EPA  Superfund
       Record of Decision:
       Fields Brook Site, OU 2
       Ashtabula, OH
       9/29/1997
                                 PB97-964113
                                 EPA/541/R-97/115
                                 January 1998

-------
   RECORD OF DECISION
          FOR THE
SOURCE CONTROL OPERABLE UNIT
           OF THE
 FIELDS BROOK SUPERFUND SITE

         Ashtabula, Ohio
         September, 1997

-------
                DECLARATION FOR THE RECORD OF DECISION


SITE NAMK ANT> I jftT ATTON

Fields Brook Site, Operable Unit II, Source Control Areas, Ashtabula, Ohio

STATEMENT OF BASIS ANT> PITPPOSF

This decision document represents the selected Final Remedial Actions for the Fields Brook
Site, Operable Unit n (Source Control Areas), in Ashtabula, Ohio.  These actions were chosen
in accordance with the Comprehensive Environmental Response, Compensation and Liability
Act of 1980 (CERCLA), as amended by the Superfund Amendments and Reauthorization Act
of 1986 (SARA), and to the extent practicable, with the National Oil and Hazardous
Substances Contingency Plan (NCP). The decisions contained herein are based on information
contained in the administrative record for this site.

This Record of Decision (ROD) is the third for the Fields Brook Superfund Site. The State of
Ohio did not concur with the Floodplain/Wedand Operable Unit ROD, dated June 30, 1997.
In addition, the State of Ohio elected not to concur with the Sediment Operable Unit cleanup
plan, as revised in the August IS, 1997, Explanation of Significant Differences. The remedial
activities selected in mis ROD for the Source Control Operable Unit support the cleanup of the
Floodplain/Wetland and Sediment Operable Units by preventing the recontamination of Fields
Brook sediment. The scope of the Source Control Operable Unit has been limited to those
areas that have the potential to recontaminate Brook sediment above cleanup goals.  The State
of Ohio disagrees with the limited scope of the Source Control action and has elected not to
concur with this ROD.  A letter of nonconcurrence  from the Ohio Environmental Protection
Agency (OEPA) is attached to this Declaration.

ASSRSSMRNT OF THF. HlgMF.T>IFS

Actual or threatened releases of hazardous substances from the site, if not addressed by
implementing the response actions selected in this ROD. may present an imminent and
substantial endangerment to public health, welfare,  or the environment.

DESCRIPTION OF THF.
 These remedies are intended to be the final actions for Operable Unit D (Source Control
 Areas, "SC") of this site.  These final actions address contamination at six (6) locations that
 have been identified as sources of contamination to Fields Brook.  For the evaluation of
 disposal options, the Sediment and Floodplain/Wetland Consolidation area (to be built on one
 of the industrial properties within the watershed) is considered to be an on-site landfill. The
 six source areas and the major components of the selected remedies are, as follows:

-------
            i
      The selected alternative (Alternative VI) requires excavation of surface soil with PCB
      concentrations greater than or equal to SO parts per million (ppm).

      Excavation to a depth of approximately 1 foot will remove all soil regulated by the
      Toxic Substances Control Act (TSCA) and will result in an estimated volume of 1,800
      cubic yards.

      The excavated soils will be disposed at either an on-site or off-site TSCA-approved
      landfill.

      Following completion of excavation activities, the excavated areas will be backfilled
      with clean soil and graded to allow for adequate drainage.

      The remaining surface soils included in the remedial response area will be contained
      on-site with a 12-inch soil cover and an erosion control blanket and will be Vegetated to
      reduce erosion. For traffic and work areas, a geotextile and 6 inches of gravel will be
      used.
Milk«nfami
       The selected alternative (Alternative VI) requires excavation of soil with PCB
       concentrations greater than or equal to SO ppm.

       The excavated soils will be disposed at either an on-site or off-site TSCA landfill.

       Following completion of excavation activities, the excavated areas will be backfilled
       with clean soil and graded to allow for adequate drainage.

       The remaining surface soils included in the remedial response area will be contained
       on-site with a 12-inch soil cover and an erosion control blanket and will be vegetated to
       reduce erosion.  For traffic and work areas, a geotextile and 6 inches of gravel will be
       used.
North and South
       The selected alternative (Alternative HI) involves the removal of sediment and debris
       from inside the sewer lines and the associated catch basins.

       Portions of sewers that are blocked and difficult to clean will be closed off, and the
       sediment within the sewers contained. The sediments in these sewer segments will be
       contained by filling the sewer pipe with a cement grout to restrict flow in the sewer and

                                           ii

-------
RMI
      prevent migration of sediments into Fields Brook.

      Replacement sewers will be constructed to divert water from the sections that have been
      closed and to connect the remaining sections of the sewers that have been cleaned.
      These sewers will continue to be used after remedial activities are completed.

       f!nrpnratfnn
      The selected alternative (Alternative IV) includes the construction of a partial slurry
      wall to contain the Dense Non-Aqueous Phase Liquid (DNAPL) and contaminated
      groundwater,

      Vacuum-enhanced extraction wells will be installed to lower the groundwater table and
      collect DNAPL.  Extracted groundwater will be treated by Detrex's existing
      stormwater treatment system that uses carbon filtration to remove contaminants from
      collected surface water. Extracted DNAPL will be treated or recycled off-site.

      Low-lying areas within the existing'collection system area and areas with surface soil
      cleanup goal exceedances will be filled and regraded. These areas would then be
      covered with a 12-inch thick soil layer, an erosion control blanket, and a vegetative or
      crushed stone layer surface.  The regraded areas will be vegetated to protect against
      erosion.
       The selected alternative (Alternative IV) requires excavation of soils with PCB
       concentrations greater man 10 ppm.

       The depth of the excavation will be approximately 1 foot and will result in an estimated
       volume of ISO cubic yards

       The excavated soils will be disposed at either an on-site or off-site Toxic Substances
       Control Act (TSCA)-approved landfill.
f!nnrail
       The selected alternative (Alternative IV) requires the consolidation and containment of
       arsenic-contaminated soils.

       Excavation to a depth of approximately 6-inches will remove approximately 90 cubic
       yards.

       Excavated soils will be moved a short distance to a consolidation area (on Conrail

                                           iii

-------
      property) for final disposal.  Upon placement of excavated soils, this area will be
      graded and covered with 6 inches of gravel to prevent soil erosion.
All
For all source areas where contamination will remain on-site within a containment area, the
remedies will include the following:

•     Long-term operation and maintenance (O&M) and post-closure care of die remedial
      actions to help ensure effectiveness.

•     Long-term monitoring to verify the effectiveness of the remedial actions.

•     Placement of institutional controls on deeds and title for properties where hazardous
      substances, pollutants or contaminants will remain above levels mat allow for unlimited
      use and unrestricted exposure. These controls will limit the future use of areas so as to
      ensure that contamination does not migrate to the Brook.

•     Implementation of access restrictions, including the construction of new fencing where
      necessary to prevent access and maintain the  integrity of cover systems.
STATUTORY DETERMINATIONS

These final Remedial Actions are protective of human health and the environment, comply
with Federal and State applicable or relevant and appropriate requirements and are cost-
effective.  The selected remedial actions utilize permanent solutions and considered use of
alternative treatment technologies to the maximum extent practicable.  However, due to the
significant volume and heterogeneous distribution of waste at the Site, treatment as a principle
element is not considered practicable at the Site. Thus, these remedies do not address the
statutory preference for treatment that reduces toxicity, mobility, or volume as a principal
element.  However, treatment is a secondary element in that DNAPL from the Detrex facility
will be collected and treated resulting in destruction of hazardous substances.

A review  of the remedies will be conducted five years after commencement of the remedial
actions to ensure that the remedies continue to provide adequate protection of human health
and the environment by preventing the flow of contamination to Fields Brook.
 William E. Muno, Director
 Superfund Division
                                          IV

-------
                               State of Ohio EavtrauMOtal Protection AgencJ* C C B I V £
Si^oTT^lOW                    TELE:(614)644«2DFA>t(614)644.a29      —  I - 1997 Cou^ON43216-1049
      Septembers, 1997
       Mr. David A. Ullrich
       Acting Regional Administrator
       USEPA Region V
       77 West Jackson Blvd.
       Chicago, IL 60604

       Dear Mr. Ullrich:

       Thank you for the opportunity to review and comment on the draft Record of Decision (ROD)
       for the Source Control Operable Unit (SCOU) of the Fields Brook Supertund Site (Fields
       Brook).

       As you know, Ohio EPA made a decision over a year ago to relinquish our role in providing joint
       oversight with USEPA for Fields Brook in order to focus our attention on the Ashtabula River
       project Prior to this decision we had expressed concerns about USEPA's overall approach to
       risk management for the SCOU.  We felt that source control remedies should be based on
       managing risk at each individual source area by following the usual process of evaluating risk by
       all appropriate pathways and developing cleanup goals based on site risk. USEPA took the
       approach that source control remedies would be designed to address the risk of recontaminating
       Fields Brook Sediment at concentrations in excess of the Brook Sediment Operable Unit (SOU)
       cleanup goals (CUGs). SOU CUGs were based solely on human health effects from incidental
       sediment ingestion. SCOU remedies were limi 'd to areas which could potentially cause the
       SOU CUGs to be exceeded in the future. All potential source areas were screened by comparing
       contaminant concentration to the SOU CUGs and  evaluating pathways of contaminant migration
       from the source area to the Brook Sediments. Any potential source area which was lower in
       concentration than the SOU CUGs or for which there was no pathway by which that source could
       recontaminate Brook sediments (to concentrations in excess of the SOU CUGs) was eliminated
       from further consideration. Originally about 200 potential source areas were considered.  After
       the screening process only 6 areas were carried forward. These potential source areas were
       eliminated without regard to risk to human health  or the environment Recharge of the Brook by
       contaminated groundwater and surface water were eliminated because these processes could not
       result in sediment concentrations higher than the SOU CUGs.  USEPA contended that any areas
       which present risk to receptors other than Fields Brook  sediment or which may violate any
       regulatory standards should be addressed separately under other regulatory programs such as
       RCRA Corrective Action or the Clean Water Act. It was even suggested that a source area or
       areas could be individually scored as separate NPL sites in the future.

                                        George V. Voinovfch. Governor
                                        Nancy P. Hottster. U Governor
 EPA 1613 (rev. S/96)                         Donald R. Schnjgwous.  Director
 ^£ Pnrtea on tlecycieu Pyac

-------
                               Slate of Ohio Eavbonmental Protection Agency
IMOWMMMMkMM
Columbus, OH 4321S-100B
  TELE: (614) 644-3000 FAX: (614) 644-2329
        P.O. Bra 1049
Cohmbus. OH 43216-1049
      Mr. David A. Ullrich
      September 8,1997
      Page-2-
      Ohio EPA continues to disagree with this approach. When we informed USEPA of our decision
      to allow you to manage the Fields Brook site without active Ohio EPA participation we
      expressed the hope that you would consider these concerns when making final remedy decisions.
      This SCOU ROD does not reflect any change in USEPA's approach to the SCOU cleanup,
      therefore, for the reasons stated above Ohio EPA does not concur with the ROD for the SCOU.

      Please feel free to contact Ohio EPA should you have any concerns or questions regarding this
      letter.
      Sincerely,
      Director
      Ohio Environmental Proteci
      SW/DS.wmk
Agency
      cc:    Jenny Tiell, Deputy Director, CO  "
             Jan Carlson, DERR, CO
             Mike Czeczeie, DERR, CO
             Ray Beaumier, DERR, CO
             Bill Skowronski, District Chief, NEDO
             Bob Wysenski, Assistant District Chief, NEDO
             Rod Seals, DERR, NEDO
                        Steve Love, DERR, NEDO
                        Sig Williams, DERR, NEDO
                        Heidi Sorin, DERR, CO
                        Jeff Hurdley, Legal, CO
                        Peter Whitehouse, DERR, CO
                        Vanessa Steigerwald, DERR, CO
                        Tim Kern, Ohio AGO
 ERA 1613 (rev. 5/96)
     George V. Vttnovfcft. Governor
     Nancy P. HoHstar. U. Governor
     Donald R. Schregaidus. Director

-------
                       RECORD OF DECISION SUMMARY
                           SOURCE CONTROL AREAS
                    FIELDS BROOK SITE, ASHT ABULA OHIO
I.  SITE NAME, LOCATION, AND DESCRIPTION

The Fields Brook Site is located in die city, township, and county of Ashtabula, in
northeastern Ohio, approximately 55 mites east of Cleveland, Ohio (Figure 1). The main
channel of Fields Brook is 3.9 miles in length and begins at Cook Road, just south of the Perm
Central Railroad tracks. From this point, Fields Brook flows northwest to Middle Road, then
west to its confluence with the Ashtahula Rivet. From Cook Road downstream to Stale
Highway 11, Fields Brook flows through an industrialized area. Downstream of State Highway
11 to near its confluence with the Ashtabula River. Fields Brook flows through a residential
area within the city of Ashtabula. Fields Brook empties into the Ashtabula River,
approximately 8,000 feet (ft) upstream from Lake Erie.

The city of Ashtabula, with a population of approximately 23,000, is the only urban area in
the Fields Brook watershed.  The industrial zone of Ashtabula is concentrated around Fields
Brook and contains several chemical industries yd waste disposal sites. This Record of
Decision addresses contamination at six source areas located in the industrial zone of the Fields
Brook watershed.

Sediments of the brook and the Ashtabula River are contaminated with polychlorinated
biphenyls (PCBs), chlorinated benzene compounds, chlorinated solvents, hexachlorobutadiene,
polyaron*rtic hydrocarbons (PAHs), arsenic, and other hazardous substances.  Soils at the
source areas addressed by this Record of Decision are also contaminated with a wide variety of
             although PCBs predominate. Specific contaminants found at each source area
 are discussed in Section IV of this Record of Decision.

 The Fields Brook Site (Site) was placed on the National Priorities List (NPL) for hazardous
 waste sites on September 8, 1983. The site consists of Fields Brook, its tributaries, and any
 surrounding areas which contribute, potentially may contribute, or have contributed to the
 contamination of the brook and its tributaries. The site is a multi-source site and involves
 multiple media, including soil, sediment, groundwater and surface water.

 The U.S. Environmental Protection Agency (U.S. EPA) divided the site into four areas of

-------
concern, three of which have been designated as "operable units" (OUs) associated with the
Fields Brook Supernmd site (See Figure 2).  The Sediment OU (OUfl) involves the cleanup
of contaminated $f^imfnt in Fields Brook and its tributaries.  The Source Control OU (OU#2)
involves die location and cleanup of sources of contamination to Fields Brook to prevent
               nf the hmok, and is the subject of this Record of Decision dnmmmt   Figure
3 shows the location of the source areas in the watershed. The third area, die Ashtabula River
Area of Concern, evaluates die type and amount of contamination in the Ashtabula River, die
effect of contamination on the river sediment", and any risks to human health and die
environment. The Floodplain/Wetiand (FWA) OU (OU#4) involves die cleanup of
contaminated soils and sediments in die FWA which are located within die 100-year floodplain
area surrounding Fields Brook and outside of the channel and skteslope areas of Fields Brook.
 n. SITE HISTORY AND ENFORCEMENT AciivnusS

 The industrial zone of Ashtabula is concentrated around Fields Brook and is comprised of
 several chemical industries and waste disposal sites. Manufacturing has occurred since die
 early 1940's in this area.  Activities ranging from metal-rabrication to production of complex
 chemical products occurred on approximately 18 separate industrial properties, and the
 of industrial activity along Field* Brook and its tributaries resulted in me release of chemical
 contamination to the Fields Brook watershed, particularly the sediments of Fields Brook, the
 FWA soils and sediments, and Ite soils sunoundnig the industries. These media are
 contaminated with PCBs, chlorinated benzene compounds, chlorinated ethenes (solvents).
 hexachlorobutadiene, arsenic, and other organic and inorganic contaminants.

 Between April 1983 and July 1986. a Remedial Investigation/Feasibility Study (RI/FS) was
 conducted on the Fields Brook Sediment OU by the U.S. EPA. The 1986 RI/FS included a
 baseline tinman healm risk assessment which demonstrated human healm risks not only for
 exposure to die brook sediment, but also exposure in die FWA. The U.S. EPA issued a
 Record of Decision (ROD) hi September 1986 detailing a cleanup remedy that U.S. EPA  vith
 the concurrence of Ohio Environmental Protection Agency (OEPA), determined to be
 necessary for die Fields Brook sediments. The 1986 ROD required die excavation, treatment
 and disposal of sediment from Fields Brooi*.  It also recommended that investigations be
 conducted to identify current sources of contamination to die Brook.

 In late 1986. the U.S. EPA began negotiating with a number of Potentially Responsible Parties
 (PRPs) to conduct die source control OU12 RI/FS activities and sediment operable unit design
 activities.  The PRPs are comprised of die companies who are considered die owners and
 operators of die chemical industries and waste disposal sites surrounding Fields Brook. The
 PRPs also include die companies who, by contract, agreement, or other means, either
 accepted, or arranged for transport, disposal or treatment of, hazardous substances within the
 Fields Brook site.

-------
In 1989, the PRPs were issued a Unilateral Order to design a remedy for the Fields Brook
sediments, complete a Remedial Investigation to identify the sources of contamination, and
develop and evaluate cleanup alternatives for the sources of contamination.  From 1992 to
199S, the PRPs evaluated 94 areas of potential contamination within the Fields Brook
watershed to determine whether they were a source of past contamination or could cause future
recontamination once die Brook cleanup is underway. Contamination could be caused by
discharges from pipes, the movement of contaminated soil or sediment during rainstorms, and
subsurface releases to the brook from flowing groundwater.

As a result of this evaluation, the PRPs identified five industrial properties as sources of
contamination to Fields Brook.  The industrial properties include Detrex, Millennium Plant II
TiCM (formerly SCM), ACME. RMI Metals, and Conrail. In addition, several sewer systems
located to the norm and south of Fields Brook were also found to be potential sources of
contamination.  Detailed information about the types and extent of contamination at the source
areas can be found in the Source Control Remedial Investigation (RI) reports.  The final Phase
1 Source Control RI was approved in May of 1997.

In conjunction with die preparation of the Source Control Remedial Investigation report, the
PRPs prepared a Source Control Feasibility Study to identify and evaluate cleanup alternatives.
The Source Control Feasibility Study was finalized in June,  1997.  The report describes the
initial screening of alternatives, the identification of a range of remedial alternatives, and the
detailed analysis of the assembled alternatives for each of the five properties and the sewer
systems.

The Source Control Remedial Investigation and Feasibility Study reports form the basis for
U.S.  EPA's cleanup strategy. These reports have been included in the information repositories
and the Administrative Record.
 m. HIGHLIGHTS OF COMMUNITY PARTICIPATION

 Various public meetings and availability sessions have been held by U.S. EPA in Ashtabula
 between 1984 and the present to discuss the general progress of the ongoing Fields Brook site
 investigations.

 U.S. EPA has provided regular updates of Fields Brook site activities to the Ashtabula River
 Remedial Action Plan (RAP) Advisory Council at the monthly RAP meetings in Ashtabula.

 On May 26-27,  1993, U.S. EPA conducted several availability sessions and a public meeting
 in Ashtabula to update the public regarding activities at the site, including the Source Control
 Operable Unit. After the meeting, U.S. EPA provided the RAP Council and interested citizens
 with a written response to comments and questions raised at the various meetings.

-------
On September 26, 1996, U.S. EPA conducted another public availability session in Ashtabula,
and provided the public with a detailed update regarding the various FWA studies, risk issues
and cleanup alternatives being considered to be conducted. In November 1996, U.S. EPA
provided the public with a written 'question and answer* response to comments and questions
raised at the September meeting.

U.S. EPA issued a Proposed Plan for the Source Control Operable Unit (SCOU) in Jury 1997.
U.S. EPA provided a public comment period on the SCOU Proposed Plan from July 24, 1997
through August 22, 1997, and conducted an evening public meeting on the Source Control
Proposed Plan on July 31, 1997 in Ashtabula. Upon request, the comment period was
extended to September 15,1997. After a follow-up request for more time to submit comments
regarding the Acme property, die comment period was again extended. The comment period
closed on September 22,1997.  All comments were carefully reviewed and considered by the
U.S. EPA prior to ifmFarre of this ROD. U.S. EPA's response to the public comments
received are ymmanTeO in the attached Responsiveness Summary, which is Attachment 1 of
this Record of Decision.  This ROD will become part of the Administrative Record pursuant to
the NCP Section 300.825 (a)(2). The Administrative Record can be found at the site
repository in the local library and at the U1S.  EPA Region V office.  The addresses are, as
follows:

 1)    Ashtabula County District Library
       335 West 44th Street
       Ashtabula. OH

 2)    U.S. Environmental Protection Agency
       Waste Management Division Records  Center,  7th Floor
       77 West Jackson Blvd.
       Chicago, IL
 IV. SUMMARY OF SITE CHARACTERISTICS

 The Fields Brook watershed eu-xunpasses 6.0 sq. mi. All of the industrial facilities addressed
 in this ROD are located to the north of the Perm Central Railroad line that runs east-west
 through the middle of the watershed. The area is located in the Lake Plain physiographic
 province of Ashtabula County. The elevation of the Lake Plain ranges from 620 ft mean sea
 level (MSL) to 660 ft msl.

 In general, the subsurface geology of the Fields Brook watershed consists of three geologic
 formations. In descending order, these formations are: glacial-lacustrine, glacial till, and shale
 bedrock.  Additionally, several feet of miscellaneous soil fill materials were encountered on
 several properties investigated during the Phase 1 of the source control RI.  These fill
 materials are distributed sporadically and the result of several years of industrial activities.

-------
Mote detailed information concerning site characteristics can be found in the SCRI report.

According to information from die Ohio Department of Natural Resources, the groundwater
production potential of the area within die watershed is considered very limited and not
capable of yielding water at rates greater than 3 gallons per minute.  No drinking water wells
are located within the industrialized portion of the watershed. The water supply  for the
Industries and residences in die area is from Lake Erie.

A) Acme Scrap Iron & Metal Company

The Acme properly is located in the southwebt portion of the industrialized area near Fields
Brook.  Structures at the site include former manufacturing plant buildings, loading and
unloading areas, drum storage areas, and an oil retention lagoon.  See Figure 4.

The site is currently operating as a scrap recycling facility. The site was owned by die U.S.
Government in die late 1940's and was later sold to National Carbide Corporation.  Specific
industrial activities by die U.S. Government and National Carbide are not known. However,
die Acme site was operated as a calcium carbide manufacturing plant from 1943 until 1952.
The facility was men vacant until 1974, when Acme purchased the property.

In die past.  Acme dismantled and recycled transformers to recover copper, ahiminum, and
steel for resale as scrap metal. On several occasions, the cutting operation used to dismantle
the transformers would set the residual oil on fire. Oil containing PCBs may have been
released into the environment from me transformers during this process.  A preliminary
assessment of die Acme facility in 1985 identified the chemicals of interest to include PCBs
and several metals, including ahiminum, arsenic, copper, iron, lead, mercury and zinc.

The Recontamination Assessment performed as part of die Fields Brook Source  Control
Remedial Investigation (SCRI) identified several source areas at Acme  as having die potential
to recontaminatc Fields Brook.  This evaluation  is presented in Chapter 6 of die SCRI Report.
Twenty surface soil samples were collected at the facility.  The analytical results showed
contamination at die following locations on die Acme property.

       1.     Drum Storage Area

       The drum storage area covers approximately 1.4 acres. It is located southeast of die
       main structure and includes a small storage building and the property surrounding  the
       building.  The building is used by Acme to store empty drums and drums of grease
       used for equipment maintenance. Surface soil samples collected from inside and
       around the building were found to have concentrations of PCBs ranging  from 2.19
       parts per million (ppm) to 16.9 ppm. The unit of measurement  "parts per million"  (or
       "ppm") is equivalent to the unit of measurement "rag/kg."

-------
      2.      Oil Soaked Sofl

      The Oil Soaked Soil location consists of several areas on the Acme property which
      display surface soil staining. In total, the oil soaked soil covers a combined area of
      approximately 12 acres.  The stained soils generally are found near the scrap processing
      areas.  A number of surface soil samples were collected in these areas and
      concentrations of PCBs range from below die detection limit to 79.5 ppm. For die
      development and analysis of remedial alternatives, the oil  soaked soil areas were
      combined with the transformer processing area.
                                      I
      3.

      The transformer processing area covers a combined area of approximately 12 acres
      where transformers were processed in die area north of the main facility building.  The
      transformers were processed to recover copper wire.  A surface soil sample collected in
      this area was found to have 3.2 ppm PCBs. As noted above, die transformer
      processing area was combined with die oil soaked soil areas for die development and
      analysis of remedial alternatives.  ''

      4.     Other Surf ace SoU Areas

      PCBs were detected in surface soil samples collected during die Phase ISCRI in the
      northwestern portion of uw property.  PCB concentrations range from below die
      detection  limit to 4.1 ppm. No specific sources are associated widi diese areas but they
      are being considered in the remedial alternatives.  These areas cover approximately 4.7
      acres.

      5.     Oil-She Storm Sewers

      U.S. EPA required the PRPs to conduct and present detailed analysis of alternatives for
      the Acme property on-site storm sewers.  The storm sewers are believed to have
      sections that have breaks and are blocked in certain parts  by debris. No information is
      available  about the volume of sediment in the on-site storm sewers.

B) Millennium Plant D, TfCI. Facility

Millennium Plant D, the TiCl« (titanium tetrachloride) facility is  located in die south-central
portion of die industrialized area near Fields Brook.  The structures currently at die site
include several process buildings, a tank farm with numerous aboveground storage tanks
contained entirely within a diked area, and diree settling ponds.  The western half of die
property contains most of die process-related structures, whereas the eastern half remains
largely undeveloped and is covered by a large pile of mining wastes and filter residue.  See
Figure 5.

-------
The TiCl« plant was designed, constructed and initially operated by the Stauffer Chemical
Company.  Construction was completed in 19S8.  The facility was sold to National Distillers
and Chemicals in 1959 and was operated for the next five years by National Distillers (and its
affiliates Mallory-Sharon Metals and RMI Titanium).  Cabot Titania acquired the plant in 1963
and operated it until 1972. when it was leased to Gulf and Western Industries, Inc. Gulf and
Western purchased the plant in 1975.  SCM purchased the TiCl, facility in 1983.

At the commencement of operations, the plant utilized a heat transfer system mat used
Aroclor-based fluids. This system remained in use until Gulf and Western had pure Aroclor
removed from the heat transfer system in 1974 and replaced it with Monsanto PCB-Free
Thenninol.

There have been multiple investigations of contamination at the TiCU facility. A Toxic
Substances Control Act (TSCA) action in 1983 tod to the excavation and disposal of PCB-
contaminated sediment from rainwater trenches (660 ppm) and overflow channels (330 ppm).
In 1990, SCM identified PCB contamination (to 41,000 ppm). This was reported to the
Region V TSCA office.  TSCA required die preparation of a work plan and an investigation to
determine the extent of soil contamination and identify buried drums. This work was
postponed in 1991, to allow coordination with the Fields Brook Source Control Remedial
Investigation.

As pan of the SCRI, the Recontamination Assessment of Millennium identified die Mining
Residuals Pile, die Non-Traffic Area and the Norm Traffic Area as areas that possess the
potential to "-contaminate Fields Brook.  At the consensus of U.S.  EPA and  Millennium,
remedial action is also being planned for other plant areas that have PCB concentrations
greater than the Fields Brook cleanup goal. These additional areas include: the Laydown
Area; the Plant Process Area; and the Existing Soil Piles. It should be noted that these three
plant areas were analyzed by the Recontamination Assessment and were determined not to be
potential sources of ^contamination of Fields Brook. Descriptions of the six plant areas and
analytical results are summarized in the following sections.

        1.     Non-Traffic Area

        Site investigations have identified PCBs in surface soils (approximately the upper 6 ft)
        hi the west-central portion of the facility, extending norm beyond the existing security
        fence-line. The area extending north beyond the fence-line to the 100-year floodplain
        is the Non-Traffic Area. PCB concentrations in surface soils in the Non-Traffic Area
        range from 3.1 ppm to 50  ppm.  However, a few sampling locations  near the old
        outfall were found to have concentrations of PCBs greater man 50 ppm, and some
        borings had soils containing greater than 500 ppm.  At the consensus of U.S. EPA and
        Millennium, Millennhim evaluated the past sampling in comparison with a 50-foot
        sampling grid, with samples collected at 2-foot depth increments. The results of this

-------
additional delineation sampling are undergoing U.S. EPA review.

 2.    North Traffic Area

Site investigations identified PCBs in surface soils (approximately the upper 6 ft) in the
west-central portion of the facility, extending north beyond die existing security fence-
line. The area south of Ihe fence-line and north of the Plant Process Area is defined as
the North Traffic Area.  The surface area in the North Traffic Area is covered with
pavement, structures, or gravel.  The gravel was placed to prevent further contact with
on-site surface soils in this area and to reduce the potential for erosion of the surface
soils.

PCB concentrations in surface soils in die North Traffic Area have generally been
identified in die range of 3.1 ppm to SO ppm. However, a few sampling locations near
an old outfall had concentrations of PCBs greater dian SO ppm and a small area with
PCBs greater than 500 ppm.  At die consensus of U.S. EPA and Millennium,
Millennium evaluated die past sampling in comparison with a 50-foot sampling grid,
 with samples collected at 2-foot depth increments. The results of this additional
delineation sampling are undergoing U.S. EPA review.

 3.      Lay down Area

 The Laydown Area is located """»*«M«*»iy soum of die concrete pad.  The Laydown
 Area consists of bare soils and vegetated soils.  The average PCB concentration in the
 Laydown Area is 3.S ppm, and die maximum concentration is 37.9 ppm (at l.S to 3.0
 ft depth). The Rccontamination Assessment found neither groundwater nor overland
 erosion to be complete pathways for recontamination of Fields Brook. The Laydown
 Area is being addressed in this document at die consensus of U.S. EPA and
 Millennium, not because it has die potential to recontaminate Fields Brook.

 4.     Plant Process Area

 The Plant Process Area is die active, operating portion of die TiQ, facility. The Plant
 Process Area is almost completely covered with either pavement or structures.  PCB
 concentrations in surface soils in die Plant Process Area have generally been identified
 in die range of 3.1 ppm to SO ppm.  However, a few scattered sampling locations have
 identified PCB concentrations greater dun SO ppm and a small area with PCB
 concentrations greater than 500 ppm. The primary area widi elevated PCB
 concentrations is associated with die old Therminol system. At die direction of U.S.
 EPA. Millennium evaluated die past sampling in comparison with a 50-foot sampling
 grid, with samples collected at 2-foot depth increments.  The results of this additional
 delineation sampling are undergoing U.S. EPA review.
                                    8

-------
      5.    Existing SMI Files

      The Existing Soil Piles are located on die concrete storage pad in the east central
      portion of die TiCl* facility.  Standard plant maintenance and upgrades occasionally
      require the excavation of small amounts of soil. These soils are stockpiled on die
      concrete pad. Historic sampling results from die excavation locations indicate that
      some of these soils may contain couLicnUations greater than 50 ppm PCBs. The soil
      piles are being addressed in this document at die consensus of U.S. EPA and
      Millennium; however, die soil piles were not designated as having die potential to
      recontaminate Fields Brook.

      6. Mining Residuals Pile

      The inactive Mining Residuals PUe is located in die eastern portion of the facility
      between Middle Road and Fields Brook.  The pile received •BevuT exempt mining
      residuals (e.g., iron hydroxide) from previous plant operations prior to Millennium's
      operations. As stated in die Bevill exemption, die mining residuals are neither
      hazardous wastes nor hazardous substances.

      Information gathered during the Mining Residuals Pile investigation indicates that the
      material is primarily iron hydroxide, with a tow moisture content (measured at about 25
      to 30 percent, as compared to an approximate field capacity of SO to 60 percent), and a
      (disturbed) density ranging between 1.0 and 1.2S tons per cu yd.  Although die mining
      residuals are not hazardous wastes, sample results revealed that PCBs are present in the
      Mining Residuals Pile at concentrations ranging from non-detect to 760 ppm.

