PB98-964024

                                EPA 541-R98-104

                                November 1998
EPA Supei fund

      Record of Decision:
      Calhoun Park Area
      Charleston, SC
      9/30/1998

-------
           ENFORCEMENT
        RECORD OF DECISION
   REMEDIAL ALTERNATIVE SELECTION
    CALHOUN PARK SUPERFUND SITE
  CHARLESTON, CHARLESTON COUNTY
          SOUTH CAROLINA
           PREPARED BY:

U.S. ENVIRONMENTAL PROTECTION AGENCY
             REGION IV
         ATLANTA, GEORGIA

-------
               DECLARATION FOR THE RECORD OF DECISION

SITE NAME AND LOCATION

Calhoun Park Area Superfund Site
Charleston, Charleston County, South Carolina

STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action for the Calhoun Park Area
Superfund Site (the Site) in Charleston, South Carolina, which was chosen in accordance
with the Comprehensive Environmental  Response, Compensation,  and Liability Act of
1980 (CERCLA), as amended by the Superfund Amendments and Reauthorization Act of
1986 (SARA), 42 U.S.C § 9601 etseq.. and, to the extent practicable, the National Oil and
Hazardous Substances Pollution Contingency Plan (NCP), 40 C.F.R. Part 300 et seg. This
decision is based on the administrative record for this Site. The State of South Carolina,
acting as a support agency,  concurs with the selected remedy.

ASSESSMENT OF THE SITE

Existing soil and groundwater contamination at this Site, consists mainly of BTEX and
PAHs,  is attributable to the previous manufactured  gas  plant operations. Actual or
threatened releases of hazardous substances from this  Site,  if  not • addressed by
implementing the response action selected in this Record of Decision (ROD), may present
an imminent and substantial endangerment to human health.


DESCRIPTION OF THE SELECTED REMEDY

This remedial action addresses NAPLs source areas, shallow groundwater contamination,
and contaminated soil  as the principal threat at this Site. Sediment and  surface water
contamination, in addition to intermediate groundwater contamination will  be addressed
in a separate ROD.

The major components of the selected remedy include:

a    Excavation and transportation of contaminated soils to a permitted landfill followed
      by the backfilling of the excavated areas with clean fill;

G    Source removal of NAPLs from both the shallow and  intermediate aquifer;

D    Treatment of groundwater plume through a combination of recovery wells/filtration
      system and phytoremediation;

G    Additional sampling of surface water and sediment, following mitigation of coal tar
      discharge into Cooper River, to fully delineate extent of contamination and potential
      threat to aquatic and terrestrial life.

-------
STATUTORY DETERMINATIONS

The selected remedy is protective of human health, complies with Federal and State
requirements that are legally applicable or relevant and appropriate to the remedial action,
and is cost effective.  The groundwater portion of the remedy was  based  on EPA's
expectation that the remediation of groundwater to MCLs will be challenging given the
presence  of  NAPLs at this  Site.  Therefore a  phased approach has been  selected
consisting of removal or treatment of NAPL to the maximum extent practicable, followed
by containment of potentially non-restorable source areas, and restoration of aqueous
contaminant plumes.

This selected remedy will result in  contaminated groundwater remaining on-Site above
health-based levels until remedy implementation is complete. Therefore, five (5) year
reviews will  be conducted after initiation of remedial action to insure that the remedy
continues to provide-adequate protection of human health and the environment.
Richard Green
Division Director

-------
1.0    SITE NAME, LOCATION, AND DESCRIPTION	  6

2.0    SITE HISTORY AND ENFORCEMENT ACTIVITIES	,	6
      2.1    Previous Site Operations  	6
      2.3    Previous Investigations and Containment Measures  	  9

3.0    HIGHLIGHTS OF COMMUNITY PARTICIPATION 	  11

4.0    ADDITIONAL EARLY RESPONSE ACTIONS	  12

5.0    SUMMARY OF SITE CHARACTERISTICS	  12
      5.1    Physical Characteristics  	  13
            5.1.1 Demography	  13
            5.1.2 Meteorology	  13
            5.1.4 Surface Water Hydrology	  14
            5.1.5 Geology/Hydrogeology	  14
      5.2    Nature and Extent of Impact	  15
            5.2.1 Surface/Subsurface Soils	  19
            5.2.2 Groundwater	  19
            5.2.3 NAPLs 	  25
            5.2.4 Sediments	  27
            5.2.5 Surface Water  	  29

6.0   SUMMARY OF SITE RISKS	29
      6.1    Human Health Baseline Risk Assessment 	  30

7.0   DESCRIPTION OF ALTERNATIVES	  33
      7.1    Development of Cleanup Levels	  33
            7.1.1 Soils	  33
            7.1.2 Groundwater/NAPL 	  34
      7.2   Soil Alternatives 	  38
            7.2.1 Alternative 1: No Action	  38
            7.2.2 Alternative 2: Natural Attenuation  	  38
            7.2.3 Alternative 3: Surface Cover/Capping  	  39
            7.2.4 Alternative 4: In Situ Bioremediation 	  39
            7.2.5 Alternative 5: Excavation, Chemical/Biological Treatment,
                   & Replacement  	  39
            7.2.6  Alternative 6: Excavation, Thermal Desorption, & Replacement
                   	  39
            7.2.7  Alternative 7: Excavation & Off-Site Incineration	40
            7.2.8  Alternative 8: Excavation & Off-Site Landfill	  40
      7.3   Shallow Groundwater	  40
            7.3.1  Alternative 1: No Action  	  40
            7.3.2  Alternative 2: Institutional Controls	  40
            7.3.3  Alternative 3: Institutional Controls, Source Removal,
                   Phytoremediation, and Natural Attenuation	 41
            7.3.4  Alternative 4: Institutional Controls, Source Removal,
                   Phytoremediation. and In Situ Bioremediation  	 41

-------
            7.3.5  Alternative 5: Institutional Controls. Source Removal,
                   Phytoremediation, Grout Curtain, Vertical Wells, Separation,
                   Filtration, GAC, and POTW Discharge	  41
            7.3.6  Alternative 6: Institutional Controls, Source Removal,
                   Phytoremediation, Sheet Piling, Vertical Wells, Separation,
                  Filtration, GAC, and POTW Discharge	  41
            7.3.7  Alternative 7: Institutional Controls, Source Removal,
                   Phytoremediation, Interceptor Trenches, Separation,
                  Filtration, GAC, and POTW Discharge	  42
            7.3.8  Alternative 8: Institutional Controls, Source Removal,
                  Phytoremediation, Vertical Wells, Separation, Filtration,
                  GAC, and POTW Discharge	  42
      7.4   Intermediate Groundwater  	  42
            7.4.1  Alternative 1: No Action 	  42
            7.4.2  Alternative 2: Institutional Controls	  42
            7.4.3  Alternative 3: Institutional Controls and Natural Attenuation ...  42
            7.4.4  Alternative 4: Institutional Controls and In Situ Bioremediation .  43
            7.4.5  Alternative 5: Institutional Controls, Vertical Wells,
            Separation, Filtration, GAC, and POTW Discharge 	  43

8.0   SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES 	  43
      8.1   Overall Protection of Human Health & the Environment
              	  43
            8.1.1  Soil		  44
            8.1.2  Shallow Groundwater/NAPL	  46
            8.1.3  Intermediate Groundwater	  50
      8.8   STATE ACCEPTANCE	 .  . . :	  50
      8.9   COMMUNITY ACCEPTANCE	  51

9.0   THE SELECTED REMEDY	  51
      9.1   Soil - Excavation and Off-Site Disposal  	  51
      9.2   Groundwater/NAPL	  52
            9.2.1   NAPL/Groundwater  	  52
      9.3   Cost Summary	  53

10.0  STATUTORY DETERMINATIONS 	  54
      10.1  Protection of Human Health and the Environment  	  54
      10.2  Compliance with Applicable or Relevant and Appropriate
            Requirements 	: :	  55
      10.3  Cost Effectiveness	  55
      10.4  Utilization of Permanent Solutions and Alternative Treatment
            Technologies or Resource Recovery Technologies to the
            Maximum Extent Practicable	  56
      10.5  Preference for Treatment as a Principal Element	  56

-------
FIGURES

Figure 1-1  (Site Map)	7
Figure 5-1  (Stratigraphic Cross Section)	16
Figure 5-2 (Soil & Groundwater Sampling Locations)	17
Figure 5-3 (Sediment & Surface Water Sampling Locations)	18
Figure 5-4 (Benzene Isoconcentration Map for Shallow Groundwater)	22
Figure 5-5 (Total PAH Isoconcentration Map for Shallow Groundwater)	23
Figure 5-6 (Naphthalene Isoconcentration Map for Shallow Groundwater)	24
Figure 7-1  (NAPL/Groundwater Remediation Locations)	37
TABLES

Table 5-1 (Chemicals Detected in Soil)	20
Table 5-2 (Chemicals Detected in Shallow Groundwater)	21
Table 5-3 (Contaminants Detected in Intermediate Groundwater)	26
Table 6-1 (Carcinogenic & Non-Carcinogenic Risks)	32
Table 7-1 (Soil Preliminary Remediation Goals)	35
APPENDIX

Appendix A  (State Concurrence Letter)
Appendix B  (Responsiveness Summary)
Appendix C  (Public Meeting Transcript)

-------
                                                              Record of Decision
                                                                 September 1998
                                                              	Page6
1.0   SITE NAME, LOCATION, AND DESCRIPTION

The Calhoun Park Area Superfund site (hereinafter referred to as "the site") is located in
Charleston, South Carolina. The general location of the site is depicted in Figure 1 -1. The
site consists of an electrical substation and an abandoned city park as well as portions of
the Ansonborough Homes housing project, Ludens Marine, and the National Park Service
property

The site under investigation initially consisted of an 18 acre area comprising an electrical
substation, an abandon city park, and the Ansonborough Homes housing project. Based
on initial sampling data the investigation was later expanded to include Ludens Marine, the
National   Park  Service  property,  the George  E.   Campsen  property,   Dockside
Condominiums, and the Deyton property. Presently these properties consists of a mixture
of industrial, commercial and residential land usage. A detailed figure of these properties
is illustrated in Figure 1-1.
2.0   SITE HISTORY AND ENFORCEMENT ACTIVITIES

2.1   Previous Site Operations

Historically the various properties which comprise the site have been used for several
purposes including a manufactured gas plant (MGP), a steam generating plant, a sawmill,
a rosin wood treating operation (Fernoline Chemical), and a shipyard. The MGP operated
on the location of the present electrical substation. The Ludens marine property originally
housed a steam plant supporting the MGP operations. This same building was later
converted to a ship repair/marine retail store known as Ludens Marine. Both the sawmill
and the rosin wood treating company operated at the present location of the abandon city
ballpark. The rosin wood treating operations also utilized portions of the Ansonborough
Homes property. Shipyard operations were previously performed at the present location
of the NPS property, Dockside condominiums, and the Deyton property.

While many of these past operations may have contributed to the environmental impact
upon this area, the MGP was the major contributor for contamination at this site. This is
evidenced from both the composition of waste present and  the distribution of this waste
relative to the former MGP location. For these reasons the following historical information
focuses on the MGP operations.

Manufactured Gas Plant operations began at the site in  the 1850's with the construction
of a Manufactured Gas Plant (MGP) located on the property presently occupied by the
electrical substation. Manufactured gas, also referred to as town gas, was produced at the
site under two basic processes known as coal carbonization and carbureted water gas.
The MGP was originally constructed in 1855 as a coal gasification plant and operated in
this manner until 1910 at which time operations were

-------
 C  00
    Qw
    J3
<*••  6
 o  5

"
               Q.

               ro




               0)
              4—*


              CO
               05

-------
                                                                Record of Decision
                                                                  September 1998
                                                               	PageS
 converted to a carbureted water plant which continued to produce gas until the plant
 closed in 19571.

 The coal carbonization process consisted of three steps where coal was first heated to
 generate  a  gas. The gas was then collected and cooled using both a condenser and
 scrubber. The gas was then purified by passing the gas through a filter material and finally
 sent to a gas holder tank for storage. The carbureted gas operations consisted of passing
 steam over a bed of hot coal which generated a product called "blue gas". To enrich the
 heat value of blue gas, it was next passed through a carburetor unit. In this unit oil was
 sprayed over hot bricks in the presence of blue gas. This process in turn produced an oil-
 enriched blue gas. The oil-enriched gas was passed through a super-heater where the oil
 vapors  were "cracked" to simpler gasses. Finally the  gas was then sent through the
 condenser/scrubber/purifier process and sent to the gas holder tank for storage.

 Waste areas typically associated with MGPs include the general area surrounding the gas
 holder tanks. Here waste products consisting of oils and PAHs would precipitate out of the
. gas suspension, collect in the bottom of the gas holder tanks, and infiltrate into adjacent
 soils. The location of the gas holder tank, in addition to a series of smaller tanks can be
 seen in the  northwest portion of Figure 1-1.  As evidenced at this site these gas holders
 were usually partially buried within the soils.

 MGP operations also generated a waste fluids stream containing an emulsion  of oils,
 PAHs, and water. This emulsion would be sent to a water/oil separator to recover the oils
 and discharge the water to a drying pond or nearby water body. The separator worked by
 slowing the  flow of the mixture which in turn allowed the oils and PAHs to float to the top
 where they were removed with a skimmer and recycled or sold depending upon the quality
 and/or the local demands for such mixtures. The water portion of this waste stream was
 discharged  to  local  water bodies. Historically there  were  problems  associated with
 incomplete  separation of the emulsion.  In general carbureted water-gas plants were
 universally  known to have^chronic problems with  the separation process2 and that the
 waste water containing oils and PAHs were typically discharged into streams with some
 of the oils depositing on the banks of the stream3.

 A plant design drawing dated April 28, 1941 revealed that in the past plant waste water
 was discharged to the Cooper River via a pipe at a location corresponding to the pre-1940
       'Draft Final Remedial Investigation Report, Calhoun Park Area Site, Volume 1,
 dated September 1996, page 1-5.

       •U.S. Production of Manufactured Gases: Assessment of Past Disposal
 Practices, EPA/600/2-58/012, dated February 1968, pages 136-139.

       'L/.S. Production of Manufactured Gases: Assessment of Past Disposal
 Practices, EPA/600/2-58/012, dated February 1968, pages 65-69.

-------
                                                              Record of Decision
                                                                September 1998
	Page9

shoreline4. It is of significance to note that prior to 1940 the Cooper River shoreline was
located immediately east of Concord Street. The shoreline was later extended to the east
between  1941  and 1942 with the addition of fill  material, an action which created the
present day property currently owned by the NPS. The routing of this discharge pipe would
have placed the point of release in the general area of what is now the northwest corner
of the NPS property.
2.3   Previous Investigations and Containment Measures

Prior to the Rl, several investigations had been preformed on the various portions of the
properties associated with this site. These individual investigations covered a variety of
separate topics  including air quality  in the crawl space and  apartment  interiors of
Ansonborough Homes, analysis of soil and groundwater samples collected from Calhoun
Park and Ansonborough Homes, organic and inorganic analysis of surface water and
sediment samples collected from the Cooper River.

During this time a Site Screening Investigation was completed by SC DHEC on June 2,
1992  on the site to gather the necessary information required  to prepare the Hazard
Ranking System (HRS) package.  Based upon the results of this investigation, the site
receivecha HRS score of 48.9 due primarily to the human food chain threat5. Listing the site
on the  National  Priorities List (NPL) has been suspended based  on  the  present
cooperation by SCE&G in performing the required site activities.

On January 22,  1993, SCE&G entered into an AOC with EPA to perform  a Remedial
Investigation6. To the extent  possible  data from previous investigations were used for
planning the comprehensive sampling approach seen in the Remedial Investigation. The
Rl was also designed to sample additionally properties such as  Ludens, NPS property,
Campsen property, Dockside Condominiums, and the Deyton property which had not been
sampled to date.

SCE&G retained Fluor Daniel GTI of East Pittsburgh, PA to conduct the work required to
complete the RI/FS process.  EPA and SC DHEC provided oversight of work conducted
during the RI/FS. A complete listing of the documents generated during the RI/FS process
can be found in the Index to the Administrative Record for this site. This ROD is intended
to summarize key information from the Administrative Record and provide the rationale for
the selected response action specified in Section 9.0. The reader is referred to the site
Administrative Record for a more detailed account of the information presented in this
             Engineering Drawing, dated February 1, 1936. Revised April 28, 1941.

       5PREscore 1.0 - HRS Documentation Record, Calhoun Park/Ansonborough
 Homes/Coal Gas, 6/10/92.

       Administrative Order on Consent, dated January 22, 1993.

-------
                                                               Record of Decision
                                                                  September 1998
                                                               	Page10
document.

Three additional investigations were also performed concurrent with the Rl and later came
to influence the Rl activities. These included the Killam Report, the PSI Report, and the
Aquarium Containment Plan. During the early  stages of the Rl EPA had planned to
investigate the NPS property under a separate investigation. Meanwhile both the City of
Charleston  and the NPS were performing separate investigations on this property
concurrent with the  Rl. These  reports were  titled  the South Carolina Aquarium Site
Investigation Results7 and the Site Inspection Charleston Harbor Site8 respectively. Data
from these two reports were later included  into the Rl and also  used in support of risk
assessment calculations.

the general area within the City of Charleston where the site is located has been, and
continues to be, subject to aggressive construction efforts. Regulatory concerns over the
planned construction of a City aquarium on  a contaminated portion of the site owned by
the NPS led to the creation  of a containment plan. Ultimately this containment plan was
implemented to minimize potential discharges of contaminants from  the construction
activities associated with  the aquarium.  The containment system  as  implemented
consisted of a sand blanket to minimize resuspension of contaminated sediments, a timber
lagging wall to limit  discharge of particulates to the subtidal area, and a silt curtain to
contain sand  from the sand blanket which  might be disturbed  during  construction.
Following the completion of the subtidal construction activities a demonstrations report was
generated which documented the effectiveness of the containment system.

During the  Rl the City of Charleston began work to  relocate an old storm drain which
traversed a portion of the site. Because a portion of the storm drain traversing the site was
constructed of brick with deteriorating mortar joints it was acting in part as a groundwater
collection system. Storm  water from  off  site properties, and portions of the   site
groundwater which infiltrated the deteriorating pipe, was discharged into the Cooper River.
In order to mitigate this effect, and to prevent the gravel bed required for the replacement
pipe from acting in a similar  manner, sheet piling was installed between the contaminated
shallow aquifer and the location of the new pipe. A groundwater monitoring plan was also
established to monitor the effectiveness of  the sheet piling in preventing the future
infiltration of contaminated groundwater in this area.

A second sediment containment system was later installed on another portion of the NPS
property in support of the construction of  a tour boat dock. This second containment
system, located south of the aquarium containment  system, was  designed to address
contaminated sediments present at the point where the old storm drain discharged into the
Cooper River.
       7South Carolina Aquarium Site Investigation Reports, Killam Associates, dated
 December 1994.

       "Site Inspection Charleston Harbor Site, PSI Inc., dated April 1994.

-------
                                                               Record of Decision
                                                                 September 1998
                                                              	Pagel1
The investigations and containment measures associated with  both the  aquarium
construction and the storm drain were addressed during the early stages of the Rl. During
the completion of the IR an oily sheen was observed on the surface of the Cooper River.
This sheen was traced to seeps along the banks of Cooper River at end of Charlotte
Street. The seeps were observed to be discharging a oily tar substance with the lighter
fractions floating to the surface of the Cooper River while the heaver portions were
observed flowing underwater towards the river channel. Two actions were initiated by
SCE&G. The first consisted of the installation of a floating boom to contain the oily sheen
floating on the surface. The second action consisted of investigating the source of the
material contributing to the seeps. These activities have since been documented in a
report  titled Charlotte Street Investigation Report9. The mitigation of the source area
responsible for these seeps, the contaminated sediments resulting from the seeps, and
sediment contamination documented in the Rl will be addressed in a separate ROD for this
site. On May 13, 1998 SCE&G signed a removal AOC which addresses an interim action
on these seeps. This interim action is currently underway to mitigate the discharge from
these seeps.
3.0    HIGHLIGHTS OF COMMUNITY PARTICIPATION

In May 1995, EPA issued a fact sheet to local citizens and public officials announcing the
initiation of RI/FS activities at the site. Concurrent with the release of this fact sheet, the
Final RI/FS Work Plan documents were submitted for public review to the information
repositories located at EPA's office in Atlanta, GA and the Charleston County Main Library
in Charleston,  SC.   On May 1995, EPA held an  Rl Kick-Off Public Meeting at the
Charleston  Public Works  Building in Charleston, SC to provide a description of the
Superfund process, the work to be performed, and to  answer any questions regarding the
site.

In January 1998, EPA released a public fact sheet to provide the public with a summary
of the findings of the Rl and the human health  Baseline Risk Assessment. A public
information  session was held on January 20, 1998, to discuss the information presented
in this fact sheet and to answer site specific questions from the public. During March 1998,
EPA released the proposed plan public fact sheet which presented the proposed remedial
action and  also recapped the  Rl and  Baseline Risk Assessment finding. The  Final Rl
Report,  Final Human Health Baseline Risk Assessment (BRA),  and other site related
documents  were assembled in an Administrative Record  (AR)  and submitted to the
information repositories for public review concurrent with the release of the fact sheet.

A notice to  area citizens regarding the proposed plan public meeting, the location of the
local information repository, and the initiation of  a 60-day public comment period was
published in Charleston's daily newspaper, The Post and Courier, on March 1998. Due
to public interest and explicit requests expressed  during the previous public information
       'Charlotte Street Investigation Report, dated December 1997.

-------
                                                              Record of Decision
                                                                September 1998
                                                                       Page12
session, the public comment period was opened for 60 days from March 16, 1998, to May
15,  1998.  The proposed  plan public meeting was  held on  March 16,  1998, at the
Charleston Public Works Building and was attended by approximately 50 people. At the
request of local area residents an additional public information session was held on April
28, 1998, to discuss risk assessment issues and groundwater conditions.

Public comments  were received during the 60 day comment period.  Each  specific
comment,  in addition to EPA's  specific response to these comments, is provided  as an
attachment to this ROD titled as "Responsiveness Summary". A transcript of the March 16,
1998, public meeting and a copy of all comments received during the 60-day public
comment period have been provided as an attachment to this ROD.
4.0   ADDITIONAL EARLY RESPONSE ACTIONS

Previous early response actions, in the form of sediment containment measures, have
been taken at this site  and are described in section 2.3. Additional actions are also
planned for contaminated soils and seeps at Charlotte Street and are currently being
addressed under a Removal AOC. The rationale for this additional early response is two
fold. The City of Charleston will soon begin construction of the parking garage which when
built would cover a large portion of contaminated soils associated with this -site. In order
to remove the soils while  still accessible, and to minimize exposure  risk to the on-site
construction workers, the contaminated soils will be removed prior to beginning the garage
construction. Additionally the seeps located along the end of Charlotte Street have been
discharging coal tar waste into Cooper River since November 1997. As such, a response
action was deemed necessary.

According to  the Removal AOC, which became  effective May 22,1998, the work to be
performed will be as follows:

•     Delineation, excavation, and disposal of contaminated soils as presented in the
      Calhoun Park Feasibility Study dated November 1997, to a depth of 3 feet below
      land surface and having an estimated volume of approximately 6,080 cubic yards;

•     Further investigation and prevention or mitigation of the discharge of coal tar into
      the Cooper River from seeps along Charlotte Street.

