1978-1983 WORK  PLAN
        FOR THE

\
C3
NATIONWIDE URBAN RUNOFF  PROGRAM
                  November, 1978
                Water Planning Division
            U.S. Environmental Protection Agency
                Washington, D.C. 20460

-------
         1978-1983 WORK PLAN
               FOR THE
   NATIONWIDE URBAN RUNOFF PROGRAM
            NOVEMBER 1978
       WATER PLANNING DIVISION
U.S. ENVIRONMENTAL PROTECTION AGENCY
       Washington, D.C.   20460

-------
                                                               CONTENTS
Section I - INTRODUCTION                                          1






Section II - PROBLEM STATEMENT                                    2






Section III - NATIONWIDE URBAN RUNOFF PROGRAM                     4




              Objectives                                          4




              Strategy                                            5




              Approach                                            6




              Prototype Projects                                  8




              Schedule                                           10




              Resource Requirements                              10






Appendix -    TASK DESCRIPTIONS                                  13






Appendix -    WORK ELEMENT DESCRIPTIONS                          23

-------
APPROACH

     The  objectives  of the   Nationwide Urban Runoff  Program  will be
achieved  by accomplishing  the   ten  tasks  whose  relationship  is shown
below.    The end  product  of the  program  is  the assessment  of  urban
runoff  on a nationwide basis  (i.e.,  from  problem  definition  through
control'planning)  and  the  resultant report  to  Congress.  The Prototype
Projects  conducted with the Regions  will provide the vehicle for devel-
oping information, insights, and perspective.
             7. Project
               Monitoring/
               Coordination
                           1. Program Development
                           Z Program Management
                           3. 208 Urban Runoff Status Development
                           4. Agency Coordination
                              5. Prototype Project Selection
                              6. Work Plan Development
 PROTOTYPE PROJECTS
CONDUCTED IN REGIONS
Technical/
Management
Assistance
                            9. Program Assessment and Evaluation
                            10. NATIONWIDE ASSESSMENT AND
                              REPORT TO CONGRESS
     Although the  tasks  referred to  here are  to be  performed by  the
Water Planning Division staff assigned to  the Nationwide Urban Runoff
Program (supported  by consultants as needed),  substantial participation
by the Regions is recognized as being  essential.  It is anticipated that
the Regions will  contribute  in  the  selection of  prototype  projects,
coordination  with  grantees, and  provision of  administrative support.
Tasks 1  through 4  are  the   effort  required  to establish the  program.
Tasks 5  and 6 are  associated  with  initiating  the Prototype  Projects.
Tasks 7  and 8 are the on-going efforts required to support  the Regions
and grantees who conduct  the projects.  In Task 9, the knowledge gained
will be synthesized to yield the products  of Task  10.  Table 2 summarizes
the work elements which make up these  ten tasks.   Additional  detail is
presented in the Appendix.

-------
Table 2.   TASKS COMPRISING THE  NATIONWIDE  URBAN RUNOFF  PROGRAM
1. PROGRAM DEVELOPMENT:
       • Define objectives for NURP.
       • Develop strategy.
       • Develop Program Execution Plan.
       • Coordinate with Regions.
       • Estimate resource requirements.
       • Obtain contractual support.

2. PROGRAM MANAGEMENT:
       • Prepare and maintain Program Management Notebook.
       • Prepare and maintain Master Plan.
       • Prepare and maintain Staffing Plan.
       * Prepare Program Budget Requests.
       • Provide ad hoc briefings to higher authorities.
       • Manage headquarters-level contracts.

3. 208 URBAN RUNOFF STATUS DETERMINATION:
       • Collect basic information.
       • Prepare 208 pre-screening checklist.
       • Visit Regions, review urban runoff portions of
         WQM plans.
       • Prepare summary reports.

4. AGENCY PROGRAM COORDINATION:
       • Coordinate with other EPA offices:
             - Office of Water Planning and Standards
             - Office of Water Programs Operation
             - Office of Toxic Substances
             - Office of Enforcement
             - Office of Solid Waste
             - Office of Research and Development
             - Office of Air, Noise, and Radiation

5. PROTOTYPE PROJECT SELECTION:
       • Develop project selection criteria.
       • Support Regions' project solicitation processes.
       • Pre-screen potential grantees.
       • Support preparation of grant applications.
       • Participate in final selection process.

6. WORK PLAN  DEVELOPMENT:
       • Receive requests for technical assistance.
       • Prepare model work plan.
       • Review initial work plan drafts.
       • Provide comments and guidance for revising and
         completing final work plans.
       • Meet with Regions, states, and areawide and
         local WQM agency representatives as required.
7. TECHNICAL/MANAGEMENT ASSISTANCE:
       •  Provide on-site technical assistance to projects.
       •  Establish data collection quality assurance protocol.
       •  Provide training for Regions, states, and areawide and
         local WQM agencies.
       •  Provide project management assistance to Project
         Officers in Regions.

8. PROJECT MONITORING/COORDINATION:
       •  Review and comment on progress reports.
       •  Attend project status briefings.
       •  Prepare and distribute/Voj/afn Newsletters.
       •  Provide information clearinghouse function.
       •  Maintain Prototype Project Status File.
       •  Establish Program Steering Committee, chair meetings.
       •  Provide program policy and guidance.

9. PROGRAM ASSESSMENT AND EVALUATION:
       •  Analyze information developed in preceding tasks to
         identify and assess major trends and cause-and-effect
         relationships.
       •  Analyze available information to determine its
         relationship to policy issues (including legal,
         institutional, and financial implications).
       •  Assess the practical applicability of effective control
         measures.
10. NATIONWIDE ASSESSMENT AND REPORT TO CONGRESS:
       •  Review quarterly and annual 208 reports.
       •  Summarize information on problem identification.
       •  Summarize cause-and-effect relationships, resource
         needs, and cost-effectiveness of control alternatives.
       •  Summarize institutional, legal, and financial aspects.
       •  Document urban runoff problems, effectiveness of
         controls, and cost of implementation.
       •  Synthesize a Nationwide Urban Runoff Control Program.
       •  Prepare report to Congress.

-------
PROTOTYPE PROJECTS

     The Prototype  Projects  provide a means for obtaining  information
essential to developing a nationwide perspective and will simultaneously
provide Regions, states, and 208 agencies with site-specific  information
they need for planning  and  decision making.  Projects will be conducted
in all Regions  during  the  course of  the program.   The projects  which
have been identified for the first round  (i.e., 1978-1979 funding)  are
described briefly in Table 3.

     The prototype projects will vary  considerably in scope and focus.
Attempts will be made to  allocate the funds  approximately in proportion
to need.  As a first approximation, the "need" of each each Region  was
defined in  terms  of a  rough index which was obtained by computing  the
product  of  population  and annual  runoff.    Those regions with large
populations and high runoff were  assumed  to be more likely  to  have  ur-
ban runoff problems; sparsely populated arid regions  less  likely.  The
results of such computations are charted below along with a chart showing
the preliminary allocation of funds among the Regions.
       Index of Need in Region
       f (population, runoff volume)
      VIM
Allocation of Funds to
Prototype Projects
    COMPARISON OF NEED VERSUS FUNDING ALLOCATION  '

-------
Table 3.  SUMMARY OF PROTOTYPE PROJECTS
REGION
I.
II.

III.
IV.


V.





VI.
VII.

mi.
IX.
i.
PROJECT RECEIVING
LOCATION WATER TYPE
Massachusetts
Middlesex, HJ river/estuary
Nassau/ Suffolk, ITT groundvater
Balciaore, MD river
Vaccamav , SC ocean
Tampa/St. Petersburg, H. river
Winston-Salcm, NC river/lake
NIPC, H stream
EPA, 11 river
SZHCOC, MI river/lakes
Ann Arbor, MI
Lansing , MI river
SEVRPC, VI lake
Houston, TX
Kansas City, MO river
St. Louis, MO river/lake
Denver, CO stream
Castro Valley, CA creek
Bellevue, UA creeks
FOCUS OF
STUDY
-
recreation,
industry,
standards
violations
water supply
aesthetics,
recreation,
standards
violations
recreation,
standards
violations
-
standards
violations
fishery Impacts,
standards
violations
standards
violations
eutrophication,
standards
violations
-
recreation,
fishery impacts,
aesthetics
-
-

-

fishery iapacts,
sesthetics
fishery
Impacts
MAJOR
POLLUTANTS
-
bacteria,
coxics
coxics
coxics
bacteria,
oxygen
demand
bacteria,
coxics
-
bacteria,
toxics,
demand
oxygen
bacteria,
toxics,
oxygen
denand
toxics
sediments,
bacteria,
nucleate
-
bacteria,
coxics,
nutrients
-
-
-
-
*
sediments,
heavy aecals
sediments,
coxics ,
CONTROL PRECIPITATION
MEASURES AND LAHDFORM
-
-
percolation through
soil mantle,
street sweeping
sedimentation basin,
street sweeping,
catchbasin cleaning
outfalls , rediverslon
disinfection,
ordinance enforcement
-

detention basins,
source Identification
street sweeping
detention basins
-
detention baelns
(above and below
grade)
-
-
-
-
™
street sweeping,
catchbasins
ordinances,
street iweeping,
45 in/yr
45 in/yr
piedmont
43 In/yr
coastal
45 In/yr
piedmont
50 ia/jr
coastal
53 in/yr
coastal
45 in/yr
piedmont
35 In/yr
plains
35 ia/yr
plains
30 in/yr
plains
30 U/yr
plains
30 in/yr
plains
30 In/yr
plains
45 la/yr
plains
35 ta/yr
plains
40 in/yr
plains
li in/yr
mountains,
plains
20 in/yr
foothills
35 in/rr
piedmont
STUDY
AREA SIZE
-
large river basin
small subcatchment
medium basin
medium, linear
watershed
-
small, dense,
urban catchment
smell, dense,
urban catchment
small, dense,
urban catchment
small, developing
basin

Small , urban
basin
-
-
-
-

medium, aev«l oping,
suburban catchment
small, residential
subcacchmencs

-------
 SCHEDULE

 The Nationwide  Urban  Runoff  Program is  planned  to  extend  over a period
 of  five years,  yielding  its  major output in late 1983 (i.e., the nation-
 wide assessment and report  to Congress). However, the program is designed
 such that  there will be numerous other  outputs at  various  times,  as
 indicated  in  the  following figures.
RESOURCE REQUIREMENTS

