United States
           Environmental Protection
           Agency
             Office of
             Emergency and
             Remedial Response
EPA/ROD/R02-88/056
January 1988
oEPA
Superfund
Record of Decision
            American Thermostat, NY

-------
 50277-101	,
  REPORT DOCUMENTATION
         PAGE
1. REPORT NO.
          EPA/ROD/R02-88/056
                                                3. Recipient's Accession No.
 4. Title end Subtitle
 .   SUPERFUND RECORD OF DECISION
             Thermostat, NY
          Remedial  Action
                                                9. Report Oete
                                                      01/07/88
 7. Authorts)
                                                                         8. Performing Organization Rept. No;
 9. Performing Organization Name and Address
                                                                         10. Project/Task/Work Unit No.
                                                                         11. Contract(C) or Grant(G) No.

                                                                         (C)

                                                                         (G)
 12. Sponsoring Organization Name and Address
    U.S. Environmental Protection Agency
    401 M Street,  S.W.
    Washington,  D.C.   20460
                                                13. Type of Report & Period Covered

                                                     800/000
                                                                         14.
 IS. Supplementary Notes
 16. Abstract (Limit: 200 words)
       The American Thermostat  Corporation  (ATC) site,  occupying approximately eight acres,
    is located  in  South Cairo,  New York.  Private homes are near the site on its  eastern and
    western boundaries.-  Former plant operations involving the assembly of thermostats for
    small appliances were carried out in  one existing  large building.   From the mid 1950s
    through at  least 1981, waste containing TCE and PCE sludges were poured down  drains
    which were  connected to an  abandoned  septic system and dumped outside onto plant
              The  drains were connected to  the abandoned septic system.  .In March 1981, two
        employees  were observed dumping solvents on plant property.   This triggered
    investigations into the company's waste handling practices by the New York State
    Department  of  Environmental Conservation (NYSDEC)  and the New York State Attorney
    General's office.  Subsequently, water  samples collected in five privately-owned wells
    in the ATC  vicinity revealed the presence of high  levels of TCE  and PCE.  As  a result,
    ATC began supplying bottled water to  local residents in April 1981.  By late  1982, ATC
    had installed  carbon filters on its own well and the affected residential wells.
    Pursuant  to a  1983 Consent  Order, ATC and AMRO Realty Coperation (AMRO), the  owners of
    the property,  agreed to clean up the  site and its  surroundings;  supply bottled water for
    cooking and drinking purposes; and install, monitor, and maintain carbon filter systems
    (See Attached  Sheet)
 17. Document Analysis  a. Descriptors
    Record of  Decision
    American Thermostat, NY
    First Remedial  Action
    Contaminated Media:  gw
                        PCE,  TCE,  VOCs
   c. COSATI Field/Group
 l^_Ayailab!lity Statement
                                                         19. Security Class (This Report)
                                                                None
                                                         20. Security Class (This Page)
                                                                None
                                                          21. No. of Pages
                                                                  104
                                                                                   22. Price
(See ANSI-Z39.18)
                                         See Instructions on Reverse
                                                         OPTIONAL FORM 272 (4-77)
                                                         (Formerly NTIS-35)
                                                         Department of Commerce


-------
                 DO  NOT  PRINT  THESE  INSTRUCTIONS AS  A PAGE  IN  A REPORT


                                                     INSTRUCTIONS
Optional Form 272. Report Documentation Page is based on Guidelines for Format and Production of Scientific and Technical Reports.
ANSI Z39.18-1974 available from American National Standards Institute. 1430 Broadway, New York, New York 10018. Each separately
bound report—for example, each volume in a multivolume set—shall have its unique Report Documentation Page.

 1. Report Number. Each  individually bound report shall carry a unique alphanumeric designation assigned by the performing orga-
    nization or provided by the sponsoring organization in accordance with American National Standard ANSI Z39.23-1974, Tec^sitai
    Report Number (STRN). For registration of report code, contact NTIS Report Number Clearinghouse. Springfield, VA 22161. Use
    uppercase letters. Arabic  numerals,  slashes, and hyphens  only,  as in  the  following  examples:  FASEB/NS-75/87 and  FAA/
    RD-75/09.

 2. Leave blank.
 3. Recipient's Accession  Number. Reserved for use by each report recipient.

 4. Title and Subtitle. Title should indicate clearly and  briefly the  subject coverage of the report, subordinate subtitle to the main
    title. When a report is prepared in more than one volume, repeat the primary title, add volume number and include subtitle for
    the specific volume.

 5. Report Date.  Each  report shall carry  a date indicating at least  month and year. Indicate the basis on which it was selected (e.g.,
    date of issue, date  of approval, date of preparation,  date published).

 6. Sponsoring Agency Code.  Leave blank.

 7. Author(s). Give name(s) in conventional order (e.g., John R. Doe, or J. Robert Doe).  List author's affiliation  if  it differs from
    the performing organization.

 8. Performing Organization Report Number. Insert  if  performing organization wishes to assign this number.

 9. Performing Organization Name and  Mailing Address. Give name, street, city, state, and ZIP code. List no more than two levels of
    an organizational hierarchy. Display the name, of the organization exactly as it should appear In Government  indexes such as
    Government Reports Announcements & Index (GRA & I).

10. Project/Task/Work Unit Number. Use the project, task and work unit numbers under which the report was prepared.

11. Contract/Grant Number.  Insert.contract or grant number under which report was prepared.

12. Sponsoring Agency Name and Mailing Address. Include ZIP code. Cite main sponsors.

13. Type of Report and Period Covered. State interim,  final, etc.. and. if applicable, inclusive dates.

14. Performing Organization Code.  Leave blank.

15. Supplementary Notes. Enter information not included elsewhere but useful, such as: Prepared In cooperation with ... Translation
    of ... Presented at conference of ... To be published in ...  When  a report  is revised, include a statement whether the  new
    report supersedes  or supplements the older report.

16. Abstract. Include a brief (200 words or less) factual summary  of the most significant information contained in the report. If the
    report contains a significant bibliography or literature survey, mention it here.

17.  Document Analysis, (a). Descriptors. Select from the Thesaurus of Engineering and Scientific Terms the proper  authorized terms
    that identify the major concept of the research and are sufficiently specific and precise  to be used as index entries for cataloging.
    (b).  Identifiers and Open-Ended Terms. Use  identifiers for project names, code names, equipment designators, etc.  Use open-
    ended terms written in descriptor form for those subjects for which no descriptor exists.
     (c). COSATI Field/Group. Reid and Group assignments are to  be  taken from the  1964 COSATI Subject Category  List. Since the
    majority of documents are multidisciplinary in  nature, the primary Field/Group assignment(s) will be the specific  discipline,
    area  of human endeavor, or  type of physical object. The  application(s) will be cross-referenced with secondary Reid/Group
    assignments that will follow the primary posting(s).

18. Distribution Statement Denote public reusability, for example  "Release  unlimited", or limitation for  reasons other  than
    security. Cite any availability to the public, with address, order  number and price, if known.

 19. & 20. Security Classification. Enter U.S. Security Classification in  accordance witM U.S. Security Regulations (i.e., UNCLASSIFIED).

 21. Number of pages. Insert the total number of pages, including introductory pages, but excluding distribution list, if any.

22.  Price.  Enter price  in paper copy (PC) and/or microfiche (MF) if known.

••••  Cr-O :  1983 0  -  381-526 (8393)                                                          OPTIONAL FORM 272 BACK (4-77)

-------
EPA/ROD/R02-88/056
American Thermostat, NY
First Remedial Action

16.  ABSTRACT (continued)


for the five affected homes.  ATC and AMRO did not fully comply with the Consent Order
and did not remedy the contamination at the site.  In June 1983, a new onsite
4,500-gallon septic system was installed and, in September 1983, ATC provided carbon
filtration for septic system discharges to lower PCE levels.  ATC ceased operations in
May 1985 and filed involuntary bankruptcy.  EPA has been sampling area wells and
maintaining previously installed carbon filtration units.  In addition, EPA installed
two new carbon filtration units on contaminated private wells; installed an air
stripping system on a highly contaminated well; and drilled a new well attempting to
locate a clean water supply.  The primary contaminates of concern affecting the ground
water are VOCs including PCE and TCE.

   The selected remedial action for this site includes:  extension of the existing
Catskill Water District pipeline from Sandy Plains Road or from Rudolph Weir Road to the
affected and potentially affected area.  The exact route of the pipeline will be
determined during design.  The estimated capital cost for this remedial action ranges
from $2,270,000 to $2,380,000 with annual O&M of $100,000 to $110,000, pending the
pipeline route decision.

-------
                   UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

        flfli* . „                       REGION H
  DATE:  liiSC S i J8J7


SUBJECT:   Record of Decision for the American  Thermostat Site
                                      ^,, . ,.'~>
       /Stephen D. Luftig,      . ^^_ ^      .
      •^/[Emergency and Remedial Response DJIvision
      V
    TO:   Christopher J. Daggett          "
         Regional Administrator


         Attached, pleased find the American  Thermostat site Record of
         Decision (ROD) prepared by my staff.

         The American Thermostat Corporation  site  is located in  the
         Catskill Creek Valley in South Cairo, Greene County,  New
         York.  Water in the area is supplied by private wells;  there
         is no nearby public water supply.

         American Thermostat Corporation commenced operations  at the
         Site in 1954.  The operations consisted of the manufacturing
         of thermostats for small appliances.  In  1981, the New  York
         State Department of Environmental  Conservation (NYSDEC)
         discovered employees of AT improperly disposing of chemicals
         at the Site.  Preliminary investigations  by NYSDEC and  the
         New York State Department of Law in  1981  revealed that  for a
         number of years AT employees had been pouring  waste organic
         solvents down drains connected to  the septic system and that
         waste solvents and sludges were dumped on the  parking lot.
         Sample analysis of the discharge from two facility outfalls
         by the New York State Department of  Health ("NYSDOH"),  detected
         elevated levels of tetrachloroethylene ("PCE") and trichloroethylene
         ("TCE").  Subsequent potable water sampling of homes  within a
         quarter of a mile from the site, conducted in  1981 by NYSDOH,
         indicated the presence of PCE and  TCE in  five  residential
         wells (Rath, Rivenburg, Lais, Nesensohn,  and Briggs)  and at
         the AT facility.  The concentrations of PCE ranged from 130
         ppb to 47,000 ppb; TCE concentrations were much lower.  The
         highest concentration of PCE was detected at the Rath's well,
         adjacent to the AT facility.  The  affected residents  were
         advised by NYSDOH not to utilize their well water for drinking
         or cooking purposes.

         On February 17, 1983, AT signed an Interim Consent Order with
         the State of New York which stated that AT must provide for
         the installation, monitoring, and  maintenance  of carbon
         filtration systems, and must also  supply  bottled water  for
         cooking and drinking purposes to the five affected homes.
         Other provisions called for the monitoring of  two groups of
         private wells in order to ensure prompt identification  of
         additional potable water contamination, and for a limited
         remedial investigation to determine  the nature and extent of
         surface and subsurface contamination.
  REQIOM II FORM 132O-1 »/M>

-------
                             -2-
AT provided bottled drinking water and installed carbon
filters at its facility and at three of the affected homes.
The Rath's residence was connected to AT's own treated water
supply because the high concentration of PCE and TCE in the
Rath's well would have required frequent recharge of the
carbon filter to prevent breakthrough.  One affected resident
whose water was contaminated declined a carbon filter.

On May 7, 1985, AT ceased operations, and a bankruptcy petition
was subsequently filed against the company.  As a result, AT
ceased providing maintenance of the carbon filtration systems
to ensure that breakthrough did not occur, and stopped supplying
bottled water to the five affected homes.  In June 1985, EPA
sampled the water at homes in the vicinity of the Site to
determine potable water quality and to monitor carbon treatment
effectiveness for those homes with filters.  PCE and TCE
were also detected at another residential well (Cornell).

In response to a request from NYSDEC, a removal action to
maintain the carbon filters installed by AT, to sample other
potable wells near the site and, where necessary, to provide
homes with bottled water and carbon filters, was authorized
by EPA in August 1985.  EPA performed the sampling, recharged
the existing carbon filters at three residences, and installed
a filter at the Cornell residence.

In April 1986, NYSDEC requested that EPA extend the removal
action to provide a reliable source of safe drinking water
for the Raths and the Rivenburgs.  Both wells had high concen-
trations of PCE.  In September 1986, EPA authorized the
drilling of a new well for the Rivenburgs and the installation
of an airlift pump, organic adsorption unit, and carbon
filters for the Rath's well.  The treatment system was installed
on the Rath's well; the new well that was drilled for the
Rivenburgs, however, was found to be contaminated with PCE
and TCE.

in February 1987, an additional contaminated well was discovered,
EPA authorized funding for the installation of a carbon
filter at the affected residence (Franks) and for continued
operation of the Rath's water treatment system.

-------
                                 -3-



   This ROD reflects  the  recommendations  of  the Emergency and
   Remedial Response  Division  for an alternate water supply for
   the residents affected or threatened by PCE- and  TCE- contaminated
   groundwater  from the AT site.   Upon completion of a source
   control remedial investigation/feasibility study  (RI/FS)  to
   further define  the nature and  extent of contamination at the
   site, a separate ROD will be prepared.

   Our recommendations were developed based  upon the Administrative
   Record for this site,  which includes a  focused feasibility
   study (FFS)  prepared by Ebasco Services,  Inc.

   The recommended remedy to provide an alternate water supply
   involves the extension of the  Catskill  water supply pipeline
   to the affected and potentially affected  area.  Under this
   remedy, service connections will be provided to all residents
   who currently have contaminated wells  and those wells that
   are threatened.

   The capital  and present worth  costs for the recommended remedy
   range from 2.27-2.38 million and 3.21-3.47 million, respectively.

   The State of New York  has been consulted, and agrees that the
   recommended  alternative is  the most appropriate means of
   providing an alternate water supply for the residents surrounding
   the site.

   The recommended actions, I  believe, are consistent with the
   goals and objectives of the Comprehensive Environmental
   Response, Compensation, and Liability  Act of 1980,  as amended
   by the Superfund Amendments and Reauthorization Act of 1986
   (CERCLA), and the  National  Contingency Plan, to provide
   adequate protection of human health and the environment.
   This remedy  satisfies  all applicable or relevant  and appropriate
   requirements for this  operable unit.

   Notice to the potentially responsible  parties,  in accordance
   with the special notice procedures outlined in $122(e)  of
   CERCLA, was  sent on December 4, 1987 with the release of  the
   FFS.

   The costs of construction of  the recommended remedy will  be
   cost-shared  as  follows: 90% EPA and 10%  NYSDEC.

   Should you have any questions  concerning  the ROD, do not
   hesitate to  contact me.

   Attachment
.-.v, -rv W-^v^^*#.^S!^^^^^

-------
                      Record of Decision
                Remedial Alternative Selection


            DECLARATION FOR THE RECORD OF DECISION


SITE NAME AND LOCATION

American Thermostat Corporation, South Cairo, Greene County,
New York.

STATEMENT OF PURPOSE AND BASIS

This decision document represents the selected remedial action
for providing an alternate water supply for the residents
affected or threatened by the tetrachloroethylene and trichloro-
ethylene-contaminated groundwater around the American Thermostat
Corporation site.  The selected remedial alternative was
developed in accordance with the Comprehensive Environmental
Response, Compensation and Liability Act of 1980 (CERCLA), 42
USC $9601, et sea,., as amended by the Superfund Amendments
and ReauthorTzation Act of 1986 (SARA), and to the extent
practicable, the National Oil and Hazardous Substance Pollution
Contingency Plan (NCP), 40 CFR Part 300.

This decision is based on the administrative record for the
American Thermostat Corporation site.  The attached index
identifies the items that comprise the administrative record,
upon which the selection of the remedial action is based.  Among
the documents relied upon are:

   -Focused Feasibility Study, Ebasco Services, Inc, September 1987,
   -Attached Summary of Remedial Alternative Selection for the
       American Thermostat Site.
   -Attached Responsiveness Summary, December 1987.

A copy of the administrative record is located at the following
locations:

         Greene County Court House
         County Clerk's Office
         446 Main Street
         Catskill, New York  12414


         U.S. Environmental Protection Agency
         Emergency and Remedial Response Division
         26 Federal Plaza
         New York, New York  10278

-------
                             -2-
DESCRIPTION OF SELECTED REMEDY

The remedial alternative presented  in this document  is  the
first operable unit of a permanent  remedy for  the American
Thermostat Corporation site.  It will provide  a permanent and
reliable solution for the prevention .of health risks  to area
residents associated with exposure  to contaminated groundwater.
The alternative selected involves extension of the Catskill
water supply pipeline to the affected and potentially affected
area.  The specific waterline route will be determined  during
the design phase.  Service connections will be provided to
all residents currently utilizing contaminated or potentially
threatened wells.

The contaminant plume and source or sources of contamination
will be addressed in a subsequent remedial investigation/
feasibility study and Record of Decision.

DECLARATIONS

Consistent with CERCLA as amended, and the NCP, I have  determined
that the selected remedy is protective of human health  and
the environment, attains federal and state requirements that
are applicable or relevant and appropriate, and is cost-effective,

The selected remedy represents a permanent solution for a
portion of the problem posed by the site — namely, the threat
posed to area residents as a result of exposure to contaminated
groundwater.  The selected remedy does not satisfy the  statu-
tory preference for remedial actions in which treatment  which
permanently and significantly reduces the volume, toxicity or
mobility of the hazardous substances is a principal element.
The reason for this is that such treatment options were  not
found to be practicable or appropriate for this operable
unit.  Such options, including possible methods of treating
the contaminated groundwater, will be considered in the  next
operable unit.

The State of New York has been consulted and agrees with the
selected remedy, as is documented in the attached letter of
concurrence.

I have also determined that the selected remedial action for
the American Thermostat Corporation site is appropriate  when
balanced against the availability of Superfund monies for use
at other sites.
         7. iM8
     Datei                       Chrfstophet J. Xfcggett
                                 Regional Administrator
                  :;'ft«*V-»'«--;iI----'R.--'^>:'.~*-'J''--' :>^i*A";"---* •': '• •'^-•^X^ i^i^V^^

-------
  SUMMARY OF REMEDIAL ALTERNATIVE SELECTION
           AMERICAN THERMOSTAT SITE
                   NEW YORK
United States Environmental Protection Agency
                   Region  2
                   New York


-------
                      TABLE OF CONTENTS
                                                         Page
Site Location and Description	  1
Site History	  2
Current Site Status	  3
Enforcement History	  4
Community Relations	  5
Preliminary Public Health Risk Assessment	  6
Alternatives Evaluation	  9
Selected Remedy	 49
Schedule	 54

     ATTACHMENTS

A - Administrative Record Index
B - NYSDEC Letter of Concurrence
C - Responsiveness Summary

-------
              American Thermostat Corporation Site
                     South Cairo, New- York


 SITE  LOCATION AND DESCRIPTION

 The American Thermostat Corporation (AT)  site is located in
 South Cairo, Greene County,  approximately thirty miles south
 of Albany,  New York.  The site location is shown in Figure 1.
 The property, about eight acres, is bounded on the northeast
 and southwest by routes 23B  and 23, respectively.  Private
 homes are near the site on its eastern and western boundaries.
 The site is not fenced.  The property itself is relatively
 flat, but the surrounding land drops off  steeply to Catskill
 Creek and two small tributaries east and  west of the site.

 A site sketch is shown in Figure 2.  The  plant entrance is
 located on Route 23B.  The former plant operations were
 carried out in one existing  large building which is surrounded
 by a  large parking area, some of which is paved.  A small
 pump  house which contains the company well is located at the
 rear  of the property near Route 23.  A septic tank drainage
 field on the western side of the building was disconnected in
 1983  and replaced by a 4,500 gallon per day capacity septic
 tank  and drainage field east of the building.  State Pol-
 lutant Discharge Elimination System (SPDCS) permits were
 issued by the New York State Department of Envirnmental
 Conservation (NYSDEC) for the sewage discharge (discharge
 point 003)  and two non-contact cooling water discharges
 (discharge points 001 and 002) as shown in Figure 2.

 Regionally, the bedrock within Greene County consists of
 interbedded shales and sandstones of Devonian age known as
 the Catskill Formation (Amter, 1981).  The Catskill Formation
 is made up of four distinct  bedrock groups.  From oldest to
 youngest, these groups are the Hamilton,  Genessee, Sonyea and
 West  Falls.  The AT facility lies within  the Hamilton Group
 which is further subdivided  into the Plattekill Formation
 which underlies the site.