5.0   SUMMARY OF SITE CHARACTERISTICS

This section provides a brief and concise overview of the site characteristics as assessed
during the site Rl. The majority of the field activities performed by SCE&G as presented
in the R I were performed between November 1993 and January 1994. As previously
mentioned there were two additional investigations performed concurrent with the Rl and
the information eventually assimilated into the Rl report. These investigations consisted
of the Killam Report and the PSI Report. Collectively these field investigations generated

-------
                                                               Record of Decision
                                                                 September 1998
	Page13

a voluminous data base.  The results of these field programs and appropriate conclusions
have been presented in the following technical reports that are incorporated into the site
Administrative Record:

•     Draft Final, Remedial Investigation Report, Calhoun Park Area Site, Volumes I &
      2, Fluor Daniel GTI (September 1996)
      Feasibility Study,  Calhoun Park Area Site, Fluor Daniel GTI (November 1997)
•     South Carolina Aquarium Site Investigation, Killam Assoc.(December 1994)
•     Site Inspection Charleston Harbor Site, PSI Inc. (April 1994)

In the interest of brevity,  the information presented in the above reports is not re-iterated
in this decision document.  Rather, the conclusions of the Rl are presented in a more
qualitative summary format to provide the reader with an overview. Specific human health
risks posed by the site constituents are summarized in Section 6.1. Cleanup goals for all
media addressed by this response action are delineated in Section 7.1. The reader should
refer to  the site Administrative Record for a more detailed account of this subject matter.
 5.1    Physical Characteristics

 This section provides a summary of information regarding the physical characteristics of
 the site including demography, meteorology, topography, surface water hydrology, and
 geology/hydrogeology.
 5.1.1  Demography

 The site is located in the downtown area of Charleston, South Carolina. Current land use
 for the site, and adjacent properties consists of a mixture of commercial and light industrial
 operations interspersed with pockets of residential areas. According to a document titled
 Calhoun Street Corridor, prepared in 1989 by the City of Charleston planning commission,
 plans are underway to construct a parking garage on the current Calhoun Park property.
 Additional commercial development is planned  for portions of the NPS property, the
 Campsen property, and portions of the property previously occupied by the Ansonborough
 Homes.
 5.1.2  Meteorology

 The climate in Charleston, SC is temperate and modified considerably by the proximity to
 the Atlantic Ocean.  The marine influence is  noticeable during winter when the low
 temperatures are sometimes 10-15°F higher on the peninsula than areas ten miles inland.
 Likewise, summer high temperatures are generally a few degrees lower than inland areas.
 The average daily maximum temperature ranges from 90.2 °F in July to 57.8  °F in
 January. The average daily minimum temperature ranges from 72.7 °F in July to 37.7 °F

-------
                                                                Record of Decision
                                                                  September 1998
	Page14

in January.  Prevailing winds are northerly in the fall and winter, and southerly in the
spring and summer. The average precipitation ranges from 8 inches or more in July to 3
inches or less in November. Late summer and early fall is the period of maximum threat
to the South Carolina coast from hurricanes.
5.1.4  Surface Water Hydrology

Much of Charleston County is tidal estuary, including the area in which the site is located.
The Charleston Harbor and the Cooper River are tidally influenced and have a semidiurnal
tide which averages 5.2 feet. The Cooper River borders the site to the east. The site lies
above normal high tide levels with the exception of localized tidal flooding of the storm
drain grates in the Ansonborough Homes area to the south and portions of Charlotte Street
to the north. The 50-year storm surge level for Charleston County is 11 feet above Mean
Sea Level (MSL). A storm surge to this elevation would cause complete  flooding of the
site.

Surface water drainage at this site occurs as either overland flow or through a series of
storm water collection piping. While the old underground brick archway mentioned in
section 2.3 no longer exists, it did transect a portion of the site  for a number of years and
influenced both surface water and groundwater hydrology. The old brick archway ran due
east along Calhoun Street collecting the majority of storm water from the site. This water
was  eventually discharged into the Cooper River.  Historically the old  brick archway
terminated immediately east of the intersection of Calhoun Street and Concord Street as
the fill material comprising the NPS was not in place until 1941. Following the addition of
the fill the brick archway was then extended so that it could continue to discharge water
into the Cooper River.
 5.1.5  Geology/Hydrogeology

 The site is located in the discharge portion of the Atlantic Coastal Plain physiographic
 province. The Cooper Marl clay formation, a regional confining unit approximately 260 feet
 thick, is encountered at depths on-site ranging from 68 to 85 feet below land surface
 (BLS).  The Rl was limited to characterizing the shallow aquifer above the Cooper Marl
 confining unit.

 Three water-bearing units (shallow,  intermediate,  and deep  sands) and  two  lower
 permeability units (shallow and intermediate clays) were identified in the shallow aquifer
 above the Cooper Marl.  A representative stratigraphic model of the site is presented
 graphically  in Figure 5-1.  From the land surface to the top of the Cooper Group, the
 stratigraphic units beneath the site are 1 )artificial fill; 2)upper clay;  3)intermediate sands;
 4)intermediate clay; 5)lower sands; and 6)the Cooper Group. The presence-and thickness
 of these layers vary across the site.

-------
                                                                Record of Decision
                                                                  September 1998
                                   	      Page 15

As seen in the stratigraphic cross-sections, the site is covered with a layer of fill which
contains sand, silt, shells, gravel, including wood scraps and building rubble. The fill varies
in thickness between 4 to 15 feet bis and has an average hydraulic conductivity of 6.1  x
10'3 cm/sec. . The water table stands within this unit at approximately 2 to 4 feet bis. The
"A"-level wells and piezometers are located within this unit. The fill unit is underlain by an
upper clay unit which begins between 5 to 20 feet bis and extends to between 30 to 40 feet
bis. In general the upper clay unit serves as a unit of lower permeability with an average
hydraulic conductivity of 3.4 x 10'7 cm/sec, however, the presence of course grain particles
and hydraulic data suggest that appreciable leakage may occur though this  upper clay in
some areas. As an additional note the upper clay layer within the general vicinity of the
electrical substation was likely breached during the installation and/or removal of the gas
holder.

Beneath this uppermost  clay layer exists an  intermediate sand/silt layer  which is
encountered between 30 to 40 feet and extends to 50 to 65 feet bis. This unit is a water
bearing zone with an average hydraulic conductivity of 5.6 x 10"3 cm/sec. The intermediate
sand/silt layer is underlain by an intermediate clay layer which is encountered between 50
to 65 feet  extending  to 60 to 75 feet bis. This clay layer serves as a unit of lower
permeability where present, however, it is not present as a distinct clay zone across the
entire site.  Where present the average hydraulic conductivity is  2.1 x 10"8 cm/sec.

A lower sand/silt unit is found beneath the intermediate clay layer, encountered between
55 to 75 feet bis and extending to 60 to 85 feet bis before encountering the Ashley
Formation. The average hydraulic conductivity  of the lower sand/silt unit is 5.6 x 10'3
cm/sec. The Ashley Formation is located beneath the lower sand/silt unit and is located
between 68 to 85 feet  bis. This formation consists of a dense calcareous sand and has an
average hydraulic conductivity of 1.7 x 10'7 cm/sec. The intermediate sand and lower sand
unit  may possibly be  used locally within Charleston County as a water supply, but no
known shallow groundwater wells are in use within a four mile radius of the site. Drinking
water to this area is supplied by the City of Charleston.
 5.2    Nature and Extent of Impact

 The media investigated as  part of the Rl included soils,  groundwater, and  surface
 water/sediments. The sampling locations are presented in Figures 2-2, 2-3, & 2-4. The
 following  sections  briefly  discuss  each media  sampled  and  the  corresponding
 contamination present at the sampling locations.

-------
                                                                                   CONCORD
                                                                                   STREET
i-eio
                                                           JTyrS GRAVEL
                                                              SAND AND
                                                              CINDER
                            FILL

                            CINDER. COKE
                            GRAVEL SLAG
                                                                           CLAYEY SANO
                                                                           AND WOOD
       CLAY (SOFT)
      CLAY (DENSE)
     CLAYEY SAND
                                                                                   INTERMEDIATE
                                                                                      SAND
     CLAYEY SILT
     CLAYEY. SILT
     TO SILTY CLAY
                                                     INTERMEDIATE
                                                         CLAY
     SHELLS AND SAND
     SILTY CLAY
     SANDY aAY
     SILT  WITH  THIN
     SAND  LAYERS
    CLAY WITH  THIN
    SAND LAYERS
                       ASHLEY FORMATION  (COOPER GROUP)
                       DENSE SANDY TO CLAYEY SILT
         200
                                                  500
                                                          700
                                                   800
                                         1000
            BORING
                                              VIEW BASELINE'- FEET
                                      LEGEND
               V
BOTTOM OF
SAMPLED INTERVAL
                        GRADATIONAL
                          CONTACT
                         INFERRED
                         CONTACT
[7.3x101  - K VALUE MEASURED
1	'   BY SOIL PHYSICAL
          TESTING (FT/MIN)
                              - K VALUE MEASURED
                                BY SLUG TESTING
                                (FT/MIN)
NOTE:
 SEE FIGURE 2-7 FOR LOCATION
 OF CROSS-SECTION LINES. KEY TO
 LITHOLOGY SYMBOLS MAY BE FOUND
 IN APPENDIX  A.
                                                    GROUNDMTER
                                                    TECHNOLOGY.
                                                                                                            CO
                                                                                                             c
                                                                                                             (3
                                                                                                             Ul
                                                                                                             CO

                                                                                                             Q>
                                                                                        o
                                                                                        T»
                                                                                        2
                                                                                        o'
                                                                                        O
                                                                                        3
                                                                                        (/>
                                                                                        CO
                                                                                        CO
                                                                                        (D
                                                                                        O.
                                                                                                                                          73
                                                                                                                                          n
  "S 3.
   I 2,
•08*0
L>  -i ft
3   . f*
*  vO 5'
   *o o
   OO 3

-------
 C  00
 o  o\
'5  Ov

'§  u

Q.8
U-,  C
 o  5

•S  &
 o  u
 8 c^
 V
c£
             C
             o


             8
             O)
             C

            "5.

             E-
             ra
            CO
             ra

            T3
             c

             o

            6
            (N
            0)

            3
            O)

-------
                                                      Record of Decision
                                                         September 1998
                                                           	Page 18
Figure 5-3 (Sediment/Surface Water Sampling Locations)
                                           18/SW-18/18MS-MSD

                                             D-2J/SW-21
                                                              Lights,?
                                                       SD-15/SW-15/
                                                        SD-12/SW-12
                                                        SD-13/SW-13
                                                        SD-tO/SW-10
                                                      (-H/SW-U /
                                                      •SD-16/SW-J6
                                                               /
                                                     Habitat Area' SI
                                                     Habitat Area #3
                                                               I
                                                       rSD-20/SW-20
                                                                   .
                                                         -SD-19/SVM9
                                                                   '
                                                      Piles
                                                   __, Bay
                                                   'layground
                                                                \O
                                                                 i
                                                                 is

-------
                                                              Record of Decision
                                                                 September 1998
                                                              	Page19
5.2.1  Surface/Subsurface Soils

Impact of the site to surface soils (defined as 0 to six inches BLS) and subsurface soils
(soils 6 inches  or greater BLS) were characterized by the collection of soil borings.
Generally, this effort included the collection of samples from areas likely impacted by past
operations.  These potential source areas of interest included the gas holder area, the
relief holder area, and the rosin wood treating operation (Fernoline Chemical). Samples
were  also collected throughout other areas of the site. The sampling locations are
illustrated in Figure 5-2.

The majority of contaminants impacting the soils at this site consist primarily of volatile and
semi-volatile organic'compounds. The majority of the semi-volatile organic compounds
consist  of  PAHs,   primarily  Acenaphthene,  Acenaphthylene,  Anthracene,
Benzo(G,H,l)perylene, Fluoranthene, Fluorene, Naphthalene, Phenanthrene,  Pyrene,
Benzo(A)anthracene, Benzo(A)pyrene,  Benzo(B)fluoranthene,  Benzo(K)fluoranthene,
Chrysene, Dibenz(A,H)anthracene, and  lndeno(1,2,3-CD)pyrene. The group of volatile
organic  compounds present  are  primarily  the  BTEX  .group (benzene, toluene,
ethylbenzene, and xylene).

The areas most impacted by contaminants include the gas holder, the relief holder, and
soils surrounding the waste disposal pipe. Another concentrated area of contamination
was identified at the northwest corner of Ludens property. Contaminant concentration
ranges are  presented in Table 5-1. Both the PAH and BTEX groups are commonly
associated with contamination present at manufactured gas plants.
5.2.2 Groundwater

Shallow Sand Aquifer
Evaluation of the extent of groundwater contamination was focused primarily on the fill
aquifer as evidenced by the 32 shallow "A" wells installed across the site. The primary
contaminants present in the fill aquifer consist of the BTEX group, the PAH group, and
several inorganic compounds. Organic contaminants in the fill aquifer exceeding the MCLs
include  Benzene,  2,4-Dimethylphenol,    Benzo(a)pyrene,  Benzo(A)anthracene,
Benzo(B)fluoranthene, Benzo(K)fluoranthene, Chrysene, lndeno(1,2,3-CD)pyrene, Ethyl
benzene, Carbazole,  Chrysene, Naphthalene,  and Toluene. Inorganic contaminants
exceeding the  MCLs  include Arsenic Cyanide,  Beryllium, Lead,  Mercury, Chromium,
Nickel, and Copper. Isoconcentration maps for selected groundwater contaminant plumes
are presented in Figures 5-4, 5-5, & 5-6. These maps provide a general indicator as to the
extent of groundwater contamination associated with this site which exceed MCLs. As
evidenced from these maps, portions of the  contaminated groundwater  plume are
discharging into the Cooper River. Contaminant concentration ranges are presented in
Table 5-2.

-------
                                                              Record of Decision
                                                                 September 1998
                                                             	Page20
                                 Table 5-1
                       Chemicals Detected in greater
                          than 5% of Soil Samples
Chemical
vni x-nt = CRGANICS
Acs'.or.c
Carbon DisulHdc
2-Butanonc
Benzene
Toluene
Ethylbenzcnc
Xytenes
nASF NF.UTRALORGANICS
Dibenzofuran
Di-n-hutyiphihalaic
Carb azoic
Dis(2-cihythexyi)phthalaic
CAlis
2-.Methyt naphthalene
Acenaphthcne
Accnaphihylcnc
Anthracene
Benzo(£ji,i)perylene
Fluorenthcnc
Fluorcnc
• Naphthalene
Phenanthrenc
Pyrcne
Bcnzo(a)anihncenc
Benzo(a)pyrcne
Ben7jo(b)(luoranihene
Benzo(|;)nuoranihene
Chrysenc
Dibenz(aji)anthracene
lndeno(1.13-cd)pyrcnc
INORGANICS
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Cyanide
Lead
Manganese
* Mcrcurv .
] . Nidcel'
| Selenium
j Thallium
j Vanadium
j Zinc
Frequency
of Detection
0;

21-53
5,53
11'53
13/53
10/53
13/53
9/53

20/53
3/53
15/53
8/53
29/53
S9/53
31'53
^1*53
39/53
51/53
25/53
34/53
48/53
48/53
49/53
48/53
47/53
44/53
49/53
29/53
45/53

7/53
47/53
35/53
5/53
ft/53
53/53
50/53
31/53
53/53
53/53
29/53
20/53
14,53
3V53
37/53
52/53
Rnnje of
Detection •
(m-'ka)

0.02 - 2
0.003-0.04
0.008-0.15
0.02-43
0.004 - 100
0.017- no
0.013 - 150

0.04-9
0.05-2
0.023 - 3
0.035 - 6
O.W1-9
0.053 - 26
6.029 - 69
0.024 - 37
0.034 - 17
0.030-52
0.053-59
0.051 - 160
0.046 - 140
0.042 - 69
0.037 - 38
0.049 - 28
0.034 - 30
0.020 - 16
0.050 - 35
0.021 - 6
0.025 - 17

3.1-36
3-3-250
47.6 • 1060
1.2-3.4
1.6-9.7
3-3 - 150
3.7-496
0.67-601
10.2 - 3530
14.1 - 1390
0.12- 14
9.6 - 1 13
1.7-153
1.2-9.2
112-75
15-2 - 1600
Avtrnje
Concentration (2)
(mj/ks)

0.4S
0.02
0.05
45
15
23
24

13
0.60
0.05
0.99
75
33
4.4
3.0
13
6.3
6.4
13.6
10
8.2 '
4.2
3.7
43
12
V
1'°
i?

15
24
204
10
3.4
18
94
45
397
154
1.4
26
4.8
55
23
270
Mc:in Rackground
Concentration (?)
(m;rtt«)
"*
0.16
0.03
ND
ND
ND
ND
ND

ND
ND
0.09
0.08
ND
ND
ND
0.05
031
0.97
ND
ND
030
058
033
033
0.78
0.41
037
0.11
034

ND
13
238
ND
ND
21
58
ND
824
94
13
ND
ND
ND
37.
506
Region III
Screcnin* Valuei (3)

-------
                                                                                        Record of Decision
                                                                                           September 1998
                                                                                       	Page21
                                                    Table 5-2
                                       Chemicals Detected in greater
                                      than 5% of Groundwater Samples

VOI ATILE PRO ANICS
Acetone
Benzene
Toluene
Eihylbenzene
Xylcnes
BASE-NEUTRALQRGAN1CS
Phenol
2-Methylphenol
4-Methylphenol
2,4-Dimethylphenol
Dibenzoturan
Carbazole
B is(2-Et hylhcxyl)phl ha late
PAHs
2-Methylnaphthalene
Acenaphthcne
Acenaphthylene
Anthracene
Benzo(g,h,i)perylene
Fluoranihene
Fluorene
Naphthalene
Phenanthrene
Pyrenc
Qcnzo(a)anthracene
Benzo(a)pyrene
Benzo(b)fluoranthene
Cnryscnc
rndeno(1.2,3-cd)pyrene
INORGANICS
Arsenic
Barium
Beryllium
Chromium
Copper
Cyanide
Lead
Manganese
Mercury
Nickel
Vanadium
Zinc
Fnqatncj'
0)

6/32
14/32
i2m
14/32
13/32

3/32
3/32
2/32
2/32
16/32
13/32
3/32

17/32
21/32
11/32
19/32
7/32
21/32
20/32
21/32
23/32
21/32
13/32
8/32
13/32
11/32
7/32

21/32
21/32
2/32
21/32
10/32
14/32
17/32
32/32
27/32
7/32
8/32
25/32
Ruigt «f
Dtftedon

6-17
6-5200
2-1800
2-1200
4-1800

8-150
1-400
240 - 620
180. -890
3-140
0.8 • 150
1-22

I -1100
1-370
0.6 - 140
0.5 - 210
0.8-10
1-410
0.6-290
0.7 • 5500
0.8 - 970
1-480
0.8 - 180
1-38
1-130
2-160
0.9-12

4-88
203-1470
6-13
28-130
8-5080
11-4480
3-1920
178-3050
0.2-15
41 - 304
56-174
26-2610
Cone*nir»dMt (I)
("0")

11
571
214
200
280

58
197
430
535
40
49
8.0

157
66
23-
34
Z7
52
48
782
108
51
29
9.1
23
31
/ 3.1

23
487
9.3
35
567
832
322
959
3.5
110
91
678
M«if> B»cVjr»unJ
CmcrandMi (J)
(•CD

ND
ND
ND
ND
ND

ND
ND
ND
ND
ND
ND
ND

ND
ND
ND
ND
ND
ND
ND
ND
ZO
ND
ND
ND
ND
ND
ND

25
47
ND
ND
7.3
ND
52
366
0.5
ND
10
81
RtflMI III
Semiring V.ltui (J)
(•Cfl)

370
0.36
75
130
1200

2200
180
18
73
NA
3.4
4.8

NA
220
•NA
1100
NA
150
150
150
NA
110
0.092
0.0092
0.092
9.2
0.092

0.04
260
0.016
18
140
73
NA
18
1
73
26
1100
MCL
Vilwi (4)
(•*»

NA
5
1000
700
10000

NA
NA
NA
NA
NA •
NA
NA

NA
NA
NA
NA
NA
NA
NA
• NA
NA
NA.
NA
0.2
NA
NA
NA

50
2000
4.0
100
1300*
200
15
50"
ZO.
100
NA
5000V
NA - N« Available
ND - Not Detected
• - Maximum Contaminant Level Coal
fl) Sampling date was January 1994.
m Average of detects only used when calculating average and background concentrations.
(3) These values were obtained from EPA Region HI Risk based concentrations technical guidance for selecting chemicals o( potential concern
                I represent ta   	
(4) Maximum Contaminant Level (MCL)

-------
                                     Record of Decision
                                        September 1998
                                     	   Page22
         Figure 5-4
Benzene Isoconcentration Map
 Shallow Groundwater Aquifer

-------
                                      Record of Decision
                                        September 1998
                                     	Page23
          Figure 5-5
Total PAH Isoconcentration Map
  Shallow Groundwater Aquifer

-------
                                       Record of Decision
                                         September 1998
                                                Page24
           Figure 5-6
Naphthalene Isoconcentration Map
  Shallow Groundwater Aquifer

-------
                                                              Record of Decision
                                                                 September 1998
                                                              	Page25
Intermediate and Deep Sand Aquifers
Groundwater samples were collected from eleven intermediate and deep wells, designated
"B" and "D" respectively. The locations of these wells can be seen on the soil sampling
map designated as Figure 5-2. Constituents present in these wells include both BTEXs
and PAHs, some of which were present in concentrations in excess of MCLs. No plume
maps were presented for either of these aquifers due to the relatively small number of data
points taken. Because the extent of contamination within these aquifers were not well
defined during the Remedial Investigation,  additional evaluation will be performed as part
of the remedial design to determine if additional cleanup actions are warranted.

Analytical results from all monitoring wells were compared to Maximum Contaminant
Levels (MCLs) which have been established to be protective of human health based on
the use of site groundwater as a drinking water source. This comparison is conservative
given that the water-bearing units do not have sufficient capacity and that the groundwater
near the Cooper River is either saline or brackish. MCL exceedances were noted in either
the shallow and/or intermediate water-bearing units for the following constituents: Arsenic,
Cyanide, Benzene, 2,4-Dimethylphenol, Benzo(a)pyrene, Ethylbenzene, Beryllium, Lead,
Mercury,  Chrysene,  Naphthalene,  Chromium,  Nickel,  and  Copper. Contaminant
concentration ranges are presented in Table 5-3.

An  artesTan well, designated as  sample MG-01M, was also sampled as  part of this
investigation. Low levels of PAHs were detected within this well  but were below their
corresponding MCLs.  Dioxin sampling was also performed on the following three wells:
BM-01A (background), AM-04A (Ansonborough Homes), and CPMW-3 (Calhoun  Park).
While eight of the  PCDD/PCDF  congeners were detected  in the two on-site  wells,
examination of the 2,3,7,8-TCDD Toxicity Equivalent Concentrations revealed that the
concentrations present (<2 pg/l) were below the MCL of 30 pg/l.
 5.2.3  NAPLs

 The following discussion is limited to the NAPL investigation as presented in the RI/FS.
 Shortly following the completion of the RI/FS, coal tar was observed discharging from
 seeps near the north east portion of the site (see section 2.3 Containment Measures).
 Subsequent investigative work has revealed the presence of  additional NAPL source
 areas, other than the ones  discussed in the RI/FS, which are attributable to the MGP
 operations. As of the  writing of this  ROD additional investigative  work is currently
 underway to determine the extent of these source areas and evaluate appropriate remedial
 actions.

