50272-101
 REPORT DOCUMENTATION
        PAGE
                        1. REPORT NO.
                             EPA/ROD/R05-90/143
                                                                    3. Recipient's Accession No.
 4. Title and Subtitle
   SUPERFUND  RECORD OF  DECISION
   Springfield Township Dump, MI
   First Remedial Action - Final
                                                                     5. Report Date
                                                                             09/29/90
 7. Author(s)
                                                                    8. Performing Organization Rept No.
 8. Performing Organization Name and Address
                                                                     10. Project/Task/Work Unit No.
                                                                     11. Contract(C) or Grant(G) No.

                                                                     (C)

                                                                     (C)
 12. Sponsoring Organization Name and Address
   U.S.  Environmental  Protection  Agency
   401 M Street,  S.W.
   Washington,  D.C.  20460
                                                                    13. Type of Report & Period Covered

                                                                        800/000
                                                                     14.
 15. Supplementary Notes
 16. Abatract (Limit: 200 words)
  The  16-acre Springfield Township Dump  site is in Davisburg, Springfield Township,
  Michigan.   The site is comprised of an  open field  area surrounded by dense  woods.
  Surrounding land  use is mixed agricultural and residential.  The site overlies both a
  shallow and deep  aquifer, and there are several wetlands adjacent to the  site.  A 4-acre
  portion of the site was used  for industrial waste  disposal between 1966 and 1968.
  Unknown quantities  of industrial waste  were drained  into onsite  excavated pits in a
  central disposal  area or deposited on  low ground areas.   Random  dumping of  refuse
  occurred onsite,  and many drums containing liquid  wastes were  seen scattered throughout
  the  woods.  In 1978,  the State identified PCBs, paint  sludge,  solvents, oils,  and
  greases in 1,500  onsite drums.  State  studies also determined  that a portion of the
  aquifer underlying  the site was highly  susceptible to  contamination, due  to the absence
  of a clay layer.   In 1979 and 1980, VOC-contaminated well water  was found at private
  residences near the site.  In 1979, the State ordered  the 1,500  onsite drums removed and
  disposed of offsite.   From 1979 to 1980,  711 tons  of contaminated soil were'excavated
  and  removed from  several onsite areas  including the  centrally  located disposal pits.
  Because of limited  funding, some wastes remained onsite, but the pits were  subsequently

  (See Attached Page)
                                                        MI
17. Document Analysis a. Descriptors
   Record of Decision -  Springfield  Township Dump,
   First Remedial Action -  Final
   Contaminated Media:   soil,  gw
   Key Contaminants:  VOCs  (TCE, toluene),  other  organics . (PCBs),  metals  (arsenic,
                       chromium, lead)
  b. Identifiers/Open-Ended Terms
   c. COSAT1 Held/Group
 18. Availability Statement
                                                     19. Security Class (This Report)
                                                            None
                                                      20. Security Class (This Page)
                                                            None 	
21. No. of Pages
       144
                                                                                22. Price
(See ANSI-Z39.18)
                                      See Instructions on Reverse
                                                                               OPTIONAL FORM 272 (4-77)
                                                                               (Formerly NTIS-35)
                                                                               Department of Commerce

-------
 EPA/ROD/R05-90/143
 Springfield Township Dump, MI
iFirst Remedial Action - Final

 Abstract  (Continued)

 filled  in  and regraded.   In  1980, the State identified onsite PCB- and DDT-contaminated
 soil and onsite VOC-contamination in ground water.  This Record of Decision  (ROD)
 addresses  remediation of  onsite  contaminated soil and ground water and will  be  a  final
 remedy  for the site.  The primary contaminants of concern affecting  the  soil and  ground
 water are  VOCs including  TCE and toluene; other organics including PCBs;  and metals
 including  arsenic,  chromium, and lead.

 The selected remedial action for this site includes excavating and treating  onsite a
 total of 11,820 cubic yards  of VOC- and other organic-contaminated soil  by
 incineration, and solidifying the resulting ash; treating metal-contaminated soil using
 solidification and  redepositing  the treated soil and ash onsite or temporarily  storing
 the treated soil onsite in a solid waste unit; treating remaining soil using in-situ
 vacuum  extraction and performing a treatability study to determine its effectiveness;
 ground  water pumping and  treatment using carbon adsorption, followed by  onsite
 reinjection of the  treated ground water; and implementing site access restrictions,
 such as fencing.  The estimated  present worth cost for this remedial action  is
 $9,271,290, which includes an annual O&M cost of $97,659.

 PERFORMANCE STANDARDS OR  GOALS:  Soil remediation goals are based on a 10~6  cancer risk
 and State  Michigan  Act 307 Standards.  Chemical-specific soil cleanup levels include
 PCBs 1 mg/kg, toluene 0.08 mg/kg, and TCE 0.08 mg/kg.  Ground water  will  be  remediated
 to meet or exceed SDWA Federal MCLs or MCLGs including toluene 0.4 mg/1  (MCL) and TCE
 0.003 mg/1 (MCL).   Lead and  arsenic will be remediated to background levels  for both
 soil and ground water.

-------
         RECORD OF DECISION

   REMEDIAL ALTERNATIVE SELECTION

     SPRINGFIELD TOWNSHIP SITE
      Oakland County, Michigan
             Prepared  by  •/•'
U.S. Environmental Protection Agency

     Region V, Chicago Illinois

           September 1990

-------
                       RECORD OF DECISION
                 Remedial Alternative Selection


Site Name and Location

The Springfield Township  Dump  site  is  approximately a 400 by 500
foot fenced area located  on  an approximately 16 acre parcel of
land, south of Davisburg  in  Oakland County,  Michigan.

Statement of Basis and Purpose

This decision document presents the selected remedial action for
the Springfield Township  Dump  site  in  Oakland County, Michigan,
which was chosen in accordance with CERCLA,  as amended by SARA,
and, to the extent practicable,  the National Oil and Hazardous
Substances Pollution Contingency Plan  (NCP).  This decision is
based on the administrative  record  for this  site.  The index to
the administrative record is attached  to the Record of Decision
(ROD).

The State of Michigan has concurred with the selected remedy.

Assessment of the Site                 ^

Actual or threatened releases  of hazardous substances from this
site, if not addressed by implementing the response action
selected in this ROD,  may present an imminent and substantial
endangerment to public health,  welfare,  or the environment.

Description of Selected Remedy

The selected remedy addresses  the principal  threats posed by the
site, and is the final remedy  for the  site.   The major components
of the selected remedy are:

     •Excavation and thermal destruction of  soils to remove to
     specified cleanup levels  polychlorinated biphenyls (PCBs),
     volatile organic compounds (VOCs),  semi-volatile organic
     compounds (SVOCs), and  pesticides in the source area;

     •Solidification of incinerator ash according to ARARs;

     •Solidification of soils  contaminated only with metals;

     •Redeposition of ash and  treated  soil on-site (the ash will
     either be stabilized to make it inert prior to its on-site
     disposal or will be  placed in  a properly designed solid
     waste unit on-site);

-------
     *Recontouring of the excavated areas and control of the ash
     or dust emissions;

     •Installation of an in-situ vacuum extraction system to
     remove VOCs and SVOCs from remaining unsaturated
     contaminated soils at depth; and

     •Installation and operation of a ground water extraction and
     treatment system which utilizes a carbon adsorption unit to
     treat the groundwater before reinjection into the aquifer.

A detailed discussion of each of the components of the selected
remedy is presented in Section 9 of the ROD and in both the
Feasibility Study and Proposed Plan developed for the site.

Statutory Determinations

The selected remedy is protective of human health and the
environment, attains Federal and State requirements that are
applicable or relevant and appropriate for this remedial action,
and is cost-effective.  This remedy satisfies the statutory
preference for remedies that employ treatment that reduces
toxicity, mobility, or volume as a principal element and utilizes
permanent solutions and alternative treatment technologies to the
maximum extent practicable.

Because this remedy will not result in hazardous substances
remaining on-site above health-based levels, the five-year
facility review will not apply to this action once the cleanup
performance standards are achieved.

             fc
                                        Valdas V. rtdamkus
                                        Regional Administrator

-------
                        TABLE OF CONTENTS

Section                                                     Page
The Declaration
1.0       Site Name, Location, and Description              3
2.0       Site History and Enforcement Activities           4
3.0       Community Relations Activities                    7
4.0       Scope and Role of the Response Action             8
5.0       Summary of Site Characteristics                   9
5.1       Geology and Hydrology                             9
5.2       Drum Wastes                                       10
5.3       Soil Contamination                                10
5.3.1     Surface and Shallow Subsurface Soil               10
          Contaminat i on
5.3.2     Subsurface Soil Contamination                     11
                                       /?'
5.3.3     Test Pit Soil Contamination  '.'                    12
5.4       Surface Water/Sediment Contamination              12
5.5       Ground Water Contamination                        12
6.0       Summary of Site Risks                             13
6.1       Contaminants of Concern                           14
6.2       Exposure Assessment                               14
6.3       Toxicity Assessment                               15
6.4       Risk Characterization                             15
6.5       Environmental Risks                               17
7.0       Description of Alternatives                       17
7.1       Remedial Cleanup Levels                           17
7.2       Volume of Soil Remediation                        18
7.3       Volume of Ground Water Treatment                  19

-------
Section                                                     Page
7.4       Soil Alternative 1:  No Action                    19
7.5       Soil Alternative 2:  Off-site Land Disposal       19
7.6       Soil Alternative 3:  Surficial Capping            20
7.7       Soil Alternative 4:  On-site Incineration,        20
          Solidification
7.8       Soil Alternative 5:  On-site Incineration,        21
          Solidification, In-situ Vacuum Extraction
7.9       Ground Water Alternative 1:  No Action            21
7.10      Ground Water Alternative 2:  Ground Water         22
          Extraction and Carbon Adsorption
8.0       Summary of Comparative Analysis of Alternatives   22
8.1       Threshold Criteria                                24
8.1.1     Overall Protection of Human Health and the        24
          Environment
8.1.2     Compliance with ARARs                             24
                                       • /'
8.2       Primary Balancing Criteria    /                    25
8.2.1     Long-term Effectiveness and Permanence            26
8.2.2     Short-term Effectiveness                          26
8.2.3     Reduction of Toxicity, Mobility, or Volume        27
8.2.4     Implementability                                  27
8.2.5     Cost                                              28
8.3       Modifying Criteria                                29
8.3.1     Support Agency Acceptance                         29
8.3.2     Community Acceptance                              29
9.0       The Selected Remedy                               29
10.0      The Statutory Determinations                      32
10.1      Protection of Human Health and the Environment    32
10.2      Compliance with ARARs                             33

-------
Section                                                     Page
10.3      Cost-Effectiveness                                35
10.4      Utilization of Permanent Solutions and            35
          Alternative Treatment Technologies or Resource
          Recovery Technologies to the Maximum Extent
          Practicable
10.5      Preference for Treatment as a Principal Element   36
11.0      Documentation of Significant Changes              36
12.0      Summary                                           3 6
Attachment 1 - State Letter of Concurrence,  September 28, 1990
Attachment 2 - Responsiveness Summary/List of Commenters
Attachment 3 - Administrative Record Index

-------
            SUMMARY OF REMEDIAL ALTERNATIVE SELECTION

            SPRINGFIELD TOWNSHIP DUMP SITE, MICHIGAN


1.0       Site Name, Location, and Description

The Springfield Township Dump site is located south of the town
of Davisburg,  in Springfield Township,  Oakland County, Michigan.
The site is located on approximately 16 acre parcel of land in a
residential/agricultural area near the junction of Ormond Road
and Woodland Trail (see Figure 1).   The site is located on a
local topographic high and consists of an open, fenced area
surrounded by dense woods.

The site is located within the Huron River system on a knoll with
kettle wetlands occupying low elevations to the west, southwest,
and southeast.  The kettle wetlands are located within a 1/4 mile
radius of the site and are geographically isolated.  Wetlands
further west of site are intermittently connected to adjacent
wetlands and ultimately discharge to Big Lake which is 1 mile
northeast of the site.  The surface water drainage patterns are
poorly developed due to rapid infiltration of rain water.
                                       $•'
Springfield Township and the area around/ the site is mixed
residential and agricultural.  According to the Oakland County
Planning Department, this area is zoned for medium density
development which requires 1 to 1 1/4 acre lot size per single
family dwelling.  The township population is currently 10,063 and
projected to be 13,381 in the year 2000.  The Springfield
Township Site is located on the Nickson property and is situated
on the 16 acre parcel of land on which the 4 acre site is
located.

Area geology consists of unconsolidated glacial drift overlying
the Early Mississippian Coldwater Shale bedrock formation.  The
geology below the site is glacial outwash plain comprised of
fine-to-coarse grain sand with some silt-sized material.  This
glacial outwash deposit extends to an approximate depth of 140
feet and overlies interbedded sands and clay lenses.  Bedrock is
located at an approximate depth of 345 feet and consists of shale
or limestone.   There is no evidence to indicate that the clay
lenses are contiguous and form a continuous layer throughout the
area.

The glacial outwash deposit aquifer is utilized as a drinking
water source by local residents (Class I aquifer).  Ground water
flow is to the north east.  The nearest well is at the Nickson's

-------
'I:.
                                   •TKINCFIELO
                                   TOWNSHIP
                                          SOURCE: USGS Topographic'
                                                 Itep. 1973.
                                                                         FIGURE   1
                                                                         LOCATION MAP
                                                                         SPRINGFIELD TOWNSHIP

-------
residence, several hundred feet dovngradient of the site.
Regular groundwater sampling by the Michigan Department of
Natural Resources (MDNR) indicates that the residential wells
have not yet been impacted by groundwater contamination.

The site is approximately 400 by 500 feet, defined by an 8 foot
fence installed by MDNR.  The fenced area is on a topographical
high and is surrounded by woods and kettle wetlands.  The dune-
like topography of the area provided a natural basin on the back
portion of the Nickson property in which to store drums and
dispose of liquid wastes.  Drums were scattered throughout the
woods and in a central disposal area in which the liquid wastes
also appeared to have been dumped.

There are signs of casual use of adjacent property.  Also, there
have been several instances of trespassing and vandalism at the
site which have caused the need for well repair and fence
installation.  There are all terrain vehicles (ATV) and other
vehicular trails throughout the area.  There are also indications
of random dumping, i.e. burned-out car, trash site with burn-
barrels and miscellaneous items.


2.0       Site History and Enforcement Activities

The site was used for industrial waste disposal between 1966 and
1968 but may include other years.  An unknown amount of
industrial waste was drained into excavafted pits or low areas on
the ground surface (See Figure 2).  In addition, approximately
1,500 barrels were found on the site.

The dumping of wastes was done by waste haulers under contract or
other agreement with the waste generators.  The first official
notification of illegal dumping was made by the supervisor of
Rose Township in a letter to the Oakland County Health Department
(OCHD) in June 1968.  In a MDNR memorandum dated December 10,
1968, a staff member reported that the OCHD had recently found
another dumping site, the Springfield Township site.

In July 1971, the OCHD issued a certified letter to the property
owner, Mr. Joseph Nickson, stating that corrective action was
required.  In April 1979, a Pollution Emergency Alerting System
(PEAS) complaint was filed by the OCHD to the MDNR.  As a result
of this complaint, the MDNR conducted limited drum sampling at
the site on June 4, 1979.  Subsequent analyses by the MDNR
identified the drum contents as paint sludges, solvents, PCBs,
oils, and greases.

From August 1979 through June 1980, sampling of well water at
private residences near the site was conducted.  During initial
sampling episodes, several residential wells in the vicinity of
the site were reported to be contaminated with low levels of

-------
LEGEND
  D
MOTE:
  TAKEN r*OM W0A1CB KIT ME-f ICAVATION
  ACMAL PHOTO.
SCALE
0    Su   TOC
                                                                           ni|T| INF
                                                                                              FIGURE  2
                                                                                        OISPOSAI ARFA«;
                    200
                 SlTf SUXVf » O«TtO «.'«»
                                            FEASIBILITY  STUDV
                                    MICHIGAN DEPARTNflENT OF
                                         NATURAL RESOURCES

-------
layers of hardened multicolored sludges located near the center
of the site.

The RI report was completed in April 1989.  The results of the RI
indicated surface and subsurface soil contamination.  PCBs,
dieldrin, toluene, chlorobenzene, trichloroethene, barium, lead
and arsenic are identified as the contaminants of concern in the
on-site soils.  The shallow soil contaminants pose both a direct
contact threat and a threat to the food chain through
bioaccumulation of toxics.  The shallow and subsurface soil pose
an additional threat to the ground water, acting as a continual
source of degradation.  Ground water contamination, found mainly
within the site boundaries, consists primarily of
trichloroethene, dichloroethene, arsenic, and lead.

The MDNR conducted several additional ground water sampling
episodes since the RI investigation.  The results of the sampling
indicated that ground water contamination had spread away from
the disposal area and was migrating to the north-northeast.  The
Nickson residential well, which is located on the 16 acre parcel
of land on which the site is located, was sampled in November
1987 and found not to be contaminated.

The Feasibility Study (FS) was initiated by the lead agency,
MDNR.  In January 1988, the lead agency responsibility was
transferred to the U.S. EPA, and the project was completed in
July 1990.  The FS and Proposed Plan we£e released for the public
comment period which began on July 13, 1990.  The FS presented
several soil remediation alternatives and a ground water remedy
that will be explained in detail under the Description of
Alternatives section of this document.  A more detailed analysis
of all alternatives are presented in the "Final Report on the
Feasibility Study of the Springfield Township Site11 (July 1990).

Identification of potentially responsible parties (PRPs) was made
through interviews with haulers, review of state and private
records pertaining to the site, and examining photos taken of the
site.

On January 30, 1990, U.S. EPA issued general notice letters to
the members of the Springfield Township PRP Steering Committee
and other potential responsible parties known at that time.

A Steering Committee was formed by some members of the
potentially responsible parties and met with U.S. EPA and MDNR on
several occasions.  The initial meeting was on September 6, 1989
in Lansing, Michigan and was to discuss the cleanup levels,
possible remediation technology and the Remedial Action Plan
(RAP) submitted to the agencies by the Steering Committee.  A
subsequent meeting was planned so that the Steering Committee
could provide further clarification and expanded methodology
introduced in the RAP.  In the interim, the Steering Committee

-------
tetrachloroethene and trichloroethene,  volatile organic compounds
(VOCs),  that were similar to those found on the site.

In September 1979, the site was declared an environmental
emergency by the State of Michigan Toxic Substances Control
Commission (TSCC) based upon potential  threat to health and
environment.  During the same month,  the MDNR commenced the
excavation and removal of drums from the site.  In December, a
special appropriation was made by the State legislature for the
cleanup of the wastes and investigation of the impact on ground
water.   By July 1980, 1,500 55-gallon drums had been removed.

In 1979-1980, 711 tons of contaminated soil was removed to a
licensed hazardous waste facility in Alabama.  This included much
of the material contained in the disposal pit located in the
central portion of the site.  Because available funding was
insufficient, some wastes were left on-site.  This removal action
left the disposal pit area several feet below original grade.
Backfill, composed primarily of sand, was brought in and the
disposal pit area was regraded.

In September 1980, MDNR initiated and performed a Phase I
Hydrogeologic Investigation, during which four monitoring wells
(MW IS through 4S) were installed.  The Phase I Hydrogeologic
Investigation report, completed in 1981, indicated the presence
of significant soil contamination including PCBs at
concentrations up to 240 ppm and the pesticide DDT at up to 10
ppm.  Lows levels of 1,1,1-dichloroethane (35 ug/L in MW-1S) ,
1,1,1-trichloroethane (12 ug/L in MW-4S), and several heavy
metals were detected in the ground water.

Based on the findings of the Phase I report, a Phase II
Hydrogeologic Investigation was begun in May 1982 by MDNR.
Thirteen additional monitoring wells were installed (MS-ID
through MW-4D and MW-5 through MW-13).    Completed in 1983, the
report concluded that the portion of the aquifer underlying the
site was highly susceptible to contamination due to the absence
of an impermeable material such as clay.  Contaminants had
migrated through the existing sands impacting the ground water
and creating a plume of contamination which had since migrated
downgradient, but had not reached residential wells.

In 1983, the site was placed on the National Priority List.  The
Phase I and II Hydrogeologic Investigation reports were
incorporated in to the U.S. Environmental Protection Agency
(U.S. EPA) Remedial Action Master Plan (RAMP) which recommended
that a Remedial Investigation/ Feasibility Study (RI/FS) be
undertaken at the site.

In February 1985, MDNR initiated the RI at the site.  At the
time, the major evidence of past disposal practices consisted of
soil with entrained sludges and tar-like material and surficial

-------
                                                                8

Springfield Township representative attended meetings at MDNR in
Lansing and provided assistance and support to MDNR efforts
during the site investigation and cleanup.  An organization
called the "Schindler Road Residents" has been involved in
•onitoring site cleanup activities since 1979.  This group has
been represented at several public meetings and also some members
filed a class action suit regarding this site which was settled
without a judication.

Substantial interaction with the community occurred during the
remedial investigation and feasibility study phase conducted by
the MDNR.  Eight newsletters, several public meetings and
numerous one on one discussions both in person and over the
telephone occurred.  In addition a citizen information committee
was formed and several meetings were held with that group.

The lead agency responsibility for the RI/FS was transferred in
January 1988 from MDNR to U.S. EPA.  U.S. EPA held a public
meeting on July 11, 1989, to update area residents about the site
work and RI/FS schedule, and to explain that the cleanup remedy
was delayed pending modifications in the cleanup levels.  In
October 1988 and October 1989, the U.S. EPA sent to the members
of the public on the site mailing list updates on the status of
the project.

As the Feasibility Study concluded, a local official and citizen
requested a tour of a transportable incinerator in the Chicago
area because incineration was one of the7 alternatives under
consideration for the site remedy.  On July 18, 1990, the local
official, citizen, and the U.S. EPA site RPM received a tour of
the incinerator by the Illinois Environmental Protection Agency.

On July 24, 1990, a public meeting for the proposed plan and FS
was held.  Approximately 30 people from the community as well as
members of and contractors for the PRP Steering Committee
attended.  Oral and written comments were recorded and are
summarized in the Attachment 2, Responsiveness Summary, within
this document.  The provisions of Sections 113 (k) (2) (B) and 117
of CERCLA have been satisfied.

An information repository has been established at the Springfield
Township Hall, 650 Broadway, Davisburg, Michigan 48019 and
periodically updated.  According to Section H3(k)(l) of CERCLA,
the Administrative Record File has been made available to the
public at Springfield Township Hall.


4.0       Scope and Role of the Response Action

The Remedial Action for the site will address the principal
threats to public health and the environment posed by the
contaminated soils and contaminated ground water found on-site.

-------
submitted another report which addressed the presence of
pesticides and arsenic in on-site soils.  A meeting with the
Steering Committee,  U.S. EPA and MDNR was held at U.S. EPA
offices in Chicago on January 30, 1990.  At that time, MDNR
informed U.S.  EPA and the Steering Committee that the cleanup
levels for certain chemicals would be revised if Michigan
promulgated its Act 307 Rules.  Subsequently, a conference call
on April 12, 1990 and a meeting on May 9, 1990 at the MDNR
offices occurred between the Steering Committee, U.S. EPA and
MDNR to continue discussions on the proposed cleanup levels for
the site.  As indicated in the Administrative Record, the
Steering Committee and U.S. EPA continued to discuss the
proposed cleanup levels.


3.0       Community Relations Activities

The MDNR began field sampling during the summer of 1979 as a
result of the PEAS complaint.  In August 1979, the Detroit Free
Press printed a story titled, "Dump Sites Leak PCB's in Oakland:
Tests Due."  The article was the first notice for many residents
and local officials that a toxic chemical problem existed at the
site.  On September 1, 1979, a portable communications center for
MDNR was moved onto the site to help improve field
communications.

On September 4, 1979, MDNR hosted a meeting attended by a variety
of agency and public officials interested in the effects of
illegal dumping.  The purpose of the meeting was to summarize
action that had occurred to date and to determine
responsibilities for future actions.  Public warnings were issued
not to drill new water wells.

On March 29, 1983, MDNR held a public meeting at the Davisburg
school in Springfield Township.

MDNR contracted with the Southeast Michigan Council of
Governments to complete a review of social and economic impacts
related to the toxic waste sites in Oakland County.  Based on
interviews, the following citizen concerns and issues related to
the presence of the sites were identified:

     •potential lower property values,

     •potential drinking water supply contamination,

     •health effects of ingesting contaminated drinking water and
      the future health of families, and

     •perceived lack of communication and concern from government
      agencies.

-------
LEGEND:

  O   toc*TioN or taunt

  W   SAMPIC MNTTKATOM NMMEH

           or son.
MOTES:
  ».  MH surni otNons « SUMHCUI siuooc

SCALE
   r>0   100
                 :or r L-..T
                  FIGURE 3    j
      ESTIMATED EXTENT OF
PROPOSED^ SOIL ^REMEDIATION   '

          ; i-«^iu.w. i i  Si uu t
   MICHIGAN DEPARTMENT OF
       NATURAL  RESOURCES   :

-------
The affected area is an area in which the contaminated soils
extend to depths of 85 - 90 feet and have contaminated the ground
water underlying the site.   This response action is the final
remedy for the site and will remediate this area by excavation,
incineration, solidification and in-situ vacuum extraction of
contaminated soils and extraction and treatment of contaminated
ground water (see Figure 3).  As a result of this remedial
action, the site will not require monitoring, deed restrictions,
or institutional controls,  if the cleanup levels are attained and
the residual incinerator ash is either disposed of off-site or
stabilized prior to its on-site disposal.


5.0       Summary of Site Characteristics

The investigations conducted for the emergency removal action,
for the RAMP, and for the RI produced information on the site's
geological and hydrological conditions, soil contamination,
groundwater contamination,  environmental setting and area
demographics.  The following sections will present the major
findings.


5.1       Geology and Hydrology

A geologic cross section of the Springfield Township site from
northwest to southeast is shown in Figure 4.  The cross section
shows that the geologic materials immediately beneath the site
are relatively homogeneous, consisting primarily of deposits of
water-laid sand with some silt-sized material.  The materials
encountered in the unsaturated zone consist of moist, brown or
gray, fine to coarse sand with occasional pebbles and lenses of
silt.  Only two definite geologic changes were noted in the
materials above the water table, which occurs at depths of 85 to
95 feet below ground level.  One change was a layer of fine to
medium sand with cobbles which was present from surface to a
depth of 26 feet northwest of the site.  The other was a brown
clay layer which was encountered in the upper 4 feet in an area
immediately northeast of the site.  The glacial outwash deposits
extend to a depth of 140 to 150 feet.

A seismic profile conducted approximately 40 feet south of the
main disposal area measured velocities indicative of clay and
sand beginning at 175 feet below grade extending down to
approximately 345 feet.  At about 345 feet, bedrock was indicated
and is believed to be the Mississippian Coldwater Shale.

The site is bordered on three sides by low-lying marshy areas and
has no well developed drainage pattern.  The most probable
surface drainage route appears to be to the west towards an
adjacent marsh.  Surface water flow would terminate here except
possibly in the case of extremely heavy rainfall.

-------
                                                               10

The aquifer at the site is a Class I aquifer (drinking water
source).   Horizontal direction of ground water movement within
the vicinity of the site is varied.  The ground water from the
site may move east and west around a ground water mound, which is
located just north of the site, as it flows in a north and
northwest direction (see Figure 5) .  At other times of the year,
these pathways may become blocked hydraulically, and ground water
underlying the site may change direction for short periods of
time (see Figure 6).  Ground water flow at the site is occurring
too slowly for seasonal variations in the infiltration rate and
for ground water movement to be a significant concern.
Horizontal ground water flow rates in the area of the site range
from 1 to 50 ft/yr.


5.2       Drum Wastes

Drum contents and pools of water around the drums were sampled in
the summer of 1979.  Six of the drum samples indicated PCBs in
concentrations ranging from 32,000 ug/1 to 11,600 ug/1 with
Arochlor 1254 the most prevalent.  Analysis for heavy metals
indicated cadmium, chromium, copper, iron, nickel, lead, and
zinc.  The gas chromatograph and infrared scans showed the
presence of lubricating oil, fuel oil, gasoline, benzene,
toluene,  mineral spirits, methyl isobutyl ketone, and xylene.
All drummed wastes have been removed from the site.  There is
presently insufficient evidence to conclude that the drummed
wastes were specific RCRA listed hazardous wastes.

During excavation and removal, additional drums were sampled for
PCBs.  PCBs were detected in 253 of 525 drums with solid contents
and 70 of 431 drums with liquid contents.


5.3       Soil Contamination

The soil sampling program for the site consisted of surface and
shallow subsurface sampling, two phased subsurface sampling and
test pit investigations (see Figures 7 and 8).


5.3.1     Surface and Shallow Subsurface Soil Contamination

The surface and shallow subsurface sampling consisted of
approximately 300 samples taken by hand auger at three depths (up
to 4.5 feet) in 100 locations.  Concentrations of contaminants
encountered included:   PCBs at up to 3,800 ppm; pesticides at up
to 48 ppm; and lead at up to 5,470 ppm.  Most shallow soil
contamination was encountered within the top 2.5 feet.

VOCs were generally present in the shallow soil at typical levels
of less than 100 ppm.   The exception was at the former disposal

-------
           WEST
                                                                                                              IAST
                                                                                                                                   LEQENO
 M40
-1119
-toao
-10«0
•10*0
-1010
-1000
                                                DISPOSAL
                                                  AREA
         MWS
                                                                                        (MOUNO SURFACE
                                                                                                                       1140-
                                                                                                                       «ite-
                                                                                                                       1100-
                                                                                                              Ji lit r ttrr    -
                                                                                                                        1OTC-
                                                                                                                        tooo-
                                                            SILTS AND CLAYS
                                                                                                                                      WW( «	WILL MUMIIR
                                                                                                                                         — I-   ODOUHOWATCN LIVIL
                                                                                                                                               - SCREEN INTERVAL
                                                                                                                                              • •OTTOU Of •ORINO
«- »00
             HORIZONTAL SCALE
NOTES:
    1. WATER LEVELS CASED ON MARCH It. IMS DATA.
    I VBTTCA1. fXAOOEBATUN OF ABOUT «T»€a
              o   too   loo
                                  «00 FEET
                   FIGURE «
    INTERPRETIVE GEOLOGIC
        CROSS SECTION A-A'
SPRINGFIELD TOWNSHIP SITE
           FEASIBILITY  STUDY
  MICHIGAN DEPARTMENT OF
       NATURAL RESOURCES

-------
                                                                                                        ft'  »Jo*  tie' 300' «5(T-»6o
/ A
f i
* •
• •

• •


* *

• •

« •
' lora.u
7*1
7 • ' /• I 	
/ / V loaw.ia
I . . I . Nw - A-
/ \ i
/ ' *MM
I. ...!••••
' A xv\ ^
lot ^, /—

1 * lo^l^AL * *^ foiM * T V> * ^r f
\ A* "" X^ 'X'
« . • ••/.«•-•
^x ; A
I ^"^ ;
v 	 ^ • • ;• •
                                                            ,  I
                                                              I
                                                             I
                                                             I
                                                             h
                                                              »

                                                             I \

                                                            I  \
                                                            I   \    •
                                                            I     \
                                                            I     \
                                                            I      \
                                                            I      \
                                                           I       \
                                                           I        \
                                                           I      A  \
                                                           I     «o« ,,>--


                                                          ;--•"'
                                                                                                    *,
                                                                                                                   A  Sln«l* W«ll



                                                                                                                   A  Ct»«i«i w*u



                                                                                                                   *  W«IU««M»»



                                                                                                                   O  *»•«»<•«••« »  i



                                                                                                                   •  $•*••* ••••»•  too'



                                                                                                                   •  $»r»»» Mtik>  50O'
    «•
-°-.jO-   •
                                            O
                                            19
FIGURE  6
                    d|r»cliori
                                                                                         DNR
                                                                                                                        Environ  «nt«


                                                                                                                          R*tp< '§•


                                                                                                                          Dlvlf on
                                                                                        5prln|fl«ld Twp. S»t»
                                                                                                                         3-13-88

-------
                                                                                                                                               *{»'•
                                                                                                                                       I      I    I.    I    1
                                                                                                                                      100  700'300   '00   >n
FICURE   5       Arff»»«  i

-------
 LEGEND:

   O    LOCATION Of CAMPlC POINT
                             ER
 NOTES:
    t.  one STSTCM KT/HLtSHto IT MONK simvEr.
    ».  AM H SIFFII DENOTES * »UNFCUl SLUOOE SAMPLE.
    a.  SAimcs OCNCMAUV TAKEN AT SUMFACE. >.t FEET
       AND 4.S rttt OCEP.
    4).  *A«nes *m< tokens OFCATEK TMAN too AfC
       Or aifFA
SCALE
0    SO  100       ZOO FECT


•AtC MA» PDOU MDMII SITE »UOVf T DATED 4/lt.
                           FIGURE 8
HAND AUGER SOIL SAMPLE LOCATIONS
         S8RINGFIELD TOWNSHIP SITE
                   FEASIBILITY STUDY
           MICHIGAN DEPARTMENT OF
                NATURAL RESOURCES

-------
'00
!  O •
                                                                      MW-6
                                                                                               '•MW-8
                                                     MW-IO
                                      DO- 10" •'•'•'•' '0"

                                            •—   j
                                         2SO FEET EAST'
      LEGEND:

     A   •oftmos TO *e tin «v JOROANIKECK d«»s>.

