PB95-964027
                                EPA/ROD/R04-)§/240
                                January 1996
EPA Superfund
      Record of Decision:
       Marine Corps Base (Site 35),
       Operable Unit 10, Camp Lejeune, NC
       9/22/1995

-------
               FINAL

    INTERIM RECORD OF DECISION
    FOR SURFICIAL GROUNDWATER
FOR A PORTION OF OPERABLE UNIT NO. 10
SITE 35 - CAMP GEIGER AREA FUEL FARM

        MARINE CORPS BASE,
   CAMP LEJEUNE, NORTH CAROLINA

     CONTRACT TASK ORDER 0232

          SEPTEMBER 5,1995
            Prepared For:

      DEPARTMENT OF THE NAVY
         ATLANTIC DIVISION
         NAVAL FACILITIES
       ENGINEERING COMMAND
            Norfolk, Virginia

-------
                           TABLE OF CONTENTS
LIST OF ACRONYMS AND ABBREVIATIONS	iv

DECLARATION	vi

1.0    SITE LOCATION AND DESCRIPTION	1

2.0    SITE HISTORY AND ENFORCEMENT ACTIVITIES	1
      Previous Investigations and Findings	3

3.0    HIGHLIGHTS OF COMMUNITY PARTICD7ATION	5

4.0    SCOPE AND GOALS OF INTERIM REMEDIAL ACTION	6

5.0    SITE CHARACTERISTICS 	1

6.0    SUMMARY OF SITE RISKS	8
      Baseline Human Health Risk Assessment  	8
      Ecological Risk Assessment	•	10
             Aquatic Ecosystem 	10
             Terrestrial Ecosystem  	11

7.0    DESCRIPTION OF ALTERNATIVES	 '.	12

8.0    SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES	19
      Overall Protection of Human Health and the Environment	19
      Compliance  With ARARs 	•	19
      Long-Term Effectiveness and Permanence 	20
      Reduction of Toxicity, Mobility, or Volume Through Treatment	20
      Short-Term Effectiveness	21
      Implementabiliry	22
      Cost	23
      USEPA/State Acceptance	23
      Community  Acceptance 	23

9.0    SELECTED REMEDY	23
      Remedy Description	25
      Estimated Costs  	26

10.0  STATUTORY DETERMINATIONS	26
      Protection of Human Health and the Environment  	27
      Compliance With Applicable or Relevant and Appropriate Requirements	27
      Cost-Effectiveness 	27
      Utilization of Permanent Solutions and Alternative Treatment Technologies	27
       Preference for Treatment as a Principal Element	27

                                      ii

-------
                              TABLE OF CONTENTS
                                   (Continued)
                                                                            Page
11.0   RESPONSIVENESS SUMMARY	28
       Overview	28
       Background On Community Involvement	28
       Summary of Comments Received During the Public Comment Period
       and Agency Responses	29

12.0   REFERENCES	29
LIST OF TABLES

1      Summary of COPCs in Environmental Media of Concern
2      Total Site Risk
3      Summary of Alternatives Evaluation
4      Glossary of Evaluation Criteria
LIST OF FIGURES

1      Camp Lejeune and site 35 Location Map
2      Site Plan
3      Limits of Combined BTEX in the Upper Portion of the Surficial Aquifer
4      Limits of Combined BTEX in the Lower Portion of the Surficial Aquifer
5      Limits of Combined Halogenated Organic Compounds in the Upper Portion of Surficial
       Aquifer
6     . Limits of Combined Halogenated Organic Compounds in the Lower Portion of the Surficial
       Aquifer
7      RAA 3: Groundwater Collection and On-Site Treatment - Plan View
8      RAA 3: Groundwater Collection and On-Site Treatment - Cross Section A-A
9      RAA 3: Groundwater Collection and On-Site Treatment - Process Flow Diagram
10     RAA 5: In Well Aeration and Off-Gas Carbon Adsorption - Plan View
11     RAA 5: In Well Aeration and Off-Gas Carbon Adsorption - Typical Well Detail and Process
       Flow Diagram
12     Comparison of Costs RAAs 2, 3,4, and 5
                                        111

-------
                   LIST OF ACRONYMS AND ABBREVIATIONS
ARAR/TBC     applicable or relevant and appropriate requirements/to be considered (criteria)
AST           aboveground storage tank

Baker          Baker Environmental, Inc.
bgs     -       below ground surface
BRA           Baseline Human Health Risk Assessment
BTEX          benzene, toluene, ethylbenzene, and total xylenes

CERCLA       Comprehensive Environmental Response, Compensation, and Liability Act
CFR           Code of Federal Regulations
COPC          contaminant of potential concern
CS             Confirmation Study  .
CSA           Comprehensive Site Assessment

DON           Department of the Navy

ERA           Ecological Risk Assessment
ESE           Environmental Science and Engineering, Inc.

FFA           Federal Facilities Agreement
FFS           Focused Feasibility Study
FS             Feasibility Study

HI             Health Index

IAS           in situ air sparging
ICR           Incremental Cancer Risk
IRP           Installation Restoration Program

Law           Law Engineering, Inc.

MCB          Marine Corps Base
MTBE         methyl tertiary butyl ether

NC DEHNR    North Carolina Department of Environment, Health and Natural Resources
NCDOT        North Carolina Department of Transportation
NCP           National Oil and Hazardous Substances Pollution Contingency Plan
                                         IV

-------
NCWQS       North Carolina Water Quality Standards
NPL           National Priorities List
NUS           NUS Corporation

O&M          operation and maintenance
OU            Operable Unit

PCS           Polychlorinated Biphenyl
PRAP          Proposed Remedial Action Plan

RAA           remedial action alternative
RI             Remedial Investigation
ROD           Record of Decision
SVE           Soil Vapor Extraction

T-1,2-DCE      trans-1,2- dichloroethene
TAL           Target Analyte List
TCE           trichloroethylene
TCL           Target-Compound List
TPH           total petroleum hydrocarbons

USEPA        United States Environmental Protection Agency
UST           underground storage tank

VOC           Volatile Organic Compound

WAR          Water and Air Research, Inc.

-------
                                  DECLARATION

Site Name and Location
Operable Unit No. 10 (Site 35)
Marine Corps Base
Camp Lejeune, North Carolina

Statement of Basis and Purpose

This decision document presents the selected remedy for surficial groundwater for a portion of
Operable Unit (OU) No. 10 (Site 35), Marine Corps Base (MCB), Camp Lejeune, North Carolina,
which was chosen in accordance with the Comprehensive Environmental Response, Compensation,
and  Liability Act of 1980  (CERCLA), as amended by the  Superfund Amendments and
Reauthorization Act (SARA), and, to the extent practicable, the National Oil and Hazardous
Substances Pollution' Contingency Plan (NCP).  This particular  interim action  focuses  on
contaminated surficial groundwater in the vicinity of the former Camp Geiger Fuel Farm extending
downslope to Brinson Creek. This decision is based on the Administrative Record for Operable Unit
No. 10.

The Department of the Navy (DON) and the Marine Corps have obtained concurrence from the State
of North Carolina Department of Environment, Health and Natural Resources (NC DEHNR) and the
United States Environmental Protection Agency (USEPA), Region IV, on the selected remedy.

Assessment of the Site

Actual or threatened releases of hazardous substances from this operable unit, if not addressed by
implementing the response action selected in this Interim Record of Decision (ROD), may present
a potential threat to public health, welfare, or the environment.

Description of Selected Remedy

Five Remedial Action Alternatives (RAAs) were evaluated as part  of an  interim remedial
investigation/feasibility study for surficial  groundwater at OU No.  10  (Site 35). These  RAAs
included RAA 1  (No  Action), RAA  2 (No  Action With Institutional Controls),  RAA 3
(Groundwater Collection and On-site Treatment), RAA 4 (In Situ Air Sparging and Off-Gas Carbon
Adsorption) and RAA 5 (In Well Aeration and Off-Gas Adsorption). After all five RAAs were
compared to established criteria, RAA 5 was selected as the preferred alternative.
                                          VI

-------
RAAs 1, 2, 3 and 4 were not selected as the preferred alternative.  Neither RAA 1 nor RAA 2 were
selected primarily because of the potential environmental impacts associated with a no  action
alternative. RAA 3 was not selected primarily because of its high cost and  implementation
difficulties.  RAA 4 was not selected primarily because of potential difficulties controlling releases
of toxic vapors associated with vapor extraction. Thus, RAA 5, which was determined to be the most
cost effective alternative, was selected as the preferred alternative because it best met the various
selection criteria.,

The selected remedy focuses on positively impacting contaminated surficial  groundwater in the
vicinity of the Fuel Farm as it moves downgradient towards Brinson Creek. The physical location
of this remedial action will be just beyond the northern right-of-way boundary of the proposed U.S.
Route 17 bypass (i.e., six-lane divided highway) in the direction of Brinson Creek, and will extend
the  entire width of the contaminant plume. RAA 5 is an Interim Remedial Action representing only
one phase of a comprehensive investigation and remediation program at Site 35.

The selected remedy addressed in this Interim ROD provides for reduction of organic contaminants
in the surficial groundwater to levels below North Carolina Water Quality Standards (NCWQS) and
mitigates potential risks to human health and the environment.

The major components of the selected remedy (RAA 5) include:

        •       Six aeration wells spaced at approximately 180 feet (center to center). These wells
               would be installed in a line between the proposed highway and Brinson Creek.

        •       A submersible pump incorporated into each well. These pumps are placed near the
               bottom of the wells. They draw in contaminated groundwater and pump it to the
               stripping zone of the aeration system.

        •      An aeration system in each well. As water is pumped in from the bottom of the
               wells; air is injected into the water allowing the VOCs to move from the dissolved
               phase to the vapor phase.  As the  water  is aerated, it is forced back out into the
               formation.

        •      A header system that delivers pressurized air from the compressor/blowers at each
               well to the well heads.

        •      An air extraction  header system  that runs  from the well  heads to a  carbon
               adsorption unit adjacent to the well. This system is equipped with vacuum pumps
               that draw VOC laden air from the wellheads to carbon adsorption units.
                                            VII

-------
        •      Carbon adsorption units that adsorb vapor phase VOCs from the contaminated air
               prior to discharge to the atmosphere. These units, along with the blowers, vacuum
               pumps, and controls will be housed in individual treatment buildings, which will
               also house the in well aeration well heads.

        •      Each well head has an upper observation well (slightly above groundwater table)
               and a lower observation well below the groundwater table.

        •      Implementation of aquifer use restrictions.

        •      Long-term groundwater monitoring.

The viability of in well aeration technology at Camp Lejeune needs to be determined by means of
a field pilot test.  Such a test is scheduled to be initiated in October 1995 at Camp Lejeune. A Draft
Report of results will be available in May  1996.  Additionally, the field pilot test will provide
important design support data. If it is determined, based on the results of the field pilot test, that in
well aeration cannot perform as required, RAA 3 (Groundwater Collection and On-Site Treatment)
will be selected as the Interim Preferred Remedial Action.

The major components of RAA 3 include:

        •      A verticle interceptor trench (specifically, a biopolymer slurry  drainage trench)
               approximately two feet wide, by 30 feet deep, by 1,080 feet long. This trench will
               be constructed from the ground surface to the semiconfining layer.

        •      A groundwater collection system consisting of submersible pumps and above and
               below ground piping. Water that is intercepted by the trench is conveyed to an on-
               site groundwater treatment plant.

        •      A groundwater treatment plant located on-site. This plant will include a treatment
               building which will house the following major process units:  a filtration system,
               a settling tank, a sludge holding tank, an air stripper, an off-gas carbon adsorption
               unit, and a liquid phase carbon adsorption unit.

        •      Implementation of aquifer use restrictions.

