PB98-963127
                               EPA541-R98-118
                               March 1999
EPA Superfund
      Explanation of Significant Difference
      for the Record of Decision:
      Beacon Heights Landfill
      Beacon Falls, CT
      9/9/1998

-------
                          DECLARATION

                                  FOR THE

EXPLANATION  OF SIGNIFICANT DIFFERENCES


SITE NAME AND LOCATION:

The Beacon Heights Landfill Superfund Site is located in the town of Beacon Falls, Connecticut.


STATEMENT OF PURPOSE:

This decision document sets forth the basis for the determination to issue the attached
Explanation of Significant Differences (BSD) for the Beacon Heights Landfill Superfund Site in
Beacon Falls, Connecticut.

STATUTORY BASIS FOR ISSUANCE OF ESD:

Section 1 17(c) of the Comprehensive Environmental Response Compensation and Liability Act
(CERCL A) requires that, if any remedial or enforcement action is taken under Section 1 06 of
CERCLA after adoption of a final remedial action plan, and if such action differs in any
significant respects from the final plan (i.e., scope, performance or cost), the United States
Environmental Protection Agency (EPA) shall publish an ESD and the reasons such changes
were made. Current EPA guidance (OSWER Directive 9355.3-02) further provides that issuance
of an ESD is appropriate where the  Agency determines the need for changes to the Record of
Decision (ROD) which are significant but which do not fundamentally alter the overall remedy.
In the present case, because the required adjustments to the ROD do not fundamentally alter the
selected remedy for the Site, this ESD is being issued properly.

In accordance with section 177(d) of CERCLA, this ESD will become part of the Administrative
Record which is available for public review at both  the EPA Region I Record Center in Boston,
Massachusetts and the Clerks Office in the Town Hall in Beacon Falls, Connecticut.

DECLARATION:

For the foregoing reasons, by my signature below, I approve the issuance of an Explanation of
Significant Differences for the Beacon Heights Landfill Superfund Site in Beacon Falls,
Connecticut, and the changes stated therein.
            Date                                 Patricia L. Meaney, Director
                                          Office of Site Remediation and Restoration

-------
EXPLANATION OF SIGNIFICANT DIFFERENCES

           BEACON HEIGHTS LANDFILL SUPERFUND SITE
                    BEACON FALLS, CONNECTICUT
I.     INTRODUCTION


A.    Site Name and Location

      Site Name:         Beacon Heights Landfill Superfund Site

      Site Location:      Town of Beacon Falls, Connecticut


B.    Lead and Support Agencies

      Lead Agency:      United States Environmental Protection Agency (EPA)

      Support Agency:    Connecticut Department of Environmental Protection (CTDEP)


C.    Legal Authority

      Under Section 117(c) of the Comprehensive Environmental Response, Compensation,
      and Liability Act (CERCLA), Section 300.43 5(c) of the National Contingency Plan
      (NCP) and EPA guidance (OSWER Directive 9355.3-02), if any remedial or enforcement
      action is taken under Section 106 of CERCLA after adoption of the Record of Decision
      (ROD), and if the United States Environmental Protection Agency (EPA) determines that
      differences in the remedial action significantly change but do not fundamentally alter the
      remedy selected in the ROD with respect to scope, performance, or cost, EPA shall
      publish an explanation of the significant differences between the remedial action being
      undertaken and the remedial action set forth in the ROD and shall include the reasons
      such changes were made.

D.    Summary of Circumstances Necessitating this Explanation of Significant
      Differences

      As a direct result of events that developed after the completion of the ROD and the
      Supplemental ROD, decisions were made to: change the selected location for leachate
      treatment, to modify the RCRA cap design, and to require that wetlands damaged during
      construction activities to be replicated on the Swan portion of the site.

-------
Beacon Heights Landfill Superfund Site                                           Page 2 of 12
Explanation of Significant Differences		     September 1998

E.    Availability of Documents

      In accordance with Section 117(d) of CERCLA, this Explanation of Significant
      Differences (BSD) will become part of the Administrative Record.  The ESD, supporting
      documentation for the ESD, and the administrative record are available to the public at
      the following locations and may be reviewed at the times listed:

         U.S. Environmental Protection Agency         Town of Beacon Falls
         Records Center                             Clerks Office
         90 Canal Street                             Town Hall
         Boston, MA 02114                         10 Maple Avenue
         Weekdays from 10:00 a.m. to 1:00 p.m.,        Beacon Falls, Connecticut
         and from 2:00 p.m. to 5:00 p.m.                Weekdays: 9:00 a.m. - 4:30 p.m.
         (617)573-5729                             (203)723-5244
II.     SUMMARY OF SITE HISTORY, ENFORCEMENT HISTORY AND SELECTED
       REMEDY
A.     Site History

       From the 1920's until 1970 a small portion of what is now known as the Beacon Heights
       Site was known as "Betkoski's Dump" and consisted of approximately 6 acres of active
       dumping and open burning in the northwestern corner of the existing Site. During this
       period of operation, there were general complaints and concerns, due to fumes, smoke,
       and blowing litter. The Site was not regulated by the State until 1970.

       In 1970 Beacon Heights, Incorporated (BHI) purchased the Site, which included the
       Betkoski Dump area. BHI and its owner, Harold Murtha, owned and operated the Site as
       Beacon Heights Landfill and expanded the landfill area to approximately 34 acres.  Soil
       available on the Site as a result of this expansion was used  as cover material for the
       landfill.  Wastes were placed directly onto bedrock and covered with soil, and waste
       materials were no longer burned.

       A landslide of soil and buried waste occurred on the northwestern side of the landfill in
       1972 due to both landfill operations and the changed surface and groundwater patterns
       from construction of an on-Site access road. This landslide created groundwater and
       leachate discharge points in the northern and northwestern  areas of the landfill.  Several
       of these discharge points still persist in the former landslide area.

       From 1973 until the Site closed in July 1979 specific areas or cells were used for the
       disposal of various waste materials rather than placing waste directly onto bedrock.
       Cover material was placed over all working areas.

       In 1977 the Connecticut Department of Environmental Protection (CTDEP) approved the
       spreading of wastewater sludge from the Naugatuck municipal/industrial wastewater

-------
Beacon Heights Landfill Superfund Site                                            Page 3 of  12
Explanation of Significant Differences	September 1998

      treatment facility over covered areas of the landfill. These activities continued until the
      summer of 1984.

B.    State Response History

      The State of Connecticut began regulating the Site in 1970. In 1972 and 1973 BHI was
      ordered by CTDEP to develop plans to prevent pollution from the landfill from entering
      the surrounding ground water. An engineering report was subsequently prepared for BHI
      that provided data and information for implementing corrective actions. As part of the
      study, borings were installed around the site for collection of subsurface data.

      CTDEP attempted to close the landfill and regulate industrial  liquids and chemicals
      disposed of at the landfill by issuing additional orders to BHI  in 1975 and 1976. These
      orders cited contamination of well water and Hockanum Brook tributaries as a result of
      landfill operations. BHI submitted a second engineering report describing an improved
      landfill operating plan but not including a groundwater monitoring plan.

      These activities culminated in a Consent Order between BHI and CTDEP to close the
      landfill facility by July 1,1979.  This Consent Order was signed on June 20, 1979 and
      entered as a final Order of the Connecticut Commissioner of Environmental Protection on
      July 24, 1979. BHI complied with the Order and the landfill was closed in July 1979.

      EPA sampled forty-four residential  wells along Skokorat and  Blackberry Hill Roads in
      August and September 1984. Samples were analyzed for Hazardous Substance List
      organic and inorganic parameters. Two wells located along Skokorat Road, identified as
      being contaminated, were resampled in November 1984 to verify the results. The
      analytical results of the samples from these two wells revealed benzene at concentrations
      ranging from 32 to 131 micrograms per liter (ug/1). Based on these analytical results,
      CTDEP provided bottled water to the residents as a temporary safe drinking water
      source. Other organic compounds detected in some of the other residential well samples
      were below levels that would indicate health risks. To provide more data on the nature of
      residential well contamination, 32 of the originally sampled residential wells were re-
      sampled in January 1985.  The results of this second round of sampling generally
      confirmed the results of the previous samples.  Benzene was detected in the same two
      wells at concentrations ranging from 42 to 89 ug/1. Low levels of other organic
      compounds (below Maximum Concentration Levels) were also identified in a limited
       number of wells.

C.     Federal Response History

       EPA conducted several preliminary study/sampling activities in 1981 and  1982 to
       evaluate Site conditions, to collect preliminary sample data, and to identify the potential
       for  immediate health risk resulting  from migration of contamination from the Site. The
       Site was listed on the EPA's National Priorities List on September 1,1983.  As a result of
       the  listing, the Site became regulated under the Comprehensive Environmental Response,
       Compensation, and Liability Act (CERCLA).