 The Plattekill Formation consists of sandstones, siltstones
 and shales.  These sediments have been uplifted and folded
 resulting in a bedding plane dip to the west.  This bedrock
 structure controls the topography of the  area which in turn
 influences the surface and subsurface hydrology (Amter, 1981).
^^^

-------
MAP If A PORTION Of THE U.S.at. LEEDS. NT OUADAANOlE(7.t MINUTE ••Wti. ttl*.>HOT6nEVI8ED 1MO».~ CWTOUIl'INTERVAL'10V
                                                                               	8CM.E r «tOOO'
                                                                                           FMJUME 1
                                                                                        LOCATION MAP
                                                                                  AMERICAN THERMOSTAT SITE,
                                                                                       SOUTH  CAIRO. NY

-------
to wmnt cftctx
THWUTAKt B
                                                                   OIWHAIKM (Mil
                                                                                                      noune z
                                                                                                       AMNA
                                                                                             AMtmCAII TNIMMMTAT HI*.
                                                                                                  tOUTN CAINO, NV

-------
                             -2-


Unconsolidated glacial deposits overlie bedrock throughout
most of the region.  During the Pleistocene epoch a  layer of
till was deposited over upland mountainous areas, and thick,
well-sorted, and stratified drift consisting of gravel, silt
and clay was deposited by meltwater in lower valley  areas
(Berdan, 1954).  The surficial till soils at the site exhibit
significant variations in permeability.  Reportedly, the soil
is only about three feet thick overlying a significantly
permeable and fractured upper bedrock surface (Amter, 1981).
Alluvium is found in stream bed areas.

Groundwater is found almost exclusively in bedrock fracture
zones and joints throughout upland areas where the AT facility
is located.  The Plattekill Formation is reported to have
very low primary permeability, but due to the presence of
numerous fractures and joints, its secondary permeability is
much higher.  Yields of 20 gallons per minute (gpra)  are
documented for wells completed in sandstone; and well yields
of 14-15 gpm are documented for the more tightly cemented
siltstones and shales (Berdan, 1954).

Regionally, depth to groundwater ranges from less than one
foot in swampy areas to almost 300 feet, with the average
depth about 30 to 40 feet (Berdan, 1954).  Immediately west
of the facility is a small valley which includes Tributary
"B", a tributary to Catskill Creek.  East of the facility is
Tributary "A" which also flows into Catskill Creek.  Reportedly,
perched groundwater is found in this localized valley area     ..'
(Amter, 1981).  However, as mentioned, bedrock bedding planes
dip in a westerly direction.  Accordingly, regional  groundwater
appears to flow at depth towards the west.

SITE HISTORY

The original building was built in 1954 by AT for the assembly
of thermostats for small appliances.  As operations  expanded,
additions were made to the original building.  From  approximately
the mid-1950s through at least 1981, waste trichloroethylene
(TCE) and tetrachloroethylene (PCE) sludges were poured down
drains inside the building and were dumped outside on the
plant grounds.  The drains were connected to the abandoned
septic system.

In March 1981, two AT employees were observed dumping solvents
on plant property.  This triggered investigations into the
company's waste handling practices by NYSDEC and the New York
State Attorney General's office.

-------
                             -3-
During April and May 1981, water samples were collected from
several privately-owned wells in the vicinity of the AT site
by the New York State Department of Health (NYSDOH) and NYSDEC.

Figure 3 shows the locations of residential wells surrounding
the AT site.  Analysis of water samples taken by NYSDEC and
NYSDOH indicated the presence of TCE and PCE.  Five of the
sampled wells, those belonging to Rath, Lais, Rivenburg,
Briggs, and J. Schmidt (formerly Nesensohn), indicated concen-
tration levels of PCE in excess of the guideline of 0.05 ppm
(mg/1) for volatile organic chemicals established by the
Commissioner of NYSDOH.  TCE was detected in four of the five
wells, with two samples indicating a concentration in excess
of the State guideline.  The affected residents were advised
by NYSDOH not to utilize their well water for cooking or
drinking purposes.  In November 1981, the State of New York
filed suit against AT and Amro Realty Corporation (Amro), the
owner of the property.  Suits were also filed by several of
the plant's neighbors in late 1981.

As a result of the high level of PCE i'n several nearby wells,
AT began supplying bottled water to local residents in April
1982.  By November 1982, AT had installed carbon filters on
its own well and the affected residential wells.  The nearest
neighbor, the Raths, were connected to AT's well water supply
system.  In December 1982, the site was added to the National
Priorities List, established pursuant to Section 105 of CERCLA
42 U.S.C. §9605.

In February 1983, New York State entered into an interim
Consent Order with AT and Amro in which the companies agreed
to investigate and clean up the site and its surroundings,
supply bottled water for cooking and drinking purposes, and
install, monitor, and maintain carbon filter systems for the
five affected homes listed above.  The Order also stipulated
that two groups of bordering private wells had to be monitored
to determine whether any contamination had spread beyond the
originally affected area.  AT and Amro did not fully comply
with the Consent Order and did not remedy the contamination at
the site, but only temporarily provided the affected residences
with safe drinking water.

In June 1983, a new 4,500-gallon septic system was installed
at the AT site, and the cooling water discharges were separated.
New SPDES permits were issued for three separate discharges,
the sewage system effluent and two non-contact cooling water
discharges.   In September 1983, AT provided carbon filtration
for these discharges to lower the levels of PCE.

-------
                                                                                     Nlfi-
                                                             O OACUNIT

                                                                AIRLIFT STRIP?ING
                                                                SYSTEM


                                                              JtlYTORttlDEMTi:

                                                               MVUTIN
                                                               MUlLtfM
                                                               OHEYtTOMI MOTH.

                                                               MALLIA (FOmUflkV BAHTMANI
                                                               MIVINtUHQ

                                                                          KHLVLKMMIOTI

                                                               •tllMM»

                                                               XlOHMIOT fRMWIIILV Nf SCMSOHN)
                                                                             fAMTMAMI



                                                               ^AM(gOMIIM.V MRMVI
SCOTCH ROCK MOAO
                                                                       LOCATION 0^
                                                                     SURFACE WATf
                                                                 SCALI «*• tea*
        •OURCC:NUt CORP. RIMEWAL ACTION
              MASTER PLAN KCEMMR.1M*
SURROUNDtNQ HE8IDENT1AL WELL
  LOCATIONS-SOUTH CAIRO, N.Y.

-------
                             -4-


In 1983, EPA's contractor prepared a Remedial Action Master
Plan for the site.

AT ceased operations in May 1985.  In November 1985, several
of AT's creditors filed an involuntary bankruptcy petition
against the Corporation pursuant to Chapter 7 of the Bankruptcy
Code.  The bankruptcy court subsequently entered an order for
relief against AT.

Since June 1985, EPA has been sampling wells in the area and
has been maintaining the previously installed carbon filtration
units.  In addition, EPA installed two new carbon filtration
units on contaminated private wells, and installed an air
stripping system on a highly contaminated well, and drilled a
new well in an attempt to locate a clean water supply.

CURRENT SITE STATUS

Sampling was initially conducted at the AT site in May 1981
by NYSDOH and NYSDEC.  As summarized in Table 1, the results
of groundwater analyses revealed the presence of certain
volatile halogenated organic compounds (VHO) (TCE and PCE) in
some samples from nearby residential wells.  Concentrations
of PCC exceeded 1 part per million (ppm) in a number of
groundwater samples with a maximum value of 100 ppm observed
in one well water sample.  Concentrations of TCE were signifi-
cantly lower.

Only one soil sample was collected from the dumping area (see
Figure 1) at the southern end of the AT site in March 1981.
This sample contained measureable levels of both PCE (3400
ppm) and TCE (0.5 ppm), and traces of 1,1,1-trichloroethane
(0.02 ppra).

VHOs were also detected  in surface water samples collected
during 1981 and 1982 in  tributaries near the site.  The
principal VHO compounds detected were again PCE and TCE.  In
summary, from the existing data  it appears that the contami-
nation at the AT site  is primarily due to VHOs, with PCE and
TCE  being the principal  contaminants.  The source of these
compounds is spent  degreasing solvents and sludges previously
disposed of on on-site soils, in the on-site septic system(s)
and/or  released to  surface water.  The source, nature, and
extent of the contamination at and around the  site will be
further  investigated  in  the upcoming RI/FS.

-------
TABLE 1
AMERICAN THERMOSTAT STTE
Sample
Location
Berensheim
Briggs
Cornell
Goldstein
Lais
Nesensohn
Rath
Rivenburg
• (before
filter)
• (after
filter)
• (storage
tank)
• (spiked
storage
tank)
Ed Schmidt
Rath
Schmidt
Rivenburg
Sampling
Date
12/28/81
6/19/81
1/25/82
6/24/82
12/28/81
10/12/83
5/8/81
6/19/81
1/25/82
5/19/81
6/19/81
6/11/82
4/6/81
6/19/81
1/25/82
5/19/81
6/19/81
11/17/81
11/17/81
1/25/82
1/25/82
10/12/83
12/11/85
12/11/85
12/11/85
Trichloroethylene
(DDIlri
-
0.002
0.003
0.005
.
0.014
0.020
0.020
0.013
0.018
0.011
0.350
0.120
0.140
0.110
0.230
0.230
.-
<0.001
cO.OOl
0.001
Tetrachloroethylene
( opm)
0.002
0.220
0.430
0.220
0.003
0.001
1.6
1.5
!.•?
1.2
1.6
0.95
47.0
87.0
100.0
3.5
5.8
3.0
0.004
9.0
14.0
0.007
< 0.001
< 0.001
0.004

-------
TABLE 1    (Confd)
AMERICAN THERMOSTAT
Sample
Location
Cornell
Lais
Mallia
Chickocki
Greystone
Motel
Rath
Mariani
Frank
Goldstein
Wilczak
Sampling
Date
12/11/85
12/11/85
9/4/85
9/4/85
9/4/85
9/4/85
9/4/85
9/4/85
9/4/85
9/4/85
Rivenburg 9/10/85
(basement tap)
Schmidt
.(garage tap)
Cornell
(kitchen tap)
Lais
(kitchen tap)
Lais
• (before)
• (between)
• (after)
Hesensohn
• (before)
• (between)
• (after)
9/10/85
9/10/85
9/10/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
Trichloroethylene
( ppnO
<0.001
<0.001
<0.001
<0.001
<0.001
3.5
<0.001
<0.001
<0.001
<0.001
0.28
<0.001
<0.001
<0.001
0.028
ND
HD
0.033
HD
ND
SITE
*
Tetrachloroethylene
fopm)
< 0.001
< 0.001
0.002
< 0.001
< 0.001
98.0
0.005
< 0.001
< 0.001
0.005
14.6
0.011
0.003
< 0.001
2.1
ND
HD
3.2
0.001
HD

-------
                        TABLE 1    (Confd)

         RESIDENTIAL WELLS - ANALYTICAL RESULTS


                      AMERICAN THERMOSTAT SITE
Sample
Location

Cornell
(no filter)

Briggs
(no filter)

Rivenburg
 * (before)
 • (between)
 " (after)

Ed Schmidt

John Schmidt

Priputen
Sampling    Trichloroethylene
  Pate      	(ppm)	

 6/12/85           0.094
 6/12/85           0.004
              Tetrachloroethylene
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
6/12/85
0.19
0.28
0.016
ND
ND
ND
                      0.54


                      0.44




                      9.8
                     10.2
                      0.13

                      0.0071

                     ND

                     ND
American
Thermostat Plant
 •  (before)    6/12/85
 •  (between)   6/12/85
 •  (after)     6/12/85
 •  (Rath)      6/12/85
Berensheim
 6/12/85
ND
ND
ND
ND

ND
 0.320
 0.003
 0.014
ND

ND
 Note:    Dash (-)  indicates not  analyzed for
         •ND" indicates  not detected

 Source:  Remedial  Action Master  Plan, NUS Corp., December 1983,
         and EPA,  NYSDEC, NYSDOH analytical data from 1981-1987,

-------
                             -5-
ENFORCEMENT HISTORY

Four potentially responsible parties ("PRPs") have been
identified in connection with the AT site: Amro; AT; Mr.
Harry Moskowitz and Mr. David Moskowitz.  Amro is the owner
of the property on which the AT facility is located.  AT was
the company which operated the manufacturing facility at the
site.  Harry Moskowitz was the president of the now defunct
AT; he is also the president of Amro.  David Moskowitz is the
president of AT, and was formerly the vice president and
executive vice president of AT.

EPA filed a proof of claim on December 12, 1986 in the bank-
ruptcy proceeding of AT, seeking recovery of costs incurred
at the site.  In addition, on October 30, 1987, the United
States commenced a civil action against Amro, Harry Moskowitz
and David Moskowitz pursuant to Section 107 of CERCLA for
recovery of EPA's costs at the site.  EPA has also sent
several notice letters to the PRPs offering them the oppor-
tunity to agree to conduct or finance various response actions <
at the site.  To date, none of the PRPs have offered to
undertake or finance such activities.  The most recent notice
letter was sent to the PRPs on December 4, 1987.  This letter
gave the PRPs sixty days to make a good faith offer to conduct
or finance the remedial action selected herein.

COMMUNITY RELATIONS

On December 3, 1987, EPA published a notice and brief analysis
of the Focused Feasibility Study (FFS) and Proposed Remedial
Action Plan (PRAP) prepared with respect to the AT site, and
made these documents available to the public.  EPA informed
the public (including the Potentially Responsible Parties (PRPs))
of their opportunity to submit comments on the aforementioned
documents on or before December 24, 1987.  In addition, on
December 8, 1987, EPA held a public meeting near the site to
discuss the PFS and PRAP.  A responsiveness summary, containing
EPA's response to the significant comments received during
the public comment period, is attached hereto.

-------
                             -6-
PRELIMINARY PUBLIC HEALTH RISK ASSESSMENT

On the basis of existing site information and analytical re-
sults, a preliminary public health risk assessment was per-
formed for the site.  The objective of this assessment was
to characterize health and environmental risks that would
prevail in the absence of further remedial action.  The
methodology supporting this preliminary screening is described
below.

PCE and TCE were chosen for evaluation, as these chemicals
represent the principal contaminants detected in residential
wells.  Results of the most recent (1986-1987) sampling
investigations indicate concentrations of PCE ranging from
0.001 ppm to 131 ppm.  Concentrations of TCE ranged from
0.001 to 2.0 ppm.  Both compounds are classified by EPA as
being probable human carcinogens.  TCE has proven carcino-
genic in several strains of mice by the inhalation and oral
routes and is considered weakly mutagenic.  PCE is carcino-
genic in mice by the inhalation route.

Because the purpose of this operable unit is to address the
need for provision of an alternative water supply to the
affected residents, this assessment addressed only those
pathways relating to the existing groundwater contamination.
These pathways include ingestion of groundwater, direct contact
with groundwater via washing and/or bathing, and inhalation of
contaminants volatilized during showers.  Table 2 summarizes
the federal Applicable or Relevant and Appropriate Requirements
(ARARs).

As discussed above, the results of recent off-site groundwater
sampling programs indicate the continued presence of elevated
levels of PCE and TCE in residential well water samples.  The
measured concentrations of these contaminants may be compared to
the ARARs listed in Table 3.  As indicated in Table 3, EPA has
recently promulgated maximum contaminant levels (MCLs) for
safe drinking water for TCE (0.005 ppm) as well as several
other VHOs.

-------
                          Table 2

Federal Applicable or Relevant and Appropriate Requirements

   1) Safe Drinking Water Act, National Primary Drinking Water
      Regulations, Maximum Contaminant Levels (40 CFR 141.11-
      141.16).

   2) Other criteria/ advisories and guidance such as:

      0  Maximum Contaminant Level Goals
      0  USEPA Drinking Water Health Advisories
      0  USEPA Health Effects Assessment
      0  Cancer Assessment Group National Academy of Science
         Guidance

   3) Clean Water Act, Ambient Water Quality
      Criteria (45 PR 798318-79379, November 28, 1980).

   4) USEPA Groundwater Protection Strategy

-------
                                TABLE 3
                     CHEMICAL SPECIFIC - EPA ARARs
    PARAMETER

TETRACHLOROETHYLENE
TRICHLOROETHYLENE
1,1-DICHLOROETHYLENE
1,1,1-TRICHLOROETHANE
SDWA MAXIMUM FRESHWATER
CONTAMINANT LEVEL QUALITY CRITERIA
-(2)
0.005
0.007
0.200
ACUTE CHRONIC
5.2 0.8
45 21
11
18 - . - .
(3)
SDHA /MCL
GOAL
0<
0
0.
0.
4)

007
200
requirements
NOTES:                      ••-_. "  .     -~
d) Federal  applicable, relevant, and
(2) All  concentrations in ppm.   Dash  indic&tes^no.t  established or determined
(3) SDWA/MCL is the Safe Drinking Water Act Maximum Contaminant Level
   ..."~~~-   '-• '• . -':"""'   •*--"-         •  =•--•        ''• -=~:~'--n j^^ff:!: '.'  ..,.  -,;:-/•.:'
(4> Proposed^as of October, 1986"'           j^l    >^ -  -^\t-

-------
                           -7-


MCLs are enforceable standards established pursuant to the
Safe Drinking Water Act.  MCLs are considered to be health
protective.  For drinking water contaminants, the target
reference risk range associated with these standards  is 10~4
to 10~6.

Using the measured ranges of TCE and PCE reported above, in
conjunction with carcinogenic potency factors developed for
these constituents (USEPA, 1986), one can derive carcinogenic
risk estimates for the receptors in question.  Carcinogenic
potency factors represent the upper 95% confidence limit of
the probability of adverse response per unit intake of a
chemical over a lifetime.  Using these values, and assuming
a daily water ingestion of two liters over a 70 year  period,
the resultant risk estimates associated with TCE and  PCE well
contamination are as follows:

                             Concentration       Carcinogenic
  Constituent                    Range           Risk Estimate

Tetrachloroethylene          0.001 ppm (min.)     1.5 x 10"^
                           131     ppm (max.)     1.9 x 10'1
                                                       . t
Trichloroethylene            0.001 ppm (min.')     3.1 x 10"7
                             2.0   ppm (max.)     6.3 x 10~4

As illustrated above, the estimated risks associated  with in-
gestion of groundwater, particularly PCE-contaminated groundwater,
at selected residential wells (e.g., Rath and Rivenburg, where
maximum PCE and TCE concentrations were measured) are signifi-
cantly greater than the target reference risk range referred
to previously.

Concentrations of TCE and PCE in drinking water which correspond
to a 10~5 risk are 0.026 ppm and 0.007 ppm,  respectively.  As
indicated in Table 1, the concentrations of  these contaminants
detected in residential wells near the site  far exceed
concentrations deemed health protective.

In addition. New York State has established  water quality
standards and guidance values for Class GA  (used for  drinking
water) groundwaters.  Relevant values are presented in Table
4.  For TCE, a water quality standard of 0.01 ppm has been
established.  For PCE and TCE guidance values for Class GA
waters  have been established at 0.0007 ppm and 0.003  ppm,
respectively.  Clearly, the difference between the concentrations
of these contaminants measured  in residential wells near the
site and their associated health protective  standards and
goals  is significant.

-------
                           TABLE 4
            NEW YORK STATE WATER QUALITY STANDARDS
                     AND GUIDANCE VALUES
                  FOR CLASS GA GROUNDWATERS
     PARAMETERS



TETRACHLOROETHYLENE

TRICHLOROETHYLENE

TRANS-1,2-DICHLOROETHENE
STANDARD
 (ppm)
 0.01
GUIDANCE VALUE
    (ppm)

    0.0007

    0.003

    0.05
Source:  Ambient Water Quality'Standards and Guidance Values,
         New York State Department of Environmental Conservation,
         Technical and Operational Guidance Report 85-W-38, July
         1985.

-------
                             -8-
In addition to groundwater ingestion, the potential exists  for
residents to be exposed to contaminants via washing or bathing.
The extent-of this exposure would depend on the period of time
spent washing and bathing, the  fraction of contaminants absorbed
through the skin, and the surface area of the IndividuaK s)
exposed.

Qualitatively, evidence suggests that these two exposure path-
ways (inhalation and dermal absorption) present less health
risk of toxicity and/or carcinogenicity than ingestion.

As a result of the risk to public health from exposure to
contaminated groundwater from the AT site, remedial alterna-
tives were evaluated to address the problem.

-------
                              -9-


ALTERNATIVES EVALUATION

FPA's contractor conducted a  Focused Feasibility Study  (FFS)
aimed at identifying and evaluatinq various alternatives for
providing  a safe alternate water supoly to the affected and
potentially affected residents near the AT site.  During the
FFS, alternatives were identified screened and analyzed in
detail, as required by the NCP.  The effectiveness, implementa-
bility and cost of each of the water supoly alternatives were
evaluated and summarized in the FFS and Proposed Remedial
Action Plan (PRAP) orepar^d by EPA.

The FFS was developed and preoared based on the limited existing
information (e.g., monitoring of 28 orivate wells) without the
RI which will identify the contamination sources and the extent
of the groundwater contamination migration plume(s).  In addition,
the unique geohydrological configuration around the site (e.g.,
groundwater exists in the irregular channels and joints of the
fractured bedrock) contributed to the difficulties of predict-
ing the site-specific contamination conditions.

A preliminary review of. the existing data and information indi-
cate that approximately 100 oersons residing in the nearest 28
houses around the site are currently affected.  This number
represents the population which is supplied by private wells
located within 1/2 mile downgradient and 1/4 mile upgradient
from the AT site as shown in  Figure 3.  Based on this informa-
tion, it appears that the groundwater contamination has migrated
at least this far during the  last  20 years.

It is estimated that the groundwater remediation at this site
would take 20 years or more to complete.  Because the extent of
contaminant migration has not been adequately determined at this
time, it is anticipated that  the contamination would travel in
both directions and with the  same migration soeed of the last
10 years.  It is estimated that within the next 20 years the
contaminant plume(s) may reach one mile downgradient and 1/2
mile upgradient from the AT site.

