United States
Environmental Protection
Agency
Office of Water Planning and Standards
Criteria and Standards Division
Washington, D.C.
Technology Transfer
           EPA-625 2-80-026
Capsule Report

Restoration of
Lake Temescal

                        • :


-------
Beach at Lake Temesc?

-------
Technology Transfer                       EPA-625/2-80-026
Capsule Report


Restoration of
Lake Temescal
July 1980
This report was developed by the
Center for Environmental Research Information,
Office of Research ai-d Development,
U.S. Environmental Protection Agency
Cincinnati, Ohio 45268

-------
 SAN  FRANCISCO
                 _P
Figure 1.
San Francisco Bay Area and Lake Temescal.

-------
I.   Introduction
The Clean Lakes Program was
initiated in 1975 to implement
section 314 of the Federal Water
Pollution Control Act Amend-
ments of 1972. Section 314
gives the States the responsibil-
ity for protecting and restoring
the quality of freshwater lakes.
The program provides funding
to assist the States in
classifying their lakes according
to water quality, identifying
methods to control pollution
sources affecting them,  and
restoring those which have
been  degraded. To qualify for a
Clean Lakes restoration  grant, a
lake must be open and acces-
sible to the public. Furthermore,
the proposed restoration project
must have the potential to yield
long-term public benefits and
not merely temporary or su-
perficial improvement.

This report discusses the res-
toration of Lake Temescal, a 4-
hectare (10-acre) man-made
lake which is the main attraction
of a regional recreation  area
within the city limits of Oakland,
Calif. (Figure 1). One of  the few
public beach and swimming
sites within the populous San
Francisco metropolitan area, it
is 4.8 kilometers (3 miles) from
downtown Oakland, and readily
accessible by public transit.

Lake Temescal began to deterio-
rate  rapidly during the  1970's.
Four separate water quality
problems were identified as
causing the deterioration. Bac-
terial contamination threatened
to prevent swimming al-
together.  High nutrient con-
centrations resulted in severe
blooms of algae. Water clarity
was reduced by algae and sus-
pended sediment,  resulting in
unattractive and sometimes haz-
ardous conditions for swim-
mers. Rapid accumulation of
sediment, eroded from dis-
turbed areas in the steeply-slop-
ing watershed, had reduced the
lake's depth by 75 percent. If
these conditions persisted, it
was apparent that public use of
Lake Temescal was going to be
sharply restricted within several
years and would eventually
cease completely.

Loss of this particular recrea-
tional resource was a matter of
serious concern because of its
great popularity. A peak day
during the 4-month swimming
season  brings as  many as 3,000
people to the lake's beach and
swimming area. In 1977, in spite
of the already obvious decline
in water quality, 750,000 user-
days were recorded for the rec-
reation  area, and  beach  use
alone exceeded 150,000.  With
so many people depending on it
for some part  of their recrea-
tion, Temescal's continuing
deterioration was going to have
a significant socioeconomic im-
pact. Consequently, the  East
Bay Regional Park District de-
cided to embark on a restora-
tion program.

Restoration of Lake Temescal
entailed a combination of in-
lake and watershed measures:
dredging to restore depth and
volume, detention and partial
diversion  of stream flows to re-
duce bacterial counts and sedi-
ment inputs, and  watershed
management to eliminate pollu-
tion sources. The in-!ake activi-
ties were  completed  in 1979.
Watershed management began
in the same year  and is still in
progress.

-------
2.   Problem
     Assessment
 Fiqure 2.
In 1976, 46 percent of the water
samples collected from Lake
Temescal violated the  California
total coliform bacteria  standard
for contact recreation.  Of addi-
tional samples collected in the
lake's watershed to identify the
nature and sources of  the
contamination, more than 85
percent exceeded both total and
fecal coliform standards. The
Alameda County Health Care
Services Agency concluded that
swimming in 1977 should be
permitted only on a month-to-
month basis, conditional on sat-
isfactory reports of
bacteriological quality.

