PB98-963157
                               EPA 541-R98-189
                               March 1999
EPA Superfund
      Explanation of Significant Difference
      for the Record of Decision:
      Reilly Tar & Chemical
      (Indianapolis Plant)
      Indianapolis, IN
      10/6/1997

-------
                  EXPLANATION OF SIGNIFICANT DIFFERENCES

                   REILLY TAR & CHEMICAL SUPERFUND SITE
                              INDIANAPOLIS, INDIANA
I      Introduction

The Reilly Tar & Chemical Superfund Site (the Reilly site) is located at 1500 South Tibbs Avenue
in the southwest quadrant of Indianapolis.  Minnesota Street divides the 120 acre property into
two parcels.  The Oak Park property is located north of Minnesota Street and occupies
approximately 40 acres. The Maywood property is located south of Minnesota Street and
occupies approximately 80 acres.

The U.S. Environmental Protection Agency (U.S. EPA) and the Indiana Department of
Environmental Management (IDEM) have jointly overseen cleanup activities at the Reilly site
under the authority of the Comprehensive Environmental Response, Compensation, and Liability
Act of 1980, as amended (CERCLA), 42 U.S.C. Section 9601, et seq  U.S. EPA and IDEM
entered into a Consent  Decree with Reilly who agreed to perform the remedy for OU 2 at the site
That Consent Decree was entered by the U.S  District Court for the Southern District of Indiana
on February 6, 1995  The Consent Decree requires Reilly to implement the remedy selected by
U.S. EPA (with  IDEM's concurrence) in a September 30, 1993 Record of Decision (ROD)  That
Consent Decree and the accompanying documents will be modified, to the extent necessary, to
reflect the remedy changes described in this Explanation of Significant Differences (ESD)

Reilly has designed and implemented the final remedy for OU 2 at the site under US  EPA and
IDEM  oversight. During the implementation process, newly discovered information has
persuaded US. EPA and IDEM that certain technical modifications and improvements to the
selected remedy are appropriate.  Section 117(c) of CERCLA and Section 300 435(c)(2)(I) of the
National Oil and Hazardous Substances Contingency Plan establish procedures for explaining,
documenting, and informing the public of significant changes to the remedy that occur after the
ROD is signed.  An ESD is required when the remedial action to be taken differs significantly
from the remedy selected in the ROD but does not fundamentally alter that remedy with respect to
scope,  performance, or cost. This ESD and supporting documentation shall become part of the
administrative record file which is available at  the Indianapolis Public Library (48 East St  Claire)
and at the U.S EPA regional office in Chicago, Illinois (77 W. Jackson Blvd, 7th Floor), during
normal business hours.

-------
II      Summary of Site History, Contamination Problems, and Selected Remedy

A      Site History

Industrial development of the Reilly site began in 1921 when the Republic Creosoting Company
(which later became Reilly Tar & Chemical, which in turn became Reilly Industries, Inc.) started a
coal tar refinery and a creosote wood treatmenttJperation on the Maywood property. On-site
wood treatment operations occurred from 1921 until 1972  Beginning in 1941, several chemical
plants were constructed and operated on the Oak Park property Environmental problems at the
site are related to the management and disposal of creosoting process wastes and to wastes
associated with and substances used in the process of manufacturing custom synthesized specialty
chemicals.

In 1984, Reilly Tar was listed on U.S. EPA's National Priorities List (NPL), a roster of the
nation's worst hazardous waste sites, making it eligible for cleanup under the Superfund program
In 1987, the potentially responsible party (Reilly) agreed to conduct a remedial investigation (RI)
to characterize the nature and extent of contamination at the site, and a feasibility study  (FS) to
evaluate and compare remedial alternatives according to the terms of an Administrative  Order on
Consent between the U.S EPA and Reilly Tar & Chemical

In 1989, Reilly Tar & Chemical changed their corporate name to Reilly Industries, Incorporated,
under which they operate today.