Q  Conrail

ConraiTs Bridge Yard is located north of Fields Brook, east of die  Ashtabula River and west
of a residential area within die City of Ashtabula, Ohio.  Conrail uses this area for marshaling
or staging rail cars containing coal before and after loading and unloading rail cars. Features
in die Bridge Yard area include numerous sets of tracks, a small lift bridge control (or
yardmaster) building, and a small building that formerly housed a compressor. Main access to
die area for vehicles is from die north; however, a light i«uty bridge east of die yardmaster
building makes die property accessible from East 15th Street to die south.  The light duty
bridge is currently closed widt a metal barricade at each end. Trains enter and leave die
Bridge Yard from die south end of die Yard near die confluence of Fields Brook and die
          River.
Only a small portion of die Bridge Yard lies within die Fields Brook watershed. The area of
interest includes a long (approximately 1600 ft), narrow strip of land along Fields Brook from
15th Street to die Ashtabula River.  This area extends from die centerline of die southernmost
set of railroad tracks south to Fields Brook (see Figure 6). Within tiiis area, potential source

-------
areas originally identified in the Phase I SCRI included the aboveground storage tanks located
near the east side of the yanlmaster building, the former compressor building, and soil staining
in the area near the light duty bridge. Surface soil samples collected at the Conrail property
during completion of the SCRI contained arsenic concentrations ranging from 10.4 ppm to 62
ppm. U.S. EPA determined mat based on the close proximity of the Conrail facility to the
Brook, the facility posed a threat to the recormiinmarion of the Brook. Arsenic contaminated
soil located immediately next to the Brook on the Conrail facility may be running off the
property more man soil in the upper watershed and may not become sufficiently diluted with
the cleaner runoff to prevent an exceedance of die arsenic CUG in Fields Brook sediment.

D) Detrex Corporation

The Detrex Corporation is located in the northwestern portion of the Fields Brook watershed
adjacent to the norm bank of the main channel of Fields Brook.  The facility encompasses 58
acres. Structures on the property include a process building, office building, and numerous
aboveground storage tanks mat are either within diked areas, paved areas, or on ground
surfaces.  The northern one-third of the property is used as an active manufacturing area and
the southern two-thirds is largely undeveloped. See Figure 7.

The Detrex facility currently produces pyrrole, n-memyl pyrrole, and hydrochloric acid. The
product of the n-methyl pyrrole and pyrrole reactions are distilled to give n-methyl and pyrrole
as product and non-hazardous still bottoms. Past operations at mis plant included die
chtorination of acetylene to produce trichloroetnene and tetrachloroetfaene.  The chemicals of
interest at Detrex from current operations include furan, monomethyl amine, n-methyl pyrrole
(NMP), pyrrole and ammonia, while the chemicals from past operations included
tricholoroethene, 1,1,2,2-tetrachloroethane, hexachlorobutadiene (HCBD), and
tetrachloroethene.

 Results from sampling conducted during the SCRI indicate mat surface soil exceedances for
CUG compounds were identified in sever*, areas of the Detrex facility. These areas include:
 the stormwater collection ditch on the northern property line, several abandoned retention
 ponds, construction debris piles, sediment in the stormwater settling collection basin, and a
 catalyst pile.  In addition, the results of the Recontamination Assessment and identification  of
 Dense Non-Aqueous Phase Liquid (DNAPL) indicated that the following areas should be
 addressed to reduce possible sources of future contamination to Fields Brook:

        1.    Seven Closed Lagoons

        The closed lagoons are located in the northeastern portion of the Detrex facility.
        Subsurface soil samples collected from the area surrounding the lagoons were found to
        contain several volatile and semi-volatile organic  compounds at concentrations
        exceeding occupational CUGs. DNAPL was identified in the shallow groundwater
        bearing formation both in the closed lagoon area and at off-site locations north of

                                           10

-------
     DET1 on RMI Sodhim property.  A sample of DNAPL was collected from one of the
     on-site monitoring wells in order to characterize mis material. Four volatile organic
     compounds were Menfif*** (1,1.2,2-tetrachloroethane, 1,2-dtchloroethene,
     tetracUoroethene, and trichloroethene). Three semi-volatile organic compounds were
     identified (h^Karhtorrfrrnrenc, ^^yhiQTO^itidifnf and ^^y^|^ftvtrt>aiv>)  Based on
     existing Phase I data and the delineation borings, the DNAPL plume extends in a radial
     pattern from the closed lagoon area and encompasses an estimated subsurface area of
     approximately 500,000 sq. ft. (11.5 acres). Based on data collected to-date, the
     DNAPL plume is migrating toward the northwest, consistent with groundwater flow
     and the structure of the top of the underlying till layer.  The extent of the DNAPL
     plume will be delineated as part of a oesign investigation program to be completed
     prior to completing the final design.

     2.    Sources Within die Surface Water Treatment System

     The surface drainage system in the northern industrialized portion of the Detrex facility
      has been modified to collect and treat surface water. Of the area within die bounds of
      the surface water treatment system, approximately 60.000 sq.ft of surface area has soil
      CUG exceedances. The ponded area in the lagoon area covers approximately 4,000
      sq.ft.  In addition, approximately  1,500 sq.ft. along die drainage ditch has surface soil
      CUG exceedances. The area that is located within die bounds of the surf ace drainage
      system is underlain by the subsurface DNAPL plume

      3.    Sources Outside the Surface Water Collection System

      In the Phase ISCRI Report, die catalyst piles were not considered a potential source of
      sediment recontamination.  A surface soil sample located downslope of the floodplain
      detected a concentration of 40.4 ppm PCBs. Subsequent sampling of die catalyst
      material has indicated the presence of PCBs greater than occupational CUGs for the
      Fields Brook sediment. Additional sampling of the three catalyst piles indicated PCB
      concentrations ranged from 2 to 5 ppm.  Since die catalyst piles are in close proximity
      to Fields Brook, U.S.  EPA requested out die catalyst piles be considered in the FS.

E) Sewers North and South of Fields Brook

      1.     Sewers North of Fields Brook

      Results from the Phase I SCRI indicate dial die sediment in several storm sewers and
      outfall process facility sewers is a potential source for  recontaminau'on of Fields Brook
      sediment. These sewers consist of: die 48-in. diameter combined sewer west of State
      Road; the 5-in. diameter storm sewer west of State Road that discharges into die 48-in.
      diameter combined sewer; and the Detrex facility outfall sewer.  See Figure 8A.
                                         11

-------
      Combined Sewer (48-in. Diameter) - State Road

         Minnies from the 48-in. diameter combined sewer bid concentrations
of berao(a)pyrene and hexachtaobenzene mat ranged from 1.9 ppm to 11 ppm
and 13 ppm to 5,800 pom, respectiveiy.  This sewer is a 48-in. diameter
reinforced concrete combined stocm and facility outfall sewer. The sewer is
approximately 2,400 ft in length and runs along the west side of State Road,
norm of Fields Brook. The sewer accepts surface and facility outfall water,
which at several locations includes bom plant surface water, process water,  and
sanitary effluent.  Oil-site treatment of sanitary waste is handled by all facilities
mat discharge to die sewer.  No untreated effluent water enters the combined
sewer system. The combined sewer collects outfall water from three facilities
(Occidental, UNO Sodium, and Detrex) through three outfalls located along
State Road along with street runoff from a catch basin located at East 6th Street
and State Road. This sewer is estimated to have 4 to 6 in. of hardened calcium
carbonate precipitate in it.  No information is available about die volume of
sediment in mis sewer.  Also, ale exact condition of mis sewer is not known.
The sewer is partially blocked in certain  parts by debris which includes bricks,
wood, sediment, and pieces of concrete.   Approximately 650,000 gallons of
water per day are believed to be discharged into Fields Brook by mis sewer.

b.     Storm Sewer (5-in.  Diameter) - State Road, North of Fields Brook

A sediment sample from this storm sewer had a 5.4 ppm concentration of
benzo(a)pyrene (BAP). The storm sewer is a 5-in. vitrified clay storm water
sewer that is approximately 250 ft in length.  It runs, from the southwest corner
of the intersection of State Road and East 6th Street, south to join the north end
of die 48-in. diameter combined sewer on the west side of State Road, north of
Fields Brook. l.± information is available about the condition of this sewer or
the amount of sediment it contains.

c.     Detrex Facility Outfall Sewer

 A sediment sample was collected from within a manhole on die east side of
 State Road in the northwest comer of the Detrex property. This manhole is
 between the Detrex facility sewer and the 48-in. diameter combined sewer that
 eventually discharges to Fields Brook on the west side of State Road.  The
 sewer transfers water from the Detrex water treatment system to the 48-in
 diameter combined sewer.  The sewer is constructed of PVC and is relatively
 free of sediment. This PVC sewer discharges to the manhole which contains an
 older section of sewer line that crosses under State Road and connects to the 48-
 in. diameter combined  sewer.  The sediment sample was collected from the

                             12

-------
             bottom of die manhole where die sediment accumulates.  Approximately
             500,000 gallons per day of fluids are believed to be discharged through this
             sewer into die 48-in. diameter combined sewer, which eventually discharges
             into Fields Brook.  The sediment sample had concentrations of 1,1,2,2-
             tetrachloroethane, 1,1-dichloroethene, tetracbloroethene, benzo(a)pyrene (BAP),
             hexachlorobenzene, HCBD, hexachloroediane, heptachlor, and gamma-BHC
             (Lindane).

2.     Sewers South of Fields Brook

       Results from die Phase I SCRI indicate that the sediment in several storm sewers and
       outfall process facility sewers located on die south side of Fields Brook is a potential
       «»nr» fir»r nmnt*min»ticm nf Pieid* Bmnlr sediment  TbJS SCWer SVStem COnSlStS Of
       die 36-to 48-inch diameter sewer east of State Road which runs between die Acme
       facility and Fields Brook, as well as die 30-inch outfall sewer that connects die oil
       retention lagoon on die Acme property to die catch basin at die corner of die
       intersection of State Road and Middle Road. See Figure 8B.

       a.     Acme Sewer

              Sediment •••miea collfctffd from die catch basin at die corner of die intersection
              of State Road and Middle Road had 2.0 ppm of total PCBs. The length of
              sewer includes die 30-in. diameter reinforced concrete sewer (total length of
              approximately 300 ft) that connects die oil retention lagoon on die Acme
              property to die catch basin at the corner of die intersection of State Road and
              Middle Road. The sewer also includes die larger (36-in. or 48-in. diameter)
              reinforced concrete sewer (total length of approximately 1,200 ft) that connects
              the catch basin at die intersection of Middle and State Roads to Fields Brook.
              The on-site Acme facility outfall sewers are believed to have sections dial have
              breaks and are blocked in certain parts by debris. No information is available
              about die volume of sediment in die sewers located on die east side of State
              Road.

 F) RMI Metals Reduction

 The RMI Metals Reduction facility is located at die southwest comer of die intersection of
 State Road and East 21* Street. The RMI Metals property is bordered on die north by East
 21" Street, North Coast Auto, and RMI Extrusion facilities, on die east by State Road and die
 Acme facility, on die south by undeveloped property,  and to die west by Reach 10-1 of Fields
 Brook and State Route 10. The facility was used until 1992 to produce pure titanium metal
 (Ti) called Ti  sponge. The facility was closed in 1992.

 The results of die Recontamination Assessment presented in die Phase I SCRI Report indicated

                                          13

-------
that it was not necessary to consider remedial alternatives for any potential source areas located
at the RMI Metals facility in the feasibility study. However, based on discussions with U.S.
EPA after subm!™*1 of the Phase ISCRI Report, it was decided that additional surface soil
sampling should be conducted in the vicinity of the potential source area where one elevated
concentration (6.9 pom) of PCBs was detected in the Phase I SCRI sampling program.  This
potential source area was identified in the Phase 0 SCRI as a demolition debris landfill.  As the
result of two additional sampling and analysis efforts conducted in August and October 199S,
it was mutually decided between the RMI and the U.S. EPA mat additional sampling would be
conducted to refine and more completely delineate die remedial response areas for each
remedial alternative.  In addition to die identification of several PCB residential CUG
exceedances in this vicinity, the area is also'in close proximity to Reach 10-1 of Fields Brook.
In follow-up sampling efforts conducted in August and October 1995, several additional
surface soil samples collected in mis area were found to have concentrations of total PCBs
ranging from 0.9 ppm to 91 .Oppm. See  Figure 9A.

Data presented in the Phase I SOU Report and subsequent sampling performed in 199S for
PCBs has established the current limits of the expected remedial response area. This area is
approximately 3,900 sq. ft.  (0.1 acre) in size. The remedial response area was estimated
using the a cleanup goal of 10.0 ppm for  total PCBs.  RMI is currently conducting additional
delineation sampling.  These results may  alter die limits of die remedial response'area.  During
the remedial design plume for the selected remedy, the data obtained from the RMI sampling
effort, and,  if necessary, additional data win be  reviewed to fully delineate die remedial
response area.
 V. HUMAN HEALTH RISK ASSESSMENT

 Because of the limited scope of the Source Control Operable Unit, a separate risk assessment
 was not prepared for die areas to be addressed as part of this ROD.  Fields Brook and its
 associated floodplain and wetland areas are to be remediated in the Sediment and
 Floodplains/Wetlands Area (FWA) OUs. The goal of the SCOU is to remediate source areas
 that have the potential to cause sediment contamination to Fields Brook and its tributaries,
 thereby preventing the reoontamination of areas that will be addressed by the Sediment and
 FWA OUs. The Source Control action supports the Sediment and FWA remediations by
 helping to ensure that human-health hasgd cleanup goals are maintained.

 The Chemicals of Concern (COCs) for the Source Control OU include the COCs for both the
 Sediment and FWA OUs. Chapter 3 of the SCFS Report discusses the development of the site
 cleanup goals (CUGs).  A complete list of COCs and CUGs for die SCOU is provided in
 Table 1.  These COCs include arsenic, benzo(a)-pyrene, beryllium,  1,1,2,2,-tetrachloroethane,
 tetrachloroethene, trichloroethene, hexachloroethane, vinyl chloride, hexachlorobenzene,
 hexachlorobutadiene. and PCBs. As part of the Recontamination Assessment (Chapter 6 of the
 SCRI), source areas were evaluated to determine the extent that contaminant movement could

                                          14

-------
cause a CUG exceedance in Brook sediment.  Soil loss equations were used to determine the
extent of excavation and/or cover necessary to prevent recontamination of Fields Brook.
Unless otherwise agreed to by a facility, the remediation of source control areas will be limited
to the actions needed to prevent the recontamination of Fields Brook.  The cleanups at the
source areas are not intended to fully remediate the facilities involved.
VI.  ECOLOGICAL RISK ASSESSMENT

Because of the limited scope of the Source Control Operable Unit, a separate ecological risk
assessment was not prepared for the areas to be addressed as part of this ROD. Fields Brook
and its associated floodplain and wetland areas are to be rrmndiatprt in the Sediment and
Floodplains/Wetlands Area (FWA) OUs. The goal of the SCOU is to remediate source areas
that have the potential to cause sediment contamination to Fields Brook and its tributaries,
thereby preventing the recontamination of areas that will be addressed by the Sediment OU and
the FWA OU.

The areas to be addressed under this ROD are industrial properties. Within the Fields Brook
Superfund Site, the areas of most ecological interest and concern are the Brook and its
surrounding Floodplain/Wedand areas.  By preventing the recontamination of the Sediment
and FWA OUs, die remediation of the source control areas will help to ensure that the CUGs
are mainjaingH  Areas disturbed by the implementation of source control remedies will be
restored.
 VOL SCOPE OF THE SELECTED REMEDIES

 The purpose of this Record of Decision (ROD) is to select the final remedial actions for the
 Fields Brook Site Source Control Operable Unit. In general, these final remedies contain or
 remove the contaminated soils from the source areas through a combination of excavating with
 backfilling and landfilling, or covering the contaminated soils. Excavated material containing
 * SO ppm PCBs will be sent either to a TSCA-approved landfill off-site or will be placed in a
 TSCA-approved landfill to be built on one of the industrial facilities within the Fields Brook
 watershed.  The on-site landfill discussed in the alternative description section (Section VIII,
 is to be built pursuant to the ROD for the FWA OU (6730/97) and the Explanation of
 Significant Differences (BSD) for the Sediment Operable Unit (8/15/97).  It will be used to
 house excavated material from the Sediment, FWA and Source Control Operable Units.
 Remediation to be conducted as part of the Source Control Operable Unit will be limited to
 areas that pose a threat of recontamination to the Brook.

 The selected remedies do not include treatment of principle threat wastes in order to reduce
 toxicity, mobility, or volume of the contamination.  As discussed later in mis ROD, treatment
 of soils is not warranted in part because areas of high-level PCB contamination are widely

                                           15

-------
dispersed within areas of overall low average PCB concentrations. The treatment of soils
containing high concentrations of PCBs, such as at die Millennium source area, is not practical
because of the selective excavation and separation of soil that would be required.  Treatment is
not necessary to comply with TSCA and does not provide additional risk reduction relative to
the additional expense. Treatment or recycling of the extracted DNAPL from the Detrex
facility will reduce the toxicity, mobility and volume of contaminants currently found in
groundwater at the source area. Additionally,  treatment is a secondary element in mat leachate
liquids from the disposal of source area soils in the on-site landfill will be collected and treated
resulting in destruction of hazardous substances.
Vm. DESCRIPTION OF ALTERNATIVES

The Source Control FS identified and evaluated alternatives to address the potential for
contaminant movement to Fields Brook. For each source area, the FS evaluated a "No Action"
alternative to serve as a baseline from which to evaluate action alternatives. For some source
areas, the "No Action" alternative includes monitoring; for others, the "No Action" alternative
does not include monitoring.  This is due to the assumptions made by the various contractors
involved in the preparation of die FS.  Both approaches are acceptable and satisfy the NCP's
requirement mat a 'No Action* alternative be considered.

This Record of Decision is complex because the SCOU addresses six source areas. Full
descriptions of all alternatives would be excessively lengthy and further complicate this
document. Therefore, the alternatives presented hi this section of the ROD are summarized.
Full descriptions of the alternatives considered can be found in the Source Control FS. The
selected remedies are fully described in Section X.

A) Acme Scrap  Iron & Metal

U.S. EPA evaluated the following alternatives to address contamination at die Acme facility:

        1.     ALTERNATIVE I:  NO ACTION

              Time To Complete:         Monitoring could be initiated in 2 to 4 months.
              Capital Cost-               $  19.000
              First Year O&M:           $  12.000
              30-Year Present Worth Cost $203,500

        Alternative I would involve only monitoring, and die source areas at die Acme property
        would remain in tiieir present condition. The monitoring would include sampling of
        die outfall discharge to evaluate die amount of contamination moving off of die
        property and into Fields Brook.  This alternative serves as a baseline against which die
        effectiveness of die other alternatives can be compared.  The total. 30-year present

                                          16

-------
worth cost of this alternative is estimated at $203,500.

2.     ALTERNATIVE II:  CONTAINMENT A

       Time To Complete:         6 to 8 months
       Capital Cost:               $  641,500
       First Year O&M:           $    27,100
       30-Year Present Worth Cost $ 1.058.100

Alternative n incudes the construction of a containment berm and surface drainage
controls. The contaminated soil woiild not be moved.  Clay/soil containment berms
would be constructed where needed to control drainage. Berms would be constructed
of clay with a topsoil cover.  The topsoil would be vegetated to provide protection from
erosion.  The berm would be approximately 3 ft in height Vrith a 1.5:1 slope. This
results in a berm approximately 9 ft wide at its base. The top of the berm would be flat
so that the berm could be mowed.

Institutional controls would be  implemented, as appropriate, to protect containment
berms and surface drainage controls. The controls may include deed restrictions,
security fencing, and signs. The total. 30-year present worm cost of Alternative n is
estimated at $1,058.100.  This cost includes monitoring of the outfall discharge and
routine inspection and m«j«*»nMff» of the berms.
 3.    ALTERNATIVE HI: CONTAINMENT B

       Time To Complete:         6 to 8 months
       Capital Cost:              $ 1,578,000
       First Year O&M:           $    19,500
       30-Year Present Worth Cost $1,877,800

 Containment of surface soil would be provided through the installation of a 12-inch
 erosion control cover over the area of contamination. The contaminated soil would not
 be moved.  The erosion control cover would be vegetated to reduce the potential for
 erosion. Areas of regular vehicular traffic would be covered with 6 inches of gravel.
 The area to be covered by the erosion control cover is estimated to be approximately
 480,000 sq. ft. or 11.0 acres.  Of this area,  approximately 120.000 sq. ft.  (2.8 acres)
 would be covered with gravel and 360,000 sq. ft. (8.2 acres) would be covered with
 soil.

 Institutional controls would be implemented, as appropriate, to protect cover systems
 and drainage controls, and may include deed restrictions, security fencing, and signs.
 The total, 30-year present worth cost of Alternative in  is estimated at $1 ,877,800.
 This cost includes monitoring of the outfall discharge and routine inspection and

                                    17

-------
maintenance of die erosion control cover.

4.    ALTERNATIVE IV:  CONSOLIDATION/CONTAINMENT

      Time To Complete:         6 to 8 months
      Capital Cost:              $ 1.560.200
      First Year O&M:           S    19.500
      30-Year Present Worth Cost $ 1.860.000

Alternative IV is similar to Alternative HI except that the soil from the source areas at
the Acme property would be consolidated prior to placement of the erosion control
COVer. ConSOJkhltion fff I*"*!?"*! ""iM TM"ce *** airfare area to ht- covered  Since
the consolidation area would be at die Acme property, no soil would be removed from
the facility. The area to be excavated is approximately 1.2 acres, or 52,170 sq. ft.
This area would be excavated to a depth of 6 inches. The excavated areas would be
filled to grade with clean soil or gravel.  After consolidation, die area to be covered
consists of approximately 7.6 acres or 332.000 sq. ft. Of die area to be covered.
88,400 sq.ft. (1.9 acres) would be covered with gravel, while 245,600 sq. ft.  (5.6
acres) would be covered by a 12-inch soil erosion control cover.  The design and
implementation of die cover would be die same as described for Alternative m.

Institutional controls would be implemented, as appropriate, to protect cover systems
and drainage controls, and may include deed restrictions, security fencing, and signs.
The total, 30-year present worm cost of Alternative IV is estimated at $1.860.000.
This cost includes monitoring of die outfall discharge and routine inspection and
maintenance of die erosion control cover.

5.     ALTERNATIVE V:  EXCAVATION/TREATMENT/DISPOSAL

       Tune To Complete:         10 to 12 months
       Capital Cost:               $3.075.476
       First Year O&M:            $    19.500
       30-Year Present Worth Cost S 3,375.276

 Alternative V has been developed to include excavation of surface soil in die  source
 areas, thermal treatment, and disposal. Soils with PCB concentrations greater man
 500 pom would be excavated. The excavated soils would be diennally treated
 (incinerated) at an off-site facility. Existing data for surface soils at die Acme facility
 indicate that  no PCB concentrations greater than 500 ppm were identified. However.
 Alternative V includes an allowance for excavation, treatment, and disposal of 1.000
 cubic yards of soil. The allowance assumes diat concentrations greater than 500 ppm
 will be identified during sampling activities for die remedial design phase. However.
die excavation, treatment, and disposal would only be performed if future analytical

                                   18

-------
results indicate PCB concentrations greater than 500 ppm.

The remaining areas of surface soil contamination would be contained in place on the
Acme property. The cover system, would be the same as those described in
Alternative ffl. Institutional controls would be implemented, as appropriate, to protect
cover systems and drainage controls.  These controls may include deed restrictions.
security fencing, and signs.  The total, 30-year present worm cost of Alternative V is
estimated at $3,375,276.  This cost includes monitoring of the outfall discharge and
routine inspection and maintenance of the erosion control cover.

6.     ALTERNATIVE VI:  EXCAVATION/CONTAINMENT
       (U.S. EPA's Selected Remedy)

       Time To Complete:         10 to 12 months
       Capital Cost               $ 2,865,076
       First Year OftM:           $    19,500
       30- Year Present Worth Cost $3,164,876
                                ,«
Alternative VI has been developed to include excavation of surface soil with PCB
concentrations greater than or equal to 50 ppm.  Excavation would be conducted to a
depth of approximately 1 foot. The excavatkm to a 1-foot depth would result in an
estimated volume of 1,800 cubic yards. The excavated soils would be disposed at
either an on-she landfill (to be constructed at an industrial facility within die Fields
Brook watershed) or at an off-site TSCA-approved landfill. Following completion of
excavation activities, the excavated areas would be backfilled with clean soil and
graded to allow for adequate drainage.
 The remaining surface soils nyf™*^ in the remedial response area would be contained
 in place with a cover. Alternative VI would include the same cover, surface drainage
 controls, institutional controls, chemical monitoring and maintenance activities as those
 described for Alternatives m and V.  The erosion control cover materials would
 generally consist of a 12-inch thick layer of clean soil, an erosion control blanket and
 would be vegetated to reduce the potential for erosion.  For anticipated future traffic
 areas, a 6-inch gravel layer underlain by geotextile would be used instead of the soil.

 Institutional controls would be implemented to protect cover systems and drainage
 controls.  These controls would include, as appropriate, deed restrictions, security
 fencing, and signs. The total 30-year present worm cost of Alternative VI is estimated
 at $3,164,876. This cost includes monitoring of the outfall discharge and routine
 inspection and maintenance of the cover system.
                                    19

-------
B) Millennium Plant H, TiCl^ Facility

U.S. EPA evaluated die following alternatives to address contamination at the Millennium
facility:

       1.     ALTERNATIVE I:   NO ACTION
             Time To Complete:         	
             Capital Cost:               $       0
             First Year O&M:           S.       0
             30-Year Present Worth Cost'*       0

       Alternative I is a no action alternative, which would allow she conditions to remain as they
       currently exist. This alternative serves as a baseline for comparison with other alternatives
       as required by the NCP. No reduction in the potential of recontamination of Fields Brook
       sediments or reduction in contaminants transport to Fields Brook is associated with this
       alternative.  There is no cost associated with the no action alternative.

       2.    ALTERNATIVE Ifc  DISPOSAL OF HIGHLY-CONTAMINATED SOIL /
                                 EROSION CONTROL CAP COVER OF
                                 REMAINING TSCA SOILS

             Time To Complete:         6 to 8 months
             Capital Cost:              $ 4,018.200
             First Year O&M:           $   81,000
             30-Year Present Worth Cost $5,263.400

       Alternative Q would require the excavation and disposal of highly contaminated soils and
       the consolidation of the remaining TSCA-regulated material. Soils with concentrations
       greater than 500 ppm PCBs would be disposed at an on-site landfill (to be constructed at
       an industrial facility within the Fields Brook watershed) or at an off-she landfill which
       complies with TSCA Soils with between 50 and 500 ppm PCBs would be excavated and
       consolidated at the Mining Residuals Pile located on the Millennium property. A 12-inch
       soil erosion control cover would then be placed on the consolidated pile. Other plant
       areas would receive either sou\ gravel, or paved covers. This alternative would require the
       temporary relocation of Fields Brook.

       Deed restrictions would be established to limit the future use of the site and protect the
       cover system and drainage controls. The existing she fence would be maintained.
       Chemical monitoring of discharges from outfalls would be conducted to evaluate the
       amount of contamination moving from the site to the Fields Brook.  The 30-year present
       worth cost to implement this alternative is estimated at $5,263,400.  This cost includes
       monitoring and routine inspection and maintenance of the cover system.


                                          20

-------
3.    ALTERNATIVE IDA:  DISPOSAL OF HIGHLY-CONTAMINATED SOIL
                            / ALTERNATIVE (VERSION A) RCRA COVER
                           OF REMAINING TSCA SOILS

      Tune To Complete:   •      12 to 16 months
      Capital Cost:               S4.786.SOO
      First Year OftM:           $   81.000
      30-Year Present Worth Cost  $6.031.600

Alternative mA is similar to Alternative n, but includes a modified cover for the
consolidated material.  This alternative includes the excavation of highly contaminated
soils (>500 ppm PCBs) with required disposal in a TSC A-approved fiualrty. This disposal
could be at an on-she landfill (to be constructed at an industrial facility within the Reids
Brook watershed) or at an off-she landfill which complies with TSC A, Soil containing
between 50 ppm and 500 ppm would be consolidated at the Mining Residual Pile which is
located on the Millennium property .  The consolidated area would then be covered with
an alternate RCRA cover. The Version A cover would consists of (from bottom to top):

       12 to 24 inches of consolidation soil;
       20 mil flexible membrane finer (FML) over a geotextile;
       Fabri-Net and infiltration collection;
       12 inches of clean soil; and
 Other plant areas would receive either soil, gravel, or paved covers. This alternative
 would require the temporary relocation of Fields Brook. Deed restrictions would be
 established to Bum the future use of the she and protect the cover system and drainage
 controls. The existing she fence would be maintained. Chemical monitoring of discharges
 from outfalls would be conducted to evaluate the amount of contamination moving from
 the she to the Fields Brook. The 30-year present worth cost to implement this alternative
 is estimated at $6,03  100.  This cost includes monitoring and routine inspection and
 maintenance of the cover system.

 4.    ALTERNATIVE DIB:  DISPOSAL OF HIGHLY-CONTAMINATED SOIL
                             / ALTERNATIVE (VERSION B) RCRA COVER
                            OF REMAINING TSCA SOILS

       Time To Complete:         12 to 16 months
       Capital Cost:              $6,348,900
       First Year O&M:          $   116.000
       30-Year Present Worth Cost $8.132.000

 Alternative DIB is similar to Alternatives O and IDA. Soils with concentrations greater


                                  21

-------
than 500 ppm PCBs would be disposed at an on-she landfill (to be constructed at an
industrial faculty within the Fields Brook watershed) or at an off-site landfill which
complies with TSCA.  Soils containing between SO ppm and 500 ppm would be
consolidated at the Mining Residual Pile located on the Millennium property.  The
consolidated area would then be covered with Version B of an alternate RCRA cover
system. The cover would include (from bottom to top):

*•     consolidation soil;
»     6 inches of dean soil;
*•     40 mil flexible membrane finer (FML) over a geotextile;
»•     Fabri-Net and infiltration collection;
-     24 inches of dean ffi! soil;
*•     6 inches of dean topsofl; and
»•     erosion blanket and vegetation.

Other plant areas would receive either soil, gravel, or paved covers. This alternative
would require the temporary relocation of Fields Brook.  Deed restrictions would be
established to limit the future use of-the site and protect the cover system and drainage
controls. The existing the fence would be mahitamed Chemical monitoring of discharges
from outfalls would be conducted to evaluate the amount of contamination moving from
the she to the Fidda Brook. The 30-year present worth cost to implement this alternative
is estimated at $8,132,000.  This cost includes monitoring and routine inspection and
maintenance of die cover system.

5.     ALTERNATIVE IV:  DISPOSAL OF HIGHLY-CONTAMINATED SOIL /
                            RCRA SUBTITLE C COVER OF REMAINING
                            TSCA SOILS

       Time To Complete:         .18 to 24 months
       Capital Cost:              ' $  8,684,600
       First Year O&M:           $    116,940
       30-Year Present Worth Cost $10,483,000

 Alternative IV is similar to Alternatives ILIIIA, and mB. Alternative IV would require
 that PCB contaminated soils with concentrations greater than 500 ppm would be disposed
 at an on-site landfill (to be constructed at an industrial facility within the Fields Brook
 watershed) or at an off-site landfill which complies with TSCA. Soils containing between
 50 ppm and 500 ppm would be consolidated at the Mining Residual Pile located on the
 Millennium property. The consolidated area would then be covered with a RCRA Subtitle
 C cover system. The Subtitle C cover system would include (from bottom to top):
                                   22

-------
      12 to 24 inches of consolidation soil;
      geocomposhe clay liner, or equivalent;
      40milFML;
      Geonet or Fabri-Net with infiltration collection;
      48 inches of dean soil;
      6 inches of topsoil;
»     an erosion blanket; and
»     vegetation.

Other plant areas would receive either soil, gravel, or paved covers. Because of the
additional area required to accommodate die Subtitle C cover, it would be necessary to
permanently relocate Fields Brook to the northernmost portion of the Millennium
property. In addition, a futty-cncompaiiiOTg shiny wall would be constructed around the
capped area. Groundwater would be influenced using withdrawal weUs to promote flow
around the slurry watt, and leachate from within the shiny wall would be collected and
treated. Deed restrictions would be established to limit the future use of the she and
protect the cover system and drainage controls. The existing site fence would be
maintained. Chemical monitoring of .discharges from outfalls would be conducted to
evaluate the aiwm** of contamination moving from the she to the Fields Brook. The 30-
year present worth cost to implement this alternative is estimated at $10,483,000. This
cost includes monitoring and routine inspection and maintenance of the slurry wall and
cover system.

