EPA/ROD/R02-95/245
                            August 1995
EPA  Superfund
       Record of Decision:
       Carroll & Dubies Sewage Disposal,
       Port Jervis, NY
       3/31/95

-------
             DECLARATION FOR THE RECORD OF DECISION
SITE NAME AND LOCATION

Carroll and Dubies Superfund Site
Town of Deerpark, Orange County, New York

STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action for
the Carroll and Dubies Superfund Site  (the Site),  which was
chosen in accordance with the Comprehensive Environmental
Response, Compensation, and Liability Act  (CERCLA) of 1980, as.
amended, and to the extent practicable, the National Oil and
Hazardous Substances Pollution Contingency Plan (NCP).   This
decision document explains the factual and legal bases for
selecting the remedy for this Site.  The information supporting
this remedial action decision is contained in the administrative
record for this Site.  The administrative record index is
attached  (Appendix III).

The New York State Department of Environmental  Conservation
 (NYSDEC) concurs with  the selected remedy as per the attached
letter  (Appendix IV).                        .        '       .

ASSESSMENT OF THE SITE

Actual or threatened releases of hazardous-substances from this
Site, if not addressed by implementing the response  action
selected in this Record of Decision  (ROD), may  present a  imminent
and substantial  endangerment to public health,  welfare, or the
environment.

DESCRIPTION OF THE SELECTED REMEDY

This operable unit  (OU1) represents  the  first of  two operable
units planned for the  Site.  This operable unit addresses, the
 source  areas  (lagoons  and surrounding impacted  soils) at  the Site.
 and actions needed to  ensure that  the source  areas  do not pose  a
 threat  to human  health or the  environment,  including any
 potential cross  media  impacts  to  groundwater.   The  second
 operable  unit  (OU2), which  is  currently in progress, will further
 characterize the fate  and transport  of the contaminants  emanating
 from the  Site and will serve  as the  basis for the decision on  a
 final  groundwater remedy.

 The major components of the selected remedy include:

     o  Excavation  of  all materials.from lagoons  1,  2,  3, 4,  6, 7
     and 8,  as  well  as the  soils in the vicinity of those
     lagoons, which exceed  the excavation levels  specified in the

-------
    Selected Remedy  section of the Decision Summary,  EPA's
    current estimate of the volume of the materials requiring
    excavation  is  approximately 20,300 cubic yards  (cy) .
    However, the actual volume will be further determined during
    the  implementation of the remedy.

    o  Treatment of  excavated soil/sludges which contain organic
    constituents above the treatment levels specified in the
    Selected Remedy  Section of the Decision Summary  (estimated
    at 13,800 cy)  via on-Site ex-situ vapor extraction.

    o  Additional  treatment of lagoon 7 soils/sludges  (estimated
    at 3,400 cy) via on-Site ex-situ bioslurry  (treatment
    targeted primarily for semi-volatile contaminants) .

    o  Stabilization/solidification of soils/sludges which  fail
    the  Resource Conservation and Recovery Act's Toxicity
    Characteristic Leaching Procedure  (TCLP) for inorganic
    constituents  (estimated at 5,700 cy) .

    o  Placement of  treated and untreated soils/sludges in  a
    lined and  capped cell consistent with modified requirements
    of New York Code of  Rules  and Regulations Part 360.  The
    base of the cell will consist of a high density polyethylene
     (HDPE)  liner and a sand  drainage  layer.  The cell  will  be
    sloped to  a leachate collection  system.  The cap will
    consist of'a low-permeability clay  layer, an HDPE  membrane,
    a sand drainage layer and a  topsoil  cover layer.

    o  Development of an air-monitoring  system  and installation
     of  air pollution control equipment  to  ensure  compliance with
     air pollution control regulations;  and

     o .Recommendations that deed and well  restriction's be
     imposed to protect the integrity of the cap.

Although the use of  the bioslurry process to treat lagoon 7
materials appears to be a promising means of treating the semi-
volatile organics,  further treatability studies  are necessary to
demonstrate that this process can reduce the complex mix of
constituents in lagoon 7 to remediation goals.   Because of the
existing uncertainty, a contingency remedy will be implemented if
treatability study results indicate that bioslurry will not be
effective in reducing the levels of contaminants in lagoon 7
materials, particularly semi-volatile contaminants, to
remediation goals.   The major components of the contingency
remedy are  identical to those of the selected remedy with the
following exception:

     Excavation and  off-Site treatment  (as necessary)  and
     disposal of lagoon 7 materials at a RCRA (Subtitle C)
     permitted  treatment,  storage and disposal  facility;  it  is
     assumed that  thermal  treatment, i.e.,  incineration or  low
     temperature thermal  treatment, will* be necessary  to reduce

-------
     the contaminants to appropriate Land Disposal Restriction
     (LDR)  levels.

STATUTORY DETERMINATIONS

The selected remedy and contingency remedy are protective of
human health and the environment, comply with federal and state
requirements that are legally applicable or relevant and
appropriate to the remedial action and are cost-effective.  The
selected remedy and contingency remedy utilize permanent
solutions and alternative treatment technologies to the maximum
extent practicable and satisfy the statutory preference for
remedies that employ treatment that reduces toxicity, mobility,
or volume as a principal element.  Because the selected remedy
and contingency remedy will necessitate restrictions on the use
of the site, a five-year review will be required to ensure the
integrity of the containment system.
Jeanne M.  Fox,/"
Regional Adrtrfnistrat

-------
              DECISION SUMMARY

      Carroll  and Dubies  Superfund Site
              Town of Deerpark
           Orange County,  New York
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY.
                  Region II
             New York, New York

-------
                        TABLE OF CONTENTS
SITE NAME, LOCATION AND DESCRIPTION	1

SITE HISTORY AND ENFORCEMENT ACTIVITIES	2

HIGHLIGHTS OF COMMUNITY PARTICIPATION	  .  3

SCOPE AND ROLE OF OPERABLE UNIT	3

SUMMARY OF SITE CHARACTERISTICS	4

SUMMARY OF SITE RISKS	8

REMEDIAL ACTION OBJECTIVES  	   11

DESCRIPTION OF REMEDIAL ALTERNATIVES 	   12

SUMMARY OF COMPARATIVE ANALYSIS  OF ALTERNATIVES	17

SELECTED REMEDY		  22

STATUTORY DETERMINATIONS  	 27

DOCUMENTATION OF  SIGNIFICANT  CHANGES	32


ATTACHMENTS

APPENDIX  I.     FIGURES
APPENDIX  II.    TABLES
APPENDIX. III.   ADMINISTRATIVE RECORD INDEX
APPENDIX  IV.    STATE LETTER OF CONCURRENCE
APPENDIX V.     RESPONSIVENESS SUMMARY

-------
SITE NAME, LOCATION AND DESCRIPTION

The Carroll and Dubies Superfund Site (the Site)  occupies
approximately 3 acres in the Neversink Valley, just northeast of
the City of - Port Jervis on Canal Street in the Town of Deerpark,
Orange County, New York  (see Figure 1) .  The Site is occupied by
an office building and a garage.  The waste disposal areas at the
Site include seven lagoons.  Several automobiles from previous
salvage operations have been abandoned on-Site.  Numerous
portable toilets are also stored on-Site.

The northwest boundary of the Site is formed by the valley wall,
which consists of exposed bedrock with talus comprising .the base.
The southeast boundary and a portion of the northeast boundary of
the Site are formed by remnants of the former Delaware and Hudson
 (D&H) Canal and towpath.  The remainder of the northeast property
boundary is formed by the valley wall arid an active sand and
gravel quarry.  Adjacent to the southern boundary of the Site is
the City of Port Jervis Landfill.  The landfill is no longer
active; however, Orange County currently operates a solid waste
transfer station on a portion of the  landfill property.
Approximately 1,500-feet to the east  of the Site is Gold Creek
and its associated wetlands.  The Neversink River is located
approximately 2,000-feet beyond Gold  Creek.  Gold Creek and the
Neversink River drain into the Delaware River.

The Site ranges from approximately .440 to 520  feet above mean sea
level.  The materials encountered underlying the Site consist of
glacially derived unconsolidated materials underlain by
consolidated bedrock.  The thickness  of the unconsolidated
overburden materials ranges from zero feet at  the exposed bedrock
slope forming the northwestern  Site boundary,  to over 60 feet
along the towpath.  The  glacially derived materials consist of
two distinct  units,  including a glacial  till  unit overlain by
glacial outwash deposits.  The  outwash deposit was observed to
vary in thickness  from  31  feet  to 52  feet along the downgradient
edge of the Site.   The  outwash  deposits  typically consist of
medium dense  to very dense brown sand with some clayey  silt and
gravel.   The  glacial  till  deposits  are characterized  as  dense to
very dense dark grey silt  with  sand and  gravel.  The  glacial till
 is not continuous  beneath the Site,  and  appears to pinch out
 toward the northwestern edge  of the Site.  The depth  to
 groundwater  from  ground surface ranges from  approximately 30 to
 40 feet along the  southeastern  boundary  of  the Site.   Groundwater
 movement  is generally towards  the  southeast.

 The  major aquifer system used for potable water  supply in Orange
 County  is comprised of  the bedrock and the sand  and gravel
 deposits  in the valley.   No residential  wells have been found to
 exist between the Site, and Gold Creek.  However,  approximately 90
 residential  wells exist downgradient of  the Site  between Gold
 Creek  and the Neversink River.   The nearest  residence and
 residential  well is located approximately a quarter of a mile
 downgradient of the Site.

-------
SITE HISTORY AND ENFORCEMENT ACTIVITIES

From approximately 1970 to 1979, the Site was used.for the
disposal of septic and municipal sewage sludge, as well as
industrial wastes, primarily from the cosmetic industry.  The
industrial wastes were deposited in one or more of the seven
lagoons located at the Site (lagoons 1 through 4 and 6 through 8
depicted in Figure 2).  Initially, it was believed that the
industrial wastes were deposited only in lagoons 1 through 4.  In
July 1992, however, the Site was expanded to include the
investigation of areas believed to contain four additional
filled-in lagoons  (lagoons 5, 6, 7 and 8).  These lagoons were
tentatively identified in historical aerial photographs.
Trenching in the area of lagoons 6, 7 and 8 confirmed the
presence of sewage sludge and industrial waste; trenching in the
area of lagoon 5 revealed the presence of tires instead of
industrial waste.  The dimensions of lagoons 1, 2, 3, 4., 6, 7 and
8 are approximately 100 feet by 60 feet, 200 feet by 60 feet, 100
feet by 35 feet, 100 feet by 40 feet, 60 feet by 20 feet, 100
feet by 45 feet, and 150 feet by 40 feet, respectively.

In  1978,  lagoon  3 was ignited by the Port Jervis Fire Department
in  order  to practice suppression of chemical fires.  After this
incident, lagoons  3 and 4 were  filled in with  soil and  the area
was revegetated.  With the exception of lagoons 1 and 2, all of
the lagoons . have been covered with soil.  Lagoons 1 and 2 were
.left uncovered and are surrounded by a. wooden  fence.  In .June
1979, the New York State Department of Environmental Conservation
 (NYSDEC)  prohibited the disposal of industrial wastes at the
Site.  The Site  continued to be used for the disposal of septic
and municipal sewage wastes until  1989.

In  February  1987,  NYSDEC  issued a  Phase  II  Investigation Report
which summarized past  investigations and  included a Hazard
Ranking  System  (MRS)  score  for  the Site.  Based on  the  HRS  score,
the Site was  proposed for inclusion on  the  National  Priorities
List  (NPL)  in June 1988  and was placed  on the  NPL in  February
1990.

On  September 25, 1989,  the  United States  Environmental  Protection
Agency  (EPA)  sent "special  notice"  letters  pursuant to  Section
 122(e)  of CERCLA,  42  U.S.C.  §9622(e),  to four  potentially
 responsible  parties  (PRPs),  Kolmar Laboratories,  Inc.  (Kolmar),
Wickhen Products,  Inc.  (Wickhen) ,  Reynolds  Metals Company,  Inc.,
 and Carroll  and Dubies .Sewage Disposal Facility,  Inc.,  affording
 them the opportunity to conduct the Remedial Investigation and
 Feasibility Study (RI/FS)  for the Site.   (PRPs are  companies or
 individuals who are potentially liable under CERCLA for the costs
 of  responding to the release and threat of  release of hazardous
 substances at and from a site.)  The PRPs were given 60 days in
 which to submit a good faith offer to undertake or finance the
 RI/FS fbr the Site.

-------
On November 30, 1989, two of the four PRPs, Kolmar and Wickhen,
submitted to EPA a good faith offer to perform the RI/FS.  An
Administrative Order on Consent, Index No II-CERCLA 00202, was
signed by the two PRPs and by EPA in February 1990:  This work
has been conducted under EPA's .supervision.

During the RI, EPA learned from the City of Port Jervis that it
owned a major portion of the Site property where the lagoons are
located.  In an April 22, 1993 letter, EPA notified the City that
it was also a PRP for the Site.  After issuance of the ROD, all
the PRPs will be offered the opportunity to design and implement
the selected remedial alternative for the Site.

HIGHLIGHTS OF COMMUNITY PARTICIPATION

The RI/FS reports and the Proposed Plan for the Site were
released for public  comment on August 4, 1994.  These documents
were made available  to the public in the administrative record
file at the EPA Docket Room in Region II,  26 Federal Plaza, Room
2900, New York, New  York and at the Deerpark Town Hall, Drawer A,
Huguenot, New York.  The Proposed Plan was sent to members of the
public on EPA's mailing list on August 3,  1994.  A public notice
announcing the availability of these documents was issued on
August 15, 1994 in The Times Herald Record.  The public comment
period was held from August 4, 1994 through September 2,  1994.

During the public.comment period, EPA held .a public meeting to
present the RI/FS reports and  the Proposed Plan; answer
questions, and accept both oral and written comments.  The public
meeting was held  in  the auditorium of the  Port Jervis High
School, Port  Jervis, New York  on August  23, 1994.  At this
meeting, representatives from  the NYSDEC,  EPA  and  the New York
State Department  of  Health  (NYSDOH) answered questions about
concerns related  to  the  Site and the  remedial  alternatives under
consideration.  Responses to the comments  received at the public
meeting and to written  comments received during  the public
comment period, are  included  in the Responsiveness  Summary (see
Appendix V).

SCOPE AND  ROLE OF OPERABLE UNIT

This ROD addresses  the  first of two  operable  units planned for
this Site.  This  operable unit (OU1)  addresses the source areas
 (lagoons and  surrounding impacted  soils)  at  the  Site  and actions
needed  to  ensure  that  the  source  areas  do  not pose a  threat  to
human health  or  the environment,  including any potential cross
media  impacts to  groundwater.   The second operable unit  (OU2)
 investigation, which is currently underway,  will address the need
 for remediating  contaminated groundwater underlying the  Site.

-------
The two PRPs who performed the RI/FS for the first operable unit
are currently performing the RI/FS for the second operable unit
under supervision by EPA.   '

The purpose of the response action under OU1 is to prevent
leaching of contaminants in the soils/sludges at levels which
will contribute to the contravention of groundwater quality and
drinking water standards in the groundwater in the vicinity of
the Site, as well as to minimize potential risks to hypothetical
workers who might take part in excavation activities in
contaminated areas in the future.

SUMMARY OF SITE CHARACTERISTICS

The intent of the investigation was to characterize the soil
quality of the seven lagoons at the Site and any potential cross
media impacts to the groundwater quality in the vicinity of these
lagoons.  The remedial investigation consisted of drilling
borings and constructing monitoring we.lls, collecting soil and
groundwater samples, and conducting ambient air quality and
seismic surveys.  The PRPs hired Blasland & Bouck Engineers to
implement the RI/FS.
.Between  July and September 1991,  approximately  20  soil/sludge
 samples  were collected from lagoons  1  through 4 and the        .
 surrounding  soils;  these samples  were  analyzed  for organic  and
 inorganic  constituents.   During January and February 1993,  54
 additional soil samples were collected to  further  delineate the
 horizontal extent of lagoons 1 through 4 and to characterize the
 berm soil  around lagoons 1 and 2. Various organic constituents
 were detected in these lagoons and the surrounding soils.   Some
 of  the highest concentrations of  organic contaminants detected
 included benzene (650 parts per million (ppm)), 1,2-
 dichlorobenzene (43.0 ppm), 1,4-dichlorobenzene  (250 ppm),
 tetrachloroethene .(290 ppm), and  toluene (370 ppm).  Inorganic
 constituents detected in lagoons  1 through 4 and surrounding
 soils included arsenic  (10.7 ppm), barium  (1,290 ppm), chromium
 (137 ppm), cyanide  (320 ppm), lead (1,400  ppm), and nickel  (368
 ppm) .

 Higher levels of organic and inorganic constituents were detected
 in lagoons 6, 7 and 8.  Approximately 45 soil and sludge samples
 were collected from within and around the  perimeter of lagoons 6,
 7 and 8  during January  and February 1993.   Some of the highest
 concentrations of organic contaminants detected included benzene
 (2,800 ppm), tetrachloroethene (12,000 ppm), and  toluene (13,000
 ppm) .  Inorganic constituents detected in lagoons 6, 7 and  8
 included arsenic  (9.7 ppm), barium  (933 ppm),  chromium  (16,000

-------
pptn) ,  and lead  (609 ppmj .  In general, organic compounds were
detected at higher concentrations in lagoon 7, and inorganic
compounds were detected at higher concentrations in lagoon 8.

Five background soil samples were collected from areas not
affected by Site contamination to use as a point of reference.
One of the five soil samples was analyzed for organic
constituents.  All five background soil samples were analyzed for
inorganic constituents.  Other than 0.01 ppm of methylene
chloride,, organic compounds were not detected in the soil sample
collected to assess background concentrations of organic
compounds.  The highest concentrations of various inorganic
constituents detected in the background soil samples included 7.0
ppm of arsenic, 43.1 ppm of barium, 61.9 ppm of chromium, 45.6
ppm of lead, and 36.7 ppm of nickel.  Cyanide was not detected in
any of the background soil samples.

Tables 1 and 2  summarize the contaminant concentration averages
and ranges for  the source area materials and the background soil
samples.  In Tables 1 and 2, the NYSDEC soil cleanup levels
 (Technical and  Administrative Guidance Memorandum  (TAGM) No.
4046) are provided in place of the background soil concentrations
for organics since only one organic compound was detected in the
background soil sample.  Figure 2  shows the location of the soil
borings.

The source materials from lagoons  1,  2, 7 and 8 were tested using
the toxicity characteristic leaching  procedure  (TCLP) to
determine if these materials would be considered Resource
Conservation and Recovery Act  (RCRA)  hazardous waste based on the
characteristic  of toxicity.  The source materials  from  lagoons 1
and 2 did not  leach organic or inorganic constituents at
concentrations  above the regulatory criteria  for determining
waste to be a  RCRA characteristic  waste. The  source materials
 from lagoon 7  failed the TCLP  for  benzene,  tetrachloroethene,
 trichloroethene and vinyl chloride and are  therefore considered
RCRA hazardous  waste based on  the  characteristic of toxicity.
Lagoon  8 failed the TCLP for benzene  and chromium; therefore,
 these materials would  be considered RCRA hazardous waste based on
 the characteristic of  toxicity.  All  materials which exceed  TCLP
 levels  would be subject to pretreatment.in  order to satisfy  RCRA
 land disposal  restrictions  (LDRs).

 Grouhdwater

 During  August  1991,  December 1991,  March  1993 and  October  1993,
 groundwater  samples  were collected from the vicinity  of the
 lagoons and  analyzed for organic and inorganic compounds.
 Monitoring wells  located downgradient of  lagoons  1 through 4 were
 sampled during August  1991,  December 1991  and March 1993,  and

-------
monitoring wells located downgradient of lagoons 6,  7 and 8 were
sampled in October 1993.  These monitoring wells monitor the
bedrock, the glacial till, the glacial outwash or both the
glacial till and outwash units.  Figure 3 shows the location of
the monitoring wells at the Site.

Four organic compounds, benzene, 1,2-dichloroethene (total),
tetrachloroethene and trichloroethene, were detected above the
Federal and/or State drinking water standards in the monitoring
wells located downgradient of lagoons 1 through 4 during August
and December 1991 and March 1993.  These four organic compounds
were detected in the monitoring wells that monitor the glacial
outwash or both the glacial till and outwash.  Organic
contaminants were not detected above Federal or State drinking
water standards in any of the bedrock or glacial till monitoring
wells.  Aside from tetrachloroethene detected in monitoring well
OW-6, organic compounds were only detected above the Federal
and/or State drinking water standards at monitoring wells located
along the D&H towpath  (e.g., OW-2, OW-3 and MW-4) .  The
monitoring wells located downgradient of the D&H towpath  (e.g.,
OWr5, OW-6, OW-7 and OW-8) were  installed in 1993 and were only
sampled in the October 1993 sampling event.  The four organic
contaminants noted above were detected in higher concentrations
in 1991 than in 1993.  The highest concentrations of organic
compounds detected above drinking water standards were benzene at
52 parts per billion  (ppb) in monitoring well OW-3, 1,2-
dichloroethene  (total) at 230 ppb in monitoring well OW-2,
tetrachloroethene at 130 ppb in  monitoring well OW-2, and
trichloroethene at 41 ppb in monitoring well MW-2.  The Federal
and  State drinking water  standards for benzene, tetrachloroethene
and  trichloroethene are all 5 ppb.  The State drinking water
standard for 1,2-dichloroethene  isomers is 5 ppb, which is more
stringent than the Federal standard.

Inorganic compounds  (arsenic, beryllium, chromium,  lead and
nickel) were detected  above the  Federal and/or  State drinking
water  standard in monitoring wells located downgradient of
lagoons^1 through 4 only  during the  1991 sampling events.  During
the  March 1993 sampling,  only  cadmium Was detected  above  drinking
water  standards.  Cadmium was  detected  in monitoring well OW-3  at
6 ppb,  which  is  slightly  higher than the Federal  and State
drinking water standard of  5 ppb.

During the  October  1993  sampling of  monitoring  wells  located
downgradient  of  lagoons 6,  7  and 8  (OW-9,  OW-10,  OW-11,  OW-12,
OW-13,  OW-14  and BW-5), benzene was  detected "above  both the
Federal and State drinking water standards;  seven other organic
compounds  were  detected above  the State drinking water standards
but  below the Federal drinking water standards.  The highest
concentrations  of organic compounds  detected were benzene at

-------
1,300 ppb in monitoring well OW-12; 1,3,5-trimethylbenzene at 12
ppb in monitoring well OW-ll; 1,2,4-trimethylbenzene at 44 ppb in
monitoring well OW-12; 1,2-dichloroethene (total)  at 12 ppb in
monitoring well OW-13; ethylbenzene at 9.8 ppb in monitoring well
OW-12; toluene at 9.6 ppb in monitoring well OW-12;  and xylene at
40 ppb. in monitoring well OW-12.  The State drinking water
standard for 1,3,5-trimethylbenzene, 1,2,4-trimethylbenzene,
ethylbenzene, toluene, and xylene is 5 ppb.  The Federal drinking
water standard is 700 ppb for ethylbenzene, 1,000 ppb for toluene
and 10,000 ppb for xylene.  A Federal drinking water standard
does not exist for 1,3,5-trimethylbenzene or 1,2,4-
trimethylbenzene .

Nine inorganic compounds were detected above Federal and/or State
drinking water standards in the seven monitoring wells located
downgradient of lagoons 6, 7 and 8.  However, six of the nine
inorganic compounds were detected above standards only in
monitoring well OW-10.  Chromium, lead and nickel were detected
above drinking water standards in more than one monitoring well
and were detected at levels that ranged from 106 to 2,930 ppb,
19.1 to 924 ppb and 100 to 1,560 ppb, respectively.   The
inorganic compounds detected above  drinking water standards in
monitoring well OW-10 were about an order of magnitude higher
than the levels detected in the other monitoring wells.  The
Federal drinking water standards for chromium and nickel are set
.at 100 ppb;. the Federal action level for lead is 15 ppb.  The
State drinking water standards for  chromium and lead are 100 and
50 ppb, respectively.  A State drinking water standard does not
exist for nickel.

The NYSDOH performed a limited sampling of off-Site private wells
in 1991 and again  in 1993  for organic and  inorganic constituents.
Organic constituents were  not detected in  the groundwater from
these wells,  and  inorganic constituents were detected below
drinking water  standards.

As previously mentioned,  an  investigation  to. determine the
lateral and  downgradient  extent  of  the groundwater plume  is.
currently underway and will  be  reported  in the RI for  the second
operable unit.

Ambient Air  Monitoring and Geophysical Surveys

A seismic  survey and an  ambient  air survey were  conducted at  the '
Site.  The  ambient air survey, indicated  that  the  Site  does  not
have  an  adverse impact on air quality.   The  seismic  survey
provided  additional information on the Site  geology.

-------
SUMMARY OF SITE RISKS

Based upon the results of the RI,  a baseline risk assessment was
conducted to estimate the risks associated with current and
future Site conditions.  The baseline risk assessment estimates
the human health and ecological risk which could result from the
contamination at the Site, if no remedial action were taken.

As part of the baseline risk assessment,  the following four-step
process is utilized for assessing Site-related human health risks
for a reasonable maximum exposure scenario:  Hazard
Identification--identifies the contaminants of concern at the
Site based on several factors such as toxicity, frequency of
occurrence, and concentration.  Exposure Assessment--estimates
the magnitude of actual and/or potential human exposures, the
frequency and duration of these exposures, and the pathway  (e.g,
ingesting contaminated well-water) by which humans are
potentially exposed.  Toxicity Assessment--determines the types
of adverse health effects associated with chemical exposures, and
the relationship between magnitude of exposure  (dose) and
severity of adverse effects  (response).   Risk Characterization--
summarizes and combines outputs of the exposure and toxicity
assessments to provide a quantitative (e.g., one-in-a-million
excess cancer risk) assessment of Site-related risks.

The risk assessment was prepared before the analytical soil data
associated with lagoons 6, 7 and 8 were available.  Therefore,
only the data collected from lagoons  1 through 4 during July and
September 1991 were used  in the risk  assessment.  A separate risk
assessment was not prepared for lagoons 6,  7 and 8, since it was
anticipated that remedial action would be taken at these lagoons
due to the levels of  contaminants found, the presence of
hazardous waste and cross media impacts to  groundwater.  Higher
baseline risk levels  would be expected if the  analytical soil
data from lagoons 6,  7 and 8 were included  in  the risk
assessment.

The baseline risk assessment began with selecting contaminants  of
concern which would be representative of  Site  risks.  These
contaminants included, but were not  limited to benzene,  1,2-
dichlorobenzene, tetrachloroethene,  toluene, arsenic, barium,
chromium,  cyanide,  lead,  and nickel.  The  summary of  the
contaminants of concern  (COCs)  is provided in  Table  3.

The baseline risk  assessment addressed the potential risk  to
human  health by identifying  potential exposure pathways  by which
the public might be exposed  to contaminant releases  at  the Site
under  current .and  future land-use conditions.   The  exposure
pathways  under the  current  land-use conditions included the
exposure  to  adult  and child trespassers  through the  dermal

-------
contact with standing water contained in lagoon 1,  and through
the ingestion, inhalation and dermal contact of soils and
sludges.  When considering future land use, the exposure pathways
included the ingestion, inhalation and dermal contact of soils
and sludges by construction workers.  Because the Site is
surrounded by a cliff, a landfill and a quarry, future
residential use of the property was not considered as a
reasonable scenario.  The exposure pathways considered under
future and current land-use conditions are listed in Table 4.

Under current EPA guidelines, the likelihood of carcinogenic
(cancer causing) and non-carcinogenic effects due to exposure to
Site chemicals are considered separately.  It was assumed that
the toxic effects of the Site-related chemicals would be
additive.. Thus, carcinogenic and non-carcinogenic .risks
associated with exposures.to individual compounds of concern were
summed to indicate the potential risks associated with mixtures
of potential carcinogens and non-carcinogens, respectively.
Potential carcinogenic risks were evaluated using the cancer
potency factors developed by EPA for the compounds of concern.
Cancer slope factors  {SFs) have been developed by EPA's
Carcinogenic Risk Assessment Verification Endeavor for estimating
excess lifetime cancer risks associated with exposure to
potentially carcinogenic chemicals.  SFs, which are expressed in
units of  (mg/kg-day) "1, are multiplied by the estimated  intake of
a potential carcinogen, in mg/kg-day, to generate an upper-bound
estimate  of the excess lifetime cancer risk associated with
exposure  to the compound at that intake level.  The term  "upper
bound" reflects the conservative estimate  of the risks calculated
from the  SF.  Use of  this approach  makes the underestimation of
the risks highly unlikely.  The SF  for the compounds of concern
are presented in Table 5.

EPA's acceptable cancer risk range  is 10"4  to 10"6 which can be
interpreted to  mean that  an  individual may have a one in  ten
thousand  to a one in  a million  increased chance of developing
cancer  as a result of a site-related exposure  to a carcinogen
over a  70-year  lifetime under the specific exposure conditions at
a  site.   The  results  of the  baseline risk  assessment  indicated
that the  soils  and  sludges  associated with lagoons 1  through  4
pose no unacceptable  carcinogenic risk  to  human health.   The  sum
of the  current  cancer risks  for the exposure pathways  for adult
and child trespassers was 5  x  10"7  (five in ten million)  and 3 x
10~6  (three  in a million), respectively.   The overall future
carcinogenic  risk  for construction  workers,  through  ingestion,
inhalation  and  dermal contact  of contaminated  soils  and sludges,
was estimated to be 4 x 10"6 (four in a million) .   These
carcinogenic  risks  are within  EPA's acceptable risk  range.   A
summary of  the  carcinogenic risks  are  presented in Table 6.

-------
Noncarcinogenic risks were assessed using a hazard index (HI)
approach, based on a comparison of expected contaminant intakes
and safe levels of intake (Reference Doses) .   Reference doses
(RfDs) have been developed by EPA for indicating the potential
for adverse health effects.  RfDs,  which are expressed in units of.
mg/kg-day, are estimates of daily exposure levels for humans
which are thought to be safe over a lifetime (including sensitive
individuals) .   Estimated intakes of chemicals from environmental
media (e.g.. the amount of a chemical ingested from contaminated
soil) are compared with the RfD to derive the hazard quotient for
the contaminant in the particular medium.  The HI is obtained by
adding the hazard quotients for all compounds across all media.
An HI greater than 1 indicates that the potential exists for
noncarcinogenic health effects to occur as a result of site-
related exposures -.  The reference doses for the compounds of
concern at the Site are presented in Table 7.

The calculated HI values for adult and child trespassers are less
than 1, which EPA has determined to be acceptable.  The total
exposure HI for construction workers assumed to be participating
in excavation and grading activities was estimated to be 3.0.
Therefore, there may be unacceptable noncarcinogenic risks
associated with the construction worker scenario.  The primary
contributor to this risk is chromium-containing dust which could
be inhaled, during excavation activities.  Chromium containing
dust contributed approximately 70 percent to the HI.  A summary
of the noncarcinogenic risks are presented in Table 8.

As previously noted, higher risk levels from exposure to
contaminated soil would have resulted if the analytical soil data
from lagoons 6, 7 and 8 were included in the risk assessment.  A
risk assessment to  identify the potential risk to human health
through  groundwater exposure pathways will be prepared during the
second operable unit.  As indicated by the groundwater sampling
data, contaminants  from the soil are migrating into the
groundwater at concentrations above Federal and  State health-
based drinking water standards.

The  qualitative .ecological assessment concluded  that the  Site
provides low to moderate  habitat value to wildlife.  The.degree
of physical disturbance on-Site and  lack of  continuous quality
habitat  in  adjacent areas restrict  the diversity and extent  of
wildlife use at the Site.  Therefore, only minor impacts  on
wildlife are expected  to  occur.

Uncertainties

The  procedures and inputs used to assess risks  in this
evaluation,  as in all  such assessments,  are  subject to a wide
variety of  uncertainties.  In general,  the main sources of
uncertainty include:


                                10

-------
- environmental chemistry sampling and analysis
- environmental parameter measurement
- fate and transport modeling
- exposure parameter estimation
- toxicological data.

