United States
           Environmental Protection
           Agency
              Office of
              Emergency and
              Remedial Response
EPA/ROD/R09-88/023
February 1988     ,
$EPA
Superfund
Record of Decision
            Lorentz Barrel & Drum, CA

-------
  30273-101
   REPORT DOCUMENTATION
          PAGE
                                 EPA/ROD/R09-88/023
  4. Tttlt and Subtitle
   SUPERFUND RECORD OF DECISION
      rentz  Barrel & Drum, CA
           smedial Action
  7. Authors)
3. Recipient's Accession No.
S. Report Oete
              09/25/88
                                                                          8. Performing Orianizetion Rept. No.
                           tddress
                                                                          10. Projeet/Task/Work Unit No.
                                                                          11. Contract(C) or Grent(G) No.

                                                                          (C)

                                                                          (C)
  12. Sponsoring Organization Nam* end Address
   U.S.  Environmental  Protection Agency
   401  M Street, S.W.
   Washington, D.C.  20460
   "t
13. Type of Report & Period Covered

  800/000
14.
  15. Supplementary Notes
  16. Abstract (Limit: 200 words)                                             ~~	'	•
      The 5.4-acre  Lorentz Barrel  &  Drum (LB&D)  site is located  in San Jose,  California,
    about 0.25 mile from San Jose  State University.   The site  lies directly above a major
    source of potable  ground water in the south  San  Francisco  Bay area, with  three public
    water supply well  fields within  one mile of  the  site.  In  1947 the Lorentz  family began
    a  drum recycling operation on  10.5 acres of  land at the site.  Currently, 4.5 acres are
   Capped with  tar and gravel but contains stored drums, 0.75 acre includes  the
   Ireconditioning  facilities.  Drums containing residual aqueous wastes, organic solvents,
    acids, oxidizers,  caustic residues and oils  were received  for recycling.  During the
    early years  of  operation, portions of the site were also leased to other  companies.
    Between 1950 and 1978 a drainage ditch north of  the drum processing building carried
    process wastes  to  a large sump and other ponding areas onsite.  Prior to  1968 wastes
    from the sump were discharged  to a storm drain system.  Sometime between  1968 and 1971
    the discharge was  diverted to  a  sanitary sewer,  and investigations indicate that this
    discharge occurred until 1984.  After this time, liquid wastes were evaporated, drummed
    and disposed of as hazardous waste along with incinerator  ash, residual liquids, and
    sludge.  Subsequent surface runoff was collected and recycled in the hot  caustic drum
    wash.  Since 1981  several investigations have revealed soil  and ground water
    (See Attached Sheet)
 17. Document Analysis a. Descriptors
    Record of Decision
    Lorentz Barrel  &  Drum, CA
    First Remedial  Action
    Contaminated  Media:   gw, soil
    Key Contaminants:   metals  (arsenic, nickel),  organics  (PCBs,  pesticides),  VOCs (benzene,
    b. Identlfiers/Open-Ended Terms  PCE ,  TCE)
   c. COSATI Field/Group
   Availability Statement
(See ANSI-Z39.18)
                                                          19. Security Class (This Report)
                                                              None
                                                          20. Security Class (This Page)
                                                              None
                                         See Instructions on Reverse
          21. No. of Pages
              119
          22. Price
                                                                                   OPTIONAL FORM 272 (4-77)
                                                                                   (Formerly NTIS-3S)
                                                                                   Department of Commerce

-------
                 DO  NOT  PRINT  THESE  INSTRUCTIONS AS A  PAGE  IN  A  REPORT


                                                     INSTRUCTIONS
Optional Form 272, Report Documentation Page is based on Guidelines for Format and Production of Scientific and Technical Rep!
ANSI Z39.1S-1974 available from American National Standards Institute. 1430 Broadway, New York, New York 10018. Each separately
bound report—for example, each volume in a multivotume set—shall have its unique Report Documentation Page.

 1. Report Number. Each individually bound report shall carry a unique alphanumeric designation assigned by the performing orga-
    nization or provided by the sponsoring organization in accordance with American National Standard ANSI Z39.23-1974, Technical *
    Report Number (STRN). For registration of report code, contact NTIS Report Number Clearinghouse.  Springfield, VA 22161. Use
    uppercase letters, Arabic  numerals,  slashes, and hyphens  only, as  in  the following examples: FASEB/NS-75/87 and FAA/
    RD-75/09.                                                                          '                                  .

 2. Leave blank.

 3. Recipient's Accession  Number. Reserved for use  by each report recipient.

 4. Title and Subtitle. Title should indicate clearly and briefly the subject coverage of the report, subordinate subtitle to the main
    title. When a report is prepared in more than one volume, repeat the primary title, add volume number and  include subtitle for
    the specific volume.

 5. Report Date.  Each  report shall carry  a date indicating at least month and year. Indicate the basis on which it was selected (e.g..
    date of issue, date  of approval, date of preparation, date published).

 6. Sponsoring Agency Code.  Leave blank.

 7. Author(s). Give name(s) in conventional order (e.g.. John R. Doe, or J.  Robert  Doe). List author's affiliation  if it differs from
    the performing organization.

 8. Performing Organization Report Number. Insert  if performing organization wishes to assign this number.

 9. Performing Organization Name and  Mailing  Address. Give name, street, city, state, and ZIP code. List no more than two levels of
    an organizational hierarchy. Display  the name of the organization exactly as it should appear in Government  indexes such- as
    Government Reports Announcements & Index (GRA & I).

10. Project/Task/Work Unit Number. Use the project, task and work unit numbers under which the report was prepared.

11.- Contract/Grant Number.  Insert  contract or  grant number under which report was prepared.

12. Sponsoring Agency Name and Mailing Address. Include ZIP  code. Cite main sponsors.

13. Type of Report and Period Covered. State interim, final, etc., and. if applicable, inclusive dates.

14. Performing Organization Code. Leave blank.

19. Supplementary Notes. Enter information not included elsewhere but useful, such as: Prepared  in cooperation with . . . Translation
    of... Presented at conference of ... To be published in ... When  a report is  revised, include a statement whether the new
    report supersedes or supplements the older report.

16. Abstract. Include a brief (200 words  or lesa) factual summary of the most significant information contained  in  the report. If the
    report contains a significant bibliography or literature survey, mention it here.

17. Document  Analysis, (a). Descriptors. Select from the Thesaurus of Engineering and Scientific Terms the proper authorized terms
    that identify the major concept of the research and are sufficiently specific and precise to be used as index entries for cataloging.
    (b).  Identifiers and Open-Ended Terms. Use  identifiers for project names, code names,  equipment designators, etc. Use open-
    ended terms written  in descriptor form for  those subjects for which no descriptor exists.
     (c). COSATI Field/Group. Reid and Group assignments are to be taken from the 1964 COSATI Subject Category List. Since the
    majority of documents are multidisciplinary in  nature, the primary  Field/Group assignment(s) will  be the specific discipline,
    area  of human  endeavor, or  type  of  physical  object. The application(s) will be cross-referenced with secondary Field/Group
    assignments that will follow the primary posting(s).

18. Distribution Statement. Denote  public reusability, for example  "Release unlimited", or limitation for  reasons other than
    security. Cite any availability to the public, with address, order number and price,  if known.

19.420. Security Classification. Enter U.S. Security Classification  in accordance with U.S. Security Regulations (i.e., UNCLASSIFIED).

21. Number of  pages. Insert the total number of pages, including introductory pages, but excluding distribution list, if any.

22. Price.  Enter price in paper copy (PC) and/or microfiche (MF) if known.

       :  :~H3  :  -  331-5:5 (3393)                                                           OPTIONAL FORM Z72 BACK (*-77>

-------
JPA/ROD/R09-88/023
A>rentz Barrel & Drum, CA
Tirst Remedial Action

 16.  ABSTRACT (continued)

 contaminated with numerous metals, organics, and PCBs.  Removal of drums, stored
 hazardous materials, and highly contaminated soil has been conducted at the site.  This
 remedial action will address the offsite contaminated shallow ground water.  Onsite
 contaminated soil and additional shallow and deep ground water remediation will be
 addressed in a subsequent remedial action. The primary contaminants of concern affecting
 soil and ground water are VOCs, including benzene, PCE and TCE, other organics including
 PCBs and pesticides, and metals including arsenic and nickel.

  The selected Expedited Response Action for this site includes: onsite ground water
 pump and treatment using ozone/UV for organic removal and ion exchange for nickel
 removal, with discharge of treated water to a local creek.  The estimated present worth
 cost for this remedy is $3,238,000 with annual O&M costs of $198,000.

-------
                     LORENTZ  BARREL  & DRUM
              ENGINEERING EVALUATION/COST ANALYSIS
                       RECORD OF DECISION
PART 1 - DECLARATION

PART 2 - DECISION SUMMARY

PART 3 - RESPONSIVENESS SUMMARY

-------
                                    0000231
       LORENTZ BARREL & DRUM
ENGINEERING EVALUATION/COST ANALYSIS
         RECORD OF DECISION
              PART 1
            DECLARATION

-------
                                                    0000231
                       RECORD OF DECISION
                          DECLARATION

Statutory  Preference for  treatment  as a  principal element  is
met.

SITE NAME AND LOCATION

Lorentz Barrel & Drum
San Jose, California

STATEMENT OF BASIS AND PURPOSE
                            
-------
                                                 0000231
    o    construction and  operation  of a groundwater  treatment
         system; and

    o    disposal of  treated groundwater  to the  storm  sewer,
         from which it flows to  Coyote Creek.

DECLARATION

The  selected  remedy  is  protective  of  human  health  and  the
environment,  attains  Federal and  state  requirements  that  are
applicable  or  relevant  and appropriate to the  remedial  action,
and  is  cost  effective.   This  remedy  satisfies  the  statutory
preference  for  remedies  that reduce  tozicity,  mobility,  and/or
volume  as  a  principal   element.   It  also  utilizes  permanent
solutions to the maximum  extent  practicable. The  applicability
of  the   5-year  facility  review  provision  will  be  determined
after the RI/FS is completed.
         . 2.1.96
Date                      Signature (DRA)
                          Signature (AA/RA)
                              1-2

-------
                                                   00002U1
                    Lorentz Barrel  and Drum

                       RECORD OF DECISION

                Concurrence — Superfund Program
                                                  14-1 SP
Mary Rasters                                     / '   / Date
Remedial Project Manager
South Bay Section  (T-4-5)             *
Amy zimpfer           /                            /      Date
Chief
South Bay Section  (T-4-5)
Phil Bobel                                          /   'Date
Chief
Superfund Remedial Branch (T-4-A)
                                                   */»/#
                                                        Date
 ssistant Director for Superfund
Toxics and Waste Management Division (T-4)

-------
                    Lorentz Barrel and  Drum

                       RECORD OF DECISION

          Concurrence — Toxics and Management Division
0000231
Jeff Zelikson                                        Date
Director            .
Toxics and Waste Management Division

-------
                                                 0000231
                    Lorentz Barrel and Drum

                       RECORD OF DECISION

            Concurrence —  Water Management Division
Harry Seraydarian                                    Date
birect.or
Water Management Division

-------
                                                   0000231
                    Lorentz Barrel  and Drum

                       RECORD OF DECISION

         Concurrence — Office of Policy and Management
Nora McGee (Date
Director
Office of Policy and Management

-------
                     Lorentz Barrel and Drum

                        RECORD OF DECISION

            Concurrence — Office of Regional  Counsel
7l(
               .\\ tX'-^C,.
Nancy MarVel                                            Date
Regional Counsel
Office of Regional Counsel

-------
                                                       0000231
                      Lorentz Barrel and Drum

                         RECORD  OF DECISION

               Concurrence — Air Management Division
y^Dave Howekamp
  Director
  Air Management Division  (A-l)
ate

-------
                                    0000231
       LORENTZ BARREL & DRUM
ENGINEERING EVALUATION/COST ANALYSIS
         RECORD OF DECISION
              PART 2
          DECISION SUMMARY

-------
                                                    0000231
                     LORENTZ BARREL & DRUM

    ENGINEERING EVALUATION/COST ANALYSIS RECORD OF DECISION

                       DECISION SUMMARY


                       TABLE OF CONTENTS
                             \

SECTION                                                   PAGE

1.0  SITE LOCATION AND DESCRIPTION	    1-1

2.0  SITE HISTORY AND ENFORCEMENT ACTIVITIES  	    2-1

     2.1  HISTORY OF SITE ACTIVITIES	    2-1
     2.2  HISTORY OF SITE INVESTIGATIONS	    2-1
     2.3  HISTORY OF ENFORCEMENT ACTIONS  	    2-2

3.0  COMMUNITY RELATIONS HISTORY  	    3-1

4.0  SCOPE OF RESPONSE ACTION	    4-1

     4.1  OBJECTIVES OF RESPONSE ACTION 	    4-1
     4.2  RELEVANCE TO SITE REMEDIATION STRATEGY  .  .  .    4-2

5.0  SITE CHARACTERISTICS	    5-1

     5.1  PREVIOUS INVESTIGATIONS 	    5-1
     5.2  SOURCES OF CONTAMINATION	    5-5
     5.3  NATURE AND EXTENT OF CONTAMINATION IN THE
          SHALLOW AQUIFER 	    5-13
     5.4  HUMAN AND ENVIRONMENTAL EXPOSURE PATHWAYS .  .    5-21

6.0  SUMMARY OF SITE RISKS	    6-1

     6.1  CONTAMINANTS OF CONCERN	    6-1
     6.2  EXPOSURE ASSESSMENTS  	    6-1
     6.3  RISK CHARACTERIZATION	    6-4

7.0  DOCUMENTATION OF SIGNIFICANT CHANGES 	    7-1

8.0  DESCRIPTION OF SHALLOW AQUIFER TREATMENT AND
     DISPOSAL ALTERNATIVES  	    8-1

     8.1  APPLICABLE OR RELEVANT AND APPROPRIATE
          REQUIREMENTS  	    8-1
     8.2  TREATMENT TECHNOLOGIES  	    8-4

-------
                                                  0000231
                 TABLE OF CONTENTS (Continued)
SECTION                                                    PAGE

9.0  SUMMARY OF THE COMPARATIVE ANALYSIS OF
     ALTERNATIVES 	     9-1

     9.1  COMPARISON OF EE/CA VAND FS GUIDANCE
          CRITERIA	     9-1
     9.2 .COMPARISON EVALUATION METHODOLOGY 	     9-1
     9.3  COMPARISON OF ALTERNATIVES  	     9-5
     9.4  TREATED EFFLUENT DISPOSAL 	     9-7

10.0 THE SELECTED REMEDY	     10-1

11.0 STATUTORY DETERMINATIONS 	     11-1

     11.1 PROTECTIVENESS OF HUMAN HEALTH AND THE
          ENVIRONMENT	     11-1
     11.2 ATTAINMENT OF APPLICABLE OR RELEVANT AND
          APPROPRIATE REQUIREMENTS  	     11-1
     11.3 COST EFFECTIVENESS	     11-1
     11.4 UTILIZATION OF PERMANENT SOLUTIONS AND
          ALTERNATIVE TREATMENT TECHNOLOGIES TO
          THE MAXIMUM EXTENT PRACTICABLE  , 	     11-2
     11.5 PREFERENCE FOR TREATMENT THAT REDUCES    '  .
          TOXICITY,  MOBILITY AND VOLUME AS A
          PRINCIPAL ELEMENT 	     11-2

12.0 REFERENCES	     12-1
                              ii

-------
TABLE
                                                  0000231 '
                        LIST OF TABLES
PAGE
 5-1   PREVIOUS INVESTIGATIONS 	     5-6
 5-2   GROUNDWATER INVESTIGATIONS  	     5-12
 5-3   SUMMARY OF MONITORING WELL DATA	     5-14
 5-4   SUMMARY OF HIGHEST DETECTED CONTAMINANT LEVELS  .     5-18
 5-5   RESULTS OF TRC GROUNDWATER ANALYSES 	     5-19
 6-1   CONTAMINANTS OF CONCERN IN THE SHALLOW
       GROUNDWATER AT LB&D	     6-2
 6-2   CANCER RISK FROM GROUNDWATER INGESTION:
       WORST CASE SCENARIO	     6-5
 6-3   INHALATION DOSES, CANCER POTENCY ESTIMATES,
       AND LIFETIME CANCER RISK FOR UNCONTROLLED
       AIR STRIPPER EMISSIONS  	     6-6
 8-1   FEDERAL AND STATE OF CALIFORNIA REGULATORY,
       ADVISORY, AND ACTION LEVELS FOR ANALYTES
       IN GROUNDWATER	     8-2
 8-2   SHALLOW GROUNDWATER CLEANUP OBJECTIVES  	     8-5
 8-3   SUMMARY OF COSTS FOR TREATMENT ALTERNATIVES  ...     8-9
 9-1   TECHNOLOGY SELECTION CRITERIA 	     9-2
 9-2 ,  COMPARISON OF ALTERNATIVES	     9-6
10-1   ESTIMATED (-30%, +50%) COSTS FOR OZONE/UV
       TREATMENT ALTERNATIVE 	    10-3
                        LIST OF FIGURES
FIGURE

 1-1  SITE LOCATION MAP 	
 1-2  GENERAL MAP OF SITE VICINITY  ;  	
 1-3  SITE FACILITIES 	
 2-1  LOCATIONS OF PREVIOUS SOIL EXCAVATIONS  .  .  ,
 5-1  GENERAL GEOLOGIC CROSS-SECTION  	
 5-2  FORMER MONITORING WELL LOCATIONS  	
 5-3  APPROXIMATE EXTENT OF CONTAMINATION 	
 6-1  CONCEPTUAL EXPOSURE MODEL - SHALLOW
      GROUNDWATER CONTAMINATION 	 .  .  ,
 8-1  PROPOSED EXTRACTION WELL FIELDS .......
 8-2  FLOW DIAGRAM FOR LIQUID PHASE GAG TREATMENT .
 8-3  FLOW DIAGRAM FOR GAG/AIR STRIPPING TREATMENT
 8-4  FLOW DIAGRAM FOR OZONE/UV/GAC TREATMENT
      SYSTEM  	
Paoe

1-2
1-3
1-5
2-3
5-2
5-4
5-20

6-3
8-7
8-10
8-12

8-14
                              iii

-------
                                                   0000231
1.0  SITE LOCATION AND DESCRIPTION

The Lorentz Barrel  & Drum (LBSJD)  site is located  at  1515  South
Tenth  Street,  on the southwest  corner  of the  intersection  of
East Alma Avenue and South Tenth  Street  in  the  southern portion
of  the  City  of  San  Jose,  Santa  Clara  County,  California
(Figure 1-1).  A land use map of  the site and vicinity is  shown
in Figure 1-2.
                              \
The residential district  to  the north and east of the LB&D site
includes .Spartan Field  (San  Jose  State  University  football
stadium),  San Jose  Bees  Stadium  (City  of San  Jose),  and  San
Jose State  University recreation  fields.   The  closest  housing
to  the  site  consists  of  San  Jose  State University  student
housing, roughly 1/4 mile north of the site.

Topography  of the  site is  nearly level,  with  a  slight  slope
from the southwest  corner to the northeast corner.  The highest
elevation  at  the southwest  corner is 106  feet  and  the lowest
point at the northeast corner is  102 feet above sea level.

The site  is located in the southeastern corner  of the San Jose
subarea  as  defined  by  The  California  Department  of  Water
Resources   (DWR,  1967).   This   subarea  is  one  of  the  most
important  natural  source  of  groundwater  in  the  south  San
Francisco Bay  area  ("south bay").  The deep aquifer (250 to 400
feet  below  ground  surface)  is  a  major  source  of  potable
groundwater,  from which it is estimated  that Santa Clara Valley
extracts 107,000 acre-feet per  year.   Three public water supply
well fields (owned  by  San  Jose Water Company),  located at the
12th Street,  Cottage Grove,  and  Needles  Stations,  are within
1 mile  of  the  site.   A San  Jose  State University  well  is
located at the Spartan Stadium.

The  major  surface   water stream in  the  vicinity  is  Coyote
Creek.    It  is  less  than 1/2  mile  from the  site,  toward  the
northeast.   Coyote  Creek  perennial  flows  are  regulated  by
Coyote  and Anderson  reservoirs,  which  are  controlled by  the
Santa Clara Valley Water District.

At  the time  drum  processing  operations  started  in   1947,  the
site  included  10 1/2  acres  of  land.   The  current   site  is
L-shaped  and covers  5  1/4  acres  of  which approximately  4 1/2
acres  are  capped with  tar  and gravel.   The  area that is  now
sealed was  used for  drum storage and covers  sections  of  soil
which were discolored and possibly contaminated.
                             II-l-l

-------
                                   0000231
Spartan
 Stadium
  San Jose
Muni Baseoall
  Stadium
                    CURRDJT LBtD
       LORENTZ BARREL

         & DRUM SITE
                           FIGURE 1-1

                           SITE LOCATION

                           LORENTZ BARREL fc DRUM

-------
   l^&H'i
V^ ':$,.'%*{**•&*>'*'	-\
«^,A':§fe:y ^^'   V ' \  ::r"
                              220O
   LEGrEND

K  RE5IDEMT/AL
             27OO
6  COMMERCIAL

KA  56HOOL6, 6rOK.T$ COMPLEX,
                O
                o
    FIGURE 1-2


    GENERAL MAP OF SITE
    VICINITY

    LORENTZ BARREL ( DRUM

-------
                                             0000231
The remaining 3/4 acre includes five buildings which housed the
drum reconditioning facilities.  Two sumps and one open storage
bin adjacent to  the facility  have  held  liquid and sludge.  The
facilities show  signs  of extended use  with  minimal  upkeep, as
evidenced  by  eroded  concrete,  rusted  metal structures,  and
conduits  in  various  stages of disrepair.  Figure 1-3 shows the
locations of the onsite facilities.
                            II-1-4

-------
                                                                  0000231
          Pacific Sandblast Property
         ~\
                                                EAST ALMA AVENUE
Western Pacific
Railroad Easement
M947, 0.4 acres)
                       Arata Prooerty
                       (1981, 1.34 acres)
                                                                r
                                                                   e
                                                                 LJ

                        Present Lorentz
                        Barrel & Drum Site
                        (19B8. 5.25 acres)
                        Norton/Phelps  Property
                        (1950. 3.4 acres)
                                                                             100
                                                             200
                  LEGEND
1  Treatment Facility
2  Processing Facility
•*  Former location of
•*  Lorentz residence
4  Incinerator
5  Shop and  Bathrooma
6  Storaga Facility
7  Warehouse and Office
8  Former Sump
9  Existing Sump
       Excavations
                                                                         SCALE IN FEET
FIGURE  1-3
SITE FACILITIES
LORENTZ BARREL & DRUM

-------
                                                  0000231
2.0  SITE HISTORY AND ENFORCEMENT ACTIVITIES

2.1  HISTORY OF SITE ACTIVITIES

The  Lorentz  family  started  recycling  drums   at  the  site  in
1947.  During  the early years,  portions of the  site were also
rented or  leased to other  companies.   Several facilities  were
in operation  around  1954,  including an autowrecker,  a junkyard,
a  roofing   company,  a  construction company,  and  sandblasting
services.

Drums  for'  recycling  were received  from  both private and public
sources  throughout  California  and  Nevada.    Private  sources
included over 800 different  companies,   representing chemical,
food,  health  care,   electronics,   paint,   ink,    and   paper
industries.   Public  sources  included  military bases,  research
laboratories,  and county agencies.  Drums  arrived  at  the  site
containing  residual  aqueous  wastes,  organic   solvents,  acids,
ozidizers,   and  oils.   (Under  current  law,   drums   sent  to  a
recycling  facility can contain no more  than 1 inch  of residual
material.)     Lorentz   Barrel   &   Drum  (LB&D)   also  received
polyethylene carboys or drums containing caustic residues.

From  the   1950s  until  some  time  between 1976  and  1978,  a
drainage   ditch   (which  probably   drained  processing  waste)
existed north  of  the  processing structure (buildings 1 and 2 in
Figure 1-3).   The northeastern corner of  the  site  had  a large
sump  (30  feet by 80   feet)  from  the  1950s  through  the  late
1970s.  Aerial photographs of the  area revealed the  presence of
liquids  in the sump,  drainage  ditch,  and various ponded areas
during this period  of time.    The sump  appeared  to  have  been
filled in with soil prior to 1980.

