EXECUTIVE PANEL REPORT TO THE ADMINISTRATOR

                     ON

  THE PROPOSED MONTGOMERY COUNTY ADVANCED

        WASTEWATER TREATMENT PLANT
      ADMINISTRATOR'S EXECUTIVE PANEL

             Paul A. Brands
             John Rhett
             Daniel J. Snyder,III
    U.S. ENVIRONMENTAL PROTECTION AGENCY

          WASHINGTON, D.C.  20460

               AUGUST 6, 1976

-------
       EXECUTIVE PANEL REPORT TO THE ADMINISTRATOR
                            ON
       .  THE PROPOSED MONTGOMERY COUNTY ADVANCED
               WASTEWATER TREATMENT PLANT
INTRODUCTION

     On March 19, 1976, the State of Maryland transmitted
to EPA a construction grant application for an advanced
wastewater treatment (AWT) facility proposed for construction
by Montgomery County in the vicinity of Dickerson, Maryland.
Though -EPA has been involved with this project during the
last few years, increased public concern about potential
contamination of drinking water supplies, and substantial
changes in both the costs associated with building the plant
and the flow projections upon which it is justified, raise
sufficient concern to warrant a detailed EPA review at this
time. .This is particularly true with respect to the legisla-
tively mandated cost-effectiveness review requirements.

     Because of the complex, controversial nature of the
proposed facility, the Administrator recently formed a
special Executive Panel consisting of Paul A. Brands, Deputy
Assistant Administrator for. Planning and Evaluation; John T.
Rhett, Deputy Assistant Administrator for Water Program
Operations; and Daniel J. Snyder III, Regional Administrator,
EPA Region III, to review the proposed project.

     The Panel members were instructed to analyze and assess
all major issues relating to the grant application, to
prepare an options paper for the Administrator and to recom-
mend a specific course of action.  In response to this
charge, this report contains a summary'of the assessments of
the major issues and a series of optional courses of action.
The Panel members will not recommend a decision on a specific
course of action to the Administrator until after the Panel
has had an opportunity to obtain additional information and
comments at the public meeting scheduled for August 11,
1976.

RECENT HISTORY OF THIS PROJECT

     A number of important events have occurred since EPA -
received the grant application in March.  On April 7, 1976,
EPA issued a draft National Environmental Policy Act (NEPA)
review of the proposed project subtitled "Tentative, Pre-
liminary Document for Discussion and Comment."  Such reviews
are required for all wastewater treatment plants involving
Federal cost-sharing- participation.  The review raised

-------
                            -2-
several concerns about the Dickerson proposal and presented
cost data which indicated that at least one possible alter-
native site/ located in the vicinity of Piscataway in Prince
Georges County, appeared substantially more cost-effective
than the Dickerson proposal.

     On May 14, 1976, EPA received a report entitled "Maryland
Response to the Tentative U.S. Environmental Protection
Agency Report on the Dickerson Advanced .Wastewater Treatment
Plant."  The Response rejected the cost comparisons in EPA's
draft NEPA review, and presented cost data showing that the
cost of an alternative treatment scheme at Dickerson
(resulting in a lower level of treatment than originally
proposed)  would approximately equal the cost of the Piscataway
alternative.  In addition, the Response argued that the
Piscataway alternative was socially and politically unaccept-
able to Prince Georges County, and that Dickerson was the
only option which could be implemented soon enough to
provide the treatment capacity desired by the County to end
the sewer moratoriums imposed by the Maryland Department of
Health and Mental Hygiene.

     To narrow the areas of controversy and facilitate
an exchange of information with respect to the major issues
involved in the proposed wastewater treatment project, EPA
staff have'held a series of meetings with the staffs of many
of the impacted governmental bodies — the State of Maryland,
Montgomery County, Prince Georges County and the Washington
Suburban Sanitary Commission.

MAJOR ISSUES RELATED -TO THE PROPOSED PLANT

     The significant issues raised in the review of the
Dickerson proposal have been examined by the Panel in con-
siderable detail.  The following pages summarize these
issues and the Panel's findings.

Population and Sewage Flow Projections

     The size and cost of a proposed wastewater treatment
plant is determined to a major extent by the population
projections for the area to be served by the facility.
Since the facility proposed for Dickerson was originally
planned to serve Montgomery County, the Panel began by
reviewing wastewater flows for the Montgomery County
service area.

-------
                            -3-
     This review included examination  of  the flow projec-
tions submitted by the applicant  in support of  the grant
application  as well as more  recent population projections
made by other local and regional  planning entities.1]
Through a careful analysis of available population projec-
tions, the Panel developed an independent estimate of  sewage
flow requirements»

     Estimates for Montgomery County sewage flows are  tied
to projections of the construction of  dwelling  units.  Since
last fall, the County Planning Board has  published a series
of growth scenarios, two of  which have received endorsement
from the County Council  (Table I).  The first of these is the
"intermediate" forecast which the county  feels  is an accurate
estimate of  growth in population  and construction over the
next 10 years.  However, for planning  purposes  the County has
adopted a higher "trend" projection.
                         TABLE  I

       MONTGOMERY COUNTY PLANNING BOARD ESTIMATES
              OF DWELLING UNIT  CONSTRUCTION
                    •(UNITS PER  YEAR)

                            1975-1980     1980-1985

Intermediate Forecast         4,000          6,000
Trend Forecast                6,400          7,600


     The presentation of two forecasts by the county has
posed a significant problem to  analysis of flows.  Sound
cost-effectiveness analysis argues  that the  "intermediate"
forecast rather than the "trend" should be used,since the
council appears to believe the  former estimate most accurately
represents expected future growth.