Uncertainty in environmental sampling arises in part from the
potentially uneven distribution of chemicals in the media
sampled.  Consequently, there is significant uncertainty as to
the actual levels present.  Environmental chemistry-analysis
error can stem from several sources including the errors inherent
in the analytical methods and characteristics of the matrix being
sampled.

Uncertainties in the exposure assessment are related to estimates.
of how often an individual would 'actually come in contact with
the COCs, the period of time over which such exposure would
occur, and in the models used to estimate the concentrations of
the contaminants of concern at the point of exposure.

Uncertainties in toxicological data occur in extrapolating both
from animals to humans and from high to low doses of exposure, as
well as from the difficulties in assessing the toxicity of a
mixture of chemicals.  These uncertainties are addressed by
making conservative assumptions concerning risk and exposure
parameters throughout  the assessment.  As a result, the Risk. .
Assessment provides upper-bound estimates of the risks to
populations near the Site, and is highly unlikely to
underestimate actual risks related to the Site.

Actual or threatened releases of hazardous substances from this
Site, if not addressed by implementing the response action
selected in the Record of Decision  (ROD), may present a imminent
and substantial endangerment to the public health, welfare,  or
the environment.

REMEDIAL ACTION OBJECTIVES

Remedial action objectives are specific  goals  to protect  human
health  and the environment.  These objectives  are based on
available information  and standards  such as applicable or
relevant and appropriate  requirements  (ARARs)  and risk-based
levels  established in  the risk assessment.  The remedial  action
objectives for the source areas  at the  Site are  (1)  to prevent
leaching of contaminants  in  the  soils/sludges  at levels which
will  contribute to the contravention of  groundwater quality and
drinking water standards  in  the  groundwater in the  vicinity of
the Site; and  (2)  to minimize potential  risks  to hypothetical
excavation, workers.
                                11

-------
DESCRIPTION OP REMEDIAL ALTERNATIVES

CERCLA requires that each selected site remedy be protective of
human health and the environment, be cost effective,  comply with
other statutory laws, and utilize permanent solutions and
alternative technologies and resource recovery alternatives to
the maximum extent practicable.  In.addition,  the statute
includes a preference for the use of treatment as a principal
element for the reduction of toxicity, mobility,  or volume of the
hazardous substances.

This ROD evaluates in detail six remedial alternatives for
addressing the soil and sludge contamination at the Carroll and
Dubies Superfund site.  As used in the following text, the time
to implement reflects only the time required to implement the
remedy, and does not include the time required to design the
remedy, procure contracts for design and construction or to
negotiate with responsible parties for implementation of the
remedy, conduct operation and maintenance, or conduct long-term
monitoring.

Alternative 1:  No Action

Capital Cost:          $ 0
O & M/yr Cost:         $ 0
Present Worth:         $ 0
Time to Implement:     0 months

The Superfund program requires that the  "no-action" alternative
be considered as  a baseline  for  comparison with other
alternatives.  Under this alternative, the contaminated  soil
would  be left in  place without treatment.  The Site would remain
in its current condition and no  effort would be made  to  change
the current  Site  conditions.

Alternative  2:  Limited Action

Capital cost:           $  52,000
0 & M/yr Cost:          $  18,000
.Present Worth:          $  328,660
Time to  Implement:      6  months

This alternative  consists of institutional controls  such as deed
restrictions to limit  future use of  the  Site  and complete fencing
of the Site  to  minimize  potential human  exposure to  the  source
area materials.   The limited action alternative  would not utilize
any  remedial technologies for the treatment of the source areas.
A long-term groundwater monitoring program would be  implemented
to  track the migration of contaminants from the  source areas into
the  groundwater utilizing existing monitoring wells  at the Site
                                 12

-------
(This monitoring program may be addressed as part of OU2
groundwater remedial activities.)

Alternative 3:  Low-Permeability Cap with Slurry Cut-Of£ Wall

Capital Cost:          $ 3,299,816
0 & M/yr Cost:         $   147,060
Present Worth:         $ 5,560,128
Time to Implement:     12 months

This alternative  includes the construction of a low-permeability
cap over the.  source materials to minimize the infiltration of
precipitation.  Limiting the amount of water which percolates
through the source materials would reduce the leaching of the
chemical constituents  into the groundwater underlying the Site.
In addition to  the cap, a slurry cut-off wall would be installed
around the source area to minimize the migration of soil gas and
leachate from the impacted source areas into the surrounding
soils and to  minimize  the movement of groundwater through the
source area materials.  The cap would be constructed of a low-
permeability  material  such as natural clay, geosynthetics,
asphalt or combinations of these materials.  Additional drainage
and top soil  layers would be included to achieve a well drained,
vegetated surface upon completion.  Deed restrictions would be
recommended to  limit  future use  of the Site in order to protect
the integrity of  the  cap.

The slurry cut-off wall would be constructed by excavating
vertical trenches while filling  the excavation with a soil-
bentonite slurry.. The slurry wall would be keyed into the
bedrock unit  which underlies the Site.  This bedrock unit
consists of shale and silt stone and ranges from ground surface
to 60 feet below  grade.  Groundwater at the Site is present
within the overburden soil materials.  Therefore, hydrodynamic
controls to maintain  an  inward groundwater  flow gradient within
the cell would  be required to prevent any  leakage from the cell
into downgradient groundwater.   Hydrodynamic controls would
include pumping groundwater  from within the capped  area.  The
collected water would be  treated on-Site in a granular activated
carbon  (GAC)  adsorption  treatment  system to meet New York State
Pollution Discharge  Elimination  System  (SPDES) requirements  prior
to discharge.  The  spent  carbon  would be regenerated or  shipped
off-Site to  an appropriate  disposal  facility.  Groundwater
monitoring would be  performed annually  in  coordination with  OU2
groundwater  remedial activities.

Alternative  4:   Stabilization/Solidification and Placement  into
an On-Site  Containment Cell

Capital  Cost:          $ 5,389,215
O &  M/yr Cost:          $    26,400
Present  Worth:          $ 5/794,983

                                 13

-------
Time to Implement:      12 months

This alternative involves the physical removal of approximately
20,300 cubic yards (cy) of source area materials and treatment of
these materials through stabilization/solidification.
Stabilization/solidification is a process by which stabilizing
agents such as cement-based, pozzolanic-based, asphalt-based, and
organic-polymer-based agents are mixed with the source area
materials to convert the waste to a more stable form.  To ensure
compliance with air pollution control regulations, capture' and
control mechanisms would be installed, as necessary, to control
air emissions containing organic constituents emitted during the
stabilization/solidification process.  Air monitoring would also
be conducted during implementation of this alternative to
determine the .need for additional engineering controls.

The stabilized mass would then be placed into a lined and capped
cell, which would comply with modified requirements specified in
the New York Code of Rules and Regulations  (Part 360) .  The base
of the cell would consist of a high density polyethylene  (HDPE)
liner and a sand drainage, layer.  The cell' would be sloped to a
leachate collection system located adjacent to the cell to
collect any leachate that is generated by the solidified
materials.  Once the source area materials are placed into the
cell, a cap would be constructed over the cell to minimize the
infiltration of rainwater.  The cap would consist of a low-
permeability clay layer, an HDPE membrane, a  sand drainage layer,
and a topsoil cover layer.  Deed restrictions would be
recommended to limit future, use of the Site in order  to protect
the integrity of the cap.  Leachate would be  removed periodically
from the leachate collection system and sent  off-Site for
treatment and disposal in compliance with applicable  regulations.
Groundwater monitoring would be performed annually  in
coordination with OU2  groundwater remedial  activities.

Alternative 5.:  Organics Treatment via Ex-Situ Vapor  Extraction,
Ex-Situ Bio slurry or Low-Temperature  Thermal  Desorption;
Inorganic Treatment via  Stabilization/Solidification,  and
Placement into an On-Site Containment Cell

Capital' Cost:          $  8,105,000
O & M/yr Cost:         $  28,000
Present Worth:         $  8,535,000
Time  to Implement:     12 months

The  title/name  and  description of  this  alternative  has been
modified  from that  presented in the  Proposed Plan and FS to
reflect the  change  in  emphasis on  the likely type of process to
treat organic contaminants.  This change was warranted by
additional  information that was presented during and subsequent
to the August 23,  1994 public meeting.  (Please refer to the
community acceptance  and Documentation of Significant changes

                                14

-------
sections of this document, as well as Appendix V,  the
Responsiveness Summary.)  The Proposed Plan and other information
disseminated at the- public meeting indicated that one or a
mixture of three different processes might be used to treat
organic contaminants.  At that time, the emphasis was placed on
the use of Low-Temperature Thermal Desorption (LTTD)  as the
treatment process; the current emphasis is on the use of a
mixture of ex-situ vapor extraction and bioslurry as the
treatment processes for the organics.  The costs of implementing
this alternative have also been refined to reflect the change in
emphasis on treatment from the higher cost portion of LTTD to the
lower cost options of vapor extraction combined with bioslurry.

This alternative consists of excavating materials from lagoons 1,
2, 3, 4, 6, 7 and 8•and soils in the vicinity of these lagoons
(estimated to be 20,300 cy).  Materials, which exceed organic
contaminant treatment levels  (estimated to be 13,800 cy) and/or
inorganic contaminant treatment levels, would undergo treatment
prior to disposition into a lined cell; the remaining materials
would be deposited directly into the lined cell without
treatment.  Materials from lagoons  1, 3, 7 and 8  (approximately
13,500  cubic yards) which contain high concentrations of organic
contaminants would be treated to reduce the levels of organic
contaminants.  Three options are included under this alternative
as options for organic  treatment: LTTD, vapor extraction, and
bioslurry.  These processes are described below.

LTTD is a process by which soils/sludges are heated and the
organic constituents are  desorbed from the soils/sludges and
volatilized into an  induced air flow.  The soils/sludges are
heated  to temperatures  ranging from 200°F to 1,200°F.  Air  or
nitrogen carrier gas is passed over the soils/sludges to collect
the volatilized organic constituents.  The carrier gas  is  then
passed  through a condenser, carbon  adsorption bed, cyclone and/or
a baghouse to limit  emissions to within the air pollution  control
regulatory requirements.   In  vapor  extraction, air is drawn
through the soil to  vaporize  and  remove organic contaminants  in
the  soil.  The air flow also  provides  indigenous  microorganisms
with sufficient oxygen  to degrade organic  contaminants  present in
the  soil.   In bioslurry treatment,  the  contaminated  soil  is mixed
with water  to  form a slurry which is fed  to a bioreactor  and
aerated.  The principal objective of aeration  is  to  supply
sufficient  oxygen throughout  the  slurry to promote aerobic
micrbbial  activity that will  degrade the  organic  contaminants in
the  soil.   Nutrients for  the  microorganisms  are  also added to the
bioreactor.

Any  air emissions  generated from organics treatment  via LTTD,
vapor  extraction,  or bioslurry treatment  would be treated as
necessary to  meet air  pollution control regulations.   Regardless
of whether LTTD,  vapor extraction or bioslurry treatment is
utilized,  the cleanup criteria for organic compounds presented

                                15

-------
later in this document would have to be met (see Remediation
Goals under Selected Remedy).   Air monitoring would be conducted
during implementation of this alternative to ensure air emissions
are within regulatory limits.   Further treatability studies would
be required to demonstrate the ability of any of these processes
to effectively treat the organic constituents in the waste,
particularly the lagoon 7 materials.

Upon completion of the treatment of lagoons 1, 3, 7 and 8 for
their organic constituents, lagoons 6 and 8 (approximately 5,700
cy) would be treated through stabilization/solidification to
reduce the mobility of the inorganic constituents.  Additionally,
if source area materials from lagoons 1, 2, 3, 4 and 7 exceed the
RCRA-Regulated Levels for TCLP for inorganic constituents, they
would also be stabilized/solidified.  Additional source area
materials may also be stabilized/solidified in order to achieve
adequate load bearing capacity.  All excavated source area
materials  (estimated to be 20,300 cubic yards) would then be
placed in a lined cell with a well for leachate collection, and
then capped.  The lined cell and cap are the same as that
described in Alternative 4.  Deed restrictions would be
recommended to limit future use of the Site in order to protect
the integrity of the cap.  Leachate would be removed periodically
from the leachate collection system and sent off-Site for
treatment and disposal in compliance with applicable regulations.
Groundwater monitoring would be performed annually in
coordination with OU2 groundwater remedial activities.

Alternative 6:  Off-Site Disposal at a Permitted Landfill

Capital Cost:          $ 32,679,764
0  & M/yr Cost:         $ 0
Present Worth:         $ 32,679,764
Time to Implement:     12 months

This alternative consists of excavating 20,300  cy of source area
materials  and transporting  these materials off-Site to  a  RCRA-
permitted  treatment,  storage and disposal  facility for  treatment
and disposal, as appropriate.   The  majority of  the excavated
materials  would be placed  directly  into lined 20  cy roll-offs.
Some of the  source area  materials might need  to be dewatered
prior  to off-Site transportation.   Each roll-off  would  be sampled
to characterize the  source  area materials  prior to transportation
off-Site.   Based on  the  analytical  data available for the source
area materials, the  materials  from  Lagoons 6,  7 and  8 would
require pretreatment to  meet  the  LDRs  prior  to disposal at a
RCRA-permitted  landfill.   Air  monitoring would also  be  conducted
during implementation of this  alternative  to determine  the need
for  engineering  controls.
                                 16

-------
It is estimated that the volume of source area materials that
would require pretreatment prior to land disposal is
approximately 9,130 cy.  For purposes of evaluating this
alternative, incineration and solidification were considered to
be the appropriate pre-treatment methods to address the source
area materials which do not meet LDRs.

SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

During the detailed evaluation of remedial alternatives, each
alternative was assessed utilizing nine evaluation criteria as
set forth in the National Contingency Plan, 40 CFR
§300.430 (e) (9) (iii) and the Office of Solid Waste and Emergency
Response  (OSWER) Directive 9355.3-01.  These criteria were
developed to address the requirements of Section 121 of CERCLA,
42 U.S.C. §9621 to ensure all important considerations are
factored into remedy selection decisions.

The following  "threshold" criteria are the most important, and
must be satisfied by any alternative in order to be eligible for
selection:

1.   Overall protection of human health and the environment
     addresses whether or not a remedy provides adequate
     protection and describes how risks posed through each
     exposure pathway  (based on a reasonable maximum exposure
     scenario) are eliminated, reduced, or controlled through  .
     treatment,, engineering controls, or institutional controls.

2.   Compliance with Applicable or Relevant and Appropriate
     Requirements addresses whether or not a remedy would meet
     all of the applicable, or relevant and appropriate
     requirements of federal and state environmental statutes and
     requirements or provide grounds for invoking a waiver.

The  following  "primary balancing" criteria are used to make
comparisons and to identify the major trade-offs between
alternatives:

3.   Long-term effectiveness and permanence refers to the ability
     of  a  remedy  to maintain reliable protection of human health
     and the  environment  over  time,  once cleanup goals  have  been
     .met.   It  also addresses the magnitude and effectiveness of
     the measures that may be  required  to  manage the risk posed
     by  treatment residuals and/or untreated wastes.

4.   Reduction of toxicity, mobility, or volume  through treatment
     is  the anticipated performance  of  a remedial  technology,
     with respect to  these parameters,  that  a  remedy may employ.


5.   Short-term effectiveness  addresses the  period of  time  needed

                                17

-------
     to achieve protection and any adverse impacts on human
     health and the environment that may be posed during the
     construction and implementation periods until-cleanup goals
     are achieved.

6.    Implementability is the technical and administrative
     feasibility of a remedy,  including the availability of
     materials and services needed.

7.    Cost includes estimated capital and operation and
     maintenance costs, and the present worth costs.

The following "modifying" criteria are considered fully after the
formal public comment period on the Proposed Plan is complete:

8.    State acceptance indicates whether, based on its review of
     the RI/FS and the Proposed Plan, the State supports,
     opposes, and/or has identified any reservations with the
     preferred alternative.

9.    Community acceptance refers to the public's general response
     to the alternatives described in the Proposed Plan and the
     RI/FS reports.  Factors of community acceptance to be
     discussed include support, reservation, and opposition by
     the community.

A comparative analysis of the remedial alternatives based upon
the above evaluation criteria follows.

Overall Protection of Human Health and the Environment

All alternatives, except for no action, would offer some degree
of protection of  human health, and the environment; Alternative 1,
no action, offers no protection.  Alternative 6 would be most
protective of human health and the environment in the vicinity of
the Site, since source area materials would be removed  from the
Site.  Alternatives 4  and 5 would mitigate cross-media  impacts to
the groundwater from the source and  therefore would be  protective
of human health and the  environment.  Alternative 5 would,
however, provide  a higher degree of  overall protection  of  human
health and the environment than Alternative 4, since  it would
permanently  remove organic contaminants  from  source area
materials having  high  levels  of organic  contamination.
Alternative  3 does not include any treatment, therefore it would
not be as protective to  human health and the  environment as
Alternatives 4, 5 and  6.  Alternative 2  would be less protective
of human health and the  environment  than Alternatives 3,  4,  5,
and  6,  since it would  rely on the  proper enforcement  of
 institutional  controls and would not reduce the  leaching of
chemical contaminants  to the  Site  groundwater.
                                18

-------
Compliance with ARARs

All remedial technologies proposed for use in Alternatives 3,  4,
5 and 6 would be designed and implemented to meet ARARs and are
therefore similar in their compliance with ARARs.  Wastes would
be treated using specific technologies or treated to specific
treatment levels, as appropriate, to comply with air pollution
control and RCRA hazardous waste regulations.  Federal and State
regulations dealing with the handling and transportation of
hazardous wastes to an off-Site treatment facility would be
followed with regard to Alternative 6.  Alternative 2, 3, 4 and 5
would require compliance with various state and/or local
requirements for implementing deed restrictions.  Alternatives 1
and 2 would not comply with State closure ARARs.  In addition,
for reasons discussed below under Long-Term Effectiveness and  .
Permanence, Alternative 6 followed by Alternatives 5, 4, and 3
would best minimize cross-media impacts of contaminants migrating
from soil to groundwater, thereby enabling groundwater standards
to be achieved in a shorter time frame.  Alternatives 1 and 2
would not provide this benefit.

Long-Term Effectiveness and Permanence

Alternative 6 would provide the highest degree of long-term
effectiveness and permanence, since the contaminated soils would
be permanently removed from the Site and, following any necessary
treatment, disposed of at a RCRA permitted disposal facility.
Alternatives 4,  5 and 6 would mitigate the leaching of
contaminants to  the underlying groundwater.  Alternative 5 would,
however, provide the highest degree of long-term effectiveness
and permanence among the on-Site alternatives, since organic
contaminants would be permanently removed from the source area
materials having high levels of organic contamination;  it would
also effectively address inorganic contaminants.  Unlike
Alternative 5, Alternative 4 has not been proven effective  for
treatment of organic contaminants and relies on  the containment
cell and the leachate collection system to prevent the  leaching
of organic contaminants  into the groundwater; Alternative 4 does,
however,.effectively address inorganic contaminants over the
long-term.  Alternative  3 does not include any treatment of
contaminants;  the permanence of Alternative  3 would rely on the
continued maintenance of the cap and  slurry  cutoff wall, and  the
operation and  maintenance of the hydraulic control system.
Alternatives 1 and  2 would not provide any active treatment or
containment and therefore would  not be effective over the  long-
term or provide  permanent protection of  the groundwater
underlying the Site.
                                 19

-------
Reduction in Toxicitv. Mobility, or Volume Through Treatment

To the extent that the materials disposed of off-site would be
treated prior to disposal, Alternative 6 would provide a
reduction in mobility, toxicity, and volume of the organic and
inorganic chemical contaminants present at the Site.   Alternative
5 would significantly reduce the mobility, toxicity,  and volume
of organic contaminants in the source areas having high levels of
organic contamination by permanently removing the organics from
these materials.  Alternative 5 would provide a reduction in the
mobility of the inorganic contaminants through stabilization/
solidification of the source area materials failing TCLP and
placement of all source area materials in a lined containment
cell with a leachate collection system.  Alternative 4 would
provide a reduction in the mobility of the organic and inorganic
contaminants present in the source area materials through
stabilization/solidification of the materials and placement of
the solidified materials  in a lined containment cell with a
leachate collection system.  However, as noted previously, the
long-term effectiveness of stabilization/solidification for
immobilizing organic contaminants has not been demonstrated.
Alternative 3 would not provide a reduction in the toxicity or
volume of the organic and inorganic contaminants in the source
area materials; however,  this alternative would reduce the
mobility of the chemical  constituents through capping, installing
a slurry cut-off wall and pumping groundwater from within the
capped area.  Alternatives 1 and 2 would provide no reduction in
contaminant mobility, toxicity, or volume.

Short-term Effectiveness

Alternatives 1  and 2 would- result in no additional risk to the
community or workers during implementation  (0 months and six
months, respectively),  since source area materials would not be
disturbed.  Alternatives  3, 4,  5 and 6 would each require
approximately one year  to implement and would include activities
such as excavation and  handling of contaminated soils/sludges
that could result in  short-term exposures to on-Site workers and
the community during  implementation due to  the generation' of
fugitive dust.  Mitigation measures such  as water sprays  to
suppress dust would be  implemented to  control short-term
environmental impacts associated with  off-Site dust migration.
Alternative  5 would also  result in the potential exposure to on-
Site workers and  the  community to air  emissions associated with
the ex-situ vapor extraction and bioslurry  treatment  systems.
The air emissions from  these units would  be controlled  by
implementing air  emission treatment  systems and air  emission
monitoring programs  in  accordance with Federal and State
regulations.  Alternative 6 would  also include activities such as
off-Site  transport  of contaminated soils/sludges  that could
                                20

-------
result in potential exposure to the community.   To reduce the
potential risks to the community and the environment resulting
from an accident during transportation, a traffic control plan
would be developed.                               '"

Implementability

All alternatives are technically feasible and could be
implemented at the Site.  Alternatives 1 and 2 are the easiest to
implement, followed by Alternative 6.  A treatability study would
be necessary to demonstrate that Alternative 4
(stabilization/solidification) is able to render the lagoon 7
material nonhazardous based on the characteristic of toxicity.
The nature of the materials, particularly the lagoon 7 materials,
may also pose some problems with the organic treatment options
specified under Alternative 5.  Although additional treatability
studies are warranted to demonstrate the effectiveness of the
Alternative 5 treatment options, it is anticipated that each of
the options could effectively treat all.but the lagoon 7
materials.  Lagoon 7 materials could be effectively treated with
a combination of technologies.

A combination of physical  and chemical factors make the lagoon 7
materials highly problematic to treat: the materials have a high
clay and moisture content, and significant concentrations of both
volatile and semivolatile  organic compounds.  As a result,
problems are likely  to  arise with implementation of each of the
Alternative 5 processes,  if utilized singly to address the lagoon
7 materials.  While  it  is  believed that lagoon 7 materials that
are processed through the  LTTD could be treated to remedial
action objectives, treatability studies have indicated that some
commonly used LTTD units  could experience materials handling
problems while  processing the lagoon 7 materials; prior to
implementing LTTD, additional treatability studies would be
required to assure that such material  handling problems could be
minimized.  Ex-situ  vapor extraction is likely to be  effective  in
handling the volatile fraction of .contaminants in the lagoon  7
materials; however,  it  would not likely be effective  at treating
the  semi-volatile fraction.   Biosluirry, on the other  hand, would
be expected to  be effective  in handling the  semivolatile  fraction
of the lagoon  7 materials.  Therefore, it appears  as  though use
of ex-situ vapor extraction for  treatment of volatiles,  and
 subsequent treatment of semivolatiles  with bioslurry,' would be
 the  most  implementable combination of  treatment  options  under
Alternative  5;  this combination would avoid  the  material  handling
problems  which would be expected to be encountered with LTTD.
                                 21

-------
Cost

According to the present worth cost estimates for .all
alternatives evaluated, Alternative 6 ($32., 679,764)  would be the
most costly alternative to implement, followed by Alternative 5
($8,535,000) .   The present worth cost for Alternatives 4 and 3
would be about the same ($5,794,983 and $5,560,128,
respectively).  Alternatives 2 and 1 would be the least costly to
implement ($328,660 and $0, respectively).   Present worth
considers a 5% discount rate, and a 30-year operational period
for Alternatives 2, 3, 4 and 5.  Since Alternatives. 6 arid 1 do
not require any O & M costs, their present worth costs are
equivalent to their capital cost.

State Acceptance

The State of New York, through the NYSDEC,  concurs with EPA's
selected remedy.  The NYSDEC's letter of concurrence is in
Appendix IV.

Community Acceptance

The Proposed Plan indicated  that EPA's preferred  alternative was
Alternative 5 with the LTTD  treatment option.  A  number of
commenters voiced their opposition to any on-Site treatment which
consisted of combustion of contaminants  and  subsequent emission
of any quantity of hazardous materials.  The residents were
concerned that some of the potential LTTD units were in effect
incinerators.  The community preferred that  the materials be
excavated and transported  off-Site for treatment  and/or disposal
 (i.e., Alternative 6).  However, EPA received  a letter from the
Deerpark Environmental Commission  stating that "...all things
considered, Alternative 5  is the best one."  Other  commenters,
notably some of the PRPs for the Site, indicated  their preference
for on-Site treatment so long  as the organics  treatment process
incorporated  the bioslurry and vapor extraction treatment
options, rather than  LTTD.   These  and other  comments and  concerns
received from the  community during the public  comment period  are
identified  and addressed in the Responsiveness Summary which  is
attached as Appendix.V to  this document.

SELECTED REMEDY

Based upon  consideration of the requirements of CERCLA,  the
detailed  analysis  of  the  alternatives,  and public comment,  EPA
 and NYSDEC  have  determined that Alternative  5 (excluding the  LTTD
option), which calls  for  remediation- of  the  contaminated source
 area  materials  via stabilization/solidification of inorganics and
 ex-situ vapor extraction  and bioslurry of  organics, is the
 appropriate remedy for the first  operable unit of the Carroll and
 Dubies Superfund Site.  It is important to highlight that
 materials  from lagoons 1,  3- and 8 (approximately 10,100 cy)  which

                                22

-------
contain high concentrations of organic contaminants would be
treated via ex-situ vapor extraction, while the lagoon 7
materials  (approximately 3,400 cy of highly contaminated
materials) will be treated via ex-situ vapor extraction
 (treatment primarily  targeted at the volatile organic fraction of
organics) followed by bioslurry  (treatment targeted at the
.semivolatile fraction of organics).  LTTD has been specifically
excluded from  the selected remedy due to potential implementation
problems, significant cost, and public  (including responsible
party) opposition.

The selected remedy permanently removes organic contaminants from
source area materials and reduces the mobility of inorganic
contaminants through  stabilization/solidification and placement
of source area materials in a.lined containment cell constructed
on-Site.  Alternative 5 ensures that no leaching of contaminants
to the underlying aquifer will occur.  The elimination of cross-
media impacts  will have a positive  impact on the effectiveness of.
any future groundwater restoration  program that could be
implemented at the Site.

Aside from Alternative 6, Alternative  5 is the only alternative
that  permanently removes the  significant  levels of organic
contaminants  from the source  area.   However, Alternative  6  is
over  three times the  cost of  Alternative  5 and will not comply
with  the  statutory preference for treatment as. a principal
 element,  if the  materials are not treated prior to disposal.  The
 other proposed alternatives which cost much less than  the
preferred alternative do not  permanently  remove contaminants  from
 the source area materials.  The  preferred alternative  will
 provide  the best balance of  trade-offs among  alternatives with
 respect  to the evaluating  criteria.  EPA and  NYSDEC believe that
 the preferred alternative will be protective  of human  health and
 the environment,  comply with ARARs, be cost effective,  and
 utilize  permanent  solutions  and alternative treatment
 technologies  or resource  recovery technologies  to  the  maximum
 extent practicable.   The  remedy also will meet  the statutory
 preference for the  use  of  treatment as a principal element.

 The major components of the  selected remedy include:

      o  Excavation of all materials from lagoons 1,  2,  3, 4,  6,  7
      and 8,  as well as the soils in the vicinity of those
      lagoons,  which exceed the excavation levels specified in the
      Selected Remedy section of the Decision Summary..  EPA's
      current estimate of the volume of the materials requiring
      excavation is approximately 20,300 cubic yards (cy)  .
      However,.the actual volume will be further determined during
      the implementation of the remedy.

      o  Treatment of excavated soil/sludges which contain organic
      •constituents above the treatment levels specified in the

                                 23

-------
     Selected Remedy Section of the  Decision Summary  (estimated
     at  13,800 cy)  via on-Site ex-situ vapor extraction.

     o  Additional treatment of lagoon 7  soils/sludge's  (estimated
     at  3,400 cy)  via on-Site ex-situ bioslurry (treatment
     targeted primarily for semi-volatile contaminants).

     o  Stabilization/solidification of soils/sludges which fail
     the Resource Conservation and Recovery Act's  TCLP  for
     inorganic constituents (estimated at 5,700 cy) .

     o . Placement of treated and untreated soils/sludges  in a
     lined and capped cell consistent with modified requirements
     of  New York Code of Rules and Regulations Part 360.  The
     base of the cell will consist of a high density polyethylene
     (HDPE)  liner and a sand drainage layer.   The  cell  will be
     sloped to a leachate collection system.   The  cap will
     consist of a .low-permeability clay  layer, an  HOPE  membrane,
     a sand drainage layer and a topsoil  cover layer.

     o  Development of an air-monitoring  system and installation
     of  air pollution control equipment  to ensure  compliance with
     air pollution control regulations;  and

     o  Recommendations that deed and well restrictions be
 '.•   imposed to protect the integrity of  the  cap.

Although the use of the bioslurry process to  treat lagoon 7
materials appears to be promising, further treatability studies
are necessary to demonstrate that this  process can reduce the
complex mix of constituents in lagoon.7 to remediation goals.
Because of the existing uncertainty, a contingency remedy will be
implemented if treatability study results indicate that bioslurry
in combination with ex-situ vapor extraction will not be
effective in reducing the  levels of contaminants in lagoon 7
materials, particularly semi-volatile contaminants, to
remediation goals. . The maj.or  components of the contingency
remedy are identical to those  of the selected remedy with the
following exception:

     Excavation and off-Site  treatment (as necessary) and
     disposal of  lagoon 7  materials at a RCRA (Subtitle C)
     permitted treatment,  storage and disposal  facility; it  is
     assumed that thermal  treatment, i.e., incineration or  low
     temperature  thermal  treatment, will be necessary to reduce
     the contaminants  to  appropriate LDR levels.

Off-Site thermal  treatment was selected  as the  contingency remedy
rather  than  on-Site  LTTD,  due to implementability concerns,  as
well  as  community and responsible party  opposition to  treatment
of  these or  other materials on-Site with a thermal treatment
unit.   Although the  cost  estimate for treating these materials

                                24

-------
off-Site appears to be much higher than on-Site treatment with
LTTD (approx. $5.7M vs $3.2M), the off-Site cost estimate was
very conservative, and assumed that all lagoon 7 materials would
require incineration. If the materials were treated off -Site via
LTTD or other means, the cost could be similar to or less than
that for on-Site treatment with LTTD.  This similarity in costs
results from the significant costs ($1.6M) solely related to
mobilizing a LTTD unit to the Site.

Remediation Goals

Two types of remediation criteria have been established.  The
first criterion delineates the source area materials that require
excavation for treatment and/or containment .  The second
criterion determines the cleanup level for the excavated source
area materials; those materials above the cleanup level will
require treatment .