        •      Long-term groundwater monitoring.
                                           VIll

-------
Declaration

This interim action is protective of human health and the environment, complies with federal and
state applicable or relevant and appropriate requirements (ARARs) and criteria to be considered
(TBCs) directly associated with this action, and is cost-effective.  This action utilizes permanent
solutions and alternative treatment  technologies to the maximum extent practicable, given the
limited scope of the action. Because this action does not constitute the final remedy for Site 35, the
statutory preference for remedies that employ treatment that reduces toxicity, mobility, or volume
as a principal element for other media, including groundwater south and southwest of the above
ground storage tank (AST) area, surface water, and sediment will be addressed at the time of the
final response action. Subsequent actions are planned to address fully the principal threats posed
by this site.
Signaturo^Commanding General, MCB Camp Lejeune)         Date
                                            IX

-------
1.0    SITE LOCATION AND DESCRIPTION

Marine Corps Base (MCB), Camp Lejeune is a training base for the U.S. Marine Corps, located in
Onslow County, North Carolina. The Activity, as the base is referred to, covers approximately
236 square miles and includes 14 miles of coastline.  MCB, Camp Lejeune  is bounded to the
southeast  by the Atlantic  Ocean,  to the northeast  by State Route  24,  and to the west by
U.S. Route 17. The town of Jacksonville, North Carolina, is located north of the Activity (see
Figure  1).

Camp Geiger is located at the extreme northwest comer of MCB, Camp Lejeune. The main entrance
to Camp Geiger is off U.S. Route 17, approximately 3.5 miles southwest of the city of Jacksonville,
North Carolina. Site 35, the decommissioned Camp Geiger Area Fuel Farm, refers primarily to five,
15,000-gallon aboveground storage tanks (ASTs), a pump house, and a fuel unloading pad formerly
situated within Camp Geiger just north of the intersection of Fourth and G Streets (see Figure 2).

Site 35 is contained within Operable Unit (OU) No. 10, one of 14 operable units at MCB, Camp
Lejeune. An "operable unit," as defined by the National Oil and Hazardous Substances Pollution
Contingency Plan (NCP),  is  a discrete action that comprises an  incremental step toward
comprehensively addressing site problems.

The Interim  Feasibility Study  (FS) study area consists of a portion of OU No.  10 measuring
approximately 18 acres. More specifically, the study area consists of contaminated groundwater in
the portion of the surficial aquifer that js located roughly between the Fuel Farm and Brinson Creek
(see Figure 2).

2.0    SITE HISTORY AND ENFORCEMENT ACTTVTnES

Construction of Camp Geiger was completed in 1945, four years after construction of MCB, Camp
Lejeune was initiated.  Originally, the ASTs were used for the storage of No. 6 fuel oil, but were
later converted for storage of other petroleum products including unleaded gasoline, diesel fuel, and
kerosene.  The date of their conversion is not known.  The ASTs at the site are reported to be the
original tanks. Demolition of the Fuel Farm ASTs is completed, having begun in the spring of 1995.

Product was dispensed from the ASTs via trucks and underground piping. Routinely, the ASTs at
Site 35 supplied fuel to an adjacent dispensing pump. A leak in the underground line from the ASTs

-------
to the dispensing island was reportedly responsible for the loss of roughly 30 gallons per day of
gasoline over an unspecified period (Law, 1992).  The leaking line was subsequently sealed and
replaced.

The ASTs at Site 35 were used to dispense gasoline, diesel, and kerosene to government vehicles
and to supply underground storage tanks (USTs) in use at Camp Geiger and the nearby New River
Marine Corps Air Station until the spring of 1995.  The ASTs were supplied by commercial carrier
trucks which delivered product to fill ports located on the fuel unloading pad at the southern end of
the facility. Six short-run (120 feet maximum), underground fuel lines were utilized to distribute
the product from the unloading pad to the ASTs.

Reports of a release from an underground distribution line near one of the ASTs date back to
1957-58 (ESE, 1990). Apparently, the leak occurred as the result of damage to a dispensing pump.
At that time, the Camp Lejeune Fire Department estimated that thousands of gallons of fuel were
released, although records of the incident cannot be located.  The fuel reportedly migrated to the east
and northeast toward Brinson Creek. Interceptor trenches were excavated and the captured fuel was
ignited and burned.

Another abandoned underground distribution line extended from the ASTs to the former Mess Hall
Heating Plant, located adjacent to D Street, between Third and Fourth Streets. The underground line
dispensed No. 6 fuel oil to a UST which fueled the Mess Hall boiler. The Mess Hall, located across
"D" Street to the west, is believed to have been demolished along with its Heating Plant in the 1960s.

In April 1990, an undetermined amount of fuel had been  discovered by Camp Geiger personnel
along the unnamed drainage channels north of the Fuel Farm. Apparently, the source of the fuel,
believed to be diesel or jet fuel, was an  unauthorized discharge from a tanker truck that was never
identified. The Activity reportedly initiated an emergency clean-up action that included the removal
of approximately 20 cubic yards of soil.

Decommissioning of the Fuel Farm began in the spring of 1995 and was completed in July 1995.
The ASTs were cleaned, dismantled and removed along with associated concrete foundations, slabs
on grade, berms, and underground piping. The Fuel Farm was removed to make way for a six-lane,
divided highway proposed by the North Carolina Department of Transportation (NC DOT) (see
Figure 2).

-------
In addition to the Fuel Farm dismantling, soil remediation activities began in August 1995 along the
highway right-of-way as per an Interim Record of Decision executed on September 15, 1994. The
soil remediation work is scheduled to be completed during the fall of 1995.

Previous Investigations and Findings

Previous investigations conducted at Site 35 include the Initial Assessment Study of Marine Corps
Base, Camp Lejeune, North  Carolina (WAR,  1983); Final Site Summary Report, MCB Camp
Lejeune (ESE, 1990); Draft Field Investigation/Focused Feasibility Study, Camp Geiger Fuel Spill
Site (NUS, 1990); Underground Fuel Investigation and Comprehensive Site Assessment (Law,
1992); Addendum Report of Underground Fuel Investigation and Comprehensive Site Assessment
(Law, 1993); Interim Remedial Action Remedial Investigation/Feasibility Study for Soil (Baker,
1994); Comprehensive Remedial Investigation Report (Baker, 1994); and Interim Feasibility Study
for Surficial Groundwater (Baker, 1994).

The Initial Assessment Study identified Site 35 as one of 23 sites warranting further investigation.
Environmental media were not sampled as part of this study.

ESE performed the Confirmation Study at the  Fuel  Farm  between 1984  and 1987.  Soil,
groundwater, surface water, and sediment samples were obtained and analyzed for lead, oil and
grease. Groundwater was also analyzed for volatile organics. Oil and grease results indicated that
soils northeast of the Fuel Farm were potentially impacted by site activities.

Additional wells were installed by NUS Corporation during the Focused Feasibility Study, which
was conducted  in 1990.  Soil cuttings obtained from two of the four well  boreholes contained
hydrocarbon related contamination.

Law conducted the Comprehensive Site Assessment in  1991. A total of 18 soil borings were drilled,
sampled and converted to nested wells that monitor the upper and lower portions of water table
aquifer. An additional three soil borings were drilled to provide stratigraphic data. Five more soil
borings were drilled to provide data regarding vadose zone contamination.  Nine hand-auger
samples were also obtained. A follow-up study was conducted subsequent to the Comprehensive
Site Assessment. Three additional borings were drilled, sampled and converted to wells.

-------
Law identified separate areas of impacted soil and groundwater directly beneath and apart from the
Fuel Farm.  The nature of the contamination included both chlorinated organic compounds (e.g.,
TCE, trans- 1,2-DCE, and vinyl chloride) and petroleum hydrocarbons (e.g., TPH, MTBE, BTEX).
The majority of the soil contamination encountered appeared to be associated with a fluctuating
groundwater table. Two plumes of shallow groundwater contaminated with petroleum constituents
and two plumes contaminated with chlorinated organics were identified.  All four plumes were
located north of Fourth Street and east of E Street except for a portion of a TCE plume extending
southwest of Fourth Street. The approximate locations of these plumes are shown on Figures 3,4,
5, and 6.

The Interim Remedial Action RI conducted by Baker in 1993 and 1994 consisted of drilling seven
additional soil borings including five in those areas where groundwater contamination plumes were
suspected. In general, the Interim Remedial Action RI data confirmed the findings of the CSA (Law,
1992) which indicated contaminated soil conditions at Site 35  are primarily associated with a
fluctuating.shallow groundwater plume.

The Interim Remedial Action RI/FS culminated with an executed Interim Record  of Decision
(ROD), signed on September 15,1994, for the remediation of contaminated soil along and adjacent
to the proposed highway right-of-way at Site 35.  Three areas  of contaminated soil have been
identified (see Figure 2). The first area is located in the vicinity of the Fuel Farm and the two other
areas are located north of the Fuel Farm. The larger of these two areas is located along F Street in
the  vicinity of monitoring well MW-25. Baker has estimated that approximately 3,600 cubic yards
(4,900 tons) of contaminated soil is present in these areas. Contaminated soil located in these areas
is scheduled for removal and disposal at an off-site soil recycling facility beginning July 1995.

A fourth area of soil contamination, located immediately north of Building G480, was also identified
in the Interim ROD(1994).  Additional data pertaining to this fourth area became available
subsequent to the execution of the Interim ROD. The data indicated that contaminated soil was
encountered in this area during the removal of a UST in January 1994. The contaminated soil was
excavated and reportedly disposed off site; however, no documentation is available regarding how
or where the soil was disposed. An additional soil investigation will be conducted in this area to
confirm  that the contaminated soil  was not returned to the excavation and that follow-up  soil
remediation in this area is not necessary.

-------
A comprehensive RI was conducted by Baker in 1994 to evaluate the nature and extent of the threat
to public health and the environment caused by the release of hazardous substances, pollutants, or
contaminants, and to support a Feasibility Study evaluation of potential remedial alternatives. The
RI field program was initiated on April 11, 1994. Data gathering activities were derived from a soil
gas  survey  and groundwater  screening investigation,  a soil  investigation,  a groundwater
investigation, a surface water and sediment investigation, and an ecological investigation. From the
results of the comprehensive RI, an Interim Feasibility Study for surficial groundwater was
completed in May 1995 and is the supporting document of this Interim ROD.  An Interim Proposed
Remedial Action Plan (PRAP) identified In Well Aeration and Off-Gas Carbon Adsorption as the
method to remediate organic contamination in the surficial groundwater in the vicinity of the Fuel
Farm.

Fuel and solvent related groundwater contamination was identified in the surficial aquifer in the area
north of Fourth Street. Two additional plumes of solvent related groundwater contamination have
been identified adjacent to Site 35. The extent and sources of this contamination have not been
identified and additional RI activities are planned. In addition, significant levels of organic and
inorganic contamination were identified in sediment samples.

Two USTs located near the Fuel Farm have been the subject of previous investigations conducted
under an Activity-wide UST program. The two USTs include a No. 6 fuel oil UST situated adjacent
to the former Mess Hall Heating Plant, and a No. 2 fuel oil UST situated adjacent to the Explosive
Ordnance and Disposal Armory, Office, and Supply Building. The former UST was abandoned in
place years ago (date unknown) and has been the subject of previous environmental investigations
performed by ATEC Associates, Inc. and Law. The latter UST was removed in January 1994, and
is the UST associated with the fourth area of soil contamination identified in the previously
mentioned Interim ROD, signed September 1994. The area from which this latter UST was removed
is reported to be scheduled for an upcoming comprehensive environmental investigation.

3.0    HIGHLIGHTS OF COMMUNITY PARTICIPATION

The Final Interim Proposed Remedial Action Plan (PRAP) for surficial groundwater at Site 35 was
released to the public on May 9, 1995. These documents were made available to the public at the
information repository maintained at the Onslow County Library and Building 67, MCB, Camp
Lejeune.  The notice of availability of these documents was published in The Jacksonville Daily
News in the form of a display  ad on April 29, 1995 and a legal ad on May 3,  1995. A public

-------
comment period was held from May 10 to June 10, 1995. In addition, a public meeting was held on
May 10, 1995. At this meeting representatives from DON/Marine Corps were available to discuss
the remedial  action alternatives (RAAs) currently under consideration and address community
concerns.  However, no members of the community turned out for the meeting. Responses to the
comments received during the comment period are included in the Responsiveness Summary, which
is part of this  ROD (Section 11.0).