-------
Beacon Heights Landfill Superfund Site                                              Page 4 of  12
Explanation of Significant Differences	September 1998

       EPA performed a Remedial Investigation/Feasibility Study (RI/FS) at the Site from
       March  1984 through April 1985 to identify the nature and extent of contamination at the
       Site and to identify potential remedial alternatives. The RI/FS report was released to the
       public in April 1985.

       A more detailed description of the Site history leading up to the RI/FS, including a
       summary of the results of the RI, can be found in Section 1 of the RI/FS Report, which is
       part of the administrative record for the Site.

       Based on the results of the RI/FS, EPA issued a ROD on September 23, 1985,
       documenting the selected remedial actions for the Site. The remedy included:

          •   Excavation of Betkoski's dump and other contaminated soils and consolidation
              within the main landfill prior to its closure.1

          •   Installation of a RCRA cap over the consolidated wastes, including gas venting
              and stormwater management controls

          •   Installation of a perimeter leachate collection system.

          •   Extending a public water supply line along Skokorat Road and along Blackberry
              Hill Road to service current residences.

          •   Enclosing the Site with security fencing.

          •   Installing a more extensive groundwater monitoring system.

          •   Collecting leachate and transporting it to a licensed wastewater treatment facility
              or on-Site treatment followed by discharge to a tributary of the Hockanum Brook.

          •   Further studies and the preparation of a Supplemental ROD selecting the manner
              and location of leachate  treatment (on-Site or off-Site), the extent of excavation of
              contaminated soils, and the need for air pollution controls on the landfill gas
              vents.

       After the ROD was signed, EPA issued an Administrative Order in October 1986  in
       response to the discovery of contamination in some private residential wells and as a
       precaution against further leachate migration. The order required the Potentially
       Responsible Parties (PRPs) of the Beacon Heights Site to offer residences in the vicinity
       of the landfill the opportunity to become connected to the municipal water supply system.
       The owners of forty-nine residences opted to have their homes connected to the
       municipal water system.  The domestic water supply wells previously serving these
       l  Although the 1985-ROD and the Proposed Plan called for excavating Betkoski's dump, only a portion of
         the dump area was excavated. The remaining area was included under the cap. This revision to the ROD
         was further discussed in the Supplemental ROD, Section XV.

-------
Beacon Heights Landfill Superfund Site                                            Page 5 of 12
Explanation of Significant Differences                                           September 1998

      residences were then abandoned.  Six of the homeowners declined the offer and
      continued to use private wells to supply drinking water.

      On 14 September 1987, 32 PRPs, organized as the Beacon Heights Generators Coalition
      (BHGC), entered into a Consent Decree with the United States of America. The Decree
      required the PRPs to perform the remedial actions specified in the ROD, which included
      pre-design studies to gather additional information regarding the Site. Because Beacon
      Heights, Inc. (BHI) denied Site access to BHGC for these studies and other remedial
      activities, remedial investigation work was not performed until a court order, issued in
      October 1988, required BHI to provide access.

      In March 1990, the BHGC submitted a final draft of the Pre-Design Studies Report to
      EPA.  On May 9, 1990 EPA issued a Proposed Plan for remediation of the Site. Based on
      the RJ/FS, the Pre-Design Studies report, and public and State comments on the Proposed
      Plan, EPA issued the Supplemental ROD on September 28, 1990.

      The Supplemental ROD included an  evaluation of alternatives for treatment and disposal
      of the leachate collected from the Site.  These alternatives consisted of: treatment at the
      Beacon Falls Publicly Owned Treatment Works (POTW), treatment at the Naugatuck
      POTW, trucking the leachate off Site for treatment, and treatment on Site. The
      Supplemental ROD made the  following modifications to the ROD:

          •  Contaminated leachate generated by the landfill would be transported to and
             treated at the Naugatuck, Connecticut POTW.

          •  Soil cleanup standards were established for eight carcinogenic and nine non-
             carcinogenic contaminants of concern. Soils that contained contaminant
             concentrations in excess of these standards would be excavated from on-Site areas
             outside the landfill cap and placed  under the cap.