All lagoon materials are to be excavated  for treatment and/or
placement into an on-site containment cell.  The NYSDEC TAGM soil
cleanup levels for  organic compounds were utilized to derive
excavation levels that will be used to determine the volume of
soils impacted by the lagoon  materials which will also require
excavation for treatment and/or containment.  The TAGM soil
cleanup' levels are  objectives which were  established by NYSDEC
and are conservatively set at concentrations that are protective
of human health and groundwater quality.  Therefore, contaminants
of concern  (COCs) were selected for  comparison  to the NYSDEC TAGM
levels based on:  their mobility  (propensity to  migrate from the
soil to the  groundwater); their frequency of detection in the
soil and in  the groundwater,  and  their concentration level.  The
organic indicator COCs and their  excavation levels are as
follows :
Indicator COCs .

Benzene
1, 2-Dichlorobenzene
1,4-Dichlorobenzene
Di-n-butylphthalate
Naphthalene
Tetrachloroethene
Toluene
Trichloroethene
                                     Excavation Level  (ppm)

                                            0.06*
                                            7.9
                                            6.0
                                            8.1
                                           13.0
                                            1.4
                                            1 . 5
                                            1 . 0
      "The practicality  of  excavating  to  this level will  be
      evaluated upon obtaining additional environmental data
      during the remedial design.
                                 25

-------
All excavated source area materials will be placed into an on-
site containment cell which will further mitigate the leaching of
contaminants to the underlying groundwater.  Source area
materials containing contaminants which exceed the treatment
levels will be treated prior to placement in the on-site
containment cell.  The NYSDEC TAGM levels and the RCRA-universal
treatment standard  (UTS), were utilized to derive treatment
levels for the organic indicator COCs.  The UTS were recently
promulgated (September 19, 1994) under the RCRA LDRs. program for
listed wastes, as well as for those materials  (including soil and
debris) containing organic constituents at levels which a 'waste
is considered hazardous based on the characteristic of toxicity,
i.e., those identified with the RCRA codes D010 through D043
based on TCLP  (organic TCLP constituents).  The UTS for TCLP
constituents are considered to be applicable treatment standards
for characteristic wastes present at the site.  The least
stringent TAGM or.UTS number was utilized as the treatment level
for those organic indicator COCs which are not TCLP constituents.

The treatment levels for the organic compounds are as following:

     Indicator COCs                 Soil Treatment Levels  (ppm)

     Benzene                              10.0
     1,2-Dichlorobenzene                   7.9
     1,4-Dichlorobenzene                   6.0
     Di-n-butylphthalate            . •  •   28.0
     Naphthalene                           13.0
     Tetrachloroethene                     6.0
     Toluene                               10.0
     Trichloroethene                       6.0

Additional  indicator COCs may be added to  this  list  at  the
conclusion  of  the bioslurry  treatability study,  if  the  study
indicates that  significant levels  of  degradation products  are
generated during the biodegradation of the lagoon  7  materials.
Additionally^  if treatability study data indicate  that  bioslurry
combined with ex-situ vapor  extraction will  not effectively treat
lagoon 7 materials,  the contingency remedy will be  implemented;
under  this  scenario, the lagoon 7  materials  would  be excavated
and treated off-Site via a specific technology or  to treatment
levels specified by the LDRs.

For the inorganic contaminants,  the highest  level  of indicator
contaminants detected  in the background soil samples collected
 from the Site will be  utilized to  determine  the extent of
 excavation.  Chromium and nickel are  being used as indicator
 chemicals.   The highest levels  of  chromium and nickel detected in
background samples were 61.9 ppm and  36.7 ppm, respectively.
 Lagoons 6  and 8 and any other excavated materials which fail the
 RCRA^-TCLP levels for inorganic constituents will require
 stabilization/solidification.   Stabilized/solidified- materials

-------
will be subject to. further TCLP testing prior to placement in the
lined cell to ensure that the treated material no longer exceeds
the RCRA-regulated TCLP levels  (e.g., 5.0 ppm for chromium and
for lead).  In addition, materials treated to reduce the leachate
concentration are required to have an unconfined compressive
strength of at least 3,500 pounds per square foot as determined
by ASTM D-21^6.

The estimated amount of source  area material that would be
excavated for treatment and/or  containment is 20,300 cy. The
breakdown of the 20,300 cy by lagoon is as follows: 2,600 cy from
lagoon 1; 3,950 cy from lagoon  2; 2,300 cy from lagoon 3; 2,310
cy from lagoon 4; 520 cy from lagoon 6; 3,420 cy from lagoon 7;
and 5,200 cy from lagoon 8.  This estimate will be refined during
the soil sampling to be conducted during the implementation of
the. remedy.

STATUTORY DETERMINATIONS

Under its legal authorities, EPA's primary responsibility at
Superfund sites is to undertake remedial actions that are
protective of human health and  the environment.  In addition,
Section 121 of CERCLA establishes several other statutory
requirements and preferences.   These specify that when complete,
the selected remedial action for the Site must comply with
applicable or relevant  and appropriate environmental standards
established under federal and state  environmental laws unless a
statutory waiver is justified.  The  selected remedy also must be
cost-effective and utilize permanent solutions and alternative
treatment technologies  or resource-recovery technologies to the
maximum  extent practicable.  Finally,  the statute includes a
preference for remedies that employ  treatment that permanently
and significantly reduces the volume,  toxicity, or mobility of
hazardous substances.   The following sections discuss how the
selected remedy meets these  statutory  requirements.

Protection of Human Health and  the Environment

Alternative  5  and the contingency remedy are  considered to be
fully responsive to this  criterion and to the  identified remedial
response objectives.  The selected remedy and contingency remedy
protect  human  health  and  the environment through  the treatment  of
the more highly  concentrated organic contaminants  in the source
area  materials,  the  immobilization of  the more  highly
concentrated inorganic  contaminants  and the  placement of source
area  materials into  a lined  containment cell with a multi-layered
cap and a leachate  collection system.
                                 27

-------
Compliance with ARARs

Alternative 5 and the contingency remedy will comply with all the
chemical-, action-, and location-specific ARARs.  Chemical
specific ARARs are usually health- or risk-based numerical values
used to determine acceptable concentrations of chemicals that may
be found in or discharged to the environment  (e.g., maximum
contaminant levels  (MCLs) that establish safe levels of
contaminants in drinking water); location-specific ARARs restrict
actions or contaminant concentrations in certain environmentally
sensitive areas .(e.g., floodplains and wetlands); action-specific
ARARS are usually technology- or activity-based requirements or
limitations on actions or conditions involving specific
substances  (e.g., RCRA standards applicable to generators of
hazardous waste).  The specific ARARs for the selected remedy and
contingency remedy are the same and are listed below.

Action-specific ARARs:

     *  CAA-National Ambient Air Quality Standards  (40 CFR 1-99)

     *  CAA-Prevent ion of Significant Deterioration of Air
        Quality  (40 CFR  51.2)

     *  CAA-New Source Performance Standards  (40 CFR  60)

     *  CAA-National Emission  Standards for Hazardous Air
        Pollutants  (40 CFR 61)

     *  DOT-Rules  for Transportation of Hazardous  Materials
         (49 CFR Parts 107, 171.1-172.558)

     *  New York  State Air Resources Regulations  - General
        Provisions  (6 NYCRR  Part  200)

     *  New York  Emissions Testing, Sampling,  and Analytical
        Determinations  (6 NYCRR Part 202)

     *  New York  General Prohibitions  (6  NYCRR Part 211)

     *  New York  Regulations for  General  Process Emission Sources
         (6  NYCRR  Part 212)

      *  New York  Air Quality Classification System (6 NYCRR Part
         256)

      *  New York Air Quality Standards (6 NYCRR Part 257)

      *  New York Air Quality Area Classifications - Orange County
         (6 NYCRR Part 293)

      *   Solid Waste Management Facilities (6 NYCRR Part 360)

                                28

-------
*  Waste Transporter Permits (6 NYCRR Part 364)

*  New York Hazardous Waste Management System. (6 NYCRR Part
   370)

*  Identification and Listing of Hazardous Wastes  (6 NYCRR
   Part 371)

*  Hazardous Waste Manifest System and Related Standards for
   Generators, Transporters, and Facilities
   (6 NYCRR Part 372)

*  Final Status Standards for Owners and Operators of
   Hazardous Waste Treatment, Storage,, and Disposal
   Facilities  (6 .NYCRR Part 373)

*  Land Disposal Restrictions  (6 NYCRR Part 376)

*  NYSDEC Water Quality Regulations for Surface Waters and
   Groundwater  (6 NYCRR Part 700-705)

*  OSHA-General Industry Standards  (29 CFR 1910)

*  OSHA-Safety and Health Standards  (29 CFR 1926)

*  OSHA-Recordkeeping, Reporting, and Related Regulations
    (29 CFR  1904)  .

*  RCRA Section 3003-Standards Applicable to  Transporters of
   Applicable Hazardous Wastes  (40  CFR 170 to 179,  40  CFR
   262 and  263)

*  RCRA-Standards Applicable to Generators of Hazardous
   Waste  (40  CFR 262)

*  RCRA-Standards for Owners and Operators of Hazardous
   .Waste  Treatment,  Storage, and Disposal Facilities (40 CFR
   264)

 *  RCRA-Organic Air  Emissions  Standards for  Process Vents
   and Equipment Leaks  (40  CFR 264,  Subparts  AA and BB)

 *  RCRA-Miscellaneous Units (40  CFR 264,  Subpart X)

 *  RCRA-Surface Impoundments,  Waste Piles,  Landfills and
    Land Treatment Units  (40 CFR 264)

 *   RCRA-Preparedness and Prevention (40 CFR 264.30-264.31)

 *   RCRA-Contingency Plan and Emergency Procedures (40 CFR
    264.50-264.56)
                           29

-------
     *  RCRA-General Standards (40 CFR 264.111)

     *  RCRA-Closure and Post-Closure (40 CFR 264.110-264.120)

     *  RCRA-Land Disposal Restrictions (40 CFR 268)

     *  RCRA-Identification and Listing of Hazardous Wastes
        (6 NYCRR Part 371)

Chemical-Specific ARARs

     *  CAA-National Ambient Air Quality Standards (40 CFR 1-99)

     *  CAA-Prevention of Significant Deterioration of Air
        Quality  (40 CFR 51.2)

     *  CAA-New Source Performance Standards .(40 CFR 60)

     *  CAA-National Emission Standards for Hazardous Air
        Pollutants  (40 CFR 61)

     *  New York Emissions Testing, Sampling, and Analytical
        Determinations  (6 NYCRR Part 202)

     *  New York General  Prohibitions  (6 NYCRR Part 211)

     *  New York Regulations  for General Process Emission Sources.
         (6 NYCRR Part 212)

     *  New York Air Quality  Classification System  (6 NYCRR Part
        256)

     *  New York Air Quality  Standards  (6 NYCRR Part 257)

     *  New York Air Quality  Area  Classifications - Orange County
         (6 NYCRR Part 293)

     *  RCRA-Regulated  Levels for  Toxic  Characteristics Leaching
        Procedure  Constituents  (40 CFR  261)

     *  RCRA-Land  Disposal Restrictions  (40  CFR 268)

 Location-Specific  ARARs

      *   Clean  Water Act (Section 404,  33 USC 1344)

      *   Fish and Wildlife Coordination Act (16 USC  661)

      *   National Historic Preservation Act (16 USC  470)
                                 30

-------
Other Criteria, Advisories, or Guidance To Be Considered

     *  Executive Order 11990 - Protection of Wetlands

     *  Executive Order 11988 (Floodplain Management)

     *  NYSDEC Technical and Operations Guidance Series (TOGS)

     *  NYSDEC Technical and Administration Guidance Memoranda
        (TAGMs)

     *  NYSDEC Air Guide 1 - Guideline for the Control of Toxic
        Ambient Air Contaminants

Cost-Effectiveness

The selected remedy and contingency remedy provide overall
effectiveness proportional to cost.  The estimated present worth
cost of the selected remedy is $8,535,000, which represents
capital and present worth 0 & M costs of $8,105,000 and $430,000,
respectively.  A detailed estimate of the cost of the selected
remedy is provided in Table 9.  The estimated present worth cost
of the contingency remedy is $14,194,600, which represents
capital and present worth O & M costs of $13,764,600 and $430,000
respectively.  A detailed estimate of the cost of the contingency
remedy is presented in Table.10.

Utilization of Permanent Solutions and Alternative Treatment
Technologies to the Maximum Extent Practicable

EPA and NYSDEC have determined that the selected remedy, followed
by the contingency remedy, represents the maximum extent to which
permanent solutions and treatment technologies can be utilized in
a cost-effective manner for the source control operable unit  at
the Site.  Of  those alternatives that are protective of human
health and the environment, EPA and NYSDEC have determined that
this  selected  remedy,  followed by the contingency remedy,
provides the best balance  of  tradeoffs in terms of long-term
effectiveness  and permanence, reduction  in toxicity, mobility or
volume achieved through treatment, short-term effectiveness,
implementability, and cost, also considering the statutory
preference for- treatment as a principal  element and considering
state and community acceptance.
                                 31

-------
Preference for Treatment as a Principal Element

The selected remedy and the contingency remedy address the
principal threats posed by the Site lagoon sludges and soils by
achieving significant reductions in the- concentration of organic
contaminants and by stabilizing/solidifying the inorganic
contaminants.  Therefore, the statutory preference for remedies
that employ treatment as a principal element is satisfied.

DOCUMENTATION OF SIGNIFICANT CHANGES

The preferred alternative presented in the Proposed Plan was
modified to reflect the change in emphasis on the likely type of
process to treat organic contaminants; this change was warranted
by additional information that was presented during and
subsequent to the August 23, 1994 public meeting.  The Proposed
Plan and other information disseminated at the public meeting
indicated that one or a mixture of three different processes
might be used to treat organic contaminants under Alternative 5.
At that time, the emphasis was placed on the use of LTTD as the
likely treatment process with the option for vapor extraction or
bioslurry to be used in place of, or in combination with, LTTD.
As detailed in the Responsiveness Summary, significant public
comment was received during the comment period which opposed the
use of any type of on-Site thermal treatment.  Other comments
.were received indicating that vapor extraction and bioslurry
could be used effectively and at considerably less cost than
LTTD.

Additionally, some preliminary Site-specific treatability study
data indicated that treatment of lagoons 1, 3, and 8 via ex-situ
vapor extraction, and treatment of lagoon  7 materials via ex-situ
vapor extraction  (primarily targeted  for volatile organic
contaminants) and bioslurry  (primarily  targeted  at semivolatile
organic compounds) could be effective.  Therefore, Alternative  5
was modified to reflect  the use of bioslurry and vapor  extraction
to treat  the materials  significantly  contaminated with  organic
compounds.   In addition, Alternative  5  was further modified to
specifically exclude LTTD  from the selected remedy due  to
potential  implementation problems, significant cost,  and public
 (including responsible  party) opposition.

Due  to  the uncertainty regarding the  ability  of  any  on-Site
treatment process  (excluding high  temperature  incineration)  to
effectively treat  the  lagoon 7 materials,  excavation with off-
Site treatment  (as  necessary) and. disposal is  being  selected as a
contingency remedy for these materials.  This component of the
contingency remedy was adapted  from Alternative  6.   Under the
contingency remedy,  as in Alternative 6,  it was  assumed that the
 lagoon 7  materials would need to be treated via  incineration,
although other means of less costly treatment (if necessary)
could be utilized in order -to satisfy LDRs.

                                32

-------
APPENDIX I




  FIGURES

-------
                             FIGURES
Figure 1 - Site Location Map



Figure 2 - Sample Location Map



Figure 3 - Groundwater Monitoring Well Location Map

-------
                                                               FIGURE
                           CARROLL  AND DUBIES  SITE
                            PORT JERV1S,  NEW YORK
                           SITE  LOCATION  MAP
                          2000
SOURCE: USGS 71/2 MIN.TOPOGRAPHIC QUAD.
      PORT JERVIS NORTH, HY-PA 1969.
                                                        8LASLANO & 80UCX ENGINEERS, P.C.
J

-------
        LANDFILL
                                                                                                                                                              LCCEHQ
                                                                                                                                                        MCMrORMO VCU'M GLACUL OUTWASH
                                                                                                                                                        UOMronW HCU.-IN OAOAL 1U
                                                                                                                                                        iMMTORmo «OJ. M ounusViu.
                                                                                                                                                        HOMTORiNO »m. IN eottocx
                                                                                                                                                        COHBORtra
                                                                                                                                                        SCR. BOUND (1103)
                                                                                                                                                        ttDIUtNt SMVUNO IOCAITOH
                                                                                                                                                        Km. OA3 SAUPUNO IOCAHON
                                                                                                                                                        SHOCK mwr (ron SOSMIC sumcr)
                                                                                                                                                        ACCCSS PONT SOL SAUPU
                                                                                                                                                        NTDIWUICM SAWU
     OJCVA1MNS BASED ON NAIUNAI. \CflHCAl. DATUM
»»ioe\«iecimii.»»
   ORAPMC SCAU - in
90     0
 "II"'""
                    ,00
V •€ ww MM suit fBUCAnoN IA«
In chorgo ot_
Doslgned by_
Drown by	
ChacKad by_
CARROLL AND DUBIES SITE
 PORT JERVIS. NEW YORK
                                                                                                                          SAMPLE  LOCATION  MAP
                                                                                                                                                                                      810.06
                                                 o«u
                                                   NOVEMBER 1993
FIGURE
    2

-------
M01t» UVAlmS IUO> W NMCMN. VCTHO* MWH
    MUB.
                   In charge ot	
                     l«n«d bjr	
                   Drcwn by.	
                   Chidm) by	
•LAHAND. BOUCK • UE. tHC.
                                                       CARROU. AND DUBIES SHE
                                                        PORT JERV1& NEW YORK
GROUND-WATER  MONITORING  WELL
           LOCATION  MAP
                                                                                                                                             810.06
                                                                                              JANUARY 1904
FIGURE
   3

-------
APPENDIX II




   TABLES

-------
                             TABLES

Table 1 -  Concentration Averages and Ranges for Lagoons 1-4, 6,
           7, and 8 - Inorganics

Table 2 -  Concentration Averages and Ranges for Lagoons 1-4, 6,
           7, and 8 - Volatile Organics, Semi-Volatile Organics,'
           PCBs, and Pesticides

Table 3 -  Summary of Chemicals of Concern in Soils\Sludges

Table 4 -  Summary of Exposure Pathways

Table 5 -  Available Toxicity Criteria for the Carcinogenic
           Chemicals of Interest

Table 6 -  Summary of .Cancer Risks

Table 7 -  Available Toxicity Criteria for the Noncarcinogenic
           Chemicals of Interest

Table 8 -  Summary of Hazard Indices

Table 9 -  Detailed Cost Estimate for Selected Remedy: Ex-situ
Vapor Extraction, Bioslurry Treatment, Stabilization, and On-Site
Containment

Table 10  - Detailed Cost Estimate for Contingency Remedy: Off-
Site Incineration of Lagoon 7 Materials, Ex-Situ Vapor
Extraction,  Stabilization, and On-Site  Containment

-------
                                                                                                                    TABLE  1
                                                                                                             CARROLL &DUBIES SITE
                                                                                                             POHT JEJM3, NEW YORK

                                                                               CONCENTRATION AVERAGES AND RANGES FOB LAGOONS 1-4.6. 7. AND 8 - INORGANICS
InofQdraQ
Aluminum
Antimony
Aitenio
Barium
Baryfllum
Cadmium
Calehm
Chromium
Coban
Copper
bon
Uad
Magnesium
Manganese
Mercury
Nk**l
Polattium
Selenium
SOvtr
Sodium
Thallium . ' •-
Vanadium
Zno
Cyankto
Lagoon 1
Concentration
Range1
5,600-14,100
<11.2-I6.3'
3.8-7.3
10.8-1,290
<0,234.88
<0.8-t6.8
137-14.400
7.1-113
6.1-11.0
It. 3- 1,490
395-29,200
6.9-1.400
1,710-3.830 .
150-472
<0.1Z-7.2
<9.1-368
< 193-1, 490

-------
                                                                                                                 TABl£    1
                                                                                                                 (Continued)

                                                                                                           CARROU. & DUB1ES SITE
                                                                                                           PORT JERVB. NEW YORK

                                                                             CONCENTRATION AVERAGES AND RANGES FOR LAGOONS 1-4.6. 7. AND 8 - INORGANICS
horgarso
Aluminum
Antimony
Arsenic
Barium
Beiyffium
Cadmium
CaWum
Chromhm
Cobafl
Copper .
kon
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Sttvei
Sodun
ThaUum
Vanadium
Zinc
Cyanide
Lagoon 0
Concentration
Rang,'
5.160-9.620

-------
                                                     TABLE  2
                                               CARROLL & CUBES SITE
                                               POm JERVIS, NEW YORK

COHCENTUATION AVERAGES AND RANGES FOR LAGOONS 1-4. 6. 7. AND 6 - VOLATILE ORBAHICS. SEM-VOLA1ILE ORGANICS. PC8S. AND PESTODCS
PHrametat
VbtaSe Ctganka
Vinyl CNorl*
Melhyfone Chloride
Acetone
Cuban DioJRdt
1,1-OlcHofMlhene
l.t-Diehtoroiilhinf
1,2-Dichloroathene (total)
Chloroform
2-BuUnona
1.1.1-TricNoroelnane
Irichloroethent
1,1,2-Trlchlotoethane
Benzene
4-Methyt-2-P«ntanone
2-H«xanone
TettaeNoioethana
Toluane
Chloiotwrutna
Ethytbenzene
Lagoon 1
Coma nil aBoo
Rang«'
Aveiaga
Conoontfatfofr
lagoon 2
Ctxnenbation
Ranga1
Average
Conoentialian*
LsgoonS
Concentration
Range'
Avnage
Conoonbaliurr

<0,011-
OMedrve*

<00lt-<0.058
0.007- 
-------
                                                     TABIH  2
                                                     (ConbnuBcQ

                                               CARROLL &DUBIES SITE
                                               PORT JERVIS. NEW YORK

CONCENTRATION AVERAGES AND RANGES FOR LAGOONS 1-4.6. T. AND 8 - VOLATHE ORGANIC3. SEM-VDLATIU- OBGANIC3. PCO3. AND PESTtOOES
Paiametet
Total Xylena*
Seml-VolalflaClnjaric.
r»-jnrJ
rnonoi
1.3-DicWo(oberucn»
^^

t ,2-Dichlorobenzena
2-Melhylpnenool
2£-Oxybii(t-cNoiopropane)
4-Melhytphtnol
Nitrobenzene
ItophoionB
1 ,2.4-Trichlorobenzene
Naphthalene
4-CHoroanHina
S-MelhytnaphthBlene
2-CHoronaphthalent
Acenaphlhyl«na
Aeenaphlhena
Dbenzolutan
Lagoon 1
ConoenbaBon
Ranga1

0.021-<8.3*
0.014-0.3*
0.01-<8.3*
0.01
4.18
18.37
67.64
<0.01

<0.37-<0.4B
<0.37-<0.49
<0.37-<0.4B
<0.37-<0.49
0.064-<0.39*
<0.37-<0.4B
0.1-0.78
0.013-0.016*
<0.37-<0.4B
<0.37-<0.49
0.0t8-<0.39*
<0.37-<049
Avmaga
Conoonbabou
0.0058

<0.20
0.16
0.20
0.25
<0.20
<0.20
<0.20 •
<0.20
<0.20
0.16
<0.20
0.32
0.10
<0.20
<0.20
0.15
<0.20

TAGMOanip
(Xiedh**
1.2

0.03
1.6
8.5
7.9
0.1
NA
0.9
0.2
NA
3.4
13.0
0.22
36.4
NA
41.0
90.0
6.2

-------
                                                   TABUE 2
                                                   (Conbu>4

                                              CARROU*. CUBES sire
                                              PORT JDMS. NEW YORK

OONCENIBATK3N AVERAGES AND RANGES FOB LAGOONS 1-4.6.7. AND 8 - VOLATILE ORGANICS. SEMI-VOLATHE ORGANICS. PC83. AND PESTICIDES
PwanwM
2,4-Diribololuam
Diettiytphthalali
4-CNoiophenyl-phenylalher
Fhntana
N-NibDKxfphenytamln* (1) .
Phananlhiana
AnttMcani
Caibareto
Q-n-butylphlhalata
Fluotanlhem
Pyiane
Butyttxnzytphlhalata
3.3'-DicNorabenzidna
Beiuo(a)anlhfacana .
Chryune
bic(2-ElhyDwxyl)ptilhalala
Di-n-odylphlhBlata
GenzofbJIIuoianlhana
Benio(k)lluo)anlhen«
lagoon 1
ConoonUattan
Banga'
<0.37-<8.3
<0.37-<8.3
<0.37-<8.3
<0.37-<8.3
<0.37-<8.3
0.021-22.0
0.025-5.0
0.003-7.5
0.009-48.0
0.037-21.0
0.037-28.0
0.18-0.98'
<0.37-<8.3
0.08-8.8
0.11-10.0
0.048-130
0.054-0.36'
<0.37-6.5
<0.37-5.0
Aveiaga
Concei*allot^
<0.9I

<0.37-<0.49
<0.37-<0.49
<0.37-<0.49
0.12-<0.39*
0.015-<0.39*
<0.37-<0.49
0.047-0.29
0.07-<0.39*
0.24-<0.3B*
<0.37-<0.4B
<0.37-<0.49
<0.37-<0.49
<0.37-<0.49
0.033-0.034'
<0.37-<0.49
<0.37-<0.49
<0.37-<0.4B
Avoiaga
Conoentiotion'
<0.20
0.15
<0.20
<0.20
<0.20
0.17
0.15
<0.20
0.18
0.16
0.20
<0.20
<0.20
<0.20
<0.20
0.14
<0.20
<020
<0.20
TAGMOearafi
Gtioclna*
NA
7.1
NA
350.0
NA
220.0
700.00
NA
6.1
1.9000
665.0
122.0
0.014
3.0
0.4
435.0
120.00
1.1
1.1

-------
                                                     TABLE 2
                                                     (Oonttnuao)

                                                CARROLL &DUHESSTE
                                                PORT JERMS. NEW YORK

CONCENTRATION AVERAGES AND RANGES KOR LAGOONS 1-4.6.7. AND 8 • VOLATILE ORBANICS. SEMI-VOLATltE ORGANICa PCB3. AND PESTICIDES
Paiametar
Benzo(a)pyiana
lndeno(t.2,3-ed)pyitn«
Benzo(g.h,l)peiylana
Lagoon 1
t*imnmi Jialtnii
\AM UW Bl WWII
Rang"1
0.29-4.2
<0.37-<8.3
<0.37-<8.3
Avaag,
Cbnd&nb&fiofr
090
<0.8I
-DDD
EndocUlan SUIala
4.4-DOT
EndrlnAMehyda
Atpha-CHoidani
Gonma-CHoidan*
Aioclo(-t248
Atodor-1254

<0.0037-<0.77
<0.0037-<0.77
<0.0037-<0.77


-------
                                                                                                                TAKE  2
                                                                                                                (CortinuBcO

                                                                                                          CARROLL &LXIHESSfTE
                                                                                                         PORT JERVB, NEW YORK

                                                CONCENTRATION AVERAGES AND RANGES FOB LAGOONS 1-4. 6.7. AND 6 • VOLATILE ORGA
Parameter
A/ockx-1260
Lagoon 1
Concentration
R»«.'
<0.037-<1.5
Average
Concentration*
<0.17
Lagoon 2
Concentration
Range'
<0.035-<1.4
Average
Concentration*
<0.20
Lagoon 3
OoncentiaSon
Range1
<0.035-<0.045
Avoago
ConcentraBon1
<002
Lagoon 4
Ooncenliallon
Rang.'
<0 038-0 055
Average
Concentration*
0.030
TAGMOoanup
Objective*
10.0
 1.
 2.
 3.
 4.
 5.

 6.
 7.
 a.
 9.
The taw«i rang* value I* Ito lower ol either the lowed delected concentration or the toweM detection llmll observed. The upper range It limited to the highest detected concentration observed.
Sample recutl* reported at non-deled were Included In the determination ol average concentration! by using one-hall the detection Rrnlt lor each spedlic constituent.
TAGM cleanup objective - NYSOEC Technical and Administrative Guklence Memorandum fTAGM) No. 4046, November 16,10B2; recommended con cleanup objective to protect ground-water quality.
TAGM cleanup objective lor total PCBe In cubturlace tot.  The TAGM cleanup objective lor PCBt In surface soil It 1.0 ppm.
The upper range value Is the highest delected concentration.
concentration but not In the determination ol the concentiaUon range.
The only delected concentration lor this data eel la the towed value ol the data eet.  Non-dated values greater than this delected concentration exist end have been Included In the determlnaUon ol the concentration average and range.
Thlt table Includes dale coDeded lor only those samples located within the Imlla ol the source are* materials above cleanup levels lor each lagoon.
AD concentrationt ate reported In mgftg (ppm).
NA • not •vaBable.
ISST*

-------
                                                     TABLE  2
                                                     (Cootinueo)

                                                CARROLL &DUBIES SITE
                                                PORT JEIMS. NEW YORK

CONCENTRATION AVERAGES AND RANGES FOB LAGOONS M. 8. 7. AND 8 - VOLATILE ORGANICS. SUM-VOLATILE ORGANICS. PC83. AND PESTICIDES
Parameter
VolaBe Ctganlc*
Vinyl CHwIda
Melhytone Chloride
'Acetone
Cubon DisUBde
1.1-DicHoioethana
1,1-tXchkHwelham
1,2-Dichloio«thene (lolal)
Chtaolocm
2-Butanone
1,1.1-Titehloioethan*
TricHoroelhene
1.1,2-Tfichtofoelhane
Beniene
4-Melhyl-2-Penlinone
2-Hexanone
leUscHoioelhene
Tduen*
CWoioberuena
lagoon 6
ConoerbaHan
Range'
Avetaga
CofioeiitiabQn

.OIS*
<0.010-1.l*
<0.010-<120
<0.010-0.03B*
<0 010-0.54*
0.001-1.900

-------
                                                    TABLE 2
                                                    (Con&wad)

                                               CMVKX1& DUDES StTE
                                               PORT JEfMS. NEW YORK

CONCENTRATION AVERAGES AND RANGES FOH LAGOONS M. 6.7. AND 8 - VOLATILE OnSANICS. SEMI VOIAT1LE ORGANICS. PC83. AND PESTICIDES
Panvmlaf
Elhyftxniana
Total Xytonei
lagoon 6
OonocntaQoofi
Ranga1
0.008- <0.0 15*
<0 01 1-0.02
Avetaga
ConcenUatiorf
0.0064
0.0081
Lagoon 7
Conoanbalion
nanga'
<0 01 1-68'
0.002-310*
Aveiage
Coiccntialiorf
30.50
49.54
lagoon 8
Conoonbaton
Banfl.'
eni«na
Naphlhalerw
4-OHoiosniUne
2-Malhyfnaphttwtena
2-Chlmonaphlhaltna
Ac«naphthyien»
Acenaphlhene
<0.37-<3.1
0.034-0.1'
0.02-0.15'
0.29-0.1'
<0.37-<3.1
<0.37-<3.1
0.093-0.42*
0.14-O.1'
<0.37-<3.1
0.043-O.1*
0.055-0.16'
0.013-0.36'
0.038-0.110*
0.032-O.1*
0.12-0.67*
0.027-0.14*
<064
0.58
0.48
0.62
<0.64
<0.64
0.37
0.59
<0.64
0.58
0.31
0.39
0.30
0.58
0.27
0.36
<0.35-24.00
<0.35-<17.0
0.055-3.3*
0.35-9.1*
0.1-0.33'
<0.35-<17.0
0.073-0.33*
<0.35-.<17.0
0.033-4.7*
<0.35-<17.0
0.043-B10
<0.35-<17.0
0.033-610
0.059-270
0.041-0.054*
0.10-<17.0'
4.12
<2.2I
1.84
2.21
1.67
<2.2I
38.23
<2.21
1.93
<2.21
63.90
<2.21
61.98
20.49
1.50
M2
<0.34-<8.6
0.008-0.72
0.031-7.4
0.14-3.1
<0.34-<6.5
<0.34-<6.5
0.035^)051*
<0.34-<6.5
<0.34-<6.S
0.026-1.1*
0.014-3.0*
0.22-6.5
0.039-9.50
<0.34-<4.2
0.055-<4.Z*
0.071-1.8*
<0.75
0.21
0.93
0.62
<0.7S
<0.75
0.58
<0.75
<0.75
'0.55
0.83
0.99
1.71
<0.39
0.52
0.48
0.03
NA
NA
NA
0.1
NA
0.9
0.2
NA
NA
13.0
0.22
36.4
NA
41.0
90.0

-------
                                                     TABLE 2
                                                     (Continued)

                                               CARROLL & CUBES are
                                               PORT JEIMS. NEW YORK

CONCENTRATION AVERAGES AND RANGES FOR LAGOONS 1-4.6.7. AND 8 - VOLATILE ORGANICS. SEMI-VOLATILE ORGANICS. PC8S. AND PESTtdDeS
Paratnelet
Dbanzohjran
2.4-Oinlliololuent
Delhytphfhalala
4-CNofophenyl-phanyMhef
Flmxena
N.Nitiotodiphenytamlna (1)
Phananthreno
Anttvacena
Caibazole
D-n-butylphlhalale
Ruoranlhena
Pyiene
Butybenzytphlhalale


Benzo(a)anlhfacena
Chrysam
bls(2-Elhythexyt)phlhalal«
Di-ivoctylpnlhalala
Benzo(bjlhio)anthana.
lagoon 8
CancentraHon
Bangs'
0.062-O.461
<0.37-<3.1
0.011-0.38*
<0.37-<3.1
0.042-0.37*
<0.37-O.t
0.1 1-1 1.0
0.008-0.89*
0.008-0.88
0018-0.10*
0.088-12.0
0.11-8.9
0.014-0.10*
<0.37-<3.1
0.061-3.8
0.0854.5
<0.37-2.0*
0.024-0.083*
<0.37-4.4
Aveiaga
ConDenliation*
0.22

-------
                                                     TABLE 2
                                                     (Continued)
                                               CARROLL &DUOES SHE
                                               PORT JERVIS. NEW YORK

CONCENTRATION AVERAGES AND RANGES FOR 1AGOONS M. 6. 7. AND B • VOLATILE ORGANICS. SEMI-VOLATILE OHGAN1CS. PCBS. AND PECTC1DE8
• Parameter
Benzo(k)Ruotanlhane
6anzo(a)pytene
lndeno(l ,2,3-cd)pyi«ne
Benzo(B,h,l)peryten»
Lagoon 6
ConoenbaUon
Range1
<0.37-4.4
<0.37-3.9
<0.37-2.3
<0.37-3.1
Avetage
Coiicentmtion1
1.28
1.20
0.87
0.69
lagoon J
Concent aUoo
Bango"
<0.35-<17.0
<0.3S-<17.0
<0.35-<17.0
<0.35-<17.0
Avnage
CDnoenbalion*
<2.21
<22\
<^2I
<2.2I
Lagoon 8
Cbnoenbatton
nanga'
0.057-0.44'
0.14-0.35*
<0.34-<6.5
0.18-<4.2*
Aveiags
Conoanbafion*
0.53
0.54
<0.75
0.53

TAGMdcunup
Obfedh*'
1.1
11.0
3.2
800
^tesocicte^PCOB . *
alpha BHC
tala-BHC
gamma- BHC
Heplachlw
Endoeullan 1
Dieklrln
4.4'-DDE
4.4'-DDD
Endonjllan SUIalo
4,4'-OOT
EndrlnAktehyd*
Alpna-CHoidana
Gamma-CNotdane
Atoclw-1248

-------
                                                                                                                TABLE 2
                                                                                                                (Continued)

                                                                                                         CARROU. & DUBES STE
                                                                                                         PORT JBWIS. NEW YORK

                                                CONCENTRATION AVERAGES AND RANGES FOR LAGOONS M. 6. 7. AND B-VOLATILE ORGANICS. SEM-VOIAT11E OOGANKS. PC8S. AND P6STK3DES
Ptvameler
Atodot-1254
AfOctOf-1260
Lagoon 6
GonoBntrafion
Range'
O.OI4-<0.74'
0.02S.<0.7«'
Average
Concentration
0.12
0.12
Lagoon/
Concentration
Range'
0.025- < 1.8*
<0036-0.65*
Avecaga
Oonoei iliaBon*
0.016
0.19
Lagoon 8
Concentration
Ranga1
<0.034-1.6
<0.034-0.13*
Aveiaga
Cunumtiatton
0.18
0.094
TAGM Cleanup
Objective*
10.0'
10.3*
 teds*

 1.
 2.
 3.
 4.
 S.