This decision document presents the five RAAs which were considered.  RAA 5 has been selected
for the remediation of organic chemical contaminated surficial groundwater at Site 35.  This RAA
has been chosen in accordance with the Comprehensive Environmental Response, Compensation
and Liability Act (CERCLA), as amended by the Superfund Amendments and Reauthorization Act
(SARA) and,  to the extent practicable, the NCP. The selected RAA for surficial groundwater at
Site 35 is based on the  Administrative  Record.

The viability of in well  aeration technology (RAA 5) at Camp Lejeune will be determined by means
of a field pilot test scheduled to be initiated in October 1995. A Draft Report of results will be
available in May 1996.  Additionally, the field pilot test will provide important data to support the
full design of this alternative. If it is determined, based on the results of the field pilot test, that in
well aeration cannot perform as required, RAA 3 (Groundwater Collection and On-Site Treatment)
will be selected as the Interim Preferred Remedial Action.

4.0    SCOPE AND  GOALS OF INTERIM REMEDIAL ACTION

The response action presented in this document is interim in nature  because it represents only one
phase of a comprehensive investigation and remediation at Site 35 and is not intended to represent
the final solution for OU No. 10. This particular interim action focuses on organic groundwater
contamination in the surficial  aquifer located in the vicinity of the Fuel Farm and extending
downgradient towards Brinson Creek. A remediation system installed in this area would be designed
to mitigate the migration of groundwater contamination from OU No. 10 prior to its discharge into
Brinson Creek.

Other media of concern such as sediment, and groundwater in the upgradient portion of the surficial
aquifer, will be addressed during subsequent RI/FS activities that are due to commence later in 1995.
Soil contamination at Site 35 was the focus of an Interim Remedial Action document that was issued
by Baker on August 31,1994.

-------
The scope and goals  for the remediation of organic chemical contaminated groundwater were
developed based on North Carolina Water Quality Standards (NCWQS).  In the Interim Feasibility
Study, which addressed contaminated surficial groundwater at Site 35, risk-based cleanup goals were
established. These goals were then compared toTederal Maximum Contaminant Levels (MCLs)
and NCWQS, and the most conservative value for each contaminant was selected as the remediation
goal. In each case, the most conservative criteria was the NCWQS. The remediation goals for the
organic contaminants of concern are listed below:

       •      Benzene                     1 ug/L
       •      Trichloroethene               2.8 ug/L
       •      cis-l,2-dichJoroethene         70 ug/L
       •      trans- 1,2-dichloroethene       70 ug/L
       •      Ethyl benzene                29 ug/L
       •      Methyl Tertiary Butyl Ether    200 ug/L
       •      Xylenes                      530 ug/L

5.0    SITE CHARACTERISTICS

This section of the Interim ROD  presents an overview of the nature and extent of surficial
groundwater contamination in the vicinity of the Fuel Farm at Site 35.  The nature and extent of
contamination was determined based on the analytical results obtained under the RI (Baker, 1994).

Groundwater contamination was observed in the surficial aquifer along both the upper and lower
monitored intervals.  Fuel-related organic contaminants (e.g., BTEX), when encountered, appear
more prevalent in the upper portion of the surficial aquifer. Conversely, solvent-related organic
contaminants (e.g., TCE), when encountered, appear more prevalent in the lower portion of the
surficial  aquifer. This is likely due to the fact that the latter type of contaminants have  specific
gravities greater than water and tend to "sink" while fuel-related contaminants have specific gravities
less than water and tend to "float".

The extent of fuel-related contamination appears to be adequately defined based on the data obtained
to date. Fuel-related contaminants  are present in the area north of Fourth Street in the vicinity of
obvious suspected sources such as the Fuel Farm, and nearby former UST sites. The limits of fuel
related contamination are depicted in Figures 3 and 4.

-------
There are four distinct plumes of groundwater contamination in the upper portion of the surficial
aquifer. The most northern plume is located immediately east of F Street and north of the ASTs at
Site 35. The easternmost plume is north of Building TC474 and east of the ASTs. The westernmost
plume is in the vicinity of building G480 and the football field.  The southernmost portion of this
plume has not been adequately defined (see Figures 3 and 5).

Groundwater contamination in the lower portion of the surficial aquifer consists of two separate
plumes that conglomerate into a single plume. The easternmost plume is centered roughly under
Buildings TC474, TC473, and TC470.  The westernmost plume is south of Fourth Street and
centered directly under E Street. The southernmost boundary of this conglomerate plume has not
been adequately delineated (see Figures 4,5 and 6).  Additional investigations are planned to further
evaluate the extent of this contamination.

Other medias of concern such as sediment and groundwater in the upgradient portion of the surficial
aquifer will be addressed as part of a Supplemental Groundwater Investigation to be initiated in
December 1995.  Soil  contamination at Site 35 was the focus of an Interim Remedial Action
document that was issued by Baker on August 31,1994.

6.0    SUMMARY OF SITE RISKS

Baseline Human Health Risk Assessment

A baseline human health risk assessment (BRA) was performed as part of this study utilizing the
data obtained under the RI field investigation. Contaminants of potential concern (COPC) for the
BRA were selected for each media as shown in Table 1.

The BRA highlights the  media of interest from the human health standpoint at OU No.  10  by
identifying areas with  elevated Incremental Cancer Risk (ICR) and Health Index (HI) values.
Current and future potential receptors at the site include current military personnel, future residents
(i.e., children and adults), and future construction workers.  The total risk from each site for these
receptors was estimated by logically summing the multiple exposure pathways likely to affect the
receptor during a given activity.  The risk to human health was derived based on the following
receptors and contaminant exposure routes:
                                           8

-------
1 .      Current Military Personnel

       a.      Incidental ingestion of COPC in surface soil + dermal contact with COPC
               in surface soil + inhalation of airborne COPC

2.      Future Residents (Children and Adults)

       a.      Incidental ingestion of COPC in surface soil + dermal contact with COPC
               in surface soil + inhalation airborne of COPC

       b.      Ingestion  of COPC  in groundwater + dermal contact with COPC in
               groundwater + inhalation of volatile COPC

3.      Future Construction Worker

       a.      Incidental ingestion of COPC in on-site subsurface soil + dermal contact
                                   ce soil + inhalation of airborne COPC
                      v/:th CCPC ir. 3ub-
       4.     Current Residents (Children and Adults)

              a.      Ingestion of COPC in surface water and sediment + dermal contact with
                      COPC in surface water and sediment

              b.      Ingestion offish tissue (adults only)

The total site ICR and HI values associated with current and future receptors at this site are
presented in Table 2.  The total site ICR estimated for future residential children (2.0E-03) and
adults (4.3E-03) exceeded the USEPA's upper bound risk range (1E-04).  The total  site ICR
estimated value for the current residential child .(3.0E-07) is below the USEPA's upper bound risk
range, while the current residential adult (1 .4E-04) is slightly above the risk range (1E-04 to 1E-06).
The total site ICR estimated for future construction workers (1E-07) was less than the USEPA's
lower bound target risk (1E-06). The total site ICR estimated value for current military personnel
(3.2E-06) is within the USEPA's risk range (1E-04 to 1E-06).  Additionally, USEPA  guidance
provides for a maximum HI value of 1 .0. The total site HI for future residential children (65) and
adults (28) exceed unity (i.e., 1 .0).  The total site HI for current residential child (2.4E-02) is less

-------
than unity, while the total site HI for the current residential adult (3.5) is greater than unity. The
total site HI estimated for the future construction worker (1.7E-02) did not exceed unity.  Finally,
the total site HI for the current military personnel (1 .OE-01) did not exceed unity. The total site risk
was driven by future potential exposure to groundwater contaminated with cis-l,2-dichloroethene,
trichloroethane, benzene, antimony, arsenic, barium, beryllium, chromium, cadmium, manganese,
and vanadium; and current potential exposure to fish due to mercury.

Ecological Risk Assessment

As part of this study an ecological risk assessment (ERA)  was conducted to assess the potential
impacts to ecological receptors from contaminants  detected at Site 35. Additional data obtained
along Brinson Creek from Site 36, located downstream of Site 35, was also used in the ERA.

Similar to the BRA, COPC were selected for the media considered in the ERA. These media include
sediment, surface water, surface soil, and biota.

Overall, metais and pesticides appear to be the most significant site related COPCs that have the
potential to affect the integrity of the aquatic and terrestrial receptors at OU No. 10. Although the
American alligator and red-cockade woodpecker have been  observed at OU No. 10, potential
adverse impacts to these threatened or endangered species  are low due to the low levels of
contaminants in their critical habitats.

Aquatic Ecosystem

Surface water quality showed exceedances of aquatic reference values for lead, mercury, and zinc.
For sediments, concentrations of lead and the organics dieldrin, 4,4'-DDD, 4,4'-DDE, 4,4'-DDT,
endrin, alpha-chlordane, and gamma-chlordane exceeded the  aquatic reference values. In the surface
water, mercury exceeded aquatic reference values in the upstream stations. Although these levels
were indicative of a high potential for risk (QI > 100), mercury is not believed to be site related.
Zinc exceeded unity slightly and was only found at a single station. Lead has a single exceedance
of the aquatic reference value by slightly greater than 10 indicating a moderate potential for risk to
aquatic receptors.

In the sediments, lead exceeded the lower  sediment aquatic reference value throughout Brinson
Creek. The only exceedances of the higher sediment aquatic reference value occurred downstream

                                           10

-------
of Site 35 with the highest QI of 137 representing a high potential for risk to aquatic receptors. The
lead detected in sediments is likely site related, the result of past reported surface spills/runoff and
past and ongoing groundwater discharges to surface water.   Pesticides exceeded the sediment
aquatic reference values throughout Brinson Creek.  The highest QI, 2,600 for dieldrin, represents
a high potential for risk to aquatic  receptors.  There is no documented pesticide  disposal  or
storage/preparation activities at Site 35.  The pesticide levels detected in the sediments probably are
a result of routine application (i.e., pest control) in the general vicinity of Site 35.

Although the pesticides in the sediments were found at levels indicating contamination throughout
the  watershed, the highest levels were observed in the lower reaches of Brinson Creek,  This
deposition trend may be related to the higher organics in the sediments in the lower reach, which
would accumulate more of these types of contaminants.

The fish community sampled  in Brinson Creek was representative of an estuarine ecosystem with
both freshwater and marine species present. In addition, the presence of blue crabs, grass shrimp,
and crayfish support the active use of Brinson Creek by aquatic species.

The absence of pathologies observed in the fish  collected from Brinson Creek indicates that the
surface water and sediment quality does not adversely impact the fish community.

The benthic macroinvertebrate community demonstrated the typical tidal/freshwater species trend
of primarily chironmids and oligochaetes in the upper reaches and polychaetes and amphipods in
the  lower reaches. Species representative of both tolerant and intolerant taxa were present.  Species
richness and densities were representative of an estuarine ecosystem.

In summary, the aquatic community in Brinson Creek was representative of an estuarine community
and does not appear to be adversely impacted by surface water and sediment quality.

Terrestrial Ecosystem

Surface soil quality indicated an infrequent potential for adversely impacting the terrestrial receptors
that have indirect contact with the surface soils. This adverse impact is primarily due to arsenic and
chromium concentrations in the surface soils. For the larger receptors (rabbit, raccoon, and quail)
the terrestrial reference values exceeded unity only .slightly.  Therefore, there is no significant
adverse impact to terrestrial receptors from site-related contaminants.

                                            11

-------
7.0    DESCRIPTION OF ALTERNATIVES

Numerous technologies and process options were screened and evaluated under the Interim FS.
Based upon screening criteria, many of the technologies and process options were eliminated.
Ultimately, five RAAs were developed with the following titles:

       •      RAA 1 - No action
       •      RAA 2 - No Action with Institutional Controls
       •      RAA 3 - Groundwater Collection and On-Site Treatment
       •      RAA 4 - In Situ Air Sparging and Off-Gas Carbon Adsorption
       •      RAA 5 - In Well Aeration and Off-Gas Carbon Adsorption

A brief description of each alternative, as well as the estimated cost and timeframe to implement the
alternative, are as follows:

       •      RAA 1 - No Action
               Capital Cost: $0
               Annual Operation and Maintenance (O&M):  $0
               Total Net Present Worth (30 Years): $0
               Months to Implement: 0

               Under  RAA 1, no  remedial actions will be performed to reduce the toxicity,
               mobility, or volume of the contaminated surficial groundwater at Operable Unit
               No. 10. This method assumes  that passive remediation will occur via natural
               attenuation processes and that the contaminant levels will be reduced over an
               indefinite period of time.  However, the achievable reductions versus  time  is
               difficult, if not impossible, to predict.

