United States
Environmental Protection
Agency
Office of
Emergency and
Remedial Response
EPA/ROO/R10-88/013
March 1988
Superfund
Record of Decision
Gould, OR

-------

    ROD/R10-88/013
    d Site, OR
   st Remedial Action
16.  ABSTRACT (continued)


and lead oxide.   VOCs were discovered in ground water,  but will  be addressed  in  a  future
operable unit.

   The selected remedial action for the soils unit at the site include:   excavation  of
all battery casing fragments and matte from the Gould property and adjacent contaminated
areas; a phased design program to determine the amount of material that  can be recycled,
and to minimize the amount of material that must be RCRA landfilled;  separation  of
battery casing fragments;  recycling of all applicable components;  offsite disposal of
nonrecyclable material failing the EP Toxicity test;  onsite disposal  of  nonhazardous,
nonrecyclable components;  excavation, fixation/stabilization,  and  onsite disposal  of
remaining contaminated soil, sediments, and matte with soil capping and  revegetation;
isolation of surface water runoff to East Doane Lake by site regrading;  and a monitoring
program to determine changes in ground water contamination over  time  and to ensure that
remediation does not adversely impact air quality.  Additional ground and surface  water
studies will be performed  to determine the need for remediation  of the media.  The
estimated capital cost of  this remedy is $3,491,603,  assuming  a  "worst case"  scenario
where little of, the material is recyclable, with present worth O&M of $17,073,581.

-------
 REPORT DOCUMENTATION
         PAGE
                        1. REPORT NO.
EPA/ROD/R10-88/013
                                                                        3. Recipient's Accession No.
            ""RECORD OF DECISION
   Gould Site,  OR
    •tst Remedial Action
                                                                        5. Rtpoi
                                                                        8. Performing Organization Rept. No.
 9. Performing Organization Nam* and Address
 12. Sponsoring Organization Nama and Address
   U.S. Environmental Protection Agency
   401 M Street,  S.W.
   Washington,  D.C.   20460
                                      10. Project/Task/Work Unit No.


                                      11. Contract(C) or Grant(G) No.

                                      (C)

                                      (G)

                                      13. Type of Report & Period Covered


                                           800/000
                                                                        14.
 19. Supplementary Notes
 10. Abstract (Limit: 200 words)
      The Gould site is located in a heavily industrial  area of Portland, Oregon,
   approximately 1.3 miles  southeast of St.  John's Bridge.   The site  is contained  in a
   60-acre study area consisting of the Gould property and  outlying areas containing
   battery casings and other  residues from site operations.  The area 'is sparsely  populated
   and lies on  the left bank  floodplain of. the Willamette River.  Doane Lake, a small pond,
   is located adjacent to the site.  The Gould site  is mostly paved with asphalt,
            , onsite flora  and fauna are limited.  Between  1949 and 1981, various  owners
            the site as a secondary lead smelting facility  specializing in lead-acid
   battery recycling, lead-smelting and refining, zinc alloying and casting, cable
   sweating,  and lead oxide production.  Operations  ceased  in August  1981; and by  the
   summer of  1982 most of the structures,  facilities, and equipment were removed.   Remedial
   investigation and production records estimate that 86,900 tons of  battery casings,
   11,800 tons  of matte, and  6,570,000 gallons of acid were disposed  of at the site.
   Approximately 2% of the  total volume of battery casings  is located in surface piles, the
   remaining  98% is used as fill material,  and is in direct contact with ground water.  The
   primary contaminants of  concern affecting the soil and sediments are lead

   (See Attached Sheet)
 17. Document Analysis  a. Descriptors
   Record of Decision
   Gould Site,  OR
   First Remedial Action
   Contaminated Media: sediments, soil
   Key Contaminants: lead
    b. Identifiers/Open-Ended Terms
   c. COSATI Field/Group
 18.
      tbility Statement
                                                         19. Security Class (This Report)
                                                               None
                                                         20. Security Class (This Page)
                                                               None
                                                 21. No. of Pages
                                                        91
                                                 22. Price
(See ANSI-Z39.18)
                                         See Instructions on Reverie
                                                OPTIONAL FORM 272 (4-77)
                                                (Formerly NTIS-35)
                                                Department of Commerce

-------
      RECORD OF DECISION
REMEDIAL ALTERNATIVE SELECTION
    INTERIM  REMEDIAL ACTION
          SOILS UNIT
          GOULD SITE
       PORTLAND, OREGON

-------
                             RECORD OF DECISION

                       REHEDIAL ALTERNATIVE SELECTION
Site

    Gould site - Portland, Oregon.


Purpose

    This decision document presents the selected Interim remedial action
for the site, developed In accordance with the Comprehensive Environmental
Response, Compensation, and Liability Act of 1980 (CERCLA), as amended by
the Superfund Amendments and Reauthorlzatlon Act of 1986 (SARA), and
consistent with (where not precluded by SARA) the Nat-onal Contingency
Plan (NCP, 40 CFR Part 300).  The State of Oregon Department of
Environmental Quality concurs with the selected remedy.


Basis for Decision

    The decision is based upon the administrative record for the site.
This record Includes, but Is not limited to, the following documents'. -

8   Final  Remedial  Investigation Report for the Gould site, Portland,
   . Oregon (November 1987)

?   Final  Feasibility Study Report for the Gould Site, Final Report
    (February 1988)

0   Decision Summary of Remedial Alternative Selection (attached)

0   Responsiveness  Summary (attached as Appendix B)

8   A complete list of documents contained In the Administrative Record  Is
    Included as Appendix C


Description

    This record of decision addresses the soils unit at the Gould site.
By doing so the remedy focuses on removing the principal source of lead
contamination to the environment.  The remedy also Includes further study
to determine whether additional remedial measures are required for
groundwater and surface water at the site.

-------
     This remedial action is designed to:

     0    remove lead from the battery casings through recycling;

     0    reduce the mobility of lead in the contaminated soil, sediment an8|
          matte at the site through fixation;

          continue monitoring of surface water and groundwater at the site
          while additional study of contamination In these areas Is done; and

     0    monitor ambient air around the site to ensure that remedial actions
          are carried out in a manner that 1s protective of public health.

     The extent to which lead and other components of the battery casings can
be recycled will depend on the results of design work under this remedy.  The
results of the design studies will  be used to determine the recyclablllty of
the battery casings and the protective measures to be employed during
remediation.  A phased approach, described In the selected remedy, will be
employed in the design work.

     It is EPA's Intent in selecting this remedy to treat all of the battery
cas1ngs at the site and at the same time minimize the amount of material that
rr.it be sent to a RCRA landfill.  Should the results of the design phase show
that these goals are not compatible, an additional public comment period will
be established and this Record of Decision may be modified.  At such time, EPA
would present for comment additional options for dealing with the treated
materials.

     Treatment and removal of casings and treatment of soils will remove lead
and eliminate potential for exposure due to direct contact and Ingestlon.
Immobilization of lead in soils, sediment and matte will reduce migration o^	
lead as a potential source of further contamination to groundwater and surface
water at the site.

     Institutional  controls will be Implemented, during and after
remediation.  The purpose of these controls will be to assure that the
remedial action will  protect public health and the environment during Its
execution, and to ensure a similar level of protection after the remedial
actions have been Implemented and prior to a final decision at this site.

-------
Declaration
    Consistent with CERCLA, as amended by SARA, and the NCP, it is
determined that the selected remedy as described above is protective of
human health and the environment, attains Federal and State- requirements
which are applicable or relevant and appropriate, and is cost-effective.
This remedy satisfies the preference expressed in SARA for treatment that
reduces toxicity, mobility, and volume.  Finally, it is determined that
this remedy utilizes permanent solutions and alternative treatment
technologies to the maximum extent practicable.
Date
—Regional  Administrator
  Environmental  Protection  Agenty
  EPA  -  Region  10               \

-------
       DECISION SUMMARY
REMEDIAL ALTERNATIVE SELECTION
    INTERIM  REMEDIAL ACTION
          SOILS UNIT
          GOULD SITE
       PORTLAND, OREGON

-------
                           TABLE OF CONTENTS


                                                                 Page

 I    SITE DESCRIPTION AND BACKGROUND                               ,

          Site Location and Description
          Site Features


 II        ENFORCEMENT SUMMARY                                      «'


 III       COMMUNITY RELATIONS SUMMARY                              9


 IV        NATURE AND EXTENT OF PROBLEM                            „

          Contaminants Evaluated
          Extent of Contamination
          Treatability Studies
          Potential Transport and Need for Additional Study
          Endangerment Assessment                               . .
V         ALTERNATIVES EVALUATION

          Summary of Alternatives and Evaluation Criteria
          Screening of Alternatives
          Alternative 2C Evaluation
          Alternative IOC Evaluation
          Alternative 21 Evaluation


VI        SELECTED REMEDIAL ALTERNATIVE

          Description of the Selected Remedy
          Design Studies
          Monitoring
          Institutional Controls
          Additional Study
          Performance Standards
          Statutory Determinations
APPENDICES

     A.   APPLICABLE AND APPROPRIATE REQUIREMENTS

     B.   RESPONSIVENESS SUMMARY

     C.   INDEX TO ADMINISTRATIVE RECORD

     D.   STATE CONCURRENCE
                                                                  26

-------
                                 LIST OF TABLES
Pace,
Table 1 '
Table 2
Table 3
Table 4
Table 5


Figure 1
Figure 2
Figure 3
Figure 4

Figure 5
Figure 6
Figure 7
Figure 8
Figure 9
Enforcement History
Battery Casing Quantities and Locations
Estimated Battery Component Quantities
Estimated Secondary Source Volumes
Cost Screening Summary
LIST OF FIGURES

General Vicinity Map
Study Area Location Map
Locations of Battery Casings and Mo:*:e
Lead Contamination In Surface Soils

Lead Contamination in Fill Aquifer
Lead Contamination in Upper Alluvial Aquifer
Lead Contamination in Lower Alluvial Aquifer
Summary of Exposure Calculations
Estimated Areas to be Remediated Under Selected
7
11
12
15
29

Paqe
2
3
13
14
\
17
18,
19
24
Remedy 43
Note: Sources for Figures are Remedial Investigation and Feasibility Study
Reports.

-------
 I.  SITE DESCRIPTION

 Site Location and Description

    The Gould  site  is  located  In the Doane Lake area of Portland between
 N.H. St. Helens Road and N.W.  Front Avenue, about 1.3 miles southeast of
 St. John's Bridge.  The Gould  site Includes the property presently owned
 by  Gould, along with areas outside the property boundary where battery
 casings and other residues from operations on the Gould site were placed.
 Because of the potential for dispersion of contaminants In water, the site
 also Includes  the 1963 boundaries of Doane Lake.  As shown on Figure 1
 (General Vicinity Map), the Willamette River lies about 1,000 feet to the
 northeast and  flows northwest, parallel to Front Avenue.  The area Is
 heavily Industrialized.  The Gould site Is only a portion of the 60-acre
 study area, shown on Figure 2  (Study Area Location Map).

    The study  area  is roughly  bounded on the southwest by N.H. St. Helens
 Road, on the northeast by N.W. Front Avenue, on the southeast by 61st
 Street, and on the  west and northwest by the Burlington Northern railroad
 right-of-way.  Industrial properties adjacent to the Gould site that lie
 wholly or partly within the study area Include American Steel Industries,
 Inc.; ESCO Corporation; Rhone-Poulenc Inc.; Northwest Equipment Rentals,
 Inc. (leased from Rhone-Poulenc); Schnltzer Investment Corporation, and
 Liquid Air Corporation (leased from Schnltzer).

    Available  aerial photographs taken since 1936, and topographic mapping
 as early as 1884. indicate that the study area now occupied by"Gould
 property and adjacent industries was formed by gradual and Intermittent
man made filling of a fairly large body of shallow water known as Doane
 Lake.

    On the current Gould site, a secondary lead smelting facility was
 completed and went  into operation In 1949 under the ownership of Morris P.
Kirk and Sons  (Kirk & Sons), a subsidiary of NL Industries, Inc.  Facility
operations consisted of lead-acid battery recycling, lead smelting and
 refining,  zinc alloying and casting, cable sweating (removal of lead
 sheathing from copper cable), and (after 1965) lead oxide production.  NL
 Industries, Inc.  purchased the property from the subsidiary In 1971. The
property was sold by NL Industries to Gould, Inc. In January 1979.  In
October of the same year, Gould stopped receiving lead-acid batteries, but
continued to process a substantial existing stockpile of batteries.  In
January 1980,  lead refining operations were discontinued.  Battery
breaking operations ceased on April 1, 1981. lead oxide production ceased
 In May 1981. and the facility closed entirely In August 1981.  By the
summer of 1982, most of the structures, facilities, and equipment had been
removed.

    In 1981 EPA and DEQ began  Investigating the site, and the site was
placed on the Superfund National Priorities list In 1983.  In 1985 NL
Industries and Gould Inc. signed an Order on Consent with EPA under which
NL and Gould conducted a Remedial Investigation (RI) and Feasibility Study
(FS) at the site.  The final RI report was submitted to EPA In November
1987 and the final FS report was submitted In February 1988.

-------
                o.s
            SCALE IN MILES
o
I
Figure 1


General Vicinity Me

-------
                                                                                                     SCHNITZER
                                                                                                 INVESTMENT CORP.
                                                                                                                  AMERICAN STEEL INDUSTRIES.
                                                                                                                            INC.
                                                                                         ,\ RHONE-POULENC  INC.
X
                                                             X.
NOTE: THE STUDY AHCA BOUNDARY AS SHOWN DOES NOT INCLUDE

      THE WILLAMETTE RIVER SAMPLING AREA OR THE BACKGROUND

      SURFACE SOU SAMPLING AREAS SOUTH OF ST. HELENS ROAD.
                                       ••• • •••
                                                                                                       STUDY AREA BOUNDARY
                                                                  1OO
                                                                                  400
fiom • lapoeopklc *u»«v •>•» «•••• Mmj IS. <•••.
Dr D.E. U»« S A»
f»t Dan*** ft Mo«f*
                                                                                      rtiT
          SCALE I*  ZOO*
Figure 2
 Study Area Location
           Map

-------
 Site  Features

    In general,  the Gould site  is located in an area which Is less densely
 populated than surrounding areas to the northeast and southeast.  The   :e
 is  located  in census tract 43,  a large tract which parallels the
 Willamette  River for approximately 7 miles.  A few widely scattered
 private residences and rental units are located In a narrow zone between
 N.W.  St. Helens  Road and Forest Park, south and west of the study area.
 The 1985 census  data for all of Census Track 43 shows a total of 425
 dwelling units,  380 of which are single family homes.  The site Is located
 about 13 miles from the city center of downtown Portland, with a
 population  of over 400,000.

    The existing land use in the study area and vicinity Is primarily
 Industrial, and  generally follows the City of Portland zoning code
 designations.  No significant changes in the area's existing land use
 patterns are presently planned.

    Airflow is usually northwesterly in the Portland area In spring and
 summer, and southeasterly in fall and winter.  The winter season 1s marked
 by relatively mild temperatures, cloudy skies and rain with southeasterly
 surface winds predominating.  Summer produces mild temperatures.
 northwesterly winds and little precipitation.  Wind direction at the Gould
 site  Is strongly Influenced by the topographic features of the hillside
 southwest of the site.   Resulting wind directions tend to be
 northwest-southeast along the Willamette River.   Precipitation In the
 Portland area 1s mostly rain.  Average rainfall Is 37.39 Inches.  Monthly
 averages vary from 0.46 Inches in July to 6.41 Inches In December.

    The Gould site is located on the left bank floodplaln of the
 Willamette River, approximately 7 miles upstream from the confluence of
.the Willamette River and the Columbia River.  The floodplaln of the
 Willamette River occupies the lowest portions of the Willamette Valley,
 which is a broad downwarp between the Cascade and Coast Ranges of
 northwest Oregon and southwest Washington.  In addition to man-made fill,
 the site is underlain by a few to several  tens of feet of alluvial
 deposits,  which  in turn overlie the lava flows of the Columbia River
 Basalt.  The site is situated on the northeast flank of the Portland Hills
 anticline, where the anticline dips beneath the young sediments that fill
 the Portland Basin.  Groundwater flow Is generally In a northerly
 direction.

    The Gould site occupies a flat area between the Willamette River on
 the east and the forested slopes of the Tualatin Mountains to the west.
 The site Is mostly paved with asphalt and 1s basically devoid of natural
 vegetation.   The vegetation that exists Is mostly brush, small trees, and
 blackberries along the property fencellne.

    Occurrence of animals at the site Is low, since the habitat necessary
 to support on-slte fauna Is limited.  Common animal species that have been
 seen on-s1te Include ground squirrels that are resident on the pond, and
bird species that feed In the brushy, weedy areas around the site
perimeter.  Some cattails grow 1n East Ooane Lake.

-------
    It is doubtful that any fish reside in either West or East Doane Lake
since natural water sources and discharges are limited.  Also, high levels
of contamination have resulted in water quality levels that will  not
support higher aquatic life forms.   Some amphibians have been noted in and
around the lake.  Numerous fish species reside in or migrate through the
lower reach of the Willamette River in the vicinity of the site.

-------
 II.

    On the current Gould site, a secondary lead smelting facility was
 completed and went into operation 1n 1949 under the ownership of Morris P.>
 Kirk and Sons (Kirk & Sons), a subsidiary of NL Industries, Inc.  Facility!
 operations consisted of lead-acid battery recycling, lead smelting and
 refining, zinc alloying and casting, cable sweating (removal of lead
 sheathing from copper cable), and (after 1965) lead oxide production.

    Available records for the period between February 1960 and January
 1970 indicate that Kirk & Sons received 14 complaints and/or violations
 regarding emissions from the facility.   A January 29, 1970 report by the
 Columbia-Willamette Air Pollution Authority expressed concern over levels
 of lead In the vicinity of Morris P. Kirk, and the potential threat to
 health caused by continued plant operations.

    NL Industries. Inc. purchased the property from the subsidiary In
 1971.  Three violations for excessive emissions were recorded In 1972.
 Lead was detected in Doane Lake In 1973, and NL Industries was dted for
 improper wastewater discharge into the  lake.   On July 30, 1973, NL
 Industries curtailed all smelting operations, but the lead oxide still,
 cable sweater, and refining kettles continued to ooerate.  Available
 records Indicate that the facility operated In corr.il lance with DEQ
 guidelines during 1974 through 1976.