6.
7.
a.
9.
10.
II.
 Thf lower range value It lha tower ol either lha lovnsl detected concentration or the (owed detection Until observed The upper range It limited to lha highest detected concentration obcerved.
 Sample results reported at norvdetect wwt Included In lha determination ol average concentrations fay using one-hall the detection limit lor each cpedlic constituent.
 TAGM cleanup objective - NYSOEC Technical and Administrative Guidance Memorandum (TAGM) No. 4046. November 16.1992; recommended soft cleanup objective to protect ground-water quality.
 TAGM cleanup objective lot total PCBt In cubturiace col. The TAGM cleanup objective lor PCS* In curface coll Is t .0 ppm.
 The upper range value li the highest detected concentration. Repotted laboratory detection Omit values gtealet lhan this highest delected concentration exists due to matrix Interferences or olhet teasons. and have been Included In the calculation ol lha averse
 concentration but nol In the daletmlnallon ol-lhe concentration range.
 The only delected conoenbalion tor this data set Is the lowest value ol (he data set. Notvdelecl values greater than this detected concentration exlel and have been Included In the determination ol the concentration average and tangs.
The detection DmU ol 900 ppm reported tot this constituent, which was not delected In the analysis ol sample T7-7 (2-4) was nol Inducted In the determination ol the concentration average and large.
TNs table Indudas data collected tot only (hose samples located within lha limits ol lha source area materials above cleanup levels lor each lagoon.
AD concentialions ate tepotted In rnoAg (ppm).
NA - nol avatlaH*.

-------
                             TABLE 3

                 CARROLL & DUBIES SUPERFUND SITE  -
                   TOWN OF DEERPARK, NEW YORK

          SUMMARY  OF  CHEMICALS  OF CONCERN IN SOIL/SLUDGE
Volatiles

1,2-dichoroethene  (total)
2-butanone
2-hexanone
4-methyl-2-pentanone
acetone
benzene
carbon disulfide.
chlorobenzene
ethylbenzene
methylene chloride
tetrachloroethene
toluene
trichloroethene
xylenes  (total)

Semivolatiles    :

1,2-dichlorobenzene
1,2,4 -trichlorobenzene
1,3-dichlorobenzene
1,4-dichlorobenzene
2-chloronaphthalene
2-methylnaphthalene
4-chloroaniline
4-methylphenol
acenaphthene.
anthracene
benz(a)anthracene
benzo(a)pyrene
benzo(b)fluoranthene
benzo(k)fluoranthene
bis(2-ethylhexyl)phthalate
butylbenzylphthalate
carbazole
chrysene
di-h-butylphthalate
di-n-octylphthalate
fluoranthene
fluorene
naphthalene
phenanthrene
phenol
pyrene

Inorganics

aluminum
antimony
arsenic
barium
beryllium
cadmium
chromium
cobalt
copper
cyanide
iron
lead
magnesium
manganese
mercury
nickel
selenium
silver
vanadium
zinc

Pesticides/PCBs

Aroclor 1254

-------
           TABLE  4

     CARROLL a DUBIES  STE
     POHTJERVIS.  NEW YORK

SUMMARY OF EXPOSURE PATHWAYS
Pathway
ng cation
1
)ermal contact during
bathlrg.
Inhalation of uround water
contomlnanta during
showering. „.,
t
SflUa
IncUentallngestlon

)ermal contact
Surface Sludaa
Ire (dental Ing esllon
Dermal contact
lima -Frame Evaluated :::;:r::-: '• 'Degree of A$scjssme
Receotor Present ;i"-% Futira ': ;•.•'•'":•?: puant:V:'i"eJu^s'?:':
Resbent No Yes X
(Adult art) Child)
ResUent No Yes X
(Adult only)
Resbent No Yes X
(Adult only)
Trespasser Yes . Yes X
(Adult and Youth)
EwavaUon No Yes X
Worker
Trespasser Yes Yes X
(Adult and Youth)
Ewavatloh No Yes X
worker
Trespasser Yes Yes X
(Adult an) Youth)
Trespasser Yes Yes X
(Adult and Youth)
RatioMiotor SolscionorEmlustan :- •• : •
Private wells exist In adjacent areas,
and although contamination las not
currently reached tiese wells, It may
In the future.
See Ingestlonpathway lor tils
medium.
Presence ol VCCs In
ground water.
Acces tt the die Is not eliminated,
and the) unk cars and open land
around the die may be an attraction
to adolescents
Construction arid eicavatlon activities
may occur In the luture
See Ingesllonpathway lor tils
medium and receptor.
See Ingostlonpathway lor Ills
medium and receptor.
Acces to the site Is not eliminated,
and the | unk cars and op en land
around the site may be an attraction
to adolescents.
See Ingesllonpathway
<:•: ;-':'DatB"Evaiuaied .-.•:•'••'••"•' : ' "' .
Pending
Pending
Pending
Atton-sltesdl samples.
All on-slto sdl samples
All on-slte sdl samples.
All on - site sdl samples.
Surflclal slidge samples.
Surtfclal sludge samples.

-------
TA8l£ 4 (Contt)
P|}thwaY
Sibsuiface and surface
Sludafi..(£fi!(iiliifldL_
Incidental Ingestlon
Dermal ton lac 1
Laaaon 1 ehuidlm water
Dermal contact
All «•.
nhalatlon ot Emlsskxawb
Partbulates (rom Soda

nhelatlon of emissions and
Partbulates horn Sludges '

RecfiBtQl

Excavation
woiker .
Excavation
woiker
Trespasser
(Adult and Youth)
Trespasser
(Jutland Youtr^
Excavation
woiker
Trespasser
(Adult and Youtf<
Excavation
woiker

PreseM FiAjta^.'' :::V:;::f::;:x:Quan»'H::;::-:'Dual':W Halkmala (or Seles ton or Exclusion . . Data Evaluated

No Yea X • Construction and excavation activities All sludge samples.
may occur In the Mure.
No Yes X . See Ingestlonpathway for tils All sludge samples.
medium.
Yea Yes X Access to Ugoon 1 1s not eliminated and Lagoon 1 standing water sample and Hsdiplbate.
may be an attraction to adolescents especially.
Yes Yes X Dry soUcondllons end winds couW All son samples.
generate dusto.
No Yea X Dry soil conditions, winds, aid used . All soil tamples.
' heavy machinery and vehicles couU
generatedusb.
Yes Yes X Dry dudge conditions and wlrds could SullclalBluige samples.
generate dusts.
No ' Yes X Dry sludge conditions, winds, find use ol All sludge samples.
heavy machinery aid vohfckis couW
genucitedustt.

-------
                                                TABLE 5
                                           CARROLL & OUBIES
                                         PORT JERVIS. NEW YORK

             AVAILABLE TOXICITY CRITERIA FOR THE CARCINOGENIC CHEMICALS OF INTEREST

Chemical
VOLATILES
riethylene chloride
ienzene
'etrachloroethene
Trichloroathene

SEMIVOLATILES
1 ,4-OtohlorobenzBne
Bis(2-etnylnexyf)phtnalata
Carbazole
n— Nctrosodiphenytamine
3enzo(a)pyrene
JenzD (a) anthracene
Benzo(b)rluoranthene
Benzo(k)fluoranthene
Chrysena
PCS*
ArodoM2S4
INORGANICS
Arsenic
Beryllium
Cadmium
Chromium (VI)
Nickel
subsutfide
refinery dust

Slope
Factor
1 /(mo/ko/davt

0.0075
0.029
0.051
0.011


0.024
0.0t4
0.02
0.0049
11.5
1.15
1.15 .
1.15
1.15

7.7

ND
4.3
ND
ND

ND
ND
Oral Route-: I! :
HHEG
Reference Class Reference

B2
A
B2 "
82


c
82
•-82 . ..
"82 "
"* B2 *
••• B2 *
82
82
82

82

A
82
82
ND . • "

82
ND •*
Unit Risk
Factor
l/(mo/m(3H

0.00047
0.0083
0.000*2
0.0017


ND
NO
ND
ND
1.7
0.17
0.17
0.17
0.17

ND

4.3
2.4
1.8
12

0.48
0.24
Inhalation Route •,
Calculated (a)
Slope Factor 'i
1/(ma/ko/dav) Reference «
i
(b) * ij
0.029 • .{
0.00182 " j
0.017 (C) " I
i
•i
::
i
' 'I
i
6.1 . " \
0.61 "* |
0.61 ••• •
o.6i — :,
o.ei — ;
!|
\
\
i
1
15 • i
8.4 * .j
6.3 j
42

1.7 ••
0.84 " !
Notes:
(a) Calculated using the following equation:
     SF 1/(mg/kg/day) » UHF (m(3)/mg) x 70 kg + 20 m(3)/day
(b) As per US EPA (IRIS. 1992) guidance, it is not appropriate to calculate a slope factor..
(c) URF is based on a metabolized dose, thwetore the slope factor has not been catoutted using the unit risk factor.

References:                                                  .
• IRIS, 1992
•• USEPA. 1991d
•*• Criteria based on toxic equivalency to benzo(a)pyrene (USEPA. 1991b).

-------
                                                  TABLE 6

                                           CARROLL & DUBIES SITE  -*
                                           PORT JBWIS. NEW YORK   •'

                                         SUMMARY OF CANCER RISKS
EXPOSURE
PATHWAY

3oi
ncidental Ingestion
Dermal contact
Oust Inhalation
Surficial Sludoe
Incidental Ingestion
De.iiial Contact
Dust Inhalation
Combined Surface/
Subsurface Stud oe
Incidental digestion
Dermal contact
Dust Inhalation
Laaoon 1 Standina Water
Dermal Contact
Ground Water
Ingaition
Dermal Contact
Vapor Inhalation
ijpaSaSiifBjgiihiir^^S^S:^^8
CU RRENT RECEPTOR
Tres
Adult
3E-08
NA
66-09
2E-08
4E-07
6E-09
NE
NE
NE
7E-08
NE
NE
NE
:*•;• 5E-07
assars
Youth
5E-07
NA
3E-08
3E-07
2E-06
3E-08
NE
NE
NE
4E-07
NE
NE
NE
::::;:S.. .:.::> .- ;.:-:,- .- -• 3^iQgfA:;:-::.---:y
FUTURE RECEPTORS

Vorkerp la)
9E-08
NA
3E-06
NE
NE
NE
7E-07
3E-07
8E-08
NE
NE
NE
NE
^as*4E=Q!
Residents ft>
Adult !
NE(c)
NE
NE
NE
NE
NE
NE
NE
NE
NE
TBC(d)
TBC
TBC
:;:;:-::"-:?- -TBC^^

Youtti
NE
NE
NE
NE
NE
NE
NE
NE
NE
NE
TBC
NE
NE
=™ """" -TBC
Notes:

(a) Hypothetical excavation worker.
(b) Hypothetical use of on-site ground water.
(c) NE » Exposure pathway is not evaluated for this receptor.
(d) TBC a To be completed following additional ground-water investigation.
(e) NA » Not applicable. Dermal exposure to soil and sludges only evaluated for cadmium and. PCBs.

-------
                                    TABLE 7
                                CARROLL & CUBES
                             PORT JSTVIS, NEW YORK
ChamicsJ
VOLATIIES
1 .2— Dlchtonoatnana
cis-
trana-
1 ,1 — Oichloroathana
2-Butanona
4-Malhyl-2-pamBnona
Acatona
Caitoon dbulflda

Shtorabanzana
Etnybanzena

Matnylana cnlonda
Tatnchtcroathana
Tduene
Xylanea (total)

SEM1VOLATILES
1,2-OlcMarobanzana
1 ,2.4-Trichlcrabenzana
1 ,4— Olchtorcbanxflna
4C "WITH* Wi Ifl^l lu HlMII HJ
4-CWorotnmn«
4-M«mytpr»noi
Aconoptittwiai
VnttifBCBno
lte(2-atiylhaxyQphthalala
3utytb«xizylphfati8tB
^latttiytphthfttBtat
Dl-n-butytphthatata
3t-n-octylpmn..tatv
nuorwitttaMW
:hxxm
l^aphthaatao*
n^biltio8odtph8flyiatfnin>
Phand
Pyrana
INCRQMUCS
Antimony
Aiaanie
Barium
Sarylllum
Cadmium
food
v««ter
Chromium (111)
Chromium (VI
Ccppar
Cyanlda
Manganaaa
Marcuty
Ntakal
Satenium
SOvar
Thallium
\tanadlum
Zinc
RID
mo/ko/dav) Rafaranca

0.01 "
0.02
0.1 **
0.05
o.os ••
0.1
0.1
0.02
0.1
0.08
0.01 *
02
Z


0.09
0.00131 ••
NO
Q on •
u.uo
0.004 ***
0«J4
0.05 • ~
0^8 *
OJ *
0.02 •
0.2
Q£
0.1
0.02 ••
0.04
0.04
km *
NU
0.8
O03

OJO004 •*
0.0003
0X35
0.005

0.001
0.0005
1 •
0.005 •
ND •— •
ftn^ •
0.1
OAXQ • **
0X32
0.005
OXX33 "
QX30Q07 ••
0.007 —
0^ ~
RIC RID '|
(mo/mon (mo/ko/dav) Refaienca '

NO
NO
0.5 •
03
ojaa
NO
0X31
0.02
1
3
kin
NU
2
0.3


0.2
0.009
0.7
Kin
rau
wn
r»w
NO
hC
km
Nu
NO
NO
NO
ND
NO
ND
ND
NO
km
MJ
kafl
NU
NO
NO

ND
NO
0.0005
NO

NO
NO
ZOE-08
ZOE-06
NO
NO
0X3004
OXX303
NO
NO
NO
NO
NO
NO
!
1
1
i
O 1 ** i
U. 1 J
ox» *• i
002 " )
1
OXX33 *• 1
0.008 **
0.3 «
014 **
0.8 "
0.09 **


0.08 •*
0.003 **
o o ••
Q^£

j





i
j


4




I
0.0001 ** 1
1
t

•

ee-07 *•
86-07 **


OXXX31 •
8E-05 ~






(a) Catajl«^iBingtt» following aqua**:
     RID (mg/kg/day) • RIC (mo/m(5) x 2O m(3)/e*y * 70 kg
• IRIS. 1002
•* US6PA, 19910
—• 2-MattiytaBpmTialana Is avaluatad using attarta lor riapMtialana.
•**•  USS>AMa^umComaminanttjBvali3l.3mgfl_ TMsiabaaadonorgand«pticprepi
     and manfora cannot Da ecnvanM to a haaim -oaaad todcrty

-------
                                                 TABLE 8

                                          CARROLL & DUBIES SITE   '•
                                          PORT JERVIS. NEW YORK

                                       SUMMARY OF  HAZARD INDICES
EXPOSURE
PATHWAY

§23.
Incidental Ingestion
Dermal Contact
Dust Inhalation
Surficial Sludpe
Incidental Ingestion
Dermal Contact
Oust Inhalation
Combined Surface/
Subsurface Sludoe
Incidental Ingestion
Dermal Contact '
Dust Inhalation
Laaoon 1 Standina Water
Dermal Contact
Ground Water
Ingestion
Dermal Contact
Vapor Inhalation
Totfll SflrT H=T»rrt tncficaa
CURRENT RECEPTORS
Trea
Adult
0.002
(d)NA
0.01
6E-05
0.02
NE
NE
NE
0.004
NE
NE
NE
O.D4
assets
Youth
0.02
NA
0.08
O.OS
0.0003
0.1
NE
NE
NE
0.02
NE
NE
NE


Workers (a)
0.05
NA
0.8
NE
NE
NE
0.2
0.0008
2
. NE
NE
NE
NE
FUTURE RECEPTORS
RasiderrS (B\
Adult 1 Youth *
NE
NE
NE
NE!
NEl
NEi
i
NE
NE
NE
NE
TBC (e)
TBC
TBC
TBC
NE
NE
NEi
NE!
NEli
i!
NE!
NE
NE
NE
TBC(e)
NE
NE
TBC
Notes:

(a) Hypothetical excavation worker.
(b) Hypothetical use of on-site ground water.
(c) NE - Exposure pathway is not evaluated for this receptor.
(d) NA »' Not applicable. Dermal absorption from soil and sludges is only evaluated for cadmium and PCBa.
(e) TBC = To be completed following supplemental ground- water investtgatoru

-------
                                  TABLES




            Detailed Cost Estimate for Selected Remedy, Alternative S,




Ex-Situ Vapor Extraction. BioSlurry Treatment, Stabilization, and Qn-Stte Containment-
Ham No

1
2
3
4
5
6
7

8
9
10
11

12
13
14
15
16
17
•18
19
20
21
22
23

24
25
26
27
28
Description
EXCAVATION
Mobilization/Demobilization
Site Clearing
Erosion Control
Construct Equipment Decontamination Pad
Pre Treatment Verification Sampling
Excavation of Soil
Debris Management
CONTAINMENT (FOR TREATMENT AND CLOSURE)
Excavation for On-Site Containment Pad
Install 20 mil HOPE Geomembrane
Install 1'Sand Drainage Layer
Leachate Collection System Wet Well
VAPOR EXTRACTION
Pilot Study for Vapor Extraction
Install 6" PVC Perforated Pipes
Install 6" PVC Non Perforated Pipes
Install 8 Blowers
Air Water Separator, Heat Exchanger, Control Panels,
Wiring Etc.
Weatherproof Housing for Blowers
Electricity Charges tar 1 Year
Operator for 1 Year for Vapor Extraction System
Soil Amendments, Mixing Amendments, and Fertilizer
forl Year
Activated Carbon Units for Treatment of Vented Air
Install 20 mil HOPE Geomembrane
Post Treatment Verification Sampling
SLURRY TREATMENT
Pilot Study for Slurry Treatment
Construct Bioslurry Treatment Pad and Tanks
Install Pumps, Augers. Piping, Electrical Appurtenances,
etc.
Operating Costs for Bioslurry, Chemicals, Power, Labor,
etc.
Slurry Dewateringn/Vater Treatment
Est
Quantity -


1


66
20,300.
2.000

1,500
40,000
1,500



1,906
762
6


381,132
2,000

8
19,000
126






Unit

US
Acre
LS
LS
Samples
CY
CY

CY
SF
CY
LS

LS
LF
LF
Numbers
LS
LS
kWh
MH
LS
N urn DOTS
SF
Samples

LS
LS
LS
LS
LS
Unit Price Mat
&Lab<$)


4,000.00


2.500.00
15.00
50.00

15.00
0.30
15.00



11.00
13.00
7,500.00


0.10
30.00

6,000.00
0.30
1,400.00






Estimated Amount
($)

125,000
4.000
5,000
10.000
165,000
305,000
100,000

23,000
12.000
23.000
50,000

25,000
21,000
10,000
60,000
48,000
5.000
38.000
60,000
25.000
48,000
6,000
177.000

100,000
326,000
51,000
774,000
269,000

-------
29

30
31
32
33

34
35
36
37
38
39
40
41
Post Treatment Verification Sampling
STABILIZATION
Pilot Study for Stabilization
Stabilization of Excavated Soil
Stabilization of Soil Amendments
Post Stabilization Verification Sampling
CLOSURE
Install 2' Clay Layer
Install 20 mil HDPE Geomembrane
Install V Sand Layer
Install Geotextile
Install 24" Cover Layer
Install 6' Topsoil Layer
Backill and Compact Select Fill
Hydroseed Cap
43


17,600
800
18

3,000
46,000
1,800
46,000
3,600
900
20,300
1
Samples

LS
CY
CY
Samples

CY
SF
CY
SF
CY
CY
CY
Acre
1,400.00
-

100.00
100.00
1,400.00

25.00
0.30
15.00
2.00
15.00
20.00
15.00
2,500.00
Subtotal Capital Cost
Administration and Engineering 25%
Contingencies 25%
Total Capital Cost
60,000

25,000
1,760,000
80,000
25,000

75,000
14,000
27,000
92,000
54,000
18,000
305,000
3,000
5,403,000
1,351,000
1,351,000
$8,105,000 '

ANNUAL OPERATION AND MAINTENANCE COST
42
43
44
Annual Groundwater Monitoring
Cap Maintenance
Maintenance of Leachate Collection System



LS
LS
LS



Subtotal Operation «nd MaMenance Cost
. Conttioende. Zi%
Total Operation Mahtenance Co*
Present Worth Factor lot 30 Year. 65%- 1M7
15,000
5.000
2,000
22,000
6,000
28,000
430,000

TOTAL COST
$8,5335,000
Notes:

CF = cubic foot
CY = cubic yard
LF = linear foot
LS = lump sum
SF = square foot
SY = squart yard

-------
                                            TABLE 10




                           Detailed Cost Esftnate for Contingency Remedy




Off-Site Inciiiefalien of Lagoon 7 Materials; Ex-Sftu Vapor Extraction, Stabilization, and On-Site Containment
Item No

1
2
3
4
S
6
7

B
9
10
11

12
13
.14
15
16
17
18
19
20
21
22
23

24
25
26

27
28
Description
EXCAVATION
Mobilization/Demobilization
SHe Clearing
Erosion Control
• '

Pre Treatment Verification Sampling
Excavation of Soil
Debris Management
CONTAINMENT (FOR TREATMENT AND CLOSURE)
Excavation for On-Site Containment Pod
Install 20 mil HOPE Geomembrane
Install 1'Sand Drainage Layer
Leachate Collection System Wet Well
VAPOR EXTRACTION
Pilot Study for Vapor Extraction
Install 6" PVC Perforated Pipes
Install 6" PVC Non Perforated Pipes
Install 8 Blowers
Air Water Separator, Heat Exchanger, Control Panels,
Wiring Etc.
Weatherproof Housing for Blowers
Electricity Charges for 1 Year
Operator for 1 Year for Vapor Extraction System
Soil Amendments, Mixing Amendments, and Fertilizer
for 1 Year
Activated Carbon Units for Treatment of Vented Air
Install 20 mil HOPE Geomembrane
Post Treatment Verification Sampling
OFF-SITE INCINERATION (LAGOON 7)
Transportation
Incineration
Soil Characterization and Verification at Incinerator
Facility
STABILIZATION
Pilot Study for Stabilization
Stabilization of Excavated Soil
Est
Quantity


1


66
20,300
2,000

1,500
40,000
1,500



1,906
762
8


381,132
2,000

8
19,000
126

5,100' .
5,100'



14,200
Unit

LS
Acre
LS
LS
Samples
CY
CY

CY
SF
CY '
LS

LS
LF
LF
Numbers
LS
LS
kWh
MH
LS
Numbers
SF
Samples

Ton
Ton
LS

LS
CY
Unit Price Mat
&Lab($)


4,000.00


2,500.00
15.00
50.00

15.00
0.30
15.00



11.00
13.00
7,500.00


0.10
30.00

6,000.00
0.30
1,400.00

14.00
1,100.00



100.00
||
Estimated Amount
(«

125,000
4,000
5,000
10,000
165,000
305,000
100,000

23,000
12,000
23,000
50,000

25.000
21,000
10,000
60,000
48,000
5,000
38,000
60,000
25,000

6,000
177,000

71,400
5.610,000
12,000

25,000 ||
1,420,000 ||

-------
29
30

31
32
33
34
35
36
37
38
Stabilization of Soil Amendments
Post Stabilization Verification Sampling
CLOSURE
Install 2' Clay Layer
Install 20 mil HOPE Geomembrane
Install 1' Sand Layer
Install Geotextile
Install 24" Cover Layer
Install 6" Topsoil Layer
Backill and Compact Select Rll
Hydroseed Cap
800
18

3,000
46,000
1,800
46,000
3,600
900
20,300
1
CY
Samples

CY
SF
CY
SF
CY
CY
CY
Acre
100.00
1,400.00

25.00
0.30
15.00
2.00
15.00
20.00
15.00
2,500.00
Subtotal Capital Cost •
Administration and Engineering 25%
Contingencies 25%
Total Capital Cost
80,000
25,000

75,000
14,000
27,000
92,000
54,000
18,000
305,000
3,000
9,176,400
2,294,100
2,294,100
13,764,600

ANNUAL OPERATION AND MAINTENANCE COST
39
40
41
Annual Groundwater Monitoring
Cap Maintenance
Maintenance of Leachate Collection System



LS
LS
LS



Subtotal Operation and Maintenance Cost
Contingencies 25%
Total Operation Maintenance Cost •
Present Worth Factor for 30 Years @ 5% = 15.37
Total Present Worth of Operation and Maintenance

TOTAL COST
15,000
5,000
2,000
22,000
6,000
28,000
430,000

14,194,600
Notes:

CF = cubic foot
CY = cubic yard
LF = linear foot
LS = tump sum
SF = square foot
SY = square yard
    1 *
       3,400 cu. yd soil (Lagoon 7) is assumed to weigh 5,100 tons.

-------
        APPENDIX III




ADMINISTRATIVE RECORD INDEX

-------
                      CARROLL fi DUBIES SITE
                        OPERABLE UNIT ONE
                   ADMINISTRATIVE  RECORD FILE
                        INDEX OF DOCUMENTS
1.0  SITE IDENTIFICATION

1.4  Site Investigation Reports

P.   100001 -  Report:  Engineering Investigations at ^Inactive
     100322    Hazardous Waste Sites in the State of New York,
               Phase II Investigations. Carroll and Dubies Sitef
               Town of Deerpark. Orange County. New York.
               prepared by Wehran Engineering, P.C., prepared for
               Project Sponsors for Submission to Division of
               Solid and Hazardous Waste, New York State
               Department of Environmental Conservation, February
               1987.

P.   100323 -  Report:  Preliminary Investigation of the Carroll
     100429    and Dubies Site. City of Port Jervis. Oranae
               County. New York. Phase I Summary Report, prepared
               by Ecological Analysts, Inc., prepared for New
               York State Department of Environmental
               Conservation, November 1983.
3.0  REMEDIAL INVESTIGATION

3.3  Work Plans

P.   300001  -  Report:   Health & Safety  Plan. Remedial
     300053    Investigation/Feasibility Studyr  Carroll  &  Dubies
               Site.  Port Jervis.  New York, prepared by  Blasland
               &  Bouck Engineers,  P.C.,  January  1991  (Revised
               June 1991)..

P.   300054  -  Report:   Quality Assurance Project  Plan.  Remedial
     300250    Investigation/Feasibility Study.  Carroll  &  Dubies
               Site.  Port Jervis.  New York, prepared by  Blasland
               &  Bouck Engineers,  P.C.,  January  1991  (Revised
               June 1991).

P.   300251  -  Report:  Work Plan. Remedial Investigations/
     300325    Feasibility Study. Carroll & Dubies Site. Port
                Jervis. New York, prepared by Blasland &
                Engineers, P.C., November 1990.
Bouck

-------
3.4  Remedial Investigation Reports
P.
P.
     300326
     300762
     300763
     300948
     300949
     301359
               Reportr  Source Area Remedial Investigation.
               Carroll and Dubies Superfund Site. Eort Jervis,
New Yorkf prepared by Blasland & Bouck Engineers,
P.C., December 1993.

Report:  Preliminary  Remedial Investigation
Results. Carroll & Dubies 'Superfund Site. Port
Jervis. New York.  Volume 1 of 2.  prepared by
Blasland.& Bouck Engineers, P.C., October 1992.

Report:  Preliminary Remedial Investigation
Results. Carroll & Dubies Superfund Site. Port
Jervis. New York.  Volume 2 of 2.  prepared by
Blasland & Bouck Engineers, P.C., October 1992,
3.5  Correspondence
P.
P.
P.
     301360 -  Letter to Ms. Sharon L. Trocher, Remedial Project
     301361    Manager, Eastern New York/Caribbean Section I,
               Region II, U.S. EPA, from Mr. Frederick J.
               Kirschenheiter, Senior Project Engineer II,
               Blasland, Bouck & Lee, Inc. , re:  validated soil
               data tables from the Supplemental Hydrogeologic
               Investigation for. the Carroll and Dubies Site,
               January 17, 1994.

