PB96-964021
                               EPA/ROD/R04-96/278
                               April 1997
EPA Superfimd
      Record of Decision:
       Memphis Defense Depot (DLA),
       aka: Defense Depot, Operable Unit 1,
       Memphis, TN
       5/1/1996

-------
Record of Decision for Interim Remedial Action
of the Groundwater at Dunn Field (OU-1) at the
Defense Distribution Depot Memphis, Tennessee
               January 1996
                Prepared for

        U.S. Army Corps of Engineers
             Huntsville Division
                Prepared by

             CH2M HILL, Inc.
              Montgomery, AL
             DACA87-94-D-0009
                 110491.IR

-------
Record of Decision for Interim Remedial Action
of the Groundwater at Dunn Field (OU-1) at the
Defense Distribution Depot Memphis, Tennessee
               January 1996
                Prepared for
       U.S. Army Corps of Engineers
             Huntsville Division
                Prepared by
             CH2M HILL, Inc.
             Montgomery, AL
            DACA87-94-D-0009
                 110491.IR

-------
                                    Contents
                                                                               «
Section                                                                      Page

Acronyms	iv
Executive Summary	v

Part 1—Declaration for the Record of Decision Interim Remedial Action
of the Groundwater at Dunn Field (OU-1)
       1.1    Site Name and Location  	  1-1
       1.2    Statement of Basis and Purpose	  1-1
       1.3    Assessment of the Site  	  1-1
       1.4    Description of Interim Remedial Action	'.	  1-1
       1.5   'Declaration	1-2

Part 2—Decision Summary
       2.1    Site Location and Description	2-1
       2.2    Site History and Enforcement Activities	  2-1
       2.3    Highlights of Community Participation  	  2-5
       2.4    Scope and Role of Operable Units	  2-6
       2.5    Summary of Site Characteristics  	2-7
       2.6    Summary of Site Risks	2-9
       2.7    Description of Alternatives	2-11
       2.8    Summary of the Comparative Analysis of Alternatives	2-18
       2.9  .  Summary of Selected Remedy	2-20
       2.10   Statutory Determinations	•	2-22
       •**  •* *   T~* /* -  _.-___                                            '            ^% <•> f\
       z.n   iv.ciciciu;cs   	,	2. 50

Part 3—Responsiveness  Summary	3-1
mgm95-DDMTMisc./002.WP5

-------
                                     Tables

Number                                                                    Page

1      Comparison of Constituents to Standards in Dunn Field Groundwater	2-10
2      Alternatives for Interim Remediation	2-13
3      Obervational Methods for Dunn Field Groundwater Remediation	2-22
4      Preliminary Identification of Potential Chemical-Specific ARARs
        for DDMT	2-24
5      Preliminary Identification of Potential Location-Specific ARARs
        at DDMT	2-25
6      Preliminary Identification of Potential Action-Specific ARARs
        for DDMT	2-26
7  '    Maximum Effluent Standards  for Discharge of Waste into the Municipal
        Sewerage System	2-28


                                     Figures

1      DDMT Location in Memphis  Metropolitan Area	  2-2
2      Operable Unit Locations  	2-3
3      Generalized Conceptual Site Model (Cross Section View)  	.2-12
4      Proposed Groundwater Recovery System (OU-1)  	2-17
mgm95-DDMTMisc./002.WP5                     111

-------
                                  Acronyms

AEHA       U.S. Army Environmental Hygiene Agency
AOC         Area of Concern
AR          Administrative Record
ARAR       Applicable or relevant and appropriate requirement
BRA         Baseline risk assessment
CERCLA     Comprehensive Environmental Response, Compensation, and Liability Act
CFR         Code of Federal Regulations
CRP         Community Relations Plan
DDMT       Defense Depot Memphis, Tennessee
DLA         Defense Logistics Agency
DNAPL      Dense non-aqueous phase liquid
DOD         Department of Defense
EE/CA       Engineering evaluation/cost analysis
EPA         U.S. Environmental Protection Agency
gpm         Gallons per minute
IRA         Interim remedial action
MCL         Maximum contaminant level
MCLG       Maximum contaminant level goal
mgd         Million gallons per day
NCP         National Oil and Hazardous Pollution Contingency Plan
NGVD       National Geodetic Vertical Datum
NPDES       National Pollutant Discharge Elimination System
NPL         National Priorities List
O&M        Operations and maintenance
OU          Operable unit
PCB         Polychlorinated biphenyl
PCP         Pentachlorophenol
POTW       Publicly owned treatment works
PW          Present worth
RAB         Restoration Advisory Board
RCRA       Resource Conservation and Recovery Act
RFA         RCRA Facility Assessment
RI/FS        Remedial investigation/feasibility study
ROD         Record of Decision
SARA       Superfund Amendments  and Reauthorization Act
SWMU       Solid waste management unit
TDEC       Tennessee Department of Environment and Conservation
USATHMA   U.S. Army Toxic and Hazardous Materials Agency
UV          Ultraviolet
VOC         Volatile organic compound
mgm95-DDMT Misc./002.WP5

-------
                               Executive Summary
This Record of Decision (ROD) presents the selected interim remedial action (IRA) for
DDMT in accordance with the Comprehensive Environmental Response, Compensation,
and Liability Act of 1980 (CERCLA).  In 1992, after receiving a Hazard Ranking System
(MRS) score of 58.06, DDMT was placed on the National Priorities List by the
Environmental Protection Agency. The selected IRA provides for hydraulic control of a
contaminant plume in groundwater beneath Dunn Field.  Contaminants identified as those
of potential concern include volatile organic compounds, such as solvents used for
cleaning mechanical parts, and metals.  It is not intended as a permanent solution;
however, it is intended to be compatible with the final remedy.

DDMT and the involved regulatory agencies have been working to inform the community
about activities involved with the site since 1992 through press releases, mailings,
newspaper ads, and public meetings.

•Eight alternatives, each consisting of groundwater extraction, groundwater treatment, and
disposal components, were evaluated.  The alternative chosen as the preferred alternative
consists  of extraction on/offsite and discharge to a publicly owned treatment works
(POTW). This alternative assumes that pretreatment will not be necessary before
treatment at the POTW.  If, however, chemical analyses indicate that pretreatment is
necessary, a pretreatment provision is part of the contingency remedy.
 mgm95-DDMT Misc./002.WP5

-------
                 Parti
   Declaration for the Record of Decision
Interim Remedial Action of the Groundwater
   at Dunn Field [Operable Unit (OU-1)]

-------
                  UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

      ?                                 REGION IV

                                  345 COURTLAND STREET. N.E.
                                   ATLANTA. GEORGIA 3O365
                                      May 1, 1996

 4WD-FFB

 Certified Mail
 Return Receipt Requested

 Colonel Michael J. Kennedy, Commander
 Defense Distribution Depot Memphis
 2163 Airways Boulevard
 Memphis, Tennessee 38114-5210

 SUBJ: Concurrence with Interim Record of Decision, Operable Unit 1
       Defense Distribution Depot Memphis, Tennessee

 Dear Col. Kennedy:

   The U.S. Environmental Protection Agency (EPA) Region IV has reviewed the above
 referenced decision document and concurs with the Interim Record of Decision (EROD) for
 groundwater at Operable Unit 1, Dunn Field, as supported by the Remedial Investigation in
 progress.
   The selected remedy is Alternative 8 in the IROD. EPA concurs with the selected remedy as
detailed in the IROD with the following stipulation:  It is unuersiuud that the selected ir.icrin:
remedy for Operable Unit 1 may not be the final remedial action to address all media potentially
affected by past disposal practices at this unit.

   This  action is protective of human health and the environment, complies with Federal and
State requirements that are legally applicable or relevant and appropriate to the remedial action
and is cost effective.
                                               Sincerely,
                                              Richard D. Green
                                              Acting Director
                                              Waste Management Division

cc:  Jordan English, Tennessee Department of Environment & Conservation
                                                                                 ' ,->;: /?,Ti-/v/<-,; P.:;

-------
                             1.1  Site Name and Location
 Defense Depot Memphis, Tennessee (DDMT)
 Memphis, Shelby County, Tennessee
                        1.2  Statement of Basis and Purpose

 This decision document (Record of Decision [ROD]) presents the selected interim remedial action
 (IRA) for the DDMT site, Memphis, Tennessee, developed in accordance with the
 Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA),
 as amended by the Superfund Amendments and Reauthorization Act of 1986 (SARA), 42 U.S.C.
 Section 9601 et seq., and to the extent practicable, the National Oil and Hazardous Pollution
 Contingency Plan (NCP) 40 Code of Federal Regulations (CFR) Part 300.The DDMT is the lead
 agency for the remedial investigation/feasibility study (RI/FS) process for the site. The U.S.
 Environmental Protection Agency (EPA) and the Tennessee Department of Environment and
 Conservation (TDEC) are the supporting regulatory agencies for the site. In accordance with 40
 CFR 300.430, the regulatory agencies have provided input during this process. The regulatory
 agencies are provided with a draft IRA ROD for review and their comments are incorporated into
 the final document.  The U.S. EPA and the State  of Tennessee concur with the selected interim
 remedy.

                             1.3 Assessment of the Site

 Actual or threatened releases of hazardous substances from the DDMT site, if not addressed by

 endangerment to public health, welfare, and the environment.
                   1.4  Description of Interim Remedial Action

This ERA provides for hydraulic control of a contaminant plume in groundwater beneath Dunn
Field (also called OU-1). Because the contaminated Fluvial Aquifer poses a potential threat to the
deeper Memphis Sand Aquifer, it is considered as a potential threat to human health and the
environment.  Thus, the groundwater IRA is designed to provide a quick, interim response
measure that will help prevent the possible contamination of the area's drinking water supply.  As
a contingency remedy, the ERA also includes a provision for pretreatment if necessary. As
described in the IRA Proposed Plan contained in the Administrative Record, follow-on activities
include monitoring the groundwater plume and its response to the IRA. Once the plume has been
fully characterized, subsequent action may be taken to provide long-term definitive protection,
including remediation of source areas. To the extent possible, the interim action will not be
inconsistent with, nor preclude implementation of, the expected final remedy.  RI/FS activities at
OU-2, OU-3, and OU-4 will address contamination found within the southwestern quadrant,
southeastern watershed and golf course, and northern portions of the Main Installation,
respectively.