               The No Action RAA is required by the NCP to provide a baseline for comparison
               with other alternatives.  Since contaminants will remain at the site under this
               alternative, DON is required by the NCP [40 CFR 300.430(f)(4)] to  review the
               effects of this alternative no less often than every five years after initiation of the
               selected remedial action.
                                           12

-------
RAA 2 - No Action with Institutional Controls
Capital Cost: $6,200
Annual Operation and Maintenance (O&M) Costs: $19,100
Total Net Present Worth (30 years):  $299,800
Months to Implement: 1

Under RAA No.2, no remedial actions will be performed to reduce the toxicity,
mobility, or volume of the contaminated surficial groundwater at Operable Unit
No. 10. This RAA assumes that the Base Master Plan will be modified to include
restrictions on the use of the surficial aquifer in  the vicinity of the Fuel  Farm.
These  institutional  controls will reduce  the risk  to human  health and the
environment posed by eliminating potential  exposure to shallow groundwater;
however, without additional remediation the contaminated surficial groundwater
will remain a future source of contamination  for Brinson Creek via groundwater
discharge.

In addition to aquifer-use  restrictions, long-term  groundwater monitoring is
included under tins KAA to provide data regarding the impact of natural attenuation
and the progress  of contaminant migration. Long-term groundwater monitoring
will include: the semi-annual collection and analysis (TCL VOCs) of groundwater
samples from 11 monitoring wells; the development of a semi-annual monitoring
report; and the replacement of one monitoring well every five years.

Since contaminants will remain at the site under this alternative, the DON is
required by the NCP [40 CFR 300.430(f)(4)] to review the effects of this alternative
no less often than every five years after initiation of the selected remedial action.
RAA 3 - Groundwater Collection and On-Site Treatment
Capital Cost: $2,122,700
Annual Operation and Maintenance (O&M) Costs: $57,100
Total Net Present Worth (30 years):  $3,000,500
Months to Implement: 3

RAA 3 is a source'collection and  treatment alternative; the source being the
contaminated surficial groundwater in the vicinity of the Fuel Farm at Operable
                            13

-------
Unit No. 10. Under this alternative a vertical interceptor trench will be installed at
the downgradient edge of the contaminated plume in the area between the proposed
highway and Brinson Creek (see Figure 7). The interceptor trench will extend from
the ground surface to the semi-confining layer at the base of the surficial aquifer
(see  Figure 8).  The purpose of the interceptor trench is to collect contaminated
surficial groundwater for transfer to an on-site treatment facility prior to it being
discharged to Brinson Creek.

The  type of interceptor trench proposed under RAA 3 is termed a "biopolymer
slurry drainage trench."  This type of trench can be installed without dewatering or
structural bracing. Through the use of a natural,. biodegradable slurry, the wails of
a trench excavation can be supported  and the trench can be installed without
personnel entering an excavation.  Compared to  other trenching methods, this
technique is safer and more cost-effective in areas with a high groundwater and
unstable soil because dewatering and shoring are not required.
The interceptor Lcucli will be uc&igneu 10 coiiecv groundwater at a rate roughly
equal to the rate of groundwater flow (5 to 10 gpm) across the upgradient face of
the trench (3 1,900 square feet). Flow across the downgradient face of the trench
will be restricted by an impermeable geomembrane barrier. Drawdown of the
groundwater surface will be minimized so as to mitigate the potential of excessive
ground settlement beneath the highway.  The collected groundwater will  be
conveyed to an on-site treatment system located just east of the proposed highway
right-of-way, creek-side, where it appears that adequate space and firm ground is
available.

Baker, LANTDIV, and MCB, Camp Lejeune  will negotiate  with NC DOT
regarding the specifics of site access to the creek side of the new highway. EPA
and NC DEHNR will be kept abreast of developments regarding this subject.  In
this Interim ROD, Baker proposes an access road running parallel to the east side
of the highway from the south.

The collected groundwater will be treated sufficiently to allow for its discharge to
Brinson Creek at a point downstream of OU No.  10.  It is anticipated that the
groundwater treatment system will include filtration for the removal of suspended
                            14

-------
solids, precipitation for the removal of inorganics, sludge collection and disposal,
volatilization (air stripping)  for the removal of volatile organic contaminants
(VOCs), and secondary treatment of VOC emissions from the air stripper and of the
treated groundwater (i.e., via earbon adsorption).   Figure  9 is a process flow
diagram of this treatment train. The treatment plant effluent will be sampled once
a month to insure that water discharged to Brinson Creek meets all applicable water
quality standards.

RAA 3 assumes that the Base  Master Plan will be modified to include restrictions
on the use of the surficial aquifer in the vicinity of the Fuel Farm. This institutional
control will reduce the  risk to human health and the environment posed by this
media by eliminating potential exposure to shallow groundwater.

In addition to aquifer-use restrictions, long-term groundwater monitoring is to be
included under this RAA to provide data regarding the-impact of natural attenuation
and the progress of contaminant migration. Long-term groundwater monitoring
will include: the semi-annual  collection ««iiU analysis (TCL VOCs) ofgioundwater
samples from 11 monitoring wells; the development of a semi-annual monitoring
report; and the replacement of one monitoring well every five years.

Since contaminants will remain at the site under this alternative,  the DON is
required by the NCP [40 CFR  300.430(f)(4)] to review the effects of this alternative
no less often than every five years after initiation of the selected remedial action.
RAA 4 - In Situ Air Sparging And Off-Gas Carbon Adsorption
Capital Cost: $1,068,400
Annual Operation and Maintenance (O&M) Costs: $90,100
Total Net Present Worth (30 years): $2,459,600
Months to Implement: 3

In situ air sparging (IAS) is a technique in which air is injected into water saturated
zones for the purpose of removing organic contaminants primarily via volatilization
and  secondarily, via  aerobic  biodegradation.    IAS  systems   introduce
contaminant-free air  into an  impacted aquifer  near the base of the zone of
                             15

-------
contamination, forcing contaminants to transfer from the groundwater into sparged
air bubbles.  The air bubbles are then transported into soil  pore spaces in the
unsaturated zone where they are typically collected via soil vapor extraction (SVE)
and conveyed to an above-ground off-gas treatment system.

An IAS system typically is comprised of the following components: 1) air injection
wells;  2) an  air  compressor; 3)  air extraction wells;  4)  a vacuum  pump;
5) associated piping and valving for air conveyance; and 6) an off-gas treatment
system (e.g., activated carbon, combustion, or oxidation). Under RAA 4, a line of
air sparging wells will be installed between the proposed highway  and Brinson
Creek in order to treat and contain the contaminant plume near its downgradient
extreme.  Based on empirical data from similar sites, the radius of influence of an
air sparging well ranges from five to almost 200 feet, but is typically on the order
of 25 feet (EPA, 1992).  The proposed off-gas treatment  system, consisting
primarily of activated carbon units,  will be located just east of the proposed
highway right-of-way, creek-side, where it appears that there is adequate space and
firm foundation material available.  The air emissions from the off-gas treatment
system will be sampled monthly to insure that all applicable air emissions standards
are being met.

Air sparging systems are most effective in sandy soils,  but can be adversely
impacted by high levels of inorganic compounds in the groundwater which oxidize
and precipitate when contacted by the sparged air. These inorganics can form a
heavy scale on well screens and clog the well space of the sand pack surrounding
the well  screen resulting in a reduction in permeability.  A field  pilot test is
recommended to determine the loss of efficiency over time as a result of inorganics
precipitation and oxidation, the radius of influence of the wells under various heads
of injection air pressure, and the  rate of off-gas organic contaminant removal via
carbon adsorption and carbon breakthrough.

Baker, LANTDIV, and  MCB,  Camp  Lejeune will  negotiate with NC DOT
regarding the specifics of site access to the creek side of the new highway.  EPA
and NC DEHNR will be kept abreast of developments regarding this subject. In
this Interim ROD, Baker proposes an access road running parallel to the east side
of the highway from the south.
                             16

-------
RAA 4 assumes that the Base Master Plan will be modified to include restrictions
on the use of the surficial aquifer in the vicinity of the Fuel Farm.  This institutional
control will reduce the risk to human health and the environment posed by this
media by eliminating potential exposure to contaminated shallow groundwater.

In addition  to aquifer-use restrictions, long-term groundwater monitoring is to be
included under this RAA to provide data regarding the impact of natural attenuation
and the progress of contaminant migration.  Long-term groundwater monitoring
will include: the semi-annual collection and analysis (TCL VOCs) of groundwater
samples from 11 monitoring wells; the development of a semi-annual monitoring
report; and  the replacement  of one monitoring well every five years.

Since contaminants will remain  at the site under this alternative, the DON is
required by the NCP [40 CFR 300.430(f)(4)] to review the effects of this alternative
no less often than every five years after initiation of the selected remedial action.
RAA 5 - In Well Aeration and Off-Gas Carbon Adsorption
Capital Cost: $1,248,300
Annual Operation and Maintenance (O&M):  $82,320
Total Net Present Worth (30 years):  $2,519,700
Months of Implementation: 3

In well  aeration is a new technology that utilizes circulating air flow within a
groundwater well that, in effect, turns the well into an air stripper. In well aeration
differs from air sparging in that volatilization occurs  outside the well  via air
sparging and within the well via aeration. Similar to air sparging, this technique
removes organic contaminants from groundwater primarily via volatilization and
secondarily via aerobic biodegradation.  Under RAA 5, a line of in well aeration
wells will be installed between the proposed highway and Brinson Creek in order
to treat and contain the contaminated plume near its downgradient extreme (see
Figure 10).

The radius of influence of an in well aeration well is reportedly much greater than
a typical air sparging well system. At Site 35, the radius of the influence has been
calculated  by the technology's developers  to be over  100 feet.  The radius of
                             17

-------
influence is based upon site-specific geological and hydrogeological parameters.
Volatilized organic contaminants collected by the in well aeration system, unlike
air sparging, will be conveyed to independent carbon adsorption units placed
adjacent to each well system (see Figure 11). The air emissions from the off-gas
treatment system will be sampled monthly to insure that all applicable air standards
are met.  Each well and above-ground off-gas treatment system will be housed in
a small prefabricated building.

In well aeration systems, like IAS systems, are most effective in sandy soils, but
can  be adversely impacted  by high levels of inorganic compounds in the
groundwater which oxidize and precipitate when contacted by air. These inorganics
can form a heavy scale on well screens and clog the well space of the sand pack
surrounding the well screen resulting in a reduction in permeability.  The results of
a field pilot test will help determine the loss of efficiency over time as a result of
inorganics precipitation and oxidation, the radius of influence of the wells under
various heads of injection air pressure, and the rate of off-gas organic contaminant
removal via carbon adsorption and carbon breakthrough.

Baker, LANTDlV, and  MCB, Camp  Lejeune  will negotiate with NC DOT
regarding the specifics of site access to the creek side of the new highway.  EPA
and NC DEHNR will be kept abreast of developments regarding this subject.  In
this Interim ROD, Baker proposes an access road running parallel to the east side
of the highway from the south.

RAA 5 assumes that the Base Master Plan will be modified to include restrictions
on the use of the surficial aquifer in the vicinity of the Fuel Farm. This institutional
control will reduce the risk to human health and the environment posed by this
media by eliminating future potential exposure to shallow groundwater.

In addition to aquifer-use restrictions, long-term groundwater  monitoring is
included under this RAA to provide data regarding the impact of natural attenuation
and the progress of contaminant migration. Long-term groundwater monitoring will
include:   the semi-annual collection and analysis  (TCL VOCs) of groundwater
samples  from 11 monitoring wells; the development of a semi-annual monitoring
report; and the replacement of one monitoring well every five years.
                             18

-------
              Since contaminants will remain at the site under this alternative, the DON is
              required by the NCP [40 CFR 300.430(f)(4)] to review the effects of this alternative
              no less often than every five years after initiation of the selected remedial action.