The existing private well monitoring data indicate that no
contaminated well around the  site was located outside the area
between Catskill Creek and Route 23.  It is also assumed at
this point that the Catskill  Creek and Route  23 act as bound-
ariesfor the migration of contamination on the north and south
sides of this site.  Based on the above analysis,.the affected
and potentially affected areas are within the boundaries of
one mile downgradient,  1/2/ mile upgradient, Catskill Creed and
Route  23  (see Figure 4).  Aporoximately 80 homes are located
within those boundaries.

-------
    (80 HOUSES
    260 PEOPLE)
            FIGURE 4

PROPOSED WATER SUPPLY SERVH*

-------
                              -10-
Within the water suooly service  area,  it  is  estimated  that
approximately  250 oersons residing  in  approximately 80 houses
would he ultimately affected and need  to  be  orovided with an
alternate water suooly.

All but seven of the alternatives which underwent  initial
screening during the FFS were eliminated.  Table  2 lists the
water supply alternatives which were evaluated  during  the
initial screening phase, and summarizes the  reasons why
certain alternate water suoply options were  rejected.

The alternatives which were retained for  a detailed evaluation
are as follows:
         ALTERNATIVE  1
         ALTERNATIVE  3Q

         ALTERNATIVE  4A-1
         ALTERNATIVE  4A-2
         ALTERNATIVE  4A-3
         ALTERNATIVE  4C
         ALTERNATIVE  4D
NO ACTION
TANKER TRUCK AND ELEVATED
STORAGE TANK
PIPELINE FROM LEEDS
PIPELINE FROM SANDY PLAINS ROAD
PIPELINE FROM RUDOLPH WEIR ROAD
NEW WELL FIELD  -
WATER SUPPLY FROM TRAILER PARK
WELLS
DESCRIPTION OF ALTERNATIVES
                                                 • - ' •
With the exception of Alternative  1  (No  Action), each water
supoly alternative was evaluated on  the  assumption that  it
would need to meet a typical domestic demand for a rural  area
of 75 gallons oer capita oer day  (gpcd)  (aooroximately  15
gallons per minute  (gpm) for  250 persons).  The provision of
such an alternate water supoly system for  the potentially
affected residents is consistent with Section  121 of the
CERCLA, which requires that remedial actions assure protection
of human health, attain ARARs, and be cost-effective.   This
operable unit does, not satisfy the statutory preference  for
treatment.  This statutory preference will be addressed"in
the second operable-unit.
                            ^.-,^_-..,-.,:.i.,r..,r:.,;,,^,^.;^^^

-------
                           TABLE 5
             .SUMMARY OF ALTERNATE WATER SUPPLY
            OPTIONS EVALUATED IN INITIAL SCREENING
Water Supply Alternative
Status
1. No Action

2. Point-of-Use Treatment

   2A.Install Carbon Filters
      on 72 Houses
       O&M of systems

   2B. Centralized Well Water
       Treatment System

3. Point-of-use Water Supply

   3A-1.Tanker Truck Delivery
   3A-2.Bottled Water Delivery
   3B.Tanker Truck and
      Storage Tank

   3C.Collection of Rainwater

4. Alternate Water Sources

   4A.Catskill Water Supply
      System

      4A-1.Pipeline from Leeds
      4A-2.Pipeline from Sandy
           Plains Road

      4A-3-Pipeline from
           Rudolph Weir Road

   4B.New Surface Water
      Supply (Catskill Creek)
   4C.New Well Field

   4D.Water Supply from
      Trailer Park Wells
Reason for Rejection
 Retained



 Rejected



 Rejected




 Rejected




 Rejected




 Retained


 Rejected
 Retained
 Retained
 Retained


 Rejected




 Retained

 Retained
Fails to provide completel
safe water supply, complex
O&M

Fails to provide permanent
and long-term remedy, comp
construction
Fails to provide standard
domestic water supply,
considered temporary
solution only

Fails.to provide standard
domestic water supply,
considered temporary
solution only
Unproven, unreliable, compl
construction
Unproven, uncertain useful
life, complex O&M and
construction, major negativ<
environmental impact

-------
                             -12-


ALTERNATIVE 1 - NO ACTION

The no-action alternative includes long-term monitoring of the
28 potentially affected homes immediately surrounding the AT
site.  Water samples taken from these homes every 3 months
would be analyzed for organic contaminants.  The existing
treatment systems, including one airlift stripper and seven
carbon filter units, would be operated and maintained.  This
alternative would not, however, provide for any additional
treatment units which might be required if contamination is
detected at any of the other potentially affected residences.

No construction of major facilities or installation of large
equipment would be required for this alternative.  Only
monitoring and operation and maintenance (O&M) services would
be provided.

ALTENATIVE 3B -  WATER DELIVERY BY TANKER TRUCK, ELEVATED
STORAGE TANK, WATER LIFT PUMP AND WATER DISTRIBUTION SYSTEM

Alternative 3B is a point-of-use water supply system utilizing
an alternative water source and a water distribution system.
This water supply system would provide a standard rural water
demand by trucking water from the nearby water district.

The proposed water supply system would consist of two tractor
trucks, two 5,000 gallon tanker trailers, an elevated storage
tank, a water lift pump and a water distribution system.  The
nearest municipal water supply system is the Cats kill Mater
Supply system where the water loading station for trucking
could be located either at the Potuck Reservoir Water Treatment
Plant or at the existing transmission pipeline which crosses
Route 23B in Leeds.  Purchase of treated water from this
water supply system would require a delivery by tanker truck
along public roadways.  It is estimated that the total water
demand for the proposed service area would be approximately
0.02 million gallons per day (MGD) and that it would require four
deliveries per day at a distance of approximately twenty
miles each round trip.

An elevated hydrostorage tank with a 50,000 gallon capacity
would be required to provide adequate storage to compensate
for water demand fluctuations.  The preliminary location
of the water tower would be at the AT site, where an approxi-
mately 55 feet (ft) of static hydraulic head will be available
(based on an elevation of 255 ft at the site and an elevation
of 200 ft at the furthest residence).  The water tower would
have a 80 ft height to provide a normal working pressure
range of 35 to 60 pounds per square inch.
^

-------
                             -13-
A 6-inch diameter ductile iron pipe would be  installed  as  the
primary transmission pipe for a total length  of approximately
11,000 ft from the water tower to the proposed service  area
and along Route 23B.  As shown in Figure 5, a 4-inch diameter
branch pipe would be installed along the streets off Route
23B for the domestic water distribution system.  The total
length of the branch pipes would be approximately 7,500 ft,
providing hookups for approximately 80 homes.  The installation
of water supply pipeline would include rock excavation,
dewatering, loam excavation, restoration and  repavement.

ALTERNATIVE 4A-1 - EXTENDED CATSKILL WATER SUPPLY PIPELINE
FROM LEEDS

Alternative 4A-1 consists of purchasing water from the Catskill
Water Supply system and extending the Catskill water supply
pipeline from Leeds along Route 23B.  The current average
daily demand for Catskill is approximately 1.7 million gallons
per day (MGD).  To supply the potentialy affected residences,
it is estimated that the additional load on the system would be
0.02 MGD.                                         >

As shown in Figure 6, the proposed system would connect to
the existing pipeline by means of a water diversion station
in Leeds.  A 6-inch diameter ductile iron pipeline would be
installed along Route 23B as the primary transmission pipe
for a total length of approximately 18,000 ft.  The pipeline
would cross 400 ft pf Catskill Creek by submerged installation
near the historic bridge.

A booster pumping station would be required to provide  adequate
flow and pressure for domestic conditions.  Approximately
7,500 feet of 4-inch diameter ductile iron branch pipe  would
be installed along the streets off Route 23B  to supply  each
potentially affected residence.  Approximately 80 homes would be
connected to th«^ distribution system.            ..

ALTERNATIVE 4A-2 - EXTENDED CATSKILL WATER SUPPLY PIPELINE
FROM SANDY PLAINS ROAD                            '  ;

Alternative 4A-2 is similar to alternative 4A-lr except that
the tie-in to the existing Catskill pipeline  would" be at
Sandy Plains Road.  As shown in Figure 7, the propos**'system
would utilize a water diversion station on Sandy Plains Road
and the pipeline would cross privately-owned  t-arviF. - Trt"addition,

-------
                                                                                       s
                                                                                 LOCATION MAP
AMERICAN
THERMOSTAT
                                       SERIES. l»5». •HOTOREVISEO 10SOI. CONTOUR* INTERVAL* 10*.,



                                                                     SCALE 1* • 9AAA*
                                                              EBASCO SERVICES INCORPORATED
                                                                       FIQURE 5


                                                                  ALTERNATIVE SB -

                                                                WATER TANKER TRUCK.

-------
              r -— •"'/••
     •Ml. rNOIO*f*IMO •«•!
     COHTOMI IHIf N«M. M*
  ALTERNATIVE
CATM'IU WATEN

-------
^^^^^^T^5^
                            MIS. rnoTomnMD »ML
                            COMRXM IMTE***! ••
                         EBASCO KNVICf • IMCOXPOHATtO

                                   FKUM  7

                          ALTtHNATIVC 4A-t tlTBHOtO

                        CATtKIU WATCH »WfLT MMtlNt

-------
                             -14-
both the 60 ft. Potic and 200 ft Catskill creeks would be
crossed by .submerged installation.  A 6-inch diameter ductile
iron pipeline of approximately 13,000 ft in length, would
serve as the primary transmission pipe along Route 23B.  A
booster pumping station would also be required to supply ade-
quate flow and pressure for domestic conditions.  The same
amount of branch piping as Alternative 4A-1 would be installed
and the service area would include the same 80 homes.

ALTERNATIVE 4A-3 - EXTENDED CATSKILL WATER SUPPLY PIPELINE
FROM RUDOLPH WEIR ROAD

Alternative 4A-3 is similar to Alternatives 4A-1 and 4A-2,
except that in this option the tie-in to the existing Catskill
water supply pipeline would be near Rudolph Weir Road.  As
shown in Figure 8, the proposed system would have a diversion
station on the east side of Potic Creek.  A 6-inch diameter
ductile iron pipeline, approximately 23,000 ft long, would
serve as the primary distribution pipe.  The extension would
cross 60 ft Potic Creek by submerged installation and would
be hung from an existing 200 ft steel truss bridge over
Catskill Creek at Route 67 in -Cairo.  An identical booster
pumping station in this case would be located at the inter-
section of Route 67 and Sandy Plains Road.'  The same amount
of branch piping would be installed and the service area
would include the same 80 homes.

ALTERNATIVE 4C - NEW WELL FIELD WATER SUPPLY SYSTEM

Alternative 4C consists of developing a new well field to
provide a water supply system for the affected and potentially
affected area.  As indicated previously, the Plattekill
Formation, located throughout the upland area where the AT
site is located consists mainly of sandstones, siltstones and
shales.  Groundwater is found almost exclusively in bedrock
fracture zones and joints in this area.  Yields of 20 gpm are
documented for wells completed in sandstone (Berdan, 1954).
Some currently installed deep wells located near the stream
bed areas have operated in the range of 30 to 60 gpm.  This
is due to two important factors: the area adjacent to the
creek consists of loamy soil formed in alluvium which has
favorable recharge characteristics, and the direction of
groundwater flow is expected to be towards the creek.

-------
          room  b
  ALTtMNATIVI «A-| IITCNOCO
CAT win «rATin sumv

-------
                             -15-
Based on these factors, the preliminary location of the
proposed new well field would be approximately one mile
upgradient of the site between Catskill Creek and Route 23B
as shown in Figure 9.  Use of the Sandstone aquifer would
require new wells approximately 400 ft deep, and wells in
this aquifer would have a safe yield of approximately
40 gpm each.  The groundwater pumped from this aquifer is
expected to be good quality potable water after chlorination.

Based on the above geohydraulic information, two 400 ft deep
wells of 6-inch diameter and 400 ft deep would provide a
total of 75 gpm, sufficient for the nearby affected residents.
It is estimated that a reinforced concrete ground storage
tank with a 50,000 gallon capacity and a booster pumping
station would be required to provide the necessary pressure
and flow.  A 6-inch ductile iron force main of approximately
13,000 ft would be required from the water storage tank to
the western end of the proposed service area- along Route 23B.
A total of approximately 7,500 ft of 4-inch diameter branch
pipeline along the side streets off Route 23B would be required
for the domestic water distribution system which will have
hook-ups for approximately 80 homes.

ALTERNATIVE 4D - EXTENDED TRAILER PARK WELL WATER SUPPLY
SYSTEM

Alternative 4D is similar to Alternative 4C in that it would
use uncontaminated groundwater from a well field which is
located approximately 3/4 mile upgradient from the AT
site.  A trailer park, located off Route 23B, consists of
roughly 43 trailers and is currently expanding to accommodate
an additional 37 units.  One older well and one which was
recently drilled could provide a combined flow of approximately
70 gpm.  Since this is considerably more than the instantaneous
demand at the trailer park, it could be possible to extend this
system to supply the potentially affected area near the AT site.
An agreement would have to be negotiated with the owner of the
trailer park in order to implement this alternative.

The combined flow from the two trailer park wells would have to
be chlorinated and pumped to a reinforced concrete ground
storage tank with a 50,000 gallon capacity.  As shown in
Figure 10, the proposed distribution system would include the
installation of a 12,000 ft, 6-inch diameter ductile iron pipe-
line along Route 23B as the primary transmission pipe.  The
water storage tank and booster pumping station would provide
a buffer against fluctuations in demand while maintaining an
adequate supply of water to meet a typical rural demand of 75
gpcd.

-------
      FIGURE 9

  ALTERNATIVE 4C -
   NEW WELL FIELD
WATFR SIIPPI V UVCTCM

-------
                             -16-
Approximately 7,500 feet of 4-inch diameter ductile iron
branch pipe would be installed along the streets off Route
23B to supply each potentially affected residence.  A total
of 80 homes would be connected to the distribution system.

EVALUATION CRITERIA

The above seven alternatives were evaluated using evaluation
criteria derived from the NCP and CERCLA.  These criteria
relate directly to factors mandated by CERCLA in Section 121
and to the maximum extent practicable, EPA's Interim Guidance
on Selection of Remedy (December 24, 1986 and July 24, 1987).
The primary objective of this operable unit is to provide safe
drinking water to the current and potentially affected
residents.  This operable unit does not address a preference
for treatment.  In addition, the reduction of toxicity,
mobility or volume of waste is not addressed, but will be
addressed in the subsequent operable unit.  The criteria
which are applicable to the selection of an alternate water
supply system for the AT site are as follows:

0 EFFECTIVENESS

  - Protection of public health and welfare
  - Minimization of exposure pathways
  - Adverse environmental impacts
  - Operation and maintenance complexity

0 IMPLEMENTABILITY

  - Technical feasibility and availability
  - Constructability
  - Timeliness
  - Institutional requirements (public acceptance, permits)
  - Safety

* COST

  - Capital cost
  - Operation and maintenance cost
  - Present worth cost
  - Sensitivity analysis

EVALUATION PROCESS

This section presents a detailed evaluation of each of the
alternatives which passed the initial screening.  The de-
tailed evaluation process includes:

   0 Refinement and confirmation of the appropriateness of each
     water supply alternative with respect to site conditions;


-------
                          -17-
8 An assessment of the extent to which the alternative is
  expected to effectively prevent exposure, minimize
  threat's to and provide adequate protection of public
  health and welfare and the environment (Evaluation of
  Effectiveness);

0 Evaluation in terms of technical feasibility and
  availability, constructability, timeliness, institutional
  requirements and safety (Evaluation of Implementability);
  and

0 Detailed cost estimation including capital cost, annual
  operation and maintenance cost and distribution of cost
  over time.


-------
                             -18-
Effectiveness

Effectiveness is evaluated in terms of performance, reliability,
public health protection, and environmental impacts.

Performance is the ability to effectively perform the intended
functions.  Performance of a water supply alternative is
evaluated based on two factors: productiveness and useful
life.  Productiveness refers to the quantity and quality of
the water supply which an action will provide for the potentially
affected residences.  The useful life is the length of time
the level of productiveness can be maintained.

Reliability of a water supply alternative is evaluated in
terms of 0 & M requirements and demonstrated performance at
similar sites.  Evaluation of 0 & M includes availability of
labor and materials and the frequency and complexity of the
necessary O&M.  Technologies requiring frequent or complex
operation and maintenance activities are considered less
reliable.  The evaluation of demonstrated performance includes
an estimate of the probability of failure for each water
supply alternative.

Public health protection of a water supply alternative is
evaluated based upon assessing how well the alternative
satisfies the health-based remedial objectives, i.e., prevents
ingestion of and direct contact with the contaminated groundwater,
The ARARs against which the protectiveness of the various
alternatives may be judged are summarized in Tables 2 and 3.
The qualitative evaluation and comparison of public health
impacts and protection is focused on the public health risk
reduction resulting from implementing each water supply
alternative.

Environmental impacts are compared based on the expected
environmental results for the seven water supply alternatives
and their relative beneficial and adverse effects on the
environment.  Effects of substantial earthwork, construction
of submerged creek crossing support trenches, and the
associated adverse traffic impacts are also considered.

   0 Performance

Alternative 1 - No Action

This alternative includes a long-term monitoring program for
twenty-eight houses near the site which have a high potential
of contamination in the near future and a long-term O&M
program for the existing eight individual point-of-use treatment
systems.  The periodic monitoring program will not provide
any mitigative measures.  The continuous O&M would only be a
partial and temporary solution for the present problem.

-------
                             -19-
This alternative requires separate 0 & M  for each individual
house which, will have a lower effectiveness and efficiency
than for a centralized treatment system.  The 0 & M consists
primarily of replacement of carbon filters and cleaning of
the airlift stripping unit.  With proper  operation and adequate
maintenance, these point-of-use treatment systems can supply
safe drinking water for each individual resident.  It is
estimated that carbon filter replacement  would be required
once every six months, and the inspection, adjustment and
repair would be required on a weekly basis for the airlift
stripping system.

Alternative 3B - Water Delivery By Tanker Truck, Elevated
Storage Tank, Water Lift Pump and Water Distribution System

Under this alternative, a permanent small municipal water
supply system would be installed to provide a domestic water
demand (75 gpcd).  Except for the type of water delivery,
this community water supply system is a standard rural water
supply system.  Since the daily water demand is approximately
0.02 MGD water transport by tanker trucks is highly feasible
and practical.  The effectiveness and efficiency of this
alternative is slightly lower than the pipeline transport
system.     _•  	-  •-•-'•"L!-3
The useful life of a community water distribution system is
normally over 30 years, but requires long-term  0 & M.  The
tanker truck would have a  life of approximately 10 years
based on a 100 mile daily  drive.

Alternative 4A-1 - Extended Catskill Water Supply Pipeline
From Leeds

Under this alternative, a  water  transfer and distribution
system would be installed  to connect with an existing and
nearby municipal water supply system, thereby providing safe
drinking water to the designated service area.  The Catskill
Water Supply District-has  a water treatment design capacity
of 2.8 MGD at the Potuck Plant,  which is capable of providing
more than 0.5 MGD out of the current district area.  The
Potuck Water Plant supplies the  district water demands in
compliance with established drinking water criteria.  This
alternative would be an expansion project of the Catskill
Water Supply District.

-------
                             -20-
This alternative is very effective, since the use of an
alternative water source, which is a proven technology, would
terminate the use of contaminated groundwater and the associated
potential exposure pathways.  A booster pumping station would
be installed to ensure adequate water flow and pressure to
the potentially affected area.

The  useful life of a community water supply system is normally
over 30 years and this system would become a permanent public
facility under proper O&M.

Alternative 4A-2 - Extended Catskill Water Supply Pipeline
From Sandy Plains Road"

This alternative is similar to Alternative 4A-1 except for a
different water transfer pipeline route.  The water diversion
pipeline along Sandy Plains Road has to cross both Catskill
Creek and Potic Creek, but will have shorter distance
(approximately 4,000 ft) than Alternative 4A-1.  Accordingly,
the booster pumps will require lower pressure head and the
pipeline maintenance will be substantially reduced.  The
effectiveness and efficiency of this alternative for providing
safe drinking water is equivalent to Alternative 4A-1.

This public water supply system would be very effective in
providing a standard rural water demand, and the use of an
alternate water source would eliminate the exposure pathways
of ingestion and direct contact with contaminated groundwater.
With 0 & M by the appropriate state or local entities, the
level of effectiveness would remain the same over a long-terra
period.

Similarily, the useful life of this alternative would be over
30 years since it would become a permanent public facility.

Alternative 4A-3 Extended Catskill Water Supply Pipeline From
Rudolph Weir Road

This alternative would have a longer water transfer pipeline
along Rudolph Weir Road, and the booster pumps would require
higher pressure head than Alternative 4A-1.  The standard
water works criteria would govern construction of the water
supply extension.  The alternative water supply source concept
has been proven to be effective at similar sites where alternate
supplies have been installed.   Therefore, the effectiveness
and efficiency of this alternative is very good.