Research into San Jose City  records  has  shown  that  prior  to
1968, the waste stream  from the  drum recycling processes flowed
from  the processing structure,  through  the drainage ditch,  to
the  large  sump in the northeast  corner of the  site.   It  was
then  discharged  to  the storm  drain system.   Between  1968  and
1971  the   discharge   was   diverted  to  the   sanitary  sewer.
Previous investigations have  indicated  that  discharge  to  the
sanitary sewer  ceased in  1983 or  1984.  After 1984,  liquid
wastes  were   reportedly   reduced   in   volume   by  evaporation,
drummed  and   disposed  of  as   hazardous   waste   along   with
incinerator ash,  residual  liquids,  and  sludge.   Surface runoff
was  reportedly collected and  recycled  in the hot caustic wash
cycle of the drum recycling process.

2.2  HISTORY OF SITE INVESTIGATIONS

Since  1981  there  have  been  several  environmental  sampling
studies at  the LB&D  site aimed at investigating the  extent  and
nature of  contamination.   The  California Department of  Health


                            II-2-1

-------
                                                  0000231
Services  (DHS),  their  consultants and  various consultants  to
LB&D  have  collected  soil  and groundwater  samples from  onsite
and offsite monitoring wells.  On six occasions,  groundwater or
soil  samples  were  taken  from  the  site.   Numerous  metals,
organics, and polychlorinated biphenyls  (PCBs)  were found above
Total Threshold  Limit Concentrations (TTLC).   Sampling  results
from  these  efforts  are  summarized in Section  5.0  of  this
Decision Summary.
                             \
2.3  HISTORY OF ENFORCEMENT ACTIONS

Since 1966, there have been many  regulatory actions at the LB&D
site.  A complete chronological  list of enforcement  events  is
given  in Appendix 8  of  the Engineering  Evaluation  and  Cost
Analysis (EE/CA) (Ebasco, May 1988).

In summary, the major enforcement episodes have been:

    o    1982  -   The  DHS  investigated   soil  contamination,
         resulting in a Remedial Action Order in 1987.

    o    1982  -  The  Regional   Water   Quality  Control   Board
         (RWQCB)    investigated     groundwater    contamination,
         resulting in Clean Up & Abatement Order No. 86-001.

    o    1984  -  The  United  States  Environmental  Protection
         Agency (EPA) formally proposed  LB&D  as a candidate for
         the National Priority List.

    o    1987 -  The  LB&D  facility ceased  operation  due to  a
         temporary restraining order  from DHS.  The EPA assumed
         the   lead   agency   responsibility   for   the   site
         remediation.

    o    Since 1984,  several parties have  excavated  known "hot
         spots"   of  contaminated  soil   from  the  sump  areas.
         These include three contractors hired  by LB&D,  as well
         as   a   DHS    contractor    (Canonie    Environmental).
         Excavated areas are shown in Figure 2-1.

    o    In December  1987,  EPA initiated an  Expedited Response
         Action (ERA)/Operable Unit for  the shallow groundwater
         plume  extending northward  from the  site.   The EE/CA
         recommended extraction of  the groundwater,  followed  by
         treatment and disposal to the storm sewer.

Other agencies which  have  cited  LB&D for some type of violation
include:

    o    California Department of Fish & Game (CDFG);
    o    San Jose/Santa Clara Water Pollution Control  Plant;
                             II-2-2

-------
                                                             0000231
         Pacific Sandblast Property
                                             EAST ALMA AVENUE
                      Arata Property
                      (1981. 1.34 acres)
                       Present Lorentz
                       Barrel & Drum Site
                       H988, 5.25 acres)
                    _|_ Norton/Phelps Property
                       (1950, 3.4 acres)
Western Pacific
Railroad Easement
(1947. 0.4 acres)
      LEGEND
 2|
 3
 4
           1—84
Excavation depth 2.0 leet.
CONSERVTECH 3-85
Excavation depth 2.0  feet.
REED CORPORATION 6-85
Excavation depth ?
CAN ON IE 10-87
Eicavation depth 4-12 feet.
                    100
                   =±=
                                                                    SCALE IN FEET
FIGURE 2-1
LOCATIONS  OF  PREVIOUS
SOIL EXCAVATIONS
LORENTZ  BARREL & DRUM

-------
                                          000(1201
o    California Department of Occupational Safety  &  Health
     (OSHA);
o    San Jose Fire  Department; and
o    Santa  Clara   District  Attorney's  Office  (Civil  and
     Criminal Proceedings).
                        II-2-4

-------
                                                   0000231
3.0  COMMUNITY RELATIONS HISTORY
A history of the  community  relations  activities  at  the Lorentz
Barrel  &   Drum  (LB&D)   site,  the  background  on  community
involvement and concerns,  and specific comments  and responses
on  the Engineering  Evaluation and  Cost  Analysis  (EE/CA)  are
summarized  in   the  Responsiveness  Summary   (Part  3)  of  this
Record of Decision (ROD).       .
                            II-3-1

-------
                                                      0000231
4.0  SCOPE OF RESPONSE ACTION

4.1  OBJECTIVES OF RESPONSE ACTION

This Expedited Response Action  (ERA)/Operable Unit  will address
the  three principal hazards  posed by the  contaminated shallow
aquifer.  These  hazards  are:   further migration  of the  plume;
potential  plume  discharge  into   Coyote  Creek;  and  potential
contamination of the drinking-water supply  (deep  aquifer).   The
United  States Environmental  Protection Agency (EPA)  believes
that  the .drinking  water  supply   is  potentially at  risk,  and
action    should    not   be    delayed   until   the    Remedial
Investigation/Feasibility Study (RI/FS)  process  is  completed.

4.1.1  Plume Migration

A groundwater extraction system is proposed in  order  to prevent
existing  contamination  in the  shallow aquifers from  migrating
deeper  and  farther  from the  site.  The groundwater  extraction
system  will  consist of  a series  of  linear well fields.   Each
row  of  extraction wells,  pumped  simultaneously,  will  create  a
trough  in the water table beyond which groundwater should  not
flow.  Final design of the extraction system will be  based  upon
data obtained  during  the RI  (which has already been  initiated)
concerning aquifer yield and water quality  parameters  which can
affect   system  hydraulics   (e.g.,   hardness)   and   effluent
limitations (e.g., nickel).

4.1.2  Plume Discharge to Covote Creek

Existing  data  suggest that portions  of  the shallow aquifer  are
hydraulically  connected   with   (i.e.,   discharge  to)   Coyote
Creek.  As  a  result,  contamination  in  the shallow aquifer  may
lead to  Coyote Creek contamination,  posing a threat  to aquatic
life and  human populations  (via fish or shellfish  ingestion or
dermal  contact).   The proposed extraction system  will attempt
to  retard  north and  northeasterly  migration  of   the  plumes
toward Coyote Creek, thus preempting  such  a threat.

4.1.3  Contamination of the Drinking  Water  Supply

The  San Jose  Water  Company  relies  on water  contained in  the
deep    aquifer    underlying    the     contaminated    aquifer.
Contamination of the deep  aquifer could eventually occur as the
result  of  discontinuities  in  the   50-foot   aquitard,  either
natural  or  as  created around  abandoned  private  supply wells
located within the plume  areas  (see  Chapter  5.0  for a  more
detailed  discussion  of  the area's  groundwater  regime).    In
June,  five  San  Jose  Water  Company  municipal  wells   were
sampled.  The  analytical  data  are not yet  available,  but  those
                             II-4-1

-------
wells will  be  sampled again during the RI,  and  results will be
presented  in RI  report.   To  date,  no  contamination  has  been
found in the San Jose Water Company municipal wells.

The  proposed   extraction   and  treatment  system  will  remove
contaminated  water   from   the  shallow  aquifer   and  control
continued  lateral  and/or  vertical  spreading  of  the  plume.
These   actions  will  greatly,  reduce  the   possibility   of
contamination of potable water supplies.

4.2  RELEVANCE TO SITE REMEDIATION STRATEGY

The  remedial actions taken to date have  been  aimed at reducing
or  stabilizing further  infiltration  of  contaminants  into  the
shallow  aquifer.    These   actions   have  included  removal  of
contaminated  drums  from  the  site/   drainage  of  the  existing
storage  tanks;   removal   of   the  heavily  contaminated  soil,
particularly  underneath the  former  northeast sumps;  and  (in
early 1988)  paving most of  the site to  preclude surface water
infiltration  from  being  a  continued  vector  of  contaminant
transport into groundwater.

The  proposed action  will  further EPA's  interim  remediation of
the  site by retarding contaminant migration in  groundwater and
removing    and    treating    some   of   the   water   presently
contaminated.   This  action  is  referred  to  as  ERA/Operable
Unit 1,  and  it  is   considered  to  be  consistent with  future
action expected to be implemented  to  permanently remediate site
conditions.  While the  ongoing RI/FS will include evaluation of
potential source removal (i.e.,  contaminated soils)  the problem
is  mainly  one of  groundwater  contamination,  a principal remedy
of which is  groundwater pumping  and  treatment.  The remediation
presented  in this ROD  is  therefore  relevant  to  and  consistent
with the overall site remediation strategy.
                             II-4-2

-------
                                                  000('231
5.0  SITE CHARACTERISTICS

5.1  PREVIOUS INVESTIGATIONS

The Lorentz  Barrel  & Drum (LB&D)  site  has been the  subject of
numerous  investigations.   The following discussion  of regional
and site-specific  hydrogeology has been  adapted from  a  report
entitled   "Technical  Memorandum:    Preliminary  Hydrogeologic
Assessment"   (CH2M   Hill,   November  19873),  as  modified  by
observations  and  measurements  made  by  Ebasco in   a  limited
sampling  program  performed   in   June   1988  and   bench  scale
treatability-related studies done in July/ August 1988.

5.1.1  Regional Hydroaeolooy of the Santa Clara Vallev

The LB&D site  lies  near the  center  of the Santa Clara  Valley
between  the Santa  Cruz  Mountains  to the west  and  the  Diablo
Range  to the east.   The Santa Clara  Valley  is  a broad alluvial
basin  trending  northwesterly.  The  sediments  are divided  into
the  lower  Plio-Pleistocene  Santa  Clara  Formation,  which  is
somewhat  consolidated and  has  been  deformed,  and   the  upper
Quaternary  alluvium,  which is poorly consolidated.   Both units'
consist  of  interbedded gravel, sand,  silt,  and clay,  and  they
cannot  be  reliably  differentiated  in well  logs   (CH2M  Hill,
February 1987).

The San  Jose subarea,  in which  LB&D is located,  is considered
one of the  most  important parts  of the  South  Bay  Groundwater
Basin   due   to  the   thickness    and   permeability   of   the
water-bearing units.  At  least two major water-bearing units or
aquifers are believed to exist in the LB&D area, separated  by a
marine clay  layer or aguitard, formed during past incursions of
San Francisco  Bay.   The upper water-bearing unit is  a shallow
aquifer  zone that  may be confined.   Below this  is  an aquitard;
below the aquitard and approximately  250 feet  below  the surface
lies the stressed  confined  aquifer  zone  from  which  municipal
wells are pumped.   The lateral extent of this  major  aquitard is
not fully known, but it seems to be present in the LB&D area.

5.1.2  Site-Specific Hydrogeolooy

Within the  site,  the sediments are  primarily  composed of fine-
grained, unconsolidated  silts and  clays  with interbedded  sand
and gravel lenses.

A  generalized cross-section  of  the  site-specific  hydrogeology
is shown in  Figure  5-1.   Based on the  information available,  a
layer  of  clayey-silt underlies the  site to a depth  of about 5
feet.   Beneath  this  is  a layer of sand and  gravel which  ranges
from 2 to  15 feet  thick.  Below the  sand  and  gravel  layer  is a
silty  clay  layer  to about  70 feet below  surface.   This  layer
                             II-5-1

-------
       s
  110-    HW-I
MW-1
  100-
   00—
-  00-
I
III
-«  TO —

in
VI
ui
O

"  •«-
ui
_i
™  50-
   «0 —
   JO —
   JO —
MW-S
MW-4
  MW-I
                                                        MW.I
                                                                     FIGURE 5-1

                                                                     GENERAL GEOLOGIC CROSS-
                                                                     SECTION (adapted from
                                                                     CH2M Hill PSAR, February 1987)
                                                                     LORENTZ BARREL & DRUM

-------
                                                  0000231
contains  scattered  sand  lenses  which  may   or   may  not  be
connected  to  the  overlying   sand.   Below  the clay  layer  is
another  sand  and  gravel  layer  approximately  15 feet  thick.
Well  locations used  to establish  the  onsite  stratigraphy and
groundwater levels are shown in Figure 5-2.

Based  on previous  sampling  by  DHS and  EPA,   there  are  three
aquifers  of  concern  at the  site:  a  potential  shallow  water
table  that  could be  affected^ by  seasonal  recharge;  a shallow
upper  aquifer;  and  a  deep  aquifer.    Each  of   these  three
aquifers are described in the following sections.

Shallow Water Table

It is  possible that  a seasonal shallow water table  could  exist
above  the  silty clay layer.   This water table  was not found by
either DHS  or EPA.   However,  both  of  those previous sampling
events occurred  following  extended  dry  periods.  It is possible
that a seasonal  water table could  form during  the  wet season.
If  so/  then  it  is likely that  it would be contaminated.   The
RI/FS will address this potential seasonal aquifer.

Shallow Upper Aquifer

Data  on  the  shallow upper aquifer are based  on  two sampling
events: one event  in October  1986 by DHS;  and the  second during
August 1988  by EPA.  The  latter sampling followed  2  years  of
drought.  During both events,  the groundwater  depth was roughly
25 feet  below ground surface.   This places the groundwater in
the  silty clay.   The shallow groundwater  appears  to be  in  a
semi-confined  aquifer.   The August 1988 sampling  showed  that
the  potentiometric surface of  the groundwater  was  generally  1
to  5 feet  above where  the  groundwater was  first  encountered
during drilling,  indicating  that the upper  groundwater surface
is confined by the silty clay  layer.  The October  1986 sampling
by DHS showed  the presence of  an  unsaturated zone  at the 75
foot depth, which is below the shallow  upper  aquifer.  However,
the  integrity  of  the  well  that  was used   to  identify  the
unsaturated zone has  been  questioned by State  hydrogeologists.
The  presence  of the  unsaturated zone  below the  shallow  upper
aquifer is therefore not conclusive.

The direction of flow in the shallow upper aquifer is generally
northward.   However,   the  flow  direction  may  have  changed
because  of  the recent drought.   Data  collected  by  DHS  in
October  1986   indicated  a northward flow,   with  a  groundwater
gradient of  0.0015 ft/ft.   However,  data  collected by EPA  in
August  1988  (after  2  years  of  drought)  showed  a  negligible
northward gradient and  a slight  eastward flow.   It  is believed
                             II-5-3

-------
                                                                    0000231
                                   MW-7<
                                                 MW-6,
in
0.
                  Pacific Sandblast Property
                                                    EAST ALMA AVENUE
                                                         MW-4
                             Arata Prooertv
                             (1961, 1.34 acres)
                                                                  *    i
                                                    M£-1   /    /  n
                                                 MW-2
                              Present Lorentz
                              Barrel & Drum Site

                              (1988. 5.25 acres)
                               Norton.'Pheips Property

                               (1950. 3.4 acres)
 ii

LEGEND


Monitoring well


1987 Excavations


Existing sump
                                                                         100
                                                                  200
                                                                      SCALE IN FEET
                                                       FIGURE 5-2

                                                       FORMER  MONITORING
                                                       WELL LOCATIONS

                                                       LORENTZ BARREL & DRUM

-------
                                                 0000231
that the August  1988  data are strongly affected by the drought,
and  do   not  reflect  the   long-term  historical  or   future
groundwater properties.

Slug tests  to measure the characteristics of  the  shallow upper
aquifer were  conducted by EPA  during August  1988.  The  tests
were done using  two monitoring  wells that had screened sections
extending  10  feet into  the  30-foot  saturated  zone  of  the
aquifer.   Slug  tests  are considered to  be  accurate  only  to
within  an order of  magnitude.   The  slug  tests   indicated  an
apparent  aquifer  transmissivity  (T)  of  0.22  gpm/ft  and  a
storitivity  (S)  of  0.001.    Assuming   that   the  aquifer  is
homogeneous,  the  calculated  radius  of  influence  for  a  5  gpm
extraction well would be 50 feet, with a 10 foot drawdown.

Groundwater  monitoring by  DHS  and  EPA  have  shown  that  the
shallow  upper   aquifer   has  been   contaminated  by  the  LB&D
operations.  This indicates that the silty clay layer  above the
shallow upper  aquifer has not  prevented vertical  migration  of
contaminants.  Additional hydrogeological data will be  needed
to fully design the shallow aquifer extraction system.

Deep Aquifer

Based on data  collected by.DHS,  the LB&D site is underlain by a
deep  aquifer  with an apparent  water  table  roughly  at  the
100-foot  depth.   The  deep  aquifer  is  used 'for  municipal
drinking water supplies.   The groundwater flow  direction  in the
deep aquifer  is  governed by  troughs created by municipal well
fields.  No sampling of the deep aquifer near the  LB&D  site has
yet been  conducted.   It  is therefore not yet  known whether the
silty  clay  layer  prevents  vertical  migration  of  contaminants
between  the   shallow  upper  aquifer  and  the  deep   aquifer.
Sampling of  the deep  aquifer will  be conducted  in the  future
RI/FS for the LB&D site.

5.1.3  Soil and Groundwater Contamination

Previous   investigations   of   contamination   of   soil   and
groundwater at the LB&D  site date  back  to  1981,  as summarized
in  Table  5-1.   Also  included  in  Table   5-1 are  dates  and
locations  of  soil excavations  performed as  partial  remedial
actions.    Table  5-2  summarizes   the  history   of   previous
groundwater investigations done at the site,  in terms  of  dates,
contractors, and parameters measured.

5.2  SOURCES OF CONTAMINATION

Residues contained in the used  barrels  and drums  accepted for
processing   at   the  site,    incineration   products  of   those
residues,   and   other  chemicals  used   to  handle,  store,  or
recondition  the drums  gradually contaminated  site  soils  and
groundwater.

                            II-5-5

-------
                                                                         TABLE 5-1
                                                  SUMMARY OF SAMPLING ACTIVITIES TO DATE AT THE LB&D SITE
                                                              (August 1981 through July 1988)
                                                                                        Page 1 of 6
DATE
SAMPLED CLIENT
8-81 DHS
9-82 LB&D
10-82
SAMPLED OR
PERFORMED
BY
DHS
Associated
Labs
ANALYZED BY
DHS
Associated
Labs
ACTIVITY
25 surface soil
samples around
site
35 subsurface
soils (A few
ANALYTE,
METHOD
Metals. Purgeables (EPA
624) Organophosphorus
Pesticides (EPA 614)
Chlorinated Pesticides/
PCBs (EPA 608)
Metals, Chlorinated
Pestlcldes/PCBs
RESULTS
ABOVE TTLC
(Soil)
Cd, Cr. Pb
PCBs. DOE
Pb. N1
PCBs. ODD. DDE
RESULTS ABOVE
ACTION CRITERIA
(Groundwater)
N/A
N/A
ALSO DETECTED
(Above Background) .
Toluene. Xylenes.
Ethylbenzene, Dtazlnon,
Malathton. Ethlon. etc.
g-BHC. Heptachlor.
Heptachlor Epoxide
Cr
DDT
10-83        LBtD        Feuersteln     B&C
11-83        LB&D        Geotechnlcal   B&C
                         Consultants
                         for
                         Feuersteln
11-83        LB&D       .Feuersteln     N/A
 1-84        LB&O        Feuersteln    B&C
sediment/liquids
from around site)

18 surface soils
along drainage
ditch

Monitoring wells
1 & 2 Installed
 - soils sampled
   In borewells
   at 10'  depth
 - groundwater
   from wells
   1 & 2 sampled

Excavation of
soil In & around
drainage ditch

12 soil samples
taken at base of
excavation
                                                                         (EPA  608)
Chlorinated Pesticides/
PCBs (EPA 608)
Metals. CN-, Phenols
Purgeables (EPA 625)
Chlorinated Pesticides/
PCBs (EPA 608)
Extractables (EPA 625)
Excavation only; no
samples taken
Chlorinated Pesticides/
PCBs (EPA 608)
PCBs.              N/A
chlordane. ODD.
DDE
None
N/A
PCBs.
chlordane,
ODD. DDE. DDT
N/A
N/A
                        DDT
As. benzene.'   Soil: Various VOCs
chloroform,    (TCE. Xylenes, etc.)
PCE. TCE.
1.1-DCE        Various VOCx and
               semi-VOCs
   N/A
None
                                                                                                                                                             o
                                                                                                                                                             o
                                                                                                                                                             CO

-------
                 TABLE 5-1 (Continued)
SUMMARY OF  SAMPLING ACTIVITIES TO DATE AT THE LB&O SITE
            (August 1981 through July 1988)
          Page 2  of  6
DATE
SAMPLED CLIENT
1-84 LB&D
1-84 LB&D
1-84 LB&D
1-34 LB&D
3-85 DHS
SAMPLED OR
PERFORMED ANALYZED BY
BY
Feuersteln
Feuersteln B&C
Geotechnlcal B&C
Consultants
for
Feuersteln
Feuersteln B&C
DHS DHS &
McKesson
ACTIVITY
Further excava-
tion of soil In
and around
drainage ditch
1 soil sample
at base of
excavation
Monitoring Hell
3 Installed
- soil sampled
In borehole
at 10' depth
- groundwater
sampled MH-3
Monitoring wells
1. 2, 3 sampled
4 surface soils
on & off site
ANALYTE.
METHOD
Excavation only;
no samples taken
Chlorinated Pesticides/
PCBs (EPA 608)
Chlorinated Pesticides/
PCBs (EPA 608) Purgeable
Halocarbons (EPA 601)
Purgeable Halocarbons
(EPA 601)
Metals Purgeables
Chlorinated Pesticides/
RESULTS RESULTS ABOVE
ABOVE TTLC ACTION CRITERIA
(Soil) (Groundwater)
N/A N/A
None N/A
None PCBs, TCE
PCE. 1,1-DCE
N/A 1,1-DCE, 1,
2-OCE,
Dkhloro-
propane,
PCE, TCE
ODD. DDE, DDT N/A
ALSO DETECTED
(Above Background)
N/A
None
Soil: PCBs. PCE
Groundwater:
1.1.1-TCA
Freon 113.
1.1.1-TCA. 1-OCA
PCBs, PCE. Toluene.
                      PCBs (EPA 608)  Serai -
                      volatlles (EPA  625)
                      Total  Hydrocarbons
Ethylbenzene, Xylenes
                                                                                                     o
                                                                                                    £2

-------
                 TABLE 5-1 (Continued)
SUHHARY OF SAMPLING ACTIVITIES TO DATE AT THE LB&D SITE
            (August 1981 through July 1988)
                                                                      Page  3 of  6
DATE
SAMPLED
3-85
3-85
4-85
4-85
5-85
6-85
6-85
CLIENT
LB&O
LB&D
LB&D
LB&D
DHS
LB&D
LB&D
DHS
LB&O
SAMPLED OR
PERFORMED
BY
Feuersteln
Conservtech
Geotechnlcal
Cons.
Reed
DHS
Reed
Reed

ANALYZED BY
N/A
Associated
Associates
Labs
B&C
DHS
B&C
N/A
DHS
B&C
ACTIVITY
Excavation of
soil at 6
locations around
5 soils at base
of excavation
Monitoring
wells 4 & 5
Installed and
sampled
Monitoring wells
1 & 5 sampled
18 soil samples
taken at base of
excavation
Splits sent to
different labs
Excavation of soil
In Area 3
15 soil samples
taken around the
site, splits
ANALYTE ,
METHOD
Excavation only;
no samples taken
Metals
Purgeables (EPA-624)
Chlorinated Pesticides/
PCBs (EPA 608)
Purgeable Halocarbons
(EPA 601)
Chlorinated Pesticides/
PCBs (EPA 608) Semi-
volatiles (EPA 625)
Purgeables (EPA 624)
Pb
PCBs
N/A
Metals
Chlorinated Pesticides/
PCBs (EPA 608)
RESULTS
ABOVE TTLC
(Soil)
N/A
PCBs
N/A
N/A
PCBs
N/A
Cd. Pb. PCBs.
DDE
RESULTS ABOVE
ACTION CRITERIA ALSO DETECTED
(Groundwater) (Above Background)
N/A N/A
N/A ODD, DDE. Pb. TCE. PCE
1.2-DCE. None
1.2-DCA. PCE.
TCE
None . Freon 113
N/A Pb
N/A N/A
N/A
DleldHn,
    sent  to
    different  labs
Organophosphorus
Pesticides (EPA 614)
dtsulfoton, methyl
parathlon. ethlon.
azlnphos-methyl
o

-------
                                                                   TABLE 5-1  (Continued)
                                                  SUMMARY OF SAMPLING ACTIVITIES TO DATE AT THE LB&D SITE
                                                              (August 1981 through July 1988)
                                                                                                                                 Page 4 of 6
 DATE
SAMPLED      CLIENT
             SAMPLED OR
             PERFORMED
                BY
               ANALYZED BY
                  ACTIVITY
                      ANALYTE.
                      METHOD
                              RESULTS
                             ABOVE TTLC
                               (Soil)
              RESULTS ABOVE
             ACTION CRITERIA
              (Groundwater)
                    ALSO DETECTED
                  (Above Background)
 6-85
 7-85
 6-86
DHS
LB&D
DHS
LB&D
DHS
Reed
DHS
Reed
DHS
B&C
DHS
TMA (EAL)
10-86
DHS
CH2M Hill
CH2M Hill
 8-87        DHS
11-87
            CH2M Hill
              TRC
32 soil samples
from area near
processing
facility;
Splits sent to
different labs

1 soil sample
east of main
building

Monitoring wells
6 & 7 Installed
and samples
taken from
monitoring wells
1, 2. 3. 4. 6.
and 7
Monitoring
wells 4 and
sampled
               Soil-gas and
               groundwater
               study offsite
Chlorinated Pesticides/
PCBs (EPA 608)
Extractables (EPA 625)
Organophosphorus pesti-
cides (EPA 614)
VGA's (EPA 5020-GC/MS)

Metals
PCBs
Purgeable Halocarbons
(EPA 601)
PCBs
PCBs
N/A
Metals
Purgeables (EPA 624)
Chlorinated Pesticides/
PCBs
N/A
                   Volatile organic
                   compounds (TRC,
                   November 1987
                               N/A
    N/A
    N/A
1.2-Dichloro-
propane.
chlorform. TCE.
vinyl chloride.
1.1.1-TCA.
1.1-OCE.
1,2-DCE. PCE,
1,2-DCA,
PCE. 1,2-DCA

Ba
Benzene, vinyl
chloride.
1.1-DCE 1,2-DCE
1,2-Dlchloro-
propane. TCE.
1,1,2,2-PCA
chlordane.
PCBs

  N/A
                                                                                                                                        Parathion
   None
Chloroethane,
1,1-DCA.
Bromodi-
chloromethane
                                                                                                                                        Toxaphene.
                                                                                                                                        phthalates
                                 Off site plume;
                                 TCE. TCA, Freon 113,
                                 Vinyl chloride
                                                                                                                                                            O
                                                                                                                                                            .-"-^

-------
Late B7
Early
  88
Early
  88
                                                                   TABLE 5-1 (Continued)
                                                  SUMMARY OF SAMPLING ACTIVITIES TO DATE  AT THE LB&D SITE
                                                              (August 1981 through July 1988)
                                                                                                                                 Page 5 of 6
DATE
SAMPLED
Mid-87
CLIENT
DHS
SAMPLED OR
PERFORMED
BY
Canonte
ANALYZED BY
Canonie
& Acurex
ACTIVITY
Soil sampled In
Perimeter &
ANALYTE.
METHOD
Metals
VOCs (EPA 624)
RESULTS
ABOVE TTLC
(Soil)
Cd. Cr. Pb.
RESULTS ABOVE
ACTION CRITERIA
(Groundwater)
N/A
ALSO DETECTED
(Above Background)
None
 6-88
DHS
DHS
EPA
EPA
Emergency
Response
Division
EPA
Canonie
IT
E&E
EPA/E&E
  N/A
Curtis &
Tomklns
Curtis &
Tomkins
EBASCO
CLP
                                                      "Hot  Spot"  areas
                                                      In  northern
                                                      part  of  site
Excavation
of soil
Drum removal
etc.