-------
including remediation of source areas. To the extent possible, the interim action will not
be inconsistent with, nor preclude implementation of, the expected final remedy.  RI/FS
activities at OU-2, OU-3, and OU-4 will address contamination found within the
southwestern quadrant, southeastern watershed and golf course, and northern portions of
the Main Installation, respectively.  This IRA addresses only Dunn Field.  OU-2, OU-3,
and OU-4 will be addressed in the remedial documents for those OUs.

The major components of the selected IRA for OU-1 include the following:

       •      Evaluation of aquifer characteristics  which may include installation of a
              pump test  well

       •      Installation of additional monitoring wells to locate the western edge of the
              groundwater plume

       •      Installation of recovery wells along the leading edge of the plume

       •      Obtaining  discharge permit for disposal of recovered groundwater to the
              T. E.  Maxson Wastewater Treatment Plant publicly owned treatment works
              (POTW) or municipal sewer system

       •      Operation  of the system of recovery wells until the risk associated with the
              contaminants is reduced to acceptable  levels or until the final remedy is in
              place

       •      Chemical analysis will be conducted to monitor the quality of the discharge
              in accordance with the city discharge permit requirements; the permit will
              include parameters to be monitored and frequency.
                                 1.5 Declaration

This interim action is protective of human health and the environment, complies with
federal and  state requirements that are legally applicable or relevant and appropriate, and
is cost-effective.  This action is interim; it is not intended as a permanent or final
remedy.  However, it is intended to be compatible with the permanent solution.  It is not
intended to  be the permanent solution, and uses  alternative treatment technologies to the
maximum extent practical for this interim response.  Because this action does not
constitute the final remedy for this OU, the  statutory preference for remedies that employ
treatment that reduces toxicity, mobility, or  volumes as a principal element has not been
entirely accommodated  and will be addressed at the time of the final response action.
Subsequent  actions are planned to address fully the threats posed by the conditions at this
OU.  Because this remedy will result in hazardous substances remaining onsite above
health-based levels, a review will be conducted to ensure that the remedy continues  to
provide adequate protection of human health and the environment within 5 years after the
mgm95-DDMTMisc./001.WP5                     1-2

-------
 This IRA addresses only Dunn Field. OU-2, OU-3, and OU-4 will be addressed in the remedial
 documents for those OUs.

 The major components of the selected IRA for OU-1 include the following:

              • Evaluation of aquifer characteristics which may include installation of a pump
              test well

              • Installation of additional monitoring wells to locate the western edge of the
              groundwater plume

              • Installation of recovery wells along the leading edge of the plume

              • Obtaining discharge permit for disposal of recovered groundwater to the T. E.
              Maxson Wastewater Treatment Plant publicly owned treatment works  (POTW) or
              municipal sewer system

              • Operation of the system of recovery wells until the risk associated with the
              contaminants is reduced to acceptable levels or until the final remedy is in place

              • Chemical analysis will be conducted to monitor the quality of the discharge in
              accordance with the city discharge permit requirements; the permit will include
              parameters to be monitored and frequency.
                                   1.5 Declaration

This interim action is protective of human health and the environment, complies with federal and
state requirements that are legally applicable or relevant and appropriate, and is cost-effective.
This action is interim; it is not intended as a permanent or final remedy.  However, it is intended
to be compatible with the permanent solution. It is not intended to be the permanent solution, and
uses alternative treatment technologies to the maximum extent practical for this interim response.
Because this action does not constitute the final remedy for this OU, the statutory preference for
remedies that employ treatment that reduces toxicity, mobility, or volumes as a principal element
has not been entirely accommodated and will be addressed at the time of the final response action.
Subsequent actions are planned to address fully the threats posed by the conditions at this OU.
Because this remedy will result in hazardous substances remaining onsite above health-based
levels, a review will be conducted to ensure that the remedy continues to provide adequate
protection of human health and the environment within 5 years after the commencement of this
remedial action.  Because this is an interim action ROD, review of the remedy will be ongoing as
DDMT continues to develop  the final remedial action for OU-1.
CHRISTINE E. KARTMAN                            Date
Chief, Environmental Protection and Safety Office

-------
THU   i:t)»
                                STATE OF TENNESSEE
              OEPARTMENI OF ENVIRONMENT AND CONSERVATION
                       MEMPHIS ENVIRONMENTAL FIEL.D OFFICE
                              SUITE E-045. PERIMETER PARK
                                   2510MT.MORIAH
                             MEMPHIS. TENNERRPP MI 15-1520
 April 24, 1996

 Commander
 Defense Distribution Depot Memphis
 Attn:  DDMT-DE (Ms. Christine Kartman)
 2163 Airways Blvd.,
 Memphis, Tennessee 38114-5210

 Re:    Concurrence for the Record of Decision for Interim Remedial Action of the GrounHwater
       at Dunn Field (OU-1) at the Defense Depot site, Memphis, Shelby County, Tennessee,
       April 1996, TDSF #79-736, cc 82

 Dear Ms. Kartman:

 The Tennessee Division of Superfund (TDSF) Memphis Field Office (MFO) has reviewed the ,,
 Interim Remedial Action Record of Decision for the Groundwater at Dunn Field, for the Defense
 Depot site dated April IPP6 referenced above.

 The Tennessee Department of Enviiutimcni and Conservation (TDEC) is in concurrence with the
 selected remedy, a pump and treat containment alternative, Alternative 8 as described.  TDEC has
 been actively involved with the development of the alternatives as well as the selection process
through closely coordinated project management among Base Closure Team (BCT) members and
extended BCT members.

This concurrence is provided within the authority of the Federal Facilities Agreement (FFA) for the
 Defense Depot, the Defense Department/State Memorandum yf Agreement (DSMOA), and the
delegated powers of the Commissioner of TDEC as part of the President's five step Base Cleanup
Plan (BCP) process.

 Sincerely,
     Wilier, Director
Tennessee Division of SupeiTuud

c:      TDSF, NCO
       TDSF, MFO
       Dann Spariosu
              United States .Environmental Protection Agency
              Federal Facilities Branch
              3'I5 Courtland Street, N.C.
              Atlanta, GA 30365

-------
     Part 2
Decision Summary

-------
                      2.1  Site Location and Description

DDMT covers 642 acres of federal land in Memphis, Shelby County, Tennessee, in the
extreme southwestern portion of the state.  Approximately 5 miles east of the Mississippi
River and just northeast of the Interstate 240-Interstate 55 junction, DDMT is in the
south-central section of Memphis, approximately 4 miles southeast of the Central
Business District and 1 mile northwest of Memphis International Airport.  Airways
Boulevard borders DDMT on the east and provides primary access to the  installation.
Dunn Avenue, Ball Road, and Perry Road serve as the northern,  southern, and western
boundaries,  respectively. The installation is surrounded by mixed residential,
commercial, and industrial  areas. Figure 1 shows the installation's location within the
Memphis area.

The Defense Logistics Agency (DLA), an agency of the Department of Defense (DOD),
provides logistics support to military services. As a major field installation of the DLA,
DDMT receives, warehouses, and distributes supplies common to all U.S. military
services and some civil agencies located primarily in the southeastern United States,
Puerto Rico, and Panama.  Stocked items include food,  clothing,  electronic equipment,
petroleum products,  construction materials, and industrial, medical, and general supplies.

The installation contains approximately 110 buildings, 26 miles of railroad track, and 28
miles of paved streets. It has about 5.5  million square feet of covered storage space and
approximately 6.0 million square feet of open storage space.  The land and buildings are
owned by the U.S. Army and leased by  DLA.  DDMT  consists of two main sections:
the Main Installation, which is intensely developed, and Dunn Field, an open storage area
about 64 acres in size. A more  detailed description of the OUs, whose current
boundaries are shown in Figure  2, is found in Section 2.4.
                 2.2  Site History and Enforcement Activities

DDMT began operations in 1942 with the charge to inventory and supply materials for
the U.S. Army. In 1964, its mission was expanded to serve as one of the principal
distribution centers for a complete range of commodities.

Past activities at DDMT include a wide range of storage, distribution, and maintenance
practices.  Dunn Field (OU-1) has been used as a landfill area (northwestern quadrant), a
storage area for mineral stockpiles (southwestern and southeastern areas), and  a pistol
range, and later as a pesticide storage area (northeastern area).  Activities in the
southwestern quadrant of the  Main Installation (OU-2)  have included hazardous material
storage and recoupment (Building 873), sandblasting and painting activities (Buildings
1086 through 1089), and maintenance (Building 770).  The southeastern portion of the
Main Installation (OU-3) includes the bulk of the storage and distribution warehouses at
DDMT. Other activities that are documented to have occurred in this area include the
polychlorinated biphenyl (PCB) transformer storage (near Building 274), pesticide  and
mgm95-DDMTMisc./001.WP5                     2-1

-------
         SCALE IN MILES
        LEGEND


         INTERSTATE
    	STATE LINE
         RIVER CREEK
    ALLEN
                                                                  DDMT
                                                       AREA OF
                                                       MEMPHIS,
                                                       TENNESSEE
         MEMPHIS LIGHT, GAS AND
         WATER DIVISION WELL FIELD
 Source: En(i«^ring-Science, 1993
                                      FIGURE  1
DDMT LOCATION  IN MEMPHIS METROPOLITAN AREA
  	Defense Depot Memphis,  Tenness^l
mwp-0022.ogn
          '09-MAY-1995

-------
      1000   500
1000
                      OU-1
                   DUNN FIELD
           LEGEND
             DDMT  BOUNDARY

             OU BOUNDARY
  Source: Engineering-Science. 1993
                                        BALL ROAD
                                    FIGURE 2
                 OPERABLE UNIT LOCATIONS
           Defense Depot Memphis,  Tennessee
mwp-0023.dgn   09-MAY-1995
                                       2-3

-------
herbicide storage and use (several locations), and fire truck pump testing (Lake
Danielson).  The northern portion of the installation (OU-4) has a history of the following
major activities:  hazardous material  storage (several locations), treatment of wood
products with pentachlorophenol (PCP) (Building 737), and storage of items awaiting
disposal (several locations).

