PB96-963819
                                 EPA/ROD/R02-96/286
                                 Janaury 1997
EPA  Superfund
       Record of Decision:
       Carroll and Dubies Sewage Disposal,
       Port Jervis, NY
       9/30/1996

-------
              DECLARATION FOR THE RECORD OF DECISION
SITE NAME AND LOCATION

Carroll and Dubies Sewage Disposal, Inc., Superfund Site
Town of Deerpark, Orange County, New York

STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action  for
the contaminated groundwater at the Carroll and Dubies Superfund
Site  (the Site), which was chosen in accordance with the
Comprehensive Environmental Response, Compensation, and Liability
Act (CERCLA) of 1980, as amended, and to the extent practicable,
the National Oil and Hazardous Substances Pollution Contingency
Plan  (NCP).   This decision document explains the factual and
legal bases for selecting the remedy for the contaminated
groundwater at this Site.  The information supporting this
remedial action decision is contained in the administrative
record for this Site.  The administrative record index is
attached  (Please see Appendix III).

The New York State Department of Environmental Conservation
(NYSDEC)  concurs with the selected remedy as per the attached
letter (Appendix IV).

ASSESSMENT OF THE SITE

Actual or threatened releases of hazardous substances from this
Site,  if not addressed by implementing the response action
selected in this Record of Decision (ROD),  may present an
imminent and substantial endangerment to public health, welfare,
or the environment.

DESCRIPTION OF THE SELECTED REMEDY

This operable unit represents the second of two operable units
planned for the Site.  It addresses the contaminated  groundwater
underlying and downgradient of the Carroll and Dubies site.  The
remedy for the first operable unit (OU1), involving the cleanup
of lagoon sludges and contamination in the soil in and around the

-------
 lagoons, was selected  in a ROD, signed March 31, 1995, and is
 presently in the design phase.

 The major components of the selected remedy include:

     Natural attenuation of organic contaminants in the
     groundwater to below federal drinking water and State
     groundwater standards through naturally occurring removal
     processes.  The remediation of the lagoons, which will be
     implemented under OU1, will minimize any additional
     contaminant contribution to the groundwater.  Groundwater
     modeling estimated that contaminants would attenuate to
     these standards within five years of completion of the
     remedy selected for the lagoons.

     Implementation of institutional controls,  such as deed
     restrictions, contractual agreements, local law or
     ordinances or other governmental action for the purpose of
     restricting installation and use of groundwater wells
     throughout the contaminated groundwater plume.

     Monitoring of the groundwater to evaluate improvement in
     groundwater quality and ensure the effectiveness of the
     remedy.

     Sampling in Gold  Creek to ensure that site related
     contaminants do not impact the creek.

STATUTORY DETERMINATIONS

The selected remedy is protective of human health and the
environment,  complies with federal and state requirements that
are legally applicable or relevant and appropriate to the
remedial action and is cost-effective.  The selected remedy
utilizes permanent solutions and alternative treatment
technologies to the maximum extent practicable for this Site.
However, the remedy does not satisfy the statutory preference for
treatment as a principal element of the remedy; naturally
occurring processes will be relied upon to reduce the mobility,
toxicity and volume of the contaminants in the groundwater.
Groundwater modeling has predicted that the natural attenuation
processes of the selected remedy will achieve drinking water and
groundwater standards  in approximately the same time frame as
active treatment alternatives.

-------
Since contaminants will remain at the Site above levels which
allow for unrestricted use and unlimited exposure,  this remedy
will require five-year reviews to ensure that the remedial action
is protective of human health and the environment.
Jeanne M. Fox//^7 /S'      I                    Date
             //•    .
Regional Administra

-------
              RECORD OF DECISION
               DECISION SUMMARY

      Carroll and Dubies  Superfund Site
               Town of Deerpark
           Orange County,  New York
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                  Region  II
              New York, New York
                 September 1996

-------
                         TABLE OF CONTENTS
                                                             PAGE
SITE NAME,  LOCATION AND DESCRIPTION 	  1

SITE HISTORY  AND ENFORCEMENT ACTIVITIES  	  2

HIGHLIGHTS  OF COMMUNITY PARTICIPATION 	 4

SCOPE AND ROLE OF OPERABLE UNIT	4

SUMMARY OF  SITE CHARACTERISTICS	  5

SUMMARY OF  SITE RISKS	10

REMEDIAL ACTION OBJECTIVES 	 16

DESCRIPTION OF REMEDIAL ALTERNATIVES 	   16

SUMMARY OF  COMPARATIVE  ANALYSIS OF ALTERNATIVES 	 21

SELECTED REMEDY 	 26

STATUTORY DETERMINATION 	 27

DOCUMENTATION OF SIGNIFICANT CHANGES 	   29


ATTACHMENTS

APPENDIX I.     FIGURES
APPENDIX II.    TABLES
APPENDIX III.   ADMINISTRATIVE RECORD INDEX
APPENDIX IV.    STATE LETTER OF CONCURRENCE
APPENDIX V.     RESPONSIVENESS SUMMARY

-------
SITE NAME, LOCATION AND DESCRIPTION

The Carroll & Dubies site (the Site)  is located just northeast of
the City of Port Jervis, on Canal Street in the Town of Deerpark,
Orange County, New York.  The Site is approximately 5.5 acres in
size  (see Figure 1).   The Site is occupied by an office building
and a garage.  The waste disposal areas at the Site include seven
lagoons, several automobiles from previous salvage operations
that have been abandoned, and numerous portable toilets that are
stored on-Site.

The northwest boundary of the Site is formed by the valley wall,
which consists of exposed bedrock with talus comprising the base.
The southeast boundary and a portion of the northeast boundary of
the Site is formed by remnants of the former Delaware and Hudson
Canal and towpath.  Adjacent to the southern boundary of the
Carroll and Dubies property is the City of Port Jervis Landfill  .
and gravel and cement block manufacturing operations.  The
landfill is no longer active; however, Orange County currently
operates a solid waste transfer station on a portion of the
landfill property. Approximately 1,500-feet to the east of the
Site is Gold Creek and its associated wetlands.  The Neversink
River is located approximately 2,000-feet beyond Gold Creek.
Gold Creek and the Neversink River drain into the Delaware River.
The nearest resident located downgradient of the Site is about a
quarter of a mile from the Site on the opposite side of Gold
Creek (see Figure 2).

The Site ranges from approximately 440 to 520 feet above mean
sea level.  The materials encountered underlying the Site consist
of glacially derived unconsolidated materials underlain by
consolidated bedrock.   The thickness of the unconsolidated
overburden materials ranges from zero feet at the exposed bedrock
slope forming the northwestern Site boundary, to over 60 feet
along the towpath.  The glacially derived materials consist of
two distinct units, including a glacial till unit overlain by
glacial outwash deposits.  The outwash deposit was observed to
vary in thickness from 31 feet to 52 feet along the downgradient
edge of the Site.  The outwash deposits typically consist of sand
with some clay, silt and gravel.  The glacial till deposits are
characterized as dense to very dense dark grey silt with sand and
gravel.   The glacial till is not continuous beneath the Site, and
appears to pinch out toward the northwestern edge of the Site,

-------
adjacent to the exposed bedrock slope.  The depth to groundwater
from ground surface ranges from approximately 30 to 40 feet along
the southeastern boundary of the Site.  Groundwater movement is
generally towards the southeast.

The major aquifer system used for potable water supply in Orange
County is comprised of the bedrock and the sand and gravel
deposits in the valley.  No residential wells have been found to
exist between the Site and Gold Creek.  However, approximately 90
residential wells exist downgradient of the Site between Gold
Creek and the Neversink River.  The nearest residence and
residential well is located approximately a quarter of a mile
downgradient of the Site.

SITE HISTORY AND ENFORCEMENT ACTIVITIES

From approximately 1970 to 1979, the Site was used for the
disposal of septic and municipal sewage sludge and industrial
wastes, primarily from the cosmetic industry.  The industrial
waste was deposited in seven lagoons located at the Site (lagoons
1 through 4 and 6 through 8 are depicted in Figure 2) .  No
industrial wastes were found in lagoon 5.   The dimensions of
lagoons 1,  2,  3, 4,  6, 7 and 8 are approximately 100 feet by 60
feet,  200 feet by 60 feet, 100 feet by 35 feet, 100 feet by 40
feet,  60 feet by 20 feet, 100 feet by 45 feet, and 150 feet by 40
feet,  respectively.

In 1978,  lagoon 3 was ignited by the Port Jervis Fire Department
in order to practice suppression of chemical fires.  After this
incident, lagoons 3 and 4 were filled in with soil and the area
was revegetated.  With the exception of lagoons 1 and 2, all of
the lagoons have been covered with soil.   Lagoons 1 and 2 were
left uncovered and are surrounded by a wooden fence.  In June
1979,  NYSDEC prohibited the disposal of industrial wastes at the
Site.   The Site continued to be used for the disposal of septic
and municipal sewage wastes until 1989.

In February 1987,  NYSDEC issued a Phase II Investigation Report
which summarized past investigations and included a Hazard
Ranking System  (HRS) score for the Site.   Based on the HRS score,
the Site was proposed for inclusion on the National Priorities
List (NPL)  in June 1988 and was placed on the NPL in February
1990.

-------
 On September 25, 1989, EPA sent "special notice"  letters to four
 potentially responsible parties (PRPs),  affording them the
 opportunity to conduct the RI/FS for the Site.   PRPs are
 companies or individuals who are potentially responsible for
 contributing to the contamination at the Site and/or are past  or
 present owners of the property.  The four PRPs  were Carroll and
 Dubies Sewage Disposal, Inc.  (C&D),  Kolmar Laboratories,  Inc.
 (Kolmar),  Wickhen Products,  Inc. (Wickhen)  and  Reynolds Metals
 Co.,  Inc.  (Reynolds) .   The PRPs were given 60 days in which to
 submit a good faith offer to undertake  or finance the RI/FS for
 the  Site.

 On November 30,  1989,  two PRPs, Kolmar  and Wickhen,  submitted  a
 good faith offer to perform the RI/FS..  An Administrative Order
 on Consent was signed by the  two PRPs and by EPA  in February
 1990.   Kolmar and Wickhen conducted  all  RI/FS work (addressing
 both the  groundwater and lagoons) , pursuant to  the RI/FS  Order
 with oversight by EPA.  During  the RI, EPA learned from the City
 of Port Jervis that it owned  a  major portion of the Site  property
 where  the  lagoons are  located.   In an April 22, 1993  letter, EPA
 notified  the City that it was also a PRP for the  Site.

 In March  1995,  EPA signed a Record of Decision  (ROD)  for  the
 first  operable unit (OU1)  which called for  the  excavation of
 approximately 20,000  cubic yards (cy) of contaminated material
 from the  lagoons and  soils in the vicinity  of the  lagoons.
 Materials  exceeding treatment levels will undergo  treatment via
 solidification/stabilization  (for inorganic contaminants)  and
 bioslurry  (for organic contaminants)  or  a combination of  the two
 treatment  processes.    All treated and untreated materials will
 be placed  on-site in a lined  and capped  cell with  leachate
 collection.

On May  19,  1995,  EPA issued "special notice" letters  to the PRPs
 requesting that  they submit a good faith offer  to  perform the
Remedial Design/Remedial  Action (RD/RA)  for OU1.   The  PRPs and
EPA were unable  to  reach  an agreement and thus,  on September 29,
1995, EPA  issued a  Unilateral Administrative Order to  C&D, Kolmar
and Wickhen  ordering them to  implement the  first operable unit
remedy.

-------
 On September 29,  1995,  EPA entered into a de -rininis Settlement
 ir. the  form  of  an Order on Consent with Reynolds regarding EPA's
 past response costs  for the Site, and Reynold's share of the OU1
 RD/RA Costs.  This settlement became effective on July IS, 1996.

 After issuance  of the ROD for OU2,  ail r.on-de •?.ir.ir?.is ?R?s will
 be offered the  opportunity to design and implement the selected
 OU2 remedy.   EPA  will offer Reynolds a ce mir.ir-.is settlement for
 OU2 costs.

 HIGHLIGHTS OF COMMUNITY PARTICIPATION

 The Second Operable Unit RI/F5 reports and the Proposed Plan for
 the contaminated  groundwater beneath the Site were released for
 public comment on August 28,  1996;  a notice announcing the
 availability  of these documents was mailed to the Site mailing
 list.   These  documents were made available to the public  in the
 administrative record file at the EPA-Region II  Document  Control
 Center,  290 Broadway, 18th floor, New York,  New  York 10007-1866
 and at  the Deerpark Town Hall,  Drawer A,  Huguenot,  New York.   A
 public  newspaper notice announcing  the availability of these
 documents was placed in The Times Herald Record  on  September  10,
 1996.   The public comment period was  held from August  28,  1996
 through  September 27,  1996.

 During  the public comment period, EPA  held  a  public  meeting to
 present  the RI/FS reports and  the Proposed  Plan,  answer
 questions,  and accept both oral  and written comments.  The  public
 meeting  was held in the  auditorium of  the  Port Jervis  High
 School,  Port  Jervis,  New York  on September  11, 1996. Responses  to
 comments  received at  the public  meeting  and to written comments
 received  during  the public comment period are included in the
 Responsiveness Summary (see Appendix V) .

 SCOPS AND  ROLE OF  OPERABLE UNIT

 Site remediation activities are  sometimes segregated into
 different  phases  or operable units,  so that remediation of
 different  environmental  media or areas of a site can proceed
 separately.   This  phased  approach results in an expeditious
remediation of the entire  site.  EPA has designated two operable
units for  the  Carroll  and  Dubies site as described below.

-------
*The first operable unit  (OU1) addresses the lagoon sludges and
contaminated soils from lagoons 1, 2, 3, 4, 6, 7, and 8, which
are contaminated primarily with heavy metals and volatile organic
compounds  (VOCs).  The ROD for OU1 was issued in March 1995 and
calls for the excavation of approximately 20,000 cubic yards  (cy)
of contaminated material from the lagoons and soils in the
vicinity of the lagoons.  Materials exceeding treatment levels
will undergo treatment via solidification/stabilization (for
inorganic contaminants) and bioslurry (for organic contaminants)
or a combination of the two treatment processes.   All treated
and untreated materials will be placed on-site in a lined and
capped cell with leachate collection.  This operable unit is
currently in the remedial design phase.

^Operable Unit 2 (OU2) addresses the contaminated groundwater
beneath and downgradient of the Carroll and Dubies site.  This is
the final operable unit and is the subject of this ROD.

SUMMARY OF SITE CHARACTERISTICS

The nature and extent of groundwater contamination found at the
Carroll and Dubies site was assessed through sampling of
groundwater, sediment in Gold Creek, residential wells and
through groundwater modeling and geophysical surveys.  A total of
34 monitoring wells was installed and four groundwater sampling
events were conducted during the investigation.

The geology under the Site consists of unconsolidated overburden
materials of glacial and glaciofluvial origin, which overlie
shale bedrock.  The thickness of the unconsolidated overburden
materials ranges from zero foot at the exposed bedrock slope
forming the northwestern Site boundary,  to over 60 feet along the
towpath.  The glacially derived materials consist of two distinct
units, including a glacial till unit overlain by glacial outwash
deposits.  The outwash deposit, which constitutes an aquifer,
ranges in thickness from 31 feet to 52 feet along the
downgradient edge of the Site.  The glacial till is not
continuous beneath the Site, and appears to pinch out toward the
northwestern edge of the Site, adjacent to the exposed bedrock
slope.  The till formation is defined as an aquitard, because it
consists of silt and clay, which typically have low permeability.

-------
The  till  formation  is underlain by shale bedrock. Groundwater
found  in  the bedrock can be developed and therefore the bedrock
is defined  as  an  aquifer.  The depth to groundwater from ground
surface ranged from approximately 30 to 40 feet along the
southeastern boundary of the Site.  Groundwater movement beneath
the  Site  is generally to the southeast, towards Gold Creek, which
is located  approximately 1,500 feet southeast of the Carroll and
Dubies property line (see Figure 2) .

Groundwater samples were collected downgradient of the lagoons
and  analyzed for  organic and inorganic compounds.  The monitoring
wells monitor  either the bedrock (well depths ranging from 39
feet to 86  feet below land surface) , the glacial till (well depth
at 60 feet  below  land surface) ,  the glacial outwash (well depths
ranging from 16 feet to 58 feet below land surface) or both the
glacial till and  outwash units (well depths ranging from 35 feet
to 51 feet  below  land surface) .   The analytical results for the
groundwater samples for the 1991,  1993, 1994, and 1995 sampling
events did  not  indicate the presence of organic contaminants
above federal  drinking water or State drinking water or
groundwater standards in any of the bedrock or glacial till
monitoring  wells.  No pesticides or PCBs were detected in any of
the groundwater samples collected from the Site.  The sampling
events did  show VOCs, semivolatile organic compounds (SVOC),  and
chlorinated organic compounds at concentrations exceeding federal
drinking water  and State groundwater and drinking water standards
in monitoring wells that are screened in the outwash and across
the outwash and till interface (see Table 1) . As a result two
plumes of total organic compounds exceeding 100 micrograms per
liter  (/KJ/L) or parts per billion (ppb) were defined (see Figure
3) .   One plume  originates at lagoons 1 and 2, the other at
lagoons 7 and  8.  The concentration of organics in the
groundwater decreases dramatically further downgradient of the
lagoons,  which  suggests that significant attenuation of
contaminants has occurred.   This has been simulated through
groundwater modeling conducted at the Site. The plumes are of
limited extent,  and have not extended far enough to impact Gold
Creek,  or to affect groundwater or the residential wells south of
Gold Creek.

The discussion below is intended to summarize groundwater results
for organic constituents by plume (i.e., results of samples
collected from monitoring wells in the plume downgradient from

-------
 lagoons  1-4  and  results  of  samples collected from monitoring
 wells  in  the plume downgradient of lagoons 6-8) .  The discussion
 focuses on the 1?94 and  1995 sampling results,  as these results
 indicate  the highest concentrations of organic contaminants and
 during these sampling events all wells in the monitoring network
 had been  installed (the  wells had been installed in phases).

 Groundwater Dowr.cradient of Lagoons 1-4

 During the 1994 sampling event,  four organic compounds,  benzene,
 1, 2-dichloroether.e, tetrachloroethene and trichloroethene were
 detected above the federal drinking water and/or State drinking
 water and groundwater standards  in the monitoring wells located
 downgradient of lagoons 1 through 4.   The highest concentrations
 of  the chlorinated organic compounds  were observed in shallow
 outwash well OW-2, located downgradient of lagoon 2.   Groundwater
 samples from monitoring well OW-2 detected 1,2-dichloroethene at
 130 ppb,  tetrachloroethene at 100 ppb,  and  trichloroethene at 24
 ppb.   The federal drinking water and  State drinking water
 standards for tetrachloroethene  and trichloroethene are  5 ppb;
 the State drinking water standard for 1,2-dichloroethene is 5
 ppb,  which is more stringent than the federal standard.   Benzene
 was observed  in shallow outwash  well  MW-4  at  15  ppb.   The State
 groundwater standard  for benzene is 0.7  ppb.  The 1995
 groundwater results detected organic  constituents at  similar
 concentrations  as those  detected during  the  1994  sampling event.

 Groundwater Downgradient  of  Laaoons 6-8

 Groundwater data  collected  in the  1995 sampling event, in  the
 vicinity of lagoons 7 and 8,  indicates that benzene is the
 primary organic contaminant  in the  plume originating  from  these
 lagoons.   During  the 1995 sampling  of monitoring  wells located
 downgradient  of lagoons  6, 7  and 8  (OW-9,  OW-10,  OW-ll,  OW-12,
 OW-13), benzene  (State grcundwater  standard of 0.7 ppb)  was
 detected in monitoring well  OW-9 at 900 ppb.  Monitoring well  OW-
 10,  which  is  located immediately downgradient of  lagoon  8,  had
 concentrations of  benzene at  2,600 ppb, xylene at 30 ppb (State
 drinking water standard of 5 ppb), and isophorone at 440 ppb
 (State drinking water standard of 10 ppb) .  Monitoring well OW-ll
 had concentrations of benzene at 970 ppb,  ethylbenzene at 30 ppb
 (State drinking water standard of 5 ppb),  xylene  at 51 ppb, and
naohthalene at 17  oob (State drinkinc water standard of  10 ocb).

-------
Benzene and phenol  (State drinking water standard of 1 ppb) were
detected at 2,400 ppb and 55 ppb, respectively, in monitoring
well OW-12.  Monitoring well OW-13 had concentrations of 1,2-
dichloroethene at 20 ppb, benzene at 350 ppb, and vinyl chloride
at 34 ppb  (State drinking water standard of 2 ppb).   The 1994
groundwater results detected organic constituents at similar
concentrations as those detected during the 1995 sampling event.

As previously stated, the concentrations of organics in
groundwater in the outwash aquifer decreased dramatically
downgradient from the lagoons in the 1994 and 1995 sampling
rounds.  In 1995, sampling data from the furthest downgradient
wells from the lagoons  (OW-17, OW-18, OW-19, and OW-23) only
indicated three organic compounds above the State drinking water
standards.  Benzene was detected at 12 ppb, chlorobenzene at 10
ppb and xylene at 29 ppb in monitoring well OW-18.  Benzene and
chlorobenzene were detected at 6 ppb and 8 ppb, respectively in
monitoring well OW-19.  No organic compounds were detected in
monitoring wells OW-17 and OW-23.

The discussion below is intended to summarize groundwater results
for inorganic constituents.  The discussion focuses on the 1994,
1995 and 1996 sampling results.

Inorganic sampling results for the September 1994 and April 1995
sampling events were contradictory, leading EPA to conduct
another round of groundwater samples in July 1996. Groundwater
samples collected in the 1994 sampling event were non-filtered
inorganic samples.  Although the results of the 1994 analyses
indicated the presence of inorganic compounds,  very few samples
indicated concentrations above federal drinking water and State
drinking water and groundwater standards. Monitoring well OW-19
detected arsenic at 28.9 ppb  (State groundwater standard of 25
ppb),  chromium was found in monitoring well OW-9 at 123 ppb
(State groundwater standard of 50 ppb),  antimony was found at 65
ppb (State groundwater standard of 3 ppb) in monitoring well OW-
23 .   For each of the inorganic compounds that exceeded their
respective criteria (arsenic, chromium and antimony) exceedances
occurred in only one sample out of the 32 samples collected.

Groundwater samples collected in the 1995 sampling event were
highly turbid.  These samples were filtered in the field.  The
results of the 1995 inorganic analyses indicated the presence of

                                8

-------
various inorganic constituents in the groundwater downgradient of
the lagoons above background concentrations. Several inorganic
constituents were detected at concentrations that exceeded the
federal drinking water and/or State drinking water and
groundwater standards.  Monitoring well OW-10 detected antimony
at 15 ppb  (State groundwater standard of 3 ppb) and nickel at 425
ppb (there is no drinking water standard for nickel at this
time), arsenic was detected at 105 ppb  (State groundwater
standard of 25 ppb) in monitoring well OW-20, chromium was
detected at 669 ppb (State groundwater standard of 50 ppb) in
monitoring well OW-13, and lead was detected at 283 ppb  (federal
drinking water action level of 15 ppb) in monitoring well OW-9.

Due to the inconsistency between the 1994 and 1995 sampling
results for inorganic constituents,  EPA conducted another
sampling event for inorganic constituents in July 1996.  It was
suspected that the high concentrations of inorganics detected in
1995 may have been an artifact of highly turbid samples resulting
from the sampling protocols used at that time.  Because of this,
the July 1996 groundwater samples were collected via a low-flow
pump,  and these samples were not filtered.  Also, during sample
collection, the presence of high turbidity in some of the samples
was observed, an indication that the filter pack around the
screen zone had become filled with fine particles from the
geologic formation. Therefore some monitoring wells were
re-developed prior to collecting the groundwater samples.  The
results of this sampling event only indicated the presence of
inorganic compounds in three samples.  Chromium was detected in
monitoring well OW-9 at 70 ppb (State groundwater standard of 50
ppb),  arsenic was detected at 43 ppb and 37 ppb  (State
groundwater standard of 25 ppb)  in monitoring wells OW-19 and OW-
18, respectively.

The levels of inorganics detected in the 1995 samples tend to
directly depend on the amount of suspended sediment (turbidity)
in the samples.   Since the excessive turbidity present in the
1995 groundwater samples is believed to be both an artifact of
sampling and clogging of the filter pack in the wells,  these
higher levels are not representative of true Site conditions in
the aquifer.   Therefore,  the results of the groundwater data
suggests that the inorganic compounds found in the groundwater
beneath the Site are likely present at naturally occurring
levels.  As the potential for inorganic compounds to be present

-------
in groundwater at concentrations above naturally occurring levels
due to leaching  from the lagoon sediments is low, the potential
for these inorganic compounds to subsequently discharge with
groundwater to Gold Creek is also low.  It should be noted that
the results from the 1994 sampling event for inorganic
constituents were included in the risk assessment (see Summary of
Site Risks below).

Sediment samples were collected from two locations in Gold Creek
south of the Site.  These samples were collected in September
1994 and analyzed for organic and inorganic compounds.  The
analytical results of the sampling indicate that Site related
contaminants have not impacted Gold Creek.

As part of the RI, groundwater modeling was conducted to
determine whether the organic contaminant patterns found in the
groundwater beneath the Site have stabilized due to intrinsic
biodegradation and to estimate future concentrations of
contaminants at  potential off-site locations.   The results of the
groundwater modeling indicate that the organic contaminants in
the groundwater  are not migrating to Gold Creek and that the
concentration patterns observed at the Site have stabilized or
are not expected to change in the future.   Thus, contaminants in
the groundwater  beneath the Site are not expected to reach Gold
Creek or off-site residences in the future.

Also,  as part of the RI,  limited data was collected to evaluate
the extent of biodegradation at the Site.   This limited
evaluation included the collection of dissolved oxygen and the
presence of microorganisms in the groundwater capable of
degrading volatile organic compounds under expected Site
conditions.   The dissolved oxygen levels in the benzene plume
indicated the potential for biodegradation to be occurring; the
degrading microorganisms population was in the range of 10s to
106, indicating  a healthy and robust  community  of  degraders
present in the aquifer.  Therefore,  the limited field data
combined with the groundwater modeling projections demonstrate
the potential for biodegradation of organic contaminants at the
Site.   The groundwater modeling results estimated that
contaminants will attenuate to levels below State and Federal
drinking water standards within five years after completion of
the OU1 remedy.
                               10

-------
The City of Port Jervis is served by a municipal water supply
that relies on three hydraulically-upgradient reservoirs as water
sources.  Outside of the City limits, private supply wells
provide drinking water.  It should be noted that the New York
State Department of Health (NYSDOH) sampled several wells located
downgradient of the Site while the RI/FS was being conducted.
Several private wells were sampled in 1991 and again in 1993 for
organic and inorganic constituents.  Organic constituents were
not detected in the groundwater from these wells, and inorganic
constituents were detected below drinking water standards.
Subsequently, in September 1994 and March 1995,  NYSDOH sampled
and analyzed a total of ten private wells in the area for
volatile organic compounds.  The wells were located along Andrew
Drive, Evergreen Lane, Mark Drive, Michael Drive, Van Avenue, and
NY Route 209.  The results indicate that no volatile organic
compounds were detected in any of the wells sampled.

SUMMARY OF SITE RISKS

EPA conducted a baseline risk assessment to evaluate the
potential risks to human health and the environment associated
with the Site groundwater under current and future conditions.
The Risk Assessment focused on contaminants in the groundwater at
the Site, which are likely to pose significant risks to human
health and the environment, if no remedial action were taken.

Human Health Risk Assessment

As part of the baseline risk assessment, the following four-step
process is utilized for assessing site-related human health risks
for a reasonable maximum exposure scenario:   Hazard
Identification--identifies the contaminants of concern at the
site based on several factors such as toxicity,  frequency of
occurrence,  and concentration. Exposure Assessment--estimates the
magnitude of actual and/or potential human exposures,  the
frequency and duration of these exposures, and the pathway  (e.g,
ingesting contaminated well-water) by which humans are
potentially exposed.   Toxicity Assessment--determines the types
of adverse health effects associated with chemical exposures, and
the relationship between magnitude of exposure (dose)  and
severity of adverse effects (response).   Risk Characterization--
summarizes and combines outputs of the exposure and toxicity
assessments to provide a quantitative (e.g.,  one-in-a-million

                                11

-------
excess cancer risk) assessment of site-related risks.

The baseline risk assessment began with the selection of
contaminants of concern.  A summary of the contaminants of
concern detected in the groundwater is provided in Table 2.
These contaminants included the organic contaminants benzene,
chloroform, 1,2-dichlorobenzene, tetrachloroethene, toluene,
vinyl chloride, xylene, phenol, and the inorganic contaminants
arsenic, antimony, barium, chromium, lead, and zinc.  The organic
contaminants were present in monitoring wells close to the
lagoons at levels which exceeded State and Federal drinking water
standards and State groundwater standards.

EPA's baseline risk assessment addressed the potential risks to
human health by identifying several potential exposure pathways
by which the public may be exposed to contaminant releases at the
Site under current and future land-use conditions. Table 3
provides the potential exposure pathways for current and future
land-use scenarios evaluated in the risk assessment.

There are no current on-site groundwater users at the S-ite,
therefore there are no potential current receptors at the Site.
Potential off-site receptors included residents to the east and
southeast of Gold Creek who use groundwater as drinking water and
recreational users of Gold Creek.  Groundwater modeling,  in
conjunction with measured groundwater concentrations, sediment
data from Gold Creek and groundwater concentrations from off-site
residential wells, indicates that the plumes have stabilized and
that contaminants have not migrated either to Gold Creek or to
off-site residences on the other side of Gold Creek, nor are they
expected to migrate to or beyond Gold Creek in the future.  Thus,
current exposures to either off-site residents or recreational
users of Gold Creek are not occurring and are not expected to
occur in the future.   These exposure pathways therefore,  were not
quantitatively evaluated in the risk assessment.

The Site and land immediately adjacent to the Site are currently
zoned exclusively for industrial land use; the Site is surrounded
by a sheer rock cliff, the City of Port Jervis Landfill and
gravel and cement block manufacturing operations.  Therefore,
future residential or commercial use of the Site is not expected
to occur and industrial use of the Site was the only use
evaluated in the risk assessment.

                                12

-------
EPA was concerned that industrial workers at the Site could be
exposed to contaminants in the groundwater and evaluated these
potential exposures in the risk assessment.  The baseline risk
assessment considered the potential health effects for industrial
workers that could result from incidental ingestion of
contaminated groundwater from the on-site aquifer.

Under, current EPA guidelines, the likelihood of carcinogenic
(cancer-causing) and non-carcinogenic health effects due to
exposure to Site chemicals are considered separately.  It was
assumed that the toxic effects of the Site-related chemicals
would be additive.  Thus, carcinogenic risks and non-carcinogenic
health effects associated with exposures to individual compounds
of concern were summed to indicate the potential risks associated
with mixtures of potential carcinogens and non-carcinogens,
respectively.

Potential carcinogenic risks were evaluated using the cancer
slope factors developed by EPA for the contaminants of concern.
Cancer slope factors (SFs) have been developed by EPA's
Carcinogenic Risk Assessment Verification Endeavor (an Inter-
agency workgroup of scientists with expertise in carcinogens) for
estimating excess lifetime cancer risks associated with exposure
to potentially carcinogenic chemicals.  SFs, which are expressed
in units of  (mg/kg-day) "1, are multiplied by the estimated intake
of a potential carcinogen, in mg/kg-day, to generate an upper-
bound estimate of the excess lifetime cancer risk associated with
exposure to the compound at that intake level.  The term "upper
bound" reflects the conservative estimate of the risks calculated
from the SF.  Use of this approach makes the underestimation of
the risk highly unlikely.  The SF for the compounds of concern
are presented in Table 4  (see column identified as cancer slope
factor).

For known or suspected carcinogens,  EPA considers excess upper-
bound individual lifetime cancer risks in the range of 10'4 to
10'6 to be acceptable.  This level indicates that an individual
has not greater than a one in ten thousand to one in a million
chance of developing cancer as a result of Site-related exposure
to a carcinogen over a 70-year period under specific exposure
conditions at the Site.  As noted above, under the current Site
                                13

-------
conditions, there are no current on-site groundwater users at the
Site, therefore there are no potential current receptors at the
Site.  Evaluation of risks to potential future industrial workers
was 1.4 x 10'4  (approximately one-in-ten thousand) which is
considered to be within the.U.S. EPA target risk range of 10~4  to
10"6.  The main contributors to  the total cancer risk were
arsenic, vinyl chloride, and benzene through ingestion of
groundwater.  A summary of the carcinogenic risks associated with
the chemicals for a potential future industrial worker drinking
contaminated groundwater is found in Table 5.

Non-carcinogenic health effects were assessed using a hazard
index (HI) approach, based on a comparison of expected
contaminant intakes and safe levels of intake (Reference Doses) .
Reference doses (RfDs) have been developed by EPA for indicating
the potential for adverse health effects.   RfDs,  which are
expressed in units of milligrams/kilogram-day (mg/kg-day),  are
estimates of daily exposure levels for humans which are thought
to be safe over a lifetime (including sensitive individuals).
Estimated intakes of chemicals from environmental media (the
amount of a chemical ingested from contaminated drinking water)
are compared to the RfD to derive the hazard quotient for the
contaminant in the particular medium.  The HI is obtained by
adding the hazard quotients for all compounds across all media
that impact a particular receptor population.

An HI greater than 1.0 indicates that the potential exists for
non-carcinogenic health effects to occur as a result of site-
related exposures.  The HI provides a useful reference point for
gauging the potential significance of multiple contaminant
exposures within a single medium or across media.   The reference
doses for the compounds of concern at the Site are presented in
Table 4.

The calculated HI value, which reflects non-carcinogenic effects,
was estimated to be 0.55 which is below the acceptable level of
1.0 indicating no adverse health effects to future industrial
workers.  The main contributor to the total noncancer risk was
arsenic through ingestion of drinking water.  A summary of the
non-carcinogenic risks associated with the chemicals for a
potential future industrial worker drinking contaminated
groundwater is found in Table 5.
                                14

-------
Ecological Risk Assessment

There are no impacts to ecological receptors in Gold Creek, since
contaminants in groundwater have not migrated to Gold Creek and
are not anticipated to migrate there in the future.

Uncertainties

The procedures and inputs used to assess risks in this
evaluation, as in all such assessments, are subject to a wide
variety of uncertainties.  In general, the main sources of
uncertainty include:

•    environmental chemistry sampling and analysis
•    environmental parameter measurement
•    fate and transport modeling
•    exposure parameter estimation
•    toxicological data.

Uncertainty in environmental sampling arises in part from the
potentially uneven distribution of chemicals in the media
sampled.  Consequently, there is significant uncertainty as to
the actual levels present.  Environmental chemistry-analysis
error can stem from several sources including the errors inherent
in the analytical methods and characteristics of the matrix being
sampled.

Uncertainties in the exposure assessment are related to estimates
of how often an individual would actually come in contact with
the chemicals of concern, the period of time over which such
exposure would occur,  and in the models used to estimate the
concentrations of the chemicals of concern at the point of
exposure.

Uncertainties in toxicological data occur in extrapolating both
from animals to humans and from high to low doses of exposure, as
well as from the difficulties in assessing the toxicity of a
mixture of chemicals and the availability of toxicity data for
all chemicals of concern.  These uncertainties are addressed by
making conservative assumptions concerning risk and exposure
parameters throughout the assessment.  As a result, the Risk
Assessment provides upper-bound estimates of the risks to
populations near the Site, and is highly unlikely to

                                15

-------
underestimate actual risks related to the Site.

More specific information concerning public health risks,
including a quantitative evaluation of the degree of risk
associated with various exposure pathways, is presented in the
Risk Assessment Report.
Actual or threatened releases of hazardous substances from this
Site, if not addressed by implementing the response action
selected- in the ROD, may present an imminent and substantial
endangerment to the public health, welfare, or the environment.

REMEDIAL ACTION OBJECTIVES

Remedial action objectives are. specific goals to protect human
health and the environment.  These objectives are based on
available information and standards such as applicable or
relevant and appropriate requirements (ARARs)  and risk-based
levels established in the risk assessment.

The remedial action objective for the groundwater beneath the
Site is to reduce or eliminate potential health risks associated
with ingestion of Site contaminated groundwater by potential
future industrial workers and to reduce the concentration of
contaminants in the groundwater to drinking water standards.

DESCRIPTION OF REMEDIAL ALTERNATIVES

CERCLA requires that each selected site remedy be protective of
human health and the environment, be cost effective,  comply with
federal and state requirements that are legally applicable or
relevant and appropriate,  and utilize permanent solutions and
alternative technologies and resource recovery alternatives to
the maximum extent practicable.  In addition,  the statute
includes a preference for the use of treatment as a principal
element for the reduction of toxicity,  mobility,  or volume of the
hazardous substances.

This ROD evaluates in detail four remedial alternatives for
addressing the contaminated groundwater beneath the Carroll and
Dubies Sewage Disposal Inc.,  Site.  Since each alternative would
still result in contaminants remaining at the Site above levels
which allow for unrestricted use and unlimited exposure, each
alternative would require five-year reviews to ensure that the

                                16

-------
remedial action is protective of human health and the
environment.  Five-year reviews are currently required as part of
OU1.  As used in the following text, the time to implement a
remedial alternative reflects only the time required to construct
or  implement the remedy and does not include the time required to
design the remedy, negotiate with the responsible parties, or
procure contracts for design and construction, or conduct
operation and maintenance at the Site.

Alternative 1:  No Action

Capital Cost:           $ 0
O & M/yr Cost:         $ 0
Present Worth:         $ 0
Time to Implement:     0 months

The Superfund program requires that the "no-action" alternative
be considered as a baseline for comparison with other
alternatives.  As demonstrated through the results of the
groundwater modeling study, naturally occurring processes for
reducing the concentration of contaminants in the groundwater are
at work at the Site.  Under this alternative, no action would be
taken to address the contaminated groundwater.  There would be no
monitoring of these naturally occurring processes in the
groundwater to evaluate the rate and extent of the reduction and
mobilization of contaminants in the groundwater beneath the Site.
The period for the groundwater to reach federal drinking water
and State drinking and groundwater standards was projected
through the groundwater modeling to be approximately five years
after the implementation of the OU1 remedy.  The remediation of
the lagoons, which will be implemented under OU1, would'minimize
any additional contaminant contribution to the groundwater.

Alternative 2: Natural Attenuation with Institutional Controls
and Monitoring

Capital cost:           $ 0
0 & M/yr Cost:  -       $  58,000
Present Worth:         $ 284,000
Time to Implement:     6 months

Similar to Alternative 1,  Alternative 2 would also rely on
natural attenuation, with intrinsic biodegradation as a principal

                                17

-------
mechanism,  to  reduce  contaminants in the groundwater to drinking
water  standards.   The remediation of the lagoons and the
contaminated soils, which will be implemented under OU1, would
minimize any additional  contaminant contribution to the
groundwater.   This alternative includes the implementation of
institutional  controls,  such as deed restrictions, contractual
agreements, local  law or ordinances or other governmental action
for the purpose of restricting installation and use of
groundwater wells  throughout the contaminated groundwater plume.
These  restrictions would complement any restrictions implemented
as part of  the OU1 remedy.  Institutional controls restricting
the use of  Site groundwater would be required until the
groundwater has been  demonstrated to meet federal drinking water
and State groundwater and drinking water standards.   Groundwater
modeling projected that  intrinsic biodegradation and flushing
mechanisms  would reduce  the concentration of contaminants in the
groundwater to levels below drinking water standards within five
years  of the completion  of the GUI remediation.   Once these
levels have been demonstrated to be met,  the restrictions on
groundwater use would no longer be required.  Groundwater
monitoring  at  the  Site and sampling in Gold Creek would also be
conducted.

This alternative includes a component of initial assessment of
the groundwater parameters which favor natural attenuation and a
groundwater monitoring requirement to evaluate the rate and
extent of reduction of the organic contaminants  in the
groundwater.   The  initial assessment would include an evaluation
for the presence of constituent-degrading microorganisms,  pH,
oxygen or other electron acceptors,  elemental nitrogen,
phosphorous and other parameters necessary to evaluate the
progress of natural attenuation.   Groundwater monitoring would be
conducted on a semiannual basis.

Alternative 3: Groundwater Pump and Treat via Precipitation,
Filtration  and Carbon Adsorption

Capital Cost:        $  1,070,000
O & M/yr Cost:      $    287,200
Present Worth:      $ 2,105,000
Time to Implement:     9 months

This alternative would consist of a series of recovery wells used

                               18

-------
to capture contaminated groundwater immediately downgradient of
the source areas or the lagoons.  The recovery wells would
capture the most concentrated portion of  the contaminant plume
emanating from the source areas.  Any impacted groundwater that
would not be captured by the recovery wells would be .naturally
attenuated.  This alternative would eliminate the potential for
migration of organic contaminants off site.  The recovery wells
would be located in that portion of the outwash aquifer located
downgradient of the towpath.  Beneath the lagoons, a saturated
outwash unit does not exist.

The preliminary configuration of the treatment system assumes
that approximately six wells would be used to pump groundwater at
controlled rates to capture the impacted groundwater.  Two sets
of three pumping wells, each pumping at a rate of 5 gallons per
minute  (gpm), would be used.  The total pumping rate of the six
wells is 30 gpm.  One set of wells would be located between 100
feet to 150 feet downgradient of  lagoon 8. This set of three
wells would be designed to capture impacted groundwater passing
beneath lagoons 6, 7, and 8.  One set of wells would be located
between 100 feet to 125 feet downgradient of lagoons 1 and 2.
This set of three wells would be designed to capture impacted
groundwater passing beneath lagoons 1 and 2.  The recovered
groundwater would be treated on-site through a series of
treatment processes.  Conceptually, the treatment system would
consist of iron and suspended solids removal via precipitation
followed by filtration and carbon adsorption.  Following
treatment,  the groundwater would be discharged to Gold Creek in
accordance with the State Pollutant Discharge Elimination System
(SPDES)  requirements.  Residuals generated from the treatment
processes would be managed in accordance with the Resource
Conservation and Recovery Act (RCRA)  regulations.

This alternative would also include groundwater monitoring to
measure the effectiveness of the pump-and-treat system,  as well
as the institutional controls specified in.Alternative 2.  The
treatment system would be operated until contaminant levels in
the groundwater reach federal drinking water and State drinking
water and groundwater standards, which has been estimated to be
approximately five years after implementation of the remedy for
the lagoons.
                                19

-------
Alternative 4: In Situ Groundwater Treatment

Capital Cost:       $ 1,017,000
O & M/yr Cost:      $   248,000
Present Worth:      $  1,912,787
Time to Implement:     12 months

This alternative involves the injection of air into the saturated
zone (i.e., below the water table), via a series of wells, to
reduce the volatile constituents dissolved in groundwater. These
wells would be located in the same general vicinity as the
pumping wells outlined in Alternative 3, thus allowing treatment
of the most concentrated portion of the groundwater plumes.  Any
impacted groundwater that would not be captured by the in situ
groundwater treatment system would be naturally attenuated.  The
levels of organic constituents would be decreased in the
saturated zone during aquifer aeration via mass transfer of the
chemicals from the water phase to the gaseous phase.  If the
levels of organic compounds exceed air quality guidelines, then a
soil venting system would be installed in the subsurface to
collect the air emissions.  The exhaust air from the vapor
extraction system would be discharged to a treatment system.  The
gaseous treatment system for this alternative would be an
activated carbon filter.   Groundwater monitoring would also be
conducted as part of this alternative to evaluate the
effectiveness of the air sparging system.  A reduction in the
levels of organics may also take place in the saturated zone
through the enhancement of biodegradation due to the increase in
oxygen.  With this alternative,  air sparging ma'y be used in
conjunction with vacuum extraction and/or enhanced bioremediation
with the addition of nutrients.

A preliminary configuration of the aquifer aeration system would
consist of approximately 30 air sparging wells.  This alternative
would include the same monitoring program and institutional
controls described in Alternative 3.   Treatment of the
groundwater would continue until contaminant levels in the
groundwater achieve federal drinking water and State drinking
water and groundwater standards.  This alternative would achieve
groundwater remediation goals within about five years after
implementation of the remedy for the lagoons.
                               20

-------
 SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

 During the detailed evaluation of remedial alternatives,  each
 alternative was assessed utilizing nine evaluation criteria as
 set forth in the National Contingency Plan,  40  C.F.R.
 §300.430 (e) (9) (iii) and the Office of Solid Waste  and  Emergency
 Response (OSWER) Directive 9355.3-01.  These criteria  were
 developed to address the requirements of Section 121 of  CERCLA,
 42  U.S.C.  §9621 to ensure all important considerations are
 factored into remedy selection decisions.

 The following "threshold" criteria are the most important,  and
 must be satisfied by any alternative  in order to be eligible for
 selection:

 1.   Overall  protection of human  health and  the environment
     addresses  whether or not a remedy provides adequate
     protection and describes how risks posed through  each
     exposure pathway (based on a reasonable  maximum exposure
     scenario)  are eliminated,  reduced,  or controlled  through
     treatment,  engineering controls,  or institutional controls.

 2.   Compliance  with Applicable or Relevant  and Appropriate
     Requirements  addresses whether or not a  remedy would  meet
     all of the  applicable,  or relevant  and appropriate
     requirements  of federal and  state statutes and requirements
     or provide  grounds  for invoking  a waiver.

The  following "primary balancing"  criteria are used to make
comparisons and  to identify the major  trade-offs between
alternatives:

3.   Long-term effectiveness  and permanence refers to the  ability
     of a remedy to  maintain  reliable protection of human  health
     and the  environment  over time, once cleanup goals have been
     met.  It also addresses  the magnitude and effectiveness of
     the measures  that may  be  required to manage the risk posed
     by treatment  residuals and/or untreated wastes.

4.    Reduction of  toxicitv. mobility,  or volume through treatment
     is the anticipated performance of a remedial  technology,
     with respect  to these parameters, that a remedy may employ.
                                21

-------
 5.   Short-term effectiveness addresses the period of time needed
      to achieve protection and any adverse impacts on human
      health and the environment that may be posed during the
      construction and implementation periods until cleanup goals
      are achieved.

 6.    Implementability is the technical and administrative
      feasibility of a remedy,  including the availability of
      materials and services needed.

 7.    Cost  includes estimated capital and operation and
      maintenance costs,  and the present worth costs.

 The following "modifying"  criteria are considered fully after the
 formal  public comment period on the  Proposed Plan is  complete:

 8.    State  acceptance indicates whether,  based on its review of
      the RI/FS and the Proposed Plan,  the State supports,
      opposes,  and/or has identified  any reservations  with the
      preferred alternative.

 9.    Community, acceptance  refers to  the public's  general  response
      to the alternatives described in  the Proposed Plan and the
      RI/FS reports.   Factors of community acceptance  to be
      discussed include support, reservation,  and  opposition by
      the community.

A comparative  analysis of  the remedial  alternatives based upon
the above evaluation criteria follows.

Overall Protection of  Human Health and  the Environment

For No Action  (Alternative 1) and Natural Attenuation with
Institutional -Controls and Monitoring  (Alternative 2), the
concentration  of contaminants in the groundwater would be reduced
due to natural attenuation of contaminants until  federal drinking
water and State drinking and groundwater  standards are met.   This
period has been estimated to be approximately  five years from
implementation of the  OU1 remedy.  The No Action alternative
would present a slightly greater risk to human health and the
environment than Alternatives 2, 3, and 4 in the short-term
because the potential  would exist that an on-site worker could
come in contact with the contaminated groundwater.  Under

                                22

-------
Alternative 2, protection of human health would be enhanced with
the implementation of institutional controls, preventing the use
of the contaminated groundwater.