     •   •onwos u« TO u> FEET) BY MOHFI (itie).

    ::=  ACCESS «O»D
NOTES:
  BOXINGS OB-10S. 106. 10'. AND 108 WE«E CONVERTED
  TO MONITORING WELLS MW-IOV 106. 107. AND ice
  RLSt'LCUvtl*. Sit flliUHt 4 HJK LXAC1 LOCATIONS 0^
  OB-10*. 107. AND IOC.
    SCALE
            100
                      200 FEET
                                       FIGURE  7
           TEST PITS AND DEEP BORING LOCATIONS
                      SPRINGFIELD TOWNSHIP SITE
                                FEASIBILITY STUDY
                        MICHIGAN DEPARTMENT OF
                             UATIIBAi  Beer

-------
                 NORTH
                                                                                          8O ITH
     I— 1120
     — 1110
    wrt^ 1^%^ >
INCL.UDED

TEST PIT J
2 ^-1
i ^1
Q:^
^\
TES r PIT 3,
** w * *
I * 2 I ^



















0.03
0.45
0







001
0.5.'
0

0.14
0.37
0












0.04
046
0
11.7^*N_
0.22
0













115.6
0.48
0
. 	 ^
3964
42.4
6HO







950
141.5
5?


1356
58
3.4

35289
931.5
780




r--***' 7732
15.7
94830 67
513
21
11639
787
310
0
196
?00 360
0
x^








.-^
\ •' '




0.09
19.2
° l
xn.08
0.08 6.6
3.2 U
0.7
^F
.T
°^*n b.osl . L o
A
1


100
29



070
116.7
0






439
0
0.73
1.49
0.46























1^ % 5.1 |0.82
g 85 R 0.64
f ^
0.4 610
•il 14S
14 2«

1.1
0.32
0






1
!








f 0.09
n tt 1 "-20
0.23 | n
0.76 • u
0



ORGANIC CONTAMIN/
     I—1080
  NO HORIZONTAL SCALE
                          LEGEND:
                            1356 TOTAL VOLATILES. PPM
                              58 TOTAL SEMIVOLATILES. PPM
                              3.4 TOTAL PCB. PPM
4465-53
                                                                        FIG JRE  9
                                                                       TS Ihf SOI S
                                                     PEEP BORINGS AND  TEST PI S
                                                      SPRINGFIELD TOWNSHIP SI E
                                                                FFASIBILITY  STU Y
                                                        MICHIGAN  DEPARTMENT  r
                                                             NATURAL RESOURC 3
                                                     ,	  CJORDANCO •

-------
                                                               11

pit location where total VOCs were found at 9,000 ppm and 12,100
ppm at a depth of 2.5 feet.   The chemicals found at high
concentrations were primarily aromatics (toluene and xylene).

PCBs, principally identified as Arochlor 1254 and Arochlor 1260,
were widely distributed through the shallow soils and detected in
one fifth of the samples analyzed.  Indicative of the relative
immobility of PCBs, the distribution of PCBs in soils at the site
decreases with depth.  The exception to this is in the principal
disposal pit area where infiltration of solvents may have
solubilized and carried semi-volatile organic compounds (SVOCs)
and PCBs deeper.

Pesticides in shallow soils were detected at relatively low
levels, and in some cases identification was tentative.  Dieldrin
was found in two samples with the highest pesticide
concentrations.

The SVOCs are present at the site primarily as phthalates and
polynuclear aromatics (PNAs) with relatively low levels of phenol
and chlorinated aromatics.  The highest concentration of total
PNAs (362 ppm) was found at the disposal pit location.

Elevated levels of inorganics in soils occur largely near the
main disposal areas.  Lead, cadmium, barium and chromium are
elevated in some areas which are may be associated with the
disposal of paint wastes at the site.  $he metals present in the
near surface soils included barium whiclr was detected at 4,540
ppm at a depth of 2.5 feet; cadmium which had a maximum
concentration detected at 2,220 ppm at a depth of 2.5 feet;
chromium which was found at a maximum concentration of 130 ppm;
and lead which was found at a maximum concentration of 5,470 ppm.


5.3.2     Subsurface Soil Contamination

Subsurface soil borings were located in areas where subsurface
contamination was indicated or suspected on the basis of former
site activities and results from the RI.  The first phase of the
sampling consisted of 11 borings to a depth of 25 feet, followed
by a second phase which conducted 11 borings ranging in depths
from 44 to 112 feet (see Figures 9 and 10).
Analysis of the samples from the first phase indicated the
presence of PCBs and VOCs.  PCBs were detected at 680 ppm at 0-2
feet, 5.2 ppm at 13-15 feet, and 3.4 ppm at 23-25 feet.  Organic
chemicals were detected at greater than 1 ppm in 5 out of 11
borings at a depth of 25 feet.  One sample had a concentration of
3 percent of total VOCs (e.g., 3% is equivalent to 30,000 ppm) at
a depth of 3.5 feet.  Another sample result collected from 25
feet had 1,356 ppm of VOCs which led to a second phase of
borings.

-------
                                                               12

Borings from the second phase indicated soil contamination by
VOCs at 11 ppm,  SVOCs at 76 ppm,  pesticides at 1.3 ppm and PCBs
at 19 ppm at 10 feet.  In one boring, PCBs were detected at 44
ppm at 25 feet and 6 ppm at 30 feet,  and total VOCs were detected
at 36 ppm at 75 feet and 3 ppm at 85 feet.  Lead was detected in
borings at 385 ppm at 10 feet and 222 ppm at 25 feet.


5.3.3     Test Pit Soil Contamination

Test pit excavations were made at three locations which were
identified as anomalous during a metal detector and magnetometer
survey conducted at the site (see Figure 11).  These locations
coincided with former disposal and drum storage areas.  Fifteen
samples of soils and sludges were collected and submitted for
analysis.

Test pit number 3, located directly in the area of the former
disposal pit, provided samples with the highest contaminant
concentrations.   VOCs were present at a concentration of about 10
percent in the shallow soils which contained waste materials.
VOCs were detected at 360 ppm and total SVOCs were detected at 37
ppm at a depth of 9 feet.  PCBs were detected at 6.4 ppm at 9
feet and 310 ppm at 8 feet.  Lead was detected at 1,560 ppm.

The concentrations in the other two test pits were lower, but
still revealed significant contamination, i.e., PCBs were
detected at 248 ppm at 3 feet in test pit number 1 and 390 ppm at
2 feet in test pit number 2.  Lead was detected at 5,470 ppm in
test pit number 1.


5.4       Surface Water/Sediment Contamination

There are five kettle wetlands which are located within a 1/4
mile radius of the site. The kettle wetlands appear to contain
perched water which recharges the groundwater; they are not a
reflection of the water table.  The surface water/sediment
sampling of the kettle wetlands was to assess the extent of site-
derived contamination from Springfield Township site.  Analysis
of the samples indicated that past site activities have not
impacted the surface water quality or the wetland sediments.


5.5       Ground Water Contamination

During earlier hydrogeologic studies, 17 monitoring wells were
constructed at the site.  Thirteen additional monitoring wells
were installed in 1982 and eight monitoring wells were installed
in conjunction with the RI/FS.

-------
ul
ui
O
>
UJ
                                                             8
                                 «»
                                 o
   -1110
   - 1100
   -1090
   -1080
   -1070
   -1060
   -1050
   -1040
   -1030
   -1020
   L-1010
                                 m
                                 o
0.01
 NO
 NO
0.01
 NO
 NO
0.01
 NO
 ND
                                   0.04
                                   0.04
                                   ND
0.02
0.12
 NO
               0.02
               0.1
                NO
                                   0.01
                                   0.04
                                   ND
 NOH
      NOTES:

     1  NOT ALL SAMPLES ARE SHOWN. ONLY THOSE SELECTED AS REPRESENTATIVE
       OF  THE CONTAMINANT PROFILE WITH DliPTH

     2. DATA QUALIFIED WITH A 'B' OR "JB" WAS NOT INCLUDED.
        NTAL SCALE
                                                                                         s
                                                                                         S
                                                                                LEGEND


                                                                               11 TOTAL VOA(pt

                                                                               7fi TOTAL SVOA(|

                                                                               19 TOTAL PCB(pp

                                                                              NDNOTOETECTE

                                                                              NA NOT ANALYZE
                                                                             •)

                                                                              n)
                                                                                FIGURE  10
                                                       ORGANIC CONTAMINANTS IN SOILS
                                                                     MDNR DEEP BORINGS
                                                             SPRINGFIELD TOWNSHIP SITE
                                                                       FEASIBILITY  STUDY
                                                               MICHIGAN DEPARTMENT OF
                                                                    NATURAL  RESOURi
                                                      	.	 ECJORDAf

-------
                                                               13

Ground water analyses completed through 1982 revealed that the
levels of contamination were relatively low and that groundwater
gradients were small.  Contaminants were detected up to 40 feet
below the water table.  Neither the total depth of the plume nor
the thickness of the water table aquifer beneath the site had
been defined.

Sampling analysis conducted during the RI revealed the presence
of organic and inorganic chemicals in the groundwater in the
vicinity of the site.  Chlorinated aliphatics and ketones were
consistently detected in site monitoring wells.  Only two wells
had concentrations greater than 10 ppb total chlorinated
aliphatics (primarily 1,1-dichloroethane and 1,1,1-
trichloroethane).  Aliphatics were detected at ranges of 73 ppb
to 134 ppb; ketones were detected at ranges of 85 to 190 ppb
(though their inconsistent detection indicates that ketones are
not a predominant contaminant); and aromatics were detected at
ranges of 15 to 70.6 ppb.

Arsenic and lead were consistently detected in the ground water
samples collected from on-site monitoring wells in concentrations
up to 34 ppb and 67 ppb, respectively.  Other metals found in on-
site ground water include cadmium (6 ppb), chromium (9.5 ppb),
cobalt (19 ppb), and mercury (0.12 ppb).

Analysis of ground water samples collected from 13 area domestic
wells indicated there were elevated concentrations of iron,
copper, and zinc in some samples when compared to background
wells.  The presence of these metals were likely due to
dissolution of the individual water supply systems' piping and .
pumps.  Analyses of area domestic water supply wells indicated no
contamination by site-related contaminants.

The MDNR conducted two sampling episodes in 1987 after the
completion of the RI field work.

Chlorinated aliphatics (primarily 1,1-dichloroethane and 1,1,1-
trichloroethane) were detected in four of the on-site monitoring
veils and two off-site monitoring wells.  The highest on-site
concentration was 234 ppb total chlorinated aliphatics.  Arsenic
was detected in four monitoring wells with the highest
concentration at 29 ppb.  Lead was detected in six wells of which
two off-site wells had concentrations at 150 ppb and 110 ppb.
6.0       Sunary of Site Risks

CERCLA requires that U.S. EPA protect human health and the
environment from current and potential exposure to hazardous
substances found at the site.  The RI Report contains a Risk
Assessment which characterizes the nature and estimates the
  gnitude of potential and/or actual risks to public health and

-------
|00
f   G.
   J
         MW-S
I  - - .
                                       • V V. 1 C
                                                     FIGURE  11
                                                     TEST  PIT  LOCATIONS
                                                     SPRINGFIELD TOWNSHIP SITE

-------
         TABLE  1
     CHEMICALS OF CONCERN
   SPRINGFIELD  TOWNSHIP  SITE
  VOLATILE ORGANIC COMPOUNDS
          2-Butanone
        Chlorobenzene
            To!uene
     1,1,1-Tri'c hi o roe thane
       Trichloroethylene
SEMIVOLATILE ORGANIC COMPOUNDS
  Bis(2-ethyl hexyl )phthala'#>
         Naphthalene
       PCBs/PESTICIDES
           Dieldrin
             PCBs
          INORGANICS
           Arsenic
            Bar i'.jri
             Lead.
           Cadmium
           Chromium

-------
                                                               14

the environment caused by the contaminants identified at the
site.  A summary of the findings of the Risk Assessment is
presented in the following sections.


6.1       Contaminants of Concern

Chemicals identified as chemicals of potential concern and used
in the risk assessment consisted of a variety of organics and
inorganics.  The chemicals of concern were selected to represent
all organic classes (e.g., volatile organic compounds,
semivolatile organic compounds)  and inorganics present at the
site.  Nine chemicals of concern were detected in on-site ground
water monitoring wells and were evaluated in the risk assessment
based on hypothetical exposure through ingestion of ground water.
Eight chemicals of concern were identified based on the soil data
analyses and evaluated in the risk assessment based on
hypothetical exposure through direct contact with and ingestion
of contaminated soils.  The chemicals of concern are listed in
Table 1.  These chemicals have been used to evaluate toxicity,
exposure pathways and potential health risks for individuals
residing near the site or workers/trespassers on the site.


6.2       Exposure Assessment

Potential human exposure pathways evaluated in the baseline risk
assessment include direct contact and ingestion of soils and
ingestion of groundwater under current and future land use
conditions.  Current conditions at the site include a fence,
though access can still be obtained.  Future conditions include
modelling the effects of continued leaching of source materials
into the groundwater and the possibility that even deep
subsurface soils will be disturbed.  Exposure pathways for the
sediments in the marshes in the vicinity of the Springfield site
were also examined.

The exposure pathways for soils assumed recreational exposures
for children (ages 6-15) and adults.  It was hypothesized that
children would access the site six times per year for 3 years and
adults only once in their lifetime under the most probable case
exposure scenario.  For a hypothetical worse case exposure
scenario, it was assumed that the site was unrestricted.  Under
this scenario, children access the site once per week from May
through October for ten years; while adults access the site twice
per week or fifty times per year for ten years.  The groundwater
exposure pathways assumed a lifetime of exposure, 70 years, at an
ingestion rate of two liters of water per day.

The concentrations of chemicals used in the Risk Assessment for
significant exposure pathways are presented in Tables 2, 3, & 4.

-------
                                 Table 3
                         Chemicals of Concern in Soils
           Direct Contact and Ingestion of Contaminated Surface Soil
                  (Onsite; 0-2 ft. depth, Present Conditions)
                                      Average
                                      Concentration
                                      (ug/g)
                      Maviimim
                      Concentration
                      (ug/g)
        2-Butancne
        Toluene
        1, 1, 1-Trichloroethane
        Trichloroethylene
        Bis (2-etnylhexyl) Rithalate
        Naphthalene
        Dieldrin
        PCBs
        Arsenic
        Barium
        Lead
        Cadmium
        Chromium
  0.97
  6.49 J
248.4
  0.0001 J
  0.48
   .71 J
   .72 J
   .33
7.
1.
1.
 19.74
  1.60
765.9
283.9
 49.64
 18.08
   68.87
  390.0
18000
    0.0050 J
   25.00
  350.0
   63.00
   48.00
  680.0
   12.00
18400
 5470
  196.0
  128.0
J = approximate: During the data validation process, certain reported values
were qualified by a "J*' due to a variations in detection levels achieved.
Values qualified with a "J" are, however, real values.  Where these "J"
          values were used, the WJ" was retained and listed above.

-------
 Table 2
Conoc
                                          in Groundwater
                         (Onsite; Present Conditions)
                                     Average
                                     Concentration
                                      (ug/1)
                       Oonoentration
2-Butanone
Qhlorobenzene
Toluene
1, 1, l-Trichlaroethane
Trichloroethylene
Bis (2-ethylhexyl) Fhthalate
Naphthalene
Dieldrin
PCBs
Arsenic
Barium
Lead
4.5 J
0.1 J
0.2
4.6 J
1.2 J
1.6 J

—
-
6.0
57.2
14.6
110.0
3.0 J
7.0
65.0
12.0
10.0

-
-
34.0
349.0
67.0
J = approximate: During the data validation process,  certain reported values
were qualified by a "J" due to a variations in detection levels achieved.
Values qualified with a "J" are, however,  real values.   Where these "J"
qualified values were used, the "J" was retained and listed above.

-------
                                                               15

6.3       Toxicity Assessment

Using data generated during the RI, a site-specific baseline risk
assessment was conducted to characterize the current threat to
human health and the environment for each of the actual or
potential exposure pathways discussed in the above section.
Cancer potency factors (CPFs) have been developed by EPA's
Carcinogenic Assessment Group for estimating excess lifetime
cancer risks associated with exposure to potentially carcinogenic
chemicals.  CPFs, which are expressed in units of (mg/kg-day)"1,
are multiplied by the estimated intake of a potential carcinogen,
in mg/kg-day, to provide an upper-bound estimate of the excess
lifetime cancer risk associated with exposure at that intake
level.  The term "upper bound" reflects the conservative estimate
of the risks calculated from the CPF.  Use of this approach makes
underestimation of the actual cancer risk highly unlikely.
Cancer potency factors are derived from the results of human
epidemiological studies or chronic animal bioassays to which
animal-to-human extrapolation and uncertainty factors have been
applied (e.g., to account for the use of animal data to predict
effects on humans).

Reference doses (RfDs) have been developed by EPA for indicating
the potential for adverse health effects from exposure to
chemicals exhibiting noncarcinogenic effects.  RfDs, which are
expressed in units of mg/kg-day, are estimates of lifetime daily
exposure levels for humans, including sensitive individuals.
Estimated intakes of chemicals from environmental media (e.g.,
the amount of a chemical ingested from contaminated drinking
water) can be compared to the RfD.  RfDs are derived from human
epidemiological studies or animal studies to which uncertainty
factors have been applied (e.g. to account for the use of animal
data to predict effects on humans).  These uncertainty factors
help ensure that the RfDs will not underestimate the potential
for adverse noncarcinogenic effects to occur.

Based on toxicological studies of the contaminants of concern
found in the soil and ground water at the site, some chemicals
are classified as carcinogens (PCBs, dieldrin, TCE, and arsenic)
and noncarcinogens (chlorobenzene, toluene, barium, and lead).


6.4       Risk Characterization

Excess lifetime cancer risks are determined by multiplying the
intake level with the cancer potency factor.  These risks are
probabilities that are generally expressed in scientific notation
(e.g., 1 x 10~6 or IE-6).  An excess lifetime cancer risk of
1 x 10~6 indicates that,  as a plausible upper bound, an
individual has a one in one million chance of developing cancer
as a result of site-related exposure to a carcinogen over a 70-
year lifetime under the specific exposure conditions at a site.

-------
                                   Table 4
                         Chemicals of Concern  in Soils
                                  Sub-Surf aoe
                  (Onsite - 2'  - 100' depth; Future Potential
                        Conditions Assuming Excavation)
                                     Average
                                     Concentration
                                      (ug/g)
                        iff im
                    Concentration
        2-Butanone
        Chlorobenzene
        Toluene
        1,1,1-Trichloroethane
        Trichloroethylene
        Bis (2-ethylhexyl) Bithalate
        Naphthalene
        Dieldrin
        PCBs (Total Aroclor)
        Arsenic
        Barium
  0.32
 11.80 J
147.16
  0.002J
   .60 J
   .20 J
   .60 J
0.
9.
7.
 37.36
  1.9000
 79.8000 J
 71.4000
   34.81
  770.00
12650.00
    0.03
   48.00
  510.00
  330.00

 3800.00
   39.0000
 4540.0000
 3240.0000
J «= approximate: During the data validation process,  certain reported values
were qualified by a "J" due to a variations in detection levels achieved.
Values qualified with a "J" are, however,  real values.   Where these "J"
          values were used, the "J" was retained and listed above.

-------
                                   Table 5
               Risk Assessment Summary - Present Conditions
                         Springfield Township Site
 Exposed                                  Most
Population          Scenario            Probable
                          NCNCARCDtXENIC
Child          Drinking Water           2.6 E-04
               Surface Soil
                 Ingestion              1.0 E-07            8.3 E-03
                 Direct Contact         9.0 E-08            6.7 E-04
  Total Risk                            2.6 E-04            1.0 E-02

Adult          Drinking Water           2.6 E-04            1.5 E-03
               Surface Soil
                 Ingestion              1.6 E-09            1.7 E-04
                 Direct Contact         4.0 E-09            7.0 E-04
  Total Risk                            2.6 E-04 ^          2.4 E-03
Child          Drinking Water                0.40             1.62
               Surface Soil
                 Ingestion                   0.20           622.0
                 Direct Contact              0.17            53.0
  Total Hazard Index                         0.77           677.0
Adult          Drinking Water                0.40             1.6
               Surface Soil
                 Ingestion                   0.16             6.3
                 Direct Contact              0.13            26.4
  Total Hazard Index                         0.70            34.3

-------
                                                               16

Potential concern for noncarcinogenic effects of a single
contaminant in a single medium is expressed as the hazard
quotient (HQ)  (or the ratio of the estimated intake derived from
the contaminant concentration in a given medium to the
contaminant's reference dose).  By adding the HQs for all
contaminants within a medium or across all media to which a given
population may reasonably be exposed,  the Hazard Index (HI) can
be generated.   The HI provides a useful reference point for
gauging the potential significance of multiple contaminant
exposures within a single medium or across media.

The U.S. EPA attempts to reduce risks at Superfund sites to a
range of 1 x 10-4 to 1 x 10-6, with emphasis on the lower end
(1 x 10-6) of the scale.  Any HI value of greater than 1.0
suggests that a noncarcinogen presents a potentially unacceptable
toxic effect.

Under present and future potential conditions on-site for
exposure to contaminated soils, four chemicals (PCBs,  dieldrin,
arsenic, and trichloroethene)  have incremental cancer risks
within or above the target range under present realistic worst
case conditions, with the highest risk posed by PCBs and
dieldrin.  However, under future potential conditions on-site,
incremental cancer risks are within or above the target range for
only two of the four chemicals, PCBs and arsenic.  ("Present
conditions" is defined as potential exposure to chemical levels
that are currently found in the surfacersoil, and "future
potential conditions" is defined as the /conditions that would
exist if, in the future, the subsurface soil were exposed, under
recreational use, and there was no remediation.)  In addition,
four chemicals (chlorobenzene, toluene, barium, and lead) pose a
potentially significant risk of noncarcinogenic adverse effects
under realistic worst case conditions.

Under present conditions on-site for ingestion of contaminated
ground water,  lead poses a potential hazard index ranging from
0.001 to 622 of non-carcinogenic adverse effects, and arsenic
and trichloroethene pose incremental cancer risks ranging from
1.46 X 10 -3 to 1.53 X 10 -9.   Under predicted future potential
conditions (using the Organic Leachate Model), both non-
carcinogenic and carcinogenic risks would be much higher than
under present conditions.  Future potential conditions on-site
take into account chemical leaching from contaminated soils.

A summary of the risk characterization for the site is presented
in Tables 5 and 6. Very low risk was associated with exposure to
marsh sediments and is not presented in the table.

The site is fenced, so access to the contaminated soil is
temporarily restricted.  Casual usage of areas in and
surrounding the site might possibly expose individuals to
potential airborne contaminated particulates.  Ground water in

-------
                                                               17

the area is a source for residential drinking water.  However,
data from the nearby residential wells indicated that the
contaminated ground water has not yet impacted individual
drinking water wells.


6.5       Environmental Risks

The effects of the contamination on the environment were
evaluated using potential exposures for PCBs, VOCs, SVOCs, and
inorganics.  Current and future potential impacts to the
environment are primarily the adverse effects to terrestrial
wildlife which inhabit or feed in the fenced site area where high
levels of contamination were detected in surface soils (3,800 ppm
PCBs, 2,200 ppm cadmium, 5,470 ppm lead).  The site fence
minimizes the intrusion of the large mammals and thus their
contact to contaminated soil or ingestion of on-site flora.
Sampling of nearby kettle wetlands indicated no impact from site-
related activities.  No critical habitats or endangered species
are associated with the site.


7.0       Description of Alternatives

The FS Report presented several remediation alternatives for the
cleanup of the Springfield Township site.  A complete description
of the alternatives and the criteria used to initially screen
them are provided in the FS Report.  Initially 13 alternatives
were examined for remediation of the soil contamination and seven
alternatives were examined for remediation of the ground water
contamination.  Through a pre-screening process in which each of
the alternatives were evaluated with respect to effectiveness,
implementability and cost, five soil remediation alternatives and
two ground water alternatives were retained for final evaluation.
The alternatives are summarized in the following sections.


7.1       Remedial Cleanup Levels

As explained in detail in sections 8.1.2 and 10.0 of this
document, U.S. EPA has used the framework outlined in the NCP to
•elect a remedy that will reduce the concentration of hazardous
substances to levels presenting a site risk of not greater than
1 x 10 -6 or background for carcinogens and a hazard index of one
for noncarcinogens.  These levels also meet the cleanup criteria
described in Michigan Act 307 Rules for Type A/B cleanups
(hereafter referred to as Type A/B cleanup levels).  The cleanup
levels for the Springfield Township site reduce the concentration
of hazardous substances either to levels presenting a 1 X 10 -6
risk or background for carcinogens (Rule 299.5711), to levels
protective of the aquifer (Rule 299.5711), to levels based on

-------
                                  Table 6

                Risk Assessment Sunnary - Future Conditions
                         Springfield Township Site
                           CAHZCNDG39HC
                                          Most              Realistic
Population     gT?n^riQ                 Probable
Child          Drinking Water
                 On-Site                1.8 E-03            1.7 E-02
                 Off-Site               6.3 E-O4            5.8 E-03

               Deep Soil                1.3 E-07            2.9 E-03
                 (direct contact)

  Total Risk                            2.4 E-03            2.6 E-02

Adult          Drinking Water
                 On-Site                1.8 E-03            1.7 E-02
                 Off-Site               6.3 E-04            5.8 E-03

               Deep Soil                7.0 E-09            3.6 E-04
                 (direct contact)

  Total Risk                            2.4 E-O3^          2.3 E-02

Child
MQNCARC

Drinking Water
On-Site
Off-Site
LLNDGUUC EPH4CTS

0.40
0.16

6.7
2.3
                                             0.04
                 (direct contact)

  Total Hazard Index                         0.6                41.1

Adult          Drinking Water
                 On-Site                     0.40                6.7
                 Off-Site                    0.16                2.3

               Deep Soil                     0^0^               16.1
                 (direct contact)

  Total Hazard Index                         0.6                25.1

-------
                               TABLE  7

                              Levels for Chemicals
                           of Concern in Soil
                      at Springfield Township Site
                                  (PIM)
                                       Cleanup levels
                                            on compliance
                                          with ARARs
Dieldrin                                     .08*

Barium2                                   100

t*>*d                                        Background**

Arsenic                                     Background**

Toluene3                                     .800

Chlorobenzene4                              2.8  #

7CE1                                         .06


1 - value calculated using 10"6 cancer risk and Michigan Act 307.

2 - value calculated using proposed Maxijiura Contaminant Level Goal (MCLG)
    in Michigan Act 307.

3 - value calculated using secondary maxiiam contaminant level in
    Michigan Act 307.

4 - value calculated using reference dose (Rfd) in Michigan Act 307.


• .08 or background which ever is higher in Michigan Act 307

** Background in Michigan Act 307 establishes the Type A/B cleanup levels
   which reduces the concentration of hazardous substances to levels of  1
   X 10 ~6 risk-based level for  carcinogens (Rile  299.5711), to levels
   protective of the aquifer  (Rile 299.5711 (1)  (a)),  to levels based on
   taste and  odor  threshold concentrations  (Role  299.5709  (d)}  or to
   detection  limits  or  background  concentrations  levels  at  the
   Springfield Township site.

-------
                                                               18

taste and odor threshold concentrations (Rule 299.5709 (d)),  or
to detection limits or background concentrations.

Cleanup levels for contaminants in soil at Springfield Township
site are 1 ppm for PCBs; 100 ppm for barium; .8 ppm for toluene;
2.8 ppm for chlorobenzene; .06 ppm for TCE; .08 ppm or
background, whichever is higher, for dieldrin;  and background
levels for lead and arsenic (see Table 7) .  Cleanup levels for
contaminants in ground water are .04 ng/1 for toluene and .003
•g/1 for TCE, and background levels for arsenic and lead  (see
Table 8).

U.S. EPA selected the Type A/B cleanup because it will assure
permanence, reliability, and long-term certainty of protection of
human health and the environment; implementation will be cost
effective given the small size of the site and the isolated areas
of high contamination; the toxicity of PCBs at very low
concentrations; the area is zoned residential and agricultural
and anticipated to grow in the next ten years with increased use
for recreational or other use compatible with human presence; and
the State and local community strongly prefer EPA's selected
remedy.


7.2       Volume of Soil Remediation

Based on the soil sampling data collected during the RI, an area
of surficial, subsurface and deep soil requiring remediation was
identified.  The estimated depth of excavation for remediation
ranges from 3 feet to 32 feet and is based on the above defined
cleanup levels.  The estimated volume of excavated soil is
calculated by converting the area of contaminated soils to cubic
yards using the proposed excavated depths.  The areas of
excavation and proposed depths are depicted in Figure 3.  Further
sampling during the remedial design phase will be used to define
the exact areas of excavation and total volume.  Based on
available data, the estimated volumes are as follows:

               Area to be
               Excavated          Area             Volume

Surficial      0- 3 feet      3,687 sq. yds.     3,687 cu. yds.
Subsurface     0-15 feet        657 sg. yds.     3,283 cu. yds.
Deep Soil      0-32 feet        455 sq. yds.     4,849 cu. yds.

The total volume of soil remediation is estimated at 11, 820
cubic yards.

-------
                                                               19

7.3       Volume of Ground Water Treatment

The volume of groundwater was not determined for the FS, because
the contaminated ground water is not immediately impacting area
drinking water wells.  However, the capture zone was determined
to be 1000 feet perpendicular to ground water flow and 300 feet
downgradient.


