EPA  Superfund
       Record of Decision:
                                  PB94-964642
                                  EPA/ROD/R10-93/069
                                  February 1995
       Harbor Island (Lead),
       Seattle, WA
       9/30/1993

-------
50272-101
 REPORT DOCUMENTATION
	     PAGE    	
1. REPORT NO.
EPA/ROD/R10-93/069
3. Recipient's Accession No.
4.  TUb and Subtitle
   SUPERFUND RECORD  OF DECISION
   Harbor Island-Lead,  WA
   First  Remedial Action	
                                          5.  Report Date
                                          	09/30/93
7.  Authors)
                                          8.  Performing Organization Rapt No.
       nlng Organization Nairn and Address
                                          10  Project T«»kWork Unit No.
                                                                    11.  Contract(C)orGrant(G)No.
                                                                    (C)
12. Sponsoring Organization Harm and Address
   U.S.  Environmental Protection Agency
   401 M Street, S.W.
   Washington, D.C.   20460
                                          13. Type of Report & Period Covered

                                             800/800
                                          14.
15. Supplementary Notes

    PB94-964642
16. Abstract (Limit: 200 words)

  The 400-acre Harbor  Island-Lead site is a man-made  industrial island in Seattle,  King
  County, Washington.  Land use in the  area is predominantly commercial and industrial,
  with residential properties to the west of the  site.   The site  lies at the mouth  of the
  Duwamish  Waterway on the southern edge of Elliott Bay, in the inland marine waterway
  known as  Puget Sound.  Ground water on Harbor Island currently is  not used for drinking
  water, and all water users on the island are serviced by the City of Seattle municipal
  water system.   Prior to 1985, the area consisted of tidal flats and a river mouth delta
  with some piling-supported structures.  Initial  construction of the island began
  between 1903 and 1905 when dredging  of the East  and West waterways and the main
  navigational channel of the Duwamish River occurred.   Since its construction, major
  activities  at  Harbor Island have included ocean  and rail transport operations,  bulk
  fuel storage and transfer, secondary lead smelting, lead fabrication, shipbuilding, and
  metal plating. Warehouses, laboratories, and office buildings also have been located on
  the island.   In 1937,  a secondary lead smelter  was  constructed  near the center  of
  Harbor Island.  In 1979, State investigations showed that the quarterly average ambient
  air concentration of lead from smelter activities exceeded the  Federal standard for

  (See Attached Page)
17. Document Analysis     a. Descriptors
   Record of Decision - Harbor Island-Lead,  WA
   First  Remedial  Action
   Contaminated Media: soil,  gw,  sw
   Key Contaminants:  VOCs (benzene, PCE, TCE,  toluene,  xylenes), other organics  (oils,
                       PAHs, PCBs),  metals  (arsenic, chromium,  lead)

   b.   Identifiers/Open-Ended Terms
   c.   COSATI Raid/Group
18. Availability Statement
                          19. Security Class (This Report)
                                    None	
                                                     20.  Security Class (This Page)
                                                               None	
          21. No. of Pages
                 102
                                                                              22.  Price
(See ANSI-Z39.18)
                                   Sf* Instructions on Reverse
                                                   OPTIONAL FORM 272 (4-77)
                                                         •ms-35)
                                                         I of Commerce
                                                                              (Formerly NTIS-35)
                                                                              Department^"

-------
EPA/ROD/R10-93/069
Harbor Island-Lead, WA
First Remedial Action

Abstract (Continued)

lead ninety-five percent of the time. Subsequently, in 1982, an EPA inspection identified
a significant volume of lead-contaminated soil at the onsite lead smelter  facility.  In
1984, the lead smelter ceased operations, but the facility later was subject to a RCRA
enforcement action in conjunction with the closure of a surface impoundment.  As part of
this RCRA action, ground water monitoring wells were installed and soil borings were
taken, which identified elevated concentrations of lead at the facility.   In 1985, State
investigations revealed numerous types of contaminants, including metals,  PAHs, PCBs,
petroleum products, and a floating product at the shipyard facility; all of which were a
result of past smelting and improper disposal activities.  In 1990, EPA required the City
of Seattle to clean contaminated sediment from its storm drain system on Harbor Island.
In 1991, EPA required a PRP to remove and dispose of approximately 80 drums of spent
electroplating solution off site.  EPA has divided the site into four OUs for remediation.
This ROD addresses the island-wide unit, which includes all contaminated soil, ground
water, surface water, and NAPLs, as OU1.  Future RODs will address the petroleum tank
farms, the Lockheed Shipyard, and the marine sediment from Harbor Island,  as OUs 2, 3,  and
4, respectively.  The primary contaminants of concern affecting the soil,  ground water,
surface water, and NAPLs are VOCs, including benzene, PCE, TCE, toluene, and xylenes;
other organics, including oils, PAHs, and PCBs; metals, including arsenic, chromium, and
lead.

The selected remedial action for this site includes excavating and onsite  stockpiling
of soil containing the highest levels of organic contamination  ("hot spots"), defined as
Total Petroleum Hydrocarbons  (TPH) greater than 10,000 mg/kg, PCBs greater than 50 mg/kg,
and soil with mixed carcinogens 'with a total risk greater than 10~^; treating 91,000 yd^
of TPH-contaminated soil onsite using thermal desorption; backfilling the  excavated areas
with clean soil; testing and solidifying, if necessary, the TPH-contaminated soil from the
treatment process prior to onsite disposal; capping the TPH-contaminated soil that passes
leachability testing, but contains contaminants with concentrations above  cleanup goals;
recycling, if possible, or disposing of the waste oil offsite; treating 2,000 yd^ of
PCBs-contaminated soil offsite using incineration or disposing of it at a  hazardous waste
disposal facility; disposing of 1,200 yd^ of organic "hot spot" soil with  risk greater
than 10~^ in a hazardous waste disposal facility; capping 40 acres of exposed contaminated
soil exceeding inorganic or organic cleanup goals with a low permeability  cap; repairing
existing asphalt and concrete surfaces to prevent infiltration of rainwater; pumping and
treating contaminated ground water and associated floating petroleum product onsite using
an oil water separator, followed by air stripping and carbon adsorption, with offsite
discharge of the treated water to a POTW and offsite recycling or disposing of the
recovered floating petroleum product; monitoring ground water; implementing engineering
controls to control runoff and prevent soil from being transported into the island  storm
sewer system; conducting training and meetings to inform workers of site hazards;, and
implementing institutional controls, including deed restrictions.  The estimated  present
worth cost for this remedial action is $40,192,548, which includes an estimated present
worth O&M cost of $33,000,000 for 30 years.

PERFORMANCE STANDARDS OR GOALS:

Chemical-specific soil cleanup goals are based on  risk standards set  forth in the State  of
Washington Model Toxics Control Act, and include TPH greater than  10,000 mg/kg; PCBs
greater than 50 mg/kg; and mixed carcinogens with total risk greater  than  10"  .
Chemical-specific ground water cleanup goals are based on protection  of marine  organisms
or human health from consumption or organisms with greater  than  10~6  risk, and  include
arsenic 36 ug/1; benzene 71 ug/1; cadmium  8 ug/1;  carbon tetrachloride  4.4 ug/1;  copper
2.9 ug/1; cyanide 1 ug/1; lead 5.8 ug/1; mercury  0.025 ug/1; nickel  7.9  ug/1;  PCBs  0.03
ug/1; PCE 8.8 ug/1; silver 1.2 ug/1; TCA 42 ug/1;  thallium  6.3  ug/1;  and zinc  76.6  ug/1.

-------
              RECORD OF DECISION

        DECLARATION, DECISION SUMMARY,
         AND RESPONSIVENESS  SUMMARY

                     FOR

      HARBOR ISLAND SOIL AND GROUNDWATER
             SEATTLE, WASHINGTON

                SEPTEMBER 1993
UNITED STATES ENVIRONMENTAL  PROTECTION AGENCY
                  REGION  10
              1200 SIXTH  AVENUE
             SEATTLE, WASHINGTON

-------
                        TABLE OF CONTENTS







  Section   	   Page



I.  Declaration



II. Decision Summary



  Introduction  	 .......  1



  Site Name, Location and Description   	  1



  Site History and Enforcement Activities   	4



  Highlights of Community  Participation  	  7



  Scope and Role of Response Action   	8



  Summary of Site Characteristics	   10



  Summary of Site Risks   	   16



  Remedial Action Objectives  	   24



  Description of Alternatives   	   26



  Summary of the Comparative Analysis of Alternatives     66



  The Selected Remedy   	:	   72



  Statutory Determinations  	   81



  Documentation of Significant Changes  	   85





Appendices



  Appendix A: Responsiveness Summary



  Appendix B: Method for Selecting Hot Spot Treatment Levels



  Appendix C: Administrative Record Index   (Renewed)

-------
                       List of Figures





Figure l: Harbor Island Location Map  	  2



Figure 2: Harbor Island Facilities  	  3



Figure 3: Harbor Island Operable Units  	  9



Figure 4: Surface Soil Exceeding Cleanup Goals  ...   27



Figure 5: Soil Hot Spot Locations   	   44



Figure 6: Contaminated Areas to be Capped   	   74







                       List of Table:;





Table 1: Potential Sources of Contamination   	  5



Table 2: Maximum Surface Soil Concentrations  	   17



Table 3: Summary of Industrial Exposure Intake Factors  18



Table 4: Summary of Commercial Exposure Intake Factors  19



Table 5: Summary of Noncancer Risk Calculations   .  .   22



Table 6: Summary of Cancer Risk Calculations  ....   22



Table 7: Remedial Action Objectives and Cleanup Goals   25



Table 8: Volumes of Soil Exceeding Cleanup Goals  .  .   26



Table 9: Soil Hot Spot Treatment Levels   	   43



Table 10: Organic Hot Spot Volumes	   46



Table 11: Present Worth Cost for Remedial Alternatives  71



Table 12: Soil Remediation Alternative Costs  ....   78



Table 13: Groundwater Remediation Alternative Costs     80

-------
                           DECLARATION
SITE NAME AND LOCATION

Harbor Island

Seattle, King County, Washington


STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected final remedial action,
for soil and  groundwater,  for the Harbor Island Site in Seattle,
King County,  Washington, which was chosen in accordance with the
Comprehensive Environmental Response, Compensation, and Liability
Act (CERCLA) (42 U.S.C.  §§  9601-96), as amended,  and,  to the extent
practicable, the National Contingency Plan (NCP). This decision is
based on the Administrative Record.

The Washington State Department of Ecology  (Ecology) concurs with
the selected remedy given  the specifics found at this site.

This decision document  excludes  three  separate  operable units on
Harbor Island:  the Shell, Arco, and Texaco petroleum tank farms;
Lockheed  Shipyard; and marine  sediments.    EPA  has  designated
Ecology  as  the  lead  agency  for the  three petroleum  tank farm
facilities  on the  island.   The  primary contamination  at these
facilities  is petroleum,  which  is  generally excluded  from the
definition  of a  hazardous  substance in CERCLA but is a regulated
hazardous substance under the State's Model Toxics Control Act
(MTCA). Ecology intends to issue a decision document for the tank
farm unit in early 1995.

The Lockheed  Shipyard on Harbor Island has been  designated as a
separate operable  unit  and EPA anticipates  that  it will issue a
separate decision  document for this unit in early 1994.  Marine
sediments around Harbor Island  have  also  been designated  as a
separate operable  unit  and EPA anticipates  that  it will issue a
separate decision document for this unit in  late 1994.


ASSESSMENT  OF THE FACILITY AND ADJACENT AREAS OF CONTAMINATION

Actual or threatened  releases of  hazardous substances from this
site, if not addressed by implementing the response action selected
in  this  Record  of  Decision  (ROD),  may present an imminent and
substantial   endangerment   to public   health,   welfare  or  the
environment.

-------
DESCRIPTION OF THE SELECTED REMEDY

The remedial action described in this Record of Decision represents
a final remedy for treatment of Harbor Island soil and groundwater,
except for those areas identified above as separate operable units.
The remedial  action  presented  in  this ROD  addresses the risks to
human health  and the  environment by:

   1)    Excavation and treatment of the soil containing the highest
        levels  of organic contamination  ("hot  spots").  These
        organic soil  hot  spots  are  defined  as Total  Petroleum
        Hydrocarbons  (TPH)  greater than 10,000 mg/kg, PCBs greater
        than 50 mg/kg,  and soil with mixed carcinogens with a total
        risk greater  than 10"*.   TPH hot spot soil will be treated
        en site in a  thermal desorption unit.   PCBs hot spot soil
        will either be sent off site for treatment (incineration)
        or be  disposed in a  hazardous waste disposal  facility.
        Organic hot spot soil with risk greater than 10"* will be
        disposed in a hazardous waste disposal facility.

   2)    Capping exposed contaminated  soil  exceeding inorganic or
        organic cleanup goals.   The  cap would  consist of  a low
        permeability    material   such  as   asphalt  to   prevent
        infiltration  of rainwater  and  reduce contaminant migration
        into  the  environment.  Existing  asphalt  and  concrete
        surfaces would be repaired to  also prevent infiltration of
        rainwater.

   3)    Invoking institutional controls which would require long
        term maintenance  of  new  and  existing  caps, warn future
        property owners of remaining contamination contained under
        capped areas  on their  properties,  and  specify procedures
        for handling  and disposal of excavated  contaminated soil
        from beneath the capped areas if excavation is necessary in
        the future.

   4)    Removal  of and treatment of floating petroleum product and
        associated contaminated groundwater at Todd Shipyards to
        prevent   its    migration   into the  marine  environment.
        Implementing   groundwater  monitoring  for  30 years,  with
        review of groundwater quality  trends  every  5  years to
        assess the effectiveness of  the selected  remedy.


STATUTORY DETERMINATIONS

The  selected  remedy  is  protective  of  human  health  and  the
environment, complies with state and federal requirements that are
legally applicable  or relevant and appropriate to  the remedial
actions,  and is  cost effective.   This  remedy uses  permanent
solutions  and  treatment  technologies  to  the  maximum  extent

-------
practicable for this site by treating the most highly contaminated
areas and capping less contaminated areas.  This remedy satisfies
the statutory preference for remedial actions that employ treatment
to reduce toxicity, mobility and
Because this remedy will  leave some hazardous substances on site
above cleanup goals, a  review of the site and its remedy will be
conducted within five years after initiation of the remedial action
to ensure the remedy continues to provide adequate protection of
human health and the environment.
                                                     7-
Gerald A. Emison                                         Date
Acting Regional Administrator, Region 10
U.S. Environmental Protection Agency

-------
                         DECISION SUMMARY
                HARBOR ISLAND, SEATTLE,  WASHINGTON
INTRODUCTION

The  Harbor Island  site, Seattle,  King County,  Washington,  was
listed on the National Priorities List (NPL) as a Superfund site in
1983 due to elevated lead concentrations in the soil from a lead
smelter on the island, as well as elevated  concentrations  of other
hazardous  substances.   The site  was  ranked  number 738  in the
Hazardous Ranking System (HRS)  based on a site assessment performed
by the United States Environmental Protection Agency (EPA)  in 1985,
pursuant  to  Section 105  of the  Comprehensive  Environmental
Response,  Compensation,  and Liability Act of 1980,  42  U.S.C.  §
9605, as amended, (CERCLA).

Pursuant to Executive Order 12580  (Superfund Implementation) and
the  National  Oil and Hazardous Substances Pollution Contingency
Plan   (NPC) ,  40  C-F-R-  Part 300,  EPA  performed  a   Remedial
Investigation/Feasibility   Study    (RI/FS).       The    Remedial
Investigation  (RI)  characterized  contamination  in  soil,  surface
water and  groundwater at the  facility.  The  RI .was completed in
1992.  A (baseline)  risk assessment was completed as part of the RI
and  evaluated potential  effects  of the contamination  on human
health and the environment.  The Feasibility Study (FS), completed
in   February   1993,   evaluated   alternatives   for  remediating
contamination.

SITE NAME, LOCATION,  AND DESCRIPTION

Harbor  Island is located about one mile  southwest  of  downtown
Seattle, in King County, Washington (Figure 1) .   It lies at the
mouth of the Duwamish Waterway  on the southern edge of Elliott Bay,
in the  inland marine waterway known as  Puget  Sound.   The island
occupies large portions of Sections 7 and 18 in Township 24, Range
4, and smaller portions of Sections 12 and  13, Township 24, Range
3.   The flat-lying island covers  an  area of  approximately 400
acres, and is  bordered on either side by the East Duwamish  and West
Duwamish waterways.   Elevation of the island varies from  about 12
to 15 feet above sea level. There are no wetlands on  the  island and
no endangered or threated species are known to inhabit the island.

Harbor Island is zoned exclusively  as General Industrial,  with the
exception of a 200-foot shoreline  zone  that is designated  as Urban
Industrial. Major facilities and structures on the island are shown
in Figure  2.   Almost the entire  eastern  side  of  the  island is
occupied  by  the Port  of  Seattle Terminal  18  cargo  container
facility.  The interior of the  island is occupied by  numerous small
to medium sized businesses including Seattle Foundry Company, Aspen
Points, Value Metal  Plating, Pacific Rendering,  Harbor Island

-------
       Figure 1
Harbor Island Location

-------
   Figure 2
Harbor Island

-------
Machine  Works,  and other  metal fabricating  companies.   Arco,
Texaco,  and Shell  maintain  petroleum  tank farms  in  the central
portion of the island.  Stevedoring  Services of America operates a
•^'pping and receiving dock with a cc. tainer storage area  along the
north portion  of the  island.  Todd Shipyard, a large shipbuilding
facility, occupies  the northwest corner of the island.  A portion
of the western side of the island is owned by Lockheed Corporation
and was at one time used for shipbuilding.  A concrete company, a
marina, and a fishing pier are located  on the southern part of the
island.  Commercial developments on the island include retail and
wholesale establishments, offices, restaurants, and parking areas.

Approximately  70   percent  of  Harbor  Island  is  covered  with
buildings,  roads,  or  other impervious  substances (e.g.,  concrete
pads, parking lots).  There are three main roads that run  north and
south:   llth Avenue SH, 13th Avenue SW, and  16th Avenue SE; and
three  streets that run east  and west:  Hanford,  Klickitat, and
Florida.  Union Pacific railroad lines extend through the  median of
llth Avenue SW and  16th Avenue SW.  Union Pacific also operates a
railroad  switching facility on  the northern  end  of  the island,
providing  railroad spurs which  lead  to barge loading docks and
industrial facilities.

Water and/or waste water generated on Harbor Island is transported
via the Metro Sanitary Sewer Collection System to the West Point
Metro sewage treatment plant.  Storm water runoff  is diverted into
the Puget Sound through a storm sewers.  Storm water is discharged
into the East and  West Waterways through municipal and  privately
owned outfalls around the perimeter of the island.


SITE HISTORY AND ENFORCEMENT ACTIVITIES

Harbor Island  is a man-made  industrial island covering about 400
acres  located at  the mouth  of  the Duwamish River  in  Seattle,
Washington.  Prior  to  1885, the area consisted of tideflats and a
river mouth  delta  with some piling-supported structures. Initial
construction  of the  island  began  between  1903  and 1905  when
dredging of the East and West waterways and the main navigational
channel of the Duwamish River occurred.  Dredged sediment was spread
across the present  island area to form a fill 5 to 15 feet thick.
This dredged  sediment was  later  covered with soil and demolition
debris from Seattle regrade projects. Since its construction, the
island has  been used  for commercial  and  industrial  activities.
Major activities have  included ocean and rail transport operations,
bulk  fuel  storage  and transfer, secondary lead  smelting,  lead
fabrication,   shipbuilding,   and metal  plating.    Warehouses,
laboratories,  and  office buildings  also have  been located on the
island. The  secondary lead smelter  was originally constructed on
Harbor  Island in  1937 and  was  located near  the center  of the
island.

-------
Concern over the levels of lead in the air, due to the operation of
the  lead smelter,  prompted several air monitoring  studies during
the  1970s.  A  study  conducted  in  1979  by  the  Puget  Sound  Air
Pollution Control Agency (PSAPCA) showed tha . the quarterly average
ambient air concentration of lead exceeded the federal standard for
lead of 1.5 A*g/m3 95% of the time. Subsequently,  a site inspection
conducted by EPA in 1982 identified a significant  volume of  lead
contaminated soil at the lead smelter facility. As a result of this
site inspection, the  island was listed on the tJPL in 1983.

The lead smelter ceased operation in 1984, but the  facility  later
was  subject to a RCRA  enforcement  action  in conjuction with the
closure  of a  surface   impoundment.   As  part  of  this  action,
groundwater monitoring  wells were installed  and  soil borings  were
taken to determine soil quality.  Elevated concentrations  of  lead,
cadmium and  sulfate  were  found at the facility.   A groundwater
monitoring  program  is  now  in  effect  which  requires   periodic
sampling of the groundwater to ensure that the closed lagoon  is not
acting  as a contaminant source to the groundwater.

In  1985,   the  Department  of  Ecology performed  a  preliminary
investigation of the  site  to further define  the  nature and extent
of contamination on the island. This investigation,  and subsequent
investigations,  revealed numerous  other types of contaminants in
addition to lead,  including: cadmium,  chromium,  arsenic, copper,
zinc,    mercury,   polycyclic   aromatic   hydrocarbons   (PAHs),
polychlorinated biphenyls  (PCBs),  and petroleum products.  Table 1
identifies some of the  potential sources of  these contaminants on
the island.

                   Table 1 - Potential Sources of Contaminants
     Contaminants                   Sources (Present and Historical)

     Metals                        -Metal smelting and refining
                                 -Metal plating operations
                                 -Scrap metal recycling
                                 -Paint pigments
                                 -Battery recycling
                                 -Waste oil
                                 -Automotive emissions

     Polychlorinated                  -Transformer oils
     Biphenyls (PCBs)                 -Heat transfer fluids
                                 -Metal cutting oils

     Polycyclic Aromatic                -Incomplete combustion of
     Hydrocarbons (PAHs)              organic matter
                                 -Automotive and truck exhausts
                                 -Diesel and fuel oil. petroleum

-------
In  1986,  approximately 220 parties were  sent 104(e) information
request  letters  by  EPA.  Based  on  the  responses received,  a
Potentially Responsible Party (PRP) search was completed for Harbor
Island  in 1987.  Since many  of the facilities on the  island had
multiple owners and operators, the search identified approximately
150  PRPs. These  PRPs- were   subsequently  sent  "general  notice"
letters. As a result of further .evaluation of PRP list, EPA removed
about 50  parties  from the  PRP list in 1989, bringing the current
total of PRPs to 98.

In 1987, EPA planned a Phase  I RI  which  included  only areas on the
island where there had been a known release of hazardous substances
from past operations. In an attempt to have this  work performed by
the PRPs, EPA sent "special notice" letters to 13  PRPs stating that
EPA intended to conduct  a  remedial investigation unless the PRPs
agreed to perform the work. EPA subsequently elected  to perform the
work with federal  funds  because EPA could not reach an agreement
with these 13 PRPs.  The Phase I investigation was  initiated in 1988
and completed in 1990.

During implementation of the Phase I RI, EPA negotiated a Consent
Order with the City of Seattle.  Under  the terms of this Order, the
City of Seattle cleaned contaminated sediments from its storm drain
system on Harbor Island. These storm drains were considered a major
pathway for contaminants entering the surrounding waters and marine
sediments. The work under this Order was completed in the Spring of
1990 and the  City  is now periodically monitoring the discharge from
these stormdrains to ensure that they meet water quality standards.
In a separate  enforcement  action,  EPA negotiated a  Consent Order
for a removal with the owner of the Value Metal Plating facility in
January,  1991. This  Order  required  the  removal   and  off-site
disposal of about  80 drums of spent electroplating  solution. The
work under this Order was completed in December, 1992.

Before proceeding with the next phase  of the RI/FS, EPA decided to
break up the Harbor Island site into several operable units which
could  be managed  more  efficiently.  Initially,  six  areas  were
defined as potential operable units: the petroleum tank  farms, Todd
Shipyard, Lockheed Shipyard, Terminal 18, the island-wide unit, and
the marine sediment unit. The petroleum  tank farm unit consists of
three tank farms  owned by Shell, ARCO, and  Texaco. Since petroleum
is generally excluded from the definition of hazardous substance
under CERCLA but is a hazardous substance under  the State's Model
Toxics Control Act  (MTCA),  EPA and Ecology signed a memorandum of
agreement that gives  Ecology  the  lead in undertaking enforcement
actions for these  three tank farms.  Agreements between  Ecology and
the tank farm owners to conduct RI/FSs were finalized in early 1993
and the selection  of remedial actions is scheduled for early 1995.

Todd  Shipyard and  Lockheed  Shipyard were  sent special  notice
letters requesting that they conduct an RI/FS on their facilities
in June, 1990.  In September,  1990,  a Consent Order was signed with

-------
Lockheed and the Record of Decision for this unit is scheduled for
the Spring of 1994. Negotiations were terminated with Todd due to
submission of  an inadequate  good  faith offer. An  RI/FS special
notice letter was sent to the Port of Seattle for Terminal 1C. in
January,  1991,  but negotiations were terminated after  the Port
decided  not to  conduct  the work.  Both the  Todd Shipyard  and
Terminal 18 facilities were then added to the island-wide operable
unit.

The island-wide operable unit includes the entire island except for
Lockheed Shipyard and the petroleum tank farms. The  Phase II RI
field work for this unit was  initiated in May, 1991, and involved
sampling  soil  at approximately 300 locations and  installing 49
groundwater monitoring wells. The RI/FS reports for1 the island-wide
operable unit were completed  in February, 1993. The RI field work
for the marine sediment unit was initiated in September, 1991, and
involved sampling marine sediments at over 100 locations around the
island.  The marine  sediment  RI/FS  reports  are  scheduled  for
completion in the Spring of  1994. The ROD for the marine sediment
unit is scheduled for the  fall  1994.
HIGHLIGHTS OF COMMUNITY PARTICIPATION

    CERCLA requirements for public participation include releasing
the Remedial  Investigation and Feasibility Study Reports and the
Proposed Plan to the public and providing a public comment period
on  the  Feasibility Study and  Proposed Plan.    EPA met  these
requirements in May, 1993, by placing both documents  in the public
information repositories  for  the  site.   EPA mailed copies of the
Proposed  Plan in  June,   1993,  to about  300 individuals  on the
mailing list.  EPA published  a notice of the release of the RI/FS
and proposed plan in the  Seattle Times in the morning and evening
editions on June  23,  1993.   Notice  of the  30 day public comment
period and  the public meeting discussing  the proposed plan were
included in the newspaper notice.  The public meeting was held on
July 14,  1993, at  the EPA  Region 10 Headquarters on Sixth Avenue in
Seattle.   A request  for  a 30  day extension of the public comment
period was received by EPA and was granted, extending the comment
period to 23  August  1993.   Public  comments received  and EPA's
responses  are  located in the  attached Responsiveness  Summary
section.

    To date, the following community  relations activities have been
conducted by EPA at the Harbor Island site over  the past 5 years:

March 1988- EPA updated the Community Relations  Plan from 1985.

April 1988- EPA released a fact sheet explaining the environmental
problems at the site.