In June, 1992, a Record of Decision was signed by the Regional Administrator for the first
operable unit at the site, calling for a groundwater extraction/treatment/discharge system to be
installed to contain the migration of groundwater contaminated by the site at the site boundary

In September,  1992, Reilly agreed to incorporate RCRA corrective action requirements into
existing site studies according to the terms of an amendment to the existing Administrative Order
on Consent between the U.S  EPA and Reilly Tar & Chemical

B      Contamination Problems

A detailed analysis of past operations during Task 2 of the Remedial Investigation demonstrated
that there are at least five former waste disposal areas onsite  These five former waste disposal
areas were identified as potential source  areas for both on-site and off-site contamination  These
include the Lime Pond on the Oak Park property, the Abandoned Railway Trench on the northern
portion of the Maywood property, the Former Sludge Treatment Pit on the northern portion of
the Maywood property, the Drainage Ditch on the southern portion of the Maywood property
and the South Landfill on the southern portion of the Maywood property (See Figure 1)  This
task also identified groundwater as a primary area of investigation for the RI.

-------
The Lime Pond was a lagoon constructed in 1953 to receive waste discharges from the first
synthetic pyridine base processing unit constructed on the Oak Park property  Dimensions of the
Lime Pond are approximately 350 feet by 350 feet Until  1965, discharges from process areas on
the Oak Park property went to the Lime Pond, which included solid material and sludge that had
settled out of the waste water discharged to the Lime Pond area Since 1965, when a connection
to the city sewer was made, the Lime Pond has received only water from boiler blowdown from
the boiler operations on the Oak Park property

Buried drums were discovered during the RI soil borings at the Lime Pond  These drums were
encountered at locations to the east and southeast of the lime pond during soil boring activities
A magnetometry survey was immediately conducted which highlighted several areas to the north
and east of the lime pond where buried metallic debris such as drums may be located.  A drum
removal plan was prepared and its requirements were incorporated into the amended
administrative order on consent signed in September, 1992  This plan called for the investigation
of the areas identified by the magnetometer survey and if drums were unearthed, they were to be
removed.  A total of 149 drums were removed during field activities in November  1992 The area
from where the drums were excavated is referred to as the Lime Pond Drum Removal area and is
one of the areas addressed by the September 1993 ROD

Borings in the Lime Pond generally encountered lime sludge from the pond surface to a depth of
four to seven feet. The Lime Pond contains on the order of 15,000 cubic yards of lime sludge
generated from boiler blowdown (water used for cooling of boilers that does not come into
contact with production of chemicals). This lime sludge generally contains less than one part per
million total  organics.

The soils to the north and east of the Lime Pond, in the Drum Removal Area, were found to be
contaminated with volatile organics up to levels of approximately 5,522,000 parts per billion
(ppb) and semi-volatile organics up to levels of approximately 9,870,000 ppb.

The Abandoned Railway Trench was used as an unloading and loading area for incoming rail
shipments. The railroad tracks were constructed below grouniJevel to facilitate these operations
During the 1960s, the use of the railway trench for loading and unloading purposes decreased and
it was gradually filled in with drums  of off-specification coal tar enamel.  Foundry sand obtained
from a variety of local  industry was also used to complete the filling of the trench  It is estimated
that the  trench was approximately five feet deep by fifteen feet wide by 580 feet long based on
Phase II investigations.

Test pits completed in  the railway trench area revealed a sloping rail bed at a depth of
approximately  three feet at the south end of the trench and at a depth of approximately four feet
at the north end. A surface layer of crushed stone was encountered at each test pit location and
fill material consisting of black,  brown or gray sand and gravel, foundry sand, coal  cinders, coal
tar wastes, wood debris and drums was found beneath  Soil contaminant concentrations in the
trench sampling for volatile organics ranged to 656,000 ppb and for semi-volatile organics

-------
126,020,000 ppb.

From the early 1950s until 1979, waste water sludge from the coal tar refinery and synthetic
chemicals operations was dried by placing it in the Former Sludge Treatment Pit, located in the
center of the Maywood property.  The sludge pit was used for thickening sludge by evaporation
prior to off-site landfill disposal. The current RCRA-permitted sludge treatment area is located
directly above the northern portion of this historical area.  The dimensions of the original sludge
pit, as reported in the RI, are 110 feet long by 20 feet wide by 4 feet deep

Soil contaminant concentrations in the sludge pit sampling for volatile organics ranged  to 202,900
ppb and for semi-volatiles 53,710,000 ppb.