The volume  of sediment carried
by the lake's two tributaries was
another factor which contrib-
uted to hazardous swimming
conditions. During 1975, for
example, water transparency as
measured by the depth at which
a Secchi disk could be seen
from the surface, ranged from
38 to 107 centimeters (15 to 42
inches). Turbidity was  always
worse along the bathing beach,
where accumulated  silt was
continually disturbed by swim-
mers. Recognizing that poor
visibility had contributed to
drownings in other U.S. lakes
by impeding supervision and
rescue, county health officials
recommended in early 1977 that
"if a major rehabilitation pro-
gram so as to provide a safe
               LAKE TEMESCAL SILTATION 1907-1977
swimming area is not to be ini-
tiated, other public uses of the
lake be developed which do not
include swimming."

Algal blooms were partly
responsible for the reduced
water clarity. Dominant species
included  blue-green algae which
are common in eutrophic lakes
and have often been implicated
in fish kills; the blooms oc-
curred because of high  phos-
phorus and nitrogen
concentrations.

Rapid accumulation of sediment
was Lake Temescal's most se-
rious problem, from the stand-
point of its long-term usefulness
as a recreational resource.
When developed in 1868, the
lake was  reported to have been
approximately 24 meters (80
feet) deep. Figure 2 illustrates
how its depth has changed. The
earliest bathymetric map, dated
1907, shows a maximum depth
of 11 meters (36 feet). In spite
of dredging  conducted in 1963
and 1968, the maximum depth
was a mere 5.5 meters (18 feet)
by 1973.  It has been estimated
that more than 71,000 cubic me-
ters (94,000  cubic yards) of sedi-
ment — 39 percent of the lake's
1963 volume — were deposited
between  1963 and  1973. This
was accompanied by formation
of deltas at the mouth of each
tributary. Sediment sources in-
cluded natural erosion in steep
terrain, erosion at highway and
residential construction sites,
streambank erosion resulting
from increased runoff, and ero-
sion of poorly designed and
managed road cuts and drain-
age systems.

Lake Temescal is a lake which
undergoes thermal stratification,
and summertime dissolved oxy-
gen concentrations approach

-------
Eroded Slope at
Construction Site
zero in the deepest layer
(hypolimnion). The oxygen
depletion  has two adverse ef-
fects on recreation: it prevents
the establishment of  some spe-
cies of fish and leads to produc-
tion of hydrogen sulfide gas at
the bottom of the lake. Bubbles
of H2S rising to the surface have
made swimming unpleasant
from time to time.

The 1976 watershed  bacteri-
ological survey detected several
points of sewer line overflow or
leakage and one malfunctioning
septic system, and steps were
taken to abate these  discharges.
However,  it was obvious that
this was only a partial solution;
surface runoff and storm sewer
discharges to the two tributar-
ies, Caldecott and Temescal
Creeks, were responsible for
much of Lake Temescal's
deterioration.

Caldecott Creek drains 256 hec-
tares (633 acres) of the lake's
769 hectare (1,900 acre) water-
shed (Figure 3). Freeway and
tunnel construction activities
there spanned several years in
the 1960's and were accom-
panied by severe erosion. For a
time, the creek  received acid
and detergent used to clean
Caldecott Tunnel, but this has
been diverted by agreement
with the California Department
of Transportation. However,
highway runoff containing bac-
teria, sediment, organic matter,
and other pollutants  is a major
component of Caldecott Creek's
discharge during storms.
Temescal Creek, with a water-
shed of 513 hectares (1,267
acres), drains existing and
developing residential areas,
many of which  are on slopes
exceeding 45 percent. It trans-
ports sediment, bacteria, and
nutrients into the lake.  It also
experienced the results of se-
vere erosion during highway
construction between 1971  and
1973.
                                  Figure 3.
                                     Lake
                                 Temescal
                               Watershed.

-------
3.   Development of
     Restoration and
     Management
     Alternatives
East Bay Regional Park District
applied for a Clean Lakes Dem-
onstration Grant in June 1976.
The proposed project, as it was
then defined, consisted of
dredging the deeper part of the
lake, forming a  dike with the
dredged  material to transform
the upstream third of the lake
into a large sediment trap for
Caldecott and Temescal Creeks,
and isolating the swimming
area with an impermeable bar-
rier and a circulation-filtration
system. An aeration system and
a bottom water withdrawal
structure were to be installed.
The objectives of these in-lake
measures were to eliminate
health hazards to swimmers;
alleviate  nuisance conditions
caused by algae, turbidity, and
hydrogen sulfide production in
the lake; and reduce the dif-
ficulty and cost of maintenance
dredging. The project's cost was
estimated at $609,450.