-------
                              -21- •


The useful life of a public  water supply system is normally
over 30 years but would  require  long-term operation and
maintenance.  As a portion of the Catskill Water Supply
District, the useful life of this alternative would be
permanent.

Alternative 4C - New Well Field  Water  Supply System

The effectiveness of a new well  field  water supply is considered
to be good, but it is unproven for  long-term operation.  The
potential new well field would be located along the banks of
Catskill Creek based on  the  favorable  recharge characteristics
of this location, and the assumption that groundwater is
flowing towards the creek.   The  expected yield of deep wells
in this area may vary seasonally.   Based on current operational
results of two trailer park  wells which  were installed in
this area in the Summer  of 1987, the effectiveness of this
alternative is good.                _^_:?J". ..__..;:  ... --_^_-..-'-.  -^
       ^    -   *•••-••-   • ••  ••-.«p ~"a  ?V*cer  :".-, 3" •_•-.•.', » - -~  " - .. "^
An old municipal landfill, however, is located approximately
1/2 mile upgradient of the new well field,'and could become a  .
potential contamination  source in the  future.

Alternative 4D - Extended Trailer Park Well Water Supply
System

Two deep wells for trailer park  use were installed approximately
one mile upgradient of the AT site. The" total combined yield
is approximately 70 gpm, which is sufficient to serve both
the trailer park and the potentially affected area.  The well
water is not contaminated and meets the  drinking water criteria.
The installation of an elevated  storage  tank and a water
distribution system will create  an  independent water supply
district and provides i.  standardr"rural water supply.
                 - • —•    -*     -          -  -f^ • ~; » . _ -. - .

This alternative will accomplish the design'objectives (75
gpcd, 35 to 60 psi) for  short-term  operation, but its ability
to maintain the same level for long-term operation is uncertain
as in the case of Alternative 4C.   The effectiveness of this
alternative is high based on the current operational results.
             -w ,= •- • -^ : .    • - , •      ••••-•,-. -*,-,  •--.-• .B^, .    . ,*    •-«..,.

The trailer park wells are facing a potential contamination
threat from both the AT  site and the municipal landfill.
There is insufficient information to confirm and quantify this
contamination potential  at this  time.  The useful life of
this alternative is, therefore,  unknown  and depends upon the
migration of the nearby  contamination  sources.


-------
                             -22-
   0 Reliability

Alternative 1 - No Action

To maintain the effectiveness of this alternative requires
intensive operation and maintenance of an airlift stripping
system and seven carbon filter systems.  Vendor O&M may be
required for the airlift stripping system.

Any potential scaling and bio-fouling will result in failure
of the air stripper to remove volatile organics.  Weekly
inspection, adjustment, repair and cleaning would be required
for normal operation.  The level of operator training required
would be intensive and specific.

Periodic monitoring and replacement of carbon filter s would
have difficulty maintaining the same effectiveness for safe
drinking water, because the groundwater contamination is
changing due to the continuous migration.  The possibility
of replacing carbon filters after their exhaustion is high,
therefore, the possibility of failing to provide safe-drinking
water is also high.  The replacement of exhausted filters and
well water sampling and analysis requires well-trained and
experienced technicians.

Alternative 3B - Water Delivery by Tanker Truck, Elevated
Storage Tank, Water Life Pump and Water Distribution SysTem

Labor and materials are readily and commercially available
for all components of this alternative.  The operation and
maintenance requirements are not complex.  This alternative
will create a new water supply district which would require
independent administrative, financial and technical resources.

This alternative would require daily water deliveries by
tanker trucks and periodic maintenance of the water tower and
water distribution system.  The possibility of failure due to
truck maintanance problems, and adverse weather conditions is
low because the water tower would have sufficient storage for
approximately 10 days normal water demand, and a standby truck
would be provided.  Other failure due to pipe leakage is
rarely possible within its useful life.

-------
                             -23-
Alternative 4A-1 - Extended Catskill Water Supply Pipeline
From Leeds_

This alternative would divert water from the Catskill Water
District's  16-inch transfer line to the proposed service area
by means of a 12-inch diameter pice along Route 23B from
Leeds.  The extended water distribution facilities including
water diversion station, booster pumping station, force main
and domestic connections are made from readily available
material and technologies.  The O&M of public water works
systems is  straightforward and requires no special technologies.
This alternative would not create an independent water district,
but would instead be governed by the Catskill Water Supply
District.

The probability of a public water works failure is generally
low because an emergency water source is provided, and most
of the pipelines are underground to protect from freezing.
The Catskill Water Supply District has pumped emergency water
from Catskill Creek in an extreme drought season.  The booster
pumping station in this alternative provides a standby pump
and diesel  generator in case of power failure.

Alternative 4A-2 - Extended Catskill Water Supply Pipeline
from Sandy  Plains Road

This alternative is similar to Alternative 4A-1, but has a
shorter transfer pipeline diverting the water from the Potuck
Water Plant to the potentially affected area.  The extended
force main  requires two submerged creek crossing support
trenches for both Catskill and Potic creeks.  All of the
technologies to install the creek crossing trenches have been
proven under similar site conditions, and the availability of
labor and material is generally good.

The O&M of  this extended water tranfer and distribution
system is not complex.  The Catskill  Water Supply District
has sucessfully operated and maintained the same type of
water works for more than 50 years.  The probability of
failure for a water distribution system is relatively low
within its  useful life.

-------
                             -24-
Alternative. 4A-3- Extended Catskill Water Supply Pipeline
From Rudolph Weir Road

This alternative is similar to Alternative 4A-1 , but has a
longer transfer pipeline along Rudolph Weir Road.  The pipe
would be hung on the Route 67 bridge crossing Catskill Creek.
This bridge hangling technology has been proven and demonstrated.
Labor and materials for this technology are readily and
commercially available.  The pipe will be insulated, and
requires a periodic and long-term maintenance which is technically
simple.

The possible mode of water supply failure in a water transfer
and distribution system is primarily from pipe leakage beyond
the useful life of the pipe joints.  The technologies of
water pipe leakage prevention are available and proven.

Alternative 4C - New Well Field Water Supply System

This alternative consists of two new deep wells, an in-line
chlorinator, a water storage tank and a water distribution
system.  Except for the deep wells, the reliability of other
water supply facilities is generally high, since labor and
materials are readily available and technologies are proven
and demonstrated.  06M of the water transfer and distribution
system are normally simple.

The long-term reliability of new deep wells with respect to
yield and water quality is uncertain based on the following
considerations:

   0 The area groundwater is found almost exclusively in
     bedrock fracture zones and joints, and typical yields
     are approximately 20 gpm;

   0 Within two miles upgradient of the AT site, only the
     flood plain area near Catskill Creek (Leeds Flat area)
     appears to be capable of providing a yield of more than
     30 gpm.  This is based upon favorable recharge character-
     istics and the assumption that groundwater is flowing
     towards the stream.  Two trailer park wells are currently
     installed in this area; and

   0 The proposed new well field would be located between
     Catskill Creek and Route 23B in the Leeds Flat area.
     The long-term operation of the new well field would have
     two uncertainties: the potential for interference from
     of the trailer park wells, and the potential for contaminatio
     from the old municipal landfill which is located approxi-
     mately one half mile upgradient of the proposed well
     field.

-------
                             -25-
At this time,, there is not enough information to  resolve
these two uncertainties related to the future operation of
new wells.

Alternative 4D - Extended Trailer Park Well Water Supply
System

The utilization of the trailer park wells to serve the potentially
affected area is technically feasible based on the current
operation performance.  The availability of a sufficient
yield and the maintenance of water quality of the trailer
park well field are not issues of concern, since  the wells
are currently operating and can provide the required capacity
at this time.  However, the future capacity and the potential
for contamination from the upgradient municipal landfill are
unknown.

 "Public Health Protection

Alternative 1-No Action

This alternative includes a long-term groundwater monitoring
program and an operation and maintenance program  for the
existing point-of-use treatment devices, seven carbon filters
and one airlift stripping system.

This alternative will provide limited protection  of public
health in the present eight affected residences only.  These
point-of-use treatment devices reduce the public  health threat
to less than a 10"^ risk level.  However, to maintain the
same level of effectiveness, regular replacement  of the carbon
filters and proper cleaning to prevent the growth of microbes
is required for an airlift stripping system.  Treatment system
malfunctions and operational errors could cause exposure to
accumulated contaminated residues on the equipment and facilities.
The long-term monitoirng program would exert no effect on
health concerns, but  it would provide an early warning of any
additional contaminated wells.

-------
                             -26-
Alternative 1 would not include any  implementation of  treatment
facilities and, therefore, no  construction  hazards are expected.
However, the direct contact and inhalation  risk  of volatile
contaminants might threaten workers  during  the operation and
maintenance activities.  Hence, a health  and  safety protection
procedure would be required for workers.

Post-remedial reductions in public health risks  would  be
moderate and not complete  for Alternative 1.  The  continously
migrating groundwater contaminants may cause  additional  well
contamination, and additional  installation  of carbon filters
would be required in the future.

In summary, this alternative provides only  partial public
health protection.

Alternative 3B - Water Delivery By Tanker Truck, Elevated
Storage Tank, Water Lift Pump  and Water Distribution System

This alternative consists  of a water tanker truck, an  elevated
storage tank, water lift pumps and a water  distribution
system.  The. intent of this alternative  is  to provide  a  rural
community with an alternate water source  so that the potentially
affected residences can discontinue  the use of potentially
contaminated groundwater.

Utilizing  trucked  in water, this alternative  will  eliminate
the  potential exposure of  the  public through ingestion and
direct  contact of  contaminated groundwater  from  the currently
unprotected wells,  significantly reducing the associated
public  health risk.

This alternative would  be  implemented  in  the potentially
affected area where  the  extent of contaminated soil is unknown,
particularly  where the  elevated  storage  tank will  be located
at the  AT  site.  Since  the water distribution system would b«
 installed  in a shallow  subsurface  (4 to  5 ft), normal  construction
hazards such a« dust,  soil erosion and dewatering  would  be
 encountered.   The  regular  occupational  safety and  health
 protection measures would  be  provided  during the short-ten
 construction.

-------
                             -27-


Health considerations associated with the construction of an
elevated water storage tank on-site could be significant,
since there is a potential to come in direct contact with
hazardous materials.  Volatile emissions may be  released and
cause a possible deterioration of air guality, hence a short-
term air monitoring program may be required.

After remedial action is completed, no further exposures
would be expected before the contaminated groundwater is
remediated.  The probability of the alternate water distribution
system being contaminated by groundwater is very low.

Alternative 4A-1 - Extended Ca"tskill Water Supply Pipeline
From Leeds

This alternative would provide an alternative water source by
extending the Catskill water supply pipeline to  the potentially
affected area.  The expanded water distribution  system consists
of a water diversion station, a booster pumping  station, the
creek crossing support trench and a water distribution system.

This remedial alternative is designed for a risk level below
10~*> and focuses on providing a totally alternate water
source.  The alternate water supply does not contain any hazardous
substances.  Termination of the contaminated groundwater uses
would totally eliminate the existing exposure pathways of
ingestion, inhalation and direct contact of the  contaminated
groundwater.  The public health risk reduction of this alternative
is high and complete.

Normal construction hazards such as dust, noise  and temporary
air quality deterioration due to traffic congestion are
expected during the implementation of this public water works
project.  Basic public health and safety protection measures
would be applied as a short-term requirement.  Aside from
normal construction hazards associated with the  water transfer
pipeline installation, the construction of the water distribution
system in the potentialy affected area would have a low
probability of direct worker contact with the contaminated
soil and groundwater.  There should be only minimal effects
on neighboring communities during construction of this alternative
if dust and traffic control measures are taken.

-------
                             -28-


This alternative is similar to Alternative 38 in that the
complete elimination of potential post-remediation public
health risk would be achieved.  Considering the extent and
level of contaminants where the pipeline would be installed,
the exposure of subsurface contaminanted soil and groundwater
to the water supplies would be minimal.


Alternative 4A-2 - Extended Catskill Water Supply Pipeline From
                   Sandy Plains Road

This alternative would have a water transfer system and water
distribution system identical to Alternative 4A-1, except for
different water transfer pipe routing.  A shorter water
transfer pipeline is not developed based on any public health
risk concerns.

The minimization of exposures to the contaminants, safety
concerns and post-remediation risk reduction would be equivalent
to those detailed in Alternative 4A-1.


Alternative 4A-3 - Extended Catskill Water Supply Pipeline From
                   Rudolph Weir Road

This alternative would have a water transfer system and water
distribution system identical to Alternative 4A-1, except for
different water transfer pipe routing.  A longer water transfer
pipeline is not developed based on any public health risk
concerns.

The  same exposure minimization to the volatile organic contaminants
that was outlined in Alternative 4A-1 can be applied to this
alternative.

-------
                             -29-


The same safety concerns with implementing Alternative  4A-1 can be
applied to this alternative.  However, traffic congestion
could have greater consequences on Route 67 and the surrounding
residences because of the construction activities  in hanging
the water transfer pipe on the bridge.

The complete elimination of potential post-remediation  public
health risks would occur after implementation of this alternative.

Alternative 4C - New Well Field Water Supply System

This alternative involves the implementation of a  new well
field, a water storage tank and a water distribution system.
This new system would provide an alternative water source by
utilizing uncontaminated groundwater upgradient from the AT
Site.

Technologies being considered for Alternative 4C would  successfully
mitigate the existing and future exposures of the  receptor
population to all contaminated on-site matrices.   As long as
the new well field is not contaminated, the reduction in
public health risks contributed by this alternative is  complete.

This alternative would have the normal hazards associated with
construction activities as outlined in Alternative 3B,  except
the potential for workers to contact and inhale volatile
organics during the construction of an elevated storage tank
on-site.  Alternative 4C would have the elevated storage tank
installed on the new well field site where no volatile  air
emissions could expose the workers and the surrounding
population.

Improperly  constructed new wells  can  provide  an effective
conduit  for  contaminant*  to move  from a contaminated aquifer
to  an  uncontamlnated  aquifer.  As  discussed previously, the
new well  field would  be  located approximately one  mile  upgradient
of  the AT site and  1/2 mile downgradient of the municipal landfill.
The precise, location  of  the contaminant plumes from the AT site
as  well  as  the possibility of  the  presence of a plume from the
landfill  cannot be  determined  at  this time.

-------
                             -30-


In the future, this alternative might completely eliminate
the potential post-remediation public health risks.  However,
if any contaminant migration reaches the new well  field,  this
would create significant post-remediation risk.

Alternative 4 D - Extended Trailer Park Well Water Supply System

This alternative would utilize the existing trailer park  wells
as an alternative water source and create a new water supply
district covering both the potentially affected area and  the
trailer park.  This alternative consists of a water storage
tank and a water distribution system similar to Alternative
4C, except that a portion of the force main would  be extended
to serve the trailer park.

The minimization of exposure to the contaminants would occur
in the same manner as those detailed in Alternative 4C.

The same safety concerns with implementing alternative 4C can
be applied to this alternative.  However, since the wells are
currently existing., the hazards posed by remediation is less
than Alternative 4C.

Since Che trailer park well field is located- approximately 3/4 mile
upgradient of the AT site and 1/2 of a mile downgradient  of the
municipal landfill, the post-remediation risk reduction of this
alternative would be the same as Alternative 4C.

   0 Environmental Impacts


Alternative 1 - No Action

This alternative  involves only groundwater monitoring and 0AM
of the existing treatment facilities.  Essentially, no im-
plementation would be  required,  since the treated flow  is
small compared to the  contaminated groundwater, there would
be no change  in the existing migration of groundwater con-
tamination.  The  possibility that this action would appreciably
affect groundwater quality  is considered remote.   Any beneficial
effects  on groundwater restoration would depend upon the
long-term  natural soil attenuation and groundwater flushing.

-------
                             -31-


The intermittent pumping and treatment of eight residential
wells would have essentially no effect on the existing environmental
conditions of the surface water, groundwater and ecosystem.
The groundwater pumping may slightly affect the migration
pattern of groundwater contaminants, but the positive impact
of removing contaminants and the negative impact of spreading
contaminant would be balanced.  Since this alternative requires
no construction, there would be no improvement of human use
resources, and the existing migration of contaminants off-site
via groundwater would continue indefinitely. This alternative
would not increase the extent and/or level of contamination
in this study area.

Alternative 3B - Water Delivery By Tanker Truck, Elevated
                 Storage Tank, Water Lift Pump and Water
                 Distribution System

This alternative includes the implementation of an elevated
storage tank at the AT site and a water distribution system
in the potentially affected area.  The construction activities
may result in a slight beneficial impact on removal of contamination
sources in the study area.  During the excavation activities,
soils would be monitored and those with high contaminant
levels would either be removed for off-site disposal and
replaced with clean soils or handled as part of the source
control remedy.  The possibility of disturbing and removing
contamination sources is much higher for the elevated storage
tank construction than for the installation of the water
distribution system, since it would be installed on the AT
property.

The implementation of Alternative 3B would temporarily increase
the potential for contaminated surface water runoff, particulate
(dust) dispersion, traffic congestion and high noise levels.
Since the pipeline excavation, restoration and repavement
would be completed in the same day, the amount of contaminated
surface runoff would be minimized.  Portions of the pipeline
installation would require dewatering which would be monitored.
Adequate treatment should be provided for contaminated groundwater
prior to discharge.  The potential of shallow groundwater
contamination within the affected area cannot be determined
at this time.

-------
                             -32-


Dust suppression measures would be provided for the earthwork
construction*- particularly an air monitoring program during
the excavation of a water tank foundation at the site.  A
runoff drainage barrier system such as a silt fence would.be
installed to offset the possibility of erosion at the site.

A traffic control plan would be developed and executed to
minimize the potential increase of traffic congestion, air
pollution and noise.  Since the rural area does not have a
heavy volume of traffic on Route 23B, the short-term traffic
impacts on the human environmental are considered insignificant.
The long-term traffic impacts due to the water deliveries at
four round-trips per day are also considered minimal.

Alternative 4A-1 Extended Catskill Water Supply Pipeline From
                 Leeds

This alternative includes the installation of a water transfer
pipeline, a booster pumping station and water distribution
system.  Since these construction activities are not directly
related to environmental improvement/ no beneficial impact on
the contamination source removal and groundwater restoration
is expected.  A long-term water supply would directly raise
the living standards and improve the community's environment.

The same adverse environmental impacts in terms of traffic
effects, dust dispersion and increased noise that was discussed
in Alternative 3B during the water distribution system construction
can be applied to this alternative.  In addition, the water
transfer pipeline would cross Catskill Creek and would require
submerged pipe installation.  Catskill Creek is classified as
a B(T) stream which denotes that it has a water quality
suitable for fishing, especially for trout.  The construction
of submerged trenches would require a short-term diversion of
creek flow which would alter the existing flow pattern.
Marine biota and species would not be adversely affected
after construction is complete.  The installation of pipe
submerged trenches in the creek would not raise the water
level, change flow patterns or increase the possibility of
flooding.

-------
                             -33-


Alternative 4A-2 - Extend Catskill Water Supply Pipeline From
                   Sandy Plains Road

This alternative would implement a water transfer and distri-
bution system utilizing an alternate water source similar to
Alternative 4A-1, except by means of a different water transfer
route.  As discussed in Alternative 4A-1, the beneficial
impacts on the human environment, ecosystem and human use
resources for this alternative are insignificant.  However,
this alternative provides a public water supply and terminates
the use of potentially contaminated groundwater, thereby
creating an unquestionable long-term benefit for the community.

The same adverse environmental impact concerns with implementing
Alternative 4A-1 can be applied to this alternative.  However,
a portion of this water transfer pipeline would be trenched
subgrade through a strip of agricultural land before and after
crossing the Catskill Creek.  The loss of approximately one
quarter acre of farm land is not considered a significant
adverse impact.

Alternative 4A-3 - Extended Catskill'water Supply Pipeline From
                   Rudolph Weir Road

This alternative is similar to Alternative 4A-1 and Alternative 4A-2,
since the beneficial environmental impact of this alternative
is considered minimal.

The same adverse environmental impact concerns related to
implementing alternative 4A-1 can be applied generally to
this alternative, except the adverse environmental impacts on
Catskill Creek.  This alternative would involve the hanging
of the water transfer pipe on the Route 67 bridge instead of
the creek crossing support trenches.  During the temporary
construction of pipe supports on the bridge, adverse environmental
impacts would be limited to traffic-related effects.  An
increase in noise levels would accompany the construction
activities, but once completed, the negative impacts would be
completely eliminated.

Alternative 4C - New Well Field Water Supply System

This alternative would install a new well field in an uncontaminated
aquifer and a water distribution- system to serve the potentially
affected area.  Any beneficial effects to the biological
environment and human environment are minimal.  However, this
alternative creates a new public water supply district which
would improve the social-economic environment for the community.

-------
                             -34-
Short-term adverse effects such as traffic, dust and noise
during the installation of a water distribution are the same
as described in Alternative 3B.  However, adverse impact on
the area ecosystem may occur as a result of this alternative.

A slight environmental risk would still remain after the
implementation of the new well field, since the well pumping
would create a radius of influence which may interfere with
the migration of contaminants from both the AT site and any
contaminants the could be migrating from the old municipal
landfill.  During long-term pumping, the groundwater flow
pattern may be changed, and deleterious effects on other
wells in the area may result from intercepting contaminated
groundwater.