Post excava-
tion soil
sampling
Incinerator
ash from barrel
on site sampled;
more facility
cleanup etc.
CHIP and SEAL
Installed on
drum storage area

Municipal Hell
sampling (RI/FS)
                                                           Semi-VOCs (EPA 625)
                                                           Organochlorlne Pestl-
                                                           cldes/PCBs (EPA 614)
Excavation only;
no samples taken
Ml. PCBs. ODD.
DDT. Xylenes.
Benzene. Ethy-
benzene. Toluene

    N/A
Metals. Semi-volatile      PCBs (some
Organlcs (EPA 3270)        samples)
Organochlorlne  •
Pestlcldes/PCBs (EPA 8080)
Volatile* (EPA 8240)

Metals                          Pb
Dloxlns and Furans
(EPA 8280)
    N/A
                      N/A
                      N/A
Semi-Volatile organlcs
(CLP RAS)
Pestlclde/PCBs (CLP RAS)
Data not
received yet
Data not
received yet
   N/A
                    None
                  High Cr. N1. Zn
                  Low concentrations
                  of heptachloro-
                  dlbenzo-p-dloxln.
                  octachlorodlbenzo-
                  p-dloxln, octachloro-
                  dlbenzo furan
Data not received yet
                                                                                                                                                           CJ

-------
                                                                   TABLE 5-1  (Continued)
                                                  SUMMARY OF SAMPLING ACTIVITIES TO DATE  AT THE LB&D SITE
                                                              (August 1981  through July 1988)
                                                                                    Page 6 of 6
DATE
-AMPLEO
7-88
CLIENT
EPA
SAMPLED OR
PERFORMED
BY
EBASCO
ANALYZED BY
Hlttman-
Ebasco
ACTIVITY
Groundwater
characterization
ANALYTE,
METHOD
Metals
Semi-volatile organic*
RESULTS
ABOVE TTLC
(Soil)
N/A
RESULTS ABOVE
ACTION CRITERIA
(Groundwater)
Vinyl chloride
1.1-DCA;
ALSO DETECTED
(Above Background)
Acetone 1.1-DCA;
trans- 1,2-DCE;
                                                     sampling for
                                                     treatablllty
                                                     study (RI/FS)
               (EPA 601/602. 624)
              Organochlorlne pesticides/
              PCBs (EPA 605/608)
              Phenols (EPA 606)
              Phthalate esters (EPA 604)
              Chemical & Physical
               Properties (EPA)
              01oxIns (EPA 8280)
               modified)
1.2-DCP; TCE;
Benzene; PCE*
1.1,1-TCA; Toluene;
Chlorobenzene;
Ethyl benzene*
                                                                                                   Data not yet
                                                                                                   received (dloxlns)
ABBREVIATIONS:

B&C - Brown and Caldwell
Canonic - Canonle Environmental
CLP - Contract Laboratory Program
DHS - California Department of Health  Services
E&E - Ecology & Environment
EBASCO - Ebasco Services. Incorporated
EPA - Environmental Protection Agency
Feuerstetn - Feuersteln Associates  Consulting Engineers
N/A - Not Applicable
IT - IT Corporation
LB&D - Lorentz Barrel ft Drum
McKesson - McKesson Environmental
RAS - Routine Analytical Services
Reed - Reed Corporation
RI/FS - Remedial Investigation/Feasibility Study
TMA - Thermo Analystlcal, Inc.
TRC - Tracer Research Corporation
* - Results preliminary awaiting validation (Ebasco 1988)
                                                                                                                                                             o
                                                                                                                                                             o
                                                                                                                                                             CO

-------
     TABLE 5-2
GROUNOWATER ANALYSES
Date
Sampled
11-23-83
01-20-84
03-02-84
04-04-85
04-29-85
07-86
10-02-86
06-30-88
07-16-88
Client Sampled By Analyzed By
LB&D Feuerstein ft Associates Brown ft Cal dwell Laboratory
LB&D Feuerstein ft Associates Brown ft Cal dwell laboratory
LB&D Feuerstein ft Associates Brown ft Cal dwell Laboratory
LB&D Geotechnlcal Consultants, Inc. Associated Laboratories
LBKD Reed Corporation Brown ft Cal dwell Laboratory
LB&D Reed Corporation • Thermo Analytical, Inc./
Environmental Research Group
OHS CH2M Hill, Inc. CH2M Hill Environmental
Laboratory
EPA Ebasco Services, Inc. Contract Laboratory Program
EPA Ebasco Services, Inc. Hittman-Ebasco
Analytical
Method
Unknown
EPA 624
EPA 625
EPA 601
EPA 608
EPA 601
EPA 601
EPA 624
EPA 608
EPA 624
EPA 601
Unknown
EPA 624
EPA 608
EPA 625
Unknown
CLP RAS
CLP RAS
EPA 608
EPA 604
EPA 606
EPA 601 /
602 & 624
EPA 625
EPA 200
Series
EPA
Various
Analyte/Method
Metals. CN. Phenols
Purgeables/Gas Chromatography-
Mass Spectrometry (GC-MS)
Extractables/CG-MS
Purgeable Halocarbons/GC
Chlorinated Pesticides and PCBs/GC
Purgeable Halocarbons/GC
Purgeables/GC
Semi volatile Organics/GC-MS
Chlorinated Pesticides and PCBs/GC
Purgeables
Purgeable Halocarbons/GC
Metals
Purgeables/GC-MS
Organochlorine Pesticides and
PCBs/GC
Semivolatiles Organics/GC-MS
Minerals
Semi volatile organics/GC-MS
Chlorinated Pesticides and
PCBs/GC
Pesticides/PCB
Phenol s
Ph thai ate Esters
Volatile organics
Semivolatiles
Metals
Chemical ft Physical
Properties
                                                                                        o

-------
                                                    000(631
5.3  NATURE AND EXTENT OF CONTAMINATION IN THE SHALLOW AQUIFER

The shallow  groundwater beneath both  onsite  and offsite  areas
is  contaminated   with  volatile   organic  compounds   (VOCs),
pesticides, polychlorinated biphenyls (PCBs),  and some metals.

Table 5-3  summarizes  results  of groundwater  analyses  performed
to date by various  consultants .to  LB&D.  Table 5-4  provides the
maximum    contamination    levels    detected    for    selected
contaminants.   No  remedial  actions  to  date  have  addressed
groundwater  contamination.  Therefore,  all of  these data  must
be  considered  in  assessing  site  contamination.  Results  from
Tracer  Research  Corporation  (TRC)  1987  study  are  shown  in
Table 5-5.   The  Data  Quality   Level   (DQL)  for  the  previous
studies was   taken  into consideration by  the  Regional  Board
(1981-1986)  and  DHS  (1986-1987)  in  their  decisions  as  lead
agencies  at  LB&D.   For this  ROD,  EPA  has  determined that  the
DQL is Level 3, appropriate for  preliminary engineering design.

The   1987 TRC  study  showed   a   complex  pattern   of   water
contamination   (Figure  5-3).    In   addition,   the   groundwater
samples   analyzed  from well  MW-6  indicate  that  contaminants
other than VOCs have migrated offsite.  The potential migration
of PCBs  is of particular concern.   PCBs do not  migrate readily
in groundwater, but they are  soluble in organic  solvents  (e.g.,
1,1,1-TCA  and  TCE)  and can  be transported   along  with  those
solvents.  The lack  of information  about the  transport  and
actual  extent of PCB  contamination is one of  the major  data
gaps  that needs  to  be filled by  collection  and  laboratory
analysis  of   samples  from  groundwater  monitoring wells  before
design  of the treatment facility  can  be  implemented.   Samples
collected  for treatability studies in  summer  1988 did  not have
measurable levels of PCBs,  but further work needs to  be done to
confirm this.

Other data gaps which  will be addressed during the  RI/FS  before
further  remedial  action  evaluation  and  design  are  completed
include determination of:

    o    the types of contaminants  comprising  the plume(s);

    o    the  vertical  and  horizontal extent  and variability of
         contamination;

    o    the  extent of  actual or potential migration pathways,
         such as potential  conduits between aquifers; and

    o    the  potential  for  vertical  migration between aquifers,
         via either natural or man-made discontinuities.
                            II-5-13

-------
                                                                       TABLE 5-3
                                                            SUMMARY OF MONITORING WELL DATA
                                      (units for analysis are specified for each  category of analyte in Column 1.)

Analyte
METALS (ppb)
Arsenic
Barium
Chromium (total)
Cobalt
Molybdenum
Nickel
Vanadium
Zinc
VOLATILE ORGAN ICS (ppb)
Benzene
Chloroethane
Chloroform
1,1-Dichloroethane
1,2-Dichloroethane
1,1-Dlchloroethene
Trans- 1,2-Dichloroethene
Methylene Chloride
1,2-Dlchloropropane
Tetrachloroethene
1,1,2,2-Tetrachloroethane
1,1.1-Tri Chloroethane
Trlchloroethene
Vinyl Chloride
Freon 113
Carbon Disulfide
Bromodlchtoromethane
Olchlorotrif luoroethane
C6H12 Cyclic Hydrocarbon
SEMI -VOLATILE ORGANICS (ppb)
Di-n-Butyl Phthalate (f)
Butylbenzyl Phthalate (f)
Bls(2-Ethyl HexyDPhthalate (f)
Oi-n-Octyl Phthalate (f)
MU-1
B ft C (b)
11/83 3/84 4/85

3.0

0.3


43.0

—

1.0
...
...
10.0 51.0
...
12.0 9.0
9.0 10.0
—
4.0 3.0
5.0 2.0
—
30.0 33.0
59.0 54.0
—
30.0 26.0 4.0
...
—
50.0
5.0






TMA (c)
7/86











—
11.0
11.0
—
9.0
8.4
—
1.7
(e)
3.0(e)
34.0
61.0
—


—







MW-2
B 1 C (b)
11/83 3/84

4.0

0.1


33.0

...

...
—
2.0
— ...
—
— —
— —
—
— —
... ...
—
2.0 -•-
— —
—
7.0 6.0
3.0
—
6.0







TMA (c)
7/86











..j
1.4
—
—
—
—
—
—
(e)
— (e)
0.36
—
—


—







MU-3
B ft C (b)
1/84 3/84













46.0

29.0 47.0
105.0

45.0
17.0 38.0

26.0 34.0
640.0 1000.0

41.0










TMA (c)
7/86











—
29.0
40.0
18.0
22.0
91.0
—
60.0
(e)
65.0(e)
60.0
950.0
62.0


1.5







MtH
Associated
4/85
.










—
...
—
—
—
240.0
—
...
...
—
—
510.0
—


...





5100.0


TMA (c)
7/86











24.0
...
85.0
58.0
160.0
750.0
—
170.0
(e)
140. 0(e)
220.0
1100.0
1100.0


—







MU-4A (a)
CH2M Hill
10/86

—
160.0
—
60.0
—
130.0
30.0
20.0

26.0 (d)
—
...
38.0 (d)
—
90.0
430.0
26.0 (d)
89.0
...
91.0
75.0
1766.0
455.0

—
...



31.0
...
73.0
...
MU-4B (a)
CH2M Hill
10/86

—
160.0
—
50.0
20.0
120.0
30.0
20.0

26.0 (d)
—
...
41.0 (d)
—
97.0
488.0
—
92.0
...
106.0
83.0
2108.0
553.0

...
—



24.0
17.0
680.0
60.0
(a)       Splits of sample collected from MU-4 (10-86)
(b)       Brown ft CaIdwell
(c)       Thermo Analytical,  Inc.
(d)       Indicates an Estimated Trace Value
(e)       Co-Eluting Compounds
(f.)       Phthalates are most probably laboratory contaminants
          Not Detected
(blank)   Not Analyzed
C.3
>-•

-------
                                                    TABLE 5-3 (continued)
                                               SUMMARY OF MOMI TORIMG WELL DATA
                          (unit* for analysis are specified for each category of analyte .In Co I inn 1.)

Analyte
HETALS (ppb)
Arsenic
Barium
ChromiuM (total)
Cobalt
Molybdenum
Nickel
Vanadium
Zinc
VOLATILE ORGAN ICS (ppb)
Benzene
Chloroethane
Chloroform
1.1-Oichloroethane
1,2-Oichloroethane
1 , 1 - D i ch 1 oroethene
Trans-1,2-Dichloroethene
'Methylene Chloride
1 ,2-Dichloropropane
Tetrachloroethene
1,1,2,2-Tetrachloroethane
1,1.1-Trichloroethane
Trichloroethene
Vinyl Chloride
Freon 113
Carbon Disulfide
Bromodichloromethane
D i ch 1 orot r i f I uoroethane
C6H12 Cyclic Hydrocarbon
SEMI -VOLATILE ORGAN ICS (ppb)
Di-n-Butyl Phthalate (f)
Butylbenzyl Phthalate (f)
Bis(2-Ethyl HexyDPhthalate (f)
Dl-n-Octyl Phthalate (f)
MW-
Associated
4/85











—
—
—
4.8
...
—
...
—
23.0
—

45.0
—


—





—

5
B t C (b)
4/B5
























...









MV
TMA (C)
7/86











—
9.9
35.0
8.5
49.0
120.0
...
23.0
(e)
60.0(e)
32.0
770.0
510.0


—







1-6
CH2M Hill
10/86

...
110.0
10.0
20.0
20.0
60.0
30.0
...

—
—
—
18.0 (d)
—
33.0
61.0
...
—
...
22.0 (d)
14.0 (d)
413.0
60.0

—
—



113.0
32.0
39.0
...
MU-7
TMA (c)
7/86











—
—
1.0
270.0
1.7
—
...
—
(e)
— (e)
5.2
0.5
—


—







MU-16
HITTMAN EBASCO
7/88

—
141
1.9
13

72
25


8
—
—
14
...
27
52
...
18
18
—
11
300
66

—
—



...
...
...
...
MU-16 (field duplicate)
HITTMAN EBASCO
7/88

...
128
2.4
15

71
32


8
—
0.5
16
20
29
56
...
19
19
—
12
311
72

—
...



...
—
...
...
MU-20
HITTMAN EBASCO
7/88

...
99
2.3
11

...
25-


3
—
—
3
—
86
14
...
1
...
—
34
2
8

—
—



...
...
...
...
(a)
(b)
(c)
(d)
(e)
(f )

(blank)
Splits of sample collected from MU-4 (10-86)
Brown I Ca I dwell
Thermo Analytical, Inc.
Indicates an Estimated Trace Value
Co-Eluting Compounds
Phthalates are most probably laboratory contaminants
    Detected
                                                                                                                                                         o
                                                                                                                                                         o
CO

-------
                                                                 TABLE 5-3 (continued)
                                                            SUMMARY OF MONITORING WEIL DATA
                                      (units for analysis are specified for each category of anatyte In Column 1.)

Analyte
EXTRACTABLES (ppb)
Isophorone
D I methyl ethoxyethanol
>C9 Aldehyde
Docosanoic Acid
Hexadecanoic Acid
C4 Benzole Acid
>C10 Fatty Acid
MINERALS (ppm)
Calcium
Magnesium
Potassium
Sodium
Bicarbonate
Carbonate
Chloride
Nitrate
Phosphate
Sulfate
Silica
CaC03
PESTICIDES (ppb)
Chlordane
Toxaphene
POLYCHLORINATED
BYPNENVLS (ppb)
PCB 1221
PCB 1242
PCB 1254
PCB 1260
MU-1
• ft C (b)
11/83 3/84 4/85

2.0
2.0
2.0
2.0
4.0
2.0















...
...







TMA (c)
7/86






























MU-2
B ft C (b)
11/83 3/84







1.0














...
...







TMA (C)
7/86






























MU-3
B & C (b)
1/84 3/84






















...
...





0.36

TMA (c)
7/86






























MV-<
Associated
4/85












,









...
...







TMA (c)
7/86














'















NW-4A (a)
CH2M Hill
10/86









97.0
140.0
0.92
200.0
1293.0
—
79.0


83.8
24.0
24.0

0.2
1.0


2.0
1.0
0.4

MU-4B (a)
CH2M Hill
10/86









96.0
140.0
1.0
210.0
1220.0
—
78.0


82.0
26.0
26.0

0.1
2.0


3.0
— .
0.4

(a)       Splits of  sample collected from MU-4 (10-86)
(b)       Brown ft CaIdwell
(c)       Thermo Analytical,  Inc.
(d)       Indicates  an Estimated Trace Value
(e)       Co-Elutlng Compounds
(f)       Phthalates are most probably laboratory contaminants
          Not Detected
(blank)   Not Analyzed
CJ

-------
                                                              TABLE 5-3 (continued)
                                                         SUMMARY OF MONITORING WELL DATA
                                   (units for analysis ere specified for each category of anatyte .in Colum 1.)

Analyte
EXTRACTABLES (ppb)
Isophorone
Dlmethylethoxyethanol
>C9 Aldehyde
Docosanoic Acid.
Hexadecanoic Acid
C4 Benzole Acid
>C10 Fatty Acid
MINERALS (ppm)
Calcium
Magnesium
Potassium
Sodium
Bicarbonate
Carbonate
Chloride
Nitrate
Phosphate
Sulfate
Silica
CaC03
PESTICIDES (ppb)
.Chlordane
Toxaphene
POL YCHLORI HATED
BYPHENYLS (ppb)
PCB 1221
PCB 1242
PCB 1254
PCB 1260
MW-
Associated
4/85






















...
...






5
B ft C (b)
4/85






























MV
TMA (C)
7/86






























1-6
CH2M Hill
10/86









73.0
110.0
1.12
290.0
1250.0
—
55.0


95.0
24.0
24.0

—
...


4.0
...
0.2

MW-7
TMA (c)
7/86






























MU-16
HITTMAN EBASCO
7/88
f








70
123
...
297





83

613

—
...


...
—
—
—
MU-16 (field duplicate)
HITTMAN EBASCO
7/88









67
118
...
285

••



73

601

—
...


...
...
...
...
MU-20
HITTMAN EBASCO
7/88









123
15
1.8
659





253

870

—
...


...
—
...
...
(a)       Splits of sample collected from MU-4  (10-86)
(b)       Brown ft Caldwell
(c)       Thermo Analytical.  Inc.
(d)       Indicates an Estimated Trace Value
(e)       Co-Eluting Compounds
(f)       Phthalates are most probably laboratory contaminants
          Not Detected
(blank)   Not Analyzed
                                                                                                                                                                o

-------
                                        TABLE 5-«
                                 GROUNDWATER CONTAMINATION LEVELS
                        DETECTED AT LORENTZ BARREL AND DRUM SITE*
                                                                     0000231
          Analyte
   DHS Action
    Criteria
   References'-*
     (ppb)
  Highitt
   Level
 Dtticttd*
   (PPb)
                                                                            Date
 HHALS

 Arsenic
 Barium
 Chromium (toUl)
 Cobilt
 Molybdenum
 Nickel
 Vanadium
 21 nc

 VOLATILE ORGANIC?

 B«niint
 Chloroethane
 Chloroform
 1.1-Oichloroethane
 1,2-Oichloroethane
 1.1-Oiehloroethene
 trans-l,2-Dichloroethene .
 Dichlorome thane
 1.2-01chloropropane
 Tttrtchlorotthint
 1,1,2.2-tetrachloroethane
 1,1,1-Trichloroethane
 Trichloroethene
 Vinyl Chloride
 Frton 113

 PESTICIDES

 Chlordane
 Toiaphene

 POLVCHLORINATED BIPHENYLS

 PCBi
    0.002 (2)
    10.00 (3)
    51.00 (3)
  150.00 (1)

7,480 (3)



    0.70 (1.4)

    0.50 (3)
4>000.00 (3)
    0.51 (3)
     LOQ (4)
   70.00 (1)
   10.00 (4)
   10.00 (4)
    0.87 (3)
    0.17 (3)
  200.00 (4)
    1.80 (3)
    0.015 (3)
    O.OS (4)
   35.00 (2)
                                O.OOB  (3)
     4.00*
   160.00*
    10.00
    60.00
    20.00
   130.00
    30.00
    20.00
   26.00*
   24.00
   29.00*
   85.00
  270.00*
  160.00*
  750.00*
   26.00*
  170.00*
  140.00*e
  106.00*
  220.00*
2.108.00*
1.100.00*
   41.00
    0.20*
    2.00
                             6.40*
 11/83
 10/86
 10/86
 10/86
 10/86
 10/86
 10/86
 10/86
10/86
07/86
07/86
07/86
07/86
07/86
07/86
10/86
07/86
07/86
10/86
07/86
10/86
07/86
03/84
10/86
10/86
                                                                            10/86
a    Concentrations are shown in parts  per billion (ppb) unless otherwise indicated.

b    DHS Action Criteria are as defined in a March 17, 1986. memorandum from David J.
     Leu, Ph.D., DHS'I Chief of Alternative Technology and Policy Development Section,
     Tonic Substances Control Division,  to all Section Chiefs in DHS's  Tosic Substance
     Control Division.  Reference numbers are shown in parentheses and  indicate  the
     source of each criterion.   These sources are listed in the Reference section
     following this table.

c    140.00 ppb is the sum  of PCE and 1,1.2.2-tetrachloroethane concentrations.