Other alternatives which had
been considered at this early
stage included dredging alone,
bypass of dry-season stream
flows to  control coliform bac-
teria, bypass of rainy-season
flows to  reduce sediment influx,
and taking no action. Dredging
alone would have had to be re-
peated regularly and offered
only dilution as a means of
reducing coliform counts and
nutrient concentrations. Each of
the bypass alternatives would
have alleviated only part of Lake
Temescal's problem, and either
would have made water level
and flow maintenance  difficult.
To take no action was clearly
unacceptable, since it was prob-
able that swimming would be
prohibited within 1 or 2 years,
and most other uses would be
lost in no more than 15 years.

EPA awarded the Clean Lakes
Demonstration Grant on March
31, 1977, and East Bay Regional
Park District initiated its water
quality monitoring program and
feasibility study. Several
modifictions to the project re-
sulted almost immediately.

An on-site study of bacterial
die-off rates showed that an
average of 98 percent of total
coliform and 93 percent of fecal
coliform in a given sample
would die during the course of
72 hours (Figure 4). This sug-
gested detention as a  more
cost-effective method  of control,
and the concept of isolating and
filtering swimming area water
was dropped from further
consideration. The proposed
desilting  basin could  be used to
effect the necessary detention.

The East  Bay Regional Park Dis-
trict had realized since the
beginning of the project that the
feasibility of the in-lake desilting
basin could not be confirmed
without detailed geologic and
soils analyses. Three  borings,
extending as deep as 33 feet
into the lake bottom, were
made in November 1977. They
showed the lake bottom sedi-
ments to be very soft clays and
silts of low bearing capacity, un-
able to support the weight of
the dike as proposed  without
risking substantial settlement or
failure. A dike could be con-
structed at the intended location
in the lake, but the dredged ma-
terial would be unsuitable and
rocky fill would have to be im-
ported. The engineering geolo-
gists recommended that a  less
costly alternative be explored.

The District and its consultants
re-examined and eventually se-
lected the concept of diversion
of dry-weather flows from both
creeks for bacteria and nutrient
loading control, supplemented
by a detention structure on

-------
Temescal Creek to allow bac-
teria die-off and sediment set-
tling. Dredging remained in the
work plan. The aeration system
was deleted; high operating
costs and poor performance at
other shallow lakes in the
United States were the main
considerations in that decision.
The bottom withdrawl structure
was also eliminated when it
was determined that if water
level was to be maintained, the
limited inflow during summer
months would not allow
enough water to be released
from the hypolimnion to signifi-
cantly improve the water
quality.
The project was amended in
June of 1979 to include a major
watershed management compo-
nent. Designated the "Lake
Temescal Pollution Identification
and Source Control  Program,"  it
was designed to provide data
which could be used in develop-
ing and implementing ap-
proaches to reduce the
generation  of pollutants in the
drainage basin. If successful, it
would  help protect the invest-
ment made in  in-lake restora-
tion measures by slowing the
rate of future deterioration.
                                                     Figure 4.
   500

   300
    100


     50
   i
   i
     30
     10

      5

      3
                         24               48
                       DETENTION TIME IHoirsl
                           72

-------
4.   Implementation
                      Dredged
              Material Disposal.
                Caldecott Creek
                     Diversion.
 Temescal Creek Weir
 and Detention  Pond.
                                 Figure 5 shows the structural
                                 portion of the restoration
                                 project as it was implemented.
                                 The construction phase began
                                 early in 1979 and was com-
                                 pleted in time for the swimming
                                 area to be reopened  to the pub-
                                 lic on July 4.