For the Pump-and-Treat  (Alternative 3) and In Situ Groundwater
Treatment  (Alternative 4) scenarios, the potential risks to human
health from potential exposure to impacted groundwater would be
reduced by removal and treatment of contaminants in the
groundwater captured by the remedial systems. These alternatives
would achieve groundwater remedial goals within about five years
of the implementation of OU1.  Institutional controls preventing
the use of Site groundwater would eliminate the potential
exposure to contaminated groundwater while the groundwater is
being remediated.  The contaminants would continue to migrate
until attenuated under Alternatives 1 and 2.  However, impacts
are expected to be minimal since, as noted in the risk assessment
section,  the levels of contaminants in the groundwater present no
significant human health risk under current or future uses.
Furthermore, impacts to ecological receptors in Gold Creek from
the implementation of all the remedial alternatives would be
unlikely since contaminants in groundwater have not migrated to
Gold Creek and are not anticipated to migrate there in the
future.

Compliance with ARARs

Actions taken at any Superfund site must meet all ARARs of
federal and state law or provide grounds for waiving these
requirements.   All of the alternatives have been designed to
achieve or comply with the ARARs.

Since the groundwater at the Site is a future potential source of
drinking water, federal drinking water standards (Maximum
Contaminant Levels [MCLs])  and New York State Drinking Water
Standards and New York State Groundwater Quality Standards are
ARARs.  For  No Action  (Alternative 1) and Natural Attenuation
with Institutional Controls and Monitoring (Alternative 2),
federal drinking water and State drinking water and groundwater
standards would be achieved over time through natural
biodegradation of organic contaminants in the groundwater.  The
period for the groundwater to reach federal drinking water and
State drinking and groundwater standards was projected through
groundwater modeling to be approximately five years from

                                23

-------
 implementation of  the OU1 remedy.  For the Pump-and-Treat
 (Alternative 3) and  In Situ Groundwater Treatment (Alternative 4)
 scenarios, groundwater standards would be met by removal and
 treatment of contaminants in the groundwater.  The discharge of
 treated groundwater  to Gold Creek during implementation of
 Alternative 3 would  comply with the Federal Clean Water Act arid
 State Pollutant Discharge Elimination System (SPDES)  regulations.
 The residual sludges from the treatment system under  Alternative
 3  would be treated or disposed of off-site in accordance with
 RCRA regulations.   The spent carbon generated from the
 groundwater treatment system under Alternative 3  and  the gas
 treatment system under Alternative 4 would either be  regenerated
 off-site or sent off-site for treatment and disposal  in
 accordance with RCRA regulations.   As with Alternatives 1 and 2,
 federal drinking water and State drinking water and groundwater
 standards are expected to be achieved with Alternatives 3 and 4
 within slightly less than five years after implementation of the
 OU1 remedy.

 Long-Term Effectiveness  and Permanence

 With all four alternatives,  within approximately  five  years  of
 the implementation of OU1 remedy,  the  concentrations of
 contaminants  in the groundwater are  expected  to be permanently
 reduced to levels  below ARARs.   Implementation of Alternatives  3
 and 4  might result in a slightly reduced  time  frame to achieve
 ARARs  downgradient of the lagoons.   Therefore, all alternatives
 are relatively  similar in terms  of  this criterion.

 Reduction  of  Toxicity, Mobility, and Volume through Treatment

 Alternatives  1  and 2  rely solely on  naturally occurring
 mechanisms to reduce  the  toxicity and volume of contaminants in
 the  groundwater, and  therefore do not satisfy the CERCLA
 preference for  treatment  to  reduce toxicity, mobility,  and volume
 of  contaminants.   Under Alternatives 3 and 4, treatment to reduce
 contaminants  in the groundwater  would be achieved by extraction
 of  the contaminants and subsequent treatment.  Alternatives 3 and
 4 are similar in their abilities to  reduce toxicity, mobility and
volume and would provide  reduction of toxicity, mobility  and
volume somewhat more  rapidly than Alternatives 1 and 2.
                                24

-------
 Short-Term Effectiveness

 Alternatives 1 and 2 would have no adverse effects at all on the
 community, site workers, or the environment since there would be
 no potential exposure to any of the contaminants because no
 construction activities would occur.   Alternative 2 includes
. Institutional controls preventing the use of Site groundwater,
 which would minimized impacts during implementation until cleanup
 goals are achieved. However,  Alternatives 3 and 4 would present
 greater impacts than Alternatives 1 and 2,  due to construction
 activities.   For example,  the construction of extraction wells
 and piping to transport the created groundwater to Gold.Creek
 would have minor negative impacts on residents and workers in the
 area.  These impacts would be associated with the disruption of
 traffic,-excavation on public and private land,  and noise and
 fugitive  dust emissions.  Appropriate measures,  however,  would  be
 implemented to minimize these impacts.

 Implamentability

 Alternative  1 -  No Action is  clearly  the most implementable.
 Alternative  2 would require groundwater-use restrictions  to
 prevent the  use  of groundwater wells  throughout  the contaminated
 aquifer;  although sometimes difficult to obtain,  these
 restrictions  are being used at numerous  sites.   Alternative  2
 would also require additional geochemical and intrinsic
 biodegradation studies and monitoring.   These studies and
 monitoring requirements  are being implemented at numerous sites.
 Alternatives  3 and 4  would be more  difficult  to  implement due to
 construction  requirements.  Additionally, Alternative 3 would
 require that  access be obtained to  construct  the piping to
 transport  the treated groundwater to  Gold Creek;  authorization  to
 discharge  treated water  to Gold Creek would add  to  the complexity
 of  implementing  this  remedy.   Nonetheless,  these are successfully
 proven  technologies at  the field  scale and  considered to  be
 readily implementable.

 Cost

 There is. no cost  associated with  the No Action alternative.
Alternative 2, Natural Attenuation with  Institutional Controls
 and Monitoring,  is the next lowest cost alternative with  a

                                25

-------
present worth of $284,000; there is no capital cost associated
with this alternative.  Alternative 3, Groundwater Pump and
Treat, has the highest cost with a present worth and capital cost
of $2,105,000 and $1,070,000, respectively.  Alternative 4, In
Situ Groundwater Treatment, with a present worth and capital cost
of $1,912,787 and $1,017,000, respectively, is slightly less than
Alternative 3.

State Acceptance

The State of New York, through the NYSDEC, concurs with EPA's
selected remedy.  The NYSDEC's letter of concurrence is attached
as Appendix IV.

Community Acceptance

Community acceptance of the preferred remedy has been assessed in
the Responsiveness Summary portion of this ROD following review
of all public comments received on the RI/FS report and the
Proposed Plan.   All comments submitted during the public comment
period were evaluated and are addressed in the attached
Responsiveness  Summary (Appendix V) .   In general, the public is
supportive of EPA's preferred remedy.

SELECTED REMEDY

EPA has determined,  after reviewing the alternatives and public
comments,  that  Alternative 2 is the appropriate remedy for the
groundwater beneath and downgradient  of the Site, because it best
satisfies the requirements of CERCLA and the NCP's nine
evaluation criteria for remedial alternatives.

The major components of the selected remedy are as follows:

     Natural attenuation of organic contaminants in the
     groundwater to below federal drinking water and State
     groundwater standards through naturally occurring removal
     processes.  The remediation of the lagoons,  which will be
     implemented under OU1, will minimize any additional
     contaminant contribution to the  groundwater.  Groundwater
     modeling estimated that contaminants would attenuate to
     these standards within five years of completion of the
     remedy selected for OU1.

                                26

-------
     Implementation of institutional controls, such as deed
     restrictions, contractual agreements, local law or
     ordinances or other governmental action for the purpose of
     restricting installation and use of groundwater wells
     throughout the contaminated groundwater plume.

     Monitoring of the groundwater to evaluate improvement in
     groundwater quality and ensure the effectiveness of the
     remedy.

     Sampling in Gold Creek to ensure that site related
     contaminants do not impact the creek.

STATUTORY DETERMINATIONS

Under Section 121 of CERCLA, EPA's primary responsibility at
Superfund sites is to undertake remedial actions that are
protective of human health and the environment, and complies with
federal and State requirements that are legally applicable or
relevant and appropriate unless a statutory waiver is justified.
The selected remedy also must be cost-effective and utilize
permanent solutions and alternative treatment technologies or
resource-recovery technologies to the maximum extent practicable.
Finally, the  statute includes a preference for remedies that
employ treatment that permanently and significantly reduces the
volume, toxicity,  or mobility of hazardous substances.  The
following sections discuss whether and how the selected remedy
meets these statutory requirements.

Protection of Human Health and the Environment

The selected  remedy is protective of human health and the
environment.   The concentration of contaminants in the
groundwater will be reduced to federal drinking water and State
drinking and  groundwater standards via natural attenuation.  It
has been estimated that these levels will be met approximately
five years after implementation of the OU1 remedy.  Under this
remedy, protection of human health would be enhanced with the
implementation of institutional controls,  preventing the use of
the contaminated groundwater.
                               27

-------
 Compliance with  ARARs

 Alternative  2  remedy will  comply with all ARARs for the
 groundwater.   These ARARs  include the Federal Safe Drinking Water
 Act Maximum  Contaminant  Levels  (MCLs)  (40 CFR Part 141.11-141.16
 and Part  141.60-141.63), the New York Public Water Supply
 Regulations  (NYCRR Title 10, Part 5-1), and New York State Water
 Classifications  and Quality Standards for Class GA Ground Water
 (NYCRR, Title  6,  Parts 701-703).   It has been estimated that
 these levels would be met  approximately five years after
 implementation of the OU1  remedy.

 Cost-Effectiveness

 The selected remedy is cost-effective because it has been
 demonstrated to  provide  overall effectiveness proportional to its
 costs.  The selected remedy is technically and administratively
 implementable  and represents the lowest cost of the alternatives
 considered while achieving cleanup objectives in approximately
 the same  time-frame.  The  present worth of the selected
 alternative is $284,000.   There are no capital costs associated
 with this remedial action.

 Utilization of Permanent Solutions and Alternative Treatment
 Technologies to  the Maximum Extent Practicable

 The selected remedy addresses all of the media of concern and
 utilizes permanent solutions and treatment technologies to the
 maximum extent practicable.  In addition,  the selected remedy
 provides the best balance  of trade-offs among the alternatives
 evaluated with respect to  the evaluation criteria.

 Preference for Treatment as a Principal Element

Alternative 2 relies solely on naturally occurring mechanisms to
 reduce the toxicity, mobility and volume of contaminants in the
groundwater.   Groundwater  modeling has predicted that Alternative
 2 will attain ARARs in approximately the same time frame, five
years after the  implementation of the OU1 remedy,  as the other•
alternatives.  This remedy is the most practical choice to
address the contamination  of the groundwater underlying and
downgradient of the Carroll and Dubies site,  even though it does
not satisfy the CERCLA preference for treatment.

                                28

-------
DOCUMENTATION OF SIGNIFICANT CHANGES

There are no significant changes from the preferred alternative,
as presented in the Proposed Plan.
                               29

-------
                            APPENDIX I

                             FIGURES

Figure 1 - Site Location Map

Figure 2 - Site Layout Map

Figure 3 - Isoconcentration Contours of Total Organics in the
Outwash Formation
                               30

-------
                        Carroll and Dubies She, Port Jerris, New York
Source:       USGS 7W M3N. Topographk Qo*d.
             Port Jerris North. .VY-PA 1969

-------
               /CARROLL   tf
             /:  DUBIES  SITE    /   c.,
                      on a
                     ruti 4*>
X
   \
      \
                                                                           T7TTI    T    **•
                                                                           AI'PflOxiUAlC  SCAiC ill fit!
                                                                                                                    A    CAAVfl Pll



                                                                                                                    ^^ -- ' SuNfACt WAltH
                                                                                                                          HCSiOfllllAL n(u

                                                                                                                          (»SiUM(0 tOCAliOii)



                                                                                                                          NlilOCMIIAl M'll.

                                                                                                                                O lOCAliOn)
                                                                                                                             U**«<«iUI M^.
                                                                                                              l. Mnool I » MM ii«4t CM-c**hbi U^L on
                                                                                                               Nt lniiL rMl 44^1 MaiiM, Nt-»>. Itnil
— l,t~
~-
«*JM"« 	
	
t
I
i

t~.

rl"

•-- «—•
^"*- 	 !! 	 1

rr

ri-

hi

ri~
CARROLL AND OUBICS
OCCR PARK, NCW YORK
"•a" r^ •(•.V| 7 «-•• 	 1.1
Site Layout Map ^^1*1 1 "V
suptRfuiio sue IJSSJL: -*
PORT JfdVIS, NCW YORK | flCUHC ?

-------
I. USCS '5 UH.  lOPOCIUPMiC OUAORAMClC  IUf: fOM
  JCIXAS MOA1I1.  KT-PA (IBtt).

1. NrSOOl  M UIH. SdCS OUAfiUWClf  UAP5: OlrSVllt.
  NT (1191). PORI JIIMS MMIH. Ht-PA. (IB9I). PORT
  >CHV1S SOUllt.  MJ-KT-PA. (l»«l).        !

) ORAHCC  COUNIY I/JC U^P. RIVISCO
 *«0-OOI
                                                                                                                                                      GRAVEL  PIT         V
                           CITY LANDFILL
                                •(14)
                       \
        IB      uomioRiNC MIL IN CIACIAI ourwASn

        •      MONITORING MCLL IN OUrWASM/PLL

        Q      UOHllORINC *Cll IN GLACIAL HLL

        0      MOKI10RINC WCLL IN BEDROCK

       100-    lSOCONC(NIRAt10N  CONTOUR (ppb)
       (II)     AC1UAL CONCCHtHARON (ppo)
                                                                                                                                                                  180  110   60    0      40     ISO


                                                                                                                                                                    APPROXIMAIC SCALC IN fEEI
                                                                                                    CARROLL AND  OUBICS
                                                                                                   DEER PARK,  NEW YORK
                                                                                                          1-II44-I11
    ISOCONCENTRATION  CONTOURS 01
TOTAL  ORCANICS  IN  OUTWASH FORMATION  • k
               APRIL,  1995

-------
                           APPENDIX II

                             TABLES

Table 1   -  Primary Constituents of Concern Detected in
             Groundwater

Table 2 -  Risk Assessment:  Contaminants of Concern

Table 3 -  Risk Assessment:  Summary of Exposure Pathways

Table 4 -  Risk Assessment:  Non-carcinogenic and Carcinogenic
                          Toxicity Values

Table 5 -  Risk Assessment:  Non-carcinogenic and Carcinogenic
               Risk Estimates

Table 6 -  Detailed Cost Estimate for Alternative 2
                               31

-------
                                           TABLEi  (Continued)

                                    VOLATILE ORGANIC COMPOUNDS
                         EXCEEDANCES FOUND IN GROUNDWATER SAMPLES
                                 CARROLL & DUBIES SUPERFUND SITE
                                         PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
OW-2
9/94" 4/95
VOLATIl.ES(uR/L)
Clilofomelhanc
Irornomeihane
Vinyl Chloride
Chlorocllinnc
Mclbylcnc ClilotiJc
Acetone
,'arbon DisiilfiJc
l,l-l)ichloroclhcnc
I.l-Dichloroclliane
l.2-l)ichloroelliene(lolal)
Cliloiofonn
1.2-Dichloroelbane
'•Dutiinone
I.l.l-Trichloiociliane
Carbon Tctrachloride
Jromodichloromclliane
1 ,2-Dicbloropropane
cis-l,3-Dichloropropene
I'ricliloroctlicnc
Dibromochloromelhane
1.1.2-Tricliloroclhane
Dcnzcne
Trans- 1.3-Dicbloropropene
Biomofonu
4-Mclhyl-2-l>cnlonone
2-llcxanone
I'cirachlorocihcne
Toluene
1 , 1 .2.2-Telraclilorocllmne
Clilorobcnzcnc
l-iliylhcnzenc
Slyrcnc
rnliil Xylcnes









130 85








24 22







100 76






OW- 3
9/94" 4/95






















15











OW-4
9/94 " '4/95


































OW-5
9/94 4/95










19 7























OW-6 OW-7
9/94 4/95 9/94 4/95



















6


8




17 19






OW-8
9/94 4/95


































OW-9
~9/94~" 4~/95



4


















530 900











OW-9
9/94" 4/95
:cdcral
MCI.
NYSUECT
SOV



5


















780











NA
NA
2
NA
5
NA
NA
7
NA
70
100
5
NA
200
5
100
5
NA
5
NA
5
5
NA
100
NA
NA
5
1.000
NA
NA
700
100
10.000
NA
5(0)
2(S)
5(S)
5(S)
50(0)
NA
5(S)
5(S)
5(S)
7(S)
5(S)
50 (0)
5(S)
5(0)
50 (G)
5(S)
5(S)
5(S)
50 (G)
5(S)
0.7 (S)
5(S)
50 (G)
NA
50 (0)
5(S)
5(S)
5(S)
5(S)
5(S)
5(S)
5(S,
Nolti:
Analysis performed by method 8240.
Diiia lor wells OVV-12 and OW-14 have been torrccled for lliis table.
MC'I. • l;ederal Maximum Conlamiiiiml Level.
SOV • N YSDMC Ambient Water Quality Staiularils (S) mid (iiiidance ((!) Values.
NA • Not applicable/no value available.
I)  Compound not detected above the sample qiiiinlilation limit.
J  Reported value is estimated based on dalu validation.
F.  Concentration rxcreded calibration range of instrument.
I)  Diluted sample.
0  Compound was round in blank.

-------
                                           TABLEi  (Continued)
                                    VOLATILE ORGANIC COMPOUNDS
                          EXCEEDANCES FOUND IN GROUNDWATER SAMPLES
                                  CARROLL & DUBIES SUPERFUND SITE
                                         PORT JERVIS, NEW YORK
\Vell Number 	 1
Suinpliri)! lljlc: |
VOI.ATII.ES(uR/I.)
.'lilixouiellianc
liunininctliane
Vinyl Clilnridc
tliloiocllirinc
Mcihylcne ChloiiJe
Acetone
Curium Divtilflde
I.l-Dicliluioclhcnc
,l-l)iclil(iroelliunc
l.}-l)ichloioi;llicnc(lolol)
lilorofdfin
l.2-l)icliloroelnane
2-llulanone
I.l.l-Tfichlotoclhanc
L'uibun Teirachlocide
liomoilicliloiomcllisne
1.2-DiclilofOpropanc
cis-IJ-Uicliloropropcne
Ificliloiocilicnc
libroniocliloromclhonc
1.1.2- 1 ricliloruclliane
Icnzcnc
1 r3iis-l,)-l)icliloropropcnc
Iliomuform
IMclli)l-2-IVnlDi)onc
2 llexanone
Iclraclilorocllicnc
toluene
1 . 1 .2.2-Tetracliloruclhanc
Cliloiobciizene
r.lliylben/cnc
Siyrene
1 ulal Xvlcncs
OW- 10 1
9/94 ' 4/95 1
1





68















1100 2600





8


9

S3 .10
O\V- 10 1
9/94 4/95 1
1





















2900











OW- 1 1 1
9/9-1 4/95 1
1









8

8









JJO 970








20 30

62 51
OW- 14
9/94' 4/95
1





51



























OW- 13 OW-IJ
9/94 4/95 9/94 4/95



9 34






6 20











40 390 350











OW- 12
9/94 4/95



4


















1100 2400





18

9
12

50
OW- 1 5 1
9/94 '4/95 I
1

































OW- 16
9/94 "4/95


































I'cJcml
MCI.

NA
MA
2
NA
5
NA
NA
7
NA
70
100
5
NA
200
5
100
5
NA
5
NA
5
5
NA
too
NA
MA
5
1.000
NA
NA
700
100
1 0.111)0
NY$I>I:C
sc;v

NA
5(0)
2(S)
MS)
J(S)
30 (G)
HA
5(S)
5(S)
S(S)
7(S)
5(S)
50(0)
S(S)
5(0)
50(0)
J(S)
MS)
J(S)
50(0)
S(S)
0.7(S)
S(S)
50(0)
NA
50 (G)
S(S)
5(S)
5(S)
5(S)
5(S)
5(S)
5(S)
Nolci:
Analysis performed by incllioil 8240.
|)jia fur wells OW-12 and OW-14 liuvc been cnrrettod fur llii* liiblc.
MCI. • l-'ederul Maximum Conluininanl Level.
S(iV • NYSDCC Ambient Water Quality Standard* (S) ;mJ (iuidanvc (G) Values.
MA • Nut ;ipplicablc/no value available.
I)  Compound mil dcleelcd above llie sample i|uanlilalion limit.
J  Itepoiled value is estimated based on data validation.
E  Coiieeiitiiiliiin exceeded cidtbrniton range "I inilriiinent.
D  Diluted sninplc.
I)  CuniputiiiJ wiij liuind in lilunk.

-------
                                           TABLE 1  (Continued)
                                    VOLATILE ORGANIC COMPOUNDS
                         EXCEEDANCES FOUND IN GROUNDWATER SAMPLES
                                 CARROLL & DUBIES SUPERFUND SITE
                                         PORT JERVIS, NEW YORK
Well Number
Sampling Hale:
VOI.ATII.ESfuR/l.)
Jliloroinelhane
Iromnrnclhine
Vinyl Chloride
Chloroelhonc
Meibylenc Chloride
Acetone
Carbon Disiilfide
I.l-Diclilwoellicno
1,1-Diclilnroelliunu
I.M)icliloroelhcnc(lolal)
Clilotoform
1.2-Didiloroelhanc
2-Dulanone
1,1.1-Trichloroelliane
Carbon Telrachloiide
Oromodicliloromclliane
1.2-Dicliloropropanc
cis-l.l-DichlotopfOpcne
Tricliloroclbcne
Oibromocliloromclhone
1,1,2-Trichlorucibane
Ocnzene
Kans-l,3-Uiclilotopropene
Dromoform
J-Mcthyl-2-l'cnlanone
2-llcxanone
fcliaclilotocllicnc
Toluene
1 . 1 .2.2- 1 elracliloroclhane
Clilorobcnzciie
lilbylbenzcnc
Slyrenc
I'mal Xvlencs
OW- 10 1
9/94 4/95 1
1





68















1100 2600





8


9

S3 30
OW- 10 1
9/94 4/95 1
1





















2900











OW- 1 1
9/94 4/95
1









8

8









350 970








20 30

62 51
OW- 14
9/94 " 4/95
1





51



























OW- 13 OW- 13
9/94 "4/95" 9"/94" '4/95'



9 34






6 20











40 390 350











OW- 12
9/94 " 4/95



4


















1100 2400





18

9
12

50
OW- IS
9/94 4/95
1

































OW- 16
9/94 "4/95


































Federal
MCI.

NA
NA
2
NA
5
NA
NA
7
NA
70
100
5
NA
200
5
100
5
NA
5
NA
5
5
NA
100
NA
NA
5
1.000
NA
NA
700
100
10.00(1
HYSDKC
sov

NA
5(0)
2(S)
S(S)
5(S)
50(0)
NA
5(S)
5(S)
5(S)
7(S)
5(S)
50 (0)
S(S)
5(0)
50(0)
5(S)
5(S)
5(S)
50(0)
5(S)
0.7 (S)
5(S)
50(0)
NA
50(0)
5(S)
5(S)
5(S)
5(S)
5(S)
5(S)
5(S)
Nolei:
Analysis performed by method 8240.
Dala for wells OW-12 end OW-M have liccn corrected fur this table.
MCI. • Federal Maximum Coiiliiininanl Level
S(iV • NYSOCC Ambicnl W;iier Quality Standard* (S) and Guidance (G) Values.
NA • Noi applicable/no value available.
U
J
E
U
U
Compound mil tleleclcd above (lie sample (|iiaii(ilalion limil.
Reported value is estimated based uu data validation.
C'onecnlraliiin exceeded calibration range nl'instrument.
Diluted sample.
Compound was round in blank.

-------
                                                   TABLE ^Continued)
                                        SEMI-VOLATILE ORGANIC COMPOUNDS
                                EXCEEDANCES FOUND IN GROUNDWATER SAMPLES
                                         CARROLL & DUBIES SUPERFUND SITE
                                                PORT JERVIS, NEW YORK
\Vrll Hiimlicr 1
Sampling Dale: |
OW- 2 I
9/9I 4/9$ I
Sl.MI VOI.A III.KS(|.R/I.) 1
rl.cnnl
llij(2 •Clitnioelliyl)l:llicr
•( ItllllllpllClllll
. ) |)iilil(iinlx;ii»cnc
.4-l)iililiiinlii-n/i:iie
, ? Dicliliunlxn/cnc
•Melliylpliennl
,2'-O«yliij(l-CldnnipropBne)
I- Mi-lli) l|>lii:iml
) Niliosoili H-l'iopyluiiiinc
IcxaililoKiclltaiie
tiliolien/eite
ioplipiune
2 Milinpliciiol
!.•! l)inii:lli)lpliciiol
lis(2-('lilofocllioxy) Mcllinnc
2.-) Dicliloidpliini)!
|.7,4-Tiichloiolien/cne
Haplillolcnv
l-Cldofoanilinc
le \ncliloiiibnliidiciic
l-ClilofO-3-Mclhylplienol
7-Mi-ili)lnaplillialtiie
llexarlilomcyclopcntndicne
7.-I.6- liicldoiopliciuil
2.1.5 lii(lilnio|i|iciiiiiti(ri)littnciic
VHitmaniliue
































OW- ]
9/9 1 .J/9J

•I































OW- -I
9/9 1 4/95

































OW. $ I
9/94 4/9$ |

































OW- 6 .
9/94 -l'/9$

































OW- 7
9/9.J" 4/9$

































OW- g
9/9-1 4/9$

































OW-9 1
9/91 4/9$ 1

71 -IX































OW- Ill
9/91 1/95
1 edciul 1
MC 1.
nvsnr.c
SVC

27











•no



















HA
HA
HA
600
7$
600
HA
HA
HA
HA
HA
HA
HA
HA
HA
NA
HA
70
HA
HA
HA
HA
HA
50
HA
HA
HA
HA
HA
HA
HA
HA
1 (S)
MS)
HA
MS)
4.7 (S)
4.7 (S)
50lr/iiii value availdle.
II  Compound not delected iiluive the sample ijiianlil.iiiiiii limit.
J  Kepnilcd value is estimated Imscd on il.iln validation.
I:  Concenlfiilion exceeded calilxalinn ijinge nl'iii
II  Compound was found in blank.
l(  D.il.i is (ejected based on data validation.

-------
                                                 TABLE i (Continued)
                                      SEMI-VOLATILE ORGANIC COMPOUNDS
                               EXCEEDANCES FOUND IN GROUNDWATER SAMPLES
                                       CARROLL & DUBIES SUPERFUND SITE
                                              PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
SKMI-VOI.ATII.KS(jiK/l.)
I'licnol
l)is(2-Chloroelliyl)Hihcr
2-Chloroplienol
l.3-l)ichlorobeiucrie
l.4'l)iclmmiben*ene
1,2-PiclilurobeM/cnc
2-Melliylphcnol
2,2'-Oxybis( 1 -Chloropropane)
4-Melhylphcnol
'•J-Nilrosodi-N-l'ropylaminc
llcxachloroetliiine
^iuobenzcnc
sophoronc
2-Niuophcnol
2,4-l)imc(hylplicnol
Ois(2-Cbloroclboxy) Methane
2.4-Dichlorophenol
1.2,4-Triclilorobciizciic
Naphthalene
4-Chloroaniline
llcxachlorohutadicnc
•J-Chloro-3-McUiylpticnol
2-Mclhylnaphihalcne
1 lexachlorocyclopcnladiene
2.4.6-Trichlorophenol
2,^,5-Trichlorophenol
2-Chloronaphlhalene
2-Nilroanilinc
Dimcthylphihalatc
Accnapluliylcne
2.6-l)inillOtulllCnO
3-Nilrnaniline
OW- 1 1
9/9-1 4/95

24

















21 17













OW- U
9/94 .1/95

































OW- 1 3
9/
-------
                                                 TABLE i (Continued)
                                      SEMI-VOLATILE ORGANIC COMPOUNDS
                               EXCEEDANCES FOUND IN GROUNDWATER SAMPLES
                                       CARROLL & DUBIES SUPERFUND SITE
                                              PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
SF.MI-VOI.AHI.KS (MR/I.)
Acenaphthcnc
2,4-Dinilrophcnol
4-Nilronhcnol
Dihciizofnran
2.4-l)inilrololiiene
Dielhylphlhalulc
•t-Clilorupliviiyl-l'liciiyl lithcr
l-luorenc
4-Nilroaniline
4,6-l)ini(ro-2-Mclliylphenol
hJ-Nilrosodipheny famine
4-Bromophenyl-Phenylclhcr
!lexachlorobcn/cnt:
Penlachlorophenol
Phenanlhrcne
Anlluacene
Carbazolc
Di-N-Hulylphlhalale
Fluoranlhenc
I'yrcne
Uulylbenzylphlhalale
3.3'-Dichlorobcnzidinc
[knzo(A)Anlhracene
Chrysene
l)is(2-i:lhylnexyl)l'hlhalale
Di-N-Oclylplilhalalc
Uenzo(IJ)Fluoranthcnc
[hnzo(K)Fluoranlhcnc
Rcnzo(A)l'yrenc
Indcno(l,2.3-Cd)l'yrcnc
Dibcn/(A,l IJAiithraccne
nenzo(O.IU)Pcrvlene
OW- 1 1
9/94 4/9$






57


























OW- H
9/9-1 4/95

































OW- 13
9/94 4/95

































OW- 12
9/94 4/95

































OW- 15
9/94 4/95

































OW- 16
9/94 4/95

































OW- 17
9/94 4/95

































OW- 18
9/94 4/95

































OW- 19
9/94 4/95

































l:cdcr;il
MCI.

NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
1
1
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
6
NA
NA
NA
2
NA
NA
NA
NYSDHC
SVG

20 (S)
NA
NA
NA
5(S)
50 (G)
NA
50(0)
NA
NA
50 (G)
NA
0.35 (S)
I(S)
50 (G)
50 (G)
NA
NA
50 (G)
50 (G)
50(0)
NA
0.002 (S)
0.002 (S)
50 (S)
NA
0.002 (S)
0.002 (S)
ND
0.002 (S)
NA
NA
Notes:
Analysis performed by method 8240.
Data for wells OW-12 imd OW-14 have been toneeled lor this table.
MCI. • Federal Maximum Contaminant Level.
SOV - NYSDIIC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value availble.
U  Compound no( delected above the sample <|uanlilaiion limit.
J  Reported value is estimated based on data validation.
!•  Concentration exceeded calibration range of instrument.
I)  Compound was found in blank.
It  Data is rejected based on data validation.

-------
                                           TABLE i

                                     ANALYTE LIST METALS
                            HITS FOUND IN GROUNDWATER SAMPLES

                              CARROLL & DUBIES SUPERFUND SITE
                                    PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
M ETA I .S (MR/1
Aluiniiuun
Antimony
Arsenic
Barium
Ikryllitim
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
Federal
MCLs
)
200
6
50
2,000
4
5
100
1.000
NA
NA
NA
50
2
50
100
NA
2
NA
200
NYSDI-C
SGVs

IOO(S)
3(0)
25 (S)
I.OOO(S)
3(0)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35,000(0)
300 (S)
2(S)
IO(S)
50 (S)
20.000 (S)
4(0)
300 (S)
IOO(S)

9/9-1









304


6060



38600



MW- 1
4/95 7/96












5640 5850



33100 28000




9/94

160







3250


3360







MW-3
4/95

1980

180




935
51900
54.3

4230





620


7/96












4520








9/94

172







17700


7850



257000



MW- 4
4/95

MOO







18200


6380



264000
4.2



7/96









12500


5880



205000



MW-5
4/95

2850







6710


355







MW- 10
7/96









26600


4640







Nolcs:

MCL - Federal Maximum Contaminant Level.
SGV - NYSDEC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value available.

-------
                                    TABLE 4

                             ANALYTE LIST METALS
                     HITS FOUND IN GROUNDWATER SAMPLES

                      CARROLL & DUBIES SUPERFUND SITE
                            PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
Federal
MCl.s
NYSDEC
SGVs
Y!ETALSOie/I.)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
200
6
50
2.000
4
5
100
1.000
NA
NA
NA
50
2
50
100
NA
2
NA
200
IOO(S)
3(0)
25 (S)
I.OOO(S)
3(0)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35.000(0)
300 (S)
2(S)
IO(S)
50 (S)
20,000 (S)
4(0)
300 (S)
IOO(S)
OW-6
9/94

924







3930

3780








4/95

28200
3.3
28.8





61700
58.9

5940







OW-7
9/94 4/95

60! 43200

31.2

3.4

455

715 66800
79.9

4260







7/96




















9/94

1170







12100


3850







OW-8
	 4/95 " '

12100

26.8





31800
35.3

4560







7/96









9740


4790







Noles:

MCL - Federal Maximum Contaminant Level.
SGV - NYSDEC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Nol applicable/no value available.

-------
                                 TABLE!

                          ANALYTE LIST METALS
                  HITS FOUND IN GROUNDWATER SAMPLES

                    CARROLL & DUBIES SUPERFUND SITE
                         PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
VI ETA LS (UK/I
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium •
Silver
Sodium
Thallium
Zinc
Cyanide
Federal
MCLs
)
200
6
50
2.000
4
5
100
1,000
NA
NA
NA
50
2
50
100
NA
2
NA
200
NYSDEC
SGVs

IOO(S)
3(0)
25 (S)
I.OOO(S)
3(0)
!«
-------
                                   TABLE 1

                             ANALYTE LIST METALS
                    HITS FOUND IN GROUNDWATER SAMPLES

                      CARROLL & DUBIES SUPERFUND SITE
                            PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
Federal
MCl.s
NYSDI-C
SGVs
VI ETA I-S OIK/I.)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
200
6
50
2,000
•1
5
100
1,000
NA
NA
NA
50
2
50
100
NA
2
NA
200
100(S)
3(0)
25 (S)
I,000(S)
3(0)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(S)
10(S)
50 (S)
20,000 (S)
4(0)
300 (S)
IOO(S)
9/9«l

1750







53200


5420







O\V- 12
•1/95

8440
4.2






68100


6780







7/96









69800


8690







9/94

931







2320


1680







OW- 13
4/95 "

54200
3.2
39

3.3

669
236
73300
61

6010





1010

7/96









19200


7960







9/94

7540







17700


1990



22500



OW- N
4/95

19800







35800


2580







Notes:

MCL - Federal Maximum Contaminant Level.
SGV - NYSDEC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value available.

-------
                                       TABLE 1

                                ANALYTE LIST METALS
                        HITS FOUND IN GROUNDWATER SAMPLES

                          CARROLL & DUBIES SUPERFUND SITE
                                PORT JERVIS, NEW YORK
Well Number
Sampling Date:
METALS (ME/I
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
Federal
MCLs
)
200
6
50
2,000
4
5
100
1,000
NA
NA
NA
50
2
50
100
NA
2
NA
200
NYSDEC
SGVs

IOO(S)
3(0)
25 (S)
I.OOO(S)
3(0)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35.000 (G)
300 (S)
2(S)
IO(S)
50 (S)
20,000 (S)
4(0)
300 (S)
IOO(S)

9/94

671







28800


6980







OW- 15
4/95

353







25700


5750




6.8


OW
9/94

2610







2720


2430



25200



-16
4/95

26700





81.1

65500
49.5

2130



22100
5.8


OW-16D
7/96









978


2640







OW-I6S
7/96












2650



31000




9/94

2290


f




4920


8890







OW- 17
4/95

20300
3.3






39100
29.4

7860








'"7/96""












8440







Notes:

MCL - Federal Maximum Contaminant Level.
SGV - NYSDEC Ambienl Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value available.

-------
                                      TABLE 1

                                ANALYTE LIST METALS
                       HITS FOUND IN GROUNDWATER SAMPLES

                         CARROLL & DUBIES SUPERFUND SITE
                               PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
METALS (HE/I
Aluminum
Antimony
Arsenic
Barium
Reryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
Federal
MCl.s
)
200
6
50
2,000
4
5
100
1,000
NA
NA
NA
50
2
50
100
NA
2
NA
200
NYSDILC
SGVs

IOO(S)
3(G)
25 (S)
I.OOO(S)
3(G)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35.000(G)
300 (S)
2(S)
10(S)
50 (S)
20.000 (S)
4(G)
300 (S)
IOO(S)

9/94

7250







24300


7570







OW- 18
4/95

19900
5.7
70.9





98600


5090



21900




7/96



37.7 .





54000


1 480








9/94

1 220

28.9





58800


3190



31000



OW- 19
"4/95 "

22700
3.5
78.6





92800
46.9

3640



25700




' 7/96



43.1





67200


5060



24000




9/9'i









5 1 800


- 3520







OW- 20
"4/95 "

38000
4.5
105



375

121000
78.6

6560





364


7/96









29000


2440







Notes:

MCL - Federal Maximum Contaminant Level.
SGV - NYSDEC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value available.

-------
                                      TABLE i.

                                ANALYTE LIST METALS
                        HITS FOUND IN GROUNDWATER SAMPLES

                         CARROLL & DUBIES SUPERFUND SITE
                               PORT JERVIS, NEW YORK
Well Number
Sampling Date:
V1ETALS(ne/L
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
Federal
MCLs
)
200
6
50
2,000
4
5
1 00
1, 000
NA
NA
NA
50
2
50
1 00
NA
2
NA
200
NYSDEC
SGVs

IOO(S)
3(0)
25 (S)
I,000(S)
3(0)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(S)
IO(S)
50 (S)
20,000 (S)
4(0)
300 (S)
IOO(S)

9/94

6370







40900


4960



25400



OW-2I
4/95

453







30100


4720



24400




7/96









27000


4700








9/94

926







62900


3000



24600



OW-22
"4/95"

142
3.4






58000


2720



23500




7/96



35





52000


2450



42000




9/94

669







15700


2180



44100



OW-23
~4/95









11000


1080



31600




7/96









26300


1830



57000



Notes:

MCL - Federal Maximum Contaminant Level.
SGV - NYSDEC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value avnilnblc.

-------
                           TABLE i

                     ANALYTE LIST METALS
             HITS FOUND IN GROUNDWATER SAMPLES

              CARROLL & DUBIES SUPERFUND SITE
                    PORT JERVIS, NEW YORK
Well Number
Sampling Dale:
Federal
MCLs
NYSDEC
SGVs
METAI.S(|iu/I.)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
200
6
50
2,000
4
5
100
1.000
NA
NA
NA
50
2
50
100
NA
2
NA
200
IOO(S)
3(G)
25 (S)
I.OOO(S)
3(G)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(S)
10(S)
50 (S)
20,000 (S)
4(G)
300 (S)
IOO(S)
IJW
9/9
-------
                                  TABLE L

                           ANALYTE LIST METALS
                   HITS FOUND IN GROUNDWATER SAMPLES

                    CARROLL & DUBIES SUPERFUND SITE
                          PORT JERVIS, NEW YORK
Well Number
Sampling Dal
Federal
MCLs
NYSDEC
SGVs
VIETAl,SOic/[,)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Chromium
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Selenium
Silver
Sodium
Thallium
Zinc
Cyanide
200
6
50
2,000
4
5
100
1,000
NA
NA
NA
50
2
50
100
NA
2
NA
200
IOO(S)
3(0)
25 (S)
I.OOO(S)
3(0)
IO(S)
50 (S)
200 (S)
300 (S)
25 (S)
35,000 (0)
300 (S)
2(S)
IO(S)
50 (S)
20,000 (S)
4(0)
300 (S)
IOO(S)
BU
9/94

558







4640


3440



22100



/-5
4/95

2100







7830


3390







TW-2
9/94

989







1410










4/95

1890







5190







5


TWO
9/94

123














28600



4/95

554







935


6910



25100
4.7


XW-2
4/95

11900







20300


2610







XW- 14
4/95

18900







36200


2540




4.7


Notes:

MCL - Federal Maximum Contaminant Level.
SGV - NYSDEC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not appliciible/no value available.

-------
                                                TABLE 1
                                     TARGET ANALYTE LIST METALS
                                   FOUND IN GROUNDWATER SAMPLES

                                  CARROLL & DUBIES SUPERFUND SITE
                                        PORT JERVIS, NEW YORK
Well Number
SamplinK Date:
METALSOiC/L
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Silver
Sodium
Thallium
Vanadium
Zinc
MW- 1
07/23/96
)
200 U
60 U
10 U
200 U
5 U
5 U
23000
12 J
50 U
25 U
100 U
3 U
8000
5850

40 U
5000 U

10 U
28000

50 U
20 U
MW-3
07/24/96

200 U
60 U
10 U
200 U
5 U
5 U
19000
10 U
50 U
25 U
300
3 U
5000
4520

40 U
5000 U

10 U
6000

50 U
20 U
MW-4 MW- 10
07/18/96 	 07/17/96

200 U 200 U
60 U 60 U
10 U 10.7
200 U 200 U
5 U 5 U
5 U 5 U
108000 76000
10 U 10 U
50 U 50 U
25 U 25 U
12500 26600
4.1 3 U
14000 7000
5880 4640
0.2 U 0.2 U
40 U 40 U
6000 5000 U
7 5 U
10 U 10 U
205000 18000
10 U 10 U
50 U 50 U
20 U 20 U
MW-20
07/18/96

200 U
60 U
10 U
200 U
5 U
5 U
112000
18
50 U
25 U
12500
3 U
15000
5890
0.2 U
40 U
6000
6.3
10 U
204000
10 U
50 U
20 U
MW-30
07/24/96

200 U
60 U
10 U
200 U
5 U
5 U
19000
10 J
50 U
25 U
338
3 U
5000
4470

40 U
5000 U

10 U
6000

50 U
20 U
OW-2 .
07/18/96

200 U
60 U
10 U
200 U
5 U
5 U
56000
10 J
50 U
25 U
100 U
3 U
7000
171
0.2 U
40 U
5 U
5 U
10 U
10000
10 U
50 U
20 U
Federal
MCLs

200
6
50
2,000
4
5
NA
100
NA
1,000
NA
NA
NA
50
2
NA
NA
50
100
NA
2
NA
NA
NYSDEC
SGVs

IOO(S)
3(G)
25 (S)
I.OOO(S)
3(G)
10(S)
NA
50 (S)
NA
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(S)
NA
NA
10(S)
50 (S)
20,000 (S)
4(G)
NA
300 (S)
Notes:

MCI. - Federul Maximum Contaminant Level.
SOV - NYSD1-C Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value available.
U Not detected.
J Value is estimated.

-------
                                                TABLE 1
                                     TARGET ANALYTE LIST METALS
                                  FOUND IN GROUNDWATER SAMPLES

                                  CARROLL & DOBIES SUPERFUND SITE
                                        PORT JERVIS, NEW YORK
Well Number
Sampling Date:
METALS(nc/L
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Silver
Sodium
Thallium
Vanadium
Zinc
MW- 1
07/23/96
)
200 U
60 U
10 U
200 U
5 U
5 U
23000
12 J
50 U
25 U
100 U
3 U
8000
5850

40 U
5000 U

10 U
28000

50 U
20 U
MW-3
07/24/96

200 U
60 U
10 U
200 U
5 U
5 U
19000
10 U
50 U
25 U
300
3 U
5000
4520

40 U
5000 U

10 U
6000

50 U
20 U
MW-4 MW- 10
07/18/96 07/17/96

200 U 200 U
60 U 60 U
10 U 10.7
200 U 200 U
5 U 5 U
5 U 5 U
108000 76000
10 U 10 U
50 U 50 U
25 U 25 U
12500 26600
4.1 3 U
14000 7000
5880 4640
. 0.2 U 0.2 U
40 U 40 U
6000 5000 ' U
7 5 U
10 U 10 U
205000 18000
10 U 10 U
50 U 50 U
20 U 20 U
MW-20
07/18/96

200 U
60 U
' 10 U
200 U
5 U
5 U
1 12000
18
50 U
25 U
12500
3 U
15000
5890
0.2 U
40 U
6000
6.3
10 U
204000
10 U
50 U
20 U
MW-30
07/24/96

200 U
60 U
10 U
200 U
5 U
5 U
19000
10 J
50 U
25 U
338
3 U
5000
4470

40 U
5000 U

10 U
6000

50 U
20 U
OW-2
07/18/96

200 U
60 U
10 U
200 U
5 U
5 U
56000
10 J
50 U
25 U
100 U
3 U
7000
171 '
0.2 U
40 U
5 U
5 U
10 U
1 0000
10 U
50 U
20 U
Federal
MCLs

200
6
50
2,000
4
5
NA
100
NA
1,000
NA
NA
NA
50
2
NA
NA
50
100
NA
2
NA
NA
NYSDEC
SGVs

IOO(S)
3(0)
25 (S)
I,000(S)
3(G)
IO(S)
NA
50 (S)
NA
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(S)
NA
NA
10(S)
50 (S)
20,000 (S)
4(G)
NA
300 (S)
Notes:

MCI. - Federal Maximum Contaminant Level.
SGV - NYSDIiC Ambient Water Quality Standards (S) and Guidance ((J) Values.
NA • Not applicable/no value available.
U Not detected.
J Value is estimated.

-------
                                           TABLE i (Continued)
                                     TARGET ANALYTE LIST METALS
                                   FOUND IN GROUNDWATER SAMPLES

                                  CARROLL & DUBIES SUPERFUND SITE
                                        PORT JERVIS, NEW YORK
Well Number
Sampling DaU
OW-5
07/22/96
OW-7
07/22/96
OW- 8 OW- 9
07/1 8/96 07/16/96
OW- 10
07/23/96
OW- 11
07/24/96
OW- 12
07/16/96
Federal
MCLs
NYSDEC
SGVs
METALSOie/L)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Silver
Sodium
Thallium
Vanadium
Zinc
200 U
60 U
10 U
200 U
5 U
5 U
31000
10 U
50 U
25 U
5710
3' U
5000 U
3440

40 U
5000 U

10 U
75000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
119000
14
50 U
25 U
100 U
3 U
6000
38

40 U
5000 U

10 U
7000

50 U
20 U
200 U 200 U
60 U 60 U
17.5 10 U
200 U 200 U
5 U 5 U
5 U 5 U
12000 95000
14 70
50 U 50 U
25 U 25 U
9740 53800
3 U 4.6
5000 U 9000
4790 8600
0.2 U 0.2 U
40 U 48
5000 U 5000 U
5 U 5 U
10 U 10 U
13000 11000
10 U 10 U
50 U 50 U
20 U 25
677
60 U
10 U
200 U
5 U
5 U
128000
24
50 U
25 U
41400
3 U
9000
6180

40 U
5000

10 U
12000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
163000
10 U
50 U
25 U
26800
3 U
9000
5660

40 U
5000 U

10 U
9000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
134000
29
50 U
25 U
69800
3 U
. 10000
8690
0.2 U
40 U
5000 U
5 U
10 U
17000
10 U
50 U
20 U
200
6
50
2,000
4
5
NA
100
NA
1,000
NA
NA
NA
50
2
NA
NA
50
100
NA
2
NA
NA
IOO(S)
3(0)
25 (S)
1,000(8)
3(0)
IO(S)
NA
50 (S)
NA
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(8)
NA
NA
10(8)
50 (S)
20,000 (S)
4(0)
NA
300 (S)
Notes:

MCL • l;ederal Maximum Contaminant Level.
SGV - NYSDliC Ambient Water Quality Standards (S) und Guidance (G) Values.
NA - Not applicable/no value available.
U Not detected.
J Value is estimated.