      The Nationwide  Urban  Runoff  Program  described here will  require
an  estimated  22  person-years effort and $30 million over its five year
duration.  Most of the effort will be by EPA Headquarters (17 person-years) .
The prototype projects  (approximately  30 in  all)  will  require an esti-
mated $29  million, about  $6 million of  which is  allocated  to the first-
round of  19 projects (see Table  4). The consulting group  will require
an  additional $600,000  in contract funds.   Travel over  the  five years
will cost  approximately $300,000 (consisting of about $42,000 for Head-
quarters,  $1000 for Regional  personnel, and $50,000 per year for  the
consulting group) . It is anticipated that the development of wet-weather
.flow criteria methodology will require.ah  additional $75,000.
                                   10

-------


Program Development

Program Management

208 Urban Runoff
Status Determination

Agency Program Coordination

Prototype Project Selection

Work Plan Development

Technical and
Management Assistance

Project Monitoring

Program Assessment
and Evaluation

Nationwide Assessment and
Report to Congress

Calendar Years
1978 , 1979 , 1980 , 1981 , 1982

111114

H 1

1 i

h 1

} A J|

* 4

I !

i 1

1... \ 1.1 ill i

C3 C"*! i ^
A- Arnusl reoort output
SCHEDULE FOR OVERALL PROGRAM

Program Management
Prototype Project Selection
Work Plan Development
Agency Program Coordination
Project Monitoring
and Coordination
Program Assessment
and Evaluation
Technical Management
and Assistance
SONOJ FMAMJ J ASO

1* • 1
Comotete program
«rat«qv statement
t *|
Initiate first
round projects
f *l
Complete work plans
for first round project*
\ * \
tnritate cooperative program
with U.S. Geological Survey
I * Q Q Q *j
Submit status Submit annual
report reuo't
1 1

1 i
Q • Quarterly reports
SCHEDULE FOR FISCAL YEAR 1979
                              11

-------
TABLE  4.   STATUS  AND  FUNDING OF PROTOTYPE  PROJECTS
REGION
              PROJECT
              LOCATION
                             STATUS AS OF
                             OCTOBER 1978
   I.
           Massachusetts
                              proposal
                              due 9/78
  II.      Middlesex, KJ
           Nassau/Suffolk, NY
                              potential
                              project  1/79

                              potential
                              project  1/79
 III.
Baltimore,  MD
work plan in
preparation
  IV.      Waccaaaw, SC
           Tampa/St. Petersburg,  FL
           Winston—Salem, NC
                              project
                              began  8/78

                              project
                              began  8/78

                              work plan in
                              preparation
   7.
KIPC, n.


UPA, U,  •


SEMCOG, MI


Ann Arbor, MI

Lansing, MI


SEWRPC, WI
                                         project
                                         selected

                                         project
                                         selected

                                         project
                                         selected

                                         to be designated

                                         project
                                         selected

                                         project
                                         selected
    VI.     Houston, IX
                              to be designated
   VII.     Kansas  City, MO
            St.  Louis, MO
                              potential
                              project 1/79

                              proposal due
                              10/78
   VIII.     Denver  CO
                              potential
                              project
     IX.     Castro  Valley, CA
      X.     Bellevue,  WA
                              pilot project


                              pilot project
                                                12

-------
            Appendix




Task Descriptions

-------
Task 1. PROGRAM DEVELOPMENT

Objective;      To  develop clearly stated program objectives,  a well-
                founded strategy,  and  an implementable execution plan
                for the Nationwide Urban Runoff Program

Work Elements;   Define objectives for NURP (11/77 to 3/78)

                Develop strategy (1/78 to 8/78)

                Develop Program Execution Plan (1/78 to 8/78)

                Coordinate with Regions (2/78 to 7/78)

                Estimate resource requirements (7/78 to 8/78)

                Obtain contractual support (3/77 to 3/78)
Description;
Products:
An initial draft of the Nationwide Urban Runoff Program
 Plan will  be  prepared  and (following Headquarters re-
 view)  sent to the Regions for review and comment.  Meet-
 ings will  be held in each Regional Office to discuss the
 proposed program, answer questions,  and receive comments
 (especially on the  program objectives, nationwide stra-
 tegy,  and roles and responsibilities of the team parti-
 cipants). Following this round of Regional visits, com-
 ments  received and insights  gained will be used to pre-
 pare a refined program strategy and execution plan. Based
 upon this,  a  refined estimate of resource requirements
 will be  prepared.

 Nationwide Program Strategy

 Program  Execution  Plan
                Resource requirements estimate

Resource Requirements;            p - yr   travel

                Headquarters:      .72      $ 0

                Regions:           .16      $ 0
                                 13

-------
Task 2. PROGRAM MANAGEMENT
Objective:
Work Elements:
Description;
 To assure  that  the Nationwide Urban Runoff Program is
 well managed  through completion.

 Prepare  and maintain Program Management Notebook (4/78
 to completion of program)

 Prepare  and maintain Master Plan (7/78 to 9/78 to pre-
 pare, will be maintained throughout the program.)

 Prepare  and maintain Staffing Plan (8/78 to 9/78)

 Provide  Program  Budget Requests (6/79 to completion of
 program;  to be done annually)

 Provide ad hoc briefings to higher authorities (initiated
 upon request)

 Manage Headquarters-level contracts (3/78 to 3/80)

The initial Program Management Notebook, Program Master
 Plan, Program Budget  Request,  and Staffing  Plan  will
 be prepared,  using the Nationwide Strategy  and Program
 Execution Plan, developed during Task 1.  These will be
 updated  and maintained throughout  the  duration of the
 program.  The maintenance of  program management docu-
 mentation will facilitate the ad hoc status brief ings to
 higher authorities and others. The Program Manager will
 serve as Project Officer on Headquarters-level contracts.
Products:       Current Program Management and Notebook

                Current Program Master Plan

                Current Program Staffing Plan

Resource Requirements;          p - yr     travel

                Headquarters:    1.23       $ 0

                Regions:           0        $ 0
                                 14

-------
Task 3. 208 URBAN RUNOFF STATUS DETERMINATION

Objectives;      To  assemble  and  document information on  the status of
                the urban runoff portion of the WQM plans.   To estab-
                lish the basis  upon which to  develop the  NURP.    To
                identify potential Prototype  Project  areas.

Work Elements;  Collect basic information (10/77 to 2/78)

                Prepare 208 Pre-screening Checklist (2/78)

                Visit each Region to  review urban runoff portion of WQM
                plans (3/78 to 6/78)
Description;
Prepare Summary Reports (5/78 to 8/78)

Using "Profile" information,  a first assessment of the
extent of urban runoff  problems will be made.  Meetings
will be held in each region with WQM Branch Chiefs, Sec-
tion Chiefs, Project Of f icers, WQM and NPS coordinators,
and technical support staff.  Regional 208 Project Offi-
cers will be asked to complete a Pre-screening Checklist.
The current status  of 208 urban  runoff studies  will
be discussed with regional staff.  The 208 projects which
show potential for further work  will be selected from
Pre-screening Checklists  and  discussed with the Project
Officers.  Reports  summarizing discussions with Region-
al staffs  and  information learned from  Pre-screening
Checklists will be prepared,  and a  list of  potential
Prototype Projects will be developed.

Pre-screening Checklist

Report summarizing Checklists

Report summarizing Regional  visits

List of potential Prototype Projects
Resource Requirements;            p - yr   travel

                Headquarters;      1.10    $9300

                Regions:            .97    $  0
Products:
                                  15

-------
Task 4. AGENCY PROGRAM COORDINATION
Objective;
 To provide information  for other  Agency programs and
 obtain support for NURP.
Work Elements;  Coordinate with other EPA offices:

                Office of Water Planning and Standards (10/78 to 1/80)

                Office of Water Programs Operation (10/78 to completion
                of program)

                Office of Toxic Substances ( 1/79 to completion of program)

                Office of Enforcement (10/78 to completion of program)

                Office of Solid Waste  (1/80  to completion  of  program)

                Office  of  Research  and  Development  (8/79 to  comple-
                tion of program)

                Office of Air, Noise,  and  Radiation (1/79 to completion
                of program)
Description:
Products:
 Wet-weather  flow  criteria  nust be  developed through
an effort involving  the  Water  Quality  Standards Cri-
teria Division and  the NURP.  Step One grants for combined
sewer projects in Prototype Project areas should be joint-
ly developed with this program.   NURP will assess  the
magnitude and extent of the toxic contribution to water
pollution  and  may  identify  sources of  toxic material
of which OTS may need to be aware.  The NPDES and General
Permit  programs will need  information  from  the  NURP
to write meaningful  permits.   The residuals generated
by some  BMP's  will create  demands   for  disposal space
and must be considered in solid waste management plans.
NURP can  also  provide  information  regarding  needs  for
research and development.

None
Resource Requirements;

                Headquarters:

                Regions:
p - yr
1.10
0
travel
$ o
$ o
                                  16

-------
Task 5. PROTOTYPE PROJECT SELECTION

Objective:       To  select (from  208 areawide and  statewide  agencies
                willing to participate) appropriate Prototype Projects
                to assure that overall  program objectives can  be met.

Work Elements;  Develop project selection criteria (3/78 to 7/78)

                Support Regions'  project  solicitation  processes  (7/78
                to 7/79)

                Pre-screen potential grantees (7/78 to 7/79)

                Support preparation  of grant applications (8/78  to 8/79)

                Participate in final selection process  (7/78 to 9/79)
Description;
Products:
Criteria for selecting Prototype Projects will be dis-
cused in meetings at  each Regional  office, and inputs
to the final selection process will be requested. Follow-
ing the round of Regional visits, a selection criteria
guideline document  will be prepared.    Support to  the
Regional solicitation process will be provided on request
(probably in the form of program presentations and on-site
visits).   Potential  grantees  will be pre-screened to
avoid duplication of effort or inappropriate activities.
Grant application support will be provided  (on request),
ranging  from  review and  comment on  draft material to
on-site  technical  or managerial consultation.   Final
selection of Prototype Projects will be made in consul-
tation with Regional staff.