     In order to insure adequate treatment capacity, the
Panel has based its independent flow analysis on a forecast
of 6,000 new dwelling units per year over the projects
planning period.  This compares with the basis of the
applicant's estimate which is an average of  7,000 units per
year.


JJ Montgomery County Planning Board, Washington Metropolitan
  Council of Governments, and the National Planning Association,

-------
                            -4-
     The resulting projected sewage flows for Montgomery
County to the year 2000 are shown in Table II.  The assump-
tions upon which the projections are based are included in
Appendix A.

                         TABLE II

       ESTIMATES OF MONTGOMERY CODNTY SEWAGE FLOWS
             Applicant
                                               EPA
     Total               Treatment
     Sewered    Flow     Capacity
Year Population Estimate Need*	
             (million gallons/day)
                                    Total               Treatment
                                    Sewered    Flow     Capacity
                                    Population Estimate Need*
                                            (million gallons/day)
1975  515,700
73.5
                                     515,700
                                                70.0
                           9.5
                          22.5
                          34.9
                          47.2
                          59.8
*Total projected flow minus 76.6 mgd allocation at Blue
 Plains wastewater treatment plant; these figures do not
 include planned capacities of Montgomery County interm
 treatment facilities.
1980
1985
1990
1995
2000
587,200
664,746
735,996
807,246
878,496
86.1
99.1
111.5
123.8
136.4
578,563
630,054
688,872
748,804
808,437
78.9
86.8
94.9
102.7
111.7
                                                          2
                                                         10
                                                         18
                                                         26
                                                            3
                                                            2
                                                            3
                                                            1
                                                         35.1
     As outlined in the Response, the State and Montgomery
County now, however, are generally justifying the proposed
60 mgd capacity on the basis  of Dickerson being a regional
plant which would directly or indirectly service flows from
the District of Columbia and Virginia as well as Montgomery
County.  While there is some history suggesting that the
proposed plant at Dickerson would treat regional flows,
discussion of specific offers to provide permanent treatment
capacity to other jurisdictions is relatively new.  Because
no formal agreements have been consummated among the
regional jurisdictions as to what capacities they would be
willing to "buy" or "sell,"'it is not possible to assess
adequately the magnitude of potential regional flows that
would be serviced by the proposed Dickerson plant.

     The Applicant has recently offered 7 1/2 mgd of permanent
capacity to the District of Columbia.  The District has
indicated that it would accept such capacity if there would-
be no adverse water supply impacts and if treatment costs
were not greater than those of other alternatives.         ,

-------
                            -5-
     Even more recently, the Applicant has offered 10 mgd of
permanent capacity and 10 mgd of temporary capacity to
Virginia.  While Virginia has stated that it would not
"purchase" temporary treatment capacity/ it has indicated
that it would consider approving a permanent allocation of
capacity at Dickerson.  Montgomery County, however, has
offered capacity only to Fairfax County, whereas the State
of Virginia appears concerned about obtaining capacity .for
additional jurisdictions.

     Assessment of this issue indicates that a plant of
35 mgd capacity could be justified from a flow standpoint on
the basis of projected Montgomery County sewage flows.
However, should firm commitments of capacity utilization
(based upon reasonable flow projections) by Virginia and the
District similar to those that have been offered actually
be consummated, then a plant of 50-60 mgd capacity could be
justified from a flow standpoint.

Cost-Effectiveness

     The cost-effectiveness of five basic treatment plant
alternatives were examined by the Panel:

     o  Dickerson I —'a 60 mgd plant as proposed in the
        March 19 grant application.  This facility would
        provide nitrogen as well as phosphorous removal and
        would involve a 23-mile force main delivery system
        with five pumping stations.  This is the only
        alternative for which plans and specifications have
        been submitted.

     o  Dickerson II — a 60 mgd plant reflecting the design
        changes suggested by the State in their Response
        document.  This facility would provide phosphorous
        removal and nitrogen oxidation and would involve the
        same force main system as proposed under Dickerson I.

     o  Dickerson II - 35 mgd -- a smaller version of "Dicker-
        son II" sized to treat 35 mgd.

     o  Piscataway Alternative - 60 mgd — a 60 mgd expansion
        of Prince Georges County's proposed 30 mgd plant in
        the vicinity of the Piscataway plant, including the
        additional transmission costs necessary to deliver
        Montgomery County flows to the project site.  The
        plant would provide nitrogen oxidation treatment
        similar to the treatment now provided at the Blue
        Plains treatment plant.

-------
                            -6-

     o  Piscataway Alternative -  35 mgd — a  smaller version
        of  "Piscataway -  60 mgd"  sized to treat  35 mgd,
        including the additional  transmission costs  for
        Montgomery County flows.

