the DOE Surface
Impoundments Project Public Meeting, Oak Ridge, Tennessee, July 15, 1997, with Notes
Added July 16, 1997.
As I noted as an aside in the meeting, I did not have time to go into the detail* of how an
optimization (ALARA) study, which is part of the ALARA process, would have been done for
a project such as this. However, such a study should have been done as pan of the feasibility
study, (i.e., ALARA methods are supposed to be applied from 'he earliest conceptualizing of the
project, not just wh n the project is about to begin. In in oprrr^mion study, the cost and dose
estimates would have been handled first, then the criteria otiier than cost and dose would have
been evaluated in a ranking system established for the purpose.
DOE Response: ALARA methods were considered in the development of every
alternative in the FS. Significant attention was given to development of methods of
accomplishment that would reduce dose to remediation workers. The cost estimates included
substantial costs associated with personal protective equipment, reductions in productivity due to
dress-out requirements, shielding, remote operations, health physics and industrial hygiene
surport, and other safety considerations. ALARA opti-nization studies will be performed, as
appropriate, during remedial design. Under CERCLA, worker dose (as evaluated under short-
term effectiveness) and cost are only two of the evaluation criteria. Determination of the selected
remedy was based on evaluation of all criteria.
/TiiUi.«-||T IMI Cjl: 3-29 ' September 15. I'M?
-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON. D.C 20460
Jut 15 I9f7 office or
SCU9 WASTE AND EMERGENCY
Pt:SPOMS£
f/EMURANDUM
SUBJECT: National Remedy Review Beard Recommendations on the
Surface Impoundment Unit for the Oak Ridge National Laboratory Site
FROM: Bruce K Means, Chair
National Remedy Review Board
TO: Richard D. Green. Acting Director
Waste Management Division . --
EPA Region 4
Purpose
The National Remedy Review Board (NRRB) has completed its review of the proposed
remedial action for the Surface Impoundment Operable Unit of the Oak Ridge National
Laboratory site in Oak Ridge, Tennessee. This memorandum documents the NRRB's advisory
recommendations.
Context for NRRB Review
As you recall, the Administrator announced the NRRB as one of the October 1995
Superfund Administrative Reforms to help control remedy costs and promote consistent and
cost-effective decisions. The NRRB furthers these goals by providing a cross-regional,
management-level, "real time" review of high cost (and thus potentially controversial) proposed
response actions. The Board will review all proposed cleanup actions'where: (1) the
estimated cost of the preferred alternative exceeds $30 million, 9r (2) the preferred alternative
costs more than $10 million and is 50% more expensive than the least-costly, protective,
ARAR-compliant alternative.
The NRRB review evaluates the proposed actions for consistency with the National
Contingency Plan and relevant Superfund policy and guidance. It focuses on the nature and
complexity of the site; health and environmental risks; the range of alternatives that address site
risks; the quality and reasonableness of the cost estimates for altanra'jves; Regional.
Stcte/tribal, and other stakeholder opinions on the proposed aciicns (to the extent they are
known at the time or review); and any other relevant fade. s.
Generally, the NRRB makes "advisory recommendations" to the appropriate Regional
decision maker before the Region issues the proposed plan. The Region will then include these
recommendations in the Administrative Record for the she. While the Region is expected to give
the Board's recommendations substantial weight, other important factors, such as subsequent
public comment or technical analyses of remedial options, may influence the final Regional
decision. It is important to remember that the NRRB does net change the Agency's current
• Prr.'.w n'T. Vecuaa* O. BistO inks O" 100% P.e-r. ceo Pawr (^0% Posico-.sumeO
-------
NRRB Advisory Recommendations
The NRRB reviewed the site package for the Oak Ridge site and dscussed related
issues with EPA Remedial Project Manager Ec'ward Carreras on July 30. 1997. Based on this
review and discussion, the NRRB:
• Finds that the Department of Energy (DOE) proposal does not adequately demonstrate
the cost effectiveness end environmental benefits of the preferred alternative (off-site
disposal). Based on the proposed plan, other alternatives are orotective and achieve
•entedial objectives at significantly lower cost.