Until 1970, army supplies, including hazardous and nonhazardous materials whose
containers were damaged or shelf life expired, were occasionally burned or buried in a
portion of Dunn Field.  Wastes disposed of in this  manner may have included oil and
grease, paint, paint thinner, methyl bromide, pesticides, herbicides, and food supplies.
Documentation indicates that most of the materials  disposed of during this time period
were buried in  the northwestern portion of Dunn Field.

In 1981, the U.S. Army Toxic and Hazardous Materials Agency (USATHMA) prepared
an installation assessment of hazardous materials disposal  practices to assess potential
sources  of contamination.  The  burial sites at Dunn Field  were identified and ranked as
having the greatest potential for offsite migration of contaminants in groundwater.

In 1982, a hydrogeologic evaluation was conducted by the U.S. Army Environmental
Hygiene Agency (AEHA) to determine groundwater quality beneath Dunn Field.  Seven
wells were  installed in the northwestern quadrant of Dunn Field and analyzed for
inorganic constituents.  The results did not reflect any  significant groundwater
contamination from the past disposal  operations.

A Resource Conservation and Recovery Act (RCRA) Facility Assessment (RFA) was
performed in 1989 by A. T. Kearney to.identify solid waste management units (SWMUs)
and areas of concern (AOCs).  To satisfy CERCLA requirements, an RI/FS was
conducted in 1989 and concluded in 1990.  The RI was conducted on a sitewide basis to
confirm the presence or absence of contamination,  to evaluate the extent and significance
of detected contamination,  and to provide a scientific foundation for cleanup alternatives.
An RI Report was submitted to EPA in August 1990.  A  quantitative baseline risk
assessment  (BRA) was conducted as part of the RI  and submitted along with the RI
Report.  The remedial alternatives are presented in a draft FS,  which  was submitted to
EPA in  September 1990.  A final RI for the installation has not yet been accepted by
either EPA or TDEC.

During the  RI,  monitoring  wells were installed in the Fluvial Aquifer and Memphis Sand
Aquifer. Several groundwater samples collected from  monitoring wells around the
installation contained levels above regulatory limits of  volatile organic compounds
(VOCs) and heavy metals.  The results suggested that the groundwater contaminant plume
was  generally migrating to the west and northwest of Dunn Field.  Later data (ESE 1994)
indicates that there may be a west to  southwest component. In 1992,  the EPA placed
DDMT  on the National Priorities List (NPL).
mgm95-DDMTMisc./001.WP5                    2-4

-------
In 1993, an Engineering Report-Removal Action for Groundwater (Engineering Science),
was prepared for DDMT.  The intent of the report was to meet all requirements of the
engineering evaluation/cost analysis (EE/CA) under CERCLA and the NCP for a
non-time critical removal.  The report evaluated a variety of technologies, previously
presented in the 1990 RI/FS, that would treat contaminated groundwater in the Fluvial
Aquifer to prevent possible human exposure.

This IRA represents the first step in the remediation of the contaminated groundwater
beneath the northern portion of Dunn Field (OU-1). Additional actions will be necessary
to provide long-term definitive protection for OU-1.
                 2.3  Highlights of Community Participation

DDMT, EPA, and TDEC have made significant efforts to inform interested parties and
provide input on activities associated with the site.  As part of its requirements under
CERCLA, DDMT has been working with the community surrounding the site since 1992.
In October 1992, press releases informing the community of the NPL listing of the site
were released.  The Information Repository located at the Memphis/Shelby County Public
Library, 1850 Peabody Avenue, Memphis, Tennessee, was established  in May 1993.
Two other repositories are located at the Cherokee Branch Public Library and the
Memphis-Shelby County Public Health Department.  A draft final Community Relations
Plan (CRP) was issued in April  1994 and has been placed in the information repositories.
On May 24, 1993, at the request of the Memphis Mayor's office, DDMT had a meeting
at Corey Junior High School to discuss the restoration effort and to provide a forum for
the community to express its concerns about health issues.  DDMT also led a public
exhibition and discussion on the restoration process ou August 10, 1993.  In December
1994, DDMT, EPA, and TDEC held a public meeting to discuss the start of the  RI/FS.

The FS, the Proposed Plan,  and the Administrative Record (AR) for  the OU-1 IRA were
released to the public in  November 1994.  These documents were made available in the
AR and maintained in the repositories and in the information repository at the site.  The
notice of availability of these documents and the AR was published in December 1994 in
the Silver Star News, the Tri-State Defender, and the Commercial Appeal. A public
comment period was held from December 4, 1994, to January 17, 1995.  In addition, a
public meeting was held on December 20, 1994. At this meeting, representatives from
DDMT, EPA, and TDEC answered questions about  problems at the site and the  remedial
alternatives under consideration, including the IRA.  Responses to the comments  received
during this comment period are presented in the responsiveness summary in Part 3 of this
document.

The Technical Review Committee, established in February  1994, was converted to a
Restoration Advisory Board (RAB) in July 1994. The RAB consists  of representatives
from the Memphis area community and from the state and federal government, and meets
on a monthly basis to discuss activities associated with DDMT.  After each meeting,
meeting minutes are distributed to board members.
mgm95-DDMT Misc./OOl .WP5                     2-5

-------
In addition to the RAB, newsletters are prepared on a quarterly basis and disseminated to
approximately 3,000 individuals. The mailing list of 3,000 was established from the
response to  an initial mailing to 20,000 individuals within a 1-mile radius of DDMT in
October 1994, the response to newspaper advertisements, and from the existing DDMT
mailing list.  Factsheets are also completed and distributed whenever new or additional
restoration activities occur at DDMT.  A hotline (901-775-4569) was established  in
February 1994 to assist local citizens or other interested parties in obtaining information
concerning the environmental restoration activities at the site.
                    2.4  Scope and Role of Operable Units

Because of the size of the installation (642 acres) and its complexity, DDMT, EPA and
TDEC have organized the work at this site into the four OUs, which are discreet parts of
an entire response action.  Figure 2 shows the location and areal extent of the OUs.

Dunn Field, which is the only area on DDMT where burial of waste is known to have
occurred, is designated OU-1.  Substances found in OU-1 probably resulted from use of
the area for landfill operations, mineral stockpiles, pistol range use, and pesticides
storage.

The Main Installation is divided into three other OUs. OU-2, in the southwestern
quadrant, is an area where maintenance and repair activities have occurred.  Potential
contamination of OU-2 may have resulted from spills or releases from the hazardous
material storage and repouring area, or sandblasting and painting activities.  OU-3
includes the Golf Course Pond, Lake Danielson,  and former transformer and pesticide
storage areas.  Storage of PCBs and the use of pesticides and herbicides are potential
sources of contamination for OU-3.  OU-4, in the north-central area, is mainly
characterized by  the presence of  the main hazardous materials storage building at DDMT.
Principal contamination in  OU-4  probably resulted from a wood treatment operation and
hazardous material storage.

Because the contaminated groundwater beneath Dunn Field poses a potential threat to the
drinking  water aquifer, it is considered a possible threat to human health and the
environment.  Thus, the objective of the groundwater IRA is to provide a quick response
measure  that will help prevent the possible contamination of the area's drinking water
supply.  Follow-on activities include characterizing and monitoring the groundwater
plume migration.  Once the plume has been characterized,  subsequent action may be
taken to provide  long-term definitive protection, including remediation of source areas.
To the extent practicable, the interim action will  be consistent with any planned  future
actions.
mgm95-DDMTMisc./001.WP5                     2-6

-------
The IRA addresses contamination of groundwater beneath Dunn Field from past disposal
practices at DDMT. The IRA represents the first step in the remediation of the
contaminated groundwater beneath the northern portion of Dunn Field.  The remainder of
OU-1 and OUs-2, 3, and 4 will be evaluated later and will be addressed in future
documents.
                     2.5 Summary of Site Characteristics

The major site characteristics presented in the RI/FS that are applicable to OU-1 are
summarized below.

2.5.1  Physiography

DDMT is situated within the Gulf Coastal Plan subdivision of the Atlantic Coastal Plain
Physiographic Province. The area is characterized by dissected loess-covered uplands
and generally  lacks distinct features.

Dunn Field lies just north of the Main Installation and Dunn Avenue, and consists of
approximately 64 acres of undeveloped land.  Most of Dunn Field is unpaved. About
one-half of the area is grassed;  the remaining area contains crushed rock and bauxite and
fluorspar piles.  Several large hardwood trees are present in the northeastern part of the
field.  The southwestern quadrant of the field is a grassed, gently sloping area.  The
southeastern quadrant is a level zone used for both covered and uncovered bulk materials
storage (bauxite and fluorspar).

Dunn hiekfs topography is a levei-to-gentiy roiling terrain which has been somewhat
altered by past activities of heavy equipment operators.  The land appears to slope to the
west from the bauxite piles in the center of the field.  An arc-shaped ridgeline separates
the field's two northern quadrants.  In the northeastern quadrant of the field, the areas
surrounding the  former pistol range (later used as a pesticide/herbicide storage shed
[Building  1184]) and the former burn area are level and  grassed. The northwestern
quadrant of the field (the portion used  for burial of waste materials) is a level-to-gently
sloping grassed area.   Surface elevations range from a low of 273 ft,  National Geodetic
Vertical Datum of 1929 (NGVD), at the north outfall/installation boundary fenceline to
315 ft NGVD in the field's approximate center.   Maximum local relief is about 25  ft at
the pistol range  bullet stop.

Installation surface drainage is accomplished by overland flow to swales, ditches,
concrete-lined channels, and an efficient storm drainage  system.  Most of DDMT is
generally level with, or above,  surrounding terrain; therefore, DDMT receives little or no
runoff from adjacent areas.  Most Dunn Field drainage is achieved by overland flow to
the adjacent properties to the north and west. The northeastern quadrant drains east to a
concrete-lined channel, or to adjacent properties to the north.  The concrete-lined channel
consists of two separate segments that  join approximately 200 ft north of Building 1184.
mgm95-DDMTMisc./001.WP5                     2-7

-------
Both channel segments convey adjacent residential neighborhood storm water through the
northeastern quadrant of Dunn Field.  The concrete-lined channel directs flow northward
to Cane Creek, which drains into Nonconnah Creek at a point several miles southwest of
DDMT.  Nonconnah Creek drains into Lake McKellar, a Mississippi River tributary.

Runoff from the northwestern quadrant flows overland to a roadside ditch along Kyle
Street (northwestern boundary of the installation).  The remainder of the runoff flows
overland to the west onto neighboring  properties outside of DDMT.