7.4       Soil Alternative 1: No Action

Under the No Action Alternative, U.S. EPA would not take any
action to remove or reduce contaminant levels on-site.  Ground
vater would continue to be degraded.  Institutional controls
(deed and land-use restrictions) would be necessary to limit
exposure to surface contaminants by restricting the future use of
the site and to protect human health from direct contact.  This
alternative may be effective in the short-term by minimizing
worker exposure and potential impacts to the environment from
construction of treatment systems but is not protective over the
long-term.  Institutional controls would not be effective for the
long-term because they do not reduce the toxicity, mobility
and/or volume of on-site contaminants.  Periodic site inspections
would occur, determining the need for maintenance activities on
the site fence.  Little reduction in risk to human health or the
environment would occur.

The capital costs for this alternative would be $9,213 for site
fencing extensions and deed restrictions.  Annual site
inspections and maintenance could cost $8,315, giving the project
a present-worth cost of $87,601.  This alternative is easily
implementable, but does not protect the public health and the
environment.  This alternative will not meet the identified ARARs
for this site.


7.5       Soil Alternative 2:  Off-site Land Disposal

This alternative would consist of the excavation and transport of
contaminated soil to an off-site, RCRA permitted, land disposal
facility.  About 11,820 cubic yards of contaminated soils would
be excavated and hauled away by truck.  This would not address
contamination in the deep soil at 85 to 95 feet below the
surface.  Surface depressions left by excavations will be
backfilled with clean soil and graded to prevent surface water
ponding.  The RCRA land disposal restrictions, which regulate
the land disposal of RCRA hazardous wastes, may severely limit
the implementability of this alternative.

It is estimated that six months - one year would be required to
implement this alternative.  The capital costs for this remedy

-------
                               TABLE 8

                      Cleanup Levels for Chemicals
                        of Concern in Groundwater
                       at Springfield Township Site
                                   (PFW)

                              Cleanup levels
Contaminant                   based on compliance
                                 with ARARs

Toluene-'                         . 04

TCE1                             .003

Arsenic                          Background**

Lead                             Background**


1 - value is 10~6 Cancer risk

3 - value is secondary maximum contaminant level.

** - Background in Michigan Act 307

-------
                                                               21

incinerated; they will be treated in the same manner as proposed
for the resultant ash

from the incineration.  Not all the on-site contamination will
be addressed by this alternative, so that future monitoring and
perhaps additional treatment will be required.

Construction is expected to take six months to one year.  Based
upon an estimated feed rate of 5 tons/hour, it will take
approximately six months to complete the incineration process.
Capital costs total $8,642,736.  Annual operation and maintenance
costs total $5,618, giving a present-worth cost of $8,664,035.
If inorganics are immobilized in the incinerator ash,
solidification will be unnecessary and a savings of approximately
$2,660,000 would result, giving a present worth cost of
$6,004,035.


7.8       Soil Alternative 5:  On-site Incineration,
          Solidification, In-situ Vacuum Extraction

This Alternative, like Alternative 4, utilizes excavation,
incineration and solidification for the removal and destruction
of contaminated soil as described in Alternative 4 summary.
Alternative 5 also utilizes in-situ vacuum extraction to remove
and treat the organics which have migrated to the deep soil unit.
The system involves the installation of /wells beneath the surface
to create a negative pressure in the ungaturated zone.  The
vacuum induces a flow of air through the soil, thereby
volatilizing VOCs that are absorbed on soil particles and
extracting the contaminants in the vapor phase.  The subsequent
treatment of extracted soil vapors is usually accomplished
through use of a liquid/vapor condenser,  activated carbon
absorber, combustion, or a catalytic oxidation unit.

In-situ vacuum extraction would require site specific field
testing to ascertain its effectiveness prior to full
implementation. This system is highly reliable for removing VOCs.
Alternative 5 will protect human health and the environment as
the soil contaminants will be destroyed,  treated or isolated, and
the ground water degradation source will be eliminated.

Construction and implementation of the Alternative is expected to
take approximately one to two years.  Capital costs are estimated
to be $8,853,613.  Annual operation and maintenance costs total
an estimated $63,418, giving a present-worth cost of $8,991,668.


7.9       Ground Water Alterative 1:  No Action

Under this Alternative, the only remedial response to the present
ground water plume would be to attempt to restrict future ground

-------
                                                               20

would be about $6,717,258.   Annual  maintenance costs would be
about $5,618, resulting in  a present-worth cost of $6,738,556.


7.6       Soil Alternative  3:  Surficial Capping

Alternative 3 consists of capping the surfaces of the site which
exhibit chemical contamination.   This Alternative is similar to
capping required for closure under  the Resource Conservation and
Recovery Act (RCRA)  Subtitle C.   However,  horizontal migration of
hazardous substances may continue depending on the ground water
flow on-site.  The cap would serve  to prevent dermal contact with
surficial contaminants,  as  well  as  to significantly reduce
further leaching of subsurface chemicals by diverting rainwater
away from the contaminated  soil.  The cap also minimizes erosion
by wind and water preventing migration of contaminants in the
soil.  The cap system would consist of a 24 inch layer of
compacted clay, a synthetic liner,  another 24 inches of earthen
materials, and finally clean topsoil and vegetation.  Periodic
inspections and maintenance would be needed to maintain the
physical integrity of the cap to insure against further risk and
to evaluate the effectiveness of the cap to reduce horizontal
migration.

It is estimated that four months would be required to implement
this remedy.  Capital costs total $753,740 for this remedy.
Annual inspection, maintenance,  and security costs total $17,080,
resulting in a present-worth cost estimate of $914,752.  The
technology required for this remedy is well established.
However, the potential for  noise and dust problems exists during
construction.
7.7       Soil Alternative 4:   On-site Incineration,
          Solidification

The same volume of soil  excavated for Alternative 2 would be
excavated and incinerated on-site for this Alternative.  Thermal
destruction by incineration will  permanently treat the PCBs,
VOCs, and pesticides currently contaminating the soil in the
excavated areas.  The deep soil contamination will not be
remediated by this option but  will be left on-site untreated.
The metals in the resultant ash will effectively be immobilized
by solidification, if the ash  does not pass the required tests.
The treated ash will no  longer be considered RCRA hazardous waste
once it no longer exhibits the characteristic of toxicity.
Treatment to stabilize the metals will render the ash inert.  A
treatability study will  be conducted to select the most cost-
effective method of solidification.   The solidified ash will be
backfilled on-site, and  the solidified material will be covered
with clean soil up to the previous grade.  Those soils in which
only metals are detected above cleanup levels will not be

-------
                                                               23

health, attains applicable or relevant and appropriate
requirements (ARARs) ,  is cost-effective and represents the best
balance among the evaluating criteria (see Table 9).  Comparisons
are based on the nine criteria, as determined to be applicable to
this final remedy, outlined in the National Contingency Plan
(Section 300.430(e) (9) (iii) and Section 121 of CERCLA, as amended
(Clean-up Standards) .

The nine criteria are summarized as follows:

     Overall Protection of ljum,an Health and the Environment-
     addresses whether or not a remedy provides adequate
     protection and describes how risks posed through each
     pathway are eliminated, reduced or controlled through
     treatment, engineering controls, or institutional controls.

     Compliance with ARARS (Applicable or Relevant and
     Appropriate Requirements! -addresses whether or not a remedy
     will meet all of the applicable or relevant and appropriate
     requirements (ARARs) of other environmental statutes and/or
     provide grounds for invoking a waiver.

     Long-term Effectiveness and Permanence-refers to the ability
     of a remedy to maintain reliable protection of human health
     and the environment over time once cleanup goals have been
     net.
     Reduction of Toxicitv.  Mobility, or" Voluiflf-is the
     anticipated performance of the treatment technologies a
     remedy may employ.

     Short-term Effectiveness-involves the period of time needed
     to achieve protection and any adverse impacts on human
     health and environment that may be posed during the
     construction and implementation.

     Implementability-is the technical and administrative
     feasibility of a remedy, including the availability of goods
     and services needed to implement the chosen solution.

     Cast-includes capital and operation and maintenance costs
     and present worth.

     Support Agency Acceptance-indicates whether, based on its
     review of the RI/FS and Proposed Plan, the support agency
     concurs, opposes, or has no comment on the preferred
     alternative.  This acceptance will be assessed from support
     agency comments received during the public comment period.

     Community Acceptance-will be assessed later in this Record
     of Decision.

-------
                                                               22

water use through institutional controls and to monitor the
potential migration of contaminants off-site.  Supplemental
monitoring wells would be installed on-site to help track the
plume.  Bi-annual sampling of the wells would occur, and a
contingency plan for future site action would be developed if the
contaminants exceed predetermined limits.

The present-worth cost of this Alternative is estimated to be
$504,613.  Capital costs for placement of additional monitoring
wells total $6,742.  Annual operation, sampling, and maintenance
costs total $52,813.  Additional costs may be incurred at a
future time if off-site drinking water wells are degraded by the
Springfield Township site plume.  These costs have not been
calculated at this time.  The remedy is easily implemented, but
ARARs are not met.


7.10      Ground Water Alternative 2:  Ground Water Extraction
          and Carbon Adsorption

This Alternative would utilize a system of extraction wells to
arrest and reverse the movement of the ground water plume on-
site.  The pH of the extracted ground water would be lowered to
approximately 4.5 to enhance subsequent adsorption.  Activated
carbon is then employed to remove TCE, toluene, lead and arsenic.
TCE would be treated to a target cleanup level of .003 mg//l and
toluene to .04 mg/1, and arsenic and le$d would be treated to
reduce their concentration to background levels.  The area of
attainment would be throughout the area of the plume.

Following treatment, it is anticipated that the cleaned water
would be discharged back into the ground water system after the
pH is readjusted to the neutral range.  The carbon would be
monitored for buildup of radon decay products and, if necessary,
may require disposal as a radioactive waste.  It is anticipated
that the carbon units will be regenerated for reuse in the
treatment system.  Additional ground water sampling will be done,
if necessary, during remedial design (RD) to redefine the extent
of ground water contamination.  The ground water remedy will be
refined based on sampling conducted during RD.

It is estimated that one to one and half years would be required
to implement this alternative.  Capital costs are estimated to be
$47,467 and annual operation and maintenance costs are projected
to be $61,241.  The present-worth cost is estimated at $279.622.


8.0       Summary of Comparative Analysis of Alternatives

Alternatives were evaluated against each other to determine the
most appropriate alternative for remediation of the on-site soils
and ground water contamination that is protective of human

-------
                                                                               TABLE  9   cont.
it tern* »• Protectlvenest
Koote x
1 Ho »i Ion Somewhat
protective
(monitorlnq)
t»tri tlon Remedy Is 'ully
Carb * protective.
*d»0' t Ion
long- tern
ll»ettlve'*is
•
Institutional cxitrolt
may be inrcllnt.le,
Concentrations of
C n^*ni c ( I S fR0y
1 f^c r^n)c ,
Inqrltlon r Uk wit 1
reduced.
Short -term

Inst (tut ion.il control'.
may be reliable iver
Short • term
Air emissions may
increase slightly.
Possible carbon
disposal problems.
• edt» tm of tnttclty
Mobf ir, or Volifn* Implcmentabl 1 My Co-,

No r • '• t ion o' t A S*ly A.
1.
toil* tv. ffx>bilttyt ii*pl emrnt etf .
or v unp ol
Cool' m.lltS.
• «xji> '. to'ieity C.irbon Is very '•
b .
o( w rrs. vohnr reliable, tosy c
and' hility to inplemcnt
ol f -meals.
                                                                                                                                                        Copfunity
                                                                                                                                                                     tttt*
                                                                                                                                            Complltnt
                                                                                                                                 •no.eu
                                                                                                                                            IRtD(  »rp   Won?
                                                                                                                                            r«ot  met
                                                                                                                                                                    Hone
                                                                                                                                  61,?4?
                                                                                                                                                       Acceptable    Acceptable
                                                                                                                                            • re "Ct
Preftn  d »l terntt lve»
a. (  pit«l  costs
b. '  rual operation »nd maintenance
c. I  esent-tiorih cost

-------
                                                                          1AULI 9
                                                            ALTIRNATIVC I VALUATION

Alternative
1. Ho Action

I. Olf-SItt
land Olspos.il

J. Capping

4. On- lit*
Inclnerat 'on
Jolldlf lean-in
*
J. On-«ltt»
Incineration/
Solidification
and In-tltu
toll Vapor
extraction


long- turn
Protect ivenrs* 1 f feet lv>ess
• isltS »rt not Inst ilul tonnl controls
•Hrnu.io-iy cviy l>e u certain.
reduced potentia' for M-
ditiongl remprli nt ion.
• is*s re-vr.f.
Direct fntitact, a'paUs "»y be
• T ion ri)t" protect '•••.
reduced
Remedy is not Some hazards
fully will be
protective. addressed.
lewedv It fully •educe-.! potential far
protective. hirwm exposure to
soil ftf-Vor
Contamu*nt mlqrgtion
to qrounrfwater.



Shof t • term
f f f PI t i vrn«". s
Inst t tut ion.il controls
mny !«• rel i»hle
over the short trri"

Potential for noise,
emissions oVi'tr*)
eicnvntions n'v)
Potential for noi',e
BrvJ dust dur in.)
Construct ion.

Potential for noisr,
dust, and air
excavation, nni|
incineration.
Increased potential
for noise, dust, and
air emissions
especially If off-
site Incineration
occurs.


PMuctinn of to«icM<
»'.liil Ity, or Voliit.
Mo rr-VlCt ion of
•lit ir ity, mnl,)) i(y_
or volume ol
ronto^lnnnu..
Ho reduction, only
1 rnnsfer to .1 more
"si-cure" fnc i 1 i ty.

No r rrVic t ion in
t i'i ic 1 1 y or vol irv
M..(il lily 1'. 1 r-lurf
Over shor t • t Cf i"
Cnntnminnnts ore
flrstt oyrd or
•'$;•.""" " '"* '
Siqni f icnnt
reduct ion ol
ton ic Ity, mrhil ity.
nml volu?ne o*
cont.imin,int \.



»t»f» Crminity St.it*
|mpl emrnt .itn 1 1 1 y Cost (%) Compliance iccept*n-n nrertrd
lor mnbi le
inc inrr nt or .
• Preferred »liernmivrs
                                                                                                                 n. C.ipilnl rosls
                                                                                                                 h. »iwi«l oprr.ilion nnd
                                                                                                                 c. Presrnl-Mor|h cost

-------
TABLE 10
 ARARs
ALTERNATIVES


A
R
MCI 299.35« and MAC
299.3313 to 299.3317
42 U.S. C. 7401 Jt.
seo. and 40 CFR 50.
52
Executive Order
11986 and 11990 and
40 CFR 6. Appendix A
(Wetland and
Management
MCI 299,601 £t. seq.
MAC R. 299. 5101, et
seo. Parts 6 and 7
(Michigan
Environmental
Response Act)
No
Action



X

NA
X




X




Off-Site
Land
Disposal


X

X
X




X




Surficial
Cap



X

X
X




X




Incin
soil
solid of
ash

X

X
X



ff -.
X




Incin. soil
sol id of
ash, SVE


X

X
X




X




CW punp
» treat
carbon
absorpti
on
NA

X
X




X





-------
                                                               24

8.1       Threshold Criteria

The criteria outlined above are commonly grouped into three
groups:  threshold criteria (the first two),  balancing criteria
(the next five),  and modifying criteria (the last two).  The two
threshold criteria must be satisfied by any proposed remedy if it
is to be further considered.  The balancing and modifying
criteria are used to evaluate the strengths and weaknesses of the
variously accepted threshold criteria and to thereby assist in
the choices of an alternative.


8.1.1     Overall Protection of Human Health and the Environment

The soil alternatives, with the exception of the No Action
Alternative, would provide at least some protection of human
health and the environment by preventing direct contact with
contaminated soil.  However, the contaminated soil extends to the
ground water and is a potential source of degradation of the
ground water.  The off-site land disposal, the surficial capping,
and the on-site incineration, solidification alternatives provide
limited protectiveness because these alternatives only partially
address the soil contamination.  VOCs present in the deep soil
unit would not be eliminated, reduced or removed and could
potentially leach to the ground water.  Alternative 5, On-site
Incineration, Solidification, In-situ Vacuum Extraction would
remediate the entire soil column, thereby providing protection of
human health and the environment by eliminating the threat
through direct contact and removing the source of continual
ground water degradation.

The No Action Alternative for ground water does not provide
protection of human health and the environment through ingestion
of contaminated ground water since it only proposes to monitor
the plume.  Ground Water Alternative 2, Ground Hater Extraction
and Carbon Adsorption, would be protective of human health and
the environment,  because it would treat the contaminated ground
water until cleanup levels were achieved.


8.1.2     Compliance with ARARs

Table 10 lists the operational ARARs for the Springfield Township
site.  It only lists those ARARs necessary for on-site remedial
activities. In some instances, rules cited contain both
substantive and procedural or administrative requirements.  Only
the substantive requirements are ARARs for the purpose of on-site
activities.  Examples of administrative or procedural
requirements which are not considered ARARs include, but are not
limited to, reporting requirements and permit application
requirements.

-------
  TABLE 10
(Continued)
ALTERNATIVES
R
A
R
NCL 691.1201, et. SfrQ.
(Anderson Gordon
Rockwell Environmental
Protection Act of
1970)
NCL 325.201 et. sea.
•nd MAC R 299.2901-
299. 2927 (Water Works
and Sewerage System
Act)
NCL 319.211 et. sea.
•nd MAC 299.2201-299.
2229 (Mineral Well
Act)
MCL 281.701 £t. seg.
and MAC 281.921-
281.925 (Goemeere
Anderson Wetland
Protection Act)
NO
ACTION

X



NA



NA


X



OFF-SITE
LAND
DISPOSAL

X



NA



NA


X



SURF1C1AL
CAP

X



NA



NA


X



INCIN.
SOILS
SOL10IFICA
T-ION OF
ASH
X



NA



NA

^-.
X



INCIN.
SOIL
SOLIDIFICA
T-ION OF
ASH, SVE
X



NA



NA


X



GU PUMP «
TREAT,
CARBON
ABSOPRTION

X



X



X


X




-------
                        TABLE 10

                      (continued)
ALTERNATIVES


A
R
40 CFR 141 (MCLs and
non-zero MCLGs for
Constituents of
concern
MCI 282.101 £t. seq.
•nd MAC 323.1701-
17U (Soil Erosion
•nd Sedimentation
control Act)
NCI 336.11 et. seq.
and MCA 336.1201 et.
seg.; 1301 et. seg.;
1701 and 1702 and
1901 et. tea. (Air*
Pollution Act)
49 C« § 107. 171.1-
171.5 (Packaging and
Shipping
requirements for
off-site
transportation
40 C« 268
No Action




X



NA




NA





NA





NA
Off-Site
Land
Disposal


X



X




X





X





X
Surficial
Cap



X



X




NA





NA





NA
Incin.
soils,*
sol idif ica
tion of
ash
X



X




X





/**
V




X
Incin.
•oils.
solidif ica
tion of
ash SVE
X



X




X





NA





X
GW punp
« treat,
carbon
absorpti
on
X



X




X





NA





NA
applicability of these rules will depend on the source of
emissions exceeding threshold quantity limits specified in
the rules for applicability.

-------
  TABLE 10



(Continued)
ALTERHATIVES
R
A
R
MC 323.2201
H. sea.: and
NCL 323.1
i£. «eo.« (yater
•.•source
CeaBision Act)*
MC 299. 4101
It. sea. 4301 et.
sea, and 4601;
U. sea. NCL
299.401, H- sea.
(Sol id
Waste
Act)
NCI 299.501
ej. sea, and MAC
.299.9301 9401. 9501,
9601 it. sea.
(Hazardous Waste
Narisytaarit Act)
MCL 325.1001
and MAC
R. 10601,
et. sea.
Part 6
* The Sta1
Sti
No
Action
X
X
X
NA
Off-Site
Land
Disposal
X
X
X
NA
Surf icial
Cap
X
X
X
NA
Incin.
soils
solid-
ification
of Ash
X
X

NA
Incin.
solid
ifiation
of ash,
SVE
X
X
X
NA
CW punp +
treat
carbon
absorption
X
NA
X
X
be of Michigan has identified the Act as a
ite ARAR. The U.S. EPA disagrees.

-------
  TABLE 10
(Continued)
ALTERHATIVEB


A
R
MCA 325.1666
(Abandonment of wells)
40 CFR 761.40, 60,79
and 40 CFR 266.42 (PCS
Requirements)
40 CFR 144,
146, 264. (Construct ion,
operation, maintenance
plugging, and
abandonment of
extraction, injection
and monitoring welts)
No
Action



NA
X


NA



Off-site
land
Disposal


NA
X


NA



Surficial
Cap



NA
X


NA



Incin.
soils
•olidifica
tion of

NA
X


NA



tncin.
soildifica
tion of
solids,
SVE
NA
X


NA



CW pump «
treat
carbon
absorpt i on

X
NA


X




-------
                                                               26

8.2.1     Long-tern Effectiveness and Permanence

The long-tern effectiveness criterion primarily requires
assessing the magnitude of residual risks remaining after an
alternative has been implemented and the remedial action
objectives have been met.   Long-tern effectiveness of each
alternative's inpact on human health and the environment through
direct contact would be inproved by all of the soil alternatives,
except the No Action Alternative, by either containing, removing,
or treating the surface soil contamination.  However,
Alternatives 2 through 4 would not address the contanination in
the deep soil unit, so long-term maintenance, operation,
monitoring and potential ground water treatment would be required
to ensure protection of the public health and the environment and
achieve a level of long-term protectiveness equivalent to that
provided by Soil alternative 5.  Soil Alternative 5 remediates
the entire contaminated soil strata to cleanup levels that are
in compliance with all ARARs, and eliminates the need for any
further soil or ground water remediation once the soil and ground
water cleanup levels are attained.

Ground Water Alternative 2 would remove the contaminated plume
from the aquifer ensuring its safety as a drinking water source.
This Alternative would reduce the threat of ingesting
contaminants upon completion of the remedy.  The source of
degradation of the aquifer would have to be removed to eliminate
the need for long-term maintenance and monitoring of the ground
water.  This Alternative would have to be coupled with a soil
alternative which eliminates the source of further ground water
degradation to achieve long-term effectiveness and permanence.


8.2.2     Short-term Effectiveness

Short-term effectiveness considers the effects that result during
the implementation of the alternatives.  Except for the No Action
Alternative, the soil alternatives pose a potential for noise,
dust and air emissions which may affect the workers during
excavation, hauling, construction, and/or incineration of the
contaminated soil and preparation of the site for remedy
implementation.  Standard health and safety procedures would be
followed by workers.  Community protection from indirect adverse
effects such as noise, air emissions, dust, and truck traffic
during the remedial activities will be minimized.  Monitoring for
emissions would be performed during the excavation and dust
control measures would be enforced.  Incineration increases the
likelihood of impacts to the on-site workers, area residents and
surrounding environment due to its method of treatment and
requirements for operation.  There are safeguards which can be
incorporated into the incineration operation to insure its
compliance with safety guidelines and regulatory requirements.

-------
                                                               25

Only Soil Alternative 5,  as developed in the FS and the Proposed
Plan, satisfies all identified ARARs for remediating the soil
contamination without development of further actions (e.g.,
implement at ion of a long-term ground water monitoring and
treatment system to clean any ground water contaminated by deep
soil contamination).   Soils which are found at depth are
contaminated with VOCs and SVOCs and may continue to degrade
ground water quality. Since these contaminants remain on-site
with Soil Alternatives 1  through 4,  these alternatives, without
further refinement or remedial action,  do not satisfy all ARARs
identified in attached Table 12.  As examples, these four
alternatives do not,  by themselves,  adequately treat or contain
the contaminated soils in a manner which would satisfy the "RCRA-
type-closure requirements of Michigan Act 64" (e.g., neither
removal of all contaminated subsoils nor long-term ground water
monitoring program to detect and remediate contaminated ground
water), or the preferences in Michigan's Act 307 Rules or SARA to
permanently reduce the volume, mobility or toxicity of the
hazardous substances.  These alternatives may be redesigned or
combined with other remedial actions (e.g. ground water pump and
treat) to meet all of the identified ARARs.  For instance,
Alternative 5 is a refinement of Soil Alternative 4 in that by
adding Soil Vapor Extraction to Soil Alternative 4, the deep soil
contamination is remediated and the potential for future ground
water contamination should be eliminated. Additionally, Soil
Alternative 2 is not consistent with SARA and the Act 307 Rules
in that it calls for disposal, the least preferred remedial
method.  Soil Alternative 2 may also require further treatment of
the contaminated soils prior to their off-site disposal if it is
to comply with the RCRA land ban restrictions.

Ground water Alternative  2 would meet all respective applicable
or relevant and appropriate requirements of Federal and State
environmental laws.  The  No Action Alternative would not meet all
ARARs.

All treatment systems would be designed to operate in compliance
with ARARs.


8.2       Primary Balancing Criteria

Five primary balancing criteria are used to identify major trade-
offs between protective,  ARAR-compliant remedial alternatives.
These trade-offs are ultimately balanced to identify the
preferred alternative and to select the final remedy.  The five
criteria are as follows:

-------
                                                               27

Measures will be taken to minimize any adverse effects from the
handling of the soils and ash.

Air emissions may increase slightly during the ground water
treatment; however, air emissions would be monitored to comply
with Federal and State regulations.  Spent-carbon units would be
treated and disposed at an off-site RCRA permitted facility.  The
No Action Alternative would have little to no short-term impacts.


8.2.3     Reduction of Toxicity, Mobility, or Volume Through
          Treatment

Soil Alternatives 2 and 3 would not reduce the toxicity,
•obility, or volume of the contaminants through treatment.  Off-
site disposal would only remove the contaminants in the surface
and subsurface soil from the Springfield Township site and place
it in a disposal area which is controlled and monitored.
Surficial capping of the site would contain the contaminants and
reduce the infiltration process; however, it does not treat the
toxicity, or volume of the hazardous substances.  Soil
Alternative 4 would reduce the toxicity, mobility, and volume of
contaminants through treatment in the surface and subsurface
soil, but it would not address the VOCs in the deep soil unit
which would continue to degrade the ground water.  Soil
Alternative 5 would achieve this criterion by destroying or
immobilizing the contaminants in the surface and subsurface soil,
and removing the contaminants from the deep soil unit with the
use of the in-situ vacuum extraction system.

Ground Water Alternative 2 would reduce the toxicity, mobility
and volume of the contaminants by extracting them with the
activated carbon unit and subsequently regenerating the unit or
properly disposing of it.  The No Action Alternative would not
satisfy this criterion.


8.2.4     Implementability

Soil Alternatives 2 through 5 utilize technologies that are well
established and easily implemented.  Off-site land disposal would
require that licensed and permitted haulers be hired to haul the
waste and that a permitted special waste landfill be available to
receive the waste.  The implementability of the off-site disposal
alternative will be affected by the treatment of these wastes
prior to their off-site disposal so as to comply with the RCRA
land disposal restrictions.  Transportable incinerators have been
utilized at other Superfund sites and have been effective in
achieving the cleanup levels.  The incinerator for Soil
Alternatives 4 and 5 would require site specific design
specifications and trial burn tests to insure that destruction
and removal efficiencies (ORE) are achieved.  In-situ vacuum

-------
                                                               28

extraction is a simple technology that has been used
successfully.  Soil Alternative 5 would require pilot testing of
the in-situ vacuum extraction and trial burn tests of the
incinerator.

Ground Water Alternative 2 technology is veil established and
easily implemented.


8.2.5     Cost

Cost comparisons of the soil alternatives are based on present-
worth costs.  The No Action Alternative is the least costly of
the alternatives, however, it provides extremely limited
protection of human health and the environment.  The least costly
of the containment or treatment soil alternatives is surficial
capping, however, it, by itself, does not meet ARARs and does not
satisfy the statutory preference for treatment to the maximum
extent practicable.  The two soil treatment alternatives (4 and
5) are comparative in price for present-worth costs ($8,664,035
and $8,991,669, respectively).  Soil Alternative 4 does not
address the source of degradation of the ground water, and could,
therefore, add additional costs in terms of a long-term ground
water remediation and monitoring program.  The additional cost
incurred with Soil Alternative 5 would provide a complete
remediation of the soil, requiring no monitoring and eliminating
degradation of the aquifer.            ^

Ground Water Alternative 2 is less costly than the No Action
Alternative, for remediation of the ground water would be
accomplished in a short time period compared to the long-term
maintenance and monitoring required in the No Action Alternative.

Alternative         Capital Cost   Annual Operation    Present-
                                   and Maintenance     Worth Cost

Soil
  No Action         $    9,212     $  8,315            $   87,600

  Off-site Land
  Disposal          $6,717,258     $  5,619            $6,738,557

  Surficial
  Capping           $  753,739     $ 17,080            $  914,752

  On-site
  Incineration/
  Solidification    $8,642,737     $  5,619            $8,664,035

-------
                                                               29

  On-site
  Incineration/
  Solidification/
  In-situ Vacuum
  Extraction        $8,853,613     $ 36,419            $8,991,669

Ground water
  NO Action         $    6,742     $ 52,814            $  504,614

  Ground Hater
  Extraction/Carbon
  Adsorption        $   47,467     $ 61,242            $  279,622


8.3       Modifying Criteria

These two criteria reflect the comments and concerns of the State
and the local communities on the alternatives presented to
address the Springfield Township site contamination.  These two
criteria are as follows:
8.3.1     Support Agency Acceptance

The Michigan Department of Natural Resources had been the lead
agency for the emergency and removal activities and the RI. The
lead for the project was transferred to/gthe U.S. EPA in 1988 for
completion of the FS.  The MDNR has proVided support and reviewed
this Record of Decision.  A Letter of Concurrence is attached to
this ROD as Attachment 1.  The MDNR in its June 29, 1990 letter
indicated a strong preference for a Type A/B cleanup for the
site.  MDNR clearly indicated their rationale for this
preference, and is in agreement with the cleanup levels and
remedy selected for this site as contained in this Record of
Decision.

   •
8.3.2     Community Acceptance

The comments and concerns from the public regarding the
Springfield Township site and the Proposed Plan are addressed
with the Responsiveness Summary which is Attachment 2 to this
ROD.  In summary, the community is strongly in favor of the
proposed remedial action for the site and for the cleanup levels
established.
9.0       The Selected Remedy

Based on the findings of the RI/FS and the documents within the
Administrative Record and the results of the public comment

-------
                                                               30

period,  the components of the selected remedy for the Springfield
Township site are as follows:

     Soil Alternative 5:   On-site Incineration,  Solidification,
     In-situ Vacuum Extraction

     -Maintenance of the  existing fence and,  if necessary,
     expansion of the fence to secure the site during
     remediation;

     -Trial burn test of  the incinerator to demonstrate its
     effectiveness and compliance with performance standards set
     forth in 40 CFR 264,  Subpart O and to determine
     characteristics of residual ash,  operating parameters and
     limits, and expected emissions;

     -Excavation and thermal destruction of contaminated soils to
     the specified cleanup levels for polychlorinated biphenyls
     (PCBs),  volatile organic compounds (VOCs),  semi-volatile
     organic compounds (SVOCs),  and pesticides from designated
     areas;

     -Solidification of incinerator ash according to ARARs;

     -Solidification of soils contaminated only with
     metals;                           /

     -Redeposition of ash and treated soils on-site (the ash will
     either be stabilized to make it inert prior to its on-site
     disposal or will be  placed in a properly designed waste unit
     on-site);

     -Recontouring of the excavated areas and control of the ash
     or dust emissions;

     -Installation of an  in-situ vacuum extraction system to
     remove VOCs and SVOCs consisting of a network of an
     estimated 12 wells,  screened in the unsaturated soils and
     finished just below  the water table, at the identified areas
     of contaminated soils; the exact location and area
     circumscribed by the system will be defined during the
     remedial design phase of the RD/RA;

     -Pilot test of the in-situ vacuum extraction system to
     demonstrate its effectiveness and its compliance with
     cleanup and performance standards; and

     -Treatment of off-gases from the in-situ vacuum extraction
     operation using vapor-phase carbon units.