December 1988- A fact sheet was released announcing the beginning

                                7

-------
of the Remedial Investigation.

June 1989- EPA mailed an update on the work at the site.

November 1989- A fact sheet was released explaining the work being
conducted by the City... of.  Seattle  to clean and  sample  the- storm
drain system on the island.

June 1990- EPA released an update of the activities at the site.

January 1991- EPA released a fact sheet announcing plans to remove
approximately  80  drums and some miscellaneous containers  at the
Value Metal  Plating facility.

April 1991-  EPA released a fact sheet announcing the availability
of  the  Phase  I  report  and  the  beginning  of  the  Phase  II
investigation.

September 1992- EPA released an update cf site activities.site.

June 231 1993- EPA ran an  ad in the Seattle Times announcing the
Public Comment Period and the date  and time of the Public Meeting.

June 23, 1993- EPA released the Proposed Plan for site cleanup.

July 9,  1993- EPA releases a notice of the extension to the public
comment period.

August 23, 1993- The Public Comment Period closed.


SCOPE AND ROLE OF RESPONSE ACTION WITHIN THE REMEDIAL STRATEGY

The operable unit addressed by  this Record of Decision  (ROD) is the
island-wide  unit.  The  remedial  action  selected  in  this  ROD
addresses all  contaminated soil and groundwater  exclusive of the
petroleum tank farms and the Lockheed Shipyard, which are separate
operable  units  as described  previously.  The  marine  sediments
contaminated with hazardous substances released from Harbor Island
is the fourth  operable unit for this site.  The  areas covered by
each of these four operable units are shown in Figure 3.

The remedial action  selected  for this  operable unit is the first
action to occur in any of  the  operable units. It is intended that
the remedial actions to be selected for the  Lockheed and tank farm
operable  units  will  be   consistent  with  the  remedial  actions
selected for the island-wide  unit.  Contaminated media  at Harbor
Island consists  of soil,   groundwater and  sediments.  The overall
remedial strategy for Harbor  Island  is  to initiate  clean up of
contaminated soil and groundwater first because they pose a  risk to
human health and act as sources of contamination to the marine

-------
                          Figure 3
             Harbor Island Operable Units
     Sediments Operable Unit


     Lockheed Operable Unit


     Tank Farm Operable Unit
I	I Harbor Island Operable Unit

-------
environment.  The need for cleanup of  sediments  and the Lockheed
Shipyard will be the  subject of future RODS. Actions necessary to
address the  tank farms will be identified by  Ecology  in a state
ROD.  Cleanup of the sediments,  *f  n»-.:essary, wil-1 occur iiJter
source control  identified in this ROD has been initiated.

Sediments at Harbor Island have been  contaminated by direct runoff
from contaminated surface soil, indirect runoff through storm sewer
systems,  and groundwater  contaminant  loading.  Contamination by
direct  and indirect  runoff  will be  controlled by  the selected
remedy for this island-wide  operable unit through: 1)  excavating
and  treating organic contaminant "hot  spots"  in soil,  and 2)
capping  all  areas   where  contaminants  exceed  cleanup  goals.
Groundwater  modeling conducted  during  the  Feasibility  Study
indicates that the only significant contaminant loading to surface
water is from floating petroleum  product near the shoreline. The
selected  remedy  will address  this  source  by:  1)  pumping and
treating  floating petroleum product and associated contaminated
groundwater  at  Todd Shipyard, and  2)  monitor the  groundwater
quality for  30  years with  review of  groundwater  quality trends
every 5 years.  The selected  remedial action on floating product,
followed  by  Ecology's  actions  on  floating  petroleum  product
associated with the  tank farm  operable unit,  is expected to meet
the surface water cleanup goals over  time and be protective of the
marine sediments.
SUMMARY OF SITE CHARACTERISTICS

General Characteristics

Harbor Island is situated in a geographic area known as the Puget
Lowlands,  a  trough  characterized  by low relief,  with glacially
shaped bluffs and low rising hills, and a vast area of intertidal
and tidal flats.  Puget Sound, in which Harbor Island is located,
is an inland marine waterway formed through continental glaciation.
Harbor Island is located on the former delta of the Duwamish River,
which flows  into Elliott Bay and  Puget  Sound from the Duwamish-
Green River valley.

The island is recognized as one of the largest artificial islands
in the world.   The  island is composed  largely of native fluvial
sand dredged from the  surrounding  areas.   Prior to dredging, the
surface of the delta was intertidal.  When the lower Duwamish River
channel   and   surrounding  delta  underwent  major  engineering
modifications in the early 10900s, these former shallow tidal areas
of the  Duwamish River  delta were filled with  material largely
derived  from  dredging  of  the  Duwamish  Channel and  adjacent
waterways.   Dredged sediment  was  placed  across the  Duwamish
tidelands to  form a fairly  homogeneous sandy fill which  is now
Harbor Island.  This fine-grained fill consists primarily  of poorly
graded, very dark gray,  fine to  medium,  damp to wet, loose sand.

                                10

-------
The fine-grained fill thickness ranges from 3 to 15 feet.  Alluvial
deltaic  deposits,  consisting of unconsolidated,  fine to coarse-
grained  sand, underlie  the fill  material.  Overlying  the fine-
grained  fill  is  a  layer  of coarse-grained  fill which  is from
Seattle  regrade projects  conducted  in the  early  1900's.  This
coarse-grained fill consists of gravelly sand to coarse sand, dark
grayish brown, poorly graded, loose, dry to moist.  The thickness
of the coarse-grained fill ranges from 0 to 7 feet.


Adjacent Land Use and Use of Natural Resources

Adjacent Land Use

Harbor  Island is  located  in  an  area  of  mixed  industrial  and
commercial  use.   Immediately adjacent to the  island are similar
industrial  areas.     Further to  the west are  residential  and
commercial properties.  To the east lies the metropolitan Seattle
area, which is primarily commercial with limited residential use.
South of the  island  are industrial developments.

Use of Natural Resources

Surface water runoff is collected and drained from the site via a
storm  drain  system  consisting  of catch  basins, outfalls,  and
drainage manholes throughout the island.  This system discharges at
11 outfalls around the perimeter of Harbor Island and  into the East
and West  waterways.   The  East and West waterways are primarily
commercial  shipping  lanes,  but  yacht clubs  and  marinas  are
permitted within the shoreline areas.  There are no natural ponds
on Harbor Island.

There are no drinking water wells in use on Harbor Island.  Harbor
Island groundwater is not currently used for drinking water and all
water users on the  island are serviced by the City of Seattle water
system.   Groundwater  at  a  depth  of approximately  40  feet  is
naturally brackish and not potable. Groundwater at Harbor Island is
not considered to be a future drinking water source.

Groundwater Resources

Groundwater   at  Harbor  Island  occurs  as  shallow,  unconfined
groundwater within the fill and deltaic sediment.  The depth to the
groundwater is shallow and  ranges  from  2.5  feet to 11 feet below
ground surface (bgs).  This  groundwater occurs as freshwater and
becomes brackish  at depths  of 45  feet near the shoreline,  and
deeper at inland locations.  The water bearing stratographic column
behaves as a  single hydrostatigraphic unit.

Groundwater recharge, occurs through infiltration of precipitation.
The groundwater  level is  highest  in  the  northern  half  of  the
island,  where  recharge  is  greatest.     Groundwater  elevation

                                11

-------
distribution  indicates a radial  flow condition with discharge to
the  adjacent  waterways. Groundwater  surface  elevation decreases
from  the north  central portion  of the  island to  the southern
portion because a greater percent of  :he southern portion is paved,
preventing recharge through infiltration.

The groundwater responds to tidal forces within the adjacent marine
estuary.  Areas of the island where tidal  forcing is sufficient to
cause a  reversal  in the direction of groundwater  flow are in the
tidally  influenced  zone, which is 500  feet wide at the northern
portion of the site and may extend to 1,000 feet at portions of the
southern end  of the island.

Water levels  suggest that  the south central portion of the island
is internally drained.   The aquifer may be infiltrating the METRO
sewer system  in that area.
Known or Suspected Sources of Contamination

Since construction,  the island has been used  for commercial and
industrial activities.  Major activities include shipping, railroad
transportation,  bulk fuel  storage  and transfer,  secondary lead
smelting,  lead  fabrication,   shipbuilding,  and  metal  plating.
Warehouses,  laboratories, and  office  buildings  have  also been
located on the island.

Current sources of contamination were identified in the RI/FS and
include current and past  industrial p::c -tices associated with the
activities mentioned above.   Based on current  information, the
major sources of contamination appear to be:

     • Atlantic Richfield  Company  (ARCO) —  tank farm
     • Lockheed Shipyard #1
     • Nonferrous Metals,  Incorporated
        The  secondary  lead   smelter,   currently  Seafab  Metal
      Corporation
     • Seattle Iron  & Metals, main yard
     • The  former Leckenby Company,  (Port of Seattle property)
     • Shell  Oil Co.,  current tank farm  and past tank farm located
      on Terminal 18 (Port  of  Seattle)
     • Texaco USA —  tank farm
     • Todd Shipyards

Types of Contamination  and Affected Media

The  Harbor  Island  RI  involved the  collection  of  surface and
subsurface  soil  samples  from  over 300  locations.   Soil   sample
locations were based on a combination  of a grid pattern over the
entire  island  and  additional  (biased)   sampling in areas  of
suspected or known contaminant releases. Surface soil samples were
taken from the  top 6 inches of soil  and subsurface soil samples
were taken at at intervals of 0.5-3.0,  3.0-6.0, and 6.0-10.0 feet.

                                12

-------
Groundwater  samples taken from approximately 69 monitoring wells
(49 new wells and  20 existing wells) .  The intent of the sampling
was to characterize the extent of contamination.  The results of
the sampling efforts for each medium are presented in the RI report
and are summarized below.

Surface Soil  (O-6  Inches)

Surface  soil is  contaminated  with elevated  levels  of  organic
compounds  and  inorganic elements  over  a major portion  of the
island.   By volume, the most  significant organic contaminant in
surface soil  is petroleum products [total petroleum hydrocarbons
(TPH) ].  Approximately 95 percent of the samples with detectable
TPH concentrations were between 20 mg/kg and 51,000 mg/kg, although
most were  between  50  and 2,000 mg/kg.   Also  present in smaller
quantities  in surface  soil were polycyclic aromatic hydrocarbons
(PAHs). The highest concentrations  of heavy PAHs found in surface
soil ranged between 10  and  50  mg/kg.   Polychlorinated biphenyls
(PCBs) in  surface  soil  ranged  from 2  to  420  mg/kg.  TPH and PAHs
were found mainly  around the petroleum tank farms, and at Seattle
Iron and  Metals 'and Todd Shipyard facilities.   PCBs were found
predominantly in the central portion of the island.

The most significant inorganic  contaminant on the island is lead,
which is  found  over most  of the island  and  originated primarily
from  the  lead  smelter.  Approximately 55% of the  surface soil
samples  and  12%  of  the  subsurface  soil  samples  exceeded  a
concentration of 1,000 mg/kg.  The highest detected concentration
was 401,000 mg/kg.  Lead contamination was primarily confined to the
upper three feet of soil. The  majority  of samples with elevated
lead in the range  from 5,000  to 200,000 mg/kg,  occurred in the
central portion  of the site.  The highest concentrations of other
inorganics  are  found  in surface soil  include:  arsenic  at 1,830
mg/kg, cadmium at 131 mg/kg,  and chromium at 791 mg/kg. The highest
concentrations of  most inorganic contaminants  in surface soil are
located in  the  central  portion  of  the island and are associated
with industrial  operations in that  area.

TCLP tests conducted on surface soil samples showed that leachate
for lead exceeded the RCRA threshold for  a characteristic waste at
six locations.

Subsurface Soil  (Below 6 inches)

Subsurface  soil  is  also  contaminated   with  the  same  organic
compounds  and  inorganic  elements  found  in  surface soil,  but
contaminated subsurface area decreases rapidly  with  depth.  The
major organic  subsurface  contaminant  is TPH,  which  ranges from
nondetect to 90,517 mg/kg in  subsurface soil.  TPH contamination is
associated with the petroleum t?nk farms,  Seattle Iron and Metals,
and Todd  Shipyard  facilities.    High  concentrations of  TPH are
located at depths  from 0.5 to  10 feet below the surface in these

                                13

-------
areas.

PAH  concentrations  in  subsurface  soil  range  from  below  the
detection  limit to 182 mg/kg.   Approximately 90 percent  of the
subsurface soil contains  less than 5 mg/kg heavy PAHs.   PCBs in
subsurface soil range from 0.02 to 5.48 mg/kg.

The most  significant inorganic contaminants  found  in  subsurface
soil are lead and mercury.  Lead contamination ranges from 2.3 to
32,200  mg/kg and  mercury from 1.0  to 8.1 mg/kg.   The  highest
concentrations  of  lead are  found in  the vicinity of the old lead
smelter at depths of 0.5 to 10 feet, and the highest concentrations
of mercury are  located at depths of  0.5 to  3  feet at the Seattle
Iron and Metal  and Todd Shipyard facilities.

Groundwater

The results of  the remedial investigation show that measurable or
trace amounts of light nonaqueous phase liquid (floating product)
is present in eight wells associated  with the petroleum tank farms
and three wells associated with Todd  Shipyards.  The only location
where significant floating product is found near the shoreline is
at Todd Shipyards.   Components of this floating product include
diesel fuel  and gasoline.  Thicknesses ranged from  a  sheen to 7
inches.

Groundwater  at  several   locations  along the shoreline  on  the
northern   portion  of   the   island   also    contained   benzene,
ethylbenzene,  and xylene,  vinyl   chloride,  and other  compounds
associated with petroleum products.   Benzene ranged from nondetect
to 3,900 Aig/L, ethylbenzene  from nondetect to 1,800 pg/L, O-xylene
from nondetect to 16,000 ^g/L, and vinyl chloride  from nondetect to
7.0 /xg/L.

Elevated  levels  of  inorganic contaminants  including  mercury,.
nickel, cadmium,  lead, and zinc are  also  found  in groundwater
across the  island.  Mercury  ranges  from nondetect  to  3.0 M9/L/
nickel from  nondetect  to 230 Mg/L, cadmium from nondetect to 21
jig/L,  lead from nondetect to  64 Mg/L/  and  zinc from nondetect to
1,700 M9/L-   Ammonia is  also present in elevated  levels  in the
groundwater.

Based on the  results  of  a groundwater model (FLOWPATH)  which EPA
used to predict the rate  of  migration of the above contaminants.to
the shoreline  (where marine organisms could  be  exposed),  it was
determined  that  most  of  the  contaminants  currently  in  the
groundwater would  not  reach the shoreline within 50 years.  The
only contaminants which are at the shoreline now or will be there
in the  next  50  years are the  floating petroleum product at Todd
Shipyards and low  levels  of VOCs  dissolved  in the groundwater at
Todd Shipyards  and two other locations along the shoreline.


                                14

-------
Routes of Migration

The fate of contaminants originating from Harbor Island depends on
location-specific  migration  patlrv.ys .  ^nd  or. the chemical  and
physical properties of each contaminant.  This section focuses on
the contaminants of concern and identifies their probable routes of
migration in surface soil, subsurface soil, and groundwater.

A transport of contaminants  was  established by review  of storm
drain analytical  data and examination  of RI maps  depicting the
concentration distributions  for contaminants of  concern  in soil,
groundwater, and  offshore sediment.  The  presence of localized,
elevated  concentrations  of  contaminants  in two  or more media
connected by a transport pathway (e.g., spil/groundwater or surface
soil/storm drain/sediment) was considered evidence of contaminant
release and transport.

Surface Soil

The principal transport mechanisms of the contaminants in surface
soil are as suspended soil in surface water runoff. Surface water
runoff is a significant current transport pathway for contaminants
to reach the surrounding waterways and  marine sediments. Surface
water runoff can transport dissolved, suspended,  and particulate-
bound  contaminants  through   storm drains  into  the  surrounding
estuary.

Subsurface Soil

The probable transport mechanism of  the primary  contaminants in
subsurface soil is vertical transport of dissolved contaminants in
rainwater which  permeates through  the  soil. The  primary factor
which determines the rate which  inorganic and organic contaminants
leaches  from  the  soil  is  the  contaminant  solubility.  For
inorganics, the pH of the water contacting the contaminated  soil is
also an important factor. Inorganics are relatively less mobile in
the soil  than  organics   because  inorganics have  relatively low
solubility  in  water  and they  also  strongly  adsorb  to  soil
particles,  particularly  silts and  clay. Organics, on the other
hand,  are generally more soluble in  water  and primarily bind to
naturally  occurring soil organic  matter,  such  as  humic acid.
Organic contaminants in high concentrations, such  as petroleum, can
also travel through pores in the soil as  a Non-Aqueous  Phase Liquid
(NAPL) .  Organic contaminants in the NAPL state will  not bind to
soil organic matter and can flow through soil pores  at  a relatively
fast rate.  Residual NAPL can remain  in the unsaturated (vadose)
zone for long periods of  time due to capillary attraction.

Groundwater

Contaminants  in  groundwater  at  Harbor  Island  are  typically
transported as either  dissolved constituents or  light nonaqueous

                                15

-------
phase  liquids (floating product).  A two-dimensional groundwater
transport model (FLOWPATH)  along with a Digital Elevation Model was
used  to  determine  both  loading  rates  and concentrations  of
contaminants   at   the  shoreline.    "The   -->ntaniinant  transport
calculations  performed by  the model predict the concentration of
contaminants at the discharge point  to the estuary and the time for
the concentration  of  a contaminant  to exceed a reference standard
at the island-estuary interface.

On the basis of transport modeling, only floating petroleum product
and benzene dissolved in the groundwater near the shoreline may
exceed surface water quality standards at the  shoreline within the
next 50 years. All other contaminants currently in the groundwater
across  the island will take more than  50  years  to  reach the
shoreline at  levels exceeding these standards. The loading model
estimates  that groundwater  transport  to estuarine  sediment .and
water  is not  likely  to  be  significant  for  most  contaminants,
especially when compared to  loading from surface water runoff and
storm drains on Harbor Island.
SUMMARY OF SITE RISKS

An  assessment of  the  human health  risk at  Harbor  Island was
completed according  to  EPA Region 10 risk assessment guidelines.
The results of a habitat evaluation indicated that Harbor Island is
unable to sustain  a  wildlife population or support a funcitoning
wildlife  habitat  due   to  widespread  industrial  development.
Therefore, an ecological risk assessment was not performed due to
the  absence  of  wildlife  habitat  areas  on  Harbor  Island.  An
ecological  risk  assessment will  be  conducted  for  the  marine
sediment  operable unit of  this  island.  The  human health risk
assessment  at  Harbor  Island  involved  analyte  screening  and
evaluation,   exposure   assessment,  toxicity   assessment,   lead
biokinetics modeling and risk characterization.

People who may  incidentally ingest  soil through hand-to-mouth
contact  and  absorb  contaminants through  dermal contact  with
contaminated soil were identified as the population most at risk of
adverse health effects.  Inhalation is not a significant pathway of
exposure to contaminants on Harbor Island based on the  results of
air   dispersion   modeling   conducted   during   the   remedial
investigation.  The  noncancer  hazard  from  inhalation was  not
significant (hazard  index  of less  than one), and the cancer risk
was approximately two orders of magnitude less than that observed
for the ingestion pathway  for all scenarios evaluated.

Exposure to contaminants in groundwater was not evaluated because
there is no current or foreseeable use  of groundwater for drinking
water purposes, and  the entire  island  is serviced by the city of
Seattle water  system.  Also, the majority  of groundwater beneath
Harbor Island is naturally brackish and unsuitable for'drinking.

                                16

-------
Contaminants of Concern
A  multiple-step  screening  approach  was  used  to  identify  the
analytes of  concern for the human health  risk assessment.  To be
included in  the risk assessment,  cc ntaminants had to occur in at
least  5%  of the  samples and had to  be at  a concentration high
enough to have a  risk greater than 10~6 or hazard index of  0.1
As a result of this screening process, forty  one contaminants were
identified  for evaluation  at  Harbor  Island.    These included
tetrachloroethane,   2,4-dinitrotoluene,    3,3'-dichlorobenzidine,
bis(2-ethylhexyl)phthalate,  carbazole,  pentachlorophenol,  eight
polynuclear    aromatic    hydrocarbons    (2-methylnaphthalene,
benz(a)anthracene,     chrysene,    benzo(b)fluoranthene,
benzo(k)fluoranthene,  benz(a)pyrene,  indeno(l,2,3-cd)pyrene,  and
dibenz(a,h)anthracene),  four PCB mixtures  (aroclors 1242,  1248,
1254,  and  1260),  six pesticides or pesticide breakdown products
(alpha-BHC,  aldrin,  dieldrin,  4,4'-ODD,  4,4'-DDE, 4,4'-DDT),  and
seventeen metals  (antimony,  arsenic,  barium,, beryllium, cadmium,.
chromium, cobalt,  copper, lead, manganese,  molybdenum, mercury,
nickel, thallium,  tin, vanadium, and  zinc).   Of these, antimony,
arsenic,  lead,  carcinogenic PAHs  and  PCBs are  considered  the
contaminants of concern because of their higher concentrations and
toxicity  compared  to  other  contaminants.    The  maximum  soil
concentrations of these  contaminants  (the  concentrations  which
resulted in the highest risk estimates)  are  shown  in Table 2.

	Table 2— Maximum Surface Soil Contaminant Concentrations	

 Contaminant	Ma?:z~'":n  Concentration (lag/kg)

 Antimony                                      3,640

 Arsenic                                       1,830

 Lead                                         401,000

 Benz(a)anthracene                              37

 Chrysene                                       49

 Benzo(b)fluoranthene                           39

 Benzo(k)fluoranthene                           39

 Benz(a)pyrene                                  18

 Indeno(l,2,3-cd)pyrene                        10.6

 Dibenz(a,h)anthracene                         2.9

 Aroclor-1242                                  2.1

 Aroclor-1248                                  4.3

 Aroclor-1254                                  360

 Aroclor-1260                                  420
                                17

-------
Exposure Assessment

Harbor  Island  has  been  used   for  industrial  purposes  for
approximately  the  last  80 years.   Currently, there are no homes,
residential  areas, or  commercial  daycare  facilities  on Harbor
Island.   For these reasons, both   current  and future industrial
exposure scenarios were evaluated.  However, because Harbor Island
is  currently  zoned  as   "industrial/commercial,"  a  commercial
scenario (daycare center) was also evaluated as a  plausible future
use of the island.

Risk was calculated  for the resonable maximum exposure (RME) and
for.an average exposure.  The risks  cited in this  document are for
RME.  The  risks  for the  average  exposure  can be found  in the
Baseline Human Health Risk Assessment.  RME  is equal to the upper
95% confidence limit of  the concentration  distribution for each
contaminant.   For incidental  soil ingestion  and dermal contact
exposures, measured soil concentrations were used  to determine the
RME values.   RME values  for  inhalation exposures were estimated
using  the  results  of  air dispersion modeling.  The  exposure
assumptions used for all three pathways are  based  on EPA Region 10
risk assessment guidelines and are specified in the Baseline Human
Health Risk Assessment.

Due to uncertainty on the appropriate toxicity criteria to use for
evaluating  lead,  this  metal  was  not  included  in   cancer and
noncancer risk calculations,  but was  evaluated using the uptake
biokinetics model.

Industrial Exposures

RME values were determined at every surface  soil sampling location
on Harbor Island.  In calculating risk from hypothetical industrial
exposures it was assumed that risks from incidental soil ingestion,
dermal absorption, and inhalation were additive and contributed to
the total body burden.   Combining all of the exposure assumptions,
summary  intake  factors   (rates  of   ingestion,   absorption  and
inhalation)  were derived for each exposure pathway. These factors
are shown in Table 3.

          Table 3— Summary of Intake Factors for Industrial Exposure Pathways
Noncarcinogenic
Summary Intake Factor
Carcinogenic Summary
Intake Factor
Incidental Soil
Ingestion
4.89E-07
1.75E-07
Dermal Absorption
1.86E-05
6.64E-06
Inhalation of Paniculate
and Vapors
1.96E-01
6.98E-02
                                18

-------
commercial Exposures

In the  commercial scenario it was  assumed that infants would be
exposed to airborne contaminants for ore year  (age 0-1) and  tha;
children would be exposed to contaminants in air and soil for  five
years  (age  1-6).   Reasonable maximum exposure was determined at
every surface  soil sampling location  on  Harbor Island.  As  with
industrial exposures,  it was assumed that doses from  incidental
soil ingestion, dermal absorption, and inhalation (both infant and
child) were additive for cancer  risk  and  contributed  to the total
body burden.  For  noncancer health effects, child exposure pathways
were summed to estimate the total dose to a child and  the infant
inhalation pathway was used to estimate total dose to  an infant.
Other key exposure assumptions used for the soil ingestion, dermal
absorption, and  inhalation pathways are  based EPA Region X  risk
assessment guidelines.  Combining all of the exposure  assumptions,
summary intake factors for each  exposure  pathway were derived for
the child, and for the inhalation pathway for the infant.  These
factors are shown  in Table 4.

          Table 4— Summary Intake Factors for Commercial Exposure Pathways
Noncarcinogenic
Summary Intake
Factor
Carcinogenic
Summary Intake
Factor
Incidental Soil
Ingestion (Child)
9.13E-06
6.52E-07
Dermal
Absorption (Child)
9.57E-05
6.83E-06
Inhalation of
(Infant)
4.57E-02
6.52E-04
Paniculate and Vapors
(Child)
4.57D-01
3.26E-02
Toxicity Assessment

In order of priority, the following EPA sources were consulted for
toxicity  criteria:  Integrated Risk  Information  System  (IRIS);
Health  Effects  Assessment  Summary  Tables  (HEAST);  and  EPA's
Environmental Criteria and Assessment Office (ECAO). The basis for
the  noncarcinogenic and  carcinogenic toxicity  criteria used  to
calculate risk for the contaminants of concern is briefly discussed
below.

The  toxicity  criteria  used  to  evaluate  noncancer  risks  are
reference doses  (RfDs).   The term  RfD  refers to a  daily intake of
a  contaminant   to  which  an  individual,  including   sensitive
subpopulations,   can  be   exposed  without  any   expectation  of
noncarcinogenic   adverse  health   effects   (e.g.,   organ  damage,
biochemical alterations,  birth defects).
                                19

-------
The  contaminants  of concern  for  noncancer health  effects were
arsenic  and antimony.   These contaminants were  only of concern
through the oral route.  The oral reference dose for arsenic  (3.0E-
fM for both chronic  and  subchronic c.rposures) is based on a study
in  which  skin effects  were  noted  in humans  following arsenic
ingest ion.  The oral reference dose for antimony (4.0E-04 for both
chronic  and subchronic  exposures)  is  based on a  study  in which
blood  chemistry changes were noted  in rats  following  antimony
ingestion.