From the beginning of site operations in 1921 until the mid 1970s, the southern portion of the
Maywood property was used as a  landfill, the South Landfill, for construction debris and  soil  In
addition, various solid and semi-solid wastes (tars, sludges, still bottoms, tank cleanings) from the
coal tar and the synthetic chemicals operations were also deposited in this area. Coal refinery
wastes deposited in the area included off-specification pitches, creosoted timbers, coal, and tank
car sludges and waste water sludge from the Maywood American Petroleum Institute (API)
separator. Wastes from the synthetic chemical operations were also deposited in the south landfill
beginning in the 1960s.  These wastes included waste water sludge from the API separator and
distillation residues from various unit processes including vinylpyridine residue and 3-pyridine
carbonitrile residue.  Dimensions of the south landfill are approximately 1000 feet by 200 feet

A dug well, or fire pond, was situated at the  extreme southeast corner of the south landfill   This
pond was reportedly dug by facility personnel for the  purpose of providing a water supply  for fire
suppression.  The dimensions of the fire pond were approximately 112 feet in diameter and 23 feet
in depth. The fire pond dried up after a period of time, probably due to the increased industrial
groundwater  usage in the site vicinity. Limited data regarding the materials used to fill the dry
dug well (reported to be tars, sludges, various chemical production residues, and foundry sand)
were derived  during the RI.

The estimated volume of fill material in the South Landfill is 34,000 cubic yards  Soil
contaminant concentrations in the  South Landfill sampling for volatile organics range to 197,300
ppb and for semi-volatiles 35,280,000 ppb.  Field investigations in this area also identified  both
NAPLs (non-aqueous phase liquids) and DNAPLs (dense non-aqueous phase liquids) as present
in the groundwater in the form of oily sheen  and distinct oil phases in groundwater samples

A RCRA facility investigation in 1990 identified potential releases of hazardous constituents from
surface water drainage from the South Landfill.  An inspection by the Department of Fish and
Wildlife on January 31, 1992 identified the fire pond sludges as imminently hazardous to wildlife
As a result, EPA directed Reilly to perform an interim measure at the South Landfill to minimize
these risks until a final remedial action could be implemented.  This interim measure consisted of
regrading and covering the eastern portion of the landfill with six inches of clean soil, placement

-------
of plastic netting over the fire pond to prevent waterfowl from landing in this area, and
construction of drainage controls to prevent runoff from this area from leaving the site These
activities were completed in April 1992

Prior to 1970, waste water and storm water were conveyed from the API separator by the
Former Drainage Ditch into the Raymond Street storm sewer, which then discharged directly to
Eagle Creek  This water consisted of water separated from the raw tar,  water decanted from the
tar storage tanks, water separated from the oil-water, "wet-dry" in the refinery, blowdown water
from the boiler operations, aqueous sodium sulfate from the extraction of tar acids and tar bases
from the light and middle oils,  and storm water entering the system due to natural drainage
Historically, the length of the ditch was 1220 feet, the width was between 15 and 50 feet, and the
depth was approximately 8 feet.

Soil contaminant concentrations in the Former Drainage Ditch sampling for volatile organics
range to  199,930 ppb and for semi-volatiles 117,120,000 ppb.

Hot Spot Delineation

Further evaluation of the RI data by U.S. EPA determined that the soil contamination was present
in discrete locations within the CERCLA Areas  These hot spots,  if addressed, would
significantly reduce the contaminant concentrations at the site as well as significantly reduce the
risks posed by contributions to soil and groundwater contamination from these areas  All of the
CERCLA Areas were reevaluated by US. EPA to develop hot spot volumes for treatment
alternatives for soil cleanup; this reevaluation process yielded revised volumes for three of the
areas, the Lime Pond Drum Removal Area,  the Abandoned Railway Trench, and the Former
Drainage Ditch, that were significantly lower than those presented in the Feasibility
Study/Corrective Measures Study (FS/CMS), that represent the majority of the contamination
associated with the CERCLA Areas.