     The cost  estimates for the Piscataway alternatives
 include the costs of constructing and operating  the  following
 related facilities:

     o  Enlargement of the proposed force main between Blue
        Plains and Piscataway.

     o  Construction of an additional 7 mgd of interim plant
        capacity in Montgomery County to serve county flows
        temporarily between 1981  and 1984.

     o  Operation and maintenance of all interim plants  (14.5
        mgd) for 3 years  from 1982 through 1984.

     o  Construction of relief sewers, pumping stations  and
        other  works to convey Montgomery County  flows to  the
        Potomac Interceptor sewer.

     o  Augmentation of Potomac Interceptor capacity by
        construction of retention facilities  when conveyance
        capacity is reached.

     In addition to the five treatment plant  alternatives
 examined in this analysis, other  alternatives such as varia-
 tions in the Darnestown proposal, a re-rating of Blue Plains,
 and  additional Dickerson  modifications were examined.  They
 were not examined in as much detail, however, either because
.of substantially higher project costs, potential impacts  on
 drinking water supplies,  insufficent data available  at this
 time, or other similar problems and limitations.  This does
 not  imply that other feasible alternatives do not exist.

     The present worth comparisons of the five alternatives
 examined in detail are displayed  in Table III.1J  A more
 detailed cost-effectiveness presentation is included in
 Appendix B.  The present  worth calculations are  in accordance
 with the requirements of  Appendix A of the Construction
 Grants Regulations.  Secondary costs or benefits (e.g.,
 potential loss of tax revenue at  the county level)  are not
 included in this comparison — they are discussed as separate
 issues.

JJ The present worth calculations involve laying out the
   expected annual flow of capital and O&M dollars and then
   discounting those dollar flows back to a base year (in
   this case 1980).  This approach reflects the  time-value of
   money.

-------
                            -7-


                        TABLE III

        PRESENT WORTH COMPARISON OF ALTERNATIVES

                   Capacity   Present Worth *
Alternative        (mgd)      (million dollars)	
                              Capital   O&M   Total

Dickerson I  "        60        $273    $108   $381
Dickerson II         60         247      90    337
Piscataway 60 mgd    60         154      82    236
Dickerson 11-35 mgd  35         175      67    242
Piscataway 35 mgd    35         103      65    168

*1980 present worth in 1975 dollars

     Table III indicates that the Dickerson alternatives
are substantially more cos.tly than the comparable capacity
of the Piscataway alternatives.  In the case of the 60 mgd
alternatives, the Piscataway plant would cost about $100
million less than Dickerson II — about 30-35 percent less.
Similarly, the difference for the 35 mgd alternatives is $75
million — about 30 percent less costly.

     The Maryland Response also presented a present worth
comparison between Dickerson II and "Piscataway - 60 mgd" .
The analysis in the Response concluded that there are
essentially no total cost differences between the two
alternatives.

     The principal reasons why there are wide cost differ-
ences between those two alternatives as calculated by the
Panel, while the Response estimates them to be about equally
costly, involve the following four factors:

     o  Interim capacity.  Based on the revised flow require-
        ments, less than 7 mgd rather than 14 mgd of additional
        interim plant capacity would be required to serve
        Montgomery County needs from 1981 to 1984 — thus
        reducing the Panel's cost estimates associated with
        Piscataway in comparison to the Response's estimates.

     o  Conveyance capacity.  The Panel's estimate includes
        lower costs to provide conveyance capacity due to '
        augmenting capacity of the Potomac Interceptor
        through construction of retention facilities rather
        than constructing a relief tunnel as provided in the
        Response estimate.

-------
                            -8-


     o  Virginia facilities.  Considering only Montgomery
        County flows, the Panel believes it inappropriate to
        include the costs of providing Virginia interim
        treatment facilities.  If the alternatives are
        assessed on a regional basis/ there is inadequate
        information to support cost estimates for interim
        treatment facilities in Virginia.

     o  Value of water supply.  For reasons discussed later
        in this paper, the Panel feels it inappropriate to
        include in the cost comparison a value for water
        supply augmentation as was done in the Response
        comparison.

     After careful review of the issues involved in deriving
cost comparisons, the Panel believes that the costs as shown
in Table III more accurately reflect the appropriate costs
which should be included in a cost-effectiveness comparison.

Public Health Considerations

     The proposed 60 mgd AWT facility at Dickerson calls
for wastewater effluent discharge 20 miles above the Washington,
D.C. drinking water intakes and 8 miles above the proposed
drinking water intake for Leesburg, Virginia.  Because.small
quantities of organic contaminants, trace metals and viruses
could be found in the effluent, concern about possible
public health risks is an important issue..

     In the grant application and related documents both
Montgomery County and Maryland have said that the proposed
facility is designed to avoid any undue public health risk.
They point to the breakpoint chlorination and charcoal
filtering processes included in the proposal as insurance
that the effluent would pose no risk to public health.

     In making its assessment of the factors relating to
public health, the Panel requested the EPA Office of Water
Supply and the EPA Municipal Environmental Research Laboratory
to evaluate the effects of the proposed discharge on the
quality of downstream drinking water supplies.  In- response,
the Office of Water Supply acknowledged that there is a
possibility that contaminants would not be removed so completely
as to eliminate all potential risk to health.  In addition,
it indicated that experience with AWT facilities and health
data for the kinds of contaminants known to be in sewage are
not sufficiently extensive or precise to predict accurately
all the health effects which might result.