The  toxicity  criteria used to evaluate cancer risks are cancer
slope factors.   A  cancer slope factor is a numerical estimate of
the potency of a contaminant  that, when multiplied by the average
lifetime dose, gives the probability of an individual developing
cancer over a lifetime.  In developing cancer slope factors, it is
assumed by the EPA that any  dose of  a carcinogen,  no matter how
small, is capable of causing cancer.   Slope factors are derived by
EPA using a linearized multistage model and reflect the upper-bound
limit of a contaminant's cancer potency.

The contaminants of concern for cancer health effects were arsenic,
PAHs, and  PCBs.  Because these contaminants were only of concern
through  oral   and  dermal  routes,  only  slope  factors for  these
exposure routes are  discussed.

EPA  uses  a  weight-of-evidence  system  to convey  how  likely  a
chemical is  to be  a human carcinogen,  based  on epidemiological
studies,   animal   studies,  and   other  supportive  data.     The
classification scheme for characterization of weight-of-evidence
for carcinogenicity includes:  Group A-known human carcinogen, Group
B-probable human carcinogen,   Group  C-possible  human carcinogen,
Group D-not classifiable as to human carcingenicity, and Group E-
evidence of non-carcinogenicity in humans.

Arsenic is classified by EPA as a known human carcinogen (Group A) .
The  oral  slope  factor  for arsenic obtained  from IRIS  was  1.8
(mg/kg-day)'1.  Carcinogenic PAHs are classified by EPA as probable
human carcinogens  (Group B).   The oral slope factor (also used as
the dermal slope factor)  obtained from the EPA ECAO was 5.8 (mg/kg-
day)"1.     This  is  the  slope factor for  benzo(a)pyrene.   In
evaluating risk for other carcinogenic PAHs, this  slope factor was
used in conjunction with  a  toxic equivalency factor (TEF) approach.
Using the  TEF approach,  the  slope  factor  for benzo(a)pyrene was
multiplied  by  a  numeric   factor  to  adjust  for the  differing
toxicities of the carcinogenic PAHs.   PCBs are also classified by
EPA as probable human carcinogens  (Group B) .  The oral  slope  factor
(also used as the dermal slope factor) obtained from  IRIS was 7.7
(mg/kg-day)'1.
                                20

-------
Risk Characterization

Noncarcinogenic risks were evaluated by comparing contaminant daily
intakes  to  reference  doses  (RfDs) .    This  wa^  accomplished, by
calculating hazard quotients and hazard indices.  A hazard quotient
for a particular contaminant through a given  exposure route  is the
ratio between  the  estimated daily intake and the applicable RfD.
A hazard  index is  a sum of hazard quotients,_which may be  summed
for  all contaminants  for a  given exposure' pathway,  and  across
pathways.   If  a hazard quotient or  hazard index exceeds 1.0, it
indicates that potential noncarcinogenic health effects may occur
under the defined exposure conditions.

For all three  scenarios evaluated  (industrial current, industrial
future, and commercial future) hazard indices greater than one were
determined for the incidental soil ingestion pathway only.   In all
three  scenarios,  the  contaminants contributing  the majority of
noncancer risk at most sample locations were  arsenic and antimony.
Results show that for the current and future  industrial scenarios,
less than one  percent  of the sample location have a hazard index
greater than one.  For the  commercial  scenario,  approximately 39
percent of the sample  locations have a hazard index greater than
one. Results for each pathway and  scenario are shown in Table 5.

Carcinogenic risk was calculated for each carcinogen by multiplying
the estimated daily intake of carcinogen by the appropriate  cancer
slope factor.  Carcinogenic risk was calculated for each carcinogen
through each  exposure  pathway  for  each individual.   The total
carcinogenic  risk  for  each scenario  was calculated  by summing
carcinogenic  risk  across  exposure  pathways for  the industrial
(current)   and  the  industrial   (future)   scenarios, and   across
exposure pathways  and  age groups  (i.e.,  infant  + child)  for the
commercial scenario.

According to the  National Contingency  Plan,  the acceptable risk
range for carcinogens at a Superfund site is between 1 in 1,000,000
(10"6) and 1 in 10,000 (10"*).  The excess lifetime cancer risk from
reasonable maximum exposure to arsenic,  PAHs, and PCBs ranges from
less than 10"8  to  10~3  for both  the current and future industrial
scenarios. For both scenarios,  the total carcinogenic risks were
greater than 10"* at only  2%  of  the sample locations.

The cancer risks range from less than 10~8  to 3 x  10"3 for children
attending  a daycare  center (commercial  scenario),  if  such   a
facility is established on Harbor  Island  in  the  future.  For this
scenario,  the total carcinogenic risk was greater than 10"*   at 11%
of the  sample  locations. For both the  industrial and commercial
scenarios,  the majority of  the  carcinogenic   risk was  due to
incidental ingestion of  soil containing arsenic, PAHs, and PCBs.
Results of cancer risk calculations are  shown in  Table 6.
                                21

-------
Tablf 5  Summary of Noncancer Risk Calculations
Scenario
Industria(Current)
Industria(Future)
Commercial(Child)
Range of Hazard Indices for the Following Pathways:
Inhalation Ingestion
1.0
<0.00001 -3.9 
-------
The  biokinetic  uptake  model  was use  to determine  appropriate
cleanup  levels for lead.  This model estimates total  blood lead
levels in a child,  resulting from exposure through routes which are
both related  to conditions at Harbor Island  (such as incidental
soil  ingestion  and  inhalation-based on  soil  concentrations  on
Harbor Island), and routes which are  general for a child living in
the  Seattle  area   (such  as  fruit/vegetable  ingestion-based  on
regional lead  levels in produce).  Using this model, the range of
acceptable soil lead concentrations was  from 500-550 mg/kg for the
commercial daycare scenario.

Uncertainty

The accuracy  of the risk estimates depends in  large  part on the
accuracy  and   representativeness  of  the sampling  data,  exposure
assumptions,   and  toxicity   criteria.     Most   assumptions  are
intentionally  conservative so  the risk  estimates will  be more
likely to overestimate than underestimate.

Uncertainties  in sampling data directly influence  the final risk
calculations.  All analytical results have variability associated
with them.  A  variability of minus 50 to plus 100% is typical for
samples  containing  analytes  at  concentrations   less  than  the
contract-required  quantitation  limit.    For  samples  containing
higher levels of analytes, relative percent differences of 35% for
soil  are   considered   acceptable.     Depending  on  the  actual
concentration  of the analyte  at these points, the reported value
may either  over- or underestimate the  actual concentration.   In
addition to this uncertainty,  the lack of  PAH  sampling in the tank
farm areas on Harbor Island likely resulted in an underestimate of
carcinogenic risk in these areas.

Another  source  of uncertainty  in  the risk  assessment  is  the
assumptions  used  to  arrive  at  exposure doses.   A number  of
assumptions were made  in  the risk  assessment  that overestimate
exposure  in areas where  the  limitations  in  the  available data
mademore  specific  quantitation difficult  or  impossible.   It is
inherent in these  assumptions that the  actual case would clearly
result in reduced exposure and consequent  risk.

A  final  source  of uncertainty  relates to the method  by which
carcinogenic and noncarcinogenic  toxicity  criteria are developed.
Several  conservative   uncertainty  factors  are   used   in  the
development  of  toxicity   criteria,  which  in  turn  cause these
criteria to have an associated uncertainty spanning several orders
of magnitude.  Specific to this risk assessment, two of the three
contaminants which made a  significant contribution  to carcinogenic
risk, PAHs and PCBs, have cancer  slope  factors  which were derived
from animal studies, which contributes a high level  of uncertainty.
With respect to noncarcinogenic effects, the contaminants  found to
contribute most of the noncarcinogenic risk (arsenic and antimony)

                                23

-------
had  associated uncertainty factors of 3  and 1000, respectively.
Based  on these  uncertainly factors,  there is  a high  level of
confidence in the RfD for arsenic, but a larger uncertainty for the
RfD  for antimony.

Environmental  Evaluation

As the first step in the environmental evaluation, a habitat and
ecological community evaluation was performed. The results of the
habitat  evaluation  showed that  Harbor  Island  consists of an
industrial   matrix  with a  number  of  small  and  disconnected
undeveloped  patches of land.  Due  to the industrial development on
the  island,  these patches  do not appear sufficient in  size or
quality to sustain a wildlife population or support a functioning
ecological   community.  The  evaluation of  potential  ecological
receptors  indicated  that only those  species  (i.e.,  rats,  dogs,
crows, and gulls) associated with  urban areas would be expected to
temporarily  reside on Harbor Island.  A field investigation as well
as interviews were unable to verify the presence  of any mammals on
Harbor  Island.  The  lack  of suitable   habitat  and  ecological
receptors  precluded  the  necessity  for  further  environmental
evaluation.
REMEDIAL ACTION OBJECTIVES

The  remedial  action  objectives  (RAOs),  and  their  associated
numerical cleanup goals, are intended to protect human health and
the environment by  reducing risks  to acceptable levels.  RAOs are
based  on  the  state  and  federal  applicable  or  relevant  and
appropriate requirements  (ARARs) . The numerical cleanup goals are
based on criteria identified in these ARARs and on the results of
the human health  risk assessment.  The RAOs and cleanup goals for
Harbor Island are shown in Table 7.

For  Harbor  Island,  the  primary  soil  ARARs  are  the  criteria
contained  in the State  of Washington  Model Toxics  Control Act
(MTCA). Three different MTCA methods were used to identify cleanup
goals for contaminants in soil:
1) Method "A"  for industrial  soil, which specifies cleanup goals
based on  a  risk of  10"5  from an individual  carcinogen or hazard
index of 1.0 from a  non-carcinogen, was  applied  to subsurface soil
because the  potential for human exposure  to the  subsurface soil
would be infrequent.  Method "A" for industrial soil was used for
lead  in  the   surface  and  subsurface,  because  a  risk-based
calculation method has not yet been scientifically determined for
lead.
2)  The more  stringent  Method  "C"  for  industrial  soil,  which
specifies cleanup goals based  on  a total  risk of 10"5  from all
carcinogens or hazard index of 1.0 from all non-carcinogens, was
applied to the surface soil where the potential for human exposure


                                24

-------
                      Table 7— Remedial Action Objectives and Cleanup Goals
                  Primary Receptors
                        Remedial Action Ob . 3tive
                                 Cleanup Goals"
Soil-Surface
Humans
                                          Protect human hearth from
                                          exposure to contaminants in
                                          surface soil which pose a
                                          combined risk of greater than 1 x
                                          10'5.
                                 Lead: 1,000 mg/kgb
                                 Arsenic: 3.60 to 3ZJB mg/kgc
                                 Antimony: 180 to 677° mg/kg
                                 Carcinogenic PAHs: 0.1
                                                                           PCBs: 0.18 to ^99C mg/kg
Soil—Subsurface
Humans and
Environment
Protect human health from
infrequent exposure to
contaminants in the subsurface
which pose a risk greater than
10"s for each contaminant
Prevent release of contaminants
into the groundwater where they
can be transported to the
shoreline, where marine organisms
could be exposed.
Lead: I.OOOmg/kg"
TPH(diesel): 600mg/kgd
TPH (gas): 400 mg/kgd
Cadmium: lOmg/kg1*
Chromium S00mg/kgb
Mercury:  l.0mg/kgb
PAHs (carcinogenic): 20 mg/kgb
Arsenic:  200mg/kgb
Benzene: tJOmgfltga
Ethylbenzene: 200mg/kgd
Toluene: 100 mg/kgd
Xytenes: 150 mg/kgd
Groundwater
Environment
Prevent migration of contaminants
to the shoreline where marine
organisms could be exposed.
Protect human health from
consuming contaminated marine
organisms which pose a risk
greater than 1 x 10"6
Carbon Tetrachloride: 4.4pg/Le
Benzene: 71 jtg/L
Trichloroethane: 42/tg/L
Tetrachtoroethytene;  8£(ig/L
PCBs: 0.03 Mg/L
Arsenic:  36
-------
would be more  frequent.
3)  The  Petroleum-Contaminated Soils  Rating Matrix  method (which
satisfies  Method  "B")  was used  to determine  cleanup goals  for
surface and  subsurface  soil contain•• r: te-? with petroleum produces.

Approximately  200  acres of  surface soil, shown in Figure 4, exceed
the above  listed cleanup goals.  Of the total surface  area which
exceeds cleanup goals, only 40 acres are unpaved. The total volume
of soil which exceeds these cleanup goals is approximately 900,000
cubic yards. Estimates  for  volumes of surface and subsurface soil
exceeding the  cleanup goals are shown in Table 8.


                Table 8 - Volumes of Soil Exceeding Cleanup Goals

 Contaminant Type                    Volume of Son (bank cubic yards)
                          Surface Sofl (<0.5 Feet)     Subsurface So3 (>0.5 Feet)
Organics
Inorganics
Organics and Inorganics
Total
58.000
33,000
21.000
112.000
416.000
267,000
71,000
754.000
For groundwater,  EPA and Ecology have determined that the federal
and state drinking water standards do not apply because:
1)  there is  no  current or  foreseeable use  of groundwater  for
drinking water  purposes, 2) the entire  island  is serviced by the
city of Seattle water system,  and 3) surface water ARARs will apply
at the  shoreline. For Harbor Island, the  surface water ARARs are
the marine  chronic criteria  in  the "Water Quality  Standards for
Surface Waters  of the State  of  Washington" and  the human health
criteria.for consumption of marine organisms in the federal "Water
Quality Standards; Establishment of Numeric Criteria for Priority
Toxic Pollutants; States' Compliance Final Rule".


DESCRIPTION OF  ALTERNATIVES

Eleven  soil  alternatives  and four groundwater  alternatives were
evaluated. Groundwater alternatives are presented separately after
the section on  soil  alternatives.

Soil Alternatives.

Alternative 1:  No Action
Evaluation  of  a  no  action alternative is  required in  order to
provide a basis for comparison of existing conditions and risks of
potential  conditions resulting  from  implementation  of  other
remedial alternatives.

                                26

-------
                        Figure 4
         Surface Soil Exceeding 1.0E-5 Risk
                   or MTCA Criteria
 &etow MTCA MetlwdA Lovots


 Abovo MTCA Maawd A w Risk Unit el 1E-OS


• • lank Fann Area

-------
Major Components of the Remedial Alternative

Under the no action alternative, no additional remedial action will
be  taken to.  eliminate existing sou -ces  of contamination  or to
reduce the risks to humans or the effects on the environment.  No
engineering,  or .institutional, controls would be  implemented.   No
additional requirements under Superfund would be imposed on local
companies to inform workers of site conditions, nor would they be
required to use precautions in their daily work activities, other
than those required under existing regulations.

Treatment Component

There is no treatment component for this alternative.- Reduction in
toxicity or volume will occur only through natural processes such
as  photodegradation  or biodegradation. Natural  biodegrdation of
some  organics would   occur  over  time due  to  the presence  of
indigenous bacteria  in the soil.  However,  due to uncontrollable
environmental factors  and  unknown  biodegradation rates,  the rate
and degree in reduction of organic contaminants  cannot be predicted
with any level of certainty.

Containment Component

Containment is not a component of the no action alternative.

General Component

The no action alternative has no general component.   There would be
no source control,  management of migration or long-term monitoring
activities implemented in this alternative.

Cost and Remediation Time Frame

There  are no  costs  associated with this  alternative and  the
alternative can be implemented immediately.

Physical Effects on Environment Caused by Implementation

The no action alternative would not remove contaminated soil from
Harbor Island.  No remedial activities are performed.  Therefore,
the risk from implementation of this alternative is minimal.

Compliance with ARARs

This alternative will not meet any  ARARs (see page 81, "Compliance
with  ARARs",  for a  complete  list of  ARARs  which apply  to all
alternatives).
                                28

-------
Alternative 2:  Institutional Controls

Major Components of the Remedial Alternative

This  alternative  consists  of implementing various  engineering,
safety  and institutional controls  to protect workers  on Harbor
Island  from  exposure to contaminated soil and groundwater.   The
contaminated soil and groundwater would  not be  treated and would
remain a potential exposure route.

Treatment Component

This  alternative  does  not  have   a  treatment  component.  Some
reduction in toxicity or volume of organic contaminants would occur
over  time  through natural processes, such as biodegredation,  as
described in Alternative 1.

Containment Component

This alternative does  not have a containment component.

General Components

This  alternative  would provide  some degree of protection  for
workers through the  use of  various  controls.  Workers exposed to
uncovered contaminated soil in industries that involve significant
soil  contact would  be  instructed  to  wear  personal  protective
equipment. Facility  operators would be  instructed  to provide air
monitoring to determine if dust control measures were necessary to
protect workers during daily work  activities.   Dust suppression
could be implemented  by spraying  the site  with  water or covering
the areas  with  tarps.   if  dust suppression  is  not  effective or
practical, the workers would be instructed to wear respirators.

Training and informational  meetings would  be  held  with employees
and property owners  to  inform them  of site  hazards.   Safety
meetings  would  be  held  with  employees  instructing  them  on
precautions to be taken when  working  on  the site to avoid dermal
contact or ingestion.

Controls would  also  be necessary  for  construction work  on the
island.  If contaminated, soil piles would need to be provided with
run-on/runoff controls such as tarps,  curbing  and liquid absorbing
booms.  Contaminated  soil  from construction excavations would be
taken to a permitted  off-site facility for treatment, storage or
disposal.  Signs would be located around the island to warn about
underground contamination  and hazards incurred  by  excavation in
those areas. Notices would be posted within  buildings to inform
employees of hazards.

Institutional  controls  would  also be  imposed.    One  type  of
institutional control  which could be used is deed notices. Deed

                                29

-------
notices would warn future property owners of the contamination on
their property and would specify that contaminated soil excavated
in the  future be properly handled and disposed  of in accordance
with state and federal regulations.

Alternative  2 would  be  easily implemented.   Reduction  in risk
relies on the education of workers  and property owners in addition
to  the  enforcement  of  safety  regulations.    Since  numerous
businesses and heavy  industrial activity exist across the island,
enforcement  of  safety regulations may be difficult.   Over long
periods of  time,  the hazards, safety requirements,  and need for
protective clothing could be forgotten;

This alternative does not treat or contain the contaminated soil.
The toxicity, mobility,  and  volume of the contaminated materials
can  be  expected  to remain  in  the current condition  for  an
indefinite period of time.

Costs and Remediation Time Frame

The estimated capital costs  for  this alternative  are $180,000.
There are no operation and maintenance costs associated with this
alternative.

The institutional  controls alternative  would take  ten months to
implement.

Physical Effects on the Environment Caused by Implementation

The physical  effects on the  environment are minimal,  since the
alternative incorporates no constuction.

Compliance With ARARs

This alternative would not meet any  ARARs (see  page 81) since no
treatment or  containment would be performed.   Concentrations of
organics  in   the  groundwater  may  decrease   through  natural
attenuation; the number of years for  the concentration to decrease
to cleanup goals cannot be predicted  with  any degree of certainty.


Alternative 3:  Soil Containment

Major Components of the Remedial Action

This  alternative  consists  of  capping  over  areas  where  the
contamination  exceeds   surface  and subsurface  cleanup  goals
identified  in Table 7.   The intent of  this action would  be to
minimize  the  transport  of   the  contaminants   by   rainwater
infiltration  and  to prevent  dermal  contact or  ingestion of the
contaminated soil by personnel working on site.   This alternative
also includes engineering, safety, and  institutional controls as

                                30

-------
described in Alternative 2.

Treatment Component

This alternative has no treatment component.

Containment Component

Approximately  420,000  square yards  (about 40 acres), ~which are
currently uncovered and exceed cleanup goals, would be graded and
capped.  The design of  the cap would be based on the subsequent use
of each capped area.  At a minimum, a 3-inch-thick asphalt cap with
a mimimum permeability of 10'5 cm/sec would be required. In heavy
industrial  areas,  a thicker  asphalt cap or  a reinforced,  high-
strength concrete cap may be required to  support  heavy loads.  Any
existing  asphalt or  concrete caps  which  are damaged would  be
resurfaced.  A fence and/or warning signs would be placed around
areas  where  capping   is  impractical  or  ineffective.    Covered
surfaces would be inspected quarterly and repaired if needed.

Capping reduces the mobility of contaminants by providing a barrier
to infiltration which  causes  leaching of the organics and metals
and  by  eliminating   erosion.    Because  caps  do  not  destroy
contaminants,  they  provide no  reduction in  toxicity or  volume.
However, a reduction in toxicity and volume may be seen over, time
due to natural biodegradation of the organics.  Long-term, periodic
maintenance  of  the   cap  would  be  required  to  maintain  its
effectiveness.

General Component

In preparation for capping,  some areas would be regraded  to enhance
surface drainage.  Placement of the crushed rock  sub-base would be
done in a manner that does not disrupt surface drainage. Excavation
of contaminated soil would be kept to a minimum.

Resurfacing paved areas on site with a surface treatment would be
performed, although a  thorough inspection of all pavement on site
would be required to ensure  that all damaged areas are located and
repaired.  This would require moving heavy equipment and stockpiled
scrap  materials   to  fully   investigate  pavement   conditions.
Quarterly noncompliance inspections for all covered areas, as well
as periodic maintenance of damaged caps would be implemented.

Because contamination  would remain on site, engineering,  safety,
and institutional  controls  would be  implemented as  described in
Alternative 2.

Costs and Remediation  Time Frame

The estimated present worth cost  for  this alternative  is $15


                                31

-------
million.  Capital costs, which include regrading and capping, are
$8.3 million.  Operation and maintenance costs are $6.7 million and
include cap inspection and repair.  The cost estimate provided for
this alternative, as well as the estimates ^or other alternatives
which include a cap, are based on the minimum 3-inch asphalt cap.
The  identification  of  areas which  will require a  high-strength
concrete cap, and the cost of this cap,  will be determined in the
remedial design phase.

Containment and associated engineering,  safety, and institutional
controls would take 2 years to complete.

Physical Effects on the Environment Caused by Implementation

Minimal impacts to the environment would be associated with capping
exposed portions of  the  site.  Areas would be graded, compacted and
paved at one time, minimizing the risk to the environment.  During
wet weather, shallow ditches would be placed around work areas to
minimize  runoff.    This  would  minimize  the  potential  for  the
transport of contaminated soil  into the storm drain system and into
the environment.

Compliance With ARARs.

This alternative  would  meet  all  ARARs except for  the Clean Water
Act and the  Washington  Water Pollution  Control Act which protect
surface water quality at  the shoreline.  These ARARs would not be
met because  of remaining high levels of  petroleum contamination
left in the soil and floating on  the goundwater which would act as
continuing  sources  of  contamination  to  the surface water.  The
cleanup goals  for  soil would be  met through  capping,  invoking
institutional controls, and compliance monitoring.   Capping would
provide protection by isolating contaminated soil to remove human
exposure pathways.  The  cap would also mitigate further degradation
of groundwater by reducing infiltration  of rainwater and migration
of contaminants  to  the groundwater.  Institutional  controls and
long-term monitoring would also be implemented in compliance with
MTCA.


Alternative 4:  Soil Incineration/Solidification

Major Components of the Remedial Action

This alternative consists of excavating all soil contaminated above
cleanup  levels with  organics  and  inorganics, transferring the
material to an on-site treatment  area, and treating it to levels at
or below cleanup standards.  Soil contaminated with organics would
be incinerated,  and soil  contaminated  with  inorganics  would be
solidified.   Soil  with both organic and  inorganic contaminated
would be incinerated first and subsequently solidified.  In areas
where  excavation could not be  implemented,  warning  signs and

                                32

-------
information and  safety meetings would be implemented as described
in Alternative 2.

Treatment Component

A transportable  incinerator and stabilization and solidification
processing equipment would be set up on the island.  The treatment
area required to locate the incinerator, solidification equipment,
a  stockpile  area,  mobile  laboratory,   and  pollution  control
equipment  is  approximately 400  feet  long  by  300  feet  wide.
Contaminated soil would be transported to the treatment area.  Soil
would  be stockpiled  in  the treatment area in  accordance  with
Washington Dangerous Waste Regulations.  The stockpile area would
have an impermeable bottom.  Asphalt curbing would be provided to
prevent run-on/runoff.

Soil  contaminated  with  organics  would   be screened  prior  to
incineration.     Approximately  474,000   cubic   yards   of  soil
contaminated with  organics would  be treated in the transportable
incinerator.  A destruction and removal efficiency (ORE) of 99.9999
percent would be achieved for PCBs and a ORE of 99.99 percent would
be  ahcieved   for   other  organic  contaminants.    Incineration
permanently destroys organics and achieves almost total reduction
in contaminant toxicity and volume.   Trial  burns  would be required
prior  to  incineration  of  contaminated  soil  to determine  the
destruction  efficiency and  performance of  air  emission control
equipment.  A continuous emissions monitoring system would be used
in conjunction with air  pollution  control equipment  to regulate
emissions from the incinerator.  Treated soil would be sampled for
total organic concentration to ensure that  soil cleanup goals were
achieved before  it was placed back  in the  ground.

Approximately  300,000  cubic  yards  of soil contaminated  with
inorganics would be fed directly into the  solidification process.
The soil would be  solidified to stabilize the inorganics, tested
according to the TCLP leachate  method,  and  placed in the ground if
it passes the TCLP test.  Solidification tests performed on Harbor
Island soil indicates  that this process may be implemented as an
effective   method    to   immobilize   inorganic   contaminants.
Treatability studies were performed  during the feasibility study to
quantitatively evaluate the  potential success of a process option
to meet cleanup goals.  Solidification testing was performed using
materials common in the cement  industry and/or in common use.  Lead
was used as the design controlling  contaminant as an indicator of
the overall performance of the  technology.   The solidified samples
prepared under optimum conditions displayed a reduction in leachate
concentrations of 2 to 3  tiroes when compared to  untreated soil.

Soil contaminated  with both organics and  inorganic contaminants,
approximately 92,000 cubic yards, would be incinerated to destroy
organic  contamination   and subsequently  processed  through  a
solidification treatment  system to  treat inorganic contamination.

                                33

-------
This solidified soil would be tested according to the TCLP method
before being placed in the ground.

Containment Component

This alternative has no containment component	 .

General Component

Excavation would require removal of asphalt or concrete surfaces to
access the soil.  The asphalt and concrete would be pressure-washed
to  remove  adhering soil.   After all contaminated soil  had been
removed, the concrete and asphalt would be taken to a construction
landfill for  disposal. Contaminated soil  would be  removed from
under pavement and around utilities  but  not from under permanent
buildings.  Contaminated  soil  would be  excavated  in  cells  and
transported via  trucks  to the  treatment  area.   Soil  would  be
preprocessed through a  screening  and crushing  operation prior to
incineration.

Following treatment, treated soil would be loaded onto trucks and
taken to the cell it came from to be  used as backfill.  Clean fill
would be brought  in to return the site  to  the  current grade,  if
necessary.    Excavation  would  be performed around  underground
utilities and pipes and beneath pavement  to minimize disruption of
services.   Areas  under buildings and major permanent  structures
would not  be  excavated.  In  areas where excavation could  not be
implemented, warning signs would be posted to notify workers that
training and  personal  protective equipment  are  recommended when
conducting industrial and construction activities as described in
Alternative 2. Information and safety meetings would be offered to
employees to warn  them of any remaining hazards.