The revised volumes represent the most heavily contaminated soils in the unit, which is a portion
of all the soil in the unit  CERCLA Areas were evaluated by examining  the results of the
soil/sludge testing and the Toxicity Characteristic Leachate Procedure (TCLP) testing. The
samples collected during the Remedial Investigation/RCRA Facility Investigation (RI/RFI)
activities were evaluated to determine if the contaminant concentration for pyridines or
carcinogenic PAHs exceeded the risk-based target cleanup levels (RBTCLs) presented in the  FS.
and if the TCLP results exceeded discharge criteria (Maximum Contaminant Levels (MCLs)) for
drinking water for benzene, pyridine and carcinogenic polynuclear aromatic hydrocarbons
(CPAHs).

The visual characteristics of the samples were compared and areas that appeared to contain the
majority of contamination were identified for removal and  treatment The volume of soil to be
removed was calculated and an estimate of the mass of contaminants to  be treated was made  An
estimate of the mass of contaminants to remain was also made   By comparing ihe two, the

-------
percentage of the total contaminant mass to be treated was estimated. The following summarizes
this process for the three CERCLA Areas

Abandoned Railway Trench: According to the FS/CMS, the railway trench is approximately
640 feet long by 17 feet wide.  The railway trench is bordered by a wooden retaining wall on the
north and on the east and by a concrete building foundation on the south.  The FS/CMS extended
the width of soil requiring remediation beyond the limits of the trench 5  feet to the east and to the
west to include additional impacted soils.  The depth requiring remediation was estimated to be 20
feet for the northern 490 feet (representing the depth to groundwater) and 4 feet for the
remainder of the railway trench (representing the depth to just below the railbed). The volume of
material requiring treatment was estimated in the FS/CMS to be 10,320 cubic yards

The gross contamination is present in the original width of the railway trench (17 feet) to a depth
of approximately 5  feet (to the bottom of the railbed)  The gross contamination appears to end
within test pit J-05 where the description of the soil above the railbed changes from dark brown-
grey sand and clay to brown sand and gravel, trace cobbles, medium coarse sand  No samples
were taken south of this transition point. The length of gross contamination considered in the
revised volumes was 512 feet (compared to 640 feet estimated in the FS/CMS), because the
contamination was not as laterally extensive to the south as originally estimated, using the criteria
for identification of hot spots, as outlined below

The results of the evaluation showed that a  reduction in the amount of soil to be treated could be
made, while keeping a high percentage of reduction in the amount of contamination removed
The FS/CMS identified 10,320 cubic yards of soil to be treated. The EPA evaluation determined
an 82% reduction in that amount.  A revised amount of 1850 cubic yards of soil needed treatment
The percentage removal of contaminants found in the revised soil amount is as follows: 100% of
the detected benzene; 99 9% of the detected pyridines; and 73 9% of the detected CPAHs

The volume of soil  to be treated  encompasses 12 of the 15 samples where concentrations
exceeded the industrial RBTCL (presented in the FS/CMS) and all four of the samples where the
Toxicity Characteristics Leaching Procedure (TCLP) data she*£d exceedances of discharge
criteria.  This volume does not include soils outside of the wooden retaining wall, because they
are part of the kickback area which is to be  addressed in future actions,  as is stated in the
FS/CMS

Former Drainage  Ditch:  The Former Drainage Ditch contains two apparently separate areas of
contamination - a layer of cinders/tar/oily gravel that varies from about  1 to 1.5 feet thick, and an
oily material that occurs within the original  drainage ditches  The FS/CMS did  not include
remediation of the cinder/tar/oily gravel layer in the volume calculations. This layer is attributed
to the kickback area in the FS/CMS.  The volume estimated in the FS/CMS that requires
remediation includes an area 35 foot wide by 4 feet thick along 660 feet of the west drainage
channel and 50 feet along the east drainage  channel (3700 cubic yards). The total volume of
contamination in the area of the drainage ditch, as presented in the FS/CMS, is approximately

-------
5800 cubic yards.