The chlorination of groundwater would not require intensive
material handling and would not increase the risk of exposure
or accident.

Alternative 4D - Extended Trailer Park Well Water Supply
System

This alternative would divert the trailer park well water to
a newly built water storage tank and then a water distribution
system within the potentially affected area.  The positive
and negative environmental impacts described in Alternative
4C are similar for this alternative.  However, this project
would not include the installation of new wells.  Accordingly,
the groundwater pumping interference would be reduced and the
associated environmental risk would be minimized.  In general,
this alternative has the same long-term benefit as Alternative
4C, but with less adverse side effects resulting from construction
and operation.

-------
                                -35-
  ImplemenCability

  Each alternative  is evaluated with  respect  to  technical
  feasibility, constructability, institutional requirements,
  and safety.

  The evaluation of technical feasibility consists of determining
  how technically practicable each water supply  alternative
  would be to implement at this specific site under these
  particular conditions.  Feasibility considers  the availability
  of required equipment and facilities for an alternative in
  addition to the appropriateness of recommending that alternative.

  Constructability  relates to the ease of installation and the
  estimated time required to design and construct each water
  supply alternative.  This evaluation reflects  the estimated
  difficulty of construction due to the need for rock excavation,
  dewatering, crossing of steep terrain or bodies of water, and
  access to private property.  Timeliness (time  to implement)
  system) also considers how long it might take  to secure all  ,
  of the required state, county, and local construction approvals
  for each alternative.

  The implementation of each water supply alternative will
  involve certain site-specific and technology-specific insti-
  tutional requirements.  These include administrative and permit-
  ting, requirements and compliance with all of  the ARARs, including
  more stringent state requirements.  State and  public acceptance
  of the alternative is also considered.

  The evaluation of safety includes the potential short-term
  occupational health impacts to workers during  implementation
  of an alternative based on Occupational Safety and Health
  Administration and National Institute of Occupational Safety
  and Health guidelines for health and safety.   In addition,
  consideration is given to safety and potential impacts to nearby
  residents.

0 Technical Feasibility

  The technical feasibility evaluation is based on whether the
  water supply alternative is technically practicable, available
  and appropriate for implementation at this site under these
  particular conditions.

-------
                               -36-
Alternative 1 - No Action

This alternative includes long-term O&M for the eight existing
point-of-use treatment systems along with a long-term monitor-
ing program of the other twenty homes in the potentially affected
area immediately surrounding the AT site.  It is technically
practicable to continue to use these treatment systems since
they have functioned effectively to date and replacements are
readily available.  This alternative is not appropriate for
this site, since it continues to pose a threat to the residents
not currently utilizing (point of use) treatment systems.

Since there is no way to predict when the carbon filters will
be exhausted ("break through"), it is possible that  the
residents could be exposed to contaminated water at  their
taps and not be aware of this until the laboratory analysis
is received from the next round of sampling.  Also,  this
alternative has no provisions for carbon treatment units in
the other homes should the contamination continue to migrate
beyond the current eight residences.

-------
                             -37-
Alternative 3B - Water Delivery by Tanker Truck, Elevated
  ""Storage Tank, Water Lift Pump, and Water
                 Distribution System

This alternative entails establishing a new  independent water
supply district consisting of an elevated storage tank,
regular deliveries of purchased water by tanker truck, a lift
pump and a complete distribution system.  Since each required
piece of equipment is both conventional and  readily available,
implementing this alternative is technically practicable.

Although this type of system has not been previously used, it
would provide an appropriate solution for this small and rural
community.  A 5000-gallon tanker truck would have to pick up
and deliver water to the 50,000-gallon water tower four times
per day, seven days per week.  Water could be purchased from the
nearby Catskill Water District and each delivery would only
entail a 20-mile round trip.  The water tower could be installed
on the AT site for easy access from Route 23B and to take
advantage of the available static head from  this local point
of maximum elevation.  An adequate supply of water would be  .
provided.
. r                                 "           -      -
Alternative 4A-1 - Extended Catskill Water Supply Pipeline
from Leeds'

This alternative consists of purchasing water from the nearest
available municipal water supply system by extending the
Catskill water supply pipeline from Leeds, across Catskill
Creek, and along Route 23B.  Since the Catskill Water District
system has a capacity of 2.8 MGD and currently uses only 1.7
MGD during typical average demand periods, it is technically
feasible to extend this system to supply the 80 residences
(approximately 250 persons) in the potentially affected area.

The Catskill water District is well-established and has been
functioning successfully for over 50 years.  Installing an
extension would entail standard and readily  available equip-
ment such as a water diversion station and a booster pumping
station.  In addition, this type of project  has been implemented
at other similar sites.  This alternative is appropriate for
this site and would provide an adequate supply of water to
meet a typical rural demand of 75 gpcd.

-------
                             -38-


Alternative 4A-2 - Extend Catskill Water Supply Pipeline from
                   Sandy Plains Road

This alternative is similar to alternative 4A-1, except that
the tie-in to the existing Catskill pipeline would be at
Sandy Plains Road, and the extension would have to cross both
Potic and Catskill Creeks by submerged installations.  Less
piping is required than for either Alternative 4A-1 or 4A-3.
Implementing this alternative is technically practicable,
uses conventional and readily available equipment and
facilities, and is appropriate for use at this site.

Alternative 4A-3 - Extend Catskill Water Supply Pipline from
                   Rudolph Weir Road

This alternative is similar to Alternative 4A-1 and 4A-2,
except that in this option the tie-in to the existing Catskill
pipeline would be near Rudolph Weir Road, and the extension
would have to cross both Potic and Catskill creeks.  More
piping is required than for either Alternative 4A-1 or 4A-2,
but this route does not require crossing private land and
uses the Route 67 bridge to hang the pipe over Catskill
Creek.

Implementing this alternative is technically practicable,
uses conventional and readily available equipment and
facilities and is appropriate for use at this site.

Alternative 4C - New Well Field Water Supply System

This alternative establishes a new independent water supply
district consisting of two new wells, a water storage tank,
chlorine treatment and a complete distribution system.  The
proposed location of the new well field is approximately one
mile southeast of the AT site, in an area labeled as the
"Leeds Flat" on the USGS topographic map, between Catskill
Creek and Route 23B.  Deep wells installed in this area have
yielded between 30-60 gpra.  Sand and gravel deposits are
capable of yielding the most water.  Each well should be
capable of providing at least 40 gpm based on the favorable
recharge characteristics of this location, and the assumption
that groundwater is flowing towards the creek.

-------
                             -39-


Pumping the groundwater to a 50,000-gallon water storage tank
provides a buffer against the continually fluctuating domestic
demand.  Based on recent results at a trailer park located
less than 1,000 feet northwest of the proposed location, the
groundwater pumped from this aquifer is expected to be suitable
for potable use after chlorination.  However, definitive
proof to confirm the adequacy of this water supply with
respect to quantity and quality can only be obtained when the
wells are actually drilled and tested.   Several wells might
have to be drilled before meeting the requirements.

Implementing this alternative is technically practicable,
uses conventional and readily available equipment and facilities,
and appears to be appropriate for use at this site.

Alternative 4D- Extend Trailer Park Well Water Supply System

Alternative 4D is similar to Alternative 4C since it would
use uncontaminated groundwater from a well field which is
located approximately 3/4 mile upgradient of the AT site.
The trailer park has two existing wells which could provide a
combined flow of approximately 70 gpm.   Since .this flow is
considerably more than the instantaneous demand at the trailer
park, it would be technically feasible to pump the groundwater
continuously to a 50,000-gallon water storage tank which
would enable servicing the potentially affected area (80
homes, 250 persons) and would provide a buffer against con-
tinual fluctuations in the domestic demand.

Combining and extending the trailer park system is practicable,
and uses conventional and readily available equipment and
facilities.  This alternative should be appropriate for use
at this site, and it would benefit the residents of the trailer
park.

The existing wells currently provide groundwater of adequate
quantity and quality.  This mitigates the uncertainty associated
with installing a new well field (Alternative 4C).

0  Constructibility and Timeliness

The constructibility evaluation is based on the ease of
installation and the timeliness of implementing the water
supply alternative at this site under these particular
conditions.

-------
                             -40-
Alternative 1 - No Action

Since this alternative only includes long-term O&M of the eight
existing point-of-use treatment systems and monitoring of the
other 20 homes immediately surrounding the AT site  no con-
struction is required

Alternative 3B - Water Deliver by Tanker Truck,_ Elevated Storage
                 Tank, Water Lift Pump, and Water Distribution
                 System

This alternative requires the construction of a 50,000 gallon
elevated storage tank at the abandoned AT site to take advantage
of its central location, available static head due to elevation,
and paved access roads.  The ease of installation of this
80-foot high water tower constructed of steel and supported
with a multi-column structure should be relatively straight-
forward since this site has had previous construction work.
Burial of 11,000 feet of transmission and 7,500 feet of
branch piping along Route 23B and its side streets will
entail moderate difficulty due to the need for rock excava-
tion over approximately one quarter of the total excavation
length.  The pipe'.will be buried at least five feet to protect
against freezing.

The time required to  implement would be approximately nine
months, including construction approvals from the Greene
County Highway Department and the Town of Cairo, and possible
precautionary procedures while excavating contaminated soil at
the AT site.

Alternative 4A-1 - Extended Catskill Water Supply Pipeline
                   from Leeds

This alternative entails construction of a water diversion
station in Leeds/ extension of the pipeline across Catskill
Creek by means of a 400 ft submerged installation, construction
of a booster pumping  station and installation of 18,000 ft of
transmission and 7,500 ft of branch piping along Route 23B
and its side streets.  Crossing Catskill Creek near the
historic bridge  in Leeds will require submerged installation
of the pipe in a 3 ft wide by 5 ft deep trench.

-------
                             -41-


Road excavation along the proposed route will  require  roughly
45 percent rock excavation and 35 percent dewatering.  The
majority of .the piping will be along a straight and relatively
flat segment of Route 23B.  The excavation requirements within
the proposed service area (branch piping) are  the same for each
water supply alternative.

The time required to implement would be approximately one
year, including construction approvals from the Greene County
Highway Department and the Town of Cairo.

Alternative 4A-2 - Extended Catskill Water Supply .Pipeline from
                   Sandy Plains Road

Alternative 4A-2 is similar to Alternative 4A-1 except that
it connects to the existing Catskill pipeline  at Sandy Plains
Road in Athens and crosses both Potic and Catskill Creeks
along with various private properties, resulting less  (13,000
ft) transmission pipeline than either Alternative 4A-1 or
4A-3.  Crossing Potic Creek will require a pipe support
trench (3 ft. wide x 5 ft deep) approximately 60 feet long,
while crossing Catskili Creek will require a similar structure
roughly 200 feet long.

Only 20 percent of the total excavation will be rock excavation
in this case, although roughly 50 percent will require dewatering
due to the prevalence of low-lying floodplain  areas.  Some of
the terrain will be rolling but the installation of both the
water diversion and booster pumping stations should not pose
unusual difficulties.

The time required to implement this alternative is estimated
at 15 months, which is longer than for Alternative 4A-1 due to
the need to cross two creeks and privately-owned land.  Access
agreements often take two to six months to negotiate.  This
land consists of mostly plowed fields used for agricultural
purposes.

-------
                             -42-


Alternative 4A-3 - Extended Catskill Water Supply Pipeline  from
                   Rudolph Weir Road

Alternative 4A-3 is similar to Alternatives 4A-1 and 4A-2
except that in this option the tie-in to the existing pipeline
would be near Rudolph Weir Road in Cairo.  The pipeline
extension would then cross Potic Creek by means of a pipe
support trench aoproximately 60 feet long.  The Route 67
steel truss bridge would be used to hang the pipe across
Catskill Creek, which is roughly 200 feet wide at that point.
This bridge has a weight limit on vehicles crossing over it
of 28 tons and should, therefore, have no problem supporting
the proposed pipeline.

Approximately 10 percent of the total proposed excavation
will be rock excavation and roughly 60 percent will require
dewatering.  As in Alternative 4A-2, some of the terrain will
be rolling, but the installation of both the water diversion
and booster pumping station are not expected to pose unusual
difficulties.

Although this alternative requires the longest length of
piping (23,000 feet of transmission pipe), it takes advantage
of an available bridge crossing and does not require access
to privately-owned land as in Alternative 4A-2.  The time
required to implement this alternative is expected to be
approximately ten months, which is shorter than for either
Alternative 4A-1 or 4A-2.

Alternative 4C - New Well Field Water Supply System

Alternative 4C requires the installation of a new well field
consisting of two new deep wells, each six inches in diameter,
approximately 400 feet deep, and with a combined capacity of
at least 60 gpra.  The proposed location of this new well
field is roughly one mile southeast of the AT site off Route
23B and within 1,000 feet of two recently installed wells at
two existing trailer parks.  This location has been picked
because this area is expected to yield the most groundwater,
and the quality of water from the new trailer park wells is
reported to be satisfactory.  However, the exact location and
number of wells can not be determined until a detailed
groundwater study is completed.

Construction of a 50,000 gallon, reinforced concrete, water
storage tank could require special foundation work depending
on the soil composition, and an agreement would have to be
negotiated with the private land owner regarding the location
of this tower on his property.

-------
                             -43-


Burial of the 13,000 ft of transmission pipeline would  re-
quire approximately 30 percent  rock excavation  and  30 percent
dewatering.  The time required  to  implement  this alternative
is estimated to be approximately seven months.

Alternative 4D - Extended Trailer  Park Well  Water Supply
System

Alternative 4D is similar to Alternative 4C  in  relation to
constructability except that it requires extending an existing
trailer park well field instead of developing a new well
field.  The major requirement in this case is to construct a
50,000 gallon, reinforced concrete, water storage tank to
enable using the maximum combined  capacity of the two existing
wells (roughly 70 gpm).  An agreement would  have to be negotia-
ted with the trailer park owner regarding the location of
this tower on his property.  Special foundation work might be
required due to the soil composition.

Burial of the 12,000 ft of transmission pipeline will require
roughly 30 percent rock excavation and 30 percent dewatering.
The time required for implementation is estimated to be
approximately six months.

0  Institutional Requirements

The institutional requirements  evaluation is based on whether
the water supply alternatives can:  1) meet  the administrative
and permitting requirements; 2) attain ARARs for this operable
unit; and 3) be acceptable to the  public and state.

Alternative 1 - No Action

This alternative only inlcudes  long-term O&M of the eight
existing point-of-use treatment systems and  monitoring of
the other 20 homes immediately  surrounding the  site.  No
permits have to be acquired for this activity.  This alterna-
tive will not attain all of the ARARs because breakthrough
could occur and not be detected until the next  round of sampling.
The public and State are not likely to accept this alternative
as a long-term protective measure.
Alternative 3B - Water Delivery by Tanker Truck, Elevated Storage
                 Tank, Water Lift Pump, and Water Distribution
            L£Y_
	Til
System
This alternative will require  the establishment of a new
independent water supply district which will own and be
responsible for the O&M of  the entire water supply system.

-------

                             -44-
A NYSDEC "Application for Permit" and its supplement, "Appli-
cation for Public Water Supnly Permit," would have to be
filed for this project.  Any such project must also be reviewed
by NYSDEC with respect to its potential environmental impact
under New York State's Environmental Quality Review Act
(SEQR).  A "negative declaration" would have to be filed by
the lead agency stating that in its judgment, this alternative
would not produce an adverse impact.

In addition to obtaining the NYSDEC permit, NYSDOH would have
to approve the proposed water supply system in terms of
compliance with water guality standards and would have to
review the engineering plans and specifications for the
distribution system.  The design should be consistent with
"Recommended Standards for Water Works - 1982" (Water Work
Standards, 1982) and "The Design of Small Water Systems"
(NYSDOH, 1985).

Construction approval will be required from the Greene County
Highway Department to enable burial of distribution pipe
along County Route 238.  An "Application for Permit to Do
Work On and Within a. County Road Area" must be filed along
with additional information such as a description of the
project and proposed activities, and a plan for handling
traffic disturbances or other special conditions.  The Highway
Engineer would also meet with the contractor to discuss the
proposed work.  A similar approval would be required from the
Town of Cairo for all work performed on town roads off Route
238.

This alternative is expected to meet the ARARs since it will
utilize purchased potable water from the nearby Catskill
Water District.

The public and State are likely to accept this alternative
since it provides a clean water supply with adequate quality
and quantity.

-------
                             -45-


Alternative 4A-1 - Extended Catskill Water Supply  Pipeline  from
                   Leeds

This alternative is different from Alternative- 38  since  it
extends the existing Catskill Water Supply District pipeline
from Leeds to the potentially affected area.   The  same NYSDOH
and NYSDEC permit applications would be required as with
respect to alternative 3B, however.

Construction approvals would have to be obtained from the
Greene County Highway Department, the Town of  Catskill and
the Town of Cairo.  Permission would be required from the
Village of Catskill to enable connection to the existing
pipeline by the construction of a water diversion  station.
Construction activities related to submerged installation of
the pipe across Catskill Creek would require an application
for a NYSDEC Stream Disturbance Permit.  Permission might
have to be obtained from either the National and/or the New
York State Historical Society to enable construction of this
structure near the historic bridge in Leeds.   No private land
would have to be acquired.

This alternative is expected to meet the ARARs  since it
extends a currently approved potable water supply  system. The
public and State are likely to accept its implementation.

Alternative 4A-2 Extended Catskill Water Supply Pipeline form
                 Sandy Plains Road

This alternative is almost identical to Alternative 4A-1 with
respect to institutional requirements.  The only major dif-
ference is that Catskill Creek would be crossed by submerged
installation at a different location and an additional NYSDEC
Stream Disturbance Permit would be required for crossing Potic
Creek near Sandy Plains Road.  Construction approval would
have to be obtained from the Town of Athens to enable work on
Sandy Plains Road.  Privately-owned agricultural land might
have to be obtained in order to enable burial  of the pipeline.

This alternative should also meet the ARARs and the public  and
State are likely to accept its implementation.
                                            V"'>~:>T't''""^Wv^

-------
«.
                                      -46-


         Alternative 4A-3 - Extended Catskill Water Supply Pipeline
         '~from Rudolph Weir Road

         This alternative is almost identical to Alternatives 4A-1 and
         4A-2 with respect to institutional requirements.  The only
         major difference is that Catskill Creek would be crossed by
         hanging the pipe on the Route 67 bridge in South Cairo.  Use
         of this bridge would require approval of the Greene County
         Highway Department.  Mo privately-owned land would be crossed
         in this alternative.

         This alternative should also meet the ARARs; and the public and
         State are likely to accept its implementation.

         Alternative 4C - New Well Field Water Supply System

         This alternative also requires the establishment of a new
         independent water supply district.  All of the same require-
         ments would have to be satisfied including obtaining the
         NYSDEC permit, complying with SEQR requirements, obtaining
         NYSDOH approval,.a Greene County Highway Department permit,
         and Town of Cairo approval.

         Private land would also have to be acquired in order to
         establish the new well field and install the storage tank.

         It is unknown whether this alternative will meet ARARs, since
         the radius of influence of the well pumping might draw
         contaminants from the AT site, or from the municipal landfill
         (if that landfill is a source of groundwater contamination).
         The public and state are not likely to accept this alternative.

         Alternative 4D - Extended Trailer Park Well Water Supply System

         This alternative is almost identical to Alternative 4C with
         respect to institutional requirements.  The only major
         difference is that an agreement would have to be negotiated
         with the trailer park owner as to the connection to and
         extension of the existing well water supply system.

-------
                             -47-
0  Safety

The safety evaluation is based on whether the water supply
alternative might cause potential short-term health impacts
to workers and the oublic during excavation, construction and
other implementation activities.

Alternative 1 - No Action

Since this alternative only includes long-term O&M of the eight
existing point-of-use treatment systems and monitoring of the
other twenty homes immediately surrounding the AT site, the
only implementation activities would be replacing exhausted
carbon filter cells with new ones and replacing parts on the
airlift stripping system.  Since these are closed systems and
no excavation or construction would he required, these activi-
ties should pose no potential short-term health impacts to
the workers and the public.

Alternative 3B - Water Delivery by Tanker Truck, Elevated Storage
                 Tank, Water Lift Pump, and Water Distribution
                 System                    .          '

This alternative requires construction of a 50,000 gallon
elevated storage tank at the abandoned AT site to take advantage
of its central location, available static head due to elevation,
and paved access roads.  Since the extent of on-site soil
contamination has not yet been completely characterized, but
dumping of hazardous waste onto site soils has been reported,
it is assumed that any excavation work conducted on the
property might result in potential short-term health impacts
to workers.

This potential risk can be mitigated by following the health and
safety plan which would be developed for the construction of this
remedy.

Installation of the transmission and branch piping along Route
23B and its side streets, common to each of the remaining
water supply alternatives, is not expected to result in any
short-term health impacts to workers.  No other complex or
dangerous work is involved in the implementation of this
alternative..