NOTES:  DHS - Department of Health Services
         LOQ • Limit of Quantification
         •   • eiceeds DHS  Action Criterion

1.   Draft Health Advisories.  Office of Drinking Water.
     U.S. Environmental Protection Agency.  Washington, D.C.
     September 30. 1985

2.   Ambient Water Quality  Criteria Documents.
     Office of Water Regulations and Standards.
     U.S. Environmental Protection Agency, Washington, D.C.
     October 1980.  (Values adjusted for drinking water.)

3.   Draft Health Effects Assessment Documents
     Office of Emergency and Remedial Response
     Office of Environmental Criteria and Assessment
     U.S. Environmental Protection Agency
     Cincinnati, Ohio.  September 19B4.

4.   Sanitary Engineering Branch California Department o< Health Services
     Berkeley, California.   1985

+    CH2H Hill.  February 1987.   Preliminary Site Allotment Report.  Lorenti  Barrel I
     Drum (IBID).   Prepared for California Department  »' Health Services  (DHS).
                                        II-5-18

-------
                                                           TABLE 5-5

                                                  ANALYTICAL RESULTS OF GROUNDUATER
                  (Tracer Research Corporation, Groundwater Investigation at Lorentz Barrel ft Drua, Novenfcer 1987)
SAMPLE
V2
U3
U4
US
W6
U7
US
W9
U10
U11
U12
U13
UU
U15
U16
U18
W19
U20
DEPTH
(feet)
27
27
20
20
26
26
20
26
26
26
26
26
25
26
24
25
26
26
DATE
11/18
11/18
11/19
11/19
11/19
11/19
11/19
11/19
11/19
11/19
11/19
11/19
11/20
11/20
11/30
11/30
11/30
11/30
FREON
113
22
3
<0.3
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
0.2
<0.02
<0.03
TRICHLOROETHANE
90
5
28
60
53
7
68
U
<0.008
4
64
60
20
69
62
33
<0.009
0.03
TRICHLOROETHENE
2600
54
30
<0.02
3
<0.02
1
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
<0.02
0.8
<0.02
<0.02
<0.02
PERCHLOROETHENE
11
0.2
0.1
<0.004
<0.004
<0.004
<0.004
<0.004
<0.004
<0.004
<0.004
<0.004
<0.004
<0.004
0.1
<0.05

-------
                                       TCA
                                    (Approximate)
                          VINYL CHLORIDE
                              (1.0 ppt>>
                                      TCE
                                    (5.0 PPt>»
                     Spartan
                      Stadium
                                                San Jose
                                              Muni BaiaDall
                                                Stadium
       GROUND* ATE R FLOW
                            tORENTZ BARREL
                              4 DRUM  SITE
o
b
500
      SCALE IN FEET
 1000
=d
FIGURE 5-3

APPROXIMATE EXTENT OF
GROUNDWATER CONTAMINATION

LORENTZ BARREL & DRUM

-------
                                              0000231
5.4  HUMAN AND ENVIRONMENTAL EXPOSURE  PATHWAYS

Potential  exposure  pathways  for  VOCs  are  ingestion,  dermal
contact,   and   inhalation   of   vapors   from   contaminated
groundwater,  as well as accidental dermal exposure or ingestion
of Coyote  Creek water.  Potential exposure pathways for metals
are  ingestion  of  contaminated  groundwater  and  dermal  contact
with   Coyote   Creek   sediments   and   exposed   surface  soils.
Potential  exposure  pathways  for PCBs  consist of  ingestion and
dermal contact from contaminated groundwater and soil.
                            II-5-21

-------
                                                  0000231
6.0  SUMMARY OF SITE RISKS
A  screening-level  health  risk  assessment  was  conducted  to
evaluate  potential health  risks  related to  remediation  of the
LB&D  site by  groundwater treatment  alternatives described  in
Engineering  Evaluation and  Cost  Analysis  (EE/CA)  (Ebasco, May
1988).   Since  the groundwater  treatment  system is  designed  to
remediate  groundwater  contamination  only,  the  scope of  this
assessment  focused on  drinking water-related  health  risks  as
the   primary  exposure   route..  However,   since  one  of* the
treatment  alternatives   also -  involved  air  emissions  of  the
extracted  contaminants,  the additional  health  risks associated
with  these emissions were  also evaluated.   Because this  is  a
screening-level   assessment,   adverse   health   impacts   were
quantified only  in terms of  increased risk of  cancer.   A much
more  comprehensive analysis of health risks at  the LB&D  site,
including  all  relevant exposure  pathways  and an  evaluation  of
noncarcinogenic  health risks, will  be included in the Remedial
Investigation/Feasibility Study (RI/FS) risk assessment.

6.1   CONTAMINANTS OF CONCERN

Contaminants included  in the assessment  (i.e.,  contaminants  of
concern)  consisted of  all groundwater  contaminants identified
at   or   near  the  LB&D  site  for  which   the  United  States
Environmental  Protection  Agency  (EPA)  has developed  a  cancer
potency  estimate.  All  such contaminants  were  assumed  to  be
carcinogens  and  were  included  in  the  analysis  regardless  of
frequency   of   detection   or    magnitude   of   concentration.
Exceptions  to  this  rule included  phthalates,  dichloromethane,
cadmium,  and  chromium.   Analytical  data   for  phthalates  and
dichloromethane  contaminants strongly  suggested that detection
of  these  contaminants  was  due  to   laboratory  contamination,
therefore   these   contaminants  were   not  included  in   the
analysis.  Cadmium and chromium were  also  excluded  since  these
compounds  are  not considered by  EPA  to  be  carcinogenic via the
oral  route of exposure.   A complete  list  of  the contaminants
included  in the  analysis,  along with the  maximum  and average
concentrations observed  at  the  LB&D site,  is provided  in  Table
6-1.

6.2   EXPOSURE ASSESSMENT

The  potential  exposure  pathways  associated  with contamination
.of  the  shallow  groundwater are  illustrated  in  Figure  6-1.
Figure  6-1  includes  all pathways  of  potential  significance.
However,  since this  was a screening-level  assessment,  only the
most   significant   exposure   pathways   were   quantitatively
evaluated.  These pathways were considered  to be drinking  water
and   inhalation  (air  stripper  emissions   only).   Quantitative
evaluation of  all other pathways  will be included in the  RI/FS
risk  assessment.
                             II-6-1

-------
                               TABLE 6-1
           CONTAMINANTS OF CONCERN IN THE SHALLOW GROUNDWATER
                        AT LORENTZ BARREL & DRUM
Estimated
Average
Maximum Concentration
Concentrations In The Plume
Found (ug/1)1 (ug/1)
1,1 Dlchloroethene
1,1,2,2 Tetrachloroethane
1,2 DUhloroethane
Arsenic
Benzene
Chlordane
Chloroform
PCBs (total)
Tetrachloroethene
Toxaphene
Trlchloroethene
Vinyl chloride
160
106
270
4.0
26
0.2
29
6.4
140
2.0
2,108
1,100
26
28
16
0.2
6.2
0.01
8.0
0.31
17
0.10
651
155
Expected
NPDES
Discharge
Limits
(ug/1)2
5
5
1
20
0.5
0.014
5
0.065
5
0.24
5
2
Source:  CH2M H111, February 1987, Preliminary Site Assessment Report,
                                           Lorentz Barrel & Drum

Source:  California Regional Water Quality Control Board, San Francisco
         Bay Region, Basin Plan Review, November 1986
                                 II-6-2

-------
CONTAMINANT
   SOURCE
CONTAMINANT
  RELEASE
 MECHANISM
CONTAMINANT
  TRANSFER
   MEDIA
POTENTIAL
EXPOSURE
  MEDIA
POTENTIAL
EXPOSURE
 ROUTES
POTENTIAL
EXPOSURE
  POINTS
                                                         Discharge In
                                                         Coyote Creek
   Onsite
    Soil
     T
                      Leaching
    Surface
    Runoff
                     Shallow
                     Ground
                     Water
 •Sumps Leakage
 -Spillage
 •Drum Leakage
 •Waste Dumping
                                      Drinking Water
                                         Supply
                                      Contamination
                                                                                   Dermal
                                                                Accidental
                                                                Ingestion
                                             Accumulated
                                              Ingestion
                                               (Fish)
                                               Dermal
                                              Ingestion
                                                                                  Inhalation
                                                                    Coyote
                                                                     Creek
                                            Shower Stalls
                                            Water Faucets
                                             Bath Tubs
                                                                                  FIGURE  6-1
                                                                                  CONCEPTUAL EXPOSURE MODEL
                                                                                  SHALLOW GROUNDWATER
                                                                                  CONTAMINATION
                                                                                  LORENTZ BARREL (  DRUM

-------
                                                0000231
Although   the   shallow  groundwater  is   not   currently  being
utilized as a drinking water source,  the  drinking  water pathway
was  considered  important based on the concern  that  the shallow
groundwater  may  have  a hydraulic  connection  with  the  deep
aquifer.   The  deep aquifer is currently  an  important  source of
drinking water in the  region.  The significance  of this concern
will be clarified  as  a result  of extensive RI  studies currently
being performed.

6.3  RISK CHARACTERIZATION

Daily drinking  water  doses of carcinogens/  EPA cancer  potency
estimates/  and  lifetime cancer risk  estimates  for each  of  the
groundwater carcinogens  are listed in Table 6-2.   Human daily
contaminant doses  associated with  the consumption  of two liters
per  day  of untreated  shallow  LB&D groundwater  for a  lifetime
were  calculated using the maximum  groundwater  concentrations
reported  for  each of  the  carcinogens.   An  average  adult human
body  weight  of  70   kg  was also  assumed  in   making  the  dose
calculation.    Lifetime   cancer   risk   was    calculated   by
multiplying  the daily dose of  ea.ch carcinogen  by the  cancer
potency estimate.  The total cancer  risk due to consumption of
untreated  drinking water   was  calculated  to  be  8.1  x  10~2,
with most  of the cancer risk attributable to vinyl chloride.

One  of  the groundwater  treatment  alternatives  (Alternative C)
discussed  in  the EE/CA  (Ebasco/  May  1988)   utilizes   an  air
stripping  tower to  volatilize  organic  contaminants  from  the
extracted  groundwater.   Use  of  the air   stripper  without  a
hazardous  substance  control  device  for  air  emissions  could
result  in  atmospheric emissions  of  chlorinated  hydrocarbons,
the  significance of which  would  be a function  of  concentration
and  dispersion.  Daily doses of  carcinogens  associated with the
inhalation  of  air  stripper  emissions,  along  with  lifetime
cancer  risk estimates, are listed for  all  volatile carcinogens
in Table 6-3.  Inhalation doses were  estimated  assuming  a daily
inhalation   rate  of   20   mVday,   an   inhalation   absorption
efficiency  of  100 percent, and  a 70 kg  body  weight.   Annual-
average  air concentrations of  the contaminants were  estimated
as  described  in  Section 5.4.3  of  the  EE/CA.   The  calculated
total cancer risk  associated with  the uncontrolled air stripper
emissions  is  2.8 x 10~6.   The  calculated cancer  risk  exceeds
the  allowable  1 x 10~6  value for  uncontrolled sources,  which
is established  by  the Bay  Area Air Quality  Management  District
(BAAQMD).   This  indicates that  BAAQMD  would  require   that  a
control  device  be  installed  to  reduce  the compound  emission
rate.
                             II-6-4

-------
                                            TABLE 6-2

                   CANCER RISK FROM GROUNDWATER INGESTION:  WORST CASE SCENARIO

Maximum Detected
Groundwater
Concentration1
Compound (ug/1)
1.1-Dichloroethene
1 , 1 ,2 ,2-Tetrachl oroethane
1,2-Dichloroethane
Arsenic"
Benzene
Chlordane
Chloroform
PCBs"
Tetrachl oroethene
Toxaphene
T rich! oroethene
Vinyl Chloride
160
106
270
4.0
26
0.2
29
6.4
140
2.0
2108
1100
Estimated Dose*
(mg/kg/day)
4
4
7
1
7
5
8
1
4
5
6
3
.58 x
.00 x
.72 x
.14 x
.43 x
.72 x
.29 x
.83 x
.00 x
.71 x
.03 x
.15 x
10-3
10-3
10-3
10-4
10-4
10~6
lo-4
ID"4
10-3
10-5
10-2
10-2
Cancer Potency
(risk/mg/kg/day)
5
2
9
1
2
1
8
7
5
1
1
2
.80
.00
.10
.5 x
.90
.61
.10
.7 x
.10
.10
.10
.30
x lO'1
x lO'1
x ID'2
10-1
x 10~2
x 10°
x ID'2
10°
x ID'2
x 10°
x ID'2
x 10°
Total Risk -
Estimated Risk
Level
2.
8.
7.
1.
2.
9.
6.
1.
2.
6.
6.
7.
8.
66 x
00 x
02 x
71 x
15 x
21 x
71 x
41 x
04 x
28 x
63 x
24 x
07 x
10-3
10-4
10-4
10-5
10-5
10-6
10-5
10-3
io-«
10-5
io-<
10-2
ID'2"
1   Based on highest levels detected in site monitoring wells.
    Dose calculation assumes 2 liters of water consumed daily and  a 70  kg  body weight consistent
    with standard United States Environmental  Protection Agency  (EPA) risk assessment assumptions.

    These are different from the Engineering Evaluation and  Cost Analysis  (EE/CA)  (Ebasco, May
    1988) Table 5-1 based on recent EPA revisions  to cancer  potency estimates.
                                              I1-6-5

-------
                                               0000231
                          TABLE 6-3
          INHALATION DOSES, CANCER POTENCY ESTIMATES,
           AND LIFETIME  CANCER RISK FOR UNCONTROLLED
                    AIR STRIPPER EMISSIONS
    Compound
Inhalation
   Dose
(mg/kg/day)
Cancer Potency
   Estimate
(risk/mg/kg/day)
Incremental
 Lifetime
  Cancer
  Risk3
Chloroform
1 , 2-Dichloroethane
1 , 1-Dichloroethene
Tetrachloroethene
1,1,2,2-Tetra-

chloroethane

Trichloroethene
Vinyl Chloride
5
1
1
1


1

4
9
.0
.0
.6
.1


.8

.1
.7
Z
z
z
z


z

z
z
10
10
10
10


10

10
10
-7
-6
-6
-7

-6
o
-5
j
-6
8
3
1
1


2

2
2
.10E-02
.50E-02
. 16E+00
.70E-03


.OOE-01

.50E-02
.50E-02
4
3
1
1


3

1
2
.1
.5
.9
.8


.-5

.9
,4
z
z
z
z


z

z
a
io-8
io-8
IO"6
io-9

_ 7
10 7
_7
10 7
io-7
Total Inhalation Risk
                             2.8 z 10
    lifetime cancer  risk=cancer  potency estimate z  inhalation
    dose
                            II-6-6

-------
                                                0000231
7.0  DOCUMENTATION OF SIGNIFICANT CHANGES

There  have  been  no   significant  changes  in  the  alternatives
considered since the  release of the Engineering Evaluation/Cost
Analysis (EE/CA) (Ebasco, May 1988).
                            II-7-1

-------
                                               QQO(BKJ
8.0  DESCRIPTION OF SHALLOW AQUIFER TREATMENT AND DISPOSAL
     ALTERNATIVES

8.1  APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS

Section  121(d)  of  the  Superfund Amendment  and Reauthoriz'ation
Act of  1986  (SARA)  requires the consideration  of  Applicable or
Relevant  and  Appropriate Requirements  (ARARs)  of  environmental
laws,   ordinances,   regulations,   and   statutes   in   remedial
actions.   In  addition,  SARA  requires  consideration  of  other
pertinent   criteria   and   advisories   that   are   not   yet
promulgated.  For  the Lorentz Barrel & Drum (LB&D) site,  ARARs
were used  to  examine  the existing  situation,  possible remedial
actions, and potential impacts.

The  United   States  Environmental  Protection   Agency   (EPA)
"Interim  Guidance  on Compliance with  ARARs"   identifies  three
separate categories of ARARs:

    o    ambient  or  chemical-specific  requirements  that  set
         health  or risk-based  concentration  limits  or  ranges
         for  specific  chemicals (e.g.,  Safe  Drinking  Water Act
         Maximum Contaminant Levels);

    o    performance-, design-,  or  action-specific requirements
         that  regulate  particular  activities   (e.g.,  the  Clean
         Water  Act  Pretreatment   Standards   of  Discharge  to
         Publicly-Owned Treatment Works  (POTW)); and

  •  o    location-specific  requirements  (e.g., POTW  discharge
         requirements).

Table 8-1  identifies  those  Federal,  State  of  California,  and
local regulatory,  advisory,  and action levels applicable to the
groundwater   at   the  LB&D  site.    The   following   presents
guidelines related to discharge of liquid and gaseous effluents:

    o    the  guidelines   on discharge  of  liquid   effluents  to
         surface water  bodies  are  provided  in the Basin  Plan
         prepared  by  the  California  Regional  Water  Quality
         Control   Board   (CRWQCB).    The  LB&D discharges  to
         surface   waters   must   satisfy  National   Pollution
         Discharge   Elimination    System   (NPDES)   discharge
         requirements.   The discharge  of water extracted  from
         the  shallow  aquifer  at the LB&D  site to the  Coyote
         Creek via a storm drain will  require satisfaction of
         NPDES requirements;
                             II-8-1

-------
                                                                                  IMLf 8-1
                                           fEKRAl MB SIAfE at CALIFORNIA REOUUTORT. ADVISORY.  UO «CII(M IEVEIS FOR ARAIVTES  II CROUMnMIER

ARAIYTE
MEIAlt
••••••
Areenlc
••rlui
ChroMluB (tot el)
Cobett
Nolybdenue
Rlckel
Venedlue
line
VOLATILE OMARin
lent en*
Chloroethen*
CMorofone
1.1-Dlchloroethene
1.2-Dlchloro«thene
1.1-Dlchleroelhcnt
Trene-1.2-Dlchloro*thene
1,2-Dlchloropropene
Tctrechloroethene
IICNEft UVU
DETECTED IN
CROUNDUATER «t
INE IUO till
ppb (•)

4.0
160.0
10.0
M.O
20.0
1)0.0
30.0
20.0

26.0 CD
. 24.0
29.0
M.O
270.0
160.0
750.0
ITOiO
UO.O

NICNCST LEVEL
DETECTED
OFFSUE
ppb (b)










.







11.0

EPA NAXIMUN
CMTAMIIMf
IEVEI (e)
P»*

to
1000
SO






5

100

s
1




EPA NAIIMJN
CONJTAIIIRANI
LEVEL GOAIS 

SO
»00
120






0



0
7
70
6
0
c* on
ORIWIN
WIEI ACIION
IEVEIS (()
B*










0.70


20

6.0


«.o

WOES
OISCMICE
limit 
B*

20

11


7.1(«)

n










MTU tMCf •
raw MM* it
OltCMIGE
DEOUIKMEIIIS 
W*

1000
5000
1000


2600

2600


10. «|l
10. (i)
10. (1)
10. (I)
10. (1)
10. (Jl

10.0 (|)
KA11M ADVI!
ACUTE 1 DAT
(EXCtPT WEtE IOTED)
Pf*>

SO

UOO (10 OATI


1000 (10 itay)

.

233



740
2000 (k>
20,000
90 (10 

0.0022








0.66

0.19

0.94
0.033


0.8
(•)  ChMlecl dit* froi Bonltorlni Mil (Mpllnfl on mi imrtay effcltt (M*  TibU 5-4).
(b)  Choice! d«t« Itam trcetr Rttnrch wblU I* ftuly oflilt*.
(c)  US EPA Nnliui ContMlnmt ll"lt (MCl)i   SO CFR 46902; Rovotwr 13.  19M.
(d)  US EPA PrepoMd MClOi  SO C« 46936;  Rovcifcer 13. 1985.
(t)  drinking Mt*r Ktlon level* rtcowmdcd by the CellfemU Dtpcrtacnt of Rnltk Scrvle**. October  1987.
(I)  Effluent Hal let lone for d lecher t*« te eurfeee wet*re receemiided by Cellfornle *t«lonel Meter Ouellty Control Roerd In the lee In Hen.
       Depending, en elte-epeclf Ic fectere. beet evelleble technology (RAD «ey be required to further reduce concent ret lone In the dledierfe,
(t)  Induetrlel  Wette 0lecher** Rcguletlone for thet Aree Irlbutery to Sen Joee-Sent* Clere Meter Pollution Control Plent.  loveeter 1986.
(h)  Drinking Meter Reelth Advleorlee fro- US EPA  Office of Drinking Meter Ouellty.  Subject to Cheng*.
(I)  RAIMC:  Retlonet Aufclent Meter Ouellty Crlterle US EPA 4*0/5-84-001. Key 1986.
(I)  PublIcly-Ouned Treetwnt Morte (POTW) Olecherg* Halt on Totel Chlorlneted Orgenlce It 10 ppb.
(k)  Oreft US EPA Itoelth Advisory.
(I)  Eelleafed trece velue.
(•)  Interlei Unit  only.  Hnel Halt to be eeteMlttwd be**d jon future bloeeieye of IRIO treeted effluent.
•lenk Specei  No eiletlni reoplteennt.
1986. tAlch le currently being revleed.
ROTE I
       Phtholetee end dlchloroMthene nor* oaltted froa thle teble due to unrelleblllty of eupportlne dete.
       (They eopeer to be leboretory or field contealnente.)

-------
                                                                                fUlf 8-1
                                rtociu MD nun or CALIFORNIA (EOUUTORT. ADVISORY. MO ACTION LEVEL* m AMITIES n GMUMHMUI (continued)

ANAim
VOLATILE (MGMin (continued)
1.1.2.2-letrechloroethane
1.1,1-lrlchloro*th*ne
TrlcMoroethene
Vinyl Chlerld*
rrcon 111
PESTICIDES
CMordan*
Toxephene
POLKRIORINATED gYPNENHS
PCS*
NICNEST UVfl
GROUNDWATE* AT
IK IUO fltf
H* <•)

UO.O
120.0
2108.0
1100.0
41.0

0.2
2.0

6.4

DftlCIED
OMSITE
ft*> (b)

w.o
2600.0
520.0
22.0





CONTAMINANT
ICVCl (e)
PI*

200
I
2

J



CONTAMINANT
LEVEL OMlt (d)
H*

200
0
0

0
0

0
c* DNS
IMtEl ACt ION
LEVELS (•)
«*

200
5.00
2.00
18000

0.05S



DISCHARGE
UNITS (f)
H*



!.().<•)
8.0.

8.0.

DISCHARGE
REOUI*ENEN!S (f)
B*

10.0 (It
10.0 (|)
10.0 (|)
10.0 <|>

10.0 (I)
10.0 

10.0 (1)
DEALT* AOVII
ACUTE 1 OAT
(EXCEPT ME«E MOTED)
W*

UOOOO (k)
2600 (10 

200





cmoNic
CANCER
ppb/70kg

2.8
0.015

0.0218
0.011


EM M
NON-
CANCER
K*>

18*00

0.00*1
0.0002

O.OJ*
WOC (II
CANCER
PI*

0.17
t.T
t.r
2.0

0.000(6
o.ooon

0.000079
(•)  Omilcil del* fro» •anllerlnt Mil Mptlnf on mi nnrby of (tit* UN t«bl» 5-«).
(b)  Chmlctl d*U frai TrK«r Rnrarch •abll*  lab (turfy offcltt.
(e)  IIS EPA Nulaui ContMlrant Unit (NCl)i  50 CfR (6902; Nevntor  1]. 1985.
(d)  US EPA Propntd NC16:  50 CFR 469M; Novoter 1). 1985.
(•>  Orlnklnf Mttr •ellon  l«v*lt rccoMicndcd by tt>« Cillfarnl* OtpuHmtHt of Nnlth Strvlcm. Octobtr 1987.
(f)  Efflutnt Iliittctlani for dlidiM-tn to rartceo twttri rocunmidtil by CcllfomU Rtf lonal U»t«r Owllty Control 8oord In MM twin Pl«n, Ruvtoinr  1986. Nbldl It currently b»ln§ rev I ltd.
       Depending on •Itt-tpeclllc (octori, bMt ovolloblo tcchnolofy  (BAT) cvy bo required to further reduce concentration* In the dlichirfe.
(•)  Induitrlol Unto BUehwte Regulotlani for thot Aroo Trlbutory to Son Jote-Sent* Clor* Witer Pollution Control Plont. No»e«t>«r  1986.
(h)  Orlnklnf Itater Roolth  AdvUarlc* Ira* US EPA Office of Drinking  Water Outllty.  Subject to Change.
(I)  NAWOCI  National Aslant Utter Quality Criteria US EPA **0/5-86-001. Hay 1986.  (10-4 cancer rlak leveti)
(I)  Publlcly-Ounad Ireitvent Uorka (POTW) DI (charge Halt on total Chlorinated Organic! la 10 ccfc.
(k)  Draft US EPA Health Advlaory
(I)  Satlaated trace value.
(•)  SetOK detection
Blank Spec*!  No editing reojulraaant.
o
•OtEs
       Phttotate* and dlchloroMthana Her* oattted fro» thli table due to unreliability of •upportlng data.
       (they oHiiai '° be laboratory or field contaminanti.)