6.     ALTERNATIVE V:       EXCAVATION AND TREATMENT OF > 500
                                 PPM PCB SOILS

       Time To Complete:         24 to 36 months
       Capital Cost:               $ 8,966,100
       First Year O&M:           $    81,000
       30-Year Present  Worth Cost S 10,211,200
        •
Alternative V is the same as AK Amative II (temporary relocation of Fields Brook,
containment, placement of an erosion control cover, deed restrictions, monitoring and
routine maintenance), except that soils with greater than (>) 500 ppm of PCBs would
be excavated and thermally  treated (incinerated) off-site.  The costs to implement this
alternative are estimated at $10,211,200. This cost includes monitoring and routine
inspection and maintenance of the erosion control cover system.
                                   23

-------
      7.     ALTERNATIVE VI:      EXCAVATION AND LANDFILL OF * 50 PPM
                                      PCB SOILS
            (U.S. EPA's Selected Remedy)

            Time To Complete:        12 to 18 months
            Capital Cost:              $6,846,500
            First Year O&M           $   43,000
            30-Year Present Worth Cost $7,505,500

      Under Alternative VI, soils with greater than or equal to (*) SO ppm of PCBs would be
      excavated and disposed at an en-site landfill (to be constructed at an industrial facility
      within the field* Brook watershed) or at an off-she landfill which complies with TSC A.
      The remaining materials in the Mining Residuals Pile would be covered in-place with an
      erosion control cover (12 inches of dean soil, an erosion blanket, and vegetation), similar
      to Alternative n. Other plant areas would receive either soil, gravel, or paved covers.
      This alternative would not require the  temporary relocation of Fields Brook.
                                     *• •
      Deed restrictions would be established to limit the future use of the she and protect the
      cover system and drainage controls. The existing she fence would be maintained.
      Chemical monitoring of discharges from outfalls wotdd be conducted to evaluate the
      amount of contamination moving from the site to the Fields Brook. The 30-year present
      worth cost to implement this alternative is estimated at $7,505,500. This cost includes
      monitoring and routine inspection and maintenance of the cover system.

Q  Conrail

U.S. EPA evaluated the following  alternatives to address contamination at the Conrail facility:

       1.     ALTERNATIVE I: NO ACTION

             Time To Complete:          	
             Capital Cost:               $  0
             FirstYearO&M:           $  0
             30-Year Present Worth Cost $  0

       The no action alternative would allow site conditions to remain as they currently exist.
       The existing berm on the property would remain in place, as would site vegetation.
       Evaluation of the no action alternative is required by the NCP and provides a baseline
       for comparison with other alternatives.  No capital or O&M costs are associated with
       this alternative.
                                         24

-------
2.    ALTERNATIVE H: CONTAINMENT/FILTRATION BERM

      Time To Complete:         6 to 8 months
      Capital Cost:              $  13,500
      First Year O&M:          $   4.400
      30-Year Present Worth Cost $  81,100

Alternative n consists of construction of surface drainage controls and berms to prevent
surface soils from entering Fields Brook.  Arsenic-contaminated soil would remain in-
place. A gravel filtration berm would be built along the top of the north bank of Fields
Brook to allow for the surface wateolhat might be draining from die property to slowly
pass through die berm to Fields Brook white filtering sediment* that may be carried by
die surface flow. By slowing runoff from the site, tiiis alternative also promotes
infiltration of surface water, thereby reducing runoff and sediment transport to Fields
Brook.  The berm would be constructed along die north bank of Fields Brook from the
Ashtabula River to just beyond die former compressor building, approximately 1,100ft
in total length.  This alternative does not include any action to be taken on die slope of
die norm bank of Fields Brook, which is relatively steep and currently vegetated with
trees and plants.

Access to the site would be restricted by the constructkmof a fence across the entrance
of the limited access bridge. Institutional controls would limit die future use of die site
to protect die berms and drainage controls.  The **#F*P**30-year, net present worm
cost for this alternative is $81,100. This cost includes die monitoring of surface soil
arsenic levels and routine inspection and maintenance of berms and other drainage
control TyiffflfflircSj.

 3.     ALTERNATIVE HI: CONTAINMENT/GRAVEL EROSION CONTROL
                            COVER

       Time To Complete:         6 to 8 ninths
       Capital Cost:              $ 12,000
       First Year O&M:           $ 5,500
       30-Year Present Worth Cost $96,500

 Alternative in consists of covering a portion of die area of the site that is in die
 watershed, and controlling drainage to prevent surface soils from entering Fields
 Brook.  Contaminated soil would remain in-place and would be covered with 6 inches
 of gravel and sloped at a 2 percent grade towards Fields Brook in order to reduce the
 potential for erosion and sediment transport. The gravel covered area, approximately
 60 feet east of die former compressor building and extending to die eastern limits of the
 property adjacent to Fields Brook, would not be covered.  Also, die north bank of
 Fields Brook would not be covered since covering the bank in this manner would not

                                    25

-------
be possible without extensive excavation or installing an engineered slope protection.

A fence would be placed across the entrance of the limited access bridge across Fields
Brook in such a manner as to prevent unauthorized entry,  instjtutio11*! controls would
limit the future use of the site to protect the cover system and drainage controls.  The
estimated 30-yr, net, present worm, total cost for this alternative is $96,500.  This cost
includes the monitoring of surface soil arsenic levels and routine inspection and
maintenance of the gravel cover and other drainage control measures.
                 «
4.     ALTERNATIVE IV: SOIL.EXCAVATION / CONSOLIDATION /
                           CONTAINMENT
       (U.S. EPA's Selected Remedy)

       Time To Complete:         6 to 8 months         4
       Capital Cost:               $  19,500
       First Year O&M:           $   5,500
       30-Year Present Worth Cost $ 104,000

 Alternative IV includes the excavation, consolidation, and containment of surface soils
 in a disposal cell located on the Conrail property. All existing vegetation in the "flat
 area" and along bank slopes to Fields Brook in the areas of interest would be removed.
 The soils would men be excavated to a depth of approximately 6 inches. Excavated
 soils (approximately  90 cu yds) would be moved to a consolidation area at a higher
 elevation along, the bank for final disposal on the Conrail property.  Upon placement of
 excavated soils, this area would be graded and covered with 6 inches of gravel to
 prevent soil erosion.  Erosion control measures would be placed on the bank, where
      sary, to minim,fae erosion.
 A fence, would be placed across die entrance of the limited access bridge across Fields
 Brook in such a manner as to prevent unauthorized entry.  Institutional controls would
 limit the future use of the site to protect the cover system and drainage controls.  The
 estimated 30-year, net present worth, total cost for this alternative is $104,000. This
 cost includes the monitoring of surface scil arsenic levels and routine inspection and
 maintenance of the gravel cover and other drainage control measures.

 5.     ALTERNATIVE V: SOIL EXCAVATION/DISPOSAL

        Time To Complete:          6 to 8 months
        Capital Cost:               $173.100
        First Year O&M:           $       0
        30-Year Present Worth Cost  $173,100

 Alternative V involves the excavation,  transport and landfill disposal of excavated soils.

                                    26

-------
      This alternative consists of removing all existing vegetation from the area to be
      remediated and excavating approximately 6 inches of soil from the area. Excavated
      soils would be transported to the landfill that is to be built at one of the industrial
      facilities within the Fields Brook watershed.
      The «eriprorte^ vohime of soil to be removed in mis alternative is approximately 310 cu
      yds.  The *«»*««••*«• 30-yr, net present worth, total cost for mis alternative is $173,100.
      Because the arsenic contamination would be removed from the area, mis alternative
      would not require deed restrictions, routine maintenance or chemical monitoring.

D) Detrex Corporation

U.S. EPA evaluated the following alternatives to address soil and groundwater contamination
at the Detrex facility:

      1.     ALTERNATIVE I: NO ACTION
                                                   \

             Tune To Complete:       ,  Monitoring could be initiated in 2 to 4 months.
             Capital Cost:               $       0
             FirstYearOftM           $ 21,200
             30-Year Present Worth Cost  $325,900  .

      Alternative I involves performing only long-term monitoring at the Detrex property.
      The groundwater would be monitored to track the DNAPL and contaminant
      concentrations. The stormwater outfall would be sampled to evaluate the amount of
      contamination moving off the property and into Fields Brook.  This alternative is
      required by the NCP for consideration and serves as a baseline against which the
      effectiveness of the other alternatives can be compared. The 30-year present worth
      total cost of mis alternative is estimated at $325,900.

      2.     ALTERNATIVE HA:  CONTAINMENT/ SH \LLOW COLLECTION
                                  TRENCH/ TREATMENT

             Tune To Complete:         Less than 1 year
             Capital Cost:              $ 2,065,602
             First Year O&M.           $   41,300
             30-Year Present Worth Cost $2,700,502

       This alternative would contain the entire DNAPL plume and prevent recontamination of
       the DS Tributary and Fields Brook sediment from either DNAPL or dissolved phase
       DNAPL constituents. A slurry wall would be constructed to cut off DNAPL migration
       towards Fields Brook and the DS Tributary.  The slurry wall would completely encircle
       the DNAPL plume and extend beyond the limits of DNAPL to contain dissolved phase

                                        27

-------
constituents. Shallow dewatering trenches would be installed within the on-site area
encompassed by the shiny wall to maintain a consistent shallow water table elevation
below ground surface and to keep an inward gradient across die shiny wall.  Extracted
groundwater would be treated by Detrex's existing stormwater treatment system that
uses carbon filtration to remove contaminants from collected surface water.

Low-lying areas within the existing collection system area and areas with surface soil
cleanup goal f7Mff*|*iir*'iy would be filled and regraded. These areas would men be
covered iit-place with a 12-inch thick soil layer, an erosion control blanket, and a
vegetative or crushed stone layer surface.'

Routine groundwater monitoring would evaluate the level of DNAPL, VOC and SVOC
contamination.  ID addition, water level data would be collected to evaluate
groundwater flows within the remedial response area.  The stormwater outfall would be
sampled to evaluate the movement of contamination from the site. The existing site
fence would be maintained.  Deed restrictions would be implemented to restrict the
future use of the site to protect the cover system, slurry wall, dewatering trenches,
drainage controls, and monitoring wells. The total 30-year present worth cost of this
alternative is *****i* at $ 2,700,502.  This cost includes the monitoring and routine
inspection and maintenance of the shiny wall, dewatering trenches, cover systems and
Detrex's carbon treatment facility.

3.     ALTERNATIVE OB:  CONTAINMENT / DNAPL COLLECTION
       TRENCH/ TREATMENT

       Time To Complete:         Less than 1 year
       Capital Cost:               $ 5,489.412
       First Year OftM.           $    80,200
       30-Year Present Worth Cost $6.722,312

 Alternative HE varies from Alternative DA in that the trenches would be deeper to
 promote DNAPL collection. Groundwater and DNAPL collection trenches would be
 installed within the slurry wall  area.  The trenches would be located near or at the
 leading edge of the DNAPL plume.  The trenches would be installed to maintain a
 consistent shallow water table elevation below ground surface, to collect and remove
 DNAPL, and to keep an inward groundwater gradient in the area of DNAPL.  The
 trenches would be approximately 25-feet deep and would have a length of
 approximately 2,300 ft. The collection trenches would be equipped with submersible
 pumps that would transfer DNAPL and groundwater to a separation unit.  Extracted
 DNAPL would be treated or recycled at an off-site facility.

 Low-lying areas within the existing collection system area and areas with surface soil
 cleanup goal exceedances would be filled and regraded.  These areas would then be

                                   28

-------
covered in-place with a 12-inch thick soil layer, an erosion control blanket, and a
vegetative or crushed stone layer surface.

Routine groundwater monitoring would evaluate the level of DNAPL, VOC and SVOC
contamination. In addition, water level data would be collected to evaluate
groundwater flows within the t**«*«ifoi response area. The stormwater outfall would be
sampled to evaluate the movement of contamination from the site. The existing site
fence would be maintained.  Deed restrictions would be implemented to restrict the
future use of the site to protect the cover system, shiny wall, dewatering trenches.
drainage controls, and monitoring wells. The total 30-year present worth cost of this
alternative is ?yf««"yft«* at $ 6,722,312. This cost includes the monitoring and routine
inspection and maintenance of the slurry wall, dewatering trenches, cover systems and
Detrex's carbon treatment facility.

4.     ALTERNATIVE ffl: HYDRAULIC CONTAINMENT / DNAPL
                           COLLECTION WELLS / TREATMENT

       Tune To Complete:       - Less than 1 year
       Capital Cost:              $1,615.440
       First Year O&M          $  245.600
       30-Year Present Worth Cost $5,390,940

This alternative would hydraulically contain the DNAPL plume and prevent
recontamination of the DS Tributary and Fields Brook sediment by reversing the
direction of groundwater flow and recovering mobile DNAPL. Vacuum-enhanced
extraction wells would be used to remove DNAPL constituents. Based on a pilot study
conducted in January 1997, it is ^rtin^M that approximately 60 wells would be
installed to collect groundwater and DNAPL.  Extracted groundwater would be treated
by Detrex's existing stormwater treatment system that uses carbon filtration to remove
contaminants from collected surface water.  Extracted DNAPL would be treated or
recycled at an off-site facility.

Low-lying areas within the existing collection system area and areas with surface soil
cleanup goal exceedtnces would be filled and regraded. These areas would then be
 covered in-place with a 12-inch thick soil layer, an erosion control blanket, and a
 vegetative or crushed stone layer surface.

 Routine groundwater monitoring would evaluate die level of DNAPL, VOC and SVOC
 contamination. In addition, water level data would be collected to evaluate
 groundwater flows within the remedial response area. The stormwater outfall would be
 sampled to evaluate the movement of contamination from the site. The existing site
 fence would be maintained.  Deed restrictions would be implemented to restrict the
future use of the site to protect the cover system, drainage controls, and extraction and

                                   29

-------
monitoring wells.  Total 30-year present worth cost of this alternative is estimated at
$5,390,940.  This cost includes the monitoring and routine inspection and maintenance
of extraction wells, dewatering trenches, cover systems and Detrex's carbon treatment
facility.

5.     ALTERNATIVE IV: DOWNGRADIENT CONTAINMENT / DNAPL
       COLLECTION WELLS / TREATMENT
       (U.S. EPA's Selected Remedy)'

       Time To Complete:        Approx. 1 year
       Capital Cost:              '$1,890,776
       First  Year OftM:          $   211,600
       30-Year Present Worth Cost $5,143,576

This alternative is a combination of Alternatives n and m with the exclusion of the on-
site shallow  dewatering trenches included under Alternative 0. The shallow dewatering
trenches would not be required in this alternative because vacuum-enhanced extraction
wells installed inside the shiny wail would lower the water table inside the slurry wall
and reverse  the flow of groundwater away from the shiny wall.  The slurry wall
component would extend beyond the edge of the downgradient portion of die DNAPL
plume to ensure that the DNAPL and contaminated groundwater flowing towards
Fields Brook or the DS Tributary would be contained or captured. The wall is
expected to  be approximately 1,500 feet; however, this length may increase depending
on the results of design investigations. Vacuum-enhanced extraction wells would be
installed near the leading edge of the DNAPL plume near the shiny wall and within the
plume to lower the groundwater table and collect DNAPL. Based on pilot test results,
 approximately 40 extraction wells are anticipated.  Extracted groundwater would be
treated by Detrex's existing stormwater treatment system that uses carbon filtration to
 remove contaminants from collected surface water.  Extracted DNAPL would be
 treated or recycled at an off-site facility.

 Low-lying areas within the existing collection system area and areas with surface soil
 cleanup goal exceedances would be filled and regraded. These areas would then be
 covered in-place with a 12-inch thick soil layer, an erosion control blanket, and a
 vegetative or crushed stone layer surface.

 Routine groundwater monitoring would evaluate the level of DNAPL, VOC and SVOC
 contamination. In addition, water level data would be collected to evaluate
 groundwater flows within the remedial response area. The stormwater outfall would be
 sampled to  evaluate the movement of contamination from the site. The existing site
 fence would be maintained.  Deed restrictions would be implemented  to restrict the
 future use of the site to protect the cover system,  drainage controls, slurry wall, and
 extraction and monitoring wells.  Total 30-year present worth cost of  this alternative is

                                   30

-------
          lated at $5,143,576. This cost includes die monitoring and routine inspection and
      maintenance of the shiny wall, extraction wells, cover systems and Detrcx's carbon
               facility.
E) Sewers North and South of Fields Brook

The U.S. EPA evaluated die following alternatives to address contamination in die north and
south sewers:

       1.     ALTERNATIVE I: NO ACTION
                                      4
       Time To Complete:         - '• -
       Capital Cost:               $0
       first YearO&M:           $0
       30-Year Present Worth Cost $0

       Alternative I is a no action alternative, which would-allow sewer conditions to remain as
       they currently exist. This alternative-serves as a baseline for comparison .with other
       alternatives as required by the NCP. No reduction in the potential of recontammation of
       Fields Brook sediments or reduction in contaminants transported to Fields Brook is
                 "•*» t**** *H**MtJvn  Them ia nft cent aaanriateH with the nft action alternative
       2.     ALTERNATIVE II; SEDIMENT REMOVAL

       Time To Complete:         Less than 4 months
       Capital Cost:               $ 399,900 for sewers north   $ 228,500 for sewers south
       First Year O&M           $       0 for sewers north   $      0 for sewers south
       30-Year Present Worth Cost S  399,900 for sewers north   $ 228,500 for sewers south

       This alternative involves die removal of sediment and debris from inside die sewer lines
       and die associated catch basins to reduce die potential of rcyontamination of die Fields
       Brook sediments. The sewers would continue to be used after remedial activities are
       completed. Sediment removal could be accomplished by cleaning die inside of die
       sewers using manual and mechanical techniques to remove sediment, followed by
       rinsing.  Major blockages may exist ttiat prevent die cleaning equipment from
       traversing die entire line. In this case,  die blockages would need to be manually
       removed or, if necessary, die sewers repaired in order to successfully clean die entire
       line.

       All sediments and debris removed by die sewer cleaning would be staged in stockpile
       areas located near access at one end of die sewer.  Solids collected during the
       dewatering process should be characterized and disposed properly in either an off-site
       landfill or hi the on-site landfill to be built in die Fields Brook watershed.  The type of

                                          31

-------
      off-site landfill (whether solid waste, RCRA, or TSCA) would depend on the chemical
      characteristics of the material. The 30-yr, present worth, total cost of Alternative II is
              at $399,900 for the sewers north of Fields Brook and $228,500 for the
      sewers south of Reids Brook.

      3.    ALTERNATIVE HI: SEDIMENT CONTAINMENT/REMOVAL
            (U.S. EPA's Selected Remedy)

      Time To Complete:  Less than a year
      Capital Cost:               $ 285,700 for sewers north  $ 324,000 for sewers south
      First Year O&M:           $       0 for sewers north  $       0 for sewers south
      30- Year Present Worth Cost  $ 285,700 for sewers north  $ 324,000 for sewers south

      This alternative is similar to Alternative n, except that portions of sewers that are blocked
      and difficult to dean would be dosed off, and the sediment within the sewers contained.
      These containment areas would include a section of the 48-in. diameter combined sewer
      north of Fields Brook and a section of the 30-inch sewer on the Acme site. The sediments
      in these sewer segments would be contained by filling the sewer pipe with a cement grout
      to restrict flow in the sewer and prevent migration of sediments into Fields Brook.

      Replacement sewers would be constructed to divert water from the sections that have
      been dosed and to connect the remaining sections of the sewers that have been cleaned.
      These sewers would continue to be used after remedial activities are completed. The total
      cost of Alternative ffl is estimated at $285.700 for the sewers north of Fidds Brook and
      $324,000 for the sewers  south of Fidds Brook.

F) RMI Metals Reduction

The U.S. EPA evaluated the following alternatives to address contamination at RMI Metals:

      1.     ALTERNATIVE I:  NO ACTION

             Time To Complete:         Monitoring could be implemented in 2 to 4 months
             Capital Cost:               $   1,900
             First Year O&M:           $  2,000
             30-Year Present  Worth Cost $32,600

      Alternative I would involve only monitoring, and the source area at the RMI Metals
      property would remain in its present condition.  As part of this alternative, a section of
      Fidds Brook immediately downgradient of the remedial response area would be
      monitored to assess the extent of contaminant migration from the area.  This alternative
      serves as a basefine against which the effectiveness of the other alternatives can be
      compared.  Because this alternative includes only chemical monitoring, the total, 30-year


                                        32

-------
present worth cost of this alternative is estimated at $32,600.

2.     ALTERNATIVE II: CONTAINMENT

       Tune To Complete:    '     6 to 8 months
       Capital Cost:               $  19,200
       First Year O&M: -          $   6,500
       30-Year Present Worth Cost $ 1 19, 100

Alternative n includes the construction of an erosion control cover and the use of
surface drainage controls to prevent recontamination of Fields Brook sediment.
Contaminated soils would remain in place. The erosion control cover would consist of
a 12-inch thick layer of clean soil, an erosion control blanket and would be vegetated to
reduce erosion and other effects of weather. The existing facility fencing would be
           tn pnwt* ntiaiithfiriw^ gntty tn thft nsffms* area Deed restrictions WOUld
 be established to restrict future uses of die site and protect the cover system and
 drainage controls. The total, 30-year present worth cost of Alternative n is estimated
 at $119,100. This cost includes surface soil monitoring and die routine inspection and
 maintenance of the cover system.

 3.    ALTERNATIVE HI: EXCAVATION/DISPOSAL/CONTAINMENT

       Time To Complete:         10 to 12 months
       Capital Cost:               $ 58,680
       First Year O&M:            $   6,500
       30-Year Present Worth Cost $158,580

 Alternative m has been developed to include partial excavation of surface soil in the
 source area and disposal, and containment The excavation would be limited to surface
 soils with PCB concentrations greater than or equal to 50 ppm. The excavated soils
 would be disposed at either an on-site landfill (to be constructed at an industrial facility
 within the Fields Brook watershed) or at an off-site landfill which complies with TSCA,
 whichever is more cost effective.  The remaining surface soils included in the remedial
 response area (soils with PCB concentrations greater than 10 ppm) would be contained in
 place with a cover consisting of a 12-inch thick layer of clean soil, and an erosion control
 blanket The cover would be vegetated to reduce erosion and other effects of weather.
 The *"*'**'Tifl facility fencing would be maintained to prevent mvnithorfecd entry to the
 response area. Deed restrictions would be established to restrict future uses of the site
 and protect the cover system and drainage controls. The total, 30-year present worth cost
 of Alternative in is estimated at $158,580. This cost includes surface soil monitoring and
 the routine inspection and maintenance of the cover system.
                                    33

-------
     4.     ALTERNATIVE IV: EXCAVATION AND DISPOSAL
            (U.S. EPA's Selected Remedy)

            Tune To Complete:        10 to 12 months
            Capital Cost:              $ 101,530
            First Year O&M:          $      0
            30-Year Present Worth Cost $101,530

      Alternative IV has been developed to include the excavation and disposal of contaminated
      surface soil. The excavated materials would be limited to surface soils withPCB
      concentrations greater than 10 ppm. *The excavation would be backfilled and graded to
      meet existing, surrounding surface contours. The excavated soils would be disposed at
      either an on-she landfill (to be constructed at an industrial facility within the Fields Brook
      watershed) or at an off-site landfill which complies with TSCA, whichever is more cost
      effective. Alternative IV would not require any erosion control cover, surface drainage
      controls, deed restrictions or maintenance activities. The total, 30-year present worth cost
      of Alternative TV is estimated at $101.530.
DC. SUMMARY OF COMPARATIVE EVALUATION OF ALTERNATIVES

The National Contingency Plan (NCP) requires mat the alternatives be evaluated on the basis
of the following nine evaluation criteria: (1) Overall protection of human health and the
environment; (2) Compliance with applicable or relevant and appropriate requirements
(ARARs); (3) Long-term effectiveness and permanence; (4) Reduction of toxicity, mobility, or
volume through treatment; (5) Short-term effectiveness; (6) Implementability; (7) Cost; (8)
State acceptance; and (9) Community acceptance.  This section compares the alternatives for
each of the six source areas with regard to these nine evaluation criteria.

A)  Acme Scrap Iron and Metal

      1.    THRESHOLD CRITERIA: OVERALL PROTECTION OF HUMAN
            HEALTH AND THE ENVIRONMENT AND COMPLIANCE WITH
            APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
            (ARARS):

      Overall  protectiveness for the alternatives associated with the Fields Brook Source
      Control Operable Unit is measured by the protectiveness at preventing recontamination
      of Fields Brook sediment. Alternative I, the No Action Alternative, would result in
      unacceptable risks to human health and the environment under current conditions.  This
      alternative would allow the potential flow of PCBs to Fields Brook.  However, the
      monitoring to be performed as part of Alternative I would provide data regarding the
      protectiveness of this alternative.

                                       34

-------
Alternatives n, ffl, IV, V. VI have been developed to protect human health and the
environment by preventing recontamination of Fields Brook sediment. Soil cover
technologies of up to 12-inch thickness, would be most suitable for areas with relatively
low levels of contamination, and would provide a potentially less protective remedy for
areas with elevated levels of contamination, in part because of the uncertainty
associated with the possible surfacing of chemicals of concern over time.

Alternatives n, m, and IV would leave contaminated soil in place and construct a
cover over the area to reduce runoff and erosion of contaminated material. Alternative
IV would consolidate material before placing the cover to reduce the area requiring
long-term maintenance.  These alternatives would not provide sufficient containment
for soils with elevated levels of PCB contamination (* SO ppm total PCBs) and, thus,
would not comply with TSCA.

Alternative V would excavate all material > 500 ppm for off-site treatment and
disposal. The remaining soils would be covered in place. This alternative would not
properly contain soils with PCB concentrations 2 SO ppm and would therefore not
comply with TSCA.            .•

Alternative VI, die selected alternative, requires excavation and disposal of soils with *
SO ppm PCBs. Remaining contammatrd soils would be contained in place.  This
alternative meets the requirements of TSCA by properly «*!«pn«'"g of TSCA-regulated
contaminated sofls. The cover for the remaining contaminated soils would protect
human health and the environment by reducing the movement of contamination to
Fields Brook.

The ARARs for die remedial actions considered for the Acme source area are indicated
in Table 2.

2.    PRIMARY BALANCING CRITERIA: LONG-TERM EFFECTIVENESS
       AND PERMANENCE; REDUCTION OF TOXICITY, MOBILITY AND
       VOLUME THROUGH TREATMENT; SHORT-TERM EFFECTIVENESS;
       IMPLEMENTABILITY; AND COST.

 All action alternatives would exhibit long-term effectiveness and perm
 characteristics, as long as they were maintained.  Soil cover technologies of up
 to 12-inch thrJmrats would be most suitable for areas with relatively low levels
 of contamination, and would provide a potentially less protective, long-term
 effective and permanent remedy for areas with elevated levels of contamination,
 in part because of the uncertainty associated with the possible surfacing of
 chemicals of concern over time. All alternatives require O&M.

 Implementation of Alternative V would result in the reduction of toxkity, mobility, and

                                  35

-------
volume of contaminants in soil with PCB concentrations greater than 500 ppm.
'Treatment is a secondary element in Alternative VI in that landfill leachate liquids
would be collected and treated resulting in destruction of hazardous substances.  Thus,
if contaminated i"Biidff teach from the landfilled materials, ftics* liquids would be
collected and treated.  Alternative IV includes consolidation of source areas which
would result in the reduction of the area! extent of source areas requiring long-term
management. The excavated areas in Alternative V and VI would also reduce long-term
management requirements. None of the alternatives except Alternative V include
treatment of principle threat wastes in order to reduce toxkity, mobility, or volume of
the contamination. Principle threat wastes generally include wastes with concentrations
greater man a 1CT* cancer risk at a site, and there are no principle threat  concentrations
of contaminants mriioittil in any location on the Acme properly with greater than a 10"*
cancer risk. The soils to be contained in place have a low average concentration of
between 10-40 ppm total PCBs. and the soils to be excavated under alternatives V and
VI have a low average concentration of between 50-70 ppm total PCBs. Thus,  for
these reasons treatment would not be required.

No significant short-term problems 'are expected during construction or soon after
construction of Alternatives D dirough VI.  Alternatives n, and m, are  effective in the
short-term because they involve minimal disturbance to the source areas. The
excavation and consolidation portions of Alternative IV and the excavation and  disposal
portions of Alternative V and VI present risk of paiticulate emission, thereby creating
exposure pathways to workers and community residents.  Standard dust control
methods would be required during remedial action to reduce mis risk. Alternatives II
through VI also impact the property operations in the short-term. All alternatives,
except for Alternative I, will require worker protection during remediation.
Implementation of Alternative I is expected to take 2 to 4 months.  Alternatives n
through IV are expected to take 6 to 8 months to implement. Implementation of
Alternatives V and VI are estimated to take about 10 to 12 months. The alternatives
may require coordination with the schedule for the construction of the en-site landfill.

 No significant implementability problems which would prevent construction of the
 remedy are expected during construction or soon after construction of Alternatives II
 through VI. Alternative I would be the easiest to implement since only monitoring
 would be included.  Alternatives n  dirough VI include construction of a containment
 berm or soil/clay cover. Construction of the berm or cover would  have material
 handling requirements. The materials, services, equipment,  and specialists required for
 the construction are readily available. The equipment and specialists required for the
 excavation portion of Alternatives IV, V, and VI  also are readily available. The berm
 and cover could be expanded or enlarged easily, if needed. Periodic inspection and
 maintenance of the berm or cover would provide  reliability in the future.

 Implementation of Alternatives n through VI would interfere with the normal

                                    36

-------
     operations at the Acme facility. Alternatives IV, V, and VI would cause the most
     interference with facility operations due to soil excavation.

     The estimated cost for each alternative is divided into capital costs and annual O&M
     costs.  The total cost for each alternative is then compute using an annual interest rate
     of 5% for a period of 30 years. The costs presented in this document are expected to
     range within +50% and -30% in accordance with the U.S. EPA guidance. Alternative
     V is the most expensive remedial alternatives, followed in order by Alternative VI, ffl,
     IV. Alternative H, and Alternative I.

     3.    MODIFYING CRTTERIAi'STATE AGENCY ACCEPTANCE;
           COMMUNITY ACCEPTANCE.

     The State of Ohio did not concur with the remedies selected for the Floodplain/Wetland
     and Sediment Operable Units of the Fields Brook site.  Because the Source Control
     Operable Unit supports the remedies selected for the Floodplain/Wetland and Sediment
     Operable Units, the OEPA has provided notice of its nonconcurrence with the remedies
     selected in this Record of Decision:'

     U.S. EPA provided a public comment period on the Source Control Proposed Plan and
     conducted a public meeting on the Source Control Proposed Plan on July 31.1997 in
     Ashtabula. The public comment period was originally scheduled from July 24 to
     August 22,1997. The public comment period was extended to September IS, 1997 in
     response to a request from the public. After a follow-up request for more time to
     submit comments regarding the Acme property, the comment period was again
     extended.  The comment period closed on September 22, 1997.

     U.S. EPA received one oral comment at the public meeting in support of U.S. EPA's
     proposed cleanups.  Eleven written sets of comment were received during the comment
     period, including comments from natural resource trustees, PRPs and their agents, and
     concerned citizens.  All comments were carefully reviewed and considered by U.S.
     EPA prior to finalization of this Record of Decision.  U.S. EPA's response to the
      public comments received are summarized in the attached Responsiveness Summary,
      which is Attachment 1 of this Record of Decision.