                                 Using a 100-ton crane and
                                 clamshell or dragline, 36,000 cu-
                                 bic meters (47,200 cubic yards)
                                 of sediment were removed from
                                 the lake. The spoil was loaded
                                 directly into end-dump trailers
                                 for hauling to another park be-
                                 ing developed by the District. At
                                 the disposal site, the material
                                 was dumped in an area sur-
                                 rounded by grassed  berms to
                                 dry for eventual use  as fill.
A pond with an earth dam pro-
tected  by a concrete apron was
built at the mouth of Caldecott
Creek,  and a pump station was
constructed to direct all dry-sea-
son flows  to a discharge point
downstream of the lake's outlet.
A detention pond with a weir
and removable flashboards was
constructed at the mouth of
Temescal Creek.  The Temescal
pond was  sized to provide 72-
hour detention for the mean
summer creek-flow.

Smaller pumps were installed at
the Temescal Creek pump sta-
tion since  not all dry-weather
flows there are diverted.
Temescal runoff is detained to
allow time for bacterial die-off
and then released to the lake,
unless  the pond level becomes
too high or monitoring shows
that water quality has not im-
proved sufficiently.  Water which
cannot be  released  is used to ir-
rigate the adjacent  meadow or
pumped to the Caldecott Creek
detention pond and thence to
the discharge point downstream
of the lake. Both  pump stations
are provided with silt traps, and
all equipment is underground
(Figure 6).

During the rainy  season, when
there is no swimming at Lake
Temescal, stream flow is not  di-
verted. The earth dam at the
mouth  of Caldecott Creek is
taken out,  allowing all flow to
enter the lake. Flashboards are
removed as necessary from the
Temescal Creek weir to allow

-------
Erosion and Sedimentation Controls.
storm flows to pass safely while
still being detained sufficiently
to undergo some desilting.

The source identification and
control program began early in
1979, as a cooperative effort by
the U.S. Geological Survey and
East Bay Regional Park District.
USGS installed gaging stations
and rain gages, provided sedi-
ment sampling and flow meas-
uring equipment, and
performed some laboratory
analyses. Automatic water sam-
plers were used at the mouths
of the two creeks, while sam-
ples were collected by hand
during storm events at the sta-
tions higher in the watershed. A
number of land developers co-
operated with the District by im-
plementing erosion controls.
This permitted comparisons of
the amounts of sediment being
transported  from controlled and
uncontrolled sites.

The District  has no direct regu-
latory authority over land devel-
opment in Lake Temescal's
watershed and must rely on  the
City of Oakland and Alameda
County to enforce best manage-
ment practices. Project per-
sonnel meet often with the
Assoua'..;:.:••  ?'   / .-.ica Hnv-
ernments and the Alamc
County Flood Control District,
both of which are involved in
areawide  water quality manage-
ment planning, to develop best
management practices in the
most usable form for the water-
shed. They  also work closely

-------
                   Figure 6.
               Pump Station.
Figure 5.

Detention and
Diversion System.
                             with the Oakland and Alameda
                             County planning agencies to
                             promote incorporation of man-
                             agement practices in City and
                             County ordinances.

                             The total cost of the Lake
                             Temescal Restoration Project
                             was $998,254. East Bay Re-
                             gional Park District provided
                             $244,486 of the funds to match
                             EPA's $315,618 grant. An addi-
                             tional $64,000 of matching
                             money was made available to
                             the District under the California
                             Urban and Coastal Park Act. The
                             remainder of the match was
                             taken from a special appropri-
         ation paid to the District via the
         State transportation fund. The
         appropriation, $359,150, was
         passed because freeway
         construction by the California
         Department of Transportation
         had been a major factor in the
         lake's rapid sedimentation and
         deterioration after 1960. The
         balance of the appropriation
         was used to cover increases in
         dredging costs, which had dou-
         bled since the application had
         been prepared. The U.S. Geo-
         logical Survey, under a coopera-
         tive agreement, contributed
         $15,000 toward the source iden-
         tification and control program.
                               SILT TRAP
TYPICAL PUMP STATION
                                                                 SCREENED INTAKE
                                                       CALDECOTT CREEK
                                                                  DIVERSION

                                          PUMP STATION
                                          IRRIGATION DIVERSION
                                                         PUMP
                                                       STATION
                                                            MESCAL CREEK
                                                         RETENTION  BASIN

-------
5.   Results and
     Benefits
The first and most obvious re-
sult of the restoration project is
that Lake Temescal was usable
for swimming in 1979. More-
over, the public evidently saw it
as more attractive as a swim-
ming site. Receipts from the
modest beach-use fees ($1.00
per adult, $.50 per child) in 1979
amounted to more than 90
percent of 1978 beach revenues,
in spite of the fact that the lake
was closed during the first 2
months of the season because
dredging and construction had
not been completed. This sug-
gests that  average daily use in-
creased by approximately 50
percent over 1978 usage rates, a
substantial public benefit.