 NAPLs comprise a broad class of compounds which are immiscible fluids with densities
 greater than water (DNAPLs), including PAHs, or lighter than water (LNAPLs).

-------
                                                                                         Record of Decision
                                                                                            September 1998
                                                                                        	Page26
                                                  Table 5-2
                                  Contaminant Concentration Ranges
                                   Intermediate Groundwater Samples
                                                                   Calhoun Park Area Site
                                                                      Risk Assessment
Chemical
VQLATILECRQAhllCS
Met ltylene Chloride
Acetone
Ctiloroform
llenzene
Toluene
Ethylbenzene
Xytenes
UASP, NmiTRALOROANICS
Phenol
2-Mefhylphenol
4-Methylphenol
2,4-DImethylphenol
Dlmethylphthalaie
Dlbenzofuran
DIelhylphthaUte
Carbazole
2>Methytnaphihalene
Aeenaphthene
Acenaphthylenc
Anthracene
,' Fluoranthene
1 1 Fluorene
^Naphthalene
Phenahlhrene
Pyrerte
Denzo(*)a nthneene
Oenzo(a)pyrcne
Denzo(b)fluoranthene
Chrysene •
INORGANICS
Chrofli Itfm
Cyanide
Manganese
Nickel
Frequency
of Detection
0)

l/ll
l/ll
1/11
.5/11
2/11
3/11
4/11

5/11
1/11
1/11
l/ll
1/11
2/11
1/11
2/11
2/11
3/11
2/11
2/11
2/11
2/11
6/11
3/11
2/11
1/11
1/11
1/11
l/ll

8/11
7/11
7/11
2/11
Range of
Detection
(ut/l)
•
17
11000
37
3-15000
160-490
250-3600
6-2500

0.9-91
12
37
130
17
2-28
34
3-81
210-370
0.9 - 42
26-62
3-9
2-12
16-54
3 - 3400
0.8 - 44
2-9
2
1
1
2

13-68
11 - 173
32-334
43-61
Average
Concentration (2)

17
11000
37
4981
325
1540
804

45
12
37
130
17-
JJ/5-
34 — -..
42
290
16
44
6.0
7.0
35
699
• 21
5.5
ZO
1.0
1-0 .
ZO

30
84
143
52
Mcin Dickground'
Concentration (2)
(ut/l>

ND
ND
ND
ND
ND
ND
ND

ND
ND • '
ND
ND
ND
ND
. ND
ND-
ND
ND
ND
ND
ND
ND
ND
2.0
ND
ND
ND
ND
ND

ND
ND
' 366
ND
Region HI.
Screening Valua (3)

4.1
370
0.15.
0.36
"75
130
1200

2200
180
18
73
37000
NA
2900
3.4
NA
220
NA
1100
150
150
150
NA
110
0.092
0.0092
0.092
9.2 .

18
73 '•
18
73
MCL
Values (4)

5
NA
NA
5
1000
700
10000

NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
0.20
NA .
NA

100
200
50«
100
NA-Not'Available'
NO. Not Deeded
(I) Sampling date ww January 1994.
(2) Avenge of detects only used when calculating average and background concentrations.
(3) llheie values were obtained from EPA Region III Risk based concentrations technical guidance for selecting chemicals of potential concern.
   All Values are based on a carcinogenic risk of 10-06 and noncarcinogenic hazard Index of 0.1. EPA Region III screening values arc based on a haznri
    of 1.0 for noncarclnogcnlc compounds. However, In accordance with Region IV guidance, the concentrations of noncarclnoECnte compounds     I
    shown In the Region III tables have been adjusted by a factor of 0.1 to reflect a concentration that would produce a hazard quotient of 0.1.
     The values listed represent lanwaicr criteria.
(4) Maximum Contaminant Level (MCL)

-------
                                                              Record of Decision
                                                                 September 1998
                                                                       Page27
Therefore, EPA adhered to the groundwater/NAPL site characterization strategy presented
in  EPA OSWER  Directive  9234.2-25,  Guidance  for  Evaluating  the  Technical
Impracticability of  Groundwater Restoration (EPA 1993).   This  guidance document
advocates a strategy which delineates three areas: 1) the NAPL entry location; 2) the
NAPL zone or source area; and 3) the aqueous contaminant plume. The entry locations
are those areas where NAPL may have entered the environment and, therefore, is likely
present in the subsurface. The NAPL zone or source area is defined by that portion of the
subsurface containing free-phase or residual NAPL.   The aqueous contaminant plume
contains dissolved phase constituents down gradient from source areas. The Rl field
program focused on likely entry zones by utilizing information gathered on historical
operating procedures for the MGP. NAPL source areas and dissolved phase constituent
plumes were delineated through the installation of monitoring wells.

The general locations where measurable thicknesses  of DNAPLs were observed during
the Rl  include wells CPMW-3, MM-01A, MM-02B, and  MZ-06A. Wells MM-01A and MM-
02B contained NAPLs layer greater than 0.5 feet. Additionally wells CM-05A, MZ-05A, and
MW-12, were observed as having visual traces of NAPLs. Consequently the occurrence
of NAPL as reported in the Rl  can be grouped  around the MGP;  more specifically the
former gas holder,  the former rail spur, and the former oil tanks. These areas constitute
both the NAPL entry location and the NAPL zone or source area. While NAPL was present
primarily~within the shallow aquifer, it was also observed in well MM-02B which is located
within the intermediate  sand aquifer in the area adjacent to the gas holder.
 5.2.4  Sediments

 The following information is provided as an overview of the general sediment conditions
 at the close of the RI/FS. With the recent release of coal tar via seeps into the Cooper
 River, a new source of sediment contamination  has occurred.  Interim  measures are
 presently underway to stop this discharge. The extent of contamination associated with this
 release is under investigation and will ultimately impact any future plans for remediating
 the sediments. A second ROD will be issued to address the sediments once the sediment
 investigation is complete.

 The nature and extent of impact to the benthic community within the Cooper River was
 determined by the analysis of seven sediment samples. Additional samples were also
 collected at the  Calhoun Street drain  discharge point or  outfall, the Calhoun Street
 manhole, the  Hassel  Street  outfall,  and the Columbus Street  outfall.  The  sediment
 sampling locations are identified in Figure 5-3.

 The analytical  results were then compared to the  relevant ecological screening criteria;
 NOAA's Effects Range-Low (ERL). Effects Range-Median  (ERM) and EPA's Sediment
 Quality Criteria (for addressing equilibrium partitioning). In summary the data indicates that
 the primary constituents present in site sediments which exceeds ERLs, ERMs, and EPA's
 Sediment  Quality Criteria would be  the PAHs.  Inorganic  constituents  including lead,

-------
                                                              Record of Decision
                                                                 September 1998
                                                              	Page28
arsenic, cadmium, and mercury were present in sediment samples in excess of ERLs. With
the exception of arsenic which appears in the soils in concentrated areas surrounding the
MGP, the remaining inorganic constituents do not appear to be associated with the MGP
operations.

Sediment samples which exceeded the screening levels are clustered around two primary
areas: the Calhoun Street drain outfall (SD-10) and the area adjacent to the NFS property.
The concentration of contaminated sediments adjacent to the NPS property can be readily
associated with the previous MGP operation of a discharge pipe as discussed previously
in section 2.1 Previous Site Operations.

The contaminated sediments located at the Calhoun Street drain outfall suggest that the
drain has acted as a conduit carrying contaminated water and/or sediment into the Cooper
River. A comparison of sediment concentrations from stations upgradient (sample SD-11
at corner of Elizabeth St. and Calhoun St.) and downgradient (sample SD-10 at drainage
outfall in Cooper River) of the site suggest that the source of contamination entered the
drain somewhere  between these two sampling points.  While the contamination  is
consistent with the type of contamination associated with MGP operations (i.e. PAHs) an
evaluation of the data did not reveal any particular source or sources responsible for this
contamination because the construction of the drain pipe was such that it received water
not only from the street storm grates but also from adjacent groundwater which infiltrated
the pipe due to decaying mortar joints.
Ecological Assessment

An ecological assessment was performed on a portion of the Cooper River adjacent to the
site. This assessment consisted of an investigation on benthic macroinvertebrates to
evaluate their  individual abundance as  well as their number and  types against  a
background location. A summation of the findings at the close of the RI/FS indicated that
there were  no  significant differences between the on site stations versus the off site
stations. This conclusion was based on conditions at the close of the RI/FS and prior to
the recent release of coal  tar via seeps  into the Cooper  River. This  recent release
represents an additional contaminant source potentially threatening ecological receptors.
The effect of this source area will be evaluated during the sediment investigation and
discussed under the  same ROD as the sediments.
 5.2.5  Surface Water

 The following  information  is provided as an overview of the general surface water
 conditions at the close of the RI/FS. With the recent release of coal tar via seeps into the
 Cooper River, a new source of surface water contamination has occurred and additional
 investigative work is underway.  Following completion of this ongoing  investigation a
 second ROD will be  issued to address surface water/sediment contamination on human

-------
                                                              Record of Decision
                                                                 September 1998
                                                              	Page29
health and the environment.

Surface water samples were collected from flood water surrounding Ansonborough Homes,
Cooper River surface waters, and three storm water outfalls. BTEX, SVOCs, and PAHs
were detected at the point where the Calhoun Street drain outfall enters the Cooper River
(SW-10). Additionally dioxins were detected in surface water samples collected from the
Cooper River and the Calhoun Street drain. These results were compared to U.S. EPA
acute  and  chronic Ambient Water Quality Criteria (AWQC).  While surface  water
contamination was present in surface waters surrounding the site, the concentrations of
these contaminants did not exceed the AWQC standards. These same contaminants were
also present in low levels throughout the study area, including some of the background
locations. While there was no significant threat from surface water contamination to
humans from this site at the close of Rl, the recent release of contamination via seeps will
require additional investigation as mentioned in the preceding paragraph.
6.0   SUMMARY OF SITE RISKS

The human health baseline risk assessment process provides the basis for taking action
and identifies contaminants and the exposure pathways that need to be addressed by the
remedial action. It estimates what risks the site poses if no action were taken.  This
section of the ROD summarizes the results of the human health baseline risk assessment
for this site. Environmental risks are presently unresolved due to the on-going discharge
of coal tar from seeps as discussed in section 4. The environmental risks resulting from
these seeps, in addition to the overall environmental risk associated with this Site, will be
evaluated under operable unit two and addressed in a second ROD for this site.

The evaluation of human health risk associated with this site is discussed within three
documents present in the Administrative Record: the Baseline Risk Assessment by Black
& Veatch, the Revision to Risk Assessment written by EPA, and the Assessment of Risk
for NPS which was also written by EPA. Typically the site risk is presented under one
document and titled as the Baseline Risk Assessment. A discussion as to why these three
documents are pertinent in assessing site risk is offered in the following paragraphs.

Initially the baseline risk assessment document was submitted to EPA in a draft format on
August 1994 with a revision submitted on October 1994 which was accepted as a final
version. EPA then discovered several errors which remained in this document. To address
these errors EPA generated the Revision to Risk Assessment dated July 1996. Meanwhile
the Killam Report and the  PS I Report were generated. Following  a review of these two
data sets, EPA initially decided to evaluate the data separate from the Rl data, and present
the results in the document  titled  "Assessment of Risk at the National Park Service
Property, December 11. 1995." This decision was based on two considerations: the highly
skewed sample locations, and that these soils would be removed during the aquarium
construction. The same exposed populations were examined,  i.e., current trespassers,
future construction workers, and future residents, for contaminated soils. In general the
contaminant  levels,  specifically  inorganics,  PAHs and  PCBs were found in higher

-------
                                                               Record of Decision
                                                                  September 1998
                                                              	Page30
concentrations in the ESI/Killam reports than in the Rl.

During the Feasibility Study EPA expanded this risk assessment strategy and required that
all future calculations for Preliminary Remediation  Goals (PRGs) evaluate information
within all three data sets. As a result the Administrative Record actually contains three sets
of PRGs: those in the revised BRA, the Assessment of Risk at the National Park Service
Property, and  those found in the FS. The PRGs  present in the  FS  are the  most
representative of the general site conditions and are therefore maintained throughout this
ROD. The following  discussion provides a generic outline for the processes used  in all
three documents.
6.1   Human Health Baseline Risk Assessment

The human health risk assessment process consists of the following major components:
exposure assessment, toxicity assessment, and risk characterization.  The exposure
assessment involves the identification of potentially exposed populations and pathways,
calculation of media-specific exposure point concentrations from data generated during
the Rl, and development of assumptions regarding exposure frequency and duration. The
toxicity assessment utilizes existing chemical-specific toxicity information to determine the
types of adverse health effects associated with chemical exposures, and the relationship
between magnitude of exposure and adverse effects. Carcinogenic risks are evaluated
by factoring the intake of a chemical with the slope factor for that contaminant. Non-
carcinogenic  risks  are  evaluated by comparing the  intake of a  chemical to  the
corresponding reference dose of that compound.  Risk characterization combines the
exposure and toxicity assessments to quantitatively and qualitatively evaluate the potential
risks posed. The risk assessment process concludes by the calculation of media-specific
cleanup levels that are  adequately protective  of human health.  Cleanup levels are
discussed further in Section 7.1 below.

EPAemployed a reasonable maximum exposure (RME) approach to estimate the potential
exposures  and  associated risks at the site.  The RME is the highest exposure that is
reasonably expected to occur at the site and  is intended to estimate a conservative
exposure case that is still within the range of possible exposures. The exposure pathways
evaluated in  this assessment included incidental ingestion and dermal contact with
surface/subsurface soils, sediments, and groundwater ingestion and inhalation.

EPA evaluated  the chemicals detected on-site  according to their potential to produce
either cancer and/or non-cancer health effects. The carcinogenic risk range EPA has set
for Superfund cleanups to be protective of human health is 1 x 10"4 to 1 x 10"6.  For
example, a cancer risk of 1 x 10'6 indicates that an individual has a 1 in 1,000,000 (or 1 in
10,000 for  1 x 10"4) incremental  chance of developing cancer as a result of site-related
exposure to a carcinogen over a 70 year lifetime under  the specific exposure conditions
at the site.  EPA generally uses the  cumulative benchmark risk level of 1 x 10"4 for all
exposures relating to a particular medium to trigger action for that medium. In other words,
a carcinogenic risk greater than 1 x lO^for soil would indicate that remedial action for soil
is necessary. However, EPA may decide that a risk level less than 10'6(i.e., a risk between

-------
                                                                Record of Decision
                                                                  September 1998
	Page31

10"" and 10"6) is unacceptable due to site-specific conditions and that remedial action is
warranted.

Non-cancer exposure estimates were developed using EPA reference doses to calculate
a Hazard Index (HI).  A HI greater that 1 indicates that constituents are  present  at
concentrations that may produce harmful effects. The resultant carcinogenic and non-
carcinogenic risks for the future on-site construction worker, future on-site worker and
future on-site resident are provided in Table 6-1.

The principle threat to human health and the environment at this Site is from exposure to
contaminated soils and groundwater. This is illustrated by the conceptual site model which
traces NAPLs migrating from MGP source areas through unsaturated soils and downward
to the groundwater. The migration of NAPLs would continue through the saturated zone
until encountering zones of lower permeability. This would result in exposure pathways
consisting of contaminated soils in  the unsaturated  and saturated zones, a dissolved
phase groundwater plume, and NAPL source areas.

Potentially exposed populations to these pathways could include both commercial workers
and  residential  populations. Commercial  workers are most likely to  be exposed  to
contaminated surface and subsurface soils whereas future residential populations would
likely be exposed to contaminated surface soils and groundwater. It should be noted that
while both commercial and residential scenarios were evaluated the most likely use of the
property is commercial.

The evaluation of the commercial workers and future residential populations within these
exposure scenarios resulted in unacceptable risk levels from soils and groundwater. As
evidenced in Table 1, risks under the construction worker and long term worker scenarios
were largely driven by incidental ingestion and/or dermal contact  with surface and
subsurface soils. The risk to future resident scenario was driven primarily by exposure to
groundwater. As footnoted in table one, the total risk values were calculated separately
regarding the shallow aquifer and the deep aquifer as it is not expected that a given child
would be exposed to both aquifers. The contaminants which contribute significantly to the
site risks are PAHs and arsenic.

For  this Site, EPA believes that remedial  action  is warranted based  on site-specific
conditions discussed above. The following sections evaluates the remedial alternatives
considered for this Site and their effectiveness in addressing these principal threats.

-------
Record of Decision
   September 1998
          Page32
TABLE 6-1
LIFETIME CARCINOGENIC AND NON-CARCINOGENIC RISKS
INDUSTRIAL AND RESIDENTIAL SCENARIOS
Exposure
Pathway
Construction
Worker
Cancer
Risk
Hazard
Index
On-Site Long Term
Worker
Cancer
Risk
Hazard
Index
Future Resident
(Child)
Cancer
Risk
Hazard
Index1
Surface Soil
Incidental
Ingestion
Dermal Contact
4-Oe-6
5.8"7
1.1e'1
7.4'3
1.0e'5
4.9e'6
5.2e"2
2.3e'2
6.2e'5
8.9G-6
1 ,4e+0
9.4e'2
Subsurface Soil
Incidental
Ingestion
Dermal Contact
7.8e'6
1.9e'6
3.9e'3
4. Be"4
NE
NE
NE
NE
NE
NE
NE
NE
Shallow Groundwater
Ingestion/
Inhalation
NE
NE
NE
NE
1 .4e'3
2.3*2
Deep Groundwater
Ingestion/
Inhalation
Total Risk
NE
2.4e'5
NE
0.12
NE
1.5-5 ,
NE
0.075
5.0e'3
5.08"3*
6.7e*3
6700*
Footnotes:
*Total risk values from exposure to deep groundwater. The total risk from shallow
groundwater calculated at 1 .4e'3 (carcinogenic) and 230 (non-carcinogenic).
NE - Not evaluated for this receptor.

-------
                                                               Record of Decision
                                                                 September 1998
                                                              	Page33
7.0   DESCRIPTION OF ALTERNATIVES
The following section provides a summary of the remedial alternatives for soils and
groundwater/NAPL that were evaluated in detail  in the Feasibility Study Report.  All
alternative cost estimates are expressed in 1997dollars and are based on conceptual
engineering, design and construction. Total present worth costs include capital costs and
operation/maintenance costs to completely finance the remedy over its planned life.
7.1   Development of Cleanup Levels

A  Final Feasibility Study was completed  in December 1997 to develop and evaluate
cleanup alternatives that provide adequate protection of human health. This effort required
the derivation of cleanup levels for the media of concern: soils and groundwater/NAPL.
Cleanup levels were necessary to identify areas to be addressed by EPA's  response
action for the site.  Based upon City of Charleston zoning plans and expected future
commercial land-use in the general site area, EPA has selected soil cleanup levels to be
protective of the construction worker under a future commercial land-use scenario. Given
the close proximity of the Dockside Condominiums to the site, potential exposure risks to
residents were also considered and as such ultimately factored into the final cleanup
levels.

In the final  analysis the cleanup  levels selected  are actually protective for  both
construction workers and future residents. This is possible because the cleanup levels
chosen were on the more protective end of the  risk range for protecting the future
construction workers. As such they also fall within the acceptable range of risk values
which would be protective for on-site residents.
 7.1.1  Soils

 The Remedial Action Objectives (RAOs) for soils are focused on the protection of human
 health and the protection of groundwater quality.  From a human health perspective the
 RAOs include ensuring that soils exposure concentrations levels are adequately protective
 for the following scenarios: the future construction worker, the future long term worker, and
 future residents.   The FS  developed cleanup levels for soils that were  within  EPA's
 protective risk range of 1 x  10"4 to 1 x 10'6 for these three scenarios.

 The corresponding Preliminary Remedial Goals (PRGs) were presented in the Rl and
 summarized  in Table 7-1. These values were based on  data presented  in the risk
 assessment. The PRGs are not the concentrations above which all soils should  be
 remediated. The PRGs are  based upon the Upper Confidence Limits10 (UCL) in the same
       '"The UCL, which followed the identical approach used in the Human Health
 Baseline Risk Assessment, defined the soil exposure point concentrations as the upper

-------
                                                               Record of Decision
                                                                 September 1998
                                                              	Page34
manner as the risk  assessment  used UCL  in calculating the soil exposure point
concentrations for determining overall site risk. Because the UCL were used in calculating
the current site risk (3x10'5) it would follow that when back-calculating from an acceptable
site risk value (1x10"6) to a specific soil cleanup value, the resulting concentrations should
also reflect the UCL.

PRGs were initially developed for carcinogenic PAHs, arsenic and beryllium. Ultimately
beryllium was removed  from further consideration. This decision was based  on  the
consideration that  only  two  of  the  43 subsurface soil samples exceeded the PRG
calculated for beryllium.

When evaluating the potential risk associated with  exposure to carcinogenic PAHs, the
toxicity associated with benzo(a)pyrene is used as a point of reference. The concentration
of cPAHs can be evaluated by relating the toxicity of each cPAH to benzo(a)pyrene. For
example,  benzo(a)anthracene  has  a  relative  potency  factor  of  0.1.   If  the
benzo(a)anthracene concentration is 5 rng/kg, it is lexicologically equivalent to a BaP
concentration of 0.5 mg/kg. These concentrations are referenced throughout the remainder
of this  ROD as Benzo(a)Pyrene toxicity equivalents, or B(a)Peq. The selected PRG for
B(a)Peq is 1.7 ppm and the PRG for arsenic is  7.6 ppm.

Based orTSummers model results as presented in Section 8.2 of the Rl report, a cPAH soil
remedial goal protective of groundwater was not necessary since such a goal would be
several orders of magnitude greater than soil remediation levels associated with direct or
indirect exposures.
7.1.2 Groundwater/NAPL

A source area of subsurface NAPL in addition to an impacted area of groundwater have
been identified at the site.  The presence of NAPL as reported in the Rl can be grouped
around  the MGP; more specifically the former gas holder, the former rail spur, and the
former oil tanks. The NAPL source areas that will be addressed are illustrated on Figure
7-1. The general locations for the placement of recovery wells addressing the dissolved
phase plume are also shown in Figure 7-1. This figure represents general locations for
both  NAPL  recovery wells and groundwater recovery wells.  The exact locations  and
number of wells may be modified or expanded based on remedial design considerations.
 limit of the 95 percent confidence interval of the arithmetic mean.