Alternative 4A-1 - Extended Catskill Water Supply Pipeline
                   from Leeds

The major construction activity in this alternative is the
submerged installation of the pipeline including the pipe


-------
                             -48-
support trench required for crossing Catskill Creek at a point
where it is roughly 400 ft wide.  Installation of the trans-
mission and" branch piping alone Route 238 and its side streets,
which is required by each of the water supply alternatives, is '
not expected to result in any short-term health impacts to the
workers.  Burial of the pipe along the boundaries of the
American Thermostat property may require the workers to wear
PPE for that portion of the project.

Construction of the pipe support trench under Catskill Creek
might involve some complex and potentially dangerous work,
but only from the standpoint of working in and around a body
of water, not in relation to exposure to hazardous waste.

Alternative 4A-2 - Extended Catskill Water Supply Pipeline
                   from Sandy Plains Road

Alternative 4A-2 is similar to Alternative 4A-1 with respect
to worker safety considerations during implementation activi-
ties.  The major construction activity in this case is the
installation of the oipeline, including two submerged trenches
to cross both Potic and Catskill creeks.

No short-term health impacts to the workers are expected
during burial of the pipeline, except maybe during the portion
of the project which entails work along the boundaries of the
American Thermostat site.  Adherence to site-specific health
and safety protocols should minimize this concern.

Alternative 4A-3 - Extended Catskill Water Supply Pipeline from
                   Rudolph Weir Road

Alternative 4A-3 has the same safety concerns as Alternatives
4A-1 and 4A-2, in addition to concerns associated with suspending
a pipeline from the bridge.

Alternative 4C - New Well Field water Supply System

The major construction activity in this alternative entails
drilling two new wells-and installing a water storage tank and
complete distribution system.  Unlike Alternatives 4A-1, 4A-2,
and 4A-3, no complex or potentially dangerous work involving
crossing water bodies will be required.  The only potential
short-term exposure to the workers might occur during excava-
tion for pipe-laying alone the boundaries of the AT site.
The remainder of the construction work should pose no safety
problems.

-------
                                                           TABDrc
                                                     AMERICAN THERMOSTAT
                                       COMPARISON OP ALTERNATIVE HATER SUPPLY ALTERNATES
                                                                        Tiro to
Capital Cost     OtM Cost  Present Worth Cost
                                                                                             Qograent
 Remedial Alternative

 Alt.  1   No Action

 Point of Use Hater Supply

 Alt.  3B   Water Delivery by
           Tanker Truck,  Elevated
           Storage Tank,  Mater
           Lift  Punp  and  Water Dis-
           tribution  System

 Alternate Mater Sou
Alt. 4A-1 Extended Cataklll Hater
          Supply Pipeline from
Alt. 4A-2 Extended Catskill Water
          Supply Pipeline from
          Sandy  Plains Road
Alt. 4A-3 Extended Catskill Hater
          Supply Pipeline froa
          Rudolph Weir Road


Alt. 4C   New Nail Field Htter
          Supply System
           2.32
           3.17
           2.27
           2.38
           2.20
Alt. 4D   attended Trailer Park Hall 2.06
          Niter Supply System
                 costs ere in 9 million
                      0.18    1.70
0.20    4.38
0.12    4.23
0.10    3.21
0.11    3.47
0.13    3.38
                     0.12    3.22
                        N/A
        Does not protect human health by providing
        potable water to the comunity.
        Would require 4 tanker truck deliveries
        per day.  Subject to service interuption
        (e.g. truck breakdowns).
lyr.
Would provide adequate potable water fron
existing water district.  Crosses Catskill
Creek near historic bridge in Leeds.
l-2yrs. Would provide adequate potable water fran
        existing water district.  Would require
        easenents or acquisition of private land
        for pipe routing.

1 yr.   Would provide adequate potable water from
        existing water district. Crossing of Cat-
        skill Creek by suspending pipe fron Route
        67 bridge.

1 yr.   Would require creation of new water dis-
        trict.  Hall field location could be sub-
        ject to leachate contamination from nearby
        landfill.

1/2 yr. Sane as 4C.

-------
                             -49-


Alternative 4P - Extended Trailer Park Well Water Supply System

Alternative-4D is similar to Alternative 4C except  that it
requires extending an existing trailer- park well field instead
of developing a new well field.

Cost

The cost evaluation of each alternative is based on the
capital cost (cost to construct), O&M cost (O&M), and present
worth cost.

Present worth analysis is used to allow the costs of the
various alternative to be compared on the basis of a single
total cost figure representing the amount of money, that, if
invested in the base year and expended as needed, would be
sufficient to cover all the costs associated with the remedial
action over its planned life.

The capital, O&M, and present worth costs for each alternative
are presented in Table 6.

SELECTED REMEDY                          .

The objective of this operable unit is to eliminate the threat
posed to area residents by exposure to contaminated groundwater,
and represents the first operable unit of a permanent remedy
for the AT site.  Identification of the nature, extent and
sources of the contamination at and around the site, and the
possible remediation of the groundwater contamination will be
addressed in a subsequent ROD.

Based upon CERCLA as well as upon the review and evaluation
of the water supply alternatives, the viable alternatives were
narrowed down to two:

Alternative 4A-2 consists of extending the existing Catskill
Water District pipeline from Sandy Plains Road along Route 23B
to supply all of the potentially affected residences.  This
option would require crossing both Potic Creek and Catskill
Creek along with crossing privately owned properties.

Alternative 4A-3 consists of extending the existing Catskill
Water District pipeline from Rudolph Weir Road along Routes
67 and 23B to supply all of the potentially affected residences.
This option would require crossing Potic Creek near an existing
wooden bridge, and Catskill Creek by hanging the pipeline from
the Route 67 bridge in South Cairo.

-------
                             -50-
EPA has rejected the various other alternatives that were
considered during the detailed evaluation phase of the FFS.
Alternative 1 was rejected because it would allow the existing
situation to continue, and therefore, would not protect human
health.  Alternative 3B is not considered reliable on a long-
term basis.  O&M problems are potentially high (e.g., road
closures due to inclement weather, tank truck breakdowns,
etc.) Alternative 4A-1 was rejected because of its relatively
high cost, compared with the expected costs of Alternatives
4A-2 and 4A-3 and because of the potential impacts of construc-
tion near the Leeds Bridge (a historical site) and the additional
rock excavation during construction.  Alternative 4C was
rejected due to the uncertainties related to developing a new
well field in this area.  While the area selected might
provide wells with a yield of 60 gpm, only a detailed and
lengthy hydrologic groundwater study would determine if this
was indeed a fact.  In addition, the proximity of an existing
landfill nearby could create a new potable water quality
problem in the future..  Alternative 4D has similar problems
associated with it.  If the existing wells were pumped at
their maximum capacity, water quality problems could arise
due to leachate from the nearby landfill.  For this reason,
Alternative 4D was also rejected.

-------
                              -51-
 The  extension of the Catskill water supply system  (in  particular,
 Alternatives 4A-2 and 4A-3) best meets all evaluation  criteria
 as previously described.  Specifically, this remedy will  best
 meet the objectives of CERCLA in that it is protective of
 human health, is implementable and cost effective, will
 provide a permanent solution to the problem of potential
 exposure of area residents to groundwater contaminants, and
 attains the ARARs and criteria relevant to this operable
 unit.

 Although Alternative 4A-2 requires less pipeline and is less
 costly than Alternative 4A-3, it would require easements or
 acquisition of private land for the waterline routing.
 Because of the concerns that significant delays in acquiring
 the  necessary easements might impact our ability to implement
 Alternative 4A-2 in a timely manner, Alternative 4A-3 was
 presented to the public as the preferred remedial alternative.
 However/ as a result of local concerns regarding possible
 vandalism associated with suspending the pipeline from the
 Route 67 bridge as called for in Alternative 4A-3, and an
 increase in O&M costs that would result from the booster pump
 and  a longer pipeline, EPA has decided that further evaluation
 of  the advantages and disadvantages of Alternatives 4A-2 and
 4A-3 should be conducted during the design phase.  After
 performing this evaluation, which will include consultation
 with state and local agencies, EPA will make a final decision
 regarding the exact route of the pipeline.

 Implementation of this remedy will effectively remove the
 risk of exposure to contaminated groundwater.  Further,
 implementation of the selected alternative is consistent with
 all  ARARs, including the Maximum Contaminant Levels established
 pursuant to the Safe Drinking Water Act.

 Extension of the waterline (Alternative 4A-2 or 4A-3) represents
 the  most cost-effective of all remedies considered.  The
 estimated present worth cost of extending-the waterline
 ranges from $3.21-3.47 million.

 Selection of the waterline extension does not satisfy  the
 statutory preference for remedial actions including treatment
 (which permanently and significantly reduces the volume,
 toxicity or mobility of hazardous substances) as a principal
 element, the reason being that such treatment options were
 not  found to be practicable or appropriate for this operable
 unit.  Such options, however, will be considered during the
 next operable unit.
 . _	„	„	.,.........,„.. -,~,,^v.^-v-*-«>^,j:W5:;;^^
''•'•••-'$ ••;,>t-V.,-.--,'-,V;f'i"-'l' "'•'V?* *"' •''*'"?* ' "•,~:"^V rJ'*-*--^t-~	• ' '-- -    . -,r - -  *--vt

-------
                             -52-

Among the alternatives considered during the FFS was one
which would have involved the provision of an alternate water
supply through the use of a centralized well water treatment
system.  However, this alternative (Alternative 2B) would
not provide-a reliable permanent and long-term remedy for
the water supply problem.  Due to the continuous migration
of groundwater contaminants in an unpredictable way in the
bedrock fractures and joints, the O&M that would be required
for Alternative 2B to produce safe drinking water in compliance
with the ARARs would be very difficult.  Construction of
this alternative would entail high difficulty in relation to
burial of two sets of pipe (one for clean and one for contami-
nated water), installation of a centralized treatment facility,
and replacement of any existing well pumps which may be in-
adequate for these purposes.

Consistency with Other Environmental Laws

EPA conducted a preliminary evaluation of the project area
for its potential for discovery of cultural resources.  The
evaluation indicates that known prehistoric occupations have
been identified on both the terraces and low-lying areas to
the north and south of the project area.  In addition, Route
23B (i.e., the Mohican Trail), which is listed on the National
Register of Historic Places,- and Leeds bridge, which is an
Historic Landmark, are in the project area and may be impacted
by the proposed operable unit alternatives.  Accordingly, it
has been determined that the project area is highly sensitive
for the discovery of cultural resources.  Therefore, a survey
will be conducted during the design phase to determine the
presence or absence of unidentified cultural resources, as
well as to provide proper documentation of known resources
that could potentially be impacted by the proposed operable
unit.  Further, if the survey determines that significant
resources will be impacted by the project, appropriate mitiga-
tion measures will be developed and implemented during the
remedial design phase of the project.

-------
                             -53-

The selected-alternative will be located within  a  500  year
floodplain.  Although the major portion of  the project (i.e.,
the water main) will not result in long-term  impacts to  the
floodplain or flooding levels, construction of the diversion
chamber associated with the project may have  long-term impacts
on flooding levels depending on its location.  Although  it is
not believed that the impacts will be significant, a floodplain
assessment will be prepared for the diversion chamber  during
the remedial design phase of the project.  This  will include
development of appropriate control measures to protect the
diversion chamber from flooding effects.

Community Acceptance

The residents were notified of the preferred  remedy with the
issuance of the PRAP, released on December 3, 1987, and at
the public meeting held on December 8, 1987.  The reaction at
the public meeting was, in general, one of support for the
proposed remedy.  The main area of questions  concerned the
possibility of adding fire protection and/or  expanding the
service area.  In addition, the Village of Catskill raised
the question regarding the ability of its water  system to
handle the additional capacity associated with adding  80
residences to the system.  According to CPA's contractor, the  .
water supply system appears to be capable of  providing enough
additional capacity for both the proposed service area
surrounding the AT site and for limited growth in the  present
water district.  It is EPA's intention to work cooperatively
with the Village to resolve the capacity issue during  the
design phase.  However, if disagreement between  EPA and the
Village still persists, EPA will seek an independent assess-
ment to evaluate the Village's capacity to handle the  additional
load.

In order to comply with the request for fire  protection, if
the local entities agree to pay for the incremental cost
associated with full fire protection, EPA is  prepared  to
provide an alternate water supply and distribution system
with partial fire protection capabilities,  including hydrants,
valves, pumps, and the means for providing adequate pressure.
EPA would not, however, provide equipment specifically related
to the provision of extra water capacity, such as a larger
diameter pipeline or larger capacity water  storage tank.
These additional costs for full fire protection  would  have
to be covered by the State or locality.  The  cost  involved in
providing partial fire protection and full  fire  protection
are compared to the base costs, and are shown in Table 7.

With regard to an expanded service area, EPA  can only  provide
water to correct the problems within an existing system.  If
the local communities wish to expand the service area,  they
would be required to pay the incremental cost increase.

-------
                                                            TABLE 7

                                                      AMERICAN THERHOSTAT

                           COMPARISON OP ALTERNATIVE WATER SUPPLY ALTERNATIVES WITH FIRE PROTECTION
                                    Capital Cost*
Remedial Alternative

Alt.  1  No Action

Point of Use Water Supply

Alt.  3B   water  Delivery by
          Tanker Truck, Elevated
          Storage Tank, Hater
          Lift Pump and Water Dis-
          tribution System

Alternate Water  Sources
                   	  OtM Cost	Present Worth Cost    Time to
                                                                            Inp lament
Without     With       With Without  With       With without With    .With  Prom ROD
FP2	Partial FP FP   FP	Partial FP FP   FP	Partial  FP    Signing
 2.50
Alt.  4A-1 Extended Catski 11 Water     3.17
          Supply Pipeline from
          Leeds

Alt.  4A-2 Extended Catski 11 Water     2.27
          Supply Pipeline from
          Sandy Plains Road

Alt.  4A-3 Extended Catski 11 Water     2.38
          Supply Pipeline from
          Rudolph Weir Road
Alt. 4C   New Well Field Water
          Supply System
 2.20
Alt. 4D   Extended Trailer Park Well 2.06
          Water Supply System
2.37
3.31



2.46



2.61



2.40


2.25
                           0   0.18     0.18     0.18    1.70   1.70    1.70   N/A
3.34   0.20     0.20     0.21    4.38   4.27    5.32   1 yr.
                        3.91   0.12     0.12     0.14    4.23   4.45     5.24   1 yr,
                        2.93   0.10     0.11     0.12    3.21   3.48     4.09   l-2yrs.
                        3.36   0.11     0.13     0.15    3.47   3.78     4.79   1 yr.
3.47   0.13     0.13     0.15    3.38   3.67
                        3.29   0.12     0.13     0.15    3.22   3.49
4. 89   1 yr>


4.68   1/2 yr,
          Notes

-------
                             -54-


                           SCHEDULE *
                               f

             AMERICAN THERMOSTAT REMEDIAL ACTION


       Activity                                    Date

0 Regional Administrator Siqns               January 1988
    Record of Decision

0 Complete 60 Day Enforcement                February 1988
    Moratorium**


If no PRP pick-up,  then:

8 Contractor Procurement and                 February-September
    Remedial Desiqn                          1988

0 Contractor Procurement Process             September to
    for Construction           .              November 1988

0 Initiation of Implementation          .     November 1988
    of Remedy

0 Construction Complete                      November 1989
 * This is a projected schedule for this site and it is
   therefore subject to future modification.

** If a "good faith" offer is made by the PRPs within the
   60 days, the enforcement moratorium would be extended an
   additional 60 days.

-------
ADMINISTRATIVE RECORD INDEX




   (to be provided)
                               ATTACHMENT A

-------
Ltv. 31  '37 12 = 56 NYS.ENV. CONS.  flLBflNY NY
Jew York State Department of Environment** Conaarvatian
0 Wolf Road, Albany, New Yorfc 12233.     nniemai con««'v«tlon
   TELEX
   Mr.  Stephen 0. Luftlg
   Director
   Office of Emergency and Remedial Response

                     Protect1on
   26  Federal Plaza
   New York. NY  10278

   Dear Mr. Luftlg:
                Re:  American Thermostat Site
                     Operable Unit 1
                     Site I.D. No. 420006
                                     sdF
                                                              (NYSOEC)
                                           .        f
 n»1i>t«.nc. iftw tht flnt J.2 S wrlt'SI.      '  h§ °Mr'tlM •»«
                                Sincerely,
 cc:  8. Pavlou,  ySEPJ, Region  II
     J. Slngermait. USEPA. Region II
                                                        ••
                                D1v1i1on  of Hazardous Haste Renedlatlon
                                                ATTACHMENT B

-------
RESPONSIVENESS SUMMARY
                          ATTACHMENT C

-------
                  >A WORK ASSIGNMENT NO.  157-2L77
                   EPA CONTRACT NO. 68-01-7250
                      EBASCO SERVICES, INC.
                      RESPONSIVENESS SUMMARY
                             FOR THE
                    AMERICAN THERMOSTAT SITE
                      SOUTH CAIRO, NEW YORK
                          JANUARY  1988
                              NOTICE

  The information in this document has been funded by the United
States Environmental Protection Agency (U.S. EPA) under REM III
Contract No. 68-01-7250 to Ebasco Services, Inc.

-------
                     AMERICAN THERMOSTAT SITE
                      SOUTH CAIRO, NEW YORK
                      RES PONS I VENESS . SUMMARY


The U.S. Environmental Protection Agency Region II  (EPA) released
to the public on December 3, 1987 a Focused Feasibility Study
(FS) and Proposed Remedial Action Plan (PRAP) on the American
Thermostat site for public review and comment from December 3,
1987 until December 24, 1987.  As part of the public comment
period, EPA held a public meeting on December 8, 1987 at the
Greene County Court House in Catskill, New York to describe the
remedial alternatives and to present EPA's preferred alternative
for the development of an alternate water supply at the American
Thermostat site.  The implementation of an alternate water supply
at the American Thermostat site is considered the first step (or
first "operable unit") for remedial action at the site.  A full-
scale Remedial Investigation and Feasibility Study (RI/FS) of the
American Thermostat site and the area groundwater will be
conducted by EPA at a later date.

The purpose of this responsiveness summary is to provide EPA and
the public with a summary of citizen comments and concerns about
the site, and EPA's response to those concerns.  A summary of
comments received during the public comment period is provided in
Section III.  All comments and concerns summarized in this
document have been factored into EPA's final decision regarding
the selection of an alternative to provide an alternate water
supply to areas affected and potentially affected by
contamination from the American Thermostat site.

This community relations responsiveness summary for the American
Thermostat site is divided into the following sections:

I.     Responsiveness Summary Overview.  This section, briefly
       outlines the proposed remedial alternatives that were
       evaluated as part of the Focused FS, including EPA's
       selected alternative.

II.    Background on Community Involvement and Concerns.  This
       section provides a brief history of community interest in
       the American Thermostat site and a chronology of community
       relations activities conducted by EPA during remedial
       response activities conducted to date.

Ill .   Summary of Major Questions and Comments Received During
                -c Comment Period and EPA Resonses to
                                                       .
       This section summarizes major questions and comments made
       verbally and in writing to EPA during the December 8th
       public meeting and public comment period  (December 3 -
       December 24) and provides EPA responses to these comments.

-------
IV.    Remaining Concerns.  This section discusses community
       concerns about the American Thermostat site that were not
       directly addressed during the Focused FS and that EPA
       should consider during the next phase of remedial
       activities, specifically the RI/FS for the second operable
       unit at the American Thermostat site.

I.     RESPONSIVENESS SUMMARY OVERVIEW

The American Thermostat site is located in the Catskill Creek
Valley in South Cairo, Greene County, New York.  American
Thermostat Corporation operated from 1954 to May 1985 assembling
thermostats for small appliances.  Tests of several residential
and commercial wells in the vicinity of the American Thermostat
plant indicated the presence of trichloroethylene (TCE) and
tetrachloroethylene (PCE) in five residential wells.  In May 1981
the State issued an advisory to affected residents advising them
not to drink or cook with their well water.  In 1983, under a
consent order from the State, American Thermostat Corporation
installed and periodically monitored carbon filters on
contaminated residential wells, provided bottled drinking water
to one resident whose well water was unfilterable, and conducted
regular sampling and analysis.  The activities were halted in Ma
1985, when the American Thermostat Corporation ceased operation
at the site.

In August 1985, in response to a request for support from the New
York State Department of Environmental Conservation  (NYSOEC), EPA
began a removal action to maintain the installed carbon filters,
sample other domestic potable wells near the site, and provide
additional affected homes with carbon filters and bottled water
if needed.  In September 1986, EPA authorized the installation of
an airlift stripping system for the residential well closest to
the site and the most seriously contaminated.  Another
contaminated residential well was discovered in February 1987 and
EPA authorized the installation of a carbon filter.

In November 1987,vEPA completed a Focused FS to identify an
alternate water supply for affected and potentially affected
residents.  The Focused FS initially identified thirteen
potential remedial alternatives.  EPA identified seven of the
most feasible for supplying an alternate water supply to affected
and potentially affected residents.  These alternatives are
briefly summarized below.

Alternative It  No Action

The no action alternative would  involve the maintenance of the
existing granular-activated carbon filters and airlift stripping

-------
system and the continued monitoring of twenty-eight residential
wells within the vicinity of the American Thermostat site.
Alternative 3B;  Water Delivery bv Tanker Truck. Elevated storage


Alternative 3B would involve the construction of an elevated
storage tank, a water lift pump, and a water distribution system.
EPA would deliver water four times per day by tanker truck to the
storage tank.