2.5.2 Hydrogeology

The Dunn  Field area of DDMT is covered by  a loess deposit,  which is a semi-cohesive
windblown deposit of silt, silty sand, and silty clay.  The loess is about 20 ft thick in the
vicinity of Dunn Field and may occasionally reach 30 ft in thickness.  Although the loess
is not typically a-water-bearing zone, seasonal perched groundwater may occur.  The
extent of this potential perched zone is unknown.  There is  no evidence that the loess
produces water to wells in the DDMT  vicinity. The loess is underlain by the Fluvial
Deposits, the Jackson Formation/Upper Claiborne Group, and  the Memphis Sand.

The Fluvial Deposits consist of a top layer of silty clay, silty sand, or clayey sand; a
clean, fine to medium-grained sand;  and a basal gravelly sand.  The thickness of the
Fluvial Deposits hi Dunn Field ranges  from 50 to 70 ft. This  unit forms the shallow
aquifer hi the vicinity of Dunn Field and receives recharge from rainfall infiltration and
lateral groundwater inflow.  Discharge is toward the Mississippi River to the west and
possibly by leakage into the underlying Memphis Sand Aquifer through the Jackson
Formation/Upper Claiborne confining bed.  Data collected from the site suggests that
groundwater hi the Fluvial Aquifer is moving generally toward the west in the Dunn
Field area.

Below the  Fluvial Deposits is the Jackson Formation and Upper Claiborne Group
consisting of stiff gray or orange plastic, lean to fat lignitic clay, silt, and fine sand with
minor lenses of lignite. This stratigraphic unit reaches thicknesses of approximately 80 ft
and forms  a regional confining bed separating  the Fluvial Deposits and the underlying
Memphis Sand Aquifer.  Although no  areas of hydraulic connection have been confirmed
in the vicinity of DDMT to date, investigations are underway to verify the existence of a
potential interconnection.

At Dunn Field, the top of the Memphis Sand Aquifer is about 160 ft below ground level
along the western property line and approximately 140 ft below ground level along the
eastern property line.  The formation is composed of thin-bedded, white to brown or
gray, very fine grained to gravelly, partially argillaceous and micaceous sand.  The
aquifer ranges in thickness from 500 to about 900 ft and is  under confined conditions.
mgm95-DDMTMisc./001.WP5                     2-8

-------
The Memphis Light, Gas, and Water Division operates eight well fields that extract water
from the Memphis Sand for municipal supply.  The Allen Well Field is located 1 to 2
miles west of DDMT. A potentiometric surface map, (Park 1990, plate 3) indicates that
groundwater flow in the Memphis Sand Aquifer beneath DDMT is toward the West.

2.5.3 Groundwater Contamination

Chemicals of potential concern identified hi Dunn Field monitoring wells screened in the
Fluvial Aquifer include the following:

                           Volatile Organic Compounds
      Carbon tetrachloride                     1,1 -Dichloroethylene
      1,2-Dichloroethylene                     Tetrachloroethylene
      1,1,2,2-Tetrachloroethane                Trichloroethylene

                                      Metals
      Arsenic                                       'Barium
      Chromium                                     Lead
      Nickel

The highest concentration of constituents detected in the groundwater samples collected
from the Fluvial Aquifer wells  are presented hi Table 1.  To date, constituents of concern
in the Fluvial Aquifer have not been detected in Memphis Sand Aquifer groundwater
samples in the vicinity of the site.

The constituents of concern found hi the Fluvial Aquifer beneath Dunn Field occur at
concentrations  above the established maximum coiiiaiiiiiiain levels (MCLs) and maximum
contaminant level goals (MCLGs).  A comparison of MCLs and MCLGs with the data
from the RI is presented hi Table 1.

Over the course of 3 sampling efforts conducted at Dunn Field (1989, 1990, and 1992),
volatile organics were detected above MCLs hi 22 out of 35 Fluvial Aquifer groundwater
samples.  Metals concentrations above MCLs were detected in 25 out of 35 groundwater
samples collected during this tune period.
                          2.6  Summary of Site Risks

In 1990, as part of the RI/FS, a preliminary risk assessment was performed hi accordance
with EPA guidance available at that tune. Potential exposure points for contaminated
groundwater from Dunn Field were identified as the following:

       •     Ingestion of groundwater through the public water supply
       •     Contact with potable water during bathing
       •     Inhalation of vapors from VOCs in potable water during household use
mgm95-DDMT Misc./OOl .WP5                     2-9

-------
                                                            Table 1
                                            Comparison of Constituents to Standards
                                                  in Dunn Field Groundwater
to
I—*
o
Constituent
Volatile Organic Compounds
1 , 1-Dichloroethene
1,2-Dichloroethene (total)
Tetrachloroethene
Trichloroethene
Carbon tetrachloride
Metals
Arsenic
Barium
Chromium
Lead
Nickel
MCL
fog/L)

7
70
5
5
5

50
2,0001
50
152
100
RI Phase I
Highest Levels 1989
(ftg/L)

130 (MW-10)
5203 (MW-11)
210 (MW-5)
1,7003(MW-12)
77 (MW-6)

85 (MW-10)
3,7404 (MW-14)
1,2404 (MW-7)
6534 (MW-10)
6024 (MW-7)
RI Phase n
Highest Levels 1990
(Mg/L)

160 (MW-10)
5103 (MW-12)
2403 (MW-10)
5.1003 (MW-12)
40 (MW-6)

210 (MW-14)
1,900 (MW-10
340 (MW-7)
1,000 (MW-10)
170 (MW-7 & 10)
      Source: Environmental Science, Inc., 1993.

      Notes:
      'Maximum contaminant level goals (MCLGs)
      2Action level
      Identified in the analysis from a secondary dilution factor
      4Spiked sample recovery not within control limits
Abbreviations:
Hg/L  = Micrograms per liter
MW   = Monitoring well
     mgm95-DDMT-Misc./003.WP5

-------
The transport medium and exposure pathway for the exposure scenarios identified above
all relate to groundwater.  Contaminants can potentially leach from materials associated
with past disposal activities at Dunn Field.  Several of these contaminants are already
present in the Fluvial Aquifer as a result of dispersion and infiltration. The Fluvial
Aquifer, which is not used as a potable water supply, potentially recharges  the Memphis
Sand Aquifer by leakage.  This potential leakage could provide  a pathway for
contaminants to the deeper Memphis Sand Aquifer, the drinking water aquifer for the
City of Memphis.  A conceptual site model is shown in Figure  3.

The Allen Well Field, located approximately 1 mile south of Dunn Field, is one of eight
pumping centers serving the Memphis area. With 35 wells, the Allen Well Field pumps
roughly 21 million gallons a day (mgd) of potable water from the Memphis Sand Aquifer
and accounts for approximately 15 percent  of the  water used within the Memphis area.
Contamination of the Memphis Sand Aquifer caused by leakage from the contaminated
Fluvial Aquifer could occur, thus directly affecting the Memphis water supply source.

Results of the preliminary risk assessment indicate that there is  a potential public health
risk associated with the Fluvial Aquifer groundwater.  Actual or threatened releases of
hazardous constituents from  Dunn Field, if not addressed by the preferred IRA, may
present a current or potential threat to public health, welfare, or the environment.

The principal goals of this groundwater IRA are to incrementally remove contaminants
from the Fluvial Aquifer, to decrease risk by mitigating the spread of constituents toward
the Allen Well Field, and to create a hydraulic barrier to prevent contamination in  the
Fluvial Aquifer at Dunn Field from reaching the Allen Well Field.

Although the IRA is not anticipated to achieve compliance with MCLs, it is consistent
with the objective to protect the Memphis Sand Aquifer.  Long-term operation of a
groundwater removal system will help to achieve  MCLs by incrementally removing
contaminants.

The more specific findings of the BRA will be included in the final action ROD  for
OU-1, along with the ultimate cleanup objectives.  No changes  were made to the
preferred alternative as presented in the Proposed Plan.


                        2.7 Description of  Alternatives

Eight alternatives were evaluated for addressing the groundwater contamination beneath
Dunn Field. These alternatives are listed in Table 2.  Each of the alternatives consist of
three elements—groundwater extraction, groundwater treatment, and disposal.  Extraction
option alternatives range from no action to  installation of deep wells on- and off site.

Treatment possibilities range from none to  air stripping or ultraviolet (UV)/oxidation of
metals. Groundwater disposal options range from none to discharge to surface drainage,
discharge to the municipal sewer  system, or reinjection into onsite wells. These
alternatives are described in greater detail in the following paragraphs. Cost analyses
provided are based on 1990  dollars and may represent a substantial cost increase by the
time implementation begins.
mgm95-DDMTMisc./001.WP5                    2-11

-------
                                                 GENERALIZED SITE MODEL
      WELL FIELD
PUBLIC
DRINKING
WATER
                                                                                                                               LAND
                                                                                                                               SURFACE
                                                                                                           SURFACE
                                                                                                           DEPOSITS
                                                                                                                              SURFACE RUNOFF
                                                                                   LOESS (SILT. SILTY CLAY,
                                                                                   SILTY SAND)          LEACHING
                                         FLUVIAL DEPOSITS (FINE TO MEDIUM SANDS,
                                         WITH MINOR LENSES OF CLAY AND GRAVEL)
                                                                             FLUVIAL AQUIFER
                                                                          JACKSON-CLAIBORNE CLAY
                                            POSSIBLE LEAKAGE?
                                                         SAND
                                                                         AQUIFER
NOT TO SCALE. VERTICAL SCALE EXAGGERATED

Source: CEHND. 1994
                                                                                                                                   FIGURE 3
                                                                                       GENERALIZED CONCEPTUAL SITE MODEL (CROSS SECTION VIEW)
                                                                                                      	Defense Depot Memphis, Tennessee

-------
                                          Table 2
                             Alternatives for Interim Remediation
Alternative
1
2
Extraction
No Action
Wells onsite
Treatment
None
Air stripping with
Disposal
None
Municipal sewer
                     Wells on- and offsite
                         Wells onsite
                         Wells onsite
                         Wells onsite
                         Wells onsite
metals removal if
    necessary

Air stripping with
metals removal if
    necessary

Air stripping with
metals removal if
    necessary

Air stripping with
metals removal if
    necessary

Air stripping with
metals removal if
    necessary

Air stripping with
metals removal if
    necessary
   Municipal sewer



   Municipal sewer



   Surface drainage



   Surface drainage
Reinjection upgradient
       onsite
     (preferred)
   Alternative 8 is the preferred alternative.