          •  Air pollution controls  would  not be required on the gas venting system. However,
             continued monitoring  of the vents would be required. The vents would be
             constructed so as to allow the addition of pollution control devices should the
             monitoring reveal levels of air contaminants exceeding the Federal National
             Ambient Air Quality Standards, State of Connecticut Air Standards, Odor
             Threshold Levels, or Hazard  Limiting Values  exceeding the 10"4 to 10'6 cancer
             risk range or exceeding a hazard index of one.

       During the fall of 1994, the owners of the  six residences who had previously declined the
       1986-1987 offer from the BHGC to connect to the public water supply were again
       contacted. The BHGC again asked if they would  like to be connected to the municipal
       water supply system. Four of the six residents again declined, while the remaining two
       residences accepted the offer and were connected  during October 1994.

-------
Beacon Heights Landfill Superfund Site                                             Page 6 of  12
Explanation of Significant Differences	September 1998
                                                                    /
D.     Delays, Violations and Penalties

       The completion of the remedial activities at the Site was delayed by more than 24
       months. The original construction schedule called for completion of the cap by 30
       September 1993. The cap was not determined to be substantially complete until
       December 1995. This delay was caused by many factors including:

              •   construction-related scheduling problems (permits, access, supplies, etc...);

              •   the replacement by the BHGC of the general contractor and the engineer;

              •   repairs to a major portion of the cap which had to be made due to questionable
                 installation techniques of the geomembrane;

              •   repairs to the cap anchor trench due to questionable construction;

  ,            •   reconstruction of runoff diversion benches due to questionable construction
                 techniques;

              •   the discovery and need to address new leachate seeps outside the leachate
                 collection system; and

              •   the discovery of additional wastes on site that had to be excavated and then
                 placed under completed portions of the cap.

       In addition, further construction activities were undertaken by the BHGC to reduce
       landfill leachate generation that extended construction activities at the site past the
       December 1995 date.

       Stipulated penalties in the amount of $600,000 were assessed to the Coalition by EPA in
       February 1997 for failure to complete the project in accordance with the approved
       construction schedule, and for violations related to topsoil placement, erosion control,
       and stormwater management.

       Numerous erosion events occurred at the site during the construction of the landfill due to
       rain falling on the uncompleted cap.  Portions of the landfill where soil had been placed
       over the impermeable cap were the most susceptible. These erosion events caused
       siltation in nearby wetlands, Hockanum Brook, and in some cases even the Naugatuck
       River,  several miles away. A total of 18 such events occurred. The cause of these
       releases can generally be attributed to under-sizing of stormwater retention basins and
       poor maintenance of those basins.

       As a result of erosion which occurred on-Site, wetlands both adjacent to the Site,
       principally on the Swan property, and other wetlands at some  distance from the Site were
       subjected to significant silt deposition. The BHGC was required to remove the
       sedimentation deposits prior to final completion of the project.

-------
Beacon Heights Landfill Superfund Site                                            Page 7 of 12
Explanation of Significant Differences	    September 1998

      The Swan property, located west of the Site, had on several occasions been affected by
      refuse being carried off the landfill.  The most significant incident was the result of a
      failure of the landfill slope  that occurred when the landfill was operated by Beacon
      Heights, Incorporated. A landslide of soil and buried waste occurred on the northwestern
      side of the landfill in 1972. This material occupied much of the "Florida area" on the
      Swan property and was subsequently removed and buried in the landfill as part of the
      remediation activities.  In addition, during a few of the larger erosion events, previously
      mentioned, which occurred while the landfill was being capped, some refuse was carried
      off the Site and onto the Swan property. This material was usually deposited in a wetland
      northwest of the Site.  The refuse material was removed and buried under the landfill cap
      during wetland construction activities that occurred on the Swan property.
E.     Summary of the Selected Remedy

       The selected remedy for the Site was described in the 1985 ROD and subsequently
       modified in the Supplemental ROD, issued in 1990.  The overall remedy consisted of:

          •   Excavation of satellite areas of contamination for consolidation within the main
              landfill prior to closure.

          •   Installation of a RCRA cap over the consolidated wastes, installation of gas
              venting, and implementation of stormwater management controls.

          •   Installation of a perimeter leachate collection system.

          •   Extension of a public water supply line along Skokorat Road and along
              Blackberry Hill Road to service current residences.

          •   Enclosing the Site with security fencing.

          •   Installation of a groundwater monitoring system.

          •   Transportation and subsequent treatment of contaminated leachate from the Site at
              the Naugatuck, Connecticut POTW (the Naugatuck facility).