One of the reasons for this re-
sult is that the beach was never
closed  in 1979. In the few years
prior to the project, the beach
had been closed an average of
four times per season because
of coliform standards violations.
Diversion of Caldecott Creek
flows eliminated coliform inputs
from that portion of the water-
shed. The Temescal Creek
detention pond proved quite
effective in reducing bacteria
counts, as the August  1979 data
in Table 1 demonstrate.
 Nutrient concentrations appear
 to have been little affected by
 the dredging, diversion, and
 detention pond. Blue-green al-
 gae decreased  somewhat in
 numbers in 1979 compared to
 1978, but algal  blooms contin-
 ued to occur, adversely affect-
 ing water clarity.

 Turbidity remained high until
 late September, when the lake
 destratified and clarity improved
 dramatically. Disturbance during
 dredging and construction was
 probably partially responsible
 for the turbidity. Sampling dur-
 ing 1980 should provide better
 data for use in  assessing the re-
 sults of the project from the
 standpoint of water clarity.

 It is, of course,  too soon to
 measure the impact of the
 project on sedimentation  rates
 in the lake. A good qualitative
 indication, though, is the large
 amount of material that has col-
 lected in  the Temescal Creek
 detention pond. After less than
 1 year, the pond already needs
 cleaning  (this can be easily
 done using a large back-hoe). In
the absence of the pond, this
 material would  have been
 deposited in the lake.
                                Table. 1.

                                Effectiveness of Temescal Creek Detection Pond, August 1979

                                                 Fecal Coliform Count (colonies/100 ml)
Date
8/1
8/7
8/16
8/21
8/29
Above Pond
1220
1476
520
2400
3933
Below Pond
160
313
297
43
263
Percent
Reduction
87
79
57
98
93

-------
Recreation on Lake Temescal.
                                  Although quite new, the source
                                  identification and control pro-
                                  gram has already yielded
                                  beneficial results. Using data
                                  from sub-basin sampling, flow
                                  measurements, and rainfall
                                  records, estimates of sediment
                                  production  by land use type
                                  were developed. Site specific
                                  sampling has provided data
                                  which can be usecJ to determine
                                  the effectiveness of various ero-
                                  sion control moas  -res which
                                  would be applicable ir  tV
                                  watershed. These results   ... _^
                                  used tooothor in r1- ^elopinr:
                                  TIC ..lei e'c<=i' •; r-   ' '••'     i _ • .
                                   o for iocai gc <-     •'• s
                                  onstrating the .;.  \-         ,  i .olb Ly a
                                         '  "•   "\<.l< ..    In some
                                                                             USGPO661-054  9/80

-------
    This report has been reviewed by the Clean Lakes Section, Criteria and
Standards Division, U.S. Environmental Protection Agency and approved for
publication. Mention of trade names or commercial products does not consti-
tute endorsement or recommendation for use.

    Single copies of this report are available from:

                Center for Environmental Research Information
                U.S. Environmental Protection Agency
                Cincinnati, Ohio    45268
    Thisrepu,  v;-s prepared for the U.S. r-ivrunmenT3' Pro' ?ciior>A> ••_
          'O.H   jrt fcvas. ir-.-j-.G"!, Pen,-;a. -'•iG='-g"?-jf-c *^ch':;:^> M.-irr
                     ,  . :e'o   ^   >\  tps;  3a-  f -i..  -r-\  '••,.-. ris.tr
       /,d. . ,crmation or reference material may be requested from:

            Denn.     ^  '^~'
              j-..   ,  I7:,/  \v  pur< r
            11500 Skyline Boulevard
            Oakland, Calif.     94619
            Clean Lakes Program
            Office of Water Planning and
                       -mental Protection Agency

-------