8.0    SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

A detailed analysis was performed on the RAAs using the nine evaluation criteria in order to select
a site remedy. A brief summary of each alternative's strengths and weaknesses with respect to the
evaluation criteria follows. (Table 3 presents a complete summary of the alternatives evaluation;
Table 4 provides a glossary of the evaluation criteria.)

Overall Protection of Human Health and the Environment

RAA 1 (No Action) and RAA 2 (No Action With Institutional Controls) are similar in that neither
alternative involves active treatment.  RAA 2 provides for some overall protection to human health
through the incorporation of aquifer-use restrictions which are not included under RAA 1.

RAA 3 (Groundwater Collection and On-Site Treatment), RAA 4 (In Situ Air Sparging And Off-Gas
Carbon Adsorption), and  RAA 5 (In Well  Aeration And Off-Gas Carbon Adsorption)  have a
common element in that each is intended to reduce groundwater contamination at the downgradient
extreme of the contaminated plume and to serve as a barrier to future contaminated groundwater
discharge to Brinson  Creek. RAA 3 would likely be the most effective barrier in that it is designed
to span the entire length and depth of the contaminated portion of the surficial aquifer and will be
equipped with an  impermeable geomembrane along its downgradient face.  RAA 3 is the only
treatment alternative that  will impact both organic and inorganic contaminants which could be
important if it is determined in the future that inorganic contaminants in groundwater are still a
concern.

Compliance With ARARs

RAA 1 (No action) and RAA 2 (No Action With Institutional Controls) are no action alternatives
that will not comply with ARARs. RAA 3 (Groundwater Collection and On-Site Treatment), RAA 4
(In Situ Air Sparging And Off-Gas Carbon Adsorption), and RAA 5 (In Well Aeration And Off-Gas
Carbon Adsorption)  are primarily source control measures that will reduce contaminant levels over
a limited area defined as the particular zone of influence of each system.
                                          19

-------
 Wetlands disturbance will be an issue with RAA 3, 4, and 5, but, most significantly with RAA 3
 which includes the excavation of an approximately two-foot wide, by 30-foot deep, by 1,080-foot
 interceptor trench. The disturbance associated with RAA 4 and 5 is limited primarily to drilling and
 well installations, although of the two, RAA 4 wiH have the greater impact due to the large number
 of wells to be installed.

 Treated air and groundwater discharge are provisions of RAA 3, whereas, only air emissions are a
 part of RAA 4 and 5. These discharges will need to comply with applicable ARARs.

 Long-Term Effectiveness and Permanence

 In the case of all five RAAs, contamination will remain at the site and require the DON to review
 the effectiveness of the alternative on a five-year basis.  RAA 1 (No Action) and RAA 2 (No Action
 With Institutional Controls) provide for no active means of contaminant reduction although, under
 RAA 2, aquifer-use restrictions will provide a permanent means for protection against direct human
 exposure to the contaminated surficial groundwater.

The effectiveness of RAA 3 (Groundwater Collection and On-Site Treatment), RAA 4 (In Situ Air
 Sparging And Off-Gas Carbon Adsorption), and RAA 5 (In Well Aeration and Off-Gas Carbon
Adsorption) can be assumed to be roughly equivalent without the benefit of the results of field pilot-
 scale testing. RAA 3 may be the most difficult of the three to install, however, once installed it will
 likely be the most reliable and easiest to control. RAA 4 and 5 may encounter clogging problems
 if dissolved metals precipitate out of solution when placed in contact with forced air. At a minimum
the metals problem  will prompt  increased maintenance which could lead  to complete well
 replacement. RAA 4 has the additional problem of releasing toxic vapors to the atmosphere during
operation because it is difficult to apply sufficient vacuum to the vadose zone where the groundwater
 surface is within a few feet of the ground surface.

 Reduction of Toxicity, Mobility, or Volume Through Treatment

 No reduction of contaminants will occur under RAA 1 (No Action) and RAA 2 (No Action With
 Institutional Controls) as the result of active treatment because active treatment is not provided for
 under these RAAs.
                                           20

-------
RAA 3 (Groundwater Collection and On-Site Treatment) provides for on-site treatment of the
collected contaminated groundwater (organics and inorganics) using standard wastewater treatment
technology. Conversely, RAA 4 (In Situ Air Sparging And Off-Gas Carbon Adsorption) and RAA 5
(In Well Aeration And Off-Gas Carbon Adsorption) provide for treatment of the organic phase of
contaminated groundwater in-situ. Both RAA 4 and 5 primarily utilize volatilization technology and
biodegradation technology secondarily. The  principle difference between the two is that under
RAA 4, both volatilization and biodegradation occur outside the well and within the soil column.
Under RAA 5, volatilization occurs within the well while biodegradation occurs outside the well
within the soil column. Under RAA 4, it may be difficult to efficiently collect all of the volatilized
organic contaminants via conventional soil vapor extraction because of the proximity  of the
groundwater surface to the ground surface at this site. Without an efficient means of collecting the
volatilized organics under RAA 4, toxic vapors may be released to the atmosphere. The zone of
influence of an air sparging system may also be significantly reduced due to vapor extraction wells
only four to five feet deep, the depth of groundwater. Vapor extraction wells this close to the ground
surface may short circuit and actually draw in air from the atmosphere. Under RAA 5 these are not
of concern because the volatilization is conducted within the well and vapors are conveyed to
activated carbon  via piping which means the system is  essentially a closed ioop.

RAA 3 will produce the highest volume of residual waste during operation because it is the only
alternative involving groundwater treatment. However, the volume of air treatment under RAA 3
will  be less than that under RAAs 4 and 5 because  the latter  are specifically  designed as air
volatilization systems. Under RAAs 4 and  5  a small volume of contaminated  water will be
generated because extracted air contains water which condenses and collects in a knock-out tank at
the treatment facilities.

Short-Term Effectiveness

Worker protection against exposure will not be a significant issue for any of the RAAs. Each system
provided for under RAA 3 (Groundwater Collection and On-Site Treatment), RAA 4 (In Situ Air
Sparging and Off-Gas Carbon Adsorption), and RAA 5 (In Well Aeration and Off-Gas Carbon
Adsorption) will require approximately 30 to 60 days  to install with the total time  in the field for
construction being a little  longer.  It has also  been  assumed  that system start-up and  testing
operations will require an additional 90 days.
                                           21

-------
Under RAA 1 (No Action) and RAA 2 (No Action With Institutional Controls) there will be no
increase in the risks to the community resulting from implementation of the RAA. RAAs 3 and 5
will likely present minimal risk of community exposure during implementation and operation
because they are, in essence, closed loop systems.  RAA 4 has the potential for releases of toxic
vapors to the atmosphere because of close proximity of the groundwater surface to the ground
surface will make efficient soil vapor extraction difficult.

Some disturbance of the wetlands is expected under RAAs 3,4, and 5. The greatest disturbance will
be associated with RAA 3.

Implementabiiity

Aside from RAAs 1  and 2, which  are essentially no action alternatives, RAA 3 (Groundwater
Collection And On-Site Treatment) will present greater technical challenges during construction
than RAA 4 (In Situ Air Sparging and Off-Gas Carbon Adsorption) arid RAA 5 (In Well Aeration
and Off-Gas Carbon Adsorption). This is because RAA 3 involves the construction of a two-foot
wide by 30-toot deep by 1,080 root long interceptor trench while RAAs 4 and 5 involve primarily
well installation.

The interceptor trench  under RAA  3 represents specialized technology that is available from  a
limited number of vendors,  whereas,  the air sparging technology  of RAA 4 is relatively
commonplace and in well aeration (RAA 5) is a relatively new technology offered by a few vendors
in the United States.  Two of these companies are IEG Technologies Corporation and EG&G
Environmental.

The proposed  groundwater monitoring plan coupled with routine  system  maintenance  and
monitoring should be sufficient to provide sufficient notice of a system failure under either RAA 3,
4 or 5. The purpose of the monitoring is to provide for system adjustments with sufficient time so
that a significant contaminant release to the environment will not occur.

Because each system under RAA 3, 4, and 5 will require construction within a wetlands area and
because  air and water discharges  are incorporated into  the designs, federal  and state agency
interaction will be required.
                                           22

-------
Cost
The estimated total present worth costs of the alternatives, excluding RAA 1 - No Action, range
from  $299,800  for RAA 2 .- No Action with  Institutional  Controls  to  $3,000,500 for
RAA 3 - Groundwater Collection and On-Site Treatment.  These costs are based on the assumption
of 30 years of active use. The ranking of the alternatives in terms of costs is as follows:

RAA   1 - No Action                                                               $0
RAA   2 - No Action with Institutional Controls                                  $299,800
RAA   4 - In Situ Air Sparging and Off-Gas Carbon Adsorption                   $2,459,600
RAA   5 - In Well Aeration and Off-Gas Carbon Adsorption                      $2,519,700
RAA   3 - Groundwater Collection and On-Site Treatment                        $3,000,500

Figure 12 graphically displays a comparison of costs for RAAs 2, 3, 4, and 5.

USEPA/State Acceptance

The USEPA and NC DEHNR are in favor of either RAA 3 or 5 since both alternatives involve
treatment and containment of the plumes leading edge.

Community Acceptance

Community acceptance is difficult to evaluate since public interest in  Site 35 is minimal. It can,
however, be assumed that the community wouldnot object to interim treatment of a grounidwater
condition that is impacting Brinson Creek.

9.0    SELECTED REMEDY

The interim preferred remedial action alternative is RAA 5 (In Well Aeration and Off-Gas Carbon
Adsorption). The following paragraphs describe the process by which RAA 5 was selected over
RAAs 1, 2, 3, and 4. This process involved a comparison/contrast evaluation of the five RAAs
based on seven criteria:  overall protectiveness, compliance with ARARs, long-term effectiveness/
permanece, reduction of toxicity, mobility, or volume through treatment, short-term effectiveness,
implementabilty, cost, USEPA/State acceptance, and community acceptance. (Table 3 presents a
                                          23

-------
complete summary of the alternatives evaluation; Table 4 provides a glossary of the evaluation
criteria).

RAA 1 (No Action) and RAA 2 (No Action With Institutional Controls) are no action alternatives;
RAA 3 (Groundwater Collection and On-Site Treatment), RAA 4 (In Situ Air Sparging and Off-Gas
Carbon Adsorption), and RAA 5 (In Well Aeration and Off-Gas Carbon Adsorption) are source
control alternatives. RAAs 3,4, and 5 are preferred over the no action alternatives because source
control alternatives are more effective at complying with ARARs achieving remediation goals,
contributing to the overall protection of human health and the environment, and achieving a
permanent reduction in toxicity, mobility, and volume of waste.

Of the three source control alternatives, RAA 3 is the most difficult to implement because it involves
constructing a large permeable trench (approximately 2 feet wide, by 30 feet deep,  by 1,080 feet
long) in the soft ground of a wetlands area. RAA 4 and RAA 5, on the other hand, have similar
implementability ratings because the major construction activity, in both cases, involves the drilling
and installation of multiple vertical wells.  Since well installation at OU No. 10 has been  executed
successfully in the past, RAAs 4 and 5 should be relatively easy to implement compared to RAA 3.

Despite its more difficult implementability, RAA 3 would likely be the easiest alternative to operate
and maintain because it involves fewer operable components than RAAs 4 and 5.  Additionally,
under RAAs 4 and 5, high metals in the groundwater could precipitate and oxidize easily because
these RAAs involve in situ aeration. The process could clog the well screens which would require
frequent maintenance or even well replacement.

Both RAA  3 and RAA  5 performed well under the short-term and long-term effectiveness/
performance evaluation. RAA 4, however, did not perform well.  When the groundwater surface
is within several feet of the  ground surface, like it  is at OU No. 10, vapor extraction (a main
component of RAA 4)  is difficult  to control and there is a risk of releasing toxic  vapors to the
atmosphere. Thus, RAA 4 could pose a risk to the community that RAAs 3 and 5 do not.