• Finds (hat the absence of a site wide management plan impairs the remedy selection
process for this facility. The Board understands that DOE will conduct a number of
actions at the Oak Ridge reservation. In order to enhance the cost effectiveness of
overall site remediation, the Board strongly recommends a comprehensive site-wide
waste management plan be developed expeditiously. This plan should address the
feasibility of the centralized waste management facility described as a contingency under
alternative 6 in the proposed plan. However, development of this plan should not delay
timely and appropriate action for the impoundment areas.
The NRRB appreciates the Region's efforts to work closely with the State and community
to identify the current proposed remedy. The Board members also express their appreciation to
the Region for their participation in the review process. We encourage Region 4 management
and staff to work with their Regional NRRB representative and the Region 4/10 Accelerated
Response Center at Headquarters to discuss any appropriate follow-up actions.
Please do not hesitate to give me a caV if yc" h&ve any questions at 703-603-8815.
cc: S. Luftig
T. Fields
B. Breen
E Cotsworth
J. Cunningham
-------
UNITED STAVES ENVIRONMENTAL PROTECTION AGENCY
REGION 4
ATLANTA FEDERAL CENTER
:,-•:: ALAEAMA STREET. S VJ
ATLANTA. GEORGIA 20202-2:0.:
MEMORANDUM
SUBJECT National Remedy Review Board Recommend ""-ions rn the
Surfl^e Impoundments Operable Unit for the
Oak RJdge National Laboratory Site
FROM Richard D Green, Acting Director
Waste Management Division
EPA Region 4
TO: Bruce K Means, Chair
National Remedy Review Board
Region 4 has received the National Remedy Review Board's (NRRB) memorandum,
dated August 15, 1997, regarding the Surface Impoundments Operable Unit of the Oak RJdge
Reservation in Oak Ridge, Tennessee The Region has carefully reviewed the NRRB's input and
has considered it in addition to other input received on this project from the Department of
Energy (DOE), the State of Tennessee, the Oak Ridge Site Specific Advisory Board (SSAB), and
other stakeholders
In brief, the NRRB found that the DOE proposal for this operable unit did not adequately
demonstrate the cost effectiveness and environmental benefits of the preferred alternative (off-site
disposal). The NRRB further recommended that DOE "expeditiously" develop a "comprehensive
site-wide management plan." However, the NRRB further noted that this comprehensive plan
should not delay timely and appropriate action for the Surface Impoundments Operable Unit.
The Region fully understands the points made by the RRi.-. The Region initially concurred
with a proposal from the DOE for an alternative that would have resulted in the construction of
an on-site waste cell within the ^erable unit. The Region's support for this alternative was based
upon an evaluation of the threshold and balancing criteria of the National Contingency Plan
(NCP). However, information was incomplete at that time c-Mcerning the NCP's modifying
criteria: state acceptance and community acceptance. The three panics to the Oak Ridge
Reservation Federal Facility Agreement (FFA) agreed to embark upon a major public outreach
effort, through the SSAB, that resulted in the formation of the "End Use Working Group," made
up of local citizens and representatives of the SSAB. The purpose of this effort was to solicit
more public input prior to the FFA parties publicly noticing a preference for a remedial
alternative.
Recycied/Recyc^SK?. Pnr.K-d v.,;r. v«-g«?iab«e O>: 8aseO Inks on 100'.. Pec. k-0 ••>.!».»' i*O-.«
-------
The End Use Working Group began meeting in January 1997 and produced a set of
recommendations for th" Oak Ridge Reservation Bethel Valley area including the loc°':~ ~f the
^jrface impoundments, titled "Recomrnen^._..ons for the End Use ui Contaminated Lands in the
Bethel Vaiiey Area of the Oak Ridge National Laboratory." The SSAB also produced~a~?et of
recommendations for the Surface Impoundments and issued a letter stating their concurrence with
the preferred alternative presented in the final proposed plan (off «=••..' Hi-oosal) Copies of these
lettc and recommendations were included in the remedy selection onefing package provided to
the NRRB for the July 30, 1997, review of this project.