-------
    o    reinjection of water  into  an  aquifer is  controlled  by
         CRWQCB  and  the provisions  of  the Safe Drinking  Water
         Act which require that  the quality of water  should  at
         least meet  the drinking water  standards  prescribed  by
         EPA  and  California  Department   of   Health  Services
         (DHS).   In  addition,   the best  available  technology
         must  be   used  for  treatment   of   water   prior   to
         reinjection;
                              \
    o    the discharge  of  treated  groundwater to  POTW from the
         LB&D  site  is  prohibited  by  San  Jose  Municipal  Code
         Ordinance #20710,  Title 15, Section 15.12.200; and

    o    the  discharge  of   volatile organic  compounds  (VOCs)
         into the atmosphere  is  controlled by the Bay  Area  Air
         Quality  Management   District   (BAAQMD).   The  releases
         from the air stripper at the LB&D  site will  be subject
         to  toxic  risk  assessment  as  required  by  the  Air
         Pollution  Control   Officer's  proposed  Guidelines  for
         Risk  Screening  and  Risk   Management.   The  LB&D  air
         stripper would have  to satisfy  the  BAAQMD  licensing
         requirements.

8.2  TREATMENT TECHNOLOGIES

Four  alternatives  were evaluated in detail in the  Engineering
Evaluation and Cost Analysis (EE/CA) (Ebasco,  May 1988):

    Alternative A:  No Action (Periodic Groundwater Monitoring);

    Alternative B:  Groundwater  Extraction;  Granular  Activated
                    Carbon    (GAC)   Treatment;    Disposal   of
                    Groundwater to Storm Sewer;

    Alternative C:  Groundwater  Extraction;  GAC Guard Bed  for
                    PCB    Removal;     Air    Stripping;    Fume
                    Incineration  or  GAC   Vapor   Control;   GAC
                    Polishing    Bed;    Disposal   of    Treated
                    Groundwater to Storm Sewer; and

    Alternative D:  Groundwater   Extraction;   Ozone-Ultraviolet
                    (ozone-UV);  GAC Polishing Bed;  Disposal  of
                    Groundwater to Storm Sewer.

The primary  treatment  technologies  were chosen on the  basis  of
removal  of  organics,  to the  cleanup objective levels  given  in
Table 8-2.   Subsequent  to  the May  1988 EE/CA, and  performance
of treatability  studies and  additional  groundwater analyses,  it
was felt that nickel removal may have to be considered in order
to  attain   present   NPDES   effluent  limitations.   Therefore,
Ebasco has  included  an example  of  the  type of treatment  which
                             II-8-4

-------
                                0000231
            TABLE 8-2
SHALLOW GROUNDWATER CLEANUP OBJECTIVES





Compound
1,2 Dlchloropropane
Trlchloroethane
Chloroform
1 ,2-D1chloroethane
1 ,l-D1chloroethene
Tetrachloroethene
1,1.2,2-
Tetrachloroethane
Trlchloroethene
Vinyl Chloride
Benzene
PCBs (Total)
Chlordane
Toxaphene
Arsenic
Barium
Chromium (Total)
Z1nc
Cobalt
Nickel
Minerals (pom):
Calcium
Magnesium
Potassium
Sodium
Bicarbonate
Chloride
Sulfate
Silica
pH
* «. Interim llmi
bloassays of
NP . No limit has
(1) - 0.065 ug/1 1
number 0.065
limits of al

Estimated
Contaminant
Concentrations
In Extracted
Groundwater
(ug/1)
25
42
8.0
16
26
17

28
651
155
6.2
0.31
0.01
0.1
0.2
120
3.0
5.0
13
36











Expected
NPDES
Discharge
Limit
(ug/1)
5
5
5
1
5
5

5
5
2
5
0.065
0.014
0.24
20
NP
11
58
NP
7.1*

97
140
1
210
1,293
79
84
26
7.0



Federal
MCLs
(ug/1)
. NP
NP
NP
5
7
NP

NP
NP
2
5
0
NP
5
50
1000
50 (Cr +6)
NP
NP
NP










t only. Final limit to be established based
LB&D treated effluent
been promulgated for
s the method detection
used 1n this table 1s
.


Desired
Treated
Effluent
Level
(ug/1)
5
5
5
1
5
5

5
5
1
5
0.065CD
0.014
0.24
0.23
N/A
N/A
N/A
N/A
7.1*










on future

this compound.
limit for
meant to
aroclor 1242
represent the
only. The
detection
1 the PCB aroclors combined.
II-8-5
*



-------
could  be utilized  for nickel  treatment,  in conjunction  with
Alternatives  B,  C,  and D.  The  need to actually  utilize  such
technology  however   is  pending   final  determination   of  an
appropriate   NPDES   Permit  effluent  limitation   for  nickel.
Determination  of  this effluent   limitation  will  include:  an
evaluation of whether  the source  is controlled to  the  maximum
extent  feasible; an  analysis  of  the  costs and  benefits  of
reducing  (treating)  nickel  concentrations  to  (as  low  as)  7.1
ppb;  and an  assessment  of  effluent  toxicity  to  fish  and/or
invertebrates using bioassay procedures  to  be prescribed by the
Regional Water Quality  Control Board in conjunction with EPA.

In  this  section,  conceptual  designs  and  order-of-magnitude
(-30%,  +50%)  cost  estimates  are given  for each  alternative.
For  purposes  of  comparison, cost  estimates  include  potential
removal  of  nickel  by  the  candidate  treatment  technologies
described.  Further,  they are based  on  an assumed  groundwater
flow  rate of  100 gallons per  minute (gpm).   Results of EPA's
ongoing RI, which includes aquifer pump  tests, will  provide the
data  needed  to  make  an  accurate  and precise determination of
extraction rates prior  to final design of the system.

8.2.1  Alternative A:  No Action (Periodic Groundwater
       Monitoring)

The  "no  action"  alternative would  require  that no  remedial or
removal  actions  take  place  at this  time.    Adoption  of  this
alternative will require monitoring of plume migration.

Based  on the  calculations shown  in Table  6-2,  the  "No  Action"
Alternative would fail to  reduce  the  existing public  health
risks.   However,  the  ongoing  monitoring  programs  that   are
included  in the  "No  Action"  Alternative  would provide an early
warning if the drinking water aquifer became contaminated.

8.2.2  Groundwater Extraction System

As  discussed  in  Section  5.0,  the level  of current  information
precludes  a  detailed  design  for  the  groundwater  extraction
system at this time.   The design  of the system will be provided
in  more  detail after  the  field activities associated with the
RI  are performed in  October  and November 1988.   Final design of
the  entire  system  will  await  the  initial  installation  of
several   of   the  extraction  wells.    Nevertheless,   for   the
purposes  of the  EE/CA, a  conceptual  design had to  be selected
to  establish   a  baseline  and  estimate  costs.   The  extraction
well  system  conceptualized  for  such  purposes  is  shown  on
Figure 8-1.
                             II-8-6

-------
                             TCA PLUME
                             (approximate)
                   VINYL CHLORIDE
                      PLUME
                            TCI PLUME
         PUMP
        STATION
EXTRACTION
 HELLS
                FORCED
                 MAIN  V 'VTREATMENT
                           PLANT
                     LORENTZ  BARREL
                       & DRUM SITE
GROUNDWATER
   FLOW
                                          FIGURE  8-1
                                          PROPOSED EXTRACTION
                                          WELL FIELDS
                                          LORENTZ BARREL & DRUM

-------
                                           0000231
The  system  is  designed  to prevent  the  existing  plumes  from
migrating  further,  and  to remove  the  existing  contaminated
groundwater so it can be treated.  To accomplish  this,  lines  of
wells were  considered:  a pair of wells  at  the  northeast corner
of the site, where groundwater contamination is known  to be the
highest;  two  principal  lines of wells,  one  at  the  northern end
of the TCE/vinyl  chloride  plume,  and the other along  East  Alma
Avenue;   and  two   200-foot-wide   lines   of   wells   at  • the
downgradient  ends  of   the two   smaller  side  plumes.    The
treatment facility will be located on the LB&D site itself.

Order-of-magnitude   (-30%,  +50%)   capital   costs   for   the
groundwater extraction system have been estimated at $803,000.

8.2.3  Alternative B;  Groundwater Removal. GAG Treatment.
       Nickel Removal, Disposal to Storm Sewer

As shown  in Figure 8-2, this  treatment  alternative consists  of
the following series of processes:

    o    a  groundwater   interception  system  identical  to  that
         described in Section 8.2.2;

    o    ion   exchange   water   softening   to   prevent   scale
         formation.  The spent resin is  regenerated daily using
         dilute  brine.   The spent  brine  is  not a  RCRA waste,
         but will be disposed of appropriately;

    o    a GAC  guard bed  to remove PCBs  and pesticides.   The
         spent  GAC from the  guard. bed is  shipped to  offsite
         incineration facilities;

    o    a GAC  main bed for VOC  removal.   The  spent GAC  from
         the main bed is  shipped offsite  for  regeneration  once
         per year; and

    o    if  necessary,-  an  ion-exchange  column   for   nickel
         removal.  The  spent resin is  regenerated  onsite using
         dilute acid.  The  spent  regenerant  solution is  shipped
         offsite  for  recycling  and  disposal  at  a  licensed
         hazardous waste disposal facility.

For  this  analysis,  the influent  flow  rate  is  assumed to  be
100 gpm.  Approximately fifty-two million  gallons per  year  of
groundwater would be treated.

The  total estimated  order  of magnitude  capital  cost  (-30%;
+50%) for  this system  is  $1,902,000.  The  estimated first  year
costs are $255,000.   Based on an  assumed  10 year  project  life
and  a  10 percent  discount  rate,  the  present  worth  for  the
Alternative  B system is  $3,469,000.    Costs  for  all  of  the
alternatives are  summarized on Table 8-3.
                             II-8-8

-------
                           TABLE 8-3

               SUMMARY OF COSTS  (-30% +50%) FOR
                    TREATMENT ALTERNATIVES*

•
Capital Costs
First Year
Operation and
Maintenance
Present Worth

B
GAC
1,902,000

255,000
3,469,000
Alternative
C
>GAC/Air Stripping
1,964,000

243,000
3,457,000

D
Ozone-UV/GAC
2,022,000

198,000
3,238,000
*  The estimated capital  and  O&M costs of treating the effluent
   for  removal  of   nickel   are  $200,000.  and  $54,000/year,
   respectively.  These are assumed constant among alternatives.
                             II-8-9

-------
                  .Brine
                Regenerant
                                                                                                                      Acid
                                                                                                                    Regenerant
   Raw
  Water
 (100 gpm)
   Water
  Softening
(Ion Exchange)
                   Spent
                   Brine to
                   POTW
                 (10,000 gpd)
PCB/GAC
Guard Bed
VOC/GAC
 Main Bed
                         Spent PCB/GAC
                           to Incinerator
                           (2,000 Ibs/yr)
   Nickel
  Removal*
(Ion Exchange)
  Treated
 Effluent to
Storm Sewer
                                                   Spent VOG/GAC
                                                      to Recycle
                                                    (50,000 Ibs/yr)
                                                          Spent
                                                       Regenerant to
                                                         Disposal
                                                       (2,000 gal/yr)
*  If necessary
                                                          Figure 8-2
                                      Flow Diagram for Liquid-Phase GAG Treatment

-------
8.2.4  Alternative C;  Groundwater Removal. Air Strippina/GAC
       Treatment. Nickel Removal.. Disposal to Storm Sewer

This alternative includes the following operations:

    o    a  groundwater  interception  system  identical  to  that
         described in Section 8.2.2;

    o    ion   exchange  water   softening   to  prevent  scale
         formation (as discussed in Alternative B,  above);

    o    a  GAC guard bed adsorption  system to remove PCBs  and
         pesticides;

    o    an  air stripper  with  a  vapor  phase GAC  scrubber  to
         remove most of the VOCs;

    o    a  liquid phase GAC system to remove unstripped VOCs;

    o    ion exchange nickel removal; and

    o.    disposal of treated effluent to a local storm sewer.

The  flow   diagram  for  this   treatment   system   is  shown  in
Figure 8-3.  Following  water softening,  a  combination of three
systems will be used to  remove  PCBs/Pesticides  and VOCs.  A GAC
guard  column  is first used  to  remove PCBs/pesticides.  Next,  a
packed tower  air stripper with a  vapor-phase GAC  scrubber  is
used   to   remove  the  most  easily   stripped VOCs  from  the
groundwater.   Finally,  VOCs  that  are  not  removed  by  the  air
stripper  are  removed  by  a  downstream  GAC  polishing  column.
Although the  May 1988 EE/CA  identified fume  incineration  as  a
possible  component  of  this  alternative,  recently  completed
treatability  studies showed  that   a  fume  incinerator  was  not
necessary,  and that a vapor  phase GAC unit  would be adequate.
Finally, an ion exchange column can be  used  to remove nickel if
necessary.

The hydrocarbon  exhaust  rate  from  the air stripper/GAC  scrubber
will be less  than  the 15 Ibs/day  limit specified  by the BAAQMD
for  total   emissions  of  smog   inducing   substances  in  the
atmosphere.  These emissions  will  concurrently comply with  the
10~6  cancer risk  limit  imposed  by  the  Toxic Risk Screening
Policy of the BAAQMD.

As  shown  in Table  8-3,  the estimated  capital cost for  this
alternative   is   $1,964,000.    First   year   operation   and
maintenance costs are estimated at  $243,000.   The  present worth
of this alternative  is  $3,457,000  using a 10-year life  and a 10
percent discount rate.
                            II-8-11

-------
                Brine
              Regenerant
                                                                                            Clean Au-
                                                                                           to Exhaust
  Raw
  Water
(lOOgpm)
Water Softening
(Ion Exchanger)
  PCB/GAC
Guard Column
             Spent Brine to
            POTW Disposal
            (10,000 gal/day)
                                                                        Vapor Phase
                                                                        GAC Scrubber
                                                                                  t
                                                      Spent GAC to
                                                        Recycling
                                                      (24,000 Ibs/yr)
Dilute Acid
Regenerant
                                                   Air
                                                   Stripper
                                       Fan
                                                                       VOC/GAC
                                                                      Main Column
                                                                                                 Nickel Removal*
                                                                                                  (Ion Exchange)
                                                                                                              Treated Effluent
                                                                                                              to Storm Sewer
                                     Spent GAC
                                      toOffsite
                                      Incinerator
                                    (2,000 Ibs/yr)
                                                                                  Spent Regenerant
                                                                                 *  to Recycling
                                                                                    (2,000 gal/yr)
                                                                           Spent GAC
                                                                           to Recycle
                                                                          (12,000 Ibs/yr)
                                                                                                                                   o
 * If necessary
                                                              Figure 8-3
                                          Flow Diagram for GAC/Air Stripping Treatment

-------
                                                  0000231
8.2.5  Alternative D;  Groundwater Removal.  Ozone-UV/GAC
       Treatment. Nickel Removal.  Disposal to Storm Sewer

The  flow  diagram  for  this treatment  alternative  is  shown  in
Figure 8-4.  A  combination of  two  technologies would  be  used:
first,  a   commercially  available  packaged  ozone-UV  system  to
destroy VOCs and  PCBs/pesticides; and  second (if necessary),  an
ion  exchange column to remove .nickel.   Ozone-UV treatment has
been  shown to  be  effective  for destruction of  PCBs/pesticides
and  VOCs  such  as  1,1,1-TCA,  TCE,  and  vinyl  chloride.   Also,
treatability studies conducted in  August 1988  determined  that
GAC  polishing  was  not  necessary.   Based on  discussions  with
equipment  manufacturers,  it  is assumed  that  pretreatment for
water softening should not be needed.

Estimated  capital  cost  for  this   alternative  is  $2,022,000
(Table  8-3).  First  year  operation  and  maintenance costs are
estimated at $198,000. Assuming a  10-year life  and  a 10 percent
discount   rate,  the present   worth  of  this  alternative  is
$3,238,000.
                            II-8-13

-------
                                        Ozone
                                       Generator
                                                                             Acid
                                                                           Regenerant
Raw Water
(100,000 gpd) ^

o
o
o
o
0
0
o
o
0
o
o
0
o
w

Nickel
Removal *
(Ion Exchange)
^ Treated
Effluent to
Storm Sewer
                     UV-OZONE
                      SYSTEM
    i
    t
 Spent Acid
to Recycling
(2,000 gal/yr)
* If necessary
                                     Figure 8-4
                   Flow Diagram for Ozone/UV Treatment System
                                                                                                   CO

-------
                                                   0000231
9.0  SUMMARY OF THE COMPARATIVE ANALYSIS OF ALTERNATIVES

9.1  COMPARISON OF ENGINEERING EVALUATION/COST ANALYSIS
     AND FEASIBILITY STUDY GUIDANCE CRITERIA

The  United   States  Environmental   Protection  Agency   (EPA)
guidance  criteria  for  evaluating  remedial  alternatives  for
Engineering   Evaluation   and .  Cost   Analysis   (EE/CA)    and
Feasibility Studies (FS) are presented below for comparison.
  FS Guidance Criteria

  o  Short-term effectiveness
  o  Long-term effectiveness
     and permanence
  o  Reduction of toxicity,
     mobility, or volume
  o  Implementability
  o  Cost
  o  Compliance with Applicable
     or Relevant and Appropriate
     Requirements (ARARs)
  o  Overall protection of
     human health and
     environment
  o  State acceptance
  o  Community acceptance
                                    EE/CA Criteria
                                  (non-time-criticaV)

                                  o  Technical feasibility
                                     -  Effectiveness
                                     -  Demonstrated
                                        performance
                                        Operation and
                                        maintenance
                                        requirements
                                     -  Useful life
                                     -  Environmental effects
                                        upon operations
                                     -  Constructability
                                  o  Reasonable cost
                                  o  Institutional
                                     considerations
                                     -  Permitting and other
                                        factors
                                        affecting startup
                                     -  Time to complete
                                     -  Safety
                                  o  Environmental impacts

The  major  differences  between  the EE/CA  guidance  and the  FS
guidance are  that  there are no  requirements to meet ARARs or to
perform  a  Risk Assessment  in the EE/CA.  As  shown  above,  the
evaluation  criteria  are  otherwise very  similar.   Since  the
Lorentz  Barrel &  Drum (LB&D) EE/CA  included consideration  of
ARARs   and   provided   preliminary   risk   assessments,    the
alternative  actions  have  been   evaluated  by  all  of  the  FS
criteria.

9.2  COMPARISON EVALUATION METHODOLOGY

The  evaluation  method  used  is  based  on  the  method  under
development  by United  States Environmental  Protection  Agency
(EPA) as EE/CA guidance  for  non-time-critical  removal actions.
This  method  uses  a   set  of   criteria   based   on  technical
feasibility,  cost  reasonableness, institutional  considerations,
and environmental impacts.  Table 9-1 presents the  criteria and
associated ratings.
                            II-9-1

-------
                                                   0000231
                           TABLE 9-1

                TECHNOLOGY SELECTION CRITERIA*
                                                        Rating
             Criteria                                   Points
1. TECHNICAL FEASIBILITY

    A.  Effectiveness

        .  Destroys hazardous substances                    4
        .  Prevents release of hazardous substances;         3
          contaminants are isolated but not
          eliminated
        .  Minimizes the release of hazardous               2
          materials; adequately protects public
          health and environment
        .  Allows or promotes release of hazardous          1
          substances; ineffective.

    B.  Demonstrated Performance

        .  Proven reliable in the field under similar       4
          conditions on the same waste materials;
          widely demonstrated to be effective
        .  Proven reliable in the field under similar       3
          conditions on similar waste materials
        .  Proven reliable, but under different             2
          conditions and materials; limited
          experience and reliability

    C.  Useful Life

        .  Permanent; irreversible                          4
        .  Long-term, potentially reversible;               3
          effectiveness decreases in time
          with a low probability of release
        .  Long-term, potentially reversible with a         2
          high probability for release
        .  Short-term solution; difficult to repair or      1
          replace upon failure; temporarily mitigates
          hazards; long term abilities questionable

    D.  .  Environmental Effects Upon Operations
        .  Performs well under all environmental            4
          conditions
        .  Performs well under most environmental           3
          conditions
        .  Performs adequately under most conditions        2
        .  Susceptible to adverse weather conditions        1

                             II-9-2

-------
                                                 0000231
                     TABLE 9-1 (Continued)

                TECHNOLOGY SELECTION CRITERIA*
                                                        Rating
             Criteria                                   Points
2. REASONABLE COST

    This item is discussed but not scored

3. INSTITUTIONAL CONSIDERATIONS

    A.  Permitting and Other Factors Affecting Start-up

        .  No permitting or significant lead time           4
          required
        .  Minimal lead time required (3 months)             3
        .  Moderate lead time required (6 months)           2
        .  Significant lead time required (1 year)           1

    B.  Time to Complete

        .  Can be completed within the 12-month             4
          statutory limit
        .  Site is expected to qualify for an exemption     3
          to the 12-month limit and an alternative can
          be completed within a reasonable time
          thereafter
        .  Site is expected to qualify for an exemption,    2
          but requires significant time beyond the
          12-month limit to complete
        .  Cannot be completed within the 12-month          1
          statutory limit and the site is not expected
          to qualify for an exemption

    C.  Safety

    1)  During Installation/Operation

        .  Very safe; requires no more than normal          4
          safety procedures required for workers
          at hazardous waste sites; no threat to
          surroundings at any time
        .  Safe; requires few safety procedures             3
          other than those normally required at
          hazardous waste sites; minor threat
          to adjoining residential areas may occur
        .  Hazardous; requires stringent safety             2
          procedures to ensure worker safety; may


                             II-9-3

-------
                                                 0000231
                     TABLE 9-1 (Continued)

                TECHNOLOGY SELECTION CRITERIA*
                                                        Rating
             Criteria                                   Points
          require evacuation of homes near  the  site
        .  Very hazardous;  requires remote operation         1
         'and evacuation of area homes

    2)  Effects of Failure

        .  Very safe; redundant controls  prevent            4
          hazardous substance release
        .  Failure results  in hazard that is less            3
          than that presented by the site prior to the
          removal action
        .  Failure results  in hazard that is                2
          approximately
          equal to that presented by the site prior  the
          removal action
        .  Failure results  in hazard greater than  that       1
          presented by the site prior to the removal
          action

    D.  Other relevant institutional considerations
        may be added

4.  ENVIRONMENTAL IMPACTS

        Positive environmental impact                      4
        No detrimental environmental impact                3
        Minimal adverse environmental impact               2
        Extreme adverse environmental impact               1
    Based on guidance from EPA for the EE/CA
                            II-9-4

-------
                                                  0000231
9.3  COMPARISON OF ALTERNATIVES

Staff from EPA and Ebasco met on August 30, 1988  to  discuss  the
alternatives  and select  one  for  implementation.  During  that
meeting, GAC and ozone/UV treatability test results  of  July  and
August  1988  were  presented   by  the  respective  vendors.   The
results  of those  tests  indicate  that  action   levels  can  be
achieved  by  either  technology.    Consequently,   none  of -the
alternatives  was eliminated based  solely on  ability  to' treat
groundwater to desired levels.

An  evaluation similar  to  that presented  in section  6  of  the
EE/CA was performed.  This  evaluation  assessed  each  alternative
in  light  of  the EE/CA evaluation  criteria.   The  results  are
presented in Table 9-2.  All of the treatment  alternatives were
scored  essentially  equal.   Present  worth estimates   are  also
approximately  the same, within  the accuracy  of  the  estimates
that were prepared.

Three  primary distinctions can be  made among  the  alternatives
however.  These  are:

    o    GAC  systems have  been  proven reliable  over  a  longer
         time period than the ozone/UV system;

    o    the  ozone/UV  system  provides  onsite  destruction  of
         contaminants,  as   opposed  to  transporting  wastes  for
         offsite    destruction    of    contaminants    through
         regeneration of the carbon; and

    o    GAC/air   stripping   could   require   additional   air
         emission  controls  in  order  to  comply  with  BAAQMD
         standards.

Two other water  treatment  considerations were  identified during
the treatability testing.   One involved  influent  treatment;  the
other  involved  possible effluent  treatment.    The  GAC testing
revealed  a carbonate  precipitate  in  the  test  column.   As  a
result,  it was  recommended  that  a  water  softening  step  be
included prior to  the  GAC  options.   The ozone/UV system did not
experience  scaling  during the   treatability   testing.    Both
processes    require    further   consideration   of    effluent
concentrations of nickel as well.   This issue will  be examined
through  additional  groundwater  sampling  and  analyses,  and
bioassays  of  treated  effluent.   If  results of  these studies
show  that  nickel removal is necessary, a  treatment  system such
as  that described  in  Section  8.2.3 will  be  included  in  the
process prior to discharge of the effluent.