Dust suppression methods  would be used  to minimize fugitive dust
generated during remedial actions.  Daily cleaning of paved roads
would be performed using vacuum  sweeping.  Contamination controls
(i.e.,  dust  abatement  and  run-on,   runoff controls)   would  be
provided  for  excavation,  stockpiling,  and  treatment  areas.   A
debris washing station  would be constructed near the soil screening
operation.  Debris screened from the soil, in addition to asphalt
and concrete removed during excavation,  would be washed.

Costs and Remediation Time Frame

The total present worth cost for this alternative is estimated at
$245  million.     Capital  costs,   $17   million,   include  site
preparation, mobilization, and equipment  costs and construction of
the treatment area. Operation and maintenance costs, $228 million,
include excavation of the soil, incineration, solidification, and
implementation  of  warning  signs  and  information  and   safety
meetings.
                                34

-------
The  time   required   to  implement  this  alternative  would  be
approximately 130 months  (10.8 years).

Physical Effects on the Environment Caused by Implementation

This alternative has activities that have the potential to impact
the  environment.     These  activities  consist  of  excavation,
incineration/solidification system installation and operation, soil
transport, material handling and storage and treated soil handling.
To  mitigate the  risks to the environment from  these  actions,
certain precautions and procedures would be implemented.

Implementation  of  this alternative  would  require  excavation of
approximately 900,000 cubic yards of soil at numerous locations on
the island.  Ditches  and/or berms and tarps would be used during
excavation  to  eliminate  contaminated  runoff  and  protect  the
environment.   Control  of contamination would  be  implemented by
setting up  contamination  control  zones.    Workers  and equipment
would require decontamination before leaving  the zones.   Hazards
from  dust  and  contaminated  runoff from  handling,  storing  and
screening untreated soil  would be minimized by using ventilation
and dust collection systems  on the soil screening and cement off-
loading equipment,  by covering loads of soil as  it is being moved,
by  keeping  the soil  moist,  and  by storing  all soil  on double
contained and covered pads.

Compliance With ARARs

This alternative would meet all ARARs.  Soil  cleanup goals would be
met through incineration  and stabilization  of all soil above the
cleanup goals.  Emissions  generated  during the remedial  actions
(e.g., incineration, excavations,  etc.) would be controlled to meet
Puget Sound Air Pollution Control  Authority  (PSAPCA) requirements.
The incinerator will also  be operated in conformance with Dangerous
Waste  incinerator  performance  standards,   and  will achieve  the
99.9999 percent destruction removal efficiency for  PCBs•to meet
TSCA   incinerator   requirements.   Any   construction  activities
performed within 200 feet  from the shoreline will be performed in
conformance with the Shoreline Management Act.


Alternative 5:  Soil Bioremediation/Solidification

Major Components of the Remedial Action

This  alternative  consists of  in situ  bioremediation of  areas
contaminated with the organic contaminants  of concern, excavation
and  solidification of areas  contaminated  with  inorganics  and
landfarming and  solidification of areas contaminated  with both
organics and inorganics.   In areas where excavation could not be
implemented, warning  signs  and  information  and  safety meetings
would be implemented as described  in Alternative 2.

                                35

-------
Treatment Component

In situ bioremediation of soil would be implemented by constructing
*  series of  infiltration  galleries  in  areas contaminated  with
organic   contaminants  only.     Approximately  70   independent
infiltration systems would be installed,  each with its own set of
tanks,  pumps,  instruments  and  pipes.    Oxygenated  water  and
nutrients would be pumped  into  the soil  through  the infiltration
system   to  enhance   bacterial  growth   and  degrade   organic
contaminants.   Extraction  wells  would  be  installed around  the
systems to remove the infiltration solution and recycle it back to
the feed tank.

In areas which are only contaminated  with  organics  and  which are
currently covered by  pavement,  the pavement  would be removed and
infiltration galleries would be  installed.  These areas would then
be  repaired.    Areas  under buildings would be  left to  slowly
biodegrade under natural conditions.

Soil having  both  organic and inorganic  contamination,  and areas
where the organic contamination is limited to surface soil, would
be  excavated,  loaded  into  trucks and  transferred  to an  area
established  for  landfarming.    The  landfarming area  would  be
approximately 650 feet long by 500 feet wide.  Approximately 92,000
cubic yards  of soil  would  be excavated for  landfarm treatment.
Landfarming would biologically  degrade the organic  contaminants.
Following  landfarming,  the  soil  would  be  sent  through  a
solidification process to treat inorganic contamination.

Areas  contaminated  with  inorganics  only  would  be  excavated,
transferred  and  directly  treated  through  the  solidification
process.  Approximately 300,000 cubic yards  of soil contaminated
with inorganics would be treated in this manner. After treatment by
landfarming or solidification,  soil would  be tested according to
the methods identified in  alternative 4  before being returned to
the ground.

The effectiveness of  in situ bioremediation to meet cleanup goals
is  uncertain,  as   this  technology  has   limited   full  scale
demonstration.    Site-specific  treatability  studies  would  be
required to ensure that bioremediation would effectively degrade
site contaminants in  the soil.  A pilot project demonstration would
be required to confirm that  soil  cleanup goals could be met.   In
situ bioremediation and landfarming would continue until the soil
cleanup goals were reached.

Reductions of  TPH as  high  as 95  percent  have  been demonstrated
using in situ bioremediation.  Significant reductions in volitile
organics  and  methylene  chloride  may  also  be  expected,  but
implementing a  reduction of  PCBs through bioremediation  may be
difficult to achieve.  Most organics may be degraded to  levels below
their treatment  levels within  one  year  using landfarming.   The

                                36

-------
effectiveness  of  landfarming  PCB  contaminants  in  soil  is  not
proven.    Installing  a  landfarming  operation  on  site may  be
difficult due to the large area (approximately 3 acres) required.

Containment Component

This alternative has no containment component.

General Component

Excavation and backfill, as well as contamination  control, would be
implemented  as described  in  Alternative  4.    Dust suppression
methods  and  contamination  controls  would  be  implemented  as
described in  Alternative  4.   Areas which could  not be excavated
would be covered by engineering, safety,  and institutional controls
as described in Alternative 2.

Costs and Remediation Time Frame

The ability  to effectively  degrade site contaminants  to levels
below  cleanup goals through  in situ bioremediation is unknown,
because  full-scale  implementation  of   this  process   is  not  a
demonstrated technology.  The  remediation time  frame for in situ
bioremediation, therefore, has some uncertainty.

The total present worth cost  for this alternative is  $117 million.
Capital costs, $13 million, include landfarming and solidification
processing  of  soil  and  installation  of  infiltration systems.
Operation and maintenance costs, $104 million, include activities
associated with maintaining and operating the infiltration system,
excavation  and implementation  of  the  engineering,  safety,  and
institutional controls.

This alternative would  take approximately 87  months  (7.25 years) to
implement.

Physical Effects on the Environment Caused by Implementation

This alternative  contains  activities that have  the potential to
impact the environment.  These activities consist  of excavation, in
situ bioremediation, landfarming,  solidification, soil transport,
material handling and storage,  and treated soil handling.  Hazards
to the  environment from these activities  would be minimized by
imposing the precautions and procedures described in Alternative 4.
This alternative would cause minimal impacts to the  environment.

Compliance With ARARs

Treatment of  contaminated  soil by  landfarming  and  stabilization
would meet all  ARARs.  However, the degree to  which soil cleanup
goals would be met using in situ bioremediation is uncertain/ since
this technology has had limited full-scale demonstration. Emissions

                                37

-------
generated during the remedial actions would be controlled to meet
PSAPCA requirements. Landfarming would be performed in conformance
with Dangerous  Waste landfarming requirements.  Any  construction
activities performed within 200 feet from the  shoreline will be
performed in conformance with the Shoreline Management Act.


Alternative 6:  Solvent Extraction and Solidification

Major Components of the Remedial Alternative

In  this  alternative, organics  in soil would  be extracted  by a
solvent extraction  process,  and inorganics would  be solidified.
Mixtures (soil contaminated with organics and inorganics) would be
treated by solvent extraction followed by solidification.  In areas
where  excavation  is   impractical,  engineering,   safety,   and
institutional controls would be implemented as in Alternative 2.

Treatment Component

Excavated  soil   would   be  transported  to  a  treatment  area
(approximately 300 feet long by 250  feet wide) which would include
a  solvent  extraction system and solidification process.   Soil
contaminated  with  organics  would  be   treated  using  solvent
extraction.   Waste water  generated from the  solvent extraction
process could be treated and discharged to the POTW or used in the
solidification process.  Soil contaminated with inorganics would be
treated with the solidification process as described in Alternative
4.    Soil  contaminated with mixtures of organics  and inorganics
would be treated first  in the solvent extraction process to remove
organics  and subsequently  with  the  solidification process  to
stabilize the inorganics.  After treatment by solvent extraction or
solidification,  soil  would  be tested according to  the methods
identified in alternative  4  before being returned to the ground.

Solvent extraction processes have been demonstrated to be effective
in  laboratory  scale treatability  studies,  but  few have  been
successfully demonstrated  in full-scale  field remedial projects.
Approximately 90  to  95 percent of organic contaminants have been
removed in treatability and prototype pilot studies. Solvents used
in  the  process  would  be  regenerated  and   recycled.  Organic
contaminants  removed from  the soil  would  be  sent  off-site for
incineration.or disposal in  a hazardous waste facility.

Solvent extraction treatability studies using methanol and acetone
were performed  during  the  Harbor   Island  feasibility  study to
determine the effectiveness  of removing organic  contaminants from
soil.  Polychlorinated biphenyls (PCBs) and  PAHs were the organics
targeted for removal. These organics are  the major  health risks in
Harbor  Island  soil.  The   results  of  the  solvent  extraction
treatability studies indicated that acetone was a better solvent
than methanol.  Approximately 96 percent of the PCBs and 84 percent

                                38

-------
of  the PAHs  were  removed  in  the  extraction tests.  Additional
prototype testing would be needed to  fully demonstrate the removal
efficiency of this process.

Construction of a treatment facility that would house the solvent
extraction  unit,  stabilization  process,  screening  apparatus,
stockpiles, and mobile laboratory would require approximately two
acres.  Although areas of this size are*available on Harbor Island,
permission to  use an areas of this  size  could be  difficult to
obtain.

Containment Component

This alternative has  no containment component.

General Component

Alternative 6 consists of excavation and  treatment of approximately
474,000 cubic  yards of organic contaminated  soil,  300,000 cubic
yards  of  inorganic contaminated soil, and 92,000 cubic yards of
organic and inorganic contaminated soil.

Excavation and backfill contamination control would be conducted as
described  in Alternative  4.   Dust suppression  and  run-on/runoff
controls would be  implemented as  described  in Alternative 4.  In
areas  where  excavation  is impractical,  engineering,  safety, and
institutional  controls  would  be implemented  as  described  in
Alternative 2.

Costs and Remediation Time Frame

The  estimated  present worth  cost for  this alternative  is  $184
million.    Capital   costs,  which  include  the  soil  treatment
equipment, are  $9  million.   Operation  and  maintenance  costs are
$175 million and include excavation, treatment, and implementation
of engineering, safety,  and institutional controls.

This alternative would take 175 months  (14.6 years)  to complete.

Physical Effects on the Environment Caused by Implementation

This alternative predominantly consists of the same activities as
Alternative 4, which  are  soil  excavation  and transport, material
handling  and  storage,  and  construction  and  operation  of the
treatment  process.    Potential  environmental  hazards  exist due
primarily  to  runoff containing contaminated  material.    Run-
on/runoff controls (i.e., stockpile pads, ditches,  and tarps) would
be used to minimize  the  potential  impact to the  environment as
described in Alternative 4.  Other precautionary measures would be
implemented as described in Alternative 4.

Compliance With ARARs

                                39

-------
This alternative  would be designed  and  implemented to meet all.
ARARs. Soil cleanup goals  would be met by solvent extraction and
stabilization  of all  soil  above  the cleanup goals.  Emissions
generated during the remedial actions would be controlled to meet
PSAPCA requirements.  Any construction activities performed within
200 feet from the shoreline will be performed in conformance with
the Shoreline Management Act.


Alternative 7:  Soil Off-Site Treatment and Disposal

Major Components of the Remedial Action

This  alternative consists  of  excavating  areas  that have  soil
exceeding cleanup goals and  transporting the  soil to an off-site
treatment  and/or  disposal  facility.    Soil  contaminated  with
organics (474,000 cubic yards),  inorganics  (300,000 cubic yards)
and both organics and inorganics  (92,000  cubic yards) would be
excavated.   Areas that could not be excavated would be subject to
engineering, safety,  and institutional controls  as discussed in
Alternative  2.    The  excavated  areas  would  subsequently  be
backfilled with clean fill.

Treatment Component

Soil containing  organics  or mixtures of organics and inorganics
that include PCBs in excess of 50 mg/kg (approximately 2,000 cubic
yards)   would  be  transported  to  an  off-site  incinerator  for
treatment.     After  incineration,   the  soil  residue  would  be
transported to a hazardous waste landfill  for solidification, if
necessary,  and disposal.   Soil containing organics or mixtures of
organics  and  inorganics  including  less  than  50  mg/kg  PCBs
(approximately 201,000 cubic yards)  would be  tested  by  the TCLP
method to determine if it qualifies as a RCRA characteristic waste.
Any portion of the soil which is a RCRA waste would be transported
to an off-site hazardous  waste disposal facility for stabilization
and disposal. Soil which is not a RCRA waste would be taken to an
approved sanitary  landfill.    Soil  containing   inorganics  only
(approximately 300,000 cubic  yards)  would be  treated in the same
manner.  Soil  containing  only total  petroleum hydrocarbons  (TPH)
exceeding the cleanup goal of 200 mg/kg (363,000 cubic yards) would
be disposed in a local regulated landfill.

Containment Component

Soil exceeding cleanup  goals is taken off-site  for containment.
There is no on-site containment component in this alternative.

General Component

Excavation and backfilling of the soil  would be performed  in  cells
as  described  in  Alternative  4.  Decontamination  pads would be

                                40

-------
constructed  at  critical  locations  to  minimize the  spread  of
contamination from excavation equipment and transport trucks.  The
transport  trucks would  be decontaminated  prior to leaving  the
rontaminated areas to minimize the spread of contamination to other
areas of the site and to the roadways. Immediately after the soil
was excavated for off-site  disposal, clean fill would be brought in
to backfill the hole.  Roadways, parking lots and  operational areas
would be repaved with asphalt after backfilling. Dust and organic
emission suppression would be implemented; contamination control
addressed as discussed in Alternative 4.  Areas that could not be
excavated   would  be   subject  to   engineering,  safety,   and
institutional controls as discussed in Alternative 2.

This alternative would  be difficult to  implement because  of  the
large volume of soil which must be excavated and transported  off
site for disposal.  Limitations of institutional controls are the
same as discussed in Alternative 2.
Costs and Remediation Time Frame

The total present worth cost for this alternative is estimated to
be $220 million.  Capital costs, which include equipment purchase
for  excavation and  transport,  are $12  million.    Operation and
maintenance  costs  are  $208  million  and  include  excavation,
transport, and disposal expenses, fill and regrading expenses, as
well as implementation  of  engineering,  safety,  and institutional
controls.  Alternative  7  would  take 62  months  (5.2 years)  to
implement.

Physical Effects on the Environment Caused by Implementation

Activities that would occur under this alternative consist of soil
excavation, transport and backfill of excavated areas with imported
soil. Off-site disposal  would require hauling the contaminated soil
to  either  an off-site hazardous  waste  landfill,   an  off-site
incinerator,  or  a  local  landfill  permitted  to  accept  TPH-
contaminated  soil.   This  would require approximately  40,000 to
60,000 truck loads of material to be transported  to the appropriate
facilities.   The two main hazards associated  with this include
vehicle accidents  and  spread  of contamination off-site.   Truck
payloads would be covered with tarps to prevent loss of material.

Environmental risks  would  be  associated with contaminated runoff
from the  excavation areas.   This would be  minimized by placing
ditches or berms around the work location.   In addition, vehicle
accidents resulting in an overturned truck could cause a release of
contaminated soil into the  environment.  The adverse impacts to the
environment would depend upon the accident location and conditions.
                                41

-------
Compliance With ARARs

This  alternative  will be  designed and  implemented to  meet all
ARARs. MTCA goals  for soil would be met Jn this alternative through
removal  and   off-site   disposal.   Any   construction  activities
performed within  200 feet from the shoreline will be performed in
conformance with  the Shoreline Management Act.


Alternatives 8 Through 11
Definition of Hot Spot Treatment Levels

Soil  contaminated  with  TPH,   lead,  mercury,  PCBs,  and  mixed
carcinogens at concentrations significantly above the cleanup goals
(Table 7) were identified as "hot spots" in the Feasibility Study.
The precise contaminant concentration which defines  a hot spot was
originally called the "cleanup action level" but is  now called the
"treatment  level",  to  indicate that it  is the  level  at  which
contaminated soil will be excavated and treated in alternatives 8
through 11.  For each hot spot  contaminant, the selected treatment
level is based on  a cost-benefit analysis or on existing regulatory
limits.  The treatment levels for lead, mercury, and TPH  are based
on a cost-benefit analysis which compared the cost of treating the
entire volume of  soil above each contaminant concentration to the
benefit,  which is  the  total  mass  of  contaminant removed and
treated.  The  treatment  levels for  lead, mercury,  and  TPH were
selected at the point where the incremental mass  of contaminant
treated was found to be disproportionate to the incremental volume
of contaminated soil.    Appendix B describes in more  detail the
method used for selecting the treatment levels for  lead, mercury,
and TPH by this method.

The  treatment  level for  PCBs is  based  on  the   federal  Toxic
Substances  Control   Act  (TSCA) regulation  which  specifies that
concentration of PCBs exceeding 50 rag/kg must either be incinerated
or disposed in a  hazardous waste disposal facility. The  treatment
level  for mixed  carcinogens  is based  on  the exceedance  of the
highest acceptable risk  (1 x 10"*)  for Superfund sites as  specified
by the National Contingency Plan (NCP).

The treatment levels selected for  the hot spots, shown  in Table 9,
represent approximately  20 percent of the total contaminated soil
volume, but contain approximately 70  percent of the total volume of
contamination.    Through this  approach  of  identifying these hot
spots, the volume  of soil representing the greatest threat to human
health and the environment could be  treated to permanently  reduce
its  toxicity   in  a   cost-effective  manner.    Figure 5  shows the
approximate locations of organic and inorganic  hot  spots on  Harbor
Island.
                                42

-------
                    Table 9— Soil Hot Spot Treatment Levels

                  Item	Surface Soil	Subsurface Son

                  Risk       > 1 x 10"4       Does not apply

                  PCBs      > 50 mg/kg     > 50 mg/kg

                  Lead       > 10.000 mg/kg   > 10.000 mg/kg

                  Mercury    > 5 mg/kg      > 5 mg/kg

                  TPH	> 10.000 mg/kg   > 10.000 mg/kg


Alternative  8A:   Soil Hot Spot Solvent Extraction/Solidification
              and Containment

Major Components of this Remedial Alternative

Alternative 8A consists of solvent extraction and/or solidification
of areas containing contaminant concentrations above the treatment
levels for organics and  inorganics. Following hot spot removal and
treatment, the remaining  areas contaminated above  cleanup goals
would  be  capped.   In  areas  where  excavation  is  impractical,
engineering,   safety,   and  institutional   controls   would  be
implemented  as discussed in Alternative 2.

Treatment Component

Approximately 94,200 cubic yards of surface and  subsurface soil
contaminated with  organics above the  treatment  levels  would be
excavated and processed  in an on-site solvent extraction system as
in Alternative 6. Treated organic hot spot soil would be tested for
total   organic   and   inorganic   concentrations   and   inorganic
contaminant  leachability,  according to  the  TCLP method,  before
being returned to the soil. Soil which fails the TCLP test would be
considered a  RCRA characteristic  waste.  This soil would have to be
solidified so that it no  longer  fails  the TCLP test before being
returned to the ground.  If soil passes the TCLP test, but contains
organics or inorganics above  the  cleanup goals, it would be placed
in the  ground and  capped.   Approximately 85,000 cubic yards of
surface and subsurface soil contaminated with inorganics  (lead and
mercury)  above   the  treatment   levels  would  be  excavated  and
solidified until  it passes, the TCLP test, as in Alternative 6.

An on-site  treatment  area would  be  constructed  as  described in
Alternative  6.  This  alternative has  the  same  destruction and
removal efficiencies (DREs), treatability and prototype pilot study
requirements, and limitations as Alternative 6.
                                 43

-------
             Figure 5
     Soil Hot Spot Locations
Combined Organic
and Inorganic

-------
Containment Component

Areas  where the  soil exceeds the  cleanup goals for  TPH, lead,
arsenic, mercury,  PCBs,  and PAHs would still exist after hot spcL
removal.   Much of this area is presently  covered  with existing
impermeable barriers  of asphalt and concrete.  The remaining areas
not covered by asphalt/concrete would be capped with  a  3 inches of
asphalt for non-load-bearing surfaces. Load-bearing surfaces would
require a thicker asphalt cap  or reinforced concrete cap.  The area
to be capped is approximately 3.4 million square feet  (40 acres).
In addition,  an inspection would be  performed to identify areas
where existing impermeable barriers were cracked or damaged.  These
areas would be patched or sealed.  The  capped surfaces would be
maintained as described  in Alternative 3.
General Component

Excavation  and  backfill  would  be  conducted  as   described  in
Alterative 4.   All treated soil  would be transported back to its
original  location  to be  used  as  backfill.   Dust suppression
methods, run-on/runoff controls, and contamination controls would
be implemented as  described  in Alternative 4.   In areas where
excavation is impractical, engineering, safety,  and  institutional
controls  would be implemented  as  described  in Alternative  2.
Limitations  of  the  engineering,   safety,  and   institutional
controlsare the same  as  those described in Alternative 2.

Costs and Remediation Time Frame

Capital  costs,  which  include  the  solidification  and  solvent
extraction equipment, are estimated to be $6.2 million.  Operation
and maintenance costs are $76.5 million and include excavation,
treatment,  maintenance   of  the  cap,   and  implementation  of
engineering, safety,  and institutional controls.

Alternative 8A would take 57 months (4.75 years) to implement.  The
total present worth cost for  this alternative  is estimated to be
$83.2 million.

Physical Effects on the Environment Caused by Implementation

This alternative has the same  potential risks to the environment as
described in Alternative 6.   However, the  risk  would be reduced
substantially due to confinement of  the remedial activities to hot-
spots.  Environmental risks would still consist of potential damage
due to contaminated runoff.   However, with fewer locations being
remediated, the potential for  environmental damage would be reduced
below that anticipated in Alternative 6.
                                45

-------
Compliance With ARARs

This  alternative will  be  designed  and  implemented to  meet all
ARARs. ARARs  would  be met by selective: treatment (extraction and
stabilization)  of soil  contaminated above  "hot spot"  treatment
levels, followed by capping the- remaining soil above cleanup goals
with   long-term  monitoring   of  the   capped   areas.   Although
concentrations  above cleanup  goals  for  lead, arsenic,  mercury,
PCBs, and TPH will  remain in the unexcavated  soil,  capping would
protect  human   health   and   mitigate  further  degradation  of
groundwater  from infiltration. Some of  the  remaining  organics
exceeding  cleanup  goals  would naturally attenuate  over  time.
Emissions generated during the remedial actions would be controlled
to meet PSAPCA requirements. Any construction activities performed
within 200 feet from the shoreline will be performed  in conformance
with the Shoreline Management  Act.


Alternative    8B:    Soil    Organic    Hot   Spot    Solvent
Extraction/Solidification and  Containment

Major Components of  the Remedial Action

Alternative 8B  is similar to 8A except that only the organic hot
spots previously  identified for PCBs, TPH, and  risk greater than
10"*, are included. The soil volumes,  associated with  each treatment
level for the organic hot spots, are shown in Table 10.


                    Table 10— Organic 'Hot Spot" Volumes


     Soil Type                                Volume (Bank Cubic Yards)

     TPH greater than 10.000 mg/kg                             91,000

     PCBs greater than 50mg/kg                                2,000

     Mixed Carcinogens with risk greater than 10"4                     1.200

     Total                                               94,200
The organic hot spots  are selected for treatment here  (as well  as
in alternatives 9B, 10B,  and 11B) because TPH, which is associated
with all the organic hot  spots, is mobile in soil and groundwater.
It could,  therefore,  be  reasonably expected to  migrate into the
groundwater, and ultimately into surface water surrounding Harbor
Island.   In  addition,  these organic hot spots  pose a significant
potential risk to human health and marine organisms because the TPH
contains  carcinogens  such as  PAHs  which bioaccumulate readily  in
marine organisms  and  pose a potential  risk to  humans who consume
these organisms.


                                46

-------
In this alternative, approximately 94,000 cubic yards of soil with
organics above the treatment level would be excavated and processed
in an on-site solvent extraction system as in Alternative 6.  Areas
contaminated   above   the   cleanup  ~o?1«?  but  below  hot  .sppts
concentrations,  would  be capped  in  place  as  described  in
Alternative 3, rather than treated.

In  areas   where  extraction  or   containment  is  impractical,
engineering,   safety,   and   institutional  controls  would  be
implemented as described in Alternative 2.

Treatment Component

Approximately  91,OOO cubic yards  of soil contaminated with TPH
would be excavated and treated in  an  on-site solvent extraction
system as described  in  Alternative 6.   Approximately 3,200 cubic
yards  of soil  contaminated with  mixed  organics  would  also  be
excavated and  treated  in  the  on-site solvent extraction process.
After treatment, organic hot spot soil would be tested for total
inorganic concentrations and for leachability of inorganics, as in
alternative  8A,  to  determine  if  solidification  or capping  is
necessary prior to replacing the treated soil  in the ground. This
alternative has  the same  removal  efficiencies, treatability and
prototype study requirements, and limitations  as Alternative 6.

Containment Component

Areas where  the soil  exceeds  the  cleanup goals  for  TPH,  lead,
arsenic, mercury, PCBs, and PAHs would still exist after hot spot
removal.   Much of this area  is presently covered with existing
impermeable barriers of asphalt and concrete.   The  remaining areas
not covered by asphalt and concrete would be capped with asphalt.
The area to  be capped  would be  slightly  less than 40 acres.
Damaged existing surfaces would be resurfaced.  All  capped surfaces
would  be  inspected  quarterly  and replaced  as  needed.    This
alternative  has the same containment  component  limitations  as
Alternative 3.

Tests conducted during the remedial investigation to determine the
adsorption of inorganics to soil showed that inorganics have a high
affinity for the soil and have a low mobility  in the groundwater.
In  addition,   groundwater  transport  modeling  conducted  in the
feasibility study  indicates that  the inorganics currently in the
groundwater will take more than  50 years to reach the shoreline.
Capping, with proper long-term maintenance, is expected to further
decrease the mobility of  inorganics in the hot spots by reducing
the infiltration of  rainwater through these areas.