          •   Excavation of  contaminated soils, located outside the main landfill, to levels
              specified within the Supplemental ROD and placement under the cap

          •   Construction of landfill cap gas vents such that they could be augmented with air
              pollution mitigating devices in the event that future air monitoring results require
              such action. In addition, post-construction air quality monitoring would be
              conducted on the Site at, but not limited to, the locations of each gas vent.

       With the exception of the items listed in Section III of this ESD, the requirements set forth
       in the ROD and Supplemental ROD  were fully met during the remediation of the site.

-------
Beacon Heights Landfill Superfund Site                                             Page 8 of 12
Explanation of Significant Differences                                            September 1998
III.    DESCRIPTION OF SIGNIFICANT DIFFERENCES

       As a direct result of events that developed after the completion of the ROD and the
       Supplemental ROD, decisions were made to change the selected location for leachate
       treatment, to modify the RCRA cap design, and to require the construction of
       compensatory wetlands. The changes made are discussed below.

       1.  Leachate Transportation and Treatment

          Although the Supplemental ROD had identified the Naugatuck facility as the location
          for leachate treatment, the leachate is currently being transported to the Beacon Falls
          Publicly Owned Treatment Works (POTW) for treatment for the reasons explained
          below.

          Originally, the 1990 Proposed Plan outlined several options for leachate
          transportation and subsequent treatment.  The two best options were transportation of
          contaminated leachate via a dedicated pipeline to the Naugatuck POTW for treatment,
          and transportation via a different pipeline to the Beacon Falls POTW for treatment.

          However, in 1989 - 1990  when the Town of Beacon Falls and the Beacon Heights
          Generators Coalition (BHGC) could not reach an agreement regarding the terms for
          transporting and treating contaminated leachate at the Beacon Falls facility, this
          option was eliminated as infeasible. The 1990 Supplemental ROD, therefore,
          required implementation of the Naugatuck option based upon strict evaluation criteria
          and the  unfeasibility of the Beacon Falls option.

          During  the development of the design of the leachate pipeline to the Naugatuck
          POTW  certain administrative and economic concerns related to the proposed route for
          the dedicated pipeline were identified. Some  of these concerns included: destruction
          of retaining walls, mailboxes, and trees within the right-of-way; removal and
          replacement of utility poles; removal and replacement of fire hydrants; construction
          of a 50- to 60-foot long elevated brook crossing; possible interruption of railroad
          traffic during construction and lack of a construction agreement with the railroad;
          and, the necessity for constructing a pipeline crossing the Naugatuck River.  These
          difficulties would have resulted in significantly greater costs, inconveniences to the
          general public, and project delays, as compared with implementation of the Beacon
          Falls option.

          In addition, the Beacon Falls pipeline would be considerably shorter (less than one
          mile) than the Naugatuck pipeline (approximately 5 miles). Accordingly, the Beacon
          Falls pipeline would have a lower propensity  for leaks, clogging, and other operation
          and maintenance problems. The community disruption caused by construction of the
          Beacon Falls pipeline was less than that resulting from construction of the much
           longer Naugatuck pipeline.

-------
Beacon Heights Landfill Superfund Site                                           Page 9 of 12
Explanation of Significant Differences	September 1998

          For these reasons, the BHGC re-opened negotiations with the Town of Beacon Falls
          in an attempt to reach an agreement to transport the contaminated leachate to the
          Beacon Falls POTW.  An agreement was eventually reached culminating with a
          contract between the BHGC and the Town of Beacon Falls on August 31, 1992 for
          the execution of the Beacon Falls option. The major terms of the agreement included
          permission by the Town of Beacon Falls for the BHGC to construct the Beacon Falls
          pipeline and to transport contaminated leachate from the Site to the Beacon Falls
          POTW for subsequent treatment. Also included in the agreement was the
          commitment by the BHGC to fund an appropriate upgrade of the Beacon Falls
          POTW.

          EPA, in consultation with the CTDEP , decided to adjust the overall cleanup plan for
          the Site so that contaminated leachate originating at the Site could be transported via
          the Beacon Falls pipeline to the Beacon Falls POTW for treatment and subsequent
          discharge to the Naugatuck River. The shorter Beacon Falls pipeline, the upgrade of
          the Beacon Falls POTW, and the shorter pipeline construction schedule that resulted
          in an earlier remedial action completion date were all benefits resulting from this
          change in the plan.