Designation of Prototype Projects
Resource Requirements;

                Headquarters:

                Regions:
                p - yr   travel

                 .72     $10,000

                 .60     $   0
                                  17

-------
Task 6. WORK PLAN DEVELOPMENT

Objectives;        To assure comparability in the emerging information
                base.   To  achieve  a uniform  approach toward the de-
                velopment  of water  quality management  plans.  To as-
                sure that  work plans are  developed around local, Re-
                gional , and  national needs.

Work  Elements;  Receive requests for technical assistance (8/78 to  7/82)

                Prepare a model work plan  (8/78 to  9/78)

                Review initial  work  plan drafts (8/78 to 3/79)

                Provide comments and guidance for revising and completing
                final work  plans  (8/78 to  5/79)

                Meet with Regions,  States, and  areawide and  local WQM
                agency representatives as  required  (1/79 to 8/81)
Description;
Selection of Prototype Projects will be based on needs.
Work plan development will be guided by Headquarters by
sending  teams when  requested.   It is envisioned that
teams consisting  of  one  person  from Headquarters and
two consultants (each consultant having a different area
of expertise)  will (after selection  of  the Prototype
Project)   review initial work plans, provide comments
and guidance, visit  Prototype  Project areas (when re-
quested),  and help write  final work plans.
Products;       Model work  plan

                Prototype Project work plans

Resource Requirements;          p - yr    travel

                Headquarters:     .48      $9500

                Regions:          .26      $ 0
                                   18

-------
Task 7. TECHNICAL/MANAGEMENT ASSISTANCE
Objectives:
Work Elements:
Description;
Products:
                 To provide technical  and  management  assistance  with
                which to extend Regional, Statewide, areawide, and local
                capabilities in developing  and  implementing  WQM plans.
                To assure comparability in the emerging information base.

                Provide on-site technical assistance  to projects (8/78
                to 9/81)

                Establish   quality assurance protocol for  data  collec-
                tion (6/78  to 8/78)

                Provide training for Regions, States,  and  areawide and
                local WQM  agencies (8/78 to completion of  program)

                Provide project management  assistance to Project Of-
                ficers in  Regions

                Initiate a  public  participation program  (8/78-9/82)

                Technical  and management assistance in the form of on-
                site help   in  all technical areas will be provided to
                the  Regions  and Prototype  Projects  by Headquarters.
                Training will be provided to Regional, State, areawide,
                and local  WQM Agency staff s. All assistance and training
                will be provided  upon  request.   Protocol for  quality
                assurance  will be developed to  provide  guidelines (con-
                sistent with supporting agencies such as the U.  S. Geologi-
                cal Survey) with which to develop high quality,  compar-
                able information.
	           Quality assurance protocol

                Technical/management assistance

Resource Requirements:            p - yr  travel

                Headquarters:      .94    $6000

                Regions:          .85    $1000
                                     19

-------
Task 8. PROJECT MONITORING / COORDINATION
Objective;


Work Elements:
Description:
Products:
To  provide a nationwide overview and assure  that pro-
gram  objectives are being met in each Prototype Project.

Review and  comment on progress reports (10/78 to 9/81)

Attend project status briefings  (8/78 to 9/81)

Prepare  and distribute Program  Newsletters  (11/78  to
9/81)

Provide information clearinghouse function (8/78  to com-
pletion of  program)

Maintain  Prototype Project Status  File (8/78  to com-
pletion of  program)
                Establish Program  Steering  Committee;
                (9/78 to completion of program)
                                        chair meetings
Provide  program policy and  guidance  (8/78  to comple-
tion of program)

This task  will provide overview and control  to assure
that program goals  are met.  Quarterly reports will be
provided  so that  Regional Project Officers  and Head-
quarters  coordinators will be able make minor adjust-
ments of the  direction of  projects.    Annual reports
will be used to evaluate projects' merit  for the following
year's  funding.   A  quarterly newsletter will be used
to  keep  program participants informed  as  to  the pro-
jects' status  and any new information which nay be help-
ful.  A project status file will be kept current. Head-
quarters will  form and chair a program Steering Committee
composed  of members  from EPA,  the States,  and local
users.   The committee will provide review,   direction,
and guidance to the NURP.  Program policy on such matters
as  financial,  institutional, and legal issues will be
dealt with  by  other Branches within the Water Planning
Division.

Quarterly newsletter
Bulletins on recent developments
Project Status  File
Program Steering Committee
Program policy  and  guidance
Resource Requirements;            p - yr    travel

                Headquarters:      2.65     $7700

                Regions:           1.85     $1000
                                 20

-------
Task 9. PROGRAM ASSESSMENT AND EVALUATION
Objective;
Work Elements:
Description;
To gain an accurate perspective of the degree to which
urban runoff  is  a problem of  national  importance and
assess the implications of various control strategies.

Analyze  information  developed in  preceding  tasks to
identify and  assess major  trends and cause-and-effect
relationships (11/78 to 9/82)

Analyze  available  information to  determine its rela-
tionship  to  policy issues  (including  legal, institu-
tional, and financial implications) (1/81 to 1/82)

Assess the  practical applicability of effective control
measures (9/81 to 3/82)

Assess public support  for  implementing  urban  runoff
controls.

This  task consists largely of an effort to synthesize
what is learned from the program to  date. It will involve
a review  of the various  memoranda,  reports,  and  other
file materials developed  during the program. The effort
will focus  on identifying  ways  in which the findings
of this  program  indicate  needs  for policy changes  or
reconsideration.

This task  will assess  the ways in which urban control
will interface with established policy and their legal,
institutional, financial,  and/or  environmental implica-
tions.  The importance of urban runoff as a nationwide
problem is defined in terms of water quality standards
and policies regarding beneficial use. The legal basis
for requiring control  involves policy considerations.
The responsibility for implementing controls and their
funding both involve policy considerations.  At the local
level, some  of the more  cost-effective controls will
involve careful considerations of (and possibly amend-
ments of)  public policy.

The task  will also involve an assessment of the costs
and effectiveness of various candidate control measures
and their  financial,  social,  and environmental impli-
cations.   Effectiveness  will  be  expressed in terms of
the measures' ability to practicably reduce  impacts on
water quality.
 Products:        Various  inputs  to Task  10

 Resource  Requirements;              p - yr     travel

                 Headquarters:        2.50      $ 0

                 Regions:               .38      $ 0
                                     21

-------
Task 10. NATIONWIDE ASSESSMENT AND REPORT TO CONGRESS
 Objectives;
To provide a nationwide assessment of NURP results, data
 transferability, and  implications for problem solution
 across  the country.   To prepare a  report to Congress
 showing where urban runoff problems  exist, the degree of
 severity, and estimated cost  for correction on a regional
 and national basis.
 Work Elements;  Review quarterly and annual 208 reports (10/79 to 12/81)

                 Summarize  information on problem  identification (10/79
                 to  9/82)

                 Summarize cause-and-ef fect relationships, resource needs ,
                 and  cost  effectiveness of  control alternatives (10/79
                 to  9/82)

                 Summarize  institutional,  legal,  and financial aspects
                 (10/79  to  9/81)

                 Document  urban runoff  problems,  effectiveness of con-
                 trols,  and cost of  implementation (12/80 to  12/81)

                 Synthesize  a  Nationwide  Urban Runoff Control Program
                 (12/81  to  12/82)
 Description;
Prepare report  to Congress (12/81 to late  1982)

Progress reports from the Prototype Projects and other
applicable  urban runoff  information will be reviewed
from  a  nationwide  perspective.   Summary  reports will
be  prepared.  They will contain cause-and-effeet data,
and control  effectiveness  and  costs,  and  address in-
stitutional,  legal,  and financial aspects.  A Nation-
wide  Urban Runoff Control  Program will  be developed and
summarized in a report  to Congress.
 Products;       Annual NURP summary  reports

                Nationwide Urban  Runoff Control Program Plan

                Report to Congress

 Resource Requirements;            p - yr    travel

                Headquarters:     6.45     $ 0

                Regions:             0      $ 0

-------
                    Appendix



Work Element Descriptions

-------
WORK ELEMENT la - DEFINE OBJECTIVES FOR NURP
METHOD:
      This Work Element will  consist  of  a  thorough review of pertinent
      prior Agency accomplishments  in the urban runoff area, facilitated
      by inputs  from  Work Element 3a. Based upon an assessment of the
      current state of the  art and  needs identified  by 208 agencies and
      other federal activities (such as the Congressional Public Works
      Committee), the objectives  of the Nationwide Urban Runoff Program
      will be developed,  reviewed,  and finalized.
PRODUCT:
      Clearly defined and agreed  to program objectives which can be incor-
      porated in the  plan  to be developed in Work  Elements  Ib  and Ic.
SCHEDULE:
      This Work Element will be initiated in November 1977 and essentially
      completed by March 1978.
RESOURCE REQUIREMENTS:

      Completion of this Work Element, including reviews at  various agency
      levels, will require approximately three  person-months  of Head-
      quarters and Regional effort, plus some consultant team support.
                                            Travel

      Headquarters            .17             0

      Regional                .08             0

                              .25             0
                                 23

-------
WORK ELEMENT Ib -  DEVELOP STRATEGY
METHOD:
      A draft  nationwide  strategy  for  the program will  be  developed
      at Headquarters, based upon inputs from Work Elements la and 3a,
      as well as other sources.  It  will be  sent  to the Regions for re-
      view and comment as an Information Memorandum. During the Regional
      visits (conducted as part of Work Element  3c) , the proposed strategy
      will be discussed; suggestions and Regional perspectives will be
      solicited.   A  refined strategy will be prepared  incorporating
      these comments.
PRODUCT:
      The strategy for the Nationwide Urban Runoff Program.
SCHEDULE:
      This Work  Element will  be  initiated  in January 1978 and completed
      in August 1978.
RESOURCE REQUIREMENTS;

      Completion of this Work Element, including reviews at various agency
      levels, is estimated to require  approximately  three person-months
      of Headquarters and  Regional effort, plus consultant team support.
      Resource requirements (including travel)  are  included  underwork
      Element 3c.
                                            Travel