    The property was sold by NL Industries to Gould, Inc. 1n January
 1979.  In October of the same year, Gould stopped receiving lead-add
 batteries, but continued to process a substantial existing stockpile of
 batteries.  In January 1980, lead refining operations were discontinued.
 Battery breaking operations ceased on April 1, 1981, lead oxide produc-
 tion ceased in May 1981, and the facility closed entirely In August 1981.
 By the summer of 1982, most of the structures, facilities, and equipment
 had been removed.

    In 1981  EPA and DEQ began Investigations of the site.  The site was
 placed on the Superfund National  Priorities List In 1983.  In 1985 an
order on consent was signed with NL and Gould which Involved the
 performance of an RI/FS at the site.

    More recently, Special  Notice Letters have been sent to NL and Gould
under the authority of Section 122 of CERCLA.  Information requests under
Section 104(e) have also been sent to Industries In the vicinity of the
 site requesting Information on hazardous contaminants and contamination at
 those facilities.  The Information received from these companies will be
 used In designing the additional  groundwater and surface water studies
described In the selected remedy.

    A historical sequence of enforcement related events Is presented 1n
Table 1.

-------
                                   TABLE 1

                             ENFORCEMENT HISTORY
July  1966



Dec.  1966


1967


Dec.  1968


March 1969


Nov.  1969


Jan.  1970
March-June 1970


1971



March 16, 1972


March 1973



April 1973
July 1973
The Air Quality Control 
-------
Oct.  1976        Violations for wastewater discharge by NL Industries
                 corrected.

Aug.  15, 1978    East Doane Lake sampled by DEQ; test results Indicated 0.1
                 and 0.3 ppm lead.

Jan.  1979        Gould Inc. purchased the facility from NL Industries.

Nov.  8, 1979     Preliminary modeling analysis by DEQ suggested Gould may be
                 violating the new ambient lead standard for the lead
                 trailer loading operation.

March 5, 1981    DEQ issued notice to Gould of discharge violations and
                 creating offensive conditions.

April 1981        DEQ obtained two yard-cleaning samples; EP leachate test
                 results indicated 280 and 4,200 ppm lead.

July  1981         DEQ sent notice to Gould of Intent to assess dv1l
                 penalties.

Aug.  1981         Gould facility ceased all operations.

Oct.  30, 1981    DEQ requested that Gould .undertake a comprehensive cleanup
                 program.

July  22, 1982    DEQ decided no cleanup of the Gould site was warranted b*i
                 the groundwater data received to date.

Sept. 24,  1982   DEQ requested that Gould submit a schedule for removing the
                 battery cases from the site and for sampling soil  and pond
                 sediments on the site.

Oct.  26, 1982    Gould responded to DEQ request. Indicating that they would
                 level  and cover the battery casings.

Dec.  1982         DEQ rejected Gould's plan for covering the battery casings.

Feb.  1983         Gould Inc. submitted a letter to EPA objecting to EPA's
                 Hazard Ranking System (HRS) score for the site (see
                 Appendix D).  The score had been used by EPA to propose
                 Inclusion of the site on the NPL.  In particular,  the Gould
                 letter objected to the methods used to determine airborne
                 contaminant hazards at the site.

Aug.  1985         Gould Inc. and NL Industries signed Section 106, Adminis-
                 tration Order on Consent for the Remedial Investigation/
                 Feasibility Study (RI/FS) of the facility.

April 1986       Work. Plan for RI/FS by Dames & Moore was approved and site
                 Investigations began.

Nov.  1987         Final  RI report submitted to EPA and OEQ.

Feb., 1988       Final  FS report submitted to EPA and DEQ.


                                      8

-------
III.  COMMUNITY RELATIONS SUMMARY


    In 1983, Oregon congressional representative Les AuCoin corresponded
with DEQ about the site, and DEO held a meeting with city, county, and
state agency officials to present information about environmental concerns
in the area and to solicit comments.  Representative AuCoin specifically
requested that DEQ assure him that site cleanup would completely remove
potential contaminants.

    A Community Relations plan was prepared for this site In 1985 based on
research and Interviews with interested community members and officials.
The Community Relations Plan identified several Issues of concern to the
affected community and local officials, Including:

    1.   Groundwater Pollution.   People were concerned about ground- water
         contamination in the area and how It might affect future growth
         of the area.

         EPA responsed to this concern by including extensive groundwater testing
         in the RI.

    2.   Airborne Lead.  Several  agency officials "ndlcated that high
         levels of lead emissions were a primary concern and that high
         levels of airborne lead  could adversely affect the health of
         nearby workers.   Exposure to lead at the approximately 10 houses
         in  the hills  above the  site was thought unlikely, but necessary
         to  investigate.

         EPA has included air monitoring in the RI.

    3.   Effects  on Workers' Health.   Individuals were concerned about
         exposure through incidental  Ingestlon of ground water obtained
         for Industrial use and  exposure to airborne lead.

         EPA has included exposure scenarios for workers in the risk assessment
         for the site.

    4.   Cleanup  Schedule.   Staff from Representative AuCoin1s office and
         a  representative from the Oregon State Public Interest Research
         Group expressed dissatisfaction that cleanup measures had not
         been Implemented earlier.

         EPA has attempted to evaluate the site and make a remedial decision in
         an expeditious manner. By focusing on the soils unit, a decision will be
         made now.

    5.   Future Development of the Doane Lake Area.  The media and local
         officials expressed concern about how the current pollution would
         affect or restrict future uses of the land.

         Future use restrictions are expected to be minimized by removing or
         treating as much of the lead at the site as possible.

    6.    Disposal  of Dredged Materials from the River.  A representative
         from the Port of Portland Indicated the Port's concern about
         disposing of  dredged materials from the Willamette River that
         might be found to contain contaminants from the site.

-------
         The RI included an evaluation of sediment around the outfall from East
         Doane Lake.

    7.   Environmental Investigation of Doane  Lake Area.  A representative
         from  the Association of Oregon Industries and  representatives of
         elected officials indicated concern that OEQ's environmental
         Investigation In the Doane Lake area  could decrease future
         Industrial development and jobs In the community.

         No reports of decreased industrial development as a result of these
         investigations has been received by EPA.

    8.   Disposal of Battery Casings.  An aide to Representative AuColn's
         office expressed dissatisfaction that battery  casings had not
         been  removed from the site.  Representatives from the Portland
         Department of Public Works cautioned  that any  plan to dispose of
         waste materials at St.  John's'Landfl11 would be unpopular.

         EPA intends to recycle as much of the battery casing components as is
       .  feasible.

    Throughout the course of the RI/FS, additional  updates were provided
to the public during the investigation and reporting phases.  A proposed
plan and notice of public hearing was published In the Oregon Ian on
February 8, 1988.  The public comment period for the site was from
February 8 through March 18.   Two public meetings were  held to discuss the
results of these studies and EPA's proposed plan: the first on February
18, 1988 and the second on March 10, 1988.  At both meetings, there  was
clear community support for thorough cleanup of the site and contaminated
groundwater.  The results of these meetings will be discussed further  In
the Responsiveness Summary (Appendix B).
IV. NATURE AND EXTENT OF PROBLEM


Contaminants Evaluated

    During the scoping of the RI/FS, the emphasis at this site was on
metals contamination from the battery recycling operations.  Of primary
Importance was the presence of lead In each of the media.  Although
groundwater In this area also has organic chemical contamination, that
contamination was not evaluated In these studies.  As part of .the selected
remedy, additional work 1s proposed for the groundwater which will take
Into account organic chemical contamination.  The purpose of this
additional work will be to determine what, If any, remediation actions are
required for the surface water and groundwater at the site.

    Contaminated media at the Gould site that were Investigated Include
battery casings, matte, surface soils, subsurface soils, lake sediments,
surface water, and groundwater.
                                     10

-------
 Extent of Contamination

     Battery Casings and Matte.  The lead smelter on the Gould property
 operated between  1949 and  1973.  During this period, a dally production of
 approximately 35  to 40 tons of lead has been reported.  An average of
 1,500  batteries were processed dally.  As a result of these production
 records and the RI Investigation, a total of 86,900 tons of battery
 casings and 6,570,000 gallons of acid were estimated to be disposed of at
 the  site.

     In addition to acid and battery casings, a third waste product called
 matte  was produced by the  smelting operation.  Matte disposal Is estimated
 at 11,800 tons. This material was reportedly used as fill only on the
 Gould  site, just  to the northeast of the facility.

     Much of the battery casing fragments produced during this period
 (1949-1973) were  disposed off site on the Rhone-Poulenc property.    The
 quantity of battery casing materials disposed was calculated using test
 pits and a fill thickness contour map.  Table 2 summarizes the locations
 and  estimated quantities of battery casings.  Figure 3 shows the locations
 of the battery casings and matte within the study area.

                                   TABLE 2

                  BATTERY CASINGS QUANTITIES AND LOCATIONS

 Gould Property (1949-1973)     41,300 cu yds    44,500 tons
               (post-1973)     11.100 cu yds    12",000 tons
               Surface Piles    1.700 cu yds     1,600 tons

 Rhone-Poulenc Property         26.700 cu yds    28.200 tons
              Totals           80,800 cu yds    86,900 tons

     The batteries consist of hard rubber, ebonite, plastic casings,
 metallic lead, and lead oxides.  Lead concentrations (mostly lead oxide)
 ranged from 7,600 mg/kg (0.76 percent) to 190,000 mg/kg (19 percent).  All
 of the battery casing samples had EP Toxlclty results for lead above the
 regulatory limit  (EP Toxlclty limit « 5.0 mg/1).  These values ranged from
 21 mg/1 to 220 mg/1.   There was no apparent correlation between total lead
 concentration and EP Toxlclty leachate lead concentration.  The EP
 Toxlclty results for arsenic, chromium, and cadmium were below detection
 limits.

    About 21 of the total volume of battery casings Is located In surface
 piles on the Gould property, the remaining 981 Is part of the fill on the
 Gould and Rhone-Poulenc properties.  These subsurface casings are In
 direct contact with groundwater underneath the site.  The characteristics
of the surface piles of casings differ from the subsurface piles.  The
 surface piles contain a higher percentage of plastic and metallic lead
 relative to subsurface casings on the Gould property'or from the
 Rhone-Poulenc property, which contain a higher percentage of rock and
 slag.  The metallic lead, plastic, ebonite and lead oxide components of
 these casings are potentially recyclable.  The estimated fractions of the
 various components In the surface and subsurface casings are shown 1n
 Table 3.
                                     11

-------
                                   TABLE 3
                    ESTIMATED BATTERY COMPONENT QUANTITIES
Rhone-Poulenc &
Gould Subsurface
Ebonite
Plastic
Metallic Lead
Lead Oxide/Mud
Rock/Slag
Other
Moisture
Subtotal
In-Situ Density
Ibs/cu. ft.
68.00
46.56
297.46
238.37
105.56
74.28
62.30
79.80
In-SItu Volume
cu. yds.
69,008
4.070
117
2,703
1,938
1,264
0
79,100
Tons
63.349
2.558
469
8.700
2,762
1.268
6.113
85,218
Per Cent
(weight)'
74.3
3.0
0.6
10.2
3.2
1.5
7.2

Gould Surface

Ebonite
Plastic
Metallic Lead
Lead Oxide/Mud
Rock/Slag
Other
Moisture
   Subtotal

Total
 65.81
 45.06
 287.88
 230.69
102.16
 71.89
 62.30
 70.07

79.60
  899
  595
     6
    52
  148
    0
	0
 1.700

80,800
  799
  362
    24
   161
  204
   0
	H
 1.609

86,827
50.0
22.5
 1.5
10.0
12.7
 - 0
 3.7
    The matte materials consist of metallic sulflde chunks primarily
containing Iron and lead.  Lead concentrations In the matte samples ranged
from 6.4 percent to 11 percent.  All of the samples had EP Toxlclty
results for lead above the regulatory limit of 5.0 mg/1.    Low
concentrations of arsenic and cadmium were detected 1n the EP Toxlclty
leachates.  These concentrations were within the regulatory limits (5.0
mg/1 and 1.0 mg/1, respectively).

Surface Soils. Subsurface Soils, and Sediments

    In addition to battery casings and matte, large quantities of soil at
the site are contaminated with lead and can serve as secondary sources for
lead transport.  The quantities of surface soil, subsurface soil, and
sediment considered to be secondary sources were estimated by using total
lead and EP Toxlclty data.

    Figure 4 shows the areas of surface soil that were Identified as
secondary source areas using the above total lead criteria.  The quantity
of surface soil on the Gould property considered a secondary source Is
approximately 2.400 cu yds.   The quantity on the Rhone-Poulenc property Is
approximately 970 cu yds.  These quantities are based on a 3,000 ppm lead
level  In soils.  Criteria for surface soils In the selected remedy are
based on a lower lead level  and as a result actual volumes determined In
design may be higher than these estimates.
                                     12

-------
                                                                       AMEMCAN STEEL MDUS1MES.
                                                                             INC.
              AUTO 000V nu. MTO


  A9MOUMATI OLMT MMAM HAITI »*1 WTI
• MATT! Tt«f MT 1OCATMM*
                                                                       Location of Battery
                                                                         Casings & Matte

-------
                                                           PENNWALT CORP.
                                                             SCHNITZER
                                                          INVESTMENT CORP.
                                            C"A   \             '
                                            ;f*\  \   OOULOINC. +*$•'
                                            ^ .Una*8*  ;*
                                                                         MN STEEL INDUSTTUES.
                                                                            INC.
                                   D   \
                                              ••-10
                             •x.
  % RHONE-fOULENC INC.
  V\
                                                                                  a
LIMMO
                                                       -i\
     •UMAC! tAMPil LOCATION
     COMCMTIIATMNI Of IIAO «»f M)
 •M  OuriWATI
MIT
               86.
                                                                  Figure 4
                                                                   Lead Contamination
                                                                      in Surface*

-------
    The volumes of subsurface soils estimated to be secondary sources are
as follows:

    1.   One foot of soil below the entire area of the battery casing/
         matte excavations. This would amount to 4,300 cu yds from the
         area on Rhone-Poulenc property and 5,000 cu yds from the area on
         the Gould property; and,

    2.   One foot of soil from the sides of the excavations. Assuming
         average excavation depths of 20-feet on the Rhone-Poulenc pro-
         perty and 25-feet on the Gould property, and an excavation
         side-slope ratio of 2:1, this would amount to approximately 2,170
         cu yds from the Rhone-Poulenc property and 2,180 cu yds from the
         Gould property.

    Sediment samples collected from East Doane Lake contained total lead
concentrations ranging from 160 mg/kg (parts per million) to 12,000
mg/kg.  The estimated quantity of secondary source material In East Doane
Lake Is 5,500 cubic yards.  West Doane Lake sediments are not considered
secondary sources.

    Sediments collected In the Willamette River during August 1986 a.nd
February 1987 had generally low metals concentrations.  Total lead con-
centrations ranged from 26 to 56 mg/kg.  Other metals concentrations
Included total arsenic at 5.7 to 6.2 mg/kg, total chromium at 9 to 26
mg/kg, and total  zinc at 72 to 82 mg/kg.  Cadmium and hexavale«it chro--
m1um concentrations were near or below the detection limits.  Like the
West Doane Lake sediments, Willamette River sediments are not considered
secondary sources.  The total  quantity of soil considered secondary source
material is summarized In Table 4.      '      -

                                   TABLE 4

                     ESTIMATED SECONDARY SOURCE VOLUMES
         TYPE AND LOCATION                      QUANTITY (cu yds)
         Surface Soil
         Gould property
         Rhone-Poulenc property                 	
                         Surface Soil Total     3,370        3.370

         Subsurface Soil
         Gould property                    5.000
         Bottom Sides                      2.180
                  Sub-total                7.180

         Rhone-Poulejic property            4,300
         Bottom Sides                      2.170
                  Sub-total                6,470
                     Subsurface Soil Total 13.650            13.650

         Sediment
         East Doane Lake       5.500        5.500

                         Secondary Source Total              22,520

                                     15

-------
     Surface Hater.  Surface water in the study area consists of two
 remnants of Doane Lake.  The two remnants are referred to as East Doane
 Lake and West Doane Lake (see Figure 2).

     Direct precipitation and precipitation runoff from surrounding
 properties are the only sources of surface water to the lake remnants.
 Groundwater recharge also contributes water to the remnants.  Their
 surface elevation rises and falls seasonally with rainfall and presumable
 groundwater recharge.  However, there Is no simple relationship apparent
 between precipitation and lake level.

     East Doane Lake discharges via a drain pipe to the north beneath N.W.
 Front Street; the discharge enters the Willamette River approximately 200
 feet east of the railroad bridge.  There Is no known surface discharge
 from the West Doane Lake remnant.

    Surface water In East Doane Lake exceeds the lead drinking water
 standard of 0.05 mg/1.  Surface water concentrations were as high as 0.28
 mg/1.  Levels In West Doane Lake were below the standard.

    Ground Water.  The site hydrostratlgraphy Includes unconsol1 dated fill
 and alluvial deposits overlying basalt flows.  The fill consists largely
 of sands and gravels, silts, and an abundance of slag, bricks, metal
 parts, and battery casings.  The alluvial deposits consist predominantly
 of clays, silts and sands with the silt content generally Increasing with
 depth.  The basalt flow beneath the fill and alluvial deposits 1s thought
 to be fractured and weathered.  Ground water occurs In the fractured and
 weathered portions of the basalts.                            "

    The fill and alluvial deposits form an Interconnected, heterogen-
 eous, and anisotropic aquifer.:  The fill.and alluvial water-bearing zones
 are believed to be generally unconflned; however, due to the layering,
 heterogeneity,  and anisotropy there may be locally confined conditions
 within the aquifers.

    Four water-bearing units are Identified beneath the site.  These units
 are the fill, the upper alluvial, the lower alluvial, and the basalt
 water-bearing units.  In the upper aquifers there Is a significant
 component of downward flow, although flow at the basalt-alluvial Interface
 appears to be from the basalt to the alluvial aquifer.

    Groundwater Contaminant Delineation.  Figures 5,6 and 7 show the
 extent of lead contamination In the fill and alluvial aquifers.  The
 contours show where dissolved lead concentrations exceed the MCL of 0.05
 mg/1  as well as the MCLG of 0.02 mg/1.  The sulfate plume that has
 resulted from disposal of battery add Is also shown.

    The relationship between dissolved metals, sulfate concentrations and
 pH 1s similar In both the fill and alluvial aquifers.  Both show elevated
 dissolved metals and sulfate levels In association with lower pH values.