     301362 -  Letter to Mr. Tyler E. Gass, C.P.G., Vice
     301362    President, Blasland & Bouck Engineers, P.O.,
               from Ms. Sharon Trocher, Remedial Project Manager,
               Eastern New York/ Caribbean Superfund Section  I,
               Region II, U.S. EPA, re:  correction to item  3
               of the January 8, 1993 letter from Mr. Gass,
               January 12, 1993.

     301363 -  Letter to Mr. Tyler E. Gass, C.P.G., Vice
     301365    President, Blasland &  Bouck Engineers, P.C. ,  from
               Mr. Doug Garbarini, Chief, Eastern New
               York/Caribbean Superfund Section I, Region II,
               U.S. EPA, re:  the New York  State Department  of
               Environmental Conservation's and the U.S.
               Environmental Protection Agency's comments on the
               December 29, 1992 letter: transmitting
               modifications to the  scope of work  for
               supplemental groundwater and on-site soil
               sampling, January 11,  1993.

-------
P.   301366 -  Letter to Ms. Sharon Trocher, Eastern New
     301368    York/Caribbean Remedial Action Brandt, Region....II,.
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,
               Executive Vice President, Blasland &-Bouck
               Engineers, P.C., re:  response to the January 5,
               1993 letter from Doug Garbarini and subsequent
               telephone conversations which have modified some
               of the items addressed in'jbhat particular letter,
               January 8, 1993.

P.   301369 -  Letter to Mr. Tyler E. Gass, C.P.G., Vice
     301372    President, Blasland & Bouck Engineers, P.O., from
               Mr. Doug Garbarini, Chief, Eastern New
               York/Caribbean Superfund Section I, Region II,
               U.S. EPA, re:  the New York State Department of
               Environmental Conservation's and the U.S.
               Environmental Protection Agency's comments on the
               December 16, 1992 scope of work for the four
               tentatively identified former lagoons (TIFLs)
               located adjacent to the Carroll and Dubies
               property, January 5,  1993.   (Attached:  Figure 1,
               New Potential Source  Area. Site Map and Proposed
               Sampling Locations, prepared by Blaslanrl & Bouck
               Engineers, P.C., October 19, 1992.)

P.   301373 .—  Letter to Mr. Doug Garbarini, Eastern New
     301378    York/Caribbean Remedial Action Branch, Region II,
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,
               Executive Vice President,  Blasland  &  Bouck
               Engineers, P.C., re:  submission of various
               documents to Ms. Sharon Trocher regarding the
               tentatively  identified former lagoons (TIFLs), and
               a  response to Attachment 1 of Mr. Garbarini's
               November  20, 1992 letter entitled,  "Additional
               Issues to be Included in the Supplemental Work
               Proposed  on  October  13,  1992", December  29,  1992.
                (Attached:   Figure  1, prepared by Blasland  & Bouck
               Engineers, P.C.,  (undated).)

P.   301379  -  Letter to Ms. Sharon Trocher, Eastern New
     301383    York/Caribbean  Remedial Action Branch, Region II,
               U.S. EPA,  from  Mr.  Tyler E.  Gass,  C.P.G.,
               Executive Vice  President,  Blasland & Bouck
               Engineers, P.C.,  re:  potential  investigation of
               possible adjacent lagoon area, Carroll and  Dubies
                Site,  December 1£>  1992.   (Attachedt  Figure; 1,
               New Potential  Source Area. Site  Map and  Proposed
                Sampling Locations,  prepared by  Blasland &  Bouck
                Engineers,  P.C.,  October 19, 1992.)

-------
P.   301384 -  Letter to Mr. Tyler. E.  Gass,  C.P.G.,  Vice
     301392    President, Blasland & Bouck Engineers,  P.C.,  from
               Mr. Doug Garbarini, Chief,  Eastern New
               York/Caribbean Superfund Section I, Region II,
               U.S. EPA, re:  response to the October  13, 1992
               letter which transmitted the  proposed schedule for
               completing the Remedial Investigation and
               Feasibility Study (RI/FS)"and the proposed scope
               of supplemental work for the  Carroll  and Dubies
               Superfund Site, November 20,  1992.  (Attached:  l.
               Enclosure 1, Report: Additional Issues to be
               Included in the Supplemental  Work Proposed on
               October 13. 1992; 2. Figure 1, prepared by
               Blasland & Bouck Engineers, P.C., (undated); 3.
               Figure 2, Rock Aquifer Monitoring Well.
               (undated).)         .

P.   301393 -  Letter to Ms. Sharon Trocher, Eastern New
     301398    York/Caribbean Remedial Action Branch,  Region II,
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,
               Executive Vice President, Blasland & Bouck
               Engineers, P.C., re:  Carroll & Dubies Site, Port
               Jervis, New York, Supplemental Investigation,
               Scope of Work, October 13, 1992.   (Attached:  Site
               Map and Proposed Supplemental Sampling Locations.
               prepared by Blasland & Bouck, Engineers, P.C.,
               October 6, 1992.)

P.   301399 -  Letter to Ms. Vita DeMarchi, Senior Project
     301400    Hydrogeologist, Blasland & Bouck Engineers, P.C.,
               from Ms. Sharon Trocher, Remedial Project Manager*
               Eastern New York & Caribbean Section I, Region  II,
               U.S. EPA, re:  response  to Ms. DeMarchi's December
               6,  1991  letter proposing the analytical parameters
               for the  second round of  groundwater  samples to  be
               obtained from the  Carroll  and Dubies Site,
               December 13,  1991.

P.   301401  -  Letter to Mr. Tyler E. Gass,  C.P.G., Project
     301403    Director, Blasland & Bouck Engineers,  P.C.,  from
               Ms. Sharon  L. Trocher, Remedial  Project Manager,
               Eastern  New York and Caribbean Section I,  Region
               II, U.S.  EPA,  rer  summary of the agreement
               reached  between  Mr.  William  McCune and Ms.  Sharon
               L. Trocher during telephone  conversations
               occurring on September 17 and 18, 1991,  September
                18, 1991.

-------
P.   301404 -  Letter to Ms.  Sharon Trocher,  Eastern New
     301408    York/Caribbean Remedial Action Branch, Region IX,
               U.S. EPA, from Mr.  Tyler E. Gass,  C.P.G., Vice
               President, Blasland & Bouck Engineers, P.C.,  re:
               proposed methods of resolving the outstanding
               concerns raised in Ms. Trocher's letter dated
               August 21, 1991 and the subsequent meeting of
               September 5, 1991,  September 16, 1991.

P.   301409 -  Memorandum to Mr. Tyler E. Gass, C.P.G.,  Project
     301410    Director, Blasland & Bouck Engineers, P.C., and
               Ms. Debra L. Rothenberg, Esq., Winston & Stravn,
               from Ms. Sharon Trocher, Remedial Project Manager,
               Region II, U.S. EPA, re:  Carroll and Dubies
               Site - summary of 9/5/91 meeting, September 9,
               1991.

P.   301411 -  Letter to Mr. Tyler E. Gass, C.P.G., Project
     301413    Director, Blasland & Bouck Engineers, P.C., from
               Ms. Sharon L. Trocher, Remedial Project Manager,
               Region II, U.S. EPA, re:  concerns of the U.S. EPA
               and the New York State Department of Environmental
               Conservation regarding the sampling depth of the
               sludge samples obtained from lagoons  1 and 2, and
               the limited recharge rate of monitoring well OW-4,
               August 21, 1991.

P.   301414 -  Letter to Mr. Tyler E. Gass, C.P.G.,  Project
     301415    Director, Blasland & Bouck Engineers, P.C., from
               Ms. Sharon Trocher, Remedial Project  Manager,
               Eastern New York and Caribbean  Section I, Region
               II, U.S. EPA, re:  summary of discussion between
               Mr. Robert Patchett of Blasland & Bouck  Engineers
               and Mr. Robert Cunningham, an Environmental
               Protection Agency representative, concerning the
               development of monitoring wells for the  Carroll
               and Dubies Superfund Site, August 9,  1991.
                (Attached:  Transmission  Confirmation Report,
               August  12,  1991.)

P.   301416 -  Letter  to Ms. Sharon Trocher, Eastern New
     301417    York/Caribbean Remedial Action  Branch, Region II,
               U.S.  EPA, from Mr. Tyler  E.  Gass, C.P.G.,  Vice
               President,  Blasland &  Bouck. Engineers, P.C.,  re:
               an addendum to the Work Plan and Sampling and
               Analysis Plan (SAP)  for the Carroll and  Dubies
               Superfund Site  in  Port Jervis,  New  York, August 7,
                1991.

-------
     301418 -  Letter to Ms. Sharon Trocher, Eastern New
     301419    York/Caribbean Remedial Action Branch, Region II,
              U.S. EPA, from Mr. Tyler E. Gass, C.P.G., Vice
              President,  Blasland & Bouck Engineers-, P.C., re:
              acknowledgement of U.S. EPA's letter dated July
              29,  1991 granting approval for use of mud rotary
              drilling method during advancement of the
              boreholes for the till monitoring wells, July 30,
              1991.

     301420 -  Letter to Mr. Tyler E. Gass, C.P.G., Project
     301421    Director, Blasland & Bouck Engineers, P.C., from
              Ms.  Sharon  Trocher, Remedial Project Manager,
              Eastern New York & Caribbean Section I, Region II,
              U.S. EPA, re:  approval of the use of mud rotary
              drilling techniques for the construction of the
              till monitoring wells, July 29,  1991.

     301422 -  Letter to Ms. Sharon Trocher, Eastern New
     301425    York/Caribbean Remedial Action Branch, Region II,
              U.S. EPA, from Mr. William T. McCune, Senior
              Project Geologist II, Blasland & Bouck Engineers,
              P.C., re:   drilling methods considered for use
              in drilling three glacial till boreholes at the
              Carroll and Dubies Site  in Port  Jervis, New
              York, July  26,  1991.
4.0  FEASIBILITY STUDY

4.3  Feasibility Study Reports

P.   400001 -  Letter to Ms. Sharon Kivowitz, Office of Regional
     400096    Counsel, U.S. EPA, from Ms. Debra L. Rothberg,
               Attorney at Law, and Mr. Robert J. Glasser,  Gould
               & Wilkie, re:  submission of the Technical
               Memorandum on behalf of Respondents, Kolmar
               Laboratories, Inc. and Wickhen Products, Inc.,
               July 18, 1994.  (Attached Report:  Technical
               Memorandum. Alternative Remedial Technology
               Evaluation. Carroll and Dubies Site. Port Jervis,
               New York, prepared by Remediation Technologies,
               Inc., prepared for Mr. Robert J. Glasser, Gould
               and Wilkie, and Ms. Debra L. Rothberg, July 15,
               1994.)

P.   400097 -  Report:  Technical Memorandum. Carroll & Dubies
     400113    Site. Port Jervis. New York, prepared by Blasland,
               Bouck & Lee, Inc., February 1994  (Revised March
               1994) .

-------
P.   400114 -  Report:   Source Area Feasibility Study.  Carroll &
     400438    Dubies Site. Port Jervis.  New York,  prepared by
               Blasland, Bouck & Lee, Inc.,  January 1994 (Revised
               May 1994; Revised July 1994).

4.6  correspondence

P.   400439 -  Letter to Ms. Sharon L. Trocher, Remedial Project
     400440    Manager, Eastern New York/Caribbean Section I,
               Region II, U.S. EPA, from Mr. Tyler E. Gass,
               C.P.G, Ph.G., Executive Vice President,  Blasland,
               Bouck & Lee, Inc., re:  Carroll & Dubies Site,
               Port Jervis, New York, Source Area Feasibility
               Study, June 17, 1994.

P.   400441 -  Letter to Ms. Sharon Trocher, Remedial Project
     400446    Manager, Eastern New York/Caribbean Section I,
               Region II, U.S. EPA, from Mr. Tyler E. Gass,
               C.P.G.S., Executive Vice President, Blasland,
               Bouck & Lee, Inc., re:  Source area feasibility
               study, Carroll & Dubies Site, Port Jervis, New
               York, March 23, 1994.   (The  following are
               attached:  1. Table 1, Carroll & Dubies Site, Port
               Jervis, New York, Comparison of Volume of Source
               Area Materials Above Cleanup Levels Proposed
               in source Area Feasibility Study vs. U.S. EPA
               Proposed Alternative Approaches,  (undated); 2.
               Table 2, Carroll  & Dubies Site, Port Jervis, New
               York, Soil Sample Data Above the Source Area
               Feasibility Study Inorganic  Cleanup Levels but not
               Above U.S. EPA Alternative Inorganic Cleanup
               Levels,  (undated); 3.  Figure 1, Carroll and Dubies
               Site, Port Jervis, New York, Horizontal and
               Vertical Extent of Source Area Materials Above
               Cleanup  Levels Using U.S. EPA Alternative 1.
               prepared by  Blasland,  Bouck  & Lee, Inc., March
               1994; 4. Figure 2, Carroll & Dubies Site, Port
               Jervis,  New  York, Horizontal and Vertical Extent
               of Source Area Materials Above  Cleanup  Levels
               Using U.S.  EPA Alternative2. prepared  by
               Blasland, Bouck  & Lee,  Inc., March 1994.)

-------
400447 -  Letter to Ms. Sharon Trocher,  Eastern New
400450    York/Caribbean Remedial Action Branch,  Region II,
          U.S. EPA, from Mr.  Tyler E.  Gass,  C.P.G.,
          Executive Vice President, Blasland & "Bouck
          Engineers, P.C., re:  proposed soil cleanup values
          for priority pollutant inorganics for the Carroll
          & pubies Site, November 30,  1993.   (Attached:  1.
          Table 1, Carroll &  Dubies Site, Port Jervis New
          York, Proposed Priority Pollutant Inorganic
          Cleanup Levels, (undated); 2.   Table 2, Carroll &
          Dubies Site, Port Jervis, New York, Risk-Based
          Preliminary Remediation Goals (PRGs) for
          Inorganics in Soils, (undated).)

400451 -  Letter to Ms. Sharon L. Trocher, Remedial Project
400454    Manager, Eastern New York/Caribbean Section 1,
          Region II, U.S. EPA, from Mr.  Tyler E. Gass,
          C.P.Gi, PHg, Executive Vice President, Blasland &
          Bouck Engineers, P.C., re:  addendum to
          correspondence dated September 24, 1993 pertaining
          to remedial action objectives, Carroll & Dubies
          Site, October 1, 1993.

400455 -  Letter to Ms. Sharon Trocher, Eastern New
400466    York/Caribbean Remedial Action Branch, Region II,
          U.S. EPA, from Mr.  Tyler E. Gass, C.P.G., PHg,
          Executive Vice President, Blasland  & Bouck
          Engineers, P.C., re:  proposed approach  for
          establishing  cleanup criteria to determine the
          extent of source area materials that need to be
          addressed as  part of the Carroll &  Dubies Site
          remedy,  September 24, 1993.   (Attached:  1.
          Memorandum to Regional Hazardous Waste Remediation
          Engineers, Bureau Directors,  and Section Chiefs,
          from Mr. Michael J. O'Toole,  Jr.,  Director,
          Division of  Hazardous Waste Remediation, New York
          State Department of Environmental  Conservation,
          re:  division technical  and administrative
          guidance memorandum:  determination of soil
          cleanup objectives  and  cleanup levels, November
           16,  1992;  2.  Appendix A,  Table 4,  Recommended Soil
          Cleanup Objectives  fma/kg or  ppm.}  for Heavy
          Metals,  (undated);  3.  Conventional Sediment
          Variables.  Total Organic Carbon (TOO. March
           1986.)
                            8

-------
P.   400467 -  Letter to Mr.  Tyler E.  Gass,  C.P.G.,  Vice
     400468    President, Blasland & Bouck Engineers,  P.C.,  from
               Ms. Sharon L.  Trocher,  Remedial Project Manager,
               Eastern New York/Caribbean Section I,"Region II,
               U.S. EPA, re:   the development of soil  cleanup
               numbers for the Carroll & Duties Sewage Disposal
               Site, May 21,  1993.
7.0  ENFORCEMENT

7.3  Administrative Orders

P.   700001 -  Administrative Order on Consent,  in the matter of
     700030    Kolmar Laboratories, Inc.,  and wickhen Products,
               Inc., Respondents, Index No. II CERCLA - 00202,
               February 8, 1990.  (Attached:  i.  Figure 1, Map:
               Site Location Map. Carroll and Dubies Site,
               (undated); 2. Appendix II,  Outline of
               Modifications to EPA RI/FS Work Plan. Carroll and
               Dubies Site, (undated); 3.  Map:  Field
               Investigation Location Map, prepared by Blasland &
               Bouck Engineers, P.C., (undated).)

7.7  Notice Letters and Responses - 104e's

P.   700031 -  Notice letter to Honorable R. Michael Worden,
     700032    Mayor, City of Port Jervis, from Mr. William
               McCabe, signing for Mr. George Pavlou, Acting
               Director, Emergency and Remedial Response
               Division, Region II, U.S. EPA, re:  notification
               that the City of Port Jervis may be a potentially
               responsible party of the Carroll & Dubies
               Superfund Site, April 22, 1993.

P.   700033 -  Notice letter to Messrs Joseph Carroll and Gustave
     700037    Dubies, Carroll and Dubies Sewage Disposal
               Facility, Inc., Mr. Adolf A. Maruszewski,
               President, Kolmar Laboratories, Inc., Mr. Richard
               G. Holder, President, Reynolds Metal Company,  Mr.
               Jere D. Marciniak, President, Wickhen Products,
               Inc., from Mr. Stephen D. Luftig, Director,
               Emergency and Remedial Response Division, Region
               II, U.S. EPA, re:  offer to  conduct  a remedial
               investigation and feasibility study  at the Carroll
               & Dubies Superfund Site, September 25, 1989.

-------
8.0  HEALTH ASSESSMENTS

8.1  ATSDR Health Assessments

P.   800001 -  Report:   Preliminary Health Assessment for Carroll
     800025    & Dubies.  Port Jervis.  Orange County.  New York,
               prepared by New. York State Department of Health
               Under Cooperative Agreement with the Agency for
               Toxic Substances and Disease Registry, July 31,
               1991.


10.0 PUBLIC PARTICIPATION

10.2 Community Relations Plans

P.   10.00001- Report:   Community Relations Plan. Carroll and
     10.00027  Dubies Sewage Disposal Site, Deerpark. Orange
               County.  New York, prepared by Alliance
               Technologies Corporation,  prepared for U.S. EPA,
               June 14, 1991.

10.6 Fact Sheets and Press Releases

P.   10.00028- Fact Sheet:  Superfund Update. Carroll and Dubies
     10.00033  Site. Town of Deerpark. Orange County. New York.
               Fact Sheet #2,  Status of Current EPA Remedial
               Activities, at the Carroll and Dubies Site.
               January 1993.

P.   10.00034- Fact Sheet:  Superfund Update, Carroll and Dubies
     10.00039  Site. Town of Deerpark. Orange County. New York.
               Fact Sheet II,  EPA to Conduct Investigation of
               Carroll and Dubies Site. May 1991.

10.10 correspondence (FOIA)

P.   10.00040- Letter to Ms. Frances Hodson, from Ms. Sharon
     10.00042  Trocher, Remedial Project Manager, Eastern New
               York/Caribbean Section, Region II, U.S.  EPA, re:
               response to Ms.  Hodson's March 28, 1994  letter
               requesting information on the status  of  the
               Carroll and Dubies Site, April 22, 1994.
                (Attached:  Letter to Ms. Sharon Trocher, Remedial
               Project Manager, U.S. EPA,  from  Ms.  Frances
               Hodson, re:  request for  information regarding  the
               Carroll and Dubies Superfund Site, March 28,
                1994.)
                                10

-------
P.   10.00043- Letter to Ms. Frances Hodson,  from Mr.  Doug
     10.00045  Garbarini, Chief,  Eastern New  York/Caribbean
               Section I, Region II, U.S.  EPA,  re:   response to
               Ms. Hodson's September 23,  1992  letter requesting
               an update on the Carroll and Dubies  Superfund
               Site, November 16, 1992.  (Attached:   1.  Update
               for the Carroll and Dubies  Superfund Site.
               November 1992; 2.  Letter to Mr.  William McCabe,
               Chief, New York/Caribbean Remedial Action Branch,
               Region II, U.S. EPA, from Ms.  Frances Hodson, re:
               request for information regarding the Carroll and
               Dubies Superfund Site, September 23,  1992.)

P.   10.00046- Letter to Ms. Frances J. Hodson, from Ms. Sharon
     10.00047  Trocher, Eastern New York/Caribbean Section I,
               Region II, U.S. EPA, re:  response  to Ms. Hodson's
               November 12, 1991 letter concerning the status of
               the Carroll and Dubies Superfund Site, November
               17, 1991.   (Attached:  Letter to Ms. Sharon
               Trocher, Remedial Project Manager,  Eastern New
               York/Caribbean Section I, Region II, U.S. EPA, re:
               request for information regarding the Carroll and
               Dubies Superfund Site, November 12,  1991.)
                                 11

-------
                      CARROLL &  DUBIES SITE
                    OPERABLE UNIT ONE UPDATE
                   ADMINISTRATIVE RECORD PILE
                       INDEX OF DOCUMENTS
4.0  FEASIBILITY STUDY

4.6  Feasibility correspondence

P.   400469 -  Fax transmittal to Ms.  Sharon Trocher,  Remedial
     400474    Project Manager, U.S.  EPA,  Region II,  from K.
               Jones, Remediation Technologies Incorporated, re:
               Cost Estimates for Modified Remedial Alternatives,
               plus LTTD, August 3,  1994.   (Attached:   Cost
               Estimates for Modified Remedial Alternatives,
               (undated).

10.0 PUBLIC PARTICIPATION

10.9 Proposed Plan

P.   10.00048- Plan:  Superfund Proposed Plan, Carroll and Dubies
     10.00059  Sewage Disposal Inc.,  Town of Deerpark, Orange
               County, New York, prepared by U.S. EPA, Region II,
               August 4, 1994.

-------
                     CARROLL AND DUBIES SITE
                    OPERABLE UNIT ONE UPDATE
                   ADMINISTRATIVE RECORD PILE
                       INDEX OF DOCUMENTS
4.0  FEASIBILITY STUDY

4.2  Feasibility Study Work Plans

P.   400475 -  Plan:  Vapor Extraction and Bioslurry Treatability
     400495    Investigation Workplan. Carroll and Dubies Site.
               Port Jervis, New York, prepared for Mr. Robert J.
               Glasser, Gould and Wilkie, and Ms. Debra L.
               Rothberg, Periconi & Rothberg, P.C., prepared by
               Remediation Technologies, Inc., July 25, 1994.
                                    (

4.3  Feasibility Study Reports
P.   400496
     400513
P.
400514
400539
P.
400540
400675
Letter to Ms. Sharon Trocher, Carroll and Dubies
Site Project Manager, U.S. EPA, from Ms. Brenda B.
McDevitt, Environmental Scientist, Remediation
Technologies, Inc., and Ms. Barbara H. Jones,
Project Engineer, Remediation Technologies, Inc.,
re:  Addendum to Treatability Study Report,
November 8, 1994. .  (Attached report:  Addendum to:
Technology Evaluation Laboratory Treatability
Study. Carroll and Dubies Superfund Site. Final
Report (October 10. 1994.). November 8, 1994.

Report:  Cost Estimates for Modified Remedial
Alternatives. prepared for Mr. Robert J. Glasser,
Gould and Wilkie, and Ms. Debra L. Rothberg,
Periconi & Rothberg, P.C., prepared by Remediation
Technologies, Inc., October  13, 1994.

Report:  Technology Evaluation Laboratory
Treatability Study. Carroll  and Dubies Superfund
Site. Final Report, prepared for Mr. Robert J.
Glasser, Gould and Wilkie, and Ms. Debra L.
Rothberg, Periconi  & Rothberg, P.C., prepared by
Remediation Technologies, Inc., October 10, 1994.

-------
4.6  Correspondence

P.   400676 -  Letter to Mr. Doug Garbarini, Carroll- and Dubies
     400681    Site Contact, U.S. EPA, from Ms. Brenda B.
               McDevitt, Environmental Scientist, Remediation
               Technologies, Inc., and Mr. Kevin R. Jones,
               Associate, Remediation. Technologies, Inc., re:
               ARARs Summary, December 21, 1994.   (Attached:
               Table 2-1. Carroll and Dubies Site. Port Jervis,
               New York. Action~Specific ARARs, undated.)

P.   400682 -  Letter to Ms. Sharon Trocher, Carroll and Dubies
     400684    Site Project Manager, U.S. EPA, from Ms. Brenda B.
               McDevitt, Environmental Scientist, Remediation
               Technologies, Inc., re:  Cost Estimate for Off-
               Site Incineration  of Lagoon 7 Material, December
               9, 1994.   (Attached:   1. Table 2-1A. Carroll &
               Dubies Site. Port  Jervis. New York. Detailed Cost
               Estimate. Slurry Treatment for Lagoon 7 Soil.
               undated; 2. Table  2-*lB. Carroll & Dubies Site,
               Port Jervis. New York. Detailed Cost Estimate.
               Incineration for Lagoon 7 Soil, undated.).
10.0 PUBLIC PARTICIPATION

10.4 Public Meeting Transcripts

P.   1000060  - Transcript:   "Public Meeting for the  Carroll  and
     1000157    Dubies Superfund Site,  Port Jervis, New York,"
                transcribed by Rockland and Orange Reporting,
                transcribed on August 23,  1994.

10.9 Proposed Plan

P.   1000158  - Report:  Superfund Proposed Plan. Carroll and
     1000169    Dubies Sewage Disposal Inc.. Town of  Deerpark.
                Orange County. New York, prepared by  U.S. EPA -
                Region II, August 1994.

-------
        APPENDIX IV




STATE LETTER OF CONCURRENCE

-------
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION
50 Wolf Road. Albany. New York  12233
                                                                          Langdon Marsh
                                                                          Commissioner
                                                             JAN 30  1995
    Ms. Kathleen Callahan
    Director
    Emergency & Remedial Response Division
    U.S. Environmental Protection Agency
    Region II
    26 Federal Plaza
    New York, NY 10278
                          Re: Carroll & Dubies Site ID No. 336015
                               Record of Decision
    Dear Ms. Callahan:
          The New York State Department of Environmental Conservation (NYSDEC) has
    reviewed the Record of Decision (ROD) for Operable Unit 1 of the Carroll & Dubies site,
    which addresses the source areas (lagoons and surrounding impacted soil). Alternative
    number 5 as described in the ROD is NYSDEC's preferred alternative, which is also the
    USEPA's preferred option, NYSDEC concurs with the ROD as written.

          Please call Victor Cardona at (518) 457-3976 with any questions you may have.

                                         Sincerely,
                                         Ann Hill DeBarbieri
                                         Deputy Commissioner
                                         Office of Environmental Remediation

-------
      APPENDIX V




RESPONSIVENESS SUMMARY

-------
     RESPONSIVENESS  SUMMARY




CARROLL AND BUSIES SUPERFUND SITE  -

-------
                      RESPONSIVENESS  SUMMARY

           CARROLL AND DUBIES  SEWAGE  DISPOSAL  INC. .SITE
INTRODUCTION

A responsiveness summary, required by the National Contingency
Plan  (NCP) at 40 CFR §300.430  (f) (3) (F) ,  provides a summary of
public comments and concerns received during the public comment
period, and the United States Environmental Protection Agency's
(EPA's) and the New York State Department of Environmental
Conservation's  (NYSDEC's) responses to those comments and
concerns.  All comments summarized in this document have been
considered in EPA's and NYSDEC's  final decision for selection of
a remedial alternative for the Carroll and Dubies Sewage Disposal
Inc.  site  (the site).
SUMMARY OF COMMUNITY RELATIONS ACTIVITIES

The Remedial  Investigation and Feasibility Study  (RI/FS) reports
and the Proposed  Plan  for the site were made available for public
review on August  4, 1994.  The documents were placed in
information repositories located at the Deerpark  Town Hall,
Drawer A, Huguenot, New York and the EPA Document Control Center,
26 Federal Plaza,  Room 2900, New York, New York,  and the Proposed
Plan was mailed to all names on EPA's community relations mailing
list.  A public meeting was held at the Port Jervis High School
on August 23,  1994,. to discuss the results of the RI/FS, to
present EPA's preferred remedial alternative and  to provide  an
opportunity for the interested'parties to present oral comments
and questions to  EPA on the Proposed Plan for remediation of the
site.  A period for public review and comment on  these documents
was held from August 4, 1994 to September 2, 1994.

The notice of the public meeting and the availability of the
above-referenced  documents appeared in The Times  Herald Record on
August 15, 1994.

Attached to the Responsiveness  Summary are the  following
Appendices:

      o  Appendix  A -  Proposed  Plan,
                      Carroll and Dubies  Sewage  Disposal  Inc.
                      Town of Deerpark,
                      Orange  County, New  York

      o  Appendix B -  Public  Notice

      o  Appendix C -  August  23,  1994  Public  Meeting
                      Attendance Sheet

-------
SUMMARY OF COMMENTS AND RESPONSES

The following section is a summary of comments and .xjuestions
received from the public, with EPA's responses.   The comments
provided below are a summary of statements made at the public
meeting and written comments received during the public comment
period.  In several cases, the responses provided at the meeting
have been supplemented with additional information.

Comments Regarding the Nature and Extent of Contamination

1.   COMMENT:  A resident requested that the existing results of
     the groundwater sampling conducted at the site be
     summarized.  The resident was also interested in the
     location and depth of the monitoring wells, as well as any
     plans to install monitoring wells further downgradient of
     the existing monitoring wells.

     EPA RESPONSE:  It should be noted that the groundwater
     contamination will be addressed in operable unit II, as such
     the groundwater investigation is not yet complete.  A
     significant amount of data have already been generated from
     the on-going investigation.  During 1991 and 1993,
     groundwater samples  were collected from monitoring wells
     located within approximately 150 feet of the lagoons at the
     site and were analyzed for organic and inorganic compounds.
      (Refer to  Figure 3  contained in the Record of Decision  (ROD)
     for the location of  the monitoring wells.)  Results can best
     be described relative to lagoons 1 through 4 and 6 through
     8.   (Lagoon 5 is not considered here  since it contained
     tires and  not industrial wastes.)  Results indicated that
     organic compounds  (benzene, 1,2-dichloroethene,
     tetrachloroethene  and trichloroethene) were detected above
     drinking water standards  in the groundwater samples
     collected  from the monitoring  wells  located nearest to
     lagoons 1  through  4  (e.g., MW-4, QW-2, OW-3), but were
     detected at or near the  State, or. Federal  drinking water
     standards  in  the groundwater  samples collected  from the
     wells located furthest  from lagoons  1 through 4 (e.g., OW-5,
     OW-6, OW-7 and OW-8).   During the  1993 sampling event,
      inorganic  compounds were detected  at or  near the drinking
     water standards.   Based on the results of this  sampling,  the
     horizontal extent  of the groundwater contamination plume was
      determined to extend no farther than approximately 150 feet
      downgradient  of  lagoons 1 through 4.

      Benzene,  chromium, lead and nickel were  the primary
      contaminants  detected in the groundwater samples collected
      from monitoring wells located downgradient of  lagoons 6, 7
      and 8  (e.g.,  OW-9 through OW-13).   These contaminants were
      detected above drinking water standards.  Since contaminants
      were detected above the drinking water standards in the

-------
     furthest downgradient monitoring wells, it is evident  that a
     plume extends beyond the existing monitoring wells.  In
     August  and  September of 1994, additional monitoring wells
     were installed  (not shown  in Figure  3)  and groundwater
     samples were collected to  determine  the extent of the
     groundwater contamination  plume.  These monitoring wells
     extended as far as the downgradient  edge of the City of Port
     Jervis  landfill (approximately  1,000 feet from the site).
     Additional  monitoring wells will be  installed if the results
     of  the  recent sampling indicate that the site groundwater
     contamination plume extends beyond the  downgradient edge of
     the landfill.   A RI report which summaries the groundwater
     sampling data from the site is  expected to be completed in
     mid 1995, while a Proposed Plan which addresses the
     groundwater at  the site is expected  to  be completed shortly
     thereafter.