B) Millennium Plant H, TiCl, Facility

      1)    THRESHOLD CRITERIA: OVERALL PROTECTION OF HUMAN
            HEALTH AND THE ENVIRONMENT AND COMPLIANCE WITH
            APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
            (ARARS):

      Overall protectiveness for the alternatives associated with the Fields Brook Source

                                       37

-------
Control Operable Unit is measured by the protectiveness at preventing recontamination
of Fields Brook wdinK** All alternatives, except for the no action alternative, would
be protective of human health and the environment by preventing the recontamination
of Fields Brook •*A\m***l and also by preventing direct exposures to elevated levels of
soil contamination.  O&M will be an integral part of any selected alternative in order to
ensure long-term protection of hi"***" health and the environment. Alternatives nt
OLA, and V may not be protective because they include either a cover alternative
involving 12 inches of soil cover, or a 12-inch soil cover with a liner over the total
PCB contaminated materials between 50-500 ppm.  These alternatives may result in
unacceptable risks to hitmana in the event ***•*• the higher concentration contaminants
potentially reach the cover surfaces over time and release to Fields Brook.  Alternatives
ITIB and IV would be more protective than Alternatives n and IDA, because these
alternatives offer thicker covers (i.e.. Alternative IHB involves use of a 30-inch soil
cover with a geomembrane liner, and Alternative IV involves the use of a 48-inch soil
cover with a geomembrane liner).

Alternatives n, mA and V are expected to comply with all ARARs and TBC
recommendations, except that Alternatives n, mA and V would not provide an
equivalent level of protection as a disposal which complies with TSCA 761.60 and
761.75. Although U.S. EPA has the option to waive TSCA requirements if there is
•no unreasonable risk" to human health and the environment, the U.S. EPA does not
believe that a 12-inch soil cover would provide sufficient protection over the long term
for the levels of PCB contamination in the Millennium soils. Alternative mB is also
expected to comply with all ARARs and TBC recommendations, except that Alternative
IIIB would require a waiver under TSCA for the implementation of the specified cover
system. Alternative IV is expected to comply with all ARARs and TBC
recommendations, including TSCA.  The Region V TSCA office has determined that.
in general, the combination of a Subtitle C cover system and a fully encompassing
slurry wall could meet the disposal requirements of TSCA.  Alternative VI would offer
an equivalent lev•.•'• of protection as disposal that complies with TSCA 761.60 and
761.75.  Consolidation does not trigger any additional ARARs.

The ARARs for the remedial actions considered for the Millennium source area are
 indicated in Table 2.

 2)     PRIMARY BALANCING CRITERIA: LONG-TERM EFFECTIVENESS
       AND PERMANENCE; REDUCTION OF TOXICITY, MOBILITY AND
       VOLUME THROUGH TREATMENT; SHORT-TERM EFFECTIVENESS;
       IMPLEMENTABILITY; AND COST.

 An alternatives, except for the no action alternative, would be effective in the long-term
 and would be permanent, as long as they are maintained. However, Alternatives II, IIIA,
 and V involve the use of a 12-inch thick soil cover which would provide a potentially less

                                   38

-------
long-term effective and permanent remedy than alternatives ITJB, IV, and VI, because of
the uncertainty ym^Btf** with the possible sur&cing of chemicals of concern over time
from the areas with elevated levels of PCB contamination.

Alternatives n, mA, IHB, and IV all should have long-term effectiveness and permanence,
but each leaves in place a largo volume of contaminated material. Alternative V requires
off-site thermal treatment of soils with greater than 500 ppm, but u otherwise comparable
to Aherrotivenmk»g-tenne£fe(^rveneM and permanence.  Alternative VI provides the
best long term effectiveness and permanence in terms of preventing recontamination of
Fields Brook, because higher concentration PCB materials are removed from the site.

Alternatives n, mA, fflB, and IV do not reduce toxicity, mobility , or vohime throu^j
treatment.  Alternative V reduces the toxicity, mobility, and volume of hazardous
           in i imnn ipwtfry nf •"** (2,1
-------
the time necessary for implementatioa
Alternative I would be the easiest to implement because no action is required. Alternative
n is relatively easy to implement and can be installed in a short time frame. Alternatives
niA, IDS, and IV win be more difficult to implement due to the complexity of the cover
system components. Also, Alternative IV may be difficult to implement because the
Mining RipukhmH Pfle is not conducive to excessive grading, compaction, or the added
weight of a 7-foot thick cap, and may be thus subject to liquefaction.  Alternative V would
be more difficult to implement due to scheduling and the time and personnel commitment
for excavation, transportation, and treatment. Alternative VI may be more difficult to
implement than Alternative n, becausdt although it involves the installation of a relatively
simple cover system, it also requires a time and personnel commitment for excavation,
transportation, and landfilling. AD alternatives other than no action may encounter
difficulties during implementation due to the dose proximity of contaminated soils to the
floodplain and Fields Brook, the relatively steep northern slope between the Mining
Residuals Pile and Fields Brook, and due to the ongoing business operations at the  facility.
In addition, construction activities for Alternatives n through VI may cause dust to be
released to the atmosphere, thereby..creating exposure pathways to workers and
community residents. Standard dust control methods would be required during
remedial action to reduce mis risk. Alternatives n through V also impact the property
operations in die short-term. All alternatives, except for Alternative I, will require
worker protection during remediatkm;

       The costs to implement the alternatives are:
ALTERNATIVE
I
n
IIIA
DIB
IV
V
. VI
30-YEAR PRESENT
WORTH COST
$0
$5,263.400
$6.031.600
$8.132.000
$10.483.000
$10.211.200
S7.S05.500
 Alternatives n through VI will all prevent recontamination of Fields Brook by preventing
 erosion of soils containing PCBs above the CUG.  Alternatives IDA, HIE, and IV are
 more expensive due to engineered barriers to prevent infiltration. Alternative V is more
 expensive than Alternative n (to which it is substantivdy similar), because highly-
                                    40

-------
     contaminated soils (> 500 ppm PCBs) would be thermally treated instead of being placed
     in a landfill. Alternative VI is more expensive than Alternatives n and fflA, yet less
     expensive than Alternatives IJJB, IV, and V. Alternative VI provides the greatest benefit
     for the cost, as materials greater than SO ppm would be excavated from the site and
     disposed at an on-she or off-site landfill which complies with TSCA.

     3)    MODIFYING CRITERIA: STATE AGENCY ACCEPTANCE;
           COMMUNITY ACCEPTANCE.

     The State of Ohio did not concur with the remedies selected for the Floodplain/Wetland
     and Sediment Operable Units of the Fields Brook site. Because the Source Control
     Operable Unit supports die rcntffffcy selected for the Floodplain/Wetland and Sediment
     Operable Units, die OEPA has provided notice of its wnconcurrence with the remedies
     selected in this Record of Decision.

     U.S. EPA provided a public comment period on die Source Control Proposed Plan and
     conducted a public meeting on die Source Control Proposed Plan on July 31, 1997 in
     Ashtabula.  The public comment period was originally scheduled from July 24 to
     August 22, 1997. The public comment period was extended to September IS, 1997 in
     response to a request from die public. After a follow-up request for more time to
     submit comments regarding die Acme property, die comment period was again
     extended.  The comment period closed on September 22, 1997.

     U.S. EPA received one oral comment at die public meeting in support of U.S. EPA's
     proposed cleanups.   Eleven written sets of comments were received during die
     comment period, including comments from natural resource trustees, PRPs and their
     agents, and concerned citizens. All comments were carefully reviewed and considered
     by U.S. EPA prior to finalization of tiiis Record of Decision. U.S. EPA's response to
     die public comments received are summarized in die attached Responsiveness
      Summary, which is Attachment 1 of this Record of Decision.
QConrail
      1)    THRESHOLD CRITERIA: OVERALL PROTECTION OF HUMAN
            HEALTH AND THE ENVIRONMENT AND COMPLIANCE WITH
            APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
            (ARARS):

      Overall protectiveness for die alternatives associated with die Fields Brook Source
      Control Operable Unit is measured by die protectiveness at preventing recontamination
      of Fields Brook sediment. Alternatives I, II, and III may not be protective of human
      health and the environment because they do not include removal or containment of arsenic
      contaminated soils along die north bank of Fields Brook. Such removal would prevent

                                      41

-------
releases of elevated concentrations of arsenic within surface soils above the CUGs to the
Brook. Alternatives IV andV would be protective because they would prevent releases of
elevated concentrations of arsenic within surface soils above the CUGs to the Brook.

Alternatives n, in, IV and V are expected to comply with site ARARs andTBC
recommendations. ARARs are not relevant for Alternative I, the no action alternative.
The ARARs for the remedial actions considered for the Conrail source area are
indicated in Table 2.

2)    PRIMARY BALANCING CRITERIA:  LONG-TERM EFFECTIVENESS
      AND PERMANENCE; REDUCTION OF TOXKTTY, MOBILITY AND
      VOLUME THROUGH TREATMENT; SHORT-TERM EFFECTIVENESS;
      IMPLEMENTABILrrY; AND COST.

Alternatives I, D, and m may not be permanent or long term effective because they do
not include removal or containment of arsenic contaminated s»ii» along the north bank
of Fields Brook which would prevent releases of elevated concentrations 'of arsenic
within surface soils above the CUGs to the Brook.  Alternatives IV and V would be
permanent and long term effective because tiiey would prevent releases of elevated
concentrations of arsenic within surface soils above the CUGs to die Brook.

Alternatives I, n, and m may reduce short term effectiveness because they do not
include removal or containment of arsenic contaminated soils along die norm bank of
Fields Brook which would prevent releases of elevated concentrations of arsenic within
surface soils above the CUGs to die Brook.  Alternatives IV and V may enhance short
term effectiveness because they would prevent releases of elevated concentrations of
arsenic within surface soils above the CUGs to the Brook. Construction activities for
Alternatives n through V may cause dust to be released to die atmosphere, thereby
creating exposure pathways to workers and community residents. Standard dust control
methods would be required during remedial action to reduce this risk.  Alternatives  n
through V also impact die property operations in the short-term. All alternatives,
 except for Alternative I, will require worker protection during remediation. In
 addition. Alternative V  also will be less effective in the short-term since it is dependent
 upon the construction of the Sediment/FWA Landfill and therefore has a longer
 imptemfntfitHm tune.

 Alternative I requires no implementation because no action is required (i.e., maintain
 existing conditions).  The implementation of Alternatives D and HI involves the
 construction and maintenance of surface drainage controls, gravel covers, and erosion
 control, measures mat are simple and well-known.  Alternatives IV and V are the most
 difficult to implement due to die destruction of vegetation and wildlife habitat, soil
 excavation and handlii^g activities, the proximity of work areas to moving trains and
 the need for sedimentation control during construction.

                                  42

-------
     Alternative I, the no action alternative, would not involve any costs. Alternatives n
     and in have estimated 30-yr, net present worth, total costs of $81,100 and $96,500,
     respectively. Both of these alternatives include the implementation of surface soil,
     erosion and storm water drainage control measures to prevent soil transport to Fields
     Brook.  Annual O&M cost for Alternative m is approximately one-half the estimated
     remedial costs.

     3)    MODIFYING CRITERIA: STATE AGENCY ACCEPTANCE;
           COMMUNITY ACCEPTANCE.
                                  /
     The State of Ohio did not concur with the  remedies selected for the Floodplain/Wetiand
     and Sediment Operable Units of the Fields Brook site. Because the Source Control
     Operable Unit supports the remedies selected for the Floodplain/Wetiand and Sediment
     Operable Units, the OEPA has provided notice of its nonconcurrence with die remedies
     selected in mis Record of Decision.

     U.S. EPA provided a public comment period on the Source Control Proposed Plan and
     conducted a public meeting on the Source  Control Proposed Plan on July 31, 1997 in
     Ashtabula. The public comment period was originally scheduled from July 24 to
     August 22,1997. The public comment period was extended to September 15,1997 in
     response to a request from the public. After a follow-up request for more time to
     submit comments regarding the Acme property,  the comment period was again
     extended. The comment period closed on September 22.1997.

     U.S. EPA received one oral comment at the public meeting in support of U.S. EPA's
     proposed cleanups. Eleven written sets of comments were received during the
     comment period, including comments from natural resource trustees, PRPs and their
     agents, and concerned citizens. All comments were carefully reviewed and considered
     by U.S. EPA prior to finalization of this Record of Decision. U.S. EPA's response to
     the public comments received are summarized in the attached Responsiveness
     Summary, which is Attachment 1 of this Record of Decision.

D) Detrex Corporation

     1)    THRESHOLD CRITERIA:  OVERALL PROTECTION OF HUMAN
           HEALTH AND THE ENVHtONMENT AND COMPLIANCE WITH
           APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
           (ARARS):

     Overall protectiveness for the alternatives associated with the Fields Brook Source
     Control Operable Unit is measured by the protectiveness at preventing recontamination
     of Fields Brook sediment. The no action  alternative (Alternative I) will not reduce the

                                      43

-------
existing potential for migration of DNAPL compounds to Fields Brook. Alternatives
HA, IIB, m, and IV provide good overall protection of Fields Brook through physical,
hydraulic, or combined physical and hydraulic containment and removal. Alternatives
TJB and IV provide die highest expected degree of protectiveness because the DNAPL
plume would be bom contained and collected/treated.

Compliance with location and action-specific ARARs would be met for each of the four
alternatives.  No action-specific ARARs were identified for the no action alternative
(Alternative I). USEPA's TBC guidance indicates mat long-term remediation
objectives of DNAPL remedies should be to remove free-phase, residual and vapor
phase DNAPL "to the extent practicable'. Since Alternatives I and n do not involve
DNAPL removal, they do not meet this TBC.  The ARARs for me remedial actions
considered for the Detrex source area are indicated in Table 2.

2)     PRIMARY BALANCING CRITERIA: LONG-TERM EFFECTIVENESS
       AND PERMANENCE; REDUCTION OF TOHCTTY, MOBILITY AND
       VOLUME THROUGH TREATMENT; SHORT-TERM EFFECTIVENESS;
       IMPLEMENTABELITY; AND COST.

Residual risks to Fields Brook sediment would remain for each alternative. The no
action alternative (Alternative I) would not change die existing risk to Fields Brook
sediment.  The shiny wall included in Alternatives HA and DB would effectively
contain DNAPL sources on die Detrex property and at off-site locations. However, die
DNAPL zone would remain in the subsurface as a residual risk.  Alternatives OB, D3,
and IV would reduce the amount of DNAPL in the subsurface, but this partial
reduction may not produce a significant reduction in risk especially if all DNAPL is not
removed from die low permeability clay soils.  The combination of physical (slurry
wall) and hydraulic containment/DNAPL collection and treatment (trenches or
extraction wells) hi Alternatives nB and TV provides die highest expected'reduction of
off-site migration.

 No controls to prevent recontamination of Fields Brook sediment would be provided
under Alternative I. The slurry wall, shallow and deep extraction trenches, and
 regrading of low-lying areas (Alternatives HA and IIB) are adequate and reliable
controls in the long term and require low maintenance. Vacuum-enhanced extraction
 wells (Alternatives m and IV) are effective and reliable, and they would require
 long-term O&M. Maintenance requirements for the groundwater/DNAPL extraction
 systems would be moderate. Uncertainties associated with the effectiveness of
 extraction wells in low-permeability glacial clays would be evaluated through the
 long-term monitoring program. Complete removal of DNAPL in low permeability clay
 soils is not possible with currently available technology and treatment to asymptotic
 levels is expected.
                                  44

-------
The long-term groundwater monitoring program would be implemented with each of
the alternatives (including no action) to monitor the effectiveness of each alternative. A
performance review would be required for each alternative to evaluate the effectiveness
of die alternative in ffp****^ die goal of preventing recontamination of Fields Brook
sediment and to evaluate the need for continued remediation (i.e. extraction and
treatment under Alternatives OB, in and IV).

All alternatives, except for die no action alternative, either reduce the mobility of
DNAPL compounds or reduce the toxteity and volume of contaminants. Alternative I,
die no action alternative, does not include treatment; therefore, die toxicity, mobility,
and volume of DNAPL in die subsurface are not reduced. DNAPL would be treated
and destroyed under Alternatives OB, in and IV. However, more DNAPL removal is
anticipated with the more aggressive vacuum-rnhanml groundwater/DNAPL removal
systems (Alternative m and IV). All DNAPL that would be separated  from
groundwater would be destroyed by treatment or recycling.  Dissolved-phase and
vapor-phase DNAPL constituents would be adsorbed onto activated carbon and would
be destroyed during carbon regeneration. The amount of DNAPL compounds tiiat
could be removed over time under. Alternatives HA, OB, HI, and IV is uncertain.

The activated  carbon processes proposed for treatment of extracted groundwater and
DNAPL compounds for Alternatives HA, OB m, and IV are irreversible.  Treatment
or recycling of liquid DNAPL and DNAPL compounds from extracted soil vapor under
Alternatives HE, m and IV is also irreversible.

Residuals remaining after on-site treatment of groundwater and DNAPL under
Alternatives HA, HE, m, and IV would include spent activated carbon for Alternatives
HA, UB, m, and IV and separated DNAPL for Alternatives UB, m and IV. Smaller
quantities of these residuals would be expected for Alternative HA than for. Alternatives
 HB, m and IV. The extraction systems under Alternatives  OB, m and IV would
 extract DNAPL compounds from the entire DNAPL zone.  Residual DNAPL would be
 destroyed off site by treatment or recycling, while DNAPL compounds adsorbed onto
 the spent carbon would be destroyed during off-site regeneration.  DNAPL compounds
 from die soil vapor would be destroyed by treatment or recycling under Alternatives m
 and IV.

 Alternatives DB, m and IV satisfy die preference for treatment of principle direat
 contaminants (i.e., the DNAPL) that could potentially recontaminate Fields Brook
 sediment  Alternative n (slurry wall) does not satisfy die preference for treatment of
 principle threat contaminants; however, treatment is provided for as a secondary
 element in that contaminated groundwater collected in die trench would result in
 destruction of h^yarrfmi^ substances.

 Alternative I poses no additional short-term risks to the community. Alternatives HA.

                                   45

-------
OB, m and IV pose slightly increased risks to the community by off-site disposal of
sediment, catalyst pile area excavations and DNAPL treatment  Alternative m would
require disposal of the smallest volume of soil compared to Alternatives HA, DB, m,
and IV. For Alternative I, worker protection would be required only by workers
performing groundwater sampling activities.  Appropriate protective equipment would
be required by construction workers to wEjnhnfoe exposure to DNAPL constituents
during construction of the remedial process options under Alternatives HA, HE, m,
and IV. Appropriate worker protection would also be required during O&M activities
of the dual-phase wells and treatment system under Alternatives DA, HE, m and IV.
                               «
Short-term environmental impacts would be the same as existing environmental impacts
for the no action alternative. Short-term environmental impacts associated with
disposal of excavated soil and possible air emissions from die excavations would be
possible under Alternatives HA, HE, m. and IV. Standard dust control methods would
be required during remedial action to reduce die risk from paiticulates.  VOC
monitoring would be required during remedial action to ensure  worker safety.

The design and construction period for the remedial process options included under
Alternatives HA, HE, m, and IV would be about 1 to 2 years.  Protection from
recontaminatkm would be achieved when die systems are installed.

The technologies included under Alternatives HA, HE, m, and IV are demonstrated
technologies tiat have been constructed at similar sites.  There  will be difficulties
associated wim constructing die shiny wall in Alternatives IIA, HE, and IV beneath the
Conrail railroad tracks north of die facility without interrupting rail service.  There are
 no expected difficulties or uncertainties associated with construction of die vacuum-
 enhanced extraction well system in Alternatives m and IV.  Recent pilot-scale tests
 completed at die site have evaluated die feasibility and effectiveness of die technology
 in extracting DNAPL and groundwater.  Based on these preliminary tests, die
 technology is feasible, although yields will be  relatively low.

 A groundwater monitoring program would be  implemented under each alternative
 (including die no action alternative) to monitor die effectiveness of the remedial action.
 Additional extraction wells or trenches can be added to any of die alternatives if the
 monitoring program suggests that additional remedial measures are required to protect
 Fields  Brook sediment.

 No regulatory agency approvals would be required for Alternative I. The requirements
 of die existing NPDES permit would have to be met to account for increased flow rates
 from die extraction trenches and wells for Alternatives HA, DB, m. and IV.  Air
 discharge permit requirements for soil vapor emissions from die extraction wells would
 be met for Alternatives III and IV.
                                    46

-------
     Services and capabilities to implement each of the Detrex alternatives are readily
     available.  Alternatives n and IIB would not require special equipment, material, or
     specialists. Alternatives in and IV would require groundwater and soil vapor
     extraction system operators.  The technologies proposed for Alternatives HA, ITJB, HI,
     and IV are available from more than one bidder for competitive bidding.

     The estimated cost fat each Detrex alternative is divided into capital costs and annual
     O&M costs. The total present worm cost for each alternative is then computed using
     an annual interest rate of 5% for a period of 30 years. The feasibility study costs are
     expected to be accurate to within +50% and -30%  in accordance with the U.S. EPA
     guidance. The present worm of Alternative IIB is the most expensive remedial
     alternative, followed in order by Alternative ffl, Alternative IV, Alternative HA, and
     Alternative I (no action).

     3)    MODIFYING CRITERIA: STATE AGENCY ACCEPTANCE;
            COMMUNITY ACCEPTANCE.

     The State of Ohio did not concur with the remedies selected for the Floodplain/Wetland
     and Sediment Operable Units of the Fields Brook site. Because the Source Control
     Operable Unit supports the remedies selected for the Floodplain/WetUnd and Sediment
     Operable Units, the OEPA has provided notice of its nonconcunence with the remedies
     selected in this Record of Decision.

     U.S. EPA provided a public comment period on the Source Control Proposed Plan and
     conducted a public meeting on the Source Control Proposed Plan on July 31, 1997 in
     Ashtabula. The public comment period was originally scheduled from July 24 to
     August 22,1997. The public comment period was extended to September IS,  1997 in
      response to a request from the public.  After a follow-up request for more time to
      submit comments regarding the Acme property, the comment period was again
      extended. The comment period closed on September 22, 1997.

      U.S. EPA received one oral comment at the public meeting in support of U.S. EPA's
      proposed cleanups.   Eleven written sets of comments were received during the
      comment period, including comments from natural resource trustees, PRPs and their
      agents, and concerned citizens.  All comments were carefully reviewed and considered
      by U.S. EPA prior to finalization of this  Record of Decision. U.S. EPA's response to
      the public comments received are gimmariygd in the attached Responsiveness
      Summary, which is Attachment 1 of this  Record of Decision.

E) Sewers to the North and South of Fields Brook

      1)    THRESHOLD CRITERIA: OVERALL PROTECTION OF HUMAN
            HEALTH AND THE ENVIRONMENT AND COMPLIANCE WITH

                                        47

-------
      APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
      (ARARS):

Overall protectiveness for the alternatives associated with the Fields Brook Source
Control Operable Unit is measured by the protectiveness at preventing recontamination
of Fields Brook sediment.  Alternatives 0 and m would be protective of the
            Bom alternatives would prevent recontamination of Fields Brook
            xtiment removal is the primary activity under Alternative n, while
Alternative m includes sediment containment in addition to removal.

Compliance with ARARs would be met for Alternatives n and m. Action-specific
ARARs are not relevant to the no action alternative (Alternative I) because there would
be no remedial actitn. Alternatives n and m would be protective of the environment.
TVtfh afrgrmtrvffft wffliM rrcvynf ffc^nfrmimtMM1 ftf FH«fc Prwfr n^1"n^ntff  Sediment
removal is the primary activity under Alternative n, white Alternative ffl includes
sediment containment in addition to removal.

Compliance with ARARs would be met for Alternatives n and m. Action-specific
ARARs are oat relevant to the no action alternative (Alternative I) because there would
be no remedial action. The ARARs for the remedial actions considered for the sewer
source areas are mdiratrd in Table 2.

2)    PRIMARY BALANCING CRITERIA: LONG-TERM EFFECTIVENESS
      AND PERMANENCE; REDUCTION OF TOXICITY, MOBILITY AND
      VOLUME THROUGH TREATMENT; SHORT-TERM EFFECTIVENESS;
      IMPLEMENTABIUTY; AND COST.

Alternative n provides the highest degree of long-term effectiveness and
because mis alternative includes sediment removal and would eliminate the potential of
COC migration to impact on Fields Brook sediments.  The existing contaminated
sediment is the result of historical accumulation.  Remediation of the potential source
areas discussed in mis FS for the Detrex Site is expected to eliminate significant future
accumulation of contaminated sediment. Alternative in would have lower long-term
effectiveness and permanence because it would leave some of the sediments contained
in the sewer, however this alternative would eliminate the potential for discharge water
tO COme hi mntart urith pn»vimi«ly gftnnn^jn*^ porffoq of fljf SfWT that fOnPMIW*
.sediment.  Alternative m requires very little maintenance.

Alternative I would not result in any reduction of toxicity. mobility, or volume of
COCs. Implementation of Alternatives n and HI would result in the reduction of
toxicity, mobility, and volume through treatment of contaminants that are present in
any wastewater generated during sewer cleaning.

-------
Alternative I does not add additional risk to the existing risk to the community.
Alternatives U and m present slight additional risk to workers from the construction
activities necessary to clean, close and/or replace sewers.  Emission controls on die
wastewater treatment unit fat Alternatives n and in would reduce risk associated with
vapor emisskm.  Risks to the community would be marginally increased by off-site
disposal of contaminated sediments and control of dust generated by construction
activities. Standard dust control methods would be requited diiriiig remedial action to
reducetfae risks from particulates.

Implementation of Alternative n is expected to take less than 4 months, while
implementation of Alternative HI is expected to be completed in less than 1 year.  It is
anticipated that Alternative m will require the additional time for the installation of
            sewer sections.
 Alternative I would be the easiest to implement since no action would be taken.
 Alternative n *iwhHtff sewer sediment removal and sewer cleaning which may be
 difficult to implement. There could be added difficulties associated with sediment
 removal due to possible blockage of the sewer.  Alternative m includes grouting a
 portion of die sewer hi addition to fflffaffffitt removal.  Grouting is a demonstrated
 technology that his been applied at other sites and can be readily implemented.
 Disposing contanimated sediments and treating of wastewater can also be readily
 The rsHmatfd costs for Alternatives n and m were computed based on the assumption
 that all sewers are one-quarter full of sediments at the present time.  Calculation of the
 estimated total quantity of sediments in the north sewers mdifatfd mat approximately
 320 cu yd of sediments may be present in the combined sewer.  Calculation of the
 assumed total quantity of sediments in the south sewers inrtiratnd that approximately
 180 cu yd of «**i«niCT!ff may be present. The costs were divided into capital costs and
 annual O&M costs. The total for each alternative is men computed using a discount
 rate of 5% for a period of 30 years. F  • the Sewers norm of Fields Brook, the cost of
 Alternative n is higher than the cost for Alternative m.  For the Sewers south of Fields
 Brook, the cost of Alternative in is higher than the cost for Alternative EL

 3)     MODIFYING CRITERIA: STATE AGENCY ACCEPTANCE;
        COMMUNITY ACCEPTANCE.

 The State of Ohio did not concur with the remedies selected for the Floodplain/WeUand
 and Sediment Operable Units of the Fields Brook site.  Because the Source Control
 Operable Unit supports the remedies selected for the FloodplauVWetland and Sediment
 Operable Units, the OEPA has provided notice of its nonconcurrence with the remedies
 selected in this Record of Decision.
                                    49

-------
     U.S. EPA provided a publk comment period on the Source Control Proposed Plan and
     conducted a public meeting on the Source Control Proposed Plan on July 31,1997 in
     Ashtabula. The public comment period was originally scheduled from Jury 24 to
     August 22,1997. The public comment period was extended to Septenrttet IS, 1997 in
     response to a request from the public.  After a follow-up request for more time to
     submit comments regarding die Acme property, the comment period was again
     extended. The comment period closed on September 22,1997.

     U.S. EPA received one oral comment at the public meeting in support of U.S. EPA's
     proposed cleanups.  Eleven written sets of comments were received dining the
     comment period, including comments from natural resource trustees, PRPs and their
     agents, wd concerned citizens.  All comments were carefully reviewed and considered
     by U.S. EPA prior to finalization of this Record of Decision. U.S. EPA's response to
     the public enmmantt received are summarized in the attached Responsiveness
     Summary, which is Attachment 1 of this Record of Decision.

F) RMI Metals Reduction

      1)    THRESHOLD CRITERIA: OVERALL PROTECTION OF HUMAN
            HEALTH AND THE ENVIRONMENT AND COMPLIANCE WTTH
            APPLICABLE OR RELEVANT AND APPROPRIATE REQUIREMENTS
            (ARARS):

      Overall protectiveness for the alternatives associated with the Fields Brook Source
      Control Operable Unit is measured by die protectiveness at preventing reoontaminarion
      of Fields Brook sediment  Alternatives I and n may be potentially less protective than
      Alternatives m and IV, because areas with elevated levels of PCB contamination would
      be uncovered or covered with up to 12 inch of soil. Such a cover is most*uitable for
      areas with relatively low levels of contamination, and would provide a potentially less
      protective remedy for areas with elevated levels of contamination, in part because of
      the uncertainty associated with the possible surfacing of chemicals of concern over
      time.

      There are no known location-specific ARARs that apply to the remedial alternatives
      that have been developed for the RMI Metals facility.  Alternatives m and IV have
      been designed to meet all potential action-specific ARARs. Alternative n would not
      meet the substantive requirements of TSCA, and thus mis alternative would not comply
      with ARARs.  Although U.S. EPA has die option to waive TSCA requirements if there
      is "no unreasonable risk" to human health and the environment, the U.S. EPA does not
      believe that a  12-inch soil cover would provide sufficient protection over the long term
      for the levels of PCB contamination in the RMI soils.  The ARARs for the remedial
      actions considered  for the RMI Metals source area are indicated in Table 2.
                                       SO

-------
2)    PRIMARY BALANCING CRITERIA: LONG-TERM EFFECTIVENESS
      AND PERMANENCE; REDUCTION OF TOXICTTY, MOBILITY AND
      VOLUME THROUGH TREATMENT; SHORT-TERM EFFECTIVENESS;
      IMPLEMENT ABILITY; AND COST.

Alternatives I and H may be potentially less permanent and long-term effective than
Alternatives in and IV, because areas with elevated levels of PCB contamination would
be uncovered or covered with up to 12 inch of soil.  Such a cover is most suitable for
areas with relatively low levels of contamination, and would provide a potentially less
permanent and long-term effective remedy for areas with elevated levels of
contamination, in part because of the Jmcertainty associated with the possible surfacing
of chemicals of concern over time.

Alternatives I, n, in and IV would not result in any reduction of toxicity, mobility, or
volume of COCs through treatment.  However, implementation of Alternatives n, EQ
and IV would result in the reduction of transportability of contaminants in soil with
Alternative ffl rBBiHing in a further reduction in soil with PCB concentrations greater
than 50 ppm,  and Alternative IV resulting in the complete reduction of PCB greater
man 10 ppm in soil.

Alternative n is effective in the short-term became it involves minimal disturbance to
the source areas.  The excavation and disposal portions of Alternatives HI and IV
present risk of paniculate emission, thereby creating exposure pathways to workers and
community residents. Standard dust control methods would be required during
remedial action to reduce this risk. All alternatives, except for Alternative I,  will
require worker projection during remediation.

Implementation of Alternative I is expected to take 2 to 4 months.  Alternative n is
expected to take 6 to 8 months to implement.  Implementation of Alternatives m and
IV is estimated to take about 10 to 12 months but excavation activities would  need to
be scheduled to coincide with the construction of t * on-site consolidation area, if this
consolidation area is selected for disposal.

 Alternative I would be the easiest to implement since only monitoring would be
 included. Alternatives n and HI include construction of a soil/clay cover.
 Construction of the cover would have material handling requirements. The materials,
 services, equipment, and specialists required for the construction are readily available.
 The equipment and specialists required for the excavation portion of Alternatives m
 and IV are also readily available.  The cover could be expanded or enlarged easily, if
 needed.  Periodic inspection and maintenance of the cover would provide reliability in
 the.future.

 Implementation of Alternatives n, m and IV would interfere with the normal

                                  51

-------
operations at the RMI facility, however this disruption is minimtMH if the facility
remains closed.  Alternatives JO and IV would cause the most interference with facility
operations due to soil excavation.
The t**m9**4 cost for each alternative is divided into capital costs and annual O&M
costs. The total cost for each alternative is then computed using an annual interest rate
of 5% for a period of 30 years. The costs presented in this document are expected to
range within -1-50% and -30% in accordance with the U.S. EPA guidance. Alternative
m is the most expensive remedial alternative, followed in order by Alternative IV,
Alternative n, and Alternative I.