2.7.1  Alternative 1:  No Action

Capital Costs:  N/A
Annual O&M Costs:  N/A
Present Worth (PW): N/A

The no action alternative is carried out through the screening process as required by the
NCP.  The no action alternative assumes no further action at the site and is used as a
baseline to measure the other alternatives.  Under this alternative, no action would be
taken hi terms of containment and treatment of the groundwater plume.  Groundwater
contamination would  remain and continue to migrate.
mgm95-DDMT Misc./OOl .WP5
                                           2-13

-------
2.7.2  Alternative 2:  Extraction Onsite, Air Stripping, and Discharge to
POTW

Capital Costs:  $600,000
O&M:  $270,000
PW: $6,000,000

The groundwater extraction system for Alternative 2 consists of eight wells located in
Dunn Field. The wells would be located to extract groundwater from the most
contaminated portion of the plume, according to existing data.  The groundwater would
be removed from the eight wells and stored in a holding tank.

The extracted groundwater would be pumped from the holding tank to an air stripping
tower for removal of VOCs.  The use .of a carbon treatment system will be dependent on
the concentration of VOCs in the air stream. Removal of heavy metals, if necessary,
would be performed after VOC treatment.  The treated groundwater would be released
into the local sewer system, where it would be treated at the POTW.

2.7.3  Alternative 3:  Extraction On/Offsite, Air Stripping, and
Discharge to POTW (Contingent Alternative)

Capital Costs:  $600,000
O&M:  $230,000
PW: $5,200,000

The pumping and treatment system for Alternative 3 is similar to Alternative 2 except for
the placement and pumping rate of the wells. Like Alternative  2, this alternative has
eight extraction wells, but with different locations.  Two of the wells are located west of
Dunn Field, downgradient of the property boundary, with the remainder on DDMT
property.  Alternative 3 would provide greater capture of the contaminated groundwater
off site.  The treatment and handling of the groundwater would be similar to
Alternative 2.

2.7.4  Alternative 4:  Extraction Onsite, UV/Oxidation, and Discharge to
POTW

Capital Costs:  $830,000
O&M:  $300,000
PW: $6,900,000

The extraction well system would be identical to Alternative 2.   The extracted
groundwater would be treated by a UV/oxidation process using ultraviolet light, ozone,
and hydrogen peroxide to break down the VOCs into carbon dioxide, water,  and
inorganic chlorides. Treatment for heavy metals, if needed, would follow UV/oxidation.
The treated water would be discharged to the POTW.
mgm95-DDMTMisc./OOI.WP5                   2-14

-------
2.7.5  Alternative 5:  Onsite Extraction, Air Stripping, and Discharge to
Surface Drainage Channel

Capital Costs:  $470,000
O&M: $130,000
PW:  $3,100,000

The extraction and treatment system of Alternative 5 is identical to Alternative 2.
However, the treated water would be discharged into the existing surface water drainage
system rather than to the POTW.  Surface drainage channels exit from the northern and
western boundaries of Dunn Field. Both of these channels terminate at Cane Creek,
located north of Dunn Field. A National Pollutant Discharge Elimination System
(NPDES) permit would be required before discharge would be allowed.

2.7.6  Alternative 6:  Extraction Onsite, UV/Oxidation, and Discharge to
Surface Drainage Channel

Capital Costs:  $660,000
O&M: $160,000
PW:  $3,900,000

Alternative 6 is similar to Alternative 4, except that the treated groundwater would be
discharged into the surface water drainage system discussed in Alternative 5.

2.7.7  Alternative 7:  Extraction Onsite, Air Stripping, and Reinjection
     ni
Capital Costs:  $500,000
O&M: $150,000
PW:  $3,500,000

Alternative 7 would extract groundwater from six wells on government property.  The
extracted water would be treated by air stripping (similar to the treatment method in
Alternative 2), and treated for heavy metals, if needed.  The treated water would be
reinjected into the Fluvial Aquifer upgradient from the extraction wells at Dunn Field.
Reinjection would be completed using four injection wells located on the eastern side of
Dunn Field. Pumps and piping would have to be installed to transmit  the water from the
treatment site to the eastern side of Dunn Field.
mgm95-DDMTMisc./001.WP5                    2-15

-------
2.7.8  Alternative 8:  Extraction On/Offsite, and Discharge to POTW
(Preferred Alternative)

Capital Costs:  $500,000
O&M:  $250,000
PW:  $5,600,000

Alternative 8 is the preferred alternative and is a hybrid of Alternative 3.  However,
unlike Alternative  3, Alternative 8 places most of the groundwater recovery wells offsite
along the leading edge of the plume.  This placement will be more effective in protecting
the Memphis Sand Aquifer from contaminants in the Fluvial Aquifer at OU-1.
Additionally, this alternative does not assume that pretreatment before discharge will be
required making it a less expensive alternative.  However, this alternative uses the
treatment component of Alternative 3 as a contingency should pretreatment be required.

Alternative 8 would be used to contain the contaminated groundwater by inducing a
hydraulic barrier.  The hydraulic barrier will be achieved by pumping the groundwater
from the containment wells placed along the leading edge of the plume.  The leading  .
edge of the plume  will be located as part of the RI activities planned for OU-1. Data
gathered during the OU-1 RI will be used to locate the leading edge  of the plume.
Leading edge identification and containment of the plume will be achieved in the
following manner:

       •     A groundwater recovery well will be installed onsite in the middle of the
             plume to establish aquifer characteristics.

       •     Additional monitoring wells will be installed to establish the western edge
             of the contaminant plume.  The western edge will be established when
             samples from these wells are uncontaminated.

       •     After the aquifer characteristics are established and the leading edge of the
             plume is identified, additional groundwater recovery wells will be installed
             as appropriate to contain the plume. These wells are  located along the
             leading edge of the plume and  screened in the Fluvial Aquifer down to the
             confining clay layer of the Memphis Sand Aquifer.

The groundwater and the associated contamination will be captured by the recovery wells
(see Figure 4).  Calculations and modeling are performed to ensure that the zone of
recovery from each well overlaps.   The spacing and pumping rate of the wells  will be
such that the contamination should not move beyond the line of wells. Once the recovery
wells are operating, the system will be checked frequently (by comparing field data with
predicted model results) and any necessary adjustments made (including the installation of
additional recovery wells, if needed) to verify that the plume is contained.
mgm95-DDMTMisc./001.WP5                    2-16

-------
   N  NOT TO
      SCALE
  PROPOSED
  RECOVERY
    WELLS
    (TYP)
       CONTAMINATION
           "PLUME-
                                   DUNN
                                    FIELD
                                      AERIAL VIEW OF
                                      DUNN FIELD AND
                                        PROPOSED
                                      RECOVERY WELLS
                                        LEGEND
                                        GROUNDWATER
                                        FLOW DIRECTION
            PROPOSED
            RECOVERY
              WELL
          RECOVERED GROUNDWATER
             PIPED TO CITY SEWER
  GROUNDWATER
      FLOW
    DIRECTION
                                                   FLUVIAL AQUIFER
                                     \   \  \
                         CONTAMINATION   \  \
                                        \    I
             "PLUME"
          >   •.  \  \  \  \  '

.   .   ,   ,  \  \  \  \ \ \;
                            V
:\  ^  \   \   \  \  \  \  \ /
    V   '-.          .   -.   \   \>
                                   GROUNDWATER
                                   FLOW DIRECTION
       ^^^^^^c^v\v^^^^^^^c<^^:^^x^^^^^^^^
       \x^;'\<^C^X\v^^:\v^^^^c CLAY BARRIER N^^C:^X\NS%VXX:>;:
       \\ \ -- \\\ \ V\\\\ X\ \\\ ••..":. \\ \. -• •, \ \ \ -: -.. \ \ \ '-. •-.. X\ \ ••- •:. \ \ \ '•• •, \\ \ '••

                                                         FIGURE 4
                         PROPOSED GROUNDWATER RECOVERY SYSTEM (OU-1)
                                     Defense Depot Memphis, Tennessee
5-9-95 SRE70348.WP
                                    2-17

-------
DDMT will obtain a discharge permit to allow the groundwater pumped from the wells to
be discharged into the municipal sewer system or POTW.  The discharge permit will set
maximum levels for groundwater constituent concentrations.  If the extracted groundwater
exceeds these limits, the treatment contained in Alternative 3 will be used.  The cost of
Alternative 8, without the use of a contingency treatment remedy, assumes that the
groundwater  will meet the City's permit limits and that no  treatment will be needed.
        2.8  Summary of the Comparative Analysis of Alternatives

This section of the interim ROD provides the basis for evaluating which alternative (a)
meets the threshold criteria of overall protection of human health and the environment,
EPA and TDEC approval, and compliance with applicable or relevant and  appropriate
requirements (ARARs); (b) provides the best balance with respect to effectiveness,
reduction of toxicity, mobility, or volume through treatment, implementability, and cost;
and (c) satisfies community acceptance.

Federal law requires that nine criteria be used for evaluating the anticipated performance
of remedial actions. The nine criteria are described below,  followed by an analysis of
the degree  to which each alternative satisfies the criteria:

       1.      Overall Protection of Human Health and Environment-Assesses degree to
              which alternative eliminates, reduces, or controls health and environmental
              threats through treatment, engineering methods, or institutional controls.

       2.      Compliance with ARARs—Assesses compliance with federal and state
              requirements.

       3.      Long-Term Effectiveness—Degree  to which a remedy can maintain
              protection of health and the environment once cleanup goals have been
              met.

       4.      Reduction of Toxicity, Mobility, or Volume Through Treatment—Refers  to
              expected performance of the treatment technologies to lessen harmful
              nature,  movement, or amount of contaminants.

       5.      Short-Term Effectiveness-Length  of time for remedy to achieve protection
              and potential effects of construction and implementation of a remedy.

       6.      Implementability-Refers to the technical feasibility and administrative ease
              of a remedy.

       7.      Cost-Weighing the benefits of a remedy against the cost of
              implementation.
mgm95-DDMTMisc./001.WP5                    2-18

-------
       8.      State Acceptance-Consideration of the state's opinion of the preferred
              alternative.