    In the-upper alluvium,  the lead plume has migrated at least as far
 north as well 100. shown in Figure 6.  Increased dissolved metal
 concentrations appear to be the result of the lower pH which Increases  the
 solubility of metals, thus carrying high levels of lead as the "plume"
migrates.  Total lead migration from the site Is estimated to be from 0.3
 to 0.6 Ib/yr.
                                     16

-------
                                                                  PEMHW ALT CORP
                                                                                       UOUD MR COHP.
                                                                     SCHNIZTER
                                                                  INVESTMENT CORP.
                                      ELEVATED
                                      SULFATE _
                                       .AREA
                                                                                 AMERICAN STEEL MMJSTRCS.
                                                                                           INC.
                                                           RHONE-POULENC
PROPERTY LINE
RAH.ROAO SPUR
STRUCTURE
REMNANT LAKE. DASHED WHERE APPROXIMATE
WELL LOCATION AND NAME
BORING LOCATION AND NAME
TEST PIT .LOCATION AND NAME
STAFF GAUGE
APPROXIMATE SULFATE PLUME BOUNDARY
 (AVERAGE OISSOLVEO SULFATE CONCENTRATION > SO PPM)

AVERAGE OISSOLVEO LEAD CONCENTRATION >0.02 PPM
                                                                                X
AVERAGE OISSOLVEO LEAD
CONCENTRATION 20.03 PPM
                                   100
                                          •••too*
Flgun 5
 Lead Contamination
     in Fill Aquifer

-------
                      ELEVATED
                       SULFATE
                        AREA
   SCHNIZTER
INVESTMENT CORP
                                                                                                                    X
STRUCTURE
REMNANT LAKE. DASHED WHERE APPROXIMATE
WELL LOCATION AND NAME
•ORMG LOCATION AND NAME
TEST PIT LOCATION AND NAME
STAFF GAUGE
APPftOXMATE SULFATE PLUME BOUMOARV
(AVERAGE DISSOLVED SULFAT* CONCENTRATION i 90 PPM)
AVERAGE DISSOLVED LEAD CONCENTRATION 20.02 PPM
AVERAGE DISSOLVED LEAD
CONCENTRATION jO.OS PPM
                                          r-j
                              Figure 6
                               Lead Contamination in
                               Upper Allu\^BtAquifer

-------
V —
"±
^•<
^'
	 ^
/'
riU-
f'l ' , "
NW FRONT AVI •
A
	 iK2*t — ::"" —
PCNNWALT CORP.
X

                                                                      SCHNIZTER
                                                                   INVESTMENT CORP.
                                                                                        UQUD AIR COUP.

                           ELEVATED
                           SULFATE
                             AREA fr-
                                                                                  AMERICAN STEEL MMISTOES
                                                                                            INC.
STRUCTURE
REMNANT LAKE. DASHED WHERE APPROXIMATE
WELL LOCATION AND NAME
•ORMO LOCATION AND NAME
TEST PIT LOCATION AND NAME
STAFF GAUGE
APPROXMATE SULFATE PLUME BOUNDARY
(AVERAGE DISSOLVED SULFATE CONCENTRATION > SO PPM)

AVERAGE DISSOLVED LEAD CONCENTRATION 20.02 PPM


                              0.
                                                                                 X
AVERAGE OISSOLVEO LEAD .
CONCENTRATION 20.08 PPM
                                   100
                                          IN MO*
Flgurt 7

 Lead Contamination in
 Lower Alluvial Aquifer

-------
Treatability Studies on Casings and Contaminated Soils

    As part of  the  Feasibility  Study, several engineering studies were
performed  to determine whether  the SARA preference for treatment could be
met.  A bench-scale soil stabilization study was performed by Weston
Services,  Inc.  Weston used several different reagents to determine the
applicability of the soil stabilization technique to site soils and lake
sediments.  The results  showed  that admixtures of.Portland cement, cement
kiln dust, and  lime kiln dust with the soil and sediment at specific
Increments Improved the  consistency and structural stability of the soils
and sediments,  and  also  reduced the leachablllty of the contaminated
materials  to levels generally below hazardous waste designation levels.

    Three  battery casing separation tests were performed on site
materials.  One test was performed on equipment manufactured by MA
Industries, Inc.  and the other two on equipment manufactured by
Poly-Cycle Industries, Inc.  To conduct each test, representative material
was excavated from  the site and shipped to  locations where equipment
manufactured by the two  companies Is in use.  In the case of MA
Industries, the test was run on equipment operated by Ace Battery Company
of Indianapolis, Indiana.  The  tests of Poly-Cycle equipment were run at
the Poly-Cycle  plant in  Jacksonville, Texas.  The studies show that much
of the battery  casing material  Is potentially recyclable, however,
additional design work will be  required to modify the pilot facilities
used in the treatability studies to actual conditions at the site.
Reasonable physical separation of the plastic and ebonite components with
some equipment modifications appears to be possible, although sthe degree
of metallic lead contamination of ebonite may be h'igh even after
separation; additional design work will be required to modify the process
to treat the ebonite stream in order for It to pass the EP Toxlclty test.

    During the evaluation of alternatives,  similar tests were run
independently by researchers working on materials from the United Scrap
Lead Superfund  site near Troy, Ohio.  Researchers there performed
bench-scale tests using various solutions and mechanical cleaning steps to
determine the amenability of lead to be removed from the ebonite
material.   The results of this  test are generally favorable Indicating
that the ebonite stream can be cleaned.  However, the researchers have
concluded that more work Is required before the bench-scale results could
be applied to any field-scale unit.  This Is a typical requirement for any
bench scale testing.

Contaminant Transport and Need for Additional Study

    Two types of lead sources exist at the Gould site.  The major source
Includes debris remaining from earlier lead recovery operations, Including
battery casings and parts and the smelter matte.  Secondary sources which
may be significant  Include surface, sediment, and subsurface soils near
the Industrial  sources.  These materials may act as a source for lead In
ground water, surface water or air after the primary (Industrial) sources
have been removed or stabilized.

    Groundwater Transport.  The most Important chemical change encountered
In the groundwater system on (and near) the site Is pH change.  At the
primary sources, the pH  Is generally quite  low (pH <5) because of the
sulfurlc add from the scrapped batteries.  As pH Increases, the
solubility of lead  In water decreases, accompanied by the precipitation of
lead oxides and hydroxides.
                                     20

-------
     The  amount  of  lead  that  can  be  dissolved  in  ground water  is a function
 of  temperature,  pH,  other  dissolved species present, amount of available
 lead and contact time.   Assuming temperatures  to be constant, all these
 factors  are  significant  with  regard to  lead solubility In ground water  in
 the study area.   Based on  these  factors,  an estimated migration rate of
 0.3 to 0.6 Ib/yr was  derived  during the  RI.

     Airborne  Transport.  The  potential for airborne contamination comes
 from the surface piles of  casings and contaminated surface soils at the
 facility.  During  the RI,  the  highest dally ambient lead values observed
 were 5.20 ug/m3.   This  is  above  the NAAQS of  1.5  ug/m3.  The  highest
 monthly  average  airborne lead  concentrations observed were 1.56 ug/m3
 and 0.94 ug/m3.   The  highest  quarterly average airborne lead
 concentration was  0.56 ug/m3.  These results  indicate that dry weather
 and disturbance  of site  mater  dls may cause airborne transport of lead
 containing materials.

     Need for Additional  Study  The  exact nature of lead migration has not
 yet been well characterized.   For that reason,' additional Investigations
 of  the groundwater and surface water unit at this site are recommended  In
 the  selected remedy.  The  proposed  additional  work will Involve expanding
 the  area for groundwater and  surface water monitoring and Including
 organic  chemical contamination in the evaluation of groundwater quality.


 Endflpf^erment Assessment

     Human  Health Effects.  An  endangerment assessment was perf6rmed to
 evaluate  the potential for human health and environmental exposure risks
 associated with  the no-action  alternative as well as the remedial action
 alternatives.  The primary contaminants Included  In the assessment are
 lead, along with arsenic cadmium, chromium and zinc.  Arsenic Is treated
 as  a carcinoge/i  for both inhalation and Ingestion routes, while cadmium Is
 treated  as a carcinogen for only the Inhalation route.  As part of the
 endangerment assessment, a screening analysis for these other contaminants
 was  performed based on the values found at the site and the relative
 toxlclty of these  compounds compared to lead.   As a result of this
 screening, risks from lead exposure were found to dominate risks from
 exposure  to the other chemicals.   Lead was selected as the Indicator
 compound for assessing risk and evaluating the various remedial
 alternatives.

     Three potential critical pathways were Identified, Including airborne
 exposure from on-slte fugitive dust sources. Incidental oral   Ingestion of
 contaminants, and  dermal contact as well as Incidental Ingestion of lead
 from surface water In East Doane Lake.  No exposure from drinking water
 was  Included.  Groundwater contamination will  be evaluated further In the
 additional work proposed under the  selected remedy.

     Inorganic lead may be absorbed  by Inhalation or by Ingestion.
Absorption by either route contributes In an additive fashion to the total
 body burden.   Among adults. Inhalation Is the more efficient of the two
mechanisms.  The fraction of Inhaled lead absorbed from the respiratory
 tract Is  approximately 40 percent,  while the fraction of Ingested lead
absorbed  from the gastrointestinal  tract Is approximately 10 percent.
These rates may be higher in children and are of particular relevance In
assessing exposures In this sensitive subpopulatlon.
                                     21

-------
     Lead  is highly persistent  in the environment and is bioaccumulatlve.
 When  lead  is first absorbed, it enters the bloodstream and is dispersed
 unevenly  in the body among blood, soft tissue, and bone.   Approximately
 90 percent of the lead in blood is bound to the red blood cells.  The
 overall half-life of lead in blood has been calculated to be 36 + 5 days.
 Lead  Is excreted from the blood into the urine.  Lead In soft tllsue has a
 calculated mean half-life slightly less than that In the blood and Is
 excreted by alimentary tract secretions, hair, sweat, and nails.  Most
 lead  absorbed Into the human body Is deposited in the bone.   Lead 1n the
 bone  is calculated to have a half-life of approximately 10,000 days (27
 years).

    The toxicology of lead has been extensively reviewed.   Alterations In
 the hematopoetic (blood forming) and central  nervous systems are the
 primary toxic effects caused by exposures to lead.   Cognitive and
 behavioral deficits are the focus of much current research on relatively
 low levels of lead exposure.

    The Centers for Disease Control  (CDC) has determined that a blood lead
 level in children of 25 ug/dl or above indicates excessive lead absorption
 and constitutes grounds for medical  Intervention.  That determination Is
 based on the occurrence of enzymatic abnormalities  In the red blood cells
 at blood lead levels above 25 ug/dl  and by the finding of neurologic
 dysfunction in children at blood lead levels  between 35 and 50 ug/dl.
 Further, the CDC defines  childhood lead poisoning at a blood lead level of
 25 ug/dl in association with an erythrocyte protoporphyrln (EP.) level- of
 35 ug/dl or above (CDC 1985).  In its draft toxlcologlcal  profile for
 lead, CDC has also cautioned that concentrations greater-than 500-1000 ppm
 could lead to elevated blood lead levels In children Inhaling or
 swallowing dirt.   Recent  findings of cognitive deficits associated with  '
 lower blood lead concentrations may result In a review of the adequacy of
 the existing CDC threshold level.   EPA has Issued a revised maximum
 contaminant level  goal  (MCLG) of 20 ug/llter  lead.   The current MCL of 50
 ug/liter is used to derive an acceptable Intake chronic (AIC) risk
 criterion for Ingestlon of lead.

    Based on discussions  with EPA and following the noncardnogenlc risk
 evaluation procedures of  the Superfund Public Health Evaluation Manual .
Acceptable Intake:   Chronic (AIC)  values were used  to assess the
 significance for human health of potential  Inhalation and Ingestlon
exposures to lead calculated for the Gould Inc. site.  AIC criteria are
designed to represent an  Intake for a contaminant that would be acceptable
on a  long-term continuing basis without producing adverse health effects.
Separate AIC values for inhalation and Ingestlon exposures are derived by
EPA from the National Ambient Air Quality Standard  (NAAQS) for lead (1.5
ug/m3 quarterly) and the  drinking water standard for lead (0.05.mg/1),
respectively.   Each AIC Is calculated as the  environmental criterion
concentration times contact rate divided by adult body weight.  Assuming
20 m3/day of air breathed, 2 liters/day of water Ingested, and an adult
body weight (bw) of 70 kg, the derived AIC values are 0.0004 mg/kg-bw/day
for Inhalation and 0.0014 mg/kg-bw/day for Ingestlon.  For each calculated
exposure dose (In mg/kg-bw/day) In this endangerment assessment, risk Is
represented by a hazard Index (HI) number equal to the calculated dose
divided by the appropriate AIC value.  Thus,  a hazard Index greater than
 1.00 represents a calculated dose greater than the  AIC criterion value,  ^
given the exposure model  assumptions and the environmental concentrations!
used  In the model.
                                     22

-------
     Figure 8  provides a visual  summary of the results of the exposure
 calculations  for  the No-Action  Alternative.  Inhalation and ingestion
 exposures for each  scenarios are scaled appropriately In comparison to AIC
 values.  As Figure  8 shows, the high dose cases for Ingestion of soils
 Indicate extremely  high Intakes of lead.  These Intakes result from
 calculations  assuming contact with the lead oxide—almost pure lead—In
 the  battery casing  waste piles.  Even If more realistic assumptions than
 continuous dally  contact with the waste piles are made, the results of any
 contact with  and  ingestion of contaminants from the battery casing piles
 would be significant in comparison to either baseline exposures or
 Ingestion AIC values.  The high dose Ingestion calculations are not
 considered to be  a  basis for evaluation of potential health Impacts from
 the  site (they are  excessively  conservative); however, they clearly
 demonstrate the potential significance of any contact with the existing
 source materials  on site.

     For on-slte workers (adults only), total lead Intake Increases to
 about 2.5 times baseline intake, with Inhalation exposures Increasing by a
 greater percentage  than ingestion exposures but still  accounting for less
 than 10 percent of  total exposures.  Both Inhalation and Ingestion mean
 dose exposures are  lower than AICs.  Off-site residential total lead
 Intake Increases  only marginally for adults or children (about 14
 percent).  Only inhalation exposures are Included In this scenario, with
 the  ambient air lead concentration assumed to be constant at 0.33 ug/m^,
 or 22 percent of  the NAAQS value of 1.5 ug/m3.   In the on-slte
 residential  base  case scenario, adult lead Intake Increases almost   • .
 fivefold and children's lead intakes by a factor of more than )l.  Both
 Inhalation and ingestion exposures are substantially Increased In all age
 intervals; all hazard indices for children and adults are greater than
 1.00, with a maximum of 11.2 for inhalation and 34.2 for Ingestion among
 children's age intervals.

     Environmental  effects.  It  is doubtful that any fish reside In either
 East.or West Doane  Lake.  During field sampling activities, numerous
 aquatic insects and frogs were observed In the West Doane Lake.  None were
 observed during concurrent sampling In the East Doane Lake, although
 mallards are reported to be resident there.   Numerous fish species reside
 In or migrate through the lower reach of the Willamette River 1n the
 vicinity of the site.  These Include migrant Chinook and Coho salmon, and
 Steelhead and American shad.  Resident species Include largemouth and
 smallmouth bass,  crapple, blueglll, walleye, northern squawflsh, catfish,
 mountain whlteflsh, carp, sucker, peamouth,  and chlselmouth (Oregon
 Department of Fish & Wildlife 1972. 1986).

    The Willamette River In the site reach flows through a highly
 Industrialized area that receives a variety of point- and non-point source
 pollutants.   Dissolved lead values upstream of the area of the discharges
 from the Gould site have exceeded the chronic aquatic life standard of 1.3
 ug/1  In some 45 percent of the samples from the past decade (USGS 1975 -
 1984 data).   Total recoverable lead values have been still higher.  Levels
of lead have trended downward with no values greater than 2 ug/1 In the
 last three years of this period.
                                     23

-------
                                              10 ACTION ALTERATIVE
                                          IKBEMEWAL AVEBAGE DAILT DOSE
Figure 8                                      81 EXPOSURE SCEJABIO
Summary of Exposure Calculations    
-------
    Estimates of the quantity of surface water overflow from the East
Doane remnant indicate a maximum value of 7,800,000. gallons per year.
Using a range of discharge-values, dilution calculations were made to
estimate the distance downstream of the outfall at which the concentration
in a plume within the Willamette River will reach background levels.
Using the above estimates, the plume where lead values measurably exceed
background could be several thousand feet long and up to 100 feet wide.

    Few recent data are available on fish populations In the vicinity of
the Gould discharges; however it Is likely that these populations reflect
the stresses of the existing habitat.  Of primary economic and
recreational concern are effects on anadromous (migratory) salmonlds.
Both Juveniles and adults migrate past the site on their way to and from
upstream spawning areas.  Because of the shallowness of the beach adjacent
to the discharges, adults would not be expected to move through
concentrated areas of the plume and should suffer little Impact from their
limited exposures.  Thus, it is likely that a significant percentage of
outmlgrating Juvenile salmonlds will pass through the plume.  Expected
residency in the plume would be on the order of minutes If actively
migrating or hours if passively drifting down current.  Exposures of this
duration may cause some minor stress to respiration and metabolism but
would not be expected to result In significant numbers of deaths unless a
fish were somehow trapped for an extended period In a region with very
high concentrations.   The EPA criterion for short-term exposure (1 hour)
Is 0.034 mg/1.
                                     25

-------
V.  ALTERNATIVES EVALUATION

Summary of Alternatives and Evaluation Criteria

    This section summarizes the detailed evaluation of the final  candidate*
remedial action alternatives.  First, alternatives are subject to a
screening for compliance with the protectiveness and ARAR criteria.  An
additional  screening of cost effectiveness Is then done to ensure the the
selected remedy is a cost effective one.  Those that pass the screening
are then evaluated against all nine criteria and an alternative Is
selected that best addresses the combination of criteria.  This
alternative is considered to represent treatment to the maximum extent
practicable.

    The Final  Candidate Alternatives, Identified briefly, are:

    Alternative 1  - No-Action Alternative (presented to provide a baseline
for evaluating the other alternatives).

    Alternative 2A - Removal and Disposal of Surface Piles of Battery
    Casings;  Lime  Application to Contaminated Soils.

    Alternative 28 - Removal and Disposal of Surface Piles of Battery
    Casings;  Capping of Contaminated Surface Soils; Regradlng of the Site
    and Isolation  of East Doane Lake.

    Alternative 2C - Excavation and Separation of'Surface Pile's of Battery
    Casings,  and Subsequent Off-Site Management of Casings; Lime
    Treatment; Capping of Contaminated Surface Soils; Treatment of Surface
    Water;  and Regrading and Revegetation of the Site.