3)    MODIFYING CRITERIA: STATE AGENCY ACCEPTANCE;
      COMMUNITY ACCEPTANCE.

The  State of Ohio did not concur with the remedies selected for the Floodplain/Wetland
and Sediment Operable Units of the Fields Brook site.  Because the Source Control
Operable Unit supports the remedies selected for the Floodplain/Wetland and Sediment
Operable Units, the OEPA has provided notice of its nonconcurrence with the remedies
selected in this Record of Decision.

U.S. EPA provided a public comment period on the Source Control Proposed Plan and
conducted t public meeting on the Source Control Proposed Plan on Jury 31, 1997 in
AshtabuUi. The public comment period was originally scheduled from July 24 to
August 22, 1997.  The public comment period was extended to September IS, 1997 in
response to a request from the public. After a follow-up request for more time to
submit comments regarding the Acme property, the comment period was again
extended. The comment period closed on September 22,  1997.

U.S. EPA received one oral comment at the public meeting  in support of U.S. EPA's
proposed cleanups.  Eleven written sets of comments were received during the
comment period, including comments from natural resource trustees, PRPs and their
agents, and concerned citizens. All comments were carefully reviewed and considered
by U.S. EPA prior to finalization'of mis Record of Decision.  U.S. EPA's response to
the public comments received are summarized in the attached Responsiveness
Summary, which is Attachment 1 of mis Record of Decision.
                                  52

-------
X. THE SELECTED REMEDIES

A)  Detailed Requirements of Hie Selected Remedies

       1)    Aone Scrap Iron and Metal

       The selected remedy is Alternative VI, which involves the excavation of soil with PCB
       concentrations greater than or equal to 50 pom. Excavated soil will be disposed of at
       either an on-site landfill (to be built on one of the source areas) or at an off-site
       landfill, whichever is more cost-effective. Remaining contamination will be contained
       on site.  This remedy will reduce the volume of contaminants at the site and comply
       with TSCA by property handling of TSCA-regulated soils.

       More specifically. Alternative VI includes the following components:

              a)     Clear Scrap, Debris and Vegetation / Remove Physical Hazards

              In order to «np<«re"t the Remedial Action, scrap, debris and vegetation must
              be cleared in response and work areas.  Physical hazards (i.e., unstable building
              sections) mat could threaten workers must also be addressed prior to Remedial
              Action.

              b)    Excavation of Soils with Total PCB Concentrations * 50 ppm

              This ROD requires excavation of soils with total PCB concentrations greater
              than or equal to SO ppm.  Based on existing data, it appears mat limiting
              excavations to a depth of approximately 1 foot should remove all TSCA-
              regulated soil.  However, mis remedy requires removal of all TSCA-regulated
              soils (*  SO ppm PCBs), regardless of depth. Therefore, if areas of additional
              contamination are identified, the excavation depth will be adjusted accordingly.
              During the remedial design phase, additional samples will be collected to further
              delineate the design remedial response area and ensure that the PCB
              contamination is not present on other areas of the Acme property.

              The *«ritnatffl remedial response area for Alternative VI is shown in Figure 4.
              The excavation area was developed based on linear interpolation between
              existing data points and covers approximately 47,000 square feet. Excavation in
              this area would be conducted to a depth of approximately 1 foot.  The
              excavation to a depth of 1 foot would result in an estimated volume of 1,800
              cubic yards.

              The excavation of surface soils in Alternative VI would be accomplished using
              conventional earth-moving equipment.  Upon excavation, the soil would be

                                           53

-------
placed in lined roll-off containers or dump trucks for transportation to either the
SOU/FWA on-site landfill or to an off-site landfill.  Verification sampling may
be required to ensure removal of TSCA-regulated soils. Following completion
of excavation activities, the excavated areas would be backfilled with clean soil
and graded to allow for adequate drainage. Any disturbed areas not receiving
an erosion control cover will be graded and seeded,  as necessary.

Areas of excavation and locations of the filled/ covered areas are preliminary
and will be revised in the event that the Acme property is selected as the
location for the on-site landfill (SOU/FWA Consolidation Area).

c)     Refinement of Area to Be Covered

As part of the Remedial Design, soil loss calculations will be reviewed to
finalize the area to be covered. The cover areas have been developed based on
current operations and include the proposed excavation area since  it is located
within the cover interior. The areas may be altered during Remedial Design if
assumptions on future operations are revised and/or the Remedial  Design
includes consolidation.

d)    Optional Consolidation

Based on public comment from representatives from Acme Scrap  Iron and
 Metal, the U.S. EPA has determined that it will allow consolidation as an
 optional component of Alternative VI. Consolidation will minimize the area to
be covered and maximize the productivity of the properly.  Depending on the
 degree of consolidation, mis could either result in a cost savings or an increase
 in remediation costs.

 e)     Construction of Cover, Surface Drainage Controls

 For the cover areas, the erosion control cover materials will consist of a 12-inch
 thick layer of clean soil, an erosion control blanket and will be vegetated to
 reduce die potential for erosion.  For anticipated future traffic areas, a 6-in.
 gravel layer underlain by geotextile will be used instead of the soil.

 As estimated during the Feasibility Study, the erosion control cover for
 Alternative  VI consists of approximately  120,000 sq. ft.  (2.8 acres) that will  be
 covered with gravel and 360,000 sq. ft.  (8.2 acres) that will be covered with
 soil.

 The location of the erosion control cover (as described in the SCFS) would
 preclude use of the existing on-site sewer. Therefore, if the cleanup at the

                              54

-------
      Acme facility is implemented as described in the SCFS, the existing sewer
      system would be plugged prior to the installation of the erosion control cover
      and other drainage controls would be implemented. However, if the design of
      the Acme remedy utilizes consolidation, it may be possible mat the existing
      sewer system could be cleaned and kept in service. This will be addressed
                     Design.
      I)     infl*itiitJMiai Controls* Chemical monitoring and O&M

      Institutional controls will be implemented for any area where hazardous
      substances, pollutants or contaminants will remain above levels that allow for
      unlimited use and unrestricted exposure. More specifically, institutional
      controls will be implemented to protect the cover system and drainage controls
      and will include deed restrictions, security fencing, and signs. The Operations
      and Maintenance Plan portion of the Remedial Design will specify maintenance
      and monitoring requirements. The performance of the selected alternative will
      be reviewed and evaluated every five years after initiation of the remedial action
      to assure that human health .and the environment are being protected.
             Points of Compli

      In conjunction with completion of die Remedial Action and performance of
      required O&M. erosion and runoff from the Acme facility must meet the
      occupational Cleanup Goals (CUGs) established for the FWA and Sediment
      Operable Units. The occupational CUG for total PCBs is 3.1 ppm.  At a
                the points of compliance are the property boundary and any
      discharge locations.  Additional performance monitoring locations may be
      identified during remedial design.

2)    MJUennium

The selected remedy is Alternative VI. which involves the excavation of soil with PCB
concentrations greater man or equal to SO ppm. Excavated soil will be disposed of at
either an on-site landfill (to be built on one of the source areas) or at an off-site .
landfill, whichever is more cost-effective.  Remaining contamination will be contained
on site.  This remedy will reduce die volume of contaminants at the site and comply
with TSCA by properly handling TSCA-regulated soils.

More specifically. Alternative VI requires:

      a)     Clear Debris and Vegetation / Remove Physical Hazards

      In order to implement the Remedial Action, debris and vegetation must be

                                  55

-------
cleared in response and work areas.  Any physical hazards that could threaten
workers must afcn be addressed prior to Remedial Action.

b)    Excavation of Soils with Total PCB Concentrations * SO ppm

This ROD requires excavation of soils with total PCB concentrations greater
man or equal to SO ppm. The estimated remedial response area for Alternative
VI is shown in Figure S. Based on data presented in the FS, volume estimates
for excavation are, as follows:

       Non-Traffic Area -   approximately 545 cubic yards of soil with 2 50
       ppmPCBs.

       Norm Traffic Area • approximately 3,427 cubic yards of soil with * 50
       ppmPCBs.

       Laydown Area - no anticipated soils  with * 50 ppm PCBs.

       Plant Process Area - approximately 1,003 cubic yards of soil with * 50
       ppm PCBs.

       Existing Soil Piles -Soil piles will be removed regardless  of PCB
               irton, Contaminant concentrations will determine ultimate
       disposal location.

       Mining Residuals Piles - approximately 11,163 cubic yards of soil with
       * 50 ppm PCBs.

•Following completion of excavation activities, excavated areas will be backfilled
 with clean soil and graded to allow for adequate drainage. In the Mining
 Residuals Pile, however, excavated areas will not be backfilled. These areas
 will instead be graded to lessen the overall height of the pile. Any disturbed
 areas not receiving an erosion control cover will be graded and seeded, as
       uy.
 Upon excavation, the soil would be placed in lined roll-off containers or dump
 trucks for transportation to the SOU/FWA on-site landfill or an off-site TSCA-
 compliant landfill. Millennium has provided U.S. EPA with the specifications
 of a landfill currently being constructed under a Ohio EPA permit for disposal
 of Millennium process wastes. The specifications are being reviewed by the
 U.S. EPA Region V TSCA Section. If the landfill is given an approval by the
 TSCA section, disposal of source control soils in mis facility would be an
 acceptable option for solid wastes or TSCA-regulated wastes.

                             56

-------
c)     Refinement of Excavation and Coyer Areas

Millennhim has conducted additional delineation sampling to better define
excavation areas. U.S. EPA is currently reviewing a draft report submitted by
           and dated August 4, 1997. This draft report presents the results of
die delineation sampling effort ?"d is included in die Administrative Record.
As part of the Remedial Design, excavation and cover areas will be finalized
and stability analyses will be conducted. The remedial action areas presented in
the FS and ttus ROD may be altered during Remedial Design based on new
sampling data, changes in the assumptions concerning future operations, or the
addition of consolidation as a component of the remedy.  After excavation, all
areas With surface soil contaminant concentrations exceeding die occupational
CUG for PCBs (3. 1 ppm) will be contained within the erosion control cover
system.

d)    Optional Consolidation

Based on public comment from representatives from Acme Scrap Iron and
Metal, the U.S. EPA has determined mat it will allow consolidation as an
optional component of the Acme cleanup.  Upon consideration of the
Millennium alternatives, U.S. EPA has determined mat consolidation could also
be inryw u an optional component of the selected Millennium alternative,
 Alternative VI. Consolidation will minimize die area to be covered and
 maximise the productivity of die property.  Depending on die degree of
 consolidation, this could either result in a cost savings or an increase in
 remediation costs.

 e)     Construction of Cover, Surface Drainage Controls

 For the cover areas, the erosion control cover materials will consist of a 12-inch
 thick layer of clean soil, an erosion control blanket and will be vegetated to
 reduce the potential for erosion.  For anticipated future traffic areas, a 6-in.
 gravel layer underlain by geotextile will be used instead of the soil. The
 selected alternative, as presented in die FS, assumes the following cover
 requirements after excavation:

        Norm Traffic Area  -  Areas not already covered with gravel, structures,
        or non-erodible areas, will be covered with a geotextile and then 6
        inches of gravel.

        LaydownArea - The Laydown Area will be covered with a geotextile
        and then 6 inches of gravel.
                              57

-------
      Plant Process Area - The Plant Process Area will be covered with
      structural-grade asphalt or concrete, as necessary.  Areas currently
      covered with asphalt, concrete, or structures and will be left in place.

      Existing Soil Piles - No cover anticipated.  Soil piles will be removed.
      Mining B**MH«I« Pile  - After excavation of soils for disposal
      regradmg of area, a 12-inch soil erosion control cover will be placed
      over the Mining Residuals Pile. An erosion control blanket and a
      vegetative layer will then be placed on top of the 12 inches of soil.
      Instead of a vegetative layer, crushed stone may be used in some areas to
f)      Surface Drainage Controls

A silt curtain will be placed between the Mining Residuals Pile and Fields Brook to
minimize erosion. Topography will be graded as necessary to control run-on to
the Mining Residual Pile. However, because the plant areas wifl all be covered
with dean materials, it wffl be unnecessary to treat surface water in the wastewater
treatments system or by any other method. Sheet flow runoff from these areas will
be adequate. AD surface water controls win be maintained.

g)     Miscellaneous Requirements

A concrete curb or wall would be placed between the concrete pad and the Mining
Residuals Pile to prevent accidental damage to the erosion control cover from
facility vehicles.

h)     Institutional Controls, Chemical Monitoring and O&M

Institutional controls will be implemented for any area where hazardous
substances, pollutants or contaminants will remain above levels that allow for
unlimited use and unrestricted exposure.  More specifically, institutional
controls will be implemented to protect the cover system and drainage controls.
Such institutional controls will include deed  restrictions, security  fencing, and
signs. The Operations and Maintenance Plan portion of the Remedial Design
will specify maintenance and monitoring requirements.

O&M activities would include the maintenance of the soil erosion control cover,
the stormwater drainage ways, and the vegetated areas (if any). Chemical
monitoring requirements would include the annual collection of total PCB surface
soil and groundwater samples.
                              58

-------
      The performance of the selected alternative will be reviewed and evaluated
      every five years after initiation of the remedial action to assure that human
      health and the environment are being protected.

      0     Points off Compliance

      In conjunction with completion of the Remedial Action and performance of
      required O&M, erosion and runoff from the Millennium facility must meet the
      Cleanup Goals (CUGs) established for the FWA and Sediment Operable Units.
      The extent and integrity of the cover must be maintained to contain soil that
      exceeds occupational CUGs. 'At a mmimufn, the points of compliance are the
      property boundary, discharge locations, and the edge of the floodplain.
      Additional performance monitoring locations may be identified during remedial
      design.

3)    Conrafl

The primary selected remedy for the Conrail property is Alternative IV, which requires
consolidation, containment of surface soils in an on-stte disposal cell, institutional controls,
deed restrictions, isolation of the site from unauthorized entry, and O&M to prevent
surface soils from entering Fields Brook.  U.S. EPA believes that Alternative IV will
effectively prevent the movement of arsenic-contaminated material into Fields Brook.

The selected remedy for the Conrail property (Alternative IV) requires the following
activities:

       a)     Clear Debris and Vegetation / Remove Physical Hazards

       In order to implement the Remedial Action, debris and vegetation must be
       cleared in response and work areas, including but not  limited to the "flat area"
       and along bank slopes to Fields Brook.  Any physical hazards that could threaten
       workers must also be addressed prior to Remedial Action.

       b)     Excavation and Consolidation of Anente-contaminated Soils

       The soils on the arsenic-contaminated portion of the north slope of Fields Brook
       will be excavated to a depth of approximately 6-inches.  The excavation area
       includes the eastern edge of the yardmaster building to approximately 375 ft east
       of the yardmaster building and from approximately SO ft west of the former
       compressor building to approximately 60 ft east of the former compressor
       building, approximately 485 ft in total length.  The excavated soils (estimated
       volume of approximately 90 cu yds) will be transported to the consolidation area
       shown on Figure 6 for final disposal. The consolidation area is located at the

                                   59

-------
Conrail property.

c)     Cover and Erosion Control Requirements

Upon placement of excavated soils, the consolidation area will be graded and
covered whh gravd to prevent soil erosion.  Within the consolidation area, 6
inches of griwd wifl be placed to cover the area and prevent soil erosion. Erosion
control measures (e.g., concrete revetment mats or riprap) will be placed on the
bank, where necessary, to minimize erosion. The cover will men be sloped to a
minimum 2 percent grade from the southernmost tracks towards Fields Brook to
meet the riprap or other erosion control measures to be placed on sloped bank
areas along Fields Brook. The area covered by gravel and bank protection will not
be revegetated.

As part of the Remedial Design, the extent of excavation and cover areas will be
finalized.  The remedial action areas presented in the FS and *his ROD may be
altered during Remedial Design based on new sampling data, changes in the
assumptions concerning future operations at the Conrail property, or changes in
the extent of consolidation.  After excavation and consolidation, all areas with
surface soil contaminant concentrations exceeding residential CUGs will be
inchided in the containment area.

d)     Institutional Controls, Chemical Monitoring and O&M

institutional controls will be implemented for any area where hazardous
substances, pollutants or contaminants will remain above levels that allow for
iinijtnfod use and unrestricted exposure. More specifically, institutional
controls will be implemented to protect the cover system and drainage controls.
Such institutional controls will include, as appropriate, deed restrictions,
security fencing, and signs. The Operations and Maintenance Plan portion of
the Remedial Design will specify maintenance and monitoring requirements.  A
fence would be placed across the entrance  of the limited access bridge across
Fields Brook in such a manner as to prevent unauthorized entry.

Chemical monitoring requirements will include the annual collection of surface
 soil arsenic samples.  The performance of the selected alternative will be
reviewed and evaluated every five years after initiation of the remedial action to
assure that human health and the environment are being protected.

 Maintenance would involve visual inspection of the gravel and riprap cover.
Occasional repairs to restore the cover thickness or riprap will likely involve the
addition of gravel or riprap in areas of subsidence or erosion.
                             60

-------
     e)     Points of Compliance

     In conjunction with completion of the Remedial Action and performance of
     required O&M, erosion and runoff from the Conrail facility must
      residential Cleanup Goals (CUGs) established for the FWA and Sediment
      Operable Units.  The extent and integrity of the cover must be maintained to
      contain soil that exceeds CUGs. At a minimum, the point of compliance is the
      property boundary.  Additional performance monitoring locations may be
      identified during remedial design.

      Optional Imptementsaioo of Alternative V In Lieu of Alternative IV

      U.S. EPA believes mat Alternative IV will be effective in reducing the
      movement of contamination to Fields Brook and has selected Alternative IV as
      its primary remedy for the Conrail property. However, U.S. EPA notes that
      Alternative V is an acceptable enhancement of the selected remedy.  The
      complete excavation of contaminated soils and elimination of O&M has benefits
      that cannot he readily itemized in a cost estimate, such as a reduction in long-
      term liability concerns, a shortened remedial design phase, and the elimination
      of U.S. EPA staff time required to track O&M compliance and review
      monitoring results.

4)    Detrex

The selected remedy for the Detrex source area is Alternative IV, which requires the
containment and treatment of groundwater contamination by the construction of a
partial slurry wall and vacuum-enhanced extraction wells. Alternative IV would also
reduce the potential for migration of contaminated surface soil due to reach the DS
Tributary and Fields Brook by containment of surface soil contamination, ditch
cleaning, catalyst pile removal and retention pond sediment removal.

More specifically. Alternative IV consists of the following:

       a)     Clear Debris and Vegetation, Remove Physical Hazards

       In order to implement the Remedial Action, debris and vegetation must be
       cleared in response and work areas. Physical hazards that could threaten
       workers must also be addressed prior to Remedial Action.

       b)    Construction of Partial Slurry Wall

       This ROD requires the construction of a partial slurry wall to restrict the flow of
       the Detrex groundwater contamination.  The slurry wall component will extend

                                   61

-------
beyond the downgradient portion of the en-site and off-site DNAPL and
dissolved phase COCs plume, and be located outside of the DNAPL and
extended to ensure that the DNAPL and contaminated groundwater flowing
towards Fields Brook or die DS Tributary particularly along the northern and
western directions from die Detrex facility would be contained or captured.
The wall will extend along the western side of the RMI Landfill. The estimated
location of the shiny wan is shown on Figure 7. 'Design investigations will be
conducted to properly locate the wall in order to ensure mat the DNAPL and
contaminated groundwater flowing towards Fields Brook or the DS Tributary,
particularly along the northern and western directions from the Detrex facility,
will be contained or captured.  The wall is expected to be approximately 1,500
feet long; however, the final specifications of the shiny wall will be determined
Airing Ffmfilinl Design.
 The shiny wall would be constructed of a soil-bentonite shiny or other clay
 mineral slurry. The permeability of the slurry wall will be designed to be
 approximately 1 x 10* cm/sec.  Due to die high percentage of naturally
 occurring clay soil material 'in the proposed shiny wall area, it is possible mat a
 portion of the excavation spoils could be reused and incorporated into the slurry
 Wall.  Tfie remaning erovarinn apniU will he temporarily stockpiled nn-site
 and characterized to evaluate on-site and off-she disposal options consistent with
 ARARs.

 Compatibility testing to evaluate potential integrity issues related to DNAPL and
 other COCs in contact with die slurry material -will be performed during design
 phases. As part of this evaluation, a laboratory study will be conducted using
 soils from the Detrex site mixed with a clay mineral slurry.  A sample of
 DNAPL will be collected and placed in contact with the shiny. Laboratory
 compatibility tests will be performed to evaluate potential permeability changes
 in the slurry m; .:rial. Selection of the clay mineral additive (e.g. bentonite.
 attapulgite) will be performed in this remedial design phase.

 c)     Vacuum-Enhanced Extraction Wells

 Vacuum-enhanced extraction wells will be installed near the leading edge of the
 DNAPL plume near the shiny  wall and within the plume to lower groundwater
 and collect DNAPL in source areas. Based on pilot test results, approximately
 40 extraction wells are anticipated.

 Spoils from the installation of extraction wells will be temporarily stockpiled
 on-site and characterized to evaluate off-site disposal options consistent with
 ARARs.
                              62

-------
Fluids collected from the vacuum-enhanced extraction wells will be routed to a
knockout tank to separate the vapor phase from the liquid phase.  The vapor
phase will be treated with granular activated carbon to remove organic
contaminant vapors before being released into the atmosphere.

The liquid phase from the knockout tank will be conveyed to a DNAPL/water
separator where DNAPL will be separated from water. The separated DNAPL
wUl be collected and transported to an off-site facility for treatment or
recycling.  The separated water will be conveyed to the existing activated
carbon treatment system at the Detrex facility..

d)     Surface Water and Erosion Control /  Soil Cover

Low-lying areas within the existing surface water collection system area on the
Detrex facility and areas with surface soil occupational CUG exceedances will
be filled and regraded as part of this alternative, and these areas will be covered
with a 12-inch thick soil cover, an erosion control blanket, and a vegetative or
crushed stone layer surface..- Clean clay soil would be used for backfill.
Regrading and vegetative cover would prevent  ponding of surface water in
former source areas and reduce infiltration of surface water into die ground.
.OHimenfti lying within retention basin DET7 **v* in the drainage ditch on the
northern boundary ***** collects surface water will be excavated aftd analyzed to
evaluate disposal options consistent with ARARs. Following cleaning,  the ditch
would be filled with gravel or cement.

e)     Catalyst POe Excavation and Disposal

The catalyst pile material will be excavated, evaluated, characterized and
disposed of in a manner consistent with ARARs. Approximately 100 cu. yds of
catalyst material contained in the mice small piles and underlying soil will be
removed from the catalyst pile area.  The excavation will extend to a depth of
approximately six inches. Since the material is a solid, inert catalyst, leaching
through die soil is unlikely to have occurred.  Upon completion of removal  of
visible catalyst and excavation to the six inch depth, confirmation samples will
be collected from the base of the excavation, prior to backfilling. Clean soil
 will be replaced in the excavation and the area will be regraded and revegetated.

 I)     Off-site Surface Water Control In The DS Tributary

 In order to reduce the potential for subsurface  water seepage to enter the DS
 Tributary hi the northeast portion of the site, a 30-inch diameter culvert will be
 installed in the DS Tributary to contain surface water flow and keep
groundwater from entering the stream flow. This culvert will connect to the

                              63

-------
existing culvert beneath State Road and will extend along the northern side of
the railroad spur, approximately 600 feet upstream.  This configuration will
entirely contain the surface water in the DS Tributary north of the Detrex
facility, seal off potential groundwater seepage and prevent soil erosion. All
joints will be sealed to eliminate seepage. Sediment beneath the culvert will be
excavated to a depth of approximately 2.0 feet. The sediment excavated
beneath the culvert would be analyzed to evaluate disposal options consistent
witnARARs.

g)     Institutional Controls, Chemical monitoring and O&M

O&M activities for the vacuum-enhanced extraction well system will include
routine inspections of blowers, electrical equipment, belts, fuses, and pertinent
operating parameters. O&M requirements for the shiny wall and regraded
areas will consist of inspections, with regrading and revegetating, as necessary.
Routine sampling of selected extraction wells will be required to monitor the
effectiveness of the system.  At a minimum, annual groundwater monitoring
will be conducted at points of compliance, with samples to be analyzed for
DNAPL, VOC and SVOC parameters. In addition, water level data will be
gathered on a  semi-annual basis from all monitoring wells and piezometers
installed inside and outside of the shiny wall to evaluate groundwater gradients
within the remedial response area. More frequent analyses may be required in
the first few years of operation to establish a post-remediation baseline.

Storm water treatment system O&M activities, such as carbon replacement, will
remain the same as are currently used at the facility; however, die frequency of
carbon replacement will increase depending on the  concentration of
contaminants in the water pumped out of the extraction wells. O&M activities
will also include separator maintenance, handling and disposal of DNAPL, and
 inspection and periodic sediment removal from the settling pond at DET7.

The outfall from the existing stormwater treatment system will  be monitored
 for existing NPDES monitoring requirements and DNAPL constituents not
 included as part of the current monitoring program. Samples will be collected
 at the same time as the NPDES monitoring.

 Institutional controls will be implemented for any area where hazardous
 substances, pollutants or contaminants will remain above levels that allow for
 unlimited use and  unrestricted exposure. More specifically, institutional
 controls will be implemented to protect the cover system, drainage controls,
 slurry walls, extraction and monitoring wells. Such institutional controls will
 include deed restrictions, security fencing, signs and restrictions on the
 placement of wells.

                             64

-------
      The performance of the selected alternative will be reviewed and evaluated
      every five years after initiation of the remedial action to assure that human
      health and the environment are being protected
      h)    Points of Compli

      In conjunction with completion of the Remedial Action and performance of
      required O&M, sheet flow erosion and runoff from the Detrex facility must
      meet the occupational Cleanup Goals (CUGs) established for the FWA and
      Sediment Operable Units. The points of compliance for surface runoff will be
      the property boundary and tfte DS Tributary.  Groundwater contamination must
      also meet the occupational CUGs to prevent lecontamination of the Brook. At a
               , the points of compliance for the contaminants present in groundwater
      will be the edge of the shiny wall or, for areas without the shiny wall, the
      property boundary and the DS tributary.  Contaminant levels at the Detrex
      outfall must meet residential CUGs to ensure mat the 48* combined sewer can
      meet residential CUGs when it discharges to Fields Brook. Additional points of
      compliance monitoring may-toe identified during P^ny^Hiai Design.

5)    Sewers North and South of Fields Brook

The primary selected remedy for the sewer source area is Alternative ffl, which
requires the cleaning of the source area sewers specified in Section IV(E) of this ROD.
For the portions of the sewers that cannot be cost-effectively cleaned, the sections will
be filled with grout to contain the sediment and debris within the pipe.

The selected remedy for the sewer source area requires the following activities:

       a)     Cleaning of Sewer Lines and Catch Basins

       This alternative includes the removal of sediment and debris from inside the
       sewer lines and the associated catch basins to reduce die potential of
       recontamination of the Fields Brook sediments in excess of CUGs.  The sewer
       lines will continue to be used after remedial activities are completed.  Sediment
       removal could be accomplished by cleaning the inside of the sewer using
       manual and mechanical  techniques to remove sediment, followed by rinsing.
       Selection of the equipment to be used will be based on the size and conditions of
       the sewer lines at the time of work activities. The equipment selected will be
       capable of removing sediments, din, grease, rocks, and other foreign materials.
       Mechanically powered cleaning equipment consists of belt-operated buckets and
       a power rodding machine that is powerful enough to remove sediments and
       large debris  from the sewer lines. Rinsing equipment will include a high
       velocity gun for washing and scouring sewer walls and floors.

                                   65

-------
Sewer cleaning will begin at one access location, such as a manhole or a catch
basin, and continue to the next access location. All manholes along the sewer
lines will be located prior to sewer cleaning.  Additional manholes or access
points may need to be constructed between existing manholes, if the distance
between the two existing access points is longer than the reach of the  sewer
cleaning equipment.

All sediments and debris removed by the sewer cleaning will be staged in
stockpile areas located near access at one end of the sewer.  The stockpile areas
will be equipped with filter fabric or other equivalent measures to assure that
efdhnenta are not released to Fields Brook during remediation of the  sewers.
 The ««Himai*« god debris will be dewatered to reduce the water content and
 volume of the solids. Solids collected during the dewatering process will be
 characterized and disposed of consistent with ARARs. Collected sediments and
 solids will be transported to either the onshe-landfill (to be constructed on one
 of the industrial properties within the watershed) or an off-site landfill for
 disposal. The selection of off-site disposal facility (whether solid waste,
 RCRA, or TSCA) will depend on the chemical characteristics of the sediment
 material.

 The w**"«*f«* dewatering liquid will be combined with the rinse water generated
 during the final sewer cleaning.  Rinse water collected during me sewer
 cleaning process will be characterized for proper discharge. Rinse water may
 be treated on site with a portable  water treatment unit to meet surface water
 discharge criteria before discharging to Fields Brook.  Rinse water may also be
 recycled after removing the suspended sediments to reduce the amount of
 wastewater generated and the associated cost of treatment.

 Sediment and debris removal from the sewer pipe after cleaning will be verified
 by internal pipe inspection. Internal pipe inspection could be accomplished with
 remote pipe inspection using either electric or manually operated winches to pull
 inspection cameras specifically designed for use in sewer line inspection work.
 The camera may be pulled through the sewer line in either direction.

 b)     Sediment Containment - Sewers North

 Sewer sections that cannot be cost-effectively cleaned will be filled with grout to
 contain contaminated sediment and debris. This containment approach will be
 used for a portion of the 48-inch diameter combined sewer that runs from the
 Detrex outfall to the sewer discharge  point at Fields Brook (Figure 8A).   The
 existing sewer line will be abandoned and replaced with a new sewer diversion
 line.  The length of sewer considered for grouting is approximately 1 ,300 linear
 feet.  The sediments in this sewer segment would be contained by filling the

                              66

-------
sewer pipe with a cement grout to restrict flow in the sewer and prevent
migration of sediments into Fields Brook.  The sewer segment would be
plugged at bom ends before grouting proceeds. Lean cement grout or fly ash
grout would be used to grout the inner space of the sewer. Grouting would be
accomplished from both ends and at several locations along the sewer pipe.
Grout notes could be drilled at the crest of the sewer pipe through the
overburden. Grout pipes would be inserted through the grout holes to pump the
grout. Vents would be installed to allow air and water in the sewer to escape as
it is replaced with the grout material.

A replacement (diversion) sewer would be constructed to drain the water in the
remaining sections of the combined sewer.  The new sewer section would be
constructed to divert the combined sewer water discharge from a point south of
the Detrex outfall to the DS tributary.  The new sewr segment would be
approximately 100 ft long and have a diameter consistent with the existing
outfall. Sediments in the combined sewer south of mis diversion point would be
contained by grouting.  Sediments in the combined sewer north of this diversion
point and the other sewers would be removed. The estimated volume of
sediments in mis portion is 120 cu yds. These sewers would continue to be
used after remedial activities are completed.

c)     Sediment Containment • Sewers South

In the FS discussion of Alternative in for the sewers to the south of Fields
Brook, it was assumed that a portion of the sediments in the 30-inch sewer on
the Acme site would be contained (Figure 8B). Based on this assumption, the
FS cost estimate for Alternative in exceeds Alternative H, which requires
complete cleaning of the sewer lines without opportunity for containment.
Although Alternative ffl is selected in this ROD, inherent in this selected
remedy is the option to fully clean the  sewer lines. Alternative ffl provides
greater flexibility than Alternative n for the design'of a cost-effective and
protective solution.

Assuming a portion of the Acme sewer line would require containment, the
sediments in die impacted segment would be contained by filling the sewer pipe
with a cement grout to restrict flow in  the sewer  and prevent migration of
sediments into Fields Brook.  The sewer segment would be plugged at both ends
before grouting proceeds.  Lean cement grout or fly ash grout would be used to
grout the inner space of the sewer.  Grouting would be accomplished from both
ends and at several locations along the sewer pipe. Grout holes could be drilled
at the crest of the sewer pipe through the overburden. Grout pipes would be
 inserted through the grout holes to pump die grout.  Vents would be installed to
allow air and water in the sewer to escape as it is replaced with the grout

                             67

-------
            material.