-------
                                         TABLEi (Continued)
                                    TARGET ANALYTE LIST METALS
                                  FOUND IN GROUNDWATER SAMPLES

                                 CARROLL & DUBIES SUPERFUND SITE
                                       PORT JERVIS, NEW YORK
Well Number
Sampling DaU
OW-5
011221%
OW-7
07/22/96
OW- 8 OW- 9
07/18/96 07/16/96
OW- 10
"07/23/96"""
OW- 11
07/24/96'
OW- 12
"07/16~/96"~~
Federal
MCLs
NYSDEC
SGVs
V1ETALS(uc/U
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Silver
Sodium
Thallium
Vanadium
Zinc
200 U
60 U
10 U
200 U
5 U
5 U
31000
10 U
50 U
25 U
5710
3' U
5000 U
3440

40 U
5000 U

10 U
75000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
119000
14
50 U
25 U
100 U
3 U
6000
38

40 U
5000 U

10 U
7000

50 U
20 U
200 U 200 U
60 U 60 U
17.5 10 U
200 U 200 U
5 U 5 U
5 U 5 U
12000 95000
14 70
50 U 50 U
25 U 25 U
9740 53800
3 U 4.6
5000 U 9000
4790 8600
0.2 U 0.2 U
40 U 48
5000 U 5000 U
5 U 5 U
10 U 10 U
13000 11000
10 U 10 U
50 U 50 U
20 U 25
677
60 U
10 U
200 U
5 U
5 U
128000
24
50 U
25 U
41400
3 U
9000
6180

40 U
5000

10 U
12000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
163000
10 U
50 U
25 U
26800
3 U
9000
5660

40 U
5000 U

10 U
9000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
134000
29
50 U
25 U
69800
3 U
10000
8690
0.2 U
40 U
5000 U
5 U
10 U
17000
10 U
50 U
20 U
200
6
50
2,000
4
5
NA
100
NA
1,000
NA
NA
NA
50
2
NA
NA
50
100
NA
2
NA
NA
100(S)
3(0)
25 (S)
1,000(5)
3(0)
IO(S)
NA
50 (S)
NA
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(S)
NA
NA
10(S)
50 (S)
20,000 (S)
4(G)
NA
300 (S)
Notes:

MCI. - Federal Maximum Contaminant Level.
SGV - NYSDI-C Ambient Water Quality Standards (S) and Guidance (G) Values;
NA - Not applicable/no value available.
U Not detected.
J Value is estimated.

-------
                                           TABLE! (Continued)
                                      TARGET ANALYTE LIST METALS
                                   FOUND IN GROUNDWATER SAMPLES

                                   CARROLL & DUBIES SUPERFUND SITE
                                         PORT JERVIS, NEW YORK
Well Number
Sampling Dak
OW-21
07/17/96
OW-22
07/17/96
OW-23
07/24/96
EQBtfl
07/19/96
EB#3
07/24/96
EQB 02 [Federal
07/19/96 iMCLs
NYSDEC
SGVs
METALS (ne/L)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Silver
Sodium
Thallium
Vanadium
Zinc
200 U
60 U
10 U
200 U
5 U
5 U
78000
10 U
50 U
25 U
27000
3 U
8000
4700
0.2 U
40 U
5000 U
5
10 U
18000
10 U
50 U
20 U
200 U
60 U
35
200 U
5 U
5 U
73000
10 U
50 U
25 U
52000
3 U.
16000
2450
0.2 U
40 U
27000
8
10 U
42000
10 U
50 U
20 U
200 U
60 U
12.3
381
5 U
5 U
155000
10 U
50 U
25 U
26300
3 U
15000
1830

40 U
9000

10 U
57000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
5000 U
10 U
50 U
25 U
100 U
3 U
5000 U
15 U
0.2 U
. 40 U
5000 U
5 U
10 U
5000 U
10 U
50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
5000 U
10 U
50 U
25 U
100 U
3 U
5000 U
15 U

40 U
5000 U

10 U
5000 U

50 U
20 U
200 U
60 U
10 U
200 U
5 B
5 U
5000 U
29
50 U
25 U
130
3 U
5000 U
15 U
0.2 U
40 U
5000 U
5 U
10 U
5000 U
10 U
50 U
20 U
200
6
50
2,000
4
5
NA
100
NA
1,000
NA
NA
NA
50
2
NA
NA
50
100
NA
2
NA
NA
IOO(S)
3(0)
25 (S)
I.OOO(S)
3(0)
10(S)
NA
50 (S)
NA
200 (S)
300 (S)
25 (S)
5,000 (G
300 (S)
2(S)
NA
NA
10(S)
50 (S)
20,000 (S)
4(0)
NA
300 (S)
Notes:

MCL - Federal Maximum Contaminant Level.
SGV - NYSD1-C Ambient Water Quulily Standards (S) and Guidance (G) Values.
NA - Not applicable/no value available.
U Not detected.
J Value is estimated.

-------
                                            TABLE i (Continued)
                                      TARGET ANALYTE LIST METALS
                                    FOUND IN GROUNDWATER SAMPLES

                                   CARROLL & DUBIES SUPERFUND SITE
                                          PORT JERVIS, NEW YORK
Well Number
Sampling Date
OW- 13
07/22/96
OW-I6D
07/22/96
OW-16S OW- 17
07/22/96 07/27/96
OW- 18
07~/24/96
OW- 19
07/24/96
OW-20
07/17/96
Federal
MCLs
NYSDEC
SGVs
VIETALSOie/L)
Aluminum
Antimony
Arsenic
Barium
Beryllium
Cadmium
Calcium
Chromium
Cobalt
Copper
Iron
Lead
Magnesium
Manganese
Mercury
Nickel
Potassium
Selenium
Silver
Sodium
Thallium
Vanadium
Zinc
200 U
60 U
10 U
200 U
5 U
5 U
148000
10 U
50 U
25 U
19200
3
10000
7960

40 U
5000 U

10 U
17000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
18000
10 U
50 U
25 U
978
5.1
5000 U
2640

40 U
5000 U

10 U
7000

50 U
20 U
200 U 200 U
60 U 60 U
10 U 10 U
200 U 200 U
5' U 5 U
5 U 5 U
36000 52000
23 J 10 U
50 U 50 U
25 U 25 U
194 100 U
4.1 3 U
6000 6000
2650 8440

40 U 40 U
5000 U 5000 U

10 U 10 U
31000 15000

50 U 50 U
20 U 20 U
200 .U
60 U
37.7
200 U
5 U
5 U
62000
10 U
50 U
25 U
54000
3 U
8000
1480

40 U
25000

10 U
17000

50 U
20 U
200 U
60 U
43.1
261
5 U
5 U
85000
10 U
50 U
25 U
67200
3 U
12000
5060

40 U
18000

10 U
24000

50 U
20 U
200 U
60 U
10 U
200 U
5 U
5 U
58000
10 U
50 U
25 U
29000
3 U
5000
2440
0.2 U
40 U
5000 U
5 U
10 U
8000
10 U
50 U
20 U
200
6
50
2,000
4
5
NA
100
NA
1,000
NA
NA
NA
50
2
NA
NA
50
100
NA
2
NA
NA
IOO(S)
3(G)
25 (S)
1,000(8)
3(G)
10 (S) •
NA
50 (S)
NA
200 (S)
300 (S)
25 (S)
35,000 (G)
300 (S)
2(S)
NA
NA
10(S)
50 (S)
20,000 (S)
4(G)
NA
300 (S)
Notes:
OW-16S - Represents readings taken at a depth of 26.0
MCL - Federal Maximum Conlaminanl Level.
SGV - NYSDEC Ambient Water Quality Standards (S) and Guidance (G) Values.
NA - Not applicable/no value available.
OW-I6S - Represents readings taken at a depth of 43.5
U Not detected.
J Value is estimated.

-------
                                                 TABLE   3.
                                      EXPOSURE POINT CONCENTRATIONS
                           CROUNDWATER IN OUTWASII.TILL, AND BEDROCK AQUIFERS
                                      CARROLL & DUBIES SUPERFUND SITE
                                           PORT JERVIS, NEW YORK
•" •. % *
'

tfbc^TiMBu^f'^vficcfif
VoUllle Organic empound
Vuiyl Chloride
QJorocUunc
l.2-Dichlorocthcncul)
Chloroform
rrichlon>c(hcnc
JOUCM
rctnchlorocthcnc
Toluene
Chlorobaucnc
:(hy|bcnune
Tool Xylcna
kml-V»UUl«'Oninlc Con
Phenol
,4-D)cUo(i>bcnzcnc
,2-Dichloiobcracne
2-Mclhylphenol
4-Mcthylphcnol
tophorone
Niphllulcnc
2-Mcthybuph!hilcnc
DieUi/lpodultl*
Di-fl-butylpbdultlc
Di-n-octylphuulue •
Mfi*t6M/U '"'.'":•• ' "••• "'''' •' •
Aluminum
Arsenic
lirium
Icryltium
Chrocnium
Copper
Utd
Selenium
Silver
VinAdium
line
-
Numtxr of

S*mi'|tf
i(nr/U
61
61
61
61
61
61
61
61
61
61
61

59
59
59
59
59
59
59
59
59
59
59

10
30
30
30
30
30
30
30
30
30
10
V <
Numtxr «t

Dflfrt*
,
6
1
10
1
4
21
4
5
10
5
1
• .'• ' 1
II
2
2
2
5
1
4
6
24
II
5

30
19
30
23
23
26
25
2
3
27
30

Number «f

Non<)rtf£li
'
55
60
51
60
57
31
57
56
51
56
53

41
57
57
57
54
51
55
53
35
4S
54

0
11
0
7
7
4
5
28
27
3
0
\ > % •*•
iw«i«A

Connnlratlon
- ' -
34
15
110
10 I
14
2.600
100
II
10 )
30 J
62
••
71
2 I
2 J
1 I
4 1
440
21
27
57
10 J
3 I

10.300
29
284
1 B
121
51
19.2
1.5 B
7.9 U
26.7 B
170
/'VVv£
*"^ ff'f » v ' * ,'
* *• >-. J '
, Geometric ',..
% . * < '* *

•• N- - ,
5.7B
5.64
6.4
5.tf
5M
14.7
6.34
5.31
5.74
5.73
6.41

6.15
5.04
5.04
4.91
4.79
5.46
5.57
5.69
4.69
4.57
49

1.180
3.16
69.3
0.145
6.35
5.75
1.64
0574
2.44
5.38
362
* >-;;
•f^njeiF

^Cl'lltfV'
' -i >
1.71
1.61
2.11
1.62
1.71
6.74
2.04
I.I
1.65
1.72
2.12
..
2.04
1.49
1.49
1.54
1.63
I.I
1.41
1.51
224
1.66
1.49

3.60
3.26
2.24
2.07
2.94
3.20
3.21
1.31
1.38
2.09
24J.
-: \ , ; c","'^; ";5 ;
*r 'uJL.siX*

n' • - *\9tVi -"'••

1.167
1.806
2.01]
1.106
1.167
3.355
2.012
1.167
1.167
1.867
2.012
>•
2.015
1.757
.757
.107
.807
.869
.757
.107
.100
.169
.107

2.756
2.565
2.213
2111
2.437
2.565
2.565
1.7449
1.797
2.1 II
2213
.7 »V


1 I-fmll
•,./,;-;'
7.60
7.IJ
10.)
7.03
7.61
207
9.12
7.39
7.34
7.55
104

9.5«
5.9S
5.91
6.07
6.05
7.5
6.5J
7.03
1.13
5.17
5.15

5.170
11.2
134
0.25
11.5
19.7
5.64
0.65
215
9.41
71.1 .
C;|;;.£<>:^
cV'Hn* pZT'' •
* j.\ *\ ..'i"1
1 * ConcepitratloB
> *»' ', ," s " '' ' '
1.60
7.1)
10.1
' 7.03
7.6J
207
912
7.39
7.J4
7.55
10.4
•••. ' , ' ' - '•• •• •*
9.5«
2.00
100
1.00
4.00
7.5
6.51
7.03
(.13
5.17
300
' .* ' » 7 s-
5.170
11.2
134
0.25
11.5
19.7
5.64
0.65
2.15
9.41
78.4
NaU*.

On* M/ihJ &MXOO+ Iwu uMd in «jiiiua.

     otcrf
-------
             TABLES-
  POTENTIAL EXPOSURE PATHWAYS FOR
CURRENT AND FUTURE LAND USE SCENARIOS
   CARROLL & DUBIES SUPERFUND SITE
        PORT JERVIS, NEW YORK
Exposure;;
Selling -
Current

Future



. •:::^mm •&:{'•• ;-x ••••" ^^!5«"W^ .%®%wmti$$®$$!$
='• ReceptorM;i ;;}¥i^''.:- ^ >:WMedlavi:l- ^MedlumV$$^.
Off-sile Residential Groundwatcr User Groundwatcr Groundwater
S'hower Air
Off-sile Recreational User of Gold Creek Groundwaler Surface Water
On-iile Industrial Worker Groundwater Groundwater
Shower Air
On-sile Residential Groundwaler User Groundwiter Groundwater
Shower Air
Off-silt Residential Groundwtter Us«r Groundwater Groundwatcr
Shower Air
Off-site Recreational User of Gold Creek Groundwater Surface Water
ty!&fKW*^-f$t&?XfX:**f^-8-?'*iy>**i'?fl
:Ss\«;>*rasw;Mis':s-.''K**s;y«Jsi><'^:K'.»;».*''»'
%&$?&^y$^m$&&&&i%^*&
;;&*fo
Ingestion
Dermal ConUct
Inhalation While Showering
Ingestion
Dermal ConUct
Ingestion
Dermal ConUct
Inhalation While Showering
Ingeslion
Dermal ConUct
Inhalation While Showering
Ingeslion
Dermal ConUct
Inhalation While Showering
Ingeslion
Dermal Contact
jRtitiined For
;•:.•:••>::;:«•;;> *\ <<•'•**• ',-•••'• '•»;-•
lEjiitot^i
SYY'ea/Nblill
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
No
[^w^^-y^^^^^^K^^'r
W&S^^^^1^'^^^^.:^
RjitioQilc For Elimination
Incomplete exposure pathways.
Groundwater plume hu not reached
dosmestic wells.
Incomplete exposure pathways.
Groundwatcr plume bu not reached
turUce water.
Dermal conUct and inhalation of
volatile* during showering seems
unlikely at th« site.
Implausible scenario.
Site is expected to remain industrial
in the future.
Incomplete exposure pathways.
Groundwater plume is not expected
to migrate to ofiEiite domestic wells.
Incomplete exposure pathways.
Groundwatcr plume is not expected
to migrate to surface water.

-------
                            TABLE  4
         CANCER SLOPE FACTORS AND REFERENCE DOSES
                  FOR CHEMICALS-OF-CONCERN
               CARROLL &DUBIES STJPERFUND SITE
                    PORT JERVIS, NEW YORK

Clieniic*tof-Con«rn";'''-' -,•.:,•-',?
Volatile Organic CoupovuH
Vinyl Chloride
Chloroethane
1,2-Dichloroethene
Chloroform
Trichloroethene
Benzene
TetrachlorDethene
Toluene
Chlorobenzene
ithylbenzene
Total Xvlenes
SemJ-Vbla tiles Organic Compounds
Phenol
1 ,2-DichJorobenzene
1 ,4-Dichlorobenzene
2-Methylphenol
4-MethyIphenol
[sophorone
Naphthalene
2-Methylnaphthalene
Di-n-butylphthalate
Diethylphthalate
Di-n-ocrylphthalate
Meisili" ' * -"
Aluminum
Arsenic
Barium
Beryllium
Chromium (1)
Copper
Lead
Selenium
Silver
Vanadium
Zinc

; {m^/Ke/dmyy
^-y^-.'.X'^'-
—
0.4 N
0.009 H
0.01 I
0.006 N
—
0.01
0.2
0.02
0.1
2
, , .<< , " .,
0.6
0.09
—
0.05 i
0.005 H
0.2 I
0.04 N
-
0.1 i
O.S i
0.02 H
.' >
1 N
0.0003 i
0.07 i
0.005 i
0.005 i
0.037 H
—
0.005 i
0.005 i
0.007 H
0.3 i

'mt^Q^dayi-i
".j-Jl'VrV ~"&
1.9 H
0.0029 N
-
0.0061 i
0.011 N
0.029 i
0.052 M
—
—
-
-
,*% " > „ s "^
—
-
0.024 H
-
-
0.00095 i
-
-
-
-
—
~ - , '
—
1.5 i
-
4.3 I
-
-
—
-
—
—
-
:,Evidence>
'£?$,'?• ;• '''>
;•,-•.'' '' x -"
A
C-B2
~
B2
C-B2
A
C-B2
D
D
D
D
t~< ' '*.' t >
D
D
C
C
C
C
D
—
D
D
—

_
A
—
B2
A
D
B2
D
D
—
D
Notes:
 — Indicates that no criteria is available.
 I - Integrated Risk Information System (IRIS), January 1996.
 H -Health Effects Assessment Summary Tables (HEAST), FY-1995. Annual and Supplement No. 1.
 N - National Center for Environmental Assessment (NCEA).
 (1)- Values presented are for Chromium VI.

-------
                        TABLE £

    SUMMARY OF CANCER RISKS AND HAZARD INDICES FOR
             INDUSTRIAL WORKERS EXPOSED TO
GROUNDWATER FROM OUTWASH , TELL, AND BEDROCK AQUIFERS
             CARROLL & DUBIES SUPERFUND SITE
                  PORT JERVIS, NEW YORK
" " - "<•><•<



vocj* ~< *
Vinyl Chloride
Chloroethane
1 ,2-Dichloroethene(total)
Chloroform
Trichloroethene
benzene
Tetrachloroethene
Toluene
Chlorobenzene
Ethylbenzene
Total Xvlenes'
Total VOCs
Semi^VOCs - '--'•'•' -
Phenol
1 ,2-D ichlorobenzene
[ ,4-D ichlorobenzene
2-Methylphenol
4-Methylphenol
isophorone
SFaphthalene
2-Methylnaphthalene
Di-n-butylphthalate
Diethylphthalate
Di-n-octylphthalate
Total Semi-VOCs __,
WetaJiv<-:.V.i:'--:;U •' '•••- \w-r#vr ':-• •
Aluminum
Arsenic
Barium
Beryllium
Chromium
Copper
Lead
Selenium
Silver
Vanadium
Zinc
Total Metals
TOTAL
* V ^f

•, s *""
Cinctr Rbk 	
' «
5.0E-05
7.2E-08
NA
1.5E-07
3.0E-07
2.1E-05
1.8E-06
NA
NA
NA
NA
7.4E-05
•v;.;-:.::.-:,:.;.'::.;:' : •
NA
NA
1.7E-07
NA
NA
2.5E-08
NA
NA
NA
NA
NA
1.9E-07

NA
5.9E-05
NA
3.8E-06
NA
NA
NA
NA
NA
NA
NA
6.2E-05
1.4E-04
^ v

^Percent **-.,'
<• f V
" - Cin.ctr Rbk1
^ - > -
37.00%
0.05%
NA
0.11%
0.22%
15.38%
1.31%
NA
NA
NA
NA
54.06%
^ -.
NA
NA
0.12%
NA
NA
0.02%
NA
NA
NA
NA
NA
0.14%
•'•'•. •.<' .'••<•••••'.• '••• ':•• ••••••••
NA
43.04%
NA
2.75%
NA
NA
NA
NA
NA
NA
NA
45.80%
100%
ft ^
" \ *•
•>•> Chronic > -
-------
u
u
a.
5
01
o
                                                                                   TABLE 6
                                                       CAPITAL AND O&M COST ESTIMATE FOR ALTERNATIVE 2
                                                   INTRINSIC BIODEGRADATION WITH INSTITUTIONAL CONTROLS
                                Task
"_""	| (. <&aijtily_J.'. .V.'}!!l."L' UnU c<>sl  I'TiMal Cost") [	"  _""	Notes'	I1....!.I..
                I . Initial Latiorrilory Study,
                Sample Collection
                Study
                               Subtotal
                I. Legal Costilor. Land- anil    '.'.•  '••;;::
                 aod («'rounilwi(cr-llsc Ucstrictionis; V."
                5|>eijaj nn.< beyond Uiosc mxcssary for OU I
                                                       Suhunal - One-Time Expenditure	|_^  $75,(XX)|
                3: Knyifoririicntal SArtipling       "''•> '•
                 'iroundwnier San>pling and AJialysis	
                               Subiobil
 Animal .Summary reports
«               Subtotal
         	28_	I   \vclls__   $1.000  J  $28.000
                                           $28.000
                                                                       LS   I   $30.000   I  S30.UOO
                                                                                         _S30,000
                                                                                     Organic :uia[y_sis of 2 upRrad'cnt and 12 Jtmtigradiem wells
                                                      Annual cost Tor unnual reporting to suntrnaiize above analyticnl
                                                       Subtotal (Annuiil O&M)
                                                       Total Net Presmit Value (@ 12% ROR)
                                             S58,(XX)
                                            S2&4.077
O1

o

(L

-------
        APPENDIX III
ADMINISTRATIVE RECORD  INDEX
             32

-------
                        CARROLL AND DUBIES
                         OPERABLE  UNIT TWO
                   ADMINISTRATIVE RECORD FILE
                        INDEX OF DOCUMENTS
3.0  REMEDIAL  INVESTIGATION

3.4  Remedial  Investigation Reports

P.   300001 -  Report:  Addendum to  Supplemental Hydrogeologic
     300245    Remedial Investigation;   Results of  Field
               Investigation/  at the Carroll  and Dubies Site,
               During April/  1995, prepared by Remediation
               Technologies,  Inc., prepared for Mr.  Jonathan A.
               Murphy, Lester,  Schwab,  Katz,  Dwyer,  and Mr.
               Robert J. Glasser,  Gould and Wilkie,  August 4,
               1995, revised November 1,  1995.

P.   300246 -  Report:  Supplemental Hydrogeologic  Remedial
     300579    Investigation,  Carroll and Dubies Superfund Site,
               Port Jervis,  New York,  prepared by Remediation
               Technologies,  Inc., prepared for Mr.  Jonathan A.
               Murphy, Lester,  Schwab,  Katz,  Dwyer,  and Mr.
               Robert J. Glasser,  Gould and Wilkie;  April 7,
               1995.

P.   300580 -  Report:  Exposure Pathway Analysis Report, Carroll
     300604    and Dubies  Site,  Port Jervis,  New York, prepared
               by Remediation Technologies, Inc., prepared for
               Mr. Jonathan A.  Murphy,  Lester, Schwab, Katz,
               Dwyer, and  Mr.  Robert J.  Glasser, Gould and
               Wilkie; March 3,  1995.
4.0  FEASIBILITY STUDY

4.2  Feasibility Study Work Plans

P.   400001 -  Letter to Ms. Sharon Trocher, U.S. EPA, Region II,
     400090    from Mr. Robert Block, Principal, RETEC, and Mr.
               David Morgan, Associate, RETEC, re: Revisions to
               Groundwater Modeling Workplan, October 9,  1995.
               (Attached:  1. "Response to Comments from  EPA
               Dated September 18, 1995," September 18, 1995.  2.
               "Response to Comments from EPA Dated October 2,
               1995," October 2, 1995.  3. Plan:  Groundwater
               Modeling Workplan, Carroll and Dubies Superfund
               Site, undated.)

-------
4.3  Feasibility  Study Reports

P.   400091  -  Report:  Groundwater Modeling Report,  Carroll  and
     400349    Dubies Superfund Site, Port  Jervis, New  York,
               prepared by Remediation Technologies,  Inc.,
               prepared for Mr. Jonathan A. Murphy,  Lester,
               Schwab, Katz, Dwyer, and Mr. Robert J. Glassner,
               Gould and Wilkie, January 1996.

P.   400350  -  Report:  Feasibility Study for the Groundwater
     400507    Operable Unit, Carroll and Dubies Site,  prepared
               by Remediation Technologies, Inc., prepared  for
               Mr. Jonathan A. Murphy, Lester, Schwab,  Katz,
               Dwyer, and Mr. Robert J. Glassner, Gould and
               Wilkie, May 1996.
7.0  ENFORCEMENT

7.2  Endangerment Assessments

p.   700001 -  Report:  Baseline Risk Assessment, Carroll  and
     700534    Dubies Superfund Site, Port Jervis, New York,
               prepared by Remediation Technologies,  Inc.,
               prepared for Mr. Jonathan A. Murphy, Lester,
               Schwab, Katz, Dwyer, and Mr. Robert J. Glassner,
               Gould and Wilkie, April 3, 1996.

7.8  Correspondence

P.   700535 -  Letter to Ms. Sharon Trocher, U.S. EPA, Region
     700838    II, from Jonathan A. Murphy, Esq., Lester,  Schwab,
               Katz & Dwyer, re:  New York  (Carroll & Dubies)  v.
               Kolmar Laboratories, Inc., November 9, 1995.
               (Attached:  1. Zoning Map; 2. Report:  Zoning
               Laws, prepared by Town o'f Deerpark, New York,
               adopted January 8, 1990, amended September  17,
               1990, December 7, 1992, August 2,  1993, and
               October 4, 1993; 3. Plan:  Master  Plan  (Or
               Comprehensive Development Plan), Town of Deerpark,
               Orange County, New York, June, 1989, prepared by
               Garling Associates, Consulting Planners, prepared
               for the Town of Deerpark, Orange County, New York,
               adopted by the Town Board, September 11, 1989;  4.

-------
               Report:   Subdivision Regulations of the Town of
               Deerpark, County of Grange/ State of New York,
               prepared by Ms, Shirley Zeller/ Town Clerk, Town
               of Deerpark, Orange County, adopted by the Town of
               Deerpark, Town Board, December 20, 1993.
10.0 PUBLIC PARTICIPATION

10.9 Proposed Plan

P.   10.00001- Plan:     Superfund Proposed Plan, Carroll and
     10.00020  Dubies Sewage Disposal Inc., Town of Deerpark,
               Orange County, New York, prepared by U.S. EPA,
               Region II, August 28,1996.

-------
              CARROLL & DUBIES SEWAGE DISPOSAL SITE
                        OPERABLE UNIT TWO
                ADMINISTRATIVE RECOFD FILE UPDATE
                        INDEX OF  DOCUMENTS
3.0  REMEDIAL INVESTIGATION

3.1  Sampling and Analysis Plans

P.   300605-   Report:  Summary of Laboratory Data Sampling
     300610    Event, Carroll & Dubies Sewage Disposal Site, Port
               Jervis. New York. July 15-26. 1996.
5.0  RECORD OF DECISION

5.1  Record of Decision

P.   500001-   Record of Decision - Carroll & Dubies Sewage
     500250    Disposal, Inc., Superfund Site, Town of Deerpark,
               Orange County, New York, September 30, 1996.


6.0  STATE COORDINATION

6.3  Correspondence

P.   600001-   Letter to Mr. Richard Caspe, Director, Emergency &
     600001    Remedial Response Division, U.S. EPA, Region II,
               to Mr. Michael J. O'Toole, Jr., Director, Division
               of Environmental Remediation, N.Y.S. Department of
               Environmental Conservation, re: Carroll & Dubies
               OU2 Proposed Remedial Action Plan, August 22,
               1996.
10.0 PUBLIC PARTICIPATION

10.2 Community Relations Plan

P.   10.00021- List of interested parties, Carroll & Dubies
     10.00032  Sewage Disposal Superfund Site, Port Jervis, New
               York. (Note:    This document is CONFIDENTIAL. It

-------
               can be located at the. Superfund Records Center,
               290 Broadway, 18th floor, New York, New York,
               10007-1866.)

10.3 Public Notices

P.   10.00033- Public Notice: "The U.S. Environmental Protection
     10.00033  Agency (EPA) Invites Public Comment on its
               Proposed Plan for   remediating contaminated
               groundwater at the Carroll & Dubies Sewage
               Disposal Superfund Site, Port Jervis, New York,"
               prepared by U.S. EPA, Region II.
Note: The documents listed on the attached index for the Carroll
& Dubies Sewage Disposal Site Administrative Record file for
Operable Unit 1 (OU1) are hereby incorporated into this
Administrative Record file Operable Unit 2 (OU2) by reference.

-------
                      CARROLL S DUBIES SITE
                        OPERABLE UNIT ONE
                    ADMINISTRATIVE  RECORD PILE
                        INDEX OP  DOCUMENTS
1.0  SITE IDENTIFICATION

1*4  Site Investigation Reports.

P.   100001 -  Report:  Engineering Investigations at Inactive
     100322    Hazardous Waste Sites in the State of New York.
               Phase II Investigations, Carroll and Dubies Site,
               Town of Deerpark.  Orange County, New York.
               prepared by Wehran Engineering, P.C., prepared for
               Project Sponsors for Submission to Division of
               Solid and Hazardous Waste, New York State
               Department of Environmental Conservation, February
               1987.

P.   100323 -  Report:  Preliminary Investigation of the Carroll
     100429    and Dubies Site. Citv of Port Jervis. Orange
               County. New York.  Phase I Summary Report, prepared
               by Ecological Analysts, Inc.,  prepared for New-
               York State Department of Environmental
               Conservation, November 1983.
3.0  REMEDIAL INVESTIGATION

3.3  Work Plans

P.    300001 -  Report:  Health & Safety Plan. Remedial
     300053    Investigation/Feasibility Study. Carroll & Dubies
               Site. Port Jervis. New York, prepared by Blasland
               & Bouck Engineers, P.C., January 1991 (Revised
               June 1991) ..

P.    300054 -  Report:  Quality Assurance Project Plan, Remedial
     300250    Investigation/Feasibility Study. Carroll & Dubies
               Site. Port Jervis. New York, prepared by Blasland
               & Bouck Engineers, P.C., January 1991 (Revised
               June 1991).

P.    300251 -  Report:  Work Plan. Remedial Investigations/
     300325    Feasibility Study. Carroll & Dubies Site. Port
               Jervis. New York, prepared by Blasland  & Bouck
               Engineers, P.C., November 1990.

-------
4.6  Correspondence

P.   400676  -   Letter  to  Mr.  Doug  Garbarini, Carroll- and Dubies
     400681     Site  Contact,  U.S.  EPA,  from Ms. Brenda B.
                McDevitt, .Environmental  Scientist, Remediation
                Technologies,  Inc., and  Mr. Kevin R. Jones,
                Associate,  Remediation. Technologies, Inc., re:
                ARARs Summary,  December  21, 1994.   (Attached:
                Table 2-1,  Carroll  and Dubies Site. Port Jervis,
                New York.  Action-Specific ARARs. undated.)

P.   400682  -   Letter  to  Ms.  Sharon Troch.er, Carroll and Dubies
     400684     Site  Project Manager, U.S. EPA, from Ms. Brenda B.
                McDevitt,  Environmental  Scientist, Remediation
                Technologies,  Inc., re:  Cost Estimate for Off-
                Site  Incineration of Lagoon 7 Material, December
                9, 1994.   (Attached:  1. Table 2-1A. Carroll &
                Dubies  Site, Port Jervis, New York. Detailed Cost
                Estimate.  Slurrv Treatment for Lacroon 7 Soil.
                undated; 2. Table 2-1B,  Carroll & Dubies Site,
                Port  Jervis, New York, Detailed Cost Estimate,
                Incineration for Lagoon  7 Soil, undated.).
10.0 PUBLIC PARTICIPATION

10.4 Public Meeting Transcripts

P.   1000060 - Transcript:   "Public Meeting for the Carroll  and
     1000157   Dubies Superfund Site, Port Jervis, New York,"
               transcribed by Rockland and Orange Reporting,
               transcribed on August 23, 1994.

10.9 Proposed Plan

P.   1000158 - Report:  Superfund Proposed Plan. Carroll and
     1000169   Dubies Sewage Disposal Inc., Town of Deerpark.
               Oranae Countv, New York, prepared by U.S. EPA -
               Region II, August 1994.

-------
P.   301366 -  Letter to Ms. Sharon Trocher, Eastern New
     301368    York/Caribbean Remedial Action Branch.,. Region. II,
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,
               Executive Vice President, Blasland &-Bouck
               Engineers, P.C., re:  response to the January 5,
               1993 letter from Doug Garbarini and subsequent
               telephone conversations which have modified some
               of the items addressed in~;that particular letter,
               January 8, 1993.

P.   301369 -  Letter to Mr. Tyler E.  Gass, C.P.G., Vice
     301372    President, Blasland- & Bouck Engineers, P.Cv, frcm-
               Mr. Doug Garbarini, Chief,  Eastern New
               York/Caribbean Superfund Section I, Region II,
               U.S. EPA, re:  the New York State Department of
               Environmental Conservation's and the U.S.
               Environmental Protection Agency's comments on the
               December 16, 1992 scope of work for the four
               tentatively identified former lagoons (TIFLs)
               located adjacent to the Carroll and Dubies
               property, January 5, 1993.   (Attached:  Figure 1,
               New Potential Source Area,  Site Hap and Proposed
               Sampling Locations, prepared by Blasland & Bouck
               Engineers, P.C., October 19, 1992.)

P.   301373. —  Letter to Mr.. Doug Garbarini, Eastern New
     301378    York/Caribbean Remedial Action Branch, Region II,
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,
               Executive Vice President, Blasland & Bouck
               Engineers, P.C., re:  submission of various
               documents to Ms. Sharon Trocher regarding the
               tentatively identified former lagoons (TIFLs),  and
               a response to, Attachment. 1 of Mr. Garbarini.1 s
               November 20, 1992 letter entitled, "Additional
               Issues to be Included in the Supplemental Work
               Proposed on October 13, 1992", December 29, 1992.
               (Attached:  Figure 1, prepared by Blasland & Bouck
               Engineers, P.C., (undated).)

P.   301379 -  Letter to Ms. Sharon Trocher, Eastern New
     301383    York/Caribbean Remedial Action Branch, Region II,
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,
               Executive Vice President, Blasland & Bouck
               Engineers, P.C., re:  potential investigation of
               possible adjacent lagoon area, Carroll and Dubies
               Site, December 16> 1992.   (Attached:..  Figure. 1,
               New Potential Source Area. Site Map and Proposed
               Sampling Locations, prepared.by Blasland & Bouck
               Engineers, P.C., October 19, 1992.)

-------
301384 -  Letter to Mr.  Tyler E.  Gass,  C.P.G.,  Vice
301392    President, Blasland & Bouck Engineers,  P.C.,  from
          Mr. Doug Garbarini, Chief,  Eastern New
          York/Caribbean Superfund Section I, Region II,
          U.S. EPA, re:   response to the October 13, 1992
          letter which transmitted the  proposed schedule for
          completing the Remedial Investigation and
          Feasibility Study (RI/FS)  and the proposed scope
          of supplemental work for the  Carroll  and Dubies
          Superfund Site, November 20,  1992.  (Attached:   1.
          Enclosure 1, Report:  Additional Issues to be
          Included in the Supplemental  Work Proposed on
          October 13. 1992; 2. Figure 1, prepared by
          Blasland & Bouck Engineers, P.C., (undated);  3.
          Figure 2, Rock Aquifer Monitoring Well.
          (undated).)

301393 -  Letter to Ms.  Sharon Trocher, Eastern New
301398    York/Caribbean Remedial Action Branch,  Region II,
          U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,
          Executive Vice President,  Blasland &  Bouck
          Engineers, P.C., re:  Carroll & Dubies Site,  Port
          Jervis, New York, Supplemental Investigation,
          Scope of Work, October 13,  1992.  (Attached:   Site
          Map and Proposed Supplemental Sampling locationsf
          prepared by Blasland & Bouck, Engineers, P.C.,
          October 6, 1992.)

301399 -  Letter to Ms.  Vita DeMarchi,  Senior Project
301400    Hydrogeologist, Blasland & Bouck Engineers, P.C.,
          from Ms. Sharon Trocher, Remedial Project Manager,
          Eastern New York & Caribbean  Section I, Region II,
          U.S. EPA, re:   response to Ms. DeMarchi's December
          6, 1991 letter proposing the  analytical parameters
          for the second round of groundwater samples to be
          obtained from the Carroll and Dubies Site,
          December 13, 1991.

301401 -  Letter to Mr.  Tyler E. Gass,  C.P.G.,  Project
301403    Director, Blasland & Bouck Engineers, P.C., from
          Ms. Sharon L.  Trocher, Remedial Project Manager,
          Eastern New York and Caribbean Section I, Region
          II, U.S. EPA,  re:  summary of the agreement
          reached between Mr. William McCune and Ms. Sharon
          L. Trocher during telephone conversations
          occurring on September 17 and 18, 1991, September
          18, 1991.

-------
P.   301404 -  Letter to Ms. Sharon Trocher, Eastern New
     301408    York/Caribbean Remedial Action Branch, Region II,
               U.S. EPA, from Mr. Tyler E. Gass, c.P.G.,  Vice
               President, Blasland & Bouck Engineers, P.O., re:
               proposed methods of resolving the outstanding
               concerns raised in Ms. Trocher's letter dated
               August 21, 1991 and-the subsequent meeting of
               September 5, 1991, September 16, 1991.

P.   301409 -  Memorandum to Mr. Tyler E. Gass, C.P.G., Project
     301410    Director, Blasland & Bouck Engineers, P.C., and
               Ms. Debra L. Rothenberg, Esq., Kinston & Strawn,
               from Ms. Sharon Trocher, Remedial Project Manager,
               Region II, U.S. EPA,  re:  Carroll and Dubies
               Site - summary of 9/5/91 meeting, September 9,
               1991.

P.   301411 -  Letter to Mr. Tyler E. Gass, C.P.G., Project
     301413    Director, Blasland & Bouck Engineers, P.C., from
               Ms. Sharon L. Trocher, Remedial Project Manager,
               Region II, U.S. EPA,  re:  concerns of the U.S. EPA
               and the New York State Department of Environmental
               Conservation regarding the sampling depth of the
               sludge samples obtained from lagoons 1 and 2, and
               the limited recharge rate of monitoring well OW-4,
               August 21, 1991.

P.   301414 -  Letter to Mr. Tyler E. Gass, C.P.G., Project
     301415    Director, Blasland & Bouck Engineers, P.C., from
               Ms. Sharon Trocher, Remedial Project Manager,
               Eastern New York and Caribbean Section I,  Region
               II, U.S. EPA, re:  summary of discussion between
               Mr. Robert Patchett of Blasland & Bouck Engineers
               and Mr. Robert Cunningham, an Environmental
               Protection Agency representative, concerning the
               development of monitoring wells for the Carroll
               and Dubies Superfund Site, August 9, 1991.
               (Attached:  Transmission Confirmation Report,
               August 12, 1991.)

P.   301416 -  Letter to Ms. Sharon Trocher, Eastern New
     301417    York/Caribbean Remedial Action Branch, Region II,
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G.,  Vice
               President, Bias-land & Bouck Engineers, P.C., re:
               an addendum to the Work Plan and Sampling and
               Analysis Plan- (SAP) for. the Carroll. and,. Dubies.
               Superfund Site in Port Jervis, New York, August 7,
               1991.

-------
P.   301418 -  Letter to Ms. Sharon Trocher, Eastern New
     301419    York/Caribbean Remedial Action Branch, Region II,
               U.S. EPA, from Mr. Tyler E. Gass, C.P.G., Vice
               President, Blasland & Bouck Engineers-, P.C., re:
               acknowledgement of U.S. EPA's letter dated July
               29, 1991 granting approval for use of mud rotary
               drilling method during advancement of the
               boreholes for the till monitoring wells, July 30,
               1991.

P.   301420 -  Letter to Mr. Tyler E. Gass, C.P.G., Project
     301421    Director, Blasland & Bouck Engineers, P.C., from
               Ms. Sharon Trocher, Remedial Project Manager,
               Eastern New York & Caribbean Section I, Region II,
               U.S. EPA, re:  approval of the use of mud rotary
               drilling techniques for the construction of the
               till monitoring wells, July 29, 1991.

P.   301422 -  Letter to Ms. Sharon Trocher, Eastern New
     301425    York/Caribbean Remedial Action Branch, Region II,
               U.S. EPA, from Mr. William T. McCune, Senior
               Project Geologist II, Blasland & Bouck Engineers,
               P.C., re:  drilling methods considered for use
               in drilling three glacial till boreholes at the
               Carroll and Dubies Site in Port Jervis, New
               York, July 26, 1991.
4.0  FEASIBILITY STUDY

4.3  Feasibility study Reports

P.   400001 -  Letter to Ms. Sharon Kivowitz, Office of Regional
     400096    Counsel, U.S. EPA, from Ms. Debra L. Rothberg,
               Attorney at Law, and Mr. Robert J. Glasser, Gould
               & Wilkie, re:  submission of the Technical
               Memorandum on behalf of Respondents, Kolmar
               Laboratories, Inc. and Wickhen Products, Inc.,
               July 18, 1994.   (Attached Report:  Technical
               Memorandum. Alternative Remedial Technology
               Evaluation. Carroll and Dubies Site. Port Jervis,
               New York, prepared by Remediation Technologies,
               Inc., prepared for Mr. Robert J. Glasser, Gould
               and Wilkie, and Ms. Debra L. Rothberg, July 15,
               1994.)

P.   400097 -  Report:  Technical Memorandum, Carroll & Dubies
     400113    Site. Port Jervis. New York, prepared by Blasland,
               Bouck & Lee, Inc., February 1994  (Revised March
               1994) .

-------
P.   400114 -  Report:  Source Area Feasibility Study, Carroll &
     400438    Dubies Site. Port Jervis,  New York,  prepared by
               Blasland, Bouck & Lee,  Inc. ,  January 1994 (Revised
               May 1994; Revised July 1994).

4.6  Correspondence

P.   400439 -  Letter to Ms.  Sharon L.  Trocher, Remedial Project
     400440    Manager,  Eastern New York/Caribbean Section I,
               Region II, U.S. EPA, from  Mr. Tyler E.  Gass,
               C.P.G, Ph.G.,  Executive  Vice President, Blasland,
               Bouck & Lee, Inc.,  re:   Carroll & Dubies Site,
               Port Jervis, New York,  Source Area Feasibility
               Study, June 17, 1994.

P.   400441 -  Letter to Ms.  Sharon Trocher, Remedial  Project
     400446    Manager,  Eastern New York/Caribbean Section I,
               Region II, U.S. EPA, from  Mr. Tyler E.  Gass,
               C.P.G.S., Executive Vice President,  Blasland,
               Bouck & Lee, Inc.,  re:   Source area feasibility
               study, Carroll & Dubies  Site, Port Jervis, New
               York/ March 23, 1994.   (The following are
               attached:  1.  Table 1,  Carroll & Dubies Site,  Port
               Jervis, New York,  Comparison of Volume  of Source
               Area Materials Above Cleanup Levels Proposed
               in Source Area Feasibility Study vs.  U.S. EPA
               Proposed Alternative Approaches, (undated); 2.
               Table 2,  Carroll &  Dubies  Site, Port Jervis, New
               York, Soil Sample Data  Above the Source Area
               Feasibility Studv Inorganic Cleanup Levels but not
               Above U.S. EPA Alternative Inorganic Cleanup
               Levels, (undated);  3.  Figure 1, Carroll and Dubies
               Site, Port Jervis,  New York,  Horizontal and
               Vertical Extent of  Source  Area Materials Above
               Cleanup Levels Usina U.S.  EPA Alternative 1.
               prepared by Blasland,  Bouck & Lee,  Inc., March
               1994; 4.  Figure 2,  Carroll & Dubies Site, Port
               Jervis, New York, Horizontal and Vertical Extent
               of Source Area Materials Above Cleanup Levels
               Using U.S. EPA Alternative 2. prepared by
               Blasland, Bouck & Lee,  Inc.,  March 1994.)

-------
400447 -  Letter to Ms.  Sharon Trocher,  Eastern New
400450    York/Caribbean Remedial Action Branch, Region II,
          U.S. EPA, from Mr.  Tyler E.  Gass,  C.P.G.,
          Executive Vice President,  Blasland & "Bouck
          Engineers, P.C.,  re:  proposed soil cleanup values
          for priority pollutant inorganics  for the Carroll
          & Dubies Site, November 30,  1993.   (Attached:  1.
          Table 1, Carroll  &  Dubies Site, Port Jervis New
          York, Proposed Priority Pollutant  Inorganic
          Cleanup Levels, (undated);  2.   Table 2, Carroll &
          Dubies Site, Port Jervis,  New York, Risk-Based
          Preliminary Remediation Goals (PRGs)  for
          Inorganics in  Soils, (undated).)

400451 -  Letter to Ms.  Sharon L. Trocher, Remedial Project
400454    Manager, Eastern  New York/Caribbean Section 1,
          Region II, U.S. EPA, from Mr.  Tyler E. Gass,
          C.P.G., PHg, Executive Vice President, Blasland &
          Bouck Engineers,  P.C.,  re:   addendum to
          correspondence dated September 24, 1993 pertaining
          to remedial action  objectives,  Carroll & Dubies
          Site, October  1,  1993.

400455 -  Letter to Ms.  Sharon Trocher,  Eastern New
400466    York/Caribbean Remedial Action Branch, Region II,
      •.   U.S. EPA, from Mr.  Tyler E.  Gass,  C.P.G., PHg,
          Executive Vice President,  Blasland & Bouck
          Engineers, P.C.,  re:  proposed approach for
          establishing cleanup criteria to determine the
          extent of source  area materials that need to be
          addressed as part of the Carroll & Dubies Site
          remedy, September 24,  1993.   (Attached:  1.
          Memorandum to  Regional Hazardous Waste Remediation
          Engineers, Bureau Directors, and Section Chiefs,
          from Mr. Michael  J.  O'Toole, Jr.,  Director,
          Division of Hazardous Waste Remediation, New York
          State Department  of Environmental  Conservation,
          re:  division  technical and administrative
          guidance memorandum:  determination of soil
          cleanup objectives  and cleanup levels, November
          16, 1992; 2. Appendix A, Table 4,  Recommended Soil
          Cleanup Objectives   (mq/kg or ppm.) for Heavy
          Metals, (undated);  3.  Conventional. Sediment
          Variables. Total  Organic Carbon (TOO. March
          1986.)
                           8

-------
P.   400467 -
     400468
Letter to Mr. Tyler E. Gass, C.P.G., Vice
President, Blasland & Bouck Engineers, P.C., from
Ms. Sharon L. Trocher, Remedial Project Manager,
Eastern New York/Caribbean Section I,"Region II,
U.S. EPA, re:  the development of soil cleanup
numbers for the Carroll & Dubies Sewage Disposal
Site, May 21, 1993.
7.0  ENFORCEMENT

7.3  Administrative Orders

P.   700001 -  Administrative Order on Consent, in the matter of
     700030    Kolmar Laboratories, Inc.,  and Wickhen Products,
               Inc., Respondents, Index No. II CERCLA - 00202,
               February 8, 1990.  (Attached:  1.  Figure 1, Map:
               Site Location Man. Carroll  and Dubies Site,
               (undated); 2. Appendix II,  Outline of
               Modifications to EPA RI/FS  Work Plan, Carroll and
               Dubies Site,  (undated); 3.  Map:  Field
               Investigation Location Map, prepared by Blasland &
               Bouck Engineers, P.C., (undated).)

7.7  Notice Letters and Responses - 104e's
P.   700031
     700032
     700033
     700037
Notice letter to Honorable R. Michael Worden,
Mayor, City of Port Jervis, from Mr. William
McCabe, signing for Mr. George Pavlou, Acting
Director, Emergency and Remedial Response
Division, Region II, U.S. EPA, re:  notification
that the City of Port Jervis may be a potentially
responsible party of the Carroll & Dubies
Superfund Site, April 22, 1993.

Notice letter to Messrs Joseph Carroll and Gustave
Dubies, Carroll and Dubies Sewage Disposal
Facility, Inc., Mr. Adolf A. Maruszewski,
President, Kolmar Laboratories, Inc., Mr. Richard
G. Holder, President, Reynolds Metal Company, Mr.
Jere D. Marciniak, President, Wickhen Products,
Inc., from Mr. Stephen D. Luftig, Director,
Emergency and Remedial Response Division, Region
II, U.S. EPA, re:  offer to conduct a remedial
investigation and feasibility study at the Carroll
& Dubies Superfund Site, September 25, 1989.

-------
8.0  HEALTH ASSESSMENTS

8.1  ATSDR Health Assessments

P.   800001 -  Report:  Preliminary Health Assessment for Carroll
     800025    & Dubies. Port Jervis. Orange County. New York.
               prepared by New York State Department of Health
               Under Cooperative Agreement with the Agency for
               Toxic Substances and Disease Registry, July 31,
               1991.


10.0 PUBLIC PARTICIPATION

10.2 Community Relations Plans

P.   10.00001- Report:  Community Relations Plan. Carroll and
     10.00027  Dubies Sewage Disposal site. Deerpark. Orange
               County. New York, prepared by Alliance
               Technologies Corporation, prepared for U.S. EPA,
               June 14, 1991.

10.6 Fact sheets and Press Releases

P.   10.00028- Fact Sheet:  Superfund Update. Carroll and Dubies
     10.00033  Site. Town of Deerpark. Orange County. New York.
               Fact Sheet #2. Status of Current EPA Remedial
               Activities, at the Carroll and Dubies Site.
               January 1993.