General Component

Excavation  and  backfill   would  be conducted  as described  in
Alternative 4.  All  treated soil would be transported back to its

                                47

-------
original location to be used as backfill.  Dust suppression, run-
on/runoff controls, and contamination controls would be implemented
as  described  in  Alternative 4.   In  areas  where excavation  is
impractical, engineering, safety,  and  insti^'-t.rmal controls would
be implemented as described in Alternative 2.

Costs and Remediation Time Frame

The total present worth cost for this alternative is $54.7 million.
Capital  costs are  $6.7  million  and  include  site  preparation,
mobilization,  and  the  solvent  extraction  and  solidification
processing  equipment.   Operation  and maintenance costs  are  $48
million and include excavation, treatment, maintenance of the cap,
and  implementation  of  engineering,   safety,  and  institutional
controls.

Alternative 8B would take 57 (4.75 years) months to implement.

Physical Effects on the Environment Caused by Implementation

This  alternative  would  pose  the same  potential risks to  the
environment as described in Alternative 8A.

Compliance With ARARs

Solvent  extraction/solidification  of  hot  spots,  followed  by
containment  of the  remaining  soil,  would  achieve all  ARARs  as
described in Alternative 8A.


Alternative  9A:  Soil  Hot Spot  Off-Site Treatment/Disposal  and
Containment

Major Components of the Remedial Action

This alternative consists of selective off-site disposal of areas
highly contaminated with organics and/or inorganics ("hot spots),
as  defined in Alternative 8A,  followed by containment of  the
remaining portions of the site.  Excavated soil  hot spots would be
classified into types  based  on disposal  options,  as  discussed in
Alternative 7.  Soil  contaminated  with  organics  or  mixtures  of
organics and inorganics, which contain PCBs  in excess of 50 rag/kg
(2,000 cubic yards), would be taken to an off-site incinerator for
treatment and disposal.  Soil contaminated with  TPH and inorganics
(71,000 cubic  yards), and soil containing inorganics only (85,000
cubic yards) would be taken to an off-site hazardous waste disposal
facility for disposal.  Soil containing only TPH above 10,000 mg/kg
(21,000 cubic yards) would be taken to a  landfill that accepts TPH
contaminated soil.

In  areas   where  excavation  or  containment   is  impractical,
engineering,   safety,   and   institutional   controls   would  be

                                48

-------
implemented as described in Alternative 2.

Treatment Component

Alternative 9A includes only one treatment component, the off-site
incineration of hot  spots  containing PCBs  in excess of 50 mg/kg.
This  treatment  component   has  the  same  DREs as  discussed  in
Alternative 7.

Containment Component

As discussed in Alternative 8A, the remaining lower contaminated
areas would  be capped with  asphalt or concrete, and  cracked or
damaged existing impermeable barriers would be patched or sealed.
The  containment  component  of  this alternative  has  the  same
limitations as discussed in Alternative 3.

General Component

Excavation  and  contamination   control  would  be  performed  as
described  in  Alternative  4.     Decontamination  pads  would  be
constructed near the areas of excavation and used to minimize the
spread of contaminated soil as in Alternative 7. Immediately after
soil was excavated, clean soil would be brought in for backfilling.
Roadways,  parking lots,  and  other operational  areas would  be
repaved  after backfilling was complete.    The  limitations  to
excavation and disposal are the  same as described in Alternative 7.

Where excavation is  impractical, signs  would be posted to inform
workers of the contamination and of appropriate safety precautions.
Employee  informational and  safety  meetings  would  be held  and
institutional controls implemented as described in Alternative 2,
as  necessary.     Limitations  of  the   engineering,  safety,  and
institutional controls are the same as described in Alternative 2.

Costs and Remediation Time Frames

The total present worth cost for the alternative is $75.7 million.
Capital  costs  are  $6.7 million  and  include  capping  expenses.
Operation  and maintenance costs  are  $69  million and  include
excavation, transport, disposal  expenses, and  cap maintenance and
implementation of engineering and  institutional controls.

This alternative would take 54  months to implement.

Physical Effects on the Environment Caused by  Implementation

In this alternative,  soil hot spots are excavated and transported
off site for treatment and/or disposal.  The remaining contaminated
soil is  capped.   This  alternative presents  the  same short-term
risks to  the environment  as  Alternative  7.   The  frequency of
occurrence  of  these  risks  is  expected  to  be   less  than  in

                                49

-------
Alternative  7  due  to  the  large  reduction  in  the  volume  of
contaminated  soil  that  is  excavated  and  disposed  off  site.
Approximately 179,000  cubic  yards  of soil would be excavated and
disposed under this alternativei The risks to the environment are'
due  to contaminated runoff. ' These risks would be  mitigated as
discussed in Alternative 4.

Compliance With ARARs

The  off-site  treatment disposal of soil hot spots,  followed by
containment of  the  remaining  soil  above  cleanup  goals will be
designed   and  implemented  to   meet   all   ARARs.      Although
concentrations  above cleanup  goals for lead,  arsenic,  mercury,
PCBs,  and  TPH will remain in  the  unexcavated  soil,  capping with
long-term  monitoring  would  protect  human  health and  mitigate
further  degradation of  groundwater from  infiltration.  Organics
exceeding  cleanup  goals would  naturally attenuate  over  time.
Emissions generated during the  remedial actions would be controlled
to meet PSAPCA requirements.  Any construction activities performed
within 200 feet from the shoreline will be performed in conformance
with the Shoreline Management  Act.


Alternative 9B: Soil Organic Hot Spot Off-Site Treatment/Disposal
              and Containment

Major Components  of the Remedial Action

This alternative  is similar to  Alternative 9A except that only the
"hot spots" contaminated with organics as defined in Alternative 8B
would be excavated for  off-site disposal or treated. The remaining
portions of the site would be capped.  In areas where excavation or
containment is impractical, engineering,  safety, and institutional
controls would be implemented.

Treatment Component

Soil organic  hot  spots, as  defined in Alternative 8B,  would be
excavated  and  taken  off-site  for  disposal.    Excavated  soil
contaminated with organics  or mixtures of organics and inorganics,
which contain PCBs in excess  of 50  mg/kg  (2,000 cubic yards) would
be taken to an off-site incinerator for treatment and disposal, as
described in Alternative 7.  This is the only treatment component
of Alternative 9B.  This treatment component has the same removal
efficiencies as Alternative 7.

Containment Component

The  hot  spot  areas contaminated with lead  and  mercury  would be
capped along  with the areas which exceed the  cleanup  goals for
other  contaminants, as  described  in  Alternative 8B.    Damaged
existing surfaces would be  inspected quarterly and  repaired as

                               50

-------
needed.  The containment component of this alternative has the same
limitations as Alternative 3.

General Components

The general components  of this alternative are the same as those
described in Alternative 9A.  Excavated soil which contains TPH and
PCB levels  less  than 50 mg/kg and soil which contains inorganics
only (71,000 cubic yards) would be taken to an off-site hazardous
waste  landfill  for disposal.  Soil which  contains TPH exceeding
10,000 mg/kg, but for which all other constituents are below MTCA
or  other  regulatory  considerations,   would  be  disposed  in  a
regulated landfill. The limitations to  excavation and disposal are
the same as described in Alternative 7.  Engineering, safety, and
institutional controls have the same limitations  as Alternative 2.

Costs and Remediation Time Frames

The total present worth cost for the alternative  is $50.7 million.
Capital  costs are  $6.7  million  and  include capping  expenses.
Operation  and  maintenance  costs  are  $44  million   and  include
excavation,  transport  and  disposal   expenses  as  well  as  cap
maintenance  and  implementation   of   engineering,  safety,  and
institutional controls.

This alternative would  take 54 months  (4.5 years)  to  implement.

Physical Effects on the Environment Caused by Implementation

This alternative presents the  same risks to  the environment as
described in Alternative 9A.

Compliance With  ARARs

Compliance with  all ARARs is achieved as described in Alternative
9A.
Alternative  10A:  Soil  Hot Spot  Incineration/Solidification and
Containment

Major Components of the Remedial Alternative

This alternative consists of incineration and/or solidification of
organic and inorganic hot spots, as defined in Alternative 8A, with
containment  of  the  remainding portions  of  the site contaminated
above cleanup goals.   In  areas where  excavation is impractical,
engineering,   safety   and  institutional   controls   would  be
implemented.
                                51

-------
Treatment Component

Organic hot spots would be excavated and transported to an on-site
mobile incinerator  for treatment,  ar.  described in Alternative 4.
.ihe  treatment   component  of  this   alternative  has  the  same
operational requirements,—trial burn requirements, and limitations
as Alternative 4. After treatment, organic hot spot soil would be
tested for total inorganic concentrations and for leachability of
inorganics, as in alternative 8A, to determine if solidification or
capping is  necessary prior to replacing the  treated  soil  in the
ground.  Inorganic  hot  spots would  be  treated by  an  on-site
solidification process as described in Alternative "4.

Containment Component

The  remaining contaminated  areas  not covered by  an  impermeable
barrier of  asphalt or concrete  would be capped as described in
Alternative 8A.  Cracked or damaged asphalt  or concrete would be
repaired or sealed.  The containment component of this alternative
has the same  limitations as discussed in Alternative 3.

General Component

Excavation  procedures -,  contamination  control, dust control,  and
backfill would occur as  discussed  in  Alternative 4.   Areas where
capping is impractical would be posted with signs, employees would
be informed of potential hazards, and  institutional controls would
be implemented as described in Alternative^,  as appropriate.  This
alternative has  the  same limitations  to  engineering,  safety, and
institutional controls as discussed in Alternative 2.

Costs and Remediation Time Frame

The total present worth cost  for the alternative is $103 million.
Capital  costs  are  $14  million  and   include site  preparation,
mobilization, equipment purchase and capping expenses.  Operation
and  maintenance costs are  $89 million  and  include  excavation
expenses, incineration and solidification costs, cap maintenance,
and  implementation  of  engineering,   safety  and  institutional
controls.

This alternative would take  57 months (4.75 years) to implement.

Physical Effects on the Environment Caused by Implementation

This  alternative  presents  the  same short-term  risks  to  the
environment as discussed in Alternative  4.   Because the remedial
action is limited  to "hot spots," the volume of soil treated is
reduced  as  compared  to Alternative  4,   and  the  frequency  of
occurrence  of  adverse  effects would  be  reduced  accordingly.
Contaminated  runoff from  excavated   areas  and  stockpiles  would
present  a  potential  risk  to the environment.    Runoff  control

                                52

-------
measures  would be  implemented  as discussed in  Alternative  4 to
reduce or eliminate this hazard.

Compliance With ARARs

The alternative, which features the incineration/solidification of
soil  hot spots followed  by containment of  remaining soil above
cleanup goals, will be designed and implemented to meet all ARARs.
Although  concentrations above  cleanup goals  for  lead,  cadmium,
chromium,  PCBs,  and  TPH  will  remain  in  the unexcavated soil,
capping would protect human health and mitigate  further degradation
of groundwater from infiltration.  Organics  exceeding cleanup goals
would naturally attenuate over time.   Emissions generated during
the remedial actions (e.g., incineration, excavations, etc.) would
be controlled to meet Puget Sound Air  Pollution Control Authority
(PSAPCA)  requirements.  The  incinerator  will  be  operated  in
conformance with Dangerous Waste incinerator performance standards,
and will achieve the 99.9999 percent destruction removal efficiency
for PCBs  to meet TSCA incinerator requirements.  Any construction
activities performed within 200 feet  from the shoreline will be
performed in conformance with the Shoreline Management Act.


Alternative 1OB: Soil Organic Hot  Spot  Incineration/Solidification
    and  Containment

Major Components of the Remedial Alternative

This  alternative  consists of excavation and incineration and/or
solidification of  organic hot spots as defined in Aternative 8B,
followed  by containment of the remaining portions of the  site.  In
areas where excavation or containment  is impractical, engineering,
safety, and institutional  controls would be implemented.

Treatment Component

Soil organic hot spots  would be treated in  an on-site  incinerator.
After treatment, organic  hot  spot soil would be tested  for total
inorganic concentration and for leachability of inorganics, as in
alternative  8A,  to determine  if  solidification  or  capping is
necessary prior to  replacing the treated soil  in the ground.  The
treatment component of this  alternative  has  the  same  operating
requirements,  trial   burn  requirements,   and   limitations  as
Alternative 4.

Containment Component

The hot  spot areas contaminated  with lead and  mercury  would be
capped along  with  the  areas  which exceed the cleanup goals, as
described in Alternative SB.  Damaged  existing surfaces  overlying
contaminated soil would be repaired or replaced.  Capped surfaces
would  be  inspected  quarterly  and  repaired  as  needed.    The

                                53

-------
containment component of this alternative has the same limitations
as discussed  in Alternative  3.

General Components

Excavation  procedures,  contamination control, dust  control,  and
backfill would occur as discussed in Alternative 4.  In areas where
excavation or containment is impractical, engineering, safety, and
institutional  controls  would  be   implemented  as  described  in
Alternative 2.   The limitations to the controls are  the same as
described in Alternative 2.

Costs and Remediation Time Frame

The total present worth cost of the alternative  is  $67 million.
Capital  costs  are  estimated  to   be  $14  million  and  include
mobilization,  site preparation, incineration and  solidification
equipment.  Operation and maintenance costs are estimated to be $53
million and include excavation, treatment, cap maintenance,  and
implementation of engineering, safety, and institutional controls.

This alternative would  take  57 months (4.75 years)  to implement.

Physical Effects on the Environment Caused by Implementation

This alternative  presents the  same risks  to the  environment as
Alternative 10A.

Compliance With ARARs

Incineration and solidification of  soil hot  spots  defined by the
modified criteria,  followed  by containment of the remaining soil
above  cleanup goals,  would  achieve  all  ARARs  as described in
Alternative 8A.
Alternative 11A:  Soil Hot Spot Thermal Desorption/Solidification
               and Containment

Major Components  of the Remedial Alternative

This alternative consists of thermal desorption and solidification
of soil hot spots, as defined in Alternative 8A, with containment
of the remaining contamination  above cleanup goals.  Since thermal
desorption is not highly effective for removing PCBs from soil, hot
spots containing PCB contaminants  (3,200  cubic yards)  would be
excavated and treated in an off-site incinerator or disposed at a
hazardous waste landfill.  In areas where excavation or containment
is impractical, engineering, safety, and industrial  controls would
be implemented.
                                54

-------
Treatment Component

Thermal  desorption is  a process  by  which soil  is heated  to a
moderate  temperature  (usually  in the  range of  2OO-1,000°F)  to
vaporize organic contaminants.  The organics are not destroyed by
this  process,  but  are  physically  separated  from  the  soil.
Vaporized organics can then either be combusted in an afterburner
or removed in liquid form after condensation.  Thermal desorption
would be a suitable technology for Harbor Island hot spots, since
the technology requires lower capital  and operating costs compared
to  incineration,  organics  are removed  from solids  and  may  be
recycled, and low treatment temperatures minimize the potential to
volatilize heavy metals.  Based on literature performance data, it
is probable that thermal desorption would effectively remove TPH,
benzene,  ethyIbenzene,  and  xylene from soil  to cleanup  goals.
Thermal desorption  has not been proven as  effective  in removing
PCBs and high molecular weight PAHs from soil and therefore it is
uncertain if cleanup goals for these compounds could be achieved.
Thermal desorption treatability studies would be required to verify
removal efficiencies.

Soil TPH  hot spots  would be  transported  to an  on-site thermal
desorption unit for  treatment.  After  treatment,  organic hot spot
soil would  be tested  for total inorganic  concentration  and for
leachability of inorganics, as in alternative 8A, to determine if
solidification  or capping  is necessary prior  to  replacing the
treated soil  in the ground.   Limitations  for  the solidification
process are the same as described in Alternative 4.

Soil  contaminated with  PCBs  in  excess  of  50  mg/kg would  be
excavated and taken off-site either for incineration  or directly to
a hazardous  waste disposal  facility.   The requirements  for PCB
incineration  are  the  same  as described  in Alternative  7.  Soil
contaminated with PCBs less than 50 mg/kg or with heavy  PAHs would
be excavated  and taken  to  an off-site hazardous waste disposal
facility..  Imported, clean soil would be used as backfill.

Soil contaminated with inorganics only would be treated  in  the on-
site solidification process and returned to its original location
as backfill.

Containment Component

This alternative has the same containment component as Alternative
8A.   All areas  where  soil exceeds cleanup  goals would be  capped.'
Existing and impermeable barriers would be inspected  and patched or
sealed  if necessary.    All  capped surfaces  would be inspected
quarterly  and  repaired as  required.   The  limitations  to the
containment component are the same as Alternative 3.
                                55

-------
General Components

Excavation  procedures,  contamination  control,  and  dust  control
would occur as described in Alternative 4.  Areas where capping if
impractical would be posted with signs, employees would be informed
of  potential  hazards,   and  institutional   controls   would  be
implemented as described  in Alternative 2, as  appropriate.   The
limitations to institutional controls are the  same as described in
Alternative 2.

Costs and Remediation Time Frame

The total present worth cost for the  alternative is $57.1 million.
Capital costs are  $6.7  million and include thermal treatment and
solidification  equipment,  mobilization,   site  preparation,  and
capping.  Operation and maintenance costs are estimated to be $50.4
million and include excavation, treatment,  transport, and disposal
of  soil,   cap maintenance,  and  implementation of  engineering,
safety, and institutional controls.

Alternative 11A would take 57 months  (4.75 years)  to implement.

Physical Effects to the Environment Caused by Implementation

This alternative presents the same risks to the environment as the
other  excavation,  treatment,  and disposal alternatives  for hot
spots.  Contaminated runoff from excavated areas  and  stockpiles
presents  a potential  risk  to the  environment.    Run-on/runoff
control measures would be implemented as discussed in Alternative
4 to reduce or eliminate  this  hazard.  Transport of contaminated
soil off site presents a potential risk to  the environment.  Truck
decontamination areas would be established on site to minimize or
eliminate the spread of contamination off site.   Truck payloads
would be covered with tarps to prevent loss of material.

Compliance With ARARs

The  alternative,  which  features  the  thermal  desorption  and
solidification or off-site disposal of soil hot spots followed by
containment of remaining soil above cleanup goals, will be designed
and implemented to  meet all ARARs.  Although concentrations above
cleanup goals  for  lead,  arsenic, mercury,   PCBs,  and  TPH will
remain in the unexcavated  soil, capping would  protect human health
and mitigate further degradation of groundwater  from infiltration.
Organics exceeding  cleanup goals would  naturally  attenuate over
time.   Emissions  generated during the  remedial  actions would be
controlled  to  meet   PSAPCA  requirements.     Any  construction
activities performed  within 200  feet  from the  shoreline will be
performed in conformance with  the Shoreline Management Act.
                                56

-------
Alternative 11B:  Soil Organic Hot Spot Thermal Desozption and
                  Containment

Major Components of the Remedial Alternative

This alternative consists of thermal desorption and solidification
or off-site disposal  of  soil excavated from organic hot spots as
defined  in   Alternative   8B.     Treatment  components  of  this
alternative are the same as those of Alternative 11A, except that
soil contaminated only with inorganics would not be solidified, but
would be capped.  The remaining contaminated areas not currently
covered by an impermeable barrier of asphalt or concrete would be
capped with asphalt.  Institutional controls would be implemented.

Treatment Component

The organic hot spots would be treated the same as in Alternative
11A, although hot spot soil contaminated with inorganics only (lead
and mercury) would not be treated on site but would be capped. In
this alternative, 91,000  cubic yards of TPH contaminated soil would
be treated with  thermal  desorption. After treatment-, organic hot
spot soil would be tested for total inorganic concentration and for
leachability of inorganics, as in alternative 8A, to determine if
solidification or capping  is  necessary  prior to  replacing  the
treated soil in the ground.

Soil  contaminated  with   PCBs  greater  than  50  mg/kg would  be
excavated and taken off-site either for incineration  or diposed of
at a hazardous waste disposal facility.  The requirements for PCB
incineration  are the same as described  in Alternative  7.  Soil
contaminated  with mixed  organics with  a  risk greater thatn  10"*
would  be excavated and  taken  to  an  off-site  hazardous  waste
disposal facility.  Imported, clean soil would be  used as backfill.
The operational requirements, treatability study requirements, and
limitations of the treatment component of  this alternative are the
same as discussed in Alternative 11A.

Containment Component

This alternative has the same containment component as described in
Alternative 11A.   Contaminated soil not excavated, treated and/or
disposed would be capped.  The alternative has the same  limitations
to the containment component as discussed in Alternative 3.

General,Components

General  components  of  this alternative  are  the  same  as  those
described in Alternative 11A.  Excavation procedures, contamination
control,  and dust control would occur as discussed in  Alternative
4.  Backfill  would  occur as discussed  in Alternative  11B.   This
alternative has the  same limitations to the engineering, safety and


                                57

-------
institutional controls as Alternative 2.

Costs and Remediation Time Frame

The total present worth cost for this alternative is approximately
$38.,6 million.  Capital-costs—are-$6.7- mil~l~ion, and operation and
maintenance costs  are  $36.9  million.   The  costs include the same
items outlined in  Alternative 11A.

Alternative 11B would take 57 months (4.75 years) to implement.

Physical Effects on the Environment Caused by Implementation

The physical effects on the environment caused by implementation of
this alternative are the  same as  those discussed for Alternative
11A.

Compliance With ARARs

This alternative  complies with all ARARs  in the same  manner as
Alternative 11A,


Description of Groundwater Alternatives

Alternative 1:  No Action

Evaluation  of  a no  action alternative  is  required in  order to
provide a basis for comparison of  existing conditions and risks of
potential  conditions  resulting  from  implementation  of  other
remedial alternatives.

Major Components of the Remedial Alternative

Under the no action alternative, no additional remedial action will
be  taken to eliminate existing  sources  of contamination  or to
reduce the risks to humans.

Treatment Component

There is no  treatment component for this alternative.  Reduction in
toxicity or volume will occur only through natural processes such
as  biodegradation.     Toxicity,   mobility   and  volume  of  the
contaminated materials will  remain at  their present value for an
indefinite period  of time.

Containment Component

There is no containment component for this alternative.

General Component
                                58

-------
In this alternative, no action is required for its implementation.

Costs and Remediation Time Frame

Since no action is taken in this alternative, no costs or time are
required for implementation.

Physical Effects on Environment Caused by Implementation

Since  no action  is  taken in  this alternative,  the risk  from
implementation of this alternative is minimal.

Compliance with ARARs

The  no  action  alternative  will  not meet  any  ARARs.    This
alternative is  provided as a  baseline to assess the  effects of
leaving the site in its current state.


Alternative  2:    Removal  of  Floating  Petroleum  Product  and
Monitoring of Groundwater

Major Components of the Remedial Alternative

In this  alternative,  floating petroleum product located  at Todd
Shipyard facility will be removed and treated.  Groundwater in the
immediate  vicinity  of this  floating  product,  which has  been
contaminated  with  benzene and  other  soluable  constituents  of
petroluem, will  be pumped and treated.  Groundwater contaminant
concentrations at selected wells across Harbor Island will also be
monitored semi-annually for a period of 30 years.

Treatment Component

The  floating  petroleum product  and the  associated  contaminated
groundwater, will be treated on-site by oil/water separation, air
stripping, and carbon adsorption.

Containment Component

Containment will be  provided through the extraction of contaminated
water associated with the floating product.

General Components

In this alternative, floating petroleum product will  be removed by
groundwater  pumping.    The  water  will then  be  treated by  an
oil/water separator,  air stripping and carbon  adsorption before
discharge to the Metro POTW.

In all interior areas or the island where groundwater contaminants
concentrations exceed the cleanup goals identified in Table 7, and

                                59

-------
in all  shoreline wells downgradient of  these  areas,  groundwater
will  be sampled  and  analyzed  semi-annually  for  30 years.  The
shoreline  wells will be  considered  the point of  compliance for
achieving  the cleanup goals. Groundwater quality  trends  wil.~. be
reviewed every 5 years to determine af reasonable progress is being
made  towards achieving- the  cleanup  goals.  If adequate progress
towards  the cleanup  goals  is not being achieved, the need for
additional remedial actions will be evaluated.

Costs and.Remediation Time Frame

The  estimated  capital cost  for  removal of  floating  product,
monitoring and  institutional controls is $500,000.  The estimated
operations and  maintenance cost is $1,100,000.

It  is anticipated  that  removal  of the petroleum product  will
require  1  year for completion.   Monitoring will  continue for 30
years.

Physical Effects on Environment Caused by Implementation

The majority of effects on the environment caused by implementation
of this  alternative are associated with  the installation of the
groundwater  extraction  system.    Human  health   risks  could  be
incurred  by  contact  with contaminated  soil  during  excavation.
Releases of  toxic  vapors could occur through  excavation  of soil
containing volatile organic contaminants. Some  contaminants may be
emitted to the environment through the 'i«=e of the air stripper ana
other treatment units.  The system will be designed to meet PSAPCA
regulations.

Compliance with ARARs

 The  primary ARARs are the  Water Quality Standards  for  Surface
Water of the State  of Washington  (WAC 173-201A) ,  and the federal
surface water quality standards (40 CFR Part 131).  These surface
water quality standards were adopted for the protection of marine
organisms and protection of human health from consumption of marine
organisms.  With the  removal  of   the  floating product  at  Todd
Shipyard, and treatment of associated contaminated groundwater, the
surface water cleanup goals for organics in that area should be met
in a relatively short timeframe. Subsequent actions to be taken by
Ecology on floating product associated with the  tank farms operable
unit, should allow the goals for benzene in two other areas along
the shoreline  to be met over a longer  timeframe  through natural
biodegrdation.

This groundwater alternative,  if  coupled with  a soil alternative
which controls  sources of inorganic contamination  over the entire
island,  should also  meet the  surface  water  cleanup  goals for
inorganics.  This  conclusion  is   supported  by   the  results  of
groundwater  transport modeling, conducted during the Feasibility

                                60

-------
Study, which indicates that inorganics currently in the groundwater
will take more than 50 years to reach the shoreline.

This alternative should also meet  all  other groundwater/surface
water ARARs.  These include the Washington Water Pollution Control
Act  (RCW 90.48, WAC  173-201A)/Water Resources Act  (RCW 90.54),
State  Water Code  (RCW 90.03)  and  Water Rights  (RCW90.14),  the
substantive requirements of the NPDES Program as regulated by the
State Discharge Permit Program  (WAC  173-220), and the construction
and maintenance of wells  (WAC 173-160). Releases of contaminants to
the air  from  the groundwater treatment  system will  also meet air
quality  standards established  by the Puget Sound  Air Pollution
Control Authority  (PSAPCA) (Regulations I,III).


Alternative   3:      Precipitation/Filtration/Ion   Exchange/Air
Stripping/Nitrif ication/Denitrif ication with Storm Sewer Discharge

Major Components of the Remedial Alternative

In Alternative 3, contaminated groundwater will be extracted from
three target  areas along the shoreline  to prevent migration of a
contaminant (benzene)  to the surrounding waterways.  The water will
be treated to meet surface water quality standards  before discharge
to the storm  sewer. Floating petroleum product at Todd Shipyards
would  also  be  removed  and  treated.  Groundwater  contaminant
concentration across  the island would  also be monitored  for 30
years.