            A replacement (diversion) sewer would be constructed to drain surface water
            runoff from the Acme site. The new sewer segment would be approximately
            300 ft long and would replace the grouted portion.  The estimated volume of
            sediments in the section of the sewer to be cleaned is 140 cubic yards.

                           iil
             Institutional controls will be implemented for any section of sewer where
             hazardous mrtmanmt. pollutants or contaminants will remain above levels that
             allow for unlimited use and unrestricted exposure. More specifically,
             institutional controls will be imptementea to control excavation into sewers that
             have been seated to contain contaminants »i*l to define hanHiji^g and disposal
             requirements for such sewers.  Such institutional controls will include, as
             appropriate, deed restrictions and signs. The performance of the selected
             alternative will be reviewed and evaluated every five years after initiation of the
             remedial action to assure mat human health and the environment are being
             protected.  The sewers to the north of Fields Brook discharge west of State
             Road and are therefore subject to residential CUGs.  The sewers to the south of
             Fields Brook discharge east of State Road and are subject to occupational
             CUGs.
6)    RMIMetab
      For the RMI Metals source area. U.S. EPA selects Alternative IV. However, selection
      of this alternative is based on the fstimatnd volumes and costs presented in the FS.
      Should additional sampling find the extent of soil contamination to be greater than
      currently known, cost estimates for Alternatives m and IV will be revised.  If the
      revised cost estimates demonstrate that Alternative in would provide significant cost
      savings over Alternative IV, U.S. EPA may elect to allow implementation of
      Alternative m instead of Alternative IV.  Therefore, the implementation of Alternative
      IV will be contingent upon its relative cost as compared to Alternative in. Because
      there is a preference for permanent remedies that do not rely on O&M to maintain their
      effectiveness, any cost difference between the two remedies will need to be significant
      for U.S. EPA to approve implementation of Alternative m.

      Alternative m requires the excavation of soil with PCB concentrations greater than or
      equal to 50 ppm and oil-site containment of soil with greater than 10 ppm. Excavated
      soil would be disposed of at either an on-site landfill (to be built on one of the source
      areas) or at an off-site landfill, whichever is more cost-effective.  Remaining
      contamination would be contained on site. Alternative IV requires the excavation and
      disposal of PCB-fiontaminated soil with concentrations greater than 10 ppm.  Since

                                         68

-------
         surface soil contamination would be at or below 10 ppm total PCBs for both
alternatives, die result is essentially the same, assuming proper O&M for the
containment remedy. Bom the selected alternative (Alternative IV) and the contingent
alternative (Alternative ID) would reduce the volume of contaminants at the site and
comply with TSCA.

More specifically, the selected alternative and the contingent alternative include the
following components:

       a)     dear Debris and Vegetation / Remove Physical Hazards

       In order to implement the Remedial Action, debris and vegetation must be
       cleared in response and work areas.  Physical hazards mat could threaten
       workers must also be addressed prior to Remedial Action.

       b)     Excavation of Soils

       Alternative IV requires excavation of soils with total PCB concentrations greater
       man 10 ppm to meet the 1.3 ppm total PCBs residential CUG at the Brook and
       its tributaries. During the remedial design phase, additional samples may be
       required to further delineate the remedial response area.

       Alternative 10 requires excavation of soils with total PCB concentrations greater
       than or equal to SO ppm. Based on existing data, it appears mat limiting
       excavations to a depth of approximately 1 foot should remove all TSCA-
       regulated soil. However, this remedy requires removal of all TSCA-regulated
       soils (* SO ppm PCBs). regardless of depth.  Therefore, if areas of additional
       contamination are identified, the excavation depth will be adjusted accordingly.
       During the remedial design phase, additional samples may be required to further
                the remoouJ (espouse •
        For both alternatives, the excavation of soils would be accomplished using
        conventional earth-moving equipment.  Upon excavation, the soil would be
        placed in lined roll-off containers or dump trucks for transportation to the
        landfill. Following completion of excavation activities, the excavated areas
        would be backfilled with clean soil or gravel and graded to allow for adequate
        drainage. Gravel fill would be used in areas subject to vehicle traffic.
        Verification sampling may be required to ensure removal of TSCA-regulated
        soils and demonstrate compliance with excavation requirements.

        For Alternative IV, it is estimated that an area of approximately 30 ft x 130 ft
        in size would be excavated to a depth of 1-foot (Figure 9A).  As shown in
        Figure 9B, die FS estimated that to implement Alternative m, an area of

                                    69

-------
approximately 20 ft x 80 ft in size would be excavated to a depth of 1-foot.
The excavated soils would disposed at either the on-site landfill (the SOU/FWA
consolidation area) or at an TSCA-compliant landfill.

c)     Refinement of Area to Be Covered

If Alternative ID is ultimately implemented, soil loss calculations will be
reviewed during the Remedial Design to finalize the area to be covered. It is
currently estimated that soils with PCB concentrations greater than 10 ppm will
be contained by the cover system. The cover areas have been developed based
on current operations and include the proposed excavation area since it is
located within the cover ulterior. The extent of the cover areas may be altered
during Remedial Design if a; iimptions  on future operations are revised.

d)     Construction of Cover, Surface Drainage Controls

If Alternative m is ultimately implemented, the erosion control cover materials
will consist of a 12-inch thick layer of clean soil, an erosion control blanket and
will be vegetated to reduce the potential for erosion. For anticipated future
traffic areas, a 6-in. gravel layer underlain by geotextile will be used instead of
the soil.

e)      Surface Drainage Controls

 If Alternative ffl is ultimately implemented, on-site surface drainage will be
controlled.  The erosion control cover design will include a sloped surface to
 control drainage and prevent surface water from pooling on the surface.
                              *
 f)      Institutional Controls, Chemical Monitoring and O&M
 No monitoring, institutional controls or 5-year review will be required for
 Alternative IV.

 If Alternative HI is ultimately implemented, institutional controls will be
 implemented for any area where hazardous miKfrtanmt. pollutants or
 contaminants will remain above levels that allow for unlimited use and
 unrestricted exposure.  More specifically, institutional controls will be
 implemented to protect the cover system and drainage controls.  Such
 institutional controls will include deed restrictions, security fencing, and signs.

 O&M for Alternative in will include regular inspections of the erosion control
 cover to check for cracking and wear and die implementation of appropriate
 repairs. Chemical monitoring requirements include the annual collection of

                              70

-------
            total PCB surface soil samples.

            Reviews of Alternative in will be required to be conducted every five years
            after initiation of the remedial action to assure that human, health and the
            environment are being protected by the remedial action. This is required
            because hPTagdfflis tnibfflnyyyt pollutants or contaminants will remain on die
            facility and on-site above levels that allow for unlimited use and unrestricted
            exposure.

            g)     Points of Compliance
                                     v
            Alternative IV must meet residential CUGs at the Brook. Based on calculations
            performed during die RI/FS process. Alternative IV will prevent CUG
                        in the Brook.  The alternative requires no O&M, long-term
             monitoring, or institutional controls.

             If Alternative m is ultimately implemented, O&M, long-term monitoring and
             institutional controls will be/required.  In conjunction with completion of the
             Remedial Action for Alternative m and performance of required O&M, erosion
             and runoff from the RMI Metals facility must meet residential Cleanup Goals
             (CUGs) established for die FWA and Sediment Operable Units.  At a minimum.
             the points of compliance are the property boundary and die edge of the
             floodplain. Additional performance monitoring locations may be identified
             during remedial design.

B) ARARs To Be Met

Section 121(d) of CERCLA requires that Superfund remedial actions meet ARARs.  In
addition to ARARs, die ARARs analysis which was conducted considered guidelines, criteria.
and standards useful in evaluating remedial alternatives. These guidelines, criteria, and
standards are known as TBC  '"to be considered").  In contrast to ARARs, which are
promulgated cleanup standards, standards of control, and other substantive environmental
protection requirements, criteria or limitations. TBCs are guidelines and other criteria that
have not been promulgated or are not directly applicable. The selected remedy will comply
with the ARARs and the TBCs listed in Table 2 which is attached to this ROD.

Two of the important action-specific ARARs for remediation of die source areas are the
Ambient Water Quality Criteria and die Ohio Water Quality Standards, which contain specific
standards that would be applicable if remediation water or treatment plant wastewater is
discharged directly to Fields Brook or the Ashtabula River.  In addition to the water quality
criteria, substantive requirements of National Pollutant Discharge Elimination System
(NPDES), as implemented under Ohio regulations, would also be applicable to wastewaters
planned to be discharged to Fields Brook which will require treatment. These wastewaters

                                         71

-------
include liquids generated during construction activities such as dewatering liquids, excavation
area liquids, and liquids generated during construction of the on-site consolidation area.
Discharges to Publicly Owned Treatment Works (POTWs) may be pursued as an alternative
discharge location.  However, such discharges must also comply with limitations to ensure
acceptable discharge from the POTW after treatment.  The specific discharge levels will be
determined during the design stage in coordination with OEPA.

A large portion of the soils and sediments to be excavated from the source areas for disposal
into the on-site consolidation area landfill will contain PCBs exceeding SO ppm. Excavation of
these wastes and soils and containment in an on-site landfill  will be considered disposal of
PCBs pursuant to 40 CFR 761. l(b).  In this case. 40 CFR 761 -60(aX2) requires any non-
liquid PCBs at concentrations of SO ppm or greater in die form of contaminated soil, rags, or
other debris to be disposed  of in w incinerator which complies with 761.70 or in a chemical
waste landfill which complies with 761.7S.

Regulations related to the dewatering of the soils and sediments prior to consolidation must be
met, including 40 CFR 264.228(a)(2). which requires elimination of free liquids by removal or
solidification. Thus, it is required that dewatering of the excavated soils and sediments to be
landfilled will occur in part to ensure that no tree liquids will remain in the soils and sediments
prior to disposal into the landfill unit.

Treatment and air emission requirements relevant to hazardous waste in 40 CFR 260-268 could
be potential ARARs for facilttiflg where  listed or characteristically hazardous wastes are
known to have been disposed of in the source control areas.

Actions must be taken to minimise the destruction, loss, or degradation of wetlands due to
construction activities and the final remedy.
 XI. EXPLANATION OF SIGNIFICANT CHANGES

 There is one significant change from the recommended alternatives described in the Proposed
 Plan. The U.S. EPA is selecting Alternative IV at the RMI Metals source area, with the
 contingent implementation of Alternative in if future volume and cost estimates prove
 Alternative in to be significantly more cost effective than Alternative IV.

 In addition, mere are some important clarifications in this ROD mat were not presented in the
 Proposed Plan.

 »     For the Acme source area, Alternative VI was recommended in the Proposed Plan.
       This ROD selects Alternative VI, but notes that consolidation may be an acceptable
       component of the remedy.
                                         72

-------
      Based on public comment and a subsequent review of site data, the U.S. EPA has
      determined that the Acme facility is subject to occupational CUGs, rather than
      residential CUGs.  This may result in a substantial decrease in the cost of remediation
      for the Acme property.

      For the Millennium source area. Alternative VI was recommended in the Proposed
      Plan. This ROD selects Alternative VI, but notes that consolidation may be an
      acceptable component of the remedy.

      For the sewers source area, Alternative in was recommended in the Proposed Plan.
      This ROD selects Alternative m and notes that, under this alternative, the containment
      and replacement of sewers are not required if cleaning of sewers proves to be more
      cost-effective.

      As discussed above, Alternative m was recommended in the Proposed Plan for the
      RMI Metals Reduction source area. Based on comments from the U.S. Fish and
      Wildlife Service and discussions with the State of Ohio, mis ROD selects Alternative
      IV, but allows for the contingent implementation of Alternative in should revised
      volume and cost estimates demonstrate that a significant cost savings could be realized
      by the implementation of Alternative m instead of Alternative IV.
XH. STATUTORY DETERMINATIONS

U.S. EPA's selected alternatives provide die best balance of trade-offs among alternatives with
respect to the criteria used to evaluate remedies.  Based on the information available at this
time, U.S. EPA believes that these final Remedial Actions are protective of human health and
the environment, comply with Federal and State applicable or relevant and appropriate
requirements and are cost-effective. The selected remedial actions utilize permanent solutions
and considered use of alternative treatment technologies to die maximum extent practicable.
However, due to the significant volume  i.d heterogeneous distribution of waste at the Site,
treatment as a principle element is not considered practicable at the Site. Thus, these remedies
do not address the statutory preference for treatment that reduces toxicity, mobility, or volume
as a principal element. However, treatment is a secondary element in that DNAPL from the
Detrex facility will be collected and treated resulting in destruction of hazardous substances.

A review of the remedies will be conducted five years after commencement of the remedial
actions to ensure that the remedies continue to provide adequate protection of human health
and die environment by preventing the flow of contamination to Fields Brook.
                                         73

-------

-------
                                          Table 1
                        Fields Brook Cleanup Goals rCUGs)
   PARAMETER
Resideiitui     Occupational    TypeofExceedancein
   CUG            CUG        Source Control Areas
  Volatile Orgufe Compound*
  1.1.1-TricUaradttne
  l,l>TricbIorortb
  U-Dkfalaroethene
  1 .2-Dichloroelhen0 (bins)
  Chlorofcnn
  EtbyibenxGoo
 . TctnchlororabcDc
  Toluene
  Vinyl Chloride
 Semi-VcfatOeOrvuik
  • « *t*™ 1 ndiiyn in pffi i?id iff
  U-Dichlorobenzenc
  1 ,4-Diduunutifii/iBne
 2-Chlc*ophenol

 Anthncene
 Benzidcac
 Bu(2-etbylhexyl)phtfaalate
 Chiysenc
 Di-n-butyl phthalate
 Di-n-octyl pfathalite
Dicthyl pfatfaalate
Dimethyl phthaUte
       393,451
           SI
          179
           17
        87.433
          352
        87.433
         1.672
      437.167
          196
      874435
          927
          5.4
       43.717
      393.451
         425
       21.858
      262.300
    1.311.502
         .04
        13.97
         1.4
        13.97
        13.97
         729
       139.73
     437.167
      87.433
         1.4
   3.497.338
    437.167
   766.500
       119
       418
        40
   170.333
       822
   170433
     3.909
   851.667
       459
  1.703433
     2.168
        13
    85,167
   766.500
      994
    42483
   511.000
 2.555.000
       .1
       33
      3.3
       33
       33
    1.703
     327
  851.667
  170,333
     3.3
6.813.333
 851.667
                                                                         residential
occupational
                                                                  residential / occupational
msidmtinl

-------
                            Table 1- continued
                   Fields Brook Cleanup Goals (CUGrt
PARAMETER
Fhurane
I IcxachlorobtiiiKiit
Henchkrabutadkn
Ideno(l.2J-cd)pyitne
Inophcfuue
N-ohYondipheny
        /PCBa

BHC (alpha)
oHC (ffUXUDft J I ilUfMIVT

Total PCBi
 Antimony
 Arsenic
 Boy Ilium
 Cadmium
 Chromium
 Copper
 Mercury
 Nickel
 Selenium
 Thallium
 Zinc
 Cyanide
RnMfiititl '
CUG
174^67
174,867
6.38
131
729
14
10.737
2.081.75
174.867
.2.186
2,623.004
U11^02
1.6
7.8
2.3
1.3
1.749
27.6
2.4
2.186
21.858
161.752
500
1.312
87.433
21.858
262
847335
87.433
Occupational
CUG
340.667
340.667
15
306
1,703
33
25.102
4.867
340.667
4.258
5.110.000
2.555.000
3.8
18
5.3
3.1
3.407
28
5.5
4,258
42.583
315.117
500
2.555
170.333
42.583
511
1.703^33
170.333
Tvnr ftf EicftiltiHT in
Scarce Control Areas






•




AM«*m«ti«wft*l



residential / occupational
residential










-------
     POTENTIAL LOCATION-SPECIFIC ARARS
     FIELDS BROOK SITE • SOURCE CONTROL OPERABLE UNIT
     ASHTABULA, OHIO
                             Requirement
                                                                                                           CommenU
                                                                               Appropriate
                      Lawa/R.niilrrTff.tT
-A.
y
v\
      FEDERAL REGULATIONS

      B.P. m»» Protection of Flood,!.!™

      I.   Llmlti activities In noodpltlnt. Floodplain h denned u "the
           lowland and rtlitlvely flu irew idjolnln| Inland and cowttl
           waien including flood prone ana* of ofT-inon liluidi,    '
           Includlni at a minimum, that area lubject to a one percent or
           •fewer chance of flooding in any given year." Federal agencies
           mm t evaluate the potential effect! of action taken In a
           floodplain and avoid advene Impacts from remedial activities
           (40 CFR 6.302 and Appendix A]
      E&
                                                                     Yes
Itf
2.   Minimiies advene Impacts on areas designated as wetlands.
    HO CFR 6.302(a) and Appendix A]


Clean Wijer Act Section 404

3.   Requires Federal agencies to avoid, to the extent possible.
    adverse impacts associated with destruction or loss of wetlands.
    MO CFR 230-231; 33 CFR 320-330)
                                                                     Yes
                                                                    Yes
                                                                                     • The FWA Is located wlihjn a 100-year
                                                                                      floodplain. If remedial activities are conducted
                                                                                      within the floodplain, or adversely affect natural
                                                                                      floodplain values, this regulation will be
                                                                                      applicable.
                                                                                            Wetlands are present along portions of Fields
                                                                                            Brook.  Regulations are applicable only if
                                                                                            remedial activities impact the wetlands areas.
                                                                                            Wetlands occur along Fields Brook; regulations
                                                                                            would be applicable only if the remedial
                                                                                            activities impact the wetlands areas and/or other
                                                                                            waters of the United Slates.
                                                                                                                                                      f
                                                                                                                                                      rr

                                                                                                                                                      A/
    I \DKOOH CttTMWECnVTAOLE ) WM-09 »J
                                                              Page 1 of 5

-------
POTENTIAL LOCATION-SPECIFIC ARARS
FIELDS BROOK SITE - SOURCE CONTROL OPERABLE UNIT
ASHTABULA, OHIO
                                                               Potentially
                                                               Applicable
                                                                                 Potentially
                                                                                Relevant and
                                                                                Appropriate
                                       Comment!
c
%
*l
  4.   Prohibits discharge of dredged or filled material Into water! of
      the U.S. without a permit. (40 CFR 230, 33 CPU 320-330)


  Riven and Harbon Ad of 1899: Section 10

  3.   Section 10 permit required for itructures or work In or
      affecting navigable waien. (33 USC 403,33 CFR 320-330]

  Endinaered Specie. Act
                                                                      Ye!
  6.
           Protect! endangered species and threatened species and
           preserves their habitat. Require! coordination with federal
           agencies for mitigation of impact!.  (16 USC IS3I
           SO CFR 200, 90 CFR 402)
  Fish and Wildlife Coordination Act

  7.   Requires coordination with federal and stale agencies on
      activities affecting/modifying streams or riven If the activity
      his a negative impact on fish or wildlife. (16 USC 661 £lj£0,;
      40 CFR 6.302(8))
                                                                      Yes
Yei
                                                                      Yes
                        Regulation! would be applicable if the remedial
                        action involve! dredge and/or fill activities in
                        Fields Brook
                       ' If the remedial activity iffecti navigable waters.
                        these regulations are applicable.
If there are threatened/endangered (T/B) species
or critical habitat! within the areas impacted by
the remedial activities, this regulation would be
applicable. No such endangered specie! are
known within the area.
                        If Field! Brook will be impacted by rented!*!
                        activities, thii regulation would be applicable.
I.:UIROOKFS\TM]\SECT)\TABIE.)-M»-OM7
                                                                 Page 2 of 5

-------
 POTENTIAL LOCATION-SPECIFIC ARABS
 FIELDS BROOK SITE - SOURCE CONTROL OPERABLE UNIT
 ASIITADULA, OHIO
                          Requirement
   Potentially
   Appllcibli
 Potentially
Relevant and
Appropriate
Comments
   12.  Any activity modifying a ilream or river, which will have a
       diversion, channeling or other action and which affects fish or
       wildlife must be implemented with action to protect fish or
       wildlife 116 U.S.C 661 el seq.)
      Yes
  (Source Conservation ind Recovery Act iRCRAl
  13   A treaimeni/storaie/diiposal (TSD) facility within a 100-year
       floodpliin mutt be designed, constructed, operated, and
       maintained to avoid washout.
  14.  Landfills may not be located within vulnerable hydrogcology
       areas. (RCRA 3004 (oX7)|.
      Yes
      Yes
              This Act would only be applicable if:
              (I) pollutants or dredge and fill are discharged
              into a body «f water or wetlands, and/or (2)
              dams, levees, Impoundments, stream  relocation,
              rip-rap or channeling activity, and/or water
             •diversion structures are constructed, and/or any
              other construction activity within or in the
              vicinity of the stream which affects fish or
              wildlife.
               This requirement would only apply to
              permanent hazardous waste landfill located
              within the site and located within a 100-year
              floodplain. Interim storage does not n»rd tq
              attain ARARt, if the appropriate interim storage
              requirements are met.

              This requirement  would only apply, if a
              landfill is proposed to be placed within  a
              vulnerable hydrogeology area.
L vtmooKi SUMJVSECT MABLC J.JVBJ w »J
Page 3 of 5

-------
     POTENTIAL LOCATION-SPECIFIC ARARS
     FIELDS OROOK SITE - SOURCE CONTROL OPERABLE UNIT
     ASHTADULA, OHIO
                            Requirement
                                            CommenU
r
i.
      I9S|C SupSiaiKTS Con.ml Aq
15.  Requires that TSCA landfills meet specified siting, design,
    handling, and monitoring requirements (40 CFR 761.60 and
    761.75 (B)J.
      STATE STATUTES AND REGULATIONS
      gfflO Hawdoui Waite Sli|nB
                                                                   Yes
                             These regulations would apply if a remedy
                             includes construction of a TSCA landfill or if a
                             remedy Includes disposal of material that
                            •• contains PCB concentrations at or greater than
                             50 mg/kg.  Interim storage does not need to
                             attain ARARs If appropriate interim storage
                             requirements are met.  .
      I.   A hazardous waste facility installation and operation permit
          ihall not be approved unless It proves that the facility   .
          represents the minimum risk of all of the following:

          (i)   Contamination of Ground and Surface Water
          (ii) Fires or Explosions from Treatment, Storage or Disposal
              Methods
          OH)  Accident during Transportation
          (iv)  Impact on Public Health and Safety
          (v)  Air Pollution
          (vi)  Soil Contamination
          (ORC 3734-06 (D) (6) (d)J
      Yes
Yes
                                                                                   Would be an ARAR if (he remedy involved
                                                                                   treatment, storage or disposal of hazardous
                                                                                   waste.
   L\BROOKFSvrMJ\SECT)\TABlE.)-]tt>-0«-*7
Page 4 of 5

-------
   POTENTIAL LOCATION-SPECIFIC ARAKS
   FIELDS BROOK SITE - SOURCE CONTROL OPERABLE UNIT
   ASHTABULA, OHIO
                           Requirement
Potentially
Applicable
     2.   Prohibit* the following location* for treatment, storage, and
          diipoul of acute hatardous wute: (I) within 2,000 feet of any
          residence, school/hospltal, jail, or prison; (2) any naturally
-\        occurring wetland; (3) any Hood hazard area; (4) within any •
r        state park or national park or recreation area.
T "      IORC 3734.03 
-------
 POTENTIAL ACTION-SPECIFIC ARARS
 FIELDS BROOK SITE • SOURCE CONTROL OPERABLE UNIT
 ASHTABULA, OHIO
                       Requirement
Potentially
Applicable
                                                                     Potentially
                                                                    Relevant and
                                                                    Appropriate
Comment*
FEDERAL REGULATIONS

To«ic Substances Control Ac. fTSCAl

I.   Establishes regulations to govern the storage and disposal of '    Yes
    PCBs including PCB-contaminated soil. [40 CFR 761)

2.   Prescribes design, construction, and operation standards for       Yes
    TSCA landfills.  (40 CFR 761.73)

    Specifies requirements for disposal of materials containing       Yes
    PCBs. (40 CFR 761.60)

    Establishes standards for PCB incinerators, Including            Yes
    combustion criteria, combustion efficiency, other operating
    standards, and monitoring requirements.
    |40 CFR 761.70)
 3.
 4.
                                      TSCA regulations for storage and disposal could be
                                      applicable to disposal of PCB contaminated soils.

                                      Only applicable for alternatives that Include disposal
                                      of TSCA materials.

                                      The
-------
•\
    POTENTIAL ACTION-SPECIFIC ARARS
    FIELDS OROOK SITE - SOURCE OPERABLE UNIT
    ASHTABULA, OHIO
                          Requirement
                                                                      Potentially
                                                        Potentially    Reterut and
                                                        Applkable    Appropriate
                                                                                                                    Comments
Clean Air Agj

National Ambient Air Quality Standards fNAAOS)

3.    Establishes ambient air quality standards to protect public    •    Yes        Unknown
     health and welfare.  Includes National Primary and
     Secondary Ambient Air Quality Standards for Paniculate
     Miller. (40 CFR 90]


Ambient Air Moni|orjng                                          •

6.   Specifies methods for conducting ambient air monitoring.         Yes           ~
    140 CFR 33|

Safe Drinklnt Water Act

Undcriround Inlecilon Control (UjC)

7.    Establishes standards for injection wells to provide protection   Unknown      .  —
    of underground sources of drinking water. (40 CFR Parts
     144-148)
                                                                                                   Only applicable if criteria pollutant! are discharged
                                                                                                   to the atmosphere during waste handling or a
                                                                                                   treatment process. NAAQS would t* uteri to
                                                                                                   compare ambient air quality during the remedial
                                                                                                   action.
                                                                                                   Would only be applicable to actions resulting In
                                                                                                   emissions of pollutants.
                                                                                                   If the remedial action alternative involves
                                                                                                   underground Injection, these regulations could be
                                                                                                   applicable.
    L\BROOKFS\TM)\FDI7\SECT)\TAni.E.).)ttS09-9?
                                                                Page 2 of 12

-------
     POTENTIAL ACTION-SPECIFIC ARARS
     FIELDS DROOK SITE - SOURCE OPERABLE UNIT
     ASHTABULA, OHIO
                           Requirement
                                                                        Potentially
                                                         Potentially   Reform! and
                                                         Applicable    Appropriate
                                        Comment*
     CJeanWaier Act
H
National Pollui.nl DI*charM Elimination System (NPDES>

8.   Require* dischargers of pollutants from my point source into
    surface waters of the United States to meet certain
    requirement* and obtain a NPDES permit. (40 CFR 122, 123
    •and 123 are Involved)
                                                                 Ye*
     Ambient W.ter Quail,, Criteria

     9.   Requires EPA to publish water quality criteria for specific
         pollutants for the protection of human health and the
         protection of aquatic life.  (40 CFR 1311

     National Pretrealment Siandanh
                                                            No
Yes
                      No permit would be required for in on-site
                      CBRCLA remedial action that involves a dlwharge.
                      but the substantive requirement* of the NPDES
                      program would apply if the remedial action
                      involve* surface water discharge, ThJsARAR
                      would be applicable or a substantive modification to
                      an eiNnt PDBS permit may be needed for the
                      following remedial alternatives: a) the Deirex
                      facility UNAPL alternative*  where the DNAPL
                      would be collected and treated on-slle;  b) the sewer
                      flushing alternatives where releases to Fields Brook
                      may occur, c) on-site treatment of contaminated
                      water generated during construction (e.g.,
                      leachate/diainage water, decon fluids, etc.).  Other
                      alternatives may also be required to meet this
                      ARAR if a point source occurs during remediation.
Relevant and appropriate if contaminant* are
released to surface waters or if treated groundwatcr
is collected and discharged to surface waters.
    L \DROOKrS\TMJ\F8l7\SECT J\TADLEJ«>H».»7
                                                                 Page 3 of 12

-------
POTENTIAL ACTION-SPECIFIC ARARS
FIELDS DROOK SITE - SOURCE OPERABLE UNIT
ASIITABULA, OHIO
                       Requirement
10.  Establishes general and specific «t*ndards for pollutants that
    are discharged to a POTW.  (40 CFR 403)

Storm Water Discharge Regulations

11.  Establishes permitting, sampling and analysis requirements
    for industries in certain categories which discharge storm
    water to waters of the United States.  Includes storm water
    discharge from construction activities. (40 CFR 122)
              Potentially  .
Potentially    Relevant and
Applicable    Appropriate

   Yes           .-
                                                             Yes
                                                                                                                  CommfnU
                                                                                                 If thf remedial action involves discharging to a
                                                                                                 POTW, these standards would be an ARAR.
                                       No storm water permit would be required for an on-
                                       sile CBRCLAJtemedial action that involves a
                                       discharge. Subsfntive requirements  (e.g..  Storm
                                       Water Pollution Prevention Plans) could be
                                       applicable.
 Discharies of Dredged or Fill Materials

 12.  Prohibits discharges of dredged or fill materials Into waters
     of the U.S. without a permit. (33 CFR 320 to 330. Section
     401 and 404 of Clean Water Act]
   Yes
                                                                                                Regulations would be applicable If the remedial
                                                                                                action Involves dredge and/or nil activities in Fields
                                                                                                Brook.
L:»OROOKFS\TM)\rDI7\SECTJ\TABI.E.).M>30»9J
         Page 4 of 12

-------
 POTENTIAL ACTION-SPECIFIC ARARS
 FIELDS BROOK SITE • SOURCE OPERABLE UNIT
 ASHTABULA, OHIO
                     Rcqulrcmtnt
                                                               PotentlaUy
                                                   Potentially   Rcltrwl ind
                                                   Applicable   ApproprUU
                                   CommenU
                             Ael (RCRAl
faHWM Conservation .nd Recc  	

PCRA OTCCllvr Aciion M.nt.^nt Unit Rule

13.  Providei for designation of • Cornellve Action Minagement •
    Unit tnd euei regulatory requirements for remedial actions
    conducted within unit boundwtei. (40 CFR 260 et al]
                                                       No
Yes
Would be potentially relevant and appropriate
requirement for management of hazardous waste
within the plant sites.
L:\BROOK FSYTMWBIMCCTMABLE J-WM-OT »I
                                                         Page 5 of 12

-------
 POTENTIAL ACTION-SPECIFIC ARARS
 FIELDS BROOK SITE - SOURCE OPERABLE UNIT
 ASIITADULA, OHIO
                        Requirement
                                                                        Potentially
                                                          Potentially    Relevant aad
                                                          Applicable    Appropriate
                                                                                                                     Comments
RCRA
                                          Dliooul (TSD1
  14.  Prevlde* regulations for the notification of hazardous waste
      •divides, identification and listing of hazardous wastes and '
      management of hazardous wastes by generators, transporters
      •nd operator* of treatment storage and disposal facilities. (40
      CPU 260 et at). Specific RCRA TSD rrjiulatlons that may
      need to be evaluated as potential ARARs on a case-by-case
      basis include:
          •)  40 CFR 268 (movement of excavated materials)
          b)  40 CFR 6, Appendix A
          c)  RCRA 3003
          d)  40 CFR 262 and 263
          e)  40 CFR 170-179
          0   EPA Hazardous Waste Permit Program
              (promulgated In part as 40 CFR 300.440
              (9/22/93)).
          g)  RCRA Section 3005
          h)  40 CFR 270 and 124
          i)   50 FR 45933(11/3/83).

 15.  Specifies performance standards and other operating
      requirements for incineration of hazardous waste. [40 CFR
      261.340 to 261.351)

 16.  Specifies requirements for closure of hazardous waste
      management  units. [40 CFR 264.1 1 7(c). 228(a) and (b). and
      3lO(a) and (b)|
L:WROOKFJ\TM)\FBI7\SOCTJ\TABLE)-)»}09.»7
                                                             Yes
                                                             Yes
                                                             Yes
Substantive requirements would be potentially
applicable to any hazardous waste landfill built at
the site. However, contaminated soils In the SCOU
are not known to be hazardous wastes pursuant to
RCRA or the Ohio solid wa*e disposal statute .
Oven If contaminated soil were considered solid or
hazardous wattr. designation of a corrective action
management unit would allow movement of soil
without triggering the Lawl Disposal Restriction
regulations.
These requirements would tpply If chosen
alternatives include incineration.