In preparation for the release of the final proposed plan, the Region had many discussions
with the DOE and State regarding consideration of the modifying criteria (state and community
acceptance) in addition to the other remedy selection criteria. It was the determination of the
Region that the off-site disposal option, which has the support of the State and community, was
the best alternative considering all of the nine criteria for remedy selection. The DOE decided to
issue the proposed plan for formal public review with off-site disposal as the preferred alternative
The Region has reevaluated its support of the off-site disposal remedy in view of the input
received from the NRRB. However, after consideration of all of the NCP's criteria - including
Mate acceptance and community acceptance - the Region has concluded that we should reaffirm
the appropriateness of our decision that the off-site disposal remedy (with an on-site disposal
contingency should a "Centralized Waste Management Facility" be approved and constructed
under a separate action) represents the best remedy. The need for timely action, the State's
strong opposition to other alternatives, the likelihood of reductions to the total cost based upon
our experience with other DOE projects, and the support of the SSAB were all significant factors
in reaching this decision.
The Region appreciates the efforts of the RRB in their review of {his project. If you have
any questions regarding this matter, please contact Mr. Jon Johnston, Chief, Federal Facilities
Branch, at 404/562-8527, or Camilla Warren, Chief, DOE Remedial Section, at 404/562-8519.
cc: S Luftig
T. Fields
B Breen
J. Woolford
E. Cotsworth
J Cunningham
-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
[ • REGION 4
ATLANTA FEDERAL CENTER
ICC ALABAMA STREET. S.W
*'"• n»c"^ ATLANTA. GEORGIA 30303-3104
SEP 2 4 ".':!
MEMORANDUM
SUBJECT: National Remedy Review Board Recommendations on the
Surface Impoundments Operable Unit for the
Oak Rjuge National Laboratory
FROM: RJchard D. Green, Acting Director ^
Waste Management Division 1
EPA Region 4
TO: Bruce K. Means, Chair
National Remedy Review Board
Tl.c purpose of this nv.-morandum is to provide additional iiuormation in response to the
National Remedy Review Board's (NRRB) August 15, 1997 recommendations concerning final
remedy selection a: the Surface Impoundments Operable Unit of the Department of Energy (DOE)
Oak Ridge Reservation (ORR), Oak Ridge Tennessee As you know, DOE, with the support of the
Tennessee Department of Environment and Conservation and EPA Region 4, has proposed a
remedial alternative for these surface impoundments involving removal, treatment, and off-site
disposal of contaminated materials, with a contingent alternative for disposal at the centralized waste
facility at ORR now under consideration, in the event that such a facility is constructed.
As indicated in our August 21, 1997 memorandum to you, Region 4's support for selecting
this remedial alternative has been based upon consideration of all nine of the remedy selection criteria
specified in the National Contingency Plan, including the modifying criteria of state and community
acceptance to be applied before final remedy selection, as required by the NCP at 40 C.F.R.
§300.430(f)(4). In supplementation of our previous memorandum, we are herein providing additional
information to clarify the basis for our conclusion that this off-site disposal remedy meets the NCP's
cos' effectiveness criterion.
Pursuant to 40 C.F.R. §300.430(f)(l)(ii)(D), cost-effectiveness is to be determined by
evaluating a remedy's lonu term effectiveness and permanence, reduction of toxicity, mobility, or
vol.jme, and short term effectiveness to determine the reneoVs overall effectiveness. Overall
effectiveness is then compared to cost. A remedy is considered to be cost effective if its costs are
proportional to its overall effectiveness.
Cost and Potential Savings
The cost for the preferred alternative presented in the proposed plan was $53.1 million in
present worth value. The DOE has since refined this estimate and the revised estimated cost is $38.7
Recycled/Recyclable « Pnnled with Vegetable OH Based Inks on 100% Rpcyciea Paper (40% Posloonsumer)
-------
million in present worth value. The differences in cost are due to the elimination of certain
contingency factors built into DOE's cost estimates and ^ change in overall site operations strategy
from a Management and Operations Contr-ctor approach to a Managemen* ind Integration
Contractor approach. However, in evaluating the overall cost-effectiv'eness of this estimated outlay
of S38.7 million, one must consider a number of factors which will offset this initial outlay by added
future value and/or savings which will be realized from implementatior, of this alternative
The cost of the remedial action will be partially offset by the value of rcutilization of the
specific parcel of land currently occupied by the impoundments The DOE currently has preliminary
plans for the use of that parcel for a new. research facility. Beneficial reuse of this land parcel, located
within the heavily industrialized portion of the Laboratory, will help to ensure the overall continued
economic contribution to the local and regional economy
The cost of the remedial action will be additionally offset by the continued viability and
desirability of the overalJ Laboratory for future use The Oak Ridge National Laboratory is a national
resource that has historically distinguished itself by making many significant contributions to national
research and development efforts This Laboratory' and its highly s^ iiled scientific community is a
major economic engine supporting eastern Tennessee Relocation of these waste materials will avoid
stigmatizing the Laboratory area by commingling waste disposal areas with research facilities This
will help maintain the attractiveness of the facility and thereby enhance the likelihood that it will
continue to be a national scientific resource.