       9.      Community Acceptance—Consideration of public comments about the
              preferred alternative and about the proposed plan.

These nine criteria can be categorized into three groups.  The first and second categories
are threshold criteria. The chosen alternative must meet  the threshold criteria to be
eligible for selection. The third, fourth, fifth, sixth, and seventh criteria are considered
the primary balancing criteria.  The final two criteria are termed the modifying criteria
and are evaluated after issuance of the Proposed Plan for public review and comment.

2.8.1   Analysis

2.8.1.1  Threshold Criteria

Overall Protection of Human Health and Environment.  The preferred interim action
would contain the contamination plume and prevent it from migrating while removing a
portion of the contaminated groundwater.  Because the plume is believed to have
migrated offsite, the preferred alternative must have extraction wells located offsite. The
wells in Alternatives 2,  4, 5, 6, and 7 are located onsite  and would not sufficiently
contain the plume.  This lack of containment would lead  to further environmental effects
and would be a continual threat to human  health.  Alternative 1 offers no protective
measures for human health and the environment.

Alternatives 3 and 8 offer adequate  degrees of protection by reducing and controlling the
risks through removal and containment. Alternatives 1, 2, 4, 5, 6,  and  7 are not options
for this site  because they do not adequately reduce the risks associated with the
contaminated groundwater.

Compliance with ARARs.  Under the preferred alternative, groundwater will be
discharged to the POTW. Compliance issues are  further discussed in Section 2.10.

2.8.1.2 Primary  Balancing Criteria

Long-Term Effectiveness and Performance.  Alternatives 3 and 8 should be effective in
reducing long-term contaminated groundwater levels and  associated  health risks. Because
of residual contamination, the size of  the aquifer,  and inherent complexities, it may not
be possible to completely remediate the aquifer to its original condition using technology
currently available.  Additional actions will be necessary  to provide long-term definitive
protection for OU-1.
mgm95-DDMTMisc./001.WP5                    2-19

-------
Reduction of Toxicity, Mobility, or Volume of the Contaminants through Treatment.
The toxicity and volume of the contaminated groundwater would be reduced by the
groundwater extraction in Alternatives 3 and 8.  Mobility of the contamination plume
would be restricted by the physical forces of the groundwater extraction. This hydraulic
barrier should prevent lateral and vertical movement of the contaminated groundwater,
thus reducing the threat to the Memphis Sand Aquifer.

Short-Term Effectiveness.  Groundwater removal should contain the groundwater
contamination plume fairly rapidly and help to reduce further lateral contamination
migration.  Implementing the preferred alternative would result in a reduction of the
potential effects to nearby residents from contaminants at Dunn Field.

Implementability. The groundwater recovery systems will be relatively simple to
implement.  The technology and processes have been reliably demonstrated. Equipment
and materials are readily available.  However, as previously stated, the Fluvial Aquifer
and the  contaminated groundwater plume will have to be further characterized.

Cost. The cost analysis hi Alternative 3 includes the cost of well installation and O&M
cost of the air stripper.  The capital costs are estimated at $600,000, O&M costs at
$230,000 and present worth cost at $5,200,000.

The cost of Alternative 8 is based on the installation of eight recovery wells.  This cost
estimate assumes  a quarterly sampling plan to ensure that the system is operating
efficiently and that no prior treatment before discharge will be required. However,
because of the uncertainties associated with groundwater  recovery, additional wells may
be required that would affect the estimated cost.  Additionally, the cost'of Alternative 8
does not include pretreatment costs. For Alternative  8, the capital costs are estimated at
$500,000, O&M costs at $250,000 and present worth cost at $5,600,000.

2.8.1.3  Modifying Criteria

State Acceptance. DDMT has been actively  working with TDEC throughout the cleanup
process.  TDEC supports this approach. However, information obtained during the RI
may suggest other alternatives that would involve the concurrence of the state.

Community Acceptance. Community response to the alternatives is presented in the
responsiveness summary, which addresses comments received during the public meeting
and the  public comment period.
                      2.9  Summary of Selected Remedy

Through consideration of the requirements of CERCLA, the NCP, the detailed analysis
of alternatives and public and state comments, DDMT has selected an interim remedial
action for OU-1.  Of the eight alternatives reviewed,  only two were considered viable
mgm95-DDMTMisc./001.WP5                    2-20

-------
options.  Because "no action" does not address or rectify the problem and Alternatives 2,
4, 5, 6, and 7 do not contain the contamination plume, they are not considered
appropriate.  The preferred alternative is Alternative 8, which is a hybrid of
Alternative 3. However, Alternative 8 puts more emphasis on plume containment and
does not assume that pretreatment before discharge will be required making it a less
expensive alternative.  The placement of ground water recovery wells in Alternative 8 will
be more effective in protecting the Memphis Sand Aquifer from contaminants in the
shallow aquifer at OU-1.

If chemical analysis indicate that treatment is required  before discharge, the treatment
option contained in Alternative 3 (the contingency remedy) will be used.  The preferred
alternative for the IRA of the contaminated groundwater below Dunn Field is
Alternative 8—on/offsite extraction and POTW disposal.  The criteria used to determine
whether the contingency remedy is implemented are the discharge limitations established
in the City of Memphis' discharge permit.

On the basis  of current information, this alternative appears to  offer the most reasonable
approach for the protection of the drinking water supply and containment of the plume.
Currently, groundwater recovery is the only appropriate alternative to contain the plume.
This alternative represents an interim action and is intended only to  stabilize the site and
to prevent further degradation. However, with the additional information that will be
collected during the RI, other alternatives may become available. No conditions are
currently foreseen where the interim action will be inconsistent with, or preclude
implementation of, the final remedy.

The approach used to design and implement the preferred alternative will consist of the
following:

       •     Establishing the conditions that are believed to exist on the basis of
             available information.  Design will be based on expected conditions.

       •     Establishing, in advance, conditions that are reasonable deviations from the
             probable conditions.

       •     Implementing the base design and monitor conditions.

       •     Implementing contingent designs as warranted  by monitoring.

This approach is referred to as the observational method.  The approach recognizes and
manages uncertainties inherent in groundwater remediation.  Table  3 illustrates the
planned approach for managing uncertainties associated with the implementation of this
remedial action.
mgm95-DDMTMisc./001.WP5                     2-21

-------
The observational method will be used during design and implementation and is not part
of the selection process for the IRA alternative.  If changes to the selected remedy are
required, based on information obtained through the observational approach, then the
public will be made aware of these changes either through a fact sheet, explanation of
significant differences, or ROD Amendment.
Table 3
Observational Method for Dunn Field Groundwater Remediation
Probable
Condition*
8 recovery wells
needed
Pump at 75 gpm
Groundwater meets
City discharge
limits
Plume extends 600
ft west of Dunn
Field
Reasonable
Deviation*
12 recovery wells
needed
Pump at 125 gpm
Limits not met
Plume extends
1,200 ft west of
Dunn Field
Parameters to
Observe
Capture zone extent.
Observe water levels
in monitoring wells.
Capture zone extent.
Observe water levels
in monitoring wells.
Permit parameters
Data from RI
monitoring wells
Contingency Plan
Install additional
wells.
Pump at increased
rate; provide
adequate sewer
capacity.
Provide
groundwater
treatment.
Locate recovery
wells at western
extent of plume.
*Will be updated as additional information becomes available.
gpm— Gallons per minute
                        2.10  Statutory Determinations

DDMT, EPA, and TDEC concur that the extraction system (with the potential for
pretreatment, if necessary) will satisfy the CERCLA § 121 (b) statutory requirements of:
providing protection of human health and the environment, attaining applicable or
relevant and appropriate requirements directly associated with this action, being cost-
effective,  using permanent solutions and alternative treatment technologies to the
maximum extent practicable, and including a preference for treatment as a principal
element.

2.10.1  Protection  of Human Health and  the Environment

Although  the groundwater within the contaminated plume is not currently used as a
source of drinking water for the  local residents, under future or other potential exposure
scenarios  it presents a  potential threat to human health and the environment.  The interim
mgm95-DDMTMisc./001.WP5
                                        2-22

-------
action remedy initiates protection of human health under the exposure scenarios through
mitigation of the spread of the plume and removing a portion of the contaminated
groundwater until a final action is determined.  The remedy also provides protection to
the environment by providing the option of treatment of the extracted groundwater before
discharge, and effective management of all  residual wastes generated during
implementation of the action.

The final cleanup levels for the groundwater are not addressed in this interim action
record of decision (ROD) because such goals are beyond the limited  scope of this action.
The final cleanup levels will be addressed by the final remedial action ROD for the site.

2.10.2  Compliance with ARARs

The Comprehensive Environmental  Response, Compensation, and Liability  Act
(CERCLA) of 1980 was passed by Congress and signed into law on  December 11, 1980
(Public Law 96-510).  The act was  intended to provide  for "liability, compensation,
cleanup, and emergency response for hazardous substances released into the environment
and the cleanup of inactive waste disposal sites."  The Superfund Amendments and
Reauthorization Act (SARA), adopted on October 17, 1986 (Public Law 99-499), did not
substantially alter the original structure of CERCLA,  but provided extensive amendments
to it.  In particular, § 121 of CERCLA specifies that remedial actions for cleanup of
hazardous substances  must comply with requirements or standards under federal or more
stringent state environmental  laws that are applicable or relevant and appropriate to the
hazardous substances  or particular circumstances at a site.

A listing of applicable or relevant and appropriate requirements (ARARs) (chemical-
specitic, location-specific, and action-specific) are provided in Tables 4, 5,  and 6 of this
document.  Discharge to the publicly owned treatment works (POTW) will  be subject to
both the substantive and administrative requirements of  the national pretreatment program
and all applicable state and local pretreatment regulations (Tables 4,  5, and 6).  Should
treatment be required prior to discharge to the  POTW,  Alternative 3 will be implemented
as a contingency to provide groundwater treatment.

Alternative 3 uses an air stripper for the removal of volatile organic compounds (VOCs)
from the extracted groundwater.  Air stripping is a viable treatment process for removal
of VOCs from water  and will be used if treatment for VOCs is required.