Some of these requirements would apply if
containment or other on-sile disposal of RCRA
regulated hazardous waste is a selected alternative.
                                                                  Page 6 of 12

-------
POTENTIAL ACTION-SPECIFIC ARARS
FIELDS BROOK SITE - SOURCE OPERABLE UNIT
ASHTADULA, OHIO
«
g
 17.  Thete regulations establish sunduds for design Instillation.
     and maintenance of dikes around • unit, to ensure the unit
     does not fail or overtop, and to remedy problems and any
     contamination. (40 CFR 264.22I(|) and (h), and 261.277]

 RCRA Land Dlsnoul Restrictions

 II.  Establishes a timetable for restriction of land disposal of
     hazardous wastes and treatment criteria of hazardous waste
     prior to land disposal. (40 CFR 268]
 RCRA Solid Waste Treatment Storaie f nd Ditoostl (TSD1
 Reiulailonf

 19. Establishes requirements for owners and operators of solid
     waste disposal facilities (40 CFR 238)
                                                                              Potentially
                                                               Potentially    Rdevutand
                                                               Applicable    Appropriate

                                                                   Yes
                                                                   Yes
                                                                   Yes
                                                                                                                    Commend
These regulations would apply If remedies selected
include installation of a dike around • hazardous
waste management unit.
Substantive requirements would be potentially
applicable if hazardous wastes are generated during
remedial activities and disposal is off site.
However, only applicable If no equally or more
stringent State regulation exists (see below).
Substantive requirements would be potentially
applicable If solid wastes are generated during
remedial activities.  However, only applicable if no
equrlly or more stringent state regulation exists (see
below).
I.\jmOOKrS\TMJ\FBI7\JECTJYMBLe J-J»1-0»-9J
                                                                         Page 7 of 12
                                                                                                                                                I

-------
 POTENTIAL ACTION-SPECIFIC ARARS
 FIELDS DROOK SITE - SOURCE OPERABLE UNIT
 ASHTABULA, OHIO
                        Requirement
                                                                        Potentially
                                                          Potentially    Relevant and
                                                          Applicable    Appropriate
                                        ComrotnU
 STATB REGULATIONS
 g"IP HMlpnaJ Pollutant Pitch.™ BHmln.t|?n {fy..m
C    I.
f>
M
      Requires permit! for the discharge of polluitnU from any
      point source into waters of the United Slates.  Must meet
      technology.based effluent limitations and standards (either
      "best conventional pollutant control technology* or "best
      available technology economically achievable"), determined
      on a casc-by-case basis. (OAC. Title 3743, Chapter 33)
 PMff rVTreatmr, nt Rmuir^^,
2
     Rc|ul«esihcdiKhw|eorpollulMtiloPOTWs. (OAC.
     Till* 374J. Chapter 3}
 Ptrfp Non-Point Source ReffHm!
3.
     Regulations call for the use of conservation practices to
     control sediment pollution of water resources.
     IOAC, Title 1501. Chapters I, 3, 5)
 Ohl°
4.
     establishes minimum water quality requirements for all
     surface waters of the state.  Establishes stream use
     designations and water quality criteria protective of such
     u«es. See Table 4-3. [OAC. Title 3745, Chapter I]
                                                             Yes
Yet
                                                             Yes
                                                             Yes
                                                             Yes
Applicable if the remedial action involves discharge
to surface water located oiT-sita oj[ relevant and
appropriate for discharges to on-slle surface water.
Subslanlive*iequirements must be met, but no
permit will be required for on-slte discharges.
                      Applicable if groundwater or waste/treatment water
                      from the site is discharged to the POTW.
                      These regulations could be applicable for any major
                      earth-Hlsiuibing activities.
                      Applicable if contaminated water is discharged into
                      surface waters.
L \HROOKFS\TM)\fDI7\JECT)\TAOLe) )»JO»-»7
                                                                  Page R of 12

-------
POTENTIAL ACTION-SPECIFIC AltARS
FIELDS BROOK SITE • SOURCE OPERABLE UNIT
ASHTABULA, OHIO
                      Requirement
                                                                       Potentially
                                                         Potentially    Referral tad
                                                         Applicable    Appropriate
                                                                                                                  Comment!
 Ohio Haianlous -Waste Min«iement Remlalloni

 3.   Provldw regulations for the notification of hasardoui waste
     activities, (tatlficaiion and listing of haiardws wastes and
     management of hasardous waste* by generators, transporters
     •fid operators of treatment storage and disposal facilities.
     IOAC, Title 374S, Chapters 30-69]

 Haiatdous Waste Manaiement Systems. General

 6.   Establishes procedures and criteria for modification or
     revocation of any provision in OAC, Title 3745,
     Chapters 50-69.

 Identification and Lhlint of Hazardous Wastes

 7.   Defines those solid wastes  which ire subject to regulation as
     hazardous wastes (OAC, Title 3745, Chapter 51].
Standards Applicable to Generators
                                          w"le
 8.   Establishes standards for generators of haiardoui waste
     IOAC, Title 3745, Chapter 52).
                                                            Yea
                                                                        Unknown
                                                                        Unknown
                                                                         Unknown
Substantive requirements are applicable If remedial
actions Involve management of hazardous wastes
and construction of on-slte hasardous waste
facilliy(les), and the requlremf nu are more stringent
than the federal.
May be applicable if a contaminant is to be
excluded from list of items defined as hazardous
waste.
Applicable if remedial action involves generation of
hazardous wastes.
                                                                                                 Applicable If remedial action Involves treatment.
                                                                                                 temporary storage, or off-siif disposal of ha«ardn,«
                                                                                                 waste.
                                                                   Page 9 of 12

-------
    POTENTIAL ACTION-SPECIFIC ARARS
    FIELDS BROOK SITE - SOURCE OPERABLE UNIT
    ASHTABULA, OHIO
                           Requirement
              Potentially
Potentially    ReUrutaod
Applicable     Appropriate
                                                                                                                         CommcnU
     Slindiidi Aw|fcrfr|y !? Transporters of Hatardous Waste

 i    9.   Biubllthei itairiaidi which apply to persons transporting    .     Yet
"I        huantoui waste within the U.S. if the transportation requires
-  .      a manifett (OAC, Title 3745, Chapter 52 and S3).

     Slandai^ for Qwneta and Onemtoni of HattfJous  Waste
.    Trcatmen^ Storae^ apd Disposal Facillllei

     10.  Bitibliihet minimum standards which define the acceptable       No
         management of hatardous waste for ownen and operaton of
         permitted facilities which treat, store, or dispose hatardous
         waste IOAC. Title 3745. Chapter 54).   -
     Interim Standards for Owners and Operators of Haiardous Waste
     Treatment. Storaae. and Dlinoul Facilities
                                                              •
     II.  Establishes minimum standards that define the acceptable         No
         management of hazardous wute for impermltted treatment,
         storage, and disposal facilities during the period of Interim  •• .
         status and until certification of final closure or, If the facility
         is subject to post-closure requirements, until post-closure
         responsibilities are fulfilled (OAC, Title 3745, Chapter'65].
                  Yes
                 Yea
                                        Applicable If remedial action involves off-site
                                        transportation of hazardous waste.
Relevant and appropriate if remedial action involves
stockpiling, treatment, or disposal of hacardous
waste.  RCRA standard coven are not ARARi for
the mining residuals pile at the SCM - Plant II
TK34 facility. A detailed analysis of this
conclusion will be provided In a separate
submission to USEPA.
May be relevant and appropriate if units at the site
are operating under interim itmtus regulations.
RCRA standard covers are not ARARs for tl»e
mining residuals rile at the SCM - Plant IIT1CI,
facility.  A detailfd analysis of this concluiion will
be provided in a separate submission to USEPA.
    L.\DROOXrS\ft'"*l)l7\SECT)VTAOLE.)-)ttS-OM)
        Page  'Oaf 12

-------
'•&
    )TENTIAL ACTION-SPECIFIC ARARS
  FIELDS BROOK SITE - SOURCE OPERABLE UNIT
  VSIITABULA, OHIO
                        Requirement
                                                                      Potentially
                                                        Potentially    Relevant and
                                                        Applicable    Appropriate
                                       Commenli
 12.  Eiiiblishes • limetoble for restriction of land disposal of
     hmrdoui wuiei (OAC. Tllle 3743. Chapter 59J.
  Ohto Solid Wf ,,t pJTrTr|
 19. Establishes requirement* for lic*niln|. looting, constructing,
    operaiing, and clot in( of wild wuie facilities (OAC, Tllle
    3745. Chapffr 27J
                                                             Yes
                                                             Ye*
Ye*
fihip AfflMenl Air Oualltv Stand.^ ffifKj gy^lin.,

M.  Buabliihe* ambient air quality itandaidi for criteria
    pollutant* applicable in Ohio.  Requite* attainment with the
    Mndaidi through application of pollution control technique*.
    IOAC, Title 3745, Chapter 21)
                                                             Ye*
                      Applicable If the remedial action involves off-site
                      land disposal of hazardous waste.
Applicable if the remedial action involves the land
disposal of Industrial or municipal nonhazardous
•olid waste.
                      May be applicable if the remedial action chosen
                      involve*, air emissions of any criteria pollutants.
L \BROOKFftTMJ\FBI7\SECTJ\TADLE I.WM-OM;
                                                               Page  11  of 12

-------
POTENTIAL ACTION-SPECIFIC ARARS
FIELDS BROOK SITE • SOURCE OPERABLE UNIT
ASHTABULA, OHIO
 Other Ohio Air
     13. AmMemAlrStamiardi(OAC3743-l7.02(AX(B),aiid(C)
"I   16. ReitrkUoni of Fugitive Du«U (OAC 3745-17-08)
£   17. Control of Emission of VOCl(OAC 37^21^)9)
M    II. Ambient Air SUndudi of Lead and Inorganics.
        (OAC 3743.71-02 and -82-l2(A). (B), and (C))
  •   19. Stile Permit Requiremenu for Bmlnioni in Atuinment
        Areu (OAC 3745-31, «id 33)
     20. Slue Permit Requiremenu for Emluions in Prevention of
        Slinlficim Detericniion (PSD) AKM. (OAC 3704 and
        3745-17, IB, 21, and 71)
                                                     Ye»
                                                     Yet
                                                     Yd
                                                     Yes

                                                     Yei

                                                     Yei
    l\B»OOKPS\TMI\FBI7VSECTJ\TAOL6.3 l«l W»J
                                                         PagC 12 Of 12

-------
POTENTIAL ACTION-SPECIFIC ARARs
SURFACE WATER QUALITY STANDARDS
FIELDS BROOK SITE • SOURCE CONTROL OPERABLE UNIT
ASHTABULA, OHIO



*— 1*
Pwaarium Maul
AlttOUDUaiD Mflttl
Anenic Maul
Anaafclll Maul
Anenic V Metal
Barium . Metal
BoyliiuoV Mettl
Cadmium* Meul
Calcium Mettl
Chromium (Total)* Mettl
Chromium III Metal
CbnaiumVI Mettl
Cobalt Maul
Ira (Wai) Maul

Iran (oliMlved) Maul
Lead* Metal
Majnetium Metal
MMIUWM Mettl

mUAL CtrmiA
CWA AWQC fcr Fntecte of MM* Vtf
Aato
Vaaaa

750

360
850

130
5.7(33)

2300(8,500)

16



125(970)

Vaaaa

87

190
48

5.3
1.5(5.2)

2700400)

11

; ijno

4.9(38)

Water*
H*


^•JaJlP


IflOO
0068
10

170000

50

300

50
50
la*^

-------
                         ARARs
SURFACE WATER QUALITY STANDARDS  •
FIELDS BROOK SITE - SOURCE CONTROL OPERABLE UNIT
ASHTABULA, OHIO




Parameter Type

Mercury Meui
Nkk"' Metal
Sodium Meul
Varudium Mett|
ane' Meul
Chloroform Voletile
I.l.2.2-Tetnchloroethane' Volatile
1.1.2-Trichloroethane Volatile
1.2-Dkhloroethane' Volatile
I.l-Dkhloreethene' Volatile
Vinyl Chloride' Volatile
Tetnchloroethene' Volatile
Trichloroeihene (TCE) Volatile
1.2-Dlchlorobenune Semi-Volatile
1.2.4-TricNorobenzene Semi- Volatile
Mrt Arhtrvntwii •••••* * i • i i • .
nuKiuoroDeiUcnc Seml-VoliUle
He«achlorobuudiene' Semi-Volaiile
He»echloroethane' Semi-Volatile
FEDERAL CRITERIA
CWA AWQC for FnrtecUoa of Aqoatle Ufe'

Acute
Value

2.4
•1.900(7.400)


160(610)



118.000
11.600

5.280
45,000



90
980

Chronic
Value

0.012
210(820)


141(551)

2.400

20,000


840
21,900



9.3
540

Water*
Ftih
lafaetfoa
a 144
13.4




1.7

0.94
0.3J
20
0.8
27


.0072
4.5
1.9

nth
Consumption
Only
0.146
100




107

243
18.5
5.250
8.85
807


0.0074
500
8.74
STATE STANDARDS
Attainable or Detlfoaled Uie*
Aquatic Lift

Anil* Value

I.I
2.100(8.500)


160(600)

1,001

12.000
1.500

540
1.700
160
150



Chronic
Value
0.20
f. 232(940)


140(550)

360

3.500
78

7.'
73
II
77



Human Health

Fish*
Water
0.012
610


5.000

1.7

?.8
0.57
2.0
320
5.0


0.96
4.5
19
Fbh

0.012
4.600




107

990
32
5.250
3.500
80w
}
8
0.9W
xxa
87.4U
        .7\$ECTJ\TABLE.W«J-0».97
Page 7 of 3

-------
                 , ACTION-SPECIFIC ARARs
    SURFACE WATER QUALITY.STANDARDS
    FIELDS BROOK SITE • SOURCE CONTROL OPERABLE UNIT
    ASIITABULA, OHIO
Parameter Type
«-CMe«>.1.meihylphenol Send-VoUUIt
Wm-BAjrl-henyOphUwiM, Semi-Volatlle
PCS.' rcg
• FEDERAL CRTTBJUA
CWA AWQC for Protection of Aquatic Lift'
Acute
Value
2.0
Chronic
Value
0.014
Water*
ffch
iBfeetfM
DflQQ
0.00079
rah
CoMumptlOB
Only
90.000
0.00079
STATE STANDAWW
Attalubli or DtdtMM UM
Aqo»tle Life
AnrttViliN
MOO
Chronic
Valut
8.4
0.001
Huron Health
IWiA
WiUr
18
0
Fbh
59
0.00079
J   CWA - The federal Clean Water Act, Section 303.
    AWQC • Ambient Water Quality Criteria. eiubUihed pursuant to the Clean Water Act
    Qu«mlUe« are uprated In uj/l unlett otherwite noted.
     EPA. Water Quality Criteria for Protection of Aquatic Ufa. 1986.
    ' Carclnoieni; human health lundardi for thete parameter* are bated on a ritk factor of 10».                                                               herdnett
    •Hardnen dependent.  Valuei are for the Aihtatwla River and are bated on an awaja hardnen of 140 mf/L  The valuee given In paranlheit* are for Heidi Broc^ end •» bated on a naronw
       of700m|/l.
   L \SROOKFS\TMJ\raiMECTJ\TABLE >-4»3fl».«
Page 3 of 3

-------
   HBBMB^a^!^^^^*

   OTHER MA'
        : MATERIAL TO BE CONSIDERED (tBCs)
FIELDS BROOK SITE - SOURCE CONTROL OPERABLE UNIT
ASHTABULA, OHIO
               GuMellat, Standard, etc. TIC
    PCB Spill Policy, « 40 CFR 761.120 lo 761.139
                                                             Why Ihb to • TBC
                                                             aodootaoARAR
                                                                                                          ConuncnU
vl   Guidance on Remedial Actions for Superfund Sites with
    PCB Contamination, USEPA. August 1990

    RCRA Design Guidelines for capping


    RCRA Permit Writer's Guidance for TSD facillUes


    NPDES Best Management Practice Guidance (EPA 83/2-R-
    92-003 and 006; September 1992)
    CERCLA Site Discharges to POTWs (EPA 340/0-90/005;    •
    August 1990)                                        •
    Requirements for Hazardous Waste Landfill Design,
    Construction and Closure (EPA 623/4-89/022)
                                                        Not promulgated
                                                        The TSCA PCB Spill Cleanup Policy
                                                        b not • potentially applicable or
                                                        relevant and appropriate requirement
                                                        tor Superfund rapo&M Ktirai (tea 39
                                                        FR 62793-94)
                                                        Applies only to spills that occurred '• •
                                                       ' after May 4, 1987

                                                        Not promulgated
                                                        Guidance only

                                                        Not promulgated
                                                        Guidance only

                                                        Not promulgated
                                                        Guidance only

                                                        Not promulgated
                                                        Guidance only
                                                        Not promulgated
                                                        Guidance only
                                                        Not promulgated
                                                        Guidance only
To be considered if alternative includes
cleanup of PCB • contaminate*! soil
To be considered in reference to PCB
remediation activities

To be considered for alternatives that
Involve containment

To be considered for alternatives that
involve treatment, storage, and/or disposal

To be considered for alternatives that
include discharge of waste water and/or
norm water

To be considered for alternatives that
includ". itischarge of *«iie water and/or
storm wntrr to POTWs

To be considered for alternatives that
include containment
   L:\BROOKFS\TM *" '7\SECTJ\TABLE.J-5VM-0».»7
                                                          Page 1 of 2

-------
          MATERIAL TO BE CONSIDERED (TBCs)
 FIELDS BROOK SITE • SOURCE CONTROL OPERABLE UNIT
 ASHTABULA, OHIO
             GuhMlot, Standard, tte. TBC
          Why thai b • TBC
          and not an ARAR
             Comments
  Technical Guidance Document- Final Covers an
  Hatardotts Wute Landfills and Surface Impoundments
  (EPA 53WW-89-047; July 1989)

  TSCA's "Outdance Documenl for • 40 CFR 761.73
  L«»«TiU Application"

  Interim Guidance on non Non-Liquid PCB Disposal
  Methods to be uied u Altemativei to • 40 CFR 761
  Chemical Waste Lmdnil (July 3. 1990)

  RCRA Corrective Action Strategy, 61 FR.19.43" (1996)


  HWIR Contaminated Media Rule, 61 FR 18,780 (1996


  TSCA Spill Cleanup Policy (40 CFR 761, Subpait 0]
•   Not promulfaied
•   Guidance only


•   Not promulgated
•   Guidance only
• .  Not phMnulgaled
•   Guidance only

•   Not promulgated
•   Ouiduce only

•   Not promulgated
•   Guidance only

•   The TSCA PCB Spill Cleanup Policy
    U not • potentially applicable or
    relevant and approprltte requirement
    for Superfund mponM actions (tee 59
    FR 62793-94).
To be considered for alternatives that
include containment


To be considered for alternative* that
include landfllling of PCBs
To be considered for alternatives that
include disposal of PCBs
L VMOOKFS\TM)\FBIT\SECTJVTABLE.J.«» W-9J
      Page 2 of 2

-------
               FIELDS BBOQK SUFOEUD SITE
                    AahtabulA, Ohio
                                     N.
  FIGURED
LOCAnONMAP

-------
                                                                              Approximate Current
                                                                              Watershed Boundary
3

t
*ii


J
                                                                                                      figure te

-------
           Source Control Slto Map
(Industrial Portion of Reids Brook Watershed)

-------
E.2HL
                                                                 MIT OF
                                                                EXCAVATION AREA
LIMIT OF AREA
TO BE COVERED
                                                             LIMIT OF POTENTIAL
                                                             RESPONSE AREA
                      Acme Scrap Iron & Metal Company Site Map
                                    -

-------
          FIELDS BROOK
                                                                                      K« CONCENTRATION
                            NORTH TRAFFIC AREA
                                                                                      PC* CONCENTRATION
                                                                                      »Wmgta
   ACTIVE
PORTION OF 0
THE FACILITY
                                                                                   MINING
                                                                                  RESIDUALS
                                                                                    PILE
CONCRETE PAD
 (SOILS PILES)
                          PLANT
                         PROCESS
                          AREA
LAYDOWNAREA
                                  Milennium TiCI., Site Map

-------
ASHTABULA
  RIVER
                                                                                                   OOMMCSSM WUWO
                                                                                                EXCAVATION AREA

                                                                                                CONTAINMENT AREA
                                                Conrail Site Map

-------
                                RMI  SODIUM
                                  LANDFILL
                        APPROX EXTENT
                        OF DNAPL PLUME
               30"*
            0 CULVERT
TREATMENT
  AREA
 EXISTING
 SURF
  WATER
 HOLflme
  TANK
                                          APPROX EXTENT
                                          OF DNAPL PLUME
                             DETREX
                          CORPORATION
                  SLURRY WALL
                        CATALYST PIES
                        (PLANNED EXCAVATION)
                                         OUTFALL
                                      COLLECTION AREA
                       DETREX Site Map
                            ^

-------
              9 in. ou. vmHFco—
-------
                                                                       f)gg 717

                                  AREA TO BE
                                  EXCAVATED
                                (>10 ppn-'PCBs)
                                                                          RMI METALS
                                                                           BULDMQ
    APFROK
    AREA
>SO pan PCBs

-------
             EAST 21ST STREET
                  400FETT
                             AREA TO BE
                              COVERED
                                                              SCALE IN FEET
                                                                          RMI METALS
                                                                           BUILDING
AREA TO BE
EXCAVATED
  COVERED
                                                                      \
                                                                    RAILROAD
                           rhav^r*.
                             taJ

-------

-------
           ATTACHMENT 1 TO TWP RETPED OF nFTTSIfW SUMMARY

                        RESPONSIVENESS SUMMARY
                     SOURCE CONTROL OPERABLE UNIT
                            RECORD OF DECISION
                   FIELDS BROOK SITE, ASHTABULA OfflO
PITPPQSF.
This responsiveness summary has been prepared to meet the requirements of Sections
113(kX2)(BXiv) and 117(b) of the QMnprchensive Environmental Response, Compensation,
and liability Act of 1986 (CERCLA), as amended by the Superfund Ainemiingma and
Reauthorization Act of 1986 (SARA), which requires the United States Envir
Protection Agency (U.S. EPA) to respond to the comments submitted, either written or oral
presentations, on the proposed plan for remedial action. All comments received by U.S. EPA
during the public comment period were considered hi the selection of the final remedial
alternative for the Source Control Operable Unit

This document summarizes written and oral comments received during the public comment
period of July 24, 1997 to September 22,1997. The comments have been paraphrased to
efficiently summarize them in mis document. The public meeting was held at 7:00 p.m. on
July 31, 1996 in the Auditorium of the Asbtabula Campus of Kent State University in
Ashtabula Ohio. A full transcript of the public meeting, as well as all written comments
received during the public comment period and all site related documents, are available for
review at the Information Repositories, at the following locations: 1) Aahtuhiila County
District Library, 335 West 44th Street, Ashtabula, OH; and 2) U.S. Environmental Protection
Agency, Waste Management Division, Records Center, 7th Floor, 77 West Jackson Blvd..
Chicago, IL.                                                        •'
             •

Comment HI
ECKENFELDER, INC OB behalf of RMI Titanium Company	

ECKENFELDER, INC. comments that the proposed alternative for the Detrex facility should be
enhanced to provide better protection for the adjacent RMJ Sodium Plant  ECKENFELDER
noted that DNAPL has been detected in at least one groundwater monitoring well on the southern
side of the RMI Sodium landfill. RMJ and ECKENFELDER recommend the installation of one
or more DNAPL recovery wells in the vicinity of the southern edge of the landfill (in the general
vicinity of monitoring well RMI 2-S. Vacuum-enhanced extraction in horizontal wells should be
considered.

       Response:    ECKENFELDER and RMI are correct that DNAPL has been detected in
                   the groundwater on the RMJ property. ECKENFELDER and RMJ's

                          Responsiveness Summary - Page 1

-------
                   recommendations fell within the scope of the selected Detrex remedy.  The
                   number, placement and type of extraction wells will be determined during
                   the Remedial Design process.

Comment #2
ECKENFELDER. INC on bduut of BM1 Titanium Company	

ECKENFELDER, INC. notes that, based on pilot testing of the vacuum-enhanced extraction
system, the design radius of influence for the test well as approximately 20 to 30 feet. Based on
this data, Woodward-Clyde calculated a spacing of 40 to 60 feet between wells.
ECKENFELDER commented that, "if the spacing design is based on the radius of influence, then
the basis for the design is flawed. The radius of influence does not directly equate to the zone of
capture. In a situation in which there is a sloping water table, which is the case tt the Detrex site,
the groundwater capture zone would be significantly less than the observed zone of influence.
Additionally, due to higher viscosity and capillary forces associated with the surface tension of the
DNAPL-water interface, the effective capture zone of the DNAPL would be significantly less than
that of the groundwater capture zone. The Source Control-Feasibility Study (SCFS) states that
Alternative IV would reduce the size if the DNAPL plume through extraction and treatment and
which would reduce the potential for migration of the DNAPL compounds to Fields Brook or the
DS Tributary. Based on the information presented in the Proposed Plan and SCFS,
ECKENFELDER, Inc. questions the effectiveness of Alternative IV to meet t*"» remedial
objective."

       Response:    Comment noted. During the design of the Detrex remedy, U.S. EPA will
                   reevaluate the spacing and placement of extraction wells to ensure capture
                   of DNAPL. However, complete removal of DNAPL is not expected.

Comment #3^~
ECKENFELDER, INC on behalf of RMT Titanium Company	

ECKENFELDER, INC. notes that the slurry wall does not extend to the north of the Detrex
property and, as such would not prevent the migration of contaminants to the DS Tributary and
the RMI Sodium property. ECKENFELDER notes that the extent of DNAPL beneath the landfill
remains undefined. ECKENFELDER and RMI recommend additional investigation around the
perimeter of the landfill to assess the potential for DNAPL migration to RMTs property.
ECKENFELDER further recommends extending the shiny wad along the northern perimeter of
Detrex's property and, if DNAPL is identified along the northern perimeter of the landfill,
consideration should be given to the installation of DNAPL recovery wells in that area.

       Response:     U.S. EPA will require additional sampling during the remedial design phase
                    to better define the extent of DNAPL contamination that has moved into
                    the RMI property.  As stated on page 8-30 of the SCFS,
                           Responsiveness Summary - Page 2

-------
                         "Additional design investigations would be needed to establish
                         design criteria for the selected alternative. These investigations
                         may include shiny wall compatibility tests and additional
                         geotechnical borings to locate the depth and position of the
                         containment structures. Waste characterization to evaluate soil
                         disposal options -would be needed to locate off-site disposal
                         facilities.  Also, a pilot study to better evaluate DNAPL recovery
                         may be required during design. In addition, the extent of the
                         DNAPL phone particularly towards the northward direction onto
                         the RMI-Sodhanproperty in the vicinity of 'the landfill on RMI-
                         Sodium would'befurther definedduringdesign, and the position of
                         the extraction wetts and the slurry watt, if selected as components
                         within the final remedy would be adjusted or extended to ensure
                         that the DNAPL and contaminated groundwaterflowing towards
                         Fields Brook ortheDS Tributary particularfy along the northern
                         or western directions in these areas would be contained or
                         captured  Design investigation drilling or installation of
                         extraction weMswiU not be conducted in the area encompassed by
                          the RM1Sodium Landfill"

                   The nmnbcr md placement of DNAPL recovery wcDs win be determined
                   during remedial design. Depending on the placement of wells and the
                   resuhmg capture zone, U.S. EPA may require the shiny waO to extend
                   along the north boundary of the Detrex property.

Comment #4
AquAcTcr on behalf of Mfflenniam Inorganic Chemicals

The goal of the source control cleanup is to remediate areas that could potentially recontaminate
Fields Brook. AquAeTer notes that Millennium is committed to a cleanup which meets or
exceeds this goal.  A large portion of the Millennium facility drains to its Facility Storarwater
Collection Area (FSCA), which treats runoff prior to discharge under a National Pollutant
Discharge Elimination System (NPDES) permit. Outside of the FSCA, materials that erode have
the potential to recontaminate Fields brook. AquAeTer states that approximately 42% (by
volume) of the soils to be excavated do not have the potential to recontaminate Fields Brook and
notes that Millennium is demonstrating "good industrial citizenship" by its willingness to conduct
a cleanup which is more thorough and provides increased protection of human health and the
environment.

       Response:    Comment noted.
                            Responsiveness Summary - Page 3

-------
Comment #5
AauAeTer on behalf of MiDeanium Inorgank Chemicals
AquAeTer notes that the Proposed Plan Summary for the Millennium recommended alternative
states, "Annual O&M Cost: $2,011,000." AquAeTer commented that the annual OftM cost is
$43,000. The amount mentioned in the Proposed Plan ($2,011,000) is the sum of the indirect
capital costs for the alternative.

       Response:     AquAeTer is correct. The O&M amount stated in the Proposed Plan
                    summary is incorrect The ROD discussion of alternatives for the
                    Millennium source area lists the correct costs.

Comment #6
AqoAeTer OB behalf of MuTenninm Inorganic Chemicals	

AquAeTer references a statement in the Proposed Plan Summary, "Soils with PCB contamination
greater than or equal to 50 rug/kg are regulated by the Toxic Substances Control Act (TSCA)."
AquAeTer comments that PCB contamination at the Millennium Plant n facility is considered a
historical spin under TSCA. AquAeTer states that because U.S. EPA designated the entire
watershed ^ncH^^g the millennium she) as a Comprehensive Environmental Response,
Compensation, and Liability Act (CERCLA) she, the TSCA Office has no jurisdiction over the
current Millennhim she.

       Response:    Although the PCBs at the Millennium property may have been dumped at
                    the site prior to May 4,1997, TSCA is soil an applicable ARAR for the
                    CERCLA cleanup of the Fields Brook site. A strict interpretation of
                    TSCA as interpreted by the Standard Scrap decision would lead to the
                    conclusion that remediation of the PCB-contaminated soils would require
                    them to be removed from the improper disposal location and incinerated or
                    landfilled at a different she.

 Comment #7
 AquAeTer OB behalf of Millennium Inorgank Chemicals	

 AquAeTer notes that Millennium has proposed that its industrial waste landfill (currently under
 construction) be used for disposal of soils to be excavated from the Millennhim TiCl« facility.
 AquAeTer comments that the Millennium landfill has equivalent protection as would be provided
 by a TSCA chemical waste landfill.

        Response:    The Region V TSCA Office has reviewed the landfill information submitted
                    by AquAeTer (May 22, 1997 letter from HoIIiday and Corn to Van
                    Donsd).  TSCA has requested that additional information be provided in

                            Responsiveness Summary - Page 4

-------
                   order to complete its review of the Millennium landfill. Based on telephone
                   discussions between Van Donsd and Com, Millennium expects to submit
                   this information in early October, 1997.

Comment #8
AquAcTcr on behalf of Mfltennhim Inorganic Chemicals

The Proposed Plan states that, "chemical monitoring of outfalls would be conducted to evaluate
the amount of contamination moving from the she to Fields Brook." AquAeTer comments that
chemical monitoring of discharges from outfalls is neither required nor necessary. Millennium has
no effluent discharges to Fields Brook, therefore discharge monitoring should not be required.
Millennium's extensive monitoring of the faculty effluent within the last tea years (under the
NPDES permit program) has not detected PCBs. AquAeTer further states that, "the NPDES
permit program has determined mat it is not necessary for Millenniun. to test for PCBs in then-
discharge, and nehlier sho«ild the Proposed Plaan

       Response:           Comment noted. The Recontamination Assessment determined
                          that the only complete pathway for the movement of contamination'
                          is from the overland erosion of contanrnmtfid soil from areas
                          outside of the Facility Stormwater Collection Area (FSCA).  This
                          assumes the continued operation of the treatment system, with
                          sufficient capacity to handle storm events. Surface water from
                          within the FSCA is currently treated in the facility wastewater
                          treatment system and discharged to Lake Erie under a NPDES
                          permit. After the completion of the remedial action, sheet flow
                          runoffwitt be monitored for CUG exceedances.  The complete
                          monitoring program will be developed for the Operations and
 Comment #9
 U.S. Department of Interior - Trustee
 The U.S. Department of Interior (U.S. DOI) is one of three natural resource trustees for the
 Fields Brook she. The U.S. DOI is working with the Fields Brook Action Group in an effort to
 address the issue of natural resource damages. The U.S. DOI defers to the State of Ohio and the
 U.S. Fish and Wildlife Service to comment on the proposed alternatives for the Source Control
 Operable Unit  However, the U.S. DOI does request that U.S. EPA consult with the U.S. Fish
 and Wildlife Service and the appropriate State agency during remedial design to select a seeding
 mix and mowing regimen that will promote wildlife values consistent with erosion prevention and
 maintenance of remedial action.