Under the final criterion, cost effectiveness, RAA 4 resulted  in the lowest net present worth,
$2,459,600, although the cost of RAA 5 is nearly the same, $2,519,700. RAA 3, however, requires
$3,000,500 which is roughly $500,000 more than RAAs 4 and 5. RAAs 4 and 5 are nearly tied as
the most cost effective alternatives with RAA 4 being slightly less expensive.
                                          24

-------
In conclusion, neither RAA 1 nor RAA 2 was selected to be the preferred alternative because of the
potential environmental impacts associated with a no action alternative. RAA 3 was not selected
because of its high cost and difficult implementability. Despite its similarities to RAA 5, RAA 4
was not selected because of the possible release of toxic vapors associated with vapor extraction at
Operable Unit No. 10. Thus, RAA 5, which is nearly the most cost effective alternative, was
selected as the interim preferred remedial action. Figure  10 presents a plan view of this interim
proposed remedial action.

The viability of in well aeration technology (RAA 5)  at Camp Lejeune will be determined by means
of a field pilot test scheduled to be initiated in September 1995. A Draft Report of results will be
available in February 1996. Additionally, the field pilot test will provide important design support
data.  If it is determined,  based on the results of the field pilot test, that in well aeration cannot
perform as required, RAA 3 (Groundwater Collection and On-Site Treatment) will be selected as
the Interim Preferred Remedial Action.

Remedy Description

The major components of RAA 5 include:

       •       Six aeration wells spaced at approximately 180 feet (center to center). These wells
               would be  installed in a line between the proposed highway and Brinson Creek.

       •       A submersible pump incorporated into each well. These pumps are placed near the
               bottom of the wells.  They draw in  contaminated groundwater and pump it to the
               stripping zone of the aeration system.

       •       An aeration system in each well. As water is pumped in from the bottom of the
               well, air is injected into the water allowing the VOCs to move from the dissolved
               phase to the vapor phase.  As the water is aerated, it is forced back out into the
               formation.

        •      A header  system that delivers pressurized air from the compressor/blowers at each
               well to the well heads.
                                           25

-------
        •      An air extraction  header system  that runs from the well heads to a carbon
               adsorption unit adjacent to the well.  This system is equipped with a vacuum
               pump(s) that draw VOC laden air from the wellheads to a carbon adsorption unit.

        •      Carbon adsorption units that adsorb vapor phase VOCs from the contaminated air
               prior to discharge to the atmosphere. These units along with the blowers, vacuum
               pumps and controls  will be housed in individual treatment buildings which will also
               enclose the in well aeration well heads.

        •      Each well head has an upper observation well (slightly above groundwater table)
               and a lower observation well below the groundwater table.

        •      Implementation of aquifer use restrictions.

        •      Long term groundwater monitoring.

Estimated Costs

The costs that will be incurred to implement RAA 5 are as follows:

        Capital Cost   -       $1,248,300
        Annual O&M   -          $82,320

The total net present worth (over 30 years) of these costs is $2,519,700. It is important to note that
the cost estimate was calculated for the FS evaluation and should not be considered a construction
quality estimate. An FS cost estimate should have an accuracy of +50 or -30 percent (EPA, 1988).

10.0    STATUTORY DETERMINATIONS

A selected remedy should satisfy the statutory requirements of CERCLA Section 121 which include:
(1) be  protective  of  human health and the  environment; (2)  comply  with ARARs; (3) be
cost-effective; (4) utilize permanent solutions and  alternative treatment technologies or resource
recovery technologies  to the maximum extent  practicable; and (5) satisfy the preference for
treatment that reduces toxicity, mobility, or volume as a principal element, or provide an explanation
                                           26

-------
as to why this preference is not satisfied. The evaluation of how RAA 5 satisfies these requirements
for Site 35 is presented below.

Protection of Human Health and the Environment

RAA 5 provides protection to human health and the environment through the in-situ remediation of
contaminated groundwater that exceeds state groundwater standard.  The potential risks associated
with exposure to surficial groundwater is eliminated under this alternative.

Compliance With Applicable or Relevant and Appropriate Requirements

RAA 5 will comply with ARARs identified in the FS.  Chemical-specific ARARs  include the
Federal Maximum Contaminant Levels (MCLs) and North Carolina Water Quality Standards for
Groundwater (NCWQS). Location-specific ARARs which are potentially applicable to OU No. 10
and therefore may require compliance from RAA 5 include: the Fish'and Wild Life Coordination
Act, the Federal Endangered Species Act, the North Carolina Endangered Species Act, Executive
Order 11990 on Protection of Wetlands, txecutive Order i 1988 on Fioodplain Management, and
RCRA Location Requirements. Action-specific ARARs which may be applicable to OU No. 10 and
RAA 5 are defined by the Resource Conservation Recovery Act, the Clean Water Act, the Clean Air
Act, the Safe Drinking Water Act, and the Department of Transportation.

Cost-Effectiveness

The selected remedy, RAA 5, has been evaluated to be the most cost-effective of the  alternatives
considered (exclusive of the no action alternatives).

Utilization of Permanent Solutions and Alternative Treatment Technologies

RAA 5 represents a permanent  treatment solution. That is, it utilizes, a permanent solution and
alternative treatment technology to the maximum extent practicable.

Preference for Treatment as a Principal Element

RAA 5 satisfies the preference for treatment as a principal element since the contaminated
groundwater exceeding the remediation goals will be treated in-situ.

                                          27

-------
11.0    RESPONSIVENESS SUMMARY

Overview

At the time of the public comment period (May 10 through June 10, 1995), the Department of the
Navy/Marine Corps had already selected a preferred alternative for the remediation of contaminated
groundwater at Operable Unit No. 10 (Site 35). The preferred alternative specified in the Interim
ROD is in well aeration and off-gas carbon adsorption.  This alternative involves the in-situ
treatment of contaminated surficial groundwater in the area between the highway right-of-way and
Brinson Creek.

No written comments were received during the public comment period or at the public meeting on
May 10, 1995. In addition, the EPA Region IV and the NC DEHNR are in support of the preferred
alternative. Based on the lack of public comments, it appears that there is no public opposition to
the preferred alternative.

Background On Community involvement

A record review of the MCB Camp Lejeune files indicates that the community involvement centers
mainly on a social nature, including the community outreach programs and base/community clubs.
The file search did not locate written Installation Restoration Program concerns of the community.
A review of historic newspaper articles indicated that the community  is interested in the local
drinking and groundwater quality, as well as that of the New River, but that there have been few
expressed interests or concerns specific to the environmental sites  (including Site 35).  Two local
environmental groups, the Stump Sound Environmental Advocates and the Southeastern Watermen's
Association, have posed questions to the  base and local officials in  the past regarding  other
environmental issues. These groups were sought as interview participants prior to the development
of the Camp Lejeune, IRP, Community Relations Plan.  Neither group was available for the
interviews.

Community relations activities to date are summarized below:

        •      Conducted additional community relations interviews, February through March
               1990.  A total  of 41 interviews were conducted with a  wide range  of persons
               including base personnel, residents, local officials, and off-base residents.

                                          28

-------
       •      Prepared a Community Relations Plan, September 1990.

       •      Conducted additional community relations interviews, August 1993.  Nineteen
              persons were interviewed, representing local business,  civic groups, on- and
              off-base residents, military and civilian interests.

       •      Prepared a revised Preliminary Draft Community Relations Plan, August 1993.

       •      Established two information repositories.

       •      Established the Administrative Record for all of the sites at the base.

       •      Released PRAP for public review in repositories, May 9, 1995 .

       •      Released public notice announcing public comment and document availability of
              the PRAP, April 29, 1995.

       •      Held Technical  Review Committee meeting, May 10, 1995, to review PRAP and
              solicit comments.

       •      Held  public meeting on  May 10,  1995,  to solicit comments and  provide
              information. No members of the community attended the meeting, consequently
              no transcript was prepared.

Summary of Comments Received During the Public Comment Period and Agency Responses

No comments to this document were received during the public comment period. No representatives
of the public at large attended the public meeting held on May 10, 1995.

12.0   REFERENCES

Baker.  1994a.  Baker Environmental, Inc.  Interim Remedial Action. Remedial Investigation.
Operable Unit No. 10. Site 35 - Camp Geiger Fuel Farm. Marine Corps Base, Camp Lejeune, North
Carolina.
                                         29

-------
Baker.  1994b.  Comprehensive Remedial Investigation Report. Operable Unit No.  10: Site 35 -
Camp Geiger Fuel Farm. Marine Corps Base, Camp Lejeune, North Carolina.

Baker. 1994c. Interim Feasibility Study for Surficial Groundwater. Operable Unit NO. 10. Site 35 -
Camp Geiger Fuel Farm. Marine Corps Base, Camp Lejeune, North Carolina.

ESE.   1990.  Final Site Summary Report. MCB Camp Lejeune.  ESE Project No. 49-02036,
September 1990.
Herrling, B., et al., "In Situ Bioremediation of Groundwater Containing Hydrocarbons, Pesticides,
or Nitrates Using Vertical  Circulation  Flows (UVB/GZB Technique)," Air Sparging for Site
Remediation.  Lewis Publishers, Boca Raton, Florida, 1994, pp. 56-80.

Law Engineering and Environmental Services.  1993. Addendum to Report of Underground Fuel
Investigation and Comprehensive Site Assessment. Camp Geiger Fuel Farm, Marine Corps Base,
Camp Lejeune, North Carolina.

Law.  1992. Final Report. Underground Fuel Investigation and Comprehensive Site Assessment.
Camp Geiger Fuel Farm.  Marine Corps Base, Camp Lejeune, North Carolina.

NC DEHNR.  1993.  North Carolina Department of Environment, Health, and Natural Resources.
Classifications and Water Quality  Standards Applicable to Surface Waters of North Carolina.
Administrative Code 15ANCAC.2B.0200. Division of Environmental Management, February 1993.

NUS Corporation. 1990.  Draft Field Investigation/Focused Feasibility Study. Camp Geiger Fuel
Spill Site. Camp  Lejeune. Onslow County. North Carolina.  NUS Project No. 2F37, December 1990.

USEPA. 1992. United States Environmental Protection Agency. A Technology Assessment of Soil
Vapor Extraction and Air Sparging.  Office of Research and Development.  Washington, D.C.,
EPA/600/R-92/173.  September 1992. p. 28.

USEPA.  1990.  United States Environmental Protection Agency.  National Oil and Hazardous
Substances Pollution Contingency Plan. 55 FR 8665. Office of Emergency and Remedial Response.
Washington, D.C. March 1990.

                                          30

-------
USEPA.   1988.  United States Environmental Protection Agency.  Guidance for Conducting
Remedial  Investigations and Feasibility Studies Under CERCLA.  Office of Emergency and
Remedial Response, Washington, D.C. EPA/540/G-89/004.

Water and Air Research, Inc. 1983.  Initial Assessment Study of Marine Corps Base Camp Lejeune.
North Carolina. Prepared for Naval Energy and Environmental Support Activity.
                                         31

-------
TABLES

-------
                      TABLE 1
SUMMARY OF COPCs IN ENVIRONMENTAL MEDIA OF CONCERN
            OPERABLE UNIT NO. 10 (SITE 35)
         INTERIM RECORD OF DECISION, CTO-0232
         MCB CAMP LEJEUNE, NORTH CAROLINA
Contaminant
1 , 1 ,2-Trichloroethane
1,1-Dichioroethane
1 , 1 -Dichloroethene
Benzene
cis- 1 ,2-Dichloroethene
Ethylbenzene
Heptachlor
Methyl Tertiary Butyl Ether
Naphthalene
Tetrachloroethane
Toluene
trans- 1 ,2-Dichloroethene
Trichloroethene
Xylenes (Total)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Cobalt
Copper
Lead
Manganese
Mercury
Nickel
Selenium
Thallium
Vanadium
Zinc
Iron
2-Methylnaphthalene
4,4'-DDE
4,4'-DDT
4,4'-DDD
Surface
Soil
































X
X
X
Subsurface
Soil









X

























Ground-
water
•
•
•
•
•
•
•
•

•
•
•
•
•

•
•
•
•
•

•
•
•
•
•
•
•

•








X
X
X

X
X

X
X
X
X

X
X
X
X
X
X
X
X
X
X
X
X
X
X
X

X



Surface
Water















•
•





•
•
•


•


•
















'*


X




X

X
X
X


X
X
X





Sediment
















•




•
•

•
•



•


•
•
•
















X
X
X

X
X
X
X

X


X
X


X
X
X
Fish






X







X


X

X

X

X
X

X


X


X
X
X

-------
                           TABLE 1 (Continued)
       SUMMARY OF COPCs IN ENVIRONMENTAL MEDIA OF CONCERN
                     OPERABLE UNIT NO. 10 (SITE 35)
                 INTERIM RECORD OF DECISION, CTO-0232
                 MCB CAMP LEJEUNE, NORTH CAROLINA
Contaminant
alpha-Chlordane
beta-BHC
Carbon disulfide
Chromium
Dieldrin
Endosulfan II
Endrin Ketone
Endrin Aldehyde
Endrin
gamma-BHC
gamma-Chlordane
Heptachlor Epoxide
[^Methoxychlor
Surface
Soil
X



X



X

X


Subsurface
Soil













Ground-
water





-




















Surface
Water






















._



Sediment
•


•
•



•

•


X



.X
X

X
X

X
X
X
Fish
X
X
X

X

X

X
X



Selected for comparison to existing criteria.
Selected with respect to human health risk.