     Ground Water Alternative 2:  Ground Hater Extraction/Carbon
     Adsorption

-------
                                                               31

     -Installation of a ground water extraction system with a
     minimum of two extraction wells pumping at a minimum of
     10  gpm to capture the contaminated plume plus the necessary
     number of injection wells to handle the treated ground
     water; development and preparation of detailed design of
     system during the design phase; and

     -Pilot test of ground water extraction and carbon adsorption
     to demonstrate its effectiveness and its compliance with
     performance standards.

The goal of this remedial action is a clean closure which will
treat the contaminated soils and ground water to the Michigan
Type A/B cleanup levels.  This will restore the ground water to
its beneficial use as a drinking water source and eliminate the
direct contact threats resulting from the contaminated soils and
potential for further degradation of the aquifer.  Based on the
information obtained during the RI and the analysis of all
remedial alternatives, the U.S. EPA and the State of Michigan
believe that the selected remedy will achieve this goal.

The selected remedy will include excavation and incineration of
contaminated soils which are expected to take six months to one
year for construction and six months to one year to complete the
incineration process; in-situ solidification of soils
contaminated only with metals  (duration^time has not been
estimated); in-situ vacuum extraction Wfiich is expected to take
approximately one to two years for construction and
implementation; and ground water extraction and carbon adsorption
of the contaminated plume which is expected to take three to six
months for construction and approximately one to two years to
complete treatment of the groundwater.

The selected remedy will be carefully monitored on a regular
basis and adjusted as warranted by the performance data collected
during operation.  Possible modifications to the remedy will
include:

     -reprocess the soil through the incinerator should testing
     indicate that cleanup levels of organics are not achieved;

     -solidification of incinerator ash according to ARARs; and

     -reactivation of the ground water treatment system or
     implementation of other activities, should monitoring
     indicate that concentration levels of contaminants have
     increased above the aquifer final remedial action goals.

The projected remedial action costs for the selected remedy are
$8,853,613 for capital costs, $36,418 for annual operation and
maintenance costs, resulting in $8,991,668 for present-worth
costs for the soil remediation alternative (Table 11); and

-------
                           TABLE 11.
                   SOIL ALTERNATIVE  NO.  5
              ONSITE INCINERATION/SOLIDIFICATION/
                    IN-SITU VACUUM EXTRACTION
                         COST ESTIMATE
CAPUA! AMD HUD COSYS
           UE«
OUAHT11Y
                                     UMITS
UHM COST
                                                            lOUl
SITE rtEPAIATION
1. SITE ClEAtJNC
2. SITE WAD IMC
3. 0UVU SUSSASE
4. rcMCiMC
S. MOBU1UTIOM (ITEMS 1-4}

SOU TIEATNENT
1. tUOT TEST *UIM
2. WELL AIAMDQMMENT
3. SHEET P1LIXC
4. SOU CICAVATIQN
5. TMEtftAL TIEATMENl
6. SOLtOIMCATION
7. SACtflLL AID BECOMPACT
6. flHAL CO Vie
9. HMAL WASUG
10. TOPSOIL
11. VEGETATION
12. WELL IEPLACEMEN1
13. NOC1L12. (ITEMS 2-4. 7-12)
14. UCIHEIAT10N HOIlLlZATtOM
SOU VAPO* TIEATMEWT
1. SITE PIEPAIATIOM COUTUCENCT
(OME TIME COST)
2. INITIAL PU01 TEST
I. CAPPIMC
i. EITIACT10* WELLS (17)
S. Alt «AKOll«C STSTEM
(llOWEI AND DUCTUC)
A. CAtlOv ADSOKPTIO* TIEATMiNT
STSTEM (75 C'N)
7. IIHAUST CAS nx not me
1. VEtlMUTlOk SOU SAHPLIHC
AMD AKA1TSIS
1.55
4,200
1.«00
saoo.oo
i



i
7
10.000
11.870
11.620
10.636
12.766
5.200
16.000
1.800
16.000
7
1
1



ONE WEEK
1500
S50

4

1
4 PEI WEEl

20
ACtE
CU. TO.
CU. TD.
IIKEAI fl.
LUMP SUM



LUMP SUM
EACH
so. n.
cu. TD.
CU. TD.
CU. TD.
CU. TD.
CU. TD.
SO. TD.
CU. TO.
SO. TD.
EAC«*
LUMP/*U*
LUMP-SUM




CU. TD.
fEET

STSTEM

UNIT
rot OME TEAK

SAMPLE
3,n2.95
J.93
11.24
13.46
101

SUITOTAL

150.000.00
674.22
20.23
13.48
300.00
250.00
11.24
5.62
1.69
6.74
0.56
1.64S.5S
lOi
500,000.00



10.000
13.50
50

22.000

16.000
127

127
S6.096.07
16.506.00
20.232.00
10.784.00
5.361.61

S56.979.6E

S150.0DO.OO
4.7lP.ii
202.30C.CD
159.3JJ.6C
5.546.00C.CC-
2.659.500.00
14J.485.8-
29. 2?. .DC
27.040.0:
12.132.0:
6, 96:. CO
V.796.SV
5l.39J.7t
5oc.oo:.o:


i.occ-.o:
lo.ooc.o:
2C.25C.O:
2'.5o:.c:

BE.OOC.O:

i6. o::.::
26.416 ::

2.S-: ::
                                             sucou.

-------
                                  Table  11,  cont.
 WASTE  CNACACTEtlZATIQN
 1. -MILE LAftOMTOll
 X.   »llLO Cut" III
.5.   lA»«ATOtT ANALYSIS
  6
  6
400
                                               MONTHS
                                               "JONTNS
                                              tAAPLES
                                                             J.3T1.10
                                                             7.«6S.90
                                                               $61.8$

                                                          MTOTAL
                                TOTAL  CAPITAL AMD  MXED COSTS
                                CONTINGENCIES (SS)
                                ENC1NIEI1NC AMD ADMINISTIATION (SI)

                                                          TOTAL
   S20.226.60
    47.10$,40
   224.740.00

  S792.162.0C

 8.&46.TJ9.47
   402.4J6.97
   402.4)6.97

M.B5J.6U.4?
O»EKAT10ft AND MAIIITEMANCE COSTS
                                                                          ANNUAL CCS'
1.  riNCINC AND SECUSITt
2.  Alt (LOWER
3.  IEPLACEMENT ACTIVATED CAIBO.
MESENT UOfTK COS!  (r«<) yetrt.  i«10S)
                                                       TOI»L
                                                                                J.61B.SC
                                                                               2D.oo:.o:
                                                                               10.BO:.oo
                                                                           M.W..66E f
ASSUMPTIONS USED IN THE DEVELOPMENT Of  COST  ESTIMATE

1.  This cost cstiMte wtt pr*p*rtd uking eoct*  eer>iifl»rttf appropriate    those
           i«d **»»*.
                           • -SOS to *Sn range.
2.  Costs tstiiMttd
S.  Unit cost for th«rwt trt«t«mt is considered • typieil  vtndor Quote
    to ircluOe •oeililttion. ioplomenttt tori,  ond OC*r«iion »nfi Mim»r\*nce
    of on- tit*
4.
                                                    o<
                                                                   t(
    in fipur* t-\ of tr,i» report.

S.  field Chtnilt to conOuct «ir ojonitoring during project ioplownttt ion.

-------
                                                               32

$47,467 for capital costs,  $61,241 for annual operation and
maintenance costs,  resulting in $279,  622 for present-worth costs
for ground water treatment  (Table 12).  Total present-worth for
the selected remedy is $9,271,290.


10.0      The Statutory Determinations

U.S. EPA's primary responsibilities at Superfund Sites are to
undertake remedial actions  that are protective of human health
and the environment.  In addition, Section 121 of CERCLA
established several other statutory requirements and preferences.
These specify that when completed, the selected remedy must
comply with ARARs under Federal and State environmental laws,
unless a statutory waiver is justified.  The selected remedy must
also be cost effective and  utilize permanent solutions and
alternative treatment or resource recovery technologies to the
maximum extent practicable.   Finally,  the statute includes a
preference for remedies that employ treatment to permanently and
significantly reduce the toxicity, mobility or volume of
hazardous substances, pollutants and contaminants.  The following
sections discuss how the selected remedy, where applicable, meets
the statutory requirements  and preferences.


10.1      Protection of Human Health and the Environment

The selected remedy will be protective of human health and the
environment through destruction and/or stabilization of
contaminated soils and by the extraction and treatment of
contaminated ground water.   The human health threat via direct
contact with contaminated soils and ingestion of contaminated
ground water will be eliminated as well as the environmental
threat via off-site migration of contamination and ingestion,
direct contact, and/or bioaccumulation of contaminants in flora
and fauna.  Upon remediation, carcinogenic risks presented by the
site will not exceed 1 x 10 -6 or background and hazard indices
will not exceed one.

Protection of human health  and the environment will be achieved
by the selected remedy by the excavation and incineration of
surface and subsurface contaminated soils, solidification of
•oils contaminated with inorganics only, solidification if
necessary of incinerator ash, and in-situ vacuum extraction of
organics from contaminated  soils in the deep soil unit.  The
•elected remedy also calls  for treatment of the ground water by
extraction and removal of contaminants by a carbon adsorption
unit.  The used carbon adsorption units will be properly handled
and disposed.

Upon certification of completion of the selected remedy, the
site will be fully remediated and will not require monitoring.

-------
                                   TABLE  12
                       GROUNDWATER ALTERNATIVE NO.  2
                           GROUNDWATER EXTRACTION/
                              CARBON ADSORPTION
                                COST ESTIMATE
CAHTAi AMD M«D COSTS
ESCALATED
ITEM fiUAKTITT UNITS IMIT COST
SITE m»A!AT10M
T. SITE CLEAtlHC 0.1 ACIE 3.371.10
2. SITE GRACING 1.100 SS. TO. 2.25
3. CRAVU SU8SASE 200 CD. TO. 11.24
4. CONCRETE EOUI»*E»a *A5 275 SO. TD. 17.98
S. ICiUlZATIOft (MEMS 1-4) 1 IUHP SUM 1DX
SUBTOTAL
StOUW WATER TREATMENT fAClLlTT
1. IMITIAL TES1IKC 1 LUMP $UH 4.494.80
2. CAtSO* AUSOSfTIO.
TtEATMEkl STS. (SO C^K) 1 LUX" SUM 12.360.7C
3. EVTtACTjOK WEUS 2 EACH 3.371.10
4. lECMACl yUiS 2 EACH . 1.6£5.55
SUBTOTAL
TOTAL CAPITAL AND flXEO COSTS
COMTINCEUC1ES (10X)
EHCINEEIIMC AMD ADMINISTRATION (151)
TOTAL
VERATIOli AND MINTEKANCE COSTS

ITEM
1 WATE> TIEATEMt.,1 STSTEX
2. Ok-SlTC C»OUKD MATE! n*»UC
3. ^ErtlNC UK SECUtlTT
A. CtOUH: WATER HON1TOVIK (•*l-A«KUAl IS «LlS)
ESCALATED
TOTAL

S3J7.11,
2.475.0C
2.24e.o:
4.944.5C
1.000.46
S11.005.07

S4.494.S:

12, 36:. 7:
6.74? ?:
3.37-, .1:
S26.965 E:
S37.97J.E7
3.797.J5
S.Wt.OS
147. 467. J.

ESCAi.AT(3
AMNUAv CCS1
IV f"? '"
2.605.PV
s.6'.e.5:
47.195.4?
MESEH1 WOtTM COST
                                            «5 r"r».
S275.6?.- IE

-------
                                                               33

All contaminants will be reduced to below health-based levels, so
no five year review is required.

There will be no unacceptable short-tern risks or cross-media
impacts caused by the implementation of the selected remedy.
Some short-term risks will be created by the excavation and air
emissions from the incinerator,  off-gases from the in-situ vacuum
extraction and ground water treatment system.  However, regular
monitoring of the air, dust control measures, and proper
installation and operation practices will be implemented to
maintain the risks to acceptable levels.


10.2      Compliance with ARARs

The ARARs for this site are presented in Tables 13 and 14.
Following is a brief narrative summary of the major ARARs and
TBCs presented in the Tables.  The selected remedy will be
designed to meet all applicable or relevant and appropriate
requirements of Federal and more stringent State environmental
laws.

The soil and ground water cleanup standards chosen for the site
are based on U.S. EPA's selection of a type A/B cleanup for this
site.  Criteria for complying with Type A, B or C cleanups are
contained in Michigan's Act 307 Rules. /The substantive
provisions of Parts 6 and 7 of the Act $B7 rules are considered
ARARs for the remedial action to be undertaken at this site.
These rules provide, inter alia, that remedial actions shall be
protective of human health, safety, the environment and natural
resources (Rule 299.5705(1)).  The Act 307 rules specify that
this standard is achieved by a degree of cleanup which conforms
to one or more of the Type A, B or C cleanup criteria.  A Type A
cleanup generally achieves cleanup to background or non-
detectable levels (R299.5707); a Type B meets risk based cleanup
levels in all media (R299.5709-5713, 5723-5725), and a Type C
cleanup is based on a site specific risk assessment which
considers specified criteria (299.5715-19).

As indicated in the FS, reference doses, secondary MCLs, proposed
MCLGs 10-6 cancer risk numbers and background were used to
determine the cleanup levels for the Act 307 Type A/B cleanup.
MCLs, non-zero MCLGs and proposed secondary MCLs are considered
appropriate to the remedial action at the Springfield Township
site because the aquifers are or may be used for drinking water
purposes.  As MCLs and MCLGs apply to water at its point of
distribution ("at the tap"), these levels are appropriate for
ground water at this site because residential wells that would
use this aquifer would have minimal treatment.

The U.S. EPA selected a Type A/B cleanup given the residential
and agricultural nature of the area around the site and its

-------
                            TABLE 13

                          FEDERAL ARARS

The major ARARs that will be addressed and net by the selected
reaedy and whether the ARARs are listed as follows:

     Executive Order 11988 and 11990;  40 CFR 6, Subpart A which
     requires that remedial actions must avoid adverse affects to
     floodplain or wetlands and evaluate potential impacts to
     these areas.

     The Clean Air Act and 40 CFR 50 and 52 which require that
     select types and quantities of air emissions be in
     compliance with regional air pollution control programs;
     approved State Implementation Plans and other appropriate
     federal air criteria.

     40 CFR 141 which requires that ground water used as
     drinking water meet maximum contaminant levels (MCLs) for
     pollutants of concern.

     40 CFR 144 and 146 well plugging and abandonment and other
     requirements for the injection of treated ground water under
     the Underground Injection Control Program.

     40 CFR 268 Land Disposal Restrictions for the handling,
     treatment, and placement of hazardous wastes.

     49 CFR 107 requirements for transporting hazardous materials
     off-site.

     40 CFR 761 TSCA regulations for the treatment, storage, and
     handling of PCBs.

-------
                       TABLE 14

                      STATE ARARs
Act 60 of 1976 (PCB Compounds)  which prohibits the disposal
of waste containing a concentration equal or greater than
100 ppm of PCBs.

Act 64 of 1979 (The Hazardous Waste Management Act) which
regulates the treatment,  transport and disposal of hazardous
wastes from site restoration.

Act 98 of 1913 (The Waterworks and Sewerage Systems Act)
which are rules for construction and operation of sewerage
systems, as applicable for discharge of ground water via new
sewer connection and certification of the operator.

Act 127 of 1970 (The Michigan Environmental Protection Act)
which prohibits any action which pollutes, impairs, or
destroys the State's natural resources, due to any remedial
action at the site.

Act 203 of 1979 (The Goemare-Anderson Wetland Protection
Act) which regulates discharges to wetlands.

Act 307 of 1990 (The Michigan Environmental Response Act)
which provides for response activity to eliminate
environmental contamination as sites containing hazardous
substances and establishes cleanup standards.

Act 315 of 1969 (The Mineral Well Act) which establishes
requirements for monitoring wells at the site.

Act 347 of 1972 (The Soil Erosion and Sedimentation control
Act) which requires a soil erosion control measures at the
site consistent with locally approved soil sedimentation and
erosion control plans or rules.

Act 348 of 1965 (The Air Pollution Act) which requires air
emissions to have 'non-injurious effects."

Act 641 of 1978 (The Solid Waste Management Act) which
establishes provisions governing the regulation and
management of solid waste.

Public Health Code Act 368 which establishes the procedures
for well abandonment.

-------
                                                               34

future growth potential; the present and future potential use of
the property for recreational purposes; its amenability to a
totally clean closure; the small size of the site and the
isolated nature of the areas of high contamination; the increased
permanence,  reliability, and long-term certainty of protection of
human health and the environment; the increased reduction in the
volume of hazardous substances remaining on site; and the State
and community's strong preference for a Type A/B cleanup

Since hazardous wastes will be treated and stored on-site, the
substantive requirements of the Resource Conservation and
Recovery Act (RCRA) and Michigan Act 64 are applicable
requirements which must be  met.  Additionally, excavation and
construction activities must comply with locally promulgated
rules pursuant to Michigan's Soil Erosion and Sedimentation
Control Act (MCL 282.106).

RCRA regulations concerning the design, construction, operation
and maintenance of incinerators are also applicable regulations
with which the remedy must comply.  In addition, storage,
labelling, and packaging of PCB contaminated soil for
incineration must comply with the appropriate requirements found
in the Toxic Substance Control Act (TSCA) and Michigan PCB Rules
MAC 299.3313-3317.  If there are any discharges of treated ground
water to the marshes or surface waters located off-site, they
will have to meet the permit and substantive requirements of all
applicable environmental regulations including, but not limited
to, the Michigan Water Quality Criteria or other specified levels
found in the Clean Water Act or the Michigan Wetlands Protection
Act.  The emission control requirements of the Clean Air Act
(CAA) and Michigan Air Pollution Control Act are potential ARARs
for any on-site incinerator and fugitive dust emissions.
Parameters of concern are nitric oxides (NOx), VOCs, other gases
and particulates.  Air pollution control may also be a part of
the ground water and soils remedial action.

RCRA regulations for the identification of characteristic
hazardous waste will be used to determine whether or not the
incinerator ash can be disposed off-site.  If the incinerator ash
is determined to be a hazardous waste under RCRA, or if any other
hazardous wastes are transported off-site, the Department of
Transportation Rules for transportation of hazardous materials
and RCRA will be applicable to any off-site transportation or
handling of the hazardous wastes.

The ash and residue from the incineration of the contaminated
soils .must be tested to determine if they are non-hazardous,
solid waste regulated by Michigan Act 641 and its implementing
regulations.  If they are regulated non-hazardous, solid wastes,
then the ash must be either: (1) stabilized prior to on-site
disposal; (2) disposed of off-site or (3) disposed of on-site in
an area which meets the location, liner, ground water monitoring

-------
                                                               35

and deed restriction requirements of Michigan Act 641 and its
implementing regulations.

The proposed remedy involves treatment of soils and debris wastes
and placement of residual  ash.   Placement of certain restricted
hazardous wastes or treated residuals is prohibited under the
RCRA Land Disposal Restrictions (LDRs)  unless certain treatment
standards are met.  Because the wastes are not RCRA listed or
unknown to be RCRA characteristic wastes prior to treatment,
they are not subject to any waste code-specific treatment
standards.  Disposal of treatment residuals are subject to the
land disposal restrictions if it is determined that the
incinerator ash exhibits a hazardous characteristic.


10.3      Cost-Effectiveness

The selected remedy for the Springfield Township site is
considered the most cost effective when considering that the site
will be fully remediated requiring no institutional controls or
deed restrictions and that ground water contamination and its
source of degradation will be eliminated.  The other soil
alternatives were less expensive; however, they do not remediate
all the contaminated soils and would not be fully protective of
human health and the environment.  The Ground Water Alternative 2
is less expensive than the No Action Alternative, for it would
not require long-term monitoring and maintenance.  The total cost
of the combined soil and ground water alternatives as the
selected remedy is $ 9,721,290.


10.4      Utilization of Permanent Solutions and Alternative
          Treatment Technologies or Resource Recovery
          Technologies to  the Maximum Extent Practicable

The selected remedy represents the best balance of alternatives
evaluated to address the contamination problems at Springfield
Township site.  By excavating,  incinerating, solidifying, and in-
situ vacuum extraction treatment of the contaminated soils, and
by extracting, treating the contaminated ground water and
reinjecting clean ground water, the potential health threats to
area residents will be drastically reduced and/or eliminated.
The destruction and/or stabilization of the contaminants in the
soils eliminates the future degradation of the ground water.  The
selected remedy offers permanent solutions by utilizing treatment
technologies where practicable with only minimal removal
activities such as the carbon adsorption unit in the ground water
treatment and in the in-situ vacuum extraction which will require
off-site disposal.

-------
                                                               36

10.5      Preference for Treatment as a Principal Element

The principal threats posed by the Springfield Township site are
the contaminants in soil and ground water in concentrations that
exceed acceptable human health risks.  The selected remedy
directly addresses these threats by treatment using on-site
incineration, solidification, in-situ vacuum extraction and
ground water extraction and carbon adsorption which will destroy
or remove the contaminants in the soils and ground water.


11.0      Documentation of Significant Changes

The selected remedy has not changed significantly from the
preferred remedy that was presented within the Proposed Plan and
which was available for public review and comment from July 13,
1990 through September 12, 1990.


12.0      Summary

The presence of soil contamination and ground water contamination
at the Springfield Township site requires that remedial actions
be implemented to reduce the risk to public health and
environment.  The U.S. EPA believes, based on the RI/FS and
Administrative Record, that the selectejJ remedy provides the best
balance of trade-offs among alternatives with respect to the
criteria used to evaluate the remedies. ' Based on the information
available at this time, the U.S. EPA believes that the selected
remedy will be protective of human health and the environment,
will attain ARARs and will utilize permanent solutions and
alternative treatment technologies or resource recovery
technologies to the maximum extent practicable.

-------
MfttUUL MIOMICCI COMMIttlON
 THOMAS j
 MAMV.CNE J
      t  oi/ve»,
STATE OF MICHIGAN


        5?
                                                                     Attachment 1
                                 JAMES J BLANCMARD. Governor

                        DEPARTMENT  OF NATURAL RESOURCES
                                     STCVEN5 T MASON BUILDING
                                         P.O. BOX 300?t
                                        LA.N5INO  Ml 40409
                                      DAVID t. MALES. Director
                                                     September 27, 1990
             Mr.  Valdas Adarakus,  Regional  Administrator
             U.S. Environmental Protection Agency
             Region V,  5RA-14
             230  South  Dearborn
             Chicago,  Illinois 60604

             SUBJECT:   Springfield Township Dump Superfund Site, Oakland  County

             Dear Mr. Adarokus:

             The  Michigan Department of Natural Resources (MDNR), on  behalf of the
             State of Michigan, has reviewed the proposed Record of Decision (ROD)
             for  the Springfield  Township Dump site.  The remedy  in the proposed ROD
             consists  of the following:
                                                     s-
                  * excavation and thermal destruction of soils to remove
                  polychlorinated biphenyls to 1 ppm, as well as volatile
                  organic compounds (VOCs), semi-volatile organic
                  compounds (SVOCs), and pesticides from designated
                  areas;

                  * solidification of incinerator ash and residue to
                  comply with ARARs;

                  * solidification of soils contaminated only with
                  metals to comply with ARARs;

                  * in-situ vacuum extraction to remove VOCs and  SVOCs
                  from the remaining unsaturated soils;

                  * groundwater extraction, treatment with carbon
                  adsorption and  re inject ion of treated water upgradient
                  of the contaminant plume; and

                  * maintenance and possible expansion of the existing
                  fence to secure the site during remedial action.

             We  concur with this  remedy for the Springfield  Township  Dump site.

-------
Yr. Valdas Adamkus                 -2-            September 27, 1990


"he State does not concur with the omission of the Michigan Water
Resources Cowmission Act 245, PA 1929, MCI 323.6(4) and the associated
Part 22 Administrative Rules, MAC R. 323. 2201 fit seg.  The State has
previously identified these requirements as ARARs for the remedial
action being selected for this site.  The Mater Resources Commission Act
and the Part 22 Rules are ARARs for this remedial action as it includes
reinfection of treated water back into the groundwater, an activity
specifically regulated by those rules.

It is the Department's judgement that the selected remedial action for
this site can provide for attainment of all ARARs including the Michigan
Water Resources Commission Act and Part 22 Rules.  The remedial action
Mill halt the migration of contaminated yroundwater and restore the
aquifer to a usable condition.  The purged Mater will be treated prior
to reinfection.  If it is reinjected upgradient and then hydraulically
contained on-site by the purge wells in a manner that will prevent
degradation of groundwater quality, it will be consistent with the Water
Resources Commission Act and Part 22 Rules.

I look forward to implementation of the final remedy for this site.

                                   Sincerely,
                                   OeVtert Rector
                                   Deputy Director
                                   517-373-7917
 cc:  Mr. Jonas Dikinis, U.S. EPA
     Ms. Susan Louisnathan, U.S.  EPA
     Ms. Marilou Martin, U.S.  EPA
     Mr. Jeremy Firestone, AG
     Dr. James Truchan, MDNR
     Mr. Andrew Hogarth, MDNR
     Mr. William Bradford, MDNR
     Ms. Claudia Kerbawy, MDNR
     Ms. Robin Campbell, MDNR

-------
                          ATTACHMENT 2

                     RESPONSIVENESS SUMMARY

                    SPRINGFIELD TOWNSHIP SITE
                       DAVISBURG,  MICHIGAN


The Responsiveness Summary has been prepared to meet the
requirements of Sections 113(k)(2)(B)(iv)  and 117(b) of the
Comprehensive Environmental Response,  Compensation and Liability
Act of 1980 (CERCLA),  as amended by the Super fund Amendments and
Reauthorization Act of 1986 (SARA),  which requires the United
States Environmental Protection Agency (U.S.  EPA) to respond
"...to each of the significant comments,  criticisms, and new data
submitted in written or oral presentations'* on a Proposed Plan
for remedial action.

The U.S. EPA has gathered information on the types and extent of
contamination found,  evaluated remedial measures and has
recommended remedial actions to address the contamination found
at the Springfield Township site,  south of Davisburg in Oakland
County, Michigan.  As part of the  remedial action process, two
public meetings were held at the Springfield Township Hall in
Davisburg.  The purpose of the meetings were to explain the
intent of the project,  to describe the results of the Remedial
Investigation (RI) and the Feasibility Study (FS) ,  and to receive
comments from the public.  The first meeting was held on July 11,
1989 and was attended by approximately 20 citizens.  The second
meeting was the Proposed Plan Public Meeting which was held on
July 24, 1990 and was attended by  approximately 30 citizens.  A
court reporter was present to record the proceedings of the
second public meeting.   A copy of  the transcript is included in
the Administrative Record.

Public participation in Superfund  projects is required by SARA.
Comments received from the public  are considered in the selection
of the remedial action for the site.   The Responsiveness Summary
serves two purposes:   to provide the U.S.  EPA with information
about the community preferences and concerns regarding the
remedial alternatives and to show  members of the community how
their comments were incorporated into the decision-making
process.  Comments regarding information specifically contained
in the RI/FS are not addressed in  this Responsiveness Summary as
this information is contained in the reports available in
Springfield Township Hall, 640 Broadway,  Davisburg, Michigan.
Also, comments not directly related to the selection of the
remedial alternatives have not been addressed within the
Responsiveness Summary.

This document summarizes the oral  comments received at the public
meeting held on July 24, 1990, and the written comments received
during the public comment period running from July 13, 1990

-------
through September 12, 1990.  Please refer to Appendix A for a
list of the commenters.

Judging from the comments received during the public comment
period, the selected remedy specified in the Record of Decision
(ROD) is supported by the residents of Springfield Township.  The
Michigan Department of Natural Resources (MDNR) also concurs with
the selected remedy.  The Springfield Township Board also
supports the selected remedy which accomplishes their primary
objective, complete cleanup.  The Springfield Township Board and
area residents urged that the project "move forward with as much
speed as possible."

Comments received during the public comment period on the FS and
Proposed Plan for the selected remedy along with U.S. EPA's
responses are summarized below.  Comments and responses have been
divided into three sections and are further categorized by topic
within each section.  The three sections are as follows:

     A.   Summary of comments received during the public meeting,
          July 24, 1990;

     B.   Summary of comments submitted by the public during the
          public comment period; and

     C.   Summary of comments prepared for the PRP Steering
          Committee by their consultants.

The comments below have been paraphrased in order to effectively
summarize them in this document.  Copies^ of the public meeting
transcript and written comments are available for review at the
public information repository.


A.   SUMMARY OF COMMENTS RECEIVED DURING THE PUBLIC MEETING,
     JULY 24, 1990

Comment:  One resident inquired as to the how long it would take
     to implement the ground water treatment phase.

Response: The Groundwater Alternative, Ground Water Extraction
     and Carbon Adsorption, technology has been widely used at
     other hazardous waste sites, and equipment is readily
     available.  It is estimated that one month will be required
     to complete construction of the system once the contractor
     is selected.  A two month pilot test may be required to
     determine the final design parameters.  The ground water
     treatment is expected to take a year to a year and a half
     before the ground water is remediated to cleanup levels.

     The Ground Hater Alternative will be developed during the
     remedial design phase of the project.  Pending the

-------
     finalization of design plans,  the ground water treatment may
     not be implemented until soil  contamination,  the source of
     ground water degradation,  is eliminated.  The Soil
     Alternative is estimated to take between one and two years
     before completion of the remediation.

Cement:  One resident inquired as  to the location of the
     Springfield Township site.

Response:  The Springfield Township site is located at 12955
     Woodland Trail, formerly Shindler Rd., in Springfield
     Township, Oakland County,  Michigan.  The Springfield
     Township site is on the National Priorities List which
     targets it for investigation as a potential source of risks
     to the public health and the environment.

Comment:  One public meeting attendee asked if there would be
     further clarification as to how the cleanup levels were
     derived from the new (Michigan)  Act 307 Rules since they
     were not fully explained in the Feasibility Study and the
     Proposed Plan.

Response: The Michigan Act 307 Rules contain cleanup criteria
     which include three different  methods by which cleanup
     levels can be determined.   The levels are Type A, Type B,
     and Type C.  The methodology for Type A cleanup is based on
     background levels or method of detection limits for
     chemicals of concern.  The methodology for Type B cleanup
     uses standardized risk assumptions and exposure assumptions
     to determine cleanup levels which will be protective of
     human health and the environment and the use of the involved
     resource.  R. 299.5709 and R.  299.5711 provide thorough
     explanation on how to apply the Type B cleanup to the
     chemicals of concern and calculate the figures to the site.
     The methodology for Type C cleanup reviews the actual
     conditions of the site; the uses,  present and future, of the
     site; a site specific risk assessment; and cost-
     effectiveness analysis.  R.  299.5717 provides a thorough
     explanation of how to apply the Type C cleanup to the
     chemicals of concern to the site.

Comment:  One public meeting attendee asked if the calculations
     for the cleanup levels would be provided.