-------
                            -9-
     To minimize the risks posed by "upsets" in the treat-
ment process within the plant, clear water reservoirs  (i.e.,
after-treatment storage lagoons) are incorporated in the
facility design.  The Office of Water Supply states that
from its perspective these reservoirs are necessary features
for the plant.

     The official responses from the Research Laboratory and
the Office of Water Supply concluded that from a drinking
water health standpoint the risks associated with the high
quality effluent discharge from Dickerson I or Dickerson II
would be minimal.  However, these responses also indicated
that, because of the many unknowns associated with the
situation, "the best alternative would be to discharge all
sewage below the water intakes."

     After reviewing all available evidence on this issue,
the Panel's assessment is that, though it would be preferable
to discharge below the metropolitan area's water intakes, the
health risks associated with the discharge from the proposed
project do not, by themselves, warrant rejection of the
proposed facility and denial of the grant application.

Cost of Delay

     In examining the total costs :— secondary as well as
first-order costs -- associated with the five alternative
treatment plants, it is important to consider whether
potential treatment plant construction delays will result in
loss of tax revenues.

     In the State Response the argument is advanced that if
the Dickerson treatment plant is not constructed in the near
future Montgomery County will incur substantial losses in tax
revenue because of a stifling of growth.  The Response
includes an estimate that continuance of a sewer moratorium
would reduce revenues by about $120 million.

     The Panel's review of the data presented in the State
Response suggests .that the cost of delay has been substan-
tially overstated for two reasons:  first, because interim
plants either under construction or planned for construction
are expected to ^eliminate any treatment capacity shortage;
and second; because, in any case, the Response does not
consider the costs associated with providing the services
which must accompany growth (e.g., schools and roads).  The
Response focuses solely on -the potential loss of tax revenues
which would be generated by expected growth in Montgomery
County.

-------
                             -10-
 Though there are many assumptions and uncertainties associated
 with this type of analysis, a Montgomery County study indicates
 that a slightly higher growth rate would place the county in
 a more favorable fiscal position. However, other studies of
 land development indicate that the type of growth generally
 experienced in suburban communities frequently creates more
 costs for the local government than it produces in tax
 revenues .jj

      The assessment indicates that if interim treatment plants
 are constructed as planned there will be no loss of.revenue.
 In the event they are not constructed on schedule the.potential
 net cost of delay would likely be very limited — certainly
. substantially less than the estimated $120 million.

 Land Opportunity Cost

      The Maryland Response contends that EPA has not
 considered that there would be an added land oportunity cost
 of $6 million associated with an expansion at Piscataway.2J
 While the concept of land opportunity cost is valid,  the
 Panel's review indicates that the calculations in the
 Response do not accurately reflect the situation.  The
 Response's estimate of the amount of land which must
 be secured at Dickerson does not include the 150 acres
 currently owned by PEPCO which would also be removed from
 the tax base.  But most important, the Response does not
 include the fact that development of land cannot occur
 without county investment in public services.  Hence, it is
 the Panel's view that when all appropriate factors are
 considered, the land opportunity cost differences between
 these two alternatives would be minimal.

 Water Supply Augmentation Value

      As the Washington metropolitan area's demands for water
 increase, greater withdrawals will be required from the
 Potomac River.  Because of projected water supply shortages,
 the potential value of recycling water in the river should
 be considered.

jj One such report on Fairfax County concluded that the
    development associated with an influx of population of
   • 23,000 to 24,000 would have a negative fiscal impact.
    This study calculated that for each new house the County
    would pay $38 more to provide services than it would
    receive in tax revenues.

 2j Land opportunity cost can be viewed as the value of the
    land if it were used for another purpose.  In this case
    it was assumed the land would be developed.

-------
                             -11-
      The  State  Response  estimated  a  water  supply augmenta-
 tion  value  of $19 million  (later  revised to  $14  million)  for
 the 60 mgd  facility  proposed  for  Dickerson.   This estimate
 was derived by  calculating  the  least cost  alternative  method
 of achieving equivalent  additional water supplies.

    •  The  Panel's assessment is  that  the value associated
 with  water  supply augmentation  is  much  smaller than  that
 estimated in the Response.   By  including Potomac River flows
 not considered  in the  Response, and  by maintaining the
 option, to use for water  supply  purposes  flows which  the
 Response  assumed would be by-passed  to  the estuary,  the
 Panel believes  that  water supply  deficits  would  not  likely
 occur during the planning horizon of the proposed facility.
 Based on  the above,  the  Panel concludes  that in  the  context
 of the Dickerson issue,  the water  supply augmentation  value
 would be  small,  certainly  far  less  than $14-19  million.

      At  the same time  it should be pointed out that  there
 are in fact several  unquantifiable benefits  to water supply
 augmentation.   Additional flows could provide aesthetic and
 fisheries benefits  in  the short term, and  in- the longer term
 (beyond  the 20  year  planning  horizon) could  help meet  the
 eventual  need for additional  water supplies.