-------
                                        Record of Decision
                                           September 1998
                                       	Page35
            Table 7-1
Soil Preliminary Remediation Goals
HYPOTHETICAL FUTURE RES
BSG-CAUQULAILC*.
II
II
ft
F
E
E
E
;
•4GESTION OF SOIL
1
,f
\
.F
:D
tw
tt
200
1.00E-06
1
365
6
15
25550

t
• >
JERMAL CONTACT
JA
^F
4490
0.6

EABAMETER.
EKA)Pe<»
Arsenic
EKA)P«q
Arsenic
B(A)Pe 7.3 9.1 0.01
) 1.8 8.8 0.001
': 0.6!MG^G
) 2.9;MG/KG

) '. 6.0 'MG/KG
}' 291MG/KG
PRG (1.0E04) '• «FMG/KG _ *
PRG(1.0E-04): 290~MC/KG _ >•

-------
                                                              Record of Decision
                                                                September 1998
                                                                       Page36
EPA has  adopted the long-term  remediation objectives  for sites  where  NAPL  is
encountered in groundwater as presented in the EPA OSWER Directive 9234.2-25,
"Guidance for Evaluating the Technical Impracticability of Groundwater Restoration (EPA
1993)". In general EPA's groundwater/NAPL remediation objectives are:

      •      Removal or treatment of NAPL to the maximum extent practicable;

      •      Containment of potentially non-restorable source areas; and

      •      Restoration of aqueous contaminant plumes.

A phased approach for groundwater remediation will be used to achieve these objectives
at this Site. The initial effort will concentrate on removal or treatment of NAPLs previously
identified at the former gas holder, the former rail spur, and the former oil tanks. This would
typically consist of free-phase NAPL removal aided by pump-and -treat. Removal of NAPLs
is anticipated to have the effect of mitigating the primary contaminant source responsible
for groundwater contamination at this Site. Concurrent with the NAPL removal, additional
actions will be undertaken to restore the aqueous contaminant plumes to meet MCLs.

The NAPLs removal will be monitored to evaluate the practicability of such actions. Should
complete source removal or treatment prove impracticable, the use of migration controls
or containment measures will  be taken for the  non-restorable source  areas. The
determination of technical impracticability will be made by EPA, in consultation with SC
DHEC, based on site-specific characterization data and remedy performance data. Such
data would include, but not necessarily be limited to:

      A demonstration that contaminant sources have been removed and contained to the
      maximum extent practicable;
      An analysis of the performance of any  ongoing or completed remedial actions;
      Predictive analysis of the time frames to attain required cleanup levels using
      available technologies; and
      A demonstration that no other remedial technologies could attain the cleanup levels
      within a reasonable time frame.

Should EPA ultimately make a determination of technical impracticability based on an
evaluation of the supporting data, the remedy would be re-evaluated and documented by
a ROD amendment. The groundwater/NAPL alternatives developed in the FS Report and
summarized in  this ROD will  focus on a phased  approach to achieving  the three
groundwater/NAPL remediation objectives listed above. Ultimately it is it is expected that
the MCLs listed below will apply to this Site.  Carbazole is the one exception where the
value listed is based on risk-based calculation rather than an MCL.

-------
FLUOR DANIEL GTI
REV. NO.:
DRAWING DATE:  | ACAO FILE:

   2/4/98
     - IMPACTED  SOIL TO BE EXCAVATED
                                    *


     - PROPOSED DNAPL RECOVERY

       LOCATION




     ~ PROPOSED RECOVERY WELL
                                                                                                           o

                                                                                                           o
                                                                                                           c
                                                                                                              a>
                                                                                                           o'
                                                                                                           D
                                                                                                           O
                                                                                                   o'


                                                                                                   CO
                                                                                                            •s   .
                                                                                                             g o
                                                                                                             3 -^
                                                                                                               8
                                                                                                               0;
                                                                                                             vo o
                                                                                                             oo 3

-------
                                                               Record of Decision
                                                                 September 1998
                                                              	Page38
                    GROUNDWATER CONTAMINANTS (PPM)
Contaminant
Arsenic
Cyanide
Benzene
2,4-Dimethylphenol
Benzo(a)pyrene
Ethylbenzene
Beryllium
Lead
Carbazole
Mercury
Chrysene
Naphthalene
Chromium
Nickel
Copper
Toluene
Maximum Detected
0.088
4.5
5.2
0.89
0.038
1.2
0.013
1.9
0.15
0.015
0.16
5.'5
0.13
0.30
5.1
1.8  .
Cleanup Goal
0.05
0.2
0.005
0.7
0.0002*
0.7
0.004
0.015
0.005**
0.002
0.020
1.5
0.1
0.1
1.3
1.0
•Represents PAHs as a group.
"Based on actual risk calculation rather than MCL
7.2   Soil Alternatives

The following information presents the different cleanup alternatives which were initially
considered for remediating the contaminated soils at the Site.
 7.2.1 Alternative 1: No Action

 The No Action Alternative entails performing no remedial activities and is included in
 accordance with the NCP.
 7.2.2  Alternative 2: Natural Attenuation

 This alternative would involve the processes  of natural attenuation to  degrade soil
 contamination over time.  Natural Attenuation  is dependent upon demonstrating that
 contaminant  levels are decreasing  due to natural processes.  The use  of Natural
 Attenuation is dependent upon several factors including the monitoring of'contaminant
 levels in soils, existing microbial populations,  nutrient levels, and electron  acceptor
 conditions.  This  alternative will be eliminated from further consideration due  to

-------
                                                                 Record of Decision
                                                                   September 1998
                                                                          Page39
implementability constraints  associated with the planned development  for the Site,
specifically buildings and urban cover.
7.2.3 Alternative 3: Surface Cover/Capping

This alternative consists  of utilizing a  low  permeability surface  cover to  isolate  the
contaminated soil from direct human contact and reduce infiltration of surface waters
through these same area. The surface cover would be constructed of low permeability soils
or other man made materials. This alternative will be retained for further evaluation.
7.2.4 Alternative 4: In Situ Bioremediation

This alternative involves the application of an electron acceptor and nutrients to enhance
any naturally occurring biodegradation which may be occurring at the Site. Potential
electron acceptors and nutrients could include oxygen, hydrogen peroxide, or nitrate which
would be introduced into the contaminated  soil. Due to  implementability  constraints
associated with buildings, an expected lengthy treatment duration, and lack of fit with the
planned site use, this alternative will be eliminated from further consideration.
7.2.5 Alternative 5: Excavation, Chemical/Biological Treatment, & Replacement

This alternative would initially involve the excavation of contaminated soil. Debris would
be steam cleaned and disposed of in" a landfill The  soils would be added to a slurry
reactor along with a chemical oxidant. This slurry would then be dewatered followed by the
addition of nutrients and air into the reactors. Following this treatment the soil would be
dewatered and backfilled into the excavation. Due to implementability constraints including
limited available   on-site  space,  this  alternative will  be eliminated  from  further
consideration.
 7.2.6  Alternative 6: Excavation, Thermal Desorption, & Replacement

 This alternative would consist of excavating the contaminated soil and treating the soil in
 an on-site low temperature thermal desorption unit. This process requires heating the soil
 to elevate the vapor pressure of the contaminants which would enable diffusion through,
 and volatilization from, the soil. The treated soil  would then be used to backfill the
 excavation  areas.

 Thermal  desorption is affected by several factors including the  type  of contaminants
 present, their concentrations in the soil, their desorption temperature, and the duration of
 treatment. Due to space limitations, possible recalcitrant contaminants, and public relation
 concerns within this highly populated area, this alternative will be eliminated from further

-------
                                                                Record of Decision
                                                                   September 1998
                                                                          Page40
consideration.
7.2.7  Alternative 7: Excavation & Off-Site Incineration

This alternative would involve excavating the contaminated soil and transporting them to
an off-site facility for incineration. The excavated areas would then be backfilled with clean
fill material. This alternative is generally effective for  treating similar sites and will be
retained for additional evaluation.
7.2.8 Alternative 8: Excavation & Off-Site Landfill

This alternative involves excavating the soils followed by transportation to an off-site
landfill. Following excavation, the area will be backfilled with clean fill. Presently the waste
associated with MGPs are not subject to the Land Disposal Restriction but are regulated
as hazardous because they typically exhibit a toxicity characteristic of hazardous waste,
most often due to the  concentration of benzene.  Overall  this still remains a viable
alternative and will be retained for evaluation.
7.3    Shallow Groundwater

The following sections address the remedial alternatives for shallow groundwater. In the
context of the site wide groundwater objectives this requires addressing both the dissolved
phase portion of the plume in addition to the removal or treatment of NAPLs. The removal
or treatment of NAPLs is referenced to as source removal in these following sections.
 7.3.1  Alternative 1: No Action

 The No Action Alternative would leave the Site groundwater untreated. Long term
 monitoring of the groundwater would be included to monitor site specific contaminants of
 concern. The No Action alternative is retained throughout the FS in accordance with the
 NCP.

 7.3.2  Alternative 2: Institutional Controls

 Under this alternative no remediation would be performed and site groundwater would
 remain untreated. This alternative would involve imposing restrictions on the future uses
 of groundwater at the Site.  These institutional controls would consist of deed restrictions
 and access restrictions. This alternative will not be retained for further evaluation as it is
 not capable of meeting the three groundwater objectives stated in section 7.1 Development
 of Cleanup Levels. While this alternative will be eliminated as a stand-alone alternative,
 it will be combined with other alternatives to address contaminated shallow groundwater.

-------
                                                                Record of Decision
                                                                   September 1998
                                                                	Page41
7.3.3  Alternative 3: Institutional Controls, Source Removal, Phytoremediation, and
      Natural Attenuation

This alternative utilizes institutional controls as mentioned in the preceding alternative in
combination with several other processes including source removal (NAPLs),
phytoremediation and natural attenuation. Source  removal would consist of extracting
NAPL from known NAPLs locations via recovery wells followed by either reuse, energy
recovery, or destruction of recovered material. The phytoremediation would involve the
planting of specifically selected tree species which are theoretically capable of breaking
down the contaminants present in the grogndwater. The natural attenuation approach
would assess electron acceptors and nutrients in addition to evaluating the microbiological
populations and conditions. While there is no evidence that this particular combination of
processes would be effective for the site specific contaminants and conditions, it has the
potential to work under limited conditions. As such it will be retained for further evaluation.

7.3.4 Alternative 4: Institutional Controls, Source Removal,  Phytoremediation, and
      In Situ Bioremediation

This alternative would utilize those technologies/processes described in alternative 3  but
replace natural attenuation with in situ bioremediation. This would require the application
of an electron acceptor and nutrients to the shallow groundwater in order to stimulate
biological degradation of the contaminants. While this alternative is considered to be
marginally implementable due to constraints of placement and access to injection points,
it will be retained for further consideration.

7.3.5 Alternative 5: Institutional Controls, Source Removal, Phytoremediation, Grout
      Curtain, Vertical Wells, Separation, Filtration, GAC, and POTW Discharge

This alternative would utilize  a portion of the technologies/processes described in
alternative 4 (Institutional Controls, Source Removal, Phytoremediation) in combination
with a downgradient grout curtain to contain groundwater. Additionally this alternative also
includes the extraction of  the dissolved  phase groundwater plume. This extracted
groundwater would  then  undergo separation, filtration,  and granular activated carbon
treatment before discharging to a sanitary sewer system  (POTW). Although site specific
conditions would result in implementation constraints for this alternative (existing electrical
substation and underground utilities), this alternative will be retained for further evaluation.

7.3.6  Alternative 6: Institutional Controls, Source Removal, Phytoremediation, Sheet
       Piling, Vertical Wells, Separation,  Filtration, GAC, and POTW Discharge

This alternative would utilize the technologies/processes described in alternative 5 but
would substitute sheet piling for the grout curtain. The sheet piling would essentially act
to retain the groundwater in a manner similar to the grout curtain.  This alternative  has
 been eliminated from further consideration due to the implementation difficulties, especially

-------
                                                                Record of Decision
                                                                  September 1998
                                                               	Page42
those associated with installing sheet piling in areas having underground utilities.

7.3.7 Alternative 7: Institutional  Controls,  Source Removal, Phytoremediation,
      Interceptor Trenches, Separation, Filtration, GAC, and POTW Discharge

This alternative is a variation of alternative 6 and uses interceptor trenches instead of
sheet piling. The interceptor trench or trenches would act as a barrier to the migration of
shallow groundwater. Due to implementation  difficulties associated with the presence of
underground utilities, this alternative was eliminated from further consideration.

7.3.8 Alternative 8: Institutional  Controls,  Source Removal, Phytoremediation,
     . Vertical Wells, Separation, Filtration, GAC, and POTW Discharge

This alternative is similar to alternative 5 with the exception of omitting the grout curtain
and in turn depending entirely upon the use  of vertical wells to attain hydraulic control.
Because this alternative would potentially address the groundwater objectives for this site,
it will be retained for further evaluation.

7.4   Intermediate Groundwater

This secTion presents alternatives developed to address contaminated groundwater in the
intermediate aquifer.
7.4.1  Alternative 1: No Action

The No Action alternative would leave the intermediate groundwater untreated. Long term
monitoring of the intermediate groundwater would be included to determine groundwater
conditions over time. This alternative is retained throughout the FS in accordance with the
NCP.
 7.4.2  Alternative 2: Institutional Controls

 Under this alternative  no remediation would be performed and site groundwater would
 remain untreated. This alternative would involve imposing restrictions on the future uses
 of groundwater at the Site. These institutional controls would consist of deed restrictions
 and access restrictions. This alternative will not be retained for further evaluation as it is
 not capable of meeting the three groundwater objectives stated in section 7.1 Development
 of Cleanup Levels. While this alternative will be eliminated as a stand-alone alternative,
 it will be combined with other alternatives to address contaminated shallow groundwater.
 7.4.3  Alternative 3: Institutional Controls and Natural Attenuation

-------
                                                                Record of Decision
                                                                   September 1998
	Page43

This alternative utilizes institutional controls as mentioned in the preceding alternative in
combination with natural attenuation.  The natural attenuation approach would assess
electron acceptors and nutrients in addition to evaluating the microbial populations and
conditions. While there is no evidence that this particular combination of processes would
be effective for the site specific contaminants and conditions,  it has the potential to work
under limited conditions. As such it will be retained for further evaluation.
7.4.4 Alternative 4: Institutional Controls and In Situ Bioremediation

This alternative would utilize the institutional controls described above in conjunction with
in situ bioremediation. Bioremediation would be approached through the application of an
electron acceptor and nutrients to the groundwater to stimulate biological degredation of
the contaminants. While this alternative is considered to be marginally implementable due
to constraints of placement and access to injection points, it will be retained for further
consideration.
 7.4.5  Alternative 5: Institutional Controls, Vertical Wells, Separation, Filtration, GAC,
       and POTW Discharge

 In addition to the institutional controls this alternative would include the installation of
 vertical wells to remove intermediate groundwater for treatment and hydraulic control.
 Additionally  this  alternative  also  includes  the extraction of the  dissolved  phase
 groundwater plume. This extracted groundwater would then undergo separation, filtration,
 and granular activated carbon treatment before discharging to  a sanitary sewer system
 (POTW). This alternative will be retained for further evaluation.
 8.0    SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

 The objective of this section of the ROD is to evaluate the relative performance of the
 alternatives with respect to the nine evaluation criteria, so that the advantages and
 disadvantages of each are clearly understood. The Threshold Criteria must be met for an
 alternative to be selected. These criteria are presented in Sections 8.1 and 8.2, followed
 by a discussion presented in the following media-specific subsections: 1) soils; 2) shallow
 groundwater; and 3) intermediate groundwater. Sections  8.3 through 8.7 present the
 Balancing Criteria, which are used to weigh the major advantages and disadvantages of
 each remedial alternative. The discussion in these Sections is organized using the same
 media-specific  subdivisions.   Sections 8.8  and 8.9 discuss State Acceptance and
 Community Acceptance, respectively.
 8.1   Overall Protection of Human Health & the Environment

-------
                                                                 Record of Decision
                                                                   September 1998
                                                                	Page44
Overall  protection of human health and the environment  addresses  whether each
alternative  provides  adequate protection of human health and the  environment and
describes how risks posed through each exposure pathway are eliminated, reduced, or
controlled through treatment, engineering controls, and/or institutional controls
9.1.1  Soil

Four remedial action alternatives for soil were retained for detailed evaluation. These
include:
      Alternative 1:  No Action;
      Alternative 3:  Surface Cover/Capping;
      Alternative 7:  Excavation & Off-Site Incineration; and
      Alternative 8:  Excavation & Off-Site Disposal
In the following analysis these alternatives are compared to one another against the nine
criteria. The relative advantages and disadvantages of each  alternative  are also
summarized in the following table.
COMPARISON OF SOIL CLEANUP OPTIONS
Cleanup Option
No Action
Cover/Capping
Off-Site
Incineration
Off-Site Landfill
Overall
Protection
X
o
•
•
Compliance
with ARARs
X
$
•
•
Long-term
effectiveness
X
&
•
&
Reduction of
toxicity, mobility.
& volume
X
o
•
®
Short-term
effectiveness
X
•
&
€>
Ability to
Implement
•
&
%
%
Cost
•
#
®
%
 X - Fails Minimum Requirements, O - Nominally Acceptable,  & - Moderately acceptable,
 acceptable
- More
 Overall Protection of Human Health and the Environment

 Alternative 7, Excavation & Off-Site Incineration, and Alternative 8, Excavation & Off-Site
 Land filling, both provide the most protection to human health and the environment through
 the removal of impacted soil thereby preventing potential future exposure. Both of these
 alternatives are considered the most effective alternatives in meeting this criteria.

-------
                                                                Record of Decision
                                                                   September 1998
                                                                	Page45
Alternative 3, Surface Cover/Capping, would provide limited protection for some exposure
pathways but not to the future on-site construction workers. It also does not address the
soil to groundwater pathway for migration of contaminants.  The No-Action  alternative
would not provide adequate protection of human health and the environment and is not
considered effective in meeting this criteria.

Compliance with Applicable or Relevant and Appropriate Requirements

Alternatives 7, and 8 could be designed appropriately to be in compliance with all federal
and  state applicable or  relevant and appropriate requirements (ARARs) and are all
considered effective in meeting this criteria. Alternative 3, Cover/Capping may meet action-
specific and location-specific ARARs but may not meet chemical-specific ARARs. The No
Action alternative does  not meet the  ARARs for  protecting human health and the
environment and is considered  ineffective in meeting this criteria.

Short-Term Effectiveness

While alternatives 3, 7, and 8,  are capable of meeting this criteria to varying degrees,
Alternative 3, Surface Cover/Capping, would be the most effective in meeting this criteria.
Alternatives 7 and 8 are least effective in meeting this criteria due to short term risk
associated  with worker  exposure'  during  excavation and transportation activities.
Alternative 1, No Action,  would have no short term effectiveness.

Long-Term Effectiveness

Alternatives 7  and 8 would  both provide the greatest long-term effectiveness due to
removal of the impacted soil. Because Alternative 7 includes destruction of impacted soil
via incineration, it would be the best choice in meeting the long-term effectiveness criteria.
Alternative 3, Surface Cover/Capping, would be somewhat less effective over the long term
since it would rely on periodic maintenance of the cover/cap to maintain its integrity. The
No Action alternative would not provide any long term  effectiveness.

Reduction of Toxicitv. Mobility, or Volume

Alternative 7, Excavation and Off-Site Incineration, would reduce the toxicity, mobility, and
volume of impacted soil and is considered to be the most effective alternative in meeting
this criteria. Alternative 8, Excavation & Off-Site Landfilling, provides a reduction in toxicity
and mobility but does not reduce the volume and is therefore slightly less effective in
meeting this criteria. Alternative 3, Cover/Capping, would also reduce mobility and toxicity.
The No Action alternative would not effectively meet this criteria.

 Implementabilitv

 The No Action alternative meets this criteria and would also be the easiest alternative to
 implement. Alternative 3, Cover/Capping, is also  readily implementable for this site.

-------
                                                                Record of Decision
                                                                   September 1998
                                                               	Page46
Alternative 7, Excavation & Off-Site Incineration, and Alternative 8, Excavation & Off-Site
Incineration, would be implementable but are also the most difficult of the alternatives to
implement.

Present Worth Costs

Since there would be no costs associated with the No Action alternative, it is inherently the
most desirable in meeting this criteria. Alternative 3, Cover/Capping ($458,000) is more
expensive than the No Action alternative but considerably less costly than alternatives 7
($7,570,000) and 8 ($2,280,000). Alternative 7, Excavation & Off-Site Incineration, and
Alternative 8, Excavation & Off-Site Incineration, would be considered the most expensive
to implement and are the least desirable from a cost alone consideration.

8.1.2  Shallow Groundwater/NAPL

As discussed previously in Section 7.1.2 the remedial action objectives for sites where
NAPL is encountered in groundwater consists of the following:

            Removal or treatment of NAPL to the maximum extent practicable;
      •     Containment of potentially non-restorable source areas; and
      • ~   Restoration of aqueous contaminant plumes.
 Five alternatives were retained for comparative evaluation of the shallow groundwater.
 These alternatives consist of the following:

       •      Alternative 1:   No Action;

       •      Alternative 3:   Institutional Controls, Source Removal, Phytoremediation,
             and Natural Attenuation;

       •      Alternative 4:   Institutional Controls, Source Removal, Phytoremediation,
             and In Situ Bioremediation;

       •      Alternative 5:   Institutional Controls, Source Removal, Phytoremediation,
             Grout Curtain, Vertical Wells, Separation,  Filtration, GAC,  &  POTW
             Discharge; and

       •      Alternative 8:   Institutional Controls, Source Removal, Phytoremediation,
             Vertical Wells, Separation, Filtration, GAC, & POTW Discharge.

 With the exception of Alternative 1, the No Action alternative, all remaining alternatives
 include source removal in accordance  with the first remedial action objective. The
 remaining alternatives differ in their approach to addressing the remaining two objectives.
 specifically that of containing potentially non-restorable source areas and restoration of

-------
                                                               Record of Decision
                                                                  September 1998
                                                               	Page47
the aqueous contaminant plume. These alternatives are summarized in the table below.
:COMPARISON OF SHALLOW GROUNDWATER CLEANUP OPTIONS
Cleanup Option
No Action
Source removal,
Phyto. Natural
Attenuation
Source removal,
Phyto,
Bioremediation
Source removal,
Phyto, Grout
Curtain, Recover
Wells with Filter
System
Source removal,
Phyto, Recover
Wells with Filter
System
Overall
Protection
X
;!>
%
•
•
Compliance
with ARARs
X
o
0
•
•
Long-term
effectiveness
X
^
&
•
•
Reduction of
toxicity, mobility.
& volume
X
®
•®
•
•
Short-term
effectiveness
X
%>
©
®
®
Ability to
Implement
•
•
<$
O
&
Cost
•
•
<®
O
*
 X - Fails Minimum Requirements, O - Nominally Acceptable, f: - Moderately acceptable,  • - More
acceptable
Overall Protection of Human Health and the Environment

The primary component of this evaluation criterion is the ability of a remedial alternative
to achieve the remedial action objectives established for groundwater. This would consist
of the removal, treatment and containment of NAPL and the containment and restoration
of aqueous contaminant plumes. Alternatives 5 and 8 would meet these objectives and is
therefore considered to be  two alternatives most protective of human health and the
environment. These technologies have been well established at other sites.