      Headquarters            .17             0

      Regional                .08             0
                                 24

-------
WORK ELEMENT Ic - DEVELOP PROGRAM EXECUTION PLAN
METHOD:
      A preliminary execution plan will be developed  jointly  with the
      nationwide strategy of Work Element Ib and submitted to the same
      review and refinement  process. Based upon  the  results, a detailed
      program execution plan (divided into Tasks  and  Work Elements) will
      be developed.
PRODUCT:
      An implementable  execution plan  for  the Nationwide Urban  Runoff
      Program.  This  will be incorporated in the Program Master  Plan
      developed in Work Element 2b.
SCHEDULE:
      This Work Element  will be  initiated  in January  1978 and  com-
      pleted in August 1978.
RESOURCE REQUIREMENTS;

      Resources required for developing the execution plan have been in-
      cluded  in  the  estimate for Work Element  Ib. Travel  requirements
      are included in Work Element 3c. Development of  the final program
      execution plan is estimated to require approximately two person-
      months of Headquarters effort, plus consultant team support.
                                          Travel

      Headquarters            .17            0

      Regional                 0             0
                                 25

-------
WORK ELEMENT Id - COORDINATE WITH REGIONS
METHOD:
      In order to obtain Regional perspectives as well as Headquarters
      viewpoints in all aspects of the Nationwide Urban Runoff Program,
      close coordination with the Regions will be  established and main-
      tained throughout the program development period. This will include
      meetings and  discussions (at Headquarters and in Regional offices),
      dissemination of  draft program documentation for review and comment
      (e.g., proposed strategy, program tactics,  team approach, roles
      and responsibilities), and  incorporation of comments into  final
      products.
PRODUCT:
      Inclusion  of Regional  perspective along with Headquarters view-
      points in all program development products.
SCHEDULE:
      This Work Element will  be  initiated in February 1978 and completed
      in July 1978.
                                 26

-------
WORK ELEMENT le - ESTIMATE RESOURCE REQUIREMENTS
METHOD:
      This Work Element will  consist  of  reviewing the planned Work Ele-
      ments and identifying  their  level of effort. The estimates will
      be compiled into a matrix, and the rows and columns summed hori-
      zontally and vertically (balancing the highs and lows).
PRODUCT:
      An estimate of required resources.
SCHEDULE:
      This effort will  begin when the first  Work  Element is begun and end
      with the completion of the matrix.  See Work Element 2b.
RESOURCE REQUIREMENTS;

      This Work Element will require 2 person-weeks effort in addition to
    . 'that identified in Work Element 2b.
                              P-Yr          Travel

      Headquarters            .04             0

      Regional                 0              0

                              .04             0
                                 27

-------
WORK ELEMENT If - OBTAIN CONTRACTUAL SUPPORT
METHOD:
      Prepare Request  For Proposal after identifying contractual needs.
      Identify  tasks  for consultants.  Work  with  contracts  office to
      ensure timely finalization of contracting procedure.
PRODUCT:
      Contractual support.
SCHEDULE:
      This Work Element must be initiated no  later than March 1977 to
      ensure completion by March 1978.
RESOURCE REQUIREMENTS;

      It is estimated that this Work Element will require a program man-
      ager to spend two person-months of effort.
                              P-Yr          Travel

      Headquarters            .17             0

      Regional                	0             0

                              .17             0
                                 28

-------
WORK ELEMENT 2a - PREPARE AND MAINTAIN PROGRAM MANAGEMENT NOTEBOOK
METHOD:
      The outline and organization  of  the Program Management Notebook
      will be developed, and  all applicable information sources will be
      collected  and  assembled (e.g., nationwide strategy, program exe-
      cution plan, resource estimates, contractual documentation, vouch-
      ers, progress reports).
PRODUCT:
      A basic  source  of  information,  in  notebook  form,  covering all
      aspects of the program.
SCHEDULE:
      This Work Element will  be initiated by April  1978 and will continue
      until program is completed.
RESOURCE REQUIREMENTS;

      It is estimated  that a  program manager  and consultant will need
      two person-weeks to prepare and two person-weeks per year to maintain
      the management notebook.

                              P-Yr          Travel

      Headquarters            .25             0

      Regional                	0             0

                              .25             0
                                 29

-------
WORK ELEMENT 2b - PREPARE AND MAINTAIN PROGRAM MASTER PLAN
METHOD:
      A master  plan covering  all  functions,  tasks, and Work Elements
      will be produced.  This will  be  used  for  informational as well as
      managerial purposes.
PRODUCT:
      Master plan document.  This effort will facilitate implementation
      of Work Element 2c.
SCHEDULE:
      This Work Element will be initiated July 1978, be operational by
      September 1978, and continue through program completion.
RESOURCE REQUIREMENTS:

      Program manager and consultant will prepare the plan. It is estimated
      that two person-months will be needed to prepare and two person-
      weeks per year will be needed to maintain the plan over the life
      of the program.
                              P-Yr          Travel

      Headquarters            .38              0

      Regional                	0              0

                              .38              0
                                 30

-------
WORK ELEMENT 2c - PREPARE AND MAINTAIN PROGRAM STAFFING PLAN
METHOD:
      The Headquarters program organization and staffing  plan with per-
      sonnel responsibilities will be  prepared, based upon Headquarters
      requirements, estimates made in  the program execution plan (devel-
      oped in Work Element Ic), and the availability of personnel.
PRODUCT:
      A staffing plan to be used  by  the program manager in assigning in-
      dividual work details.
SCHEDULE:
      This Work Element will be initiated August 1978 and largely com-
      pleted by September 1978.
RESOURCE REQURIEMENTS:

      Program manager  and  consultant  will  prepare  the  document.  One
      person-month of effort will  be  required  to  prepare and one person-
      week per year will be needed to maintain  the plan  over  the life
      of the program.

                              P-Yr          Travel

      Headquarters            .17              0

      Regional                	0              0

                              .17              0
                                 31

-------
WORK ELEMENT 2d - PREPARE PROGRAM BUDGET REQUESTS
METHOD:
      Program budget  requests  (including  travel dollars, personnel, and
      contract funding) will be  prepared  on an annual  basis  for integra-
      tion into the division's budget preparation process. These will be
      based upon estimated future program requirements.
PRODUCT; Budget requirements for Division use.
SCHEDULE;

      This Work Element  will be performed annually, beginning June 1979
      and terminating with the program.
RESOURCE REQUIREMENTS;

      A program manager with an assistant  will  require about one person-
      week per year over the life of the contract.
                              P-Yr          Travel

      Headquarters            0.1             0

      Regional                	0             0

                              0.1             0
                                 32

-------
WORK ELEMENT 2e - PROVIDE AD HOC BRIEFINGS TO HIGHER AUTHORITIES
METHOD:
      Briefing packages will  be  prepared   on short notice, to inform
      upper-level management of current status of the NURP.  Depending
      on the time available, packages of slides, films, speech notes, etc. ,
      can be provided.
PRODUCTS:
      Briefing packages.
SCHEDULE:
      This Work Element will be initiated upon request.
RESOURCE REQUIREMENTS;

      Depending on the briefing package requested, the requirements can
      range from one to three persons and consultant team support.
                              P-Yr          Travel

      Headquarters         to 0.1 per          0
                           briefing

      Regional                  0              0

                           to 0.1              0
                                33

-------
WORK ELEMENT 2f - MANAGER HEADQUARTERS-LEVEL CONTRACTS
METHOD:
      This Work Element will include directing the technical support to
      be provided via contracts.
PRODUCT:
      Technical support program.
SCHEDULE:
      This Work Element is to be initiated March 1978 and terminate in
      March 1980.
RESOURCE REQUIREMENTS;

      A program manager will spend approximately four months full time
      during a typical three-year contract.
                              P-Yr          Travel

      Headquarters             .33            0

      Regional                	0            0

                               .33            0
                                 34

-------
WORK ELEMENT 3a - COLLECT BASIC INFORMATION
METHOD:
      Basic information will be collected from  the  "computerized  pro-
      files", from work  plans that have been submitted to Headquarters,
      and from other reports  (e.g.,  publications  of  State,  local, and
      professional organizations dealing with urban runoff).
PRODUCT:
      This information will be used to identify needs and aid in finalizing
      the urban runoff program strategy being developed in Work Element
      Ib.
SCHEDULE:
      This Work Element will  be  initiated in November 1977 and completed
      by February 1978.
RESOURCE REQUIREMENTS;

      Nine person-months effort will  be  required,  involving the program
      manager,  the  information center,  and technical  specialists.  No
      contract funds  are  needed.   Travel  will  be necessary  to attend
      urban runoff conferences in December 1977.
                                            Travel

      Headquarters            .75           $ 400

      Regional                	0           	0

                              .75           $ 400
                                 35

-------
WORK ELEMENT 3b - PREPARE 208 PRE-SCREENING CHECKLIST
METHOD:
      A pre-screening checklist will be developed after an initial review
      of the urban runoff portion  of  all work  plans  within one Regional
      office.  The  purpose of  the  checklist  will  be to maximize the ef-
      ficiency of the review team, document the current status of work
      plan development, aid in identifying  potential prototype projects,
      and identify needs for assistance.
PRODUCTS:
      Pre-screening questionnaire and checklist.
SCHEDULE:
      This Work Element will  be initiated during February 1978; the final
      checklist is needed by March 1978.
RESOURCE REQUIREMENTS;

      One person from Headquarters, a program manager  or  a Regional Proj-
      ect Coordinator, and the consultant team will prepare the checklist.
      It is anticipated that  the Regional needs will be approximately 400
      person-hours (there are about 100 projects to be reviewed). No travel
      is anticipated.
                             P-Yr          Travel