The gross contamination (besides the cinders/tar/oily gravel layer) does appear to be centered on
the west drainage channel.  The width of the contaminated soil (visually identified as black clayey
silt, black silty clay, black silt (oily), and black tar) varies from 5 to 12 feet wide according to the
test pits.  The revised volume of soil to  be excavated and treated includes the material centered on
the west drainage channel and the cinders/tar/oily gravel layer that covers the area

The results of the evaluation showed that a reduction in the amount of soil to be treated could be
made, while keeping a high percentage of reduction in the amount of contamination removed
The FS/CMS identified 5800 cubic yards of soil to be treated. The EPA evaluation determined an
66% reduction in that amount, which resulted in a revised amount of 1950 cubic yards to be
treated. The percentage  removal of contaminants found in the revised soil amount is as follows
96.5% of the detected benzene; 99.6% of the detected pyridines; and 94.7% of the detected
CPAHs

The volume of soil to be  treated encompasses 7 of the 8 samples where concentrations exceeded
the industrial RBTCL and both  samples where the TCLP data showed exceedances of discharge
criteria.

Lime Pond Drum Removal Area: Waste materials were deposited north and east of the Lime
Pond in what is referred to in the FS/CMS as the drum removal area.  The wastes were originally
assumed to have been deposited in trenches, two running north-south east of the lime pond and
one running east-west north of the lime pond. The volume of waste associated with these
trenches was estimated based on the results  of a geophysical investigation

The drums were located  and removed as part of the Lime Pond drum removal project. Samples
of the waste material around the drums  were collected during the drum removal  The FS/CMS
estimated the volume of waste material  based on an "L" shaped area to the north and east of the
lime pond The depth of contaminated material was estimated to be 15 feet. Based on these
assumptions, the volume of material requiring remediation was estimated in the FS/CMS to be
29,000 cubic yards

In the revised volume calculations, it was assumed that the gross contamination  is limited to the
trenches. Analytical data is unavailable in the areas outside the drum removal excavation areas
While it is possible that gross contamination may exist outside of the trench areas, the volume of
gross contamination is not anticipated to be significant  This assumption is based on the RI
geophysical evaluation. The depth of gross  contamination was estimated to be 10 feet  The test
pits excavated during the Lime Pond drum removal project extended to depths from 4 to 12 feet
below ground surface. Drums were encountered as deep as 6 feet below ground surface

The revised volume of gross contamination is about 5400 cubic yards, approximately  19% of the
volume calculated in the  FS/CMS.  No samples were collected and tested outside of the

-------
excavation areas, therefore no comparison of mass contamination to remain versus mass
contamination to be treated can be performed  Some contamination may remain through the
leaching of the waste material.

Former Sludge Treatment Pit: The Former Sludge Treatment Pit was reevaluated using the
criteria mentioned above for determination of hot spot volumes  The volume presented in the
FS/CMS (800 cubic yards) was found to be accurate for hot spot delineation at this area

South Landfill/Fire Pond: The South Landfill/Fire Pond was reevaluated using the criteria
mentioned above for determination of hot spot volumes  Due to the widespread contamination at
this area, the absence of any discernable hot spot area, and the prohibitive volume of
contaminated soils at this area, it was determined that the South Landfill/Fire Pond would not be  ,
included in the hot spot delineation.  One area that was identified as a hot spot was the Fire Pond,
which is the subject of remediation as a portion of the September 1993 ROD

The cost and volume estimates presented in the FS for the alternatives analysis are for hot spot
soils in the source areas which address the most contaminated portions of these areas.  The term
"hot spot soils" is defined as including, but not limited to, those soils which exhibit visible
evidence of contamination, or which fail the TCLP test

The FS estimated volumes  of contaminated soil for each of the source areas. Further evaluation
of the RI data showed  that the soil contamination was concentrated in discrete locations within
the source areas.  These hot spots were found to be the greatest contributors to groundwater
contamination. Over 90%  of the soil contamination is present in these hot spot areas which
comprise approximately 20% of the total volume presented in the FS  As a result, treating the hot
spot soils, which constitute a small portion of the source areas, was also considered by EPA
Treatment alternatives presented in the September 1993  ROD represent cleanup of those hot spot
areas.

C      Selected  Remedy

The ROD for OU 2 (September 1993) required:

       Excavation and thermal treatment of 8,100 tons of contaminated soils at four on-site
       areas.

       Disposal  of treatment condensate by off-site incineration

       Treatment of sludge in a fifth on-site area by in-situ solidification.