Alternatives 3 and 4 may be capable of meeting this criteria under controlled conditions,
however, such site specific conditions were not effectively established as of the writing of
this ROD. It would follow that there is some uncertainty as to their effectiveness in meeting
the criteria of overall protection of  human health and the  environment. Limitations on
 locations for  tree planting  is limited and irregularly spaced which could  impact the
effectiveness of phytoremediation.
 Since  the  no-action alternative does not  include  active  measures to  address
 groundwater/NAPL except for what is planned under the Interim Remedial Action, this

-------
                                                               Record of Decision
                                                                  September 1998
                                                              	Page48
alternative is not protective.

Compliance with ARARs

Section 121 (d) of CERCLA requires that remedial actions at CERCLA sites at least attain
legally applicable or relevant and appropriate federal and state requirements, standards,
.criteria and limitations which are collectively referred to as ARARs, unless such ARARs
are waived under CERCLA Section 121(d)(4).  Applicable requirements  are those
substantive environmental protection requirements, criteria, or  limitations promulgated
under federal or state law that specifically address hazardous substances, the remedial
action  to be implemented at the site, the location of  the site,  or other circumstances
present at the site.  Relevant  and appropriate requirements are those substantive
environmental protection requirements, criteria, or limitations promulgated under federal
or state law which, while not  applicable to hazardous materials found at the  site, the
remedial action itself, the site location or other  circumstances at the site, nevertheless
address problems or situations sufficiently similar to those encountered at the site that
their use is well-suited to the site.  Compliance with ARARs addresses whether a remedy
will meet all of the ARARs of other federal and state environmental statutes or  provides
a basis for invoking a waiver.

Alternatives 3,4,5, and 8 were evaluated with respect to action-specific, chemical-specific,
and location-specific ARARs.  Alternatives 3, 4,  5, and 8 all incorporate technologies to
contain and/or potentially recover NAPL and impacted groundwater from the source areas
on-site. While achievement of MCL-based cleanup levels maybe technically impracticable
at sites with NAPL contamination, Alternatives 5 and 8 incorporate a series of extraction
wells that are expected to have a beneficial impact on the restoration of dissolved-phase
aqueous plumes downstream of the source area in the former Treatment Area. Therefore,
Alternatives 5 and 8 provide the highest degree of compliance with ARARs.

Alternative 3 relies solely on phytoremediation and natural attenuation for groundwater
containment and restoration and therefore receives a lower rating for this criterion. While
research does indicate that phytoremediation via trees can successfully treat groundwater
contaminated with BTEX and  some  inorganic compounds under controlled conditions,
there is no research indicating their effectiveness  on  PAH contaminated groundwater.
Other  phytoremediation studies, using grasses to  remediate PAHs,  have shown some
effectiveness on  soils but not groundwater. Additionally  these studies were limited to
 anthracene and pyrene in soils and  not groundwater.  In a similar manner Alternative 4
relies  entirely upon phytoremediation and in situ  bioremediation for containment and
 restoration and therefore receives a  lower rating than alternatives 5 and 8.
 Short-Term Effectiveness

 Short-term effectiveness refers to the period of time needed to complete the remedy and
 any adverse impacts on human health and the environment that may be posed during

-------
                                                                Record of Decision
                                                                   September 1998
                                                                 	Page49
construction and implementation of the remedy until Performance Standards are achieved.
The primary factors influencing ratings for short-term effectiveness are potential adverse
impacts to the community and/or remediation workers during site construction activities,
potential environmental impacts and duration of remedy implementation activities.

None of the alternatives were significantly better than the others with regards to short-term
effectiveness. Alternatives 3 and 4 can be implemented quickly with minimal disruption yet
the growth period required for phytoremediation would require several growing  seasons
to reach its maximum  effectiveness. Alternatives 5 and 8 could be effective  within a
relatively short time frame but would have potential short-term risk associated with worker
exposure to contaminated groundwater recovered during the initial installation. For these
reasons alternatives 3 and 4 received a slightly higher rating for short-term effectiveness
than alternatives 5 and 8. The No Action alternative would not be considered to have any
short-term effectiveness.

Long-Term Effectiveness

Long-term effectiveness and permanence refers to expected residual risk and the ability
of a remedy to maintain reliable protection of human health and the environment over time,
once Performance Standards have  been  met. This criterion includes the consideration or
residual risk and the adequacy and reliability of controls.

While alternatives 3, 4, 5, and 8  may  all effectively meet this criteria, the long-term
effectiveness for alternatives 5 and 8 have been better documented  than for alternatives
3 and 4. Once again it should be noted that the technologies associated with alternatives
3 and 4 may be capable of meeting this criteria under controlled conditions, however, such
site specific conditions have not been effectively established for this site to date. Due to
the uncertainty associated with alternatives 3 and 4, alternatives 5 and 8 received the
higher  ratings  for long-term effectiveness.  The No Action alternative is considered
ineffective in regards to long-term effectiveness.

Reduction of Toxicitv. Mobility or Volume

This criterion evaluates the reduction in toxicity, mobility or volume through the treatment
technology components of the remedial alternatives.

Alternatives 5, and 8 will reduce  the TMV of the  contaminants of concern in shallow
groundwater and  as such received the highest ratings among the alternatives  when
evaluated against this criteria. Alternatives 3 and 4 will likely reduce the mobility, volume,
and to a lessor extent some of the toxicity associated with groundwater contamination via
phytoremediation. While phytoremediation may act to contain the groundwater it  is not
expected to effectively degrade all the contaminants of concern. The No Action alternative
would not effectively reduce the TMV.

implementabilitv

-------
                                                               Record of Decision
                                                                 September 1998
                                                              	PageSO
This criterion addresses the relative ease of remedy implementation and the availability
of treatment technologies necessary to meet Performance Standards.

The No Action alternative is considered the most effective in meeting this criteria. All the
remaining alternatives are implementable yet require varying degrees of effort for their
implementation. Alternative 3 would require the least amount of effort among the remaining
alternatives. Alternative 5 would be the least implementable due to the major construction
associated with the grout curtain.

Present Worth Costs

This criterion evaluates the present worth costs of the developed remedial alternatives.
Since there would be no cost associated with the No Action alternative other than
groundwater monitoring,  it receives the highest rating among the alternatives for  this
criteria at $307,000.  Alternative 3 is the second least costly alternative ($1,426,000)
followed  closely by alternative 4 ($1,931,000). The remaining alternatives (5  and 8)
represent a substantial increase cost  over the other alternatives at $4,961,000  and
$5,463,000.

8.1.3  Intermediate Groundwater

The groundwater remedial action objectives for the intermediate groundwater are similar
to those applied to the  shallow groundwater  in section 8.1.2.   The  remedial action
objectives for sites where NAPL is encountered in groundwater consists of the following:

•      Removal or treatment of NAPL to the maximum extent practicable;
•      Containment of potentially non-restorable source areas; and
•      Restoration of aqueous contaminant plumes.

The Rl revealed the  presence of both NAPL and a dissolved phase contaminant plume
within the intermediate aquifer. While NAPL appears to be isolated within the area of the
gas holder,  the extent of the dissolved phase contaminant plume was  not well defined
during the Rl. Because the extent of the dissolved groundwater contaminant plume within
the intermediate aquifer was not well defined during the Remedial Investigation, additional
investigation will be performed to  characterize the extent of this contamination  and
presented as operable unit two under a separate ROD. This ROD will address the issue
of source removal (and disposition of this source) for the intermediate aquifer within the
Selected Remedy section of this ROD.
 8.8    STATE ACCEPTANCE

 SC DHEC does concur with EPA's selected remedy described in Section 9.0. The SC
 DHEC concurrence letter is attached to this ROD as Appendix A. SC DHEC believes that
 EPA's selected remedy will be of benefit in the reduction of risk at the site achieving long

-------
                                                              Record of Decision
                                                                September 1998
                                                                 •	PageS 1
term protection of human health and the environment.
8.9   COMMUNITY ACCEPTANCE

A public meeting was held on March 1998 to discuss the remedial alternatives under
consideration and EPA's Proposed Plan for cleanup of the Calhoun Park Superfund Site.
A 60-day public comment period on EPA's Proposed Plan was held from March 16, 1998
to May 15, 1998. A copy of all comments received, EPA's response to these comments,
and a verbatim transcript of the March 1998 meeting are attached to this ROD as Appendix
B, The Responsiveness Summary. In general the community expressed acceptance with
EPA's Proposed Plan as presented during the public meetings.
9.0   THE SELECTED REMEDY

This section of the document provides a description of the components of EPA's selected
remedy on Operable Unit One for the Calhoun Park Superfund Site in Charleston, South
Carolina.  The Performance Standards and other ARARs of EPA's selected remedy are
delineated in the sections that follow. The remedy described has been selected under the
authority granted in CERCLA and is consistent with the requirements of the NCP. EPA's
selected remedy is based upon a full consideration  of remedial alternatives and all
comments received during the 60-day comment period on the Proposed Plan. Cost details
of EPA's selected remedy are delineated in Section 9.4.
 9.1    Soil - Excavation and Off-Site Disposal

 The overall objective of the soil component of EPA's selected remedy is to provide for
 adequate protection of the construction worker under a future industrial land-use exposure
 scenario. As discussed in Section 6.0 of this document, EPA's Human Health Baseline
 Risk Assessment utilized conservative exposure pathways and assumptions to estimate
 the potential risks posed to the future on-site worker. Under the future industrial exposure
 scenario, unacceptable carcinogenic and non-carcinogenic risks were calculated for the
 future on-site worker exposed to subsurface soils (six inches to water table).  Exposure
 pathways quantified were incidental ingestion of and dermal contact with soils.

 EPA's Human Health Baseline Risk Assessment developed cleanup levels for surface and
 subsurface soils within EPA's protective risk range of 1 x 10"4 to 1 x 10"6. The soil remedy
 consists of the excavation of an estimated 6,080 tons of impacted soil with subsequent off-
 site disposal in an approved landfill. EPA's selected soil remedy will eliminate exposure
 to unacceptable concentrations of constituents in soil and permit beneficial future use of
 the  property.

 All excavation activities shall be conducted in a manner which provides adequate short-

-------
                                                              Record of Decision
                                                                 September 1998
                                                              	Page52
term protection of on-site workers, and minimizes disruptions to local businesses and
adjacent neighborhoods.  Air monitoring during active excavation shall be implemented for
the protection of on-site workers and to assess potential off-site impacts.  As warranted,
dust and odor control measures shall be instituted to mitigate adverse impacts in the active
excavation areas, haul roads and adjacent off-site areas. On-site excavations shall be
backfilled and restored to a  condition consistent with the intended future use of the
property.

All excavated soil shall be transported off-site for disposal in an approved hazardous
waste landfill. All transportation and off-site disposal activities shall be conducted in full
accordance with all ARARs, including but not limited to, RCRA and DOT regulations.
9.2   Groundwater/NAPL

EPA's groundwater/NAPL remediation strategy presented in this section applies to the
shallow aquifer described in Section 5.2.  NAPL source removal, followed by either reuse,
energy  recovery,  or destruction of recovered material, will  also be  required for the
intermediate  aquifer.  Additional  performance  standards  may be required for this
intermediate aquifer pending characterization of the dissolved phase contaminant plume.

Implementation of the groundwater/NAPL remedy at this site shall be consistent with
OSWER Directive 9234.2-25, Guidance for Evaluating the Technical Impracticability of
Groundwater Restoration (EPA 1993).  This guidance promotes an iterative, phased
approach which includes early actions to remove contaminant sources, control plume
migration, and mitigate risks posed by impacted groundwater.
 9.2.1  NAPL/Groundwater

 The source areas of subsurface NAPL have been defined on-site, as presented in
 Sections 5.2. These areas are referred to as the former gas holder, the former rail spur,
 and the former oil tanks. The goal of EPA's groundwater/NAPL remedy is the restoration
 of  impacted groundwater at these source areas to the ARAR-based cleanup levels,
 Maximum Contaminant Levels specified by the Safe Drinking Water Act.  However, EPA
 recognizes that restoration to these levels may be technically  impracticable given the
 characteristics  of  NAPL,  limitations  in  remediation  technology  and/or  complex
 hydrogeology. Therefore, the groundwater/NAPL remedy in the three NAPL source areas
 shall, at a minimum, achieve the following Performance Standards:

 1)     Removal or treatment of NAPL to the maximum extent practicable;

 2)     Containment of potentially non-restorable source areas; and

 3)     Containment and restoration of aqueous contaminant plumes.

-------
                                                               Record of Decision
                                                                 September 1998
                                                                        Page53
The above Performance Standards  shall  be achieved  by the recovery of NAPL and
impacted groundwater by extraction wells installed in the shallow aquifer underlying the
three source areas.  An additional extraction well or wells will  be installed  in the
intermediate aquifer in the area of the former gas holder. Figure 7-1 provides an illustration
of the source areas and general locations  of extractions wells. Disposal options for the
recovered NAPLs material may include reuse, energy recovery, or destruction.

All groundwater recovered via this remedy component shall be treated to meet the ARARs
of the selected discharge option.  It is envisioned that all recovered groundwater will be
conveyed to an on-site water treatment system. The water treatment system shall be
properly operated and  maintained to meet the discharge requirements imposed  by the
Charleston POTW.

The full-scale groundwater/NAPL remedy shall be monitored, modified and/or enhanced
where appropriate  to demonstrate that best professional  efforts have been made to
achieve ARAR-based cleanup levels and the applicable Performance Standards of this
remedy component. A comprehensive monitoring network will be established to delineate
the NAPL zone and aqueous contaminant plume. The data generated by this monitoring
program will be  utilized to  track the effectiveness of the remedy  in  achieving the
established objectives.   The.conceptual remedy described herein may be modified and
enhanced as warranted based on review and analysis of monitoring data generated.
Recovery and treatment enhancements may include the installation of additional extraction
wells.  EPA considers the full-scale groundwater/NAPL remedy to be an iterative process
which must be conducted for a sufficient period of time before its ability  to meet applicable
cleanup levels and long-term Performance Standards can be fully evaluated.  All decisions
regarding the technical impracticability of achieving ARAR-based  cleanup levels and the
long-term Performance Standards at the three NAPL source areas shall be made by EPA,
with consultation  by SC DHEC.

Phytore'mediation will  also be used as a supplemental technology to the extraction
wells/separation/filtration system in the shallow aquifer. While the existing research does
not prove that trees would be effective upon all site-specific contaminants, this technology
would be effective on some of the contaminants thereby reducing the overall contaminant
mass and doing so in a low cost approach.

Because phytoremediation is a relatively new technology, its performance upon the
contaminants of concern under these site-specific conditions is untested. For this reason
this technology will be implemented on a limited basis, concurrent with an extraction well
recovery/treatment system, to evaluate its effectiveness on the dissolved phase portion of
the plume. Should phytoremediation prove effective in meeting the performance standards,
this technology  could eventually  be  used  to  replace  portions  of  the extraction
well/separation/filtration system.
 9.3    Cost Summary

-------
                                                             Record of Decision
                                                               September 1998
                                                            	Page54
This section of the document provides a cost summary for the key elements of EPA's
selected remedy at the Calhoun Park Superfund Site. The estimated capital costs for each
major remedy component, estimated operation and maintenance (O&M) costs, and total
net present worth over a 30-year period  are provided below.   All cost estimates are
expressed in 1997  dollars and are based  upon conceptual engineering, design and
construction. The reader is referred to the Final FS Report for a more detailed breakout
of the cost information summarized below.

Soil and Drainage Ditch Sediments
Excavation of 6,080 tons	$152,000
Transportation  and off-site disposal of 6,080 tons	$1,800,000
Backfill	..$121.600

                  Sub-Total Soil Component	$2,280,000

Groundwater/NAPL

Source removal, recovery system and phytoremediation	$997,000
Total Annual Operation & Maintenance	$290.000

Present Worth  Cost (Interest rate 5% over 30 yrs)	$5,463,000


Total Estimated Cost of  EPA's Selected Remedy	$7>743,,000


10.0  STATUTORY DETERMINATIONS

Under CERCLA Section 121, EPA must select remedies that are protective of human
health and the  environment,  comply with  applicable  or  relevant  and  appropriate
requirements  (unless a statutory waiver is justified), are  cost-effective,  and utilize
permanent solutions and  alternative treatment  technologies or resource recovery
technologies to the maximum extent practicable.  In addition, CERCLA  includes a
preference for remedies that employ treatment that permanently and significantly reduces
the volume, toxicity, or mobility of hazardous wastes as a principal element. The following
sections discuss how the selected remedy meets these statutory requirements.

10.1  Protection of Human Health and the Environment

EPA's selected remedy protects human health and the environment through media-specific
components designed to eliminate or mitigate potential risks posed by the site.  EPA's
remedy consists of: excavation and off-site disposal of 6,080 tons of impacted soil;
containment and recovery of NAPL and groundwater.

-------
                                                              Record of Decision
                                                                September 1998
                                                               	PageSS
Excavation of 6,080 tons of the impacted soil will eliminate potential risks posed to the
future construction worker by exposure to surface/subsurface soils. All excavated soil will
be disposed off-site in a controlled and permitted landfill. The excavation and off-site
disposal of impacted soils provides a residual risk (post-remediation risk) of 1x10"6 which
is at the more protective end of EPA's acceptable risk range.

The Performance Standards developed for groundwater and NAPL at the source areas will
remove and treat NAPL to the maximum extent possible, contain potentially non-restorable
source  areas,  and contain/restore aqueous  contaminant  plumes.   All  recovered
groundwater will be treated to protective levels prior to discharge.  Groundwater in the
shallow aquifer is not currently used for residential or industrial purposes, however, EPA's
selected remedy will eliminate risks posed by off-site transport to surface water bodies and
drainage ditches.
10.2  Compliance with Applicable or Relevant and Appropriate Requirements

      EPA's selected response action will meet all ARARs discussed in Section 9.0 of this
document.  These include, but are not limited to:

•     RCRA  Requirements for Identification, Management and  Transportation  of
      Hazardous Waste (40 CFR 261, 262 and 263)
      RCRA Land Disposal Restrictions (40 CFR 268)
      DOT Hazardous Materials Regulations  (49 CFR 107 and 171-179)
      Safe Drinking Water Act (40 CFR 141)
      Clean Water Act (40 CFR 403 and 404)
      Coastal Zone Management Act (15 CFR 930)
      OSHA Health and Safety Requirements (29 CFR 1910 and 1926)
 10.3   Cost Effectiveness

 EPA's selected response action will provide adequate protection of human health and the
 environment at an estimated cost of $7,743,000. The soil component of EPA's selected
 remedy involves the excavation and off-site disposal of 6,080 tons of impacted soil.  EPA's
 selected soil remedy provides an estimated residual risk, or post-remediation risk of 1 x
 1Q-6 at an estimated cost of $2,280,000.

 The groundwater/NAPL component  addresses source removal (NAPLs) for  both the
 shallow and intermediate groundwater units and dissolved phase plume in the shallow
 groundwater unit at an estimated present  worth cost of $5,463,000. The decision to
 incorporate phytoremediation as part of the groundwater treatment technology may provide
 a substantial reduction in this estimated costs, should this technology prove effective, and
 thereby enhance cost effectiveness.

-------
                                                              Record of Decision
                                                                September 1998
                                                             	PageS6
Based upon the above discussion, EPA has determined that the selected remedy provides
protectiveness that is proportionate to its costs and represents a reasonable value for the
money that will be spent.
10.4  Utilization of Permanent Solutions and Alternative Treatment Technologies or
      Resource Recovery Technologies to the Maximum Extent Practicable

EPA has determined that the selected remedy represents the maximum extent to which
permanent solutions and treatment technologies can be utilized in a practicable manner
for the response action at the Calhoun Park Site. Of those alternatives that are protective
of human health and the environment and comply with ARARs,  EPA has determined that
this selected remedy provides the best balance in terms of the five balancing criteria, while
also considering the statutory preference for treatment as  a principal element and
considering state/community acceptance. The implementation of this remedy is also
expected to result  in positive economical and environmental benefits to the local
community.

The groundwater/NAPL remedy component involves technologies that recover NAPL to
the maximum  extent practicable  at the  three source areas on-site.  All  recovered
groundwater will  be treated to. permanently  reduce  contaminant concentrations to
appropriate standards.   This component also selects  innovative phytoremediation
technology as a  supplemental remedy for  restoration  and  hydraulic- control of the
dissolved-phase aqueous contaminant plumes downgradient of NAPL source areas.
 10.5   Preference for Treatment as a Principal Element

 EPA's selected remedy will fulfill the preference for treatment as a principal element
 through the recovery and treatment of impacted groundwater and NAPL. Furthermore, this
 response action incorporates phytoremediation as an innovative groundwater treatment
 in conjunction with an extraction well/recovery system.

-------
       APPENDIX A
STATE CONCURRENCE LETTER

-------
     09/30/08  WED  14:16  FAi  803 238  3302
                                                         SPRINCMAID  BEACH
                                                                                     0)002
D      H     E     C
 PROMOTE PROTECT  PROSPER
 2600 Bull Street
 Columbia. SC 29201-1708
                                                          September 30, 1998
 COMMISSIONER:
        . BfytM
.BOARD:
 lohnHBmritt
 Chiirmm

 WiBi.jnM.HulI. Jr.. MD
 Vice Chairman

 Refer Le«k», Jr.
 Secretary

 MutB. Kcot

 Cy*di C. MooeUer

 Brian K. Smith

 Rodney L. Onndy
John H. Hanldnaon, Jr.
Regional Administrator
U.S. EPA, Region IV
61ForsyihSt.,SW
Atlanta. GA 30303

RE:    Calhoun Park Superfund Site - Record of Decision

Dear Mr. Haokinson:

The Department has reviewed and concurs with all parts of the revised Record of Decision
(ROD) dated September 23,  1998  for the Calhoun Park located in Charleston, S.C. In
concurring with this ROD, the South Carolina Department of Health and Environment
Control (SCDHEC) does not waive any right or authority it may have under federal or slate
law. SCDHEC reserves any right or authority it may have to require corrective action in
accordance with the South Carolina Pollution Control Act. These rights include, but are not
limited to, the right to insure that all necessary permits are obtained, all clean-up goals and
criteria are met, and to take separate action in the event clean-up goals and criteria are not
met Nothing in the concurrence shall preclude SCDHEC from exercising any administrative,
legal and equitable remedies available to require additional response actions in the event that:
OXa) previously unknown or undetected conditions arise at the site, or (b) SCDHEC receives
additional information not previously  available concerning the premises upon which SCDHEC
relied in concurring with the selected alternative; and (2) me implementation of the remedial
alternative selected in the ROD is no longer protective of public health and the environment

SCDHEC concurs with the selected alternative for contaminated soils consisting of excavation
and disposal in a permitted landfill followed by the backfilling of the excavated areas with
clean fill. SCDHEC concurs with the selected groundwater alternative consisting of source
removal of NAPLs from both the shallow and intermediate aquifer and treatment of the
groundwater plume  through a combination of recovery  wells/filtration system and
Phytoremedianon.
                                                                               Sincerely,
                                                                               R. Lewis Shaw, P.E.
                                                                               Deputy Commissioner
                                                                               Environmental Quality Control
                           cc:     Hartsill Truesdale .
                                   Keith Lindler
                                   Wayne Fanning, Trident EQC
                                   Gary Stewart
                u r Aonr IN A nRPARTMF. NTOFHEALTH AND ENVIRON MENTAL CONTROL

-------
      APPENDIX B
RESPONSIVENESS SUMMARY

-------
                        RESPONSIVENESS SUMMARY
                     CALHOUN PARK SUPERFUND SITE
                      CHARLESTON, SOUTH CAROLINA
1     Comment: Correspondence from the South Carolina Department of Health &
      Environmental Controls Office of Ocean and Coastal Resource Management
      (OCRM) group dated March 26, 1998, requests that EPA comply with the
      Federal Consistency provisions of the Coastal Zone Management Act,  15 CFR
      930.