    Alternative 8A - Removal and Disposal of Surface Piles of Battery
    Casings  and Sediments of East Doane  Lake; Capping of Contaminated
    Surface  Soils; Treatment of Surface  Water; and Regradlng and
    Revegetation of the-Site.

    Alternative 86 - Excavation and Separation of Surface Piles of Battery
    Casing  Components, and Subsequent Off-Site Management of Casings;
    Capping  of Contaminated Surface Soils; Treatment of Surface Water; and
    Regrading  and  Revegetation of the Site.

    Alternative 10A - Excavation and Separation of all Battery Casings,
    and Subsequent Recycle of Some Casing Components; On-Slte Incineration
    of Non-recyclable Components; Fixation or Stabilization of Surface
    Soils,  Subsurface Soils, Sediments,  and Matte; Treatment of Surface
    Hater.

    Alternative 10B - Excavation and Separation of all Battery Casings,
    and Subsequent Recycle of Some Casing Components-; Incineration of
    Non-recyclable Battery Casing Components; L1me Treatment and On-Slte
    Placement  of Sediments; Treatment of Surface Hater.
                                     26

-------
    Alternative  IOC - Excavation and Separation of all Battery Casings,
    and Subsequent Recycle of Some Casing Components; Off-Site Disposal of
    Non-recyclable Components that Fail EP Toxicity;.Fixation or
    Stabilization of Surface Soils, Subsurface Soils, Sediments, and
    Matte; Additional Study of Groundwater and Surfacewater Quality.

    Alternative 21 - Excavation of Battery Casing Components and Permanent
    Disposal in an On-Site RCRA Landfill; Fixation or Stabilization of
    Surface Soils, Subsurface Soils, Sediments, and Matte; Treatment of
    Surface Water.

    Alternative 25 - Permanent Disposal In an On-Site RCRA Landfill of all
    Site Contaminated Materials, including Battery Casing Components.
    Surface Soils, Subsurface Soils, Sediments, and Matte; Treatment of
    Surface Water.
Evaluation Criteria

    Nine factors will be considered in evaluating the Final Candidate
Alternatives:

    0    Long-term effectiveness and permanence;
    0    Reduction in toxicity*, mobility or volume;
         Short-term effectiveness;
    0    Implementabi1ity;                                     •«
         Cost;
         Overall protection of human health and the environment;
    0    Compliance with applicable or relevant and appropriate
         requirements (ARARs) that are shown in Appendix A;
    "    State acceptance;  and
    0    Community acceptance.
                                     27

-------
     The  process  begins  by  applying  the  protectiveness and ARAR factors  to
 each of  the  candidate alternatives'.  Alternatives  that do not satisfy
 these requirements  will  be  s.creened out.   Then  a cost effectiveness       *
 screening  is  done  to ensure  that each of  the alternatives would be a cost!
 effective  solution  to the  problems  at the  site.  Finally, for the
 remaining  alternatives  which  have passed  these  screening steps, all of  the
 factors  are  weighed in  determining  the  best overall solution to be applied
 at  this  site.
Screening of Alternatives

Alternatives  1. 2A. 2B. 8A. and 86

    These alternatives fail the protectiveness and ARAR screens for the
following reasons:

    0    The  alternatives rely heavily on Institutional controls and
         monitoring for the protection of public health and the
         envi ronment.

    0    Uncontrolled wastes would be left In place on site.

    e    Extensive continued migration of site contaminants Into the
         groundwater aquifers will occur.

    0    The  alternatives fail to meet ARARs.               .  N

Alternative 2C

    Although  Alternative 2C has many of the same disadvantages of  the
above alternatives, it involves some treatment of the remaining
contaminated  material at the site and Is therefore considered more
protective than the above alternatives.  The alternative fails the EP Tox
ARAR, and a waiver in this instance would be required.  Since alternative
2C Is the preferred alternative in the FS report submitted by HI and
Gould, It will be carried through the evaluation process.

Alternatives  10A & 10B

    These two alternatives pass the protectiveness and ARARs screens.
However, the  alternatives each Involve Incineration of the ebonite
casings.  Due to expected opposition from the community and the State of
Oregon, these two remedies are also being screened out at this point.

Alternative IOC

    This alternative passes the protectlveness/ARAR screening and  will be
evaluated In more detail.

Alternatives  21 & 25

    These alternatives pass the protectlveness/ARAR screening. They are  In
fact quite similar alternatives, with the one difference being that 1n
Alternative 21 the soils and sediment are treated before being placed In
the RCRA landfill.  Since alternative 21 appears to go further In
satisfying the preference In the law for treatment to the maximum  extent
practicable,  and since It Is later shown to be cost effective, only 21
will  be evaluated in detail.
                                     28

-------
Screening for Cost Effectiveness

    The  alternatives which pass the initial screening screen are 2C, IOC,
and 21.  These are then evaluated to determine if any one falls to provide
for a solution that is cost effective.  The evaluation for these Is shown
in Table 5.

                                   TABLE 5
                   SUMMARY OF COST EFFECTIVENESS  SCREENING
                           Alternatives Evaluated
Reduction In
Toxlclty, Mobility
or Volume
      1C

$4,923,481

Moderate

Low
IOC

$20,565,184

High

High
11

$15.661.848

Moderate

Moderate
    The costs for Alternative IOC are extremely difficult to estimate.
The above costs have been prepared by the Dames & Moore for NL and Gould
and are considered worst case costs assuming little of the material is
recyclable.   In particular, costs for disposal  of non-recyclable battery
components such as ebonite in a RCRA landfill  are estimated at*over  "
$2,500.000 per year for five years.  These costs also do not allow for any
credit from the sale of recyclable components.   Design costs for this
project are estimated at only $226,000.  EPA views these detailed cost
estimates as providing a strong justification for Increasing the amount of
effort devoted to designing a process that minimizes the amount of
material  that requires disposal In a RCRA landfill.

    Based on the analysis above, all of the above alternatives are
considered to be cost effective ones.  Each appears to provide an Increase
in effectiveness and reduction In toxlclty, mobility or volume Xboth
criteria evaluated together) that Is commensurate with the Increased
cost.   The basis for the ratings In this table  Is Included In the detailed
analysis that follows for these three alternatives.
                                     29

-------
 Alternative 2C Evaluation

     Alternative 2C comprises removal of  the surface piles of battery
 casing  fragments, followed by off-site component separation and recycle o&
 some components, off-site disposal of others;  lime treatment of the exposi
 surface soils and battery casing material, followed by low-permeability
 capping and revegetation; lime treatment of the East Doane Lake surface
 water;  site grading; and a long-term monitoring program.

     Short-Term Effectiveness.  Under this alternative, most of the fill
 material would be left in place.  During remediation, remedial action
 worker  safety issues similar to those for minor earthmovlng projects will
 arise.  Hazards associated with site contaminants will be controlled by
 appropriate respiratory protection, proper safety attire and the
 application of dust suppression techniques.  Therefore, the short-term
 risks for workers on-site would be negligible.

     During remediation, lead concentrations In air emissions at the
 fencellne of the property will be monitored to detect any exceedences of
 the NAAQS for lead.  Proper dust suppression techniques should minimize the
 likelihood of this event.

     The surface piles carry the greatest potential for environmental risk
 because of their availability.  Battery casing corrrnents contained In the
 surface piles will be transported to an off-site recycler for separation of
 components.  After separation, some components will be recycled, while
 others may have to be disposed of in a landfill.  Risks associated wl.th
 transport of hazardous wastes from the site to the recycler, and hazardous
 waste transport from the recycler to a RCRA landfill, will be mitigated by
 transporting the wastes in accordance with 40 CFR 263  and State of Oregon.
 requirements for hazardous waste transportation.                          4

     Alternative 2C could be executed in approximately one year. Including
 planning,  review,  contracting and implementation.

     The disadvantages of this alternative In terms of short term
 effectiveness are that significant quantities of hazardous materials remain
 at the site and there is potential exposure to these substances 1f the
 institutional  controls proposed  n this alternative are not effective.
 Secondjy,  the lime treatment proposed In this alternative has not been
 fully evaluated during the FS and therefore Its effectiveness at this site
 is not wel1 known.

     Lonq-Term Effectiveness.  Removal of the surface piles Is expected to
 substantially reduce the potential for entrapment of dust from the site by
 wind, and to reduce the potential  for human contact with site
 contaminants.   Pumping and lime treatment of the site surface water may
 reduce the concentrations of dissolved contaminants by raising the pH of
 the water.   Site grading will reduce the amount of runoff In East Doane
 Lake, and eliminate the transport of surface water off site.  The
 application of lime to the surface areas where soil Is exposed or where
 casings are exposed or burled may reduce the concentration of dissolved
contaminants In surface runoff by raising the local pH.  However, the
effectiveness of this treatment technique at the Gould site has not been
fully evaluated.
                                     30

-------
    Subsequent capping will partially  Isolate the remaining contaminants,
 thereby reducing their avai-labl 1 Ity for off-site transport by surface
 water, air and direct contaminant ingestlon with soils.  However, the
 location of the site in a  100 year floodplaln, the problems with
 Implementing Institutional controls, particularly on the Rhone Poulenc and
 ESCO properties, and the fact that only 2X by volume of the contaminated
 casings will be removed make the long  term effectiveness of this
 alternative questionable.

    Reduction in Toxicity. Mobility, or Volume.   Alternative 2C reduces
 the volume and toxicity of the  site contaminants contained In surface
 piles, which are about 2% of the total battery casings.  The mobility of
 contaminants In soil and subsurface casings may be reduced by Increasing
 the pH of the soil system through lime treatment.  Lime treatment may not
 be effective In preventing mobilization from groundwater moving underneath
 the site.  Periodic reapplication of lime may be required to ensure the
 effectiveness of the treatment.  Subsurface contaminants are not reduced
 In volume or toxicity.

    Implementability.  Equipment for separating the battery casing fill at
 the site is available.   However, the separation equipment tested during
 the FS was designed to work on whole batteries,  not on the mix of
 materials found at the Gould site.   In particular, plastic and ebonite
 streams analyzed after processing through available separation equipment
 contained sufficient residual  lead to fall the EP Tox test.  Further, lead
 oxide is combined with much dirt in the separation process, which w11-1.
 serve to reduce the recyclability of this fraction.   Alternative 2C would
 be accomplished using modified conventional machinery at an off-site
 facility.

    Alternative 2C involves the removal and treatment of the surface piles
 of battery casings, surface soil treatment with lime, and surface water
 treatment by pH adjustment and filtration.  Recovered battery casing
 components will  be sent to other facilities for recycling or disposal.
 Those facilities receiving battery casing components will be required to
 meet RCRA Treatment, Storage or Disposal  facility requirements for
 processing of hazardous wastes, as required by the EPA Off-Site Policy.
 Applicable DOT,  EPA and State of Oregon regulations for the transport of
 hazardous materials will  also have to be followed.

    Any facility Interested In accepting the lead compounds for the
 purposes of recovering the lead would have to be permitted as a TSD
 facility under RCRA.  Recovered battery casing materials which cannot be
 recycled and which fall EP Tox will  be disposed of In a RCRA landfill.
 Nonrecyclable materials which pass EP Tox may be disposed of In a sanitary
 landfill.

    Cost.   The costs associated with this alternative are divided Into two
 categories.   The first Is capital cost which Includes direct costs such as
 transportation,  separation and disposal costs associated with the surface
casings; surface water treatment costs; lime addition to soil; site
grading; and Installation costs associated with monitoring.  Also Included
                                     31

-------
 in  capital cost are  indirect costs such as permitting, engineering and
 design, start-up, and contingency.  The second category of cost is operating
 and maintenance costs including site monitoring and reporting.  Operating
 costs are discounted to present worth for comparison of alternatives.

                    Capital       -O&M 9 12X
                    Cost           Present north

 Alternative 2C      $3,133,760     $1,789,722          $4,923,481

     Compllance with ARARs.  Contaminant-specific, location specific and
 action specific ARARs that apply to the Gould site are contained In Appendix
 A.  All contaminant-specific, location-specific and action-specific ARARs
 will be met by Alternative 2C, except for the EP Toxlclty requirement for
 lead In soils and battery casing materials.   This alternative also allows a
 continual  source of lead to impact the groundwater under the site, which
 already exceeds the MCL of 0.05 mg/1  and Is  considered a Class II aquifer.

     Overall  Protection of Human Health and  the Environment.  Surflclal
 contamination on site is reduced under Alternative 2C by removal of the
 surface battery casings piles and by paving/capping areas of highest
 residual  soil contamination, with lime applied before paving/capping to
 further reduce the potential mobility of residual lead In subsurface soils.
 These measures will  provide controls for general Inhalation exposures and
 direct contact ingestion exposures in these  areas of the site, barring
 physical  disturbance of the pavement/cap.   East Doane Lake surface waters
 will also be  treated under Alternative 2C.         .            >       ' .

     Assuming that the cap is not disturbed,  on-slte residential exposures
 by inhalation and Ingestion result in hazard  Indices less than 1.00 for
 age groups.   On-site worker and off-site residential populations have
 lower hazard  indices for all exposure pathways evaluated.  On-s1te and
 off-site  air  lead concentrations are 1n compliance with the NAAQS ARAR
 value.   However, these values are based on the effectiveness of the cap and
 the Institutional  controls that would be required on the Gould,
 Rhone-Poulenc, and the ESCO properties.  There Is considerable uncertainty
 as to whether Rhone-Poulenc or ESCO would allow these types of Institutional
 measures  on  their property.  Should the cap  become disturbed, substantially
 higher exposures for Ingestion might result.

     Short-term, off-site worker inhalation  exposures from fugitive dusts
 generated  during Alternative 2C remedial activities are determined to  be
 non-significant, with a hazard Index of 0.19.  Maximum short-term
 (quarterly)  air lead concentrations off site  are projected to be 1n
 compliance with the NAAQS ARAR value.

     Community Acceptance.  Several letters  were Included In the record of
 public comment which clearly Indicate that this alternative Is not
 acceptable to portions of the community.  For example, the Northwest
 District  Association, which covers an area representing 12,000 residents,
 stated that  It cor.iders this alternative to be "totally unacceptable".
Other groups  that have expressed opposition  to Alternative 2C Include:
 Hlllamette Heights Neighbors Concerned About  Noise and Chemical Pollution,
 Northwest  Environmental  Advocates, and OSPIRG.  These responses are  Included
 In Appendix  B.
                                     32

-------
     State Acceptance.  The State of Oregon Department of Environmental
Quality (DEQ) has carefully reviewed this alternative and finds 'it
unacceptable.
                                     33

-------
 Alternative IOC Evaluation

     Alternative  IOC comprises excavation of all of the battery casing
 fragments and matte from the Gould property and adjacent properties, follj
 by on-slte separation of the battery casing fragments.  Separation is foil
 by recycling of those components (or portions of components) that can be
 recycled; off-site disposal for non-recyclable components that fall the EP
 Toxiclty test, and on-site disposal of non-hazardous components.  It is EPA's*
 Intent under this alternative to minimize the amount of material that would
 require disposal  in a RCRA landfill.  Treatment studies performed during
 design will be used to define what portions of the battery casings are
 recyclable.

     Additional processes under Alternative IOC Include excavation,
 fixation/stabilization and on-site disposal of contaminated soil, sediment and
 matte; soil capping of treated areas and revegetatlon; isolation of East Doane
 Lake by site regrading; and a monitoring program to determine changes In
 groundwater contamination over time.  Under Alternative IOC, additional study
 will be performed on surface and groundwater in this area.  The proposed study
 will help determine whether action needs to be taken to deal with the
 contamination underneath the site, and how that action should be coordinated
 with other cleanup efforts by nearby Industries that are currently going on.
 The study will also address organic contamination as well as lead
 contamination.  The study would begin later this year.

     Short-Term Effectiveness.  Beneficial effects of removing and
 successfully separating battery casings and fixing/stabilizing soils,- -
 sediments and matte will be immediate on completion.  The groundwater and
 surface water monitoring program for Alternative TOC will be conducted as long
 as site contaminants remain unremediated.

     During remediation, worker safety Issues similar to those for moderate^
 earthmoving projects will arise.   For on-site workers, personnel protective
 equipment,  including respiratory protection, will mitigate the safety
 concerns.  However several  activities will be conducted simultaneously In a
 relatively small area,  leading to some concern over worker safety due to the
 intensive nature of site activity.   As part of the remedial action, a
 comprehensive health and safety plan will be developed before field work
 begins.

     During remediation, lead concentrations in air emissions at the fenceline
of the property will be monitored to detect any exceedences of the NAAQS for
 lead.   Proper dust suppression techniques should minimize the likelihood of
 this events.   Most of the material  to be remediated Is currently saturated  in
groundwater,  which will also help prevent fugitive emissions.

     The completion of remedial  activities under Alternative IOC may take up
to 6 years after remedial design Is complete.  Site conditions that may delay
execution of the alternative Include logistical difficulties associated with  .
dredging of the lake sediments.   Requirements related to stabilization of the
 lake shoreline during deployment of dredging equipment may also serve to
extend the time required for dredging.  The estimate Is based on a variety  of
factors that Include the size of the facility and other Items that will be
evaluated during the design phase.   It Is the agency's Intent to minimize the
time that Is  required for remediation under this alternative.

-------
     Long-Term Effectiveness.  Removal and successful separation of the
battery casing fragments would substantially reduce sources of pollution at
the site.  Without the battery casings, levels of pollution In all  media will
decrease.  Removal and disposal of contaminated sediments without treatment of
the site surface water will raise the concentration of dissolved and suspended
contaminants for a period of time.

     Under this alternative, health and environmental hazards posed by the
site are Intensively addressed by treatment.  Potential  hazards posed by the
site fill are addressed by treatment of the battery casing fragments.  The
treatment undertaken by this alternative addresses essentially all  of the
contaminated material and related risks.  Risks remaining after remediation is
completed are posed mainly by unremedlated surface soils, ground water and
surface water in the study area.   The groundwater and surface water risks will
be addressed In the additional study that Is proposed under this alternative.
Should the cap become disturbed,  additional Inhalation and Ingestlon risks
might result.  However, because of the Intensive treatment employed 1n this
alternative, these risks are considered to be less than  those presnented in
either Alternative 2C or 21.