-------
                                                     TABLE 2
                                                 TOTAL SITE R!SK
                                           OPERABLE UNIT NO. f 0 (SITE 35)
                                       INTERIM RECORD OF DECISION, CTO-0232
                                       MCB CAMP LEJEUNE, NORTH CAROLINA
Receptors
Future Child Resident
Future Adult Resident
Current Military Personnel
Future Construction Worker
Current Child Resident
Current Adult Resident
Soil
ICR
4.IE-05
(<1)
I.9E-05
(
-------
                  TABLE3
    SUMMARY OF ALTERNATIVES EVALUATION
         OPERABLE UNIT NO. 10 (SITE 35)
INTERIM PROPOSED REMEIDAL ACTION PLAN, CTO-0232
      MCB CAMP LEJEUNE, NORTH CAROLINA
Evaluation Criteria
OVERALL PROTECTIVENESS
• Human Health
• Environment
COMPLIANCE WITH ARARs
• Chemical-Specific
• Location-Specific
RAA1
No Action
Potential risks associated with
groundwater exposure will
remain. Some reduction in
contaminant levels may result
from natural attenuation.
Contaminated groundwater will
continue to be • source of future
contamination to Brinson Creek.
No active effort made to reduce
groundwater contaminant levels
to below federal or slate ARARs.
Not Applicable.
RAA2
No Action with Institutional
Controls
Aquifer-use restrictions mitigate
risks from direct groundwater
exposure.
Contaminated groundwater will
continue to be • source of future
contamination to Brinson Creek.
No active effort made to reduce
groundwater contaminant levels
to below federal or state ARARs.
Not Applicable.
RAA3
Groundwater Collection and
On-Site Treatment
Active collection and treatment
will reduce contaminant levels in
groundwater within capture zone
of i: terceptor trench (estimated at
IOC feet upgradient maximum).
Aq: ifer-use restrictions will also
mil gate risks from direct
grotttdwater exposure.
Intexeptor trench serves as a
bar.ier to contaminated
groi-ndwater discharge to Brinson
Crcik.
Ret jclions in groundwater
coi: aminant levels to below
fed ral or state ARARs can be
expsted within capture zone of
interceptor trench. Reductions
upgradient will be less substantial
if at all.
Wetlands and alligators
(endangered . species) are
concerns because of proposed
location of interceptor trench. It
is assumed that necessary
approvals can be obtained.
RAA4
In Situ Air Sparging and Off-
Gas Carbon Adsorption
Active in situ volatilization and
biodegradation will reduce
contaminant levels in
groundwater within radius of
Influence of wells (estimated at
25 feet). Aquifer-use restrictions
will also mitigate risks from
direct groundwater exposure.
Air sparging wells and SVE wells
serve as a barrier to contaminated
groundwater discharge to Brinson
Creek.
Reductions in groundwater
contaminant levels to below
federal or state ARARs can be
expected within radius of
influence of wells. Reductions
upgradient will be less substantial
if at all.
Wetlands and alligators
(endangered species) are
concerns because of proposed
location of interceptor trench. It
is assumed that necessary
approvals can be obtained.
RAA5
In Well Aeration and Off-Gas
Carbon Adsorption
Active in-well volatilization and
in situ biodegradation will reduce
contaminant levels in
groundwater within radius of
influence of wells (estimated at
45 to 60 feet). Aquifer-use
restrictions will also mitigate
risks from direct groundwater
exposure.
Aeration wells serve as a barrier
to contaminated groundwater
discharge to Brinson Creek.
Reductions in groundwater
contaminant levels to below
federal or state ARARs can be
expected within radius of
influence of wells. Reductions
upgradient will be less substantial
if at all.
Wetlands and alligators
(endangered species) are
concerns because of proposed
location of interceptor trench. It
is assumed that necessary
approvals can be obtained.

-------
              TABLE 3 (Continued)

     SUMMARY OF ALTERNATIVES EVALUATION
         OPERABLE UNIT NO. 10 (SITE 35)
INTERIM PROPOSED REMEDIAL ACTION PLAN, CTO-0232
      MCB CAMP LEJEUNE, NORTH CAROLINA
Evaluation Criteria
• Reduction of Toxicily, Mobility or
Volume
• Residuals Remaining After
Treatment
• Statutory Preference for Treatment
SHORT-TERM EFFECTIVENESS
• Community Protection
• Worker Protection
RAAI
No Action
No reduction except by natural
attenuation.
No active treatment process
applied.
Not satisfied.
Risks to community not increased
by remedy implementation.
None.
RAA2
No Action with Institutional
Controls
No reduction except by natural
attenuation.
No active treatment process
applied.
Not satisfied.
Risks to community not increased
by remedy implementation.
Protection required during well
installation and sampling.
RAA3
Groundwater Collection and
On-Site Treatment
Reduction of organic and
inorganic contaminants expected
within capture zone of trench.
Residuals include metals sludge
and spent carbon which would
have to be disposed of properly.
Sal ified except that area
imj icted by treatment is limited
and does not include entire plume
of contaminated surficial
gro: ndwater.
Minimal, if any, risks during
colt xtion and treatment.
Trt'.ch installation procedure
limi i worker exposure by design.
RAA4
In Situ Air Sparging and Off-
Gas Carbon Adsorption
Reduction of organic
contaminants expected within
radius of inflir ice of wells.
Residuals requiring disposal
include spent carbon and a small
volume of condensed
contaminated vapor (water).
Satisfied except that area
impacted by treatment is limited
and does not include entire plume
of contaminated surficial
groundwater.
Possible migration of toxic
vapors through ground surface
because vapor extraction is
difficult to control when
groundwater surface is within
several feet of ground surface.
Minimal potential for worker
exposure.
RAA5
In Well Aeration and Off-Gas
Carbon Adsorption
Reduction of organic
contaminants expected within
radius of influence of wells.
Residuals requiring disposal
include spent carbon and a small
volume of condensed
contaminated vapor (water).
Satisfied except that area
impacted by treatment is limited
and does not include entire plume
of contaminated surficial
groundwater.
Minimal, if any, risks during
operation and treatment.
Minimal potential for worker
exposure.

-------
              TABLE 3 (Continue, I)

     SUMMARY OF ALTERNATIVES EVALUATION
         OPERABLE UNIT NO. 10 < SITE 35)
INTERIM PROPOSED REMEDIAL ACT ION PLAN, CTO-0232
      MCBCAMPLEJEUNE.NORTI CAROLINA
Evaluation Criteria
• Environmental Impacts
• Installation Period
IMPLEMENTABILITY
• Ability to Construct and Operate
RAAI
No Action
Continued impacts from
unchanged existing conditions.
Not Applicable.
No construction or operation
activities.
RAA2
No Action with Institutional
Controls
Continued impacts from
unchanged existing conditions.
Less than 30 days required to
install additional groundwater
monitoring wells.
Involves standard well
installation and sampling only.
RAA3
Groundwater Collection and
On-Sile Treatment
Wetlands disturbance during
installation could be significant.
Trench will serve as a barrier for
contaminated groundwater
discharge to Brinson Creek.
60 to 90 days estimated to install
trench and treatment system.
Soft ground in wetlands areas
may hamper construction and
result in delays. Once installed,
operating is straight-forward
using commercially proven
technology. Approximately
2,000 to 3,000 cubic yards of
potentially contaminated soil
excavated from the trench will
require disposal. Lack of access
may be a significant lost factor.
RAA4
In Situ Air Sparging and Off-
Gas Carbon Adsorption
Minimal wetlands disturbance.
System will serve as a barrier for
contaminated groundwater
discharge to Brinson Creek.
60 to 90 days estimated to install
sparging and SVE wells and
treatment system.
Construction of activities involve
primarily well installation which
has been previously executed
successfully in this area.
Disposal of drill cuttings
required.
.Thin vadose zone may hamper
effective vapr • extraction which
could result in the release of toxic
vapors to atmosphere.
High metals in groundwater could
clog well screens which would
require frequent maintenance or
well replacement.
RAA5
In Well Aeration and Off-Gas
Carbon Adsorption
Minimal wetlands disturbance.
System will serve as a barrier for
contaminated groundwater
discharge to Brinson Creek.
60 to 90 days estimated to install
aeration wells and treatment
system.
Construction of activities involve
primarily well installation which
has been previously executed
successfully in this area.
Disposal of drill cuttings
required.
High metals in groundwater could
clog well screens which would
require frequent maintenance or
well replacement.

-------
              TABLE 3 (Continued)

     SUMMARY OF ALTERNATIVES EVALUATION
         OPERABLE UNIT NO. 10 (SITE 35)
INTERIM PROPOSED REMEDIAL ACTION PLAN, CTO-02J2
      MCB CAMP LEJEUNE, NORTH CAROLINA
Evaluation Criteria
• Ability to Monitor Effectiveness
• Availability of Services and
Equipment
• Requirements for Agency
Coordination
COSTS
• Net Present Worth (30 years)
USEPA/Stale Acceptance
Community Acceptance
RAA 1
No Action
No monitoring.
None required.
None required.
SO
Not preferred because impact to
Brinson Creek would be
unabated.
Not preferred because impact to
Brinson Creek would be
unabated.
RAA 2
No Action with Institutional
Controls
Proposed monitoring will provide
an indication of effects of natural
attenuation and progress of
contaminants migration.
Well installation and sampling
services available from multiple
vendors.
Must submit semi-annual reports
to document sampling reports.
$299.800
Not preferred because impact to
Brinson Creek would be
unabated.
Not preferred because impact to
Brinson Creek would be
unabated.
RAA 3
; roundwater Collection and *
On-Site Treatment
Pri posed monitoring will give
no ce of failure so that system
car be adjusted before a
significant contaminant release
oci irs.
Bit wlymer trench technology
available from a limited number
of • endors.
Special permit to perform
construction in wetlands may be
required. Air and water discharge
permits required.
S3.225.000
Acceptable because impact to
Brinson Creek would be
controlled. In addition,
EPA/State prefer treatment
alternatives.
Acceptance likely because
impact to Brinson Creek would
be controlled.
RAA 4
In Situ Air Sparging and Off-
Gas Carbon Adsorption
Proposed monitoring will give
notice of failure so that system
can be adjusted before a
significant contaminant release
occurs.
Air sparging technology is
available from multiple vendors.
Special permit to perform
construction in wetlands may be
required. Air and water discharge
permits required.
$2.810,800
EPA/Slate prefer treatment
alternatives. Acceptance likely
if off-gas discharges do not
present health hazards.
Acceptance likely if off-gas
discharges do not impact the
neighboring populace.
RAAS
In Well Aeration and Off-Gas
Carbon Adsorption
Proposed mpnitoring will give
notice of failure so that system
can be adjusted before a
significant contaminant release
occurs.
In well aeration is a patented
priority technology currently
available from only one vendor.
Special permit to perform
construction in wetlands may be
required. Air and water discharge
permits required.
S2.62S.IOO
Acceptable because impact to
Brinson Creek would be
controlled. In addition.
EPA/State prefer treatment
alternatives.
Acceptance likely because
impact to Brinson Creek would
be controlled.