          The BHGC procured all necessary state and federal permits and licenses, and
          proceeded with construction of the upgrades necessary for the Beacon Falls POTW to
          provide long-term treatment of the contaminated leachate to the levels required by
          those permits. According to the Town's engineer , Fuss and O'Neill, the upgrades
          were substantially complete and the expanded facility operational in June 1995.

          In  the short-term and prior to completion of the upgrades, leachate collected at the
          Site was discharged to the Beacon Falls sewer system, treated at the POTW, and
          discharged to the Naugatuck River. Discharge of the leachate to the Beacon Falls
          POTW began on July 13, 1993.  According to the chief operator of the POTW, from
          the time leachate transportation to the Beacon Falls POTW began to the completion
          of the facility upgrades, the POTW remained in compliance with its National
          Pollutant Discharge Elimination System (NPDES) discharge permit requirements.
          CTDEP has reported to EPA that the POTW's NPDES permit limits have regularly
          been met since the time that the  leachate has been sent to the plant. A Final
          Pretreatment Permit was issued to the BHGC by the CTDEP on March 2, 1998,
          replacing the previous Emergency Discharge Authorization Permits the BHGC had
          obtained during the construction phase. Since the issuance of the final Pretreatment
          Permit, the BHGC has consistently met the terms of this permit.

          The adjustment  of the 1990 Supplemental ROD to allow treatment of the leachate at
          the Beacon Falls POTW resulted in a less expensive remedial action, created a less
          adverse impact on the environment and the general public, and met the cleanup
          objectives established in the 1990 Supplemental ROD. Approval of this adjustment
          by EPA did not  change any other requirements outlined in the 1985-ROD and the
          1990 Supplemental ROD. These requirements were expected to be adhered to in the
          time frames contained in the EPA approved construction schedule.

-------
Beacon Heights Landfill Superfund Site                                            Page 10 of 12
Explanation of Significant Differences                            	      	September 1998
       2.  Substitution of the RCRA Landfill Cap

          The ROD called for capping of the landfill with a RCRA cap. The cap was designed
          to prevent the infiltration of precipitation through the wastes, which would minimize
          the generation of leachate within the landfill. The RCRA cap was to consist of a two-
          component, low permeability cap comprised of a flexible synthetic membrane
          installed on an 18-inch thick low permeability soil layer. This soil layer was required
          to have permeability equal to or less than 1 x 10'7 cm/sec.

          The design of the cap, prepared by Bechtel Environmental Inc., included two different
          capping methods. At the top of the landfill, where the slopes were relatively flat, a
          40-mil high density polyethylene liner would be placed over a geosynthetic clay liner
          (GCL) consisting of a bentonite layer sandwiched between an upper and lower layer
          of geosynthetic fabric. On the 3.5:1 side slopes, the geocomposite liner would be
          replaced with 18-inches of low permeability soil. This soil would have a permeability
          of less than IxlO'5 cm/sec. The design was approved on this basis since EPA
          determined the replacement system was comparable in permeability to that originally
          required in the ROD. EPA accepted the PRPs' position that the higher permeability
          soil, IxlO'5 cm/sec, on the 3.5:1 side slopes would have a lower rate of rainfall
          infiltration due to the slope of the cap and, therefore, would be equivalent to a soil
          with 1x1O'7 cm/sec on the flat slopes at the top of the landfill.

          Acquisition of a source for the low permeability soil and the ability to transport the
          soil to the Site became an issue once the BHGC retained a contractor. Public
          inconvenience caused by approximately 6,500 truckloads of soil being delivered to
          the Site was also an issue. Consequently, BHGC proposed and EPA  accepted an
          alternate capping system that would replace the low permeability soil on the side
          slopes. The alternate system replaced the low-permeability soil, originally proposed,
          with a GCL. The  landfill cap as constructed consisted of the following major features:

                             •  Gas venting geotextile
                             •  GCL
                             •  Textured 40-mil HDPE geomembrane  and
                             •  Geonet composite.

          The GCL provided a barrier with a permeability of 5 x  10'10 cm/s, which is three and
          five orders of magnitude less permeable than the soil permeability requirements of the
          top and side slopes (respectively) specified in the ROD. It was also less expensive to
          install, it eliminated the high-volume of truck traffic associated with  the delivery of
          low-permeability soil to the Site, and it also accelerated the completion schedule by
          an estimated 60 days.