Treatment Component

Alternative 3 provides treatment of  groundwater at three locations
by precipitation and  filtration of  inorganics, air stripping of
organics, and nitrification/denitrification of ammonia. Floating
product at Todd  Shipyards would also be removed and treated.

Containment Component

The  goal of  the  groundwater  extraction  system  is  to  provide
containment of a contaminant  (benzene)  that  is  expected to migrate
to the  periphery  of  the  island  at concentrations  which exceed
cleanup goals within 50 years.

General Components

Alternative 3 includes the removal of groundwater from three target
areas,  which  are located  on Todd Shipyard,  Shell,  and Atlantic
Richfield properties.  These target areas were chosen to prevent
the migration of contaminants  to the periphery of  the island at
concentrations which exceed cleanup goals within  50 years.

The groundwater  will be extracted through wells,  then  pumped to  a

                                61

-------
centrally  located  treatment facility.   The treatment  train will
include  a gravity  separation unit to  remove floating  product.
After gravity separation, a precipitation/sedimentation unit will
be  used  to  remove the  bulk  of  the  soluble  and  particular
inorganics.  Microfiltration and ion exchange will be subsequently
used to  polish  the remaining particulate  and  soluble inorganics,
respectively.  Organics will then be removed by air stripping.  A
nitrification/denitrification process will then be used to remove
ammonia before subsequent discharge to the storm sewer.  Off-gases
will be treated by catalytic oxidation.

In all areas where groundwater contaminants concentrations exceed
these  cleanup  goals   and   in   associated downgradient  areas,
groundwater  will  be  sampled and  analyzed  semi-annually  for 30
years. Groundwater data trends  will be  reviewed  every 5  years to
determine  if progress towards  achieving  cleanup goals  is being
made. If adequate  progress  towards cleanup  goals  is not being
achieved,  the  need  for additional  remedial  actions  will  be
evaluated.

Costs and Remediation Time Frame

The  estimated capital  cost for  the  groundwater extraction  and
treatment facility and for installation of the monitoring network
is $5,000,000.  The estimated operation and maintenance  cost for
both the treatment facility  and  monitoring network is $15,000,000.
Engineering, administrative, and contingency costs are include with
operation  and  maintenance   costs.     The estimated  time  for
groundwater treatment is 10 years.  Monitoring  will continue for 30
years.  Monitoring may indicate  that additional time or effort for
remediation is required.

Physical Effects on the Environment Caused by  Implementation

Many of the effects on the environment caused by implementation of
this  alternative   are  associated  with  the installation  of  the
groundwater  extraction  system and the  associated piping.   Human
health risks could  be  incurred  by contact with contaminated soil
during excavation.   Release of toxic vapors  could  occur through
excavation of soil containing volatile organic contaminants.

Some contaminants may be  released to  the  environment through the
use of the air stripper and  other  treatment  equipment.  The effect
of  this  contamination will  be  minimized through  the  use of
catalytic oxidation.
                                62

-------
Compliance with ARARs

The  primary ARARs  are the  Water Quality Standards  for Surface
Waters of  the State of Washington  and  the federal surface vrater
quality  standards.   These  surface water  quality  standards were
adopted  for  the protection  of marine organisms and protection of
human health from consumption of marine  organisms.  The groundwater
treatment and  extraction  system will be designed and operated to
meet  the*  surface  water  cleanup goals  for  soluable  petroleum
constituents  (primarily benzene)  currently in the groundwater at
three areas along the  shoreline.  With the  removal  of the floating
product  at  Todd  Shipyard, and  subsequent  actions  to  be taken by
Ecology  on  floating product associated with  the tank farms,  the
long term sources of soluable constituents of petroleum should also
be eliminated.

This groundwater  alternative,  if coupled with a soil alternative
which controls sources of inorganic contamination  over the entire
island,  should also  meet  the surface  water cleanup  goals  for
inorganics.  This  conclusion  is  supported  by the  results  of
groundwater  transport  modeling, conducted during the Feasibility
Study, which indicates that  inorganics currently in the groundwater
will take more than 50 years to reach the  shoreline.

This alternative  should also  meet  all  other groundwater/surface
water ARARs.  These include  the Washington Water Pollution Control
Act  (RCW 90.48,  WAC  173-201A)/Water Resources  Act  (RCW 90.54),
State Water Code  (RCW 90.03)  and  Water  Rights (RCW90.14),  the
substantive requirements of  the NPDES Program as regulated by the
State Discharge Permit Program (WAC 173'-220) ,  and the construction
and maintenance of wells (WAC 173-160). Releases of contaminants to
the air  from the  groundwater treatment  system will also meet air
quality  standards established  by the Puget  Sound Air Pollution
Control Authority (PSAPCA)  (Regulations I,III).


Alternative 4: Precipitation/Filtration/Ion Exchange/UV Oxidation
with Discharge by Reinjection

Major Components of the Remedial  Alternative

In this  alternative,   contaminated  groundwater  will  be extracted
from the three target areas, as in alternative 3, but treated by a
different treatment technology  system. In  this  alternative, since
the  treated water  will  be  reinjected  into  the  ground  and not
released directly to the surface water; the performance goal  of the
treatment  system  may  be  slightly  less  stringent than  that of
alternative 3. The performance  goal of this treatment system will
be to reduce  contaminant  concentrations to levels which will not
exceed the  surface water  standards  at the  shoreline. Floating
petroleum product at  Todd  Shipyards would  also  be  removed and
treated.  Groundwater  contaminant concentration across the  island

                                63

-------
would also  be  monitored for  30 years.

Treatment Component

Alternative 4 provides treatment of groundwater at three locations
by precipitation, filtration, and ion exchange of inorganics, andJtJV
oxidation ~of  orgarficsV Floating  product at  Todd Shipyards would
also be removed  and  treated.

Containment Component

The  goal  of   the  groundwater  extraction  system  is to  provide
containment of the contaminants that are expected to migrate to the
periphery of the island at concentrations which exceed the cleanup
goals within 50  years.

General Components

Alternative 4 includes the removal of groundwater from three target
areas, which  are located on Todd Shipyard,  Shell,  and Atlantic
Richfield properties.   These target  areas  were chosen to prevent
the migration  of contaminants to the periphery  of  the  island at
concentrations which exceed  cleanup goals within 50 years.

The groundwater  will be extracted through  wells then pumped to a
centrally located  treatment facility.  The  treatment train will
include  a  gravity  separation unit  to  remove  floating product.
After gravity  separation,  a  precipitation/sedimentation unit will
be  used  to  remove  the  bulk  of  the  soluble  and  particulate
inorganics.  Microfiltration and ion  exchange will be subsequently
used to polish the  remaining particulate  and soluble inorganics,
respectively.  Organics will then be removed by UV oxidation before
subsequent  discharge by reinjection.   Off-gases will be treated by
catalytic oxidation.

In all areas where groundwater contaminants concentrations exceed
these  cleanup  goals  and  in   associated  downgradient  areas,
groundwater will be sampled and analyzed semi-annually  for 30
years. Groundwater data trends  will  be  reviewed every 5 years to
determine  if  cleanup  goals  are  being  achieved.  At each  5 year
review, the need for additional remedial actions will be evaluated.

Costs and Remediation  Time Frame

The estimated capital  cost for  the groundwater  extraction and
treatment facility and  for installation of the monitoring network
is $3,000,000.   The  estimated operation and maintenance cost for
both the treatment facility and  monitoring  network is $10,000,000.
Engineering, administrative, and contingency costs are include with
operation and maintenance costs. The estimated time for groundwater
treatment is  10 years.   Monitoring  will  continue  for  30 years.
Monitoring  may  indicate  that  additional  time  or  effort for

                                64

-------
remediation is required.

Physical Effects on the Environment Caused by Implementation

The majority of effects on the environment caused by implementation
of this  alternative are associated with  the  installation of the
groundwater extraction system and the  associated piping.   Human
health risks could be incurred by contact with contaminated soil
during excavation.   Release of toxic vapors  could  occur through
excavation of soil containing volatile organic contaminants.

Some contaminants  may be  released to the environment through the
use of the air stripper and other treatment equipment.  The effect
of  this  contamination will be  minimized  through the use  of
catalytic oxidation.

Compliance with ARARs

The  primary  ARARs  are the  Water Quality Standards for Surface
Waters of the State of Washington and federal surface water quality
standards.  These surface water quality  standards were adopted for
the protection of marine organisms and protection of human health
from consumption of marine organisms. The groundwater treatment and
extraction system will be designed and operated to meet the surface
water cleanup goals for soluable petroleum constituents (primarily
benzene) currently in the  groundwater  at three areas  along the
shoreline.  With the  removal  of  the  floating product  at  Todd
Shipyard, and subsequent actions to be t^en by Ecology on floating
product associated  with the tank farms,  the  long  term sources of
soluable constituents of petroleum should also be eliminated.

This groundwater alternative,  if  coupled with a soil alternative
which controls sources of inorganic contamination over the entire
island,  should also  meet  the  surface  water cleanup goals for
inorganics.  This  conclusion  is  supported   by  the  results  of
groundwater transport  modeling,  conducted during  the Feasibility
Study,  which indicates that  inorganics currently in the groundwater
will take more than 50 years to reach the shoreline.

This alternative  should also meet  all  other groundwater/surface
water ARARs.   These include the  Washington Water Pollution Control
Act  (RCW  90.48,  WAC  173-201A)/Water Resources Act  (RCW 90.54),
State Water  Code  (RCW 90.03)  and  Water Rights  (RCW90.14), the
substantive requirements of the NPDES Program as regulated by the
State Discharge Permit Program (WAC 173-220),  and the construction
and maintenance of  wells (WAC 173-160). Releases of contaminants to
the air from the groundwater treatment  system will  also meet air
quality standards  established  by the Puget  Sound  Air  Pollution
Control Authority  (PSAPCA)  (Regulations I,III).
                                65

-------
SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

The following section discusses the comparison of alternatives with
respect to the nine statutory CERCLA requirements.

Protectiveness of Human Health and the Environment
Alternatives 4,  5,  6,  and 7 rank highest of all alternatives, in
terms of protection, because they either treat or remove from the
site all contaminants above the cleanup goals. Alternatives 8A, 9A,
10A, and llA are next because they treat  or  remove the organic and
inorganic hot  spots while  leaving the remaining contaminants in
place beneath an asphalt cap. Alternatives SB,  9B, 10B, and 11B are
next because they treat  or  remove the organic hot spots and leave
the remaining  contamination beneath  a  cap.  Alternative  3 is next
because it prevents direct human contact  with contaminants but may
not  prevent   the   migration  of  organic  contaminants  to  the
surrounding surface water where marine organisms may be exposed.
Alternative  2  provides  only marginal protection  because  direct
exposure to contaminants is still possible.  Alternative 1 provides
no protection  to human health or the environment.

Groundwater

Alternative  3  and  4   rank  the highest   because  they  provide
protection to  the  environment  in the  shortest timeframe through
removal  of  one  area   of   floating  product  and  treatment  of
contaminated groundwater in three areas along the shoreline where
marine organisms may currently be exposed  to  elevated  levels of
organic  contaminants.       Alternative 2 ranks next because it
provides  protection to  the environment  in a  longer timeframe.
Alternative 2 will  achieve cleanup in a relatively short timeframe
in the most critical area of organic contamination, the floating
petroleum product  at Todd  Shipyard.  For the two  other areas of
contaminated  groundwater,  cleanup  goals  for  benzene  will  be
achieved over  a  longer timeframe through a  combination of source
control and natural biodegrdation. If coupled with an adequate soil
source control alternative, alternatives 2, 3,  and 4,  will also
protect marine organisms from exposure to elevated concentrations
of  inorganics.   Alternative  1  provides   no  protection to  the
environment.
Compliance  with  Federal  and  State Applicable  or  Relevant and
Appropriate Regulations (ARARs)
                                66

-------
Alternatives  4-11 comply with all  chemical-specific  and action-
specific ARARs because they address all contaminated soil above tht
cleanup goals through containment,  treatment, or both. Alternative
3  meets all  ARARs except  the state  and federal  surface  water
quality standards.  Alternatives 1 and 2  do not meet any chemical-
specific or action-specific ARARs because they do not include any
action to address soil contamination above the cleanup goals.

Groundwater

Alternatives  3  and 4 ranked highest  in  terms  of compliance with
chemical-specific and  action-specific ARARs  because they achieve
compliance  with  surface  water  quality standards  for  organic
contaminants  in the shortest timeframe.  Alternative 2 ranks next
because it achieves compliance with surface water quality standards
for organic contaminants over a longer timeframe. If coupled with
a soil source control  alternative,  alternatives  2,  3,  and 4 will
also   protect  marine   organisms   from  exposure  to  elevated
concentrations of inorganics. Alternative 1 ranks  lowest because it
does  not provide any action  to  achieve surface  water quality
standards at  the  shoreline.


Long-Term Effectiveness and Permanence

Soil

Alternatives  4,   5,  6,  and  7  ranked  highest  for  long-term
effectiveness and permanence because  they permanently destroy or
remove all contamination  in the  soil  exceeding cleanup goals and
require no long-term maintenance or controls.  Alternatives 8A, 9A,
10A, and 11A are next best in terms of  effectiveness and permanence
because  they permanently destroy  or  remove both organic  and
inorganic hot spots  but would require maintenance  of  the capped
areas. Alternatives  8B,  9B, 10B,  and 11B are next because they
permanently  treat only the organic hot spots and  would require
long-term maintenance of  the capped areas. Alternative 3 is next
because  it  is effective  over  the  long-term  only if  the cap is
properly maintained.   Alternatives 1 and 2 do  not  permanently
remove health and  environmental .risk and, therefore,  rank  lowest in
terms of long-term effectiveness and permanence.

Groundwater

If  coupled with  an  adequate  soil  source  control alternative,
alternatives  3 and 4 are equally ranked because  they provide the
equivalent long-term effectiveness and permanence in protecting the
environment  from  contaminants  in the  groundwater.  Alternative 2
ranks  next  because  it  depends more  heavily on  adequate source
control to achieve the cleanup  goals than do  alternatives 3 and 4.

                                67

-------
Alternative  1  ranks  lowest  because  it  provides  no  long-term
effectiveness.


Kaduction of Toxicity, Mobility, and Volume Through Treatment

Soil

Alternatives 4, 5, and 6 rank highest because they reduce toxicity
or mobility for all contaminated soil on the site. Alternatives 8A,
10A, and 11A rank next because they remove, destroy, or immobilize
organic  and  inorganic  hot  spot  contaminants which  amount  to
approximately   60%  of  the   total   organic   contaminants   and
approximately 70% of the total inorganic contaminants. Alternatives
8B, 10B, and 11B rank next because they remove or destroy organic
hot spot contaminants and reduce the mobility of the inorganics by
capping in  place.   Alternatives 3, 7,  9a, and 9B all  rank next
because they  primarily  provide reduction  in mobility  either by
capping contaminants in place or disposal in an off-site hazardous
waste  landfill.  Alternatives 1  and  2  rank  lowest because  they
provide no  reduction  in toxicity, mobility,  or volume  through
treatment.

Groundwater

Alternatives  3 and  4 provide  the best  reduction in  toxicity,
mobility,  and  volume of contaminants  in the  groundwater through
extraction  and treatment.   Alternative 2  ranks next because it
extracts and  treats  floating  product  and associated contaminated
groundwater in the most  critical area  which  could effect surface
water  quality.  Alternative  1 provides  no  reduction  in  toxicity,
mobility,  or volume of contaminants through treatment.


Short Term Effectiveness
Alternative 3 ranks highest in short-term effectiveness because it
addresses site  contaminants in the  shortest period of  time and
causes  minimal   additional   short   term   risk  to  workers  and
environment during  remediation activities.   Alternatives 8A, 8B,
9A, 9B, 10A, 10B, 11A and 11B all  rank next in terms of short-term
risk to workers,  the  community, and  the environment because they
require excavation and handling of comparatively moderate volumes
of contaminated soil.  Alternatives 4, 5, 6,  and 7  rank next because
they present a slightly higher  degree of short-term risk due to the
fact that they  require excavation and  handling  of a  much larger
volume  of   contaminated  soil  and allow human  exposure  to  this
excavated soil over a longer period of  time. Alternatives 1 and 2
rank the lowest  because  they do not  provide any protection to
human health or the environment in the  short term.

                                68

-------
Groundwater

Alternative 2 has good short-term effectiveness because it presents
minimal  exposure to  humans  during inplea.. r tatian and  prov'.des
protection to  the environment in ths short term.   Alternatives 3
and 4 rank next because, even though they provide good short-term
protection to the environment, they expose workers to contamination
during well installation or during treatment facility construction
and operation.  Alternative 1 ranks lowest because it provides no
protection to  the environment in the short term.


Implementability

Soil

Alternatives  1,   2,  and 3  are  easily implemented because  they
require little or no  excavation, have the shortest implementation
schedules, and provide the least interruption to island businesses.
Among  the   alternatives  which  require   soil  treatment,   the
alternatives  which  treat  the hot  spots minimize disruption of
island business because they require less excavation and have less
logistical  constraints  compared  to alternatives that treat all
contaminated  soil.  Therefore, alternatives  8B, 9B,  10B,  and 11B
rank  next  in terms  of  implementability  because  they  require
excavation   and   treatment  of  only   the   organic   hot  spots.
Alternatives 8A,  9A,  10A,  and 1IA rank next because they require
excavation and treatment of the organic and inorganic hot spots.
Alternatives 4, 6, and 7 rank next because they require excavation
and treatment  of  large  quantities of soil which will cause major
disruptions to businesses on the island. Alternative 5 ranks last
due   to  uncertainties  regarding  the   ability   of   in-situ
bioremediation to achieve cleanup goals in a reasonable timeframe,
and the requirement  for  a large open area needed for bioremediation
by land farming for the excavated soil.

Groundwater

Alternatives  3  and  4  may be  difficult  to  implement' due  to
difficulties   in  constructing  the  groundwater  extraction  and
treatment systems. Also, the extraction  system may pull in brackish
water which may decrease the effectiveness of the treatment system.
Alternative 2, because it only requires removal of  floating product
and a limited  amount  of contaminated groundwater, is more easily
implemented. Alternative 1 does not require  any action and is the
easiest to implement.


Cost

Costs for all alternatives are summarized in Table  11. Alternatives
1 and 2 have  the lowest costs of any soil alternatives. Alternative

                                69

-------
3 has the next lowest cost because  it only requires containment of
the contaminated soil.  The alternatives which require treatment of
hot  spots  have  the  next  lowest range  of costs.  Among  the
alternatives which require treatment of only the organic hot spcrts,
alternative  11B is  the lowest. For  alternatives  which require
treatment of both organic and inorganic  hot spots, alternative 11A
is the lowest. Alternatives 4, 5, 6, and 7, which require treatment
or disposal of all contaminated .soil,  have the highest costs.

For  groundwater,  treatment  alternatives 3  and  4  are  the  most
expensive. Alternatives 2 is relatively inexpensive and alternative
1 has no cost.
State Acceptance

The Department of Ecology concurs with EPA's preferred alternative,
which is identified below.
Community Acceptance

The  comments  received  during  the  public  comment  period  were
substantially in favor of the preferred alternative identified in
the Proposed Plan. A  complete  summary of comments received and
EPA's responses are provided in the Responsiveness Summary.
                                70

-------
             Table 11— Present Worth Costs for Harbor Island Remedial Alternatives
I.     Soil Alternatives

    1    No Action	None
    2    Institutional Controls	$150,000
    3    Asphalt Cap (All Areas Above Cleanup Goals)  	$15.000,000

    Alternatives Which Treat All Contaminants

    4    Incineration/Solidification	$244,700.000
    5    Bioremediation/Solidification	$117,400.000
    6    Solvent Extraction/Solidification	$184.600,000
    7    Off-Site Disposal	$220.000,000

    Alternatives Which Treat Hot Spots and Cap Remaining Areas

    8A  Solvent Extraction/Solidification	 $83.200.000
    8B  Solvent Extraction (Organics Only) 	$54,800.000
    9A  Off-Site Disposal	$75.400.000
    9B  Off-Site Disposal (Organics Only)	$50,400.000
    10A Incineration/Solidification  	$103,000,000
    10B Incineration (Organics Only)  	$67,100 000
    11A Thermal Desorption/Solidrfication  	'.	$57,100,000
    11B Thermal Desorption (Organics Only)	$38,600,000
II.  Groundwater Alternatives

    1    No Action	None
    2    Petroleum Product Removal/Monitoring	$1,600,000
    3    Air Stripping/Monitoring  	$19,900,000
    4    UV Oxidation/Monitoring	$13,300,000
                                              71

-------
 THE SELECTED REMEDY

 Major Components of the Selected Remedy

 EPA's selected  remedy  is  soil Alternative  11B  combined with
_groundwater Alternative _2. --This remedy -was- selected -over- other
 alternatives  because  it  best  satisfies  the  nine evaluation
 criteria.  In particular,  it: is protective of human health and the
 environment, meets all ARARs,  has  good  long-term and short-term
 effectiveness,  reduces  the toxicity and  volume  of  the  primary
 threat (TPH, PCBs, and mixed organics with risk exceeding  10"*) and
 reduces  the mobility of the  low  level threat  (inorganics and
 organics  below   the  treatment  level),   is  technically  and
 administratively feasible to implement, has the lowest cost of all
 other reasonable protective alternatives, and is acceptable to the
 state and  the public.

 The selected remedy includes  the following specific  components:

      Excavation and  treatment of the soil containing the highest
      levels of organic contamination ("hot  spots"). These organic
      soil  hot  spots are defined as Total Petroleum  Hydrocarbons
       (TPH)  greater than  10,000 mg/kg, PCBs  greater than 50 mg/kg,
      and  soil  with mixed carcinogens with  a total  risk greater
      than  10"*.   TPH hot  spot soil  will be treated on site in a
      thermal desbrption  unit.   PCBs hot spot  soil will either be
      sent off site for treatment (incineration)  or be disposed in
      a  hazardous  waste disposal facility.  Organic hot spot soil
      with  risk  greater  than 10"* will be disposed in a hazardous
      waste  disposal  facility.

      Capping exposed contaminated  soil exceeding  inorganic or
      organic cleanup goals.    The  cap  would consist of a low
      permeability material such as asphalt to prevent  infiltration
      of  rainwater  and  reduce  contaminant  migration  into the
      environment. Existing asphalt and concrete surfaces  would be
      repaired to  also prevent infiltration of rainwater.

      Invoking institutional controls which would require long term
      maintenance  of  new and existing caps, warn  future  property
      owners of remaining contamination contained  under  capped
      areas  on  their  properties,   and   specify  procedures  for
      handling  and disposal of  excavated  contaminated soil from
      beneath the capped areas if future  excavation is necessary.

      Removal of  and treatment of floating petroleum product and
      associated  contaminated  groundwater  at Todd  Shipyards to
      prevent   its   migration  into  the   marine   environment.
      Implementing groundwater monitoring for 30 years, with review
      of groundwater quality  trends every  5  years to assess the
      effectiveness of the selected remedy.


                                72

-------
Soil organic hot  spots containing concentrations of TPH exceeding
the  treatment  level of  10,000  mg/kg (approximately 91,000 cubic
yards)  would  be excavated  and  treated in  an on-site  thermal
aesorption  unit.  The performance goal for the thermal desorption
unit  will  be  to achieve  soil  cleanup  goals for  TPH,  benzene,
ethybenzene, toluene, and xylene (Table 7).  TPH recovered from the
thermal desorption  treatment will be tested to determine if it is
recyclable. If it is contaminated with other waste which prohibit
recycling,  it will be disposed off-site as required by regulations
covering waste oil.

The  treatment  facility  will  consist  of a soil stockpile area,
thermal desorber unit, and a mobile  laboratory. This facility will
be provided with  contamination  control measures such as exclusion
zones, decontamination equipment and facilities, and run-on/runoff
controls. Treated organic hot spot  soil would be tested for total
organic  and inorganic  concentrations and  inorganic  contaminant
leachability, according  to the  TCLP method, before being returned
to the soil. Soil which fails  the TCLP test, would be considered a
RCRA characteristic waste.  This soil would have to be solidified so
that it no longer fails the TCLP test before being returned to the
ground.   If soil passes the  TCLP  test  but contains  organics or
inorganics  above  the cleanup  goals  (Table  7), this soil would be
placed in the ground and capped. TPH is not  a  RCRA hazardous waste
or a state  dangerous waste and the  treatment  and disposal of TPH
contaminated soil will not have to  comply with these regulations.

Organic hot spots containing concentrations of PCBs exceeding the
treatment level of 50 mg/kg (2,000 cubic yards) would be excavated
and  either treated by  off-site incineration or  disposed  at  a
hazardous waste disposal  facility. Soil contaminated only with PCBs
is not a RCRA hazardous waste  nor a  state dangerous waste but is a
TSCA waste. The remedial action for this soil meets both the TSCA
and  state  dangerous  waste   requirements.  Organic  hot  spots
contaminated above  the treatment level of  risk  greater than 10"*
(1,200 cubic yards)  would be taken  to an off-site hazardous waste
disposal facility.

The preferred alternative includes capping  of  lead and mercury hot
spots and  all  remaining contaminated  soil  exceeding  the cleanup
goals (Table 7).  Figure  6 shows areas of the  island which will be
capped. The :cap will be composed of asphalt  or concrete  with a
minimum thickness of  3  inches  and with a .minimum permeability
(hydraulic conductivity) of 10"5 cm/sec.  Capping will be effective
in containing the lead and mercury  in the hot spots because soil
adsorption tests conducted during the remedial  investigation showed
that inorganic  contaminants have a high affinity  for  the soil.
Capping,  with  proper  long-term  maintenance,  will decrease the
migration of inorganic contaminants  from the hot  spots by reducing
the infiltration of  rain water  and  the potential for migration of


                                73

-------
               Figure 6
Contaminated Areas to be Capped
     Combined Organic
     and Inorganic
     Contaminated
     Areas to be Capped

-------
these  contaminants  into  the  groundwater.  The  results  of  the
Remedial Investigation show that lead in soil fails the TCLP test
at six locations and could be a RCRA characteristic waste. However,
this soil will  be  managed  within the area of contamination (AOC)
and will receive a cap which complies with the RCRA hybrid closure
requirements.

The  floating petroleum  product  located at  the Todd  Shipyards
facility  would  be  recovered and  recycled  if  possible.  If  not
recyclable,   it  will  be  disposed  off-site   as   required  by
regualations  covering the  disposal  of waste oil. Removal  of this
petroleum is critical because it is currently at  the shoreline, and
is a direct source of contamination to the surface water of Elliott
Bay. The  contaminated groundwater associated with  this floating
product will  be pumped and treated to surface water cleanup goals
before being  discharged to the storm drain system.

Surface water cleanup goals will be met  in an acceptable period of
time by taking source control actions which  include: treatment and
off-site disposal of  the organic hot spot soil which could act as
an ongoing  source of contamination to  surface  water,  removal of
floating  petroleum product  at Todd  Shipyards,  and capping  the
remaining  contaminated  areas  above the  cleanup  goals.  These
conclusions are supported by the results of groundwater transport
modeling conducted in the feasibility study which indicate that the
inorganics  currently in the groundwater will take more  than 50
years  to  reach  the  shoreline  under current  conditions.  It is
anticipated that subsequent action which may be taken by Ecology to
remediate  floating product at  the  tank farm operable  unit will
further ensure compliance with surface water cleanup goals.