P.   10.00034- Fact Sheet:  Superfund Update. Carroll and Dubies
     10.00039  Site. Town of Deerpark. Orange County. New York.
               Fact Sheet #1. EPA to Conduct Investigation of
               Carroll and Dubies Site. May 1991.

10.10 Correspondence (FOZA)

P.   10.00040- Letter to Ms. Frances Hodson, from Ms. Sharon
     10.00042  Trocher, Remedial Project Manager, Eastern New
               York/Caribbean Section, Region II, U.S. EPA, re:
               response to Ms. Hodson's March 28, 1994 letter
               requesting information on the status of the
               Carroll and Dubies Site, April 22, 1994.
               (Attached:  Letter to Ms. Sharon Trocher, Remedial
               Project Manager, U.S. EPA, from Ms. Frances
               Hodson, re:  request for information regarding the
               Carroll and Dubies Superfund Site, March 28,
               1994.)
                                10

-------
P.   10.00043- Letter to Ms. Frances Hodson,  from Mr.  Doug
     10.00045  Garbarini, Chief, Eastern New  York/Caribbean
               Section I, Region II, U.S.  EPA,  re:   jresponse to
               Ms. Hodson1s September 23,  1992  letter requesting
               an update on the Carroll  and Dubies Superfur.d
               Site, November 16,  1992.   (Attached:   1.  Update
               for the Carroll and Dubies Suoerfund Sire,
               November 1992; 2. Letter  to Mr.  William McCabe,
               Chief, New York/Caribbean Remedial Action Branch,
               Region II, U.S.  EPA,  from Ms.  Frances Hodson, re:
               request for information regarding the Carroll and
               Dubies Superfund Site,  September 23,  1992.)

P.   10.00046- Letter to Ms. Frances J.  Hodson,  from Ms. Sharon
     10.00047  Trocher,  Eastern New York/Caribbean Section I, "
               Region II, U.S.  EPA,  re:   response to Ms. Hodson's
               November 12,  1991 letter  concerning the status of
               the Carroll and Dubies Superfund Site,  November
               17, 1991.   (Attached:   Letter  to Ms.  Sharon
               Trocher,  Remedial Project Manager,  Eastern New
               York/Caribbean Section I,  Region II,  U.S. EPA, re:
               request for information regarding the Carroll and
               Dubies Superfund Site,  November  12,  1991.)
                               11

-------
                      CARROLL & DUBIES SITE
                     OPERABLE UNIT ONE UPDATE
                    ADMINISTRATIVE RECORD  FILE
                        INDEX OF DOCUMENTS
4.0  FEASIBILITY STUDY

4.6  Feasibility Correspondence

P.   400469 -  Fax transmittal to Ms. Sharon Trocher, Remedial
     400474    Project Manager, U.S. EPA, Region II, from K.
               Jones, Remediation Technologies Incorporated, re:
               Cost Estimates for Modified Remedial Alternatives,
               plus LTTD, August 3, 1994.  (Attached:  Cost
               Estimates for Modified Remedial Alternatives,
               (undated).

10.0 PUBLIC PARTICIPATION

10.9 Proposed Plan

P.   10.00048- Plan:  Superfund Proposed Plan, Carroll and Dubies
     10.00059  Sewage Disposal Inc., Town of Deerpark, Orange
               County, New York, prepared by U.S. EPA, Region II,
               August 4, 1994.

-------
                      CARROLL AND DDBIES SITE
                     OPERABLE UNIT ONE UPDATE
                    ADMINISTRATIVE RECORD FILE
                        INDEX OP DOCUMENTS
4.0  FEASIBILITY  STUDY

4.2  Feasibility  Study Work  Plans

P.   400475 -  Plan:   Vapor  Extraction and Bioslurrv Treatability
     400495    Investigation Workplan, Carroll and Dubies Site.
               Port Jervis,  New York, prepared for Mr. Robert J.
               Glasser, Gould and Wilkie, and Ms. Debra L.
               Rothberg, Periconi & Rothberg, P.C., prepared by
               Remediation Technologies, Inc., July 25, 1994.

4.3  Feasibility  Study Reports

P.   400496 -  Letter  to Ms. Sharon Trocher, Carroll and Dubies
     400513    Site Project  Manager, U.S. EPA, from Ms. Brenda B.
               McDevitt, Environmental Scientist, Remediation
               Technologies, Inc., and Ms. Barbara H. Jones,
               Project Engineer, Remediation Technologies, Inc. ,
               re:  Addendum to Treatability Study Report,
               November 8, 1994.  (Attached report:  Addendum to:
               Technology Evaluation Laboratory Treatabilitv
               Study,  Carroll and Dubies Superfund Site, Final
               Report  (October 10, 1994.1. November 8, 1994.

P.   400514 -  Report:  Cost Estimates for Modified Remedial
     400539    Alternatives, prepared for Mr. Robert J. Glasser,
               Gould and Wilkie, and Ms. Debra L. Rothberg,
               Periconi & Rothberg,  P.C., prepared by Remediation
               Technologies, Inc., October 13, 1994.

P.   400540 -  Report:  Technology Evaluation Laboratory
     400675    Treatabilitv  Studv, Carroll and Dubies Superfund
               Site, Final Report, prepared for Mr. Robert J.
               Glasser, Gould and Wilkie, and Ms. Debra L.
               Rothberg, Periconi &  Rothberg, P.C., prepared by
               Remediation Technologies, Inc., October 10, 1994.

-------
              CARROLL & DUBIES SEWAGE DISPOSAL SITE
                        OPERABLE UNIT ONE
                ADMINISTRATIVE RECOPD FILE UPDATE
                        INDEX OP  DOCUMENTS
7.0  ENFORCEMENT

7.3  Administrative Orders

P.   700038-   Letter to Mr. Brian D. Bertonneau, Reynolds Metals
     7'00067    Company, from Ms. Sharon E. Kivowitz, Assistant
               Regional Counsel, Office of Regional Counsel, U.S.
               EPA, Region II, re: attached Administrative Order
               on Consent, II-CERCLA-95-0217, in the Matter of
               the Carroll & Dubies Superfund Site, Reynolds
               Metals Company, Respondent, July 18, 1996.

P.   700068-   Administrative Order for Remedial Design and
     700111    Remedial Action, U.S. EPA Index No. II-CERCLA-95-
               0221, in the Matter of the Carroll & Dubies
               Superfund Site, September 29, 1995.

P.   700112-   Administrative Order on Consent, II-CERCLA-95-
     700131    0217, in the Matter of the Carroll & Dubies
               Superfund Site, Reynolds Metals Company,
               Respondent, September 27, 1995.

7.8  Correspondence

P.   700132-   Letter to Mr. Brian D. Bertonneau, Reynolds Metals
     700132    Company, from Ms. Sharon E. Kivowitz, Assistant
               Regional Counsel, Office of Regional Counsel, U.S.
               EPA, Region II, re: Carroll & Dubies Superfund
               Site, Administrative Order on Consent, II-CERCLA-
               95-0217, July 18, 1996.
      ;
P.   700133- .  Letter to Mr. Robert J. Glasser, Gould &
     700135    Wilkie,  and Mr. Jonathan Murphy, Lester,
               Schwab,  Katz, & Dwyer, from Ms. Sharon E.
               Kivowitz, Assistant Regional Counsel, Office of
               Regional Counsel, U.S. EPA, Region II, re: Carroll
               & Dubies Superfund Site Response to Comments on
               Administrative Order on Consent II-CERCLA-95-0217,
               July 16, 1996.

-------
P.   700136-   Letter to Ms. Sharon E. Kivowitz, Esq., Assistant
     700140    Regional Counsel, U.S. EPA, Region II, from Mr.
               Robert J. Glasser, Gould & Wilkie and Mr.
               Jonathan Murphy, Lester Schwab Katz & Dwyer,
               re: Carroll & Dubies Superfund Site; U.S. EPA
               Index No. II-CERCLA-95-0221, March 19, 1996.

-------
        APPENDIX IV





STATE LETTER OF CONCURRENCE
             33

-------
New York State Department of Environmental Conservation
50 Wolf Road, Albany, New York 12233
                                               -__  ^                               Michael D. Zagata
                                               SEP  30  1998                         Commissioner
   Mr. Richard Caspc
   Director
   Emergency & Remedial Response Division
   U.S. Environmental Protection Agency
   Region II
   290 Broadway
   New York, NY 10007-1866
   Dear Mr. Caspe:
                             Re: Carroll & Dubics, OU2, ID No. 3360)5
                                 Record of Decision (ROD)
          The New York State Department of Environmental Conservation has reviewed the ROD for the
   above-referenced site anil finds il acceptable. It is understood to include the following provisions:

   I.      Natural attenuation of the groundwaler to below NYS groundwater standards for organics.

   2.      Institutional controls restricting the use of groundwater in the area of the groundwater plume.

   3-      Monitoring of the groundwater to ensure improvement in gronndwatcr quality.

   4.      Sediment sampling lo ensure contaminants do not reach Gold Creek.

          Please contact Sal Ervolina at (518) 457-7924 if you have any questions.
                                            Michael X/OToole, Jr.
                                            Director
                                            Division of Environmental Remediation
   cc:     D. Gtirbarini/M. Jon, USEPA-Rcgion II

-------
                            APPENDIX V

                      RESPONSIVENESS SUMMARY

            CARROLL AND DUBIES SEWAGE DISPOSAL, INC.,
                          SUPERFUND SITE
                    GROUNDWATER  OPERABLE UNIT

INTRODUCTION

A responsiveness summary is required by the National  Contingency
Plan  (NCP) at 40 CFR  §300.430(f)(3)(F).  It provides  a  summary of
citizens' comments and concerns  received during the public
comment period, and the United States  Environmental Protection
Agency's  (EPA's) and  the New York State Department of
Environmental Conservation's  (NYSDEC's) responses to  those
comments and concerns.  All comments summarized in this document
have been considered  in EPA's and NYSDEC's final decision for the
selected remedy for the Carroll  and Dubies Sewage Disposal site
groundwater operable  unit  (OU2).

SUMMARY OF COMMUNITY  RELATIONS ACTIVITIES

Community involvement at the Site has  been relatively strong.
EPA has served as the lead Agency for  community relations and
remedial activities at the Site.

The Proposed Plan for the groundwater  contamination beneath and
downgradient of the Carroll and  Dubies Site was released to the
public for comment on August 28, 1996.  This document, together
with the Remedial Investigation  report, the Baseline  Risk
Assessment and other  reports, were made available to  the public
in the Administrative Record file at the EPA Docket Room in
Region II, New York, and in the  information repository at the
Deerpark Town Hall, Drawer A, Huguenot, New York and  the Port
Jervis Public Library, 138 Pike  Street, Port Jervis,  New York.
The notice of availability for the above referenced documents was
published in the Times Herald Record on September 10, 1996.  A
similar notice was sent to the site mailing list on August 28,
1996.  The public comment period on these documents was open from
August 28, 1996 to September 27, 1996.

-------
On  September  11,  1996,  EPA  conducted a public meeting  at  the  Port
Jervis High School,  Port  Jervis, New York to discuss the  Proposed
Plan  for  Operable Unit  Two  and to provide an opportunity  for  the
interested parties to present oral comments and questions to  EPA.

Attached  to the Responsiveness Summary are the following
Appendices:

      Appendix A -   Proposed Plan

      Appendix B -   Public  Notice

      Appendix C -   September 11, 1996 Public Meeting Attendance
                     Sheets

      Appendix D -   September 11, 1996 Public Meeting Transcript

      Appendix E -   Letters Submitted During the Public Comment
                     Period

SUMMARY OF COMMENTS  AND RESPONSES

Comments  expressed at the September 11,  1996 public meeting and
written comments  received during the public comment period have
been  categorized  as  follows:

      A.   Operable Unit Two (OU-2)  Remedy Selection Issues

      B.   Operable Unit One (OU -1)  Remedy

      C.   Extent  of  Groundwater Contamination

      D.   Residential Wells

      E.   Risk and Health Assessment

      F.   Other/miscellaneous

A summary of  the  comments and EPA's responses to the comments is
provided below.

-------
A. Operable Unit Two Remedy Selection Issues

Comment #1: Some commenters inquired about the use of natural
attenuation for the remediation of contaminated groundwater at
other Superfund sites and whether there are any documented
successes.

EPA'a Response:

Within the Superfund program, natural attenuation has been
selected as the remedy to address groundwater contamination at 73
sites.  Some of these sites include municipal and industrial
landfills, refineries, and recyclers.  Natural attenuation is
also being used to remediate many petroleum-contaminated
underground storage tank sites across the country.

At the Allied Signal Brake Systems Superfund site in St. Joseph,
Michigan, microorganism are effectively removing TCE and other
chlorinated solvents from groundwater. Scientists studied the
underground movement of TCE-contaminated groundwater from its
origin at the Superfund site to where it entered Lake Michigan
about half a mile away.  At the site itself, they measured TCE
concentrations greater than 200,000 parts per billion (ppb), but
by the time the plume reached the shore of Lake Michigan, the TCE
was one thousand times less-only 200 ppb.  About 300 feet
offshore in Lake Michigan concentrations were below EPA's
allowable levels.  In fact, microorganisms were destroying about
600 pounds of TCE a year at no cost to taxpayers.   EPA determined
that nature adequately remediated the TCE plume in St.  Joseph
while avoiding significant costs which might have been spent on
conventional treatment without additional significant human
health or environmental benefit.

Comment #2: One commenter was concerned that the time frames to
implement Alternatives 3 (Groundwater Pump and Treat) and 4 (In
situ Groundwater Treatment) were shorter periods than the
estimated time frame for the groundwater to reach drinking water
standards through natural attenuation.

EPA's Response:

The time frame to implement a remedial alternative as provided in
the Proposed Plan,  reflects only the time needed to construct the

-------
components of the remedial system.  This time frame excludes the
time required for the design of the remedy, negotiations with the
responsible parties, or award of contracts, and the time needed
to operate the remedial system to achieve the remedial goals. The
estimated time frames to implement Alternatives 3 and 4 are 9
months and 12 months, respectively.

The estimated time frame for the contaminants in the groundwater
to meet drinking water standards is approximately five years
after implementation of the lagoon remedy is completed.  This
time was estimated through a groundwater modeling study.  In
order to restore the aquifer to drinking water standards, the
lagoons, which are the sources of groundwater contaminants at the
Site, would have to be removed.  Therefore, all the alternatives
that were considered to address the contaminated groundwater
beneath the Site rely on the implementation of the lagoon remedy
before contaminant levels in the groundwater could reach drinking
water standards.  For all of the alternatives that were
evaluated, the concentrations of organic contaminants in the
groundwater are expected to meet drinking water standards
approximately five years after implementation of the lagoon
remedy.  Therefore,  all the alternatives are relatively similar
in terms of the time frame to achieve drinking water standards.

Comment #3: One commenter inquired about the timetable for
implementation of Operable Units 1 and 2 remedies.

EPA's Response:

Operable unit one is currently in the remedial design phase.
Excavation and treatment of the wastes have not yet begun.
Construction of the remedy is expected to begin in 1998, and it
is anticipated that it would take another year to cleanup the
sludges and soils in and around the lagoons utilizing ex-situ
vapor extraction, bioslurry,  and solidification/stabilization.

After the ROD for OU2 is signed,  EPA will send out special notice
letters to the PRPs (with the exception of Reynolds,  which is
considered a de-minimis PRP)  providing them with an opportunity
to implement the selected remedy under EPA supervision or to fund
the remediation.   From the time notice letters are delivered to
the PRPs it usually takes approximately four to six months to
initiate and complete negotiations with PRPs.   If the PRPs decide

-------
not to fund the cleanup of the site, EPA can either order them to
do it or pay for the cleanup itself and later seek to recover the
cost from the PRPs.  In either case, the design of the remedy
would be initiated shortly after the conclusion of negotiations.
The period from signing the ROD to completing the remedial
design, which would entail development of a monitoring plan and
selecting the appropriate institutional control(s) to be
implemented, would be less than one year.

Comment #4: One commenter expressed concern about the ability of
the preferred remedy (natural attenuation with institutional
controls and monitoring) to meet drinking water standards at the
Site.  Another commenter asked whether the groundwater modeling
conducted at the Site is reliable to estimate concentration
patterns in the groundwater.

EPA'8 Response:

As part of the remedial investigation, limited data was collected
to evaluate the extent of biodegradation at the Site.  This
limited evaluation included the collection of data on dissolved
oxygen levels and the presence of microorganisms in the
groundwater capable of degrading volatile organic compounds under
expected Site conditions.  The dissolved oxygen levels in the
benzene plume indicated the potential for biodegradation to be
occurring.   The degrading microorganisms population was in the
range of 105 to  10s, indicating the presence of a healthy and
robust community of degraders present in the aquifer.

Groundwater modeling was conducted at the Site to determine
whether the organic contaminant patterns found in the groundwater
beneath the Site have stabilized due to intrinsic biodegradation
and to estimate future concentrations of contaminants at
potential off-site locations.  The results of the groundwater
modeling indicate that the organic contaminants in the
groundwater are not migrating to Gold Creek and residences south
of Gold Creek,  and that the concentration patterns observed at
the Site .have stabilized or are not expected to change in the
future.

Therefore,  groundwater data combined with the limited
biodegradation field data and with the groundwater modeling
projections demonstrate the potential for biodegradation of

-------
organic contaminants  at  the Site.

Both the potential  for biodegradation and the groundwater
modeling studies conducted at the Site were evaluated by
scientists and experts in the field of computer modeling and
biodegradation at EPA's  Office of Research and Development in
Ada, Oklahoma.  Based on their review and approval of the
modeling efforts, and the fact that monitoring will be conducted
to verify the modeling predictions, EPA is confident that the
selected remedy will  be  protective of human health and the
environment.  If the  monitoring indicates that the model
predictions are not reasonable accurate, EPA will evaluate the
need to modify the  remedy.

Comment #5: One commenter suggested that the No Action remedy,
with no cost, should  be  selected for the groundwater operable
unit, since the wastes were placed in the lagoons 17 years ago
and the most downgradient monitoring wells have not detected any
levels of concern in  the groundwater.  The commenter suggested
that selection of Alternative 2 would be a waste of $284,000.

EPA's Response:

EPA evaluates the remedial alternatives against nine criteria,
only one of which is  cost.  Based on a detailed evaluation,  EPA
selects a remedy based on all nine criteria,  which are:
1)Overall protection  of  human health and the environment,
2)Compliance with Applicable or Relevant and Appropriate
Requirements, 3)Long-term effectiveness and permanence,
4)Reduction of toxicity,  mobility,  or volume through treatment
5)Short-term effectiveness,  6)  Implementability,  7)Cost,  8)  State
acceptance, and 9)  Community acceptance.

Alternative 2 includes groundwater monitoring to evaluate the
rate of reduction of  contaminants in the groundwater,
institutional controls to prevent the future use of the
contaminated groundwater, and sediment sampling in Gold Creek to
ensure that Site-related contaminants do not impact Gold Creek.
These measures are necessary to ensure that the remedy is
protective of the public and the environment.   A detailed cost
estimate of Alternative  2 is presented in Table 6 of the Record
of Decision.   Although $284,000 is a significant amount of money,
it is a reasonable amount to fulfill EPA's responsibility to

-------
ensure that the remedy  continues to be protective of human health
and the environment, while alleviating community concerns about
the effectiveness of the remedy to protect the drinking water.
Some commenters indicated that they wanted additional monitoring
due to concerns about their drinking water wells.  Please see
comment number 9.

B. Operable Unit One  (OU-1) Remedy

Comment #6: One commenter inquired about the treatment
technologies that will  be used to treat the organic and inorganic
contaminants in the lagoons and what type of materials would be
used to stabilize the inorganic contaminants.  Another commenter
inquired if any excavation and treatment of the wastes had begun.

EPA's Response:

In March 1995, EPA signed a Record of Decision for the lagoons.
The remedy requires the excavation of approximately 20,000 cubic
yards of contaminated material from the lagoons and soils in the
vicinity of the lagoons.. Materials exceeding treatment levels
will undergo stabilization via solidification/stabilization (for
inorganic contaminants) and bioslurry (for organic contaminants)
or a combination of the two treatment processes.  All  materials
will be placed on-site  in a lined and capped cell with leachate
collection.

Solidification/stabilization has been effectively used at several
Superfund sites to bind inorganic contaminants into an inert,
nonleaching mass that can be disposed of as a nonhazardous waste.
Different stabilization agents, such as cement-based,  pozzolaic-
based,  asphalt-based, and organic-polymer-based, are commercially
available. The specific stabilizing agent or agents that will be
used at the Carroll and Dubies site have not been selected at
this time, they will be selected during the remedial action phase
of the remedy.

Bioslurry has also been used effectively at Superfund sites to
treat organic contaminants,  specifically semi-volatile organic
compounds.  In bioslurry treatment,  the contaminated soil/sludges
is mixed with water to form a slurry which is fed to a
bioreactor.  Air and nutrients are added to the bioreactor to
promote aerobic microbial activity.  Microorganisms digest organic

-------
substances for nutrients and energy thereby breaking down
hazardous substances into less toxic or nontoxic substances.
Residual contaminants in the treated soil and sludge will be
contained in the capped cell to provide an extra margin of safety
against the continued migration of contaminants in the soil to
the groundwater.

Although the use of the bioslurry process to treat lagoon 7
materials appears to be a promising means of treating the semi-
volatile organics, further treatability studies are necessary to
demonstrate that this process can reduce the complex mix of
constituents in lagoon 7 to remediation goals.  Because of the
existing uncertainty, a contingency remedy will be implemented if
treatability study results indicate that bioslurry will not be
effective in reducing the levels of contaminants in lagoon 7
materials, particularly semi-volatile contaminants, to
remediation goals.  The major components of the contingency
remedy are identical to those of the selected remedy with the
following exception:

Excavation and off-Site treatment (as necessary) and disposal of
lagoon 7 materials at a Resource Conservation and Recovery Act
(RCRA) permitted hazardous waste treatment, storage and disposal
facility; it is assumed that thermal treatment,  i.e.,
incineration or low temperature thermal treatment,  will be
necessary to reduce the contaminants to appropriate Land Disposal
Restriction (LDR)  levels.

This operable unit is currently in the remedial design phase.
Excavation and treatment of the wastes have not yet begun.
Excavation and treatment of the lagoons is expected to begin in
1998.

Comment #7: One commenter inquired about the design of the
containment cell and cover for the treated materials from the
lagoons.

EPA'a Response:

The treated and untreated soils/sludges will be placed in a lined
and capped cell consistent with modified requirements of New York
Code of Rules and Regulations Part 360 (NYCRR Part 360 Solid
Waste Management Facilities regulations).   The regulations

                                8

-------
require that the base and cover of the disposal facility meet the
minimum permeability requirements.  Although the final design of
the cover has not been completed, it is envisioned that the base
of the cell will consist of a high density polyethylene  (HOPE)
liner and a sand drainage layer; that the cell will be sloped to
a leachate collection system; and that the cover will consist of
a low-permeability clay layer, an HDPE membrane, a sand drainage
layer and a topsoil layer.

C. Extent of Groundwater Contamination

Comment #8: One commenter inquired when the most recent sampling
of the furthest downgradient wells was conducted.  Another
commenter inquired about the concentrations of organic
contaminants in these wells and their corresponding drinking
water standards.

EPA's Response:

Groundwater samples were collected from these downgradient wells
in September 1994 and April 1995 and analyzed for both organic
and inorganic compounds.  In July 1996,  groundwater samples were
also collected from these wells and analyzed for inorganic
compounds only.

Groundwater data collected in the 1995 sampling event, in the
vicinity of lagoons 7 and 8, indicates that benzene is the
primary organic contaminant in the plume originating from these
lagoons.   The 1995 sampling data of monitoring wells located
downgradient and closest to lagoons 7 and 8 (OW-9,  OW-10, OW-11,
OW-12,  OW-13),  indicated various concentrations of organic
compounds. For example,  monitoring well OW-10,  which is located
immediately downgradient of lagoon 8, had the highest
concentrations of organic compounds,  with concentrations of
benzene at 2,600  ppb (State groundwater standard of 0.7 parts per
billion or ppb),  xylene at 30 ppb (State drinking water standard
of 5 ppb), and isophorone at 440 ppb (State drinking water
standard of 10 ppb).

However,  the concentrations of organics in groundwater in the
aquifer decreased dramatically downgradient from the lagoons
(this was also the case for the 1994 sampling event).  In 1995,
sampling data from the furthest downgradient wells from the

-------
lagoons  (OW-17,  OW-18,  OW-19 and OW-23) only indicated three
site-related  organic  compounds above the State drinking water and
groundwater standards.   Benzene was detected at 12 ppb  (State
groundwater standard  of 0.7 ppb), chlorobenzene at 10 ppb  (State
drinking water  standard of 5 ppb), and xylene at 29 ppb  (State
drinking water  standard of 5 ppb) in monitoring well OW-18.
Benzene and chlorobenzene were detected at 6 ppb and 8 ppb,
respectively, in monitoring well OW-19.  No organic compounds
were detected in monitoring well OW-17.  A comparison of the 1994
and 1995 sampling data  for organic compounds indicates that only
2 of the 4 furthest downgradient monitoring wells had any organic
contaminants  (benzene,  chlorobenzene and xylene); the
contaminants  were present at low levels in both sampling events.
The concentrations detected were low levels.  No trends from 1994
to 1995 could be established.

D.   Residential Wells

Comment #9: Some commenters asked about the residential well
sampling results, the dates that the sampling was conducted,
whether they  could have their wells sampled, and the date of
sediment sampling in Gold Creek.  One commenter requested that
the New York  State Department of Health (NYSDOH) sample the
private wells and that  the results of that sampling be considered
in EPA's determination  of the final remedy for the Site.

EPA'a Response:

The NYSDOH sampled several private wells located downgradient of
the Site in 1991 and 1993 for organic and inorganic constituents.
Organic constituents were not detected in the groundwater from
these wells;  inorganic  constituents were detected below drinking
water standards, indicating their presence are at naturally
occurring levels. In September 1994 and March 1995,  NYSDOH
sampled and analyzed a  total of ten private wells in the area for
volatile organic compounds.  The wells were located along Andrew
Drive,  Evergreen Lane,  Mark Drive,  Michael Drive,  Van Avenue, and
NY Route 209.   The results indicate that no volatile organic
compounds were detected in any of the wells sampled.   Mr. Tim
Vickerson of  the NYSDOH indicated at the public meeting that any
concerned citizen who wants their private wells to be tested for
contaminants may contact him at 1-800 458-1158 ext.  305.
                                10

-------
Although the results of wells  to be  sampled by NYSDOH would
provide additional  information to be utilized in EPA's
determination of the remedy  for the  Site, there is no reason to
believe that these  results will be any different from previous
residential well sampling results.   Additionally, EPA believes
that the results of groundwater monitoring, sediment sampling,
and groundwater modeling alone provide more than adequate support
for the selection of Alternative 2.  In any case, EPA and NYSDOH
will evaluate the results of the future residential well
sampling, as well as results from the groundwater monitoring
program to ensure that the remedy remains protective of human
health and the environment.

In September 1994,  sediment  samples  were collected in Gold Creek.
Analytical results  indicate  that Site related contaminants have
not impacted the sediments in  Gold Creek.

E.   Risk and Health Assessment

Comment #10: One commenter inquired  about the risk posed by the
contaminated groundwater and EPA's acceptable risk range.
Another commenter questioned if EPA  took into account all
contaminants in the groundwater in the risk assessment
calculation.

EPA'a Response:

The baseline risk assessment addressed the potential risk to
human health by identifying potential exposure pathways by which
the public might be exposed to contaminant releases at the Site
under current and future land-use conditions.   There are no
current on-site groundwater users at the Site,  therefore there
are no potential current receptors at the Site.   EPA evaluated
whether residents to the east  and southeast of Gold Creek that
use groundwater as drinking water and recreational users of Gold
Creek should be included as off-site receptors.  Groundwater
modeling,  in conjunction with measured groundwater
concentrations,  sediment data  from Gold Creek and groundwater
concentrations from off-site residential wells,  indicates that
the plumes have stabilized and that  contaminants have not
migrated either to Gold Creek or to  off-site residences on the
other side of Gold Creek.   Groundwater modeling results indicate
that contaminants are not expected to migrate to or beyond Gold

                               11

-------
Creek.  Thus, current exposures to either off-site residents or
recreational users of Gold Creek are not occurring and are not
expected to occur in the future.  These exposure pathways
therefore, were not quantitatively evaluated in the risk
assessment.

The exposure pathway evaluated under the potential future land-
use scenario included the exposure of industrial workers to the
on-site contaminated groundwater through ingestion.  Because the
Site and land immediately adjacent to the Site are currently
zoned and used exclusively for industrial land use, future
residential or commercial use of the Site is not expected to
occur and therefore, only industrial use of the Site was
evaluated in the risk assessment. For purposes of conducting the
risk assessment it was assumed that a future industrial worker
would drink 1 liter of water per day from an on-site well for 5
days a week for 50 weeks a year (250 days/year with about 2 weeks
vacation) for 25 years out of a 70 year lifetime.

Groundwater data were evaluated to identify chemicals-of-concern
for the risk assessment analysis.  All organic chemicals that
were detected in at least one sample were retained for evaluation
in the risk assessment with the exception of acetone and bis (2-
ethylhexyl)phthalate, which were determined to be laboratory
contaminants based on laboratory blank data. Since inorganic
contaminants are naturally occurring in groundwater,  they were
evaluated to determine if they were present at the Site above
background concentrations.   As a result of this evaluation eleven
(11)  inorganic compounds were retained for evaluation in the risk
assessment.  A list of all the contaminants of concern detected
in the groundwater that were used for the risk assessment
analysis is provided in Table 2 of the ROD.  These contaminants
included benzene, chloroform, 1,2-dichlorobenzene,
tetrachloroethene, toluene,  vinyl chloride, xylene, phenol,
arsenic, antimony, barium,  chromium,  lead,  and zinc.

EPA's acceptable cancer risk range is 10~4 to 10'6 which can be
interpreted to mean that an individual may have a one in ten
thousand to a one in a million increased chance of developing
cancer as a result of a site-related exposure to a carcinogen
over a 70-year lifetime under the specific exposure conditions at
a site.
                                12

-------
Evaluation of risks  to potential future industrial workers was
1.4 x 1CT4  (approximately one-in-ten  thousand). For this
scenario, the risk was determined to be within EPA's acceptable
risk range.

To assess the overall potential for noncarcinogenic effects posed
by the groundwater contaminants at the Site, EPA has developed
the hazard index  (HI).   An HI value of greater than 1 is
considered to pose a potential noncarcinogenic risk.  The
calculated HI value  was  0.55 which is below the acceptable level
of 1.0 indicating no adverse health effects to future industrial
workers.

F.   Other/miscellaneous

Comment #11: A commenter asked for the meaning of natural
attenuation.

EPA'a Response:

Natural attenuation  is an approach for treating underground
pollutants that makes use of -natural processes to contain the
spread of contamination  and reduce the concentration of
contaminants in order to restore soil or groundwater quality at
contaminated sites.  Examples of these natural processes are
intrinsic biodegradation, dilution,  dispersion,  and adsorption.

Comment #12: A commenter asked what institutional controls are
and how they would be implemented?

EPA's Response:

Institutional controls are non-engineering measures that prevent
or limit exposure to hazardous substances, pollutants or
contaminants.  They  usually take the form of land and/or water
use restrictions. There  are primarily two general categories of
institutional controls and several types within each category.
Governmental Controls are generally implemented through State or
local authorities that restrict activities or property,  such as
zoning laws which control land use,  and laws regarding well
drilling or water usage,  including licensing or permitting
authorities.  Proprietary controls are controls placed upon real
property that restrict the use of that property.   Examples

                               13

-------
include covenants, easements, agreements or notices prohibiting a
specific land use or preventing activities that may negatively
impact specific remedial measures.  Proprietary controls in the
form of deed restrictions  (e.g. easements or covenants) are
property interests that an owner conveys to another.   These deed
restrictions can "run with the land" which means they are binding
on future title holders.

Institutional controls will be implemented at the Carroll and
Dubies Site to restrict installation and use of groundwater wells
throughout the contaminated groundwater plume.  The institutional
controls will be required until the groundwater has been
demonstrated to meet federal drinking water and State groundwater
and drinking water standards. To date, EPA has not determined
which type or types of institutional controls will be the most
effective and the easiest to implement for this Site.  This
decision will, in all likelihood,  be made during negotiations
with the PRPs regarding performance of the remedy, or during the
remedial design phase of this operable unit.

Comment #13: One commenter questioned whether EPA would implement
and pay for the remedy in the event the PRPs do not agree to do
so.

EPA's Response:

Following the selection of a remedy,  EPA issues special notice
letters to the potentially responsible parties (PRPs) requesting
that they implement and fund the design and remediation of the
site.  If the PRPs are not willing to pay for or implement the
cleanup of the site,  then EPA can order them to perform the
remedial action,  or EPA can use Superfund money to perform the
work.  When the Agency uses its money for a response action at a
site where there are financially viable PRPs,  it is authorized to
take an enforcement action against those PRPs to recover its
costs.   EPA can ultimately recover these costs through
administrative settlements, judicial settlements or litigation.

Comment #14: One commenter inquired about whether the Superfund
program is an after the fact agency.   This commenter was
concerned that efforts were not being made to prevent Superfund
sites from being created.
                               14

-------
EPA's Response:

Years ago, people did not understand how certain wastes might
affect people's health and the environment.  Many wastes were
dumped on the ground, in rivers or left out in the open. As a
result, thousands of uncontrolled or abandoned hazardous wastes
sites were created. Some common hazardous waste sites include
abandoned warehouses, manufacturing facilities, processing plants
and landfills.  In response to growing concern over health and
environmental risks posed by hazardous waste sites, Congress
established the Superfund program in December 1980 to provide EPA
with a powerful means of responding to cases of environmental
contamination.  The Superfund remedial program is generally
retroactive in nature, addressing previously-contaminated sites,
as well as chemical emergency situations.  Superfund personnel
are on call to respond at a moment's notice to chemical
emergencies, accidents or releases.  Typical chemical emergencies
may include train derailments, truck accidents, and incidents at
chemical plants where there is a chemical release or threat of a
release to the environment. On the other hand, the Resource
Conservation and Recovery Act ("RCRA"), enacted in 1976,
(implementing regulations effective November 1980) regulates
hazardous waste from cradle (generation)  to grave
(disposal/treatment)  thereby minimizing the potential for future
Superfund sites.  RCRA regulations also require owners and
operators of RCRA regulated facilities to properly "close"
facilities and to maintain financial assurance in amounts
sufficient to cover the cost of "closing" the facility and thus
avoiding the need for a Superfund clean up.

Comment #15: One commenter inquired about the potentially
responsible parties to the Consent Order.

EPA's Response:

There are four categories of PRPs:  (1)  Parties who conducted
operations at the site,  which caused the site to become
contaminated, known as "operators"; (2)parties that transported
wastes to the site,  known as "transporters"; (3)  parties that
generated wastes that were disposed of at the site, known as
"generators"; and (4)  past or present owners of the site,  known
as "owners".

                               15

-------
The five PRPs at this  Site are Carroll and Dubies Sewage
Disposal, Inc.  (C&D),  which is considered to be owner, operator
and transporter; Kolmar Laboratories, Inc.  (Kolmar), Wickhen
Products, Inc.  (Wickhen) and Reynolds Metals Co., Inc.
 (Reynolds), all considered to be generators; and the City of Port
Jervis, also considered to be an owner.

Two PRPs, Kolmar and Wickhen, signed an Administrative Order on
Consent in February 1990 for the performance of the remedial
investigation and feasibility studies (RI/FSs) . During 'the OU1
RI, EPA learned from the City of Port Jervis that it owned a
major portion of the Site property where the lagoons are located.
In an April 22, 1993 letter, EPA notified the City that it was
also a PRP for the Site.

On May 19, 1995, EPA issued "special notice" letters to the PRPs
requesting that they submit a good faith offer to perform the
Remedial Design/Remedial Action (RD/RA)  for OU1.  The PRPs and
EPA were unable to reach an agreement and thus, on September 29,
1995,  EPA issued a Unilateral Administrative Order to Carroll &
Dubies, Kolmar and Wickhen ordering them to implement the first
operable unit remedy.

On September 29, 1995, EPA entered into a de minimis Settlement
with Reynolds regarding EPA's past response costs for the Site
and remedial design/remedial action costs for OU1.   Reynolds was
considered de minimis party because it contributed a very small
percentage of the waste to the Site, approximately 0.32 percent,
and this waste was neither more toxic nor of greater hazardous
effect than the other hazardous substances at the Site.  This
settlement became effective on July 18,  1996.

After issuance of the ROD for OU2,  all non de minimis PRPs will
be offered the opportunity to design and implement the selected
OU2 remedy.   EPA will offer Reynolds a de minimis settlement for
OU2 costs.

Comment #16: One commenter expressed concern that the Port Jervis
landfill property,  in which several of the Carroll and Dubies
lagoons are located, is the major contributor to the overall
contamination at the Site.   The commenter believes that in
addition to the wastes disposed of in the lagoons,  a great deal
of other Carroll & Dubies wastes were also disposed of in the

                               16

-------
Port Jervis Landfill.  The commenter indicated that the cost to
clean up the  landfill will be much greater than the cost to clean
up the Carroll and Dubies Site, and that EPA should be addressing
the Port Jervis  landfill.

EPA's Response:

This ROD addresses only the groundwater beneath and downgradient
of the Carroll and Dubies Site.  The landfill is not being
considered part  of the Site, and therefore, is not being
investigated  at  this time.  However, if specific information
regarding the location, methods and types of Carroll & Dubies
Sewage Disposal  waste disposed of in the Port Jervis landfill is
provided to EPA, EPA will perform further investigation as
appropriate.

It should be  noted that landfills are subject to New York State
regulations for  the management of solid waste facilities (Part
360 of the New York Code of Rules and Regulations).   These
regulations include landfill closure requirements which include
installing a  landfill cover.  To date,  the City of Port Jervis
landfill has  not yet been properly capped.  Since the landfill is
not part of the  Superfund investigation conducted to date,  there
are no costs  available for remediating the landfill.  Typically,
landfills are addressed by installing a multi-layered cover over
the landfill  to prevent the percolation of snow melt and
rainwater through the landfill waste,  thereby reducing the
migration of  contaminants from the landfill to the groundwater.
Given the size of landfills, it is not practical to excavate and
treat the landfill waste.  It is probable that the proper closure
of the landfill would be a multi-million dollar effort.  The Port
Jervis landfill will be closed (including capping)  as required by
the New York  Code of Rules and Regulations (6 NYCRR Part 360)
requirements  for Solid Waste Management Facilities.   The NYSDEC
has not yet developed a schedule for the closure of the landfill.
However,  NYSDEC has requested that any questions regarding the
closure of the landfill be directed to:
                    Mr. Victor Cardona
                    Federal Projects Section
                    Bureau of Eastern Remedial Action
                    Division of Hazardous Waste Remediation
                                17

-------
                    New York State Department of
                    Environmental Conservation
                    50 Wolf Road
                    Albany, New York, 12233-7010
                    Telephone # (518) 457-3976

Comment # 17:  Several commenters requested that the water and
sediments of Gold Creek be sampled immediately and at frequent
intervals during the remediation of the lagoons.   The Creek is
adjacent to the Port Jervis High School and Elementary School and
their playing fields.  The commenters indicated that students
have had to enter the Creek to retrieve balls on more than one
occasion and that this may present a possible human exposure to
Site contaminants.

EPA's Response:

Sediment samples were collected from two locations in Gold Creek
south of the Site.  These samples were collected in September
1994 and analyzed for organic and inorganic compounds.  The
analytical results of the sampling indicate that Site related
contaminants have not impacted Gold Creek.   This is further
supported by the groundwater sampling results which show that
contaminants were detected at low levels in monitoring wells
located close to the Creek.  In addition,  EPA's risk assessment
indicates that there is no risk associated with the sediments.
The contaminants in the groundwater at the Site have not migrated
to Gold Creek and are not anticipated to migrate there in the
future.

The selected remedy requires sediment sampling in Gold Creek to
ensure that Site related contaminants do not impact the Creek in
the future.   With respect to surface water sampling,  EPA has
determined that it will require sampling of the Creek water
during the first year of the monitoring program to support the
results  of the sediment sampling.

Comment  #18: One commenter indicated that  the responsibility for
establishing the institutional controls should be placed on the
City of  Port Jervis.
                               18

-------
EPA's Response:

EPA will determine the appropriate institutional control or
controls to be implemented during negotiations with the PRPs
regarding performance of the remedy, or during the remedial
design phase of this operable unit.  After issuance of this ROD,
EPA will send "special notice letters" to all non-de minimis
PRPs; this includes the City of Port Jervis.  The special notice
letter will invite the PRPs, including the City, to submit a good
faith offer to either implement the remedy themselves or fund
EPA's implementation of the remedy.  If EPA determines that the
City is the most appropriate entity to implement the required
institutional controls, and the City does not agree to do so, EPA
could issue a unilateral order to the City, ordering them to
perform the remedy.

Comment #19: One commenter stated that no additional monitoring,
beyond what is required for OU1, is necessary.

EPA'8 Response:

The selected remedy for OU2 includes a groundwater monitoring
program.  This monitoring program will include an initial study
of the groundwater parameters which favor natural attenuation and
periodic groundwater sampling to evaluate the rate and extent of
reduction of the organic contaminants in the groundwater.

The initial study will include an evaluation for the presence of
constituent-degrading microorganisms, pH, oxygen or other
electron acceptors, elemental nitrogen, phosphorous and other
parameters that are necessary to evaluate the progress of natural
attenuation.  The results of the groundwater sampling and
analysis will be summarized to establish trends and/or reassess
further remedial actions that may be required.

The OU1 remedy includes groundwater monitoring only to ensure
that the containment cell for the treated lagoon sludges and soil
is functioning appropriately.  The purpose of this monitoring is
to detect any potential releases to the groundwater that may
occur in the future.  The OU1 groundwater monitoring program was
to be coordinated with monitoring expected to be conducted
pursuant to the OU2 remedy.
                               19

-------
Comment #20: One commenter expressed concern that the time period
presented in the Proposed Plan, for the groundwater to reach
drinking water1 standards, was of greater time duration than that
indicated by the groundwater model.  The commenter indicated that
the groundwater modeling results predict that the contaminant
plumes will attenuate over a much shorter time than the five year
time period specified by EPA.

EPA's Response:

The groundwater model was used to predict concentrations in the
future for the following three different scenarios: (1) the
remedy for OU1 is not implemented.  Under scenario 1 the extent
of the benzene and perchloroethylene (PCE) contaminant plumes
would remain constant for the foreseeable future.  (2)  The OU1
remedy is implemented and no residual contaminants remain in soil
beneath the lagoons.  Under scenario 2 the benzene contaminant
plume would retract to the lagoons within approximately five
years, while the PCE plume would retract to the lagoons within
approximately one year. (3)  The OU1 remedy is implemented and
residual contaminants remain in soil beneath the lagoons. Under
scenario 3 the benzene and PCE plumes would retract to the
lagoons within approximately five years.  The five year time
period specified by EPA assumes that all contaminants in the
groundwater at the Site will attenuate to drinking water
standards following implementation of the OU1 remedy.  EPA
believes that this is an accurate and appropriate representation
of the groundwater modeling results.

Comment #21: The Town Board of Deerpark requested that
Alternative 3  (Groundwater Pump and Treat via Precipitation,
Filtration and Carbon Adsorption)  be the selected remedy to
address the groundwater contamination at the Site.  The Town
Board believes that this alternative provides a better
containment and control of the contaminated groundwater than
Alternative 2.  Another commenter requested that Alternative 4
(In Situ Groundwater Treatment)  be the selected remedy.

EPA's Response:

EPA and NYSDEC believe that Alternative 2 provides the best
balance and trade offs with respect to the evaluation criteria.
                                20

-------
There are no current users of groundwater at the Site, therefore
no one is exposed to the contaminants present in the groundwater.
Sampling of the groundwater  indicates that the levels of
contamination in the groundwater decrease dramatically from the
wells nearest the lagoons to those wells furthest downgradient of
the lagoons and closest to Gold Creek; sediment sampling
indicates that the Creek has not been impacted by contaminants
from the Site.  This data and other data generated during the RI
were input into a groundwater model which predicted that
contaminants would not reach Gold Creek in the future.  The
groundwater modeling also predicted that Alternative 2 will
attain drinking water standards in approximately the same time
frame, five years after the  implementation of the OU1 remedy, as
Alternatives 3 and 4.  Natural attenuation in combination with
institutional controls and groundwater monitoring will ensure
that the remedy is fully protective of human health and the
environment.

Given the fact that the remedy will be fully protective of human
health and the environment,   and that it will achieve drinking
water standards in approximately the same time frame as more
costly alternatives, EPA and NYSDEC believe that Alternative 2 is
the most practical choice to address the groundwater
contamination at the Carroll and Dubies site.
                                21

-------
 Appendix A




Proposed Plan
      22

-------
Superfund Proposed Plan
                 Carroll and Dubies Sewage Disposal Inc.
                                        Town of Deerpark
                                    Orange County, New York
EPA Region 2
August 28, 1996
NYSDEC
PURPOSE OF PROPOSED PLAN

This Proposed Plan describes the remedial
alternatives considered for the contaminated
groundwater at the Carroll and Dubies
Sewage Disposal (C&D) Superfund site (the
Site) and identifies the preferred remedial
alternative for the contaminated
groundwater with the rationale for this
preference. The Proposed Plan was
developed by the U.S. Environmental
Protection Agency (EPA), as lead agency,
with support from the New York State
Department of Environmental Conservation
(NYSDEC). EPA is issuing the Proposed
Plan as part of its public participation
responsibilities under Section 117(a) of the
Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA)
of 1980, 42 U.S.C. §9617(a), and the
National Contingency Plan (NCP), 40
C.F.R.  §300.430(f). The alternatives
summarized here are described in the
Remedial Investigation and Feasibility
Study (RJ/FS) reports which should be
consulted for a more detailed description of
all the alternatives. As part of the
Administrative Record for the Site, the
          RJ/FS can be found in the public repositories
          listed on page 2.

          This Proposed Plan is being provided as a
          supplement to the RI/FS reports to inform
          the public of EPA's and NYSDEC's
          preferred remedy and to solicit public
          comments pertaining to all of the remedial
          alternatives evaluated, as well as the
          preferred alternative.

          The remedy described in this Proposed Plan
          is the preferred remedy  for the second
          operable unit (OU2) at the Site, involving
          the contaminated groundwater at the Site.
          (The selected remedy for the first operable
          unit (OU1), involving the clean-up of
          sludges and contamination in the soil in and
          around the lagoons, was announced in a
          Record of Decision (ROD) dated March 31,
          1995, and is presently in the design phase.)
          Changes to  the preferred remedy or a change
          from the preferred remedy to another
          remedy may be made, if public comments or
          additional data indicate that such a change
          will result in a more appropriate remedial
          action.  The final decision regarding the
          selected remedy will be made after EPA has

-------
taken into consideration all public
comments.  We are soliciting public
comment on all of the alternatives
considered in the detailed analysis of the
RI/FS because  EPA and NYSDEC may
select a remedy other than the preferred
remedy.

COMMUNITY ROLE IN SELECTION
PROCESS

EPA and NYSDEC rely on public input to
ensure that the  concerns of the community
are considered  in selecting an effective
remedy for each Superfund site. To this
end, the RI/FS  reports, Proposed Plan, and
supporting documentation have been made
available to the public for a public comment
period, which begins on August 28, 1996
and concludes on September 27,1996.

A public meeting will be held during the
public comment period at the auditorium of
the Port Jervis High School, Route 209, Port
Jervis, New York on Wednesday, September
11, 1996 at 7:00 p.m. to present the
conclusions of the RI/FS, to elaborate
further on the reasons for recommending the
preferred remedial alternative, and to receive
public comments.

Comments received at the public meeting, as
well as written comments, will be
documented in the Responsiveness
Summary Section of the Record of Decision
(ROD), the document which formalizes the
selection of the remedy.
      MARK YOUR CALENDAR

  August 28,1996 to September 27, 1996:
  : Public comment period on; RI-/FS report,
  Proposed Plan, and remedy considered.