In  consideration of  all  of the -factors,  EPA has decided that
the  best  course of action   is  to  demonstrate  the  ozone/UV
                             II-9-5

-------
                                         TABLE  9-2
                                COMPARISON OF ALTERNATIVES
Alternative A
No Action
Technical Feasibility
. Effectiveness
. Demonstrated Performance
. Useful Life
. Environmental Effects
on Performance .
Subtotal Score
Institutional Considerations
. Permitting and Startup
. Time to Complete "
. Safety
Subtotal Score
Environmental Impacts
TOTAL SCORE
Estimated Costs

1
1
1

-1
4

2
2
-2
6
1
11

Alternative C
Alternative B GAC/Air
Liquid Phase Stripping/
GAC Vapor Control

.3
x 4
3

_4
14

4
4
_4
12
4
30


3
4
3

_4
14

3
4
_4
11
4
29

Alternative 0
Ozone-UV
X
4
3
3

_4
14

4
4
_4
12
4
30

   Capital  Cost                        *       1,902,000      1,964.000       2,022,000
   First  Year Operation  and
   Maintenance                        •        255,000        243,000         198,000
   Present  Worth  Costs         $170,000       3,469,000      3,457,000       3,238,000
•These costs  will  depend on:

    - the number of monitoring wells;
    - the frequency of  monitoring;  and
    - which chemical  analyses  are chosen.
                                                II-9-6

-------
                                                0000231
technology   through   the   Superfund   Innovative   Technologies
Evaluation  (SITE)  program.   This  selection  was  made for  the
following reasons:

    o    the   technology   provides   onsite   destruction   of
         contaminants;

    o    a  several  week(s)  demonstration  will  allow  EPA  to
         determine the reliability of the ozone/UV system;

    o    it  appears  that   ozone/UV   may  not   require   water
         softening.   However,  the demonstration will  allow  EPA
         to  determine  whether  an  eventual  carbonate  scaling
         problem can  be  dealt with  through  pH adjustment rather
         than water softening;

    o    there  will  be  no  long-term  commitment  of  taxpayer
         dollars   until   the   testing   program   conclusively
         demonstrates the success of the technology; and

    o    should  ozone/UV not  prove adequate  based on  further
         testing, Alternative B (Liquid Phase  GAC)  provides an
         adequate backup remedy.

EPA's selected remedy is described in detail in Section 10.0.

9.4  TREATED EFFLUENT DISPOSAL

Of  the  four  treated  effluent  disposal  options,   only two  are
technically  and administratively  feasible:   discharge  to  the
storm  sewer  and  Coyote Creek;  and  groundwater  recharge   by
reinjection  wells.   Each  of  the  four  options  are  described
below.

Storm Sewer/Coyote Creek - This is  the  least  expensive and most
reliable  option.   It would only require that a  force main be
constructed  to  the  nearest  storm  drain.   The  California
Regional  Water  Quality   Control   Board   (CRWQCB)   discharge
requirements  for  surface  water  disposal   would  have  to   be
satisfied.

Groundwater  Reinfection  -  This  option  is  feasible.   Effluent
disposal  would  be  performed  by  pumping the treated  effluent
back  into the  shallow  aquifer,  using  a series  of reinjection
wells.   Because of  the  need  for  extra wells  and  pumps,  this
option  would  be  expensive  and  more  subject  to  mechanical
problems than would the  "storm sewer"  option.   The pretreatment
standards   established   by   the   CRWQCB   would   have   to   be
satisfied.  As an alternative  to  using  reinjection wells,  there
are  currently  several   large  municipal  groundwater  recharge
basins within a  few  miles of the LB&D site.   The  LB&D effluent
could  conceivably   be   pumped  off   site   to  one   of   those


                             II-9-7

-------
facilities.   However,  this  would  be   impractical  because  it
would  require  construction  of  miles  of  force  main  through
residential areas.

Publicly  Owned Treatment  Works  (POTW)  Sanitary  Sewer  -  This
option   is   not  feasible.    Discharge   of   any   groundwater,
pretreated  or  not,  to the  POTW sanitary sewer  is forbidden by
the San Jose Municipal Code Ordinance #20710,  Title  15, Section
15.12.200.

Industrial  Reuse  -  This option  is technically  feasible  but it
would be expensive and impractical.  The treated effluent could
conceivably be  stored and used by local industries  for process
water.  However, it would  require  construction of  large storage
tanks  and  complex  water   distribution  piping  systems.   This
option would  not  be .practical,  since there  are  no  industries
near  the  LB&D site  that  require  a  large,   steady  volume  of
process  water.   The  disposal  of  the LB&D  effluent  would
therefore  be  limited by  the fluctuating  water needs  of  many
small businesses.

In summary, the most  practical and  least expensive  alternative
for  treated  effluent disposal  during  the Expedited  Response
Action   (ERA)/Operable  Unit   is  disposal    to   the   storm
sewer/Coyote Creek.   Industrial  reuse  and groundwater injection
will  be  studied in  more detail during  the Feasibility Study.
Any  pf  these options could be selected  as  a  long-term solution
to the disposal question.
                             II-9-8

-------
                                                 0000231
10.0  THE SELECTED REMEDY
The  selected  remedy  consists  of  the   following   items:    a
groundwater extraction system; an  above-ground  treatment  system
(ozone/UV plus  nickel  removal);  and  treated effluent  disposal
to the storm  sewer.  As  mentioned  in Section 8.2,  until a final
decision  is   reached   between   EPA   and  CRWQCB   concerning
appropriate effluent limitations for nickel,  it is assumed that
NPDES discharge  limits  will  ^require nickel  removal.  Each  of
these items are described in the following sections.

The selected remedy was chosen for the following reasons:

    o    the contaminated shallow  groundwater will be contained
         and  removed,   thereby  minimizing  the  potential  for
         future contamination of deeper drinking water aquifers;

    o    the  ozone/UV  treatment system will  treat all VOCs  to
         below  the  MCLs  and  NPDES discharge  limits,  and  will
         treat PCBs/pesticides to below detectable levels;

    o.    as  discussed  in  Chapter 9.0,  the ozone/UV treatment
         system  received the  highest overall  rating among  the
         alternatives,   and  has  the  lowest  estimated  present
         worth cost; and

    o    the ozone/UV  treatment  system  can be  field  tested  for
         reliability    under    EPA's    Superfund    Innovative
         Technology Evaluation (SITE) program.

As discussed  in Section  8.2.2,  the groundwater  plume will  be
intercepted  and  collected using the extraction system  shown in
Figure 8-1.

As shown in Figure 8-4,  a combination of  two  technologies would
be  used:   First,   a  commercially  available  packaged  ozone/UV
system to destroy VOCs and PCBs/pesticides; and second,  an  ion
exchange treatment  system  to  remove  nickel.  Ozone/UV treatment
has  been  shown  to  be  effective  for  destruction  of  PCBs/
pesticides and halogenated  hydrocarbons such  as 1,1,1-TCA, TCE,
and vinyl chloride.

EPA and other agencies have supported a variety of tests, which
have shown  that ozone/UV  treatment  is effective  for permanent
destruction  of  VOCs  and  PCBs/pesticides  in  wastewater  and
groundwater.   Treatability tests  using  LB&D   groundwater  were
performed  in July  and August 1988.   These tests showed  that
VOCs could  be  destroyed to  below the NPDES discharge limits.
In 1980,  at a General Electric plant in Hudson  Falls, New York,
a  commercial   ozone/UV  treatment  plant  was  installed  and
successfully operated  to destroy  PCBs  in groundwater  to below
detection levels.
                            II-10-1

-------
                                                 000(631
The  contaminated  groundwater  will  initially  be  pumped  to  an
equalization  tank.   This tank  will  provide roughly  30  minutes
of storage  and will  dampen  any  short-term  variations in  flow
rates  or  contaminant concentrations.  A  commercially-available
packaged  ozone/UV  treatment  system will  be  used  to  destroy
PCBs/pesticides  and  other  organic  compounds.    The  ozone/UV
treatment  method  utilizes   ozone's  strong  oxidizing  capacity
with  UV  light's  additional  energy  to  provide  considerable
amounts of  free radicals and  excited-state  species  capable  of
effectively destroying the contaminants present.

Ozone  is  provided  by an onsite  generator and  bubbled  through
the  wastewater.   The ozonated wastewater  is  then  subjected  to
high intensity  UV  light  in  a packaged treatment  vessel.   The UV
light originates from an array of  quartz-enclosed low-pressure
mercury  lamps.   It  is  assumed  that ozone/UV  treatment  will
destroy the PCBs/pesticides, vinyl chloride,  1,1,1-TCA,  and TCE
in  the  influents.    The  residence  time  of  the  water  in  the
ozone/UV  unit is  40  minutes.   The  wastewater is  treated  using
an oxidant  dosage  of 75  mg/1 of ozone plus 25 mg/1 of hydrogen
peroxide.   Contaminant destruction  occurs inside  the treatment
vessel.

EPA  will  be working  with CRWQCB  to determine NPDES limits for
nickel.   If necessary, nickel  can be removed using  a packaged,
commercially   available    ion   exchange   system.    Additional
treatability  studies will  be  required  to select  the best  ion
exchange  resi'n.  Based on discussions  with resin manufacturers,
the  resin will be contained  in  conventional columns.   The  spent
resin will  be regenerated  several times  each year, using dilute
acid  as  the  regenerant  solution,  and  will   consist   of  a
neutralized nickel  sulfate  solution.  The  spent solutions will
be shipped to an offsite recycling firm if  further data  suggest
that economical recovery of  the nickel sulfate is possible.  If
not, the  waste  will be disposed of in accordance  with existing
solid and hazardous waste legislation.

The  ozone/UV  system will be  delivered  prepackaged and installed
skid-mounted.   The  ozone/UV   treatment  system,   the   nickel
removal columns,  and  all  required pumps  and controls will  be
housed  in a prefabricated building.   The  treatment  plant  site
will be fenced to prevent public access.

The  estimated capital and  operating costs  for   the  extraction
and  treatment systems are listed  in Table  10-1.  The  capital
costs for the groundwater extraction  system are  based on Ebasco
engineering estimates.  The capital and operating  costs  for the
treatment system are based on manufacturers'  estimates.
                            II-10-2

-------
                          TABLE  10-1

           ESTIMATED (-30%,  +50%) COSTS FOR OZONE/UV
                     TREATMENT ALTERNATIVE
Capital Costs
  I/Direct
Site preparation
Groundwater extraction system
Flow equalization
Ozone/UV equipment
Nickel removal system
Levels, controls (etc.)
Building
Disposal force main
   $10,000
   803,000
     5,000
   300,000
   200,000
    20,000
    80,000
     5.000
$1,423,000
  2/Indirect
NPDES Permit application
Engineering Construction Management
  (15% Direct costs)
Contingency (25% Direct Costs)

Total estimated Capital Costs
    30,000

   213,000
   356.000
  $599,000
$2.022.000
O&M Costs (Annual)
               Operating labor
                 (2 days/week @ $300/day)             $31,000
               Ozone power/year ($0.263/1000 gals)     14,000
               Hydrogen Peroxide/year
                 ($0.125/1000 gals)                     7,000
               Ultraviolet power/year
                 ($0.266/1000 gals)                    14,000
               Ultraviolet maintenance                 16,610
                 (including lamp replacement
                 and labor)
               Replacement of Nickel removal
                 resin ($100,000/2 years)              50,000
                            II-10-3

-------
                     TABLE 10-1 (Continued)

           ESTIMATED (-30%, +50%) COSTS FOR OZONE/UV
                     TREATMENT ALTERNATIVE
O&M Costs (Annual) (Continued)
               Processing of spent resin
                 reactivation ^solution
                 ($2/gal, 2000 gals/year)               4,000

               Treated effluents analysis
                 (I/week e$300)                        16,000
               Groundwater sampling
                 (40 wells/year $2,500/well)           20,000

               System maintenance
                 (5% 03/UV and Nickel
                 removal equipment
                 Capital Costs)                        25.000
                                                     $198.000
               Present Worth (i = 10%, 10 yrs)     $3.238.000
                            II-10-4

-------
                                                00231
The  estimated   capital   cost  for  the   selected   remedy   is
$2,022,000.   The   estimated   first  year  operating  cost   is
$198,000.  The estimated present worth cost (assuming a 10 year
project life and a 10 percent  discount)  is $3,238,000.

Treated effluent will be  disposed  of  by pumping  directly  to the
nearest storm sewer.  The  treated  effluent  will  satisfy all  of
the  required NPDES  discharge .standards.   It is  assumed that
periodic  monitoring will  be   required  to  document compliance
with the pretreatment standards.
                            II-10-5

-------
                                                  0000231
11.0  STATUTORY DETERMINATIONS
The statutory requirements of  Section  121 of  the  Comprehensive
Environmental Response, Compensation, and Liability  Act  of 1980
(CERCLA) state that the selected remedy must:

    o    be protective of human health and the environment;

    o    attain   Applicable •- or   Relevant   and    Appropriate
         Requirements (ARARs);

    o    be cost-effective;

    o    utilize  permanent  solutions and alternative  treatment
         technologies or  resource  recovery technologies to  the
         maximum extent possible; and

    o    address  whether  the  preference  for  treatment   that
         reduces  toxicity, mobility,  or volume  as  a  principal
         element is satisfied.

11.1 .PROTECTIVENESS OF HUMAN HEALTH AND THE ENVIRONMENT

The  selected  remedy  is  protective  of  human  health and  the
environment  by   preventing   further  vertical  or   horizontal
migration  of  contaminants in  the  shallow aquifer and treating
the extracted groundwater  prior  to disposal.   It  also prevents
migration  of  contamination  into  the  deeper  drinking  water
aquifer  and  Coyote  Creek.   By   stopping   the  migration  of
contaminants  and  treating   the   extracted   groundwater,   the
selected   remedy   reduces  the  potential   threats    posed   by
contamination of Coyote Creek and the drinking water  aquifer.

11.2  ATTAINMENT OF ARARS

The  selected remedy  will meet  all substantive ARARs for  the
shallow groundwater, as discussed in Section 8.1.

The numerical limits  that apply to the shallow  groundwater  are
specified  on  Table 8-2.  The  results of  the  treatability  study
will demonstrate that this remedy achieves those action limits.

11.3  COST EFFECTIVENESS

All of  the  treatment  alternatives  are  essentially  equal  with
respect  to total  present worth costs.   No distinction can be
made  among these alternatives  from the  cost  point  of  view
within  the accuracy of the  estimates  that were prepared.   All
treatment alternatives are therefore equally cost effective.
                            II-ll-l

-------
                                                 (W0231
The selected  approach,  which is  to  perform a demonstration  of
ozone/UV   through   the  SITE   program,    is   especially   cost
effective.  It defers capital expenditures until  the technology
is demonstrated over a  reasonably long  term.   Such  an  approach
reduces the  ultimate  risk borne  by  the taxpayer by increasing
the level of knowledge about this technology at the  LB&D site.

11.4  UTILIZATION OF PERMANENT SOLUTIONS AND ALTERNATIVE
      TREATMENT TECHNOLOGIES TO THE MAXIMUM EXTENT PRACTICABLE

The   selected  remedy   meets  the   Superfund  Amendment   and
Reauthorization Act of  1986  (SARA)  preference  for  permanent
solutions to  the maximum extent  practicable.   It  is expected to
remove the contaminants from the  groundwater and  to effectively
destroy them  or convert them into harmless substances posing no
threat to human health and the environment.

11.5  PREFERENCE FOR TREATMENT THAT REDUCES TOXICITY, MOBILITY,
      AND VOLUME AS A PRINCIPAL ELEMENT

The selected  remedy focuses  on  treatment  of  the  contaminated
shallow groundwater to specified  action  levels.   This treatment
technology   is   expected  to   reduce   the   toxicity  of   the
contaminants  by  rendering  them harmless.   Mobility  is  reduced
by  use  of   the  selected   groundwater  extraction   system,
preventing  the  further   spread   of  the  plumes.    Also,   by
extracting  and  treating the  shallow  grpundwater, it is  likely
that the volumes of the plumes will be reduced.
                            II-11-2

-------
                                                0000231
12.0  REFERENCES
California, State of.  Department of Water Resources (DWR).
August 1967.  Evaluation of Groundwater Resources:  South Bay
Geology.  DWR Bulletin #118-1, Appendix A.

Canonie Environmental.  August 1987.  Draft Report, Remedial
Action Plan.  Submitted to Fairchild Semiconductor Corporation,
San Jose Facility.  Project No. 82-012.

CH2M Hill.  February 1987.  Preliminary Site Assessment Report.
Lorentz Barrel & Drum (LB&D).   Prepared for California
Department of Health Services (DHS) Contract No. 84-84540,
Task 2-5-2.0-P21039.

	.  November 1987a.  Technical Memorandum:  Preliminary
Hydrogeological Assessment.  LB&D.  Prepared for DHS Contract
No. 84-84540, Task 2-5-4.0-P21039.

	.  November 1987b.  Technical Memorandum:  Soil Gas
Survey.  LB&D.  Prepared for DHS Contract No. 84-84540,
Task 2-5-4.0-P21039.

	.  November 1987c. Technical Memorandum:  Well
Canvass, Volume I.  LB&D.  Prepared for DHS Contract
No. 84-84540, Task 2-5-4.0-P21039.

	.  November 1987d.  Technical Memorandum:  Treatment
Alternative.  LB&D.  Prepared for DHS Contract No. 84-84540,
Task 2-5-4.0-P21039.

Ebasco Services, Inc.  May 1988.  Engineering Evaluation and
Cost Analysis for a Shallow Groundwater Collection and
Treatment System, LB&D.  Prepared for United States
Environmental Protection Agency (EPA) under the REM III
Contract No. 68-01-7250, EPA Work Assignment No. 203-9L64.

Freeze, R.A. and J.A. Cherry.   1979.  Groundwater.  Prentice-
Hall, Inc.

Plunkett, E.R. 1976.  Handbook of Industrial Toxicology.
Chemical Publishing Company, New York.

Prengle, H.W. and C.E. Mauk.  1978.  New Technology:  Ozone/UV
Chemical Oxidation Wastewater Process for Metal Complexes,
Organic Species and Disinfection.  The American Institute of
Chemical Engineers Symposium Series, 74 228-243.

Sitting, M. 1981.  Handbook of Toxic and Hazardous Chemicals.
Noyes Publications, Park Ridge, New Jersey.
                            II-12-1

-------
                                                0000231
Stenzel, M. and U. Gupta.  December 1985.   Treatment of
Contaminated Groundwater with Granular Activated Carbon  and Air
Stripping.  JAPCA.  35(12), 1304-1309.

Tracer Research Corporation.   November 1987.   Groundwater
Investigation at Lorentz Barrel & Drum.  Submitted to CH2M Hill,

Turner, D.B. 1970.  Workbook of-Atmospheric Dispersion
Estimates.  Prepared for EPA. x

United States Environmental Protection Agency.   April 1980.
Carbon Adsorption Isotherms for Removal of Toxic Compounds from
Water Supplies.  EPA/600/8-80-023.  PB-80-197320.

	.  1985.  Chemical, Physical, and  Biological
Properties of Compounds Present at Hazardous  Waste Sites:
Final Report.  Office of Solid Waste and Emergency Response,
Washington, D.C.

	.  1986.  Superfund Public Health  Evaluation  Manual
EPA/540/1-80/060.  Office of Emergency and Remedial Response
Washington, D.C.

            March 1987.  Data Quality Objectives for Remedial
Response Activities; EPA/540/G-87/003 (OSWER  Directive
9355.0-7B).
                            II-12-2

-------
                                   0000231
       LORENTZ BARREL  & DRUM
ENGINEERING EVALUATION/COST ANALYSIS
         RECORD OF DECISION
              PART 3

       RESPONSIVENESS SUMMARY

-------
                                                 0000*0
1.0  INTRODUCTION
From  June 1,  1988  through  June 30,  1988,  the United  States
Environmental   Protection   Agency  (EPA)   sponsored   a  public
comment  period  on EPA's Draft  Engineering Evaluation  and  Cost
Analysis  (EE/CA)  for  the  shallow groundwater  contamination at
the Lorentz  Barrel  &  Drum  (LB&D) Superfund  site  in  San  Jose,
California.   Region   IX  has .  determined  that  the  EE/CA  is
substantively   equivalent   to   a  fast   track  operable   unit
feasibility  study.   The EE/CA  evaluates  four  alternatives  for
addressing shallow groundwater  contamination at the  LB&D  site.
Each  alternative  contains  a   component  for the  removal  and
treatment   of   the    contaminated   groundwater,   which   lies
approximately   40  feet  below   the   ground  surface,  and  the
disposal  of   the  treated  water.  The  purpose  of  the  public
comment  period  was to give interested  parties  the  opportunity
to comment on the EE/CA.

The  EE/CA is   a  study  that examines  various  ways  that  the
contamination problem in the shallow  aquifer can be addressed
while  a  remedy  for  the  remainder  of   the   site   is   being
developed.   The purpose  of  the  EE/CA is to  select a  remedy for
the  shallow   groundwater  contamination  that is  protective  of
human  health and  the  environment,  attains  Federal  and  state
Applicable or  Relevant  and Appropriate  Requirements  (ARARs),
and   is   cost-effective.    Because  the  full   extent of   the
contamination at the LB&D site  is not yet  known, EPA  has  chosen
to accelerate the remediation process  by addressing  the shallow
groundwater   contamination   as    a   separate  unit.    Remedial
alternatives   for  the  other contaminated media at the site  will
be examined  in  a separate  site Feasibility  Study (FS) Report,
which will be issued in late 1989.

A  Responsiveness  Summary   is   required  under   EPA  Superfund
regulations  for the  purpose of providing  both  EPA  and  the
interested  public  with  a  review  and  summary  of  community
concerns about the site .and comments on  the  EE/CA.   In addition
to    summarizing   citizen    concerns    and   questions,    the
Responsiveness  Summary  presents  EPA's   responses   to   those
concerns.

The Responsiveness Summary  for  the EE/CA  conducted  at the  LB&D
site is divided into three sections:

Background on Community Involvement and  Concerns.  This section
provides  a brief  history of community interest  in and concerns
about the LB&D site.

Overview  of   the  LB&D EE/CA.   This  section provides a  brief
history  of the  LB&D  site,  summarizes the  contents of the  Draft
EE/CA, and identifies EPAs  preferred  alternatives.
                            •  III-l-l

-------
                                                 0000231
Summary of  Comments  Received and EPA  Responses.   This section
categorizes and  summarizes written  and oral  comments  received
during  the  public comment period and  provides  EPA's responses
to these comments.

Appendix A contains an index  and  copies  of the pages  from the
public  hearing  transcript that  contain  the  specific  comments
made.
                              III-1-2

-------
2.0  BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS

The Lorentz Barrel & Drum (LB&D) site, one of  the  many sites in
the  South  San  Francisco  Bay  area  affected  by  groundwater
contamination, has  been highly visible  in the local  press and
among  citizens  living  in  the  vicinity  of  the  site since  a
contamination  problem was  identified in  1980.    Concerns  have
been  registered  with  the  California  Regional  Water  Quality
Control Board  (CRWQCB),  City, Council representatives  and other
local  agencies  on  a  regular  basis,   and  indicate  that  the
community  has  been  concerned  primarily  with  the  potential
effects  of   the  shallow  groundwater   contamination  on  its
drinking water.

Moreover,  residents  of  the area  for the most part  have  not
distinguished  between  the  shallow  and  deeper aquifers.   They
believe that contamination at any  level would  affect the safety
of  their  drinking  water supply.   Agency representatives  have
sought  to  assure  residents that  the  deeper  aquifer  supplies
residents with their  drinking  water  and that,  to date, there is
no evidence to indicate contamination in the deeper aquifers.

Between  1980,  when California  Division  of Occupational  Safety
and Health (OSHA)  informed the  California Department  of Health
Services (DHS) of  potential hazardous material problems  at the
LB&D  site, and  1987,  when technical  progress initiated  more
contact  between  the   agencies  and  community   members,   few
community  relations  activities were conducted   at  the  site.
However, investigations, sampling  efforts, and remedial actions
were  conducted  jointly by DHS,  the  CRWQCB, and the  United
States   Environmental   Protection   Agency    (EPA)   when   the
responsible party  refused  to  comply with cleanup regulations.
As a result of the multi-agency  participation  during this time,
some   community   members   raised   the   concern   that   the
responsibility for problems at  the site had been  shifted among
the agencies  so much that no  one  agency had been exercising
adequate leadership.