       Response:    U.S. EPA will consult with U.S. Fish and Wildlife Service and the State of
                    Ohio on the recommended cover vegetation for source control areas to be

                            Responsiveness Summary - Page 5

-------
                   remediated. However, H is important to note that the Source Control
                   Operable Unit is within an industrial area and, in some cases, the response
                   areas are immediately adjacent to areas with frequent industrial activity.
                   Selection of cover vegetation will be most critical for the
                   FloodplauVWetland Operable Unit.

Comment #10
U.S. Department of Interior - Fish and Wildlife Service - Trustee	
The U.S. Fish and Wildlife Services comments that the Proposed Plan fails to provide a
justification for the recommended alternatives not meeting the "Statutory Preference for
       Response:    Section DC (Summary of Comparative Evaluation of Alternatives) of the
                    ROD discusses the "Statutory Preference For Treatment" as part of the
                    Balancing Criteria evaluation. Three source areas had contaminant levels
                    that warranted consideration of treatment.  The discussions of the
                    "Statutory Preference for Treatment" can be found on the following pages:

                           Acme Scrap Iron ft Metal           Page 36
                           Millennium                        Page 39
                           Detrex                           Page 45
Comment
U.S. Department of Interior - Fish and Wildlife Service - Trustee _

The U.S. Fish and Wildlife Service questions U.S. EPA's Proposed Plan recommendation for the
RMI Metals Reduction She.  U.S. EPA recommended Alternative in, which would excavate
soils with greater than or equal to SO ppm total PCBs and contain contaminated sotf with PCS
concentrations between 10 and SO ppm. Because of the location of the source area adjacent to a
Fields Brook tributary, the U.S. Fish and Wildlife comments that the U.S. EPA should select
Alternative IV, which requires excavation of all contaminated soil greater than 10 ppm PCBs.

       Response:    U.S. EPA agrees. After a review of the volume and cost estimates for tLe
                    RMI alternatives, U.S. EPA has selected Alternative IV in the ROD.
                    Based on current volumes. Alternative IV is less expensive than Alternative
                    m. In addition, with the costs of Alternatives DI and IV being relatively
                    comparable, it is preferable to select a remedy that does not rdy on O&M
                    for its long-term effectiveness. However, because it is unclear whether
                    further delineation will dramatically increase the volume of soil that would
                    require excavation under Alternative IV, the ROD allows the PRPs to
                    provide a justification, for U.S. EPA's consideration, that Alternative III
                    will provide significant cost savings over Alternative IV. U.S.  EPA

                            Responsiveness Summary - Page 6

-------
                   believes that Alternative ED would be a protective remedy if properly
                   implemented with the required O&M. Based on a cost justification from
                   the PRPs, the U.S. EPA may elect to change its selected remedy.

Comment #12
Citizen - Ms. Gloria McCarthy	.

Ms. McCarthy did not submit a comment on the proposed alternatives for the Source Control
Operable Unit at the Fields Brook Site.  Ms. McCarthy provided information concerning two
other facilities in the Ashtabula area with possible environmental violations.
                                       i
      Response:     The information provided by Ms. McCarthy will be forwarded to the Ohio
                    EPA, which wiD investigate Ms. McCarthy's concerns regarding the two
                    facilities. U.S. EPA will request that the Ohio EPA inform Ms. McCarthy
                    of the results of its investigation.

Comment #13                                      ~~
Citizen -Anonymous	^	

The anonymous letter did not include a comment on the proposed alternatives for the Source
Control Operable Unit The anonymous comment letter provided information about possible soil
contamination from the sand Masting of chemical storage barrels.

       Response:    A 104(e) information request letter is being prepared to gather data from
                    Detrex on past contracting for barrel cleaning services. In addition, a
                    104(e) information request letter is being prepared for the company who
                    allegedly performed the barrel cleaning for Detrex. U.S. EPA will
                    determine the appropriate follow-up based on the responses received.
                                  \

Comment #14
Cleveland Electric IHuminating Company  and Ohio Power Company	

Cleveland Electric Illuminating and Ohio Power comment that U.S. EPA should utilize a PCB
occupational cleanup goal of 3.1 at the Acme Scrap Site.  They state that, "U.S. EPA
recommends that Alternative VI be implemented for this facility, which would require excavation
and off-site disposal of surface soil with PCB concentrations greater than or equal to SO mg/kg.
Alternative VI would also require that soils contaminated with PCBs below 50 mg/kg be covered
in place to achieve the PCB residential cleanup  goal of 1.3 ppm at Fields Brook. The Millenium
[sic] TiCL4 Plant, which is located directly north of the Acme Scrap She and is contiguous to the
stormwater discharge to Fields Brook from the Acme Scrap Site, is subject to the PCB-
occupational-based goal of 3.1 ppm."

       Response:    U.S.  EPA has Devaluated the cleanup goals required for the Acme

                           Responsiveness Summary - Page 7

-------
                   property and determined that the facility should be subject to occupational
                   CUGs.
                            *
Comment #15
Cleveland Electric IDnmiamtiiiK Company «ad Ohio Power Company	

Cleveland Electric Illuminating and Ohio Power comment that technical information developed to
date as part of the SOU Design Investigation suggests that there may have been no historical
release of PCBs from the Acme Scrap facility to Fields Brook or the Fields Brook floodplain.
"The most common PCB at the Acme Scrap site is PCB aroclor 1260, with lesser amounts of
aroclor 1248 and 1254. However, aroclor 1260 has not been detected in Fields Brook or the
Fields Brook floodplain samples downstream of the discharge point from the Acme Scrap she.**

      Response:    U.S. EPA does not agree with the claim that the Acme property is not a
                    source of past contamination.  The analytical method used during the
                    investigation ( Method 8080) makes it difficult to differentiate between
                    PCB arodors and therefore extensive re-evaluation of site contaminant
                    data would be required to support such an argument  In addition, natural
                    weathering processes further complicate aroclor identification by changing
                    the aroclor distribution. Acme has been confirmed as a source of PCB-
                    contaminated oil in Fields Brook through Rhodamme B dye tests in storm
                    sewers and through comparative analyses of oil samples taken from the she
                    and Fields Brook.

                    U.S. EPA has documentation to support its claim that Acme burned
                    transformers, released oil into its sewer and contaminated its property.
                    Sampling conducted by the Ohio Department of Public Health in the early
                    1980*8 found PCB levels as high as 291 ppm total PCBs in water and oil
                    samples discharging from the storm sewer. U.S. EPA analyses in 1982
                    found soil contamination with up to 114 ppm PCBs, and discharge samples
                    with up to 189 ppm PCBs.  Additional documentation of she
                    contamination can be found in the Source Control Remedial Investigation
                    (SCRI) report.

                    Further, regardless of whether Acme is or is not a source of past
                    contamination, the Recontamtnation Assessment has shown that the
                    property is a potential source of future contamination and must be
                    addressed to prevent recontamination of the Brook.

 Comment #16
 Cleveland Electric Dluminaring Company and Ohio Power Company	

 The conunentors state that Alternatives n, m and IV will fully comply with ARARs and should
                            Responsiveness Summary - Page 8

-------
be reconsidered and recommended by U.S. EPA. Since the route for releases of PCBs is via
stormwater discharges which might carry PCB~contaminated sediment off-she, the use of
stonnwater controls and/or covers would be sufficient to prevent the movement of PCBs into the
Brook.

       Response:     U.S. EPA agrees that the pathway for movement of PCS contamination is
                    via erosion and run-off from the she. However. U.S. EPA disagrees with
                    the commentors' statement that alternatives n, in and IV fully oomph/ with
                    ARARs. TSCA is an ARAR for the cleanup at the Acme property and the
                    berms and/or covers specified in Alternatives n, m and IV do not satisfy
                    the requirements of TSCA for the management and containment of soils
                    with PCB concentrations greater than or equal to 50 ppm. To accept
                    these alternatives, the U.S. EPA would have to waive TSCA and show that
                    these alternatives would be protective and would not present unreasonable
                    risks to health and the environment U.S. EPA does not believe that the
                    stormwater controls and covers specified in Alternatives n, ffl, and IV
                    meet this standard for soils containing greater than or equal to 50 ppm total
                    PCBs.

 Comment #17              !
 Cleveland Electric fflumnuitinti Company said Ohio Power Company

 Cleveland Electric Illuminating Company and Ohio Power Company comment that U.S. EPA
 should allow modifications to the remedial response area in the final engineering design. The
 commentors state that the remedial design process should be flexible and allow the optimization
 of the remedial response area and consolidation. The commentors also note that no outfall
 monitoring has been proposed for Alternatives ffl, IV, V, VI and that outfall monitoring would be
 conducted by the she owner/operator pursuant to any monitoring obligations imposed under any
 Ohio NPDES permit for the she.

       Response:    The Soi  :e Control ROD does notsdect designs for the remedial response
                    areas. The ROD selects the technologies (Le., excavation, erosion control
                    covers) required to meet the goal of the cleanup, which is to prevent the
                    recontamination of the Brook.  The remedial response area at the Acme
                    site will be re-sized and reconfigured during remedial design based on the
                    results of soil loss equations, the degree of consolidation, and, to the extent
                    possible, practical considerations to accomodate the continued operation of
                    the facility. The selected remedy provides this flexibility.

                    The commentors noted that outfall monitoring was not proposed for
                    Alternatives ffl, IV, V. and VI and that outfall monitoring would be
                    performed by the owner/operator pursuant to NPDES requirements. U.S.
                    EPA agrees that the SCFS did not require outfall monitoring.


                            Responsiveness Summary - Page 9

-------
                   The monitoring programs for the source control areas are to be developed
                   during Remedial Design, as part of each facility's O&M Plan. Sufficient
                   monitoring must be included to demonstrate that contaminant movement
                   from each source area is not resulting in CUG exceedances in Brook
                   sediment.  The location and frequency of monitoring at Acme is dependent
                   on the configuration of the final design.

Comment #18
Cleveland Electric MuminatinR Company and Ohio Power Company	

The commentors note that the she must be setured before remedial measures can be implemented
and maintained. If Acme is to remain in operation at the site, both physical (remedial) and legal
(institutional controls, including caed restrictions) must be implemented to ensure that the site is
properly maintained.  The ROD should include a statement that the she owner/operator will be
solely responsible for recontaminah'on of the site in the future.

       Response:    U.S. EPA agrees that physical and legal controls must be utilized to ensure
                   that the remediation is not "un-done" by future actions at the she, thus
                   causing the recontamination of the Brook.  However, the ROD is not the
                   proper mechanism for assignments of liability.

Comment #19
Cleveland Electric Muminating Company and Ohio Power Company	

The commentors note that the Final Remedial Action should be modified, as needed, to take
account of she drainage requirements. "There has been limited investigation or study of the
drainage system for the Acme Scrap Site, and little indication of how stormwater runoff is to be
handled.  It will be necessary to address these matters in the site grading and drainage plans.  It
may be cost-effective, and equally protective of human health and the environment, to modify the
remedy which is ultimately selected in the final design phases before the remedial action is
implemented. USEPA should allow modifications to the alternative which is ultimately selected
by USEPA if considerations of site drainage and stormwater runoff suggest that a more cost-
effective approach can be implemented to contain or control stormwater  discharges from the
site."

       Response:    U.S. EPA agrees with the commentor that a plan for she drainage has not
                    yet been developed.  That is an element of the Remedial Design process.

                    The commentor also requests that the alternative be modified if a more
                    cost-effective approach can be found to control stormwater discharges
                    from the she.  U.S. EPA disagrees with the commentors request that the
                    alternative may be changed during the remedial design/remedial action
                    phase. The ROD requires excavation of soils with equal to or greater than

                           Responsiveness Summary - Page 10

-------
                   SO ppm total PCBs.  The remaining contaminated soil will be covered with
                   an erosion control cover, as described in the ROD, to the extent necessary
                   to ensure that soil losses from the site do not exceed occupational CUGs.
                   The site will be graded to allow for proper drainage. The remedial design
                   may include consolidation of soils prior to placement of the cover.

                   It is not anticipated that the basic dements of the ROD will change during
                   the remedial design/remedial action process. The U.S. EPA has
                   determined that the use of an erosion control cover is preferable to erosion
                   control measures mat do not make use of a cover (i.e., Alternative ITs use
                   ofberms). Any change^ that would not include the erosion control cover
                   would require a ROD Amendment or Explanation of Significant Difference
                   to document the deviation from the remedy selected in this ROD.

Comment 020
Cleveland Electric fflumuMtinK Company and Ohio Power Company	

The commentors state that flexibility should-be allowed in performing remedial work on the South
Sewer System. "USEPA has recommended Alternative m for remedial action on the sewer
system winch extends south of Fields Brook ("the South Sewer"). Alternative in involves
grouting the existing 30 inch sewer on the Acme Scrap she, which extends from the on-site
lagoon northwest to the intersection of State and Middle Road, and constructing a new 30 inch
on-site sewer. Alternative DI would also require that the storm sewer (qrtfapatEd to be a 36 inch
or 48 inch sewer), which travels parallel to State Road from the Acme Scrap she to Reids Brook,
would be cleaned of sediments and repaired, if necessary." The commentors note that very little
is known about these sewers and replacement may not be necessary.  The commentor suggest the
following language, "Replacement sewers, if determined to be necessary, would be constructed..."

      Response:   U.S. EPA agrees. Based on current information, h is premature to require
                   replacement of the sewers. Additional evaluation of the condition of the
                   sewers should be pejorated during remedial design to determine whether
                   cleaning or replacenumt would be most cost-effective. The Agency's
                   selection of Alternative HI provides the necessary flexibility. Replacement
                   sewers will be constructed only if necessary.

Comment 021
Cleveland Bectrk Dlnminating Company and Ohio Power Company	

The commentors note that the condition of the Defense Plant Building may necessitate a
modification of the selected remedial action.  "Portions of the silos located on one side of the
plant have partially collapsed, and the condition of the building may pose a safety risk to the
performance of remedial work, especially the implementation of Alternative VI." Because the
building "is in poor repair and may be structurally unsound," the U.S. EPA should allow the work


                           Responsiveness Summary - Page 11

-------
to be modified to accomodate the possible partial or complete demolition of the Defense Plant
building and associated structures.

       Response:    U.S. EPA agrees that the remedial design should accomodate any actions
                   to be taken to address stability issues at the former defense plant building.
                    In fact, the ROD requires that the site be secured before work can proceed.

Comment #22
Woodw«rd-Ctyde on behalf of the Fields Brook Action Group (FBAG)	

Regarding page 4, last paragraph, of the Proposed Plan, Woodward-Clyde notes that the FBAG
did not identify five properties in the FS.  The FS identified surface soil as a potential source for
remedial alternatives at the Acme, Millennium and Detrex facilities.  USEPA required that the
FBAG include alternatives for the RNfl Meals and Conrail facility."

       Response:    The commentor is correct.

Comment #23                  '^
Woodward-Clyde on behalf of the Fiddi Brook Action Group (FBAG)	

Regarding page S, third paragraph, of the Proposed Plan, Woodward-Clyde notes that cleanup
goals were not "calculated to reduce the movement of contanriniition from erosion and runoff."
The commentor suggests more appropriate language, "Cleanup goals were calculated in order to
provide assurance that movement of potentially contaminated sofl and sediment on the source
properties would not be sufficient to recontaminate Fields Brook sediment following the
remediation of Fields Brook."
                                                    •
       Response:    The commentor's recommended language is dear than that used in the
                    Proposed Plan.

Comment #24
Woodward-Clyde on behalf of the Fields Brook Action Group (FBAG)	

 Regarding pages "Acme-2" and "Acme-3" of the Proposed Plan, the commentors state that no
 outfall monitoring was to be included in Alternatives in, IV, V and VI.  "No outfall monitoring
 was to be included in this alternative.  The only chemical monitoring that was described in the FS
 includes the annual collection of surface soil samples for PCB analysis. Sampling was to continue
 for a 5-year evaluation period."

       Response:    The commentor is correct that the FS did not describe surface water
                    monitoring. Monitoring will include the sampling and analysis of soil and
                    sediment to demonstrate that erosion from the Acme property is not
                    causing exceedances of occupational CUGs. Specifics of the monitoring

                            Responsiveness Summary - Page 12

-------
                   program will be developed as part of the Operations and Maintenance Plan.

Comment #25
Woodward-Clyde on behalf off the Fields Brook Action Group (FBAG)	

Regarding page "Acme-3" of the Proposed Plan, the oommentors note tint incineration is not
mentioned in the FS and is only one form of thermal treatment.

       Response:     Comment noted.

Comment #26
Woodward-Clyde on behalf of the FieMi Brook Action Group (FBAG)       	

Regarding page "ConraiM" of the Proposed Plan, the commentors note "that the portion of the
property that lies in the Fields Brook watershed is nfii shown as the shaded area on the map in the
PRAP as stated. The map provide [sic] in the PRAP illustrates the potential remedial response
area designated in the Feasibility Study, and not the entire portion of the Conrail property which
lies in the Fields Brook watershed. It should be noted that Conrail performed a Recontamination
Assessment that indicated runoff would not recontaminate Fields Brook sediments."

       Response:    The commentor is correct that the shaded area on die figure is the potential
                    remedial response area. U.S. EPA is aware that the Recontamination
                    Assessment indicated that Conrail runoff would not recontaminate Fields
                    Brook sediments. However, because of concerns about the proximity of
                    the Conrail facility to the Brook, U.S. EPA utilized best professional
                    judgement in its decision to evaluate alternatives and ultimately require
                    remedial action at the property.

Comment #27                         .
Woodward-Clyde on behalf of the Fields Brook Action Group (FBAG)	
 Regarding page "Conrail-2" of the Proposed Plan, the commentors note that the correct capital
 cost for Alternative TV is $19,500 not $19,800.

       Response:    Comment noted.

 Comment #28
 Woodward-Clyde on behalf of the Fields Brook Action Group (FBAG)	

 Regarding page "Conrail-2" of the Proposed Plan, the commentors note that the correct 30-year
 present worth cost for Alternative V is $173,100 not $173.000.

       Response:    Comment noted.

                           Responsiveness Summary - Page 13

-------
Comment #29
Woodward-Clyde on behalf of the Fiddi Brook Action Group (FBAG)	

Regarding page "Detrex-l" of the Proposed Plan's discussion of Alternative 1 (No Action), the
conunentors state, "The PRAP references stonnwater outfidl sampling to evaluate the amount of
contamination moving off the property and into Fields Brook. The FS did not describe surface
water monitoring."

       Response:     The commentor is correct that the FS did not describe surface water
                    monitoring.  Specifics* of the monitoring program will be developed as part
                    of the Operations and Maintenance Plan, and wifl likely include soil,
                    sediment, and groundwater sampling and analysis. Sufficient monitoring
                    will be required to demonstrate that contamiraw* movement from the
                    Detrex property is not resulting in CUG exceedances in the Brook.

Comment #30
Woodward-Clyde on behalf of the Fields Brook Action .Group (FBAG)     	
                                     "s
Regarding pages "Detrex-2" and "Detrex-3" of the Proposed Plan, die commentors note that
Alternatives HA, OB, m and IV also include "the characterization and disposal of approximately
100 cu. yards of catalyst material located in a pfle in source area DET6. In addition, sediment
from the retention pond and ditches on the northern property would be removed. Post
remediation monitoring will extend for at least a S year period and then be re-evaluated to
determine appropriateness for extending monitoring."

       Response:    U.S.  EPA agrees. The necessary detail is included for the remedy selected
                    in the ROD.

Comment #31                          "
Woodward-Clyde on behalf of the Fiddi Brook Action Group (FBAG)    	
••^^^•••^•^^••^^•^•••••^•••'•••^•••••••^^^^••^••^•^•Mi^^^MIMAa^BM^H^MH^^^^^^^M^^B^HVBB^^^VVBi^HMV^BMaa^b^^MB^MHMBB^H^MPM^MMMaMVM^B^HBHaM^BIMi^^HnHBa «•

The commentors note that the Proposed Plan's discussion of RMI Alternatives n, m, and IV did
not indicate that post remediation monitoring will extend for at least a 5-year period and then be
re-evaluated to determine appropriateness for extending monitoring.

       Response:    U.S. EPA agrees. The necessary detail is included for the remedy selected
                    in the ROD.

 Comment #32
 Mark W. Andrews representiiut Acme Scrap Iron & Metal Company          	

 The commentor states, "Acme continues to believe that the scope of the remediation
contemplated by Alternative VI is an ultra conservative approach to the problems that had

                            Responsiveness Summary - Page 14

-------
occurred in the past at the Acme she. Acme has been told by the U.S. EPA that h has the least
contaminated property in the Fields Brook Superfimd Site, and yet it is the only property which is
being subjected to the residential standard for PCB's. This is particularly concerning in view of
the tact that (1) most of the detectable amounts of PCB's at the Acme site are located in the top
six inches of soil, and the minimal amounts of PCB's are not likely to migrate; (2) Reids Brook
does not traverse through the Acme operation, or any part of the property owned by Deha
Associates, Ltd., as it does through the other properties in the Superfimd site; (3) the only source
for future contamination of Reids Brook by Acme would have to involve surface water "nut-off*
which could possibly flow through the interrupted storm sewer system, which is regularly
monitored for PCB's, and consistently shows no detectable levels of PCB's; and (4) Acme has not
handled regulated substances for more than a decade, and has absolutely no intentions of doing so
in the future."

       Response:    U.S. EPA does not believe that Acme is the "least contaminatod property
                    in the Fields Brook Superfimd She."  This statement is not supported by
                    she data.

                    Although U.S. EPA has reevahiated the cleanup goal requirements for
                    Acme and determined that occupational CUGs must be met at the Acme.
'   *                 property, Mr. Andrews is incorrect in his statement that Acme wis the only  .
                    property which is being subjected to the residential standard fbrPCB's."
                    The U.S. EPA is requiring that residential CUG« be met at the following
                    locations: Conrafl, RMI Metals, and the Detrex outfall

                    Regarding the presence of PCBs in surface soil, U.S. EPA believes that Mr.
                    Andrews is confusing two different mectiamyng of contaminant transport.
                    Mr. Andrews states that PCB contamination is primarily in the upper 6
                    inches of soil and is not likely to migrate. When migration is discussed, h
                    is usually referring to the movement of contaminants independent of soil or
                    sediment particles. For example, solvent contamination in soils win
                    generally migrate, meaning h will travel with groundwater and move
                    through soil.  Although PCB contamination generally does not migrate
                    because the contaminants bind to the soil particles, the addition of other
                    contaminants into the system (such as solvents) can mobilize PCBs and
                    result in the migration of PCB contamination.

                    Mr. Andrews states that the storm sewer system is monitored for PCBs and
                    consistently shows no detectable levels of PCB's.  The Acme faculty has
                    had an NPDES permit since 1986. and the discharge of PCBs is prohibited.
                    According to the SCRI report, Mr. Tackett has stated that Acme is in
                    compliance with its NPDES permit limits.  U.S. EPA is pleased that the
                    monitoring has apparently shown that Acme is complying with NPDES
                    requirements. However, according to the evaluation of the Acme property,


                            Responsiveness Summary - Page 15

-------
                   there is still a risk that contamination from the Acme property could
                   recontaminate Fields Brook in excess of CUGs. The implementation of the
                   remedial action will ensure the reduction of contaminant movement off-
                   site.

                   The concern at the Acme property is the erosion of contaminated soil and
                   its movement into Fields Brook.  Although the Acme facility is not adjacent
                   to the Brook, contamination from the Acme faculty can enter the Brook
                   from the Acme sewer. The presence of the contamination in the surface
                   soil causes this material to be subject to erosion. The implementation of
                   the remedial action will ensure that erosion from the she will not result in
                   the recontamination of the Brook.

Comment #33
Mark W. Andrews representing Acme Scrap Iron A Metal Company	

Mr. Andrews states that Acme agrees that there are "small areas of contaminated soil on its
property." He further states that, "This contaminated soil must be removed and properly disposed
of.  Acme does not believe H is necessary to contain the remaining areas where the presence of
PCBs have been detected in minimal amounts that would normally be acceptable under industrial
standards, especially where the containment and fencing would render an otherwise productive
parcel of industrial property useless for all intents and purposes."

       Response:    U.S. EPA disagrees with Mr. Andrews that the contaminated areas could  '
                   be characterized as "smafl."  Mr. Andrews states that it should not be
                   necessary to contain low-level PCB contamination in site soils since the
                   levels would normally be acceptable under industrial standards. U.S. EPA
                   does not agree with Mr. Andrews assertion that containment should not be
                   necessary after excavation.  Most industrial standards are designed to
                   protect workers and do not address ecological concerns or the movement
                   of contamination into an area with other types of exposures,  rhe cleanup
                   at the Acme property is being performed to prevent recontamination of the
                   Brook. The extern of the area to be covered win be primarily determined
                   by soil loss calculations.

Comment #34
Mark W. Andrews representing Acme Scrap Iron A Metal Company	

Mr. Andrews states that Acme has always cooperated  with U.S. EPA in its endeavor to remediate
the Fields Brook site. He also notes that, "Acme is now righting for its business life to enable it to
continue to employ its workers and serve its customers.**

       Response:     Comment noted.  Based on current information, U.S. EPA does not believe


                           Responsiveness Summary - Page 16

-------
                   that the performance of the cleanup will require Acme to permanently
                   cease its operations at its current location. There is sufficiently flexibility in
                   the ROD for the development of a design that can accomodate Acme's
                   continued operation.

Comment #35
Alternative Proposal for Site Remediation, submitted by Mark W. Andrews representing
Acme Scrap Iron A Metal Company _ ._ _

On behalf of Acme, Mr. Andrews presented an alternative proposal for remediation of the Acme
facility.  The alternative included the foOowufg' components:

•     Excavation and off-she disposal of soil with FOB concentrations exceeding SO ppm.
      Excavation would be to a depth of 6 inches to 1 foot Backfill with clean material.

•     Excavate remaining contaminated material on the north of the property and stock pile into
      an earthen benn north of Acme's area of general operations.  Excavate to a depth of 6
      inches and backfill excavated areas. .For aesthetic reasons, cover mound with topsoil and
      seed. Benn will be parabolic in shape and approximately 200 feet long, 45 feet in width,
      and 10 feet in height Note that the figure provided with the proposal identifies
      significantly different dimensions.

•     Excavate remaining contaminated material on the south of the property and stock pile into
      an earthen benn south of Acme's area of general operations.  Excavate to a depth of 6
      inches and backfill excavated areas.  For aesthetic reasons, cover mound with topsoil and
      seed. Benn will be parabolic in shape and approximately 800 feet long, 40 feet in width,
      and 10 feet in height. Note that the figure provided with the proposal identifies
      significantly different dimensions.

•     The bermswOl  act as a natural surface water barrier and wiO contain PCB contaminated
      soil.

       Response:    U.S. EPA has evaluated the proposal and hopes that the Agency can work
                    with Acme during the design process to meet the goal of the source control
                    cleanup and, to the extent practical, accomodate Acme's operations. U.S.
                    EPA is pleased that Acme is willing to excavate sofl containing greater than
                    50 ppra total PCBs. However, U.S. EPA would like to note that TSCA
                         itCT soils with contaminant levels equal to or greater th*n SO ppm.
                    U.S. EPA supports the concept of consolidation. However, the movement
                    of all areas of contamination is quite dramatic.  The extent of consolidation
                    (if any) and ulrinntg location of containment areas will be developed during
                    remedial design, after the remedial response area is reconfigured to address


                            Responsiveness Summary • Page 17

-------
                   the change in the CUG requirement (from residential to occupational).

                   The dimensions and cover specified for the earthen benns proposed by
                   Acme do not appear to be workable. The cleanup is meant to prevent the
                   erosion of contaminated soils. The slopes of the earthen benns would be
                   too steep to effectively control erosion, especially with a limited soil cover.
                   The remedial design for the Acme site must include the erosion control
                   cover specified in the ROD. A larger area of the Acme property will likdy
                   need to be allotted for containment of contaminated soil.
                   The proposal •gfopnttf that only 6 inches of soil will need to be excavated
                   in areas of low-level contamination. The ROD assumes 1 foot of
                   excavation. A re-evaluation of the data during remedial design and
                   possible confirmatory sampling during remedial action will likely be needed
                   to ensure contaminated soils have been addressed.

                   The evaluation of the source control properties and the preparation of
                   SCRI and SCFS documents occurred over a period of years.  U.S. EPA
                   believes that had Acme been more actively involved in the Superfund
                   process, its concerns could have been more readily addressed in the
                   conceptual design of alternatives presented in the SCFS. Acme's
                   involvement in the Remedial Design process is critical to the
                   implementation of a Rfnwfinl Action that can accommodate Acme's
                   continued operation at the she.

Comment #36
Mr. Bradley Schneider of ENCORE Environmental in Rochester, Michigan _

Mr. Schneider commented on the remedy selected for the Floodplains/Wetlands Site (Operable
Unit #4) and recommends the addition of a bioremediation program. He asks that U.S. EPA
contact his telemarketing specialist if there is interest in the services that ENCORE could provide.

      Response:     !*he remedy for the Floodplains/Wetland Operable Unit has already been
                    selected. The inclusion of a bioremediation program to reduce PCB
                    concentrations in soils n**4 sediments does not seem warranted at this time
                    for either the Floodplains/Wetlands or Source Control Operable Units.

Comment #37
Mr. Steven Kellat, Edgewood Senior High School _

During the public meeting, Mr Steven Kellat, a student at Edgewood Senior High School,
provided an oral comment on the Proposed Plan for the Source Control Operable Unit.  Mr.
Kellat stated that he supports U.S. EPA recommendations. However. Mr. Kellat stressed that his


                           Responsiveness Summary - Page 18

-------
position was presented as an individual and does not represent the position of his school's Student
Council unless ratified by said Student Council. Mr. KeDat also recommended that fences be
properly constructed and routinely inspected and that U.S. EPA consider the use of guards during
Remedial Action.

       Response:     U.S. EPA is pleased that Mr. Kdlat supports U.S. EPA's recommendations
                    for the she. Fencing wfll be required to restrict access to containment
                    areas,  and the inspection and upkeep of the fences wiU be required as part
                    of she Operation and Maintenance (O&M)  U.S. EPA wiU consider the
                    use of guards during Remedial Action. However, it may not be necessary
                    to add additional security since many of the companies involved already
                    employ security guards for their acuities.

Comment #38
Mr. Donald R. Schrcgardus, Director of the Ohio Environmental Protection Agency

The Ohio Environmental Protection Agency (OEPA) does not agree with the overall risk
management approach used at the Fields Brook she. In his comment letter, Mr. Schregardus
states that, "source control remedies should be based on managing risk at each individual source
area by following die usual process of evaluating risk by all appropriate pathways and developing
cleanup goals based on she risk." The OEPA also does not support the way that potential source
areas were screened relative to pathways of contamination to the Brook and how the source
control cleanup was Bruited to those areas which could result in CUG exceedances in Brook
sediment.

       Response:    The U.S. EPA has elected to limit the scope of the source control cleanup
                    to those areas that could potentially  recontaminate Fields Brook sediment.
                    This was a practical decision. The Fields Brook Superfund She is very
                    large and complex. Expanding the Source Control OU cleanup beyond its
                    current scope would be unwieldy and result in extensive delays in the
                    Sediment and
                    The Remedial Investigation evaluated approximately 200 source areas and
                    six areas were ultimately carried forward in the Source Control FS and this
                    ROD for remediation to prevent lecontamination of Brook sediment.
                    Contamination is unfortunately aU too common in industrial areas, and it is
                    not reasonable to expect the Fields Brook Superfund action to prepare
                    individualized risk assessments for each of the 200 source areas evaluated
                    and to enforce and/or fund cleanups at all of these sites. The US EPA
                    believes that the scope of the Source Control OU cleanup is appropriate.
                    Source control areas that would not result in Brook CUG exceedances
                    should be handled independent of the Fields Brook Superrund action.
                            Responsiveness Summary - Page 19

-------