      Response: All activities will be performed to meet the substantive requirements
      for State of South Carolina's OOCRM for activities occurring in coastal zone.
      Such activities would include, but not necessarily be limited to, the management
      of surface water run-off during remedial actions. The OOCRM will receive work
      plans associated with these activities for comment. Letter sent to OOCRM
      reflecting this response.

2.     Comment: Dr. Arthur LaBruce writes to suggest the possible use of a calcium
      sulfate product produced by E&C Williams, Inc. as a possible clean up option.

      Response: The referenced product identified as "Enthrall" acts primarily by
      converting inorganic oxides to less reactive sulfides and has shown some
      usefulness in treating inorganic contaminated soils and wastewater. Enthrall's
      effectiveness in treating organic contamination, or more specifically the
      polyaromatic hydrocarbons associated with the coal tar waste present at the
      Calhoun Park site,  has not been tested. Enthrall's most likely application here
      could be reducing the  RCRA characteristic nature of the inorganic waste
      contaminants (i.e. leachability) so that the waste could be placed in a subtitle "D"
      landfill instead of a subtitle "C" landfill. As such the parties performing the
      cleanup (SCE&G) may pursue such a product's usefulness at that time.

3     Comment: Fluor Daniel GTI, on behalf of SCE&G, submitted a letter and
      attachments dated May 14 ,1998, recommending phytoremediation over pump &
      treatment. The general points to be derived from these  submittals suggest that
      a) when pump & treatment technology is implemented at sites where DNAPL is
      present, the cleanup levels are seldom attained,  and b) phytoremediation will
      both contain and treat the site specific contaminants of concern present on
      groundwater.

      Response: With regards to the first point, DNAPL sites  are particularly difficult to
      remediate regardless of any technology used. This is a substantial point yet one
      which was not considered within SCE&Gs letter or attachments. Td address the
      technical  issue surrounding the remediation of sites containing NAPL

-------
contamination, EPA published Directive 9234.2-25 titled Guidance for Evaluating
the Technical Impracticability of Ground-Water Restoration, September 1993.
The presence of DNAPL at the Calhoun Park site will likely result in a Tl
approach which is precisely the reason EPA has pursued the threefold
groundwater objective of 1) Removal or treatment of NAPL to the maximum
extent practicable, 2) Containment of non-restorable source areas; and 3)
Restoration of the aqueous plume. To this end pump & treatment would be
effective in meeting these objectives over a broad range of sites.
The groundwater objectives as listed above also become crucial in evaluating
the manner in which any cleanup technology will be implemented at such sites.
Any design document would therefore be based upon these objectives and
should discuss specific components required for a Tl evaluation including:
identification of the specific ARARs or media cleanup standards for which Tl
determinations are sought, spatial  area over which the Tl decision will apply,
and a conceptual site model.

Because of the lack of actual site data supporting the effectiveness of
phytoremediation on PAH contaminated groundwater, the discussions have
been limited to theoretical evaluations. These evaluations covered groundwater
fFbw conditions, depth of aquifer, contaminant concentrations, and general
research papers on phytoremediation on soils, rather than groundwater. A vital
area of concern which has been repeatedly mentioned by EPA but not
addressed in any deliverable is the effectiveness of phytoremediation in treating
all site specific contaminants of concern. Research does indicate that
phytoremediation can successfully treat groundwater contaminated with BTEX
and  some inorganic compounds under controlled conditions, however there is
no research data proving that phytoremediation is effective on PAH
contaminated groundwater, nor on its effectiveness through the use of trees.

In effect SCE&G is assuming that phytoremediation will remediate groundwater
because of research by Reilley (1996) indicates that plants were effective in
reducing concentrations of anthracene and pyrene in soil. A  study using grasses
to treat two non-carcinogenic PAH compounds in soils would not have any
substantive application in predicting the effectiveness of trees on groundwater
contaminated with carcinogenic PAHs. SCE&G's assumption that trees would be
effective at this site because grasses were effective on another site is
unfounded. There is also the additional assumption relating a method that works
for soils as being applicable to groundwater. Such an assumption is also
unfounded. In effect that which works on soil does not necessarily work on
groundwater and that which works through grasses does not necessarily work
through trees. Overall the proposal is speculative and therefore are not a solid
basis for acceptance as a sole source remedy.

-------
Another problematic issue is also mentioned within Reilley's research yet
omitted from the summary offered by SCE&G. The original research paper notes
that "Although there is little evidence that microbial growth can be sustained in
presence of PAHs with four or more rings as a sole substrate, they may be
degraded by cometabolism". Here it is unclear under what conditions for which
these higher ring compounds could be expected to degrade if at all. This point
simply brings to light yet another unanswered question relating to predicting the
possible effectiveness of phytoremediation.
The issue of achieving hydrological containment for the groundwater plume has
not been adequately demonstrated for phytoremediation, either by theoretical or
empirical means. While a given number of trees can be estimated to remove a
predicted volume of water from the vados zone, containing the areal extent of
the plume will likely be compromised due to the limited available surface area for
planting trees relative to the location of the plume. In other words, while we may
be theoretically able to plant enough trees, the ability to  place them in strategic
locations would be compromised due to existing and/or planned future use of the
site.

In summary EPA would not endorsed phytoremediation as a sole source remedy
for groundwater at this site based on the research information presented to date.
This does not imply that phytoremediation is without merit, but simply that  the
weight of evidence is not such that EPA is willing to implement this technology
as a sole source remedy for this particular site. For these reasons the proposed
plan and the Record of Decision includes pump & treatment in conjunction with
phytoremediation. The pump & treatment would be installed first to address
early cleanup action. Meanwhile a phytoremediation system would be
established and its effect on contamination monitored. If phytoremediation
proves effective in meeting the cleanup strategy,  the pump & treatment system
could be replaced by phytoremediation at that time.

-------
       APPENDIX C
PUBLIC MEETING TRANSCRIPT

-------
 1

 2

 3

 4

 5

 6

 7

 8

 9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25
IN RE:  CALHOUN  PARK  AREA

SUPERFUND SITE
PUBLIC MEETING

DATE :

TIME:


LOCATION:




TAKEN BY:

REPORTED BY:
                            M A 1
                           i I -4 r\ L
                 March  16,  1998

                 7:00 PM
                 Charleston  Public Works Building
                 103  St.  Philip Street
                 Charleston,  SC

                 EPA

                 LORA L.  McDANIEL,
                 Registered  Professional Reporter
Computer-Aided Transcription  By:

        A. WILLIAM ROBERTS, JR.,  & ASSOCIATES
Charleston, SC
(803) 722-8414

Greenville, SC
(864) 234-7030
                                    Columbia, SC
                                    (803)  731-5224

                                    Charlotte, NC
                                    (704)  573-3919
              A. WILLIAM  ROBERTS,  JR.  & ASSOCIATES

-------
 1   APPEARANCES:

 2
                  TERRY TANNER, EPA  Project  Manager
 3                CYNTHIA PEURIFOY,  EPA  Community
                   Involvement Coordinator
 4

 5   CONCERNED CITIZENS:

 6                BARBARA JOHNSON
                  PAUL CAMPBELL
 7                RICK RICHTER
                  PAT McGOWEN
 8                LORRAINE PERRY
                  DIANE OLDSTON
 9             '   ROBERT WELLS
                  ALLEN COHEN
10                CRAIG ZELLER

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25
               A.  WILLIAM ROBERTS,  JR.  &  ASSOCIATES

-------
 1               MR. TANNER:  Folks, if I can have your



 2   attention.  On behalf of the Environmental Protection



 3   Agency, I would like to welcome you-all to the



 4   meeting here tonight on the Calhoun Park Superfund



 5   Site.  We've got a couple of things that we are  going



 6   to be talking about tonight.  And I've got at least



 7   three objectives that I hope we can cover tonight



 8   during the course of this meeting; the first is  an



 9   introduction to the environmental district of this



10   particular area of the site.  I've got some overheads



11   on the slide; I am going to show you that a little



12   bit later on.



13               We are also going to talk about



14   contamination and the risk posed by that



15   contamination as well as a proposed cleanup method



16   for this site.  Before I go any further, I would like



17   to introduce to you another important part of this



18   team, and that is a lady by the name of Cynthia



19   Peurifoy.



20               Cynthia is our community relations



21   coordinator.  She makes sure all of us bonehead



22   scientists with our slide rulers communicate a little



23   bit better for folks who don't do this every day.



24   She does a very good job.



25               Cynthia, would you like to say a few
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
 1   words?



 2                MS.  PEURIFOY:   Sure,  I  will just stand



 3   over  here,  if  you don't mind.   I  want to welcome



 4   you-all  to  this  proposed plan  meeting and encourage



 5   you to participate,  ask questions and be a part of



 6   this  decision-making process.   As Terry has told you,



 7   he's  got a  lot to cover,  and we want you to know this



 8   is an extended comment  period.   We've got 60 days



 9   starting today to get your input  in.



10                So take  a part of  this  process.  We have



11   an information repository  set  up  at the John Dart



12   Library.  There  you.will  find  the administrative



13   records,  which has all  the documentation that led to



14   the decisions  that's being made or  proposed here



15   tonight.  So take some  time and go  by and take a look



16   at some  of  those documents.



17                I  also want to tell you we have an 800



18   number;  it's listed  there  in the  fact sheet.  Call



19   them.  If you  go through  something, if you have a



20   question .or concern,  feel  free  to call and ask a



21   question.   We  are available for that; Terry and I




22   both  can be reached  at  that number.



23                We have  a court reporter here tonight.



24   When  you speak tonight,  please  identify yourself so



25   that  she can record  what you are  saying and we can
               A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
 1   have a good record of this because part  of  this



 2   process is to respond to your questions  and concerns.



 3   With that, I think that's all I  have  to  say;  Terry,



 4   thanks.



 5               MR. TANNER:  Thank you, Cynthia.   I  will



 6   use a  slide here to give you a quick  view of  the site



 7   we are talking about tonight.  The site  consists of



 8   the current -- I will describe things  in its  current



 9   context.  There's an electrical  substation  located at



10   the intersection of Charlotte Street  and Concord



11   Street.  This is also adjacent to the  old ballpark.



12   Some of you might have seen it.  It's  rather  grown up



13   and abandoned, but I believe there still is a ball



14   diamond here and a backstop.



15               Directly across the  street we have what



16   used to be the Ansonborough Homes in  this area here.



17   These were recently demolished,  I think,  in the  past



18   seven or eight months ago; therefore,  none  of these



19   structures exist.  We also have, as part of the  site,



20   as an example, the former Detyen's property,  Dockside



21   Condominiums, as well as private land  here  owned by



22   the Park Service.



23               If you folks have been keeping  up with



24   the news,  you've probably heard  a lot  about the



25   aquarium that they are building  in Charleston; you
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
 1   almost  have  to  live  under  a  rock  not  to.   The



 2   aquarium  itself  is  located here.   It's  a  source of a



 3   lot of  ongoing  construction  activities.   We've also



 4   got in  this  area  Luden's Marine and  Supply.   It's a



 5   rather  old building.   They are an outdoor/fishing



 6   supply  outfitter.



 7                This, in  essence, is  one  of  the  sites we




 8   are going to talk about.   This was a  very active site



 9   over the  last 100 years.   Some of the industries that



10   have operated within  this  plot that  we  know  about are



11   an old  gas manufacturing plant used  to  supply town



12   gas to  the City  of Charleston by  the  burning of coal;



13   we will get  into  that  a little bit more  when we start



14   talking about contamination.



15                We  also  had, at  one time,  a  turpentine



16   plant located here.   You can see  the  outline of where



17   the building used to  be.   We have in  this area -- let



18   me get  my bearings.   We have an old  Navy  shipyard



19   that was  very active  during  World War II  that



20   serviced  minesweepers, as  I  understand  it.   And those



21   are the big  ones.



22                Any  questions  so far? I  want to



23   encourage you to  ask  questions as this  goes  on.  I



24   don't want this  to turn into some formalized,



25   complicated  thing.
              A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
 1               MS. JOHNSON:  Could you point to  the  site




 2   that's now the Maritime Center and say that's  part  of




 3   it?



 4               MR. TANNER:  The Maritime Center  would



 5   actually be located, I think, further down here.



 6               UNIDENTIFIED SPEAKER:  Right where your



 7   hand is.



 8               MS. JOHNSON:  That's not part of  it?



 9               MR. TANNER:  No, ma'am.  I think  there



10   has been some environmental sampling that has  gone  on



11   at the Maritime Center but not as part of this



12   project.



13               What we found in doing our investigation



14   at this site, and you can see -- perhaps you  can  see



15   it a little better if I dim these lights slightly;



16   see what happens.  That's a little bit better.



17               We literally peppered the site with



18   sampling locations.  All of these places where you



19   see triangles and circles with Xs are essentially



20   sampling points.  And what we found as we went out



21   and sampled this area was a large volume of a



22   particular group of compounds, which I will



23   abbreviate, polyaromatic hydrocarbons.



24               And we also found another group;



25   Benzene,  toluene, ethene and xylene.  Now, both of
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                          8
 1   these groups  -- and I will talk about these



 2   interchangeably tonight -- are very common



 3   contaminants  from old manufacturing gas  plants.



 4               What the plant used to do --  and  the




 5   plant actually operated on this portion  of the



 6   property here -- is they would take coal  out  of  coal



 7   mines, ship it in by rail, which you can  see  here is



 8   part of an old rail strip.  They would run the  coal



 9   into this large container, remove the oxygen  and  heat




10   the coal.



11               Now, as part of that process, w.hat  it



12   does is it extracts this very flammable  gas 'out  of



13   the coal itself.  And because you are doing  it  in the



14   absence of oxygen, it doesn't actually blow  up  on



15   you.  What it produces is, again, a very  flammable



16   gas, which was distributed throughout the Charleston



17   area for use  of the gas line.



18               Now, as an unfortunate byproduct  of  this



19   process, it also produced a lot of waste  that,  again,



20   we call PAHs; polyaromatic hydrocarbons.  They  are



21   essentially a large family of carbon type materials



22   that runs from the range of being very soupy-like



23   water all the way to the thick, heavier  substances



24   you see in road tar.  We have a wide range of



25   viscosity, especially with this material, as  well as
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
 1   varying compositions of contaminants  found within



 2   this group of contamination.



 3               What we've seen  --  and  I  will  focus in a



 4   little bit -- is that when we took  our  samples, not




 5   surprisingly enough, most of the  contamination that



 6   we noted with regard to soils start  there, was along



 7   this area here and here and  here.



 8               What we also found  when  we  looked at the



 9   groundwater samples is, not  surprisingly enough, with



.10   groundwater flow this way, we found  a large dissolved



11   plume-contaminated groundwater, and  it  goes right



12   through this drawing, something like  this, which is



13   not surprising given the sources  of  contamination.



14               This will give you  a  little  bit better



15   drawing of what happens environmentally  at the site.



16   Initially, you have your release  of  contamination



17   here.  And as it is continually injected into the



18   soil -- poured, dumped, however it may  be  -- it



19   eventually begins to saturate,  and  it flows down



20   into -- you can almost read  that.  What  happens, the



21   contamination comes in contact  with  the  soil, goes




22   right on down meantime into  the groundwater table.



23               If you can imagine  this  as  being a solid



24   table of soil, from here to  here  where  the clay ends



25   down here to contain the groundwater, and  then here
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         10
 1   you have  a  layer  of  water which is  perched upon the



 2   ground, perched upon the  clay,  and  on top of that you



 3   have nonsaturated soils.



 4               What  happens  in sites  just like this is



 5   that the  contamination  comes in contact with the soil



 6   and continues  to  seep down into the soil.  It



 7   eventually  comes  into contact with  the groundwater.



 8   When it does,  you get --  in this direction, you have



 9   clean groundwater; here,  as it  passes through the



10   soil, which is ladened  with contamination, you



11   develop contaminated groundwater;  thus you end up



12   with a plume like this, much like  you see at the



13   site.



14               Here  is  an  actual drawing of the



15   contamination.  It's something  like this.  Again, you



16   can see where  it's corresponding to what we believe



17   to be the source  of  the contamination here.



18               MS. JOHNSON:   How far down is the plume?



19   How far below  the ground  level  is  the plume?




20               MR. TANNER:   There's actually two



21   instances where I believe the contamination is down



22   as deep as  50, 60 foot.   Let me ask the drawers,  the



23   experts.  How  far down  would you say that is?  Do you




24   happen to recall  how deep that  groundwater



25   contamination  is;  just  in that  one  area?
              A. WILLIAM ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         11
 1               MS. CANOVA:   I  think your  estimate  is



 2   close enough.



 3               MR. TANNER:   Okay.  What we  actually have



 4   at this site is a couple  of  things  going on  with



 5   regards to the soil.   I hope  to shed some light on



 6   this issue.  We have/  as  we  mentioned  before,  clay



 7   here.  And this particular  site, the clay layer



 8   terminates at about -- this  is land surface.   We've



 9   got this clay layer down, I  think it starts  about  12



10   foot more or less, and it terminates down --  it may



11   run about seven to ten foot.



12               And we have another layer  of soil  down



13   here.  And then below  that,  even deeper,  another



.14   layer of clay.   What is happening at the site  is



15   we've got not only the contamination,  which  is  down



16   and is perched on top  of  this clay  layer,  we  also



17   have at one point on the  site a hole.  And the  clay



18   begins itself where initial  contamination has  come --



19   and contamination has  come  and now  it's  down  into



20   this deeper layer as well.




21               MS. JOHNSON:  How fast  is  that moving,



22   can you tell, the plume?  Is  it getting  bigger?  Is



23   it moving in one direction?




24               MR. TANNER:   Well, we can  tell that it is



25   moving simply by the earlier  figure where you  can
              A. WILLIAM ROBERTS, JR.  & ASSOCIATES

-------
                                                         12
  1    look  at the groundwater.   If this was the original



  2    source, it spread at least this far.   We can tell



  3    that  from the wells that  we have monitoring it.



  4                In summation,  what we have is both soil



  5    contamination and groundwater contamination at this



  6    site.   Are there any questions, at least on this



  7    point,  before we move on  and talk about what we



  8    looked  at in cleaning up  the site?



  9                UNIDENTIFIED  SPEAKER:  Quick question.



.10                MR.  TANNER:   Yes.



11                UNIDENTIFIED  SPEAKER:  Is there



12    separation between the soil contamination and the



13    groundwater based on PAHs  and BTEX?  Is one more



14    permeable than the other?



15                MR.  TANNER:   Well, in general,  the BTEXs



16    tend  to enter into the groundwater a  little more



17    readily than the PAHs, but we do have both.  On this



18    drawing here/ I  believe this is actually an outline



19    of  the/ I think, the benzene.



20                If you were to look at the PAH



21    contamination, because it  doesn't absorb in the water



22    quite as readily as the BTEX, we've got PAH; it's



23    looking something like --  little different



24    concentrations -- something like this, and  you may



25    have  a  little bit right there, much like that.
               A.  WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         13
 1               THE COURT REPORTER:  Please  state  your



 2   name.



 3               MR. CAMPBELL:  My  name  is  Paul  Campbell,



 4   I'm with the College of Charleston  graduate program.



 5   So a majority of the groundwater contamination is



 6   going to be cleaned up?



 7               MR. TANNER:  Yes.

  ""^-.^^
  \  -/
 8               MR. CAMPBELL:  BTEXs are as  much as 50



 9   feet?



10               MR. TANNER:  I would say that  the



11   majority of the size of the plume is certainly BTEX;



12   at least to the further extent.  BTEX  has  migrated



13   faster and further than PAHs.



14               Yes.



15               MR. RICHTER:  Rick Richter,  Trident EQC



16   here in Charleston with DHEC.  How  is  the  seepage  on



17   Charlotte Street going to fit  into  the overall



18   picture?  Have you-all been able to tie  that in yet?



19   Do you have seepage going into the  harbor  down there?



20               MR. TANNER:  Yes, we have.   That's one



21   thing that I will touch on.  I will go ahead and do



22   that now.  About six months ago, we found,  to  give



23   you a reference point -- this  is, again, where the



24   old gas plant and current site of the  electrical



25   substation is now.  This is the Cooper River.
              A. WILLIAM ROBERTS, JR.  & ASSOCIATES

-------
                                                         14
 1               As  I was  saying  earlier,  about  six  months



 2   ago we noticed  that there was  a  sheen here  on  the



 3   river.  We went back  and traced  the  source  to  a



 4.   seepage, an outbreak.   Along the shoreline  here were




 5   a series of hairline  cracks.   It's probably not the



 6   correct technical term; it's close enough.



 7               Throughout  these cracks,  coal tar  was



 8   found discharging.  The majority of  it  appears  to be



 9   heavier than water; therefore, it's  flowing down into



10   the sediment.   However, a portion of  it is  floating



11   on the surface  and can  be observed as a sheen  on the



12   water itself.



13               Now, we thought  at the time that we had,



14   at least, most  of the contamination  identified.   I'm



15   beginning to feel like  Brier Rabbit  in  a tar patch.



16   What we discovered was  there's some  additional  source



17   area that is feeding  these seeps that appears  to be



18   coming from the gas holder itself.   And this issue,



19   which will not  be covered as part of  the proposed



20   plan, is under  investigation.



21               And when  I  say under investigation,  I



22   have been working with  the gas company,  and they have



23   agreed to go in and take some  type of interim  action,



24   stop this flow  while  we go on  with the  normal



25   process of the  rest of  the site  itself.
              A. WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         15
 1               MS. JOHNSON:  Is that green  line  in  front



 2   of the Columbus Street terminal site?   Is  that where



 3   that is?



 4               MR. TANNER:  Are you talking about the



 5   Ports Authority terminal?  Is that  the  same?



 6               MS. JOHNSON:  Yes.



 7               MR. TANNER:  Yes, it is.  Actually,  the



 8   large cement structures themselves  would start



 9   about -- this is not, of course, to scale.  This  is



10   the street, and Charlotte Street terminates here.



11   The seeps are right along this area, feeding  out  here



12   and the Ports Authority, the actual large  pier



13   itself, starts here.



14               MS. JOHNSON:  Is that why Charlotte



15   Street is closed off now at that point?



16               UNIDENTIFIED SPEAKER:   No,  that's



17   construction.



18               MR. TANNER:  Yes, I believe they  are



19   actually storing -- there is a current, I  think,



20   fence and has been a fence all along here.  It's



21   actually preventing access to that, but recently  due



22   to the construction activities you  mentioned, they



23   closed this off and are storing equipment  back there




24   at this time.  I will just leave that up there so we



25   can continue to reference it.
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         16
 1                Let's  talk a  little  bit  about -- we've



 2   covered  the  history,  the  contamination and the risk.



 3   What  we  do  once we generate all  these  sampling data



 4   is go back  and say,  well,  what kind  of threat is this



 5   to the public?  What  does  it mean?   What do all these



 6   numbers  mean?