In 1987, community involvement  increased  significantly when DHS
released a  Preliminary Site Assessment for public review,  held
an agency  briefing to  present  a status report on  the  LB&D  site
investigations,  published  a series  of  fact sheets  and  updates
detailing  technical  progress  at   the   site,  and  drafted  a
Community  Relations  Plan (CRP)  for the site.  The CRP is based
on  interviews conducted  by  the  DHS with  community  members,
elected  officials,  and  agency  representatives.    It summarizes
past  community  concerns  and  discusses  current  and  potential
issues in the community related to the site.
                             III-2-1

-------
                                               0000231
In  June  1987,  DHS  held  a  public  meeting  to  provide  the
community with  information  regarding  the  site investigation and
Preliminary Site Assessment Report.   Over  100 community members
attended    the    meeting.     Several    attendees    expressed
dissatisfaction with  the length  of  time  that  the  agency  was
taking  to   investigate  and  cleanup  the   site.    They  also
expressed their concerns about the status of  the drinking water
in the  area  and the effects that water might  have on  fruit and
vegetable gardens  near  the vsite.  On  September 3,  1987,  DHS
held  another  public  meeting  (with   roughly  100 attendees)  to
discuss the  proposed  actions  for  drum and  sump removal.   The
public  expressed   dissatisfaction  with  the   format   of  the
meeting, claiming  that  it did not provide an  appropriate forum
for  public  involvement.   In response  to  this  concern,  DHS
hosted an informal community open house on November  18,  1987 to
answer  community  questions, especially those  related  to health
issues.

On December  1,  1987,  EPA  was designated  as  the  lead  agency
responsible  for site  investigation  and cleanup.   DHS  and  EPA
distributed a joint fact sheet in  February informing  the public
that  responsibility  for the site  had been transferred.   On
February 25,  1988, a  public  meeting was held  to  discuss  the
changes in  responsibility  for the  site  cleanup. Approximately
25 people attended this meeting.

Since  EPA  became  involved  at the  site,  it has  conducted  a
Limited Sampling  Program,   taking  soil and  water samples  from
private  fruit  gardens,  community  gardens,   a  local  grocery
store,  and nearby  Coyote Creek.   EPA prepared and distributed a
fact  sheet  in June 1988 explaining  the Engineering  Evaluation
and   Cost    Analysis    (EE/CA)   and   detailing   the   remedial
alternatives proposed  for the shallow groundwater contamination
problem.  A  public meeting,  attended by roughly 30  people,  was
held  on  June  15,  1988   to  discuss  the-  proposed   remedial
alternatives  and  to give  community  members  an  opportunity  to
comment  formally  on  these  alternatives.    Results  from  the
produce and  creek sampling  and a  presentation of opportunities
for community involvement also were presented.   A few  community
members at  the meeting stated that they were generally pleased
with  EPA's  approach to community relations  activities  at  the
site.

The following  list  summarizes concerns  raised during interviews
conducted in  DHS's preparation  of the  April 1987  CRP  and  in
community meetings.

    o    Groundwater Quality  - The primary concern  at  the LB&D
         site is the.quality  of  the  groundwater  supply  and  the
         potential  for  contamination to  move   to  the  deeper
         aquifers,  which supply  residents with a  portion  of
         their  drinking   water.    Many   residents   fear   the
         potential  short-   and long-term  health  effects  from

                             III-2-2

-------
                                                0000231
         contamination.    Some   community   members  fear   the
         possibility   of   contamination   spreading   to   food
         •products, because  some  of  the active wells  serve  food
         processing  facilities.   Other  residents  .living  near
         the  site have  expressed  concern  about the  potential
         for   contamination  to   affect   private   fruit   and
         vegetable   gardens,   as   well   as  public   gardens.
         Residents  also have .expressed  concern that  inactive
         wells  could  allow .. contaminants  to  leach  into  the
         deeper  aquifer.   Some  community  members  affiliated
         with San Jose State University are concerned  about the
         'effects   of   the  contamination  on   a   University
         recreational    area.     Drinking   water    for    the
         recreational  facility  is  provided  by  a  university
         owned  well  which  is  screened  in the  deeper  drinking
         water  aquifer below 200  feet and located within 1 mile
         of the site.

    o    Need for Frequent  Monitoring -  Some  community  members
         believe   that  frequent   groundwater  monitoring  is
         necessary to  characterize  the  extent of  contamination
         at  the  site  accurately.    These individuals  believe
         that frequent monitoring would enable EPA  to  identify
         the  spread  of the  contamination plume  in  a  timely
         manner.

    o    Duration  of Investigation  - Some  citizens  criticized
         the government  agencies  for spending  too much time and
         money  on  investigations without achieving  any tangible
         results.

    o    Inefficiency  of  Agency  Involvement  -  Prior  to  the
         increase in community  relations efforts in  1987,  some
         community  members  expressed  frustration  that  their
         concerns  regarding the  safety  of drinking water  near
         the  site  had  not been  adequately  addressed  by the
         agencies  involved.  Local  media  attention  emphasized
         the  extent  of the  problem  and  minimized  discussion
         about  agency activity.

The San  Jose Mercury News   and the  Spartan Daily,  the San  Jose
State University  newspaper, have  presented most  of the coverage
on  the  shallow groundwater contamination  at  the  LB&D  site.
Generally,  the  level   of   media  coverage  has  corresponded  to
technical  progress  made  at  the site  and the  occurrence  of
public   meetings   and  agency   briefings.    Media   coverage
concerning the  site was particularly  active during  August  1987,
as a result of  the death of Mr.  Ernest  Lorentz, owner of  LB&D,
who  had been   placed  in  custody  by  the Santa  Clara  County
District  Attorney  for . his  refusal  to  comply  with  cleanup
requirements of the site.
                             III-2-3

-------
                                                0000231
The  following  is  a  list  of  community  relations  activities
conducted to date by DHS and EPA at the LB&D Superfund site.
February 10, 1987
April 1987
June 1987
June 24, 1987
August 1987
September 3, 1987
October 1987
November 1987
November 18, 1987
December 1, 1987
DHS   presents   status    report    on   site
investigation  at  an agency  briefing.   Those
present  included  representatives  from:  EPA,
DHS,  Santa Clara  County  Health  Department,
Santa Clara County  Executive's  Office,  Santa
Clara  Valley  Water  District,  Bay Area  Air
Quality  Management  District  (BAAQMD),  San
Jose   City   Manager's   Office,   San   Jose
Attorney's   Office,   San    Jose   Planning
Department, San Jose Office  of  Environmental
Management, and the San Jose Fire Department.

DHS drafts CRP  based  on interviews  that  DHS
conducted  with  community members  and agency
representatives regarding  activities at  the
site.

DHS   distributes    the   first   fact   sheet
explaining   technical   progress   and   the
February  1987  release  of  the  Preliminary
Site Assessment Report.

DHS  holds  a  public meeting  to explain  the
Preliminary   Site  Assessment   Report   and
technical progress made at the site to date.
DHS  distributes  an  update  explaining
planned removal actions at the site.
the
DHS  holds a  public meeting  to discuss  the
proposed removal actions.

DHS  distributes an  update  on the  proposed
transportation route for the removal actions.

DHS  distributes   an   update  informing  the
public  that  EPA will  be  taking the  lead  as
the    agency    responsible    for    further
investigation and cleanup.

DHS  holds  an  open  house/public  forum  for
community members  to  question  or  comment  on
activities at the site.

EPA  becomes  the lead  agency  responsible  for
site investigation and cleanup.
                             III-2-4

-------
                                               0000231
February 1988
February 25, 1988
March 1988



May 1988



June 1988


June 15, 1988
June 30, 1988
EPA and DHS publish  a  joint fact  sheet  that
explains    the     transfer    of     agency
responsibility.    The   fact   sheet    also
explains EPA's plan  to  pave most  of the site
to prevent surface water runoff and leaching.

EPA and DHS hold a public meeting  to explain
the transfer  of lead  agency,  EPA's role  in
the   Superfund   process,   recent   paving
activities,  and  EPA's  plans  for  further
activities.

EPA distributes  letters  to  some  residents
requesting  permission   to   sample  private
fruit and vegetable gardens.

EPA   conducts   Limited  Sampling   Program
testing water  and  soil samples from private
gardens, community gardens,  and Coyote Creek.

EPA distributes a fact  sheet summarizing the
EE/CA for shallow groundwater contamination.

EPA holds  a community  meeting  to  discuss the
EE/CA  and  EPA's proposed  cleanup  solution,
and   to  accept  public  comments  on   the
proposed alternatives.

EPA conducts municipal well  sampling program
testing water from area drinking water wells.
                             III-2-5

-------
                                                  0000201
3.0  OVERVIEW OF THE LORENTZ BARREL & DRUM ENGINEERING
     EVALUATION AND COST ANALYSIS

The  contemplated  Expedited Response Action  (ERA)/Operable  Unit
is a  shallow  groundwater  collection and treatment  system.   The
objective  of  the  Engineering  Evaluation  and  Cost  Analysis
(EE/CA)  was  to  consider  various  potential   removal  action
options for this  system,  screen them,  evaluate specific options
in greater detail,  and compare those  that appear  to  offer  the
greatest  benefits.   Figure  3-1  diagrams  the  general  EE/CA
process.

In the EE/CA,  the  potential  technologies under  consideration
were   judged  on   their   ability   to  achieve  compliance  with
identified  clean-up  standards.   The  San  Jose publicly-owned
treatment works  (POTW) acceptance  criteria were  also included
in the action-specific review. The  situation-specific  nature  of
the threat was  reviewed to evaluate whether the need to protect
public  health  and  the  environment  required  more  stringent
requirements than the ARAR's.

The  .EE/CA  first  reviewed the  site  characterization.   After
formulation  of  removal  action  objectives  which  arose  from
review of  the site characterization  various  technologies  were
considered and   initially screened  against  the prescribed  ERA
evaluation  criteria.  The  screened  technologies  that  survived
were used  to  develop various  ERA  alternatives as  combinations
of technologies.  These alternatives were  evaluated,  additional
data  requirements  were identified,  and a limited  sensitivity
analysis  was  performed   as  part  of   the  comparison   of
implementation costs for the alternatives.
                             III-3-1

-------
IDENTIFY
SITE
PROBLEMS
IDENTIFY
GENERAL
RESPONSE
OBJECTIVES
IDENTIFY
TECHNOLOGIES AND
PROCESS OPTIONS
SCREEN PROCESS OPTIONS

  PUBLIC HEALTH PROTECTION
  TIMELINESS
  TECHNICAL FEASIBILITY
  INSTITUTIONAL ACCEPTABILITY


DEVELOP ALTERNATIVES
BY COMBINING
PROCESS OPTIONS



EVALUATE AND
COMPARE ALTERNATIVES
COMPLIANCE WITH ARAR'S
REASONABLE COST
ENVIRONMENTAL EFFECTS
INSTITUTIONAL ACCEPTABILITY


SELECT
TENTATIVE
ALTERNATIVE



EXAMINE
COST
SENSITIVITY
FOR TENTATIVE
ALTERNATIVE

                                                                                                       o
                                                                        FIGURE 3-1
                                                                        ENGINEERING  EVALUATION/COST
                                                                        ANALYSIS PROCESS

                                                                        LORENTZ BARREL & DRUM

-------
                                               0000231
4.0  SUMMARY OF COMMENTS RECEIVED AND THE UNITED STATES
     ENVIRONMENTAL PROTECTION AGENCY RESPONSES

4.1  COMMENTS FROM THE JUNE 15,  1988 PUBLIC MEETING

1.   Comment:

         One community member asked  whether,  after the water is
         treated,  and   assuming   that  the   flow  rates   are
         sufficiently low, evaporation could  be  considered  as a
         disposal alternative.  [10]

    United   States   Environmental   Protection   Agency   (EPA)
    Response:

         The  assumed flows  for the  Expedited Response  Action
         (ERA)/Operable Unit (100 gallons per  minute  (gpm))  are
         too  large  for  effective  use of  an  evaporation  pond.
         The required amounts of land  are  not available  in  the
         site  vicinity.   As  a  result,  evaporation ponds  were
         not  considered  viable   for   the  ERA.   During   the
         Remedial Investigation  (RI)  and  the operation  of  the
         ERA groundwater extraction  system, more  information on
         groundwater flows  and  potential pumping  rates will be
         developed.   Evaporation  ponds  will  be  considered  in
         the  Feasibility  Study  (FS)  as  a  long-term  disposal
         option.

2.   Comment:

         Another community member,  referring  to  the potentially
         large-scale  plumbing  effort  necessary  to   transport
         contaminated water  from  the wells  to  the   treatment
         plant,  asked  whether the  construction  activity could
         be  kept  to a  level that  would  be  tolerable -to  the
         neighborhood.   [11]

    EPA Response:

         The  piping  associated with  the extraction well  system
         will  be similar  to that   for  a  local  water  supply
         system.  Construction  of  the  required  pipelines will
         involve  digging   5-foot   trenches   at  appropriate
         locations.   As   with  any  public  works   construction
         project, it will be planned to minimize disturbance in
         the    residential   areas.    After   this    temporary
         disturbance, the  water  transmission  system  will   be
         hidden from view.
                             III-4-1

-------
                                              0000231

3.   Comment:

         A   representative   of   the  Silicon   Valley   Toxics
         Coalition asked  what cleanup goals EPA was  following
         in  its  evaluation  of cleanup technologies,  and  urged
         EPA  to   consider   an   approach  that  combines   the
         California  Regional  Water  Quality  Control   Board's
         (CRWQCB)  policy of  "nondegradation"  with  the -"best
         available technology"  approach.   He  also  asked  that,
         if  EPA  does  a comparative  cost  estimate  on  these
         approaches  the  community  be  allowed  to   comment  on
        'those results.   [12]

    EPA Response:

         Prior to discharge, the  groundwater will be treated to
         meet  the most  stringent  of  any  of   the  applicable
         regulations.   The  treatment  system  incorporates  the
         "best  available technology"  for  removal  of  organic
         compounds and  trace  metals.   The CRWQCB requires  that
         the treated  effluent  contain no detectable  pesticides
         or  PCBs.  The  CRWQCB discharge  limits  are  designed to
         ensure  that   the  treated   effluent   will  cause   no
         degradation of  Coyote Creek.

4.   Comment:

         That same  comraenter,  referring  to  the air  stripping/
         fume incinerator alternative, asked that  EPA use  the
         best available  technology  guidelines  to treat the  air
         emissions   from  the   fume  incinerator.    He   also
         suggested  that  the  level  of  treatment  attained  by
         incineration should exceed  the  guidelines  set  by  the
         Air Board.  [13]

    EPA Response:

         As  described  in Section 6.0  of  the Decision Summary,
         the risk  presented  by  the air emissions  from the  air
         stripper  is   the   result   of   the  volatile   organic
         hydrocarbons  (VOCs)   stripped from  the   groundwater.
         There are two  ways to remove these compounds from  the
         air:  fume  incineration; or  granular activated  carbon
         (GAC).     However,   EPA  is   concerned   about   GAC's
         effectiveness  in  removing   vinyl   chloride.   As   a
         result,    gas-fired   incineration   was    tentatively
         selected as  the Best Available Technology  for reducing
         these  emissions.   As   stated   in  Section   6.0  (and
         presented  in  more  detail  in Section 5.4.3   of   the
                             III-4-2

-------
                                               0000231
         EE/CA),  the Bay  Area Air  Quality Management  District
         (BAAQMD)  has  set a  criterion of  an allowable  cancer
         risk  of   1 x   10"6.    The  calculated  risk  from  the
         uncontrolled  emissions   (before  use   of   the   fume
         incinerator) is  2.8  x  10~6,  which   is  only  slightly
         above  the  BAAQMD   limit   of   1.0   x  10~6.    The
         destruction efficiency of  a  fume  incinerator  could
         reduce  the  cancer   risk  well  below  the   BAAQMD
         guidelines.  However since  the EE/CA was written,  the
         effectiveness  of  GAG  for  removal  of  VOC  vapors  has
         been evaluated by treatability tests  during  the  summer
         -of 1988.    Results  of these studies  indicated  that  GAC
         would effectively  remove  VOC  vapors to  below  BAAQMD
         limits,   thus   rendering  use  of  a   fume  incinerator
         unnecessary.
5.   Comment:
         The community group  representative also asked  whether
         EPA could  consider reinjection of  the water into  the
         shallow aquifer  as an alternative  to disposal.   [14]
    EPA Response:
         A discussion of the groundwater reinjection  option,  as
         it compares with  other disposal options,  is presented
         in Section  9.4 of  the  Decision  Summary.   There  are
         several  different   ways  to   reinject  the   treated
         effluents.   For example, it could be  reinjected either
         upstream or downstream of the  contaminated  zone.   Each
         different   method   has   its   own   advantages    and
         disadvantages.   Groundwater  reinjection,  as  well  as
         the effects of  extraction on the shallow  aquifer,  will
         be  evaluated  in   detail  during   the  RI/FS  process.
         Based  on  the  current  level  of   knowledge  and   cost
         considerations, it  was not selected  for  the ERA.   It
         may or may not be selected  for the long-term  remedial
         action chosen as  a result of  the RI/FS.
6.   Comment:
         One community member asked if  tests  had been conducted
         to  determine  whether   contaminated  groundwater   is
         rising to  the  surface  and evaporating off,  which,  she
         said,  would  be  potentially harmful  to  people who  use
         the track  and  tennis courts on  a  regular basis.   She
         also asked what kind of  tests  had  been conducted  west
         of the designated  plume.   [15]
                             III-4-3

-------
                                            0000231
    EPA Response:
         Soil  gas  sampling  has been  performed  on site  in  a
         westerly  direction/   and   was   used  to  define   the
         boundary of the small  western TCA plume.  (See  Figure
         5-3  of  the  Decision Summary.)   Additionally,   the
         health  risk  assessment  to  be  performed during   the
         RI/FS  process  will   evaluate  the  vapor  inhalation
         pathway for exposure to humans.   This assessment will
         model  volatilization  from  the   plume  and   diffusion
        •through the  soil  and  into  the   atmosphere.   It will
         then evaluate the predicted ambient concentrations  of
         chemicals   in  light   of   known   or   expected  vapor
         inhalation risks.   The objective of this  study is  to
         estimate risks associated  with  this potential  pathway
         before and during implementation  of remedial  actions.
         Results of this evaluation will  be made available  to
         the public during  the RI/FS.
7.   Comment:
         One  community  member  asked  which  government  body  is
         responsible   for    recovering    costs    from    those
         potentially responsible parties  who sent drums to  the
         Lorentz Barrel  & Drum  (LB&D)  site.   [16]   He  asked
         whether EPA knew  the  names  of these  companies  and
         whether;  if  they were contacted,  the  companies  had
         been willing  to  inform EPA  of  the  contents  of  the
         barrels.   [16]    He  also   asked  whether  the  tags
         attached  to  the  barrels  provided  any  information  on
         the barrels'  contents.   [17]
    EPA Response:
         Both EPA and DHS plan to cost recover.  EPA has  a  list
         of approximately 800 potential responsible parties  who
         utilized  the  LB&D  recycling plant.   EPA  is  in  the
         process  of   refining  and  prioritizing  this  list  and
         plans  to contact  companies,  in  a  phased   approach.
         There is very little  information on barrel contents on
         the tags.
8.   Comment:
         One  community   member  asked   why  the   "no-action*
         alternative cost $170,000.
                             III-4-4

-------
    EPA Response:
         The   no-action    alternative   requires    continuing
         monitoring of plume migration.  The  cost is associated
         with the installation of several monitoring wells,  and
         periodic  sampling  and  analytical  work   related   to
         long-term monitoring requirements.
9.   Comment:
         One community  member said  he feared  that test  wells
         and borings could potentially contribute  to the spread
         of aquifer contamination.   [18]
    EPA Response:
         Properly designed and constructed wells will  not cause
         cross-aquifer   contamination.    When    a    well   is
         constructed,   a  casing  is  placed  outside  the  well
         pipe.   After the  well  pipe  is  installed,  the  space
         between the  well  pipe and  the casing  is  filled  with
         grout.   The  casing  is   then  removed.   The  well  is
         screened (i.e., where the water  flows  into  the  well)
         only  10  to  20  feet  in  one of  the aquifers.   With  a
         properly   constructed    and    installed    well,    no
         cross-contamination occurs.

10. Comment:

         One   community   member,   asserting  that  neighboring
         businesses  use chemicals  similar to those found  at the
         LB&D  site,  asked  why  the  LB&D  property  has  been
         targeted for cleanup over other areas in  the  City.  He
         recommended  that  EPA  simply, pave over the  site  as  a
        . parking lot,  with  a  gravel base  and  a  top layer  of
         concrete.   [19]

    EPA Response:

         Lorentz Barrel & Drum was targeted for cleanup because
         of  noncompliance   with   hazardous  waste   management
         regulations.   There are  several Superfund sites  in the
         South  Bay,  as  well  as   sites   under   state  orders
         requiring  cleanup  actions.  If additional  information
         is  gathered  indicating   other  sources  of  potential
         chemical contamination in  areas near the  Lorentz site,
         those sources will  be investigated.  Investigations  of
         this  sort  may  result in a  site being  added  to the
         federal  or  state   Superfund  list.   Paving  over  the
         Lorentz  site  will  not   result '  in cleaning  up  the
         groundwater  contamination  plume   which,  has  migrated
                             III-4-5

-------
                                                0000231
         offsite.   The potential  threat  that  exists  to  public
         health and the  environment  would not be  alleviated  by
         this alternative.
11.  Comment:
         One  community  member  questioned  why  spent   carbon
         solids could not  be .incinerated at  a  location on  the
         LB&D site  rather  than at an  incineration  facility  in
         Texas.[20]
    EPA Response:
         It would be  very difficult and  expensive  to obtain  a
         licensed mobile hazardous waste incinerator to come  to
         the  site  to  incinerate  such  a  small  amount  of  GAG.
         Mobilization  costs  are  a  major  component  of  overall
         mobile  incineration  costs.  On  a  per-ton  basis, the
         resulting costs would be  prohibitive.
12.  Comment:
         That  same   commenter,   referring   to   the   proposed
         treatment alternatives,  asked  that  EPA  consider more
         closely:  the  pollution caused by natural  gas  during
         incineration;   the  number   of  British   thermal  units
         (Btu)   per   hour  dispersed  into  the   air   following
         incineration;  Bay Area  standards  set for pollution  in
         the  air;   and  the   possibility  of   simply  using
         evaporation  treatment  on the water.  [22]

    EPA Response:

         From  AP-42   (an . EPA   compilation   of   air   pollutant
         emission  factors),  the following  pollutant  emissions
         can be expected from a natural  gas incinerator.

                               Emissions in   Emissions in
                               lb/106 cu ft   lb/106  Btu

        Particulate               1 to 5        0.001  to 0.005
        Sulfur  dioxide            0.6           0.0006
        Nitrogen oxides          100  to  140  ' 0.1 to  0.14
        Carbon  monoxide          20  to 40      0.02 to 0.04
        VOCs -  methane            2.7  to  3      0.0027  to 0.003
             -  nonmethane        2.8  to  5.3   0.0028  to 0.0053
                             III-4-6

-------
                                                  0000231
         At a  rate  of 32,000 Btu/min,  or  1.92  x 10~6  Btu/hr,
         the  AP-42   estimated  emissions  from  the  burning  of
         natural gas are:

                                      Estimated  Emissions
                                      	in Ib/hr	

          Particulate                 0.0019  to  0.0096
          Sulfur dioxide     v        0.0012
          Nitrogen oxides              0.192  to 0.269
          Carbon monoxide              0.038  to 0.077
          VOCs - methane              0.0052  to  0.0058
               - nonmethane           0.0054  to  0.0102

              All of the  energy consumed  in  the  incinerator
              would  be  released  to   the   atmosphere,   either
              through the  flue  gas  or radiant  heat loss  from
              the incinerator and its peripherals.

              Bay area standards for  carcinogenic emissions are
              addressed in the risk  assessment  (Section  6.0  of
              the  Decision  Summary).   None  of  the  pollutant
              emissions listed  in the  table would  exceed  the
              BAAQMD limit of 15  Ib/day.

              The use of evaporation  for treated groundwater is
              addressed in  the   answer  to  question  1  in  this
              section.