'Water Quality

      Preliminary findings by both  the Applicant  and  EPA
 indicate  that the Dickerson facility as  proposed in  the
 grant application would  meet applicable water quality
 standards.   However, modifications to the  original proposal
 to reduce projected  plant costs would result in  the  dis-
 charge of nutrients  at levels greater than originally
 anticipated. Specifically, in  place of  the  pure oxygen
 activated sludge and .breakpoint chlorination for nitrogen
 removal  in  the  Dickerson I  configuration,  the modified
 facility  would  have  an air  activated sludge  nitrification
 system.   Total  nitrogen  concentrations expected  with this
 configuration would  be 19 mg/1  as  opposed  to the 3 mg/1
 concentrations  in the  original  proposal. Average phosphorus
 concentrations  are  expected to  increase  from 0.1 mg/1  for
 Dickerson I to  0.2 mg/1  for Dickerson II.

      Examination of  this change indicates  that the increase
 in nutrient discharge-from  Dickerson would tend  to aggravate
 a nutrient  problem  in  the upper reaches of the Potomac
 Estuary.  However,  the degree to  which  the situation
 would be  impacted is uncertain.   The EPA Annapolis field
 station has not yet  completed its  review of  these water
 quality  impacts.

-------
                           -12-
     The Panel's assessment suggests that Dickerson II would
be acceptable from a water quality standpoint, but additional
information is needed prior to reaching a final decision on
this issue.

Land Use Impacts

     Considerable apprehension has been expressed concerning
construction of the proposed Dickerson delivery line  (force
main) through the "green wedge" section of Montgomery
County.  It has been asserted by a number of groups that
such a sewer line would encourage development in the wedge
that would be .in conflict with the County's Wedges and
Corridors General Plan.lJ

     The County and State say that this is not a significant
concern in that there are adequate safeguards and procedures
to insure the integrity of the General- Plan, including:  .

     -  New planning requirements and approval procedures.

        Rezoning of 104,000 acres in the "green wedge" from  •
        2-acre to 5-acre minimum tracts.

        State and County control through development and
        revision" of the Ten Year Water and Sewerage Plan.

     -  Application of "the adequate public facilities
        ordinance" to prevent unwanted development.

     In addition, both the State and County feel that
lack of adequate treatment capacity results in distorted
growth patterns which are at least as environmentally
undesirable as possible development in the "wedge" areas.

     The Panel's assessment indicates that although there
are safeguards in place and current county officials seem
dedicated to resisting unwarranted developmental pressures,
construction of such a sewer line clearly holds the potential
for future large scale development in conflict with the
County's General Plan.  However, the Panel believes that the
decision with respect to the proposed Dickerson plant should
not be based primarily on this concern as it is essentially
a local land use issue.
   A plan approved by Montgomery County in 1969 which lays
   out the desired major physical developmental plan for the
   county.

-------
                           -13-


ALTERNATIVE COURSES OF ACTION

     The specific decision confronting the Agency at this
time is to determine the disposition of the grant application
submitted March 19, 1976 for construction of a 60 mgd  '
advanced wastewater treatment plant at Dickerson, Maryland.
A positive decision calls for "continuing the processing of"
the grant application, while a negative decision would
terminate further consideration of the grant application.

    .The Panel's assessment of the issues related to this
specific decision suggest the following considerations argue
in favor of proceeding with the grant application process:

        Construction of Dickerson I could be initiated in the
        immediate future.  Other alternatives would require
        further delay, hence, inflation might largely offset
        any anticipated savings associated with these solutions

        The population and flow projections submitted by the
        State indicate a need for a 60 mgd facility.  Uncer-
        tainty with respect to area growth-forecasts may make
        these estimates as valid as any others.

        The Dickerson site has been selected after a long
        review process.  Presumably it represents the most
        "acceptable alternative to area residents.

        Dickerson I has the potential of meeting both
        Montgomery County needs and regional requirements.

     On the other hand, the considerations listed below
argue that it would not be advisable to proceed further with
the grant application process:

     -  The.Panel's analysis indicates that Montgomery
        County's additional treatment requirements (35 mgd
        capacity) do not support a plant of 60 mgd.

     -  The Panel's cost-effectiveness analysis indicates
        that there are at least two substantially more
        cost-effective alternatives to the treatment plant
        proposed in the grant .application.

        The absence of firm agreements among the local
        jurisdictions on the treating of regional flows at
        Dickerson precludes approval of the proposed treat-
        ment plant as a regional facility.

-------
                           -14-
     If the decision is made to terminate further considera-
tion of the March 19th grant application, it may be approp-
riate, because of the complex nature of this issue and in
the interest of time, to provide "guidance" to Montgomery
County, Maryland, the District of Columbia, and  Virginia as
to. how they might want to proceed to meet the metropolitan
area sewage treatment needs.  Should you "desire to do this,
selection of one of the options presented below could
provide the basis for structuring that "guidance."

     Considering only Montgomery County flows, the Panel
estimates a projected unsatisfied treatment capacity need of
35 mgd in the year 2000.  Thus, you might want to consider
at least the following thr.ee alternative solutions:

     Alternative 1;  Dickerson II - 35 MGD
                                       >
          This alternative is generally acceptable from
          both a water quality and water supply point of
          view, but it is less cost-effective than the other
          two alternatives.  It would supply all of Montgomery
          County's additional capacity needs until about the
          year 2000.  This alternative would probably be
          more acceptable politically than Alternative 2.

     Alternative 2;  Piscataway - 35 MGD

          This alternative is more cost-effective than
          Alternative 1 ($74 million less costly).  It would
          also satisfy Montgomery County's sewage treatment
          needs until 2000.  However, it is likely that there
          would be substantially more political opposition to
          it than to Alternative 1.