 7                We take  the numbers  and  through



 8   mathematical modeling we  determine,  statistically,



 9   what  the risk  is to  people living  in the area.  In



10   this  site,  we  looked  at a  couple of  different



11   scenarios.   We said,  well,  if you  have people living



12   on the site  such as  Dockside Condominiums and



13   Ansonborough Homes,  there  were children out there



14   playing,  would there  be a  risk to  them?



15                We also  looked at commercial construction



16   workers.  We said, well,  if you've got this area



17   covered  in  commercial property and you have



18   construction workers  out  there dealing in soil every



19   day,  what is the actual risk to  them?   And we also



20   looked at the  trespassers.   What is  the likelihood of



21   people just  wandering up  and coming  in contact with




22   the soil?  What's  the risk to them?



23                And what  we found is,  in looking at all



24   of those possible  situations, the  more probable use



25   of this  land was commercial.  And  we said, given
               A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         17
 1   that, what is the risk to the  construction  worker



 2   because he is the most likely  person  that's  going to



 3   come into contact with contaminated soils?   So  what



 4   we did is crunch the numbers on  that  and  came up with



 5   these areas here.



 6               Let me see if I can  put this  on.  What we



 7   found out after all our foo.t and  ticking  was that



 8   these areas here — and here you  can  see  them



 9   slightly shaded; and if you have  the  flyer  that was



10   sent in the mail, the same figure  that's  on  that back



11   page -- you will see that these  areas are the ones



12   that posed the greatest risk on  the site.   Now,  this



13   is with regards to soil.  We will  get into



14   groundwater in a minute.  Any  questions?



15               UNIDENTIFIED SPEAKER:  Which  ones are you



16   talking about, soil?



17               MR. TANNER:  The soils, yes.  Let me get



18   this up a little bit higher.   See  the shaded area



19   here?



20               UNIDENTIFIED SPEAKER:  Looks  just like in



21   the pamphlet.



22               MR. TANNER:  It's  here and here.



23               UNIDENTIFIED SPEAKER:  Thank  you.



24               MR. TANNER:  And for groundwater, as



25   I've shown you earlier on this figure, the
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                          18
 1    contaminated groundwater that will have to be



 2    addressed is essentially something like this here.



 3                MS.  JOHNSON:   Is  this  including the



 4    groundwater contamination map in the handout?  Can



 5    you  print it up?  It's  a nice companion piece to this



 6    soil.   That's really nice.



 7                MR.  TANNER:   Yes, I  can do that.  Would



 8    you  like  a particular copy of that?



 9                MS.  JOHNSON:   Yes,  this one;  at your



10    convenience.  Yes,  that  would be nice.



11                MR.  TANNER:   Let's  quickly review;



12    history,  contamination,  risk, proposed cleanup



13    methods .



14                Are  there any questions today before I



15    move  into those  areas?



16                MS.  JOHNSON:   Groundwater risk; a little



17    bit  more  about that.   Is  there  anything more to say



18    about  that,  let's  put it  that way?



19                MR.  TANNER:   Well,  we  actually took the




20    numbers and ran  a  risk  assessment  on the  groundwater,



21    and  no surprise, we  found out that the groundwater



22    does  pose a risk.   For  cleanup  numbers -- well, I'll



23    get  into  cleanup numbers  in a bit.   Yes,  to answer




24    your  question.   Yes,  the  groundwater numbers pose a



25    risk.
               A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         19
 1               MS. JOHNSON:   I wi'll  probably  ask a



 2   definite question sometime later  on,  how  is  that risk



 3   modified by the tendency to flood  in  the  area,  lot of



 4   standing water certain times of the year.  Does that



 5   change the risk at all, make it a  greater  risk  at



 6   certain times during the flooding  period,  et  cetera?



 7               MR. TANNER:  What  it  would  tend  to  do is



 8   actually flush the contaminated groundwater  out of



 9   the more concentrated areas into  lower  concentrated



10   areas.  Use this figure here.  Anytime  you have rain



11   or flooding, it would percolate down  through  the soil



12   and increase the amount of water  coming into  contact



13   with the contaminated material.   And  the groundwater



14   table would actually rise.



15               Now, this area is  a little  more



16   complicated than that because  you've  got tidal.



17   That's a very simplistic picture.



18               On most of these sites, Superfund sites



19   in general, we usually have a  wide choice  of  cleanup



20   options available to us.  This site is  a little



21   unique.  In fact, the group of PAHs are unique  in



22   that the treatment options we  have available  to us



23   are very limited.  These compounds are  very



24   persistent, very hard to neutralize or  destroy



25   chemically, and there's just not  a lot  of  options,
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         20
 1   again, that we  can do with  them  when  they are in the



 2   soil.



 3               The  options that  we  did  look  into for



 4   this site include a couple  of  things.   We looked at



 5   capping it; that is coming  back  here  and  placing some



 6   type of permeable cap over  the material  itself.   As



 7   you can imagine, it might be  somewhat  effective  for



 8   the portion of  the soil above  the  groundwater but



 9   doesn't do much  for the portion  below  it.



10               We  also looked  at  bioremediation.   That's



11   an issue that's  been getting  more  and  more press



12   lately.  Bioremediation is  where we  actually take



13   bugs, or bacteria we should call them,  expose them to



14   the soil, and if conditions are  favorable to those



15   bugs, they will  actually help  to break  down the



16   contaminants.



17               We  looked at thermal destruction/  which



18   is a fancy term  for burning the  soil.   And we looked



19   at landfill; that is literally excavating the soil,



20   getting it up from this area  and putting  it in a



21   containerized cell to control  the  landfill.



22               With regards to the  groundwater portion



23   of this, we looked at several  different choices; one




24   we looked at, deed restrictions, which  is very common



25   to do; simply attach deeds  to  the  land  saying don't
              A. WILLIAM ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         21
  1   drink the water.



  2               We looked  at  phytoremediation.   Again,



  3   that's a relatively new technology  where plants  are



  4   used to actually help  treat  the  groundwater by



  5   infiltration.  Roots come  down,  and through several



  6   different means, are actually  able  to  provide some



  7   effect in treating this groundwater.



  8               There's a  couple different  ways it works.



  9   The plants in some instances with some  contamination



.10   are able to actually absorb  and  concentrate the



11   contamination into the root  system  and  the  plant



12   bodies themselves.



13               There's another  mechanism where you  also



14   have bacteria that tends  to  colonize the ground  roots



15   themselves.  In some instances,  that's  very effective



16   on contaminants.  It can  be  very effective  if the



17   bugs do tend to like that  contamination and can



18   digest it; again, a very  simplistic, crude



19   explanation of phytoremediation.



20               We looked  at  natural attenuation;  that  is



21   what would happen if we left the site as is and  what



22   would happen to it.  Under some  very controlled



23   conditions, natural attenuation  can be  an effective



24   remedy.   Again, there  are  some factors  that really



25   have to be balanced very carefully  in order for  it  to
              A. WILLIAM ROBERTS, JR.  & ASSOCIATES

-------
                                                         22
 1   work.




 2                What  else  did  we  look  at?   We looked at,



 3   again,  bioremediation,  just  like soil  except this



 4   time  it will  be groundwater;  looking  for  bugs that



 5   can actually  be introduced to  the  groundwater and



 6   that  live  in  the  soil  or can  live  in  this particular



 7   type  of soil  and  might  potentially be  effective  in



 8   breaking down  a contamination.



 9               We also  looked at  a very  standard



10   practice of pump  and treat where a series of recovery



11   wells are  installed; this  being the well  and slots in



12   the well itself.  Groundwater  enters  the  well,  is



13   pumped  up  and  on  to  some type  of treatment process --



14   it's  a  filtering  mechanism —  and  then sent to



15   usually the sewer or,  depending upon  how  clean  it is,




16   can even be  introduced  back  into the  streams.



17               Questions,  comments about  the options?



18   Yes.



19               MS. OLDSTON:   Diane Oldston with the



20   environmental  science  program, College of Charleston.



21   I have  a question.   Bioremediation, I  understand, is



22   a very  quick  multiplication  of bacteria numbers  that



23   might be effective in  breaking down the network  of



24   contamination  very quickly but if  bioremediation is a



25   very  lengthy  process where the root systems have to
               A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         23
 1   take . . .



 2               MR. TANNER:  Yes, it is.   It actually



 3   involves several seasons for a particular  root  to



 4   establish itself, and, therefore, it's probably not



 5   as quick and a little more difficult  to monitor the



 6   effectiveness because we can't go out  today.



 7               MS. OLDSTON:  What is the  time  line the



 8   EPA is focusing on for the treatment?  Is  there some



 9   sort of time line in which you are hoping  to



10   remediate?



11               MR. TANNER:  As far as actually



12   implementing a strategy, yes, we will  have  that



13   implemented within the next ten to 12  months.   But



14   because, in this instance I am using  the one  for



15   groundwater, you can't get down there  using the



16   existing technology that we have effectively  enough



17   to have the entire area cleaned up in  six  to  12 or



18   eight months, whatever interval that we are choosing,



19   say, for the soils.  What we typically do,  we come



20   in, we can treat the soils relatively  quickly.



21               The groundwater is another issue.



22   Depending upon the technology, it takes much  longer.



23   It may take a period of years before we can make a




24   dent in the contamination level.  That's one  area



25   where  technology is really lagging behind,
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         24
 1   environmentally  speaking.   Once  contamination gets in



 2   the groundwater,  it's  very  difficult to get to and to



 3   treat.   It can  be  done,  but it's very expensive.



 4               MS.  JOHNSON:   I have another question



 5   about the groundwater  remediation processes.   How



 6   does the use configuration  of  these  properties affect



 7   the selective or  the optimum method;  being one method



 8   might be very good  for a  forest  or a meadow but this



 9   is not?



10             .  MR.  TANNER:   Yes,  it does.   The actual



11   use of the property comes  into play  and actually  at



12   two points:  One  is when  we are  trying  to determine



13   how clean should  we clean  this up to;  that is^, what



14   standard should  we  use,  commercial standard,  should



15   we use residential  standards;  and two is, when we've



16   gotten past that  and decided to  actually implement



17   the remedy, how  is  the remedy  going  to  work within



18   the existing conditions.



19               As we  can  see  out  here,  the area  being by



20   and large commercial where  we  are certainly limited



21   to options to put  in place  to  do that.   So it plays a



22   very good part.   Yes.



23               MS.  PERRY:   Lorraine Perry  from MESNE



24   Register.  I have  a question.  You keep saying that



25   this property is  going to be commercial.   My
              A. WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         25
 1   understanding is that a lot of this  property,



 2   especially where the Ansonborough  Homes  was,  is  being



 3   considered for a park.  So that would  seem  to  me that



 4.   the level of cleanup would be different.  And  if you



 5   look at what the city plans for most of  the area,



 6   where Ansonborough is, in back of  Harris  Teeter, in



 7   that whole area, if the Ports Authority  does  leave,



 8   is to combine it to be partially residential  and



 9   partially commercial.



10               MR. TANNER:  Let's look  at the  areas



11   where we have contamination.  Yes, you do bring  up a



12   good point.  There are areas out there now  that  are



13   residential; Dockside Condominiums is  one of J:hem.



14               When we looked at the  risk and  we  were



15   assessing the risk, we knew that the electrical



16   substation here was going to be -- actually,



17   technically would be industrial, but from a risk



18   standpoint, it's the same thing as commercial.



19   There's usually no difference.



20               In this piece of property  here  we  knew



21   there was going to be industrial or  commercial.   We



22   also knew that with regards to the Park  Service



23   property, which is here, that it was also going  to be



24   commercial or industrial.



25               MS. PERRY:  How can that be  commercial
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         26
 1   when you  are  talking  about  an  aquarium,  talking  about



 2   bringing  in umpteen  trillion kids  every  day?   I  mean,



 3   I realize it's  commercial because  it's going  to  be a



 4   business  but  you  closed  this one area  next  to the



 5   gas, SCE&G, where they are  going to  put  a parking



 6   garage where  the  kids play  soccer  because they



 7   couldn't  play there  because it  was too contaminated



 8   so you closed them down;  just  like they  closed the



 9   Ansonborough  Homes down  because it was contaminated.



10   And now the mayor says we are  going  to have a



11   symphony  hall on  there surrounded  by parks  for the



12   children.



13               MR. TANNER:  Okay.   I  think  I can^answer



14   your question.



15               MS. PERRY:   Good.



16               MR. TANNER:  When we went  in and  did the



17   risk assessment,  what we did essentially, we  measured



18   the existing  soil concentration; not only at  the



19   surface,  we also  measured them  down  deeper  as well.




20   What we found was that in these areas, in this group



21   of samples here,  that there was no -- well, I should



22   say that,  in  general, none  of the  soil is pristine;



23   it all has levels of  PAHs.  Again, what  we  found,  it




24   seems to  be concentrated in the area here.



25               Now,  we did  find PAHs  in this area in the
              A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         27
 1   surface soils, but  it was not at  levels  creating  an



 2   unacceptable risk;  that  is, children  could  live  here,



 3   they could play here, they could  go out  and  eat  the



 4   dirt if they want to in  this area, and it is  safe.



 5   What we di'd find out is  that was  not  the case for the



 6   areas here.



 7               Now, going back to your question  of  how



 8   do you say, like, for instance —



 9               MS. PERRY:   The aquarium.



10               MR. TANNER:  Okay, the aquarium  here.   I



11   am losing my train  of thought.



12               What is going to happen -and  the  reason



13   why we are calling  this  commercial at the aquarium



14   is, when we did our first round of sampling,  if  this



15   was the surface soil, we knew that -- well,  it's



16   almost a moot point because these areas  here  from a



17   surface standpoint  are also safe; that is,  kids  can



18   play on this; it's  not a problem.



19               Going out a  little bit further,  even  if



20   it was, this soil will actually be covered,  I think,



21   with a three-foot layer  of additional fill  material



22   for the landscaping.  But I think it's a moot point



23   because, again, these soils do not exceed residential



24   standards.



25               I believe the only case where that
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         28
 1    actually occurred was  on the substation itself.  I



 2    have  some reports here I can quickly check —



 3    hopefully,  I  can quickly check -- to see if they



 4    exceeded in this area  as well.  I don't believe they



 5    did;  I  think  the only  place they actually posed a



 6    threat,  surface soil  samples,  was the actual



 7    electrical  station itself.



 8                Does that  make  sense?



 9                MS. PERRY:   It  makes sense now.  It was a



10    different story at the time they changed it, when



11    they  tore down the homes, threw all  those people out



12    because  it  was too contaminated.  Since.the city



13    bought  the  property,  now it's  no longer contaminated.



14               MR. TANNER:   As I  understand it, the



15    decision to move the  people out of that Ansonborough



16    Homes was based on a  couple of factors:  Potential



17    threat  of contamination  as  well as substandard



18    building practices.   The homes were  in bad shape;



19    there was flooding continually.  I think it was a



20    little  bit  of  both of  those factors  together



21    involved,  but  I am speaking out of school and



22    speaking on behalf of  HUD.




23               MS. PERRY:   Okay.




24               MR.  TANNER:   Other questions?



25               MR.  WELLS:   I am Robert  Wells,
               A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         29
 1   Preservation Society.  I understand the sites  are



 2   contaminated.  Are there any opportunities  to  do



 3   archeological work?  These are sites from the  1800s.



 4   Is there any opportunity at all to monitor  as  you  do



 5   the cleanup; can archeologists work in that



 6   environment or have any input?



 7               MR. TANNER:  I .believe that is  one of  the



 8   requirements of doing actual cleanup actions.   I will



 9   have to go back and check that.  We did a couple of



10   archeological digs across these areas here.  I



11   believe there were two trenches; here and here.  We



12   actually have someone from the Park Service; if you



13   can comment on that, John, from the Park Service;



14   comment on that archeological dig.



15               UNIDENTIFIED SPEAKER:  As part  of  our



16   development, we are a federal agency, we are required



17   to go through what is referred to as the Wother



18   Process.  (Phonetic)  We did archeological work on



19   our sites.  The two excavations that Terry  alluded to




20   were completed back in, I believe it was 1988.  We



21   found no remains of any significant structures



22   there.  And that determination was made in  accordance



23   with the federal guidelines as well as the  state's



24   preservation office.  The only thing that we found on



25   the site that we did do a site documentation for was
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         30
 1   the turpentine  building  located  down  in  the  very



 2   southwest corner  that was remnants  of that particular



 3   site.  It wasn't  found as being  worthy for any



 4   further exploration  in that  area.



 5               MR. TANNER:  Thanks,  John.



 6               Going back to your question,  I think what



 7   you are asking, when we  come  in  and do the actual



 8   soil removal, will we?   I don't  know.   I  will  check.



 9               MR. WELLS:   The  sites have been  occupied



10   since 1867; there may be some very  interesting things



11   in the soil we  would like to  see.



12               MR. TANNER:  If  we were to base  it on - -



13   well, we have an  additional  sampling  grid thaj: goes



14   something like  this  in the area  where we  came  in and



15   did some additional  sampling; as  you  can  see,  we



16   really peppered the  site.  It doesn't mean it's



17   loaded with artifacts; haven't found  anything  yet.



18   In answer to your question,  I don't know.  I will



19   check.



20               MR. WELLS:   How  would we  follow  through



21   with that?  Can you  give me  a call?



22               MR. TANNER:  Yes, I  will  exchange  phone




23   calls.



24               MR. WELLS:   At the end  of the meeting.



25               MR. TANNER:  And we  will  follow  up.
              A. WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         31
 1               MR. WELLS:  Thank you.



 2               MS. JOHNSON:  Before we go  off  on  another



 3   topic, I found the things that you threw  in  in an  ad



 4   hoc way very interesting.  In addition  to the  map



 5   showing the groundwater contamination,  it would be



 6   nice to see the entire site with some markings on  it



 7   as to not only where the contamination  is found but



 8   those sites that are not contaminated so  that  the



 9   whole Calhoun Park picture -- these are not, these



10   are not, these are, these are — all in one  place,



11   that would be nice because it's the information we



12   came here to talk about.



13               MR. TANNER:  I agree.  These drawings  are



14   very piecemeal.  Prior to the conclusion, I  will get



15   some type of figure that shows the study area  in a



16   much more presentable manner rather than what  we are



17   seeing now because, obviously, the site is now



18   expanding off of here.



19               MS. JOHNSON:  That's right.  Thank you.




20               MR. TANNER:  Administratively what we



21   will do as part of what we are required by law is,



22   essentially, make sure that we keep you folks



23   up-to-date on what we do know and what we are



24   proposing for those areas that we do know about.



25               I will digress a little bit before  I get
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         32
 1   to  the  last method.   As part of EPAs process, we work



 2   with  the  community.   What we do is we go through an



 3   outline much like this, come to the public and say,



 4   this  is the contamination, this is what we propose to



 5   do .



 6                Unless it is an emergency action, we tend



 7   to  go through steps  like that and make sure that you



 8   folks stay involved;  you know what we are doing.  We



 9   are not out there doing something that you don't know



10   about.



11                Let's go  into this last item and then we



12   will  just open up the meeting to general cojnments or



13   feedback  or whatever.  In looking at all of 'the



14   possible  options, both the cleanup of soils and the



15   groundwater and something which I've neglected to



16   mention,  which is this dark pool of stuff that's



17   sitting down here that is in these handouts.  What we



18   are proposing to do  is three things.



19                With regards to the soils,  after



20   considering the entire universe of options, we are



21   proposing to excavate the soils, take them to a



22   controlled landfill.



23                With regards to the contaminated



24   groundwater,  we are actually trying a two-fold



25   approach:   One is the standard pump and treat.  We
               A.  WILLIAM ROBERTS,  JR.  & ASSOCIATES

-------
                                                         33
 1   are  also  going  to  work  as  best  we  can  with



 2   phytoremediation in  with that.   We  are going  to  use



 3   essentially  the pump and treat  as  the  frontline



 4   treatment.



 5                MS. JOHNSON:   Is  that  source  removal?



 6   Pump  and  treat  means source removal?



 7                MR. TANNER:  No,  ma'am.  That would



 8   actually  be  another  issue.  Irwill  mention  that  next.



 9   That's  a  third  thing.



10                With regard to this  dissolved phase  of



.11   the  groundwater, it  will essentially be a two-fold



12   approach.  We will use  pump and  treat  until we can



13   get  phytoremediation established underground.



14   Hopefully, what we would like to do is, if  we can get



15   out  there and show that, yes, indeed,  the tree roots



16   are  coming down and  they are  beginning to destroy the



17   contamination, we  can back off  this additional pump



18   and  treat mode.  At  that time,  we will come back to



19   the  public and  say,  this is what we found;  it works



20   or it doesn't work.   This  is  what we are  going to



21   continue  to  do.



22                Now, the third item  is  the dark liquid



23   here.   This  is  actual saturated  contamination liquid




24   pools of  these PAHs,  this coal  tar  and BTEX as well.



25   And what we  are going to do on  these areas, because
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         34
 1   it's so concentrated,  get  right  to  it;  we  are going



 2   to go in with  a  well;  literally  seep  it  right down in



 3   this area.



 4                So the opening here  is  actually




 5   collecting this  product.   It's more of  a way  where we



 6   can pump on  this  and pump  and pump, and  it's  not



 7   going to be  nearly as  effective  as  a  combination  of



 8   going in and actually  going after the actual  source



 9   itself.  That  in  a nutshell is the  proposed plan.



10                UNIDENTIFIED SPEAKER:   How  big is this



11   excavation?  Are  we just going to see this massive



12   excavation ten or 15 feet  down and  planting trees  in



13   it?



14                MR.  TANNER:  What we are  going to do,  you



15   will be seeing this excavation rather soon.   We are



16   actually going down from land surface.   We are going



17   down to about  three foot,  which  in  this  case  is



18   virtually right  on top of  the water table.



19                We are going to excavate  down  from the



20   land surface,  down to  right at three  foot  on  these



21   areas that you will see here, here.   Let me put up



22   the areas it's in.  These  have been merged; is that



23   correct?  It's more like one or  something  like that.



24   There's another  area here.



25                Our  concept is go after the  highly
              A. WILLIAM  ROBERTS, JR.  &  ASSOCIATES

-------
                                                         35
 1   contaminated  concentrated  areas.



 2               MR. COHEN:   I  have  a  question for you.



 3   My name is Allen Cohen.  You  seem to  focus mainly on



 4   the rehab.  Do you have  any  free  product  here?  Is



 5   there free product versus  you focus where there's



 6   apparently some contaminants  in the aqueous phase?



 7   Is there a second phase  on top  of the water table?



 8   Do you have any gasoline or  gasoline  type products?



 9               MR. TANNER:  At  one point in  the



10   investigation, we did  notice  some type of product,



11   and it would  probably  be --  I will use this.



12               A little background on the gentleman's



13   question.  Most chemicals  are either  heavier than.



14   water or lighter than  water.  The ones that are



.15   heavier, (sic) obviously,  float and form  the NAPLs



16   that we talked about.  The BTEXs  that we  also have at



17   the site tend to be lighter  than  groundwater and they



18   float.  What  we've seen  based on  this particular site



19   history is the sinkers tend  to  be in  this area here.



20               Now, at one  point we  did  observe some



21   floaters out  in one of these  wells, I think it was



22   MW12.  We've  since gone  back, at  least once if not



23   twice, and I  have not  seen any  floaters since then.