Response:  The formula for calculation of the cleanup levels can
     be found in Michigan Act 307 R 299.5711.  The actual
     calculations are as follows:

-------
Dieldrin  Type B Cleanup Criteria
          Direct Contact Soil Criterion
          6.25 X 10 -8 ma/kcr/d x 70 ka x 1000  - 80 ppb or
          (0.09 g/d X 0.5) + (0.9 g/d x 0.01)    .08 ppm
PCB       Type B Cleanup Criteria
          Direct Contact Soil Criterion
          5 X 10 -7 acr/ka/d X 70 ka X 1000     - 650 ppb
          (0.09 g/d X 0.5) + (0.9 g/d X 0.01)    rounded to
                                                 1 ppm
Barium    Type B Cleanup Criteria
          Ground Water Protection, Soil Criterion
          5 ppm (MCLG) x 20 B 100 ppm
Chlorobenzene  Type B Cleanup Criteria
          Ground Water Protection, Soil Criterion
          Rfd - 2 X 10 -2 ng/kg/d
          HLSC - 2X10-2 ncr/kcr/d X 0.2X70kaxlOOO - 140 ppb
                              2 1                  rounded
                                                 to 100 ppb
          20 X 100 ppb (HLSC) = 2000 ppb or  2 ppm
TCE       Type B Cleanup Criteria ••/'
          Ground Water Criterion
          10 -6 GW Concentration «
                9.1 X 10-5 ma/kct/d X 70 ka =3.2 ppb
                           2 1               rounded to
                                             3 ppb
          (10 -6 Dose «= 1 X 10 -6
                        1.1 X 10 -2  mg/kg/d
                                     9.1 X  10  -5 mg/kg/d
          Ground Water Protection, Soil Criterion
          20 X 3 ppb (HLSC) - 60 ppb,  .06 ppm

-------
     Toluene   Type B Cleanup  Criteria
               Ground Water  Criterion

               Proposed  Secondary Maximum Contaminant Level
                    40 ppb,  or .04 ppm

               Ground Water  Protection,  Soil  Criterion

               20  X .04  ppm  (SMCLs) -  .8 ppm

     Arsenic   Type A Cleanup  Criteria
               Ground Water  and Soil Criteria

               Background

     Lead      Type A Cleanup  Criteria
               Ground Water  and Soil Criteria

               Background

Comment:  One public meeting attendee asked how long it would
     take to excavate and remediate the  soil.

Response:  The soil remediation alternative consists of
     excavation, on-site incineration, solidification, and in-
     situ vacuum extraction.   It is estimated that the
     construction,  excavation,  and test  burns for incineration
     will take from 6 months to one year.   Incineration of the
     contaminated  soils  will take approximately one year.
     Solidification, of  the  ash and residue,  if necessary, and of
     the soils contaminated  with metals  will  be interfaced with
     the incineration process  when possible.   The average time
     required to construct an  in-situ vacuum  extraction system is
     one to two months,  and  treatment duration is estimated from
     one to two years.  Total  duration of this alternative
     treatment may take  from two to three years.

Comment:  One resident asked how the implementation of the
     preferred remedy would  impact Shindler Rd.'s (currently,
     Woodland Trail) present and future  condition.

Response:  The preferred remedy entails  on-site treatment of the
     soil and ground water contamination.   Increased traffic on
     Shindler Rd.  would  consist of vehicles transporting the
     necessary equipment and supplies to the  site, commuting of
     on-site workers, and removal of the remedy equipment and
     refuse.

     During the design phase of the remedial  action, Shindler
     Rd. 's condition would be  evaluated  in terms of needed
     improvements  and accessibility.  Any such improvements or
     modifications to Shindler Rd. would be coordinated with the

-------
     necessary agencies and in observance of applicable
     regulations or requirements.  Impact to Shindler Rd. would
     be kept to a minimum, where possible.  Following completion
     of the remedial action,  Shindler Rd. would be restored to
     its original condition in so far as it is practicable.

Comment:  One public meeting attendee asked for the time frame of
     the preferred remedy from the date of the signature of the
     Record of Decision through the remediation of the ground
     water.

Response:  The Record of Decision was signed by the Regional
     Administrator on September 29, 1990.  The actual start date
     of the remedial design would depend on the negotiations
     with the potential responsible parties (PRPs) and its
     outcome.  A projected date for the start of the design
     phase is January 1990.  This phase may take one and half
     years before the remedial action can be implemented which
     would be the summer of 1992.  The total duration of the
     remedial action is estimated at two to three years which
     would place the completion of the activity in 1994 or 1995.

     This time frame is estimated and is dependent on many
     variables which can not be accounted for at this time. A
     more accurate schedule will be provided upon completion of
     the design.

Comment:  One public meeting attendee asked how the treatments
     for the preferred remedy might be sequenced.
                                       />
Response:  The preferred remedy will remediate the soil and the
     ground water contamination of the site.  The soil
     remediation will be implemented initially to control and
     remove the source of degradation to the ground water and
     the risk from direct contact.  It is anticipated that
     excavation and incineration of contaminated soils will
     occur, followed by solidification, unless it can interface
     with the incineration process, and in-situ vacuum
     extraction.  Upon completion of the soil remediation, the
     ground water treatment system will be constructed and
     operated.  During the design and/or operation of these
     treatments, measures will be taken to expedite the
     remediation of this activity.

Comment:  One resident asked what was the noise factor from the
     excavation and incineration of the on-site soils.

Response:  Noise levels are measured by decibels  (dB).  Normal
     conversation is measured at 55-60 dB.  Noise levels for an
     incinerator stack, the main source of noise, is 65 dB.  For
     excavation, the noise levels for construction would be
     applicable, and they are 50 dB.  Both figures are estimated

-------
     readings at a distance of 1/4  mile from the source.   Noise
     levels when positioned next to the incinerator stack would
     be 120 dB,  which is almost equal  to an airplane taking off.
     Noise levels at the excavation site would be 90 dB,  which is
     equivalent  to the noises  of highway traffic.

     Measures to minimize the  noise generated at the site are
     installation of a stack silencer  which would lower the
     readings to 30 dB,  and installation of an air intake
     silencer and additional insulation of air jets.  Possible
     modifications for excavation are  the use of mufflers that
     reduce noise levels by 45 dB,  the modification of the
     radiation fan motor operation,  and possible elimination of
     beeper noises emitted by  vehicles and equipment.

Comment:  One resident asked if the excavation of soils increased
     the likelihood of contamination moving deeper into the soil
     unit.

Response:  The excavation of soils  would temporarily expose lower
     soil profiles possibly containing contaminants to
     precipitation which could potentially carry these
     contaminants deeper into  the soil unit.   The inorganic
     contaminants and PCBs are insoluble in water and generally
     adhere to soil particles,  making  it less likely they will
     migrate deeper via precipitation.    However, the impact of
     excavation  and the exposure of the lower soil profile will
     be considered during the  remedial design.  Safety
     precautions for these concerns and other factors at the site
     will be incorporated into the  impl&entation of the remedy.

Comment:  One resident asked why TCCD  or dioxin which had
     previously  been identified as  a contaminant at the site was
     not mentioned in the current site documents.

Response:  Specific sampling was performed for dioxins and
     dibenzofurans during the  remedial investigation.  The
     samples were analyzed for a congener-specific analysis.  The
     results of  the analysis indicated that the health risk posed
     by dioxins  at the site is below current action levels.  A
     complete explanation of the analysis is provided in the
     Remedial Investigation Report,  Section 5.2.2.1, pages 5-11
     through 5-13.

     Based on the risk assessment of the chemicals detected at
     the site, other chemicals were identified with much higher
     concentrations and toxicity which were used to determine the
     appropriate cleanup action and cleanup levels needed at the
     Springfield Township site.   Excavation and incineration of
     on-site soils were determined  to  be the most effective
     technology  for removing all contaminants, except metals, in

-------
     the excavated soils.   The metal contaminated soils will be
     addressed by solidification.

Content:  One public meeting attendee introduced himself as a
     •ember of the PRP Steering Committee for Springfield
     Township site.  He is acting on behalf of the Steering
     Committee and wanted  to express the Committee's concern that
     "appropriate cleanup  take place at the site..." and that it
     is protective and completed in a timely fashion.  He also
     mentioned that the Committee has met with both EPA and MDNR
     to discuss the site and that they have retained consultants
     to assist with the evaluation of the site and the preferred
     remedy.  He stated that they have a number of concerns about
     the proposed remedies and will be submitting them in a
     written document within the public comment period.  He then
     introduced their consultant.

Response:  U.S. EPA agrees with the Committee's concern that
     appropriate cleanup action be implemented at the site in the
     most timely manner.  U.S. EPA selected what it believes to
     be the best remedy based upon its evaluation using the nine
     criteria (overall protection of human health and the
     environment; compliance with ARARs; long-term effectiveness
     and permanence; reduction of toxicity, mobility or volume;
     short-term effectiveness; implementability; cost; support
     agency acceptance; and community acceptance).

     U.S. EPA acknowledges that meetings with the PRP Steering
     Committee to discuss  the site have^een held.
                                       ' /•'
Comment:  The consultant for the PRP Steering Committee agreed
     with the conclusions  of the Remedial Investigation Report;
     namely that there are two areas of concern, soil and ground
     water.  He stated that they did not agree with the cleanup
     levels established by the U.S. EPA and MDNR, but recognize
     that the ground water needs to be addressed in a timely
     fashion.

     He commented that the soil remediation identified as a
     preferred alternative is based upon the results of the risk
     assessment in the Remedial Investigation Report.  He
     continued that the risk assessment included calculations
     and assumptions for future potential exposure at the site
     for which the alternative has been developed.  He added that
     he did not necessarily agree with the assumptions and
     calculations.

     He acknowledged that  the soil and ground water alternatives
     outlined in the Feasibility Study and the Proposed Plan are
     evaluated based on the nine criteria, of which one is
     compliance with ARARs.  He pointed out that one of the most
     important ARARs for this site is Michigan Act 307

                                8

-------
     administrative  rules which were promulgated on July llth,
     one day before  the  release of the  Feasibility Study and
     Proposed Plan for public  comment and review.   He expressed
     the opinion  that neither  the Feasibility Study nor the
     Proposed Plan provided  a  thorough  or comprehensive
     explanation  of  Act  307  and their application to the site.
     He stated that  an explanation and  discussion should have
     been included in these  documents.

     He commented that the Proposed Plan identified two
     alternatives, one to remediate the soil,  and one to treat
     the ground water at a estimated cost of $300,00.  He
     restated his and the Steering Committee's position that the
     ground water program should be implemented in a timely
     fashion.  However,  he said he did  not feel that the proposed
     remedy for soil was necessary to protect the public health
     and environment.  He added that there are other alternatives
     he will be evaluating which are as protective as the
     preferred remedy and may  be more timely implemented, more
     technically  feasible and  more cost-effective.

Response:  D.S. EPA  agrees with the necessity of selecting a
     remedy protective of human health  and the environment which
     is easily implementable,  readily available and cost-
     effective.   By  evaluating the alternatives against the nine
     criteria,  U.S.  EPA  was  able to select a remedial action for
     the Springfield Township  site which satisfies protection,
     permanence,  implementability, cost-effectiveness, etc.,
     and meets all ARARs.  In  response  £o this detailed comments,
     U.S. EPA has responded  to the generic concerns raised by
     this commenter  in other portions of this Responsiveness
     Summary.

Comment:  One resident identified himself as a homeowner on
     Woodland Trail  who  wanted to make  a comment more for the
     benefit of his  neighbors  in Springfield Township.  He
     indicated that  he had been concerned about the use of
     incineration as a method  for cleanup.  However, after his
     visit to a mobile destruction unit in Chicago, he was
     confident that  it is a  good alternative for this site.

     He explained that he and  the Township Supervisor were given
     a tour of a  transportable incinerator operating a facility
     in the Chicago  area by  the engineer who supervises
     the project. He learned  that the  soils of Springfield
     Township,  sand  and  gravel, are more suitable for use in an
     incinerator.

     He expressed his initial  concern with emissions from the
     incinerator, but upon learning about the system design and
     the computer safe guards, he is convinced that any emissions

-------
     from the stacks will be within the limits of EPA and DNR air
     quality standards.

     He described the computer system which is used to monitor
     the operations and status of the incinerator and which can
     be accessed by the citizens of that area.  He noted that he
     would like to have a similar computer system available to
     the residents of Springfield Township.

     He agreed with the Feasibility Study and Proposed Plan, and
     supports the preferred alternative.  He feels that the soil
     contamination should be addressed before treating the ground
     water contamination.  He stated that as an engineer, he has
     reviewed the documents and shared his opinions with
     colleagues over the years.  He noted that there may be some
     questions that require answers, but they would best be
     addressed during the remedial design stage.

     His last point concerned the possibility of providing
     expeditious fire protection for the site and the nearby
     residential area; perhaps in the form of a neighborhood fire
     truck and training for local residents.

Response:  U.S. EPA thanks the resident for presenting his
     comments and insights concerning the preferred remedy
     technology.  U.S. EPA acknowledges the resident's concern
     for safeguards and fire protection during the remedial
     activity and ensures that the remedial action, to the extent
     necessary, is coordinated with local, State, and Federal
     emergency response personnel.      /

     U.S. EPA would like to add to the resident's comment that
     the incinerator toured at a site in the Chicago area
     represents the type of facility that would be used at the
     Springfield Township site, but not necessarily the actual
     incinerator.  The implementation of the preferred remedy
     would be subject to the specifications developed during the
     remedial design and the awarding of the contract based on
     bid submittals.

     During the design,  all the safeguards and precautionary
     measures and contingency plans including fire protection
     will be examined and incorporated into the final remedial
     alternative design.

Comment:  One resident identified himself as a person who has
     extensive knowledge in engineering and who has served the
     county by studying the solid waste issues.  He felt that it
     provided him with the background to understand the concerns
     and issues involved with technology associated with waste
     handling.  His primary concerns were air quality and noise.
     He went to Chicago with a fellow township resident to tour

                                10

-------
     the incinerator and learned from the on-site engineer that
     there are technical measures which can be added to the
     system to attain reasonable noise levels and to ensure the
     air quality of the stack emissions.

     He added that he supported the recommended alternatives and
     reminded those present at the meeting that the llth
     anniversary of the site discovery date will be observed in
     two weeks.  He stated that there is an obligation on the
     part of politicians and government personnel to clean up
     the site so that there are no remaining risks.

Response:  U.S. EPA thanks the resident for his comments and
     concerns regarding the preferred remedy.  It is the U.S.
     EPA's intent to proceed with this project in a timely
     fashion until the cleanup levels are achieved and the
     remedial action is completed.

Comment:  Three area residents voiced their support for the
     preferred remedy and urged that it be implemented in a most
     expeditious manner.

Response:  U.S. EPA thanks the residents for their comments on
     the preferred remedy and recognizes the need to expedite the
     project so that the cleanup action is performed quickly and
     thoroughly.


B.   SUMMARY OF COMMENTS SUBMITTED BY TH£ PUBLIC

Comment:  Two letters were received from area residents stating
     that they believe the only acceptable alternative is the
     preferred alternative recommended by the U.S. EPA.

Response:  The U.S. EPA thanks the commenters for their support
     of the preferred alternative and appreciates their time and
     interest on this project.

Comment:  The Oakland County Health Division indicated that upon
     review of the laboratory analysis of the soil, sediment and
     ground water sampling; the 1987 report on the site; and the
     remedial alternatives, the preferred alternative would be
     the most effective means of eliminating the risk to public
     health and the environment.  Also mentioned, was that soil
     remediation should be completed before the ground water
     remedy and that some measure of fire protection should be
     developed for possible fire threat from the operation of the
     incinerator.

Response:  The U.S. EPA thanks the commenter for their support of
     the preferred alternative and notes the suggestions for
     sequencing of remedial actions and fire protection measures.

                                11

-------
Content:  The Springfield Township Board stated that they
     supported the preferred alternative because it
     "accomplishes the community's primary objective - complete
     clean-up and an end to the project."  They also urged that
     the project "move forward with as much speed as possible."

Response:  The U.S. EPA thanks the commenter for their support of
     the preferred alternative.  The U.S. EPA acknowledges that
     the project has been in implementation for 11 years and will
     expedite the process to the best of its abilities.


C.   SUMMARY OF COMMENTS PREPARED FOR THE PRP STEERING COMMITTEE
     BY THEIR CONSULTANTS

The following comments were submitted on behalf of the PRP
Steering Committee by Geraghty & Miller, Inc. and Gradient
Corporation:  Comments Relative to the Remedial Investigation,
Feasibility Study, and Proposed Plan for the Springfield Township
Superfund Site and Technical Review Document and Proposal of
Remedial Alternative for the Springfield Township Site.  The
comments are grouped into the following categories:

     Summary Comments
     Remedial Investigation
     Risk Assessment
     Feasibility Comments
     Cleanup Levels
     Proposed Remedial Action Plan
     Evaluation of ARARs               /*•
     Compliance with NCP

The responses are divided into the same categories except for
Summary Comments and Proposed Remedial Action Plan.  Since the
Summary Comments are addressed in detail in the respective
category heading, they are not answered to avoid redundancy.
Comments referring to the Proposed Remedial Action Plan are
addressed in the last section by the same name.


Remedial Investigation

Comment 1:  Commenter states that the RI/FS and all conclusions
     are derived from biased database and are scientifically
     unreliable.  Field screening of 476 collected soil samples
     resulted in only 41% of the samples determined to not be
     "clean" were forwarded for further analysis.  Generating
     data only from predetermined contaminated samples results in
     overestimates of the degree and extensiveness of contaminant
     concentration at the site.  Average concentrations used in
     the Risk Assessment were determined from the 41% analyzed
     samples and do not reflect the number of "non detects."

                                12

-------
Response:  According to the Guidance for Conducting Remedial
     Investigations and Feasibility Studies Under CERCLA (OSWER
     9355.3-01,  October 1988),  "field screening techniques (e.g.,
     soil gas analysis...)  can  be useful for directing soil
     sampling into areas of greatest contamination or 'hot
     spots.'  ...Results of field screening can then be used to
     determine which samples should be further analyzed using
     more rigorous methods." The use of field screening at the
     site optimized the sample  analysis while employing cost
     effective measures.  The selection of specific samples for
     further analysis from 476  samples collected provided data
     indicating actual concentration levels at the site.  The
     samples targeted for further analysis were sent to Contract
     Laboratory Program (CLP) labs which provide
     quantitative data that is  used for determining risk
     assessment values.

     The commenter states that  those samples not used for further
     analysis were considered free of organic chemicals.  The
     Review Report, Section 3.1.1.1, implies that field screening
     was utilized to select 'those samples deemed contaminated'
     for further analysis by the Agency.  The RI Report, Sections
     3.2.5.2 and 3.2.5.3, explains how field screening was used
     to select samples and references Appendix B 5, 6, and 7.  A
     review of the Appendices indicates that the samples were
     screened and ranked based  on the instrument readings.  Of
     the 300 samples collected  for surface soil sampling, 165
     samples were ranked with 1 (1 on a scale of 3 indicated the
     sample with the most pronounced reading) , and of these 165
     samples, less than half (72)  were forwarded to the CLP lab
     for further analysis.   Included in the samples designated
     for further analysis were  samples ranked 2 and 3.  The
     statement by the commenter that those samples not analyzed
     further were free of organic chemicals is not substantiated
     by the field screening summaries in the RI Appendices.

     Surface soil sampling locations were based on a 100 ft. by
     100 ft. grid blocks and topography, accessibility, and
     observations of surficial  contamination.  Discrete samples
     from three depths were collected and screened.  The soil
     boring samplings were located in areas where subsurface
     contamination was indicated or suspected on the basis of
     former site activities and the results from ongoing RI
     exploration.  The samples  were selected from the area of
     concern which is approximately 4 acres in size and within
     the 4 acres the samples are well distributed through out as
     evidence in Figure 8 of the ROD.  Included in those samples
     designated for further analysis are samples which range from
     1 to 3 in the field screening ranking.  The sample results
     indicate that contamination is found throughout the site and
     that the samples are representative of the conditions on
     site.

                                13

-------
     The corrected risk estimates presented by the commenter in
     the Review Report, Section 4.0,  were calculated according to
     U.S. EPA's "Risk Assessment Guidance for Superfund" (OSWER
     EPA 540/1-89/002, December 1989) which was not issued until
     six months after the finalization of the RI Report.  The RI
     risk assessment was prepared according to "Superfund Public
     Health Evaluation Manual" (SPHEM, 1986).  As stated in the
     Preface for the Risk Assessment Guidance for Superfund,
     "issuance of the new manual does not invalidate human health
     risk assessments completed before (or in progress at)  the
     publication date."  Therefore,  the comments are noted but
     are not valid arguments.

     The U.S. EPA does not recognize percentages of samples
     collected containing a contaminant as a reasonable
     determination for the remediation of that contaminant at the
     site.  Remediation is based upon the baseline risk
     assessments using values that are based on analytical data
     and not on the factoring of percentages of occurrences.

     In summary, the comment that the risk assessment values do
     not reflect the 59% "non detects" and are therefore
     overestimates is incorrect because (1) the "non detects"
     noted by the commenter are not "non detects," (2) the risk
     assessment values are based on data results which show
     overall soil contamination as representative of the site
     conditions, and (3) the risk estimates which were prepared
     according to the SPHEM guidance are valid.

Comment 2:  The RI/FS fails to represent' the limited nature of
     contamination at the site which in turn does not support the
     depth and volume of soil proposed for excavation and
     treatment in the final remedy by U.S. EPA.  The commenter's
     calculations for the excavated soil volume using U.S.  EPA's
     depth and area is 17,800 cy.

Response:  The RI report provides a detailed description of the
     sampling conducted during the field investigation and
     provides the results in a descriptive narrative and in
     Appendices B and D.  It is true that the majority of the
     samples containing PCBs are found at a depth of less than 2
     feet and this is reflected in Figure 3 of the ROD in which
     the area (3,687 sg yds) slated for excavation to 3 feet is
     much greater than the other areas requiring deeper
     excavation.  The depths of excavation for the other two
     areas are based on the detected concentration levels of PCBs
     and the cleanup levels chosen by U.S. EPA and in compliance
     with ARARs (applicable, or relevant and appropriate
     requirements).

     One of the ARARs for this site is Michigan Act 307 Rules
     from which a Type A/B cleanup level was selected by U.S.

                                14

-------
     EPA.   The Type A/B cleanup  level  for PCBs is 1 ppm.   The
     comnenter explains in  the Review  Report,  Section 5.1.1.1,
     that  PCBs at levels less than  100 ppm may be left on site  if
     contained according to the  U.S. EPA Guidance on Remedial
     Actions for Superfund  Sites with  PCB Contamination (OSWER
     No. 9355.4-01,  August  1990).   This same guidance states
     "(t)he concentration that defines the area over which some
     action must be taken is the concentration of PCBs that can
     protectively be left on site without management controls...
     A concentration of 1 ppm PCBs  should therefore generally be
     the starting point for analysis at PCB contaminated
     Superfund sites where  land  use is residential."  Since the
     guidance recognizes the validity  of 1 ppm PCB concentration
     as a  starting point, it does not  contradict the Type A/B
     cleanup level for this site which is 1 ppm PCB cleanup
     level.  The guidance also recognizes full treatment of soils
     to levels of 1 ppm PCBs for which no long-term management
     controls (including access  restrictions)  are necessary.

     The excavation depths  and volume  are based on the cleanup
     levels for the site and the depths at which the contaminants
     are located.   The volume of soil  to be excavated is an
     estimated volume and will be refined during the remedial
     design.  U.S. EPA acknowledges that the volume noted in the
     FS may change based on data collected during the design
     phase, but an approximated  volume was necessary for the
     preparation of estimated remedy costs.

Comment 3:  The RI report identifies numerous deficiencies in the
     quality of data generated which ar^ not acknowledged in the
     FS in terms of scoping the  alternatives and cost estimates.
     The commenter questions the U.S.  EPA's entire evaluation of
     the site and the selected remedy  which are based on these
     deficiencies (Review Report 3.1.1).

Response:   Review Report, Section 3.1.1 was reviewed and it was
     unclear what exactly the "numerous deficiencies in the
     quality of data" are without specific citations.  However,
     an attempt will be made to  deduce the referenced
     deficiencies.  These deficiencies seem to be a matter of
     interpretation of the  data  and/or selective nature of the
     sampling.  The selective nature of the sampling was
     addressed in the response to Comment 1.  Interpretation of
     data  is a more difficult issue which is subject to
     differences of opinion from both  parties.

     The  first interpretation of data  by the commenter is that
     PCBs  are not a concern at the  site because of the detection
     frequency when averaged for the total number of samples.
     However, U.S. EPA's review  of  the samples themselves show
     that  levels of 1,938 ppm of PCBs  were detected at the
     surface and 44 ppm of  PCBs  were detected at a depth of 25

                                15

-------
feet.  Given the carcinogenic nature of PCBs, the
residential nature of the area, and the preferred cleanup
level, the U.S. EPA believes that it is correct to select a
remedy that will remediate soils with PCBs to 1 ppm level
which is protective of human health and the environment and
will not require management controls.

The RI presents the PCB data analysis and provides an
assessment of its threat in the Risk Assessment section, but
it does not state that the site is a "PCB Site11 as stated by
the commenter.

The commenter questions the interpretation of RI data for
dieldrin which had a detection frequency of less than 1% if
all 476 samples collected were included.  As noted in an
above statement, U.S. EPA does not recognize the validity of
using a detection frequency to determine the need for
remediation.  Dieldrin was selected as a chemical of concern
according to the methodology stated in the SPHEM; namely,
the chemical represents the most toxic, mobile, and
persistent chemical within its given class.  Some of the
dieldrin samples had lab qualifiers indicating the data
values could not be validated, but not indicating the source
of the difficulty.  However, dieldrin, 4,4'-DDE, 4,4'-DDT,
and 4,4'-DDD were detected without qualifiers in the hand
auger samples from surface soil.  Since dieldrin was
selected as a chemical of concern, its use for cleanup
level will ensure that the other pesticides detected in the
soil will be remediated.          /
                                  • /'•'
The commenter cites the interpretation of data of selective
sampling and its use for developing the Risk Assessment as a
problem.  The U.S. EPA addressed the validity of the
sampling data and its use for developing the Risk Assessment
in its response to Comment 1.  The commenter continues to
use detection frequency as a method for determining risk
estimates which is not acceptable to U.S. EPA.  The U.S. EPA
disagrees with the commenter's opinion that it is an
unreasonable assumption to use the likelihood of continuous
exposure to the maximum contaminated soil in the Risk
Assessment.  The response to Comment 4 in the Risk
Assessment section addresses this concern.

The commenter questions the background levels of inorganics
for the site citing published background soil concentrations
for the State of Michigan.  The U.S. EPA acknowledges that
the background levels for arsenic, lead, and barium may be
those noted in Appendix A of the Review Report.  However,
UiS. EPA prefers to determine the background levels based on
more local and site specific information.  Therefore,
background samples will be collected during the remedial
                           16

-------
     design to establish  the  background cleanup levels for the
     above mentioned inorganics.

     The RI and Feasibility Study indicate that the hydrogeology
     of the site is complex and provides an explanation of the
     hydrogeology and groundvater flow.   Michigan Department of
     Natural Resources provided interpretation of its ground
     water sampling and data  collection from which they provided
     reasonably reliable  information  on the ground water
     elevations and flow.  The commenter indicates that the U.S.
     EPA conclusions are  not  scientifically sound, because the
     coamenter is assuming that the data collected was
     inadequate.   However, the data is  current and quality
     controlled.

     The commenter states that the following are invalid:

     A constant chemical  source because drums and soils were
     removed and the site's use as a  disposal area was for a
     short period.   However,  soil samples indicate the presence
     of contaminants which have been  detected in the ground water
     samples and may continue to  serve  as a source of degradation
     to the ground water.

     No Dilution by Recharge  statement  in the Review Report is
     unclear in its intent, therefore a response is not provided.

     No Chemical Retardation  because  the movement of all
     constituents detected at the site  zTre known to be retarded
     by the sorbent nature of the subsurface materials. U.S.  EPA
     acknowledges that PCBs and metals  are not generally soluble
     in water and may absorb  to the soil particles, but it does
     not agree with the assumption that the volatile organic
     compounds (VOCs)  and semi-VOCs are sorbing to the subsurface
     materials, especially since  they have been detected in the
     ground water.

     Receptor Location has not been identified,  nor has a  plume
     been defined.   Data  analysis in  the RI indicates that the
     ground water beneath the site is contaminated.  The plume
     was identified in the FS in  Figure 1-11 and indicates that
     it is moving off-site to the north-northwest.  The ground
     water plume will be  reanalyzed during the remedial design so
     as to tailor the ground  water treatment system to the actual
     problem.

Comment 4:  The RI and baseline risk  assessment do not adequately
     address the implications of  naturally occurring elevated
     levels of iron, arsenic, and lead;  therefore, what values
     were used?
                               17

-------
Response: The RI states on page 5-7 that "(i)n general, the
     levels of most metals found in the surface soils are within
     the range of naturally occurring concentrations of metals in
     the environment (see Table 14)."   On that same page, the RI
     adds that levels of arsenic,  lead, barium, and lead are
     elevated at the site; barium is detected in one sample at
     4,540 ppm, and lead was detected at 1,378 ppm.  In Table 14,
     the highest level of iron is 7,930 ppm in HA-97 and arsenic
     is 4 ppm in HA-97 (arsenic was detected at 39 ppm in sample
     HA-80 noted in Appendix D-9 of the RI).  On page 5-18 of the
     RI, a chart of the metals detected in the ground water is
     given and their respective background concentrations.
     Background levels for cleanup are applied only to lead and
     arsenic in both soils and ground water and possibly to
     dieldrin in soils.  Since background levels will be used as
     a cleanup standard for arsenic and lead, U.S. EPA recognizes
     that it will be necessary to collect background samples
     during the remedial design to establish site specific
     background levels.


Risk Assessment

Comment 1:  The RI incorrectly presents noncarcinogenic health
     risks by not accounting for exposure frequency.  This error
     resulted in an overestimate of risk by factors of 100
     (probable case) and 1,000 (worst case).

Response:  The Risk Assessment (RA) was^prepared by the MDNR's
     contractor, E.G. Jordan, utilizing /the Superfund Public
     Health Evaluation Manual, (SPHEM) Office of Solid Waste and
     Emergency Response, Directive 9285.4-1, 1986.  On page 96,
     it states "... any single chemical with an exposure level
     greater than the reference level will cause the hazard index
     to exceed unity, and when the index exceeds unity, there may
     be a concern for a potential health risk."  The omission of
     exposure frequency and duration was used as an initial
     screening to identify potential noncarcinogenic risk.  Since
     U.S. EPA does not use a probability approach to estimating
     the potential for noncarcinogenic risk, the calculated
     indices do not imply high, medium or low risk.

Comment 2:  The U.S. EPA's use of an RfD for estimating health
     risks from lead is in violation of its own policy.  Use of a
     scientifically valid risk assessment approach results in
     lead posing no unacceptable health concerns under
     •reasonable maximum exposure" scenarios which is the current
     U.S. EPA method for conducting risk assessments.  This is
     significantly different from its own conclusion in the RI
     that lead poses the most significant noncarcinogenic risk at
     the Site.
                               18

-------
Response:  As stated in the above response to comment 11, the RA
     was conducted according to the SPHEM manual,  which listed an
     RfD for lead of 1.4 x 10-3 mg/kg/day.  since that time, the
     Agency has determined that the RfD for lead is not
     protective because of background exposures to lead, and the
     uncertainty of a safe exposure level for lead existing,
     especially in light of the recent classification of lead as
     a 62 carcinogen.  The STSSC has identified a bio-kinetic
     uptake madel to calculate a safe exposure level to lead
     which has not been approved for use yet by U.S. EPA.
     Consequently, U.S. EPA believes a determination of whether
     the risk from lead was overstated or understated is not
     known.