     Headquarters            .02             0

     Regional                .20             0

                             .22             0
                                 36

-------
WORK ELEMENT 3c - VISIT EACH REGION TO REVIEW
                  URBAN RUNOFF PORTION OF WQM PLANS
METHOD:
      Ten Regional meetings  will be  scheduled  with  each  Region.  Two
      members from Headquarters and four consultants (each with a dif-
      ferent area  of  expertise) will  comprise the review team.  The pro-
      posed strategy will be discussed for further refinement, Project
      Officers will  be  asked to present  completed  questionnaires and
      checklists,  and likely candidates will be reviewed and discussed
      in detail.
PRODUCTS:
      Completed  questionnaires  and  checklists, information with which
      to refine and  finalize the strategy being developed in Work Element
      Ib, and a list of potential prototype projects to facilitate execu-
      tion of Work Element 5c.
SCHEDULE:
      It is anticipated that the visits will  be  conducted  between March
      1978 and June 1978.
RESOURCE REQUIREMENTS:

      Sixty person-days for the Headquarters team, 120 person-days for
      the consultant team, and 200 person-days (20 per Region) for the
      Regions will be required.  Considerable travel and consultant time
      will be needed.
                              	          Travel

      Headquarters

      Regional
                                 37

-------
WORK ELEMENT 3d - PREPARE SUMMARY REPORTS
METHOD:
      Upon completion of  the Regional visits, the comments  of the Regions
      and review team  will  be  summarized in two  reports. One report will
      summarize the information gained from the pre-screening checklist;
      the other will summarize the visit.
PRODUCTS:
      Summary reports to be used in the initial selection of prototype
      projects.
SCHEDULE:
      Summary report preparation will be initiated in May 1978; reports
      will be issued by August 1978.
RESOURCE REQUIREMENTS;

      It is anticipated that four person-weeks will be required. Head-
      quarters team  members  will  write the reports, and a member of the
      consultant team will provide review.
                              P-Yr          Travel

      Headquarters            .08             0

      Regional                	0             0

                              .08             0
                                 38

-------
WORK ELEMENT 4a - COORDINATE WITHIN THE OFFICE OF WATER PLANNING
                  AND STANDARDS
METHOD:
      Coordination between the NURP and OWP&S must be developed either
      through an ongoing agreement or  through  a  liaison person.  This
      is necessary  because  the Nationwide  Urban Runoff Program needs
      to have wet-weather criteria to plan and implement properly. Co-
      ordination  of this type  will  take  advantage  of  the  expertise
      available in the OWP&S so as to develop the criteria as efficiently
      as possible.
PRODUCT:
      A set of wet-weather  flow criteria,  for use in planning controls
      and evaluating their effectiveness.
SCHEDULE:
      It is anticipated that criteria will be developed  by January 1980
      (so the prototype projects can use them in planning).
RESOURCE REQUIREMENTS;

      Approximately 60 person-days will  be needed by Headquarters person-
      nel and/or the  consultant  team to develop  this  coordination, in
      addition to the time required by OWP&S personnel.
                                            Travel

      Headquarters            .23              0

      Regional                	0              0

                                               0
                                 39

-------
WORK ELEMENT 4b - COORDINATE WITH OFFICE  OF WATER  PROGRAMS OPERATION
METHOD:
      Coordination will be developed between the NURP and the Office of
      Water Programs Operation, either by an inter-division agreement or
      by one person from the Nationwide Urban Runoff Program acting as
      liaison. This coordination is  necessary in order that information
      gathered from the  "Needs Survey" maybe  used in the program, and so
      that Combined Sewer program's Step-One grants (in prototype project
      areas) can be jointly developed with the NURP.
PRODUCT:
      A working relationship between the NURP and the Office of Water Pro-
      grams Operation to ensure that efforts are not duplicated and that
      relevant information in both of f ices is used to gain maximum output.
SCHEDULE:
      This coordination will begin in October  1973 and  will continue
      throughout the duration of the program.
RESOURCE REQUIREMENTS;

      An estimated 35 person-days effort will be expended by Nationwide
      Urban Runoff Program personnel, plus effort by the Of f ice of Water
      Programs Operation. Coordination will continue throughout the pro-
      gram.
                               P-Yr          Travel

       Headquarters            .15              0

       Regional                	0             	

                               .15              0
                                 40

-------
WORK ELEMENT 4c - COORDINATE WITH OFFICE OF TOXIC SUBSTANCES
METHOD:
      Some of the problem constituents of urban runoff are toxic (e.g.,
      heavy metals, pesticides). Some  will be monitored in the Prototype
      Projects.  Coordination with  the Office of Toxic Substances will
      be necessary  to  prevent  duplication of  efforts and  to  benefit
      from past research efforts by  OTS. Coordination will take place
      either by NURP personnel   acting as a point  of  contact or  by an
      agreement between  the two offices.
PRODUCT:
      A working relationship with  the Of f ice of Toxic Substances to gain
      input from them and to relay information to them.
SCHEDULE:
      The initial coordination must take place by January 1979, and co-
      ordination between the offices will continue throughout the program.
RESOURCE REQUIREMENTS;

      An estimated 40 person-days effort will be needed initially by Head-
      quarters and/or  the  consultant  team  to develop the required re-
      lationship.  Additional  time will be  required to  continue  this
      coordination.
                              P-Yr          Travel

      Headquarters            .17              0

      Regional                	0              0

                              .17              0
                                 41

-------
WORK ELEMENT 4d - COORDINATE WITH OFFICE OF ENFORCEMENT
METHOD:
      Coordination between the NURP and  the Office  of Enforcement  is
      necessary to ensure that appropriate permits (e.g.,  General Per-
      mits or NPDES) will be prepared. The information gathered in the
      NURP will be useful to  the  Office of Enforcement,   but  the NURP
      will also benefit  from  relevant  information  on the Prototype Proj-
      ect study areas. This coordination  will come  about  by using one
      NURP contact person or by an agreement between the offices to trans-
      mit information.
PRODUCT:
      Cooperation between the two offices that will minimize duplication
      of effort  and  ensure  that  resources  are  used  to  their maximum
      extent.
SCHEDULE:
      Information collection will be initiated on respective prototype
      areas in October 1978. Data collected by the Nationwide Urban Runoff
      Program, which is meaningful to the Office of Enforcement (or vice
      versa), will be transmitted  throughout  the duration of  the program.
RESOURCE REQUIREMENTS;

      Initially, approximately 20 person-days will be required by NURP
      personnel to gather any information already available and to set
      up the coordination program.  Time will be needed throughout the
      program to continue this coordination.
                              P-Yr          Travel

      Headquarters            .11             0

      Regional                	0             0

                              .11        '     0
                                 42

-------
WORK ELEMENT 4e - COORDINATE WITH OFFICE OF SOLID WASTE
METHOD:
      The Best Management Practices implemented in the Prototype Project
      areas will generate residuals, causing a need for adequate disposal.
      Accordingly,  solid  waste management  plans must  recognize  this
      need.   The coordination  needed  between  NURP and OSW will be de-
      veloped either through a NURP point of contact or by an inter-office
      agreement.
PRODUCT:
      An inter-division coordination to insure that the efforts of the
      NURP are not hindering the effect of the other existing programs
      within the Agency.
SCHEDULE:
      The element should be initiated by the time the initial projects
      are underway and will continue until the final projects are com-
      pleted.
RESOURCE REQUIREMENTS;

      An estimated 35 person-days  effort  will  be  needed  by Headquarters
      personnel to  develop  the coordination,  in addition to effort by
      Of fice of  Solid  Waste  personnel. Additional time will be required
      to continue the  coordination.
                              P-Yr          Travel

      Headquarters            .14             0

      Regional                	0             0

                              .14             0
                                 43

-------
WORK ELEMENT 4f - COORDINATE WITH  OFFICE  OF  RESEARCH  AND DEVELOPMENT
METHOD:
      Coordination with  the Of f ice of Research and  Development is neces-
      sary, so that when a need  for  research  is  identified  by  theNURP,
      OR&D can respond.  Pertinent information on study findings  and gaps
      will be relayed by a NURP contact person.
PRODUCT:
      An inter-division agreement whereby information gathered from the
      NURP is transmitted to OR&D and identified needs are met.
SCHEDULE:
      This element will  be initiated after the Prototype Projects are well
      underway (and needs are identified).  Coordination will continue
      until all projects are completed (possibly thereafter).
RESOURCE REQUIREMENTS:

      An estimated 35 person-days effort by NURP personnel will be re-
      quired to  develop  the coordination.  Coordination must  continue
      throughout the duration of the projects.
                              P-Yr          Travel

      Headquarters            .14             0

      Regional                	0             0

                              .14             0
                                 44

-------
WORK ELEMENT 4g -  COORDINATE WITH  OFFICE OF AIR,  NOISE, AND RADIATION
METHOD:
      Coordination with air quality programs will be effected by assign-
      ing a NURP staff person as intra-agency coordinator. Because the
      sources  of  urban pollution are clearly related to air pollution
      (air being a  major  source),  information needs  to  be exchanged
      regarding the  magnitudes  of source and potential  reduction through
      mandates and controls.
PRODUCT:
      Exchange of information.
SCHEDULE:
      This element has been initiated informally. The process will  be for-
      malized  by  January  1979  and continued  throughout  the  program.
RESOURCE REQUIREMENTS:

      Coordination time requirements for the duration of the program is ap-
      proximately 50 person-days and one trip per year to Research Triangle
      Park, North Carolina.
                              P-Yr          Travel

      Headquarters            .20           $ 500

      Regional                	0           	0

                              .20           $ 500
                                 45

-------
WORK ELEMENT 5a - DEVELOP PROTOTYPE PROJECT SELECTION CRITERIA
METHOD:
      A final  selection  criteria  guideline  document will be prepared,
      based on inputs from Work Elements  3b and 3c, (following an overall
      review of the state of  the art of urban runof f ).  These criteria will
      insure that program objectives will be met (including nationwide
      representation and the solution of actual water quality problems).
PRODUCT:
      A criteria guideline  document  to  be used in selecting the Prototype
      Projects.
SCHEDULE:
      This Work Element  will be  initiated  in March  1978  and completed
      by July 1978.
RESOURCE REQUIREMENTS;

      Completion of this Work Element will require two person-weeks of
      Headquarters effort and assistance from consultants, in addition
      to the  time  and  travel  requirements  of Work  Element  3c.
                             P-Yr           Travel