24               Now, does  that mean that  they were there



25   because of one freak incident?  I don't know; we will
               A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         36
 1   continue  to  monitor this to make sure they don't pop



 2   back  up,  if  there is not some other little pocket



 3   source  area  out here that we are not seeing.



 4                MR. COHEN:   Are you getting any



 5   downgrading  of  those wells?  I don't know which way



 6   the water is flowing in that direction.



 7                MR. TANNER:   Groundwater is flowing this



 8   way,  directly towards the river.  And your question



 9   was ?



10                MR. COHEN:   I was just wondering, in



11   response  to  your answer,  do you think it could have



12   migrated  past that.well?   Do you have any wells like



13   that  well  more  than you  once did?



14                MR. TANNER:   Yes.  The question is, is



15   the contamination migrating past this last well.  On



16   some  of the  samples,  yes.  On some of the sampling,



17   yes;  on others, no.   So  what that tells us, going



18   back  to this plume,  is  that depending upon, I guess,



19   the site  conditions,  at  any given time, the season




20   probably  has as much effect on this as anything.



21                As  you can  see, this is a -- I will try



22   to enhance it a little  bit.  We've got 100 micrograms



23   per liter.   I shouldn't  do that; I don't know what it



24   is.   You  can see it ends  right here.



25                I guess  beyond here we really don't know.
              A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         37
 1   We came back in and sampled those particular  wells



 2   again, and we weren't getting -- well, the



 3   concentrations were different.  They weren't



 4   extending all the way out.  But there's a good  chance



 5   we could come back in two months again, resample,  and



 6   it will look just like this.



 7               Groundwater is in a very dynamic  state;  a



 8   lot of things going on.  Obviously, what we hope  to



 9   do is, based on our actions taken, to stop this plume



10   from discharging into the river.



11               That's the three big items.  Now, at  this



12   point, this is going to end the formalized



13   presentation.  Let's open it up to general questions.



14   I am sure there's a load of things I might have



15   glossed over or whatever.  Question?



16               MR. CAMPBELL:  You might want to  put  the



17   slide back up of the recovery well sites.  My name



18   again is Paul Campbell, I am with the College of



19   Charleston.  The way in which the screen is set up



20   with the proposed recovery wells, we've got two in



21   the back that kind of look like little linebackers.



22   Is there a purpose?  Is there a preferential  back



23   way?



24               MR. TANNER:  Yes, we have.  This  other



25   groundwater slide, this slide, is easier to address
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         38
 1   the  general  concept  of  this  issue  here.   These would



 2   be crude  estimates.   The  points  might  actually work



 3   out  to  be something  like  this,  this  and  this.  Who



 4   knows?



 5                We  will  do  all our  groundwater models



 6   that will tell  us  where we should  best put them.



 7   Maybe it  works  out to be  something like  that; again,




 8   just an estimate;  something  to  get the idea across



 9   that something  is  going on here, again,  in the same



10   place as  we  noted  as  those floaters  before.



11                MR.  CAMPBELL:  We didn't expect the



12   screen  of wells  that  you've  got, the ones  that are



13   boxed,  those  two that are set back,  to collect



14   groundwater  plume  and perhaps capture  those;  those



15   two  further  back.



16                MR.  TANNER:   Yes, that is  our  intent.



17   What we are  running  up  against  is,  if  you  get too



18   close to  the  river,  you start recovering water from



19   this way  --



20                MR.  CAMPBELL:  Right.



21                MR.  TANNER:   --  rather than  that  way.  We



22   want to avoid pumping the Cooper River and cleaning



23   it up although  that  may not  necessarily  be a  bad



24   idea.   I  don't  think  it would be appropriate  to ask



25   the gas company  to do that in this case.
              A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         39
 1               UNIDENTIFIED SPEAKER:  That  would be a



 2   big project.



 3               MR. CAMPBELL:  What's the  life  cycle on



 4   these?  What's the estimated time it's going  to take



 5   to do the groundwater cleanup work?



 6             '  MR. TANNER:  We don't know.   We will



 7   install the system probably within the next ten to 12



 8   months.  As far as how the aquifers is going  to



 9   respond, they all respond a little bit differently.



10               MR. CAMPBELL:  Was that included  in the



11   estimate cost and the options?



12               MR. TANNER:  Yes, it was.  I  believe for



13   estimation purposes; the cost was pu.t  out at  30 years



14   of operation.



15               MR. CAMPBELL:  That's a lot  of  work.



16               MS. JOHNSON:  That's kind  of  a  leading



17   question.  You just used the word aquifer the first



18   time.  You just said it was a lot of work.  Talk



19   about the amount of water; talk about  the direction



20   of the flow.  Where is it coming from?   What  is the



21   water pressure?  What is the velocity  of  the  flow



22   through there?



23               MR. TANNER:  I am not sure I  can  answer



24   all of your questions.  I will try to  answer  the ones



25   that I can and see if we can get you additional
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         40
 1   brainpower  from  the  room.   Groundwater at  this  site



 2   tends to  flow  as  in  throughout  all  the peninsula.   It



 3   tends to  flow  from inland  out  towards  the  river.



 4   That occurs through  a  variety  of  actions.



 5               On this  particular  piece  of  property,



 6   groundwater is flowing this  way.   Judy,  do you  happen



 7   to remember any  of those specifics  about  flow  rates?




 8               MS.  CANOVA:  I  think  we were  looking



 9   around 100  feet  per  year.   We  have  to  look it  up;



10   that was  the general idea;.100  feet per  year.



11               MR.  TANNER:  Keep  in  mind  that what this




12   means, although  the  groundwater may be flowing  at



13   100 foot  per year -- there's my scale  --  that



14   doesn't necessarily  mean that  the contamination is



15   keeping up with  that.




16               What  happens is  the contamination  tends



17   to attract the soil.   There's  a lot of factors  going



18   on.  It's not  flowing,  obviously,  200  feet per  year.



19   If it were, this  site  has  been  in operation or  did



20   operate over a one-hundred-year period,  this would  be



21   washed clean.



22               I  can get  you  specifics on those numbers.



23   I just don't have them.



24               MS.  JOHNSON:   Sure.   Thank you.  Another



25   question; the  brochure for  this meeting  said that you
              A. WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         41
 1   were in the process of selecting  remediation methods



 2   and yet you are kind of talking about  you  have



 3   already selected the remediation  method.



 4               MR. TANNER:  What we've  done  is  that --



 5   to answer your question/ what we  actually  do during



 6   this meeting is propose cleanup methods.   I  may have



 7   used those two words interchangeably;  if  I did,  my



 8   apology.



 9               MS. JOHNSON:  Looking  at the  chart,  which



10   one is closest to the proposal?



11               MR. TANNER:  Talking  about the



12   groundwater?



13               MS. JOHNSON:  Yeah.   Which one is



14   closest to your preference right  now,  put  it that



15   way?  What seems to you to be the  best?



16               MR. TANNER:  The one  that  would  be  the



17   closest would be the one just before the  last one,



18   the source removal, phytoremediation,  the  grout



19   curtain, which has been eliminated.



20               MS. JOHNSON:  Why was  that eliminated?



21               UNIDENTIFIED SPEAKER:  More work.



22               MR. TANNER:  There wasn't  any  great



23   benefit from having it in there.   It is a  rather



24   expensive part of that package.



25               What actually happens  when we  get a  study
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         42
 1   in that evaluates  all  these  options  is,  the



 2   responsible parties, potentially  responsible parties,



 3   send us a document  that  says,  here  is  what  we think



 4   are some reasonable  options.



 5               And we  all sit down,  and we  look at those



 6   options and we evaluate  it from an  engineering



 7   standpoint and say,  well, this one  looks reasonable



 8   from this perspective, but it  has some shortcomings



 9   here.



10               And on  the chart  it essentially lists out



11   the way we evaluate.   We  try  to do  them  as  fair and



12   as objectively as  humanly possible.



13               MS. McGOWEN:  Is  it cost effective



14   analysis and whether financially  it'll be feasible to



15   actually get it done and  do  the job?



16               MR. TANNER:   Yes.  The  cost  of  it is part




17   of it as well.



18               MS. JOHNSON:  Four and  5 look the same.



19               MR. TANNER:   My  apologies, yes.  The one



20   that we are implementing  is  actually the last one.



21               MS. JOHNSON:  As  far  as  the  soil cleanup



22   option, I think you  said  the  landfill, off-site



23   landfill, was the  preferred?



24               MR. TANNER:   Right.



25               MS. JOHNSON:  Where are  there landfills
               A.  WILLIAM  ROBERTS,  JR.  & ASSOCIATES

-------
                                                         43
 1   that would take stuff like this?  Are  there  any



 2   places ?



 3               UNIDENTIFIED SPEAKER:   Laidlaw.



 4               MR. TANNER:  Laidlaw  is  still  operating.



 5               MS. JOHNSON:  You are naming a company.



 6   I am saying where.



 7               MR. RICHTER:  Some  of that  goes  to



 8   Chambers Oakridge.  I'm a hazardous  waste  consultant



 9   for DHEC.



10               MS. JOHNSON:  For the project?



11               MR. RICHTER:  For this  district.   We



12   oversee the disposal of soil.   Some  of  that  soil



13   could go to Chambers Oakridge.  It  doesn't exhibit



14   the characteristics of a hazardous  waste.  It's not  a



15   listed waste.  In some cases it doesn't meet  the



16   characteristics.  So it can go  to a  subtitle  D



17   landfill.  A lot of it probably has  already  gone



18   there.  That landfill has check control.



19               MS. McGOWEN:  Oakridge  where?



20               MR. RICHTER:  Chambers  Oakridge  up in



21   Dorchester County.



22               MR. TANNER:  What we'll  actually  do is



23   characterize the waste.  Actually we've done  some



24   preremoval characterization of  the  waste.



25               Because of the expense  involved  in
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         44
 1   sending  it  to a, quote,  unquote — I am trying to



 2   avoid  all  the nomenclature and buzz words in the



 3   environmental group.   There's a difference between



 4   contaminated waste versus RCRA contaminated waste.



 5-   They have  to be handled  a little bit differently.



 6   The waste  that is a RCRA contaminated waste has to be



 7   sent to  a  special facility.



 8                MS. JOHNSON:  What was the word again?



 9                MR. TANNER:   RCRA.  It's Resource



10   Conservation something.



11                MS. McGOWEN:  Resource Conservation.



12                MS. JOHNSON:  I  would like the person in



13   charge here  to answer the question.  Go ahead.



14                MR. TANNER:   Okay.  Let me go back and



15   get a  global view of  what we are doing with the



16   waste.   The  waste,  obviously, is not all contaminated



17   in a uniform manner.   There  are areas that are very



18   hot cleanup  goals as  well as there are other areas



19   that are not as hot as those but still exceed the



20   cleanup  criteria.  You might have some that are --



21   and I  don't  know the  actual  RCRA numbers, but we will



22   when we  actually put  it  in these disposal facilities.



23   You might  have some of these areas that are 100,000



24   parts  per  million or  greater in these little pockets



25   but what you will find is it's not all uniformly
               A.  WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         45
 1   contaminated.



 2               What we try to do for cost purposes  is  to



 3   say, where can we send this waste if we don't  all



 4   have to send it to a place that charges us  $50  a  ton.



 5   And this is one area of waste disposal that  is  also



 6   regulated by the Environmental Protection Agency  as



 7   well as DHEC.



 8               We say, where can we send the waste.   Do



 9   we all have to send it to a subtitle D facility  or



10   can we send a portion of it to a subtitle C  facility?



11   They both offer containerized storage; one  just



12   offers a much more higher level because the  waste  in



13   turn is more hazardous.  I'm hesitant to use the  term



14   more hazardous because it's all hazardous.   We  get  in



15   there with little subtleties of what we are  doing



16   here; a disposal that is cost effective.



17               MS. JOHNSON:  Now we are at the  point



18   where I can ask the question again:  Where  are  the



19   sites that can take, for example, class C and  class D



20   contaminants?



21               MR. TANNER:  Pinewood, South Carolina  is



22   subtitle C.



23               MS. JOHNSON:  Thank you.



24               MR. RICHTER:  Chambers Oakridge  in



25   Dorchester County is subtitle D.  They got  a line.
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         46
 1




 2




 3




 4




 5




 6




 7




 8




 9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25
            MS.  JOHNSON:   Where  is  that,  please?



            MR.  RICHTER:   Dorchester County,  South
Carolina .
            MS.  JOHNSON:   You  used  a  name,  Chambers?



            MR..  RICHTER:   Oakridge.



            MS.  JOHNSON:   Chambers  Oakridge.   That's



a place name, Chambers  Oakridge?



            MR.  RICHTER:   Uh-huh.



            MR.  TANNER:   If  it's  any  comfort  --



            MS.  JOHNSON:   That's  B  you  said?



            MR.  RICHTER:   No,  that's  a  subtitle D.



            MR.  TANNER:   They  have  smart  people on  --



like this gentleman  --  the project  so people  like me



aren't making the decision.  We can say,  these are



the levels, where can we  dispose  of them?



            MR.  RICHTER:   Can  I ask a question before



we quit?



            MR.  TANNER:   Yes.



            MR.  RICHTER:   The  future  parking  garage



fits right along the edge of the  contaminated soils



that's going to  be excavated.   Is that  drawn  like



that because the soil is  going to be  excavated before



the future parking garage is built, or  does it



actually run straight down in  a line  like that?



            MR.  TANNER:   It's  not exactly a.straight
               A.  WILLIAM ROBERTS,  JR.  & ASSOCIATES

-------
                                                         47
 1   line, but the garage looks something  like  this.   And



 2   it will be excavated prior to the garage going  in



 3   place.  The garage itself is -- I don't know  --



 4   something like this.  There's about a 20-foot



 5   quarter, I believe, in this area here where we  are



 6   going to be moving that.



 7               UNIDENTIFIED SPEAKER:  That is actually



 8   under the parking garage where you are going  to  move



 9   it?



10               MR. TANNER:  It's going to be  close,  it's



11   not exactly under.  The removal will  precede  the



12   construction of the garage itself.  We may be out



13   there digging around and find a little pocket righ.t



14   here and come out that far; something like that.   But



15   after we are done with that, the garage will  come



16   back and cover this.  It would probably have  been a



17   more descriptive figure if this wasn't here,  if



18   that's causing some confusion.



19               MS. JOHNSON:  According to the City  of



20   Charleston, the size of the parking garage -- this



21   was public information at a zoning meeting ten  days



22   ago -- the configuration of the garage was related to



23   your remediation plans, if that's what you said.



24               Is there any chance that  with  some



25   possible change in the remediation plan that  will
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         48
 1   impact  it?   I  am not  asking an alarming question with



 2   everything  still in  a developmental  stage here.



 3                Is there  any chance that there may be



 4   other changes  in the  use of that area -- the size of



 5   the garage,  how far  it extends into  the area that's



 6   requiring  remediation,  in the whole  configuration?



 7   Is there any chance  that there will  be further




 8   modifications  of the  planned construction, do you



 9   think?   I  am asking  a what do you think question.



10                MR.  TANNER:   Let me see  if I understand



11   your question.



12                MS.  JOHNSON:   Sure.



13                MR.  TANNER:   Would changes to the garage



14   blueprint  itself affect--



15                MS.  JOHNSON:   No,  the remediation plans;



16   are there  additional  further developed remediation



17   plans?  Will they impact the garage  site, the



18   configuration  of the  site,  do you think?



19                MR.  TANNER:   I don't think so.



20                MS.  JOHNSON:   You think  you are far



21   enough  along so that  you feel sure?   You have enough



22   area for pumping and  digging wells and the various



23   methods, enough space to do all that?  I guess that's




24   the question.   Do you have enough space to do all



25   those things?
               A.  WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         49
 1               MR. TANNER:  Yes, we do.  It's  been a



 2   juggling act, working with all the different  agencies



 3   to make sure that we can clean the site up, put it



 4   back into productive use.  Even if things change



 5.   again, we will modify whatever we are doing to  a



 6   limited amount; obviously, not going to go  in and



 7   completely change the remedy because of something and



 8   then go out and do it.



 9               MR. ZELLER:  Along that line, actual



10   cleanup numbers that are issued, maybe to help  answer



11   the question, if the number is 50 for PAHs, all soil



12   that is greater than 50 would be excavated, just for



13   an example.



14               So as Terry mentioned, had they estimated



15   a certain amount of volume above 50, that will  have



16   to be excavated.  If that number goes up, excavate



17   everything above 50.  Once they are done with that,



18   they have to backfill in or whatever.  It's not a



19   manual situation.  They can come back in and  develop



20   it as the aquarium and parking garage and everything



21   else.



22               MR. TANNER:  Yes.  These cleanup  numbers



23   are driven by risks so we have to follow up.



24               MR. ZELLER:  Of course, it%'s unknown to



25   some degree; shouldn't tripl.e or quadruple.
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                          50
  1                MR. TANNER:  There's one group here  --



  2    let me introduce this group.  Mike Hammerpart  is  on



  3    this project with the State of South Carolina, and



  4    he's sitting in the front row.  I would like them to



  5    introduce themselves.  This is the group here  in



  6    South Carolina that I work with.



  7                MR. COLEMAN:   My name is Ken Coleman, I



  8    am the manager of the Superfund in South Carolina.



  9                MR. HAYNES:  Richard Haynes, I'm the



 10    state project manager for the Superfund.



 11                MS. CANOVA:  Judy Canova, project



 12    geologist.



 13                MR. MALERO:  Eric Malero, Division of.



 14    Health Hazard Evaluation.



.15                MS. JOHNSON:   Do you have your operating



 16    offices nearby?



 17                MR. HAYNES:  Columbia.



 18                MR. TANNER:  Thanks.  I work with  these



 19    folks a good deal on the  sites.  When we get the



 20    reports in,  we get together and we review them and we



 21    go back to  comments, work out the technical details




 22    to make sure that we are  in agreement.  It's a system



 23    of checks and balances.



 24                Yes.



 25                MS. MAREKI:  Do you know yet what  kind of
               A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         51
 1   plants you are going to use for the phytoremediation?



 2               MR. TANNER:  We have looked at  oak  trees.



 3   And I don't know if we've looked at any other



 4   specific species beyond that.  Walter, could you



 5   elaborate on that?



 6              ' UNIDENTIFIED SPEAKER:  We've  looked at



 7   several different species working with the  City of



 8   Charleston on the type of criteria that they have on



 9   the listing of approvable trees.  So we are trying  to



10   stick with the same type of vegetation they have



11   around the city and around the area/ but  there's



12   going to be a couple different; not just  one species.



13               MR. TANNER:  Yes.



14               UNIDENTIFIED SPEAKER:  It seems that if



15   the roots of the tree are sucking up all  this stuff,



16   the tree would die.



17               MR. TANNER:  In certain concentrations,



18   it would be toxic,  obviously.  The levels that  we are



19   seeing here in the groundwater don't appear to  be



20   toxic to the plants.



21               Now, if we were to plug down  a  tree right



22   into this heavily contaminated soil area, it might



23   kill it.   But if we are looking at phytoremediation



24   from the perspective of groundwater, we wouldn't do



25   that.   Again,  on these groundwater concentrations we
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         52
 1   are seeing here, we don't think it's going  to  affect



 2   it.  The bigger concern is, will  it work.



 3               A couple of things I  wanted  to  mention



 4   briefly while I'm on this subject before  our meeting



 5-   draws to a close.  We have done some sampling  out



 6   here in the sediments and found that we've  got some



 7   contamination, let's see, here, and this  isn't



 8   exactly to scale; it's more or less; and  we found



 9   some more here.  And, of course,  with the outbreak of



10   this seep here, it's a good bet we've got some



11   contamination out here as well.   I will  be  back to



12   discuss that at a future meeting.



13               One of the things I wanted to do.for



14   purposes of this meeting was to address  specifically



15   the soils and the groundwater.  We want  to  get moving



16   on that.  And we will be addressing those soils at



17   another point in time.



18               What you guys are going to see  within the



19   next month or two months is some  activity on these



20   soils here.  SCE&G has agreed to  go in and  do  a



21   removal action on these soils concurrent  with  the



22   proposed plan.  We are also working with  them  to take



23   some type of action on these seeps at that  same time.



24   So, again, within the next couple of months, you are



25   going to see a good deal of activity out  here; just
              A. WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         53
 1   know that that's what it's for.  Questions,  comments?



 2   If not, we will try to wrap this thing up  and  get



 3   home.    Yes.



 4               UNIDENTIFIED SPEAKER:  Could we  have a



 5.   little bit more advance notice?  I received  this



 6   Friday.



 7               MR. TANNER:  Yes, my apologies.  That



 8   should have been handled better.



 9               MS. JOHNSON:  This has been a  good



10   meeting.  This will be on my desire to hear  more.



11               MR. TANNER:  I hope it's been  helpful.



12   At least you've got some idea of what's going  on.



13   Yes.



14               MS. McGOWEN;  If I can beg the group's



15   indulgence for a moment.  I have been trying to get



16   some help with a problem.  I thought maybe I might



17   collar the right people in this room.



18               I own Turkey Creek in Sumter,  one  of the



19   most polluted areas in the state.  We've got



20   pollution for almost 40 years; cadmium, lead,



21   mercury, chromium.  Our numbers are a lot  higher than



22   what you got  on this sheet.



23               We've had eight corporations polluting us



24   with impunity; no one has even looked at cleaning up



25   the problem.   It flows into the Pocotaligo River.
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------
                                                         54
 1   The City of Sumter is thinking  about  taking  some



 2   dredges and going in and opening  up the  waterway



 3   without permit or notifying the right people and  will



 4   probably resuspend a lot of stuff  that you don't  want



 5   resuspended.



 6               The reason they are doing this is  because



 7   they have got almost 60 acres of  my property under



 8   water now, and I'm drowning.  This is the  last



 9   battleground of the Civil War and  the 54th regiment,



10   the Glory guys, are buried on my  land, and I need



11   some help.  And I hope that lady  over there  is typing



12   this.  So to go on record, my phone number is



13   556-9487, and I expect some phone  caj.ls  in the



14   morning.  Thank you.



15               MR. TANNER:  I don't  get  that  at every



16   meeting.  I will, ma'am.  I will  call you.



17               MS. McGOWEN:  Thank you so much.   Your



18   name?



19               MR. TANNER:  Terry  Tanner.   I  will meet




20   you after this.



21               MS. McGOWEN:  We will  do  lunch.



22               MR. TANNER:  Everybody has my  number.



23               (Thereupon, the hearing was  concluded at



24   8:30 p.m.)



25
              A. WILLIAM  ROBERTS,  JR.  &  ASSOCIATES

-------
                                                         55
 1

 2                  CERTIFICATE OF  REPORTER

 3

 4               I, Lora L. McDaniel,  Registered

 5   Professional Reporter and Notary  Public  for  the  State

 6   of South Carolina at Large, do  hereby certify  that

 7   the foregoing transcript is a  true,  accurate and

 8   complete record.

 9               I further certify  that  I am  neither

10   related to nor counsel for any  party to  the  cause

11   pending or interested in the events  thereof.

12

13

14

15                        APRIL 6,  1998

16

17
19                       Itsura L. McDaniel
                         Registered Professional  Reporter
20                       My Commission expires
                         November  12, 2006
21

22

23

24

25
              A. WILLIAM ROBERTS, JR. & ASSOCIATES

-------