     The materials encountered  underlying the site consist  of
     glacially derived unconsolidated materials  (e.g.,  sand,
     gravel  and  clay)  underlain by  consolidated bedrock.  The
     glacially derived materials consist  of  two distinct units, a
     glacial till unit overlain by  glacial outwash deposits.  The
     monitoring  wells installed during  1991  and 1993 monitor the
     bedrock, the glacial  till, the glacial  outwash  or  both the
     glacial till and outwash units. The monitoring wells
     installed  in  1994 primarily monitor  the water table.   The
     deepest monitoring well  at the site  is  located  in  the
     bedrock and is  approximately  87 feet below ground  surface.

2.   COMMENT:   One  commenter  questioned whether EPA had
     overestimated the depth  to groundwater at  the  site (30 to  40
     feet).   The commenter has  installed  shallow  wells  at  less
     than 25 feet  on Route 209  in Hugenot.

     EPA RESPONSE:   The  depth to groundwater varies  significantly
     in the vicinity of  the site.   Along the southeastern
     boundary of the site,  the depth to groundwater from ground
     surface ranged from approximately 30 to 40 feet.   Whereas,
     approximately 1000  feet  from the site  (towards Gold Creek)
     the depth  to groundwater from ground surface ranged from 10
     to 20  feet.  The reduction in depth to groundwater is due to
     the proximity to the Creek.   The water table is located at a
     shallower  depth near the Creek since groundwater is
     discharging into it.

3.   COMMENT:   A resident asked whether  residential wells  in the
     area would be tested.

     EPA RESPONSE:  The New York State Department of Health
      (NYSDOH) has sampled a few private  wells near the site along
     Route  209.  NYSDOH did not detect contaminants above
     drinking water standards  in any of  the wells tested.  During

-------
     the August 23, 1994 public meeting,  NYSDOH indicated that
     they would sample residential wells located a reasonable
     distance from the site if so requested by the.property
     owners.
Comments Regarding the Evaluation of Remedial Alternatives and
the Preferred Alternative

4.  "COMMENT:  Commenter objected to burning contaminated soil at
     the site and "to any process that would release contaminants
     into the ambient air.   (One commenter agreed that, all
     things considered, Alternative 5 is the best alternative.)
     Commenters wanted to know where the contaminants that were
     "removed from the soil during the low-temperature thermal
     desorption  (LTTD) process ended up.  These commenters were
     concerned that the thermal inversions which frequently occur
     in the Neversink Valley would inhibit dispersion of the air
     emissions released during the remediation process, affecting'
     the nearby residents and school children.

     EPA RESPONSE:  In addition to the factors set forth in the
     Summary of Comparitive Analysis of Alternatives Section of
     the ROD, the significant public opposition to the use of any
     type of on-site thermal treatment unit has been taken into
     consideration in selecting the remedy.  As noted  in the ROD,
     the remedy has been modified from that proposed in the
     Proposed Plan  (see Public Acceptance and Documentation of
     Significant  Changes sections of the Decision Summary.)
     Nonetheless, in response to the question, it should be noted
     that the thermal desorption process described in  Alternative
     5 is not incineration,  since the destruction of organic
     contaminants is not the desired result.  Thermal  desorption
     is a process that uses  either an indirect or direct heat
     exchange to  heat organic contaminants to a temperature high
     enough  to volatilize and separate them  from the contaminated
     soil.   Air  or an  inert  gas is used as the transfer medium
     for the vaporized components.  Thermal  desorption systems
     are physical separation processes, that transfer
     contaminants from one phase to another, and are not designed
     to provide  high  levels  of organic destruction.  As the soil
     is heated,  the contaminants reach their respective boiling
     points, vaporize, and then become part  of the gas stream
     which  flows through the air pollution control equipment.

     In evaluating  the alternatives,  it was  anticipated that  any
     LTTD unit  utilized  at the  site would be capable of treating
     all  the soil and sludge contaminated with organic compounds
     in  less than one year.  Thermal  desorption  units  have
     extensive  air  pollution control  systems which would  comply
     -with all  State and Federal  air pollution control
     regulations.  Two diff-erent  types  of LTTD units,  an

-------
     anaerobic thermal processor (ATP)  and a typical  screw LTTD
     were considered.   Flue gases from the ATP are  extensively
     treated prior to  discharge.  Treatment is by ll)  cyclone and
     baghouse for particle removal,  (2)  wet scrubber  for removal
     of acid gases,  and (3)  carbon adsorption bed for removal of
     trace organic compounds.   The screw-type LTTD  unit uses
     condensation and carbon adsorption to treat flue gases.  The
     air pollution control equipment associated with  the LTTD can
     achieve greater than 99 percent removal efficiencies.  The
     purpose of the separation process is to obtain a
     significantly reduced volume of waste that can be treated
     on-site or sent off-site for treatment and/or disposal.  The
     spent carbon would be regenerated off-site.  Particulates
     that are collected in the baghouse and cyclone are recycled
     back to the LTTD unit or blended with the treated soil.

5.   COMMENT:  One commenter asked whether LTTD was the same
     process included in a 1991 proposal to burn contaminated
     soil in an area near the site.  The proposal was withdrawn
     since the residents were opposed to burning contaminated
     soil.

     EPA RESPONSE:  It is EPA's understanding from the discussion
     at the meeting, that the 1991 proposal included high
     temperature combustion i.e, incineration.  As noted above,
     the LTTD process is not an incineration process.

6.   COMMENT:  A resident asked whether the LTTD process would
     comply with provisions contained in the Town of Deerpark
     Zoning law which prohibit  the use of any equipment which
     involves the burning or incineration of garbage or solid
     waste.

     EPA RESPONSE:  EPA and NYSDEC believe  that the LTTD units
     would comply with the Town of Deerpark Zoning law since they
     are physical separation systems and are not designed  to
     incinerate or  decompose the organic contaminants.  Refer  to
     response #4  for  a further  discussion on the LTTD unit.

7.   COMMENT:  A  representative of Clean Earth  of New York,  Inc.
      (CENY)  stated  that it  currently operates a mobile thermal
     treatment unit and expects a permit  to operate  a  stationary
     thermal-treatment unit by  October  1994.  CENY presented the
     option  of treating the contaminated  materials off-site at
     its  stationary soil  remediation  facility instead  of  on-site
     as proposed  by EPA.

     EPA RESPONSE:  The off-site  treatment and  disposal  of the
     contaminated soil was evaluated.   It was determined that the
     on-site treatment  of the contaminated soils was protective
     of  human health  and  the  environment,  will  comply with
     applicable  or relevant and appropriate requirements (ARARs) ,

-------
    will  utilize permanent  solutions  and  alternative treatment
    technologies or resource  recovery technologies to the
    maximum extent practicable,  meets the statutory preference
    for treatment, and was  much less  expensive  than treating  and
    disposing of the materials off-site.   The selected remedy
    calls for on-site treatment of  the  source area materials
    utilizing ex-situ vapor extraction, bioslurry, and
    solidification/ stabilization;  on-site LTTD was removed from
    consideration as an option for  treatment of the source  area
    materials in the selected remedy.  However,  as noted in the
    contingency remedy, if  it is determined that the combination
    of ex-situ vapor extraction and bioslurry will not
    effectively treat the lagoon 7  materials, 'then the
    contingency remedy will need to be  implemented.  The
    contingency remedy would  require  that the lagoon 7 materials
    be sent off-site for treatment  (as  necessary) prior  to
    disposal in accordance  with Land  Disposal Requirements
     (LDRs) .  The contingency  remedy does  not specify the type of
    treatment to be used in treating  the  lagoon 7 materials
     (although incineration was utilized for developing a
    conservative cost estimate), so long  as LDRs are achieved.
    Therefore, if the contingency remedy  is implemented, it is
    possible that some or all of the  lagoon 7 materials  could be
    treated off-site via LTTD.

8.  COMMENT:  A commenter asked why Alternative 6 wasn't the
    preferred remedial alternative since  it is  permanent,
    provides the greatest protection, transports the
     contaminated  soil to a facility which specializes  in
     handling this kind of waste, and avoids on-site  containment
     of lagoon material at a site where the water table  is
     located not far- from the ground  surface.   The commenter also
     asked whether .cost is the deciding factor in selecting
     Alternative 5 as the preferred remedy over Alternative 6.

     EPA RESPONSE:   Each of the proposed remedial alternatives
     was assessed  utilizing the nine  evaluation criteria set
     forth in the  NCP.  The primary criteria that must  be
     satisfied by  any alternative are: 1)  overall protection of
     human health  and the environment and 2) compliance with
     ARARs.  The remaining seven criteria: 1)  long-term
     effectiveness and  permanence, 2)  reduction of toxicity,
     mobility or volume, 3) short-term effectiveness,  4)
     implementability,  5) cost,  6) State  acceptance,  and 7)
     community acceptance are  used to make comparisons and  to
     identify  the  major trade-offs between alternatives.  The
     cost  of the  alternative  is. considered only after it has  been
     determined  that the remedy would be  protective of human
     health and  the  environment and meet  ARARs.
                                 •6

-------
     Although Alternative 6 would provide the greatest protection
     to human health and the environment in the vicinity  of  the
     site,  Alternative 5 is considered to be fully-protective of
     human health and the environment.   The selected  remedy
     (Alternative 5) protects human health and the environment
     through the permanent removal of organic contaminants from
     soils containing levels of organic contaminants  in excess of
    ! the treatment standards set forth in the Decision Summary;
     the immobilization of the concentrated inorganic
     contaminants that fail the RCRA TCLP for inorganic
     constituents, and the placement of the source area materials
     into a lined and capped containment cell with a  leachate
     collection system.  Both of these alternatives satisfy  the
     primary criteria and are similar in their abilities  to
     satisfy the other criteria with the exception of cost.
     Therefore, cost was the deciding factor in  selecting
     Alternative 5 as the preferred alternative  over  Alternative
     6.

     The depth to groundwater at the site is deep enough  to  allow
     the installation of a lined containment cell above the  water
     table while maintaining a sufficient protection  zone.   The
     depth to groundwater from ground surface ranged  from
     approximately 30 to 40 feet along the southeastern boundary
     of the site.  Along the northwestern boundary of the site,
     the water table was not encountered before  bedrock was
     reached.

9.   COMMENT:  A resident questioned whether the long-term
     effectiveness of stabilization/solidification had been
     demonstrated for immobilizing organic and inorganic
     contaminants.
     EPA RESPONSE:  The long-term effectiveness of immobilizing
     'organic contaminants through stabilization/solidification
     has not been demonstrated.  However, stabilization/
     solidification is not being used to immobilize the organic
     contaminants.  The organic contaminants will be removed from
     the source area materials via ex-situ vapor extraction or in
     the case of lagoon 7 materials via a combination of ex-situ
     vapor extraction and bioslurry.  Stabilization/
     solidification will only be utilized to immobilize the
     inorganics.  The long-term effectiveness of stabilization/
     solidification has been demonstrated for immobilizing
     inorganic contaminants.

     It should be noted that the selected remedy contains
     redundancy in the treatment system to protect human health
     and the environment.  The mobility of organic contaminants
     from the more highly contaminated source areas will be
     reduced through treatment via ex-situ vapor extraction and
     bioslurry, and placement into a lined and capped containment

-------
     cell.   The mobility of inorganic contaminants  will  be
     reduced through stabilization/solidification and/or
     placement into a lined and capped containment-cell.
     Additionally,  the containment  cell will be sloped to a well
     where any leachate (if generated) from the source area
     materials will be collected.   A groundwater monitoring
     program will also be implemented to  monitor the groundwater
     (although it is unlikely that  any appreciable  amount of
     contamination could migrate to the groundwater from these
     materials).

10.  COMMENT:  A resident asked if  it wouldn't be cheaper in the
     long run to treat and dispose  of the waste off-site, since
     we may learn later that what appears to be a permanent
     solution for addressing the waste is not.  The resident
     indicated that the deposition  of the industrial waste  in the
     ground at the site was deemed  acceptable at the time of
     deposition; however, we are currently examining alternatives
     to remediate this same waste.

     EPA RESPONSE:  At the time of  the original disposal of this
     material, there were no safeguards  in place to ensure  that
     the materials did not leach.  Alternative 5 permanently
     removes organic contaminants from  source area materials
     through ex-situ vapor extraction and bioslurry, reduces the
     mobility of inorganic contaminants  through
     stabilization/solidification and further reduces the
     mobility of the organic and inorganic contaminants through
     placement of source area materials  in an on-site lined .
     containment cell with a cap and a  leachate collection
     system.  Both ex-situ vapor extraction and bioslurry,  and
     stabilization/solidification are proven technologies for
     removing organic contaminants and immobilizing inorganic
     contaminants, respectively.  A proven technology is a
     technology  for .which there is extensive experience available
     demonstrating its  effectiveness.  Additionally, further
     treatability studies will be conducted to ensure that these
     technologies will  effectively treat the on-site
     contaminants.   The on-site containment cell is also a proven
     technology for  reducing the migration of  contaminants, and
     it provides redundancy in the treatment  system for the
     protection of the  groundwater.  After  thoroughly evaluating
     the various alternatives  for  addressing  the contamination  at
     the  site,  EPA believes that Alternative  5 provides a
     technically sound solution  for treating  the waste.

     EPA  and DEC do  have particular concerns  regarding  the
     ability to effectively treat  the lagoon 7 materials.   As
     such,  a contingency remedy has been selected  in the event
     ex-situ vapor  extraction  and  bioslurry cannot effectively
     treat the complex mixture of  contaminants in  lagoon 7;  the
     contingency remedy requires that the materials be  sent off-

                                 8

-------
     site for treatment (as necessary)  to comply with LDRs prior
     to off-site disposal.

11.  COMMENT:  A resident asked why the slurry cut-off wall
     proposed in Alternative 3 was not included in Alternatives
     4 or 5.
             i

     EPA RESPONSE:  Under Alternative 3,  a cap and slurry cut-off
     wall would be utilized to minimize the migration of leachate
     from the untreated contaminated source area materials into
     the surrounding soils and groundwater.  The cap restricts
     the infiltration of rainwater through the impacted soils and
     sludges.  The slurry cut-off wall is a vertical wall
     constructed by filling excavated vertical trenches with low
     permeable material which minimizes the migration of leachate
     from the impacted soils and sludges into the surrounding
     soils and groundwater.  Alternatives 4 and 5 would curtail
     the migration of contaminants through treatment of the
     source area materials  (stabilization/solidification under
     Alternative 4 and ex-situ vapor extraction and bioslurry,
     and stabilization/solidification under Alternative 5) and
     through placement of the materials in an on-site lined
     containment cell with a cap and leachate collection system.
     Therefore, a slurry wall would not be heeded under
     Alternatives 4 or 5.

12.  COMMENT:  In reference to the preferred alternative, a
     resident requested  information regarding the location of the
     containment cell, whether the cap would be extended over all
     the lagoons, and whether the containment cell would leak.

     EPA RESPONSE:  It is anticipated that the source area
     materials will be consolidated to reduce the size of the cap
     and that the cap will be installed in the area of lagoons  1
     and 2.  The actual  location and size of the containment cell
     will  be. determined  during the design phase.

     If  leaks develop  in the  liner, it is unlikely that this
     would result in significant degradation of the groundwater.
     This  is because prior  to the  source area materials being
     placed into  the lined  cell, the more  contaminated source
     area  materials will be treated via one or more of the
     following  treatment processes: ex-situ vapor  extraction,
     bioslurry  and  solidification/stabilization.   In  addition,  a
     cap will be  installed over  the  lined  cell.  The  cap  will
     reduce the migration  of  untreated contaminants  in, the  cell
     to  the groundwater  by restricting the percolation of
      rainwater  through the  source  area materials.   The
      containment  cell  will  also be sloped  to  a well where any
      leachate,  if generated,  will  be  collected.   Finally,  a
      groundwater  monitoring program will be  implemented under the
      groundwater  operable  unit.

-------
13.  COMMENT:  One commenter felt that the most economical
     approach for implementing the preferred alternative would be
     to locate a single centrally located cell large enough to
     hold the 20,300 cubic yards of contaminated material.  The
     commenter believed that the cap should extend well past the
     containment cell and over all the lagoons as well.  The
     commenter would like the cap to be keyed into the bottom
     cliff bedrock to the northwest, so that no runoff penetrates
     underneath the lagoons or the containment cell.  The
     commenter believed this would minimize the future leaching
     of pollutants into the groundwater and could possibly reduce
     the amount of soil that would be subjected to the thermal
     desorption.  The commenter also believed that the minimum
     temperature used in the thermal desorption should be
     increased considerably; suggesting that the minimum of 200°F
     given in the proposed plan would be too low to boil off.all
     the water, and would not vaporize many oily organics.

     EPA RESPONSE:  EPA also believes that the best approach
     would be to consolidate the source area materials into a
     single containment cell and is pursuing this approach.  It
     is difficult to determine whether keying the cap into the
     bedrock would provide any additional benefits beyond those
     afforded from a typical cap design; this approach could
     present problems which would not be encountered with a
     standard design.  For instance, the presence of fractured
     bedrock would prevent a good seal and could create movement
     along the interface of the liner and the cap, resulting in
     runoff entering the containment cell.  Typical ways to
     prevent runoff from entering the containment cell is through
     joining the liner and the cap  (e.g., heat bonding) or by
     overlapping the cap over the liner.  Additionally, the
     drainage layer which is one of the  layers of the  cap and the
     drainage system  (e.g., trench  around the perimeter of the
     cap) diverts runoff away from  the containment cell.  The
     location, size and other design details of the containment
     cell will be determined during the  remedial design of the
     remedy.

     As noted above, the selected remedy does not incorporate
     LTTD.   In any  case, EPA agrees that if LTTD had been
     selected as the treatment process,  the temperature of the
     soils would have  to be heated  above 200°F to remove organic
     contaminants to attain the  cleanup  standards established  for
     the  site.  The 200°F was given as the bottom end of the
     range to which.soils  are heated  in  LTTD  units.   The  upper
     end  of  the range  provided  in the Proposed Plan was  1200°F.
                                10

-------
14.  COMMENT:  A resident questioned how bioslurry treatment
     would work and whether it is a proven technology.

     EPA RESPONSE:  In bioslurry .treatment,  the contaminated soil
     is" mixed with water to form a slurry which is fed to a
     bioreactor.   Air and nutrients are added to the bioreactor
     to promote aerobic microbial activity.   Certain
     microorganisms can digest organic substances that are
     hazardous to humans.  Microorganisms digest organic
     substances for nutrients and energy thereby breaking down
     hazardous substances into less toxic or nontoxic substances.
     Bioslurry treatment has been used successfully at other
     sites for the treatment of contaminated soil.  The success
     of bioremediation depends on the types and mixture of
     contaminants present, the type of soil and other soil
     conditions at the site.

15.  COMMENT:  One commenter questioned whether bioremediation is
     applicable to a  20 year old toxic site that contained
     everything from  batteries to cosmetic dyes and anti-
     perspirant chemicals.  The commenter pointed out that
     microbes are selective about what chemicals they degrade and
     bioremediation would be more appropriate for a site that has
     a single contaminant.  The commenter also raised the concern
     that the contaminants at the site may be too toxic for the
     microorganisms.

     EPA RESPONSE:  Although a single contaminant that readily
     biodegrades  would be preferable for bioremediation,
     bioremediation can  occur under conditions where there are
     multiple contaminants.  Microorganisms are selective about
     what chemicals they degrade.  However, there is usually more
     than one type of microorganism found in a given soil.  The
     growth  of  microorganisms can be stimulated to  accelerate
     bioremediation by adjusting soil conditions  such as
     temperature, pH, and oxygen and nutrient  content.
     Therefore,  bioremediation can work  at  an  old hazardous waste
     site that  contains  everything  from  batteries  (batteries were
     not detected in  the lagoons at the  site)  to  cosmetic  dyes
     and anti-perspirant chemicals.  However,  the soil would
     require pretreatment.   Pretreatment would include  removing
     large  objects,  such as batteries,  if  they were present.
     Additionally,  if the contamination level  is  too toxic for
     the microorganisms, pretreatment would also  be necessary -to
     reduce the toxicity of the  soil.   For instance,  if  the
      levels of  volatile  organic  contaminants were unfavorable for
      sustaining microorganisms,  air could be drawn through the
      soil  to vaporize and remove volatile organic contaminants
     present in the  soil to nontoxic levels prior to implementing
     bioremediation.   It is for this reason that ex-situ vapor
      extraction will be utilized to treat the lagoon 7 materials
      prior to their  treatment via bioslurry.

                                 11

-------
16.  COMMENT:  Two of the potentially responsible parties (PRPs)
     believe that vapor extraction and bioslurry treatment are
     alternatives to LTTD that will achieve the same  remedial
     objectives as LTTD and will satisfy the nine Comprehensive
     Environmental Response, Compensation and Liability Act
     (CERCLA) evaluation criteria as well as,  or better than,
     LTTD.  The'two PRPs submitted preliminary test results to
     demonstrate the capability of vapor extraction and bioslurry
     in reducing the concentration of organic contaminants in the
     soil.

     The two PRPs believe that vapor extraction and bioslurry
     technologies have been successfully demonstrated for actual
     site source area materials; whereas, the treatability study
     for LTTD encountered both treatment and implementation
     problems.  The problems encountered included:  1) the sludge
     matrix did not reach the target treatment temperature due to
     the high moisture content in the sludge and 2)  the thermally
     treated sludge could not be solidified due to  the
     characteristics of the material.  The two PRPs  believe that
     selection of LTTD is not supportable given the  existing
     treatability information on the site source area materials.

     The two PRPs also indicated that additional support for the
     selection of soil vaporization and bioslurry technologies in
     lieu of LTTD is provided by .USEPA guidance.  Vapor
     .extraction  is one of the presumptive remedies for the        .
     treatment of organics  in soils  (USEPA, 1993;  OSWER Directive
     9355.048FS).  In addition, bioslurry represents one of  the
     proven  treatment technologies for organic impacted soils
     that are subject to  land disposal restrictions  (Federal
     Register. Vol.  58, No. 176).

     EPA RESPONSE:   Although additional  treatability studies are
     warranted  to demonstrate the  effectiveness of each of the
     Alternative 5 treatment options, EPA believes that each of
     the  options could effectively treat all but the lagoon  7
     materials.

     A combination of physical  and chemical  factors  make  the
     lagoon 7 materials  highly  problematic  to  treat: the
     materials  have  a high  clay and  moisture content,  and
     significant concentrations of both  volatile and semivolatile
     organic compounds.   As a result,  none  of  the Alternative  5
     processes,  in  and  of themselves,  appear to be particularly
     well suited for implementation  at the  site.   While it  is
     believed that  lagoon 7 materials that  are processed through
     the  LTTD could be  treated  to remedial  action objectives,  EPA
     agrees that treatability studies have indicated that
     commonly used LTTD units could experience significant
     materials handling problems while processing the  lagoon 7
     materials; prior to implementing LTTD,  additional

                                 12

-------
     treatability studies would be required to assure  that  such
     material handling problems could be addressed/minimized
     e.g.,  via blending the material with additives, or
     utilization of an LTTD unit better designed to handle  such
     problems.  Ex-situ vapor extraction is likely to  be
     effective in handling the volatile fraction of contaminants
     in the lagoon 7 materials, however, it would not  likely be
     effective at treating the semi-volatile fraction.
     Bioslurry, on the other hand, would be expected to be
     effective in handling the semivolatile fraction of the
     lagoon 7 materials.  Therefore, it appears as though use of
     ex-situ vapor extraction for treatment of volatiles, and
     subsequent treatment of semivolatiles with bioslurry,  would
     be the most implementable combination of treatment options
     under Alternative 5; this combination would avoid the
     material handling problems which would be expected to  be
     encountered with LTTD.  Based upon this assessment, and the
     significant public comment opposed to the use of  any type of
     on-site thermal treatment unit, the bioslurry and ex-situ
     vapor extraction options of Alternative 5 were specified as
     the treatment options to be implemented iri the selected
     remedy; the LTTD option was specifically excluded from the
     selected remedy.


Comments Regarding Site Risks

17.  COMMENT:  A resident asked for a summary of the results of
     the risk assessment conducted at the  site.

     EPA RESPONSE:  A baseline risk assessment was conducted
     using the soil data associated with lagoons 1 through 4.
     Baseline  risk assessments estimate the human health risk
     which could result  from  the  contamination at the site, if no
     remedial  action were taken.  The baseline risk assessment
     addressed the potential  risk to human health by  identifying
     potential exposure  pathways  by which  the public might be
     exposed to contaminant releases at the site under  current
     and future land-use conditions.  The  exposure pathways
     evaluated under the current  land-use  conditions  included
     exposure to trespassers  through  ingestion,  inhalation  and
     dermal  contact of  soils  and  sludges.  When  considering
     future  land use,  the  exposure  pathways  included  the
     ingestion, inhalation and dermal  contact  of  soils  and
     sludges by hypothetical  construction  workers.  Because the  ••
     site  is surrounded by a  cliff, 'a landfill  and a  quarry,
     future  residential use of the  property was  not considered as
     a reasonable  scenario.
                                 13

-------
     The  results of the baseline risk assessment indicated that
     the  soils and sludges  associated with lagoons 1 through 4
     pose an unacceptable noncarcinogenic risk for .hypothetical
     construction workers at  the site.  The primary contributor
     to the unacceptable noncarcinogenic risk is chromium-
     containing dust which  could be inhaled during excavation
     activities.  The risk  assessment indicated that there are no
     unacceptable noncarcinogenic risk to trespassers; nor were
     there any unacceptable carcinogenic risks under .any of the
     scenarios evaluated.

     The  risk assessment was  prepared before the analytical data
     associated with lagoons  6  through 8 were available.
     Therefore, only the data collected from lagoons 1 through 4
     during July and September  1991 were used in the risk
     assessment.  A separate  risk assessment was not prepared for
     lagoons 6 through 8 since  it was anticipated that remedial
     action would be taken  at these lagoons due to the levels of
     contaminants found, the  presence of hazardous waste and
     cross media impacts to groundwater.  Higher baseline risk
   •  levels would be expected if the analytical soil data from
     lagoons 6, 7 and 8 were  included in the risk assessment.  A
     risk assessment to identify the potential risk to human
     health through groundwater pathways will be prepared as part
     of the RI  for the groundwater; it is anticipated that  the RI
     will be released to the  public, in the  summer of 1995.

18.  COMMENT:  A Town official  asked whether the recreational  use
     of the towpath which forms the southeast border of  the site
     would result in exposure to  site contaminants.  He  indicated
     that the towpath has been designated  to become a multiple
     use pathway across the County.

     EPA RESPONSE:  The results of  the baseline  risk  assessment
     indicated  that there are no unacceptable  carcinogenic  or
     noncarcinogenic risk to trespassers.   The  remedial
     alternative that was selected for  the site  eliminates  the
     pathway  for exposure to site contaminants  by trespassers
     through  the treatment of the contaminated source area
     materials  and  the placement of the  source area materials
     into an  on-site lined containment  cell with a cap.

19.  COMMENT:   A resident asked whether it is better to leave the
     contaminants  in the soil to migrate to the groundwater or  to
     release  the contaminants into the ambient air.   The resident
     indicated that he drinks six glasses of water a day while  he
     breathes twenty or thirty times a minute.

     EPA RESPONSE:  Neither  is preferable.  The selected
     alternative will  reduce the toxicity, mobility and volume  of
     contaminants  in the soil via treatment.  As an added measure
     of-1 safety, the source -area materials will be placed in a

                                14

-------
     lined cell to minimize the potential  for the remaining low
     level contamination to migrate into the  groundwater.
    .Measures will be taken during the  implementation of the
     remedy, to ensure that releases of contaminants into the air
     are insignificant.  EPA believes that implementation of the
     selected remedy will be fully protective of human health and
     the environment over the short and long-term.

20.  COMMENT:  A resident asked if excavation of the soil under
     the preferred alternative would continue down to the bedrock
     and if not, whether contaminated soil would be left at the
     site.

     EPA RESPONSE:  All lagoon materials are  to be excavated for
     treatment and/or placement into an on-site containment cell.
     The NYSDEC TAGM soil cleanup levels for  organic compounds
     were utilized to derive excavation levels which will be used
     to determine the volume of soils impacted by the lagoon
     materials, that also require excavation  for treatment and/or
     containment.  The TAGM soil cleanup levels are objectives
     which were established by NYSDEC and are conservatively set
     at concentrations that are protective of human health and
     groundwater quality.  Therefore, contaminants of concern
      (COCs) were selected for comparison to the NYSDEC TAGM
     levels based on: their mobility (propensity to migrate from
     the soil to the groundwater); their frequency of detection
     in the soil and in the groundwater, and their concentration
     level.  The organic indicator COCs and their excavation
     levels are as follows:
                             Table 1
            Excavation  Criteria for Organic Compounds

      Indicator  COCs                        Excavation. Level  (ppm)

      Benzene                            0.06
      1,2-Dichlorobenzene                7.9
      1,4-Dichlorobenzene                6.0
      Di-n-butylphthalate                8.1
      Naphthalene                      13.0
      Tetrachloroethene                  1.4
      Toluene                            1.5
      Trichloroethene                   1.0

      The excavation criteria for  the  inorganic  contaminants  was
      determined utilizing the  highest levels  of indicator
      contaminants (chromium and nickel) detected in the
      background soil samples collected from the site.   The
      highest  levels of  chromium and nickel detected in background
      samples  were 61.9  parts per  million  (ppm)  and 36.7 ppm,
      respectively. -Soil  that  has contaminants  above the levels

                                15

-------
     listed in Table 1 or levels above the highest background
     level for chromium and nickel will require excavation.
     Therefore, only soils below the excavation criteria will
     remain on-site without being treated or placed into an on-
     site containment cell.  EPA and NYSDEC believe that these
     excavation criteria will be fully protective of human health
     and the environment.
Comments Regarding Funding of Remedial Alternatives.
Timeframes for Implementing the Site Cleanup and Enforcement

21.  COMMENT:  A resident wanted to know the potentially
     responsible parties (PRPs) for the site and which of the
     PRPs had funded the remedial investigation to date.  (Note:
     PRPs are companies or individuals who are potentially liable
     under CERCLA for the costs of responding to the release and
     threat of release of hazardous substances at and from a
     site)The resident also wanted to know the extent of
     participation by the City of Port Jervis in the
     investigation of the site.

     EPA RESPONSE:  The five PRPs for the site are:  1) Carroll
     and Dubies Sewage Disposal, Inc., 2) Kolmar Laboratories,
     Inc., 3) Wickhen Products, Inc., 4) Reynolds Metals Company,
     and 5) the City of Port Jervis.  In September 1989, all the
     PRPs, with the exception of the City of Port Jervis were
     provided an opportunity to.fund and/or perform the RI/PS for
     the site.  The City of Port Jervis was not offered an
     opportunity to participate in the RI/FS since it was not
     determined that it was one of the owners of the site
     property until February 1993, well after the RI/FS was
     underway.  To date, the extent.of participation in the RI/FS
     by the City of Port Jervis has been limited to its granting
   ,  access and use of its property to  install monitoring wells
     for groundwater sampling.

     Of the four remaining PRPs, only Kolmar Laboratories,  Inc.
     and Wickhen Products, Inc. have  funded and performed the
     RI/FS for the site pursuant to Administrative Order on
     Consent, Index #11 CERCLA 00202.   All the PRPs will be  .
     offered the opportunity to fund  and/or perform the cleanup
     of the  contaminated  soils at  the  site.

 22.  COMMENT:  A resident  questioned  who would pay for the
     remedial investigation  and the  remediation of the site and
     whether taxes would  go  up in  the area  to pay for  the cleanup
     of the  site.