     The STSSC has identified 500-1000 ppm lead as levels of
     concern using USEPA policy and guidance (Review Document
     p. ES-5).  These levels are exceeded in the disposal area
     as evidenced by the maximum concentration found there.  The
     STSSC is not familiar with the uses of a risk assessment at
     Superfund sites.  A risk assessment is always used to
     determine if action is needed to protect public health and
     the environment, but need not be used to set cleanup
     levels.  Cleanup levels may be based on risk management,
     policy or compliance with ARARs.  Clearly, at the
     Springfield site there is a lead concern,  and the cleanup
     level is consistent with the Type A/B cleanup from Michigan
     Act 307 Rules ARARs and RCRA clean closure policy.

Comment 3:  According to the RI, human contact with site soil
     poses a significant risk under basiftine, current conditions.
     This is inaccurate and causes an unnecessary image of
     imminent endangerment.  The scenarios posed by the RI
     includes very frequent visits onto the site despite the
     existence of a fence.  Despite acknowledgement of restricted
     site access in at least two places in the RI, this fact was
     ignored in developing on-site human exposure scenarios.

Response:  U.S. EPA believes it characterized the site as a
     potential imminent endangerment as a result of the risk
     assessment. The exposure pathways developed in the RI are
     very clear with respect to the scenarios developed and are
     explained within the RI document.  On page 5-75, it is
     written explicitly, " ... derived risk estimates are all
     based on hypothetical exposure scenarios ...  However, it
     should be emphasized that a risk does not exist unless there
     are two basic conditions: 1) the presence of a chemical at
     sufficient concentrations; and 2) an exposed population that
     is coming into contact with that chemical."  On pages 5-74
     through 5-76 of the RI, uncertainties with the risk
     assessment process that overstate or understate the risk are
     enumerated.
                               19

-------
     The U.S.  EPA cannot use site access restrictions in the RA
     process for Superfund sites.  This has been the policy and
     is stated in the 1986 SPHEM manual (page 41),  the newer Risk
     Assessment Guidance for Superfund (OSWER Directive
     9285.701A), 1989, (page 1-11)  and the final National
     Contingency Plan (NCP)  March 8,  1990. The rationale is
     explained in the NCP on page 8711:

          "The role of the baseline risk assessment is to address
          the risk associated with a site in the absence of any
          remedial action or control,  including institutional
          controls.  The baseline assessment is essentially an
          evaluation of the no-action alternative.
          Institutional controls, while not actively cleaning up
          the contamination at the site can control exposure and,
          therefore, are considered to be limited action
          alternatives.  The effectiveness of the
          institutional controls in controlling risk may
          appropriately be considered in evaluating the
          effectiveness of a particular remedial alternative, but
          not as part of the baseline risk assessment."

Comment 4:   The U.S. EPA's "reasonable" worst case human exposure
     scenarios are indeed not reasonable at all, as demonstrated
     by several examples which follow.  For example, the 5,000
     ng/day soil ingestion rate used is 25 times the 200 mg/day
     value recommended in the USEPA's own guidance (USEPA, 1989)
     and is representative only of a pica behavioral abnormality
     which exists in less than 0.5% of the population (USEPA
     Exposure Factors Handbook, 1989) . ^SMso, the absorption
     factors used for inorganics were up to 10 times higher than
     the literature suggests.  In addition, the marsh sediment
     dermal contact rate used, 2.77 mg/cm2, is five times higher
     than the value most frequently used in Risk Assessment
     (Hawley,  1985).  Also,  the use of maximum concentrations
     found anywhere on the site for "worst case" exposures is
     unrealistic.  It assumes that each time a person contacts
     the site (up to 500 total Site visits according to the
     report) contact with precisely the same maximum occurs.
     This is statistically not possible; a more valid approach
     should use a statistically-based upper bound of the entire
     data set.  Finally, the USEPA guidance (USEPA), 1989)
     discourages the use of two exposure scenarios, probable and
     worst case, but recommends that a single "reasonable maximum
     exposure" scenario be used which is representative of actual
     conditions.  When corrected to comply with the U.S. EPA
     guidance while retaining the same exposure scenarios
     described in the RI results, the risk estimates for soil
     exposure are lower by a factor of 150.  Using the same
     corrections while also modifying the exposure scenarios to
     be more realistic results in risk estimates 1,350 times
     lower than those in the RI (Review Report Section 4.1.4).

                                20

-------
     The Risk Assessment for this Site ignored the Agency's own
     guidance on performing Risk Assessments and also violated
     sound scientific and statistical  principals to arrive at
     inflated estimates of risk.

Response:  The U.S.  EPA recognizes that changes in Risk
     Assessment guidance have occurred subsequent to preparation
     of the RA for the Springfield Township site. As indicated
     in the response to comment # 1,  in this section, the RA was
     completed using the SPHEM, 1986  guidance.  The new guidance,
     Risk Assessment Guidance for Superfund, was issued in
     September 1989 and on page ii specifically states:

          "Following the date of its  publication, this manual is
          intended to be used as guidance for all human health
          risk assessments conducted  as part of the Superfund
          remedial investigations and feasibility studies.
          Issuance of this manual does not invalidate human
          health risk assessments completed before (or in
          progress at) the publication date and based on
          previously released Agency  guidance."

     The STSSC has challenged the use of average and worst case
     exposure scenarios and soil ingestion rates developed for
     the Springfield RA.  The use of  such scenarios is
     recommended in the SPHEM on page 50, " A second, and
     generally preferred, approach is to calculate both best
     estimates and conservative upper bound estimates for all
     exposure point chemical concentrations.11  A range of
     possible soil ingestion rates is recommended on page 86,
     "... soil ingestion rates can vary from 0.1-5 grams per
     day, with higher values representative of pica behavior."

     U.S. EPA believes that although  the soil ingestion rates
     have changed and the concept of  reasonable maximum exposure
     scenarios been implemented with  the new guidance, this does
     not have a significant effect on the Risk Assessment for two
     reasons: the use of residential  exposures is also in the new
     guidance to replace exposure scenarios such as trespasser
     scenarios used in the Springfield RA, and the use of
     indicator chemical selection has been eliminated.  In the
     current Springfield RA, a maximum of 500 site visits took
     place in the lifetime of an adult under the worst case
     scenario, the new guidance would call for 365 days per year
     exposure for at least 30 years,  or 10,950 exposure events.
     In the current Springfield RA, only 14 chemicals were
     selected and evaluated, the new  guidance would ask for an
     •valuation of all 54 chemicals detected in the RI
     (Table 19).

     U.S. EPA recognizes that in the  past, best professional
     judgement was used to arrive at  soil ingestion rates and

                               21

-------
exposure frequencies and durations.  The move toward a
standard residential exposure scenario was meant to
eliminate the variation that occurred as a result of best
professional judgement.  U.S. EPA believes that within the
context of the SPHEM the soil ingestion rates and exposure
frequencies and durations are justified.

U.S. EPA notes that as part of their Technical Review
Document, the STSSC has submitted a revised RA for the
Springfield Township site, addressing their concerns about
soil ingestion rates and frequencies of site visits.  In
Table 2 of the document, the worst case risk levels are
still outside of the target risk range for U.S. EPA for PCBs
and dieldrin, just as they were in the RA prepared by E.G.
Jordan.  The Hazard index for lead still exceeds one, even
with the new model suggested by the STSSC, just as in the
E.G. Jordan document.  The revised RA calculations provided
by STSSC can still be used as a basis for action at the
Springfield Township site.

The STSSC also conducted their own RA for the Springfield
Township site purportedly using the new 1989 U.S. EPA
guidance (see page  of the Technical Review Document).
U.S. EPA rejects this RA because it altered the basic
equation on page 6-21 for calculating chemical intakes by
inserting a multiplying factor based on the number of
detects of the chemical in samples.  The effect of adding
this factor was to reduce the dose for each chemical of
concern and subvert the concept of reasonable maximum
exposure identified in the guidanc^ manual.  U.S. EPA
rejects the RA because it also does not consider a
residential exposure scenario recommended by the 1989
guidance on page 6-7:

     "Because residential land use is most often associated
     with the greatest exposures, it is generally the most
     conservative choice to make when deciding what type of
     alternate land use may occur in the future.  However,
     an assumption of future residential land use may not be
     justifiable if the probability that the site will
     support residential use in the future is exceedingly
     •mall."

As stated in the Feasibility Study and Proposed Plan, the
land is zoned residential, so the residential exposure must
be completed.

Nonetheless, despite the problems identified in the STSSC
Reasonable Maximum Exposure RA, U.S. EPA evaluated the
concentration values presented in Table 2 - Summary of
Reasonable Maximum Baseline Risk Calculations of the
Technical Review Document.  Using a residential exposure

                           22

-------
     with 10 years for children  and  30  years  for adults,  and the
     correct chemical  intake  equation  (minus  the illegal
     multiplying factor but with other  variables used by  the
     STSSC), the following table was constructed.

                   Pathway Soil Ingestion

                  95%  Upper     Dose             Risk
         Cone.      Bound     Child   Adult    Child    Adult

PCBs      0.09       321    2.62x10-4 2.0x10-4 2.0x10-3 1.5x10-3
                  Pathway  Dermal  Contact

PCBs      0.09      321      3.3x10-4  7.9x10-4  2.5x10-3 6.0x10-3

     As previously stated,  these risk  numbers are similar to
     those in the Springfield RA and support  our conclusion that
     despite the changes  in the guidance  there has been no
     significant effect on  the conclusions of the RA.
     Furthermore,  because the risk numbers for PCBs are already
     outside the risk range, a recalculation  of risk for other
     chemicals  would only increase the risk in these two
     pathways.   U.S.  EPA  does not  feel that exercise is warranted
     to prove its point in  this matter.

     Likewise,  U.S.  EPA did not reevaluate the groundwater
     pathway submitted  by the STSSC  because the risk was still
     significant,  and as  before accountable by lead and arsenic.
     Finally, U.S. EPA  does not believe it is necessary to
     respond to the marsh sediment contact rate comment as no
     risk was identified  for marsh sediments,  and no remedial
     action is  being planned for them.


Feasibility Study

Comment 1:  The FS appears  to be based on policies and procedures
     that are outdated  by the current  NCP and U.S. EPA guidance;
     which version of the U.S. EPA RI/FS  guidance is the site FS
     based on?

Response:  The  FS preparation was  initiated prior to the
     issuance of the revised NCP and U.S.  EPA guidance,
     therefore, some sections may  reflect procedures and
     methodology that were  utilized  earlier.   Neither the revised
     NCP nor CERCLA required FS's  to be revised.  As stated
     previously, certain  guidances explicitly sanction continued
     use of prior guidances.  As the FS was reworked, however,
     U.S. EPA did revise  sections  based on the revised current
     NCP.  The  U.S.  EPA acknowledges that not all the changes may

                               23

-------
     have been incorporated and that for the reasons articulated
     in this Responsivness Summary to specific examples given by
     this commenter,  does not believe that further refinement is
     necessary.

Comment 2:  Throughout the FS, sections of the NCP are cited
     which were eliminated in the revised NCP; which version of
     the NCP was utilized during the FS evaluation.

Response:  Preparation of the FS and evaluation of possible
     remedial alternatives began before the finalization of the
     current NCP.  It would have to be said that the evaluation
     and preparation of the FS was conducted under both; however,
     revisions and changes were to have been incorporated into
     the final FS so that the FS would reflect the March 14, 1990
     NCP.  To the extent the commenter has provided explicit
     examples where the FS has significant errors that U.S. EPA
     agrees with, U.S. EPA will correct the error in the
     Responsiveness Summary.

Comment 3:  The FS does not incorporate the elevated background
     levels of naturally occurring compounds like iron, etc.
     during the screening and evaluation of the remedial
     technologies.  Specifically, did the U.S. EPA evaluate the
     effects of elevated levels of iron on the ground water
     treatment.

Response:  The U.S. EPA stated in previous comments that
     background levels for naturally occurring compounds in the
     soil will be established during th^ remedial design phase,
     so U.S. EPA does not necessarily agree with the commenter's
     reference to elevated background levels.  U.S. EPA
     considered the naturally occurring compounds when evaluating
     the technologies, for two of these compounds, arsenic and
     lead, are chemicals of concern which are assigned cleanup
     standards.  In the RI, average on-site concentration levels
     and average background levels for iron in ground water are
     noted as 3,730 ppb and 122 ppb, respectively.  U.S. EPA did
     not consider the effects of iron content on the ground
     water treatment system.  During the remedial design, it will
     be determined if a pre-treatment for iron is necessary to
     the ground water treatment process.

Comment 4:  The screening process from the RI/FS guidance
     document dated October 1988 does not appear to have been
     used for the technologies in the FS.  Why was the current
     guidance not followed?

Response:  The Notice to the RI/FS guidance dated October 1988
     states that "(t)he policies and procedures established in
     this document are intended solely for the guidance of
     government personnel...  The Agency reserves the right to

                                24

-------
     act at variance with these policies and procedures and to
     change them at any tine without public notice."  As stated
     earlier,  the preparation of the FS was initiated before the
     issuance  of the RI/FS guidance of October 1988.  The earlier
     screening process is reflected in the FS format and the
     evaluation criteria used.   It was deemed unnecessary to
     mirror the new guidance in the FS since the criteria for the
     evaluation process was valid and provided the same results.

Consent 5:  The STSSC requests an explanation of why three of the
     conventional and 14 of the treatment technologies were
     removed from further consideration in the FS evaluation
     without a discussion.

Response:  The following provides an explanation to the removal
     of the aforementioned technologies:

     Conventional Technologies:

     Subsurface Containment Wall was removed because the depth
     to the confining layer at the site renders excavation
     impracticable.

     Site Fencing was removed since site fencing already existed
     at the site.

     Municipal Water was removed because of the non-existence of
     a public  water supply to the area and the inappropriateness
     of proposing a technology that has social and economic
     implications to the area.          •£'

     Treatment Technologies:

     Biological Methods was removed because it is not effective
     in remediating PCBs, pesticides,  and inorganics and may not
     be effective in remediating the VOCs located in the deep
     soils.

     Composting and Landspreading were removed because due to the
     presence  of PCBs, pesticides, and metals in the soils.

     Acid Leaching, In-situ Thermal Destruction, Catalysis,
     Crystallization, In-Situ Adsorption, Microwave Plasma,
     Particle  Radiation, and Polymerization were removed because
     these technologies are consider conceptual or only proven on
     a bench scale and nay not be implement able.

     Hydrolysis and Oxidation/Hydrogen Peroxide were removed
     because they were not considered appropriate for use at an
     unconfined site with a mixed chemical waste stream since
     they require strictly controlled environments.


                               25

-------
     Distillation was removed because it was considered
     inappropriate for treating a low concentration waste stream
     such as the one at Springfield Township site.

Comment 6:  The FS is deficient since it does not explain how Act
     307 Rules were applied to this site and no calculations
     supporting those levels were presented in the FS
     consequently the public was not provided with an
     opportunity to comment on the application of Act 307.

Response:  The FS and the Administrative Record File contained
     information on how the Michigan Act 307 Rules were applied.
     Tables 2-la and 2-lb of the FS and the June 29, 1990 letter
     from MDNR, which is in the Administrative Record, explain
     the regulatory basis in Michigan Act 307 for each of the
     clean-up levels presented in the FS.  The Michigan Act 307
     rules in turn specify the manner in which cleanup levels are
     to be calculated. (For example, to satisfy the Type B clean-
     up criteria for soils, where the migration pathway is
     inhalation, the hazardous substance concentration shall not
     result in air emissions that cause an increased cancer risk
     Of 1 X 10-6 (R.299.5711(b) (4)) .   MDNR'S June 29, 1990,
     letter also presents MDNR's justification for preferring a
     Type A/B clean-up of the site.  This letter was available in
     the Administrative Record File at the time the FS and
     Proposed Plan were public noticed.  Finally, although not
     necessary or required, U.S. EPA provided this commenter, and
     has included in the Administrative Record File, the staff
     work sheets that were used to apply the Act 307 Type A/B
     cleanup levels to the data contained in the RI for this
     site.

Comment 6a:  There are inconsistencies in the application of the
     307 Rules.  An August 31, 1990 letter adopts the Michigan
     Act 307 Rules procedure for calculating "Human Life Cycle
     Safe Concentrations" and cleanup levels in ground water for
     PCBs, dieldrin, TCE, arsenic, and chlorobenzene.  The Act
     307 Rules specify under 299.5725 2 (b) that HLSC values for
     noncarcinogens are to be based on MCLs when available.

Response:  The U.S. EPA disagrees with this commenter.  There is
     no letter dated August 31, 1990 which adopts cleanup levels.
     The U.S. EPA assumes that the commenter is referring to the
     staff notes on the cleanup calculations that U.S. EPA
     transmitted to the commenter at its request.  These notes do
     not adopt any cleanup levels.  The cleanup levels proposed
     for adoption by U.S. EPA and MDNR for this site are
     contained in the FS and the June 29, 1990 MDNR letter.
     Neither of these documents proposed ground water cleanup
     levels for PCBs or dieldrin.  Of the chemicals listed in
     this comment, the FS and MDNR June 29, 1990 letter do
     establish ground water cleanup-levels for TCE and arsenic.

                                26

-------
     These chemicals are considered carcinogens.  Use of Rule
     299.5725 (2)(b) is inappropriate for establishing cleanup
     levels for these chemicals since it is only to be used to
     establish Type B cleanup levels for noncarcinogens.  The
     proper rule to use to establish a Type B ground water
     cleanup level for TCE would be 299.5709(2)(a).  For arsenic,
     a Type A cleanup was chosen with the proper rule being
     299.5707(a).   This was explained in both the FS and the MDNR
     June 29, 1990 letter.

Content 6b:  Soil cleanup levels have not been based on any
     identified consistent application of ARARs.  The target
     cleanup levels (TCLs) in soil are based on direct contact
     for two chemicals (PCBs and dieldrin) , and are based on
     ground water protection ("20 times" the ground water TCL)
     for four chemicals (TCE, barium, toluene, and
     chlorobenzene).  The U.S.  EPA failed to provide the
     rationale for setting the TCLs.

Response:  U.S. EPA established TCLs according to Type A/B
     cleanup levels of the Michigan Act 307 Rules as explained in
     the letter to Valdas Adamkus from Delbert Rector dated
     June 29, 1990.  Michigan Act 307 Rules call for cleanup
     levels which protect from direct contact or groundwater
     ingestion, which ever is more stringent.  USEPA believes
     this rationale is quite clear.  The more stringent cleanup
     levels are direct contact for PCBs and TCE.

Comment 6c:  Toxicity constants (CPFs a#a RfDs)  used in the
     cleanup level calculations are in st>me cases inconsistent
     with the values used in the Baseline Risk Assessment, and,
     moreover, some are inconsistent with current U.S. EPA
     guidelines.

     The use of any toxicity values in the calculation of risk-
     based cleanup levels which are not those currently
     recommended for use in assessing human health risks and/or
     are different from the values used in the Baseline Risk
     Assessment is inconsistent with the Agency's own procedures
     and policies.  A consistent, and valid, toxicity standard
     •ust be applied for both the cleanup levels and assessing
     baseline health risks.

Response:  The STSSC has misinterpreted the use of the Risk
     Assessment (RA) for Superfund sites.  The RA identified
     risks in the disposal areas for several chemicals of
     concern.  The selection of cleanup levels can be based on
     risk management, policy or ARARs.  The changes in the
     toxicity constants and risk reference doses for these
     chemicals have been evaluated.  These changes are reflected
     in the MDNR letter to U.S. EPA dated June 29, 1990.  These


                                27

-------
     levels represent chemical specific ARARs which must be
     achieved for the Type A/B cleanup standard.

Comment 7:  The FS did not identify the soil volumes or areas
     until after the alternatives had been assembled, and
     therefore do not seem to have been used during the scoping
     of the potential response requirements.

Response:  The FS reports the soil volumes and areas in Section
     3.5.1, because it was the most logical placement within the
     report.  The RI/FS guidance on page 4-15, Section 4.2.3,
     states that "(d)uring the development of alternatives an
     initial determination is made of areas or volumes of media
     to which general response actions might be applied."  The
     areas requiring response actions were delineated based on
     the data collected during the RI.  The areas were further
     differentiated by the depths of contaminants detected,  it
     is this information which was used during the scoping which
     provided the magnitude of contamination.  Soil volumes are
     pertinent to those technologies requiring excavation which
     is not the intent of the scoping step.

Comment 8:  Based on comment 7, were the elimination of
     technologies in any way related to the volumes or areas of
     impacted media.

Response:  The elimination of the three conventional and 14
     treatment technologies was explained in the response to
     comment 5 of this section.
                                       ?
Comment 9:  The volumes of excavated soils presented in Section
     3.5.1 of the FS are inconsistent with the areas and depths
     presented in the same section and Figure 3-3 of the FS.

Response:  The U.S. EPA will require more information to respond
     to the comment concerning the sections which are
     inconsistent with Section 3.5.1.  The U.S. EPA acknowledges
     that the legend on Figure 3-3 contains errors.  For the
     "Depth of Soil Remediation," 1st line, the box for 0-3'
     should be darkened, and 3rd line, the box should be cross-
     hatched with 0-32.'

Comment 10:  Section 3.6.1 of the FS states that there is a one
     percent volume difference between 10 ppm and 1 ppm PCB
     contaminated soil.  A re-evaluation of the information
     indicates there is a 43 percent volume difference between 10
     ppm and 1 ppm.  The assumptions and calculations for the one
     percent figure are requested.

Response:  The estimated volume detailed in Section 3.5.1 in the
     FS provided the following breakdown of areas and ranges of
     depth to be excavated to meet 1 ppm PCB cleanup level:

                                28

-------
     Surficial  Soil           Area            Volume

     0-3 feet                 3,687  sq yd    3,687 cu yd
     0-15 feet                   657  sg yd    3,283 cu yd
     0-32 feet                   455  sg yd    4,849 cu yd

     The excavated volume of soil required to meet the 10 ppm PCS
     cleanup level is based on substituting the 0-32 feet depth
     with 0-27  feet that results in  a  volume of 4,091 cu yd.   The
     RI data indicated that PCBs were  detected at 44 ppm at a
     depth of 25 feet, so to meet a  10 PCB ppm cleanup level  it
     was determined that excavation  to a depth of 27 feet would
     be required in the cross hatched  area in Figure 3 of the
     ROD.  The  volumes for 0-3 feet  and 0-15 feet remain the
     same.  The estimated total volume for 10 ppm PCB cleanup
     level is 11,060 and the estimated total volume for 1 ppm PCB
     cleanup level is 11,820 and that  calculates to .935 percent
     difference.

Conent 11:  The U.S. EPA estimates  the volume of soil to be
     excavated  to be 11,  820 cy; the Review Report estimates the
     volume of  soil to be 17,800 cy; and MDNR estimates the
     volume of  soil to be 13,023 cy.

Response:  As stated earlier, actual soil volumes will be
     determined during the remedial  design phase.

Comment 12:  The calculation of the  extent of impacted media is
     essential  in determining the nature,  cost and duration of an
     appropriate response.   Since the  FJy stated that the volume
     of ground  water to be remediated  could not be determined, it
     is questioned on what basis is  the analysis for the proposed
     soil vapor extraction and carbon  treatment units; and how
     were the cost and duration established?

Response:  The  soil vapor extraction system will be implemented
     to remediate the soil contamination.   The parameters of the
     soil contamination were determined during the RI and were
     used for the suggested design of  the system.  Ground water
     sampling results provided information on which to estimate
     the extent of ground water contamination, the ground water
     flow velocity, and the ground water flow direction.  The
     suggested  design, number of wells, and pump rate for the
     ground water treatment system is  proposed to capture the
     plume.  However, pilot testing  will be conducted to
     determine  the capacity of the carbon column, retention time,
     and pump rate.  Cost for the ground water treatment is based
     on the number of wells, construction of the system, and the
     operation  and maintenance over  a  5 year period.  Actual
     duration of the ground water treatment will be determined
     during the design.
                               29

-------
Comment 13:  It was felt that air stripping was improperly
     removed from consideration and it is requested that it be
     reevaluated as a potential ground water alternative.

Response:  The U.S. EPA may reconsider air stripping during the
     remedial design of the ground water treatment system.

Comment 14:  The screening evaluation of the carbon adsorption
     alternative notes in Section 3.6.3.5 that "(t)he anticipated
     contaminated water waste stream would be low in suspended
     solids or other contaminants which would foul the carbon
     filters.11  This is an incorrect statement since the
     naturally high iron content in the ground water would be
     expected to cause plugging and fouling of the carbon
     filters.  During regular maintenance requirements, it may be
     necessary to pretreat the waste stream.  Therefore, it is
     requested that the Agency reconsider the carbon adsorption
     alternative.

Response:  During the remedial design, the.levels of iron and
     their impact on the carbon treatment will be determined and
     if necessary, a pretreatment system will be developed and
     implemented to render the usage of the carbon filters more
     effective and efficient.

     The U.S. EPA may reconsider during the remedial design phase
     the carbon adsorption treatment and may replace it with air
     stripping as a ground water treatment alternative based on
     remedial design determinations.
                                       '$'
Comment 15:  The soil vapor extraction system, ground water
     treatment system, and removal of contaminated soil under any
     alternative will effectively act together to reduce the
     presence of volatile organics in all affected media.  It is
     asked why was this synergism not reflected in the U.S. EPA's
     alternatives analysis as required by the RI/FS guidance?

Response:  The U.S. EPA did consider the synergism of the
     treatments on the effected media, and that is why
     incineration was selected to remove the contamination by
     PCBs, pesticides, VOCs, and semi-VOCs; solidification was
     •elected to stabilize the inorganics in the incinerator ash,
     if necessary/ and in soils containing only metals; soil
     vapor extraction was selected to remove the VOCs and semi-
     VOCs from the deep soil units; and the ground water
     treatment system will remove those chemicals which have
     migrated from the soils and contaminated the ground water.
     It is recognized that the remediation of the problem at
     Springfield Township site is inter-related, and that the
     technologies must be interfaced to ensure the cleanup to the
     levels selected by U.S. EPA.


                                30

-------
Comment 16:  The solidification/stabilization of ash and
     redeposition of soil  on-site will  effectively decrease the
     permeability of the site surface soil which will lead to
     lower percolation of  rainwater through the soil, and thus
     will lower the leaching potential  of any contaminated
     residuals left in the subsoil.   Will the stabilized soil
     "cap" have an effect  on the  efficiency of the soil vapor
     extraction system or  ground  water  treatment?

Response:  The solidification/stabilization of ash and
     redeposition of soil  on-site does  not necessarily decrease
     the permeability of the site surface soil.  The consistency
     of solidified material can be selected and ranges from
     gravel-like consistency to a type  of monolithic cement
     block.  Gravel-like consistency solidified material would be
     preferable for use at Springfield  Township site.
     Precipitation will be able to percolate through a gravel-
     like solidified material and could cause leaching of the
     contaminants left on-site should the site not be cleaned to
     the Target Cleanup Levels.

     Redeposition of solidified ash,  solidified soils containing
     metals,  and incinerated soil would occur above the ground
     water table which is  at an approximate depth of 85 - 90 feet
     and in a limited area.   The  extent of redeposition will not
     effect the ground water treatment  system.  Depending on the
     soil type, sometimes  it is necessary to cap the area to be
     treated by soil vapor extraction to increase the efficiency
     of the vacuum pumping.   Pilot testing of the soil vapor
     extraction system on-site will determine the need of a cap
     at Springfield Township site.   The physical state of the
     solidified material should not affect the soil vapor
     extraction operation.   However,  if additional soil is added
     during regrading of the site,  this soil cover may have the
     beneficial effect of  a cap.

Comment 17:  The actual need for  solidification of the
     incinerator ash is unknown at this time.  Without the
     benefit of bench and  pilot studies, the need for and type of
     ash stabilization which may  be necessary at the site, and
     the implementability,  effectiveness, and cost associated
     with this process alternative cannot be accurately
     determined.

Response:  Solidification/stabilization has been used for the
     control of inorganics at several hazardous waste sites, and
     substantial documentation of the effectiveness of the
     process exists for these waste types.  Of the available
     solidification processes currently being marketed, most can
     be classified as either portland cement-based or silicate-
     based.  If solidification/stabilization is necessary, field
     testing of the materials will be necessary to determine

                               31

-------
     which of the processes would be successfully used at the
     Springfield Township site.   The selected remedy includes the
     costs of solidification which nay not be necessary for the
     incinerator ash and therefore could be an overestimate.  The
     costs in the FS are estimates, and according to the RI/FS
     guidance "these 'study estimate' costs made during the FS
     are expected to provide an accuracy of +50 percent to -30
     percent and are prepared using data available from the RI."
     The U.S. EPA recognizes that the costs presented in the FS
     and Proposed Plan may be modified during the remedial design
     of the selected remedy.

Comment 18:  During the FS evaluation of the various soil
     alternatives, the units of cy and tons were used
     interchangeably which is not a correct assumption.  A
     conversion factor of 1.35 tons per cubic yard should have
     been used which would increase the weight of the soil and
     the length of time needed to complete incineration.  The
     underestimation of the incineration time is a significant
     concern to the STSSC since it improperly presents the
     actual implementation schedule.

Response:  The U.S. EPA acknowledges that the interchanging of cy
     and tons may be incorrect.   The soil weight depends on the
     types of soil and its physical state which will have to be
     determined for the soil at Springfield Township site.  A
     test burn will be conducted to determine the operating
     parameters and limits, expected emissions and residual ash
     characteristics of the incinerator/;  Results of the test
     burn will provide information upon *&hich a more accurate
     schedule for the selected remedy can be projected.  The U.S.
     EPA will continue to proceed in an expeditious manner.

Comment 19:  It is apparent that the soil volumes were calculated
     based on an incorrect analysis of Michigan Act 307
     Administrative Rules.  The FS contains numerous
     contradictions and deficiencies which make it impossible to
     determine whether the soil volumes will efficiently achieve
     the level of protectiveness.  The Review Report provides
     calculations based on the RI Data and the RI/FS guidance for
     identifying volumes and developing source control actions
     which efficiently and effectively eliminate or minimize the
     need for long term management.  The U.S. EPA should evaluate
     the analysis in the Review Report and provide a response to
     it or a revision of its own calculated values prior to any
     attempt to select an appropriate remedy.

Response:  It is unclear as to what exactly the commenter would
     like addressed.  Therefore, the U.S. EPA will respond as
     follows.  The U.S. EPA recognizes that the estimated soil
     volume of 11,820 cy may be modified during refinement of the
     remedial design.  The volume of soil as defined by the

                                32

-------
     surface area and depth has been identified for remediation
     purposes.  The soil volume differences requiring
     remediation, as noted by the commenter,  refers to the
     conversion of the cubic yards to tons which may impact the
     duration of the selected remedy.   The U.S. EPA selected a
     remedy which will be protective,  satisfy the remedial
     action objectives cited in Section 2 of the FS, and
     eliminate the need for long term management or monitoring.
     The cleanup levels applied by the STSSC in the Review Report
     does not eliminate long term management nor does is provide
     full protection to human health and the environment.

Comment 20:  It is requested that arsenic be eliminated as a
     target compound because the average concentration of arsenic
     in the ground water is more than 10-times less than the U.S.
     EPA's MCL drinking water guideline and concentration levels
     in the soils are within the range of Michigan ambient soil
     levels determined by MDNR's background soil study.