-------
Beacon Heights Landfill Superfund Site                                             Page 11 of 12
Explanation of Significant Differences	September 1998

       3.  Construction of Compensatory Wetlands

          Following extensive negotiations with an abutting property owner, Mr. Wilfred Swan,
          the BHGC purchased 46 acres of the Swan property, west of the Site. These 46 acres
          had been impacted by major erosion events during the time the landfill was actively
          operated and during the construction of cap. The property was also affected by a
          series of slope failures that had occurred prior to the capping of the landfill. During
          the construction of the cap and the leachate collection system, the Swan property was
          also used to store two equalization tanks that had been installed at the request of the
          State of Connecticut.  These tanks were intended to provide equalization of the
          characteristics and rate of flow of the leachate.  Several leachate overflows and spills
          were documented to have occurred from these tanks. These incidents (i.e., erosion
          events, slope failures, and leachate releases) resulted in the discharge of hazardous
          waste to the Swan property. The waste and the contaminated soils and sediments
          were removed and placed back within the landfill boundaries.

          As described above, the construction of the landfill cap and other facilities associated
          with the Site resulted in the disturbance of about 18 wetland areas on or adjacent to
          the Site.  These areas ranged in size from 500 square feet to nearly 2.5 acres.  In
          accordance with the Consent Decree (U.S. v. B.F. Goodrich Co.. et al. D. CT
          No.87-286)., 40 C.F.R. Part 230.10 (d) and Section 404 of the Clean Water Act,
          wetlands disturbed or destroyed by the installation of the remediation system are to be
          replaced in kind. A total of 4.9 acres were affected by activities associated with
          remediation of the Site. EPA required that 1.15 acres of compensatory wetlands be
          created for every one acre of wetland destroyed. Using that ratio, a total of 5.7 acres
          of wetlands were required to be created for the Site.

          Initially, an attempt was made to locate the compensatory  wetlands only on the
          original 82 acres that comprised the Site.  However, the areas that could be used for
          wetlands construction were limited due to the presence of the landfill cap and leachate
          collection system, topography, hydrology, soils, and the availability of surface water
          and groundwater. Ultimately, a suitable area for wetland creation was located on the
          Swan property. A 5.7 acre wetland was created in the area indicated at Figure 1.

          Because the Swan property had been contaminated by activities at the landfill before
          and during construction, and was an area in close proximity to the waste necessary for
          the response action, it was within the definition of "on-site" for purposes of Sections
          104, 106, 120,121, and 122 of CERCLA.  See  40 C.F.R. § 300.400(e). The site
          boundaries have been modified as a result of this determination,  and are defined in
          Figure 1: Beacon Heights Site Boundaries.

       The adjustments to the Supplemental ROD set forth herein will not fundamentally alter
       the overall remedy with respect to scope, performance,  or cost. These adjustments will
       not impact the other aspects of the original remedy.

-------
Beacon Heights Landfill Superfund Site                                          Page 12 of 12
Explanation of Significant Differences	September 1998

IV.   SUPPORT AGENCY COMMENTS

      State participation throughout the Remedial Action process has been extensive, and the
      State, through the Department of Environmental Protection (CTDEP), has provided
      comments on the matters addressed in this BSD. Those comments, which are
      summarized in a letter from CTDEP to EPA dated September 4, 1998, are included in the
      administrative record for this Site. In sum, the State supports the changes made to the
      leachate transport and compensatory wetland construction aspects of the remedy, but has
      concerns with changes to the cap design and has not concurred with the constructed cap.

V.    STATUTORY DETERMINATIONS

      EPA believes that the selected remedy set forth in the 1990 Supplemental ROD, with the
      adjustments described in Section III, remains protective of human health and the
      environment, complies with Federal and State requirements that are applicable or relevant
      and appropriate to this remedial action, and is cost-effective.  In addition, the revised
      remedy utilizes permanent solutions and alternative treatment technologies to the
      maximum extent practicable for this Site.
VI.    PUBLIC PARTICIPATION

       In accordance with Section 117(d) of CERCLA, the ESD and all supporting
       documentation that is included in the Administrative Record for the Site is available for
       public review at the locations and times listed above in Section 1 .D.

-------
Beacon Heights Coalition1
  BEACON HEIGHTS NPL SITE
 BEACON FALLS, CONNECTICUT
I  !  (  I  I  !
                                I  9  '•  I !  ?  I  ?
                                              :GK>SYNTBC CONSULTANTS.
    Figure 1: Beacon Heights Site as of September 1998

-------