  Wednesday, September 11,1996
  Public meeting to be held at 7:00 p.m. in
  the auditorium of the Port Jervis High
 Written comments should be addressed to
Maria Jon
Project Manager
U.S. Environmental Protection Agency
290 Broadway, 20th floor
New York, New York 10007-1866
(212) 637-3967
   Copies of the RI/FS reports, Proposed
   Plan and supporting documentation are
   available at the following locations:

   Town Hall
   Drawer A.:.:     .    ...... .
   .; Huguenot, New ,-York:  12746
   Tel.: (914) 856r2210:,.:;:  .
   Hours:  8:00 a:rri;:- 4:00: p;m; (Mon. - Fri.)

   EPA Document ControlGenter
   290 Broadway,. 18th;floor
   New York, New York ; 10007-1866
SITE BACKGROUND

The Carroll & Dubies site is located just
northeast of the City of Port Jervis, on Canal
Street in the Town of Deerpark, Orange
County, New York.  The Site is
approximately 5.5 acres in size (see Figure
1). The northwest boundary of the Site is
formed by the valley wall, which consists of
exposed bedrock with talus comprising the

-------
base.  The southeast boundary and a portion
of the northeast boundary of the Site is
formed by remnants of the former Delaware
and Hudson Canal and towpath. Adjacent to
the southern boundary of the Site is the City
of Port Jervis Landfill. The landfill is no
longer active; however, Orange County
currently operates a solid waste transfer
station on a portion of the landfill property.
Approximately 1,500-feet to the east of the
Site is Gold Creek.  The nearest resident
located downgradient of the Site is about a
quarter of a mile from the Site.

From  approximately 1970 to 1979, the Site
was used for the disposal of septic and
municipal sewage sludge and industrial
wastes, primarily from the cosmetic
industry. The industrial waste was
deposited in one or more of the seven
lagoons  located at the Site (lagoons 1
through  4 and 6 through  8 are depicted in
Figure 2). Lagoon 5  contains tires; no
industrial waste was found.

In 1978, lagoon 3 was ignited by the Port
Jervis Fire Department in order to practice
suppression of chemical fires. After this
incident, lagoons 3  and 4 were filled in with
soil and  the area was revegetated.  With the
exception of lagoons 1 and 2, all of the
lagoons  have been covered with soil.
Lagoons 1 and 2 were left uncovered and are
surrounded by a wooden  fence.  In June
1979,  NYSDEC prohibited the disposal of
industrial wastes at the Site.  The Site
continued to be used for the disposal of
septic and municipal sewage wastes  until
1989.

In February 1987, NYSDEC issued a Phase
II Investigation Report which summarized
past investigations and included a Hazard
Ranking System (HRS) score for the Site.
Based on the HRS score, the Site was
proposed for inclusion on the National
Priorities List (NPL) in June 1988 and was
placed on the NPL in February 1990.

On September 25, 1989, EPA sent "special
notice" letters to four potentially responsible
parties (PRPs), affording them the
opportunity to conduct the RI/FS for the
Site. PRPs are companies or individuals
who are potentially responsible for
contributing to the contamination at the Site
and/or are past or present owners of the
property. The four PRPs were Carroll and
Dubies Sewage Disposal, Inc. (C&D),
Kolmar Laboratories, Inc.  (Kolmar),
Wickhen Products, Inc. (Wickhen) and
Reynolds Metals Co., Inc. (Reynolds). The
PRPs were given 60  days in which to submit
a good faith offer to undertake or finance the
PJ/FS for the Site.

On November 30, 1989, two PRPs, Kolmar
and Wickhen, submitted a good faith offer to
perform the RI/FS. An Administrative
Order on Consent was signed by the two
PRPs and by EPA in February 1990.
Kolmar and Wickhen conducted all RI/FS
work, pursuant to the RI/FS Order with
oversight by EPA. During the RI, EPA
learned from the City of Port Jervis that it
owned a major portion of the Site property
where the lagoons are located.  In an April
22, 1993  letter, EPA notified the City that it
was also a PRP for the Site.

In March 1995, EPA signed a ROD for the
first operable unit which called for the
excavation of approximately 20,000 cubic
yards (cy) of contaminated material from the
lagoons and soils in the vicinity of the
lagoons. Materials exceeding treatment

-------
levels will undergo treatment via
solidification/stabilization (for inorganic
contaminants) and bioslurry (for organic
contaminants) or a combination of the two
treatment processes.  All  materials will be
placed on-site in a lined and capped cell
with leachate collection.

On May 19, 1995, EPA issued "special
notice" letters to the PRPs requesting that
they submit a good faith offer to perform the
Remedial Design/Remedial Action (RD/RA)
for OU1. The PRPs and EPA were unable
to reach an agreement and thus, on
September 29, 1995, EPA issued a
Unilateral Administrative Order to C&D,
Kolmar and Wickhen ordering them to
implement the first operable unit remedy.

On September 29, 1995, EPA entered into a
De Minimis Settlement with Reynolds
regarding past costs for OU1. This
settlement became effective on July 18,
1996.

After issuance of the ROD for OU2, all the
PRPs will be offered the opportunity to
design and implement the selected OU2
remedial alternative.

SCOPE AND ROLE OF ACTION

Site remediation activities are sometimes
segregated into different phases or operable
units, so that remediation of different
environmental media or areas of a site can
proceed separately. This phased approach
results in an expeditious remediation of the
entire site.  EPA has designated two
operable units for the Carroll and Dubies site
as described below.
     first operable unit (OU1) includes the
materials and contaminated soils from
lagoons 1, 2, 3, 4, 6, 7, and 8, which are
contaminated primarily with heavy metals
and volatile organic compounds (VOCs).
This operable unit is currently in the
remedial design phase.

"•Operable Unit 2 (OU2) addresses the
contaminated groundwater beneath and
downgradient of the Carroll and Dubies
property. This is the final operable unit and
is the subject of this Proposed Plan.

REMEDIAL INVESTIGATION
SUMMARY

The nature and extent of groundwater
contamination found at the Carroll and
Dubies site was  assessed through sampling
of groundwater, sediment  in Gold Creek,
residential wells and through groundwater
modeling and geophysical surveys. A total
of 34 monitoring wells was installed and
four groundwater sampling events were
conducted during the investigation.

The geology under the Site consists of
unconsolidated overburden materials of
glacial and glaciofluvial origin, which
overlie shale bedrock.  The thickness of the
unconsolidated overburden materials ranges
from zero foot at the exposed bedrock slope
forming the northwestern  Site boundary, to
over 60 feet along the towpath.  The
glacially derived materials consist of two
distinct units, including a  glacial till unit
overlain by glacial  outwash deposits. The
outwash deposit, which constitutes an
aquifer, ranges in thickness from 31 feet to
52 feet along the downgradient edge of the
Site. The glacial till is not continuous
beneath the Site, and appears to pinch out

-------
toward the northwestern edge of the Site,
adjacent to the exposed bedrock slope. The
till formation is defined as an aquitard,
because it consists of silt and clay, which
typically have low permeability.   The till
formation is underlain by shale bedrock.
Groundwater found in the bedrock can be
developed and therefore the bedrock is
defined as an aquifer.  The depth to
groundwater from ground surface ranged
from approximately 30 to 40 feet along the
southeastern boundary of the Site.
Groundwater movement beneath the Site is
generally to the southeast, towards Gold
Creek, which is located approximately 1,500
feet southeast of the Carroll and Dubies
property line.

Groundwater samples were collected
downgradient of the lagoons and analyzed
for organic and inorganic compounds. The
monitoring wells monitor either the bedrock
(well depths ranging from 39 feet to 86 feet
below land surface), the glacial till (well
depth at 60 feet below land surface), the
glacial outwash (well depths ranging from
16 feet to 58 feet below land surface) or both
the glacial till and outwash units (well
depths ranging from 35 feet to 51  feet below
land surface). The analytical results for the
groundwater samples for the 1991, 1993,
1994, and 1995 sampling events did not
indicate the presence of organic
contaminants above federal drinking water
or State drinking water or groundwater
standards in any of the bedrock or glacial till
monitoring wells. The sampling events did
show VOCs, semivolatile organic
compounds (SVOC), and chlorinated
organic compounds at  concentrations
exceeding federal drinking water and State
groundwater and drinking water standards in
monitoring wells that are screened in the
outwash and across the outwash and till
interface. As a result two plumes of total
organic compounds exceeding 100 ug/L
(micrograms per liter) or parts per billion
(ppb) were defined.  One plume originates
at lagoons 1 and 2, the other at lagoons 7
and 8.  The concentration of organics in the
groundwater decreases dramatically further
downgradient of the lagoons, which suggests
that significant attenuation of contaminants
has occurred. This has been demonstrated
through groundwater modeling conducted at
the Site. The plumes are of limited extent
and have not extended far enough to impact
Gold Creek, or to affect groundwater or the
residential wells south of Gold Creek.

The discussion below is intended to
summarize groundwater results for organic
constituents by plume (i.e., results of
samples collected from monitoring wells in
the plume downgradient from lagoons 1-4
and results of samples collected from
monitoring wells in the plume downgradient
of lagoons 6-8). The discussion focuses on
the 1994 and 1995 sampling results, as these
results indicate the highest concentrations of
organic contaminants and during these
sampling events all wells in the monitoring
network had been installed (the wells had
been installed in phases).

Groundwater Downgradient of Lagoons 1-4

During the 1994 sampling event, four
organic compounds, benzene, 1,2-
dichloroethene, tetrachloroethene and
trichloroethene were detected above the
federal drinking water and/or State drinking
water and groundwater standards in the
monitoring wells located downgradient of
lagoons 1 through 4. The highest
concentrations of the chlorinated organic

-------
compounds were observed in shallow
outwash well OW-2, located downgradient
of lagoon 2. Groundwater samples from
monitoring well OW-2 detected 1,2-
dichloroethene at 130 ppb, tetrachloroethene
at 100 ppb, and trichloroethene at 24 ppb.
The federal drinking water and State
drinking water standards for
tetrachloroethene and trichloroethene are 5
ppb; the State drinking water standard for
1,2-dichloroethene is 5 ppb, which is more
stringent than the federal standard. Benzene
was observed in shallow outwash well
MW-4 at 15 ppb. The State drinking water
standard for benzene is 0.7 ppb. The 1995
groundwater results detected organic
constituents at similar concentrations as
those detected during the 1994 sampling
event.

Groundwater Downgradient of Lagoons 6-8

Groundwater data collected in the 1995
sampling event, in the vicinity of lagoons 7
and 8, indicates that benzene is the primary
organic contaminant in the plume
originating from these lagoons.  During the
1995 sampling of monitoring wells located
downgradient of lagoons 6, 7 and 8 (OW-9,
OW-10, OW-11, OW-12, OW-13), benzene
(State drinking water standard of 0.7 ppb)
was detected in monitoring well OW-9 at
900 ppb.  Monitoring well OW-10, which is
located immediately downgradient of lagoon
8, had concentrations of benzene at 2,600
ppb, xylene at 30 ppb (drinking water
standard of 5 ppb), and isophorone at 440
ppb (drinking water standard of 10 ppb).
Monitoring well OW-11 had concentrations
of benzene at 970 ppb, ethylbenzene at 30
ppb (drinking water standard of 5 ppb),
xylene at 51 ppb, and naphthalene at 17 ppb
(drinking water standard of 10 ppb).
Benzene and phenol (drinking water
standard of 1 ppb) were detected at 2,400
ppb and 55 ppb, respectively, in monitoring
well OW-12.  Monitoring well'OW-13 had
concentrations of 1,2-dichloroethene at 20
ppb, benzene at 350 ppb, and vinyl chloride
at 34 ppb (drinking water standard of 2 ppb).
The 1994 groundwater results detected
organic constituents at similar
concentrations as those detected during the
1995 sampling event.

As previously stated, the concentrations of
organics in groundwater in the outwash
aquifer decreased dramatically downgradient
from the lagoons in the 1994 and 1995
sampling rounds.  In 1995, sampling data
from the furthest downgradient wells from
the lagoons (OW-17, OW-18, and OW-19)
only indicated three organic compounds
above the State drinking water standards.
Benzene was detected at 12 ppb,
chlorobenzene at 10 ppb and xylene at 29
ppb in monitoring well OW-18.  Benzene
and chlorobenzene were detected at 6 ppb
and 8 ppb, respectively in monitoring well
OW-19. No organic compounds were
detected in monitoring well OW-17.

In September 1994, April 1995 and July
1996, groundwater samples were collected
and analyzed for inorganic compounds.
Groundwater samples collected  in the 1994
sampling event were non-filtered inorganic
samples. Although the results of the 1994
analyses indicated the presence of inorganic
compounds, very few samples indicated
concentrations above federal drinking water
and State drinking water and groundwater
standards. Arsenic was detected at 28.9 ppb
(drinking water standard of 25 ppb),
chromium was found in one sample at 123
ppb (drinking water standard  of 50 ppb),

-------
antimony was found at 65 ppb (drinking
water standard of 3 ppb) and lead was found
in one sample at 39.2 ppb (drinking water
action level of 15 ppb).  For each of the
inorganic compounds that exceeded their
respective criteria (arsenic, chromium, lead
and antimony) exceedances occurred in only
one sample out of the 32 samples collected.

Groundwater samples collected in the 1995
sampling event were highly turbid.  These
samples were also filtered in the field. The
results of the 1995 inorganic analyses
indicated the presence of various inorganic
constituents in the groundwater
downgradient of the lagoons above
background concentrations. Several
inorganic constituents were detected at
concentrations that exceeded the federal
drinking water and/or State drinking water
and groundwater standards. Antimony was
detected at 15 ppb (drinking water standard
of 3 ppb), arsenic was detected at 105 ppb
(drinking water standard of 25 ppb),
beryllium was detected at 7.2 ppb (drinking
water standard of 3 ppb), chromium was
detected at 669 ppb (drinking water standard
of 50 ppb), lead was detected at 283 ppb
(drinking water action level of 15 ppb), and
nickel was detected at 425 ppb (there is no
drinking water standard for nickel at this
time).

Due to the inconsistency between the  1994
and 1995 sampling results for inorganic
constituents, EPA conducted another
sampling event for inorganic constituents in
July 1996. It was suspected that the high
concentrations of inorganics detected in
1995 may have been an artifact of highly
turbid samples resulting from the sampling
protocols used at that time. Because of this,
the July 1996 groundwater samples were
collected via a low-flow pump, and these
samples were not filtered. Also, during
sample collection, the presence of high
turbidity in some of the samples was
observed, therefore some monitoring wells
were re-developed prior to collecting the
groundwater samples.  The results of this
sampling event indicated the presence of
inorganic compounds.  Only three samples
indicated concentrations above State
groundwater standards. Chromium was
detected in monitoring well OW-9 at 70 ppb,
arsenic was detected at 43 ppb and 37 ppb in
monitoring wells OW-19 and OW-18,
respectively.

The levels of inorganics detected in the 1995
samples tend to directly depend on the
amount of suspended sediment (turbidity) in
the samples. Since the excessive turbidity
present in the 1995 groundwater samples is
believed to be an artifact of sampling, these
higher levels are not representative of true
site conditions in the aquifer. So, the results
of the groundwater data suggests that the
inorganic compounds found in the
groundwater beneath the Site are most likely
present at naturally occurring levels. Thus,
the potential for inorganic compounds to be
present in groundwater at concentrations
above naturally occurring levels due to
leaching from the lagoon sediments is low
and the potential for these inorganic
compounds to subsequently discharge with
groundwater to Gold Creek is also low.  It
should be noted that the results from the
1994 sampling event for inorganic
constituents were included  in the risk
assessment (see Summary of Site Risks
below).  No pesticides or PCBs were
detected in any of the groundwater samples
collected from this Site.

-------
Sediment samples were collected in Gold
Creek. Analytical results indicate that Site
related contaminants have not impacted the
sediments in Gold Creek.

As part of the RJ, groundwater modeling
was conducted to determine whether the
organic contaminant patterns found in the
groundwater beneath the Site have stabilized
due to intrinsic biodegradation and to
estimate future concentrations of
contaminants at potential off-site locations.
The results of the groundwater modeling
indicate that the organic contaminants in the
groundwater are not migrating off-site and
that the concentration patterns observed at
the Site have stabilized or are not expected
to change in the future. Thus, contaminants
in the groundwater beneath the Site are not
expected to reach Gold Creek or off-site
residences in the future.

Also, as part of the RI, limited data was
collected to evaluate the extent of
biodegradation at the Site. This limited
evaluation included  the collection of
dissolved oxygen and the presence of
microorganisms in the groundwater capable
of degrading volatile organic compounds
under expected Site  conditions.  The results
of this evaluation indicated that at the
Carroll and Dubies site the dissolved oxygen
levels in the benzene plume indicated the
potential  for biodegradation to be occurring,
and the degrading microorganisms
population was in the range of 105 to 106,
indicating a healthy  and robust community
of degraders present in the aquifer.
Therefore, the limited field data combined
with the groundwater modeling projections
demonstrate the potential for biodegradation
of organic contaminants at the Site. The
groundwater modeling results estimated that
contaminants will attenuate in five years
after completion of the remedy selected for
the lagoons. Since the groundwater
modeling results indicated the potential for
intrinsic biodegradation to be occurring in
the aquifer, this potential is evaluated in the
analysis of remedial alternatives.

The City of Port Jervis is served by a
municipal water supply that relies on three
hydraulically-upgradient reservoirs as water
sources. Outside of the City limits,  private
supply wells provide drinking water.  It
should be noted that the New York State
Department of Health (NYSDOH) sampled
several wells located downgradient of the
Site while the RI/FS was being conducted .
Several private wells were sampled in 1991
and again in 1993 for organic and inorganic
constituents.  Organic constituents were not
detected in the groundwater from these
wells, and inorganic constituents were
detected below drinking water standards.
Subsequently, in September 1994 and March
1995, NYSDOH sampled and analyzed a
total often private wells in the area for
volatile organic compounds. The wells were
located along Andrew Drive, Evergreen
Lane, Mark Drive, Michael Drive, Van
Avenue, and NY Route 209. The results
indicate that no  volatile organic compounds
were detected in any of the wells sampled.

SUMMARY OF  SITE RISKS

Based upon the results of the RI for the
groundwater operable unit, a baseline risk
assessment was conducted to estimate the
risks associated with current and future Site
conditions. The baseline risk assessment
estimates the human health and ecological

-------
risk which could result from the
contamination at the Site, if no remedial
action were taken.

As part of the baseline risk assessment, the
following four-step process is utilized for
assessing site-related human health risks for
a reasonable maximum exposure scenario:
Hazard Identification—identifies the
contaminants of concern at the site based on
several factors such as toxicity, frequency of
occurrence, and concentration. Exposure
Assessment—estimates the magnitude of
actual and/or potential human exposures, the
frequency and duration of these exposures,
and the pathway (e.g,  ingesting
contaminated well-water) by which humans
are potentially exposed. Toxicity
Assessment—determines the types of adverse
health effects associated with chemical
exposures, and the relationship between
magnitude of exposure (dose) and severity
of adverse effects (response).  Risk
Characterization—summarizes and
combines outputs of the exposure and
toxicity assessments to provide a
quantitative (e.g., one-in-a-million excess
cancer risk) assessment of site-related risks.

The baseline risk assessment began with
selecting contaminants of concern which
would be representative of the risks posed
by the groundwater underlying the Site.
These contaminants included benzene, 1,2-
dichlorobenzene, chloroform,
tetrachloroethene, toluene, vinyl chloride,
xylene, phenol, arsenic, antimony, barium,
chromium, lead, and zinc.

The baseline risk assessment addressed the
potential risk to human health by identifying
potential exposure pathways by which the
public might be exposed to contaminant
releases at the Site under current and future
land-use conditions. There are no current
on-site groundwater users at the Site,
therefore there are no potential current
receptors at the Site. Potential off-site
receptors included residents to the east and
southeast of Gold Creek that use
groundwater as drinking water and
recreational users of Gold Creek.
Groundwater modeling, in conjunction with
measured groundwater concentrations,
sediment data from Gold Creek and
groundwater concentrations from off-site
residential wells, indicates that the plumes
have stabilized and that contaminants have
not migrated either to Gold Creek or to off-
site residences on the other side of Gold
Creek. Groundwater modeling results
indicate that contaminants are not expected
to migrate to or beyond Gold Creek. Thus,
current exposures to either off-site residents
or recreational users of Gold Creek are not
occurring and are not expected to occur in
the future. These exposure pathways
therefore, were not quantitatively evaluated
in the risk assessment.

The exposure pathway evaluated under the
potential future land-use scenario included
the exposure of industrial workers to the on-
site contaminated groundwater through
ingestion. Because the Site and land
immediately adjacent to the Site are
currently zoned exclusively for industrial
land  use, future residential or commercial
use of the Site is not expected to occur and
therefore, only industrial use of the Site was
evaluated in the risk assessment.  For
purposes of conducting the risk assessment
it was assumed that a future industrial
worker would drink 1  liter of water per day
from an on-site well for 5 days a week for
50 weeks a year (250 days/year with about 2

-------
weeks vacation) for 25 years out of a 70 year
lifetime.
EPA's acceptable cancer risk range is 10"4 to
10"6 which can be interpreted to mean that an
individual may have a one in ten thousand to
a one in a million increased chance of
developing cancer as a result of a site-related
exposure to a carcinogen over a 70-year
lifetime under the specific exposure
conditions at a site.

The results of the baseline risk assessment
indicated that the groundwater underlying
the Site poses no unacceptable carcinogenic
risk to industrial workers exposed to the
groundwater at the Site.  The sum of the
current cancer risks for industrial workers
was 1.4 x 10^ (approximately one-in-ten
thousand) which is considered to be within
the U.S. EPA target risk range of 10" tolO'6.
The main contributors to the total cancer risk
were arsenic, vinyl chloride, and benzene.

To assess the overall potential for
noncarcinogenic effects posed by the
groundwater contaminants at the Site, EPA
has developed the hazard index (HI). An HI
value of greater than 1 is considered to pose
a potential noncarcinogenic risk. The
calculated HI value was 0.55 which is below
the acceptable level of 1.0 indicating no
adverse health  effects to future industrial
workers. The main contributor to the total
noncancer risk was arsenic.

There are no impacts to ecological receptors
in Gold Creek, since contaminants in
groundwater have not migrated to Gold
Creek and are not anticipated to migrate
there in the future.
REMEDIAL ACTION OBJECTIVES

Remedial action objectives are specific goals
to protect human health and the
environment. These objectives are based on
available information and standards such as
applicable or relevant and appropriate
requirements (ARARs) and risk-based levels
established in the risk assessment.

The remedial action objective for the
groundwater beneath the Site is to reduce or
eliminate potential health risks associated
with ingestion of Site contaminated
groundwater by potential future industrial
workers and to reduce the concentration of
contaminants in the groundwater to drinking
water standards.

SUMMARY OF REMEDIAL
ALTERNATIVES

CERCLA at Section 121, 42 U.S.C. §9621
requires that each selected site remedy be
protective of human health and the
environment, be cost effective, comply with
other statutory laws, and utilize permanent
solutions and alternative technologies and
resource recovery alternatives to the
maximum extent practicable.  In addition,
the statute includes a preference for the use
of treatment as a principal element for the
reduction of toxicity, mobility, or volume of
the hazardous substances.

This Proposed Plan evaluates  in detail four
remedial alternatives for addressing the
contaminated groundwater beneath the
Carroll and Dubies Sewage Disposal Inc.,
Site.  Since contaminants will remain at the
Site above levels which allow for
unrestricted use and unlimited exposure,
each alternative would require five-year
                                           10

-------
reviews to ensure that the remedial action is
protective of human health and the
environment. Five-year reviews are
currently required as part of OU1.  As used
in the following text, the time to implement
a remedial alternative reflects only the time
required to construct or implement the
remedy and does not include the time
required to design the remedy, negotiate
with the responsible parties, or procure
contracts for design and construction, or
conduct operation and maintenance at the
Site.

Alternative  1: No Action

Capital Cost:          $ 0
0 & M/yr Cost:        $ 0
Present Worth:         $ 0
Time to Implement:    0 month

The Superfund program requires that the
"no-action" alternative be considered as a
baseline for comparison with other
alternatives.  As demonstrated through the
results of the groundwater modeling study,
naturally occurring processes for reducing
the concentration of contaminants in the
groundwater are at work at the Site. Under
this alternative, no action would be taken to
address the contaminated groundwater.
There would be no monitoring of these
naturally occurring processes in the
groundwater to evaluate the rate and extent
of the reduction and mobilization of
contaminants in the groundwater beneath the
Site. The period for the groundwater to
reach federal drinking water and State
drinking and groundwater standards was
projected through the groundwater modeling
to be approximately five years. The
remediation of the lagoons, which will be
implemented under OU1, would minimize
any additional contaminant contribution to
the groundwater.

Alternative 2: Natural Attenuation with
Institutional Controls and Monitoring
Capital cost:
O & M/yr Cost:
Present Worth:
Time to Implement:
$0
$ 58,000
$ 284,000
6 months
Similar to Alternative 1, Alternative 2 would
also rely on natural attenuation, with
intrinsic biodegradation as the principal
mechanism, to reduce contaminants in the
groundwater to drinking water standards.
The remediation of the lagoons, which will
be implemented under OU1, would
minimize any additional contaminant
contribution to the groundwater. This
alternative includes the implementation of
institutional controls, such as deed
restrictions, contractual agreements, local
law or ordinances or other governmental
action for the purpose of restricting
installation and use of groundwater wells
throughout the contaminated groundwater
plume. Groundwater monitoring at the  Site
and sediment sampling in Gold  Creek would
also be conducted.  These restrictions would
complement any restrictions implemented as
part of the OU1 remedy.  Institutional
controls restricting the use of Site
groundwater would be required until the
groundwater has been demonstrated to meet
federal drinking water and State
groundwater and drinking water standards.
This period was projected through the
groundwater modeling to be a five year
period necessary for the intrinsic
biodegradation and flushing mechanisms to
reduce the concentration of contaminants in
the groundwater to levels  below drinking
                                           11

-------
water standards.  Once these levels have
been demonstrated to be met, the restrictions
on groundwater use would no longer be
required.

As predicted by the groundwater modeling
results, the organic contaminants in the
groundwater would meet drinking and
groundwater standards within a period of
approximately five years after the
implementation of the OU1 remedy. This
alternative includes a component of initial
assessment of the groundwater parameters
which favor natural attenuation and a
groundwater monitoring requirement to
evaluate the rate and extent of reduction of
the organic contaminants in the
groundwater. The initial assessment would
include an evaluation for the presence of
constituent-degrading microorganisms, pH,
oxygen or other electron acceptors,
elemental nitrogen, phosphorous and other
parameters necessary to evaluate the
progress of natural attenuation. Groundwater
monitoring would be conducted on a
semiannual basis.

Alternative 3: Groundwater Pump and
Treat via Precipitation, Filtration and
Carbon Adsorption
Capital Cost:
O & M/yr Cost:
Present Worth:
Time to Implement:
$ 1,070,000
$  287,200
$2,105,000
 9 months
This alternative would consist of a series of
recovery wells used to capture contaminated
groundwater immediately downgradient of
the source areas or the lagoons.  The
recovery wells would capture the most
concentrated portion of the contaminant
plume emanating from the source areas.
Any impacted groundwater that would not
be captured by the recovery wells would be
naturally attenuated. This alternative would
eliminate the potential for migration of
organic contaminants off site. The recovery
wells would be located in that portion of the
outwash aquifer located downgradient of the
towpath.  Beneath the lagoons, a saturated
outwash unit does not exist.

The preliminary configuration of the
treatment system assumes that
approximately six wells would be used to
pump groundwater at controlled rates to
capture the impacted groundwater.  Two sets
of three pumping wells, each pumping at a
rate of 5 gallons per minute (gpm), would be
used. The total pumping rate of the six
wells is 30 gpm.  One set of wells would be
located between 100 feet to 150 feet
downgradient of lagoon 8. This set of three
wells would be designed to capture impacted
groundwater passing beneath lagoons 6, 7,
and 8. One set of wells would be located
between 100 feet to 125 feet downgradient
of lagoons 1 and 2.  This set of three wells
would be designed to capture impacted
groundwater passing beneath lagoons 1 and
2. The recovered groundwater would be
treated on-site through a series of treatment
processes. Conceptually, the treatment
system would consist of iron and suspended
solids removal via precipitation followed by
filtration and carbon adsorption. Following
treatment, the groundwater would be
discharged to Gold Creek in accordance
with the State Pollutant Discharge
Elimination System (SPDES) requirements.
Residuals generated from the treatment
processes would be managed in accordance
with the Resource Conservation and
Recovery Act (RCRA) regulations.
                                          12

-------
This alternative would also include
groundwater monitoring to measure the
effectiveness of the pump-and-treat system,
as well as the institutional controls specified
in Alternative 2. The treatment system
would be operated until contaminant levels
in the groundwater reach federal drinking
water and State drinking water and
groundwater standards, which has been
estimated to be approximately five years.

Alternative 4: In Situ Groundwater
Treatment
Capital Cost:
0 & M/yr Cost:
Present Worth:
Time to Implement:
$ 1,017,000
$   248,000
$ 1,912,787
 12 months
This alternative involves the injection of air
into the saturated zone  (i.e., below the water
table), via a  series of wells, to reduce the
volatile constituents dissolved in
groundwater. These wells would be located
in the same general vicinity as the pumping
wells outlined in Alternative 3, thus
allowing treatment of the most concentrated
groundwater plume. Any impacted
groundwater that would not be captured by
the in situ groundwater treatment system
would be naturally attenuated.  The levels of
organic constituents would be decreased in
the saturated zone during aquifer aeration
via mass transfer of the chemicals from the
water phase to the gaseous phase.  If the
levels of organic compounds exceed air
quality guidelines, then a soil venting
system would be installed in the subsurface
to collect the air emissions. The exhaust air
from the vapor extraction system would be
discharged to a treatment system. The
gaseous treatment system for this alternative
would be an activated carbon filter.
Groundwater monitoring would also be
conducted as part of this alternative to
evaluate the effectiveness of the air sparing
system. A reduction in the levels of
organics may also take place in the saturated
zone through the enhancement of
biodegradation due to the increase in
oxygen. With this alternative, air sparging
may be used in conjunction with vacuum
extraction and/or enhanced bioremediation
with the addition of nutrients.

A preliminary configuration of the aquifer
aeration system would consist of
approximately 30 air sparging wells. This
alternative would include the same
monitoring program and institutional
controls described in Alternative 3.
Treatment of the groundwater would
continue until contaminant levels in the
groundwater achieve federal drinking water
and State drinking water and groundwater
standards. This alternative would achieve
groundwater remediation  goals within about
five years .

EVALUATION OF ALTERNATIVES

During the detailed evaluation of remedial
alternatives, each alternative is assessed
against nine evaluation criteria, namely,
overall protection of human health and the
environment; compliance with applicable
and relevant and appropriate requirements
(ARARs); long-term effectiveness and
permanence; reduction of toxicity, mobility,
or volume through treatment; short-term
effectiveness; implementability; cost; and
community and state acceptance. For a
more detailed explanation, see the
comparative analysis contained in the FS.

-------
Glossary of Evaluation Criteria

*  Overall protection of human health and
the environment addresses whether or not a
remedy provides adequate protection and
describes how risks are eliminated, reduced,
or controlled through treatment, engineering
controls, or institutional controls.

A  Compliance with ARARs addresses
whether or not a remedy will meet all of the
applicable or relevant and appropriate
requirements and/or provide grounds for
invoking a waiver.

*  Long-term effectiveness and permanence
refers to the ability of a remedy to maintain
reliable protection of human health and the
environment over time, once cleanup goals
have been met. It also addresses the
magnitude and effectiveness of the measures
that may be required to manage the risk
posed by treatment residuals and/or
untreated wastes.

A  Reduction of toxicity. mobility, or volume
through treatment is the anticipated
performance of the treatment technologies a
remedy may employ.

•«•  Short-term effectiveness addresses the
period of time needed to achieve protection
from any adverse impacts on human health
and the environment that may be posed
during the construction and implementation
period until cleanup goals are achieved.

* Implementability is the technical and
administrative feasibility of a remedy,
including the availability of materials and
services needed  to implement a particular
option.
*•  Cost includes both estimated capital and
operation and maintenance costs, and net
present worth costs.

*  State acceptance indicates whether, based
on its review of the RI/FS report and
Proposed Plan, the State concurs with,
opposes, or has no comment on the preferred
alternative.

*  Community acceptance will be assessed
in the ROD and refers to the public's general
response to the alternatives described in the
RI/FS report and the Proposed Plan.

A comparative analysis of the remedial
alternatives based upon the evaluation
criteria noted above follows.

Overall Protection of Human Health and
the Environment

For No Action (Alternative  1) and Natural
Attenuation  with Institutional Controls and
Monitoring (Alternative 2), the
concentration of contaminants in the
groundwater would be reduced due to
natural attenuation of contaminants until
federal drinking water and State drinking
and groundwater standards are met. This
period has been estimated to be
approximately five years from
implementation of the OU1  remedy.  The
No Action alternative would present a
slightly greater risk to human health  and the
environment than Alternatives 2, 3, and 4 in
the short-term because the potential would
exist that an on-site worker could come in
contact with the contaminated groundwater.
Under Alternative 2, protection of human
health would be enhanced with the
implementation of institutional controls,
preventing the use of the contaminated
                                           14

-------
groundwater.

For the Pump-and-Treat (Alternative 3) and
In Situ Groundwater Treatment (Alternative
4) scenarios, the potential risks to human
health from potential exposure to impacted
groundwater would be reduced by removal
and treatment of contaminants in the
groundwater captured by the remedial
systems. These alternatives would achieve
groundwater remedial goals within about
five years. Institutional controls preventing
the use of Site groundwater would eliminate
the potential exposure to  contaminated
groundwater while the groundwater is being
remediated.  The contaminants would
continue to migrate until  attenuated under
Alternatives  1 and 2. However, impacts are
expected to be minimal since, as noted in the
risk assessment section, the levels of
contaminants in the groundwater present no
significant human health  risk under current
or future uses. Furthermore, impacts to
ecological receptors in Gold Creek from the
implementation of Alternatives 1 and 2
would be unlikely since contaminants in
groundwater have not migrated to Gold
Creek and are not anticipated to migrate
there in the future.

Compliance with ARARs

Actions taken at any Superfund site must
meet all ARARs of federal and state law or
provide grounds for waiving these
requirements. All of the alternatives have
been designed to achieve or comply with the
ARARs.

Since the groundwater at the Site is a future
potential source of drinking water,  federal
drinking water standards  (Maximum
Contaminant Levels [MCLs]) and New York
State Drinking Water Standards and New
York State Groundwater Quality Standards
are ARARs.  For No Action (Alternative 1)
and Natural Attenuation with Institutional
Controls and Monitoring (Alternative 2),
federal drinking water and State drinking
water and  groundwater standards would be
achieved over time through natural
biodegradation of organic contaminants in
the groundwater. The period for the
groundwater to reach federal drinking water
and State drinking and groundwater
standards was projected through
groundwater modeling to be approximately
five years. For the Pump-and-Treat
(Alternative 3) and In Situ Groundwater
Treatment (Alternative 4) scenarios,
groundwater standards would be met by
removal and treatment of contaminants in
the groundwater. The discharge of treated
groundwater to Gold Creek during
implementation of Alternative 3 would
comply with the Federal Clean Water Act
and State Pollutant Discharge Elimination
System (SPDES) regulations. The residual
sludges from the treatment system under
Alternative 3 would be treated or disposed
of off-site  in accordance with RCRA
regulations. The spent carbon generated
from the groundwater treatment system
under Alternative 3 and the gas treatment
system under Alternative 4 would either be
regenerated off-site or sent off-site for
treatment and disposal in accordance with
RCRA regulations.

Long-Term Effectiveness and
Permanence

With all four alternatives, after
approximately five years, the concentrations
of contaminants in the groundwater are
expected to be permanently reduced to
                                           15

-------
levels below ARARs. Implementation of
Alternatives 3 and 4 might result in a
slightly reduced time frame to achieve
ARARs downgradient of the lagoons.
Therefore, all alternatives are relatively
similar in terms of this criterion.

Reduction of Toxicity, Mobility, and
Volume through Treatment

Alternatives 1  and 2 rely solely on naturally
occurring mechanisms to reduce the toxicity
and volume of contaminants in the
groundwater. Although CERCLA has a
preference for treatment to reduce
contaminants,  Alternatives 1 and 2 would
reduce the contaminants in the groundwater
by natural attenuation process. Alternatives
3 and 4 are similar in their abilities to reduce
toxicity, mobility and volume and would
provide reduction of toxicity, mobility and
volume somewhat more rapidly than
Alternatives 1  and 2. Under Alternatives 3
and 4, treatment to reduce contaminants in
the groundwater would be achieved by
extraction of the contaminants and
subsequent treatment.

Short-Term Effectiveness

Alternatives 1  and 2 would have no adverse
effects at all on the community, site workers,
or the environment since there would be no
potential exposure to any of the
contaminants because no construction
activities would occur. Alternatives 3 and 4,
with potentially shorter time periods to meet
ARARs, rank highest in terms of this
criterion to meet the response objectives.
However, Alternatives 3 and 4 would
present greater impacts than Alternatives 1
and 2, due to construction activities. For
example, the construction of extraction wells
and piping to transport the treated
groundwater to Gold Creek would have
minor negative impacts on residents in the
area. These impacts would be associated
with the disruption of traffic, excavation on
public and private land, and noise and
fugitive dust emissions. Appropriate
measures, however, would be implemented
to minimize these impacts.

Implementabiliry

Alternative 1 - No Action is clearly the most
implementable. Alternative 2 would require
groundwater-use restrictions to prevent the
use of groundwater wells throughout the
contaminated aquifer; although sometimes
difficult to obtain, these restrictions are
being used at numerous sites. Alternative 2
would also require additional geochemical
and intrinsic biodegradation studies and
monitoring.  These studies and monitoring
requirements are being implemented at
numerous sites. Alternatives 3 and 4 would
be more difficult to implement due to
construction requirements. Additionally,
Alternative 3 would require that access be
obtained to construct the piping to transport
the treated groundwater to Gold Creek;
authorization to discharge treated water to
Gold Creek would add to the complexity of
implementing this remedy. Nonetheless,
these are successfully proven technologies
at the field scale and considered to be
readily implementable.

 Cost

There is no cost associated with the No
Action alternative. Alternative 2, Natural
Attenuation with Institutional Controls and
Monitoring, is the lowest cost alternative
with a present worth of $284,000.
                                           16

-------
Alternative 3, Groundwater Pump and Treat,
has the highest cost with a present worth of
$2,105,000. Alternative 4, In Situ
Groundwater Treatment, with a present
worth of $1,912,787, is slightly less than
Alternative 3.

Community Acceptance

Community acceptance of the preferred
alternative will be assessed in the ROD
following a review of the public comments
received on the RI/FS report and the
Proposed Plan. A response to comments
will be included in a Responsiveness
Summary, which will be attached to the
ROD.

State Acceptance

The State of New York concurs with the
preferred alternative

PREFERRED ALTERNATIVE

Based upon an evaluation of the various
alternatives, EPA and NYSDEC
recommend Alternative 2, Natural
Attenuation with Institutional Controls.
Long-term protection und'er this alternative
would be afforded by the reduction in the
concentration of contaminants in the
groundwater below the ARARs through
naturally occurring removal processes.  This
alternative includes the  implementation of
institutional controls, such as deed
restrictions, contractual agreements, local
law or ordinances or other governmental
action for the purpose of restricting
installation and use of groundwater wells
throughout the contaminated groundwater
plume, monitoring of the groundwater to
measure improvement in groundwater
quality and sediment sampling in Gold
Creek to ensure that contaminants have not
reached Gold Creek.

Since contaminants will remain on Site,
EPA will review the Site at least once every
five years to ensure that the remedy selected
continues to be protective of human health
and the environment.  If the natural
attenuation of contaminants in the
groundwater at the Site has not improved
groundwater quality to federal drinking
water and State drinking water and
groundwater standards, EPA and NYSDEC
will determine the need  for a program to
evaluate and implement contingency
alternatives for groundwater remediation at
the Site.

Alternative 2 addresses all of the media of
concern and provides the best balance of
trade-offs among the alternatives with
respect to the evaluation criteria.  EPA and
NYSDEC believe that the preferred
alternative will be protective of human
health and the environment, comply with
ARARs, be cost-effective, and utilize
permanent solutions to the maximum extent
practicable.
                                          17

-------
                                       A J VJ V. JXJJ 1

                                 SITE LOCATION MAP
                       Carroll and Dubies Site, Port Jerris, New York
Source:       USGS 7>/i MEN. Topographic Quad.
             Port Jerris North, NY-PA 1969

-------
    > t UN ICI^CWHC euwuxai >ur: MMI

tfttv«f NOIHH. HT-PA (Itttt,
xrwai r.i UN. «•«» OUMMMOI uiPi: ennui.

tfr <1ltl|. PWI XHvtf MO»IH. lrr.»X, l»«fl|.

jur»if ifiurii MJ-HT-^ (itti).
atwa couxn lu lur. «tv««o ]/>/•>.
                                                                                                                                 GRAVEL  PIT        V
                     CITY LANDFILL
                                                                                                                                 VOhlTOftiNC Kli M ClAOAt.
                                                                                                                                         '[»




                                                                                                                                       APPHO»IU»Tt 5CAl€ IN rtO
                                                                                            ANO OUBItS

                                                                                   OttR PARK, NtW YORK

                                                                                                                      CORRtMt UONKOftlHO W|((. IOCA1IOMS
                                                                                                                            POBI  JCRVIS. NtW
;.  IUI,AMUM>   ^



ST.	p^'-ipa
JORK	IflfiURt.fc   '''

-------
 Appendix B




Public Notice
      23

-------
                            * -   •   •       c.i     .,.•.•
                   The'Times Herald RECOUP ...... ' ' Tuesday: Sepferriber'TO. 1996
            PUBLIC  NOTICE
 U.S. Environmental Protection Agency
     Announces Public Meeting and Comment Period
                 on the Proposed Plan for the
 CARROLL AND DUBIES SEWAGE DISPOSAL SUPERFUND SITE
                      Port. Jervis, New York- g-
The United States Environmental Protection Agency (EPA) invites public comment on
its Proposed  Plan for remediating contaminated groundwater at the Carroll and
Dubies Sewage Disposal (C&D) Superfund Site in Port Jervis, New York. EPA will
accept comments during a public comment period which begins on August 27, 1996
and ends September 26,  1996. A public meeting  will be  held on Wednesday,
September 11, 1996 at 7:00 PM at the Port Jervis High School auditorium.

Complete analyses of the alternatives listed beiow are presented in the Remedial In-
vestigation/Feasibility Study and Proposed Plan, along with other documents csed by
EPA in the decision-making process for this Site. These documents are available for
public review at the following locations:
         Deerpark Town Hall                Port Jervis Public Library
         Route 209N                      1 38 Pike Street
         Drawer A                        Port jervis NY -| 2271
         Hugenot, NY 12746

The Proposed Plan evaluates four remedial alternatives for  addressing the contami-
nated groundwater beneath the Carroll and Dubies Sewage Disposal Inc. Site:
       Alternative 1 : No Action

       Alternative 2: Natural Attenuation with Institutional Controls and
                   Monitoring

       Alternative 3: Groundwater Pump and Treat via Precipitation,
                   Filtration and Carbon Adsorption

       Alternative 4: In Situ Groundwater Treatment
Based upon evaluation of the various alternatives, EPA recommends Alternative 2,
Natural Attenuation with Institutional Controls and Monitoring. This alternative would
rely on natural attenuation, with intrinsic biodegradation as the principal mechanism,
to reduce contaminants in the groundwater to drinking water standards. Groundwater
modeling results indicate that a five year period would be necessary for the intrinsic
biodegradation and flushing mechanisms to reduce the concentration of organic con-
taminants in the groundwater to levels below drinking water standards. This alterna-
tive includes the implementation of institutional controls for the purpose of restricting
installation and use of groundwater wells throughout the contaminated groundwater
plume, which is limited to the industrial area north of Gold Creek, in the vicinity of the
C&D property. Groundwater monitoring at the Site and sediment sampling in Gold
Creek would also be conducted.

Written comments must be postmarked no later than September 26,  1996 and sub-
mitted to:
                   Maria Jon, Project Manager
                   U.S. Environmental Protection Agency
                   290 Broadway, 20th Floor
                   New York, NY 10007-1866
                .  . (212)637-3967

-------
                    Appendix C




September 11,  1996 Public Meeting Attendance Sheets
                        24

-------
Q
O

Q.
lO
G>
\r>
   UNITED  STATES ENVIRON1-1ENTA1, PROTECTION AGENCY
                      REGION II
                    PUBLIC MEETING
                         FOR
          Carroll and  Dubiea  Superfund Sit"
                   Port Jervis, NY

            Wednesday,  September  11,  1996
                      ATTENDEES
r\j
.-«
r\j
                                             (Please Print Clearly)
           NAME
STREET
                                             CITY
ZIP
PHONE
REPRESENTING

-------
g
^
~
°"
uo
§
1/1
5
(M
                     UNITED STATES ENVIRONMENTAL  PROTECTION AGENCY
                                       REGION  II
                                     PUBLIC MEETING
                           Carroll  and Dubies Superfund Site
                                    Port Jervis, NY

                             Wednesday, September  11,  1996
                                       ATTENDEES
                                 (Please Print Clearly)
NAME
STREET
   CITY

XAA///CI//
ZIP
                                                                     PHONE
                                                                    REPRESENTING

-------
S

R
ID
rvj
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                  REGION II
                PUBLIC MEETING

                     FOR
       Carroll  and Dubies  Superfund  Site
               Port Jervis, NY

        Wednesday, September 11, 1996
                  ATTENDEES
                                            (Please Print Clearly)
                                                                                                          g
NAME
STREET
CITY
ZIP
                                   PHONE
                                                                              REPRESENTING
                                                         /ofro

                        zo
 §
 ID
 IR
 T-4
 A
 ib
 in

-------
                 Appendix D




September 11, 1996 Public Meeting Transcript
                     25

-------
                                            COPY
             CARROLL and DUBIES
               SUPERFUND SITE
                       Wednesday,

                       September  11,  1996

                       7:05  p.m.

                       Port  Jervis  High School

                       Route 209

                       Port  Jervis, New York

BEFORE:

       NATALIE LONEY,
            Public Outreach Branch

       MARIA JON,
            Remedial Project Manager

       DOUG GARBARINI,
            Chief of the Eastern New York
            Remediation Section

       LINDA ROSS,
            Hydrogeolegist
                      Jacqueline Maloney,  CSR
                      Certified Court Reporter
            ROCKLAND & ORANGE REPORTING
               20 South Main Street
             New City,  New York  10956
                  (914)  634-4200

-------
                                                    2



 1                         Proceedings



 2                  MS.  LONEY:   We're going



 3             to  get  started.



 4                  We're  going  to  start  by way of



 5             introducing all of the participants  who



 6             are  here.   My  name is  Natalie Loney,  I'm



 7             with the  Public Outreach Branch in EPA,



 8             and  starting from my left  is Maria Jon,



 9             who  is  the  RPN for the Carroll and Dubies



10             Site, next  to  her is Doug  Garbarini,  who



11             is  the  Chief of the  Eastern,  New York



12             Remediation Section, and next to Doug is



13             Linda Ross,  who is an  EPA  Hydrogeologist,



14             and  she is  specializing in groundwater.



15                  I'd  like  to  thank all of you for



16             coming  out  this evening.   We're here  to



17             discuss and to present to  you the results



18             of the  remedial investigation and to



19             present our proposed plan  for remediating



20             the  Carroll and Dubies Site.



21                 After  my  brief  introduction,  Doug



22             Garbarini will be coming before you.  He



23             will give you  a brief  overview of the



24             Superfund Program, followed by Maria  Jon,



25             who  will give  the results  of  the remedial

-------
                                                    3



  1                         Proceedings



  2             investigation,  in addition to our proposed



  3             plan  and  an  explanation of the plan.  That



  4             will  be followed by questions and



  5             answers.   I  will then come back to  the



  6             podium and open the floor for questions



  7             and we will  hopefully provide the



  8             answers.