Response:  Arsenic will not be eliminated as a target compound
     because the Michigan ambient soil level study does not
     provide site specific information and is not an enforceable
     document.  The background level will be determined from
     background samples collected during the remedial design.
     Also,  the U.S. EPA does not agree with the commenter's
     calculation of average concentration of arsenic.  The basis
     of the arsenic contamination is the actual concentration
     levels detected in the ground water samples.  Due to the
     carcinogenic nature of arsenic, the U.S. EPA believes that
     it is in the best interest of protection of human health and
     the environment to retain arsenic as a target compound.
     Should information collected during the remedial design
     prove otherwise, then arsenic as a target compound shall be
     reconsidered.

Comment 21:  Dieldrin has been selected by the U.S. EPA as a
     chemical of concern.  Because of its low detection
     frequency, it is requested that dieldrin be deleted from the
     list of chemicals of concern.

Response:  This comment was previously addressed in the response
     to this section's comment 3.

Comment 22:  Because of the demonstrated background levels of
     barium in Michigan soil, and the occurrence of barium off-
     site in areas not affected by disposal at levels higher
     than the TCL (100 ppm), it is requested that the Agency
     provide data and justification for the 100 ppm cleanup level
     for barium in soil.

Response:  According to information provided in Appendix A of the
     Review Report, the background concentration level ranges

                               33

-------
     from 0-291 ppm and the median is 48 ppm.  The target cleanup
     level for in the FS is above the median background
     concentration level.  Hand auger sampling data in Appendix
     D-9 of the RI identifies barium levels as high as 4,900 ppm
     which was detected in HA 104; other examples include HA 105,
     630 ppm; HA 48, 4,540 ppm; and HA 47,  2,945 ppm.  The 100
     ppm cleanup level for barium is based on Michigan Act 307,
     R 299.5711, Rule 711.(2) which refers to R 299.5709 (2)(c)
     that assures that soils do not pose a threat of aquifer
     contamination.  The calculations are available in the
     Administrative Record and in Section A of the Responsiveness
     Summary.

Comment 23:  It is requested that toluene be removed as a target
     compound for cleanup in both ground water and soil because
     concentration levels for toluene detected in the ground
     water is less than the TCL of 40 ppb and there is no health
     risk identified for toluene in soil.

Response:  Toluene was detected in hand auger samples (e.g., HA
     48, l.OE+06 ppb), in deep soil borings (e.g., DB-05,
     12,650,000 ppb at 3-5'; DB-03, 621,300 ppb at 0-2' and
     346,000 ppb at 23-25'; and DB-103, 770,000 ppb at 30' and
     13,000 ppb at 75'), and in the test pits (e.g., Test Pit 1,
     170,000 ppb; Test Pit 2, 1,300 ppb; and Test Pit 3,
     18,000,000 ppb).  The concentration levels of toluene in the
     soil sampling pose a significant threat as a source of
     degradation to the aquifer.  The presence of toluene in the
     soils and thereby, its potential to contaminate the aquifer
     and its toxicity to the central nervous system and liver
     warrant its inclusion on the target compound list.

Comment 24 and 25:  The FS is deficient in that it does not
     contain a comprehensive discussion of the impact of the
     ARARs on each alternative's ability to effectively meet
     ARARs and such an analysis should be provided prior to
     selection of a remedial alternative.

Response:  U.S. EPA disagrees with the commenter that the FS is
   •  deficient.  The FS and its ARAR discussion is consistent
     with the revised NCP.

     The revised NCP indicates that the level of analysis for a
     particular site should be commensurate with the complexity
     of the site problems being addressed (40 CFR 300.425(b) and
     (e)(9)(iii)).  The detailed analysis in the FS is to focus
     only on viable alternatives (40 CFR 300.425(e)(9)(iii)(B)).
     All alternatives must attain ARARs (42 U.S.C. 9621).  If an
     alternative does not attain ARARs then the alternative
     cannot be selected and is not considered a viable
     alternative worthy of further consideration.


                                34

-------
     A number of potential  alternatives did not pass the initial
     screening stage due  to factors  other than ARARs.
     Consequently,  the alternatives  that did not pass the initial
     screening did  not require  any further analysis since they
     were determined to be  inviable  for this site.

     Those alternatives that passed  the initial screening were
     evaluated in the FS  against  all nine evaluation criteria,
     including ARARs.  In the detailed  analysis section of the FS
     there is a narrative summary of each alternative's ability
     to meet the pertinent  major  ARARs.   Additionally, Tables 2-2
     and 2-3 of the FS present  the operable Federal and State
     ARARs for the  site along with a brief summary  of what is
     required.  Tables 2-la and 2-lb of the FS presents the
     cleanup levels and an  indication of the ARARs  which were
     used to establish these cleanup levels.  Finally, the
     Administrative Record  file that was available  for public
     review contains further analysis by MDNR of the State ARARs
     and its interpretation of  the application of Act 307 to this
     site (see the  June 26  and  29, 1990 letters from MDNR).

Comment 26:  Cleanup levels were  claimed by the U.S. EPA to be
     based on ARARs,  primarily  Michigan's Act 307 Rules.  The
     reason for and the way the 307  Rules were applied are
     undocumented by the  U.S. EPA.   In  addition, other
     inconsistencies are  noted:   Michigan Act 307 Rule Type C is
     applicable for cleanup,  U.E. EPA's interim guidance on
     cleanup levels for lead were not used,  and arsenic is being
     targeted for cleanup above the  U.SV EPA's MCLs.  The NCP
     requires that  the U.S.  EPA use  MCL3b at Superfund sites.

Response:  Section  121 of CERCLA  requires selected  remedies to
     comply with all promulgated  applicable or relevant and
     appropriate standards,  requirements,  criteria  or
     limitations.  CERCLA Section 121.(d)(2)(A)(ii) states:

          "any promulgated  standard,  requirement, criteria, or
          limitation under  a State environmental or facility
          siting law that is more stringent than any Federal
          standard, requirement,  criteria,  or limitation,
          including each  such State  standard, requirement,
          criteria, or limitation contained in a program approved
          authorized or delegated by the Administrator under a
          statute cited in  sub  paragraph (A) , and that has been
          identified to the President by the State  in a timely
          •anner, is legally applicable to the hazardous
          substance or pollutant  or  contaminant concerned or is
          relevant  and appropriate under the circumstances of
          the release or  threatened  release of such hazardous
          substance or pollutant  or  contaminant, the remedial
          action selected under section 104 or secured under
          section 106 shall require,  at the completion of the

                               35

-------
          remedial action,  a level or standard of control for
          such hazardous substance or pollutant or contaminant
          which at least attains such legally applicable or
          relevant and appropriate standard,  requirement,
          criteria, or limitation."

     The law continues  that "(s)uch remedial action shall
     require a level or standard of control which at least
     attains Maximum Contaminant Level Goals (MCLGs)..."

     The U.S. EPA identified Michigan Act 307 Rules as an ARAR
     for this site and selected the Type A/B cleanup.  The
     cleanup standards identified in R 299.5707, R. 299.5709, and
     R. 299.5711  are more stringent than the Federal
     requirements and therefore, supersede the applicability of
     the MCLs as cleanup levels.

     Guidance documents are not considered ARARs (55 FR 8745).
     If an ARAR establishes a cleanup level the remedial action
     must conform to that cleanup level and not to any level
     suggested in a guidance document.  Since U.S. EPA has
     selected a Type A/B cleanup for this site the cleanup levels
     required in Act 307 for a Type A/B clean-up are ARARs and,
     consequently, must be attained at the site.


Evaluation of ARARs

Comment 1:  U.S. EPA has not explained why a Type C cleanup is
     not acceptable and should accept tMfe commenter's proposal of
     a remedial action alternative which it alleges will meet Act
     307 Type B/C cleanup levels.

Response:  For the following reasons, U.S. EPA determined that a
     Type A/B cleanup, not a Type C cleanup,  is appropriate for
     the site and is the best at balancing the nine evaluation
     criteria contained in CERCLA and the NCP:

          the small size of the site and the isolated nature of
          the three distinct areas of high PCB contamination;

          the small volume difference between the amount of soils
          that would need to be treated to a PCB concentration of
          1 ppm versus the 10 ppm proposed by the commenter;

          the toxicity of PCBs at very low concentrations;

          the residential and agricultural nature of the area
          around the site and its future growth potential;

          the potential present and future use of the property
          for recreational and residential purposes;

                                36

-------
     the ability to achieve a 1 ppm cleanup level for PCBs
     in a cost-effective manner;

     the increased permanence,  reliability, and long-tern
     certainty of protection of human health and the
     environment with a 1 ppm PCB cleanup level;

     the increased reduction in the volume of hazardous
     substances remaining on site;

     the State and community's strong preference for a Type
     A/B cleanup;

     the fact that a Type A/B cleanup for this site
     complies with CERCLA's mandate in Section 121 to use
     permanent solutions to the maximum extent practicable;

     the fact that a Type A/B cleanup for this site is
     consistent with EPA's CERCLA program goal to choose
     remedies which maintain protection over time and is
     consistent with U.S. EPA's August 1990 Guidance on
     Remedial Actions for Superfund Sites with PCB
     Contamination; and

     the fact that there will be no need for long-term
     monitoring and future remedial action if the Type A/B
     cleanup levels are attained.

Since U.S. EPA's analysis indicates a Type A/B cleanup
level is the best at balancing the vCERCLA and NCP nine
evaluation criteria and complies with all ARARs, including
Michigan Act 307 Rules,  U.S. EPA will not present a
detailed critique of whether the commenter's proposed
remedial action and cleanup levels meet the Type C cleanup
requirements of Michigan Act 307 Rules.  U.S. EPA does note,
however, that the commenter's proposed remedial action plan
does not appear to satisfy the Type C cleanup levels since
it fails to establish cleanup levels for all of the
pertinent indicator chemicals.   Dieldrin, arsenic and
toluene in the soils and arsenic, lead and toluene in the
ground water are chemicals of concern found at the site and
are considered either carcinogenic or highly toxic.   As
such, they should be considered indicator chemicals with
cleanup levels.  Additionally,  since the commenter's
proposal calls for containment of PCBs (at one location the
residual concentration would be potentially as high  as 44
ppm), U.S. EPA interprets Michigan Act 307 Rules to require
of a Type C remedial action plan, where containment is a
component, long-term monitoring, deed restrictions,
financial responsibility and a schedule for implementation
of the remedial action.  The plan submitted by the commenter
did not contain any of these items.  Finally, the commenter

                           37

-------
     nay not be able to provide the deed restrictions required of
     a Type C cleanup since the commenter does not own the
     property where the site is located.

    ent 2:  The alternative proposed by the commenter is
     consistent with Act 307,  and pursuant to Rule 705(4)  of the
     Act 307 Rules its proposal must be granted.

Response:  U.S. EPA does not agree that it must adopt a proposed
     remedial alternative and alternate cleanup goals submitted
     by commenters.  Neither the revised NCP nor CERCLA require
     such action either in response to comments on a U.S.  EPA's
     Proposed Plan or at any other stage in the cleanup process.
     Additionally, the position articulated by the commenter
     would negate CERCLA's clear delegation of decision-making
     authority to the U.S. EPA and would lead to practical
     implementation problems.   The assertion that this portion of
     the rule is an ARAR applicable to U.S. EPA is incorrect
     since it explicitly states that it is to apply to MDNR or
     the Director of MDNR.

     Selection of the remedial action plan is to be made by U.S.
     EPA (42 U.S.C. 9621).  Under the commenter's interpretation
     of Michigan Act 307 Rules, the remedy selection decision is
     taken out of the hands of the U.S. EPA and placed into the
     hands of any person who submits a plan to the Agency.
     Additionally, since Michigan Act 307 Rules allow for any
     combination of a Type A,  B or C cleanup and do not limit
     the number of remedial action plans, it is possible,  under
     the commenter's interpretation of pale 705(4), to have
     multiple remedial action plans with varying or inconsistent
     cleanup levels or remedial technologies.

     Finally, U.S. EPA would note that the remedial action plan
     submitted by the commenter does not meet the threshold
     requirements for a cleanup in that it: 1. fails to provide
     adequate long-term protection of human health and the
     environment when balancing the long-term uncertainties
     associated with containment of PCBs versus the relative
     small volume of additional soils needed to be treated to
     eliminate those uncertainties; 2. fails to establish cleanup
     levels for all of the contaminants of concern found in the
     ground water and soils; 3. fails to provide for long-term
     monitoring, deed restrictions and financial responsibility;
     and 4. fails to submit a schedule for implementation of the
     actions proposed in their remedial alternative.

Comment 3:  U.S. EPA failed to document the reason for its
     choosing an Act 307 Type A/B cleanup.  U.S.  EPA's evaluation
     of whether Act 307 is an ARAR must be provided to the
     public for review and comment prior to signature of the
     Record of Decision since it appears to be a fundamental ARAR

                                38

-------
     for the site and U.S.  EPA indicated in the FS that it did
     not agree with or accept it as an ARAR.  Failure to provide
     its analysis prior to  the signing of the Record of Decision
     is contrary to the public participation requirements of
     Section 117 of CERCLA  and 40 CFR 300.430(f)(3)(C).

     Also, The comnenter requested another meeting to discuss the
     Act 307 rules and their application to the site.

Response:  U.S. EPA agrees  that its reason for choosing the
     Michigan Act 307 Rules Type A/B cleanup levels was not
     available in the FS and Proposed Plan.  U.S.  EPA indicated
     in Table 2-3 of the FS that it was evaluating whether
     Michigan Act 307 Rules was an ARAR.  In addition, Tables
     2-la and 2-lb of the FS and the June 29, 1990 letter from
     MDNR, which are in the Administrative Record, explain how
     Michigan Act 307 Rules were used to develop the cleanup
     levels contained in the FS and the Proposed Plan.  U.S.
     EPA's rationale for choosing the Michigan Act 307 Rules Type
     A/B levels for this site are presented in the Record of
     Decision and in other  sections of this Responsiveness
     Summary and the Administrative Record.

     U.S. EPA agrees that at the time it signs the Record of
     Decision all ARARs must be identified.  U.S.  EPA does not
     agree, however, that further public review or comment is
     required or necessary*  An additional public comment period
     is required only if new information is made available and
     the proposed plan is revised after the initial comment
     period in such a manner that there ds a significant change
     to the basic features  of the remedy with respect to scope,
     performance or cost and the change could not have been
     reasonably anticipated by the public based on the
     information available  in the Proposed Plan or the
     Administrative Record  (40 CFR 300.430(f) (3c)).  None of
     these conditions is satisfied for this site.

     As discussed in the ROD there have been no significant
     changes in the Proposed Plan for the site.  The only change
     that has occurred is that U.S. EPA has indicated its
     concurrence with MDNR  that portions of Michigan Act 307
     Rules should be an ARAR and that the Type A/B cleanup
     levels are the appropriate cleanup levels for the site.

     The cleanup level information was presented to the public
     for their review and comment at the time U.S.EPA published
     notice of the availability of the Proposed Plan and the FS.
     Both documents identified Michigan Act 307 Rules as a
     potential ARAR.  Table 2-3 of the FS and MDNR's June 29,
     1990 letter explained  how the Michigan Act 307 Rules were
     applied to develop the cleanup levels.  Consequently, at
     the time the public notice was published the public knew and

                               39

-------
     had an opportunity to comment on the proposed remedial
     action; the proposed cleanup goals;  the application of
     Michigan Act 307 Rules to this site; and MDNR's evaluation.
     The comment period on the Proposed Plan and the FS provide
     the public with reasonable opportunity to comment on the
     preferred alternative and meet the criteria in the NCP (40
     CFR 300.430(f)(2).

     U.S. EPA disagrees that another meeting was necessary to
     meet with this  commenter.  During the entire public comment
     period, the public had available to it for review and
     comment the June 26 and 29, 1990 letters regarding the
     application of  ARARs at this site and all other final
     documents relied upon by the U.S. EPA to develop the
     Proposed Plan.   Neither the NCP nor CERCLA require U.S.  EPA
     to conduct private meetings with commenters.  U.S. EPA
     provided this commenter with the opportunity to present its
     comments at the public meeting that it conducted on July 24,
     1990.  Representatives of this commenter did present
     comments at that meeting as well as during the public
     comment period.   Additionally, U.S.  EPA on July 20, 1990
     extended the public comment period an additional 30 days at
     the request of  this commenter.  The Administrative Record
     indicates that  the U.S. EPA and MDNR met with this commenter
     numerous times  from January to July to discuss the
     appropriate cleanup levels for this site and the potential
     application of  Michigan Act 307 Rules to this site.  Given
     this level of information and access to U.S. EPA and MDNR
     staff, U.S. EPA does not believe tftat a second meeting with
     this commenter  was necessary or required.  Finally, the
     public had notice and a reasonable opportunity to comment on
     the proposed cleanup levels since the FS and Proposed Plan
     clearly indicated what the proposed levels were and how they
     were calculated.

Comment 4:  The remedy proposed by the commenter should be
     adopted because it comports with statements made by MDNR at
     its presentation before the Joint Committee on
   .  Administrative  Rules (JCAR) regarding application of the Act
     307 rules.  In  particular, MDNR stated that "Type C clean-
     ups would be developed on the basis of a site-specific risk
     assessment taking into account expected real exposures,
     rather than the assumed exposure in Type B clean-ups".

Response:  The MDNR  in its March 22, 1990, statement to JCAR
     stated "that it expected most clean-ups would be Type B
     actions" and that the Type B clean-up criteria in the rules
     were chosen so  that "after the completion of a remedial
     action, the property could be used for any purpose without
     concern for potential hazardous substance exposure."  In its
     June 29, 1990,  correspondence MDNR indicated to U.S. EPA
     that applying Michigan Act 307 Rules to this site, it

                                40

-------
     preferred the Type A/B cleanup levels.   Furthermore, it
     believed that the Type B cleanup level  for PCBs would be
     "the most cost effective means to protect public health and
     the environment."

Comment 5 and 6:   The Draft September 1989 Guidance on Selecting
     Remedies for Superfund Sites with PCS Contamination and the
     PCB Spill Policy (40 CFR 761.120 - 129)  should be added to
     the ARAR chart as "to be considered" (TBCs)  since they are
     mentioned in the discussion of chemical-specific ARARs
     (section 2.2.2.1 of the FS).

Response:  The purpose of the ARAR chart was to present the
     ARARs, not the TBCs.  The use of TBCs is discretionary (55
     FR 8745-46).  TBCs may be used to establish cleanup levels
     where there are no ARAR established cleanup levels.
     However, when the ARARs establish cleanup levels, TBCs may
     not be used in competition with the identified ARARs (55 FR
     8745).  The Michigan Act 307 Rules establish the cleanup
     levels for a Type A/B cleanup for all contaminants of
     concern at the site, including PCBs. Consequently, it would
     have been incorrect to list these documents as TBCs.  These
     documents were included in the Administrative Record File
     since U.S. EPA reviewed them as part of its decision process
     on the selection of the appropriate cleanup action at the
     site.

Comment 7:  Michigan Act 60 regarding PCB compounds has been
     superceded by U.S. EPA's TSCA regulations and therefore
     should be removed from the list of -iistate ARARs.

Response:  Both Michigan Act 60 Rules (299.3301-3318), Michigan
     Act 60 and the federal TSCA regulations establish
     requirements for the disposal, packaging, labelling and
     transporting of PCB contaminated material.  As stated
     elsewhere in this Responsiveness Summary, more stringent
     State regulations are ARARs.  Michigan  Act 60 was identified
     as a potential ARAR in Table 2-2 and its potential impact
     was summarized there also.  Examples of two areas where the
     Michigan Act 60 Rules and the Act are different from and
     therefore potentially more stringent than the TSCA
     requirements are:

          a.  Michigan Rule 299.3314 requires more information on
          the warning label to be affixed to containers,
          transport vehicles or storage areas handling certain
          concentrations of PCB contaminated materials than
          required under 40 CFR 761.

          b.  MCL Section 13.28(8) prohibits the disposal of PCB
          contaminated materials if they have a concentration
          greater than 100 ppm PCBs.

                               41

-------
     The appropriate more stringent provisions of Michigan Act 60
     and its rules along with the federal TSCA requirements will
     be used during design and implementation of the selected
     remedy to regulate the storage, packaging, labelling and
     transport phases of the remedial action.

Comment 8:  There is no discussion or reference in the FS for
     the Hay 1986 study produced by the U.S. EPA's Office of
     Health Effects Assessment (OHEA) regarding PCB cleanup
     levels at Superfund sites.  The OHEA study presented the
     fundamental concepts regarding cleanup levels in soil and
     was used as a basic reference during the development of both
     the PCB spill policy and the draft cleanup guidance.  It is
     believed that the Agency should have included this pertinent
     reference in its FS evaluation.

Response:  The U.S. EPA notes that the commenter would have liked
     a reference to the OHEA study in the FS.  The U.S. EPA did
     reference The Draft Guidance on Selecting Remedies for
     Superfund Sites with PCB Contamination dated September 22,
     1989 in the FS and noted that the cleanup standards were
     based on ARARs and subsequently the selection of Type A/B
     cleanup level of Michigan Act 307 Rules.  The more
     stringent ARAR takes precedent over the Draft Guidance and
     OHEA study as they would be to be considered(TBCs).

Comment 9:  The STSSC submits that its proposed alternative
     remedy for PCB soil at the Site is not only fully protective
     of human health and the environment, but unlike the U.S.EPA
     preferred alternative, the Propose? STSSC alternative remedy
     complies with all federal and state ARARs including the
     TBCs.

Response:  This comment is addressed in the Section on Proposed
     Remedial Action Plan.

Comment 10:  Section 3.6.1 of the FS states that as a result of
     the one percent difference in soil volumes for a 1 ppm PCB
     cleanup versus a 10 ppm cleanup, the final cleanup goal
     will utilize a 1 ppm level of PCBs as the soil cleanup
     goal.  To the contrary, both Section 2.2 of the FS and Table
     2-la of the FS clearly state that the Michigan Act 307
     regulations were used as the basis of the 1 ppm cleanup
     level.  The commenter requests that the U.S. EPA explain
     these contradictory statements and detail the exact basis
     for the PCB cleanup goals for soil.

Response:  The U.S. EPA does not consider the statement that 'as
     a result of the one percent difference in soil volumes for a
     1 ppm PCB cleanup versus a 10 ppm cleanup, the final cleanup
     goal will utilize a 1 ppm level of PCBs' is contrary to
     Section 2.2 and Table 2-la of the FS which indicate that

                               42

-------
     Michigan Act 307 Rules are the basis for the cleanup levels.
     Section 3.6.1,  page 3-6,  states that "onsite soil shall be
     treated to a level where  detected concentrations of the
     target chemicals are below the preliminary cleanup goals
     and TBCs for soil, as established in Section 2 of this
     report.  ...Surficial soil exceeded the preliminary cleanup
     goals and TBCs  for all the target chemicals.  Deep soil
     exceeded the preliminary  cleanup goals for PCBs, toluene,
     chlorobenzene and lead.   Because the volume difference
     between 10 ppm  and 1 ppm  PCBs  is less than 1 percent, the
     soil alternatives utilize 1 ppm as the final cleanup goals."
     This paragraph  indicates  that  the 1 ppm PCB cleanup level
     was based on the ARAR and that the 1 percent soil volume
     difference was  used as a  primary balancing criteria for
     evaluation of the alternatives.


Compliance with the  NCP

Comment 1:  Section  117 Public Participation of SARA requires an
     opportunity for submittal of comments on the proposed plan
     and requires the President (U.S. EPA) to provide a response
     to each of the  significant comments, criticisms, and new
     data submitted  in written or oral presentations.  The
     failure on the  part of the U.S. EPA to provide a reasonable
     explanation of  how the Act 307 based cleanup type selections
     were made and how specified cleanup levels were prescribed
     prevents the public participation envisioned by Congress and
     debated heavily during reauthorization of CERCLA.
                                       &
Response:  Response  to Comment 6 of the Feasibility Study section
     addresses this  comment.

Comment 2:  The STSSC requests clarification of the specific
     status of Act 307 as an ARAR and the opportunity to comment
     on the application of this ARAR prior to remedy selection.

Response:  Response  to Comment 3 of the Evaluation of ARARS
     section addresses this comment.

Comment 3:  The draft FS prepared by the MDNR contractor and
     U.S.EPA'B comments on it  should be part of the
     Administrative  Record according to 40 CFR 300.810(a) and the
     commenter was denied effective public participation because
     it was denied these documents  and provided with notes on
     cleanup levels  late in the public review process.

Response:  Neither draft nor predecisional deliberative documents
     are included in the administrative record regardless of
     whether they are prepared by U.S. EPA, the State or their
     contractors. (55 FR 8801, 40 CFR 300.810(b)).  The only
     exception to this general rule is where the draft document

                                43

-------
     was relied on and there is no final document generated and
     made part of the record at the tine the response action is
     selected.  This exception is inapplicable to the present
     case since the final*RI and FS were the documents relied
     upon by the Agency in selecting its remedy for this site
     and they were available in the Administrative Record File at
     the time the public was notified of the U.S. EPA's Proposed
     Plan for the site.  Additionally, the June 29, 1990 letter
     from MDNR and Michigan Act 307 Rules explain how the cleanup
     levels were derived (see also responses to comment in
     Section A and Evaluation of ARARs).  The cleanup
     calculations were provided to the commenter as an aid in
     their evaluation.  In no event were the calculations
     required to be in the Administrative Record, since the June
     29, 1990 letter and Michigan Act 307 Rules indicate how the
     cleanup levels were established.

Comment 4:  The commenter quotes section 300.430 of the NCP that
     states "lead agency shall include a screening step, when
     needed, to select a reasonable number of alternatives of
     detailed analysis."  Since the technology screening is
     merely an intermediate step in the selection process, the
     U.S. EPA should have included thorough documentation of the
     screening methodology which was utilized in the FS.

Response:  The U.S. EPA did not deem the screening step which
     eliminated alternatives as necessary and therefore, it was
     not included in the FS.  Tables 2-5 and 2-6 of the FS
     identify the technologies considered and screened for use at
     Springfield Township site.  Responses to comments 5, 24, and
     25 of this Feasibility Study Section provide further
     elaboration to this comment.

Comment 5:  Aside from a single statement alluding to the Act 307
     Rules, no discussion of the ARARs or their significance as
     they pertain to the development of the remedial action
     objectives has been presented in the FS or included in the
     Record File.  The U.S. EPA failed to provide both an
     explanation for the omission and a proper and complete
     discussion of the role of the identified ARARs for the Site
     prior to its closure of the public comment period and the
     initiation of the final remedy selection process.

Response:  Responses to Comments 24 and 25 in the Feasibility
     Study section and Comment 3 in the Evaluation of ARARs
     section addresses this comment.

Comment 6:  The detailed analysis of alternatives section of the
     FS (Section 4) does not use the nine criteria to evaluate
     the alternatives.  This approach to the detailed evaluation
     of alternatives is inconsistent with the intent of both the
     statutes and the NCP.  The analysis of the nine criteria

                                44

-------
     provided in Section 5 of the FS report does not provide
     sufficient detail to allow for informed public comment on
     alternatives screening.

Response:  The U.S. EPA acknowledges that the detailed analysis
     of the FS (Section 4) used criteria stated as engineering
     considerations, public health evaluation, environmental
     evaluation, ARARs evaluation, and cost and not the nine
     criteria evaluation cited in 300.430(e)  of the NCP.  As
     noted by the commenter,  the detailed evaluation in the FS
     provides the information required of the nine criteria but
     under different headings.  Section 5.1 of the FS and the
     Proposed Plan provide a  comparison of the alternatives based
     on the nine criteria. U.S. EPA disagrees with the commenter
     that there is insufficient detail in the documents for an
     informed public comment.

Comment 7:  The current RI/FS Guidance states that when
     calculating the present  net worth of an alternative, a
     discount rate of five percent before taxes and after
     inflation should be applied.  The FS, however, uses a ten
     percent factor.  This is significant in light of concern
     related to the quality of the RI and the accuracy of
     projections relating to  volumes of contaminants and
     treatment levels which could influence the length of the
     proposed response actions and the costs.

Response:  The U.S. EPA disagrees with the commenter's
     conclusions concerning the guality^pf the RI, the volumes of
     contaminants and the treatment levels in previous responses
     in this Responsiveness Summary.  The U.S. EPA acknowledges
     that the discount rate of 10 percent was used to calculate
     present worth of O&M costs for all alternatives.  Since 10
     percent was applied consistently to all alternatives, the
     alternatives' O&M costs  in the FS does represent the
     relative difference in costs between the alternatives.

Comment 8:  In general, numerous critical pieces of background
     information are unavailable in either the FS, PRAP or
     Administrative Record making informed public participation
     impossible.  By failing  to provide this information, the
     Agency has deprived the  public an opportunity to review and
     comment prior to remedy  selection.

Response:  This comment is a  compilation of many previously
     stated comments which have already been addressed in the
     Responsiveness Summary.
                               45

-------
Proposed Remedial Action Plan

Quoted from Section 5.1 of the Review Report,  "the STSSC
alternative consists of the following items:

     *    Fully health protective cleanup of soil meeting both
          State and Federal ARARs.

     *    Thermal treatment of excavated soil either on-site or
          off-site.

     *    Solidification, as necessary,  of any ash prior to the
          redeposition of on-site.

     *    SVE of organic constituents from the soil at specific
          locations and depths.

     *    As necessary, extraction,  treatment by air stripping,
          and reinjection of groundwater which contains TCE at
          levels in excess of 3 ppb.

               "An Act 307Type B/C cleanup of soil is proposed.
          This soil remediation will provide full protection of
          human health and the environment but will eliminate the
          unnecessary removal of a large quantity of soil to
          eliminate a small amount of residuals that are deep
          below the site surface.  Any residuals following
          treatment under this alternative are neither a direct
          contact threat nor a groundwater source threat.  Any
          PCB-containing soil that is l&ated within the areas
          outlined in Figure 5 (of the Review Report) will be
          excavated and treated via thermal destruction.  The
          proposed STSSC alternative soil remedy is fully
          protective of public health and the environment,
          results in the removal and destruction of over 98% of
          the total mass of PCBs currently on the site, and
          effectively destroys all other organic constituents
          within that soil volume."

     The STSSC Proposed Remedial Action Plan is very similar to
     the U.S. EPA's selected remedy.  Both remedies proposed
     excavation and incineration of PCB contaminated soils;
     solidification of ash, if necessary; redeposition of soil
     and ash on-site; soil vapor extraction; and a ground water
     treatment system.  The remedies differ in that the U.S.
     EPA's remedy requires more soil to be remediated by
     incineration, solidification of soils containing metals
     above background levels, a larger scale soil vapor
     extraction system, and carbon adsorption treatment for the
     ground water rather than air stripping.
                               46

-------
The modifications of the STSSC Proposed Remedial Action Plan
are based on premises which are not acceptable to the U.S.
EPA.  The STSSC recognizes the Michigan Act 307 Rules as an
ARAR and selected the Type B/C cleanup level standards.  As
a result, the STSSC proposed a new target cleanup compound
list and cleanup level goals.  This list eliminated the
following from the chemicals of concern for soils:  toluene,
arsenic, and dieldrin; and the following chemicals of
concern for ground water:  toluene, arsenic, and lead,  in
the preceding sections of the Responsiveness Summary, the
U.S. EPA has provided explanation for the rejection of these
changes by the STSSC.  As a result, though the STSSC
Proposed Remedial Action Plan presents reasonable
technologies for the remediation of Springfield Township
site, it does not offer complete remediation, leaving
contamination on-site which is not acceptable to the U.S.
EPA.