In all areas  where groundwater contaminant concentrations exceed
the surface water cleanup goals  (which apply at the shoreline),
groundwater will be sampled semi-annually for 30  years. Groundwater
quality data trends would be reviewed every 5 years to determine if
additional remedial actions are required to  meet the surface water
cleanup goals.


Basis for Remediation Goals

Soil

For  Harbor Island,   the  primary  soil  ARARs  are  the  standards
contained  in  the  State  of Washington  Model Toxics  Control Act
(MTCA)  and  its  implementing regulations.  Compared  to subsurface
soil, surface soil presents a greater risk to human health because
of the potential for more frequent exposure  through direct contact
or ingestion. Therefore,  cleanup goals  for the surface are more
stringent and were based on a risk calculation specified by MTCA.

The cleanup goals for soil are shown in  Table 7.  The objective for

                                75

-------
surface cleanup goals for carcinogens is to achieve a total cancer
risk  from all  carcinogens of  less  than one  in 100,000  (10*s) .
Principle carcinogens of concern include PAHs,  PCBs,  and arsenic.
Cleanup goals for noncarcinogens in the surface  are also based upon
the combined  risk from all  contaminants  at each location.   The
cleanup  goal  for  noncarcinogens  was  to  achieve  contaminant
concentrations with a hazard index of less than  1.0 (one). A hazard
index of  less than  1.0  means contaminant  concentrations will not
pose an adverse health effect. The cleanup goal for lead, which is
considered  to  be a  probable  carcinogen,  is the MTCA  numerical
standard  for   an  industrial  exposure  because  a  risk-based
calculation  method  for  lead has  not yet  been scientifically
determined.

For  subsurface  soil,  since  human   contact  will be limited  to
infrequent  excavations   of   limited  duration,   MTCA  numerical
standards for an industrial  exposure were selected.   The goal of
these numerical  standards is  to achieve  a  risk  from individual
carcinogens of  less  than 1 in  100,000 (10~5).  The MTCA numerical
standards selected for some of the contaminants in the subsurface
are also designed to protect groundwater quality.


Groundwater

EPA and Ecology have determined that the federal and state drinking
water standards do not apply to groundwater at Harbor Island. These
drinking water standards are not releva"4-  and appropriate to Harloor
Island  because:  1)   there is  no  current  or foreseeable  use  of
groundwater for  drinking  water purposes,  2)  the  entire island is
serviced by the  city  of Seattle water system,  and 3) the surface
water quality  standards  (Table 7)  for the  protection  of marine
organisms,  and   protection  of human  health  from consumption  of
marine organisms, will apply at the shoreline.

Groundwater  contaminant  transport  modeling  conducted  in  the
feasibility  study demonstrated that  substantially  all of  the
contaminants would take more than 50  years to reach the shoreline.
Only three areas along the shoreline  were  found to contain organic
contaminants  (above  the  surface  water  standards)  which  are
currently at the shoreline or will be there  in the next 50 years.


Protection of the Environment During Remedial Action

Engineering controls will be implemented to mitigate  the impact on
the environment.  During excavation,  run-on/runoff controls will be
installed to keep soil from being transported into the island storm
sewer system and ultimately to  Elliott Bay.  Contaminated soil  in
excavation areas will be covered in  inclement weather to minimize
contaminated runoff.   The treatment area will also be  provided with


                                76

-------
run-on/runoff  controls to minimize contaminant  transport.   Soil
stockpiles  in  the  treatment  facility  area will be covered with a
rain shelter to prevent contaminated runoff.

Decontamination  pads  will  be installed  to clean  equipment and
minimize the spread  of contamination  to other areas of the site.
Transport trucks will  be covered as needed to prevent loss during
transport.

Contaminated liquid  storage  tanks  and storage facilities will be
provided with double containment to prevent leaks from entering the
environment.  Routine  inspections of facilities will be performed
to assure safety measures  are in place and functioning properly.
Discharges  to the environment  will  meet  applicable  state and
federal regulations for protectiveness.


Cost and Remediation Time Frame

The preferred soil alternative is estimated to  cost $38.6 million.
Capital costs are $6.7  million and include site  preparation, health
and safety  equipment,  and cap  placement.  Operations  costs are
$31.9  million and include  thermal  desorption  operating costs,
disposal   costs,   soil   stabilization   costs,   and   long-term
maintenance.  Soil remediation is anticipated to  take 57 months to
complete.

The preferred  groundwater  alternative is  estimated  to  cost $1.6
million.  Capital  costs of  $500,000  include  extraction well and
pump costs,  an equalization tank, oil water separator, signage, and
monitoring well costs.  Operational costs of $1.1 million include
operations  and maintenance  costs,  monitoring well  sampling and
analysis costs, and site inspections.  Floating product removal is
anticipated to require 1 year.  Site  monitoring and inspections
will occur for 30  years.

Estimated costs for the soil  and  groundwater alternative are shown
in Tables 12 and 13, respectively.
                                77

-------
Table 12—Soil Remediation Alternative Costs
Description
Rcfncdidl Action fVv^c
A. General
1. Site Mobilization & Preparation
Mobilization
Temporary Construction & Security Fencing
Site Survey/Layout
Stockpile Area Preparation
2. Site Health & Safety
Decontamination Pad (30' x 60*)
Decon Operations*
DocontamuMdion Rinsate Disposal
Health & Safety Expendables (30 Personnel @
See/day/person)*
3. Field Sampling & Analyses*
On-Site Laboratory
Reid Sampling & Analysis*
Off-Site Analyses*
4. Impose Deed Restrictions
5. Install Signage
B. Soil
1. Install Asphalt Cap
Shape & Compact Designated Areas*
Place Base Course*
Place Wearing Course*
2. Removal of Existing Pavement
Asphalt/Concrete Cutting & Removal*
Decontamination Facility
Material Decontamination*
Concrete Debris Disposal (25%)*
Asphalt Recycling and Repaying*
3. Earthwork
Soil Excavation*
Excavation System (per 30' x 30' Cell)*
Hauling*
Stockpiling*
Backfill & Compact (Treated Soil)*
Backfill & Compact (Imported Soil)*
4. Thermal Desorption
Mobilization/Demobilization
Material Pretreatment Disposal*
System Operation & Maintenance*
UrH


LS
LF
Week
Each

Pad
Day
Gallon
Day

LS
Day
Sample
Property
Sign


SY
SY
SY

SY
LS
SY
SY
SY

CY
Cell
CY
CY
CY
CY

LS
CY
CY
Quantity


. 1 .
2.700
4
5

1
974
243.500
974

1
778
97
SO
30


400,000
400.000
400.000

62,900
1
62.900
15.700
62,900

95,100
286
95.100
95,100
91,000
4,100

1
455
91.000
Unit Cost


100X100.00
11.65
2.675.00
4.290.00

4.370.00
100X0
0.77
1,980.00

200,000.00
1.920.00
125XO
1.000.00
85.00


0.68
3.63
6.15

6.40
4.370.00
1.90
6.70
10.19

1.90
2.400.00
2.91
2.91
1.49
12

500.000.00
150.00
100.00
Cost


100.000
31.455
10.700
21.450

4,370
81,962
157.776
1,622339

200,000
1.2S6£91
10,203
50.000
2JSSO


228,887
1,221,850
2,070.076

338.752
4.370
100.567
88,517
539,357

152.050
577,602
232,876
232,876
119,239
41,662

500,000
57,432
7,657,600
                   78

-------
                      Table 17. —Soil Remediation Alternative Costs (Continued)
Description
Unit
Quantity
Unit Cost
                                     Cost
   5.    Stabilization/Solidification
        Mobilization/Demobilization
        System Operation & Maintenance*
   6.    Off-Site Treatment
        Hauling
        Incineration
   7.    Off-Site Disposal (Hazardous Waste Landfill)
        Hauling
        Disposal
SUBTOTAL
   Engineering Expenses (15%)
   Contingency Allowances (25%)
TOTAL REMEDIATION COSTS (SOIL)
POST REMEDIATION MONITORING COSTS
   1.    Site Inspections***
   2.    Cap Maintenance***
SUBTOTAL
   Administrative Costs (15%)
   Contingency Allowances (25%)
TOTAL POST REMEDIATION COSTS (SOIL)
TOTAL PRESENT WORTH VALUE (SOIL)
 LS
 CY

 CY
 CY

 CY
 CY
        1     100.000.00
    1,200        100.00
    2,000
    2.000

    2.100
    2,100
    150.00
  2.550.00

     50.00
    150.00
   100.000
   100,979

   300.000
 5.100.000

   105.500
   315,000
23,649.003
Year
Year
       30      6.000.00
       30    413,000.00
              5.912,476
             33.109364

                56,561
              3.893,318
              3,949,877
               592,482
               987.469
              5,529,828
             38.639,692
   * Computed using present worth value (P/A, 10%, 2.67 years).
   ** Computed using present worth value (P/A, 10%, 10 years).
   *** Computed using present worth value (P/A, 10%, 30 years).
                                                    79

-------
                         Table 13—Ground water Remediation Cost
Item
Floating Product Removal System
A. Equipment
4-inch Extraction Wells
Downhote Fluid Pumps
Oil/Water Separator
Equalization Tank
Oil Storage Tank
Air Stripper
Fencing
Installation
Carbon Adsorption
SUBTOTAL
Engineering (15%)
Contingency (40%)
B. Operations/Maintenance
Operations/Maintenance
Metro Discharge
TOTAL A AND B ABOVE
INSTITUTIONAL CONTROLS
C. General
1. Site Health & Safety
Decon Operations
Decontamination Rinsate Disposal
Health & Safety Expendables (4 Personnel @
See/day/person)
2. Impose Deed Restrictions
3. Install Signage
SUBTOTAL
Engineering (15%)
Contingency (25%)
TOTAL C ABOVE
D. Post Remediation Monitoring Costs
1. Groundwater Monitoring
Install Monitoring Wells
Sampling*
Laboratory Analyses*
2. Site Inspections*
SUBTOTAL
Administrative Costs (15%)
Contingency Allowances (25%)
TOTAL D ABOVE
TOTAL FOR ALTERNATIVE (ITEMS A. B, C. AND D)
Unit


ea
ea
ea
ea
ea
ea
Is
Is
ea




year
Kgal




Day
Gallon
Day

Property
Sign






Well
Year
Year
Year





Quantity


6
6
1
1
1
1
1
1
1




1
31,536




60
300
60

50
30






23
30
30
30





Unit Cost



6.000
4.000
4.500
3.750
5.000
7.750
1,000
15,000
20,000




40.000
2.56




100
0.77
264

1,000
85






2,000
43.200
32,245
6.000





Cost<$)


36.000
24,000
4.500
3,750
5,000
7,750
1,000
15.000
20,000
117,000
17.550
53320

40,000
80,732
309.102



6.000
231
15.840

50,000
2,550
74,621
11,193
18.655
• 104.469


46,000
407,243
303,971
56.561
813,775
122,066
203,444
1,137,285
1,552,856
* Computed using preseni worth value (P/A. 10%. 30 years)
                                             80

-------
STATUTORY DETERMINATIONS

   The selected  remedy will  comply with  CERCLA  section  121  as
follows:

Overall Protection of Human Health and the Environment

Long  term protection of human health is obtained by removal and
treatment of soil hot spots containing TPH  and PCBs and by capping
of all the remaining soil above cleanup goals.  These actions give
a  reduction  in  contaminant  toxicity,   mobility,   and  volume.
Following implementation  of the remedy the overall  risk to human
health from contaminated soil will be less than 1 x 10~S.  Long term
protection of the surface  water quality will ultimately be achieved
through the treatment of organic hot spots  in the soil, capping of
the remaining contaminated areas, removal of the floating petroleum
product at Todd Shipyards, and natural attenuation.

Protection  of human health during  remediation will be obtained
through compliance  with OSHA requirements, the use  of personnel
protective  equipment,  and other safety measures  and engineering
controls.   Protection  of  the  environment  will be  obtained during
remediation  by  covering  stockpiles and .using berms and ditches
around excavations  to  control  contaminated runoff.   In addition,
the  environment  will  be  protected from  air pollution  through
compliance with the substantive requirement of the Puget Sound Air
Pollution Control Authority.

Long  term  monitoring  and maintenance will  be required  for the
selected  remedy.    An  asphalt  cap has  moderate permanence and
requires periodic maintenance. Island-wide groundwater monitoring
will  be  conducted semi-annually for  30 years  after remediation.
Periodic 5  year  reviews  of the island-wide  groundwater quality
trends will be conducted to determine  if additional source control
or groundwater treatment  actions are  required to  achieve surface
water cleanup goals at the  shoreline.  Removal and  treatment of
floating petroleum product and associated contaminated groundwater
at Todd Shipyards will continue until surface water cleanup goals
have been achieved.  If groundwater treatment at Todd Shipyards is
still ongoing at the time  of the first five year review, the need
for additional soil  remediation will be evaluated in consultation
with Ecology.


Compliance With ARARs

The  selected alternative will  meet all  chemical-specific and
action-specific applicable ARARs as described below. No location-
specific ARARs have  been  identified for this alternative.  •
                                81

-------
ARARs  (Applicable)

Clean Air Act  (42 U.S.C. §§ 7401 et seq.); Washington State Clean
Air Act  (RCW 70.94; WAC 173-400, -460)

Remedial actions which-would-result-in major sources of emissions-,
such as soil treatment by thermal desorption,  will be designed to
meet federal and state ambient air quality standards.

Puget Sound Air Pollution Control Authority (Regulations I, III)

Remedial actions which could  involve  releases of contaminants to
air will be performed in compliance with substantive requirements
of a permit from PSAPCA.

Washington  Water Pollution Control Act  (RCW  90.48);  Washington
State Water Quality Standards for Surface Waters (WAC 173-201A)

The State surface water quality  standards  for protection of marine
organisms  will be  achieved  over time  through the  treatment of
organic  hot spots  in soil,  capping  the  remaining  contaminated
areas, removal of the floating petroleum product at Todd Shipyards,
and natural biodegredation of remaining low level organics in the
groundwater.

State Water Pollution Control Act (RCW 90.48;  WAC 173-201A)/Water •
Resources Act  (RCW 90.54)                        .-

The  determination   of  the  known,  available  and  reasonable
technologies   (AKART)   for  achieving  surface   cleanup  goals  was
performed  during  the  feasibility  study.  State  water  quality
standards  will  be  achieved  using  the  technology  selected  for
treatment of floating petroleum product and associated contaminated
groundwater.

State Water Code (RCW 90.03) and Water Rights  (RCW 90.14)

These specifications for the extraction  of groundwater will be met
during  remedial  activities.   Groundwater remediation   (floating
product removal and long-term monitoring) will be consistent with
beneficial uses of the resources and will not be wasteful.

Model Toxics Control Act (RCW 70.105D; WAC 173-340)

MTCA soil cleanup standards .for protection of human health in an
industrial  setting   and   for  protection of  groundwater   from
contaminants leaching  from soil will  be  met  through removal and
treatment  of  organic  hot  spots,  and  capping  the  remaining
contaminated areas.
                                82

-------
Toxic Substance Control Act (15 D.S.C. §§ 2601-2671; 40 C.F.R. Part
761.60)

This regulation requires that PCBs at concentrations exceeding 50
rag/kg be destroyed  by incineration  or be disposed in a hazardous
waste disposal facility.

Washington State Dangerous Waste Regulations (WAG 173-303)

This regulation may be applicable for soils contaminated with PCBs
in the concentration  range of 1-50 mg/kg and for inorganics which
fail the TCLP test  and are a RCRA characteristic waste.

State Minimum  Standards for the construction and Maintenance of
Wells (WAC 173-160)

Standards for construction, testing, and abandonment of water and
resource protection wells  will  be met during the remediation and
monitoring.

Solid Waste Disposal  Act, also known as the Resource Conservation
and Recovery  Act,  Subchapter  III,   (42  D.S.C.  §§ 6921-6939;  40
C.F.R. Parts 261, 264, and 268)

There  are  no  RCRA listed  wastes  at  this  site.  The only RCRA
characteristic waste  is soil contaminated with high concentrations
of lead which  failed  the TCLP  leachate test conducted during the
Remedial Investigation  at  six  locations.  In the selected remedy,
this soil will be capped rather than excavated or treated because
it poses a direct contact threat, but does not pose a groundwater
threat. The three components of the  cap are:  1) it prevents direct
contact  with   residual  contamination,  2)   limited  long-term
maintenance  of the  cap  and minimal  groundwater monitoring  is
required, and 3) institutional controls restricting land use will
be used as necessary.

The RCRA Land  Disposal  Restrictions (LDRs)  may be applicable for
soil which is  excavated and disposed off-site or treated on-site
with  thermal  desorption,  if it  fails  TCLP for  lead.  Remedial
Investigation data  indicates that none of the soil to be excavated
or treated has high  enough  lead concentration to fail  the TCLP
test.  To verify that excavated soil  is not a RCRA waste, it will be
tested by  the TCLP method prior to off-site disposal  or after
treatment by thermal  desorption.  If any such soil fails TCLP, it
will be solidified  such that it passes TCLP and is in compliance
with levels specified by the LDRs.

RCRA  requirements  for  managing  RCRA  waste  piles,   storage  or
treatment  in  tanks,  and  monitoring,  may  be  applicable  if any
excavated soil fails  TCLP tests.
                                83

-------
ARARs (Relevant or Appropriate)

Clean Water Act (33 D.S.C. §§ 1251 et seq.; 40 C.F.R. Part 131)

The  Federal surface  water  standards  for  protection of  marine
organisms and human health from- ingest ion  of marine organisms will
be achieved over time through removal of hot spots from both soil
and groundwater, capping, and natural biodegredation of remaining
low level organics in the groundwater.


Cost Effectiveness

The selected remedy is cost effective because costs are allocated
to remove and treat areas  of the site  that have the highest site
contaminant concentrations and which pose  the greatest risk to the
environment and human health.  The contaminants in these areas also
have  the greatest potential for migration  in  the environment.
Areas of Harbor Island  containing  lower levels  of contaminants
would be capped, which is protective but less costly than treatment
technologies, and appropriate given  the lower site  threats.   The
selected remedy would treat approximately 55 percent of the total
contaminant mass, but  treat only 10 percent  of the contaminated
soil  volume,  providing a  balance between cost  and reduction in
toxicity and volume.


Utilization   of  Permanent   Solutions  and   Resource   Recovery
Technologies to the Maximum Extent Practical

The  selected  remedy  represents the  maximum  extent  to  which
permanent solutions and treatment technologies can be utilized in
a cost effective manner for remediation of soil and groundwater on
Harbor Island.  The selected remedy provides  the best balance in
terms of long-term  effectiveness and  permanence,   reduction of
toxicity, mobility and volume achieved through treatment,  short-
term  effectiveness,   implementability  and   cost,   while  also
considering the statutory preference for treatment as a principle
element and considering state and community acceptance.

Treatment of the organic  soil hot spots and removal of the floating
product  provides  long-term  effectiveness  and  permanence  and
provides a significant reduction of toxicity,  mobility and volume
while  minimizing   short-term   risks.     Containment   of  less
contaminated  areas  of  the  site  also reduces the  mobility and
provides long-term effectiveness, while minimizing  implementation
difficulties  and costs  associated  with  removal  of large and
inaccessible quantities of soil.

Alternatives  which  treat  all  contaminated soil  and groundwater
provide  greater  reduction  in  toxicity,  mobility and volume and
better long-term effectiveness,  but cause significant short-term

                                84

-------
risks to workers,  are  very difficult  to implement due to ongoing
facility  operations,  and  have high  costs.   Alternatives  which
consist of  little or  no treatment are more easily  and quickly
implement able and have  lower costs, but provide little reduction in
toxicity or volume.

This alternative meets requirements of the two mandatory threshold
criteria—protection  of  human  health  and  the  environment  and
compliance with ARARs.  The selected remedy uses a combination of
treatment,  containment,  and  institutional  controls  to  achieve
optimum compliance with  the five  balancing  criteria:   long-term
effectiveness,    short-term   effectiveness,    implementability,
reduction in toxicity,  mobility and volume, and cost.  Reduction in
toxicity and volume and cost effectiveness were the two balancing
criteria  which  had  the  most  influence  on  selection  of  the
recommended remedy.


Preference for Treatment as a Principal Element

The selected  remedy  treats a significant fraction  of the site's
soil contamination through the use of  thermal desorption.  Removal
of  product floating  on the  groundwater  is accomplished  using
physical  extraction  and separation technologies.  The selected
remedy meets  the  statutory preference for using treatment  as a
principal element by using  these technologies  in significant roles
in cleanup of the  site.


DOCUMENTATION OF SIGNIFICANT CHANGES

The remedy  selected  in this Record of Decision  is the preferred
alternative identified in  the Proposed  Plan. The only significant
differences between  the preferred alternative and the selected
remedy are:

1) The preferred alternative did  not specify the excavation and
off-site disposal  of hot  spot  soil containing  mixed carcinogens
with a cumlative risk exceeding 10"*.  However, the treatment level
for this soil was  identified in the Proposed Plan. The  excavation
and disposal of this organic hot spot soil is identified as a key
element of the selected remedy  in  this  Record of  Decision.

2) The soil cleanup goals  for petroleum products  has  been revised
to be consistent with Ecology's cleanup  goals  for the  petroleum
tank  farms  at Harbor  Island.  These  goals  are:  TPH  (gas)  = 400
mg/kg, TPH  (diesel) =  600  mg/kg, Benzene = 1 mg/kg, Toluene = 100
rag/kg, Ethybenzene = 200 mg/kg, and Xylene =  150  mg/kg.

3)  The  preferred  alternative  specified  incineration  of  soil
contaminated with  PCBs at  concentrations exceeding  50 mg/kg. TSCA
                                85

-------
allows  either  incineration or  disposal  in a  hazardous  waste
disposal facility. In the selected remedy, EPA will therefore allow
this  type of  soil to  either be  incinerated  or  disposed in  a
hazardous waste facility.
                                86

-------
                            Appendix A

                      RESPONSIVENESS SUMMARY
            FOR THE HARBOR ISLAND PSCORD OF DECISION
Overview
     From 1903 to 1905, Harbor Island was created from marine
sediments dredged from the Duwamish River.  Harbor Island has
been used for commercial and industrial activities including
shipping, railroad transportation, bulk fuel storage and
transfer, secondary lead smelting, lead fabrication, shipbuilding
and metal plating.  Warehouses, laboratories and office buildings
have been located on the island.  Approximately 70% of Harbor
Island is covered with buildings, roads or other impervious
surfaces.

     The site was placed on the National Priorities List in 1983,
due to elevated lead concentrations in soil, as well as elevated
levels of other hazardous substances.  The lead concentrations
were due to a lead smelter on the island, which ceased operations
in 1984.

     In 1985, Department of Ecology performed an initial
investigation to define the general nature and extent of
contamination.  In 1990, EPA completed Phase I of the
investigation, which focused on several suspected sources of
contamination on the island.  In 1991 and 1992, EPA conducted
Phase II of the investigation.

     The marine sediments and Lockheed shipyard on Harbor Island
have been designated as separate operable units.  The marine
sediments proposed plan and the Lockheed shipyard proposed plan
will be issued in 1994.

     On June 23, 1993, EPA began the public comment period on the
cleanup alternatives for the soil and groundwater at the Harbor
Island site.  The proposed plan as well as the reports of the
investigation, were released for public comment.

     The proposed plan recommended Alternative 11B for soil and
which includes removal and treatment of organic hot spots,
capping of areas exceeding defined cleanup goals for organics and
metals. The proposed plan also recommended Alternative 2 for
groundwater which includes removal and treatment of floating
petroleum product and contaminated groundwater at one location
and groundwater monitoring island-wide.

Background on Community Involvement

     As described above, the proposed plan for the cleanup of the
soil and groundwater at the Harbor Island Superfund site was

-------
 released on June 23,  1993.  The public comment  period  ran  from
 June  23  until  July 23,  1993.  A request  from a  citizen extended
 the comment period until August 23.

      As  part of the comment period, a public meeting was held on
 July  14,  1993.  'About 50^^ people""attended"th~e~ meeting/  no one gave
 public comment.   Copies of the transcript are available at the
 Region 10 Records office in the Park Place Building, 1200  West
 6th Avenue.                                                  •

      Comments  received in writing are included  in  the  following
 summary.  Where similar comments were received from several
 commentors,  the comments were lumped together and  a single
 response was prepared.

                      Responsiveness Summary

 Preferred Alternative:

 Comment:   The  Harbor  Island Employers Association  endorsed the
 preferred alternative.  The association  is anxious for the
 remediation to begin  as quickly as  possible so  that normal
 activities can proceed.

 Response;  Commented noted.


 Comment:   Several commentors agreed with the general elements of
 the preferred  alternative.

 Response;   Comment Noted.


 Comment;  The Proposed Plan calls for incineration  of soil
 containing PCBs over  50 ppm.  TSCA  specifically allows for PCB
 contaminated soil at  concentrations of 50 ppm or greater to  be
 disposed of in a chemical waste landfill.  Therefore the option
 of landfilling the soil should remain in order  to  reduce cleanup
 costs.

 Response;   EPA agrees.  The selected remedial action will  now
 include  the option of disposal at a hazardous waste disposal
 facility for soil with PCB concentrations exceeding  50 ppm.


 Comment:   Digging up  the lead contaminated  soil and  hauling it
 away  could be  more damaging than leaving it  in  the ground.

 Response;  The  preferred alternative does not  require  excavation
•of lead  contaminated  soil.  It will be capped in place to  prevent
 direct contact and migration to the surface water.

-------
Comment:  Soils which are treated by thermal desorption to remove
TPH should only be capped if concentration of other chemicals of
concern exceed their cleanup criteria. It is unclear which soils
need to be solidified after treatmer +: by thermal desorption.
During the thermal desorption process, substantial mixing and
disturbance of the soils will also occur.  Thus, prior to capping
the presence of chemical concentration exceeding the cleanup
goals should be determined.  EPA should consider consolidation of
materials that require capping to increase cost-effectiveness.


Response;  Soil which contains inorganic contaminants above the
cleanup goals, after removal of TPH by thermal desorption, would
have to be solidified if the concentrations of inorganics were
high enough to constitute a "characteristic" RCRA waste.  To
determine if treated soil is a RCRA characteristic waste, soil
would have to be tested according to the TCLP (leachate) method
before it is replaced in the ground.  If soil contains inorganics
which leach above concentrations established by RCRA regulations,
this soil would have to solidified before placing it in the
ground.  If the treated soil does not leach at concentrations
high enough to make it a RCRA waste, the soil would be placed in
the ground and then capped.  EPA will consider consolidation of
treated materials if the results of the remedial design indicate
that there may by an increase in cost-effectiveness.


Cleanup Goals:

Comment; Several commentors stated that EPA has improperly
applied the State of Washington's Model Toxic Control Act, Method
"A", to select cleanup goals for contaminants (particularly
petroleum) at Harbor Island.  Many commentors said that Method
"C" would be more appropriate for determining cleanup goals at
this site.