Alternatives 4A-1. 4A-2. and 4A-3:  Extending the Existing
Catskill Water District Pipeline

Alternatives 4A-1, 4A-2, and 4A-3 all would involve purchasing
water from the nearest municipal water supply system and
extending the Catskill water supply pipeline to the affected and
potentially affected residences.  Each alternative, however,
proposes to extend the existing pipeline from different
locations.  Alternative 4A-1 would involve extending the Catskill
water supply pipeline from the Town of Leeds and run it across
Catskill Creek and along Route 23B.  Alternative 4A-2 would
involve extending the Catskill water supply pipeline from Sandy
Plains Road then across both the Potic and Catskill Creeks and
along Route 23B.  Alternative 4A-3 would involve extending the
pipeline from a point near Rudolph Weir Road, across both Potic
and Catskill Creeks, and along Routes 67 and 23B.

Alternative 4C;  Mev Well Field Water Supply System

Under Alternative 4C, EPA would establish a new, independent
water supply district consisting of two new wells, a water
storage tank, chlorine treatment, and a booster pumping station.
In addition, EPA would extend a pipeline along Route 23B to serve
the affected and potentially affected homes.  This alternative
would require EPA to select a suitable location for drilling new
wells outside the potential area of contamination.

Alternative     ^     d  rai.ler Park Well Water Su
Alternative  4O would involve  extending the well water supply
system of an existing trailer park,  located approximately three-
quarters of  a mile upgradient of the site.

All  of the alternatives discussed  above,  except for  the no-action
alternative,  would provide adequate  potable water  to the affected
and  potentially  affected residents.

-------
         ALTERNATIVE
After careful evaluation of the remedial alternatives, EPA has
selected the extension of the Catskill water supply pipeline to
the affected and potentially affected residents.  The specific
pipeline .route to be implemented will either be alternative 4A-2
or 4A-3, described above.  The final decision will be made during
the design phase.

The selected remedial alternative is documented in the Record of
Decision (ROD) .  A remedial investigation and feasibility study
will be conducted at a later date to determine the full extent of
contamination from the site and to develop alternatives to clean
up the site and restore the groundwater.

II.    BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS

The residents that have shown the most interest and concern about
the site are mostly those residents with contaminated wells.  In
early 1986, EPA researched the community concerns and developed a
Community Relations Plan to address those concerns.  The concerns
identified in 1986 and EPA actions to address those concerns are
described briefly below.

       Effectiveness of carbon filtered water.  Residents who
       have had carbon filters installed in their homes questi
       the effectiveness of the filters in cleaning the water.
       As a result, residents have been using bottled water
       cooking and drinking.  In response to this concern, EPA
       made sampling results available- to the -residents and
       assured residents through a meeting that the carbon filter
       system does provide potable water meeting safe drinking
       water standards.

       Irregular schedule for carbon filter monitoring and
       maintenance.  The residents with carbon filters have
       expressed concern with what they perceived as an irregular
       schedule for monitoring their filters and requested that
       EPA or the New York State Department of Health (NYSDOH)
       provide regular and easily understandable monitoring
       reports, concerning the status of their filters.  In
       response to this concern, EPA has taken quarterly samples
       and has provided the monitoring reports.  In addition,
       when EPA officials visited residences to take samples they
       answered .residents' questions.

       Schedule for providing bottled water.  In January 1986,
       the residents using bottled water expressed concern about
       depleting their bottled water supply before EPA or NYSDEC
       would  resupply them.  EPA stopped providing bottled water
        in  1986 once the carbon filters were installed.  Since EPA
       has satisfied concerns about the effectiveness of the

-------
       carbon filters currently there is no requirement for EPA
       to supply bottled water.

       Concern about health effects from contamination.
       Residents were concerned about an expeditive cleanup of
       the American Thermostat site so that the plume of
       contamination does not spread and exposure is reduced.
       The remedy selected in the ROD will prevent exposure of
       the residents to contaminated groundwater.  The subsequent
       RI/FS planned by EPA for the site will, among other
       things, address possible methods of remediating the
       contamination at and around the site.

       Adverse economic impact from contamination.  Residents
       expressed concern about potential decrease in property
       values as a result of well contamination and the effect on
       employment because of the shut-down of the American
       Thermostat operation.

In addition to community interviews in January 1986 and a
Community Relations Plan, EPA issued a Public Notice on December
3, 1987 that summarized the preferred remedial alternative,
announced the availability of the Focused FS and PRAP for public
review and comment, and provided notice of the upcoming public
meeting.  The notice was published in the Catskill Daily Mail.
In addition, EPA developed a fact sheet that outlined the
remedial alternatives and described EPA's preferred remedial
alternative for the American Thermostat site.  This fact sheet
was distributed at the public meeting.

EPA conducted a public meeting on December 8, 1987 at the Greene
County Court House in Catskill, New York, to provide information
on the Focused FS and EPA's preferred remedial alternative, and
to provide an opportunity for interested parties to present
verbal comments and questions to the EPA.  Six local officials
and twelve residents attended this meeting, as well as three EPA
officials, members of EPA's contractor staff, and representatives
of NYSDOH and NYSDEC.

The comments and questions received* by EPA at the public meeting
are recorded in a full transcript of the meeting, which is
available for review at EPA's regional office in New York City,
NYSDEC'» office in Albany, New York, and the Greene County Court
House in Catskill, New York.

III.   SUMMARY OF MAJOR QUESTIONS AND COMMENTS RECEIVED DURING
       THE PUBLIC COMMENT PERIOD AND EPA'S RESPONSE TO COMMENTS

On December 3, 1987, EPA released the Focused FS and PRAP to
receive verbal and written comments from the public from December
3, 1987 until December 24, 1987.  This responsiveness summary
summarizes the significant concerns and issues raised during the

-------
public comment period and EPA's responses to those concerns.
These concerns and issues have been considered by EPA  in  the
final decision on the remedial alternative.

Verbal Continents

During the public comment period approximately twenty  verbal
comments were received at the public meeting; most dealt  with
public health protection and the proposal to expand the pipeline
capacity.  These comments are categorized by the following
topics.

A.     Health and safety,

B.     Nature and extent of contamination, and

C.     Preferred remedial alternative.


A.     Health and Safety
1.     congn^n.^ *  A local official asked if the public has been
informed of the nature and potential health effects of the
detected contaminants.

       EPA Response! . in 1981 NYSDOH informed the affected
residents of the potential health effects of using contaminated
water and advised residents not to use the water for cooking or
drinking purposes.  Furthermore, EPA has implemented a removal
action to maintain and install additional: carbon filters at seven
residences and an airlift stripping system at one residence to
mitigate the problem of drinking water contamination.
2.     CQfflfflfnt *  A resident inquired  if EPA had conducted a
health evaluation of the affected residents.

       EPA Response;  A risk assessment will be conducted by
EPA's contractor during the RI/FS for the second operable unit.
The Agency for Toxic Substances and Disease Registry  (ATSDR) will
prepare a health assessment based upon this document.
3.     CPlTBflnt *  A resident  inquired  if the quality of the
proposed alternative water source meets federal and state
drinking water standards.

       EPA Response:  Water  supplied  by the Catskill Water
District meets state and  federal standards and NYSDOH will
routinely monitor  to ensure  that the  proposed water supply
continues to meet  safe  drinking water standards.

4.     CQBTIf nfe *  A local  official asked if the carbon filters
installed at the affected residences  were proven  to provide a

-------
safe level of public protection from the contaminated water.

       EPA Response;  The carbon filters that were  installed at
seven of the affected residences have been proven to be effective
in removing contaminants.

5.     Comment ;  A local official inquired if future property
owners would be eligible to receive carbon filters  if additional
wells were drilled and contamination was detected.

       EPA Response;  In accordance with EPA policy, until the
remedy selected in the ROD is implemented, future property owners
would be eligible to receive carbon filters to treat contaminated
well water.  Once the waterline is installed, however, new
homeowners will have to hook up to the waterline at their own
expense .

B.     Nature and Extent of Contamination

1.     Comment ;  A local official inquired about the extent of
the contamination and how EPA defined the proposed  water supply
service area.                                     .

       EPA Response;  Contamination was found to extend a half
mile northwest ami a quarter mile southeast of the  American
Thermostat site and within the boundaries of Catskill Creek and
Route 23.  To determine the proposed water supply service area,
EPA estimated the potential area of contamination by projecting
the extent of contaminant migration after twenty years of
groundwater restoration efforts.  Based on these estimates, EPA
determined that the^ service area included all residents within
the boundaries of ' o'rie Trifle northwest and a half mile southeast of
the American Thermostat site and within Catskill Creek and Route
23.         -••^,^c  ;v  ,-^,.,^  _,.  ,:,v.^  .....-., ?i  ,  ..... .,.,

2.     Comment ;  One resident asked if -groundwater  contamination
will be removed.

       EPA Response:  A RI/FS will be conducted by  EPA to examine
the source, nature, and extent of tlie contamination and to
develop *«asurea_to clean up the American Thermostat site and
groundwater contraf fiat ion.  Based on the findings of this RI/FS a
remedial alternative may be selected to remove the  contaminants
from
3.     comment :  X' local  official  asked  if contaminants  were
detected  in  the  Catskill  Creek and where water samples were taken
at the creek.

       EPA Response;   Based on one sample taken in 1982  near  the
historical bridge  at  Leeds, contaminants have not been detected
in the Catskill  Creek.  Additional samples will be collected  by

-------
EPA during the upcoming RI/FS for the second operable unit.

C.     Preferred Remedial Alternative

1.     Cg]flfl?nt ;  One resident inquired about the number of
pipelines involved in implementing the preferred remedial
alternative.

       EPA Response;  The selected remedial alternative involves
the installation of one pipeline to provide a safe water supply
to the designated service areas.  Installation of a single
pipeline is efficient and can be quickly implemented to provide
the public with a safe potable water supply as quickly as
possible.

2.     Comment ;  A local official asked whether the preferred
remedial alternative can accommodate all properties within the
proposed water supply service area.

       EPA Response;  The selected remedial alternative will
accommodate all properties within the proposed water supply
service area.  A six inch diameter pipe has been determined by
EPA to provide a sufficient amount of water to the current
residents within the proposed water supply service area.

3.     £gjBmej2£:  A county official asked, who would operate and
maintain the proposed extended pipeline extension.

       EPA Response;  Pursuant to the Comprehensive Environmental
Response, Compensation and Liability Act. (CERCLA) the State of
New York is required "to provide for the operation and maintenance
of the system.  The specific arrangements regarding the operation
and maintenance of the system will have to be coordinated between
the state and local municipalities.
4 .     Comment -  A. resident inquired about the costs that may be
incurred by homeowners to implement the preferred remedial
alternative.

       EPA Response:  EPA (or the potentially responsible
parties) will assume  responsibility for all design and
construction  cost* of the selected remedial alternative  (the
state vill contribute 10 percent of the construction costs) . Once
the new pipeline is installed and homes are connected, EPA's
responsibilities do not extend  to the  additional usage and
maintenance expenses.  Further  expenses incurred by residents for
water usage would  be  determined by the water district.
 5.      C oimf n*^ ;   Several  local  officials expressed  support  for
 implementation of the preferred alternative.   These local
 officials wanted to know  whether it was possible  to increase  the
 size of the proposed pipeline to acconaodate  future development

                                 8

-------
in the Village of Catskill, and the Towns of Cairo, and Athens
and to provide fire protection.

       EPA Response:  EPA would support a proposal to increase
the capacity of the pipeline system 'to accommodate future
development and to provide fire protection.  However, EPA's
primary concern and responsibility is to quickly provide public
health protection to affected or potentially affected residents.
Also, EPA cannot assume the additional cost of the pipeline
expansion.  This additional cost would have to be borne by one or
more of the interested municipalities.  The provision of fire
protection for the potentially affected area is not required by
law.  However if the municipalities are willing to incurr the
incremental costs for fire protection, EPA would cover the costs
for partial fire protection such as the valves, hydrants, etc.
Furthermore, any commitment on their part to pay this incremental
cost would have to be made prior to the initiation of the
remedial design.

6.     Comment;  A local official asked if all the towns have
been informed of the request by the Village of Catskill to expand
the pipeline capacity.


       EPA Response;  Prior to the December 8th public meeting,
EPA representatives met with the Catskill Town Supervisor and
were informed of the request by the Town of Catskill to expand
the pipeline capacity beyond what is proposed in the Focused FS.
EPA is willing to arrange another meeting with interested parties
to discuss the request to increase the pipeline capacity.

7.     Comment ;  A resident inquired when EPA would need an
agreement among the towns to assume responsibility for the
additional costs of expanding the pipeline to accommodate future
development.

       EPA Response;  The detailed design of the remedial
alternative is scheduled to start in March 1988 and an agreement
from the towns must be reached before the design is started.
8.     egpnji^n-fc •  A local official inquired about the time period
involved in completing the design of the preferred remedial
alternative and when construction would begin.

       BPA Response;  The design of the selected remedial
alternative is scheduled to take three to four months to complete
and the construction is proposed to be funded in Fall 1988.

Written
Three letters with  approximately thirty comments were received by
EPA during the public  comment period; most involved technical

-------
questions and stressed the need to timely inform the appropriati^
agencies and municipalities and residents.  The following letters
were received by EPA from the Greene County Planning Department,
the Village of Catski11 Board of Trustees, and a resident, and
are attached as Appendix One.

 RESPONSES  TO COMMENTS  FROM  THE  GREENE  COUNTY  PLANNING DEPARTMENT
                  IN LETTER  OF DECEMBER 16.  1987
1.     Comment:  Would greatly appreciate being supplied a
transcript of the December 8th meeting as soon as it becomes
available.

       EPA Response;  A copy of the transcript and a copy of the
Responsiveness Summary will be made available at the information
repositories established for this site.  The information
repositories are located at the following addresses:

                 Greene County Court House
                 County Clerk's Office
                 P.O. Box 446
                 Main Street
                 Catskill, New York  12414

                 New York State Department of
                 Environmental Conservation
                 50 Wolf Road
                 Albany, New York  12233

                 U.S. Environmental Protection Agency
                 Emergency and Remedial Response Division
                 26 Federal Plaza
                 New York, New York  10278

2.     Comment*  There are several companies interested in
locating at the site, however, I am still not clear as to when
the site will be available for use.  I would appreciate being
informed of other additional considerations which may be of
concern in regard to the future use of the site.

       EPA Response;  The reuse of the American Thermostat site
will depend on the requirements of the second operable unit,
cleanup of the site.

During the remedial investigation planned to commence in January
1988, EPA will determine the nature and the extent of the
contamination at and around the site.  At the completion of this
study, EPA will be better able to discuss concerns about the
possible future use of this site.  Measures need to be taken to
provide a safe water supply for future use at the American
Thermostat site.  ""'"       -.*  •

                                10

-------
3.     g9flffllfn^:  Although I was very pleased to hear of a
solution close at hand, I was taken back by the inadequacy to
properly inform the appropriate municipalities of the
proposal(s).

I hope tl»t as you near a decision on a water supply alternative,
that better communication be had between your agency and those
having an interest here in Greene County.

In light of the fact that EPA's preferred alternative 4A-3 would
withdraw water from the Village of Catskill supply, I fail to
understand why the local authorities have not been fully informed
of your agency's proposal.

       EPA Response:  A public notice, which is required under
the Superfund Amendment and Reauthorization Act (SARA), was
published in the Catskill Daily frail announcing the date,
location, and time of the public meeting.  EPA's preferred
remedial alternative and the 21-day public comment period to
review the Focused FS were also announced in the public notice.
In addition, the concerned municipalities were notified about the
public meeting.  Futhermore, EPA and its contractor consulted the
Village consulting engineer during the months preceding the
issuance of the Focused FS.

EPA believed that all .of the"appropriate parties were contacted.
We regret any misunderstandings that may have resulted.  At this
time, all of the appropriate agencies and municipalities have
been contacted by EPA and it is EPA's intent to work jointly with
these municipalities and agencies to expedite the implementation
of an alternate water supply.

During preparation of the Focused Feasibility Study Report, EPA's
contractor contacted the following interested agencies.

                      MYSDEC

                      NYSDOH        -v. _,...<:o,.

                a*    Cairo Planning Board

                 •    Greene County Highway Department

                      NYSGS, UGS

                      Potic Reservoir Water Treatment Plant

                      Village of Catskill Department of Public
                      Works

                      Village of Catskill Offices

                                11

-------
                      Greene County Tax Office

                      ISO Commercial RiaK Services, inc.

                      Consulting Engineer for Village of catsKill,

4.     Confflint:  According to a newspaper article, the village of
Cat skill water supply system does not have the capacity to
withstand additional vithdrawls proposed by several future
projects, including a 400 room hotel, expansion of a nursing home
and a townhouse development project.

       EPA Raanon««!  The provision of water for this project
requires about 3 percent of the total system capacity and
therefore has a very minor impact on the Village of Cat ski 11
water supply system.

EPA was informed of a proposal to construct a 400 unit hotel but
the project was defeated.  EPA is not aware of any other proposed
projects.  Based upon available data, the water supply system has
been calculated to provide enough water to accommodate both the
proposed service area and projected growth in the present water
district.

S.     £gjDBftn£:  According to EPA schedule of events,  any
response to your proposal would be required almost immediately.
This sinply does not provide local and county governments enough
tine to accomplish the many tasks involved in preparing a
thorough response.

       EPA Reaponse!  in accordance with SARA, a public comment
period was established for 21 days after the release of the
Focused ta and EPA's preferred alternative for public review and
comment.  An independent assessment may be conducted to
facilitate an agreement, if the Village and EPA deem necessary.

        RESPONSES TO COMMgJfPS  PROM THE VILLAQE OP
                               F TRUSTEES
                  IN LETTER Q   EBER 16-  1987
1,     comment i  In reference to Figure 1-3 in the Focused FS the
septic tank absorption field is not an absorption field, it is a
sand filter with the treated effluent discharging to Tributary A o

       gpi g««t*m«rtt  The error is noted.

2 .     eoamenti  The present reservoir is inadequate to meet the
existing deaand in drought periods.  How will the reservoir
capacity be increased?  Present regulations are for a 100-year
safe yield; the Village supply has gone dry twice in the last 30
years.

                                12

-------
       SPA Rf SPCnt* :  The projected additional demand based on
population and maximum expected flow will only be approximately -
percent of the total capacity of the system.  Any supplemental
water sources used during a drought by the existing water supply
district should be applicable to the proposed service area.

3.     conaent t  The present filters will be inadequate to meet
the increased demand; the two filters which were not rebuilt in
the recent rehabilitation will have to be rebuilt.

       SPA Responses  The two filters will not be needed to
supply the projected additional demand, which will only be about
3 percent of the total system capacity.

4.     gomnanti  There is a question by the U.S. Corps of
Engineers about the safety of the Potic Oam. This must be
addressed.  The design is done, but there are no funds for the
rebuild.  If the reservoir water level has to be dropped for
safety reasons, there will be no water for the project.

       EPA Raaponsa!  The potential impact of lowering the
reservoir water level for safety reasons' will be evaluated during
the design phase.

5.     £ojua«nt:  An increased demand of icr percent of present
usage has already been requested within the present water
district, part of which has been approved (part of the increased-
demand request 1* for an existing health related facility) .
There will be a meeting February 1, 1988,  for all concerned
parties to submit comments on their future water usage requests
from- the Catsklll water supply.      -       -

       EPA Raaponaa;  The projected additional demand associated
with supplying water to the affected and potentially affected
residents is expected to be only y percent of the total capacity
of the system.  Based upon available data, the water supply
system has been calculated to .provide enough water to accommodate
both the proposed service area and the projected growth in the
present water district.  An independent assessment may be
conducted to facilitate an agreement, if the Village and EPA deem
necessary.       "               •••.<••
6.     CpmtnV  Tn* previous secondary pumping source used in
the two drought periods can no longer be used; a secondary source
must be developed prior to approval. ~Thl*r secondary source must
be acceptable to all concerned agencies and the water purveyor.
           RMponaat  Development of a new secondary source is
the responsibility of the Village of cat skill.
                                13

-------
7.     cytmienti•  Table 2-2 in the FS does not allow a proper to!
schedule foe- State Environmental Quality Review Act (SEQRA),
Water Supply Application (WSA) review, and possible approval by
the Catski11 Village Board.  Since a WSA Permit is required/ the
SEQRA process is initiated.

       EPA Response;  EPA, NYSDEC, and NYSDOH are each working to
provide an alternate water supply to the affected and potentially
affected residents in a timely manner.  To reach this goal, EPA
anticipates that all necessary permit reviews and approvals can
be performed and obtained expeditibusly.

8.     Comment:  The entire project must not produce a financial
burden upon the existing water purveyor, including costs of fire
protection, legal, technical, and administrative review of the
project on local and state levels; construction costs; inspection
costs; and operation and maintenance.