     EPA  RESPONSE:   First, EPA looks  for PRPs  to  fund  the RI/FS
     and  the remediation of  the site.   If  the  PRPs are not
     willing to pay  for the  RI/FS  or the cleanup  of the site,

                                16

-------
    then EPA can order them to perform the response action, or
    EPA can use Superfund monies to perform the work.  When the
    Agency uses its money for a response action at a site where
    there are financially viable PRPs, it is authorized to take
    an enforcement action against those PRPs to recover its
    costs.  EPA can ultimately recover these costs through
    administrative settlements, judicial settlements or
    litigation.  The Superfund monies are primarily generated
    from taxes on petroleum and chemical industries; a small
    portion of the monies are contributed from general tax
    revenues.  Therefore, local taxes would not increase to fund
    this remediation.

    During the RI, EPA learned from the City of Port Jervis that
    it owns a major portion of the site property where the
    lagoons are located.  As owner.of the majority of the site
    property, the City of Port Jervis is one of. the five PRPs
    that is responsible  for the cost of the cleanup of .the site.
    The City of Port Jervis was not offered an  opportunity to
    fund or to conduct the RI/FS at the site since, it was not
    determined that it was a PRP until after the RI/FS was
    underway.  The City  of Port Jervis will be  offered an
    opportunity,  along with the other four  PRPs, to participate
    in the clean  up of the site.  This participation can include
    funding and/or providing services to assist in the cleanup
    of the site.  For qualifying municipalities, the State has a
    program to cover  75  percent of  the municipality's  share  of
    the cost to cleanup  a  site.  Since the  City's participation
    in the cleanup, and  subsequent  sources  of  revenues  for
    participation are unclear,  it  is  impossible for  EPA  to know
    if taxes in the area would be  increased to pay  for the
    cleanup of the  site.

23. COMMENT:   Two PRPs  jointly provided  the following, comment:
    to date, only two (Kolmar  Laboratories,  Inc.  and Wickhen
     Products,  Inc.)  of  the five PRPs  for the site  have
     cooperated with the  EPA and have  expended substantial  sums
     in  the  investigation of  the site.   The EPA has  the authority
    under CERCLA to compel PRPs to participate in remediation of
     hazardous  substance  disposal sites.   Although the Agency has
     long represented to the cooperating PRPs that it intends to
     exercise  its CERCLA authority against non-participating PRPs"
     and affirmed its intentions again at the August 23,  1994
     Public Meeting,  no action to involve these additional
     parties,  other than notice letters,  has been taken by EPA.
     Both fairness and economic reality mandate that the EPA
     exercise its CERCLA authority and compel other PRPs to
     contribute to the costs of addressing the site.   Following
     issuance of the ROD, the EPA has indicated that it will
     afford the PRPs the "opportunity" to conduct the remedial
     design and remedial action.  In the event that other PRPs
     again fail to avail themselves of the-opportunity, the EPA

                                17

-------
     should exercise its CERCLA authority and compel
     participation of all PRPs.

     EPA RESPONSE:  EPA's policy is  to  seek the  participation of
     all PRPs in addressing sites.   CERCLA  authorizes  EPA to
     negotiate with and enter into settlements with PRPs  to
     perform and/or fund the work to be performed at a site,  as
     well as order PRPs to perform the  work if negotiations fail
     and a settlement cannot be reached.  EPA will also,  when
     circumstances warrant, issue Administrative Orders requiring
     those PRPs that have failed to  reach a settlement, to
     coQperate and coordinate with the  PRPs that have  settled
     with EPA.  EPA cannot, at this  time, state  definitively
     whether such orders will be necessary  in this matter.
     However, it is EPA's intent to  involve all  PRPs in a
     settlement for the implementation  of the remedial design and
     remedial action for the site.

24.  COMMENT:  A commenter expressed that until  more definitive
     property lines are established, it is  uncertain as to who is
     responsible for what and a decision of .any  sort would be
     inappropriate.

     EPA RESPONSE:  The owners of the property on which.the
     lagoons are located have been determined.  In February, 1993
     the City of Port Jervis provided EPA with a survey map that
     shows property boundary lines in the area of the  site.  The-
     City of Port  Jervis owns the property encompassing lagoons
     1, 3, 4, 5, 6, 7 and  8 and part of lagoon 2.  The Carroll
     and Dubies Sewage  Disposal, Inc. owns the remaining  portion
     of the  site property  (i.e., that property on which the
     remaining portion  of  lagoon 2 is located).

25.  COMMENT:  A  commenter questioned how long it would take to
     begin remediating  the soils at the site and to complete the
     remediation.  The  commenter also questioned whether
     attempting to have the PRPs clean up the site would  hold up
     the remediation of the site.

     EPA RESPONSE:  After  the ROD is signed, EPA will send out
     notice  letters  to  the PRPs providing them with an
     opportunity  to  implement  the selected  remedy under EPA
     supervision  or  to  fund the remediation.  From the time
     notice  letters  are delivered to the PRPs it usually  takes
     approximately four to six months  to initiate and complete
     negotiations with PRPs.   If the PRPs  decide not  to  fund the
     cleanup of  the  site,  EPA can either order  them to do it or
     pay for the  cleanup itself  and later  seek  to  recover the
     cost  from the PRPs.  In either case,  the design  of  the
     fcemedy would be initiated shortly after the  conclusion of
     negotiations.  The period from signing the ROD to completing
     the remedial design is about 2 years  (or longer  if

                                18

-------
     treatability studies are required)  regardless of who
     performs the cleanup of the site.  It is anticipated that it
     would take another year to complete the cleanup of.the site
     utilizing ex-situ vapor extraction, bioslurry,  and
     solidification/stabilization.

26.  COMMENT:  One commenter stated that the portion of the City
     of Port Jervis property which, in essence,  constitutes the
     Carroll and Dubies site, is just a small contributor to the
     overall contamination in the area caused by the City of Port
     Jervis Landfill.  The commenter believed that everyone who
     disposed of waste in the landfill is responsible for
     contamination in the area of the site and not just Joe
     Carroll and Gustave Dubies.  The commenter indicated that
     the cost to clean up the landfill will be much greater than
     the cost to clean up the Carroll -and Dubies site.

     EPA RESPONSE:  This ROD addresses only the Carroll and
     Dubies site.  The landfill is not being considered as part
     of the site, and therefore, is not being investigated at
     this time.  However, given the close proximity of the site
     to the landfill, monitoring wells which were installed to
     delineate the groundwater plume migrating from the site are
     located downgradient of both the site and the landfill.  The
     groundwater sampling results from these wells will provide
     information on the levels and types of contaminants detected
     in the groundwater .downgradient of the site and at the
     landfill.  These monitoring wells were recently installed
     and were sampled in September 1994.  The groundwater
     sampling results and alternatives proposed to address the
     groundwater at the site will be presented in a Proposed Plan
     which is expected to be completed by the fall of  1995.

     It should be .noted that landfills  are subject to  New York
     State regulations for  the management of solid waste
     facilities  (Part 360 of the  New  York. Code of Rules and
     Regulations).  These regulations include landfill closure
     requirements which include installing a landfill  cap.  To
     date, the City of Port Jervis has  not installed a landfill
     cap.  Since the  landfill  is  not  part of the  investigation
     conducted to date, there  are no  costs available for
     remediating the  landfill.  Typically, landfills are
     addressed by installing a multi-layered cap  over  the
     landfill to prevent  the percolation  of  rainwater  through the
     landfill waste,  thereby reducing the migration  of
     contaminants from the  landfill  to  the groundwater.   Given
     the  size of  landfills,  it is not practical to  excavate  and
     treat  the  landfill  waste.   It is probable  that  the  proper
     closure of  the  landfill would be a multi-million dollar
     effort.   See response  to  comment 31  for further discussion
     regarding  closure of the  landfill.


                                19

-------
     EPA does not generally consider private parties  who deposit
     municipal solid waste (MSW)  in landfills to be PRPs if they
     only deposited household hazardous  substances-  However,
     such parties may be considered PRPs if  the MSW contains
     hazardous substances from non-household sources.   These
     sources include, but are not limited to, wastes  from
     commercial or industrial processes  or activities,  or used
     oil or spent solvents from private  or municipally-owned
     maintenance shops.

27.  COMMENT:  A commenter expressed concern that it  had been
     twelve years since the first sampling was conducted at the
     site, and wanted to know how long it would be before the
     groundwater was addressed and why the groundwater wasn't
     being addressed along with the contaminated soil.

     EPA RESPONSE:  NYSDEC first conducted sampling at the site
     in 1982 to assess the site for inclusion on the  National
     Priorties List  (NPL) .  This sampling was very limited and
     consisted of the collection of only one sludge sample and
     one-groundwater sample.  The resulting  sampling data was not
     considered adequate to evaluate  the site.  More in-depth
     sampling was conducted by NYSDEC  in 1986.  Based on the 1986
     sampling results, the site was proposed for inclusion on the
     NPL in June 1988 and placed on the NPL in February 1990.
     After the site was listed on the  NPL,. the RI/FS for the site
     was conducted by the PRPs under  EPA's supervision.  The.
     RI/FS was completed  in 1994 with the issuance of this ROD
     which presents the selected remedy for addressing the
     contaminated soils at the site.   Although it  has been 12
     years since the first sample was  collected from the site,  it
     has taken EPA four years from the time  the site was listed
     on the NPL to investigate and select a  remedy for the site.
     EPA, however, acknowledges that  the remediation at Super fund
     sites is a lengthy program and is taking measures to
     streamline the process.

     In July  1992, it was determined that it would take longer  to
     collect  additional data  to complete the delineation of the
     groundwater contamination plume than to finish delineating
     the  contaminated  source  areas.   Therefore,  instead of
     delaying the selection of a remedy for the  remediation of
     the  soils  and sludges, EPA divided the site  into  two
     distinctive components or operable units  (i.e.,
     soils/sludges and groundwater) .   Following  completion of  the
     additional groundwater  investigation,  a ROD formalizing  the
     selection  of a  remedy  to address the groundwater  will be
     completed  (late 1995) .   The period from signing the  ROD  to
     completing the  design  for  the groundwater remedy would be
     about  2-3  years . (refer to  response #25) .   How long it takes
     to  clean up  the groundwater is extremely variable and
     depends on a number of factors such as the extent of

                                20.

-------
     contamination, type of contaminants,  and the geology of the
     site.  At sites where dense non-aqueous phase liquids
     (DNAPL) are present, it may not be practicable to clean the
     groundwater to drinking water standards, as timeframes to
     achieve such levels can be on the order of centuries.  Other
     sites are much better suited for treatment, and may require
     a much shorter cleanup timeframes (on the order of years) .
     The estimated timeframe for remediating the Carroll & Dubies
     site groundwater  (if necessary) will be estimated in the FS
     and Proposed Plan for the groundwater operable unit II.


Miscellaneous Comments

28.  COMMENT:  Joe Carroll, one of the owners of Carroll & Dubies
     Sewage Disposal Facility Inc., requested that the site name
     be changed to one that does not refer to Carroll and Dubies,
     since the City of Port Jervis owns the property where the
     Carroll and Dubies  facility is located.  In addition, he
     claimed that the  City of Port Jervis created the first
     lagoon  (lagoon 8) at the Carroll and Dubies site to use  to
     deposit sewage sludge.  Mr. Carroll and Gustave Dubies used
     this lagoon to deposit waste along with other companies.
     Thereafter, Mr. Carroll and Mr. Dubies started depositing
     waste on adjoining  City of Port Jervis land, which at the
     time they believed  they owned.

     EPA RESPONSE:  When the site was initially listed on the
     NPL, it was only  believed to. consist of lagoons 1 through 4;
     it was also believed that the  site was owned and operated by
     Carroll and Dubies  Sewage Disposal Facility Inc.  The site
     was  listed on the NPL as the Carroll and Dubies Superfund
     site in February  1990.  In 1992, the site  was expanded  to
     include three additional lagoons .(lagoon 6 through 8) which
     were identified in  historical  aerial photographs.  Shortly
     thereafter  (February  1993), it was.determined that the  City
     of Port Jervis owned  a major portion of the property, where
     all  the lagoons are located.   Carroll  and  Dubies Sewage
     Disposal Facility Inc. owned only a small  portion of the
     site property.  Although the property  owners are different
     than originally believed,  Carroll and'Dubies Sewage  Disposal
     Facility  Inc. was the  operator of, and transporter of  all
     the  waste  in  lagoons  1 through 4 and to EPA's knowledge, the
     operation  and the transporter  of all the waste  present  in
     lagoons  6  through 8.   As  such, EPA believes  that  the name  of
     the  site  is  appropriate and has  no reason  to  change  that
     designation.
                                21

-------
29.  COMMENT:  Joe Carroll suggested that his remaining property,
     approximately thirty-two acres,  should not be eliminated
     from any further use such as building a small.summer home,
     as this property was not used for disposal.  The commenter
     believed that<"No Action" should be selected for the thirty-
     two acres of land owned by Joseph Carroll and Gustave
     Dubies.

     EPA RESPONSE:  EPA is considering remedial alternatives to
     address only the seven lagoons at the site.  EPA is not
     restricting,any use of property owned by Joseph Carroll and
     Gustave Dubies, so long as the use of this property does not
     interfere with any remedial action that may be taken to
     remediate the groundwater, lagoons or impacted soils at the
     site.

30.  COMMENT:  A resident wanted to know what was being done to
     prevent future Superfund sites.

     EPA RESPONSE:  CERCLA was enacted in December 1980 to
     provide EPA with a powerful means of responding to cases.of
     environmental contamination.  The CERCLA remedial program is
     generally retroactive in nature, addressing previously-
     contaminated  sites.  On the other hand, the Resource
     Conservation  and Recovery Act  ("RCRA"), enacted in 1976,
      (implementing regulations effective November  1980) regulates
     hazardous waste from.cradle  (generation) to grave
      (disposal/treatment) thereby minimizing the potential  for
     Superfund sites in the future.  RCRA regulations also
     require owners and operators of RCRA regulated facilities to
     maintain financial assurance in amounts sufficient to  cover
     the  cost of  "closing" the facility and-thus avoiding the
     need.for a  CERCLA clean up.

31.  COMMENT:  A resident indicated that we have studied only a
     small  area  of Deerpark and  that there exist a number of
     other  areas  that should not be ignored.  The  resident
     identified  a number  of areas along Route 209  that  are
     potentially adversely impacting human health  and  the
     environment.

     Another commenter was concerned about the  hundreds of  pounds
     of lead shot and bullets  on the site  associated with the
      shooting ranges as  well  as  the informal  ones  at the site.
     The commenter also  identified  the continuing  Carroll and
      Dubies operation,  lagoons located to  the North  of the  site  a
      few hundred feet,  dozens of freon leaking  refrigerators
      located to  the south of  the site,  and the  landfill which has
      never been  capped as other pollution problems in  and around
      the site.
                                22

-------
EPA RESPONSE:  CERCLA authorized EPA to identify hazardous
waste sites that threaten public health and the environment,
and to locate and properly dispose of the wastes found
therein.  The first step of that identification process is
called the Preliminary Assessment (PA).  In a PA, EPA
attempts to verify the existence of released hazardous waste
at a site that may fall under Superfund.  Any person or
organization can petition EPA to conduct a PA at a site;
this is called a PA petition.  After receiving a PA
petition, EPA will decide if there is reason to believe that
an actual/potential site exists, and whether EPA has the
•legal authority under Superfund to respond to the site. If
the petition is approved, EPA will conduct a PA and provide
a copy of the PA to the petitioner.  Based upon the results
of the PA, EPA will determine if the next step, a site
investigation (SI), needs to be conducted.  Following the
SI, EPA would prepare a hazard ranking system score for the
site to determine its eligibility for inclusion on the NPL.

The site has not been used for the disposal of septic and
municipal sewage wastes since 1989.  The referenced lagoons
are actually lagoons 1 and 2.  They are the only lagoons at
the site which were not covered with soil.  These lagoons
are no longer actively used and will be addressed as part of
the remedy being selected for this site.

It is true that the Port Jervis Landfill has not yet been
properly capped.  The landfill will be closed  (including
capping) as required by the New York Code of Rules and
Regulations  (6 NYCRR Part 360) requirements for Solid Waste
Management Facilities.  The NYSDEC has not yet developed a
schedule for the closure of the landfill.  However, NYSDEC
has requested that any questions regarding the closure of
the landfill be directed to:

                     Mr. Victor Cardona
                     Federal Projects Section
                     Bureau of Eastern Remedial Action
                     Division of Hazardous Waste Remediation
                     New York State Department of
                       Environmental  Conservation
                     50 Wolf Road
                     Albany, New York,  12233-7010
                     Telephone  #  (518)  457-3976

Problems related to discarded refrigerators, and other
pollution problems encountered  around the  site are best
referred to  local authorities such as the  City of Port
Jervis, or Orange County.   If necessary, the City or  County
would elevate these  issues  to NYSDEC.   If  NYSDEC determined
that  the problem  is best addressed by EPA, NYSDEC could  then
refer the problem to EPA.

                           23

-------
           APPENDIX A

         .Proposed Plan
Carroll and Dubies Superfund Site

-------
 Superfund Proposed Plan

                   Carroll and Dubies  Sewage Disposal  Inc.
                                              Town of Deerpark
                                          Orange County, New York
 EPA Region 2
"August 1994
NYSDEC
 PURPOSE OF PROPOSED PLAN

 This Proposed Plan describes the remedial
 alternatives considered for the Carroll and Dubies
 Sewage Disposal (C&D> Superfund site (the site)
 and identifies the preferred remedial alternative for
 the soils with the rationale for this preference. The
 Proposed Plan was developed by the U.S.
 Environmental Protection Agency (EPA), as lead
 agency, with support from the New York State
 Department of Environmental Conservation
 (NYSDEC). EPA is issuing the Proposed Plan as
 part of its public participation responsibilities under
 Section 117(a) of the Comprehensive
 Environmental Response, Compensation, and
 Liability Act (CERCLA) of 1980, 42 U.S.C. §§ 9601-
 9675, and the National Contingency Plan (NCP), 40
 C.F.R. § 300.430(f). The alternatives summarized
 here are described in the Remedial Investigation
 and Feasibility Study (RI/FS) reports which should.
 be consulted for a more detailed description of all
 the alternatives. As part of the Administrative
 Record for the site, the RI/FS can be found'in the*
 public repositories listed on page 2.   ' •
                                            s

 This Proposed Plan is being provided as a
 supplement to the RI/FS reports to inform the
 public of EPA's and NYSDEC's preferred remedy
 and to solicit public comments pertaining to all the
 remedial alternatives evaluated, as well as the
 preferred  alternative.

 The remedy described in this Proposed Plan  is the
 preferred  remedy for the site. Changes to the
' preferred  remedy or a change from the preferred
 remedy to another remedy may be made, if public
 comments or additional data indicate that such a
 change will result in a more appropriate remediaT
 action.  The final decision regarding the selected
 .remedy will be made after EPA has taken into
 consideration all public comments.  We are
 soliciting  public comment on all of the ai'ematives
 considered in the detailed analysis of the RI/FS
          because EPA and NYSDEC may select a remedy
          other than the preferred remedy.

          COMMUNITY ROLE IN SELECTION PROCESS

          EPA and NYSDEC rely on public input to ensure
          that the concerns of the community are considered
          in selecting an effective remedy for each Superfund
          site.  To this end, the RI/FS reports. Proposed
          Plan, and supporting documentation have been
          made available to the public for a public comment
          period which begins on August 4, 1994 and
          concludes on September 2,1994.

          A public meeting will be held during the public
          comment period at the auditorium of the Port
          Jervis High School, Route 209, Port Jervis, New
          York on Tuesday, August 23,1994 at 7:00 p.m. to
          present the conclusions of the RI/FS, to elaborate
          further, on the reasons for recommending the
          preferred remedial alternative, and to receive public
          comments.

          Comments received at the public meeting, as well
          as written comments, will be documented jn the
          Responsiveness Summary Section of the Record of
          Decision (ROD), the document which formalizes
          the selection of the remedy.
                   MARK YOUR CALENDAR

              August 4,1994 to September 2.1994
              Public comment period on Rl report.
              Proposed Plan, and remedy considered.

              Tuesday, August 23, "1994
              Public meeting to be held at 7:00 p.m. in
              the auditorium of the Port Jervis High
              School, Route 209, Port Jervis. New York.

-------
 ^Vt^;
   Landfill
                                                                            mi M HDMOOC
                                     Figure 1 - C&D She Map
   Copies of the RI/FS reports, Proposed Plan
   and supporting documentation are available
   at the following locations:  ;   •••    ;  ;'• w

   Town Hall                       ; :;
   Drawer A
   Huguenot, New York  12746
   Tel. (914) 856-2210
   Hours: 8:00 a.m. - 4:00 p.m. (Mon. - Fri.)

   EPA Document Control Center
   26 Federal Plaza, Room 2900      / .
   New York, New York  10278    "
   Tel. (212)264-8770
   Hours: 9:00 a.m. - 5:00 p.m. (Mon. - Fri.)
All written comments should be addressed to:

Sharon L Trocher
Project Manager
U.S. Environmental'Protection Agency
26 Federal Plaza, Room 29-100
New York, New York 10278
(212)264-8476
SITE BACKGROUND

The site is located just northeast of the City of Port
Jervis on Canal Street In the Town of Deerpark,
Orange County, New York, and is approximately
3.0 acres in size.  The northwest boundary of the
site is formed by the valley wall, which consists of
exposed bedrock with talus comprising the base.
The southeast boundary and a portion of the
northeast boundary of the site is formed by
remnants of the former Delaware and  Hudson
(D&H) Canal and towpath.  The remainder of the
northeast property boundary is formed by the
valley wall and a sand and gravel quarry. Adjacent
to the southern boundary of the site is the City of
Port Jervis Landfill.  The landfill is no longer active;
however, Orange County currently operates a solid
waste transfer station on a portion of the landfill
property. Approximately 1,500-feet to the east of
the site is Gold Creek.  The nearest resident
located downgradient of the site is approximately a
quarter of a mile from the site.

From approximately 1970 to 1979. the site was
used  for the disposal of septic and municipal
sewage sludge and industrial wastes, primarily from
the cosmetic industry.  The industrial  waste was
deposited in one or more of the seven lagoons

-------
located at the site (lagoons 1 through 4 and 6
through 8 depicted in Figure  1).  Initially. EPA
believed that the industrial wastes were deposited
only in lagoons 1 through 4.  In July 1992 however,
the site was expanded to include the investigation
of areas believed to contain four additional filled-in
lagoons (lagoons 5. 6, 7 and 8).  These lagoons
were tentatively identified in historical aerial
photographs. Trenching in the area of lagoons 6. 7
and 8 confirmed the presence of sewage sludge
and industrial waste; trenching in the area of
lagoon 5 revealed the presence of tires Instead of
industrial waste. The dimensions of lagoons 1, 2,
3, 4, 6. 7 and 8 are approximately 100 feet by 60
feet, 200 feet by 60 feet, 100  feet by 35 feet,  100
feet by 40 feet,  60 feet by 20 feet, 100 feet by 45
feet, and 150 feet by 40 feet, respectively.

In 1978, lagoon 3 was ignited by the Port Jervis
Fire Department in order to practice suppression of
chemical fires.  After this incident, lagoons 3 and 4
were filled in with soil and the area was
revegetated.  With the exception of lagoons 1 and
2, all of the lagoons have been covered with soil.
Lagoons 1  and 2 were left uncovered and are
surrounded by  a wooden fence. In June 1979,
NYSDEC prohibited the disposal of industrial
wastes at the site.  The site continued to be  used
for the disposal of septic and municipal sewage
wastes until 1989.

In February 1987, NYSDEC issued a Phase II  .
Investigation Report which summarized past
investigations and included a Hazard Ranking
System (HRS) score for the site. Based on the
MRS score, the site was proposed for inclusion on
the National Priorities List (NPL) in June 1988 and
was placed on the NPL in February 1990.

On September 25, 1989, EPA sent "special notice"*
letters to four potentially responsible parties
(PRPs), affording them the opportunity to conduct
the RI/FS for the site.  (PRPs are companies or
individuals who are potentially responsible for
contributing to the contamination at the site and/or
are past or present owners of the property.)  The
PRPs were given 60 days in which to submit a
good faith offer to undertake or finance the RI/FS
for the site.

On November  30, 1989. two of the four PRPs
submitted  to EPA a good faith offer to perform the
RI/FS.  An Administrative Consent  Order was •._-
signed by the two PRPs and by EPA in February
 1990.  The PRPs conducted the RI/FS under EPA's
"supervision.
During the Rl, EPA learned from the City of Port
Jervis that it owned a major portion of the site
property where the lagoons are located.  In an April
22,1993 letter, EPA notified the City that It was
also a PRP for the site.  After issuance of the ROD.
all the PRPs will be offefed the opportunity to
design and implement the selected remedial
alternative for the site.

SCOPE*AND ROLE OF ACTION

This is the first of two planned operable units for
the site. This operable unit addresses the source
areas (lagoons and surrounding impacted soils) at
the site and actions needed to ensure that the
source areas do not pose a threat to human health
or the environment, including any potential cross
media impacts to groundwater.  The second
operable unit investigation which is currently
underway, will address the need for remediating
contaminated groundwater underlying the site. The
two PRPs which performed the RI/FS for the first
operable unit are currently performing the RI/FS for
the second operable unit with supervision by EPA.

REMEDIAL INVESTIGATION SUMMARY

The intent of the investigation was to characterize
the soil quality of the seven lagoons at the site and
any potential cross media impacts to the
groundwater quality in the vicinity of these lagoons.
The remedial investigation consisted of drilling
borings and constructing monitoring wells,
collecting soil and groundwater samples, and
conducting a geophysical survey. The PRPs hired
Elaslarid & Bouck Engineers (B&B) to  implement
the RI/FS.

The geophysical survey determined that the
elevation of the site ranges from approximately 440
to 520 feet above mean sea level. The materials
 encountered underlying the site consist of glacially
 derived unconsplidated materials underlain by
 consolidated bedrock.  The thickness of the
 unconsolidated overburden materials ranges from
 zero  feet at the exposed bedrock slope forming the
 northwestern site boundary, to over 60 feet along
 the towpath. The glacially derived materials consist
 of two distinct  units, including a glacial till unit
 overlain by glacial outwash deposits.  The outwash
 deposit was observed to vary  in thickness from 31
 feet to 52 feet along the downgradient edge of the
 site.  The outwash deposits typically consist of
 medium dense to very dense brown sand with
 some clayey silt and gravel. The glacial till
 deposits are characterized as  dense to very dense
 dark grey silt with sand and gravel. The glacial till
 is not continuous beneath the site, and  appears to

-------
pinch out toward the northwestern edge of the site.
The depth to groundwater from ground surface
ranged from approximately 30 to 40 feet along the
southeastern boundary of the site.  Groundwater
movement is generally towards the southeast.

Between July and September 1991. approximately
20 soil/sludge samples were collected from
lagoons 1 through 4 and the surrounding soils;
these samples were analyzed for organic and
inorganic constituents. During January and
February 1993, 54 additional soil samples were •.
collected to further delineate the horizontal extent
of lagoons  1 through 4 and to characterize the
berm soil around lagoons 1 and 2. Various organic
constituents were detected in these lagoons and
the surrounding soils. Some of the highest
concentrations of organic contaminants included
benzene (650 parts per million (ppm)). 1.2-
dichlorobenzene (430 ppm), 1,4-dichlorobenzene
(250 ppm), tetrachloroethene (290 ppm). and
toluene (370 ppm).  Inorganic constituents
detected in lagoons 1 through 4 and surrounding
soils included arsenic (10.7 ppm), barium (1290
ppm), chromium (137 ppm), cyanide (320 ppm),
lead (1,400 ppm), and nickel  (368 ppm).

Higher levels of organic and inorganic constituents
were detected in lagoons 6. 7 and 8.  Approxi-
mately" 45 soil and sludge samples were collected
from within and around the perimeter of lagoons 6,
7 and 8 during January and February  1993. Some
of the highest concentrations of organic
contaminants detected included benzene (2.800
ppm), tetrachioroethene (12,000 ppm), and toluene
(13,000 ppm).  Inorganic constituents detected in
lagoons 6, 7 and 8 included arsenic (9.7 ppm),
barium (933 ppm), chromium (16,000 ppm), and
lead (609 ppm).  In general, organic compounds
were detected at higher concentrations in lagoon 7,
and inorganic compounds were detected at higher
concentrations in lagoon 8.

Five background soil samples were collected from
areas not affected  by site contamination to use as
a point of reference. One of the five soil samples
was analyzed for organic constituents. All five
background soil samples were analyzed for
inorganic constituents.  Other than 0.01 ppm of
methylene chloride, organic compounds were not
detected in the background soil sample.  The
highest concentrations of various inorganic
 constituents detected in the background soil
 samples included 7:0 ppm of arsenic. 43.1 ppm of
 barium. 61.9 ppm of chromium. 45.6 ppm of lead.
 and 36.7 ppm of nickel. Cyanide was not detected
 in any of the background soil samples.
The source materials from lagoons 1. 2, 7 and 8
were tested using the toxic characteristics leaching
procedure (TCLP) to determined if these materials
would be considered Resource Conservation and
Recovery Act (RCRA) hazardous waste based on
the characteristic of toxicity. The source materials
from lagoons 1 and 2 did not leach organic or
inorganic constituents at concentrations above the
regulatory criteria for determining a RCRA
hazardous waste. The source materials from
lagoon 7 failed the  TCLP for benzene,
tetrachloroethene, trichloroethene and vinyl
chloride and are therefore considered RCRA
hazardous waste based on the characteristic of
toxicity. Lagoon 8  failed the TCLP for benzene and
chromium; therefore, these materials  would be
considered RCRA hazardous waste based on the
characteristic of toxicity.

During August 1991, December 1991, March 1993
and October 1993.  groundwater samples were
collected from the vicinity of the lagoons and
analyzed for organic and inorganic compounds.
Monitoring wells located downgradient of lagoons 1
through 4 were sampled during August 1991.
December 1991 and March 1993, and monitoring
wells located downgradient of lagoons 6, 7 and 8
were sampled in October 1993. These monitoring
wells monitor either the bedrock, the glacial till, the
glacial outwash or  both the glacial till and outwash
units.

Four organic compounds, benzene, 1,2-dichloro-
ethene (total), tetrachloroethene and
trichloroethene were detected above the Federal
and/or State drinking water standards In the
 monitoring wells located downgradient of lagoons 1
through 4 during August and December 1991 and
 March 1993. These four organic  compounds were
 detected in the monitoring wells that monitor either
 the glacial outwash or both the glacial till and
 outwash.  Organic contaminants were not detected
 above Federal or State drinking water standards in
 any of the bedrock or glacial till monitoring wells.
 Aside from tetrachloroethene detected in
 monitoring well OW-6. organic compounds only
 were detected above the Federal and/or State
 drinking water standards at monitoring wells
 located along the  D&H towpath (e.g.. OW-2. OW-3
 and MW-4).  The monitoring wells located
 downgradient of the D&H towpath (e.g.. OW-5,
 OW-6. OW-7 and  OW-8). however, were installed in
 1993 and were only sampled in the October 1993
 sampling event. Higher concentrations of the four
 organic contaminants were detected in 1991 than
 in 1993.  The highest concentrations of organic
 compounds detected above drinking water
 standards were benzene at 52 parts per billion

-------
(ppb) in monitoring well OW-3, 1,2-dichloroethene
(total) at 230 ppb in monitoring well OW-2,
tetrachloroethene at 130 ppb in monitoring wells
OW-2, and  trichloroethene at 41 ppb in monitoring
well MW-2.  The Federal and State drinking water
standards for benzene, tetrachloroethene and
trichloroethene are all 5 ppb. The State drinking
water standard for 1,2-dichloroethene isomers Is 5
ppb, which is more stringent than the Federal
standard.