The STSSC provides a rationale for the selection of the Type
B/C cleanup levels, but as explained previously, the U.S.
EPA, in its discretionary position, selected the Type A/B
cleanup levels over the Type B/C.  The selection was based
on a review of the best balancing of the nine evaluation
criteria and which included reasons such as the ability to
achieve a 1 ppm cleanup level for PCBs in a cost-effective
manner; the toxicity of PCBs at very low concentrations; the
residential and agricultural nature of the area around the
site and its future growth potential; the increased
reduction in the volume of hazardous substances remaining
on-site; and the State and community's strong preference for
a Type A/B cleanup.

The U.S. EPA rejects the STSSC Proposed Remedial Action Plan
for it does not fully satisfy the threshold criteria, that
of overall protection of human health and the environment
and compliance with ARARs.  The selection of the Type A/B
cleanup level sets the concentration level of PCBs at 1 ppm
because of the direct contact threat from the point of
exposure with the contaminated soils.  STSSC Proposed
Remedial Action Plan indicates that low level PCBs can be
left in the soils below the point of excavation based on
their risk assessment.  However, the definition of point of
exposure in relation to direct contact as cited in Michigan
Act 307, R. 299.5711 (7), is "(f)or the purposes of this
rule, the point of exposure shall be assumed to be any
location at the site or any location which hazardous
substances in or emanating from, soil are transported by
runoff, air dispersion, or other natural forces.1*   Based on
the State's interpretation of the point of exposure, PCBs
must be remediated to 1 ppm levels to be fully protective of
human health and the environment.  Since the STSSC Proposed
Remedial Action Plan is based on STSSC's selection of Type

                           47

-------
B/C cleanup goals and not the recognized Type A/B cleanup
goals, the Proposed Remedial Action Plan does comply with
the subsets of the designated ARARS for the site.

A review of primary balancing and modifying criteria, the
U.S. EPA's selected remedy more completely satisfies the
criteria than the STSSC Proposed Remedial Action Plan.  The
selected remedy provides long-term effectiveness and
permanence by removing and eliminating all contaminants
from the site, reducing the toxicity, mobility, or volume of
more contaminants through treatment; and by being cost-
effective in terms of the difference between a Type A/B
cleanup levels which require no management controls or deed
restrictions.  It should be noted that the costs provided by
the STSSC for their Plan do not include the long-term
management, 30 year ground water monitoring program, and
institutional control costs which would be incurred on a
Type B/C cleanup level.
                           48

-------
Pag? I*?.
                                         ATTACHMENT    3

                                                  lve  M.l.OHl
                                                  n-m
                                            Oui.LOfi|) i.'
                                                                                 SHE
Sj !><;.• (•Mil*  M«*.S
                                                                                                  PtUPIENT
                                                                                                      DUCUMtNj TfU-E
                                         ?'ii  I1*?*
                                                              I-:-MC 'j
                                                                              tontril
                               Form  Jpttpr  to re?i-
                               oents  el-:-*?  to tne
                               sit?,  providing '.>po»te
                               (ust  of
                                                                                 Vjno'.'S i95id?nt5    C'orresoonderee
• i     M/OC-/CK
                 6//iJi/lft
  1     eV/03/c*
         *  I
till 1/06
8i/0c'/i.»i
                         resoons?
                          concerri?
                              to
Letter frc-n
ill resident, inflicting
concern reiSpringtield
Fwp. Site

i;eply to resident's
concern aoout exoos'.tre
of children to contami-
nants at site

Letter to tlirlrston.nl
resident, responding
to (f:/£i/6?  letter
regarding Springfield
inp. Site

Letter to flatrorc, f<|
resident, stating that
there has been no
contMination of resi-
dential Nells associated
with Springfield buip
Site to date
                                            Peport
                              II to tne puohc

                              WNK froqress fteport
                              l.i to the public
                                    rogress *»B?vt
                                 to the public
                                                             I'.'.ffUS
                                                    •IW.'lf
                                                                                                  P.flcKay
                                                                                                  fc.
                                                                                                      Correspondence
                                                                                 t'.Stick, resident    Corresporiderice
                                                                                 P.Steele, resident   Correspondence
                                                                                 H. ft'.'bi nson,          Corresponderee
                                                                                 resident
                                                                                                     Fact Sheet
                                                                                                     Fact Sheet
                                                                                        Fact
  / 05/10     Hurt
                                            fieport
                                                                                                             Fact Slieet

-------
"309 N.%
                              TITLE

                              M to tne public
                                                       Hi.'fliN'i>!hH!iVt Xt
                                                                  FOWNSHIP OUK> SITE
                                                            OfiKLftMD COUNTY,  Ml
                                                                   RECIPIENT
                                                        OCultNr  FrV
                              "Wft Progress Report
                              t5 to tne
                                                                                      fact *ne
                                 «H Progress ft
                              »t> to tne ouo he
                                   Progress Report
                              17 to tne out) he
                                                                                      Fact ineet
                                                                                      fact Sneet
                 6b/0i/ii:7
                 66/
                 67/04/28
                 66/03/03
                              BDNR Progress Report
                              16 to tne public
     Progress Report
113 to tne puohc

WX«R Progress Report
lit to tne puoiic

BONR Progress Report
115 to tne puo lie

HDNft Progress Report
116 to the public
                               flDNR
RiMR
RONR
                                                       F«ct Sheet
                    Fact  Sheet
                                                        ract  Sheet
                                                        Fact  Sheet
                    Fact  Sheet
            1?    79/09/10

            i     (JO/06/04


            1     84/10/83



            i     64/li/e;7
                 67/le:/OJ
     to PEAS File
interoffice Cwunication
Preliminary Soils Data
      Olhla
     rc:Nov. 13, 1964
•ecting of the Citizens
Info. CoMittec

Ne«o retTrip Report
11/13/64, Springfield
IKP. Ou«p,«l public
•eeting  (list of fttten-
oees atttcned)

Springfield Tup
Superfund Site Public
fleeting Pgend*
HDNR
J. Lint on
J.Knoy
6-Vanderlaan
                    nemoranaun

                    Memoranduii
Citizens Info.       neticranouii
CoHittee
                                                                                                                    Other
           /     00/W/OO     Ramjficturers Inforwtion      Shirco Infrared Systi
                                                                                      Repc'rts/Stui

-------
•»/00/00
79HJO/00
14

175
ill   fli/Ot/lS
             on Inernal Obstruct ion
                   Prehniriary
                   Reoort
                        Investigation keport
             Phase I  Hyorogeologic
             Investigation Data

             Rose  ano Springfielo Tup.
             bunury  Report
62/07/19     Maiaroous  Ranking Scoring
             Package
             Site  Inspection Report
83/01/28     6roundnater Contamination
             Study  (Phase  II Hyoro-
             geologic Stuoy)
Remedial Action taster
Plan

flood Plain Study
                                      ni:n|Nibi3mlvt "fcCGRb iNDt.x
                                     s^i!«jFItLO JuWKSHiP DUMP 51 IE
                                           (»*.LHN|) IJXlMTt',  "II

                                            HUfMJR
                                                     flurpny
                                                 UStPA

                                                 RDfcR
                                                Mill
                                           tept. of rtmy
                                                                                      RECIPIENT
                                                                                        °eports/5t'

                                                                                        fieports/Sv.


                                                                                        Repcrts/St'.


                                                                                        Report s/St>.


                                                                                        Reports/St'
                                                                                                         Report s/bt '.
                                                                                                         Report s/Sti
4d    84/07/18

114   64/10/12

105   84/12/00



74    65/08/00


7     65/03/04


43    65/04/03


i\    85/07/Ob

7     85/07/24
CoMunity Relations Plan

taster Site Safety Plan

Work Plan for ftewdial
Investigation/Feasibi-
lity Study

Quality Assurance Project
Plan

Modification of  taster
Site Safety Plan

Work Plan Addendas
1 and 11

     Plan
                                           E.G. Jordan

                                           HtlNR

                                           E.G. Jordan



                                           C.C. Joroan


                                           MDNR
                                                and t'.C. Jordan
            ^remvestigative
            Evaluation
                                                 t. C.Jordan

                                                 E.G.  Jordan
                                                                                                         Reports/St

                                                                                                         Reoorts/St'

                                                                                                         Reports/St



                                                                                                         Reports/St'


                                                                                                         Report s/St i.


                                                                                                         Reoorts/St'

-------
 nbtS WiTE
i'fc    6b/*/CO

10    db/l<)/i£'4


H    Sb/ll/c6
5     67/01/H

      85/09/19
 TIFLE
                   Site 5af'ety vl»n
    : Extent of Migration
by Chlorinated filipnatic
nyorocarDons/Trictiloro'-
etnylene

UorK Plan Augwntationlll

Qfl/OC'd raw data and
Chain of Custody Forms
                                                           RECORD INDEX
                                                       TOWNSHIP OUMP SHE
                                                 OHKLMND COUNTY, Ml
                               f. C. Joroan
work Plan flugaentatienll       E.C. Jordan
Oioxin and Furin S
Plan
E.C. Jordan




E.C. Jordan

E.C.Jordan I KDNR
                                     RECIPIENT
                                                        jpr.r.vt e/ 'jt
                                                        keoorts/St
•»epcrts/St
Reports/5'

Sanphng/l

-------
Pane No.
07/c7/6fi
TITLE
                                           6U1MNCE MCLTiNT  IMEX
                                        SPRINGFIELD fOUNJHlP  OuT-P  SITE:
                                     DGCUnENiS  NUT CO^lED-fAC K  REVIEWED
                                        flT USEPft  RESIGN V,CHICflGO,  IL
flUTHOR
DflTE
N.U.S.  Corporation's
Revised Guidelines for
Data Evaluation Criteria
for Reviewing SflS Chlori-
natw Dioxin/UiDenzofuran
Data
         on fteneoial
Invent oat ions L>naer
       "
                               65/06/00
         on FessiDihty
Stnoies Uncer
                               85/06/00
       so Paolic  Healtn
Evaluation flanusl
UtEPA
86/10/00
Intern Soioanc? on
Sucsrr'und Seise: ion of
USE: A
TStfl PCt Clean-uo
Policy
       Off-Site Policy
Final Buioarce for the
CK'peration of ftlSDR
Hesltn »hE?srn9n:
Activities Nith the
Surer fund ftesedial
Process
OWSES Dir. 9585. *-02
87/04/22
Intena 6uioance  on
fcnnistrative Secoros
for tensions on  Selection
of CEfidA Keso-iTise Actions

F> '66 fegion V NOD
Process Guioance.  Memo
froi Chief of the Euer-
eency I teoeoul  Re;o-:
-------
Psae NO.
                                             6U11MICE OOCUT-tNT  INDEX
                                         SFUHiL'HtLO TOWNSHIP C-UMP  SITE:
                                       DOMINI 5 WIT (.Ct-IEH-wOV K  PfvltWf.D
                                          flT USE>'rt REGION V.CHICAGO,  II

TITt.1-:                                flUTH'Jrt                         DflTE
ftecorfl of Decision                                                  88/0*/Ol
Question; t ftnsvors-DIWFT

-------
nit to.    i
C7M/JS
ncu/tua nus tin    finr
                                       iwriijsrwiri mow • HMH 11
                                        sniiermn ronssir urn sin
                                             omuo cowrr, KI
UTSOl
ucninr
noctm
Docmm
              |J/«5/cr letter
                     leetJBj ritt SSEPl
                     ut MIR to illor
                     fifi tie oppor-
                     tisitf to present
                     reietfiitjoo pictige
                     tferejopetf /or toe
                     Jite
MeriiaiioMttr.   f.L.I«Jicti,tfSm    Correipoodeoce

-------
                    ACRONYM  LIST





MDNR    Michigan Department Of Natural Resources



PRP     Potentially Resposible Party



USEPA   United States Environmental Protection Agency

-------
    lo.    1
u/09/89
msiinm mis om     nm
      KtcoKD  • mm n
     rommf WHP sin
ouun mm, HI

             ncitiw
                                     DOCHUKltt
          31    H/07/21  fraotiittiJ jttter     t.Ltnioisai,
                        mi tiepotti Stitditl Ittj.
                        tctioo flte
                        tf Btit
                        for
M.IeJioo.BSIM    Correspondence       j
          23t  H/6T/OC Intiitl Itnstigitiet tSttA
                       (FoJoit 1 of 3)

          32!  19/04/00 Sttttitl JBffStiyatico PSfFA
                       (FcJoie 2 of Ji
                       ippeotfiees A • C|
          2(9  19/04/00 tnttitl Isrtstigttici
                       (Mate 3 et 3:
                       Appendices 0 • I)
                  Rtpont/Stvtits      2


                  leporti/Stodies      3



                  KepoTti/Sttiiits      ^

-------
    10.     J
 /1U99
icn/riiu PWIS run
rmi
     •ICOH mn - wan 13
      WIISMP mi sin
uusmt, IKIKAI

                   iicipinr
                                                    rw
          2    D/I7/H
          J     19/11/22
letter  re? lefoestia?
i leetiaf rite U.S.IM
lid IMF CO llf 22,1199

letter  ret Proeresi
report  ei i propouJ
tkit vjj] be lobiitted
to i.S.m lit IP««
tfirii;  tfte Jitter pirt
et tie  teet of JoJr J',
letter  re> Ceoeero
tifTttttt it tie Sept.
(,  198* leetu; ret
tie pretence of irseiie
lerf ftstieitn it tbe
Sprie;fjeJtf f»p. Site
                                                   r.leniiiior-riidereer
                                                   (irzii
r-leriiiiiox-riifereer
Stint
                        T.l.leJioB-f.S.IFI   CorreipoDdeoet
                                      Comipoodeoee
Meruolior-riotfereer
Cirzii
                   I.CJirJric-ff.S.IPA   Correipoodeoee
          1CJ   JO/02/M
          2     !0/»/2f
          (     ff/05/14
          2     9I/IS/25
          I     f0/H/0«
letter  fcrnrdio? toe
lotice  letter! that
rere  tent to tKfs,
dited JIB. 23, 1*50,
titi  copies of tie
receipt; for tbt
letters itticbed

letter  re: SpriojfieJd
fomoip Site/FCB
CJeiiop lerejt

letter  ret Joyemico*
for PCI CJeiDop, »iti
rei50oi listed nd
bickfroued uteriij
•id diicnijoo of PCI
letter ret leipoase
to tie Kir It, 1910
Jitter rejirdicj toe
appropnite fCt JereJ
for PCI coBtiiiiited
lOJJl

letter ret lespoose
to tie Hlf 25, 1990
Jitter ititio; tilt
                                                   Vipfirer.lideJiac t leer
                        I.Iirtia-t.S.IPA     Correipoadesce      4
r.lenioiioi-Dictj'iioB,
fri^ot.Koofi.rifi losee,
i freeno
                                                   Irijot.etiJ.
                   I.CJiririe-P.S.IPA  Correipoadeace      5
                                            CorreipoBdeice
I.CJiirlzio-D.f.fPI
                                       Correspoadejce
                                                                           IB
MeriiBim*!>JctiiioB,
Iriett.looB, fit
i freeiio
                   I.CJiririo-I.S.IPA   Correipeadeace      8

-------
 «ff Io.     2
'1/11/90
•icumus tuts tin
wru

JpriiffieJd feraiDip
Steer Ja; Ceilittee
ill let lid tie
but tit tl ttrin ct
tie fS er prcpoied
tin for ti<
           fcniiip
                                                iMiiisriirm IICOID mil • nun
                                                   tniisniii roiisijf M» sin
                                                         MUSIIK, IJtlJCAI
                         ncinnr
                                                                                     mmit mi
                                                                                                                  tocmm
          7     J0/M/JJ
letter re.- Spriaffjeld
        5ite HAS!
                                                   «tiJ.
                                            Cvrreipoadeoet
          4     9C/H/2S
          I     $«/>{/?«
          I     Kftt/tt
          20    15/16/02
letter re> I Jilt  cf
peteatiiJ Stite IM*s
ideatified iptcitietllj
fcr tie SpriaifieJd frp.
Soperfoad iJte

letter re: CJirifieitica
of MM'i position re:
tee ipplicitiPB et tee
Art 307 loJei tc
reiediite
Spriaofield fowsaJp lite

AtteadiBce Saeet for
tbt Sept. I, 1*90
leetiBj for Spria;field
Site,  IJ

i?esdi for leetia; vita
tltf Steenay Ceiiittee
SpriBy/ieJd ferasaip
Coip,  rita MIC re:
•eetiaj iBtef for tie
Ju. 30. 1*)0 Metiagl
                                                l.lirtie-O.S.IPJI     Cerrespoodeice
                        DJeetor-fCM
                                            CBrrespoodeore
                        I.Iirtio-o.S.IPJI
                        file
                                                   I.KirtJO-ff.S.IM
                                                filt
                                                                                     leetia; lotes
                                            leetiic lotes
3    N/15/10    leio re i leetiar,
                                                   I.Kirtie-O.S.rN
                                                fjjf
                                            leetiae letei
fersiiip Site,  rito
iiit «f itteideei
attiebed

CIRCll Cetpliiare ritb
Oteer firiroDieatil
Sutotes (Coidiaee)
i.s.m
                                                lejicfliJ
                                                1-1
                                                                                     leierifidoi
15

-------
aye Io.     3
7/11/50
icii/nut ruts
rmi
                                                             mow urn  - mm 13
                                                   sum/in* tonsut wit sin
                                                                 ,  IKIISAI
                                                                  iicimir
                                            pocmir mi
          I    17/05/15
          1    11/05/24
          77   IJ/03/01
          1     J0/0I/20
          23    17/01/02
ITeio rei PrelJiiaarr     S.laff-ff.S. Dept. «f
litonJ Icioorce Sorr«f». Iittrier
       n
Reio rei Fiodiliii
Itcideat it lerjf
iitttllti itllt

Ino r«t iDterii
tsHiact OB Aduoj-
itritirt tttcetts for
SfJcrtjcB of emu
Aetpcost Jcticcs
                           eaJJ  rat ttitb
caJJj  eoBcerfiiB; tot
iCBfdoJt /or proprstd
pjao tad iptrjiJ
gotieia;

federal leyiiter/
W. 52, lo. «/
IpriJ  2, JM7/
JtoJei  ( lefolatiee;
'folfeoJorieated
liptetfJi SpiJJ
CJeatnp PoJicr*
linger


J.r.forter-P.S.m
                        I.ClaritJo-P.S.IU
                                          IPA
                                                                  LCoBitasteJei-0.S.I leiorafidoi
                                                                  n
                                                                  Spriagfield f»p tilt it tor to tut
                                                                          idilos.,    leioraadui
                                                                           M
                                                                  file
                                            leioraadui
                                            Ocaer
                                                              17
          241
ClSClt  Cttflitect till
Ctoer iars 8aBoaJ-fra/t
(Coidioee)
                                          C.5.IM/05HR Cir.
                                            Otber
                                                                                       21
          I     l!/»/(0
IriefiB? ffeio> Sprj'Bj-
fjejd foiBtajp flip
fpdate
Septeiftr f
rjnaaact i
foJlOf-Bp i lev IllBfJ
leiaiader of Reio ii
redacted
I.Iirti8-P.5.IfA
                                                FiJe
                                                                                     Otber
                                                              22
10   8I/0J/22    Drift (gidiaee OB
                                                   P.S.IM
                                                                    Otaer

-------
ate lo.
1/11/30
iat/mu run IIR
          J    M/IJ/14
          1     JI/I4/1J
          192   «/«/«
          IT    99/11/26
          144   N/17/00
          17    M/17/00
rmi

feJeetiBf Inttiti for
Siperfud Sitei titb
PCI Ceitjiiojtjca
WIOI
     ircoie inn - mm «
      ronsiip tw sin
Misms, IKIIMI
                   ircmiir
                                            cocmir rrn
C0irtriitieB rteert rn
Inter Pin /or Spriif-
titlt ttf. ffereJepieit

CeertriitieB leeord ret
lut tse for Stc.  32
it
roriJ,  cr
ttsittttitl
I.Iirtii-V.S.IPJ
l.lirtii-I.S.IPJ
                        C.CMft-OikiiBd Co.  PBOBI Iteordi
                        C.Cieit-OitJiBd  Co.  Pfloflt leeordi
ttrtltftttt of
ter«Ji  for PoJfcoJcr-
utrtf iJpifflfJs (tCtl
C It IBtp

listribstics of irstaic
lod ftsticitti
SpriB;fi(Jd frp.  Site
SpriBffidd ftp., II
P.5.IPA-raiBiBctoB B.C./  PaeJje
f.S.  Pept. ef CoBierce
laticciJ  fecbaieaj
IsforiitioD SerrJce

fred C. fart JiioeJacef,  SpriBjfieJd frp
IBC.                     Steer COB
     (eport OB tb<
           5todf of
tie SpriijfieJd
fetBjfiip Site
Oitlaid
                                                   CfiJcifO,!!
Propoied Piio for
fiBaj IfirdiaJ letice
SpriBffJtld fovaiBip
loip
liriitirf, licfliyaa
P.S.fPI/Ur*
                                                         25
                                            teportf/Stodjes
                                            leportt/Stodies     27
                                            leporti/Stodies     26
                                            Itporti/Stodies     2$

-------
•Pao* to.
J7/.N/JO
imt/mu nets cm
TIJLS
                                        wnismriri mow JWH - mm n
                                                    roimit am sm
                                                nmme,
mifinr
         I   90/01/20
Kt»0 Tt: JtOt Of
Jttaspcntblt
Joeioeracor at
     IJJOCDS
Sprisgtiti lip. Sitt
lilt

-------
fag;  Ho.     1
19/16/98
ricBE/mu PAGES DAT!
                                                   ADHIHSTRATW RECORD IRDEI - DFDATE IS
                                                       SPRIPGPIELD rOIRSRIP DDKP SITE
                                                            DAVISEORG, KICBIGM
TITLI
AUTHOR
RECIPIE1T
DOCUKERT TIP!
                                                                                                                         DOCNl'H!!-F.
           4     91/18/27
           I     H/I8/2S
           2     H/IS/2S
           M    91/18/31
           2     9f/«W
           II    88/12/19
Ittttr res  Request  for
Ull'i position  OD  tbe
reiaininq issues prior
to ISIPi laking  a final
deteriitation  OD tbt
llU't tbt  Statt
Ktitifitd

Ittier foriardiog a
ecpy of tbt  transcript
froi tbt Proposed Plan
Public Httting btld on,
Tatsdaf, Jo IT  24, 19?6
as ptr request

Lttttr rt:  DSEFA hs
eeipleted its  revi«w
of the Act  3C7 Rules
tbat (HUP. identified
is MA? for  the
Springfield  Tovnsbip
Site

leto {warding
Calcolitioa? for
Cleaoap Levels

Itio re: Springfield
loiufbip Site
la? 39, \m Cleanup
Ltrels Docoient

Italtb ls;essient for
Springfield  Tovnsbip
Dnp Sitt
Oakland Coontr.Nicbigan
J.Dikiois-OSEPA
R.MartiD-OSEPA
J.Oikinis-OSEPA
LBradford-KDRP.      Correspondence
K.LeniDiaui-Vrigbt, Correspondence
etal.
K.Bradford-NDRR      Corresponienc*
K.Kartin-USEFA & HDSR     Official File        Mcionnd'ji
K.Hartio-UFEPA
Official File        Neiorandut
ATSDR-U.S.  Pnblie
Health Sttrice
                     Reports/Studies     6
           (S    M/IB/B9
Transcript  of Public
Btetiag,  btld en
TlCldaT,  JQl? 24.  195?
at Springfield Toinsbip
Ball IB Divisburg.KI
I.Turner-leporttr
                     Transcript

-------
Date

5/1/89
9/10/90


9/13/90





9/14/90


9/6/90





8/30/90


9/27/90




9/28/90




8/14/90



9/13/90




8/29/90

9/13/90
Title

Final Guidance on
Administrative Records
for Selection of CERCLA
Response Actions.
Letter requesting extension
of public comment period.

Letter regarding
comments on the draft ROD
(confidential portion of
Administrative Record).

Letter responding to
select ARAR issues.
Letter responding to
Act 307 as an ARAR.
(confidential portion of
Administrative Record)

Letter responding to
Act 307 as an ARAR.

Letter regarding appli-
cation of ARARs to certain
alternatives.

Memo regarding application
of certain ARARs to the
Springfield site.

Letter regarding FS and
Proposed Plan.

Letter, with attachments,
regarding comments on the
FS and Proposed Plan.

Letter regarding Act 307.

Letter regarding public
comment period extension.
Author

U.S. EPA
Keith J. Lerminiaux


Robin L. Campbell




 William F. Bradford


 Jeremy M. Firestone




 William F. Bradford


Claudia Kerbawy



David A. Ullrich



Keith J. Lerminiaux


Keith J. Lerminiaux



     Jonas Dikinis

Richard J. Clarizio

-------
9/10/90



9/5/90




8/31/90




8/27/90


7/20/90



8/15/90




8/7/80



2/13/84
Letter regarding trans-
mission of information.

Nemo transmitting clean-
up information to the
Administrative Record.

Letter transmitting
information to Keith
J. Lerminiaux

Letter regarding select
ARAR issues.

Letter regarding extension
of public comment period.

Guidance on Remedial Actions
for Superfund Sites with
PCS contamination.

Notification of Hazardous
Waste Activity

Notification of Hazardous
Waste Activity.
Marilou Martin


Marilou Martin



Marilou Marting



Jonas Dikinis


Richard J. Clarizio


Henry L. Longest II



J.V. Burke


P. Dugan

-------
                            APPENDIX A

       LIST OF COMMENTORS DURING THE PUBLIC COMMENT PERIOD
                FOR THE SPRINGFIELD TOWNSHIP SITE
             FROM JULY 13 THROUGH SEPTEMBER 12, 1990


COMMENTS RECEIVED DURING THE PUBLIC MEETING ON JULY 24. 1990.

NAME AND AFFILIATION

Mr. John Lowell, Resident
Mr. Martz. Resident
Mr. Keith Lerminiaux, Springfield Township Steering Committee
Mr. Bernard Dooley, Resident
Mr. Dan Caplice, Geraghty & Miller
Mr. Chris Moore, Resident
Mr. Don Balkwell, Resident
Mr. Joe Gorka, Resident
Mr. Collin Walls, Resident
Ms. LeeAnn Oliver, Resident
Mr. Noel Maxim, Resident


COMMENTS SUBMITTED BY THE PUBLIC DURING THE PUBLIC COMMENT
PERIOD.

NAME AND AFFILIATION
                                        /
                                        ',
Mr. J. Calvin Walter, Clerk, Charter Township of Springfield.

Mr. Keith L. Krinn, R.S., M.A., Environmental Health Supervisor,
                    Environmental Health Services, Dept. of
                    Institutional and Human Services, Oakland
                    County, Michigan.

Mr. & Mrs. Harold Robinson, Residents.

Ms. Mary E. Duncan, Resident.


COMMENTS PREPARED BY THE POTENTIALLY RESPONSIBLE PARTIES (PRPs)
AND THEIR CONSULTANTS.

Springfield Township Site Steering Committee,
Letter signed by Keith J. Lerminiaux,
on behalf of the Committee.

Geraghty & Miller, Inc. Environmental Services.
Comments Relative to the Remedial Investigation, Feasibility
Study, and Proposed Plan for the Springfield Township Superfund
Site Springfield Township, Michigan.

-------
Geraghty & Miller, Inc. Environmental Services & Gradient
Corporation.
Technical Review Document and Proposal of Remedial Alternative
for the Springfield Township Site.

-------

                       RECORD OF DECISION
                 Remedial Alternative Selection


Site Name and Location

The Springfield Township Dump site is approximately a 400 by 500
foot fenced area located on an approximately 16 acre parcel of
land, south of Davisburg in Oakland County, Michigan.

Statement of Basis and Purpose

This decision document presents the selected remedial action for
the Springfield Township Dump site in Oakland County, Michigan,
which was chosen in accordance with CERCIA, as amended by SARA,
and, to the extent practicable,  the National Oil and Hazardous
Substances Pollution Contingency Plan (NCP).  This decision is
based on the administrative record for this site.  The index to
the administrative record is attached to the Record of Decision
(ROD).

The State of Michigan has concurred with the selected remedy.

Assessment of the Site                  ,;
                                        •?
Actual or threatened releases of hazardous substances from this
site, if not addressed by implementing the response action
selected in this ROD, may present an imminent and substantial
endangerment to public health,  welfare,  or the environment.

Description of Selected Remedy

The selected remedy addresses the principal threats posed by the
site, and is the final remedy for the site.  The major components
of the selected remedy are:

     *Excavation and thermal destruction of soils to remove to
     specified cleanup levels polychlorinated biphenyls (PCBs),
     volatile organic compounds (VOCs),  semi-volatile organic
     compounds (SVOCs), and pesticides in the source area;

     *Solidification of incinerator ash according to ARARs;

     *Solidification of soils contaminated only with metals;

     *Redeposition of ash and treated soil on-site (the ash will
     either be stabilized to make it inert prior to its on-site
     disposal or will be placed in a properly designed solid
     we.ste unit on-site) ;

-------
     *Recontouring of the excavated areas and control of the ash
     or dust emissions;

     installation of an in-situ vacuum extraction system to
     remove VOCs and SVOCs from remaining unsaturated
     contaminated soils at depth; and

     installation and operation of a ground water extraction and
     treatment system which utilizes a carbon adsorption unit to
     treat the groundwater before reinjection into the aquifer.

A detailed discussion of each of the components of the selected
remedy is presented in Section 9 of the ROD and in both the
Feasibility Study and Proposed Plan developed for the site.

Statutory Determinations

The selected remedy is protective of human health and the
environment, attains Federal and State requirements that are
applicable or relevant and appropriate for this remedial action,
and is cost-effective.  This remedy satisfies the statutory
preference for remedies that employ treatment that reduces
toxicity, mobility/ or volume as a principal element and utilizes
permanent solutions and alternative treatment technologies to the
maximum extent practicable.

Because this remedy will not result in hazardous substances
remaining on-site above health-based levels, the five-year
facility review will not apply to this action once the cleanup
performance standards are achieved.
        2 9 SEP 1990                         t*l orieinal signed ty
                                          Valdas V. Adaiakus
Date                                    Valdas V. Adamkus
                                        Regional Administrator

-------
                SSXTES BWIROMENIAL HOTECTIGN A2MCY
                           FHUCN V

     SEP 2 8  1990


     Itaqnrrt  for concurrence en the Record of Decision for the
     Springfield Township Site located in Davisburg, Michigan.

     David A. Ullrich, Acting Director         Bertram C. Frey
     Haste Management Division             Acting Regional Counsel

TO:  Valdas V. Adamkus
     Regional Administrator
   By this memorandum we are recommending that you authorize the
   Pamela! Action for the Springfield Township Site by executing the
   attached Record of Decision (ROD).   The  site is located in
   Davisburg,  Michigan.

   The ROD was prepared in accordance  with  the Comprehensive
   Budronmental Response, Compensation,  and Liability Act (CZRdA),
   42 U.S.C. §9601 et seq.. and the National Contingency  Plan,  40 CFR
   Part 300, and is consistent with Agency  CFRCIA policies.  We have
   reviewed the documents attached and have concluded  that the  ROD
   is both legally and technically sufficient. As such,  we believe
   that the implementation of the remedial  measures  as stated within
   the ROD, is proper exercise of your delegated  authority.

   Please feel free to contact either  of us should you have any
   Questions.

-------