-------
                           TABLE 4

            GLOSSARY OF EVALUATION CRITERIA
               OPERABLE UNIT NO. 10 (SITE 35)
           INTERIM RECORD OF DECISION, CTO-0232
           MCB CAMP LEJEUNE, NORTH CAROLINA
Overall Protection of Human Health and Environmental - addresses
whether or not an alternative provides adequate protection and describes how
risks posed through each pathway are eliminated, reduced, or controlled
through treatment engineering or institutional controls
Compliance with ARARs/TBCs - addressed whether or not an alternative will
meet all of the applicable or relevant and appropriate requirements (ARARs),
other criteria to be considered (TBCs), or other federal and state environmental
statutes and/or provide grounds for invoking a waiver.
Long-term Effectiveness and Permanence - refers to the magnitude of residual
risk and the ability of an alternative to maintain reliable protection of human
health and the environment over time once cleanup goals have been met.
Reduction of Toxicity, Mobility,  or Volume through Treatment - is the
anticipated performance of the treatment options that may be employed in an
alternative.
Short-term Effectiveness - refers to the speed with which the alternative
achieves protection, as well as the remedy's potential to create adverse impacts
on human health and the environment that may result during the construction and
implementation period.
Implementability  -  is the technical and administrative feasibility of an
alternative,  including the availability of materials and services needed to
implement the chosen solution.
Cost - includes capital and operation and maintenance costs. For comparative
purposes, presents present worth values.
USEPA/State Acceptance - indicates whether, based on review of the RI and FS
reports and the PRAP, the USEPA and state concur with, oppose, or have no
comments on the preferred alternative.
Community Acceptance - assessed in the Record of Decision (ROD) following
a review of the public comments received on the RI and FS reports on the PRAP.

-------
FIGURES

-------
                                                           CAMP       LEJEUNE

                                                           MILITARY     RESERVATION
CAMP \     LEJEUNE

MILITARY^    RESERVATION.-;.
                                              v^   o
                                   GUV-MIT  SCAI.K
                           FiGURE  '
                CAIVF  I F..TUNF  AND  SITE  35
                        LOCATION  UAP
               MARIMiJ  CCR~S •.•til.  CAW-3 LCJUU
                        NORTH  CAPO. 'NA

-------
o.
 HAT IMS

SO Ml K«I
                                                                     INTERIM ROD FOR SURFICAL GROUNDWATER. CTO-0232
                                                                                MAWNB conn aiat, cur LWBUNB
                                                                                       NOHIB CUIOIDU
                                           BAKER ENVmONMENTAL.Inc.
                                            Coraopollg, Pennsylvania
               SITE  PLAN
 SITE  35  - CAMP  GEIGER AREA  FUEL  FARM
      CONTRACT TASK ORDER  -  0232


OIK    in •» ton       || us    „, im

-------
                                                                                                                                            Booaconwrn I
                                                                                                                                       "  MOHTMMt MIL MUUO (Mtt CJ (1W) IV BL
                                                                                                                                       "J"*  WMRMMO MIL HRMllD tT MB (1MCQ.
                                                                                                                                       T*  MWRMB MU HtUUa MO CU (IMl) IT UUT.
                                                                                                                                       T*  Miroiia MU Muu0 IMO tsr Monunw (itH) r *nt
                                                                                                                                                                           0»w)
                                                                                                                                            	.	_._  ___   MWmMTMW
                                                                                                                                            tr u*. (mm rv-a «rat ra * rwnm TOT KU.)
                                                                                                                                            WWTOtM MUJ MTJU1D HMO UO> a (IM4).
                                                                                                                                                             SttMB AW uuaiD nsi tin
                                                                                                                                                     IMS toinw M Mnooun onm or tin
                                                        r-.j-sxt^ ,      . =.«o I^^.-^J '  'i      ,-'
                                                                ' !      1      !••>'.!    X
                                                                                                                                                           \
 	ran im
-swwxwsw-
                                                                    INTERIM ROD TOR SUBOCIAL GBOONDWATER.  CTO-0232
                                                                                     com BUI, CIMP
                                                                                      mmcuoutt
                                                                                BAKER ENVIRONUENTAL.Inc.
                                                                                Coraopolla. Pfinnsrlvania
 UMITS OF COMBINED BTEX IN THE UPPER
   PORTION OF THE  SURFICIAL AQUIFER     n     _
SITE  35 - CAMP GEIGER AREA FUEL  FARM       3

                                                                                                                                            |T>7T."••'."•'.'. •';"', ' '""**.*'• r-"";*"j?y^y>i|*i".|f •?^1f."i;??~^i'r.?«fl-??'y"'jfiiiji'"•«;*•
                                                                                                                                            ^•^•-  ^^I^I^P?^

-------
                                                                                                                                 mi Muun
                                                                                                                                 *m muuo u
• IP™1
                                                                                                                                                     (itn) ft «it


                                                                                                                                           t tturvn un mu.rm wtm tta

                                                                                                                                           t (MCNOOMM W UTO) «• IHOVH

                                                                                                                                           g IMC jmrautn moo or rax <*/
                                                  mTBRM ROD FOR 3URPICUL GROUNDWATBR. CTO-0232
                                                              lUHNI COIFS U8I. CUIP IDItlNI
                                                                    NOS1B O10LDU
                                                              BAKER ENVIROmffiNTAL,Inc.
                                                               Coraopolla, Pennsylvania
    UNITS OF COMBINED BTEX IN THE
LOWER PORTION OF  THE SURFICIAL AQUIFER  II     A
 SITE 35  - CAMP GCIGER AREA FUEL FARM        4

-------
                                                                                                                                                     A DUMB MOM IM MHCATD DC MI«llXHI UUDOM OT
                                                                                                                                                     ooooNcominon IMC «MM nnmtCTB MU otu B NOT
                                                                                                                                                   ^   MMKMNB KU KITMJJB IKO CS (IMI) W DC.

                                                                                                                                                   °J~'   KHUMBB KU •OUUIP §T KIS (IMOX

                                                                                                                                                   T'   iiaiiwa mi t«Mi0 UNO et» (IMI) rr u».

                                                                                                                                                   T*   i«nB»« HU MUUO nco tor •nonumi (im) vr *nt

                                                                                                                                                   *y   Mcinq»» mi IBUUIP ««e» c» nuiv-w •nonMnoM (iiw)
                                                                                                                                                   	IT u». 
-------
                                                                                          cu (IMI) ir uv,

                                                                    "V   irimiaa «oi nuua wto w •mnwmM (im) *r MB.

                                                                         ViBtirrnMM mi MUIO (HBO OH nuwMv MwmunoM (mi)
                                                                         n uv. own. r*-n win n * NMPM nn •m.)

                                                                                          tt HID • (IN*).
                                                                                    •OttlB DC JfMOnuR UCAIKN Or AH
                                                                                     Mil UMHm ml uu > m «AUU.
INTERIM ROD FOR SURFICUL OBOUNDWATER, CTO-0232
           HUUNI COUPS MSI. CIMP
                  NORTH ClBOUKt
            BAKER ENVD?ONMENTAL,Inc.
            Coraopolia, Pennsylvania
LIMITS  OF COMBINED  HALOGENATED ORGANIC
    COMPOUNDS IN THE  LOWER PORTION
        OF THE SURFICIAL AQUIFER               C.
 SITE 35 - CAMP OEIGER AREA  FUEL FARM  II    U



-------
        uo Kncmo nwi*L
          uuno. ct IK
O

«  *
    wraonutt ONxmontn nov cocenoM

          rSSS
           11. 1H4.
--- NWOCO iouim or en tocos
                                        HAT IHI

                                       HI Ml Kttf
                                                                                                                                             \  NX
                                                                                                                                               \ \    i • MOTOKD tm
                                                                                                                                                \ \  / teas* taut
                                                                                                                                                 V<
INTERIM BOD FOR SUWICUl GROUNDWATER, (TO - 0232
           lumn CORPS BASI. cuo> unimi
                  NORTH ClIOUKt
                                                                                   BAKER ENVffiONMENTAL.Inc.
                                                                                    Coraopolla, Pennsylvania
RAA 3: GROUNDWATER COLLECTION  AND
  ON-SITE TREATMENT - PLAN  VIEW
   CONTRACT TASK ORDER  - 0232
                                                                                                                                                                                    7

-------
  K-
  1020
                                              -CONTROLLED ACCESS -
                                                                                                                                                  400
                                                                                                                                            iaker
  "   CROUNOWATER LEVEL IN THE SURFICIAL AQUIFER

	SURFACE OF PROPOSED HIGHWAY
OURCE: LANTDIV. FEB. 1992
                                                              Horizontal Scale: 1 inch = 40 (t
                                                                     o     10
                                                                               20
                                                                               I
«o
I
                                                               Vertical Scale: I Inch = 20 n.
                    FIGURE 8
RAA  3: GROUNDWATER  COLLECTION AND ON-SITE
       TREATMENT -  CROSS-SECTION A-Af
SITE  35,  CAMP GIEGER  FUEL  FARM  INTERIM ROD
        CONTRACT TASK ORDER - 0232
         MARINE CORPS BASE. CAMP LEJEUNE
                 NORTH  CAROLINA

-------
                                                                         OFF-GAS TREATMENT
                                                                           (VAPOR PHASE
                                                                         ACTIVATED CARBON)
                        FILTRATION
                          UNIT
                       (SUSPENDED
                      SOLIDS REMOVAL)
 SETTLING TANK
(METALS REMOVAL)
            INFLUENT
          FROM TRENCH
                                                                                          CARBON DISPOSAL/
                                                                                            REGENERATION
                                                   DISCHARGE TO
                                                   SURFACE WATER
                                                               AIR STRIPPER
                                                                 BLOWER
                                      _^ OFF SITE
                                         DISPOSAL
                                                                                                   aker
                                                                                                 Baker Environmental, he.
H21 oars
                                                                             FIGURE  9
                                                      RAA 3:  GROUNDWATER COLLECTION  AND ON-SITE  TREATMENT-
                                                                     PROCESS FLOW  DIAGRAM
                                                     SITE 35,  CAMP  GEIGER AREA FUEL  FARM INTERIM ROD
                                                                 CONTRACT  TASK  ORDER  - 0232
                                                                 MARINE CORPS BASE,  CAMP  LEJEUNE
                                                                          NORTH  CAROLINA

-------

C

                                                                 — -   -,  r
                                                                              "       .~S!5''?"

-------
 DISCHARGE TO
 ATMOSPHERE
                                                                AIR
                                                                BLOWER
                                                               GROUT
                                                               SEAL
                                                                  LOWER
                                                                  OBSERVATION
                                                                  WELL
OPERATING
WATER
TABLE
          RESTING
          WATER
          TABLE
                 GROUNDWATER
                 CIRCULATION
  LEGEND
      AIR
      GROUNDWATER.
                            SEMI-CONFINING
                            LAYER
                                     1	GROUT
                                        SEAL
REFERENCE: HERRUNG. 8.. ET AL-. FIGURE 1.(o). P.59.
                                                                      aker
                                                                    Bckar Environmental, t
                                   FIGURE 11
      RAA 5: IN  WELL AERATION  AND  OFF-GAS CARBON  ADSORPTION  -
             TYPICAL  WELL  DETAIL  AND  PROCESS  FLOW  DIAGRAM
            SITE  35,  CAMP  GEIGER  AREA FUEL FARM  INTERIM  ROD
                        CONTRACT  TASK ORDER -  0232
                        MARINE CORPS BASE, CAMP LEJEUNE
                                 NORTH  CAROLINA  -

-------
                                   FIGURE 12

                            COMPARISON OF COSTS
                                RAAs 2,3, 4, and 5
                       SITE 35 - CAMP GEIGER FUEL FARM
                            MCB CAMP LEJEUNE,  NC
                                                                             Total Costs - 30 Years (PW)
                                                                          Total Costs-SYeare (PW)
                                                                       Total Capital Costs (1)
                                                                    Annual Plant O&M

                                                                 Annual OW O&M
RAA3
                RAA5
                                 RAA4
                                                  RAA2

-------