     Alternative 3;  Intermediate - range solution

          Montgomery County is currently carrying out a
          program to construct small (1-5 mgd} sewage
          treatment plants which could (according to the
          Panel's flow projections) provide treatment
          capacity until a long range solution is found.
          The County either has under construction or has
          made commitments to construct 7 1/2 mgd of treatment
          capacity and has plans proceed toward construction
          of 7 mgd of additional capacity if permanent
          treatment is not forthcoming in the near future.
          This combined total of 14 1/2 mgd of capacity would
          meet Montgomery County's needs until approximately

-------
                           -15-
          1988 and would permit enough time to develop a long
          term regional solution to the sewage problem.  The
          impacts on water quality and drinking water appear
          acceptable, but the acceptability from a political
          standpoint is unclear.

     Though the present lack of firm commitments for the
treatment of regional flows at the proposed Dickerson  '
site preclude approving it as a 60 mgd regional plant, you
may want to address the regional issue in your "guidance"
statement.  The following information should be considered
with respect to that issue:

     o  Dickerson II at 60 MGD

        This option is estimated to be substantially more
        costly than a Piscataway alternative (by about $100
        million).  More precise cost comparisons cannot be
        made until the Virginia counties, which would be part
        of a Dickerson agreement are identified and the
        flows from both Virginia and the District which
        would be conveyed to such a regional treatment
        facility are specified.

     o  Piscataway Expansion of 60 MGD

        As an example of a less costly regional solution this
        approach would cost about $100 million less than the
        Dickerson approach.  However, there would likely be
        substantial political problems associated with
        it.

     The Panel members believe there are other longer term
regional alternatives — such as expansion of existing
treatment plants (e.g., the Blue Plains plant)  or the con-
struction of facilities at other sites — which probably
warrant further detailed examination.

RECOMMENDATION

     The Panel members, at this time, are not recommending a
specific course of action.  Following the August llth meeting,
after having had the opportunity to obtain additional informa-
tion and to hear additional points of views, the Panel
members will make their recommendation.

-------
         ASSUMPTIONS v MONTGOMERY COUNTY. FLOW PROJECTIONS
 1.  Use 1975 Base Population Sewered of 515,700 based on WSSC No. 2
     Projections, as submitted by WSSC to EPA in letter of 2/13/76.

 2.  Assume 40.1 ingd 1975 base domestic flow, and 77.8 gpd per capita
     flow in 1975, both from WSSC letter to EPA, 2/13/76.
10
11.
     Use 1975 Base Total Flow of 70
     12.7 mgd commerical/industrial
     infiltration/inflow.
                                0 mgd,  including 40
                                flow,  and 17.2 mgd.
1 domestic flow,
due to
     Assume domestic per capita flow remains constant in future years at
     77.8 gpcd due to water saving devices, price increases, and County
     policy (e.g., WSSC requirement that new housing and other construction
     utilize 3.5 gallon flush toilet, compared to previous standard
     5 or 6 gallon models).

     Assume construction of new dwelling units at 6,000 units/year from
     1975 on,  based partially on-the Montgomery County Planning Board's
     projected intermediate growth rates.

     Assume 5% on new residential growth will occur outside sewer service
     area (in  accordance with General Plan).

     Assume household size  will gradually decrease, as reported by the
     Planning  Board:

                                       People/Dwelling Unit
                                       3
                                       2
                                       2
                                       2
                                       2
                                       2
                                     04
                                     92
                                     78
                                     70
                                     64
                                     59
 As'sume  that  50  gpcd of the  77.8  gpd per  capita  flow  is  attributable
 to  personal  use.

 Assume  that  8,000  new  jobs  per year from 1975 on,  with  a  52.3  gpd
 per employee flow.

 Assume  trfat  infiltration/inflow  in  1975  represented  24.6%  of the  total
 flow and  that this  will  be  reduced  1%  every  five years  until 1995
 whereafter it will  remain constant.

 A wet weather flow  allowance  (7  percent)  is  not included  in  the pro-
 jections, primarily because the  proposed wastewater  treatment
-'facilities are  designed  to  accomodate  peak flows and infiltration  and
 inflow  resulting  from  wet weather conditions.

-------
                           APPENDIX B
               Monetary Cost Comparison- Dickerson &
      Piscataway Wastewater Treatment System Alternatives


Intorduction

     This appendix compares direct monetary costs of wastewater
treatment options at the proposed Dickerson site in Western •
Montgomery County with costs of comparable options at a site in
Prince Georges County about 20 miles below the Blue Plains waste-
water treatment plant (see map).  The analyses are based largely
on EPA review and appropriate adjustments and revisions of infor-
mation and evaluations developed by the State of Maryland and by
CH2M Hill, Inc., Consulting Engineers.  These latter evaluations
are presented, respectively, in the Maryland Response of May 1976,
a supplement to the Dickerson Project Development Report-- Con-
sideration of Alternate Treatment Processes --and a number of mem-
oranda and discussions after the documents were submitted*

     First, this appendix compares initial capital costs of
design and construction of the Dickerson 60 MGD system, including
the Nitrogen removal plant under the pending Step 3 grant
application, with costs of a 60 MGD Dickerson II system featuring
a Nitrogen oxidation plant, and with costs of a 60 MGD Piscat-
away. plant.  'Then, present worths^of the 60 MGD Dickerson II
wastewater treatment system are compared.with those for-the  •
Piscataway system.  Finally,:^ this appendix "compares-. 35':MGD
options at the proposed Dickerson and Piscataway sites.