     The technology to be used in this alternative has been demonstrated In
other situations and appears to be feasible based on the studies that have
been done at this site, since the tests clearly showed that the materials can
be separated.  Design modifications of the separation process will  be
accomplished during the engineering studies that will occur as part of the
remedial design phase.
                                                              N
     Reduction in Toxicity. Mobility, or Volume.  In the Nature and Extent of
Problem section, the estimated quantities of metallic lead, plastic, lead
oxide,  ebonite, and other material are calculated.  An estimate of the
quantity of metallic lead is shown as 0.6 percent of all primary source
materials,  plastic is estimated at 3.0 percent of primary source materials,
lead oxlde/dlrt/mud at 10.2 percent, and ebonite at 74.3 percent.  Contacts
made during the conduct of the FS Indicate that the metallic lead would likely
be completely recyclable, the plastic would be recyclable at some locations.
depending on lead content, and lead oxide would likely be accepted by some
smelters.  The largest component of source material, ebonite, may or may not
be recyclable depending on the extent to which It can be treated.  Using these
assumptions, It Is estimated that approximately 25% of the lead In the casings
can be recycled.

     The potential for long-term mobility of site contaminants 1s decreased
with Alternative IOC, by both removal of lead 1n the casings through recycling
and by treatment of contaminated soils and sediment to reduce the mobility of
lead.

     Implementabllity.  During the conduct of the FS, several efforts at
component separation and cleaning of the battery casing material were
attempted by the PRPs.  A review of the efforts of others who attempted
separation  and recycle was also conducted.  These attempts can be generally
characterized as demonstrating that separation of battery casings Is feasible
at low feed rates.

     Plastic and ebonite streams  after processing may contain enough
Interstitial lead to fail the EP Tox test.  All such materials that can not be
recycled would need to be landfllled In a RCRA facility.

     Soil stabilization Is a proven technology and was shown to be effective
In a bench-scale test during the  FS.  Pilot testing of the technology under
actual  site conditions will be required during remedial  design to determine
the correct ratios of materials and to determine whether the technique can be
effective under actual site conditions.
                                     35

-------
     Sediment dredging may contribute to the difficulty of subsequent
 treatment of East Doane Lake surface water, though some sedimentation of the-
 suspended materials should occur prior to any future surface water
 remediation.  Excavation of the fill on the Gould and off-site properties   ^t
 also include a consideration of the power lines along the northwest edge
 the Gould property, which may need to be relocated because of remediation'.

     Alternative IOC involves the excavation and separation of all battery
 casings, followed by recycle or RCRA disposal  of specific battery casing
 constituents.  Those recycle facilities receiving the lead oxide and soil
 component will have to meet RCRA TSD requirements for processing of hazardous -
 wastes, as required by the EPA Off-Site Policy.  Applicable DOT, EPA and State
 of Oregon regulations for the transport of hazardous materials will also have
 to be followed.  No permit will be required for any of the wholly on-slte
 portions of the alternative.   During remediation, separation and treatment
 facilities will be erected, operated and demolished, and excavation equipment
 will be operated.  These activities may require local construction permits.

     Recovered battery casing materials which  can not be recycled will  be
 disposed of In a landfill.  Components which fall the EP Toxlclty test will
 have to be placed in a landfill that meets the RCRA requirements of 40 CFR
 Part 264.  It is EPA's intent to minimize this portion of the separation plant
 output stream.

     Cost.  The costs associated with this alternative are divided Into two
 categories.   The first is capital  cost, which  Includes direct costs such as
 erection of process equipment,  excavation, separation and disposal costs
 associated with the surface and subsurface casings; sediment dVedglng costs,
 soil stabilization costs; site grading; and Installation costs associated with
 monitoring.   Also included in capital cost are Indirect costs such as
 permitting,  engineering and design, start-up,  and contingency.  The secon^H
 category of cost is operating and maintenance  costs that occur throughout^?
 multi-year remedial  effort, such as excavation, separation, and disposal costs
 beyond year one.   Operating and maintenance costs are discounted to present
 worth for comparison of alternatives.

               Capital          O&M 9 121           Total
                Cost          Present north        Cost

               $3,491,603     $17,073,581         $20,565,184

     The costs for this alternative are extremely difficult to estimate.  The
 above costs  have been prepared by the Dames &  Moore for NL and Gould and are
 considered worst case costs assuming little of the material Is recyclable.  In
 particular,  costs for disposal  of non-recyclable battery components such as
 ebonite In a RCRA landfill are estimated at over $2,500,000 per year for five
years.   These costs also do not allow for any  credit from the sale of
 recyclable components.   Design costs for this  project are estimated at only
 $226,000.  EPA views these detailed cost estimates as providing a strong
 Justification for Increasing the amount of effort devoted to designing a
 process that minimizes the amount of material  that requires disposal In a RCRA
 landfill.
                                     36

-------
     Compliance with ARARs.  Contaminant-specific, location specific and
action specific ARARs that apply to the Gould site are contained in Appendix
A.  All contaminant specific, location-specific and action specific ARARs will
be met by Alternative IOC.  During remediation, lead concentrations In air
emissions at the fenceline of the property could exceed the NAAQS for lead.
If continued excedences occur, remedial operations will be shut down and
appropriate modifications to the operations will be made.  Activities may also
be adjusted based on meteorological conditions.  All  materials handling will
be performed as a wet process where feasible.  A site specific health and
safety plan will be developed to ensure the safety of remedial action
workers.  Much of the material to be remediated Is currently saturated In
groundwater, which will also help prevent fugitive emissions.

     Overall Protection of Human Health and the Environment.   Surflclal
contamination on site is reduced under Alternative IOC by on-slte treatment of
all battery casings (piles and burled), with off- site disposal at a RCRA
landfill of materials failing EP Toxlclty tests and stablllzatlon/on-slte
disposal of remaining residual materials (soil, sediment, matte), and
pavement/capping of all disposal areas.  These measures will  provide
long-term, effective controls for general Inhalation exposures and direct
contact Ingestion exposures in these areas of the site.  Stabilization of
residual wastes will provide an additional component of protection and further
prevent contaminant migration to groundwater.

     Community Acceptance.  In the public record there are several letters
Indicating support for this alternative.  Groups that have expressed support
for Alternative IOC Include: Food Front Cooperative Grocery,  Willamette
Heights Neighbors Concerned About Noise and Chemical  Pollution? Northwest
Environmental  Advocates, and OSPIRG.  These responses are Included In Appendix
B.                     ;          .

     State Acceptance.   DEQ fully endorses this alternative and supports EPA's
conclusion that Alternative IOC meets the statutory requirements for a remedy
contained  In CERCLA and Oregon Senate Bill 122.
                                     37

-------
 Alternative 21 Evaluation

     Under Alternative 21, all of the fill material on the Gould, and off-si-te
 properties above  3000  ppm wi.ll be excavated for treatment (soil, sediments^" or
 on-site disposal  (battery casings).  Contaminated  soil, sediment, and matl
 would be treated  by fixation/stabilization, then backfilled into the sit«r
 excavation.   Excavated battery casing materials would be disposed of in an
 on-site RCRA  landfill.  The alternative also  includes pH adjustment and
 filtration of  the East Ooane Lake remnant, site grading, low-permeability
 surface capping,  and a long-term monitoring program.

     Short-Term Effectiveness.  Under this alternative, the recovered battery"
 casing fill would be stored on an adjacent property while the landfill Is
 constructed.   During remediation, worker safety Issues similar to those for
 moderate earthmoving projects will arise.  For on-site workers, safety attire
 will mitigate  some safety concerns, however several activities will be
 conducted simultaneously in a relatively small area, leading to some concern
 over worker safety due to the intensive nature of  site activity.  As part of
 the remedial action, a comprehensive health and .safety plan will be developed
 before field work begins.

     During remediation,- lead concentrations  In air emissions at the fencellne
 of the property will be monitored to detect any exceedences of the NAAQS for
 lead.  Proper  dust suppression techniques should minimize the likelihood of
 this events.   Most of the material to be remediated is currently saturated In
 groundwater, which will also help prevent fugitive emissions.

     Remediation under Alternative 21 might be completed In about four years,
 Including planning,  review, contracting and construction.

     Long-Term Effectiveness.  The intent of  this  alternative Is to fullyl
 mitigate potential health and environmental effects of site contaminants !
 completely Isolating the contaminants from the environment.  Enclosure of the
 battery casing fill  in a RCRA landfill  will prevent the migration of
 contaminants In water and air, and will  limit their availability for direct
 Ingestlon.   Fixation/stabilization treatment of soil, sediment and matte will
 also prevent contaminant migration and will decrease the mobility of these
 materials.   Site regradlng and blocking of the overflow from the East Doane
 Lake remnant will  reduce the accumulation'of runoff in the lake remnant, and
 decrease the movement of contaminated surface water off site.  With
 appropriate institutional controls, the health and environmental hazards posed
 by the site fill are mitigated.

     The removal and on-s1te disposal of the battery casing fill will require
 long term maintenance and monitoring.  Frequent Inspection of the cap will be
 required to ascertain that an Impermeable barrier  Is maintained between the
 contaminants and the environment.  Site monitoring equipment will require
 continued maintenance, as well.  As a result,  the effectiveness of leaving all
of the contaminated battery casings untreated on-site Is questionable, given
 concerns about the long term maintenance requirement's of caps, the location of
 the site In a floodplaln, and the effectiveness of Institutional controls at
 this site.
                                     38

-------
t.                                          •

                     Soil  stabilization  is  a  proven  technology and  was  shown  to  be  effective
                in a  bench-scale  test  during  the  FS.   Pilot testing of  the  technology  under
                actual  site  conditions will  be  required  during remedial  design to determine
                the correct  ratios  of  materials and  to determine  whether the  technique can be
                effective  under actual site  conditions.

                     Reduction  In Toxlcitv.  Mobility,  or Volume.  On-s1te disposal  of
                untreated  battery casings  cannot  be  considered a  treatment  that  permanently or
                significantly  reduces  the  toxicity or  volume of hazardous substances.   The
                mobility of  contaminated  soils  Is reduced by treatment.

                     Implementabl11ty.   Soil  stabilization Is a proven  technology and  was
                shown to be  effective  in  a  bench-scale test during  the  FS.  Pilot testing of
                the technology  under actual  site  conditions will  be required  during remedial
                design  to  determine  the  correct ratios of materials and  to  determine whether
                the technique  can be effective  under actual site  conditions.

                     Sediment  dredging will  contribute to the difficulty of subsequent
                treatment  of East Ooane  Lake  surface water.  Excavation  of  the fill  on the
                Gould and  off-site  properties must also  Include a consideration  of  the power
                lines along  the northwest  edge  of the  Gould property, which may  need to be
                relocated  because of remediation.  Power supply to  Industrial facilities may
                be Interrupted  as a  result.

                     Alternative  21  would  be  accomplished using conventional  machinery and
                techniques.  Surface capping  Is a proven technology,  and Is considered-
                reliable.  However,  failure of  a  surface cap could  require  addltlona]  .
                remediation, consisting of  replacement of the cap.            "

                     During  construction,  monitoring systems will be Installed,  site drainage
                systems  will be emplaced,  and buildings  will be demolished.  Construction
                permits  will be required  for  any  off-site portion (I.e., drainage)  of  these
                activities.

                     During  construction  of  the landfill, excavated wastes  would have  to be
                placed on  an adjacent  property.  Temporary storage  of excavated  material must
                comply with  40 CFR  265.253  and  265.254.   Off-site storage might  also require
                special  arrangements with  state and  local agencies  and  authorities, and
                special  agreements  with  neighboring  property holders.

                     The materials  and equipment  needed  to Implement Alternative 21 Include  a
                dredge for the  sediments,  common  excavation equipment,  a plastic geomembrane
                for the  landfill,  water  treatment equipment, monitoring equipment,  and a
                source of  lime  and  other  reagents for  fixation/stabilization.  All  of  these
                materials  are  readily  available.
                                                     39

-------
     Cost.   The  costs  associated with  this  alternative are divided into two
 categories.   The  first  is capital  cost, which  includes direct costs such
 as  excavation and  landfill construction costs;  sediment dredging costs
 surface water treatment  costs; soil fixation/stabilization costs; site'
 grading; and  Installation costs asso- dated with monitoring.  Also'
 Included In capital cost are  indirect costs such as permitting,
 engineering and design,  start-up,  and contingency costs.  The second
 category of cost  is operating and  maintenance  costs that occur throughout
 the  multi-year  remedial effort, such as excavation, placement and
 monitoring costs  beyond year one.  Operating and maintenance costs are
 discounted to present worth for comparison of  alternatives.

                   Capital            O&M I? 12X         Total
                      Cost           Present North .     Cost

 Alternative 21     $9,678,453        $5,983,396       $15.661,848

     Compliance with ARARs.  Contaminant-specific, location specific and
 action specific ARARs that apply to the Gould  site are contained In
 Appendix A.  Several action specific ARARs are particular to Alternative
 21.  These are  Indicated below:

     0    Landfill:  must comply with 40 CFR 264 standards for a hazardous
         waste  landfi 11.

     e    Capping:  must comply with 40 CFR 264 Subpart G standards for a
         cover over hazardous waste at closure.               s

         Closure with waste in place:  must comply with 40 CFR 264 Subpart
         G standards for closure performance and post-closure care and
         monitoring.

     0    Excavation:  hazardous wastes excavated and replaced on-s1te must
         be-replaced in a waste management unit that compiles wi.th RCRA
         requirements.

    All contaminant-specific, and  location-specific ARARs can be met by
Alternative 21.   During remediation, lead concentrations In air emissions
at the fencellne of the property could exceed  the NAAQS for lead.
However,  proper design of the materials handling process and proper dust
suppression techniques should minimize the likelihood of these events.
Much of the material to be remediated 1s currently saturated In
groundwater, which will also help prevent fugitive emissions.

    Action- specific ARARs for Alternative 21   can be met, with details to
be worked out during remedial design.

    Overall Protection of Human Health and the Environment.  Surfldal
contamination on site Is reduced under Alternative 21 by on-slte treatment
of all contaminated soils, with stabl11zation/on-s1te disposal In a
constructed landfill of these materials and battery casing components.
These measures will provide long-term, effective controls for general
Inhalation  exposures and direct contact Ingestlon exposures In these areas
of the site, barring physical disturbance of the RCRA landfill.
Stabilization of residual wastes will  provide  an additional component of
protection  If the RCRA landfill Is disturbed.
                                     40

-------
    The long-term exposures and risks after completion of Alternative 21
remediation activities are determined to be acceptable.  On-site
residential exposures by inhalation and ingestion result In hazard indices
less than 1.00 for all age groups.  Should the landfill cap become
disturbed, however, these exposures could Increase.

    Community Acceptance.  During the public comment period, most of the
comments were addressed to either Alternative 2C or IOC rather than
Alternative 21.  However, many of the comments expressed a .desire for a
"complete clean-up" of the site.  To the extent that Alternative 21 falls
to remove lead from the battery casings, community concerns about this
alternative are assumed.

    State Acceptance.  DEQ's position regarding this Alternative Is that
the agency is opposed to any alternative that will Increase the number of
RCRA landfills In the State of Oregon.  Since there Is another cost
effective alternative for this site, Alternative 21 Is deemed unacceptable.
                                     41

-------
 VI SELECTED REMEDIAL ALTERNATIVE.

Description of Selected Remedy

    The selected remedy for the soil.s unit at the Gould site is based on
Alternative  IOC.  The selected remedy comprises:

    8    Excavation of all of the battery casing fragments and matte from
         the Gould property and adjacent properties where casings have
         been Identified:

    0    A phased design program to determine the amount of material that
         can be recycled and to minimize the amount of material that must
         be RCRA landfllled.

    0    Separation of the battery casing fragments;

    0    Recycling of those components (or portions of components) that
         can be recycled, off-site disposal for non-recyclable components
         that fail the EP Toxicity test, and on-slte disposal of
         non-hazardous,  non-recyclable components;

    0    Excavation, fixation/stabilization and or'-slte disposal of the
         remaining contaminated soil, sediment, and matte;

    9    Soil capping and revegetatlon;                      N       • .

    0    Isolation of surface water runoff to East Doane Lake by site
         regrading; and

    8    A monitoring program to determine changes In groundwater
         contamination over time and to ensure that remediation does not
         adversely impact air quality.

    Under Alternative IOC, additional study will be performed on surface
and groundwater in this  area.  The proposed study will help determine
whether action needs to be taken to deal with the contamination underneath
the site, and how that action should be coordinated with other cleanup
efforts by nearby Industries that are currently going on.  The study will
also address organic contamination as well as lead contamination.  The
study should begin later this year and will' be accomplished under'a strict
schedule.
                                     42

-------
                                                                                                          PENNWALT CORP.
                                                               MW FMMT »vt
                                                                                                            SCHNITZER
                                                                                                         INVESTMENT CORP.
                                                       UOUIO AIR CORP

                                                                                                   RHONE-POULENC  INC.
                                                                    O    100
                                                                                          4OO
.••!•<••€•:
 ftMn • (••••<•»>»< •••••» ••» ••'•* *••'  '•• *••*•
 k* O.I U«l« 4 *•••€••••«. O»»«»««>. (N»-.
 !•< OMMI 4 M*«t«
•CAki I*  »00'
                                                                                                                            AMERICAN STEEL INDUSTRIE S.I
                                                                                                                                      INC.            1
Flgutf 9
   Estimated Areas to be
Remediated under Selected
          Remedy

-------
    Surface soils that have a total lead content above 1,000 ppm, and
subr-surface soils, matte, and the East Doane Lake sediments that fail EP
Toxicity standards; will be removed and treated with a fixation additive
to bind the lead  in the soils matrix.  The stabilized product from the
soils process will be backfilled, graded, and recompacted on site.
Topsol.l and a vegetative cover will be placed over the backfill to prevent
weathering of stabilized soil and subsequent remoblllzatlon of the metal
components.  Battery casings which are recyclable will be excavated and
treated to separate the component materials such that they can be
recycled.  Output streams from the separation facility that are not
recyclable, and that fail the test of EP Toxicity for lead are required
under RCRA regulations to be disposed of in a RCRA landfill.

    EPA Intends to devote extensive design effort to developing a process
that will minimize the amount of material that will require disposal In a
RCRA landfill.  If based on the results of the design phase. It appears
that the goals of treating all of the battery casings and minimizing the
amount of material requiring .RCRA disposal are not compatible, an
additional public comment period will be established, and the Record of
Decision may be amended.  At such time. EPA would present to the public
other options for dealing with the treated materials.

    Those output  streams that cannot be recycled but pass the test of EP
Toxicity, will be disposed of on site, and covered with topsoll.
                                     44

-------
     The outfall of East Doane Lake will be blocked such that water that
 fails  the Oregon Water Quality Standard for  lead will not be discharged to
 the  Willamette River.  The processes and unit operations under the
 selected remedy are described below.  The areal extent of remediation
 under  the selected remedy  is depicted in Figure 9.