              Results of  treatability  studies  have  shown  that
              the incinerator should not be  necessary.
13.  Comment:
         One  community  member   said   that  the   "No   action"
         alternative  should  be   considered  more  seriously  as
         being in the public's best interest at this time.  [22a]
    EPA Response:
         The "no action" alternative was  not selected for  this
         ERA because  it would  do nothing  to alleviate  threat
         that  the  shallow  groundwater  poses   to  the   deeper
         drinking water  aquifer.   The  "no action"  alternative
         will be considered during the  RI/FS.
14.  Comment:
         One representative  of  a community organization  wanted
         to know  the  nature of  the emissions coming out  of  the
         old incinerator  that operated  on the  site.   He  also
         wanted  to  know  the composition  of  the ash  that  is
         still  on the ground.  Finally,  he wanted  to  know  if

                             III-4-7

-------
                                                0900231
         EPA is going to  take  shallow  soil  samples downwind  of
         the  site   to   determine  if   there  is  any   metals
         contamination.  [23]
    EPA Response:
         Based on current knowledge/  EPA does not know what .the
         emissions from  the onsite  incinerator  were.  EPA  has
         already sampled ash from the incinerator.  The  samples
         contained    minimal    organic     contaminants,     at
         concentrations   far   below   EPA's   cleanup   limits.
         However, the  samples  contained high concentrations  of
         lead and zinc.  As part of  the RI, additional  samples
         of the ash will  be taken  and  analyzed to determine  its
         composition.   Shallow soil samples  will also be  taken
         around  the  incinerator's  location  and  analyzed   to
         determine  if  there  is  metals  contamination present.
         If  the   results   of  these   analyses   are  positive,
         additional samples will be  taken  (concentrically from
         the  source)   in  order  to  assure  that  the  area   of
         contamination   is    fully    defined.     A   detailed
         description  of  planned  RI   sampling   activities   is
         contained in  the  RI  Field Sampling  and Analysis Plan
         (FSAP), which was published  in June 1988.
15. Comment:
         One community  member,  referring  to the Fort  Detrick,
         Maryland  studies  on  the  epidemiological  effects  of
         airborne  bacteria,  asked  what contaminants  might  be
         released from an onsite air stripper.  [24]
    EPA Response:
         The  contaminated  groundwater  at  the  site   is   not
         expected  to  contain  any harmful  bacteria.   This,  in
         conjunction  with   adequate   equipment   maintenance,
         suggests that release of  airborne  bacteria from an air
         stripper  operation  would be  very unprobable  if  this
         alternative  had  been  chosen.    As   pointed   out  in
         Sections   9   and   10   of  the   ROD,   however,   this
         alternative  was   not   selected  by   EPA   following
         treatability studies.
16. Comment:
         That   same   commenter,   referring   to   the   ozone-
         ultraviolet  (ozone-UV)  and  GAC treatment  alternative,
         suggested that "reactive ion etching*  would be  a  more
         effective treatment technology because  this technology
         utilizes more  radicals and,  therefore, has  a  faster
                             III-4-8

-------
                                               0900231
         reaction time  and  is not dependent  on an  ultraviolet
         light source.  This  commenter also questioned  how  the
         natural  gas   and    electrical   facilities   would   be
         impacted if  the ozone/UV  treatment  alternative were
         chosen.   Specifically,   he  expressed  concern   about
         potential   power   shortages   affecting    the    local
         community and industries.  [25]
    EPA Response:
         EPA  is  not  familiar  with  the  term  "reactive  ion
         etching."   The  commentor  is  possibly  referring   to
         ozone-peroxide oxidation, which  uses  free radicals  to
         decompose  organic  compounds.   EPA  has  investigated
         ozone-UV  treatment,  which   is  known   to   be  more
         effective than ozone-peroxide  treatment.   The  treat-
         ability studies will determine whether ozone-UV  is  the
         best  technology.    If   it   is,  the  vendor  of   the
         treatment system will  be responsible  for  generating
         the ozone on site.

         Remedial activities will not  use  enough  natural  gas or
         electric energy to have any adverse affects  on  service
         to the community.
17.  Comment:
         One commenter, referring to EPA's  plan  to conduct well
         surveys, suggested  instead  that the  site be  isolated
         from the  existing  aquifers  using  a  dolomite pump  to
         isolate the clay soil from the sandy soil  —  much like
         a slurry wall. [26]
    EPA Response:
         At  the  time  the  Engineering   Evaluation   and  Cost
         Analysis (EE/CA) was  finalized,   there  was not  enough
         information  available  to  determine  whether  or  not
         slurry  walls,  or  any  other  containment  technology,
         would be effective.   As a result, containment  was not
         considered   viable   for  the  ERA.   Additionally,  the
         Superfund  Amendment  and  Reauthorization  Act  of  1986
         (SARA)  favors  the  implementation  of  remedies  that
         permanently  treat  the  contamination,  as  opposed  to
         remedies   that  merely  contain  it.    However,   a
         significant   amount   of   new   information   will   be
         generated  during  the  RI.   That   new  information  will
         allow containment technologies to be  considered during
         the FS.
                             III-4-9

-------
                                                 0000231
5.0  RESPONSES TO COMMENTS FROM SILICON VALLEY TOXICS COALITION
     LETTER OF JUNE 30. 1988

The Silicon  Valley Toxics Coalition  (SVTC)  letter of  June  30,
1988  is  reproduced  as  Exhibit  1.   The  questions  have  been
numbered  and the  responses  in this  section  relate  to  those
numbers.

1.  As part  of  the Phase I Field Investigation of  the  Remedial
    Investigation  (RI),  a  well  survey will be performed.  After
    these  wells have  been identified,  an  assessment  will  be
    made,  regarding   whether   they  could   serve   as   vertical
    conduits   between   the   shallow   and   deeper,  aquifers.
   „ Appropriate  action to prevent  cross  aquifer  contamination
    will  be taken.   Section 4.1.3.5  of  the  Final Work  Plan
    provides more details on this survey.
    The   concern   of  vertical   cross  contamination   between
    aquifers  is  addressed in  question 9  (pg  III-4-4)  of  the
    nrevimifi section.
2.

    previous section.
3.  The  Field Sampling  and Analysis  Plan  (FSAP)  for  the  RI/
    finalized   in  August   of   1988,   presents   a   detailed
    explanation  of  all sampling  and  analytical work  that  will
    be performed  during the  RI.   Sample locations are  shown on
    Figures  3-10  through 3-15  of  the FSAP.   The  monitoring
    wells  will  include  several  locations  similar  to  those
    proposed by the SVTC.

4.  The  groundwater  extraction  system  is  presented  in Section
    8.2.2 of  the  Decision Summary.  As  stated  in  that section,
    the   conceptual   design   prepared  for   the   Engineering
    Evaluation and Cost  Analysis (EE/CA)  was based  on limited
    information.  The final  design  will be based on information
    gathered during the field  investigation  of the  RI, through
    October 1988.  The final number of  wells will be determined
    at that time.

5.  Several  points  should  be  made   in   responding  to  this
    question.  First,  if  the treated water  was reinjected into
    the  same  aquifer  (i.e.,  shallow aquifer) from which  it  was
    drawn,  it would  probably not  be  used  as drinking  water.
    (Potable  water  supply  wells utilize  the  deep  aquifer.)
    However,  if  water was reinjected at  all,  it  would need to
    be  of  a  quality which  is  in compliance  with  state  and
    federal   regulations.    Bench-scale   treatability  studies
    performed  in  July/August,   1988   indicated   that  treated
    effluent   can  meet  Maximum   Contaminant  Levels  (MCLs)
    established under the Safe Drinking Water  Act,   as  well as
    DHS  drinking  water  action levels.  Further studies will be
    performed, however, to  ensure  attainment  of  these levels.
    Specifically,  an  onsite   pilot-scale  demonstration   of


                             III-5-1

-------
    the treatment  alternative recommended  in  the ROD  is  being
    planned  by  EPA  Region   IX   in  conjunction   with  EPA's
    Superfund   Innovative    Technologies    Evaluation   (SITE)
    program.   Results  will   confirm  whether   the  treatment
    technology can attain stipulated water  quality standards.

6.  As stated  in  the answer  to  question 5  (pg  III-4-3)  in the
    previous section/ the  available information  indicates  that
    reinjection of  the  treated effluent would be less reliable
    and more expensive  than  discharge  to   the  storm  sewer  and
    Coyote  Creek.   The  effluent  will be  treated to  below all
    regulatory  limits.    Each  of  the  treatment  alternatives
    investigated  in  the  EE/CA  incorporate backup  systems  to
    ensure that no  untreated  water  is accidently  discharged to
    the creek.

7.  As  stated   above/   reinjection  will be considered in  the
    RI/FS.   The  SVTC's   "Percolation   Ditch   Plan"   will  be
    considered as  one of the reinjection options.
                             III-5-2

-------
S^con
vSlev
                                       EXHIBIT  1
                                                                  0000231
vey
 Toxics
Coalition
7^0 North First Street.
Sffond Floor
San lose. California 95112
(406) 267-6707

1«
-------
                                                   0000231
Mary Masters                  -2-            30 June  1988


Comments:

I think it is necessary to keep the treated water  as  close  to  the
site as possible and not have possible contamination  in other  areas
of the valley.  The alternative to placing treated water into
Coyote Creek seems to be a means of giving the water  to people
downstream.

Attached is an idea I hope can be useful in the cleanup procedure.

XI.  Percolation ditch plan

Treating the pollution as close to the site as possible after
pumping the water out, and then letting it percolate  back into
the ground, will hopefully flush the contaminants  out of the
soil.

The positive aspects of this plan are that the water  is recycled
and kept near the site.

Drilling monitoring wells beyond the pumping  wells will aid
in keeping track of any escaping contaminants into the deep
aquifter.

The percolation ditch is "V" shaped and perforated for strength
and faster percolation, respectively.

Thanks for your consideration.

Sincerely,
Bruce Beale                            Ted Smith
                                                 \
BB»np
Enc.

-------
                             .c.
                      0000231
         ^x.
/f
/_
/
,?• 1
>\c
'• \x
e. «
6 >
. t ]9
}
                                         B
\\
    !»


>   i  'I     -  ,
    '•   I .  ,«,N X^J

 \   'A'r^   W

 \  r,^*"'
    •  \ \ ' N   VJ^
   '•""  \\ x   pt
      \\-> ^\

-------
                                               0900231
6.0  RESPONSES TO COMMENTS FROM REED CORPORATION LETTER OF
     JUNE 30. 1988

The Reed  Corporation letter of  June  30,  1988  is  reproduced  as
Exhibit 2.   The questions  are  numbered,  and  the responses  in
this section refer to those numbers.

1.  The shallow  aquifer  is not  in  use as a drinking  water  (or
    bathing)  source   at   the   current   time.    However,   the
    Superfund Public  Health Evaluation Manual, which  provides
    guidance  in  assessing  risks,  requires  the  United  States
    Environmental  Protection  Agency  (EPA)  to   consider  the
    ingestion, dermal, and inhalation pathways  anyway.   It  is
    possible that some development  may occur  in the  future,  and
    this  development could  expose  the  public  to  risks  from
    contaminated groundwater through the stated  pathways.

2.  The desired  cleanup   level  for  arsenic  for use during  the
    Expedited Response Action  (ERA) is 0.23  parts per  billion
    (ppb)  (230  parts  per  trillion (ppt))  (see Table 8-2  of  the
    Decision  Summary).    This  represents  an  estimated  cancer
    risk  of  10~4.    Since  the  treated   groundwater   will   be
    discharged  to a  surface water body  during  the  ERA,  the
    cleanup  requirements   were   derived  by  comparing   National
    Pollution Discharge Elimination System (NPDES) limits with
    the 10~4  cancer  risk  level.  The  more stringent  level was
    then selected.

3.  The levels  reported  on in  Table 2-3  of  the Engineering
    Evaluation  and   Cost   Analysis  (EE/CA)  (Table 5-3  of  the
    Decision  Summary)  are  merely  summaries  of  older data
    published by  other  contractors.   In  the  case  of  barium,
    Table  8-2 of  the Decision Summary shows  that there  is  no
    desired cleanup  level.

4.  Please see the response to  question 1  in  this section.

5.  6.4  ppb  represents   the  total   of   all   types   of  poly-
    chlorinated biphenyls  (PCBs)  (1221,  1242,  etc.)  from well
    MW-4B  in  Table 2-3 of the  EE/CA (Table 5-3 of the Decision
    Summary).  While  it is true that several of the more  highly
    chlorinated PCB  compounds  have  solubilities less  than  6.4
    ppb,  the   Handbook   of  Environmental   Data  on   Organic
    Chemicals (2nd Edition,  Van Nostrand Reinhold Company,  New
    York,   1983)   provides  the  following  solubilities  for  the
    specific PCB  compounds found at the  Lorentz Barrel  & Drum
    (LB&D) site:
                             III-6-1

-------
                                   Solubility at 24°C
         Compound                  	(PPD)	

         PCB 1221                           590
         PCS 1242                           100
         PCB 1254                            57
         PCB 1260                            80

6.  Superfund contractors  are  required in many cases  by EPA to
    use  certain  methods   to   monitor  quality   control  (QC)
    available  only   at   EPA   specified  contract   labs.    In
    determining  groundwater  quality  to  identify  contaminant
    plumes/  for  example, EPA would  not allow  the use of  2 to
    3-year-old data  taken  by private  contractors and  analyzed
    outside  the  contract  lab  program.   The  statement  in  the
    EE/CA does not indicate that the  work  was poorly  done;  it
    merely  indicates that  it  can  only  be used  to  a  certain
    extent  (i.e.,  to show the presence  of contamination)  and
    that more monitoring is required.

7.  The purpose  of  the EE/CA is  to  establish the need for the
    ERA.  It did not include  a  detailed investigation  into  the
    presence of upgradient  sources.  Such  an investigation will
    be part of the Remedial Investigation (RI).

8.  The purpose of the order of magnitude cost estimates  was to
    assess  feasibility  only.   The estimates  incorporated  the
    assumptions stated  in  the EE/CA.   The RI  will  define  the
    location of the plume in more detail.

9.. The concern  is  based  on the  current  level  of  information
    about  the  aquitard.   The  writer   seems  to  agree  in  the
    second  paragraph  of  his   letter,  that  "the  relationship
    between the  upper and   lower  aquifer is  not  well  known."
    Since this is the case,  EPA did  not want to  risk  the lower
    aquifer because of a lack of information.

10. According  to  the  Comprehensive   Environmental   Response,
    Compensation, and Liability Act  of 1980  (CERCLA) and  the
    Superfund Amendment and Reauthorization Act of 1986 (SARA),
    the source of the vinyl chloride  in the groundwater is only
    important  as  it  relates to  the   potential  to  cleanup  a
    source area and  the  potential  for  the  government to recover
    cost  from   a   potentially  responsible   party.    If   the
    groundwater is contaminated,  it  must be addressed.   The RI
    field program will  locate whatever sources remain  on site.
    With  regard  to  the  other comment  on  health  risks,  please
    see the answer to question 1 of this section.
                             III-6-2

-------
                                                 0000231
11.  The risk levels shown on  Table 5-1 of  the  EE/CA are  based
    on  a   preliminary  risk  assessment.   A more  detailed  and
    complete' risk  assessment  will  be  prepared  as  part  of  the-
    RI/Feasibility  Study   (FS).   Also/   see  the   answer   to
    question 1 of this  section.

12.  Please see the discussion in Section  8.2.2  of the Decision
    Summary.  A  significant amount of  additional  work will  be
    performed   before  the  groundwater  extraction   system   is
    finally designed.  Please  see  the  answer to  question 5  in
    Section 4.0 of this Responsiveness  Summary for  a  discussion
    of groundwater reinjection.  As  stated in the EE/CA,  these
    costs  are  based on Ebasco Services, Incorporated  experience
    and related RI/FS work in the region.

13.  Please  see  the  discussion in Section 5.4.3  of  the  EE/CA
    which   shows  that Bay Area Air Quality Management District
    (BAAQMD) requirements lead  to  the  conclusion that the fume
    incinerator is necessary.   As  stated  on  page  5-24  of  the
    EE/CA   (May, 1988),  a granular  activated carbon (GAC)  system
    for the off  gas. was not  selected  because  of  some  concern
    that   it   might  ' not   be   effective   in  absorbing   vinyl
    chloride.   However,  as  a  result  of  treatability  studies
    undertaken in  July/August 1988,  the  capability of a  vapor
    phase   GAC  to  cost-effectively remove  vinyl  chloride  has
    been   established.    In   view   of  this   finding,  fume
    incineration  is  no  longer considered  to  be  a  necessary
    component  of the  vapor control  system.

14.  The LB&D   site  has   been  proposed for  inclusion  on  the
    National  Priorities   List  (NPL).   The  question  of  the
    relative risk of LB&D as  compared  with other  Silicon  Valley
    sites  was  addressed when the site  was  proposed  in  1984.
                             III-6-3

-------
               EXHIBIT 2
                                                 OOOOJ»31
REED CORPORATION
                        Kiivliuiiiiiimlul Kii


                                             2140 ShuUuck Avenue. Suite 504
                                                 Berkeley. CA 94704
                                                   (4 IS) 524-0450
•r,,,,o in lonn                                     Mobile (415) SCO-U25
June jo, 1980                                    Telecopy (4J5) 232-3796

U.S.E.P.A.
215 Fremont Street  (t-1-3)              CONFIRMING COPY
San Francisco, CA 94105                 ORIGINAL SENT BY
                                        TELECOPY ON 6/30/88
ATTN: Ms. Gail Louis
      Community Relations Coordinator

Subject: Comments on the EE/CA for the Lorentz Superfund Site

Dear Ms. Louis:
                                             
-------
                                                0000331
Ms. Gail Louis
June 30, 1988
page 2

not  appear to  be realistic  concerns with  respect  to public
health.

Specific concerns of  regarding other contaminants are as  follows:

     o Arsenic  -  while  the Department of Health Service  (DOHS)
               has an action level  of 2.0 parts per trillion in
               the California  Administrative  Code  Title  22
               drinking  water   standards   (64435   Table  2)
               show that the maximum contaminant level  (MCL)  is
               0.05 ppro or  50,000 parts  per  trillion.   The MCL
               would  appear to  be a  more  realistic  goal  for
               discharge to non-potable water  such as would  occur
               in the Lorentz matter.

     o Barium - The reported levels of 160 ppb of barium  from the
               C112MH111  reports appear to be above the  solubility
               of barium in this ground water.  Equilibrium  would
               be approximately  100  ppb or less in the  presence
               of sulfates.  Additionally, the Title 22  standard
               for barium is 1000 ppb, which would appear to be a
               more realistic human health concern level.

     o Vinyl Chloride -  The EBASCO report states that the MCL for
               Vinyl  Chloride is  1 ppb;  USEPA MCL  is  2 ppb
               effective 12/31/88. In any case the concerns over
               actual health hazards from the reported, levels of
               vinyl  chloride  appear to be overstated due to the
               fact  that   the  ground  water  is not  used for
               drinking  and the  highly volatile nature of  vinyl
               chloride which would  cause  it  to  be  readily
               out-gassed during any normal usage of the  water.

     o PCB - The level of 6.4 ppb of PCB does  not appear  in  Table
               2-3 of the EBASCO report.  The  highest level  shown
               is 4.0 ppb.   These results appear to  be higher
               than '-would  normally  be  anticipated  for  PCB
               solubility in water.

-------
Ms. Gail Louis
June 30, 1988
page 3


p. 2-24 2.4.2 Analytical Data Review

Monitoring Well Analyses

I take  strong  exception to the  statements  that "The quality of
the ground water  analyses  from investigations prior to the  CH2M
Hill  study  is  poorly  known,  because sampling  activities  were
minimally documented.   Original lab reports for the work done by
Associated Laboratories and Brown and Caldwell are  not  available
at this time,  and the results were transcribed from handwritten
notes  and faded  photocopies.1*   I personally transmitted via
facsimile copies  of  information  requested  by  Ms.  Robin Scott of
EBASCO in January 1988.  At that time I  informed ner tnat  copies
of all lab data sheets were available at  the DOHS or RHQCB  files,
and that I assumed that she had ready access to this information.
X never heard back from Ms. Scott,  and therefore assumed that she
got what she wanted.   Additionally,  all appropriate  documentation
of sampling was submitted  to the RWQCB  and all information was
available from the files of the LorentT  consultants with minimal
additional effort from EBASCO.

p.  2-27   2.4.3  Extent  of  Shallow  Aquifer  Ground  Water
                     Contamination

Reference is  made to  Figures 2-6a and  2-6e  show  contamination
VOC starting substantially to the south  of the Lprentz  site  near
the area of the bus  (private) maintenance facility (see Figures
2-6d  and  2-6e  specifically).    No   mention of upgradient
contamination  is  made,  why is that  and  to what source is  this
likely  due to?

p. 2-33 2.4.4 Contaminant Extent Data Caps


It is  indicated that the extent  of the plume must  be determined
before a final treatment system design can  be  completed.  How can
a meaningful cost estimate be developed  without knowledge  of the
extent of the plume?  How does one assume the  length of  the plume
(i.e.  the distance of  pipelines to  return to the  site)  or the
number of  wells without this information,  and why hasn't  this
information been  determined in the  work  completed  over the  last
two years by DOHS and EPA?

-------
                                                  0000231
Ms. Gail Louis
June 30, 1988
page 4


p. 2-33 2.5.2 Potential Impacts

The  premise  that the  contaminated plume will  reach  potable
drinking water  is weak  and quite  implausible  given  the  local
hydrogeological conditions.  To  assume  that  there is sufficient
VOC  material present in  the  ground  water where the  highest
concentration of total VOCs is less  that 4 ppm (MW-4 TMA 7/86) is
frankly  ludicrous.   There  are  dozens of  sites in  the  Silicon
Valley where 50 times this  levels of VOC materials are present in
the  ground  water.   Additionally, in   the  40  years  of  Lorentz
operation there has never been any indication of any potential or
actual deep aquifer contamination.

p. 5-3 5.2  Alternative A:  Mo  Action (Periodic Ground  Hater
                    Monitoring)

Reference is made to Table 5-1  regarding relative risk, however,
closer review of Table 5-1  would  indicate that essentially all of
the risk is   related to Vinyl  Chloride which most likely  being
produced naturally  by biological  processes in  the soil  from
materials released to  the  ground water by someone  in  the  a'rea.
Vinyl Chloride accounts for 7.24*10-2 of 7.83*10-2  (or 92 percent
of the  estimated  risk).    Clearly,  this  conditions dramatically
overstates the  relative health  risk  of the non-potable ground
water in this area.

I  strongly disagree  with the assumptions made  in this section.
First, no  single  sample was utilized  for  this comparison.   It
appears  to  make little  sense to add up  the highest  data  from
unrelated samples (spatial  and time  variations in all samples).

Second, the assumption that the very deep drinking water would be
contaminated to the same degree as the shallow  aquifer is silly.
Clearly, by  simple dispersion dilution of the water would  occur
and substantial adsorption of these  materials would occur during
the vertical movement of these  materials in the unsaturated zone
between the shallow and deep aquifer.

Third, because  the water has nearly 2000  ppm  of TDS  it is not
logical  that one  would  ever drink any  of this  shallow ground
water or that anyone would ever drink the estimate 51,100 liters
per life time used in this  estimate  (nearly 14,000 gallons).

-------
                                               0000231
Ms. Gail Louis
June 30, 1988
page 5

Fourth, no existing public health risks  have been identified or •
pathway quantified even.though a  comment  is made  to this effect
in the text.

p. 5-5 5.3 Alternative B:  Ground Water  Removal;  GAC Treatment
                              Disposal to  Storm Sewer


Zt is  indicated that no  pumping  tests have  been  completed and
that this  would be required prior to final design.   Why hasn't
this been done  to date? Our analysis indicates that 50 gpm or so
is likely to  be the  maximum flow available from  the site with a
reasonable number of wells (less  than 10).  How was the number of
80 wells derived without the pump test data?

It does not appear that the data  support the requirement for the
80 wells shown on Figure 5-1 nor  does hydrogeological or chemical
data support the relative spacing of the wells with the exception
of the approximate  location of the  plume  in  the  northerly
direction  (recall  that  EBASCO previously  stated  that the extent
of the plume  was unknown).   It is  very unlikely  that the wells
will produce anything near to the five gpm assumed.

On p.  4-9 the concept of  ground water reinjection was discarded;
however, closer review may indeed indicate that this is the only
effective alternative from the hydrogeolgical  standpoint.

Several costs in Table 5-3 appear to be quite high.  The cost of
well  installation per foot is  approximately $125  (based  on
summing  $55,500+126,000+107,000+163,000  and  dividing by  80*45
feet • 3,600 feet).  No well diameter information is given in the
report.  Assuming that four inch  wells were constructed a cost pf
one half of this amount would be  more typical.

Additionally, the  cost  of $252,000  for  80 wells results  in a
cost of over  $3,000  for a pump and installation.   My experience
indicates that  $2,000 is  more typical.    No  cost is  shown for
electrical  installation and no information is presented  on the
cost per foot of pipe trench.

The  parameters  for the  design of  the  GAC units  appear to  be
within  standard ranges.

-------