Inorganic compounds (arsenic,  beryllium,
chromium, lead and nickel) were detected  above
the Federal and/or State drinking water standard in
monitoring wells downgradient of lagoons  1
through 4 only during the 1991  sampling events.
During the March 1993  sampling, only cadmium
was detected above drinking water standards.
Cadmium was detected in monitoring well  OW-3 at
6 ppb, which is slightly  higher than the Federal and
State drinking water standard of 5 ppb.

During the October 1993 sampling of monitoring
wells located downgradient of lagoons 6, 7 and 8
(OW-9,  OW-10, OW-11, OW-12, OW-13. OW-14 and
BW-5), benzene was detected above both the
Federal and State drinking water standards; seven
other organic compounds were detected above the
State drinking water standards but below the
Federal drinking water standards.  The highest
concentrations of organic compounds detected
were benzene at 1,300  ppb in monitoring well OW-
12; 1,3,5-trimethylbenzene at 12 ppb in monitoring
well  OW-11; 1,2,4-trimethylbenzene at 44 ppb in
monitoring well OW-12; 1,2-dichlorpethene (total) at
12 ppb in monitoring well OW-13; ethylbenzene at
9.8 ppb in monitoring well OW-12; toluene at 9.6
ppb in monitoring well OW-12;  and xylene at 40
ppb in monitoring well OW-12.  The State  drinking
water standard for 1,3,5-trimethylbenzene, 1.2,4-
trimethylbenzene, ethylbenzene. toluene, and
xylene is 5 ppb. The Federal drinking water
standard is 700 ppb for ethylbenzene, 1,000 ppb
for toluene and 10,000  ppb for xylene. A  Federal
drinking water standard does not exist for 1,3,5-
trimethylbenzene or 1,2,4-trimethylbenzene.

Nine inorganic compounds were detected above
 Federal and/or State drinking water standards in
the seven monitoring wells located downgradient of
lagoons 6. 7 and 8. Nine inorganic compounds
were detected above drinking water standards.
 However, six of these inorganic compounds were
detected above standards only in monitoring welf
 OW-10. Chromium, lead and nickel were detected
 above drinking water standards in more than one
 monitoring well and were detected at levels that
 ranged from 106 to 2.930 ppb. 19.1 to 924 ppb and
100 to 1,560 ppb, respectively. The inorganic
compounds detected above drinking water
standards in monitoring well OW-10 were about an
order of magnitude higher than the levels detected
in the other monitoring wells.  The Federal drinking
water standards for chromium and  nickel are set at
100 ppb; the Federal action level for lead Is 15 ppb.
The State drinking water standards for chromium
and lead are 100 and 50 ppb, respectively.  A State
drinking-water standard does not exist for nickel.
As previously mentioned, an Investigation to
determine the lateral and downgradient extent of
the groundwater plume is currently underway and
will be reported in the Rl for the second operable
unit.

The New York State Department of Health sampled
several off-site private wells in 1991 and again in
1993  for organic and inorganic constituents.
Organic  constituents were not detected  In the
groundwater from these wells, and inorganic
constituents were detected below drinking water
standards.

SUMMARY OF SITE RISKS

Based upon the results of the Rl. a baseline risk
assessment was conducted to estimate the risks
associated with current and future site conditions.
The baseline risk assessment estimates the human
health and ecological risk which could result from
the contamination at the site, if no remedial action
were taken.

As part of the baseline risk assessment, the
following four-step process is utilized for assessing
site-related human health risks for a reasonable
 maximum exposure scenario: Hazard
/ctenf/fi'car/on-identifies the contaminants of
concern at the site based on several factors such
as toxicity, frequency of occurrence, and
 concentration. Exposure Assessment-estimates
the magnitude of actual and/or potential human
 exposures, the frequency and duration of these
 exposures, and the pathway (e.g.  ingesting
 contaminated well-water) by which humans are
 potentially exposed. Toxicity Assessment-
 determines the types of adverse health effects
 associated with chemical exposures, and the
 relationship between magnitude of exposure (dose)
 and  severity of adverse effects (response).  Risk
 Characterization-summarizes and combines
 outputs of the exposure and toxicity assessments
 to provide a quantitative (e.g., one-in-a-million
 excess  cancer risk) assessment of site-related
 risks.

-------
The risk assessment was prepared before the
analytical soil data associated with lagoons 6. 7
and 8 were available.  Therefore, only the data
collected from lagoons 1 through 4 during July and
September 1991 were used in the risk assessment.
A separate risk assessment was not prepared for
lagoons 6, 7 and 8 since it was anticipated that
remedial action would be taken at these lagoons
due to the levels of contaminants found, the
presence of hazardous waste and cross media
impacts to groundwater. Higher baseline risk levels
would be expected if the analytical soil data from
lagoons 6, 7 and 8 were included in the risk
assessment.

The baseline risk assessment began with selecting
contaminants of concern which would be
representative of site risks. These contaminants
included benzene, 1.2-dichlorobehzene,
tetrachloroethene, toluene, arsenic, barium,
chromium, cyanide, lead, and nickel.

The baseline risk assessment addressed the
potential risk to human health by identifying
potential exposure pathways by which the public
might be exposed to contaminant  releases at the
site under current  and future land-use conditions.
The exposure pathways under the current land-use
condition included the exposure to adult and child
.trespassers through the dermal -contact with
standing water contained in lagoon 1, and through
the ingestion,  inhalation'and dermal contact of soils
and sludges.  When considering future land  use,
the exposure pathways included the ingestion,
inhalation and dermal contact of soils and sludges
 by construction workers.  Because the site is
surrounded by a cliff, a landfill and a quarry, future
 residential use of the  property was not considered
as a reasonable scenario.
                                               *
 EPA's acceptable cancer risk range is 10"4 to 10"8
which can be interpreted to mean that  an individual
 may have a one in ten thousand to a one in a
 million  increased chance of developing cancer as a
 result of a site-related exposure to a carcinogen
 over a  70-year lifetime under the specific exposure
 conditions at a site. The results of the baseline risk
 assessment indicated that the soils and sludges
 associated with lagoons 1 through 4 pose no
 unacceptable carcinogenic risk to human health.
 The sum of the current cancer risks for the
 exposure pathways for adult and child trespassers
 was 5 x 10"7 (fh/e  in ten million) and 3 x 10"6 (three
 in  a million), respectively. The overall future •
 carcinogenic  risk  for  construction workers, .through
 ingestion, inhalation and dermal contact of
 contaminated soils and sludges, was estimated to
be 4 x 10"" (four In a m'lIHpn). These carcinogenic
risks are within EPA's acceptable risk range.

To assess the overall potential for noncarcinogenic
effects posed by the contaminants at the site, EPA
has developed the hazard index (HI).  An HI value
of greater than 1 is considered to pose a potential
noncarcinogenic risk. The calculated HI values for
trespassers are less than 1, which  EPA has
determined to be acceptable.  The total exposure
HI for construction workers assumed to be
participating in excavation and grading activities
was estimated to be 3.0. Therefore, there are
unacceptable noncarcinogenic risks associated
with the construction worker scenario.  The primary
contributor to this risk is chromium-containing dust
which could be inhaled during excavation activities.

As previously noted, higher  risk  levels from
exposure to contaminated soil would have resulted
if the analytical soil data from  lagoons 6, 7 and 8
were included in the risk assessment.  A risk
assessment to identify the potential risk to human
health through groundwater pathways would be
prepared during the second operable unit. As
indicated by the groundwater sampling data,
contaminants from the  soil are migrating into the
groundwater at concentrations above Federal and
State health-based drinking water standards.
                                   *
The qualitative ecological assessment concluded
that the site provides low to moderate habitat value
to wildlife.  The degree of physical disturbance on-
site and lack of continuous  quality habitat in
adjacent areas restrict the diversity and extent of
wildlife'use at the site.  Therefore, only minor
impacts on wildlife are  expected to occur.

 REMEDIAL ACTION OBJECTIVES

 Remedial action objectives  are  specific goals to
 protect human health and the environment.  These
 objectives are based on available information and
 standards such as applicable or relevant and
 appropriate requirements (ARARs) and risk-based
 levels established in the risk assessment. The
 remedial action objective for the source areas at
 the site is to prevent leaching of contaminants in
 the soils/sludges at levels which will contribute to
 the contravention of groundwater quality and
 drinking water standards in the groundwater in the
 vicinity of the site and  to minimize potential risks to
 hypothetical excavation workers.

-------
SUMMARY OF REMEDIAL ALTERNATIVES

CERCLA requires that each selected site remedy
be protective of human health and the
environment, be cost effective, comply with other
statutory laws, and utilize permanent solutions and
alternative technologies and resource recovery
alternatives to the maximum extent practicable. In  .
addition, the statute includes a preference for the
use of treatment as a principal element for the
reduction of toxicity, mobility, or volume of the
hazardous substances.
                                            •
This Proposed Plan evaluates in detail six remedial
alternatives for addressing the soil/sludge
contamination at the Carroll and Dubies  Sewage
Disposal Inc. site.  As used in the following text, the
time to implement  reflects only the time required to
implement the remedy, and does not include the
time required to procure contracts for design and
construction or to  negotiate with responsible
parties for implementation of the remedy.

Alternative 1: No Action
                                  Alternative 3: Low-Permeability Cap with Slurry
                                  Cut-Off Walls
Capital Cost:
O & M/yr Cost:
Present Worth:
Time to Implement:
SO
$0
$0
0 months
The Superfund program requires that the "no- .
action" alternative be considered as a baseline for
comparison with other alternatives.  Under this
alternative, the contaminated soil would be left in
place without treatment.  The site would remain in
its current condition and no effort would be made
to change the current site conditions.

Alternative 2: Limited Action
 Capital cost:
 O & M/yr Cost:
 Present Worth:
 Time to Implement;
$  52,000
$  18,000
$ 328.660
6 months
 This alternative consists of institutional controls
 such as deed restrictions to limit future use of the
 site and complete fencing of the site to minimize
 potential human exposure to the source area
 materials.  The limited action alternative would not
 utilize any remedial technologies for the treatment
 of the source areas. A long-term groundwater
 monitoring program would be implemented to track
 the migration of contaminants from the source  -"
 areas into the groundwater utilizing existing
 .monitoring wells at the site.
                                  Capital Cost:
                                  0 & M/yr Cost:
                                  Present Worth:
                                  Time to Implement:
                        $ 3.299,816
                        $   147.060
                      "  $5.560,128
                    12 months
This alternative includes the construction of a low-
permeabfflity cap over the source materials to
minimize the infiltration of precipitation.  Limiting
the amount of water which percolates through the
source materials may reduce the leaching of the
chemical constituents into the groundwater
underlying the site.  In addition to the cap. slurry
cut-off walls would be installed around the source
area to minimize the migration of son gas and
leachate from the impacted source areas into the
surrounding soils and to minimize the movement  of
precipitation from outside the cap through the
source area materials. The cap would be
constructed of a low-permeability material such as
natural clay, geosynthetics, asphalt or
combinations of these materials. Additional
drainage and top soil layers would  be included tc
achieve a well drained, vegetated surface upon
completion.  Deed restrictions would be
recommended to limit future use of the site  in order
to protect the integrity of the cap.

The cut-off walls would be constructed  by
excavating vertical trenches while filling the
excavation with a soil-bentonite slurry.  The slurry
walls would be keyed into the bedrock  unit  which
underlies the site.  This bedrock unit consists of
shale and silt stone and ranges from ground
surface to 60 feet below grade.  Groundwater at
the site is present within the overburden soil
materials. Therefore, hydrodynamic controls would
be required to maintain the effectiveness of the cap
and slurry wall.  Hydrodynamic controls would
 include pumping groundwater from within the
 capped  area to maintain a static water level within
the capped area.  The collected water would be
treated on-site  in a granular activated carbon
 (GAC) adsorption treatment system prior to
 discharge.  The spent carbon would be
 regenerated or shipped off-site to an appropriate
 disposal facility.  Groundwater monitoring would be
 performed annually  utilizing existing monitoring
 wells at the site.

-------
Alternative 4: Stabilization/Solidification and
Placement into an On-Site Containment Cell

Capital Cost:      $ 5,389.215
O & M/yr Cost:      $   26.400
Present Worth:      S 5,794.983
Time to Implement:   12  months

This alternative involves the physical removal of
approximately 20,300 cubic yards (cy) of source
area materials and treatment of these materials
through stabilization/solidification. The volume of
source area materials requiring treatment consists
of materials that contained organic constituents at
levels above the NYSDEC soil cleanup levels
(Technical and Administrative Guidance
Memorandum No. 4046) and inorganic constituents
above the highest background level detected,
utilizing chromium and nickel as indicator
constituents. The approximate volume of source
area materials to  be removed from each lagoon is
2,600 cy from lagoon 1.  3,950 cy from lagoon 2,
2.300 cy from lagoon 3,  2.320 cy from lagoon 4,
520 cy from lagoon 6, 3,420 cy from lagoon 7. and
5,200 cy from lagoon 8.

Stabilization/solidification is a process by which
. stabilization agents such as cement-based,
pozzolanic-based, asphalt-based, and organic-
polymer-based agents are mixed with the source
area materials to  convert the waste to a more
stable form.  Capture and control mechanisms
would be installed, as necessary to control air
emissions containing organic constituents emitted
during the stabilization/  solidification process to
 ensure compliance with  Clean Air Act standards.
 Air monitoring would also be conducted during
 implementation of this alternative to determine the
 need for additional engineering controls.
                                              *
 The stabilized mass would then be placed  into a
 lined cell which would consist of a high density
 polyethylene (HOPE) liner and a sand drainage
 layer. The cell would be sloped to a wet well
 located adjacent  to the cell to collect any leachate
 that is generated by the solidified materials. Once
 the treated source area  materials are placed into
 the cell, a cap (modified New York Code of Rules
 and Regulation, Part 360) would be constructed
 over the cell to minimize the infiltration of rainwater.
 The cap would consist of a low-permeability clay
 layer, an HOPE membrane, a sand drainage layer,
 and a topsoil cover layer. Deed restrictions would
 be recommended to limit future use of the site iff
 order to protect the integrity of the cap.  Leachate
 -would be removed  periodically from  the wet well
 and sent off-site  for treatment and disposal in
compliance with applicable regulations.
Groundwater monitoring would be performed
annually utilizing existing monitoring wells at the
site.

Alternative 5: Low-Temperature Thermal
Desorption, Stabilization/Solidification, and
Placement into art On-Site Containment Cell
Capital Cost:
0 & M/yr Cost:
Present Worth:
Time to Implement:
    $ 11.351.132
    $     26.400
    $ 11,756.900
12 months
This alternative consists of excavating
approximately 20,300 cy of source area materials
and treating some of these materials on-site using
a mobile Low-Temperature Thermal Desorption
(LTTD) unit LTTD is a process by which
soils/sludges are heated and the organic
constituents are desorbed from the soils/sludges
and volatilized into an induced air flow. The
soils/sludges are heated to temperatures ranging
from 200°F to 1.200°F. Air or nitrogen carrier gas
is passed over the soils/sludges to collet the
volatilized organic constituents. The carrier gas is
then treated by either condensation and carbon
adsorption or by thermal destruction in a
combustion afterburner to limit emissions to within
the regulatory requirements. Materials from
lagoons 1, 3, 7 and 8 (approximately 13,500  cubic
yards) which contain high concentrations of
organic contaminants would be treated with the
LTTD unit. Other means of treating the lagoons
containing high concentrations of organic
contaminants, such as vapor extraction or bidslurry
treatment could conceivably achieve appropriate
treatment levels for organics and could be
considered as a substitute for the LTTD portion of
this alternative if sufficient information is generated
during the public comment process which
convinces EPA that one of these alternatives would
be appropriate.  Air monitoring would be
conducted during implementation of this alternative
to ensure air emissions are within regulatory limits.

Upon completion of the thermal treatment of the
 source materials for their organic constituents,
lagoons 6 and 8 (approximately 5,700 cy) would be
treated through stabilization/solidification to reduce
the mobility of the inorganic constituents.  Source
 area materials from lagoons 1. 2. 3, 4 and 7 that do
 not meet the RCRA-Regufated Levels for TCLP or
 that are needed to achieve adequate load bearing
 capacity would also be stabilized/solidified.  All
 excavated source area materials (approximately
 20,300 cubic yards) would then be placed in a

-------
ined cell with a wet well for leachate collection,
and then capped.  The lined cell and cap are the
same as that described in Alternative 4.  Deed
restrictions would be recommended to limit future
use of the site in order to protect the integrity of
the cap.  Groundwater monitoring would be
performed annually utilizing existing monitoring
wells at the site.

Alternative 6: Off-Site Disposal at a Permitted
Landfill
Capital Cost:
O & M/yr Cost:
Present Worth:
Time to Implement:
$ 32.679,764
$0
$32,679,764
     12 months
This alternative consists of excavating 20,300 cy of
source area materials and transporting these
materials off-site to a RCRA-permitted treatment,
storage and disposal facility for treatment and
disposal, as appropriate.  Excavated materials
would be placed directly into lined 20 cy roll-offs.
Some of the source area materials might need to
be dewatered prior to off-site transportation.  Each
.roll-off would be sampled to characterize the
• source area materials prior to transportation off-
"site.  Based on-the analytical data available for the
source area materials, the materials from Lagoons
6, 7 and 8 would require pre-treatment to meet the
land disposal restrictions  (LDRs) prior to disposal
at a RCRA-permitted landfill. Air monitoring would
also be conducted during implementation of this
alternative to determine the need for engineering  •
controls.

 For purposes of evaluating this alternative,
 incineration and solidification were considered to
 be the appropriate pre-treatment methods  to
 address the source area materials which do not   ,
 meet LDR requirements.  It is estimated that the
 volume of source area materials that would require
 pretreatment prior to land disposal is approximately
 9.130 cy.

 EVALUATION OF ALTERNATIVES

 During the detailed evaluation of remedial
 alternatives, each alternative is assessed against
 nine evaluation criteria, namely, overall protection
 of human health and the environment; compliance
 with ARARs; long-term effectiveness and
 permanence; reduction of toxicity, mobility, or
 volume; short-term effectiveness; implementabilify;
 cost; and community and state acceptance. For a
 more detailed explanation, see the comparative
 analysis contained in the FS.
Glossary of Evaluation Criteria

• Overall protection of human health and the
  environment addresses whether or not a remedy
  provides adequate protection and describes
  how risks are eliminated, reduced, or controlled
  through treatment, engineering controls, or
  Institutional controls. -

• Compliance with ARARs addresses whether or
  not a remedy will meet all of the applicable or
  relevant and appropriate requirements and/or
  provide grounds for invoking a waiver.

*  Long-term effectiveness and permanence refers
  to the ability of a remedy to maintain reliable
  protection of human health and the environment
  over time, once cleanup goals have been met.
  It also addresses the magnitude and
  effectiveness of the measures that may be
  required to manage the. risk posed by treatment
  residuals and/or untreated wastes.

 »  Reduction of toxicitv. mobility, or volume
  through treatment is the anticipated performance
   of the treatment technologies a remedy may
   employ.

 » Short-term effectiveness addresses the  period of
   time needed to achieve protection from any
   adverse impacts on human health and the
   environment that may be  posed during the
   construction and implementation period until
   cleanup goals are achieved.

 *  Imptementabilitv is the technical and
   administrative feasibility of a remedy,  including
   the availability of materials and services needed
   to implement a particular option.

 *  Cost includes both estimated capital  and
   operation and maintenance costs, and net
   present worth costs.

 »  State acceptance  indicates whether,  based on
    its review of the RI/FS  report and Proposed
    Plan, the State concurs with,  opposes, or has no
    comment on the preferred alternative.

  *  Community acceptance will be assessed in the
    ROD and refers to the  public's general response
    to the alternatives described in the RI/FS report
    and" the Proposed Plan.

  A comparative analysis of the remedial alternatives
  based upon the evaluation criteria noted above
  follows.

-------
Overall Protection of Human Health and the
Environment

Alternative 6 would be most protective of human
health and the environment since source area
materials would be removed from the site.
Alternatives 4 and 5 would mitigate cross-media
impacts to the groundwater from the source and
therefore would be protective of human health
and the environment.  Alternative 5 would,
however, provide a higher degree of overall
protection of human health and the environment
than Alternative 4 since organic contaminants
would be permanently removed from source
area materials having high levels of organic
contamination.  Alternative 3 may result in the
continued leaching of constituents to the
groundwater and therefore would not be as
protective to human health and the environment
as Alternatives 4, 5 and 6. Alternatives 1 and 2
would not reduce the leaching of the chemical
contaminants to the site groundwater and
therefore would not be protective of human
health and the environment.

Compliance with ARARs

All remedial technologies proposed for use in
Alternatives 3, 4, 5 and 6 would be designed and
implemented to meet ARARs.  Wastes would be
treated using specific technologies or treated to
specific treatment levels, as appropriate, to
comply with air pollution control and RCRA
hazardous waste regulations.  Federal and State
regulations dealing with the handling and
transportation of hazardous wastes to an off-site
treatment facility would be followed with regard
to Alternative 6.  Alternative 2, 3, 4 and 5 would
require compliance with various local
requirements for implementing deed restrictions.
Alternative 1 would  not be subject  to any
ARARs.  In addition, for reasons discussed
below under Long-Term Effectiveness and
'Permanence, Alternative 6 followed by
Alternatives 5, 4, and 3 would minimize-cross-
media impacts of contaminants migrating from
soil to groundwater thereby enabling
groundwater standards to be achieved in a
shorter time frame. Alternatives  1  and 2 would
not provide this benefit.

Long-Term Effectiveness and Permanence

Alternative 6 would provide the highest degree*
of long-term effectiveness and permanence
since the contaminated soils would be
 permanently removed from the site.  Alternatives
4 and 5 would mitigate the leaching of
  contaminants to the underlying groundwater.
  Alternative 5 would, however, provide the higher
  degree of long-term effectiveness and
  permanence than the remaining alternatives
  since organic contaminants would be
  permanently removed from the source area
  materials having high levels of organic
  contamination; it would also effectively address
  Inorganic contaminants.  Unlike Alternative 5,
  Alternative 4 depends on the long term
  effectiveness of the stabilization/solidification,
  containment cell and leachate collection system
  to prevent the leaching of organic contaminants
  into the groundwater; it does effectively address
  inorganic contaminants over the long-term.
  Alternative 3 may continue to leach
  contaminants from the source area materials
 . into the groundwater; the permanence of
  Alternative 3 would rely on the continued
  maintenance of the cap and slurry cutoff wall.
  and the operation and maintenance of the
  hydraulic control system. Alternatives 1 and 2
  would not provide any active treatment or
  containment and therefore would not be
  effective over the long-term  or provide
  permanent protection of the groundwater
  underlying the site.

*  Reduction in Tbxicity. Mobility, or Volume
   Through Treatment

   Alternative 6 would provide a reduction in
   contaminant mobility, toxicity, and volume of
   the organic and inorganic chemical
   contaminants present at the site by permanently
   removing the source area materials from the
   site and treating the materials, as necessary,
   prior to their disposal at a RCRA-permitted,
   landfill.  Alternative 5 would provide a reduction
   in the mobility, toxicity, and volume of organic
   contaminants in the source areas having high
   levels of organic contaminants by permanently
   removing the organics from the source areas.
   Alternative 5 would provide a reduction in the
   mobility of the inorganic contaminants through
   stabilization/solidification of the source area
   materials failing TCLP and  placement of all
   source area materials in a  lined containment
   cell with a leachate collection system.
   Alternative 4 would provide a reduction in the
    mobility of the organic  and inorganic
    contaminants present in the source area
    materials through stabilization/solidification of
    the materials and placement of the solidified
    materials in a lined containment cell with a
    leachate collection system. However, as noted
    above the long-term effectiveness of
    stabilization/solidification for immobilizing
                                                 10

-------
   organic contaminants has not been
   demonstrated. Alternative 3 would not provide a
   reduction in the toxicity or volume of the organic
   and inorganic contaminants in the source area
   materials; however, this alternative would reduce
   the mobility of the chemical constituents through
   capping, installing slurry cut-off walls and
   pumping groundwater from within the capped
   area.  Alternatives 1 and 2 would provide no
   reduction in contaminant mobility, toxicity, or
   volume.

* Short-term Effectiveness

  Alternatives  1 and 2 would result In no additional
  risk to the community or workers during
  implementation, since source area materials
  would not be disturbed.  Alternatives 3, 4, 5 and
  6 would include activities such as excavation
  and handling of contaminated soils/sludges that
  could result in short-term exposures to on-site
  workers and the community during
  implementation due to the generation of fugitive
  dust.  Mitigation  measures such as water sprays
  to suppress dust would be implemented to
  control short-term environmental impacts
  associated with off-site dust migration.
  Alternative 5 would also  result in the potential
  exposure to on-site workers and the community
  .to air emissions associated with the LTTD
  treatment system.  The air emissions from the
  LTTD unit would be controlled by implementing
  air emission treatment systems and air emission
  monitoring programs. Alternative 6 would also
  include activities such as off-site transport of
  contaminated  soils/sludges that could result in
  potential exposure to the community.  To reduce
  the potential risks to the community and the
  environment resulting from an accident during
  transportation, a traffic control plan would be  *
  developed.

» Implementabilitv

  All alternatives are technically feasible and could
  be implemented .at the site.  Alternatives 1  and 2
  are the easiest to implement. A treatability study
  would be necessary to demonstrate that
  Alternative 4 (stabilization/solidification) is able
  to  render the lagoon 7 material nonhazardous
  based on the  characteristic of toxicity.  The high
  moisture content and clay-like material
  properties of some of the source area materials
  may make Alternative 5  (LTTD process) difficult
  to  implement. The implementability of LTTD
  would need to be confirmed by treatability study
  testing.
» Cost

   According to the present worth cost estimates
   for all alternatives evaluated, Alternative 6
   ($32,679,764) would b.e the most costly
   alternative to implement, followed by Alternative
   5 ($11.756,900).  The present worth cost for
   Alternatives 4 and 3 would be about the same
   ($5,794.983 and $5.560,128. respectively).
   Alternatives 2 and 1 would be the least costly to
   implement ($328,660 and $0, respectively).
   Present worth considers a 5% discount rate,
   and a 30-year operational period for Alternatives
   2, 3. 4 and 5. Since Alternatives 6 and 1 do not
   require any O & M costs, their present worth
   costs are equivalent to their capital cost.

*  Community Acceptance

   Community acceptance of the preferred soil
   alternative will be assessed in the ROD
   following a review of the public comments
   received on  the RI/FS report and the Proposed
   Plan.

*  State Acceptance

   NYSDEC concurs with the preferred alternative
   for remediating the soils and sludges at the site.

PREFERRED ALTERNATIVE

Based upon an evaluation of the various
alternatives, EPA and  NYSDEC recommend
Alternative 5 (Low-Temperature Thermal
Desorption, Stabilization/Solidification, and
Placement into  an On-site Containment Cell).
Alternative 5 permanently removes organic
contaminants from source area materials and
reduces the mobility of inorganic contaminants
through stabilization/solidification and placement of
source area materials in a lined containment cell
constructed on-site.  Alternative 5 ensures that no
leaching of contaminants to the underlying aquifer
will occur. The  elimination of cross-media impacts
will have a positive impact on the effectiveness of
any future groundwater restoration program that
could be implemented at the site.

Alternative 5 is  the only alternative that permanently
 removes the organic contaminants from source
 area materials except for Alternative 6 which is over
 twice the cost of the preferred alternative and may
 not  comply with the statutory preference for
 treatment as a  principal element. The other
 proposed alternatives which cost much less than
 the  preferred alternative do not permanently
 remove contaminants from the source area
                                                  11

-------
materials. The preferred alternative will provide the
best balance of trade-offs among alternatives with
respect to the evaluating criteria. EPA and
NYSDEC believe that the preferred alternative will
be protective of human health and the
environment, will comply with ARARs, will be cost
effective, and will utilize permanent solutions and
alternative treatment technologies or resource
recovery technologies to the maximum extent
practicable.  The remedy also will meet the
statutory preference for the use of treatment as a
principal element.
                                                   12

-------
 Appendix B
Public Notice

-------
 A he U.S. Environmental Protection Agency (EPA) will hold a
public meeting to discuss the Proposed Plan for the Carroll and
Dubies Sewage Disposal Inc. Superfund site, located in Port Jervis,
New York.
EPA has scheduled a public meeting to discuss the findings of the
Remedial Investigation/Feasiblity Study at 7 p.m.,  on Tuesday,
August 23, 1994, at the Port Jervis High School in Port Jervis,
New York.  The release of the Proposed Plan and the scheduled
public meeting are in accordance with EPA's public participation
responsibilities  under  Section- 117(a)  of  the Comprehensive
Environmental  Response,  Compensation   and  Liability  Act
(CERCLA) of 1980.
EPA reviewed several alternatives to address the contaminated soil
at the site. Alternatives included: 1) No Action; 2) Limited Action;
3)  Low-Permeability  Cap   with  Slurry  Cut-Off Walls;  4)
Stabilization/Solidification  and  Placement  into  an  On-Site
Containment Cell;   5)" Low-Temperature Thermal Desportion
(LTTD), Stabilization/Solidification, and Placement into an On-Site
Containment Cell; and 6) Off-Site Disposal at a Permitted Landfill.
Based   upon  an  evaluation of  these alternatives,  EPA  is
recommending:   Low-Temperature  Thermal   Desorption,
Stabilization/Solidification  and  Placement  into  an   On-Site
Containment Cell.
EPA,  in consultation with NYSDEC, may modify  the preferred
alternative  or select another response  action based  on  new
information or  public comments.  Therefore,  the  public  is
encouraged to  review and comment  on all of the alternatives
identified   herein.  Documentation of  the  project findings  is
presented in the Administrative Record File. These documents are
available at the:

          Town Hall
          Drawer A
          Huguenot, New York 12746
          (914) 856-2210

Comments on the  Proposed Plan will be  summarized  and re-
sponses provided in the Responsiveness Summary section of the
Record of Decision. The Record of Decision is the document that
presents EPA's  final  selection for response actions.  Written com-
ments on this Proposed Plan should be sent by close of business,
September 2, 1994 to:                         ,

          Sharon Trocher, Project Manager
          U.S. Environmental Protection Agency
          26 Federal Plaza, Room 29-100
          New York, New York 10278

-------
          Appendix C  .

       August  23, 1994
Public Meeting Attendance Sheet

-------
United States Environmental  Protection Agency
                   Region  II

                   Meeting

                    For
      Public Meeting for Carroll  & Dubies Superfund Site

                 August 11,  1994

                      7pm

              Please Print Clearly
NAME
STREET
CITY
                   Sign In Sheet
               ZIP
                                   PHONE
                           X7t"
n «•* VT- , 
-------
                         United States Environmental Protection Agency
                                            Region II

                                            Meeting

                                            For
                               Public Meeting  for Carroll t Duties  Superfund Bite

                                          August 11, 1994

                                              7pm

                                       Please  Print Clearly
LwbmifaAt
                                           Sign In Sheet
                                                 ZIP
PHONE

-------
                          ROD FACT SHEET
SITE

Site name:

Site location:

HRS score:

EPA ID #

ROD

Date signed:

Selected remedy:




Capital cost:

O & M cost:

Present worth cost:


LEAD

USEPA

EPA Primary Contact:
Carroll and Dubies Sewage Disposal Inc.

Town of Deerpark, Orange County,  New York

33 .74

NYD010968014



March 31, 1995

ex-situ vapor extraction, bioslurry,
stabilization/solidification and
placement into an on-site containment
cell

$ 8,105,000

$   430,000

$ 8,535,000
Sharon Trocher  (212) 264-8476
EPA Secondary Contact:  Doug Garbarini  (212) 264-0109
Main PRPs:



WASTE

Waste type:
Carroll and Dubies Sewage Inc., Kolmar
Laboratories, Wickhen Products,
Reynold Metals and City of Port Jervis
Volatile Organic Compounds
Inorganic Compounds
Waste origin:            Septic  and  Industrial Wastes

Estimated waste quantity:   20,300 cubic yards

Contaminated medium:     Soil  (OU-1)

-------