     Battery casings will be excavated and then delivered to a stockpile
 located adjacent to the battery casing treatment plant.  The contaminated
 soils, sediments and matte will be removed and stockpiled adjacent to a
 soils  treatment facility.  The estimated 1n-s1tu casing and contaminated
 soil quantities are as shown In the following table.

                         Volume      Mass
                         (cu yd)     (tons)

 Surface Soils              3,370       4,300
 Sub-surface Soils        13,650      17,500
 Sediments                  5,500       7,520
 Matte                      6,000      12,000
 Battery Casings          80,800      86,820

     The contaminated soils wl11 be transferred to a stockpile formed
 adjacent to the soils treatment facility.  Soils *-;ich will not be treated
 but  were removed for ease  of access and slope stability will be stockpiled
 and  later used as backfill.  This volume Is  estimated to be 17,800 cu. yd.

     The treated soils will be back hauled to the excavation, then gradtd
 and  compacted in lifts suitable for the soil type.  The site will be
 graded to have swales and  slopes to provide  soil stability, drainage, and
 prevent run-on from adjacent areas.  Top soil will be Imported to provide
 a four-inch soil cap with  a vegetative cover to prevent weathering and
 subsequent airborne migration.

     In addition to the earthmoving required  on the Gould site, the
 northeast section of the American Steel Industries parking  lot, which
 drains to the lake, will require modification to reroute drainage from
 that facility.

     To prevent excess airborne migration during surface and subsurface
 excavation of material, dust control by watering and other measures will
 be practiced as required.  In addition to watering, these activities could
 Include reduced vehicle speeds; reduced drop heights; and special
 enclosures and controls for conveyors.  Additional design modifications
 may  also be required to ensure that fugitive emissions are kept to a
 minimum.  Site boundaries  will be monitored  to determine If air emissions
of lead exceed the NAAQS.  If continued excedences occur, remedial
operations will be shut down and appropriate modifications  to the
operations will be made.  Activities may also be adjusted based on
meteorological conditions.  A site specific  health and safety plan will be
 developed to ensure the safety of remedial action workers.
                                     45

-------
    The excavation of subsurface battery casings and subsequent treatment
will result in an extension of East Doane Lake in the Gould property, in
the Rhone-Poulenc property, and on the ESCO property.  To prevent erosion,
the excavation will be graveled at the shoreline and coarse gravel will  bj'
spread and graded above and below the waterline.

    A treatment facility will be constructed at the site to treat con-
taminated surface soils, subsurface soils, sediment and matte.  A typical
process for treating soils consists of a comminution system to reduce the
materials to a relatively uniform size, and then pugmllllng with an
additive to bind the metals in the soils matrix.

    In the pugmilling section, the process commences at the feed hopper.
Stockpiling, retrieval, material handling, and circulating loads In the
crushing circuit provide a uniform blend of feed material to the pugml11.
In the pugml11 the feed is joined with binder additive and a predetermined
amount of water, then fed to the pugml11 as a water based slurry.  In the
pugmlll the additive is driven into the soils.  The additive comprise of a
cement-like fixative (cement, pozzolan, lime, clays); a reducing agent,
and various proprietary chemicals.  The actual additive composition and
Its ratio will be determined by pilot testing during the design phase.
The pugmlll discharges the stabilized soil to a belt conveyer which
transports It to a stockpile from where 1t will be, retrieved by loader for
backfilling.

    A treatment facility will also be constructed at the site to treat the
contaminated battery casings and produce potentially recyclabVe products
or a reduction in material to be subsequently disposed.  The process
Includes a comminution system to reduce the materials to a size at which
they can be separated.  This is followed by a series of hydroclasslflers  ,
which separate the various products in water by the differential specific
gravities.  Separation is performed as a function of material specific
gravity and detention time in each classifier.  The quantities, specific
gravities, and loose bulk densities of each of the casing components are
estimated to be the following:

                   Specific    Bulk Density        Volume     Mass
    Component      Gravity     (Ibs/cu.ft.)       (cu. vd.)  (tons)

    Ebonite         1.40        61.21           77,642       64,148
    Plastics        0.94        41.90            5,162        2,920
    Met. Lead      11.34       267.73              136          493
    Oxide/Mud       5.65       214.54            3,059        8,860
    Rock/Slag       2.20        95.01            2.313        2,966
    Other           1.50        67.00            1,405        1,268
    Moisture        1.00        62.30            	0        6.175
    Average/Total   2.15        71.68           89,717       86,827
                                     46

-------
    The actual volume of casings to be treated will be determined after
additional design work to further define the  locations of battery casings
underneath the site and determine the characteristics of the subsurface
casings/soil matrix that can be recycled.

    It Is also assumed that both the soils treatment and battery recycling
plants will operate concurrently.

    The separated materials from the battery  separation facility will be
ebonite, plastic, metallic lead, and a combined stream of lead oxide/mud.
Based on the results of pilot studies It Is assumed that all of the
metallic lead, half of the plastic, and 25 percent of the lead oxide/mud
will be potentially recyclable.  Any of the ebonite, plastic, lead
oxide/mud streams that fail EP Toxlclty will  be sent to an off-site RCRA
landfill.  Materials that pass EP Toxlclty but which can not be recycled
may be left on site.  These amounts will depend on the the results of the
separation step.

    Rock/debris and other similar materials separated from the recycling
plant feed stream will  be sent to the fixation plant and treated with the
soil for backfilling.

    The end product of soil stabilization treatmer-: will be tested for the
appropriate physical and chemical characteristics.  The design of the
testing procedures will be developed after the pilot testing and selection
of the particular stabilization technique.    The testing program woul.d
determine treated and  untreated soil properties such as porosfty,
permeability, wet and  dry densities, particle size distribution, bulk
properties, and durability.  Chemical leach testing of stabilized soil.
Including EP Toxlclty  tests, will be done to  predict Its chemical
stability.

Design Studies

    A major feature of this selected remedy Is the design work that will
be required before the remedy can be Implemented.  As discussed earlier,
EPA Intends to devote  extensive design effort to developing a process that
will minimize the amount of material that will require disposal In a RCRA
landfill.   The design  work will consist of a  phased series of studies to:

         Define recyclabllIty criteria for the subsurface casings -that
         will be used  to determine the volumes of subsurface casings that
         can be recycled.

    *    Determine the process requirements to separate the casing
         components In a manner that minimizes fugitive emissions.
         Depending on  the results of Initial  evaluations under this step,
         large quantities of surface casing material may be transported  to
         an off-site facility for recycling and equipment modification
         studies.

    *    Determine the modifications required to adapt existing separation
         technology to conditions at the Gould site.

    *    Determine the process requirements for treating contaminated
         soils, sediment and matte.
                                     47

-------
                    APPENDIX A
APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS

-------
                                 APPENDIX A
             APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
                    LAWS AND REGULATIONS TO BE CONSIDERED
 A.   FEDERAL  LAWS  AND .REGULATIONS  THAT ARE ARARs FOR THE GOULD SITE
 0    Resource Conservation  and  Recovery  Act (RCRA)  (42  USC  6901),
     Subtitle C:
          EP  Toxlcity  Standards for  lead, cadmium, chromium, zinc.
          Landfills:   must comply with  40 CFR 264  standards  for  a  hazardous
          waste  landfi11.
          Capping:  must comply with 40 CFR  264  Subpart G standards for  a
          cover  over hazardous waste at closure.
          Closure  with waste in place;  must  comply with 40 CFR 264 Subpart
1          G  standards  for  closure performance and  post-closure  care  and
          monltorlng.

     Clean Air Act  (CAA) (72 USC 7401):
                                                              \
          National  Ambient Air Quality Standards  for.lead.
          Ambient Air  Quality Standard       1.5 ug/m3 lead
                   arithmetic  average   concentration  of  all  samples
                   collected during any  one  calendar quarter  period.

 8    OSHA  29CFR  1910:
          Regulations  governing worker safety at hazardous waste- sites.

Other Action  Specific ARARs
     The following  ARARS will  be  used for  any wastewater discharges from
remedial  actions at the Gould site.
     Safe  Drinking  Hater Act (SHOW)  (42 USC  300):
          Drinking  Water  Standards  (40  CFR  141),   Including maximum
          contaminant  levels (MCLs).
*    Clean Hater Act (CWA) (33 USC 1251):
          National  Pollutant Discharge Elimination System  (40  CFR  122)
          Water Quality Criteria (EPA440/5-86-001).

-------
 B.   OREGON  STATE  LAWS AND  REGULATIONS' THAT ARE ARARs FOR THE GOULD SITE

 Chemical Specific ARARs

 Regulation               Standard
OAR 437.100.010          No  employee  exposure  to  Inorganic  arsenic  at
                         concentrations  greater  than  10 ug/m3  of air
                         averaged over any 8 hour period.

OAR 340-31.055           Ambient  Air Quality Standard  ofl.5  ug/m3 lead.
                         Arithmetic  average  concentration of  all  samples
                         collected during any one calendar quarter period.


OAR 340.20.225           A1r/  Significant  Emission  Rate of 0.6  ton/year
                         lead
OAR 437.111.010          No  employee exposure  at  lead  concentrations
                         greater          than          50
                         ug./m3 of air averaged over an 8-hour period.

OAR 340-45               Regulations Pertaining to NPDES and WPCF Permits

Suspended Partlculate Matter

OAR 340-31..015

Annual Geometric Mean          60 ug/m3

24 hour concentration          100 ug/m3
for more than 15 I of
samples In one calendar
month.

24 hour concentration          150 ug/m3
not more than once
per year.


Fine Partlculates/ PM10

Annual Arithmetic Average            50 ug/m3

24 hour average concentration,       150 ug/m3
not exceeded more than average
of one day per year.

-------
Action Specific ARARs
Hazardous Haste
OAR 340.100-002
(Federal Regulations Incorporated by Reference)
Capping

    surface Impoundments - 40 CFR 264.228
    waste piles - 40 CFR 264.258(b>
    landfills - 40 CFR 264.310(a)
Closure with waste in place
    stabilization - 40 CFR 264.228 
-------
OAR 340-130              Notice  of Environmental  Hazards  - pertains  to
                         institutional controls  at the site
Solid Haste
Regulation               Standard .
OAR 340-61               Solid Waste  Management  -  covers  storage,  disposal
                         and treatment of solid waste.
ORS 459-005 to 459-355   Solid Waste Control - same as above.

Air Quality
Depending on  the  type of action designed, the regulations described below
may contain specific requirements  In addition to the chemical specific  air
pollution regulations cited earlier.
Regulation               Standard
OAR 340-20               Air  Pollution Control  - details  contained  In
                         regulations cited below.
OAR 340-20-001           Highest  and  Best   Practicable  Treatment  and
                         Control Required
OAR 340-20-040           Methods
OAR 340-20-240           Requirements for Sources  In Nonattalnment Areas
OAR 340-20-225           Significant Emission Rate
OAR 340-20-245           Requirements  for  Sources  In  Attainment  or
                         Unclassified  Areas (Prevention  of  Significant
                         Deterioration)
OAR 340-21               General Emission Standards for Partlculate Matter
OAR 340-31               Ambient Air Quality Standards

-------
 Oregon Occupational Safety and Health Code
 Regulation               Standard
 OAR 437-40               General  Provisions
 OAR 437-50               Personal Protective Equipment
. OAR 437-83               Construction
 OAR 437-100              Inorganic Arsenic
 OAR 437-111              Lead
 OAR 437.114              Air Contaminants
 OAR 437.129              Protective Equipment.  Apparel,  and Respirators
 OAR 437.136              General  Occupational  Health Regulations
 Transportation of Hazardous Materials
 OAR 860.66.055 to 860.66.072
 Oregon Land Use Goals:
 OAR 660.15.000(6)                                                   .  .
 Goal  6.   Air,   Water  and  Land Resources  Quality  - Establishes  that
          discharges shall  not exceed the carrying capacity of air water or
          land   and  shall   not  violate  applicable  Federal  or  State
          environmental  quality statutes and regulations.
 OAR 660.15.000(7)
 Goal  7.   Areas Subject to  Natural Disasters and Hazards - Establishes  that
          floodplain areas  should  be evaluated as  to the degree of hazard
          present.

-------
C.  FEDERAL  LAWS AND  REGULATIONS  TO BE CONSIDERED


    Safe Drinking Water Act  (SWDW) (42 USC 300):
         Drinking  Water  Standards  (40  CFR  141),   Including  maximum
         contaminant  levels  (MCLs).

0   Clean Water Act  (CWA)  (33 USC 1251):
         National Pollutant  Discharge Elimination System (40 CFR 122)
         Water Quality Criteria  (EPA440/5-86-001).

D.  STATE OF OREGON LAWS AND  REGULATIONS TO BE CONSIDERED

Chemical Specific Regulations

OAR 333.61.030           0.05 mg/1 Drinking Water Standard for chromium
                         0.05 mg/1 Drinking Water Standard for lead
                         5 mg/1  Drinking Water Standard for zinc
                         0.01 mg/1 Drinking Water Standard for cadmium
                         0.05 mg/1 Drinking Water Standard for arsenic


OAR 340-41-445           0.05 mg/1 Lead  Standard  for Protection of  Human
                         Health  from Water and Fish Ingestlon
                         0.01 mg/1  Chromium Standard  for  Protection  of
                         Human Health from Water and Fish Ingestlon
                         0.05 mg/1  Arsenic Standard  for protection .of
                         Human Health from Water and Fish 1nge«t1on

Water Quality Regulations

OAR 340-41-001 to        State Wide Water Quality Management Plan -
340-41-029               regulates groundwater quality.

OAR 340-41-442 to 470    Willamette Basin - establishes beneficial uses  to.
                         be  protected and  water quality criteria  not to be
                         exceeded.

-------
       APPENDIX B
RESPONSIVENESS SUHMARY

-------
                           RESPONSIVENESS SUHHARY


                               NL/GOULD, INC.

                              PORTLAND, OREGON
    This  community  relations responsiveness summary  Is  divided  Into the
following sections:
    PAGE

Section A:
Overview.
Section B:
3
              This  section  discusses  the  EPA selected  alternative  for
              corrective action and public reaction to this alternative.
Background on Community Involvement and Concerns.
              This provides  a  brief history  of community  Interest  and
              concerns  raised  during  remedial  planning and  Investigation
              activities at the NL/Gould, Inc., site
Section C:    Summary of Comments Received During the Public Comment
              Period and EPA's Responses to the.Comments.
              Both written  and oral  comments  are  categorized.
              responses to these comments, are also provided.
                                                    EPA's
Section D:     Remaining Concerns.

              This section describes remaining community concerns that  EPA
              should take  Into consideration In  conducting  the remedial
              design and remedial  action at the NL/Gould, Inc.. site.

-------
                                    OVERVIEW
     At the  time of  the  public comment period  (2/18-3/18/88), EPA  Identified  a
preferred  cleanup  alternative  for  the  NL/Gould  site.   EPA's  preferred
alternative  Involved  removing  the  battery casings on and beneath the site and
treating them for  proper disposal  of  lead,  plastic,  and  other materials;
treating the  lead  contaminated  soil  and sediments with a chemical  additive to
bind the lead to the soil and keep the contamination  on  site; and additional.
studies of groundwater  pollution  in  the Ooane  Lake area  to  decide  If
additional  cleanup  is necessary.  The  preferred alternative  1s  described
further In the detailed evaluation.

     This   Responsiveness  Summary describes concerns  which  the  community has
expressed   regarding  the  problems  at the  site  and  the  preferred  cleanup
alternative.   EPA's response to these comments are also provided.

     After  reviewing  all  the  comments  received during  the public  comment
period, EPA  has determined  that  residents of  the  local  communities,  local
environmental groups,  and  the Oregon  Department of  Environmental  Quality
strongly support  EPA's proposed alternative.   Indeed,  some  residents .and
groups would  go farther.                                       •  ^

     The potentially  responsible parties,  NL Industries and  Gould,  Inc.,  do
not support EPA's  preferred alternat:ve.    Instead,  they  recommend  Alternative
2C, which  is  discussed in the detailed  evaluation.

-------
                                         3

                 BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS
      From 1981 until  1985  when  EPA assumed the enforcement lead for the site.
 Oregon Department of Environmental  Quality (DEQ) conducted community relations
 activities as  part of its  regulatory efforts at the site.

      In  1982,  DEQ announced proposed  listing  of the NL/Gould  site  for the
 National  Priorities List.    There was  little public response to  the  proposed
 listing.   From December  1982  to September  1983,  the  site received moderate
 media publicity.   General   public interest In the  site  appeared to  be low
 despite the Intermittent media  coverage.

      In 1983,  Oregon Congressional  Representative Les AuColn corresponded with
 DEO about the  site,  and DEO held a  meeting with city,  county,  and state agency
 officials to present  information about  environmental  concerns  In the area and
 to solicit comments.  Representative AuColn specifically  requested  that  DEQ
 assure him that site cleanup would  completely remove potential  contaminants.


      EPA  prepared a  Community Relations  Plan for this site  In  1985,  based on
 research  and interviews  with Interested  community members and  officials"..  The
.issues of concern to the affected community and local  officials Included:

      1.-   Groundwater  Pollution.  People  were  concerned  about  ground- water
           contamination  in the   area and  how It might affect future growth of
           the  area.

           EPA responded to this concern by including extensive groundwater testing in
           theRI.

      2.    Airborne Lead.   Several  agency  officials  Indicated  that high levels
           of lead emissions were a  primary concern and that high  levels of
           airborne lead  could  adversely  affect  the health of nearby workers.
           Exposure to  lead  at the approximately 10  houses  In  the hills above
           the  site was thought  unlikely,  but necessary to  Investigate.

           EPA has included air monitoring in the RI.

      3.    Effects on  Workers'   Health.    Individuals  were concerned  about
           exposure through  Incidental  Ingestlon of  ground water obtained for
           Industrial  use and exposure to  airborne lead.

           EPA has included exposure scenarios for workers in the risk assessment for
           the site.

      4.    Cleanup Schedule.  Staff  from  Representative AuColn's office and a
           representative from  the Oregon  State  Public Interest Research Group
           expressed  dissatisfaction  that  cleanup  measures  had not   been
           implemented  earlier.

           EPA has attempted to evaluate the site and make a remedial decision in an
           expeditious manner. By focusing  on  the  soils  unit, a decision will  be made
           now.

      5.    Future  Development of the Doane  Lake Area,  the media  and   local
           officials  expressed  concern about  how the current pollution would
           affect  or  restrict future  uses  of the land*

-------
Future use restrictions are expected to be minimized by removing or treating
as much of the lead at the site as possible.

-------
     6.   Disposal of Dredged Materials from the River.  A  representative  from
          the Port of  Portland  indicated  the  Port's  concern about disposing of
          dredged materials from the Willamette  River  that might  be  found to
          contain contaminants from the site.