Response: In the Proposed Plan, EPA applied Method "A" to lead
and Total Petroleum Hydrocarbons (TPH), for which no Method "C"
calculations exist.  Method "A" was also applied to all
contaminants in the subsurface soil because of anticipated
infrequent exposure of short duration.  Method "C" was applied to
all contaminants other than lead and TPH in the surface soil.  As
a result of comments received from Ecology  (see below), EPA has
decided to revise the cleanup goals for petroleum, based on
Ecology's Petroleum-Contaminated Soils Rating Matrix method, to
be consistent with Ecology's cleanup goals for the petroleum tank
farm operable unit.  In regard to EPA's use of Method  "A",
Ecology has confirmed that Method "A" is appropriate for lead in
surface soil and for all contaminants, other than petroleum,  in
the subsurface.

-------
Comment: Ecology informed EPA that the originally selected
cleanup goal of 200 mg/kg for TPH, based on Method A, is not
appropriate for Harbor Island. Ecology has recently established
cleanup goals for petroleum contaFiran*. r for the petroleum tark
farm operable unit based on the Petroleum-Contaminated Soils
Rating- Matrix method (which satisfies MTCA Method B). Ecology has
determined that this method is appropriate for the rest of the
island. The cleanup goals using this alternate method are: TPH
(gas) = 400 mg/kg, TPH (diesel) = 600 mg/kg, Benzene = 1 mg/kg,
Toluene = 100 mg/kg, Ethybenzene = 200 mg/kg, and Xylene = 150
mg/kg.

Response; EPA will accept these new cleanup goals for the above
petroleum compounds and will eliminate the previously identified
goal of 200 mg/kg for TPH identified in the Proposed Plan.  The
island-wide petroleum cleanup goals will now be consistent with
the goals established by Ecology.


Comment: The Department of Ecology expressed concern that the
method used by EPA to select cleanup action levels for'hot spot
contaminants was not justified.

Response:  The objective of the cost-benefit method used to
select the hot spot cleanup action levels was to identify areas
containing high concentrations of contaminants in relatively
small volumes of soil, which could be excavated and treated with
an optimal cost-benefit. (The cleanup action levels are now
referred to as "treatment levels" in the Record of Decision.) The
cost-benefit method was used for the contaminants lead, mercury,
and TPH.  Treatment levels were derived through an iterative
analysis which compared the contaminant volume to the contaminant
mass within that volume, over a range of concentrations. The
treatment level for each contaminant was then selected at the
point where the incremental mass of contaminant was found to be
disproportionate to' the incremental volume of contaminated soil.
Subsequent to performing this analysis, a more comprehensive
cost-benefit analysis was performed to verify these treatment
levels. A description of how this method was used to select"
treatment levels is provided in Appendix B.

The treatment levels for the PCBs and mixed carcinogens hot spots
were set according to regulatory limits. The treatment level for
PCBs of 50 mg/kg was set equal to the concentration regulated
under the Toxic Substance Control Act  (TSCA), and the treatment
level for mixed carcinogens was set at the upper end of the
acceptable risk level  (IxlO"4)  specified  for Superfund  sites
according to the National Contigency Plan  (NCP).

-------
Comment;: The cleanup goals for PCBs of 0.18 to 2.99 mg/kg is
unreasonably stringent.  This range is significantly below the 10
mg/kg standard for industrial areas under the state of
Washington's MTCA Method A.

Response; When there is a mixture of contaminants, as occurs at
many locations on Harbor Island, MTCA Method A is not
appropriate. In such cases the appropriate method is Method C,
which requires that cumulative risk from all carcinogens at each
location not exceed 10"5.  At many locations, the PCBs are
collocated with other carcinogens, such as arsenic or PAHs. To
maintain an acceptable cumulative risk level, the PCB cleanup
level must be a fraction of what it would be if it were the only
contaminant present.


Petroleum:

Comment; Materials identified at Harbor Island as petroleum fuel
products and residues are not hazardous substances as defined in
CERCLA and therefore are not subject to EPA's jurisdiction under
CERCLA.

Response; There has been some confusion about the CERCLA
petroleum exclusion provision.  Under CERCLA, pure petroleum
products are not hazardous substances.  However, when mixed with
other hazardous substances, it is appropriate for EPA to take
jurisdiction for cleaning up such mixtures.  At Harbor Island,
EPA specifically carved out a separate petroleum tank farm
operable unit to be managed by Ecology because contamination in
this unit is derived principally from petroleum.  All areas of
the island outside of the tank farm unit are not areas of purely
petroleum contamination and are therefore subject to EPA's
jurisdiction.


Comment: One commentor stated that EPA inappropriately excluded
other viable remedial alternatives from consideration for
petroleum contaminated soil.  Two other alternatives specifically
identified were in-situ bioremediation and use of petroleum
contaminated soil for asphalt production.

Response: In the Feasibility Study, EPA evaluated a wide range of
treatment technologies used to remediate hazardous waste sites
and. screened out many of these technologies based on the criteria
of effectiveness, implementability and cost.  Of the eleven
alternatives which received full evaluation, EPA believes that
thermal desorption best meets the nine evaluation criteria. In
particular, it is a proven technology, it can meet the cleanup
action goals,.it is the most cost-effective treatment technology
identified, and is easily implemented.  In addition, the TPH

-------
removed from the soil can be recycled and used in other
applications, such as making asphalt.  In-situ bioremediation was
evaluated in alternative 5 and was not selected because: 1) it is
not certain that cleanup action goa"s could be met without
conducting an extensive treatability study, 2) it was not as cost
effective as the selected "technology, and 3) gxoundwater
extraction, as required by this method, is not feasible at the
shoreline because it would draw in and pump out saltwater from
the surrounding surface water.


Comment; Where oil is in quantity and situated where it can be
extracted from the soil it should be pumped and recovered.

Response; The selected remedial action is consistent with the
concept of recovery because it requires that high concentrations
of petroleum in the soil (hot spots) be recovered by thermal
desorption and that floating petroleum product be pumped and
recovered. Once recovered, this petroleum may have the potential
to be used in such applications as asphalt production.


Cost:

Comment: There should be better substantiation of the estimated
costs for the alternatives which are being compared.

Response; The level of cost detail anJ the assumptions used ir.
developing the cost estimates for each alternative is adequate
for a Feasibility Study.  EPA included conservative contingencies
into the cost calculations to cover additional unforeseen
expenses.  However, the costs at this point are only an
engineering estimate and will be further refined during the
remedial design.


Comment: It is unclear whether the cost estimate for the
preferred alternative includes the cost to incinerate the 2,000
cubic yards of PCB-contaminated soil in an off-site commercial
incineration facility.

Response; The cost estimate for the preferred alternative does
include -the cost of off-site incineration for PCB-contaminated
soil.
Remedial Investigation/Feasibility Study:

Comment: The description of the selected alternative presented in
the feasibility study addendum indicates that soil containing
PCBs and PAHs at levels below the hot spot criteria will be
excavated and disposed off-site in a hazardous waste landfill.

                                6

-------
No such requirement is indicated in the description of the
preferred alternative in the Proposed Plan.

Response: The Proposed Plan identified organic hot spots with a
total carcinogen risk exceeding 10"*.  These organic hot spots
constitute soil containing mixtures of PCBs (at concentrations
below 50 ppm) / PAHs, and arsenic.  The total volume of soil
associated with these organic hot spots is approximately 1,200
cubic yards.  The description of the selected alternative in the
feasibility study addendum identifies off-site disposal in a
hazardous waste landfill for this soil.  Because of an oversight,
the preferred alternative in the Proposed Plan did not discuss
disposal of this hot spot soil.  The Record of Decision will
identify this soil for off-rsite disposal.


Comment; Several commentors identified numerous technical errors,
discrepancies and inaccuracies in the Remedial Investigation and
Feasibility Study (RI/FS) Reports.

Response: None of the technical errors, discrepancies or
inaccuracies identified were regarded as significant by EPA and
did not change EPA's selection of the preferred alternative.
However, EPA has responded to these comments collectively in the
form of a Technical Errata Memorandum which will be attached to
the RI/FS report.


Comment; The Port of Seattle (Port) believes that the groundwater
monitoring plan should be revised to reduce the number and modify
the locations of proposed compliance monitoring wells on Port of
Seattle Terminal 18 property.

Response: The groundwater monitoring plan identified in the
Feasibility Study is intended to be a preliminary design.  Final
location and number of monitoring wells will be determined during
the Remedial Design and can be negotiated between EPA and the
potentially responsible parties (PRPs) at that time, assuming
that the PRPs are implementing the remedial action for the site.


Comment; Lockheed commented that the hot spot maps should be
revised to incorporate the Phase II RI data collected at the
Lockheed Shipyard 1.  This new data has reduced the area defined
as TPH hot spots on the Lockheed property by approximately 97%,
relative to the TPH hot spot area estimated by EPA in the
Feasibility Study.

Response: EPA intends to reevaluate the Phase II RI data and its
impact on the size of the TPH hot spots on the Lockheed Shipyard
facility before it issues a Proposed Plan for that facility next

-------
year.  Since -these hot spots are substantially on the Lockheed
facility, they were not addressed in the Harbor Island Proposed
Plan and are not addressed in this Record of Decision.
Groundwater:

Comment: For the groundwater model, why were maximum
concentrations of contaminants used.  Also, using the current
rate of rainfall infiltration is not reasonable since capping is
recommended as part of the soil remedial action.  The selection
of groundwater treatment is based on data from only two rounds of
groundwater sampling.

Response: Maximum contaminant concentrations and current rates of
rainfall infiltration for the groundwater model were used because
these conditions are considered conservative. Since there are
uncertainties in the groundwater data collected during the
Remedial Investigation, and uncertainties in the groundwater
modeling used, EPA believes it .is prudent to be conservative so
that the environment is protected against the most sever
groundwater contamination which could reach the shoreline. The
only groundwater treatment in the selected remedy involves
pumping•and treating the floating petroleum product at Todd
Shipyards. At this location approximately 6 inches of floating
product was observed during installation of the monitoring well.
Benzene concentrations at this location for both rounds of
sampling exceeded the surface water cleanup goal by approximately
an order of magnitude. This data indicates that this area of
groundwater contamination presents a critical risk to the
environment and should be addressed immediately.  After remedial
action is initiated, groundwater will be monitored island-wide
semi-annually for up to 30 years. This groundwater data will be
reviewed every five years to determine if progress towards
cleanup goals is being achieved. If adequate progress is not
being achieved at that time, additional groundwater treatment
could be required.


Comment; In the Feasibility Study, groundwater cleanup goals
(MCLs) based on drinking water standards were identified as
alternate cleanup goals for several contaminants. MCLs are not
appropriate for Harbor Island because the groundwater is not
potable.

Response: EPA agrees. The MCLs were initially identified as
alternate cleanup goals in the Feasibility Study before EPA and
Ecology decided that the drinking water standards do not apply to
the Harbor Island groundwater.  In the Proposed Plan, only the
surface water standards were cited as cleanup goals at the
shoreline.
                                8

-------
Comment:  Lockheed commented that "the industrial nature of the
area and the general consensus that groundwater will not be used
as a potable water supply, a much higher cleanup level for TPH,
such as 1,000 rag/kg for TPH as heavier petroleum fuel, would be
appropriate and more than adequately health protective for the
site."

Response:  EPA has adopted Ecology's cleanup goals for petroleum
products based on the Petroleum Contaminated Soils Rating Matrix
method (see response above).  The new cleanup goal for heavy
petroleum fuel (diesel), is now 600 rag/kg.


Comment: The Port commented that it is unable to determine
whether groundwater compliance will be based on monitoring data
which includes only metals that exceed cleanup goals in each
respective well or on all metals of concern at each well.  The
Port believes it would be more appropriate to monitor all
compliance monitoring wells for all metals of potential concern,
rather than selective metals, of potential concern in order to
address trends in groundwater quality.

Response: EPA agrees. It is EPA's intent to monitor for all
metals at all compliance monitoring wells.  This will be
necessary to determine trends in groundwater quality.


Comment; EPA has recommended a remedial action for soil based on
limited soil data and overestimation of volumes due to use of
Thiessen polygons.

Response: The RI/FS established preliminary estimates of
contaminated soil volumes. Additional soil sampling will be
required during the Remedial Design phase to more accurately
identify volumes of soil which must be excavated and treated or
disposed off-site.


Risk Assessment:

Comment: The risk assessment does not address background.  The
low end of the cleanup goal range for arsenic is.potentially
below background levels in surface soils for this area and it is
unrealistic to clean up below background levels. EPA used an
overconservative scenario  (daycare facility) to estimate
potential risk.  Risk was also evaluated on a location-by-
location basis which leads to an overestimation of risk.

Response:  The low end of the cleanup goal range for arsenic
occurs in locations where arsenic is collocated with other
carcinogens and the combined risks of all carcinogens present
                                9

-------
exceeds the cleanup goal of 10"5.  To maintain an acceptable
cumulative risk level, the arsenic cleanup level must be a
fraction of what it would be if it were the only contaminant
present.. There are no daycare cent-rs curr ^itiy on Harbor
Island, but the island is zoned for commercial uses, which
includes daycare centers. The daycare center scenario was
conducted as a hypothetical scenario, but was not used in
establishing cleanup goals because EPA selected cleanup goals for
an industrial scenario as appropriate .for Harbor Island.  EPA
does not agree that a location-by-location risk assessment
overestimates risk.
                         «

Potential Responsibility:

Comment: Several commentors raised the issue that they should not
be considered Potentially Responsible Parties (PRPs), even though
they were either owners of property or operators of facilities on
the site.

Response: CERCLA 107(a)(1)  which makes owners and operators of a
Superfuhd site responsible parties is a strict liability statute.
Fault is not a relevant consideration in assessing liability
under any strict liability statute.  Contribution or relative
responsibility among PRPs is relevant with respect to allocation
or cost sharing among PRPs at Harbor Island.  EPA has not
allocated relative cost share among PRPs. Allocation of liability
among PRPs will be addressed in future Consent Decree
negotiations with the PRPs for implementation of the remedial
actions selected in this ROD.

Other:

Comment: Although the lead smelter may have been a source of lead
on the island, data indicate that there are other sources of
elevated lead concentrations in the soil.

Response: EPA recognizes that another potential source of lead
found, in the soil is combustion of leaded gasoline from cars and
trucks on the island.  However, the distribution of elevated lead
in the soil (see Map 4-43 of the Remedial Investigation Report)
strongly indicates the smelter as the. primary source of lead
contamination.
Comment: In addition to deed restrictions on affected property,
EPA should also consider working with the City of Seattle to
restrict zoning to insure the area remains industrial or to place
deed restrictions on all parcels on Harbor Island to avoid
incompatible uses adjacent to affected areas.
                                10

-------
Response: EPA will consider these options. However, zoning
restrictions are subject to political change and processess and
cannot be viewed as comparably reliable or permanent as deed
restrictions.


Comment: EPA should continue to work upstream on the Duwamish and
evaluate contribution to marine sediment from the stream as well
as. from Harbor Island.

Response: As part of the marine sediment remedial investigation,
EPA sampled sediments as far upstream in the Duwamish as Kellogg
Island in an attempt to distinguish upstream sources from Harbor
Island sources.  The draft Sediment Remedial Investigation Report
which discusses the results of this sampling is available for
public review at EPA's Record Center, 7th Floor, 1200 Sixth Ave,
Seattle.  EPA intends to issue the Feasibility Study and Proposed
Plan for the sediment operable unit next summer.


Comment; There are several Puget Sound Air Pollution Control
Agency (PSAPCA) regulations that PSAPCA considers Applicable or
Relevant and Appropriate Requirement (ARARs) for several of the
options discussed in the soil cleanup plan including the
preferred alternative.

Response; EPA will require that all substantive requirements of
these PSAPCA regulations are met durin.., Implementation of the
selected remedial action.


Comment; There is a misconception that (referring to page 17 of
the Proposed Plan) "thermal desorption is not highly effective
for removing PCBs from soil".  Thermal desorbers are no less
efficient than incinerators when operated under the same time and
temperature conditions.

Response: EPA acknowledges that thermal desorbers can effectively
remove PCBs from soil given the proper operating conditions.
However, given that PCB concentrations were found as high as 420
ppm and that EPA's cleanup goal for PCBs is about 3 ppm, this
will require a removal efficiency of greater than 99%.  While
this efficiency may be attainable, EPA believes the uncertainty
of obtaining it poses a risk.  As an alternative to incineration,
EPA is now providing the option of disposal at a hazardous waste
disposal facility for PCB contaminated soil, which should be more
cost effective than.incineration.


Comment; While the polygon map approach can provide a. reasonable'
basis to screen remedial alternatives for the entire Harbor
Island site, it should not provide the sole basis  for determining

                                11

-------
areas that: require remediation.  Field testing methods will be
useful for distinguishing between soil containing PCBs and soil
containing TPH alone.

Response: Additional soil sampling will be required during the
Remedial Design phase to more accurately determine the areas and
volumes which will require excavation and treatment.  Certain
field testing methods, with the appropriate detection limits and
level of accuracy, could be used at that time as a screening
technique to distinguish between PCB and TPH contaminated soil.


Comment; EPA's use of cumulative risk levels as a criterion for
determining cleanup action levels for hot spots is not amenable
to use of field screening methods to define areas requiring
remediation during the Remedial Design phase.

Response: Field screening methods may not be as effective for
defining these hot spot areas since they contain mixtures of
carcinogens (PCBs, arsenic, PAHs). Since these areas contain
mixtures, the corresponding detection limits required for
individual carcinogens will be lower than if they occurred alone.
If appropriate detection limits cannot be achieved with field
screening methods, standard laboratory analytical methods,
similar to those used by EPA during the Remedial Investigation,
will be required.


Comment: On the Seattle Iron & Metals Corporation (SIMC)
property, a PCB concentration exceeding the hot spot criterion
was detected at one location, which was not tested for TPH.
Because it is uncertain if TPH is present at this location, it
cannot be determined if PCBs at that location are mobile. Because
the cost of proposed treatment (offsite incineration) for PCBs is
so high, additional field testing to assess TPH concnetrations at
this location would be worthwhile. If TPH is not present at
significant concnetrations, capping of the PCB contaminated soil
would provide a more cost-effective approach to protecting human
health and the environment.

Response:  Enhanced mobility of PCBs in the presence of TPH was
only one of the criteria used by EPA in selecting the cleanup
action level for PCBs. The other criteria is that according to
TSCA regulations, incineration or disposal at a hazardous waste
disposal facility is required for all PCB contaminated soil with
concentrations exceeding 50 mg/kg.  EPA will allow disposal at a
hazardous waste disposal facility as an alternative to
incineration for levels of PCBs exceeding 50 mg/kg.


Comment; Based on information regarding SIMC's operations, it
appears unlikely that gasoline or other lighter-weight, more

                                12

-------
mobile petroleum hydrocarbons were a significant source of TPH
detected at the SIMC property.  Instead, heavier-weight, less
mobile petroleum hydrocarbons are more likely to have been
handled. Thus, EPA should consider capping the TPH hot spot on
the SIMC property/

Response; EPA has made no distinction between the mobility of
lighter-weight or heavier-weight petroleum hydrocarbons. EPA
considers both types of. hydrocarbons to be relatively mobile
compared to other organic and inorganic contaminants found at
Harbor Island. EPA will still reguire treatment of the TPH hot
spot on the SIMC property.


Comment: The use of low-temperature thermal desorption is not
appropriate in every instance because of its limitation in
treatment of heavier petroleum hydrocarbons.

Response: EPA has determined that the concentrations of high
molecular weight PAHs (HPAHs) in the TPH hot spots are not
significantly elevated and can be effectively treated by thermal
desorption and reduced to levels below the cleanup goals.
Through its Research and Development Program, EPA has
demonstrated that thermal desorption technology operated at
higher temperatures and longer soil retention times can remove
HPAHs from soil with a high efficiency.
                                13

-------
                   APPENDIX  B
METHOD FOR DETERMINING HOT SPOT TREATMENT LEVELS

-------
                           Appendix B

         Method for Selecting Hot Spot Treatment Levels




I.  Method Used in the Feasibility Study

  The  objective of  selecting hot  spot  treatment  levels  in  the
Feasibility   Study   was  to   identify   areas  containing  high
concentrations of contaminants  in relatively  small  volumes which
could be excavated and treated,  providing an optimal cost-benefit.
The benefit,  in this context,  is the  total mass of contaminant
treated. The  first step  in the  process  was to   identify  the
contaminants presenting the greatest risk to human health and the
environment.  This  was  accomplished  by  comparing  contaminant
concentrations  to the cleanup  goals to  determine which  had  the
highest  exceedances.  This  process  identified  lead,  mercury,
arsenic, TPH, and  PCBs.  Arsenic was  eliminated  at  this point
because the distribution of  its concentration showed that it was
widely distributed  across the island at  levels not significantly
above background, and was not highly  concentrated in any particular
areas. PCBs were also  elimianted from  further evaluation because
EPA decided to  set  its treatment level at an existing regulatory
limit, which is 50 mg/kg as defined by the federal Toxic Substance
Control Act (TSCA).

  For TPH,  lead, and mercury, the concentrations and soil volumes
associated with these concentrations were reviewed to identify the
approximate.point at which the mass of contaminant started rapidly
decreasing as a function of increased soil volumes.  The treatment
levels were selected at the  contaminant  concentrations where the
incremental  amount   of  contaminant  was  disproportionate  to  the
incremental soil volume. The cost to treat these contaminants was
also analyzed semi-quantitatively to verify that the cleanup level
selected was  also   at  the  point  where  the  cost  per  mass  of
contaminant treated started rapidly increasing.

  For example, treating all lead contaminated  soil would result in
treating 5.9  x  106 cubic yards of soil to remove 4.4 x 106 pounds
of lead for an average of  0.75 pounds/cubic yard treated. Treating
soil exceeding  2,000 mg/kg  lead would result  in  an average lead
treatment rate  of 40 pounds/cubic yard.  Treating  soil exceeding
5,000 mg/kg, 10,000  mg/kg  and 20,000 mg/kg would result in average
rates  of 57,  60,  and 100  pounds/cubic  yard,  respectively.  A
noticeable increase in the amount of lead treated percubic  yard of
soil occurs at a lead concentration of greater than 10,000 mg/kg.
Therefore,  10,000 mg/kg was  selected as the  treatment level for
lead. This treatment level contains  approximately 85% of the total
mass of lead  within 40% of the total  volume of lead contaminated

-------
soil above the cleanup goal.  The treatment level selected for TPH,
10,000 mg/kg, contains 66% of the  total TPH mass within 14% of the
TPH contaminated soil volume. The  treatment level  selected for
mercury, 5 mg/kg, contains 27% of  th- mass of mercury within £% of
the contaminated soil volume. These results show that the objective
of  containing a majority  of the contaminant  mass in a  minimum
volume is achieved at the  treatment levels  for lead  and  TPH. The
treatment level for mercury did not capture a majority of the mass
of  mercury,   because mercury  is  more  evenly  distributed  as  a
function of concentration than TPH or lead.

  The corresponding cost analysis  for lead,  for example, also shows
that as the  pounds of contaminant per cubic  yard decreases, the
cost to treat each pound rapidly increases. Assuming it costs $100
to treat one cubic yard of soil, the average cost to treat a pound
of lead at soil concentration exceeding 2^000 mg/kg,  5,000 mg/kg,
10,000 mg/kg, and 20,000 mg/kg is $2.50/lb, $1.75/lb, $1.66/lb, and
$1.00/lb, respectively. The cost drops  significantly at  a lead
concentration exceeding 10,000 mg/kg,  indicating  it  is  the cost
effective breakpoint, and therefore, should be the treatment level.
The cost effective breakpoint for TPH occurred at a concentration
of about 10,000 mg/kg, and the breakpoint for mercury occurred at
about 5 mg/kg.


II. Cost-Benefit Analysis of Treatment Levels

  After selecting  treatment levels in  the Feasibility  Study,  a
cost-benefit  analysis  was  completed for  lead,  mercury and TPH to
confirm these treatment levels. The analysis involved generating
two types  of functions (curves). The  first type  of  curve, .soil
volume versus contaminant mass, was generated by ranking areas with
the  particular  contaminant   in  order   of  highest  to  lowest
concentration.  The  curve  is  based  on  the  cumulative   total
contaminant   mass   and  soil   volume   for  each   contaminant
concentration. One  assumption used in generating  this curve was
that  the  average   contaminant   concentration  is  an  area  is
represented by the single sample taken from that location.

  The second type of  curve, mass of contaminant treated versus cost
per  pound  of  contaminant,   was  generated  by  calculating the
excavation cost  and treatment cost, per  cubic yard  of soil, and
dividing by the mass.of contaminant treated. This process was also
performed  using  cumulative totals  as  discussed above.   It  is
important to  note that this figure is semi-quantitative in nature
since it used only excavation and treatment cost elements and did
not  include  other  costs  required  to  implement the treatment
alternative. Simplifying assumptions used to generate  these curves
include:  1)  soil excavation costs  are  $2.00 per  cubic  yard, 2)
excavation and handling costs are  $6.00 per cubic yard, 3)  lead and
mercury are treated  by solidification at a cost of $100 per  cubic
yard, 4) TPH is treated by thermal desorption at a cost of $100 per
cubic  yard,   and 5)   the  contaminated soil  associated  with the
Lockheed Shipyard operable unit was included in the calculation but

-------
the  contaminated soil  associated with  the petroleum  tank farm
operable unit was not included.

  The volume versus mass curve was ured to determine the point at
which removing and treating additional1 soil volume does not provide
a proportionate degree of benefit  in term of mass treated. The mass
versus cost per pound curve was used to determine the cost-benefit
of treating an additional incremental volume of  soil. As shown in
each  of the  figures,  the  treatment levels  generally mark  the
location   at  which  signigicantly   decreasing  quantities   of
contaminant mass are treated with each incremental increase in soil
volume  removed.  The treatment levels also generally  locate  the
point at which the cost  per pound  of contaminant treated increases
disproportionally with  the soil mass removed.

-------
        20
         15


          .
        r°
                                                                              hot spot action level
                         100
200
400
                                                        Thousands

                                                Soil Treated (cubic yards)
500
600
                                                                                                                     12,000
                                                                                                                +-• 70,000
                                                                                                                     91,000
700
RFWSMA-OtiphlA

-------
                                                  10
                                              Millions
                                    • Mass of TPH Treated  (pounds)
RfWJ
-------
  C/3
  T3
                                                    100
                                               Thousands
                                    Soil Treated (cubic yards)
RFWJMA.WK3-ORAPH3

-------
         Millions
Mass of Lead Treated (pounds)

-------
     1200
                                                           100
                                                      Thousands
                                            Soil Treated (cubic yards)
RFW5MA.WK3-ORAPH4

-------
  I
        20
        15
   R  110
   •—
   oo
   O

  u
        if
                      • hot spots •
                        200
' 400   479      600            800

Mass of Mercury Treated  (pounds)
1000
1200
RPVJMA.W10 GRAPH 7

-------