  9                  Many of you have received in the mail



10             a copy of the proposed plan and we  also



11             had a brief  one page flier that was also



12             enclosed  in  the mailer,  which gives a



13             little bit of the detail in terms of what



14             the proposed plan is,  in addition,  it



15             gives the dates for the opening and



16             closing of the comment period.  We're



17             going to  present the plan to you and open



18             the floor not only for questions tonight,



19             but we are requesting that you submit



20             comments  to us.   The person that you would



21             be submitting the comments to is Maria



22             Jon,   and  her address is  on the bottom of



23             the sheet.  If you don't have one, there



24             are some  of the  handouts at the end.  The



25             closing date for the comment  period is in

-------
                                                    4



  1                         Proceedings



  2             fact  September 27,  1996,  so we're



  3             requesting that all formal  written



  4             comments  be submitted to  our office  by



  5             that  date.



  6                  In addition, we have Tim Vickerson,



  7             from  the  New York State Department of



  8             Health, here who can answer some questions



  9             for you as  well.



10                  So without further adieu,  let me



11             bring up  Doug Garbarini and we're  going to



12             open  the  meeting.   Thank  you.



13                  MR.  GARBARINI:   Thank  you, Natalie.



14                  First  of all,  I'd  like to  thank all



15             of you for  coming out tonight.  I  see a



16             lot of familiar faces.  I've  been  out for



17             a couple  of  other public  meetings  over the



18             last  few  years.  The  last time  I was out



19             here  was  about  two  years  ago  when  we came



20             out to discuss  the  remediation  of  the



21             source areas  for the  lagoons  at the



22             Carroll and  Dubies  Site.



23                  And  as  you're  all  probably very well



24             aware, we did select  a  remedy,  a rather



25             complex remedy, which called  for treating

-------
  1




  2




  3




  4




  5




  6




  7




  8




  9




10




11




12




13




14




15




16




17




18




19




20




21




22




23




24




25
             Proceedings



 the  lagoons,  materials in the  lagoons,  and



 the  soils  around those lagoons, and  that



 remedy  was  selected last year.



     Tonight  we're here to discuss the



 remedy  for  the groundwater at  the Site.



 So we've basically partitioned the Site



 off  into two  separate, well, as we call



 them, operable units that allowed us to



 move forward  with the project  in a more



 expedited fashion.  We are already in the



 middle  -- but not in the middle,  but



 underway with the remedial design for the



 treatment of  the lagoons.   So tonight,



 since we had  to collect additional data



 before we make the decision on the



 groundwater, we're here tonight to discuss



 our groundwater investigation and the



proposed plan for the  groundwater.



     What I'm going to do  is just give you



a brief overview of the Superfund process,



 in about ten minutes  or so,  give  you an



idea how the program  came  about and where



 it's headed.



     Superfund was  passed  in 1980.

-------
                                                    6



  1                         Proceedings



  2             Superfund Law is also more formally known.



  3             as Comprehensive Environmental Response,



  4             Compensation,  and Liability Act, or



  5             CERCLA.   It  was  passed in 1980 by



  6             Congress.  Basically it was passed in



  7             response  to  a  number of natural



  8             environmental  disasters that were



  9             occurring  in terms  --  when I say natural



10             environmental  disasters I'm really talking



11             about  hazardous  --  the uncovering of



12             hazardous  waste  sites,  most notably,  I'm



13             sure you all have heard about Love Canal



14             in  the past.



15                 At that point  in  time the Federal



16             Government really didn't  have a mechanism



17             for dealing with such  sites,  with



18             hazardous waste  sites,  it  was really



19             crisis management.   There  were a number  of



20             them springing up across  the  Country.



21             People were pointing fingers,  saying,



22             well, how are we going  to  get the work



23             done?  Who's responsible?   Where  is  the



24             money going to come  from?   How can we get



25             those that were responsible  for the

-------
                                                   7
 1                        Proceedings
 2            contamination to take part in the
 3            cleanup?  And it was a very complex issue
 4            that Congress first passed CERCLA or
 5            Superfund in 1980,  and the idea was to
 6            provide a Superfund or pot of money that
 7            could be used to address abandoned
 8            hazardous waste sites.
 9                 Congress at the time we were looking
10            at a two-pronged program.  He were looking
11            as those sites that could be studied
12            rather extensively  before a decision was
13            made so that we could move forward with an
14            appropriate remedial action,  and we were
15            also looking at sites that presented a key
16            health risk, that were real,  real
17            problems.  Just to  give you an example, if
18            you can imagine having a whole load of
19            drums uncovered on  a school yard or
20            someplace where children would be playing,
21            perhaps they were leaking or they were
22            exposed to conditions that were hazardous
23            when these drums were revealed.  Those
24            sorts of situations would present a key
25            health threat,  and  EPA has mechanisms

-------
                                                   8
 1                        Proceedings
 2            whereby we can go out and take immediate,
 3            rather rapid removal actions.  And we've
 4            conducted more than 3,000 of these across
 5            the Country, it's been a very successful
 6            portion of pur program.
 7                 The other side of the program is the
 8            remedial side of the program, which we're
 9            discussing here tonight, includes sites
10            like the Carroll and Dubies Site, which
11            are on the National Priorities List.
12                 The other thing that CERCLA or
13            Superfund gave us was mechanisms to force
14            those parties that were responsible for
15            the contamination to cleanup the
16            contamination.  By responsible parties we
17            refer to them as PRP's or potentially
18            responsible parties.  And they are those
19            parties that generate waste that was
20            disposed of at a Superfund site,
21            transported waste that was disposed of at
22            a Superfund site, that operated a waste
23            disposal processes at the site or that are
24            current or were formerly owners of the
25            site during times of waste disposal.  And

-------
                                                    9



 1                         Proceedings



 2             it  gave  us  some  real,  real clout which we



 3             did not  have before,  which allowed us



 4             basically to request  that  the  PRP's do



 5             work on  consent,  and  it  also gave us the



 6             ability  to  order them to do the  work.   And



 7             if  those two mechanisms  were not



 8             successful,  it gave us an  approach whereby



 9             we  could go  back after the responsible



10             parties,  once we had  completed the cleanup



11             at  the site,  and try  and recover costs



12             from them at that point  in time.



13                  You might ask, well,  how  does a site



14             like the Carroll  and  Dubies Site or any



15             other sites  in New York  become a National



16             Priorities List  Site?  It's a  rather



17             complicated  process, but the first step of



18             the  process  is for the site to be  listed



19             on a Preliminary List, or  what we  call  our



20             Surplus  List, and there  are more  than



21             30,000 of these  types  of sites that  have



22             been evaluated across  the  Country.   There



23             are  more  than 1,700 of these that  were



24             located  in New York State.



25                  And  we  go through a process where  we

-------
                                                   10
 1                        Proceedings
 2            do preliminary assessments and site
 3            inspections, if necessary, to try and
 4            determine whether the sites should be
 5            included on the National Priorities List.
 6                 As you can see here, we've really
 7            done a pretty thorough job of looking at
 8            almost all the sites.  There are about 130
 9            that have not been evaluated to date, but
10            most of them have either been dealt with
11            and are being deleted,  they no longer need
12            to be on the National Priorities List,  or
13            there's a big bunch here that we're still
14            trying to decide whether they should be
15            put on the list or not.
16                 As you can see,  there are 89 sites
17            that are on the National Priorities List
18            in the State of New York.  I'd say
19            approximately a quarter  of those are
20            located in Long Island,  if you want to get
21            a. feel for the density of sites across the
22            State.
23                 So most of those 89 sites have had
24            remedies selected for them and are -- you
25            know,  we've completed our investigation,

-------
                                                    11
 1                        Proceedings
 2            we've decided what sort of remedies need
 3            to take place at these sites.
 4                 Okay.  Once we've gotten through the
 5            preremedial phase, as we call it, we've
 6            discovered the site, we've ranked it,
 7            placed it the National Priorities List, as
 8            I discussed before, we are also able to
 9            conduct immediate removal actions at these
10            sites or other sites requiring immediate
11            response.
12                 We then get into the remedial studies
13            phase, and we start off with a remedial
14            investigation.  We go out and we sample
15            the soils, the groundwater, the air,
16            whatever streams nearby,  whatever might be
17            necessary to try and determine,  you know,
18            how extensive the contamination is,  what
19            type of contamination you have;  do you
20            have volatile organic compounds,  solvents,
21            do you have heavy metals.   We then move
22            forward and utilize this  information and
23            try and discern what sort of risk these
24            contaminants pose to people or to the
25            environment,  ecological receptors.  If

-------
                                                   12
 1                        Proceedings
 2            these risks are deemed to be unacceptable,
 3            we then have to look at means for reducing
 4            the risk to acceptable levels, and we do
 5            that in what's call a feasibility study.
 6            A feasibility study lays out different
 7            alternatives for reducing the risks to
 8            acceptable  levels.   When we're doing the
 9            feasibility study we evaluate each of
10            these alternatives  against nine criteria.
11            And the two most important of those are
12            overall protection  of human health and the
13            environment,  and compliance with all
14            environmental regulations.
15                 In doing this  comparison we then come
16            out with what we feel is the best
17            alternative using these nine criteria,  and
18            we put that alternative forward in what's
19            called a proposed plan,  which is what
20            we're here  to discus tonight, and we open
21            up a public comment period, we take
22            comments at the public meeting, we'll
23            also, as Natalie said,  take comments in
24            writing. We'll go  back to our offices and
25            review all  these comments and make

-------
                                                    13



 1                         Proceedings



 2            modifications to the remedy, if necessary,



 3            but these  responses are all put forward  in



 4            a document called the Responsiveness



 5            Summary, which becomes part of a larger



 6            document, which is called the Record  of



 7            Decision.  This Record is Decision is



 8            signed by the highest ranking official in



 9            our regional office, the Regional



10            Administrator.



11                 This remedy is -- this Record of



12            Decision lays out a conceptual remedy for



13            cleaning up the site.  We then go into the



14            construction phase.  The first step there



15            is the remedial design.  As I mentioned



16            before, we are currently in the remedial



17            design phase for treating the lagoon



18            sediments, but a remedy has already been



19            selected there,  as I mentioned.  The



20            remedial design phase is the nuts and



21            bolts.  If you're going to have to build



22            the groundwater treatment system,  you



23            decide where you want to place the wells,



24            what sort of pipe you're going to have,  if



25            it's going to be housed in a building, you

-------
                                                   14



 1                        Proceedings



 2            decide how the building is going to be



 3            built, how large it's  going to be,  where



 4            the doors are going to be,  the typical



 5            design type issues  like if you're just



 6            building your own home.



 7                 Then we go out and do the remedial



 8            action.   This is where we  actually get in



 9            and move the earth,  if earth needs  to be



10            moved, build our treatment  systems,  if



11            they need to be built,  and start the



12            actual cleanup of the  site.   Subsequently



13            we move  then to monitoring,  if necessary,



14            and we start closeout  procedures for the



15            site,  and then we go through a deletion



16            process,  whereby the site  is deleted from



17            the National Priorities  List.



18                 As  I mentioned earlier,  there  are



19            approximately 89 -- well,  there  are  89



20            sites  on the NPL, National  Priorities



21            List,  in New York State.   There  are  about



22            1,200  that have been included on the list



23            across the Country.



24                 There really isn't  any  typical



25            Superfund site per  se.   As  I  think  I've

-------
                                                    15



 1                         Proceedings



 2            probably mentioned to some of you  in  the



 3            past, we've  got all sorts of sites with



 4            different types of contamination.  We have



 5            half acre -- sites as small as a half acre



 6            down in Long Island.  We've got, you know,



 .7            landfills that approach 100 acres or



 8            more.  We've got sites out West that are



 9            old mine sites that might even be as large



10            as 200 square miles.



11                 The cost for cleaning up a site, also



12            ranges, you know, very widely.  On



13            average, a Superfund site costs about 25



14            to 30 million dollars to cleanup.



15            Obviously, some of those may run into the



16            hundreds of millions of dollars, others



17            maybe not, just be in the hundreds of



18            thousands or not cost the State anything



19            at all in terms of the remedial action at



20            the site.



21                 In terms of time frame,  it is a very



22            long and complex process.   It takes, on



23            average, about ten years to move from the



24            investigation phase to the cleanup phase.



25            So it's not a quick process.   It's not

-------
                                                   16

 1                        Proceedings


 2            like our removal  program,  but it is a very

 3            thorough process,  to  say the least.

 4                 Just to give you an idea of the sort

 5            of  expenditures we've made in New York


 6            State.   As you can see here,  this is a


 7            chart that shows  expenditures and


 8            settlements in New York State through


 9            1995.   The total  is approximately 1.3
                                            ••
10            billion dollars.   Remedial expenditures,


11            i.e.,  the funds,  money that came out of


12            the funds of  Superfund that has  not been


13            replaced is 400 million.   We've  had

14            settlements in the amount  of  over 800

15            million dollars.   So  the enforcement


16            program has been  quite successful and

17            we've been able to get a lot  of  money in


18            for the State --  for  cleanups in the State

19            of  New  York.


20                As I stated before, the  program is a

21            very complex  one.   I  think when  Congress

22            originally passed  the  Law  in  1980 there

23            was a feeling that  we  needed  to  put

24            something together  quickly, that this was

25            not going to be a  long-lived  program,

-------
                                                    17



 1                         Proceedings



 2            might last  in  the order of a decade.  I



 3            think they  felt the cleanups were going to



 4            be a little  bit easier, maybe they'd  be



 5            more contained and we might just go in and



 6            put some soil  over or cap over sites  and



 7         •   you might be removing a bunch of drums and



 8            things like  that, but the program has



 9            become much  more complex.  We're really



10            just getting a better feel for it these



11            days.  I think in 19 -- the Law was first



12            passed in 1980 in the amount of 1.6



13            billion dollars for a five year period.



14            It was reauthorized in 1986 at a run of



15            about 8.6 billion.  So you're looking at



16            close to 1.6 billion a year.   So Congress



17            realized how complex the program was,  and



18            we're trying to work out the kinks of the



19            program now.  We have a bunch of



20            administrative reforms that are helping us



21            move along in the process at this point.



22                 And I think that's pretty much all  I



23             had to say.   I'll turn it over to Maria



24             now,  she'll  discuss the second operable



25             unit,  the groundwater remedy with you, get

-------
                                                   18



 1                        Proceedings



 2            into the details of the sampling analysis



 3            and various alternatives that we evaluated



 4            at the Site.



 5                 MS. JON:  Thank you, Doug.



 6                 I'm going to begin by giving you a



 7            presentation on the background of the



 8            Site, the findings of the remedial



 9            investigation, the result of the risk



10            assessment, the feasibility study, and



11            then I will discuss and describe all the



12            alternatives that we evaluated and the



13            preferred alternative.



14                 Site background.  The Carroll and



15            Dubies Superfund Site is located on Canal



16            Street in the City of Port Jervis.



17                 This is a map of the Site and the



18            surrounding land.  So the shaded area



19            right here represents the Carroll and



20            Dubies Sewage Disposal  Site.   The Site,  as



21            well as the land surrounding the property,



22            is being used for industrial purposes.



23            It's currently being used for that



24            purpose.   The City of Port Jervis Landfill



25            is located on the southern portion of the

-------
                                                    19



 1                        Proceedings



 2            Carroll and Dubies  Site.   The  landfill is



 3            currently inactive;  however, it's been



 4            used for the  -- as  a solid waste transfer



 5            station.  We  also have a  gravel operation



 6            right here.   Gold Creek is located 1,500



 7            feet downgradient from the Site.  The



 8            closest groundwater  treatment  wells



 9            downgradient  from the Site are located



10            south of Gold Creek.  These dots here



11            represent the drinking water wells that we



12            have identified during the investigation.



13            The Neversink River  is right here.



14                 The Carroll and Dubies Site was used



15            for the disposal of  septic and municipal



16            and industrial waste from  1970 to 1979.



17            The waste was disposed of  into several



18            unlined lagoons on the Site.  The waste



19            which contained hazardous  substances were



20            placed on these lagoons on the property.



21                 Lagoon one is located here,  two,



22            three,  four.   Five was never used for the



23            disposal of industrial waste.  Six and



24            seven and eight are  located here.   This is



25            a close-up of the Site.  And to locate

-------
                                                    20



 1                        Proceedings



 2            you, this is the City of Port Jervis



 3            Landfill, this is Gold Creek, and the



 4            Sewage Disposal Site is up here.



 5                 EPA placed the Carroll and Dubies



 6            Sewage Disposal Superfund Site on the



 7            Superfund National Priorities List in



 8            February 1990 because hazardous substances



 9            were released from the facility.  A



10            Consent Order was signed by EPA and the



11            potentially responsible parties in



12            February 1990.  The Consent Order required



13            the responsible parties to complete a



14            remedial investigation to determine the



15            nature and the extent of the contamination



16            at the site and to complete the



17            feasibility study to evaluate cleanup



18            alternatives.  Both the remedial



19            investigation and the feasibility study



20            have been completed by the responsible



21            parties.



22                 Site remediation activities at



23            Superfund sites are sometimes segregated



24            into different phases or operable units so



25            that remediation of different

-------
                                                   21



 1                        Proceedings



 2            environmental media can proceed



 3            separately.  So at this Site EPA has



 4            designated two operable units.  Operable



 5            Unit One, or OU1,  addresses the



 6            contaminated materials and surrounding



 7            soil from Lagoons  1,  2, 3, 4, 6, 7 and 8.



 8                 Operable Unit Two, or OU2,  addresses



 9            the contaminated groundwater beneath and



10            downgradient of the Carroll and Dubies



11            Property.



12                 Operable Unit 1,  which represents the



13            lagoons,  are contaminated with heavy



14            metals and organic compounds.  A Record of



15            Decision was issued by EPA on March 31,



16            1995.   The Record  of  Decision requires



17            excavation and on-site treatment of



18            approximately 20,000  cubic yards of



19            contaminated materials and soils.   The



20            treated material is going to be  placed in



21            a lined cell which is  going to be built



22            on-site and then it would be capped.   The



23            disposal  cell will have a leachate



24            collection system, as  well as groundwater



25            monitoring.

-------
                                                   22
 1                        Proceedings
 2                 The remedy for the lagoon is
 3            currently in the design phase.  We expect
 4            implementation of the remedy in 1998.
 5                 Operable Unit Number 2, which
 6            addresses the contaminated groundwater
 7            beneath and downgradient of the Carroll
 8            and Dubies Site, is going to be the
 9            subject of my presentation.
10                 The nature and the extent of the
11            groundwater contamination found beneath
12            the Site was assessed through sampling of
13            the groundwater, sediments in Gold Creek,
14            residential wells nearby and through
15            groundwater modeling.
16                 The groundwater modeling is like a
17            computer monitor that was used to
18            determine the fate and transport of the
19            groundwater contaminants found at the
20            Site.
21                 The groundwater investigation
22            conducted at the Site have identified two
23            aquifers, the shallow and the bedrock
24            aquifer or a deep aquifer.
25                 Groundwater beneath the Site flows to

-------
                                                   23
 1                        Proceedings
 2            the southeast,  in this direction, to Gold
 3            Creek.
 4                 The shallow aquifer is contaminated
 5            with organic compounds, mainly volatile
 6            organic compounds,  chlorinated
 7            hydrocarbons.   The  contaminants that were
 8            found include  benzene,  dichloroethene and
 9            tetrachloroethene.   These compounds are
10            known to degrade in the environment or in
11            the groundwater under certain conditions,
12            they decompose  from toxic to less toxic
13            compounds due  to natural occurring
14            microorganisms  in the groundwater.  The
15            deep aquifer is not contaminated.  The
16            highest concentrations  in the groundwater
17            were found near the lagoons.  These are
18            the lagoons.
19                 Two plumes of  organic compounds were
20            identified in  the groundwater.   One plume
21            is  emanating from Lagoons 1 and 2, and the
22            other plume is  emanating from Lagoon
23            Number  8.
24                 The groundwater investigation
25            conducted at the Site have identified at

-------
 1
 2
 3
 4
 5
 6
 7
 8
 9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
                                      24
             Proceedings
 the  highest  levels found near the  lagoons
 and  that the concentrations further
 downgradient from the lagoons have
 significantly decreased.  So the levels
 found  down here are very low compared to
 the  levels that were found near the
 lagoons,  which would give you an
 indication that there is some attenuation
 or biodegradation of contaminants in the
 groundwater.
     The  sediment sampling conducted in
 Gold Creek,  the analysis indicates that
 the sediments in Gold Creek have not been
 impacted  by  contaminants from the Carroll
 and Dubies Site.
     The  private and residential wells
 that are  located south of Gold Creek were
 also analyzed by the New York State
 Department of Health,  and the results show
 that those wells have not been impacted by
 the Site  contaminants.
     The  groundwater modeling conducted as
part of the investigation was to determine
whether the organic contaminants in the

-------
 1                        Proceedings



 2            groundwater have stabilized due to



 3            biodegradation and also was conducted to



 4            estimate the future migration of those



 5            contaminants and also the  future



 6            concentration of those contaminants in the



 7            groundwater.  The results  of the



 8            groundwater modeling indicates that there



 9            is potential --  there is a potential for



10            the organic contaminants to biodegrade in



11            the groundwater,  that the  contaminants



12            have not reached Gold Creek,  and they are



13            not expected to  reach Gold Creek.   And



14            also,  the modeling results indicate that



15            contaminants in  the groundwater would



16            reach drinking water standards five years



17            after the remediation of the lagoons.



18                 The risks posed by the Site



19            groundwater.  Based upon the groundwater



20            investigation conducted at the Site,  a



21            risk assessment  was conducted by EPA to



22            estimate the risks associated with current



23            and future Site  conditions.   The risk



24            assessment estimates the human health and



25            ecological risk  posed or that could pose

-------
 1
 2
 3
 4
 5
 6
 7
 8
 9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
                                     26
            Proceedings
by the contaminants in the groundwater if
no remediation were taken.  So because
this Site and the land immediately
adjacent to this Site has been zoned
exclusively for industrial use, and future
residential and commercial use of the
property is not expected to occur, we in
the risk assessment, we only assume
industrial use of the property.  So on the
current industrial use there is no --
there are no current groundwater users at
this Site, therefore, no current human
health risks associated with the
contaminated groundwater at the Site.
However, there is a future risk for an
on-site industrial worker who could drink
contaminated at the Site if the
groundwater drinking water well would be
installed on the property and the risk was
estimated to be one in 10,000.  Which is
within EPA's acceptable risk range.  There
are some assumptions that were used to
estimate the future risk for an industrial
worker drinking contaminated groundwater

-------
                                                   27
 1                        Proceedings
 2            were the following:   That a future
 3            industrial worker would drink one liter a
 4            day of contaminated  water for five days a
 5            week,  for 50 weeks a year,  for 25 years
 6            out of a 70 year lifetime.
 7                 The risk assessment also concluded
 8            that there is no risk to ecological
 9            receptors in Gold Creek, because the
10            contaminants have not reached Gold Creek
11            and they're not  expected to reach Gold
12            Creek.
13                 Remedial Action Objectives.   Remedial
14            action objectives are goals to protect
15            human health and the environment.   The
16            goals for cleaning up the Site are to
17            minimize or eliminate potential health
18            risks posed by drinking contaminated
19            groundwater by a potential  future
20            industrial worker, and to reduce the
21            concentration of contaminants in the
22            groundwater to drinking water standards.
23                 Four cleanup alternatives were
24            evaluated in the feasibility study to meet
25            the remedial objectives that have been

-------
 1
 2
 3
 4
 5
 6
 7
 8
 9
10
11
12
13
14
IS
16
17
18
19
20
21
22
23

25
                                      28
             Proceedings
previously  described.  These alternatives
are Alternative 1, which is no action;
Alternative  2, which  is natural
attenuation; Alternative 3, which is
groundwater  pump and  treat; Alternative 4,
which is in  situ groundwater treatment.  I
will briefly discuss  each one of these.
     For Alternatives 2, 3 and 4
institutional controls and groundwater
monitoring will be required for these
three alternatives.   For all the
alternatives a review every five years
would be required by  EPA so that that
would assure that the remedy that would be
selected for the Site continues to be
protective.
     So under the Alternative 1,  no
action,  the  Superfund Program requires
that the no  action alternative be
considered as a baseline for comparison
with other alternatives.  Under this
alternative  no action will be taken to
address the  contaminated groundwater.
Although groundwater monitoring as

-------
                                                   29
 1                        Proceedings
 2            indicated the contaminants in the
 3            groundwater will reach drinking water
 4            standards due to natural biodegradation of
 5            the contaminants in the groundwater, there
 6            would be no monitoring of the groundwater
 7            to measure the rate of reduction of these
 8            organic contaminants in the groundwater
 9            and there would be no institutional
10            controls to prevent the use of the
11            contaminated groundwater.  There is no
12            cost associated with Alternative
13            Number 1.
14                 Alternative Number 2 is natural
15            attenuation.  Alternative Number 2 would
16            rely solely on natural attenuation to
17            reduce the organic contaminants in the
18            groundwater to drinking water standards.
19            The groundwater monitoring results
20            indicate that after remediation of the
21            lagoons, the levels in the groundwater
22            would reach drinking water standards in
23            approximately five years after remediation
24            of the lagoons.   The remediation of the
25            lagoons will remove the sources of the

-------
                                                   30
 l                        Proceedings
 2            groundwater contamination and will
 3            eliminate any additional contribution of
 4            contaminants in the groundwater.
 5            Groundwater monitoring will be conducted
 6            under this alternative to measure
 7            improvements in groundwater quality.
 8            Institutional controls to prevent the
 9            installation of groundwater wells and the
10            use of contaminated groundwater throughout
11            the entire Site would be required, as well
12            as sediment sampling in Gold Creek.  The
13            estimated cost associated under -- with
14            Alternative 2 is approximately $284,000,
15            and it will take about six months to
16            implement.
17                 Alternative Number 3,  which is
18            groundwater pump and treat.  This
19            alternative consists of using recovery
20            wells to extract contaminated
21            groundwater.  Approximately six recovery
22            wells will be placed on the Site, they
23            will be placed immediately downgradient of
24            the lagoons.  These are the approximate
25            locations.  Three under Lagoons 1 and 2

-------
                                                    31



 1                        Proceedings



 2            and 3 downgradient of Lagoon Number  8.  At



 3            this location the recovery wells will



 4            capture the most contaminated portion of



 5            the groundwater.  The portion of the



 6            contaminated groundwater that's not going



 7            to be captured by these recovery wells



 8            will be left to attenuate naturally.  This



 9            alternative includes groundwater



10            monitoring to measure or to evaluate



11            effectiveness of the groundwater system



12            and also institutional controls similar to



13            those that I have discussed under



14            Alternative Number 2.  The groundwater



15            pump and treat system would continue to



16            operate until the levels of organic



17            contaminants in the groundwater reached



18            drinking water standards,  and from the



19            groundwater modeling that  was conducted at



20            the Site that to reach drinking water



21            standards was estimated to be



22            approximately five years.



23                 Under Alternative 3,  the estimated



24            cost is 2.1 million dollars and it would



25            take nine months to implement.

-------
                                                   32
 1                        Proceedings
 2                 Alternative Number 4, which is in
 3            situ or in place groundwater treatment.
 4            This alternative consists of injecting air
 5            into the contaminated groundwater through
 6            a series of injection wells.
 7            Approximately 30 injection wells would be
 8            used to treat the contaminants in the
 9            groundwater, they would be placed
10            immediately downgradient of the lagoons.
11            These circles represent clusters of air
12            injection wells.  These wells would treat
13            the most contaminated portion of the
14            plume, and the portion of the plume that's
15            not going to be captured or treated by the
16            air treatment system would be left --
17            would be attenuated naturally.  The
18            organic contaminants in the groundwater
19            would be reduced by transferring
20            contaminants from the groundwater to the
21            air.  A soil air venting system would be
22            installed in the subsurface to capture any
23            air emissions and the air emissions would
24            be treated on-site.  Groundwater
25            monitoring would be required in order to

-------
                                                    33



 1                         Proceedings



 2            measure  the  effectiveness of the air



 3            treatment  system.  Institutional controls



 4            similar  to those I have discussed on  the



 5            Alternatives 2 and 3, as well as the



 6            groundwater monitoring, would be required



 7            under Alternative 4.  The estimated cost



 8            for Alternative Number 4 would be 1.9



 9            million  dollars, and it would take about



10            12 months  to implement.



11                 Regarding Alternative Number 3,  the



12            groundwater pump and treat system remedy,



13            the extracted groundwater that would  be



14            collected  from the recovery wells would be



15            treated  on-site and then would be



16            discharged to Gold Creek in accordance



17            with the State and Federal Requirements,



18            which I  forget to mention before.



19                 There are nine criteria that we use



20            to evaluate remedial alternatives.   These



21            criteria are divided into three different



22            sets, and  they are the threshold criteria,



23            which includes the overall protection of



24            human health and the environment, and



25            compliance with environmental

-------
                                                   34
 1                        Proceedings
 2            regulations.
 3                 The second set, which are the primary
 4            balancing criteria, are long-term
 5            effectiveness and permanence, reduction of
 6            toxicity, mobility or volume through
 7            treatment,  short-term effectiveness,
 8            implementability,  and cost.
 9                 And the last  set is the modifying
10            criteria; State acceptance and community
11            acceptance.
12                 Based upon these evaluation criteria,
13            EPA's preferred alternative is Alternative
14            Number 2, which is natural attenuation
15            with institutional controls and
16            groundwater monitoring.
17                 Alternative 2 consists of several
18            actions to  address the groundwater
19            contamination beneath and downgradient of
20            the Carroll  and Dubies Sewage Disposal
21            Site.  This  remedy relies on natural
22            attenuation  of the organic contaminants to
23            reduce the  contaminants  in the groundwater
24            to levels below drinking water standards.
25                 The length of time  that was estimated

-------
                                                   35



 1                         Proceedings



 2            that  the  groundwater would reach drinking



 3            water standards, it's about --it was to



 4            be about  five years, following



 5            implementation of the lagoon remedy.  The



 6            lagoon remedy would remove the source of



 7            the groundwater contamination at the Site,



 8            therefore,  they would -- there's not going



 9            to be any contaminant contribution from



10            the lagoons to the groundwater.



11                  So as  far as this remedy, groundwater



12            monitoring  would be required to measure



13            improvement in groundwater quality,



14            institutional controls to prevent the



15            installation of groundwater wells, and the



16            use of  the  contaminated groundwater



17            throughout  the entire plume would be



18            required, sediment sampling in Gold Creek



19            to ensure that contaminants have not



20            reached Gold Creek would be implemented.



21            Also,  since the contaminants would remain



22            on the  Site, EPA would review the remedy



23            within five years to ensure that the
 t


24            remedy continues to be protected.  If the



25            monitoring  data shows that there is not

-------
                                                   36
 1                        Proceedings
 2            improvement  in groundwater quality within
 3            the five  year  period,  EPA will determine
 4            the need  to  implement  or evaluate cleanup
 5            alternatives for  groundwater remediation
 6            at  the  Site.
 7                 The  rationale  for proposing
 8            Alternative  2  as  the preferred alternative
 9            are it  reduces risk to human health and
10            environment, it minimizes impact of
11            remedial  activities on community,  uses
12            permanent solutions, and it is
13            cost-effective.
14                 This concludes my presentation.   What
15            I have  just  discussed  is just  an overview
16            of  the  results of the  remedial
17            investigation,  the  feasibility study,  EPA
18            preferred alternative, and the rationale
19            for selecting  the preferred alternative.
20                 The  proposed plan,  which  we provided
21 •           here, provides a more  detailed description
22            of  the  preferred alternative.
23                 The  Deerpark Town Hall has copies of
24            the Feasibility Study  and the  Remedial
25            Investigation  Reports  for your review  if

-------
                                                   37



 1                        Proceedings



 2            you would like to see --to find out more



 3            information about the findings of all the



 4            studies and investigation that have been



 5            conducted at the Site.



 6                 The comment period extends through



 7            September 27th, all written comments



 8            should be provided to EPA to the address



 9            that's presented in the proposed plan.



10                 We are open for questions, and any



11            comments.



12                 MS. LONEY:  I'm going to request that



13            you step forward so you can speak in the



14            microphone clearly and that the



15            stenographer can get it clear and can hear



16            your question clearly.  I'm also going to



17            ask that you state your name prior to



18            asking your question,  so the stenographer



19            can also keep a record of who asked what.



20            Yes?



21                 MS. HODSON:   I'm Frances Hodson.



22                 When I first read this report,



23            there's language in it that I thought was



24            difficult if this is for the general



25            public.  Say the word attenuation,  would

-------
                                                    38



 1                        Proceedings



 2            you please describe what attenuation



 3            means.



 4                 MS. ROSS:  Natural attenuation --



 5            there's a glossary on the back of the



 6            handout that you have.  I'm just going to



 7            read it first and then I'll describe it.



 8            Natural attenuation is a process where



 9            groundwater is cleaned up by relying on



10            natural processes.  Examples of these



11            natural processes are; intrinsic



12            biodegradation,  dilution (dispersion), and



13            adsorption.  There are several other



14            processes,  but they're real minor in this



15            case.



16                 So intrinsic biodegradation is one



17            that was discussed in this instance,  and



18            I'll read again  my glossary.  It's soil



19            and groundwater  contain many naturally



20            occurring microorganisms,  such as



21            bacteria,  which  can use the contaminants



22            as a food source,  naturally decreasing the



23            contamination and forming simpler



24            compounds,  eventually leading to carbon



25            dioxide and water.

-------
                                                   39



 1                         Proceedings



 2                 MS. HODSON:   Thank you.



 3                 MS. LONEY:   Does  it  answer your



 4            question?



 5                 MS. HODSON:   Yes, it does.  I looked



 6            it up in the dictionary, but you don't get



 7            as good a description, and I'm a very



 8            ordinary citizen,  I'm  not a scientist, so



 9            I needed that.



10                 Now, institutional controls.  What



11            institution  is going to be doing the



12            controlling?



13                 MR. GARBARINI:  When you get into



14            institutional controls, it's a very



15            difficult thing to try and explain, but



16            there are a number of different mechanisms



17            that you can use.  And as far as who would



18            be implementing those institutional



19            controls, typically what we try and do is



20            get the responsible parties,  as I



21            mentioned earlier, potentially responsible



22            parties, responsible for the contamination



23            at the Site to implement those



24            institutional controls.  And typically



25            what we try and do is lay that out with a

-------
                                                   40
 1                        Proceedings
 2            consent order with them and ask them to
 3            follow-up, often it requires -- if you go
 4            off the property and the responsible
 5            parties no longer own the property, it
 6            requires some coordination with town
 7            officials and with the property owners.
 8                 So, for instance, in this case we're
 9            not saying exactly how we would implement
10            the institutional controls,  but we would
11            probably restrict use of groundwater at
12            the Site perhaps with some sort of deed
13            restrictions,  and EPA also has mechanisms
14            whereby we can -- it's very,  very legal,
15            you get into real estate law and other
16            things whereby we can actually try and
17            enforce some of these institutional
18            controls.  What we do, we can give you a
19            more detailed answer in your
20            Responsiveness Summary.  We  have an
21            attorney actually write up a more detailed
22            response to your question.
23                 MS. HUDSON:  All right.   Thank you.
24                 MR. GARBARINI:   You're  welcome.
25                 MS. LONEY:  I'm going to ask that

-------
                                                    41



 1                        Proceedings



 2            anyone and everyone who has any questions,



 3            you can just lineup here, that way you can



 4            kind of expedite it rather quickly.



 5                 MR. MAYFIELD:  Hi.  My name is



 6            Richard Mayfield from Congressman Oilman's



 7            office.



 8                 I'd like to thank the EPA for this



 9            opportunity for this public comment period



10            and recognizing the relative infancy of



11            environmental science and every site being



12            unique of course.



13                 Can you point to some sites for us or



14            some past history that this proposal that



15            you're doing will be successful, so five



16            years down the road we don't have to come



17            back and revisit this and say,  gee,



18            fellows,  we spent "X" amount of dollars



19            and we're no better off than we were five



20            years ago?  Thank you.



21                 MR.  GARBARINI:  Thank you.  I guess a



22            major portion of this remedy really relies



23            on the remedy that we selected for the



24            lagoons last year and the effectiveness of



25            that remedy,  but there are a number of

-------
                                                   42



 1                        Proceedings



 2            other sites out there where we have



 3            actually gone out and cleaned up sources



 4            and sources of contamination.  So as soon



 5            as you remove that source of contamination



 6            to the groundwater, you will see some



 7            improvements in the groundwater.



 8                 And the other alternative really is



 9            to try and aggressively cleanup the



10            groundwater, go out there with a pump and



11            treat system, which is not necessarily a



12            very efficient system.



13                 At this Site here we are seeing that



14            the level of contamination dropped



15            dramatically from just below the lagoons



16            further downgradient of the Site just



17            before Gold Creek.  So we are very



18            confident that once we get the source out



19            of there, we'll start to see some



20            significant improvements in groundwater



21            quality.  We had our -- our experts out



22            in Oklahoma, folks that actually are very



23            good with groundwater modeling and looking



24            at biodegradation and things like that,



25            they reviewed all the modeling here and

-------
                                                   43
 1                        Proceedings
 2            data that we had for the Site and they
 3            also felt confident that some
 4            biodegradation was going on and that the
 5            modeling results, as predicted -- there's
 6            always -- when you're dealing with
 7            modeling, you never know exactly how
 8            things are going to turn out, but they
 9            were pretty confident with the effort that
10            was conducted here.
11                 MR.  DECKER:  Wayne Decker.
12                 You mentioned that the contaminants
13            are significantly decreasing in the
14            monitoring wells as the wells are further
15            from the  lagoon sites.   On those wells
L6            that are  furthest from the lagoon sites,
L7            are the levels approaching safe levels?
L8            Are they  still considered hazardous levels
19            that are  found there now?  Do you have any
JO            numbers on that?  And besides just giving
51            me numbers,  I  don't know what the numbers
12            mean unless  I  know what the ranges are,
!3            unless you can sort of  indicate.
:4                 MS.  ROSS:   Just in general,  right
:5            near the  lagoons our chief contaminant is

-------
                                                    44



 1                         Proceedings



 2   .          benzene,  and benzene is  in  the  thousands



 3             of  ppb right adjacent to the  lagoon,  and



 4             at  our furthest downgradient  wells,  which



 5             are just  north of Gold Creek, the  benzene



 6             is  either non-detect or  about



 7             approximately 10 ppb.  So we're seeing two



 8             orders of magnitude decrease  in that  1,500



 9             feet.   So they're either at or below  mcl's



10             or  just above mcl's in that ar'ea.



11                 MS.  LONEY:  What's  ppb?



12                 MS.  ROSS:  Oh, ppb  is parts per



13             billion.



14                 MR.  DECKER:  What's allowable in



15             drinking  water?



16                 MS.  ROSS:  0.7 is the State



17             standard.  Federal standard is 5.



18                 MR.  DECKER:  Five what was that?



19                 MS.  ROSS:  Five ppb's below standard.



20                 MR.  GARBARINI:  Just to add to that,



21             so  if  people were actually drinking that



22            water, I  mean no one is currently drinking



23             the water and we don't anticipate that



24            people will be drinking it in the near



25             future, but as an added measure of safety

-------
   1




   2




   3




   4




   5




   6




   7




   8




   9




  10




  11




  12




  13




  14




  15




  16




  17




  18




  19




\.  20



v  21




  22




  23




  24




!  25
                                      45



            Proceedings



you would have the institutional  controls



also just to make sure it didn't  happen.



     MR. DECKER:  While I'm trying  to



figure out numbers, we've got this



mythical industrial worker who's  drinking



water five days a week, and I believe you



said the risk is 1 in 10,000 and  that is



within the acceptable range.  Again,  what



is the acceptable range if it's 1 in



10,001 I'm not too happy about that,  if.



it's 1 and not much more than 10,000, is



it significant?



     MR. GARBARINI:  Yeah, the acceptable



risk range -- there was a little bit  of



discussion of what is acceptable  in the



proposed plan, but for carcinogens  it is



1 in 10,000 to 1 in 10,000,000.  That's



our acceptable risk range.  So what we saw



here was 1 in 10,000, so we were right at



the acceptable risk range.  Again, the



assumptions are that someone would be



exposed to the water for twenty-five



years,  five days a week,  drinking a liter



a day,  which are some pretty conservative

-------
                                                   46



 1                        Proceedings



 2            assumptions.



 3                 MR. DECKER:  I guess my comment would



 4            be that it seems like this approach is



 5            conservative along with the rest of your



 6            thinking there.  And what concerns me is



 7            that since it is related to the success of



 8            the lagoons being cleaned up in a timely



 9            manner, that if in fact we see any delays



10            in that process, this five year window,



11            which begins upon the completion of the



12            lagoons, is going be to stretching out



13            further and further, and a couple of the



14            other alternatives that were mentioned



15            seemed to have much shorter periods of



16            time for effectiveness, unless I wasn't



17     .       understanding those numbers right.



18                 MR. GARBARINI:  That's a little



19            confusing actually.  If I could respond.



20                 MR. DECKER:  Sure.



21                 MR. GARBARINI:  I think you might be



22            talking about the time to implement, Maria



23            had mentioned some time frames before;



24            nine months,  twelve months.



25                 MR. DECKER:  Right.  Right.

-------
                                                   47
 1                        Proceedings
 2               .  MR. GARBARINI:  That doesn't include
 3            such things as negotiating with
 4            potentially responsible parties to do the
 5            work,  the design phase of the process,
 6            actually going out and bidding or trying
 7            to get a contractor on board to do the
 8            construction work.  That really looks at,
 9            okay,  we've got a contractor on board,  now
10            you need to go back out and construct the
11            unit.   So in one instance, say the
12            groundwater pump and treat would take us
13            12 months to go out there and lay all the
14            pipe  work,  construct the unit, start
15            operating it,  shake is down, make sure
16            it's  operating effectively,  and then after
17            that,  the model projects that it can still
18            be about five  years before -- after the
19            cleanup, until you achieve the same
20            levels,  but obviously if you're taking an
21            aggressive approach,  you'll probably going
22            to clean it up a little bit quicker, but
23            the modeling is showing that it wouldn't
24            be that  much quicker.
25                 MR. DECKER:  Thank you.  These people

-------
                                                   48



 1                        Proceedings



 2            have  all gotten mad at me before, so...



 3                  Just my last one is that you



 4            mentioned that there were no site-related



 5            contaminants found in any of the test



 6            wells and any of the neighboring water



 7            wells and the stream.  And I'm just



 8            wondering if there were any



 9            non-site-related contaminants that we



10            ought to be aware of.



11                 MR. GARBARINI:  Actually,  I think I'm



12            going to pass that question along to Tim



13            Vickerson of the Department of Health.



14            DOH actually conducted the sampling of



15            those wells.



16                 MR. VICKERSON:  Yeah,  my name is Tim



17            Vickerson, New York State Health



18            Department.



19                 My agency has been involved in



20            sampling a few of those residential wells



21            in that area as of a couple years ago.



22            Bottom line is I don't recall seeing any



23            non-site related contaminants,  as well as



24            any site-related contaminants in those



25            wells.  I don't have the results with me

-------
                                                   49



 1                         Proceedings



 2             tonight,  but as  far  as  I  recall,  I don't



 3             remember  seeing  anything  else in there.



 4                  MR.  DECKER:   Thank you.



 5                  MR.  PINES:   Larry  Pines.



 6                  I  was  wondering why  no mention was



 7             made  of EPA's own invention by John Wilson



 8             of  biodegradation, what you call



 9             co-metabolism, the use  of oxygen  in a foam



.0             medium  made of surfactant and purified



.1             water pumped into the ground to increase



.2             the activity of  the  bio-organisms.



.3                  And  I'm also wondering,  on another



.4             issue,  that the  lagoon, as you talk about



.S             in  your information  here,  that you got



.6             20,000  cubic yards got  to be  contained, I



.7             guess that  means  it's gonna be --



:8                  MR.  GARBARINI:  Treated.



L9                  MR.  PINES:   Treated?



>0                  MR.  GARBARINI:  Treated  and



21             contained.



12                  MR.  PINES:   Treated  as in how;



23             water?



24                  MR.  GARBARINI:  I  guess  I'll  take



25             your  second question and  respond to that,

-------
                                                   50



 1                        Proceedings



 2            since it's fresh in ray mind and before I



 3            forget.



 4                 The Operable Unit 1 remedy that was



 5            selected last March called for basically



 6            the handling of 20,000 cubic yards of



 7            material,  some of those are contaminated



 8            with inorganic compounds, they would have



 9            to be stabilized prior to being placed in



10            a Part 360 or cell, the cell that was



11            Maria was  talking about, others have or



12            organic contamination.  We think we're



13            going to be treating those via a



14            bioslurry, using bugs basically.  And



15            other materials will be below our



16            treatment  levels that were specified so



17            they would not have to be treated via



18            either mechanism, but they're high enough



19            that they  would have to go into the cell.



20                 MR. PINES:  What about the heavy



21            metals you talked about?



22                 MR. GARBARINI:  The heavy metals



23            would be stabilized if they exceed



24            the --



25                 MR. PINES:  HOW?

-------
                                                    51



 1                        Proceedings



 2                 MR. GARBARINI:  The actual types  of



 3            materials that would be used for the



 4            stabilization process?  Those have not



 5            been selected yet, but there are a number



 6            of different types that are out there.



 7                 MR. PINES:  Yeah, I know.



 8                 MR. GARBARINI:  If you're interested,



 9            when we start approaching the phase where



10            we're going to be -- a lot of those are



11            proprietary too,  so it gets touchy, but we



12            can keep you up-to-date on where we think



13            we're headed on that.



14                 MR. PINES:  It's  just that I know of



15            a. person at Ohio  State or Penn State who



16            developed a system by  taking phosphates to



17            so call stabilize lead in the soil to make



L8            it say non-hazardous if consumed,  that the



L9            body -- won't be  absorbed into the blood



20            stream, and also  work  done by somebody, I



>1            don't know if it's EPA or whose it is, but



12            there's some work down at Liberty State



'.3            Park in New Jersey where they use



14            sunflowers and actual  mustard plant to



:5            absorb chromium and lead out of the soil

-------
                                                    52



 1                        Proceedings



 2            and it stays inside the  root  system,  which



 3            can be disposed whichever way you want,



 4            but it leaves the soil clean  apparently.



 5                 MR. GARBARINI:  Yes, I've heard  of



 6            the latter.  I know it's been used in some



 7          '  of the Eastern block countries too, it's



 8            been quite effective.  I think typically,



 9            like you said, to use a  foam  medium to try



10            and absorb the contaminants,  but we'll



11            take note of your comments here and Maria



12            will be handling the design,  so I'm sure



13            she'll keep it in mind.



14                 MR. PINES:  Okay.  Thanks.



15                 MS. ROSS:  About the co-metabolism,



16            you had said --



17                 MR. PINES:  Yes.



18                 MS. ROSS:  -- why we're  using the



19            intrinsic bioremediation, just using the



20            natural biological population, and not



21            adding to it,  not adding surgots or any



22            additional things, but that is another



23            technique that's used.  But John Wilson of



24            the U.S. EPA Lab Ada endorses intrinsic



25            bioremediation.

-------
                                                    53



 1                         Proceedings



 2                 And  I'm just going to add this,  do



 3            you feel  that you need that to achieve



 4            your goal?   Right now we believe the  Site



 5            conditions are such that we can do this



 6            without adding anything at this time.



 7                 MR.  PINES:  Are these the same people



 8            at Ada that  told me when I was in Oklahoma



 9            City that the high levels of chemicals in



10            the water system at Norman were not a



11            danger?



12                 MS. ROSS:  Probably not.



13                 MR. PINES:  I ended up in the



14            hospital and I lost my job with the postal



15            service because of it.  I'm just wondering



16            if those were the same people that say



17            it's relatively safe.



18                 MS. ROSS:  Probably not.



19                 MR. PINES:  I hope not.



20                 MR. STEIN:   Thank you for your



21            presentation so far.   My name is Eric



22            Stein.   I represent the Deerpark Planning



23            Board.



24                 And I'd like to get a little bit



25            clearer line on your time line,  basically

-------
                                                    54



 1                        Proceedings



 2            for the public.  You've got the OU1



 3            system, which is the containment and  the



 4            treatment of the tanks for the lagoons,



 5            and you've got the OU2 , which is the



 6            groundwater section.  Now, you keep



 7            referring to five years of OU2 before it's



 8            drinkable and that's, I'm assuming, after



 9            the lagoons have been completely treated



10            and contained; right?