       EPA Response;  EPA does not anticipate this project
placing a significant financial burden on the local
municipalities.  The construction costs will be paid for by EPA
and the New York State Department of Environmental Conservation
(or by the Potentially Responsible Parties).  Pursuant to CERCLA,
the State is required to assure the payment of all operation and
maintenance costs before remedial construction can proceed.  If
the local municipalities wish to have the water supply system
provide fire protection, a portion of the incremental costs-
involved will have to be borne by the municipalities, as
indicated in the ROD.

9.     Comment;  Comments by the New York State Department of
Health during the SEQRA, WSA process—which will not be available
by December 23, 1987—will be required for review by the Village
of Catskill prior to considering all concerns for the proposed
approval.  The involved state agencies did not appear at the
public hearing because the public hearing was premature.

       EPA Response;  Both NYSDEC and NYSDOH officials were
consulted during the preparation of the Focused FS.  Furthermore,
representatives of both state agencies attended a meeting with
the Town Supervisor on December 8, 1987 and participated in the
public meeting held that evening.  EPA expects both state
agencies to remain actively  involved during the implementation of
this remedial action.

10.    Comment:  The Village of Catskill requests a scoping
session for all concerned agencies to define under the SEQRA the
environmental issues to be addressed.  The lead agency must be
acceptable to the Village of Catskill and under the SEQRA
regulations must be one of the permit-issuing agencies.


                                14

-------
       EPA Response:  The potential environmental concerns
associated with implementing each alternate water supply scenario
were evaluated in the Focused Feasibility Study,  it is EPA's
intent to meet with all concerned agencies prior to the start of
the design of the selected alternative.

11.    Comment ;  Alternative 4A-3 has the longest pipe line,
almost twice that of the other alternatives, with resultant
greatest potential for failure.  The length of pipe should be
reduced to a minimum.

       EPA Response:  Based on effectiveness, implementability,
and cost, alternative 4A-3 was selected by EPA as the preferred
alternative after a comprehensive evaluation was conducted. The
many concerns raised by residents and local and county officials
have been considered by EPA and have been incorporated into the
ROD.  The selected alternate water supply remedy involves exten-
sion of the Catskill Water District pipeline to the affected
areas.  Following discussions with the local agencies, the
specific route for this pipeline will be selected during the
design phase.
12.    T9I^ffl?ntl ;  In view of the deficiencies of the Potic
reservoir and filtration system, the alternatives eliminated from
detailed evaluation, specifically, items 2 and 11 in Table 2-10
of the Focused FS, should be re-evaluated.

       EPA Response;  The detailed evaluation of each alternative
is presented in the Focused Feasibility Study report.  As
discussed in the report, Alternative 2A (Operations and
Maintenance of Existing and Additional Point-of-Use Treatment
Systems) was eliminated since it fails to provide a reliable and
permanent remedy.  Alternative 4B (New Surface Water Source and
Treatment System) was eliminated since it was unreliable,
unproven, and would require complex construction and operation
and maintenance.
13.    Comment ;  A booster pumping station is an excessive
operating cost item for the cost of energy and an unnecessary
high-maintenance item.  A larger pipe with gravity flow is
preferred, even if a water tower must be installed to provide a
fire surge reserve or peak demand.  The highest affected
residence in the potential plume area appears to be at
approximately 300 feet; the clearwell head is about 400 feet,
allowing a gravity static pressure exceeding 40 psi.  Every
effort should be made to eliminate pumps and a pumping station.

       EPA Response;  A pumping station was included to overcome
the frictional losses resulting from the 6-inch diameter
pipeline.  If a 12-inch diameter pipeline were to be used, as
described in the fire protection scenario, it may be possible to
use an elevated water storage tank and thereby eliminate the need

                                15

-------
for a pumping station.  However, the difference in cost
for using an. increased diameter will have to be paid by the
municipalities concerned.
14.    C.QTmafl5 ;  Assuming an annual operation and maintenance
cost of 100,000 (Table 4-8 in the Focused FS has a low of $99,600
to a high of $200,120), the operation and maintenance spread over
the 23 homes is $4,348/year per home; spread over 80 homes is
$l,250/year per home.  This is excessive; who will pay this
amount to operate the water district?  What will these costs be
to the user in 30, 40, and 50 years from now?  What control will
the water purveyor have over the operation and maintenance?

       EPA Response;  A more accurate estimate of the operations
and maintenance costs will be developed during the detailed
design.  As stated above, under CERCLA, the State must assure
payment of all operations and maintenance costs.  Specific
arrangements regarding payment for and performance of the
necessary operations and maintenance will have to be worked out
by the State and the local municipalities concerned.

15.    Comment:  Alternative 4D - Extension of the mobile home
park water supply:  This is a private supply.  Have the owners of
the park been consulted on possible purchase of their water
supply?  There does not appear to be a cost included in the
estimates for purchase of the private systems.  What will the
effect of any pumping be on the pollution plume?

       EPA Response:  If this alternative was selected,
negotiations with the owners would be held during the detailed
design.  Since it was not selected, the effect of pumping on the
contaminant plume was not determined.

16.    Comment:  The water district will include the entire
length of the pipe.  What are the implications and possible
demands of future requests for water and possible developments
along the pipe line?  This must be addressed.

       EPA Response:  The development of an alternate water
supply under CERCLA does not address future growth.  If the local
community desires to  increase the service area, the community
will have to bear the incremental cost.

17.    C Q.TBBtn't ?  The present water district outside of the
Village over which the transmission line traverses pays taxes to
the towns and  school districts.  What are these taxes for the new
district?  They are not  figured into the cost estimates.  The
longer line in the recommended alternative will pay much higher
taxes than the shorter line.

       EPA Response;  The Village's concern regarding higher
taxes associated with Alternative 4 A- 3 will be taken into accoun

                                16

-------
by EPA when it makes a decision during the design phase  regarding
the specific route of the water line.

18.    C7mn?nt ;  Since the Superfund will fund only the  cost of
the original 23 affected hones, who will pay for subsequent homes
affected by the plume in future years?

       EPA Response:  EPA and the State will pay for the hookup
of all of the affected and potentially affected homes that are to
be hooked-up to the waterline.  However, if new construction
should occur within the affected area after the new water
district is formed and the waterline is installed, the new
homeowners will be required to hook-up to the waterline  at their
own expense.

19.    Comment ;  The eminent domain issue for obtaining  right-of-
ways... has not been addressed.  The Village of Catskill does not
have eminent domain rights outside of the Village.  This must be
clarified.

       EPA Response:  The Greene County Highway Department has
been contacted regarding access to county roads and a sample of
the appropriate permit application has been included in Appendix
D of the report.  Final approvals will be acquired during the
detailed design and construction.
20.    Comjreurt ;  The water rates •proposed and shown in the cost
estimate do not appear to be realistic; this must be addressed.

       EPA Response;  These water rates are preliminary and are
based on current data provided by the Village of Catskill in
October, 1987.  The rates were converted from the District's
quarterly charge per thousand cubic feet of water to a price per
thousand gallons.
21.    C?lPTO?n^ ;  Looking at present and projected costs, would it
be cheaper to relocate the affected homes?  This option should be
explored; it would reduce the risk of other environmental hazards
such as the cancer cases reported in the Catskill Daily Mail.

       EPA Response:  The objective of the Focused  FS was to
develop an alternative water supply system for the  affected and
potentially affected  residents.  It is EPA's  intention to address
the contamination at  and emanating from the American Thermostat
site during the RZ/FS of this project.  Therefore,  EPA presently
does not  feel that it would be appropriate to simply relocate the
affected  residents and not attempt to clean up the  contaminated
area .

22.    comment:  The  Village of  Catskill is to directly receive
copies of all technical information, letters, comments, etc.,
associated with this  project.  The present repositories for

                                17

-------
records are not acceptable to the Village of Catskill; the
Village offices are to be a repository.
                                 ..-,•: N5
       EPA Response;  Technical report* concerning the site are
available at the established information repositories.  EPA
selected the location of this information repository based on
suggestions made during community interviews.  EPA will consider
relocating the local information repository to the Catskill
Village office, if it is deemed more convenient for the
community.


        RESPONSES TO COMMENTS BY DOROTHY AND RICHARD LAIS
                  IN LETTER OF  DECEMBER 22.  1987


1.     Comment;  Alternatives 4A-1, 2, and 3 are the safest and
most practical if an adequate water supply is available to
service the affected and potentially affected homes, and if the
Village of Catskill agrees to extend the water district.

       EPA Response;  The projected additional water demand
associated with extending the Catskill Water District waterline
based upon the population and maximum expected flow is expected
to be only 3 percent of the total capacity of the system.  EPA
would like the Village of Catskill's support to extend the
pipeline and establish a water district, in order to quickly
provide an alternate water supply to the affected and potentially
affected residents.

2.     £gjy&eji£:  In September of 1987, Senator Moynihan released
$6.75 million  of EPA funds to be used at the American Thermostat
site in 1988.  We trust this means a sincere effort will be made
to remediate the site.

       EPA Response;  Funds under Superfund to initiate a
remedial  investigation/ feasibility study at the American
Thermostat site were recently obligated.  This RI/FS will, among
other things,  evaluate possible methods of cleaning up the site.

3.     £ojBBfin£:  We feel that six days notice about the December
8, 1987 meeting, and the deadline of December 24, 1987 for
comments  on the preferred  alternative, combined with an
inaccurate, incomplete mailing list shows insensitivity to the
affected  and potentially affected community.

       EPA Response;  According to CERCLA, notification of a
public meeting and  a public comment period, including an
announcement of the availability of a  feasibility study report,
must be given  when  the report  is made  available.  Once the
Focused ?s  for the  American Thermostat site was  finalized, a
meeting announcement was sent to all those  interested residents,

                                18

-------
local officials, the media and state officials on our mailing
list.  The names and addresses of all official group
representatives and residents who should receive regular
information about the site are included in our mailing list,
which is -revised periodically.  A public notice, as required now
under SARA was also published in the legal section of The
Catskill Daily Mail, on December 3, 1987 which indicated the date,
time, and location of the meeting, provided notification of the
21 day public comment period and specified a preferred
alternative for providing an alternate water supply,  in
addition, follow-up telephone calls were made to ensure that
interested residents were well informed of the scheduled meeting,
availability of the report and the 21 day public comment period.

IV.    REMAINING CONCERN

The only remaining concern among residents is whether the
American Thermostat facility will be restored for future use and
development.              "'
                                19

-------
APPENDIX

-------
    GREENE  COUNTY               .            Telephone (518)622 325
    PLANNING   DEPARTMENT                  RONALDM  ROTH D!e
    Greene County OHice Building
    Rt. 3, Box 909
    Cairo. New York 12413
                                              December 16, 1987
 Mr.  Peter  Acker,  Remedial Project Manager
 US Environmental  Protection Agency,  Region II
 26 Federal Plaza
 New York,  NY 10278

 Dear Mr. Acker:

 Let me first take an opportunity to express my gratitude for the work
 you have done in  regard to the American .Thermostat Superfund Site in
 Greene County, NY.  I attended.the evening meeting on December 8th
 and was pleased to be informed of EPA's progress in securing a safe
 water supply for  the affected residents.  Your focused-attention is
 especially reassuring in light of the seriousness of the problem.

"In addition 1 would also like to express several thoughts and comments
 in response to the proceedings of the above mentioned meeting.

 First, I iwould greatly appreciate being supplied with a transcript of
 the December 8th meeting *s soon, as it becomes available, -in the mean-
 time, 1 would  like to request a- more immediate response to a few other
 concerns  I have in regard  to the discussion at the public meeting.

 One of my concerns relates to a  specific question raised at the Beet-
 ing regarding when the American Thermostat site could be reoccupied
 by another company.  At  present, there are several companies inter-
 ested in  locating at the site, however, I am still not clear as to when
 the site will  be available for use.  Such as it is, I would appreciate
 you clarifying this matter.  I would also appreciate being informed of
 other additional considerations which may be of concern  in regard to
 the future use of the site.

 Another concern relates  directly to your proposal(s) to supply affected
 residents with a  clean,  potable  water source.  Although  I was very
 pleased to hear of a solution close at hand, I was taken back by the
 inadequacy  to  properly  inform  the appropriate agencies and municipali-
 ties  of the  proposal(s).   If appropriate contact  had been made, I feel
 better preparation  to respond  to the study could  have been attained.

 I would hope that as you near  a  decision on a water supply alternative
 that  better  communication be had between your agency and those having
 an interest  here  in Greene County.  This  lack of  communication will only
 lead to misinformation  and possible delays  in finding solutions to the
 problem.

-------
                               -2-
            •
As a case in point,  I am aware of a potentially  significant  problem
which will  likely have a bearing on several proposals  that  require
water withdrawal from the Village of Catskill supply.   I  have en-
closed a newspaper article which sites the Village's concern over
an already  over-stressed water supply.  According  to the  article,
the Village of Catskill water supply system does not have the capa-
city to withstand additional withdrawals proposed  by several future
projects, including  a 400 room hotel, expansion of a nursing home,
and a townhouse development project.

In light of the fact that EPA's  preferred alternative  (4A-3) would
withdraw water from  the Village of Catskill supply, I  fail  to under-
stand why the  local  authorities have not been fully informed of your
agency's proposal.   This is especially disturbing  when  a  final de-
cision on an alternative water supply is scheduled to  be  made in a
few short months.              • •.-£*".             - •--'•"

Unfortunately, according to your schedule of events, any  response to
your proposal would  be required almost immediately.  This simply
does not provide  local and county governments with the  time  required
to accomplish  the many tasks  involved in preparing a thorough response
The Greene County  Planning Department also has a deep  interest  in
American Thermostat  situation.  The Planning Department  is prepared  to
respond to the proposals  discussed at the meeting;  however,  to  do so
responsibly the Department must be kept up-to-date  on  any new develop-
ments and information.  Therefore, it is imperative to keep  the lines
of communication open in  order  to guarantee the quickest and most suit-
able  solution to the problem.

 In light of this,  I  am still encouraged by the proceedings of the pub-
 lic meeting and look forward to working with you  in the  future. There-
 fore, if I may be of further assistance, please  feel free  to contact me

                                           Sincerely,
                                            Albert Flick
                                            Planner  ,/ + •.
 AF:mc
 encl.

-------
ATTORNEY FOR VILLAGE
    Robert Carpenter
""TE-^^.                  -*-45^  "
-------
Mr. Peter J. Acker, Project Manager      - 2 -                December 16,
  (4)  There is a question by the U. S. Corps of Engineers as to the safety
      of the Potic Dam, which must be addressed.  The design is done,  but
      there are no funds for the rebuild.  If the reservoir water level
      has to be dropped for safety reasons, there will be no water for the
      project.

  (5)  An increased demand of 10% of present usage has already been requested
      within the present water district, part of which has been approved
      (part of the increased-demand request is for an existing health
      related facility).  There will be a meeting February 1, 1988, for all
      concerned parties to submit comments on their future water usage re-
      quests from the Catskill water supply.

  (6)  The previous secondary pumping source used in the two drought periods
      can no longer be used; a secondary source must be developed prior to
      approval.  This secondary source must be acceptable to all concerned
      agencies and the water purveyor.

  (7)  Table 2-2 does not allow a proper time schedule for SBQRA, Water
      Supply Application review, and possible approval by the Catskill Village
      Board.  Since a NBA Permit is required, the SBQRA process is initiated.

  (8)  The entire project must not produce a financial burden upon the
      existing water purveyor, including costs of fire protection; legal,
      technical, and administrative review of the project on local and state
      levels; construction costs;  inspection costs; and operation and
      maintenance.

  (9)  Comments by the New York State Department of Health during the SBQRA,
      NBA process—which WILL NOT  be available by December 23, 1987— will be
      required  for review by the Village of Catskill prior to considering
      all concerns for the proposed approval.  The involved state agencies
      did not appear at the public hearing because the public hearing was
      premature.

 (10)  The Village of Catskill requests  a scoping session for all concerned
      . agencies to define under the SBQRA the environmental  issues  to be
       addressed.  The lead.agency  must  be acceptable to the Village of
       Catskill and under the SBQRA regulations must be one of  the permit-
       issuing agencies.

  (11)  Alternative 4A-3 has the longest  pipe line, almost twice that of the
       other alternatives,  with resultant greatest potential for failure.
       The length of pipe should be reduced to a minimum.

-------
Mr. Peter J. Acker, project Manager      - 3 -                December 16, 1967
 (12)  In view of the deficiencies of the Potic reservoir and filtration
      system, the alternatives eliminated  from detailed evaluation, Table
      2-10—namely, items 2 and  11—should be re-evaluated.

 (13)  A booster pumping  station  is an excessive operating cost item
      for the cost of energy and an unnecessary high-maintenance item.
      A larger pipe with gravity flow is preferred, even if a water
      tower oust be installed to provide a fire surge reserve or peak
      demand.  The highest affected residence in the potential plume area
      appears to be at approximately 300 feet; the clearwell head is about
      400 feet, allowing a gravity static  pressure exceeding 40 psi.
      Every effort should be made to eliminate pumps and a pumping station.

 (14)  Assuming an annual operation and  maintenance cost of $100,000 (Table
      4-8 has a low of $99,600 to a high of  $200,120), the O 4 M spread
      over the 23 homes  is $4,348/year  per home; spread over 80 homes is    .;
      $l,250/year per home.  This is excessive; who will pay this amount
      to operate the water district?  What will these costs be to the user
      in 30, 40, and 50  years from now? What control will the water pur-
      veyor have over the operation and maintenance?

 (15)  Alternative 4D - Extension of the mobile home park water supply:
      This is a private  supply.  Have the  owners of the park been consulted
      on possible purchase of their water  supply?  There does not appear
      to be a cost included  in the estimates for purchase of the private
      systems.  What will the effect of any  pumping be on the pollution
      plume?

 (16)  The water district will include the  entire length of the pipe.  What
      are the  implications and possible demands of future requests for water
      and possible developments along the  pipe line?  This must be addressed.

 (17)  The present water  district outside of  the Village over which the trans-
      mission  line traverses pays taxes to the towns and school districts.
      What are these taxes  for  the new district?  They are not figured into
       the cost estimates.  The longer  line in the recommended alternative will
      pay much higher taxes  than the shorter line.

 (18)   Since the Super fund will  fund only the cost of the original 23 affected
      homes, who will pay for subsequent homes affected by the plume  in future
       years?

 (19)  The eminent domain issue for obtaining right-of-ways—if the right-of-way
        is not given—has not been addressed.   The Village of Catskill does not
       have eminent domain rights outside of the Village.  This must be
        clarified.

-------
Mr. Peter J. Acker, Project Manager      - 4 -                December 16, 196
 (20)  The water rates proposed and shown in the cost estimate do not appear
      to be realistic; this must be addressed.

 (21)  Looking at present and projected costs, would it be cheaper to relocate
      the affected homes?  This option should be explored; it would reduce
      the risk of other environmental hazards such as the cancer cases reported
      in the Cat ski 11 DAILY MAIL.

 (22)  The Village of Cat ski 11 is to directly receive copies of all technical
      information, letters, comments, etc., associated with this project.
      The present depositories for records are not acceptable to the Village
      of Cat skill;  the Village offices are to be a depository.


 The Village of Cat ski 11 Board of  Trustees realize the health problems and water
 supply problems within  the  polluted area.  The  Board is  responsible  to  the
 approximately 8,000  existing users of  the  Catskill water system  and must
 'COMPLETELY assured that any  additional  load  on the  system will not
 costs of operation  and  maintenance and  that  there will be  a continual
 source of  potable water.  When all concerns by all  the  involved agencies and
 the  Board of Trustees  have  been addressed to the  Board's  satisfaction,  the
 Board will then consider approval of connection to the proposed water district.


                                                   Very truly yours,

                                                   VILLAGE OF CATSKILL
                                                   Michael  Battagl
                                                   President
 cc:  Robert 2. Carpenter, Esq.
      Mr. S. Lawrence Baldwin, P.E.
      Mr. J. D. Rusack, P.E.
      Mr. Gilbert Faustel, P.E.
      Mr. Jeffrey Sama, P.E.
      Mr. Neil Gaevers, EBASCO

-------
                     TEXAS WATER COMMISSION
                                 -     .
Paul Hopkins. Cheirman                  - - "^ •' /j          J. D. Head. General Counsel
John O. Houchins. CGrr.missioner             \:.'.-**•'.:/           Michael E. Field, Chief Examiner
B. J. Wynne. III. Ccrr.missiorier                 ^==^'            Karen A. Phillips, Chief Clerk

                           Allen Beinke, Executive Director


                           March  18,  1988
       Dr. Allyn M.  Davis
       Director, Hazardous Waste Management Division
       U.S. Environmental Protection  Agency
       Region VI (6H)
       1445 Ross Avenue
       Dallas, TX 75202

       Re:  Industrial Transformers Superfund Site
            Draft Record of Decision

       Dear Dr. Davis:

       We have reviewed the proposed  Record of Decision (ROD) for
       the contaminated soils  (Operable Unit I) at  the Industrial
       Transformers  Superfund  Site.   We have no objection to the
       selected remedy as described in the draft ROD.   The selected
       remedy for the  site includes treatment of soils contaminated
       with polychlorinated biphenyls (PCBs) above  the cleanup
       criterion using chemical dechlorinization.

       Sincerely,
       Allen P. Beinke
       Executive  Director

       GT/mem
               C .... - , . . ;-," N .--.- :•-.-.< A-.t

-------