       Placement of a soil cover over  the solidified sludge

       Long-term groundwater and source area  monitoring for all five CERCLA Areas
                                           8

-------
Ill  Description of the Significant Differences and the Basis for those Differences:

The Remedial Action at the South Landfill was completed in April 1996. This action included the
solidification of approximately 12,882 tons of sludge in the south landfill and the placement of a
soil cover over the solidified area.

During thermal treatment operations at the site, it was determined that the majority of the soils to
be treated by thermal desorption contained extremely high BTU levels.  The thermal desorption
system cannot process soils with a BTU level above 800 BTU/lb.  This 800 BTU/lb level is
utilized throughout the thermal desorption industry as a standard for determining eligibility and
applicability of the technology  Soils which contain organic material in excess of 800 BTU/lb
become additional fuel for the thermal desorption system which results in temperature increases
inside the primary kiln to levels beyond the capabilities of the thermal desorption equipment   This
leads to the destruction of the refractory linings, fires within the baghouse, and essentially, the
incineration of the soils instead of the desorption of the contaminants from the soils

In the sampling performed by the PRP contractor, it was determined that the high BTU level in
the soils is not a reflection of the contaminant concentration, but a reflection of the content of
total organic material (contamination and naturally occurring organics) within  the soil  The PRP
contractor tried to "blend"  the soils in order to lower the overall BTU level  However, when this
blended material was treated, an exothermic reaction occurred in the primary kiln causing an
uncontrollable increase in temperature which resulted in the shut down of the system to protect
the associated hardware and personnel at the site  The feed soils were immediately sampled  for
BTU levels and found to contain BTU "hot spots" exceeding 1000 BTU/lb.  These results
demonstrate that the high BTU material cannot be blended thoroughly enough to eliminate small
BTU "hot spots" in the soil that cause the exothermic reactions  Therefore, because this
excavated soil could not be treated using the selected remedial method of thermal desorption, the
selected remedy must be changed to address this remaining contaminated soil

A series of off-site disposal options were evaluated and submitted to U.S. EPA for consideration
These off-site disposal options included both treatment options and options for off-site disposal at
a compliant landfill.   Because the selected remedy employed treatment to address the highly
contaminated soils removed from the hot spot areas, and the remedial intent of the  ROD was to
remove the contaminants present in the soils, US  EPA and IDEM favor the treatment options
presented for the remaining soils.

Original Remedy                               Modified Remedy

Excavation and on-site thermal                    Excavation and on-site thermal
desorption of 8,100 tons of                       desorption of 3,600 tons  of contaminated
contaminated soil                                soil

-------
Off-site disposal of treatment                      Excavation of 4,000 additional tons of
residuals by incineration                          contaminated soil to be addressed by this
                                                action.

                                                Off-site thermal treatment of approximately
                                                8,500 tons of contaminated soil in an
                                                industrial boiler or a cement kiln

Through this ESD, EPA is allowing for off-site treatment of the contaminated soils as opposed to
the on-site treatment required in the original ROD  Through a combination of these two
treatment options, the soil will be treated off-site to meet the performance standards contained in
the operational permits for each respective facility

It is estimated that approximately $1,250,000 in cost savings can be realized when using the off-
site treatment soil treatment options instead of on-site thermal treatment

IV.    Support Agency Comments

IDEM concurs with this ESD

V      Affirmation of the Statutory Determinations

Considering the new information that has been developed and the changes that have been made to
the selected remedy, U.S. EPA and IDEM believe that the remedy remains protective of human
health and the environment, complies with federal  and state requirements that were identified in
the September 1993 ROD as applicable or relevant and appropriate to this remedial action at the
time of the original ROD, and is cost effective.  In addition, the revised remedy utilizes permanent
solutions and alternative treatment technologies to the maximum extent practicable for this site

VI     Public Participation Activities

U.S. EPA will publish a notice of this ESD in the Indianapolis Star, informing interested parties
that a copy of the ESD and supporting documentation is available at the Indianapolis Public
Library, 48 East St.  Clair, Indianapolis, Indiana, and at the US. EPA regional offices in Chicago;
Illinois, 77 W. Jackson-7th Floor, during normal business hours
                                            10

-------
VII    Concurrence
William E  Muno, Directo/                      Date
Superfund Division
                                                     fo
                                          ! I

-------