11                 And I'd like to know approximately



12            how long or what kind of an estimate you



13            expect that it would take from,  you know,



14            working it out with the PRP's, finding out



15            the resolutions, determining the chemicals



16            you expect to use for treating the heavy



17            metals, containing the lagoons and then



18            adding five years?  Can you give me a time



19            line,  effective time line?  Saying that we



20            started working it out with the  PRP's



21            today.



22                 MR. GARBARINI:   Okay.  Actually,



23            we're a little bit ahead of that because



24            we signed the Record of Decision for the



25            source control last  March.

-------
                                                    55
 1                        Proceedings
 2                 MR. STEIN:  Right.
 3                 MR. GARBARINI:  And we' had
 4            negotiations with the responsible parties,
 5            with a couple of the responsible parties,
 6            last year.  We were not able to come  to
 7            terms on consent and we did issue them an
 8            Order at the end of September of last year
                                            •
 9            and they complied with the Order and  they
10            have submitted a work plan to us for  the
11            remedial design, which Maria has already
12            taken a look at and commented on, as  has
13            the State of New York and other entities
14            within EPA.  So --
15                 MR. STEIN:  So we have a year or so
16            into it already?
17                 MR. GARBARINI:  Yeah.  We're already
18            into the process.
19                 MR. STEIN:  But we haven't started
20            any treatment or building?
21                 MR. GARBARINI:  That's correct.  So
22            basically what we  have is we have a work
23            plan that will allow us to now start to
24            proceed.with the design and the remedy,
>5            and there probably will be some testing

-------
                                                    56



 1                        Proceedings



 2            that goes on before we actually figure out



 3            exactly what types of materials we're



 4            going to be using, what kind of slurry is



 5            going to work.  But the long and short of



 6            it is,  is that we should have that design



 7            complete by the end of 1997, beginning



 8            part of '98.



 9                 MR. STEIN:  Okay.



10                 MR. GARBARINI:  And then I'd say it



11            would probably take a year.



12                 MR. STEIN:  Okay.  So at the end of



13            '98 you said?



14                 MR. GARBARINI:  Beginning of 19 --



15            yes, end of '98 say for the --



1.6                 MR. STEIN:  The end of '98 you'd be



17            ready to implement the actual treatment



18            and construction activities?



19                 MR. GARBARINI:  The beginning of '98



20            we probably will be ready to implement,



21            and it  would take a year from there I



22            would say.



23                 MR. STEIN:  A year after that OU1



24            would be complete?



25                 MR. GARBARINI:  Yes.  In the

-------
                                                   57



 1                         Proceedings



 2            meantime, what we'd probably -- we'd



 3            probably be  excavating and staging



 4            material as  they're being treated and



 5            whatnot.  So taking them -- hopefully



 6            we'll be taking them out as we're building



 7            the cells.   Some of the materials are



 8            going to have to go because we have to



 9            build a new  cell for them, so they're



10            going to have to be staged in certain



11            areas and things like that.  So hopefully



12            the impacts  to the groundwater will be



13            elevated to  a certain extent before we



14            actually finish all the treatment and



15            place the materials in the cell and



16            capping the  cell.



17                 MR. STEIN:  So we've got '98, '99 for



18            the finish of the lagoon section?



19                 MR. GARBARINI:  I would say



20            hopefully -- hopefully we get the work



21            done in the  construction season of 1998



22            and be done by the end of 1998.  That



23            would be my hope.



24                 MR. STEIN:  Optimum scenario.



25                 MR. GARBARINI:  Yes, if we don't have

-------
                                                   58
 1                        Proceedings
 2            any problems, that's right.
 3                 MR. STEIN:  And then another
 4            additional five years after that.  So
 5            we're talking 2004,  2005 for --
 6                 MR. GARBARINI:   2004,  2005, yes.  But
 7            you have to remember that the modeling
 8            shows that you really need to get in there
 9            and remove the source before any of the
10            remedies that we looked at are going to do
11            much good.
12                 MR. STEIN:  Yes,  of course.  It's
13            very understandable  why OU1 and OU2 are
L4            connected and correlated.
L5                 I had another question about the
16            actual retainment, the actual treatment
17            and the containment  for the materials from
L8            the lagoons.   Could  you briefly explain
.9            what that's going to be.
10                 MR. GARBARINI:   Okay.   It's going to
11            be  consistent  with New York State Part
:2            360, the 360  Landfill  Requirements,  which
:3            include clay  and probably  some synthetic
 4            liner,  leachate collection.   And I don't
 5            know,  Maria,  do you  have  anymore details

-------
                                                    59



 1                         Proceedings



 2            that you  can add  to  that?



 3                 It would be  consistent with the



 4            current landfill  requirements  for the



 5            State of  New York Part 360.



 6                 MS.  JON:  Right, it's going to be a



 7           . composite layer of clay, soil, compacted



 8            soil at the  bottom and then a  high density



 9            polyethylene  liner will be placed beneath,



10            before the true material gets  placed on



11            the cell,  and  it's going to have a



12            leachate  collective  system and will



13            collect any  liquid that might  possibly be



14            generated overtime and then a  cap is going



15            to be placed,  also made of composite layer



16            of clay and  soil  and gravel.   This is



17            going to  be  about three feet -- thickness



18            of three  feet  the cover's going to be, so



19            that would be  consistent with  the State



20            Regulations.



21                 MR.  STEIN:  And these are the



22            guidelines of  the landfill State Law 360?



23                 MS.  JON:  That's correct,  for solid



24            waste landfills.



25                 MR.  GARBARINI:  Yes.   And the Law

-------
                                                   60



 1                        Proceedings



 2            also allows for some variation in terms of



 3            the materials that  you use,  but it would



 4            be consistent.   You know,  typically the



 5            materials that  Maria was describing are



 6            the types of material that are typically



 7            used.



 8                 MR.  STEIN:   Landfills are a favorite



 9            subject around  here.



10                 MR.  GARBARINI:   I can imagine.



11                .MR.  STEIN:   Thank you  very much.



12                 MR.  GARBARINI:   You're  welcome.



13            Thank you.



14                 MR.  BERKMAN:   I'm Jeffrey Berkman.



15            I'm here  representing Assemblyman Jake



16            Gunther,  and thank  you for the



17            presentation.



18                 I have a question of  process.  If



19            there's a disagreement by  the possible



20            responsible parties,  does  EPA go ahead  and



21            do the work and then discuss how it's



22            going to  be paid for later or do you wait



23            to have that all lined up  first before  you



24            do the work?



25                 MR.  GARBARINI:   Typically what we  do,

-------
                                                   61
 1                        Proceedings
 2            the process that we use in most cases, at
 3            least when we get to the design phase, is
 4            we'll issue letters to the responsible
 5            parties requesting that they perform the
 6            cleanup or pay for the cleanup.  We then
 7            ask them to give us a good faith offer, if
 8            they're willing to do that, if they want
 9            to do that, they'll give us a good faith
10            offer and we'll sit down and negotiate
11            terms of the agreement with us and then
12            they would implement the remedy.
13                 If they decide that they don't want
14            to negotiate with us or if they negotiate
15            with us and then say, listen, we don't
16            have a deal here, what we can do is issue
17            an Order to them, order them to timely do
18            the work.   They can chose to comply with
19            the Order or not comply with the Order.
20            If they don't comply with the Order,  we
21            would actually fund the additional work
22            and then go after them later on for the
23            cost of the cleanup.
24                 In the case of the first,  the
25            operable unit with the lagoon remedy,  the

-------
                                                    62



 1                        Proceedings



 2            PRP's are implementing that remedy.



 3                 MR. BERKMAN:  They agreed?



 4                 MR. GARBARINI:  They sat down and



 5            negotiated with us and we were unable to



 6            reach an agreement on consent, but we did



 7            issue them an Order and they choose to



 8            comply with it, and they have been



 9            conducting the work in good faith.  They



10            also did the remedial investigation under



11      .      Administrative Order on Consent.  So they



12            consented to do all this study work.



13                 MR. BERKMAN:  I'm not sure how many



14            documents you dropped off at Town Hall,



15            Deerpark Town Hall.  Is it like one of



16            those large books there?



17                 A VOICE:  It's one of these.



18                 MR. BERKMAN:  It is just one of these



19            documents that I have?



20                 MR. GARBARINI:  This should also be



21            in the repository, but that provides a



22            summary of everything that's been done.



23                 MR. BECKMAN:  I was going to suggest



24            at least this, I don't know about those,



25            but some of these copies you might

-------
                                                   63



 l                        Proceedings



 I            consider dropping them off in the Port



 }            Jervis Free Library, which also is part of



 i            Deerpark, part of their library district,



 5            and it might be convenient for people that



 6            live in Deerpark, if they work in Port



 7            Jervis, they might have the opportunity to



 8            review the documents in Port Jervis and



 9            also might be interested for people in



 0            Port Jervis and Middletown and other



 1            people who might be interested as well, so



 2            if you have two sites for information,  it



 3            might be helpful.



 .4                 MR. GARBARINI:  Okay.  Yes, we'll do



 .5            that.



 .6                 MR. BECKMAN:  Thank you.  And lastly,



 .7            I was hoping the State Official, after you



 .8            review the documents, I was hoping you



 19            could write a letter to Senator Gunther



 >0             stating that it's your belief that none of



 El             the wells in the vicinity have any



 22             contaminants.  I think that's what you



 23             said.  I don't want to put words in your



 24             mouth.  But could you please write a



25             letter on that,  so that when we get

-------
                                                    64



  :                        Proceedings



  >            constituents asking about  that,  we can



  }            always refer to your letter.



  I                 MR. VICKERSON:  I will.



  5                 MS. LONEY:  I just want  to  make  sure



  5            I understand, you're requesting  that  there



  7            be an additional repository?  We have two



  8            existing repositories; one at Deerpark



  9            Town Hall and the other at the Port Jervis



  0            Public Library.



  1                 MR. BECKMAN:  You do have the Public



 2            Library?



 .3                 MS. LONEY:  Yes, there are  two.



 4                 MR. BECKMAN:  I didn't hear him  state



 .5            that in the beginning.'



 .€                 MS. LONEY:  There's a copy  of it



 .7            there, if you need copies of this



 18            document.  This was handed out and mailed



 19            out.  It should, in fact, I believe,  in



 20            that document it may in fact list  the



 21            repositories where they're located.



 22                 MR. BECKMAN:  If you have it  at  the



 23            Port Jervis Library, that's great.



24                 MS. LONEY:  Yes.



25                 MR. BECKMAN:  Thank you.

-------
                                                   65



 1                        Proceedings



 2                 MS.  LATINI:  I'm Louise Latini.  I



 3            live at Vans Beach in the Town of



 4            Deerpark,  Port Jervis, New York.



 5                 I was here two years ago for this



 6            meeting.   What is the condition of the



 7            situation up there now since two years



 8            ago?  Has there been testing at those



 9            points to see if anything has decreased



10            naturally?



11                 MS.  LONEY:  When you say points,



12            what do you mean?



13                 MS.  LATINI:  Up there at the --at



14            the dump.



15                 MS.  LONEY:  Okay.  You mean the



16            specific  wells that they were testing?



17                 MS.  LATINI:  Yes, were they tested



18            since two years ago, and I want to know



19            what the  results are.



20                 MR.  GARBARINI:  Okay.  I'll respond



21            to that,  and Linda can correct me or Maria



22            can correct me if I'm not accurate with



23            what I'm  saying.



24                 As I  mentioned before,  we really



25            aren't going to see .any real significant

-------
                                                  66

                         Proceedings

             results until we remove the source, but in

t             terms of what we have seen, the

I             groundwater testing that was done up there

             was sort of done in phases; we went out

             with one stream of wells,  then we went out

j            ..further with another stream of wells,  and

}             then further with another stream of wells,

)             and so the first couple of runs of

)             sampling didn't include the furthest

L             wells, so we can't really compare or say

2             the first round of sampling -- we can't

3             compare four rounds of sampling to wells

|             that are further off.   But the wells from

J5             the lagoon,  the results were pretty

6             similar from round to  round.  When we
i
             start to move away from the lagoons we see

             a very big decrease in the level of

             contamination and we don't think that  the

             contaminants are really migrating all  that

             far before they're naturally attenuating,

I             being eaten by the bugs that are out

I             there,  so to speak.  So we haven't really

             been able to document  a real decrease  say

             in one given well of contamination,  but we

-------
                                                  67
                         Proceedings
             expect  to  see  that  once  we  remove the
             source.
                  MS. LATINI:  Okay.   I  have  another
             question.   Two years  ago when  I  was  here  I
             requested  to have my  well checked by the
             State.  They did come down  on
             September  12th, 1994.  1 received the
             report  November 22, 1994.   There was a man
             here  asking if the  wells are
             contaminated.  I do have some  in mine.
             They  say it's  under the  New York State
i             Regulations, but it is in my water.   Says
I             it's  okay  to drink, but  it's there.   You
             can't say  that they're free.   This
             gentleman  here signed this  letter that I
l             got.  Everything is written here,  the
5             amounts and what they are,  in  three  pages
)             that  I  have.   I do  not understand it.   All
)             I know  is  what they're telling me, is that
L             it's  below the standards.   What  I'm  asking
I             for tonight, I already spoke to  him.   I
3             want  another test done.   I  cannot afford
i             to go to Orange County Department of
5             Health.  I have my  water checked for

-------
 v


If
 j                         Proceedings


              several  things  once a year, but  not  all


              these chemicals because  I couldn't afford


 4            it.  So  I  feel  that I want to  ask tonight


 5            again to have this test  done,  and I  will


              match them up what I had two years ago to


              see if there's  any changes, then I will


 8            know myself  if  the natural way is the best


 J            way to go.   As  far as I  was told years


 0            ago, the sand does not take out  these
 I/

 >:1            chemicals, you  have to use something to


 j2            get rid of 'em, they're  just not going to


 |3            go naturally.   That's why I asked you what


 i!4            the difference  was in two year's time,

 I
              what was found  two years ago and now two


 6            years later  or  one year, however you test


 i\7            them, there  should be a  change.  And I'm


 18            very much  interested in  getting  this done
 r
 9            again on my  water so that I can  see  for

 i
 ,0            myself how the  tests are coming.  If it's


 1            decreasing,  fine.   If it's increasing then


 12            it's not too good.


                   MR. VICKERSON:  Yeah, I'd just  like


 !4            to say that  most of those samples,  nearly
i1
 is            all of them  were metals, we tested for

-------
                                      69



            Proceedings



metals, and there were -- can't call  them



contaminants, but they're naturally



occurring elements, that if you go test



the gravel you're going to find naturally



occurring metals.  You know, in some  areas



of New York State you find them at higher



levels than others, but they're not really



contaminants, they're naturally occurring



in the ground.



     I'd like to elaborate a little bit on



what Doug said about the outer stream of



monitoring wells that you have coming out



of the Site.  Those wells will be acting



as a sort of a sentinel or guard,  if you



will, for contaminants that have the



potential to migrate in the direction of



residential wells which are even further,



so if we start to see any trends or if we



even start to see any detection at all on



those wells, that would be an indication



to me to get out there and get some more



private well samples.



     And I encourage anybody else, if you



live out in that area,  Maria had a map up

-------
                                                  70



L                        Proceedings



2            that showed all those tiny little



3            triangles, there's quite a few of them out



I            there,  if you're really concerned about it



5            and you're really lost, get us out there



5            and get a sample, so let me know.  I guess



7            this is a good opportunity, I'll give you



B            my 800  number:  1-800-458-1158,



9            Extension 305.  And I'll give that again,



D            it's 1-800-458-1158,  Extension 305.   Thank



1            you.



2                 MR.  GARBARINI:  Yes,  I'd just like to



3            reiterate what Tim had said,  I have public



4            water from my town and I have a lot of



5            iron magnesium in mine, it stains the



6            bathtub and it's a pain to scrub off, but



7            those are naturally occurring.  Metals are



8            naturally occurring,  so you would expect



9            to see  some of those  in your water.



0                 MS.  LATINI:  What's in mine is metals



1            plus these contaminants.  You can look at



2            this.



3                 MR.  GARBARINI:  I'm sure Tim will.



4                 MS.  LATINI:  Not natural.



5                 MR.  VICKERSON:  See me after.

-------
                                                   71



 1                        Proceedings



 2                 MR. GARBARINI:  Sounds  like he's



 3            willing to get another sample for you.



 4            Maybe you can see Tim after.



 5                 MS. SADANIANI:  Kathy Sadaniani.



 6                 My question is very similar to



 7            Louise's.  I was just wondering what  was



 8            the date say of the last sampling of  the



 9            sediment sampling of Gold Creek or of the



 0            last -- this last band of contingency



 1            wells?  If anybody knows, what was your



 2            last date.  Are you the one who does  --



 3                 MR. VICKERSON:  I guess I could



 4            answer part of that.  The last sample I



 5            got was March of '95.



 6                 As far as the groundwater wells, I'm



 7            not sure, so I'll leave it to Doug.



 8                 MR. GARBARINI:  I think, if you  do



 9            not mind, we'll take a little bit of  time



 0            and look through our document and get back



 1            to you later on in the meeting about when



 2            things were last sampled.  EPA actually



:3            went out there with our own staff in  July



:4            to sample some of the monitoring wells.



:5                 MS. SADANIANI:  This July?

-------
                                                    72



 1                         Proceedings



 2                 MR.  GARBARINI:   This  July,  this  year,



 .3             to  take  a look  at  some of  the  inorganic



 4             contaminants  there.   Before  that,  in  terms



 5             of  groundwater,  I  think  our  last sampling



 6             that was  done was  spring of  '95.



 7                 MS.  JON:   September '95.



 8                 MR.  GARBARINI:   Was it  September?



. 9             That might be when we had  the  results come



10             in.



11                 MS.  JON:   Yes, you're right.



12                 MR.  GARBARINI:   Sometime  between the



13             spring and September  of  1995.  So  spring



14             or  summer.



15                 The  Creek  sediment  sampling,  we're



16             going to  take a  look  at  the  documents and



17             see if we can get  that information for



18             you.  That probably was  done I think in



19             '94.  I'm not sure, but  we'll  try  and



20             figure it out for  you.



21                 MS.  SADANIANI:   And if  it doesn't get



22             to the Creek, then the people  on the south



23             of that are clear; is that correct?  So



24             the Creek would  be your  way  of saying, and



25             that has not been  done since '94,

-------
                                                   73



                         Proceedings



             supposedly?



J                 MR. GARBARINI:  Well, the Creek,  as



I            well -- we're really more concerned about



             what's showing up in the monitoring wells



             then the Creek.  I think the Creek



             provides us with the indication that  it's



             a good sign that nothing has shown up  in



             the Creek and it's worthwhile to continue



)             to monitor that, but what we're really



L             concerned about is the monitoring wells



             themselves.



J                  MS. SADANIANI:  Okay.  But it's over



I             a year since they were done,  the last



             band,  but that was negligible?



                  MR. GARBARINI:  That's right.



                  MS. SADANIANI:  A year ago.



                  MR. GARBARINI:  That'8 right.



                  MS. SADANIANI:  Over a year ago.



)                  MR. GARBARINI:  Yeah, sometime



L             between spring and summer of  last year,



             aside  from the wells we sampled this



i             summer for inorganic chemicals.



L                  MS.  SADANIANI:   So you have  no idea



             of what the situation is in that  last  band

-------
                                                   74
 1                         Proceedings
 2             of wells right now?
 3                  MR.. GARBARINI:  No,  I think --
 4                  MS. SADANIANI:  You know, I'm
 5             bringing this  up because we live south of
 6             the Creek.   There's three cancer cases in
 7             ten houses.  That to me is a hell of a lot
 8             of cancer in ten houses,  that I'm shocked
 9             to see  the map to see where we live.  I'm
10             shocked.
.1                  MR. GARBARINI:   Have you had your
.2             well  tested  by the Department of Health?
.3                  MS. SADANIANI:   No,  we were not,  none
.4             of us were tested.
.5                  MR.  GARBARINI:   I can understand  your
 6             concern.   It's hard not to be concerned
 7             about it.
 8                  MS.  SADANIANI:   It blew our mind
 9             tonight.
 0                  MR.  GARBARINI:   Right.   But yet you
 1             have  to  understand,  we look at the history
 2             of the disposal  at  the Site,  we look at
 3             the wells, how it's  confined in the wells,
 4             I  mean,  the  sort  of  nasty stuff,  if you
 5             recall,  that was  disposed of a number  of

-------
                                                   75
 1                        Proceedings
 2            years ago, probably in the '70's, so you
 3            would expect if that was migrating
 4            off-site, you would expect probably to see
 5            something in that last string of wells.
 6                 MS. SADANIANI:  Right.
 7                 MR. GARBARINI:  And we haven't seen
 8            anything over the last few years in those
 9            wells, so we really believe that these
10            natural processes are taking care of
11            things.
12                 MS. SADANIANI:  Taking care of
13            things.
14                 MR. GARBARINI:  But we will continue
15            to monitor.   We have semiannual monitoring
16            in the remedy.   But in the meantime, just
17            to put yourself at a little bit more ease,
18            I suggest that  you call Tim and try and
19            get your well sampled.
20                 MS. JON:  Just to give you an idea,
21            the most --  the most furthest monitoring
22            wells are located here.  This is the Site,
23            and Gold Creek  is right here.  So the
24            levels that  we  found in the monitoring
25            wells around here were either at the

-------
            Proceedings
drinking water standards or slightly,
slightly, above the drinking water
standards.
     MR. PEILL:  Arthur Peill.
     I'd just be grateful if somebody on
the panel here could remind us of who the
responsible parties to the Consent Order
are.
     MR. GARBARINI:  Okay.  We have a
series of PRP's at the Site.  Some of them
had signed on to do work or given us
notice of intent to comply and others were
noticed and are not preforming the work.
I'm just going to read from the list right
here.  We have, first of all,  Carroll and
Dubies Sewage Disposal, the owners of the
property, and we have Kolmar Laboratories
and Wickhen Products.  They were both
companies that had waste that were
provided to disposers or transporters that
were eventually dumped at the Site.  We
also had Reynolds Metals.  EPA signed a
settlement,  what's called a De Minimis
Settlement,  with Reynolds last year and it

-------
                                     77


            Proceedings


was finalized this year.  Basically what


that says is they were a small contributor


to the contamination at the Site and


because of that they played, so to speak,


a much more -- a much smaller role, a


minor role than the other PRP's, therefore


we signed a De Minimus Settlement with


them.  So they basically signed off,  paid


us some money and they're out of the


picture unless we find some additional


contamination or evidence in the future


that said they were a larger player in the


contamination of the Site.   And we have


one other party, that is the City of Port


Jervis.  Now,  Kolmar and Wickhens, they
                          »

both signed an Administrative Order on


Consent to conduct the remedial


investigation,  and they were also the


responsible parties that gave us notice of


intent to comply with our order to perform


the remedial action.


     MR. PEILL:  Thank you.


     MR. GARBARINI:  You're welcome.


     MR. CARROLL:  My name  is Carroll,

-------
                                                   78



 1                        Proceedings



 2            Carroll and Dubies.



 3                 In the paper this morning I read



 4            where you're concerned about two



 5            and-a-half acres of land adjoining the



 6            landfill,  the Port Jervis Landfill.  Who



 7            owns those two and-a-half acres?



 8                 MR. GARBARINI:  What was the



 9            reference  again?  I'm not sure of the



 0            reference  you're speaking of.



 1                 MR. CARROLL:  In the paper today it



 2            was stated that you're concerned about two



 3            and-a-half acres of land adjoining the



 4            Port Jervis Landfill,  two and-a-half acres



 5            joining the Port Jervis landfill.  Who



 6            owns those two and-a-half acres?



 7                 MR. GARBARINI:  Is the question



 8            you're trying to get out is who owns the



 9            land under which the lagoons --



 0                 MR. CARROLL:  Who owns -- you're



 1            concerned  with two and-a-half acres.



 2                 MR. GARBARINI:  I'm not sure of the



 3            reference  that you're  talking about that



4            we're concerned with two and-a-half acres,



 5            but we are concerned about the property

-------
                                      79



             Proceedings



that you  own,  the property that  the  City



of  Port Jervis owns.



     MR.  CARROLL:   I want to clarify.



     MR.  GARBARINI:  I'd have to see  the



article before I can respond to your



question.   I'm not  sure what context  that



two and-a-half acres was placed in.



     MR.  CARROLL:   Look, I say that  the



land that you're referring to is



contaminated ground is the City of Port



Jervis Landfill, not Carroll and Dubies.



We paid the City of Port Jervis to dump in



the Port  Jervis Landfill.  And something



that's not used anymore, common sense, we



have 32 acres  and we have stuff to dump,



where would you dump it?  Would you dump



it on your own land or would you dump it



in the Port Jervis Landfill?  You're



talking about  five  to ten percent of



contaminated ground.  I know where the



other 90 is, right  in the center of the



Port Jervis Landfill,  and I  know because I



was there.



     MR. GARBARINI:   Well,  all I can tell

-------
                                                  80
 L                        Proceedings
             you right now is that the center of our
 J            attention, as we described over the last
 I            years, is the lagoons,  that's what we're
             focusing on cleaning up.
                  MR. CARROLL:   Yeah,  I know,  but --
 7                 MR. GARBARINI:   Some of those lagoons
 3            are located on the City of Port Jervis
 3            property, I agree  with  you.
 3                 MR. CARROLL:   Those  that you are
 L            really concerned with are a  part  of Port
 I            Jervis Landfill, in  fact  the whole thing
 3            is.   Our land hasn't been touched.  Our
 i            land is pristine.
                  MR. GARBARINI:   I  guess that's
 5            debateable,  but  I  don't want to debate you
 7            about it right at  this  point in time.
 3                 MR. CARROLL:  You  know  why,  I'll  tell
             you  what you would do,  you know,  clarify
 D            the  ownership.   Who  owns  it?
 L                 MR. GARBARINI:   The  City of  Port
 2            Jervis owns  some of  the property  in which
 3            the  lagoons  are  located and  you own some
4            of  the property  also.
                  MR. CARROLL:  No,  no.   The City of

-------
                                                  81



L                         Proceedings



I             Port Jervis owns it all.



                  MR.  GARBARINI:  I'll go back and



             check with our attorneys.



                  MR.  CARROLL:  All right.   All right.



             Check it  out.



                  MR.  GARBARINI:  But regardless,  as I



I             mentioned earlier in my discussion,  we  had



)             four different types of potentially



i             responsible parties, and one of those are



             operators of a facility where  waste was



             disposed,  another is a transporter of



             waste,  so in either instance you are



             still --



                  MR.  CARROLL:  Absolutely.



                  MR.  GARBARINI:  -- considered to be a



             responsible party.



                  MR.  CARROLL:  You know what,  I'm



             willing to come here and tell  you that



             you're  concerned about ten percent,  we



             dumped  90  percent on the City  of Port



             Jervis  Landfill,  right'in the  middle.



                  MR.  GARBARINI:  We're not  responsible



             for  the City of Port Jervis Landfill.



                  MR.  CARROLL:  If you can  get  the

-------
                                     82



            Proceedings



price up to six or seven million on two



and-a-half acres, what are you going to do



with the City of Port Jervis Landfill.



That will run into the billions.



     MR. GARBARINI:  From what I



understand, that needs to be closed



properly under the New York State



Municipal Landfill Closure, --



     MR. CARROLL:  What you should do - -



     MR. GARBARINI:  -- and that's where



it's being handled.



     MR. CARROLL:  What you should do



first is find out who owns what.  And



Carroll and Dubies does not own the land



that you're concerned about.  You can



check that out.



     MR. GARBARINI:  Thank you.



     MR. JARVIES:  My name is Jack



Jarvies.  I live in Huguenot.  I have a



couple questions.



     First of all,  the last of the



material that was dumped in there was in



'79, it's now 17 years old.  The material



hasn't reached your test wells, your

-------
                                                  83
1                        Proceedings
2            farthest wells.
3                 You also  state  here  if no action is
4            taken there, within  five  more years the
5            groundwater should meet the State drinking
6            standards.  I  don't  understand why you
7            picked option  two if after 17 years that
8            material hasn't reached the wells, and if
9            it's not there now with the material
0            naturally degrading, the  logic is that
1            it's never going to  reach there.  So now
2            we're going to spend taxpayer dollars for
3            $284,000 for what purpose?  Why do you
4            recommend number two?  What's the
5            difference or what is your projection,
€            because even under number two you'll say
7            it takes five years  to meet the
8            groundwater standards.  It doesn't -- your
9            whole presentation here doesn't make
0            sense,  whether it's  no action,
1            Alternative 2 or 3,  and four I don't see a
2            number on.  Thank you.
3                 MR.  GARBARINI:  I have to agree with
4            your description, the very reason why we
5            did go with Alternative Number 2,  the

-------
                                                   84
1                        Proceedings
2            waste has been there for at least 17
3            years.  We aren't seeing it in that last
4            string of wells in any significant
5            quantities, that is a good sign, it's
6            telling us that in fact the material that
7            has gotten into the groundwater is
8            probably naturally degrading,  but we've
9            got a number of other people in the
0            audience that are concerned that the
1            contamination might somehow spread.   So
2            what we need to do, to be responsible
3            public officials,  is to actually sample
4            the wells to make sure this isn't in fact
5            happening and nothing unusual  happens in
6            the next few years.  It's not  necessarily
7            going to be a taxpayer dollars,  we're
8            hoping that the responsible parties  will
9            pickup the tab.  And providing people with
0            the level of comfort is something we need
1            to give them.
2                 MR.  JARVIES:   I don't care what
3            company pays for it,  the insurance company
i            pays for it.   It's  eventually  coming out
5            of our pocket,  increased cost.

-------
                                                  85
1                        Proceedings
2                 The other item is your logic doesn't
3            follow.  If you already have those wells,
4            if you continue to monitor them and
5            nothing happens,  why spend money?  I know
6            you're just paying for your existence.
7            This is one of my problems with DEC.  For
8            example,  if you go to Alternative 2, it
9            might be two years before you even start
0            any action,  by the time you draw up all
1            your plans,  that's two of the five years
2            it's going to take to happen naturally.  I
3            do not understand your reasoning.  Thank
i            you.
                  MR.  GARBARINI:   Part of what you're
             mentioning there,  in fact we do have these
7            monitor wells in  place,  we're going to  be
3            monitoring them anyway,  the $284,000
             includes  those costs in monitoring.
                  MR.  JARVIES:   But not in Option 2.
                  MR.  GARBARINI:   In Option 2 it does
             include those costs,  it also includes some
             other costs  that  probably are not quite as
             significant  as those monitoring costs,  and
             those are costs related to other types  of

-------
                                                  86
1                        Proceedings
2            monitoring that we may not typically do,
3            like looking at the number of bugs, so to
4            speak, or bacteria that are in the
5            groundwater, things like that we wouldn't
5            typically do in a monitoring program.  And
7            the only other thing that might be related
3            to it would be some small costs associated
9            with institutional controls.
3                 Just to reiterate, it is a
L            significant amount of money, but it's not
I            significant when it brings the level of
             comfort that's going to be required here.
                  MS.  HODSON:  And I'm just asking
             these questions because I only have a
             little knowledge of things.
                  I see these three organic compounds,
I            and is this whole thing just about these
I            three organic  compounds,  all this, because
I            there's pages  and pages of chemicals that
             were in this dump and so there's so many
             parts per billion of this,  so many parts
             per billion of that,  but don't they all
             add up to something harmful  to the
             people?  I do  not understand why you're

-------
                                                  87
                         Proceedings
             just talking about these three organic
I             compounds alone.
I                  MR.  GARBARINI:   You're right,  there
             were a whole lot  of  different types of
             chemicals that  were  found in the lagoons.
i             Basically when  we go through our process,
5             we  look at all  those different compounds
             and we pick the ones out that are the most
             significant,  either  in terms of
             concentration or  risk or the two put
             together,  in coming  up --
\                  MS.  HODSON:   You know,  add them all
I             up.
                  MR.  GARBARINI:   Those are all  added
             up  when we do the risk assessment.   What
1             we're trying to say  is that  in the
I             proposed  plan,  this  little plan that we
>             have here,  we're  really just focused on
             three or  four contaminants because  those
             are  the big factors,  in this case they're
             the  most  toxic  and also found in the
;             highest levels.   If  we want  to include
I             everything,  we'd  have to go  back to this
             large document  that  we were  pointing out

-------
                                                   88



1                         Proceedings



2             before.   So  we simmer the information



3             down.   It doesn't mean that  it isn't  all



4             factored into our risk assessment in  all



5             this.



6                 MS.  HODSON:  Thank you.



7                 MS.  SOMARELLI:  My name is Viola



8             Somarelli.   I have just one question.



9                 Does the -- is the EPA an after  the



0             fact agency  with the Superfund and so



1             forth?   I mean, do you monitor these



2             places,  all  these polluters, any time at



3             all or just  after the fact?  Thank you.



4                 MR.  GARBARINI:  Thank you.  That's a



5             good question.



6                 Back around the time when a lot  of



7             these different hazardous waste sites were



8             popping  up,  obviously it became known that



9             there is  a greater need to control what



0             was being disposed of out in the



1             environment, and there is another law,



2             which isn't  the Superfund Law,  but it's



3             closely  associated with it,  which is



4             called the Resource Conservation and



5             Recovery  Act.  And basically what this Act

-------
                                                  89



1                        Proceedings



2            was intended to do was to basically trap



3            waste from the time they were generated to



4            the time they were ultimately disposed,



5            treated, whatnot,  basically the term



6            that's used is from cradle to grave.  So



7            there's a whole lot of manifesting that



8            goes on when someone wants to



9            manufacture.  Operating under this Law if



0            he wants to dispose of some waste, he



1            needs to have a transporter that manifests



2            the waste being taken from his site and



3            then brought ultimately to a licensed or



4            permitted facility that's able to handle



5            these types of wastes.   That manufacturer



6            then signs when the wastes are dropped off



7            and these facilities are inspected and



3            whatnot.



9                 MS. SOMARELLI:   Well,  one note to



0            that is that there's a  hazardous -- well,



I            hazardous material,  benzene,  was in the



2            soil,  and it's adjacent to our home, the



3            plant.   They have  been  now -- we were



1            told,  by the people who owned it at that



5            time,  big business,  of  course,  that in six

-------
                                                  90



                         Proceedings



             months -- they were running this big



             vacuum machine taking the benzene out of



             the soil, running it on their property.



             They said in six months we'll have it all



             cleaned up, that's five years ago and



             they're still running it, so how long is



             this going to take.



                  MR. GARBARINI:  I'm not sure whether



             they actually removed the source of



             contamination there, but if they didn't,



             that could be why it's taking so long.



j                 MS. SOMARELLI:  It's taking so long.



I                 MR. GARBARINI:  Where is this



             located?



5                 MS. SOMARELLI:  Pardon?



7                 MR. GARBARINI:  Where was this?  This



8            is in another town.



9                 MS. SOMARELLI:  No, it's right in



0            Deerpark.



1                 MR. GARBARINI:  Oh, it's in Deerpark.



2                 MS. SOMARELLI:  And right now -- it



3            was the Dow Chemical Company, before that



4            it was the Wickhen Company.  Now it's



5            Summit Research, which I'm sure is a

-------
                                                  91



                         Proceedings



             branch of Dow Corning.



                  MR.  GARBARINI:   Right.   Well,  when it



             comes to  groundwater remediation it's a



             very complex field,  and I  think  the key



             here for  us  is to  get the  materials out of



l             the  ground and treat them.



5                  MS.  SOMARELLI:   I  hope  it doesn't



             take as long as they did with that  small



)             spill or  whatever  it was.



L                  MR.  GARBARINI:   I  hope  not  either.



                  MS.  JON:   I just wanted to  add that



\             the  regulations that Doug  just discussed



I.             about that all generators  have to manifest



             the  waste from where they  originate to



             where they're  disposed  of, that  regulation



?             came up to prevent sites like the



)             Superfund sites to be created again.   So



)             those regulations are there  to prevent



)             sites like this to occur.



L                  MR.  LATINI:  My name  is  Louis  M.



             Latini.   I live in Vans  Beach, Port



J             Jervis, New  York.



L                  You  could almost hit  a  golf  ball



             close to  where I live to the  Port Jervis

-------
                                                   92



L                         Proceedings



2            School District.  You put up a map or an



)            overlay before of the local wetlands,



I            peoples' wells.  Could you put that up and



             then overlay this map over the map of it,



             please.



7                 MS. LONEY:  It won't work.  They're



3            two different --



                  MR. LATINI:  Put the local map up



D            also.  Now,  the Site is on this side right



L            here; correct?



2      _N          MS. JON:  The immediate area, right,



3            that's where the lagoons are.



                  MR. LATINI:  Okay.  So you basically



5            tested all the wells from like Evergreen



5            Lane, Orchard Lane, just north of us, by



7            the Illet School?



B                 MS. LONEY:  This is where they were.



9            Here's Gold  Creek.



D                 MR. LATINI:  All right.



1                 MS. LONEY:  Okay.



2                 MR. LATINI:  Here, Gold Creek goes



3            through there.  That's there.  That's Gold



4            Creek.



5                 MS. LONEY:  They're two different --

-------
                                                   93



                          Proceedings



              you can see  they're  two  different scales,



              it won't work.



                   And this  is  Gold Creek.



                   MR.  LATINI:   And basically,  the last



              time these wells  were tested  is  basically



              1995 or 1994?



 I                  MR.  VICKERSON:   That's correct.



 )                  MR.  LATINI:   1994.



 )                  MR.  VICKERSON:   1994.  Saw  them in



 L             1995.



 >                  MR.  LATINI:   And the last time  these



 3             wells were tested was when?



 I                  MS.  JON:  April  '95.



 5                  MR.  LATINI:   And that was it?



 6                  MS.  JON:  April  '95 for  the  organic



 7             compounds.   For the metals, the  last time



 8             they were tested  was  July, July  '96.



 9                  MR.  LATINI:   July '96.



 0                 MS.  JON:  For metals.



 1                 MR.  LATINI:   Is  there any way I can



 2             get  a photocopy of this?



 3                 MS.  LONEY:   It will be in the



 4             repository.



;5                 MS.  JON:  Let me  see if  I have  it.

-------
                                                   94
1                        Proceedings
2                 MR. LATINI:  I would appreciate  it,
3            if possible.  Thank you.
4                 MS. LONEY: . What we'll do is the
5            handouts that were given out this evening
6            will be -- photocopies will be made
7           • available and they will be placed in both
8            repositories, so you can take a look at
9            not only the handouts that were given, but
0            the presentation as well.
1                 Are there any other questions?
2                 MS. HODSON:  You referred to
3            institutional controls, all these very
4            interesting words.   The perpetrators of
5            the crime,  like Carroll and Dubies,
6            Wickhen, Dow Corning and all the others,
7            maybe not Carroll and Dubies,  but
8            certainly the big firms knew what they
9            were doing and what chemicals  they were
0            letting go and go into the ground.  Now,
1            this whole area, I  have a list of 25
2            companies,  all along 209 for about five
3            miles,  that are all polluting  companies.
4            They're all gasoline,  metals,  all kinds of
5            contaminations.   There's lagoons where

-------
                                                   95
 1                        Proceedings
 2            only septic waste is to be put, but of
 3            course the local gossip is that the
 4            sanitation company has stock pills of
 5            sludge,  so they'll make a little
 6            cocktail.   I called the DEC and I cannot
 7            get them to check one of the trucks going
 8            through.
 9                 Now,  the DEC also gave a permit to
.0            the Sky Dime Corporation.  They're located
.1            right on the Delaware River.  They are
.2            permitted to put I believe it's either
.3            chromium or cadmium -- I believe it's
.4            chromium -- into the sewage system, but
L5            the allowance they received wasn't enough
L6            for them,  so they cheated a little and put
L7            plenty more,  and they were setup for a
L8            $250,000 fine.   Do you think they paid
19            it?  Can I find out?  Because as that
20            gentleman says,  it all ends up in the end
21            with the consumer,  the local resident,
22            footing the bills for these things, and
23            not only that,  that chromium was going
24            into the Port Jervis Sewage Treatment
25            Plant.   The local people here,  we have our

-------
                                                    96
 1                        Proceedings
 2            own systems, they're on-site, our wells
 3            and our septics.  The Port Jervis Sewage
 4            System is owned by the City of New York.
 5            Now, they're permitting people to dump
 6            that stuff into the sewer system, it's not
 7            cleaned as tox -- it's not a third -- a
 8            tertiary sewage treatment plant, it goes
 9            right into the Delaware, their drinking
10            water.   That they don't bother with, but
LI            they just made a lovely agreement that
12            they're going to pull more water out of
L3            this area to satisfy the needs of New York
L4    '        City.
L5                 I  live on the Neversink River.   I can
L.6            walk across that river and not get my
L7            knees wet,  and that was once a famous
L8            trout stream until they put the damn up in
19            1955.  It's ruined as a food source.  It's
10            being ruined as a recreation source.  What
21            are we  being left with?
12                 And institutional controls do not
53            exist,  even the DEC is guilty of giving
54            anyone  a license to put that kind of stuff
!5            into a  sewage treatment plant.

-------
                                                   97



 1                         Proceedings



 2                  MS. LONEY:  I'm not sure what exactly



 3             your question is for the panel, ma'am.



 4                  MS. HODSON:  Well, when you describe



 5             removing toxic chemicals and heavy metals



 6             with biodegradable bacteria, considering



 7             how old the earth is, I wonder how come



 8             there's any lead left.  How come there's



 9             any mercury left.  Wouldn't they have



.0             gobbled it up in all these ages, in the



.1             ions of the earth's existence?  I don't



.2             know.  I can't -- I can't accept that.



.3                  MR. GARBARINI:  Now, just to put it



.4             simply in terms of the bugs, so to speak,



.5             bacteria and all that, what it comes to



.6             what the bugs like to eat,  they're just



.7             like the rest of it, you know, if you're



.8             growing plants or whatever, you have to



.9             have the right conditions in order for the



50             plants to consume the food correctly and



51             for us to consume the food correctly, so



52             it really does depend upon the conditions



53             that the bacteria face.



>4                  You have raised a number of other



55             issues that are concerns you have there

-------
                                                   98
 1                        Proceedings
 2            regarding things  that  were sort of outside
 3            the  scope of this meeting, but if you have
 4            some additional concerns and you'd like
 5            the  EPA to take a look into them, feel
 6            free to put them  in writing and we'll
 7            respond to them in the appropriate
 8            division,  if they're able to.
 9                 MS.  LATINI:   I have one final
LO            question.
LI                 This  plan that you're going to put
L2            into implement here in this Site, has this
L3            been used  any place in the United States?
L4                 MR. GARBARINI:  Yes.
15                 MS. LATINI:   When and how and did it
16            cleanup  what  it was supposed to do and how
17            long did it  take?
18                 MR. GARBARINI:  I'm not sure whether
L9            you're  referring  to the  Operable Unit 1 or
JO            Operable Unit 2.
>1                 MS. LATINI:   The  one  that you have
>2            already  planned to put  into effect.
>3                 MR. GARBARINI:  For the treatment of
»4            the  soils  and lagoon materials?
>5                 MS. LATINI:   The  number two plan.

-------
                                                    99



 1                         Proceedings



 2                  MR.  GARBARINI:  The one that we're



 3            discussing  tonight about the groundwater?



 4                  MS.  LATINI:  Yes.



 5                  MR.  GARBARINI:  Yes, that has been



 6            chosen  at a number of different Superfund



 7            sites as  a  remedy, and we can give you



 8            details as  to the names of those sites and



 9            things  like that when we put our



LO            Responsiveness Summary together.



11                  MS.  LATINI:  It has been implemented



12            and it's  proven that it cleared these



13            chemicals up out of the Site?



14                  MR.  GARBARINI:  Yes.  Again, it



15            depends upon the level of contamination



16            that  you're looking at, but it has been



17            proven  effective in different sites around



18            the Country.



19                  MS.  LATINI:  And they've checked them



20            now after a couple years to see if there's



21            anything  left there?  That's what I want



22            to know.  When they did it,  if they did it



23            ten years ago, and if they're doing checks



24            now and it's still there, then it didn't



25            do its  job.

-------
                                                    100
  1                         Proceedings
  2                 MR.  GARBARINI:  Yes,  there  are a  lot
  3            of  --. when you're  talking  about  these
  4            things, everything is very, very site
  5            specific  when you're talking  about
  6            biodegradation, but if you want,  we can
  7            give you  a list of other sites where it's
  8            been implemented,  both Superfund sites and
  9           ' sites that aren't  Superfund sites that
10            have had  other similar .contaminants.
11                 MS.  LATINI:   Because  if  it  doesn't
12            work, it's just a  waste of money and time.
.13                 MR.  GARBARINI:  That's right.  Let me
14            pass this over to  Linda who has  got a  lot
15            more background in this area.
16                 MS.  ROSS:  One of the previous
17            speakers  talked about John Wilson, and
18            John Wilson's an expert in this  particular
19            field of  bacteria, of degrading  compounds
20            and cleaning up sites.  And when this
21            first started there was a  lot of jet fuel
22            spilled on actual  military bases, and  he
23            focused his study  on that, and it really
24            does cleanup benzene quite remarkably
25            under the right conditions and it's proven

-------
                                                   101



 1                         Proceedings



 2            and is very  well documented.  We will  •



 3            provide more references on that with the



 4            Responsiveness Summary.



 5                 MS. LATINI:  Thank you.



 6                 MS. LONEY:  Are there any further



 7            questions?



 8          .        (No response given.)



 9                 MS. LONEY:  All right then.  I just



10            want to encourage all of you who may have



11            additional questions, you can contact



12            Maria Jon, she's the Remedial Project



13            Manager, and we also are encouraging you



14            to submit written comments to us.



15                 The closing date,  again, for



16            submission of your comments is



17            September 27th.  So you get your written



18            comments in  to us.   They are taken quite



19            seriously and read and taken into



20            consideration.   So I'm going to thank all



21            of you once  again for coming out, and I



22            wish you all a safe trip home.  Thank you



23            so much.



24                                oOo



25

-------
                                                   102




 1




 2




 3




 4
 5




 6




 7




 8




 9




10
12




13



14




15



16



17




18



19



20




21



22




23



24



25
                   THE FOREGOING IS CERTIFIED to be



              a true and correct transcription of the



              original stenographic minutes to the best



              of my ability.

                                                 UJl
                                                    .,
                               Jacqueline Maloney, CSR

-------
                    Appendix E ;




Letters Submitted During the Public Comment Period
                         26

-------
                        /• nance.4. $.  Hudson
                         HCK 608 Ave.  6
                                                September 25, 1996


Maria Jon, Project Manager
U.S. Environmental Protection Agency
200 Broadway,  20th Floor
New York, New York looo?-!866              \
                                  Rei   Carroll & Dubies
Dear Ms. Jom

I moved to Godeffroy from Nassau County in I9b3.  I have lived
in Nassau over 3° years and contaminated water fupplies necessitated
the closing of 33 welJs on Long Island.   Naturally the public be-
came very conscious of the importance  of a clean water supply.  When
I read about the Carroll & Dubies Site I recognized it as a big
problem.

When I read the announcement about the Public Meeting on September
llth, and read the report I took out ray file to review the past
public hearings.  My first shock was EPA's Alternative #l' which
was to do nothing.  How could you, as  professionals, even suggest
leaving a.community with no remedial action to protect us, your
fellow Americans?  Only a few thousand feet downgrade if the Port
Jervis School Complex which has over 1,000 students, as well as
a bus garage, custodial, maintenance,  groundsmen, cafeterias
workers .Plus the professional staff -  probably boo people.  The
school was built in 1968,   In 199^ lead was in the drinking water
and it was blamed on pipes.   Adjacent to the school are junkyards,
retail auto salesrooms with repair shops on the southside.
On the upriver side is a milk farm and the smell of cow manure
drifted over to the bus garage..   This is just a little description
of the school site and environs.