      Headquarters            .02              0

      Regional                	0              0

                              .02              0
                                46

-------
WORK ELEMENT 5b - SUPPORT REGIONS' PROJECT SOLICITATION PROCESSES
METHOD:
      Upon request, support will be provided to areawide or state-level
      WQM  agencies  who wish to submit  proposed  Prototype Projects. Sup-
      port will  include  explanations of the overall program goals and
      visits to the project sites or agency offices.
PRODUCT:
      A list  of  those  potential  Prototype  Projects  supported  by the
      respective Regions.
SCHEDULE:
      This Work Element will  begin  July  1978  and  continue  until  all
      Prototype Projects have been selected (probably around September
      1979).
RESOURCE REQUIREMENTS;

      Resources required for  this  Work Element are estimated to be 45
      person-days for the Headquarters team (approximately one day for
      each potential project), 45 person-days for the consultant team,
      and 30 person-days for the Region. Considerable travel will be in-
      volved.
                                            Travel

      Headquarters             .2           $4000

      Regional                 .2_           	0

                               .4           $4000
                                47

-------
WORK ELEMENT 5c - PRE-SCREEN POTENTIAL GRANTEES
METHOD:
      The potential Prototype Project grantees will  be screened to avoid
      unwarranted  duplication  of effort and  to ensure  adequate dis-
      tribution with respect to geographic locale, receiving water type,
      and other factors. This will entail documenting each potential proj-
      ect to be sure it is in agreement with the matrix of problems to
      be solved and to meet the program's needs for information.
PRODUCT:
      A list of potential Prototype Projects which will meet the overall
      objectives of the program.
SCHEDULE:
      This Work Element will begin in July 1978 and continue until the
      selection  of  grantees has  been  completed  (i.e.,  approximately
      February 1979).
RESOURCE REQUIREMENTS:

      The Headquarters-level project manager will  be  responsible for in-
      itially screening  the  projects,  based upon information received
      from Work Elements 5b and 3c. No additional travel will  be involved.

                              P-Yr          Travel

      Headquarters             .1             0

      Regional                 _£             0

                               .1             0
                                 48

-------
WORK ELEMENT 5d - SUPPORT PREPARATION OF GRANT APPLICATIONS
METHOD:
      Support will  be provided to potential grantees who will be applying
      for Prototype Project  funds.  This support will range from review
      and comment on the draft submittals to consultation between Head-
      quarters and grant applicants.
PRODUCTS:
      Completed grant applications of potential Prototype Projects  to
      be used in the final selection process.  These applications will
      include commitments of local shares (of the cost of the project)
      in addition to Headquarters obligations.
SCHEDULE:
      This Work Element will begin after the  initial Prototype Projects
      have been selected and will continue through until the selection
      process has been completed.
RESOURCE REQUIREMENTS;

      Completion  of  this  Work Element will  require  approxiamtely  45
      person-days of Headquarters time, plus some consultant team support.
      Travel will also be needed.
                                            Travel

      Headquarters            .20           $3000

      Regional                .20           	0

                                            $3000
                                 49

-------
WORK ELEMENT 5e - PARTICIPATE IN FINAL SELECTION PROCESS
METHOD:
      Final selections  of Prototype  Projects  will  be  made  after the
      preliminary steps of the  selection process are complete (including
      pre-screening of potential grantees and preparation of grant ap-
      plications).  These  decisions  will  be  made in consultation with
      the respective Regional staffs.  The projects finally selected must
      meet, in aggregate,  the overall objectives of the program estab-
      lished in Task 1.
PRODUCTS:
      Approximately thirty Prototype Projects which will  help define the
      extent and nature of the urban runoff problem and help determine
      the approximate cost of solving the problem.
SCHEDULE:
      This Work Element will begin July 1978 with the submittal of initial
      pro ject work plans and will continue until the 30 pro jects have been
      selected.  The  final projects must be selected in time to leave
      considerable  time  for  compiling  and  assessing  the results and
      writing  the  final report to  Congress.  Therefore, most projects
      should be finished by the end of 1981.
RESOURCE REQUIREMENTS;

      Approximately 45 person-days will be required by both Regional and
      Headquarters staff, with some consultant team support.  Some travel
      will be involved.

                              P-Yr          Travel

      Headquarters            .2

      Regional                _._2

                              .4
                                 50

-------
WORK ELEMENT 6a - RECEIVE REQUESTS FOR TECHNICAL ASSISTANCE


METHOD;

      After completion  of Work Element  5d  (or  possibly in conjunction
      with it), requests for assistance in developing final work plans
      (for the Prototype Projects) will be received.  These requests may
      range from help with  initial  plan preparation  to  final review.
      Requests will  be  answered by  sending  teams of  consultants and
      Headquarters personnel to the grantee agencies when needed.
PRODUCT:
      A list of possible projects which need assistance in preparing work
      plans.
SCHEDULE:

      This Work Element will be initiated beginning with the first request
      received (probably in August 1978) and will continue until the work
      plans for all projects are .completed.


RESOURCE REQUIREMENTS:

      Completion of this Work Element will require some time from both
      Headquarters and the consultant team. This element is preliminary
      to Work Elements 6c and 6d, and the bulk of the time required for
      Task 6 is detailed in those  elements.  Nevertheless,  approximately
      15 person-days effort will be required by Headquarters.
                              P-Yr          Travel

      Headquarters            .05             0

      Regional                	0             0

                              .05             0
                                  51

-------
WORK ELEMENT 6b - PREPARE MODEL WORK PLAN


METHOD:

      Using input from Work Elements 6c, 6d, and 6e, a model work plan
      will be developed.   The  model  can  be used to guide grantees who
      have not developed workable  plans  and  can be used  as a prototype of
      future programs.  The model will contain all the necessary elements
      originally identified, in addition to any elements found to be lack-
      ing after reviewing submitted work plans.


PRODUCT;

      A model work plan  containing elements  necessary for the  project to
      be implemented.


SCHEDULE:

      The model work plan will need to be developed by mid-September 1978.
RESOURCE REQUIREMENTS;

      Approximately 15 person-days will be  needed by Headquarters  and the
      consultant team to develop the work plan. No travel will be involved.
                              P-Yr          Travel

      Headquarters            .06              0

      Regional                	0              0

                              .06              0
                                 52

-------
WORK ELEMENT 6c - REVIEW INITIAL WORK PLAN DRAFTS
METHOD:
      After initial work  plans  are  received  from  each  Prototype Project
      grantee, teams of Headquarters personnel and members of the con-
      sultant team  will review them to insure that they meet requirements
      of the "Proposed Work Plan Content" guidelines and reflect a quality
      planning effort.
PRODUCT:
      A working base for grantees to expand on.
SCHEDULE:
      Review will begin with  the initial submission of plans (August 1978)
      and continue until  each project  has  a  sound  work  plan (probably
      about May 1979).
RESOURCE REQUIREMENTS;

      An estimated 30 person-days  effort will  be  needed  by Headquarters
      and the consultant team to review the initial work plans. Travel will
      be involved.
                              P-Yr          Travel

      Headquarters            .11           $4500

      Regional                .11           	0

                              .22           $4500
                                 53

-------
WORK ELEMENT 6d - PROVIDE COMMENTS AND GUIDANCE FOR REVISING AND
                  COMPLETING FINAL WORK PLANS
METHOD:
      After completion of Work Element 6c, it is anticipated that work
      will continue in  the  Prototype  Project areas.  Comments will be
      made by Headquarters and the consultant team to assist  the Prototype
      Project agencies in developing sound, final work plans. The com-
      ments will take into consideration the  status of  the initial work
      plan and the amount of work being done on the  pro ject at that time.
PRODUCTS:
      Final work plans which are consistent with program guidelines and
      which are able to yield quality results.
SCHEDULE:
      This Work Element will be completed by May 1979, to provide time
      for developing work plans and completing  the Prototype Projects
      by August 1981.
RESOURCE REQUIREMENTS;

      Approximately 30  person-days will  be  required  by the Headquarters
      team.
                                            Travel

      Headquarters             .11            0

      Regional                	0            0

                               .11            0
                                 54

-------
WORK ELEMENTS 6e -  MEET WITH REGIONS,  STATES,  AND AREAWIDE AND LOCAL
                    WQM AGENCY REPRESENTATIVES AS REQUIRED
METHOD:
      This Work Element will  be on-going throughout  Work Elements 6c and
      6d. However, after  the final work plans are developed, some co-
      ordination may be required  to  assure  quality  results  and adherence
      to the work plan.  Visits to the Regional offices or the project
      areas may be necessary.
PRODUCTS:
      Output from this Work Element will be incorporated into Work Ele-
      ments 6d and 6a.  Final work plans will result  from these meetings.
SCHEDULE:
      Meetings will  be initiated during revision of final work plans and
      will probably be held as needed until the final  Prototype Projects
      are completed in August 1981.
RESOURCE REQUIREMENTS;

      Assistance will be provided  as  needed;  up  to  40  person-days  by
      Headquarters  and  the  consultant team may  be required, plus cor-
      responding travel.
                              P-Yr          Travel

      Headquarters            .15           $5,000

      Regional                .15           	0

                              .30           $5,000
                                 55

-------
WORK ELEMENT 7a - PROVIDE ON-SITE TECHNICAL ASSISTANCE TO PROJECTS
METHOD:
      Technical assistance will be provided in the form of on-site help
      by Headquarters and the consultant team (upon request by Regions
      and grantees). This assistance may range from  assuring the quality
      of data collection to helping with  progress reports. This assist-
      ance will be provided to  assure that project officers and grantees
      do not inadvertently waste time  researching areas where expertise
      may  be available  through Headquarters.
PRODUCT:
      A system whereby project officers may solicit Headquarters to obtain
      technical assistance.
SCHEDULE:
      This element will be initiated beginning in August 1978 and will con-
      tinue until the last request for assistance is made (probably around
      September 1981).
RESOURCE REQUIREMENTS;

      Resources needed for this Work Element will  depend on the  amount of
      assistance needed by  the  projects.   The maximum effort is esti-
      mated to be 90 person-days.
                              P-Yr          Travel

      Headquarters            .34           $2,500

      Regional                .34           	0

                              .68           $2,500
                                 56

-------
WORK ELEMENT 7b - ESTABLISH DATA COLLECTION QUALITY ASSURANCE PROTOCOL


METHOD:

      A quality assurance protocol for  data  collection will  be  devel-
      oped in the form of guidelines which will specify techniques to be
      used (both in the lab  and  the field), along with the costs of these
      techniques.  The purpose of the guidelines is to assure comparability
      in the emerging information base.
PRODUCT:
      A quality assurance protocol to insure that credible results will be
      obtained from each of the Prototype Projects.
SCHEDULE:
      This Work Element will be completed by August 1978.
RESOURCE REQUIREMENTS:

      It is estimated that 10 person-days will be required of Headquarters
      and the consultant team.
                              P-Yr          Travel

      Headquarters         x    .04             0

      Regional                 	0             0

                               .04             0
                                 57

-------
WORK ELEMENT 7c -  PROVIDE TRAINING FOR REGIONS,  STATES,  AND AREAWIDE
                   AND LOCAL WQM AGENCIES
METHOD:
      Training  sessions will be arranged  for  interested  participants,
      upon request from the  Regions.This training may be in the form
      of consultations, workshops, brief seminars, or other appropriate
      training aids. The  subjects  to be  covered  will vary  depending
      on need.
PRODUCT:
      A program  through  which Regional,  State and  areawide personnel
      may receive training in a variety of subject areas.
SCHEDULE:
      This Work Element will be initiated beginning in August 1978 and
      will continue throughout the program.
RESOURCE REQUIREMENTS;

      It is difficult to estimate time required for this resource. Al-
      though it is not known how many  sessions  will  be  required, the es-
      timated maximum effort  will be  on  the order of  30  person-days
      for the program manager and/or the consultant team.
                              P-Yr          Travel

      Headquarters            .11           $3,000

      Regional                .11           	0

                              .22           $3,000
                                  58

-------
WORK ELEMENTS  7d  -  PROVIDE  PROJECT MANAGEMENT ASSISTANCE TO REGIONAL
                   PROJECT OFFICERS
METHOD:
      Management assistance will be provided to  project  officers (upon
      request) to help in directing the Prototype Projects. This assist-
      ance may range from suggestions by telephone to preparing specific
      management guidelines for some projects.
PRODUCT:
      Management assistance to help direct Prototype Projects.
SCHEDULE:
      Assistance will be available beginning  in August 1978 and continue
      throughout the program.
RESOURCE REQUIREMENTS:

      A maximum of .20 person-years  effort  by Headquarters is estimated.


                              P-Yr          Travel

      Headquarters             .20             0

      Regional                 .15             0

                               .35             0
                                59

-------
WORK ELEMENT 7e - INITIATE A PUBLIC PARTICIPATION PROGRAM
METHOD:
PRODUCT:
SCHEDULE:
There are  three major  items necessary  for  the  NURP
 public  participation  program.  These  three items  are:
 dissemination  of information,  advisory groups and im-
 plementation.  The  dissemination  of  information  will
 involve keeping  all interested parties in touch  with
 the  program by using various media forms (news  articles,
 slide shows, speakers,  tours of sites of  evaluation).
 The  advisory groups will be composed of individuals that
 can  provide  support for  the  eventuality of decision
 making  as  the project  moves  toward completion.  This
 group will be informed and have a say on what is being
 done.   The  advisory  group will also  be  the  principal
 participants in the third function. The  group will be
 the  vehicle to provide responses to  various alternative
 control strategies in those areas where implementation
 of stormwater  controls  will  be needed.

 A public participation program involving concerned par-
 ties at various levels to  facilitate  implementation
 of the  program in  future  years.

 Initial coordination  between Program Management Branch
 and  the Urban  Runoff  Program staff  will  take place in
 August  1978. This coordination will continue heavily un-
 til  all the  work  plans have been developed  and the
 mechanisms  for implementing the public  participation
 program are in place. The coordination  will continue
 at a slower pace throughout the duration of the program
 with ongoing monitoring and  evaluation of public  par-
 ticipation in  project areas.
RESOURCE REQUIREMENTS;
               Approximately 60 person-days will be needed at the Head-
               quarters level with a large  part of the effort being
               expended in the early development of the program. Some
               travel may be involved.
               Headquarters:

               Regions:
                  P-Yr

                   .25

                   .25
                                  .50
Travel

$ 500

$1000

$1500

-------
WORK ELEMENT 8a - REVIEW AND COMMENT ON PROGRESS REPORTS
METHOD:
      Headquarters and  the consultant team will review quarterly reports
      from the Prototype Projects and will recommend any necessary adjust-
      ments to their month-to-month operation.  Comments  and recommenda-
      tions will be sent to the  project officers. Annual reports will be
      used to  evaluate each  project, regarding the  following year's
      funding.
PRODUCTS:
      Comments and recommendations to guide the project officers.
SCHEDULE:
      This Work Element will  begin in October 1978 and will continue until
      approximately September 1981.
RESOURCE REQUIREMENTS;

      Approximately 360 person-days will be needed by Headquarters and the
      consultant team (assuming  atypical Prototype Project,  which would
      last on  the  order  of  three  years).  Regional  staff  will prepare
      the reports and make recommended changes. Travel requirements are
      included under Work Element 8b.
                              P-Yr          Travel

      Headquarters             1.5             0

      Regional                 1.5             0

                               3.0             0
                                 60

-------
WORK ELEMENTS 8b - ATTEND PROJECT STATUS BRIEFINGS
METHOD:
      Meetings will  be  held  so  the project officers may  brief Head-
      quarters and  the consultant team on the Prototype Pro jects '  status,
      the problems encountered,  the  problem-solving approaches  taken,
      etc. The information gained from these meetings will  be used  in
      Work Elements 8c,  8d, and 8e.
PRODUCT:
      Information  to  be used  in  the quarterly newsletters and bulle-
      tins.
SCHEDULE:
      This Work Element will  begin in August  1978 and will continue until
      the pro jects are near completion (probably around  September 1981).
RESOURCE REQUIREMENTS;
                                                         /
      It is anticipated that each project will require at least  two brief-
      ings throughout its duration. This will amount to 60 person-days
      effort by  Headquarters  and the consultant team.  Travel  will be
      required.
                              P-Yr         Travel

      Headquarters             .2          $4,500

      Regional                 .3          	0

                               .5          $4,500
                                 61

-------
WORK ELEMENT 8c - PREPARE AND DISTRIBUTE PROGRAM NEWSLETTERS
METHOD:
      A quarterly newsletter will be prepared (using information gathered
      from Work Elements 8a and  8b) and issued to all NURP participants to
      keep them informed on the status of  the Prototype Projects. If any
      innovative  approaches  are  taken or any  breakthroughs are made,
      special bulletins will be issued to all participants.
PRODUCTS:
      A quarterly newsletter and bulletins on latest developments.
SCHEDULE:
      The first newsletter will be distributed shortly after the first
      quarterly reports are reviewed  (approximately November 1978). News-
      letters will continue until  the last quarterly reports are reviewed
      in September 1981.
RESOURCE REQUIREMENTS:

      This Work Element will require approximately 30 person-days effort
      by Headquarters  (it  is anticipated  that  this work  can  be accom-
      plished by one person in  the  Communications Section).  No travel
      is involved.
                                            Travel

      Headquarters              .1             0

      Regional                   0             0
                                  62

-------
WORK ELEMENT 8d - PROVIDE INFORMATION CLEARINGHOUSE FUNCTION
METHOD:
      Participating  agencies  will  be  encouraged to  submit  questions
      related to  their  Prototype  Projects  or  the state-of-the-art of
      urban runoff to the NURP. Files will be kept on projects nation-
      wide as well as any new  developments  within the program. Infor-
      mation will be transferred through training sessions, workshops,
      seminars, conferences, professional journals, etc.
PRODUCTS:

      Timely information in response to requests.


SCHEDULE:

      This Work Element  will  be  initiated  in August 1978 and continue
      throughout the program.


RESOURCE REQUIREMENTS:

      NURP personnel  will  require  an estimated  50  person-days effort
      to answer questions (or  research answers), set up workshops, etc.
      Some travel will be required.


                              P-Yr          Travel

      Headquarters               .3

      Regional                 	0

                                 .3
                                63

-------
WORK ELEMENT 8e - MAINTAIN PROTOTYPE PROJECT STATUS FILE
METHOD:
      Information  gained  from Work  Elements  8a,  8b,  and  8c  will be
      filed in an orderly system, with separate  files  for each Proto-
      type Project. These files will be kept current, so the status of
      each project can be determined at any time.
PRODUCT:
      An easily accessible  filing  system  to  be  used  to  determine the
      status of each Prototype Project.
SCHEDULE:
      The file will be established in August 1978 and updated throughout
      the project.
RESOURCE REQUIREMENTS;

      The filing of projects will be an ongoing process, requiring only
      the effort to place notes and reports in the proper file.
                              P-Yr          Travel

      Headquarters              .1             0

      Regional                 	0             0

                                .1             0
                                 64

-------
WORK ELEMENT 8f  - ESTABLISH PROGRAM STEERING COMMITTEE:  CHAIR MEETINGS
METHOD:
      A steering committee will be established, composed of members from
      EPA Headquarters, Regions, the Of fice  of Research and Development,
      and statewide, areawide, and local WQM agencies. It will  be chaired
      by Headquarters for the purpose of providing guidance and direction
      to the program.
PRODUCTS:
      None.
SCHEDULE:
      The committee will be formed in September 1978 and will be main-
      tained throughout the program.
RESOURCE REQUIREMENTS;

      Required time may vary  depending on the needs.  It  is estimated that
      a maximum of 15 person-days will be required for Headquarters or
      Regional personnel.
                              P-Yr          Travel

      Headquarters             .05          $3,000

      Regional                 .05          $1,000

                               .10          $4,000
                                  65

-------
WORK ELEMENT 8g - PROVIDE PROGRAM POLICY AND GUIDANCE
METHOD:
      Other Branches within the  Water Planning  Division will provide
      guidance on  financial,  institutional  and legal  issues  to avoid
      duplication of research.
PRODUCTS:
      Program  policy  and  guidance  (especially  guidance  on financial
      alternatives for implementation).
SCHEDULE;

      This Work  Element will  be  initiated  in August  1978  and  will con-
      tinue throughout the program.