Wastewater Flows

     The year 2000 wastewater flow (over existing flow) forecast
for Montgomery County totals about 35 MGD.  Thus, the two 35
MGD treatment options would serve only Montgomery County needs.
Currently, Maryland is negotiating with Virginia and with Wash-
ington, D.C. for 10 MGD and. 7.5 MGD allowances in the proposed
wastewater treatment alternatives.  Montgomery County could
provide for these allowances through corresponding reduction in
its current 76.6 MGD allocation in Blue Plains and treating
the resultant additional Montgomery County flows at either
Dickerson or Piscateaway,  Although the inter-jurisdictional
aggreements required for a Step 3 grant award have not been
reached to date, the 60 MGD alternatives have
nevertheless been assumed to provide for 17.5 MGD of regional
flows plus a Montgomery County allowance greater that the year
2000 need of 35 MGD.

-------
Wastewater Treatment System Alternatives

     The Dickerson alternatives I and II  (60 and 35 MGD) each feature a
treatment plant, a 23-mile force main and 5 pumping stations with some
lifts approaching 300 feet.  Ihe plant effluent line would discharge
into the Potomac River about 18 miles upstream from the most upstream
water supply intake for D.C.  The Dickerson I system includes an advanced.
wastewater treatment plant  (the pending Step 3 grant application) pro-
viding for Nitrogen as well as Phosphorous removal..  The plant features:

     1.  Prdjnary treatment
     2.  Secondary treatment
     3.  Lime treatment for Phosphorous removal
     4.  Recarbonation treatment
     5.  Filtration
     6.  Breakpoint Chlorination for Nitrogen Removal
     7.  Carbon treatment
     8.  Clearwater Reservoir
     9.  Hypochlorite Generation
    10.  Clearwater Reservoir
    11.  Railyard
    12.  Sludge processing facilities.

     The Dickerson 2 plant option provides for Phosphorous removal and
Nitrogen oxidation..  It departs from the above processes by modifying
the secondary treatment to provide for Nitrogen oxidation, substituting
post chlorination  (disinfection) for Breakpoint Chlorination and omitting
the Hypochlorite Generation facilities.

     The Piscataway alternatives (60 MGD and 35 MGD) would provide for
Nitrogen oxidation similar to Blue Plains.  They comprise:            i

     1.  Expansion of a proposed 30 MGD advanced wastewater treatment
plant to 90 MGD  (60 MGD option) and to 65 MGD  (35 MGD option).
                     *
     2..  60 MGD and 35 MGD enlargements of a proposed force main between
Blue Plains and Piscataway.

     3.  Construction of an additional 7 MGD of interim plant capacity
in Montgomery County to temporarily serve county needs between 1981
 (scheduled completion of Dickerson plant and 1984  (estimated completion
of Piscataway plant^.

     4.  Operation and maintenance of all interim plants  (14.5 MGD) for
three years  (1982 through 1984).

-------
     5.  Construction of certain relief sewers, pumping stations and
appurtenant works, not otherwise needed if the Dickerson plant were
built, to convey Montgomery County flows to the Potomac Interceptor.

     6.  Augmentation of effective Potomac Interceptor capacity by
construction of diurnal retention storage when present conveyance
capacity is reached.

Comparisons of Initial Capital Costs

     Table 1 compares initial capital costs of design and construction
for the 60 M3D Dickerson— I (Step 3 Grant application)  with the
Dickerson -I£ alternative.  It shows that the treatment plant changes
previously described would reduce capital posts by about $23 million in
1975 dollars.  The costs tabulated below are the same as those presented.
by Maryland and Montgomery County documents.

         Table 1 - Comparison of Initial (1976-^1 98!)
          Capital Costs of Dickerson I and Pick
                     II Systems (60MQ3)


Items                          Cost in Millions of March 1975 Dollars
                                                        Dickerson .S
1.  Plant                    •     166                       143*
2.  Force Main                     98                  '      98
3.  Ttotals                        264                       241

     *Includes added design cost of $3.2 mi, XT Inn

     Table 2 summarizes jLnitial capital costs for the exapnsion of the
proposed 30 MGD^pianc ^o^Q MGD and compares EPA and Maryland estimates
for this expansion.  The table shows the total capital costs   . '. to
be about $92 and 68 million less than those for Dickerson I and II,
respectively.

-------
       Table 2 -  Initial  (1978^384)  Capital Costs of
                  60 MGD Piscataway System
Items                      Cost in millions of March 1975 Dollars
                           EPA Estimate            Maryland Estimate

1.  Plant Capacity             98                       98
   . increase (30  to  90MGD)

2.  Added design  cost            5
                                                  «k

3.  Piscataway Force Main       27                       27

4.  Montgomery Co. Relief       29                       40
    Sewers

5.  Montgomery Co. Interim      13.                      24
    plants (7MGD)

6.  Dulles Relief Tunnel         -                       70

7.  Va. Interim AWT  & Con-       -                       27
    veyance

               Totals          172                      286

     The Item 1 cost of the 60 MGD increase in plant capacity is the
same as the Maryland estimate, although calculated independently using
a somewhat different approach.  Item 2 represents the estimated design
cost for Piscataway  above the $3.2 million estimate for design changes
for Dickerson II.  The Maryland cost estimate for the Piscataway Force
Main was adopted.