 As for the people of our area.  We are a low income area.  Wages
go from the minimum to about $8.uo at the acid battery plant.
You can check with the Department of Health for cancer and res-
peritory illnesses.  You should check on birth defects too.
You, as a federal agency can also get  the figures on the mentally
deficient and physically handicapped children in the schools
and medical facilities in Orange County.

I was shocked that the Mayor of Port Jervis was absent and that
there was no representative present with a statement.  I was also
shocked that our Supervisor* Mr.  Robert Cunningham, was absent
but a Councilman, Mr. Robert Zeller, was present as an observer
to report back to the Town Board,

Our very beautiful valley has many hidden dangers in addition to
the toxics released into the Neversink, streams and ground.

-------
  We have a heavy  inversion each morning which rises and then
 is  dispersed.  Naturally, the toxins in the air rise up and are
 part of the air we breathe.  Respiratory problems are common.
 A foul environment produces a sick population.

 I love this valley for its beauty.  I am 78 years old and will
 be  content to end my days here.  However, I was lucky and eng'oyed
 good health.  I I was very concerned with a healthy lifestyle
 and ray two daughters, my seven grandchildren and two great rrand-
 children  are fine healthy people who can enjoy living a full life.
 A foul environment will preclude  raising healthy children.

 Please take all these considerations into your decision making
 process.  The Town of Deerpark and the City of Port Jervis need
 the best possible remediation.  The burden our residents carry
 must be lightened.

 :ou are trained as environmentalists and I urge you to do the
 right thing and select #4- as the alternative remedy  for the
 sad state of affairs this area is in.


                                 Sincerely yours,
                                 Frances Hodson
HCR 60 B
Godeffroy, New York 12739

-------
»    I
New York State Department of  Environmental Conservation
60 Wolf Road. Albany, New York 12233-0001
                                                                           Henry G. Williams
                                                                            Commissioner
                                             August. 8,  1984
       Ms. Francis  Hodson
       HCR Box  60 B
       Godeffroy, New York  12739

       Dear Ms. Hodsor.:

            Governor  Cucmo has requested that this  Department reply to your letter
       of July  9, 1984.

            The State of New York does have a long  standing  active program for
       controlling  the injection of contaminants  into our grouiidwaters.  The State
       Pollutant Discharge Elimination System (SPDES)  has regulated discharges to
       ground and surface waters of New York State  since the system became law on
       September 1, 1973.

            Under the SPDES  system all discharges of  industrial  type waste to
       grcuncwaters are  required to have a  SPDSS  permit.  Standards for  such
       discharges are provided by Part 703  of New YOrk State' s official
       ccnpliation of codes,  rules,  ar.d regulations.   The water  quality  standards
       and discharge  standards contained in Parr  703  (attached)  are quite
       restrictive in controlling a wide variety  of toxic pollutants.

            Currently, about 300 industries that  discharge to groundwater  are
       regulated under SPDES permits.   For  most of these facilities, pollution
       abatement systems have long since been in  place.  Thus, much has  been done
       to prevent further  contamination of  our groundwater resources by  industrial
       discharges.

            However,  despite the successful ijiplementation oi  the  SPDES  program as
       it relates to  groundwater dischargers,  the protection of  our groundwater
       supplies frcm  toxic chtznicals still  presents a major challenge  for  the
       following reasons:

            1.    An effective survellience  and enforcement program for such
                 discharges  requires a  great deal of time and manpower and
                 resources:

                 a.    The  overwhelming  majority of industrial groundwater   .
                      dischargers are in Nassau and Suffolk Counties and the
                      majority of these coiisist of small operations.  Our
                      experience has been that the list of Industrie.- groundwater

-------
               dischargers changes by an astonishing 25% per year due to
               new industries coming into existence, existing industries
               proving or going out of business, and facilities which change
               ownership.

               Thus, administrative tracking of these dischargers alone is
               a complicated arid demanding task.

          b.   A subsurface discharge by its very nature is invisible.
               Thus, spills, whether accidental or otherwise, may go
               unnoticed or unreported.  Only frequent inspections and
               sampling by the Department can serve as an effective check
               on the data which industries are required to report by their
               permits.

     2.   The SPDES permit program does not apply to toxics leaching out of
          old landfills and other abandoned waste disposal sites.  These
          sites must be investigated and cleaned up through appropriate
          enforcement action.

     From the forgoing one can see that the protection of groundwater from
toxic industrial chemicals is a difficult and demanding task.  However,
this Department has provided strong and effective controls for industrial
discharges to the extent possible with the resources available.

     Thank you for your interest in this matter, if there are any further
questions or information needed please contact this office directly at
(518) 457-1067.

                                     Very truly yours,
J_
                                                t(c(• •->-<•£>?-
                                                       •> i -
                                     Anthony F. Adamczyk, P.E.
                                     Director
                                     Bureau of Wastewater Facilities Design
cc:  Commissioner Williams

-------
 .Citizen's Clearinghouse for Hazardous Wastes
                                               Center for Environmental Justice
                   Sewage  SIudge...A Dangerous Fertilizer
                                       By Stephen Lester. CCHW Science Director
 The land application of municipal waste-
 water sludge is fast becoming a major
 toxics issue.  Hundreds of mostly rural
 communities are suddenly being targeted
 for "land fanning" of sludge. In some
 communities like Wise County. Virginia.
 authorities want to reclaim strip mined
 land by filling it with sludge.  Other com-
 munities such as those in the Texas pan-
 handle, those in Prowers and Kiowa coun-
 ties in Colorado, and those in eastern Penn-
 sylvania have become targeted for sludge
 generated in New York City.
 What is spurring this latest  craze?  Its
 simple.  A ban on ocean dumping went
 into effect on July 1, 1992 sending many
 coastal cities like New York scrambling to
 find a way to get rid of their sludge. But
 sludge is also generated by every commu-
 nity that operates a wastewater treatment
 plant. Sludge is the end product of "clean-
 ing" waste water and disposal of this sludge
 is extremely complicated and difficult.

 The theory behind the land  fanning of
 sludge is to spread the sludge over farm
 land to allow the chemicals in the sludge to
 either dilute into local groundwaters and/
 or evaporate in to the air. This method does
 little more than transfer the chemicals in
 the sludge to groundwater and into the air
 and. therefore, is an inappropriate and
 poor method of "disposal" for sludge thai
 contains  toxic and hazardous chemicals.
 Twenty years ago, when EPA Tint consid-
 ered the idea of land fanning sludge, there
 was some merit to the concept primarily
 because  the constituents in sludge were
 mostly heavy metals. One could make the
 argument that some of these substances
could serve as "nutrients" or fertilizer in
some instances. In some circles, support
for this idea has grown to the point where
some believe that land farming is the ideal
solution,  '"an  environmentalist's  dream
come uue—waste becomes a resource."
  Unfortunately this view is naive and unre-
  alistic. While in theory, if there were few
  or no toxic substances present in sludge, it
  would be possible to land farm it safely.
  But as a practical matter this situation
  simply does not exist. All sludge contains
  large amounts of organic chemicals, heavy
  metals and pathogens.
  This toxiciry is the result of many small
  (and some large) businesses that dump
  their toxic waste into municipal sewage
  lines.   Every study  that has tested for
  organic chemicals in sludge has found
  them, lots of them. One landmark study by
  the American Society of Civil Engineers
  clearly identified a significant number of
  toxic organic chemicals that are typically
  found in sewage sludge including PCBs,
  pesticides  and many chlorinated com-
  pounds (see What's in Sludge, p. 9).
  Dr. Donald Lisk from Cornell University's
  College of Agriculture and Life Sciences
  estimates that typically 100-200 compa-
  nies will flush their waste into a single
  treatment plant and that literally thousands
  of chemicals may be present in a single
  sludge sample. In addition, newly formed
  toxic substances are created as waste prod-
  ucts break down in sludge.
  Dr. Stanford  Tackett of Indiana Univer-
  sity of Pennsylvania describes sludge as
  being "closer to the definition of a toxic
• waste than it is to fertilizer." in testimony
.  before the Pennsylvania House of Repre-
fSentatives. Dr. Tackett. who has studied
'the effects of lead on soil and groundwater
j  for 25 years, warned that "one application
\ of sludge adds more lead to the soil than
 idid SO years of using leaded gasoline" and
''that  once sludge is applied, the soil can
\ never be recovered.
  Land farming sludge poses a number of
  threats.  The most prominent risk is to
  groundwater that passes through the sludge.
•"As rain  falls on sludge, many organic
 chemicals are pulled into the groundwater ~
 as are heavy metals.  According to Dr.
 Tackett, "All lead does not stay immobi-
 lized in soil as claimed." Some of it always:
 moves from the soil to groundwater "rela- j
 lively quickly." People depending on this
 groundwater for drinking or for livestock
 use and to water crops are at increased risk
 of exposure to toxic chemicals.      "~
 Another threat is air emissions. Airpollut-
 ants  are generated when volatile chemi-
 cals  evaporate  from sludge  and when
 sludge-treated soil dries out and is carried
 away as dust. Thtse pollutants pose health
 risks to people living downwind.
The  most common concern raised about
the land farming of sludge is the impact on
crops grown on the sludge-treated soil.
EPA has set standards that limit theamoum
of heavy metals and  PCBs that can be
applied to soil.  These standards address
the ability of crops to absorb chemicals
when sludge is used as a nutrient or fertil-
izer.   They do not address sludge as a
disposal alternative and the potential health
and environmental impacts of groundwa-
ter contamination,  air emissions or the
ingestion of contaminated soil by cattle or
other grazing animals.  The absorption of
chemicals by crops is important but it is
not the only issue needing  attention and
regulation.
A critical issue that  has received little
attention is the presence of organic chemi-
cals  in sludge.  Few studies address the
health  risks these components pose and
there is little test data on the extent of these
contaminants in the sludge.  Federal regu-
 lations also fail to  address their impact.
Unless sludge is tested for these substances.
the health and environmental  risks will
remain unknown.  Make sure any sludge
coming into your community is tested for
organic chemicals.
                       Con't oa next ptgc
                                                    October, 1992
                                                         Everyone's Backyard

-------
 Center for Environmental Justice
                                  Citizen's Clearinghouse for Hazardous Wastes
 Another concern thai cannot be ignored is
 the track record of land farming sludge.
 There is little long-term experience. There
 are success stories and horror stories. For
 example. EPA originally allowed sludge
 with over 100 mg cadmium per kg soil to
 be given to farmers and gardeners. These
 sludges had high zinc  to cadmium ratios
 causing high crop uptake of cadmium.
 EPA was unaware of this factor until it was
 too late. Now crops grown in these areas
 cannot  be  used and the soil needs to be
 cleaned up.
 In  Oklahoma, nine horses died and 113
 others developed liver problems eating
 hay grown on land fertilized with sewage
 sludge and in Bloomington, Indiana. PCB-
 rich sludge was mistakenly given to gar-
 deners and farmers.  Problems like these
 prompted the Del Monte and Heinz cor-
 porations to ban the use of sludge on any
 land used for growing their food crops.
 EPA has been very slow to address this
 issue and is reluctant to even identify sludge
 treated sites that need to be cleaned up.

 Despite these realities, some environmen-
 tal  groups, including the Environmental
 Defense Fund, believe there can be "ben-
 eficial" uses of sludge.  They argue that if
 toxic substances are minimized or. better
 still, eliminated from the waste scream.
 then sludge would be "clean" and could be
 used as  nutrient or fertilizer.
Theoretically,  it's possible  to  create
 "cleaner" sludge by passing toxic use re-
 duction laws to limit chemicals discharged
 into sewage lines and to pretreat sludge to
 reduce contaminants. Some day this may
 be achieved, and we should strive towards
 this, but at this time, let's be clear, there is
 no such thing as "clean sludge."
 Dr. Lisk agrees.  He commented. "The
 concept of 'well engineered' sludg&is a
 myth. There is no sound scientific oasis
 for limiting levels of potential toxicants in
 sludge since we do not know the identity
 of most of them.  Even if both of these
 problems didn't exist, it is extremely un-
 likely that any feasible  monitoring and
 enforcement program could ensure that
 application regulations are met."
 In the end. whether a community wants to
 land farm sludge is a local  decision that
 should be made by the people who will be
 directly affected. No one has the right to
 say that land farming sludge is good for
 another community. The impacted com-
 munity must be given both sides of the
 story, so they can decide for themselves
 what risks they are willing to accept. How
 can community people be expected to ac-
cept  land farming sludge if the expert's
can't agree if sludge is safe?
           Resources:
 "LandFarmingSludge:AFactPack." CCHW.
 1992. A compilation ofnewsclips. articles and
scientific papers on what's in sludge and how
communities have been dealing with this issue.
Available from CCHW for S5.9J.
 "Land Application of V/astewater." A Report
 of the Land Application Committee of the
 American Society of Civil Engineers. 1987.
 (ASCE. 1987).

 "National Survey of Elements and Other
 Constituents in Municipal Sewage Sludges."
 Ralph O. Mumma et at.   Archives of
 Environmental Contamination andToxicology,
 Voi 13. 75-83.1984. (Mumma. 1984).

 "Organic Toxicants and Pathogens in Sewage
 Sludge andTheir Environmental Effects." JC
 Babish.  DJ Lisk. CS  Stoewsand and C
 Wilkinson.  A  Special  Report  of the
Subcommittee on Organics in Sludge, Cornell
 University. College of Agriculture and Life
Sciences. December. 1981 (Lisk. 1981).
  What's In Sludge
  According to researchers at Cornell University and a report of the American Society of Civil Engineers, the following substances
  are typically found in sludge:
  •   Polychlorinated Biphenyls (PCBs)
  •   Chlorinated pesticides — DDT. dieldrin. aldrin. endrin, chlordane. heptachlor. lindane, mirex. kepone, 2.4.5-T, 2,4-D.
  •   Chlorinatedcompounds—dioxin(TCDD)oUchlorobenzene,trichlorobenzene,tetrachlorobenzene.chloroaniline,dichloroaniline.
      dichloronaphthalene. tetrachloronaphthalene, trichlorophenol. pemachlorophenol. chlorobiphenyl.
  •   Polynuclear aromatic hydrocarbons - chrysene. benzo(b)fluoranthene. benzo(k)fluoranthene, benzo(a) pyrene, perylene,
      dibenzoU,j)anthracene. indo(1.2.3.c.d) pryene.
      Heavy metals — antimony, arsenic, cadmium, chromium, copper, lead, mercury, nickel, selenium, thorium, uranium, vanadium
      and zinc.
      Bacteria. Viruses. Protozoa. Parasitic worms. Fungi.
      Miscellaneous—flame rcurdants (asbestos),petroleum products, industrial solvents, iron. gold, nitrogen, phosphorus! potassium.
      calcium.
  Sources: ASCE. 1987; Lisk. 1981: and Mumma. 1984.

-------
 New York State Department of Environmental Conservation
 21 South Putt  Corners Road, New Paltz, New York 12561
 914-255-5453
                                                                  Thomas C Jorling
                                                                   Commissioner
                                    December 21, 1987
Frances Hodson
HCR 60B
Godeffray
New York 12739
Dear Mr. Hodson:

In response to your letter of October 15, 1987, a study of the Carrol  and
Dubies waste disposal  site in Port Jervis, New York, has just recently been
completed and it has been determined that this operation has caused contami-
nation of-the groundwater.

The Department is currently pursuing measures to further study and define
the extent of the contamination, as well as control  and remediate this
situation.

If you .have any further questions, please feel free to call  me.

                                    Yours truly,

                                        '      '   S'\
                                    Sandra L. White
                                    Assistant Sanitary Engineer
                                    Region 3
SLW:zl

-------
\m
       UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

^
 rtc,   .,<"                          REGION I I
                             26 FEDERAL PLAZA
                         NEW YORK. NEW YORK  1O278
   NOY  21  1988

 Ms. Frances Hodson
 P.O.  Box 60B
 Godeffroy, New York  12739

 Dear  Ms. Hodson:

 Your  October  18, 1988 letter to Mr.  Richard T. Dewling,  former
 Regional Administrator of Region II, concerning the  Carroll  &
 Dubies Landfill has been referred to me  for response.   The Carroll
 & Dubies site, now referred to as Carroll & Dubies Sewage Disposal,
 was proposed  for inclusion on the National Priorities List (NPL)
 in the June 24, 1988 Federal Register.   This means that  it is now
 eligible for  funding under EPA's Superfund program.

 I must advise you,  however,  that prior to the expenditure of
 Federal funds, EPA must attempt to locate those parties  potentially
 responsible for the contamination at the site in an effort to
 have  those parties fund the response action (cleanup).   I can
 assure you that the enforcement  process, i.e.  the search for and
 negotiation with potentially responsible parties will begin  by
 the end of this calendar year.   It may take several months to
 conclude this effort.   Based on  the results of the enforcement
 process for this site  and several others in the same situation,
 we will make a determination as  to which sites will be  funded by
 EPA for further action under the Superfund program.  Thereafter,
 the process to study the extent  of contamination at a site like
 the Carroll & Dubies Sewage Disposal site typically takes about
 18 months.   The study  process would then be followed by  a period
 of time to develop  an  engineering design for the site remedy and,
 after  completing the design,  the remediation (cleanup) of the
 si te.

 I  hope that I  have  addressed your concerns satisfactorily.   For
 continued site updates please contact Mr. George Pavlou of my
 staff  at  (212) 264-0106.   Mr.  Pavlou can keep you apprised of our
 enforcement efforts  and .our  future funding plans.
 Sincerely  yours,
 Stephen D.  Luftig,  Director
 Emergency  and Remedial Response Division

 cc:   Michael O'Toole,  Director
      Division of Solid & Hazardous Waste

-------
                                      -"*•'
Cortese
clean-up
continues
By TOM KANE
Record Correspondent  »    /     .—^

  NARROWSBURG — The Cortese land-   |
fill toxic removal project began two weeks  I
ago  and  will  be   completed  by  (
 mi
  id-December.
^
  During the next  few weeks, workers
will be excavating  sediment from two
seepage lagoons that contain toxic waste
deposited mere years ago. Samples will
be taken of the seepage and, according to
the results, the seepage will be taken to a
toxic waste site or a  non-toxic site.
  "We will also construct a storm water
channel which will divert rain water away
from the contaminated area," said David
Moreira, project manager of Waste Man-
agement Inc. of Massachusetts, the com-
pany contracted to  oversee the removal
action.
  Moreira is acting  on behalf of the Town
of Tusten.
  OHM Inc of Trenton, N.J., is the com-
pany doing the excavating.

  The landfill, which was used  in  the
 1950s, 1960s and 1970s,  is south  of the
 Hamlet  of  Narrowsburg  along  the
  >elaware River and next to the Erie Rail-
  ad line.
   he second phase, which .wiH bcgiq
      Workers In protective gear move burled waste yesterday
      at the Cortese landfill In Narrowsburg. This portion of the
                                                  J. TALBOTTrth* Rocord
                  clean-up Is expected to be complete by mid-December.
                  Another phase will begin In the spring.
     next spring, will sec the removal of bar-
     rels of toxic chemicals that were also
     buried years ago.
       The cost for the entire project is about
     $1 million.
       "It won't cost the town anything,", said
     Supervisor George Burkle.
       The money for the project comes from
the  federal  Environmental  Protection
Administration Supcrfund nnd from the
companies and individuals responsible for
the contamination.
  More than 20 years ago, the EPA closed
the landfill because toxic effluent was in
danger  of seeping . into  the  nearby
. Delaware River.
  The town owns about H/i acres of the
4i/i-acre site. The remaining three acres
are owned by John Cortese, Moreira said.

  It took years of negotiations and court
cases to have the landfill cleaned up.

  "It's finally going to be done and  over
with," Burkle said.

-------
age
lit
    Tests   show




    soil, water




Still  tainted
                           /            *


   But RSR site no threat


   to area,  DEC official says

   By MARIE SZANISZLO
   Staff Writer
     CRYSTAL RUN — About two  years after a state
   agency ordered Revere Smelting and Refining Corp. to
   monitor the soil and water around its plant, samples of
   both continue to show high levels  of arsenic and other
   contaminants.
     However, a Department of Environmental Conserva-
   tion official says there is no imminent threat to either
   the public's health or the environment
     In a recent memorandum, the Town of WalMU's con-
   sulting engineer, Richard McGoey, said ground water on
   the south side of the Ballard Road plant showed ele-
   vated levels of  arsenic,  antimony,  cadmium and
   chromium.
     The company's first  quarterly report for 19% also
   indicated that a nearby pond and stream, as well as soil
   samples on  the plant's boundary, also showed high
   levels of arsenic and lead, McGoey said.
     The findings are of particular concern to residents
   who have been monitoring the battery-recycling com-
   pany because the state DEC geologist most familiar
   with RSR is one of several employees who are losing
   their jobs because of budget cuts.
     "I would like to see that (the findings) don't fall into
   the cracks," said Harry Ross, chairman of the commu-
   nity  advisory committee  overseeing  the company's
   efforts to bring its plant into compliance with state and
   federal  regulations. "To fire the one expert you have
   working on this to save money doesn't make sense."
     Ellen Stoutenburghi a DEC spokeswoman, said it was
   unclear how James Yuchniewicz's workload would be
   handled after his June 14 departure.
     "There are other geologists that work for the depart-
   ment," Stoutenburgh said. "... Any time someone with
   experience leaves, however, it always  takes time  to
   bring someone else up to speed."
     The levels found in the soil and  water samples were
   consistent with previous findings, she said, and posed no
   "imminent threat to human health or the environment"
     "We think the contamination could be contained to
   the RSR property," said Aida Potter, an environmental
   engineer for the DEC.
     To bring its plant into compliance, the company began
   excavating lead-contaminated soil at the site last July,
   and was to build and begin operating by July of this year
   a separate facility designed to reduce sulfur dioxide
   emissions odors at the plant
     RSR had asked for an extension until May 10, 1997,
   Dumas  said, because its engineers  are looking at differ-
   ent ways to reduce the sulfur dioxide emissions.
     The DEC has agreed to give the company until Sept 7
   to finish the building and begin reducing emissions.

-------
Lead  linked  to  crime
By LEE BOWMAN
Scripps Howard News Service
  Lead contamination  not only
impedes brain development and
learning in  children,  but also
makes  them more  aggressive
and likely to engage in delin-
quent acts,  a new study pub-
lished Wednesday concludes.
  A four-year study of 301 Pitts-
burgh public schoolboys found
those  with  elevated  levels  of
lead in their bones were report-
ed by parents and teachers  —
and themselves — to be more ag-
gressive and  more likely to steal,
fight  and  vandalize than low-
lead counterparts.
  The results were reported  by
Dr. Herbert Needleman and col-
7/
-------
Law  to protect


area  reservoirs

By MICHAEL MELLO          O \ 1 \ 9 L
Ottaway News Service            V \   x  x
  WASHINGTON — President Clinton yesterday signed
into law a bill that could provide New York state with
$112 million over the next few  years to help protect
New York City's upstate reservoirs from pollution.
  Congress must approve a separate request to actually
spend the  money, however.  That makes  it unclear
whether federal aid will reach the city or upstate com-
munities in the reservoirs' watershed next year.
  Rep. Sherwood Boehlert, R-New Hartford, says he is
confident that it will. He'll have to move quickly to make
it happen. When Congress  returns from the  summer
recess after Labor Day, lawmakers will have only three
weeks to  wrap  up legislative  business before  they
adjourn for the fall elections.
  Boehlert, along with the state's senators, championed
the effort to win federal aid to help protect New York
City's water supply.
  Under an agreement with the federal Environmental
Protection Agency, the city would widen the buffer of
land it owns around the reservoirs in Delaware, Ulster
and Sullivan counties, and restrict development and
some farming practices in the area that could pollute
their waters.
  Communities in the region would have to  upgrade
their sewer and storm water systems to prevent runoff
into the reservoirs, potentially forcing residents to pay
some of the expensive construction costs.
  Federal  money would help pay part of what  could
be up to SI billion in project-related costs. If the city
does not act, Washington would force it to build a
filtration system that could cost more than $2 billion.
  Last week, the House approved another measure
sponsored by Boehlert seeking $25 million for watershed
protection in upstate New York. But that plan, in which
Washington would award grants to communities to help
them meet the new watershed protection requirements,
must still be approved by the Senate.

-------
     4. Provide [or the care, custody, and  control of Ike forest pre-
   serve.
     5. Provide for tlie protection and management  of marine and
   coastal resources and of wetlands, estuaries and shorelines.
     C. Foster und promote sannd practices  for the use of agricultural
   land, river valleys,  open land, and  other areas of unique value.
     7. Encourage industrial, commercial, residential  and community
   development wliicli provides the best  usage of land areas,  maxi-
   mizes environmental benefits and minimizes the  effects of less desir-
   able environmental conditions.
     8. Assure //ic preservation and  enhancement of  natural beauty
   and man-made scenic qualities.
     9. provide for prevention  and abatement  of  all water, land and
   iiir finlliilii'ii  Including iiiil  mil Innildl l<> Hull  rilnhil  In  ntir-
   ticiiiatcx, ynscs, •/, rnptirs, nnise, radiation, odor, nutrients and
   lir-atcd  liquids.
     10. Promote  control  of pests and  regulate the use, storage and
   disposal of  pesticides and other chemicals winch may  be  harmful
   to man, animals, plant life, or natural resources.
     11. 1'rontotc  cnntrol  tif   weeds  and  aquatic  growth,  develop
   methods of prevention and eradication, and  regulate herbicides.
      '5. Provide and recommend methods for disposal of solid wastes,
   including  domestic and industrial refuse,  junk cars, litter and
   debris consistent  with sound health, scenic, environmental  quality,
   and land use practices.
     13. Prevent  pollution through  the  regulation  of the  Storage,
   handling and transport iif sttlids, liquids and gasrn which tuny cniixi
   or  contribute  to pollution.
     14. Promote restoration and reclamation of degraded or despoiled
f  areas and natural resources.
     15. Encourage  recycling  and  reuse   of  products  to  conserve
   resources and reduce ivaste products.
     16. Administer properties  having unique natural beauty, wilder-
   ness character, or  geological,  ecological  or  historical signilicancc
   dedicated  by law to the state nature and historical preserve.
     17. Formulate  guides  for  measuring presently  unqualified
   environmental values and relationships xi> they may  br. given appro-
   priate consideration along with social, economic., and technical con-
   siderations in decision-making.
     1^. Encourage and undertake scientific  investigation and research
   mi  the  cctilinjieul  process,   pollution prevention  and  abatement.
   recycling anil reuse of rcsDure.es,  and  other areas essential to under-
   standing and achievement  of the environmental policy.
     1'J. Afsexs new and changing  technology,  and development pat-
   terns to identify  Inng-ranfie  implications (nr the  environment and
   • nr-iii I'niji  ulti I'n'iti i'i \  irlncli iniitiiniii' ntlt'i'i'xi- impart.
     ;?(). Monitor the environment to affonl nwre. effective and  efficient
   control practices, to identify changes and conditions in ccnlogical
   systems and to warn of emergency conditions.

-------
 Pubflc Notice 93-53
 Dots: August ". 1993
 Notice of proposed odmW-
 jtrotlve penalty assessment
 and  opportunity  to
 comment
 Agency: Environmental
 Protection Agency (EPA)
 Action: Notice of proposed
 odrrtnlstrattve  penalty  as-
 sessment cod opportunity
 to comment
 Summer/: EPA Is providing
 notice of proposed odmlnj-
 stratlve penalty assessment
 for aleged violations of the
 clean water act. EPA is atso
 providing notice of oppor-
 tunlty to comment on the
 proposed   penalty
 assessment.
 Under  33 U.S.C. §1319(G).
 EPA Is authorized to issue
 orders assessing cMI penal-
 ties for various violations of
 the act. EPA may Issue such
 orders after  the  com-
 mencement of a Class II
 penalty proceeding. EPA
 provides public notice of
 the  proposed assessment
 pursuant  to  33  U.S.C.
 §1319
-------
-Y.
                                                    August 12, 1993
 EPA   may   fine    Skydyne    $10
  By DAVID CORDON
  SUIT Reporter
   PORT JERVIS — The  federal
  Environmental Protection Agency is
  seeking a  SI00,000  fine  against
  Skydyne Corp. for alleged dumping
  of excess chromium into (he city's
  treatment plant.
   Skydyne's general manager Jay R.
  Benson said today the company has
  redesigned its production processes to
  eliminate the problem. The proposed
  fine is not final, and the company is
  seeking a hearing, he said.
   Skydyne manufactures cases  for
             45 Cents
10,000
      '         Sl'(f
    EPA officials could not comment
  on whether the company is currently
 ' in compliance, but John Dolinar, EPA
 | assistant regional counsel, said the
  fine would be levied on previous non-
  compliance.
    "We would expect them to be in
 . compliance, especially after we noli-
 • fied them (hat we were aware of the
 I noncompliance," he said. "It's nice
  that they are now complying and be-
  ing responsible, but the fines are for
  the past violations.
                                  gauges and instruments, and metal
                                  containers.      ,_ *-
                                   The alleged  violations occurred
                                  between January 1989 and December
                                  1982, according to a complaint Hied
                                  by the EPA. Wastewater from the
                                  plant  exceeded  (he  maximum
                                  monthly average limits for chromium
                                  in eight months during the period. On
                                  one day. Dec. 8.1992, the waslcwater
                                  contained more than the daily maxi-
                                  mum of chromium.
                                   According to the EPA complaint,
                                  industries are  required to pretreat
                                  wastewater going into a public treat-
ment plant to reduce or eliminate
heavy metals and other hazardous
substances.
  Wastewater entering the Port Jervis
sewage treatment plant,  which is
owned  by New York City, must
contain no more than 2.77 milligrams
of chromium per on any given day.
The monthly average must not exceed
1.71 milligrams per liter.
  The amounts of chromium found in
the EPA's review varied from 1.72
milligrams per  liter to 3.45. Most
results were in the 2.2 to 2.68 range,
with one  reading of 3.45.
  The EPA complaint also charges
that Skydyne failed to maintain-waier
samples to be tested for cyanide on
July 8, 1992, at the required 4 degrees
centigrade during transport from the
plant to the laboratory.
  Benson has been Skydyne's gen-
eral manager since last August. He
received the first notice from the EPA
on the violations in  December, he
said.
  "We were in total  compliance in
January," he said. "We've changed
the process, we've invested the mo-
ney, and we're within all the limits."
                                        llotlson
                                        HCROOD
                                        Oodeffroy. KY 12739
                                                                          Thursday, August 12 199?
                                                               The  rest of the story
                                                              *EP/\
                                                              (Continued from page 1)
                                                                Before the fine is levied, a hearing
                                                              will be held to determine whether the
                                                              amount is appropriate. Members of
                                                              the public may contact EPA Hearing
                                                              Clerk Karen Maples at the Region II
                                                              office, 26'Federal Plaza, Room 437,
                                                              New  York, N.Y.  10278  to submit
                                                              written comments.
         F.PA. hack ptqe)

-------
 Public Notice 93-53
 Dote: August 11. 1993
 Notice of proposed odminl-
 ttrcrttve penorty assessment
 and  opportunity  to
 comment
 Agency:  Environmental
 Protection Agency (EPA)
 Action: Notice of proposed
 administrative penalty  as-
 sessment and opportunity
 to comment
 Summary: EPA Is providing
 notice ot proposed admini-
 strative penalty assessment
 for oflecied violations of the
 clean water act. EPA is also.
 provtdng notice of  oppor-
 tunity to comment  on the
 proposed   penalty
 assessment.
 Under  33 U.S.C. §1319(G).
 EPA  Is authorized to issue
orders assessing cM penal-
 ties (or various violations of
 the act. EPA may bsue such
orders after the  com-
mencement of  o  Class II
penoJIy  proceeding.  EPA
provides pubic  notice of
the  proposed assessment
pursuant  to 33  U.S.C.
§1319»c comment on a prop-
osed class  II order Is thirty
(30) days after Issuance of
pubBc notice.
On the date Identified be-
low.  EPA commenced the
(otowtng class H proceed-
ing for  the assessment of
penotttes:          i
Irv «•*» mnttar <•»/ A AD <~/-»r*s-
S«
to
P<
t>


N
n
c
S<
1
m
P/
w«
 In the matter of AAR Corpo-
 ration (Skydyne. a drvtolon
 of AAR Brooks * Pertdns Cor-
 poration).  21  Rtver Rood.
 Port Jervb. New York 12771.
 Docket No.
 EPA-CWA-ll-93-SO: fted  on
 Jury 28.  1993 wtlh regional
 hearing derV Karen Maples.
 VS. EPA. Region B. 26 Fed-
 eral Plaza. Room 437. New-
 York. NSW York fQ278. (212)
 264-9&80;  proposed  pen-
 alty. S 100.000. for foSure to
 comply wtth the section 307
 of the Clean Water Act and
 the categorical preheat-
 ment regulations found at
 40 C.F.R. §433.
 For further Information: per-
 sons wtehJng to  recerve a
 copy of EPA's consolidated
 rules, review the  complaint
 or other documents filed In
 this proceeding,  comment
 upon the proposed assess-
 ment, or otherwise partici-
 pate In any of the proceed-
 ing should contact the reg-
 lonal  hearing  clerk
 Identified  above. Unless
 otherwise noted,  the admi-
 nlstrattve record for the pro-
 ceeding b located In the
 EPA regional office Identt--
 fled above, and the fie win
 be  open for pubBc Inspec-
 tion during normal business
 hours. All Wormalton sub-
 mitted by the respondent Is
 available os part of the ad-
 mlnbtraflve record. sub)ect
 to provisions of taw restrict-
 ing  public disclosure of con-
 fidential Information. In or-
 der to provide opportunity
 for  public  comment. EPA
will  Issue no final  order as-
sessing a penarty m this pro-
ceeding prior to  thirty (30)
 days from the date spect-
 ned below.
 CXited: August 11.1993
 Richard L Caspe.  P.E..
Director
Water Management
Drvteton
                                                    Ai
                                                    we
                                                    32
                                                    Nf
                                                    S3
                                                    St<

-------
  N.Y. lii'oy


                   INDUSTRY ALONG ROUTS 209

                        DBERPARK, N.Y.


  1.   Marcy South Power Line

  2.   MAS lagoons for septic waste.
      hauling it to this site.

  3.   Pete's Auto Service   Westbrookville

  4.   Lafarge-Sullivan - next to Basha Kill

  5.   Brim  Recycling - auto crushing,  batteries,  etc.  Basha Kill
  6.   Westbrookville Auto Body
                                   r-ASLu
  7.   Tenke's - Auto repair and junkyard

  8.   Lewis's Convenience store .- gas  pumps

  9.   Firohouse

10.   C & D Battery
                                                    >
11.   Town  Hall and Maintenance Sheds  for Road  Equipment
12.   Deerpark Auto Sales -  repairs  and  painting
15.   Deerpark Equestrian Farm - Han  Corp.
14.   Feenpack Sand and Gravel and Cement Plant off
      Peenpack Trail about i mile from 209

15.   Summit Labaratories (formerly Dow Chemical,  and
      before that Wickham.   Tons of contaminated  soil  removed
      by Dow and furnace to burn off  toxic  fumes  from  under-
      ground.   Development on this site has caused water
      problems to neighbors,  low pressure from  wells and
      flooding of their soil.

16.   Port  Jervis School District.  Transportation garage
      and sewer system

17.   Monk  and Tony and Delaware Valley Sand and  Cement  Block.
      Recently rezoned Rural Residential  Area.  Monk and
      Tony  had 6 acres "Industrial".   Industrial  zone  is now
      350  acres.
18.   Port  Jervis landfill

19.   Carroll  & Dubies toxic landfill
20.   Trovei Junkyard
21.   S & K Vehicle -  Battery  repair and  tire yard with
      30,000 tires.
22.   Columbia Gas  - gas  line  and station on 209.   Line
      crosses  from  west to  east


In addition we  have many  gravel pits  scattered along  209.
There are  several  power  lines  crossing over the river.
Numerous auto mechanics  operating  on  their homesite.
w.,o, - ?0 vrars  of  contamination
       '- J y  .../..,•    ty .•<££-.**.&

-------
           TOWN OF DEERPARK TOWN CLERK OFFICE
                DRAWER A, ROUTE 209 N.
                 HUGUENOT, N.Y. 12746
              SHIRLEY ZELLER.TOWN CLERK
                TELE.NO. (914) 856-5705
                                     September 23,1996

PROJECT;CARROLL AND DUBIES SEWAGE
          DISPOSAL INC.
         TOWN OF DEERPARK, ORANGE CO.
          NEW YORK
U.S. Envrionmental Protection Agency
Attention: Maria Jon, Project Manager
290 Broadway, 20th Floor
New York, New York 10007-1866

Councilman Robert Zeller, attended your public hearing representing the
Town Board and reported the information that was presented to the public
by your agency, with the board taking the following action, regarding the
several plans submitted for the clean up of the area.

The Town Board requests the Agency be informed they wished the
Alternative proposal 3-Groundwater Pump and Treat via Precipitation,
Filtration and Carbon Adsorption, be the plan used in handling the clean
up of this area.

It is felt this is a better control plan and containment of any contaminated
ground water that may be on the location of the site.
                        Shirley Zell
                        Town

-------

    Dr. and Mrs. Hassan Sadaghiani
14 Orchard Lane •  Port Jervis, NY 12771

-------
                   PJHS Parent Teacher StucCent Association
                                 Jioute209
                        Port Jervis, New york,   12771
                                       September 13, 1996

Maria Jon. Project Manager
U.S. Environmental Protection Agency
290 Broadway, 20th Floor
New York, NY 10007-1866

Dear Ms. Jon:

      Because of a prior commitment to a mandatory meeting, the majority of
our membership were unable to attend your public hearing in Port Jervis on
September 11.  We do not wish this to be misconstrued as disinterest in the
problem of a Superfund Site in such close proximity to our High
School/Elementary School complex.
      Rather, we. the  Port Jervis High School PTSA. would like to go on public
record encouraging the prompt and complete clean-up of the Carroll and Dubies
Sewage Disposal Site, Canal Street, Port Jervis/Deerpark, New York.  We
strongly urge you to proceed quickly with the completion of your recommended
action on Operable Unit 1. It was upsetting to hear that may be as far away as
1999. We currently have more than 1000 students in our high school, close to
900 in the contiguous  elementary school, and the number is continually rising.
Since the school district is using Port Jervis City water, contamination of
groundwater used for  drinking  is not a concern for our student population. We
do have a major concern with the possible contamination of Cold Brook (given
the name Gold Creek on your maps). This stream runs within 1,500 feet of the
contaminated lagoons  on the Carroll and Dubies property and is downgradient
of them. It is adjacent to our playing fields and our students have had to enter it
to retrieve balls on more than one occasion.
      Out of concern for the health of our students and possible exposure to

-------
deleterious material, we urge that you do repeat testing of the waters of Cold
Brook (Gold Creek) and its sediment immediately and at frequent intervals
until completion of your planned excavation, onsite treatment of contaminated
materials, and containment and capping of the lagoons. We had a lot of snow
last winter and heavy rains since which have most likely caused flooding of the
lagoons on site and escape of probable contaminated material through the
wooden fence surrounding Lagoons 1 and 2, as well as seepage through
groundwater from the other soil-covered lagoons. We have approached our
Superintendent to ask the School Board's permission to conduct independent
studies which can be compared with your results.
   ,   Our children are too precious to us. We, as parents, and you as agents of
our government must do all in our power to protect them from harm. We trust
you will do your part, as we will do ours.

                                        Sincerely yours,
                                        anine LaFemina, PTSA President
                                        Irene Lntranuovo, Vice-President
                                       Erin Cunningham. Vice/President
                                                          r^r-As*
                                       Deborah Cun'ningham,cSecretary


                                       Catherine Sadaehiani. Treasurer
jl/hf
cc: Patrick Hamill, Superintendent of Schools

-------
                                               September 19, 1996


                                                    Miss Haanof Back
Maria  Jon,  Project Manager
U.S. Environmental Protection Agency         '«V^V?' PcrtJ<"vis>NY12771
290 Broadway,   20th floor                      fRAL
New York, New  York  10007-1866

Dear Ms. Joni

Enclosed is a  copy of my letter to the  Editor of the  Tri-
State  Gazette.

I have struggled through the EPA report presented at  the
Public Hearing on the Carroll and Dubies Toxic  Dump.

1.  Because of the inconsistency between 199^ and 1995
sampling results, you did another test  in 1996.   The  report
stated turbidity caused the  high concentrations of inorganizs.
The cause was  the pump used  and that the samples were not
filtered.   The report stated that some  monitoring wells were
re-developed and some monitoring wells  now have lower levels
in the samples.   I can's help but wonder if turbidity is not
a normal condition underground during heavy rainfalls or
flooding.   If  filtering removese harmful chemicals, can an
ordinary sink  filter do the  same?

2.  I  refer to the statement that ground water  modelling is
an indication  that concentration patterns have  been stabilized.
I s this water modelling a foolproof system?

I have no confidence in the  plans 1 and 2 and do not  under-
stand  the mechanics/engineering of the  other systems.  I
believe the public should have a clearer explanation  of this
whole  situation.
                       \
I will appreciate your considering these questions and  will
appreciate  hearing from you  before the  end of the comment
period, September 27th.

Thank  you for  your kind attention.

                                   Sincerely yours,
                                   Eleanor Back
                                                      •k  12771
                                         Miss Eteanot Back
                                         SUaikO
                                       £, PwlJerve. NY 12771

-------
 L«tter to the Editor - Septemoer  xy,

 Dear Editor i
 I  am a newcomer to this area  -  only three years.  It is lovely here
 and I enjoy it greatly, but it  is  so sad to hear of the careless
 selfish acts  of those who have  dumped their toxic wastes on poor,
 pretty Deeerpark.
 The E.P.A.  held a  public hearing  on September 11 th, 1996 to inform
 us of their plane  to clean up "some of the lagoons and surrounding
 soil* polluted by  Reynolds Metals, Wickhara and KoTmar.
 This particular site opened in  1970 and closed in 1979.  It IB
 now almost  1997.   This site was on the "National Priority List."
 The E.P.A.  has four alternative plans for clean-up and each takes
 five years.'   Alternative one  is to do nothing and the second is
 similar except that it requires monitoring.  The third and fourth
 require great effort and more expense.  The E.P.A.  prefers Plan #2.

 The original  polluters are required to help pay for or take care
 of the  problems with E.P.A. supervision by removing 20,000 cubic
 yards yards of contaminated soil from the area.   The remaining
 contamination would be treated, placed on-site in a lined capped cell
 with leachate collection.   This leachate should be  monitored.   The
 whole area  should be  monitored.  This seems unlikely since no elected
 official was  at this  meeting in an official capacity to show
 concern for the citizens  of Deerpark.
 The  final result in five  years would be the area could be used as
an  industrial  site.  Who  knows how that would turn  out.

The B.P.A. Federal, State  or Local governments have failed to
protect our environment and our health.   I have a very cynical
feeling that  they will continue to fail to protect  our environment
and  our health.
                                 Very truly yours,
                                 Eleanor Back
                                 Port Jervis, New York

-------
THEODORE J CARLSON
WILLIAM P REILLY
GEORGE J WALSH III
JOHN E. GOULO
ROBERT J GLASSER. P C
FREDERICK W LONDON
PETER V K FUNK. JR
ROBERT E PEOERSEN
ANDREW W BANK
EDWARD V. ATNALLY

RICHARD T KORTRIGHT
WALTER A. 8OSSERT. JR.
    OF COUNSEL

OOREEN M SCHRAUFL
  ADMINISTRATOR
 GOULD  &  WILKIE

       iFOUNOCO IN 1692)

   COUNSELLORS AT LAW

ONE CHASE MANHATTAN PLAZA

 NEW YORK. N.Y. I OOO5-I 4O 1

       2 I 2-344-S68O
  SALLY A MUIR

MICHAEL R- MANLEY

 ERIC O COSTELLO

 GREGORY I SIMON

ROBERT T BARNARD

MARYLOU SCOFIELO



  C4BLC *OO*»ESS

    COLDKE"



   TELECOPIER
    By-Hand
                            September  26,  1996
    Ms.  Maria Jon
    Project Manager
    U.S.  Environmental Protection Agency
    Region II
    290  Broadway,  20th Floor
    New  York,  New York 10007-1866

         Re:   Carroll & Dubies Sewage Disposal Superfund Site
              	Port Jervis.  New York	

    Dear  Ms.  Jon:

              This letter presents the comments of Koltnar Laboratories,
    Inc.  and Wickhen Products, Inc.  concerning the proposed Remedial
    Action Plan  dated August 28,  1996 for the Second Operable Unit
    (OU2)  at  the above-referenced site.   Kolmar and Wickhen believe
    that  the  proposed Plan generally presents an appropriate recom-
    mendation for adoption of alternative 2,  natural attenuation with
    institutional controls and monitoring,  subject to the following
    qualifications.

              First,  the responsibility for establishing institutional
    controls  should be placed on the City of Port Jervis.  The  land on
    which a majority of the site exists is owned by the City of Port
    Jervis and it is appropriate that the Agency establish any  required
    institutional controls with the landowner.  The City of Port Jervis
    has been  the owner of this site for many years and it clearly knew
    of the activities being carried on on its property.  Furthermore,
    the City controlled access to the Site through controlling  access
    to the general area of the Site's Municipal Landfill/County
    Transfer  Station.

-------
GOULD &. WILKIE

   Ms. Maria Jon
   September 26, 1996
   Page 2.
             Second, with regard to monitoring the proposed Plan.is
   unclear.   The Agency will require monitoring as part of the resolu-
   tion of the First Operable Unit  (OU1) and it remains unclear as to
   whether any additional monitoring is contemplated for OU2.   Kolmar
   and Wickhen believe that no additional monitoring should be re-
   quired,  based upon the indications previously provided to them
   concerning monitoring requirements in connection with GUI.

             The presentation made by the Agency at the Public Meet-
   ing held on September 11, 1996 at the Port Jervis High School
   Auditorium generally described the attenuation of the plumes that
   will occur upon removal of the source area.

             It should be noted,  however,  that  the existing plumes are
   static and are not expanding.   The existence of a steady state
   condition at this time is significant because it shows that the,
   source areas do not presently threaten any off-site receptors,  and
   upon removal of the source areas, the plume  will contract over a
   very short period of time.  The time periods presented by the
   Agency at the Public Meeting were the more conservative values
   (i.e..  of greater time duration)  indicated by the groundwater
   modelling.   In fact,  the groundwater modelling results suggest that
   the plumes will attenuate over a much shorter time than the five
   year period suggested by the Agency at  the Public Meeting.   It
   appears  that a number of the comments presented at the Public
   Meeting are traceable to the fact that  the full extent of the
   groundwater modelling results  were not  described by the Agency in
   its presentation at the Public Meeting.   In  reality,  the concerns
   of  many of those at the Public Meeting  chat  a significant time
   period will be required for remediation have already been addressed
   by  the groundwater modelling studies indicating that natural
   attenuation will be accomplished rapidly upon source removal.

             The presencacion made by che  Agency ac the Public Meeting
   did indicated the relative costs for che various alternatives.  How-
   ever,  in  fact,  from a tirr.e line standpoint alone,  alternative 2
   will  accomplish the desired results over a time period as short: or
   shorter than could be accomplished by alternatives 3 or 4.   When
   the much  greater coses of alternatives  3 or  4 are considered,  the
   Agency's  proposal to adopt alternative  2 clearly becomes the only
   reasonable choice,  subject to  the concerns noted at the beginning

-------
GOULD &.  WILKiE

   Ms. Maria Jon
   September 26,  1996
   Page 3
   of this letter.  We hope that these comments will be of assistance
   to the Agency in the presentation of the record of decision and
   request that they be included in the public record of this matter.

                                    Respectfully  submitted,
                                    Robert J.  Giasser        '
                                    Gould & Wilkie
                                    One Chase  Manhattan  Plaza
                                    58th Floor
                                    New York,  New York 10005-1401
                                    (212) 320-0109
                                            Murphy
                                   Lester Schwab Katz & Dwyer
                                   Y20 Broadway
                                   New York, New York 10271-0071
                                   (212) 964-6611
  RJG:cw
  By-Hand
  arglmmj.Itr

  cc: v/Sharon E.  Kivowitz,  Esq.

-------