          The RI  included  an evaluation  of sediment around the outfall from East
          Doane Lake.

     7.   Environmental Investigation  of  Doane Lake Area.   A representative
          from the  Association of  Oregon Industries and  representatives  of
          elected  officials  indicated  concern  that  DEQ's  environmental
          Investigation  in  the  Doane  Lake  area  could  decrease  future
          Industrial  development and Jobs In the community.

          No reports  of decreased industrial development as a result  of  these
          investigations has been received by EPA.

     8.   Disposal of  Battery Casings.   An aide to Representative  AuColn's
          office expressed  dissatisfaction  that  battery casings  had  not  been
          removed from the  site.  Representatives  from the Portland Department
          of Public  Works  cautioned  that any  plan  to dispose  of  waste
          materials at'St. John's'Landfill would be unpopular.

          EPA  intends to  recycle as much of  the battery  casing components as  is
          feasible.
                                                                  \       •

     During the  Investigation  and  reporting phases of  the RI/FS, fact sheets
were produced and  mailed  out  to the community and the  press to  keep them
Informed of progress  at  the site.   EPA  and DEQ also consulted  by phone with
several prominent  community members about  Issues of  concern  shortly before
review and evaluation of the RI/FS produced by the contractor.

     Two public meetings  were  held  to  discuss  the  results  of these studies and
EPA's proposed  plan:  the  first on February  18th and  the second on March 10th.
The results of these meetings and comments received are discussed In the  next
section.

-------
                                        5

                                    SECTION C

          SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC COMMENT PERIOD
     The comment period was  held  from February 16, 1988,  to  March  18, 1988,
and  Included  two  public  meetings.  Comments and questions  raised  during the
NL/Gould public comment  period  on the draft FS  and the  proposed  plan  are
summarized  briefly  below.   Comments are grouped and  categorized  by subject.
Detailed comment letters from the PRPs are summarized, along with the  Agency's
response at the end of this section.

     Approximately 50  people  attended each of the  two public meetings.   Each
meeting consisted of  about 45 minutes of  presentations  followed  by question
and  answer  and  public  comment opportunities.   The  audience  questioned  EPA, the
potentially responsible parties, and their consultant. Dames  and  Moore, about
the  site,  the  studies, the alternatives,  and  the  Superfund process.   At the
first meeting,  citizens  requested  a  second public meeting and additional
explanation  by EPA  of  the  preferred  alternative  as  well  as  other
alternatives.    This resulted  In the second meeting.  For  that  meeting,  the
PRPs requested  an opportunity to make a presentation.   Dames  and Moore were
given about 20  minutes at  the  second meeting  to  present their  results, and
evaluation  of  the remedial  alternatives.   Transcripts  of both meetings  are
available in the Administrative Record.

     After  reviewing  all  the comments  received  during  the public comment
period,  EPA has determined  that  residents of the  local  communities,  local
environmental  groups,  and  the  Oregon Department  of  Environmental  Quality
strongly support EPA's proposed plan.


Preference for Remedial  Alternative


     A  total  of  21  comments  were  received  supporting  EPA's  proposed
alternative and recommending the long range cleanup of the  site.   In   addition
to their support,  the following more detailed comments were made:


1.    The Northwest District  Association's  Health  and  Environment  Committee
     prefer Alternative  IOC.   However,  they  recommended  that  the selected
     remedy be  expanded  to clean up all pollutants  In  the  qroundwater and
     provide  continuous  qroundwater  and  air  monitoring  to ensure   that
     contaminants  do not migrate Into the environment.

     EPA Response:  The intent  of  the selected remedy Is  to  Insure that all
                    health   and  environmental  hazards posed  by  sediments.
                    soils,   and  casings  at  the   site  are  addressed  by

-------
                    treatment.   Monitoring and control of  air  emissions will
                    be a  priority during  remedial  design, and  groundwater
                    issues will  be  resolved  at  the   conclusion  of  the
                    groundwater  studies  planned  for  later this  year  (see
                    Section D).

2.   The Oregon Department of Environment Quality recommends Alternative IOC.
     DEO does not feel that  Alternative  2C will  be  satisfactory  to  the  state.
     If 2C Is implemented, there  is a high probability that the site would be
     revisited under the  state's  new Superfund  authority.

     EPA Response:   These  and other concerns about  Alternative 2C contributed
                    to EPA's choice  of  the  selected   remedy  described  In
                    Section VI  of the ROD.

3.   The Oregon  State  Public  Interest Research  Group (OSPRIG) preferred  a
     complete cleanup of  the  site.   Of the alternatives described In  the FS.
     they preferred  and recommended implementation of Alternative IOC.   OSPRIG
     raised questions about  how  thorough the  site characterization was and
     supported additional, more  comprehensive, qroundwater  studies.  Concerns
     were expressed  with   any solution  leaving  hazardous  materials  on  site.
     since the  site  is within  the 100  year  floodplaln  of the  Mlllame'tte
     River.  OSPRIG  also  expressed concern about site access  and  casual .
     exposure to the hazards at  the  site,  and  that  there are no  signs  warning
     of the presence  of hazardous waste at the  site.  OSPRIG also recommended
     setting up a working task group made up of citizens,  local officials, anlf
    'academics.

     EPA Response:   The selected  remedy  will address  the  contaminated  soils,
                    sediments,  battery casings, and other solids.  The current
                    information available on the  surface  and  groundwater  at
                    and around  the site  Is  Insufficient to make  a decision on
                    how to clean up those  areas at  this  time.   EPA  will
                    propose  additional   remedial  measures  for  ground  and
                    surface water,  If  necessary,  after further  studies are
                    complete  next year  (see section  0).

                    The company  has  been asked to take measures  to restrict
                    access and  to warn  of the presence of hazardous  materials.

                    Working  task  groups  consisting  of  citizens,   local
                    officials,  etc.,  have worked  In  some  communities  and may
                    be  set up for the Gould site  If  there  Is enough  Interest.

     4.   Several  other  citizens  expressed  support   for  the  preferred
          alternative and  added  their  opinion  that the community would only
          accept solutions that fully addressed toxicity  and mobility  of both
          surface and subsurface  contaminants.

          EPA Response:   The  selected  remedy  Is Intended  to reduce   the
                        mobility,  toxicity and volume of  contaminants  to the,
                        maximum  extent practicable.

-------
5.   The PRPs and their representative, recommended Alternative 2C.
     EPA Response:
Alternative  2C  would not  meet the Superfund mandate  to
reduce  toxicity,  mobility,  and volume  to  the  extent
practicable  as   well  as   the  selected  remedy.   This
recommendation and other  concerns  are addressed  In  more
detail  1n  letters from  NL  Industries  and Gould.  A summary
of the concerns raised  in  those letters  as well  as  EPA's
detailed responses to  those  concerns  are  Included at  the
end of this section.
Technical Concerns/Questions Regarding Remedial Alternatives
1.    Resident expressed concern about reliance  on  Institutional  controls for
     the site.
     •••••••^•••^•^MMV                 ^

     EPA Response   EPA does  not  believe that  Institutional  controls alone
                    will  be protective If the contaminated material  remains on
                    site  untreated.   However,  Institutional controls  may be
                    necessary in addition to the  selected  remedy  to  ensure
                    protection of  public health.

2.    Citizen asked what lead  standard will  EPA use at this site, the  current
     standard or a new standard if one is proposed/promulgated  before  remedial
     action starts at the  site.

     EPA Response:  The selected remedy  1s  based  on the  current lead standard
                    (50 parts per  billion).   EPA will  consider  changing to any
                    new standards  if  they are  more protective  of human health
                    or the  environment.

3.    Citizen asked whether  the selected  remedy would  result 1n creation of a
     hazardous  waste landfill  by fixing  the  lead In the soil.
     EPA Response:
The  proposed  plan  would not  Involve creating  a RCRA
(hazardous waste)  landfill.   The  contaminated materials
would be  treated  In such a way  that  they would  no longer
have the properties that would make them a hazardous waste.
     Citizen asked whether there  would  be any sodium hydroxide problems with
     the preferred alternative.
     EPA Response:
There should  not be  any sodium  hydroxide  problem.   A
treatment facility  on the  site would be constructed  to
treat the 20,000  yards  of contaminated soils.   Then  the
clean material  would be  covered with some  Imported  top
soil and capped with new growth vegetation.

-------
5.   Citizen asked whether  the  technology  needed to recycle  lead  out  of tha
     casings 1s currently available.

     EPA Response:  Pilot  tests  have  shown  that  recycling  Is  possible.
                    Additional   design  work  will  be done  to apply  the
                    technology to the Gould site.

6.   Citizen asked how long monitoring  would  continue.

     EPA Response:  Under Superfund  law,  monitoring  may continue for  an
                    extended period  of time.   Under the new law, EPA  Is
                    required to re-evaluate the site once every five years to
                    determine if additional  clean up Is  necessary.


7.   Citizen asked whether Alternative  IOC  will involve draining the lake and
     dredging all  the sediments.

     EPA Response:  Alternative IOC will  involve dreo:ing the sediments out of
                    the lake, not draining  the  lake.

8.   Citizen asked whether  draining  the  lake  to reach contaminated bottom
     sediments  would  be easier  than dredging  sediments  and then  treating them.

     EPA Response:  No, because the  lake basically  represents the surface of
                    the groundwater at  the  site.   If the  lake was  drained, 1&
                    would re-fl11.

9.   Citizen asked what current technology Is  available to remove  sediments In
     the lake.

     EPA Response:  Options would Include a variety of  dredging  systems.   This
                    Is one of  the  items  that will  be dealt  with  1n the design
                    of the selected remedy.

10.   Citizen asked about the history  of filling Doane Lake and how much  of It
     has been filled  with  battery  casings  and  when  was  the last time  1t was
     routinely  done.

     EPA Response:  Based on dated aerial  photos  taken  throughout the years,
                    significant areas of the lake have been filled.  The  other
                    remaining fill  Is  just a variety of  different types  of
                    material.  ML  Industries says the last time  casing were
                    used as fill  was  1972.

-------
 11
     Citizen asked whether the aquifer has been examined for  lead  and whether
     It has ever  been  examined In times of  overflow  to see how much lead Is
     going Into the river.
     EPA Response:
                    River Impacts have been estimated based on discharges from
                    the overflow storm drain for East Doane Lake.
12.  Citizen asked about whether there was sufficient site characterization.
     EPA Response:
                    EPA feels  the  site characterization was sufficient  to make
                    a decision about  soils,  sediments,  and battery  casings.
                    There still  Is  contaminated groundwater at the sfte and  we
                    do not feel  that  the  situation  there  has  been adequately
                    addressed.   Additional   groundwater  studies  are being
                    planned.
13.  Citizen asked about the future use of the property.
     EPA Response:
                    The future use of the property wi •*  depend on  the success
                    of  the   remedial  action.   It  Is   likely that  some
                    institutional  controls  or  restriction  on  use of  the
                    property will be  part of the final remedy;  however, the
                    full extent of those controls will  not be determined -until
                    later.
     EPA Response:
Costs/Funding

1.    C111zen requested information on costs and who would pay for the cleanup.

                    Since the.PRPs  are  conducting the RI/FS, EPA  will  first
                    negotiate with  the  PRPs  to arrange to have  them pay for
                    the cleanup as  well  as for  any costs  Incurred  by  EPA
                    during the cleanup.

                    If negotiations with  the  PRPs fall monies could come from
                    the federal  trust fund set up for Superfund.
2.
     Citizens asked several  questions
     for the alternatives.
about the basis  of the price estimates
     EPA Response:
                    Cost estimates are based on Superfund program guidance  and
                    general  cost  estimation guides.   The  basis  for  these
                    specific cost estimates  Is  given In Appendix C  of the  FS
                    report.

-------
                                       10


Public Participation


1.   Citizens at the first  public  meeting expressed a concern  that  they had
     not had enough  time  or information to fully comment on the Issues.  As a
     result, they requested a second public meeting and additional explanation
     by EPA of the preferred alternative and Alternative 2C. .

     EPA Response:   The first public meeting was held at the Northwest  Service
                    Center,  Thursday,  February  18,  1988,  to  explain  the
                    results  of   the  Investigations  and  to discuss the
                    recommended   remedial   alternatives.   In  response   to
                    requests  from   the  citizens,  EPA  provided  additional
                    materials written  In   less-technical  language  explaining
                    the alternatives and  scheduled a second meeting.  A second
                    public meeting  was  held on March 10, 1988.

2.    The PRPs requested an opportunity  to  speak  at  the  second  public meeting
     and describe in their  own  words their reasons for preferring Alternative
     2C (Additional  concerns raised by the  PRPs  are  summarized and  responded
     to at the end of this section).

     EPA Response:   At  the  second  meeting,  EPA  allowed Dames  &  Moore  .(the
                    consulting firm .which performed the RI/FS)  to'make  a brief
                    presentation describing  the  relative merits  of  various
                    alternatives.  At both meetings, citizens  were Invited ton
                    address  questions  directly  to  the  PRPs   and  their
                    consultants  as  well  as  to  the Agency.  (At  the first
                    meeting, the PRPs  and  consultants  were given  the  same
                    opportunity  as  all  others  in attendance to make  comments
                    on  the record.)

-------
                                       n
Health Issues
1.
Citizens expressed concern regarding long
to contaminants at the site.
term health effects of exposure

     EPA Response:  Lead and the other contaminants at  the  site  are known to
                    cause developmental problems  In  children  who are exposed,
                    as  well  as  renal  problems.   Under  the  No  Action
                    Alternative, the  Endangerment  Assessment  prepared for NL
                    and Gould showed exposures above  health  based levels.  The
                    selected remedy would reduce the risk of exposure to below
                    these levels.

2.   Citizen asked whether  women,  particularly those of  child-bearing age.
     were more sensitive  to renal  problems  and other potential  adverse health
     affects,  and whether that was  taken Into account In the studies.


     EPA Response:  Based on the Endangerment Assessment, children are seen as
                    the most sensitive group In terms of lead  Impacts.

3.   Concern regarding reproductlvely-aged persons working and living close to
     the site  and about renal toxidty.                          x      - .

     EPA Response:-  In  the  Endangerment  Assessment,   altered   testlcular
                    function and renal  dysfunction were  among  the  reported
                    effects of elevated blood lead levels.

4.   Citizens  and- neighboring businesses have raised concerns about  the  health
     and safety of nearby workers  during and after any remedial  action.

     EPA Response:  EPA has  expressed  Its  Intent  to  Implement  the  selected
                    remedy  In  a manner that  Is fully  protective of public
                    health, based  on the National  Ambient Air Quality  Standard
                    for lead.  Specific measures  will  be part of the remedial
                    design which will   be  presented for  public comment before
                    Implementation.

-------
                                       12
Comments/Concerns Raised by Neighboring Businesses

1.   Since ESCO  corporation  boundary 1s Immediately adjacent to the NL/Gould. '
     Inc. site. ESCO objects to any  requirements  which  might be Imposed  upon
     ESCO  or  Its   property  in  connection  with  proposed   EPA  cleanup
     recommendations concerning the remedial work at the Superfund site.

     EPA Response:   Noted.

2.   Pennwalt  Corporation  wished  to  make  a correction  to  the  FS  report.
     Pennwalt  has  never manufactured or even handled sodium  arsenlte  or any
     other substances containing arsenic.  The plant Is not  a hazardous waste
     generator and  does not  customarily ship wastes to Arlington.   The report
     also Infers that  brine  purification residue Is a  hazardous  b -product.
     The residue consists of calcium carbonate  and magnesium  hydroxide  and  has
     a pH of 10 to 11.   This material Is not hazardous waste.

     EPA Response:   Noted.


3.   Richard Bach,  attorney  representing the Northwest National Gas Company.
     and James  Benedict,   attorney   representing  Rhone-Poulenc.  vine,  both
     commented that  it was their understanding  that  actions and records  to
     date regarding the NL/Gould site would not be part of  the Administrative
     Record for the planned groundwater study.


     EPA Response-:   An  Administrative  Record for  the  Record  of  Decision for
                    the groundwater/surface  water unit at  this  site  will be
                    developed.   That Administrative Record  will  contain those
                    documents  necessary  to support  appropriate  remedial
                    actions.

4.   The attorney for Rhone-Poulenc. Inc. raised concerns about  access to the
     Rhone-Poulenc   property  during  RD/RA  and  about  possible Institutional
     controls which might  affect company property, and stated while the  Issues
     were not resolved, the company Is willing to discuss those Issues.

     EPA Response:   EPA considers  this  additional  reasons   to  question the
                    effectiveness of Institutional controls  as  a  means of
                    protecting public health at this site.

-------
Comments from Potentially Responsible Parties

Concerns raised  In  the  comment letter from NL  Industries,  dated March  15.
1988, are detailed and responded to below:
1)   The  site  presents  little
     environment.
             if  any  threat to  public health  or  the
     EPA Response:
The Endangerment Assessment prepared by the  PRP's  does In
fact  show  that under the  No-Action  Alternative  AICs are
exceeded for some of the exposure scenarios.
2)   The site would not qualify today for Inclusion on the NPL.

     EPA Response:  This statement Is untimely and moot.   Since  the site J_s on
                    the NPL, EPA  is  required  by law  to conduct a RI/FS study
                    and take  appropriate remedial  action  consistent  with
                    CERCLA.   The ROD  and  Selected  Remedy reflect  the agency's
                    attempt  to do that.   Based on  the Endangerment  Assessment
                    prepared by  Dames &  Moore  for NL and Gould,  EPA  has
                    determined  that  the   No-Action   Alternative  pos.es
                    unacceptable health  risks,  and therefore remedial  action
                    Is required at this  site.                    >       " -

3)   As indicated In the FS. only Alternative  2C Is rated as "high"  across-the
     board.

     EPA Response:
As  indicated  in the Detailed  Evaluation  of Alternatives
section of the Record of Decision, EPA's evaluation of  the
Alternatives differs from NL's.
4)   Alternative IOC will  result in recycling 3 per cent of material.
     EPA Response:
Using  Information  from the  FS,  Alternative  IOC  Is
estimated to recycle over 1,000 tons of lead, or about  251
of the total lead In the battery casings.
5)   Implementation of Alternative IOC Involves substantial  air emissions.

     EPA Response:   EPA has  reviewed  Attachment 2  of NL's  letter.  Several
                    assumptions and approaches  used  1n  the report  lead  to
                    conservative emission  estimates and correspondingly  high
                    estimated ambient  lead concentrations.   Namely:

        * Some of  the emission factors  taken from AP-42   Include  general
          emission  factors that are used to represent a variety of processes.
          Including blasting.   As  a  result,  these factors  are considered
          conservative.