2.10.2.1  Chemical-specific  ARARs

The principal contaminants of concern in the groundwater plume west of Dunn Field are
presented in Table 1.  Chemical-specific ARARs are shown in Table 4.

The City of Memphis Sewer  Use Ordinance (March 1993) establishes maximum effluent
standards for discharge .of wastewater into the municipal sewerage system (Table 7).
Daily average  maximum and instantaneous  maximum concentrations  are provided for
mgm95-DDMTMisc./001.WP5                    2-23

-------























NJ
i
N)
4^














Table 4
Preliminary Identification of Potential Chemical-specific ARARs for DDMT
Actions'
Discharge to
POTW'
































Requirement
Treatment of pollutants that could pass
through the POTW without treatment,
interfere with POTW operation, or
contaminate POTW sludge is required.

Specific prohibitions preclude the
discharge of pollutants to POTWs that:

• Create a fire or explosion
hazard in the POTW
• Are corrosive (pH < 5 .0)
• Obstruct flow resulting in
interference
• Are discharged at a flow
rate and/or concentration
that will result in
interference
• Increase the temperature of
wastewater entering the
treatment plant that would
result in interference, but in
no case raise the POTW
influent temperature above
104°F(40°C)
Discharge must comply with the local
POTW pretreatment program,
including POTW-specific pollutants,
spill prevention program requirements,
and reporting and monitoring
requirements.
RCRA permit-by-rule requirements
must be complied with for discharges
of RCRA hazardous wastes to POTWs
by truck, rail, or dedicated pipe.
Prerequisites


















'















Citation
40 CFR 403.5

See Table 6
















40 CFR 403. 5 and
local POTW
regulations
•







40 CFR 270.60
Permits-by-rule


ARAR
Applicable

































Comments
If any liquid is discharged to a POTW, these requirements
are applicable. In accordance with guidance, a discharge
permit may be required even for an onsite discharge.
because permitting is the only substantive control mechanism
available to a POTW.
Categorical standards have not been promulgated for
CERCLA sites, so discharge standards must be determined
on a case-by-case basis, depending on the characteristics of
the waste stream and the receiving POTW. Some
municipalities may have published standards for non-
categorical, non-domestic discharges. Changes in the
composition of the waste stream due to pretreatment process
changes or the addition of new waste streams may require
renegotiation of the permit conditions.

Local (City of Memphis) requirements for discharge to a
POTW are summarized in Table 6 for the constituents of
concern shown in Table 1 .






DDMT is applying for a City discharge permit.









Notes:
v
•These regulations apply regardless of whether the remedial action discharges into the sewer or trucks the waste to an inlet to the sewage conveyance system located "upstream" of the POTW.
lm95-DDMT-MISC2/003.WP5/24
                                                                          2-24

-------
Table 5
Preliminary Identification of Potential Location-specific ARARs at DDMT
Location
1.
2.
3.
4.
5.
Within 61 meters (200 feet)
of a fault displaced in
Holocene time
Area affecting stream or river
Memphis/Shelby County
Within 100-year floodplain.
Wetlands
Requirement
New treatment, storage, or disposal
of hazardous waste prohibited.
Action to protect fish or wildlife.
Ozone, carbon monoxide, and lead
air pollutants for Memphis/Shelby
County have been designated a non-
attainment area.
Facility must be designed,
constructed, operated, and
maintained to avoid washout.
Action to minimize the destruction,
loss, or degradation of wetlands
Action to prohibit discharge of
dredged or fill material into wetland
without permit
Prerequisite^)
RCRA h;izardous waste; treatment,
storage, or disposal
Diversion, channeling, or other
activity tiat modifies a stream or
river and affects fish or wildlife

RCRA hazardous waste; PCB
treatment storage, or disposal
Wetlands as defined by Executive
Order 1 1 990 Section 7
Citation
40CFR264.18(a)
Fish and Wildlife
Coordination Act (16
USC 661 et seg-); 40
CFR 6.302
State of TN Air Code
40 CFR 264. 18(b);
40 CFR 761. 75
Executive Order
11990, Protection of
Wetlands (40 CFR 6,
Appendix A)
Clean Water Act
Section 404; 40 CFR
Pans 230, 231
ARAR
Not ARAR
Not ARAR

Not ARAR
Not ARAR
Not ARAR
Comments
Shelby County is not listed in 40 CFR 264,
Appendix VI, as being seismically active.
The Fish and Wildlife Coordination Act
requires consultation with the Department of
Fish and Wildlife before taking any action that
would alter a body of water of the United
States.
Memphis-Shelby County Health Department
has adopted Tennessee Air Code.
Surface elevations at DDMT (276 to 316 feet
NGVD) exceed the average Mississippi River
alluvial valley flood levels of 185 to 230 feet
NGVD. The Flood Insurance Rate maps,
published by Federal Emergency Management
Agency and revised August 19, 1985, indicate
that DDMT is not within the 100- or 500-year
floodplain, but is in Zone C — "Areas of
Minimal Flooding."

Ui
    mgm95-DDMT-M!SC2/002.WP5

-------
Table 6
Preliminary Identification of Potential Action-specific ARARs for DDMT
Page 1 of 2
Actions"
Air Stripping
Requirement
Design system to provide odor-free
operation.
Obtain Memphis/Shelby County Health
Department construction/operating
permit.
Estimate total VOC emissions.
File an Air Pollution Emission Notice
(APEN) with the State to include
estimation of emission rates for each
pollutant expected.
Include with filed APEN the following:
• Modeled impact analysis of source
emissions
• Provide a Best Available Control
Technology (BACT) review for the
source operation
Predict total emissions of volatile
organic compounds (VOCs) to
demonstrate that emissions do not
exceed 450 Ib/hr. 3,000 Ib/day,
1U gal. /day, or allowable emission
levels from similar sources using
Reasonably Available Control Tech-
nology (RACT).
Verify that emissions of VOCs do not
exceed levels expected from sources in
compliance with hazardous air pollution
regulations.
Prerequisites

Emission requirements for
groundwater treatment systems
are handled individually.

Groundwater contains regulated
air pollutants.
This additional work and
information is normally
applicable to sources meeting die
"major" source criteria and/or to
sources proposed for
nonattainment areas.
Source operation must be in an
ozone nonattainment area.

Citation
CAA Section 101"
TCA 1200-3-9(l)(a)
1990 CAAA Section 302(g)
TCA 1200-3-9(1 l)(b)14.(ii)
40 CFR 52"
40 CFR 52"
40 CFR 52"
40 CFR 61"
ARAR
Applicable
Applicable
Applicable
Applicable
Relevant and
Appropriate
Applicable
Relevant and
Appropriate
Comments
Odor regulations are intended to limit nuisance
conditions from air pollution emissions.
Each construction-operating permit is based on "Best
Available Control Technology."
Any source emitting more than 100 tpy VOCs is
classified as major and requires agency review and a -
potential permit.
State will have particular interest in emissions for
compounds on its hazardous, toxic, or odorous list.
Preliminary meeting with State prior to filing APEN is
recommended in the regulation. Meeting would identify
additional issues of concern to the State.
State may identify further requirements for permit
issuance after first review. These provisions follow the
federal Prevention of Significant Deterioration (PSD)
framework with some modifications. Additional
requirements could include ambient monitoring and
emission control equipment design revisions to match
Lowest Achievable Emission Requirements (LAER).
While a permit is not required for an onsite CERCLA
action, the substantive requirements identified during the
permitting process are applicable.
The control technology review for this regulation
(RACT) could coincide with the BACT review
suggested under the PSD program.
Any source emitting the regulated compound(s) is
subject to these regulations. However, some of the
specific regulations further restrict the scope of
applicability.
mgm95-DDMT-MISC2/005.WP5/26

-------
                                                                                                 Table 6
                                                                   Preliminary Identification of Potential Action-specific ARARs for DDMT
                                                                                                                                                                                        Page 2 of 2
           Actions*
            Requirement
         Prerequisites
                                                                                                           Citation
                                                                                                        ARAR
                                                                  Comments
      Air Stripping
                           Estimate HAP emissions.
                                       Groundwater contains HAPs.
                                 Title III, 1990 CAAA
                                 Section 112

                                 TCA 1200-3-9(ll)(b)14.(i)
                             Applicable
                  If hazardous air pollutants (HAPs) are greater than a
                  major rate, air permit and/or application of Maximum
                  Available Control Technology (MACT) may  be
                  required.  HAPs exceed 25 tpy aggregate HAPs or
                  10 tpy for a single HAP.
      Groundwater
      Cleanup
N>
Maximum contaminant level goals
(MCLGs), established under SDWA,
that are set at concentrations above zero
shall be attained if relevant and
appropriate to the circumstances of the
release.  Where MCLGs for a
contaminant have been set at a
concentration of zero, the MCLs for
that contaminant shall be attained.

Groundwater standards established
under RCRA shall be attained if
relevant and appropriate to
circumstances of the release.
Groundwater is a currer.t or
potential source of drinliing
water.
40 CFR 300.430 of NCP
Relevant and
Appropriate
No MCLG or maximum
contaminant level (MCL) has .
been established for contaminant
of concern.