RESOURCE REQUIREMENTS;

      An estimated 100 person-days  effort will be required for NURP per-
      sonnel to relay questions and obtain answers.
                              P-Yr          Travel

      Headquarters              .4             0

      Regional                 	0             0

                                .4             0
                                  66

-------
WORK ELEMENT 9a - ANALYZE THE INFORMATION DEVELOPED IN PRECEDING TASKS TO
                IDENTIFY AND ASSESS MAJOR TRENDS AND CAUSE AND EFFECT
                RELATIONSHIPS
METHOD:
      This Work Element is  necessary to gain an accurate perspective of
      the degree to which urban runoff is a problem of national impor-
      tance. The  analysis will  require a thorough examination of infor-
      mation obtained in previous tasks to determine the need for policy
      changes or reconsideration.  Major  trends and  cause and effect
      relationships will be identified using data  gathered in Prototype
      Projects.
PRODUCT:
      An analysis on which to  base  conclusions  about  the national im-
      portance of urban runoff.
SCHEDULE:
      This Work Element  will  be  initiated  November 1978 and completed
      in late 1982.
RESOURCE REQUIREMENTS;

      Considerable  time  will  be  needed  by  the program manager and the
      consultant team  to thoroughly  examine  any information gathered
      from the projects to perform a proper analysis.
                              P-Yr          Travel

      Headquarters             1.0             0

      Regional                 	0             0

                               1.0             0
                                 67

-------
WORK ELEMENT 9b - ANALYZE AVAILABLE INFORMATION TO DETERMINE ITS
                  RELATIONSHIP TO POLICY ISSUES (INCLUDING LEGAL,
                  INSTITUTIONAL, AND FINANCIAL IMPLICATIONS)
METHOD:
      Policy  issues  must be considered if control alternatives are to
      be required because  such  issues have  legal, institutional, and
      financial implications. The analysis of both established and po-
      tential  new  policies  should be  coordinated  with the governments
      that will issue them (i.e., regions, State  and  local  agencies).
PRODUCT:
      An information base by which a relationship between policies needed
      to be implemented and possibility of implementation can be deter-
      mined.
SCHEDULE:
      This Work Element will begin  in  January  1981  and will continue
      until the relationships between available information and policy
      issues have been determined (approximately in January 1982).
RESOURCE REQUIREMENTS:

      Considerable time will be needed  by both Headquarters and the con-
      sultant team  to  gather information on existing public policy in
      local areas.
                              P-Yr          Travel

      Headquarters              .5             0

      Regional                  .3             0

                                .8             0
                                 68

-------
WORK ELEMENT 9c - ASSESS THE PRACTICAL APPLICABILITY OF EFFECTIVE CONTROL
                  MEASURES
METHOD:
      To determine the practical applicability of effective  control meas-
      ures, costs and the effectiveness of various candidate control meas-
      ures will be assessed.  Monetary,  social,  and  environmental costs
      will be examined.The effectiveness of measures will  be determined
      by  how well they  practically  reduce impacts on water quality.
PRODUCTS:
      Cost-effectiveness curves for candidate control measures.
SCHEDULE:
      This Work Element will  be  initiated in September 1981 and will con-
      tinue until any valid conclusions are drawn to be included in the
      final report.
RESOURCE REQUIREMENTS;

      Considerable time  will  be  needed  to determine costs and benefits.
      Analysis will be done by the program manager and the consultant team.
                                            Travel

      Headquarters              .9             0

      Regional                 .08             0

                               .98             0
                                 69

-------
WORK ELEMENT 9d - ASSESS PUBLIC SUPPORT FOR IMPLEMENTING URBAN RUNOFF
                  CONTROLS

METHOD;         Information from ongoing public participation efforts
               associated with  this prototype project will be assessed
               by staff members of the  Water  Planning Division from
               reports prepared by Regional public involvement staff.
               Methods of obtaining the information will include:  con-
               sultation with the public, at meetings, written corres-
               pondence, phone communication, etc.  Public perspective
               and potential support for controlling urban runoff is
               what needs to be understood.

PRODUCT:       The development of management practices for controlling
               urban runoff that will reflect the values of the affected
               affected public and have its support.

SCHEDULE;      This work element will be initiated November 1978 and
               contine  through the  end of the  program.  This  is  a
               continuation of work element 7e.

RESOURCE REQUIREMENTS;

               Most of the manpower will  be on reviewing what comes from
               the work element 7e  effort.  20 person-days  will  be
               needed.

                                 P-Yr          Travel

               Headquarters:      .1             0

               Regions:            0             0

                                   0             0

-------
WORK ELEMENT lOa - REVIEW QUARTERLY AND ANNUAL 208 REPORTS
METHOD:
      Submitted Prototype Project reports (quarterly  and annually), will
      be re-reviewed from a nationwide perspective.  Information gained
      from this review  includes  cause  and effect data and control effec-
      tiveness and costs.  This element is essential  to the organization
      and completion of the remaining Work Elements.
PRODUCT:
      A general knowledge of the information contained  in the summary
      reports.
SCHEDULE:
      This Work Element will be initiated in October 1979.  The actual
      review will continue through December 1981, but the reports will
      be used as references until the final report is written.
RESOURCE REQUIREMENTS:

      Time will be needed  by both the program manager and the consultant
      team in addition to the time covered in element 7a.
                              P-Yr          Travel

      Headquarters             1.0             0

      Regional                 	0             0

                               1.0             0
                                  70

-------
WORK ELEMENT lOb - SUMMARIZE  CAUSE AND EFFECT RELATIONSHIPS,  RESOURCE
                   NEEDS, AND COST EFFECTIVENESS OF CONTROL ALTERNATIVES
METHOD:
      At the end of each year, summary reports will be written using in-
      formation gathered  from Work Element lOa. These  reports will con-
      tain information on resources and money involved, information on
      cause-and-effeet relationships, and estimates of control effective-
      ness and costs. These annual reports will be used in  assessing the
      overall NURP accomplishments.
PRODUCTS:
      Annual NURP summary reports.
SCHEDULE:
      This Work Element will be initiated inOctober 1979 and will con-
      tinue until September 1981, when the final annual reports will be
      reviewed.
RESOURCE REQUIREMENTS;

      The major part of the time required for this Work Element is covered
      in Element 8a.  However, Work Element  8a's purpose is to monitor the
      projects, whereas this  element  focuses  on summarizing the reports
      submitted. Therefore, additional  time is allotted  to summarize any
      information that was not obtained in Work Element 8a.
                              P-Yr          Travel

      Headquarters             2.0             0

      Regional                 	0             0

                               2.0             0
                                 71

-------
WORK ELEMENT lOc - SUMMARIZE INSTITUTIONAL, LEGAL, AND FINANCIAL ASPECTS
METHOD:
      Summary  reports  will be  prepared  using  applicable information
      gained  in Work Element 9b and any new information  found  in the
      progress reports.  These summaries will contain all institutional,
      legal, and financial aspects of the Prototype Projects, to be used
      in assessing the  probability of  selected  controls being implemen-
      ted.
PRODUCTS:
      Annual NURP summary reports.
SCHEDULE:
      This element will be initiated in October 1979 and will continue
      until September 1981, when the final annual reports are being re-
      viewed.
RESOURCE REQUIREMENTS:

      In addition to time required in Work Element 9b, time must be al-
      located to summarize any areas not covered in that  element.  This
      time will be required of both the program manager and the consul-
      tant team.
                                            Travel

      Headquarters              .5             0

      Regional                   0             0
                                 72

-------
WORK ELEMENT  lOd  - DOCUMENT  URBAN RUNOFF PROBLEMS,  EFFECTIVENESS OF
                    CONTROLS,  AND COST OF IMPLEMENTATION
METHOD:
      This element is essentially a summary of what the Prototype Proj-
      ects have accomplished nationwide. Using  information  in this Work
      Element, a nationwide control program  can be developed. Documenting
      the problems will  include  their geographical location and their
      severity.  Control  effectiveness  and  costs  will  be determined by
      analyzing cost-benefit figures in addition to all institutional,
      legal and financial aspects involved.
PRODUCT:
      Nationwide summary report to be used  in developing the nationwide
      urban runoff control program.
SCHEDULE:
      This Work Element will be initiated after Work  Elements  lOb and
      lOc are completed  (possibly concurrently) and will be completed by
      December 1981.
RESOURCE REQUIREMENTS:
      The element will  be  accomplished  by  the program manager and the
      consultant team.
                              P-Yr          Travel

      Headquarters             1.5             0

      Regional                 	0             0

                               1.5             0
                                73

-------
WORK ELEMENT lOe - SYNTHESIZE A NATIONWIDE URBAN RUNOFF CONTROL PROGRAM
METHOD:
      Based on information obtained and lessons learned from the NURP,
      a nationwide urban runoff control program will be synthesized. This
      program will be developed  using data from Work Element lOd, taking
      into account transferability of data and any aspects not considered
      in the previous Work Elements. The  nationwide program will include
      problems to be solved and costs associated with solutions.
PRODUCT:
      A Nationwide Urban Runoff Control Program.
SCHEDULE:
      This Work Element will  be initiated in December 1981 and completed
      in December 1982.
RESOURCE REQUIREMENTS;

      Time will be required of the program manager and the consultant team.


                              P-Yr          Travel


      Headquarters             .70            0

      Regional                 	0            0

                               .70            0
                                 74

-------
WORK ELEMENT lOf - PREPARE REPORT TO CONGRESS
METHOD:
      The final report  to Congress will  be a summary of the whole program:
      its objectives, how it accomplished its objectives, data gathered,
      documentation of problems,  effectiveness  of controls, cost of im-
      plementation,  and a  recommended  nationwide urban  runoff  control
      program.
PRODUCT:
      Report to Congress,
SCHEDULE:
      Information gathering for this report will begin in August 1979.
      Report writing will be initiated  in early December 1982, to be fin-
      ished in mid-1983.
RESOURCE REQUIREMENTS:

      In addition to the time required to organize all the information
      in the previous elements of  this task, additional time must be al-
      located to do the actual writing of the report. This element will
      be accomplished by  the  program manager and the consultant team.
                              P-Yr          Travel

      Headquarters             .75            0

      Regional                 	0            0

                               .75            0
                                 75

-------