        * A variety  of  controls  are  available that will   provide dust
          suppression   In  excess of  that  assumed   by  NL.   These  Include
          biodegradable oil  based  dust  suppressants,  controls on  vehicle
          speeds,  controls on  drop heights,  and  coverings over  specific
          fugitive  emission points.   In  particular, emissions from conveyors,
          which are responsible for most  of  the estimated fugitive  emissions
          from remediation,  are particularly  well  suited  to  fugitive dust
          controls.

-------
                                       14


        * The modeling  performed  in the report was  done  without  the use c*
          on-site or local metorological data, despite the fact that data were
          available for  use in the  model.   Instead, worst case assumptions
          were used to genrerate a one-hour average, which  was  later adjusted
          to  a  quarterly  average.   This is an  inappropriate  use  of the ISC
          model   and  leads  to  overly conservative concentration  estimates.
          Other  assumptions in  the modeling  which  lead  to conservative
          estimates include: simulation of sources as area sources rather than
          volume sources; and  the close proximity of receptors to assumed area
          source boundaries,  which  the user's  manaul  for  the  ISC model
          indicates will  generate  higher estimated concentrations.

     In conclusion, EPA's opinion  is that NL's emission rates  are
conservative and that the emissions  from Alternative IOC can  be  controlled  to
such an extent  that  the  operations  should comply with the  lead NAAQS.   It  Is
EPA's Intent to comply with  this standard  1n Implementing Alternative IOC.

7)   Alternative IOC relies  on unproven technology.

     EPA Response:   The battery recycling  equipment  *.;sed In the  pilot studies
                    was conventional machinery.  During the pilot studies that
                    equipment was  able to recycle  the material from the Gould
                    site.    EPA recognized  that there were some materials
                    handling problems associated  with  those  tests  and  that
                    those problems will require additional  design work before
                    a facility is  constructed at the Gould  site.   However,
                    is  EPA's  opinion  that  the   basic   technology  for
                    implementing IOC is proven.

8)   EPA and DEQ have failed to follow basic  administrative and environmental
     law principles in selecting their preferred alternative.

     EPA Response:   EPA and DEQ, after reading  the draft FS,  expressed  support
                    for an  alternative  that  represented  a variation  of an
                    alterantlve presented  In  the  draft  FS.   It was  requested
                    that this alternative  be further developed so that  EPA  and
                    DEQ could  evalutate It In more detail.  During subsequent
                    meetings In January,  NL  and Gould provided  EPA- and DEQ
                    with  sufficient  additional  Information that the  agencies
                    were further able to evaluate this alternative and  prepare
                    a proposed plan for  the  public.  This Information was
                    provided to EPA  prior  to the delivery  of the  final FS
                    report.

-------
                                       15
9)   EPA and  DEQ Ignored  the  recommendations  of  the  report prepared  by
     Environmental  Standards regarding risks  from remedial  actions.

     EPA Response:   EPA evaluated the report along with the FS.   As the record
                    of decision shows, EPA's evalautlon  of the  Alternatives
                    differs  from  that  contained  In  FS   report.   EPA's
                    evaluation  differs from  Environmental  Standards on  this
                    particular  issue  in that EPA  has expressed  Its Intent to
                    implement IOC In  a manner  that  Is  fully protective  of
                    public health.   During design estimates  will be made  of
                    fugitive emissions from the  designed facilities and  If  1t
                    appears  that  estimated  fugitive emissions  result  In
                    exceedences of the NAAQS for  lead,  design modifications
                    may  be  required.  In addition,  during remediation.  If
                    violations  are  noted, activities  will  be  halted  or
                    curtailed.   By doing this EPA expects to minimize off site
                    deposition  of  lead such  that  the spread  of  contamination
                    from the site on  to  adjacent  properties  should  not  occur.
                    By "spread  of contamination"  EPA means  a  statistically
                    significant increase  above backgrrjnd  levels.

10)  Alternative IOC  is not cost effective and results In costs  of $11.000 per
     ton of recyclables.
        " •"     	^"                                        .         \

     EPA Response:   The $11,000 per  ton figure  appears to  based  on  the total
                    cost for entire remedy;  the cost for the recycling portion
                    alone appears  to be far  less  than this.  For example,  the
                    detailed costs  for  this  alternative  Include  estimated
                    costs of over  $2,500,000 per  year  to dispose  of  the
                    material  at a  hazardous  waste landfill.   EPA has  stated
                    that It Intends  to minimize  the  amount of material  that
                    requires RCRA  disposal.   Also,  In  the  screening  of
                    alternatives  section  of the  Record  of Decision,  EPA states
                    that the higher costs of Alternative IOC  are commensurate
                    with the higher  long  term effectiveness  and  greater
                    reduction In volume of lead  In the waste stream achieved
                    by this remedy.

11)  Institutional  controls can be  used  effectively, those controls  are as
     much a part of IOC as they are  of 2C. and  they are  widely accepted by EPA.

     EPA Response:   Although Institutional controls  are mentioned  In both IOC
                    and 2C, the controls  differ  In the extent to which they
                    are part of a complete remedial  package.   In IOC controls
                    will  be used  In  areas where  contamination has been treated
                    to the maximum  extent practicable,  while 1n 2C  they are
                    not.   In addition,  EPA   questions  the effectiveness  of
                    Institutional  controls,   particularly  on  portions  of the
                    site that are  not owned  by Gould (see  comment  #4 on page
                    12).

-------
                                       16


12)  Has EPA/DEQ  considered  the  impacts  of utilizing  some  80.000 yards  of
     landfill space.

     EPA Response:  EPA and  DEO  have  considered the Impacts of  disposing of
                    80,000 yards  of material In a  RCRA landfill  and  consider
                    them  to  be an  undesirable  requirement associated  with
                    implementing  the selected remedy.   EPA  Intends  to devote
                    extensive design effort to  developing  a process  that will
                    minimize  the  amount of material that will  require disposal
                    in a  RCRA  landfill.   If based on the results of the design
                    phase, it  appears  that  the  goals of treating all of the
                    battery  casings  and  minimizing  the amount of material
                    requiring RCRA disposal  are  not compatible,  an additional
                    public comment period will  be  established, and the  Record
                    of Decision may be  modified.   At  such  time, EPA would
                    present to the public other options which are equally or
                    more protective of  public  health that allow  this  material
                    to remain on  site.

13)  The discrepancies between EPA's decision  at  this  site  and EPA's decision
     at the Newport Dump site were noted.

     EPA Response:  In each case  It appears  that  EPA. evaluated  the  site- In
                    accordance with the  requirements  of  CERCLA.  Using  the
                    same approach  at different  sites can  result In different
                    decisions,  depending  on   the   specific  alternatives
                    available  for  remediation,   the specific  health  and
                    environmental  threats,  and  the  laws and  regulation  that
                    are considered ARARs.

14)  EPA modified Alternative IOC  in  presenting  It  to the public.

     EPA Response:  EPA described  additional  work  that was being done   on
                    cleaning  ebonite to point out  that additional steps  that
                    were possible  aside from the washing steps  Include  In the
                    pilot  studies.  It Is  EPA's Intent to design a  treatment
                    plant  that Is  generally consistent with  the  processes
                    presented In  the  FS by NL  and  Gould.

15)  Inconsistencies were  noted  In the Supplement to  the Draft Feasibility
     Study of Cleanup Alternatives for  the NL/Gould Superfund Site.

     EPA Response:  The _.ie Inconsistency that has  not  been  addressed earlier
                    In  this   response  Involves  differences  between  the
                    evaluation of  the protectIveness   of  the  cap  under
                    Alternatives  2C and  IOC.   Although the  cap under 2C  Is
                    thicker,   the  overall  protectlveness of  a cap  In this
                    situation  Is  not considered as high because of the higher
                    levels of contamination that will  exist  under the cap  In
                    Alternative 2C.

-------
                                       17

Concerns  raised  in  the comment letter from Gould, Inc., dated March 18, 1988,
are detailed and responded to below:

1)   Alternative IOC Is so dangerous  to  human health and welfare  and  to the
environment that  It  subjects  EPA  to massive  third-party  liability  for personal
Injury and property damage.

     EPA Response:  As  stated  elsewhere   In  this  Record  of  Decision,  EPA
                    intends to  implement  IOC  in a manner  that Is protective of
                    public health and complies with ARARs, Including the NAAQS
                    lead  standard.   Given  EPA's  Intent  regarding  the
                    implementation  of  IOC,  it Is  not anticipated  that the
                    agency will  have  to  rely on  any shield provided by the
                    Federal Tort Claims Act or liability limitations  provided
                    for within CERCLA as  amended.

2)   EPA's proposal  to select  Alternative IOC is  not supported by the record.
is Inconsistent with statutory and  regulatory criteria,  and will be overturned
by judicial review.

     EPA Response:  EPA believes  that  the selected  remedy  Is  consistent with
                    statutory and  regulatory criteria.   The  standard   for
                    judicial  review is the  arbitrary and capricious standard.
                    EPA's selection must  be upheld unless  the objecting' party
                    can  demonstrate on the  Administrative Record  that the
                    remedy is  arbitrary   and  capricious  and   an  abuse   of
                    discretion or  otherwise not  In  accordance with the' law.
                    The agency believes  that its declslonmaklng  process as
                    demonstrated  by  this Administrative   Record  is both
                 •  deliberate and contemplative  of all  considerations.

3)   Gould feels that  for  EPA  to select  Alternative  IOC  would be arbitrary.
capricious, unlawful,  and  an abuse  of   decretlon  that will  violate  all
applicable criteria for remedy selection.

     EPA Response:   See response above.

4) .  Gould feels it would be arbitrary, capricious,  unlawful,  and  an  abuse of
discretion to  select an alternative not supported  by the ROD

     EPA Response:   See response to #2.

-------
5)   Gould feels EPA cannot properly take public acceptance into account wher
It has misrepresented the record to the public.

     EPA Response:  The  public  hearings  were recorded  and PRP's were given
                    sufficient opportunity to present their  alternative.   The
                    agency has  presented  both  Its  views and the views of the
                    PRPs to the  public  during  the  comment period, and  has
                    complied  with  all  requirements for public  notice and
                    comment as established by CERCLA as  amended.

6)   Gould feels  it  was  unlawful  for EPA to add  the  Portland site  to the
National Priorities List ("NPL")

     EPA Response   This statement is untimely  and moot.  Since the site |js on
                    the NPL, EPA is required by law to  conduct  a RI/FS study
                    and  take  appropriate  remedial  action  consistent with
                    CERCLA.  The ROD and Selected Remedy reflect  the  agency's
                    attempt to do that.

7)   If Alternative IOC is selected and implemented. EPA and the PRPs  will
potentially be subject to massive and costly litigation.

     EPA Response:  This  concern  as  raised by  Gould  refers   to  eithe'r.
                    litigation  brought  by the  PRP's  against the  agency or
                    third party  liability actions  brought  by other  parties.
                    As to  third  party  liability actions, as stated elsewhere^
                    in this Record of Decision, EPA Intends to Implement IOC™
                    in manner that is protective of public health  and  compiles
                 •  with ARARs,  including the  NAAQS  lead   standard.   Given
                    EPA's  Intent  regarding  the  Implementation of  IOC,  It  Is
                    not anticipated that the agency will have  to rely on any
                    shield  provided  by  the Federal  Tort  Claims  Act  or
                    liability limitations  provided  for within  CERCLA  as
                    amended.  As  to  PRP generated  litigation,  EPA considers
                    the risk of  such  litigation to be  endemic  to  the CERCLA
                    process, especially  In  such Instances  where  EPA's  proposed
                    remedy differs from  that  of the PRP's.  Such  lltlgatlve
                    risk should not  bear weight In arriving at an appropriate
                    remedy under CERCLA as amended.

-------
                                       19

                                    SECTION  D

                               REMAINING CONCERNS


     This section describes  issues  and concerns that EPA has not been able to
address to date or must continue to address  during RD/RA.

     •    How contaminated is local  qroundwater and what will be done about It?

          EPA Response:  EPA was unable to fully address this since additional
                         investigation is required to fully  characterize local
                         groundwater and the impacts  of surrounding Industries
                         and  to evaluate   feasible  remedies.   Additional
                         studies of a  wider area are In the  planning  stages
                         and results are expected by  Spring or Summer of 1989.

     •    Citizen asked what  water  quality  standards the remedy would have to
          achieve, and  if  we  did  not know,  how  could  EPA  select  a  cleanup
          alternative.

          EPA Response:  EPA  has  decided to  select  a  remedy  for soils,
                         sediments,  and casings, but to  defer the  groundwater
                         remedy until  we have  additional Information.  Cleanup
                         and monitoring  levels  for ground  and  surface  water
                         will  be determined  at that time.
     •    Hho wi11 pay for the remedy?

          EPA Response:  EPA  was  unable to  address  this  since  negotiations
          with the PRPs remain unresolved.

     Citizens rasied  the following  concerns and  questions  regarding details of
the design  of the  proposed  plan/selected  remedy  which will  have to  be
responded to In the remedial  design process:

     •    How will  EPA take  Into  account  BPA  power lines  across adjacent
          properties which must provide uninterrupted electrical service?

     •    If lead is binding to the soil. Is there a saturation  point and how
          long will  It  be  before the  lead/soils  reach the  saturation  point and
          start leaching out and contaminating qroundwater?

     •    During cleanup,  will  the  soils at the edge of the Gould property
          would be disturbed?

-------
                                       20
     •    Hhat precautions will  be  taken to control dust  and  airborne  lea
          emissions when materials  are  excavated and/or transported from  th
          site?  (Some  related  issues  were addressed In answer  to  the  PRPs
          concerns)

     •    Is  there a  risk  that  air  emissions  from  the  site  could  be
          electrically  conducted  and cause a  risk to/from  the  neighboring
          power lines?

     •    Has EPA  examined  the  existence or lack thereof of blomethylatlon of
          lead and  arsenic  and  does the selected  remedy prevent any further
          blomethylation.

     EPA Response;  EPA will address all the above issues during remedial design.


Citizens also requested the following:

     •    That EPA keep the public,  including workers 1n the area. Informed  In
          a timely  manner  of the results of engineering studies, pilot  tests,
          and other aspects  of  remedial design of  the  selected  remedy.  EPA
          will  prepare  and  distribute  fact  sheets  periodically and   as
          appropriate.                                                  . .

          EPA Response:  EPA will provide  an  opportunity for public comment,
                         including a meeting,  to discuss the remedial  design
                         before it is approved or completed by EPA.           ,

     •    That EPA  continue  with the groundwater  studies  being  planned and
          report back to the community.

          EPA Response:    The  studies   willbe  done and EPA will  provide a
                         public comment period  and meeting  when results are
                         available.

     •    That  EPA carefully  monitor  and control  air emissions  during
          remediation to minimize airborne lead emissions.

          EPA Response:  EPA will specify  and If  necessary  conduct airborne
                         emissions  monitoring and  control  measures during
                         RD/RA.

-------
      APPENDIX C
ADMINISTRATIVE RECORD

-------
                                                                MAR ?.S-1538
       Department of Environmental Quality
       811 SW SIXTH AVENUE. PORTLAND. OREGON 97204-1334  PHONE (503) 229-5696
                                       March 28,  1988


Robie Russell
Regional Administrator
Environmental Protection Agency
1200 Sixth Avenue
Seattle, WA  98101

      yj                          Re:  Gould Proposed  Plan  Certification

Dear Mr. Rurfsell:
The Oregon Department  of  Environmental Quality (DEQ)  has  carefully reviewed
the EPA proposed plan  for the soils unit as described in  the  draft final
record of decision (ROD).  The Department concurs with EPA's  selected   ' -
remedy based on alternative IOC as satisfying the statutory requirements for
a remedy as required by the State of Oregon.  It has  been determined that
the proposed remedial  action complies with the applicable or  relevant and
appropriate requirements  (ARARs) as identified to you in  the  Department's
letter of March 7,  1988.

The alternative based  on  IOC maximizes the use of recycling technologies in
providing a permanent  solution to the contamination problem at the Gould
site.  This concept is in keeping with the intent of  Oregon's "superfund"
legislation.

Department staff are available to provide you additional  information,  if
necessary.  The appropriate DEQ contact is William Renfroe, (503)  229-6900.

                                       Sincerely,
                                       Fred Hansen
                                       Director
UTR:f
ZF3002
cc:  Mike Downs, HSU
     Kurt Burkholder,  AG
     Dick Nichols, WQ
     Ron Householder,  AQ
     Tom Bispham, AQ
     Chuck Findley, EPA
     Dave Tetta, EPA
     Mike Gearheard, EPA 000
     William Renfroe,  HSW

-------
         APPENDIX 0
STATE LETTER OF CONCURRENCE

-------
         APPENDIX 0
STATE LETTER OF

-------
    NEIL OOLOSCHMIOT
                                                         MAR 29 1938
                                                          OFFICE OF
Department of Environmental Quality      q£GIONAL ADMIN!

811 SW SIXTH AVENUE. PORTLAND, OREGON 97204-1334 PHONE (503) 229-5696
                                                 March  28, 1988


          Robie  Russell
          Regional Administrator
          Environmental Protection Agency
          1200 Sixth Avenue
          Seattle, WA  98101

                Si                           Re:   Gould  Proposed Plan Certification

          Dear Mr. Russell:
          The  Oregon Department of Environmental Quality (DEQ) has carefully reviewed
          the  EPA proposed plan for the soils unit as described in the draft final
          record of decision (ROD).  The Department concurs with EPA's selected   ' •
          remedy based on alternative IOC as satisfying the statutory requirements for
          a  remedy as required by the State of Oregon.   It has been determined that
          the  proposed remedial action complies with the applicable or relevant and
          appropriate requirements (ARARs) as identified to you in the Department's
         •letter of March 7, 1988.

          The  alternative based on IOC maximizes the use of recycling technologies in
          providing a permanent solution to the contamination problem at the Gould
          site.  This concept is in keeping with the intent of Oregon's "superfund"
          legislation.

          Department staff are available to provide you additional information, if
          necessary.  The appropriate DEQ contact is William  Renfroe, (503) 229-6900.

                                                 Sincerely,
                                                 Fred Hansen
                                                 Director
          UTR:f
          ZF3002
          cc:   Mike  Downs, HSU
               Kurt  Burkholder, AC
               Dick  Nichols, WQ
               Ron Householder, AQ
               Tom Bispham, AQ
               Chuck Findley, EPA
               Dave  Tetta, EPA
               Mike  Gearheard, EPA 000
               William Renfroe, HSW
OEO-1

-------