Cleanup value for lead in
groundwater used for drinking is
not an MCL, but is established as
an action level.
                                                                                                   40 CFR 264.94
                                                                                                   USEPA memo dated
                                                                                                   June 21, 1990, from Henry
                                                                                                   Longest to Patrick Tobin
Tennessee adopted guidelines equivalent to federal
guidelines. The interim remedial action will not address
groundwater cleanup ARARs. The final remedial action
will.
                                              Memo recommended a final action level for lead of 15
                                              ppb.
      Groundwater
      Withdrawal
Water withdrawal registration is
required for wells or systems that pump
more than 50,000 gallons per day.
                                 Water Withdrawal
                                 Registration Act of 1963-
                                 Chapter 8-Water Resources
                                 Div., Section 69-8-105
                             Relevant and
                             Appropriate
                 Total flow from all recovery wells may be up to 1 mgd.
      Notes:

      "Action alternatives from ROD keyword index.
      'All of the Clean Air Act ARARs that have been established by the federal government are covered by matching state regulations. The state has the authority to manage these programs through the approval of
       its implementation plans (40 CFR 52, Subpart G).  As of January 1996, the Tennessee SIP is complete, with EPA action pending.
                  mgm95-DDMT-MISC2/005.WP5/27

-------
                                                                     Table 7
               	Maximum Effluent Standards for Discharge of Waste into the Municipal Sewerage System	
                                                            Daily Average'1'                Instantaneous
                                                       Maximum Concentration      Maximum Concentration
                            Constituent                          mg/L                         mg/L
                Metals
                       Arsenic                                    1.0                           2.0
                       Barium
                       Chromium (hexavalent)                      1.0                           2.0
                       Chromium (total)                           .5.0                           10.0
                       Lead(2)
                       Nickel                                     5.0                           10.0

                Volatile Organic Compounds
                       l,l-Dichloroethene(3)
                       1,2-Dichloroethene (total)(3)
                       Tetrachloroethene(4)
^                     Trichloroethene(3)
to                     Carbon tetrachloride(3)                    	
QQ             ___^	
                Source: City of Memphis, Sewer Use Ordinance, March 1993

                Notes:
                'Based  on 24-hour flow-proportionate composite sample
                2Cadmium, mercury, and lead discharges are severely restricted due to limitations placed on the disposal of sewage sludge
                containing cadmium, mercury, and/or lead. Actual allowable discharge concentrations for these constituents will be determined
                on a case-by-case basis.
                3No person shall discharge wastewater containing any of the materials listed herein into the municipal sewer system
                or shall have any connection to the municipal sewer system without obtaining written permission from the Approving
                Authority.
                4This parameter is not included in City of Memphis Sewer Use Ordinance.
                mgm95-DDMT-MISC2/005.doc

-------
arsenic, chromium, lead, and nickel.  With the exception of tetrachloroethene, the
remaining VOCs in Table 1 and barium cannot be discharged without written permission
from the approving authority.  Tetrachloroethene is not included in the City of Memphis'
ordinance.  The final permit for city discharge will be negotiated as part of this action.

2.10.2.2  Location-specific ARARs

Location-specific requirements  "set restrictions upon the concentration of hazardous
substances or the conduct of activities solely because they are in special locations"  (53
Fed.  Reg. 51394).  Table 5 lists location-specific ARARs that might be pertinent to this
remedial action.

2.10.2.3  Action-specific ARARs

Performance, design, or other action-specific requirements set controls or restrictions on
particular kinds of activities related to the management of hazardous waste  (52 Fed. Reg.
32496).  Selection of a particular remedial action at a site will invoke the appropriate
action-specific  ARARs that may specify particular performance standards or technologies,
as well as specific environmental levels for discharged or residual chemicals.  Federal
and state  regulations appear in Table 6 and are summarized below.

Well Construction.  State of Tennessee requirements for water production well
construction are promulgated under Tennessee Code Annotated  (TCA) Section 70-2307
Chapter 400-2-2: however, these requirements do not apply under the exemptions stated
in TCA Section 68-46, Chapter 1200-4-9.01(b) whereby wells otherwise regulated  by the
State, hi this case through CERCLA, are not considered water production wells.
However, the Memphis and Shelby County Health Department Pollution Control Section
has promulgated requirements and regulations in the Rules and Regulations of Wells in
• *>wv^  -w». .-.-^ .   £, ____  _ ,. ._| ______ _ __    -.               ___     ____,    __
specific well siting and construction requirements.

Pumping.  Under the Water Withdrawal Registration Act of 1963, Chapter 8-Water
Resources Division, Section 69-8-105 requires that any person withdrawing 50,000 or
more gallons per day (gpd) of water from any source register with the division of water
resources.  A permit is not required.  On the basis of an anticipated pumping rate that
may reach 1 million gpd for the recovery well system, it is anticipated that registration
will be required.

The action-specific ARARs for direct discharge of treatment system effluent are shown in
Table 6.  DDMT is  applying for a City discharge permit. Discharge limits will be
specified  in the permit.

2.10.3   Cost-Effectiveness

The interim action remedy uses a commercially tested technology that affords a high level
of effectiveness proportional to its costs so that the remedy represents reasonable value.
This  action will use  a relatively inexpensive technology to mitigate the spread of the
 mgm95-DDMTMisc./001.WP5                    2-29

-------
contaminated groundwater.  This limited scale containment operation should reduce the
cost of the overall remediation of the groundwater by retarding the migration of the
contaminant plume.

2.10.4 Use of Permanent Solutions and Alternative Treatment
Technologies

The interim  action is designed to minimize the possibility of contamination of the area's
drinking water supply.  This is not the final action planned for the groundwater
contamination.  Follow-on activities include monitoring the groundwater plume and its
response to the IRA. Once  the plume has been fully characterized, subsequent action
may be taken to provide long-term definitive protection, including remediation of source
areas.  To the extent possible, the interim  action will not be inconsistent with, nor
preclude implementation of, the expected final remedy.

2.10.5 Preference for Treatment as a Principal Element

This interim action satisfies  the statutory preference  for treatment of the discharged
effluent (through, at a minimum, treatment at the POTW) as a principal element of the
containment system.  If necessary, onsite treatment will be performed if needed to meet
permit criteria.


                                2.11  References

CH2M HILL, December 1994.  Proposed Groundwater Action Plan.  Defense Depot
Memphis, Tennessee.

Engineering-Science, Inc., August 1993. Engineering Report—Removal Action for
Groundwater.  Prepared for U.S. Corps of Engineers, Huntsville Division.

Engineering-Science, Inc., July 1994.  Focused Feasibility Study: Dunn Field.  Prepared
for U.S. Corps of Engineers, Huntsville Division.

Environmental Science and Engineering, Inc., July 1994. Groundwater Monitoring
Results Report for DDMT.  Prepared for U.S. Army Corps of Engineering Huntsville
Division.

Law Environmental, August 1990. Remedial Investigation at DDMT, Final Report.

Parks, William S., 1990. Hydrogeology and Preliminary Assessment of the Potential for
Contamination of the Memphis Aquifer in the Memphis Area,  Tennessee.  Water
Resources Investigations Report 90-4092.  Prepared in cooperation with the City of
Memphis, Memphis Light, Gas and Water Division.
mgm95-DDMT Misc./OOl .WP5                    2-30

-------
         Part 3
Responsiveness Summary

-------
                Responses to Written Comments Received at
          Public Hearing on the Federal Facilities Agreement and
                     Proposed Interim Remedial Action
                              December 20, 1994
1.  Comments Received from Roosevelt Sanders Jr., 2592 Fontaine Road, Memphis,
TN 38106

It is my suggestion that proposed remedial action should include a larger area of testing.
The land south of DDMT, at one time, was used as a dump.  A record check should be
done to determine whether DDMT has ever used that area for dumping purposes.  My
father told me, in 1964 (when I moved hi that area), that the homes were built on top of
a dump.

It seems to me that the IRA is using the Band-aid approach to what could possibly be a
serious problem.

DDMT RESPONSE:  The Installation Services records were checked and no records of
any dumping in this landfill were found.  Long-time employees of DDMT, who are
familiar with the disposal activities throughout its operational history, were interviewed
concerning their knowledge of any DDMT use of the land to the south of its boundaries
for dumping purposes. None of the employees had any knowledge of DDMT disposing
of any materials south of DDMT. Specifically, Mr. Ulysses Truitt, who worked at
DDMT for more than 30 years, indicated with certainty that no materials were disposed
of in the area south of DDMT.  Historically, DDMT disposed of materials either onsite or
in  permitted landfills operated by the City of Memphis.

As part of the remedial investigation, monitoring wells are proposed to be installed south
of DDMT to determine if any offsite sources are contributing to the contamination under
DDMT.  These monitoring wells may also intercept any contaminants that might be
migrating from the dump reported to be south of DDMT.

The Interim Remedial Action (IRA)  was not designed to address dumping  that was
reported  south of DDMT in the 1960s. Rather,  the IRA was intended as an interim
action to address contamination that  appears to be migrating west of Dunn Field.  This
action will be consistent  with the final remedy, and is intended to meet the objective of
protecting the Memphis Sand Aquifer.  The focus of the IRA is on Dunn Field and
contamination migrating  to the west  of the Field, not on a landfill reported to be south of
DDMT.  By implementing a groundwater IRA, contaminants will be incrementally
removed from the Fluvial Aquifer and will be contained to mitigate migration toward the
Allen Well Field. The IRA will be implemented expeditiously and will continue to
operate until a final remedy is in place.
mgm95-DDMT-Misc/004.WP5                    3-1

-------
Concerns about any material that may have been disposed of at the landfill south of Alcy
Road are valid, but are misdirected at DDMT because it was not a contributor.
However, Mr. Sanders may direct his concerns to the Tennessee Department of
Environment and Conservation (TDEC). That agency is concerned with contamination
resulting from past landfill practices. It is recommended that staff in TDEC's Memphis
and Nashville offices be contacted, starting with the Divisions of Superfund and Solid
Waste.

2. Comment Received from Dorothy Brooks, 1802 Wendy Drive, Memphis TN
38114

I live hi the Nob Hill Subdivision, south of Alcy Road.  I understand that our subdivision
was built on landfill.  Therefore, anything and all lands of materials were probably
dumped there.

Because of the large number of health problems that have occurred and are occurring, the
residents should be informed of the type of dangers that could possibly be present.

I am again requesting that the soil/water in the above stated community be tested.

DDMT RESPONSE:  Ms. Brooks' concerns are valid, but are misdirected toward
DDMT, since it does not have the authority or jurisdiction to make an initial investigation
of a landfill that is not on DoD property.  Because, to the best of its knowledge, DDMT
has not disposed of any material in the landfill to the south of its boundaries, it is not
currently involved in investigating any alleged contamination resulting from past disposal
practices at this  site.  However,  it is recommended that Ms. Brooks convey her concerns
to other responsible agencies.  TDEC may have a permit file on the old landfill.  That
file may either be in the field office in Memphis or in the central office hi Nashville.
The permit file should contain an indication of the types of materials that the landfill was
permitted to receive, and may contain some inspection reports.

Other agencies that may provide assistance include the Environmental Protection Agency
(EPA), Region IV, in Atlanta, Georgia; the City of Memphis; the Memphis and Shelby
County Health Department; Memphis Light Gas and Water (MLGW); and the Memphis
State University Ground water Institute.  Each of those agencies has specific areas of
authority, jurisdiction, and resources.
 mgm95-DDMT-Misc/004.WP5                     3-2

-------