Utilization of a centralized waste disposal facility (either off Oak Ridge Reservation or, under
the contingent scenario, within its boundaries) will significantly reduce overall DOE costs for
maintenance, monitoring, and other controls, when compared with the need to maintain many smaller
disposal cells. The Reservation is pursuing a strategy where CERCLA generated wastes will be
consolidated into one large (1 million yds3) modem waste management facility. The utilization of one
large facility is expected to result in a lower cost over the long term than'would numerous small and
scattered disposal cells. Significantly, such consolidation of radioactive waste, including use of both
off-site disposal and centralized on-site disposal in combination, has been key to the overall strategy
for remediation of other major DOE sites -- with the full support of EPA.
The preferred alternative also may avoid significant future costs which would be incurred for
readdressing remedial alternatives not in compliance with current Tennessee policy specifying a State
go?I that ORR radioactive wastes which require long-term institutional controls ultimately be
relocated. If maintained, this policy could cause future costs to be incurred for all disposal
alternatives except for the preferred alternative.
Long Term Effectiveness and Permanence
The preferred alternative involves the consolidation of the impoundment's waste with other
similar w?stes at the Nevada Test Site Environmental conditions at the Nevada Test Site are much
more compatible with the long term containment of radioactive wastes when compared to the
hydrogeology of eastern Tennessee. The low rainfall and deep groundwater conditions present at the
-------
Nevada 1 est Site make that facility more effective as a permanent disposal facility for these
radioactive wastes than presently available on-site alternatives If the Centralized Waste Management
facility, similar in construction to a large RCR/ subtitle C facility, is constructed ... 'he Reservation,
that facility will also provide greater permanence than presently available alternatives (and at a lower
cost than disposal at the Nevada Test Site).
«
Accordingly, a significant part of the increased cost associated vith the preferred alternative
is jusri ::d by the increase in prrrr^nence achieved by thir alierr.ativj. Such pecmanence ii particularly
important here because of the transuranic constituents within the surface impoundment waste
materials.
Reduction of Toxicity. Mobility, or Volume
The treatment provided under the preferred alternative will significantly reduce the mobility
of the radioactive contaminants being remediated. This reduction in mobility will enhance the
permanence of the preferred alternative over the other alternatives not including treatment. Another
enhancement to permanence will be achieved by the preferred alternative's provision for the reduction
of the toMcity through destruction of the PCBs in two of the impoundments.
These enhancements to permanence achieved through treatment, in accordance with
CERCLA's expressed preferences, also justify a portion of the preferred alternative's incremental cost.
Short Term Effectiveness
Although no pan of the cost increase associated with the preferred alternative is justified by
short-term effectiveness considerations, it should be noted that this alternative fully satisfies this
remedy selection criterion. The preferred alternative includes engineered and administrative controls
to ensure that protection of the public, workers, and environment are maintained during
implementation of the remedy, which is achieved within a reasonable time period.
Conclusion
Based on the analysis summarized above, Region 4 has concluded that the cost associated
with the preferred remedial alternative for the Surface Impoundments Operable Unit at the Oak Ridge
Natioi.u' Laboratory are proportional to this remedy's overall eflei.t'veness. Increases in cost over
otner alternatives ~ especially Considering added future value and/or savings — are justified by this
remedy's long-term effectiveness and permanence with respect to the radioactive contaminants being
remediated and the remedy's utilization of treatment which reduces the mobility and toxicity of the
wa.-'p materials in accordance with statutory preferences.
If you have any questions regarding this matter, please contact Mr. Jon Johnston, Chief,
Federal Facilities Branch, at 404/562-8527, or Camilla Warren, Chief, DOE Remedial Section, at
404/562-8519.
-------
cc. 3 Luftig
T. Fields
B Breen
J. Woolford
E. Cotsworth
J. Cunningham
-------