     The Maryland estimate for six relief sewers was accepted except for
one change.  The  proposed Seneca Tunnel was assumed to be replaced with
a force main, thus reducing the overall cost estimate from $40 million
to $29 million in 1975 dollars.

     Based on the Montgomery County flows presented in the main report,
less than 7 MGD rather than 14 MGD of additional, interim plant capacity
would be required to serve the county from 1981 (scheduled completion of
the Dickerson plant) to 1984 (estimated completion of the Piscataway
plant.  This assumed reduction of interim plant capacity (14 to 7 MGD)
decreased 1975 capital costs from $24 million to $13 million.

   .  The Maryland estimate included $69.7 million for a Dulles relief
tunnel.  This item has been deleted from the initial capital cost estimate
because the expected reduced flows are. not  likely to exceed  the
capacity  of the existing  Potomac River  (Dulles) interecptor
until beyond 1990 and, when needed, diurnal  retention  storage
is  likely to be a less costly means of  augmenting  the  flow
carrying  capability of the interceptor.   The present worth
estimates include cost of adding retention  storage beyond 1990.

-------
     Table 4 presents present worths of capital and operation and main-
tenance costs for the 60 and 35 MGD variations of the Dickerson II alter-
native.  Appropriate scaling factors (e.g. x = 0.8 for treatment plants
and x = 0.5 for force mains in the formula -  (C = KQT) were used to
reduce costs from the 60 MGD base to the 35 MGD (Montgomery Co. flows
only) option.,  The slope of cost curves of treatment plant flow versus
operation and maintenance costs were used in scaling down the 60 MGD
plant O&M costs to 35 MGD O&M costs.  The Maryland present worth estimates
were used for the 60 MGD Dickerson II alternative.

                Table 4 - Present Worth Costs
                of Dickerson II Alternatives
                             1980 p.w.  (minions of 1975 dollars)
Capital Costs                60MGD                        35MGD

Plant                         149                          100*
Force Main                     98                           75
Subtotals                     247                          175

O&M Costs
Plant                          69                           55
Force Main                     21                           12
Subtotals                      90                           67

Totals                        337                          242

*Includes $3 million of added design costs for plant resizing.

     Table 5 lists 1980 present worths of cpaital and operation and
maintenance costs for the 60 and 35 MOD variations of the Piscataway
system alternatives.  The 35 MGD estimates were derived in the same
manner as the Dickerson 35 MGD estimates.

-------
                Table 5 - Present Worth Costs
                 of Piscataway Alternatives


                              1980 p.w. (millions of 1975 dollars)
Capital Costs                 60 MGD35MGD

1.  Plant                       79                         51

    Added design cost            5                          5

    Force Main                  20                         15

    Interim Plants (Maryland)   10                  .       10

    Potomac Interceptor Retention

    Storage (1990-1995)      10-20    .                    5-10

    Montgomery Co. Relief    	20_                          12

            Subtotals          154                         103

O&M Costs

1.  Plant        .               52 .                         41

    Force Main                  12                           7

    Interim plants              16                          16

    Montgomery Co. Relief       _2_                          _1
    Sewers

          Subtotals             82                          65

          Totals               236                         168

     Table 6 summarizes and compares the present worths of the Dickerson
alternatives with the Piscataway alternatives.

-------
             Table 6 - Present Worth Comparison
          of Dickerson with Piscataway Alternatives
                           1980 p.w. in millions of March- 1975 dollars

60M3)

Dickerson I

Dickerson II

Piscataway

35MS)

Dickerson II                 175                67              242

Piscataway                   103                65              168

     The above table indicates the Piscataway alternatives to be about
30 percent less costly than the Dickerson II alternatives.  Also,
the 60 MGD Piscataway alternative is about 38 percent less costly than
Dickerson I.
Capital
273
247
154
O&M
108
90
82
Total
381
337
236

-------
                                                                                                          DETAIL
                                                                                                            EE PLATE
                                                                                      UPPER POTOMAC
                                                                                         INTERCEPTOR
                                                                POTOMAC INTERCEPTOR
                                                                                                                    BLUE PLAINS
                                                                                                                TREATMENT PLANT-
                                                                                                                (Under  Construction To
                                                                                                                     309 mgd}
        GRAVITY SEWER

  ->	-fORCE MAIN

33115.0)  PIPE DIAMETER AND CAPACITY

        SEWAGE PUMPING STATION, CAPACITIES:

                        92 mgd  (4) 20.4 mgd
A:  Uwtr
                                                                                                                  PISCATAWAY
                                                                                                              •TREATMENT PLANT
                                                                                                             (Under Construction  To
                                                                                                                  30 mgd)
                                                                          ©20.0 mgd  ©  6.0mgd

                                                                          (5) 2.7mgd  @  0.9mgd    '     '.';,
                                                                            (NOTE:Some Minor Station* Not Shown)

-------